DOCUMENT 00010

TABLE OF CONTENTS

INTRODUCTORY INFORMATION

Document 00001 Project Title Page 00010 Table of Contents

BIDDING REQUIREMENTS

Document 00220 Geotechnical Data

CONTRACTING REQUIREMENTS

Document 00500 Agreement Form (AIA A101 ) 00700 General Conditions (AIA A201)

SPECIFICATIONS

DIVISION 1 GENERAL REQUIREMENTS Section 01110 Summary 01250 Substitution Procedures 01260 Contract Modifications 01290 Payment procedure 01310 Project Management and Coordination 01320 Construction Process Documentation 01330 Submittal Procedures 01400 Quality Requirements 01420 References 01500 Temporary Facilities and Controls 01539 Temporary Tree and Plant Protection 01600 Product Requirement 01730 Execution 017419 Construction Waste Management and Disposal 01770 Closeout Procedures 017823 Operation and Maintenance Data 017839 Project Record Documents

DIVISION 2 SITE CONSTRUCTION Section 02020 Geotechnical Data 02080 Pipe Utilities 02221 Demolition 02230 Site Clearing 02750 Integral Colored Ground and Polished

See Civil and Landscape Drawings for civil and landscape specifications

DIVISION 3 CONCRETE 03100 Concrete

Whitfield Associates 00010 - 1 Table of Contents Laguna Beach Lifeguard Headquarters May 25, 2012

03200 Concrete Reinforcement 03300 Cast in Place Concrete 0336 Shotcrete 0311116 Concrete Form Liners

DIVISION 4 MASONRY Not Used

DIVISION 5 METALS Section 05120 Structural Steel 05410 Light Gage Metal Framing 05500 Metal Fabrications 055214 Aluminum Railing Systems

DIVISION 6 WOOD AND PLASTICS Section 06105 Miscellaneous Rough Carpentry 06200 Finish Carpentry 06400 Architectural Woodwork

DIVISION 7 THERMAL AND MOISTURE PROTECTION Section 07105 Slab-On-Grade Vapor Retarder 07170 Not Used 07210 Building Insulation 07265 Underlayments 07600 Flashing and Sheet Metal 07810 Spray-On-Fireproofing 07840 Firestopping 07900 Joint Sealers

DIVISION 8 DOORS AND WINDOWS Section 08220 Fiberglass Doors and Frames 08310 Access Doors and Panels 8450 All-Glass Entrances and Storefronts 084523 Fiberglass Skylight Systems 08700 Finish Hardware 8710 Door Hardware 08810 Glazing 08830 Mirrors

DIVISION 9 FINISHES Section 09220 Portland Plaster 09260 Gypsum Board Assemblies 09300 Tile 09510 Acoustical Ceilings 09775 Fiberglass Wall Panels 09815 Hi-Build Thermosetting Polyester Glazed Coatings 09815.1 Deleted 09841 Wall Acoustical Panels 09900 Paints and Coatings 09726 Tackable Wall Covering 099653 Elastomeric Coatings

Whitfield Associates 00010 - 2 Table of Contents Laguna Beach Lifeguard Headquarters May 25, 2012

099723 Concrete and Masonry Coatings

DIVISION 10 SPECIALTIES Section 10210 Wall Louvers 10426 Signage 10500 Lockers 10520 Fire Extinguisher Cabinets 10810 Toilet Accessories 102113 Solid Plastic Headrail Braced Toilet Partitions 102113.1 Not Used

DIVISION 11 EQUIPMENT Not Used

DIVISION 12 FURNISHINGS Not Used

DIVISION 13 SPECIAL CONSTRUCTION 13605 Design Build Solar PV System 13610 Design Build Solar Hot Water System

DIVISION 14 CONVEYING SYSTEMS 14240 Hydraulic Elevator

DIVISION 15 MECHANICAL 15000 Mechanical 15320 Fire Protection Sprinkler Systems 15400 Plumbing 15800 Heating Ventilation and Conditioning 15855 Registers, Diffusers and Grilles

DIVISION 16 ELECTRICAL 16100 Electrical 16511 Interior Lighting 16760 Communications

END OF DOCUMENT

Whitfield Associates 00010 - 3 Table of Contents Laguna Beach Lifeguard Headquarters May 25, 2012 SECTION 012500 - SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Requirements:

1. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

1.2 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1.3 ACTION SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Use CSI Form 13.1A . 2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable. b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate proposed substitution. c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified. d. Product Data, including drawings and descriptions of products and fabrication and installation procedures. e. Samples, where applicable or requested. f. Certificates and qualification data, where applicable or requested. g. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners. h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

WHITFIELD ASSOCIATES, INC. 012500 - 1 SUBSTITUTION PROCEDURES LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. i. Research reports evidencing compliance with building code in effect for Project, Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery. j. Cost information, including a proposal of change, if any, in the Contract Sum. k. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated. l. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Architect's and Construction Manager’s Action: If necessary, Architect and Construction Manager’s will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Architect will notify Contractor through Construction Manager of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work. b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.

1.4 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.

1. Conditions: Architect and Construction Manager will consider Contractor's request for substitution when the following conditions are satisfied:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results. b. Not Used. c. Requested substitution will not adversely affect Contractor's construction schedule.

WHITFIELD ASSOCIATES, INC. 012500 - 2 SUBSTITUTION PROCEDURES LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. d. Requested substitution has received necessary approvals of authorities having jurisdiction. e. Requested substitution is compatible with other portions of the Work. f. Requested substitution has been coordinated with other portions of the Work. g. Requested substitution provides specified warranty. h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Not allowed, unless otherwise indicated.

C. Substitutions for Convenience: Architect and Construction Manager will consider requests for substitution if received within 30 days after the Notice of Award.

1. Conditions: Architect and Construction Manager will consider Contractor's request for substitution when the following conditions are satisfied:

a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations. b. Requested substitution does not require extensive revisions to the Contract Documents. c. Requested substitution is consistent with the Contract Documents and will produce indicated results. d. Requested substitution provides sustainable design characteristics that specified product provided for achieving LEED prerequisites and credits. e. Requested substitution will not adversely affect Contractor's construction schedule. f. Requested substitution has received necessary approvals of authorities having jurisdiction. g. Requested substitution is compatible with other portions of the Work. h. Requested substitution has been coordinated with other portions of the Work. i. Requested substitution provides specified warranty. j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

PART 3 - EXECUTION (Not Used)

END OF SECTION 012500

WHITFIELD ASSOCIATES, INC. 012500 - 3 SUBSTITUTION PROCEDURES LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. SECTION 012600 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing Contract modifications.

1.2 MINOR CHANGES IN THE WORK

1. Architect will issue through Construction Manager, supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on “AIA Document G710, "Architect's Supplemental Instructions."

1.3 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Construction Manager, will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Work Change Proposal Requests issued by Construction Manager, are not instructions either to stop work in progress or to execute the proposed change. 2. Within time specified in Proposal Request or 20 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities. b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. c. Include costs of labor and supervision directly attributable to the change. d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time. e. Quotation Form: Use CSI Form 13.6D, "Proposal Worksheet Summary," and Form 13.6C, "Proposal Worksheet Detail

B. Contractor-Initiated Work Change Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Construction Manager within 5 days of discovery of changed conditions.

WHITFIELD ASSOCIATES, INC. 012600 - 1 CONTRACT MOD. PROCEDURES LAGUNA BEACH LIFEGUARD HEADQUARTERS May 25, 2012. 1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time. 2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities. 3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. 4. Include costs of labor and supervision directly attributable to the change. 5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time. 6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified. 7. Work Change Proposal Request Form: Use CSI Form 13.6A, "Change Order Request (Proposal)," with attachments CSI Form 13.6D, "Proposal Worksheet Summary," and Form 13.6C, "Proposal Worksheet Detail

1.4 ADMINISTRATIVE CHANGE ORDERS

A. Allowance Adjustment: See Section 012100 "Allowances" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs of allowances.

B. Unit-Price Adjustment: See Section 012200 "Unit Prices" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect measured scope of unit-price work.

1.5 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Work Changes Proposal Request, Construction Manager, will issue a Change Order for signatures of Owner and Contractor on AIA Document G701.

1.6 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: Construction Manager, may issue a Construction Change Directive on AIA Document G714. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.

WHITFIELD ASSOCIATES, INC. 012600 - 2 CONTRACT MOD. PROCEDURES LAGUNA BEACH LIFEGUARD HEADQUARTERS May 25, 2012. 1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012600

WHITFIELD ASSOCIATES, INC. 012600 - 3 CONTRACT MOD. PROCEDURES LAGUNA BEACH LIFEGUARD HEADQUARTERS May 25, 2012. SECTION 012900 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.

B. Related Requirements:

1. Section 012100 "Allowances" for procedural requirements governing the handling and processing of allowances. 2. Section 012200 "Unit Prices" for administrative requirements governing the use of unit prices. 3. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract. 4. Section 013200 "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule. 5. Section 018113.13 "Sustainable Design Requirements - LEED for New Construction and Major Renovations" for administrative requirements governing submittal of cost breakdown information required for LEED documentation. 6. Section 018113.16 "Sustainable Design Requirements - LEED for Commercial Interiors" for administrative requirements governing submittal of cost breakdown information required for LEED documentation. 7. Section 018113.19 "Sustainable Design Requirements - LEED for Core and Shell Development" for administrative requirements governing submittal of cost breakdown information required for LEED documentation. 8. Section 018113.23 "Sustainable Design Requirements - LEED for Schools" for administrative requirements governing submittal of cost breakdown information required for LEED documentation.

1.2 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule. Cost-loaded Critical Path Method Schedule may serve to satisfy requirements for the schedule of values.

1. Coordinate line items in the schedule of values with other required administrative forms and schedules, including the following:

a. Application for Payment forms with continuation sheets. b. Submittal schedule. c. Items required to be indicated as separate activities in Contractor's construction schedule.

WHITFIELD ASSOCIATES, INC. 012900 - 1 PAYMENT PROCEDURES LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 2. Submit the schedule of values to Architect through Construction Manager, at earliest possible date but no later than seven days before the date scheduled for submittal of initial Applications for Payment. 3. Subschedules for Phased Work: Where the Work is separated into phases requiring separately phased payments, provide subschedules showing values coordinated with each phase of payment.

B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the schedule of values:

a. Project name and location. b. Name of Architect. c. Architect's project number. d. Contractor's name and address. e. Date of submittal.

2. Arrange schedule of values consistent with format of AIA Document G703 Retain option in first subparagraph below where Contractor's ongoing activities related to Project closeout will be a line item subject to Application for Payment approval. 3. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with Project Manual table of contents. Provide multiple line items for principal subcontract amounts in excess of five percent of the Contract Sum. 4. Round amounts to nearest whole dollar; total shall equal the Contract Sum. 5. Provide a separate line item in the schedule of values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed. 6. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work. 7. Allowances: Provide a separate line item in the schedule of values for each allowance. Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities. 8. Each item in the schedule of values and Applications for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at Contractor's option.

9. Schedule Updating: Update and resubmit the schedule of values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.

1.3 APPLICATIONS FOR PAYMENT

A. Each Application for Payment shall be consistent with previous applications and payments as certified by Construction Manager, and paid for by Owner.

WHITFIELD ASSOCIATES, INC. 012900 - 2 PAYMENT PROCEDURES LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 1. Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements.

B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.

C. Payment Application Times: Submit Application for Payment to Architect by the 1st day of the month. The period covered by each Application for Payment is one month, ending on the last day of the month.

D. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 AIA Document G702/CMa and AIA Document G703 as form for Applications for Payment.

E. Application for Payment Forms: Use forms acceptable to Owner and Construction Manager: James Guerrero, Harris & Associates,] for Applications for Payment. Sample copies are included in Project Manual.

F. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Construction Manager: James Guerrero, Harris & Associates, will return incomplete applications without action.

1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made. 2. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

G. Transmittal: Submit three signed and notarized original copies of each Application for Payment to Construction Manager, by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

H. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from entities lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.

1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item. 2. When an application shows completion of an item, submit conditional final or full waivers. 3. Owner reserves the right to designate which entities involved in the Work must submit waivers. 4. Waiver Forms: Submit executed waivers of lien on forms acceptable to Owner.

I. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors. 2. Schedule of values.

WHITFIELD ASSOCIATES, INC. 012900 - 3 PAYMENT PROCEDURES LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 3. Submittal for project materials cost data. 4. Contractor's construction schedule (preliminary if not final). 5. LEED action plans. 6. Schedule of unit prices. 7. Submittal schedule (preliminary if not final). 8. List of Contractor's staff assignments. 9. List of Contractor's principal consultants. 10. Copies of building permits. 11. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work. 12. Initial progress report. 13. Report of preconstruction conference. 14. Certificates of insurance and insurance policies.

J. Application for Payment at Substantial Completion: After Architect issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum. 2. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work. 3. All Owner's manuals and warranties should be delivered upon request for substantial completion. 4. Commissioning of all building systems shall be complete upon substantial completion.

K. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements. 2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid. 3. Updated final statement, accounting for final changes to the Contract Sum. 4. AIA Document G706-1994, "Contractor's Affidavit of Payment of Debts and Claims." 5. AIA Document G706A-1994, "Contractor's Affidavit of Release of Liens." 6. AIA Document G707-1994, "Consent of Surety to Final Payment." 7. Evidence that claims have been settled. 8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work. 9. Final liquidated damages settlement statement.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012900

WHITFIELD ASSOCIATES, INC. 012900 - 4 PAYMENT PROCEDURES LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Coordination drawings. 2. Requests for Information (RFIs). 3. Project Web site. 4. Project meetings.

B. Related Requirements:

1. Section 011200 "Multiple Contract Summary" for a description of the division of work among separate contracts and responsibility for coordination activities not in this Section. 2. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

1.2 DEFINITIONS

A. RFI: Request from Owner, Construction Manager, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.

1.3 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Use CSI Form 1.5A. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products. 2. Number and title of related Specification Section(s) covered by subcontract. 3. Drawing number and detail references, as appropriate, covered by subcontract.

1.4 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

WHITFIELD ASSOCIATES, INC. 013100 - 1 PROJECT MGMNT AND COORDINATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation. 2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair. 3. Make adequate provisions to accommodate items scheduled for later installation.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule. 2. Preparation of the schedule of values. 3. Installation and removal of temporary facilities and controls. 4. Delivery and processing of submittals. 5. Progress meetings. 6. Preinstallation conferences. 7. Project closeout activities. 8. Startup and adjustment of systems.

1.5 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, where installation is not completely shown on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems. b. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

WHITFIELD ASSOCIATES, INC. 013100 - 2 PROJECT MGMNT AND COORDINATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. 2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. 3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment. 4. Structural Penetrations: Indicate penetrations and openings required for all disciplines. 5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items. 6. Review: Architect will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility.

1.6 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Construction Manager, will return RFIs submitted to Architect by other entities controlled by Contractor with no response. 2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name. 2. Project number. 3. Date. 4. Name of Contractor. 5. Name of Architect and Construction Manager. 6. RFI number, numbered sequentially. 7. RFI subject. 8. Specification Section number and title and related paragraphs, as appropriate. 9. Drawing number and detail references, as appropriate. 10. Field dimensions and conditions, as appropriate. 11. Contractor's suggested resolution. If Contractor's solution(s) impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI. 12. Contractor's signature. 13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

C. RFI Forms: AIA Document G716 Software-generated form with substantially the same content as indicated above, acceptable to Construction Manager.

WHITFIELD ASSOCIATES, INC. 013100 - 3 PROJECT MGMNT AND COORDINATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. D. Architect's and Construction Manager's Action: Architect and Construction Manager will review each RFI, determine action required, and respond. Allow seven working days for Architect's response for each RFI. RFIs received by Architect or Construction Manager after 1:00 p.m. will be considered as received the following working day.

1. The following RFIs will be returned without action:

a. Requests for approval of submittals. b. Requests for approval of substitutions. c. Requests for coordination information already indicated in the Contract Documents. d. Requests for adjustments in the Contract Time or the Contract Sum. e. Requests for interpretation of Architect's actions on submittals. f. Incomplete RFIs or inaccurately prepared RFIs.

2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt of additional information. 3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect and Construction Manager in writing within 10 days of receipt of the RFI response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly, every Friday at 12:00 pm. Use CSI Log Form 13.2B. or Software log with not less than the following:

1. Project name. 2. Name and address of Contractor. 3. Name and address of Architect and Construction Manager. 4. RFI number including RFIs that were dropped and not submitted. 5. RFI description. 6. Date the RFI was submitted. 7. Date Architect's and Construction Manager's response was received.

F. On receipt of Architect's and Construction Manager's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect and Construction Manager within seven days if Contractor disagrees with response.

1. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal Request, as appropriate. 2. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.

1.7 PROJECT WEB SITE

A. General contractor to provide On Site personnel qualified to efficiently use Primavera, Contract Manager Software.

WHITFIELD ASSOCIATES, INC. 013100 - 4 PROJECT MGMNT AND COORDINATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. B. NOT USED

C. NOT USED

D. NOT USED

E. NOT USED

1.8 PROJECT MEETINGS

A. General: Construction Manager will schedule and conduct meetings and conferences at Project site unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Architect of scheduled meeting dates and times. 2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees. 3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner, Construction Manager, and Architect, within three days of the meeting.

B. Preconstruction Conference: Construction Manager will schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner and Architect.

1. Attendees: Authorized representatives of Owner, Construction Manager, Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work. 2. Agenda: Discuss items of significance that could affect progress, including the following:

a. Tentative construction schedule. b. Phasing. c. Critical work sequencing and long-lead items. d. Designation of key personnel and their duties. e. Procedures for processing field decisions and Change Orders. f. Procedures for RFIs. g. Procedures for testing and inspecting. h. Procedures for processing Applications for Payment. i. Distribution of the Contract Documents. j. Submittal procedures. k. Not Used l. Preparation of record documents. m. Use of the premises. n. Work restrictions. o. Working hours. p. Owner's occupancy requirements. q. Responsibility for temporary facilities and controls. r. Procedures for moisture and mold control.

WHITFIELD ASSOCIATES, INC. 013100 - 5 PROJECT MGMNT AND COORDINATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. s. Procedures for disruptions and shutdowns. t. Construction waste management and recycling. u. Parking availability. v. Office, work, and storage areas. w. Equipment deliveries and priorities. x. First aid. y. Security. z. Progress cleaning.

3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Architect and Construction Manager of scheduled meeting dates. 2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents. b. Options. c. Related RFIs. d. Related Change Orders. e. Purchases. f. Deliveries. g. Submittals. h. Not Used i. Review of mockups. j. Possible conflicts. k. Compatibility problems. l. Time schedules. m. Weather limitations. n. Manufacturer's written instructions. o. Warranty requirements. p. Compatibility of materials. q. Acceptability of substrates. r. Temporary facilities and controls. s. Space and access limitations. t. Regulations of authorities having jurisdiction. u. Testing and inspecting requirements. v. Installation procedures. w. Coordination with other work. x. Required performance results. y. Protection of adjacent work. z. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

WHITFIELD ASSOCIATES, INC. 013100 - 6 PROJECT MGMNT AND COORDINATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information. 5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

D. Progress Meetings: Construction Manager will conduct progress meetings at biweekly intervals.

1. Attendees: In addition to representatives of Owner, Construction Manager,and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work. 2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present, including the following:

1) Interface requirements. 2) Sequence of operations. 3) Status of submittals. 4) Not Used 5) Deliveries. 6) Off-site fabrication. 7) Access. 8) Site utilization. 9) Temporary facilities and controls. 10) Progress cleaning. 11) Quality and work standards. 12) Status of correction of deficient items. 13) Field observations. 14) Status of RFIs. 15) Status of proposal requests. 16) Pending changes. 17) Status of Change Orders. 18) Pending claims and disputes. 19) Documentation of information for payment requests.

3. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.

WHITFIELD ASSOCIATES, INC. 013100 - 7 PROJECT MGMNT AND COORDINATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 013100

WHITFIELD ASSOCIATES, INC. 013100 - 8 PROJECT MGMNT AND COORDINATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor's construction schedule. 2. Construction schedule updating reports. 3. Daily construction reports. 4. Site condition reports.

B. Related Requirements:

1. Section 011200 "Multiple Contract Summary" for preparing a combined Contractor's construction schedule.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times. 2. Predecessor Activity: An activity that precedes another activity in the network. 3. Successor Activity: An activity that follows another activity in the network.

B. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

C. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

D. Float: The measure of leeway in starting and completing an activity.

1. Float time [belongs to Owner] [is not for the exclusive use or benefit of either Owner or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date].

1.3 INFORMATIONAL SUBMITTALS

A. Format for Submittals: Submit required submittals in the following format:

WHITFIELD ASSOCIATES, INC. 013200 - 1 CONSTR. PROGRESS DOCUMENTATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 1. Working electronic copy of schedule file, where indicated. 2. PDF electronic file. 3. Three paper copies.

B. Startup Network Diagram: Of size required to display entire network for entire construction period. Show logic ties for activities.

C. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.

1. Submit a working electronic copy of schedule, using software indicated, and labeled to comply with requirements for submittals. Include type of schedule (initial or updated) and date on label.

D. CPM Reports: Concurrent with CPM schedule, submit each of the following reports. Format for each activity in reports shall contain activity number, activity description, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known. 2. Logic Report: List of preceding and succeeding activities for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known. 3. Total Float Report: List of all activities sorted in ascending order of total float. 4. Earnings Report: Compilation of Contractor's total earnings from commencement of the Work until most recent Application for Payment.

E. Construction Schedule Updating Reports: Submit with Applications for Payment.

F. Daily Construction Reports: Submit at weekly intervals.

G. Site Condition Reports: Submit at time of discovery of differing conditions.

1.4 COORDINATION

A. Coordinate Contractor's construction schedule with the schedule of values, list of subcontracts, submittal schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from entities involved. 2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

WHITFIELD ASSOCIATES, INC. 013200 - 2 CONSTR. PROGRESS DOCUMENTATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. PART 2 - PRODUCTS

2.1 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

A. Time Frame: Extend schedule from date established for the Notice of Award to date of final completion.

1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

B. Activities: Treat each story or separate area as a separate numbered activity for each main element of the Work. Comply with the following:

1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Construction Manager. 2. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.

a. Contractor to provide procurement list to Construction Manager within 2 weeks of Notice of Award.

3. Submittal Review Time: Include review and resubmittal times indicated in Section 013300 "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's construction schedule with submittal schedule. 4. Startup and Testing Time: Include no fewer than 15 days for startup and testing. 5. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Architect's and Construction Manager's administrative procedures necessary for certification of Substantial Completion. 6. Punch List and Final Completion: Include not more than 30 days for completion of punch list items and final completion.

C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.

1. Phasing: Arrange list of activities on schedule by phase. 2. Work under More Than One Contract: Include a separate activity for each contract. 3. Work by Owner: Include a separate activity for each portion of the Work performed by Owner. 4. Work Restrictions: Show the effect of the following items on the schedule:

a. Coordination with existing construction. b. Limitations of continued occupancies. c. Uninterruptible services. d. Partial occupancy before Substantial Completion. e. Use of premises restrictions. f. Provisions for future construction. g. Seasonal variations. h. Environmental control.

WHITFIELD ASSOCIATES, INC. 013200 - 3 CONSTR. PROGRESS DOCUMENTATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 5. Work Stages: Indicate important stages of construction for each major portion of the Work. 6. Other Constraints:

D. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Completion of Structural Concrete, Substantial Completion, and final completion.

E. Upcoming Work Summary: Prepare summary report indicating activities scheduled to occur or commence prior to submittal of next schedule update. Summarize the following issues:

1. Unresolved issues. 2. Unanswered Requests for Information. 3. Rejected or unreturned submittals. 4. Notations on returned submittals. 5. Pending modifications affecting the Work and Contract Time.

F. Recovery Schedule: When periodic update indicates the Work is 5 or more calendar days behind the current approved schedule, submit a separate recovery schedule indicating means by which Contractor intends to regain compliance with the schedule.

G. Computer Scheduling Software: Prepare schedules using current version of a program that has been developed specifically to manage construction schedules.

1. Use Primavera operating system.

2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE (GANTT CHART)

A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal, Gantt-chart-type, Contractor's construction schedule within 30 days of date established for Notice of Award.

B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.

1. For construction activities that require three months or longer to complete, indicate an estimated completion percentage in 10 percent increments within time bar.

2.3 CONTRACTOR'S CONSTRUCTION SCHEDULE (CPM SCHEDULE)

A. General: Prepare network diagrams using AON (activity-on-node) format.

B. Startup Network Diagram: Submit diagram within 14 days of date established for the Notice of Award. Outline significant construction activities for the first 90 days of construction. Include skeleton diagram for the remainder of the Work and a cash requirement prediction based on indicated activities.

C. CPM Schedule: Prepare Contractor's construction schedule using a cost- and resource-loaded, time-scaled CPM network analysis diagram for the Work.

WHITFIELD ASSOCIATES, INC. 013200 - 4 CONSTR. PROGRESS DOCUMENTATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 1. Develop network diagram in sufficient time to submit CPM schedule so it can be accepted for use no later than 60 days after date established for the Notice of Award.

a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Architect's approval of the schedule.

2. Establish procedures for monitoring and updating CPM schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates. 3. Use "one workday" as the unit of time for individual activities. Indicate nonworking days and holidays incorporated into the schedule in order to coordinate with the Contract Time.

D. CPM Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the startup network diagram, prepare a skeleton network to identify probable critical paths.

1. Activities: Indicate the estimated time duration, sequence requirements, and relationship of each activity in relation to other activities. Include estimated time frames for the following activities:

a. Preparation and processing of submittals. b. Mobilization and demobilization. c. Purchase of materials. d. Delivery. e. Fabrication. f. Utility interruptions. g. Installation. h. Work by Owner that may affect or be affected by Contractor's activities. i. Testing. j. Punch list and final completion. k. Activities occurring following final completion.

2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates. 3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time. 4. Format: Mark the critical path. Locate the critical path near center of network; locate paths with most float near the edges.

a. Subnetworks on separate sheets are permissible for activities clearly off the critical path.

E. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using a network fragment to demonstrate the effect of the proposed change on the overall project schedule.

WHITFIELD ASSOCIATES, INC. 013200 - 5 CONSTR. PROGRESS DOCUMENTATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. F. Initial Issue of Schedule: Prepare initial network diagram from a sorted activity list indicating straight "early start-total float." Identify critical activities. Prepare tabulated reports showing the following:

1. Contractor or subcontractor and the Work or activity. 2. Description of activity. 3. Main events of activity. 4. Immediate preceding and succeeding activities. 5. Early and late start dates. 6. Early and late finish dates. 7. Activity duration in workdays. 8. Total float or slack time. 9. Average size of workforce. 10. Dollar value of activity (coordinated with the schedule of values).

G. Schedule Updating: Concurrent with making revisions to schedule, prepare tabulated reports showing the following:

1. Identification of activities that have changed. 2. Changes in early and late start dates. 3. Changes in early and late finish dates. 4. Changes in activity durations in workdays. 5. Changes in the critical path. 6. Changes in total float or slack time. 7. Changes in the Contract Time.

2.4 REPORTS

A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:

1. List of subcontractors at Project site. 2. List of separate contractors at Project site. 3. Approximate count of personnel at Project site. 4. Equipment at Project site. 5. Material deliveries. 6. High and low temperatures and general weather conditions, including presence of rain or snow. 7. Accidents. 8. Meetings and significant decisions. 9. Unusual events. 10. Stoppages, delays, shortages, and losses. 11. Meter readings and similar recordings. 12. Emergency procedures. 13. Orders and requests of authorities having jurisdiction. 14. Change Orders received and implemented. 15. Construction Change Directives received and implemented. 16. Services connected and disconnected. 17. Equipment or system tests and startups. 18. Partial completions and occupancies.

WHITFIELD ASSOCIATES, INC. 013200 - 6 CONSTR. PROGRESS DOCUMENTATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 19. Substantial Completions authorized.

B. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.

PART 3 - EXECUTION

3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule three days before each regularly scheduled progress meeting.

1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting. 2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations. 3. As the Work progresses, indicate final completion percentage for each activity.

B. Distribution: Distribute copies of approved schedule to Architect and Construction Manager, Owner, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.

1. Post copies in Project meeting rooms and temporary field offices. 2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.

END OF SECTION 013200

WHITFIELD ASSOCIATES, INC. 013200 - 7 CONSTR. PROGRESS DOCUMENTATION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.

B. Related Requirements:

1. Section 011000 "Summary" for work restrictions and limitations on utility interruptions.

1.2 USE CHARGES

A. General: Installation and removal of and use charges for temporary facilities shall be included in the Contract Sum unless otherwise indicated. Allow other entities to use temporary services and facilities without cost, including, but not limited to, Owner's construction forces, Architect, Construction Manager, testing agencies, and authorities having jurisdiction.

B. Water and Sewer Service from Existing System: Water from Owner's existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.

C. Electric Power Service from Existing System: Electric power from Owner's existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.

1.3 INFORMATIONAL SUBMITTALS

A. Site Plan: Show temporary facilities, utility hookups, staging areas, and parking areas for construction personnel.

B. Erosion- and Sedimentation-Control Plan: Show compliance with requirements of EPA Construction General Permit or authorities having jurisdiction, whichever is more stringent.

C. Fire-Safety Program: Show compliance with requirements of NFPA 241 and authorities having jurisdiction. Indicate Contractor personnel responsible for management of fire prevention program.

1.4 QUALITY ASSURANCE

A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.

WHITFIELD ASSOCIATES, INC. 015000 - 1 TEMP FACILITIES AND CONTROLS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.

C. Accessible Temporary Egress: Comply with applicable provisions in the U.S. Architectural & Transportation Barriers Compliance Board's ADA-ABA Accessibility Guidelines and ICC/ANSI A117.1.

1.5 PROJECT CONDITIONS

A. Temporary Use of Permanent Facilities: Engage Installer of each permanent service to assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Chain-Link Fencing: Minimum 2-inch (50-mm), 0.148-inch- (3.8-mm-) thick, galvanized-steel, chain-link fabric fencing; minimum 6 feet (1.8 m) high with galvanized-steel pipe posts; minimum 2-3/8-inch- (60-mm-) OD line posts and 2-7/8-inch- (73-mm-) OD corner and pull posts, with 1-5/8-inch- (42-mm-) OD top rails. Chain link fence shall have fabric barrier attached at the same height of the fence. Fabric shall be maintained and replaced by contractor when marked up, vandalized, torn or tattered. Chain link fence shall be suitable to withstand significant wind loads and may need to be post driven.

B. Portable Chain-Link Fencing: Minimum 2-inch (50-mm), 0.148-inch- (3.8-mm-) thick, galvanized-steel, chain-link fabric fencing; minimum 6 feet (1.8 m) high with galvanized-steel pipe posts; minimum 2-3/8-inch- (60-mm-) OD line posts and 2-7/8-inch- (73-mm-) OD corner and pull posts, with 1-5/8-inch- (42-mm-) OD top and bottom rails. Provide galvanized-steel bases for supporting posts. Chain link fence shall have fabric barrier attached at the same height of the fence. Fabric shall be maintained and replaced by contractor when marked up, vandalized, torn or tattered. Chain link fence shall be suitable to withstand significant wind loads and may need to be post driven.

C. Wood Enclosure Fence: Plywood, [6 feet (1.8 m)] [8 feet (2.4 m)] high, framed with four 2-by- 4-inch (50-by-100-mm) rails, with preservative-treated wood posts spaced not more than 8 feet (2.4 m) apart. Plywood shall be painted and maintained to be free of any markings or grafitti.

2.2 TEMPORARY FACILITIES

A. Field Offices, General: Prefabricated or mobile units with serviceable finishes, temperature controls, and foundations adequate for normal loading.

B. Common-Use Field Office: Of sufficient size to accommodate needs of Owner, Architect, Construction Manager. and construction personnel office activities and to

WHITFIELD ASSOCIATES, INC. 015000 - 2 TEMP FACILITIES AND CONTROLS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. accommodate Project meetings specified in other Division 01 Sections. Keep office clean and orderly.

C. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate materials and equipment for construction operations.

2.3 EQUIPMENT

A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures. 1. HVAC Equipment: N.A.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.

1. Locate facilities to limit site disturbance as specified in Section 011000 "Summary."

B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

3.2 TEMPORARY UTILITY INSTALLATION

A. General: Install temporary service or connect to existing service.

1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.

B. Sewers and Drainage: Provide temporary utilities to remove effluent lawfully.

1. Connect temporary sewers to municipal system as directed by authorities having jurisdiction.

C. Water Service: Install water service and distribution piping in sizes and pressures adequate for construction.

D. Water Service: Connect to Owner's existing water service facilities. Clean and maintain water service facilities in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use.

E. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.

WHITFIELD ASSOCIATES, INC. 015000 - 3 TEMP FACILITIES AND CONTROLS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 1. Toilets: Use of Owner's existing toilet facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use.

F. Heating and Cooling: Provide temporary heating and cooling required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of low temperatures or high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed.

G. Ventilation and Humidity Control: Provide temporary ventilation required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce ambient condition required and minimize energy consumption.

H. Electric Power Service: Connect to Owner's existing electric power service. Maintain equipment in a condition acceptable to Owner.

I. Electric Power Service: Provide electric power service and distribution system of sufficient size, capacity, and power characteristics required for construction operations.

1. Install electric power service overhead unless otherwise indicated. 2. Connect temporary service to Owner's existing power source, as directed by Owner.

J. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions.

1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.

K. Telephone Service: Provide temporary telephone service in common-use facilities for use by all construction personnel. Install one telephone line(s) for each field office.

1. Provide additional telephone lines for the following:

a. Provide a dedicated telephone line for each facsimile machine in each field office.

2. At each telephone, post a list of important telephone numbers.

a. Police and fire departments. b. Ambulance service. c. Contractor's home office. d. Contractor's emergency after-hours telephone number. e. Architect's office. f. Engineers' offices. g. Owner's office. h. Principal subcontractors' field and home offices.

3. Provide superintendent with cellular telephone or portable two-way radio for use when away from field office.

WHITFIELD ASSOCIATES, INC. 015000 - 4 TEMP FACILITIES AND CONTROLS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. L. Electronic Communication Service: Provide a desktop computer in the primary field office adequate for use by Architect and Owner to access project electronic documents and maintain electronic communications. Equip computer with not less than the following:

1. Processor: Intel Pentium D or Intel CoreDuo, 3.0 GHz processing speed. 2. Memory: 4 gigabyte. 3. Disk Storage: 300 gigabyte hard-disk drive and combination DVD-RW/CD-RW drive. 4. Display: 22-inch (300-mm) LCD monitor with 128 Mb dedicated video RAM. 5. Network Connectivity: 10/100BaseT Ethernet. 6. Productivity Software:

a. Microsoft Office Professional, XP or higher, including Word, Excel, and Outlook. b. Adobe Reader 7.0 or higher. c. WinZip 7.0 or higher.

7. Printer: "All-in-one" unit equipped with printer server, combining color printing, photocopying, scanning, and faxing, or separate units for each of these three functions. 8. Internet Service: Broadband modem, router and ISP, equipped with hardware firewall, providing minimum 384 Kbps upload and 1 Mbps download speeds at each computer. 9. Internet Security: Integrated software, providing software firewall, virus, spyware, phishing, and spam protection in a combined application.

3.3 SUPPORT FACILITIES INSTALLATION

A. General: Comply with the following:

1. Provide construction for temporary offices, shops, and sheds located within construction area or within 30 feet (9 m) of building lines that is noncombustible according to ASTM E 136. Comply with NFPA 241. 2. Maintain support facilities until Architect schedules Substantial Completion inspection. Remove before Substantial Completion. Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to Owner.

B. Temporary Roads and Paved Areas: Construct and maintain temporary roads and paved areas adequate for construction operations. Locate temporary roads and paved areas as indicated on Drawings.

1. Provide dust-control treatment that is nonpolluting and nontracking. Reapply treatment as required to minimize dust.

C. Temporary Use of Permanent Roads and Paved Areas: Locate temporary roads and paved areas in same location as permanent roads and paved areas. Construct and maintain temporary roads and paved areas adequate for construction operations. Extend temporary roads and paved areas, within construction limits indicated, as necessary for construction operations.

1. Coordinate elevations of temporary roads and paved areas with permanent roads and paved areas. 2. Prepare subgrade and install subbase and base for temporary roads and paved areas according to Section 312000 "Earth Moving."

WHITFIELD ASSOCIATES, INC. 015000 - 5 TEMP FACILITIES AND CONTROLS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 3. Recondition base after temporary use, including removing contaminated material, regrading, proofrolling, compacting, and testing. 4. Delay installation of final course of permanent hot-mix asphalt pavement until immediately before Substantial Completion. Repair hot-mix asphalt base-course pavement before installation of final course according to Section 321216 "Asphalt Paving."

D. Traffic Controls: Comply with requirements of authorities having jurisdiction.

1. Protect existing site improvements to remain including curbs, pavement, and utilities. 2. Maintain access for fire-fighting equipment and access to fire hydrants.

E. Parking: Construction personnel to park off site. Parking to be the sole responsibility of the GC

F. Dewatering Facilities and Drains: Comply with requirements of authorities having jurisdiction. Maintain Project site, excavations, and construction free of water.

1. Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining properties or endanger permanent Work or temporary facilities. 2. Remove snow and ice as required to minimize accumulations.

G. Project Signs: Provide Project signs as indicated. Unauthorized signs are not permitted.

1. Identification Signs: Provide Project identification signs as indicated on Drawings. 2. Temporary Signs: Provide other signs as indicated and as required to inform public and individuals seeking entrance to Project.

a. Provide temporary, directional signs for construction personnel and visitors.

3. Maintain and touchup signs so they are legible at all times.

H. Waste Disposal Facilities: Comply with requirements specified in Section 017419 "Construction Waste Management and Disposal."

I. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction. Comply with progress cleaning requirements in Section 017300 "Execution."

J. Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel.

1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities.

K. Temporary Elevator Use: N.A.

L. NOT USED.

M. NOT USED

N. Temporary Stairs: Until permanent stairs are available, provide temporary stairs where ladders are not adequate.

WHITFIELD ASSOCIATES, INC. 015000 - 6 TEMP FACILITIES AND CONTROLS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. O. Existing Stair Usage: Use of Owner's existing stairs will be permitted, provided stairs are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore stairs to condition existing before initial use.

1. Provide protective coverings, barriers, devices, signs, or other procedures to protect stairs and to maintain means of egress. If stairs become damaged, restore damaged areas so no evidence remains of correction work.

P. Temporary Use of Permanent Stairs: Use of new stairs for construction traffic will be permitted, provided stairs are protected and finishes restored to new condition at time of Substantial Completion.

3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facilities.

B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

C. Temporary Erosion and Sedimentation Control: Comply with requirements of 2003 EPA Construction General Permit or authorities having jurisdiction, whichever is more stringent and requirements specified in Section 311000 "Site Clearing."

D. Temporary Erosion and Sedimentation Control: Provide measures to prevent soil erosion and discharge of soil-bearing water runoff and airborne dust to undisturbed areas and to adjacent properties and walkways, according to erosion- and sedimentation-control Drawings requirements of 2003 EPA Construction General Permit or authorities having jurisdiction, whichever is more stringent.

E. Stormwater Control: Comply with requirements of authorities having jurisdiction. Provide barriers in and around excavations and subgrade construction to prevent flooding by runoff of stormwater from heavy rains.

F. Tree and Plant Protection: Comply with requirements specified in Section 015639 "Temporary Tree and Plant Protection."

G. Tree and Plant Protection: Install temporary fencing located as indicated or outside the drip line of trees to protect vegetation from damage from construction operations. Protect tree root systems from damage, flooding, and erosion.

H. Pest Control: Engage pest-control service to recommend practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at Substantial Completion. Perform control operations lawfully, using environmentally safe materials.

WHITFIELD ASSOCIATES, INC. 015000 - 7 TEMP FACILITIES AND CONTROLS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. I. Site Enclosure Fence: Before construction operations begin furnish and install site enclosure fence in a manner that will prevent people and animals from easily entering site except by entrance gates.

1. Extent of Fence: As required to enclose entire Project site or portion determined sufficient to accommodate construction operations.

J. Security Enclosure and Lockup: Install temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security. Lock entrances at end of each work day.

K. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.

L. Temporary Egress: Maintain temporary egress from existing occupied facilities as indicated and as required by authorities having jurisdiction.

M. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior.

1. Where heating or cooling is needed and permanent enclosure is not complete, insulate temporary enclosures.

N. Temporary Partitions: N.A.

1. Construct dustproof partitions with gypsum wallboard with joints taped on occupied side, and fire-retardant-treated plywood on construction operations side. 2. Construct dustproof partitions with two layers of 6-mil (0.14-mm) polyethylene sheet on each side. Cover floor with two layers of 6-mil (0.14-mm) polyethylene sheet, extending sheets 18 inches (460 mm) up the sidewalls. Overlap and tape full length of joints. Cover floor with fire-retardant-treated plywood.

a. Construct vestibule and airlock at each entrance through temporary partition with not less than 48 inches (1219 mm) between doors. Maintain water-dampened foot mats in vestibule.

3. Where fire-resistance-rated temporary partitions are indicated or are required by authorities having jurisdiction, construct partitions according to the rated assemblies. 4. Insulate partitions to control noise transmission to occupied areas. 5. Seal joints and perimeter. Equip partitions with gasketed dustproof doors and security locks where openings are required. 6. Protect air-handling equipment. 7. Provide walk-off mats at each entrance through temporary partition.

O. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 241; manage fire prevention program.

1. Prohibit smoking in construction areas.

WHITFIELD ASSOCIATES, INC. 015000 - 8 TEMP FACILITIES AND CONTROLS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of authorities having jurisdiction. 3. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information. 4. Provide temporary standpipes and hoses for fire protection. Hang hoses with a warning sign stating that hoses are for fire-protection purposes only and are not to be removed. Match hose size with outlet size and equip with suitable nozzles.

3.5 MOISTURE AND MOLD CONTROL

A. Contractor's Moisture Protection Plan: Avoid trapping water in finished work. Document visible signs of mold that may appear during construction.

B. Exposed Construction Phase: Before installation of weather barriers, when materials are subject to wetting and exposure and to airborne mold spores, protect materials from water damage and keep porous and organic materials from coming into prolonged contact with concrete.

C. Partially Enclosed Construction Phase: After installation of weather barriers but before full enclosure and conditioning of building, when installed materials are still subject to infiltration of moisture and ambient mold spores, protect as follows:

1. Do not load or install drywall or other porous materials or components, or items with high organic content, into partially enclosed building. 2. Keep interior spaces reasonably clean and protected from water damage. 3. Discard or replace water-damaged and wet material. 4. Discard, replace, or clean stored or installed material that begins to grow mold. 5. Perform work in a sequence that allows any wet materials adequate time to dry before enclosing the material in drywall or other interior finishes.

D. Controlled Construction Phase of Construction: After completing and sealing of the building enclosure but prior to the full operation of permanent HVAC systems, maintain as follows:

1. Control moisture and humidity inside building by maintaining effective dry-in conditions. 2. Remove materials that can not be completely restored to their manufactured moisture level within 48 hours.

3.6 OPERATION, TERMINATION, AND REMOVAL

A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.

B. Maintenance: Maintain facilities in good operating condition until removal.

1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.

WHITFIELD ASSOCIATES, INC. 015000 - 9 TEMP FACILITIES AND CONTROLS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.

D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.

1. Materials and facilities that constitute temporary facilities are property of Contractor. Owner reserves right to take possession of Project identification signs. 2. At Substantial Completion, repair, renovate, and clean permanent facilities used during construction period. Comply with final cleaning requirements specified in Section 017700 "Closeout Procedures."

END OF SECTION 015000

WHITFIELD ASSOCIATES, INC. 015000 - 10 TEMP FACILITIES AND CONTROLS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. SECTION 017300 - EXECUTION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes general administrative and procedural requirements governing execution of the Work including, but not limited to, the following:

1. Construction layout. 2. Field engineering and surveying. 3. Installation of the Work. 4. Cutting and patching. 5. Coordination of Owner-installed products. 6. Progress cleaning. 7. Starting and adjusting. 8. Protection of installed construction.

B. Related Requirements:

1. Section 011000 "Summary" for limits on use of Project site. 2. Section 017700 "Closeout Procedures" for submitting final property survey with Project Record Documents, recording of Owner-accepted deviations from indicated lines and levels, and final cleaning. 3. Section 078413 "Penetration Firestopping" for patching penetrations in fire-rated construction.

1.2 INFORMATIONAL SUBMITTALS

A. Certificates: Submit certificate signed by land surveyor and or professional engineer certifying that location and elevation of improvements comply with requirements.

B. Landfill Receipts: Submit copy of receipts issued by a landfill facility, licensed to accept hazardous materials, for hazardous waste disposal.

C. Certified Surveys: Submit two copies signed by land surveyor and or professional engineer.

D. Final Property Survey: Submit 10 copies showing the Work performed and record survey data.

1.3 QUALITY ASSURANCE

A. Land Surveyor Qualifications: A professional land surveyor who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing land-surveying services of the kind indicated.

B. Cutting and Patching: Comply with requirements for and limitations on cutting and patching of construction elements.

WHITFIELD ASSOCIATES, INC. 017300 - 1 EXECUTION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 1. Structural Elements: When cutting and patching structural elements, notify Architect of locations and details of cutting and await directions from Architect before proceeding. Shore, brace, and support structural element during cutting and patching. Do not cut and patch structural elements in a manner that could change their load-carrying capacity or increase deflection

a. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety.

b. Other Construction Elements: Do not cut and patch other construction elements or components in a manner that could change their load-carrying capacity, that results in reducing their capacity to perform as intended, or that results in increased maintenance or decreased operational life or safety

2. Visual Elements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch exposed construction in a manner that would, in Architect's opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.

PART 2 - PRODUCTS

2.1 MATERIALS

A. General: Comply with requirements specified in other Sections.

1. NOT USED

B. In-Place Materials: Use materials for patching identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible.

1. If identical materials are unavailable or cannot be used, use materials that, when installed, will provide a match acceptable to Architect for the visual and functional performance of in-place materials.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Existing Conditions: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities, mechanical and electrical systems, and other construction affecting the Work.

WHITFIELD ASSOCIATES, INC. 017300 - 2 EXECUTION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 1. Before construction, verify the location and invert elevation at points of connection of sanitary sewer, storm sewer, and water-service piping; underground electrical services, and other utilities. 2. Furnish location data for work related to Project that must be performed by public utilities serving Project site.

B. Examination and Acceptance of Conditions: Before proceeding with each component of the Work, examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.

1. Examine roughing-in for mechanical and electrical systems to verify actual locations of connections before equipment and fixture installation. 2. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed. 3. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.

C. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.

3.2 PREPARATION

A. Existing Utility Information: Furnish information to local utility Owner that is necessary to adjust, move, or relocate existing utility structures, utility poles, lines, services, or other utility appurtenances located in or affected by construction. Coordinate with authorities having jurisdiction.

B. Field Measurements: Take field measurements as required to fit the Work properly. Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

C. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.

D. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents caused by differing field conditions outside the control of Contractor, submit a request for information to Architect according to requirements in Section 013100 "Project Management and Coordination."

3.3 CONSTRUCTION LAYOUT

A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify Architect and Construction Manager promptly.

WHITFIELD ASSOCIATES, INC. 017300 - 3 EXECUTION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. B. General: Engage a land surveyor and or professional engineer to lay out the Work using accepted surveying practices.

1. Establish benchmarks and control points to set lines and levels at each story of construction and elsewhere as needed to locate each element of Project. 2. Establish limits on use of Project site. 3. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required dimensions. 4. Inform installers of lines and levels to which they must comply. 5. Check the location, level and plumb, of every major element as the Work progresses. 6. Notify Architect and Construction Manager when deviations from required lines and levels exceed allowable tolerances. 7. Close site surveys with an error of closure equal to or less than the standard established by authorities having jurisdiction.

C. Site Improvements: Locate and lay out site improvements, including pavements, grading, fill and topsoil placement, utility slopes, and rim and invert elevations.

D. Building Lines and Levels: Locate and lay out control lines and levels for structures, building foundations, column grids, and floor levels, including those required for mechanical and electrical work. Transfer survey markings and elevations for use with control lines and levels. Level foundations and piers from two or more locations.

E. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels. Include beginning and ending dates and times of surveys, weather conditions, name and duty of each survey party member, and types of instruments and tapes used. Make the log available for reference by Architect and Construction Manager.

3.4 FIELD ENGINEERING

A. Reference Points: Locate existing permanent benchmarks, control points, and similar reference points before beginning the Work. Preserve and protect permanent benchmarks and control points during construction operations.

B. Benchmarks: Establish and maintain a minimum of two permanent benchmarks on Project site, referenced to data established by survey control points. Comply with authorities having jurisdiction for type and size of benchmark.

1. Record benchmark locations, with horizontal and vertical data, on Project Record Documents.

C. Certified Survey: On completion of foundation walls, major site improvements, and other work requiring field-engineering services, prepare a certified survey showing dimensions, locations, angles, and elevations of construction and sitework.

D. Final Property Survey: Engage a land surveyor and or professional engineer to prepare a final property survey showing significant features (real property) for Project. Include on the survey a certification, signed by land surveyor and or professional engineer, that principal metes, bounds, lines, and levels of Project are accurately positioned as shown on the survey.

WHITFIELD ASSOCIATES, INC. 017300 - 4 EXECUTION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 1. Recording: At Substantial Completion, have the final property survey recorded by or with authorities having jurisdiction as the official "property survey."

3.5 INSTALLATION

A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level. 2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement. 3. Conceal pipes, ducts, and wiring in finished areas unless otherwise indicated.

B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.

C. Install products at the time and under conditions that will ensure the best possible results. Maintain conditions required for product performance until Substantial Completion.

D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.

E. Sequence the Work and allow adequate clearances to accommodate movement of construction items on site and placement in permanent locations.

F. Tools and Equipment: Do not use tools or equipment that produce harmful noise levels.

G. Templates: Obtain and distribute to the parties involved templates for work specified to be factory prepared and field installed. Check Shop Drawings of other work to confirm that adequate provisions are made for locating and installing products to comply with indicated requirements.

H. Attachment: Provide blocking and attachment plates and anchors and fasteners of adequate size and number to securely anchor each component in place, accurately located and aligned with other portions of the Work. Where size and type of attachments are not indicated, verify size and type required for load conditions.

1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by Architect. 2. Allow for building movement, including thermal expansion and contraction. 3. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

I. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.

J. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.

WHITFIELD ASSOCIATES, INC. 017300 - 5 EXECUTION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 3.6 CUTTING AND PATCHING

A. Cutting and Patching, General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.

1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.

B. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during installation or cutting and patching operations, by methods and with materials so as not to void existing warranties.

C. Temporary Support: Provide temporary support of work to be cut.

D. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.

E. Adjacent Occupied Areas: Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.

F. Existing Utility Services and Mechanical/Electrical Systems: Where existing services/systems are required to be removed, relocated, or abandoned, bypass such services/systems before cutting to minimize and prevent interruption to occupied areas.

G. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.

1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots neatly to minimum size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use. 2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces. 3. Concrete: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill. 4. Excavating and Backfilling: Comply with requirements in applicable Sections where required by cutting and patching operations. 5. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting. 6. Proceed with patching after construction operations requiring cutting are complete.

H. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other work. Patch with durable seams that are as invisible as practicable. Provide materials and comply with installation requirements specified in other Sections, where applicable.

1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate physical integrity of installation.

WHITFIELD ASSOCIATES, INC. 017300 - 6 EXECUTION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. 2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will minimize evidence of patching and refinishing. 3. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance. 4. Ceilings: Patch, repair, or rehang in-place ceilings as necessary to provide an even-plane surface of uniform appearance. 5. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weathertight condition and ensures thermal and moisture integrity of building enclosure.

I. Cleaning: Clean areas and spaces where cutting and patching are performed. Remove paint, mortar, oils, putty, and similar materials from adjacent finished surfaces.

3.7 PROGRESS CLEANING

A. General: Clean up shall be CONTINUOUS and to the satisfaction of the Construction Manager. Construction Manager shall retain the right to provide labor and materials necessary to maintain a high level of cleanliness and backcharge to the Contractor if necessary. Clean Project site and work areas daily, including common areas. Enforce requirements strictly. Dispose of materials lawfully.

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris. 2. Do not hold waste materials more than seven days during normal weather or three days if the temperature is expected to rise above 80 deg F (27 deg C). 3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.

B. Site: Maintain Project site free of waste materials and debris.

C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.

1. Remove liquid spills promptly. 2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate.

D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.

E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.

F. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.

WHITFIELD ASSOCIATES, INC. 017300 - 7 EXECUTION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012. G. Waste Disposal: Do not bury or burn waste materials on-site. Do not wash waste materials down sewers or into waterways.

H. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

I. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

J. Limiting Exposures: Supervise construction operations to assure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.

3.8 STARTING AND ADJUSTING

A. Start equipment and operating components to confirm proper operation. Remove malfunctioning units, replace with new units, and retest.

B. Adjust equipment for proper operation. Adjust operating components for proper operation without binding.

C. Test each piece of equipment to verify proper operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.

D. Manufacturer's Field Service: Comply with qualification requirements in Section 014000 "Quality Requirements"

3.9 PROTECTION OF INSTALLED CONSTRUCTION

A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.

B. Comply with manufacturer's written instructions for temperature and relative humidity.

END OF SECTION 017300

WHITFIELD ASSOCIATES, INC. 017300 - 8 EXECUTION LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012.

SECTION 03200 CONCRETE REINFORCEMENT

PART 1 – GENERAL

1.1 SUMMARY

A. Extent of concrete work as shown on drawings or as required to complete the Project. Provide Reinforcing Steel for concrete and masonry, complete, as shown and specified per Contract Documents.

B. Related work specified elsewhere: 1. Division-2, Concrete Walls 2. Division-3, Concrete Formwork 3. Division-3, Cast-in-Place Concrete 4. Division-3, Plant-Precast Architectural Concrete 5. Division-4, Assembly 6. Division-5, Epoxy Dowels and Expansion Anchors

1.2 REFERENCES

A. Reference Standards: General: All materials shall conform to the applicable current editions of standard specifications as follows: Section 1907 of California Building Code. Specifications for Structural Concrete for Buildings: ACI 301. Manual of Standard Practice for Detailing Structures: ACI 315. Reinforcing Steel Welding Code: AWS D1.4. Manual of Standard Practice: CRSI/WCRSI. Recommended Practice for Placing Reinforcing Bars: CRSI/WCRSI.

B. Testing: 1. General: Refer to Division 1.

1.3 SUBMITTALS

A. General: Submit in compliance with Division-1 section "Shop Drawings, Product Data and Samples."

B. Shop Drawings: Submit for action shop details and placing drawings for reinforcement. Show all bar sizes, lengths, material, grade, stirrup spacing and all splice and lap locations. Also include special reinforcing required for openings.

C. Samples: If specifically requested.

D. Test Reports: Refer to Division-1.

E. Certificates: Submit for action minimum two (2) certified copies of mill test reports for reinforcing bars, indicating physical and chemical properties for each heat. In addition, show

Whitfield Associates, Inc. 03200 Concrete Reinforcement Laguna Beach Lifeguard Headquarters April 23, 2012 correlation between a specific heat number and specific sizes from that heat number and location in which those bars will be placed. If the test report is not in English or metric bar sizes are submitted, provide a certified translation of the report.

F. Qualifications: Refer to Paragraph 1.4A herein.

1.4 QUALITY ASSURANCE

A. Qualifications: 1. Fabricator: A firm experienced in successfully producing work similar to that indicated for this Project, with a record of successful in-service performance consisting of at least 5 projects with a minimum value of $5 million and 10 years experience, and with sufficient production capacity to produce required units without causing delay in the Work. 2. Installer: A qualified installer who employs on project personnel qualified as ACI-Certified flatwork technician and finisher and a supervisor who is an ACI-Certified concrete flatwork technician.

B. Regulatory Requirements: Comply with all applicable requirements of the laws, codes, ordinances and regulations reference in this section.

C. Pre-Installation Meetings: Conduct meetings at Project site to comply with requirements of Division-1 section "Project Meetings."

D. Concrete Testing Service: Engage a qualified independent testing agency to perform material evaluation test and design concrete mixture.

E. ACI Publication: Comply with ACI 301 and ACI 117.

1.5 PRODUCT HANDLING:

A. Storage: Store reinforcement off ground; cover; keep clean, and prevent bending and damage.

1.6 EXTRA MATERIAL

A. Contractor shall bid to include costs to furnish and install 1.05 times the total reinforcing quantity shown on drawings, as required by details shown on the drawings, or as required by referenced codes and standards. This additional steel shall be installed during construction, in sizes and locations as directed.

PART 2 – PRODUCTS

2.1 MATERIALS

A. Reinforcement: 1. Steel Reinforcing: ASTM A615 or ASTM A706, deformed; See construction document for the usage of AGTM A706 bars. Dowel bars for installation through control or construction joints shall be smooth or shall be wrapped on one end to allow slippage. 2. Welded Wire Fabric: ASTM A185; 6x6-W1.4xW1.4, unless otherwise specified or shown.

Whitfield Associates, Inc. 03200 Concrete Reinforcement Laguna Beach Lifeguard Headquarters April 23, 2012 B. SUPPORTS: 1. General: Types per CRSI/WCRSI Manual of Standard Practice. 2. Concrete on Earth: Including footings and reinforced slabs; plain blocks. 3. Exterior Concrete: a. Exposed to View: Class C protected wire or plain precast concrete blocks especially made to match poured concrete. b. Other: Class B pregalvanized wire. 4. Interior Concrete: a. Exposed to View: Class C plastic protected wire. b. Other: Class A bright basic wire. 5. Tie Wire: Black annealed; minimum 18 gage. 6. Welding Rods: Low Hydrogen AWS Class E70 for Grade 40, E90 for Grade 60.

2.2 FABRICATION

A. GENERAL: Detail and fabricate per ACI315 or CRSI/WCRSI Manual of Standard Practice.

B. REINFORCING STEEL: Make bends using pin sizes per ACI 301 and ACI 315. Bend bars cold; do not preheat, unless permitted by Owner's Representative. Bars reduced in section, having kinks, or bends not shown, not permitted.

2.3 QUALITY CONTROL

A. Welding: Per AWS D1.4-92; the carbon equivalent (C.E.) or reinforcing bars to be welded shall be calculated from the chemical composition as shown in the mill report by the following formula:

C.E. = %C + %Mn/6 (All steel bars except A706) C.E. = %C+%Mn/6+%Cu/40+%Ni/20+%Cr/10-%Mo/50-%V/10 (A706)

If mill test reports are not available, chemical analysis shall be made of bars representative of the bars

to be welded. The C.E. for ASTM A706 bars may not exceed 0.55%. Bars with a C.E. above 0.75

shall not be welded. No welds shall be made at bends in reinforcing bars unless specifically approved

by the Owner's Representative. Cost of chemical analysis, if required, will be backcharged to

Contractor.

PART 3 – EXECUTION

3.1 EXAMINATION OF CONDITIONS

A. Substrate Conditions: Examine substrate and report any defects to Owner's Representative. Start of work is acceptance of conditions as they exist.

Whitfield Associates, Inc. 03200 Concrete Reinforcement Laguna Beach Lifeguard Headquarters April 23, 2012 B. Job Measurements: The Contractor shall take field measurements for this work and be responsible for same. Report any discrepancy between plan and field dimensions to the Owner's Representative.

3.2 INSTALLATION

A. General: Place per ACI 315 or CRSI/WCRSI Recommended Practice for Placing Reinforcing Bars. Securely hold reinforcement in position by wire ties at intersections and supports. Reinforcement must be in place before concreting is begun. Keep personnel on job to maintain position of reinforcing as concrete is placed.

B. Placement: 1. General: Before placing, clean reinforcement thoroughly of loose rust, mill scale, oil, grease, and other foreign material which reduces or destroys bond. Place reinforcing with clearances for minimum protective cover of concrete as shown. Do not bend or straighten reinforcing in any way which will weaken or injure material. Field bending of reinforcing around sleeves or openings not permitted. 2. Supports: Install types specified to support reinforcing steel. Number and location to assure reinforcement has sufficient strength to resist crushing and displacement under full concrete load when poured. 3. Interferences: Coordinate the Work to eliminate interference between reinforcing and pipes, conduits, sleeves, and other construction. Give notice to Owner's Representative and obtain method or procedure to resolve interference.

C. Welded Wire Fabric: Secure to resist transverse and lateral movements; support in same manner specified for reinforcing steel. Overlap one wire space plus 2”, or 6”, whichever is greater; wire tie. Support to locate in slab thickness as shown on Drawings.

D. Placing Tolerances: 1. General: Per ACI 301 or CRSI/WCRST Recommended Practice for Placing Reinforcing Bars, unless otherwise shown. 2. Parallel Bars: Minimum center to center distance between bars shall be 2 times diameter; in no case shall clear spacing between bars be less than 1” or 1-1/3 times maximum size coarse aggregate.

E. Splices: 1. General: Unless otherwise shown, splice top reinforcing at midspan between supports; splice bottom reinforcing at supports. Stagger laps at adjacent splices wherever possible. 2. Type: a. Lap Splices in Concrete: As shown on structural drawings. b. Welded Splices: Butt and full weld per AWS D1.4 to develop, in tension, not less than 125% of bar yield strength.

F. Welding: Both shop and field welding of reinforcing bars to each other or to structural steel are required (see Drawings), and low hydrogen rod specified must be used for either. Bars to be welded must have chemical composition a specified. All welding reinforcement is to be inspected.

3.3 FIELD QUALITY CONTROL

A. Testing: 1. Welding: Continuous inspection by Laboratory as specified in Division-1.

Whitfield Associates, Inc. 03200 Concrete Reinforcement Laguna Beach Lifeguard Headquarters April 23, 2012

A. Retesting: Make necessary corrections to work that is not in conformance with specified requirements. Retests will be paid for by Owner and backcharged to Contractor.

B. Inspections: 1. Steel reinforcement placement 2. Steel reinforcement welding

END OF SECTION

Whitfield Associates, Inc. 03200 Concrete Reinforcement Laguna Beach Lifeguard Headquarters April 23, 2012

SECTION 03300 CAST-IN-PLACE CONCRETE

PART 1 – GENERAL

1.1 SCOPE OF WORK

A. Description: Provide Cast-in-Place Concrete, complete as shown and specified per Contract Documents.

B. Related Work Specified Elsewhere: 1. Division-1, Construction Facilities & Temporary Controls 2. Division-3, Concrete Formwork 3. Division-3, Concrete Reinforcement 4. Division-3, Plant-Precast Architectural Concrete 5. Mechanical: Division-15, Unformed concrete, such as thrust blocks, etc.

1.2 QUALITY ASSURANCE

A. Reference Standards: 1. General: Comply with Chapter 19 of the California Building Code, applicable provisions of following and as specified: ACI 301 Specification for Structural Concrete for Buildings ACI 305 Recommended Practice for Hot Weather Concreting ACI 306 Recommended Practice for Cold Weather Concreting ACI 318 Building Code Requirements for Reinforced Concrete NRMCA Check List for Certification of Ready Mixed Concrete Production Facilities

B. TESTING: 1. General: Refer to Division 1. 2. Testing and Retesting: Agency selected and paid for by the Contractor. 3. Testing Agency Qualifications: An independent agency acceptable to authorities having jurisdiction, qualified according to ASTM C1077 and ASTM E329 for testing indicated, as documented according to ASTM E548. 4. Manufacturer Qualification: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C94/C94M requirements for production facilities and equipment.

1.3 SUBMITTALS

A. General: Submit in compliance with Division-1 section "Shop Drawings, Product Data and Samples."

B. Shop Drawings: 1. Concrete Mix Request: List mixes required; state where each is proposed. 2. Placing Concrete: Plan and schedule; include location of construction and control joints.

C. Concrete Mix Designs: Submit for action. Concrete mix designs shall be designed, signed and stamped by a Registered Professional Engineer (Civil) in California.

WHITFIELD ASSOCIATES, INC. 03300 CAST IN PLACE CONCRETE LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012

D. Samples: General contractor to provide a mock up of each type, finish concrete on site for approval of project manager. Mock up to be a minimum of 48” x 48”.

E. Test and Inspection Reports: 1. Compressive strength test on concrete.

F. Certificates: 1. Admixtures: Two certified copies per ASTM C494 for each type specified. 2. Continuous Batch Plant Inspection Waiver: Provide certificates as required in Section 2.3C.

1.4 PRODUCT HANDLING

A. General: Refer to Section 01600 1.2.A

B. Storage: Store cement in weathertight building, permitting easy inspection and identification. Protect from dampness. Lumpy or stale cement will be rejected and replaced at the Contractor’s expense.

1.5 JOB CONDITIONS

A. Environmental Requirements: 1. Cold Weather Placement: Per ACI 306 and as specified. When temperature is 50 degrees F or lower, take suitable means as necessary to maintain minimum concrete temperature of 50 degrees F, at time of placing. Heat aggregate, or mixing water, or both, as required. Provide suitable means for maintaining concrete at a temperature not less than 50 degrees F for at least 72 hours after placement; provide screens or enclosures to protect concrete from prevailing winds and weather; provide temporary heaters if necessary 2. Hot Weather Placement: Per ACI 305 and as specified. When temperature exceeds 85 degrees F, or when temperature exceeds 70 degrees F with wind blowing, take suitable means as necessary to maintain fresh concrete temperature below 90 degrees F; use chilled water, chipped ice, or evaporative cooling of aggregate as necessary. In addition, dampen forms, subgrade, and reinforcing steel; cool by evaporation and protect from hot sun and wind until concrete is placed.

B. Protection: Finish surfaces shall be protected at all times from concrete adjacent to them. Inspect forming against such work and establish tight leakproof seal before concrete is placed. Finish work defaced with concrete on surface shall be replaced.

C. Scheduling: 1. General: Coordinate with other sections for installation of concrete embedded items. 2. Buried Items: Do not place concrete until items have been tested for mechanical operation. 3. Concrete Surfaces to Receive Other Finishes: Coordinate with other applicable sections to assure concrete finish is suitable to receive specified finish. 4. Reinforcement: Do not place any reinforced concrete until inspected.

PART 2 – PRODUCTS

2.1 MATERIALS

WHITFIELD ASSOCIATES, INC. 03300 CAST IN PLACE CONCRETE LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012 A. Admixtures: Certified by manufacturer to contain not more than 0.1% water soluble chloride ions by mass of cemetitious material and to be compatible with other admixtures and cementitious materials. Do not use admixtures containing calcium chloride. 1. Cement Dispersing Admixture: Use admixture to improve placing, reduce water cement ratio, and ultimate shrinkage. Such admixture must conform to UBC Standard 19-9 and shall be included in original design mix. 2. : Western Fly Ash, conforming to ASTM C618 for Class N or Class F materials 3. Air-entraining admixture/ASTM C260 4. Water-reducing admixture/ASTM C494 Type A 5. Retarding admixture/ASTM C494 Type B

B. Aggregate: 1. Normal Weight Concrete: a. General: ASTM C33; except as modified herein. b. Coarse Aggregate: Grade within limits shown or specified. c. Fine Aggregate: Natural sand; grade within limits of 3/8” to No. 100 sieve. d. Combined Grading: Meet limits in Section 1905 of 2002 City of Los Angeles Building Code.

C. Cement: 1. General: Use one brand of each type of cement for exposed concrete. 2. : ASTM C150 and UBC Standard 19-1, Type II and Type V.

D. Curing Materials: 1. Curing Compounds: ASTM C309, Type I, Class B which will not discolor concrete nor affect bonding of other finishes applied there over. 2. Sheet Materials: ASTM C171; waterproof paper, polyethylene film, or white-burlap- polyethylene sheet.

E. Vapor Retarder: 1. 6 MIL “Visqueen.” 2. Plastic Vapor Retarder: ASTM E1745, Class A: Including manufacturer’s recommended adhesive or pressure sensitive tape.

F. Non-Shrink Grout: “Masterflow 713,” by Master Builders, "Hi-Flow Grout" by Euclid Chemical Company, or equal premixed, non-metallic, no chlorides, non-staining, and non-shrinking per CRD-C621 Corps of Engineers Specification.

G. Epoxy Bonding Agent: ASTM C881 “Concresive Standard Liquid” by Master Builders, Inc., "Corr Bond" by Euclid Chemical Company, or equal.

H. Sand: ASTM C144, natural sand.

I. Water: Potable; free of deleterious materials/ASTM C94

J. Expansion and Isolation – Joint-Filler Strip: ASTM D1752, cork or self-expanding cork

2.2 PROPORTIONING AND MIXES

A. Concrete Design: 1. General: All concrete used on this work will be designed for strength in accord with provisions of Section 1905.3 of the 2002 City of Los Angeles Building Code. All mixtures will be designed by Laboratory selected by the Contractor. All costs of designing mixes will

WHITFIELD ASSOCIATES, INC. 03300 CAST IN PLACE CONCRETE LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012 be borne by the Contractor. Should Contractor desire to pump concrete, a modified Class “B” mix will be designed by Laboratory at Contractor expense. Fly Ash may be used in concrete at or below grade to improve workability in amounts of up 15% of cement weight. 2. Mix Design: Proportion mix so that volume of fine aggregate is not less than 40% nor more than 45% of total of separate volume of fine and coarse aggregate measured loosely before being combined. Include surface moisture contained in aggregate in total amount of water in mix. Added water shall be difference between total amount of water and surface moisture contained in aggregates. Provide air entrainment for mixes so specified. 3. Designed Strength as specified on the drawings. 4. Classes of Concrete: a. Class “A” Concrete: 1-1/2” max. aggregate size and 0.55 maximum water to cement ratio. Use in footings and other concrete of like nature where minimum thickness equals or exceeds 8”. (Class “B” concrete may be used in lieu of Class “A” at Contractor’s option.) b. Class “B” Concrete: 1” max. size aggregate and 0.55 maximum water to cement ratio. Use in structural concrete less than 8” in min. thickness, excluding slab on grade. c. Class “C” Concrete: ¾” maximum size aggregate for fill in metal deck and interior slab on grade with 0.50 maximum water to cement ratio. 5. Slump Limits: Provide concrete, at point of final discharge, of proper consistence determined by Test Method ASTM C143. Slumps not to exceed 4”. 6. Shrinkage Limits: Provide concrete with proven shrinkage characteristics of less than 0.05%.

B. Mixing of Concrete: 1. General: Conform to requirements of Chapter 19, 2002 City of Los Angeles Building Code. 2. Mixing: All concrete shall be mixed until there is uniform distribution of material and mass in uniform and homogenous; mixer must be discharged completely before the mixer is recharged. 3. Job Mixed Concrete: Use batch mixer of approved type, with capacity to handle one or more full sack batches, no split sack batches permitted. Operate mixer as recommended by manufacturer, mixing at least one and one half minutes after all materials are in drum. 4. Ready-mix Concrete: a. General: Mix and deliver in accordance with the requirements set forth in UBC Standard No. 19-3. Collated fiber shall be added at central mixing plant. 5. Equipment: The Owner's Representative may order removal of any handling and mixing equipment, which in his opinion is insufficient or in any way unsuitable for the work being performed.

2.3 QUALITY CONTROL

A. Cement: 1. Comply with Section 1903, 2002 City of Los Angeles Building Code. 2. Mill certificates and affidavit will be accepted for Na20 equivalent provided strict controls are set up to insure they apply to cement used on job.

B. Aggregates: Comply with Section 1903, 2002 City of Los Angeles Building Code.

C. Batch Plant Inspection: 1. Testing laboratory shall maintain continuous inspection at batch plant to run check sieve analysis of aggregate; check design of mix, check cement being used with test reports, check loading of trucks and certify quantities of materials placed in each truck. Batch plant to deliver to Project Inspector with each truck, certificates, bearing signature of representatives of testing laboratory, stating quantity of cement, water, fine aggregate, coarse aggregates contained in load, and time mixer was loaded.

WHITFIELD ASSOCIATES, INC. 03300 CAST IN PLACE CONCRETE LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012 2. When the complies fully with the requirements of UBC Standard No. 19-3, has been certified to comply with the requirements of the National Ready Mixed Concrete Association, and is equipped with an automatic batcher in which the total batching cycle (exclusive of admixture measurement and introduction) is completed by activating a single starter device; the Owner's Representative may waive continuous inspection and substitute the following procedure: a. Inspection by representatives of testing laboratory shall be made at start of the work for each class of concrete to be used, to check the first batching and to furnish mix proportions to Licensed Weighmaster. b. Licensed Weighmaster shall positively identify materials as to quantity and to certify to each load by ticket. The maximum amount of water to be added at the site shall be clearly indicated. c. Ticket shall be transmitted to Project Inspector by truck driver with load identified thereon. Inspector will not accept load without load tickets identifying mix and will keep daily record of pours, identifying each truck, its load and time of receipt and will transmit two copies of record to the Owner's Representative. d. At end of project, Weighmaster shall furnish affidavit to Owner's Representative on form satisfactory to Owner's Representative certifying that all concrete furnished conforms in every particular to proportions established by mix designs. Any costs involved in this modified procedure will be paid by Contractor.

PART 3 – EXECUTION

3.1 EXAMINATIONS OF CONDITIONS

A. Substrate Conditions: Examine substrate and report any defects to Owner's Representative. Start of work is acceptance of conditions as they exist.

B. Permission To Place Concrete: Placing of concrete subject to approval of Owner's Representative. Notice of readiness shall be given Owner's Representative 48 hours before placing concrete. All forms, reinforcement and embedded items to be in place.

3.2 PREPARATION

A. General: Remove water from excavations before depositing concrete. Divert water flow through proper side drains; remove without washing over freshly deposited concrete. Clean equipment and remove debris from places to be occupied by concrete. Provide runways, or other means for wheeled equipment to convey concrete to placing points. Do not run wheeled equipment used to place concrete over reinforcement; do not support runways on reinforcement.

B. Reinforcement: Reinforcement and all other embedded items to be cleaned of all coating that

would impair bond. Clean surfaces coated with cementitious materials by wire brushing.

3.3 VAPOR RETARDER INSTALLATION

A. Following leveling and tamping of granular base for interior slabs on grade, place 2 inch sand layer beneath and over vapor retarder sheeting.

B. Lap vapor barrier joints 6” and seal with appropriate tape.

WHITFIELD ASSOCIATES, INC. 03300 CAST IN PLACE CONCRETE LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012

3.4 PLACEMENT

A. General: 1. Transportation: Handle from mixer to place of final deposit as rapidly as practicable by methods which will prevent separation or loss of ingredients; deposit as nearly as practicable in final position to avoid rehandling or flowing; partially hardened concrete must not be deposited in work. 2. Placing: When once started, carry on concrete pouring continuously until section is complete between predetermined construction joints; prevent splashing of forms or reinforcement with concrete, remove such accumulations of hardened or partially hardened concrete on forms or reinforcement above concrete already in place before work proceeds; free fall of concrete not to exceed 4’-0”, if necessary, provide openings in forms to reduce fall. 3. Form Spreaders: Remove as placing of concrete progresses. 4. Footings: Place as monolith in one continuous pour. 5. Excavations: Keep free of water; all concrete shall be placed in dry conditions. 6. Compacting: Concrete on grade shall be thoroughly compacted by spading and puddling. Concrete shall be thoroughly worked around reinforcement and embedded fixtures and into corners of forms. Vibrate outside of forms, hammering at location of pouring. All other concrete shall be compacted by high speed internal vibrators. Puddling, tamping and vibrating shall not be applied to concrete which has already taken initial set nor shall it be continued so long as to cause segregation of material. 7. Grout: a. At construction joints and where conditions make puddling difficult or where reinforcement is congested, first deposit batches of grout, containing same proportion of cement and sand used in concrete, plus max. of 50% of coarse aggregate, to 2” (or more) depth in forms, and carry on operation of filling with regularly specified mix at such rate that mix is at all times plastic and flows readily into space between bars. If transit mix is supplied, this grout should be furnished on job with small batch mixer. b. Grout Under Bearing Plates: Grout where bearing plates are erected with leveling nuts. Grout with specified non-shrink grout, as recommended by manufacturer. Band grout so that grout fills all voids. 8. Concrete Slabs (Interior and Exterior): a. General: All slabs shall be laid to required lines and grades with accurate, firm . Subgrade shall be thoroughly watered the night before laying and sprinkled the following day, immediately in advance of placing. b. Slab Depressions: Depress areas of slabs where required for finishes, floor drains, door frames and tile where shown and as required to install subsequent work. 9. Horizontal Construction Joints: Keep exposed concrete face of construction joints continuously moist from time of initial set until placing of concrete; thoroughly clean contact surface by chipping entire surface not earlier than 4 days after initial pour to expose clean hard aggregate solidly embedded, or by approved method that will assure equal bond, such as green cutting. If contact surface becomes coated with earth, sawdust, etc., after being cleaned, re-chip entire surface.

B. Concrete Finishes: 1. Finish: a. General: Tamp slab surface with grid tamper and strike off to firm screeds; following stiffening of concrete, float to true surface and finish as follows: b. Interior Slabs: Smooth finish; two steel troweling operations; long-handled or Fresno trowel not permitted; first troweling performed when concrete will support operator on kneeboards; second troweling to follow concrete initial set for burnished surface free

WHITFIELD ASSOCIATES, INC. 03300 CAST IN PLACE CONCRETE LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012 from trowel marks, depressions, ridges or other blemishes, and shall be acceptable to finish flooring applicators. Tolerance for flatness shall be 1/8” in 10’. c. Broom Finish: Apply a broom finish to all exterior and interior ramps and elsewhere as indicated. d. Joints: Mark off exposed joints, where indicated, with ¼” radius edging tool. Markings to be clean cut, straight and square with respect to border. Tool edges of exposed expansion and contraction joints, border edges, and wherever concrete adjoins other material or vertical surfaces.

3. Exposed Concrete Surfaces (Not Including Top Surface of Slabs): Immediately after removal of forms from concrete to be left exposed, remove fins and rough spots; damaged and irregular surfaces and holes left by form clamps and sleeves shall be patched with grout; tie wires are to be withdrawn and holes pointed up with neat cement paste similar to procedure noted under "Patching". This shall extend to distance of 2" below established grade lines. Elsewhere, ends of wires shall be cut off flush. Care shall be taken to approach as nearly as possible texture of exposed adjacent concrete surface. After patching, all concrete that is to remain exposed shall be grout cleaned with mixture of 1 part cement and 1-1/2 parts fine sand with sufficient water to produce consistency of thick paint. Apply to concrete surfacing with brush after first wetting concrete. Immediately after applying, float surface with wood float, scouring vigorously. Keep damp during this period in hot weather. When set, grout shall be scraped from wall with edge of steel trowel - allowed to dry - then wiped or rubbed with dry burlap. Entire cleaning operation of any area shall be completed on the same day started. This treatment shall be carried 4" below grade, and all patching and grout cleaning done immediately upon removal of forms.

C. Curing: According to ACI 308.1 1. Concrete in Forms: Keep forms and top of concrete between forms wet continuously until removal of said forms; maintain exposed concrete in wet condition for 14 days after removal of forms. 2. Interior Slabs Scheduled to be Exposed: Cure by sprinkling with fine water mist immediately behind finish and cover while still moist and as soon as possible, but in no case more than 3 hours after finishing, with specified curing paper. Lap sheets and cement together to form seal. Keep in place not less than 14 days and as long thereafter as work continues which may subject slab surface to dirt or abrasion due to nails, chips, etc. Surface shall be wet from fine water mist when paper is applied. 3. Interior Slabs Scheduled to Receive Carpet or Vinyl Tile: Cover and cure with approved membrane curing compound compatible with adhesive. 4. Exterior Slabs: Cover and cure with membrane curing or moist sand at Contractor’s option. Upon completion of job, wash clean.

D. Defective Concrete: 1. General: As approved by Owner's Representative, remove defective concrete from site, or cut out and repair before concrete is thoroughly dry. No patching is to be done until Owner's Representative has examined surfaces. 2. Permission: Consent to patch any area shall not be considered waiver of right to require removal of defective work, if patching does not, in opinion of Owner's Representative, satisfactorily restore quality and appearance of surface. 3. Defective Concrete is: a. Concrete not meeting specified 28-day strength. b. Concrete which contains rock pockets, voids, spalls, cracks, exposed reinforcing, or other defects which adversely affect strength, durability or appearance. c. Concrete which is incorrectly formed, out of alignment or not plumb or level. d. Concrete containing embedded wood or debris.

WHITFIELD ASSOCIATES, INC. 03300 CAST IN PLACE CONCRETE LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012 e. Concrete having patched voids which were not filled with Owner Representative’s approval. f. Concrete not containing required embedded items. 4. Patching: Repairs to defective concrete involving structural strength subject to approval of Owner's Representative a. Chip away minor defective areas to depth of about 1" with edges perpendicular to surface. Wet area to be patched and space at least 6" wide entirely surrounding it to prevent absorption of water from patching mortar. b. Coat with specified bonding agent per manufacturer's instructions. Apply patching mortar immediately thereafter. Patching mortar shall consist of 1 part cement to 3 parts fine aggregate mixed with solution of 1 part specified bonding agent to 6 parts water to consistency as dry as possible consistent with handling and placing. c. Thoroughly compact mortar by ramming into place and off so as to leave patch slightly higher than surrounding surface. Leave undisturbed for 1 to 2 hours to permit initial shrinkage before finial finish. Finish to match adjoining surface. Keep wet for at least 7 days. Provide protective covering such as burlap or fiberboard so that patch area is kept continuously damp. d. In general, minor defective work may be repaired by use of cement mortar, as specified above, but if defects are serious, or affect strength of structure, or, if patching does not satisfactorily restore quality and appearance of surface, complete removal and use of cement gun concrete may be ordered.

3.5 FIELD QUALITY CONTROL

A. General: Performed by Job Inspector unless assigned to Testing Laboratory. Comply with 1998 California Building Code and as specified in B. below.

B. Strength Test: Four identical cylinders shall be taken and tested for each 50 cu. yd. of concrete, or each 2000 square feet of surface area for slabs or wall or fraction thereof of each mix being placed each day. Each set of cylinders shall represent as nearly as possible the batch of concrete from which they are taken; one shall be tested at the age of 7 days and the others at 28 days. Additional cylinders for early strength testing as requested by the Contractor shall be cost, stored, tested and reported at Contractor’s expense. Owner shall back-charge Contractor for any and all costs associated with additional concrete cylinders.

C. Retesting: Make necessary corrections to work that is not in conformance with specified requirements. Retests will be paid for by Contractor.

END OF SECTION

WHITFIELD ASSOCIATES, INC. 03300 CAST IN PLACE CONCRETE LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012

SECTION 05500 METAL FABRICATIONS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Stock and custom fabricated metal items scheduled at end of this Section, complete in respect to function as intended.

1. Metal fabrications includes items made from iron and steel shapes, plates, bars, strips, tubes, pipes and castings which are not a part of structural steel or metal systems specified elsewhere.

B. Related Sections:

1. Section 09960: High performance coating for canopy.

1.2 REFERENCES

A. American Welding Society (AWS): D1.1, Structural Welding Code.

B. National Association of Architectural Metal Manufacturers (NAAMM):

1. Pipe Rail Manual. 2. Heavy Duty Metal Bar Grating Manual.

1.3 SUBMITTALS

A. Product Data: Submit manufacturer's literature for products used in metal fabrications, including paint, grout and manufactured items.

B. Shop Drawings: Submit for fabrication and erection of metal fabrications, indicate profiles, sizes, connection, reinforcing and anchorage.

1. Provide templates for anchorage installation by others.

C. Certificates: Submit certification signed by Illinois registered civil or structural engineer indicating compliance with Contract Documents and code requirements.

1.4 QUALITY ASSURANCE

A. Regulatory Requirements:

1. Access: Comply with California Building Code and Americans with Disabilities Act Accessibility Guidelines (ADAAG) requirements for access for persons with disabilities.

2. Code: Comply with requirements of applicable codes for railing design, except where more restrictive codes are specified.

Whitfield Associates, Inc. 05500 - 1 Metal Fabrications Laguna Beach Lifeguard Headquarters May 25, 2012 PART 2 - PRODUCTS

2.1 MATERIALS

A. Aluminum:

1. Rolled Structural Shapes: ASTM B 308, 6061 alloy.

2. Plates: ASTM B 209, 6161-T6 alloy and temper.

3. Extrusions: ASTM B 221, alloy and temper specified for each item specified herein.

4. Sheet: ASTM B 209, alloy and temper specified for each item specified herein.

5. Tubing: ASTM B 241-96, 6063-T6 alloy and temper.

6. Castings: ASTM B 26, 214 alloy.

B. Steel, Rolled Shapes, Plates and Bars: ASTM A36.

1. Steel Bar Grating: ASTM A36 or ASTM A1011.

2. Wrought Iron: ASTM A 29, weldable quality, low carbon mild steel.

C. Structural Steel Sheet: Hot rolled, ASTM A1011; or cold rolled, ASTM A1008, Class 1; of grade required for design loading.

D. Steel Pipe: ASTM A53, Type S seamless, grade as selected by fabricator and as required for design loading; minimum standard weight, STD or Schedule 40.

E. Pipe Sleeves: Pipe sleeves through concrete walls and footings shall be standard weight, wrought iron, mild steel, or cast iron sleeves with not less than 1/2 inch space all around between the sleeve and pipe.

F. Steel Tubing: Cold formed ASTM A500; or hot rolled, ASTM A501; minimum Grade B; seamless where exposed.

G. Castings: Gray iron, ASTM A48, Class 30; malleable iron, ASTM A47.

1. Ductile Iron Castings: ASTM A536, Grade 65-45-12.

H. Concrete Inserts: Threaded or wedge type; galvanized ferrous castings, either malleable iron ASTM A47, or cast steel ASTM A27. Provide bolts, washers and shims as required, hot-dip galvanized, ASTM A153.

I. Nonmetallic, Nonshrink Grout: For grout in exposed to view locations use premixed, nonmetallic, non-corrosive, non-staining grouting compound containing silica sands, portland cement, shrinkage compensating agents and water reducing agents, meeting the requirements of ASTM C 1107. Acceptable products or equal:

1. Bostik Findley Inc.; Upcon Grout.

2. Gifford Hill & Co., Inc.; Supreme.

Whitfield Associates, Inc. 05500 - 2 Metal Fabrications Laguna Beach Lifeguard Headquarters May 25, 2012 3. Master Builders; Masterflow 713.

4. Protex Industries, Inc.; Propak.

5. The Upco Company; Upcon Nonshrink

6. U.S. Grout Corp.; Five Star Grout.

J. Quick Setting Hydraulic Cement. Acceptable products or equal:

1. The Burke Co; Burke Plug.

2. Minwax Construction Products Div.; Super Por-Rok.

3. Tamms Industries Co.; Tammstech Rapid Rock.

4. Master Builders; Masterflow 713.

K. Polymer Modified Concrete: High strength, polyester resin having the following physical properties:

1. Compressive Strength: 14,000 psi min. per ASTM C39.

2. Tensile Strength: 1,500 psi min per ASTM C78.

3. Water Absorption: 1.0% max per ASTM C140.

L. Anchors, Bolts, and Fastenings: ASTM A307, Grade A and ASTM A563.

1. Provide zinc-coated fasteners for exterior use or where built into exterior walls.

M. Welding Materials: AWS D1.1, type required for materials being welded.

1. Electrodes: AWS A5.1-91 or A5.5-96.

N. Galvanizing Repair Compound: High zinc dust content galvanizing repair paint meeting the requirements of ASTM A780. Acceptable products or equal:

1. American Solder & Flux; Drygalv.

2. Kenco Div.; Galvicon.

3. Metalloy Products Co.; Galvalloy.

O. Shop Primer:

1. Steel Surfaces: Fast curing, lead and chromate free, modified alkyd primer. Acceptable products or equal:

a. Carboline Co.; No. GP-20 or GP-818. b. Rust-O-Leum Corp.; No. 678 or 7669. c. The Sherwin Williams Co.; No. B50 N 2 or B50N Z 6. d. Tnemec Co., Inc.; 10-99 or P10-99.

Whitfield Associates, Inc. 05500 - 3 Metal Fabrications Laguna Beach Lifeguard Headquarters May 25, 2012 P. Paint: Provide paints specified in Section 09900 - Painting.

2.2 PRE-FABRICATED PRODUCTS

A. Steel Bollards: Minimum Schedule 80 seamless steel piping, filled with minimum 2000 psi concrete.

2.3 FABRICATION, GENERAL

A. When not otherwise indicated or specified, comply with applicable requirements of AISC "Specifications for Design, Fabrication and Erection of Structural Steel for Buildings".

B. Verify all lines, levels, and dimensions, where possible, just before commencing fabrication of connection details. Correct work that does not fit.

C. Fabricate items with joints neatly fitted and properly secured.

D. Grind exposed welds continuous, smooth and flush with adjacent finished surfaces, and ease exposed edges to approximate 1/32" uniform radius.

E. Exposed Mechanical Fastenings: Flush countersunk fasteners unobtrusively located, consistent with design of structure.

F. Fit and shop assemble in largest practical sections for delivery.

G. Make exposed joints flush butt type, hairline joints where mechanically fastened.

1. Fabricate joints exposed to weather in manner to exclude water or provide weep holes where water could accumulate.

H. Cut, drill, or punch holes at right angles to the surface of the metal; do not enlarged by burning. Drill holes in base or bearing plates.

I. Supply components required for proper anchorage of metal fabrications; fabricate anchorage and related components of same material and finish as metal fabrication.

2.4 LADDERS

A. Ladders: Comply with requirements of ANSI A14.3.

1. Fabricate ladders of 3/4 inch round solid section carbon steel rods fitted into holes drilled in carbon steel side rails, welded and ground smooth. Fully weld support brackets to side rails.

a. Provide non-slip surface on top of rung, similar to epoxy resin and aluminum oxide granules surface.

2. Support ladders at top and bottom and at intermediate points spaced not more than 5 feet on center.

3. Use welded or bolted steel brackets designed for support and anchorage and to hold ladder clear of the wall surface with a minimum of 7 inches clearance from wall to centerline of rungs.

Whitfield Associates, Inc. 05500 - 4 Metal Fabrications Laguna Beach Lifeguard Headquarters May 25, 2012 B. Ladder Extensions: Provide 42" ladder extension device for fixed ladders under access hatches and floor doors.

1. Type: Bilco/LadderUP Safety Post.

C. Finish: Shop prime exposed steel surfaces of interior ladders and galvanize exterior ladders.

2.5 FLOOR GRATING

A. Welded Grating: Provide welded steel bar grating with serrated traffic surface complying with requirements of NAAMM "Heavy Duty Metal Bar Grating Manual".

B. Design gratings to support a live load of 100 pounds per square foot with deflection not greater than 1/4 inch for the spans indicated.

C. Provide edges of gratings with banding bars of the same size as bearing bars. Attach banding bars by welding.

D. Provide not less than four saddle anchors designed to fit over two bearing bars for each grating section. Provide each saddle anchor with a threaded bolt with nut and washer.

E. Provide grating with galvanized finish.

2.6 TRASH ENCLOSURE GATES

A. Not Used

2.7 ROLL-UP AND SECTIONAL DOOR EDGE GUARD

A. Not Used

2.8 MISCELLANEOUS ROLLED STEEL PLATES AND SHAPES

A. Provide for corner guards, sills, mechanical equipment supports and other locations indicated or required to complete the work.

2.9 KNOX BOX

A. Manufacturer (basis of design): Knox Company, Phone (800) 552-5669.

1. Model: Knox Box 3200 Series, recessed mounted, locking as selected by Architect.

a. Dimensions: 7”W x 7”H x 3 1/4” D.

2. Material: ¼” plate steel housing with ½” thick steel door with interior gasket seal.

3. Finish: Zinc-phosphate primer to Federal Standard TTC 490 Type II with manufacturer’s standard TGIC polyester powder coat.

a. Color: To match Architect’s sample.

2.10 FINISHING

Whitfield Associates, Inc. 05500 - 5 Metal Fabrications Laguna Beach Lifeguard Headquarters May 25, 2012 A. Galvanize and prime paint exterior work and prime paint interior work unless otherwise noted in Schedule; comply with requirements of Section 09900 - Paints and Coatings for preparation and priming.

1. Galvanizing for rolled, pressed and forged steel shapes, plates, bars and strip and for assembled steel products: Zinc coating meeting the requirements of ASTM A123.

a. Provide coating comparable to ASTM A924 and A653, minimum G90 hot dip galvanized coating for steel sheets.

2. Galvanizing for iron and steel hardware: Zinc coating meeting the requirements of ASTM A153.

3. Thoroughly clean surfaces of rust, scale, grease and foreign matter prior to applying finish.

4. Shop Painting: Apply shop primer to surfaces of metal fabrications except those which are galvanized or indicated to be embedded in concrete or masonry, unless otherwise indicated.

a. Do not shop prime surfaces in contact with concrete or requiring field welding; shop prime in one coat.

PART 3 - EXECUTION

3.1 ERECTION

A. Obtain Architect's review prior to site cutting or making adjustments which are not part of scheduled work.

1. Perform necessary cutting and altering for installation and coordination with other work.

B. Install items square and level, accurately fitted and free from distortion or defects detrimental to appearance or performance.

1. Supply items requiring to be cast into or embedded in other materials to appropriate trades.

2. Ensure alignment with adjacent construction; coordinate with related work to ensure no interruption in installation.

C. Make provision for erection stresses by temporary bracing; keep work in alignment.

D. Field bolt and weld to match standard of shop bolting and welding; hide bolts and screws whenever possible, where not hidden, use flush countersunk fastenings.

1. Perform field welding in accordance with AWS D1.1.

E. After installation, touch-up field welds and scratched and damaged surfaces; use primer consistent with shop coat or recommended for galvanized surfaces, as applicable.

F. Replace items damaged in course of installation and construction.

Whitfield Associates, Inc. 05500 - 6 Metal Fabrications Laguna Beach Lifeguard Headquarters May 25, 2012 3.2 SCHEDULE

A. Supply and install metal fabrications listed in Schedule, complete with anchorage and attachments necessary for installation.

1. Schedule lists principal items only, refer to Drawing details for items not listed.

B. Schedule:

1. Miscellaneous angles, plates and attachments to be set in concrete or masonry for anchorage of other items.

2. Iron and steel shapes, sleeves, anchors, connectors and fastenings required to complete construction work, and which are not provided in other Specification sections.

a. Rough hardware, including bolts, fabricated plates, anchors, hangers, dowels and miscellaneous metals.

b. Ledge and shelf angles, channels and plates not attached to structural steel, and for support of metal decking.

c. Angle and channel frames for doors and wall openings.

d. Beams of structural shapes, not supported by structural steel.

3. Ladders and ladder extensions.

4. Steel bar gratings; galvanized finish.

5. Steel bollards.

6. Knox box.

END OF SECTION

Whitfield Associates, Inc. 05500 - 7 Metal Fabrications Laguna Beach Lifeguard Headquarters May 25, 2012

SECTION 07210 BUILDING INSULATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Thermal batt insulation with integral vapor retarder and accessories as required for complete installation.

B. Related Work:

1. Section 07815: Sprayed fireproofing. 2. Section 07840: Firestopping. 3. Section 09260: Acoustical insulation concealed in gypsum board systems.

1.2 SUBMITTALS

A. Product Data: Furnish manufacturer's literature for each type of insulation.

1. Indicate thermal insulation name and number as included in California Energy Commission's Directory of Certified Material.

2. Submit Underwriter's Laboratory approval numbers for required fire ratings; approvals of other laboratories contingent upon acceptance of applicable authorities.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Thermal Batt Insulation: Preformed slag mineral or glass fiber with thermosetting resin binders, conforming to ASTM C665.

1. Manufacturers:

a. USG Interiors, Inc.; Thermafiber FS25 Insulation. b. Johns Manville;FSK-25 Thermal-Shield Insulation. c. Owens-Corning Fiberglas Corp.; Fiberglas FS-25 Insulation. d. Substitutions: Refer to Section 01630.

2. R-Value: Minimum R-11 at walls, R-19 at horizontal surfaces, unless otherwise indicated on Drawings. Provide R-30 at underside of roof.

3. Flame Spread/Smoke Density Rating: Maximum 25/450, ASTM E84.

4. Vapor Retarder: Type III, aluminum vapor retarder on one side.

B. Penetration Type Insulation Supports: Galvanized or electroplated steel penetration supports with adhesive attachment to substrate and support disc.

Whitfield Associates, Inc. 07210 Building Insulation Laguna Beach Lifeguard Headquarters May 25, 2012 1. Manufacturers:

a. Eckel Industries Inc.; Stic-Klip. b. Miracle Adhesives; Stuk-Ups. c. G E M C O; Gemco Hanger System. d. Substitutions: Refer to Section 01630.

C. Vapor Retarder Tape: Minimum 2" wide self-adhering type designed to maintain vapor retarder integrity and complying with fire resistance ratings as required by applicable codes.

D. Accessories: Furnish as recommended by insulation manufacturer for insulation types, substrates, and conditions involved.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify substrate and adjacent materials are dry and ready to receive insulation; beginning installation signifies acceptance of conditions.

B. Ensure mechanical and electrical items affecting work are properly placed, complete, and have been inspected by Architect prior to commencement of installation.

3.2 INSTALLATION

A. Install insulation in accordance with manufacturer's instructions.

B. Cut and trim insulation neatly, to fit spaces.

1. Backed Insulation: Use insulation free of ripped backs and edges.

C. Fit insulation tight within spaces and tight to and behind mechanical and electrical services within insulation plane; leave no gaps or voids; maintain integrity of thermal barrier.

D. Friction fit in place; use tape or penetration supports as necessary to assure permanent installation.

2. Taping: Tape tears in vapor barrer.

3. Penetration Supports: Cut or bend pins in locations accessible to maintenance personnel, to eliminate potential hazards from exposed pin points.

END OF SECTION

Whitfield Associates, Inc. 07210 Building Insulation Laguna Beach Lifeguard Headquarters May 25, 2012

SECTION 08 45 23 2-3/4” INSULATED TRANSLUCENT FIBERGLASS SANDWICH PANEL SKYLIGHT SYSTEM

PART 1- GENERAL

1.1 SUMMARY

Section includes the insulated translucent sandwich panel skylight system and accessories as shown and specified. Work includes providing and installing:

A. ______factory prefabricated structural insulated translucent sandwich panels B. Aluminum installation system C. Aluminum flashing attached to skylights

Related Sections:

D. Structural Steel/Concrete/Rough Carpentry: E. Roofing: F. Flashing and Sheet Metal: G. Sealants: H. Glazing: SUBMITTALS

Submit manufacturer’s product data. Include construction details, material descriptions, profiles and finishes of skylight components.

Submit shop drawings. Include elevations and details.

Submit manufacturer's color charts showing the full range of colors available for factory-finished aluminum.

I. When requested, submit samples for each exposed finish required, in same thickness and material indicated for the work and in size indicated below. If finishes involve normal color variations, include sample sets consisting of two or more units showing the full range of variations expected.

Sandwich panels: 14” x 28” units Factory finished aluminum: 5” long sections

Submit Installer Certificate, signed by installer, certifying compliance with project qualification requirements.

Submit product reports from a qualified independent testing agency indicating each type and class of panel system complies with the project performance requirements, based on comprehensive testing of current products. Previously completed reports will be acceptable if for current manufacturer and indicative of products used on this project.

J. Reports required are:

International Building Code Evaluation Report

WHITFIELD ASSOCIATES, INC. 084523 FIBERGLASS SKYLIGHT SYSTEMS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012 Flame Spread and Smoke Developed (UL 723) – Submit UL Card Burn Extent (ASTM D 635) Color Difference (ASTM D 2244) Impact Strength (UL 972) Bond Tensile Strength (ASTM C 297 after aging by ASTM D 1037) Bond Shear Strength (ASTM D 1002) Beam Bending Strength (ASTM E 72) Fall Through Resistance (ASTM E 661) Insulation U-Factor (NFRC 100) NFRC System U-Factor Certification (NFRC 700) Solar Heat Gain Coefficient (NFRC or Calculations) Condensation Resistance Factor (AAMA 1503) Air Leakage (ASTM E 283) Structural Performance (ASTM E 330) Water Penetration (ASTM E 331) Class A Roof Covering Burning Brand (ASTM E 108) UL Listed Class A Roof System (UL 790) (Optional) – Submit UL Card LEED Credits Daylight Autonomy

QUALITY ASSURANCE

Manufacturer's Qualifications

K. Material and products shall be manufactured by a company continuously and regularly employed in the manufacture of specified materials for a period of at least ten consecutive years and which can show evidence of those materials being satisfactorily used on at least six projects of similar size, scope and location. At least three of the projects shall have been in successful use for ten years or longer. L. Panel system must be listed by an ANSI accredited Evaluation Service, which requires quality control inspections and fire, structural and water infiltration testing of sandwich panel systems by an accredited agency. M. Quality control inspections shall be conducted at least once each year and shall include manufacturing facilities, sandwich panel components and production sandwich panels for conformance with AC177 “Translucent Fiberglass Reinforced Plastic (FRP) Faced Panel Wall, Roof and Skylight Systems” as issued by the ICC-ES.

Installer’s Qualifications: Installation shall be by an experienced installer, which has been in the business of installing specified skylight systems for at least two consecutive years and can show evidence of satisfactory completion of projects of similar size, scope and type.

PERFORMANCE REQUIREMENTS

The manufacturer shall be responsible for the configuration and fabrication of the complete skylight panel system.

N. When requested, include structural analysis data signed and sealed by the qualified professional engineer responsible for their preparation. O. Standard skylight system shall have less than 0.01 cfm/ft² air leakage by ASTM E 283 at 6.24 PSF (50 mph) and no water penetration by ASTM E 331 at 15 PSF; and structural testing by ASTM E 330. P. Structural Loads; Provide skylight system capable of handling the following loads:

WHITFIELD ASSOCIATES, INC. 084523 FIBERGLASS SKYLIGHT SYSTEMS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012

Live Load: ______PSF Snow Load: ______PSF; Drift Load: ______PSF Wind Load: ______PSF

DELIVERY STORAGE AND HANDLING

Deliver panel system, components and materials in manufacturer's standard protective packaging.

Store panels on the long edge; several inches above the ground, blocked and under cover in accordance with manufacturer's storage and handling instructions.

WARRANTY

Submit manufacturer's and installer's written warranty agreeing to repair or replace panel system work, which fails in materials or workmanship within one year of the date of delivery. Failure of materials or workmanship shall include leakage, excessive deflection, deterioration of finish on metal in excess of normal weathering and defects in accessories, insulated translucent sandwich panels and other components of the work.

- PRODUCTS

MANUFACTURER

The basis for this specification is for products manufactured by Kalwall Corporation. Other manufacturers may bid this project provided they comply with all of the performance requirements of this specification and submit evidence thereof. Listing other manufacturers’ names in this specification does not constitute approval of their products or relieve them of compliance with all the performance requirements contained herein.

Kalwall Corporation, Tel: (800) 258-9777 – Fax: (603) 627-7905 – Email: [email protected]

PANEL COMPONENTS

Face Sheets

Q. Translucent faces: Manufactured from glass fiber reinforced thermoset resins, formulated specifically for architectural use.

Thermoplastic (e.g. polycarbonate, acrylic) faces are not acceptable. Face sheets shall not deform, deflect or drip when subjected to fire or flame.

R. Interior face sheets:

Flame spread: Underwriters Laboratories (UL) listed, which requires periodic unannounced retesting, with flame spread rating no greater than ______and smoke developed no greater than 250 when tested in accordance with UL 723. Burn extent by ASTM D 635 shall be no greater than 1”.

S. Exterior face sheets:

WHITFIELD ASSOCIATES, INC. 084523 FIBERGLASS SKYLIGHT SYSTEMS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012

Color stability: Full thickness of the exterior face sheet shall not change color more than 3 CIE Units DELTA E by ASTM D 2244 after ______years outdoor South Florida weathering at 5° facing south, determined by the average of at least three white samples with and without a protective film or coating to ensure long-term color stability. Color stability shall be unaffected by abrasion or scratching. Strength: Exterior face sheet shall be uniform in strength, impenetrable by hand held pencil and repel an impact minimum of ______ft. lbs. without fracture or tear when impacted by a 3-1/4” diameter, 5 lb. free-falling ball per UL 972.

T. Appearance:

Exterior face sheets: Smooth, ______thick and ______in color. Interior face sheets: Smooth, ______thick and ______in color. Face sheets shall not vary more than ± 10% in thickness and be uniform in color.

Grid Core

U. ______I-beam grid core shall be of 6063-T6 or 6005-T5 alloy and temper with provisions for mechanical interlocking of muntin-mullion and perimeter. Width of I-beam shall be no less than 7/16”. V. I-beam Thermal break: Minimum 1”, thermoset fiberglass composite.

Laminate Adhesive

W. Heat and pressure resin type adhesive engineered for structural sandwich panel use, with minimum 25-years field use. Adhesive shall pass testing requirements specified by the International Code Council “Acceptance Criteria for Sandwich Panel Adhesives”. X. Minimum tensile strength of 750 PSI when the panel assembly is tested by ASTM C 297 after two exposures to six cycles each of the aging conditions prescribed by ASTM D 1037. Y. Minimum shear strength of the panel adhesive by ASTM D 1002 after exposure to four separate conditions:

50% Relative Humidity at 68° F: 540 PSI 182° F: 100 PSI Accelerated Aging by ASTM D 1037 at room temperature: 800 PSI Accelerated Aging by ASTM D 1037 at 182° F: 250 PSI

PANEL CONSTRUCTION

Provide sandwich panels of flat fiberglass reinforced translucent face sheets laminated to a grid core of mechanically interlocking I-beams. The adhesive bonding line shall be straight, cover the entire width of the I-beam and have a neat, sharp edge.

Z. Thickness: 2-3/4” AA. Light transmission: ______% BB. Solar heat gain coefficient ______. CC. Panel U-factor by NFRC certified laboratory: 2-3/4” thermally broken grid ______OR 2-3/4” aluminum grid ______. DD. Complete insulated panel system shall have NFRC certified U-factor of _____. EE. Grid pattern: Nominal size ______; pattern ______.

WHITFIELD ASSOCIATES, INC. 084523 FIBERGLASS SKYLIGHT SYSTEMS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012 Standard panels shall deflect no more than 1.9” at 30 PSF in 10’ 0” span without a supporting frame by ASTM E 72.

Standard panels shall withstand 1200° F fire for minimum one hour without collapse or exterior flaming.

Thermally broken panels: Minimum Condensation Resistance Factor of 80 by AAMA 1503 measured on the bond line.

Skylight System:

FF. Skylight system shall pass Class A Roof Burning Brand Test By ASTM E 108. GG. (Optional) Skylight system shall be UL listed as a Class A Roof by UL 790, which requires periodic unannounced inspections and retesting by Underwriters Laboratories.

Skylight System shall meet the fall through requirements of OSHA 1910.23 as demonstrated by testing in accordance with ASTM E661, thereby not requiring supplemental screens or railings.

BATTENS AND PERIMETER CLOSURE SYSTEM

Closure system:

HH. Extruded aluminum 6063-T6 and 6063-T5 alloy and temper clamp-tite screw type closure system. II. Curved closure system may be roll formed. JJ. Skylight perimeter closures at curbs shall be factory sealed to panels.

Sealing tape: Manufacturer's standard, pre-applied to closure system at the factory under controlled conditions.

Fasteners: 300 series stainless steel screws for aluminum closures, excluding final fasteners to the building.

Finish:

KK. Manufacturer's factory applied finish, which meets the performance requirements of AAMA 2604. Color to be ______(selected from manufacturer's standards). LL. Mill (optional)

- EXECUTION

EXAMINATION

A. Installer shall examine substrates, supporting structure and installation conditions.

B. Do not proceed with panel installation until unsatisfactory conditions have been corrected.

PREPARATION

Metal Protection:

WHITFIELD ASSOCIATES, INC. 084523 FIBERGLASS SKYLIGHT SYSTEMS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012 MM. Where aluminum will contact dissimilar metals, protect against galvanic action by painting contact surfaces with primer or by applying sealant or tape recommended by manufacturer for this purpose. NN. Where aluminum will contact concrete, masonry or pressure treated wood, protect against corrosion by painting contact surfaces with bituminous paint or method recommended by manufacturer.

INSTALLATION

Install the skylight system in accordance with the manufacturer's installation recommendations and approved shop drawings.

OO. Anchor component parts securely in place by permanent mechanical attachment system. PP. Accommodate thermal and mechanical movements. QQ. Set perimeter framing in a full bed of sealant compound, or with joint fillers or gaskets to provide weather-tight construction.

Install joint sealants at perimeter joints and within the panel system in accordance with manufacturer's installation instructions.

FIELD QUALITY CONTROL

Water Test: Installer to test skylights according to procedures in AAMA 501.2.

Repair or replace work that does not pass testing or that is damaged by testing and retest work.

CLEANING

Clean the skylight system inside and outside, immediately after installation.

Refer to manufacturer's written recommendations.

END OF SECTION 08 45 23

WHITFIELD ASSOCIATES, INC. 084523 FIBERGLASS SKYLIGHT SYSTEMS LAGUNA BEACH LIFEGUARD HEADQUARTERS MAY 25, 2012

SECTION 08810 GLAZING

PART 1 GENERAL

1.1 SECTION INCLUDES

1. High performance architectural glass.

2. High performance architectural insulating glass.

1.2 RELATED SECTIONS

3. Section 08400 – Entrances and Storefronts: Exterior Entrances and Storefront.

4. Section 08500 - Windows: Exterior Windows.

5. Section 08900 – Glazed Curtainwall: Exterior Curtainwall.

1.3 REFERENCES

6. ANSI Z97.1 - American National Standard for Glazing Materials Used in Buildings - Safety Performance Specifications and Methods of Test.

7. ASCE 7 - "Minimum Design Loads for Buildings and Other Structures".

8. ASTM International (ASTM): a. ASTM C 162 – Standard Terminology of Glass and Glass Products. b. ASTM C 1036 - Standard Specification for Flat Glass. c. ASTM C 1048 - Standard Specification for Heat-Treated Flat Glass -- Kind HS, Kind FT Coated and Uncoated Glass. d. ASTM C 1172 – Standard Specification for Laminated Architectural Flat Glass. e. ASTM C 1376 - Standard Specification for Pyrolitic and Vacuum Deposition Coatings on Flat Glass. f. ASTM E 2188 - Standard Test Method for Insulating Glass Unit Performance. g. ASTM E 2189 – Standard Test Method for Testing Resistance to Fogging in Insulating Glass Units. h. ASTM E 2190 – Standard Specification for Insulating Glass Unit Performance and Evaluation.

1.4 DEFINITIONS

9. Manufacturers of Glass Products: Firms that produce primary glass, fabricated glass, or both, as defined in referenced glazing publications.

10. Glass Thicknesses: Indicated by thickness designations in millimeters according to ASTM C 1036.

11. Interspace: Space between lites of an insulating-glass unit that contains dehydrated air or other specified gas.

Whitfield Associates, Inc. 08810 Glazing Laguna Beach Lifeguard Headquarters May 25, 2012

12. Sealed Insulating Glass Unit Surface Designations: a. Surface 1 – Exterior surface of the outer glass lite. b. Surface 2 – Interspace surface of the outer glass lite. c. Surface 3 – Interspace surface of the inner glass lite. d. Surface 4 – Interior surface of the inner glass lite.

1.5 PERFORMANCE REQUIREMENTS

13. General: Provide glass capable of withstanding thermal movement and wind and impact loads (where applicable) as specified in paragraph B following.

14. Glass Design: Glass thickness designations indicated are minimums and are for detailing only. Confirm glass thicknesses by analyzing Project loads and in-service conditions. Provide glass lites in the thickness designations indicated for various size openings, but not less than thicknesses and in strengths (annealed or heat treated) required to meet or exceed the following criteria: a. Glass Thicknesses: Select minimum glass thicknesses to comply with ASTM E 1300, according to the following requirements: Design Wind Loads: Determine design wind loads applicable to the Project according to ASCE 7, "Minimum Design Loads for Buildings and Other Structures": Section 6.5, "Method 2-Analytical Procedure," based on mean roof heights above grade indicated on Drawings. a) Basic Wind Speed: ______mph. b) Importance Factor: ______. c) Exposure Category: ______. Specified Design Snow Loads: As indicated on Drawings, but not less than snow loads applicable to Project as required by ASCE 7, "Minimum Design Loads for Buildings and Other Structures": Section 7.0, "Snow Loads." Probability of Breakage for Vertical Glazing: ______lites per 1000 for lites set vertically or not more than 15 degrees off vertical. d) Wind Load Duration: Short duration, as defined in ASTM E 1300 or ______seconds or less. Probability of Breakage for Sloped Glazing: ______per 1000 for lites set greater than 15 degrees off vertical. e) Wind Load Duration: Short duration, as defined in ASTM E 1300 or ______seconds or less. f) Snow Load Duration: Long duration, as defined in ASTM E 1300 or ______days. Maximum Lateral Deflection: For the following types of glass supported on all 4 edges, provide thickness required that limits center deflection at design wind pressure to ______times the short side length or 1 inch, whichever is less. g) For monolithic-glass lites heat treated to resist wind loads. h) For insulating glass.

15. Thermal Movements: Provide glazing that allows for thermal movements resulting from ambient and surface temperatures changes acting on glass framing members and glazing components.

16. Thermal and Optical Performance Properties: Provide glass with performance properties specified based on manufacturer's published test data, as determined according to procedures indicated below: a. For monolithic-glass lites, properties are based on units with lites 1/4 inch (6.0 mm) thick.

Whitfield Associates, Inc. 08810 Glazing Laguna Beach Lifeguard Headquarters May 25, 2012 b. For insulating-glass units, properties are based on units of thickness indicated for overall unit and for each lite. c. Center-of-Glass Values: Based on using LBL-44789 WINDOW 5.0 computer program for the following methodologies: U-Factors: NFRC 100 expressed as Btu/ sq. ft. per h per degree F. Solar Heat Gain Coefficient: NFRC 200. Solar Optical Properties: NFRC 300.

1.6 SUBMITTALS

17. Submit under provisions of Section 01300.

18. Product Data: For each glass product and glazing material indicated.

19. Verification Samples: For the following products, in the form of 12 inch (305 mm) square samples for insulating glass units.

20. Glazing Schedule: Use same designations indicated on Drawings for glazed openings in preparing a schedule listing glass types and thicknesses for each size opening and location.

21. Product Certificates: Signed by manufacturers of glass and glazing products certifying that products furnished comply with requirements. a. For solar-control low-e-coated glass, provide documentation demonstrating that manufacturer of coated glass is certified by coating manufacturer.

22. Qualification Data: For installers.

23. Product Test Reports: For each of the following types of glazing products: a. Tinted float glass. b. Coated float glass. c. Insulating glass.

24. Warranties: Special warranties specified in this Section.

1.7 QUALITY ASSURANCE

25. Sustainable Design Certification: Glass shall be Cradle to Cradle certified, minimum Silver Level, by McDonough Braungart Design Chemistry, LLC.

26. Fabricator Qualifications: PPG Certified Fabricator Network, as acceptable to the manufacturer.

27. Installer Qualifications: An experienced installer who has completed glazing similar in material, design, and extent to that indicated for this Project; whose work has resulted in glass installations with a record of successful in-service performance; and who employs glass installers for this Project who are certified under the National Glass Association Glazier Certification Program as Level 2 (Senior Glaziers) or Level 3 (Master Glaziers).

28. Source Limitations for Glass: Obtain the following through one source from a single manufacturer for each glass type: clear float glass, coated float glass and insulating glass.

29. Glass Product Testing: Obtain glass test results for product test reports in "Submittals" Article from a qualified independent testing agency accredited according to the NFRC CAP 1 Certification Agency Program.

Whitfield Associates, Inc. 08810 Glazing Laguna Beach Lifeguard Headquarters May 25, 2012

30. Glazing Publications: Comply with published recommendations of glass product manufacturers and industry organizations, including but not limited to those below, unless more stringent requirements are indicated. Refer to these publications for glazing terms not otherwise defined in this Section or in referenced standards. a. IGMA Publication for Insulating Glass: SIGMA TM-3000, "Glazing Guidelines for Sealed Insulating Glass Units." b. GANA Publications: “Laminated Glazing Reference Manual”; “Glazing Manual.” c. AAMA: “Sloped Glazing Guidelines.” d. IGMA: “Guidelines for Sloped Glazing.”

31. Insulating-Glass Certification Program: Permanently marked either on spacers or on at least one component lite of units with appropriate certification label of the following testing and inspecting agency: a. Insulating Glass Certification Council. b. Associated Laboratories, Inc.

32. Safety Glazing Products: Comply with testing requirements in 16 CFR 1201 and, for wired glass, ANSI Z97.1. a. Subject to compliance with requirements, obtain safety glazing products permanently marked with certification label of the Safety Glazing Certification Council or another certification agency acceptable to authorities having jurisdiction. b. Lites more than 9 square feet (sf) (0.84 sq. m) in area are required to be Category II materials. c. Where glazing units, including Kind FT glass and laminated glass, are specified in Part 2 articles for glazing lites more than 9 sf in area, provide glazing products that comply with Category II materials, and for lites 9 sf. or less in area, provide glazing products that comply with Category I or II materials.

1.8 DELIVERY, STORAGE, AND HANDLING

33. Protect glazing materials according to manufacturer's written instructions and as needed to prevent damage to glass and glazing materials from condensation, temperature changes, direct exposure to sun, or other causes.

34. For insulating-glass units that will be exposed to substantial altitude changes, comply with insulating-glass manufacturer's written recommendations for venting and sealing to avoid hermetic seal ruptures.

1.9 WARRANTY

35. Manufacturer's Warranty for Coated-Glass Products: Manufacturer's standard form, made out to the glass fabricator in which the coated glass manufacturer agrees to replace coated glass units that deteriorates during normal use within the specified warranty period. Deterioration of the coated glass is defined as peeling and/or cracking, or discoloration that is not attributed to glass breakage, seal failure, improper installation, or cleaning and maintenance that is contrary to the manufacturer’s written instructions. a. Warranty Period: ______years from date of Substantial Completion.

36. Manufacturer's Warranty on Insulating Glass: Manufacturer's standard form in which the insulating glass unit manufacturer agrees to replace insulating-glass units that deteriorate during normal use within the specified warranty period. Deterioration of insulating glass units is defined as an obstruction of vision by dust, moisture, or a film on the interior

Whitfield Associates, Inc. 08810 Glazing Laguna Beach Lifeguard Headquarters May 25, 2012 surfaces of the glass caused by a failure of the hermetic seal that is not attributed to glass breakage, improper installation, or cleaning and maintenance that is contrary to the manufacturer’s written instructions. a. Warranty Period: ______years from date of Substantial Completion.

37. Manufacturer’s Warranty on Laminated Glass: Manufacturer’s standard form in which the laminated glass manufacturer agrees to replace laminated glass units that deteriorate during normal use within the specified warranty period. Deterioration of laminated glass is defined as defects, such as discoloration, edge separation, or blemishes exceeding those allowed by ASTM C 1172 that are not attributed to glass breakage, improper installation, or cleaning and maintenance that is contrary to the manufacturer’s written instructions. a. Warranty Period: ______years from date of Substantial Completion.

2.2 PRODUCTS

1.10 MANUFACTURERS

1. Acceptable Manufacturer: PPG Industries, Inc., Glass Group; Glass Business and Discovery Center., 400 Guys Run Rd., Cheswick, PA 15024. ASD. Toll Free Tel: (800) 377-5267. Fax: (800) 367-2986. Web: http://www.ppgglazing.com.

2. Substitutions: Not permitted.

3. Requests for substitutions will be considered in accordance with provisions of Section 01600.

1.11 GLASS PRODUCTS

4. Annealed Float Glass: ASTM C 1036, Type I (transparent flat glass), Quality-Q3; of class indicated.

5. Heat-Treated Float Glass: ASTM C 1048; Type I (transparent flat glass); Quality-Q3; of class, kind, and condition indicated. a. Fabrication Process: By horizontal (roller-hearth) process with roll-wave distortion parallel to bottom edge of glass as installed, unless otherwise indicated. b. Provide Kind HS (heat-strengthened) float glass in place of annealed float glass where needed to resist thermal stresses induced by differential shading of individual glass lites and to comply with glass design requirements specified in Part 1 "Performance Requirements" Article. c. For uncoated glass, comply with requirements for Condition A. d. For coated vision glass, comply with requirements for Condition C (other uncoated glass). e. Provide Kind FT (fully tempered) float glass in place of annealed or Kind HS (heat- strengthened) float glass where safety glass is indicated or required.

6. Pyrolitic-Coated Float Glass: ASTM C 1376, float glass with metallic-oxide coating applied by pyrolitic deposition process during initial manufacture, and complying with other requirements specified.

7. Sputter-Coated Float Glass: ASTM C 1376, float glass with metallic-oxide or -nitride coating deposited by vacuum deposition process after manufacture and heat treatment (if any), and complying with other requirements specified.

Whitfield Associates, Inc. 08810 Glazing Laguna Beach Lifeguard Headquarters May 25, 2012 8. Tempered Patterned Glass: ASTM C 1048, Kind FT (fully tempered), Type II (patterned flat glass), Class 1 (clear), Form 3 (patterned); and of quality, finish, and pattern specified.

9. Insulating-Glass Units, General: Factory-assembled units consisting of sealed lites of glass separated by a dehydrated interspace, and complying with ASTM E 774 for Class CBA units and with requirements specified in this Article and in Part 2 "Insulating-Glass Units" Article. a. Provide Kind HS (heat-strengthened) float glass in place of annealed glass where needed to resist thermal stresses induced by differential shading of individual glass lites and to comply with glass design requirements specified in Part 1 "Performance Requirements" Article. b. Provide Kind FT (fully tempered) glass lites where safety glass is indicated or required. c. Overall Unit Thickness and Thickness of Each Lite: Dimensions indicated for insulating-glass units are nominal and the overall thicknesses of units are measured perpendicularly from outer surfaces of glass lites at unit's edge. d. Sealing System: Comply with requirements in Section 07920 - Joint Sealants. Dual seal, with primary and secondary sealants of polyisobutylene and silicone. e. Spacer Specifications: Manufacturer's standard spacer material and construction complying with the following requirements: Spacer Material: Aluminum with mill or clear anodic finish. Desiccant: Molecular sieve or silica gel, or blend of both. Corner Construction: Manufacturer's standard corner construction.

1.12 FABRICATION OF GLAZING UNITS

10. Fabricate glazing units in sizes required to glaze openings indicated for Project, with edge and face clearances, edge and surface conditions, and bite complying with written instructions of product manufacturer and referenced glazing publications, to comply with system performance requirements.

1.13 UNCOATED INSULATING GLASS

1.14 LOW-E INSULATING GLASS

11. Type: Low-E Tinted Insulating Glass. Clear color, low-reflective glass outdoor appearance. a. Product: Clear + “Sungate®” 500 (3) Clear by PPG Industries, Inc. b. Insulating Unit Construction: 1/4 inch (6mm) Clear Glass, + 1/2 inch (13mm) air space + 1/4 inch (6mm) Clear (transparent) Float Glass “Sungate” 500 (Sputtered) Coated on third surface (3). c. Performance Values: Visible Light Transmission – 74 percent; SHGC – 0.65; Shading Coefficient – 0.75; Outdoor Visible Light Reflectance – 17 percent. d. Heat Transfer Coefficient: U-Value Winter – 0.35, U-Value Summer – 0.35.

12. Type: Low-E Tinted Insulating Glass. Sky blue color, low-reflective glass outdoor appearance. a. Product: “SolarblueTM” + “Sungate®” 500 (3) Clear by PPG Industries, Inc. b. Insulating Unit Construction: 1/4 inch (6mm) “Solarblue” Glass, + 1/2 inch (13mm) air space + 1/4 inch (6mm) Clear (transparent) Float Glass “Sungate” 500 (Pyrolitic) Coated on third surface (3).

Whitfield Associates, Inc. 08810 Glazing Laguna Beach Lifeguard Headquarters May 25, 2012 c. Performance Values: Visible Light Transmission – 46 percent; SHGC – 0.44; Shading Coefficient – 0.51; Outdoor Visible Light Reflectance – 10 percent. d. Heat Transfer Coefficient: U-Value Winter – 0.35, U-Value Summer – 0.35.

13. Type: Low-E Tinted Insulating Glass. Cool Gray color, low-reflective glass outdoor appearance. a. Product: “Solargray®” + “Sungate®” 400 (3) Clear by PPG Industries, Inc. b. Insulating Unit Construction: 1/4 inch (6mm) “Solargray” Glass, + 1/2 inch (13mm) air space + 1/4 inch (6mm) Clear (transparent) Float Glass “Sungate” 400 (Sputtered) Coated on third surface (3). c. Performance Values: Visible Light Transmission – 38 percent; SHGC – 0.38; Shading Coefficient – 0.44; Outdoor Visible Light Reflectance – 7 percent. d. Heat Transfer Coefficient: U-Value Winter – 0.32, U-Value Summer – 0.31.

2.3 EXECUTION

1.15 INSTALLATION

1. Refer to Section 08800 - Glazing for installation requirements.

END OF SECTION

Whitfield Associates, Inc. 08810 Glazing Laguna Beach Lifeguard Headquarters May 25, 2012

SECTION 09726 TACKABLE WALLCOVERING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: 1. Resilient cork/linoleum tackable wallcovering. 2. Accessories.

B. Related Divisions: 1. Division 09 91 23 Interior Painting: Priming for wallcoverings. 2. Division 09 72 16.13 Flexible Vinyl Wallcoverings. 3. Division 10 11 00 Visual Display Surfaces: Tackboards.

1.2 SUBMITTALS

A. Comply with Division 01 33 00. B. Product data indicating compliance with specified requirements. C. Installation Instructions. D. Samples: 7 inch (18 centimeter) by 9 inch (23 centimeter) samples of each type of tackable wallcovering material required.

1.3 QUALITY ASSURANCE

A. Surface Burning Characteristics Classification: Provide materials that meet classification ratings below: ASTM E84 (Flame Spread and Smoke Developed) II/B B. Single Source Responsibility: Obtain tackable wallcovering system components from a single source.

C. Deliver materials in original factory packaging, labeled with manufacturer, brand name, size, color, and lot number. D. Store materials in original, undamaged packaging inside a well-ventilated area protected from weather, moisture, soiling, and extreme temperatures. Maintain room temperature within the storage area at not less than 68 degrees Fahrenheit (20 degrees Celsius) during the period materials are stored. E. Mock-ups: Prepare mock-ups for architect's review and to establish requirements for seaming and finish trim. 1. Correct areas, modify method of application/installation, or adjust finish texture as directed by architect to comply with specified requirements. 2. Maintain mock-ups accessible to serve as a standard of quality. 3. Install sample panel of each type of wallcovering specified. 4. Install panels in areas designated by architect.

Whitfield Associates, Inc. 09726 Tackable Wallcovering Laguna Beach Lifeguard Headquarters April 23, 2012

1.4 PROJECT CONDITIONS

Maintain ambient temperature within the building at not less than 68 degrees Fahrenheit (20 degrees Celsius) for a minimum of seventy-two hours prior to beginning of installation. 1. Do not install tackable wallcovering until the space is enclosed and weatherproof. 2. Do not install tackable wallcovering until temperature is stabilized and permanent lighting is in place.

1.5 MAINTENANCE

Maintenance Instructions: Include precautions against cleaning materials and methods that may be detrimental to finishes and performance.

1.6 WARRANTY

Submit manufacturer's limited five-year written warranty against manufacturing defects.

PART 2 - PRODUCTS

2.1 PRODUCTS tac•wall® resilient, tackable, linoleum surface material. Width: 48 inch (122 centimeter). Gaug; 1/4 inch (6 millimeter). Approximately ± 95 lineal foot (29.1 meter) rolls. Flexible enough to bend around a 2-3/4 inch (7 centimeter) radius. Dimensionally stable due to burlap backing.

Walltalkers® tac•wall: Uni-color resilient homogeneous tackable linoleum surface consisting of linseed oil, granulated cork, rosin binders, and dry pigments calendered onto natural burlap backing. Color shall extend through thickness of material.

2.2 ACCESSORIES

A. Adhesive: Solvent-free, SBR type linoleum adhesive (L-910) or polyvinyl acetate dispersion type (contact adhesive) when used in a press. B. Color matched caulk:

C. ¼ inch aluminum trim for tac•wall E. Q-Pins: 1. WTQP-01: 24 Push Pins Translucent.

PART 3 - EXECUTION

3.1 EXAMINATION

Examine areas and conditions in which tackable wallcoverings will be installed. 1. Complete finishing operations, including painting, before beginning installation of tackable wallcovering materials.

Whitfield Associates, Inc. 09726 Tackable Wallcovering Laguna Beach Lifeguard Headquarters April 23, 2012

2. Wall surfaces to receive wallcovering materials shall be dry and free from dirt, grease, loose paint, and scale. 3. Notify the contractor and architect in writing of any conditions detrimental to the proper and timely completion of the installation. 4. Beginning of installation means acceptance of surface conditions.

3.2 PREPARATION

Surface Preparation: Remove hardware, accessories, plates, and similar items to allow tackable wallcovering to be installed. 1. Plaster surface: Remove surface chalk. In new work, use moisture meter to determine moisture content. Do not begin installation when moisture content is greater than five percent. 2. Gypsum board surface: Recess nails and screws. Repair irregular tape joints, sand and remove dust. 3. Painted surface: Remove loose paint or scale. Sand surface of enamel or gloss paint and wipe clean with damp cloth. 4. Ensure wall surfaces scheduled to receive tackable wallcovering are properly sealed with a quality primer specified for use under flexible vinyl wallcoverings.

3.3 APPLICATION

A. Comply with manufacturer's printed installation instructions. B. Cut sheets to size including a few inches of overage. Allow sheets to lay flat for at least twenty-four hours prior to the application. Mark roll direction and sequence on the backside of each sheet. Hang sheets in sequence as cut from the roll, do not reverse sheets. C. Permanent HVAC system should be set to 68 degrees Fahrenheit (20 degrees Celsius) for at least seventy-two hours prior to, during, and after the installation. D. Back roll each sheet prior to the installation to release curl memory. E. For seamed applications, using a seam and strip cutter remove the factory edge of one sheet. Using the same tool, overlap and trace cut the mating edge of the second sheet. Repeat this step for as many sheets as required for the job. F. Scribe, cut, and fit material to butt tightly to adjacent surfaces, built-in casework, and permanent fixtures and pipes. G. Apply adhesive with a 1/16 inch square notch trowel to the area to receiving the sheet (apply enough for one sheet at a time). H. Work from top to bottom then side to side. Roll sheet firmly into adhesive for positive contact and to remove air bubbles. I. Remove adhesive residue immediately after each panel is hung with a mild soap/water solution and a soft cloth/sponge.

3.4 CLEANING

A. Clean wallcovering using a sponge with a neutral pH cleaning solution. Do not use abrasive cleaners. Rinse thoroughly with water and let dry before using. B. It is important to remove adhesive while wet.

3.5 PROTECTION

Protect installed product and finish surfaces from damage during construction.

Whitfield Associates, Inc. 09726 Tackable Wallcovering Laguna Beach Lifeguard Headquarters April 23, 2012

END OF SECTION

Whitfield Associates, Inc. 09726 Tackable Wallcovering Laguna Beach Lifeguard Headquarters April 23, 2012

SECTION 09841 ACOUSTICAL WALL PANELS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Acoustical wall panels and installation components, complete.

1.2 REFERENCES

A. American Society for Test Methods (ASTM): 1. E 84 Test Method for Surface Burning Characteristics of Building Materials 2. C 423 Sound Absorption and Sound Absorption Coefficients by the Reverberation Room Method 3. E795 Standard Practices for Mounting Test Specimens During Sound Absorption Tests B. Scientific Certification Systems (SCS): 1. Environmental Certification Services, Recycled Content Standard 1.3 SUBMITTALS

A. Submittals: Submit listed submittals in accordance with Conditions of the Contract and Division 01 Submittal Procedures Section

B. Product Data: Submit manufacturer’s technical data and installation instructions for each typical of acoustical wall panel required. C. Samples: Submit 12 inch X 12 inch samples of specified acoustical wall panel featuring specified surface material, edge and corner detail and method of attachment. D. Certifications: Submit manufacturer's written product certification that all furnished wall panels meet or exceed the specification requirements. Include certified copies of tests specified when required. E. Shop Drawings: Submit elevation drawings showing wall panel layout, methods of attachment and installation details.

1.4 QUALITY ASSURANCE

A. Single-Source Responsibility: Provide acoustical panel units and installation components by a single manufacturer whose published product literature clearly indicates compliance of acoustical wall panels with specified requirements. B. Applicator: Installation by skilled applicators with no less than three years of documented experience installing acoustical wall panels of the types and extent specified for the project. C. Fire Performance Characteristics: 1. Surface Burning Characteristics: All panel components have a Class 1/A fire rating when tested in accordance with ASTM E 84. D. Mock-ups: 1. Install onsite mock-up equivalent to ______SF of wall panels in an area designated by the Architect. Replace unacceptable panels.

Whitfield Associates, Inc. 09841 Acoustical Wall Panels Laguna Beach Lifeguard Headquarters April 23, 2012

2. Approved mock-up panels will be used as the standard of performance for the project a and will be incorporated into the finished project.

1.6 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Delivery: Deliver acoustical wall panels to the project site in unbroken and undamaged original factory packaging and clearly labeled with the manufacturer's identification label, quality or grade.

B. Storage: Store materials in a clean, dry, climate controlled storage area within temperature and humidity ranges recommended by manufacturer. Provide protection from damage and exposure to harmful environmental conditions.

C. Acclimatization: Before installing acoustical wall panels, allow panels to acclimatize to room temperature and humidity.

D. Handling: Carefully handle acoustical wall panels to avoid soiling and damage.

1.7 PROJECT CONDITIONS

A. Environmental Conditions: 1. Do not apply acoustical treatments when surface and ambient temperatures are outside the temperature ranges required by the wall panel manufacturer. 2. Do not install acoustical panels until wet work such as concrete, plastering and painting is done and building is completely enclosed. 3. Provide continuous ventilation and heating facilities to maintain substrate surface and ambient temperatures above 60 degrees F unless required otherwise by manufacturer's instructions. 4. Maintain constant recommended temperature and humidity for at least 48 hours prior to, throughout the installation period and for 48 hours after panel installation completion. 5. Field Measurements: Check and verify actual wall surfaces by accurate field measurements before fabrication.

1.8 WARRANTY

A. Submit manufacturer’s 1 year written warranty against manufacturing defects from date of substantial completion.

1.9 MAINTENANCE

A. Replacement Materials: Provide full-size units equal to ______percent of each type ofacoustical wall panel installed for maintenance purposes. Furnish replacement materials fromthe same production run as installed materials. Protect material with clearly marked packagingindicating product identification and project location.

PART 2 – PRODUCTS

2.1 MANUFACTURERS

Whitfield Associates, Inc. 09841 Acoustical Wall Panels Laguna Beach Lifeguard Headquarters April 23, 2012

A. Acoustical Wall Panels: Sound Designs™, Koroseal Acoustical Treatments, Koroseal Interior Products Group, a Division of RJF International Corporation, Fairlawn, OH.

2.2 ACOUSTICAL WALL PANELS

A. Acoustical Wall Panels: 1. Product: Sound Designs™, Koroseal Acoustical Treatments 2. Surface Material: Provide material fully laminated to the fiberglass core face, edges and returned no less than 1-1/2” to the back of the panel to provide fully finished edges and tailored corners.

3. Provide panel surface materials as described below: See Drawings. Textile Surface Finish: Pattern: Color: Fabric Content: Fabric Width: Fabric Width: Perforated Vinyl Surface Finish: Pattern: Color: ______Acoustical Perforation: 18 % open area

a. Total Weight: 21ounces per linear yard. b. Backing Weight: 2.7 ounces per linear yard. c. Fabric backing and content: Poly-Cotton Osnaburg

3.1 EXAMINATION

A. Site Conditions: Do not proceed with installation until space is conditioned to meet manufacturer’s recommendations and all wet work is complete.

3.2 PREPARATION

A. Measure each wall area and establish layout of acoustical treatments. B. Assure equal border widths at opposite edges of each wall. C. Coordinate panel layout with mechanical and electrical fixtures.

3.3 INSTALLATION

A. Install wall panels by attaching the panels to an existing wall per the manufacturers written instructions, as shown on Drawings. B. Attach wall panels to the wall using RotoFast snap-on panel anchors C. All field fabricated edge details will be finished in accordance with manufacturer’s written Installation instructions.

3.4 CLEAN-UP COMPLETION

A. Clean exposed surfaces of acoustic wall panels that have become soiled during handling and installation according to manufacturer’s recommended cleaning instructions. C. Replace damaged panels.

Whitfield Associates, Inc. 09841 Acoustical Wall Panels Laguna Beach Lifeguard Headquarters April 23, 2012

D. Upon completion of the work, remove surplus materials, rubbish and debris resulting from the wallcovering installation. Leave areas in neat clean and orderly condition.

END OF SECTION

Whitfield Associates, Inc. 09841 Acoustical Wall Panels Laguna Beach Lifeguard Headquarters April 23, 2012

SECTION 099653 ELASTOMERIC COATINGS

PART 1 – GENERAL

1.01 Related Documents A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.02 Summary A. Section includes surface preparation and application of water-based, elastomeric waterprooffing coating.

1.03 Submittals A. Product Data: For each type of product indicated. B. Samples for Initial Selection: For each type of Wall coating indicated. C. Product List: For each product indicated, including the following: 1. Cross-reference to coating system and locations of application areas. Use same designations indicated on Drawings and in schedules. 2. Manufacturer's recommended spreading rate for each separate coat, including primers and block fillers for each type of substrate as applicable.

1.04 Quality Assurance A. Mockups: 1. Install at Project site or pre-selected area of building an area for field sample, minimum 4 feet by 4 feet (1.2m by 1.2m), using specified material. 2. Apply material in accordance with manufacturer’s written application instructions. 3. Manufacturer’s representative or designated representative will review technical aspects; surface preparation, repair, and workmanship. 4. Field sample will be standard for judging workmanship on remainder of Project. 5. Maintain field sample during construction for workmanship comparison. 6. Do not alter, move, or destroy field sample until Work is completed and approved by Owner. 7. Obtain Owners written approval of field sample before start of material application, including approval of aesthetics, color, texture, and appearance. 8. Perform adhesion test in accordance with ASTM D3359, Method A. Minimum adhesion rating of 4A required on 0 to 5 scale.

1.05 Delivery, Storage and Handling A. Store materials not in use in tightly covered containers in well-ventilated areas with ambient temperatures continuously maintained at not less than 45°F. 1. Maintain containers in clean condition, free of foreign materials and residue. 2. Remove rags and waste from storage areas daily.

1.06 Project Conditions A. Do not Apply coatings only when temperature of surfaces to be coated and ambient air temperatures are below 40° or expected to be below 40° within 24 hours after application. B. Do not apply coatings in snow, rain, fog, or mist; when relative humidity exceeds 85% or to damp or wet surfaces or when rain is expected within 24 hours of application.

Whitfield Associates, Inc. 099653 Elastomeric Coatings Laguna Beach Lifeguard Headquarters April 23, 2012

C. Allow wet surfaces to dry thoroughly and attain temperature and conditions specified before starting or continuing coating operation. D. Do not apply over moving cracks, control or expansion joints. E. Do not apply on Horizontal Surfaces that will receive traffic. F. Apply according to manufactures application instructions and recommendations.

1.07 Warranty A. Manufacturer's single source standard form warranting material within specified warranty period. Warranty Period: Five years from date of Substantial Completion.

Part 2 – PRODUCTS

2.01 Manufacturers: A. Provide products from the following manufacture: Tremco Commercial Sealants & Waterproofing

2.02 Ensure all Wall Coatings and Exterior Joint Sealants are provided from a single source.

2.03 Materials: A. Water-based, 100% acrylic waterproof coating. 1. Products: Subject to compliance with requirements, provide the following: a. Tremco; Vulkem TREMGard E b. Tremco; Vulkem TREMGard HB 2. Surface Profile: Smooth. 3. VOC Content: 100 g/L or less. B. Substitutions: Not Permitted.

2.04 Other Materials A. Crack Fillers: Wall coating manufacturer's recommended crack fillers or sealants, including crack filler primers, compatible with substrate and other materials indicated; VOC content complying with limits of authorities having jurisdiction. B. Joint Sealants: Single or multi-component polyurethane sealants, supplied by coating manufacturer. 1. Dymonic FC 2. Dymeric 240FC 3. Spectrem 1 4. Spectrem 2 5. Spectrem 3 6. Spectrem 4-TS C. Primer: Wall coating manufacturer's recommended, factory-formulated, alkali-resistant primer compatible with substrate and other materials indicated. 1. TREMGard H/P Primer D. Concrete Unit Masonry Block Filler: Elastomeric coating manufacturer's recommended, factory-formulated, high-performance latex block filler compatible with substrate and other materials indicated. 1. VOC Content: 100 g/L or less. 2. TREMGard Masonry Primer.

Part 3 – EXECUTION

3.01 Examination

Whitfield Associates, Inc. 099653 Elastomeric Coatings Laguna Beach Lifeguard Headquarters April 23, 2012

A. Protection: Protect adjacent Work areas and finish surfaces from damage during coating application. B. Prepare surfaces in accordance with manufacturer’s instructions. C. Ensure that substrate is sound, clean, dry, and free of dust, dirt, oils, grease, laitance, efflorescence, mildew, fungus, biological residues, and other contaminants that could prevent proper adhesion. D. Ensure concrete substrates have a minimum 28-day cure and are free of bond-inhibiting contaminants. E. Clean surface to achieve texture similar to medium grit sandpaper. F. Repair holes and spalled and damaged concrete with repair materials approved by coating manufacturer. G. Remove protruding concrete accessories and smooth out irregularities. H. When chemical cleaners are utilized, neutralize compounds and fully rinse surface with clean water. Allow surface to dry before proceeding. I. Remove blisters and delaminated areas and sand edges to smooth rough areas and provide transition to existing paint areas. J. Check adhesion of existing paint in accordance with ASTM D 3359, measuring adhesion by Tape Method A. K. Treat cracks greater than 1/32 inch (0.8mm) with approved patching compound or Approved Tremco Sealant. L. Treat cracks greater than 1/4 inch (6mm) as expansion joints and fill with sealant approved by coating manufacturer. M. Prepare and treat cracks in accordance with manufacturer’s instructions.

3.02 Preparation A. Comply with manufacturer's written instructions applicable to substrates and coating systems indicated.

3.03 Application A. Apply coatings according to manufacturer's written instructions per the project. 1. Use equipment and techniques best suited for substrate and type of material being applied. 2. Coat surfaces behind movable items the same as similar exposed surfaces. 3. Apply as a 2 coat system according to manufacturer's written instructions 4. Maintain proper uniform wet-film thickness during application to ensure performance characteristics desired. 5. Apply coating using consistent application techniques to achieve uniform color and texture. B. Primers: Apply at a rate to ensure complete coverage. C. Block Fillers: Apply at a rate to ensure complete coverage with pores filled. D. Mixing: Mix coating in accordance with manufacturer’s instructions to ensure uniform color and aggregate disbursement and to minimize air entrapment. E. In multi-pail applications, mix contents of each new pail into partially used pail to ensure color consistency and smooth transitions from pail to pail.

3.04 Cleaning and Protection A. At end of each workday, remove rubbish, empty cans, rags, and other discarded materials from Project site.

Whitfield Associates, Inc. 099653 Elastomeric Coatings Laguna Beach Lifeguard Headquarters April 23, 2012

END OF SECTION

Whitfield Associates, Inc. 099653 Elastomeric Coatings Laguna Beach Lifeguard Headquarters April 23, 2012

SECTION 10500 LOCKERS

Part 1 – General

1.01 Submittals

A. Shop Drawings: Drawings supplied detailing locker parts and assembly along with layout indicating dimensions and installation procedure to cover all situations.

1.02 Product Handling

A. Storage: Lockers will be protected and stored in a suitable environment.

B. Delivery: Assembled lockers to be delivered when installation area is complete and watertight.

Part 2 – Products

2.01 Components

A. Locker body: Tops, bottoms, sides and shelves to be constructed from ¾” Marine plywood with abrasion, stain and impact resistant white Melamine. Backs of the same material using a ½” thickness.

B. Edge banding: All exposed edges to be banded with matching PVC, or Wood Veneer.

C. Hooks: Single or double pronged side-hooks available in either brass, nickel plated or chrome.

D. Hinges: Piano Hinges, self-closing hinges.

E. Locks: Heavy-duty cam lock with 2 keys each. Master built-in combination, coin operated card key, push button and pad lock hasps are also available.

F. Ventilation: Perimeter ventilation through 3/16” opening between tops, bottoms, sides and door.

G. Doors and End Panels:

1. ¾” Marine plywood door with a high-pressure laminate applied to both sides. Exposed sides edge- banded to match.

2. Not Used

3. ¾” flat panel veneer door with exposed edges banded to match.

4. ¾” end panels to match door style supplied.

H. Finish: All wood components supplied with one coat of sealer and two coats of clear lacquer. Optional stains available.

I. Number/Name Plates: 1 /12” round number disks available in brass, chrome or brushed aluminum, inlaid flush with door.

Whitfield Associates, Inc. 10500 Lockers Laguna Beach Lifeguard Headquarters May 25 2012 2.02 Fabrication:

A. Fabricate lockers rigid, square and without warp with finished surfaces flat and free from chips.

B. Machine all parts and holes accurately and mechanically fasten for tight joints and connections.

C. Supply matching fillers as required for proper installation.

D. Submit shop drawings in AutoCAD format to project manager and architect for review prior to fabrication.

Part 3 – Execution

3.01 Installation:

A. Lockers to be installed in accordance with manufacturers instructions. Units must be level, plumb and rigid with faces flush. Units to be connected together through pre-drilled holes and anchored to base and walls as directed.

B. Adjust all doors and hinges for proper operation.

C. Attach number plates in sequence as requested.

Part 4 – Warranty

All wood parts shall be structurally sound and free from defects in materials and workmanship under normal use and conditions for a period of five (5) years from the date of delivery. All locks carry a one (1) year manufacturer’s warrantee. Heavy-duty, rust-proof hinges offer a manufacturer’s lifetime guarantee.

END OF SECTION

Whitfield Associates, Inc. 10500 Lockers Laguna Beach Lifeguard Headquarters May 25 2012

SECTION 14240 HYDRAULIC ELEVATOR

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes hydraulic passenger elevators.

B. See Division 9 Section for finish flooring in elevator cars.

1.2 SUBMITTALS

A. Product Data: Include capacities, sizes, performances, operations, safety features, finishes, and similar information for each elevator required.

B. Shop Drawings: Show plans, elevations, sections, and large-scale details indicating service at each landing, machine room layout, relationships with other construction, and locations of equipment and signals. Indicate maximum and average power demands.

C. Samples: For each exposed finish.

D. Manufacturer Certificates: Signed by elevator manufacturer certifying that hoistway, pit, and machine room layout and dimensions, as shown on Drawings, and electrical service, as shown and specified, are adequate for elevator system being provided.

E. Maintenance manuals.

F. Inspection and Acceptance Certificates and Operating Permits: As required by authorities having jurisdiction for normal, unrestricted elevator use.

1.3 QUALITY ASSURANCE

A. Regulatory Requirements: Comply with local governing regulations and with applicable provisions in ASME A17.1, "Safety Code for Elevators and Escalators."

1. Project's Seismic Risk Zone: [3 or greater].

B. Accessibility Requirements: In addition to local governing regulations, comply with [Section 4.10 in the U.S. Architectural & Transportation Barriers Compliance Board's "Americans with Disabilities Act (ADA).

1.4 MAINTENANCE SERVICE

A. Initial Maintenance Service: Beginning at Substantial Completion, provide [12] months' full maintenance service. Include monthly preventive maintenance, repair or replacement of worn or defective components, lubrication, cleaning, and adjusting.

Whitfield Associates, Inc. 14240 Hydraulic Elevators Laguna Beach Lifeguard Headquarters May 25, 2012

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering hydraulic elevators that may be incorporated into the Work include, but are not limited to, the following:

B. Manufacturers: Subject to compliance with requirements, provide hydraulic elevators by one of the following: 1. Thyssen Elevator Group North America.

2.2 MATERIALS AND COMPONENTS

A. General: Provide manufacturer's standard elevator systems, published by manufacturer as included in standard preengineered elevator systems and as required for a complete system.

B. Pump Units: Positive-displacement type with a maximum of 10 percent variation between no load and full load and with minimum pulsations.

1. Pump: [Mounted on top of oil tank with vibration isolation mounts and enclosed in prime-painted steel enclosure lined with 1-inch- (25-mm-) thick, glass-fiber insulation board] [Submersible, suspended inside tank from vibration isolation mounts] [Mounted on top of oil tank with vibration isolation mounts and enclosed in prime-painted steel enclosure lined with 1-inch- (25-mm-) thick, glass-fiber insulation board or submersible, suspended inside tank from vibration isolation mounts]. 2. Motor Starting: [Wye delta or solid state].

C. Hydraulic Silencers: Containing pulsation-absorbing material in a blowout-proof housing at pump unit.

D. Protective Cylinder Casings: PVC pipe casings complying with ASME A17.1, of sufficient size to provide not less than 1-inch (25-mm) clearance from cylinder, and extending above pit floor.

E. Protective Cylinder Coating: Two or more layers of PVC tape with a total thickness not less than 0.040 inches (1.0 mm)[or other coating complying with ASME A17.1].

F. Car Frame and Platform: Welded steel units.

G. Finish Materials:

1. Satin Stainless Steel: ASTM A 666, Type 304, with No. [4, directional] [6, nondirectional] satin finish. 2. Enameled-Steel Sheet: Cold-rolled steel sheet complying with ASTM A 366/A 366M, matte finish, stretcher-leveled standard of flatness; hot-rolled steel sheet complying with ASTM A 569/A 569M may be used for door frames. Provide with factory-applied enamel finish.

a. Colors: [As selected from manufacturer's full range]

3. Prime-Painted Steel Sheet: Cold-rolled steel sheet, ASTM A 366/A 366M, or hot-rolled steel sheet, ASTM A 569/A 569M, with factory-applied rust-inhibitive primer.

Whitfield Associates, Inc. 14240 Hydraulic Elevators Laguna Beach Lifeguard Headquarters May 25, 2012

4. Plastic Laminate: High-pressure type complying with NEMA LD 3, Type HGS.

a. Colors, Textures, and Patterns: [As selected from manufacturer's full range]

2.3 OPERATION SYSTEMS

A. Provide manufacturer's standard microprocessor operation system of the type indicated.

1. Single Elevator, Two Stops: Provide "automatic operation" as defined in ASME A17.1. 2. Single Elevator: Provide "selective collective automatic operation" as defined in ASME A17.1. 3. Multiple-Car Group: Provide "group automatic operation" as defined in ASME A17.1.

B. Auxiliary Operations:

1. Standby Powered Lowering: On activation of standby power, cars are lowered to the lowest floor, open their doors, and shut down. 2. Battery-Powered Lowering: When power fails, cars are lowered to the lowest floor, open their doors, and shut down. System includes rechargeable battery and automatic recharging system. 3. Emergency Hospital Service: Service is initiated by a keyswitch at designated floors. One elevator is removed from group operation and directed to the floor where service was initiated. Car is placed in operation by selecting a floor and pressing door close button or by operating keyswitch to put car in independent service. After responding to floor selected or being removed from independent service, car is returned to group operation. 4. Independent Service: Keyswitch in car control station removes car from group operation and allows it to respond only to car calls. Key cannot be removed from keyswitch when car is in independent service.

C. Security Features: Security features do not affect emergency firefighters' service.

1. Secured Landing Feature: Allows each landing to be secured or cleared. If landing is secured, car buttons for that landing do not register a call unless landing access code is entered within a predetermined time period after landing button is pressed. Access codes are programmed at each car operating panel using a security keyswitch. Secured landing feature is activated and deactivated by a security keyswitch at the main landing. 2. Car-to-Lobby Feature: Feature, activated by a keyswitch at main lobby, that causes all cars in a group to return immediately to lobby and open doors for inspection. On deactivation by keyswitch, cars complete calls registered before keyswitch activation and resume normal operation. 3. Card-Reader Operation: For access to restricted landings based on security system provided by others. Provide required conductors in traveling cable and panel in machine room for interconnecting card readers, other security access system equipment, and elevator controllers. Allow space in car as indicated for card reader.

2.4 SIGNAL EQUIPMENT

A. General: Satin stainless-steel signal equipment with hall-call and car-call buttons that light when activated and remain lit until call has been fulfilled. Fabricate lighted elements of acrylic or other permanent, nonyellowing translucent plastic.

Whitfield Associates, Inc. 14240 Hydraulic Elevators Laguna Beach Lifeguard Headquarters May 25, 2012

B. Car Control Stations: Manufacturer's standard car control stations mounted in return panel adjacent to car door, unless otherwise indicated.

C. Emergency Communication System: Complying with ASME A17.1 and the U.S. Architectural & Transportation Barriers Compliance Board's "Americans with Disabilities Act (ADA), Accessibility Guidelines (ADAAG)." On activation, system dials preprogrammed number of monitoring station and identifies elevator location to monitoring station. System provides two- way voice communication without using a handset and provides visible signals that indicate when system has been activated and when monitoring station has responded. System is contained in flush-mounted cabinet, with identification, instructions for use, and battery backup power supply.

D. Fire Department Communication System: [Flush-mounted cabinet] [Telephone jack] in each car and required conductors in traveling cable for fire department communication system specified in Division 16 Sections.

E. Car Position Indicator: Locate above car door or above car control station and include audible signal to indicate to passengers that car is either stopping at or passing each of the floors served.

1. Include travel direction arrows if not included in car control station.

F. Hall Push-Button Stations: Locate at each landing for each elevator or group of elevators as indicated.

G. Hall Lanterns: Units with illuminated arrows.

1. With each lantern, include audible signals. Signals sound once for up and twice for down.

H. Hall Position Indicators: Locate above each hoistway entrance at ground floor.

I. Corridor Call Station Pictograph Signs: Matching hall push-button stations with text and graphics according to ASME A17.1, Appendix H.

2.5 DOOR REOPENING DEVICES

A. Infrared Array: Uniform array of 36 or more microprocessor-controlled, infrared light beams projecting across car entrance. Interruption of one or more of the light beams causes doors to stop and reopen.

2.6 ELEVATOR CAR ENCLOSURES

A. General: Provide manufacturer's standard [enameled-steel car enclosures with removable wall panels], suspended ceiling, trim, accessories, access doors, doors, power door operators, sills (thresholds), lighting, and ventilation.

1. Floor Finish: [As specified in another Section] 2. Metal Wall Panels: Flush hollow-metal construction, fabricated from metal indicated. 3. Plastic-Laminate Wall Panels: Plastic laminate adhesively applied to 1/2-inch (13-mm) fire-retardant-treated particleboard with manufacturer's standard protective edge trim. 4. Fabricate car with recesses and cutouts for signal equipment. 5. Fabricate car door frame integrally with front wall of car.

Whitfield Associates, Inc. 14240 Hydraulic Elevators Laguna Beach Lifeguard Headquarters May 25, 2012

6. Enameled-Steel Doors: Flush, hollow-metal construction. 7. Stainless-Steel Doors: Flush, hollow-metal construction, fabricated from stainless steel. 8. Plastic-Laminate Doors: Flush, hollow-metal, prime-painted-steel doors, faced with plastic laminate; with manufacturer's standard protective edge trim. 9. Sills: Extruded aluminum, with grooved surface, 1/4 inch (6.4 mm) thick. 10. Luminous Ceiling: Fluorescent light fixtures and ceiling panels of translucent acrylic or other permanent rigid plastic complying with flammability requirements. 11. Handrails: Manufacturer's standard metal handrails.

2.7 HOISTWAY ENTRANCES

A. General: Manufacturer's standard horizontal-sliding, door-and-frame hoistway entrances complete with track systems, hardware, sills, and accessories.

1. Where gypsum board wall construction is indicated, provide self-supporting frames with reinforced head sections. 2. Stainless-Steel Frames: Formed stainless-steel sheet. 3. Enameled-Steel Doors[and Transoms]: Flush, hollow-metal construction. 4. Stainless-Steel Doors[and Transoms]: Flush, hollow-metal construction, fabricated from stainless steel. 5. Plastic-Laminate Doors[and Transoms]: Flush, prime-painted-steel, hollow-metal construction, faced with plastic laminate; with manufacturer's standard protective edge trim. 6. Sills: Extruded aluminum, with grooved surface, 1/4 inch (6.4 mm) thick. 7. Nonshrink, Nonmetallic Grout: Factory-packaged, nonstaining, noncorrosive, nongaseous grout complying with ASTM C 1107.

2.8 ELEVATORS

1. a. Front Walls: [Satin stainless] steel with integral car door frames. b. Side and Rear Wall Panels: [Plastic laminate] c. Door Faces (Interior): [Plastic laminate].

2. Hoistway Entrances:

a. Width: [42 inches (1067 mm)] b. Height: 84 inches (2134 mm). c. Type: [Single-speed side sliding] d. Frames:

1) First Floor: [Satin stainless] steel. 2) Other Floors: [Satin stainless] steel.

e. Doors[and Transoms]:

1) First Floor: [Plastic laminate].

Whitfield Associates, Inc. 14240 Hydraulic Elevators Laguna Beach Lifeguard Headquarters May 25, 2012

2) Other Floors: [Plastic laminate].

3. Additional Requirements:

a. Provide inspection certificate in each car, mounted under acrylic cover with satin stainless-steel frame.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Excavation for Jack: Drill excavation in each elevator pit to accommodate installation of cylinders; comply with applicable requirements in Division 2 Section "Earthwork."

1. Provide [waterproof well casings] to retain walls of well hole.

B. Install cylinders in protective casings within well [holes or casings] after removing water and debris [and providing a permanent waterproof seal at bottom of well casing].

1. Align cylinders and fill space between well casing and protective casing with fine sand.

C. Install cylinders in well [holes or casings] after removing water and debris[and provide permanent waterproof seal at bottom of casing].

1. Align cylinder and fill void space with fine sand.

D. Install cylinders plumb and accurately centered for elevator car position and travel. Anchor securely in place, supported at pit floor. Seal between [well casing, protective casing, or cylinder] and pit floor with 4 inches (100 mm) of nonshrink, nonmetallic grout.

E. Leveling Tolerance: 1/4 inch (6 mm), up or down, regardless of load and direction of travel.

F. Set sills flush with finished floor surface at landing. Fill space under sill solidly with nonshrink, nonmetallic grout.

3.2 FIELD QUALITY CONTROL

A. Acceptance Testing: On completion of elevator installation and before permitting use (either temporary or permanent) of elevators, perform acceptance tests as required and recommended by ASME A17.1 and by governing regulations and agencies.

3.3 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain elevators. Review emergency provisions and train Owner's personnel in procedures to follow in identifying sources of operational failures or malfunctions. Refer to Division 1 Section "[Closeout Procedures]”

Whitfield Associates, Inc. 14240 Hydraulic Elevators Laguna Beach Lifeguard Headquarters May 25, 2012

3.4 PROTECTION

A. Temporary Use: Do not use elevators for construction purposes unless cars are provided with temporary enclosures, either within finished cars or in place of finished cars, to protect finishes from damage.

1. Provide full maintenance service by skilled, competent employees of elevator Installer for elevators used for construction purposes.

END OF SECTION

Whitfield Associates, Inc. 14240 Hydraulic Elevators Laguna Beach Lifeguard Headquarters May 25, 2012