MAIN ROADS WESTERN AUSTRALIA DECEMBER 2018 Construction Update

NorthLink WA - Central Section to Ellenbrook

Great Northern Connect, a joint venture between BGC Contracting and Laing O’Rourke, is working in partnership with Main Roads to deliver the NorthLink WA central section. The $1.02b NorthLink WA initiative is jointly funded by the Australian ($821m) and Western Australian ($204m) governments.

We’re back into another summer, and we’re about 70 per cent Construction progress of the way through construction. Between now and mid-2019 you’ll • The new Marshall Road flyover opened to traffic in November. see new sections of the project open to traffic. • Works on all major interchanges are nearing completion, with Upcoming road network changes plans well underway for upcoming changes in road layouts. • The bridge beams for all 15 road bridges and WA’s first In coming months, you’ll notice some significant road network fauna bridge are installed with deck pours and finishing changes as we progress towards the opening of NorthLink WA works continuing. central section in mid-2019. • Three new pedestrian footbridges have been installed over In January the temporary roundabout at Tonkin/Reid Highway , and Gnangara Road, with intersection will be removed as new interchange ramps open to finishing works underway. create WA’s first free flowing freeway to freeway interchange. Further • Works have started on widening Reid Highway between ramps will open in March to complete the interchange. Next will be North and Altone Road. Tonkin Highway to Gnangara Road, followed by The Promenade. • Noise wall acrylic panels have now been installed along Driving conditions are constantly changing and you remain in an Ballajura, Beechboro and Bennett Springs. active construction site, so please pay careful attention and slow • Asphalting and pavement works are ongoing across the site down when moving through the area and obey the signs. and works on our principal shared paths and shared use paths We’ll soon be sending notifications to nearby residents, updating are taking shape. the website, posting in the NorthLink WA community group on Facebook and advertising important information which could affect your usual travel patterns. Sign up for news about road changes and road works directly to your inbox at [email protected].

Current expected schedule January 2019 Removal of temporary roundabout at Tonkin/Reid Highway intersection

March 2019 Tonkin/Reid Highway interchange complete

May 2019 Tonkin Highway to Gnangara Road complete

Mid-2019 Tonkin Highway Gnangara Road to the Painting works take shape at Hepburn Avenue interchange Promenade complete

Works progress on the bridge decks at the Hepburn Avenue Interchange The 151st bridge beam is lifted into position on Gnangara Road interchange in November bridges in Ballajura Upcoming works In coming months, there will be a lot of exciting activity as the central section works progressively open to traffic. Watch out for: • Opening of Tonkin/Reid Highway interchange ramps and associated removal of the temporary roundabout. • Bridge works at Gnangara Road, the Promenade, Hepburn Avenue, and Beechboro Road North. • Asphalting across the entire project length. • Safety barriers and wire rope barriers being installed. • Respread of mulch continuing along the alignment. • Painting of noise walls and bridge abutments continues. • Opening of the Beechboro Road North flyover across Reid Highway and associated removal of the temporary roundabout.

Works continue at the Tonkin/Reid Highway interchange, in readiness for upcoming traffic switches in early 2019 Landscaping reaches the halfway point Our landscaping team has been hard at work spreading mulch Works progress on the Beechboro Road North flyover across the site before spreading of seed and planting of tube stock takes place during the winter of 2019. The landscaping for this The site was on show for our local community project will involve more than two million seedlings and 750kg of In September, we took more than 250 people from our local seed, making it the largest ever landscaping requirements on a communities on a tour through the NorthLink WA central Main Roads WA project. section construction site. The six groups enjoyed a close look at the construction site and learnt about how NorthLink WA central section is being built. Many community members told us they enjoyed seeing parts of NorthLink WA that are not visible from the current road network.

Stockpiled mulch ready to be spread and barrier posts ready to be fitted with wire rope in Ellenbrook.

NorthLink WA central section construction site will shut down over the Christmas break from 5pm Friday 21 December to 7am Wednesday 2 January 2019. If you need contact us during that time, please phone 1800 874 998

A group of community members board the bus for the Northlink WA central section site tours in September WANT MORE INFORMATION? Vines resident David Karr, booked his ticket for the tour online. Join us on Facebook. Search NorthLink WA Community Group, He said the site tours were well planned and gave visitors a real or head to www.facebook.com/groups/NorthLinkWA. insight into the works happening onsite. “The tour gave me an appreciation of all the works happening For more construction related information about in tandem and the careful planning required to keep it all NorthLink WA central section, email [email protected] progressing towards completion,” David said. “You get a real or call 1800 874 998. sense of the job when you see it up close.”