Public Sector Development Programme (Sectorwise) 2014 - 15 Original
06-18-2014 1 of 162 Public Sector Development Programme (Sectorwise) 2014 - 15 Original
Chapter: AGRICULTURE Sector: Agriculture Subsector: Agricultural Extension Estimated Cost Exp: Upto June 2014 Fin: Allocation 2014-15 Fin: Thr: Fwd:
S No Project ID Project Name GOB / Total GOB / Total Achv: Capital/ Revenue Total Target GOB / FPA FPA FPA % FPA % Ongoing
1 Z2004.0083 CONST: OF MARKET SQUARES 187.881 187.881 140.456 140.456 74% 10.000 0.000 10.000 80% 37.425 Provincial AT LORALAI, K. SAIFULLAH, 0.000 0.000 0.000 0.000 Approved PISHIN, LASBELA, PANJGUR & KHUZDAR. 2 Z2008.0015 MIRANI DAM COMMAND AREA 150.000 150.000 105.000 105.000 70% 10.000 0.000 10.000 76% 35.000 Kech DEVELOPMENT PROJECT. 0.000 0.000 0.000 0.000 Approved
3 Z2008.0016 SABAKZAI DAM COMMAND AREA 134.500 134.500 119.519 119.519 88% 14.981 0.000 14.981 100% 0.000 Zhob DEVELOPMENT PROJECT. 0.000 0.000 0.000 0.000 Approved
4 Z2013.0187 AGRICULTURE DEVELOPMENT 19.100 19.100 0.000 0.000 0% 5.000 0.000 5.000 26% 14.100 Pishin SCHEME FOR WATER 0.000 0.000 0.000 0.000 Approved RESOURCE MANAGEMENT IN DIST. PISHIN. 5 Z2013.0195 AGRICULTURE DEVELOPMENT 30.100 30.100 0.000 0.000 0% 10.000 0.000 10.000 33% 20.100 Qilla SCHEME FOR WATER 0.000 0.000 0.000 0.000 Abdullah RESOURCE MANAGEMENT IN Approved DIST. KILLA ABDULLAH. 6 Z2013.0196 AGRICULTURE DEVELOPMENT 12.290 12.290 0.000 0.000 0% 5.000 0.000 5.000 40% 7.290 Loralai SCHEME FOR WATER 0.000 0.000 0.000 0.000 Approved RESOURCE MANAGEMENT IN DIST. LORALAI. 7 Z2013.0345 INSTALATION OF SPRINKLER 0.650 0.650 0.000 0.000 0% 0.650 0.000 0.650 100% 0.000 Quetta