Contents

1.0 Design Team 2.0 Introduction 3.0 Vision/Brief 4.0 Site & Context 5.0 Site Location 6.0 Site Photographs 7.0 Outdoor Amenity 8.0 Planning Drawings 9.0 Design Description 10.0 Proposed Materials 11.0 Illustrative Views 12.0 Consultation 13.0 Construction Management Strategy 14.0 AY Architects Profile

Document Control

Revision Date Description Author Status - 21.04.16 - AB Planning Eleanor Palmer Science & Technology Lab / Design & Access Statement

1.0 Design Team

Client Eleanor Palmer Primary School Lupton Street NW5 2DB

AY Architects Architect Studio 23 AY Architects 25-27 Bickerton Road London N19 5JT

Ritchie + Daffin Environmental / Studio D, Holborn Studios Building Services 49/50 Eagle Wharf Road London N1 7ED

Stockdale Chartered QS Cost Consultant 58 Streatham High Road London SW16 1DA

Price & Myers Structural Engineer 37 Alfred Place London WC1E 7DP Eleanor Palmer Science & Technology Lab / Design & Access Statement

2.0 Introduction

Introduction

AY Architects have been working with Eleanor Palmer Primary School located on Lupton Street in to develop the design of a small Science & Technology classroom building on the school grounds.

The new facility will provide opportunities for pupils to engage with science in a stimulating high quality and innovative purpose-built environment that promotes the learning of science within the school and with other schools and the local community.

The project is funded by Section 106 fund for science and technology facilities. An outline feasibility assessment was carried out on behalf of LB Camden by Curl la Tourelle Architects [CLTA] in December 2014 as part of the project selection stage.

The proposal for the science lab building has developed with the involvement of the school’s “Lab RATS” (Radical Architecture Technology & Science) made up of teachers, staff, governors, parents in the field and pupils.

Pre-planning advice was sought for a concept design proposal and revisions have been included in the design now seeking planning approval.

a“curiosity” cupboard of science Eleanor Palmer Science & Technology Lab / Design & Access Statement

3.0 Vision / Brief

Vision

The vision for the project is to create a high quality and inspiring place that fosters curiosity and wonder of the world that is engaging for school children both inside and outside. This should involve an understanding of the building, not as a conventional classroom, but as ‘living’ tool box of science and technology.

The building should be a place of discovery and stimulating experimentation with a spatial quality that engages with the physical environment; nature, light, sky, structure, materials and mechanical systems. The building should be an instrument that supports the school curriculum, which one can read and analyse its parts.

Brief

The brief is to create a single flexible classroom space for 31 children aged 3-11 years and a maximum of 4 adults for teaching science and technology. In addition to supporting the school curriculum the science lab will be used for after school clubs and cooking groups and be made available for use by other schools and the neighbouring community.

Gillespie Primary School Lab 13 - display of pupil work and equipment The science lab is to be equipped with fittings for cooking (ovens and hobs) and sinks for teacher-led learning and experiments and working in small groups of 5-6. Moveable tables will allow flexible arrangements to suit different types of teaching and an interactive whiteboard should be included for traditional teaching in front of children sitting on a carpet. It is important that the facility includes sufficient storage and different types of display for equipment and materials to present a variety of pupils work.

AY Architects worked with the school in researching the brief by examining the national science curriculum in England, particularly the statutory guidance for ‘Science Programmes of Study: Key Stages 1 and 2’. They sought ways in which the building could respond creatively to the major topics of the curriculum. This included attending science lessons in the school itself and examining successful examples of science teaching in other primary schools in London. Together with a group of Eleanor Palmer staff and pupils, they visited Gillespie Primary School Lab 13: an outstanding science and technology classroom managed by pupils with the guidance of a scientist in Residence.

The science lab should engage with an outdoor “science garden” to further support outdoor activities / experiments such dealing with weather/sky, light, nature, energy etc. The design of the science garden is being developed with the involvement of inspirational artists engaged in interactive scientific equipment and devices for learning. Gillespie Primary School Lab 13 - testing experiments Eleanor Palmer Science & Technology Lab / Design & Access Statement

4.0 Site & Context

Eleanor Palmer Primary School is located in Kentish Town between Lupton Street to the east, Fortess Road to the west and Raveley Street to the north. The main school entrance is from Lupton Street, with secondary (maintenance) access from Raveley Street.

Site Development History

Acland School was the first school building on the site, opening in 1898. The original 3 story Victorian school building was situated at the centre of the original site, understood to be the current playground and ball court adjacent to Fortess Road, surrounded by a high brick boundary wall. The original school building was demolished when nearby was built in the late 1960’s. Eleanor Palmer Primary School was built soon after when the site was enlarged towards Lupton Street.

The existing school buildings are one and two storey brick with shallow tiled gable roofs. The main entrance of the school is charcaterised by a painted steel and glass canopy connecting the admin office, hall and classroom buildings. The open canopy structure located along the boundary with Fortess Road is a remnant from the Victorian school but the roof has been altered and refinished.

The only development to take place on the site following the 1970’s is a single storey extension built in 2004 to the east elevation fronting Lupton Street providing a staff meeting room and the erection of a timber clad classroom outbuilding at the north of the site in 2013.

Aerial View from South-East The school is not situated within a conservation area. The Kentish Town Conservation Area is located to the south of the site but does not boarder onto the school.

Transport & Access

There is no envisaged increase in pupil numbers as a result of the development although the use of the facility will be open to the community and local schools.

The school is well served by public transport, situated only 5 mins walk from Underground Station (Northern Line) and within 10 mins from a number of bus routes. Bus No.134 stops on Fortess Road outside the school, Bus Nos. 4 and 390 stop at Tufnell Park Station and additional routes serve Kentish Town within 10 mins walking distance. Kentish Town Thameslink Railway Station is also located within 10 mins walking distance. Currently there is a small provision for cycle parking in front of the school on Lupton Street. There is currently no provision for car parking on the site.

The original Victorian Acland School Building, 1898 Eleanor Palmer Science & Technology Lab / Design & Access Statement

4.0 Site & Context (con’t)

Topography

The school sits at the top of a hill and the natural topography slopes away from the school to the south and west. The ball court sits about 1.2m lower then the school buildings. The original brick boundary wall retains a change in level between the ball court and Fortess Road. The difference in level here at the centre of school grounds is approximately 1.5m.

Landscape & Trees

The school external areas are made up of a mix of planted and paved areas, with the majority of paved areas located in the playgrounds and ball courts on the western half of the site.

There are some trees on the site, the majority which are clustered at the southern boundary. A few trees are located in the infants playground at the northwest corner of the site. Here, a mature tree is being proposed for removal along the boundary wall due to it’s detrimental effect on the structural integrity of wall. The school has been liaising with Camden arboricultural department regarding its removal.

There are no Tree Protection Orders [TPO’s] on the site.

The original boundary wall as seen from Fortess Road looking north (with proposed tree for removal in background)

The classroom outbuilding built in 2013 Existing School Entrance on Lupton Street Eleanor Palmer Science & Technology Lab / Design & Access Statement

4.0 Site & Context (con’t)

Surrounding Context

The surrounding context of Eleanor Palmer Primary is made up of a mix of residential, commercial/retail, light industrial and educational uses.

The residential stock is predominantly made up of 3-4 storey Victorian townhouses. There are rows of shops located along Fortess Road with a concentration of small independent retailers located directly to the north of the school on both the east and west sides of

Acland Burghley School Main Entrance (1969) The Junction Tavern Public House - Fortess Road the road. Acland Burghley Secondary School is located at the junction of Fortess Road with Dartmouth Park Hill.

Architectural Character

The architectural character of surrounding buildings is varied. This ranges from mid to late 19th century stock brick terraced and semi-detached houses and warehouses of the same era, to contemporary developments built in the post-war era and in recent years.

The Victorian Junction Tavern public house sits opposite the school on Fortess road, while the character of Fortess Road is made up of both traditional and contemporary painted shop fronts, many of which have been altered and extended over the years.

Modernist concrete and brick buildings from the 1960’s and 1970’s, including that of the school, contribute largely to the character of the area. Acland Burghley School is a predominately concrete “brutalist” architecture. Acland Burghley School Hall Building (1969) Two-storey painted timber shopfronts Fortess Road - West Side Recent developments in the area include more contemporary render, timber and aluminium clad flat roof buildings, such as the 5 storey Junction Housing development on Junction Road close to Tufnell Park Station.

The Junction Housing Development Fortess Road (2014) Otis Yard accessed from Southcote Road (2014) Eleanor Palmer Science & Technology Lab / Design & Access Statement

5.0 Site Location

43

116 37 to

114 35

112 Surgery Proposed Site Location 103 Lady Raveley Somerset St 43

116 37 to Road 27 St The proposed location for the Science Lab Building is the site of the existing canopy

114 35 F E Lupton structure located along the western boundary fronting Fortess Road. 112 Surgery D

8 101 The preferred site for the building was initially identified in the feasibility assessment 103 Lady A Raveley Somerset St by CLT Architects involving the replacement of the canopy structure. This included a

99 Road Road 27 St provision for access to the facility for community use directly from Fortess Road.

Fortess F G E Eleanor Lupton Primary Palmer 27 95 School C D 27 AY Architects has assisted the school in investigating the feasibility of alternative locations

8 101 for the proposed building and have concluded that the site of the existing canopy A structure to be most suitable. The structure, although providing outdoor covered space, 91 99 B Road is dark and largely under-used for school activities, contributing very little to the outdoor

102 Fortess G Eleanor amenity of the school. Primary Palmer 27 95 School C 27 6 Community access to the facility has been concluded to be most viable via the main St

98 4 school entrance, as this best satisfies security and operational requirements. Lupton 91 B

102 Proposed Site : 6 Existing Canopy Structure

St

98 4 Lupton 2ND DRAFT

0 10.0 30.0M

LOCATION PLAN Key Location Plan 1:1000 (@ A3) DWG NO. : P001 2ND DRAFT REV : A - 11.04.16 A. Proposed Science Lab Building Site SCALE : 1:1000 @ A4 B. School entrance STATUS : PLANNING DATE : 31.03.16 C. Main building BY : NS

D. Classroom out building 0 10.0 DO30 NOT.0M SCALE OFF DRAWINGS / USE FIGURED DIMENSIONS ONLY E. New play area - replacing previous car parking area CHECK DIMENSIONS ON SITE / NOTIFY ARCHITECT OF DISCREPANCIES REFER TO STRUCTURAL ENGINEER DRAWINGS FOR STRUCTURAL F Infants playground LOCATION PLAN DESIGN Key G . Ball court COPYRIGHT: AY ARCHITECTS

DWG NO. : P001 1505 - ELEANOR PALMER SCIENCE LAB A. Proposed Science Lab Building Site REV : A - 11.04.16 SCALE : 1:1000 @ A4 C B. School entrance STATUS : PLANNING AY Architects DATE : 31.03.16 Studio 23, 25-27 Bickerton Road, London N19 5JT, UK C. Main building BY : NS LOCATION PLAN 1: 1000 @ A4 [t] ++44(0)20 7272 8899 [e] info@ayarchitects .com D. Classroom out building DO NOT SCALE OFF DRAWINGS / USE FIGURED DIMENSIONS ONLY E. New play area - replacing previous car parking area CHECK DIMENSIONS ON SITE / NOTIFY ARCHITECT OF DISCREPANCIES REFER TO STRUCTURAL ENGINEER DRAWINGS FOR STRUCTURAL F Infants playground DESIGN G. Ball court COPYRIGHT: AY ARCHITECTS 1505 - ELEANOR PALMER SCIENCE LAB

C AY Architects Studio 23, 25-27 Bickerton Road, London N19 5JT, UK LOCATION PLAN 1: 1000 @ A4 [t] ++44(0)20 7272 8899 [e] info@ayarchitects .com Eleanor Palmer Science & Technology Lab / Design & Access Statement

6.0 Site Photographs of Existing

view of the Main Building Entrance from the school entrance

view from ball court looking north view from ball court looking southwest view from ball court looking south

view from infants playground looking southeast view from Fortess Road looking south view from Fortess Road looking northeast Eleanor Palmer Science & Technology Lab / Design & Access Statement

7.0 Outdoor Amenity

Outdoor Amenity / Play Space

The maximum footprint of the proposed development has been assessed to be 82m2. This is equal to the area of new outdoor play space created by the school in the location of the pre-existing car park area along the north boundary and accessible from Raveley Street. This new playground space is located directly to the east of the existing infants playground with step-free access. It is asphalt and used as a football pitch for the infants school.

The proposed development would therefore not result in any loss of the school’s outdoor play area.

Raveley photograph of new playground area (former carpark) photograph of new playground area (former St carpark) looking west looking east

Raveley St

CAR PARK AREA CONVERTED TO 82m2 NEW INFANT'S PLAYGROUND AREA

Road

Fortess CAR PARK AREA CONVERTED CLASSROOM TO 82m2 NEW INFANT'S PLAYGROUND AREA OUT BUILDING INFANTS Road PLAYGROUND

Fortess CLASSROOM OUT BUILDING INFANTS PLAYGROUND PIERS + WALLS TO BE DEMOLISHED TOTAL FOOTPRINT = 1.30m2

PROPOSED SCIENCE LAB BUILDING FOOTPRINT = 83.30m2 PIERS + WALLS TO BE DEMOLISHED PROPOSED SCIENCETOTAL BUILDING FOOTPRINT FOOTPRINT = 1.30m 283.30m2 PLAYGROUND SUBTRACT PIERS + WALLS TO BE DEMOLISHED 1.30m2 = 82.00m2 PROPOSED SCIENCE LAB BUILDING 2 RECEPTION FOOTPRINT = 83.30m BUILDING PROPOSED SCIENCE BUILDING FOOTPRINT 83.30m2 PLAYGROUND SUBTRACT PIERS + WALLS TO BE DEMOLISHED 1.30m2 = 82.00m2

RECEPTION BALL COURT BUILDING

2nd DRAFT BALL COURT

0 1.0 2.0 7.0M

PLAY AREA LAYOUT AND ACCESS Measurements and calculations of carpark area converted into playground in comparison with the proposed building footprint STRATEGY 2nd DRAFT

DWG NO. : P013 REV : A - 11.04.16 SCALE : 1:200 @ A3 STATUS : PLANNING DATE : 31.03.16 0 1.0 2.0 7.0M BY : NS

DO NOT SCALE OFF DRAWINGS /PLAY USE FIGURED AREA DIMENSIONS LAYOUT ONLY AND ACCESS CHECK DIMENSIONS ON SITE / NOTIFY ARCHITECT OF DISCREPANCIES REFER TO STRUCTURAL ENGINEERSTRATEGY DRAWINGS FOR STRUCTURAL DESIGN COPYRIGHT: AY ARCHITECTS DWG NO. : P013 REV : A - 11.04.16 SCALE : 1:200 @ A3 1505 - ELEANOR PALMERSTATUS : PLANNING SCIENCE LAB DATE : 31.03.16

C BY : NS AY Architects Studio 23, 25-27 Bickerton RoadDO, NOTLondon SCALE N19 OFF 5JT DRAWINGS, UK / USE FIGURED DIMENSIONS ONLY [t] ++44(0)20 7272 8899 [e] info@ayarchitectsCHECK DIMENSIONS.com ON SITE / NOTIFY ARCHITECT OF DISCREPANCIES REFER TO STRUCTURAL ENGINEER DRAWINGS FOR STRUCTURAL DESIGN COPYRIGHT: AY ARCHITECTS

1505 - ELEANOR PALMER SCIENCE LAB

C AY Architects Studio 23, 25-27 Bickerton Road, London N19 5JT, UK [t] ++44(0)20 7272 8899 [e] [email protected] Eleanor Palmer Science & Technology Lab / Design & Access Statement

8.0 Planning Drawings

List of Planning Drawings

EXISTING & PROPOSED DRAWINGS 1505-P001 - Location Plan - Scale 1:1000 @A4 1505-P002 - Existing & Proposed Site Plan - Scale 1:200@A3 1505-P003 - Existing & Proposed Street Elevation (West) - Scale 1:200@A3 1505-P004 - Existing & Proposed Ground Floor Plan - Scale 1:100@A3 1505-P005 - Existing & Proposed Roof Plan - Scale 1:100@A3 1505-P006 - Existing & Proposed East Elevation - Scale 1:100@A3 1505-P007 - Existing & Proposed West Elevation - Scale 1:100@A3 1505-P008 - Existing & Proposed South Elevation - Scale 1:100@A3 1505-P009 - Existing & Proposed North Elevation - Scale 1:100@A3 1505-P010 - Existing & Proposed Cross Section A-A - Scale 1:100@A3 1505-P011 - Existing & Proposed Long Section B-B - Scale 1:100@A3 1505-P012 - Construction Management Strategy - Scale 1:500@A3 1505-P013 - Outdoor Play Area Calculations - Scale 1:200@A3 1505-P014 - Illustrative View From Fortess Road Looking South - NTS 1505-P015 - Illustrative View From Fortess Road Looking Northeast - NTS 1505-P016 - Illustrative View From Ballcourt Looking North - NTS Eleanor Palmer Science & Technology Lab / Design & Access Statement

9.0 Design Description

The proposal is for a high quality and environmentally friendly stand-alone classroom building in the location of the existing canopy structure.

The single storey building will be a flexible space containing lab stations, science equipment, display areas and storage for science and technology. The building is conceived as a large display cabinet and “tool box” for the sciences.

Planning Policy

The following local planning guidance has been referred to in developing the concept design proposal:

- Camden Local Development Framework (Core Strategy and Development Policy documents) Supplementary Planning Documents relevant to the proposals: - Camden Planning Guidance 1 - Design (2013), - Camden Planning Guidance 3 - Sustainability (2013) Model view looking east to west - Camden Planning Guidance 6 - Amenity

Summertime Ventilation Site Location & Footprint

High level free opening area: 4 m2 The proposal involves the demolition of the existing canopy structure to be replaced by the new building on the same location. The width of the building is slightly larger then the footprint of the canopy structure. The additional width is necessary to maximise the Openable windows for occupant psychological comfort and to increase internal classroom area for suitable and flexible teaching activities. ventilation when necessary The total footprint of the proposal is 82m2, equal to the additional playground space,

Low level free already in use, gained by converting the existing carpark. See Section 7.0 for calculations opening area: 3.5 m2 and further details. Option 1 MVHR for heating & ventilation Part L compliant The Plan & Access

High level extract vents No.2 x 0.13m2 free area The proposal has a simple rectangular plan with the main entrance located on the south 300mm diameter supply duct end. The building will be accessed through the main school entrance via the existing playground and ball court. Disabled access will be through the infants playground from the north and through a new opening in the existing retaining wall in front of the building. + A secondary entrance is planned to the north of the lab for access to the science garden. Low level supply vents External supply louvre Wall or ceiling mounted and 2 No.6 x 0.17m free area No.1 0.256m2 free area concealed MVHR unit 300mm diameter extract duct External extract louvre FlaktWoods Eco Premium unit No.1 0.256m2 free area 1900mm x 1520mm x 425mm Alternative duct/void locations - located on different Proposed heating and ventilation strategy. facades or 1m apart. Air intake at low level and extract at high level via concealed louvres within the rainscreen

+ Electric water heater for sinks 30 litres, 788mm(H) x 370mm(W) x 352mm(D) Eleanor Palmer Science & Technology Lab / Design & Access Statement

9.0 Design Description (con’t)

Daylight and Environmental Design

The environmental design strategy is integral to the design of the science lab proposal. A day lighting strategy based on bringing in good levels of indirect northern light from high level into the space was an important development of the design brief and was developed with environmental design consultants Ritchie + Daffin. This presents the best day lighting conditions for teaching spaces and school laboratories. Minimal west facing glazing and (internal and external) solar shading on the east and south facades mitigate glare and over heating.

Noise

Background noise levels from Fortess Road have an impact of the treatment of openable glazing and ventilation areas in the design. North facing roof windows are proposed to be fixed and natural ventilation is proposed via low level (intake) and high level (extract) integrated into the east facade facing the school. Openable windows at lab counter Model view looking west to east height are proposed as part of the east facade glazing to provide purge ventilation in the summer.

Outline of buildings on west side of fortess road Relationship to the Boundary Wall

4

2

3 The west elevation of the proposed science lab forms a sensitive and carefully considered

1 2 +03.81 TOP RIDGE relationship with the Victorian brick boundary wall along Fortess Road. The design

TOP WALL +02.68 approach considers the wall as an important west elevation integral to the small building;

+01.79 TOP WALL one that respects the existing qualities and proportions of the original wall construction, while subtly integrating the proposed roof form and the ‘display’ window within the wall.

FORTESS ROAD FFL. -01.34 The west elevation of the building itself is set behind the existing boundary wall. It has FFL. -01.34 a visible elevation 0.5m higher then the top of the boundary wall and is 0.5m set back EXISTING WEST ELEVATIONExisting Fortess Road Elevation from the street face of the wall. The wall cladding of this visible area and the rest of the

Outline of buildings on west side of fortess road building is proposed as timber. The result is felt to be subordinate and respectful to the 4

7 7 6 character, proportions and materiality of the historic wall. 9

+04.82 TOP PARAPET 3

9 5 The display window is designed as an opening within the boundary wall set out centrally +03.52 TOP PARAPET +03.17 TOP FENCE

8 between two piers. The window provides a subtle and elegant connection between the +02.40 TOP CANOPY +01.79 TOP WALL science lab, Fortess Road and the surrounding community for which the lab will cater. The

+0.75 U/S Window window heightens the relationship of classroom and the school with local area. The single fixed pane of glass is framed by a dark aluminium clad frame and designed to Secure by

FORTESS ROAD FFL. -01.34 Design standards. An internal shutter will allow the window to be closed when desirable.

PROPOSED WEST ELEVATIONProposed Fortess Road Elevation

Key

EXISTING: EXISTING: 0 1.0 3.0M 1 - Existing canopy structure 1 - Existing canopy structure EXISTING AND PROPOSED WEST 2 - Existing fence ELEVATION 3 - Existing brick boundary wall DWG NO.: P007 4 - School buildings in background REV: SCALE: 1:100 @ A3 STATUS: PLANNING DATE: 18.04.16 PROPOSED: BY: NS

DO NOT SCALE OFF DRAWINGS / USE FIGURED DIMENSIONS ONLY 5 - New wire mesh fence to replace existing CHECK DIMENSIONS ON SITE / NOTIFY ARCHITECT OF DISCREPANCIES REFER TO STRUCTURAL ENGINEER DRAWINGS FOR STRUCTURAL 6 - Display window - laminated toughened glass with pre-weathered zinc flashing DESIGN 7 - Roof window COPYRIGHT: AY ARCHITECTS 8 - Timber clad entrance canopy 1505 - ELEANOR PALMER SCIENCE LAB

C C PROPOSED MATERIALS: AY Architects Studio 23, 25-27 Bickerton Road, London N19 5JT, UK [t] ++44(0)20 7272 8899 [e] info@ayarchitects .com 9 - Timber rainscreen Eleanor Palmer Science & Technology Lab / Design & Access Statement

9.0 Design Description (con’t)

Massing and Roof Form

The massing of the building is a rectangular volume with the main roof line on the north, south, west and part of the east elevation established at 3.5m above playground level and 0.5m above the top of the existing boundary wall.

Integrated within the roof volume are two triangular volumes that extend 1.5m higher then the main roof level and form part of the east elevation facing the school where the two triangular volumes meet to create the elevation facing the school.

The two raised triangular areas are key to the design of the science lab to:

• create ideal natural day lighting conditions for teaching fundamental to the environmental design strategy of the building - see description above. • provide high level air extraction zone integrated into the east elevation as part of the environmental design strategy for heating and ventilation. • create a location for a modestly higher space within the classroom for hanging objects/devices that support science and technology experiments and the teaching curriculum.

Along the west elevation the building line is set back from the existing boundary wall along Fortess Road as single storey volume with a height 0.5m higher then the top of the boundary wall. The two 1.5m high triangular sitting above the single storey roof line Model view looking south to north Model view looking northeast to southeast narrow towards the boundary, meeting 0.5m back from the building face. The design and geometry of the two tapering flat roof volumes have a relationship to the street that break up the upper roof line as experienced along Fortess Road, reducing the massing and visible impact of the building.

A screw piled foundation is proposed for the substructure of the building, to avoid any impact on the structure of the existing boundary wall and its underpinning recently installed.

The superstructure of the building is proposed as a simple timber frame made up of standard sized softwood members. The structure is internally visible giving the lab workshop feel on the inside. The exterior is made up of horizontal timber cladding and aluminium framed glazing that will sit elegantly behind the Victorian brick boundary wall and enhance the playground area as seen from the school. Eleanor Palmer Science & Technology Lab / Design & Access Statement

10.0 Proposed Materials

External Rain Screen

The external cladding of the science lab is proposed as a horizontal timber rainscreen made from FSC Certified Siberian Larch. The character of cladding is to have pronounced gaps that pick up on the horizontal banding found in the brick boundary wall. The cladding will sit in front of concealed louvres for air extraction located at high level in the east elevation.

The timber will weather over time to a become brown/grey in colour. The cladding material and format will sit comfortably within its context and behind the brick boundary wall along Fortess Road.

Anodised Aluminium Windows & Doors

The external windows, roof windows and doors are proposed as an anodised aluminium framed system in a brushed bronze finish. The robust and well insulated glazing system will sit comfortably amongst the Victorian brick wall and the timber rainscreen cladding as it PREGROWNPREGROWN SEDUM ROOFSEDUM ROOF weathers over time. All Organic Roofs specsAll Organic are based Roofs on specs GRO areCode based guidance on GRO on Codegreen guidanceroof build on ups, green but weroof build ups, but we encourage deeper encouragesubstrate depths deeper wherever substrate possible depths towherever increase possible biodiversity to increase potential. biodiversity potential. example of weathered larch cladding proposed horizontal timber cladding - Siberian larch Aluminium Flashings Ask us about our HabitatAsk us Upgrade about our package: Habitat Upgradea range of package: specially a selected range of biodiversity specially selected biodiversity hotspots for bees, butterflieshotspots for and bees, other butterflies invertebrates and otherto improve invertebrates the biodiversity to improve the biodiversity contribution of whichevercontribution green of roof whichever you choose green roof you choose Parapet flashings are proposed to be concealed behind the timber rainscreen. Where visible, such as to the frame of the display window onto Fortess Road, these are proposed SATURATED mm SATURATED mm WEIGHT WEIGHT KG PER M2 KG PER M2 as anodised in a brushed bronze finish to match the proposed windows. Planting Planting 25 25 25 25 Substrate Substrate 63 60 63 60 Sedum Roof Filter Fleece Filter Fleece Drainage Layer/Reservoir DrainageBoard Layer/Reservoir Board Geotextile Protection LayerGeotextile Protection Layer The roof finish to all flat roof areas is proposed as pre-grown sedum on a growing Waterproof Membrane Waterproof Membrane 12 12 substrate with a reservoir board. A Sedum roof with a growing medium will help increase Plywood Deck Plywood Deck Insulation Insulation local biodiversity, retain rainwater from entering the public sewage system and are 9 9 Vapour Control Layer Vapour Control Layer attractive to look down upon from surrounding buildings / residences. Plywood Deck Plywood Deck Joists Joists

Other information Other information 120 120 Typical Flowering SeasonTypical Flowering Season May-Aug May-Aug Recommended MaintenanceRecommended Maintenance Regime Regime Bi-annual Bi-annual Biodiversity Contribution Biodiversity Contribution Fair Fair 18 18

proposed sedum roof build-up example of anodised aluminium framed windows and flashings - camden arts centre WHY WHYTRANSPARENCY TRANSPARENCYSIMPLICITY SIMPLICITYPEACE OF MIND PEACE OF MIND CHOOSE Once the project spec Once theWe projectavoid jargon spec and We avoidHabitat jargon and and roofing Habitat and roofing CHOOSEis agreed, the price youis agreed,oversee the price all communications you oversee expertise, all communications fully warrantied expertise, fully warrantied ORGANIC ORGANICsee is the price you pay.see is thewith price clients, you design pay. teamwith clients,workmanship design team and workmanship and ROOFS? ROOFS? and contractors to ensureand a contractors manufacturer-backed to ensure a manufacturer-backed smooth install smoothguarantees install on all installedguarantees on all installed components components

WWW.ORGANICROOFS.CO.UKWWW.ORGANICROOFS.CO.UK | TEL: 01273 774| TEL: 152 01273 774 152 OUR CURRENT CLIENTS INCLUDE OUR CURRENT CLIENTS INCLUDE Eleanor Palmer Science & Technology Lab / Design & Access Statement

11.0 Illustrative Views

View from Fortess Road looking north Eleanor Palmer Science & Technology Lab / Design & Access Statement

11.0 Illustrative Views (con’t)

View from Fortess Road looking southeast Eleanor Palmer Science & Technology Lab / Design & Access Statement

11.0 Illustrative Views (con’t)

View from ball court looking northwest Eleanor Palmer Science & Technology Lab / Design & Access Statement

11.0 Illustrative Views (con’t)

Internal view looking northeast 4

2

+03.81

+02.81 Eleanor Palmer Science & Technology Lab / Design & Access Statement

1

3

-00.07 ±00.00 BALL COURT

FORTESS ROAD -01.35

EXISTING CROSS SECTION AA 12.0 Consultation

+06.59

Pre planning proposed outline +04.82 London Borough of Camden Pre-planning Consultation

+03.52 The design proposal follows pre-planning advice with Camden Planning Authority, Pre- application Reference 2015/6712/PRE dated 08/02/16.

Feedback was provided by planning officer Tania Skelli-Yaoz following a meeting at the school and site visit for the Stage 2 proposal. The design proposal consisted of a single storey building along the boundary fronting Fortess Road with a sloping roof rising to a BALL COURT ±00.00 two storey building along the east elevation facing the school. The overall volume was proposed to accommodate the provision for a raised storage area within the building. FORTESS ROAD -01.35 The main advice from planning was a recommendation to reduce the overall height of the building and consider a reduction of the two-storey volume. The proposal was considered PROPOSED CROSS SECTION AA to be overly visible and appear isolated from Fortess Road. DRAFT Cross-section of proposed building showing reduction in volume following pre-planning advice from The current proposal has been developed to omit the raised storage area within the KeyCamden Planning. Section outline of pre-planning proposal dashed

building, resulting in a substantially reduced volume0 with1.0 reduced3.0M building height along EXISTING: Fortess Road and elsewhere. See comparative sectionEXISTING ANDof pre-planningPROPOSED CROSS and current 1 - Existing canopy structure SECTION AA 2 - Existing fence proposals. The two 1.5m high volume extensionsDWG are. : P00XX triangular in plan and taper towards 3 - Existing brick boundary wall REV: SCALE: 1:100 @A3 4 - School Buildings the street. The design retains the day lighting strategySTATUS: PLANNING of the scheme but substantially DATE: 31.03.16 reduces the visible impact of the building from theBY: NSsurrounding context. DO NOT SCALE OFF DRAWINGS / USE FIGURED DIMENSIONS ONLY CHECK DIMENSIONS ON SITE / NOTIFY ARCHITECT OF DISCREPANCIES REFER TO STRUCTURAL ENGINEER DRAWINGS FOR STRUCTURAL DESIGN The School and Local Community COPYRIGHT: AY ARCHITECTS 1505 - ELEANOR PALMER SCIENCE LAB

C AY Architects Studio 23, 25-27 Bickerton Road, London N19 5JT, UK The school has been widely engaged in the process[t] ++44(0)20 of 7272 developing 8899 [e] info@ayarchitects .com the brief and building proposal. Participation by teachers, staff, local parents, governors and pupils making up the “Lab RATs” advisory group have met regularly since the conception of the project, providing import input in developing all aspects of the design.

An exhibition was set up in the school entrance from 13th-15th April, inviting parents and local residents to drop in to view the proposal and leave any comments. Several comments and questions were received and the feedback was overwhelmingly positive.

AY Architects presented the proposal and process of design to all Year 3-6 pupils on 13th April. Children are very excited about the proposal and made several suggestions for how the building could be used.

The consultation process has had a very positive influence on the development of the current proposal.

Exhibition at the school April 2016 AY Architects Presentation to pupils April 2016 Eleanor Palmer Science & Technology Lab / Design & Access Statement

13.0 Construction Management Strategy

An initial Construction Management Strategy (as outlined on the following page) has been developed forming the basis for further coordination with the design team, the principal designer, the local authority and the appointed main contractor in order to plan, manage and monitor the health & safety of pupils and staff during all phases of the construction and to minimise impact of construction on the surrounding area.

Construction access is considered via the secondary entrance to the school grounds via Raveley Street with all construction access coming from Fortess Road. This strategy establishes a clear separation of school children and staff from the works. The main entrance to the school would operate as normal and be unaffected during the construction period.

The site area is proposed to occupy part of the infants playground at the northwest corner of the school with an undisturbed connection to the building site from the site entrance on Raveley Street for vehicle access, deliveries and removals.

A temporary hoarding is proposed on the pavement on Fortess Road for a short period of time for the works associated with the new display window. Proposed construction access via secondary entrance on Raveley Street The management strategy will be further developed to ensure an effective plan is agreed and in place prior to the start of construction.

Proposed construction access via secondary entrance on Raveley Street Eleanor Palmer Science & Technology Lab / Design & Access Statement

114 112

BUILDING SITE AREA

103 PROPOSED HOARDING LINE Lady Somerset POTENTIAL SKIP LOCATION Road Raveley St SITE ACCOMMODATION / WELFARE FACILITIES St EXISTING VEHICLE ENTRANCE FROM RAVELEY STREET USED FOR TREE PROTECTION Lupton CONSTRUCTION ACCESS

STAFF ROOM INFANTS CONSTRUCTION VEHICLE PARKING PLAYGROUND TEMPORARY ENTRANCE IN LOW WALL FOR ACCESS BETWEEN INFANTS PLAYGROUND AND BALL COURT DURING CONSTRUCTION 101

PROPOSED BUILDING FOOTPRINT

TEMPORARY HOARDING / TOWER FOR WINDOW WORKS

PROPOSED HOARDING LINE

BALL COURT

Road

Fortess

RECEPTION BUILDING

MAIN HOME ENTRANCE ZONE PLAYGROUND PLAYGROUND SCHOOL MAIN ENTRANCE FROM LUPTON STREET UNEFFECTED

2nd DRAFT St

Lupton 0 5.0 10.0 15.0M 98 PRELIMINARY SITE LAYOUT AND ACCESS STRATEGY

DWG NO. : P012 REV : A - 11 .04.16 SCALE : 1:500 @ A3 STATUS : PLANNING DATE : 31.03.16 BY : NS

DO NOT SCALE OFF DRAWINGS / USE FIGURED DIMENSIONS ONLY CHECK DIMENSIONS ON SITE / NOTIFY ARCHITECT OF DISCREPANCIES REFER TO STRUCTURAL ENGINEER DRAWINGS FOR STRUCTURAL DESIGN COPYRIGHT: AY ARCHITECTS

1505 - ELEANOR PALMER SCIENCE LAB

C AY Architects Studio 23, 25-27 Bickerton Road, London N19 5JT, UK PRELIMINARY SITE STRATEGY AND ACCESS STRATEGY 1: 500 @ A3 [t] ++44(0)20 7272 8899 [e] info@ayarchitects .com Initial Construction Management Strategy Eleanor Palmer Science & Technology Lab / Design & Access Statement

AY Architects Profile (con’t)

AY Architects, founded by Partners Anthony Boulanger and Yeoryia Manolopoulou in 2005, has become recognised for ecologically-minded and community-based projects of exceptional quality.

Completed as our first public building, Montpelier Community Nursery in Kentish Town was mid-listed for the 2013 Stirling Prize, having won 2013 RIBA Regional and National Awards and the 2013 Stephen Lawrence Prize. Speaking about the nursery the judges said:

‘The architects were key to the vision for the nursery which is why it was delivered without compromise and produces an all-encompassing educational experience…. The building is designed to maximise sunlight, with a part-glazed saw tooth roof orientated north-south…. Internally the rooms are treated as giant furniture items working against the geometry of the structure. They are cleverly designed with and easily navigable by a small child. The selection of materials was a key part of the success. The black stained Siberian larch cladding allows the nursery to sit inconspicuously in amongst the treescape and contrasts with the white-washed internal timber against which the playful objects to come to life.’

The nursery was Highly Commended in the 2014 Camden Design Awards and the practice were a Building Design Magazine ‘Small Project Architect of the Year’ Award Finalist. Montpelier Community Nursery, Kentish Town, 2012 AY Architects has since worked with on a small new library building and are currently leading £1M extension and renovation works at .

The practice works closely and positively with communities and the local authority on public and private developments within the Borough of Camden.

AY Architects is a Limited Liability Partnership and a RIBA Chartered Practice.

Montpelier Community Nursery, Kentish Town, 2012 New entrance and extensions to Camden School for Girls, Kentish Town