Project name: Project for Strenghtening National Rural Transport Program New Activities Modified Loan: IDA-5336 & H8990 Activities Public Disclosure Authorized Canceled Procurement Plan Version: 2016-5 Activities Activities Status: Sent to the Bank without Date of Last Change of Status: 19/05/2016

Category Works: Activities ShowHide Total days of Process

Public Disclosure Authorized (between Bid Opening End of No Objection to Contract and Contract Contract No Objection Publication / Evaluation Evaluation Signature Signature (Complet Description Reference # Documents Invitation Bid Opening of Bids Report Date Date) ed) Comment P.P. - Executing Agency: 2016-5- Method: NCB (National Competitive 5.Construction of Sandhikhark- SNRTP-22-NCB-O-SNRTP-ARG-W-NCB- N/A 01/02/14 03/03/14 18/03/14 N/A 10/05/14 68 11/05/15 Dharapani-Maidan Rd. (08 Km) 1.05-UG-070-71 DTO Arghakhanchi Contract under execution Add Comment

Public Disclosure Authorized Post Review N/A 15/03/14 14/04/14 15/05/14 N/A 11/07/14 88 6. Construction of Sandhikhark- SNRTP-23-NCB-O-SNRTP-ARG-W-NCB- N/A 01/02/14 03/03/14 18/03/14 N/A 10/05/14 68 11/05/15 Nuwakot-Asurkot-Pyuthan Rd. (07 Km): 1.06-UG-070-71

DTO Arghakhanchi Contract under execution Add Comment

Post Review N/A 15/03/14 15/04/14 14/05/14 N/A 15/07/14 91 4. Construction of Rajmarg-Budha- SNRTP-55-NCB-O-SNRTP-KAN--W-NCB- 25/01/14 01/02/14 03/03/14 18/03/14 11/05/14 11/05/14 69 10/12/15 Jhajpur-Gauji-Briddhassharam 10.04-UG-070-71 Road.(6.50 Km) DTO Kanchanpur Contract under execution Add Comment

Prior Review 11/01/14 18/03/14 17/04/14 15/09/14 28/09/14 20/10/14 186 Public Disclosure Authorized 3. Construction of Mandredhunga – SNRTP-80-NCB-O-SNRTP-NUW-W-NCB- N/A 17/01/14 16/02/14 03/03/14 N/A 02/05/14 75 10/12/15 Khargabhanjyang-Gorsyang –Dangsing 16.03-UG-070-71 Road (12.00 km) DTO Nuwakot Contract under execution Add Comment

Post Review N/A 04/03/14 06/04/14 14/05/14 N/A 30/05/14 54 1. Construction of Badhkhola-Taksar- SNRTP-119-NCB-O-SNRTP-SYA-W-NCB- N/A 25/01/14 24/02/14 03/03/14 N/A 02/05/14 67 25/11/15 Dadegaunda Road (10 Km) 28.01-UG-070-71 DTO Syanja Contract under execution Add Comment

Post Review N/A 27/01/14 26/02/14 01/05/14 N/A 26/05/14 89 2. Construction of Whalighuwas- SNRTP-120-NCB-O-SNRTP-SYA-W-NCB- N/A 25/01/14 24/02/14 03/03/14 N/A 02/05/14 67 25/11/15 Rampurr Road (7.50 Km) 28.02-UG-070-71 DTO Syanja Contract under execution Add Comment

Post Review N/A 27/01/14 26/02/14 28/03/14 N/A 26/05/14 89 3. Construction of Rangkhola-Biruwa SNRTP-121-NCB-O-SNRTP-SYA-W-NCB- N/A 25/01/14 24/02/14 03/03/14 N/A 02/05/14 67 25/11/15 Road. (7.50 Km) 28.03-UG-070-71 DTO Syanja Contract under execution Add Comment

Post Review N/A 27/01/14 26/02/14 30/03/14 N/A 26/05/14 89 3.Construction of Sandhikharka-Balkot- SNRTP-171-NCB-O-SNRTP-ARG-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Tamghash Rd (25.50 Km) 1.03-UG-070-71 N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16

DTO Arghakhanchi Expected Add Comment

Post Review 1. Construction of Chama- SNRTP-175-NCB-O-SNRTP-BAN-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 Samjhanachowk-Khajura-Radhapur 2.01-UG-070-71 Road (11 Km): DTO Banke Contract under execution Add Comment

Post Review N/A 15/07/15 14/08/15 06/10/15 N/A 23/11/15 101 2. Construction of RRM-Mahendranagar- SNRTP-176-NCB-O-:SNRTP-BAN-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Hirminiya-Holyia Road.(06 km) NCB-2.02-UG-070-71

DTO Banke Expected Add Comment

Post Review 3.Construction of MRM-Titirihiya- SNRTP-177-NCB-O-SNRTP-BAN-W-NCB- N/A 10/01/15 10/01/15 10/01/15 N/A 10/01/15 0 08/07/16 Sohanpur-Udrahapur Road (18.50 Km) 2.03-UG-070-71

DTO Banke Expected Add Comment

Post Review 4. Construction of Paraspur- Gaughat SNRTP-178-NCB-O-SNRTP-BAN-W-NCB- N/A 26/01/15 25/02/15 27/03/15 N/A 26/04/15 60 25/04/16 Road. (12.75 Km) 2.04-PM-070-71 DTO Banke Expected Add Comment

Post Review 4. Construction of Kabahigoth- SNRTP-182-NCB-O-SNRTP-BAR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 11/01/16 Update Bariyarpur Road (5.5 Km) 3.04-UG-070-71 Internal ID (SNRTP-BAR-W- NCB-3.04-UG- 070-71) 09/05/2016 06:21 DTO Bara Evaluation under execution Add Comment

Post Review N/A 13/07/15 08/11/15 06/03/16 N/A 2. Construction of Pushap Lal Marg SNRTP-184-NCB-O-SNRTP-BRD-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 Road (16.60 Km) 4.02-UG-070-71 DTO Bardia Contract under execution Add Comment

Post Review N/A 04/07/15 04/08/15 31/08/15 N/A 03/11/15 91 3. Construction of Laxmana-Gauripara- SNRTP-185-NCB-O-SNRTP-BRD-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 Ganeshpur Road (13.65km) 4.03-UG-070-71

DTO Bardia Contract under execution Add Comment

Post Review N/A 04/07/15 04/08/15 31/08/15 N/A 03/11/15 91 4.Construction of Rajapur Ring Rd. SNRTP-186-NCB-O-SNRTP-BRD-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 (47.25 Km) 4.04-UG-070-71 DTO Bardia Contract under execution Add Comment

Post Review N/A 04/07/15 04/08/15 31/08/15 N/A 03/11/15 91 1.Construction of Kalakate- SNRTP-187-NCB-O-SNRTP-DAN-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 Road(35 Km) NCB-5.01-UG-070-71 DTO Dang Contract under execution Add Comment

Post Review N/A 08/04/15 11/05/15 05/07/15 N/A 15/07/15 65 2. Construction of - SNRTP-188-NCB-O-SNRTP-DAN-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 11/01/16 Road(5.75 Km) NCB-5.02-UG-070-71 DTO Dang Contract under execution Add Comment

Post Review N/A 08/04/15 11/05/15 05/06/15 N/A 15/07/15 65 1. Construction of Bhimdhunga- SNRTP-189-NCB-O-SNRTP-DHA-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 11/01/16 Lamidanda-Galchi Road (27.75 Km): NCB-6.01-UG-070-71 N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 11/01/16

DTO Dharding Contract under execution Add Comment

Post Review 05/07/15 15/09/15 15/10/15 11/12/15 28/12/15 21/01/16 98 4. Construction of Bhimdhunga- SNRTP-192-NCB-O-SNRTP-DHA-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Update Lamidanda-Galchi Road (18.50 Km) NCB-6.04-PM-070-71 Internal ID (SNRTP-DHA-W- NCB-6.04-PM- 070-71) 09/05/2016 10:30 DTO Dharding Expected Add Comment

Post Review 1. Construction of Devpura-Ghodghas- SNRTP-193-NCB-O-SNRTP-DHAN-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Fulgama-Tulshiyahi Road (13.20 Km) NCB-7.01-UG-070-71

DTO Dhanusha Contract under execution Add Comment

Post Review N/A 18/02/15 22/03/15 14/05/15 N/A 18/06/15 88 2. Construction of Mahuwa-Dhabauli- SNRTP-194-NCB-O-SNRTP-DHAN-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Yaddukwaha-Balabakhar Road (16.25 NCB-7.02-UG-070-71 Km) DTO Dhanusha Contract under execution Add Comment

Post Review N/A 08/06/15 08/06/15 08/06/15 N/A 08/06/15 0 3. Construction of Janakpur- SNRTP-195-NCB-O-SNRTP-DHAN-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 Manaharpur-Kharihani Road (16.85 Km) NCB-7.03-UG-070-71

DTO Dhanusha Contract under execution Add Comment

Post Review N/A 18/02/15 22/03/15 14/05/15 N/A 17/07/15 117 4. Construction of Devpura-Ghodghas- SNRTP-196-NCB-O-SNRTP-DHAN-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 11/01/16 Update Fulgama-Tulshiyahi Road (4.00 Km) NCB-7.04-PM-070-71 Internal ID (SNRTP-DHAN- W-NCB-7.04- PM-070-71) 10/05/2016 03:05

DTO Dhanusha Expected Add Comment

Post Review 5. Construction of Janakpur- SNRTP-197-NCB-O-SNRTP-DHAN-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 11/01/16 Manaharpur-Kharihani Road (9.15 Km) NCB-7.05-UG-070-71

DTO Dhanusha Expected Add Comment

Post Review 3. Rudrabeni-Dhuseni-Padigaun (09.50 SNRTP-200-NCB-O-SNRTP-GUL--W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Km) NCB-8.03-UG-070-71 DTO Gulmi Expected Add Comment

Post Review 1. Construction of Sadakpur-Bauniya- SNRTP-201-NCB-O-SNRTP-KAI-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 Joshipur-Vajani Road (25 Km) 9.01-UG-070-71

DTO Kailali Expected Add Comment

Post Review 3. Construction of Jute Pani Nala Bridge SNRTP-203-NCB-O-SNRTP-KAI-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/03/16 on Sukhad-Khailad-Bhajeni Road (20 m. 9.03-UG-070-71 Span) DTO Kailali Contract under execution Add Comment Post Review N/A 16/07/15 16/08/15 15/11/15 N/A 16/12/15 122 1. Construction of Suspension Bridge- SNRTP-204-NCB-O-SNRTP-KAN--W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Kutiyakavar Road (10.50 Km) NCB-10.01-UG-070-71 DTO Kanchanpur Expected Add Comment

Post Review 2. Construction of Parasan- SNRTP-205-NCB-O-SNRTP-KAN--W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 Tribhuvanbasti-Laxmipur-Belauri Road NCB-10.02-UG-070-71 (28.50 km) DTO Kanchanpur Contract under execution Add Comment

Post Review N/A 04/07/15 04/08/15 27/08/15 N/A 01/11/15 89 3. Construction of Red Cross- SNRTP-206-NCB-O-SNRTP-KAN--W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Baghphanta Road (2.50 Km) NCB-10.03-UG-070-71 DTO Kanchanpur Expected Add Comment

Post Review 1. Construction of Tikkar-Buddhi-Bijgauri-SNRTP-207-NCB-O-SNRTP-KAP-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Hulaki (10.Km) 11.01-UG-070-71 DTO Kapilbastu Expected Add Comment

Post Review 4. Construction of - Bikuli- SNRTP-210-NCB-O-SNRTP-KAP-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/01/16 Bungchi Road:( 2.50 km) 11.04-UG-070-71 DTO Kapilbastu Expected Add Comment

Post Review 2. Construction of Chhorepatan-Kristi- SNRTP-212-NCB-O-SNRTP-KAS-W-NCB- N/A 11/01/05 10/02/05 12/03/05 N/A 11/04/05 60 10/10/16 Nirmalpokhar-Bharatpokhari Road 12.02-UG-070-71 (28.50 km) DTO Kaski Expected Add Comment

Post Review 4. Construction of Naundandada- SNRTP-214-NCB-O-SNRTP-KAS-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Kaskikot-Sarankot Road (11.00 Km) 12.04-UG-070-71 DTO Kaski Expected Add Comment

Post Review 5. Construction of Kaunkhola-Kaure- SNRTP-215-NCB-O-SNRTP-KAS-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Melbot-Sikles-Dudhpokhari Road:(10 12.05-UG-070-71 Km) DTO Kaski Expected Add Comment

Post Review 7. Construction of Lamachaur-Kharpani- SNRTP-217-NCB-O-SNRTP-KAS-W-NCB- N/A 26/01/15 25/02/15 27/03/15 N/A 26/04/15 60 26/01/16 Macchapuchhare Road (15.50 km) 12.07-UG-070-71

DTO Kaski Expected Add Comment

Post Review 1. Construction of Matihani-Pipra- SNRTP-218-NCB-O-SNRTP-MAH-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Bhamarpura-Mahdaiya Tapanpur Road NCB-13.01-UG-070-71 (22.50 km) DTO Mahottari Expected Add Comment

Post Review 2. Construction of Jaleshwor-Rauja- SNRTP-219-NCB-O-SNRTP-MAH-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/01/16 Bardibas Road (42 Km) NCB-13.02-UG-070-71 DTO Mahottari Expected Add Comment

Post Review 1. Construction of Kulekhani-Phakhel- SNRTP-220-NCB-O-SNRTP-MAK--W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Humanebhanjang Road (6.50 Km) NCB-14.01-UG-070-71 N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16

DTO Makawanpur Expected Add Comment

Post Review 3. Construction of Daman-Dandabas- SNRTP-222-NCB-O-SNRTP-MAK--W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 Baikuntha Road.(13 km) NCB-14.03-UG-070-71 DTO Makawanpur Expected Add Comment

Post Review 2. Construction of Maheshpur-Triveni SNRTP-226-NCB-O-SNRTP-NAW-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Road (10.50 Km) NCB-15.02-UG-070-71 DTO Nawal Parasi Expected Add Comment

Post Review 3. Construction of Daldale-Dhawadi SNRTP-227-NCB-O-SNRTP-NAW-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 11/01/16 Road (10 Km) NCB-15.03-UG-070-71 DTO Nawal Parasi Expected Add Comment

Post Review 4. Construction of Panchnagar- SNRTP-228-NCB-O-SNRTP-NAW-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 11/01/16 Maheshpur Road (16 Km) NCB-15.04-UG-070-71 DTO Nawal Parasi Expected Add Comment

Post Review 2. Construction of Nuwakot-Bageshwori- SNRTP-230-NCB-O-SNRTP-NUW-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 Urleni Road (23.50 Km) NCB-16.02-UG-070-71 DTO Nuwakot Expected Add Comment

Post Review 2. Construction of Bastari-Jhadewa Road SNRTP-233-NCB-O-SNRTP-PAL-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 (8 Km) 17.02-UG-070-71 DTO Palpa Expected Add Comment

Post Review 1. Construction of Atama Ram Path SNRTP-234-NCB-O-SNRTP-PAR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 (24.25 km) 18.01-UG-070-71 DTO Parsa Expected Add Comment

Post Review 2. Construction of Janata Sadak (29.50 SNRTP-235-NCB-O-SNRTP-PAR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 Km) 18.02-UG-070-71 DTO Parsa Expected Add Comment

Post Review 3. Construction of Pokhariya-Viswa SNRTP-236-NCB-O-SNRTP-PAR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 Road (13.50 km) 18.03-UG-070-71 DTO Parsa Expected Add Comment

Post Review 1. Construction of Cherneta-Puranthanti- SNRTP-237-NCB-O-SNRTP-PYU-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 Jogitari Road (7.70 Km) 19.01-UG-070-71 DTO Pyuthan Expected Add Comment

Post Review 3 Construction of Khalanga-Jogitari- SNRTP-239-NCB-O-SNRTP-PYU-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Arghakhanchi Road (7.70 Km) 19.03-UG-070-71 DTO Pyuthan Expected Add Comment

Post Review 1. Construction of Bogatitar-Simle-Vorle- SNRTP-240-NCB-O-SNRTP-RAS-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/10/16 Parchyang Road (12 Km) 20.01-UG-070-71 DTO Rasuwa Expected Add Comment

Post Review 2. Construction of Dharapani-Rupsepani- SNRTP-241-NCB-O-SNRTP-RAS-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/01/16 Bhorle Road (6 Km): 20.02-UG-070-71 DTO Rasuwa Expected Add Comment

Post Review 1. Construction of Aurahaiya- SNRTP-242-NCB-O-SNRTP-RAU-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 11/01/16 Rampurkhap-Bankul-Himalibas Road (6 21.01-UG-070-71 Km): DTO Rautahat Expected Add Comment

Post Review 3. Construction of Gaur-Banjarha-Auriya- SNRTP-244-NCB-O-SNRTP-RAU-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 06/11/16 Dumariya-Bishanpatti-Inerwari Road (27 21.03-UG-070-71 Km) DTO Rautahat Expected Add Comment

Post Review 4. Construction of Rajpur-Akolwa- SNRTP-245-NCB-O-SNRTP-RAU-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Dumariya-Latmari Road ( 9 Km) 21.04-UG-070-71 DTO Rautahat Expected Add Comment

Post Review 5. Construction of Aurahaiya- SNRTP-246-NCB-O-SNRTP-RAU-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Rampurkhap-Bankul-Himalibas Road (12 21.05-UG-070-71 Km) DTO Rautahat Expected Add Comment

Post Review 7. Construction of Gaur-Banjarha-Auriya- SNRTP-248-NCB-O-SNRTP-RAU-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Dumariya-Bishanpatti-Inerwari Road (8 21.07-UG-070-71 Km) DTO Rautahat Expected Add Comment

Post Review 1. Construction of Madhubaliya- SNRTP-249-NCB-O-SNRTP-RUP-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Bhutaha Road (8.50 Km) 22.01-UG-070-71 DTO Rupandehi Expected Add Comment

Post Review 2. Construction of Fireline- SNRTP-250-NCB-O-SNRTP-RUP-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Road.(9 Km) 22.02-UG-070-71 DTO Rupandehi Expected Add Comment

Post Review 5. Construction of Dhakdhai-Khaireni SNRTP-254-NCB-O-SNRTP-RUP-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Road. (17 Km) 22.05-UG-070-71 DTO Rupandehi Expected Add Comment

Post Review 1. Construction of Tharmare-Badagaun- SNRTP-255-NCB-O-SNRTP-SAL--W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Sanipiply-Chorjhari Road (36 Km) 23.01-UG-070-71

DTO Salyan Expected Add Comment

Post Review 2. Construction of Simkhark- SNRTP-256-NCB-O-SNRTP-SAL--W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Kupendedaha-Baluwasangharhi 23.02-UG-070-71 Road.(13.50 Km) DTO Salyan Expected Add Comment

Post Review 3. Construction of Khalanga-Simkhark- SNRTP-257-NCB-O-SNRTP-SAL--W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/01/16 Baluwasangharhi Road (32 Km) 23.03-UG-070-71 N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/01/16

DTO Salyan Expected Add Comment

Post Review 1. Construction of Jandaul-Kushaha SNRTP-264-NCB-O-SNRTP-SAP-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Road (24.50 Km) 24.01-UG-070-71 DTO Saptari Expected Add Comment

Post Review 2. Construction of Kusha-Belihi Road SNRTP-265-NCB-O-SNRTP-SAP-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 (16.50 Km) 24.02-UG-070-71 DTO Saptari Expected Add Comment

Post Review 1. Construction of Karmaiya-Hathiaul SNRTP-266-NCB-O-SNRTP-SAR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Road (20 km) 25.01-UG-070-71 DTO Sarlahi Expected Add Comment

Post Review 2. Construction of Kaudena-Janakinagar SNRTP-267-NCB-O-SNRTP-SAR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Rod (10 km) 25.02-UG-070-71 DTO Sarlahi Expected Add Comment

Post Review 3. Construction of -Kanchanpur- SNRTP-270-NCB-O-SNRTP-SIR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Road (4 Km) 26.03-UG-070-71 DTO Siraha Expected Add Comment

Post Review 4 . Construction of Zeromile-Bariyarpatti SNRTP-271-NCB-O-SNRTP-SIR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Road (8) Km 26.04-UG-070-71 DTO Siraha Expected Add Comment

Post Review 6. Construction of Mainawati Khola SNRTP-273-NCB-O-SNRTP-SIR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Bridge, Siraha-Pipara Road, Sirah (25 m 26.06-BRI-070-71 span) DTO Siraha Expected Add Comment

Post Review 2. Construction of Dasharathpur- SNRTP-275-NCB-O-SNRTP-SUR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Dandagaun Road. (8 km) 27.02-UG-070-71 DTO Surkhet Expected Add Comment

Post Review 4 . Construction of Nagdanda-Karkineta SNRTP-279-NCB-O-SNRTP-SYA-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Road. (20 Km) 28.04-UG-070-71 DTO Syanja Expected Add Comment

Post Review 8. Construction of Rangkhola-Biruwa SNRTP-284-NCB-O-SNRTP-SYA-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Road. (5.60 Km) 28.08-UG-070-71 DTO Syanja Expected Add Comment

Post Review 1.-Bhirkot (Shringa Path) (20 Km) SNRTP-285-NCB-O-SNRTP-TAN-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 29.01-UG-070-71 DTO Tanahun Expected Add Comment

Post Review 2. Construction of Dulegauda-Sankhe SNRTP-286-NCB-O-SNRTP-TAN-W-NCB- N/A 10/01/15 10/01/15 10/01/15 N/A 10/01/15 0 26/05/15 Raipur (Dhorbarahi Marg) 10 Km 29.02-UG-070-71

DTO Tanahun Expected Add Comment Post Review 2. Construction of Gaighat-Phatepur SNRTP-288-NCB-O-SNRTP-UDA-W- N/A 15/01/15 14/02/15 16/03/15 N/A 15/04/15 60 14/04/16 Road. (10 Km): NCB-30.02-UG-070-71 DTO Udayapur Expected Add Comment

Post Review 3. Construction of Katari-Bahunitar Road SNRTP-289-NCB-O-SNRTP-UDA-W- N/A 15/01/15 14/02/15 16/03/15 N/A 15/04/15 60 14/04/16 (11 Km) NCB-30.03-UG-070-71 DTO Udayapur Expected Add Comment

Post Review 3. Construction of Karmaiya-Hathiaul SNRTP-326-NCB-O-SNRTP-SAR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Road (40 km) 25.03-UG-071-72 DTO Sarlahi Expected Add Comment

Post Review 4. Construction of Kaudena- SNRTP-327-NCB-O-SNRTP-SAR-W-NCB- N/A 25/01/14 24/02/14 03/03/14 N/A 10/04/14 45 10/12/14 JanakinagarRoad (15 km) 25.04-UG-071-72 DTO Sarlahi Expected Add Comment

Post Review 1. Construction of Baddichaur-Guttu (28 SNRTP-328-NCB-O-SNRTP-SUR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 25/11/16 Km) 27.01-UG-070-71 DTO Surkhet Expected Add Comment

Post Review 3 Construction of Ratanangla Dharma SNRTP-329-NCB-O-SNRTP-SUR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 14/12/15 Rd (20 km) 27.03-UG-071-72 DTO Surkhet Expected Add Comment

Post Review 4 Construction of Dhuliya -bit - SNRTP-330-NCB-O-SNRTP-SUR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/11/16 Bhedabari Rd (15 km) 27.04-UG-071-72 DTO Surkhet Expected Add Comment

Post Review 5 Construction of Ramghat-Samuji ghat SNRTP-331-NCB-O-SNRTP-SUR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/11/16 Rd. (10 km) 27.05-UG-071-72 DTO Surkhet Expected Add Comment

Post Review 5. Construction of Whalighuwas-Rampur SNRTP-332-NCB-O-SNRTP-SYA-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Road (10 Km) 28.05-UG-070-71 DTO Syanja Expected Add Comment

Post Review 6. Construction of Mirdi-JagatBhanjyang- SNRTP-333-NCB-O-SNRTP-SYA-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Kinare-Chapakot Road (7 Km) 28.06-UG-070-71

DTO Syanja Expected Add Comment

Post Review 7. Construction of Badhkhola-Taksar- SNRTP-334-NCB-O-SNRTP-SYA-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/16 Dadegaunda Road (8 Km) 28.07-UG-070-71 DTO Syanja Expected Add Comment

Post Review 3.Samung-Deurali-Gajarkpt-Keladighat SNRTP-335-NCB-O-SNRTP-TAN-W-NCB- N/A 10/01/15 10/01/15 10/01/15 N/A 10/01/15 0 10/07/16 (15 Km) 29.03-UG-071-72 DTO Tanahun Expected Add Comment

Post Review 5. Construction of Damauli- SNRTP-338-NCB-O-SNRTP-TAN-W-NCB- N/A 10/01/15 10/01/15 10/01/15 N/A 10/01/15 0 10/07/16 Pokharibhanjyang-- 29.05-UG-071-72 Dharampani-Bandipur 20 Km DTO Tanahun Expected Add Comment

Post Review 6. Parsahi-Baluwa River Bridge (50 SNRTP-339-NCB-O-SNRTP-DHAN-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/01/16 Update meter span) across JMK Road NCB-7.07-BRI-071-72 Internal ID (SNRTP-DHAN- W-NCB-7.07- BRI-071-72) 10/05/2016 05:09

DTO Dhanusha Contract under execution Add Comment

Post Review N/A 07/07/15 14/08/15 16/10/15 N/A 09/12/15 117 7. Construction of Baghchaura arhari SNRTP-340-NCB-O-SNRTP-DHAN-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/01/16 Update River Bridge 25 meter span) across JMK NCB-7.06-BRI-071-72 Internal ID Road (SNRTP-DHAN- W-NCB-7.06- BRI-071-72) 10/05/2016 04:19

DTO Dhanusha Contract under execution Add Comment

Post Review N/A 07/07/15 14/08/15 16/10/15 N/A 09/12/15 117 8. Construction of Rupakot Thumki Road SNRTP-365-NCB-O-SNRTP-KAS-W-NCB- N/A 01/02/14 03/03/14 18/03/14 N/A 10/05/14 68 07/12/14 (22 km) 12.08-UG-070-71 DTO Kaski Expected Add Comment

Post Review 9. Construction of Baidam Pame SNRTP-366-NCB-O-SNRTP-KAS-W-NCB- N/A 26/02/15 28/03/15 27/04/15 N/A 27/05/15 60 26/05/17 Chhadichhita Road (14 Km.) 12.09-UG-070-71 DTO Kaski Expected Add Comment

Post Review 6. Construction of Gaidahawa Khola SNRTP-367-NCB-O-SNRTP-RUP-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Bridge across Thu-Piprahawa Karauta 22.06-BRI-070-71 Semara Road (30 meter Span)

DTO Rupandehi Expected Add Comment

Post Review 8. Construction of Bakuwakhola Bridge SNRTP-368-NCB-O-SNRTP-RAU-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 across Akolwa-Dumariya Road (25 21.08-BRI-070-71 Meter Span) DTO Rautahat Expected Add Comment

Post Review 9. Construction of Aruwa Khola Bridge SNRTP-369-NCB-O-SNRTP-RAU-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Malahi Ghat across Santapur Road (25 21.09-BRI-070-71 Meter Span) DTO Rautahat Expected Add Comment

Post Review 7. Construction of Siraha-Shukhipur SNRTP-371-NCB-O-SNRTP-SIR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/17 Road (10 Km.) 26.07-UG-070-71 DTO Siraha Expected Add Comment

Post Review 4. Construction of Dulegauda-Sankhe SNRTP-372-NCB-O-SNRTP-TAN-W-NCB- N/A 10/01/15 10/01/15 10/01/15 N/A 10/01/15 0 09/01/17 Raipur (Dhorbarahi Marg) 10 Km: 29.04-UG-070-71

DTO Tanahun Expected Add Comment

Post Review 6. Lapang phedi-Lapang Khola Truss SNRTP-376-NCB-O-SNRTP-DHA-W- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 09/10/16 Bridge across Dharding Besi Sangkosh NCB-6.06-BRI-071-72 Tipling Road (35 Meter Span)

DTO Dharding Expected Add Comment

Post Review 4. Construction of Seugha-Simaghat- SNRTP-383-NCB-O-SNRTP-GUL--W- N/A 26/03/15 25/04/15 25/05/15 N/A 24/06/15 60 22/09/16 Update Daha -Aglung Phedi Road (57 NCB-8.05-UG-071-72 Internal ID Km) (SNRTP-GUL-- W-NCB-8.05- UG-071-72) 13/05/2016 07:32 DTO Gulmi Expected Add Comment

Post Review 5. Construction of Chorkate Santipur SNRTP-384-NCB-O-SNRTP-GUL--W- N/A 26/03/15 25/04/15 25/05/15 N/A 24/06/15 60 22/09/16 Update Gwaghat -Phosing -Purtighat Road (45 NCB-8.04-UG-071-72 Internal ID Km) (SNRTP-GUL-- W-NCB-8.04- UG-071-72) 13/05/2016 07:51 DTO Gulmi Expected Add Comment

Post Review 7. Gachchhe - Dhanachaur -Lamtal - SNRTP-390-NCB-O-SNRTP-ARG-W-NCB- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 17/01/17 Bhaluwang Rd. (65 Km) 1.07-UG-071-72 DTO Arghakhanchi Expected Add Comment

Post Review 8. Ghumti- Palpa Rd. (29 Km) SNRTP-391-NCB-O-SNRTP-ARG-W-NCB- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 18/10/16 1.08-UG-071-72 DTO Arghakhanchi Expected Add Comment

Post Review 9. Rajupanikhada-Masurpata Rd. (10 SNRTP-392-NCB-O-SNRTP-ARG-W-NCB- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 19/07/16 Km) 1.09-UG-071-72 DTO Arghakhanchi Expected Add Comment

Post Review 10. Sandhikharka - Pakale -dharapani - SNRTP-393-NCB-O-SNRTP-ARG-W-NCB- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 18/10/16 Chujathi Rd. (10 Km) 1.10-UG-071-72 DTO Arghakhanchi Expected Add Comment

Post Review 11. Samne khola bridge (40 m. span) SNRTP-394-NCB-O-SNRTP-ARG-W-NCB- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 17/01/17 across Sandhikharka - Pakale -Dharapani 1.11-BRI-071-72 -Chujathi Rd DTO Arghakhanchi Expected Add Comment

Post Review 12. Khakabesi khola bridge (40 m. span) SNRTP-395-NCB-O-SNRTP-ARG-W-NCB- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 17/01/17 across Sandhikharka - Pakale -Dharapani 1.12-BRI-071-72 -Chujathi Rd DTO Arghakhanchi Evaluation under execution Add Comment Post Review N/A 06/10/15 05/11/15 29/11/15 N/A 5. kulo Bridge (40 m span) across SNRTP-396-NCB-O-SNRTP-BRD-W-NCB- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 17/01/17 Rajapur Ring Rd. 4.05-BRI-071-72 DTO Bardia Expected Add Comment

Post Review 3. -Manpur -Buruwa Rd (15 Km) SNRTP-397-NCB-O-SNRTP-DAN-W- N/A 17/01/14 16/02/14 03/03/14 N/A 02/05/14 75 02/08/15 NCB-5.03-UG-071-72 DTO Dang Expected Add Comment

Post Review 4. Chyati Khola Bridge (40 m span) SNRTP-398-NCB-O-SNRTP-DAN-W- N/A 17/01/14 16/02/14 03/03/14 N/A 02/05/14 75 31/10/15 across pawan nagar purandhara road NCB-5.04-BRI-071-72

DTO Dang Expected Add Comment

Post Review 5. Kalipuruwa Bridge (40 m span) across SNRTP-399-NCB-O-SNRTP-DAN-W- N/A 17/01/14 16/02/14 03/03/14 N/A 02/05/14 75 31/10/15 Kalakate - Gadhawa Rd. NCB-5.05-BRI-071-72 DTO Dang Expected Add Comment

Post Review 6. Khagriya Kholoa Bridge (40 m span) SNRTP-400-NCB-O-SNRTP-DAN-W- N/A 17/01/14 16/02/14 03/03/14 N/A 02/05/14 75 31/10/15 across Kalakate - Gadhawa Rd. NCB-5.06-BRI-071-72 DTO Dang Expected Add Comment

Post Review 7. Gurung Khola Bridge (40 m span) SNRTP-401-NCB-O-SNRTP-DAN-W- N/A 17/01/14 16/02/14 03/03/14 N/A 02/05/14 75 31/10/15 across Kalakate - Gadhawa Rd. NCB-5.07-BRI-071-72 DTO Dang Expected Add Comment

Post Review 8. Dhanusadham-Raghunathpur- SNRTP-402-NCB-O-SNRTP-DHAN-W- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 19/07/16 Kirathpur Rd (10 Km) NCB-7.08-PM-071-72 DTO Dhanusha Contract under execution Add Comment

Post Review N/A 20/04/15 21/05/15 02/07/15 N/A 15/07/15 55 9. Janaki Medical college -Ramdaiya- SNRTP-403-NCB-O-SNRTP-DHAN-W- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 19/07/16 sabaila Pakerwa Rd (10 Km) NCB-7.09-PM-071-72 DTO Dhanusha Contract under execution Add Comment

Post Review N/A 20/04/15 21/05/15 29/06/15 N/A 15/07/15 55 10. Kurtha- Santipur -Jamunibas Rd (10 SNRTP-404-NCB-O-SNRTP-DHAN-W- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 19/07/16 Km) NCB-7.10-PM-071-72 DTO Dhanusha Contract under execution Add Comment

Post Review N/A 20/04/15 21/05/15 26/06/15 N/A 15/07/15 55 11. Mahuwa-Dhabauli-Yaddukwaha- SNRTP-405-NCB-O-SNRTP-DHAN-W- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 17/01/17 Balabakha Rd(15 Km) NCB-7.11-UG-071-72 DTO Dhanusha Expected Add Comment

Post Review 12. Charnath Bridge (100 m Span) across SNRTP-406-NCB-O-SNRTP-DHAN-W- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 17/01/17 .Mahuwa-Dhabauli-Yaddukwaha- NCB-7.12-BRI-071-72 Balabakhar Rd DTO Dhanusha Expected Add Comment

Post Review 13. Kajipaini Bridge (40 m span) across SNRTP-407-NCB-O-SNRTP-DHAN-W- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 19/10/16 Mahuwa-Dhabauli-Yaddukwaha- NCB-7.13-BRI-071-72 Balabakhar Rd DTO Dhanusha Expected Add Comment

Post Review 14. Aurahi Khola Bridge (120 m span) SNRTP-408-NCB-O-SNRTP-DHAN-W- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 17/01/17 across Kurtha- Santipur -Jamunibas Rd NCB-7.14-BRI-071-72

DTO Dhanusha Expected Add Comment

Post Review 15. Baluwa khola Bridge (40 m span) SNRTP-409-NCB-O-SNRTP-DHAN-W- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 17/01/17 across Dhanusadham Raghunathpur Rd NCB-7.15-BRI-071-72

DTO Dhanusha Expected Add Comment

Post Review 4. Chorkote-Santipur- Gwagha -Foksing- SNRTP-410-NCB-O-SNRTP-GUL--W- N/A 06/05/15 05/06/15 20/06/15 N/A 20/07/15 45 17/01/17 Purti ghat Rd (45 Km) NCB-8.04-UG-071-72 DTO Gulmi Expected Add Comment

Post Review 4. Sukhad- Khaila- Bhajhani Rd (24 km) SNRTP-412-NCB-O-SNRTP-KAI-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 9.04 -UG-071-72 DTO Kailali Expected Add Comment

Post Review 5. Malaria Khola Bridge.( 25 m span) SNRTP-413-NCB-O-SNRTP-KAN--W- N/A 07/05/15 06/06/15 06/07/15 N/A 05/08/15 60 02/02/17 across Dadthan- Baliban Rd NCB-10.05-BRI-071-72 DTO Kanchanpur Expected Add Comment

Post Review 10. Rakhi- Mijauri Road (20 Km.) SNRTP-414-NCB-O-SNRTP-KAS-W-NCB- N/A 07/05/15 06/06/15 06/07/15 N/A 05/08/15 60 02/02/17 12.10-UG-071-72 DTO Kaski Expected Add Comment

Post Review 11. Kaseri- Majsadhi-Thumako Danda SNRTP-415-NCB-O-SNRTP-KAS-W-NCB- N/A 07/05/15 06/06/15 06/07/15 N/A 05/08/15 60 02/02/17 Road (20 Km.) 12.11-UG-071-72 DTO Kaski Expected Add Comment

Post Review 12. Wardi Khola Bridge (40 m. Span) SNRTP-416-NCB-O-SNRTP-KAS-W-NCB- N/A 07/05/15 06/06/15 06/07/15 N/A 05/08/15 60 02/02/17 across Rakhi- Mijauri Road (20 Km.) 12.12-BRI-071-72 DTO Kaski Expected Add Comment

Post Review 13. Aapu Khola Bridge (40 m. Span) SNRTP-417-NCB-O-SNRTP-KAS-W-NCB- N/A 07/05/15 06/06/15 06/07/15 N/A 05/08/15 60 02/02/17 across Talo -Gulegaunda - Polyang Tar 12.13-BRI-071-72 Rd DTO Kaski Expected Add Comment

Post Review 3. Musharpatti -Suga- Simaradhi - SNRTP-418-NCB-O-SNRTP-MAH--W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/08/16 Parkauli Rd (10 Km) NCB-13.03-PM-071-72 DTO Mahottari Expected Add Comment

Post Review 4. Tikuliya- Banuata -Leuri -Madyapura SNRTP-419-NCB-O-SNRTP-MAH--W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/08/16 Rd (10 Km) NCB-13.04-PM-071-72 DTO Mahottari Ongoing Activity Add Comment

Post Review N/A 07/02/16 5. Bakhari - Ankar - Parsa - Chakwa- SNRTP-420-NCB-O-SNRTP-MAH--W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/08/16 Nainahi Rd (10 Km) NCB-13.05-PM-071-72 DTO Mahottari Ongoing Activity Add Comment

Post Review N/A 07/02/16 6. Malwahi- Tharkholi-Ekdanda -Sandha SNRTP-421-NCB-O-SNRTP-MAH--W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/08/16 Rd (10 Km) NCB-13.06-PM-071-72 DTO Mahottari Ongoing Activity Add Comment

Post Review N/A 07/02/16 8. Bakhari -Halkhori - Batnaha - SNRTP-423-NCB-O-SNRTP-MAH--W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/11/16 Sisuwaha - Kataiya -Manra Jawka Rd (15 NCB-13.08-UG-071-72 Km) DTO Mahottari Expected Add Comment

Post Review 9. Chauriya -Ekdada- Koluha -Mahottari - SNRTP-424-NCB-O-SNRTP-MAH--W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/11/16 Rd (10 Km) NCB-13.09-UG-071-72 DTO Mahottari Expected Add Comment

Post Review 10. Musarpatti-Suga-Sadi-Parkauli- SNRTP-425-NCB-O-SNRTP-MAH--W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/11/16 Mahottari-Bhagwanpur- Loharoatti NCB-13.10-UG-071-72 Rd(10 Km) DTO Mahottari Expected Add Comment

Post Review 11. Jaleswar -Sadi -Simradhi -Dhirapur - SNRTP-426-NCB-O-SNRTP-MAH--W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/11/16 Majhaura- Phulgama Rd (12 Km) NCB-13.11-UG-071-72

DTO Mahottari Expected Add Comment

Post Review 5. Sahid Alok Chakra Path (40 Km) SNRTP-427-NCB-O-SNRTP-NAW-W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 NCB-15.05-UG-071-72 DTO Nawal Parasi Expected Add Comment

Post Review 6. Jharaha Khola Bridge (40 m Span) SNRTP-428-NCB-O-SNRTP-NAW-W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across Maheshpur -Tribeni Rd NCB-15.06-BRI-071-72 DTO Nawal Parasi Expected Add Comment

Post Review 3.Harthok- Chahara Rd (25 Km) SNRTP-430-NCB-O-SNRTP-PAL-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 17.03-UG-071-72 DTO Palpa Expected Add Comment

Post Review 4. Chilangdi -Chappani Ramdi Rd (16 SNRTP-431-NCB-O-SNRTP-PAL-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/11/16 Km) 17.04-UG-071-72 DTO Palpa Expected Add Comment

Post Review 5. Amliyan Bridge (40 m span) across SNRTP-432-NCB-O-SNRTP-PAL-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 Bastari-Jhadewa Rd 17.05-BRI-071-7 DTO Palpa Expected Add Comment

Post Review 5. Mulghat Bridge (40 m. span) across SNRTP-434-NCB-O-SNRTP-PYU-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 Bagdula-Bahane-Syaulibang 19.05-BRI-071-72 DTO Pyuthan Expected Add Comment

Post Review 7. Tunihawa- Mukundghadha Rd (19 SNRTP-435-NCB-O-SNRTP-RUP-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/11/16 Km) 22.07-UG-071-72 DTO Rupandehi Expected Add Comment

Post Review 8. Tamnagar- Bethari Rd (23 Km) SNRTP-436-NCB-O-SNRTP-RUP-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/11/16 22.08-UG-071-72 DTO Rupandehi Expected Add Comment

Post Review 4. Luhan Kavra - Rampur Rd (25 Km) SNRTP-437-NCB-O-SNRTP-SAL--W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 23.04-UG-071-72 DTO Salyan Expected Add Comment

Post Review 5. Dhorchaur -Gurdase -Kain Danda Rd SNRTP-438-NCB-O-SNRTP-SAL--W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 (20 Km) 23.05-UG-071-72 DTO Salyan Expected Add Comment

Post Review 6. Tharmare-Baghchaur - Kotmaula - SNRTP-439-NCB-O-SNRTP-SAL--W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 Patihalna -Bafo Khola Khaula Rd(15 Km) 23.06-UG-071-72

DTO Salyan Expected Add Comment

Post Review 7. Majhkanda Khola Bridge (40 m span) SNRTP-440-NCB-O-SNRTP-SAL--W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across Simkhark-Kupendedaha- 23.04-BRI-071-72 Baluwasangharhi Rd DTO Salyan Expected Add Comment

Post Review 8. Jimari Khola Bridge (40 m span) SNRTP-441-NCB-O-SNRTP-SAL--W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across.Tharmare-Badagaun-Sanipiply- 23.08-BRI-071-72 Chorjhari Rd DTO Salyan Expected Add Comment

Post Review 9. Luhan Khola Bridhe (40 m span) SNRTP-442-NCB-O-SNRTP-SAL--W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across Luhan Kavra - Rampur Rd 23.09-BRI-071-72 DTO Salyan Expected Add Comment

Post Review 3 .Mahuli -Lohajra -Hanuman Nagar Rd SNRTP-443-NCB-O-SNRTP-SAP-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/11/16 (15 Km) 24.03-UG-071-72 DTO Saptari Expected Add Comment

Post Review 4 .Kadarbona- Rautahat - Ramnagar Rd SNRTP-444-NCB-O-SNRTP-SAP-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/11/16 (15 Km) 24.04-UG-071-72 DTO Saptari Expected Add Comment

Post Review 5 .Kharchuhiya- Tachan Rd (15 Km) SNRTP-445-NCB-O-SNRTP-SAP-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/11/16 24.05-UG-071-72 DTO Saptari Expected Add Comment

Post Review 8. Jamta -Lagri diyani Road (20 Km.) SNRTP-446-NCB-O-SNRTP-SIR-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/08/16 26.08-PM-071-72 DTO Siraha Expected Add Comment

Post Review 9. Mainawati river Bridge (40 m span) SNRTP-447-NCB-O-SNRTP-SIR-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across Siraha-Shukhipur Road 26.09-BRI-071-72 DTO Siraha Expected Add Comment

Post Review 10. Gagan Khola Bridge (40 m span) SNRTP-448-NCB-O-SNRTP-SIR-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across Siraha-Shukhipur Road 26.10-BRI-071-72 DTO Siraha Expected Add Comment

Post Review 11.Kamala Canal Bridge (20 m span) SNRTP-449-NCB-O-SNRTP-SIR-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/08/16 across Siraha-Kalyanpur-Mirchaiya Rd 26.11-BRI-071-72

DTO Siraha Expected Add Comment

Post Review 6. Sanke Khola Bridge (40 m.span) SNRTP-450-NCB-O-SNRTP-TAN-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across .Dulegauda-Sankhe Raipur 29.06-BRI-071-72 (Dhorbarahi Marg) DTO Tanahun Expected Add Comment

Post Review 7. Jamunyauli -Duni Daha Rd (14 Km) SNRTP-452-NCB-O-SNRTP-SUR-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/11/16 27.07-UG-071-72 DTO Surkhet Expected Add Comment

Post Review 8 . Chhinchu- Ghariban-Badakholi - SNRTP-453-NCB-O-SNRTP-SUR-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 Betani -Phalate -Kalche Rd (40 Km) 27.08-UG-071-72 DTO Surkhet Expected Add Comment

Post Review 9. Jyamire Khola Bridge (40 m span) SNRTP-454-NCB-O-SNRTP-SUR-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across Ramghat-Samuji ghat Rd. 27.09-BRI-071-72 DTO Surkhet Expected Add Comment

Post Review 10. .Karre Khola Bridge (40 m span) SNRTP-455-NCB-O-SNRTP-SUR-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across Dhuliya -bit -Bhedabari Rd 27.10-BRI-071-72 DTO Surkhet Expected Add Comment

Post Review 9. Rangkhola Juge bagal Bridge (40 m. SNRTP-456-NCB-O-SNRTP-SYA-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 span) across Nagdanda-Karkineta Rd 28.09-BRI-071-72

DTO Syanja Expected Add Comment

Post Review 10. Bastra Khola Bridge (40 m span) SNRTP-457-NCB-O-SNRTP-SYA-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across Rangkhola-Biruwa Rd. 28.10-BRI-071-72 DTO Syanja Expected Add Comment

Post Review 11. Suragi Khola pyuri dovan Bridge (40 SNRTP-458-NCB-O-SNRTP-SYA-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 m span) across Badhkhola-Taksar- 28.11-BRI-071-72 Dadegaunda Rd DTO Syanja Expected Add Comment

Post Review 12. Galaiche ghat Bridge (40 m. span) SNRTP-459-NCB-O-SNRTP-SYA-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 Update across Badhkhola-Taksar-Dadegaunda 28.12-BRI-071-72 Internal ID Rd (SNRTP-SYA-W- NCB-28.12-BRI- 071-72) 02/04/2016 02:29 DTO Syanja Expected Add Comment

Post Review 13. Pauwaigaude Khola Bridge (40 m. SNRTP-460-NCB-O-SNRTP-SYA-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 span) across Badhkhola-Taksar- 28.13-BRI-071-72 Dadegaunda Rd DTO Syanja Expected Add Comment

Post Review 14. Andhi ghat Khola Bridge (40 m. SNRTP-461-NCB-O-SNRTP-SYA-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 Update span) Across Mirdi-Jagat Bhanjyang- 28.14-BRI-071-72 Internal ID Kinare-Chapakot Rd (SNRTP-SYA-W- NCB-28.14-BRI- 071-72) 02/04/2016 02:40 DTO Syanja Expected Add Comment

Post Review 1. Bhojpur Mane Bhanjyang -Rani bas- SNRTP-462-NCB-O-SNRTP-BHOJ-W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/11/16 Ghodetar Rd (15 Km) NCB-31.01-UG-071-72 DTO Bhojpur Expected Add Comment

Post Review 2. Bhojpur -Dingla - Mulpani - Keureni SNRTP-463-NCB-O-SNRTP-BHOJ-W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/11/16 pani Rd (15 Km NCB-31.02-UG-071-72 DTO Bhojpur Expected Add Comment

Post Review 3. Bhojpur -Dingla - Mulpani - Keureni SNRTP-464-NCB-O-SNRTP-BHOJ-W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/08/16 pani Rd (15 Km) NCB-31.03-PM-071-72 DTO Bhojpur Expected Add Comment

Post Review 4. Taksar- Gumba -Dalgaun- Okhare - SNRTP-465-NCB-O-SNRTP-BHOJ-W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 03/08/16 Dodhalekhani Rd 158 Km) NCB-31.04-PM-071-72 DTO Bhojpur Expected Add Comment

Post Review 11. Gam Khola Bridge (40 m span) SNRTP-466-NCB-O-SNRTP-SUR-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across Dhuliya -bit -Bhedabari Rd 27.11-BRI-071-72 DTO Surkhet Expected Add Comment

Post Review 12. Chaur Khola Bridge (40 m span) SNRTP-467-NCB-O-SNRTP-SUR-W-NCB- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across Badichaur-Guttu Rd. 27.12-BRI-071-72 DTO Surkhet Expected Add Comment

Post Review 5.Thadi Khola Causeway (40 m span) SNRTP-468-NCB-O-SNRTP-UDA-W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across Gaighat (Moti gadha) Phattepur NCB-30.5-BRI-070-71 Rd DTO Udaypur Expected Add Comment

Post Review 6.Luhale Khola Bridge (50 m span) SNRTP-469-NCB-O-SNRTP-UDA-W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across Gaighat (Moti gadha) Phattepur NCB-30.06-BRI-070-71 Rd DTO Udaypur Expected Add Comment

Post Review 7.Babiya Khola Bridge (40 m span) SNRTP-470-NCB-O-SNRTP-UDA-W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 across Gaighat (Moti gadha) Phattepur NCB-30.07-BRI-070-71 Rd DTO Udaypur Expected Add Comment

Post Review 8.Konga Khola Bridge (50 m span) across SNRTP-471-NCB-O-SNRTP-UDA-W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 Gaighat (Moti gadha) Phattepur Rd NCB-30.08-BRI-070-71

DTO Udaypur Expected Add Comment

Post Review 10. Construction of Saruhatha-Badarwa- SNRTP-472-NCB-O-SNRTP-RAU-W-NCB- N/A 16/05/15 15/06/15 15/07/15 N/A 14/08/15 60 11/02/17 Bankul-Aruwa Khola Road (17.51 Meter 21.10-PM-070-71 Span) DTO Rautahat Expected Add Comment

Post Review 5 Construction of Kalaiya -Jaitapur Road SNRTP-474-NCB-O-SNRTP-BAR-W-NCB- N/A 01/07/14 01/08/14 31/08/14 N/A 15/09/14 45 14/03/15 (11 Km) 3.05-PM-071-72 DTO Bara Expected Add Comment

Post Review 8. -Hapur-Eyes Hospital Road SNRTP-475-NCB-O-SNRTP-DAN-W- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 maintenance(12.32 km) NCB-5.08-PM-071-72 DTO Dang Expected Add Comment

Post Review 9. Khairakhothari-Duruwa Road SNRTP-476-NCB-O-SNRTP-DAN-W- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 maintenance(8.4 km) NCB-5.09-PM-071-72 DTO Dang Expected Add Comment

Post Review 10. -Belaspur Road SNRTP-477-NCB-O-SNRTP-DAN-W- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 14/03/16 maintenance(6 km) NCB-5.10-PM-071-72 DTO Dang Expected Add Comment

Post Review 6.Baletaksa-Kaule-Rimuwa- SNRTP-478-NCB-O-SNRTP-GUL--W- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 14/03/16 RudrabeniRoad 16.00 Km) NCB-8.06-PM-071-72 DTO Gulmi Expected Add Comment

Post Review 7.Ratamata-Talkhola-Gwuadi-Rimuwa SNRTP-479-NCB-O-SNRTP-GUL-8.07-W- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 14/03/16 Road (12.00 Km) NCB-PM-071-72 DTO Gulmi Expected Add Comment

Post Review 8. Shantipur-Harrachaur-Olibang- SNRTP-480-NCB-O-SNRTP-GUL--W- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 13/09/15 Sindurghanse Road(20.00 Km) NCB-8.08 -PM-071-72 DTO Gulmi Expected Add Comment

Post Review 5. Sahajpur-Nigali-Kjairala road SNRTP-481-NCB-O-SNRTP-KAI--W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 maintence (22.2 KM)- 9.05-PM-071-72 DTO Kailali Expected Add Comment

Post Review 6. Malakheti-Bandrekhal-Kolmoda road SNRTP-482-NCB-O-SNRTP-KAI--W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 maintence (4 KM) 9.06-PM-071-72 DTO Kailali Expected Add Comment

Post Review 7. Badaipur-Udashipur-Hasliya road SNRTP-483-NCB-O-SNRTP-KAI--W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 maintence (20.5 KM) 9.07-PM-071-72 DTO Kailali Expected Add Comment

Post Review 6. Babsthan-Chandani-Bailbanda road SNRTP-484-NCB-O-SNRTP-KAN--W- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 maintence ( 12.9 KM) NCB-10.06-PM-071-72 N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15

DTO Kanchanpur Expected Add Comment

Post Review 7. Krishnapur (Malubela) – Krishanapur SNRTP-485-NCB-O-SNRTP-KAN--W- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 (M R M) Raikwarbirchawa- NCB-10.07-PM-071-72 Rajghat(17.63) DTO Kanchanur Expected Add Comment

Post Review 8. Bansamiti-Pipalladi-Jonpuri-Ranipur SNRTP-486-NCB-O-SNRTP-KAN--W- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 road maintence ( 10.55 KM) NCB-10.08-PM-071-72 DTO Kanchanpur Expected Add Comment

Post Review 5. Odari-Patna-Kothi Nadi Road SNRTP-487-NCB-O-SNRTP-KAP-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 Maintenance(10.Km) 11.05-PM-071-72 DTO Kapilbastu Expected Add Comment

Post Review 14. Dobilla-Bagmara Road's Causeway SNRTP-491-NCB-O-SNRTP-KAS-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 13/09/15 Maintenance (24 m) 12.14-PM-071-72 DTO Kaski Expected Add Comment

Post Review 7. Sunwal-Parsawal-Amraud-banjariya- SNRTP-494-NCB-O-SNRTP-NAW-W- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 13/09/15 Ginabakina-Lalpati-Tonawa Road NCB-15.07-PM-071-72 maintenance (16.09 Km)

DTO Nawalparasi Expected Add Comment

Post Review 6. Banstari-Jhadewa Road Maintenance SNRTP-495-NCB-O-SNRTP-PAL-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 . (7.7 Km) 17.06-PM-071-72 DTO Palpa Expected Add Comment

Post Review 7. Harthok-Chhahara-Tingire Road SNRTP-496-NCB-O-SNRTP-PAL-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 Maintenance . (8 Km) 17.07-PM-071-72 DTO Palpa Expected Add Comment

Post Review 4. Dhore-Pakaha-Bankatwa-Sonbarsa SNRTP-497-NCB-O-SNRTP-PAR-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 Road . (28 Km) 18.04-PM-071-72 DTO Parsa Expected Add Comment

Post Review 5. SonBarsa-Gadi-Sakhuwa-Parsauni- SNRTP-498-NCB-O-SNRTP-PAR-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 Mahuban Ramnagari Road . (16 Km) 18.05-PM-071-72 DTO Parsa Expected Add Comment

Post Review 11. Construction of Gaur -Gangapipara- SNRTP-500-NCB-O-SNRTP-RAU-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 Samanpur-Santpur Road (25 Km) 21.11-PM-071-72

DTO Rautahat Expected Add Comment

Post Review 12. Construction ofJayanagar-Dewahi- SNRTP-501-NCB-O-SNRTP-RAU-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 Pataura-Sonarmiya Road (... Km) 21.12-PM-071-72

DTO Rautahat Expected Add Comment

Post Review 9. Hati Bangai-Semara-Khairaghat Road SNRTP-502-NCB-O-SNRTP-RUP-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 Maintenance . (22.56 Km) 22.09-PM-071-72 DTO Rupandehi Expected Add Comment

Post Review 10.Kutta-Chhapiya-Banbhusadi- SNRTP-503-NCB-O-SNRTP-RUP-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 Manamateriya-Sau.Pharsaatikar Road 22.10-PM-071-72 Maintenance . (18 Km DTO Rupandehi Expected Add Comment

Post Review 10. Dhorchaur-Gurudase-Kainakarda SNRTP-504-NCB-O-SNRTP-SAL--W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 Rural Road Maintenance (10.52 Km) 23.10-PM-071-72 DTO Salyan Expected Add Comment

Post Review 11. Baghchaur-Kotmaula-Patihalna Rural SNRTP-505-NCB-O-SNRTP-SAL--W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 Road Maintenance (12.1 Km) 23.11-PM-071-72 DTO Salyan Expected Add Comment

Post Review 6. Construction of Atrauli -Sasapur Road SNRTP-506-NCB-O-SNRTP-SAR--W- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 (15 Km) NCB-25.06-PM-071-72 DTO Sarlahi Expected Add Comment

Post Review 7. Construction of Bhaktipur- SNRTP-507-NCB-O-SNRTP-SAR--W- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 Chandranagar-Brampuri Road (18.8 Km) NCB-25.07-PM-071-72

DTO Sarlahi Expected Add Comment

Post Review 12. Construction of chikanagadha Rd (42 SNRTP-508-NCB-O-SNRTP-SIR-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 14/12/15 km) 26.12-PM-071-72 DTO Siraha Expected Add Comment

Post Review 13. Dhuliyabit-Bhedabari-Dang- SNRTP-512-NCB-O-SNRTP-SUR-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 14/03/16 Purandhara Road maintenance (10 Km) 27.13.-PM-071-72

DTO Surkhet Expected Add Comment

Post Review 15. Construction of Rangkhol-Machabari-SNRTP-513-NCB-O-SNRTP-SYA-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 14/03/16 Biruwa-Chinnebas Road Maintenance (6 28.15-PM-071-72 Km) DTO Syanja Expected Add Comment

Post Review 16. Badkhola-Taksar Dulegaunda Road SNRTP-514-NCB-O-SNRTP-SYA-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 14/03/16 Maintenance :(8 Km) 28.16-PM-071-72 DTO Syanja Expected Add Comment

Post Review 17. Construction of Naudanda-Karkineta SNRTP-515-NCB-O-SNRTP-SYA-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 14/03/16 Road Maintenance ( 10 Km) 28.17-PM-071-72

DTO Syanja Expected Add Comment

Post Review 18. Construction of Mirdi-jagat SNRTP-516-NCB-O-SNRTP-SYA-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 14/03/16 Bhanjyang Road Maintenance (8.5 Km) 28.18-PM-071-72 N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 14/03/16

DTO Syanja Expected Add Comment

Post Review 19. Construction Putalikhet-Aaruchaur- SNRTP-517-NCB-O-SNRTP-SYA-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 14/03/16 Road Maintenance (7.5 Km) 28.19-PM-071-72

DTO Syanja Expected Add Comment

Post Review 20. Construction of Waling SNRTP-518-NCB-O-SNRTP-SYA-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 14/03/16 Dumrebhanjyang-Kakikakot Cause (60 28.20-PM-071-72 m span) DTO Syanja Expected Add Comment

Post Review 7. Construction of Bhagawati SNRTP-519-NCB-O-SNRTP-TAN-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 13/09/15 Rangapath(Chhirken-Maiwal-Nabrung- 29.07-PM-071-72 -) Road miantenance (14.95 Km)

DTO Tanahun Expected Add Comment

Post Review 8. Construction of SNRTP-522-NCB-O-SNRTP-TAN-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 13/09/15 Barbhanjyang-Patake Pasal Road 29.08.-PM-071-72 miantenance (12.5 Km) DTO Tanahun Expected Add Comment

Post Review 9. Construction of Baisjagar-Jyamire- SNRTP-523-NCB-O-SNRTP-TAN-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 13/09/15 Patikadi-Thanithan-Tuhurepasal Road 29.09.-PM-071-72 (17 Km) DTO Tanahun Expected Add Comment

Post Review 15. Construction of Khahare Khola SNRTP-524-NCB-O-SNRTP-KAS-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 13/09/15 bridge (40 m span ) 12.15-BRI-071-72 DTO Kaski Expected Add Comment

Post Review 8. Construction of Baghchaur-Kotmaula- SNRTP-526-NCB-O-SNRTP-SAR--W- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 12/03/15 Patihalna Rural Road Maintenance (12.1 NCB-25.08-PM-071-72 Km) DTO Sarlahi Expected Add Comment

Post Review 21. Putalikhet-Aaruchaur- Road SNRTP-528-NCB-O-SNRTP-SYA-W-NCB- N/A 30/06/14 30/07/14 29/08/14 N/A 13/09/14 45 14/03/16 Maintenance (7.5 Km) 28.21-UG-071-72 DTO Syanja Expected Add Comment

Post Review 9. Construction of Gadauli Khola Bridge SNRTP-532-NCB-O-SNRTP-SAR-W-NCB- N/A 10/01/14 10/01/14 09/02/14 N/A 06/03/14 55 06/03/15 across Karmaiya-Hathiwal Rd (20 Meter 25.09-BRI-071-72 Span) DTO Sarlahi Expected Add Comment

Post Review 1. Construction of Khadbari-Ramche- SNRTP-533-NCB-O-SNRTP-SANK-W- N/A 26/06/15 26/07/15 25/08/15 N/A 14/09/15 50 13/09/16 Lebrang-Dake-Bharabise Rd (27 Km) NCB-32.01-PM-071-72 DTO Sankhuwasava Expected Add Comment

Post Review 2. Construction of Taksar- Gumba - SNRTP-534-NCB-O-SNRTP-SAN-W-NCB- N/A 26/06/15 26/07/15 25/08/15 N/A 14/09/15 50 13/09/16 Dalgaun- Okhare - Dodhalekhani Rd (18 32.02-PM-071-72 Km) DTO Sankhuwasava Expected Add Comment

Post Review 1. Construction of Sukrabare - SNRTP-535-NCB-O-SNRTP-TER-W-NCB- N/A 26/06/15 26/07/15 25/08/15 N/A 14/09/15 50 13/09/16 Phakchamara - Hakparaghat Sadak Rd 33.01-PM-071-72 18 Km) DTO Terahthum Expected Add Comment

Post Review 2. Construction of Serma-jaljale-Isibu SNRTP-536-NCB-O-SNRTP-TER-W-NCB- N/A 26/06/15 26/07/15 25/08/15 N/A 14/09/15 50 13/09/16 Sadak Rd (18 Km) 33.02-PM-071-72 DTO Terahthum Expected Add Comment

Post Review 22. Construction of Saradi Khola Bridge SNRTP-537-NCB-O-SNRTP-SYA-W-NCB- N/A 26/06/15 26/07/15 25/08/15 N/A 14/09/15 50 13/09/16 along Naudanda Karkineta - Road 28.22-BRI-071-72 Maintenance (25 Km) DTO Syanja Expected Add Comment

Post Review 6 Kalaiya -Gunjbhawanipur- Malahi SNRTP-538-NCB-O-SNRTP-BAR-W-NCB- N/A 02/10/15 01/11/15 26/11/15 N/A 16/12/15 45 17/03/17 Road (18.31 Km) 3.06-UG-071-72 DTO Bara Expected Add Comment

Post Review 7 Piparpati Bairiya Road (9 Km) SNRTP-539-NCB-O-SNRTP-BAR-W-NCB- N/A 02/10/15 01/11/15 26/11/15 N/A 16/12/15 45 17/06/16 3.07-PM-071-72 DTO Bara Expected Add Comment

Post Review 4.Patle-Duipipal-Kolputar Road (15.00 SNRTP-540-NCB-O-SNRTP-NUW-W- N/A 02/10/15 01/11/15 26/11/15 N/A 16/12/15 45 15/06/17 km) NCB-16.04-UG-070-71 DTO Nuwakot Expected Add Comment

Post Review 6. Construction of Shivalawa-Labani-Ma. SNRTP-547-NCB-O-SNRTP-KAP-W-NCB- N/A 08/10/15 08/11/15 08/12/15 N/A 07/01/16 60 07/07/17 Ra. Ma Road (15Km) 11.06-UG-072-73 DTO Kapilbastu Expected Add Comment

Post Review 9. Construction of Bani-Dekhatvuli-Kanja-SNRTP-548-NCB-O-SNRTP-KAN--W- N/A 12/10/15 12/11/15 12/12/15 N/A 26/01/16 75 26/07/17 Shankarpur- NCB-10.09-UG-072-73 Panchagadiya,Baisebuchawa (Dodhapul) Road ( 7 KM) DTO Kanchanpur Expected Add Comment

Post Review 10. Construction of Chapaghat-Tharpek- SNRTP-549-NCB-O-SNRTP-TAN-W-NCB- N/A 08/10/15 08/11/15 08/12/15 N/A 07/01/16 60 07/07/17 Kotre(Sindhu and Laldhoj Marga) Road 29.10-UG-072-73 (12.3 Km) DTO Tanahun Expected Add Comment

Post Review 6 Khalanga-Jogitari-Arghakhanchi II SNRTP-560-NCB-O-SNRTP-PYU-W-NCB- N/A 08/01/16 08/02/16 23/02/16 N/A 19/03/16 40 19/03/17 package (6 Km) 19.06-UG-072-73 DTO Pyuthan Expected Add Comment

Post Review 7. Bagdula-Damti-Bahane-Syaulibang SNRTP-561-NCB-O-SNRTP-PYU-W-NCB- N/A 30/06/15 30/07/15 29/08/15 N/A 13/09/15 45 14/03/17 Road maintenance(4 Km) 19.07-PM-071-72 N/A 30/06/15 30/07/15 29/08/15 N/A 13/09/15 45 14/03/17

DTO Pyuthan Expected Add Comment

Post Review 5. Construction of Pedari Nala SNRTP-562-NCB-O-SNRTP-BAN-W-NCB- N/A 09/01/16 09/02/16 24/02/16 N/A 20/03/16 40 18/09/17 Bankatawa Bridge (50 m span) 2.05-BRI-072-73 DTO Banke Expected Add Comment

Post Review 11.Kalakate-Gadhawa-Bela-Rajpur Road SNRTP-564-NCB-O-SNRTP-DAN-W- N/A 09/01/16 09/02/16 24/02/16 N/A 20/03/16 40 20/03/17 (7.14 Km) NCB-5.11-UG-072-73 DTO Dang Expected Add Comment

Post Review 14. Bijukhol Bridge along Buddichaur- SNRTP-565-NCB-O-SNRTP-SUR-W-NCB- N/A 09/01/16 09/02/16 24/02/16 N/A 20/03/16 40 20/03/17 Guttu-Bijuwara-Benighat Doti Dipayal 27.14-BRI-072-73 Road (25 m span) across Badichaur- Guttu Rd. DTO Surkhet Expected Add Comment

Post Review 15. Mainghat khola Bridge along SNRTP-566-NCB-O-SNRTP-SUR-W-NCB- N/A 09/01/16 09/02/16 24/02/16 N/A 20/03/16 40 20/03/17 Buddichaur- Guttu-Bijuwara-Benighat 27.15-BRI-072-73 Doti Dipayal Road (25 m span) across Badichaur-Guttu Rd. DTO Surkhet Expected Add Comment

Post Review 6. Trisuli-Deurali-Meghang Khimtang- SNRTP-567-NCB-O-SNRTP-NUW-W- N/A 02/10/15 01/11/15 26/11/15 N/A 16/12/15 45 15/12/16 Thamby Khola Road (13.00 km NCB-16.06-PM-070-71

DTO Nuwakot Expected Add Comment

Post Review 7 .Mandredhunga – Khargabhanjyang- SNRTP-568-NCB-O-SNRTP-NUW-W- N/A 08/01/16 08/02/16 23/02/16 N/A 19/03/16 40 19/03/17 Gorsyang –Dangsing -Kaphal pani Road NCB-16.07-UG-070-71 (0- 12.00 km)

DTO Nuwakot Expected Add Comment

Post Review 5. Ranipuwa-Chaturale-Belkot-Tadi- SNRTP-569-NCB-O-SNRTP-NUW-W- N/A 08/10/15 08/11/15 23/11/15 N/A 18/12/15 40 17/06/17 Bridge Road (13.00 km) NCB-16.05-UG-070-71 DTO Nuwakot Expected Add Comment

Post Review 3. Construction of Khandbari-Badreni- SNRTP-574-NCB-O-SNRTP-SANK-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 wana-ligling-chainpur Rd (28 Km) NCB-32.03-PM-072-73

DTO Sankhuwasava Expected Add Comment

Post Review 4. Construction of Rammandir- SNRTP-575-NCB-O-SNRTP-SANK-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Update Okharbote-Mawadin-Nundhaki Rd (20 NCB-32.04-PM-072-73 Internal ID Km) (SNRTP-SANK- W-NCB-32.04- PM-072-73) 02/04/2016 06:15 DTO Sankhuwasava Expected Add Comment

Post Review 5. Construction of Tiwari-Bhanjyang- SNRTP-576-NCB-O-SNRTP-BHOJ-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Chyangre-Bastim Thulogaon Duma Sano NCB-31.05-PM-072-73 Duma Road Rd (15 Km) N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17

DTO Bhojpur Expected Add Comment

Post Review 6. Construction of Rupani Kataiya SNRTP-577-NCB-O-SNRTP-SAP-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Malekpura Lokharm Sadak Road Rd (33 24.06-PM-072-73 Km) DTO Saptari Expected Add Comment

Post Review 10. Construction of Tapeshwori SNRTP-578-NCB-O-SNRTP-UDA-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Bhagalpur Rampur Road (24 Km NCB-30.10-PM-072-73 DTO Udaypur Expected Add Comment

Post Review 13. Construction of Tarengana SNRTP-579-NCB-O-SNRTP-SIR-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Mahadevsthan Rd 26.13-PM-072-73 DTO Siraha Expected Add Comment

Post Review 14. Construction of Dhangadi Patari SNRTP-580-NCB-O-SNRTP-SIR-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 KachnariRd (12 km) 26.14-PM-072-73 DTO Siraha Expected Add Comment

Post Review 16. Construction of Puspalpur Ichhapur SNRTP-581-NCB-O-SNRTP-DHAN-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Tarapati Rd (17 Km) NCB-7.16-PM-072-73 DTO Dhanusha Expected Add Comment

Post Review 17. Construction of Balha-Gotha SNRTP-582-NCB-O-SNRTP-DHAN-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Saghara Lakkar Road (13 Km) NCB-7.17-PM-072-73 DTO Dhanusha Expected Add Comment

Post Review 12. Construction of Sonaul-Sahasaula SNRTP-583-NCB-O-SNRTP-MAH--W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Laxminiya Basbitti RoadRd (17 Km) NCB-13.12-PM-072-73

DTO Mahottari Expected Add Comment

Post Review 10. Construction of Parsa Riterchor SNRTP-584-NCB-O-SNRTP-SAR-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Update Road (11 Km) 25.10-PM-072-73 Internal ID (SNRTP-SAR-W- NCB-25.10-PM- 072-73) 02/04/2016 02:44 DTO Sarlahi Expected Add Comment

Post Review 11. Construction of Raniganj Parwanipur SNRTP-585-NCB-O-SNRTP-SAR-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Road (8 Km) 25.11-PM-072-73 DTO Sarlahi Expected Add Comment

Post Review 12.Periodic maintenance of Bridge SNRTP-586-NCB-O-SNRTP-SAR-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 (Dhangra Khola) (0.02 Span ) 25.12-PM-072-73 DTO Sarlahi Expected Add Comment

Post Review 13. Periodic maintenance of Causeway SNRTP-587-NCB-O-SNRTP-SAR-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 (0.01 Km) 25.13-PM-072-73 DTO Sarlahi Expected Add Comment Post Review 6. Construction of Janakitole-Bhishwa SNRTP-588-NCB-O-SNRTP-PAR-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Road (10 Km) 18.06-PM-072-73 DTO Parsa Expected Add Comment

Post Review 7. Construction of Mahuwan-Baluwa- SNRTP-589-NCB-O-SNRTP-PAR-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Deurbana-Gaadi Road (12 Km) 18.07-PM-072-73

DTO Parsa Expected Add Comment

Post Review 6 Construction of Kolbi Maduwa Road SNRTP-590-NCB-O-SNRTP-BAR-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Update (11.15 Km) 3.08-PM-072-73 Internal ID (SNRTP-BAR-W- NCB-3.08-PM- 072-73) 02/04/2016 02:37 DTO Bara Expected Add Comment

Post Review 7 Construction of Khakhariya Pheta SNRTP-591-NCB-O-SNRTP-BAR-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Update Motisar Kalaiyar Road (6.14 Km) 3.09-PM-072-73 Internal ID (SNRTP-BAR-W- NCB-3.09-PM- 072-73) 02/04/2016 02:38 DTO Bara Expected Add Comment

Post Review 6 .Construction of Padrang Ichung SNRTP-592-NCB-O-SNRTP-MAK-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Budhichaur Road (8.01 Km) NCB-14.06-PM-072-73 DTO Makawanpur Expected Add Comment

Post Review 7. Construction of Hepinge Khahare SNRTP-593-NCB-O-SNRTP-DHA-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Ringe Satdobato Chimchok Ri Road 10 NCB-6.07 PM-072-73 Km) DTO Dharding Expected Add Comment

Post Review 8 Construction of Nuwakot-Bageshwori- SNRTP-594-NCB-O-SNRTP-NUW-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Urleni (10 Km) NCB-16.08-PM-072-73 DTO Nuwakot Expected Add Comment

Post Review 9. Construction of Nuwakot-Bageshwori- SNRTP-595-NCB-O-SNRTP-NUW-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Activity Urleni (10 Km) NCB-16.09-PM-072-73 Cancelled 19/05/2016 06:19 DTO Nuwakot Activity Cancelled Add Comment

Post Review 3. Construction of Kalikasthan Jibjibe SNRTP-596-NCB-O-SNRTP-RAS-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Sarsung Rd (6 Km) 20.03-PM-072-73 DTO Rasuwa Expected Add Comment

Post Review 4. Construction of Dharapani-Rupsepani- SNRTP-597-NCB-O-SNRTP-RAS-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Bhorle(10.4 Km) 20.04-PM-072-73 DTO Rasuwa Expected Add Comment Post Review 1. Construction of Naubise Chautara SNRTP-598-NCB-O-SNRTP-SIND-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Update Melamchi Rd (13 Km) NCB-34.01-PM-072-73 Internal ID (SNRTP-SIND- W-NCB-34.01- PM-072-73) 02/04/2016 02:42 DTO Sindhupalchowk Expected Add Comment

Post Review 16. Construction of Baddichaur-Guttu SNRTP-599-NCB-O-SNRTP-SUR-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Road (12 Km) 27.16-PM-072-73 DTO Surkhet Expected Add Comment

Post Review 8. Construction of Periodic Manitenance SNRTP-600-NCB-O-SNRTP-PAL-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 of Causeways along Banstari-Jhadewa- 17.08-PM-072-73 Gothadi Road (171 m) (18 Nos)

DTO Palpa Expected Add Comment

Post Review 6. Construction of Pikhuwa Khola Bridge SNRTP-601-NCB-O-SNRTP-BHOJ-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 (75 m. Span) NCB-31.06-BRI-072-73 DTO Bhojpur Expected Add Comment

Post Review 7. Construction of Behul Khola Bridge SNRTP-602-NCB-O-SNRTP-SAP-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Activity (60 m. Span) 24.07-BRI-072-73 Cancelled 09/05/2016 07:58 DTO Saptari Activity Cancelled Add Comment

Post Review 8. Construction of Jita Khola Bridge-1 SNRTP-603-NCB-O-SNRTP-SAP-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 (15 m. Span) 24.08-BRI-072-73 DTO Saptari Expected Add Comment

Post Review 9. Construction of Jita Khola Bridge-2 SNRTP-604-NCB-O-SNRTP-SAP-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 (50 m. Span) 24.09-BRI-072-73 DTO Saptari Expected Add Comment

Post Review 10. Construction of Patharwa Khola SNRTP-605-NCB-O-SNRTP-SAP-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Bridge (15 m. Span) 24.10-BRI-072-73 DTO Saptari Expected Add Comment

Post Review 9. Construction of Chhalditari- SNRTP-606-NCB-O-SNRTP-GUL--W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Thaddhunga-Naya Pokhara-Ismamaidan- NCB-8.09 -UG-072-73 Arkhawang-Gagare Road (28.00 Km)

DTO Gulmi Expected Add Comment

Post Review 12.Construction of Causeway at SNRTP-607-NCB-O-SNRTP-DAN-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Mugreta Khola and Salbhauri Khola NCB-5.12-BRI-072-73 along Kalakate-Gadhawa-Bela-Rajpur Road (100 m) DTO Dang Expected Add Comment

Post Review 8. Periodic Manitenance of British Camp SNRTP-608-NCB-O-SNRTP-NAW-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 (Dumkibas)- Katusghari-Koltari-Bagaicha-NCB-15.08-PM-072-73 Deurali Road (17.20 Km)

DTO Nawalparasi Expected Add Comment

Post Review 6. Construction of Duduwa nala Road SNRTP-609-NCB-O-SNRTP-BAN-W-NCB- N/A 09/01/16 09/02/16 24/02/16 N/A 20/03/16 40 18/09/17 Bridge Betahani (40 m span) 2.06-BRI-072-73 DTO Banke Expected Add Comment

Post Review 6. Construction of Dundra Khola Bridge SNRTP-610-NCB-O-SNRTP-BRD-W-NCB- N/A 21/06/15 21/07/15 22/08/15 N/A 11/09/15 52 10/09/16 across Bardi Kusnba Rd. (25 m span) 4.06-BRI-071-72

DTO Bardia Contract under execution Add Comment

Post Review N/A 02/10/15 02/11/15 26/11/15 N/A 31/12/15 59 7. Construction of Jhangkhola Bridge SNRTP-611-NCB-O-SNRTP-BRD-W-NCB- N/A 21/06/15 21/07/15 22/08/15 N/A 11/09/15 52 11/03/17 across Bardi Kusnba Rd (25 m span) 4.07-BRI-071-72

DTO Bardia Expected Add Comment

Post Review 5. Construction of Lakhandehi Bridge SNRTP-612-NCB-O-SNRTP-SAR-W-NCB- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 10/04/17 across Kaudena-Janakinagar (300 Meter 25.05-BRI-071-72 Span) DTO Sarlahi Expected Add Comment

Post Review 5. Construction of Kalikathan Dhunge SNRTP-614-NCB-O-SNRTP-RAS-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Karmi Danda Banua (10.4 Km) 20.05-PM-072-73

DTO Rasuwa Expected Add Comment

Post Review 5. Construction of Dhadingbesi SNRTP-615-NCB-O-SNRTP-DHA-W- N/A 17/01/15 17/02/15 19/03/15 N/A 08/04/15 50 07/04/17 Sangkhosh Tipling Road(42 Km) NCB-6.05-UG-071-72 DTO Dharding Expected Add Comment

Post Review 9. Construction of Gaighat-Nepaltar- SNRTP-616-NCB-O-SNRTP-UDA-W- N/A 06/05/15 05/06/15 05/07/15 N/A 04/08/15 60 01/02/17 Udayapurgadhi (24 Km) NCB-30.09-PM-072-73 DTO Udaypur Expected Add Comment

Post Review 7. Construction of RCC Box Bridge over SNRTP-620-NCB-O-SNRTP-BAN-W-NCB- N/A 21/04/16 21/05/16 10/06/16 N/A 30/06/16 40 30/06/17 Update Gandhaili Nala (10 m span) 2.07-BRI-072-73 Internal ID (SNRTP-BAN-W- NCB-2.07-BRI- 072-73) 02/04/2016 03:58 DTO Banke Expected Add Comment

Post Review 1. Laxmibazar-Tinmane-Jumlichautara- SNRTP-622-NCB-O-SNRTP-GOR-W- N/A 21/04/16 21/05/16 10/06/16 N/A 30/06/16 40 30/06/17 Update Rainas-Butar Road (24 Km): NCB-35.01-UG-072-73 Internal ID (SNRTP-GOR-W- NCB-35.01-UG- 072-73) 02/04/2016 04:18 N/A 21/04/16 21/05/16 10/06/16 N/A 30/06/16 40 30/06/17

DTO Gorkha Expected Add Comment

Post Review 2. Chorkate-Chitrepokhari-Chipleti- SNRTP-623-NCB-O-SNRTP-GOR-W- N/A 21/04/16 21/05/16 10/06/16 N/A 30/06/16 40 30/06/17 Update Bhachchek-Bichaur Road (11 Km) NCB-35.02-UG-072-73 Internal ID (SNRTP-GOR-W- NCB-35.02-UG- 072-73) 02/04/2016 04:21 DTO Gorkha Expected Add Comment

Post Review 3. Syauli bazar-Bakrang-Mankamana SNRTP-624-NCB-O-SNRTP-GOR-W- N/A 21/04/16 21/05/16 10/06/16 N/A 30/06/16 40 30/06/17 Update Road (15 Km) NCB-35.03-UG-072-73 Internal ID (SNRTP-GOR-W- NCB-35.03-UG- 072-73) 02/04/2016 04:22 DTO Gorkha Expected Add Comment

Post Review 11. Construction of Baidana (Badaula) SNRTP-627-NCB-O-SNRTP-RUP-W-NCB- N/A 02/05/16 02/06/16 22/06/16 N/A 07/07/16 35 07/07/17 Update Khola Bridge (25 m span) across 22.11-BRI-072-73 Internal ID Mahilwar-Laxmipur-Jamuhe Rd (SNRTP-RUP-W- NCB-22.11-BRI- 072-73) 02/04/2016 04:54 DTO Rupandehi Expected Add Comment

Post Review 12. Construction of Ghamana Khola SNRTP-628-NCB-O-SNRTP-RUP-W-NCB- N/A 02/05/16 02/06/16 22/06/16 N/A 07/07/16 35 07/07/17 Update Bridge (22 m span two bridges) across 22.12-BRI-072-73 Internal ID Buddhanagar-Serawa-Kisauli-Suryapura (SNRTP-RUP-W- Rd NCB-22.12-BRI- 072-73) 02/04/2016 04:55 DTO Rupandehi Expected Add Comment

Post Review 9. Construction of Daldale-Munde SNRTP-631-NCB-O-SNRTP-NAW-W- N/A 21/04/16 21/05/16 10/06/16 N/A 30/06/16 40 30/06/17 Update Kumsot(Daldale-Munde Section) NCB-15.09-UG-072-73 Internal ID (SNRTP-NAW- W-NCB-15.09- UG-072-73) 02/04/2016 06:24 DTO Nawalparasi Expected Add Comment

Post Review 10. Construction of Trisuli-Deurali- SNRTP-632-NCB-O-SNRTP-NUW-W- N/A 09/02/16 11/03/16 10/04/16 N/A 25/04/16 45 25/04/17 Update Meghang Khimtang-Thamby Khola Road NCB-16.10-PM-072-73 Internal ID (9.00 km) (SNRTP-NUW- W-NCB-16.10- PM-072-73) 02/04/2016 05:34 DTO Nuwakot Expected Add Comment

Post Review 10. Construction of Bungdi Khola Bridge SNRTP-633-NCB-O-SNRTP-NAW-W- N/A 27/04/16 28/05/16 27/06/16 N/A 12/07/16 45 12/07/17 Update (40m) NCB-15.10-BRI-072-73 Internal ID (SNRTP-NAW- W-NCB-15.10- BRI-072-73) 02/04/2016 05:39 DTO Nuwakot Expected Add Comment

Post Review 11. Construction of Chauharbi Khola SNRTP-634-NCB-O-SNRTP-NAW-W- N/A 27/04/16 28/05/16 27/06/16 N/A 12/07/16 45 12/07/17 Update Bridge (20m) NCB-15.11-BRI-072-73 Internal ID (SNRTP-NAW- W-NCB-15.11- BRI-072-73) 02/04/2016 05:40 DTO Nuwakot Expected Add Comment

Post Review 16. Construction of Dobilla-Bagmara SNRTP-636-NCB-O-SNRTP-KAS-W-NCB- N/A 23/04/16 23/05/16 22/06/16 02/07/16 17/07/16 55 17/07/17 Update Road's Maintenance (8.5km): 12.16-PM-072-73 Internal ID (SNRTP-KAS-W- NCB-12.16-PM- 072-73) 22/04/2016 03:21 DTO Kaski Expected Add Comment

Post Review 17. Construction of Kaunkhola- SNRTP-637-NCB-O-SNRTP-KAS-W-NCB- N/A 23/04/16 23/05/16 22/06/16 02/07/16 17/07/16 55 17/07/17 Update Dudhpokhari Road Maintenance 12.17-PM-072-73 Internal ID (3.5km): (SNRTP-KAS-W- NCB-12.17-PM- 072-73) 22/04/2016 03:23 DTO Kaski Expected Add Comment

Post Review 11.. Construction of Dhande Khola SNRTP-638-NCB-O-SNRTP-NUW-W- N/A 23/04/16 23/05/16 22/06/16 02/07/16 17/07/16 55 15/01/18 Update Bridge (40 m) NCB-16.11-BRI-072-73 Internal ID (SNRTP-NUW- W-NCB-16.11- BRI-072-73) 22/04/2016 03:30 DTO Nuwakot Expected Add Comment

Post Review 14. Construction of Manusmara Bridge SNRTP-639-NCB-O-SNRTP-SAR-W-NCB- N/A 23/04/16 23/05/16 22/06/16 02/07/16 17/07/16 55 15/01/18 Update across Karmaiya-Hathiwal Rd (40 Meter 25.14-BRI-072-73 Internal ID Span) : (SNRTP-SAR-W- NCB-25.14-BRI- 072-73) 22/04/2016 04:02 DTO Sarlahi Expected Add Comment

Post Review 15.Construction of Salempur-Hirapur- SNRTP-640-NCB-O-SNRTP-SAR-W-NCB- N/A 23/04/16 23/05/16 22/06/16 02/07/16 17/07/16 55 17/07/18 Update Bagmati Road(20 km) 25.15-UG-072-73 Internal ID (SNRTP-SAR-W- NCB-25.15-UG- 072-73) 22/04/2016 04:04 DTO Sarlahi Expected Add Comment

Post Review 6. Construction of Syafur-Gatlang- SNRTP-641-NCB-O-SNRTP-RAS-W-NCB- N/A 29/04/16 29/05/16 13/06/16 N/A 28/06/16 30 22/04/18 Re-estimation Somdang (20 Km) 20.06-UG-072-73 of dates 22/04/2016 04:15

DTO Rasuwa Expected Add Comment

Post Review 7. Construction of Jharniya khola Bridge SNRTP-642-NCB-O-SNRTP-BRD-W-NCB- N/A 21/06/15 21/07/15 22/08/15 N/A 11/09/15 52 11/03/17 Update across Kusumbaghat-Baidi_MRM Road 4.07-BRI-071-72 Internal ID Rd (25 m span) (SNRTP-BRD-W- NCB-4.07-BRI- 071-72) 09/05/2016 07:25 DTO Bardia Contract under execution Add Comment

Post Review N/A 02/10/15 02/11/15 26/11/15 31/12/15 59 6. Construction ofTikkar-Buddhi-Bijgauri- SNRTP-643-NCB-O-SNRTP-KAP-W-NCB- N/A 30/04/16 30/05/16 29/06/16 N/A 13/07/16 44 13/07/16 Update Hulaki(12.Km) 11.07-PM-072-73 Internal ID (SNRTP-KAP-W- NCB-11.07-PM- 072-73) 09/05/2016 07:38 DTO Kapilbastu Expected Add Comment

Post Review 7. Construction of Bigul Khola Bridge (75 SNRTP-644-NCB-O-SNRTP-SAP-W-NCB- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Update m. Span) 24.07-BRI-072-73 Internal ID (SNRTP-SAP-W- NCB-24.07-BRI- 072-73) 09/05/2016 08:18 DTO Saptari Expected Add Comment

Post Review 11. Construction of Bigul Bridge (35 m. SNRTP-645-NCB-O-SNRTP-SAP-W-NCB- N/A 01/05/16 02/06/16 01/07/16 N/A 21/08/16 80 21/08/17 Update Span): 24.11-BRI-072-73 Internal ID (SNRTP-SAP-W- NCB-24.11-BRI- 072-73) 09/05/2016 08:16 DTO Saptari Expected Add Comment

Post Review 12. Construction of Bigul Khola Bridge SNRTP-646-NCB-O-SNRTP-SAP-W-NCB- N/A 01/05/16 02/06/16 01/07/16 N/A 21/08/16 80 21/08/17 Update across Kachan-Deuri Road (25m. Span) 24.12-BRI-072-73 Internal ID (SNRTP-SAP-W- NCB-24.12-BRI- 072-73) 09/05/2016 08:26 DTO Saptari Expected Add Comment

Post Review 13. Construction of Bigul Khola Bridge SNRTP-647-NCB-O-SNRTP-SAP-W-NCB- N/A 01/05/16 02/06/16 01/07/16 N/A 21/08/16 80 21/08/17 Update across Kadmaha Chowk-Chakdaha- 24.13-BRI-072-73 Internal ID Parampur-Tikuliya-Dhattitol Road (25 m. (SNRTP-SAP-W- Span) NCB-24.13-BRI- 072-73) 09/05/2016 08:28 DTO Saptari Expected Add Comment

Post Review 11. Construction of Gaighat-Phatepur SNRTP-648-NCB-O-SNRTP-UDA-W- N/A 26/04/16 26/05/16 27/05/16 N/A 28/05/16 2 26/11/17 Update Rd. (20 Km) NCB-30.11-UG-072-73 Internal ID (SNRTP-UDA-W- NCB-30.11-UG- 072-73) 09/05/2016 09:29 DTO Udayapur Expected Add Comment

Post Review 13. Periodic Manitenance of Causeways SNRTP-649-NCB-O-SNRTP-DAN-W- N/A 01/04/16 02/05/16 01/06/16 N/A 21/06/16 50 21/06/17 Update of the along Pawan Nagar Purandhara Road (4 NCB-5.13-PM-072-73 % of Bank Loan Nos)(160 m) Amount (100) 09/05/2016 10:13

DTO Dang Expected Add Comment

Post Review Method: .SQ (Sealed Quotation - Local 7. Periodic Manitenance of Causeways SNRTP-621-SQ-O-SNRTP-BHOJ-W-SQ- N/A 21/04/16 06/05/16 26/05/16 N/A 05/06/16 30 02/12/16 Update along different 4 roads ( 8 Nos 31.07-PM-072-73 Internal ID (SNRTP-BHOJ- W-SQ-31.07- PM-072-73) 02/04/2016 04:33 DTO Bhojpur Expected Add Comment

Post Review 14. Periodic Manitenance of two bridges SNRTP-625-SQ-O-SNRTP-ARG-W-SQ- N/A 21/04/16 06/05/16 26/05/16 N/A 05/06/16 30 02/12/16 Update Gochhekhola box culvert (B) and 1.14-PM-072-73 Internal ID Gochhekhola Bridge(A) at Ch. 00+000 (SNRTP-ARG-W- and at Ch. 00+250 SQ-1.14-PM- 072-73) 02/04/2016 04:40 DTO Arghakhanchi Expected Add Comment

Post Review

Category Goods: Activities ShowHide Total days of Process

End of No Objection to Contract Contract No Objection Publication / Evaluation Evaluation Signature (Complet Description Reference # Documents Invitation Bid Opening of Bids Report Date ed) Comment (between Bid Opening End of No Objection to Contract and Contract Contract No Objection Publication / Evaluation Evaluation Signature Signature (Complet Description Reference # Documents Invitation Bid Opening of Bids Report Date Date) ed) Comment P.P. - Executing Agency: 2016-5- Method: NCB (National Competitive 4. Procurement of Desk top Computers SNRTP-291-NCB-B-SNRTP-CPCU-G- N/A 11/02/15 13/03/15 12/04/15 N/A 12/05/15 60 11/07/15 95 Nos. including UPSs( 2 Nos for 33 NCB-04-070-71 DTOs, 6 Nos.for CPCU and 6 Nos. for Expected Add Comment two PMUs 4 Nos for IDD and remaining for others) Post Review 5. Photocopiers, Scanners, Fax SNRTP-292-NCB-B-SNRTP-CPCU-G- N/A 11/02/15 13/03/15 12/04/15 N/A 12/05/15 60 26/06/15 Machines and Printers 42 Nos. each ( 33 NCB-05-070-71 Nos for DTOs , 4 Nos. for Two PMUs and Expected Add Comment 3 No. for CPCU 2 nos for IDD) Post Review 6. Procurement of Lap tops and external SNRTP-293-NCB-B-SNRTP-CPCU-G- N/A 21/02/15 23/03/15 22/04/15 N/A 22/05/15 60 21/07/15 hard drives-87 Nos. each (70 Nos for 33 NCB-06-070-71 DTOs , 10 Nos. for two PIUs & 4 Nos. for Expected Add Comment CPCU 3 nos for IDD) Post Review 7. Procurement of GPS 40 Nos. and 18 SNRTP-294-NCB-B-SNRTP-CPCU-G- N/A 21/02/15 23/03/15 22/04/15 N/A 22/05/15 60 21/06/15 Nos. Total Station survey equipments NCB-07-070-71 for DTOs Expected Add Comment

Post Review 13. Procurement of Lab equipments for SNRTP-345-NCB-B-SNRTP-CPCU-G- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 11/06/15 33 districts NCB-13-071-72 Expected Add Comment

Post Review 14. Procurement of 36 Nos Generator SNRTP-346-NCB-B-SNRTP-CPCU-G- N/A 11/01/15 10/02/15 12/03/15 N/A 11/04/15 60 11/06/15 (10 KVA) for backup for 33 districts, NCB-14-071-72 PMU and CPCU Expected Add Comment

Post Review Method: SH (Shopping) 8. Purchase of Furnitures: Sofaset-6 SNRTP-295-CP-B-SNRTP-PMU1-G- N/A 17/02/15 04/03/15 11/03/15 N/A 16/03/15 12 25/03/15 sets,Executive Table-16 No.,Executive SHOP-08-070-71 Chair -16 Nos, Meeting Table-1 No,Tea- Table1No,Meeting Chair-10 Nos.White Board-3 Nos, Soft Board-4 Nos. for Expected Add Comment PMU1 : Post Review 9. Purchase of Furnitures: Sofaset-6 SNRTP-296-CP-B-SNRTP-PMU2-G- N/A 01/03/15 16/03/15 23/03/15 N/A 28/03/15 12 30/03/15 sets, Executive Table-16 No.,Executive SHOP-09-070-71 Chair -16 Nos, Meeting Table-1 No,Tea- Table -1 No, Meeting Chair-10 Expected Add Comment Nos.White Board-3 Nos, Soft Board-4 Nos. for PMU2 Post Review Method: DC (Direct contracting) 10. Purchase of Purchase of Different SNRTP-342-CD-B-SNRTP-CPCU-G-DP- N/A N/A N/A N/A N/A 17/03/15 20/03/15 goods with reference to 15 contracts 10-071-72 not exceeding Nrs. 300,000 for single contract This will be procured as per Expected Add Comment Government of Direct Purchase System as these are very small contracts. Single contract will not exceed USD 3,000.00. Post Review 11. Purchase of Different goods with SNRTP-343-CD-B-SNRTP-PMU1-G-DP- N/A 11/03/15 26/03/15 02/04/15 N/A 07/04/15 12 10/04/15 reference to 6 contracts not exceeding 11-071-072 Nrs. 300,000 for single contract

This will be procured as per Expected Add Comment Government of Nepal Direct Purchase System as these are very small contracts. Single contract will not exceed USD 3,000.00. Post Review 12. Purchase of Different goods with SNRTP-344-CD-B-SNRTP-PMU2-G-DP- N/A 11/03/15 26/03/15 02/04/15 N/A 07/04/15 12 14/04/15 reference to 6 contracts not exceeding 12-071-72 Nrs. 300,000 for single contract

This will be procured as per Expected Add Comment Government of Nepal Direct Purchase System as these are very small contracts. Single contract will not exceed USD 3,000.00. Post Review Method: ICB (International Competitive

Category Training: Activities ShowHide

No Objection Total days of End of Description Reference # to ATP Process Activity Comment P.P. - Executing Agency: 2016-5- Method: DC (Direct contracting) 1. SNRTP Project Orientation Training to SNRTP-353-CD-SC-SNRTP-CPCU-NCS- N/A 14/11/14 DDC, DTO & PMU DC-01-071-72 Lovely Banquet Hall, Jawlakhel Contract Completed Add Comm ent Post Review N/A 18/11/14 2. SNRTP Project Launching Work Shop SNRTP-354-CD-SC-SNRTP-CPCU-NCS- N/A 18/11/14 & MOU signing: SNRTP-CPCU-NCS-DP- DC-02-071-72 02-071-72 Hotel Himalaya , Kupondole Contract Completed Add Comm ent Post Review N/A 21/11/14 3. Road Pavement Design Training to SNRTP-355-CD-SC-SNRTP-CPCU-NCS- N/A 22/02/15 DTO officials DC-03-071-72 Expected Add Comm ent Post Review 4. Road Bridge Design to DTO and PMU SNRTP-356-CD-SC-SNRTP-CPCU-NCS- N/A 25/02/15 officials DC-04-071-72 Expected Add Comm ent Post Review 5. Procurement and Contract SNRTP-357-CD-SC-SNRTP-CPCU-NCS- N/A 25/02/15 Management Training to DTO & PMU DC-05-071-72 officials Nepal Administrative Staff College, Contract Completed Add Comm Jawlakhel ent Post Review N/A 22/01/15 6. Financial Management Trainings to SNRTP-358-CD-SC-SNRTP-CPCU-NCS- N/A 25/02/15 DDC & DTO Account Officials DC-06-071-72 Rajashwa Prashashan Talim Kendra, Contract Completed Add Comm Harihar Bhawan ent Post Review N/A 07/01/15 7. RuTIMS Application Training to DTO SNRTP-359-CD-SC-SNRTP-CPCU-NCS- N/A 25/03/15 and PMU officials DC-07-071-72 Expected Add Comm ent Post Review 8. Road Maintenance Training to DTO & SNRTP-360-CD-SC-SNRTP-CPCU-NCS- N/A 25/03/15 PMU officials DC-08-071-72 Expected Add Comm ent Post Review 9. Safeguard and Governance Training SNRTP-361-CD-SC-SNRTP-CPCU-NCS- N/A 25/04/15 to DDC, DTO and PMU officials DC-09-071-72 Expected Add Comm ent Post Review 10. Mobile Monitoring Training to DTO SNRTP-362-CD-SC-SNRTP-CPCU-NCS- N/A 20/04/15 and CBOs DC-10-071-72 Expected Add Comm ent Post Review 11. Quality Training to DTO officials SNRTP-363-CD-SC-SNRTP-CPCU-NCS- N/A 12/03/15 DC-11-071-72 Expected Add Comm ent Post Review

Category Consultants - Firms: Activities ShowHide Total days of Request for Final No (betweenProcess Bid Proposal No Objection No Objection Evaluation Objection Opening and End of (RFP) and to RFP and Invitation Bid Technical to Technical and to Contract Contract Contract Description Reference # Short List Short List for RFP Opening Evaluation Evaluation Negotiation Contract Signature Date Signature (Completed) P.P. - Executing Agency: 2016-5- Method: QCBS (Quality and Cost Based 35. Procurement of Consulting Firm for SNRTP-381-SBCC-CF-SNRTP-CPCU-CS- 22/03/15 N/A 25/03/15 24/04/15 24/05/15 N/A 13/06/15 N/A 03/07/15 70 04/02/19 baseline study of project districts QCBS-35-071/072 Expected Post Review 36. Procurement of Consulting Firms for SNRTP-382-SBCC-CF-SNRTP-CPCU-CS- 19/04/15 N/A 22/04/15 22/05/15 21/06/15 N/A 11/07/15 N/A 31/07/15 70 04/02/19 Market Infracture study of 75 districts QCBS-36-071/072 Expected Post Review 43. Consulting services for development SNRTP-529-SBCC-CF-SNRTP-CPCU-CS- N/A N/A 26/06/15 N/A N/A N/A 11/07/15 N/A 18/07/15 16/10/15 of eprocurement system for consultants SSS-43-071/072

Dry ice Solutions, Baneswar to be hired Expected

Post Review 47. Procurement of NGO for Beneficiary SNRTP-551-SBCC-CF-SNRTP-CPCU-S- 19/11/15 29/11/15 02/12/15 01/01/16 16/01/16 26/01/16 10/02/16 20/02/16 06/03/16 65 07/04/17 Monitoring : Eastern Cluster QCBS-46-072/073 Expected Prior Review 48. Procurement of NGO for Beneficiary SNRTP-552-SBCC-CF-SNRTP-CPCU-S- 19/11/15 29/11/15 02/12/15 01/01/16 16/01/16 26/01/16 10/02/16 20/02/16 06/03/16 65 07/04/17 Monitoring : Western Cluster QCBS-47-072/073 Expected Prior Review Method: CQS (Selection based on 39. Procurement of Consulting Firm for SNRTP-617-SCC-CF-SNRTP-CPCU-CS- 15/05/16 22/05/16 25/05/16 24/06/16 09/07/16 16/07/16 26/07/16 02/08/16 09/08/16 46 07/02/17 baseline study of project districts CQS-39-072/073 Expected Prior Review Method: SSS (Selection based on a International Consultant of UN SNRTP-167-SSF-CF-SNRTP-CPCU-S-SSS- 25/12/13 N/A N/A N/A N/A N/A N/A 02/03/14 12/03/14 11/03/19 Agency(ILO Nepal) for Rural Road 25-070-71 maintenance 5 years Contract under execution Prior Review 14/02/14 N/A 25/03/14 28/03/14 27. Institute of Engineering (IoE) , SNRTP-323-SSF-CF-SNRTP-CPCU-CS- N/A N/A 14/05/14 21/05/14 N/A N/A 20/07/14 N/A 21/07/14 61 20/10/14 Central Campus, Pulchowk, T.U for SSS-27-070-71 procurement and training of Single Contract Completed Source Consultant 27. Institute of Engineering (IoE) , Central Campus, Pulchowk, T.U for procurement and training of Single Source Consultant Post Review N/A N/A 02/07/14 04/07/14 N/A N/A 25/07/14 N/A 28/07/14 24 28/01/15 31. Hiring Consultant for the SNRTP-379-SSF-CF-SNRTP-CPCU-S-SSS- N/A N/A 15/08/14 04/09/14 N/A N/A 04/09/14 N/A 04/09/14 0 29/08/19 Maintenance , Upgrading and hosting of 31-071/072 RuTIMS Software : M/s Softwel Pvt.Ltd , New Baneshwar for 5 years

M/s Softwel Pvt.Ltd , New Baneshwar Contract under execution has developed Software. That's why this firm needs to be continued for the stated services.

Post Review N/A N/A 30/11/14 04/12/14 N/A N/A 20/12/14 N/A 29/12/14 25 Hiring Institute of Engineering (IoE) , SNRTP-545-SSF-CF-SNRTP-CPCU-S-SSS- N/A N/A 20/06/15 27/06/15 N/A N/A 28/06/15 N/A 01/07/15 4 08/07/15 Central Campus, Pulchowk, T.U for the 27/2-071-72 evaluation of proposals Single Source Consultant Justification: Technical evaluation of Expected proposals to be conducted immediately. Post Review International Consultant of UN Agency SNRTP-550-SSF-CF-SNRTP-CPCU-S-SSS- 30/08/15 N/A N/A N/A N/A N/A 07/09/15 15/09/15 21/09/15 15/06/19 (ILO Nepal Country Office) for Rural 45-072-73 Road maintenance in three new additional districts (Lamjung, Gorkha and Sindhupalchwok) for 4 years

Justification: ILO Nepal Country Office is Expected working in the other 33 districts

Prior Review 54. Hiring Institute of Engineering (IoE) , SNRTP-570-SSF-CF-SNRTP-CPCU-S-SSS- 28/03/16 N/A 30/03/16 31/03/16 N/A N/A 01/04/16 N/A 02/04/16 2 01/06/16 Central Campus, Pulchowk, T.U. for the 53/3-072-73 Procurement of of the Individual Consultants (42 nos) Justification: Institute of Engineering Expected (IoE), Central Campus, Pulchowk, T.U. will be hired for the selection of individual consultants Post Review 58. Hiring of NGO for VCDP and GAP SNRTP-613-SSF-CF-SNRTP-CPCU-S-SSS- 01/04/16 N/A N/A N/A N/A N/A N/A N/A 08/04/16 07/07/16 Training for 7 contracts in (Nuwakot, 57-072-73 Arghakhanchi, Syanja, Kanchanpur)

Will be hired M/S SKY Samaj Nepal, Expected Lalitpur Prior Review 59. Development of accounting SNRTP-618-SSF-CF-SNRTP-CPCU-S-SSS- 01/04/16 N/A N/A N/A N/A N/A N/A N/A 08/04/16 07/07/16 Software to generate monthly, 58-072-73 trimester report Will be hired M/S Himalayan Institute Expected of Technology, New Baneshwor, Kathmandu Prior Review 60. Development of webbase SNRTP-619-SSF-CF-SNRTP-CPCU-S-SSS- 01/04/16 N/A N/A N/A N/A N/A N/A N/A 08/04/16 07/07/16 application for Works Contracts 59-072-73 Will be hired M/S Rockmandu Expected Developer, Kathmandu Prior Review

Category Consultants - Individuals: Activities ShowHide Contract No Objection Signature Total days End Date Description Reference # to the TOR Date of Process of Activity Comment P.P. - Executing Agency: 2016-5- Method: IND (Individual Consultants - 1. Hiring Central Monitoring & SNRTP-297-IND-CI-SNRTP-CPCU-CS- N/A 25/02/15 04/02/19 Evaluation Consultant for 5 (Five) Years IND-01-070-71 Expected Add Comment Post Review 2. Hiring of Environmental Safeguard SNRTP-298-IND-CI-SNRTP-CPCU-CS- N/A 25/02/15 04/02/19 Specialist for 2.5 years intermittent IND-02-070-71 input of total 5 years Expected Add Comment Post Review 3. Hiring of Social Safeguard Specialist SNRTP-299-IND-CI-SNRTP-CPCU-CS- N/A 25/02/15 04/02/19 for 2.5 years intermittent input of total IND-03-070-71 5 years Expected Add Comment Post Review 4. Hiring of Financial Management SNRTP-300-IND-CI-SNRTP-CPCU-CS- N/A 05/02/14 04/06/19 Assistant for 5 years IND-04-070-71 Contract under execution Add Comment Post Review N/A 12/09/14 5. Procurement and Contract SNRTP-301-IND-CI-SNRTP-PMU1-CS- N/A 05/03/15 04/02/19 Management Consultant for 5 (Five) IND-05-070-71 years at cluster PMU 1 Expected Add Comment Post Review 6. Procurement and Contract SNRTP-302-IND-CI-SNRTP-PMU2-CS- N/A 05/03/15 04/02/19 Management Consultant for 5 (Five) IND-06-070-71 years at cluster PMU 2 Expected Add Comment Post Review 7. Hiring of Quality Monitoring SNRTP-303-IND-CI-SNRTP-PMU1-CS- N/A 25/02/15 04/02/19 Consultant for 5 (Five) Years at PMU1 IND-07-070-71 Expected Add Comment Post Review 8. Hiring of Quality Monitoring SNRTP-304-IND-CI-NRTP-PMU2-CS- N/A 25/02/15 04/02/19 Consultant for 5 (Five) Years at PMU2 IND-08-070-71 Expected Add Comment Post Review 9. Hiring of Road Design Specialist for 5 SNRTP-305-IND-CI-SNRTP-PMU1-CS- N/A 25/02/15 04/02/17 Years at PMU1 IND-09-070-71 Expected Add Comment Post Review 10. Hiring of Road Design Specialist for 5 SNRTP-306-IND-CI-SNRTP-PMU2-CS- N/A 25/02/15 04/02/17 Years at PMU2 IND-10-070-71 Expected Add Comment Post Review 11. Hiring of Bridge Design Specialist for SNRTP-307-IND-CI-SNRTP-PMU1-CS- N/A 05/03/15 04/02/17 5 Years at PMU1 IND-11-070-71 Expected Add Comment Post Review 12. Hiring of Bridge Design Specialist for SNRTP-308-IND-CI-SNRTP-PMU2-CS- N/A 05/03/15 04/02/17 5 Years at PMU2 IND-12-070-71 Expected Add Comment Post Review 13. Hiring of Social Development Expert SNRTP-309-IND-CI-SNRTP-PMU1-CS- N/A 05/03/15 04/02/19 for 5 (Five)years at PIU 1: IND-13-070-71 Expected Add Comment Post Review 14. Hiring of Social Development Expert SNRTP-310-IND-CI-SNRTP-PMU2-CS- N/A 05/03/15 04/02/19 for 5 (Five)years at PMU2 IND-14-070-71 Expected Add Comment Post Review 15. Hiring of Environmental Safeguard SNRTP-311-IND-CI-SNRTP-PMU1-CS- N/A 05/03/15 04/02/19 Consultant for 5 years at PMU1 IND-15-070-71 Expected Add Comment Post Review 16. Hiring of Environmental Safeguard SNRTP-312-IND-CI-SNRTP-PMU2-CS- N/A 05/03/15 04/02/19 Consultant for 5 years at PMU2 IND-16-070-71 Expected Add Comment 16. Hiring of Environmental Safeguard Consultant for 5 years at PMU2

Post Review 17. Hiring of Financial Management SNRTP-313-IND-CI-SNRTP-PMU1-CS- N/A 05/03/15 04/06/19 Assistant for 5 years at PMU1 IND-17-070-71 Expected Add Comment Post Review 18 Hiring of Financial Management SNRTP-314-IND-CI-SNRTP-PMU2-CS- N/A 05/03/15 04/06/19 Assistant for 5 years at PMU2 IND-18-070-71 Expected Add Comment Post Review 19. Hiring of Senior Lab. Technician 2 SNRTP-315-IND-CI-SNRTP-PMU1-CS- N/A 05/03/15 04/02/19 Nos for 5 (five) years at PMU1 IND-19-070-71 Expected Add Comment Post Review 20. Hiring of Senior Lab. Technician 2 SNRTP-316-IND-CI-SNRTP-PMU2-CS- N/A 05/03/15 04/02/19 Nos for 5 (five) years at PMU2 IND-20-070-71 Expected Add Comment Post Review 21. Hiring of Project Support Engineers SNRTP-317-IND-CI-SNRTP-PMU1-CS- N/A 05/03/15 04/02/19 for 16 Project Districts corresponding to IND-21-070-71 PMU1 for 5 years(32 Nos)

. There will be about 32 individual Expected Add Comment contracts. The value of single individual contract will not be of more than NPR of 09.00 million Post Review 22. Hiring of Project Support Engineers SNRTP-318-IND-CI-SNRTP-PMU2-CS- N/A 05/03/15 04/02/19 for 17 Project Districts corresponding to IND-22--070-71 PMU2 for 5 years(34 Nos):

There will be about 34 individual Expected Add Comment contracts. The value of single individual contract will not be of more than NPR of 09.00 million Post Review 23. Hiring of Safeguard Consultant for SNRTP-319-IND-CI-SNRTP-PMU1-CS- N/A 05/03/15 04/02/19 Project districts under PMU1 for 5 IND-23-070-71 (Five)years at 16 DTOs (16 Nos) There will be about 16 individual Expected Add Comment contracts. The value of single individual contract will not be of more than NPR of 03.38 million Post Review 24. Hiring of Safeguard Consultant for SNRTP-320-IND-CI-SNRTP-PMU2-CS- N/A 05/03/15 04/02/19 Project districts under PMU2 for 5 IND-24-070-71 (Five)years at PMU1 (17 Nos) There will be about 17 individual Expected Add Comment contracts. The value of single individual contract will not be of more than NPR of 03.38 million Post Review 26. Short Term Consultants 4 Nos for 12 SNRTP-321-IND-CI-SNRTP-CPCU-CS- N/A 12/03/14 11/03/15 months as and when required in IND-26-070-71 diferrent discipline : Contract Completed Add Comment Post Review N/A 21/10/14 31/01/15 30. Hiring of Financial Management SNRTP-348-IND-CI-SNRTP-CPCU-S-IND- N/A 15/02/15 14/10/17 Expert Individual Consultant 30-071-72 intermittent ( 5 months in a year) for Expected Add Comment Five years Post Review 33. Procurement of gender specilist SNRTP-351-IND-CI-SNRTP-CPCU-S-IND- N/A 15/02/15 14/10/17 intermittent ( 6 months over the period 33-071/072 of 3 years) Expected Add Comment Post Review 38. Short Term Consultants (Social SNRTP-377-IND-CI-SNRTP-CPCU-CS- N/A 10/02/15 11/04/15 safeguard Rajendra Pandit and SSS-38-071-72 (Environmental Safeguard) Mr. Sita Ram Kandel ) 2 Nos for 2 months till permanentally recruitment of Consultant Above two Consultants have worked till Expected Add Comment 31 January 2015. Now they are needed to continue the services till the permanent recruitment of the Consultants. Post Review 40. Procurement of Individual Social SNRTP-387-IND-CI-SNRTP-CPCU-CS- N/A 05/05/15 02/10/15 Development Expert for global IND-40-071/072 (umbrella) ESMS Expected Add Comment Post Review 41. Procurement of Individual SNRTP-388-IND-CI-SNRTP-CPCU-CS- N/A 10/05/15 09/05/16 Environmental Specialist for global IND-41-071/072 (umbrella) ESMS Expected Add Comment Post Review 42. Procurement of Individual Quality SNRTP-389-IND-CI-SNRTP-CPCU-CS- N/A 20/05/15 19/05/19 Mgmt. Expert IND-42-071/072 Expected Add Comment Post Review 52. Procurement of Social safeguard SNRTP-557-IND-CI-SNRTP-CPCU-S-SSS- N/A 10/10/15 22/02/16 expert for umbrella ESMF for 4.5 51-072-73 months Justification: Urgent need of the Expected Add Comment consultants Post Review 53. Procurement of Environmental SNRTP-558-IND-CI-SNRTP-CPCU-S-SSS- N/A 10/10/15 22/02/16 safeguard expert for umbrella ESMF for 52-072-73 4.5 months Justification: Urgent need of the Expected Add Comment consultants Post Review 55. Project Support Engineers for SNRTP-571-IND-CI-SNRTP-CPCU-S-IND- N/A 02/05/16 02/05/19 Project Districts for 3 years (10 Nos) for 54-072-73 different DTOs- Single Contract does not exist more Expected Add Comment than NPR 4.70 million. There will be 10 individual contracts. Post Review 56. Hiring of Social Safeguard Consultant SNRTP-572-IND-CI-SNRTP-CPCU-S-IND- N/A 02/05/16 02/05/19 for Project Districts for 3 years (12 55-072-73 Nos)for different DTOs- Single Contract does not exist more Expected Add Comment than NPR 2.52 million. There will be 12 individual contracts. Post Review 57. Hiring of Environmental Consultants SNRTP-573-IND-CI-SNRTP-CPCU-S-IND- N/A 02/05/16 02/05/19 for Project Districts for 3 years (20 Nos) 56-072-73 for different DTOs Single Contract does not exist more Expected Add Comment than NPR 2.55 million. There will be 20 individual contracts. Post Review Method: SSS (Selection based on a 28. Hiring of Procurement Management SNRTP-324-SSF-CI-SNRTP-CPCU-CS- 15/09/14 15/02/15 14/02/17 Expert- 6 months Intermetint over the SSS-28-071-72 period of two year 15/09/14 15/02/15 14/02/17

Mr. Shakti Prasad Shrestha has been Expected Add Comment working in SEPA online system for different WB Projects. Prior Review 29. Hiring of Quality Management SNRTP-347-SSF-CI-SNRTP-CPCU-S-SSS- N/A 12/11/14 15/04/15 Expert for 6 month intermittent over 29-071/072 the period of two year Mr. Sudarshan Lal Shrestha has Contract under execution Add Comment developed Quality Assurance Manual(QAM) for Rural Roads. But as agreed with Mr. TTL SNRTP needs to develop QAM for Rural Transport including Bridges. Post Review N/A 21/10/14 32. Hiring of Transformation of RAIDP SNRTP-350-SSF-CI-SNRTP-CPCU-S-SSS- N/A 25/02/15 14/10/19 web Site to SNRTP web site and 32-071/072 Maintenance , Upgrading and hosting of newly created SNRTP web site : M/s itechies P.Ltd., Ktm 5 years:

M/s itechies P.Ltd has developed RAIDP Contract under execution Add Comment Web site. That's why this firm needs to be continued for the stated services.

Post Review N/A 28/12/14 37 Procurement of Inetrnational SNRTP-375-SSF-CI-SNRTP-CPCU-CS- N/A 05/04/15 25/05/15 Consultant Mr. Shahidur Khandkar for SSS-37-071/072 Baseline and impact study Expected Add Comment Post Review Hiring of IT Expert for the inspection of SNRTP-546-SSF-CI-SNRTP-CPCU-S-SSS- N/A 04/07/15 11/07/15 IT Equipments- Single Source Consultant 44-071-72 -Mr. Daya Sagar Baral

Mr. Daya Sagar Baral will be hired as he Expected Add Comment has expertise in the inspection of IT equipment and inspection of IT equipment are to be conducted immediately. Post Review