Some Cost Implications of Electric Power Factor Correction and Load Management
SOME COST IMPLICATIONS OF ELECTRIC POWER FACTOR CORRECTION AND LOAD MANAGEMENT
BY
HERCULES VISSER
Dissertation submitted in partial fulfilment of the requirements for the degree
Magister Philosphiae in Engineering Management
In the
Faculty of Engineering
at the
Rand Afrikaans University
Supervisor: Prof. J.H. Pretorius Co. Supervisor: Prof. L. Pretorius
May 2001 ACKNOWLEDGEMENTS
I would like to thank my Creator for the ability and guidance He gave me during this study.
Without His support, this work would not have been possible.
What shall I render to the Lord
For all His benefits toward me?
Ps. 116:12
Then I would like to thank various people for their direct and indirect contributions to this
research study:
My wife, Ria, for her encouragement and support.
Prof J.H. Pretorius and Prof L. Pretorious for the privilege to study under them
and for their patience and wise guidance.
"Everything should be made as simple as possible, but not simpler."
Albert Einstein. 1879 - 1955 SUMMARY
Presently, ESKOM is rated as the fifth largest utility in the world that generates and distributes electricity power to their consumers at the lowest price per kilowatt-hour
(kW.h). As a utility, ESKOM is the largest supplier of electrical energy in South Africa and is currently generating and distributing on demand to approximately 3000 consumers.
This represents 92% of the South African market. ESKOM was selected as the utility supplying electrical energy for the purpose of this study.
ESKOM's objective is to provide the means and systems by which the consumer can be satisfied with electricity at the most cost-effective manner. In order to integrate the consumers into these objectives, ESKOM took a decision in 1994 to change the supply tariff from active power (kW) to apparent power (kVA) for a number of reasons:
To establish a structure whereby the utility and the consumer can control the
utilisation of electrical power supply to the consumer.
To utilise demand and control through power factor correction and
implementation of load management systems.
To identify some cost implications of electrical power factor correction and load
management.
Consumers with kW maximum demand tariff options had little or no financial incentives to improve their low power factor (PF) by reducing their reactive current supply.
Switching to (kVA) maximum demand will involve steps to be taken to ensure that the reactive component is kept to a minimum with maximum power factor. ESKOM has structured various tariff rates and charges with unique features that would accommodate the consumers in their demand side management and load cost requirements, which, when applied, will result in an efficient and cost effective load profile. These tariffs are designed to guide consumers automatically into an efficient way of using electrical power, as it is designed to recover both the capital investment and the operating cost within two to three years after installation of power factor correction equipment.
ESKOM's concept of Time-of-use (TOU) periods for peak, standard and off-peak times during week, Saturday and Sunday periods is discussed as load management.
Interruptible loads can be scheduled or shed to suit lower tariff rates and to avoid maximum demand charge. The concept of load management will change the operation pattern of the consumer's electricity demand whereby the consumer will have immediate technical and financial benefits.
In the last chapter of this dissertation, a hypothetical case study addresses and concludes on some of the technical and cost implications of electrical power factor correction and load management as a successful and profitable solution to optimize electrical power supply to the consumer. By implementing the above, ESKOM ensures that the consumer utilizes the electrical power supply to its optimum level at the lowest cost per kilowatt- hour (kW.h) generated. OPSOMMING
ESKOM is tans die vyfde grootste verskaffer in die wereld wat elektriese drywing genereer en versprei na kliente teen die laagste eenheidsprys per kilowatt-uur (kW-uur).
ESKOM is die grootste verskaffer van elektriese energie in Suid-Afrika en ontwikkel en versprei elektriesie energie op aanvraag na ongeveer 3000 kliente wat ± 92% van die
Suid-Afrikaanse mark verteenwoordig. Vir die doel van hierdie studie word ESKOM gekies as die verskaffer van elektriese energie.
ESKOM se doelwit is om middele en stelsels te voorsien wat tevredenheid sal besorg aan kliente sodat hulle die beste en mees effektiewe koste-voordeel van elektriese verbruik kan geniet. Om te verseker dat die klient 'n deelname in hierdie doelwitte het, het ESKOM 'n besluit gedurende 1994 geneem om die voorsieningstariewe van aktiewe drywing (kW) na skynbare drywing (kVA) te verander vir 'n aantal redes:
Om 'n struktuur daar te stel waarby die voorsiener en die klient die bestuur en
benutting van elektriese drywingstoevoer optimaal kan beheer.
Aanvraag en ladingsbeheer kan benut word deur arbeids-faktor regstelling en die
implementering van lading bestuurstelsels.
Om sekere koste-implikasies van elektriese en arbeids-faktor regstelling en
ladingsbestuur te identifi seer.
Kliente met (kW) maksimum aanvraag tarief-opsies het min of geen finansiele voordeel om sodoende die lae arbeidsfaktor (PF) te verbeter deur die reaktiewe stroom lewering te verminder. Die oorskakeling na kVA maksimum aanvraag sal tot gevolg he dat versekerde stappe geneem sal word om die reaktiewe komponente tot a minimum te beperk met 'n maksimum arbeidsfaktor.
ESKOM het verskeie strukture met tariewe en unieke kenmerke wat die klient sal skik in sy terrein van bestuurs-aanvraag en ladingskoste vereistes. Wanneer dit wel geimplimenteer word, het dit doeltreffende en koste-effektiewe ladingsprofiele. Hierdie tariewe is ontwerp om die klient outomaties na 'n meer doeltreffende metode van die gebruik van elektriese ladingsbestuur te lei, omdat dit ontwerp is vir beide kapitaal belegging en bedryfskoste herwinning binne twee tot drie jaar na die installering van arbeidsfaktor regstellingstoerusting.
ESKOM se konsep vir ladingsbestuur word bespreek en dit behels die gebruik van periodes van tye van drywingsverbruik (TOU) waaronder spits-, standaard- en laagtyd verduidelik word, betreffende weekstye, Saterdae en Sondagperiodes. Onderbroke ladings kan geskeduleer of gekanselleer word sodat die lae verbruikstariewe in aanmerking kan kom en maksimum aanvraag kostes vermy kan word. Hierdie konsep van ladingsbestuur sal die bedryfspatroon van die klient se elektriese aanvraag verander en daardeur sal die klient onmiddellike tegniese en finansiele voordeel geniet.
`n Hipotetiese gevallestudie word aangespreek wat van die tegniese en koste implikasies van arbeidsfaktor-regstelling en ladingsbestuur as 'n suksesvolle en winsgewende oplossing uitwys en sodoende die kragvoorsiening na die klient optimaliseer. Deur die bogenoemde to implimenteer, verseker ESKOM dat die klient elektriese kragvoorsiening optimaal sal aanwend teen die laagste koste per kilowatt-uur (kW-uur). TABLE OF CONTENTS
ACKNOWLEDGEMENTS
SUMMARY
CHAPTER 1 ELECTRICITY SUPPLY IN SOUTH AFRICA PAGE
Introduction 1
1.1 Historical background 1
1.2 Presently 2
1.3 Problem statement 3
1.4 The structure of the study 5
1.5 Objectives of power factor correction 6
1.6 Conclusion 9
CHAPTER 2 POWER FACTOR CORRECTION
2.1 Introduction 10
2.2 What is power factor correction (PFC) 11
2.2.1 Constant kW correction 12
2.3 The importance of power factor correction 14
2.4 Some technical disadvantages of a poor power factor 16
2.5 Some methods of obtaining a good power factor 17
2.6 The need for power factor correction 19
2.6.1 Technical reasons 20
2.6.2 Economic reasons 20
TOC 1 2.7 The impact of poor power factor on the utility 21
2.8 Factors affecting power factor levels 22
2.9 Power factor measurement 22
2.10 Capacitor Rating 25
2.11 Conclusion 25
CHAPTER 3 TARIFF STRUCTURES OF THE UTILITY
3.1 Introduction 27
3.2 The approach 28
3.3 Tariffs 29
3.4 Tariff options 30
3.5 Time-of-use (TOU) tariffs 31
3.6 Tariffs on power factor 32
3.7 Cost implications for time-of-use 34
3.8 Implication of tariffs 34
3.9 Two-part tariffs 37
3.9.1. Capital investment costs 37
3.9.2. Running costs 38
3.10 Conclusion 38
CHAPTER 4 LOAD MANAGEMENT 4.1 Introduction 40 4.2 Load management planning 41
TOC 2
4.2.1. Planning 41
4.3 Load Measurement categories 44
4.3.1 Load factor 44
4.3.2 Interruptible loads 45
4.3.2.1 Interruptible electric service 46
4.3.2.2 Appliance control 46
4.3.2.3 Demand limitations 46
4.3.3 Strategic conservation 46
4.3.4 Energy management 47
4.4 Time-of-use load scheduling 48
4.4.1 ESKOM's Megaflex / Miniflex / Ruraflex 49
4.4.2 ESKOM's night-save 51
4.5 Time-of-use maximum demand 52
4.6 The need for load shedding 53
4.6.1 Primary load shedding 54
4.6.2 Frequency load shedding 54
4.6.3 Manual load shedding 55
4.6.4 Maximum peak power demand shedding 55
4.7 Demand control 55
4.8 Conclusion 57
CHAPTER 5 CASE STUDY
5.1 Introduction 59
TOC 3 5.2 Problem statement 60
5.3 Case study 60
5.4 Approach to the case study 61
5.5 Power supply and improvements 61
5.6 Summary of the case study 63
5.7 Conclusion 64
CHAPTER 6 CONCLUSIONS AND RECOMMENDATIONS 6.1 Final conclusion 66 6.2 Recommendations 67
ANNEXURE TO THE CASE STUDY
7 Power supply and improvements 69
7.1 Power load distribution 69
8 ESKOM's tariffs and charges for 2001 70
8.1 Annual energy cost before power factor correction 71
8.2 Annual cost saving after power factor correction 71
8.3 Annual energy cost saving after power factor correction 72
8.4 Capital cost to improve power factor correction to 0.96 72
8.5 Pay-back time on capital investment 72
9 Load management (LM) 73
TOC 4 9.1 Annual energy cost before load management 73
9.2 Annual cost saving after power factor correction
and load management 73
9.3 Total annual cost saving after load management
and power factor correction 73
10 Compound amount of capital 74
10.1 Equal payment series with compound amount after
power factor correction 74
10.2 Equal payment series with compound amount after
load management 75
10.3 Grand total compound amount on capital saving 75
LIST OF FIGURES
LIST OF TABLES
BIBLIOGRAPHY
TOC 5 LIST OF FIGURES AND TABLES
FIG. NO. DESCRIPTION CHAPTER PAGE
2.1 Power vector for constant kW 2 12
2.2 Vector of active, apparent and reactive currents 2 13
2.3 Vector angle between kW and kVA with lagging
power factor 2 14
2.4 Wave-forms of leading power factor 2 23
2.5 Daily demand versus power factor 2 23
3.1 Comparison of Standard-rate 3 32
3.2 Vector for free charge loads 3 33
3.3 Increase of capacitance required as unity
power factor is reached 3 36
4.1 Average cost as a function of load factor 4 45
4.2 Demand periods for weekdays 4 51
4.3 Demand periods for night-save 4 51
4.4 Typical demand profile without demand control 4 56
4.5 Typical demand profile with demand control 4 57
7.1 Power load distribution Annexure 69 8 ESKOM's tariffs and charges for 2001 Annexure 70
8.1 Factory plant working (TOU) schedules Annexure 70
8.2 Proposed change of (TOU) schedules for plant Annexure 70
TABLE NO. DESCRIPTION CHAPTER PAGE
4.1 Average time-of-use cost 4 49
8 ESKOM tariffs and charges for Megaflex Annexure 70 CHAPTER 1
PROBLEM STATEMENT AND OBJECTIVES
INTRODUCTION
1.1 HISTORICAL BACKGROUND
On 5 June 1873, the British Minister of U.K. decided to change the farm Vooruitzicht in South Africa to Kimberley, the place that some time ago delivered the greatest diamond of all time, the Star of Africa. Kimberley had a population of 20 000 and developed in a short period to the full status of a city. Steam trolley-bus services existed in 1881, which were replaced with electrical trolley-busses in 1902.
South Africa has always been well advanced in the use of electricity. Kimberley had electric street lighting in 1882 before the City of London and only three years after
Edison started supplying electricity from the Pearl Street Power Station in New York.
The first electric reticulation system was commissioned in Kimberley in 1890, and
Johannesburg Municipality began to supply electricity in 1891 [26]. Electricity supplies were provided in Pretoria, Cape Town, Durban, East London, Port Elizabeth,
Bloemfontein and Pietermaritzburg by 1906 [43, 44].
"The need was recognized for a national electricity authority early in the 1920s and in terms of the Electricity Act of 1922 the Electricity Supply Commission (ESCOM, later changed to ESKOM) was formed by a notice in the Government Gazette of 6
March 1923" [26, 40].
Page 1 A cheap and abundant supply of electricity was provided by ESKOM throughout
South Africa [42, 5]. In less than thirty (30) years, ESKOM owned and operated six
electricity undertakings. Each undertaking generated and supplied power to the major
load centres throughout the country via a transmission network system. For ESKOM
to meet the rapid increase in power demand, they had to build seven new power
stations between 1950 — 1961 [41, 43].
"South Africa's first nuclear station using sets of about 1000 MW rating was
commissioned near Cape Town in 1982" [26]. Up to 1970, virtually all generation
was done in coal-fired stations. The world's largest dry-cooling coal power station,
Matimba, was finally commissioned in 1995 near Ellisras in South Africa. ESKOM
is rated as the world's fifth largest utility in the supply of electrical power and the
lowest cost producers of electricity in the world. (ESKOM's Annual Report 1999)
[41].
1.2 PRESENTLY
South Africa has, until recently, been in a position where the utility supplying
electrical energy to the different consumer sectors, had adequate capacity to supply its
consumers. This situation is rapidly changing due to various factors.
ESKOM has introduced a pilot project aimed at the development and introduction of a
real-time pricing tariff to its consumers. There are a number of factors that affect the
electricity cost to consumers, each of which can be managed by the consumer in order
to reduce a consumer's electricity bill.
Page 2 1.3 PROBLEM STATEMENT
For many years, the gold mines and large power users enjoyed a special dispensation with respect to electricity in the previous ESKOM-era structure via kilowatt-hour
(kW.h) tariff rate [25, 40].
The mines and other large consumers enjoyed kW maximum demand tariff as opposed to the kVA maximum demand tariff for the rest of the country. A one-hour block demand integrating period was allowed to calculate the kW maximum demand in contrast to the half-hour block demand integrating period for the kVA maximum demand tariff. ESKOM specified that consumers use the kW maximum demand tariff to maintain an average power factor for each one-hour integrating period to be greater than 0,85 (i.e. the kvar.h units consumed to be less than 62% of the kilowatt-hour units consumed, for each integrating period). This was seldom enforced on the consumers with no effect of any financial penalty [25, 40].
Many consumers on the kW maximum demand tariff option had power factors below the contractual limits as there was little or no financial incentive due to the special dispensation for improvement. Consumers on the half-hour kVA demand tariff paid significantly more than consumers on the one-hour kW demand tariff for electricity.
However, notification was given to all kW demand tariff users that their privileged position would be terminated. Financial opportunities were made available to change to a half-hour kVA demand tariff and the simultaneous installation of power factor correction equipment [25].
Page 3 It was announced in an advertisement in the Business Day (11 January 1998) that
"ESKOM proposed an amendment to standard prices and the promulgation of a charge for excess demand on Standard-rate and Night-save tariffs" [25].
With effect from 1 April 1998, ESKOM introduced charges for excess demand on kW demand consumers whose power factor was below 0,85 , based on the kVA and kW demand readings in the one-hour block interval during which the kW maximum demand was registered, as follows:
"Excess demand = (kVA demand x 0,85) — (kW demand)". (1.1)
It was then decided that active power (kW) demand consumers with a power factor at maximum demand of less than 0,85, would be financially penalised [25].
For the following four years, the Standard-rate and Night-save active power (kW) demand charges were progressively increased by 1,42% per annum above the average annual increase applicable to the apparent power (kVA) demand tariff. The implementation of the above actions turned out that the apparent power (kVA) demand tariff was more attractive to the consumers. This resulted that after a few years, kW demand consumers with a power factor greater than 0,85, benefit more by changing to kVA demand tariff, with effectively no cost penalty, and with the opportunity of very significant cost savings in their electricity bill by installing power factor correction equipment" [25].
Page 4 Distribution power economy, a company in load management, offered a comprehensive tariff analysis and tariff impact study service. This included design, engineering, supply, installation and management of effective power factor correction and demand side management projects. In most cases, these projects can be fully financed by the savings in the electricity bill effected by the installation of the power factor correction equipment. This capital outlay on the power factor equipment was usually paid back within one to two years, which was indeed a good investment opportunity [25].
1.4 THE STRUCTURE OF THE STUDY
In the light of the above mentioned historical background and problem statement, this study will cover some cost implications of power factor correction and load management that are considered to be necessary to improve the utilisation of electrical power supply to the consumer. The following factors will be covered in Chapter 2, i.e. what is power factor correction, the relationship between active power (kW), apparent power (kVA) and reactive power (kvar), the importance of power factor correction, technical and economical reasons affecting the power factor (PF) levels.
The tariff structure in Chapter 3 will address the impact of the various tariff options for the consumer that are applicable to power factor conditions, time-of-use tariffs and two-part tariffs. Load management is the second factor in this study
Chapter 4 will cover load management planning, categories of load management, time-of-use (TOU), load scheduling, maximum demand control are all factors when implemented and managed correctly. This should reduce the load demand to the
Page 5 consumer and ultimately turn into financial savings. A hypothetical case study in
Chapter 5 addresses and concludes the above mentioned methods and implications with cost analysis, conclusions and final recommendations.
1.5 OBJECTIVES OF POWER FACTOR CORRECTION
Financial benefits in the installation of certain specialised equipment can be achieved in an industrial or mining installation in the following three areas:
"Savings on electrical tariff charges.
Enabling additional installed capacity without additional cost.
Increased operational efficiency of electrical equipment, including reduction of
maintenance costs" [24].
Any sizable electrical system is usually charged with a tow-part tariff by nature:
"A unit charge based on the number of units consumed per month.
A charge based on the highest half hour (or one hour) maximum demand over a
monthly period" [24].
Currently, there are two methods in operation to measure maximum demand:
kVA (kilo-Volt Amp), and
kW (kilowatt).
ESKOM prefers to measure maximum demand in apparent power (kVA), and it is now mandatory for all new installations to be installed and charged on this basis. The active power (kW) method is in the process of being phased out, and certain financial incentives for existing installations to switch from active power (kW) to apparent
Page 6 power (kVA) basis have been offered by ESKOM. The apparent power (kVA) of a load comprises two components:
The kW or active component (which can be converted directly into useful work),
and
The kvar or reactive component (which cannot be converted directly into useful
work) [24, 25].
The reactive component of electrical load indicates the measure of the power factor of an installation. The utilisation of items of equipment that has inductance and requires magnetic fields to operate (i.e. electric motors and transformers) tends to have higher reactive components. To improve the efficiency of the plant, system or electrical distribution network, the reactive component is to be kept to a minimum throughout the system.
The power factor in a system ranges theoretically from zero to one. When a plant or system has a power factor of one, the operation has maximum efficiency. As the system current drops, it provides a clear evidence that the system's efficiency has improved when plant losses decrease and output increases, i.e. less motor burn-outs and the starting of motors improves. ESKOM' s new charge for maximum demand on installations (apparent power) is directly related to the power factor, as is shown in the following equation: [24]
Power factor = active power (kW) (1.2) apparent power (kVA)
S2 p2 ± Q2
Where S = apparent power P = active power Q = reactive power
Page 7 When the reactive component decreases, the apparent power component will decrease, the power factor will increase and the maximum demand charge will decrease, which will result in a tangible cost saving.
However, the maximum demand charge is not affected by the power factor for those installations still operating on active power (kW) maximum demand basis.
Depending on the nature of the electricity usage by the operation, a strategy could be devised to reduce the maximum demand charge. Switching to apparent power (kVA) maximum demand will involve steps to be taken to ensure the measurement basis of the strategy is and that the reactive component is kept at a minimum, with maximum power factor [8, 24, 25, 40].
Various methods are available to ensure that a high power factor of 0,98 to 0,99 is maintained during plant operation. This will require the correct design and installation of specialised equipment for the purposes of power factor correction. The operational efficiencies of the installation will also enhance the importance and attractiveness of such power factor equipment [24].
Page 8 1.6 CONCLUSION
Power factor correction with its attendant cost savings both in the short and long term are an issue, which should be investigated thoroughly by all managers who are serious about improving their financial performance.
The system to perform a complete service analysis in the area of power factor correction is available from preliminary investigation through to design, supply and implementation. To reveal the possible cost savings and pay-back period, preliminary sophisticated measuring and reporting facilities could be used and followed by a more tailored design, manufacture, installation and maintenance plan.
Page 9 CHAPTER 2
POWER FACTOR CORRECTION
2.1 INTRODUCTION
ESKOM changed the power supply tariffs from active power (kW) to apparent power
(kVA) in 1994 and introduced a maximum demand tariff that aims at forcing the
consumer to improve the power factor to 0.96.
Eric Granger [5] states that power factor correction is a method of using alternating
current in the most economic fashion. It can reduce current, reduce losses and, as a
possible consequence, reduce electricity charges. It is a method ensuring that the
voltage and current remain substantially in phase with each other, producing the
optimum power [5]. This chapter will cover the following aspects of power factor
correction:
What is power factor correction [4]?
Constant active power (kW) correction.
The importance of power factor correction [5].
Some technical disadvantages of a poor power factor [3].
Some methods of obtaining a good power factor [3].
The need for power factor correction [1].
The impact of poor power factor on the utility [1, 5].
Factors affecting power factor levels.
Page 10 • Power factor measurements.
2.2 WHAT IS POWER FACTOR CORRECTION?
All electrical operational plants comprise two kinds of current, namely active current
and the reactive component. These components effect the power factor Cos 4). The
definition of power factor as stated by Theodore Wildi is "the power factor of an
alternating current circuit is the ratio of the active power P to the apparent power S,
given by the equation;
Power factor = P / S = Cos 4) (2.1)
Where P = active power (W)
S = apparent power (VA)" [6]
The active current (or working) is the current that the equipment requires for useful work, while the reactive current is the wattless current that is produced by different types of loads. W.G. Hutcheon defines that the power factor may be expressed as the ratio of working current in a circuit to the total current in that circuit, and its value is exactly equal to the ratio of active power (kW) or the working power to the total apparent power (kVA) [4].
Power factor = Iw = active power (kW) = Cos • (2.2) It apparent power (kVA)