Metro Program Management Master Schedule June 2019
Total Page:16
File Type:pdf, Size:1020Kb
j Metro Program Management Master Schedule June 2019 FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY Type Project Name 20182018 20192019 20202020 20212021 20222022 20232023 20242024 20252025 20262026 20272027 20282028 20292029 20302030 20312031 20322032 20332033 20342034 20352035 20362036 20372037 20382038 20392039 20402040 20412041 20422042 20432043 20442044 20452045 20462046 20472047 20482048 20492049 20502050 20512051 20522052 20532053 20542054 20552055 20562056 20572057 20582058 20592059 20602060 20612061 20622062 20632063 20642064 20652065 20662066 20672067 20682068 20692069 20702070 Transit Rail Crenshaw/LAX Transit Corridor Regional Connector Transit Corridor Westside Purple Line Extension Section 1 Westside Purple Line Extension Section 2 Westside Purple Line Extension Section 3 Gold Line Foothill Extension Phase 2B (Phase 1 & 2) West Santa Ana Transit Corridor LRT (Phase 1 & 2) East SF Valley Transit Corridor Project Green Line Extension to Crenshaw Blvd in Torrance Eastside Transit Corridor Phase 2 (Align 1 & 2) Sepulveda Phases 2 & 3 Crenshaw Northern Extension Green Line Eastern Extension (Norwalk) Orange Line Conversion to Light Rail Transit BRT Orange Line Grade Separations North Hollywood to Pasadena BRT North San Fernando Valley BRT Improvements Vermont Transit Corridor Lincoln BRT Corridor Transit Airport Metro Connector Facilities Link Union Station Highway I-5 Carmenita Road Interchange Congestion Relief I-5 North Capacity Enhancements SR-134-SR-118 I-5 South Capacity Enhancements I-605 to Orange County I-5 N Cap. Enhancements (SR-14 to Parker Rd) SR-71 Gap from I-10 to Rio Rancho Rd. SR-138 Corridor Improvement Project* SR-57/SR-60 Interchange Improvements I-710 South Corridor Project (Ph 1) I-710 South Corridor Project (Ph 2) I-5 Corridor Improvements (I-605 to I-710) I-405/I-110 Int. HOV Connect Ramps & Intrchng Improv I-605/I-10 Interchange SR 60/I-605 Interchange HOV Direct Connectors South Bay (I-405, I-110, I-105 and SR-91) I-605 Corridor "Hot Spot" Interchange Improvements Highway Sepulveda Phase 1 - Express Lanes Express Lanes I-105 Express Lane from I-405 to I-605 I-110 Express Lane Ext South to I-405/I-110 Interchange Other High Desert Corridor *Project Development TBD This document is a working draft meant for discussion purposes only and may contain preliminary conclusions not necessarily reflected in the final decision. Legend Environmental Engineerng Bid D/B Construction D/B/Construction Groundbreaking Date Right of Way Program Implementation P3 Construction Testing Forecasted Date GraphicSchedule.com.