By on-line TAMILNADU FOREST DEPARTMENT

From To

Vinod Kumar IFS The Project Director, Principal Chief Conservator of Forests National Highways Authority of (Head of Forest Force), , Project Implementing Unit, Panagal Maaligai, Saidapet, Krishnagiri, - 600 015. Door No. 2591/1, Salem Main Road. Near KAKC Petrol Bunk, Krishnagiri 635 001.

C.No. TS3 /36408/2014, Dated: 09.12.2014

Sir, Sub: Forest (Conservation) Act, 1980 - Forest Circle / Vellore Forest Division - Proposal for diversion of 5.42 ha of forest land in Magimandalam Reserved Forests of Vellore Forest Division for Construction of 4-Lane -Chennai Expressway by the National Highways Authority of India - Online proposal Submission - Regarding.

Ref: Online application uploaded by the User Agency - Project Director, National Highways Authority of India, Project Implementing Unit, Krishnagiri 635 001 - dated 27.11.2014.

* * *

In the reference cited, the Project Director of National Highways Authority of India, Project Implementing Unit, Krishnagiri has submitted online application Form A - Part I under Section 2 of Forest (Conservation) Act, 1980 proposal for diversion of 5.42 ha of forest land in Vellore Forest Division in Vellore District for construction of 4-Lane Bangalore-Chennai Expressway by the National Highways Authority oflndia.

The User Agency has not furnished the following essential Documents / Undertakings for the project. Further the following defects / shortcomings have been noticed in the proposal. 1) Certificate to effect that no violation of the provision of Forest (Conservation) Act, 1980 occurred has not been furnished. 2) Certificate from the District Collector about non availability of non forest land for the project has not been furnished. 3) Purpose wise breakup of forest land required for the project has been furnished by the User Agency as follows. In this, Design chainage from 171.300km to 171.840km for 540m length of forest area has been proposed for diversion. From centerline 45m either side has been sought for. Based on this, forest area required is arrived at 4.86 ha (90mx540m=48600 Sq. Km ie., 4.86 Ha) Whereas, area required has been proposed by the User Agency for 5.42 ha. Hence the exact area required for the project to be clarified. 4) Scanned copy of the Geo-referenced map of the forest land proposed to be diverted preparing by using GPS or total station has not been uploaded. (Section C ofMaps-C.iv) 5) Map indicating location of alternative examined for the proposal not uploaded. 6) Undertaking to bear the cost along with any escalation for exploitation of trees in lieu of forest land to be diverted to the project has not been submitted I uploaded. 7) Undertaking to pay the cost towards lease rent as fixed by the Forest department at the time of approval along with any escalation for the forest land to be diverted of the above project has not been submitted I uploaded. 8) Under section H of the proposal - Status of Environmental Clearance - It has been stated that, this project requires clearance under Environmental (Protection) Act 1986, but EC application yet to be submitted. Action taken in this regard should be specified in the form. 9) Under section I of the proposal - Status of Wildlife Clearance - It has been stated that this project or part thereof is located in Protected Area or their Eco Sensitive Area and requires clearance from Supreme Court of India and approval from the Standing Committee of National Board for the Wildlife. Area in which approval has to be obtained has not been furnished in the form and present stage be specified. 10) Report on identification of double the extent of Non Forest Land proposed as Compensatory Land in lieu of the proposed diversion of forest land. 11) Signed copy of Form A, Part I and maps may be uploaded in the proposal. Hence the above defects may be rectified and the details uploaded for the proposal for further action.

Yours faithfully, Sd/- Ashutosh Samant Singhar for Principal Chief Conser vator of Forests (Head of Forest Force)

Copy to the Conservator of Forests, Vellore Circle, Vellore. Copy to the District Forest Officer, Vellore Division, Vellore.

/True copy/ By order/ J. ~ ,J-J "'1 \1Z-1 ,'-\ . Senior Draughting Officer

ANNEXURE-I 11/27/2014 Report Part 1

FORM ­ A

Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area

PART ­ I (To be filled up by User Agency)

A. General Details

A­ Project Details 1.

(i). Proposal No. : FP/TN/ROAD/8238/2014

(ii). Name of Project for which Forest Land is required : Bangalore­Chennai Expressway

(iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Govt. of India is taking up the project of 4­Lane Bangalore­Chennai Expressway through National Highways Authority of India (NHAI) under NHDP Phase­VI which passes through the states of , and measuring the total length of the alignment as 262.278 Km

(iv). State : Tamil Nadu

(v). Category of the Project : Road

(vi). Shape of forest land proposed to be diverted : Non Linear

(vii). Estimated cost of the Project(Rupees in lacs) : 553400

(viii). Total Area of Forest Land proposed for diversion(in ha.): 5.42

(ix). Total Area of Non­Forest Land proposed for diversion(in ha.): 592.69

(x). Total period for which the forest land is proposed to be diverted(in years): 99 A­ Details of User Agency 2.

(i). Name : NATIONAL HIGHWAY AUTHORITY OF INDIA PIU KRISHNAGIRI

(ii). Address1 : Door No. 259/1, Salem Main Road

(iii). Address2 : Near KAKC Petrol Bunk Krishnagiri

(iv). State : Tamil Nadu http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fTN%2fROAD%2f8238%2f2014 1/6 11/27/2014 Report Part 1

(v). District :

(vi). Pin : 635001

(vii). Landmark : KAKC Petrol Bunk

(viii). Email address : [email protected]

(ix). Landline Telephone No. : 234250

(x). Fax No. : 4343

(xi). Mobile No. : 9442275834

(xii). Website (if any) : www.nhai.org

(xiii). Details of Proposals seeking prior approval of Central Government under the Act for diversion of forest land submitted by the User Agency in the past : Yes

(xiv). Legal status of User Agency : Central Government A­ Details of Person Making Application 3.

(i). First Name: Talla

(ii). Middle Name: NIL

(iii). Last Name: Parvateesam

(iv). Gender: Male

(v). Designation: Project Director

(vi). Address 1: Door No. 259/1, Salem Main Road

(vii). Address 2: Near KAKC Petrol Bunk Krishnagiri

(viii). State: Tamil Nadu

(ix). District: Dharmapuri

(x). Tehsil: Dharmapuri

http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fTN%2fROAD%2f8238%2f2014 2/6 11/27/2014 Report Part 1 (xi). Pin: 635001

(xii). Landmark: KAKC Petrol Bunk

(xiii). Email Address: [email protected]

(xiv). Landline Telephone No.: 234250

(xv). Fax No.: 4343236208

(xvi). Mobile No.: 9442275834

(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure U.A Document

B. Details of land required for the Project

B­ Details of proposal seeking prior approval of Central Government under the 1. Act for diversion of forest land for the Project already submitted in the past

(i). Whether any proposal seeking prior approval of Central Government under the Act for diversion of forest land required for the project has been submitted in the past?. : Yes

(ii). Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past.

Proposal Submitted in Past

Date of Moef Area Date of Proposal Proposal Area In­ S.no File Proposed for Final Status. No. Diverted(Ha.) Principle No. Diversion(Ha.) Approval Approval

1 Under 2.56 0 Processing at State Government B­ Details of forest land proposed to be diverted 2.

B­2.1 Details of Divisions involved

Details of Divisions involved

Non­Forest S.no Division Name Forest Land(ha.) Land(ha.)

1. Vellore 5.42 592.69

B­2.2 Details of Districts involved

http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fTN%2fROAD%2f8238%2f2014 3/6 11/27/2014 Report Part 1 District wise breakup

Non­Forest S.no District Name Forest Land(ha.) Land(ha.)

1. Vellore 5.42 592.69

B­2.3 Village wise breakup

Villages wise breakup

Non­Forest S.no Village Forest Land(ha.) Land(ha.)

1 Magimandalam 5.42 54.85

B­2.4 Component wise breakup

Component wise breakup Non­Forest S.no Component Forest Land(ha.) Land(ha.) 1 KM 171.300 to KM 171.840 5.42 0

C. Maps of forest land proposed to be diverted

Division 1. : Vellore

(i). Area of forest land proposed to be diverted(in ha.) : 5.42

(ii). : Non Linear

(a). No. of patches : One

Patch wise details

Patch Area of Patch(in ha.) Kml File of Patches No.

1. 5.42 Annexure Patch1 (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted: Annexure Survey of India Toposheet

(iv). Scanned copy of the Geo­referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station: Annexure scanned copy of the Geo­referenced map

Justification for locating the Project in forest land and details of D. alternatives examined:

(i). Copy of note containing justification for locating the Project in forest land : Annexure Justification

E. Employment likely to be generated

http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fTN%2fROAD%2f8238%2f2014 4/6 11/27/2014 Report Part 1

(i). Whether the Project is likely to generate employment ?: Yes

(ii). Permanent/Regular Employment(Number of persons): 2800

(iii). Temporary Employment(Number of person­days): 86000

F. Displacement of People due to the Project, if any

(i). Whether Project involves displacement?: No

G. Details of Cost­Benefit analysis for the Project

(i). Whether the Project requires Cost­Benefit analysis?: Yes

(a). Copy of Cost­Benefit analysis: Annexure Cost­Benefit analysis

H. Status of Environmental Clearance

(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : Yes

(a). Status of the Environmental Clearance to the Project: EC application yet to be submitted

I. Status of Wildelife Clearance

(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : Yes

(a). Whether Project or a part thereof is located within a Protected Area ? : Yes

(b). Status of approval of the Supreme Court : Approval under cons

(ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project : Application under process

(a). Date of submission of proposals : 14 Jun 2013

(b). Current status : NIL

J. Applicability of special provisions governing Scheduled Areas

(i).Whether the Project or a part thereof is located in a Scheduled Area? : No

Status of settlement of rights under the Forest Rights Act,2006 on the http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fTN%2fROAD%2f8238%2f2014 5/6 11/27/2014 Report Part 1 K. forest land proposed to be diverted

(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : No

L. Details of land identified for Compensatory Afforestation

(i). Whether non­forest or Revenue forest land is required to be provided by User Agency?: NIL

(ii). Whether the area of non­forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: NIL

(iii) . Reason for not providing Non­Forest Land: NIL

Additional information Details

Documents

S.No Documents Remarks

1 Additional Info. Scanned Copy of Form­A

2 Additional Info. Undertakings by NHAI

3 Additional Info. Purpose­wise Breakup of the Reserved Forest Land

4 Additional Info. Brief Note of the Project

5 Additional Info. SOI Toposheet Indicating Boundary of RF land to be diverted scale 1:25000

6 Additional Info. First Submission Letter of the Forest Clearance Proposal of Magimandalam Reserved Forest in Vellore Forest Division

7 Additional Info. Wild Life Clearance Proposal Submission Letter for the Project in the Rayala Elephant Reserve in of Andhra Pradesh

Print page

http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fTN%2fROAD%2f8238%2f2014 6/6

ANNEXURE-II

CERTIFICATE

No Violations of the Provision of the Forest Conservation Act 1980 (Certificate of Project Authority)

ANNEXURE-III

ANNEXURE-IV ~: Tel&gram : PARYAVARAN. NEW DELHI ~~: Tele-phone: 2436 8526 ~: Telex: W-66186 DOE IN • FAX: 4360678 'fln:.~ ~ q,,~ ~ ~ *'r~ GOVERN M ENT OF 'NO IA MINISTRY OF ENVIRONMENT & FORESTS ~~<:"f 'Ililr-f, m. ~. aft .• f*q~lffi PARYAVARAN SHAVAN. C.G,D. COMPLEX ~ m, ;:rf ~-11 0003 lODH I ROAD. NeW DELHI-11OO03 F.No.10-44/2013-IA.III Dated: ar= October, 2013

To Chief General Manager (LA), MIs National Highways Authority of India, G- 5&6, Sector - 10, Dwarka, New Delhi - 110075

Subject: Finalization of ToRs for construction of 6 laning of Bangalore- Chennai Expressway from Bangalore (kmO.OOO)to Chennai (km 258.800) including spur alignments in the States of Karnataka, Andhra Pradesh and Tamil Nadu by MIs NHAI - Reg.

Dear Sir,

Kindly refer to your above proposal submitted to this Ministry. The project involves construction of 6 laning of Bangalore-Chennai Expressway from Bangalore (kmO.OOO)to Chennai (km 258.800) including spur alignments in the States of Karnataka, Andhra Pradesh and Tamil Nadu. The proposed project is a Expressway and start from the Bangalore - Chennai Section of NH-4 about 415m from Kondaspur, which is to the East of Bangalore and ends at (Km 258.800) -Sriperumbadur. The total length of the Bangalore Chennai Expressway is 258.800 Km and it falls in the states of Karnataka, Andhra Pradesh and Tamil Nadu. The proposed ROWis 90m throughout the project stretch. Spur Alignment - 3 has been provided for connectivity from the industrial town of Gold Fields (KGF)/ to Bangalore Chennai Expressway. The Spur-3 alignment takes off from km 51.900 of BCE and is aligned in the Southern direction and the alignment is stopped on MDR connecting SH 95 towards Betamangal and KGF, about 2 km North of KGF as this MDR continues further and passes through KGF, and acts as a connecting road from Spur- 3 to KGF. The alignment ends MDR, at km 4.94. The total length of this Spur Alignment is 2.05 km and is aligned South of Kolar in Karnataka. The proposed RoW of spur-3 is 90 m. About 2295.63 hectares of land is required for the required construction space of Bangalore-Chennai Expressway including spur-3 at . It includes agricultural, barren lands, forest lands and lands under private ownership. The total design length of the project is 260.84 km including Spur-3 (2.14 km) and the BCE passes through three states which are Karnataka (From Km 0.000 to Km 175.900 & Km 81.800 to Km 83.800), Andhra Pradesh (From Km 75.100 to Km 81.800 & Km 83.800 to Km 164.400) and Tamil Nadu (Km 1 •

164.400 to Km 258.800). One water tank affected due to the project road. 52 nos. of pedestrian and 41 vehicular underpasses are provided for the project road. 9 nos. of major bridges, 153 nos. of minor bridges, 143 box culverts and 2 nos. (Elephant Underpass) are to be proposed.

The land requirement is 224.47 ha of Govt. and 2350 ha of private. The project involves forest land is of 67.12 Ha. The proposed project is passing through the Rayala Elephant Reserve for a length of about 7.083Km. Kaundinya Wildlife Sanctuary is situated at a distance of 2.2 Km from proposed Bangalore-Chennai Expressway.

There are about 125 villages along the project road. The project section passes through 6 districts namely Bangalore Rural, Kolar, Chittoor, Vellore, Kachipuram and Thiruvallur. The proposed Expressway project will require felling of a total number of 1,50,000 trees (average 576 trees per km) within 90m RoW in Karnataka, Andhra Pradesh and Tamil Nadu section including spur-alignment in Kolar, which will be inevitable. Efforts will be made to minimize the tree felling to the possible extent. In an average about 21000 KL/day water will be consumed for the project road. The 12600 KL/day surface water will preferably be used for meeting the water requirement for construction to the possible extent depending upon the availability of water in nearby rivers/streams with requisite permission from line department. 8400 KL/day Ground water will be used only in those areas, where there is no source of surface water. The EMP cost is approx. Rs. 149.79 crores, R&R cost is Rs. 2129.45 crores, Civil cost is Rs. 4999 crores. The total cost of the project is 7278.24 crores.

The above proposal was considered in the 126th EAC meeting held on 19th - 21st September, 2013. The details as presented by the project proponents and after discussions, the following "Terms of Reference" were finalized to be suitably added to those furnished by the project proponent.

(i) As the project road falls within 10 km radius from Kaundinya Wildlife Sanctuary at 2.2 km. Necessary prior clearance from NBWLshall be obtained.

(ii) The proposal indicates the acquisition of 67.12 ha Forest land including land within Sanctuary. Necessary stage -I forestry clearance shall be obtained.

(iii) It is indicated that 1,50,000 nos. trees fall within the proposed RoW, however, bare minimum trees to be cut, the information should be provided about their species and whether it also involved any protected or endangered species. Necessary green belt shall be provided on both side of the highway with proper central verge and cost provision should be made for regular maintenance.

(iv) Committee noted that the project road passes through Rayala Elephant Reserve/Palamaner Reserved Forest for a length of 2 • 7.083 km and requires 63.747 ha land acquisition. Submit the details of the elephant corridors.

(v) Submit the details of the water bodies along the project road.

(vi) Explore the possibilities for utilization of fly ash.

(vii) Explore the possibilities of cooled mixed technology instead of hot mixed technology.

(viii) Submit details on borrow areas as per OMdated 18.12.2012.

(ix) Examine and submit a brief description of the project, project name, nature, size, its importance to the region/ state and the country.

(x) As the project involves diversion of forests land, guidelines under OM dated 20.03.2013(Annexure-I) may be followed and necessary action taken accordingly.

(xi) Details of any litigation(s) pending against the project and/or any directions or orders passed by any court of law/any statutory authority against the project to be detailed out.

(xii) Submit detailed alignment plan, with details such as nature of terrain (plain, rolling, hilly), land use pattern, habitation, cropping pattern, forest area, environmentally sensitive areas, mangroves, notified industrial areas, sand dunes, sea, rivers, lakes, details of villages, teshils, districts and States, latitude and longitude for important locations falling on the alignment by employing remote sensing techniques followed by "ground truthing" and also through secondary data sources.

(xiii) Describe various alternatives considered, procedures and criteria adopted for selection of the final alternative with reasons.

(xiv) Submit Land use map of the study area to a scale of 1: 25,000 based on recent satellite imagery delineating the crop lands (both single and double crop), agricultural plantations, fallow lands, waste lands, water bodies, built-up areas, forest area and other surface features such as railway tracks, ports, airports, roads, and major industries etc. and submit a detailed ground survey map on 1:2000 scale showing the existing features falling within the right of way namely trees, structures including archeological & religious, monuments etc. if any.

(xv) If the proposed route is passing through any hilly area, examine and submit the measures for ensuring stability of 3 •

slopes and proposed measures to control soil erOSIOnfrom embankment.

(xvi) If the proposed route involves tunneling, the details of the tunnel and locations of tunneling with geological structural fraction should be provided. In case the road passes through a flood plain of a river, the details of micro-drainage, flood passages and information on flood periodicity at least of the last 50 years in the area should be examined.

(xvii) If the project is passing through/located within the notified ecologically sensitive zone (ESZ) around a notified National Park/Wildlife Sanctuary or in the absence of notified ESZ, within 10 km from the boundary of notified National Park/ Wildlife Sanctuary, the project proponent may simultaneously apply for the clearance for the standing committee of NBWL. The EC for such project would be subject to obtaining this clearance from the standing committee of NBWL.

(xviii)Study regarding the Animal bypasses/underpasses etc. across the habitation areas shall be carried out. Adequate cattle passes for the movement of agriculture material shall be provided at the stretches passing through habitation areas. Underpasses shall be provided for the movement of Wild animals.

(xix) The information should be provided about the details of the trees to be cut including their species and whether it also involves any protected or endangered species. Measures taken to reduce the number of the trees to be removed should be explained in detail. Submit the details of compensatory plantation. Explore the possibilities of relocating the existing trees.

(xx) Necessary green belt shall be provided on both sides of the highway with proper central verge and cost provision should be made for regular maintenance.

(xxi) If the proposed route is passing through a city or town, with houses and human habitation on either side of the road, the necessity for provision of bypasses/diversions/under passes shall be examined and submitted. The proposal should also indicate the location of wayside amenities, which should include petrol stations/service centres, rest areas including public conveyance, etc.

(xxii) Submit details about measures taken for the pedestrian safety and construction of underpasses and foot-over bridges along with flyovers and interchanges.

4 (xxiii)Assess whether there is a possibility that the proposed project • will adversely affect road traffic in the surrounding areas (e.g. by causing increases III traffic congestion and traffic accidents).

(xxiv)Examine and submit the details of use of fly ash in the road construction, if the project road is located within the 100 kms from the Thermal Power Plant.

(xxv) Explore the possibilities of utilizing the debrisj waste materials available in and around the project area.

(xxvi) Submit the details on compliance with respect to Research Track Notification of MoRTH.

(xxvii)Examine and submit the details of sand quarry and borrow area as per OM no.2-30j2012-IA-III dated 18.12.2012 on 'Rationalization of procedure for Environmental Clearance for Highway Projects involving borrow areas for soil and earth" as modified vide OM of even no. dated March 19, 2013.

(xxviii) Climate and meteorology (max and min temperature, relative humidity, rainfall, frequency of tropical cyclones and snow fall); the nearest IMD meteorological station from which climatological data have been obtained to be indicated.

(xxix)The air quality monitoring should be carried out as per the notification issued on 16th November, 2009. Input data used for Noise and Air quality modeling shall be clearly delineated.

(xxx) The base line data used for the EIA shall be not more than one year old.

(xxxi)Identify project activities during construction and operation phases, which will affect the noise levels and the potential for increased noise resulting from this project. Discuss the effect of noise levels on nearby habitations during the construction and operational phases of the proposed highway. Identify noise reduction measures and traffic management strategies to be deployed for reducing the negative impact if any. Prediction of noise levels should be done by using mathematical modeling at different representative locations.

(xxxii)Examine the impact during construction activities due to generation of fugitive dust from crusher units, air emissions from hot mix plants and vehicles used for transportation of materials and prediction of impact on ambient air quality using appropriate mathematical model, description of model, input requirement and reference of derivation, distribution of

5 •

major pollutants and presentation In tabular form for easy interpretation shall be carried out.

(xxxiii) Also examine and submit the details about the protection to existing habitations from dust, noise, odour etc. during construction stage.

(xxxiv) If the proposed route involves cutting of earth, the details of area to be cut, depth of cut, locations, soil type, volume and quantity of earth and other materials to be removed with location of disposal/ dump sites along with necessary perrmssron.

(xxxv) If the proposed route is passing through low lying areas, details of filling materials and initial and final levels after filling above MSL, should be examined and submit.

(xxxvi) Examine and submit the water bodies including the seasonal ones within the corridor of impacts along with their status, volumetric capacity, quality and likely impacts on them due to the project along with the mitigation measures.

(xxxvii)Examine and submit details of water quantity required and source of water including water requirement during the construction stage with supporting data and also classification of ground water based on the CGWAclassification.

(xxxviii)Examine and submit the details of measures taken during constructions of bridges across rivers/canals / major or minor drains keeping in view the flooding of the rivers and the life span of the existing bridges. Provision of speed breakers, safety signals, service lanes and foot paths should be examined at appropriate locations through out the proposed road to avoid accidents.

(xxxix) If there will be any change in the drainage pattern after the proposed activity, details of changes shall be examined and submitted.

(xl) Rain water harvesting pit should be at least 3 - 5 m. above the highest ground water table. Provision shall be made for oil and grease removal from surface runoff.

(xli) If there is a possibility that the construction/widening of road may cause an impact such as destruction of forest, poaching or reduction in wetland areas, examine the impact and submit details.

6 (xlii) Submit the details of road safety, signage, service roads, • vehicular under passes, accident prone zones and the mitigation measures.

(xliii) IRC guidelines shall be followed for widening & upgradation of roads.

(xliv) Submit details of social impact assessment due to the proposed construction of the road.

(xlv) Examine road design standards, safety equipment specifications and Management System training to ensure that design details take account of safety concerns and submit the traffic management plan.

(xlvi) Accident data and geographic distribution should be reviewed and analyzed to predict and identify trends - in case of expansion of the existing highway and provide Post accident emergency assistance and medical care to accident victims.

(xlvii)If the proposed project involves any land reclamation, details to be provided of the activity for which land is to be reclaimed and the area of land to be reclaimed.

(xlviii)Details of the properties, houses, business activities etc likely to be effected by land acquisition and an estimation of their financial losses.

(xlix) Detailed R&R plan with data on the existing socio-economic status of the population in the study area and broad plan for resettlement of the displaced population, site for the resettlement colony, alternative livelihood concerns/ employment and rehabilitation of the displaced people, civil and housing amenities being offered, etc and the schedule of the implementation of the specific project

(1) Submit environment management and monitoring plan for construction and operation phases of the project. Submit a copy of your corporate policy on environment management and sustainable development.

(li] Estimated cost of the project including that of environment management plan (both capital and recurring) and source of funding. Also, the mode of execution of the project, viz. EPC, BOT, etc.

(Iii) Submit a copy of your CSR policy and plan for meeting the expenditure to address the issues raised during Public Hearing.

7 •

(liii) Any further clarification on carrying out the above studies including anticipated impacts due to the project and mitigative measure, project proponent can refer to the model ToR available on Ministry website "httpr/ yrnoef.nic.iny Marrual/ Highways".

General Guidelines

(i) The EIA document shall be printed on both sides, as far as possible.

(ii) The status of accreditation of the EIA consultant with NABET/ QCI shall be specifically mentioned. The consultant shall certify that his accreditation is for the sector for which this EIA is prepared.

(iii) On the front page of EIA/EMP reports, the name of the consultant/ consultancy firm along with their complete details including their accreditation, if any shall be indicated. The consultant while submitting the EIA/EMP report shall give an undertaking to the effect that the model TORs have been complied with and the data submitted is factually correct (Refer MoEF Office Memorandum No. J-l1013/41/2006-IA.II(I) dated 4th August, 2009).

(iv) While submitting the EIA/EMP reports, the name of the experts associated with/ involved in the preparation of these reports and the laboratories through which the samples have been analysed should be stated in the report. It shall clearly be indicated whether these laboratories are approved under the Environment (Protection) Act, 1986 and the rules made there under (Please refer MoEF Office Memorandum No. J- 11013/41/2006-IA.II(I) dated 4th August, 2009). The project leader of the EIA study shall also be mentioned.

(v) Environmental Management Plan presented before the EAC as a part of EIA report, shall be made part of Concessionaire Agreement/ other relevant documents. Proponent shall submit an undertaking in this regard.

(vi) Since most of the environmental issues are related to design parameters, following additional information should also be provided by PP apart from the information required as per Chapter - 12 of the EIA Guideline manual for Highways (Disclosure of Consultant)

a) Name of the Design Consultant.

b) Name of the EIA consultant, EIA Coordinator, Functional Area Expert and details of accreditation. 8 •• (vii) The EIA report shall be prepared as per the EIA Notification, 2006, as amended from time to time.

Public hearing to be conducted for the project as per provisions of Environmental Impact Assessment Notification, 2006 and the issues raised by the public should be addressed in the Environmental Management Plan.

A detailed draft EIAjEMP report should be prepared as per the above additional TOR and should be submitted to the Ministry as per the Notification.

The prescribed ToRs would be valid for a period of two years for submission of the EIAjEMP Reports, after public consultation.

(Lali Kapur) Director (lA-III) Copy to: 1. The Member Secretary, Karnataka State Pollution Control Board, Paryavaran Parisar, 4th & 5th Floor, # 49, Church Street, Bangaluru - 560001 2. The Member Secretary, Andhra Pradesh Pollution Control Board, Paryarana Bhawan, A-III, Industrial Area, Sanathnagar, Hyderbabad - 500018, Andhra Pradesh 3. The Member Secretary, Tamil Nadu State Pollution Control Board, 76, Mount Salai, Guindy, Chennai-600032

9