2019 - 2024 Transportation Improvement Program (TIP)

for the Tri-Cities Metropolitan Area & Benton-Franklin Region DRAFT Benton-Franklin Region

«¬21

«¬261

«¬17

«¬26

«¬263

¤£395

«¬241

«¬240 Benton County Franklin County

«¬225 West Richland #!"$182 «¬224 #!"$82 Legend #!"$82 #!"$182 #!"$82 #!"$82

#!"$82 Richland Pasco #!"$82 Metropolitan Planning Area Prosser #!"$82 Kennewick «¬22 (MPA)

#!"$82 Regional Transportation Planning «¬397

«¬221 Organization (RTPO) Boundary

#!"$82

#!"$82

«¬14 0 5 10 20 ¯ Miles

Benton-Franklin Council of Governments P.O. Box 217, Richland WA 99354 509.943.9185 www.bfcog.us Table of Contents

Table of Contents...... 2 Title VI Public Notice...... 3 Introduction...... 6 Benton-Franklin Council of Governments...... 6 Federal and State Requirements...... 9 Federal Legislation...... 9 Annual Federal Listing of Obligations Report...... 9 State Legislation ...... 9 Performance Measures...... 10 Metropolitan/Regional Transportation Plan Consistency...... 11 Congestion Management Process ...... 11 Air Quality...... 11 TIP Development Process...... 13 TIP and STIP Development...... 13 Project Selection of Federal Funds...... 13 Public Input Process...... 14 TIP Adoption...... 14 TIP Project Changes...... 14 Financial Plan...... 16 2019 - 2024 TIP Projects...... 19 Project Analysis...... 19 Federal Funding Codes...... 21 State Funding Codes...... 21 Project Type ...... 21

Appendix...... A2 Appendix A - Public and Agency Participation Process...... A3 Appendix B - Annual Listing of Federal Obligations...... A12 Appendix C - Secured Projects 2019-2022...... A13 Appendix D - Planned Projects 2019-2024...... A81

2 2019-2024 TIP Title VI Public Notice

Benton‐Franklin Council of Governments hereby gives public notice that it is the policy of the agency to assure full compliance with Title VI of the Civil Rights Act of 1964, the Civil Rights Restoration Act of 1987, Executive Order 12898 on Environmental Justice, and related statutes and regulations in all programs and activities. Title VI requires that no person in the United States of America shall, on the grounds of race, color, sex, or national origin, be excluded from the participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program or activity for which BFCG receives federal financial assistance. Following 29 USC 794, no otherwise qualified individual with a disability shall, solely by reason of their disability, be excluded from participation in, be denied benefits of, or be subjected to discrimination under any program or activity receiving Federal financial assistance.

Any person who believes they have been aggrieved by an unlawful discriminatory practice under Title VI has a right to file a formal complaint with BFCG. Any such complaint must be in writing and filed with the BFCG Title VI Coordinator within one hundred eighty (180) days following the date of the alleged discriminatory occurrence. Title VI Complaint Forms may be obtained from BFCG at no cost by calling (509) 943‐9185.

If information is needed in another language, please contact BFCG at (509) 943‐9185. Si se necesita información en otro idioma, por favor contacte a BFCG (509) 943‐9185

Access the complete document on the BFCG website http://www.bfcog.us/TitleVI%20Plan_July2014.pdf

3 2019-2024 TIP Pending

Benton‐Franklin Council of Governments Draft 2018-2024 Regional Transportation Improvement Program Tri‐Cities MPO and Benton‐Franklin RTPO

RESOLUTION #03-18 Adoption of the 2019‐2024 Transportation Improvement Program for the Tri‐Cities MPO and the Benton‐Franklin RTPO

Whereas, The Benton‐Franklin Council of Governments (BFCG) has been certified by the United States Department of Transportation (USDOT) and the Washington State Department of Transportation (WSDOT) and is responsible for coordinating the regional transportation planning process as set forth in Title 23 U.S.C. Section 134 and 49 U.S.C. Section 5303 of the Federal Transit Act; and

Whereas, BFCG must review, prioritize, and select Surface Transportation Block Group (STBG) projects, as a Metropolitan Planning Organization (MPO); and

Whereas, Local jurisdictions and state agencies have submitted projects for inclusion in the MPO and Regional Transportation Planning Organization (RTPO) Transportation Improvement Programs (TIPs), which are based on reasonably available financial resources at the federal, state, and local levels; and

Whereas, The RTPO TIP includes a six‐year list of regionally significant transportation projects of which the first four years are prioritized by year; and

Whereas, A public open house was held on August 29th, at the Ben Franklin Transit Administration Office, 1000 Columbia Park Trail, Richland, to receive public input on the TIP and afford a public comment period, and all comments have been addressed by either the BFCG staff or local jurisdictions; and

Whereas, The WSDOT Regional Highways and Local Programs Office and Regional Programming Office have reviewed the MPO and RTPO TIP and find the contents free of omissions; NOW THEREFORE

BE IT RESOLVED that the BFCG Board adopts the 2019‐2024 TIP for the Tri‐Cities MPO and the 2019‐ 2024 TIP for the Benton‐Franklin RTPO; and

BE IT FURTHER RESOLVED that the MPO and RTPO Transportation Improvement Programs be submitted to the appropriate state and federal agencies for review and approval.

PASSED AND APPROVED this 30th day of October, 2018.

Attest: Brian Malley, Executive Director Skip Novakovich , BFCG President

4 2019-2024 TIP 5 2019-2024 TIP Introduction

The 2019 Transportation Improvement Program BFCG, and the metropolitan transit agency, Ben (TIP) is a list of proposed upcoming transportation Franklin Transit (BFT), defines the responsibilities for projects within the Tri-Cities Metropolitan Planning cooperatively carrying out transportation planning Organization (MPO) and the Benton-Franklin and programming in the metropolitan area. Regional Transportation Planning Organization (RTPO). Transportation projects included in the TIP BFCG Membership and Structure are either proposed for Federal funding according to The BFCG is comprised of sixteen member 23 U.S.C. (Federal Highway Administration) and 49 jurisdictions, which represent the region’s population U.S.C. (Federal Transit Administration), or are projects of 255,075. that have regional significance. MPO/RTPO Membership RTPO Membership The purpose of the TIP is to document proposed • Ben Franklin Transit • City of Mesa projects for a four-year and six-year fiscal period, so • City of Benton City • City of Connell that project funding can be secured. In order to be • City of Kennewick • City of Kahlotus considered for federal or state funding, local projects • City of Richland • City of Prosser • City of Pasco must be in the TIP. The TIP is developed to meet • City of West Richland federal regulations (23 CFR 450.326) by the Benton- • Franklin County Franklin Council of Governments. • Benton County • Port of Pasco Benton-Franklin Council of • Port of Benton • Port of Kennewick Governments • WSDOT- South Central

The Benton-Franklin Council of Governments (BFCG) provides economic development, transportation planning, and metropolitan planning for Benton The organization is structured under state law as a and Franklin Counties in Washington State. regional planning commission (RCW136.70.060), BFCG is a federally designated Metropolitan a council of governments (RCW 36.64.080), and Planning Organization (MPO), and a Transportation a Regional Transportation Planning Organization Management Area (TMA) for the Tri-Cities (RTPO) (RCW 47.80.020). metropolitan area. The BFCG is also the Economic Development District (EDD) for Benton and Franklin Planning responsibilities of BFCG are further defined Counties. in the Unified Planning Work Program (UPWP), the MPO certification documentation, and the BFCG The Metropolitan Planning Area (MPA) includes the Public Participation Plan; Public and Agency urban area and a projected 20 year urbanized area. A Participation Procedures for Transportation Planning. Memorandum of Agreement between the Washington More information can be found on the BFCG website State Department of Transportation (WSDOT), at www. http://bfcog.us/

6 2019-2024 TIP BFCG fulfills its MPO responsibilities through Tri‐ BFCG as an MPO MATS (Tri‐Cities Metropolitan Area Transportation MPOs are federally designated and federally funded Study), consisting of a Technical Advisory Committee planning organizations for metropolitan areas over (TAC), a Policy Advisory Committee (PAC), and the 50,000 people. BFCG is the designated MPO for BFCG Board. the Tri-Cities region. MPOs were introduced by the Federal-Aid Highway Act of 1962. Figure 2 on page The TAC provides planning and engineering 8 shows the BFCG MPA. perspective on behalf of member jurisdictions. Committee members actively participate in BFCG as an RTPO collaborative discussions, and provide input on RTPOs were created in 1990 as part of Washington projects, plans and policies that effect the metropolitan State’s Growth Management Act (GMA). RTPOs, and regional transportation system. Input and much like MPOs on a broader scale, serve as a recommendations from the TAC are sent forward mechanism for local governments and the state to to the PAC. The PAC provides a forum for focused coordinate planning for regional transportation discussion of transportation policy issues prior to facilities and services. There are 16 RTPOs covering 38 making recommendation to the BFCG Board. of the 39 counties in Washington. Figure 1 shows the BFCG planning area in Washington State.

Figure 1: BFCG Boundary in Washington State

BFCG

7 2019-2024 TIP Figure 2: BFCG MPA Boundary s e g d i r B

n i y w Battelle a T W

n o t Franklin 240 g n UV i h

Ya s C y a Count kim o s l a W u

R n m iv e b

e v e r g i

r a z e t t

o R

n e

S i v h e

e t G r r L

R o

d N

e

d a l ¤£395 Clark G 225 Ruppert McMurray UV Collins tain r Red Moun Van Giesen h t e 8 v

i Foster Wells 5 R 8

Paradise Williams Burns 6

224 d t

e 240 UV a t n h

t g UV o t o n i h

n

s s e 8 Sandifur R m a g 3 d w n i l d r n d R u s e R Lee a

s s S B W l

g u

J a t o

h o n n Burden l i h g m a 0 i a b e

0 6 K

s i H l

m o 1 3

l 182 D

y o sc e § d ¨¦ nne d d a Ke B P a a W ntain o o Candy Mou R R rtail Argent Dupo

82 4

¨¦§ 4 C Wernett Ke olu d m a e b h t ne ia P o 4

a rk Court R 182 T h § rai t ¨¦ l 0 2 s a l l Badger Mountain Co a lu mb Lew D ia is d Riv v e 'A' St Gage l r 12 B 240 £

¤

r UV

e C

n a t nal alla ton n Walla W

n s o Be e e i i

d r C s l

E e e a v i L Clearwater i County County b 124 Kennewick Ave R UV m e u g

l 4th k d l g

o a e o

i n l C f l

r S e

Reata a

K 10th G a i p n Burbank o m i y n l y U l r O e r E g te 27th d l 397 a fe UV B d o

l k C 82 ¤£395 a ¨¦§ O 45th Bowles

UV397 MPA/UZA/City Limits Pasco Kennewick Richland Benton City West Richland Metropolitan Planning Area 0 2.5 5 10 FHWA Urbanized Area Miles October 2016 Federal and State Requirements

Federal Legislation Annual Federal Listing of Obligations Report The federal requirements for the TIP development process are established in federal surface According to 23 CFR 450.334, BFCG is required to transportation legislation, Fixing America’s Surface annually publish a list of projects for which federal Transportation (FAST) Act. Signed into law on funds have been obligated1. BFCG prepares ts Annual December 4, 2015, the FAST Act continues many of Listing of Federal Obligations, which is published on the parameters for TIP development from previous the BFCG website2. The Annual Obligation Reports for legislation, the most recent being the Moving Ahead BFCG’s Regional TIP lists the projects for which Fed- for Progress in the 21st Century (MAP-21) Act from eral transportation funds have been obligated in the 2012. The FAST Act mandates MPO’s to approach Benton‐Franklin region during the calendar year. The planning and programming with a performance-based report is published within 90 calendar days following approach. the end of the program year. Federal Legislation requires that the TIP: State Legislation • Include any projects with federal funding under 23 U.S.C. (Federal Highway Washington State has further requirements for the TIP. Administration) and 49 U.S.C. Chapter 53 The TIP shall be updated at least every two years and (Federal Transit Administration) and projects include a program of project that covers a period of at that are regionally significant; least six (6) years (RCW 47.80.023(5)). Additionally, • Ensure consistency between projects in the TIP The TIP shall be developed in cooperation with the and the projects in the M/RTP; department of transportation, public transportation • Include a demonstration that the projects providers and local governments within the region, included in the TIP can be implemented with and include programs, projects, and transportation reasonably available resources; demand management measures of regional • Certify that the National Highway System significance as identified by transit agencies, cities, and (NHS) facilities are in adequate condition; counties. • Provide reasonable opportunity for public comments, including a formal public meeting; During TIP development, the BFCG consults with • Be developed at least every four years by the local and state officials, regional and local transit MPO in cooperation with the State and any operators (both public and private carriers), recipients affected public transportation operators. of FTA funding assistance, and other agencieswhich may affect transportation activities. Figure 1-6 shows the flow of input into the TIP. 1 Obligated is defined as: Federal funds made available from the noted fund program and phase, on the approved date. 2http://bfcog.us/transportation/documents/metropolitanregional-transportation-improvement-program/

9 2019-2024 TIP Performance Measures and non-motorized serious injuries. These targets are required for all public roads regardless of ownership or In 2012, the adoption of Moving Ahead for Progress functional class. in the 21st Century Act (MAP-21) created new requirements on performance management. 23 USC The Benton-Franklin Council of Governments has 150 states that performance management provides agreed to plan and program projects so that they a means to the most efficient investment of federal support the Washington State Department of transportation funds by: (1) focusing on national Transportation (WSDOT) safety targets as transportation goals, and (2) improving project reported to the Federal Highway Administration as decision making through performance-based planning part of WSDOT’s Highway Safety Improvement and programming. Program annual submittal.

MAP-21 requires reporting performance on the PM 3 following areas: Safety; Pavement and Bridge; System System Performance, Freight and Congestion Performance/ Congestion; Freight, and Congestion Mitigation and Air Quality (CMAQ) (known as PM3) Mitigation and Air quality. encompass the following four national goals: • Congestion reduction: To achieve a significant WSDOT has finalized MAP-21 performance targets reduction in congestion on the National for Safety, and System Performance, Freight and Highway System; Congestion Mitigation and Air Quality measures • System reliability – To improve the efficiency of (commonly referred to as PM3). The remaining the surface transportation system; performance targets are under development. • Freight movement and economic vitality – To improve the national freight network, Safety strengthen the ability of rural communities to The stated goal for safety is: to achieve a significant access national and international trade markets, reduction in traffic fatalities and serious injuries on all and support regional economic development; public roads. and • Environmental sustainability – To enhance Pursuant to these national goals, State Departments the performance of the transportation system of Transportation (DOTs) are required by the federal while protecting and enhancing the natural Highway Safety Improvement Program regulations environment. under 23 CFR 924 to set five performance targets. These five required performance targets use five year A number of tools and resources were used to analyze rolling averages for (1) number of fatalities, (2) rate of required data for target setting. The final rule will use fatalities per 100 million VMT, (3) number of serious data on the percent of miles traveled that are reliable injuries, (4) rate of serious injuries per 100 million on the Interstate and Non-Interstate Systems, and the VMT, and (5) number of non-motorized fatalities Travel Time Reliability Index, as well as several relating

10 2019-2024 TIP to CMAQ. Only areas designated as a non-attainment to the regions goals as established by Transition2040. or maintenance area fall under the performance Applications by the jurisdictions for use of STBG and measure requirements for CMAQ, which BFCG does TA funds require information about the alignment of not. the project to the current M-RTP goals and objectives.

BFCG anticipates the adoption of WSDOT targets for Congestion Management Process PM3 in November 2018. The Congestion Management Process (CMP) is a Metropolitan/Regional Transportation federal transportation planning requirement. The Plan Consistency purpose of the CMP is to identify congested areas, develop strategies, and track the progress of congestion Per Federal Regulations (23 CFR 450.326), each mitigation. To fulfill this requirement, the BFCG project in the TIP is consistent with the approved adopted the initial CMP, the Tri-City Metropolitan Area Metropolitan Transportation Plan. The current Congestion Management Process, in December 2013. Metropolitan/Regional Transportation Plan, Transition2040 (Adopted in May 2017), outlines Four measurement programs were established in the 5 goals for the region, each with accompanying CMP to evaluate the location and level of congestion. objectives: These are programs designed to measure and evaluate • Safety & Security travel time, traffic volumes, transit system data and • Preservation collision data. The CMP supports the goals and • Mobility & Accessibility objectives in the Transition2040. • Freight Movement & Economic Development • Community & Environmental Sustainability. Air Quality

These goals align with the national goals established Nonattainment and maintenance areas face additional by MAP-21 and the FAST Act (23 USC 150): Safety, requirements in federal legislation. A nonattainment Infrastructure Condition, Congestion Reduction, area is an area that does not meet the National System Reliability, Freight Movement & Economic Ambient Air Quality Standards (NAAQS) set by the Vitality, Environmental Sustainability, and Reduced EPA. NAAQS establishes measures for six pollutants: Project Delivery Delays. Additionally, they align carbon monoxide, ozone, particulate matter, lead, with the Washington State Transportation Goals and sulfur dioxide, and nitrous oxide. Policies. Projects included the TIP are drawn directly from the strategies in Transition2040. BFCG is not a non-attainment or maintenance area at this time, and is labeled as “Attainment/ The purpose of the TIP is to demonstrate that Unclassifiable.” Data indicates the Tri-City ozone available resources are being used to implement the levels exceed federal ambient air quality standards. region’s long-range transportation plan, consistent BFCG is coordinating with Benton Clean Air, Washington State Department

11 2019-2024 TIP of Ecology, the Federal Highway Administration, and In 2016, permanent air quality moniters were placed Ben Franklin Transit on outreach and education of a when the Washington State Department of Ecology non-attainment status, and to support a community commissioned The Tri-Cities Ozone Precursor Study1 strategy for moving forward. (T-COPS) final report (published in 2017).

In 2013 air quality specialists began monitering ozone Further information is pending. after Washington State University’s air quality forecast model indicated consistently elevated ozone levels.

1https://ecology.wa.gov/Research-Data/Scientific-reports/Air-quality-studies

12 2019-2024 TIP TIP Development Process

TIP and STIP Development Project Selection of Federal Funds

Jurisdictions submit all required projects to BFCG BFCG, as the MPO and county lead agency, is (regionally significant and/or federally funded). From responsible for selecting projects for the federal there, BFCG compiles the regional projects and creates Surface Transportation Block Grant (STBG, formally the TIP. Once BFCG’s TIP is adopted, BFCG submits STP) and the STBG Set-Aside for transportation the regional TIP to Washington State for the State alternatives (TA, formally TAP) in alignment with TIP (STIP). WSDOT is responsible for the statewide BFCG’s identified regional priorities. coordination of their STIPs. Following federal approval of the STIPs, local jurisdictions may begin obligating Projects are selected by BFCG transportation federal funds TIPfor theirDevelopment projects. Process committees with final approval by the BFCG Board. A competitive process is designed to ensure that project selections are consistent with the Metropolitan/ Figure 3: Development of the TIP Regional Transportation Plan (M-RTP) Goals and Objectives.

Washington STIP Projects are selected for funding at a joint meeting of the Policy Advisory Committee (PAC) and the Technical Advisory Committee (TAC) in which members are considered the “Scoring Committee” and score projects with provided evaluation criteria. The BFCG Regional TIP meeting is open to the public and project applications are available for comment on the BFCG website 30 days prior to the meeting.

Each jurisdiction with a request for funding presents a brief description of their project(s) to the Scoring Committee and others in attendance. Using evaluation BFCG criteria consistent with the M-RTP, the Scoring Committee scores each application, and BFCG staff tallies up the scores to create the ranked list.

Scoring and ranking is discussed and a draft prioritization, voted upon by both the PAC/TAC is Jurisdictions Public WSDOT forwarded to the BFCG Board. The draft project / Agencies Transit prioritization is posted to the website for public comment prior to the BFCG Board meeting.

13 2019-2024 TIP Public Input Process TIP Project Changes

Opportunity for public input begins at the local agency As a project gets underway a change to the TIP may level via the council/board meeting process. Once be necessary because of cost adjustments, scope publically vetted, the local agencies submit their TIP changes, new secured funds, etc. A change to the TIP projects to the BFCG. When the BFCG compiles the can be either an amendment or an administrative projects to create the TIP, the public has an additional modification. and must follow the following rules. opportunity to provide input. Amendments BFCG hosts a public meeting to seek comments prior Amendments can be made throughout the calendar to formal adoption of the Regional TIP. The meeting year by submitting a written request to BFCG staff. for the 2019 TIP was held on August 29th, from 5pm Amendments to the TIP may include adding a new to 7pm at Ben Franklin Transit’s Administration Office. project, deleting a project, adding a new phase, The open house was advertised in two consecutive increasing federal funds, changing funding from non‐ weeks prior to the event, in two newspapers: the Tri- federal to federal, or major scope change. Once BFCG City Herald, and tu Decides (in Spanish). The open staff receives a written request, the amendment will be house was combined with topics by Ben Franklin reviewed for consistency with the M/RTP and State Transit, Benton Clean Air, and the Washington State and Federal regulations. Transportation Commission. Representatives from jurisdictions were present to talk with and answer any BFCG staff ensures the amendment is placed on the questions from the public. Technical and Policy Advisory Committee (TAC/ PAC) agendas. These committees meet monthly and TIP Adoption forward their recommendations to the BFCG Board for local approval. The Board action is then sent to After the public meeting, the TIP is recommended for the appropriate state and federal agencies for review approval at the TAC and PAC Committee meetings, and approval. Amendments take approximately 45 to and then approved at the Board. All three meetings are 60 days. Amendments are posted to the website for open to the public. a 30 day comment period as they move through the committees. Once approved by BFCG, WSDOT, FTA The public process for TIP development is consistent and FHWA the date approved is posted. with the current BFCG Public Participation Plan: Public & Agency Participation Procedures for Administrative Modifications Transportation Planning1. The BFCG 2019–2024 Administrative Modifications can include: revisions to MPO/ RTPO TIP has an approved TIP development lead agency, changes to a project’s total programmed schedule (Figure A-1 on page 14). amount less than 30%, minor changes in scope, 1 http://bfcog.us/wp-content/uploads/2015/08/2015-BFCG-Public-Participation-Plan.pdf

14 2019-2024 TIP minor changes or errors in project information in a project’s funding authorization for award of (environmental type, right-of-way required, contract. Administrative Modifications are considered improvement type, etc.), changes in a project’s corrections and do not require the process for a formal federal fund source, authorization for any federal amendment. funds currently programmed in the TIP without consideration of the phase split, and adjustments

15 2019-2024 TIP Financial Plan

An essential part of TIP development is fiscal 3. Ben Franklin Transit 2017 Transit Development constraint. This financial plan demonstrates that the Plan BFCG has reasonably available revenue for the TIP 4. WSDOT South Central Region. program of projects. The 2019 M/R TIP is based on documented allocations of Federal, State, Local and Figure 4 shows the Estimated Maintenance and private funds being used to finance projects. A selected Operation cost for 2019-2022. project must have documented funding that is secured/ committed, available or reasonably available to be Future Revenue included in the TIP. The TIP is consistent with BFCG’s For the current M-RTP, Transition2040, BFCG worked current M-RTP, Transition2040. in coordination with WSDOT and BFT to develop the financial forecasts for local, state and federal revenue Maintenance and Operation sources. For the long range forecasts, BFCG used Maintenance and Operation are costs needed by the projections based on ten years of historic data (2005- local jurisdictions to adequately maintain, preserve, 2014) provided by WSDOT’s County Road and City and operate the existing transportation system. The Street Revenue and Expenditure Report. The urban Maintenance and Operation cost for this financial plan revenues annualized growth rate over the period 2005- is derived from several sources for the development of 2014 was 0.97%, while the rural was 0.53%. Using the M-RTP: the historic revenues from 2005-2014, revenues were 1. BFCG’s M-RTP: Transition2040 calculated for 2017-2040 in three band years. 2. WSDOT Economic Analysis Unit

Figure 4: Estimated Maintenance and Operating (M&O) Cost

Estimated Maintenance and Operating (M&O) Cost

2019 2020 2021 2022 Urban - MPO $19,734,130 $20,840,341 $22,008,560 $24,264,437 Rural - RTPO $12,282,953 $12,514,028 $12,749,450 $12,989,301 Ben Franklin Transit $41,398,386 $43,281,826 $44,637,484 $46,668,288 WSDOT - South Central Region $3,100,000 $3,100,000 $3,100,000 $3,100,000 Sources: Benton-Franklin Council of Governments - Transition2040 Sources: WSDOT Economic Analyis Unit Benton-Franklin Council of Governments - Transition2040 Ben Franklin Transit - 2017 Transit Development Plan WSDOT Economic Analyis Unit WSDOT - South Central Region Ben Franklin Transit - 2017 Transit Development Plan WSDOT - South Central Region

16 2019-2024 TIP Urban Forecasted Revenues and Expenditures Figure 6: Urban Forecasted Revenues and Expenditures, 2017-2025 2017-2025 Forecasted Revenues $ 453,986,148 Forecasted Expenditures $ 453,986,148 Forecasted Preservation, Maintenance & Operations $ 114,981,072 Forecasted All Other Expenditures $ 139,668,838 Reasonably Available Project Funds $ 199,336,238

Rural Forecasted Revenues and Expenditures Figure 7: Rural Forecasted Revenues and Expenditures, 2017-2025 2017-2025 Forecasted Revenues $ 251,448,904 Forecasted Expenditures $ 251,448,904 Forecasted Preservation, Maintenance & Operations $ 108,035,022 Forecasted All Other Expenditures $ 67,913,835 Reasonably Available Project Funds $ 75,500,048

WSDOT Financials, 2017-2040 Figure 8: WSDOT Forecasted Revenues and Expenditures, 2017-2025 2017-2025 Forecasted Revenues $ 147,300,000 Forecasted Expenditures Forecasted M&O Expenditures $ 27,900,000 Connecting Washington Account $ 119,400,000 Ben Franklin Transit Forecasted Revenues$ and147,300,000 Expenditures Figure 5: BFT Forecasted Revenues and Expenditures, 2017-2025 2017-2025 Reasonably Available Revenues Total Operating $ 406,431,471 Total Capital $ 34,973,098 $ 441,404,569 Forecasted Expenditures Total Operating Expense $ 406,431,471 Total Capital Expense $ 34,973,098 $ 441,404,569

17 2019-2024 TIP Projected road and street maintenance costs for each is an increasing backlog of maintenance and capital jurisdiction in the MPO and RTPO are summarized improvement needs. above. Maintenance funding comes from state gas tax distribution and locally generated revenues from Small jurisdictions in the RTPO with inadequate property taxes, sales tax, utility tax, and B&O tax. The locally generated tax bases are experiencing difficul- gasoline tax revenues have not kept pace with inflation ties in maintaining their infrastructure. Many streets or the population growth and demand for services. are deteriorating beyond the point where they can be Consequently, jurisdictions must rely more heavily on resurfaced and, therefore, reconstruction is needed. locally generated tax revenues to adequately maintain Where streets have been reconstructed through federal their systems. As construction and maintenance costs and/or state funding programs, the communities may continue to rise, there is an ever-widening gap between not have necessary funds to adequately maintain and available revenues and service demands. The net result protect that structural integrity.

18 2019-2024 TIP 2019 - 2024 TIP Projects

Project Analysis Funding Sources This section details the 2019-2024 projects included in Figure 10 on page 20 shows the fund source the TIP (either regionally significant and/or federally and fund program, meaning where the funds funded). originate from, and to where they are being spent (programmed). There are 66 secured projects programmed in the TIP for the years 2019-2024. The TIP projects are summarized in the following table. For a detailed look at the TIP projects, see Projects by Type “Appendix C - Secured Projects 2019-2022”.

Projects submitted to the TIP must classify the Improvement Type. Figure 9 shows all secured projects in the 2019-2024 TIP, summarized by their Improvement Type.

Figure 9: 2019 TIP Projects by Project Type

Number of Programmed Percent of Project Type Projects Amount Program ($) Transit 4 $89,885,020 26.5% Reconstruction - Added Capacity 6 $72,307,175 21.3% Special Bridge 5 $63,035,202 18.6% Safety 19 $42,386,884 12.5% Maintenance Resurfacing 3 $23,433,938 6.9% Bridge Rehab - No Added Capacity 4 $21,116,062 6.2% Reconstruction - No Added Capacity 9 $17,142,978 5.0% Environmental Only 2 $3,291,930 1.0% New Construction Roadway 3 $3,076,797 0.9% Maintenance Restoration and Rehab 4 $2,130,253 0.6% Facilities for Peds and Bikes 3 $555,614 0.2% Bridge Rehabilitation, Added Capacity 1 $477,226 0.1% Rail/Highway Crossing 2 $445,555 0.1% Planning 1 $189,306 0.1% Total 66 $339,473,940 100% *Only projects with secured funding are included.

19 2019-2024 TIP Figure 10: 2019 TIP Projects - Fund Sources and Programs 2019 TIP Projects - Fund Source and Program $90,000,000

$80,000,000

$70,000,000

$60,000,000

$50,000,000

$40,000,000

$30,000,000

$20,000,000

$10,000,000

$- WSDOT Transit Local Federal $78,526,881 $27,797,397 $11,090,805 State $73,701,516 $12,289,994 $13,759,309 Local $$ $26,032,611 $35,124,916 $17,332,763

20 2019-2024 TIP Federal Funding Codes UAP Urban Arterial Program UCP Urban Corridor Program BIA Bureau of Indian Affairs SP Sidewalk Program CMAQ Congestion Mitigation Air Quality SCAP Small City Arterial Program CDBG Community Development Block Grant SCPP Small City Preservation Program DOD Department of Defense FLAP Federal Lands Access Program County Road And Administration Board (Crab): HSIP Highway Safety Improvement Program CAPP County Arterial Preservation Program NHPP National Highway Performance RAP Rural Arterial Program Program NHFP The National Highway Freight Program Other State Funding Codes: FMSIB Freight Mobility Strategic Investment Federal Transit Administration (FTA): Board FTA Section 5307 Urban Areas WSDOT WSDOT funding FTA Section 5309 New Starts CWA Connecting Washington Account (2015 FTA Section 5310 Elderly/Disabled Persons Legislation) FTA Section 5311 Rural Areas OTHER All other unidentified state fund codes

Surface Transportation Block Group (STBG) Project Type Formally Surface Transportation Program - STP 01 New Construction Roadway TA (UL) Transportation Alternatives-Urban 03 Reconstruction – Added Capacity Large 04 Reconstruction – No Added Capacity TA (US) Transportation Alternatives Urban 05 4RMaintenance Resurfacing Small 06 4R Maintenance- Restoration & Rehabilitation TA (R) Transportation Alternatives Rural 13 Bridge Rehabilitation, Added Capacity TA (SR) Safe Routes to Schools 14 Bridge Rehabilitation, No Added Capacity STBG (L) Legislative 18 Planning STBG (R) Regionally Selected Rural 20 Environmental Only STBG (US) Regionally Selected Urban Small 21 Safety STBG (UL) Regionally Selected Urban Large 22 Rail/Highway Crossing STBG STP – WSDOT Use Only 23 Transit STP (BR) STP Bridge 28 Facilities for Pedestrians & Bicycles 40 Special Bridge Washington State Funding Codes 44 Other

Transportation Improvement Board (TIB):

21 2019-2024 TIP Figure 11: 2019 TIP - All Secured Projects

Amount Project Title Jurisdiction Type STIP ID Total Cost Programmed Phase Start Year

2019 - 2022 Equipment Ben Franklin Transit 23 WA-06637 $7,425,551 $6,300,551 ALL 2019

2019 - 2022 Operating, Preventative Maintenance Ben Franklin Transit 23 WA-04000 $60,127,348 $49,855,194 ALL 2019

2019 - 2022 Transit Vehicle Replacements Ben Franklin Transit 23 WA-05091 $25,039,560 $16,929,275 ALL 2019

2019 - 2022 Facilities Ben Franklin Transit 23 WA-05096 $17,275,000 $16,800,000 ALL 2019 9th Street Sidewalks Benton City 21 BC-000013 $121,148 $121,148 PE/CN 2019 NINE CANYON RD Ph. III: Coffin to Beck Benton Co 4 BCO2012-09 $3,356,000 $10,000 CN 2019 Badger Road Pathway Benton County 28 WA-10232 $420,000 $420,000 CN 2022

Badger Mountain - Candy Mountain Connector Trail Benton County 28 WA-09854 $107,614 $95,614 CN 2019 EMERGENT PROJECTS Benton County 4 BCO2012-27 $1,500,000 $1,400,000 ALL 2019 2019-2021 Unified Planning Work Program BFCG 18 WA-10725 $189,306 $189,306 PE 2019 East Birch Street Connell 3 WA-00822 $860,000 $860,000 PE/CN 2019 Connell Rail Interchange Connell 3 WA-10805 $24,100,000 $24,100,000 PE/CN 2020 Street Preservation Program Connell 5 WA-00688 $35,000 $35,000 CN 2019 Hailey Railroad/Highway Crossing Franklin County 22 WA-10962 $105,555 $90,555 CN 2019 Smith Canyon #722-0.07 Bridge Replacement Franklin County 11 WA-11517 $15,000 $13,500 CN 2019 Basin City Alternative Transportation Route Improvements II Franklin County 28 WA-07940 $375,000 $74,600 PE 2019 Safety - Rumble Bars Franklin County 21 WA-10373 $125,000 $114,000 CN 2019 Taylor Flats Bridge #903-3.46 Franklin County 11 WA-00157 $1,172,803 $1,745,578 CN 2019

Pasco-Kahlotus Road Reconstruction/ Overlay II Franklin County 4 WA-05183 $2,796,561 $2,181,618 CN 2019 Selph Landing #906-8.79 Replacement Franklin County 11 WA-09041 $363,100 $291,390 CN 2019 Coyan Bridge #200-9.93 Franklin County 11 WA-10376 $1,113,585 $952,560 CN 2019 Juniper Dunes Recreation Area Access Franklin County 1 WA-01006 $3,063,750 $2,597,083 CN 2019

Safety - Countywide Intersection Improvements Franklin County 21 WA-10372 $295,000 $270,000 CN 2019 Safety - Flexible Guidepost Franklin County 21 WA-10371 $160,000 $145,000 CN 2019

22 2019-2024 TIP Amount Project Title Jurisdiction Type STIP ID Total Cost Programmed Phase Start Year West 10th Widening Kennewick 4 kenn9 $2,615,000 $2,585,000 CN 2019

US395/Ridgeline Drive Intersection Improvements Kennewick 4 kenn6 $5,644,259 $5,644,259 RW/CN 2019 Wrigley Drive Extension Pasco 1 WA-06941 $260,000 $260,000 PE/CN 2019 Lewis Street Overpass Pasco 3 WA-01715 $35,547,906 $31,100,000 PE/CN 2019 Road 68 Interchange Improvements Pasco 4 WA-07739 $4,317,000 $4,317,000 PE/CN 2019

Traffic Signal Improvements - City Wide Phase 2 Pasco 21 WA-08734 $3,400,000 $3,300,000 RW/CN 2019 Big Pasco Intermodal Rail Reconstruction Port of Pasco 4 WA-11625 $1,435,775 $1,435,775 PE/CN 2019 Bennett Avenue Improvements Prosser 4 WA-10056 $2,901,916 $715,816 PE/RW/CN 2019 Center Parkway Extension Richland 1 R001 $3,422,834 $1,374,144 CN 2021

George Washington Way Pavement Preservation Richland 5 R037 $4,192,000 $4,092,000 CN 2019 Duportail Bridge - Phase 2 Richland 3 R036 $4,601,695 $8,358,390 CN 2019 Columbia Park Trail - East Richland 4 R010 $2,906,410 $2,906,410 PE/CN 2019 BOMBING RANGE RD BRIDGE REHABILITATION West Richland 13 WA-08830 $577,226 $477,226 CN 2019

I-82/Red Mountain Vicinity - Construct Interchange WSDOT 3 508207R03 $25,047,175 $50,094,361 RW/PE/CN 2019 SR 240/Columbia Center Blvd - Pedestrian Facility Improvement WSDOT - SC 21 524003R03 $671,867 $645,259 CN 2019

SR 221/Paterson Vicinity - Install Weigh-in-Motion WSDOT - SC 21 522102000 $358,720 $293,720 CN 2019

US 395/Ridgeline Drive - Construct Interchange WSDOT - SC 3 539504O03 $17,000,000 $17,000,000 CN 2019 I-82/SR 14 Interchange - Plymouth Weigh Station Improvements WSDOT - SC 21 508211A03 $15,088,500 $15,088,500 PE/RW/CN 2020 I-82/ Bridge WB - Deck Rehabilitation WSDOT - SC 14 508210R03 $15,186,032 $15,186,032 PE/CN 2019 I-82/Columbia River Bridge at Umatilla EB - Bridge Painting WSDOT - SC 40 508202G03 $29,455,726 $29,455,726 PE/CN 2019

I-82/Columbia River Bridge EB - Special Repairs WSDOT - SC 40 508210S03 $908,024 $908,024 PE/CN 2023

23 2019-2024 TIP Amount Project Title Jurisdiction Type STIP ID Total Cost Programmed Phase Start Year US 395/Kennewick - W 19th Ave Noise Walls WSDOT - SC 20 539503W03 $2,084,656 $2,084,656 PE/CN 2019 SR 397/E Bruneau Ave - Railroad Crossing Improvements WSDOT - SC 22 539701V03 $568,039 $355,000 RW/CN 2019 US 395/SR 240 Interchange NB - Safety Improvements WSDOT - SC 21 539504Y03 $184,451 $184,451 PE/CN 2021 SR 397/Ed Hendler Columbia River Bridge - Joint Repair WSDOT - SC 14 539702G03 $1,260,640 $1,260,640 PE/CN 2020 US 395/Pioneer Memorial Bridge - Bridge Painting Stage 2 WSDOT - SC 40 539505R03 $16,036,768 $16,036,768 PE/CN 2021 US 395/Pioneer Memorial Bridge - Bridge Painting Stage 1 WSDOT - SC 40 539504R11 $13,030,154 $12,867,120 CN 2019 US 395/Pasco - Flamingo Mobile Home Park Noise Walls WSDOT - SC 20 539503X11 $1,401,044 $1,207,274 CN 2019 SR 240/Richland Corridor Improvements WSDOT - SC 21 524003O03 $5,000,000 $5,000,000 PE/CN 2019 US 395/Kartchner St & SR 260 I/C - Mitigate Redirectional Landforms WSDOT - SC 21 539506R11 $219,880 $219,880 PE/CN 2019 US 395/Safety Corridor Improvements WSDOT - SC 21 539504P03 $15,000,000 $14,445,815 CN 2019 I-182/Yakima River RC Bremmer Bridges - Joint Repair WSDOT - SC 14 518202P03 $2,718,190 $2,718,190 PE/CN 2020 SR 24/SR 240 to Vernita - Shoulder and Centerline Rumble Strips WSDOT - SC 21 502402T03 $47,789 $41,186 CN 2021 SR 24/Vernita Weigh Station - Preservation WSDOT - SC 21 502402W03 $73,099 $62,940 CN 2019 SR 24/Columbia River Vernita Bridge - Bridge Painting WSDOT - SC 40 502405S03 $3,767,564 $3,767,564 PE/CN 2021 I-182/Col R Lee-Volpentest Columbia River Bridge EB - Joint Repair WSDOT - SC 14 518202R03 $1,951,200 $1,951,200 PE/CN 2020 SR 224/N 62nd Ave to Canal Dr Vicinity - ADA Compliance WSDOT - SC 21 522402G03 $67,692 $67,692 PE/CN 2021 I-82/Gibbon Rd Vic to 1 Mile W of Yakitat Rd - Median Cable Barrier WSDOT - SC 21 508209V03 $942,515 $942,515 PE/CN 2019 Asphalt/Chip Seal Preservation Benton-Franklin Council of Governments WSDOT - SC 5 BPBF $22,692,858 $19,306,938 PE/CN 2019

24 2019-2024 TIP Amount Project Title Jurisdiction Type STIP ID Total Cost Programmed Phase Start Year SR 128 Et Al/SE Washington - Centerline Rumble Strips WSDOT - SC 21 500000G03 $213,428 $213,428 PE/CN 2021 SCR 17-19 Region Wide BCT Replacement - Non Interstate WSDOT - SC 21 500002I03 $300,000 $240,000 CN 2019 SCR Tri-Cities Vicinity - Mitigate Redirectional Landforms WSDOT - SC 21 500001R03 $991,350 $991,350 PE/CN 2019

25 2019-2024 TIP Appendix

Table of Contents Appendix A - Public and Agency Participation Process...... A3 Appendix B - Annual Listing of Federal Obligations...... A12 Appendix C - Secured Projects 2019-2022...... A13 Appendix D - Planned Projects 2019-2024...... A81 Appendix A - Public and Agency Participation Process

Figure A-1: BFCG Expanded Development Schedule for the 2019 TIP

July 1st - Date by which cities and towns are required to adopt their TIPs. (RCW 35.77.010) July 17th - Jurisdiction TIPs due to BFCG – sent electronically through web based STIP software

August 7th – DRAFT 2019-2024 MPO/RTPO TIP is posted to BFCG website for public review August 17th and 24th - Ad in tu Decides August 19th and August 26th – Ad in the Tri-City Herald August 29th – Public Meeting 5:00 – 7:00 pm, Ben Franklin Transit, Richland

September 6th – Technical Advisory Committee (TAC) DRAFT TIP review September 13th - Policy Advisory Committee (PAC) DRAFT TIP review September 28th – Public Comments due to BFCG September 28th – Response(s) from jurisdiction are due to BFCG

October 4th – TAC approval of errata sheet and 2018 MPO/RTPO TIP October 11th – PAC approval of errata sheet and 2018 MPO/RTPO TIP October 19th – BFCG Board DRAFT TIP Review October 19th – BFCG Board approval of errata sheet and 2018 MPO/RTPO TIP October 19th – Forward approved 2018 MPO/RTPO TIP to WSDOT Olympia

A3 2019-2024 TIP Figure A-2: Certification of Private Enterprise Participation Process& Financial Capacity of Transit Operator

Ben Franklin Transit Certification Statement

The Benton‐Franklin Council of Governments as the designated MPO/TMA for the Tri‐Cities, Certifies that Ben Franklin Transit has followed the local process for the projects contained in the 2019 TIP. This process informed all private sector providers of Ben Franklin Transit improvement plans.

MPO Certification Of Transit Operator’s Financial Capacity

UMTA (FTA) Circular 7008.1 requires that MPOs certify the financial capacity of the transit operator for the Annual Element portion of the TIP. The Benton‐Franklin Council of Governments hereby certifies that Ben Franklin Transit has provided financial information showing that they have the financial capacity to carry out the projects programmed in the 2019 M/R TIP. Ben Franklin Transit provided to the Benton‐Franklin Council of Governments a six‐year financial plan that covers 2010‐2024. Ben Franklin Transit’s budget of revenues and expenses for 2019 shows they have the financial capacity to carry out the projects programmed in 2019.

A4 2019-2024 TIP Figure A-3: Open House Flyer - English

Transportation Public Meeting For the Tri-Cities Metropolitan Area and Benton-Franklin Region

Topics Include: Date: Wednesday, August 29th -2019-2024 Transportation Improvement Time: 5:00pm - 7:00pm, Program (TIP)* Presentations at 5:45pm -Ben Franklin Transit Six Year Development Plan & Program of Projects Location: Ben Franklin Transit -Washington State Transportation Administration Building Commission’s Washington Transportation Address: 1000 Columbia Park Trail, Plan Phase 1 -Benton Clean Air Agency & local ozone Richland, WA 99352 information

Attend to learn about and provide Questions? feedback on future transportation [email protected] plans and projects. (509)942-9185 Visit the open house and hear presentations.

*The TIP is a federally mandated planning document of current transportation projects planned to be completed or constructed in the upcoming four years in the Benton-Franklin region. The draft TIP document can be found at www. bfcog.us.

A5 2019-2024 TIP Figure A-4: Open House Flyer - Spanish

Benton Franklin Council of Governments & Ben Franklin Transit Exhibición Abierta al Público para el Área Metropolitana de Tri-Cities y el Área Regional Benton-Franklin -2019 Programa de Mejoramiento de Transportación* (TIP) -Plan de Desarrollo Ben Franklin Transit de Seis Años y Programa de Proyectos -Washington State Transportation Commission’s Washington Transportation Plan Phase 1 -Benton Clean Air y información local sobre el ozon

Asista para aprender y proporcionar reacción sobre futuros planes y proyectos Fecha: 29 de Agosto 2018 de transporte. Horario: 5:00pm - 7:00pm Encuentre el TIP inicial en: Ubicación: Ben Franklin Transit http://bfcog.us/transportation/documents/ Edificio Administrativo metropolitanregional-transportation-impro vement-program Domicilio: 1000 Columbia Park Trail, Para preguntas sobre este evento, por favor Richland, WA 99352 envíe email a [email protected]

Benton-Franklin Council of

Governments 509.943.9183

www.bfcog.us

Ben Franklin Transit www.BFT.org 509-734-5201

A6 2019-2024 TIP Figure A-5: Advertisement in Tu Decides (Spanish Newspaper)

Benton Franklin Council of Governments & Ben Franklin Transit Exhibición Abierta al Público para el Área Metropolitana de Tri-Cities y el Área Regional Benton-Franklin

-2019 Programa de Mejoramiento de Transportación* (TIP) -Plan de Desarrollo Ben Franklin Transit de Seis Años y Programa de Proyectos -Washington State Transportation Commission’s Washington Transportation Plan Phase 1 -Benton Clean Air y información local sobre el ozon

Fecha: 29 de Agosto 2018 Horario: 5:00pm - 7:00pm Ubicación: Ben Franklin Transit Edificio Administrativo Domicilio: 1000 Columbia Park Trail, Richland, WA 99352

Asista para aprender y proporcionar reacción sobre futuros planes y proyectos de transporte.

Encuentre el TIP inicial en: http://bfcog.us/transportation/documents/metropolitanregiona l-transportation-improvement-program

Para preguntas sobre este evento, por favor envíe email a [email protected]

Benton-Franklin Council of Governments 509.943.9183 www.bfcog.us Ben Franklin Transit www.BFT.org 509-734-5201

A7 2019-2024 TIP Figure A-6: Facebook Event for Open House 1 Search FrontOffice Home Find Friends

Event Insights Edit

INSIGHTS See More Events

Events

Calendar 6.3K 43 People Reached Responses Birthdays +1.5K last 7 days +3 last 7 days Discover

Hosting Audience

Track ticket sales on Women 25-34 Create Event your next event by 15% of total reach adding a ticket link

AUG Transportation Public Open House 29 Public · Hosted by Ben Franklin Transit and Benton-Franklin Council of Governments English (US) · Español · Português (Brasil) · Français (France) · Deutsch Interested Going Privacy · Terms · Advertising · Ad Choices · Cookies · More Facebook © 2018 Wednesday, August 29 at 5 PM – 7 PM 5 days ago

Ben Franklin Transit Show Map 1000 Columbia Park Trail, Richland, Washington 99352

Hosted by Benton-Franklin Council of Governments Message Host

About Discussion

Write Post Add Photo/Video Create Poll

Write something...

4 Went · 39 Interested Share this event with your followers

Details

Do you have opinions about current traffic conditions, or want to know what the next four years will bring? Do you want to learn more about ozone in the Tri-Cities?

If you currently drive, carpool, bike, walk, and/or take transit in the Tri-Cities, this public meeting is for you!

Benton-Franklin Council of Governments and Ben Franklin Transit are hosting a public meeting about transportation in the Tri-Cities and the Benton and Franklin region. A variety of topics will be covered, with presentations and an open house format.

Presentations start at 5:45pm. Topics include: (1) the 2019-2024 Transportation Improvement Program (TIP)*, (2) Ben Franklin Transit Six Year Development Plan & Program of Projects, (3) Washington State Transportation Commission’s Washington Transportation Plan Phase 1, and A8 (4) local ozone information. 2019-2024 TIP

Attend to learn about and provide feedback on future transportation plans Chat (Off) Figure A-7: Facebook Event for Open House (Continued)

and projects. 1 Search FrontOffice Home Find Friends If you have any questions or cannot attend, message us here, email Event Insights [email protected], or call us at (509)943-9185. Edit

*The TIP is a federally required planning document of current transportation INSIGHTS See More Events projects planned to be completed or constructed in the upcoming four years in the Benton-Franklin region. More information about the TIP can be found at http://bfcog.us/transportation/documents/metropolitanregional- Events transportation-improvement-program/.

Calendar For more information on upcoming open houses ‘like us’ on Facebook, or 6.3K 43 People Reached Responses contact our office at (509) 943-9185. Birthdays +1.5K last 7 days +3 last 7 days

Discover See Less

Hosting Audience Networking Track ticket sales on Women 25-34 your next event by Create Event 15% of total reach adding a ticket link Recent Post

Benton-Franklin Council of Governments — If you currently drive, carpool, bike, walk, and/or take transit in the Tri-Cities, this public meeting is for you! English (US) · Español · Português (Brasil) · Français (France) · Deutsch August 16, 2018 at 9:22 PM

Privacy · Terms · Advertising · Ad Choices · See All Posts Cookies · More Facebook © 2018

About Benton-Franklin Council of Governments

Benton-Franklin Council of Governments Government Organization · Richland, Washington Economic Development | Community Development | Metropolitan Transportation Planning

About the Venue

Ben Franklin Transit Transportation Service · 1,486 likes

Go to Page

1 post in the discussion.

See Discussion

A9 2019-2024 TIP

Chat (Off) Figure A-8: Tri-City Herald Advertisement for Open House

A10 2019-2024 TIP Figure A-9: TIP Administration Appendix B - Annual Listing of Federal Obligations

PENDING

A12 2019-2024 TIP Appendix C - Secured Projects 2019-2022

A13 2019-2024 TIP Washington State S. T. I. P. 2019 to 2022 (Project Funds to Nearest Dollar) totals for years 2019 thru 2022

Report Date - August 29, 2018

Selection Criteria (from SEARCH panel - if any)

Agency MPO Project ID County Agency Project ID MPO Secured Y Inside MPO Planned Region Amended Amendment Number Is New Envrionmental Classification Current Action Priority Number Future Action PIN Approved as of Date Title Federal Fund Code STIP ID State Fund Code

Page 1 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: Ben Franklin Transit

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 00 WA-06637 23 CE No N/A N/A 7,425,551 2019 - 2022 Equipment: Communication, security, data collection, passenger amenities, maintenance equipment, integrated technology projects Purchase equipment to be installed on vehicles at the manufacturer or post vehicle delivery on BFT site. Also includes back office support for on road applications and maintenance equipment, design and permitting on projects, and Integrated Technology Systems (ITS) such as on-board technologies and ITS items to be installed at transit centers and bus stops.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total ALL 2019 5307 100,000 0 547,500 647,500

ALL 2020 5307 100,000 0 1,625,000 1,725,000

ALL 2021 5307 600,000 0 826,865 1,426,865

ALL 2022 5307 640,000 0 636,186 1,276,186

Project Totals 1,440,000 0 3,635,551 5,075,551

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 647,500 1,725,000 1,426,865 1,276,186 2,350,000 Totals 647,500 1,725,000 1,426,865 1,276,186 2,350,000

Page 2 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: Ben Franklin Transit

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 00 WA-05096 23 CE No N/A N/A 17,275,000 2019 - 2022 Facilities This is a bucket TIP project containing Ben Franklin Transit's FTA and State funding for facilities design/planning, equipment, paving, painting, security systems, shelters, passenger amenities, and aesthetics. During the years of the TIP this funding will provide upgrades and improved security to the system.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total ALL 2019 5307 800,000 0 2,625,000 3,425,000

ALL 2019 0 WSDOT 6,640,000 1,360,000 8,000,000

ALL 2019 5339 1,200,000 0 300,000 1,500,000

ALL 2020 5307 120,000 0 1,730,000 1,850,000

ALL 2021 5307 160,000 0 990,000 1,150,000

ALL 2022 5307 180,000 0 245,000 425,000

Project Totals 2,460,000 6,640,000 7,250,000 16,350,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 12,925,000 1,850,000 1,150,000 425,000 925,000 Totals 12,925,000 1,850,000 1,150,000 425,000 925,000

Page 3 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: Ben Franklin Transit

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 00 WA-04000 23 CE No N/A N/A 60,127,348 2019 - 2022 Operating, Preventative Maintenance This is a bucket TIP project containing Ben Franklin Transit FTA funded, General Labor Operating for fixed route operations. During all years of this project 5307 Funds will be matched with local to maintain transit service.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total ALL 2019 5307 4,886,801 0 4,886,801 9,773,602

ALL 2020 5307 4,935,669 0 4,935,669 9,871,338

ALL 2021 5307 4,985,026 0 4,985,026 9,970,052

ALL 2022 5307 5,034,876 0 5,034,876 10,069,752

Project Totals 19,842,372 0 19,842,372 39,684,744

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 9,773,602 9,871,338 9,970,052 10,069,752 20,442,604 Totals 9,773,602 9,871,338 9,970,052 10,069,752 20,442,604

Page 4 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: Ben Franklin Transit

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 00 WA-05091 23 CE No N/A N/A 25,039,560 2019 - 2022 Transit Vehicle Replacements This is a bucket TIP project which contains Ben Franklin Transit's FTA and State funded Revenue Vehicles for Replacement or Expansion including Transit Buses, Paratranist Coaches, Staff, and Vanpool Rideshare Vehicles. During all years of this project, the project will provide a cumulative total of up to 345 transit vehicles.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total ALL 2019 0 WSDOT 2,128,033 748,963 2,876,996

ALL 2020 0 WSDOT 759,316 1,060,907 1,820,223

ALL 2021 0 WSDOT 774,502 778,579 1,553,081

ALL 2022 5307 1,222,119 WSDOT 1,988,143 1,100,317 4,310,579

ALL 2022 5339 2,832,906 0 708,227 3,541,133

Project Totals 4,055,025 5,649,994 4,396,993 14,102,012

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 2,876,996 1,820,223 1,553,081 7,851,712 10,937,548 Totals 2,876,996 1,820,223 1,553,081 7,851,712 10,937,548

Federal Funds State Funds Local Funds Total Agency Totals for Ben Franklin 27,797,397 12,289,994 35,124,916 75,212,307 Transit

Page 5 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: Benton City

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 02 BC-000013 21 0.180 CE No Ellen Ave Horne Drive 121,148 9th Street Sidewalk Construct new sidewalk, ADA ramps, curb & gutter, storm drainage and small block walls.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 TAP(R) 15,000 0 0 15,000

CN 2019 TAP(R) 106,148 0 0 106,148

Project Totals 121,148 0 0 121,148

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 15,000 0 0 0 0 CN 106,148 0 0 0 0 Totals 121,148 0 0 0 0

Federal Funds State Funds Local Funds Total Agency Totals for Benton City 121,148 0 0 121,148

Page 6 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: Benton Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 17 3509(009) WA-09854 28 0.300 CE No 3.19 3.49 107,614 Badger Mountain - Candy Mountain Connector Pathway Construct a new multimodal pathway along Dallas Road between the Badger Mountain trailhead and the new Candy Mountain trailhead.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 TAP(R) 95,614 0 0 95,614

Project Totals 95,614 0 0 95,614

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 95,614 0 0 0 0 Totals 95,614 0 0 0 0

Page 7 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: Benton Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 08 WA-10232 28 7.100 CE No 4.679 11.765 420,000 Badger Road Pathway This project proposes to construct multimodal pathways along either side of Badger Road from approximately Dallas Road to I-82 (about seven miles).

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2022 0 0 420,000 420,000

Project Totals 0 0 420,000 420,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 0 0 0 420,000 0 Totals 0 0 0 420,000 0

Federal Funds State Funds Local Funds Total Agency Totals for Benton Co. 95,614 0 420,000 515,614

Page 8 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: BFCG

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 00 WA-10725 18 CE No N/A N/A 189,306 2019-2021 Unified Planning Work Program This project will support tasks outlined in BFCG's UPWP for years 2019,2020 and 2021. Primarily "Program Administration, Interagency Coordination and Public Involement" in the Tri-Cities metropolitan area. The work elements are identified numerically as 220 in the UPWP.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 STP(UL) 45,984 0 6,208 52,192

PE 2019 STP(US) 1,512 0 204 1,716

PE 2019 STP(R) 8,100 0 1,094 9,194

PE 2020 STP(R) 8,100 0 1,094 9,194

PE 2020 STP(US) 1,512 0 204 1,716

PE 2020 STP(UL) 45,984 0 6,208 52,192

PE 2021 STP(UL) 45,984 0 6,208 52,192

PE 2021 STP(US) 1,512 0 204 1,716

PE 2021 STP(R) 8,100 0 1,094 9,194

Project Totals 166,788 0 22,518 189,306

Page 9 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: BFCG

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 63,102 63,102 63,102 0 0 Totals 63,102 63,102 63,102 0 0

Federal Funds State Funds Local Funds Total Agency Totals for BFCG 166,788 0 22,518 189,306

Page 10 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Franklin Agency: Franklin Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 09 2011(050) WA-09041 11 0.100 CE No 8.74 8.84 363,100 Selph Landing #906-8.79 Replacement Replace existing bridge

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 STP(BR) 233,090 CRAB 58,300 0 291,390

Project Totals 233,090 58,300 0 291,390

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 291,390 0 0 0 0 Totals 291,390 0 0 0 0

Page 11 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Franklin Agency: Franklin Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 07 E112(002) WA-00157 11 0.100 CE No Milepost 3.41 Milepost 3.51 1,172,803 Taylor Flats Bridge #903-3.46 The project consists of replacing a functionally obsolete bridge to meet current standards.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 STP(R) 520,438 CRAB 81,196 28 601,662

CN 2019 STP(UL) 234,537 CRAB 36,604 0 271,141

Project Totals 754,975 117,800 28 872,803

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 872,803 0 0 0 0 Totals 872,803 0 0 0 0

Federal Funds State Funds Local Funds Total Agency Totals for Franklin Co. 988,065 176,100 28 1,164,193

Page 12 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: Kennewick

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 12 3457(002) kenn6 04 0.250 CE Yes Ridgeline Drive US395 Intersection 5,644,259 US395/Ridgeline Drive Interchange Construction of a grade separated intersection at US395 and Ridgeline Drive, and associated vicinity improvements. Construction will be done by WSDOT and is programmed under STIP # 539504003.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2020 NHFP 1,944,259 0 0 1,944,259

Project Totals 1,944,259 0 0 1,944,259

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 0 1,944,259 0 0 0 Totals 0 1,944,259 0 0 0

Page 13 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: Kennewick

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 16 kenn9 04 0.540 CE No Joliet Street Columbia Center Blvd. 2,615,000 West 10th Avenue Widening - Joliet St. to Columbia Center Blvd. Widen south side of 10th Avenue to complete 3-lane road, with bike lane, curb, gutter, sidewalk, storm drainage, illumination and HMA Overlay of existing.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 STP(UL) 2,585,000 0 0 2,585,000

Project Totals 2,585,000 0 0 2,585,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 2,585,000 0 0 0 0 Totals 2,585,000 0 0 0 0

Federal Funds State Funds Local Funds Total Agency Totals for Kennewick 4,529,259 0 0 4,529,259

Page 14 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Franklin Agency: Pasco

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 14 3530(006) WA-01715 03 0.450 EIS Yes Oregon Ave 2nd Ave 35,547,906 Lewis Street Overpass Construct a new overpass between 2nd Ave and Oregon Ave. A new overpass will replace the existing underpass which is deteriorating.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 0 CWA 600,000 0 600,000

Project Totals 0 600,000 0 600,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 600,000 0 0 0 0 CN 0 0 0 0 30,500,000 Totals 600,000 0 0 0 30,500,000

Page 15 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Franklin Agency: Pasco

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 14 WA-08734 21 CE Yes various various 3,400,000 Traffic Signal Improvements - City Wide Phase 2 Replace all of the City’s obsolete signal equipment with updated signal controllers, signal equipment, signal interconnect equipment, optimized corridor timing plans, vehicle detection system and emergency vehicle priority system. Pedestrian access will be upgraded to meet current ADA right of way accessibility design guidelines for the signalized intersections. PE done under federal project 9911(010)

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total RW 2019 STP(UL) 259,500 0 40,500 300,000

CN 2019 STP(UL) 2,382,861 0 470,248 2,853,109

CN 2019 TAP(UL) 146,891 0 0 146,891

Project Totals 2,789,252 0 510,748 3,300,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th RW 300,000 0 0 0 0 CN 1,500,000 1,500,000 0 0 0 Totals 1,800,000 1,500,000 0 0 0

Page 16 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Franklin Agency: Pasco

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 09 WA-06941 01 1.000 CE No Clemente Lane Convention Drive 260,000 Wrigley Drive Extension This project will extend Wrigley Drive from Clemente Lane to Convention Drive. This project will design and construct a “core” road, 28-ft in width without curb and gutter, for an approximate length of 500 feet. The project will also require the relocation of an existing center-pivot irrigation system, drilling of a new irrigation well to replace the existing center-pivot well, and acquisition of right-of-way. The intersections at both ends will be designed & constructed to potentially accommodate future roundabouts (~10% design).

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 0 0 30,000 30,000

CN 2019 0 0 230,000 230,000

Project Totals 0 0 260,000 260,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 30,000 0 0 0 0 CN 230,000 0 0 0 0 Totals 260,000 0 0 0 0

Federal Funds State Funds Local Funds Total Agency Totals for Pasco 2,789,252 600,000 770,748 4,160,000

Page 17 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Franklin Agency: Port of Pasco

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 00 WA-11625 04 1.130 CE No SE Road 18 E SE Road 36 E 1,435,775 Big Pasco Intermodal Rail Reconstruction Reconstruct WWII era port-owned rail which is actively used for intermodal transloading and bulk deliveries.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 NHFP 150,000 0 20,250 170,250

CN 2020 NHFP 1,115,000 0 150,525 1,265,525

Project Totals 1,265,000 0 170,775 1,435,775

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 170,250 0 0 0 0 CN 0 1,265,525 0 0 0 Totals 170,250 1,265,525 0 0 0

Federal Funds State Funds Local Funds Total Agency Totals for Port of Pasco 1,265,000 0 170,775 1,435,775

Page 18 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: Richland

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 16 3459(001) R001 01 0.330 CE Yes Gage Blvd Tapteal Dr 2,623,444 Center Parkway North Extension Construct new 3-lane roadway with bike lanes, curb, gutter and sidewalk on both sides. Construct a signalized/gated at-grade crossing of the Port of Benton R/R track.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2021 0 TIB 219,714 0 219,714

Project Totals 0 219,714 0 219,714

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 0 0 1,374,144 0 0 Totals 0 0 1,374,144 0 0

Page 19 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: Richland

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 16 R010 04 0.720 CE No SR 240 WB Offramp East City Limits 2,906,410 Columbia Park Trail - East Reconstruct the street to provide 3-lanes, with curb, gutter, sidewalks, bike lanes street lights, drainage facilities and streetscape on both sides.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 TAP(UL) 50,000 0 0 50,000

PE 2019 STP(UL) 55,000 0 20,000 75,000

CN 2020 STP(UL) 918,700 0 925,000 1,843,700

CN 2020 TAP(UL) 353,623 0 584,087 937,710

Project Totals 1,377,323 0 1,529,087 2,906,410

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 125,000 0 0 0 0 CN 0 2,781,410 0 0 0 Totals 125,000 2,781,410 0 0 0

Page 20 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: Richland

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 16 3440(001) R036 03 0.200 EA Yes Riverstone Drive Cottonwood Street 3,717,500 Duportail Bridge - Phase 2 Reconstruct roadway, railroad crossing, and the signalized SR 240 intersection to accommodate additional lanes on Duportail Street and SR 240.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 0 CWA 3,300,000 0 3,300,000

Project Totals 0 3,300,000 0 3,300,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 4,184,195 0 0 0 0 Totals 4,184,195 0 0 0 0

Page 21 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: Richland

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 14 R037 05 4.700 CE No Guyer Street Horn Rapids Road 4,192,000 George Washington Way Pavement Preservation This project will mill and fill the entire roadway, address ADA ramp compliance, and restripe.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 NHPP 3,033,600 0 1,058,400 4,092,000

Project Totals 3,033,600 0 1,058,400 4,092,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 4,092,000 0 0 0 0 Totals 4,092,000 0 0 0 0

Federal Funds State Funds Local Funds Total Agency Totals for Richland 4,410,923 3,519,714 2,587,487 10,518,124

Page 22 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Benton Agency: West Richland

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 16 WA-08830 13 0.000 CE No Bombing Range Road SR 224 577,226 BOMBING RANGE RD BRIDGE REHABILITATION BRIDGE REHABILITATION: REPLACE PORTION OF SUPERSTRUCTURE DUE TO AGING GIRDERS.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 STP(BR) 412,800 0 64,426 477,226

Project Totals 412,800 0 64,426 477,226

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 477,226 0 0 0 0 Totals 477,226 0 0 0 0

Federal Funds State Funds Local Funds Total Agency Totals for West Richland 412,800 0 64,426 477,226

Page 23 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 00 BPBF BPBF 05 CE No Varies Varies 22,692,858 Asphalt/Chip Seal Preservation Benton-Franklin Council of Governments Resurface the roadway with chip seal or hot mix asphalt to preserve the structural integrity of the roadway and extend the service life of the pavement. This record is for chip seal/asphalt paving projects within Benton and Franklin counties. For a list of included projects, go to www.wsdot.wa.gov/projects/search.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2020 NHPP 31,942 0 1,278 33,220

PE 2021 NHPP 166,193 0 7,977 174,170

PE 2021 STP 33,233 0 0 33,233

PE 2022 STP 242,584 0 9,703 252,287

CN 2019 NHPP 6,080,747 0 146,133 6,226,880

CN 2019 STP 1,225,885 0 0 1,225,885

CN 2020 NHPP 542,974 0 24,724 567,698

CN 2020 STP 693,215 0 0 693,215

CN 2021 STP 1,959,653 0 68,844 2,028,497

CN 2021 NHPP 1,482,529 0 0 1,482,529

CN 2022 NHPP 915,696 0 31,072 946,768

CN 2022 STP 637,905 0 0 637,905

Project Totals 14,012,556 0 289,731 14,302,287

Page 24 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 7,452,765 1,294,133 3,718,429 1,836,960 5,004,651 Totals 7,452,765 1,294,133 3,718,429 1,836,960 5,004,651

Page 25 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 01 518202R 518202R03 14 0.370 CE No 5.87 6.24 1,951,200 I-182/Col R Lee-Volpentest Columbia River Bridge EB - Joint Repair Repair expansion joints - Bridge 182/16S. The bridge joints on the eastbound I-182 Col R Lee-Voplentest bridge over the Columbia River are deteriorating and need to be repaired. This project will replace the existing joints to provide a smoother ride and preserve the structural integrity of the bridges.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2020 NHPP 185,760 0 7,740 193,500

CN 2021 NHPP 1,722,546 0 35,154 1,757,700

Project Totals 1,908,306 0 42,894 1,951,200

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 72,512 127,047 1,713,026 38,614 Totals 0 72,512 127,047 1,713,026 38,614

Page 26 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 01 518202P 518202P03 14 0.160 CE No 3.54 3.70 2,718,190 I-182/Yakima River RC Bremmer Bridges - Joint Repair Repair expansion joints - Bridges 182/10S & 182/10N. The bridge joints on the I-182 Yakima River - R.C. Bremmer Bridges in Richland are deteriorating and need to be repaired. This project will replace the existing joints to provide a smoother ride and preserve the structural integrity of the bridges.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2020 NHPP 258,000 0 10,750 268,750

CN 2021 NHPP 2,400,451 0 48,989 2,449,440

Project Totals 2,658,451 0 59,739 2,718,190

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 105,232 171,051 2,424,762 17,146 Totals 0 105,232 171,051 2,424,762 17,146

Page 27 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 01 508207R 508207R03 03 1.500 CE Yes 99.00 100.50 25,047,175 I-82/Red Mountain Vicinity - Construct Interchange Construct interchange. Improved access to the I-82 corridor between Benton County and the I-182 junction is critical for continuing economic development. This project will construct a new freeway overpass and on- and off-ramps for I-82 east of Benton City, to provide direct interstate access to West Richland and the surrounding Red Mountain area, and a new connection to SR 224.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 STP 492,883 CWA 578,466 0 1,071,349

RW 2019 0 CWA 4,648,640 0 4,648,640

CN 2020 0 CWA 19,327,186 0 19,327,186

Project Totals 492,883 24,554,292 0 25,047,175

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 500,000 5,129,989 19,000,000 327,186 0 Totals 500,000 5,129,989 19,000,000 327,186 0

Page 28 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 00 500002I 500002I03 21 CE No Varies Varies 300,000 SCR 17-19 Region Wide BCT Replacement - Non Interstate Replace breakaway cable terminals. This project will replace existing breakaway cable terminals on guardrail runs on non-interstate routes in South Central Region to meet current standards and reduce the severity of collisions. This record is for the BFCG portion of a region wide project.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 NHPP 235,200 0 4,800 240,000

Project Totals 235,200 0 4,800 240,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 240,000 0 0 0 0 Totals 240,000 0 0 0 0

Page 29 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 00 500001R 500001R03 21 CE No Varies Varies 991,350 SCR Tri-Cities Vicinity - Mitigate Redirectional Landforms Mitigate redirectional landforms. Redirectional landforms are no longer used for mitigating fixed objects along the roadway. This project will remove or shield existing reidrectional landforms on I-182, SR 240, and US 12 to reduce the risk of collisions.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 NHPP 151,056 0 6,294 157,350

CN 2020 NHPP 817,320 0 16,680 834,000

Project Totals 968,376 0 22,974 991,350

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 30,464 128,489 803,782 28,615 0 Totals 30,464 128,489 803,782 28,615 0

Page 30 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 00 500000G 500000G03 21 CE No Varies Varies 213,428 SR 128 Et Al/SE Washington - Centerline Rumble Strips Install centerline rumble strips. These sections of state routes 125, 128, 225, and 240 are two-lane roadways with a high potential for crossover collisions. By installing centerline rumble strips, this project will reduce the risk of this type of collision and improve safety. Shoulder rumble strips may also be considered if warranted. This record is for the Benton County portion of the project.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2021 HSIP 41,202 0 1,717 42,919

CN 2022 HSIP 167,099 0 3,410 170,509

Project Totals 208,301 0 5,127 213,428

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 32,919 180,509 0 Totals 0 0 32,919 180,509 0

Page 31 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 06 522402G 522402G03 21 0.890 CE No 6.55 7.44 67,692 SR 224/N 62nd Ave to Canal Dr Vicinity - ADA Compliance Upgrade existing curb ramps to meet ADA Compliance. Pedestrian ADA curb ramps at various intersections on SR 224 in West Richland do not fully meet ADA standards. This project will upgrade the curb ramps to meet current standards, improving accessibility for all pedestrians.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2021 STP 5,870 0 245 6,115

CN 2021 STP 60,345 0 1,232 61,577

Project Totals 66,215 0 1,477 67,692

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 6,115 6,038 939 Totals 0 0 6,115 6,038 939

Page 32 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 14 524003R 524003R03 21 0.230 CE No 0.00 0.23 671,867 SR 240/Columbia Center Blvd - Pedestrian Facility Improvement Improve pedestrian mobility and safety features. The existing SR 240/Columbia Center Blvd interchange does not have facilities to allow pedestrians to safely cross the highway. This project will improve existing and construct new pedestrian facilities to allow safe crossing of the highway on Columbia Ctr. Blvd. The termini are for the RRT/RRQ LX03890.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 NHPP 632,354 0 12,905 645,259

Project Totals 632,354 0 12,905 645,259

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 602,672 42,587 0 0 0 Totals 602,672 42,587 0 0 0

Page 33 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 14 524003O 524003O03 21 12.700 CE No 20.40 34.87 5,000,000 SR 240/Richland Corridor Improvements Intersection Improvements. SR 240 in Richland is experiencing increased congestion at several existing intersections. This project will construct intersection improvements along the SR 240 corridor in Richland to improve the safety and operational efficiency of this route. Improvements include acceleration and deceleration lanes, new channelization and signal system upgrades.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 0 CWA 500,000 0 500,000

CN 2020 0 CWA 4,500,000 0 4,500,000

Project Totals 0 5,000,000 0 5,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 298,000 4,245,038 456,961 0 0 Totals 298,000 4,245,038 456,961 0 0

Page 34 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 02 0397(013) 539701V 539701V03 22 0.100 CE Yes 17.76 17.86 568,039 SR 397/E Bruneau Ave - Railroad Crossing Improvements Install cantilever-mounted beacons - Xing #808925X. The railroad crossing on SR 397 at E Bruneau Ave has been identified as a location with a potential for train/vehicle collisions. The crossing is currently equipped with shoulder-mounted railroad crossing signs. This project will install cantilever-mounted flashing beacons to reduce the risk of collisions.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total RW 2019 HSIP 58,800 0 1,200 60,000

CN 2019 HSIP 289,100 0 5,900 295,000

Project Totals 347,900 0 7,100 355,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 346,000 9,000 0 0 0 Totals 346,000 9,000 0 0 0

Page 35 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 14 539702G 539702G03 14 0.480 CE No 18.08 18.56 1,260,640 SR 397/Ed Hendler Columbia River Bridge - Joint Repair Repair expansion joints - Bridge 397/20. The bridge joints on the SR 397 Ed Hendler Bridge over the Columbia River are deteriorating and need to be repaired. This project will replace the existing joints to provide a smoother ride and preserve the structural integrity of the bridges.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2020 NHPP 165,120 0 6,880 172,000

CN 2021 NHPP 1,066,867 0 21,773 1,088,640

Project Totals 1,231,987 0 28,653 1,260,640

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 56,638 117,805 1,078,400 7,797 Totals 0 56,638 117,805 1,078,400 7,797

Page 36 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 02 539506R 539506R11 21 31.520 CE No 23.63 55.15 219,880 US 395/Kartchner St & SR 260 I/C - Mitigate Redirectional Landforms Mitigate redirectional landforms. Redirectional landforms are no longer used for mitigating fixed objects along the roadway. This project will remove or shield the existing redirectional landforms on US 395 to reduce the risk of collisions.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 NHPP 40,282 0 1,678 41,960

CN 2020 NHPP 174,362 0 3,558 177,920

Project Totals 214,644 0 5,236 219,880

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 8,920 33,040 175,771 2,149 0 Totals 8,920 33,040 175,771 2,149 0

Page 37 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 14 539503W 539503W03 20 0.260 CE No 15.58 15.84 2,084,656 US 395/Kennewick - W 19th Ave Noise Walls Install noise walls. This project will install noise walls in the vicinity of West 19th Ave to reduce the highway noise for adjacent homes and properties.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 NHPP 276,014 0 11,501 287,515

CN 2021 NHPP 1,761,199 0 35,942 1,797,141

Project Totals 2,037,213 0 47,443 2,084,656

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 123,317 138,423 1,822,916 0 0 Totals 123,317 138,423 1,822,916 0 0

Page 38 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 14 0395(099) 539503X 539503X11 20 0.260 CE No 19.07 19.33 1,401,044 US 395/Pasco - Flamingo Mobile Home Park Noise Walls Install noise walls. This project will install noise walls in the vicinity of Flamingo Mobile Home Park to reduce the highway noise for adjacent homes and properties.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 NHPP 1,183,128 0 24,146 1,207,274

Project Totals 1,183,128 0 24,146 1,207,274

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 1,181,764 25,510 0 0 0 Totals 1,181,764 25,510 0 0 0

Page 39 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 14 0395(111) 539504R 539504R11 40 0.230 CE No 18.75 18.98 13,030,154 US 395/Pioneer Memorial Bridge - Bridge Painting Stage 1 Paint Bridge 395/40. The existing steel surfaces on the US 395 Pioneer Memorial Bridge between Kennewick and Pasco are in need of cleaning and painting. This project will clean and paint the existing steel surface to preserve the structural integrity of the bridge.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 NHPP 12,614,824 CWA 252,296 0 12,867,120

Project Totals 12,614,824 252,296 0 12,867,120

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 12,424,061 190,762 0 0 0 Totals 12,424,061 190,762 0 0 0

Page 40 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 12 539505R 539505R03 40 0.220 CE No 18.75 18.97 16,036,768 US 395/Pioneer Memorial Bridge - Bridge Painting Stage 2 Paint Bridge 395/40. The existing steel surfaces on the US 395 Pioneer Memorial Bridge between Kennewick and Pasco are in need of cleaning and painting. This project will clean and paint the existing steel structure to preserve the integrity of the bridge.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2021 NHPP 499,014 0 20,793 519,807

CN 2022 NHPP 15,206,621 0 310,340 15,516,961

Project Totals 15,705,635 0 331,133 16,036,768

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 65,059 446,740 15,460,877 Totals 0 0 65,059 446,740 15,460,877

Page 41 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 02 3457(002) 539504O 539504O03 03 0.800 CE No 13.30 14.10 17,000,000 US 395/Ridgeline Drive - Construct Interchange Construct interchange. The intersection of US 395 and Ridgeline Drive experiences congestion due to recent development in this fast growing area of Kennewick, including a new high school and hospital. This four-laned limited access highway connects I-82 with I-182 through Pasco and Kennewick. Heavy truck volumes and higher vehicle speeds make safe access at this intersection a concern. This project will construct a new grade separated interchange to reduce congestion, improve access, and reduce the of collisions. PE and possible RW phases are being delivered by the City of Kennewick under STIP ID "kenn6".

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 0 CWA 15,000,000 2,000,000 17,000,000

Project Totals 0 15,000,000 2,000,000 17,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 16,818,043 181,957 0 0 Totals 0 16,818,043 181,957 0 0

Page 42 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG Y Inside N Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 12 539504Y 539504Y03 21 0.500 CE No 17.95 18.45 184,451 US 395/SR 240 Interchange NB - Safety Improvements Reconfigure lanes. This location on northbound US 395 at the off-ramp to westbound SR 240 has a history of collisions. This project will reconfigure the lanes to improve traffic flow between US 395 and SR 240 and reduce the risk of collisions.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2021 NHPP 40,960 0 1,707 42,667

CN 2022 NHPP 138,948 0 2,836 141,784

Project Totals 179,908 0 4,543 184,451

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 32,798 151,653 0 Totals 0 0 32,798 151,653 0

Federal Funds State Funds Local Funds Total Agency Totals for WSDOT - SC 54,697,881 44,806,588 2,887,901 102,392,370

Page 43 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Benton Agency: Benton Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 00 BCO2012-27 04 CE No various various 1,500,000 EMERGENT PROJECTS Construct emergent projects.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total ALL 2019 0 0 1,400,000 1,400,000

Project Totals 0 0 1,400,000 1,400,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 233,000 234,000 250,000 250,000 500,000 Totals 233,000 234,000 250,000 250,000 500,000

Page 44 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Benton Agency: Benton Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 08 BCO2012-09 04 3.000 CE Yes Coffin Rd Beck Rd 10,000 NINE CANYON RD Ph. III: Coffin to Beck Reconstruct a segment of gravel road to an all weather road.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 0 0 10,000 10,000

Project Totals 0 0 10,000 10,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 10,000 0 0 0 0 Totals 10,000 0 0 0 0

Federal Funds State Funds Local Funds Total Agency Totals for Benton Co. 0 0 1,410,000 1,410,000

Page 45 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Franklin Agency: Connell

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 00 WA-10805 03 3.520 No MP 110.45 MP 112.55 24,100,000 Connell Rail Interchange Relocating current switch yard to new location, for better mobility and ease of access.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2020 0 CWA 600,000 0 600,000

CN 2021 0 CWA 9,400,000 0 9,400,000

Project Totals 0 10,000,000 0 10,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 600,000 0 0 0 CN 0 0 23,500,000 0 0 Totals 0 600,000 23,500,000 0 0

Page 46 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Franklin Agency: Connell

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 19 WA-00822 03 0.300 CE No Columbia Ave Pioneer Pool 860,000 East Birch Street Reconstruction, drainage, curbs, gutters and sidewalk on one side.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 0 OTHER 60,000 0 60,000

CN 2019 0 TIB 778,500 21,500 800,000

Project Totals 0 838,500 21,500 860,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 60,000 0 0 0 0 CN 800,000 0 0 0 0 Totals 860,000 0 0 0 0

Page 47 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Franklin Agency: Connell

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 16 WA-00688 05 No City Limit City Limit 35,000 Street Preservation Program Overlays, seals,ETC.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 0 0 35,000 35,000

Project Totals 0 0 35,000 35,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 35,000 0 0 0 0 Totals 35,000 0 0 0 0

Federal Funds State Funds Local Funds Total Agency Totals for Connell 0 10,838,500 56,500 10,895,000

Page 48 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Franklin Agency: Franklin Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 09 WA-07940 28 0.200 CE No 0.06 0.26 375,000 Basin City Alternative Transportation Route Improvements II Replace pedestrian ramps, install new trail and/or sidewalks, improve adjunct facilities, and improve drainage.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 TAP(R) 34,600 0 5,400 40,000

Project Totals 34,600 0 5,400 40,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 20,000 20,000 0 0 0 Totals 20,000 20,000 0 0 0

Page 49 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Franklin Agency: Franklin Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 09 2011(049) WA-10376 11 0.100 CE No 9.88 9.98 1,113,585 Coyan Bridge #200-9.93 Replace existing structurally-deficient bridge

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 STP(BR) 762,048 CRAB 190,500 12 952,560

Project Totals 762,048 190,500 12 952,560

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 952,560 0 0 0 0 Totals 952,560 0 0 0 0

Page 50 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Franklin Agency: Franklin Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 09 2011(051) WA-10962 22 0.330 CE No 0.00 0.33 105,555 Hailey Railroad/Highway Crossing Upgrade existing crossing warning to solar powered flashing system at USDOT Crossing Number 089696T

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 HSIP 81,500 0 9,055 90,555

Project Totals 81,500 0 9,055 90,555

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 90,555 0 0 0 0 Totals 90,555 0 0 0 0

Page 51 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Franklin Agency: Franklin Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 09 WA-01006 01 4.200 CE Yes Pasco-Kahlotus Road Milepost 4.2 3,063,750 Juniper Dunes Recreation Area Access Construct new access road into the Area managed by USBLM. The federal portion of the funding includes both a Federal Lands Access Program grant and a grant from the Bureau of Land Management.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 WFL 1,570,000 0 75,000 1,645,000

CN 2019 Discretionary 952,083 0 0 952,083

Project Totals 2,522,083 0 75,000 2,597,083

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 2,597,083 0 0 0 0 Totals 2,597,083 0 0 0 0

Page 52 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Franklin Agency: Franklin Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 07 F115(003) WA-05183 04 3.010 CE Yes MP 5.92 - Peterson Road MP 8.93 2,796,561 Pasco-Kahlotus Road Reconstruction/Overlay II The project will upgrade an existing two-lane roadway to provide safety, mobility, and approach improvements. The improvements will consist of reconstructing a portion of the roadway to correct for vertical sight distance issues, pavement widening and overlay for the total length of the project, roadway-related storm water facilities, and address clear zone issues.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 0 CRAB 1,620,000 180,000 1,800,000

CN 2019 STP(R) 330,100 0 51,518 381,618

Project Totals 330,100 1,620,000 231,518 2,181,618

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 2,181,618 0 0 0 0 Totals 2,181,618 0 0 0 0

Page 53 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Franklin Agency: Franklin Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 00 000S(497) WA-10372 21 CE No Varies Varies 295,000 Safety - Countywide Intersection Improvements Install/upgrade signing, pavement markings, illumination, and rumble strips

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 HSIP 270,000 0 0 270,000

Project Totals 270,000 0 0 270,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 270,000 0 0 0 0 Totals 270,000 0 0 0 0

Page 54 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Franklin Agency: Franklin Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 07 000S(495) WA-10371 21 CE No Varies Varies 160,000 Safety - Flexible Guidepost Install flexible guidepost

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 HSIP 145,000 0 0 145,000

Project Totals 145,000 0 0 145,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 145,000 0 0 0 0 Totals 145,000 0 0 0 0

Page 55 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Franklin Agency: Franklin Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 07 000S(494) WA-10373 21 2.040 CE No 1.96 4.00 125,000 Safety - Rumble Bars Install surface mounted shoulder rumble bars

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 HSIP 114,000 0 0 114,000

Project Totals 114,000 0 0 114,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 114,000 0 0 0 0 Totals 114,000 0 0 0 0

Page 56 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Franklin Agency: Franklin Co.

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 09 WA-11517 11 0.020 CE No 0.06 0.08 15,000 Smith Canyon #722-0.07 Bridge Replacement Replace existing 22' timber structure with steel arch pipe structure

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 0 0 13,500 13,500

Project Totals 0 0 13,500 13,500

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 13,500 0 0 0 0 Totals 13,500 0 0 0 0

Federal Funds State Funds Local Funds Total Agency Totals for Franklin Co. 4,259,331 1,810,500 334,485 6,404,316

Page 57 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Benton Agency: Prosser

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 17 WA-10056 04 0.600 CE Yes Florence St 7th St 2,901,916 Bennett Avenue Improvements Reconstruct roadway including new curb and gutter, sidewalk, storm drainage improvements, hot mix asphalt, street lighting, and pavement markings.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 STP(US) 292,690 0 45,680 338,370

PE 2019 TAP(US) 21,232 0 3,314 24,546

Project Totals 313,922 0 48,994 362,916

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 362,916 0 0 0 0 Totals 362,916 0 0 0 0

Federal Funds State Funds Local Funds Total Agency Totals for Prosser 313,922 0 48,994 362,916

Page 58 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 01 508202G 508202G03 40 0.240 CE No 132.36 132.60 29,455,726 I-82/Columbia River Bridge at Umatilla EB - Bridge Painting Paint Bridge 82/280S. The existing steel surfaces are in need of cleaning and painting to preserve the structural integrity of this bridge south of Kennewick. By cleaning and painting the steel surfaces this project will preserve the bridge and maintain the safety of the highway. This project is split between Washington and Oregon.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 NHPP 267,600 0 11,150 278,750

PE 2019 0 0 278,750 278,750

CN 2020 0 CWA 14,449,113 0 14,449,113

CN 2020 0 0 14,449,113 14,449,113

Project Totals 267,600 14,449,113 14,739,013 29,455,726

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 92,725 456,660 9,901,334 9,189,631 9,815,377 Totals 92,725 456,660 9,901,334 9,189,631 9,815,377

Page 59 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 01 508210R 508210R03 14 0.240 CE No 132.36 132.60 15,186,032 I-82/Columbia River Bridge WB - Deck Rehabilitation Scarify and overlay bridge deck on Bridge 82/280N. The bridge deck on the westbound I-82 Columbia River Bridge at the WA/OR state boundary is showing signs of deterioration due to normal wear and age. This project will repair and resurface the existing bridge to maintain structural integrity, continue safe operation of the highway, and extend the life of the bridge. This project is split between Washington and Oregon.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 0 0 301,950 301,950

PE 2021 NHPP 289,872 0 12,078 301,950

CN 2022 NHPP 7,145,245 0 145,821 7,291,066

CN 2022 0 0 7,291,066 7,291,066

Project Totals 7,435,117 0 7,750,915 15,186,032

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 221,773 393,453 14,459,876 Totals 0 0 221,773 393,453 14,459,876

Page 60 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 01 508209V 508209V03 21 3.630 CE No 88.51 92.14 942,515 I-82/Gibbon Rd Vic to 1 Mile W of Yakitat Rd - Median Cable Barrier Upgrade existing cable barrier. The existing 3-strand median cable barrier along this section of I-82 east of Prosser no longer meets current design standards. This project will replace the existing barrier with 4-strand high tension cable barrier to further reduce the risk of collisions.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2019 HSIP 122,473 0 5,103 127,576

CN 2020 NHPP 798,640 0 16,299 814,939

Project Totals 921,113 0 21,402 942,515

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 27,129 100,447 784,526 30,413 0 Totals 27,129 100,447 784,526 30,413 0

Page 61 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 01 508211A 508211A03 21 0.800 CE No 131.08 131.88 15,088,500 I-82/SR 14 Interchange - Plymouth Weigh Station Improvements Construct new weigh station. The existing weigh station on SR 14 near Plymouth is aging due to normal wear and tear and does not have adequate facilities for truck inspections and parking. This project will construct a new larger weigh station near the I-82/SR 14 interchange to provide adequate inspection and parking facilities, and install Virtual Weigh-in-Motion systems on I-82 and SR 14.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2020 NHPP 1,042,560 0 43,440 1,086,000

RW 2021 NHPP 1,714,020 0 34,980 1,749,000

CN 2022 NHPP 12,008,430 0 245,070 12,253,500

Project Totals 14,765,010 0 323,490 15,088,500

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 209,516 809,155 1,605,120 12,442,196 Totals 0 209,516 809,155 1,605,120 12,442,196

Page 62 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 06 522102E 522102E03 21 5.000 CE No 1.00 6.00 358,720 SR 221/Paterson Vicinity - Install Weigh-in-Motion Install virtual weigh-in-motion system. SR 221 is frequently used by large trucks entering the Yakima Valley. This project will install a virtual weign-in-motion system.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 0 0 293,720 293,720

Project Totals 0 0 293,720 293,720

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 293,720 0 0 0 0 Totals 293,720 0 0 0 0

Page 63 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 02 502405S 502405S03 40 0.380 CE No 43.60 43.98 3,767,564 SR 24/Columbia River Vernita Bridge - Bridge Painting Paint Bridge 024/105. The existing steel surfaces are in need of cleaning and painting to preserve the structural integrity of the bridge on the Benton/Grant County Line. By cleaning and painting the steel surfaces this project will preserve the bridge and maintain the safety of the highway.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total PE 2021 STP 338,116 0 14,088 352,204

Project Totals 338,116 0 14,088 352,204

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 29,331 252,719 3,476,117 Totals 0 0 29,331 252,719 3,476,117

Page 64 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 06 502402T 502402T03 21 4.850 CE No 38.74 43.59 47,489 SR 24/SR 240 to Vernita - Shoulder and Centerline Rumble Strips Install shoulder and centerline rumble strips. This two lane section of SR 24 has a history of run-off-road and crossover collisions. This project will install shoulder and centerline rumble strips to reduce the risk of collisions.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2021 HSIP 40,363 0 823 41,186

Project Totals 40,363 0 823 41,186

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 41,186 0 0 Totals 0 0 41,186 0 0

Page 65 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 06 502402W 502402W03 21 0.200 CE No 43.24 43.44 73,099 SR 24/Vernita Weigh Station - Preservation Rehab/replace weigh station scale approaches. The existing scale approaches at the Vernita weigh station are deteriorated and in need of repair. This project will rehabilitate or replace the approaches to preserve the weigh station.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 STP 61,681 0 1,259 62,940

Project Totals 61,681 0 1,259 62,940

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 62,940 0 0 0 0 Totals 62,940 0 0 0 0

Page 66 Washington State S. T. I. P.

2019 to 2022 (Project Funds to Nearest Dollar) MPO/RTPO: BFCG N Inside Y Outside August 29, 2018 County: Agency: WSDOT - SC

Total Project Total Est. STIP Func Project Imp Length Environmental RW Begin End Cost of Amend. Cls Number PIN STIP ID Type Type Required Termini Termini Project No. 02 539504P 539504P03 21 36.840 CE Yes 24.40 61.24 15,000,000 US 395/Safety Corridor Improvements Intersection improvements. US 395 between Pasco and Ritzville is a critical freight corridor. This project will add acceleration and deceleration lanes, improve existing left turn lanes, and construct safety improvements between between Pasco and the Franklin county line north of Connell to reduce congestion and the risk of collisions.

Funding Federal Funds Phase Start Date Federal Fund Code State Fund Code State Funds Local Funds Total CN 2019 0 CWA 14,445,815 0 14,445,815

Project Totals 0 14,445,815 0 14,445,815

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 14,295,815 150,000 0 0 0 Totals 14,295,815 150,000 0 0 0

Federal Funds State Funds Local Funds Total Agency Totals for WSDOT - SC 23,829,000 28,894,928 23,144,710 75,868,638

Page 67 Appendix D - Planned Projects 2019-2024

A81 2019-2024 TIP Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton City County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 2 BC-000010 06/17/14 04 0.300 CE No 8th Street * Della Sidewalks, Curb & Gutters 8th Street/Della Ave. Dale Avenue to Della/ 8th & 9th Remove existing deteriorated sidewalk, construct new curb and sidewalk with ADA ramps, pave between new sidewalk and add storm drainage

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2019 0 TIB 189,000 21,000 210,000 Totals 0 189,000 21,000 210,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 210,000 0 0 0 0 Totals 210,000 0 0 0 0

Report Date: August 29, 2018 Page 1 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton City County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 3 BC-000014 01 0.150 No Edith Avenue Construction Project Edith Della Avenue to 13th Street Construct Edith Avenue to connect existing roadway with 13th street

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2019 0 0 330,000 330,000 Totals 0 0 330,000 330,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 330,000 0 0 0 0 Totals 330,000 0 0 0 0

Report Date: August 29, 2018 Page 2 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton City County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 5 BC-000005 06/19/12 06/19/12 2012-22 05 0.140 CE No 6th Street Overlay Project 6th Street Babs Avenue to Belle Avenue Pavement Overlay and Striping

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2019 0 0 28,000 28,000 Totals 0 0 28,000 28,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 28,000 0 0 0 0 Totals 28,000 0 0 0 0

Report Date: August 29, 2018 Page 3 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton City County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 6 BC-000016 04 0.140 CE No Sun Valley Way Roads Project Sun Valley Way- Aspen Court - Birch Court 9th Street to Capri Court Total Reconstruction (road only with compaction of settlement areas, drainage repairs & total repaving

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 TIB 59,850 3,150 63,000 P CN 2024 0 TIB 273,600 14,400 288,000 Totals 0 333,450 17,550 351,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 63,000 CN 0 0 0 0 288,000 Totals 0 0 0 0 351,000

Report Date: August 29, 2018 Page 4 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton City County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 7 BC-000002 06/19/12 06/19/12 2012-22 05 0.240 CE No 12th Street Overlay Project 12th Street Corral Creek Road to 350' South of Neptune Pavement Overlay

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2019 0 OTHER 35,000 13,000 48,000 Totals 0 35,000 13,000 48,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 48,000 0 0 0 0 Totals 48,000 0 0 0 0

Report Date: August 29, 2018 Page 5 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton City County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 10 BC-000015 05 CE No Carol/Cora/Irma Double Shot Road Surface Carol, Cora, Irma to Double Shot surface - 20' wide

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2020 0 0 60,000 60,000 Totals 0 0 60,000 60,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 60,000 0 0 0 Totals 0 60,000 0 0 0

Federal Funds State Funds Local Funds Total Funds Grand Totals for Benton City 0 557,450 469,550 1,027,000

Report Date: August 29, 2018 Page 6 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 3 BCO2014-03 07/02/13 07/02/13 2013 519 01 C G P T 0.700 CE Yes WILLAMETTE HEIGHTS S. 38th Ave. W. Rich. City Limits to W. Rich. City Limits New construction in the vicinity of the Willamette Heights subdivision, S 38th Ave.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2019 STP(U) 250,000 0 0 250,000 Totals 250,000 0 0 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 250,000 0 0 0 0 Totals 250,000 0 0 0 0

Report Date: August 29, 2018 Page 7 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 5 WA-10229 07/10/18 07/17/18 2018-468 01 P T 1.100 EA Yes ADAIR ROAD 44830 1.484 to 2.584 The proposed project would build approximately 1.1 miles of new roadway from the current northern end of Adair Road to Christensen Road. The surface will be hot-mix asphalt.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2022 0 0 755,000 755,000 Totals 0 0 755,000 755,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 0 0 0 755,000 0 Totals 0 0 0 755,000 0

Report Date: August 29, 2018 Page 8 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 11 BCO2016-01 07/10/18 07/17/18 01 C G P T 0.500 CE Yes DAGUE RD Dague Rd Terril Rd to Game Farm Rd Proposed new roadway to be built to an all weather standard.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2022 0 0 250,000 250,000 Totals 0 0 250,000 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 250,000 0 Totals 0 0 0 250,000 0

Federal Funds State Funds Local Funds Total Funds Grand Totals for Benton Co. 250,000 0 1,005,000 1,255,000

Report Date: August 29, 2018 Page 9 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 14 WA-09037 06/26/18 06/26/18 2018-205 04 P T W 3.460 CE No Taylor Flats Overlay and Widening I 09030 0.0 Clark Road to 3.46 Taylor Flats Bridge Reconstruct and resurface to an all-weather standard.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2020 0 CRAB 2,000,000 200,000 2,200,000 Totals 0 2,000,000 200,000 2,200,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 50,000 2,150,000 0 0 Totals 0 50,000 2,150,000 0 0

Report Date: August 29, 2018 Page 10 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 22 WA-01011 06/26/18 06/26/18 2018-205 18 CE No Dent Road and Burns Road Corridor Study

to A study for transportation needs along the Dent Road and Burns Road corridor.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2021 0 0 75,000 75,000 Totals 0 0 75,000 75,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 75,000 0 0 Totals 0 0 75,000 0 0

Report Date: August 29, 2018 Page 11 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 29 WA-06282 06/26/18 06/26/18 2018-205 04 P T W 1.040 CE No Dent Road Widening 10050 MP 2.19 to Burns Road Widen existing county road to accommodate additional traffic from recent development.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 68,000 68,000 P CN 2022 0 0 507,000 507,000 Totals 0 0 575,000 575,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 68,000 0 CN 0 0 0 507,000 0 Totals 0 0 0 575,000 0

Report Date: August 29, 2018 Page 12 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 30 WA-01308 06/26/18 06/26/18 2018-205 04 P T W CE Yes Dent Road/Road 68/Taylor Flats Road/Clark Road Intersection Various Roads Intersection Project to Intersection Project Re-design and construct a new intersection for all five (5) legs.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2022 0 0 1,000,000 1,000,000 Totals 0 0 1,000,000 1,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 1,000,000 0 Totals 0 0 0 1,000,000 0

Federal Funds State Funds Local Funds Total Funds Grand Totals for Franklin Co. 0 2,000,000 1,850,000 3,850,000

Report Date: August 29, 2018 Page 13 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 kenn25 06/19/18 06/19/18 18-15 04 C G O P S 0.440 CE Yes T W 10th Avenue Reconstruction 10th Avenue Clearwater Avenue to Steptoe Street (Clodfelter) Reconstruct to 3-lane road with curb, gutter, sidewalk, storm drainage and illumination. Widen Clearwater for left turn storage. Roundabout or Traffic Signal @ Clearwater & 10th Avenue.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 320,000 320,000 P CN 2021 0 0 3,520,000 3,520,000 Totals 0 0 3,840,000 3,840,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 320,000 0 0 0 CN 0 0 3,520,000 0 0 Totals 0 320,000 3,520,000 0 0

Report Date: August 29, 2018 Page 14 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 kenn68 06/19/18 06/19/18 18-15 04 C G O P S 0.100 CE Yes T W 10th Avenue/Morain Street Intersection

to Construct traffic signal

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 50,000 50,000 P CN 2022 0 0 530,000 530,000 Totals 0 0 580,000 580,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 50,000 0 0 CN 0 0 0 530,000 0 Totals 0 0 50,000 530,000 0

Report Date: August 29, 2018 Page 15 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 kenn69 06/19/18 06/19/18 18-15 03 C G O P S 0.100 CE Yes T W 27th Avenue/Southridge Intersection 27th Avenue to Construct northbound right turn slip lane at roundabout.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 40,000 40,000 P RW 2023 0 0 60,000 60,000 P CN 2024 0 0 400,000 400,000 Totals 0 0 500,000 500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 40,000 RW 0 0 0 0 60,000 CN 0 0 0 0 400,000 Totals 0 0 0 0 500,000

Report Date: August 29, 2018 Page 16 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 kenn38 06/19/18 06/19/18 18-15 04 C G O P S 1.000 DCE Yes T W 45th Avenue Widening

Ely Street to Olympia Street Reconstruct 2/3 lane road with curb, gutter, sidewalks, storm drainage, illumination, replace AC water lines.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 180,000 180,000 P RW 2023 0 0 70,000 70,000 P CN 2024 0 0 1,980,000 1,980,000 Totals 0 0 2,230,000 2,230,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 180,000 RW 0 0 0 0 70,000 CN 0 0 0 0 1,980,000 Totals 0 0 0 0 2,230,000

Report Date: August 29, 2018 Page 17 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 Kenn62 06/19/18 06/19/18 18-15 21 C G O P S 0.100 CE No T W Amistad Elementary School Crossing Improvements Kennewick Avenue S. Kent Street to Intersection project Install Rectangular Rapid Flash Beacon and associated signage across Kennewick Avenue.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 SRTS 8,000 0 8,000 P CN 2020 0 SRTS 77,000 0 77,000 Totals 0 85,000 0 85,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 8,000 0 0 0 0 CN 0 77,000 0 0 0 Totals 8,000 77,000 0 0 0

Report Date: August 29, 2018 Page 18 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 kenn50 06/19/18 06/19/18 18-15 21 C G P S T 0.240 DCE Yes W Canal Drive & Edison Street Intersection Improvements Canal Drive Intersection Canal Dr. to and Edison Street Construct second eastbound left turn lane (Widen both east and west legs). Reconstruct accesses, sidewalk, frontage improvements, signal modification.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 138,000 138,000 P RW 2022 0 0 150,000 150,000 P CN 2023 0 0 1,137,000 1,137,000 Totals 0 0 1,425,000 1,425,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 138,000 0 RW 0 0 0 150,000 0 CN 0 0 0 0 1,137,000 Totals 0 0 0 288,000 1,137,000

Report Date: August 29, 2018 Page 19 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 kenn16 06/19/18 06/19/18 18-15 28 O 0.550 CE No Canal Drive Sidewalks Canal Drive US 395 to Hartford Street Construct new sidewalks. Minor widening & curb construction.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 TIB 14,000 4,000 18,000 P CN 2022 0 TIB 186,000 46,000 232,000 Totals 0 200,000 50,000 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 18,000 0 0 CN 0 0 0 232,000 0 Totals 0 0 18,000 232,000 0

Report Date: August 29, 2018 Page 20 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 Kenn61 06/19/18 06/19/18 18-15 21 C G O P S 0.730 DCE Yes T W Cascade Elementary School Sidewalk

Lyle Street to Cascade Street Construct approximately 3,700 linear feet of new curb, gutter and sidewalk from Lyle Street to Cascade Street. Project includes a crossing of Highland Drive with a pedestrian activated Rectangular Rapid Flash Beacon (RRFB).

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 SRTS 40,000 0 40,000 P RW 2021 0 SRTS 400,000 0 400,000 P CN 2022 0 SRTS 360,000 80,000 440,000 Totals 0 800,000 80,000 880,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 40,000 0 0 0 RW 0 0 400,000 0 0 CN 0 0 0 440,000 0 Totals 0 40,000 400,000 440,000 0

Report Date: August 29, 2018 Page 21 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 kenn12 06/19/18 06/19/18 18-15 01 C G P S T 0.240 CE Yes W Cascade Street

W. 45th Avenue to S. Highland Drive Construct new 3-lane collector road with curb, gutter, sidewalk, storm drainage, canal crossing and illumination.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 205,000 205,000 P RW 2023 0 0 150,000 150,000 P CN 2024 0 0 2,255,000 2,255,000 Totals 0 0 2,610,000 2,610,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 205,000 RW 0 0 0 0 150,000 CN 0 0 0 0 2,255,000 Totals 0 0 0 0 2,610,000

Report Date: August 29, 2018 Page 22 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 kenn24 06/19/18 06/19/18 18-15 21 C G O P S 0.100 CE Yes T W Center Parkway & Deschutes Ave. Roundabout

Center Parkway to Deschutes Avenue Construct small diameter roundabout

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 90,000 90,000 P RW 2020 0 0 40,000 40,000 P CN 2021 0 0 900,000 900,000 Totals 0 0 1,030,000 1,030,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 90,000 0 0 0 RW 0 40,000 0 0 0 CN 0 0 900,000 0 0 Totals 0 130,000 900,000 0 0

Report Date: August 29, 2018 Page 23 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 kenn47 06/19/18 06/19/18 18-15 04 C G P T W 0.100 DCE No Clearwater Avenue - Utah Street Intersection Improvement

Intersection Clearwater to and Utah Street Construct eastbound and westbound right turn lanes

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 44,000 44,000 P RW 2021 0 0 40,000 40,000 P CN 2022 0 0 440,000 440,000 Totals 0 0 524,000 524,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 44,000 0 0 RW 0 0 40,000 0 0 CN 0 0 0 440,000 0 Totals 0 0 84,000 440,000 0

Report Date: August 29, 2018 Page 24 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 kenn55 06/19/18 06/19/18 18-15 04 C G O P S 0.100 CE Yes T W Clearwater/Kellogg Intersection Improvements

intersection to intersection Construct second southbound left turn lane. Signal modifications.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 93,000 93,000 P RW 2021 0 0 107,000 107,000 P CN 2022 0 0 930,000 930,000 Totals 0 0 1,130,000 1,130,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 93,000 0 0 RW 0 0 107,000 0 0 CN 0 0 0 930,000 0 Totals 0 0 200,000 930,000 0

Report Date: August 29, 2018 Page 25 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 kenn70 06/19/18 06/19/18 18-15 01 C G O P S 1.000 EA Yes T W Colorado Street Construction- Ridgeline to Bob Olson Parkway

Ridgeline Drive to Bob Olson Parkway Construct new 3-lane collector road with curb, gutter, sidewalk, storm drainage and illumination.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 0 165,000 165,000 P RW 2019 0 0 435,000 435,000 P CN 2020 0 0 1,815,000 1,815,000 Totals 0 0 2,415,000 2,415,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 165,000 0 0 0 0 RW 435,000 0 0 0 0 CN 0 1,815,000 0 0 0 Totals 600,000 1,815,000 0 0 0

Report Date: August 29, 2018 Page 26 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 WA-07765 06/19/18 06/19/18 18-15 03 C G O P S 0.750 CE Yes T W Columbia Center Boulevard Widening

Quinault Avenue to Deschutes Avenue Construct new 3rd northbound and southbound through lanes, curb, gutter, sidewalk, kenn18 storm drainage, illumination, signal modifications. At Quinault, construct 2nd eastbound lane.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 732,000 732,000 P RW 2023 0 0 700,000 700,000 P CN 2024 0 0 7,325,000 7,325,000 Totals 0 0 8,757,000 8,757,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 732,000 0 RW 0 0 0 0 700,000 CN 0 0 0 0 7,325,000 Totals 0 0 0 732,000 8,025,000

Report Date: August 29, 2018 Page 27 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 kenn14 06/19/18 06/19/18 18-15 31 O 1.500 CE No Columbia Overlook - Phase 2 Canal Drive Neel Street to US 395 Install concrete sidewalk on north side of roadway. Irrigation system installation and landscaped linear park. Requires agreement with BNSF Railway.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 76,000 76,000 P CN 2024 TAP(UL) 598,580 0 93,420 692,000 Totals 598,580 0 169,420 768,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 76,000 CN 0 0 0 0 692,000 Totals 0 0 0 0 768,000

Report Date: August 29, 2018 Page 28 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 kenn71 06/19/18 06/19/18 18-15 03 C G O P S 0.100 CE Yes T W Deschutes/Columbia Center Boulevard Intersection

to Construct westbound right turn lane.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 40,000 40,000 P RW 2020 0 0 100,000 100,000 P CN 2021 0 0 400,000 400,000 Totals 0 0 540,000 540,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 40,000 0 0 0 RW 0 100,000 0 0 0 CN 0 0 400,000 0 0 Totals 0 140,000 400,000 0 0

Report Date: August 29, 2018 Page 29 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 kenn17 06/19/18 06/19/18 18-15 28 O 0.200 CE No E. 10th Avenue Sidewalks E. 10th Avenue SR 397 to Oak Street Construct new sidewalks to fill in gap, including over railroad tracks.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2019 0 0 250,000 250,000 Totals 0 0 250,000 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 250,000 0 0 0 0 Totals 250,000 0 0 0 0

Report Date: August 29, 2018 Page 30 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 Kenn63 06/19/18 06/19/18 18-15 28 C G O P S 0.360 DCE No T W East Columbia Park Bicycle Improvements – Phase 2 Columbia Park Trail SR240 entrance to 1900 feet west Construct pavement widening for dedicated bicycle lanes, including permanent pavement markings and signage.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 Ped/Bike Program 25,000 3,000 28,000 P CN 2020 0 Ped/Bike Program 181,800 18,200 200,000 Totals 0 206,800 21,200 228,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 28,000 0 0 0 0 CN 0 200,000 0 0 0 Totals 28,000 200,000 0 0 0

Report Date: August 29, 2018 Page 31 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 Kenn60 06/19/18 06/19/18 18-15 21 C G O P S 0.080 CE No T W Hawthorne Elementary School Crossing Improvements Neel Street John Day Avenue to 400 feet north Construct a new crossing at the intersection of Neel & John Day, construct a median refuge at the existing crossing at mid-block, extend the school zone on Neel Street to encompass both crosswalks, install RRFB at both crossings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 Ped/Bike Program 16,000 0 16,000 P CN 2020 0 Ped/Bike Program 158,000 0 158,000 Totals 0 174,000 0 174,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 16,000 0 0 0 0 CN 0 158,000 0 0 0 Totals 16,000 158,000 0 0 0

Report Date: August 29, 2018 Page 32 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 kenn72 06/19/18 06/19/18 18-15 04 C G O P S 0.100 CE Yes T W Kellogg Street / Metaline Avenue Intersection

to Construct traffic signal.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 40,000 40,000 P RW 2021 0 0 20,000 20,000 P CN 2022 0 0 450,000 450,000 Totals 0 0 510,000 510,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 40,000 0 0 RW 0 0 20,000 0 0 CN 0 0 0 450,000 0 Totals 0 0 60,000 450,000 0

Report Date: August 29, 2018 Page 33 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 kenn73 06/19/18 06/19/18 18-15 04 C G O P S 0.100 CE No T W Kennewick Avenue / Yelm Street Intersection

to Upgrade traffic signal poles and equipment

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 30,000 30,000 P CN 2021 0 0 300,000 300,000 Totals 0 0 330,000 330,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 30,000 0 0 0 CN 0 0 300,000 0 0 Totals 0 30,000 300,000 0 0

Report Date: August 29, 2018 Page 34 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 kenn41 06/19/18 06/19/18 18-15 04 C G O P S 1.090 DCE Yes T W Montana Street Extension

Bob Olson Parkway to Ridgeline Drive Construct new 3-lane collector road with curb, gutter, sidewalk, storm drainage and illumination.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 100,000 100,000 P RW 2022 0 0 264,000 264,000 P CN 2023 0 0 1,100,000 1,100,000 Totals 0 0 1,464,000 1,464,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 100,000 0 0 RW 0 0 0 264,000 0 CN 0 0 0 0 1,100,000 Totals 0 0 100,000 264,000 1,100,000

Report Date: August 29, 2018 Page 35 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 kenn80 06/19/18 06/19/18 18-15 05 C G O P S CE No T W Pavement Preservation (Capital) City-wide

to Pavement infrastructure preservation capital projects for arterials, collectors and local residential streets

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2019 0 0 2,000,000 2,000,000 P CN 2020 0 0 2,000,000 2,000,000 P CN 2021 0 0 2,000,000 2,000,000 P CN 2022 0 0 2,000,000 2,000,000 P CN 2023 0 0 2,000,000 2,000,000 P CN 2024 0 0 2,000,000 2,000,000 Totals 0 0 12,000,000 12,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 2,000,000 2,000,000 2,000,000 2,000,000 4,000,000 Totals 2,000,000 2,000,000 2,000,000 2,000,000 4,000,000

Report Date: August 29, 2018 Page 36 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 kenn28 06/19/18 06/19/18 18-15 04 C G O P S 1.250 DCE Yes W Ridgeline Drive Extension Phase 3

Center Parkway to Sherman Street Construct new 3-lane collector road with curb, gutter, sidewalk, storm drainage and illumination.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 280,000 280,000 P RW 2022 0 0 220,000 220,000 P CN 2023 0 0 3,086,000 3,086,000 Totals 0 0 3,586,000 3,586,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 280,000 0 RW 0 0 0 220,000 0 CN 0 0 0 0 3,086,000 Totals 0 0 0 500,000 3,086,000

Report Date: August 29, 2018 Page 37 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 kenn32 06/19/18 06/19/18 18-15 03 C G O P S 0.530 DCE Yes T W Ridgeline Drive Reconstruction

Sherman St. to Southridge. Construct 3-lane road with curb, gutter, sidewalks, illumination, intersection control.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 80,000 80,000 P RW 2021 0 0 50,000 50,000 P CN 2022 0 0 878,000 878,000 Totals 0 0 1,008,000 1,008,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 80,000 0 0 RW 0 0 50,000 0 0 CN 0 0 0 878,000 0 Totals 0 0 130,000 878,000 0

Report Date: August 29, 2018 Page 38 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 kenn29 06/19/18 06/19/18 18-15 04 C G O P S 0.300 DCE No W Sherman Street

Ridgeline Drive to Bob Olson Parkway Construct 3 lane road with curb, gutter, sidewalks, illumination, intersection control.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 75,000 75,000 P CN 2021 0 0 825,000 825,000 Totals 0 0 900,000 900,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 75,000 0 0 0 CN 0 0 825,000 0 0 Totals 0 75,000 825,000 0 0

Report Date: August 29, 2018 Page 39 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 kenn82 06/19/18 06/19/18 18-15 28 C G O P S CE No T W Sidewalk Renewals/Replacements/ADA Citywide

to Repair/replace/construct sidewalk in areas of tripping hazards, damaged sidewalk, missing sidewalk, substandard or missing ADA ramps.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2019 0 0 125,000 125,000 P CN 2020 0 0 125,000 125,000 P CN 2021 0 0 125,000 125,000 P CN 2022 0 0 125,000 125,000 P CN 2023 0 0 125,000 125,000 P CN 2024 0 0 125,000 125,000 Totals 0 0 750,000 750,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 125,000 125,000 125,000 125,000 250,000 Totals 125,000 125,000 125,000 125,000 250,000

Report Date: August 29, 2018 Page 40 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 Kenn64 06/19/18 06/19/18 18-15 28 C G O P S 0.620 DCE No T W Spirit of America Trail – 15th to 27th Spirit of America Trail 15th Avenue to 27th Avenue The project will construct a 12-foot wide shared use (ped/bike) facility. The project includes paving the staging/parking area at the south termini, pavement markings and signage.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 Ped/Bike Program 45,000 5,000 50,000 P CN 2020 0 Ped/Bike Program 180,000 20,000 200,000 Totals 0 225,000 25,000 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 50,000 0 0 0 0 CN 0 200,000 0 0 0 Totals 50,000 200,000 0 0 0

Report Date: August 29, 2018 Page 41 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 Kenn65 06/19/18 06/19/18 18-15 28 C G O P S 0.960 CE Yes T W Steptoe Blvd. to Columbia Center Blvd. Pathway

Steptoe Blvd. to Columbia Center Blvd. Construct pathway along abandoned rail line.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 Ped/Bike Program 30,000 0 30,000 Totals 0 30,000 0 30,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 30,000 0 Totals 0 0 0 30,000 0

Report Date: August 29, 2018 Page 42 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 kenn74 06/19/18 06/19/18 18-15 03 C G O P T 0.100 CE No W Steptoe Street / Gage Boulevard Intersection

to Construct double left turn lanes and single right turn lanes at all approaches (where not existing). Eliminate split phase timing.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 230,000 230,000 P CN 2021 0 0 2,080,000 2,080,000 Totals 0 0 2,310,000 2,310,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 230,000 0 0 0 CN 0 0 2,080,000 0 0 Totals 0 230,000 2,080,000 0 0

Report Date: August 29, 2018 Page 43 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 kenn81 06/19/18 06/19/18 18-15 24 CE No Traffic Signal System Upgrades / Re-timing City-Wide

to New signal system equipment, software, communications, re-timing and modifications

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2019 0 0 170,000 170,000 P CN 2020 0 0 170,000 170,000 P CN 2021 0 0 170,000 170,000 P CN 2022 0 0 170,000 170,000 P CN 2023 0 0 170,000 170,000 P CN 2024 0 0 170,000 170,000 Totals 0 0 1,020,000 1,020,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 170,000 170,000 170,000 170,000 340,000 Totals 170,000 170,000 170,000 170,000 340,000

Report Date: August 29, 2018 Page 44 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 12 kenn77 06/19/18 06/19/18 18-15 03 C G O P S 0.100 CE No T W US395 / 10th Avenue Intersection

to Construct southbound dual left turn lanes

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 100,000 100,000 P CN 2023 0 0 960,000 960,000 Totals 0 0 1,060,000 1,060,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 100,000 0 CN 0 0 0 0 960,000 Totals 0 0 0 100,000 960,000

Report Date: August 29, 2018 Page 45 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 kenn78 06/19/18 06/19/18 18-15 03 C G O P S 0.100 CE No T W US395 / Clearwater Avenue Intersection

to Construct dual eastbound left turn lanes, dual northbound left turn lanes, eastbound and westbound right turn lanes.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2024 0 0 250,000 250,000 Totals 0 0 250,000 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 250,000 Totals 0 0 0 0 250,000

Report Date: August 29, 2018 Page 46 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 12 kenn79 06/19/18 06/19/18 18-15 03 C G O P S 0.100 CE No T W US395 / Hildebrand Intersection

to Construct northbound and southbound dual left turn lanes, channelize eastbound and westbound dual left turn lanes, construct eastbound and westbound right turn lanes.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2020 0 0 300,000 300,000 Totals 0 0 300,000 300,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 0 300,000 0 0 0 Totals 0 300,000 0 0 0

Report Date: August 29, 2018 Page 47 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 12 / 3457(002) kenn6 06/19/18 06/19/18 18-15 04 C G P S T 0.250 CE Yes W US395/Ridgeline Drive Interchange

Ridgeline Drive to US395 Intersection Construction of a grade separated intersection at US395 and Ridgeline Drive, and associated vicinity improvements. Construction will be done by WSDOT and is programmed under STIP # 539504003.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P RW 2019 0 0 3,700,000 3,700,000 S CN 2020 NHFP 1,944,259 0 0 1,944,259 Totals 1,944,259 0 3,700,000 5,644,259

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th RW 3,700,000 0 0 0 0 CN 0 1,944,259 0 0 0 Totals 3,700,000 1,944,259 0 0 0

Report Date: August 29, 2018 Page 48 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 Kenn31 06/19/18 06/19/18 18-15 21 C G O P S 0.100 CE No T W Washington Elementary School Crossing Improvements at W. 21st Ave.

Intersection to Intersection Install rectangular rapid flash beacon and associated signage and channelization

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 SRTS 5,000 0 5,000 P CN 2020 0 SRTS 45,000 0 45,000 Totals 0 50,000 0 50,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 5,000 0 0 0 0 CN 0 45,000 0 0 0 Totals 5,000 45,000 0 0 0

Report Date: August 29, 2018 Page 49 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 kenn75 06/19/18 06/19/18 18-15 04 C G O P S 0.310 CE Yes T W Washington Street -Complete Streets, 1st Avenue - Columbia Drive. Washington 1st Avenue to Columbia Drive Connect the wine village area with downtown, including sidewalks, benches, landscaping, railroad crossings, street lighting, and road widening/diet options

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 TIB 50,000 0 50,000 P RW 2019 0 TIB 50,000 0 50,000 P CN 2020 0 TIB 500,000 0 500,000 Totals 0 600,000 0 600,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 50,000 0 0 0 0 RW 50,000 0 0 0 0 CN 0 500,000 0 0 0 Totals 100,000 500,000 0 0 0

Report Date: August 29, 2018 Page 50 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 kenn76 06/19/18 06/19/18 18-15 03 C G O P S 0.100 CE No T W Washington Street / Columbia Drive Intersection

to Construct eastbound right turn lane

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 0 50,000 50,000 P CN 2020 0 0 530,000 530,000 Totals 0 0 580,000 580,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 50,000 0 0 0 0 CN 0 530,000 0 0 0 Totals 50,000 530,000 0 0 0

Report Date: August 29, 2018 Page 51 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 kenn83 06/19/18 06/19/18 18-15 03 C G O P S 0.200 CE No T W West 36th Ave. Sidewalk West 36th Ave. S. Vancouver to S. Sharron Street Construct sidewalk on north side of street, minor roadway widening, storm drainage, street lighting and ADA ramps.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 SRTS 20,000 0 20,000 P CN 2020 0 SRTS 226,000 0 226,000 Totals 0 246,000 0 246,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 20,000 0 0 0 0 CN 0 226,000 0 0 0 Totals 20,000 226,000 0 0 0

Report Date: August 29, 2018 Page 52 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Kennewick County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 kenn4 06/19/18 06/19/18 18-15 01 C P S T W 1.000 CE Yes Zintel Way/Ridgeline Drive/Bofer Canyon

Zintel Way to US 395 Construct remaining Zintel Way to 3-lane urban street and realign Bofer Canyon per US395/Ridgeline interchange project. Right-of-way by developer donation.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2020 0 0 1,100,000 1,100,000 Totals 0 0 1,100,000 1,100,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 0 1,100,000 0 0 0 Totals 0 1,100,000 0 0 0

Federal Funds State Funds Local Funds Total Funds Grand Totals for Kennewick 2,542,839 2,616,800 57,044,620 62,204,259

Report Date: August 29, 2018 Page 53 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 WA-08131 06/18/18 06/18/18 05 No Annual Pavement Preservation Program various locations various to various This program includes all pavement preservation activities such as crack seal, rubberized chip seal, overlays and micro-surfacing throughout the city.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2019 0 0 750,000 750,000 P CN 2020 0 0 750,000 750,000 P CN 2021 0 0 750,000 750,000 P CN 2022 0 0 750,000 750,000 P CN 2023 0 0 750,000 750,000 P CN 2024 0 0 750,000 750,000 Totals 0 0 4,500,000 4,500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 750,000 750,000 750,000 750,000 1,500,000 Totals 750,000 750,000 750,000 750,000 1,500,000

Report Date: August 29, 2018 Page 54 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 WA-08132 06/18/18 06/18/18 01 P S T W 1.000 CE Yes Burns Road (Road 52 to Road 36) Burns Road Road 52 to Road 36 Extension of Burns Road from Road 52 to Road 36.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 250,000 250,000 P RW 2021 0 0 200,000 200,000 Totals 0 0 450,000 450,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 250,000 0 0 RW 0 0 200,000 0 0 Totals 0 0 450,000 0 0

Report Date: August 29, 2018 Page 55 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 WA-08149 06/18/18 06/18/18 01 0.500 Yes Burns Road (Road 68 to Convention Dr) Burns Road Road 68 to Convention Dr Extension of Burns Road from Road 68 to Convention Drive.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 200,000 200,000 Totals 0 0 200,000 200,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 200,000 0 0 0 Totals 0 200,000 0 0 0

Report Date: August 29, 2018 Page 56 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 WA-06311 06/18/18 06/18/18 01 C G O P S 1.000 CE Yes T W Chapel Hill Boulevard Extension Chapel Hill Blvd. Road 84 to Road 68 Extension of Chapel Hill Blvd. from Road 68 to Road 84. The project will include the necessary signal improvements at the intersection of Road 68 and Chapel Hill Blvd.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2019 0 0 4,136,000 4,136,000 Totals 0 0 4,136,000 4,136,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 4,136,000 0 0 0 0 Totals 4,136,000 0 0 0 0

Report Date: August 29, 2018 Page 57 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 02 WA-11221 06/18/18 06/18/18 44 P No Court St & Road 68 Intersection Improvements Court Street Road 68 to Road 68 This project will construct improvements that will address intersection efficiency and improve safety.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 105,000 105,000 P RW 2021 0 0 45,000 45,000 P CN 2022 0 0 700,000 700,000 Totals 0 0 850,000 850,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 105,000 0 0 RW 0 0 45,000 0 0 CN 0 0 0 700,000 0 Totals 0 0 150,000 700,000 0

Report Date: August 29, 2018 Page 58 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 WA-10387 06/18/18 06/18/18 01 0.310 No Crescent Road Crescent Road Road 108 to Chapel Hill Boulevard This project constructs a new road in existing Crescent Road right-of-way, connecting Road 108 to Chapel Hill Boulevard.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 45,000 45,000 P CN 2020 0 0 355,000 355,000 Totals 0 0 400,000 400,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 45,000 0 0 0 CN 0 355,000 0 0 0 Totals 0 400,000 0 0 0

Report Date: August 29, 2018 Page 59 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 WA-10388 06/19/17 06/19/17 06 0.150 No East B Circle Roadway Improvements East B Circle to This project will address poor roadway surface conditions along East B Circle. There have been a number of developments along the road with half street improvements leaving a few frontages as unimproved.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 0 20,000 20,000 P CN 2019 0 0 300,000 300,000 Totals 0 0 320,000 320,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 20,000 0 0 0 0 CN 300,000 0 0 0 0 Totals 320,000 0 0 0 0

Report Date: August 29, 2018 Page 60 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 WA-10396 06/18/18 06/18/18 04 0.380 No James Street Improvements James Street Oregon Avenue to culdesac This project will improve James Street from Oregon Avenue to the east.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 0 48,000 48,000 P CN 2019 0 0 435,000 435,000 Totals 0 0 483,000 483,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 48,000 0 0 0 0 CN 435,000 0 0 0 0 Totals 483,000 0 0 0 0

Report Date: August 29, 2018 Page 61 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 WA-10395 06/18/18 06/18/18 04 0.600 Yes Oregon Avenue (SR 397) Corridor Improvements - Phase 2 Oregon Ave (SR 397) Ainsworth Avenue to 'A' Street This project will upgrade the existing Oregon Avenue corridor between Ainsworth Ave and 'A' Street, widening pavement installing median/curbing in select locations, restriping to create left turn lanes at intersections and two-way left-turn between intersections. Installations of sidewalks, curbe and gutter, ADA ramps, illumination and stormwater infrastructure will also be included.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P RW 2023 0 0 200,000 200,000 P CN 2023 0 0 2,530,000 2,530,000 Totals 0 0 2,730,000 2,730,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th RW 0 0 0 0 200,000 CN 0 0 0 0 2,530,000 Totals 0 0 0 0 2,730,000

Report Date: August 29, 2018 Page 62 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 WA-04364 06/18/18 06/18/18 28 C G O P S 0.100 CE No T W Pedestrian Walkway on Road 68 Overpass Road 68 I-182 to Road 68 This project will widen the existing Road 68 overpass to accommodate a pedestrian walkway.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2024 0 0 250,000 250,000 P CN 2024 STP(UL) 1,000,000 0 0 1,000,000 Totals 1,000,000 0 250,000 1,250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 250,000 CN 0 0 0 0 1,000,000 Totals 0 0 0 0 1,250,000

Report Date: August 29, 2018 Page 63 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 WA-08142 06/18/18 06/18/18 04 0.300 No Pedestrian Walkway on Sylvester Street Overpass Sylvester St 32nd Ave to 28th Ave Provide a pedestrian walkway at the Sylvester Street overpass at US 395 to allow for safe pedestrian crossing.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2024 0 TIB 232,500 67,500 300,000 P CN 2024 HSIP 1,000,000 TIB 200,000 0 1,200,000 Totals 1,000,000 432,500 67,500 1,500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 300,000 CN 0 0 0 0 1,200,000 Totals 0 0 0 0 1,500,000

Report Date: August 29, 2018 Page 64 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 WA-06309 06/18/18 06/18/18 03 C G O P S 1.000 CE Yes T W Road 68 Widening - South of I-182 Road 68 Argent Road to South I-182 Widening Road 68 from Argent to I-182; increasing to two travel lanes in each direction, center turning movement with total of 5 lanes. Sidewalks will be installed on both sides, street lights and landscaping.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 250,000 250,000 P CN 2023 STP(UL) 519,000 0 81,000 600,000 Totals 519,000 0 331,000 850,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 250,000 CN 0 0 0 0 600,000 Totals 0 0 0 0 850,000

Report Date: August 29, 2018 Page 65 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 WA-04362 06/18/18 06/18/18 03 G O P S T 0.050 EA Yes Sandifur Parkway Widening (Convention to Road 68) Sandifur Parkway Convention Drive to Road 68 This project will widen the existing roadway to the equivalent of a five lane section to accommodate future growth and traffic impacts. It will include curb and gutter, sidewalks, illumination and landscaping.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 50,000 50,000 P RW 2022 0 0 35,000 35,000 P CN 2022 STP(UL) 216,250 0 33,750 250,000 Totals 216,250 0 118,750 335,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 50,000 0 RW 0 0 0 35,000 0 CN 0 0 0 250,000 0 Totals 0 0 0 335,000 0

Report Date: August 29, 2018 Page 66 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 8 / 3522(001) WA-01693 06/18/18 06/18/18 03 C G O P S 1.620 CE Yes T W Argent Road Improvements (Rd 44 to 20th Ave) Argent Road Road 44 to 20th Avenue The project consists of widening the existing 3 lane roadway to 5 lanes as part of mobility improvement for this corridor, which will accommodate future traffic needs including Columbia Basin College traffic and commercial development for Port of Pasco. This project also includes intersection improvements for Road 36 and Argent Road, as well as modifications/upgrades to existing traffic signals at Varney Lane/Saraceno Way and 20th Avenue intersections.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 0 811,000 811,000 P RW 2020 0 0 850,000 850,000 P CN 2021 0 0 6,000,000 6,000,000 Totals 0 0 7,661,000 7,661,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 811,000 0 0 0 0 RW 0 850,000 0 0 0 CN 0 0 6,000,000 0 0 Totals 811,000 850,000 6,000,000 0 0

Report Date: August 29, 2018 Page 67 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 15 WA-01699 06/18/18 06/18/18 03 C G O P S 0.750 CE No T W Road 100 Widening Road 100 Chapel Hill to Court Street This project will improve traffic conditions by widening the road from Court Street to Chapel Hill Boulevard.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 STP(UL) 103,800 0 16,200 120,000 P CN 2023 STP(UL) 951,500 0 148,500 1,100,000 Totals 1,055,300 0 164,700 1,220,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 120,000 CN 0 0 0 0 1,100,000 Totals 0 0 0 0 1,220,000

Report Date: August 29, 2018 Page 68 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 16 WA-01700 06/18/18 06/18/18 03 C G O P S 0.500 CE No T W Sandifur Parkway Widening (Rd 60 to Rd 52) Sandifur Parkway Road 60 to Road 52 This project will complete Sandifur Parkway from Road 60 to Road 52 where there is currently a half street. Finishing the roadway will improve safety and provide the same street width for the continuation of Sandifur Parkway.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 50,000 50,000 P CN 2022 STP(UL) 389,250 0 60,750 450,000 Totals 389,250 0 110,750 500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 50,000 0 CN 0 0 0 450,000 0 Totals 0 0 0 500,000 0

Report Date: August 29, 2018 Page 69 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 25 WA-01705 06/18/18 06/18/18 04 C G O P S 1.500 EA No T W Heritage Trail/Levee Lowering Sacagawea Heritage Trail Road 72 to Road 52 This project will lower the levee and install pathways for pedestrians, thus providing access along the river and connecting trails.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 129,000 129,000 P CN 2021 TAP(UL) 600,000 TIB 200,000 50,000 850,000 Totals 600,000 200,000 179,000 979,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 129,000 0 0 CN 0 0 850,000 0 0 Totals 0 0 979,000 0 0

Report Date: August 29, 2018 Page 70 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 33 WA-01710 06/18/18 06/18/18 01 C G O P S 1.250 CE Yes T W Road 76 Overpass - Argent Road to Burden Blvd Road 76 Argent Road to Burden Blvd Extend Road 76 north from Argent Road to Burden Blvd. Extending Road 76 between Argent Road and Burden Blvd will serve as a connector between two arterial roadways near the new Chiawana High School which will lower volumes in the West Pasco area along Argent Road and at the intersection of Argent Road and Road 68 and Road 68 and Burden Blvd.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2024 STP(UL) 432,500 0 1,067,500 1,500,000 P RW 2024 STP(UL) 500,000 0 0 500,000 Totals 932,500 0 1,067,500 2,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 1,500,000 RW 0 0 0 0 500,000 Totals 0 0 0 0 2,000,000

Report Date: August 29, 2018 Page 71 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Pasco County: Franklin MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 41 / 3530(006) WA-01715 06/18/18 06/18/18 03 C G O P S 0.450 EIS Yes T W Lewis Street Overpass Lewis Street Oregon Ave to 2nd Ave Construct a new overpass between 2nd Ave and Oregon Ave. A new overpass will replace the existing underpass which is deteriorating.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S PE 2019 0 CWA 600,000 0 600,000 S CN 2023 0 CWA 13,000,000 2,500,000 15,500,000 P CN 2023 0 0 15,000,000 15,000,000 Totals 0 13,600,000 17,500,000 31,100,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 600,000 0 0 0 0 CN 0 0 0 0 30,500,000 Totals 600,000 0 0 0 30,500,000

Federal Funds State Funds Local Funds Total Funds Grand Totals for Pasco 5,712,300 14,232,500 41,519,200 61,464,000

Report Date: August 29, 2018 Page 72 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 WA-10127 06/13/18 06/13/18 18-12 01 0.570 No Extend Kingsgate Way

to Extend Kingsgate Way north 3,000 LF into the 1,341 acre land transfer area.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 OTHER 1,600,000 500,000 2,100,000 Totals 0 1,600,000 500,000 2,100,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 2,100,000 Totals 0 0 0 0 2,100,000

Report Date: August 29, 2018 Page 73 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 WA-08224 06/13/18 06/13/18 18-12 03 0.300 CE No Improvements to Waterfront Drive, North of University Drive Waterfront Drive to Reconstruct existing Gravel road and add asphalt.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 OTHER 275,000 100,000 375,000 Totals 0 275,000 100,000 375,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 375,000 Totals 0 0 0 0 375,000

Report Date: August 29, 2018 Page 74 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 WA-10128 06/13/18 06/13/18 18-12 01 1.520 EIS No New Industrial Road

to Extend a new industrial road west from Stevens Drive 1.52 miles into the 1,341 acre land transfer area.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 STP(US) 2,600,000 OTHER 2,000,000 1,000,000 5,600,000 Totals 2,600,000 2,000,000 1,000,000 5,600,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 5,600,000 Totals 0 0 0 0 5,600,000

Report Date: August 29, 2018 Page 75 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 WA-05723 06/13/18 06/13/18 18-12 03 0.250 CE No Snyder Road Reconstruction & Rail Road Crossing Snyder Road to Improve existing Roadway and Install Rail Road Crossing

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 OTHER 275,000 100,000 375,000 Totals 0 275,000 100,000 375,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 375,000 Totals 0 0 0 0 375,000

Report Date: August 29, 2018 Page 76 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 4 WA-01843 06/13/18 06/13/18 18-12 01 0.490 CE No Larson Road - Battelle Boulevard To Horn Rapids Larson Road to Construct a two lane Road from Battelle Blvd to Horn Rapids Road approximately 2,640 LF.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 1,850,000 1,850,000 Totals 0 0 1,850,000 1,850,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 1,850,000 Totals 0 0 0 0 1,850,000

Report Date: August 29, 2018 Page 77 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 5 WA-01844 06/13/18 06/13/18 18-12 05 CE No Slurry Seal Project

to Slurry Seal Project, various locations from 1st Street to Horn Rapids Road. Within the Technology and Business Campus.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 100,000 100,000 Totals 0 0 100,000 100,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 100,000 Totals 0 0 0 0 100,000

Report Date: August 29, 2018 Page 78 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 6 WA-01845 06/13/18 06/13/18 18-12 04 CE No Battelle Blvd. Traffic Signal Upgrade

to Battelle Blvd and George Washington Way Traffic Signal Upgrade.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 200,000 200,000 Totals 0 0 200,000 200,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 200,000 Totals 0 0 0 0 200,000

Report Date: August 29, 2018 Page 79 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 7 WA-01846 06/13/18 06/13/18 18-12 01 0.200 CE No Horn Rapids Road Extension Project

to Horn Rapids Road Extension from East end of Horn Rapids Road to 1,000 ft East. Technology & Business Campus.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 700,000 700,000 Totals 0 0 700,000 700,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 700,000 Totals 0 0 0 0 700,000

Report Date: August 29, 2018 Page 80 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 8 WA-01847 06/13/18 06/13/18 18-12 06 1.000 CE No Sidewalk Improvement Project Phase 2

to Sidewalk Improvement Project Assorted within the Technology and Business Campus. Area boundaries George Washington Way, Richardson rd., University Drive, and 11th Street.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 1,060,000 1,060,000 Totals 0 0 1,060,000 1,060,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 1,060,000 Totals 0 0 0 0 1,060,000

Report Date: August 29, 2018 Page 81 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 9 WA-01848 06/13/18 06/13/18 18-12 03 CE No South Richland Rail Transload Facility

to Construction of Transload Facility, including road and rail improvements adjacent to I-182, SR 240, and Jadwin Ave.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 250,000 250,000 Totals 0 0 250,000 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 250,000 Totals 0 0 0 0 250,000

Report Date: August 29, 2018 Page 82 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 11 WA-01851 06/13/18 06/13/18 18-12 03 0.300 CE No Benitz Road

to Reconstruction of Benitz Road from Wine Country Road to Yakima River. Industrial Road. Approximately 1600 LF of Two Lane Roadway

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 250,000 250,000 Totals 0 0 250,000 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 250,000 Totals 0 0 0 0 250,000

Report Date: August 29, 2018 Page 83 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 12 WA-01852 06/13/18 06/13/18 18-12 03 0.470 CE No Lee Road Lee Road to Reconstruction 24' side roadway to 36' wide roadway from Benitz Road to West POB Boundary.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 625,000 625,000 Totals 0 0 625,000 625,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 625,000 Totals 0 0 0 0 625,000

Report Date: August 29, 2018 Page 84 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 13 WA-01853 06/13/18 06/13/18 18-12 03 P S T W 0.380 CE No 1st Street West Project 1st Street to Construct roadway west from Stevens Drive 2000 LF at the intersection of Stevens and University Dr.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 1,400,000 1,400,000 Totals 0 0 1,400,000 1,400,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 1,400,000 Totals 0 0 0 0 1,400,000

Federal Funds State Funds Local Funds Total Funds Grand Totals for Port of Benton 2,600,000 4,150,000 8,135,000 14,885,000

Report Date: August 29, 2018 Page 85 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 4 / 3459(001) R001 06/19/18 06/19/18 01 0.330 CE Yes Center Parkway North Extension Center Parkway Gage Blvd to Tapteal Dr Construct new 3-lane roadway with bike lanes, curb, gutter and sidewalk on both sides. Construct a signalized/gated at-grade crossing of the Port of Benton R/R track.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S CN 2021 0 TIB 219,714 0 219,714 P CN 2021 0 0 1,154,430 1,154,430 Totals 0 219,714 1,154,430 1,374,144

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 0 0 1,374,144 0 0 Totals 0 0 1,374,144 0 0

Report Date: August 29, 2018 Page 86 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 5 R018 06/19/18 06/19/18 28 P W 0.400 CE Yes Vantage Highway Pathway - Phase 2 Snyder Street Robertson Drive to Stevens Drive Construct a new, separated Hot Mix Asphalt multi-use pathway connecting the Vantage Highway Pathway Phase 1 with the Stevens Drive Pathway.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 Ped/Bike Program 47,700 5,300 53,000 P RW 2019 0 Ped/Bike Program 23,850 2,650 26,500 P CN 2020 0 Ped/Bike Program 725,130 80,570 805,700 Totals 0 796,680 88,520 885,200

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 53,000 0 0 0 0 RW 26,500 0 0 0 0 CN 0 805,700 0 0 0 Totals 79,500 805,700 0 0 0

Report Date: August 29, 2018 Page 87 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 6 R031 06/19/18 06/19/18 03 O S W 0.680 CE Yes South George Washington Way Intersection Improvements George Washington Way I-182 to Comstock Street Upgrade and reconfigure George Washington Way(GWW) including the intersections of GWW/Columbia Point Drive/Adams Street and GWW/Comstock Street to provide improved safety, capacity, and mobility. Also includes modifying the WB I-182, NB SR 240, and SB SR 240 ramps to improve safety.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 STP(UL) 141,940 TIB 340,640 85,160 567,740 P RW 2022 STP(UL) 128,750 TIB 77,250 309,000 515,000 P CN 2023 STP(UL) 1,606,500 TIB 3,855,580 963,900 6,425,980 Totals 1,877,190 4,273,470 1,358,060 7,508,720

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 567,740 0 RW 0 0 0 515,000 0 CN 0 0 0 0 6,425,980 Totals 0 0 0 1,082,740 6,425,980

Report Date: August 29, 2018 Page 88 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 7 WA-11158 06/19/18 06/19/18 28 O S W 0.050 CE No South George Washington Way Pedestrian Access & Safety Improvements George Washington Way Aaron Way to Columbia Point Drive Improve pedestrian access an safety crossing George Washington Way by constructing a grade-separated pedestrian crossing.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 206,000 206,000 P CN 2023 0 TIB 257,500 1,390,500 1,648,000 P CN 2023 0 Ped/Bike Program 824,000 0 824,000 Totals 0 1,081,500 1,596,500 2,678,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 206,000 0 CN 0 0 0 0 2,472,000 Totals 0 0 0 206,000 2,472,000

Report Date: August 29, 2018 Page 89 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 12 8 WA-11163 06/19/18 06/19/18 03 O 0.570 CE No SR240/Aaron Intersection Improvements SR240 SR240 EB Ramp to I-182 EB Ramp Construct grade separated eastbound ramp from EB SR240 to EB I-182. Reconstruct existing SR240/Aaron Dr intersection.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 4,000,000 4,000,000 P CN 2024 0 0 36,000,000 36,000,000 Totals 0 0 40,000,000 40,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 4,000,000 CN 0 0 0 0 36,000,000 Totals 0 0 0 0 40,000,000

Report Date: August 29, 2018 Page 90 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 9 WA-11165 06/19/18 06/19/18 21 P S 0.100 CE Yes VanGiesen/Thayer Intersection Improvements VanGiesen St Thayer Dr to Thayer Dr Reconstruct the intersection of VanGiesen Street and Thayer Drive as a single lane roundabout.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 HSIP 47,100 0 5,200 52,300 P RW 2019 HSIP 11,100 0 1,200 12,300 P CN 2020 HSIP 737,600 0 0 737,600 Totals 795,800 0 6,400 802,200

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 52,300 0 0 0 0 RW 12,300 0 0 0 0 CN 0 737,600 0 0 0 Totals 64,600 737,600 0 0 0

Report Date: August 29, 2018 Page 91 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 10 WA-11164 06/19/18 06/19/18 28 O P 0.010 CE No McMurray RFB - Safety Grant McMurray Everest to Everest Installation of a Rapid Flash Beacon and restripe turn lanes to sort traffic and reduce confusion at the intersection.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 HSIP 3,100 0 400 3,500 P CN 2019 HSIP 37,000 0 0 37,000 Totals 40,100 0 400 40,500

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 3,500 0 0 0 0 CN 37,000 0 0 0 0 Totals 40,500 0 0 0 0

Report Date: August 29, 2018 Page 92 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 11 R035 06/19/18 06/19/18 28 O W 0.200 CE No Marcus Whitman Elementary - SRTS Winslow Ave Wright Ave to Lee Blvd Construct sidewalks and ADA ramps along Humphreys St and Winslow St on the designated school walk route for Marcus Whitman Elementary.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 SRTS 23,400 2,600 26,000 P CN 2020 0 SRTS 106,335 11,815 118,150 Totals 0 129,735 14,415 144,150

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 26,000 0 0 0 0 CN 0 118,150 0 0 0 Totals 26,000 118,150 0 0 0

Report Date: August 29, 2018 Page 93 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 12 WA-11162 06/19/18 06/19/18 28 0.010 CE No Orchard Elementary - SRTS Gala Way Gala Way to Gala Way Construct a raised pedestrian crosswalk with ADA ramps and flashing beacons.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 SRTS 7,395 0 7,395 P CN 2019 0 SRTS 43,500 0 43,500 Totals 0 50,895 0 50,895

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 7,395 0 0 0 0 CN 43,500 0 0 0 0 Totals 50,895 0 0 0 0

Report Date: August 29, 2018 Page 94 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 13 R008 06/19/18 06/19/18 01 O P S W 0.520 CE Yes Center Parkway South Extension Rachel Road Leslie Rd to Clearwater Creek Construct a 2-lane rural collector with bike lanes, separated pathway, street lights and storm drainage on both sides of the street. Left turn lanes will be constructed where needed.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 0 210,000 210,000 P RW 2020 0 0 200,000 200,000 P CN 2021 0 0 2,167,000 2,167,000 Totals 0 0 2,577,000 2,577,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 210,000 0 0 0 0 RW 0 200,000 0 0 0 CN 0 0 2,167,000 0 0 Totals 210,000 200,000 2,167,000 0 0

Report Date: August 29, 2018 Page 95 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 14 R012 06/19/18 06/19/18 01 C G P S T 0.450 CE Yes W Queensgate Drive Extension - Phase 1 Queensgate Drive Shockley Rd to Keene Rd Construct a 3-lane street with curb, gutter, sidewalk, street lights and drainage facilities on both sides. Construct a roundabout at the Queensgate Drive/Shockley Road intersection. Modify the Keene Road/Queensgate Drive traffic signal to accommodate the new south leg of Queensgate Drive.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 150,000 150,000 P RW 2023 0 0 100,000 100,000 P CN 2024 0 0 850,000 850,000 Totals 0 0 1,100,000 1,100,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 150,000 RW 0 0 0 0 100,000 CN 0 0 0 0 850,000 Totals 0 0 0 0 1,100,000

Report Date: August 29, 2018 Page 96 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 15 R029 06/19/18 06/19/18 03 S W 0.230 CE Yes Steptoe Street / Tapteal Drive Intersection Improvements

CID Canal to Canyon Street Realign Tapteal Drive and Steptoe Street intersection by constructing a new intersection. Also includes sidewalks, street lights, fully signalized and gated at- grade railroad crossing, storm drainage.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 0 100,000 100,000 P CN 2020 0 0 1,369,900 1,369,900 Totals 0 0 1,469,900 1,469,900

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 100,000 0 0 0 0 CN 0 1,369,900 0 0 0 Totals 100,000 1,369,900 0 0 0

Report Date: August 29, 2018 Page 97 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 12 16 WA-11160 06/19/18 06/19/18 28 O 0.510 Yes Island View to Vista Field Trail Georgia Ave Tapteal to Columbia Park Trail Construct a grade separated pathway across SR240 with continued pathway connecting into existing and proposed sidewalks on either end.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 745,570 745,570 P RW 2023 0 0 160,000 160,000 P CN 2024 0 0 4,250,000 4,250,000 Totals 0 0 5,155,570 5,155,570

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 745,570 RW 0 0 0 0 160,000 CN 0 0 0 0 4,250,000 Totals 0 0 0 0 5,155,570

Report Date: August 29, 2018 Page 98 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 17 WA-11173 06/19/18 06/19/18 03 P S 0.110 CE No Dallas Rd/Trowbridge Blvd I/S Improvements Trowbridge Blvd Dallas Rd to Dallas Rd Reconstruct intersection for additional capacity.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 65,000 65,000 P CN 2024 0 0 435,000 435,000 Totals 0 0 500,000 500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 65,000 CN 0 0 0 0 435,000 Totals 0 0 0 0 500,000

Report Date: August 29, 2018 Page 99 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 18 WA-11174 06/19/18 06/19/18 03 0.110 CE No Dallas Rd/Ava Way I/S Improvements Ava Way Dallas Rd to Dallas Rd Reconstruct intersection for additional capacity.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 65,000 65,000 P CN 2024 0 0 435,000 435,000 Totals 0 0 500,000 500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 65,000 CN 0 0 0 0 435,000 Totals 0 0 0 0 500,000

Report Date: August 29, 2018 Page 100 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 19 R013 06/19/18 06/19/18 01 P S W 0.640 CE Yes Queensgate Drive Extension - Phase II Queensgate Drive Legacy Ln to City Limit Construct new 2-lane collector with curb, gutter, sidewalk, street lights, and storm drainage facilities on both sides

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 81,160 81,160 P RW 2023 0 0 436,160 436,160 P CN 2024 0 0 349,310 349,310 Totals 0 0 866,630 866,630

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 81,160 0 RW 0 0 0 0 436,160 CN 0 0 0 0 349,310 Totals 0 0 0 81,160 785,470

Report Date: August 29, 2018 Page 101 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 20 WA-11166 06/19/18 06/19/18 01 O P S W 0.600 CE Yes Shockley Rd Extension Shockley Rd Keene Rd to Columbia Park Trail Construct a new 2-lane street with curb, gutter, sidewalk, bike lanes, street lights and storm drainage facilities

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 110,280 110,280 P RW 2023 0 0 824,380 824,380 P CN 2024 0 0 367,600 367,600 Totals 0 0 1,302,260 1,302,260

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 110,280 RW 0 0 0 0 824,380 CN 0 0 0 0 367,600 Totals 0 0 0 0 1,302,260

Report Date: August 29, 2018 Page 102 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 21 WA-11168 06/19/18 06/19/18 01 O P S W 0.500 CE Yes Trowbridge Blvd Trowbridge Blvd Dallas Rd to Ava Way Construct additional 2-lane half street with curb, gutter, sidewalk, bike lanes, street lights and storm drainage facilities.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 0 128,280 128,280 P RW 2019 0 0 456,570 456,570 P CN 2020 0 0 427,600 427,600 Totals 0 0 1,012,450 1,012,450

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 128,280 0 0 0 0 RW 456,570 0 0 0 0 CN 0 427,600 0 0 0 Totals 584,850 427,600 0 0 0

Report Date: August 29, 2018 Page 103 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 22 WA-11169 06/19/18 06/19/18 01 O P S W 1.040 CE Yes Trowbridge Blvd Trowbridge Blvd Ava Way to Road B-c Construct a new 2-lane street with curb, gutter, sidewalk, bike lanes, street lights and storm drainage facilities.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 422,860 422,860 P RW 2023 0 0 1,480,610 1,480,610 P CN 2024 0 0 1,409,540 1,409,540 Totals 0 0 3,313,010 3,313,010

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 422,860 RW 0 0 0 0 1,480,610 CN 0 0 0 0 1,409,540 Totals 0 0 0 0 3,313,010

Report Date: August 29, 2018 Page 104 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 23 WA-11171 06/19/18 06/19/18 03 P S 0.720 CE No Dallas Road Widening Dallas Road City Limits to I-82 Widening Dallas Road from 2-lanes to 4-lanes with curb, gutter, sidewalk, bike lanes, streets lights and storm drainage facilities.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 274,270 274,270 P CN 2023 0 0 914,230 914,230 Totals 0 0 1,188,500 1,188,500

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 274,270 CN 0 0 0 0 914,230 Totals 0 0 0 0 1,188,500

Report Date: August 29, 2018 Page 105 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 24 WA-11170 06/19/18 06/19/18 01 O P S W 0.200 CE Yes Ava Way Extension Ava Way Malbec Ave to Trowbridge Blvd Construct a new 2-lane street with curb, gutter, sidewalk, bike lanes, street lights and storm drainage facilities.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 0 81,120 81,120 P RW 2019 0 0 280,030 280,030 P CN 2020 0 0 270,380 270,380 Totals 0 0 631,530 631,530

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 81,120 0 0 0 0 RW 280,030 0 0 0 0 CN 0 270,380 0 0 0 Totals 361,150 270,380 0 0 0

Report Date: August 29, 2018 Page 106 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 11 25 WA-11177 06/19/18 06/19/18 03 P S 0.410 CE No Dallas Rd/I-82 WB Ramp I/S Improvements Dallas Road I-82 to I-82 Reconstruct ramp and intersection for added capacity.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 78,000 78,000 P CN 2024 0 0 522,000 522,000 Totals 0 0 600,000 600,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 78,000 CN 0 0 0 0 522,000 Totals 0 0 0 0 600,000

Report Date: August 29, 2018 Page 107 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 11 26 WA-11178 06/19/18 06/19/18 03 P S 0.410 CE No Dallas Rd/I-82 EB Ramp I/S Improvements Dallas Road I-82 to I-82 Reconstruct ramp and intersection for added capacity.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 78,000 78,000 P CN 2024 0 0 522,000 522,000 Totals 0 0 600,000 600,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 78,000 CN 0 0 0 0 522,000 Totals 0 0 0 0 600,000

Report Date: August 29, 2018 Page 108 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 27 WA-11172 06/19/18 06/19/18 01 O P S W 1.340 CE Yes Bella Coola Ln Bella Coola Ln Trowbridge Blvd to Road B-C Construct a new 2-lane street with curb, gutter, sidewalk, bike lanes, street lights and storm drainage facilities.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 534,420 534,420 P RW 2023 0 0 1,858,130 1,858,130 P CN 2024 0 0 1,781,400 1,781,400 Totals 0 0 4,173,950 4,173,950

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 534,420 RW 0 0 0 0 1,858,130 CN 0 0 0 0 1,781,400 Totals 0 0 0 0 4,173,950

Report Date: August 29, 2018 Page 109 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 28 WA-11175 06/19/18 06/19/18 03 P S 0.110 CE No Trowbridge Blvd/Ava Way I/S Improvements Trowbridge Blvd Ava Way to Ava Way Reconstruct intersection for additional capacity.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 52,000 52,000 P CN 2024 0 0 348,000 348,000 Totals 0 0 400,000 400,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 52,000 CN 0 0 0 0 348,000 Totals 0 0 0 0 400,000

Report Date: August 29, 2018 Page 110 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 29 WA-11176 06/19/18 06/19/18 03 P S 0.110 CE No Trowbridge Blvd/Bella Coola Ln I/S Improvements Trowbridge Blvd Bella Coola Ln to Bella Coola Ln Reconstruct intersection for additional capacity.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 39,000 39,000 P CN 2024 0 0 261,000 261,000 Totals 0 0 300,000 300,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 39,000 CN 0 0 0 0 261,000 Totals 0 0 0 0 300,000

Report Date: August 29, 2018 Page 111 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 30 WA-11179 06/19/18 06/19/18 03 P S 0.110 CE No Road B-C/Trowbridge I/S Improvements Trowbridge Blvd Road B-C to Road B-C Reconstruct intersection for additional capacity.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 65,000 65,000 P CN 2024 0 0 435,000 435,000 Totals 0 0 500,000 500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 65,000 CN 0 0 0 0 435,000 Totals 0 0 0 0 500,000

Report Date: August 29, 2018 Page 112 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 31 WA-11167 06/19/18 06/19/18 01 O P S W 0.880 CE Yes Road B-C Road B-C Corvina St to Queensgate Dr. Construct a new 2-lane street with curb, gutter, sidewalk, bike lanes, street lights and storm drainage facilities.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 162,650 162,650 P RW 2023 0 0 1,215,900 1,215,900 P CN 2024 0 0 542,180 542,180 Totals 0 0 1,920,730 1,920,730

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 162,650 RW 0 0 0 0 1,215,900 CN 0 0 0 0 542,180 Totals 0 0 0 0 1,920,730

Report Date: August 29, 2018 Page 113 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 32 R028 06/19/18 06/19/18 04 O P 0.750 CE No Gage Boulevard Improvements Gage Boulevard Penny Royal Ave to Morency Dr. Add bike lanes, shoulders, sidewalks, street lights, storm drainage on Gage Boulevard.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 77,250 77,250 P CN 2024 0 0 772,500 772,500 Totals 0 0 849,750 849,750

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 77,250 CN 0 0 0 0 772,500 Totals 0 0 0 0 849,750

Report Date: August 29, 2018 Page 114 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 33 WA-11159 06/19/18 06/19/18 01 O P 0.600 CE Yes Gage Boulevard Extension Gage Boulevard Morency Dr. to Queensgate Blvd. Construct a 3-lane street with curb, gutter, sidewalk, street lights and drainage facilities on both sides.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 192,420 192,420 P RW 2023 0 0 983,710 983,710 P CN 2024 0 0 823,130 823,130 Totals 0 0 1,999,260 1,999,260

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 192,420 RW 0 0 0 0 983,710 CN 0 0 0 0 823,130 Totals 0 0 0 0 1,999,260

Report Date: August 29, 2018 Page 115 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 14 34 R016 06/19/18 06/19/18 28 C P T 2.250 CE No Stevens Drive Pathway Stevens Drive Spengler St to Horn Rapids Rd Construct a separated multi-use pathway on east side of Stevens Drive.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 72,100 72,100 P CN 2024 0 0 906,400 906,400 Totals 0 0 978,500 978,500

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 72,100 CN 0 0 0 0 906,400 Totals 0 0 0 0 978,500

Report Date: August 29, 2018 Page 116 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 12 35 R034 06/19/18 06/19/18 28 1.750 CE No Vantage Highway Pathway - Phase 3 SR 240 Twin Bridges Road to Kingsgate Way Construct a new, separated Hot Mix Asphalt multi-use pathway on the north side of SR 240.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 TAP(UL) 31,800 0 21,200 53,000 P CN 2024 TAP(UL) 530,000 0 53,000 583,000 Totals 561,800 0 74,200 636,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 53,000 CN 0 0 0 0 583,000 Totals 0 0 0 0 636,000

Report Date: August 29, 2018 Page 117 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 36 WA-11161 06/19/18 06/19/18 01 4.770 EA Yes Kingsgate/Queensgate Corridor Improvements Kingsgate/Queensgate Queensgate Drive to SR240 Construct a new 2-lane street and bridge over the Yakima River with curb, gutter, sidewalk, bike lanes, street lights and storm drainage facilities.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 9,642,000 9,642,000 P RW 2023 0 0 8,575,385 8,575,385 P CN 2024 0 0 46,062,615 46,062,615 Totals 0 0 64,280,000 64,280,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 0 9,642,000 RW 0 0 0 0 8,575,385 CN 0 0 0 0 46,062,615 Totals 0 0 0 0 64,280,000

Federal Funds State Funds Local Funds Total Funds Grand Totals for Richland 3,274,890 6,551,994 140,511,965 150,338,849

Report Date: August 29, 2018 Page 118 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 2 / 3476(001) WA-00169 05/15/18 06/05/18 20-18 01 C G O P S 1.000 CE Yes T W Paradise Way Extension - Phase 4 Paradise Way Well # 6 to SR 224 New construction of a two lane roadway with a center turn lane. Including constructing pedestrian and bicycle facilities, storm drainage, and illumination.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2020 0 0 1,390,000 1,390,000 Totals 0 0 1,390,000 1,390,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 1,390,000 0 0 0 Totals 0 1,390,000 0 0 0

Report Date: August 29, 2018 Page 119 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 3 WA-08831 05/15/18 06/05/18 20-18 11 C O P S T 0.000 CE No W S 38TH AVE BRIDGE REPLACEMENT S 38TH AVE S 38TH AVE to S 38TH AVE BRIDGE REPLACEMENT

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2021 0 0 900,000 900,000 Totals 0 0 900,000 900,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 900,000 0 0 Totals 0 0 900,000 0 0

Report Date: August 29, 2018 Page 120 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 4 WA-08829 05/15/18 06/05/18 20-18 21 C O P S T 0.000 CE No W BOMBING RANGE RD/ KEENE RD ROUNDABOUT MODIFICATIONS BOMBING RANGE RD/MT ADAMS VIEW DR Bombign Range Road to KEENE RD ROUND-A-BOUT MODIFICATIONS

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2021 0 0 1,000,000 1,000,000 Totals 0 0 1,000,000 1,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 1,000,000 0 0 Totals 0 0 1,000,000 0 0

Report Date: August 29, 2018 Page 121 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 5 WA-07769 05/15/18 06/05/18 20-18 05 S W 0.760 CE No Grosscup Blvd Pavement Preservation Grosscup Blvd SR 224 to North 62nd Ave Pavement Restoration

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2021 0 0 253,125 253,125 Totals 0 0 253,125 253,125

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 253,125 0 0 Totals 0 0 253,125 0 0

Report Date: August 29, 2018 Page 122 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 6 00190 05/15/18 06/05/18 20-18 05 C P S T W 0.720 CE No North 62nd Pavement Preservation North 62nd Ave SR 224 to Grosscup Blvd Pavement Preservation

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2021 0 0 907,000 907,000 Totals 0 0 907,000 907,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 907,000 0 0 Totals 0 0 907,000 0 0

Report Date: August 29, 2018 Page 123 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 7 WA-07770 05/15/18 06/05/18 20-18 05 S W 1.280 CE No Harrington Dr Pavement Preservation Harrington Dr North 62nd Ave to West City Limits Pavement Preservation

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2021 0 0 230,604 230,604 Totals 0 0 230,604 230,604

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 230,604 0 0 Totals 0 0 230,604 0 0

Report Date: August 29, 2018 Page 124 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 8 WA-07771 05/15/18 06/05/18 20-18 05 S W 1.000 CE No Kennedy Rd Pavement Preservation Kennedy Rd Bombing Range Road to West City Limits Pavement Preservation

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2021 0 0 143,732 143,732 Totals 0 0 143,732 143,732

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 143,732 0 0 Totals 0 0 143,732 0 0

Report Date: August 29, 2018 Page 125 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 9 WA-07772 05/15/18 06/05/18 20-18 05 S W 1.150 CE No Paradise Way Pavement Preservation Paradise Way Bombing Range Road to 600' W of Jade Ave Pavement Preservation

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2022 0 0 492,000 492,000 Totals 0 0 492,000 492,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 492,000 0 Totals 0 0 0 492,000 0

Report Date: August 29, 2018 Page 126 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 10 WA-07773 05/15/18 06/05/18 20-18 05 S W 2.480 CE No Ruppert Rd Pavement Preservation Ruppert Rd SR 224 to West City Limits Pavement Preservation

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2022 0 0 298,280 298,280 Totals 0 0 298,280 298,280

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 298,280 0 Totals 0 0 0 298,280 0

Report Date: August 29, 2018 Page 127 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 11 WA-00171 05/15/18 06/05/18 20-18 03 C G P S T 0.700 CE No W Bombing Range Road Widening Bombing Range Road Collins Road to Norma Roadway Widening

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 3,729,000 3,729,000 Totals 0 0 3,729,000 3,729,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 3,729,000 Totals 0 0 0 0 3,729,000

Report Date: August 29, 2018 Page 128 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 12 WA-00178 05/15/18 06/05/18 20-18 03 C G O P S 2.780 CE No T W Keene Road Widening Keene Road Bombing Range Road to SR 224 Road Widening to 4 Lanes with 12' Paved Pathway

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 7,180,000 7,180,000 Totals 0 0 7,180,000 7,180,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 7,180,000 Totals 0 0 0 0 7,180,000

Report Date: August 29, 2018 Page 129 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 13 00184 05/15/18 06/05/18 20-18 03 C P S T W 0.230 EA Yes S 38th Ave Downtown Redevelopment Project S 38th Ave Van Giesen (SR 224) to Fallon Dr Construct Urban Collector Roadway

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 4,707,000 4,707,000 Totals 0 0 4,707,000 4,707,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 4,707,000 Totals 0 0 0 0 4,707,000

Report Date: August 29, 2018 Page 130 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 14 00185 05/15/18 06/05/18 20-18 03 C P S T W 0.390 EA Yes Fallon Dr Downtown Redevelopment Project Fallon Dr SR 224 to S 39th Ave Construct Urban Collector

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 2,053,000 2,053,000 Totals 0 0 2,053,000 2,053,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 2,053,000 Totals 0 0 0 0 2,053,000

Report Date: August 29, 2018 Page 131 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 15 WA-08825 05/15/18 06/05/18 20-18 21 C O P S T 0.000 CE Yes W SR 224 / RUPPERT ROAD TRAFFIC SIGNAL SR 224 / RUPPERT RD SR 224 to RUPPERT RD SIGNALIZE INTERSECTION

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 500,000 500,000 Totals 0 0 500,000 500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 500,000 Totals 0 0 0 0 500,000

Report Date: August 29, 2018 Page 132 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 16 WA-08826 05/15/18 06/05/18 20-18 21 C O P S T 0.000 CE No W SR 224 / PARADISE WAY TRAFFIC SIGNAL SR 224/PARADISE WAY SR 224 to PARADISE WAY SIGNALIZE INTERSECTION

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 420,000 420,000 Totals 0 0 420,000 420,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 420,000 Totals 0 0 0 0 420,000

Report Date: August 29, 2018 Page 133 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 17 WA-08827 05/15/18 06/05/18 20-18 21 C O P S T 0.000 CE No W SR 224 / KEENE RD TRAFFIC SIGNAL SR 224 / KEENE RD SR 224 to KEENE RD SIGNALIZED INTERSECTION

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 500,000 500,000 Totals 0 0 500,000 500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 500,000 Totals 0 0 0 0 500,000

Report Date: August 29, 2018 Page 134 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 18 WA-10034 05/15/18 06/05/18 20-18 21 C P T 0.000 CE No Keene Road / Preakness Blvd Traffic Signal Keene Road/ Preakness Blvd Keene Road to Preakness Blvd Signalize Intersection

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 350,000 350,000 Totals 0 0 350,000 350,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 350,000 Totals 0 0 0 0 350,000

Report Date: August 29, 2018 Page 135 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 19 WA-00181 05/15/18 06/05/18 20-18 01 C G O P S 1.100 CE Yes T W Belmont Blvd - Phase 2 Belmont Blvd Paradise Way to SR 224 Construct Urban Arterial Collector

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 3,410,000 3,410,000 Totals 0 0 3,410,000 3,410,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 3,410,000 Totals 0 0 0 0 3,410,000

Report Date: August 29, 2018 Page 136 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 20 WA-00168 05/15/18 06/05/18 20-18 01 0.720 CE No Keene Road - Phase 6 Keene Road Pacific Rim Winery to Ruppert Road Construct 3 Lane Urban Section with 12'Paved Pathway.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 3,313,000 3,313,000 Totals 0 0 3,313,000 3,313,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 3,313,000 Totals 0 0 0 0 3,313,000

Report Date: August 29, 2018 Page 137 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 21 WA-00180 05/15/18 06/05/18 20-18 03 C O P S T 0.800 CE Yes W S 38th Ave - Phase 2 S 38th Ave Grant Street to Orchard St Construct 3 Lane Urban Section and Widen Bridge

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 2,068,000 2,068,000 Totals 0 0 2,068,000 2,068,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 2,068,000 Totals 0 0 0 0 2,068,000

Report Date: August 29, 2018 Page 138 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 22 WA-00183 05/15/18 06/05/18 20-18 01 C G O P T 0.120 No Watkins Way Extension Watkins Way West Lattin to Hazelwood Drive Construct Arterial Collector

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 346,000 346,000 Totals 0 0 346,000 346,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 346,000 Totals 0 0 0 0 346,000

Report Date: August 29, 2018 Page 139 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 23 WA-00173 05/15/18 06/05/18 20-18 01 C G O P S 1.980 CE Yes T W Keene Road - Phase 7 Keene Road Ruppert Road to Twin Bridges Construct 2 Lane Rural Section

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 4,206,000 4,206,000 Totals 0 0 4,206,000 4,206,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 4,206,000 Totals 0 0 0 0 4,206,000

Report Date: August 29, 2018 Page 140 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 24 WA-00172 05/15/18 06/05/18 20-18 01 C G O P S 1.500 CE Yes T W Paradise Way Extension - Phase 5 Paradise Way SR 224 to Ruppert Road Construct 3 Lane Urban Section

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 3,259,000 3,259,000 Totals 0 0 3,259,000 3,259,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 3,259,000 Totals 0 0 0 0 3,259,000

Report Date: August 29, 2018 Page 141 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 25 WA-10035 05/15/18 06/05/18 20-18 01 C G P S T CE No W Preakness Blvd Preakness Blvd Paradise Way to Red Mountain Way Construct arterial collector

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 2,800,000 2,800,000 Totals 0 0 2,800,000 2,800,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 2,800,000 Totals 0 0 0 0 2,800,000

Report Date: August 29, 2018 Page 142 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 26 WA-10036 05/15/18 06/05/18 20-18 01 C P T CE No Red Mountain Way Red Mountain Way Belmont Blvd to Alderman Ave Construct arterial collector

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 1,400,000 1,400,000 Totals 0 0 1,400,000 1,400,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 1,400,000 Totals 0 0 0 0 1,400,000

Report Date: August 29, 2018 Page 143 Six Year Transportation Improvement Program From 2019 to 2024 Agency: West Richland County: Benton MPO/RTPO: BFCG Y Inside N Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 27 WA-10037 05/15/18 06/05/18 20-18 01 C T CE No Wagner Ave Wagner Ave SR 224 to Red Mountain Way Construct arterial collector

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 400,000 400,000 Totals 0 0 400,000 400,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 400,000 Totals 0 0 0 0 400,000

Federal Funds State Funds Local Funds Total Funds Grand Totals for West Richland 0 0 46,255,741 46,255,741

Report Date: August 29, 2018 Page 144 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton City County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 1 BC-000006 06/19/12 06/19/12 2012-22 05 P S T W 0.340 CE No Chris Avenue Overlay Project Chris Avenue SR 225 to 14th Street Overlay and Widening

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 TIB 64,600 3,400 68,000 P CN 2019 0 TIB 581,400 30,600 612,000 Totals 0 646,000 34,000 680,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 68,000 0 0 0 0 CN 612,000 0 0 0 0 Totals 680,000 0 0 0 0

Report Date: August 29, 2018 Page 145 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton City County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 6 BC-000007 06/19/12 06/19/12 2012-22 03 T W 0.200 CE No Alma Avenue Overlay Project Alma Avenue 2nd Street to West End Pavement Overlay & Cul-de-Sac Construction

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2019 0 WSDOT 32,000 8,000 40,000 Totals 0 32,000 8,000 40,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 40,000 0 0 0 0 Totals 40,000 0 0 0 0

Report Date: August 29, 2018 Page 146 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton City County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 9 BC-000012 06/19/12 06/19/12 2012-22 05 0.220 CE No Della Avenue Overlay Project Della Avenue 13th Street to West End Pavement Overlay

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2019 0 0 66,000 66,000 Totals 0 0 66,000 66,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 66,000 0 0 0 0 Totals 66,000 0 0 0 0

Federal Funds State Funds Local Funds Total Funds Grand Totals for Benton City 0 678,000 108,000 786,000

Report Date: August 29, 2018 Page 147 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 1 BCO2012-17 07/10/18 07/17/18 2018-468 04 P T 2.000 CE No BERT JAMES RD PH I 15650 Williamson Rd (MP 8.146) to SR 221 (MP 10.240) Reconstruct a 2 lane road segment.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 CRAB 25,000 25,000 50,000 P CN 2022 0 CRAB 200,000 0 200,000 Totals 0 225,000 25,000 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 50,000 0 CN 0 0 0 200,000 0 Totals 0 0 0 250,000 0

Report Date: August 29, 2018 Page 148 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 4 BCO2015-11 07/10/18 07/17/18 2018-468 04 C P T W 1.500 CE Yes HANKS RD I Hanks Rd Phase 1 6.07 to 7.6 Reconstruction of vertical and horizontal alignment to an all weather road standard.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 CRAB 1,530,000 170,000 1,700,000 Totals 0 1,530,000 170,000 1,700,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 1,700,000 Totals 0 0 0 0 1,700,000

Report Date: August 29, 2018 Page 149 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 5 BCO2015-10 07/10/18 07/17/18 2018-468 04 C P T W 1.530 CE Yes HANKS RD II Hanks Rd Phase 2 7.6 to 9.1 Reconstruction of vertical and horizontal alignment to an all weather road standard.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2022 0 0 1,700,000 1,700,000 Totals 0 0 1,700,000 1,700,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 1,760,000 Totals 0 0 0 0 1,760,000

Report Date: August 29, 2018 Page 150 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 6 WA-10231 07/10/18 07/17/18 2018-468 01 1.200 EA Yes BELMONT ROAD Belmont Road 0.000 to 1.200 The proposed project would construct a new paved roadway from the current city limits (end of Belmont) to Kennedy Road. The road is proposed to have hot-mix asphalt as a wearing surface.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2022 0 0 861,000 861,000 Totals 0 0 861,000 861,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 0 0 0 861,000 0 Totals 0 0 0 861,000 0

Report Date: August 29, 2018 Page 151 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 7 2014-17 07/10/18 07/17/18 2018-468 04 P T 3.000 CE Yes COUNTY WELL ROAD - Phase 1 County Well Rd. #11110 SR 221 to McBee Road Reconstruct current road to an all weather road. Existing alignment will remain the same but the profile will be improved. New subgrade will have one foot of surfacing with 0.30' of HMA. Other items of work include Guardrails and drainage.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 175,000 175,000 P RW 2020 0 0 50,000 50,000 P CN 2020 0 0 2,025,000 2,025,000 Totals 0 0 2,250,000 2,250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 175,000 0 0 0 RW 0 50,000 0 0 0 CN 0 2,025,000 0 0 0 Totals 0 2,250,000 0 0 0

Report Date: August 29, 2018 Page 152 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 8 WA-09498 07/10/18 07/17/18 04 P T 2.150 CE No BERT JAMES RD PH II 15650 5.993 to 8.146 Reconstruct 2.15 miles of roadway to all-weather standard.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 CRAB 25,000 25,000 50,000 P CN 2022 0 CRAB 200,000 0 200,000 Totals 0 225,000 25,000 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 50,000 0 CN 0 0 0 200,000 0 Totals 0 0 0 250,000 0

Report Date: August 29, 2018 Page 153 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 8 2014-18 07/10/18 07/17/18 2018-468 04 P T 2.000 CE Yes COUNTY WELL ROAD - Phase 2 County Well Rd. #11110 McBee Rd. to Clodius Rd. Reconstruct current road to an all weather road. Existing alignment will remain the same but the profile will be improved. New subgrade will have one foot of surfacing with 0.30' of HMA. Other items of work include Guardrails and drainage

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2022 0 0 1,500,000 1,500,000 Totals 0 0 1,500,000 1,500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 1,500,000 0 Totals 0 0 0 1,500,000 0

Report Date: August 29, 2018 Page 154 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 9 2014-19 07/10/18 07/10/18 2018-468 04 P T 1.800 CE Yes COUNTY WELL ROAD -Phase 3: Clodius to County Pit County Well Rd. #11110 Clodius Rd. to County Pit Reconstruct current road to an all weather road. Existing alignment will remain the same but the profile will be improved. New subgrade will have one foot of surfacing with 0.30' of HMA. Other items of work include Guardrails and drainage.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2021 0 0 1,350,000 1,350,000 Totals 0 0 1,350,000 1,350,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 1,350,000 0 0 Totals 0 0 1,350,000 0 0

Report Date: August 29, 2018 Page 155 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 10 BCO2014-16 07/10/18 07/17/18 2018-468 04 P T 2.100 CE Yes FINLEY RD Finley Road M.P. 5.2 to End of Pavement Reconstruct a segment of gravel road to an all weather road.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 125,000 125,000 P RW 2020 0 0 50,000 50,000 P CN 2020 0 0 1,575,000 1,575,000 Totals 0 0 1,750,000 1,750,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 125,000 0 0 0 RW 0 50,000 0 0 0 CN 0 1,575,000 0 0 0 Totals 0 1,750,000 0 0 0

Report Date: August 29, 2018 Page 156 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 10 BCO2012-19 07/10/18 07/17/18 04 P T 0.500 CE No JOHNSON RD/GRIFFIN RD 20250 / 20280 Intersection to Intersection Intersection improvements.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 100,000 100,000 P CN 2022 0 0 900,000 900,000 Totals 0 0 1,000,000 1,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 100,000 0 CN 0 0 0 900,000 0 Totals 0 0 0 1,000,000 0

Report Date: August 29, 2018 Page 157 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 11 BCO2016-22 07/28/15 07/28/15 11 0.000 CE No OBSOLETE BRIDGE REMOVAL Varies N/A to N/A Removing short span bridges over filled in irrigation canals.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2020 0 0 100,000 100,000 P CN 2021 0 0 100,000 100,000 P CN 2022 0 0 100,000 100,000 Totals 0 0 300,000 300,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 0 100,000 100,000 100,000 0 Totals 0 100,000 100,000 100,000 0

Report Date: August 29, 2018 Page 158 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 12 BCO2016-23 07/28/15 07/28/15 21 0.000 CE No ROADSIDE WATERWAY PIPING AND SAFETY MITIGATION

N/A to N/A Safety improvements of roadways next to waterways.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2021 0 0 300,000 300,000 Totals 0 0 300,000 300,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 0 0 150,000 150,000 0 Totals 0 0 150,000 150,000 0

Report Date: August 29, 2018 Page 159 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 13 BCO2012-24 07/10/18 07/17/18 44 No PATHS & TRAILS various various to various Construct Paths & Trails, as required. (Emergent path projects)

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2019 STP(E) 54,000 0 6,000 60,000 Totals 54,000 0 6,000 60,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 10,000 10,000 10,000 10,000 0 Totals 10,000 10,000 10,000 10,000 0

Report Date: August 29, 2018 Page 160 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 16 BCO2012-14 07/10/18 07/17/18 04 P T 2.300 CE No CASE RD 31550 OIEH to Hanks Rd. Reconstruct a segment of road to an all weather road.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2020 0 0 2,000,000 2,000,000 Totals 0 0 2,000,000 2,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 0 0 660,000 670,000 670,000 Totals 0 0 660,000 670,000 670,000

Report Date: August 29, 2018 Page 161 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Benton Co. County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 25 BCO2012-26 07/10/18 07/17/18 22 CE No RAILROAD CROSSINGS various various to various Upgrade RR-Xings, when approved for funding.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2019 STP(E) 54,000 0 6,000 60,000 Totals 54,000 0 6,000 60,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 10,000 10,000 10,000 10,000 0 Totals 10,000 10,000 10,000 10,000 0

Federal Funds State Funds Local Funds Total Funds Grand Totals for Benton Co. 108,000 1,980,000 13,243,000 15,331,000

Report Date: August 29, 2018 Page 162 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 16 1 WA-00682 07/02/18 07/02/18 2018-05 03 G P S T W 0.510 CE No East Clark Street E. Clark St. Columbia Ave to Ford Ave Reconstruction, drainage, curbs, gutters and sidewalk on both sides.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 150,000 150,000 P CN 2021 0 TIB 1,650,000 0 1,650,000 Totals 0 1,650,000 150,000 1,800,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 150,000 0 0 0 CN 0 0 1,650,000 0 0 Totals 0 150,000 1,650,000 0 0

Report Date: August 29, 2018 Page 163 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 2 WA-03813 07/02/18 06/19/17 2018-05 04 0.230 CE No South 5th Street Re-Construct

Hawthorne to Juniper Reconstruction, drainage, curbs and gutters.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 70,000 70,000 P CN 2020 0 TIB 680,000 0 680,000 Totals 0 680,000 70,000 750,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 70,000 0 0 0 CN 0 680,000 0 0 0 Totals 0 750,000 0 0 0

Report Date: August 29, 2018 Page 164 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 3 WA-00690 07/02/18 07/02/18 2018-05 03 0.330 CE No Hawthorne Street Project Hawthorne St S. Columbia Ave to S. 5th Reconstruction, curbs, gutters,and sidewalk on one side.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 PWTF 80,000 0 80,000 P CN 2022 0 TIB 720,000 0 720,000 Totals 0 800,000 0 800,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 80,000 0 0 CN 0 0 0 720,000 0 Totals 0 0 80,000 720,000 0

Report Date: August 29, 2018 Page 165 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 5 WA-00685 07/02/18 07/02/18 2018-05 03 C G P S T 0.170 CE No W East Davis Street E.Davis St. Almira to Chelan Reconstruction with drainage, curbs, gutters and sidewalk on both sides.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 50,000 50,000 P CN 2021 0 TIB 200,000 0 200,000 Totals 0 200,000 50,000 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 50,000 0 0 0 CN 0 0 200,000 0 0 Totals 0 50,000 200,000 0 0

Report Date: August 29, 2018 Page 166 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 6 WA-08035 07/02/18 07/02/18 2018-05 05 1.100 No W. Clark St. Chip Seal

Columbia Ave to SR 260 Chip Seal from Columbia Ave. to SR 260

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 0 20,000 20,000 P CN 2019 0 TIB 230,000 0 230,000 Totals 0 230,000 20,000 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 20,000 0 0 0 0 CN 230,000 0 0 0 0 Totals 250,000 0 0 0 0

Report Date: August 29, 2018 Page 167 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 7 WA-06634 07/02/18 07/02/18 2018-05 04 0.120 CE No 600 Blk. S. Burke Re-Construct

Fir Street to Elm Street Reconstruction with drainage, curbs, gutters and sidewalk on 1 side

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 42,000 42,000 P CN 2022 0 TIB 378,000 0 378,000 Totals 0 378,000 42,000 420,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 42,000 0 CN 0 0 0 378,000 0 Totals 0 0 0 420,000 0

Report Date: August 29, 2018 Page 168 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 8 WA-00691 07/02/18 07/02/18 2018-05 06 0.610 Yes Ford Ave. Bike Path Extension Ford Ave Clark St. to N. Columbia Ave. Construction and extension of pedestrian/bicycle path.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 50,000 50,000 P CN 2022 0 TIB 300,000 0 300,000 Totals 0 300,000 50,000 350,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 50,000 0 0 CN 0 0 0 300,000 0 Totals 0 0 50,000 300,000 0

Report Date: August 29, 2018 Page 169 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 19 9 WA-03814 07/02/18 07/02/18 2018-05 01 0.020 No Birch to Burke Connector

Birch St to Burke Ave Construct road across old railroad right of way to connect Birch to Burke.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 30,000 30,000 P CN 2020 0 TIB 320,000 0 320,000 Totals 0 320,000 30,000 350,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 30,000 0 0 0 CN 0 320,000 0 0 0 Totals 0 350,000 0 0 0

Report Date: August 29, 2018 Page 170 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 10 WA-00686 07/02/18 07/02/18 2018-05 06 0.220 Yes Old Railroad right of way path E.Side

Columbia Ave to Chelan Ave Construction of pedestrian/bicycle path.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 20,000 20,000 P CN 2020 BR 180,000 0 0 180,000 Totals 180,000 0 20,000 200,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 20,000 0 0 0 CN 0 180,000 0 0 0 Totals 0 200,000 0 0 0

Report Date: August 29, 2018 Page 171 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 11 WA-11369 07/02/18 07/02/18 2018-05 06 W 0.140 Yes Old Railroad right of way path W.Side

Columbia Ave. to Adams St. Construction of pedestrian/bicycle path.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 20,000 20,000 P CN 2022 0 TIB 80,000 0 80,000 Totals 0 80,000 20,000 100,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 20,000 0 0 CN 0 0 0 80,000 0 Totals 0 0 20,000 80,000 0

Report Date: August 29, 2018 Page 172 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 12 WA-00693 07/02/18 07/02/18 2018-09 01 0.350 Yes South Sixth Street Extension S. Sixth St. Clark St. to Elm Street New construction of road and bridge over railway and Equatzel Coulee.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 500,000 500,000 P RW 2022 0 0 110,000 110,000 P CN 2023 0 TIB 2,890,000 0 2,890,000 Totals 0 2,890,000 610,000 3,500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 500,000 0 0 RW 0 0 0 110,000 0 CN 0 0 0 0 2,890,000 Totals 0 0 500,000 110,000 2,890,000

Report Date: August 29, 2018 Page 173 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 13 WA-09018 07/02/18 07/02/18 2018-05 04 0.350 CE No Old Town Re-Constuct-Phase 1 N. 3rd, 4th, 5th & Franklin 100 Blk of N. 3rd to 200 Blk of N. 5th Reconstruct, drainage, curbs, gutters & sidewalk on one side.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 60,000 60,000 P CN 2021 0 TIB 1,210,000 30,000 1,240,000 Totals 0 1,210,000 90,000 1,300,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 60,000 0 0 CN 0 0 1,240,000 0 0 Totals 0 0 1,300,000 0 0

Report Date: August 29, 2018 Page 174 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 14 WA-09019 07/02/18 07/02/18 2108-05 04 0.500 CE No Old Town Reconstruct-Phase 2 N.3rd,4th,5th & Borah 200 N. 3rd to 300 N. 5th Reconstruct, drainage, curbs, gutters & sidewalk on one side.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 80,000 80,000 P CN 2021 0 TIB 1,690,000 30,000 1,720,000 Totals 0 1,690,000 110,000 1,800,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 80,000 0 0 CN 0 0 1,720,000 0 0 Totals 0 0 1,800,000 0 0

Report Date: August 29, 2018 Page 175 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 15 WA-11370 07/02/18 07/02/18 2018-05 04 G S T W 0.070 No N. Burke Ave Reconstruction

E. Adams St to E. Franklin St. Reconstruction by adding curbs,gutter,and sidewalk on one side

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 25,000 25,000 P CN 2022 0 TIB 225,000 0 225,000 Totals 0 225,000 25,000 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 25,000 0 CN 0 0 0 255,000 0 Totals 0 0 0 280,000 0

Report Date: August 29, 2018 Page 176 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Connell County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 16 WA-10805 07/02/18 07/02/18 2018-05 03 3.520 No Connell Rail Interchange

MP 110.45 to MP 112.55 Relocating current switch yard to new location, for better mobility and ease of access.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S PE 2020 0 CWA 600,000 0 600,000 S CN 2021 0 CWA 9,400,000 0 9,400,000 P CN 2021 TIGER 14,100,000 0 0 14,100,000 Totals 14,100,000 10,000,000 0 24,100,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 600,000 0 0 0 CN 0 0 23,500,000 0 0 Totals 0 600,000 23,500,000 0 0

Federal Funds State Funds Local Funds Total Funds Grand Totals for Connell 14,280,000 20,653,000 1,287,000 36,220,000

Report Date: August 29, 2018 Page 177 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 11 WA-07940 06/26/18 06/26/18 2018-205 28 P S T W 0.200 CE No Basin City Alternative Transportation Route Improvements II Bailie Boulevard 0.06 to 0.26 Replace pedestrian ramps, install new trail and/or sidewalks, improve adjunct facilities, and improve drainage.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S PE 2019 TAP(R) 34,600 0 5,400 40,000 P CN 2020 TAP(R) 71,771 0 11,201 82,972 P CN 2021 TAP(R) 218,005 0 34,023 252,028 Totals 324,376 0 50,624 375,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 20,000 20,000 0 0 0 CN 0 0 335,000 0 0 Totals 20,000 20,000 335,000 0 0

Report Date: August 29, 2018 Page 178 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 12 / F114(003) WA-01027 06/26/18 06/26/18 2018-205 04 P T W 4.120 CE Yes Glade North Overlay III Glade North Road Selph Landing Road to Sagemoor Road Widen and Overlay existing road and upgrade to an All-weather standard.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P RW 2019 STP(R) 259,500 0 40,500 300,000 P CN 2020 STP(R) 2,486,875 0 388,125 2,875,000 Totals 2,746,375 0 428,625 3,175,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th RW 300,000 0 0 0 0 CN 0 2,875,000 0 0 0 Totals 300,000 2,875,000 0 0 0

Report Date: August 29, 2018 Page 179 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 13 WA-11399 06/26/18 06/26/18 2018-205 21 P T W CE No Hollingsworth - Wahluke - Chestnut Intersection Hollingsworth Road Intersection to Intersection Reconfigure existing cross-with-a-curve intersection

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2019 0 0 10,000 10,000 P CN 2020 0 0 90,000 90,000 Totals 0 0 100,000 100,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 10,000 0 0 0 0 CN 0 90,000 0 0 0 Totals 10,000 90,000 0 0 0

Report Date: August 29, 2018 Page 180 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 15 WA-01015 06/26/18 06/26/18 2018-205 04 P T W 2.520 CE No Pasco-Kahlotus Road V Pasco-Kahlotus Road MP 13.08 to MP 15.60 Murphy Rd Reconstruct and Resurface Road.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2020 0 CRAB 1,800,000 200,000 2,000,000 Totals 0 1,800,000 200,000 2,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 50,000 1,950,000 0 0 Totals 0 50,000 1,950,000 0 0

Report Date: August 29, 2018 Page 181 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 06 16 WA-01040 06/26/18 06/26/18 2018-205 04 P T 2.020 CE Yes Hollingsworth Road All-Weather Hollingsworth Road Sagehill Road to South Wahluke Road Reconstruct and resurface to an All-weather standard.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2020 0 CRAB 1,350,000 150,000 1,500,000 Totals 0 1,350,000 150,000 1,500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 50,000 1,450,000 0 0 Totals 0 50,000 1,450,000 0 0

Report Date: August 29, 2018 Page 182 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 17 WA-11400 06/26/18 06/26/18 2018-205 04 P T W 0.040 CE No Moon Road Subgrade Repair and Stabilization 02070 2.25 to 2.32 Repair and stabilize a section of Moon Road that has settled

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 25,000 25,000 P CN 2020 0 0 475,000 475,000 Totals 0 0 500,000 500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 25,000 0 0 0 CN 0 475,000 0 0 0 Totals 0 500,000 0 0 0

Report Date: August 29, 2018 Page 183 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 18 WA-06254 06/26/18 06/26/18 2018-205 21 P T CE No Bridge Approach Adjustment Countywide Countywide to Countywide Correct approaches on bridges countywide that are either higher or lower than the bridge deck.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 15,000 15,000 P CN 2020 0 0 135,000 135,000 Totals 0 0 150,000 150,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 15,000 0 0 0 CN 0 135,000 0 0 0 Totals 0 150,000 0 0 0

Report Date: August 29, 2018 Page 184 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 19 WA-10377 06/26/18 06/26/18 2018-205 44 P T CE No Drainage Improvements - Countywide Varies Varies to Varies Install and/or improve drainage structures throughout the County

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 0 5,000 5,000 P CN 2020 0 0 45,000 45,000 Totals 0 0 50,000 50,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 5,000 0 0 0 ALL 0 45,000 0 0 0 Totals 0 50,000 0 0 0

Report Date: August 29, 2018 Page 185 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 20 WA-09036 06/26/18 06/26/18 2018-205 04 P T 0.300 CE No Elm Road and Everett Road Intersection Elm Road/Everett Road Intersection to Intersection Reconstruct intersection to address drainage issues

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 15,000 15,000 P CN 2021 0 0 135,000 135,000 Totals 0 0 150,000 150,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 15,000 0 0 CN 0 0 135,000 0 0 Totals 0 0 150,000 0 0

Report Date: August 29, 2018 Page 186 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 21 WA-11401 06/26/18 06/26/18 2018-205 04 P T 1.000 CE No Dayton Road Phase I 09190 Cedar Road to Dogwood Road BST existing gravel road

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 20,000 20,000 P CN 2022 0 0 230,000 230,000 Totals 0 0 250,000 250,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 20,000 0 0 CN 0 0 0 230,000 0 Totals 0 0 20,000 230,000 0

Report Date: August 29, 2018 Page 187 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 23 WA-11402 06/26/18 06/26/18 2018-205 04 P T 2.010 CE No Ione Road 09450 Sagemoor Road to Dogwood Road BST existing gravel road

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 45,000 45,000 P CN 2022 0 0 475,000 475,000 Totals 0 0 520,000 520,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 45,000 0 0 CN 0 0 0 475,000 0 Totals 0 0 45,000 475,000 0

Report Date: August 29, 2018 Page 188 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 24 WA-06261 06/26/18 06/26/18 2018-205 05 P T CE No Roadway Approach Improvement Countywide Countywide to Countywide Improve roadway approaches to BST roads from gravel roads.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 20,000 20,000 P CN 2021 0 0 180,000 180,000 Totals 0 0 200,000 200,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 20,000 0 0 CN 0 0 180,000 0 0 Totals 0 0 200,000 0 0

Report Date: August 29, 2018 Page 189 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 25 WA-11403 06/26/18 06/26/18 2018-205 04 O P T 2.900 CE No Taylor Flats Road Overlay and Widening II 09030 Taylor Flats Bridge to Sagemoor Road Reconstruct and resurface to all-weather route

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 0 75,000 75,000 P CN 2022 0 0 2,425,000 2,425,000 Totals 0 0 2,500,000 2,500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 75,000 0 0 CN 0 0 0 2,425,000 0 Totals 0 0 75,000 2,425,000 0

Report Date: August 29, 2018 Page 190 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 26 WA-06258 06/26/18 06/26/18 2018-205 06 P T CE No Scooteney Road Drainage Correction 03070 MP 5.20 to MP 5.20 Roadway repair and drainage redirection.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 30,000 30,000 P CN 2022 0 0 170,000 170,000 Totals 0 0 200,000 200,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 200,000 0 Totals 0 0 0 200,000 0

Report Date: August 29, 2018 Page 191 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 27 WA-01010 06/26/18 06/26/18 2018-205 18 CE No Rural Freight Mobility Plan Study Countywide to This study will include performing an analysis of existing classified and non classified routes in selected areas of the county.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2022 0 0 75,000 75,000 Totals 0 0 75,000 75,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 75,000 0 Totals 0 0 0 75,000 0

Report Date: August 29, 2018 Page 192 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 28 WA-09034 06/26/18 06/26/18 2018-205 21 P CE No Illumination LED Retrofit Countywide Countywide n/a to n/a Convert existing high-pressure sodium lights to energy-efficient LED lights

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 5,000 5,000 P CN 2022 0 0 45,000 45,000 Totals 0 0 50,000 50,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 5,000 0 0 0 0 CN 45,000 0 0 0 0 Totals 50,000 0 0 0 0

Report Date: August 29, 2018 Page 193 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 31 WA-10399 06/26/18 06/26/18 2018-205 11 P T 0.100 CE No Hollingsworth Bridge #460-6.25 Hollingsworth Road 6.20 to 6.30 Replace existing bridge 460-6.25

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 365,000 365,000 Totals 0 0 365,000 365,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 365,000 Totals 0 0 0 0 365,000

Report Date: August 29, 2018 Page 194 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 32 WA-06257 06/26/18 06/26/18 2018-205 01 P T 3.060 CE Yes Coyan Road (Warehouse Road to Muse Road) I 02000 2.28 Muse Road to 5.34 Warehouse Road Construct gravel roadway to an all-weather route.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 2,500,000 2,500,000 Totals 0 0 2,500,000 2,500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 2,500,000 Totals 0 0 0 0 2,500,000

Report Date: August 29, 2018 Page 195 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 33 WA-06256 06/26/18 06/26/18 2018-205 11 P T W 0.100 CE No N Cherry Dr Bridge #944-0.05 Replacement 09440 0.00 to 0.10 Replace existing, structurally-deficient bridge. 944-0.05

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 BR 865,000 0 135,000 1,000,000 Totals 865,000 0 135,000 1,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 1,000,000 Totals 0 0 0 0 1,000,000

Report Date: August 29, 2018 Page 196 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 34 WA-09043 06/26/18 06/26/18 2018-205 03 P W 2.240 CE Yes Coyan Road (Muse Road to Hatton Road) II 02000 0.04 Hatton Road to 2.28 Muse Road Reconstruct and pave to an all-weather road. This project includes a R/R overpass.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 STP(R) 4,325,000 0 675,000 5,000,000 Totals 4,325,000 0 675,000 5,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 5,000,000 Totals 0 0 0 0 5,000,000

Report Date: August 29, 2018 Page 197 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 35 WA-01048 06/26/18 06/26/18 2018-205 04 P T W 3.600 CE Yes R-170 Road (Klamath Road to Ringold Road) All Weather R-170 Road MP 11.95 Klamath Hill Road to MP 15.55 Ringold Road Reconstruct and resurface to all-weather standard.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 3,000,000 3,000,000 Totals 0 0 3,000,000 3,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 3,000,000 Totals 0 0 0 0 3,000,000

Report Date: August 29, 2018 Page 198 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 36 WA-09046 06/26/18 06/26/18 2018-205 03 P T W 3.000 CE Yes Ringold Road (Taylor Flats to R-170) Reconstruction 05060 3.07 Taylor Flats to 6.07 R-170 Reconstruct to all weather road, add truck climbing lane, address intersection of Ringold Road and Taylor Flats

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 5,000,000 5,000,000 Totals 0 0 5,000,000 5,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 5,000,000 Totals 0 0 0 0 5,000,000

Report Date: August 29, 2018 Page 199 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 37 WA-10374 06/26/18 06/26/18 2018-205 21 P T 1.000 CE No Install Guardrail - Ringold Road Ringold Road 5.00 to 6.00 Install guardrail

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 115,000 115,000 Totals 0 0 115,000 115,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 115,000 Totals 0 0 0 0 115,000

Report Date: August 29, 2018 Page 200 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 38 WA-01031 06/26/18 06/26/18 2018-205 04 P T 2.760 CE Yes Pepiot Road All Weather - Phase I Pepiot Road Mesa City Limits to Milepost 2.76 Reconstruct and resurface to an all-weather standard. The route will need to be re- classified.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 3,000,000 3,000,000 Totals 0 0 3,000,000 3,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 3,000,000 Totals 0 0 0 0 3,000,000

Report Date: August 29, 2018 Page 201 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 39 WA-11404 06/26/18 06/26/18 2018-205 04 P T 1.500 CE Yes Pepiot Road All Weather - Phase II 07800 MP 2.76 to Coordes Road Reconstruct and resurface to all-weather standard. The route will need to be re- classified

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 2,000,000 2,000,000 Totals 0 0 2,000,000 2,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 2,000,000 Totals 0 0 0 0 2,000,000

Report Date: August 29, 2018 Page 202 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 40 WA-11405 06/26/18 06/26/18 2018-205 04 P T 2.000 CE Yes Pepiot Road All Weather Phase III 07800 Coordes Road to Blanton Road Reconstruct and resurface to all-weather standard. The route will need to be re- classified

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 2,000,000 2,000,000 Totals 0 0 2,000,000 2,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 2,000,000 Totals 0 0 0 0 2,000,000

Report Date: August 29, 2018 Page 203 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 41 WA-10378 06/26/18 06/26/18 2018-205 04 P T 3.500 CE No Glade North Overlay IV Glade North Road Sagemoor Rd to 1/2 mile South of Fir Road Reconstruct and resurface to all-weather standard

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 4,000,000 4,000,000 Totals 0 0 4,000,000 4,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 4,000,000 Totals 0 0 0 0 4,000,000

Report Date: August 29, 2018 Page 204 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 42 WA-11406 06/26/18 06/26/18 2018-205 04 O P T W 5.000 CE No Taylor Flats Road Overlay and Widening III 09030 Sagemoor Road to Eltopia West Road Reconstruct and resurface to all-weather route

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 4,000,000 4,000,000 Totals 0 0 4,000,000 4,000,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 4,000,000 Totals 0 0 0 0 4,000,000

Report Date: August 29, 2018 Page 205 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Franklin Co. County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 43 WA-11407 06/26/18 06/26/18 2018-205 03 P T 2.290 CE No Palouse Falls Road 01900 SR-261 to State Park Reconstruct and resurface route to State Park

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 1,500,000 1,500,000 Totals 0 0 1,500,000 1,500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 1,500,000 Totals 0 0 0 0 1,500,000

Federal Funds State Funds Local Funds Total Funds Grand Totals for Franklin Co. 8,260,751 3,150,000 33,864,249 45,275,000

Report Date: August 29, 2018 Page 206 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Mesa County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 02 / Mesa(002) WA-11559 05/29/18 07/19/18 2018-02 03 S W 0.200 CE No First Avenue Intersection

Pepiot Road to Old Town Road Reconstruct intersection with public safety concerns and proximity of school nearby.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2021 Discretionary 0 TIB 450,000 0 450,000 Totals 0 450,000 0 450,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 450,000 0 0 0 Totals 0 450,000 0 0 0

Report Date: August 29, 2018 Page 207 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Mesa County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 06 1 / Mesa(001) WA-11562 05/29/18 07/19/18 2018-02 03 S W 0.190 CE No Pepoit Road Pepoit Road SR17 to Eastern most school exit. Widen, pave, drains, sidewalks and engineering.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2020 Discretionary 0 TIB 375,000 0 375,000 Totals 0 375,000 0 375,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 375,000 0 0 0 0 Totals 375,000 0 0 0 0

Report Date: August 29, 2018 Page 208 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Mesa County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 02 3 / Mesa(003) WA-11561 05/29/18 07/19/18 2018-02 44 S W 0.040 CE No Manton way Manton Way First Avenue to Rowell Avenue Construct Sidewalk; also other streets located within Mesa to which meet the requirements to make improvements mentioned.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2022 Discretionary 0 TIB 75,000 0 75,000 Totals 0 75,000 0 75,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 75,000 0 0 Totals 0 0 75,000 0 0

Report Date: August 29, 2018 Page 209 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Mesa County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 4 / Mesa(004) WA-11563 05/29/18 07/19/18 2018-02 05 S W 0.030 CE No Petra Court Petra Court First Avenue to Eveland Heights Asphalt/Chip Seal Preservation Rsurface the roadway with chip seal or hot mix asphalt to preserve the structural integrity of the roadway and extend the service life of the pavement. Also other streets located within Mesa to which meet the requirement to make improvements mentioned.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 Discretionary 0 TIB 10,000 0 10,000 Totals 0 10,000 0 10,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 10,000 0 Totals 0 0 0 10,000 0

Report Date: August 29, 2018 Page 210 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Mesa County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 5 / Mesa(005) WA-11564 05/29/18 07/19/18 2018-02 05 S W 0.280 CE No First Avenue First Avenue Pepiot Road to Franklin Street Asphalt/Chip Seal Preservation. Resurface the roadway with chip seal or hot mix asphalt to preserve the structural integrity of the roadway and extend the service life of the pavement. This record is for chip seal/asphalt paving projects within the City of Mesa also other streets located within Mesa to which meet the requirement to make improvements mentioned.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 Discretionary 0 TIB 17,000 0 17,000 Totals 0 17,000 0 17,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 17,000 0 0 0 0 Totals 17,000 0 0 0 0

Report Date: August 29, 2018 Page 211 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Mesa County: Franklin MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 6 / Mesa(006) WA-11565 05/29/18 07/19/18 2018-02 05 S W 0.200 CE No Franklin Street Franklin Street First Avenue to Rowell Avenue Asphalt/Chip Seal Preservation Benton-Franklin Council of Governments Resurface the roadway with chip seal or hot mix asphalt to preserve the structural integrity of the roadway and extend the service life of the pavement. This record is for chip seal/asphalt paving projects within the City of Mesa, and other streets located within Mesa to which meet the requirements to make improvements mentioned.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 Discretionary 0 TIB 1,000 0 1,000 Totals 0 1,000 0 1,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 1,000 Totals 0 0 0 0 1,000

Federal Funds State Funds Local Funds Total Funds Grand Totals for Mesa 0 928,000 0 928,000

Report Date: August 29, 2018 Page 212 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 WA-10130 06/13/18 06/13/18 18-12 01 0.950 EIS No Extend Kingsgate Way Phase II

to Extend Kingsgate Way road north 5,000 LF into the 1,341 acre land transfer area.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 STP(US) 1,500,000 OTHER 1,000,000 1,000,000 3,500,000 Totals 1,500,000 1,000,000 1,000,000 3,500,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 3,500,000 Totals 0 0 0 0 3,500,000

Report Date: August 29, 2018 Page 213 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Port of Benton County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 00 WA-10129 06/13/18 06/13/18 18-12 44 2.080 EIS No Industrial Area Rail Spur

to Extend a new rail spur approximately 11,000 LF into the 1,341 acre land transfer area

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 OTHER 2,000,000 750,000 2,750,000 Totals 0 2,000,000 750,000 2,750,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 2,750,000 Totals 0 0 0 0 2,750,000

Federal Funds State Funds Local Funds Total Funds Grand Totals for Port of Benton 1,500,000 3,000,000 1,750,000 6,250,000

Report Date: August 29, 2018 Page 214 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 17 1 WA-10056 06/26/18 06/26/18 18-1580 04 C P S T W 0.600 CE Yes Bennett Avenue Improvements

Florence St to 7th St Reconstruct roadway including new curb and gutter, sidewalk, storm drainage improvements, hot mix asphalt, street lighting, and pavement markings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S PE 2019 STP(US) 292,690 0 45,680 338,370 S PE 2019 TAP(US) 21,232 0 3,314 24,546 P RW 2020 0 0 110,000 110,000 P CN 2021 0 TIB 2,186,100 242,900 2,429,000 Totals 313,922 2,186,100 401,894 2,901,916

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 362,916 0 0 0 0 RW 0 110,000 0 0 0 CN 0 0 2,429,000 0 0 Totals 362,916 110,000 2,429,000 0 0

Report Date: August 29, 2018 Page 215 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 2 / B030(001) PROSSER 7 06/26/18 06/26/18 18-1580 04 C P S T W 0.760 CE No Old Inland Empire Highway Improvements

West City Limits to Wine Country Road Reconstruct and widen roadway, curb and gutter, sidewalk, storm drainage, street lighting, hot mix asphalt, and pavement markings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P CN 2020 STP(US) 2,172,500 0 339,100 2,511,600 Totals 2,172,500 0 339,100 2,511,600

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 0 2,511,600 0 0 0 Totals 0 2,511,600 0 0 0

Report Date: August 29, 2018 Page 216 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 3 PROSSER 10 06/26/18 06/26/18 18-1580 04 C P S T W 0.250 CE No Old Inland Empire Highway - Phase 2

Wine Country Road to Wamba Road Reconstruct and widen roadway, curb and gutter, sidewalk, storm drainage, street lighting, hot mix asphalt, and pavement markings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 TIB 126,450 14,050 140,500 P CN 2021 0 TIB 969,750 107,750 1,077,500 Totals 0 1,096,200 121,800 1,218,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 140,500 0 0 0 CN 0 0 1,077,500 0 0 Totals 0 140,500 1,077,500 0 0

Report Date: August 29, 2018 Page 217 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 4 WA-06502 06/26/18 06/26/18 18-1580 04 C P S T W 0.510 CE Yes Old Inland Empire Highway - Phase 3

Wamba Road to Grant Road Reconstruct and widen roadway, curb and gutter, sidewalk, storm drainage, street lighting, hot mix asphalt, and pavement markings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 STP(US) 226,900 0 35,400 262,300 P RW 2021 STP(US) 55,400 0 8,600 64,000 P CN 2022 STP(US) 1,739,500 0 271,500 2,011,000 Totals 2,021,800 0 315,500 2,337,300

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 262,300 0 0 RW 0 0 64,000 0 0 CN 0 0 0 2,011,000 0 Totals 0 0 326,300 2,011,000 0

Report Date: August 29, 2018 Page 218 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 5 PROSSER 3 06/26/18 06/26/18 18-1580 21 C P S T W 1.000 CE No Kinney Way/ Concord/ Market Sidewalk Improvements

Park Avenue to State Route 22 Curb and gutter and sidewalk improvements.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 0 OTHER 59,490 6,610 66,100 P CN 2021 0 OTHER 620,800 69,000 689,800 Totals 0 680,290 75,610 755,900

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 66,100 0 0 0 CN 0 0 689,800 0 0 Totals 0 66,100 689,800 0 0

Report Date: August 29, 2018 Page 219 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 6 PROSSER 5 06/26/18 06/26/18 18-1580 04 C P S T W 0.440 CE No Wamba Road Improvements - Phase 1

Old Inland Empire Highway to Merlot Drive Reconstruct and widen roadway, curb and gutter, sidewalk, storm drainage, street lighting, hot mix asphalt and striping.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 OTHER 152,100 38,000 190,100 P CN 2022 0 OTHER 1,166,600 291,700 1,458,300 Totals 0 1,318,700 329,700 1,648,400

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 190,100 0 0 CN 0 0 0 1,458,300 0 Totals 0 0 190,100 1,458,300 0

Report Date: August 29, 2018 Page 220 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 7 PROSSER 6 06/26/18 06/26/18 18-1580 04 C P S T W 0.150 CE No Wamba Road Improvements - Phase 2

Wine Country Road to Old Inland Empire Highway Reconstruct and widen roadway, curb and gutter, sidewalk, storm drainage, street lighting, hot mix asphalt, and pavement markings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 OTHER 56,700 14,200 70,900 P CN 2023 0 OTHER 434,700 108,700 543,400 Totals 0 491,400 122,900 614,300

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 70,900 0 CN 0 0 0 0 543,400 Totals 0 0 0 70,900 543,400

Report Date: August 29, 2018 Page 221 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 8 PROSSER 8 06/26/18 06/26/18 18-1580 04 C P S T W 0.950 CE No Byron Road Improvements

Sheridan Avenue to West City Limits Reconstruct and widen roadway, curb and gutter, sidewalk, storm drainage, street lighting, hot mix asphalt, and pavement markings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 OTHER 275,300 68,800 344,100 P CN 2022 0 OTHER 2,110,300 527,600 2,637,900 Totals 0 2,385,600 596,400 2,982,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 344,100 0 0 CN 0 0 0 2,637,900 0 Totals 0 0 344,100 2,637,900 0

Report Date: August 29, 2018 Page 222 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 08 9 PROSSER 9 06/26/18 06/26/18 18-1580 04 C P S T W 0.390 CE No Nunn Road Improvements

West City Limits to 200 east of Casi Court Reconstruct and widen roadway, curb and gutter, sidewalk, storm drainage, street lighting, hot mix asphalt, and pavement markings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 TPP 127,100 14,100 141,200 P CN 2022 0 TPP 974,800 108,300 1,083,100 Totals 0 1,101,900 122,400 1,224,300

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 141,200 0 0 CN 0 0 0 1,083,100 0 Totals 0 0 141,200 1,083,100 0

Report Date: August 29, 2018 Page 223 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 10 PROSSER 11 06/26/18 06/26/18 18-1580 04 C P S T W 0.500 CE No Prosser Avenue Improvements

Market Street to Memorial Street Reconstruct and widen roadway, curb and gutter, sidewalk, storm drainage, street lighting, hot mix asphalt, and pavement markings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2021 0 0 1,804,000 1,804,000 Totals 0 0 1,804,000 1,804,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 1,804,000 0 0 Totals 0 0 1,804,000 0 0

Report Date: August 29, 2018 Page 224 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 11 PROSSER 12 06/26/18 06/26/18 18-1580 04 C P S T W 0.310 CE No Alexander Court Improvements - Phase 1

Highland Drive to Paterson Road Reconstruct and widen roadway, curb and gutter, sidewalk, storm drainage, street lighting, hot mix asphalt, and pavement markings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 1,052,000 1,052,000 Totals 0 0 1,052,000 1,052,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 1,052,000 Totals 0 0 0 0 1,052,000

Report Date: August 29, 2018 Page 225 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 12 PROSSER 13 06/26/18 06/26/18 18-1580 04 C P S T W 0.230 CE No Alexander Court Improvements - Phase 2

Wine Country Road to Highland Drive Reconstruct and widen roadway, curb and gutter, sidewalk, storm drainage, street lighting, hot mix asphalt, and pavement markings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2023 0 0 757,000 757,000 Totals 0 0 757,000 757,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 757,000 Totals 0 0 0 0 757,000

Report Date: August 29, 2018 Page 226 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 09 13 PROSSER 14 06/26/18 06/26/18 18-1580 04 C P S T W 0.200 CE No Benson Avenue Improvements

Mercer Court to Alexander Court Reconstruct and widen roadway, curb and gutter, sidewalk, storm drainage, hot mix asphalt, and pavement markings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 637,300 637,300 Totals 0 0 637,300 637,300

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 637,300 Totals 0 0 0 0 637,300

Report Date: August 29, 2018 Page 227 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 07 14 PROSSER 15 06/26/18 06/26/18 18-1580 04 C P S T W 0.280 CE No Highland Drive Improvements

Alexander Court to State Route 22 Reconstruct and widen roadway, curb and gutter, sidewalk, storm drainage, hot mix asphalt, and pavement markings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 1,182,300 1,182,300 Totals 0 0 1,182,300 1,182,300

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 1,182,300 Totals 0 0 0 0 1,182,300

Report Date: August 29, 2018 Page 228 Six Year Transportation Improvement Program From 2019 to 2024 Agency: Prosser County: Benton MPO/RTPO: BFCG N Inside Y Outside Environmental Type Improvement Type Priority Number Resolution No. RW Required Utility Codes Total Length Amendment

Functional A. PIN/Project No. B. STIP ID Adopted C. Project Title Hearing

Class D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID 06 15 PROSSER 16 06/26/18 06/26/18 18-1580 06 P S T W 0.170 CE No Downtown Intersection Improvements - 5th Street

Bennett Street to Meade Street Intersection Improvements including planing, hot mix asphalt overlay, curb and gutter, sidewalk, storm drainage, and pavement markings.

Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2024 0 0 362,000 362,000 Totals 0 0 362,000 362,000

Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 0 0 0 362,000 Totals 0 0 0 0 362,000

Federal Funds State Funds Local Funds Total Funds Grand Totals for Prosser 4,508,222 9,260,190 8,219,904 21,988,316

Report Date: August 29, 2018 Page 229