BEUP Schemes of 16TH Bidhansabha 2016 to 2021

Upto July-2021 Sl. No. Name of A.C. Sl. No. Name of A.C.

1 259- (SC)A.C 9 267- A.C

2 260- DAKSHIN A.C 10 268- DAKSHIN A.C

3 261-RAINA (SC) A.C 11 269-PURBASTHALI UTTAR A.C

4 262-JAMALPUR (SC)A.C 12 270- A.C

5 263- A.C 13 271- A.C

6 264-KALNA (SC) A.C 14 272- A.C

7 265- A.C 15 273-AUSGRAM (SC) A.C

8 266-BARDHAMAN UTTAR (SC) A.C 16 274-GALSI (SC) A.C

2 Assets Handover Status Report

Sl. Completed AHS AHS Sl. Completed AHS AHS Name of A.C. Name of A.C. No. Scheme Received Pending No. Scheme Received Pending

259-KHANDAGHOSH (SC) 1 36 34 2 9 267-BHATAR A.C 26 25 1 A.C 260-BARDHAMAN DAKSHIN 268-PURBASTHALI 2 31 0 31 10 31 16 15 A.C DAKSHIN A.C 269-PURBASTHALI UTTAR 3 261-RAINA (SC) A.C 60 48 12 11 74 52 22 A.C

4 262-JAMALPUR (SC)A.C 56 7 49 12 270-KATWA A.C 82 82 0

5 263-MONTESWAR A.C 89 41 48 13 271-KETUGRAM A.C 45 37 8

6 264-KALNA (SC) A.C 41 30 11 14 272-MONGALKOTE A.C 24 0 24

7 265-MEMARI A.C 53 23 30 15 273-AUSGRAM (SC) A.C 49 36 13

266-BARDHAMAN UTTAR 8 35 25 10 16 274-GALSI (SC) A.C 44 37 7 (SC) A.C 3 Shri Nabin Chandra Bag Hon’ble M.L.A. of 259- Khandaghosh (SC) AC

4 COMPLETED SCHEMES

5 NABIN CHANDRA BAG, HON'BLE MLA-259 KHANDAGHOSH (SC) A.C.

UC Sl. Sanction Date of Amount Amount Amount Physical Asset Handover Name of the Scheme Year Executing Agency Submit No. Order No Sanction Sanction Released Utilized Progress Status ted

Constn. of Open Stage at 2016 - Executive Officer, 1 Mogalisima Hat Tala F.P. 2769/DP 28/11/2016 450000 420161 420161 100 Yes 2017 Galsi- II P.S. School

Constn. of Samsan Shed at 2016 - Executive Officer, 2 180/DP 16/01/2017 300000 276676 276676 100 Yes Punia under Khandagosh 2017 Khandaghosh P.S. Instn of Solar Light of 18 2016 - Executive Officer, Asset Handover 3 180/DP 16/01/2017 200000 184800 184800 100 Yes watt at Khandagosh BPHC 2017 Khandaghosh P.S. Report Received as per the Clause No. Constn. of Shed at 2016 - Executive Officer, 8 under updated 4 Nischintapur Kabarsthan 180/DP 16/01/2017 400000 400000 400000 100 Yes 2017 Khandaghosh P.S. BEUP Guidelines under Khandagosh 2019 Constn. of Samsan Shed at 2016 - Executive Officer, 5 180/DP 16/01/2017 300000 289871 289871 100 Yes Khandagosh Tantipara 2017 Khandaghosh P.S. Constn. of Samsan Chulli at 2016 - Executive Officer, 6 180/DP 16/01/2017 480000 471026 471026 100 Yes under Khandagosh 2017 Khandaghosh P.S. Constn. of Swasan Shed and 2016 - Executive Officer, 7 234/DP 18/01/2017 650000 560889 560889 100 Yes Chully at Gopal Bera 2017 Khandaghosh P.S. Constn. of Concrete road of 2016 - Executive Officer, 8 283/DP 29/01/2017 150000 140000 140000 100 Yes Khandagosh Girls School 2017 Khandaghosh P.S.

6 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn. of Culvert at Sankhari on 2016 - Executive Officer, 9 approach road of Sankari Boys 798/DP 15/03/2017 800000 800000 800000 100 Yes 2017 Khandaghosh P.S. High School Constn. of Drain from Berugram 2016 - Executive Officer, 10 road to Khandagosh Tanti Para 798/DP 15/03/2017 300000 300000 300000 100 Yes 2017 Khandaghosh P.S. F.P. School Constn. of Samsan Shed and 2016 - Executive Officer, 11 Chully at Saranga village of 798/DO 15/03/2017 650000 613352 613352 100 Yes 2017 Khandaghosh P.S. G.P. Asset Handover Constn. of Samsan Shed at 2016 - Executive Officer, Report Received as 12 798/DP 15/03/2017 320000 312589 312589 100 Yes Paharpur of Sagrai G.P. 2017 Khandaghosh P.S. per the Clause No. 8 under updated BEUP Guidelines Constn. of Atchala at Madhpur 2016 - Executive Officer, 13 798/DP 15/03/2017 500000 496785 496785 100 Yes 2019 village of sagrai G.P. 2017 Khandaghosh P.S.

Constn. of Atchala at Ghosh Para 2016 - Executive Officer, 14 904/DP 22/03/2017 250000 190472 190472 100 Yes of Bhuri G.P. 2017 Galsi- II P.S.

Constn. of Atchala at Jahanpur 2016 - Executive Officer, 15 904/DP 22/03/2017 250000 170407 170407 100 Yes Paschim Hattala of Bhuri G.P. 2017 Galsi- II P.S.

Total 6000000 5627028 5627028

7 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn. of Boitarani scheme at Sanko Exe. Engg. PWD 2017 - 16 village Jl.154 Plot No 4636 of Sanko 1508/DP 24/05/2017 890000 (Social Sector), 845985 845985 100 Yes 2018 G.P. Burdwan. Constn. of Boitarani scheme at Sasanga Exe. Engg. PWD 2017 - 17 village Jl.58 Plot No 1581 of Sasanga 1508/DP 24/05/2017 890000 (Social Sector), 845985 845985 100 Yes 2018 G.P. Burdwan. Constn.. of Baitorani Scheme at Exe. Engg. PWD 2017 - 18 Hakordanga village Jl 104 Plot no. 1508/DP 24/05/2017 890000 (Social Sector), 845985 845985 100 Yes 2018 60,61,62 under Khandaghosh P.S. Burdwan. Constn.. of Baitorani Scheme at Khano Exe. Engg. PWD 2017 - 19 village JL104 Plot No. 8428 of Khano 1508/DP 24/05/2017 890000 (Social Sector), 845985 845985 100 Yes Asset Handover 2018 G.P. under Galsi-II P.S. Burdwan. Report Received as per the Clause Constn. of Boitarani scheme Berugram Exe. Engg. PWD 2017 - No. 8 under 20 village Jl.26 Plot No 6341 of Berugram 1508/DP 24/05/2017 890000 (Social Sector), 845985 845985 100 Yes 2018 updated BEUP G.P. Burdwan. Guidelines 2019 Constn. of Plastering work Decorative 2017 - E.O., 21 Cement base paint at Rashbihari Ghosh 149/DP 24/01/2018 600000 600000 600000 100 Yes 2018 Khandaghosh P.S. Mahavidlaya at Ukhrid Constn. of Atchala at Khandagosh 2017 - E.O., 22 149/DP 24/01/2018 400000 400000 400000 100 Yes Metepara 2018 Khandaghosh P.S. Constn. of Swamsan Shed at Ukhrid 2017 - E.O., 23 149/DP 24/01/2018 300000 300000 300000 100 Yes Moralpukur 2018 Khandaghosh P.S.

Constn. of Swamsan Shed at Keudia 2017 - E.O., 24 149/DP 24/01/2018 300000 300000 300000 100 Yes LatifpurMouza Khedua 2018 Khandaghosh P.S. Total 6050000 5829925 5829925 8 UC Asset Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Handover No. Order No Sanction Sanction Agency Released Utilized Progress ted Status Constn. of Atchala at Nabagram Mouza 2018 - E.O., 25 NabagramPlot No.578 Jl.No 7 under C-283/DP 08/02/2018 400000 400000 400000 100 Yes 2019 Khandaghosh P.S. Khandagosh Constn.. of ghat at Amral dighi under 2018 - E.O., 26 690/DP 27/02/2019 200000 195940 195940 100 Yes Gopalbera G.P. within Khandaghosh P.S. 2019 Khandaghosh P.S. Constn.. of gate at Khandaghosh Tantipara 2018 - E.O., 27 Primary school under Khandaghosh G.P. 690/DP 27/02/2019 50000 49305 49305 100 Yes 2019 Khandaghosh P.S. within Khandaghosh P.S. Constn.. of drain from Akale Majhi house to Bapi Roys house at Khandaghosh 2018 - E.O., Asset Handover 28 690/DP 27/02/2019 300000 292650 292650 100 Yes tantipara under Khandaghosh G.P. within 2019 Khandaghosh P.S. Report Khandaghosh P.S. Received as per the Clause No. 8 Constn.. of atchala at Manasatala of 2018 - E.O., under updated 29 Dewan Dighir Par under Sagrai GP. 1272/DP 28/05/2019 400000 390560 390560 100 Yes 2019 Khandaghosh P.S. BEUP within Khandaghosh P.S. Guidelines 2019 Constn.. of Chagram Paschimpara under 2018 - E.O., 30 1272/DP 28/05/2019 400000 370579 370979 100 No Ukhrid GP. within Khandaghosh P.S. 2019 Khandaghosh P.S.

Constn.. of passenger shed at Bamunari more main canel (Bridge 150 chains) of 2018 - E.O., 31 690/DP 27/02/2019 350000 341635 337066 100 Yes Berugram road under Lodna G.P. 2019 Khandaghosh P.S. within Khandaghosh P.S. Constn.. of passenger shed at Garsankari 2018 - E.O., 32 more of Badulia Berugram road under 690/DP 27/02/2019 350000 341845 331213 100 Yes 2019 Khandaghosh P.S. Ukhrid G.P. within Khandaghosh P.S. 9 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Constn.. of ghat at South side Mosdapukur of Berugram village Jl. E.O., Asset Handover 2018 - 33 No. 26 Plot No. 5409 under 690/DP 27/02/2019 300000 Khandaghosh 292830 213383 75 Yes Report Received 2019 Berugramm G.P. within P.S. as per the Clause Khandaghosh P.S. No. 8 under Constn.. of Atchala at Amral Charak E.O., updated BEUP 2018 - 34 dangapar under Berugram GP. 1272/DP 28/05/2019 400000 Khandaghosh 390120 382495 95 Yes Guidelines 2019 2019 within Khandaghosh P.S. P.S. Constn.. of Ghat at Badulia Samanta Executive Pukur (mouza-Badulia, Plot-822, Jl- 2018 - Officer, Asset Handover 35 2625/DP 08/10/2020 149025 149025 149025 100 Yes 79) under Sagrai G.P. within 2019 Khandaghosh Report Wanting Khandaghosh P.S. P.S. as per the Clause Constn.. of Atchala at Keshabpur Executive No. 8 under (Mouza-Keshabpur, Plot-1325, JL- 2018 - Officer, updated BEUP 36 2625/DP 08/10/2020 347550 347550 260663 75 Yes 68) under Sankari-I G.P. within 2019 Khandaghosh Guidelines 2019 Khandaghosh P.S. P.S. Total 3646575 3459766 3372879 Grand Total 15438575 14723219 14636332

10 ONGOING SCHEMES

11 NABIN CHANDRA BAG, HON'BLE MLA-259 Khandaghosh (SC) A.C.

Sanction UC Present Status Sl. Date of Amount Executing Amount Amount Physical Present Status for Name of the Scheme Year Order Submit for the Month No. Sanction Sanction Agency Released Utilized Progress the Month of June No ted of July 100% Work Executive Constn.. of Atchala at 100% work completed, UC 2018 - Officer, completed, UC 1 Gaitanpur village within 4022/DP 05/11/2019 392600 294450 294450 75 Yes will be submitted 2019 Khandaghosh received on Khandaghosh PS after getting the P.S. 22/06/2021 2nd installment.

Executive 100% work Constn.. of Atchala at 100% Completed, 2018 - Officer, completed, 2nd 2 Muidhara village Daspara 4021/DP 05/11/2019 384440 384440 288330 75 Yes Final UC will be 2019 Khandaghosh phase amount within Khandaghosh PS submitted shortly P.S. not credited

Executive 100% work Constn.. of Atchala at 100% Completed, 2018 - Officer, completed, 2nd 3 Durgapur near Masjidtala 4020/DP 05/11/2019 392280 392280 294210 75 Yes Final UC will be 2019 Khandaghosh phase amount within Khandaghosh P.S. submitted shortly P.S. not credited

Constn. of Atchala at Executive 100% work 100% Completed, Sankari Village 2018 - Officer, completed, 2nd 4 458/DP 05/02/2020 507326 507326 380494 75 Yes Final UC will be Barawaritala within 2019 Khandaghosh submitted shortly phase amount khandaghosh P.S. P.S. not credited

Total 16844366 1578496 1257484 12 Sanction UC Present Status for Sl. Date of Amount Executing Amount Amount Physical Present Status for the Name of the Scheme Year Order Submitt the Month of No. Sanction Sanction Agency Released Utilized Progress Month of July No ed June Constn. of boundary wall at Executive 100% Completed, 100% work completed, 2019- UC will be Final UC will be 5 Tetulmuri Play Ground 373/DP 30/01/2021 285080 Officer, 213810 213810 75 Yes 2020 submitted within 7 submitted getting the 2nd under Masjidpur GP Galsi- II P.S. days installment. Executive 100% Completed, Constn. of Atchala at Channa 2019- UC will be 100% work completed, 6 373/DP 30/01/2021 291960 Officer, 218970 0 0 No Adibasipara under Khano GP 2020 submitted within 7 bill in progress. Galsi- II P.S. days Constn. of Waiting Shed at Executive 100% Completed, 2019- UC will be Work in progress, 70% 7 Jujuti Sishu Uddan under 373/DP 30/01/2021 265650 Officer, 199238 0 0 No 2020 submitted within 7 work done. Bhuri GP Galsi- II P.S. days Constn. of Ghat at Executive 100% Completed, 100% work completed, 2019- UC will be Final UC will be 8 Chandanpur Ratipukur under 373/DP 30/01/2021 88762 Officer, 66572 66572 75 Yes 2020 submitted within 7 submitted getting the 2nd Satinandi GP Galsi- II P.S. days installment. Executive Constn. of Pukur Ghat at Problem arries not started 2019- Officer, due to land owner of 9 Bamnari Pukur at Village 374/DP 30/01/2021 149625 112219 0 0 No Not started. 2020 Khandaghosh pond and will be started Gopalbera GP P.S. shortly. Executive Problem arries not started Constn. of Protection wall due to local demand of 2019- Officer, 10 and Beatification at 374/DP 30/01/2021 449550 337163 0 0 No Not started. madrash committee and 2020 Khandaghosh Nischintapur High Madrasha also 1st installment not P.S. credited. Constn of Atchala near Executive 100% work completed, Sonda Durga Mandir under 2019- Final UC will be 11 373/DP 30/01/2021 400000 Officer, 193500 193500 75 Yes Nil Gohagram G.P. Within 2020 submitted getting the 2nd Galsi- II P.S. Galsi-II P.S. installment. 13 Sanction UC Present Status Sl. Date of Amount Amount Amount Physical Present Status for Name of the Scheme Year Order Executing Agency Submitt for the Month of No. Sanction Sanction Released Utilized Progress the Month of July No ed June 100% Work completed, UC will Constn. of Ghat at Jarul 2019- Executive Officer, 100% Work 12 374/DP 30/01/2021 349300 261975 261975 75 Yes Completed 2nd be submitted after Fulpukur at Sagrai GP Khandaghosh P.S. 2020 Installment to be getting the 2nd release installment. Constn. of Atchala at 85% completed 82% work 2019- Executive Officer, 1st Phase UC will completed, 75% UC 13 Khandagosh Tantipara under 374/DP 30/01/2021 399600 299700 0 0 No 2020 Khandaghosh P.S. be submitted will be submitted Khandagosh within 7 days 05/08/2021 100% Work Installation of Submersible completed, UC will 2019- Executive Officer, 100% Completed, 14 Pump at Kamalpur under 374/DP 30/01/2021 99200 74400 74400 75 Yes be submitted after 2020 Khandaghosh P.S. UC received. Sankri GP getting the 2nd installment. Constn. of Atchala at 75% completed 85% work 2019- Executive Officer, 1st Phase UC will completed, 75% UC 15 Kamalpur Ghoshpara under 374/DP 30/01/2021 398800 299100 0 0 No 2020 Khandaghosh P.S. be submitted will be submitted Sankari-I GP within 7 days 05/08/2021 Constn. of Atchala at 75% completed 90% work 2019- Executive Officer, 1st Phase UC will completed, 75% UC 16 Chancher Dhar under 374/DP 30/01/2021 399920 299940 0 0 No 2020 Khandaghosh P.S. be submitted will be submitted Khandaghosh within 7 days 05/08/2021 100% Work Constn. of Boundary Wall completed, UC will 2019- Executive Officer, 100% Completed, 17 including Drain at 374/DP 30/01/2021 99500 74625 74625 75 Yes be submitted after 2020 Khandaghosh P.S. UC received. Khandaghosh High School getting the 2nd installment. Constn. of High Mast Light 100% work 2019- Executive Officer, 35% Ongoing 18 at Mongalsima under Bhuri 788/DP 22/02/2021 172500 129375 0 0 No completed, bill in 2020 Galsi- II P.S. Progress GP progress. Total 3849447 2780587 884882 14 Sanction UC Present Status Sl. Date of Amount Amount Amount Physical Present Status for Name of the Scheme Year Order Executing Agency Submitt for the Month No. Sanction Sanction Released Utilized Progress the Month of July No ed of June Constn. of High Mast Light 100% work completed 2020 - Executive Officer, Ongoing .2nd 19 Electric at Khandagosh Thana 333/DP 29/01/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not 2021 Khandaghosh P.S. More under Khandagosh GP release credited

Costn of High Mast Light 100% work completed 2020 - Executive Officer, Ongoing .2nd 20 Electrict at Khandagosh 333/DP 29/01/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not 2021 Khandaghosh P.S. Hattala release credited

Constn. of High Mast Light at 100% work completed 2020 - Executive Officer, Ongoing .2nd 21 Berugram Dighir Par under 333/DP 29/01/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not 2021 Khandaghosh P.S. Berugram GP release credited

Constn. of High Mast Light 100% work completed 2020 - Executive Officer, Ongoing .2nd 22 Electric at Kule Bazar under 333/DP 29/01/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not 2021 Khandaghosh P.S. Ukhrid GP release credited

Constn. of High Mast Light 100% work completed 2020 - Executive Officer, Ongoing .2nd 23 Electric at Keshabpur Bazar 333/DP 29/01/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not 2021 Khandaghosh P.S. under Sankari-I GP release credited Constn. of High Mast Light 100% work completed Electric at Bowal Chandi 2020 - Executive Officer, Ongoing .2nd 24 333/DP 29/01/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not Thakurtala under Berugram Khandaghosh P.S. 2021 release credited GP Constn. of High Mast Light 100% work completed 2020 - Executive Officer, Ongoing .2nd 25 Electric at Badulia Bazar 333/DP 29/01/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not 2021 Khandaghosh P.S. under Sagrai GP release credited

Constn. of High Mast Light at 100% work completed 2020 - Executive Officer, Ongoing .2nd 26 Sankari Hattala under Sankari 333/DP 29/01/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not 2021 Khandaghosh P.S. II release credited 15 Sanction UC Present Status Sl. Date of Amount Amount Amount Physical Present Status for Name of the Scheme Year Order Executing Agency Submitt for the Month of No. Sanction Sanction Released Utilized Progress the Month of July No ed June

Constn. of High Mast Light Ongoing .2nd 100% work completed 2020- Executive Officer, 27 at Khejurhati Bazar under 333/DP 29/01/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not 2021 Khandaghosh P.S. Khandagosh GP release credited

Constn. of High Mast Light Ongoing .2nd 100% work completed 2020- Executive Officer, 28 at Berugram Bus Stand 333/DP 29/01/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not 2021 Khandaghosh P.S. Bazar under Berugram GP release credited

Constn. of High Mast Light Ongoing .2nd 100% work completed 2020- Executive Officer, 29 Electric Ukhrid Bazar at 333/DP 29/01/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not 2021 Khandaghosh P.S. Ukhrid GP release credited

Constn. of High Must Light Ongoing .2nd 100% work completed 2020- Executive Officer, 30 Electric at Sagrai Bazar 333/DP 29/01/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not 2021 Khandaghosh P.S. under Sagrai GP release credited

Ongoing .2nd 100% work completed Constn. of High Mast Light 2020- Executive Officer, 31 789/DP 22/02/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not Electric at Tokona bazar 2021 Khandaghosh P.S. release credited

Constn. of High Mast Light Ongoing .2nd 100% work completed 2020- Executive Officer, 32 Electric at Khandagosh 789/DP 22/02/2021 240000 180000 180000 75 Yes Installment to be 2nd installment not 2021 Khandaghosh P.S. Pathanpara More release credited

Ongoing .2nd 100% work completed Constn. of High Mast Light 2020- Executive Officer, 33 789/DP 22/02/2021 239400 179550 179550 75 Yes Installment to be 2nd installment not Electric at Gopalbera Bazar 2021 Khandaghosh P.S. release credited 16 Sanction UC Present Status Sl. Date of Amount Amount Amount Physical Present Status for Name of the Scheme Year Order Executing Agency Submitt for the Month of No. Sanction Sanction Released Utilized Progress the Month of July No ed June 100% work Ongoing, 2nd Constn. of High Mast Light 2020- Executive Officer, completed 2nd 34 789/DP 22/02/2021 239400 179550 179550 75 Yes Installment to be Electric at Kendur Bazar 2021 Khandaghosh P.S. installment not release credited 100% work Constn. of High Mast Light Ongoing, 2nd 2020- Executive Officer, completed 2nd 35 Electric at KumirKhola 789/DP 22/02/2021 239400 179550 179550 75 Yes Installment to be 2021 Khandaghosh P.S. installment not Bazar release credited 100% work Constn. of High Mast Light Ongoing, 2nd 2020- Executive Officer, completed 2nd 36 Electric at Mete Danga 789/DP 22/02/2021 239400 179550 179550 75 Yes Installment to be 2021 Khandaghosh P.S. installment not bazar release credited Installation of electric High 100% work Agro Mast Light at 2020- completed, 75% UC 37 2752/DP 29/06/2021 240000 Industries 18000 0 0 No Nil Chandanpur Bus stop under 2021 will be submitted Corporation Ltd. Satinandi G.P. 05/08/2021 100% work Installation of electric High West Bengal Agro 2020- completed, 75% UC 38 Mast Light at Kulgoria 2752/DP 29/06/2021 240000 Industries 18000 0 0 No Nil 2021 will be submitted Bazar under Sanko G.P. Corporation Ltd. 05/08/2021 100% work Installation of electric High West Bengal Agro 2020- completed, 75% UC 39 Mast Light at Baromuria 2752/DP 29/06/2021 240000 Industries 18000 0 0 No Nil 2021 will be submitted Bazar under Sanko G.P. Corporation Ltd. 05/08/2021 Installation of electric High 100% work West Bengal Agro Mast Light at Tentulmuri 2020- completed, 75% UC 40 2752/DP 29/06/2021 240000 Industries 18000 0 0 No Nil Bus stop under Masjidpur 2021 will be submitted Corporation Ltd. G.P. 05/08/2021 17 Sanction UC Present Status Sl. Date of Amount Amount Amount Physical Present Status for Name of the Scheme Year Order Executing Agency Submitt for the Month of No. Sanction Sanction Released Utilized Progress the Month of July No ed June

100% work Installation of electric High West Bengal Agro 2020- completed, 75% UC 41 Mast Light at Bus 2752/DP 29/06/2021 240000 Industries 18000 0 0 No Nil 2021 will be submitted stop under Gohogram G.P. Corporation Ltd. 05/08/2021

100% work Installation of electric High West Bengal Agro 2020- completed, 75% UC 42 Mast Light at Sikarpur 2752/DP 29/06/2021 240000 Industries 18000 0 0 No Nil 2021 will be submitted under Bhuri G.P. Corporation Ltd. 05/08/2021

Installation of electric High 100% work West Bengal Agro Mast Light at Ishanchandi 2020- completed, 75% UC 43 2752/DP 29/06/2021 240000 Industries 18000 0 0 No Nil Mandirtala under Khano 2021 will be submitted Corporation Ltd. G.P. 05/08/2021

Total 5989800 4435800 3232350 Grand Total 11523613 8794883 5374716

18 Dr. Rabiranjan Chottopadhyay, Hon’ble M.L.A. of 260-Bardhaman Dakshin A.C.

19 COMPLETED SCHEMES

20 RABIRANJAN CHOTTOPADHYAY, HON'BLE MLA-260 Bardhaman Dakshin A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Constn. of Concrete road with drain 2016 - CEO, Burdwan 1 Sadarghat Rabindrapally from T. Dutta 302/DO 27/01/2017 394404 377773 377773 100 Yes 2017 Dev. Authority house to Sk. Mirchands Addl Work Stage Submersible and 2016 - CEO, Burdwan 2 Electrification ladies Park named Bande 302/DP 27/01/2017 484387 474359 474359 100 Yes 2017 Dev. Authority Mataram Constn. of Concrete road with drain at Sarada Sukanta pally from 2016 - CEO, Burdwan 3 302/DP 27/01/2017 365623 291283 291283 100 Yes R.Chakraborty house to G. Mondal 2017 Dev. Authority Asset Handover house to A. Mondal Report Wanting Constn. of Concrete road from Malirbag as per the Clause 2016 - CEO, Burdwan 4 to Bhubaneswar road including Guard 302/DP 27/01/2017 914931 914931 914931 100 Yes No. 8 under 2017 Dev. Authority Wall of the ponds updated BEUP Constn. of Concrete Road at Keshab Guidelines 2019 Ganj Chotti from Sneha Mess to 2016 - CEO, Burdwan 5 302/DP 27/01/2017 534429 420771 420771 100 Yes Mrghamallar fromAlam house to Rasida 2017 Dev. Authority Bhavan via P K. Das Constn. of Pucca Drain at Western side 2016 - CEO, Burdwan 6 302/DP 27/01/2017 306226 244760 244760 100 Yes of Krishnapur Road Ward No.1 2017 Dev. Authority

Rep work at Burdwan Vivekananda 2016 - CEO, Burdwan 7 Balika Vidyalaya Arabindapally ward 968/DP 28/03/2017 195783 179347 179347 100 Yes 2017 Dev. Authority No. 8 21 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Constn. of Concrete road including 2016 - CEO, Burdwan 8 guard wall from P.Das house to Jail 968/DP 28/03/2017 268971 194406 194406 100 Yes 2017 Dev. Authority boundary ward no. 3

Constn. of Concrete Road from 2016 - CEO, Burdwan 9 A.Bhandari house to 968/DP 28/03/2017 773440 773440 773440 100 Yes 2017 Dev. Authority Athletic Club Gate No. 11

Constn. of C. Rd. R. Rajjak house to 2016 - CEO, Burdwan 10 C. Mondal house and Rajbati Joswara 968/DP 28/03/2017 232903 190861 190861 100 Yes 2017 Dev. Authority Asset Handover house to S. Joswara house Wd No. 7 Report Wanting as per the Clause Supp. High Must Light at Tarun No. 8 under 2016 - CEO, Burdwan 11 Sangha Play Ground beside Borehat 998/DP 30/03/2017 381604 370156 370156 100 Yes updated BEUP 2017 Dev. Authority Kamalakanta Kalibari ward No. 28 Guidelines 2019 Med.Suptd.- Supply of One Transportation Van cum-Vice 2016 - 12 Carrying Patient at Burdwan Medical 2208/DP 04/08/2017 129916 Princ, Burdwan 129916 129916 100 Yes 2017 College and Hospital Med. College Ho

Dev. of Kabar Sthan at Kamal Sayer 2016 - CEO, Burdwan 13 2862/DP 09/11/2017 662119 662119 662119 100 Yes ward No. 26 2017 Dev. Authority

Total 5644736 5224122 5224122 22 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Constn. of Boundary Wall Chain-link at the 2017 - CEO, Burdwan 14 side of Play Ground at Bharati Bhavan Boys 3048/DP 21/11/2017 200000 200000 200000 100 Yes 2018 Dev. Authority High School Parbirhata Burdwan

Constn. of Boundary Wall at Rathtala 2017 - CEO, Burdwan 15 Adarsha Prathamic Vidyalaya Padma Pukur 3048/DP 21/11/2017 300000 287578 287578 100 Yes 2018 Dev. Authority Kanchannagar Constn. of Class Room at Municipal Boys 2017 - CEO, Burdwan 16 School High School G.T. Road Burdwan 3048/DP 21/11/2017 1400000 1163365 1163365 100 Yes 2018 Dev. Authority Ward No. 34 Repair and Renovation of Exisisting School Asset Handover Building Burdwan Sri Sri Ramkrishna 2017 - CEO, Burdwan Report Wanting 17 3048/DP 21/11/2017 600000 598414 598414 100 Yes Saradapith Urban Junior Basic School, 2018 Dev. Authority as per the Clause Borehat Burdwan Wr No. 28 No. 8 under updated BEUP Repair and colouring works at Burdwan Guidelines 2019 2017 - CEO, Burdwan 18 Vivekananda Balika Vidyalaya 62/DP 09/01/2018 150000 141007 141007 100 Yes 2018 Dev. Authority Arabindapally Burdwan

Constn. of Boundary Wall at Rathtala GSFP 2017 - CEO, Burdwan 19 62/DP 09/01/2018 300000 264752 264752 100 Yes Vidyalaya Rathtala Kanchan Nagar 2018 Dev. Authority

Constn. of Concrete floor and drain 2017 - CEO, Burdwan 20 62/DP 09/01/2018 400000 397684 397684 100 Yes Batdhaman Banipith Girls high School 2018 Dev. Authority Constn. of Class Room Bharati Balika 2017 - CEO, Burdwan 21 277/DP 08/02/2018 534000 534000 534000 100 Yes Bidyalaya at Borehat 2018 Dev. Authority 23 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Rep. and renovation of exsisting 2017 - CEO, Burdwan 22 School building Burdwan Shiv 277/DP 08/02/2018 500000 486954 486954 100 Yes 2018 Dev. Authority Kumar Harijan Bidyalaya

Rep and Renov of exsisting School 2017 - CEO, Burdwan 23 Building Burdwan Banipith High 277/DP 08/02/2018 300000 300000 300000 100 Yes 2018 Dev. Authority School Asset Handover Painting Work and other Ancilleary Report Wanting 2017 - CEO, Burdwan 24 Works Utsab at Parbirhata 993/DP 24/05/2018 109539 109539 109539 100 Yes as per the Clause 2018 Dev. Authority Burdwan Ward No. 35 No. 8 under updated BEUP Guidelines 2019 Constn.. of concrete road at 2017 - CEO, Burdwan 25 Kamalsayer Kabarsthan ward 2318/DP 30/08/2019 465817 456966 342725 100 Yes 2018 Dev. Authority no.26 under Burdwan Municipality

Constn.. of concrete road with Guardwall at Northside Samanta 2017 - CEO, Burdwan 26 2318/DP 30/08/2019 337744 331157 248368 100 Yes Pukur ward no. 9 under Burdwan 2018 Dev. Authority Municipality

Total 5597100 5271416 5271416

24 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Mural, artificial grass, cladding stone tiles and other decorative works at the 2018 - CEO, Burdwan 27 2283/DP 10/10/2018 2715790 2696881 2696881 100 Yes multilevel parking space and electrical 2019 Dev. Authority works at Mandela Park Writing and fixing of radium boards 2018 - CEO, Burdwan 28 at the poles of high mast light under 3203/DP 14/12/2018 179798 179798 179798 100 Yes 2019 Dev. Authority Asset Handover Burdwan Muty. Report Wanting Fitting and Fixing of radium boards at 2018 - CEO, Burdwan as per the Clause 29 the sites of new schemes under 3203/DP 14/12/2018 104412 104412 78309 100 Yes 2019 Dev. Authority No. 8 under Burdwan Muty. updated BEUP Mural, artificial grass cladding stone Guidelines 219 2018 - CEO, Burdwan 30 tiles at Mendela park near Curzan 1336/DP 04/06/2019 1696664 1696664 1696664 100 Yes 2019 Dev. Authority gate 2nd phase

Beautification of Kamalsayer 2018 - CEO, Burdwan 31 Kabarsthan, Burdwan at ward no. 26 1336/DP 04/06/2019 388275 194640 194640 100 Yes 2019 Dev. Authority under Burdwan Muty.

Total 5084939 4872395 4872395

Grand Total 16326775 15367933 15367933

25 ONGOING SCHEMES

26 RABIRANJAN CHOTTOPADHYAY, HON'BLE MLA-260 Bardhaman Dakshin A.C. UC Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Present Status for Name of the Scheme Year Submit for the Month No. Order No Sanction Sanction Agency Released Utilized Progress the Month of July ted of June 100% work Constn. of Pucca Road from 80% work completed. 2016- CEO, Burdwan completed UC will 1 Kiran Ch Das house to Ganesh 697/DP 15/02/2021 775490 775490 581618 75 Yes Final UC will be given be submitted after 2017 Dev. Authority shortly Ch Das house receiving of fund Total 775490 775490 581618 Re excavation and Protection 100% work 80% work completed. work of Pond in front of 2017- CEO, Burdwan completed UC will be Final UC will be given 2 727/DP 18/02/2021 488357 488357 366268 75 Yes submitted after Burdwan Istitute of Medical and 2018 Dev. Authority shortly life Science BIMLS receiving of fund Total 488357 488357 366268 100% work Constn.. of Park at ward no. 27 2018 - CEO, Burdwan 100 % completed. 3 1375/DP 11/05/2020 385629 385629 336554 95 Yes UC of 1st. phase completed. Final UC within Burdwan Municipality 2019 Dev. Authority already received will be given shortly 80% work completed. Constn. of Bituminous road 2018 - CEO, Burdwan 100% completed. UC 1st Phase UC will be 4 728/DP 18/02/2021 499937 374953 0 0 No to be send shortly with covered slab in ward no 26 2019 Dev. Authority given shortly Total 885566 760582 336554 Constn.. of an ACR with stair 90% work completed. case of Monohardas Vidyalaya 2019- CEO, Burdwan 100% completed. UC 1st Phase UC will be 5 1605/DP 02/06/2020 496001 371703 0 0 No to be send shortly (Pry) Rajganj under Burdwan 2020 Dev. Authority given shortly Muty. Constn.. of colouring painting of the inner wall of Bardhaman 100% work 2019- CEO, Burdwan 100% completed. UC 6 Adarsha Vidyalaya (High) 1605/DP 02/06/2020 113493 113209 104066 95 Yes completed. Final UC 2020 Dev. Authority to be send shortly Keshabganj Chati under will be given shortly Burdwan Muty. 27 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted of June July Constn.. of colouring painting of 100% work the inner wall of Bardhaman CEO, 100% completed. 2019- completed. Final 7 Nivedita Kanyaa vidyalaya 1604/DP 02/06/2020 278479 Burdwan Dev. 277783 261578 95 Yes UC to be send 2020 UC will be given Indrapastha under Burdwan Authority shortly shortly Muty. 100% work Constn..of Masonry Ghat with CEO, 100% completed. 2019- completed. Final 8 beautification at Mallick Pukur 1604/DP 02/06/2020 411271 Burdwan Dev. 410242 344430 95 Yes UC to be send 2020 UC will be given under Burdwan Muty. Authority shortly shortly Erection of decorative light pole 100% work line washer and focus light at CEO, 100% completed. 2019 - completed. Final 9 Abasarika Park Utsab Maidan 2595/DP 05/10/2020 493379 Burdwan Dev. 493379 370034 75 Yes UC to be send 2020 UC will be given Parbirhata within Burdwan Authority shortly shortly Muty. Supply and fixing of fucas lights 100% work CEO, 100% completed. for mural illumination Mandela 2019 - completed. Final 10 2595/DP 05/10/2020 325135 Burdwan Dev. 325135 243851 75 Yes UC to be send Park ward No. 9 within 2020 UC will be given Authority shortly Burdwan Muty. shortly Installation of one submersible CEO, 100% completed. Work in progress. pump near Olaichanditala 2019 - 11 2847/DP 02/11/2020 99615 Burdwan Dev. 74711 0 0 No UC to be send 50% work mandir Complex at ward no. 11 2020 Authority shortly completed. under Burdwan Muty.

CEO, 100% completed. Work in progress. Constn. of Toilet at Bhatari 2019- 12 729/DP 18/02/2021 297000 Burdwan Dev. 222750 0 0 No UC to be send 80% work Girls School Primary 2020 Authority shortly completed. 28 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted of June July 100% work Constn. of Guard Wall with Iron CEO, 100% completed. 2019- completed. 1st Phase 13 Grill Surrounding BDA Clock 729/DP 18/02/2021 916720 Burdwan Dev. 687540 0 0 No UC to be send UC will be given 2020 shortly Tower Authority shortly CEO, 90% completed. Work in progress. Development of Medical 2019- 14 729/DP 18/02/2021 1003544 Burdwan Dev. 752658 0 0 No UC to be send 60% work College Ground in Ward No 27 2020 Authority shortly completed.

CEO, 100% completed. Work in progress. Constn. of Concrete Road at 2019- 15 729/DP 18/02/2021 491820 Burdwan Dev. 368865 0 0 No UC to be send 60% work Bidhanpally Ashram 2020 Authority shortly completed. Total 4926457 4097975 1323959

Work will be Constn. of CC Road from CEO, Work in progress. 2020- started, not started 16 Kamal Sayer from the house of 700/DP 15/02/2021 119988 Burdwan Dev. 89991 0 0 No 60% work due to land 2021 completed. Sk Samser Alamto Sk Sabir Authority problem

Constn. of Concrete road near CEO, 100% completed. Work in progress. 2020- 17 Kamal Sayer From the House of 700/DP 15/02/2021 199980 Burdwan Dev. 149985 0 0 No UC to be send 60% work 2021 Sk Sadai Authority shortly completed.

100% work Constn. of one No pump House CEO, Work in progress. 2020- completed UC will 18 and Land Dev beautification of 700/DP 15/02/2021 451955 Burdwan Dev. 451955 338966 75 Yes 80% work be submitted after 2021 completed. area near ADM (G) Banglow Authority receiving of fund

100% work Constn. of Road at Ashram Par CEO, 80% work 2020- completed UC will 19 to Vidyasagar Colony 700/DP 15/02/2021 460271 Burdwan Dev. 460271 345203 75 Yes completed. Final UC be submitted after 2021 will be given shortly Bidhanpally Authority receiving of fund 29 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month No. Order No Sanction Sanction Agency Released Utilized Progress ted of June of July 80% work 2020- CEO, Burdwan Ongoing, 95 % completed. Final 20 Dev of Park at Sukanta Nagar 700/DP 15/02/2021 494690 494690 371018 75 Yes 2021 Dev. Authority work done UC will be given shortly 100% work 70% work Painting of the outer walls of 2020- CEO, Burdwan completed UC will completed. 1st 21 700/DP 15/02/2021 83292 62469 0 0 No the Nivedita Kenya Vidyalaya 2021 Dev. Authority be submitted after phase UC will be receiving of fund given shortly Landscape and Beautification 95% work work fromADM(ZP) Banglow 2020- CEO, Burdwan 70% completed. completed. 1st 22 734/DP 18/02/2021 292058 219044 0 0 No to Circuit House beside Kalna 2021 Dev. Authority Work in progress phase UC will be Road given shortly 90% work 100% completed. Beatification of Kanta Pukur 2020- CEO, Burdwan completed. 1st 23 734/DP 18/02/2021 439385 329539 0 0 No UC to be send phase UC will be Ward No 1 2021 Dev. Authority shortly given shortly 90% work Constn. of Boundary Wall of 100% completed. 2020- CEO, Burdwan completed. 1st 24 the Play Groundof Tarun 734/DP 18/02/2021 470250 352688 0 0 No UC to be send phase UC will be 2021 Dev. Authority shortly Sangha Club, Borehat given shortly 100% work Constn. of Permanent Bus Stand 100% completed. 2020- CEO, Burdwan completed. 1st 25 Waiting Shed at Nurse 734/DP 18/02/2021 241951 181461 0 0 No UC to be send phase UC will be 2021 Dev. Authority shortly QarterMore South Side given shortly 90% work Illumination of Garden Near 2020- CEO, Burdwan 70% completed. completed. 1st 26 734/DP 18/02/2021 349583 262187 0 0 No Bunglow beside Kalna Road 2021 Dev. Authority Work in progress phase UC will be given shortly Total 3603403 3054280 1055187 Grand Total 10679273 9176684 3663586 30 Shri Nepal Ghorui, Hon’ble M.L.A. of 261-Raina (SC) AC

31 COMPLETED SCHEMES

32 NEPAL GHORUI, HON'BLE MLA-261 RAINA(SC) A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Constn. of Concrete road from 2016 - Executive Officer, 1 Kalupukur Par to Pirtala at Ausara 2138/DP 15/09/2016 150000 150000 150000 100 Yes 2017 Raina- I P.S. of Sehara G.P.

Constn. of Concrete road from 2016 - Executive Officer, 2 Hansir Kaltala Ahar to S.C. Mallik 2138/DP 15/09/2016 350000 350000 350000 100 Yes Asset Handover 2017 Raina- I P.S. premises at Ausara Report Received as per the Clause No. 8 under Constn. of Drain and cover by slab 2016 - Executive Officer, updated BEUP 3 from the premises of T.K. Nandi to 2138/DP 15/09/2016 150000 150000 150000 100 Yes 2017 Raina- I P.S. Guidelines 2019 the premises of T.Puille at Alalpur

Constn. of Drain and cover Slab 2016 - Executive Officer, 4 from premises of D. Pullay to the 2138/DP 15/09/2016 150000 150000 150000 100 Yes 2017 Raina- I P.S. pond of S. Malik at Alalpur

District Purchase an Ambulance for Arui 2016 - 5 2430/DP 21/10/2016 524879 Magistrate, 524879 524879 100 Yes Asset Handover G.P. under Raina II P.S. 2017 Burdwan Report Wanting as per the Clause No. 8 under District Purchase an Ambulance for 2016 - updated BEUP 6 2509/DP 27/10/2016 524879 Magistrate, 524879 524879 100 Yes G.P. 2017 Guidelines 2019 Burdwan 33 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Constn. of Community Room at 2016 - Executive Officer, 7 2549/DP 03/11/2016 300000 300000 300000 100 Yes Belsor Purbapara of Hizalna G.P. 2017 Raina- I P.S.

Constn. of Community Room at 2016 - Executive Officer, 8 Belsor Shibtala Para of Hizalna 2549/DP 03/11/2016 300000 300000 300000 100 Yes 2017 Raina- I P.S. G.P Asset Handover Report Received Constn. of Burning Ghat Chully 2016 - Executive Officer, as per the Clause 9 and Waiting room at Shipta of 120/DP 08/01/2017 500000 500000 500000 100 Yes 2017 Raina- I P.S. No. 8 under Narugram updated BEUP Guidelines 2019 Constn. of Burning Ghat Chully 2016 - Executive Officer, 10 and waiting Room at Bamunia of 799/DP 15/03/2017 500000 500000 500000 100 Yes 2017 Raina- I P.S. Hizala

Constn. of Burning Ghat Chully 2016 - Executive Officer, 11 and Waiting Room at Palasan 799/DP 15/03/2017 500000 500000 500000 100 Yes 2017 Raina- I P.S. Paschim Para

Asset Handover Report Wanting Constn. of Boundary Wall of 2016 - Executive Officer, as per the Clause 12 Uchha Vidyalaya of 903/DP 22/03/2017 400000 400000 400000 100 Yes 2017 Raina- II P.S. No. 8 under Uchalan G.P. updated BEUP Guidelines 2019

34 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn. of waiting room at 2016 - Executive Officer, 13 Hospital more to Gotan 903/DP 22/03/2017 300000 293677 293677 100 Yes Asset Handover 2017 Raina- II P.S. G.P. Report Wanting as per the Clause No. 8 Constn. of Burning Ghat and under updated 2016 - Executive Officer, 14 waiting room at Kamardihi of 1086/DP 06/04/2017 500000 488018 488018 100 Yes BEUP Guidelines 2017 Raina- II P.S. Gotan G.P. 2019

Constn.. of burning ghat with chully and waiting room at 2016 - Executive Officer, 15 Shyamdasbati, Mouza C- 1312/DP 02/05/2017 500000 500000 500000 100 Yes 2017 Raina- I P.S. Shyamdasbati, Plot No. 200, JL No. 28 Constn. of Boundary Wall of 2016 - Executive Officer, 16 Ghustia Nandanpur High 406/DP 26/02/2018 350000 349999 349999 100 Yes 2017 Raina- II P.S. School HS Uchalan G.P. Asset Handover Total 5999758 5981452 5981452 Report Received as per the Clause No. 8 Constn. of Boitarani scheme at Exe. Engg. PWD under updated 2017 - 17 Bandgacha of Hijalna G.P Plot 1461/DP 17/05/2017 890000 (Social Sector), 843730 843730 100 Yes BEUP Guidelines 2018 No. 18 Jl No. 5. Burdwan. 2019 Constn. of Boitarani scheme at Exe. Engg. PWD 2017 - 18 Barabainan Plot No. 5314, 1461/DP 17/05/2017 890000 (Social Sector), 843730 843730 100 Yes 2018 Kh.No. 1752 Burdwan. Constn. of Boitarani scheme at Exe. Engg. PWD 2017 - 19 Bujrukdighi Plot No. 394,JL 1461/DP 17/05/2017 890000 (Social Sector), 843730 843730 100 Yes 2018 No. 62 Burdwan. 35 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Exe. Engg. PWD Constn. of Boitarani scheme at 2017 - 20 1461/DP 17/05/2017 890000 (Social Sector), 843731 843731 100 Yes Chatadighi Plot No. 4,JL No. 176 2018 Burdwan.

Constn. of Boitarani scheme at Exe. Engg. PWD 2017 - 21 Dakshin Gopalpur Plot 1461/DP 17/05/2017 890000 (Social Sector), 843730 843730 100 Yes 2018 No.1142,JL No. 177 Burdwan.

Constn. of Burning Ghat and 2017 - Executive Officer, 22 Waiting Room Belar Malik Para 970/DP 22/05/2018 500000 500000 500000 100 Yes Asset Handover 2018 Raina- II P.S. at Paitna G.P. Report Received as per the Clause No. 8 under Constn. of New Drain Eklakhi 2017 - Executive Officer, updated BEUP 23 970/DP 22/05/2018 300000 300000 300000 100 Yes bazar at Uchalan G.P. 2018 Raina- II P.S. Guidelines 2109

Constn. of Burning Ghat Haripur 2017 - Executive Officer, 24 1113/DP 18/06/2018 250000 250000 250000 100 Yes at Natu G.P. under Raina I P.S. 2018 Raina- I P.S.

Constn. of Burning Ghat and 2017 - Executive Officer, 25 waiting Room bantir Dhara Para 1310/DP 16/07/2018 500000 500000 500000 100 Yes 2018 Raina- I P.S. at Hijalna G.P.

Total 6000000 5768651 5768651

36 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn.. of Mukta Mancha at Raina Executive Domepara village (Mouza-Rainagar, 2018 - 26 1376/DP 10/06/2019 400000 Officer, 400000 400000 100 Yes plot no 1480) under Raina G.P. within 2019 Raina- I P.S. Raina-I P.S.

Constn.. of waiting room at Executive 2018 - 27 Mogholmari of Sehara G.P. under 2010/DP 07/08/2019 400000 Officer, 400000 400000 100 Yes 2019 Raina-I P.S. Raina- I P.S. Constn.. of gate at Executive 2018 - 28 College Math under Shyamasundar 2010/DP 07/08/2019 500000 Officer, 490000 490000 100 Yes 2019 G.P.within Raina-I P.S. Raina- I P.S.

AC high must tower, luminaries150 Asset Handover Report Executive watt led base at Machkhanda near 2018 - Received as per the Clause 29 4233/DP 25/11/2019 455000 Officer, 454363 454363 100 Yes High School under Hijalna GP within 2019 No. 8 under updated Raina- I P.S. BEUP Guidelines 2019 Raina-I P.S. Constn.. and purchase of 10 mtr. High Executive 2018 - 30 must light at Bolpur Bislaxmitala under 4231/DP 25/11/2019 250000 Officer, 250000 250000 100 Yes 2019 Hijalna G.P. within Raina-I P.S. Raina- I P.S. AC high must tower, luminaries150 Executive 2018 - 31 watt led base at Belsor Tematha under 4232/DP 25/11/2019 455000 Officer, 454363 454363 100 Yes 2019 Hijalna GP within Raina-I P.S. Raina- I P.S. Constn.. of Mukta Mancha at Executive Machkhanda village (Mouza- 2018 - 32 4613/DP 20/12/2019 400000 Officer, 400000 400000 100 Yes Machkhanda, Plot No. 1430) under 2019 Raina- I P.S. Hijalna G.P. within Raina-i P.S. 37 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn.. of Mukta Mancha at Lohai 2018 - Executive Officer, 33 Sammilani Vidyaniketan under Arui 90/DP 08/01/2020 400000 400000 400000 100 Yes 2019 Raina- II P.S. G.P. within Raina-II P.S. Constn.. of Mukta Mancha at Pasra 2018 - Executive Officer, 34 under Barabainan G.P. within Raina-II 90/DP 08/01/2020 400000 400000 400000 100 Yes 2019 Raina- II P.S. P.S. Constn.. of Mukta Mancha at 2018 - Executive Officer, 35 Rashbehari Basu Trust under 90/DP 08/01/2020 400000 400000 400000 100 Yes 2019 Raina- II P.S. Barabainan G.P. within Raina-II P.S. Constn.. of Mukta Mancha at Alampur 2018 - Executive Officer, 36 90/DP 08/01/2020 400000 400000 400000 100 Yes under Arui G.P. within Raina-II P.S. 2019 Raina- II P.S. Asset Handover Report Constn.. of Burning Ghat at Dharan Received as per the 2018 - Executive Officer, 37 Vill. (Mouza-Dharan, Plot No. 869) 171/DP 14/01/2020 350000 349650 349650 100 Yes Clause No. 8 under 2019 Raina- I P.S. under Palashan G.P. within Raina-I P.S. updated BEUP Guidelines 2019 Constn.. and purchase of 10 mtr High must light at near Aushara 2018 - Executive Officer, 38 94/DP 06/02/2020 250000 250000 250000 100 Yes Barowarital;a under Sehara GP within 2019 Raina- I P.S. Raina-I P.S. Installation of submersible at Jotchillam 2018 - Executive Officer, 39 F.P. School under Hijalna G.P. within 774/DP 28/02/2020 120000 120000 120000 100 Yes 2019 Raina- I P.S. Raina-I P.S.

Land scarping work at Rashbihari Basu 2018 - Executive Officer, 40 vita and Trust under Barabainan G.P. 1012/DP 19/03/2020 420000 420000 420000 100 Yes 2019 Raina- II P.S. within Raina-II P.S

Total 5600000 5597376 5597376 38 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Asset Handover Report Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, Wanting as per the 42 2198/DP 09/09/2020 250000 250000 250000 100 Yes Clause No. 8 under mast light Belar Manasa Bazar Raina- I P.S. 2020 updated BEUP Guidelines 2019 Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, 43 2198/DP 09/09/2020 250000 250000 250000 100 Yes mast light infront of Babrakpur 2020 Raina- I P.S.

Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, 44 2198/DP 09/09/2020 250000 250000 250000 100 Yes mast light Baharampur Pirtala 2020 Raina- I P.S.

Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, 45 2198/DP 09/09/2020 250000 250000 250000 100 Yes Asset Handover Report mast light Samuspur Mazar 2020 Raina- I P.S. Received as per the Clause No. 8 under Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, updated BEUP 46 2198/DP 09/09/2020 250000 250000 250000 100 Yes mast light near Palsona Barowaritala 2020 Raina- I P.S. Guidelines 2019

Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, 47 2198/DP 09/09/2020 250000 250000 250000 100 Yes mast light Haripur Shibtala 2020 Raina- I P.S.

Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, 48 2198/DP 09/09/2020 250000 250000 250000 100 Yes mast light Madangar Pirtala 2020 Raina- I P.S.

Asset Handover Report Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, Wanting as per the 49 2198/DP 09/09/2020 250000 250000 250000 100 Yes Clause No. 8 under mast light Dommara Bus Stand Raina- I P.S. 2020 updated BEUP Guidelines 2019 39 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Asset Handover Report Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, Wanting as per the 50 2198/DP 09/09/2020 250000 250000 250000 100 Yes Clause No. 8 under mast light Pusar Pipuladaha more Raina- I P.S. 2020 updated BEUP Guidelines 2019 Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, 51 2198/DP 09/09/2020 250000 250000 250000 100 Yes mast light near Gopalpur barowaritala 2020 Raina- I P.S.

Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, 52 2198/DP 09/09/2020 250000 250000 250000 100 Yes mast light Hijalna arairajtala 2020 Raina- I P.S.

Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, 53 2198/DP 09/09/2020 250000 250000 250000 100 Yes Asset Handover Report mast light near Jamna barowaritala 2020 Raina- I P.S. Received as per the Clause No. 8 under Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, updated BEUP 54 2198/DP 09/09/2020 250000 250000 250000 100 Yes mast light Golgram Charaktala 2020 Raina- I P.S. Guidelines 2019

Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, 55 2198/DP 09/09/2020 250000 250000 250000 100 Yes mast light near Rambati barowaritala 2020 Raina- I P.S.

Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, 56 2198/DP 09/09/2020 250000 250000 250000 100 Yes mast light near bansha barowaritala 2020 Raina- I P.S.

Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, 57 2198/DP 09/09/2020 250000 250000 250000 100 Yes Asset Handover Report mast light Sanko more 2020 Raina- I P.S. Wanting as per the Clause No. 8 under Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, updated BEUP 58 2198/DP 09/09/2020 250000 250000 250000 100 Yes mast light Uchalan Amtala 2020 Raina- I P.S. Guidelines 2019 40 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, 59 2198/DP 09/09/2020 250000 250000 250000 100 Yes mast light Binodpur Bazar 2020 Raina- I P.S. Asset Handover Report Wanting as per the Constn.. and purchase of 10 mtr. high 2019 - Executive Officer, 60 2198/DP 09/09/2020 250000 250000 250000 100 Yes Clause No. 8 under mast lightt Nandanpur village 2020 Raina- I P.S. updated BEUP Guidelines 2019 Total 4750000 4750000 4750000

Grand Total 22349758 22097479 22097479

41 ONGOING SCHEMES

42 NEPAL GHORUI, HON'BLE MLA-261 RAINA(SC) A.C.

Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ted of June of July 75% work 90% work Constn.. of entrance gate at Belsor Executive completed, 1st completed 1st 2018- 2554 1 Football Ground within Hijalna 24/05/2021 400000 Officer, Raina- 300000 0 0 No phase UC will be UC will be 2019 (042)/DP G.P. under Raina-I P.S. I P.S. submitted end of submit on June, 2021 06/08/2021 Total 400000 300000 Executive 90% work Constn. of Gate at Machkhanda 2019 - 85% work completed 1st UC 2 603/DP 10/02/2021 500000 Officer, Raina- 500000 375000 75 Yes School Math within Hijalna GP 2020 completed. will be submit on I P.S. 06/08/2021 80% work Executive completed, 1st 85% work Constn. of Samsan Chulli at 2019 - completed 1st UC 3 667/DP 12/02/2021 435836 Officer, Raina- 326877 0 0 No phase UC will be Srirampur Uttarpara Kaity 2020 will be submit on II P.S. submitted end of 06/08/2021 June, 2021 Total 935836 826877 375000 100% work West Bengal 100% work Constn.. and purchase of 10 mts completed, 1st 2020- Agro Industries Completed UC 4 high mast light at Baliyarpur under 2550/DP 24/05/2021 250000 187500 0 0 No phase UC will be will submitted 2021 Corporation submitted end of Natu GP 05/08/2021 Ltd. June, 2021 100% work West Bengal 100% work Constn.. and purchase of 10 mts completed, 1st 2020- Agro Industries Completed UC 5 high mast light near Saknara High 2550/DP 24/05/2021 250000 187500 0 0 No phase UC will be will submitted 2021 Corporation submitted end of School under Palashan GP 05/08/2021 Ltd. June, 2021 43 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ted of June of July Constn.. and purchase of 10 mts West Bengal 100% work completed, 1st 100% work high mast light beside Math 2020- Agro Industries 6 2550/DP 24/05/2021 250000 187500 0 0 No phase UC will be Completed UC Nurpur Maszidtala under Palashan 2021 Corporation submitted end of will submitted GP Ltd. June, 2021 05/08/2021 West Bengal 100% work Constn.. and purchase of 10 mts completed, 1st 100% work 2020- Agro Industries 7 high mast light near Dharan 2550/DP 24/05/2021 250000 187500 0 0 No phase UC will be Completed UC 2021 Corporation Barawaritala under Palashan GP submitted end of will submitted Ltd. June, 2021 05/08/2021 West Bengal 100% work Constn.. and purchase of 10 mts completed, 1st 100% work 2020- Agro Industries 8 high mast light near Milki Danga 2550/DP 24/05/2021 250000 187500 0 0 No phase UC will be Completed UC 2021 Corporation Bus Stand under Raina GP submitted end of will submitted Ltd. June, 2021 05/08/2021 West Bengal Constn.. and purchase of 10 mts 100% work 2020- Agro Industries 45% work 9 high mast light near Hariharpur 2550/DP 24/05/2021 250000 187500 0 0 No Completed UC 2021 Corporation completed. Siddeswari tala under Raina G.P. will submitted Ltd. 05/08/2021 West Bengal 100% work Constn.. and purchase of 10 mts completed, 1st 100% work 2020- Agro Industries 10 high mast light near Raina Eshani 2550/DP 24/05/2021 250000 187500 0 0 No phase UC will be Completed UC 2021 Corporation Kalitala under Raina G.P. submitted end of will submitted Ltd. June, 2021 05/08/2021 West Bengal 100% work Constn.. and purchase of 10 mts completed, 1st 100% work 2020- Agro Industries 11 high mast light near Nurpur 2550/DP 24/05/2021 250000 187500 0 0 No phase UC will be Completed UC 2021 Corporation Shivtala under Narugram G.P. submitted end of will submitted Ltd. June, 2021 05/08/2021 44 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ed of June of July

100% work Constn.. and purchase of 10 mts West Bengal 100% work completed, 1st high mast light near Mansdanga 2020- Agro Industries Completed UC 12 2550/DP 24/05/2021 250000 187500 0 0 No phase UC will be will submitted Barwararitala under Narugram 2021 Corporation submitted end of 05/08/2021 G.P. Ltd. June, 2021 100% work Constn.. and purchase of 10 mts West Bengal 100% work completed, 1st high mast light near Narugram 2020- Agro Industries Completed UC 13 2550/DP 24/05/2021 250000 187500 0 0 No phase UC will be will submitted Sarkari Kalitala under Narugram 2021 Corporation submitted end of 05/08/2021 G.P. Ltd. June, 2021 100% work West Bengal 100% work Constn.. and purchase of 10 mts completed, 1st 2020- Agro Industries Completed UC 14 high mast light near Samaspur 2550/DP 24/05/2021 250000 187500 0 0 No phase UC will be will submitted 2021 Corporation submitted end of Majhpara under Narugram G.P. 05/08/2021 Ltd. June, 2021 100% work West Bengal 100% work Constn.. and purchase of 10 mts completed, 1st 2020- Agro Industries Completed UC 15 high mast light near Kule Party 2550/DP 24/05/2021 250000 187500 0 0 No phase UC will be will submitted 2021 Corporation submitted end of office under Narugram G.P. 05/08/2021 Ltd. June, 2021 45% work Const. of Mukta Mancha at Executive completed 16 Raninagar near Jotram Belar Par 2781/DP 30/06/2021 350000 Officer, Raina- 2625000 0 0 No Nil Remaining work under Raina-I P.S. I P.S. will be completed by 25 days Total 3350000 4875000 0 Grand Total 4685836 6001877 375000 45 Shri Samar Hazra, Hon’ble M.L.A. of 262-Jamalpur (SC) AC

46 COMPLETED SCHEMES

47 SAMAR HAZRA, HON'BLE MLA-262 JAMALPUR(SC) A.C. UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed Constn. of Bituminus Road 2016 - Executive Officer, 1 from Maina Rail Gate to 2373/DP 18/10/2016 1500000 1053059 1053059 100 Yes 2017 Jamalpur P.S. Bituminus road at Nabagram

Instn of Tubewell at Uttar 2016 - Executive Officer, 2 Mohanpur Bandh at Jargram 2548/DP 03/11/2016 35000 35000 35000 100 Yes 2017 Jamalpur P.S. G.P.

Instn of Tubwwell at 2016 - Executive Officer, 3 Kashinathpur Tala of Kolsara 2548/DP 03/11/2016 35000 35000 35000 100 Yes 2017 Jamalpur P.S. village at Abujhati Asset Handover Report Wanting as Inst of tubewell at Saswan of 2016 - Executive Officer, 4 2548/DP 03/11/2016 35000 35000 35000 100 Yes per the Clause No. Salanpur village at Ajhapur 2017 Jamalpur P.S. 8 under updated BEUP Guidelines Constn. of Pucca Drain at 2019 Ramnathpur village from 2016 - Executive Officer, 5 2685/DP 18/11/2016 60000 58462 58462 100 Yes Sandani Mondal Shop to Biswa 2017 Jamalpur P.S. Pukur Constn. of Pucca drain at 2016 - Executive Officer, 6 Ramnathpur vill from house of 2685/DP 18/11/2016 135000 132178 132178 100 Yes 2017 Jamalpur P.S. N. Santra

Constn. of Black Top Toad 2016 - Executive Officer, 7 from Badhpur Raildhar to 2717/DP 21/11/2016 1000000 995070 995070 100 Yes 2017 Jamalpur P.S. Bakultala at Jougram G.P. 48 Sanction UC Sl. Date of Amount Amount Amount Physical Name of the Scheme Year Order Executing Agency Submit Asset Handover Status No. Sanction Sanction Released Utilized Progress No ted Constn. of Jhama Compaction Asset Handover Report 2016 - Executive Officer, Wanting as per the Clause 8 road from Nabagram MBF brick 819/DP 16/03/2017 200000 172845 172845 100 Yes 2017 Jamalpur P.S. No. 8 under updated BEUP field to Verili Khalar math Guidelines 2019 Instt of ( 4 ) four Nos. Deep Exe. Engg. Purba Asset Handover Report 2016 - Received as per the Clause 9 Tubewell for Irrigation of Land 1657/DP 09/06/2017 2168428 Bardhaman (Agri- 1869486 1869486 100 Yes 2017 No. 8 under updated BEUP 500 Bighas of Paratal -I G.P. Irrign.) Divn. Guidelines 2019 Constn. of Bituminus road from Nabagram MBF Brick field to 2016 - Executive Officer, 10 2337/DP 24/08/2017 478456 478456 478456 100 Yes Verili Khelar Math of Ajhapur 2017 Jamalpur P.S. G.P.

Purchase an Ambulance for 2016 - District Magistrate, 11 2530/DP 13/09/2017 595204 595204 595204 100 Yes Panchra G.P. 2017 Burdwan

Instn of five No Solar Light on the Asset Handover Report 2016 - Executive Officer, 12 Math Rasta from Nabagram Rly. 2711/DP 17/10/2017 101250 101250 101250 100 Yes Wanting as per the Clause 2017 Jamalpur P.S. No. 8 under updated BEUP station to Musunda Guidelines 2019 Instn of one no Tubewell near 2016 - Executive Officer, 13 Mahisgharia Kalitala Adibasipara 3326/DP 19/12/2017 40000 40000 40000 100 Yes 2017 Jamalpur P.S. Nutanpukurpar of Jargram

Instn of one tubewell near Siali 2016 - Executive Officer, 14 3326/DP 19/12/2017 40000 40000 40000 100 Yes Kalitala of Jotsrirampur 2017 Jamalpur P.S.

Total 6423338 5641010 5641010 49 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ted Constn. of Swamsan Chulli at Bele Executive 2017 - 15 Swasan nearest to the 2771/DP 30/10/2017 318805 Officer, 318805 318805 100 Yes Asset Handover Report 2018 Khelaghar ground under Jamalpur Jamalpur P.S. Wanting as per the Clause Constn. of Concrete Road from Executive No. 8 under updated BEUP 2017 - 16 Panchra Simuldanga to 3020/DP 17/11/2017 199993 Officer, 199993 199993 100 Yes Guidelines2019 2018 Ghatakpukur of Panchra G.P. Jamalpur P.S. Asset Handover Report Constn. of Samsan Chulliand Executive 2017 - Received as per the Clause 17 waiting Roomat Mugura Village 3020/DP 17/11/2017 500000 Officer, 500000 500000 100 Yes 2018 No. 8 under updated BEUP near Raina- I P.S. Guidelines 2019 Constn. of School Building of Executive 2017 - 18 Basantapur Junior High School at 3069/DP 23/11/2017 480291 Officer, 480291 480291 100 Yes Asset Handover Report 2018 Paratal G.P. Jamalpur P.S. Wanting as per the Clause Instn of one No. Cycllinder well at Executive No. 8 under updated BEUP 2017 - 19 Shambhupur Purba Adibasipara 3325/DP 19/12/2017 40000 Officer, 40000 40000 100 Yes Guidelines 2019 2018 under Jamalpur Jamalpur P.S. Constn. of Moorum Road from Asset Handover Report Executive Sankita to Boro Road from 2017 - Received as per the Clause 20 83/DP 11/01/2018 1500000 Officer, 1500000 1500000 100 Yes Angona Asaktala to Dalshinkul 2018 No. 8 under updated BEUP Raina- I P.S. village Guidelines 2019 Executive Constn.. of Swasan Chulli and 2017 - 21 221/DP 01/02/2018 497500 Officer, 497500 497500 100 Yes Asset Handover Report waiting room at Karalgram 2018 Jamalpur P.S. Wanting as per the Clause Executive No. 8 under updated BEUP Constn. of Samsan Chulli and 2017 - 22 221/DP 03/02/2018 497400 Officer, 497400 497400 100 Yes Guidelines 2019 waiting room at Jharagram village 2018 Jamalpur P.S.

50 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Constn. of Samsan Chulli and 2017 - Executive Officer, 23 waiting room at Chaksanjadi vill 221/DP 03/02/2018 500000 500000 500000 100 Yes 2018 Jamalpur P.S. near Khelar Math under Jamalpur Asset Handover Instn of one no. Cycllinder 2017 - Executive Officer, Report Wanting as 24 680/DP 27/03/2018 39800 39800 39800 100 Yes Tubewell at Kamghosha village 2018 Jamalpur P.S. per the Clause No. 8 Instn of one no. Cycllinder 2017 - Executive Officer, under updated BEUP 25 680/DP 27/03/2018 39620 39620 39620 100 Yes Tubewell at Sukpur village 2018 Jamalpur P.S. Guidelines 2019 Instn of one no. Cycllinder 2017 - Executive Officer, 26 Tubewell at Ramchandrapur 680/DP 27/03/2018 39740 39740 39740 100 Yes 2018 Jamalpur P.S. village Installation of One no., Tubewell Asset Handover Report with Electric Motor at Meral 2017 - Executive Officer, Received as per the 27 1137/DP 21/06/2018 100000 100000 100000 100 Yes Clause No. 8 under village under Mugura G.P. within Raina- I P.S. 2018 updated BEUP Raina-I P.S. Guidelines 2019 Constn.. of one Community Hall 2017 - Executive Officer, 28 at Balarampur village at Berugram 470/DP 14/02/2019 500000 498500 498500 100 Yes 2018 Jamalpur P.S. G.P. under Jamalpur P.S. Asset Handover Constn.. of one wall and one 2017 - Executive Officer, Report Wanting as 29 pucca ghat at Ajhapur Hattala 709/DP 24/02/2020 500000 499900 499900 100 Yes 2018 Jamalpur P.S. per the Clause No. 8 within Jamalpur P.S. under updated BEUP Constn.. of drain beside newly Guidelines 2019 Constn.. bituminus road at Moyna 2017 - Executive Officer, 30 4271/DP 27/11/2019 201347 201347 201347 100 Yes under Ajhapur G.P. within 2018 Jamalpur P.S. Jamalpur P.S. Total 5954496 5952896 5952896 51 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn.. of Toe Wall beside Uttarsura District Majher Ghosh Para road for widening and 2018 - 31 1997/DP 06/09/2018 600000 Magistrate, 541378 541378 100 Yes strengthing of village road under Jamalpur 2019 Burdwan P.S. Constn.. of Bituminous road from Maina District Durgatala to Canelpul with drain from B. 2018 - 32 1997/DP 06/09/2018 1200000 Magistrate, 1200000 1200000 100 Yes Bag house to S. Bag House under Jamalpur 2019 Burdwan Asset Handover P.S Report Wanting as Constn.. of one shed at Jamalpur Block Executive per the Clause No. 8 2018 - 33 Hospital under Jamalpur G.P. within 2121/DP 20/09/2018 200000 Officer, 200000 200000 100 Yes under updated BEUP 2019 Jamalpur P.S. Jamalpur P.S. Guidelines 2019 Installation of 1 no. Tubewell with Executive 2018 - 34 Submersible Motor Pump and pipe line 2282/DP 10/10/2018 100000 Officer, 99930 99930 100 Yes 2019 Kulingram High School within Jamalpur P.S. Jamalpur P.S. Constn.. of Swasan Chulli with waiting room Executive 2018 - 35 at astai village under Abujhati-I GP within 3118/DP 07/12/2018 500000 Officer, 498250 498250 100 Yes 2019 Jamalpur Ps. Jamalpur P.S. Asset Handover Constn.. of School Building (Class room) of Executive 2018 - Report Received as 36 Meral FP School at Meral Village under 3118/DP 07/12/2018 500000 Officer, 499405 499405 100 Yes per the Clause No. 8 2019 Mugura within Raina-I P.S. Raina- I P.S. under updated BEUP Guidelines 2019 Constn.. of waiting shed for Jamudaha Executive 2018 - 37 Kalitala Swasan under Berugram G.P. 418/DP 06/02/2019 400000 Officer, 399880 399880 100 Yes 2019 Asset Handover within Jamalpur P.S. Jamalpur P.S. Report Wanting as Installation of 1 no. cyllinder tube well at per the Clause No. 8 Executive Sially village near masjidtala JL no. 72 Plot 2018 - under updated BEUP 38 844/DP 06/03/2019 45000 Officer, 45000 45000 100 Yes Guidelines 2019 no. 1263 under Jotesriram G.P. within 2019 Jamalpur P.S. Jamalpur P.S. 52 Amount UC Sl. Sanction Date of Amount Executing Amount Physical Asset Handover Name of the Scheme Year Release Submi No. Order No Sanction Sanction Agency Utilized Progress Status d tted Installion of 1 no. cycillender tube well at Executive Mosagram Miarber para Plot no. 1731 near 2018 - 39 844/DP 06/03/2019 45000 Officer, 44775 44775 100 Yes Abdul Razek house under Panchra G.P. within 2019 Asset Handover Report Jamalpur P.S. Jamalpur P.S. Wanting as per the Clause No. 8 under Installation of 1 no. cyllinder tube well at Executive updated BEUP Mosagram Fotepur para near Sk. Ohidul house 2018 - Guidelines 2019 40 844/DP 06/03/2019 45000 Officer, 45000 45000 100 Yes at Mosagram village under Panchra G.P. 2019 Jamalpur P.S. within Jamalpur P.S. Asset Handover Report Installation of 1 no. cyllinder tube well at Executive 2018 - Received as per the 41 Uchitpur village JL no. 92 Plot no. 503 under 844/DP 06/03/2019 45000 Officer, Raina- I 45000 45000 100 Yes Clause No. 8 under 2019 Mugura G.P. within Raina-I P.S. P.S. updated BEUP Guidelines 2019 Installation of one Cylider Tube well with Executive Asset Handover Report 2018 - 42 subnersible motor with water tank and 2009/DP 07/08/2019 100000 Officer, 100000 100000 100 Yes Wanting as per the Clause 2019 No. 8 under updated BEUP Pipeline at Nabagram Moyna L.S.B Vidyalya Jamalpur P.S. Guidelines 2019 Asset Handover Report Installation of 1 no. tubewell at Meral Math Executive 2018 - Received as per the 43 Para near Laltu Cycle Shop under Mugura 4235/DP 25/11/2019 45000 Officer, Raina- I 45000 45000 100 Yes Clause No. 8 under 2019 G.P. P.S. updated BEUP Guidelines 2019 Executive Constn.. of School Building at Junior High 2018 - 44 4514/DP 12/12/2019 499850 Officer, 499850 499850 100 Yes School at Duluk Village 2019 Asset Handover Report Jamalpur P.S. Wanting as per the Clause No. 8 under Installa of one tubewell at Astai Sasan at Astai Executive updated BEUP 2018 - 45 village under Abujhati-I GP. within Jamalpur 523/DP 07/02/2020 45000 Officer, 45000 45000 100 Yes Guidelines 2109 2019 P.S. Jamalpur P.S. 53 UC Asset Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Handover No. Order No Sanction Sanction Agency Released Utilized Progress ted Status

Executive Const. of one roof shed Jaragram Makhanlal 2018 - 46 710/DP 24/02/2020 199900 Officer, 199900 199900 100 Yes Pathagar at Jarogram under Jarogram GP. 2019 Jamalpur P.S. Asset Handover Report Wanting Constn.. of one patients shed and purified Executive as per the 2018 - 47 drinking water system at Chakshanjadi PHC 2195/DP 09/09/2020 437400 Officer, 437182 437182 100 Yes Clause No. 8 2019 within Jamalpur P.S. Jamalpur P.S. under updated BEUP Constn.. of bituminus road from Amarpur Executive Guidelines 2109 Bimola Krishi High School to Damodar bandh 2018 - 48 1307/DP 30/05/2019 500000 Officer, 498750 498750 100 Yes at Amarpur village under Jotesriram 2019 Jamalpur P.S. G.P. within Jamalpur P.S.

Total 5506000 5444300 5444300

Constn.. of cycle stand at Ajhapur Balika Executive 2019 - 49 Vidyalaya (High) under Ajhapur GP. within 728/DP 25/02/2020 400000 Officer, 397200 397200 100 Yes 2020 Jamalpur P.S. Jamalpur P.S. Asset Handover Report Wanting Executive as per the Constn.. of Manch shed at Nabogram Moyna 2019 - 50 2232/DP 14/09/2020 653042 Officer, 653042 653042 100 Yes Clause No. 8 P.B. High School under Ajhapur G.P. 2020 Jamalpur P.S. under updated BEUP Installation of one no cylinder tube well at Executive Guidelines 2109 2019 - 51 Sanchra Birghosh Pukurpar within Jamalpur 2232/DP 14/09/2020 45000 Officer, 45000 45000 100 Yes 2020 P.S. Jamalpur P.S. 54 UC Asset Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Handover No. Order No Sanction Sanction Agency Released Utilized Progress ted Status

Executive Constn.. of Swasan Chulli at Sambhupur 2019 - 52 728/DP 25/02/2020 400000 Officer, 397000 397000 100 Yes village under Berugram G.P. 2020 Jamalpur P.S.

Constn.. of one dinning room for Midday meal Executive 2019 - 53 at Guregarh High School under Chakdighi 2232/DP 14/09/2020 587018 Officer, 587018 587018 100 Yes 2020 G.P. Jamalpur P.S. Asset Handover Report Wanting Executive Constn.. one children park at Narayanpur 2019 - as per the 54 2233/DP 14/09/2020 500000 Officer, Raina- I 500000 500000 100 Yes village under Mugura G.P. 2020 Clause No. 8 P.S. under updated BEUP Executive Guidelines 2109 Constn.. of one Class room at Ajhapur 2019 - 55 3017/DP 13/11/2020 604462 Officer, 604462 604462 100 Yes Chatushpally Jr. High School at Abujhati P.S. 2020 Jamalpur P.S.

Executive Installation of one cylinder tube well at 2019 - 56 3330/DP 14/12/2020 45000 Officer, Raina- I 45000 45000 100 Yes Narayanpur village under Raina -I P.S. 2020 P.S.

Total 3234522 3228722 3228722 Grand Total 21118356 20266928 20266928

55 ONGOING SCHEMES

56 SAMAR HAZRA, HON'BLE MLA 262 JAMALPUR(SC) A.C. UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt for the Month for the Month No. Order No Sanction Sanction Agency Released Utilized Progress ed of June of July Installation of one cylinder tube 100% work 100% work Executive completed, final well at Jotekrista Hazra Para 2016- completed UC 1 3178/DP 03/12/2020 50000 Officer, 50000 37500 75 Yes UC will be under Jamalpur-II G.P. within 2017 submitted on Jamalpur P.S. submitted very Jamalpur P.S. soon. 06/08/2021 75% work 75% work Constn. of Toilet with UP 2016- Executive completed, 1st completed UC 2 Gradation of Main Building at 2017 330/DP 29/01/2021 299100 Officer, 224325 0 0 No Phase of UC will submitted on Chakdighi PHC Jamalpur P.S. be submitted end of June, 2021 06/08/2021 Total 349100 274325 37500 100% Work 100% work Constn. of Two Nos of Pucca Executive completed, final 2018- completed UC 3 Ghat with Toe wall at Moyna 251/DP 25/01/2021 500000 Officer, 500000 375000 75 Yes UC will be 2019 submitted on Village Jamalpur P.S. submitted after receiving of fund. 06/08/2021 Total 500000 500000 375000

Installation of one one Cylinder 100% work 100% work Executive tube well at Sambhupur village 2019- completed, final completed UC 4 3179/DP 03/12/2020 46982 Officer, 46982 35236 75 Yes UC will be Duley para under Berugram 2020 submitted on Jamalpur P.S. submitted very G.P. within Jamalpur P.S. soon. 06/08/2021 Installation of one Cylinder tube 100% work 100% work Executive well at Danga Faridpur village 2019- completed, final completed UC 5 3179/DP 03/12/2020 49980 Officer, 49980 37485 75 Yes UC will be near Salchand under Jamalpur-I 2020 submitted on Jamalpur P.S. submitted very G.P. within Jamalpur P.S. soon. 06/08/2021 57 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt for the Month for the Month No. Order No Sanction Sanction Agency Released Utilized Progress ed of June of July

100% work Installation of one cylinder tube 100% work Executive completed, final well at Adghoshar Par near 2019- completed UC 6 3179/DP 03/12/2020 50000 Officer, 50000 37500 75 Yes UC will be Ranjit Halder under Ajhapur GP 2020 submitted on Jamalpur P.S. submitted very within Jamalpur P.S. 06/08/2021 soon. 100% work Constn. of one sasan waiting 100% work Executive completed, final room at Astai village under 2019- completed UC 7 3179/DP 03/12/2020 300000 Officer, 300000 225000 75 Yes UC will be Abujhati-I G.P. within Jamalpur 2020 submitted on Jamalpur P.S. submitted very P.S. 06/08/2021 soon. 100% work 100% work Installan of One Solar light Executive completed, final 2019- completed UC 8 Mayna Rail Gate Kalitala at 261/DP 25/01/2021 49750 Officer, 49750 37313 75 Yes UC will be 2020 submitted on Mayna village Jamalpur P.S. submitted very 06/08/2021 soon. 100% work 100% work Installan of One Solar light at Executive completed, final 2019- completed UC 9 Near Durgatala Nabagram 261/DP 25/01/2021 49750 Officer, 49750 37313 75 Yes UC will be 2020 submitted on village at Lahapara Jamalpur P.S. submitted very 06/08/2021 soon. 100% work 100% work Installan of One Solar light at Executive completed, final 2019- completed UC 10 Jamudaha Sasan at Jamudaha 261/DP 25/01/2021 49750 Officer, 49750 37313 75 Yes UC will be 2020 submitted on Villagene at near kalitala Jamalpur P.S. submitted very 06/08/2021 soon. 58 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month of for the Month No. Sanction Sanction Agency Released Utilized Progress No ted June of July

90% work 100% work Executive Constn. of of Samsan Waiting 2019- completed, 1st completed UC 11 261/DP 25/01/2021 348950 Officer, 261711 0 0 No room at Panch Simuli village 2020 Phase UC will be submitted on Jamalpur P.S. submitted on 1st 06/08/2021 week of July,2021

75% work 75% work Executive Constn. of Community Hall at 2019- completed, final completed UC 12 261/DP 25/01/2021 550000 Officer, 550000 412500 75 Yes Basodapur Nabagram Village 2020 UC will be submitted on Jamalpur P.S. submitted 1st week 06/08/2021 of July, 2021

Installation of one submersible 100% work 100% work Executive pump with pipe line at Karala 2019- completed, final completed UC 13 2552/DP 24/05/2021 1200000 Officer, 900000 900000 75 Yes village under Jamalpur G.P. 2020 UC will be submitted on Jamalpur P.S. within Jamalpur P.S. submitted after 06/08/2021 receiving of fund. Total 2695162 2607923 1759660 75% work Executive Constn. of one office room 2020 - completed UC 14 2786/DP 30/06/2021 499400 Officer, 374550 0 0 No Nil adjustent BMOH office 2021 submitted Jamalpur P.S. 06/08/2021 75% work Executive Constn. of Mancha shed cum 2020 - completed UC 15 2786/DP 30/06/2021 549065 Officer, 411779 0 0 No Nil atchala near Tele F.P. School 2021 submitted Jamalpur P.S. 06/08/2021 59 Sanction UC Present Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit Status for the for the Month No. Sanction Sanction Agency Released Utilized Progress No ted Month of June of July

75% work Constn. of children park at Executive 2020 - completed UC 16 Surekalna Bandhab Sammilon 2786/DP 30/06/2021 599400 Officer, 449550 0 0 No Nil 2021 submitted Play Ground Jamalpur P.S. 06/08/2021

75% work Executive Installation of 5 nos of Solar 2020 - completed UC 17 2786/DP 30/06/2021 248750 Officer, 186562 0 0 No Nil Light at BDO office 2021 submitted Jamalpur P.S. 06/08/2021

75% work Installation of 2 nos. of solar Executive 2020 - completed UC 18 light at Mosagram Village 2786/DP 30/06/2021 99950 Officer, 74962 0 0 No Nil 2021 submitted near Majhipar Mayerthan Jamalpur P.S. 06/08/2021

75% work Constn. of sahapur Sri Executive 2020 - completed UC 19 Ramkrishna Vivekananda 2786/DP 30/06/2021 498501 Officer, 373876 0 0 No Nil 2021 submitted Sava Kendra Jamalpur P.S. 06/08/2021

Total 2495066 1871279 0

Grand Total 6039328 5253527 2172160

60 Shri Saikat Panja, Hon’ble M.L.A. of 263-Monteswar AC

61 COMPLETED SCHEMES

62 Lt. SAJAL PANJA & SAIKAT PANJA, HON'BLE MLA 263 MONTESWAR A.C.

UC Sl. Sanction Date of Amount Amount Amount Physical Asset Handover Name of the Scheme Year Executing Agency Submit No. Order No Sanction Sanction Released Utilized Progress Status ted

Constn. of Concrete road from Bijur 2016 - Executive Officer, 1 230/DP 18/01/2017 200000 200000 200000 100 Yes Hattala to Doltala of Bijur G.P. 2017 Memari- II P.S.

Constn. of Boundary Wall of Birta 2016 - Executive Officer, 2 230/DP 18/01/2017 300000 300000 300000 100 Yes Hospital of Bohar G.P. 2017 Memari- II P.S.

High Must Electric Light at 2016 - Executive Officer, 3 230/DP 18/01/2017 200000 174679 174679 100 Yes More Bijur G.P. 2017 Memari- II P.S. Asset Handover High Must Electric Light at 2016 - Executive Officer, 4 230/DP 18/01/2017 200000 155830 155830 100 Yes Report Received Mondalgram Bazar 2017 Memari- II P.S. as per the Clause No. 8 under High Must at Bitra Barowaritala of 2016 - Executive Officer, updated BEUP 5 230/DP 18/01/2017 200000 153902 153902 100 Yes Bohar G.P. 2017 Memari- II P.S. Guidelines 2019

Constn. of waiting shed at Dhokolpur 2016 - Executive Officer, 6 230/DP 18/01/2017 200000 182984 182984 100 Yes of Bijur G.P. 2017 Memari- II P.S.

High Mast Electric Light at Bohar 2016 - Executive Officer, 7 230/DP 18/01/2017 200000 168638 168638 100 Yes Bazar of Bohar G.P. 2017 Memari- II P.S.

Constn..of waiting room infront of 2016 - Executive Officer, 8 Rabindra Nazrul Mahavidyalaya of C- 522/DP 16/02/2017 300000 300000 300000 100 Yes 2017 Memari- II P.S. Satgachia- I GP 63 Sanction UC Sl. Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Order Submit No. Sanction Sanction Agency Released Utilized Progress Status No ted

Drinking Water Project at 2016 - Executive Officer, 9 Majhergram Bazar Source of Water I 743/DP 09/03/2017 300000 210000 210000 100 Yes Asset Handover Report 2017 Monteswar P.S. HP Motor of Majher Gram Received as per the Clause No. 8 under Constn. of C C Road from Bhagra 2016 - Executive Officer, updated BEUP 10 Bara Masjid towards Bagra village 806/DP 15/03/2017 400000 400000 400000 100 Yes 2017 Monteswar P.S. Guidelines 2019 road upto Bagra-Mulgram Asset Handover Report High Mast Electric Light at Bijur 2016 - Executive Officer, Wanting as per the 11 2018/DP 18/07/2017 200000 164607 164607 100 Yes Clause No. 8 under Bazar Hattala of Bijur-I G.P. Memari- II P.S. 2017 updated BEUP Guidelines 2019 Total 2700000 2410640 2410640 Constn.. of High Mast Light at 2017 - Executive Officer, 12 Sridharpur Hattala of Satgachia-I 2288/DP 18/08/2017 200000 135377 135377 100 Yes 2018 Memari- II P.S. G.P.

Constn. of High Mast Light at Jhikra 2017 - Executive Officer, 13 2288/dp 18/08/2017 200000 134231 134231 100 Yes More of Satgachia-I G.P. 2018 Memari- II P.S. Asset Handover Report Received as per the Clause No. 8 under Constn. of High Mast Light at Bohar 2017 - Executive Officer, 14 2288/DP 18/08/2017 200000 132756 132756 100 Yes updated BEUP Hattala of Bohar-II G.P. 2018 Memari- II P.S. Guidelines 2019

High Mast Light at Barapalason to 2017 - Executive Officer, 15 2288/DP 18/08/2017 200000 149319 149319 100 Yes Barapalason-II G.P. 2018 Memari- II P.S.

Constn. of waiting Shedat Ashapur 2017 - Executive Officer, 16 2288/DP 18/08/2017 200000 200000 200000 100 Yes of Bijur-II G.P. 2018 Memari- II P.S. 64 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Constn. of Waiting Shed at Kala Dighi 2017 - Executive Officer, 17 2288/DP 18/08/2017 200000 200000 200000 100 Yes Par of Barapalason-I G.P. 2018 Memari- II P.S.

Constn. of Waiting Shed at Begunia 2017 - Executive Officer, 18 2288/DP 18/08/2017 200000 200000 200000 100 Yes More of Bijur-II G.P. 2018 Memari- II P.S.

Constn. of Concrete road from Bijur 2017 - Executive Officer, 19 2288/DP 18/08/2017 200000 200000 200000 100 Yes Hattala to Doltala of Bijur-I G.P. 2018 Memari- II P.S.

Asset Handover Constn. of Concrete road at Paharhati 2017 - Executive Officer, Report Received as 20 2288/DP 18/08/2017 200000 200000 200000 100 Yes Golapmoni High School 2018 Memari- II P.S. per the Clause No. 8 under updated BEUP Guidelines Constn. of PCC Road from S. Banerjee 2017 - Executive Officer, 2019 21 House to K. Mondal house of 2823/DP 06/11/2017 300000 300000 300000 100 Yes 2018 Monteswar P.S. Monteswar G.P.

Constn. of PCC Road from Garsona 2017 - Executive Officer, 22 Danga Ramchandra House to Hazra 2823/DP 06/11/2017 150000 149726 149726 100 Yes 2018 Monteswar P.S. Para Rasta of Mamudpur G.P.

Constn. of PCC Road at Susunia 2017 - Executive Officer, 23 2823/DP 06/11/2017 200000 200000 200000 100 Yes Ranibala Bidyamandir of Susunia G.P. 2018 Monteswar P.S.

65 UC Sl. Sanction Date of Amount Amount Amount Physical Asset Handover Name of the Scheme Year Executing Agency Submitt No. Order No Sanction Sanction Released Utilized Progress Status ed Constn. of PCC Road from A.Pal 2017 - Executive Officer, 24 house to M. Santra house at 2823/DP 06/11/2017 100000 99278 99278 100 Yes 2018 Monteswar P.S. Daukadanga of Denur G.P. Constn. of three nos. Culvert 2017 - Executive Officer, 25 between Sahajadpur to Rakuspur 3065/DP 23/11/2017 300000 300000 300000 100 Yes 2018 Memari- II P.S. road of Bohar-I G.P Constn. of PCC Road from 2017 - Executive Officer, 26 Bandhupur Durgatala to Uday 3065/DP 23/11/2017 150000 150000 150000 100 Yes 2018 Monteswar P.S. Ghosh Kolghar of Mamudpur G.P. Constn. of Community Hall at Ujna 2017 - Executive Officer, 27 Adibasipara of Bhagra Mulgram 3065/DP 23/11/2017 300000 299135 299135 100 Yes 2018 Monteswar P.S. Asset Handover Report G.P. Received as per the Clause Constn. of PCC Road from pakka 2017 - Executive Officer, No. 8 under updated BEUP 28 3065/DP 23/11/2017 110000 110000 110000 100 Yes Rasta to N.Raj house at 2018 Monteswar P.S. Guidelines 2019 Constn. of Boundary Wall around 2017 - Executive Officer, 29 Banui Panchapali Vidyamandir of 3065/DP 23/11/2017 100000 100000 100000 100 Yes 2018 Monteswar P.S. Susunia G.P. Constn. of PCC Road from Parulia 2017 - Executive Officer, 30 Tematha N. Chatterjee house to 3289/DP 13/12/2017 300000 298897 298897 100 Yes 2018 Monteswar P.S. Mirpur Bazar of Majher Gram Constn. of PCC Foot Path from S. 2017 - Executive Officer, 31 3289/DP 13/12/2017 50000 49492 49492 100 Yes Hazra to M. Hazra house at Kitsihi 2018 Monteswar P.S. Constn. of PCC Foot Path from T 2017 - Executive Officer, 32 Hazra house to N. Hazra House at 3289/DP 13/12/2017 50000 49799 49799 100 Yes 2018 Monteswar P.S. Katsihi 66 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn. of PCC Road from Daspara 2017 - Executive Officer, 33 SSK School via Kabarsthan to 3289/DP 13/12/2017 300000 300000 300000 100 Yes 2018 Monteswar P.S. Bamunia Paka rasta

Constn. of PCC Road from Hafijul 2017 - Executive Officer, 34 Sk house to Ansar Mallick house 3289/DP 13/12/2017 200000 200000 200000 100 Yes 2018 Monteswar P.S. via Ibraham Sk house Asset Handover Constn. of PCC Road from Report Received as 2017 - Executive Officer, 35 Nabagram towards Baishnab 1417/DP 01/08/2018 200000 200000 200000 100 Yes per the Clause No. 8 2018 Monteswar P.S. Danga High School under updated BEUP Guidelines Constn. of PCC Road from Khirod 2017 - Executive Officer, 2019 36 Das houseto Madhai Das House via 1820/DP 14/08/2018 200000 199252 199252 100 Yes 2018 Monteswar P.S. Panchanantala

Constn.. of Baitarani Scheme at Exe. Engg. PWD Monteswar and Ghatak Para More 2017 - 37 2459/DP 10/10/2018 890000 (Social Sector), 694916 694916 100 Yes (mouza-Satgachia) within 2018 Burdwan. Monteswar P.S. Asset Handover Report Wanting as Constn.. of waiting shed at 2017 - Executive Officer, per the Clause No. 8 38 314/DP 13/02/2021 100000 100000 100000 100 Yes Pakurmuri of Bhagason G.P. 2018 Monteswar P.S. under updated BEUP Guidelines 2019 Total 5800000 5352178 5352178 67 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ted

Constn.. of CC road from 2018 - Executive Officer, 39 2077/DP 18/09/2018 300000 299910 299910 100 Yes Galatun to Denua Village 2019 Monteswar P.S.

Constn. of Concrete Road 2018 - Executive Officer, 40 from Tribarna Club to 2077/DP 18/09/2018 50000 50000 50000 100 Yes 2019 Monteswar P.S. Baromatala of Kusumgram Asset Handover Report Constn.. of CC road from Received as per the Ansar Ali Mondal to 2018 - Executive Officer, 41 2077/DP 18/09/2018 250000 250000 250000 100 Yes Clause No. 8 under Gandgoria Masjid under 2019 Monteswar P.S. updated BEUP Mamudpur-I GP Guidelines 2019 Constn.. of Beneficiaries 2018 - Executive Officer, 42 refreshment shed at 3217/DP 17/12/2018 548000 548000 548000 100 Yes 2019 Memari- II P.S. Gargeswar Constn.. of waiting shed at 2018 - Executive Officer, 43 jamna Shivtala of Jamna 3217/DP 17/12/2018 150000 150000 150000 100 Yes 2019 Monteswar P.S. G.P. 12 watt Led Solar Street West Bengal Agro Light with 5 meter 2018 - Industries 44 563/DP 20/02/2019 21420 21420 21420 100 Yes Satgachia Paschimpara 2019 Corporation Ltd. Asset Handover Report under Satgachia-I G.P 23 B Wanting as per the Nine Mtr high Must tower Clause No. 8 under lighting system 4 nos 80 West Bengal Agro updated BEUP watt Led lighting fitting 2018 - Industries 45 561/DP 20/02/2019 180000 180000 180000 100 Yes Guidelines 2019 with each complete with 2019 Corporation Ltd. all accessories under 23 B Susuni G.P. 68 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ted 12 watt Led Solar Street West Bengal Agro Light with 5 mtr tuble pole 2018 - Industries 46 40 AMPS Battery Near 561/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. Bhadai Masjid under 23 B Bhagra Mulgram G.P. 12 watt Led Solar street West Bengal Agro light with 5 mtr tuble pole 2018 - Industries 47 40 AMPS Battery near 561/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. kaltala under Bhagra 23 B Mulgram G.P. 12 watt Led Solar street West Bengal Agro light with 5 mtr tuble pole 2018 - Industries 48 561/DP 20/02/2019 21420 21420 21420 100 Yes Asset Handover Report 40 AMPS Battery under 2019 Corporation Ltd. Wanting as per the Bhagra Mulgram G.P. 23 B Clause No. 8 under 12 watt Led Solar street West Bengal Agro updated BEUP light with 5 mtr tuble pole 2018 - Industries 49 561/DP 20/02/2019 21420 21420 21420 100 Yes Guidelines 2019 40 AMPS Battery under 2019 Corporation Ltd. Bhagra Mulgram G.P... 23 B 12 watt Led Solar Street West Bengal Agro light with 5 mtr tuble 2018 - Industries 50 pole40 AMPSb Battery 561/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. near Boro Masjid under 23 B Bhagra Mulgram G.P. 12 watt Led Solar Street West Bengal Agro light with 5 mtr. tuble pole 2018 - Industries 51 40 AMPS Battery near 561/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. Masjidtala under Bhagra 23 B Mulgram G.P. 69 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ted 12.5 Mtr Mini high Must Tower lighting System with 6 West Bengal Agro nos 150 Watt Led Light at 2018 - Industries 52 563/DP 20/02/2019 455000 454999 454999 100 Yes Malamba Bazar under 2019 Corporation Ltd. Barphalasan- I G.P within 23 B Memari-II P.S. 7.5 Mtr Tubler Pole with 4 West Bengal Agro nos. 100 watt Led Light fitting 2018 - Industries 53 561/DP 20/02/2019 100000 100000 100000 100 Yes with each complete with all 2019 Corporation Ltd. acceories Majhergram G.P. 23 B 12 watt Led Solar Street Light West Bengal Agro with 5 meter Ahira near 2018 - Industries 54 563/DP 20/02/2019 21420 21420 21420 100 Yes Asset Handover Report Durgatala under Satgachia-I 2019 Corporation Ltd. Wanting as per the G.P 23 B Clause No. 8 under 9 Mtr Tubler pole with 4 nos West Bengal Agro updated BEUP 120 watt Led light fittings 2018 - Industries Guidelines 2019 55 with each complete with all 561/DP 20/02/2019 150000 150000 150000 100 Yes 2019 Corporation Ltd. accressories under 23 B Kusumgram G.P. 12 watt Led Solar Street Light West Bengal Agro with 5 meter Satgachia near 2018 - Industries 56 563/DP 20/02/2019 21420 21420 21420 100 Yes Sastitala under Satgachia-I 2019 Corporation Ltd. G.P. 23 B Nine Mtr high Must tower West Bengal Agro lighting system 4 nos 80 watt 2018 - Industries 57 Led lighting fitting with each 561/DP 20/02/2019 180000 180000 180000 100 Yes 2019 Corporation Ltd. complete with all accessories 23 B under Piplon G.P. 70 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Asset Handover Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status Nine Mtr Mini high Must tower West Bengal Agro lighting system 6 nos 80 watt Led 2018 - Industries 58 light fitting with each complete 561/DP 20/02/2019 215475 215475 215475 100 Yes 2019 Corporation Ltd. with all accessories under 23 B Baghason G.P. Nine Mtr Mini high Must tower West Bengal Agro lighting system 6 nos 80 watt Led 2018 - Industries 59 light fitting with each complete 561/DP 20/02/2019 215475 215475 215475 100 Yes 2019 Corporation Ltd. with all accessories under 23 B Kusumgram G.P. Nine Mtr Mini high Must tower West Bengal Agro lighting system 6 nos 80 watt Led 2018 - Industries 60 light fitting with each complete 561/DP 20/02/2019 215475 215475 215475 100 Yes Asset Handover 2019 Corporation Ltd. with all accessories under Report Wanting as 23 B Monteswar G.P. per the Clause No. Nine Mtr Mini high Must Tower 8 under updated West Bengal Agro lighting System with 6 nos 120 BEUP Guidelines 2018 - Industries 61 Watt Led Light Near Jabuldanga 563/DP 20/02/2019 215475 215475 215475 100 Yes 2019 2019 Corporation Ltd. More under Bijur-I G.P within 23 B Memari-II P.S. Nine Mtr Mini high Must Tower West Bengal Agro lighting System with 6 nos 120 2018 - Industries 62 Watt Led Light at Bora Hazra Para 563/DP 20/02/2019 215475 215475 215475 100 Yes 2019 Corporation Ltd. under Bohar-II G.P within 23 B Memari-II P.S. Nine Mtr Mini high Must tower West Bengal Agro lighting system with 6 nos 80 watt 2018 - Industries 63 Led light fitting with each 561/DP 20/02/2019 215475 215475 215475 100 Yes 2019 Corporation Ltd. complete with all accessories 23 B under Mulgram G.P. 71 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Asset Handover Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status Nine Mtr Mini high Must tower West Bengal Agro lighting system with 6 nos. 80 watt 2018 - Industries 64 Led light fitting with each 561/DP 20/02/2019 215475 215475 215475 100 Yes 2019 Corporation Ltd. complete with all accessories 23 B under Jamna G.P. Nine Mtr Mini highn Must tower West Bengal Agro lighting system 6 nos 80 watt Led 2018 - Industries 65 light fitting with each complete 561/DP 20/02/2019 215475 215475 215475 100 Yes 2019 Corporation Ltd. with all accessories under 23 B Kusumgram G.P. 7.5 Mtr Tubler Pole with 4 nos. West Bengal Agro 100 watt Led light fitting with each 2018 - Industries Asset Handover 66 561/DP 20/02/2019 100000 100000 100000 100 Yes complete with all accessories 2019 Corporation Ltd. Report Wanting as Under Monteswar G.P. 23 B per the Clause No. 8 under updated West Bengal Agro 12 watt Led Solar Street Light with BEUP Guidelines 2018 - Industries 67 5 meter Goaldingi near Durgatala 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 2019 Corporation Ltd. under Satgachia-I G.P 23 B Nine Mtr. Mini high Must tower West Bengal Agro lighting system 6 nos 80 watt Led 2018 - Industries 68 light fitting with each complete 561/DP 20/02/2019 215475 215475 215475 100 Yes 2019 Corporation Ltd. with all accessories under Piplon 23 B G.P. West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 69 5 meter Ashapur Bangal Para 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. Under Bijur-II G.P. 23 B 72 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Asset Handover Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 70 5 meter at Begunia Aimapara 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. Under Bijur-II G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 71 5 meter Benigram near Kalitala 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. under Bijur-II G.P 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Asset Handover 72 5 meter Benigram Paschimpara 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. Report Wanting as under Bijur-II G.P 23 B per the Clause No. 8 under updated West Bengal Agro 12 watt Led Solar Street Light with BEUP Guidelines 2018 - Industries 73 5 meter Beside Gargeswar Under 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 2019 Corporation Ltd. Bijur-II G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 74 5 meter Bharkhanda beside 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. Tematha under Satgachia-I G.P 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 75 5 meter Bilbari near Barowaritala 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. under Bijur-II G.P 23 B 73 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Asset Handover Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 76 5 meter Biskopa near Bankarpul 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. Under Bijur-II G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 77 5 meter Shridharpur near 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. Durgatala Under Satgachia-I G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Asset Handover 78 5 meter Dhunui Pulpara Under 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. Report Wanting as Bijur-II G.P. 23 B per the Clause No. 8 under updated West Bengal Agro 12 watt Led Solar Street Light with BEUP Guidelines 2018 - Industries 79 5 meter Shantidanga near 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 2019 Corporation Ltd. Durgatala under Satgachia-I G.P 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 80 5 meter Kalapukur near Durgatala 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. under Satgachia-I G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 81 5 meter Kathalia near Durgatala 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. under Satgachia-I G.P. 23 B 74 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Asset Handover Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 82 5 meter Nanna Dighirpara under 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. Bijur-II G.P 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 83 5 meter Near Jotram Primary 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. School Under Bijur-II G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries Asset Handover 84 5 meter Near Sarra Masjidtala 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. Report Wanting as Under Satgachia-I G.P. 23 B per the Clause No. 8 under updated West Bengal Agro 12 watt Led Solar Street Light with BEUP Guidelines 2018 - Industries 85 5 meter Near Shridharpur High 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 2019 Corporation Ltd. School Under Satgachia-I G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 86 5 meter Satgachia Bazarpara 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. Under Satgachia-I G.P. 23 B

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 87 5 meter Satgachia Ghatakpara 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. under Satgachia-I G.P 23 B 75 Sl. Sanction Date of Amount Executing Amount Amount Physical UC Asset Handover Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

West Bengal Agro 12 watt Led Solar Street Light with 2018 - Industries 88 5 meter Near Biskopa Monosatala 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 Corporation Ltd. Asset Handover Under Bijur-II G.P. 23 B Report Wanting as per the Clause No. 8 under updated West Bengal Agro 12 watt Led Solar Street Light with BEUP Guidelines 2018 - Industries 89 5 meter Dhunui near Haritala 563/DP 20/02/2019 21420 21420 21420 100 Yes 2019 2019 Corporation Ltd. under Bijur-II G.P 23 B

Total 5066295 5066204 5066204

Grand Total 13566295 12829022 12829022

76 ONGOING SCHEMES

77 SAIKAT PANJA, HON'BLE MLA 263 MONTESWAR A.C.

Present Sanction UC Present Status Sl. Date of Amount Executing Amount Amount Physical Status for Name of the Scheme Year Order Submitt for the Month of No. Sanction Sanction Agency Released Utilized Progress the Month of No ed July June 75% work completed West Bengal 100% work Nine mtr. mini High Mast tower and delay due to 2016 - Agro Industries completed,1st. lighting 6 nos. 120 watt at 2016/DP 10/09/2018 399898 399898 299924 75 Yes lockdown and non 1 Phase UC 2017 Corporation Ltd. availability of Monteswar Kamar Shal More received 23 B transportation 75% work completed West Bengal 100% work Nine mtr. mini High Mast tower and delay due to 2016 - Agro Industries completed,1st. 2 lighting 6 nos. 120 watt at 3884/DP 21/10/2019 199949 199949 149962 75 Yes lockdown and non Phase UC 2017 Corporation Ltd. availability of Monteswar Denur G.P. received 23 B transportation Total 399898 399898 299924

7.5 mtr. High Mast Tower lighting West Bengal 75% work completed system with 4 nos. 80 watt of 7 2017 - Agro Industries and delay due to 3 places under Bijur-II / 2612/DP 02/06/2021 700000 525000 0 0 No Nil lockdown and non Barapalashan-I / 2018 Corporation Ltd. availability of Barapalaapalalashan-II/Jamna G.P. 23 B transportation Total 700000 525000 0

12 watt Led Solar Street Light West Bengal 100% work 100% work with 5 meter Katabari near 2018 - Agro Industries completed,1st. completed. UC will 4 563/DP 20/02/2019 21420 21420 16065 75 Yes Kalitala under Barapalashon-II 2019 Corporation Ltd. Phase U/C be given after 2nd G.P. 23 B received August 12 watt Led Solar Street Light West Bengal 100% work 100% work with 5 meter Barapalashon 2018 - Agro Industries completed,1st. completed. UC will 5 563/DP 20/02/2019 21420 21420 16065 75 Yes Hazrapukur near Kalitala Under 2019 Corporation Ltd. Phase U/C be given after 2nd received Barapalashon-II G.P. 23 B August78 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ted of June of July 12 watt Led Solar Street Light West Bengal 100% work 100% work with 5 meter Barapalashon 2018 - Agro Industries completed,1st. completed. UC 6 563/DP 20/02/2019 21420 21420 16065 75 Yes beside Sankor Matha Under 2019 Corporation Ltd. Phase U/C will be given Barapalashon-II G.P. 23 B received after 2nd August 12 watt Led Solar Street Light West Bengal 100% work 100% work with 5 meter Mirzapur beside 2018 - Agro Industries completed,1st. completed. UC 7 563/DP 20/02/2019 21420 21420 16065 75 Yes Gorer More Under 2019 Corporation Ltd. Phase U/C will be given Barapalashon-II G.P. 23 B received after 2nd August 100% work 12 watt Led Solar Street Light West Bengal 100% work 2018 - Agro Industries completed,1st. completed. UC 8 with 5 meter Kuroram Palli 563/DP 20/02/2019 21420 21420 16065 75 Yes 2019 Corporation Ltd. Phase U/C will be given under Barapalashon-II G.P. 23 B received after 2nd August 12 watt Led Solar Street Light West Bengal 100% work 100% work with 5 meter Near Dihipalashon 2018 – Agro Industries completed,1st. completed. UC 9 563/DP 20/02/2019 21420 21420 16065 75 Yes Shivtala under Barapalashon-II 2019 Corporation Ltd. Phase U/C will be given G.P. 23 B received after 2nd August 100% work 12 watt Led Solar Street Light West Bengal 100% work 2018 - Agro Industries completed,1st. completed. UC 10 with 5 meter Koruri near Kalitala 563/DP 20/02/2019 21420 21420 16065 75 Yes 2019 Corporation Ltd. Phase U/C will be given Under Barapalashon-II G.P. 23 B received after 2nd August Twelve watt Led Solar Street West Bengal 100% work 100% work Light with five meter near 2018 - Agro Industries completed,1st. completed. UC 11 563/DP 20/02/2019 21420 21420 16065 75 Yes Bhadul Shivtala under Bijur-I 2019 Corporation Ltd. Phase U/C will be given G.P. within Memari-II P.S. 23 B received after 2nd August 100% work 12 watt Led Solar Street Light West Bengal 100% work 2018 - Agro Industries completed,1st. completed. UC 12 with 5 meter Near Melna 563/DP 20/02/2019 21420 21420 16065 75 Yes 2019 Corporation Ltd. Phase U/C will be given Bijur-I G.P. 23 B received after 2nd August 79 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month of No. Sanction Sanction Agency Released Utilized Progress No ted of June July 12 watt Led Solar Street Light West Bengal 100% work 100% work with 5 meter Near 2018 - Agro Industries completed,1st. completed. UC will 13 563/DP 20/02/2019 21420 21420 16065 75 Yes Kandarpapur Haritala Under 2019 Corporation Ltd. Phase U/C be given after 2nd Bijur-I G.P. 23 B received August 12 watt Led Solar Street Light West Bengal 100% work 100% work with 5 meter Near 2018 - Agro Industries completed,1st. completed. UC will 14 563/DP 20/02/2019 21420 21420 16065 75 Yes Munsidanga Primary School 2019 Corporation Ltd. Phase U/C be given after 2nd Under Bijur-II G.P. 23 B received August 12 watt Led Solar Street Light West Bengal 100% work 100% work with 5 meter Near Udaynala 2018 - Agro Industries completed,1st. completed. UC will 15 563/DP 20/02/2019 21420 21420 16065 75 Yes Club under Barapalashon-II 2019 Corporation Ltd. Phase U/C be given after 2nd G.P. 23 B received August 12 watt Led Solar Street Light West Bengal 100% work 100% work 2018 - Agro Industries completed,1st. completed. UC will 16 with 5 meter Melna More 563/DP 20/02/2019 21420 21420 16065 75 Yes 2019 Corporation Ltd. Phase U/C be given after 2nd Under Bijur-I G.P. 23 B received August 12 watt Led Solar Street Light West Bengal 100% work 100% work with 5 meter Barapalashan 2018 - Agro Industries completed,1st. completed. UC will 17 563/DP 20/02/2019 21420 21420 16065 75 Yes Janapara near Kalitala under 2019 Corporation Ltd. Phase U/C be given after 2nd Barapalashon-II G.P. 23 B received August 12 watt Led Solar Street Light West Bengal 100% work 100% work with 5 meter Barowari beside 2018 - Agro Industries completed,1st. completed. UC will 18 563/DP 20/02/2019 21420 21420 16065 75 Yes Gachtala under Barapalashon- 2019 Corporation Ltd. Phase U/C be given after 2nd II G.P. 23 B received August 12 watt Led Solar Street Light West Bengal 100% work 100% work with 5 meter Near Gorapur 2018 - Agro Industries completed,1st. completed. UC will 19 563/DP 20/02/2019 21420 21420 16065 75 Yes Club under Barapalashon-II 2019 Corporation Ltd. Phase U/C be given after 2nd G.P. 23 B received August Total 342720 342720 257040 80 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ted of June of July 100% work Installation of 12 watt led solar West Bengal 100% work completed. UC light Near Babunpur 2019- Agro Industries completed,1st. 20 2428/DP 23/09/2020 96921 72691 72691 75 Yes will be given Rakkhakaliala under Baghashon 2020 Corporation Phase U/C after 2nd G.P. within Monteswar P.S. Ltd. 23 B received August 100% work Installation of 12 watt led solar West Bengal 100% work completed. UC light Near Piplon Dangapara 2019- Agro Industries completed,1st. 21 2426/DP 23/09/2020 96921 96921 72691 75 Yes will be given under Piplon G.P.within 2020 Corporation Phase U/C after 2nd Monteswar P.S. Ltd. 23 B received August

100% work Installation of 12 watt led solar West Bengal 100% work completed. UC street light Near Patikeldanga 2019- Agro Industries completed,1st. 22 2430/DP 23/09/2020 96921 96921 72691 75 Yes will be given Masjidtala under Monteswar 2020 Corporation Phase U/C after 2nd G.P. within Monteswar P.S. Ltd. 23 B received August 100% work Installation of 12 watt led solar West Bengal 100% work completed. UC street light at Bhagra Bhomra 2019- Agro Industries completed,1st. 23 2429/DP 23/09/2020 96921 96921 72691 75 Yes will be given par u 1nder Bhagra-Mulgram 2020 Corporation Phase U/C after 2nd G.P. within Monteswar P.S. Ltd. 23 B received August

100% work Installation of 12 watt led solar West Bengal 100% work completed. UC street light Uttarpara Kalitala 2019- Agro Industries completed,1st. 24 2427/DP 23/09/2020 96921 96921 72691 75 Yes will be given under Monteswar G.P. within 2020 Corporation Phase U/C after 2nd Monteswar P.S. Ltd. 23 B received August 81 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ted of June of July 100% work Installation of 12 watt led solar West Bengal 100% work completed. UC street light Near Untia Malpara 2019- Agro Industries completed,1st. 25 2418/DP 23/09/2020 96921 96921 72691 75 Yes will be given Thakurtala under Barapalashon-I 2020 Corporation Phase U/C after 2nd G.P. within Memari-II P.S. Ltd. 23 B received August Installation of 12 watt led sollar 100% work West Bengal 100% work street light with 5 mtr. tuble pole completed. UC 2019- Agro Industries completed,1st. 26 40 amps battery 60 watt Jamna 2421/DP 23/09/2020 72690 72690 54518 75 Yes will be given 2020 Corporation Phase U/C Bazar under Jamna G.P. within after 2nd Ltd. 23 B received Monteswar P.S. August

100% work West Bengal 100% work Street Light at Shyambazar under completed. UC 2019- Agro Industries completed,1st. 27 Jamna G.P. within Monteswar 2421/DP 23/09/2020 100000 100000 75000 75 Yes will be given 2020 Corporation Phase U/C P.S. after 2nd Ltd. 23 B received August Installation of 9 Mtr. mini high 100% work West Bengal 100% work mast tower lighting system with 6 completed. UC 2019- Agro Industries completed,1st. 28 nos. 80 watt led light under 2420/DP 23/09/2020 150000 150000 112500 75 Yes will be given 2020 Corporation Phase U/C Barapalashon-I G.P. within after 2nd Ltd. 23 B received Memari-II P.S. August

Installation of 9 Mtr. mini high 100% work West Bengal 100% work mast tower lighting system with 6 completed. UC 2019- Agro Industries completed,1st. 29 nos. 80 watt led light under 2419/DP 23/09/2020 200000 199951 149964 75 Yes will be given 2020 Corporation Phase U/C Barapalashon-II G.P. within after 2nd Ltd. 23 B received Memari-II P.S. August

82 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ted of June of July 100% work Installation of 12 watt led solar West Bengal 100% work completed. UC street light Near Goyepur 2019- Agro Industries completed,1st. 30 2417/DP 23/09/2020 96921 96921 72691 75 Yes will be given Masjidtala under Barapalashan-I 2020 Corporation Phase U/C after 2nd G.P. within Memari-II P.S. Ltd. 23 B received August 100% work Installation of 12 watt led solar West Bengal 100% work completed. UC light Near Kuljora FP School 2019- Agro Industries completed,1st. 31 2425/DP 23/09/2020 96921 96921 72691 75 Yes will be given under Piplon G.P.within 2020 Corporation Phase U/C after 2nd Monteswar P.S. Ltd. 23 B received August 100% work Installation of 12 watt led solar West Bengal 100% work completed. UC light At Kalui Phuldhobar par 2019- Agro Industries completed,1st. 32 2423/DP 23/09/2020 72690 72690 54518 75 Yes will be given under Susunia G.P.within 2020 Corporation Phase U/C after 2nd Monteswar P. Ltd. 23 B received August 100% work West Bengal 100% work Installation of 12 watt led solar completed. UC 2019- Agro Industries completed,1st. 33 light Near Borojugram under 2424/DP 23/09/2020 72690 72690 54518 75 Yes will be given 2020 Corporation Phase U/C Piplon G.P.within Monteswar P.S. after 2nd Ltd. 23 B received August 100% work West Bengal 100% work Installation of 12 watt led solar completed. UC 2019- Agro Industries completed,1st. 34 light Asuri More under Jamna 2422/DP 23/09/2020 96921 96921 72691 75 Yes will be given 2020 Corporation Phase U/C G.P.within Monteswar P.S. after 2nd Ltd. 23 B received August 83 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ted of June of July

Installation of 9 Mtr with 6 nos. West Bengal 100% work 100% work 80 watt led Light at Mirpur under 2019- Agro Industries completed,1st. completed. UC 35 2416/DP 23/09/2020 200000 199951 149964 75 Yes Majhergram G.P. within 2020 Corporation Phase U/C will be given after Monteswar P.S. Ltd. 23 B received 2nd August

Installation of 12 watt led solar West Bengal 100% work 100% work street light Susunia School more 2019- Agro Industries completed,1st. completed. UC 36 2493/DP 25/09/2020 96921 96921 72691 75 Yes under Susunia G.P. within 2020 Corporation Phase U/C will be given after Monteswar P.S. Ltd. 23 B received 2nd August

Installation of 12 watt led solar West Bengal 100% work 100% work street light Near Sankratala under 2019- Agro Industries completed,1st. completed. UC 37 2493/DP 25/09/2020 96921 96921 72691 75 Yes Mamudpur-I G.P. within 2020 Corporation Phase U/C will be given after Monteswar P.S. Ltd. 23 B received 2nd August

Installation of 12 watt led solar West Bengal 100% work 100% work street light Near Tullya under 2019- Agro Industries completed,1st. completed. UC 38 2493/DP 25/09/2020 96921 96921 72691 75 Yes Susunia G.P. within Monteswar 2020 Corporation Phase U/C will be given after P.S. Ltd. 23 B received 2nd August

Installation of 12 watt led solar West Bengal 100% work 100% work street light Near Health Cenrte 2019- Agro Industries completed,1st. completed. UC 39 2493/DP 25/09/2020 96921 96921 72691 75 Yes under Mamudpur-I within 2020 Corporation Phase U/C will be given after Monteswar P.S. Ltd. 23 B received 2nd August

Installation of 12 watt led solar West Bengal 100% work 100% work street light Near Swetpur 2019- Agro Industries completed,1st. completed. UC 40 2493/DP 25/09/2020 96921 96921 72691 75 Yes Durgamandir under Susunia G.P. 2020 Corporation Phase U/C will be given after within Monteswar P.S. Ltd. 23 B received 2nd August 84 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month of No. Sanction Sanction Agency Released Utilized Progress No ted of June July

Installation of 12 watt led solar West Bengal 100% work 100% work street light Near Habibul House 2019- Agro Industries completed. UC will 41 2431/DP 30/09/2020 96921 96921 72691 75 Yes completed,1st. be given after 2nd under Bhagra-Mulgram G.P. 2020 Corporation Phase UC received within Monteswar P.S. Ltd. 23 B August Constn. of cc road from West Bengal Work not started, Mondalgram Borodaspara within 2019- Agro Industries Work started due to shortage of 42 612/DP 10/02/2021 249970 187478 0 0 No Barapalashan G.P. under Memari- 2020 Corporation shortly man power & covid II P.S Ltd. 23 B situation Constn. of cc road from Main road West Bengal Work not started, towards Harindanga Adibasipara 2019- Agro Industries Work started due to shortage of 43 612/DP 10/02/2021 279357 209518 0 0 No within Bohar-II G.P. under 2020 Corporation shortly man power & covid Memari-II P.S Ltd. 23 B situation West Bengal Constn. of cc road from Kochi 75% work 2019- Agro Industries Work started completed. 1st phase 44 Saha house within Bohar-II G.P. 612/DP 10/02/2021 299994 224995 0 0 No 2020 Corporation shortly UC will be given under Memari-II P.S Ltd. 23 B after 2nd August West Bengal Constn. of cc road from Gonesh Work not started, 2019- Agro Industries Work started due to shortage of 45 Hazra house within Bijur-II G.P. 612/DP 10/02/2021 270000 202500 0 0 No 2020 Corporation shortly man power & covid under Memari-II P.S Ltd. 23 B situation West Bengal Constn. of cc road from Ganga Work not started, 2019- Agro Industries Work started due to shortage of 46 house within Bijur-I G.P. under 612/DP 10/02/2021 35000 26250 0 0 No 2020 Corporation shortly man power & covid Memari-II P.S Ltd. 23 B situation Constn.. of cc road from West Bengal Work not started, 2019- Agro Industries Work started due to shortage of 47 Chittarranjan Naiya house within 612/DP 10/02/2021 184680 138510 0 0 No 2020 Corporation Ltd. shortly man power & covid Bijur-II G.P. under Memari-II P.S 23 B situation 85 Present Sanction UC Present Status Sl. Date of Amount Executing Amount Amount Physical Status for Name of the Scheme Year Order Submit for the Month of No. Sanction Sanction Agency Released Utilized Progress the Month of No ted July June Constn.. of cc road from Satgachia West Bengal 100% work 2019- Agro Industries Work started completed. 1st phase 48 Sastitala within Satgachia-I G.P. 612/DP 10/02/2021 280000 210000 0 0 No 2020 Corporation Ltd. shortly UC will be given under Memari-II P.S 23 B after 2nd August Constn.. of cc road from Astham West Bengal Work not started, due 2019- Agro Industries Work started to shortage of man 49 Ghosh house within Bijur-I G.P. 612/DP 10/02/2021 50000 37500 0 0 No 2020 Corporation Ltd. shortly power & covid under Memari-II P.S 23 B situation Installation of 12 Watt Led Solar West Bengal 100% work 2019- Agro Industries 25% work completed. 1st phase 50 Street Light with 5 Mrtutble Pole 599/DP 10/02/2021 242300 181725 0 0 No 2020 Corporation Ltd. completed UC will be given 40 AMPS Battery 23 B after 2nd August West Bengal 75% work Street Light at Dharapukur under 2019- Agro Industries 25% work completed. 1st phase 51 598/DP 10/02/2021 50000 37500 0 0 No Denur GP 2020 Corporation Ltd. completed UC will be given 23 B after 2nd August Constn.. of cc road from West Bengal Work not started, due Chandrakanta Ghosh House 2019- Agro Industries Work started to shortage of man 52 612/DP 10/02/2021 39995 29996 0 0 No within Bijur-I G.P. under Memari- 2020 Corporation Ltd. shortly power & covid II P.S 23 B situation Installation of 12 watt led solar West Bengal 100% work 100% work street light Uttarpara Kalitala 2019- Agro Industries completed, 1st. completed. UC will 53 2432/DP 30/09/2021 96921 96921 72691 75 Yes under Monteswar G.P. within 2020 Corporation Ltd. Phase U/C be given after 2nd Monteswar P.S. 23 B received August Nine mtr. High Mast tower West Bengal 75% work 2019- Agro Industries completed. 1st phase 54 lighting system 3 no. place under 2613/DP 02/06/2021 450000 337500 0 0 No Nil 2020 Corporation Ltd. UC will be given Kusumgram G.P. 23 B after 2nd August Total 4850102 4242180 1814038 86 Sanction UC Present Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit Status for the for the Month No. Sanction Sanction Agency Released Utilized Progress No ted Month of June of July 75% work West Bengal 9 Mtr. High Mast Tower Lighting completed. 1st 2020- Agro Industries 55 system with 4 nos. 80 watt flood 2615/DP 02/06/2021 900000 675000 0 0 No Nil phase UC will 2021 Corporation Ltd. light at 5 placess be given after 23 B 2nd August 75% work West Bengal 9 Mtr. High Mast Tower Lighting completed. 1st 2020- Agro Industries 56 system with 6 nos. 80 watt flood 2615/DP 02/06/2021 646425 484819 0 0 No Nil phase UC will 2021 Corporation Ltd. light at 3 placess be given after 23 B 2nd August 75% work West Bengal 7.5 Mtr. High Mast Tower completed. 1st 2020- Agro Industries 57 Lighting system with 4 nos. 80 2615/DP 02/06/2021 1400000 1050000 0 0 No Nil phase UC will 2021 Corporation Ltd. watt flood light at 14 placess be given after 23 B 2nd August Total 2946425 2209819 0 Grand Total 9239145 7719617 2371002

87 Hon’ble M.L.A. Shri Biswajit Kundu M.L.A of 264-Kalna (SC) AC

88 COMPLETED SCHEMES

89 BISWAJIT KUNDU, HON'BLE MLA-264 KALNA(SC) A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ed Asset Handover Report Constn. of Shed at Kusodanga 2016 - E.O., Kalna- Received as per the Clause 1 2515/DP 28/10/2016 150000 150000 150000 100 Yes Champatala of Kalyanpur G.P. 2017 II P.S. No. 8 under updated BEUP Guidelines 2019 Asset Handover Report Rep of School Building for 2016 - E.O., Kalna- Wanting as per the Clause 2 Sadhupukur Jr. High School at 2515/DP 28/10/2016 498000 498000 498000 100 Yes 2017 II P.S. No. 8 under updated BEUP Anukhal G.P. Guidelines 2019

Constn. of New Pukur Ghat at 2016 - E.O., Kalna- 3 Hanspukur Jangri Pukur of 2515/DP 28/10/2016 100000 100000 100000 100 Yes 2017 II P.S. Satgachia G.P.

Constn. of New Pukur Ghat at 2016 - E.O., Kalna- 4 Nasipur Purba Satgachia of 2515/DP 28/10/2016 100000 100000 100000 100 Yes 2017 II P.S. Asset Handover Report Satgachia G.P. Received as per the Clause No. 8 under updated BEUP Constn. of New Pukur Ghat at Guidelines 2019 2016 - E.O., Kalna- 5 Sahapur Muso Pukur of 2515/DP 28/10/2016 100000 100000 100000 100 Yes 2017 II P.S. Satgachia G.P.

Constn. of Pay and used Toilet 2016 - E.O., Kalna- 6 2515/DP 28/10/2016 400000 400000 400000 100 Yes at Rathtala of G.P. 2017 II P.S.

90 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Year Submitt Asset Handover Status No. Name of the Scheme Order No Sanction Sanction Agency Released Utilized Progress ed

Constn. of waiting Shed at Asset Handover Report Khagrakur Sesapota 2016 - E.O., Kalna- II Received as per the Clause 7 2515/dp 28/10/2016 150000 150000 150000 100 Yes Baroyaritala of Kalyanpur 2017 P.S. No. 8 under updated BEUP G.P. Guidelines 2019

Constn. of Pukur Ghat of 2016 - E.O., Kalna- II 8 Khadipara San Bandha Pond 2655/DP 15/11/2016 120000 120000 120000 100 Yes 2017 P.S. at Akalpoush G.P.

Constn. of Waiting Room 2016 - E.O., Kalna- II 9 2655/DP 15/11/2016 150000 150000 150000 100 Yes infront of Baradhamas G.P. 2017 P.S. Asset Handover Report Wanting as per the Clause No. 8 under updated BEUP Repar. of School Building for 2016 - E.O., Kalna- II Guidelines 2019 10 Balindar MSK at Baradhemas 2655/DP 15/11/2016 100000 100000 100000 100 Yes 2017 P.S. G.P.

Constn. of Pukur Ghat at 2016 - E.O., Kalna- II 11 2655/DP 15/11/2016 130000 130000 130000 100 Yes Narengha of AkalpoushG.P. 2017 P.S.

Asset Handover Report Constn. of New Waiting room 2016 - E.O., Kalna- II Received as per the Clause 12 and Burning Ghat at Boro 2655/DP 15/11/2016 200000 200000 200000 100 Yes 2017 P.S. No. 8 under updated BEUP Bohakuli of Badla G.P. Guidelines 2019 91 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Asset Handover Constn. of Pukur Ghat of Report Wanting as per 2016 - E.O., Kalna- II 13 Kulepara Bedra Pond at 2655/DP 15/11/2016 150000 150000 150000 100 Yes the Clause No. 8 under 2017 P.S. Akalpoush G.P. updated BEUP Guidelines 2019 Asset Handover Constn. of Burning Shade and Report Received as per 2016 - E.O., Kalna- II 14 Stage at Noara Goara of Badla 2655/DP 15/11/2016 100000 100000 100000 100 Yes the Clause No. 8 under 2017 P.S. G.P. updated BEUP Guidelines 2019 Asset Handover Constn. of Concrete drain for Report Wanting as per 2016 - E.O., Kalna- II 15 Biruha Kshetrapalpara of 2655/DP 15/11/2016 150000 150000 150000 100 Yes the Clause No. 8 under 2017 P.S. Baradhemos G.P. updated BEUP Guidelines 2019

Constn. of ACR at Angerson 2016 - E.O., Kalna- II 16 2959/DP 19/12/2016 400000 400000 400000 100 Yes M.M. High School at Pindira G.P. 2017 P.S. Asset Handover Constn. of Road and Drain from Report Received as per 2016 - E.O., Kalna- I 17 Company Danga to ICDS Centre 664/DP 02/03/2017 250000 250000 250000 100 Yes the Clause No. 8 under 2017 P.S. of Hatkalna updated BEUP Guidelines 2019 Constn. of Concrete road at 2016 - E.O., Kalna- I 18 664/DP 02/03/2017 250000 250000 250000 100 Yes Mirarpur to Hatkalna G.P. 2017 P.S.

92 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Constn. of Concrete Road 2016 - E.O., Kalna- I 19 Dharmadanga F.P. School to 664/DP 02/03/2017 250000 250000 250000 100 Yes 2017 P.S. Mirpur of Hatkalna

Constn. of Concrete Road from 2016 - E.O., Kalna- I 20 Peari Nagar Health Centre to 664/DP 02/03/2017 300000 300000 300000 100 Yes Asset Handover Report 2017 P.S. Biswajit Dharas House Received as per the Clause No. 8 under Constn. of New Cycle Shed at 2016 - E.O., Kalna- I updated BEUP 21 664/DP 02/03/2017 200000 200000 200000 100 Yes Krishnadevpur High School 2017 P.S. Guidelines 2019

Constn. of Concrete Road from 2016 - E.O., Kalna- I 22 Sikarpur Daksnhin Para Masjid 664/DP 02/03/2017 150000 150000 150000 100 Yes 2017 P.S. to ICDS Centre Asset Handover Report District Wanting as per the Constn. of New gate at 2016 - 23 1126/DP 10/04/2017 200000 Magistrate, 200000 200000 100 Yes Clause No. 8 under Mahishardini High School 2017 Burdwan updated BEUP Guidelines 2019 Asset Handover Report Constn. of Guardwall of Pond Received as per the 2016 - E.O., Kalna- I 24 of Pathaigachia of Bagnapara 1126/DP 10/04/2017 250000 250000 250000 100 Yes Clause No. 8 under 2017 P.S. G.P. updated BEUP Guidelines 2019 93 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Constn. of New Waiting Shade 2016 - E.O., Kalna- I 25 1126/DP 10/04/2017 150000 150000 150000 100 Yes at Kaikhali of Bagnapara G.P. 2017 P.S.

Constn. of New Waiting Shade 2016 - E.O., Kalna- I 26 at Shyamganj Para of Hatkalna 1126/DP 10/04/2017 200000 200000 200000 100 Yes 2017 P.S. G.P.

Constn. of New Waiting Shed at 2016 - E.O., Kalna- I 27 1126/DP 10/04/2017 150000 150000 150000 100 Yes Alagarh of BagnaparaG.P. 2017 P.S. Asset Handover Report Received as per the Clause No. 8 under Up Gradation of Waiting Shed at District updated BEUP 2016 - 28 SDO Office CompoundKalna 1200/DP 17/04/2017 600000 Magistrate, 600000 600000 100 Yes Guidelines 2019 2017 1st phase Burdwan

Total 5948000 5948000 5948000

Exe. Engg. PWD Constn. of Baitoroni scheme at 2017 - 29 2357/DP 28/08/2017 890000 (Social Sector), 781869 781869 100 Yes Hasan Hati Village Plot No 272 2018 Burdwan.

Constn. of Baitoroni scheme at Exe. Engg. PWD 2017 - 30 Balindar Village Plot No 2357/DP 28/08/2017 890000 (Social Sector), 781868 781868 100 Yes 2018 75,76,77 Burdwan. 94 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ted Constn. of Baitoroni scheme Exe. Engg. PWD 2017 - 31 at Gopaldas Village Plot No 2357/DP 28/08/2017 890000 (Social Sector), 781869 781869 100 Yes 2018 455 Burdwan. Exe. Engg. PWD Constn. of Baitoroni scheme 2017 - 32 2357/DP 28/08/2017 890000 (Social Sector), 781868 781868 100 Yes at Deara Village Plot No 969 2018 Burdwan. New Constn. of Pond Ghat at 2017 - E.O., Kalna- II 33 3349/DP 22/12/2017 150000 150000 150000 100 Yes Tala of Baidyapur 2018 P.S. Inst of Submesible at 2017 - E.O., Kalna- II 34 Baradhamas Jl No 122 Plot C-466/DP 07/03/2018 250000 250000 250000 100 Yes Asset Handover Report 2018 P.S. No. 489 under Kalna-II Received as per the Inst of Submesible at Clause No. 8 under 2017 - E.O., Kalna- II 35 Baradhamas Jl No 122 Plot C-466/DP 07/03/2018 250000 250000 250000 100 Yes updated BEUP 2018 P.S. No. 2603 under Kalna-II Guidelines 2019 Instn of Drinking Water supply Project for the Public 2017 - E.O., Kalna- II 36 971/DP 22/05/2018 90000 90000 90000 100 Yes Use adjacent to Kalna BDO 2018 P.S. Office Installation of water supply Executive scheme for public under 2017 - 37 1370/DP 11/05/2020 248750 Officer, Kalna- 248750 248750 100 Yes Kalyanpur G.P. within Kalna- 2018 II P.S. II P.S. Total 4548750 4116224 4116224

95 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ted

Constn.. of cycle shed at Executive 2018 - 37 Satgachiya High School 1374/DP 11/05/2020 199700 Officer, Kalna- 199700 199700 100 Yes Asset Handover Report 2019 under Satgachia G.P. II P.S. Received as per the Clause No. 8 under H.M. & Constn. of New Cycle Sade at updated BEUP 2018 - Secretary, Kalna 38 Kalna Ambika M.M. High 2344/DP 15/09/2020 249300 249300 249300 100 Yes Guidelines 2019 2019 Ambika M.M. School High School Total 449000 449000 449000

Constn. of Atchala ear Executive 2019- 39 buddadeb Mondal House 601/DP 10/02/2021 134985 Officer, Kalna- 101238 101238 100 Yes 2020 village of Sabitpur II P.S. Asset Handover Report Executive Wanting as per the Constn. of Waiting Shed near 2019- 40 601/DP 10/02/2021 267450 Officer, Kalna- 200588 200588 100 Yes Clause No. 8 under Sitala Mandir vill Kamarpara 2020 II P.S. updated BEUP Guidelines 2019 Submersible Pump and Executive 2019- 41 supply for Drinking water at 601/DP 10/02/2021 294000 Officer, Kalna- 220500 220500 100 Yes 2020 village Buranpara II P.S.

Total 696435 522326 522326

Grand Total 11642185 11035550 11035550

96 ONGOING SCHEMES

97 BISWAJIT KUNDU, HON'BLE MLA 264 KALNA(SC) A.C.

Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt for the Month of for the Month No. Sanction Sanction Agency Released Utilized Progress No ed June of July Installation of sub-mercible pump for drinking water supply Executive Completed, Final 100% work at Nischantapur (Plot-1019, Jl.- 2018 - UC will be completed. UC 1 1499/DP 28/05/2020 199700 Officer, 199700 149775 75 Yes 60, Mouza-Nischintapur ) under 2019 submitted very will be submitted Kalna- I P.S. Bagnapara G.P. within Kalna-I shortly 05/08/2021 P.S. Constn.. of Concrete road near 100% work Suraha Nurshing Home from Executive 2018 - completed, Final 2 Bapi Pradhan House to main 1499/DP 28/05/2020 197900 Officer, 197900 148425 75 Yes UC will be Work not started 2019 road under Hat Kalna G.P. Kalna- I P.S. submitted very within Kalna-I P.S. shortly Constn.. of concrete road Executive Completed, Final 100% work opposite of Kalna SD Hospital 2018 - UC will be completed. UC 3 1499/DP 28/05/2020 296940 Officer, 296940 222705 75 Yes inside Jnanananda Math under 2019 submitted very will be submitted Kalna- I P.S. Hat Kalna G.P. within Kalna-I shortly 05/08/2021

100% work 100% work Constn. of Pukur Ghat at Executive completed, Final 2018 - completed. UC 4 Rathtala Khaspukur at 258/DP 25/01/2021 150000 Officer, 112500 112500 75 Yes UC will be will be submitted 2019 submitted after Bhanapara Rathtala Kalna- I P.S. 05/08/2021 receiving of fund.

H.M 100% work st 75% UC will be Constn. of New Class Room at 2018 - Angerson completed 1 5 358/DP 29/01/2021 300000 225000 0 0 No Phase UC will be submitted on Angersons MM High School 2019 MM High submitted by 09/08/2021. School 25/06/2021 98 Sanction UC Present Status Sl. Date of Amount Executing Amount Amount Physical Present Status for Name of the Scheme Year Order Submitt for the Month of No. Sanction Sanction Agency Released Utilized Progress the Month of July No ed June Executive 100% work Constn. of Waiting Shed at 2018 - 85% work 6 408/DP 02/02/2021 200000 Officer, 150000 150000 75 Yes completed. UC will be Bijara Young Star Club 2019 completed Kalna- I P.S. submitted 05/08/2021

Executive 100% work Constn. of waiting Shed near 2018 - 85% work 7 408/DP 02/02/2021 200000 Officer, 150000 150000 75 Yes completed. UC will be Alaghar Basantapur Shibmandir 2019 completed Kalna- I P.S. submitted 05/08/2021 100% work Executive 100% work Constn. of Pathway and lighting 2018 - completed, Final 8 605/DP 10/02/2021 455950 Officer, 341962 341962 75 Yes UC will be completed. UC at ECO Park 2019 Kalna- II P.S. submitted after already submitted. receiving of fund 100% work Constn. of Waiting Shed village Executive 100% work 2018 - completed, Final 9 Dakshin Durgapur under 605/DP 10/02/2021 149625 Officer, 112218 112218 75 Yes UC will be completed. Balance 2019 Pindira GP Kalna- II P.S. submitted after fund need to release. receiving of fund 100% work Executive 100% work Constn. of Waiting Shed village 2018 - completed, Final 10 605/DP 10/02/2021 199200 Officer, 149400 149400 75 Yes UC will be completed. UC Panchpara Patharghat 2019 Kalna- II P.S. submitted after already submitted. receiving of fund Executive 100% work Constn. of Shed near Talbona 2018 - 90% work 11 661/DP 12/02/2021 494500 Officer, 370875 370875 75 Yes completed. UC will be Durga Mandir 2019 completed Kalna- I P.S. submitted 05/08/2021 Constn. of Shed near Gaja Executive 100% work 2018 - 85% work 12 Laxmi Mandir within Kalna I 661/DP 12/02/2021 499000 Officer, 374250 374250 75 Yes completed. UC will be 2019 completed PS Kalna- I P.S. submitted 05/08/2021 99 Sanction UC Present Status for Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt the Month of for the Month No. Sanction Sanction Agency Released Utilized Progress No ed June of July Not started because the work order has Work just Executive already been issued Constn. of Waiting Shed village 2018 - started. 75% UC 13 821/DP 24/02/2021 183280 Officer, 137460 0 0 No but agency not Kanibamni under Pindira GP wil be submitted 2019 started the work in Kalna- II P.S. 18/08/2021 field level due to lockdown

Completed, Final Constn. of Waiting shed at Executive 100% work 2018 - UC will be completed. UC 14 Singerkone near Radha Kanta 821/DP 24/02/2021 194000 Officer, 194000 145500 75 Yes 2019 submitted after already Mandir under Badla GP Kalna- II P.S. receiving of fund. submitted.

Total 3720095 3175993 2277835

Completed, Final Executive 100% work Constn. of Boundary Wall at 2019- UC will be completed. UC 15 257/DP 25/01/2021 199800 Officer, 149850 149850 75 Yes Rameswarpur Primary School 2020 submitted after will be submitted Kalna- I P.S. receiving of fund. 05/08/2021

Constn. of Waiting Shed near Executive 100% work 2019- 85% work completed. UC 16 Sastitala Barowaritala vill 602/DP 10/02/2021 199800 Officer, 149850 149850 75 Yes 2020 completed will be submitted Krishnadevpur Kalna- I P.S. 05/08/2021

100 Sanction UC Present Status for Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt the Month of for the Month No. Sanction Sanction Agency Released Utilized Progress No ed June of July

Completed, Final Constn. of waiting Shed at Executive 100% work 2019- UC will be 17 Madrasha Jamin Islamia Ulam 601/DP 10/02/2021 199500 Officer, Kalna- 199500 149625 75 Yes completed. UC submitted after 2020 already submitted. village II P.S. receiving of fund.

Work completed 1st Executive 100% work Constn. of Waiting Shed at 2019- Phase UC will be 18 601/DP 10/02/2021 199500 Officer, Kalna- 199500 149625 75 Yes completed. UC submitted end of Madrasha Khajinatil Ullom 2020 already submitted. II P.S. June, 2021

Total 798600 698700 598950 H.M. & Constn. of Head Teacher Room Secretary, 75% UC will be 2020- Not started due to 19 at Kalna Ambika Mahismardini 822/DP 24/02/2021 389360 Kalna Ambika 292020 0 0 No submitted on 2021 lockdown High School M.M. High 09/08/2021. School Constn.. of Cycle Shed at Executive 100% work Kalna-I Block Office 2020- 85% work completed. UC 20 2551/DP 24/05/2021 249875 Officer, Kalna- 187406 187406 75 Yes Compound under Hat Kalna 2021 completed will be submitted I P.S. G.P. 05/08/2021 Total 639235 479426 187406 Grand Total 5157930 4354119 3064191

101 Hon’ble M.L.A. Nargis Begum MLA of 265 Memari AC

102 COMPLETED SCHEMES

103 NARGIS BEGUM, HON'BLE MLA 265 MEMARI A.C.

Sl. Sanction Date of Amount Executing Amount Amount Physical UC Handed Over Name of the Scheme Year No. Order No Sanction Sanction Agency Released Utilized Progress Submitted Status

Executive Constn.. of Mid Day Meal Shed at 2016 - 1 2048/DP 07/09/2016 262000 Officer, 262000 262000 100 Yes High School 2017 Memari- I P.S.

Constn. of Kitchen Cum Store for Executive 2016 - 2 Mid Day Meal at Borea A.W. 2048/DP 07/09/2016 235000 Officer, 235000 235000 100 Yes 2017 Centre of Amadpur Memari- I P.S.

Executive Constn. of Mid Day Meal Shed at 2016 - 3 2048/DP 07/09/2016 262000 Officer, 262000 262000 100 Yes Sashinara High School 2017 Memari- I P.S. Asset Handover Report Received as per the Clause No. 8 Constn. of Mid Day Meal at Executive 2016 - under updated BEUP 4 Ularah Primary School of 2048/DP 07/09/2016 262000 Officer, 262000 262000 100 Yes Guidelines 2019 2017 Daluibazar Memari- I P.S.

Constn. of Meal Day Meal Shed at Executive 2016 - 5 Alipur Parimary School of 2048/DP 07/09/2016 262000 Officer, 261610 261610 100 Yes 2017 Durgapur G.P. Memari- I P.S.

Constn. of Mid Day Meal Shed at Executive 2016 - 6 Gobindapur High School of 2048/DP 07/09/2016 262000 Officer, 262000 262000 100 Yes 2017 Debipur Memari- I P.S. 104 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Handed Over Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Constn. of Mid day Meal Shed 2016 - Executive Officer, 7 at Bholanath Bidyapith Gantey 2295/DP 28/09/2016 262000 262000 262000 100 Yes 2017 Memari- II P.S. of Kutuch G.P.

Constn. of Samsan at Keja of 2016 - Executive Officer, 8 327/DP 30/01/2017 200000 162009 162009 100 Yes Amadpur G.P. under Memari -I 2017 Memari- I P.S.

Constn. of Samsan at Nudipur 2016 - Executive Officer, 9 DVC bridge side Bagila G.P. 327/DP 30/01/2017 200000 200000 200000 100 Yes 2017 Memari- I P.S. Asset Handover Burning Shed Report Received as per the Clause No. 8 Constn. of Community Centre under updated BEUP 2016 - Executive Officer, 10 beside Bonerdanga Foot Ball 701/DP 07/03/2017 250000 250000 250000 100 Yes Guidelines 2019 2017 Memari- I P.S. Ground

Constn. of Waiting Shed at 4 2016 - Chairman, Memari 11 778/DP 14/03/2017 200000 200000 200000 100 Yes No Bus Stand Ward No. 5 2017 Muty.

Constn. of waiting Shed at 2016 - Chairman, Memari 12 Memari College more bus 778/DP 14/03/2017 300000 300000 300000 100 Yes 2017 Muty. Stopage under Memari Muty 105 UC Sl. Sanction Date of Amount Amount Amount Physical Handed Over Name of the Scheme Year Executing Agency Submitt No. Order No Sanction Sanction Released Utilized Progress Status ed

Asset Handover Report Received as Repair of Baggoria F.P School 2016 - Executive Officer, per the Clause No. 8 13 Building of Debipur G.P under C- 781/DP 14/03/2017 235000 235000 235000 100 Yes 2017 Memari- I P.S. under updated Memari- I P.S BEUP Guidelines 2019 Inst of Solar Light total five Nos. PEC LTD, Unit 22, from Krishnapur More to 2016 - 14 1157/DP 12/04/2017 125000 55, 125000 125000 100 Yes Sashinara School more of Bagila 2017 Rd., 71 G.P. Inst of Solar Light Total seven PEC LTD, Unit 22, G.P. from Mahesdanga Camp 2016 - 15 1157/DP 12/04/2017 175000 55, Chowringhee 175000 175000 100 Yes toMaheshdanga Camp Bazar of 2017 Rd.,Kolkata 71 Nimo G.P Asset Handover Report Wanting as Inst of Solar Light Total Seven PEC LTD, Unit 22, 2016 - per the Clause No. 8 16 from Maheshpur Masjid Tala to 1157/DP 12/04/2017 175000 55, Chowringhee 175000 175000 100 Yes 2017 under updated Sikshaniketan More of Daluibazar Rd.,Kolkata 71 BEUP Guidelines 2019 Inst of Solar Light Total Nine PEC LTD, Unit 22, 2016 - 17 G.P.Kalitala DVC to Matiswar 1157/DP 12/04/2017 275000 55, Chowringhee 275000 275000 100 Yes 2017 bazarunder Memari-I P.S. Rd.,Kolkata 71

Instn of six Nos of Solar light PEC LTD, Unit 22, from Radhakantapur Bazar to 2016 - 18 1157/DP 12/04/2017 175000 55, Chowringhee 175000 175000 100 Yes Katna Baroyari Sibtala of Gope 2017 Rd.,Kolkata 71 Gantar II G.P. 10 UC Sl. Sanction Date of Amount Amount Amount Physical Name of the Scheme Year Executing Agency Submitt Handed Over Status No. Order No Sanction Sanction Released Utilized Progress ed

Instn. of Solar Light Nine PEC LTD, Unit 22, G.P.from Chotkhanda Bazar 2016 - 19 1157/DP 12/04/2017 225000 55, Chowringhee 225000 225000 100 Yes Syrya Baroyari Tala under 2017 Rd.,Kolkata 71 Memari I P.S.

Instn. of Nine Nos Solar Light PEC LTD, Unit 22, 2016 - 20 from Mamudour to Netaji Sattue 1157/DP 12/04/2017 225000 55, Chowringhee 225000 225000 100 Yes 2017 of dalui bazarI G.P. Rd.,Kolkata 71

Inst. of Solar Light Total Eight PEC LTD, Unit 22, 2016 - 21 G.P. from Keja Manasatala to 1157/DP 12/04/2017 200000 55, Chowringhee 200000 200000 100 Yes 2017 Asset Handover Gopinathputpur Barwaritala Rd.,Kolkata 71 Report Wanting as per the Clause No. 8 under Instn. of Ten Nos of Solar Light PEC LTD, Unit 22, updated BEUP from Tarapur South Masjidtala 2016 - 22 1157/DP 12/04/2017 200000 55, Chowringhee 200000 200000 100 Yes Guidelines 2019 to Parijat Nagar Primary School 2017 Rd.,Kolkata 71 of Nimo I G.P. Instn. of Solar Light Ganter PEC LTD, Unit 22, Chandi talaGanter Football 2016 - 23 1157/DP 12/04/2017 100000 55, Chowringhee 100000 100000 100 Yes Busstand Ganter G.P. Office 2017 Rd.,Kolkata 71 Magra River canal River Bridge

Instn. of three Nos of Solar Light PEC LTD, Unit 22, 2016 - 24 at Sikshs Niketan More to Parijat 1266/DP 25/04/2017 75000 55, Chowringhee 75000 75000 100 Yes 2017 Nagar Primary School Rd.,Kolkata 71 107 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Handed Over Status No. Order No Sanction Sanction Agency Released Utilized Progress ed Re-conatn. of Baggoria F.P. 2016 - Executive Officer, 25 School of Debipur G.P 2nd 1425/DP 11/05/2017 150000 150000 150000 100 Yes 2017 Memari- I P.S. phase. Re-conatn. of Baggoria F.P. 2016 - Executive Officer, 26 School of Debipur G.P 3rd 1425/DP 11/05/2017 108000 108000 108000 100 Yes 2017 Memari- I P.S. phase Constn. of Patient Waiting 2016 - Executive Officer, 27 Shed at Memari Rural C-1742/DP 19/06/2017 350000 350000 350000 100 Yes 2017 Memari- I P.S. Hospital OPD Building Constn.. of Patient Waiting 2016 - Executive Officer, 28 Shed at Memari Rural C-1742/DP 19/06/2017 250000 250000 250000 100 Yes 2017 Memari- I P.S. Asset Handover Hospital Emergency Building Report Received as Total 6000000 5961619 5961619 per the Clause No. 8 Constn.. of Baitarani scheme under updated BEUP Exe. Engg. PWD at Memari- I and Kenna , 2017 - Guidelines 2019 29 2207/DP 04/08/2017 890000 (Social Sector), 849856 849856 100 Yes Mouza-Chamardighi (Plot. 2018 Burdwan. No. 3842 Jl 139)

Constn.. of Baitarani scheme Exe. Engg. PWD 2017 - 30 at Memari- I and Amadpur 2207/DP 04/08/2017 890000 (Social Sector), 849855 849855 100 Yes 2018 (Jl-128, Dag-467) Burdwan.

Constn.. of Baitarani scheme Exe. Engg. PWD at Memari- I and Shanui 2017 - 31 2207/DP 04/08/2017 890000 (Social Sector), 849856 849856 100 Yes Mouza, Shanui Binoypally, 2018 Burdwan. Jogomaya (Jl-133, plot 1407 108 Sanction UC Sl. Date of Amount Amount Amount Physical Name of the Scheme Year Order Executing Agency Submit Handed Over Status No. Sanction Sanction Released Utilized Progress No ted Asset Handover Report Building Repair and maitn. of 2017 - Executive Officer, Received as per the 32 Memari V.M. Institution for 3288/DP 13/12/2017 300000 300000 300000 100 Yes Clause No. 8 under 2018 Memari- I P.S. Quasquicenteunial Celebration updated BEUP Guidelines 2019 Asset Handover Report Inst of Solar Light Street LED National Small 2017 - Wanting as per the 33 Based Lumiaries SPV 43/DP 05/01/2018 660000 Industries 660000 660000 100 Yes Clause No. 8 under 2018 ModelNos of Thirty Corporation Ltd. updated BEUP Guidelines 2019 Constn. of wooden Guard Wall 2017 - Executive Officer, 34 Mobarakpur Girls Junior High 972/DP 22/05/2018 200000 200000 200000 100 Yes Asset Handover Report 2018 Memari- I P.S. School Received as per the Clause No. 8 under Constn. of Nimo Samsan Shed 2017 - Executive Officer, updated BEUP 35 at Nimo I G.P.under Memari I 972/DP 22/05/2018 200000 200000 200000 100 Yes 2018 Memari- I P.S. Guidelines 2019 G.P. Inst. of Solar Street Light 12 Kendriya Bhandar B-I 2017 - 36 Watt Led Based Lumiaries SPV 1401/DP 30/07/2018 1435140 Shyamali Housing 1435140 1435140 100 Yes 2018 Model under Mamari-I and II state, Kolkata Asset Handover Report Constn.. of changing room Wanting as per the 2017 - District Magistrate, 37 including sitting bench at 3918/DP 23/10/2019 150000 148125 148125 100 Yes Clause No. 8 under 2018 Burdwan Hatpukur Shan ghat updated BEUP Guidelines 2019 Constn.. of RCC shed over the stage 2017 - District Magistrate, 38 at Khanro Yubak Sangha under 4270/DP 27/11/2019 300000 298500 298500 100 Yes Memari Muty. 2018 Burdwan Total 5915140 5791332 5791332 109 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Handed Over Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Constn.. of concrete road of Data 2018 - Executive Officer, 39 Rouza at Nawhati of Kuchut 2317/DP 12/10/2018 350000 350000 350000 100 Yes 2019 Memari- II P.S. G.P. within Memari-II P.S. Asset Handover Constn.. of Patient shed Report Received as 2018 - Executive Officer, 40 Paharhati Hospital at Kuchut 2317/DP 12/10/2018 500000 500000 500000 100 Yes per the Clause No. 8 2019 Memari- II P.S. G.P. under Memari-II P.S. under updated BEUP Guidelines 2019 Constn.. of culvert at Borowa 2018 - Executive Officer, 41 near Bhagar Site at Satgachia-II 2317/DP 12/10/2018 250000 250000 250000 100 Yes 2019 Memari- II P.S. G.P. within Memari-II P.S.

Asset Handover Kendriya AC High Mast Tower Report Wanting as 2018 - BhandarB-I 42 Luminaries 90 watt Led Base Six 2460/DP 14/11/2018 200000 200000 200000 100 Yes per the Clause No. 8 2019 Shyamali Housing Arm Bracket and Octagonal pole under updated BEUP state,Kolkata Guidelines 2019 Constn.. of Cycle shed at Mohinimohan Basu School at 2018 - Executive Officer, 43 3297/DP 26/12/2018 300000 300000 300000 100 Yes Durgapur G.P. under memari-I 2019 Memari- I P.S. Asset Handover P.S. Report Received as per the Clause No. 8 Constn.. of Cycle shed at under updated BEUP 2018 - Executive Officer, 44 Radhakantapur School at Gantar- 3297/DP 26/12/2018 300000 299700 299700 100 Yes Guidelines 2019 2019 Memari- I P.S. II G.P. under Memari-I P.S.

110 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Handed Over Status No. Order No Sanction Sanction Agency Released Utilized Progress ted Asset Handover Constn.. of Auditoriam at Executive Report Received as 2018 - 45 Kanaidanga under Daluibazer -II 523/DP 18/02/2019 300000 Officer, Memari- 299880 299880 100 Yes per the Clause No. 8 2019 G.P. within Memari-I P.S. I P.S. under updated BEUP Guidelines 2019 Purchase of Dead Body Carrier Van 2018 - Prodhan, Bagila 46 under Bagila G.P. under Memari-I 2307/DP 29/08/2019 450000 450000 450000 100 Yes 2019 Gram Panchayat P.S. Supply Transportation and National Small 2018 - 47 Installation of AC High Mast Tower 406/DP 05/02/2020 200000 Industries 200000 200000 100 Yes 2019 at Memari P.S. under Memari Muty. Corporation Ltd. Supply Transportation and National Small Installation of AC High Mast Tower 2018 - 48 406/DP 05/02/2020 200000 Industries 200000 200000 100 Yes at Baneswarpur Samabai Samiti 2019 Corporation Ltd. Asset Handover Bazar under Satgachia-II G.P. Report Wanting as Supply Transportation and National Small per the Clause No. 8 Installation of AC High Mast Tower 2018 - 49 446/DP 05/02/2020 200000 Industries 200000 200000 100 Yes under updated BEUP at Gantar Busstand beside Najrul 2019 Corporation Ltd. Guidelines 2019 Smriti Sangha under Kuchut G.P. Supply Transporation and National Small Installation of AC High Mast Tower 2018 - 50 446/DP 05/02/2020 200000 Industries 200000 200000 100 Yes at Palla ACN high School stand 2019 Corporation Ltd. under Daluibazar-II G.P. Supply Transporation and National Small Installation of AC High Mast Tower 2018 - 51 446/DP 05/02/2020 200000 Industries 200000 200000 100 Yes at Belut primary School Busstand 2019 Corporation Ltd. under Daluibazar-I G.P. 111 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Supply Transporation and Installation National Small 2018 - 52 of AC High Mast Tower at Baror 446/DP 05/02/2020 200000 Industries 200000 200000 100 Yes 2019 Kalitala Busstand under Durgapur G.P. Corporation Ltd. Supply Transporation and Installation National Small of AC High Mast Tower at 2018 - 53 446/DP 05/02/2020 200000 Industries 200000 200000 100 Yes Mobarakpur DVC par under Debipur 2019 Corporation Ltd. G.P. Supply Transporation and Installation National Small of AC High Mast Tower at Gantar 2018 - 54 446/DP 05/02/2020 200000 Industries 200000 200000 100 Yes Kachari Road Busstand under Gope 2019 Corporation Ltd. Asset Handover Gantar-I G.P. Report Wanting Supply Transporation and Installation National Small as per the Clause 2018 - 55 of AC High Mast Tower at Kenna Bus 446/DP 05/02/2020 200000 Industries 200000 200000 100 Yes No. 8 under 2019 Stand under Nimo-II G.P. Corporation Ltd. updated BEUP Guidelines 2019 Supply Transporation and Installation National Small 2018 - 56 of AC High Mast Tower at Nishanka 446/DP 05/02/2020 200000 Industries 200000 200000 100 Yes 2019 Bazar under Amadpur G.P. Corporation Ltd. District Constn. of Gate in front of College 2018 - 57 2380/DP 18/09/2020 330000 Magistrate, 330000 327137 100 Yes Campus of Memari College 2019 Burdwan Constn. of Boundary wall at west side District 2018 - 58 of Bagila Purna Chandra Smriti Vidya 3364/DP 16/12/2020 464830 Magistrate, 464830 464830 100 Yes 2019 Mandir Burdwan

Total 5444830 5444410 5441547 112 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Handed Over Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed Asset Handover Report Wanting Constn. of proposed GYM room and District 2019- as per the Clause 53 ladies dressing room from lintel level 3365/DP 16/12/2020 347550 Magistrate, 347550 347525 100 Yes 2020 No. 8 under to onwards completion of ground floor Burdwan updated BEUP Guidelines 2019 Total 347550 347550 347525

Grand Total 17707520 17542411 17539523

113 ONGOING SCHEMES

114 NARGIS BEGUM, HON'BLE MLA 265 MEMARI A.C.

Sanction UC Present Status for Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt the Month of for the Month of No. Sanction Sanction Agency Released Utilized Progress No ed June July 100% Completed. Constn. of Gate of main Work completed 2018 - Prodhan Dalui UC will be entrance of Palla Road Girls 1371/DP 11/05/2020 150000 150000 112500 75 Yes Final UC submitted 1 submitted by 2019 Bazar-I G.P. shortly High School 02/08/2021 100% Completed. Constn. of Cycle Shed at Work completed 2018 - Prodhan Dalui UC will be Palla A.C.N. Smiriti 2230/DP 14/09/2020 150000 150000 112500 75 Yes Final UC submitted 2 submitted by 2019 Bazar-II G.P. shortly Bidyapith 02/08/2021 Purchase of Laboratory Not started due to HM, Gantar 75% UC will be Instrument under Geography 2018 - school authority not 3 803/DP 23/02/2021 250000 BM High 187500 0 0 No Submitted on and Nutration Deptt of 2019 started procurement School 06/08/2021 Gantar BM High School the items Total 550000 487500 225000 Constn.. of work for Executive 75% UC will be 2019- 30% work 4 Modification of Chamber of 3232/DP 08/12/2020 85010 Officer, 63757 0 0 No completed, work is submitted on 2020 BMOH Memari- I P.S. ongoing 02/08/2021 Scheme not Installation of Submersible Executive continued due local 2019- 63% work 5 for drinking water Boror Pir 3212/DP 08/12/2020 105015 Officer, 78761 0 0 No completed, work is problem and UC 2020 Darga Site at Durgapur G.P. Memari- I P.S. ongoing will be submitted after PS resolution 100% work 100% work Constn. of cultural Executive completed. Balance 2019- completed final UC 6 Auditorium at Ichabacha 3414/DP 21/12/2020 399600 Officer, 299700 299700 75 Yes will be submitted UC will be 2020 under Debipur G.P. Memari- I P.S. after receiving of submitted after fund. getting the fund 115 UC Present Status for Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt the Month of for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ed June July 100% work 100% work Street Light Luminary GM West Bengal completed final UC 2019- completed. 75% UC 7 AC Street Light at 809/DP 23/02/2021 153600 Agro Indries 115200 0 0 No will be submitted will be submitted 2020 after receiving of Durgapur GP 32 Nos. Corp LTD 04/08/2021 fund.

Street Light Luminary GM West Bengal 100% work 100% work 2019- completed 1st UC completed. 75% UC 8 AC Street Light at 809/DP 23/02/2021 124800 Agro Indries 93600 0 0 No 2020 will be submitted 1st will be submitted Bagila GP 26 Nos. Corp LTD week of July,2021 04/08/2021

Street Light Luminary GM West Bengal 100% work 100% work 2019- completed 1st UC completed. 75% UC 9 AC Street Light at 809/DP 23/02/2021 211200 Agro Indries 158400 0 0 No 2020 will be submitted 1st will be submitted Daluibazar GP 44 Nos Corp LTD week of July,2021 04/08/2021 Street Light Luminary GM West Bengal 100% work 100% work AC Street Light at 2019- completed 1st UC completed. 75% UC 10 809/DP 23/02/2021 480000 Agro Indries 360000 0 0 No Daluibazar II GP 100 2020 will be submitted 1st will be submitted Corp LTD nos week of July,2021 04/08/2021 100% work 100% work Street Light Luminary GM West Bengal completed Final UC 2019- completed. 75% UC 11 AC Street Light at 809/DP 23/02/2021 480000 Agro Indries 360000 0 0 No will be submitted will be submitted 2020 after receiving of Debipur GP 100 nos. Corp LTD 04/08/2021 fund. 100% work 100% work Street Light Luminary GM West Bengal completed Final UC 2019- completed. 75% UC 12 AC Street Light at 809/DP 23/02/2021 480000 Agro Indries 360000 0 0 No will be submitted will be submitted 2020 after receiving of Durgapur GP Corp LTD 04/08/2021 fund. 116 Sanction UC Present Status for Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt the Month of for the Month No. Sanction Sanction Agency Released Utilized Progress No ed June of July 100% work 100% work GM West Bengal completed 1st UC completed. 75% Street Light Luminary AC 2019- 13 809/DP 23/02/2021 297600 Agro Indries 223200 0 0 No will be submitted UC will be Street Light at Kutuch GP 2020 Corp LTD 1st week of submitted July,2021 04/08/2021 100% work 100% work Street Light Luminary AC GM West Bengal completed final completed. 75% 2019- 14 Street Light at Debipur GP 809/DP 23/02/2021 355200 Agro Indries 266400 0 0 No UC will be UC will be 2020 74 nos Corp LTD submitted submitted July,2021 04/08/2021 100% work 100% work Street Light Luminary AC GM West Bengal completed final completed. 75% 2019- 15 Street Light at Kutuch GP 809/DP 23/02/2021 480000 Agro Indries 360000 0 0 No UC will be UC will be 2020 12 Watt Corp LTD submitted submitted July,2021 04/08/2021 100% work 100% work GM West Bengal completed. 75% Street Light Luminary AC 2019- completed 1st UC 16 809/DP 23/02/2021 480000 Agro Indries 360000 0 0 No UC will be Street Light at Nimo GP 2020 will be submitted Corp LTD submitted end of June,2021 04/08/2021 100% work 100% work Street Light Luminary AC GM West Bengal completed Final completed. 75% 2019- 17 Street Light at Nimo GP 809/DP 23/02/2021 480000 Agro Indries 360000 0 0 No UC will be UC will be 2020 100 Nos Corp LTD submitted after submitted receiving of fund. 04/08/2021 117 Sanction UC Present Status for Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt the Month of for the Month No. Sanction Sanction Agency Released Utilized Progress No ed June of July 100% work 100% work Street Light Luminary AC 2019- GM West Bengal completed Final completed. 18 Street Light at Nimo I GP 2020 809/DP 23/02/2021 268800 Agro Indries 201600 0 0 No UC will be 75% UC will 56 Nos Corp LTD submitted after be submitted receiving of fund. 04/08/2021 100% work 100% work Street Light Luminary AC GM West Bengal completed Final completed. 2019- 19 Street Light at Satgachia 809/DP 23/02/2021 374400 Agro Indries 280800 0 0 No UC will be 75% UC will 2020 GP 78 nos Corp LTD submitted after be submitted receiving of fund. 04/08/2021 100% work 100% work Street Light Luminary AC GM West Bengal completed Final completed. 2019- 20 Street Light at Durgapur 809/DP 23/02/2021 326400 Agro Indries 244800 0 0 No UC will be 75% UC will 2020 GP 12 Watt Corp LTD submitted after be submitted receiving of fund. 04/08/2021

Total 5581625 4186218 299700

Constn. of Shed at Nudipur District 100% work Bhupendra Smirti 2021- 90% work 21 721/DP 18/02/2021 246875 Magistrate, 246875 0 0 No completed. Bill Vidyamandir under Bagila 2020 completed. Burdwan in progress. GP

Constn. of Tona District Ongoing, 52% 2021- 50% work 22 Auditorium under Gope 721/DP 18/02/2021 395520 Magistrate, 395520 0 0 No work 2020 completed. Gantar-I GP Burdwan completed. 118 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt for the Month of for the Month of No. Sanction Sanction Agency Released Utilized Progress No ed June July

Constn. of Ghosh District 2020- 45% work Ongoing, 56% 23 Audtorium under Gope 783/DP 21/02/2021 633750 Magistrate, 633750 0 0 No 2021 completed. work completed Gantar -II GP Burdwan

40% work Renovation and 75% UC will be 2020- BMOH, completed, 24 Upgradation of Memari 782/DP 21/02/2021 749007 561755 0 0 No submitted on 2021 Memari-I P.S. Ongoing Rural Hospital Memari 04/08/2021 Progress

100% work 100% work 2 No. AC High Mast Tower GM West completed, final completed. 75% Light Luminaries 150 Watt. 2020- Bengal Agro 25 805/DP 23/02/2021 400000 400000 300000 75 Yes UC will be UC will be LED at Chotkhanda Bazar 2021 Indries Corp received after submitted and Maheshdanga Camp LTD received the fund 04/08/2021

100% work 100% work GM West completed, Final Street Light Luminary AC completed. 75% 2020- Bengal Agro UC will be 26 Street Light 12 Watt at 806/DP 23/02/2021 460800 345600 0 0 No UC will be 2021 Indries Corp submitted after Amadpur GP submitted LTD receiving of 04/08/2021 fund.

100% work 100% work GM West Street Light Luminary AC completed, 1st completed. 75% 2020- Bengal Agro 27 Street Light 12 Watt at 806/DP 23/02/2021 480000 360000 0 0 No Phase UC will be UC will be 2021 Indries Corp Bagila GP submitted July, submitted LTD 2021 04/08/2021 119 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt for the Month for the Month of No. Sanction Sanction Agency Released Utilized Progress No ed of June July

100% work 100% work completed, 1st Street Light Luminary AC GM West Bengal completed. 75% 2020- Phase UC will 28 Street Light 12 Watt at 806/DP 23/02/2021 403200 Agro Indries 302400 0 0 No UC will be 2021 be submitted Dalui Bazar I GP Corp LTD submitted after receiving 04/08/2021 of fund

100% work 100% work completed, 1st Street Light Luminary AC GM West Bengal completed. 75% 2020- Phase UC will 29 Street Light 12 Watt at 806/DP 23/02/2021 432000 Agro Indries 324000 0 0 No UC will be 2021 be submitted Gantar-I GP Corp LTD submitted after receiving 04/08/2021 of fund

100% work 100% work completed, 1st Street Light Luminary AC GM West Bengal completed. 75% 2020- Phase UC will 30 Street Light 12 Watt at 806/DP 23/02/2021 432000 Agro Indries 324000 0 0 No UC will be 2021 be submitted Gantar-II GP Corp LTD submitted after receiving 04/08/2021 of fund

Total 5028752 4289500 300000

Grand Total 12302757 10105598 284700

120 Hon’ble M.L.A Shri Nisith Kumar Malik MLA of 266-Bardhaman Uttar (SC) A.C.

121 COMPLETED SCHEMES

122 NISITH KUMAR MALIK, HON'BLE MLA 266-Bardhaman Uttar (SC) A.C.

UC Sl. Sanction Date of Amount Amount Amount Physical Asset Handover Name of the Scheme Year Executing Agency Submitt No. Order No Sanction Sanction Released Utilized Progress Status ed

Purchase an Ambulance for 2016 - Executive Officer, 1 1975/DP 01/09/2016 520467 520467 520467 100 Yes Gobindapur G.P. 2017 Burdwan- II P.S.

PEC LTD, 55, Constn. of 13 PC Solar Street 2016 - 2 2901/DP 08/12/2016 325000 , 325000 325000 100 Yes Light five nos of G.P. 2017 Asset Handover Kolkata- 71. Report Wanting as per the Clause No. 8 PEC LTD, 55, Constn. of 18 PC Solar Street 2016 - under updated BEUP 3 2901/DP 08/12/2016 450000 Chowringhee Road, 450000 450000 100 Yes Light three nos of G.P. 2017 Guidelines 2019 Kolkata- 71.

PEC LTD, 55, Constn. of 17 PC Solar Street 2016 - 4 2901/DP 08/12/2016 425000 Chowringhee Road, 425000 425000 100 Yes Light four nos of G.P. 2017 Kolkata- 71.

Constn. of Busstand at 2016 - Executive Officer, 5 2969/DP 19/12/2016 300000 294467 294467 100 Yes Bhandardihi of Bondul-I G.P. 2017 Burdwan- I P.S. Asset Handover Report Received as per the Clause No. 8 under updated BEUP Constn. waiting Hall at Haldi 2016 - Executive Officer, 6 2969/DP 19/12/2016 300000 263000 263000 100 Yes Guidelines 2019 Bus Stand of Bhagar G.P 2017 Burdwan- I P.S.

123 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Constn. of Electric High Mast 2016 - Executive Officer, 7 2969/DP 19/12/2016 200000 198000 198000 100 Yes at Bhandardihi of Bondul G.P. 2017 Burdwan- I P.S. Asset Handover Report Received as per the Clause No. 8 under updated BEUP Constn. of Burning Ghat at 2016 - Executive Officer, 8 2969/DP 19/12/2016 350000 267540 267540 100 Yes Guidelines 2019 Talit Daspara of Bhagar G.P. 2017 Burdwan- I P.S.

Asset Handover Report Constn. of Liabrary grant of 2016 - Executive Officer, Wanting as per the 9 435/DP 08/02/2017 50000 50000 50000 100 Yes Clause No. 8 under Krishnapur High School Burdwan- I P.S. 2017 updated BEUP Guidelines 2019 Asset Handover Report Constn. of Waiting Hall at 2016 - Executive Officer, Received as per the 10 655/DP 01/03/2017 300000 274351 274351 100 Yes Clause No. 8 under Alampur Bus Stand of Bhagar-I Burdwan- I P.S. 2017 updated BEUP Guidelines 2019 Asset Handover Report Library Grant of Vidyasagar 2016 - Executive Officer, Wanting as per the 11 Uchha Vidyalaya of Saraitikor 704/DP 07/03/2017 50000 50000 50000 100 Yes Clause No. 8 under 2017 Burdwan- I P.S. G.P. updated BEUP Guidelines 2019

Asset Handover Report Constn. of Electric High Mast 2016 - Executive Officer, Received as per the 12 945/DP 27/03/2017 200000 199500 199500 100 Yes Clause No. 8 under in front of Nabastha I-G.P. Burdwan- II P.S. 2017 updated BEUP Guidelines 2019

124 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed Executive Constn. of Busstand at Raipur of 2016 - 13 1243/DP 21/04/2017 300000 Officer, 272771 272771 100 Yes Gobindapur G.P. 2017 Burdwan- II P.S. Asset Handover Report Received as Constn. of Burining Ghat Executive 2016 - per the Clause No. 8 14 waiting Shed at Amirpur of 1243/DP 21/04/2017 170000 Officer, 170000 170000 100 Yes 2017 under updated baikunthapur G.P. Burdwan- II P.S. BEUP Guidelines 2019 Constn. of Mukta Mancha at Executive 2016 - 15 Nandur Vivekananda F.P. 1358/DP 04/05/2017 100000 Officer, 100000 100000 100 Yes 2017 School of Baikunthapur Burdwan- II P.S.

Asset Handover Report Wanting as Executive Purchase an Ambulance for 2016 - per the Clause No. 8 16 2531/DP 13/09/2017 595204 Officer, 595204 595204 100 Yes Rayan -II G.P. 2017 under updated Burdwan- I P.S. BEUP Guidelines 2019 Four PC Computer for Barsul Executive 2016 - 17 CDP High School of Borsul II 3047/DP 21/11/2017 140000 Officer, 140000 140000 100 Yes Asset Handover 2017 G.P. Burdwan- II P.S. Report Received as per the Clause No. 8 under updated Constn. of Green Room for Executive 2016 - BEUP Guidelines 18 Community Hall Karanda of C-968/DP 22/05/2018 319834 Officer, 318051 318051 100 Yes 2017 2019 Nabastha G.P. Burdwan- II P.S.

125 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed Constn. of Community Hall 2016 - Executive Officer, 19 Karanda Of Nabastha C-968/DP 22/05/2018 452493 450292 450292 100 Yes 2017 Burdwan- II P.S. G.P.under Burdwan-II Total 5547998 5363643 5363643 Constn. of Boitarani scheme at Exe. Engg. PWD 2017 - 20 Bhandardihi, Jl. No. 36 of 1462/DP 17/05/2017 890000 (Social Sector), 857571 857571 100 Yes 2018 Asset Handover Bondul G.P. Burdwan. Report Received Constn. of Boitarani scheme at Exe. Engg. PWD as per the Clause 2017 - 21 Gopalpur, Plot No. 1713 of 1462/DP 17/05/2017 890000 (Social Sector), 857572 857572 100 Yes No. 8 under 2018 Bhagar G.P. Burdwan. updated BEUP Guidelines 2019 Constn. of Boitarani scheme at Exe. Engg. PWD 2017 - 22 Nabastha, Jl. No. 31 Plot No. 1462/DP 17/05/2017 890000 (Social Sector), 857571 857571 100 Yes 2018 1950 Burdwan. Constn. of Boitarani scheme at Exe. Engg. PWD 2017 - 23 Chandul, Jl. No. 31 Plot No. 1462/DP 17/05/2017 890000 (Social Sector), 857571 857571 100 Yes 2018 851 Burdwan.

Asset Handover Report Wanting as Library Grant of Sadhanpur 2017 - Executive Officer, per the Clause No. 24 Vivekananda High School 3356/DP 26/12/2017 50000 50000 50000 100 Yes 2018 Burdwan- I P.S. 8 under updated under Saraitikar BEUP Guidelines 2019

126 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed Electric High Mast Light at 2017 - Executive Officer, 25 Dewandighi More of Saraitikor 294/DP 09/02/2018 350000 350000 350000 100 Yes 2018 Burdwan- I P.S. Gram Purchase of 25 Nos Electric 2017 - Executive Officer, 26 Light Led Based at Atagarh 731/DP 05/04/2018 400000 397351 397351 100 Yes Asset Handover 2018 Burdwan- II P.S. Bazar Report Received as per the Clause No. 8 Purchase of 12.50 Mtr Electric 2017 - Executive Officer, under updated BEUP 27 Light Led Based at Saktigarh 731/DP 05/04/2018 430000 426622 426622 100 Yes 2018 Burdwan- II P.S. Guidelines 2019 Police Station to Barsul-I G.P. Purchase of 25 Nos Electric 2017 - Executive Officer, 28 Light Led Based at Kestopur 731/DP 05/04/2018 400000 397462 397462 100 Yes 2018 Burdwan- II P.S. More to cannel Bridge

Constn. of High School Main 2017 - Executive Officer, 29 1400/DP 30/07/2018 100000 100000 100000 100 Yes Asset Handover gate at Bondul-II G.P. 2018 Burdwan- II P.S. Report Wanting as per the Clause No. 8 Colouring of Wall of School 2017 - Executive Officer, under updated BEUP 30 Building at Saddaya High 1478/DP 09/08/2018 400000 400000 400000 100 Yes 2018 Burdwan- II P.S. Guidelines 2019 School Asset Handover Report Received as Instn of 10 Mtr Electric Mini 2017 - Executive Officer, per the Clause No. 8 31 High Mast Light at Jagadabad 1819/DP 14/08/2018 200000 200000 200000 100 Yes 2018 Burdwan- I P.S. under updated BEUP Shibtala ofBhaghar -I G.P. Guidelines 2019

Total 5890000 5751720 5751720

127 Sanction UC Sl. Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Order Submitt No. Sanction Sanction Agency Released Utilized Progress Status No ed

Constn.. of Mid day meal shade at Executive Kanthalgachi FP High School under 2018 - Officer, 32 560/DP 20/02/2019 200000 199707 199707 100 Yes Baikunthapur-II GP. within Burdwan-II 2019 Burdwan- II P.S. P.S. Installation of 10 mtr.High Mast Light Executive (Led Based) at Chandsona under 2018 - Officer, 33 560/DP 20/02/2019 200000 198610 198610 100 Yes Baikunthapur-II G.P. within Burdwan-II 2019 Burdwan- II P.S. P.S. Asset Handover Report Received as Constn.. and purchase of 16 nos. Executive per the Clause No. Electric Street Light (Led Based) near 2018 - Officer, 8 under updated 34 Gobindapur Kalitala Police Phanri 560/DP 20/02/2019 300000 280860 280860 100 Yes 2019 Burdwan- II BEUP Guidelines under Gobindapur GP. within Burdwan- P.S. 2019 II P.S.

Renovation and upgradation of Executive Community centre at Ullhas under 2018 - Officer, 35 046/DP 07/01/2020 300000 290864 290864 100 Yes Baikunthapur-II G.P. within Burdwan-II 2019 Burdwan- II P.S. P.S.

Total 1000000 971431 971431

Grand Total 12437998 12086794 12086794

128 ONGOING SCHEMES

129 NISITH KUMAR MALIK, HON'BLE MLA 266-Bardhaman Uttar (SC) A.C. UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month No. Order No Sanction Sanction Agency Released Utilized Progress ted of June of July Fund related Work completed, Constn. of Electric High Mast at 2016 - Executive Officer, 1 945/DP 27/03/2017 200000 200000 199500 95 Yes problem not Balance fund will Swastipally of Baikunthapur 2017 Burdwan- II P.S. solved. be refunded. Total 200000 200000 199500 Constn.. of Main Gate at Work order Dangapara F.P. School under 2017 - Executive Officer, work will be issued, work will 2 2659/DP 12/10/2020 100000 74775 0 0 No Rayan -I G.P. within Burdwan-I 2018 Burdwan- I P.S. started shortly. start on 1st week P.S. of August Printing works for exterior and GM, Agro Work just interior side of Nandur Industries Corpn. 3 2619/DP 02/06/2021 219802 164852 0 0 No Nil started. 10% Vivekananda F.P. School under Ltd. 23 B, Netaji work completed Burdwan-II P.S. Subha Total 319802 239627 0 Constn.. of Harinarayanpur 100% work Payment not Bidyasagar Culvert under 2018- Executive Officer, completed, Final 4 451/DP 05/02/2020 300000 245910 184433 75 Yes made due to lack Saraitikar G.P. within Burdwan- 2019 Burdwan- I P.S. UC will be given of fund I P.S. shortly. Installation of 10mtr. Mini High GM, Agro 100 % work 100% work Mast Tower at Balisha 2018- Industries Corpn. completed, UC completed. UC 5 1023/DP 20/03/2020 299700 299700 224775 75 Yes Masjidtala under Bondul-I GP 2019 Ltd. 23 B, Netaji will be sent will be sent after within Burdwan-I P.S. Subha shortly 2nd August Installation of 10mtr. Mini High GM, Agro 100 % work 100% work Mast Tower infront of 2018- Industries Corpn. completed, UC completed. UC 6 1022/DP 20/03/2020 299700 299700 224775 75 Yes Dangapara Pry. School under 2019 Ltd. 23 B, Netaji will be sent will be sent after Rayan-I within Burdwan-I P.S. Subha shortly 2nd August

130 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted of June July Installation of 10mtr. Mini High GM, Agro 100 % work 100% work Mast Tower near Jyotipally 2018- Industries Corpn. completed, UC completed. UC 7 Football Ground under 1023/DP 20/03/2020 299700 299700 224775 75 Yes 2019 Ltd. 23 B, Netaji will be sent will be sent after Baikunthapur -I G.P. within Subha shortly 2nd August Burdwan-I P.S. Installation of 10mtr. Mini High GM, Agro 100 % work 100% work Mast Tower near 2018- Industries Corpn. completed, UC completed. UC 8 Kasthakurumba Shibtala under 1023/DP 20/03/2020 299700 299700 224775 75 Yes 2019 Ltd. 23 B, Netaji will be sent will be sent after Bondul-II G.P.within Burdwan- Subha shortly 2nd August I P.S. Installation of 10mtr. Mini High GM, Agro 100 % work 100% work Mast Tower near Kharidya 2018- Industries Corpn. completed, UC completed. UC 9 1022/DP 20/03/2020 299700 299700 224775 75 Yes Kalitala under Rayan-II GP 2019 Ltd. 23 B, Netaji will be sent will be sent after within Burdwan-I P.S. Subha shortly 2nd August

Installation of 10mtr. Mini High GM, Agro 100 % work 100% work Mast Tower near Sapar Kalitala 2018- Industries Corpn. completed, UC completed. UC 10 1022/DP 20/03/2020 299700 299700 224775 75 Yes under Rayan-II within 2019 Ltd. 23 B, Netaji will be sent will be sent after Burdwan-I P.S. Subha shortly 2nd August 100 % work 100% work Executive Constn.. of Boundary wall at 2018- completed, UC completed, Final 11 2590/DP 05/10/2020 161800 Officer, 121350 0 0 No Jiara Upper Primary School 2019 will be sent UC will be given Burdwan- I P.S. shortly shortly work completed, Mini High Mast Light at Sona GM, Agro 100% work 75 % work Palashi Buro Shibtala under 2018- Industries Corpn. completed. UC 12 3225/DP 08/12/2020 299850 224888 0 0 No done, UC will Kurmun-II G.P. within 2019 Ltd. 23 B, Netaji will be sent after be sent within 7 Burdwan-II P.S. Subha 2nd August days 131 Sanctio UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year n Order Submit for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ted of June of July

100 % work 100% work Executive Constn. of Muktamancha at 2018- completed, UC completed, Final 13 446/DP 04/02/2021 196000 Officer, 147000 0 0 No Shaktigarh Girls High School 2019 will be sent UC will be Burdwan- II P.S. shortly given shortly Work completed, Repairing and renovation for Executive Work in 2018- 75 % work done, 14 Constn. of muktamancha at 595/DP 10/02/2021 489304 Officer, 366978 0 0 No progress, 70% 2019 UC will be sent Chandsona under Baikunthapur-II Burdwan- II P.S. work completed within 7 days

Constn. of Bondul Burning Ghat Executive Work in 2018- 15 at Bondul G.P. under Burdwan -I 2622/DP 02/06/2021 294000 Officer, 220500 0 0 No Nil progress, 75% 2019 P.S. Burdwan- I P.S. work completed

Constn. of embankment Executive Work started. protection Pranabananda 2018- 16 2622/DP 02/06/2021 294000 Officer, 220500 0 0 No Nil 10% work Samabay Griha under Burdwan-I 2019 Burdwan- I P.S. completed. P.S. GM, Agro Constn. of Mukta Mancha at Work started. 2018- Industries Corpn. 17 Baikunthapur at Baikunthapur 2755/DP 29/06/2021 399960 299970 0 0 No Nil 30% work 2019 Ltd. 23 B, Netaji Barowaritala completed. Subha Installation of 10 mtr. High Mast GM, Agro 100% work Light with 6x100 watt flood light 2018- Industries Corpn. completed. UC 18 2753/DP 29/06/2021 249950 187463 0 0 No Nil near Saligram Ram Rajtala at 2019 Ltd. 23 B, Netaji will be sent after Nabastha-I G.P. Subha 2nd August Total 4483064 3832759 1533083 132 Sanctio UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year n Order Submit for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ted of June of July Constn. of Community Hall at 80% work Executive Alampur Malikpara under 2019- 80 % work completed. UC 19 2504/DP 28/09/2020 307840 Officer, 230880 0 0 No Baghar-I G.P. within Burdwan-I 2020 completed will be sent Burdwan- I P.S. P.S. within 15 days. GM, Agro work completed, 100% work 10 Mtr. High Mast Towr Lighting 2019- Industries Corpn. 75 % work done, completed. UC 20 3245/DP 08/12/2020 249875 187406 0 0 No System at Borshul Utsab Maidan 2020 Ltd. 23 B, Netaji UC will be sent will be sent after Subha within 7 days 2nd August GM, Agro Work completed, 100% work 10 Mtr. High Mast Towr Lighting 2019- Industries Corpn. 75 % work done, completed. UC 21 3245/DP 08/12/2020 249875 187406 0 0 No System at Borsul PTTI College 2020 Ltd. 23 B, Netaji UC will be sent will be sent after Subha within 7 days 2nd August GM, Agro Work completed, 100% work 10 Mtr. High Mast Tower 2019- Industries Corpn. 75 % work done, completed. UC 22 Lighting System at Gobindapur 3245/DP 08/12/2020 249875 187406 0 0 No 2020 Ltd. 23 B, Netaji UC will be sent will be sent after Hattala Subha within 7 days 2nd August GM, Agro work completed, 100% work 10 Mtr. High Mast Tower 2019- Industries Corpn. 75 % work done, completed. UC 23 Lighting System at Palsa Bus 3245/DP 08/12/2020 249875 187406 0 0 No 2020 Ltd. 23 B, Netaji UC will be sent will be sent after Stand Subha within 7 days 2nd August GM, Agro work completed, 100% work 10 Mtr. High Mast Tower 2019- Industries Corpn. 75 % work done, completed. UC 24 Lighting System at Shaktigar 3245/DP 08/12/2020 249875 187406 0 0 No 2020 Ltd. 23 B, Netaji UC will be sent will be sent after Cinematala Subha within 7 days 2nd August GM, Agro work completed, 100% work 10 Mtr. High Mast Tower 2019- Industries Corpn. 75 % work done, completed. UC 25 Lighting System at Simdal Bus 3245/DP 08/12/2020 249875 187407 0 0 No 2020 Ltd. 23 B, Netaji UC will be sent will be sent after stand Subha within 7 days 2nd August 133 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted of June July GM, Agro 100% work 10 Mtr. High Mast Towr work completed, 2019- Industries 75 % work done, completed. UC will 26 Lighting System infront of 3245/DP 08/12/2020 249875 187406 0 0 No 2020 Corpn. Ltd. 23 UC will be sent be sent after 2nd Iscon Mandir at Parmra B, Netaji Subha within 7 days August GM, Agro 100% work 10 Mtr. High Mast Towr work completed, 2019- Industries 75 % work done, completed. UC will 27 Lighting System in front of 3245/DP 08/12/2020 249875 187407 0 0 No 2020 Corpn. Ltd. 23 UC will be sent be sent after 2nd Baghar-I G.P. B, Netaji Subha within 7 days August GM, Agro 100% work Inst of 10 Mtr High Mast at Work completed, 2019- Industries 75 % work done, completed. UC will 28 Ganga Bus Stand under 656/DP 12/02/2021 248000 186000 0 0 No 2020 Corpn. Ltd. 23 UC will be sent be sent after 2nd Baikunthapur GP B, Netaji Subha within 7 days August Installation of 15 mtr Led GM, Agro Work completed, 100% work Solar with 5 metre Tabular 2019- Industries 75 % work done, completed. UC will 29 652/DP 12/02/2021 89640 67230 0 0 No pole and 75 watt solar panel 2020 Corpn. Ltd. 23 UC will be sent be sent after 2nd complete with all accessories B, Netaji Subha within 7 days August GM, Agro 100% work Inst of 10 Mtr Mini High Work completed, 2019- Industries 75 % work done, completed. UC will 30 Mast at Malirbagan Canel 656/DP 12/02/2021 248250 186188 0 0 No 2020 Corpn. Ltd. 23 UC will be sent be sent after 2nd Bridge under Rayan-I B, Netaji Subha within 7 days August GM, Agro 100% work Instal of 15 mtr Led Solar Work completed, 2019- Industries 75 % work done, completed. UC will 31 with 5 meter tabular pole and 654/DP 12/02/2021 268650 201488 0 0 No 2020 Corpn. Ltd. 23 UC will be sent be sent after 2nd 75 watt solar Panel B, Netaji Subha within 7 days August

Constn. of waiting shed at 2019- Executive Work not started du 32 Balisha Bus stand at Bondul-I 2020 2626/DP 02/06/2021 336000 Officer, 252000 0 0 No Nil to dispute in land G.P. Burdwan- I P.S. 134 Sanction UC Present Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit Status for the for the Month of No. Sanction Sanction Agency Released Utilized Progress No ted Month of June July GM, Agro 100% work Installation of 15 watt LED 2019- Industries Corpn. completed. UC will 34 2625/DP 02/06/2021 359820 269865 0 0 No Nil Solar Light near 12 placess 2020 Ltd. 23 B, Netaji be sent after 2nd Subha August Installation of 15 watt Led solat GM, Agro 100% work 2019- Industries Corpn. completed. UC will 35 Light near 12 placess under 2624/DP 02/06/2021 358200 268650 0 0 No Nil 2020 Ltd. 23 B, Netaji be sent after 2nd Burdwan-I P.S. Subha August Installation of 15 mtr Led Solar GM, Agro 100% work with 5 metre Tabular pole and 2019- Industries Corpn. completed. UC will 36 2616/DP 02/06/2021 327690 245768 0 0 No Nil 75 watt solar panel near Mullie 2020 Ltd. 23 B, Netaji be sent after 2nd more and 10 placess Subha August Installation of 15 mtr Led Solar GM, Agro 100% work with 5 metre Tabular pole and 2019- Industries Corpn. completed. UC will 37 2623/DP 02/06/2021 268920 201690 0 0 No Nil 75 watt solar panel near Nadur 2020 Ltd. 23 B, Netaji be sent after 2nd Barowaritala to eight no. place Subha August Installation of 5 watt Led Solar GM, Agro 100% work 2019- Industries Corpn. completed. UC will 38 Light with 5 mtr. at 4 placess 2620/DP 02/06/2021 119880 89910 0 0 No Nil 2020 Ltd. 23 B, Netaji be sent after 2nd under Burdwan -I P.S. Subha August Constn. of Mukta Mancha at GM, Agro 2019- Industries Corpn. Work started, 35% 39 Samanti High School under 2780/DP 30/06/2021 299726 224795 0 0 No Nil 2020 Ltd. 23 B, Netaji work completed Bondul-II G.P. Subha Installation of 10 mtr. High GM, Agro 100% work 2019- Industries Corpn. completed. UC will 40 Mast with 6x12 watt Flood 2775/DP 30/06/2021 250000 187500 0 0 No Nil 2020 Ltd. 23 B, Netaji be sent after 2nd Light at Raipur Kaiiare School Subha August Total 5631616 4221464 135 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted of June July

GM, Agro 100% work Instn of 10 Mtr Mini High Mast work completed, 2020- Industries Corpn. 75 % work done, completd. UC 41 watt Flood Light at Alampur 653/DP 12/02/2021 249750 187313 0 0 No 2021 Ltd. 23 B, Netaji UC will be sent will be sent after Bus Stand Subha within 7 days 2nd August

GM, Agro 100% work Inst of 10 Mtr Mini High Mast work completed, 2020- Industries Corpn. 75 % work done, completd. UC 42 Light with Watt Flood Light at 653/DP 12/02/2021 248750 186563 0 0 No 2021 Ltd. 23 B, Netaji UC will be sent will be sent after Mahinnagar Bus Stand Subha within 7 days 2nd August

GM, Agro work completed, 100% work Inst of 10 Mtr Mini High Mast 2020- Industries Corpn. 75 % work done, completd. UC 43 653/DP 12/02/2021 249750 187313 0 0 No Light at Haldi Bus Stand 2021 Ltd. 23 B, Netaji UC will be sent will be sent after Subha within 7 days 2nd August

GM, Agro 100% work Inst of 10 Mtr Mini High Mast work completed, 2020- Industries Corpn. 75 % work done, completd. UC 44 watt Flood Light at infront of 653/DP 12/02/2021 248750 186563 0 0 No 2021 Ltd. 23 B, Netaji UC will be sent will be sent after 108 Shib Mandir Subha within 7 days 2nd August

GM, Agro work completed, 100% work Instal of 10 High Mast Watt 2020- Industries Corpn. 75 % work done, completd. UC 45 653/DP 12/02/2021 248750 186563 0 0 No Flood Light at Talit Bus Stand 2021 Ltd. 23 B, Netaji UC will be sent will be sent after Subha within 7 days 2nd August 100% work 10x14 sqf constn. of Mukta Executive 2020- completed. UC 46 Mancha at Mirzapur Play 2628/DP 02/06/2021 386800 Officer, 290100 0 0 No Nil 2021 will be given ground under Saraitikar G.P. Burdwan- II P.S. within 15 days 136 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted of June July Instn of 10 Mtr Mini High Mast GM, Agro 100% work watt Flood Lligh in front of 2020- Industries Corpn. completed. UC 47 2778/DP 30/06/2021 249000 186750 0 0 No Nil Begut Shivtala at Nabasta-I 2021 Ltd. 23 B, Netaji will be sent after G.P. Subha 2nd August GM, Agro 100% work Instn of 10 Mtr Mini High Mast 2020- Industries Corpn. completed. UC 48 watt Flood Llight at 2778/DP 30/06/2021 249750 187313 0 0 No Nil 2021 Ltd. 23 B, Netaji will be sent after Hatudewan Bus Stand Subha 2nd August Instn of 10 Mtr Mini High Mast GM, Agro 100% work watt Flood Llight at 2020- Industries Corpn. completed. UC 49 2778/DP 30/06/2021 249375 187031 0 0 No Nil Chandrahati Shibtala within 2021 Ltd. 23 B, Netaji will be sent after Rayan-II G.P. Subha 2nd August GM, Agro 100% work Instn of 10 Mtr Mini High Mast 2020- Industries Corpn. completed. UC 50 watt Flood Llight at Jamalpur 2778/DP 30/06/2021 249750 187313 0 0 No Nil 2021 Ltd. 23 B, Netaji will be sent after Sastitala under Rayan-II G.P. Subha 2nd August GM, Agro 100% work Instn of 10 Mtr Mini High Mast 2020- Industries Corpn. completed. UC 51 watt Flood Llight near Bandul 2778/DP 30/06/2021 249750 187313 0 0 No Nil 2021 Ltd. 23 B, Netaji will be sent after Bazar at Bondul-I G.P. Subha 2nd August Instn of 10 Mtr Mini High Mast GM, Agro 100% work watt Flood Llight in front of 2020- Industries Corpn. completed. UC 52 2778/DP 30/06/2021 249750 187406 0 0 No Nil Gossainpar Panchayat Market 2021 Ltd. 23 B, Netaji will be sent after at Baikunthapur-I G.P. Subha 2nd August Instn of 10 Mtr Mini High Mast GM, Agro 100% work watt Flood Llight in front of 2020- Industries Corpn. completed. UC 53 2778/DP 30/06/2021 249875 187406 0 0 No Nil Volibal Math at Nabasta- 2021 Ltd. 23 B, Netaji will be sent after II G.P. Subha 2nd August 137 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted of June July

Instn of 10 Mtr Mini High Mast GM, Agro 100% work watt Flood Llight at 2020- Industries Corpn. completed. UC 54 2778/DP 30/06/2021 249875 187405 0 0 No Nil Mirchridanga Adibasipara at 2021 Ltd. 23 B, Netaji will be sent after Nabasha-II G.P. Subha 2nd August

Instn of 10 Mtr Mini High Mast GM, Agro 100% work watt Flood Llight at Sripur 2020- Industries Corpn. completed. UC 55 2778/DP 30/06/2021 249875 187406 0 0 No Nil Baroaritala under Nabastha-II 2021 Ltd. 23 B, Netaji will be sent after G.P. Subha 2nd August

Total 3879550 2909758 0

Grand Total 14514032 11403608 1732583

138 Hon’ble M.L.A. Shri Subhash Mondal MLA 267 BHATAR A.C.

139 COMPLETED SCHEMES

140 SUBHAS MONDAL, HON'BLE MLA 267 BHATAR A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ed Asset Handover Report Constn. of Mouners waiting Executive Wanting as per the 2016 - 1 Room at Burning Ghat of Khetia 3007/DP 22/12/2016 300000 Officer, 300000 300000 100 Yes Clause No. 8 under 2017 G.P. Burdwan- I P.S. updated BEUP Guidelines 2019 Instn of High Mast Light at Executive 2016 - 2 Kurmun Hospital of Kurmun 3007/DP 22/12/2016 300000 Officer, 300000 300000 100 Yes 2017 G.P. Burdwan- I P.S.

Executive Constn. of Kurmun Girls School 2016 - 3 3007/DP 22/12/2016 300000 Officer, 300000 300000 100 Yes Building Boundary Wall 2017 Burdwan- I P.S. Building boundary wall between Asset Handover Report Kherur Chhadni Khetronath Executive Received as per the 2016 - 4 Uchha Bidlaya and Khetronath 3072/DP 28/12/2016 200000 Officer, Bhatar 200000 200000 100 Yes Clause No. 8 under 2017 Prathomik Bidyalaya of Amru P.S. updated BEUP G.P. Guidelines 2019 Constn. of Mourners waiting Executive 2016 - 5 room at Burning ghat of 3072/DP 28/12/2016 250000 Officer, Bhatar 227995 227955 100 Yes 2017 Moragore Ghat Shilakote village P.S.

Executive Constn. of Waiting Shelter at Bus 2016 - 6 206/DP 17/01/2017 300000 Officer, Bhatar 204576 204576 100 Yes Stand at Mahata G.P. 2017 P.S. 141 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ed Executive Passenger of Waiting Shelter at 2016 - 7 206/DP 17/01/2017 300000 Officer, 220541 220541 100 Yes Bus Stand of Barabelun Daspara 2017 Bhatar P.S.

Executive Passenger waiting shelter at Bus 2016 - 8 206/DP 17/01/2017 300000 Officer, 197152 197152 100 Yes Stand of Muratipur 2017 Bhatar P.S.

Constn. of Bhamsore Gram Jr. Executive 2016 - 9 High School building Class Room 263/DP 20/01/2017 400000 Officer, 400000 400000 100 Yes 2017 of Bhatar G.P. Bhatar P.S. Asset Handover Report Received as per the Constn. of Boundary Wall with Executive Clause No. 8 under 2016 - 10 gate at Health Centre at Bhnatakul 263/DP 20/01/2017 250000 Officer, 187254 187254 100 Yes updated BEUP Guidelines 2017 village Bhatar P.S. 2019

Constn. of Mouners waiting Room Executive 2016 - 11 at Burning Ghat of Shalkuni 700/DP 07/03/2017 300000 Officer, 205484 205484 100 Yes 2017 Adibasipara Bhatar P.S.

Constn. of Furnace and shed at Executive 2016 - 12 Burning Ghat at Bonpas 700/DP 07/03/2017 300000 Officer, 245080 245080 100 Yes 2017 Kamarpara Bhatar P.S.

142 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ted

Executive Constn. of Mouners waiting Room 2016 - 13 700/DP 07/03/2017 300000 Officer, 300000 300000 100 Yes at Burning Ghat of Arur Gram 2017 Bhatar P.S.

Executive Constn. of Mouners waiting Room 2016 - 14 700/DP 07/03/2017 300000 Officer, 298105 298105 100 Yes at Burning Ghat of Sunur Gram 2017 Bhatar P.S.

Passenger of waiting shelter at Executive 2016 - 15 Busstand including Toilet of Debpur 700/DP 07/03/2017 250000 Officer, 200631 200631 100 Yes 2017 Shed Bhatar P.S. Asset Handover Report Received as per the Clause No. 8 under updated BEUP Executive Constn. of Mouners waiting Room 2016 - Guidelines 2019 16 700/DP 07/03/2017 300000 Officer, 289497 289497 100 Yes at Burning Ghat at Patuna village 2017 Bhatar P.S.

Passenger Waiting Shelterat Executive 2016 - 17 Busstandof Kurmun Gram under 997/DP 30/03/2017 250000 Officer, 177448 177448 100 Yes 2017 Bhatar Bhatar P.S.

Constn.. of burning furnance at Executive 2016 - C- 18 burning station of Nasigram 05/06/2017 300000 Officer, 300000 300000 100 Yes 2017 1588/DP Barabelun of Barbelun - II G.P. Bhatar P.S.

Total 5200000 4553763 4553763 143 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Constn. of one new Class Room Executive 2017 - 19 at Dasarathi Hazra Memorial 2681/DP 13/10/2017 1200000 Officer, 1200000 1200000 100 Yes 2018 College Bhatar P.S.

Exe. Engg. Constn.. of Baitarani scheme at 2017 - PWD (Social 20 Bhatar Development Block and 2827/DP 06/11/2017 890000 845011 845011 100 Yes 2018 Sector), Orgram (Jl-011, Plot-8052) Burdwan. Asset Handover Report Exe. Engg. Constn.. of Baitarani scheme at Received as per the 2017 - PWD (Social 21 Bhatar Development Block and 2827/DP 06/11/2017 890000 845011 845011 100 Yes Clause No. 8 under 2018 Sector), Palar (Jl. no. 063, Plot-2573) updated BEUP Burdwan. Guidelines 2019

Constn. of Cycle Stand Banpas Executive 2017 - 22 Sikhsha Niketan under Banpas 771/DP 10/04/2018 350000 Officer, 294156 294156 100 Yes 2018 G.P. Bhatar P.S.

Constn. of New Passenger Executive 2017 - 23 Waiting Shelter at Busstop 771/DP 10/04/2018 300000 Officer, 260857 260857 100 Yes 2018 Rampur under Aruar G.P. Bhatar P.S.

144 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Constn.. of burning furnace and Executive 2017 - 24 waiting room at the burning 771/DP 10/04/2018 500000 Officer, 413980 413980 100 Yes 2018 Asset Handover Report station at Muraripur Bhatar P.S. Received as per the Clause No. 8 under Constn. of new passenger Executive updated BEUP waiting shelter at bus stop 2017 - 25 2496/DP 15/11/2018 300000 Officer, 215828 215828 100 Yes Guidelines 2019 Ramchandrapur under Mahata 2018 Bhatar P.S. G.P. within Bhatar P.S.

Total 4430000 4074843 4074843

Constn. of Boundary wall at Asset Handover Report Tulsidanga Burning Station (Plot Executive Received as per the 2018 - 26 No. 117, J.L. no. 79, Tulsidanga) 1798/DP 22/07/2019 300000 Officer, 251070 251070 100 Yes Clause No. 8 under 2019 under Bolgona G.P. within Bhatar P.S. updated BEUP Bhatar P.S. Guidelines 2019

Total 300000 251070 251070 Grand Total 9930000 8879676 8879676

145 ONGOING SCHEMES

146 SUBHAS MONDAL, HON'BLE MLA 267 BHATAR A.C.

UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month of for the Month No. Order No Sanction Sanction Agency Released Utilized Progress ted June of July Installation of X ray West Bengal Work order issued, Work order issued, machine at Bhatar 2016 - Medical informed to PWD informed to PWD 1 2294/DP 11/10/2018 567368 425526 0 0 No Hospital of Bhatar G.P. 2017 Services for infrastructural for infrastructural under Bhatar P.S. Corporation Ltd. development development Total 567368 425526 0

Constn. of New Passenger Executive 100% Work Waiting Shelter at Busstop 2017 - 100 % completed, completed, final 2 771/DP 10/04/2018 300000 Officer, Bhatar 300000 218713 95 Yes Baneswarpur Bus Stand 2018 UC will be sent UC will be P.S. under Barabelun G.P. received shortly. Constn.. of burning furnace and waiting room Executive 100% Work 2017 - 100 % completed, completed, final 3 at the burning station at 771/DP 10/04/2018 500000 Officer, 440886 375000 75 Yes 2018 UC sent UC will be Kharjuli of Khetia G.P. Burdwan- I P.S. received shortly. under Burdwan -I P.S. Constn.. of new passenger waiting shelter at bus stop Executive 100% Work 2017 - Rs, 13018 will be completed, final 4 kurmun under Kurmun 2285/DP 11/10/2018 350000 Officer, 263000 249982 92 Yes 2018 refunded UC will be G.P. within Burdwan-I Burdwan- I P.S. received shortly. P.S. Fund will be Constn.. of new Class 90% work Executive released, Panchayet room at Selenda F.P. 2017 - completed, 2nd 2496/DP 15/11/2018 400000 Officer, Bhatar 331960 200000 50 Yes samity sent a 5 phase UC will be School at Bolgona G.P. 2018 resolution but to be P.S. recevided shortly. under Bhatar P.S. received yet Total 1550000 1335846 1043695 147 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month of for the Month of No. Sanction Sanction Agency Released Utilized Progress No ted June July Constn.. of new passenger 100% work 100% Work waiting shelter at bus stop Executive 2018 - completed UC will completed, 1st 6 Nasigram Daspara More near 49/DP 04/01/2019 300000 Officer, 225000 0 0 No 2019 be submitted after phase UC will be Gramin Bank under Barabelun- Bhatar P.S. receiving of fund recevided shortly II G.P. within Bhatar P.S. Fund will be Constn.. of new passenger released, 100% work waiting shelter at bus stop (Plot Executive 2018 - Panchayet samity completed, final 7 No. 262 Sodkhali Bhatar 616/DP 22/02/2019 400000 Officer, 300000 300000 75 Yes 2019 sent a resolution UC will be College under Arurar G.P. Bhatar P.S. but to be received received shortly. within Bhatar P.S. yet Fund will be released, 90% work Constn.. of new class room Executive 2018 - Panchayet samity completed, 2nd 8 Arurar BMDP Institution under 1449/DP 18/06/2019 500000 Officer, 421500 375000 75 Yes 2019 sent a resolution phase UC will be Aurar within Bhatar P.S. Bhatar P.S. but to be received recevided shortly. yet Constn.. of waiting hall at 100% Work Gramdihi Burning Station (Plot Executive 2018 - 100 % completed, completed, final 9 No.-530 Gramdihi) under 2333/DP 30/08/2019 300000 Officer, 239850 225000 75 Yes 2019 UC will be sent UC will be Sahebgunj-II G.P. within Bhatar P.S. received shortly. Bhatar P.S. Constn. of Burning Furnace at Aimapara Das para Burning 100% Work Executive Station (Plot No. 3213, 2018 - 101 % completed, completed, final 10 2333/DP 30/08/2019 200000 Officer, 159990 150000 75 Yes Aimapara, Das para) under 2019 UC will be sent UC will be Bhatar P.S. Sahebgung-II G.P. within received shortly. Bhatar P.S. 148 Sanction UC Present Status Present Sl. Date of Amount Executing Amount Amount Physical 17Name of the Scheme Year Order Submit for the Month of Status for the No. Sanction Sanction Agency Released Utilized Progress No ted June Month of July

Constn. of Stage of Bhatar Executive Work not started, 2018 - Work will be started 11 College under Bhatar G.P. within 432/DP 04/02/2020 376150 Officer, Bhatar 282112 0 0 No workorder just 2019 shortly Bhatar P.S. P.S. issued 100 % Constn.. of Passenger waiting at Executive Work Completed, 100% Work 2018 - UC submitted within completed, final 12 Bus Stand at Jatradighi under 059/DP 07/01/2020 350000 Officer, Bhatar 262500 0 0 No 2019 10 days, UC UC will be Aruar G.P. within Bhatar P.S. P.S. submitted within 10 received shortly. days Constn.. of High Mast Light Plot- West Bengal 100 % 7828 Kh-3062 Jl-89 Mouza- Work Completed, 100% Work 2018 - Agro Industries 13 Nasigram Shiv Mandir under 2788/DP 16/10/2020 299700 224775 0 0 No 1st Phase UC under completed, bill 2019 Corporation Baro Belun-II G.P. within Bhatar Process, 1st Phase on process Ltd. P.S. UC under Process Constn.. of High Mast Light near West Bengal 100 % Panchayat Samity Guest House Work Completed, 100% Work 2018 - Agro Industries 14 Orgram Plot-5561, Jl-11 under 2788/DP 16/10/2020 299700 224775 0 0 No 1st Phase UC under completed, bill 2019 Corporation Sahebgunj-I G.P. within Bhatar Process, 1st Phase on process Ltd. P.S. UC under Process Constn.. of High Mast Light near West Bengal 100 % Barobelun Baro Ma Kali Mandir Work Completed, 100% Work 2018 - Agro Industries 15 Plot-2985, Jl-93 Kh-630 mouza- 2788/DP 16/10/2020 299700 224775 0 0 No 1st Phase UC under completed, bill 2019 Corporation Barobelun under Barobelun-I G.P. Process, 1st Phase on process Ltd. within Bhatar P.S. UC under Process Constn.. of waiting room near 100% work Parhat Shib Mandir on Plot No. Executive 100% Work 2018 - completed UC will 2896 Jl-47 Mouza-Parhat under 2852/DP 02/11/2020 371750 Officer, Bhatar 371750 278813 75 Yes completed, Final 16 be submitted after 2019 bill on process. Mahachanda G.P. within Bhatar P.S. receiving of fund P.S. 149 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ted of June of July Constn. of Passenger waiting room at Executive 100% work 100% Work Dauradanga Bus stand on Plot no. 2018 - completed UC will completed, final 17 2852/DP 02/11/2020 218550 Officer, 218550 163913 75 Yes 1174, Jl-7, Mouza-Daura under 2019 be submitted after UC will be Bhatar P.S. Mahata G.P. within Bhater P.S. receiving of fund received shortly.

Constn.. of open air stage near 100% work Executive 100% Work Bhairabpur Baroaritala Plot-1044, Jl- 2018 - completed UC will 18 2852/DP 02/11/2020 213150 Officer, 213150 159863 75 Yes completed, Final 75 Kh-485/1 under Nityanandapur 2019 be submitted after Bhatar P.S. bill on process. G.P. within Bhatar P.S. receiving of fund Constn.. of Mournes waiting room at burning ghat on Plot No.29, Jl-31 at Executive 100% work 100% Work 2018 - completed UC will completed, final 19 Kashipur Nonadanga Adbasipara 2852/DP 02/11/2020 150020 Officer, 150020 112515 75 Yes 2019 be submitted after UC will be under Sahebgung-I G.P. within Bhatar P.S. receiving of fund received shortly. Bhatar P.S. Constn.. of Burning Furnance at 100% work Burning station at Sunur Purba Executive 100% Work 2018 - completed UC will village under Amarun-I G.P. 2852/DP 02/11/2020 186825 Officer, 186825 140119 75 Yes completed, Final 20 be submitted after 2019 bill on process. (Mouza-Ghugia, Jl-102, Plot-1592) Bhatar P.S. receiving of fund within Bhatar P.S. Constn. of Mourner waiting room at Executive 70% work 2018 - 21 Burning station Kolabagan at 2946/DP 22/07/2021 228900 Officer, 171675 0 0 No Nil completed. Bill on 2019 Mahachanda G.P. Bhatar P.S. process Executive 100% Work Constn. of new class room Rampur 2018 - 22 2946/DP 22/07/2021 384040 Officer, 288030 0 0 No Nil completed, Final Improved F.P. School at Aruar G.P. 2019 Bhatar P.S. bill on process. Total 5078485 4165677 1905223 150 Present Sanction UC Present Status Sl. Date of Amount Executing Amount Amount Physical Status for the Name of the Scheme Year Order Submit for the Month No. Sanction Sanction Agency Released Utilized Progress Month of No ted of July June Constn. of one classroom at Executive 2019- Work in progress, 23 Malkita Basic Higher Secondsry 2754/DP 29/06/2021 392000 Officer, 294000 0 0 No Nil 2020 10% work done. School Burdwan- I P.S. Executive 100% Work Constn. of Open cultural stage 2019- 24 2754/DP 29/06/2021 432000 Officer, 324000 0 0 No Nil completed, Final near shibmandir at Kurmun-I G.P. 2020 Burdwan- I P.S. bill on process. Constn. of public waiting room Executive 2019- Work will be 25 nearr Daspur Baromayertala under 2754/DP 29/06/2021 288000 Officer, 216000 0 0 No Nil 2020 started on August Khetia G.P. Burdwan- I P.S. Executive 100% work Constn. of Swasan Chulli at Parui 2019- completed, final 26 2754/DP 29/06/2021 248250 Officer, 186188 0 0 No Nil under Khetia G.P. 2020 UC will be given Burdwan- I P.S. within 15 days. Constn. of one classroom at Executive 2019- Work will be 27 Kharjuli Sri Sri Ramkrishna F.P. 2754/DP 29/06/2021 343000 Officer, 257250 0 0 No Nil 2020 started on August School Burdwan- I P.S. Constn. of Public waiting room Executive 2019- Work will be 28 near Daspur Baroaritala under 2754/DP 29/06/2021 288000 Officer, 216000 0 0 No Nil 2020 started on August Khetia G.P. Burdwan- I P.S. Executive 90% Work Constn. of Community Hall near 2019- 29 2947/DP 22/07/2021 328880 Officer, Bhatar 246660 0 0 No Nil completed, Final shiv Mandir at Mohanpur 2020 P.S. bill on process. Constn. of open air theatre near Executive 95% Work 2019- 30 Basuda Ramkrishna Ashram under 2947/DP 22/07/2021 320000 Officer, Bhatar 240000 0 0 No Nil completed, Final 2020 Machanda G.P. P.S. bill on process. Total 2640130 1980098 0 151 Present Sanction UC Present Status Sl. Date of Amount Executing Amount Amount Physical Status for the Name of the Scheme Year Order Submit for the Month No. Sanction Sanction Agency Released Utilized Progress Month of No ted of July June

West Bengal 100% work Supply and installation Led light 2020- 31 2811/DP 02/07/2021 299100 Agro Industries 224325 0 0 No Nil completed, bill near Jhama More 2021 Corporation Ltd. will be processed

West Bengal 100% work Supply and installation Led light 2020- 32 2811/DP 02/07/2021 299100 Agro Industries 224325 0 0 No Nil completed, bill near Orgram Bus Stand 2021 Corporation Ltd. will be processed

West Bengal 100% work Supply and installation Led light 2020- 33 2811/DP 02/07/2021 299100 Agro Industries 224325 0 0 No Nil completed, bill near Salkuni Shiv Mandir 2021 Corporation Ltd. will be processed

West Bengal 100% work Supply and installation Led light 2020- 34 2811/DP 02/07/2021 299100 Agro Industries 224325 0 0 No Nil completed, bill near Joy Durga Mandir 2021 Corporation Ltd. will be processed

West Bengal 100% work Supply and installation Led light 2020- 35 2811/DP 02/07/2021 299100 Agro Industries 224325 0 0 No Nil completed, bill near Kamarpara Durga Mandir 2021 Corporation Ltd. will be processed

West Bengal 100% work Supply and installation Led light 2020- 36 2811/DP 02/07/2021 299100 Agro Industries 224325 0 0 No Nil completed, bill near Bazar 2021 Corporation Ltd. will be processed

West Bengal 100% work Supply and installation Led light 2020- 37 2811/DP 02/07/2021 299100 Agro Industries 224325 0 0 No Nil completed, bill near Kherur Chhatni Bazar 2021 Corporation Ltd. will be processed 152 Present Sanction UC Present Status Sl. Date of Amount Executing Amount Amount Physical Status for the Name of the Scheme Year Order Submit for the Month No. Sanction Sanction Agency Released Utilized Progress Month of No ted of July June 100% work West Bengal Supply and installation Led light 2020 - completed, bill 38 2811/DP 02/07/2021 299100 Agro Industries 224370 0 0 No Nil near Durgadanga Bus Stand 2021 will be Corporation Ltd. processed 100% work Supply and installation Led light West Bengal 2020 - completed, bill 39 near Dasarathi Hazra Memorial 2811/DP 02/07/2021 299100 Agro Industries 224325 0 0 No Nil 2021 will be College Corporation Ltd. processed 100% work West Bengal Supply and installation Led light 2020 - completed, bill 40 2811/DP 02/07/2021 299100 Agro Industries 224325 0 0 No Nil near Muratipur Choumatha 2021 will be Corporation Ltd. processed 100% work West Bengal Supply and installation Led light 2020 - completed, bill 41 2811/DP 02/07/2021 299100 Agro Industries 224325 0 0 No Nil near Khemi Maa Mandirtola 2021 will be Corporation Ltd. processed Total 3290100 2467620 0

Grand Total 13426083 10374767 2948918

153 Hon’ble M.L.A. Shri Swapan Debnath 268 PURBASTHALI DAKSHIN A.C.

154 COMPLETED SCHEMES

155 SWAPAN DEBNATH, HON'BLE MLA 268 PURBASTHALI DAKSHIN A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ed

Constn. of Waiting Shed at 2016 - Executive Officer, 1 2630/DP 10/11/2016 400000 400000 400000 100 Yes Vill. Isabpur of Sultan G.P. 2017 Kalna- I P.S.

Constn. of waiting Shed at 2016 - Executive Officer, 2 village Durgapur of Nandai 2630/DP 10/11/2016 400000 400000 400000 100 Yes 2017 Kalna- I P.S. G.P. Constn. of Waiting Shed at 2016 - Executive Officer, 3 Village Kasimpur of Sultanpur 2630/DP 10/11/2016 200000 200000 200000 100 Yes 2017 Kalna- I P.S. G.P. Asset Handover Report Constn. of waiting shed at 2016 - Executive Officer, Received as per the 4 village SandalpurAtgoria of 2630/DP 10/11/2016 600000 538178 538178 100 Yes 2017 Kalna- I P.S. Clause No. 8 under Simlon G.P. updated BEUP Sinking Tubewell with 1 H.P. Guidelines 2019 Motor and Tank for supplying 2016 - Executive Officer, 5 2630/DP 10/11/2016 100000 100000 100000 100 Yes drinking waterat vill Bhatra of 2017 Kalna- I P.S. Sultanpur G.P. Sinking Tubewell with 1 H.P. Motor and Tank for supplying 2016 - Executive Officer, 6 2630/DP 10/11/2016 100000 100000 100000 100 Yes drinking waterat vill 2017 Kalna- I P.S. Kasirampur Constn. of Bathing Ghat at 2016 - Executive Officer, 7 Nagragachi Uttarpara of 2630/DP 10/11/2016 200000 160218 160218 100 Yes 2017 Kalna- I P.S. Nandai G.P. 156 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed Constn. of a Community Shed 2016 - Executive Officer, 8 at Baghandanga vill begpur 3092/DP 29/12/2016 140000 140000 140000 100 Yes 2017 Kalna- I P.S. G.P.

Constn. of Bathing Ghat at 2016 - Executive Officer, 9 Kharama Pond vill 3092/DP 29/12/2016 130000 130000 130000 100 Yes 2017 Kalna- I P.S. Choughoria of Begpur G.P.

Constn. of Bathing Ghat at 2016 - Executive Officer, 10 Talbona pond vill Simalgoria 3092/DP 29/12/2016 130000 130000 130000 100 Yes Asset Handover 2017 Kalna- I P.S. of Begpur G.P. Report Received as per the Clause No. 8 under Infrastructual Development of 2016 - Executive Officer, updated BEUP 11 Kulora Graveyard of Begpur 152/DP 11/01/2017 200000 200000 200000 100 Yes 2017 Kalna- I P.S. Guidelines 2019 G.P.

Infrastructual Development of 2016 - Executive Officer, 12 Fakirdanga Gravyard of 152/DP 11/01/2017 200000 200000 200000 100 Yes 2017 Kalna- I P.S. Begpur G.P.

Infrastructual Development of 2016 - Executive Officer, 13 Kapurdanga Graveyard of 152/DP 11/01/2017 200000 200000 200000 100 Yes 2017 Kalna- I P.S. Begpur G.P.

Asset Handover Constn. of addl work of Report Wanting as per Flood Shelter 2016 - Executive Officer, 14 891/DP 22/03/2017 167000 167000 167000 100 Yes the Clause No. 8 under Adjacent to Police 2017 Purbasthali- I P.S. updated BEUP Station Guidelines 2019 157 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Constn. of waiting Shed at Duley 2016 - Executive Officer, 15 891/DP 22/03/2017 33000 32852 32852 100 Yes Para of Samudragarh G.P. 2017 Purbasthali- I P.S.

Setting of Solar street System at Babulitala Bazar of Sultanpur, 2016 - Executive Officer, 16 996/DP 30/03/2017 500000 500000 500000 100 Yes Kalna RoadBurdwan Road Bitra 2017 Kalna- I P.S. Road Memari Road

Asset Handover Constn. of waiting Shed at Report Wanting as 2016 - Executive Officer, 17 Dakshinbati Samudragarh under 996/DP 30/03/2017 300000 294273 294273 100 Yes per the Clause No. 8 2017 Purbasthali- I P.S. Purbasthali under updated BEUP Guidelines 2019

Dev. of frist Floor Class Rooms 2016 - Executive Officer, 18 at Bhabatarini Roy Girls High 1630/DP 08/06/2017 500000 490000 490000 100 Yes 2017 Purbasthali- I P.S. School of Srirampur

Constn. of bathing Ghat at Land 2016 - Executive Officer, 19 of Gopal BagDag No 140 Mouza 1368/DP 23/07/2018 300000 300000 300000 100 Yes 2017 Purbasthali- I P.S. Vidyanagar of Srirampur GP

158 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn. of Community Room with Toilet and bathroom at 2016 - Executive Officer, 20 vhaktibhandar Jl No. 135Mouza 1368/DP 23/07/2018 500000 500000 500000 100 Yes 2017 Purbasthali- I P.S. Asset Handover Report Srirampurkh No 2270 of srirampur Wanting as per the GP. Clause No. 8 under Constn.. of Bathing Ghat beside the updated BEUP Guidelines 2019 house of R. Biswas on Khari river at 2016 - Executive Officer, 21 674/DP 27/02/2019 400000 399160 399160 100 Yes Nasaratpur G.P. under Purbasthali-I 2017 Purbasthali- I P.S. P.S. Total 5700000 5581681 5581681 Renovation and upgradation of flood Asset Handover Report shelter at Nasaratpur (Dag No. 204, 2017 - C- Executive Officer, Wanting as per the 22 04/08/2017 1300000 1231876 1231876 100 Yes Clause No. 8 under 1060) Mouza - Nasaratpur, JL No. 2018 2198/DP Purbasthali- I P.S. updated BEUP 186. Guidelines 2019 Constn. of Bathing Ghat at Pado 2017 - Executive Officer, 23 Pukurin Bhabanipur village at 2287/DP 18/08/2017 300000 300000 300000 100 Yes 2018 Kalna- I P.S. G.P. Asset Handover Report Constn. of Bathing Ghat on the Bank Received as per the 2017 - Executive Officer, 24 of Bhgirathi River at Gram Kalna of 2287/DP 18/08/2017 300000 300000 300000 100 Yes Clause No. 8 under 2018 Kalna- I P.S. updated BEUP Dhatrigram Guidelines 2019 Constn. of Waiting Shed at 2017 - Executive Officer, 25 2287/DP 18/08/2017 300000 300000 300000 100 Yes Chakarpur of Dhatrigram G.P. 2018 Kalna- I P.S. Asset Handover Report Constn. of Concrete Road from 2017 - Executive Officer, Wanting as per the 26 house of Sri S Jar towards J. Mondal 2360/DP 28/08/2017 386000 386000 386000 100 Yes Clause No. 8 under 2018 Purbasthali- I P.S. Pond at Bonpukur updated BEUP Guidelines 2019 159 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Dev of One Childern Park within 2017 - Executive Officer, 27 the Block Office Campus under 3031/DP 20/11/2017 500000 486412 486412 100 Yes 2018 Purbasthali- I P.S. Purbasthali-I Constn.. of Dangapara Burial Ground under Nasaratpur G.P. 2017 - Executive Officer, 28 82/DP 08/01/2019 500000 479750 479750 100 Yes (Mouza-Nasaratpur, Jl-186, Plot- 2018 Purbasthali- I P.S. 844) under Purbasthali-I P.s. Total 3586000 3484038 3484038 Asset Handover Report Wanting Extension/ Expantion and allied 2018 - Executive Officer, as per the Clause 29 work of the Community hall of 2602/DP 06/10/2020 1969800 1969800 1477350 100 Yes 2019 Kalna- I P.S. No. 8 under Kalna-I P.S. updated BEUP Total 1969800 1969800 1477350 Guidelines 2019

Constn.. of waiting shed at 2019 - Executive Officer, 30 Gopalpur Jl-2889 under Srirampur 2886/DP 04/11/2020 967500 967500 967500 100 Yes 2020 Kalna- I P.S. G.P. within Kalna I P.S. Constn.. of waiting shed cum Night Shelter with drinking water facility 2019 - Executive Officer, 31 4516/DP 12/12/2019 937640 937640 703230 100 Yes at Srirampur within Purbasthali -I 2020 Purbasthali- I P.S. P.S. Total 1905140 1905140 1670730 Grand Total 13160940 12940659 12213799

160 ONGOING SCHEMES

161 SWAPAN DEBNATH, HON'BLE MLA 268 PURBASTHALI DAKSHIN A.C. Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ted of June of July Refund Renovation and upgradation of a Executive 100% work Notesheet has room at the centre for mental 2017 - Officer, completed, UC been done but 1 571/DP 12/02/2020 274530 274530 272103 99 Yes peace at Bogpur G.P. Under 2018 Purbasthali- will be submitted pending at casier Purbasthali-I P.S. I P.S. very shortly level due to COVID 100% work 100% work 6 nos. AC High mast Tower Light W.B Agro completed, Final completed. UC 2017 - 2 illumineries 150 Watt Led Based 804/DP 23/02/2021 1200000 Industries 1200000 900000 75 Yes UC will be will be 2018 four Arm Bracket and poll 10 Corp. Ltd. submitted after submitted receiving of fund 06/08/2021 Total 1474530 1474530 1172103 Constn. of new room of bright Executive 100% work 100% work Sishu Niketan more 2018 - completed final UC 3 4520/DP 12/12/2019 480100 Officer, 480100 360075 75 Yes completed. Bill under Atghoria Simlon G.P. 2019 will be submitted Kalna- I P.S. in progress within Kalna-I P.S. by 28/06/2021 Constn. of a new Class room of Executive 100% work 100% work Sujoti Sishu Niketan Simlon more 2018 - completed final UC 4 4519/DP 12/12/2019 480100 Officer, 480100 360075 75 Yes completed. Bill under Atghoria Simlon G.P. 2019 will be submitted Kalna- I P.S. in progress within Kalna-I P.s. by 28/06/2021 100% work Constn. of waiting shed at vill- Executive 100% work completed. UC Bhaidharpara Ashram under 2018 - Officer, completed final UC 5 4558/DP 17/12/2019 452300 452300 339225 75 Yes will be Begpur G.P. within Purbasthali-I 2019 Purbasthali- will be submitted submitted P.S. I P.S. by 25/06/2021 05/08/2021162 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted of June July

Constn.. of waiting shed at Executive 100% work 100% work Bamungram under Nadanghat 2018 - Officer, completed, UC completed. UC 6 G.P. (Dag-167, Jl.-168, 2399/DP 22/09/2020 455600 455600 341700 75 Yes 2019 Purbasthali- I will be submitted will be submitted Mouza-Gahok) within P.S. 25/06/2021 05/08/2021 Purbasthali-I P.S.

100% work 100% work Constn. of Waiting Shed at Executive completed, Final 2018 - completed. UC 7 Bibirjule Dhatrigram under 247/DP 25/01/2021 461800 Officer, 461800 346350 75 Yes UC will be 2019 will be submitted Dhatrigram Kalna- I P.S. submitted after 05/08/2021 receiving of fund

100% work Executive completed, Final Constn. of Rest Room for 2018 - 75% work 8 247/DP 25/01/2021 479250 Officer, 479250 359438 75 Yes UC will be villagers Durgapur 2019 completed Kalna- I P.S. submitted after receiving of fund

100% work Constn. of Waiting Shed at Executive completed, Final 100% work 2018 - 9 Ashrampara Mouza Nandai JL 773/dp 21/02/2021 197500 Officer, 497500 373125 75 Yes UC will be completed. Bill in 2019 No 43 Kalna- I P.S. submitted after progress receiving of fund

Total 3006650 3306650 2479988

163 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted of June July 100% work 100% work Executive completed, Final Constn. of Waiting Shed at 2019 - completed. UC 10 248/DP 25/01/2012 300000 Officer, 300000 225000 75 Yes UC will be Sakati 2020 will be submitted Kalna- I P.S. submitted after 05/08/2021 receiving of fund Executive 100% work 75% UC will be Constn. of Cycle Standat 2019 - Officer, completed, UC 11 249/DP 25/01/2021 425050 318788 0 0 No submitted Kuricha under Bhogpur GP 2020 Purbasthali- I will be submitted 05/08/2021 P.S. 25/06/2021 Work not started Executive Constn. of Boundary wall at due to land 2019 - Officer, 12 G.C. Pal Bilika 2804/DP 02/07/2021 269310 201982 0 0 No Nil problem and work 2020 Purbasthali- I Vidyalaya will start by P.S. August 1st week Total 994360 820770 225000 100% work 100% work Constn. of Waiting Shed at Executive 2020- completed, UC completed. UC 13 Ranibandh village under 259/DP 25/01/2021 827550 Officer, 827550 620662 75 Yes 2021 will be submitted will be submitted Kurkuba GP Kalna- I P.S. 25/06/2021 05/08/2021 100% work 2 nos. High Mast Tower Light 100% work W.B Agro completed, Final Illuminerise 150 watt Led 2020- completed. UC 14 808/DP 23/02/2021 400000 Industries 400000 300000 75 Yes UC will be based at Kalinagar Ghat, 2021 will be submitted Corp. Ltd. submitted after Dangapara 05/08/2021 receiving of fund Total 1227550 1227550 920662

Grand Total 6703090 6829500 4797753 164 Hon’ble M.L.A. Shri Pradip Kumar saha MLA 269 PURBASTHALI UTTAR A.C.

165 COMPLETED SCHEMES

166 PRADIP KUMAR SAHA, HON'BLE MLA 269 PURBASTHALI UTTAR A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Constn. of Concrete road from 2016 - Executive Officer, 1 Pakhi Mondals house to Debu 1795/DP 12/08/2016 200000 200000 200000 100 Yes 2017 Monteswar P.S. Mondals house at Pursuri village Constn. of Concrete road from 2016 - Executive Officer, 2 Manju Dafadar house to Madhu 1795/DP 12/08/2016 150000 150000 150000 100 Yes 2017 Monteswar P.S. Dafadar house at Monadanga

Constn. of Concrte road Sashtitala 2016 - Executive Officer, 3 1795/DP 12/08/2016 75000 75000 75000 100 Yes to Narayan Ghar at Natun Gram 2017 Monteswar P.S. Asset Handover Constn. of Concrete road from 2016 - Executive Officer, Report Received 4 Sibtala to Manasa Tala at Gulita vill 1795/DP 12/08/2016 150000 149622 149622 100 Yes 2017 Monteswar P.S. as per the Clause of Bamunpara G.P. No. 8 under updated BEUP Constn. of Concrete road from 2016 - Executive Officer, Guidelines 2019 5 1795/DP 12/08/2016 75000 75000 75000 100 Yes Masjid to Kabarsthan at Narugram 2017 Monteswar P.S.

Constn. of concrete road from 2016 - Executive Officer, 6 Simul Majhi House to Kebal Majhis 1795/DP 12/08/2016 200000 200000 200000 100 Yes 2017 Monteswar P.S. house at Pursuri village Constn.. of concrete road from Bindu Ghosh house to Haru Ghosh 2016 - Executive Officer, 7 C- 2043/DP 07/09/2016 150000 150000 150000 100 Yes house at Goalbari villlage at 2017 Monteswar P.S. Mamudpur G.P 167 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn. of Concrete Rd. from 2016 - Executive Officer, 8 Pucca Rd. near Madra F.P. School 2182/DP 20/09/2016 250000 250000 250000 100 Yes 2017 Purbasthali- I P.S. to P.C. das house Asset Handover Constn. of CC Rd. from Report Wanting as 2016 - Executive Officer, 9 Brahamani Tala to Amal 2259/DP 26/09/2016 200000 178046 178046 100 Yes per the Clause No. 8 2017 Purbasthali- I P.S. Sammadar house under updated BEUP Constn. of CC Road from Dwaiper Guidelines 2019 2016 - Executive Officer, 10 Math Primary School to B. Deys 2259/DP 26/09/2016 200000 157580 157580 100 Yes 2017 Purbasthali- I P.S. house Constn. of CC Road from Hachai 2016 - Executive Officer, 11 Sks house to Salamat Sks house of 2259/DP 26/09/2016 400000 400000 400000 100 Yes 2017 Purbasthali- II P.S. Masjid Asset Handover Constn. of CC Road from Report Received as 2016 - Executive Officer, 12 Sardanga Srikanta Das house to 2259/DP 26/09/2016 200000 200000 200000 100 Yes per the Clause No. 8 2017 Purbasthali- II P.S. H.Das house under updated BEUP Guidelines 2019 Constn. of CC Road from Khanpur 2016 - Executive Officer, 13 Masjid to Mehar Ali Sks house of 2259/DP 26/09/2016 350000 350000 350000 100 Yes 2017 Purbasthali- II P.S. Pilla G.P. Asset Handover Constn. of CC Road Kasthali Report Wanting as 2016 - Executive Officer, 14 Bazar to Suku Sks house near 2259/DP 26/09/2016 400000 400000 400000 100 Yes per the Clause No. 8 2017 Purbasthali- II P.S. Kasthali Khalpara under updated BEUP Guidelines 2019

168 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Asset Handover Constn. of Concrete road from Report Wanting as 2016 - Executive Officer, 15 Kuchya Jalpara to Aswathatala to 654/DP 01/03/2017 250000 250000 250000 100 Yes per the Clause No. 8 2017 Purbasthali- I P.S. M. Majhi house under updated BEUP Guidelines 2019 Constn. of Concrete road from 2016 - Executive Officer, 16 Pakka Road near Simla F.P. 654/DP 01/03/2017 300000 300000 300000 100 Yes 2017 Purbasthali- II P.S. School to Uttar Sajiara Bridge

Constn. of Concrete road from 2016 - Executive Officer, 17 654/DP 01/03/2017 300000 300000 300000 100 Yes Pakka Road to Pratima Das house 2017 Purbasthali- II P.S.

Constn. of Concrete Road from 2016 - Executive Officer, 18 Rahamattullah to Atab Sks Shop at 654/DP 01/03/2017 300000 300000 300000 100 Yes Asset Handover 2017 Purbasthali- II P.S. Harishpur Report Received as per the Clause No. 8 Constn. of Concrete road from 2016 - Executive Officer, under updated BEUP 19 Thandu Sks house to Hamed Ali 654/D{ 01/03/2017 200000 200000 200000 100 Yes 2017 Purbasthali- II P.S. Guidelines 2019 Sks house

Constn. of Jhama Moorum road 2016 - Executive Officer, 20 from Nawpara Pakka Rastato 654/DP 01/03/2017 250000 250000 250000 100 Yes 2017 Purbasthali- II P.S. Harekrishnapur F.P. School

Constn. of Concrete road from 2016 - Executive Officer, 21 654/DP 01/03/2017 200000 200000 200000 100 Yes Atul Sks house to Akai Sks house 2017 Purbasthali- II P.S.

169 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Repair of Black Top road Dakshin 2016 - Executive Officer, Asset Handover 22 Ghosh Para Harimandir to 1389/DP 05/05/2017 400000 400000 400000 100 Yes 2017 Purbasthali- II P.S. Report Received as Patulia G.P. per the Clause No. 8 Repair of Black Top Road from under updated BEUP 2016 - Executive Officer, 23 Parulia Bus Stop to Parulia Park 1389/DP 05/05/2017 250000 250000 250000 100 Yes Guidelines 2019 2017 Purbasthali- II P.S. with small culvertof Kalekhanala

Constn. of atchala at Jhawdanga 2016 - Executive Officer, 24 1484/DP 19/05/2017 100000 100000 100000 100 Yes Dakshin Para of Jhawdanga G.P. 2017 Purbasthali- II P.S. Asset Handover Report Wanting as Constn. of atchala at Jhawdanga 2016 - Executive Officer, 25 1484/DP 19/05/2017 100000 100000 100000 100 Yes per the Clause No. 8 Dutta Para of Jhawdanga G.P. 2017 Purbasthali- II P.S. under updated BEUP Guidelines 2019 Constn. of atchala at Sarishgram 2016 - Executive Officer, 26 1484/DP 19/05/2017 100000 100000 100000 100 Yes of Jhawdanga G.P. 2017 Purbasthali- II P.S.

Constn.. of Ghat Naopara Panfala pukur with guardwall of 2016 - Executive Officer, 27 C-3272/DP 21/12/2018 250000 249625 249625 100 Yes Mukshimpara G.P. under 2017 Purbasthali- II P.S. Asset Handover Purbasthali-II P.S. Report Received as Total 6000000 5934873 5934873 per the Clause No. 8 under updated BEUP Constn. of Concrete road 2017 - Executive Officer, Guidelines 2019 28 2570/DP 18/09/2017 200000 200000 200000 100 Yes Barorpara village of Mukshimpara 2018 Purbasthali- II P.S. 170 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Constn. of Concrete road Paschim Asset Handover Report Tamaghata from J.Krtaniya 2017 - Executive Officer, Received as per the Clause 29 2570/DP 18/09/2017 175000 175000 175000 100 Yes houseT. Sarkar house of Majda 2018 Purbasthali- II P.S. No. 8 under updated BEUP G.P. Guidelines 2019 Constn. of Drain from Saper Asset Handover Report 2017 - Executive Officer, Wanting as per the Clause 30 Khans house to Surat Alis house 2570/DP 18/09/2017 200000 197635 197635 100 Yes 2018 Purbasthali- II P.S. No. 8 under updated BEUP of Purbasthali house Guidelines 2019

Constn. of Purba Atpara Mooram Asset Handover Report 2017 - Executive Officer, Received as per the Clause 31 Road by Jhama Bads and moorum 2570/DP 18/09/2017 250000 247491 247491 100 Yes 2018 Purbasthali- II P.S. No. 8 under updated BEUP Majhida G.P. Guidelines 2019

Constn. of concrete road from M. Asset Handover Report 2017 - Executive Officer, Wanting as per the Clause 32 Sks house to s. Sks house of 2570/DP 18/09/2017 200000 200000 200000 100 Yes 2018 Purbasthali- II P.S. No. 8 under updated BEUP Purbasthali G.P. Guidelines 2019

Constn. of Concrete road from K. 2017 - Executive Officer, 33 2570/DP 18/09/2017 125000 125000 125000 100 Yes Biswas house to S. Mondal house 2018 Purbasthali- II P.S.

Constn. of Concrete road from G. Asset Handover Report 2017 - Executive Officer, Received as per the Clause 34 Mondals house to Durga Mandap 2570/DP 18/09/2017 200000 200000 200000 100 Yes 2018 Purbasthali- II P.S. No. 8 under updated BEUP of Mukshimpara Guidelines 2019

Constn. of concrete road from 2017 - Executive Officer, 35 Fakir Sks house to Ekai Sks 2570/DP 18/09/2017 200000 200000 200000 100 Yes 2018 Purbasthali- II P.S. house 171 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn. of concrete road from 2017 - Executive Officer, 36 Bakultala to Natun Laxmipur 2570/DP 18/09/2017 200000 200000 200000 100 Yes 2018 Purbasthali- II P.S. Majhida Constn. of Concrete road Kaibati 2017 - Executive Officer, 37 Dhalai Panchkorais Banshtala 2570/DP 18/09/2017 250000 250000 250000 100 Yes 2018 Purbasthali- II P.S. towards Makshimpara

Constn. of Concrete road from 2017 - Executive Officer, 38 Dwan High School to village of 2824/DP 06/11/2017 100000 100000 100000 100 Yes 2018 Monteswar P.S. G.P. Asset Handover Constn. of Concrete Drain from Report Received as 2017 - Executive Officer, 39 Golam Mortajas Khamar house to 2824/DP 06/11/2017 200000 200000 200000 100 Yes per the Clause No. 8 2018 Monteswar P.S. near Kandar of Putsuri G.P. under update BEUP Guidelines 2019 Constn. of Concrete Road from 2017 - Executive Officer, 40 near Joy Ghosh house to 2824/DP 06/11/2017 300000 288298 288298 100 Yes 2018 Monteswar P.S. Annapurnatala of Mamudpur G.P.

Constn. of concrete road from 2017 - Executive Officer, 41 Mujaharnagar Masjid to ICDS 2824/DP 06/11/2017 100000 100000 100000 100 Yes 2018 Monteswar P.S. Centre of Putsuri G.P.

Constn. of Concrete Road from 2017 - Executive Officer, 42 Samashpur Jogadhatala to Milan 2824/DP 06/11/2017 150000 143877 143877 100 Yes 2018 Monteswar P.S. Mondal house of Bamunpara G.P.

172 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Constn. of Concrete road from 2017 - Executive Officer, 43 Sudpur U. Ghosh house to R. 3066/DP 23/11/2017 200000 200000 200000 100 Yes 2018 Purbasthali- I P.S. Das house of Dogachia Constn. of Concrete Road from Bhandartikuri G,Debnath 2017 - Executive Officer, 44 3066/DP 23/11/2017 150000 149925 149925 100 Yes house to Ganga Ghat Road of 2018 Purbasthali- I P.S. Jahannagar Constn. of Concrete road from 2017 - Executive Officer, 45 Madra R. Mazumdar house to 3066/DP 23/11/2017 75000 75000 75000 100 Yes Asset Handover 2018 Purbasthali- I P.S. moram road of Dogachia G.P. Report Wanting as per the Clause No. 8 Constn. of Concrete road from under updated BEUP 2017 - Executive Officer, 46 Golahat G.Kar house to R. 3066/DP 23/11/2017 100000 99920 99920 100 Yes Guidelines 2019 2018 Purbasthali- I P.S. Debnath house of Jahanagar

Constn. of Concrete Road from 2017 - Executive Officer, 47 behind of A. Debnath house to 3066/DP 23/11/2017 200000 199940 199940 100 Yes 2018 Purbasthali- I P.S. Paschimpara Kirtan Math

Constn. of Concrete road from 2017 - Executive Officer, 48 Belgram M. Das house to P. 3066/DP 23/11/2017 200000 200000 200000 100 Yes 2018 Purbasthali- I P.S. Das house of Dogachia Asset Handover Constn. of concrete Road Report Received as 2017 - Executive Officer, 49 Khondekarpara of Nimodaha 3066/DP 23/11/2017 300000 299839 299839 100 Yes per the Clause No. 8 2018 Purbasthali- II P.S. G.P. under update BEUP Guidelines 2019 173 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Asset Handover Report Constn. of Atchala at Kashipur 2017 - Executive Officer, Wanting as per the Clause 50 3066/DP 23/11/2017 200000 200000 200000 100 Yes village of Jhaodanga 2018 Purbasthali- II P.S. No. 8 under updated BEUP Guidelines 2019 Asset Handover Report Constn. of Concrete Drain 2017 - Executive Officer, Received as per the Clause 51 3066/DP 23/11/2017 100000 100000 100000 100 Yes Singhari of G.P. 2018 Purbasthali- II P.S. No. 8 under updated BEUP Guidelines 2019 Asset Handover Report Constn. of Concrete Road Near 2017 - Executive Officer, Wanting as per the Clause 52 3066/DP 23/11/2017 175000 175000 175000 100 Yes G. Mukherjee Pally Palashpuli 2018 Purbasthali- II P.S. No. 8 under updated BEUP Guidelines 2019 Constn. of Road from Lohana 2017 - Executive Officer, 53 Primary School Gate towards 3281/DP 13/12/2017 150000 150000 150000 100 Yes 2018 Monteswar P.S. Sastipukur of Bamunpara Constn. of Metal Road from 2017 - Executive Officer, 54 Babuidanga Purbapara to 3382/DP 28/12/2017 1000000 973470 973470 100 Yes 2018 Purbasthali- II P.S. Garbitala Constn. of Atchala at Nimdaha 2017 - Executive Officer, 55 64/DP 09/01/2018 100000 100000 100000 100 Yes Mahishya Para of Nimdaha G.P. 2018 Purbasthali- II P.S. Asset Handover Report Received as per the Clause Constn. of Atchala Mouza No. 8 under updated BEUP 2017 - Executive Officer, 56 Karishnabati, Plot No. 273 of 64/DP 09/01/2018 200000 200000 200000 100 Yes Guidelines 2019 2018 Purbasthali- II P.S. Pila G.P. Total 6000000 5950395 5950395 Constn.. of concrete road from Purba Para Durgamandir 2018 - Executive Officer, 57 towards Bama Charan Mondal 677/DP 27/02/2019 100000 99320 99320 100 Yes 2019 Purbasthali- II P.S. house under Mukshimpara G.P. within Purbasthali-II P.S. 174 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn.. of CC road from the house of Mantu Asset Handover Report 2018 - Executive Officer, 58 Seikh house of Kalim Seikh under 677/DP 27/02/2019 250000 249800 249800 100 Yes Wanting as per the Clause 2019 Purbasthali- II P.S. No. 8 under updated BEUP Purbasthali G.P. within Purbasthali-II P.S. Guidelines 2019 Constn.. of concrete road from Dilip Kar 2018 - Executive Officer, 59 towards the house of Litan Das vill. under 677/DP 27/02/2019 200000 198540 198540 100 Yes 2019 Purbasthali- II P.S. Mukshimpara G.P. within Purbasthali-II P.S. Constn.. of concrete road from the house of 2018 - Executive Officer, 60 Dilip Bhumi towards late Binoy Bhumi under 677/DP 27/02/2019 200000 199200 199200 100 Yes 2019 Purbasthali- II P.S. Kalekkhanta-I G.P. within Purbasthali-II P.S. Asset Handover Report Constn.. of concrete road from the house of Received as per the Clause No. 8 under updated BEUP Patal Seikh towards the house of Kutubuddin 2018 - Executive Officer, 61 677/DP 27/02/2019 300000 298800 298800 100 Yes Guidelines 2019 Seikh under Nimdaha G.P. within 2019 Purbasthali- II P.S. Purbasthali-II P.S. Constn.. of concrete road from the house of Habul Mallick towards Bhasan Seikh house 2018 - Executive Officer, 62 677/DP 27/02/2019 300000 298050 298050 100 Yes of Faleya under Kalekhanta -I G.P. within 2019 Purbasthali- II P.S. Purbasthali-II P.S. Cost of brick solling road from house of Asset Handover Report 2018 - Executive Officer, 63 Pradip Bhowal towards Bhandertikuri station 3475/DP 11/09/2019 150000 128415 128415 100 Yes Wanting as per the Clause 2019 Purbasthali- I P.S. No. 8 under updated BEUP under Jahannagar G.P . Guidelines 2019 Constn.. of Atchala at Telinipara Sabuj Asset Handover Report 2018 - Executive Officer, 64 Sangha Club under Kalekhantala-II G.P. 081/DP 08/01/2020 175000 174913 174913 100 Yes Received as per the Clause 2019 Purbasthali- II P.S. No. 8 under updated BEUP within Purbasthali-II P.S. Guidelines 2019 Asset Handover Report Purchase of Multi GYM equipment for Patuli 2018 - Secy. Patuli 65 755/DP 28/02/2020 174900 174900 174900 100 Yes Wanting as per the Clause Sporting Club within Purbasthali-II P.S. 2019 Sporting Club No. 8 under updated BEUP Guidelines 2019 175 Sanction UC Asset Sl. Date of Amount Amount Amount Physical Name of the Scheme Year Order Executing Agency Submitt Handover No. Sanction Sanction Released Utilized Progress No ed Status Constn. of Atchala near the house of Biswanath 2018 - Executive Officer, 66 Sanyal under Pilla G.P. within Purbasthali-II 081/DP 08/01/2020 200000 199910 199910 100 Yes 2019 Purbasthali- II P.S. P.S. Constn.. of Atchala near the house of Jadab 2018 - Executive Officer, 67 081/DP 08/01/2020 200000 198800 198800 100 Yes Sadhu under Pila G.P. within Purbasthali-II P.S. 2019 Purbasthali- II P.S. Constn.. of Guard wall with earth filling near 2018 - Executive Officer, 68 Pirtala pukur par under Majida G.P. within 081/DP 08/01/2020 250000 248250 248250 100 Yes 2019 Purbasthali- II P.S. Purbasthali -II P.S. Constn.. of atchala at Dasghariya para near the 2018 - Executive Officer, Asset Handover 69 081/DP 08/01/2020 175000 174860 174860 100 Yes house of Janardhan Saha vill-Parulia, dag-458 2019 Purbasthali- II P.S. Report Received as per the Clause Repairing with black stone and bitumin from 2018 - Executive Officer, No. 8 under 70 Parulia Bazar towards Parulia KK H.S. under 526/DP 07/02/2020 450000 450000 450000 100 Yes 2019 Purbasthali- II P.S. updated BEUP Kalekhantala Guidelines 2019 Constn.. of Atchala at Telinipara near Amar 2018 - Executive Officer, 71 Sangha Club Dag No. 13/439 under 754/DP 28/02/2020 175000 175000 175000 100 Yes 2019 Purbasthali- II P.S. Kalekhantala-II G.P. within Purbasthali-II P.S Constn.. of cement concrete road near Pukur Par 2018 - Executive Officer, 72 2220/DP 10/09/2020 199820 199820 199820 100 Yes under Putsuri G.P. within Monteswar P.S. 2019 Monteswar P.S. Constn.. of cement concrete road from sutra 2018 - Executive Officer, 73 paschimpara towards gobraghat under 2220/DP 10/09/2020 299940 299940 299940 100 Yes 2019 Monteswar P.S. Mamudpur G.P. within Monteswar P.S. Asset Handover Constn. of CC road from Chhoto Kalitala Report Wanting 2018 - Executive Officer, as per the Clause 74 towards east under Bamunpar G.P. within 3182/DP 03/12/2020 296400 296400 296400 100 Yes 2019 Monteswar P.S. No. 8 under Monteswar P.S. updated BEUP Guidelines 2019 Total 4096060 4064918 4064918 Grand Total 16096060 15950186 15950186 176 ONGOING SCHEMES

177 PRADIP KUMAR SAHA, HON'BLE MLA 269 PURBASTHALI UTTAR A.C.

Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month of No. Sanction Sanction Agency Released Utilized Progress No ted of June July Constn. of Atchala at 100% work 100% work Gangapur Bakultala under 2018 - Executive Officer, completed, UC completed. UC 1 081/DP 08/01/2020 250000 250000 187500 75 Yes Jhowdanga G.P.within 2019 Purbasthali- II P.S. will be submitted will be submitted Purbasthali-II P.S. on 28/06/2021 02/08/2021 Purchase of Multi GYM 100% Work Procurement equipment for Narayanpur 2018 - Secy. Narayanpur completed. 2 665/DP 18/02/2020 174900 131175 131175 75 Yes process not Evening Star Club within 2019 Evening Star Club Balance fund to started. Purbasthali-II P.S. be released. Constn. of atchala near the 100% work 100% Work house of Puru Seikh completed, Final 2018 - Executive Officer, completed. 3 (Charbattala) paschim under 936/DP 13/03/2020 200000 199000 149925 75 Yes UC will be 2019 Purbasthali- II P.S. Balance fund to Majida withhin Purbasthali-II submitted on be released. P.S. 28/06/2021 100% work Constn. of atchala at Gagra 100% Work completed, Final (Dag-330 Mouza-Gogra, Jl.- 2018 - Executive Officer, completed. 4 1457/DP 21/05/2020 199860 199860 149895 75 Yes UC will be 121) under Dogachia G.P. 2019 Purbasthali- I P.S. Balance fund to submitted on withhin Purbasthali-I P.S. be released. 25/06/2021 Constn. of atchala at sonakuri 100% work 100% Work (Dag-1379, 1719 Mouza- completed, Final 2018 - Executive Officer, completed. 5 Dogachia, Jl.-107 under 1457/DP 21/05/2020 199860 199860 149895 75 Yes UC will be 2019 Purbasthali- I P.S. Balance fund to Dogachia G.P. withhin submitted on be released. Purbasthali-I P.S. 25/06/2021

178 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month No. Order No Sanction Sanction Agency Released Utilized Progress ted of June of July

Constn. of waiting room for Work not started. tourist on the land of 2018 - Secy. Kasthasali Not started due 6 2537/DP 30/09/2020 300000 225000 0 0 No Amount will be Kasthasali Banabithi under 2019 Banabithi to land problem refund. Purbasthali

Constn. of CC Road from 100% work Executive 100% Work Madra Ratan Majumdar house completed, Final 2018 - Officer, completed. 7 to Moorum road under 2892/DP 04/11/2020 73687 73687 55266 75 Yes UC will be 2019 Purbasthali- I Balance fund to Dogachia G.P. within submitted on P.S. be released. Purbasthali-I p.S. 25/06/2021 100% work Constn. of CC roaad from Executive completed, Final 100% Work Golahat Natun Bazar towards 2018 - Officer, UC will be completed. 8 2892/DP 04/11/2020 245000 183750 183750 75 Yes Bagdebitala under Jahannagar 2019 Purbasthali- I submitted after Balance fund to G.P. within Purbasthali -I P.S. P.S. receiving of be released. balance fund 100% work Constn. of concrete Ghat of 100% work Executive completed, Final Jaruli Pukurpar near Putsuri 2018 - completed. UC 9 3182/DP 03/12/2020 197800 Officer, 148350 143850 75 Yes UC will be Bazar under Putsuri G.P. 2019 will be submitted Monteswar P.S. submitted on within Monteswar P.S. 06/08/2021 25/06/2021

1st Phase UC Purchase Library Book for the 2018 - H.M. Parulia KK will be submitted 10 Student of Parulia KK High 255/DP 25/01/2021 50000 37500 0 0 No 2019 High School end of June, School 2021

Total 1891107 1648182 1155756 179 Sanction UC Present Sl. Date of Amount Executing Amount Amount Physical Present Status for Name of the Scheme Year Order Submit Status for the No. Sanction Sanction Agency Released Utilized Progress the Month of June No ted Month of July

Purchase computer Materials 100% work H.M. Purchase completed, for the interest of the student 2019- 100% final UC will be completed, 11 3425/DP 21/12/2020 100000 Barapara F.P. 75000 75000 75 Yes of Barapara F.P. School 2020 submitted after receiving balance fund to School Mukshimpara G.P. of fund. be released

Executive 100% work Constn. of Krishak 100% work completed, 2019- Officer, Final UC will be completed, 12 Bishramagar at Babupara uttar 275/DP 25/01/2021 250000 187500 187500 75 Yes 2020 Purbasthali- II submitted after receiving balance fund to Jhadanga under Jhaudanga P.S. of balance fund be released

Executive 100% work Constn. of CC Road from 100% work completed, 2019- Officer, Final UC will be completed, 13 Dubrajpur Vill from house of 275/DP 25/01/2021 299820 224865 224863 75 No 2020 Purbasthali- II submitted after receiving balance fund to Amal Mistri P.S. of balance fund be released

Executive 100% work Constn. of CC Road from 100% work completed, 2019- Officer, Final UC will be completed, 14 Aynul House towards 275/DP 25/01/2021 249950 187463 187463 75 Yes 2020 Purbasthali- II submitted after receiving balance fund to Sabujsathi Club P.S. of balance fund be released

Constn. of CC Road from Executive 100% work completed, 100% work from the house of Uttam 2019- Officer, Final UC will be completed, 15 275/DP 25/01/2021 149880 112410 112410 75 Yes Mondal house of Sukumar 2020 Purbasthali- II submitted after receiving balance fund to Mondal P.S. of balance fund be released

180 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month of No. Sanction Sanction Agency Released Utilized Progress No ted of June July

100% work Executive 100% work Constn. of CC Road from House completed, Final 2019- Officer, UC will be completed, 16 of Jagadish Sarkar towards of 275/DP 25/01/2021 149925 112444 112444 75 Yes 2020 Purbasthali- II submitted after balance fund to be Kalo Tudu P.S. receiving of released balance fund 100% work Executive completed, Final 100% work Constn. of CC Road from Kanai 2019- Officer, UC will be completed, 17 275/DP 25/01/2021 99970 74977 74977 75 Yes Das house of Sunil Das 2020 Purbasthali- II submitted after balance fund to be P.S. receiving of released balance fund 100% work Executive 100% work Constn. of CC Road from completed, Final 2019- Officer, UC will be completed, 18 Rashid Mallik house to Mosa Sk 275/DP 25/01/2021 199840 149880 149880 75 Yes 2020 Purbasthali- II submitted after balance fund to be House P.S. receiving of released balance fund 100% work Executive completed, Final 100% work Constn. of Kitchen cum store 2019- Officer, UC will be completed, 19 275/DP 25/01/2021 250000 187500 187500 75 Yes for an oldage Home under Pilla 2020 Purbasthali- II submitted after balance fund to be P.S. receiving of released balance fund 100% work Executive 100% work Constn. of Krishak Bishramagar completed, Final 2019- Officer, UC will be completed, 20 village Belgachi Raghabati 275/DP 25/01/2021 200000 150000 150000 75 Yes 2020 Purbasthali- II submitted after balance fund to be under Kalekhantala P.S. receiving of released balance fund 181 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month of No. Sanction Sanction Agency Released Utilized Progress No ted of June July

100% work Executive completed, Final Constn. of CC Drain from 100% work 2019- Officer, UC will be 21 Akshay Banerjee house of 275/DP 25/01/2021 99970 74977 74977 75 Yes completed, balance 2020 Purbasthali- II submitted after Rakesh Mallik fund to be released P.S. receiving of balance fund 100% work Executive completed, Final Constn. of Krishak Bishramagar 100% work 2019- Officer, UC will be 22 village Daspara Harijan under 275/DP 25/01/2021 200000 150000 150000 75 Yes completed, balance 2020 Purbasthali- II submitted after Kalimatapith fund to be released P.S. receiving of balance fund 100% work Executive completed, Final Constn. of Krishak Bishramagar 100% work 2019- Officer, UC will be 23 at Madhupur Rajowarpara 275/DP 25/01/2021 200000 150000 150000 75 Yes completed, balance 2020 Purbasthali- II submitted after under Nimdaha fund to be released P.S. receiving of balance fund 100% work Executive completed, Final 100% work Constn. of Krishak Bishramagar 2019- Officer, UC will be 24 275/DP 25/01/2021 200000 150000 150000 75 Yes completed, balance submitted after Dag No1840 villge Feleya 2020 Purbasthali- II fund to be released P.S. receiving of balance fund Scheme has Changed the Executive Constn. of Krishak Bishramagar changed by scheme as sl. No. 2019- Officer, Hon'ble MLA and 18, refund notesheet 25 Vill Sardanga Adibasipara 275/DP 25/01/2021 200000 150000 0 0 No 2020 Purbasthali- II sanction amount approved but under Kalekhantala P.S. will be refunded pending at a/c very shortly. section. 182 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month of for the Month No. Sanction Sanction Agency Released Utilized Progress No ted June of July

Executive 100% work 100% work Constn. of krishak Bisrammagar 2019- Officer, completed, Final UC completed, 26 vill Belgachi Majherpara near 275/DP 25/01/2021 200000 150000 150000 75 Yes will be submitted 2020 Purbasthali- II balance fund to jawar Bari after receiving of P.S. balance fund be released

Executive 100% work 100% work Renovation of Work of Atchala 2019- Officer, completed, Final UC completed, 27 at Baghnachra Rajoarpara under 275/DP 25/01/2021 100000 75000 75000 75 Yes will be submitted 2020 Purbasthali- II balance fund to Kalekhantala after receiving of P.S. balance fund be released

Executive 100% work 100% work Constn. of Krishak Bishramagar 2019- Officer, completed, Final UC completed, 28 village Kamalpur Lakshmi 275/DP 25/01/2021 200000 150000 150000 75 Yes will be submitted 2020 Purbasthali- II balance fund to Narayantala under Majhida after receiving of P.S. balance fund be released 100% work Executive Constn. of Cement Concrete Work completed, 1st completed. UC 2019- Officer, Phase UC will be 29 road from the Girinagar Masjid 604/DP 10/02/2021 99920 74940 0 0 No will be 2020 Monteswar submitted by to Firoj Sk Vill submitted P.S. 25/06/2021 02/08/2021 100% work Constn. of Cement Concrete Executive Work completed, 1st completed. UC road from the house of Dukhu 2019- Officer, Phase UC will be 30 604/DP 10/02/2021 299820 224865 0 0 No will be Sarkar to the Shop fo Abbas 2020 Monteswar submitted by submitted Khan P.S. 25/06/2021 02/08/2021 183 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month of for the Month of No. Sanction Sanction Agency Released Utilized Progress No ted June July

Constn. of Concrete Cement 100% work Executive Work completed, 1st Road from the house of Jamal 2019- Phase UC will be completed. UC 31 604/DP 10/02/2021 299760 Officer, 224820 0 0 No Mondal to the shop of Asai sk 2020 submitted by will be submitted Monteswar P.S. vill 25/06/2021 02/08/2021

Executive 100% work 100% work Constn. of Concrete Road near 2019- Officer, completed, Final UC completed, 32 the house of Jahar Ghosh to 647/DP 12/02/2021 150000 112500 112500 75 Yes will be submitted 2020 Purbasthali- II balance fund to be Taru Biswas after receiving of P.S. balance fund released

Constn. of CC Road near the Executive 100% work 100% work house of Mir Dalo towards 2019- Officer, completed, Final UC completed. 75% 33 647/DP 12/02/2021 150000 112500 0 0 No will be submitted Sadhan Hazra house under Purbasthali- II UC already 2020 after receiving of Mukshimpara G.P. P.S. balance fund submitted.

Executive 100% work 100% work Constn. of Cow catcher and 2019- Officer, completed, Final UC completed. 75% 34 Dumoing Room at Purbasthali 771/DP 21/02/2021 200000 150000 150000 75 Yes will be submitted 2020 Purbasthali- II UC already BPHC Purbasthali-II PS after receiving of P.S. balance fund submitted. Construction of concrete road 100% work from the house of Sanatan Executive 2019- completed. UC 35 Ghosh towards the house of 2782/DP 30/06/2021 299820 Officer, 224865 0 0 No Nil 2020 will be submitted Putul Ghosh at Mamudpur-II Monteswar P.S. 02/08/2021 G.P. Total 4848675 3636506 2624514 184 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month of for the Month No. Sanction Sanction Agency Released Utilized Progress No ted June of July

Constn. of Road from Shop of Executive 100% work 100% work Biltu Sekh towards 2020- Officer, completed, Final UC completed, 36 649/DP 12/02/2021 250000 187500 187500 75 Yes will be submitted Baithakkana Sekhpara at Purbasthali- II balance fund to 2021 after receiving of Hatsuri P.S. balance fund be released

Executive 100% work 100% work Constn. of Concrete Rd from 2020- Officer, completed, Final UC completed, 37 house of Samsuddin Sekh 649/DP 12/02/2021 199960 149970 149970 75 Yes will be submitted 2021 Purbasthali- II balance fund to towards Chuppi Kabar Khana after receiving of P.S. balance fund be released

Executive 100% work 100% work Constn. of Concrete Rd from 2020- Officer, completed, Final UC completed, 38 house of Kanai Mondal towards 649/DP 12/02/2021 150000 112500 112500 75 Yes will be submitted 2021 Purbasthali- II balance fund to house of Chintaharan Roy after receiving of P.S. balance fund be released

Executive 100% work 100% work Constn. of Concrete Rd from 2020- Officer, completed, Final UC completed, 39 house of Shisir Dasl towards 649/DP 12/02/2021 99950 74962 74962 75 Yes will be submitted 2021 Purbasthali- II balance fund to house of Kania Das after receiving of P.S. balance fund be released

Executive 100% work 100% work Constn. of Concrete Road from 2020- Officer, completed, Final UC completed, 40 Adar Sks House of Buro Sekh 649/DP 12/02/2021 199960 149970 149970 75 Yes will be submitted 2021 Purbasthali- II balance fund to house at Kasthasali Char after receiving of P.S. balance fund be released 185 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month of for the Month No. Sanction Sanction Agency Released Utilized Progress No ted June of July

Executive 100% work 100% work Constn. of Concrete Road 2020- Officer, completed, Final UC completed, 41 from Bikash Mondal house to 649/DP 12/02/2021 200000 150000 150000 75 Yes will be submitted 2021 Purbasthali- II balance fund to Sufal Mondal Houseat Moyil after receiving of P.S. balance fund be released Executive 100% work 100% work Constn. of Concrete road from 2020- Officer, completed, Final UC completed, 42 Faijul Stall to the house of 649/DP 12/02/2021 300000 225000 225000 75 Yes will be submitted 2021 Purbasthali- II balance fund to Sirajul Sekh after receiving of P.S. balance fund be released Constn. of concrete Road from Executive 100% work 100% work Kamalnagar Metal Road 2020- Officer, completed, Final UC completed, 43 649/DP 12/02/2021 250000 187500 187500 75 Yes will be submitted towards Guru Charan Mandal Purbasthali- II balance fund to 2021 after receiving of under Majhida P.S. balance fund be released Executive 100% work 100% work Constn. of Concrete Road 2020- Officer, completed, Final UC completed, 44 from Swapan Das house to 649/DP 12/02/2021 199960 149970 149970 75 Yes will be submitted 2021 Purbasthali- II balance fund to Lolit Mohan Das at Sardanga after receiving of P.S. balance fund be released Constn. of Concrete Road Executive 100% work 100% work from the house of Yusuf 2020- Officer, completed, Final UC completed, 45 649/DP 12/02/2021 300000 225000 225000 75 Yes will be submitted Mollah towards the house of Purbasthali- II balance fund to 2021 after receiving of Hamed Ali Mollah P.S. balance fund be released Executive Constn. of Jhowdanga daspara 2020- Officer, Work just 46 krishak Bishramagar under 2765/DP 30/06/2021 200000 150000 0 0 No Nil 2021 Purbasthali- II started. Jhowdanga P.S. 186 Present Sanction Present Status Sl. Date of Amount Executing Amount Amount Physical UC Status for Name of the Scheme Year Order for the Month No. Sanction Sanction Agency Released Utilized Progress Submitted the Month of No of July June Renovation work on tchala at 2020- Executive Officer, Work just 47 2765/DP 30/06/2021 150000 112500 0 0 No Nil Singhari Purba Para 2021 Purbasthali- II P.S. started.

Constn. of krishak 2020- Executive Officer, Work just 48 2765/DP 30/06/2021 200000 150000 0 0 No Nil Bishramagar at daspara 2021 Purbasthali- II P.S. started.

Set up high mast light 2020- Executive Officer, Work just 49 2765/DP 30/06/2021 300000 225000 0 0 No Nil Teliopara 2021 Purbasthali- II P.S. started.

Constn. of krishak 2020- Executive Officer, Work just 50 Bishramagar at Mahipara 2765/DP 30/06/2021 200000 225000 0 0 No Nil 2021 Purbasthali- II P.S. started. Dafarpota

Constn. of krishak 2020- Executive Officer, Work just 51 Bishramagar shyambati under 2765/DP 30/06/2021 200000 150000 0 0 No Nil 2021 Purbasthali- II P.S. started. Kalekhanta-II G.P.

Krishak Bishramagar at 2020- Executive Officer, Work just 52 Baidyapur Rajbanshipar under 2765/DP 30/06/2021 199960 149970 0 0 No Nil 2021 Purbasthali- II P.S. started. kalekhantala-II G.P.

Constn. of sharmik 2020- Executive Officer, Work just 53 2765/DP 30/06/2021 200000 150000 0 0 No Nil Bishramgar at Chhatni 2021 Purbasthali- II P.S. started.

Renovation work for 2020- Executive Officer, Work just 54 2765/DP 30/06/2021 150000 112500 0 0 No Nil vivekananda club 2021 Purbasthali- II P.S. started. Total 3949790 3037342 1612372 Grand Total 10689572 8322030 5242642 187 Hon’ble M.L.A. Shri Rabindranath Chatterjee HON'BLE MLA 270 KATWA A.C.

188 COMPLETED SCHEMES

189 RABINDRANATH CHATTERJEE, HON'BLE MLA 270 KATWA A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn. of High Drainat Choto 2016 - Executive Officer, 1 Kulgachi beside house of P.Hazra 2046/DP 07/09/2016 200000 136768 136768 100 Yes 2017 Katwa- II P.S. Culvert Upgradation Jhama Moorum Road 2016 - Executive Officer, 2 at Chandpur near house of Ajmat 2046/DP 07/09/2016 100000 100000 100000 100 Yes 2017 Katwa- II P.S. Skto Lasker Sk. Constn. of RCC drain at 2016 - Executive Officer, 3 Natungram near Bituminous road 2046/DP 07/09/2016 150000 150000 150000 100 Yes 2017 Katwa- II P.S. upto house of Anwar Sk Asset Handover Constn. of Bathing Ghat on the 2016 - Executive Officer, Report Received as 4 Baram Pukurat Gourdanga of 2046/DP 07/09/2016 100000 100000 100000 100 Yes 2017 Katwa- II P.S. per the Clause No. 8 Singhi G.P. under updated BEUP Guidelines 2019 Constn. of Boundary Wall of the 2016 - Executive Officer, 5 Kabi Sekhar Sri Kalidas Heritage 2046/DP 07/09/2016 150000 89493 89493 100 Yes 2017 Katwa- II P.S. house to Kauri Vill.

Constn. of CC Road at Kurchi 2016 - Executive Officer, 6 near house of Mihir Samanta upto 2046/DP 07/09/2016 100000 100000 100000 100 Yes 2017 Katwa- II P.S. house of M.Mondal Constn. of CC Road at Panjoa 2016 - Executive Officer, 7 near house of Kalosona Para upto 2046/DP 07/09/2016 100000 100000 100000 100 Yes 2017 Katwa- II P.S. house of Natun Majhi 190 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Upgradation of Jhama Moorum 2016 - Executive Officer, 8 Road at Singhi near house of 2046/DP 07/09/2016 100000 100000 100000 100 Yes 2017 Katwa- II P.S. B.Santra

Const of Bathing Ghaton the 2016 - Executive Officer, 9 Bakul Garh Pukur at Choto 2046/DP 07/09/2016 100000 100000 100000 100 Yes 2017 Katwa- II P.S. Meyagachi

Constn. of CC Road and drain 2016 - Executive Officer, 10 2046/DP 07/09/2016 500000 325277 325277 100 Yes at Kalikapur beside Old Kalna 2017 Katwa- II P.S. Asset Handover Constn. of Guard Wall Report Received as per 2016 - Executive Officer, 11 Chotokulgachi Suhasini Sishu 2046/DP 07/09/2016 150000 150000 150000 100 Yes the Clause No. 8 under 2017 Katwa- II P.S. Sikhsa Kendra of Gazipur updated BEUP Guidelines 2019 Constn. of Guard Wall and bathing Ghat at Mustuli 2016 - Executive Officer, 12 2046/DP 07/09/2016 200000 137900 137900 100 Yes Moyragarh Pukur of 2017 Katwa- II P.S. Jaganandapur Constn. of Guard Wall and 2016 - Executive Officer, 13 Bathing Ghat at Baro Kangi 2046/DP 07/09/2016 200000 136060 136060 100 Yes 2017 Katwa- II P.S. Dighi of Jaganandapur

Constn. of CC Road Ghumuria 2016 - Executive Officer, 14 Near house of Hamijul Mollah 2046/DP 07/09/2016 100000 100000 100000 100 Yes 2017 Katwa- II P.S. upto Masjid 191 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed Constn. of CC Road at 2016 - Executive Officer, 15 Sutragachi beside house of S. 2046/DP 07/09/2016 200000 136278 136278 100 Yes 2017 Katwa- II P.S. Mondal to K. Majhi Constn. of CC Road at Purba 2016 - Executive Officer, 16 Multi Near the house of 2046/DP 07/09/2016 250000 138086 138086 100 Yes 2017 Katwa- II P.S. Sahidulla Mollah to Kalapukur Constn. of CC Road at Natun 2016 - Executive Officer, 17 Gram near the house of Abul 2046/DP 07/09/2016 250000 191187 191187 100 Yes 2017 Katwa- II P.S. Mallick Upgradation of Jhama moram road at karajgram near house of 2016 - Executive Officer, 18 937/DP 27/03/2017 200000 200000 200000 100 Yes A. Pan upto B. Mondal of 2017 Katwa- I P.S. Asset Handover Karajgram G.P. Report Received as per Constn. of C C road at the Clause No. 8 under Karajgram near Jora Dharmatala 2016 - Executive Officer, updated BEUP 19 937/DP 27/03/2017 200000 200000 200000 100 Yes to Kauri Katwa road of 2017 Katwa- I P.S. Guidelines 2019 Karajgram G.P.

Constn. of C C Road and Drain 2016 - Executive Officer, 20 at Haripur from H. Sk. Shop upto 937/DP 27/03/2017 250000 250000 250000 100 Yes 2017 Katwa- I P.S. M.R. Shop

Constn. of C C Road at Mera 2016 - Executive Officer, 21 Near house of J.Sk upto house 937/DP 27/03/2017 100000 100000 100000 100 Yes 2017 Katwa- I P.S. upto L. Sk of Sudpur

192 Sanction UC Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit Asset Handover Status No. Sanction Sanction Agency Released Utilized Progress No ted

Constn. of Bathing Ghat North side to Executive 2016 - 22 Dighir Pukur at Khejurihi Sardar Para 937/DP 27/03/2017 125000 Officer, 125000 125000 100 Yes 2017 Khejurdihi G.P. Katwa- I P.S.

Constn. of Bathing Ghat Hatgacha Executive 2016 - 23 Pukur at Bunidighi of 937/DP 27/03/2017 125000 Officer, 125000 125000 100 Yes 2017 Khejurdihi G.P. Katwa- I P.S. Constn. of C.C. Road at Panuhat Executive Baidyapara near house of S. Roy 2016 - 24 937/DP 27/03/2017 125000 Officer, 125000 125000 100 Yes upto house of Sudev Halder of 2017 Katwa- I P.S. Khajurdihi G.P. Asset Handover Report Constn. of C.C. road at Sudpur Executive Received as per the Bhattarchya Para to Radha 2016 - 25 937/DP 27/03/2017 200000 Officer, 200000 200000 100 Yes Clause No. 8 under Karishnapur Bagdi Para of Sudpur 2017 Katwa- I P.S. updated BEUP Guidelines G.P. 2019 Constn. of C.C. Road at Tikarkhaji Executive 2016 - 26 near the Laxmi Mandir upto behind 937/DP 27/03/2017 200000 Officer, 200000 200000 100 Yes 2017 the narayan Mandir of Sudpur G.P. Katwa- I P.S.

Constn. of Community Centre at Executive 2016 - 27 Auria on the K. Bharati Melatala of 937/DP 27/03/2017 200000 Officer, 200000 200000 100 Yes 2017 Palason G.P. Katwa- II P.S.

Constn. of C.C. Road at Ronda near Executive 2016 - 28 house of G.Ghosh upto ICDS 937/DP 27/03/2017 200000 Officer, 200000 200000 100 Yes 2017 Centreof Palason Katwa- II P.S. 193 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn. of Bathing Ghat on the Bara Executive 2016 - 29 Bandh Pukur at Auria of Palason 937/DP 27/03/2017 100000 Officer, 100000 100000 100 Yes 2017 G.P. Katwa- II P.S.

Constn. of drain at palikpara vill near Executive 2016 - 30 house of K. Sk. upto the house of M. 937/DP 27/03/2017 100000 Officer, 100000 100000 100 Yes 2017 Sk of Jagadanandapur Katwa- II P.S.

Constn. of Cremation 2nd unit at 2016 - Chairman, 31 1020/DP 03/04/2017 322000 322000 322000 100 Yes Katwa Burrning Ghat 2017 Katwa Muty.

Constn. of extn building at Katwa 2016 - Chairman, 32 Jhankar Ward No. 6 under Katwa 1959/DP 12/07/2017 150000 150000 150000 100 Yes Asset Handover 2017 Katwa Muty. Muty Report Received as per the Clause No. 8 Constn. of Extn Building at Youth 2016 - Chairman, under updated BEUP 33 Club Ward No. 17 under Katwa 1959/DP 12/07/2017 150000 150000 150000 100 Yes 2017 Katwa Muty. Guidelines 2019 Muty

Constn. of Gem Room at Jhankar 2016 - Chairman, 34 1959/DP 12/07/2017 178000 178000 178000 100 Yes Ward No6 under Katwa Muty 2017 Katwa Muty.

Total 5875000 5216049 5216049

Constn. of Concrete Drain at Majhari Executive 2017 - 35 Joghadya tala to Bamun Pukur of 2286/DP 18/08/2017 97010 Officer, 97010 97010 100 Yes 2018 Kauri G.P. Katwa- II P.S.

194 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Constn. of CC Road at Panjoa 2017 - Executive Officer, 36 Apanjan Club to T.Bandhus house of 2286/DP 18/08/2017 146996 146996 146996 100 Yes 2018 Katwa- II P.S. Kauri G.P.

Constn. of CC Road at Akhra Sheial 2017 - Executive Officer, 37 2286/DP 18/08/2017 241480 241480 241480 100 Yes Mara Para of Jaganandapur G.P. 2018 Katwa- II P.S.

Constn. of CC Road at Dona Purba 2017 - Executive Officer, 38 Para Durga Mandir to K. Kundas 2286/DP 18/08/2017 148516 148516 148516 100 Yes 2018 Katwa- II P.S. house of Kuri G.P. Asset Handover Report Received as Constn. of CC Road at Ekdela 2017 - Executive Officer, per the Clause No. 8 39 2286/DP 18/08/2017 250000 245000 245000 100 Yes Jogadhya Tala of Jaganandapur G.P. 2018 Katwa- II P.S. under updated BEUP Guidelines 2019 Constn.. of CC road at Deriyapur 2017 - Executive Officer, 40 from the house of B. Kunda to 2461/DP 05/09/2017 250000 242424 242424 100 Yes 2018 Katwa- II P.S. Primary School

Constn. of CC Road at Agradwip 2017 - Executive Officer, 41 Sarawari from ICDS Centre to 2461/DP 05/09/2017 500000 500000 500000 100 Yes 2018 Katwa- II P.S. Beltala of Agradwip G.P.

Constn.. of CC road and drain at 2017 - Executive Officer, 42 Kuyara Danga from Masjid Tala to 2461/DP 05/09/2017 250000 244500 244500 100 Yes 2018 Katwa- II P.S. Jinnal Sk house of Palsona G.P. 195 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Constn. of CC Road at Natungram 2017 - Executive Officer, 43 from Sultans house to Porkorer Par 2461/DP 05/09/2017 100000 97000 97000 100 Yes 2018 Katwa- II P.S. of G.P.

Constn. of drain from the house of A. Debnath house of R. Kanta 2017 - Executive Officer, 44 2825/DP 06/11/2017 125000 124403 124403 100 Yes Debnath at Ekaihat of Khajuridihi 2018 Katwa- I P.S. G.P. Constn. of C.C. Road from Katwa Karul Road to the house of Biduri 2017 - Executive Officer, 45 2825/DP 06/11/2017 125000 125000 125000 100 Yes Pal at Panchghora of Khajuridihi 2018 Katwa- I P.S. G.P. Asset Handover Constn. of CC Road from Katrsj Report Received as per 2017 - Executive Officer, 46 Gram oad house of 2825/DP 06/11/2017 150000 150000 150000 100 Yes the Clause No. 8 under 2018 Katwa- I P.S. N.Pandit Durga Gram updated BEUP Guidelines 2019 Constn. of CC Road from Karajgram from Paschimpara 2017 - Executive Officer, 47 2825/DP 06/11/2017 250000 250000 250000 100 Yes Simultala to Karajgram High School 2018 Katwa- I P.S. of Karajgram G.P. Constn. of C.C. Road from the 2017 - Executive Officer, 48 house of M. Malik house of Gafur 2825/DP 06/11/2017 125000 125000 125000 100 Yes 2018 Katwa- I P.S. Sk at Natungram of Karajgram G.P.

Constn. of CC Road from the house 2017 - Executive Officer, 49 of R. Roy house of R. Dutta at Char 2825/DP 06/11/2017 125000 125000 125000 100 Yes 2018 Katwa- I P.S. Panuhat of Karajgram G.P. 196 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ted Constn. of CC Road from Bandhmura Executive 2017 - 50 Bagdipara house of R. Hazra house of 2825/DP 06/11/2017 100000 Officer, 100000 100000 100 Yes 2018 Asraf Sk of Karajgram G.P. Katwa- I P.S. Instn of High Mast Light of different 2017 - Chairman, 51 1096/DP 14/06/2018 500000 500000 500000 100 Yes Location of Town 2018 Dainhat Muty. Constn. of CC Road from Abdul Baki Executive 2017 - 52 Mallick to Choyer A. Mallick house at 1188/DP 26/06/2018 150000 Officer, 150000 150000 100 Yes 2018 Garagacha vill Gazipur Katwa- II P.S. Constn. of CC Road from S. Bairagya Executive 2017 - 53 house to S. Baiagya house at Suagachi 1188/DP 26/06/2018 200000 Officer, 200000 200000 100 Yes 2018 vill Katwa- II P.S. Asset Handover Report Constn. of gate at DD Girls High 2017 - Chairman, Received as per the 54 1403/DP 30/07/2018 200000 200000 200000 100 Yes School at Katwa Municipality 2018 Katwa Muty. Clause No. 8 under updated BEUP Guidelines Instan. of color Doppler Ultrasound 2017 - Chairman, 2019 55 1403/DP 30/07/2018 800000 800000 800000 100 Yes Machin at Dr. B.C. Roy Polytechnic 2018 Katwa Muty. Constn.. of CC road from Brindaban Executive Ghosh House to Gartala at Bijoy 2017 - 56 472/DP 14/02/2019 200000 Officer, 199300 199300 100 Yes Nagar Village at Sudpur G.P. under 2018 Katwa- I P.S. Katwa-I P.S. Installation of water purifier for the 2017 - Chairman, 57 255/DP 21/01/2020 125000 125000 125000 100 Yes student Dainhat High School 2018 Dainhat Muty. Installation of Submersible pump set 2017 - Chairman, 58 for drinking water at Keshia Masjid 431/DP 04/02/2020 125000 125000 125000 100 Yes 2018 Katwa Muty. under Katwa Municipality Total 5284002 5261629 5261629 197 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ted

Constn.. of C.C. road at Executive Mahakhaltore Dutta Para under 2018 - 59 484/DP 14/02/2019 500000 Officer, 495250 495250 100 Yes Agradwip G.P. within Katwa-II 2019 Katwa- II P.S. P.S.

Supply of Funeral Car (Dead Body 2018 - Chairman, 60 Removal Van) under Dainhat 1301/DP 30/05/2019 468370 468370 468370 100 Yes 2019 Dainhat Muty. Municipality

Constn.. of drain at beside Executive Mukherjee Pukur to Muchi Pukur 2018 - 61 1301/DP 30/05/2019 150000 Officer, 149250 149250 100 Yes under Sribati G.P. within Katwa-II 2019 Katwa- II P.S. Asset Handover Report P.S. Received as per the Clause Constn. of drining sheed at Akhra No. 8 under updated BEUP Executive High School under 2018 - Guidelines 2019 62 1301/DP 30/05/2019 300000 Officer, 298500 298500 100 Yes Jagadanandapur G.P. within 2019 Katwa- II P.S. Katwa-II P.S. Constn.. of drain at Mulgram Executive beside Monduptala to Susanta 2018 - 63 1301/DP 30/05/2019 150000 Officer, 149400 149400 100 Yes Ghosh house under Sribati G.P. 2019 Katwa- II P.S. within Katwa-II P.S.

Constn.. of Protection wall at Executive 2018 - 64 Auria Bandh pukur under Palsona 2043/DP 09/08/2019 200000 Officer, 199000 199000 100 Yes 2019 G.P. Katwa- II P.S. 198 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Constn.. of community sheed at Musthuli Laha Para under 2018 - Executive Officer, 65 2325/DP 30/08/2019 200000 199000 199000 100 Yes Jaganandapur G.P. within Katwa-II 2019 Katwa- II P.S. P.S. Constn.. of C.C. road with drain at Nandigram from Goutam Roy House 2018 - Executive Officer, 66 4234/DP 25/11/2019 200000 199000 199000 100 Yes to Sujit Roy House under Sribati GP. 2019 Katwa- II P.S. within Katwa-II P.S. Constn.. of waiting room at Srirampur 2018 - Executive Officer, 67 Bus Stand under Karajgram G.P. 4692/DP 26/12/2019 500000 499000 499000 100 Yes 2019 Katwa- I P.S. within Katwa-I P.S. Asset Handover Report Received Constn.. of CC road and drain at as per the Clause Haripur, beside the house of Mostafa 2018 - Executive Officer, 68 4692/DP 26/12/2019 400000 399960 399960 100 Yes No. 8 under Sk. to Surhok Sk. under Goai G.P. 2019 Katwa- I P.S. updated BEUP within Katwa-I P.S. Guidelines 2019 Installation of High Mast Light (Mini) 2018 - Executive Officer, 69 at Agradwip Railbazar near 604/DP 13/02/2020 150000 150000 150000 100 Yes 2019 Katwa- II P.S. Allahadabad Bank

Installation of High Mast Light (Mini) 2018 - Executive Officer, 70 604/DP 13/02/2020 150000 150000 150000 100 Yes at Gajipur Dasduari Bandh 2019 Katwa- II P.S.

Installation of High Mast Light (Mini) 2018 - Executive Officer, 71 604/DP 13/02/2020 150000 150000 150000 100 Yes at Dewasin Bridge at Gajipur G.P. 2019 Katwa- II P.S. 199 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed Instalation of High Mast Light (Mini) 2018 - Executive Officer, 72 at Barakulgachi Bakultala at Gajipur 604/DP 13/02/2020 150000 150000 150000 100 Yes 2019 Katwa- II P.S. G.P. Fencing for Development of Play Asset Handover 2018 - Chairman, Katwa 73 groundof Gibinda Bagan Play Ground 644/DP 17/02/2020 897637 897637 897637 100 Yes Report Received 2019 Muty. at Kashigang para under Katwa Muty. as per the Clause No. 8 under Supply of Funeral Car (Dead Body) Chairman, Katwa 74 2018 - 212/DP 17/01/2019 500000 500000 500000 100 Yes updated BEUP Removal van under Katwa Muty. 2019 Muty. Guidelines 2019 Addition and Alteration of 1st floor of 2018 - Chairman, Katwa 75 College Canteen at Katwa College 924/DP 13/03/2020 800000 800000 800000 100 Yes 2019 Muty. Campus Total 5866007 5854367 5854367 Installation of submersible pump set 2019 - Chairman, Katwa 76 for drinking water at Adarshapally 1498/DP 28/05/2020 187915 187915 187915 100 Yes 2020 Muty. School Constn.. of room for drinking water 2019 - Chairman, Katwa Asset Handover 77 cooling and purifing Machine at B.C. 1498/DP 28/05/2020 193446 193446 193446 100 Yes 2020 Muty. Report Received Roy Statue as per the Clause Constn.. of room for drinking water No. 8 under 2019 - Chairman, Katwa 78 cooling and purifing Machine at Nichu 1498/DP 28/05/2020 193426 193426 193426 100 Yes updated BEUP 2020 Muty. Bazar Guidelines 2019 Constn.. of room for drinking water 2019 - Chairman, Katwa 79 cooling and Purifing Machine at 1498/DP 28/05/2020 193366 193366 193366 100 Yes 2020 Muty. Panuhat Bazar

200 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Constn.. of room for drinking water 2019 - Chairman, Katwa 80 cooling and purifing Machine at 1498/DP 28/05/2020 193465 193465 193465 100 Yes 2020 Muty. D.D.C. Girls School Asset Handover Report Received Constn.. of room for drinking water as per the Clause 2019 - Chairman, Katwa 81 cooling and puriing at Kashiram Das 1498/DP 28/05/2020 193226 193226 193226 100 Yes No. 8 under 2020 Muty. H.S. School updated BEUP Guidelines 2019 Constn.. of one single Storied building 2019 - Chairman, Katwa 82 1498/DP 28/05/2020 1000000 1000000 1000000 100 Yes at Katwa College 2020 Muty.

Total 2154844 2154844 2154844 Grand Total 19179853 18486889 18486889

201 ONGOING SCHEMES

202 RABINDRANATH CHATTERJEE, HON'BLE MLA 270 KATWA A.C.

Sanction UC Present Status Sl. Date of Amount Executing Amount Amount Physical Present Status for Name of the Scheme Year Order Submitt for the Month of No. Sanction Sanction Agency Released Utilized Progress the Month of June No ed July Installation of Submesible 100% Work 100% work 2016 - Chairman, Completed, Final UC completed. UC will 1 Pump set for Drinking water 274/DP 25/01/2021 187450 187450 140588 75 Yes 2017 Katwa Muty. will be submitted after be submitted Facility at Katwa receiving of fund 04/08/2021 Upgradation of Gallery with 100% Work 100% work 2016 - Chairman, completed. UC will 2 dismantalling RCC Brick Work 274/DP 25/01/2021 281852 281852 211389 75 Yes Completed, Final UC 2017 Katwa Muty. will be submitted after be submitted and Plaster receiving of fund 04/08/2021 Constn. of Drain at North side 100% Work 100% work 2016 - Chairman, completed. UC will 3 of Stadium play Ground Ward 274/DP 25/01/2021 220000 220000 165000 75 Yes Completed, Final UC 2017 Katwa Muty. will be submitted after be submitted No 20 receiving of fund 04/08/2021 Total 689302 689302 516977 Constn. of CC road from Kalitala to House of Somnath Executive 80% Work 100% work 2017 - Completed, 1st Phase completed. Balance 4 Majhi at Nalhati village under 3181/DP 03/12/2020 199880 Officer, 149910 149910 75 Yes 2018 UC will be submitted UC will be submitted Sudpur G.P. within Katwa-I Katwa- I P.S. end of June, 2021 after getting the fund P.S. 100% Work 100% work Constn. of Drain outside 2017 - Chairman, Completed, Final UC completed. Balance 5 271/DP 25/01/2021 230000 230000 172500 75 Yes Boundary Wall 2018 Katwa Muty. will be submitted after UC will be submitted receiving of fund after getting the fund 100% Work 100% work Constn. of Road with Stone dust 2017 - Chairman, Completed, Final UC completed. Balance 6 271/DP 25/01/2021 265462 265462 199096 75 Yes at Entrance Gate of Stadium 2018 Katwa Muty. will be submitted after UC will be submitted receiving of fund after getting the fund Total 695342 645372 521506 203 Sanction UC Present Status Sl. Date of Amount Executing Amount Amount Physical Present Status for Name of the Scheme Year Order Submitt for the Month No. Sanction Sanction Agency Released Utilized Progress the Month of June No ed of July

100% work 100% Work Constn.. of Clock Tower at completed. 2019- Chairman, Completed, Final UC 7 Duckbangalow road side in 1498/DP 28/05/2020 283036 283036 212277 75 Yes Balance UC will will be submitted very 2020 Katwa Muty. be submitted after front of Municipal Office soon getting the fund

100% work 100% Work Beautification work at Goalpara completed. 2019- Chairman, Completed, Final UC 8 Ghat VIZ Concrete chair with 268/DP 25/01/2021 256233 192174 192174 75 Yes Balance UC will will be submitted after 2020 Katwa Muty. be submitted after chequer Tiles receiving of fund getting the fund

100% work 100% Work Beatification work at completed. 2019- Chairman, Completed, Final UC 9 Mondalpara Ghat VIZ Concrete 268/DP 25/01/2021 169422 127066 127066 75 Yes Balance UC will will be submitted after 2020 Katwa Muty. be submitted after Chair with Chequer tiles receiving of fund getting the fund

75% Work Constn. of Boundary Wall at Executive Completed. UC 2019- Completed, Final UC 10 Kalikapur Football Ground 246/DP 25/01/2021 497000 Officer, 496950 372750 75 Yes will be submitted will be submitted very 2020 30/08/2021 within Katwa-II Katwa- II P.S. soon

100% Work Constn. of High Mast light at Executive Completed. UC 2019- Completed, 1st Phase 11 Barakulgachi Bilkash Das 701/dp 15/02/2021 150000 Officer, 112500 0 0 No will be submitted UC will be submitted 2020 30/08/2021 Cycle Store Katwa- II P.S. very soon

204 Sanction UC Present Status Sl. Date of Amount Executing Amount Amount Physical Present Status for Name of the Scheme Year Order Submit for the Month No. Sanction Sanction Agency Released Utilized Progress the Month of June No ted of July

Executive Completed. UC Constn. of High Mast Light at 2019- 100% Work Completed, 12 701/DP 15/02/2021 150000 Officer, 112500 0 0 No 1st Phase UC will be will be submitted Delapur Bus Stand 2020 Katwa- II P.S. submitted very soon 30/08/2021

Executive Completed. UC Constn. of High Mast Light at 2019- 100% Work Completed, 13 701/DP 15/02/2021 150000 Officer, 112500 0 0 No 1st Phase UC will be will be submitted Islampur more High School 2020 Katwa- II P.S. submitted very soon 30/08/2021

Constn. of High Mast Light at Executive Completed. UC 2019- 100% Work Completed, 14 Multi village Mayratala of 701/DP 15/02/2021 150000 Officer, 112500 0 0 No 1st Phase UC will be will be submitted 2020 Sribanti GP Katwa- II P.S. submitted very soon 30/08/2021

Constn. of high Mast Light at Executive Completed. UC 2019- 100% Work Completed, 15 Suagachi village near 701/DP 15/02/2021 150000 Officer, 112500 0 0 No 1st Phase UC will be will be submitted 2020 Dharmatala Katwa- II P.S. submitted very soon 30/08/2021

Constn. of High Mast Light Executive Completed. UC 2019- 100% Work Completed, 16 near Dewasin Sarbeswar 701/DP 15/02/2021 150000 Officer, 112500 0 0 No 1st Phase UC will be will be submitted 2020 Mandir Katwa- II P.S. submitted very soon 30/08/2021

Executive Completed. UC Constn. of High Mast Light at 2019- 100% Work Completed, 17 701/DP 15/02/2021 150000 Officer, 112500 0 0 No 1st Phase UC will be will be submitted Multi More of Sribati 2020 Katwa- II P.S. submitted very soon 30/08/2021

Constn. of High Mast Light at Executive Completed. UC 2019- 100% Work Completed, 18 Agradwip Kalimandir under 701/DP 15/02/2021 150000 Officer, 112500 0 0 No 1st Phase UC will be will be submitted 2020 Gajipur GP Katwa- II P.S. submitted very soon 30/08/2021 205 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month of for the Month of No. Sanction Sanction Agency Released Utilized Progress No ted June July

Installation of 9 mtr. Tubuler pole with 4 nos. 120 watt led 2019- Chairman, Completed. UC 19 2762/DP 30/06/2021 419418 314564 0 0 No Nil street light of 4 nos. placess 2020 Dainhat Muty. will be submitted under Dainhat Muty. 03/08/2021

Total 2825109 2313790 531517

100% Work 100% work Completed, Final Development of Play Ground completed. 2020- Chairman, UC will be 20 at Katwa Stadium under 260/DP 25/01/2021 3000000 2250000 2250000 75 Yes Balance UC will 2021 Katwa Muty. submitted after Katwa Muty be submitted after receiving of fund getting the fund Nil

Total 3000000 2250000 2250000 Grand Total 7209753 5898464 3820000

206 Hon’ble M.L.A. Sekh. Saho Nawez MLA 271 KETUGRAM A.C.

207 COMPLETED SCHEMES

208 SEKH SAHO NEWAZ, HON'BLE MLA 271 KETUGRAM A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submi Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress tted

Constn. of Ghat at Ankhona 2016 - Executive Officer, 1 2727/DP 21/11/2016 150000 150000 150000 100 Yes Shattala Pond of Ankhona G.P. 2017 Ketugram- I P.S.

Constn. of Ghat at Rikha ir Pukur 2016 - Executive Officer, 2 2727/DP 21/11/2016 200000 200000 200000 100 Yes of Rajoor G.P. 2017 Ketugram- I P.S.

Constn. of Concrete Road from Madhusudan Bagdi house to D. 2016 - Executive Officer, 3 2727/DP 21/11/2016 300000 300000 300000 100 Yes Mukherjee house at Gonna 2017 Ketugram- I P.S. Serandi of Palita G.P. Asset Handover Report Received as per the Constn. of Ghat at Kantari Dighir 2016 - Executive Officer, Clause No. 8 under 4 2727/DP 21/11/2016 150000 150000 150000 100 Yes Par of Palita G.P. 2017 Ketugram- I P.S. updated BEUP Guidelines 2019 Constn. of Ghat at Chenchuri 2016 - Executive Officer, 5 2727/DP 21/11/2016 150000 150000 150000 100 Yes Thakrun Pukur of Ankhona G.P. 2017 Ketugram- I P.S.

Constn. of New Room Kandra 2016 - Executive Officer, 6 Hospital of Kandra 2958/DP 19/12/2016 500000 500000 500000 100 Yes 2017 Ketugram- I P.S. G.P.

Constn. of entrance of Kandra 2016 - Executive Officer, 7 3046/DP 27/12/2016 500000 500000 500000 100 Yes RKK College of Kandra G.P. 2017 Ketugram- I P.S. 209 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn. of Road from Charsujapur 2016 - Executive Officer, 8 Chowrasta to Dyoam of Mougram 61/DP 05/01/2017 300000 299608 299608 100 Yes 2017 Ketugram- II P.S. G.P.

Constn. of Road from Bankim 2016 - Executive Officer, 9 Nanda house to D. Bhattacherjee 61/DP 05/01/2017 300000 300000 300000 100 Yes 2017 Ketugram- II P.S. house with drain at Nirol

Constn. of Culvert at Baharan 2016 - Executive Officer, Asset Handover 10 61/DP 05/01/2017 300000 300000 300000 100 Yes Hazrapara of G.P. 2017 Ketugram- II P.S. Report Received as per the Clause No. 8 Constn. of Culvert at Haldi to under updated BEUP 2016 - Executive Officer, 11 Srigram Road near Fullaratala of 742/DP 09/03/2017 625000 625000 625000 100 Yes Guidelines 2019 2017 Ketugram- I P.S. Agardanga

Constn. of Guard Wall at Keoguri 2016 - Executive Officer, 12 742/DP 09/03/2017 300000 282964 282964 100 Yes High School of Sitahati G.P. 2017 Ketugram- II P.S.

Rep. of all Anganwari, SSK,MSK 2016 - Executive Officer, 13 742/DP 09/03/2017 500000 497894 497894 100 Yes Building under Ketugram-II 2017 Ketugram- II P.S.

Asset Handover Report Wanting as Computer Set at Shibloon ACM 2016 - Executive Officer, 14 1152/DP 12/04/2017 100000 100000 100000 100 Yes per the Clause No. 8 High School of Nabagram 2017 Ketugram- II P.S. under updated BEUP Guidelines 2019 Total 4375000 4355466 4355466 210 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed Constn.. of Baitarani scheme Exe. Engg. PWD 2017 - 15 Ketugram-II and Chakta, near 2248/DP 11/08/2017 890000 (Social Sector), 740653 740653 100 Yes 2018 Kuye River (Jl.-2, Dag-1681) Burdwan. Constn.. of Baitarani scheme at Exe. Engg. PWD 2017 - 16 Ketugram-II and Kalyanpur 2248/DP 11/08/2017 890000 (Social Sector), 740653 740653 100 Yes Asset Handover 2018 Gangaghat (JL-111, Dag-324) Burdwan. Report Wanting as Constn.. of Baitarani scheme at Exe. Engg. PWD per the Clause No. 8 2017 - 17 Ketugram-II and Jakdanga 2248/DP 11/08/2017 890000 (Social Sector), 740653 740653 100 Yes under updated BEUP 2018 Srigram (Jl.-7, Dag.-1858) Burdwan. Guidelines 2019 Constn. of ACR 2017 - Executive Officer, 18 Dakshin Muskim F.P. School of 2376/DP 29/08/2017 250000 250000 250000 100 Yes 2018 Katwa- I P.S. Srikhanda G.P. Constn. of Ghat at Majhipara 2017 - Executive Officer, 19 Dighi Pukur at Sripur vill of 2376/DP 29/08/2017 150000 150000 150000 100 Yes 2018 Ketugram- I P.S. Khandra G.P. Impv of Road from Badsahi 2017 - Executive Officer, 20 road towards Aargoon viilage 2376/DP 29/08/2017 300000 300000 300000 100 Yes 2018 Ketugram- I P.S. of Rajoor G.P. Asset Handover Constn. of Boundary Wall Bara 2017 - Executive Officer, Report Received as 21 Purulia Mahendra Vidyalaya of 3280/DP 13/12/2017 200000 179748 179748 100 Yes 2018 Ketugram- II P.S. per the Clause No. 8 Nabagram under updated BEUP Constn. of one ACR Bileswar Guidelines 2019 2017 - Executive Officer, 22 Binodilal Balika Vidyalaya 146/DP 24/01/2018 300000 300000 300000 100 Yes 2018 Ketugram- II P.S. under Ketugram Rep of Room Gurpara High 2017 - Executive Officer, 23 School of Billeswar under 146/DP 24/01/2018 300000 298458 298458 100 Yes 2018 Ketugram- II P.S. Ketugram 211 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed

Constn. of road from Nalipur More to 2017 - Executive Officer, 24 290/DP 09/02/2018 450000 450000 450000 100 Yes Keogari High School under Ketugram 2018 Ketugram- II P.S.

Constn. of Toilet at Rajoor Bandhab 2017 - Executive Officer, 25 1448/DP 06/08/2018 200000 200000 200000 100 Yes High School of Rajoor G.P. 2018 Ketugram- I P.S.

Constn.. of ghat at Painfola ghat at 2017 - Executive Officer, 26 Raghupur (daag no. 1358 Jl-65 of 2194/DP 28/09/2018 150000 150000 150000 100 Yes 2018 Ketugram- I P.S. Pandugram G.P. under Ketugram-I P.S. Asset Handover Report Received Constn.. of ACR at Kulai High School 2017 - Executive Officer, as per the Clause 27 638/DP 26/02/2019 300000 300000 300000 100 Yes under Pandugram G.P. 2018 Ketugram- I P.S. No. 8 under updated BEUP Constn. of Ghat at Bannagara Sukhmoy 2017 - Executive Officer, Guidelines 2019 28 2076/DP 18/09/2018 150000 149985 149985 100 Yes Pond of Srikhanda G.P. 2018 Katwa- I P.S.

Constn.. of Culvet at Barnna Gara 2017 - Executive Officer, 29 1797/DP 22/07/2019 400000 399960 399960 100 Yes Kandar under Katwa-I P.S. 2018 Katwa- I P.S.

Constn.. of bathroom and ghat at 2017 - Executive Officer, 30 Khaspukur Nawpukur of Rajoor G.P. 2123/DP 19/08/2019 250000 250000 250000 100 Yes 2018 Ketugram- I P.S. under Ketugram-I P.S. Asset Handover Constn. of Kalu Pukur Ghat and 2017 - Executive Officer, Report Wanting as 31 Bathroom at Berugram G.P. within 826/DP 04/03/2020 180000 180000 180000 100 Yes 2018 Ketugram- I P.S. per the Clause No. Ketugram-I P.S. 8 under updated BEUP Guidelines Total 6250000 5780110 5780110 2019 212 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn.. of Cycle Stand Ketugram Asutosh Memorial Institution at 2018 - Executive Officer, 32 2138/DP 24/09/2018 200000 200000 200000 100 Yes Ketugram GP within Ketugram-II 2019 Ketugram- II P.S. P.S. Constn.. of roade from Dakshin Para Kaltala To Football Ground at Belun 2018 - Executive Officer, 33 2138/DP 24/09/2018 200000 149850 149850 100 Yes of Nabagram GP within Ketugram-II 2019 Ketugram- II P.S. PS. Constn.. of Boundary wall of Ketugram Jr. Girls High School under 2018 - Executive Officer, 34 2138/DP 24/09/2018 200000 200000 200000 100 Yes Ketugram G.P. within Ketugram-II 2019 Ketugram- II P.S. P.S. Asset Handover Constn.. of bondary wall of 2018 - Executive Officer, Report Received as 35 Enayetpur FP School of Sitahati GP 2138/DP 24/09/2018 150000 150000 150000 100 Yes 2019 Ketugram- II P.S. per the Clause No. 8 within Ketugram PS. under updated BEUP Constn.. of drain at Kandra from Kalu Guidelines 2019 2018 - Executive Officer, 36 Bairagya House to Akter within 2213/DP 10/10/2018 100000 100000 100000 100 Yes 2019 Ketugram- I P.S. Ketugram-I P.S. Repairing of room at Srikhanda High 2018 - Executive Officer, 37 School of Srikhanda G.P. under 488/DP 14/02/2019 100000 99990 99990 100 No 2019 Katwa- I P.S. Katwa-I P.S. Constn.. of Hatmurgram High 2018 - Executive Officer, 38 Madrasha Ceremony Stage within 562/DP 20/02/2019 150000 150000 150000 100 Yes 2019 Ketugram- I P.S. Ketugram-I P.S. Constn.. of High must light at 2018 - Executive Officer, 39 Futisanko Bus stand within Ketugram 562/DP 20/02/2019 540000 540000 540000 100 Yes 2019 Ketugram- I P.S. -I P.S. 213 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn.. of Community Hall at 2018 - Executive Officer, 40 Tourism Spot at Nowpara Ketugram-I 562/DP 20/02/2019 300000 300000 300000 100 Yes 2019 Ketugram- I P.S. P.S. Repairing of room at Srikhanda Asset Handover 2018 - Executive Officer, 41 Muslim primary School under Katwa-I 639/DP 26/02/2019 250000 249875 249875 100 Yes Report Received as 2019 Katwa- I P.S. per the Clause No. 8 P.S. under updated BEUP Constn. of road from Ajij Molla house Guidelines 2019 to Harej Mollah House at Chandrakota 2018 - Executive Officer, 42 843/DP 06/03/2019 200000 199920 199920 100 Yes under Srikhanda G.P. within Katwa-I 2019 Katwa- I P.S. P.S. Constn. of road from Dhanu Mondal Asset Handover house to Islam Sk house at 2018 - Executive Officer, Report Wanting as 43 843/DP 06/03/2019 200000 96653 96653 100 Yes per the Clause No. 8 Gangulidanga under Srikhanda G.P. Katwa- I P.S. 2019 under updated BEUP within Katwa-I P.S. Guidelines 2019 Asset Handover Constn.. of Pukur Ghat at Kodampukur 2018 - Executive Officer, Report Received as 44 under Srikhanda G.P. within Katwa-I 843/DP 06/03/2019 150000 149970 149970 100 Yes per the Clause No. 8 2019 Katwa- I P.S. P.S. under updated BEUP Guidelines 2019 Total 2740000 2586258 2586258 Asset Handover Constn.. of Bathing Ghat at Gora pukur Report Wanting as 2019 - Executive Officer, 45 Plot-6984 under Nirole G.P. within 1401/DP 14/05/2020 150000 112500 112500 100 Yes per the Clause No. 8 2020 Ketugram- II P.S. Ketugram-II P.S. under updated BEUP Guidelines 2019 Total 150000 112500 112500

Grand Total 13515000 12834334 12834334 214 ONGOING SCHEMES

215 SEKH SAHO NEWAZ, HON'BLE MLA 271 KETUGRAM A.C. Sl. Sanction UC Present Status Present Date of Amount Executing Amount Amount Physical No Name of the Scheme Year Order Submitt for the Month Status for the Sanction Sanction Agency Released Utilized Progress . No ed of June Month of July 100% work 100 % work Constn. of Ghat to Bhagirathi Near Executive completed, 2017 - completed, UC Dulal Sadhu Ashram at Sankhai of 998/DP 25/05/2018 150000 Officer, 150000 142362 75 Yes balance fund 1 will be submitted Sitahati G.P. 2018 will be refunded Ketugram- II P.S. shortly. soon. Total 150000 150000 142362 100% work 100% work Constn.. of Gopalsagar pond ghat and Executive 2018 - completed, Final completed, final Bathroom at Jl-90, Dag-2053 under 3499/DP 2 13/09/2019 160000 Officer, 119952 119952 75 Yes UC will be UC will be sent Ketugram-II P.S. 2019 Ketugram- II P.S. submitted shortly. shortly 100% work 100% work Constn.. of community hall at Executive 2018 - completed, Final completed, final Tourism spot at (Chhoto) 3958/DP 3 31/10/2019 299970 Officer, 299970 224978 75 Yes UC will be UC will be sent under Ketugram-II P.S. 2019 Ketugram- II P.S. submitted shortly. shortly 100% work 100% work Repairing of Aikyatan Community Executive 2018 - completed, Final completed, final Hall at Pachundi under Ketugram-II 256/DP 4 21/01/2020 492437 Officer, 492437 369328 75 Yes UC will be UC will be sent P.S. 2019 Ketugram- II P.S. submitted shortly. shortly 100% work 100% work Elec. of Solar Plant at Baranda Executive 2018 - completed, Final completed, final Paramanda Seba Kendra within 1400/DP 14/05/2020 148499 Officer, 148499 5 111374 75 Yes UC will be UC will be sent Ketugram-II P.S. 2019 Ketugram- II P.S. submitted shortly. shortly 100% work Smart Class Room with decoration at Executive 100 % completed, completed, final 2018 - 6 Churpuni High School under 3241/DP 08/12/2020 199880 Officer, Katwa- I 149910 149910 75 Yes UC will be given UC will be sent 2019 Koshigram GP within Katwa-I P.S. P.S. within this week after getting the balance fund Total 1300786 1210768 975542 216 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ted of June of July

Executive Constn.. of Bolla Pukur Ghat, 100% work 100% work 2019 - Officer, completed, Final completed, final 7 Plot-3061 under J-kandra G.P. 825/DP 04/03/2020 150000 150000 112500 75 Yes 2020 Ketugram- I UC will be UC will be given within Ketugram-I P.S. P.S. submitted shortly. shortly

Renovation of Community Executive 100% work 100% work Hall at Janadas Path bari Plot- 2019 - Officer, completed, Final completed, final 8 970/DP 17/03/2020 200000 200000 150000 75 Yes 2781 under J-Kandra G.P. 2020 Ketugram- I UC will be UC will be given within Ketugram-I P.S P.S. submitted shortly. shortly

100% work Constn.. of Bathing Ghat at Executive 100% work completed, final Talbona pukur Plot-2217 2019 - Officer, completed, Final 9 UC will be given 970/DP 17/03/2020 150000 150000 112500 75 Yes UC will be under Rajoor G.P. within 2020 Ketugram- I within 1st week of submitted shortly. Ketugram-I P.S. P.S. August Constn.. of waiting shed for bus passenger at Srikhanda 2019 - Executive 100% work 100% work completed, Final completed, 2nd 10 Bus Stand Plot-923 under 2020 3246/DP 08/12/2020 399850 Officer, 299850 299850 75 Yes UC will be installment to be Srikhanda G.P. within Katwa- Katwa- I P.S. submitted shortly. released. I P.S. Total 899850 799850 674850 Grand Total 2350636 2160618 1747754

217 Hon’ble M.L.A. Siddiqullah Chowdhury MLA 272 MONGALKOTE A.C.

218 COMPLETED SCHEMES

219 SIDDIQULLAH CHOWDHURY, HON'BLE MLA 272 MONGALKOTE A.C.

UC Sl. Sanction Date of Amount Amount Amount Physical Asset Handover Name of the Scheme Year Executing Agency Submit No. Order No Sanction Sanction Released Utilized Progress Status ted

Purchase an Ambulance for 2016 - District Magistrate, 1 1979/DP 01/09/2016 488220 488220 488220 100 Yes Alampur G.P. 2017 Burdwan

Purchase an Ambulance for 2016 - District Magistrate, 2 2459/DP 25/10/2016 492344 492344 492344 100 Yes Lakhuria G.P. 2017 Burdwan

Purchase an Ambulance for 2016 - District Magistrate, 3 2459/DP 25/10/2016 492344 492344 492344 100 Yes Bhalugram G.P. 2017 Burdwan

Constn. of Cycle Stand at 2016 - District Magistrate, 4 Mathrun NC Institution 892/DP 22/03/2017 450000 444098 444098 100 Yes 2017 Burdwan (H.S)under Mathrun Report Wanting Constn. of Addl Room for Exe. Engg. PWD Patients with Sanitation and 2016 - 5 892/DP 22/03/2017 1748000 (Social Sector), 1748000 1748000 100 Yes water supply at Mongalkote 2017 Burdwan. BPHC Constn. of Boundary Wall in 2016 - District Magistrate, 6 the school Campus of 3274/DP 12/12/2017 860000 860000 860000 100 Yes 2017 Burdwan Kowarpur High School

Constn. of Concrete road from 2016 - District Magistrate, 7 Ghat to Liabrary 417/DP 27/02/2018 490000 487550 487550 100 Yes 2017 Burdwan and Hattala under Mongalkote 220 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted District Constn. of PCC road at Bhatpara from 2016 - 8 1916/DP 28/08/2018 390000 Magistrate, 385826 385826 100 Yes Nazu Sk House to A. Rauf house 2017 Burdwan Total 5410908 5398382 5398382 Constn. of PCC Road at Village District 2017 - 9 Pindira from Abul Khair house to main 1811/DP 28/08/2018 750000 Magistrate, 639225 639225 100 Yes 2018 Rd.Pucca Udyan at Bhaligram Burdwan

Constn. of PCC road at Village District 2017 - 10 Dharsona from Chand Sk house to L. 1911/DP 28/08/2018 380000 Magistrate, 373267 373267 100 Yes 2018 Chand Sk house Khioragram Burdwan

Constn. of PCC road at Village at District Report Wanting 2017 - 11 Musaru Adibasipara from PWD Pacca 1911/DP 28/08/2018 350000 Magistrate, 346080 346080 100 Yes 2018 Road to Debu Hansda at Nigan Gram Burdwan

Constn. of Cycle Stand Shade at District 2017 - 12 majhigram Biswesri High School at 1911/DP 28/08/2018 470000 Magistrate, 464970 464970 100 Yes 2018 Majhigram Burdwan Constn.. of Mid-day meal shade for District 2017 - 13 students for Pindira High School under 2352/DP 29/10/2018 760000 Magistrate, 677920 677920 100 Yes 2018 Mongalkote P.S. Burdwan Constn.. of Mid-day meal shade at District 2017 - 14 Bazar Bankapasi F.P. School under 2352/DP 29/10/2018 800000 Magistrate, 708903 708903 100 Yes 2018 Mongalkote P.S. Burdwan Total 3510000 3210365 3210365 221 Sanction UC Sl. Date of Amount Amount Amount Physical Asset Handover Name of the Scheme Year Order Executing Agency Submit No. Sanction Sanction Released Utilized Progress Status No ted Constn.. of concrete road from Jillar 2018 - District Magistrate, 15 Rahaman House to Najrul Islam House 2676/DP 12/10/2020 300000 224843 224843 100 Yes Report Wanting 2019 Burdwan under Shimulia-II within Mongalkote P.S.

Total 300000 224843 224843

Constn.. of Toe wall at Mongalkote 2019- District Magistrate, 16 Madrasah Madina Darul Uloom under 3020/DP 13/11/2020 346850 346815 346815 100 Yes 2020 Burdwan Mongakote G.P. within Mongalkote P.S.

Constn.. of concrete road from Kamrul Jaman House towards Sahifur Rahaman 2019- District Magistrate, 17 3020/DP 13/11/2020 297000 297000 297000 100 Yes under Simulia-II G.P.within Mongalkote 2020 Burdwan P.S.

Constn.. of concrete road from main road 2019- District Magistrate, 18 towards masjid at Bhattpara village under 3020/DP 13/11/2020 296700 296700 296700 100 Yes 2020 Burdwan Report Wanting Jhiloo-II P.S. within Mongalkote P.S.

Constn.. of ACR at 1st floor of Madhpur 2019- District Magistrate, 19 3328/DP 14/12/2020 655900 655886 655886 100 Yes F.P. School under Majhergram G.P. 2020 Burdwan Constn.. of Boundary wall adjacent of 2019- District Magistrate, 20 bituminious road of Bagandanga 3328/DP 14/12/2020 566700 566521 566521 100 Yes 2020 Burdwan Graveyard under Ballagram G.P. Renovationn of Damage buidg at Kasem 2019- District Magistrate, 21 726/DP 18/02/2021 502197 500008 500008 75 Yes Nagar Naj High School 2020 Burdwan Total 2665347 2662930 2662930 222 UC Sl. Sanction Date of Amount Amount Amount Physical Asset Handover Name of the Scheme Year Executing Agency Submit No. Order No Sanction Sanction Released Utilized Progress Status ted

Constn. of Boundary Wall at Chakda 2020- District Magistrate, 22 Kalanpur Jamina Arabia Anowarul 588/DP 10/02/2021 345555 345521 345521 100 Yes 2021 Burdwan Ullom

Constn. of Concrete Road from House 2020- District Magistrate, 23 of Sultan Hansdar to House of kalo 588/DP 10/02/2021 395000 394985 394985 100 Yes Report Wanting 2021 Burdwan Hembram

Constn. of Petient relative Waiting 2020- District Magistrate, 24 Shed with attached Toilet at 790/DP 22/02/2021 461250 461226 461226 100 Yes 2021 Burdwan Mongalkote BPHC

Total 1201805 1201732 1201732 Grand Total 13088060 12698252 12698252

223 ONGOING SCHEMES

224 SIDDIQULLAH CHOWDHURY, HON'BLE MLA 272 MONGALKOTE A.C.

Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ed of June of July 100% work 100% work Constn. of boundary wall of West Bengal completed, final 2018 - completed UC 1 Natunhat SDM Girls School 776/DP 28/02/2020 170914 Agro Industries 170914 128186 75 Yes UC will be 2019 will be submitted within Mongalkote Dev. Block Copn. Ltd. submitted shortly 05/08/2021 100% work 100% work Arrangement for drinking water West Bengal completed, final 2018 - completed UC 2 at Joykrishna FP School within 776/DP 28/02/2020 199920 Agro Industries 199920 149940 75 Yes UC will be 2019 will be submitted Mongalkote Dev. Block Copn. Ltd. submitted shortly 05/08/2021 100% work Constn. of Class room 100% work West Bengal completed, final Mongalkote-II SSK Drinking 2018 - completed UC 3 776/DP 28/02/2020 299880 Agro Industries 299880 224910 75 Yes UC will be water Gate and Boundary wall 2019 will be submitted Copn. Ltd. submitted within Mongalkote Dev. Block shortly 05/08/2021 100% work 100% work Constn. of community hall at West Bengal completed, final 2018 - completed UC 4 Buichi Sashtitala within 775/DP 28/02/2020 698671 Agro Industries 698671 524003 75 Yes UC will be 2019 will be submitted Mongalkote P.S. Copn. Ltd. submitted shortly 05/08/2021 100% work 100% work Constn.. of meeting room cum West Bengal completed, final 2018 - completed UC 5 office Lakshimipur SKUS Ltd. 775/DP 28/02/2020 700000 Agro Industries 700000 524003 85 Yes UC will be 2019 will be submitted within Mongalkote P.S. Copn. Ltd. submitted shortly 05/08/2021 225 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt for the Month of for the Month No. Sanction Sanction Agency Released Utilized Progress No ed June of July 100% work Constn. of cc road from house 100% work West Bengal completed, final of Sudhir Ghosh to house of 2018 - completed UC will 6 775/DP 28/02/2020 300000 Agro Industries 300000 225000 75 Yes UC will be Chand Mondal within 2019 be submitted Copn. Ltd. submitted Mongalkote P.S. shortly 05/08/2021 100% work Constn. of fencing over 100% work West Bengal completed, final boundary wall at Natunhat 2018 - completed UC will 7 775/DP 28/02/2020 200000 Agro Industries 200000 150000 75 Yes UC will be Milan Pathagar within 2019 be submitted Copn. Ltd. submitted Mongalkote P.S. shortly 05/08/2021 Constn. of addl. room for 100% work 100% work Diniyat AL Qulam Mission West Bengal completed, final 2018 - completed UC will 8 under Pindira Helful Fujul 2935/DP 09/11/2020 996000 Agro Industries 996000 747000 75 Yes UC will be 2019 be submitted Society under Mongalkote Dev. Copn. Ltd. submitted shortly Block 05/08/2021 100% work 100% work Constn. of Addl Class Room West Bengal completed, final 2018 - completed UC will 9 and purchase and Installation of 448/DP 04/02/2021 513946 Agro Industries 513946 385460 75 Yes UC will be 2019 be submitted Grill Copn. Ltd. submitted shortly 05/08/2021 100% work 100% work Constn. of Kitchen cum Dinning West Bengal completed, final 2018 - completed UC will 10 Room at Madrasha Ashraful 448/DP 04/02/2021 797368 Agro Industries 797368 598026 75 Yes UC will be 2019 be submitted Ulamkhaitan Copn. Ltd. submitted shortly 05/08/2021

226 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt for the Month for the Month of No. Sanction Sanction Agency Released Utilized Progress No ed of June July

100% work 100% work Constn. of School Boundary West Bengal completed, final 2018 - completed UC 11 Wall of AL Jamia As Salafiha 448/DP 04/02/2021 398000 Agro Industries 398000 298500 75 Yes UC will be 2019 will be submitted AniulnmUllom at Palshgram Copn. Ltd. submitted shortly 05/08/2021 Total 5274699 5274699 3955028

Constn.. of Children Park at District 100% work Kulsuna Play Ground South 2019- 90 % work 12 3020/DP 13/11/2020 395000 Magistrate, 395000 0 0 No completed, Bill in Side under Bhallyagram G.P. 2020 completed Burdwan progress. within Mongalkote P.S.

Constn.. of High Mast Light at District 100% work 100% work 2019- 13 Kasem Nagar Bazar within 3328/DP 14/12/2020 351500 Magistrate, 351500 0 0 No completed bill completed, Bill in 2020 Mongalkote P.S. Burdwan under process progress.

Constn. of High Mast Light at District 100% work 100% work 2019- 14 Natunhat Nadir Dhar under 3328/DP 14/12/2020 351500 Magistrate, 351500 0 0 No completed bill completed, Bill in 2020 Jhilu-I G.P. Burdwan under process progress.

Constn. of High Mast Light at District 100% work 100% work 2019- 15 Nigan Chati under Shimulia-I 3328/DP 14/12/2020 351500 Magistrate, 351500 0 0 No completed bill completed, Bill in 2020 G.P Burdwan under process progress.

227 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt for the Month for the Month No. Sanction Sanction Agency Released Utilized Progress No ed of June of July Installation of a High Mast District 100% work 100% work Light at the road junction 2019- 16 3328/DP 14/12/2020 351500 Magistrate, 351500 0 0 No completed bill completed, Bill in adjacent to Natunhat BDO 2020 Burdwan under process progress. office Constn. of Boundary wall with District 100% work 2019- 80% work 17 Gate at Alfallaha Mission 726/DP 18/02/2021 345765 Magistrate, 345765 0 0 No completed, Bill in 2020 Completed Within Mongalkote Burdwan progress. Total 2146765 2146765 0 0 Work completed, Executive 100% work final UC will be Constn. of Boundary Wall of 2020- 18 447/DP 04/02/2021 599700 Officer, 449775 449775 75 Yes completed UC tobe submitted after Bhalsuni P School 2021 Katwa- I P.S. submitted shortly getting the balance fund. Work completed, Constn. of Black Top Road Executive 100% work final UC will be 2020- 19 from Alampur Bus Stand twards 447/DP 04/02/2021 706265 Officer, 529666 529666 75 Yes completed UC tobe submitted after 2021 Alampur Katwa- I P.S. submitted shortly getting the balance fund. Constn. of Midday Meal District 100% work 2020- Work completed, 20 Kitchen Shed at Jhllu AHM 588/DP 10/02/2021 395800 Magistrate, 395800 0 0 No completed bill 2021 Bill in progress. Institution Burdwan under process Constn. of Boundary Wall at District West and south side of Hatiputa 2020- 80% work Work completed, 21 790/DP 22/02/2021 584400 Magistrate, 584400 0 0 No Danga Graveyard under 2021 Completed Bill in progress. Burdwan Mongalkote Total 2286165 1959641 979441 Grand Total 9707629 9381105 4934469 228 Hon’ble M.L.A. Shri Abhedananda Thander MLA 273 AUSGRAM (SC) A.C.

229 COMPLETED SCHEMES

230 ABHEDANANDA THANDER, HON'BLE MLA 273 AUSGRAM (SC) A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submitt No. Order No Sanction Sanction Agency Released Utilized Progress Status ed Constn. of Boundary wall for 2016 - Chairman, 1 Community Centre at 2724/DP 21/11/2016 115122 115122 115122 100 Yes 2017 Gushkara Muty. Sukantapally Ward No. 4 Constn. of Boundary wall for 2016 - Chairman, 2 Community Centre at 2724/DP 21/11/2016 183296 183296 183296 100 Yes 2017 Gushkara Muty. Purbopally Ward No. 4

Constn. of Road side Guard 2016 - Chairman, 3 2724/DP 21/11/2016 297902 297902 297902 100 Yes Wall at Ward No. 3 2017 Gushkara Muty. Asset Handover Report Received as Constn. of CC Road at Ward 2016 - Chairman, 4 2724/DP 21/11/2016 98598 98598 98598 100 Yes per the Clause No. 8 No. 7 under Muty 2017 Gushkara Muty. under updated BEUP Guidelines 2019 Constn. of CC Road at Ward 2016 - Chairman, 5 2724/DP 21/11/2016 100543 100543 100543 100 Yes No. 2 under Guskara Muty 2017 Gushkara Muty.

Constn. of CC Drain at Ward 2016 - Chairman, 6 2724/DP 21/11/2016 103003 103003 103003 100 Yes No. 10 under Guskara Muty 2017 Gushkara Muty.

Constn. of CC Road at Ward 2016 - Chairman, 7 2724/DP 21/11/2016 99435 99435 99435 100 Yes No. 1 under Guskara Muty 2017 Gushkara Muty.

231 Sanction UC Sl. Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Order Submit No. Sanction Sanction Agency Released Utilized Progress Status No ted Asset Handover District Report Wanting as Purchase an Ambulance for Billagram 2016 - 8 2770/DP 28/11/2016 540085 Magistrate, 540085 540085 100 Yes per the Clause No. 8 under Ausgram-I 2017 Burdwan under updated BEUP Guidelines 2019

Executive Constn. of waiting shed at 2016 - 9 600/DP 27/02/2017 800000 Officer, 800000 800000 100 Yes Bannabagram BPHC of Ausgram G.P. 2017 Ausgram- I P.S.

Constn. of waiting Shed with drinking Executive 2016 - 10 water facility at Ukhra PHC at Ukhra 645/DP 01/03/2017 900000 Officer, 900000 900000 100 Yes 2017 G.P. Ausgram- I P.S.

Executive Constn. of Samsan Chulli at Dharala 2016 - 11 905/DP 22/03/2017 250000 Officer, 250000 250000 100 Yes Asset Handover village under Ausgram-II P.S. 2017 Ausgram- II P.S. Report Received as per the Clause No. 8 Executive Constn. of Boundary Wall at 2016 - under updated BEUP 12 905/DP 22/03/2017 300000 Officer, 300000 300000 100 Yes Abhirampur F.P. School 2017 Guidelines 2019 Ausgram- II P.S.

Executive Constn. of Toilet including Flooring at 2016 - 13 946/DP 27/03/2017 400000 Officer, 400000 400000 100 Yes Bhedia Community Hall 2017 Ausgram- II P.S.

Executive Constn. of Hatchala at Bishnupur 2016 - 14 946/DP 27/03/2017 400000 Officer, 400000 400000 100 Yes village under Ausgram 2017 Ausgram- II P.S. 232 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ted Executive Constn. of Drain Palpukur 2016 - 15 2079/DP 25/07/2017 168300 Officer, 168300 168300 100 Yes toward Tulsey in Billwagram 2017 Ausgram- I P.S.

Constn. of Busstand at Executive 2016 - 16 Morebandh Mouza Chhora plot 2173/DP 01/08/2017 500000 Officer, 500000 500000 100 Yes 2017 no. 1658 Ausgram- II P.S.

Executive Constn. of Boundary wall at 2016 - 17 2173/DP 01/08/2017 250000 Officer, 250000 250000 100 Yes Jamtara BPHC of Bhalki G.P. 2017 Ausgram- II P.S. Constn. of Community Hall at Executive Parisha Simultala, Mouza- 2016 - C- Asset Handover Report 18 29/11/2017 400000 Officer, 400000 400000 100 Yes Parisha, J.L. No. 11, Plot No. 2017 2860/DP Received as per the Ausgram- II P.S. 2024 under Ausgram- II P.S Clause No. 8 under updated BEUP Guidelines Constn. of drain from Panja Executive 2016 - 19 Pukur to P. Pals house at Belari 3287/DP 13/12/2017 91600 Officer, 91600 91600 100 Yes 2017 of Billagram Ausgram- I P.S.

Total 5997884 5997884 5997884 Constn.. of Baitarani scheme at Exe. Engg. PWD 2017 - 20 Aushgram-II and Dighnagar (Jl- 1537/DP 26/05/2017 890000 (Social Sector), 859089 859089 100 Yes 2018 136, Plot-6112) Burdwan. Constn.. of Baitarani scheme at Exe. Engg. PWD 2017 - 21 Aushgram-II and Sitalgram, 1537/DP 26/05/2017 890000 (Social Sector), 859089 859089 100 Yes 2018 Gangarampur, 3179 Burdwan. 233 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn.. of Baitarani scheme at Exe. Engg. PWD 2017 - 22 Ausgram-II and Raghunathpur, 1537/DP 26/05/2017 890000 (Social Sector), 859089 859089 100 Yes 2018 Kota G.P. (Jl.-79, Plot-349) Burdwan. Asset Handover Report Received as Constn.. of Baitarani scheme at Exe. Engg. PWD 2017 - per the Clause No. 8 23 Aushgram-I and Ramnagar, 1537/DP 26/05/2017 890000 (Social Sector), 859089 859089 100 Yes 2018 under updated Khanngar (Jl-44, Plot 202/209) Burdwan. BEUP Guidelines Constn.. of Baitarani scheme at Exe. Engg. PWD 2017 - 2019 24 Aushgram-II and Bhedia (Jl -88, 1537/DP 26/05/2017 890000 (Social Sector), 859089 859089 100 Yes 2018 Dag-111, Plot-01) Burdwan.

Asset Handover District Purchase An Ambulance for 2017 - Report Wanting as 25 30/DP 04/01/2018 595204 Magistrate, 595204 595204 100 Yes per the Clause No. 8 Ausgram-II 2018 Burdwan under updated BEUP Guidelines 2019

Constn. of Siksha Charcha Kendra 2017 - Executive Officer, 26 145/DP 24/01/2018 300000 300000 300000 100 Yes at Amragarh under Ausgram-II 2018 Ausgram- II P.S.

Constn.. of boundary wall of Asset Handover 2017 - Executive Officer, 27 Ramnagar PHC under Ramnagar 283/DP 24/01/2019 689106 689106 689106 100 Yes Report Received as 2018 Ausgram- II P.S. G.P. within Ausgram-II P.S. per the Clause No. 8 under updated Total 6034310 5879755 5879755 BEUP Guidelines Constn. of Children Park and 2019 beautification at Plot No. 2397 Jl- 2018 - Executive Officer, 28 2318/DP 01/10/2018 335000 331167 331167 100 Yes 110 Mouza-Guskara within 2019 Ausgram- I P.S. Ausgram-I PS. 234 Sanction UC Sl. Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Order Submit No. Sanction Sanction Agency Released Utilized Progress Status No ted

Beautification with Decorative LED Executive 2018 - 29 Light at Chandni Park (Phase-II) of 2212/DP 01/10/2018 300000 Officer, 288206 288206 100 Yes 2019 Dignagar-I G.P. Ausgram- I P.S.

Beautification with Decorative LED Executive Light at Chandni Park (Phase-I) of 2018 - 30 2212/DP 01/10/2018 300000 Officer, 298950 298950 100 Yes Dignagar-I G.P. within Ausgram-I 2019 Ausgram- I P.S. P.S.

Constn.. of Children Park and Executive beautification at Plot No. 2398 Jl-110 2018 - 31 2318/DP 01/10/2018 265000 Officer, 262282 262282 100 Yes Mouza-Guskara within Ausgram-I 2019 Asset Handover Ausgram- I P.S. PS. Report Received as per the Clause No. 8 Constn.. of Cultural centre at Executive under updated BEUP Jadabganj Avarani FP School JL-104 2018 - 32 2318/DP 01/10/2018 300000 Officer, 297049 297049 100 Yes Guidelines 2019 Plot-1539 Mouza-Jadabganj at 2019 Ausgram- I P.S. Dignagar-II within Ausgram-I PS.

Beautification of Chandni Park at Executive 2018 - 33 Chandni of Dignagar-I G.P. within 2212/DP 01/10/2018 260000 Officer, 258545 258545 100 Yes 2019 Ausgram-I P.S. Ausgram- I P.S.

Installation of Solar Light system Executive with all accessories at Chandni park 2018 - 34 2212/DP 01/10/2018 240000 Officer, 239040 239040 100 Yes at Dignagar-I GP. within Ausgram-I 2019 Ausgram- I P.S. P.S. 235 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Beautification with Decorative LED 2018 - Executive Officer, 35 Light at Chandni Park (Phase-III) of 2212/DP 01/10/2018 300000 283194 283194 100 Yes 2019 Ausgram- I P.S. Dignagar-I G.P. Constn.. of Atchala at Kalikapur 2018 - Executive Officer, Asset Handover 36 under Amarpur G.P. within 527/DP 18/02/2019 500000 495000 495000 100 Yes Report Received as 2019 Ausgram- II P.S. Ausgram-II P.S. per the Clause No. 8 under updated Constn.. of Community Hall at 2018 - Executive Officer, BEUP Guidelines 37 Nabagram Kaibartya para under 3920/DP 23/10/2019 400000 397600 397600 100 Yes 2019 Ausgram- I P.S. 2019 Berenda G.P. within Ausgram-I P.S.

Upgradation of Sanhati Mancha 2018 - Executive Officer, 38 3919/DP 23/10/2019 200000 198800 198800 100 Yes (Meeting Hall) at Ausgram-I P.S. 2019 Ausgram- I P.S.

Sinking of Submersible pump with 2018 - Executive Officer, 39 drinking water supply at Koucha 3998/DP 01/11/2019 200000 199900 199900 100 Yes 2019 Ausgram- II P.S. Adibasipara within Ausgram-II P.S. Asset Handover Report Wanting as Sinking of Submersible pump with 2018 - Executive Officer, per the Clause No. 8 40 drinking water supply at Debsala 4000/DP 01/11/2019 200000 199840 199840 100 Yes 2019 Ausgram- II P.S. under updated Dangapara within Ausgram-II P.S. BEUP Guidelines 2019 Sinking of Submersible pump with drinking water supply at Tapuspure 2018 - Executive Officer, 41 4001/DP 01/11/2019 200000 199980 199980 100 Yes under Debsala G.P. within Ausgram- 2019 Ausgram- II P.S. II P.S.

Total 4000000 3949553 3949553

236 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Executive Purchase of Hearse Van (Sabobahi 2019 - Officer, 42 Jaan) for I.C Chhora Police Station 2934/DP 09/11/2020 800000 800000 800000 100 Yes 2020 Ausgram- II under Ramnagar G.P. P.S.

Total 800000 800000 800000

Upgradation of Earthen Stadium at Executive 2020 - 43 Jadabganj Bonpara at Dignagar-II 2547/DP 30/09/2020 299100 Officer, 299100 224325 100 Yes 2021 G.P. within Ausgram-I P.S. Ausgram- I P.S. Asset Handover Report Wanting as Constn.. of Dinning Shed at Jaganath Executive per the Clause No. 8 2020 - 44 Masir Bari at Dignagar-I within 2547/DP 30/09/2020 279160 Officer, 279160 209370 100 Yes under updated BEUP 2021 Ausgram-I P.S. Ausgram- I P.S. Guidelines 2019

Executive Electrical works at Panchayat Samity 2020 - 45 2547/DP 30/09/2020 61183 Officer, 61183 45887 100 Yes Store room under Ausgram-I P.S. 2021 Ausgram- I P.S.

Executive Electrification of BNRGSK building 2020 - 46 2547/DP 30/09/2020 329010 Officer, 329010 246758 100 Yes within Ausgram-I P.S. 2021 Ausgram- I P.S.

237 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted

Installation of pipe line and sanitary Executive 2020 - 47 plumbing works Panchayat Samity 2547/DP 30/09/2020 88538 Officer, 88538 66404 100 Yes 2021 Store room under Ausgram-I P.S. Ausgram- I P.S.

Upgradation and extension work of Asset Handover Executive Report Wanting as Chandni ICDS with boundary wall at 2020 - 48 2547/DP 30/09/2020 209475 Officer, 209475 157106 100 Yes per the Clause No. 8 Dignagar-I G.P. withinAusgram-I 2021 Ausgram- I P.S. under updated BEUP P.S. Guidelines 2019

Upgradation and renovation work of Executive 2020 - 49 Panchayat Samity Store room under 2547/DP 30/09/2020 349170 Officer, 349170 261878 100 Yes 2021 Ausgram-I P.S. Ausgram- I P.S.

Total 1615636 1615636 1211728

Grand Total 18447830 18248828 18248828

238 ONGOING SCHEMES

239 ABHEDANANDA THANDER, HON'BLE MLA 273 AUSGRAM (SC) A.C. Sanction UC Present Status Present Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submitt for the Month of Status for the No. Sanction Sanction Agency Released Utilized Progress No ed June Month of July Constn.. of Community Hall at Executive 100% work 100% work 2018 - completed, final UC completed. UC 1 Jamtara Gramin Club at Bhalki 2151/DP 20/08/2019 598800 Officer, 598800 450000 75 Yes st 2019 will be submitted 1 will be sent G.P. under Ausgram-II P.S Ausgram- II P.S. week of July shortly. Solar system at Sajal Dhara Executive 100% work 100% work prakalpa at Kota Raghunathpur 2018 - completed, final UC completed. UC 2 3718/DP 24/09/2019 336000 Officer, 336000 252000 75 Yes st at Kota G.P. under Ausgram-II 2019 will be submitted 1 will be sent Ausgram- II P.S. PS (1st Phase) week of July shortly. Solar system at Sajal Dhara Executive 100% work 100% work prakalpa at Kota Raghunathpur 2018 - completed, final UC completed. UC 3 3717/DP 24/09/2019 336000 Officer, 336000 252000 75 Yes st (Phase-II) at Kota GP under 2019 will be submitted 1 will be sent Ausgram- II P.S. Ausgram-II PS week of July shortly. Constn.. of Rest room at Maa Executive 100% work 100% work 2018 - completed, final UC completed. UC 4 Mati Park under Eral GP within 3764/DP 27/09/2019 499500 Officer, 499500 375000 75 Yes st 2019 will be submitted 1 will be sent Ausgram-II PS Ausgram- II P.S. week of July shortly. Total 1770300 1770300 1329000 Constn.. of workshop for Executive 100% works 100% work Adibasi at Hatmadhabpur under 2019 - completed, UC completed. Final 5 2194/DP 09/09/2020 219000 Officer, 164250 164250 75 Yes Ramnagar G.P. within 2020 received on UC will be sent Ausgram- II P.S. Ausgram-II 21.06.2021 shortly. Construction of a room with AC Executive 100% works 100% work for Dead body preservation at 2019 - Completed, UC completed. Final 6 2194/DP 09/09/2020 227030 Officer, 227030 170273 75 Yes Jamtara BPHC within Ausgram- 2020 received on UC will be sent Ausgram- II P.S. II P.S. 21.06.2021 shortly. 240 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month for the Month of No. Sanction Sanction Agency Released Utilized Progress No ted of June July Construction of Community Executive 100% works 100% work Hall at Pratappur Dangapara 2019 - Completed, UC completed. Final 7 2194/DP 09/09/2020 740000 Officer, 555000 555000 75 Yes under Bhalki G.P. within 2020 received on UC will be sent Ausgram- II P.S. Ausgram-II P.S. 21.06.2021 shortly. Constn. of shed at Genrar Executive 100% works 100% work Pirtala under Amarpur G.P. 2019 - Completed, UC completed. Final 8 2194/DP 09/09/2020 248400 Officer, 186300 186300 75 Yes (Phase-I) within Ausgram-II 2020 received on UC will be sent Ausgram- II P.S. P.S. 21.06.2021 shortly. Constn. of shed at Genrar Executive 100% works 100% work Pirtala under Amarpur G.P. 2019 - Completed, UC completed. Final 9 2194/DP 09/09/2020 248400 Officer, 186300 186300 75 Yes (Phase-II) within Ausgram-II 2020 received on UC will be sent Ausgram- II P.S. P.S. 21.06.2021 shortly. Total 1682830 1318880 1097873 100% work Upgradation and extension Executive completed, final UC 2020 - Physically 70% 10 work at Chandni at Dignagar-I 2547/DP 30/09/2020 448785 Officer, 448785 336589 75 Yes will be submitted 2021 completed G.P. within Ausgram-I P.S. Ausgram- I P.S. after getting the balance fund 100% work Upgradation of Sanhati Executive completed, final UC 2020 - Physically 70% 11 Mancha (Meeting Hall) at 2547/DP 30/09/2020 299250 Officer, 299250 224438 75 Yes will be submitted 2021 completed Ausgram-I (1st Phase) Ausgram- I P.S. after getting the balance fund 100% work Upgradation of Sanhati Executive completed, final UC 2020 - Physically 70% 12 Mancha (Meeting Hall) at 2547/DP 30/09/2020 299160 Officer, 299160 224370 75 Yes will be submitted 2021 completed Ausgram-I (2nd Phase) Ausgram- I P.S. after getting the balance fund 241 Sanction UC Present Status Present Status Sl. Date of Amount Executing Amount Amount Physical Name of the Scheme Year Order Submit for the Month of for the Month No. Sanction Sanction Agency Released Utilized Progress No ted June of July 100% work Upgradation of Sanhati Executive completed, final 2020 - Physically 70% UC will be 13 Mancha (Meeting Hall) at 2547/DP 30/09/2020 249375 Officer, 249375 187031 75 Yes 2021 completed submitted after Ausgram-I (3rd Phase) Ausgram- I P.S. getting the balance fund 100% work Electrification of Sanhati Executive completed, final 2020 - Physically 70% UC will be 14 Mancha (Meeting Hall) 2547/DP 30/09/2020 79784 Officer, 79784 59838 75 Yes 2021 completed submitted after withinin Ausgram-I P.S. Ausgram- I P.S. getting the balance fund Total 1376354 1376354 1032266

Grand Total 5487184 5225484 3623389

242 Hon’ble M.L.A. Shri Alok Kumar Majhi MLA 274 GALSI (SC) A.C.

243 COMPLETED SCHEMES

244 ALOK KUMAR MAJHI, HON'BLE MLA 274 GALSI (SC) A.C.

UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn. of CC Road at 2016 - Executive Officer, 1 Mollapara approach road of 2607/DP 09/11/2016 300000 300000 300000 100 Yes 2017 Galsi- I P.S. Kabarsthan at Budbud Constn. of Concrete Road approach to 2016 - Executive Officer, 2 2607/DP 09/11/2016 250000 250000 250000 100 Yes Narayanpur Junior High School 2017 Galsi- I P.S. Asset Handover Constn. of CC Road Gopaleswar Tala Report Received as 2016 - Executive Officer, per the Clause No. 8 3 to Ajay Mondal house of 2607/DP 09/11/2016 300000 300000 300000 100 Yes 2017 Galsi- I P.S. under updated Ramgopalgram 1st Phase BEUP Guidelines Constn. of Concrete road at 2016 - Executive Officer, 2019 4 Joykrishnapur Bagdipara at Kurkuba 2607/DP 09/11/2016 300000 300000 300000 100 Yes 2017 Galsi- II P.S. G.P. Constn. of BPHC Gate of Adrahati at 2016 - Executive Officer, 5 2607/DP 09/11/2016 200000 158554 158554 100 Yes Adrahati G.P. 2017 Galsi- II P.S. Asset Handover Report Wanting as Constn. of ACR at Basudebpur Upper 2016 - Executive Officer, per the Clause No. 8 6 2645/DP 11/11/2016 500000 500000 500000 100 Yes Primary School 2017 Kanksa P.S. under updated BEUP Guidelines 2019 Asset Handover Constn. of Cycle Stand at Report Received as 2016 - Executive Officer, per the Clause No. 8 7 Ramgopalpur High School at Lowa 2844/DP 05/12/2016 200000 200000 200000 100 Yes 2017 Galsi- I P.S. under updated Ramgopalpur High School BEUP Guidelines 2019 245 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ted Asset Handover Report Executive Constn. of Open Stage at Paraj 2016 - Wanting as per the Clause 8 2844/DP 05/12/2016 200000 Officer, 200000 200000 100 Yes HBM High School 2017 No. 8 under updated BEUP Galsi- I P.S. Guidelines 2019

Constn. of Boundary Wall new Executive 2016 - 9 Setup Ramgopalpur Girls High 2844/DP 05/12/2016 250000 Officer, 250000 250000 100 Yes 2017 School Galsi- I P.S.

Executive Constn. of Cremation Shed at 2016 - 10 2844/DP 05/12/2016 250000 Officer, 250000 250000 100 Yes Nurkona Cremation Ground 2017 Galsi- I P.S.

Executive Constn. of Cycle Stand at Jamdaha 2016 - 11 2844/DP 05/12/2016 200000 Officer, 200000 200000 100 Yes School of Bidbihar G.P. 2017 Asset Handover Report Kanksa P.S. Received as per the Clause No. 8 under updated BEUP Constn. of ACR with Cycle Stand at Executive Guidelines 2019 2016 - 12 Pursa High School at Potna Pursa 660/DP 02/03/2017 650000 Officer, 650000 650000 100 Yes 2017 G.P. Galsi- I P.S.

Constn. of Cremation Shed at Executive 2016 - 13 Pandudaha Samsan Ghat at Lowa 660/DP 02/03/2017 250000 Officer, 250000 250000 100 Yes 2017 Krishnapur Galsi- I P.S.

Executive Repair of Puratan Gram High 2016 - 14 660/DP 02/03/2017 100000 Officer, 100000 100000 100 Yes School Building at Serorai G.P. 2017 Galsi- I P.S. 246 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn. of Sishu Uddyan Gate of 2016 - Executive Officer, 15 884/DP 22/03/2017 150000 150000 150000 100 Yes Galsi Bazar at Galsi G.P. 2017 Galsi- II P.S. Constn. of CC Road from G.Mondal house to N. Bairagya 2016 - Executive Officer, 16 1000/DP 30/03/2017 250000 250000 250000 100 Yes house to Ramgopalpur Ghosh Para 2017 Galsi- I P.S. of Lowa Ramgopalpur 2nd phase Constn. of Cremation Shed at 2016 - Executive Officer, 17 Mollasarul Malgore Samsan Ghat 1085/DP 06/04/2017 250000 250000 250000 100 Yes Asset Handover Report 2017 Galsi- I P.S. at Serorai G.P. Received as per the Clause No. 8 under Constn. of Atchala at 2016 - Executive Officer, 18 1085/DP 06/04/2017 250000 250000 250000 100 Yes updated BEUP Samshanghat at Mankar G.P. 2017 Galsi- I P.S. Guidelines 2019 Constn. of Cremation Shed at 2016 - Executive Officer, 19 1085/DP 06/04/2017 250000 250000 250000 100 Yes Budbud Sadhunagar Samsanghat 2017 Galsi- I P.S. Constn.. of atchala at Uchchagram 2016 - C- Executive Officer, 20 G.P under Galsi- I P.SD (2nd 24/05/2017 250000 250000 250000 100 Yes 2017 1509/DP Galsi- I P.S. Phase) Constn. of Gate of Galsi Samsan 2016 - Executive Officer, 21 1975/DP 13/07/2017 150000 99611 99611 100 Yes Ghat of Galsi at Galsi G.P. 2017 Galsi- II P.S. Asset Handover Report Constn. of Atchala at Beldanga Executive Officer, Wanting as per the 22 792/DP 14/03/2021 250000 203200 203200 100 Yes Clause No. 8 under Adibasipara under Kanksa Kanksa P.S. 2016 - updated BEUP 2017 Guidelines 2019 Asset Handover Report Constn. of Cremation shed at Executive Officer, Received as per the 23 Railpar Canel Samsanghat at 792/DP 14/03/2021 250000 160500 160500 100 Yes Clause No. 8 under Kanksa P.S. 2016 - updated BEUP 2017 Guidelines 2019 Total 6000000 5771865 5771865 247 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Submit No. Order No Sanction Sanction Agency Released Utilized Progress Status ted Constn.. of Baitarani scheme at Exe. Engg. PWD Galsi-I and Galigram under 2017 - 24 1761/DP 21/06/2017 890000 (Social Sector), 857672 857672 100 Yes Uchchagram G.P. (Jl.-54, Plot.-5422, 2018 Burdwan. 11502) Constn.. of Baitarani scheme at Exe. Engg. PWD 2017 - 25 Galsi-I and Mouza, 1761/DP 21/06/2017 890000 (Social Sector), 857672 857672 100 Yes 2018 (Jl.-36, Plot.-310, Kh.-184,238) Burdwan.

Constn.. of Baitarani scheme at Exe. Engg. PWD 2017 - 26 Galsi-I and Ramgopalpur (Jl.-27, 1761/DP 21/06/2017 890000 (Social Sector), 857672 857672 100 Yes 2018 Plot.-496) Burdwan. Asset Handover Report Received as Constn.. of Baitarani scheme at Exe. Engg. PWD 2017 - per the Clause No. 8 27 Galsi-I and Ghagra Mouza (Jl.-30, 1761/DP 21/06/2017 890000 (Social Sector), 857672 857672 100 Yes 2018 under updated Plot.-2186, 2313) Burdwan. BEUP Guidelines Executive 2019 Constn. of submersible for water 2017 - 28 2291/DP 18/08/2017 100000 Officer, Galsi- I 100000 100000 100 Yes resource at Mankar High School 2018 P.S.

Constn. of submersible for water Executive 2017 - 29 resource at New Setup Ramgopalpur 2291/DP 18/08/2017 100000 Officer, Galsi- I 100000 100000 100 Yes 2018 Girls High School P.S.

Constn. of submersible for water Executive 2017 - 30 resource at Budbud Mahakhali High 2291/DP 18/08/2017 100000 Officer, Galsi- I 100000 100000 100 Yes 2018 School P.S.

248 UC Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Asset Handover Status No. Order No Sanction Sanction Agency Released Utilized Progress ted

Constn. of submersible for Executive Asset Handover Report water resource at Lowa 2017 - Wanting as per the Clause No. 31 2291/DP 18/08/2017 100000 Officer, 100000 100000 100 Yes School at Lowa Ramgopal 2018 8 under updated BEUP Galsi- I P.S. G.P. Guidelines 2019

Constn. of Cremation Shed at Executive 2017 - 32 Simasini Samsanghat at 2772/DP 30/10/2017 300000 Officer, 300000 300000 100 Yes 2018 Serorai G.P. Galsi- I P.S. Asset Handover Report Received as per the Clause No. 8 under updated BEUP Constn. of concrete Ghat at Executive 2017 - Guidelines 2019 33 Block Krishak Bazar Farm 3228/DP 06/12/2017 300000 Officer, 300000 300000 100 Yes 2018 Pond of Mankar G.P. Galsi- I P.S.

Exe. Eng. Constn. of Baitoroni Scheme Asset Handover Report 2017 - 215/DPC/PSC Asansol Divn Wanting as per the Clause No. 34 at Kanksa Block Mouza 22/12/2017 890000 857672 857672 100 Yes 2018 HM Social Sector 8 under updated BEUP Bonkati Jl No. 33 plot No 371 PW Dte Guidelines 2019 Constn. of Cycle Stand at Executive 2017 - 35 Mankar High School at 1332/DP 18/07/2018 250000 Officer, 250000 250000 100 Yes 2018 Asset Handover Report Mankar G.P. Galsi- I P.S. Received as per the Clause Upgradation of Morum Road Executive No. 8 under updated BEUP 2017 - Guidelines 2019 36 and Constn. Concrete road 1389/DP 26/07/2018 200000 Officer, 145340 145340 100 Yes 2018 from canal Bandh to Ashram Galsi- II P.S.

Total 5900000 5683700 5683700

249 Sanction UC Sl. Date of Amount Executing Amount Amount Physical Asset Handover Name of the Scheme Year Order Submit No. Sanction Sanction Agency Released Utilized Progress Status No ted Constn.. of Corrugated Shed of Executive Asset Handover Report 2018 - Wanting as per the Clause 37 Ekalavya Model Residential School 132/DP 11/06/2019 1000000 Officer, Kanksa 804006 804006 100 Yes 2019 No. 8 under updated BEUP under Kanksa G.P. P.S. Guidelines 2019 Constn.. of pucca ghat at Executive 2018 - 38 Brindabanpur, Moralpukur at 2282/DP 28/08/2019 88842 Officer, Galsi- 62063 62063 100 Yes 2019 Asset Handover Report Kurkuba G.P. under Galsi-II P.S. II P.S. Received as per the Clause Constn.. of concrete cullvert with Executive No. 8 under updated BEUP 2018 - 39 Hume Pipe at Pilgram Manasa Tala 2282/DP 28/08/2019 88904 Officer, Galsi- 63740 63740 100 Yes Guidelines 2019 2019 of Kurkuba G.P. under Galsi-II P.S. II P.S. Total 1177746 929809 929809 Constn.. of 10mtr. Mini High Mast 2019 - Prodhan, 40 Light at Joykrishnapur Paschimpara 4306/DP 28/11/2019 225000 225000 225000 100 Yes 2020 Kurkuba G.P. Kalitala Constn.. of 10mtr. Mini High Mast 2019 - Prodhan, Asset Handover Report 41 Light at Askaran Masjid tala plot 4306/DP 28/11/2019 225000 225000 225000 100 Yes Received as per the Clause 2020 Kurkuba G.P. no. 568 No. 8 under updated BEUP Guidelines 2019 Constn.. of 10mtr. Mini High Mast 2019 - Prodhan, Galsi 42 Light at near Uttar Galsi Cannel 208/DP 16/01/2020 224750 224750 224750 100 Yes 2020 G.P. Bridge 3628 Constn.. of 10mtr. Mini High Mast 2019 - Prodhan, Galsi 43 208/DP 16/01/2020 224800 224800 224800 100 Yes Light at Galsi Sahapirtala plot-1041 2020 G.P. Constn. of 10mtr. Mini High Mast Asset Handover Report 2019 - Prodhan, Galsi Wanting as per the Clause 44 Light at Galsi Gargeshwar tala plot 208/DP 16/01/2020 224800 224800 224800 100 Yes 2020 G.P. No. 8 under updated BEUP 6282/7065 Guidelines 2019 Total 1124350 1124350 1124350 Grand Total 14202096 13509724 13509724 250 ONGOING SCHEMES

251 ALOK KUMAR MAJHI, HON'BLE MLA 274 GALSI (SC) A.C.

UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submitt for the Month for the Month No. Order No Sanction Sanction Agency Released Utilized Progress ed of June of July 100% work Constn. of boundary wall at Executive Physically 100 % 2018 - completed, UC 1 Dayalpur Graveyard at Galsi 2537/DP 21/11/2018 200000 Officer, 150000 150000 75 Yes completed, UC 2019 submitted G.P. under Galsi-II P.S. Galsi- II P.S. sent shortly. Constn. of boundary wall at 100% work Executive Physically 100 % Deypara Graveyard at 2018 - completed, final 2 2537/DP 21/11/2018 210000 Officer, 208215 157500 75 Yes completed, UC Kurkuba G.P. under Galsi-II 2019 UC will be Galsi- II P.S. sent P.S. received shortly. Constn. of cement concrete 100% work Executive Physically 100 % road from Kurie Sasan ghat to 2018 - completed, 2nd 3 2537/DP 21/11/2018 150000 Officer, 112500 112500 75 Yes completed, UC Sasan Chulli at Galsi G.P. 2019 installment to be Galsi- II P.S. sent under Galsi-II P.S. released. 100% work Upgradation of road and slab Executive Physically 100 % 2018 - completed, 2nd 4 NH2 to Amit Roy house at 2537/DP 21/11/2018 55000 Officer, 41250 41250 75 Yes completed, UC 2019 installment to be Galsi G.P. under Galsi-II P.S. Galsi- II P.S. sent released. 100% work Constn. of Boundary wall at Executive Physically 100 % 2018 - completed, final 5 Darbarpur F.P. School at Galsi 2537/DP 21/11/2018 200000 Officer, 198300 150000 75 Yes completed, UC 2019 UC will be G.P. under Galsi-II P.S. Galsi- II P.S. sent received shortly. Installation of CCTV from 100% work NH2 to Galsi Bazar (Fakir Ch. Executive Physically 100 % 2018 - completed, 2nd 6 Roy Sarani) via Galsi Sabji 132/DP 11/01/2019 225000 Officer, 168750 168750 75 Yes completed, UC 2019 installment to be Market at Galsi under Galsi-II Galsi- II P.S. sent released. P.S. 252 UC Present Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Status for the for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted Month of June July Installation of High Mast Light 100% work Executive Physically 100 % on plot no. 8116 mouza-Mankar 2018 - completed, 1st phase 7 824/DP 04/03/2020 379850 Officer, 379850 0 0 No completed, UC to near Galsi-I BDO office within 2019 UC will be received Galsi- I P.S. be sent Galsi-I P.S. shortly. Installation of High Mast Light 100% work Executive Physically 100 % on plot no. 613/3913 mouza- 2018 - completed, 1st phase 8 824/DP 04/03/2020 379850 Officer, 379850 0 0 No completed, UC to Sukdal near Budbud Police 2019 UC will be received Galsi- I P.S. be sent Station within Galsi-I P.S. shortly. Constn. of Electrical Executive 100% work submersible pump at 2018 - completed, 1st UC 9 2756/DP 29/06/2021 85005 Officer, 63754 0 0 No Nil Bahirghanya Masjid under 2019 will be received Galsi- II P.S. Galsi-I P.S. shortly. Constn. of concrete cement road Executive Work not started, 2018 - 10 at Deul Park at Bonkati G.P. 2813/DP 02/07/2021 205323 Officer, 153992 0 0 No Nil work order just 2019 under Kanksa P.S. Kanksa P.S. issued. Total 2090028 1856461 780000

1 No of 10 Mtr Mini High Mast 100% work 100% work Executive completed UC Light near Puratangram Bus 2019- completed, final 11 559/DP 08/02/2021 224977 Officer, 224977 168733 75 Yes will be submitted Stand within Uchchagram G.P. 2020 UC will be Galsi- I P.S. after receiving of under Galsi-I P.S. fund received shortly.

100% work 100% work 1 No of 10 Mtr Mini High Mast Executive completed UC 2019- completed, 1st 12 Light near Paraj Hattala under 558/DP 08/02/2021 224977 Officer, 168733 0 0 No will be submitted 2020 phase UC will be Paraj GP Galsi- I P.S. after receiving of fund received shortly.

253 UC Present Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Status for the for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted Month of June July 1 No of 10 Mtr Mini High Mast 100% work 100% work Executive completed UC Light near Mankar Taxi Stand 2019- completed, final 13 559/DP 08/02/2021 224977 Officer, 224977 168733 75 Yes will be submitted within Mankar G.P. under 2020 UC will be Galsi- I P.S. after receiving of Galsi-I P.S. fund received shortly. 1 No of 10 Mtr Mini High Mast 100% work 100% work Light near Krishnarampur Executive completed UC 2019- completed, final 14 Football Ground within Lowa 559/DP 08/02/2021 224977 Officer, 224977 168733 75 Yes will be submitted 2020 UC will be Krishnarampur G.P. under Galsi- I P.S. after receiving of received shortly. Galsi-I P.S. fund 100% work 100% work Executive completed UC 1 No of 10 Mtr Mini High Mast 2019- completed, 1st 15 558/DP 08/02/2021 224977 Officer, 168733 0 0 No will be submitted Light near Kasba Shibtala 2020 phase UC will be Galsi- I P.S. after receiving of fund received shortly. 100% work 100% work 1 No of 10 Mtr Mini High Mast Executive completed UC 2019- completed, 1st 16 Light near Rampur Math Lowa 558/DP 08/02/2021 224977 Officer, 168733 0 0 No will be submitted 2020 phase UC will be Ramgopalpur GP Galsi- I P.S. after receiving of fund received shortly. 100% work 100% work 1 No of 10 Mtr Mini High Mast Executive completed UC 2019- completed, 1st 17 Light near Budbud Mahakali 558/DP 08/02/2021 379920 Officer, 284940 0 0 No will be submitted 2020 phase UC will be High School Galsi- I P.S. after receiving of fund received shortly. 1 No of 10 Mtr Mini High Mast 100% work 100% work Executive completed UC Light near Busstand 2019- completed, final 18 559/DP 08/02/2021 224977 Officer, 168733 0 0 No will be submitted within Chaktentul G.P. under 2020 UC will be Galsi- I P.S. after receiving of Galsi-I P.S. fund received shortly. 254 UC Present Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Status for the for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted Month of June July 1 No of 10 Mtr Mini High Mast 100% work 100% work Executive completed UC Light near Goligram Chabbish 2019- completed, final 19 559/DP 08/02/2021 224977 Officer, 224977 168733 75 Yes will be submitted Prahar tala within Uchchagram 2020 UC will be Galsi- I P.S. after receiving of G.P. under Galsi-I P.S. fund received shortly. 1 No of 10 Mtr Mini High Mast 100% work 100% work Executive completed UC Light near Serorai Godown 2019- completed, final 20 559/DP 08/02/2021 224977 Officer, 224977 168733 75 Yes will be submitted within Serorai G.P. under Galsi- 2020 UC will be Galsi- I P.S. after receiving of I P.S. fund received shortly. 100% work 100% work 1 No of 10 Mtr Mini High Mast Executive completed UC 2019- completed, 1st 21 Light near Shimnori Morth 558/DP 08/02/2021 224977 Officer, 168733 0 0 No will be submitted 2020 phase UC will be under Paraj GP Galsi- I P.S. after receiving of fund received shortly. 100% work 100% work 1 No of 10 Mtr Mini High Mast Executive completed UC 2019- completed, 1st 22 Light near Silya Park Lowa 558/DP 08/02/2021 224977 Officer, 168733 0 0 No will be submitted 2020 phase UC will be Ramgopalpur GP Galsi- I P.S. after receiving of fund received shortly. 1 No of 10 Mtr Mini High Mast 100% work 100% work Executive completed UC Light near Uchchagram More 2019- completed, final 23 559/DP 08/02/2021 224977 Officer, 224977 168733 75 Yes will be submitted within Uchchagram G.P. under 2020 UC will be Galsi- I P.S. after receiving of Galsi-I P.S. fund received shortly. 100% work 100% work 1 No of 10 Mtr Mini High Mast Executive completed UC 2019- completed, 1st 24 Light near Pursa Hospital under 558/DP 08/02/2021 379920 Officer, 284940 0 0 No will be submitted 2020 phase UC will be Potna Porsa GP Galsi- I P.S. after receiving of fund received shortly. 255 UC Present Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit Status for the for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted Month of June July

West Bengal Supply and installation 1 no. 100% work Agro 12.5 Mini High Mast Light near 2019- completed, 1st 25 2621/DP 02/06/2021 400000 Industries 300000 0 0 No Nil Panagarh Bazar Rail par under 2020 phase UC will be Corporation Kanksa P.S. received shortly. Ltd.

West Bengal Supply and installation 1 no. 100% work Agro 12.5 Mini High Mast Light near 2019- completed, 1st 26 2621/DP 02/06/2021 400000 Industries 300000 0 0 No Nil Gurudwara Panagarh Bazar 2020 phase UC will be Corporation under Kanksa P.S. received shortly. Ltd.

West Bengal Supply and installation 1 no. 100% work Agro 12.5 Mini High Mast Light near 2019- completed, 1st 27 2621/DP 02/06/2021 400000 Industries 300000 0 0 No Nil Daan Baba Mazar under 2020 phase UC will be Corporation Kanksa P.S. received shortly. Ltd.

Supply and Installation i no. 60% work Mini High Mast Light near joy 2019- Prodhan, completed, UC 28 2815/DP 02/07/2021 224950 168712 0 0 No Nil Krishnapur Kalitala Purba Para 2020 Kurkuba G.P. will be received under Galsi-I P.S. shortly.

4884514 4057096 1181131

256 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month of No. Order No Sanction Sanction Agency Released Utilized Progress ted of June July Supply and Inst 1 No of 10 Mtr Executive 100% work 100% work 2020- completed UC will completed, final UC 29 Mini High Mast Light Near 698/DP 15/02/2021 224977 Officer, 168733 0 0 No 2021 be submitted after will be received 1st uchhagram Shivtala Galsi- I P.S. receiving of fund week of August. Supply and Inst 1 No of 12.5 Executive 100% work 100% work 2020- completed UC will completed, final UC 30 Mtr Mini High Mast Light 698/DP 15/02/2021 399960 Officer, 299970 0 0 No 2021 be submitted after will be received 1st Near Mallasarul Shib Mandir Galsi- I P.S. receiving of fund week of August. Supply and Inst 1 No of 12.5 Executive 100% work 100% work 2020- completed UC will completed, final UC 31 Mtr Mini High Mast Light 698/DP 15/02/2021 399960 Officer, 299970 0 0 No 2021 be submitted after will be received 1st Near Korkona Barakalitala Galsi- I P.S. receiving of fund week of August. Supply and Inst 1 No of 10 Mtr Executive 100% work 100% work Mini High Mast Light Supply 2020- completed UC will completed, final UC 32 698/DP 15/02/2021 149985 Officer, 112489 0 0 No and Inst 10 Nos of Solar Street 2021 be submitted after will be received 1st Galsi- I P.S. Light near Sondalpur Janasthan receiving of fund week of August. Supply and Inst 1 No of 10 Mtr Executive 100% work 100% work Mini High Mast Light Supply 2020- completed UC will completed, final UC 33 698/DP 15/02/2021 299970 Officer, 224978 0 0 No and Inst 10 Nos of Solar Street 2021 be submitted after will be received 1st Galsi- I P.S. Light near Kondaipur receiving of fund week of August.

Supply and Inst 1 No of 10 Mtr Executive 100% work 100% work 2020- completed UC will completed, final UC 34 Mini High Mast Light Sihigram 698/DP 15/02/2021 224977 Officer, 168733 0 0 No 2021 be submitted after will be received 1st Durga Mandir Galsi- I P.S. receiving of fund week of August.

Supply and Inst 1 No of 10 Mtr Executive 100% work 100% work 2020- completed UC will completed, final UC 35 Mini High Mast Light Near 698/DP 15/02/2021 224977 Officer, 168733 0 0 No 2021 be submitted after will be received 1st Rokhona Chobbish Prohartala Galsi- I P.S. receiving of fund week of August. 257 UC Present Status Present Status Sl. Sanction Date of Amount Executing Amount Amount Physical Name of the Scheme Year Submit for the Month for the Month No. Order No Sanction Sanction Agency Released Utilized Progress ted of June of July 100% work 100% work Supply and Inst 1 No of 10 Mtr Executive completed, final 2020- completed UC will Mini High Mast Light Near 698/DP 15/02/2021 224977 Officer, Galsi- I 168733 0 0 No UC will be 36 be submitted after 2021 received 1st week Bodutia More P.S. receiving of fund of August. 100% work 100% work Supply and Inst 1 No of 10 Mtr Executive completed, final 2020- completed UC will Mini High Mast Light Kuraj 698/DP 15/02/2021 224977 Officer, Galsi- I 168733 0 0 No UC will be 37 be submitted after 2021 received 1st week Kamaleswar tala P.S. receiving of fund of August. 100% work 100% work Supply and Inst 1 No of 10 Mtr Executive completed, final 2020- completed UC will Mini High Mast Light Jhurul 698/DP 15/02/2021 224977 Officer, Galsi- I 168733 0 0 No UC will be 38 be submitted after 2021 received 1st week Vill Durgatala P.S. receiving of fund of August. 100% work 100% work Supply and Inst 1 No of 10 Mtr Executive completed, final 2020- completed UC will Mini High Mast Light Near 698/DP 15/02/2021 224977 Officer, Galsi- I 168733 0 0 No UC will be 39 be submitted after 2021 received 1st week Jalpaiguri P.S. receiving of fund of August. 100% work Constn. of Cement concrete Executive Physically 100 % 2020- completed, 1st road at Galsi College under 781/DP 21/02/2021 200010 Officer, Galsi- 150008 0 0 No completed, UC to 40 phase UC will be 2021 be sent Galsi GP II P.S. received shortly.

Building Repair of Kanksa Executive Work not started, 41 Swasthakendra under Kanksa 2814/DP 02/07/2021 284999 Officer, Kanksa 213749 0 0 No Nil work order just P.S. P.S. issued.

Total 3309723 2482295 0

Grand Total 11049265 8395852 1961131 258 Thank You