The Answer Is Blowing in the Wind?
Total Page:16
File Type:pdf, Size:1020Kb
Load more
Recommended publications
-
Preliminary Incident Report - Trip of Torrens Island a and B West 275 Kv Busbars on 12 March 2021
Preliminary Incident Report - Trip of Torrens Island A and B West 275 kV busbars on 12 March 2021 March 2021 A preliminary operating incident report for the National Electricity Market – information as at 16/03/2021 ABBREVIATIONS Abbreviation Term AEMC Australian Energy Market Commission AEMO Australian Energy Market Operator AEST Australian Eastern Standard Time LOR Lack of Reserve NEM National Electricity Market NER National Electricity Rules TNSP Transmission Network Service Provider © AEMO 2021 | Preliminary Incident Report - Trip of Torrens Island A and B West 275 kV busbars on 12 March 2 2021 Important notice PURPOSE AEMO has prepared this preliminary report as part of its review of the reviewable operating incident involving trip of Torrens Island 275 kV West busbar in South Australia on 12 March 2021 as a first step in reporting under clause 4.8.15(c) of the National Electricity Rules. The observations in this report will be updated in AEMO’s final operating incident report, where new information becomes available. DISCLAIMER AEMO has been provided with preliminary data by Registered Participants as to the performance of some equipment leading up to, during and after the event in accordance with clause 4.8.15 of the National Electricity Rules. In addition, AEMO has collated preliminary information from its own systems. Any analysis and conclusions expressed in this document are also of a preliminary nature. While AEMO has made every reasonable effort to ensure the quality of the information in this report, its investigations are incomplete, and any findings expressed in it may change as further information becomes available and further analysis is conducted. -
Project Energyconnect Review of Economic Assessment
Project EnergyConnect Review of economic assessment 31 March 2021 Project EnergyConnect Review of economic assessment Copyright and Disclaimer Copyright in this material is owned by or licensed to ElectraNet. Permission to publish, modify, commercialise, or alter this material must be sought directly from ElectraNet. Reasonable endeavours have been used to ensure that the information contained in this report is accurate at the time of writing. However, ElectraNet gives no warranty and accepts no liability for any loss or damage incurred in reliance on this information. Revision Record Date Version Description Author Checked By Approved By 31 Mar 2021 1.0 For submission to the Brad Harrison Simon Appleby Rainer Korte AER and publication Hugo Klingenberg Page 1 of 12 Project EnergyConnect Review of economic assessment Project EnergyConnect material change in circumstances assessment Executive Summary On 14 September 2020, ElectraNet submitted an updated economic cost benefit analysis for Project EnergyConnect (PEC) to the AER for approval. The AER confirmed on 28 September 2020 that: “…the AER considers that the updated cost benefit analysis provides a not unreasonable basis for ElectraNet’s opinion that PEC remains the preferred option. We expect both ElectraNet and TransGrid to submit full and complete contingent project applications for PEC as soon as possible.” On 29 September 2020, the ElectraNet Board approved submission of a contingent project application (CPA) based on the AER’s confirmation and the CPA was submitted to the AER on 30 September 2020. This note reviews several subsequently announced policies and other changes in the National Electricity Market (NEM) and considers the impact that these could have on the benefits of PEC. -
Clean Energy Fact Sheet We All Want Affordable, Reliable and Clean Energy So We Can Enjoy a Good Quality of Life
Clean Energy fact sheet We all want affordable, reliable and clean energy so we can enjoy a good quality of life. This fact sheet sets out how we’re leading a transition from fossil fuels to cleaner forms of energy. Background Minimising or, where we can, avoiding financial EnergyAustralia is one of the country’s biggest hardship is part of the challenge as we transition generators of power from fossil fuels. Each to cleaner generation. We need to do this while preserving the reliability of supply. +800 MW year we produce around 20 million tonnes Rights to of greenhouse gases, mostly carbon dioxide Our approach involves supporting the renewable energy or CO₂, from burning coal and gas to supply development of clean energy while helping our electricity to our 2.4 million accounts across customers manage their own consumption so eastern Australia. they use less energy. Because when they do For around a century, coal-fired power plants that, they generate fewer emissions and they ~$3B have provided Australians with reliable and save money. Long term affordable power and supported jobs and renewable Supporting renewable energy agreements economic development. The world is changing with fossil fuel generation being replaced by Right now, EnergyAustralia has the rights to lower emissions technologies. more than 800 MW worth of renewable energy, combining solar and wind farm power purchase The way we generate, deliver and use energy agreements, and we half-own the Cathedral 7.5% has to change. As a big emitter of carbon, it’s Rocks wind farm. Of large-scale up to us to lead the transition to cleaner energy wind and solar in a way that maintains that same reliable and project in the NEM affordable access to energy for everyone. -
BUILDING STRONGER COMMUNITIES Wind's Growing
BUILDING STRONGER COMMUNITIES Wind’s Growing Role in Regional Australia 1 This report has been compiled from research and interviews in respect of select wind farm projects in Australia. Opinions expressed are those of the author. Estimates where given are based on evidence available procured through research and interviews.To the best of our knowledge, the information contained herein is accurate and reliable as of the date PHOTO (COVER): of publication; however, we do not assume any liability whatsoever for Pouring a concrete turbine the accuracy and completeness of the above information. footing. © Sapphire Wind Farm. This report does not purport to give nor contain any advice, including PHOTO (ABOVE): Local farmers discuss wind legal or fnancial advice and is not a substitute for advice, and no person farm projects in NSW Southern may rely on this report without the express consent of the author. Tablelands. © AWA. 2 BUILDING STRONGER COMMUNITIES Wind’s Growing Role in Regional Australia CONTENTS Executive Summary 2 Wind Delivers New Benefits for Regional Australia 4 Sharing Community Benefits 6 Community Enhancement Funds 8 Addressing Community Needs Through Community Enhancement Funds 11 Additional Benefts Beyond Community Enhancement Funds 15 Community Initiated Wind Farms 16 Community Co-ownership and Co-investment Models 19 Payments to Host Landholders 20 Payments to Neighbours 23 Doing Business 24 Local Jobs and Investment 25 Contributions to Councils 26 Appendix A – Community Enhancement Funds 29 Appendix B – Methodology 31 References -
LIVERPOOL RANGE WIND FARM Project Update - November 2009
LIVERPOOL RANGE WIND FARM Project Update - November 2009 INTRODUCTION WELCOME to the Liverpool Range Wind Farm Project Update. The Liverpool Range Wind Farm Project is a new development project being considered by Epuron Pty Ltd. The proposed wind farm is at the early stages of planning and geographical perimeters are still being considered. PROJECT AREA SITE SELECTION The Liverpool Range Project (LVP) area is located in Why is this a good area for wind energy? the Warrumbungle Shire, nearby to the townships of The area has a number of favourable conditions for Coolah and Cassilis, 50 km North of Dunedoo. The site the development of a wind farm, including; comprises a series of ridgelines running NE/SW, where it • Relatively high wind speeds is expected the turbines could be located. The site • Cleared agricultural land may comprise separate discrete project areas/stages, • Relatively few dwellings with an ultimate potential of 200+ turbines. The project • Access to transmission design and capacity is driven by electrical connection • Community support suitability. Liverpool Ranges Proposed Project Area WHO IS EPURON? Epuron is a leading wind energy developer in NSW with over 1500MW of approved wind energy across 5 projects. Epuron is working on several projects, at various stages of development, totalling in excess of Epuron would like to thank the many local 2000MW, including the large scale Silverton project in landholders who have provided & continue to western NSW. Epuron projects which have already provide their support and commitment to this exciting received planning approval represent approx 72% of project. approved wind power capacity in NSW. -
Final Report
BLACK SYSTEM SOUTH AUSTRALIA 28 SEPTEMBER 2016 Published: March 2017 BLACK SYSTEM SOUTH AUSTRALIA 28 SEPTEMBER 2016 – FINAL REPORT IMPORTANT NOTICE Purpose AEMO has prepared this final report of its review of the Black System in South Australia on Wednesday 28 September 2016, under clauses 3.14 and 4.8.15 of the National Electricity Rules (NER). This report is based on information available to AEMO as of 23 March 2017. Disclaimer AEMO has been provided with data by Registered Participants as to the performance of some equipment leading up to, during, and after the Black System. In addition, AEMO has collated information from its own systems. Any views expressed in this update report are those of AEMO unless otherwise stated, and may be based on information given to AEMO by other persons. Accordingly, to the maximum extent permitted by law, AEMO and its officers, employees and consultants involved in the preparation of this update report: make no representation or warranty, express or implied, as to the currency, accuracy, reliability or completeness of the information in this update report; and, are not liable (whether by reason of negligence or otherwise) for any statements or representations in this update report, or any omissions from it, or for any use or reliance on the information in it. © 2017 Australian Energy Market Operator Limited. The material in this publication may be used in accordance with the copyright permissions on AEMO’s website. Australian Energy Market Operator Ltd ABN 94 072 010 327 www.aemo.com.au [email protected] NEW SOUTH WALES QUEENSLAND SOUTH AUSTRALIA VICTORIA AUSTRALIAN CAPITAL TERRITORY TASMANIA WESTERN AUSTRALIA BLACK SYSTEM SOUTH AUSTRALIA 28 SEPTEMBER 2016 – FINAL REPORT NER TERMS, ABBREVIATIONS, AND MEASURES This report uses many terms that have meanings defined in the National Electricity Rules (NER). -
Project Energyconnect: Updated Cost Benefit Analysis
PROJECT ENERGYCONNECT Updated Cost Benefit Analysis 30 September 2020 Project EnergyConnect: Updated Cost Benefit Analysis Copyright and Disclaimer Copyright in this material is owned by or licensed to ElectraNet. Permission to publish, modify, commercialise or alter this material must be sought directly from ElectraNet. Reasonable endeavours have been used to ensure that the information contained in this report is accurate at the time of writing. However, ElectraNet gives no warranty and accepts no liability for any loss or damage incurred in reliance on this information. Revision Record Date Version Description Author Checked By Approved By 9 Sep 2020 Final Final draft for AER review Brad Harrison Hugo Klingenberg Rainer Korte Draft Simon Appleby 30 Sep 2020 Final Final for publication Brad Harrison Simon Appleby Rainer Korte Page 2 of 35 Project EnergyConnect: Updated Cost Benefit Analysis Executive Summary Project EnergyConnect (PEC) is the proposed new 330 kV electricity interconnector between Robertstown in South Australia and Wagga Wagga in New South Wales that also includes a short 220 kV line from Buronga in New South Wales and Red Cliffs in northwest Victoria. ElectraNet completed the Regulatory Investment Test for Transmission (RIT-T) with the release of a Project Assessment Conclusion Report (PACR) on 13 February 2019, which concluded that Project EnergyConnect was the preferred option that satisfied the requirements of the RIT-T. On 24 January 2020 the Australian Energy Regulator (AER) issued a formal determination that found that ElectraNet had correctly identified Project EnergyConnect as the preferred option. The National Electricity Rules (NER) require ElectraNet to consider whether, in its reasonable opinion, there has been a “material change in circumstances” that might lead to a change in the preferred option and thereby potentially require reapplication of the RIT-T. -
Application for Generation License
Application for Generation License Lal Lal Wind Farms Nom Co Pty Limited ABN: 37 625 768 774 Website: www.lallalwindfarms.com.au Tel: 1800 187 183 2 TABLE OF CONTENTS 1. Information on the Applicant and Nature of the application ____________ 4 1.1 Introduction __________________________________________________________ 4 1.2 Applicant Details ______________________________________________________ 5 1.3 Corporate Structure ____________________________________________________ 5 1.4 Organisational Structure ________________________________________________ 6 1.5 Project Expertise ______________________________________________________ 8 1.6 Experience of Key Personnel ____________________________________________ 11 1.7 Details of key contracts and agreements ___________________________________ 12 1.8 Planning and Environment ______________________________________________ 16 2. Essential services commisson objectives _________________________ 19 2.1 Efficiency in the industry and incentives for long term investment _____________ 19 2.2 Financial viability of the industry _______________________________________ 19 2.3 The degree of, and scope for, competition within the industry, including countervailing market power and information asymmetries ___________________________________ 20 2.4 The relevant health, safety, environmental and social legislation applying to the industry ________________________________________________________________ 20 2.5 The benefits and costs of regulation for consumers and regulated entities _______ 20 3. Information -
Macarthur Wind Farm Will Contain 140 Wind-Turbines, Enough Energy to Generate Power to 220,000 Victorian Households
Image The Macarthur Wind Farm will contain 140 wind-turbines, enough energy to generate power to 220,000 Victorian households. SUSTAINABLE ENERGY AGL Energy Limited, one of Australia’s such as noise. These studies have been AGL and Meridian, through their leading renewable energy companies complemented through a panel hearing development of the Macarthur Wind Farm, AGL Energy Limited is developing the Macarthur Wind Farm and largest private owner, operator process whereby interested stakeholders were have invested several millions of dollars with its joint venture partner, Meridian Energy, which will be the and developer of renewable generation provided with the opportunity to comment into local infrastructure, including roads. In largest wind farm in the Southern Hemisphere. assets is developing the Macarthur Wind on the development and provide additional particular, the Macarthur-Hawkesdale Road Farm with its joint venture partner, proposals for consideration by the panel. The has been redeveloped between Macarthur MAIN CONStructiON COMPANY : Leighton Contractors Meridian Energy. outcome of this process was the successful and the wind farm site, as has Tarrone OwnERS : AGL Energy Ltd & Meridian Energy PROJECT ManagEMENT : KBR issue of a planning permit to build and North Road from Woolsthorpe to Heywood VEStaS ELECTRICAL DESIGN : Consolidated Power Projects The project will become the largest wind farm operate the Macarthur Wind Farm. Road to the Tarrone site. Additional funding CIVIL DESIGN : Robert Bird Group in the Southern Hemisphere and is located has also been provided directly to both GEOTECHNICAL ENGINEERS : Coffey Geotechics approximately 16km east of the township An Engineer Procure and Construct (EPC) Moyne Shire and VicRoads to facilitate PROJECT END VALUE : $1 Billion of Macarthur in Western Victoria. -
Generator Technical and Cost Parameters
Generator Technical and Cost Parameters ElectraNet Reference: 508986 Revision: 2 FINAL 2020-07-23 Document control record Document prepared by: Aurecon Australasia Pty Ltd ABN 54 005 139 873 Level 10, 55 Grenfell Street Adelaide SA 5000 Australia T +61 8 8237 9777 F +61 8 8237 9778 E [email protected] W aurecongroup.com A person using Aurecon documents or data accepts the risk of: a) Using the documents or data in electronic form without requesting and checking them for accuracy against the original hard copy version. b) Using the documents or data for any purpose not agreed to in writing by Aurecon. Document control Report title DocumentGenerator title Technical and Cost Parameters Document code Project number 508986 File path 508986-REP-ElectraNet-Generator Technical And Cost Parameters-23July2020.docx Client ElectraNet Client contact Bradley Harrison Client reference Rev Date Revision details/status Author Reviewer Verifier Approver (if required) 0 2020-04-22 Preliminary Draft for Client MSG SHM RD review 1 2020-06-03 Revised Draft - Updates to SHM MSG RD Sections 3.1, 4.1.1, and 4.3.2 2 2020-07-23 Final Issue SHM MSG RD Current revision 2 Approval Author signature Approver signature Name Shannon Moss Name Ric Darley Title Senior Power Generation Title Technical Director Engineer Project number 508986 File 508986-REP-ElectraNet-Technical And Cost Parameters-23July2020.docx 2020-07-23 Revision 2 Contents Executive summary ......................................................................................................................................... -
Wind Farm Guide for Host Landholders
wind farm guide for host landholders Overview of wind energy in NSW Prospecting Understanding potential impacts Negotiating agreements Planning and Development Engaging with local stakeholders Construction Operation Decommissioning Where to go for more advice This Wind farm guide for host landholders 1. has been prepared by GHD Pty Ltd (“GHD”) for the NSW Farmers’ Association (“NSW Farmers”) 2. may only be used and relied on by NSW Farmers; 3. must not be copied to, used by, or relied on by any person other than NSW Farmers without the prior written consent of GHD; 4. may only be used for the purpose of assisting wind farm host landholders in NSW (and must not be used for any other purpose). GHD and its servants, employees and officers otherwise expressly disclaim responsibility to any person other than NSW Farmers arising from or in connection with this Guide. To the maximum extent permitted by law, all implied warranties and conditions in relation to the services provided by GHD and the Guide are excluded unless they are expressly stated to apply in this Guide. The opinions, conclusions and any recommendations in this Guide are based on assumptions made by GHD. GHD expressly disclaims responsibility for any error in, or omission from, this Guide arising from or in connection with any of the Assumptions being incorrect. Subject to the paragraphs in this section of the Guide, the opinions, conclusions and any recommendations in this Guide are based on conditions encountered and information reviewed at the time of preparation and may be relied on until 2014 after which time, GHD expressly disclaims responsibility for any error in, or omission from, this Guide arising from or in connection with those opinions, conclusions and any recommendations. -
2016 South Australian Electricity Report
SOUTH AUSTRALIAN ELECTRICITY REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS Published: August 2016 SOUTH AUSTRALIAN ELECTRICITY REPORT IMPORTANT NOTICE Purpose The purpose of this publication is to provide information about South Australia’s electricity supply and demand. While some historic price information is provided for completeness, this publication does not present any views on the effectiveness of price signals in the National Electricity Market. AEMO publishes this South Australian Electricity Report in accordance with its additional advisory functions under section 50B of the National Electricity Law. This publication is based on information available to AEMO as at 1 July 2016, although AEMO has endeavoured to incorporate more recent information where practical. Disclaimer AEMO has made every effort to ensure the quality of the information in this publication but cannot guarantee that information, forecasts and assumptions are accurate, complete or appropriate for your circumstances. This publication does not include all of the information that an investor, participant or potential participant in the South Australian electricity market might require, and does not amount to a recommendation of any investment. Anyone proposing to use the information in this publication (including information and reports from third parties) should independently verify and check its accuracy, completeness and suitability for purpose, and obtain independent and specific advice from appropriate experts. Accordingly, to the maximum extent permitted by law, AEMO and its officers, employees and consultants involved in the preparation of this publication: make no representation or warranty, express or implied, as to the currency, accuracy, reliability or completeness of the information in this publication; and are not liable (whether by reason of negligence or otherwise) for any statements, opinions, information or other matters contained in or derived from this publication, or any omissions from it, or in respect of a person’s use of the information in this publication.