E1678 V2

Public Disclosure Authorized Mid-term Adjustment for WB Financed Urban Environment Improvement Project

Public Disclosure Authorized Report on Environment Management Plan

Public Disclosure Authorized

WB Financed Han River Basin Pollution Control PMO

Public Disclosure Authorized The JV of Xinbao Science & Technology Co. Ltd and University

January 2014

Table of Content

Chapter I Summary ...... 3

1.1 Project Mid-term Adjustment Introduction ...... 3

1.2 EMP Adjustment Basis ...... 5

1.2.1 Relevant Laws and Regulations ...... 5

1.2.2 Regulations of Departments and Local Government ...... 7

1.2.3 Main Technical Specifications ...... 8

1.2.4 Main Environmental Standards ...... 10

1.2.5 Other Materials ...... 12

1.3 Environment Impact Scope Variation Status After Project Mid-term Adjustment

...... 13

1.3.1 Hanchuan Sewage Collection Pipeline Network Project ...... 13

1.3.2 Shayang Solid Waste Project ...... 23

1.3.3 Hanchuan Solid Waste Project ...... 28

1.4 Environment Protection Targets Variation Status After Mid-term Adjustment .. 32

1.4.1 Environment Protection Targets Variation Status of Hanchuan Sewage

Collection Pipeline Network ...... 32

1.4.2 Environment Protection Targets Variation Status of Shayang Solid Waste

Project ...... 35

1.4.3 Environment Protection Targets Variation Status of Hanchuan Solid

Waste Project ...... 35

1.5 Environment Management Organization Variation Status After Mid-term

Adjustment ...... 35

1

1.5.1 Environment Management Organization of Hanchuan Sewage Collection

Pipeline Network ...... 35

1.5.2 Environment Management Organization of Shayang Solid Waste Project

...... 37

1.5.3 Environment Management Organization of Hanchuan Solid Waste

Project ...... 39

1.6 WB Security Guarantee Policy...... 41

Chapter II Mitigation Measures ...... 42

2.1 Mitigation Measures for Hanchuan Sewage Collection Pipeline Network and

Pump Station ...... 42

2.2 Mitigation Measures of Solid Waste Landfill ...... 42

Chapter III Monitoring Scheme ...... 44

3.1 Monitoring Purpose ...... 44

3.2 Environment Monitoring Plan ...... 44

Chapter IV Training Plan ...... 46

4.1 Training Purpose ...... 46

4.2 Training Objects ...... 47

Chapter V Information Disclosure and Public Participation ...... 49

5.1 Information Disclosure ...... 49

5.2 Public Participation ...... 51

Chapter VI Conclusion ...... 53

2

Chapter I Summary

1.1 Project Mid-term Adjustment Introduction

World Bank Financed Han River Urban Environment Improvement

Project was listed in Three Year Plan of WB Financed Project from 2006 to 2008 by National Development and Reform Commission in 2005 and this project was implemented in 2008. The objective of this project is listed as the following: With the sewage collection and treatment projects and solid waste management projects constructed in the selected cities and counties along Hubei Han River Basin to reduce the waste water and solid waste pollution, strengthen the institutional reform and capacity construction and water pollution control capacity of the utility institutions of the relative cities and counties. HUEIP contains 15 subprojects locate in Hanchuan, , Shayang, , Xiaochang, Dawu, , xiangfang (renamed as on December 9th, 2010), and Yunmeng 9 cities/counties. The main construction contents include urban waste water treatment plant, sewage collection pipeline network and solid waste treatment, including 2 sewage collection pipeline network projects (Xiangfan and Honghu), 5 waste water treatment plants and sewage collection pipeline network projects (Tianmen, Shayang, Xiaochang, Yunmeng and Hanchuan), 7 solid waste landfill projects (Shayang , Hanchuan, Yunmeng, Xiaochang, Honghu, Dawu and Danjiangkou ) and one industrial pollution improvement project. The total investment of this project is RMB

3

1,142,115,100.00Yuan, and the WB loan is 84 million USD which accounts for 52% of the total investment ( the exchange rate is 1:7.1 during project appraisal stage). The project appraisal was completed by WB on July 26th, 2007, the Project Loan Legal Document was signed on July 3rd, 2008 and the WB Loan effective date is September 16th, 2008. The loan payback period is 26 years with five-year grace period. HUEIP is under full implementation stage since 2009. According to WB loan Project Consultant Selecting Guideline and QBS Procurement method, the JV of Hubei Xinbao Science & Technology Co. Ltd and Wuhan University was entrusted by PMO of HUEIP to undertake the external environment monitoring for this project. The consulting service contact was signed in September 2011. The external monitoring work for EMP implementation status will be conducted in line with contract, WB EMP and national laws and regulations during the project implementation stage. Through the mid-term adjustment, the construction contents of 14 subprojects in 9 cities/counties of this project was changed to 11 subprojects in 7 cities/counties( Hanchuan, Honghu, Shayang, Xiaochang, Dawu, Xiangyang and Yunmeng), including 3 sewage collection pipeline network projects (Xiangyang, Hanchuan and Honghu), 2 waste water treatment plants and sewage collection pipeline network projects (Shayang and Yunmeng) and 5 solid waste landfill projects (Shayang, Hanchuan, Xiaochang, Honghu and Dawu). Standard on pollution Control for Solid Waste Landfill (GB16889-2008) was implemented from July 1st,2007, this new standard increased the requirements on leachate discharging compared with GB16889-1997, so Shayang and Hanchuan Solid Waste Landfill Projects must be reformed in line with this new discharging standard. Furthermore,

4

the environmental issues generated from the newly added sewage collection pipeline network project and lifting pump station project of Hanchuan subproject.

Table 1.1-1 Environment Monitoring Variation Before and After Mid-term Adjustment

No. Before Adjustment After Adjustment Note 1 Tianmen Waste Water None Withdraw Treatment Plant and Sewage Collection Pipeline Network Project 2 Xiaochang Waste Water None Withdraw Treatment Plant and Sewage Collection Pipeline Network Project 3 Hanchuan Waste Water None Withdraw Treatment Plant 4 Yunmeng Solid Waste None Withdraw Landfill Project 5 Hanchuan sewage Newly Added The newly added sewage collection pipeline network collection pipeline network project and lifting pump station expansion project and lifting project pump station project, the monitoring work must be conducted. 6 Shayang Solid Waste Update the treatment Comply with the Landfill Project process for the leachate requirements of standard on pollution control for solid waste landfill (GB16889-2008) 7 Hanchuan Solid Waste Update the treatment Comply with the Landfill Project process for the leachate requirements of standard on pollution control for solid waste landfill (GB16889-2008)

1.2 EMP Adjustment Basis

1.2.1 Relevant Laws and Regulations

(1)Environmental Protection Law of the People's Republic of China,

5

on December 26th, 1989;

(2)Regulations on the Administration of Construction Project

Environmental Protection,On November 29th, 1998;

(3)Law of the People's Republic of China on the Prevention and

Control of Water Pollution, On June 1st, 2008;

(4)Rules For The Implementation of the People's Republic of China

Water Pollution Control Act,On March 20th, 2000;

(5)Law of the People's Republic of China on the Prevention and

Control of Atmospheric Pollution,On September 1st, 2000;

(6)The Law of the People's Republic of China on the Prevention and

Control of Environmental Noise Pollution,On March 1st, 1997;

(7)Law of the People's Republic of China on the Prevention and

Control of Pollution by Solid Waste, Amended and went into effective as of April 1st, 2005;

(8)The Law of the People's Republic of China on Promotion of

Cleaner Production, On January 1st, 2003;

(9)The decision of the State Council on Several Issues of the

Environmental Protection(Guo Fa [1996] No.31),On August 3rd, 1996;

(10) Management Regulations of Hubei Province on Environmental

6

Protection,This law went into effect on December 2nd ,1994;

(11)Prevention and Control Act of Hubei Province on Atmospheric

Pollution,( It was adopted by the 31st conference of the Standing

Committee of the 8th People's Congress of Hubei Province on December

3rd, 1997 and modified by the 10th meeting of the Standing Committee of the 10th People's Congress of Hubei Province on July 30th, 2004);

1.2.2 Regulations of Departments and Local Government

⑴ Classified Management Directory on Environmental Protection of

Construction Project, In 2007;

(2)Functional zoning of air quality of Hubei Province,On October 10th,

1998;

(3)Notification about Functional Area Category on the Surface Water

Environment, Forwarded by Provincial People's Government General

Office from the Provincial Environmental Protection Bureau of Hubei

Province, (E Zheng Ban Fa [2000] No. 10), implemented on January 31st,

2000;

(4)To Promulgate and Implement about “the Decision on the Interim

Provisions of the Adjustment to Promote the Industrial Structure”, by the

State Council (Guo Fa [2005] No. 40), On December 2nd, 2005;

7

(5)Decision on Implementing the Scientific Concept of Development and Strengthening Environmental Protection of State Council (Guo Fa

[2005] No. 39), On December 3rd, 2005;

(6)Guo Tu Zi Fa [2006] 296, the Notice on the Promulgation “the

Project Directory for Limiting the Land (2006)” and “The Project

Directory For Banning The Land (2006)”;

(7)Notice on the issuance of “the Interim Measures to public participation in environmental impact assessment by State Environmental

Protection Administration”, (Environment and Development [2006] No.

28), On March 18th, 2006;

(8)Notice to Strengthen Work for the Loans from the International

Financial Construction Project of Environmental Impact Assessment,

(EM [1993] No. 324, text).

1.2.3 Main Technical Specifications

(1)CJJ 17-2004, Waste Sanitary Landfill Technical Specifications, On

February 19th, 2004;

(2)GB50337-2003, Urban Environmental Sanitation Planning Norms,

On December 1st, 2003;

(3)CJ/T 18-1999,Standard For Setting of Town Environmental

Sanitation Facilities, On June 4th, 1999; 8

(4)GB /T 18772-2008, Technical Requirement for Environmental

Monitor on Sanitary Landfill Site of Domestic Refuse, On April 1st, 2009;

(5)GJJ47-2006,GarbageTransfer Station Technical Specifications, O n April 6th, 2006;

(6)Notification about Improvement Work on Standardization for

Discharge Outlet, Forwarded by Hubei Provincial Environment

Protection Bureau from Ministry of Environment Protection, (E Huan

Jian [1999] No.17).

(7)Notification about improvement Work on Standardization for

Discharge Outlet Issued by Ministry of Environment Protection, (Huan

Fa [1999]No.24).

(8)Implementation Rules on Environment Protection and

Management for Hubei Construction Project, (E Huan Zi [1998] No.5);

(9)Notification about Functional Area Category on the Surface Water

Environment, Forwarded by Provincial People's Government General

Office from the Provincial Environmental Protection Bureau of Hubei

Province, (E Zheng Ban Fa [2000] No. 10), implemented on January 31st,

2000;

(10)Suggestions on Accelerate Development of Circular Economy issued by the State Council, (Guo Fa [2005]N0.22);

9

(11)Notice on Implementation Standard for EIA of Counterpart

Pipeline Project of Hanchuan Urban Sewage Treatment Project issued by

Hanchuan Municipal Environment Protection Bureau, (Chuan Huan Biao

Han [2013] No.132);

(12)The eleventh Five-year Plan for Environment Protection and prospect objective in 2020 of Hanchuan City.

1.2.4 Main Environmental Standards

(1)Environmental QualityStandard for Surface

Water (GB3838-2002);

(2)Ambient Air Quality Standard (GB3095-2010);

(3)Acoustical Environmental Quality Standards (GB3096-2008);

(4)Emission Standard of Environment Noise for Boundary of

Construction Site (GB12523-2011);

(5)Emission Standard for Industrial Enterprises Noise at Boundary

(GB12348-2008);

(6)Emission Standards For Odor Pollutants (GB14554-93);

( 7 ) Discharge Standard of Pollutants for Municipal Wastewater

Treatment Plant (GB18918-2002);

(8)Wastewater Quality Standards for Discharge to Municipal Sewers

10

(CJ3082-2010);

( 9 ) Municipal Solid Waste Sanitary Landfill Disposal of

Construction Projects and Standards (established standard [2001] No.

101), On July 1st, 2001;

( 10 ) CJJ 27-2005, Urban Environmental Sanitation Plan and

Set Standards, On May 1st, 2005;

(11)CJJ/T 107-2005, Standard of Harmlessness Assessment on

Municipal Solid Waste Landfill, On December 1st, 2005;

(12)The disposal of sludge from municipal wastewater treatment plant - Quality of sludge for co-landfilling (GB/T 23485-2009);

( 13 ) Standard of Pollution Control for Solid Waste Landfill

(GB16889-2008), on July 1st, 2008.

(14)Groundwater Quality Standard (GB/T14848-93) which was implemented on January 1st, 1994.

The Variation Status on Standard of Pollution Control for Solid

Waste Landfill

Standard of Pollution Control for Solid Waste Landfill

(GB16889-1997)was replaced by Standard of Pollution Control for

Solid Waste Landfill(GB16889-2008), the main changes are listed as the following: 11

1) The standard name was revised;

2) Requirements on landfill site selection was added;

3) The design and construction requirements for basic facilities of

landfill was refined;

4) The landfill admission requirements for solid waste incineration

flying dust, medical waste, normal industrial solid waste, solid

waste generated from anaerobic methane production, solid waste

generated from excrement treatment and sludge generated from

waste water treatment were added;

5) The pollution control requirements for landfill operation, closure

and coming maintenance and management were added;

6) The quantity of pollutant to be controlled for landfill was added.

1.2.5 Other Materials

(1)Feasibility Report for Counterpart Pipeline of Hubei

Hanchuan Urban Waste Water Treatment Project;

(2)EIA for Counterpart Pipeline Expansion of Hubei Hanchuan

Urban Waste Water Treatment Project( Zhongan Zhihuan

Technology Assessment Co., Ltd., November, 2013);

(3)Reply From Huanchuan Municipal Environment Protection

Bureau on EIA Sheet for Counterpart Pipeline Construction of Hubei

12

Hanchuan Waste Water Plant Second Phase Project(Chuan Huan Shen

Han[No.123], on November 22nd, 2013);

(4)Reply on EIA Implementation Standard for Counterpart

Pipeline Construction of Hubei Hanchuan Waste Water Plant Second

Phase Project(Chuan Huan Biao Han[2013]No.132, on October 28th,

2013);

(5)Instruction for Environment Impact from Leachate Treatment

Process Variation of WB Financed Hanchuan Urban Solid Waste Landfill

Project(Hubei Academy of Environmental Sciences, January 9th, 2014);

(6)Supplementary Introduction on Environment Impact for Solid

Waste Leachate Discharging Standard for Shayang Urban Solid Waste

Treatment Project of WB Financed Han River Urban Environment

Improvement Project (Hubei Junbang Environment Technology Co., Ltd.,

January 9th,2014).

1.3 Environment Impact Scope Variation Status After Project Mid-term Adjustment

1.3.1 Hanchuan Sewage Collection Pipeline Network Project According to EIA for Counterpart Pipeline Expansion of Hubei Hanchuan Urban Waste Water Treatment Project(Beijing Zhongan Zhihuan Technology Assessment Co., Ltd., November, 2013) and Reply on EIA Sheet for Counterpart Pipeline Network Expansion of Hubei Hanchuan Waste Water Treatment Project(Chuan Huan Shen Han[2013]

13

No.123), the environment impact will be generated after the mid-term adjustment are listed as the following: This project is mainly focus on improvement and expansion for sewage system of main urban area and reserve capacity for the sewage of Chenghuang Town and Liujiage Town involved in the planning system. Sewage pipeline is mainly divided into several sections: west old urban section, two sides section of interceptor in north of urban, union ditch section of north of urban and two sides section of No2. Kaifa Road. The long-term planning capacity of newly built sewage pipeline is 0.25 million ton/day and the estimated sewage amount of this period is 50,000.00ton/day. The pipe diameter of the sewage pipeline is DN500~DN1200 with a length of 16.6KM and reserve crossing pipeline DN500 of 1.3KM. New pump will be added to the No.2 pump station. Improve the interception in drainage outlet of old urban area. Update the land reclamation pump of Sanyi Floodgate, add new sewage pump and remove and construct the upper constructions. Update the land reclamation pump of Daxing Floodgate and remove and construct the upper constructions.

Since the project pipelines are built under the ground which will be rehabilitated after the construction, so there is no land requisition and demolition work will be occurred, then there is no resettlement and house demolition work.

Gas Generated During Construction Period 1.Dust

During the whole construction period, the dust is mainly generated

14

from land excavation, pipeline traction, backfill, pipeline transportation, spoil open-air stacking, load and unload. The dust will be more serious during the dry season in a windy weather. Through the investigation, it reveals that the dust in the construction site is mainly generated from the vehicles travelling which accounts for 60% of the total dust and it has relationship with the road surface and vehicle travelling speed. Generally, the impact scope of the dust generated from the natural wind in construction site and construction road is within 100 meters. During the construction period, 70% to 80% dust will be reduced through watering the road four to five times a day which will decline the TSP pollution distance within 50 meters. 2. Waste Water Generated During Construction Period This waster water is mainly generated from storm water surface runoff, construction waste water and domestic waste water of construction staffs. (1)Storm water surface runoff at construction site: Generally, the sewage pipeline excavation and pipeline laying will not have significant impact on surface water. Nevertheless, during the storm season, the storm water surface runoff will wash away the dust, construction stone and sand, solid waste and spoil which will be directly transported to pipeline with some other pollutants, such as concrete, oil pollutant and chemicals, and then enter into the surface water body or discharged into the surface water directly. If the suspended substance of the waste water discharged into the surface water without treatment which will cause pollution to the water

15

body, river and water body blockage. (2)Construction waste water: the construction waste water is mainly generated from equipment cleaning water, construction site washing, construction materials washing, vehicles flushing, concrete maintenance and equipment hydraulic testing which has a certain amount of oil and sludge. This kind of waste water will be reused after sediment in the sedimentation tank.

(3)Domestic waste water: the domestic waste water generated from the construction staffs is the main water pollution source. There will be 50 construction staffs during the construction rush hours and the domestic waste water is 50L/day per staff, see Table 1.3-1 for the domestic waste water and pollutant amount per day at the construction site.

Table 1.3-1 Domestic Waste Water and Pollutant Amount During Construction Period

Waste Water Ammonia SS BOD5 COD(kg/d) (m3/d) nitrogen(kg/d) (kg/d) (kg/d) 2.5 0.06 0.45 0.62 0.37

Though the amount of this domestic waste water, it should not be discharged into river. The construction staffs rent the local resident houses, so their domestic waste water will be discharged into sewage pipeline network after treatment. The general principle for treatment of the construction waste water is to prevent the waste water with sludge, sand and other pollutants discharged into river. During the construction period, the construction unit must implement the Temporary Rules on Civilized Construction and

16

Environment Management of Project Construction Site strictly and conduct design for the surface water drainage, arbitrary drainage is forbidden. In conclusion, the impact on water environment is mainly caused by the poor management. If the management work are strengthened for each construction site, pay more attention to civilized construction, rapid construction and carry out a certain of environment pollution prevention and improvement measures, the above environment impact will be low and shortly.

3. Noise Generated During Construction Period The mechanical equipment which can generate noise of this proposed project include hydraulic excavator, bulldozer, loader, air compressor, vibrator and cutting machine. The noise value is listed in Table 7-2. Though the construction of pipeline is linear, the load and unload of pipeline, road surface cutting and construction of gasification station are conducted point to point, so the construction noise source can be treated as point noise source. According to the point noise source decline model, we can estimated the noise value at different distance from the noise source, the estimate model is as below:

LP=LP0 - 20 lg (r/r0)

Note:Lp—Estimate Noise Value(dB(A)) r meter from the noise source.

Lp0—Reference Noise Level(dB(A)) r0 meter from the noise source. According to the noise value of different construction machinery, the estimate noise value at different distance of different construction machinery will be calculated, see Table 1.3-2 for the detailed information.

17

Table 1.3-2 The Estimate Noise Value at Different Distance of

Different Construction Machinery Unit: dB(A)

1 2 3 4 5 1 1 1 2 Distance(m) 5 Machinery 0 0 0 0 0 00 20 50 00

8 7 7 6 6 6 5 5 5 5 Hydraulic Excavator 4 8 2 8 6 4 8 3 5 2 8 8 7 7 7 6 6 5 6 5 Pipelayer 8 3 7 3 1 9 3 8 0 7 9 8 8 7 7 7 6 6 6 6 Vibrator 5 9 3 9 7 5 9 3 5 2 9 8 7 7 7 7 6 5 6 5 Loader 0 4 8 4 2 0 4 9 1 8 9 8 7 7 7 7 6 5 6 5 Bulldozer 0 4 8 4 2 0 4 9 1 8 8 8 7 7 7 6 6 5 6 5 Trucks 9 3 7 3 1 9 3 8 0 7 8 8 7 7 6 6 6 5 5 5 Moveable Crane 6 0 4 0 6 4 0 5 7 4 9 8 8 7 7 7 6 6 6 6 Cutting Machine 5 9 3 9 7 5 9 3 5 2 9 8 8 7 7 7 6 6 6 6 Welder 2 4 0 8 5 3 8 2 4 0 The noise value generated from the above construction machinery will exceed the night standard stated in Environment Noise Emission

Standard at the Boundary of Construction Site(GB12523-2011). The construction of medium pressure pipeline is along the urban traffic road which locates inside of the urban area. The surrounding environment sensitive points are school, government agency, residential area and other public site within 5 meter to 100 meter from the construction site. The noise value generated from the construction is close to the standard

18

requirement stated in Environment Noise Emission Standard at the Boundary of Construction Site which will have a certain of impact to the above environment sensitive point, so different construction time will be adopted to the different environment sensitive point. The moveable noise barrier will be adopted if it is necessary to reduce the noise impact. Try to avoid night construction and it must be approved by the relative department and notice to the public if the construction must be conducted during the night time. Though the construction noise is inevitable during the construction period, the Environment Noise Emission Standard at the Boundary of Construction Site(GB12523-2011)must be implemented strictly and the relative prevention measures must be taken to minimize the impact to the environment. 4. Solid Waste Generated During Construction Period It is analyzed that the construction solid waste is 25kg per day. If the solid waste generated from the kitchen discharged arbitrarily which will destroy the environment sanitation and have impact on aesthetic, the odour and disease will be spread and breed the flies and mosquito when the organics go bad. Moreover, the harmful factor of the solid waste will pollute the environment if it floats in the air. For the solid waste, it must be collected by the sanitation department and conduct harmlessness treatment. After adopting the measures to prevention and improve solid waste, the solid waste of this project construction has minimum impact to the surrounding environment. 5. Impact on Ecology (1)Impact on Soil from Pipeline Construction The ditch method is adopted for pipeline construction, so the impact

19

on soil is inevitable which will destroy the soil structure, soil layer and cause nutrient loss. Since the construction is conducted inside of the urban area and the surface soil will be collected during construction and cover back after construction which will not generate other impacts. (2)Impact on Agricultural Irrigation Facilities There is no pipeline cross the river of this project, so there is no impact on agricultural irrigation facilities. (3)Impact on Animal and Plant Ecological Environment Impact on terrestrial organism: through the site investigation, it is found that there is no large forest park, natural reserve area and large forest within 300 meters along the pipeline sides, there is only a small amount of forest between farmlands and greening belt along the roads. There is no large meadow and only amount of farmlands inside of the construction area, so the construction will have no impact on meadow resources. There is no rare wild animal and plant found along the pipeline. Since the ecology category is quite simple along the pipeline construction area, so there is no impact on the living environment of the wild animal and plant, only minimum impact on the terrestrial ecological environment because the project construction area is quite narrow with short construction period.

(4)Impact Estimate on Landscape Ecology

The impact on landscape ecology mainly determines by the surface vegetation, topography, residential point of the pipeline construction area and water system variation of the area that pipeline passes through. This pipeline project only passes through greening belt and landscape of traffic road.

20

The land surface will be rehabilitated after the completion of the pipeline construction, the original traffic road, farmland landscape and greening belt will not be changed. So it is estimated by the theory of landscape ecology, this project will not have impact on landscape ecology of this project area.

(5)Impact on Ecological Stability and Water Loss and soil Erosion

Since there is no large area of bare soil excavation, there is no large amount of spoil. The construction hour must be distributed reasonably and avoid excavation during intensive rainfall period in July and August.

The prevention and improvement measures must be taken to shorten the exposed time of excavated earth and excavation exposed surface. There will be minimum impact from water loss and soil erosion during construction period if the excavated earth and stone backfilled timely and reasonable treatment conducted for the spoil.

Environment Impact During Operation Stage

(1)Air

The odour generated from the pump station during the project operation stage is mainly consist of H2S, NH3 and mercaptan. The embedded design is adopted for this project and the gas skirt and odour removal system are installed inside of the pump station to degrade the odour. The odour will meet the requirements of Class II of Odour

21

Pollutant Emission Standard (GB144554-93) after the treatment. The calculated prevention distance is 50 meter and there is no resident, place of interest and other environment sensitive points within this prevention distance.

(2)Ambient Environment

Only one water pump will be added to No.2 pump station and the update work for the equipment of other pump station will be conducted without variation of pump quantity, there will be minimum impact from the noise generated from the pump station after the completion of the update work. It is estimated that the noise will meet the requirements of

Class II of Environment Noise Emission Standard at the Boundary of

Industrial Enterprise(GB12348-2008), so the noise generated from the operation of waste water treatment plant will have minimum impact on surrounding environment which will not cause nuisance issues.

(3)Solid Waste

The solid waste of this project is mainly generated from the sediment between the gratings(1277.5m3/a) which shall be disposed by the sanitation department. The sediment must be transported timely to avoid the impact from the odour generated from the sediments. The solid waste of this project will have minimum impact on the surrounding environment after the above treatment.

22

(4)Risk Analysis

Under the emergency situation, such as wastewater pipeline burst which will cause methane and waste water leakage and cause pollution and impact to some extent.Besides, the urgent repair will cause noise and waste water pollution. If the waste water pipeline burst, the methane with high concentration inside will cause poisoning to human beings and the waste water will flow into the road with odour spread, so it is necessary to build a set of prevention measures and emergency plan.The pump station will be shut off if the wastewater pipeline burst and arrange relative staffs to conduct repair work as sooon as possible which will minimize the loss and the impact on resident and environment.

1.3.2 Shayang Solid Waste Project

The ministry of Environmental Protection and General

Administration of Quality Supervision, Inspection and Quarantine of the

People's Republic of China issued the Standard of Pollution Control for

Solid Waste Landfill(GB16889-2008)on April 1st, 2008 which was implemented from July 1st, 2007. This standard lists more strict requirements on water pollutant discharging for the existing and newly built solid waste landfill.

According to Standard of Pollution Control for Solid Waste Landfill

( GB16889-2008 ) ,the original leachate treatment

23

process(140m3/dUASB+ Oxidation Ditch Pretreatment Process)stated in the report can not meet the requirements of the new discharging standard. Currently, the waste water treatment section of Shayang Urban

Solid Waste Landfill has not been constructed, so the construction unit decides to change the leachate treatment process during this mid-term adjustment to meet the requirements of the new discharging standard, the instruction on the variation status and environment impact are listed as the following.

Leachate Treatment Process After Variation and Discharging

Direction

The treatment capacity is the same after variation(130m3/d). In order to meet the requirements of Technology Specifications on Leachate

Treatment of Solid Waste Landfill(HJ564-2010,trial implementation)and

Technology Specifications on Leachate Treatment of Solid Waste

(CJJ150-2010), the treatment process adjusted to leachate pretreatment and membrane deep treatment process designed by the qualified unit. The outlet water quality can meet the requirements of Table 2 of Standard of

Pollution Control for Solid Waste Landfill(GB16889-2008).

The Wastewater after treatment will be discharged into Shayang

Sewage Pipeline Network based on the EIA report which was approved by the reply E Huan Han [2007] No.493 in October 2007.

24

Environment Impact Analysis After Variation

(1) Compliance with the Law and Regulations

After the treatment process variation which can meet the discharging standard of Standard of Pollution Control for Solid Waste Landfill

(GB16889-2008). The treatment will update from pretreatment to self treatment and the outlet water quality concentration can meet the limitation requirement of the standard.

Table 1.3.2-1 Pollutant Concentration Limitation of Solid Waste Landfill

No. Pollutant Concentration Pollutant Monitoring Location

Limitation

1 Chroma(dilution times) 40 Outlet of normal waste water

treatment facility

2 CODcr(mg/L) 100 Outlet of normal waste water

treatment facility

3 BOD5(mg/L) 30 Outlet of normal waste water

treatment facility

4 SS (mg/L) 30 Outlet of normal waste water

treatment facility

5 Total Nitrogen(mg/L) 40 Outlet of normal waste water

treatment facility

6 Ammonia Nitrogen(mg/L) 25 Outlet of normal waste water

treatment facility

7 Total Phosphorus(mg/L) 3 Outlet of normal waste water

treatment facility

25

8 Fecal coliform(No./L) 10000 Outlet of normal waste water

treatment facility

9 Total Hg(mg/L) 0.001 Outlet of normal waste water

treatment facility

10 Total Cadmium(mg/L) 0.01 Outlet of normal waste water

treatment facility

11 Total Chromium(mg/L) 0.1 Outlet of normal waste water

treatment facility

12 Hexavalent Chromium (mg/L) 0.05 Outlet of normal waste water

treatment facility

13 Total Arsenic(mg/L) 0.1 Outlet of normal waste water

treatment facility

14 Total Plumbum(mg/L) 0.1 Outlet of normal waste water

treatment facility

Table 1.3.2-2 Discharging Pollutant Highest Allowed Concentration

Limitation Listed on Standard of Urban WWTP (Average Value Per Day)

(Unit:mg/L)

Class I No. Pollutant Class II Class III Class A Class B

1 COD 50 60 100 120

2 BOD5 10 20 30 60

3 SS 10 20 30 50

4 Animal and Plant Oil 1 3 5 20

5 Petroleum 1 3 5 15

6 Negative Surfacant 0.5 1 2 5

7 Total Nitrogen(count by N) 15 20

8 Ammonia Nitrogen(count by N) 5(8) 8(15) 25(30)

26

Total Phosphorus 9 0.5 1 3 5

(2)Impact on Urban WWTP

Since the treatment capacity and outlet water quality concentration reduced greatly, the COD, BOD, Ammonia Nitrogen and Total

Phosphorus and other main indicators can meet the requirements of Class

II of Pollutant Discharging Standard for Urban WWTP(GB18918-2002) which can be obtained from the comparison of Table 1.3.2-1 and Table

1.3.2-2. After the combination with the urban sewage pipeline network, the waste water amount and water quality will not have great impact on the operation of Shayang Urban WWTP. Besides, the Hg, cadmium, chromium, plumbum and arsenic and other heavy metals of the outlet must meet the discharging requirements of Table 2 of Standard of

Pollution Control for Solid Waste Landfill, then the sludge poisoning can be further avoided for the biochemistry treatment section of urban WWTP and reduce the impact on water environment from the persistent pollutants.

(3)Impact on Water Quality of Receiving Water Body

The leachate and office waste water of Shayang Urban Solid Waste

Landfill discharged into Shayang WWTP after treatment and will discharged into Xijing River if meet the requirement of Class IB of

27

Pollutant Discharging Standard for Urban WWTP(GB18918-2002).

After the update for the waste water treatment process, the pollution load reduced greatly which will not have impact on water body nearby landfill and final receiving water body.

In summary, the project after variation comply with the relative national standards and the conclusion of the environment impact is the same as that in the original report.

1.3.3 Hanchuan Solid Waste Project

According to the Standard of Pollution Control for Solid Waste

Landfill(GB16889-2008)issued by the Ministry of Environmental

Protection, it states more strict limitation requirement for the leachate self treatment of all the solid waste landfill. The project construction unit proposed to update the leachate treatment process based on the requirements of this standard while the outlet discharging direction will no be changed.

The instructions on leachate treatment process variation status and environment impact are listed as the following:

Original Leachate Treatment Process

The leachate and office domestic waste water is treated by the pretreatment device of UBF+CT+CASS with a capacity of 250m3/d, If the outlet water quality can meet the requirement of Water Quality

28

Standard for Waste Water Discharged into Urban Sewage Pipeline

(CJ3082-1999), then discharged into urban WWTP for deep treatment through the urban sewage pipeline network, and if the treated water quality can meet the requirement of Class IB of Pollutant Discharging

Standard for Urban WWTP(GB18918-2002), then discharged into Han

River.

The characteristics of waste water pretreatment process:

(1)It has proven operation experiences and adapt to the changes of leachate water quality with a reliable and stable treatment effects.

(2)Small amount of structure and equipment with convenient maintenance.

(3)Low investment and it has a low operation cost.

(4)Stable and mall amount of sludge generated.

Hanchuan WWTP started operation from October, 2011 with a capacity of 50,000m3/d, the designed inlet water quality is: COD=

362mg/l,BOD5=181mg/l,SS = 219mg/l and NH3-N=29mg/l and the treatment method is oxidation ditch treatment process; the outlet water quality is: COD≤60mg/l,BOD5≤20mg/l,SS≤20mg/l and NH3-N≤8mg/l which can meet the requirement of Class IB of Pollutant Discharging

Standard for Urban WWTP(GB18918-2002).

The waste water discharging amount of Hanchuan Solid Waste

29

Landfill only accounts for 0.5% of the designed capacity of WWTP.

Since the concentration of SS, COD, BOD5 and NH3-N meet the inlet water quality indicator of WWTP, so the water discharged of Hanchuan

Solid Waste Landfill will not have great impact on treatment load of

WWTP.

Leachate Treatment Process After Variation

The waste water treatment capacity is still the same after variation and the treatment process is changed to MBR+RO with the characteristics as the following:

(1)The process technology is proven and stable;

(2)The balance design and stable for the inlet water quality, and has an appropriate carbon-nitrogen ratio;

(3)Outlay MBR has strong biological denitrification capacity and organic pollutant degradation capacity because it has high concentration and long age sludge.

(4)The RO process can guarantee the outlet water quality can meet the limitation requirement of Pollution Control for Solid Waste Landfill

(GB16889-2008).

Environment Impact Analysis After Variation

1. Compliance with the Law and Regulations

After the treatment process variation which can meet the discharging

30

standard of Standard of Pollution Control for Solid Waste Landfill

(GB16889-2008). The treatment will update from pretreatment to self treatment and the outlet water quality concentration can meet the limitation requirement of the standard.

2. Impact on Urban WWTP

Since the treatment capacity and outlet water quality concentration reduced greatly, the COD, BOD, Ammonia Nitrogen and Total

Phosphorus and other main indicators can meet the requirements of Class

II of Pollutant Discharging Standard for Urban WWTP(GB18918-2002).

After the combination with the urban sewage pipeline network, the waste water amount and water quality will not have great impact on the operation of Hanchuan Urban WWTP. Besides, the Hg, cadmium, chromium, plumbum and arsenic and other heavy metals of the outlet must be controlled strictly, then the sludge poisoning can be further avoided for the biochemistry treatment section of urban WWTP and reduce the impact on water environment from the persistent pollutants.

3. Impact on Water Environment

The leachate and office waste water of Hanchuan Urban Solid Waste

Landfill discharged into Hanchuan WWTP after treatment and will discharged into Han River if meet the requirement of Class IB of

Pollutant Discharging Standard for Urban WWTP(GB18918-2002).

31

After the update for the waste water treatment process, the pollution load reduced greatly which will not have impact on water body nearby landfill and final receiving water body.

In summary, the project after variation comply with the relative national standards which will not have impact on the WWTP in the downstream and will not have negative environment impact on the water body nearby landfill and Han River.

1.4 Environment Protection Targets Variation Status After Mid-term Adjustment

1.4.1 Environment Protection Targets Variation Status of Hanchuan

Sewage Collection Pipeline Network New sewage collection pipeline network will be added in Hanchuan urban area of Hubei Province and the new added environment protection targets are the institutions, schools, residential areas and nearby water bodies. The following environment quality standards shall be implemented: (1)The ambient air quality must be meet the requirements of Class II of Ambient Air Quality Standard (GB3095-1996); (2)Currently, the waste water discharged into Xujia Channel and the environment quality meet the requirement of Class IV of Surface Water Quality Standard(GB3838-2002); (3)The acoustics of the project construction area is divided into Class II and Class Iva which can meet the requirements of Class II and

32

Class Iva of Acoustical Environmental Quality Standards (GB3096-2008).

See Table 1.4-1 for the environment protection targets within the project area.

Table 1.4-1 environment protection targets within the project area

Nature of No. Name Location and Distance Sensitive Objective Point Two sides of Planning 1# Xiannvshan Village Villager Noise: Class II Air: Class II Road West Side of Dipo Residential 2# Huiyuan Jiayuan Noise: Class II Air: Class II Road~18m Site Hanchuan Youfu South Side of Renmin Noise: Class II and 4a 3# Institution Hospital Avenue~15m Air: Class II North Side of Renmin Noise: Class II and 4a 4# People’s Court Institution Avenue~15m Air: Class II People’s North Side of Renmin Noise: Class II and 4a 5# Institution procuratorate Avenue~15m Air: Class II South Side of Renmin Residential Noise: Class II and 4a 6# Xingfa Community Avenue~15m Site Air: Class II Residential Building of Hanchuan North Side of Renmin Residential Noise: Class II and 4a 7# Chengguan Land Avenue~15m Site Air: Class II Administration Department Bilingual Kindergarten of South Side of Renmin Noise: Class II and 4a 8# School Hanchuan Buxing Avenue~15m Air: Class II Street Hanchuan People’s North Side of Renmin Noise: Class II and 4a 9# Institution Congress Avenue~15m Air: Class II Hanchuan National North Side of Renmin Noise: Class II and 4a 10# School Tax Bureau Avenue ~25m Air: Class II No.2 Primary School of South Side of Renmin Noise: Class II and 4a 11# School Xiannvshan Street Avenue ~15m Air: Class II Office

33

Nature of No. Name Location and Distance Sensitive Objective Point Hanchuan Land South Side of Renmin Noise: Class II and 4a 12# and Resource Institution Avenue ~15m Air: Class II Bureau Hanchuan North Side of Renmin Noise: Class II and 4a 13# Xiannvshan Street Institution Avenue ~12m Air: Class II Office Hanchuan North Side of Renmin Noise: Class II and 4a 14# Corresponding Institution Avenue ~18m Air: Class II Bureau North Side of Renmin Residential Noise: Class II and 4a 15# Bofa Haoting Avenue ~15m Site Air: Class II Hanchuan Public South Side of Renmin Noise: Class II and 4a 16# Institution Security Bureau Avenue ~10m Air: Class II Hanchuan South Side of Renmin Noise: Class II and 4a 17# Municpal Institution Avenue ~10m Air: Class II Committee Hanchuan North Side of Renmin Noise: Class II and 4a 18# Telecommunication Institution Avenue ~15m Air: Class II Bureau North Side of Renmin Residential Noise: Class II and 4a 19# Yicheng Jiayuan Avenue ~30m Site Air: Class II South Side of Renmin Residential Noise: Class II and 4a 20# Bofa Mingyuan Avenue ~35m Site Air: Class II Hanchuan Disease South Side of Renmin Noise: Class II and 4a 21# prevention and Institution Avenue ~28m Air: Class II Control Centre Hanchuan Population and South Side of Huocheng Noise: Class II and 4a 22# Institution Birth Planning Avenue ~20m Air: Class II Bureau Hanchuan Statistics South Side of Huocheng Noise: Class II and 4a 23# Institution Bureau Avenue ~10m Air: Class II South Side of Huocheng Residential Noise: Class II and 4a 24# Yujing Chuncheng Avenue ~30m Site Air: Class II Residential 25# Tianjiaju Village North Side of Kaifa Road Noise: Class II Air: Class II Site Water Function: Class IV, 26# Xujia Channel / / apply to industry and entertainment Utilization

34

1.4.2 Environment Protection Targets Variation Status of Shayang

Solid Waste Project

The mid-term adjustment of Shayang Solid Waste Project is increase the leachate discharging standard based on Pollution Control for Solid

Waste Landfill(GB16889-2008), so there is no variation for the environment protection targets.

1.4.3 Environment Protection Targets Variation Status of Hanchuan

Solid Waste Project

The mid-term adjustment of Hanchuan Solid Waste Project is increase the leachate discharging standard based on Pollution Control for

Solid Waste Landfill(GB16889-2008), so there is no variation for the environment protection targets.

1.5 Environment Management Organization Variation Status After Mid-term Adjustment

1.5.1 Environment Management Organization of Hanchuan Sewage

Collection Pipeline Network

(1)Environmental Management Organization during construction period

Environmental management organization during construction period, see charts below

35

Chart 1.5-1 environmental management structure during construction period

(2)Environmental Management Structure during operation and closure period

Chart 1.5-2 Environmental Management Structure during operation and closure period

During the operation stage, if the industrial waste water need to

36

discharged into WWTP, the industrial enterprise shall sign relative agreements and contact the project owner when needs to combine the pipelines, then the construction can be conducted if it is approved. The waste water generated from the industrial and electroplating enterprise can not discharged into the pipeline networks. Hanchuan Sewage

Collection Pipeline Network Project shall establish a environment protection department or merge into Hanchuan sewage collection and treatment system which will supervise the operation of Hanchuan sewage collection system. This department shall have 2 staffs and one team leader.

The environment monitoring agency shall be established which will be leaded by Hanchuan Environment Monitoring Station to conduct the monitoring work.

1.5.2 Environment Management Organization of Shayang Solid Waste

Project

The mid-term adjustment of Shayang Solid Waste Project is update the leachate treatment process , so the environmental management structure is the same as before. (1)Environmental management organization during construction period, see charts below.

37

Table 1.5-3 environmental management structure during construction period

(2)Environmental Management Structure during operation and closure period

Table 1.5-4 Environmental Management Structure during operation and closure period

38

Environmental protection section shall be established after the project operation which shall be leaded by a vice manager of the landfill.

Environment monitoring office shall be established under environmental protection section, the section chief must be a professional staff on environmental protection. The environmental monitoring technical staff and maintenance worker must be involved in Environmental monitoring office. The technical staff majored in environment engineering and analytical chemistry shall be included in above staffs.

1.5.3 Environment Management Organization of Hanchuan Solid Waste

Project

The mid-term adjustment of Hanchuan Solid Waste Project is update the leachate treatment process , so the environmental management structure is the same as before.

(1) Environmental management organization during construction

period, see charts below.

39

Table 1.5-5 environmental management structure during construction period (2)Environmental Management Structure during operation and closure period

Table 1.5-6 Environmental Management Structure during operation and closure period 40

Environmental protection section shall be established after the project operation which shall be leaded by a vice manager of the landfill.

Environment monitoring office shall be established under environmental protection section, the section chief must be a professional staff on environmental protection. The environmental monitoring technical staff and maintenance worker must be involved in Environmental monitoring office. The technical staff majored in environment engineering and analytical chemistry shall be included in above staffs.

1.6 WB Security Guarantee Policy

Based on the site investigation, it is found that the environment senstive point has some change of Hanchuan sewage collection pipeline network and lifting pump station, but the cultural relics and archaeologies are not involved. Shayang and Hanchuan solid waste project only update the leachate treatment process, no other WB security guarantee policy involved.

41

Chapter II Mitigation Measures

2.1 Mitigation Measures for Hanchuan Sewage Collection Pipeline Network and Pump Station

Based on the environment impact analysis of Hanchuan Sewage Collection Pipeline Network, it is found that the original EMP is still apply to the construction period. The mitigation measures can refer to that in the EMP. See Table 2.1-1 for the detailed mitigation measures during operation stage.

Table 2.1-1 mitigation measures during operation stage of Hanchuan Sewage Pipeline Network Project.

Implementation Item Measures Protection Objects Time

Odour of pump station: adopt ground buried

Air design and install odour remove system in

well cover and pump station

Noise of pump station equipment: adopt Residents, school and Operation stage ground buried design, select the water pump institution nearby Noise with low noise and take measures to absorb,

separate and eliminate the noise.

sediment generated from the pump station Solid Waste disposed by the sanitation department

2.2 Mitigation Measures of Solid Waste Landfill

The mid-term adjustment for Shayang and Hanchu solid waste

42

project is just the update of leachate treatment process, only need to

construct the structure for the deep treatment of leachate, so the original

EMP is still apply to these projects. During the operation stage, the

leachate will be discharged after deep treatment and meet the

requirements of Pollution Control for Solid Waste Landfill

(GB16889-2008), so the mitigation measures that apply to Shayang and

Hanchuan solid waste projects are listed in Table 2.2-1.

Table 2.2-1 Environment Protection Measures for Operation Stage of Solid Waste Landfill

Protection Implementation Measures Category Measures Content Objects Time

1. Leachate discharged into urban sewage

pipeline network after treatment by the

Mitigation Measures for impact treatment facility and meet the Landfill Site on water environment requirement of discharging standard

2. Storm water collected and deposited,

used for reducing the dust

Mitigation Measures for impact Odour of landfill: collected and burned to Residents nearby Operation stage on ambient environment reduce the odour

Noise of leachate treatment system:adopt

ground buried design, select the water Mitigation Measures for impact pump with low noise and take measures Residents nearby on acoustical environment to absorb, separate and eliminate the

noise.

Mitigation Measures for impact solid waste dumped into the landfill Landfill Site from solid waste directly

43

Chapter III Monitoring Scheme

3.1 Monitoring Purpose The monitoring mentioned in this report is mainly conducted for construction and operation stage. Through the site inspection to master the status whether the mitigation measures stated in EIA implemented or not. Besides, through the sample monitoring to master the impact on environment quality, impact scope and environment quality during operation stage. Contact with the management department timely to offer scientific bases for the environment management.

3.2 Environment Monitoring Plan

The environment monitoring plan and cost after mid-term

adjustment for Hanchuan sewage collection pipeline system, lifting pump

station, shayang and hanchuan solid waste project are shown in the

following table.

Table 3.2-1 Environment Monitoring Plan and Cost After Mid-term Adjustment for

Hanchuan Sewage Pipeline Project Total Estimated Annual Monitoring Monitoring Cost(ten Period Monitoring Point Frequency Cost(ten Indicator Item thousand thousand yuan) yuan) pH, SS, Construction site, outlet petroleum, of machine maintenance Water ammonia area and wastewater twice/year 0.12 Quality nitrogen and discharging point of pH (5 construction shed items) Construction One Construction 0.264 Period material yard, Ambient twice/year TSP 0.06 Environment One construction

road,

44

two residential sites nearby construction site 4 monitoring points of twice/year Noise construction site LedB(A) 0.084 boundary 4 monitoring points Water quality COD、BOD once/year 0.075 around pump station Operation H S,NH each outlet entering into 2 3 twice/year 0.343 Period Air and 0.24 pipeline methanethiol Noise Around pump station Leq once/year 0.028

Table 3.2-2 Environment Monitoring Plan and Cost After Mid-term Adjustment for Shayang

and Hanchuan Solid Waste Project

Total Estimated Annual Cost Monitoring Cost(ten Period Monitoring Point Monitoring Item Frequency (ten Indicator thousand thousand yuan) yuan) Construction site, outlet of machine pH, SS, petroleum, Water maintenance area, ammonia nitrogen and pH 6 times/year 0.36 Quality wastewater (5 items) discharging point of Construction construction shed 0.888 Period Ambient Old landfill and 12 TSP 0.36 Environment work area times/year 4 monitoring points Noise of construction site LedB(A) 6 times/year 0.168 boundary point in upwind and downwind of Air CH4, TSP, H2S, NH3. 4 times/year 0.6 landfill and 4 points at landfill site one background well in the

upstream, one pollution dispersion 3.62 well in the pH, Hg, As, Pb, Cr, total Operation Period downstream, two Ground water nitrogen, COD, Once/year 0.3 pollution dispersion NH3-N,E-coli wells for leachate regulating pool and one monitoring point for residential area

45

each point for 4 site noise Leq Once/year 0.04 boundaries

Fly and At least 10 points Twice mosquito for landfillsite,30m Fly and mosquito density during July 0.06 monitoring to 50m each and August Chroma,CODcr,BOD5, ss, Total Nitrogen, ammonia nitrogen, total Outlet of normal phosphorus, fecal Leachate waste water coliforms count, total Hg, 6 times/year 2.62 treatment facility total cadmium, total chrome, sexavalence chrome, total arsenic, total plumbum.

Chapter IV Training Plan

4.1 Training Purpose

Since Hanchuan sewage collection pipeline network and lifting pump station were added and the construction content changed in

Standard of Pollution Control for Solid Waste Landfill which was implemented from July 1st, 2008, the relative environmental impact on environmental protection targets, project construction and operation stage changed, so the mitigation measures for the impact changed accordingly, then need to conduct training for the staffs of construction period and operation period to transmit the new environmental protection targets and mitigation measures. Through the training, the environmental protection work will go smoothly, the monitoring level will be increased and strengthen the sense of environmental protection of the relative staffs,

46

then the negative impact on society and environment will be reduced and

the environment issues will be eliminated and mitigated through the

mitigation measures.

4.2 Training Objects

The training will be conducted by the consultant for the project

construction staffs, monitoring staffs, environmental protection staffs,

specific and part-time environmental protection staffs of supervision unit

and residents nearby. See Table 4.2-1 for the detailed information.

Table 4.2-1 Training Plan for Trainees

Number of Project Period Trainee Training Time Training Content Participant

PMO and EP One for staffs of project each unit National and Hubei provincial Law operation unit After selection of and regulations on EP and water and

5 of contractor, before soil conservation, training on Hanchuan Sewage Construction Environment construction project commence environment quality standard and Pipeline Network Period supervision unit and 1 of construction, during pollution control standard during Project engineer operation construction period, different project stages, training on

unit. after project monitoring technology and mitigation

completion. measures. Emergency 1 Staff

47

Number of Project Period Trainee Training Time Training Content Participant

Residents 3

Environment National and Hubei provincial Management 1 Law and regulations on EP and water staff and soil conservation, training on

Newly built Environment environment quality standard and 5 Hanchuan and Monitoring staff pollution control standard during

Shayang Solid One added to different project stages, training on

Waste landfill Environment construction and Operation Stage 1 monitoring technology ; operation stage of Project Protection staff landfill Understanding of Pollution Control

for Solid Waste Landfill Environment ( GB16889-2008) and comparison Supervision 1 with the old version; training on staff emergency measures.

Residents 3

48

Chapter V Information Disclosure and Public Participation

5.1 Information Disclosure

The staff of Hanchuan Newly Built Solid Waste Landfill Project announced the instruction on leachate treatment process made by Hubei

Academy of Environmental Sciences in the local village committee

January 10th, 2014, the announcement time is from January 10th, 2014 to

January 20th, 2014. No harmful feedback during the announcement period.

See pictures below:

The staff of Shayang Newly Built Solid Waste Landfill Project announced the instruction on environment impact variation made by

Hubei Junbang Environment Technology Co., Ltd which was caused by the enhancement of leachate discharging standard in the local village committee on January 10th, 2014, the announcement time is from January

10th, 2014 to January 20th, 2014. No harmful feedback during the announcement period. See pictures below:

49

WB Financed Han River Basin Pollution Control PMO announced the instructions on environment impact from leachate treatment process variation of WB financed Hanchuan Solid Waste Landfill Project in website of Hubei Environmental Protection

Bureau(http://www.hbepb.gov.cn/wsbs/gsgg/hpgs/hpdwhp/201401/t2014011

4_66501.html) on January 9th , 2014.

50

5.2 Public Participation

PMO of Hanchuan Newly Built Solid Waste Landfill project organized a meeting on leachate treatment process variation of WB financed Hanchuan Solid Waste Landfill Project on January 16th, 2014.

The meeting participant includes environment protection specific staffs, management staffs and the public people. During this meeting, the public people can master the construction content, construction period, construction method, environment impact and mitigation measures of leachate treatment project based on the new discharging standard. The government mastered and accepted the suggestions from the public people which had positive functions for the project operation. See pictures below:

PMO of Shayang Newly Built Solid Waste Landfill project organized a meeting on leachate treatment process variation of WB financed Shayang Solid Waste Landfill Project on January 17th, 2014. The

51

meeting participant includes environment protection specific staffs, management staffs and the public people. During this meeting, the public people can master the construction content, construction period, construction method, environment impact and mitigation measures of leachate treatment project based on the new discharging standard. The government mastered and accepted the suggestions from the public people which had positive functions for the project operation. See pictures below:

52

Chapter VI Conclusion

Through the mid-term adjustment, the construction contents of 14 subprojects in 9 cities/counties of this project was changed to 11 subprojects in 7 cities/counties( Hanchuan, Honghu, Shayang, Xiaochang, Dawu, Xiangyang and Yunmeng), including 3 sewage collection pipeline network projects (Xiangyang, Hanchuan and Honghu), 2 waste water treatment plants and sewage collection pipeline network projects (Shayang and Yunmeng) and 5 solid waste landfill projects (Shayang, Hanchuan, Xiaochang, Honghu and Dawu).

Hanchuan sewage collection pipeline network and lifting pump station, Shayang solid waste project and Hanchuan solid waste project involve the environment impact issues. Hanchuan sewage collection pipeline network and lifting pump station projects are the newly added projects which will not have negative impact according to the analysis on environment impact and mitigation measures on EIA sheets(Chuan Huan Shen Han [123]).Since standard on pollution Control for Solid Waste Landfill (GB16889-2008) was implemented from July 1st,2007, this new standard increased the requirements on leachate discharging compared with GB16889-1997, so Shayang and Hanchuan Solid Waste Landfill Projects must update the leachate treatment process in line with this new discharging standard. Based on the Supplementary Introduction on Environment Impact for Solid Waste Leachate Discharging Standard for Shayang Urban Solid Waste Treatment Project of WB Financed Han River Urban Environment Improvement Project issued by Hubei Junbang Environment Technology Co., Ltd. On January 9th,2014 and Instruction

53

for Environment Impact from Leachate Treatment Process Variation of WB Financed Hanchuan Urban Solid Waste Landfill Project issued by Hubei Academy of Environmental Sciences on January 9th, 2014, the environment impact were analyzed respectively. Since the discharging direction was not changed and just variation made for the leachate treatment process, so there is no negative impact on environment.

New mitigation measures for environment impact, training plan and environment monitoring plan are formulated for Hanchuan sewage pipeline network and lifting pump station project, Shayang solid waste project and Hanchuan solid waste project which will be implemented in next period for these three projects.

54