Technical Assistance Consultant’s Report

Project Number: TA 7917 July 2013

Republic of : Amu Irrigation System Rehabilitation (Feasibility Study Volume 1 Supplemental Report)

Prepared by Lahmeyer International in association with Info Capital Group

For the Ministry of Agriculture and Water Resources

This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents. (For project preparatory technical assistance: All the views expressed herein may not be incorporated into the proposed project’s design.

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Amu Bukhara Irrigation System Rehabilitation

SUPPLEMENTAL REPORT

Feasibility Study

Prepared for the Asian Development Bank and the Ministry of Agriculture and Water Resources of the Republic of Uzbekistan

(TA: 7917-UZB)

20 July 2013

Lahmeyer International in association with InfoCapital Group page i

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

CURRENCY EQUIVALENTS (as of 2 July 2012)

Currency Unit – Soum (UZS)

UZS1.00 = $0.00048 $1.00 = UZS2096.19

ABBREVIATIONS

ABIS – Amu Bukhara Irrigation System ABISOA – Amu Bukhara Irrigation System Operating Authority ADB – Asian Development Bank AES – agro-economic survey BISA – Basin Irrigation System Administration BVO – River Basin Water Management Organization CC – climate change CDM – Clean Development Mechanism CRU-WG – Climate Research Unit – Weather Generator DMI – domestic, municipal, and industrial EA – executing agency FAO – United Nations Food and Agriculture Organization GDP – gross domestic product GHG – greenhouse gas ha – hectare HGME – Hydrogeological Meliorative Expedition I&D – irrigation and drainage IE – irrigation efficiency IEE – initial environmental examination IPCC – Intergovernmental Panel on Climate Change IR – Inception Report ISA – Irrigation System Administration km – kilometer MAWR – Ministry of Agriculture and Water Resources MCA – Main Canal Administration MOU – Memorandum of Understanding MT million tonne O&M – operation and maintenance NGO – non-governmental organization POW – productivity of water PPTA – project preparatory technical assistance PSE&C – Pump Station, Energy and Communications RP – Resettlement Plan RRP – Report and Recommendations of the President SA – Social Assessment

Lahmeyer International in association with InfoCapital Group page ii

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

SCADA – supervisory control and data and acquisition SPS – Safeguard Policy Statement SRES – Special Report Emissions Scenarios TOR – terms of reference UNFCC – United Nations Framework Convention on Climate Change UZBS – Uzbek Soum (national currency) WUA – water users association

GLOSSARY

Bonitet Classification system for land productivity potential Dekhan Household plot used for households immediate food requirements and sale of surplus. Given to head of family for the livelong ownership. Size of dekhan farms: irrigated land 0.35 ha and 0.50 on non-irrigated area Glavgosecoexpertiza Main Directorate for State Ecological Expertise, or SEE Goskompriroda State Nature Protection Committee Khokim Province or District Governor Khokimiyat Local government authority Makhalla Collection of villages to create a community village Oblast Province (Russian version) Oblvodkhozy Province administration O’zuvnazorat Water inspectorate Rayon District (Russian version) Rayvodkhozy District administration Shirkat Cooperative farm, successor of former kolkhoz Turman District, smaller administrative unit of the viloyat Uzglavgidromet Chief Hydrometeorological Administration Viloyat Province administrative unit of Uzbekistan. Uzbekistan has 12 viloyats and 1 autonomous republic of Karakalpakstan

Lahmeyer International in association with InfoCapital Group page iii

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

CONTENTS

I. SUMMARY ...... 1 A. Background ...... 1 B. Scope of Supplemental Design Works ...... 1 II. UPDATED DESIGN CRITERIA ...... 2 A. Design Criteria ...... 2 B. Design Capacity and Design Flow ...... 3 1. Peak Flow (Historical Pump Records) ...... 3 2. Irrigation Water Requirements ...... 5 III. KHAMZA NEW PUMP STATION DESIGN ...... 11 A. Location and Layout ...... 11 B. Pump House Mechanical Equipment ...... 13 1. Components ...... 13 2. Pump Units Design Criteria ...... 14 3. Pump Characteristics and Layout ...... 18 4. Main and Maintenance Discharge Shut-Off Valves ...... 22 5. Technical Water Supply System ...... 24 6. Pumphouse Overhead Crane ...... 26 7. Oil Supply and Disposal System ...... 27 8. Drainage & Dewatering System ...... 28 9. Emergency Dewatering System ...... 31 10. Compressed Air System ...... 32 11. Fire Fighting Equipment and Alarm System ...... 33 12. Heating, Ventilation & Air Conditioning ...... 34 13. Mechanical Workshop Equipment ...... 34 14. Water Supply System ...... 35 C. Hydro-mechanical Equipment ...... 35 1. Intake Trash Racks and Embedded Parts ...... 35 2. Intake Stoplogs and Embedded Parts ...... 37 3. Trash Rack Cleaning Machine ...... 38 4. Intake Gantry Crane ...... 39 5. Discharge Pipe System ...... 40 D. Electrical Equipment ...... 42 1. Pump Station Power Supply ...... 42 2. Main Electrical Motors and Soft Starter (LCI) ...... 44 3. 6 kV High Voltage System ...... 45 4. Protection, Metering and Control Equipment ...... 46

Lahmeyer International in association with InfoCapital Group page iv

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

5. Low Voltage (400V) AC Supplies ...... 47 6. 6 / 0.4 kV Power Transformer ...... 48 7. DC-System and UPS ...... 48 8. Lighting ...... 49 9. 400V/230 V System ...... 49 10. Grounding System ...... 50 11. Instrumentation and Control System ...... 51 12. Emergency Diesel Generating Unit ...... 54 13. Earthing System ...... 55 14. Rules and Standards ...... 56 E. Civil Works ...... 57 1. Pump Station Building ...... 57 2. Intake Canal ...... 58 3. Forebay ...... 58 4. Intake Structure with Trash Racks ...... 58 5. Subsurface Galleries ...... 58 6. Discharge Pipelines ...... 59 7. Outlet Structure ...... 59 8. Discharge Canal ...... 59 9. Sedimentation Basin for Technical Water Supply ...... 59 10. Protection Dam ...... 60 11. Auxiliary Facilities ...... 60 F. Geotechnical Investigation ...... 60 1. Introduction ...... 60 2. Geotechnical Conditions ...... 61 3. Seismic Condition ...... 61 G. Topography ...... 62 1. Introduction ...... 62 2. Topographic Survey ...... 62 H. Summary Cost Estimate ...... 63 IV. UPDATED ECONOMIC AND FINANCIAL ANALYSIS ...... 64 A. Background to Supplemental Study and Analyses ...... 64 B. Approach to the Analysis ...... 64 C. Analysis Results ...... 65 D. Guide to Revised Tables ...... 67 V. ECONOMIC AND FINANCIAL ANALYSIS (LINKED DOCUMENT FOR RRP 44458) ...... 69 A. Approach and Methodology ...... 69 B. Key Assumptions ...... 69

Lahmeyer International in association with InfoCapital Group page v

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

C. Project Benefits ...... 69 D. Financial Analysis ...... 70 E. Economic Analysis ...... 75

List of Figures

Figure 1: Peak monthly flow rate by year (2006-2012) ...... 4 Figure 2: Map of Hydro-modules in the Amu Bukhara Irrigation System ...... 8 Figure 3: Estimated monthly irrigation water requirement for the Khamza New Pump Station during the summer vegetation period (Mm3 and m3/s) ...... 10 Figure 4: Selected Site Location of Khamza New Pump Station ...... 11 Figure 5: Layout Drawing for Khamza New Pump Station ...... 12 Figure 6: Relationship between Pump Type, Efficiency and Specific Pump Speed ...... 18 Figure 7: Expected Operation Diagram of Khamza New Pump Units ...... 19 Figure 8: Expected Pump Performance Diagram of Khamza New Pump Units ...... 20 Figure 9: Expected Performance Diagram of Khamza New Pump Units ...... 20 Figure 10: Optimum Diameter of Main Discharge Header ...... 41

List of Tables

Table 1: Historical pump records for Khamza 1 and Auxiliary Pump Stations – peak monthly volumes and flows (2006-2012) ...... 4 Table 2: Design service area for the Khamza New Pump Station ...... 5 Table 3: Cropping pattern on ABIS irrigated lands for calculating design irrigation water requirements (%) ...... 6 Table 4: Hydro-modules in the service area of the Khamza New Pump Station (%) ...... 7 Table 5: Weighted average net irrigation requirements (m3/ha) (by district) ...... 9 Table 6: Design estimates of irrigation efficiency ...... 9 Table 7: Estimated monthly pumping requirements for Khamza New Pump Station ...... 10 Table 8: Pump Speed and Specific Speed ...... 16 Table 9: Comparison of Alternative Pump Speeds for Khamza New Pump Units ...... 17 Table 10: Cooling Water Requirements ...... 25 Table 11: Power Calculation for the Khamza New Pump Station ...... 43 Table 12: Summary Cost Estimate for the Khamza New Pump Station ...... 63 Table 13: Base Case and Sensitivity Analysis – EIRR % ...... 66 Table 14: Financial Returns. UZS’000/ha. 2012 ...... 71 Table 15: Financial returns/ha. ‘SUM'000/ha ‘Without’ and ‘With-Project’ situations ...... 73 Table 16: Average financial returns per farm UZS '000/farm ‘Without’ and ‘With-Project’ situations ...... 74 Table 17: Total With-Project Saved Financial Farm Returns & Manual Wages (Reduced Cost Option) ...... 75 Table 18: EIRR Summary (%) ...... 77

Lahmeyer International in association with InfoCapital Group page vi

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Appendices

1. Protocol of Joint Meeting on Agreement of Design Criteria for Design of the Khamza New Pump Station under Amu-Bukhara Irrigation System Rehabilitation Project (5 June 2013) 2. Monthly Pump Records (2006 to 2012) – Khamza 1 Pump Station and Khamza Auxiliary Pump Station 3. Crop Irrigation Norms per Hydro-module (m3/ha) 4. Weighted Average Irrigation Norms by District (m3/ha) 5. Pumping Requirements for Khamza New Pump Station (m3/ha) 6. Geotechnical Investigation Report by UZSUVLOYIHA Design Institute for the Khamza New Pump Station 7. Topographical Survey Report by UZSUVLOYIHA Design Institute for the Khamza New Pump Station 8. Cost Estimate Breakdown for Khamza New Pump Station 9. Updated Cost Estimate Breakdowns for Khamza 2, Kuyu Mazar, Kizil Tepa, and Kizil Tepa Auxiliary Pump Stations 10. Updated Economic and Financial Analysis Tables 11. Updated Supporting Tables for Economic and Financial Analysis 12. Updated Financial Management Assessment

Lahmeyer International in association with InfoCapital Group page vii

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

I. SUMMARY

A. Background

1. The Final Report for the project preparatory technical assistance (PPTA 7917) for the proposed Amu Bukhara Irrigation System (ABIS) Rehabilitation Project was prepared by Lahmeyer International in association with InfoCapital Group and submitted to the Asian Development Bank (ADB) in March 2013. The PPTA prepared a feasibility study for the works to be financed under the investment project, and bid designs and documents for the first turnkey contract for one of the main pump stations to be modernized.

2. This Supplemental Report was prepared based on an increased scope of work for the PPTA in order to conduct tasks necessary to address requested revisions to the design of the Khamza New Pump Station.

3. The Khamza 1 Pump Station (64 m3/s) was prioritized during the PPTA because as the first main pump station in the ABIS it was originally commissioned in 1965 and has exceeded its design service life. In addition, a seismic stability investigation conducted during the PPTA found that the main pump building of the Khamza 1 Pump Station requires replacement.1 As a result during the PPTA a pump station design was prepared – termed the “Khamza New Pump Station” – that combined both existing plants with a combined design discharge capacity of 105 m3/s for an estimated cost of $140 million. Criteria for the design of the pump station were established during the Inception Phase and refined subsequently in direct discussions between ADB, MAWR, the UZSUVLOYIHA Design Institute, and the PPTA Consultant.

4. During the ADB Loan Fact Finding mission in March 2013 and in the ToR for the Supplemental Works, ADB and MAWR requested the PPTA Consultant to revise the design of the Khamza New Pump Station based on (i) a lower design discharge capacity, (ii) a 6 kV power supply to be compatible with the existing power sub-station, (iii) not combining the auxiliary pump station into the design, and (iv) applying other updated design criteria as summarized in the following section. The full set of updated design criteria are included in the Protocol in Appendix 1.

5. Consequently, the design, drawings, cost estimates and bidding documents for the Khamza New Pump Station were revised and updated as summarized in this Supplemental Report.

B. Scope of Supplemental Design Works

6. The scope of work for the supplemental design included:

Development of updated design criteria and approval by MAWR Preparation of three (3) preliminary design alternatives with cost estimations for different motor and pump set options

1 Refer to Book 1 of Volume 1 of the report Technical Investigation on Seismic Stability of Pumping Stations Khamza-1 and Kuyu Mazar and Recommendations on their Further Use within the Frame of “ABIS Rehabilitation Project”, Uzbekistan prepared by the Kuprik Scientific-Research Enterprise (Tashkent, 2012).

Lahmeyer International in association with InfoCapital Group page 1

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Preparation of the feasibility-level design for MAWR’s selected alternative Updating of the economic and financial analysis Updating of the Supply-Design-Install bidding documents

7. Design and engineering work related to the following are not included in this supplemental addendum: (i) the existing 6.6 kV power sub-station(s) or high voltage transmission lines; (ii) updating of the ADB social and environmental safeguards in the feasibility study, although the revised pump station design does not change substantially any of the previously assigned categories or conclusions regarding environmental impacts, resettlement, and land acquisition; and (iii) other ABIS main pump stations or sub-components in the proposed rehabilitation project.

II. UPDATED DESIGN CRITERIA

A. Design Criteria

8. A meeting was held in Tashkent on 5 June 2013 between the MAWR and PPTA Consultant to develop the approved design criteria for the Khamza New Pump Station. A copy of the signed Protocol endorsed by the Deputy Minister of the MAWR presenting the updated design criteria is included as Appendix 1.

9. Among other things, the updated design criteria include the following:

Design discharge capacity: 80 m3/s Power supply voltage: 6.6 kV Service area (net irrigated area): 72,000 ha Other requirements (eg, location/layout, pump type, auxiliary systems, building type, control system, etc.): same as Final Feasibility Study Report

10. Due to the reduction in design discharge capacity and the requirement of using a 6.6 kV power supply, several design parameters of the pump station were affected including (i) the minimum number of main pumps and stand-by pumps, (ii) the sizes and capacities of various auxiliary system components, (iii) the pump speed, (iv) the size and configuration of the switchgear, motors, and electrical power supply components, (v) the capacity of the new intake channel and discharge basin, (vi) diameter and configuration of the discharge pipelines, and (vii) the dimensions and layout of the main pump building and quantities of associated civil works.

11. The design of the Khamza New Pump Station as presented in the Final Feasibility Study Report included the replacement of the auxiliary pump station, which was built in 1981 adjacent to the existing Khamza 1 Pump Station. The updated design criteria do not include combining the capacity or operational functionality of the auxiliary pump station. As noted in the assessment report contained in Appendix 4 of Annex 2 of the Final Report, there has been significant deterioration to the electro-mechanical and electrical equipment at the auxiliary pump station, which previous deficiency inspections have called for the replacement/repair of. At the request of the MAWR, any necessary upgrades the Khamza Auxiliary Pump Station have not been included in the supplemental design works.

Lahmeyer International in association with InfoCapital Group page 2

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

B. Design Capacity and Design Flow

12. The design capacity and design flow of the pump units in the Khamza New Pump Station have been updated considering (i) the pumped discharges that have occurred during recent years (since 2006), and (ii) the estimated crop water requirements during the peak irrigation season (summer months) for the design service area and cropping pattern.

13. Per the requirements of the MAWR, pumping in recent years (2006 to 2012) by the Khamza Auxiliary Pump Station was considered in terms of examining historical pumping records in order to derive the peak pumping flow rate, together with the Khamza 1 Pump Station. However, according to the MAWR the Khamza Auxiliary Pump Station will continue to remain in service, and therefore is not being combined as part of the construction of the Khamza New Pump Station.2 This means that the design of the intake channel and other works required for the Khamza New Pump Station had to take into account the continued operation of the Khamza Auxiliary Pump Station.

14. Similarly, the operation of the Khamza 2 Pump Station was not presently considered in determining the required design capacity of the Khamza New Pump Station. It has previously been determined that at this pump station all the main pump units are continuously operated during the peak irrigation season, including the stand-by unit (refer to the Annex 2 of the Final Feasibility Study Report). If the irrigation demand in the future is such that this amount of pumping capacity is required from the Khamza 2 Pump Station, then when it is rehabilitated or re-constructed the need for additional stand-by pumps should be considered.

15. The required design capacity has been determined as 80 m3/s. This is consistent with both historical pump records and the estimated irrigation water requirements analysed in this supplemental report.

1. Peak Flow (Historical Pump Records)

16. The MAWR provided historical discharge records for the Khamza 1 and Khamza Auxiliary Pump Stations between 2006 and 2012 (refer to Appendix 2). Table 1 summarizes the pumping records in terms of the highest monthly volume (Mm3) each year and the equivalent flow rate (m 3/s). There are two irrigation seasons in Uzbekistan: vegetation, April to September; and non-vegetation, October to March. The peak pumping period occurs during the 3-month summer period from June to August, and depending on the year one of those months has the highest irrigation demand (usually July). During the 7-year period examined, the peak pumped flow rate ranged from approximately 63 to 81 m 3/s (refer to Figure 1), with an average peak flow rate of 68 m3/s. The highest average monthly flow rate of 81 m 3/s combined from both stations occurred in July 2010. Pumping from June to August represents on average about 46% of the annual pumped volume.

2 No funds have been allocated in the ABIS Rehabilitation Program for the rehabilitation/modernization of the Khamza Auxiliary Pump Station. This pump station will stay in operation only during the commissioning of the Khamza New Pump Station and then be deactivated.

Lahmeyer International in association with InfoCapital Group page 3

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Table 1: Historical pump records for Khamza 1 and Auxiliary Pump Stations – peak monthly volumes and flows (2006-2012) Volume (Mm3) 2006 2007 2008 2009 2010 2011 2012 Khamza 1 147.3 147.4 144.0 150.9 164.3 136.9 128.1 Khamza Aux. 40.6 50.7 49.9 18.9 53.6 15.8 28.4 (peak month) (Aug) (July) (June) (July) (July) (Aug) (June) Total 187.9 198.1 193.9 169.8 217.9 152.7 156.5

Flow (m3/s)† 2006 2007 2008 2009 2010 2011 2012 Khamza 1 55 55 54 56 61 51 48 Khamza Aux. 15 19 19 7 20 6 11 Total 70 74 72 63 81 57 58 † Based on assumption of continuous running of pumps during the full month period of peak demand. Source: MAWR (Tashkent), 2013

Figure 1: Peak monthly flow rate by year (2006-2012)

Peak Discharge from Khamza 1 and Khamza Auxiliary Pump Stations (2006 to 2012) 90

80 Total 70

60

Khamza 1 PS 50 /s) 3

(m 40

30

20 Khamza Auxiliary PS 10

0 2006 2007 2008 2009 2010 2011 2012

Source: ADB PPTA UZB 7917, 2013 -- Amu Bukhara Irrigation System Rehabilitation Project

17. During the non-vegetation season (October to March), the average monthly pumped volume from both stations is approximately 51 Mm3 (refer to Appendix 2), which is equivalent to a continuous pumping flow rate of about 19 m3/s. There is considerably more variability in the amount of pumping during the non-vegetation season, and the range in minimum monthly flows ranged from 9.4 to 14.6 m3/s. For design purposes the minimum required flow has been estimated as 20 m3/s.

Lahmeyer International in association with InfoCapital Group page 4

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

18. Note that the discharge records provided by the MAWR are not based on accurate flow meter readings taken for each pump. Instead, the pumped flow rate is recorded on the basis of the discharge from the whole pump station as measured in a rated section (hydro-post) of the ABMK downstream of the discharge basin, and checked with pump rating curves. As discussed in the site visit assessments in the Final Feasibility Study Report, the accuracy of such records is expected to lie within a range of approximately ±10-15%.

2. Irrigation Water Requirements

19. The breakdown of the 72,000 ha design service area is shown in Table 2.

Table 2: Design service area for the Khamza New Pump Station Area District (ha) Vabkent 6,996 Peshkun 6,605 Gijduvan 8,258 Shafirkan 8,943 7,906 Kiziltepa 8,892 Karmana 2,185 Karaul bazar 4,466 Kagan 5,069 Bukhara 9,000 3,680 Total 72,000 Source: Uzsuvloyiha, 2013

20. Table 3 summarizes the design cropping pattern by district provided by the MAWR. Cotton represents approximately one-third on average of the irrigated lands, and is over 40% in some districts. Winter wheat represents about 11% of the cropping pattern on average.

Lahmeyer International in association with InfoCapital Group page 5

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Table 3: Cropping pattern on ABIS irrigated lands for calculating design irrigation water requirements (%)

Bukhara Region Navoi Region

Crop Bukhara Gijduvan Kagan Prshkun Romitan Jondor Shafirkan Karaulbazar City Bukhara City Kagan Kiziltepa Karmana Winter wheat 6.4 16.4 7.3 14.2 10.1 10.7 7.8 5.3 19.5 6.3 0.0 9.0 11.8 Winter wheat with second 13.4 12.6 10.2 13.6 14.0 13.1 10.8 18.1 19.9 7.7 0.0 22.6 22.7 crop Cotton 38.9 40.4 38.0 38.2 43.3 44.4 43.1 36.0 35.5 12.8 0.0 27.4 30.7 Vegetables, melons, 18.8 19.1 25.4 11.2 18.8 16.8 15.4 18.7 5.9 36.7 87.1 12.5 15.1 potatoes + homestead land Fodder and alfalfa 8.4 4.4 5.6 14.5 4.0 4.7 9.6 8.7 10.9 13.5 4.9 5.2 5.3 Orchards and other trees 11.8 6.8 8.9 6.6 8.5 7.5 9.0 10.4 2.2 22.8 7.9 9.4 10.8 Fallow lands 2.4 0.3 4.5 1.7 1.3 2.8 4.2 2.9 6.0 0.1 0.0 13.7 3.5 Source: MAWR, 2013

Lahmeyer International in association with InfoCapital Group page 6

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

21. The calculation of crop water requirements (evapotranspiration and leaching) for the design service area of the Khamza New Pump Station (72,000 ha) was determined on the basis of ‘hydro-modules’ (pre-defined tables of irrigation requirements) where soil- meliorative conditions of the irrigated lands in the service area were estimated and updated. The published figures for irrigation requirements in each designated hydro-module are based on average climatic conditions of the particular area, soil type, depth to groundwater table, and crop water requirements. The computational techniques used by the PPTA Consultant for estimating crop water requirements are based on national standards and procedures in Uzbekistan. The hydro-modules reflect both irrigation water requirements in the vegetation and non-vegetation seasons, plus leaching irrigations done in the non- vegetation season.

22. The soil-meliorative zone maps and related information used by the PPTA Consultant were provided by the Uzsuvloyiha Design Institute in Tashkent and have been in regular use since the ABIS was constructed (refer to Figure 2) and accurately reflect the coverage of zones to be used for the determination of irrigation water requirements for the Khamza New Pump Station.

23. In the ABIS command area, there are areas represented by hydro-modules III, IV, V, VI and VII as summarized in Table 4. With the existing soil-ameliorative conditions hydro-module V represents about 62% of the districts in the on average, and about 16% in the Navoi Region. In the Navoi Region, hydro-modules IV and VI predominate, representing approximately 45% and 35% on average, respectively.

Table 4: Hydro-modules in the service area of the Khamza New Pump Station (%) III IV V VI VII Total Bukhara Bukhara 8 0 78 3 11 100 Vabkent 36 0 64 0 0 100 Jondor 0 8 69 0 23 100 Kagan 0 0 42 25 33 100 Karaulbazar 100 0 0 0 0 100 Peshkun 11 0 86 0 2 100 Romitan 6 2 83 0 8 100 Shafirkan 16 0 66 14 4 100 Gijduvan 9 5 69 3 14 100 Navoi Kiziltepa 2 32 32 28 7 100 Karmana 0 58 0 42 100 Source: Uzsuvloyiha, 2013

24. The standard (normative) irrigation rates for each hydro-module by crop type during the vegetation and non-vegetation seasons are presented in Appendix 3. The tables include prescribed irrigation values (m3/ha) pertaining to the: (i) crop, (ii) number of irrigations, (iii) irrigation period, and (iv) leaching requirement by salinity level. These hydro-modules are the calculated irrigation norms for agricultural crops in the Amu Darya Basin as prepared by the Uzgipromeliovodkhoz Design Institute.3

3 “Design Crop Irrigation Rates in the Basins of the Sirdarya and Amudarya” by V. Shredder et al. (1970).

Lahmeyer International in association with InfoCapital Group page 7

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Figure 2: Map of Hydro-modules in the Amu Bukhara Irrigation System

Source: Uzsuvloyiha, 2012

Lahmeyer International in association with InfoCapital Group page 8

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

25. Application of the hydro-modules coverage areas (ratios) by district in Table 4 to the irrigation norms in Appendix 3 provides the weighted average net irrigation requirements summarized in Table 5. On average the annual net irrigation water requirements in the Bukhara and Navoi Regions are approximately 8,701 m3/ha and 8,332 m3/ha, respectively. The monthly weighted average net irrigation requirements by district for each crop type are included in Appendix 4.

Table 5: Weighted average net irrigation requirements (m3/ha) (by district) Vegetation Non-Vegetation Total Bukhara Bukhara 6,517 2,495 9,012 Vabkent 6,391 2,188 8,580 Jondor 6,186 2,601 8,787 Kagan 5,632 2,754 8,385 Karaulbazar 6,172 1,918 8,090 Peshkun 6,429 2,357 8,786 Romitan 6,230 2,427 8,657 Shafirkan 6,569 2,457 9,026 Gijduvan 6,483 2,506 8,989 Navoi Kiziltepa 5,706 2,509 8,215 Karmana 5,988 2,461 8,449 Source: ADB PPTA UZB 7917, 2013 -- Amu Bukhara Irrigation System Rehabilitation Project

26. Estimates of irrigation efficiencies in the portions of the ABIS service area to be supplied by the Khamza New Pump Station were provided by the Uzsuvloyiha Design Institute. The estimated irrigation efficiencies range from 0.58 to 0.62 (refer to Table 6).

Table 6: Design estimates of irrigation efficiency District Irrigation Efficiency Vabkent 0.58 Peshkun 0.62 Gijduvan 0.61 Shafirkan 0.61 Romitan 0.61 Karaulbazar 0.62 Kagan 0.62 Bukhara 0.62 Jondor 0.61 Kiziltepa 0.58 Source: Uzsuvloyiha, 2013

27. The estimated irrigation efficiencies have to be applied to the net irrigation water requirements (Table 5 and Appendix 4) in order to determine the pumping requirements for the design service area. On this basis the calculated annual pumping requirement for the design service area is approximately 1,031.74 Mm3, with 742.85 Mm3 of water consumption occurring in the vegetation season, and 288.89 Mm3 in the non-vegetation season. The monthly pumping requirements by district for irrigation supplies from the Khamza New Pump Station are provided in Appendix 5.

Lahmeyer International in association with InfoCapital Group page 9

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

28. The estimated monthly pumping requirements for the Khamza New Pump Station are summarized in Table 7 and Figure 3. The month of July (month VII) represents the period of peak irrigation demand. Converting the irrigation water requirement in that month of 212.17 Mm3 assuming continuous pumping (24 hrs per day, 7 days per week) results in an equivalent design flow rate of approximately 79 m3/s.

Table 7: Estimated monthly pumping requirements for Khamza New Pump Station Monthly Water Equivalent Requirement Flow Rate Month (Mm3) (m3/s) I 0 0 II 76.67 31.7 III 116.45 43.5 IV 61.60 23.8 V 74.16 27.7 VI 127.34 49.1 VII 212.17 79.2 VII 186.86 69.8 IX 86.71 33.4 X 40.87 15.3 XI 29.42 11.4 XII 19.50 7.3 Source: ADB PPTA UZB 7917, 2013 -- Amu Bukhara Irrigation System Rehabilitation Project

Figure 3: Estimated monthly irrigation water requirement for the Khamza New Pump Station during the summer vegetation period (Mm3 and m3/s)

Estimated irrigation water requirements during vegetation season 250 80 Maximum = 79.2 m 3/s

70

200 60

50 150 ) 3 /s) 3 40 (m (Mm

100 30

20 50

10

0 0 April May June July August September

Source: ADB PPTA UZB 7917, 2013 -- Amu Bukhara Irrigation System Rehabilitation Project

Lahmeyer International in association with InfoCapital Group page 10

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

III. KHAMZA NEW PUMP STATION DESIGN

A. Location and Layout

29. The new location of the proposed pump station was tentatively selected as close as possible to the existing intake canal of Khamza 1 Pump Station (the ABMK 1 section of the main conveyance canal system), which would still allow construction works for Khamza New Pump Station to occur without affecting the water supplied by the Khamza 1 and Khamza Auxiliary Pump Stations. The proposed new construction site is about 600 m from the location of Khamza 1 Pump Station (refer to Figure 4).

30. The approximate coordinates of Khamza New Pump Station location are as follows (shown in Figure 4):

East: 064 04´ North: 039 20´

Figure 4: Selected Site Location of Khamza New Pump Station

Source: Present Study, 2013

31. The layout drawing of the Khamza New Pump Station is shown in Figure 5.

Lahmeyer International in association with InfoCapital Group page 11

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Figure 5: Layout Drawing for Khamza New Pump Station

Lahmeyer International in association with InfoCapital Group page 12

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

32. The pump station building for Khamza New Pump Station will consist of a substructure and superstructure. The main equipment such as main pump unit sets, switchgear and auxiliary pump station equipment will be installed in the pump station building. For power supply the existing high-voltage sub-station will be upgraded with new transformers and other equipment and a new transmission line extended to the new building.

33. A closed gallery for dewatering the main pump units, in case of maintenance, and a drainage sump for collecting seepage water will be located at the lowest elevation of the building. Pump unit sets will be of vertical centrifugal type. Main electric motors will be installed at pump house elevation of El. 185.65 m asl. The centre line of the pump volute case is at El. 179.85 m asl. A pump house overhead crane for installation, dismantling and maintenance work will be installed inside the pump house. Outside of the main pump station building additional facilities will be located for the emergency diesel generators, the workshop, office rooms, rooms for pump station personnel, and an oil turbine storage area.

34. An unlined intake canal will be constructed with the design discharge of 91.5 m3/s (maximum). To enable crossing of the intake canal to reach the existing Khamza 1 Pump Station and the sub-station a new bridge will be required.

35. Khamza New Pump Station will consist of the following structures: (i) diversion canal (ii) trash screen structure (iii) forebay (iv) pumping station building with intake chambers (v) discharge pipeline system (vi) sedimentation basin for technical water supply (vii) water discharge structures (viii) discharge canal (ix) auxiliary facilities and building (x) sub-station

36. The overall dimensions of the pump building are: (i) length approx. 74.0 m (ii) width approx. 20.3 m (iii) total height approx. 24.5 m

37. The pump station building is to be made of in-situ concrete divided by an expansion joint into two blocks.

B. Pump House Mechanical Equipment

1. Components

38. The Khamza New Pump Station mechanical equipment consists of the following equipment and systems: (i) Main pump units (ii) Main and maintenance discharge shut-off valve

Lahmeyer International in association with InfoCapital Group page 13

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

(iii) Technical water supply system (iv) Emergency dewatering system (v) Pumphouse overhead crane (vi) Compressed air system (vii) Oil supply and disposal system (viii) Drainage & dewatering system (ix) Workshop equipment (x) Fire fighting equipment and alarm system (xi) Water supply system (xii) Heating, ventilation & air conditioning

2. Pump Units Design Criteria

39. The design criteria for the pump units include the hydraulic pump station data, the required pump station capacity, government design guidelines, and operational aspects.

40. The Khamza New Pump Station is characterized by the following design elevations:

Intake Levels Intake sill level to pump chambers El. 180.46 m asl. Intake water levels Q = 20.0 m³/s 1) El. 184.88 m asl. Q = 50.8 m³/s 2) El. 186.48 m asl. Q = 80.0 m³/s 3) El. 187.52 m asl. Q = 91.5 m³/s 4) El. 187.85 m asl. Discharge Basin Levels Discharge basin sill level El. 224.20 m asl. Discharge canal sill level El. 226.95 m asl. Discharge basin water levels Q = 20.0 m³/s 1) El. 229.39 m asl. Q = 50.8 m³/s 2) El. 230.87 m asl. Q = 80.0 m³/s 3) El. 231.80 m asl. Q = 91.5 m³/s 4) El. 232.16 m asl.

Note: 1) Minimum discharge 2) Pump station design discharge 3) Rated pump station discharge with seven (7) pump units in operation 4) Maximum pump station discharge with eight (8) pump units in operation

41. The prevailing data for the required pump head and discharge present adequate hydraulic conditions for a vertically-installed, single suction, volute casing pump with Francis type pump impeller, which has a high efficiency.

42. The expected (high) sediment content of the diverted river water requires particular attention regarding the selection of erosion-resistant materials, or coating of components of the water passages and adequate access for the replacement or repair of eroded parts.

Lahmeyer International in association with InfoCapital Group page 14

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Selection of Number of Pump Units:

43. The number of pumps for Khamza New Pump Station aims to obtain a size not too large and requiring huge mechanical, electrical and hydro-mechanical installations, nor too small with many pumps and higher equipment, facility, and operation and maintenance costs. Further the availability of large pumps on the world market and number of possible suppliers for competition needs to be considered. Control of the irrigation water supply is more precise with a higher number of pumps than smaller number with high capacities.

44. By comparing the different aspects and the gained experience of already installed pumps for the existing pump stations a number of pumps in operation of seven (7) would be recommended for the Khamza New Pump Station.

45. For agricultural areas where pumping availability is 80% or lower of the year, or the interval between operations is insufficient to allow proper maintenance of equipment, standby capacity equal to the largest pumping unit should be provided. For the Khamza New Pump Station the standby capacity was selected as one (1) pump unit set. This will provide sufficient reserve during high peak load during the irrigation season from July to August.

46. Total number of pump units for the Khamza New Pump Station is considered with eight (8) including one (1) standby unit.

Selection of Pump Speed and Specific Speed:

47. The pump speed and specific speed (nq = n * Q0.5 / H0.75) selection for pump units is one of major criteria for the entire pump station design.

48. The abrasive solids, solids passing capability, efficiency, suction inlet conditions (e.g. Net-Positive-Suction-Head), equipment cost, and desired reliability need to be considered for the selection of the pump speed.

49. Table 8 provides a summary of the influence of pump speed on different conditions:

Lahmeyer International in association with InfoCapital Group page 15

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Table 8: Pump Speed and Specific Speed

CONDITION PUMP SPEED & SPECIFIC SPEED

Abrasives Lower pump speeds are better with regard to wear life for sliding abrasion. 2.5 The wear rate varies roughly as (RPM1/RPM2) factor.

Solids Passing Pump impellers with higher specific speeds nq have more openness to the

blade passages than lower nq Pumps.

-1 Efficiency Efficiency tends to increase with nq up to around 50 to 60 min and then

decrease with further increasing nq.

Cavitation Pumps with lower speeds generally have lower NPSH requirements and a wider allowable operating range than pumps with higher speeds.

Capital costs Pumps with higher speeds are physically smaller than lower speed pumps for the same duty point. Both motors and pumps are less expensive and occupy a smaller installation area.

Reliability Pumps with higher speed are less tolerant to difficult service conditions than lower speed pumps. Factors such as solids, cavitation, and off design-point operation may severely impact reliability. Any capital cost benefit may be eliminated by pre-mature equipment failure. For difficult applications, especially where high power requirement is involved, it is usually a good practice to be conservative with equipment speed.

Source: Present Study, 2013

50. For the pump units of the Khamza New Pump Station five (5) feasible pump alternatives with pump speeds from 250 to 375 min-1 were selected for further investigations. The investment costs were estimated for the pump speed alternatives considering the main pump components and the costs related to the civil works for the pump station building intake structures (refer to Table 9).

Lahmeyer International in association with InfoCapital Group page 16

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Table 9: Comparison of Alternative Pump Speeds for Khamza New Pump Units

Pump Data / Cost Alt. 1 Alt. 2 Alt. 3 Alt. 4 Alt. 5

Pump Speed, n 1/min 375 333 300 272 250

Specific Speed, nq 1/min 64 57 51 46 43

Setting Height (Centre Volute Case below min. m -9.2 -6.9 -5.0 -3.6 -2.2 intake WL)

Pump Impeller Dia. mm 2,025 2,185 2,335 2,485 2,625

Wear rate coefficient 2.5 - 1.8 1.3 1.0 0.8 0.6 (RPM1/RPM2)

Costs Pump Sets Mio. US$ 24.7 27.3 30.2 34.1 38.3 (pumps and motors)

Civil costs pump house Mio. US$ 18.9 14.8 11.0 8.9 6.8 and intake structure

Costs construction pit/ 11.6 10.7 10.0 9.1 7.8 Mio. US$ dewatering

TOTAL COSTS Mio. US$ 55.2 52.8 51.2 52.1 52.9

Source: Present Study, 2013

51. Alternative 3 with a pump speed of 300 min-1 would be the recommended pump speed with regard to the lowest investment costs for the pump set equipment and civil structures. Compared to the wear rate of Alternative 3, the wear rate of Alternative 4 would decrease by 20%. However, with new technologies to protect the wetted pump parts from abrasion such coatings of impellers and casings the pump units designed with a speed of 300 min -1 would still be the recommended alternative.

52. The pump specific speed has been determined with 51 min-1 using formula nq = n * Q 0.5 / H0.75; whereas Q = 11.25 m³/s, H = 53 m and n = 300 min-1 for the Khamza New pump units. The relationship between pump specific speed, pump type and hydraulic pump efficiency is shown in Figure 6. The selected pump type for Khamza New is of Francis vane with a maximum theoretical pump hydraulic efficiency of 93%.

Lahmeyer International in association with InfoCapital Group page 17

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Figure 6: Relationship between Pump Type, Efficiency and Specific Pump Speed

Source: Literature “Wasserkraftanlagen Planung, Bau und Betrieb Giesecke, Mosonyi”

3. Pump Characteristics and Layout

53. Main pump unit data are outlined below:

Type of pump single suction, volute casing pumps Orientation of installation vertical shaft Impeller diameter (discharge side outer) 2335 mm Number of pump units 8 (incl. 1 stand-by unit) Orientation of installation vertical shaft Orientation of rotation (viewed from top) anti-clockwise Maximum geodetic pump head 47.28 m Design geodetic pump head 44.39 m Minimum geodetic pump head 41.54 m Maximum total pump head *) 53.00 m Design total pump head 47.78 m Minimum total pump head 44.20 m Pump discharge at maximum total pump head 11.25 m³/s Setting height, centre of volute casing El. 179.85 m asl. -1 Pump speed 300 min Pump specific speed nq at maximum total pump head 51 min-1 Impeller type Francis vane type Max. pump shaft power requirement 6887 kW Note: *) with four (4) units in parallel operation

54. The operating range of the Khamza New pump units is shown in Figure 7. The pump performance diagrams show parallel operation with system head loss curves for minimum and maximum geodetic pump heads. The parallel operation of the four identical centrifugal pumps requires the losses of individual lines (head losses up to the collecting line) to be taken into account in the reduced pump characteristic curve.

Lahmeyer International in association with InfoCapital Group page 18

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Figure 7: Expected Operation Diagram of Khamza New Pump Units

Source: Present Study, 2013 55. The required discharge of 80 m³/s for Khamza New Pump Station is reached at the most unfavourable pump condition with maximum total pump head by four (4) units operating at one main discharge pipe with a total expected pump capacity of 45 m³/s and three (3) units operating at the second main discharge pipe with a total expected pump capacity of 35 m³/s.

56. The expected hydraulic parameters of the pump operation are presented in Figure 8 and 9. The diagrams show the expected pump head, pump hydraulic efficiency, pump shaft power and the NPSH_req. versus the pump flow.

57. The maximum pump shaft power of 6887 kW is reached at the lowest total pump head with expected maximum pump flow of 13.5 m³/s. The pump operating range is expected between 11.25 m³/s and 13.5 m³/s. The pump hydraulic efficiency expected maximum at 91.5 % at 11.25 m³/s.

58. The maximum expected NPSH_req. of 16.2 m is at pump flow of 13.5 m³/s. With a setting height of the volute casing of 179.85 m asl. (centre line) a cavitation free operation is guaranteed over the entire operating range; but will ultimately depend on the final dimensions of the selected pump and the hydraulic design of the water passages.

Lahmeyer International in association with InfoCapital Group page 19

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Figure 8: Expected Pump Performance Diagram of Khamza New Pump Units

(Pump Head, Hydraulic Efficiency via Pump Flow)

Source: Present Study, 2013

Figure 9: Expected Performance Diagram of Khamza New Pump Units

(Pump NPSH_req., Pump Shaft Power via Pump Flow)

Source: Present Study, 2013 59. The average canal discharge or pump station discharge for Khamza New Pump Station can be estimated with approximately 64% of the full pump station capacity of 80 m³/s. The pump design point is calculated for the average canal discharge of 50.8 m³/s with a design geodetic pump head of 44.39 m. Design total pump head is 47.55 m and design pump flow is 12.69 m³/s with two (2) pump units operating at each main discharge header.

Lahmeyer International in association with InfoCapital Group page 20

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

60. The Khamza New Pump Station will contain eight (8) vertical centrifugal pump units with Francis type runners including one (1) stand-by unit.

61. The pump spiral case will be embedded to the second stage concrete and incorporated into the pump house structure. The pump units will be directly coupled to the synchronous electrical drivers of 7,575 kW nominal capacity.

62. The eight (8) pump-sets will be installed with parallel intake chambers and parallel discharge pipes. Each pump intake will be protected by a trash rack. The pump discharge pipe will be equipped with a hydraulically-operated butterfly valve with a diameter of 2100 mm and electrical operated maintenance butterfly valve of 2300 mm diameter.

63. The new pump units for Khamza New Pump Station will consist mainly of:

(i) impeller of 13.4 stainless steel (ii) pump impeller wear rings (iii) pump shaft (iv) shaft coupling (v) pump cover (vi) pump volute casing (vii) suction cone (viii) hydrostatic type shaft seal (ix) pump guide bearing including lubrication oil system

64. The pump shaft will be guided by an oil lubricated guide bearing. The guide bearing will be cooled by oil-to-water heat exchangers. The thrust bearing for carrying the weight of the rotating parts of the pump and the motor as well as the hydraulic thrust, will be furnished as part of the electrical motor.

65. The shaft seal will preferably be water lubricated hydrostatic seal. An axial type design is preferred. The shaft seal can be removed and replaced easily. For lubrication for the hydrostatic shaft seal, water needs to be cleaned by the removal of all sand and silt particles as far as possible. The water for lubrication purposes will be provided by the technical water supply system, which cleanses water by use of fine filters with a mesh size of approx. 0.05 mm. The sealing elements will be of a self-compensating type and will adjust automatically for wear during their full service life.

66. Both the impeller and casing of the pumps will be provided with renewable wear rings. Replaceable shaft sleeves will be provided for the impeller and in the area of the shaft seals.

67. The volute casing shall be manufactured from several steel plate sections as welded construction. The number of sections shall be chosen suitably so that the water does not change its flow direction abruptly. The volute casing shall be welded as far as applicable in the manufacturer’s workshop.

68. The pump units and the associated equipment will include all instruments and safety devices necessary for the correct monitoring and safe operation of the installed equipment, e.g., bearing temperature measurement, vibration monitoring system, pressure measurements, etc.

Lahmeyer International in association with InfoCapital Group page 21

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

69. A pump model test according to Standard IEC 60193 “Hydraulic turbines, storage pumps and pump turbines – model test” shall be performed with a homologous pump model, if prototype pump tests cannot be performed at the hydraulic laboratory of the pump manufacturer due to limitations in capacity of the test facilities. The prototype pumps then shall cover all relevant hydraulic performance tests in accordance with EN ISO 9906 “Rotodynamic Pumps - Hydraulic Performance Acceptance Tests - Grades 1, 2 and 3”.

70. To monitor pump performance, it is recommended to measure each pump’s individual discharge by the Winter-Kennedy measurement method at the volute casing. Calibration of the Winter-Kennedy taps at the spiral case shall be determined during the model test.

71. Spare parts and tools for maintenance will be kept on site at the pump station own workshop building. Larger repairs will be carried out at the Central Workshop in Bukhara.

4. Main and Maintenance Discharge Shut-Off Valves

72. Each main pump will be equipped with a main butterfly shut-off valve and a maintenance butterfly discharge valve.

73. The main butterfly valves are designed for shutting off the discharge pipe before starting the main pumps and also after stopping of the main pumps for shutting off pipelines for inspection and repairs of the main pumps. The maintenance valves will be closed to enable repair and maintenance works on the main valves without interrupting the operation of other pumps by dewatering a complete main raiser pipe.

74. The main butterfly valves with a diameter of 2100 mm at each of the pump discharge side serve as main shut-off valve. The main butterfly valves are installed inside the pump house at El. 179.85 m asl. (valve centre line).

75. The maintenance valve will be designed with a diameter of 2300 mm and will be installed upstream of the main butterfly valve at El. 195.55 m asl. (valve centre line).

76. The maintenance main butterfly valve will be provided with a bypass and bypass valve. The bypass valve will be opened to balance the upstream and downstream pressure during opening of the maintenance valve.

77. The main butterfly valve will be closed during stand-still of the pumps. Maintenance butterfly valve kept open during standstill of the main pumps.

78. The butterfly valves to be installed shall be of lense type.

79. The main valve will be operated by falling weights in closing direction, respectively, by one (1) oil hydraulic servomotors in opening direction which also operate as brake during closing procedure. This will provide adequate fail safe operation. The maintenance valve will be operated by an electrical actuator.

80. The valves shall be connected by flanges to the discharge pipe of the pumps and to a dismantling joint. The valve shall be equipped with adequate mechanical or hydraulic interlocks to ensure the correct sequence for the opening and closing of the valve.

Lahmeyer International in association with InfoCapital Group page 22

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

81. Basic main technical data of the main pump discharge valves:

Valve type butterfly valve with hydraulic drive and counter weights No. of valves to be provided 9 (incl. one complete spare valve) Valve diameter 2100 mm Design pressure PN10 No. of servomotor per valve 1 Type of valve disc lense type

82. Basic main technical data of the maintenance butterfly valves:

Valve type butterfly valve with electrical actuator No. of valves to be provided 9 (incl. one complete spare valve) Size bypass pipe and valve 100 mm Valve diameter 2300 mm Design pressure PN10 Type of valve disc lense type

83. The casing of the valves shall be made of cast steel properly heat-treated or of welded steel plates properly stress relieved or of a combination of both. The bearings of the valve shaft shall be self-lubricated.

84. The butterfly valves shall be of stout construction and shall have all corresponding parts interchangeable. The butterfly valve shall be so designed and constructed as to allow a smooth flow of water and to avoid any cavitation and vibration under the different operating conditions and thus the working stresses will not exceed the allowable values.

85. The closing and opening time of the main butterfly valve will be adjustable. Valve seal shall be made of rubber (or other suitable non-metallic material) to improve the tightness.

86. The operating mechanism for the main valve shall consist of one oil-hydraulic actuated servomotor with falling weights on each side of the shaft. Closing shall be done by falling weights and opening by the oil-hydraulic servomotors which also operate as brakes during closing.

87. The servomotor of the main butterfly valve for opening and closing will be operated by high pressure hydraulic oil system, with a pressure rating of PN120. With a high pressure oil system the outline dimensions of the hydraulic pressure oil system and the accumulators will be small in size.

88. One (1) hydraulic pressure oil unit should be provided including pressure oil pump; one stand-by and one in operation.

89. The main butterfly valves will be installed by the valve crane with a capacity of 15 ton. The valve crane will be of bridge type with electrical operated hoist mechanism. The crane will operate on rails above the main butterfly valves.

Lahmeyer International in association with InfoCapital Group page 23

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

90. The maintenance butterfly valves will be installed with a gantry crane of 15 ton capacity operating on rails across the discharge pipes on El. 198.80 m asl.

Dismantling and Expansion Joint

91. For valve dismantling and expansion of the piping a dismantling and expansion joint will be installed on the downstream side of the butterfly valve. All sealing gaskets shall be made of rubber and shall be seated stainless steel.

92. The joint will facilitate installation and removal of the butterfly valve. Furthermore, the joint will accommodate small alignment errors and changes in length resulting from temperature changes and different loads for open or closed valve position. The joint will be absolutely drip-tight. The joint must be designed and constructed so that the working stresses due to a water pressure of the maximum shut-off head of the pump. Dismantling will be done by the aid of the valve crane of 15 ton capacity respectively by the gantry crane for the joint of the maintenance valve.

93. The arrangement of the main- and maintenance butterfly valve, joints and lifting equipment is shown in the relevant drawings.

5. Technical Water Supply System

94. The technical water will be provided for cooling purposes of the following components:

(i) Electrical motor air/water coolers (ii) Oil coolers of motor bearings (iii) Oil coolers of main pump bearing (iv) Water lubrication for main pump shaft seal

95. Considering the expected nature of silt and debris in the raw water, the technical water supply system will be taken from a sedimentation basin. The sedimentation basin will pre-clean the raw water and allow the settling of the sediments. Raw water will be supplied to the sedimentation basin by gravity pipe from the discharge canal system.

96. The scope will include the following supply and services:

(i) One (1) main supply header DN300 approximately 660 length from the sedimentation basin to the pump house including, motor-operated valve, three (3) automatic back flushing strainers (3 x 50%) and associated auxiliaries. (ii) Eight (8) cooling water supply branches and distribution pipes to the consumers, including for each main unit optional two (2) booster pumps for shaft seal water supply (2 x 100%) and two (2) fine filters (2 x 100%). (iii) Piping, valves, instrumentation, flow meter and control devices for the raw water flow and water flow through the consumers.

Lahmeyer International in association with InfoCapital Group page 24

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

97. From the sedimentation basin the technical water will supply the consumers of the main pump sets and motors by gravity through a pipe DN300. The length of the gravity pipe is approx. 660 m from the sedimentation basin outlet to the pump house. The water level of the sedimentation basin will be monitored by water level sensors and switches for high and low level alarm.

98. The DN300 main supply pipe will be equipped with eight (8) branches size DN100 to supply the consumers of the main pump sets and motors by gravity. After the cooling water passed the heat exchangers the water will be discharged through main outlet pipe to the intake at approx. El. 188.80 m asl. The main outlet pipe will be provided with a motorized valve opening when technical water is required. The valve operation will be in- cooperated into the start/stop automatic control sequence of the main pump sets.

99. Additional fine filtration will be provided by three (3) motorised and fully automatic back flushing strainers, each for 50% of the full technical water requirement of eight (8) pump units. The filters will be installed on El. 179.70 m asl. Filter mesh size will be 0.5 mm. Switchover isolating valves will be furnished to provide continuous operation during repair or cleaning of one (1) of the filters at the inlet and outlet. Differential pressure gauges and differential pressure transducers will be provided for each strainer. Material of the filters will be stainless steel.

100. The technical water system will be equipped with all necessary isolating valves and instrumentation for supervision and automatic control. Magnetic flow meters will be provided at the outlet pipe of each consumer. The flow meters will be provided with local displays and 3% accuracy.

101. Two (2) booster pumps will be provided for each shaft seal to increase the seal water pressure, if required, to a sufficient level above the maximum water pressure prevailing inside the seal. The pumps will be horizontal, single-stage centrifugal pumps, having an overhung impeller and be separately coupled to the motor. Each pump will be designed for 100% of shaft seal water supply. The discharge side will be equipped with check valve and butterfly valve, the suction side with a butterfly valve.

102. Shaft seals require a high purified water supply. Therefore additional fine filter with a mesh size of approx. 0.05 mm will be installed into each pump discharge pipe.

103. The preliminary estimated cooling water requirements for the layout of the technical water supply system for one unit is shown in Table 10.

Table 10: Cooling Water Requirements Technical Water Consumer Requirement Air/water cooler main electrical motor 590 l/min Oil/water cooler motor bearing 90 l/min Oil/water cooler pump bearing 45 l/min Pump shaft seal lubrication water 50 l/min Total 775 l/min

Source: Present Study, 2013

Lahmeyer International in association with InfoCapital Group page 25

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

104. The technical water requirement is preliminary estimated with 775 l/min for one (1) main unit respectively 6200 l/min for the 8 (eight) main pump unit sets.

105. Final cooling water requirements depend on the actual equipment supplied and will be verified later during the suppliers design stage.

106. The technical water system will be designed for remote, automatic control, but it will also be possible, to employ local, manual control of individual components from the local control boards on the floor 179.70 m asl. near the cooling water equipment.

107. The schematic arrangement of the equipment is shown in the conceptual schematic diagram of the cooling water system.

6. Pumphouse Overhead Crane

108. The pumphouse overhead crane is designed for lifting the heaviest part of the pump set, the rotor of the electrical motor with a weight of approximately 40 ton. The pumphouse crane will have a main hoist with a lifting capacity of 50 ton and an auxiliary hoist of 15 ton.

109. The electrically operated overhead travelling crane in the pump hall will be primarily used for handling parts at the unloading bay and erection of main pump, electrical motors, and discharge butterfly valves as well as other heavy equipment parts.

110. The pumphouse overhead crane will be required to handle pumping plant equipment and machinery up to 50 ton.

111. The main cranes and the auxiliary crane will be operated by radio control system (remote joy-stick desk).

112. The main and auxiliary hoist of the pumphouse crane will be mounted on a common trolley.

113. The general layout and arrangement of the machine hall electrically operated overhead travelling cranes are shown in the relevant drawings.

114. The pumphouse overhead travelling crane will be designed in every respect to meet safely all the requirements of the pump plant and relevant standards. The pumphouse crane will be used indoors.

115. Basic main technical data of the pumphouse overhead crane:

Type of crane electrically operated overhead bridge crane Number of cranes one (1) FEM group A1 Span, centre to centre runway rails approx. 12.20 m Crane runway length (approx.) 72.00 m Elevation of crane rail beam 197.90 m asl.

Lahmeyer International in association with InfoCapital Group page 26

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Main hoist: Rated capacity*) 50 ton Highest hook position 195.80 m asl. Lowest hook position 181.10 m asl. Max. Lift height 14.70 m Operating speed (variable) normal / inching 0.0 – 2.0 m/min

Aux. hoist: Rated capacity 15 ton Highest hook position 198.30 m asl. Lowest hook position 173.10 m asl. Max. lift height 25.20 m Operating speed (variable) normal / inching 0.0 – 10.0 m/min

Trolley drive; operating speed 0.0 – 15.0 m/min Crane drive; operating speed 0.0 – 20.0 m/min Intermittent rating for all motors 40% Load of dynamic test 125%

Note: *) The required rated lifting capacity will depend on the final mass of the motor rotor.

116. The supplier will guarantee the specified hoisting capacities and girder deflection less than 1/850 of the relevant span for the cranes.

7. Oil Supply and Disposal System

117. The oil supply and disposal system will be arranged as a stationary system in the oil treatment plant at the volute case floor of the pump house. The system will treat the lubricating oil, bearing and control oil but not the transformer oil.

118. The oil supply and disposal system will consist of the following items:

(i) one (1) fresh oil storage tank (ii) one (1) disposal oil storage tank (iii) one (1) disposal oil storage container (iv) one (1) disposal oil transfer pump (v) one (1) mobile compact oil purification system (vi) piping, control and safety devices (vii) power and control board

119. The schematic arrangement of the equipment is shown in the conceptual schematic diagram of the oil supply and disposal system.

120. The system shall be designed for the following operating modes:

(i) Filling of the fresh oil tank by mobile oil-truck and empty of disposal oil tank to mobile oil-truck (ii) Transferring oil from the clean oil tank to the units by gravity (iii) Drainage of oil from the units to the disposal oil storage container

Lahmeyer International in association with InfoCapital Group page 27

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

(iv) Transferring oil from the storage oil container to the disposal oil storage tank using the disposal oil transfer pump (v) Purification of oil through the mobile compact oil purification system

121. The preliminary estimate for the motor and pump bearings oil volumes are as follows:

Upper motor guide/thrust bearing 1.1 m³ Lower motor guide bearing 0.3 m³ Pump guide bearing 0.2 m³

122. The total oil volume for one main pump unit is preliminarily estimated to be approx. 1.6 m3.

123. Fresh and disposal oil storage tanks will be installed outside of the pump house at El. 188.80 m asl. The disposal oil storage container together with the disposal oil transfer pump will be installed at lower elevation El. 177.25 m asl.

124. Storage capacity for each of the oil storage tanks will be 120% of the entire oil volume of four (4) main pump units. Storage capacity for the oil storage container will be 120% of the entire oil volume of one (1) main pump unit.

Mobile compact oil purification system:

(i) Minimum size of removed particles: 10 microns (ii) Water contents of treated oil: 10 ppm from a 50 ppm initial content (iii) System capacity shall be at least: 0.3 m³/h

8. Drainage & Dewatering System

125. The pump station is equipped with a drainage and dewatering system on the left side (looking towards the intake) of the pump station substructure. The drainage system is designed to collect and remove seepage water of the pump house as well as leakages from the equipment, e.g. main pump shaft seal. The dewatering system is designed to dewater the water passage of the main pump units for maintenance. The water from the dewatering and drainage system will be pumped to the intake of the pump station.

126. Both systems will include the following:

(i) Drainage system with pumps, piping, valves and control equipment. (ii) Dewatering system with pumps, piping, valves and control equipment. (iii) Eight (8) dewatering foot valves for each pump suction tube (iv) Lifting equipment

Drainage System

127. Seepage water of the pump house and leakages of the equipment are collected through the floor drains and trenches in the open drainage sump.

Lahmeyer International in association with InfoCapital Group page 28

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

128. Main parameters of drainage pumps:

No. of drainage pumps three (3), incl. one stand-by unit Type of pumps submersible motor type Pump capacity each approx. 35 l/s Pump head approx. 18 m Motor power approx. 12 kW Max. pump speed 1500 1/min.

129. The drainage water flow to the drainage sump was estimated with approx. 50 l/s incl. 8 l/s of shaft seal water leakage from the eight (8) main pumps and around 42 l/s of seepage water of the pump house and others.

130. The drainage system will be equipped with three (3) submersible centrifugal pumps including one (1) stand-by pump of sufficient capacity. The capacity of two (2) drainage pumps is sufficient to discharge the max. inflow to the sump.

131. The pumps will be capable of operating without cavitation or vibration for the entire range of delivery heads encountered for any of the duties for which these pumps are designed. The core lamination of stator and rotor of the water-filled motors will be vacuum-impregnated by means of a suitable synthetic resin. All equipment and circuits will comply with DIN or equivalent standards.

132. The shaft seal between pump and motor will be of erosion- and corrosion- resistant material. The impellers will be capable of handling water containing solids up to 30 mm diameter. The journal bearings will be of corrosion-resistant material and the shafts of stainless steel. The casing parts will be of cast steel or of a ductile cast metal.

133. The drainage system will be designed for automatic operation with the possibility of local manual control of individual pumps from the local control board near to the drainage sump.

134. Control of the drainage pumps will be set according to exact levels determined during the detailed design stage.

135. Stepped-level automatic control will be as follows:

Very Low Level = Alarm (Stop of all pumps) High Level 1 = Start-up Pump No. 1 High Level 2 = Start-up Pump No. 2 High Level 3 = Start-up Pump No. 3 Low Level 1 = Shut-down of Pump No. 1 Low Level 2 = Shut-down of Pump No. 2 Low Level 3 = Shut-down of Pump No. 3 Very High Level = Alarm (Signal to CCR)

Lahmeyer International in association with InfoCapital Group page 29

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

136. Level switch equipment will be provided for the drainage sump for the automatic control and monitoring of the drainage pumps. Two level switches will be appointed to one pump, for automatic sequential start-up and shut-down according to the water levels. Master low level float switches will protect the drainage pumps against dry run at manual operation and automatic operation. A high level master switch will start up all pumps independently on the control float switches and will initiate high level alarm in case that the maximum water level in the pump sump will be reached.

137. A local control board will accommodate the control equipment, including the PLC.

138. The discharge pipes of the drainage pumps are equipped with check valves and butterfly valve dia. 150 mm. The three pump discharge pipes are connected to one main collector pipe of dia. 200 mm.

139. To insure the operation of the drainage system during power cut the drainage pumps will be connected to the essential power supply system provided by the emergency diesel units.

Dewatering System

140. Each pump intake chamber, pump suction tube, pump volute casing and discharge pipe up to the discharge butterfly valves may be dewatered through a dewatering pipe to the closed dewatering gallery. Dewatering of the suction tube will be done at its lowest point into the dewatering gallery.

141. The water from the pump suction tube will be dewatered through a foot valve dia. 200 mm over a dewatering pipe dia. 200 mm to the closed dewatering gallery. The foot valves will be operated from El. 181.10 m asl. by electrical actuator with stem extension.

142. Dewatering of the closed drainage gallery will be done by two (2) horizontal base mounted centrifugal pumps, which are both in operation.

143. The pump capacity will be sufficient to dewater the water passages of one (1) main pump unit within two (2) hours. The pumps will discharge any leakage water from the intake stoplogs and discharge butterfly valves to keep the water passage of the main pump in dry condition for maintenance.

144. Main parameters of dewatering pumps:

No. of dewatering pumps two (2) Type of pumps horizontal centrifugal Pump capacity each approx. 80 l/s Pump head approx. 18 m Motor power approx. 28 kW Max. Pump speed 1500 1/min.

145. Level switch equipment will be provided for the closed dewatering gallery for the automatic control and monitoring of the dewatering pumps. Manual start-up of the pumps by push button station for commissioning and pump testing will be foreseen.

Lahmeyer International in association with InfoCapital Group page 30

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

146. The suction pipes of the dewatering pumps are equipped with check valves dia. 250 mm and isolating valves of butterfly valve type of dia. 250 mm. In each pump discharge pipe a second butterfly valve is provided to isolate the pump from the system in case of maintenance of dia. 200 mm. The two discharge pipes are combined into one main header pipe of dia. 300 mm. The water from the dewatering system is discharged to the intake of the pump station.

147. The conceptual outline of the dewatering system components as well as the respective control is very similar to the components of the drainage system.

148. For maintenance and dismantling works an electrical monorail hoist with a capacity of 3 ton will be arranged in the drainage and dewatering pump room. The main pump house crane will be used for lifting equipment to El. 188.80 m asl.

149. The general layout, arrangement and the schematic of the drainage and dewatering system is shown in the relevant drawings.

Sludge Pump Set

150. One (1) sludge pump unit will be provided at the pump station to empty the drainage sump and dewatering gallery to permit maintenance or inspection of the areas. The sludge pump will be of the portable submersible type and highly resistant against sediment and

151. The power cables shall have watertight connections to the electric motor.

152. Main parameters of the sludge pump:

No. of sludge pumps one (1) Type of pumps submersible Pump capacity approx. 10 l/s Pump head approx. 18 m Motor power approx. 5 kW Pump speed 2800 1/min

153. The electric motor will be arranged above the pump, and close-coupled. The pumping unit shall be provided with flexible hose including sufficient lengths of discharge hose, but in any case not less than 60 m, to facilitate the easy discharge of the evacuated water to the pump station intake.

9. Emergency Dewatering System

154. For the case of a flooding incident of the pump house an emergency dewatering system is provided on the left side (looking towards the intake) of the pump station substructure. The emergency dewatering system includes three (3) submersible vertical installed pump sets, valves, piping and control equipment.

155. Emergency level switches will be provided for the case of local flooding in the pump house, for emergency shut-down of the main pump units and start-up of the emergency pumps.

Lahmeyer International in association with InfoCapital Group page 31

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

156. The three (3) submersible pumps are installed at El. 177.25 m asl. The emergency system will be designed for automatic operation with the possibility of local manual control of individual pumps from the local control board on El. 188.80 m asl. Each pump set will be provided with an electric cable (special cable for submersible motors) in one piece in order to connect it to the link box located on El. 188.80 m asl.

157. Main parameters of emergency pumps:

No. of emergency pumps three (3) Type of pumps submersible motor type Pump capacity each approx. 100 l/s Pump head approx. 18 m Motor power approx. 35 kW Max. pump speed 1500 1/min.

158. To insure the operation of the emergency dewatering system during power-cut the drainage pumps will be connected to the essential power supply system provided by the emergency diesel units.

159. The discharge pipes of the emergency pumps are equipped with check valves and butterfly valve dia. 200 mm. The three pump discharge pipes are connected to one main collector pipe of dia. 350 mm.

160. The general layout, arrangement and the schematic of the drainage and dewatering system is shown in the relevant drawings.

10. Compressed Air System

161. A low pressure compressed air system will be installed to provide service air to required points in the pumphouse. The air compressor and associated equipment will be located on floor 179.70 m asl.

162. The equipment will mainly consist of the following:

(i) One (1) piston, motor-driven compressors (ii) Two (2) air receivers sized 0.5 m³ each. The receiver will be provided with pressure switches to switch the compressors on and off. The receivers will be provided with pressure gauge, safety valve, check valve, all necessary isolating valves, drainage valve, and a manhole. (iii) The piping for distribution of low pressure compressed air will be routed to the various tapping points for the supply of service air. The line will be routed to El. 188.80 m asl., 184.60 m asl., 179.70 and El. 177.25 m asl.

163. The compressor alone will be able to fill the air receiver from atmospheric pressure up to rated pressure of 8 bars within one (1) hour.

164. The general layout, arrangement and the schematic of the drainage and dewatering system is shown in the relevant drawings.

Lahmeyer International in association with InfoCapital Group page 32

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

11. Fire Fighting Equipment and Alarm System

165. Pumping stations are considered Special Purpose Industrial Occupancy as defined in National Fire Protection Association (NFPA). Fire protection, equipment and alarm system should be provided.

166. A centralised, electronic-digital, programmable fire detection and fire alarm system will be provided for the pumphouse, cable galleries, 6 kV switchgear and supporting facilities.

167. Manual and individual addressable fire alarm stations (push buttons) will be provided in the pumphouse, staircases, corridors and lobbies following the exit paths and at all emergency exits.

168. Automatic fire detectors will be installed sensitive either to heat or smoke. Heat detectors will be combined fixed temperature / rate-of-rise type detectors with a fixed temperature setting. Smoke detectors will be of optical type.

169. Actuation of any automatic or manual fire detection device will be displayed on a main fire alarm control panel, which shall be located in the pumphouse central control room.

170. Status information of the fire alarm system will also be transmitted to the station computer system. Sirens, horns or bells will be provided as audible alarms inside all buildings. Red flash lights will be provided as visible alarms inside the buildings for the machine hall and for all other areas with a very high noise level.

171. The fire service main will be in accordance with the requirements of NFPA 24, designed in form of supply rings throughout and around the pumphouse and the auxiliary facilities. Isolating valves shall be provided for the various parts of the ring system in such a number that sections of no more than five (5) hydrants may be isolated for maintenance or repair works whereas all other parts of the main system will remain in full service. The fire service main will be made of carbon steel pipes, outside heavily protected against corrosion.

172. The supply rings and hydrants will be supplied by gravity water from a fire fighting supply tank.

173. Outdoor hydrants will be provided in all areas of buildings and equipment relevant to be protected and the distances between hydrants shall not exceed 75 m. The outdoor hydrants shall be of the wet barrel type with two (2) upper outlets DN 65 (21/2").

174. Standpipes will be provided inside these buildings to supply the fire-fighting water from the fire service main to the indoor hose stations, also called fire cocks.

175. Indoor hose stations will be provided on all floors in such number and locations, that each room or area on the floor can be reached by a hose stream.

176. For initial fire-fighting, portable fire extinguishers with capacities of 6 kg chemical dry powder, for rooms containing electrical equipment with capacities of 5 kg CO2, will be provided and placed in the rooms and buildings at strategic locations and next to exits.

Lahmeyer International in association with InfoCapital Group page 33

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

12. Heating, Ventilation & Air Conditioning

177. A sufficient ventilation and air conditioning of the pumping station building is an important design consideration to prevent concentration of heat, humidity or gases which may result in damage to the structure, equipment or personnel.

178. The heating, ventilation and air conditioning system will be provided for the pumphouse and auxiliary buildings.

179. Due to the machinery in the pumphouse, consisting of eight (8) pump units, switchgear and related auxiliary equipment, heat dissipation will increase the room temperature in several floors to an unacceptable level so that a forced ventilation system will be installed. Forced ventilation will be provided by axial roof blowers on the pump station building and radial exhaust type blowers located at the pump station lower floors.

180. For rooms with increased extent electronic components and the temperature requirements of rooms like communications centre, control room, electrical rooms, etc., standard domestic air conditioners will be provided. These air conditioners will be window type air conditioners with a rating of 2.2 kW. The air conditioners will be capable of operating in either cooling or heating mode.

13. Mechanical Workshop Equipment

181. The mechanical workshop is part of the auxiliary buildings located outside of the pump house. Assuming that major maintenance and repair works will be managed in the central workshop in Bukhara with required machinery, the pumping station will only be provided with regular workshop equipment and tools for normal operation, maintenance and repair on the electro-mechanical equipment of the pump station. In particular the following equipment will be included:

(i) one (1) universal lathe (ii) one (1) pillar-mounted drilling machine (iii) one (1) table drilling machine (iv) one (1) double-wheel rough grinding machine (v) one (1) metal hacksaw machine with adjustable supports: (vi) two (2) work benches with vice (vii) one (1) machine tool cabinet (viii) two (2) tool cabinets (ix) one (1) set of tools for the mechanical workshop incl. set of mechanical measuring equipment and instruments (x) one (1) tool trolley (xi) one (1) fork lift trolley of 1000 kg capacity (xii) one (1) chain b lock of 1000 kg capacity (xiii) one (1) set of welding equipment (xiv) equipment for external use (mobile air compressor, hand-drilling machine, etc.)

182. The quality and accuracy of the equipment will be verified and confirmed in accordance with relevant quality assurance guide lines.

Lahmeyer International in association with InfoCapital Group page 34

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

14. Water Supply System

183. The secure supply of drinking water (according to WHO quality requirements) will be provided. The supply of potable water is required for toilettes, showers and kitchens. The capacity of the potable water plant shall consider a number of 20 people for the potable water consumption. A factory canteen respectively a cafeteria is not foreseen.

184. The domestic waste water system shall be connected to a domestic sewage water treatment plant that shall be located at least 200m downstream of the pumphouse respectively 200 m downstream of any occupied building. The outcome of the waste water treatment shall be according to the WHO regulations as well. The sludge treatment shall be suitable for a correct treatment according to the WHO standard for agricultural purposes.

185. The pipework for the connection of the required equipment will be part of the supply. This includes the potable water distribution as well as the waste water drainage connection of all devices to the waste water treatment plant and after this to the discharge to the pump station intake.

C. Hydro-mechanical Equipment

186. The hydro-mechanical equipment and associated equipment to be designed for the Khamza New Pump Station consists of the following:

(i) Intake trash racks and embedded parts (ii) Intake stoplogs and embedded parts (iii) Trash rack cleaning machine (iv) Intake gantry crane (v) Discharge pipe system

1. Intake Trash Racks and Embedded Parts

187. The trashrack will be inserted at the entrance to the pump intakes and is intended to protect against entrance of debris or other large-size trash entering the main pumps.

188. Eight (8) trashracks will be installed at the pump intakes. Each of the pump intake openings is divided by a vertical separation concrete wall. With this configuration, two trashracks will be installed in each pump intake opening.

189. Each trashrack set will be built up from two (2) movable sections. The design height of each section will be 4.20 m (approximately). The trashracks will be designed to prevent vibration induced by the flow through the trashracks. The head losses of the intake trashracks will be minimized and guaranteed.

190. The clear width of one opening will be 4.5 m. The clear rack bar spacing will be 90 mm. The working stress at a hydrostatic differential pressure head of 0.6 m at the most unfavourable position on the trash rack shall not exceed 100 N/mm².

191. The minimum thickness of the bars will be 12 mm. The elevation of sill will be at 180.46 m asl. The elevation of the operation platform will be 188.80 m asl.

Lahmeyer International in association with InfoCapital Group page 35

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

192. For inspection and repair the trashrack sections will be lifted / lowered by special lifting beam using the intake gantry crane. Then the trashracks will be dismantled into sections and moved to another place for cleaning, inspection and repair. For handling and coupling of the sections at the operation platform level, provision will be made for installation of dogging devices in each of the slots.

193. Cleaning of the trashracks will be effected by a special trashrack cleaning machine arranged at the operation platform. Special guiding devices for the trashrack buckets will be installed between the upper elevation of the trashracks and the operation platform level.

194. For all the slots embedded parts, from sill level up to operation platform level, for guiding and safe positioning of the trashracks will be installed in second stage concrete. The main dimensions and the arrangement of the intake trashrack are shown in the relevant drawings. Each trashrack will be provided with head-differential measurement equipment.

195. The trashrack will be designed in every respect to safely meet all the requirements as originating from the full pump operating range.

196. Each trash rack panel will consist of the following elements:

(i) Vertically inclined trash rack bars, (ii) Equally spaced cross connection 'needles' to secure the trash rack bars in position, (iii) Transverse bars to fix the panels on to the supporting beams, (iv) All necessary bars/bolts for prevention of vibration/oscillation

197. Basic main technical data of the trashracks:

Number of trashrack openings 8 Number of trashrack sections for one opening 2 Elevation of sill 180.46 m asl. Elevation of operation platform 188.80 m asl. Inclination of trashrack slots against horizontal axis 75° Sets embedded parts 8 Rated discharge to the intake 11.43 m³/s Clear width of trashrack opening 4.50 m Design height of trashrack section 4.20 m Clear bar rack spacing 90 mm Minimum bar thickness 12 mm Average water velocity at entrance to trashrack 0.6 m/s Minimum intake water level 184.88 m asl. Maximum intake water level 187.85 m asl. Handling and moving of the trashracks by pump intake gantry crane Cleaning of trashracks by trashrack cleaning machine

Lahmeyer International in association with InfoCapital Group page 36

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

2. Intake Stoplogs and Embedded Parts

198. For closure of the intake of the pump chambers and intake water passage in case of maintenance on the main pump unit provision will be made for installation of stoplogs. The stoplogs will be installed in vertical slots positioned in the intake piers. The stoplogs will be operated by the intake gantry crane. An automatic lifting beam will be used for operation.

199. The stoplogs shall be lifted and lowered with the grabbling beam by the intake gantry crane under generally balanced upstream and downstream water pressure conditions. Balancing of the water pressure upstream and downstream will be carried out by a filling valve integrated into the stoplog panel. The valve will be operated by the grabbling beam.

200. The sill elevation of the stoplogs will be 180.46 m asl.

201. The stoplogs close the intake opening 4.5 m in span and approx. 3.1 m in height. Each stoplog set will consist of one (1) stoplog section. Three (3) stoplogs will be supplied to close two (3) intake openings at one time.

202. The stoplogs will be of the vertical sliding type with skin plate and rubber seal arranged at the downstream side. The seals of the stoplogs are arranged on the downstream side with respect to the gate and consist of lateral seals and sill seals. Lateral seals of a console type are fastened to vertical ribs of the skin - as a shaped seal element a neoprene P-shaped one is used. The lower horizontal seal is made of neoprene strip rubber. The seals are adjustable.

203. To provide accurate sealing the seals are pre-stressed to the embedded sealing surface by means of a spring load mechanism. Guide grooves in concrete piers shall be formed from stainless steel sheet. Eight (8) sets embedded parts will provide for the openings and guide grooves.

204. The stoplog panels will be of welded construction with a downstream skin plate and horizontal cross-beams and vertical bracing members. The stoplog panels shall be fabricated from mild steel in accordance with the approved standard DIN EN 10025 to S235JR or S355JR.

205. In total eight (eight) openings will be provided for installation of stoplogs. The stoplogs sections will be kept hanging in a stoplog storage device as shown on the relevant drawings. Main dimensions and the arrangement of the intake stoplogs are shown in relevant drawings.

206. Basic main technical data of the stoplog sets:

Type of stoplog vertical lift, sliding Number of stoplog opening 8 Number of stoplog sets to be supplied 3 Number of stoplog sections per set 1 Clear height of intake opening 3.1 m Clear width of intake opening 4.5 m

Lahmeyer International in association with InfoCapital Group page 37

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Height of stoplog panel 3.3 m Width of stoplog panel 4.9 m Height of stoplog slots approx. 8.3 m Design head of stoplog 9 m Design pressure 9 m W.C. Elevation of sill 180.46 m asl. Elevation of operation platform 188.80 m asl. Maximum intake water level 187.85 m asl. Weight of one (1) stoplog section approx. 5 to 6 ton Operation of stoplogs by intake gantry crane, grabbling beam Lifting and closing under balanced water condition

207. The intake stoplogs will be designed in every respect to meet safely all the requirements of the pumping plant.

208. Leakage of the stoplog set gate will not exceed 0.1 l/s per meter of active sealing length, but not more than 1.5 l/s for the complete stoplog. This value will be guaranteed in new and clean conditions, at max. intake water level of 187.85 m asl.

3. Trash Rack Cleaning Machine

209. Two types of trashrack cleaning machines are usually in use for pumping plants with a trashrack cleaning lengths up to 5 to 15 m. The classic wire rope trashrack cleaning machine and more recently, the hydraulic jib trashrack cleaner.

210. For the Khamza New Pump Station a classic wire rope cleaning machine with moving trash container is proposed due to advantages of easy maintenance, simple design (winch, control system) and high availability against more complicated hydraulic driven trashrack machines.

211. Therefore it is recommended to provide one (1) intake trashrack cleaning machine with a trashrack of 2.5 meter width for cleaning the pump intake and removal of floating material.

212. The trashrack cleaning machine is travelling on rails along the intake structure at elevation 188.80 m asl.

213. Trash from the trashrack will be containerised in one (1) container having capacity of 4 to 5 m³. The container is travelling with the trash rack cleaning machine. Filled containers shall be transported by the Pump Intake Gantry Crane for unloading in to a mobile truck.

214. The rake hoisting mechanism is equipped with twin rope drums and two hooks for pulley blocks with incorporated non-turning lifting hooks for coupling lifting operation of trashrack.

Lahmeyer International in association with InfoCapital Group page 38

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

215. The main dimensions and the arrangement of the special pump intake trashrack cleaning machine are shown in the relevant drawings. The pump intake trashrack cleaning machine will be designed for outdoor operation. The trashrack cleaning machine will be designed in every respect to safely meet all the requirements.

216. Each trashrack cleaning machine will be used for:

(i) Cleaning of trashrack (ii) Removal of floating debris and loading them in the container

217. The trashrack cleaning machine shall be driven by a double-rope hoist. The linkage operation of the ropes will be actuated by two separate drums on the trash rake trolley. The trash will be collected in a container travelling with the trash rack machine.

218. Basic main technical data of the trashrack cleaning machine:

Type of cleaning machine wire rope type electrically operated Number of cleaning equipment 1 Max. Lifting height approx. 10 m Width of rake bucket 2.5 m Length of runway approx. 55 m Span between rails approx. 2 m Clear width of trashrack opening 4.5 m Elevation of top of rails 188.90 m asl. Trash container capacity approx. 4 to 5 m³ Lifting and lowering speed of rake bucket 7 m/min

219. The Supplier will guarantee the equipment safety, the required operation of the main hook for trashrack cleaning and operating speed.

4. Intake Gantry Crane

220. A 8 (eight) ton lifting capacity intake gantry crane, 8.0 m in span, is intended for erection and maintenance of the intake trashracks and maintenance stoplogs.

221. For handling of the intake trashracks (installation and removal) and fixed wheel emergency / repair gate of the inlet portal of the sediment flushing channels the crane will be equipped with cantilever beams on the upstream side.

222. The lifting capacity of the gantry crane hoist of 8 ton is determined by consideration of the heaviest part; one (1) stoplog.

223. The intake gantry crane will be mounted on the working platform at elevation 188.80 m asl. The intake gantry crane hoist will be designed for outdoor operation. The hoist will be mounted on the trolley. The crane will be equipped with an operator cabin.

224. The hoist will be equipped with twin rope drums and one hook for pulley blocks with incorporated non-turning lifting hook. The necessary lifting beams for operation of different equipment will be designed and supplied by the crane manufacturer.

Lahmeyer International in association with InfoCapital Group page 39

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

225. The main dimensions and the arrangement of the pump intake main gantry crane are shown in the relevant drawings.

226. Basic main technical data of the intake gantry crane:

Type of crane electrical operated gantry crane FEM group A 1 Crane span (preliminary estimation) 8 m Crane runway length (approx.) 60 m Elevation of crane rail beam 189.00 m asl.

Hoist: Rated capacity*) 80 kN Highest hook position 194.45 m asl. Lowest hook position 180.50 m asl. Max. Lift height 13.95 m Operating speed (variable) normal / inching 0.0 – 2.0 m/min Trolley drive; operating speed 0.0 – 8.0 m/min Crane drive; operating speed 0.0 – 20.0 m/min Intermittent rating for all motors 40% Load of dynamic test 125% Note: *) The required rated lifting capacity will depend on the lifting requirement for one (1) stoplog.

227. The supplier will guarantee the specified hoisting capacities and girder deflection less than 1 / 850 of the relevant span.

228. The intake gantry crane will be designed in every respect to safely meet all the requirements of the pumping plant and relevant standards.

5. Discharge Pipe System

229. The discharge pipe system will deliver the water from the main pump units to the discharge basin. Each main pump unit will be connected via individual discharge pipe sections with a dia. 2100/2300 mm, pipe bends, bifurcations, collector pipe and diffuser sections to the main discharge header with an inner dia. 4100 mm and length of approx. 620 m. Two (2) main discharge headers will be constructed to provide redundancy for uninterrupted water supply in case of maintenance or repair works on one of the headers.

230. Each main discharge header is connected to a siphon structure at the discharge basin as non-return installation. The siphon system will provide protection of the main pumps and preventing dewatering of the discharge canal system in an emergency case, e.g. pipe rapture. Air venting during the start phase of the main pumps to build up the vacuum and air breaking of the vacuum to avoid reverse flow when the pumps are stopped will be achieved by an aeration valve arranged on the top of each siphon. Preliminary calculations show that the siphon system will build the necessary vacuum to compensate the head loss only if 3 or 4 pumps are in operation. To insure the head recovery of the siphon in case only 1 or 2 main pumps are operating the vacuum needs to be built up by an additional vacuum pump system connected to the top of the siphon.

Lahmeyer International in association with InfoCapital Group page 40

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

231. Water level detectors will be used for the measurement of the water level in the discharge basin. The level detectors will be of ultrasonic type. The signals of the detectors will be sent to electronic indicating instruments in the pump control room.

232. The most economic discharge main header diameter has been determined for which the sum of pipe and pumping costs is a minimum. Pipe costs were estimated with a unit cost of 7700 US$ per ton, which reflects the costs for completed or ongoing projects in Uzbekistan of similar type and sizes. Operation and maintenance costs estimated with 1% of the investment costs. The pump costs are mainly the energy costs related to the head loss of the various main header diameters calculated. Energy costs are calculated with 6 $ct/kWh. The flow discharge was calculated on average base with 70% of the maximum pump flow through one main header pipe; e.g. 32 m³/s. The expected lifetime for the discharge pipe system is 35 years. Figure 10 shows the optimum pipe diameter for Khamza New discharge main header. The maximum flow velocity is calculated to 3.53 m/s with four (4) pump units in operation at minimum geodetic pump head.

Figure 10: Optimum Diameter of Main Discharge Header

Source: Present Study, 2013 233. The piping system will be made from mild steel in accordance with standard DIN EN 10025 to S235JR or S355JR or equivalent. The pipes will be butt welded wherever possible. Wall thickness of the main discharge headers was preliminary calculated between 14 to 15 mm. Additional strengthening of the pipe will be provided by stiffener rings.

234. A protective coating will be provided on outside and inside surface of the discharge pipe system.

Lahmeyer International in association with InfoCapital Group page 41

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

235. The scope for the discharge pipe system will include all pump discharge pipes from the pump discharge flanges to the discharge basin, fittings, elbows, tapered enlargement pipes, flanges, pipe supports, drain pipes, vent pipes, expansion joints, dismantling pieces and all accessories required for necessary to complete the work.

236. Additional surge analysis need to be carried out during the implementation phase of the project to identify any surge protections is required in the discharge pipe system. The surge analysis will check that all equipment and pipes is capable of withstanding the most severe surge conditions, i.e. maximum and minimum pressures. The most severe condition is expected to occur when all pumps connected to one discharge pipeline suddenly stop as a result of a power break in main system.

237. The general arrangement of the pump discharge pipe system, elevations and layout is shown on the attached drawings.

Discharge Flow Measurement 238. For measurement of the pump discharge, flow meters will be installed at each individual pump discharge pipe dia. 2300 mm. The measurement will be ultrasonic type. A total of eight (8) flow meters are required. The accuracy of flow measurements should be within ±1.5% of the measured value. The measuring range will be at least 0-20 m³/s. The scope of supply will include all power supply, control cable, processing units, interfaces, fixing elements, etc.

D. Electrical Equipment

239. The electrical equipment to be designed for the Khamza New Pump Station consists of the following:

(i) Main electrical motors and soft starter LCI (ii) 6 kV High voltage installations (iii) Low voltage AC auxiliary supply system (iv) Protection system (v) 110 V DC supply system (vi) Computerized control system (vii) Communication and security system (viii) Earthing system and lighting protection (ix) Lighting and small power installations (x) Emergency diesel generator set (xi) 220/6 kV Substation and transmission lines

1. Pump Station Power Supply

240. The main power distribution substation for the Bukhara region is located at the Karakul District. The voltage supply is 500 kV. This is transformed down to the individual substations to distribution voltages of 110 kV and 220 kV, respectively.

241. The pumping stations in the ABIS utilize two medium voltage types as a source of supply that is derived from the main power network. These are the 10 kV and 6.6 kV voltage ratings.

Lahmeyer International in association with InfoCapital Group page 42

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

242. The substation “Khamza 1” feeds the existing Khamza 1 Pump Station from two (2) 60 MVA transformers (220/110/6kV) with 6 kV outgoing winding of 31.5 MVA from the 220 kV Bukhara network.

243. The substation “Khamza Auxiliary” feeds the existing Khamza Auxiliary Pump Station from one (1) 125 MVA transformer (220/110/6kV with 6 kV outgoing winding of 65 MVA from the 220 kV Bukhara network.

244. According to the MAWR’s design criteria, the new pump station shall be provided with the existing substation power supply from 6 kV voltage level for supply of the eight (8) 6 kV electrical main motors and the dedicated auxiliary equipment. The switchgear system with three (3) busbar sections will be supplied for bus section A from the substation “Khamza Auxiliary” and the bus section B and C from the both outgoings of the substation “Khamza 1”. Reference to SLD drawing no.: ABISR/KHN 030.

245. The scope of work of this Feasibility Study Supplemental Report include the 6 kV cable-termination on the bushings at the gantry from the 6 kV overhead lines. From this point up to the substation the scope of supply and deliveries are out of the battery limit.

246. Table 11 shows a calculation for the required power rate for bus section A, B, and C for Khamza New Pump Station main pump set.

Table 11: Power Calculation for the Khamza New Pump Station

Source: Present Study, 2013

Lahmeyer International in association with InfoCapital Group page 43

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

247. In conjunction with the requirement that only 80% of the rated transformer load can be dissipated for the power supply of the new pump station, the spare capacity of Substation “Khamza 1” transformer 1 and 2 with 25.20 MVA per transformer in variation 1 are sufficient. Likewise the spare capacity of Substation “Khamza Auxiliary” with 28.8 MVA is also sufficient. The calculation sheet demonstrates also clearly in variation 2 with only two (2) feeding stations, that the electrical power supply for the pump station only from Substation “Khamza 1” is not possible. Thus, the existing substations will require upgrades or new equipment that is outside the scope of this report.

2. Main Electrical Motors and Soft Starter (LCI)

248. The main pump units will be driven by AC synchronous electrical motors. The main motors will be capable of safely withstanding maximum stresses during normal operation, reverse runaway-speed conditions.

249. Basic main technical data of the main electrical motors:

No. of main motors to be supplied eight (8) Type of motor AC synchronous Frequency 50 Hz Nominal motor speed 300 1/min (constant speed) Type of cooling water-to-air cooling Shaft orientation vertical Orientation of rotation (viewed from top) anticlockwise Nominal capacity 7,575 kW Nominal voltage 6 kV Thrust bearing location below rotor Guide bearing location above and below rotor Cooling medium water (from technical water system)

250. The power rating of electrical motors will be 10% more than maximum power of pump in the operating range of pump.

251. The motors will be equipped with a lower thrust/guide bearing and upper guide bearing. The thrust bearing shall be capable of supporting the motor loads, the maximum hydraulic thrust loads and weights of the pump rotating parts. The design of thrust bearing housing shall provide easy access to the bearing pads. Bearings will be oil lubricated with necessary oil/water coolers. Cooling water will be provided through the technical water supply system.

252. The design of the electrical motor will consider the assembly and disassembly using the pumphouse crane. Necessary lifting equipment will be provided.

253. The electrical motors will be supplied with all necessary auxiliary equipment, sensors and instruments.

254. The main pumps will be start with a LCI-System to reduce the starting current on maximum of the nominal current in the starting phase.

Lahmeyer International in association with InfoCapital Group page 44

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

255. The LCI-System consists of frequency converter and converter transformer on the incoming side of the inverters.

256. The LCI-System shall be designed for the required main motors only for the starting phase. After nominal rotation of the motor/pump the motor shall be feed direct from the 6 kV switchgear-system with temporary overlapping of both feed systems. The circuit breaker for the LCI should be switch off after successful take-over of the 6 kV switchgear.

257. The LCI–System is to be constructed with dual Converter as redundancy system for prevention of a single fault in accordance with the SLD drawing no.: ABISR/KHN 030. The redundancy LCI allowed the parallel starting of max. 2 motors. All further motors shall be start step by step.

3. 6 kV High Voltage System

258. In order to distribute the power within the pump station and to supply the main electrical motors and auxiliary equipment an 6 kV High Voltage System will be required.

259. The system will be designed for a high degree of reliability and state-of-the-art technology.

260. The High Voltage Switchgear will include the panels as shown in the actual Single Line Drawing (SLD) no. ABISR/KHN 030.

261. In HV panel room sufficient space will be allocated for any future extension of the systems.

262. The HV system will include all services, panels, components and will be equipped with a DC battery system for the supply of DC power to all equipment required within the HV stations and the LV main distribution equipment.

263. All low voltage components must meet the requirements for LV equipment. All switch panels will be of a form 4B type and have separate wire ways and instrument chambers.

264. The switchgear will be in the form of metal-clad switchboard suitable for indoor use and will comply with IEC ISO 9001 60298/BS159, EN62271, BS-EN60265, BS- EN60694, BS-EN60298 and eats 41-36.

265. The switchboards will be suitable for bottom entry of the cables and installation and be off a form 4B type.

266. The switchgear will be designed to ensure the satisfactory operation under the site, and for the following system conditions. The internal temperature of all switchgear and switch panels will not exceed 30 degrees centigrade.

267. Basic main technical data of the switchgear: Nominal Voltage 6 kV +/- 10% Highest/ voltage for the equipment 7.2 kV

Lahmeyer International in association with InfoCapital Group page 45

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Basic insulation level at 1.2/ 50 µ sec 60 kV Peak Power frequency withstand at 50 Hz/min 20 kV Symmetrical short circuit current 25 k (3 sec) Dynamic current 63 k Frequency 50 Hz +/- 1%

268. Each current carrying component of the equipment supplied will be capable of continuous operation with the site rating without exceeding the maximum temperatures stated in the appropriate IEC recommendations.

269. 6 kV unarmoured multi-core XLPE cables will be installed between 6 kV switchgear and pump motors. Adequate mechanical protection shall be provided for non-armored cable types.

270. The cables will be designed to ensure the satisfactory operation under site and system conditions. The conductors will be copper with cross section suitable for the supply of the pump motors, and shall conform to IEC 60288.

271. The average thickness of the insulation, when determined by the method described in IEC 60811 and ISO 9001 will not be less than the value stated in IEC 60502-2.ISO 9001.

272. The thickness of any place may, however, be less than the specified nominal value provided that the difference does not exceed the limit specified in IEC 60502-2 ISO 9001. The thickness of semi-conducting screen on the conductor or over the insulation will not be included in the thickness of the insulation.

4. Protection, Metering and Control Equipment

273. Appropriate protection, control and metering equipment will be provided for the operation of Khamza New Pump Station.

274. All necessary additional protection and safety devices which will stop the pump motors in the event of abnormal operation conditions as detected by sensors and measuring devices incorporated in the pump motors and auxiliaries will be provided.

275. Each pump will have its own emergency stop facility within no more than two meters from the relevant pump or at a position.

276. Each of the 6 kV switchgear cubicles will be equipped with a multifunction protection relay it’s individually designed for necessary application of each cubicle and bay controller unit (BCU) which can communicate with the RTU. All electrical data such as current, voltage, power factor, active and reactive power, as well as the status, alarms and events related to the pump operation will be transmitted to the RTU.

277. BCU’s will be of modular construction and will be based on microprocessor technology and real time operating system. All input and output signal terminals for connection to the switchgear and other associated equipment will include isolating/shorting/test socket facilities as appropriate, for testing purposes and auxiliary relays and other devices.

Lahmeyer International in association with InfoCapital Group page 46

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

278. The power supply to BCU is to be derived from the station 110 V DC supply. BCU will have a dual power supply being fed from redundant DC power supply coming from the station battery. The power supply will have test terminals for all the voltages used in the system.

279. The design of the BCU’s will be such that the time for fault tracing and replacement of a faulty unit will be minimized.

280. A fault in a unit will be indicated by illumination of a red LED on the front edge of the unit.

281. Generally, one BCU will be provided per bay. An additional BCU will be used for station general alarms and station services.

282. The system will be compatible with a wireless SCADA system.

5. Low Voltage (400V) AC Supplies

283. A Single Line Diagram for the new LV AC supply system is included in the drawing no: ABISR/KHN 030.

284. The LV AC supply for the pumping station auxiliaries will be fed from the new 6 / 0.4 kV dry type power transformers. All the cables, panels, switchboard equipment and all other equipment and material starting from the 6 kV side of the power transformer and up to the auxiliary systems which are to be supplied with LV AC will be provided.

285. Switchboards will be metal-clad form 3B type with installed switchgears and protection devices and electrical measuring instruments. Units will be built up to circuit breakers, isolating fuse switches, isolators, contactors, molded case, miniature circuit breakers, power meter including active and reactive energy. All units, when built up into a complete switchboard, will be such that the completed switchboard has a neat and clean appearance and is readily extensible

286. All the distribution panels will be fitted with miniature circuit-breakers having thermal-magnetic overload and short-circuit protection.

287. Molded case circuit breakers will comply with IEC 947-2 miniature circuit breakers with IEC 898.

288. Motor control switchboards will have all switching equipment, circuit breakers, contactors, solenoid starters, switches, relay and alarm equipment and push-button stations.

289. Push-button stations (start and stop) will be provided with local to remote drives to allow safe operation. Besides, the switchboards will have instrumentation and control equipment. The switchboards will be designed to interface with the remote supervisory control system. All electric data like current, voltage, power factor, active and reactive energy, as well as system condition, alarms and pump operational incidents will be transferred to the control center.

Lahmeyer International in association with InfoCapital Group page 47

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

290. The bottom of the switchboards will be open for cable access. The sides of the switchboards will have a window 100 x 100 mm for control and alarm bus bars.

6. 6 / 0.4 kV Power Transformer

291. A 6 / 0.4 kV power transformer will be provided. The ratings for the power transformer will be determined by the Contractor during the design depending on the needs including spare supply of the pump station.

292. Care will be taken during the selection process that the correct vector group reference is chosen being compatible with the supply and other transformers

293. Where single core cables are selected for connection to either primary or secondary sides of the transformers non-ferrous gland plates will be installed.

7. DC-System and UPS

294. The DC and UPS systems are important systems for reliable and safe operation of the plant as well as the emergency facilities and special care has to be taken to ensure the availability and reliability of its components.

295. The DC and safe AC distributions shall be designed as metal – clad switchboards of similar design as above mentioned LV switchgear with permanently mounted devices and all necessary signaling and control accessories.

296. The DC and safe AC systems shall be provided to ensure power supply for the following:

110 V DC system for control of the switchgear; 110 V DC for essential drives, in-feed to the inverters of the UPS system and DC/DC converter for 24 V DC system; 24 V DC system for instrumentation and control; 400/230 V safe AC system for instrumentation and control;

297. In general the DC and UPS system concept shall be as follows:

2 x 100% 110 V DC systems; 2 x 100% 24 V DC systems with DC/DC-Inverter; 2 x 100% 400/230 and 230 V AC safe.

298. Each system shall be sized to serve all connected consumers and to charge the related battery.

299. The rectifiers shall be installed in closed metal clad cubicles. Each of the Pb lead acid type batteries shall have the capacity to supply 100% of the related system total load at least for one (1) hour.

300. For the power supply of 400/230 V safe AC consumers, 2 X 100% inverters shall be provided. A static change-over switch shall be connected to each inverter feeder from the essential section of the related 0.4 kV board.

Lahmeyer International in association with InfoCapital Group page 48

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

301. The capacity of all DC and safe AC equipment shall be in accordance with the power requirement. As a minimum 20% spare capacity shall be provided.

8. Lighting

302. A lighting system will be provided for the pump station. Lighting panels will be connected to the LV Main Distribution Board. Lamps will be fed from the light board. Lighting distribution board, lighting fixtures and related materials will conform to the specified international standard.

303. Emergency lighting will be provided in all areas and designed in accordance with EN 50172 or international equivalent.

304. The density of the emergency lighting will be 200 lux with respect to the control room and all switchgear rooms. In other areas the density for the emergency lighting should be not less than 10 lux.

305. The Contractor will ensure that the following lighting levels are provided in the pump station buildings:

Pump house 200 lux Office 500 lux Switchgears 300 lux Corridors, staircase 100 lux Control room 500 lux

306. It is envisaged that the following types of lighting will be installed in different areas of the pump station:

Outdoor lighting will be by means of lighting poles equipped with fixtures and lamps Indoor and entrance lighting will be by means of fluorescent lamps, high- pressure mercury and sodium lamps Lighting for smaller rooms such as the office will be by fluorescent lamps Large and high rooms such as pump house will be lighted with high-pressure mercury and sodium lamps with separate bulb fittings for emergency lighting.

9. 400V/230 V System

307. The Small power panels will connect to the LV Main Distribution Boards. Socket outlets will be fed from the small power distribution boards.

308. Small power distribution boards, socket outlets and related materials will conform to the specified international standard.

309. Single phase socket outlets will be installed in all rooms. Number of socket outlets depends of the room size; however not less than 3 socket outlets should be provided in each room. Three phase socket outlets will be installed only where three phase power is required such as in the main pump house or workshop areas.

Lahmeyer International in association with InfoCapital Group page 49

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

310. Socket outlets will be either:

400 V, three-phase, 63 A with load-break isolating switch for welding supplies or 230 V, single-phase, 16 A for general purpose outlets and special tools 311. Small power system installations will be wall-mounted using waterproof type fittings. Materials and junction boxes will be of the industrial standard, preferably of die- cast alloy or galvanized sheet-steel construction featuring an enclosure with a degree of protection of at least IP 55 according to IEC 60529. Junction boxes will have bolted front covers, hinged on boxes of larger dimensions.

312. Plastic industrial boxes with a degree of protection of at least IP 55 should be used in non-industrial buildings such as administration, rest or control room. Captive screws will be preferably used.

313. Junction boxes for installation in V-1 , V-1b, V-11 hazardous areas will be certified according to IEC 60079. Boxes will preferably be of die-cast alloy or glass- reinforced polyester. The enclosure's degree of protection will be at least IP 55 according to IEC 60529.

314. Terminals will be provided on all junction boxes as required. Earthing will be carried out by means of internal/external through-connected earth terminals.

10. Grounding System

315. Earth/ground bars will be installed and a detailed schematic produced from main incoming earth bar to switchgear room earth bars showing earth bar size/cable size and evidence by way of adiabatic equation that correct size has been selected.

316. The supply will include the following:

Earthing grid under and around the pump station Foundation earthing connected to the earthing grid Connection of the transformer’s earth and neutral to the contour with additional ground stakes Fencing earthing Lightning protection system with spark arrester on the roof Supports from the roof to the grounding system with screw connection for measurements. Auxiliary earthing for the whole electric equipment Earthing of all metal components, which are not alive.

317. The maximum earth resistance value even during the driest season will not exceed 1 Ohm at any point. The works will be carried out in full compliance with the international standards.

318. All buried copper conductors should be multi-core and flexible.

319. All protection system to minimize damages caused by lightning to buildings, structures and reservoirs constructed will be supplied.

Lahmeyer International in association with InfoCapital Group page 50

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

320. The system will be in full compliance with the local and/or any other approved safety standards.

11. Instrumentation and Control System

321. The pumping station will have its own Instrumentation and Control System (ICS). The main objective of the ICS is to improve the operational effectiveness of the pump station by ensuring the plant can only be used within safe operational parameters. In addition the system will relieve operators of the responsibility for minute by minute control and provide reports to the Monitoring Center. Main control of the pumping station is done locally.

322. For the pumping station, there will be two levels of control:

i. Local control on the Local Control Panel ii. Supervisory control via ICS system at the control room. (Provision should be made for monitoring and control from a remote PC) 323. The first level of control will not be dependent on the RTU or ICS control.

324. In normal operation, the pump station will be operated via ICS manually or automatically depending on the operator’s choice.

325. The main control parameters for the pump station are: The water level in the intake canal The demand for water Maintenance requirements (pump units and canal) Restrictions to power and energy availability Output water flow

326. The main logic of the operation is to provide control of the pump units with respect to water levels in the fore bay and downstream the pumping station. The other factors to be considered for the overall control of the canal include the unavailability of the pump units (i.e. due to maintenance), annual water entitlement.

327. In addition to basic functionality, plant will provide the following: Ease of operation Modularity allowing the expansion of the system Ease of application of the software Compatibility with technologies developed by well recognized software suppliers

328. The main control parameter for pumping station will be water level in the intake canal. If water level in the intake canal is low, then pumping will be reduced. Conversely, if water level is high pumping will be increased.

329. Water levels in the canal downstream reaches will also be monitored and if these are outside acceptable limits the rate of pumping will be adjusted accordingly.

Lahmeyer International in association with InfoCapital Group page 51

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Monitoring of Water Level 330. Water levels upstream and downstream pump station, as well as upstream and downstream trash screen will be monitored continuously and level changes will be dynamically displayed on the computer screen, and information obtained will be stored for historical recording purposes. A respective alarm will be given by the system for water levels.

Monitoring of the Flow 331. The output flows will be monitored continuously on the outlet pipes of the pumping station and the flow changes will be dynamically displayed on the computer screen, and the data gathered will be stored for historical recording purposes.

Monitoring of Electrical Parameters 332. The electrical parameters such as current, voltage, active and reactive powers, power factor will be continuously monitored, the changes in these parameters will be dynamically displayed on the computer screen, and the data gathered will be stored for historical purposes.

333. The gathered data will provide information about the disturbances and failures in the electricity at the stations, and assist in making corrections at points where it is inappropriate. It will also provide a way to observe the amount of energy consumed.

Monitoring of Pump Station Equipment 334. All the electrical valves, motors, pumps that are listed in the technology scheme including the motor and pump temperature measurements will be controlled and monitored by the ICS system.

335. The system will be off type where remote monitoring and control can be undertaken from a wireless remote PC.

Operation and Maintenance Management 336. The conditions that may result in failures during the operation of the pumps and other equipment will continuously be monitored, and the conditions having the tendency to create failures will be sensed in advance and necessary measures will be taken immediately and healthy operation of such equipment will be provided.

337. The operation period of the pump units and number of operations will be monitored and the data needed for operation and maintenance of the equipment will be provided. The operation of the pump units at equal duration at certain periods will be maintained.

338. A proper warning will be issued when the operating times or numbers of operations of the equipment that need periodic maintenance reach their pre-determined limit values.

339. The statistical data for the equipment such as pumps, motors and electrical switchgear will be obtained by monitoring and recording the failures on this equipment, the necessary alarms for the operators will be provided for the critical equipment in this respect.

Lahmeyer International in association with InfoCapital Group page 52

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

System Hardware 340. The system will have a control center where the data acquisition and storage, supervision and monitoring functions are provided.

341. The pumping station ICS equipment will consist of the following components:

A Remote Terminal Unit (RTU) A desktop computer, together with keyboard, mouse and 21” color monitor High Speed Laser Printers Flow meters to be installed at pump discharge pipes Pump station upstream and downstream water level measurement devices A DC No-break power supply system for the ICS equipment

System Software 342. The general requirements for the ICS software will be as follows:

The ICS software will be of a proven design and reliable, and conform to the industrial standards and will be open type. It will not be proprietary to the Contractor’s system, i.e. it will not be a software package that supports only Contractor’s RTU’s, rather it will be a general-purpose software. The ICS software will Sector multiple RTU brands and models and will provide the required software features needed to easily adapt an RTU that is not supported as standard to the ICS system. The lists of the RTUs supported by the Contractor’s software will be included in the Bid. The system will have an expandable architecture to provide future capacity increases. It will provide multi-level security and password mechanism to prevent the use of the system by unauthorized persons. The access privilege of authorized users will be defined separately and permission will be provided to the users only to access to the areas concerning them. It will provide an on-line operating environment. Adding a new RTU to the system or changing the configuration of the existing RTUs will not result in stopping or hindering the working of the system. The software will be object-oriented and will open more than one window simultaneously to present high resolution and animated color graphics to the users. The software will provide advanced alarm checking and reporting features. The software will provide advanced archiving and reporting features and produce graphical displays and statistical reports from the stored data.

Lahmeyer International in association with InfoCapital Group page 53

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

The software will provide interfaces to large-scale wall screens. The Contractor will provide a list of references in this area. The software will be re-loaded and opened after the completion of all works during the tests. The Contractor will handover to Client the software in “install CD” necessary for re-loading the software to the system in the case of failures.

12. Emergency Diesel Generating Unit

343. One emergency diesel generating unit will provide independent power supply to selected essential consumers during complete black-out and/ or complete shut-down of the pump station.

344. The emergency diesel generating unit will be located in the auxiliary facilities.

345. The rated power is estimated at 1,000 kVA and will be verified during detailed design.

346. The EDG shall be able to supply the following consumers:

(i) Emergency dewatering pumps (ii) Drainage pumps (iii) Emergency lighting system (iv) Charging of UPS and DC-System (v) Dedicated units and BOP related essential consumers in case of main power supply failure.

347. The EDG engine shall be designed for long time duration of 120 h per year, with a day tank with gravity flow fuel system to the injection pump for 8 h continuous operation and a storage tank.

348. The emergency diesel generator shall be equipped with the required AC and DC equipment (e.g. switchboard, battery, charger, etc.) for the power supply of the related consumers and start-up facilities.

349. The generators shall be synchronised and connected via the incoming circuit breakers to the essential service boards.

350. The entire electrical system shall be designed for local and remote operation and shall be controlled and monitored through the DCS.

351. Local and remote operation for test runs of the emergency diesel generators shall be possible under normal power plant operation. The start-up, initiating automatic synchronising and shutdown shall be possible either locally or remotely through the DCS.

Lahmeyer International in association with InfoCapital Group page 54

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

352. The emergency diesel generating unit will have the following characteristics:

Diesel engine Type Diesel 4-stroke Rated output 865 kW (estimated) Rated speed 1,500 1/min Cooling closed water, radiator with motor fan Storage tank fuel for 120 hours continuous operation at nominal conditions Generator Type 3-phase, synchronous Cooling air-cooled, self-ventilated Rated output 1,000 kVA (estimated) Rated voltage 3-ph 400/230V Rated frequency 50 Hz Rated speed 1,500 1/min Insulation class F Protection class IP23

13. Earthing System

353. In order to comply with protection specifications contained in DIN VDE 0100 and IEC it is necessary to follow the requirements to maximum earth losses.

354. Earthing device of the substation will serve for protection and working functions which include: provision of electric security; neutral ground of transformers, arc- suppression reactors and other HV and LV appliances; establishment of current circuit for protection from ground short circuit; tapping of pulse current lightning arresters and dischargers; provision of protection for underground structures from damage by ground short circuit.

355. Reliability of fulfilment of above functions will be provided by rating of electrical performance of earthing devices, as well as IEC requirements to constructive design of earthing devices. In the general case, earthing device will contain the natural grounding switches and artificial grounding switches.

356. Reduction of an impulse resistance at places of lightning conductors’ earthing, dischargers, non-linear overvoltage limiters, current and voltage transformers will be achieved by laying of horizontal grounding switches which will provide spreading of impulse and radio-frequency currents in 3 and 4 directions and not less than in 2 places are connected to earthing device. With the purpose to reduce an impact of seasonal variations of the earth electric structure on stress rate to earthing devices, horizontal elements of the basic structure will be laid at a depth of not less than 600 mm. In rocky ground mentioned depth may be decreased to 0.15 m.

357. Vertical grounding switches will be installed evenly over the basic structure perimeter and at expansion of artificial grounding switch – over its outer part perimeter. Their length and quantity will be identified by design calculation.

Lahmeyer International in association with InfoCapital Group page 55

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

358. If equipment is to be installed on a bed stone foundation, additionally vertical grounding switches may be located inside the basic structure. In this case it is recommended to install them at workplaces.

14. Rules and Standards

359. HV switchgear and power transformer will be designed, manufactured and installed in accordance with requirements of the following international standards:

Switchgear

IEC Standards IEC 298 – HV switchgear in metal case IEC 265 – HV switches IEC 129 – AC switches and earthing switches IEC 694 – General conditions for HV switchgear standards IEC 56 – HV automatic switches IEC 801 – Monitoring and control IEC 529 – Level of security

Transformers

IEC 60038 - Voltage according to IEC (International Electro-technical Commission) standard IEC 60071 – Coordination of insulation IEC 60076 – Power transformers IEC 60354 – Guide for use of power transformers submerged in oil IEC 60542 – Guide for use of on-load tap-changers IEC 60551 – Identification of pressure of transformers and reactors IEC 60606 – Guide for use of power transformers IEC 60616 – Labeling of power transformers IEC 60722 – Guide for testing of lightning impulse and switching impulse of power transformers IEC60905 – Guide for use of power transformers IEC 61024, Parts1 and 2 – Protection of structures earthing from lightning discharge DIN BDE 0141 – Earthing systems for power installations with preset voltage more than 1 kV DIN BDE 0151 – Material sizes and minimal sizes of grounding electrodes in relation to corrosion DIN BDE 0165 – Installation of electrical equipment in danger zones DIN BDE 0185 – Protection system from lightning discharge Part 1 - General for installation work Part 2 - Installation of special structures Part 100 - Protection of structures (general principles)

Lahmeyer International in association with InfoCapital Group page 56

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

E. Civil Works

360. The civil works requirements for Khamza New Pump Station will consist mainly of the design and construction of the following structures:

(i) Intake canal (ii) Forebay (iii) Intake structure with trash racks (iv) Pump station building (v) Discharge pipe system (vi) Discharge basin structure (vii) Discharge canal with automobile bridge (viii) Sedimentation basin for technical water supply

361. The pump station site will include the following facilities:

housing for operational staff facilities for garage, workshop and emergency diesel power station pump station building for drainage and dewatering guard post toilets, rest rooms

1. Pump Station Building

362. The pump station building consists of substructure and superstructure. Substructure will be constructed with in-situ reinforced concrete. The building will be split with expansion joints into two sections.

363. All main and auxiliary equipment, as well as drainage system, gallery and suction emptying system, technical water supply system, oil supply and disposal system, etc. will be located in the substructure.

364. The pump room building consists of pillars made of reinforced concrete with walls made from reinforced panels and slabs, 20.3 m 24.5 m 74.0 m (width height length). Two sections divided by expansion joints have a length of 37 m each.

365. An overhead bridge crane with a capacity of 50/15 ton will be installed in the pump house.

366. All electric equipment, switchgear, control panel will be located on the first floor, while administration and residential premises will be on the second floor.

367. Reinforced concrete elements for construction of the pump station building can be manufactured in Uzbekistan. Internal partitions will be made from brick.

368. Pump house, switchgear, control panel rooms will have concrete floors, and in the office facilities the floor surface will be parquet and linoleum.

369. The roof will be constructed from a special steel sheet cover with integrated heat isolation.

Lahmeyer International in association with InfoCapital Group page 57

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

2. Intake Canal

370. The intake canal, 420 m long with a designed capacity of 91.5 m³/s, takes water from the existing ABMK 1 canal downstream of the existing Jondor Pump Station. The canal cross section has a bottom width of 8 m, side slope (m) is 2.5 and a depth of 6.62 m. It is intended to construct a berm with a width of 6 m at both sides of the canal.

371. The excavation of the nearby pump station will be done with 5 m steps and construction of 2 m interim berms.

372. To avoid channel erosion the first 220 m of the canal will be gravel lined with a thickness d = 30 cm, while the remaining 200 m will be concrete-lined with a thickness d = 15 cm.

3. Forebay

373. The forebay is a section connecting the intake canal with the water intake structure, and has a total length of 39 m. To reduce siltation and improve water flow conditions through all intake openings, the forebay will have a reverse slope. Forebay bottom and slopes will be lined with concrete d =15 cm above the gravel and sand layer d = 30 cm. To reduce filtration pressure to the lining, weep holes will be provided.

374. Connection of the forebay with the intake structure will be provided with reinforced concrete reverse walls.

4. Intake Structure with Trash Racks

375. The dock type intake structure consists of an eight in-situ concrete piers structures. It is divided into two sections with 4 opening in each section, with an opening width of 4.5 m and a pier thickness of 1 m.

376. To clean water from the floating debris, each intake opening is equipped with a trash rack, which will be cleaned with a special trash rack cleaning machine, moving on the rail along the whole structure.

377. The rail is installed on the bridge made of typical reinforced concrete plates, each 6 m long. Each pump intake can be closed by stoplog.

5. Subsurface Galleries

378. To supply water from the intake structure to the pump suction pipes, rectangular subsurface galleries will be constructed in the pump station building. Each pump has its individual gallery. Gallery dimension near the intake structure is 2.2 m 4.5 m (height width) with pier thickness of 1 m, while near the pump station building the gallery dimension is 2 m 4.5 m (height width) with pier thickness of 2.5 m.

379. The gallery is 30.8 m long. Similarly to the intake structure, the gallery is divided into two sections with 4 opening in each section. The width of each section varies from 23 m (intake structure) to 29.5 m (pump station’s building). The gallery will be constructed with in-situ reinforced concrete.

Lahmeyer International in association with InfoCapital Group page 58

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

6. Discharge Pipelines

380. Eight pump units located inside the pump station will have eight individual discharge pipelines dia. 2300 mm, each 50 m long, which will extend up to the 1st anchor support. The open type pipeline is with one intermediate support and expansion joint at each line.

381. After the 1st anchor support, at the distance of 54 m, eight pipelines join into two lines with a dia. 4100 mm with a total length of each 620 m. To exclude expansion joints where pipelines join, the pipeline section between the supports No. 1 and No. 2 is buried. After support No. 2 up to outlet structure the open type pipeline is placed on anchor and intermediate supports. The pipelines are split into separate spans, each 120 m long. Each span has an expansion joint reducing the temperature stress in the pipeline walls. The distance between the interim supports is 20 m.

7. Outlet Structure

382. Both pipelines end at the siphon outlet structures with vacuum breaker valves providing a save blockage of the main canal from the discharge pipelines during the power shutdown.

383. The outlet structure is made of in-situ reinforced concrete. It comprises a siphon headwall and a stilling well serving for smooth water supply to the main canal.

384. Total dimensions of the structure are 52.5 m 11.0 m 16.5 m (length height width).

8. Discharge Canal

385. Reach of the machine canal with a section of b = 8.0 m, m = 2.0, h = 6.0 m and 500 m long provides a connection of the outlet structure to the existing main canal.

386. The entire reach (500 m) will be lined with in-situ concrete.

387. At a distance of 145 m away from the outlet structure, an automobile bridge will be constructed to cross the diversion canal.

9. Sedimentation Basin for Technical Water Supply

388. For supply of technically clean water to main pumps, the project shall arrange the technical water supply system consisting of two sediment basins with intake and discharge pipelines.

389. Subsurface intake pipelines take water from the outlet works and supply water to the primary sediment basin. All suspended sand fractions are settled in the primary sediment basin.

390. After the settlement of the sand fraction in the primary sediment basin, water is used in the water cooler of the electric motors and in oil coolers of the main pumps; a part of the flow is supplied to the sediment basin of fine purification for the further settlement and its supply to pump seals.

Lahmeyer International in association with InfoCapital Group page 59

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

391. The primary sediment basin is a trapezoidal canal with a length of 120 m, over which a special siphon cleaning machine travels on the rail track for cleaning and removal of settled sediments into the flume network and further to the intake basin.

392. Of the three-chambered secondary sediment basin, two chambers are used for desilting; the third chamber is used as a reservoir of clear water.

393. Cleaning of the sediment basin is performed by hydraulic flushing.

10. Protection Dam

394. For flood protection of the pump station building from water from a possible burst of the pipeline, it is envisaged to build a protection dam near the first anchor support.

395. The upstream slope of the protection dam is strengthened by concrete lining of 20 cm thickness.

11. Auxiliary Facilities

396. In the area of pump station it is planned to locate the auxiliary facilities: the building for the maintenance staff, garage, emergency diesel power station and workshop, the buildings of two drainage pump stations, guard post and toilets.

397. All these buildings will be built from brick on the concrete strip foundation. The floor will be made from typical round cored slabs to be manufactured at the factories of Uzbekistan. The roof will be constructed from a special steel sheet cover with integrated heat isolation.

398. The territory will be landscaped, all buildings will be plastered and painted.

F. Geotechnical Investigation

1. Introduction

399. The geotechnical investigation report prepared by the Uzsuvloyiha Design Institute as part of this feasibility study is included as Appendix 6.

400. Additional information on geotechnical investigations for the construction of the Khamza New Pump Station is also available from the following previously prepared investigation reports: In 1980 the Uzsuvloyiha Design Institute has implemented geotechnical investigations for Detailed Design of Khamza Auxiliary Pump Station in Bukhara region. In 1984 the Institute has implemented geotechnical investigations for Detailed Design of drainage construction to divert ground waters away from existing Khamza 1 Pump Station area.

401. This information is used as the basis for further geotechnical investigations and assessments of the conditions for the proposed Khamza New Pump Station.

Lahmeyer International in association with InfoCapital Group page 60

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

2. Geotechnical Conditions

402. The proposed site for the pump station is located at the western slope of Karakul plateau. The plateau consists of deposits formed in Neocene age, covered by Aeolian sands with a thickness from 0.5 to 4-5 m. Deposits of Neocene age are presented by weak sandstones with frequent interlayers and lenses of moderately stronger sandstones and siltstones with a thickness ranging between 0.1 m and 0.5 m.

403. Gypsum content in the soils is to 1.1% of the air-dry soil.

404. According to the operation manual of the existing Khamza 1 Pump Station, the elevation of ground water level is 190.5 m (as per 2012). Water is saline, with dissolved salts of sodium chloride and sulfate chloride (8.8-9.4 g/l).

405. The content of anions of SO4 is 3168 mg/l, HCO3 = 2.8 mg/eqv.

406. Water is aggressive to Portland cement as per standard, GOST 10178-76. Therefore, it is suggested to use the sulphate-resisting cement as per recommendations of the local standard.

407. Weak sandstone will be the base/sub-soil beneath the foundation of the pump station. Therefore, it is required to confirm this during the detailed geotechnical investigation and design the foundation accordingly to consider the properties and bearing capacity of the existing subsoil.

3 408. The density/unit weight (dry) of sandstone is 2.67-2.70 tons/m . The submerged (with natural moisture) density/unit weight of sandstone is 1.59-2.0 tons/m3, while only the skeleton’s unit weight is 1.57-1.83 tons/m 3.

409. Unit weight of loose sandstone (with structural damage) is 1.25-1.30 tons/m3, and under compacted condition is 1.39-1.45 tons/m 3. Sandstone filtration coefficient is 3- 5 m/day. Nominal design pressure is 3 kg/cm2.

410. The present report does not include any test results for the physical and mechanical properties of the subsoil including the bearing capacity of subsoil beneath the foundation. Therefore, during the detailed design stage further detailed geotechnical investigations of the project site will be required. The final design of structure and its foundation will be based on the properties of subsoil and the recommendations included in the final geotechnical report.

3. Seismic Condition

411. The proposed project site is located in a seismic zone. The seismicity of the proposed project site of the Khamza New Pump Station is assessed at 8 points (in accordance with K K 2.01.03-96), which can be confirmed during the detailed design of the project.

412. The category of sub-soil beneath footing is Class III with respect to seismic properties of the subsoil and shall be verified during the detailed geotechnical investigation of the site.

Lahmeyer International in association with InfoCapital Group page 61

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

413. The feasibility study level design of the building and foundations of the pumping station is according to the local seismic code “KMK 2.01.03-96” of the country.

414. The design should be verified during the detailed design phase. It is recommended to perform 3-D nonlinear structural analysis and design of the pumping station building as required by the seismic code during the detailed design phase.

G. Topography

1. Introduction

415. Information from the topographical survey conducted by the Uzsuvloyiha Design Institute as part of this feasibility study is included as Appendix 7.

416. The proposed project area of Khamza New Pump Station is located in the Alat District of Bukhara Province. The significant part of the territory is occupied with desert pasture. The Bukhara Province is located within coordinates of 39° 48’ N and 69° 10’ E.

417. The District of Alat is located on the west of Bukhara Province, bordered with Turkmenistan and is about 430 km southwest of Tashkent. The area is sharply characterized by continental climatic conditions, prolonged hot, dry summers with short periods of precipitation.

418. The proposed Khamza New Pump Station is to replace the existing Khamza 1 Pump Station and Khamza Auxiliary Pump Station. The existing Khamza 1 Pump Station is located at PK 501+00, on a part of Amu-Bukhara canal (ABMK). The building of existing Khamza 1 Pump Station was built and constructed in 1965. The water intake into Amu-Bukhara pumping canal is from the right side of Amu Darya River in the territory of Turkmenistan. The canal traverses from west to east direction and Khamza 1 Pump Station along with Khamza Auxiliary Pump Station is the first pump station on Amu-Bukhara Canal in the cascade of other pumping stations.

419. The proposed Khamza New Pump Station is located about 300 to 600 m from Khamza 1 and Khamza Auxiliary Pump Station on the southwest side.

2. Topographic Survey

420. The Design Institute conducted a survey of Khamza New Pump Station in February 2013 (refer to Appendix 7). The survey consists of an area survey for the site of proposed building of pump station and a line survey along the center line of the traverse from the intake to the outlet.

421. The area survey is on a total area of about 400 m x 300 m and it shows the existing features and the spot elevations of the ground. The spot elevations are shown with reference to a permanent benchmark (Rp-6-13g, elevation 205.762). A total of seven (7) available permanent benchmarks are marked and shown on other sheet with their elevations.

422. A line survey along the center line of the traverse of proposed intake channel and discharge channel along with the building is accomplished comprising the cross sections at a longitudinal interval of 100 m and up to 40 m at each transverse side of center line.

Lahmeyer International in association with InfoCapital Group page 62

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

423. It is recommended to do a detailed area survey of the site before detailed design is undertaken including the area from the start of intake channel to the end of outlet channel. The detailed survey should show the complete topography of the area including the contours, elevations, existing features, the coordinates and any additional cross sections as required for the detailed design.

H. Summary Cost Estimate

424. Based on the preliminary design (feasibility level) of the Khamza New Pump Station respective costs were estimated individually for the following equipment, namely all civil structures, building services, hydraulic steel structures, mechanical equipment, electrical equipment, and instrumentation and control equipment.

425. The Cost Estimation is based on “Ex Works” World market. Shipment, loading, unloading, decommissioning and recycling of equipment, installation, testing and commissioning costs were added to the “Ex Works” Costs, considering the project location and the prevailing environmental conditions.

426. A total of ten percent (10%) was considered for mechanical and electrical works and seven percent (7%) for civil works as contingencies for unforeseen events or works, respectively.

427. Considering the above conditions; the summarized costs for the proposed construction of the Khamza New Pump Station were estimated at $100.3 million as shown in Table 12. The detailed cost estimate breakdown is included in Appendix 8.

Table 12: Summary Cost Estimate for the Khamza New Pump Station

ITEM / SYSTEM / EQUIPMENT COST [US$]

(A) Mechanical Equipment 24,335,000 (B) Building Services 1,010,000 (C) Hydraulic Steel Structure 19,267,000 (D) Electrical Equipment 18,381,000 (E) Instrumentation and Control 422,000 Total Khamza New Pump Station 63,415,000 Applied Contingencies (10%) 6,341,500 Sub-total Khamza New Pump Station 69,756,500 (F) Civil Structure 28,620,500 Total Khamza New Pump Station 28,620,500 Applied Contingencies (7%) 2,003,435 Sub-total Khamza New Pump Station 30,623,935 Grand Total Khamza New Pump Station 100,380,435

Source: Present Study, 2013

Lahmeyer International in association with InfoCapital Group page 63

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

IV. UPDATED ECONOMIC AND FINANCIAL ANALYSIS

A. Background to Supplemental Study and Analyses

428. During the PPTA period there was continuous uncertainty regarding the availability of loan funds and the extent to which the Government would be willing to contribute towards real investment. Whilst it was clear which six pump stations should be replaced/rehabilitated it was, nevertheless, unclear what other supporting sub-projects should be considered and how much should be invested in these. Given no investment target, to complete the Study on schedule, the Consultants were obliged to submit an investment package which covered the replacement/repair of all the pump stations and a small number of relatively low-cost supporting sub-projects. Even prior to Study completion, it was becoming increasingly obvious that loan funds were very tight and that Government was not going to contribute any meaningful counterpart funding (apart from paying financing charges).

429. Despite the obvious lack of funding sources, the Government continued to insist that all its desired investments should be funded from external sources and to reduce the capital costs, made a belated request to design a reduced pumping capacity Khamza 1 Pump Station. This task was undertaken and overall costs were reduced by around $25 million (refer to the Section III- Khamza New Pump Station Design).

430. At the same time, there was some firming-up of possible external loans availability and by mid-2013, some $320 million had been identified. Given no counterpart funding, despite the Khamza 1 Pump Station savings, the loan availability was, nevertheless, far short of the $412 million (excluding price contingencies) required to cover the full investment package. To create an investment package to utilise the loan availability two further measures were taken, as follows: Approximately $86 million for discharge pipes was removed from the loan package and assumed would be paid by Government over a 7 year period, under its O&M budget. Some pumps in both Kizil Tepa Main and Kizil Tepa Auxiliary Pump Stations were excluded from the investment package, thus reducing the ‘with-project’ pumping capacities of these pump stations.

B. Approach to the Analysis

431. The main task was to re-assess the economic viability of the reduced cost investment package, based on revised estimates for the five (5) relevant pump stations, which were recalculated based on the above discussion. The revised detailed cost breakdowns for those pumps stations are included in Appendix 9.

432. Further reductions were introduced through the application of some lower physical contingency factors than those recommended in the PPTA Final Report. Whilst these lower rates were approved by ADB, the Consultants wish to record their opinion that they believe that their original estimates were realistic, given the high levels of uncertainty involved when installing pumps, motors and modernised support systems into operational pump stations.

Lahmeyer International in association with InfoCapital Group page 64

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

433. A number of other assumptions used in the PPTA Final Report were also changed, as a consequence of ADB directives. Of these the significant changes were as follows :

Electricity price was set at UZS 112.2/kwh or $0.53/kW-hr (using the official exchange rate) compared to $0.75/kW-hr in the original base case analysis. If the real exchange rate were to be applied the current UZS price would be equivalent to $0.4/kW-hr. Decline scenarios. ADB suggested that possibly using differing annual decline rate assumptions (for example 1%, 2%, 4% and 5%), possibly changing over time, and starting at different times, might be appropriate. Although other changes were discussed, following confirmation from ADB, in the final analysis no alterations were made to the cost of cotton-picking labour and no increases were made to ‘with-project’ crop productivity. The question of exchange rates remains in limbo. The Consultant does not believe it is appropriate to use the official $/UZB exchange rate in the economic analysis.

434. A similar approach to that taken when preparing the PPTA Final Report analyses was adopted, and each of the supporting tables which featured in the first analysis have been utilised in the latest analyses, with changes made where appropriate.

C. Analysis Results

435. With decreased capital costs of around 16% (having accounted for the extra maintenance cost transferred to Government to cover the repair/replacement of discharge pipes serving four pump stations), with decreased ‘with-project’ net benefits of around 9%, (resulting from the 24,400 ha in the service area of the Kizil Tepa Pump Station and its Auxiliary which would no longer receive irrigation water) and with similar unit energy costs, the EIRRs for the Reduced Cost Options (with pump decline and with pump failure) are quite similar to those obtained for the Full Cost Options presented in the PPTA Final Report. The results of the base case analyses and a range of sensitivity analyses are presented in Table 13.

436. Given the challenges in predicting a future ‘without-project’ situation, it is suggested that it is reasonable to consider that the base case EIRR lies between 12% and 18%.

437. There are, however, a number of issues which could arise and which could result in poorer returns. Ironically, for example, if the ABIS mechanics were able to continue keeping the aging pumps in working order, as they have done up to now, the ‘without- project’ crop returns would decline less rapidly, the ‘with-project’ benefits would be reduced, and the economic viability would become less favourable. Sensitivities, reflecting this possible situation, through reducing the assumed annual decline rates in pumping capability and through delaying the onset of decline, were carried out and the significant negative impacts these have are evident from the results presented above.

Lahmeyer International in association with InfoCapital Group page 65

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Table 13: Base Case and Sensitivity Analysis – EIRR % Case Gradual Pump Total Pump Decline Scenario Failure (base case) Scenario Base Case 12.2 18.4 Electricity price : - US$ 0.075/kwh 11 16.5 - US$ 0.100/kwh 9.4 13.9 Capital costs : - Increased to 110% 10.7 17.5 - Increased to 120% 9.4 16.6 Cotton price : - Increased to 110% 13.3 19.7 - Decreased to 90% 11 16.9 Pump capacity decline rate: - Reduced from 5% to 3% 7 na Onset of first year of decline - Advanced by 1 year 11.1 na - Advanced by 2 years 9.9 na - Advanced by 3 years 8.6 na na = not applicable.

438. Two other significant factors could negatively impact on the economic viability of this Reduced Cost Option.

439. Contingencies have been cut significantly; in reality this could result in further funds having to be found from Government resources to make good future shortfalls. Capital costs would thus increase and the EIRR would fall. Alternatively, corners could be cut with the likely impact that the system would not operate as efficiently as it was originally designed to do, resulting in either increased O&M costs or reduced pumping capacity leading to reduced ‘with-project’ irrigation, or both.

440. The shifting of financing for the construction/repair of the discharge pipes in four out of the five pump stations, from being a loan to being a Government responsibility also threatens potentially negative impacts. The Government was unable to offer any significant counterpart funding and yet is now facing the prospect of having to allocate over $80 million of additional O&M funding. The possibility for inadequate provision and the breakdown of these pipes is one of serious concern. If, has already been the experience, there are major pipe bursts, the consequences could be catastrophic, in terms of destruction of pumping facilities located at the base of the pipes, of loss of human lives, and, if repairs cannot be implemented rapidly, of major irrigation failure.

441. Whilst the above issues weigh against the economic viability of the proposed Reduced Cost Option being highly favourable, it should also be borne in mind that the ABIS system provides or supplements supplies of DMI water to a large number of towns and communities in the ABIS area. The benefits which would result from safeguarding these supplies have not been included; they are considered to be very significant.

Lahmeyer International in association with InfoCapital Group page 66

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

442. Consideration should also be given to the fact that other investments in the ABIS system have recently been or are still being made. If the main pump stations of concern to the proposed Project were not replaced or rehabilitated, these other investments would be wasted. These include the Navoi Pump Station, which is part of the Kizil Tepa irrigation system, the replacement of the Kuyu Mazar Floating Pump Station, which works in conjunction with the main Kuyu Mazar Pump Station, and the on-going Land Amelioration and Drainage Projects.

D. Guide to Revised Tables

443. In Annex 5 of the PPTA Final Report twenty-three (23) tables were presented. These are listed below, and indications given where changes have been made. The revised tables are included in Appendix 10.

Table 1: ABIS Irrigated Area (ha), by Irrigation System Administrations (text unchanged) Table 2: Irrigated and Cropped Areas (ha) by ABIS Irrigation Scheme – 2011 (reduced areas noted) Table 3: Cropping Patterns and Intensities for the Study Area Irrigation Schemes (unchanged) Table 4: The ABMK System - Reach Lengths and Capacities in km and m3/s (text unchanged) Table 5: Main Pump Stations within the Study Area - Summary of Main Features (text unchanged) Table 6: Power Consumption 2006-2011 for Main Pump Stations with Kuyu Mazar Auxiliary, Navoi and Karaul Bazar (Mwh/Month) (unchanged) Table 7: Energy Consumption and Cost by Irrigation System (Average 2006-2011 Use at 2013 Financial Prices) (latest electricity price and exchange rate used) Table 8: Current and Future Energy Consumption and Pumped Volumes for Total Study (latest electricity price, exchange rate and reduced ‘with-project’ area identified) Table 9: Non-Energy Current O&M Expenditure for Main Pump Stations (UZS Million) (unchanged) Table 10: Farm Holdings in Bukhara District (Areas in ha and numbers of holdings) (unchanged) Table 11: Poor Drainage & Salinity Areas and Amelioration Activities (unchanged) Table 12: Crop Yield Assumptions, Present & Future 'With-Project' tonnes/ha (unchanged) Table 13: Summary of Agricultural Produce and Input Prices at Constant 2012 Economic and Financial Prices (UZS/Unit) (latest exchange rates and electricity rates used) Table 14: Summary of Net Crop Returns, Present and Future, 'With-Project', at Constant 2012 Financial and Economic Prices, UZS'000 /ha/Crop (latest exchange rates used) Table 15: Current Cropping Activity and Net Income in the Project Area (latest exchange rates used) Table 16: Total Capital Costs Summary at Constant 2012 Financial Prices in US$ Million (revised sub-project costs) Table 17: 'With-Project' Pump Station Annual Non-Energy Costs (Reduced Cost Option at Constant 2012 Financial Prices in US$ Million) (revised costs based on new capital costs) Table 18: Capital Cost Summary at Constant 2012 Economic Prices (Full Cost Option in US$ Million) (revised costs based on new financial capital costs) Table 19: EIRR Summary (%) (updated) Table 20: Financial Returns in UZS’000/ha (2012) (unchanged) Table 21: Financial Returns/ha in ‘UZS'000 ‘Without’ and ‘With-Project’ Situations (updated) Table 22: Average Financial Returns per Farm in UZS '000 ‘Without’ and ‘With-Project’ Situations (updated) Table 23: Total With-Project Saved Financial Farm Returns & Manual Wages (updated)

444. In addition, a total of forty-nine (49) supporting tables have been updated for this Supplemental Report and are included in Appendix 11.

Lahmeyer International in association with InfoCapital Group page 67

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Table A.1 Cotton and Wheat. Border Parity Price Calculations (updated exchange rate) Table A.2 Fertilizers. Border Parity Price Calculations (updated exchange rate) Table A.3 Crop Budgets. Main analysis (updated exchange rate) Table A.4 Crop budgets. Vegetables (unchanged) Table A.5 Crop budgets. Fruit (updated) Table A.6 Crop budgets. Fodder (updated) Table A.7 Capital costs - Khamza New – new combination (substantial change) Table A.8 Capital costs - Kuyu Mazar – rehabilitation (substantial change) Table A.9 Capital costs - Khamza 2 – rehabilitation (substantial change) Table A.10 Capital costs - Kizil Tepa – rehabilitation (substantial change) Table A.11 Capital costs - Kizil Tepa Auxiliary – rehab (substantial change) Table A.12 Capital costs - ABMK rehabilitation (new exchange rate) Table A.13 Capital costs – SCADA (new exchange rate) Table A.14 Capital Costs - Pilot Farms (new exchange rate) Table A.15 Capital Costs – Consultancy (new exchange rate) Table A.16 Capital Costs – PMO (new exchange rate) Table A.17 Capital Costs – PIU (new exchange rate) Table A.18 WOP Decline scenario slow (unchanged) Table A.19 Without-project' Irrigated Areas and cropping patterns. Gradual (unchanged) Table A.20 Without-project' Cotton, Forage, Vegetables areas. Gradual (unchanged) Table A.21 Without-Project' Other crops & Wheat areas. Gradual (unchanged) Table A.22 Without-project' Net crop returns. Kuyu Mazar. Gradual (updated) Table A.23 Without-project' Net crop returns Kizil Tepa. Gradual (updated) Table A.24 Without-project' Net crop returns Karaul Bazar. Gradual (updated) Table A.25 Net agricultural returns. Gradual (updated) Without & with project non-energy PS Recurrent Costs - gradual decline Table A.26 (updated) Table A.27 Without-Project Power consumption. Gradual decline (updated) Table A.28 With -project power consumption. Gradual decline (updated) Table A.29 Decline scenario – failure (unchanged) Table A.30 Irrigated Areas and cropping patterns. Failure (unchanged) Table A.31 Without -project'. Cotton, Forage, Vegetables areas. Failure (unchanged) Table A.32 Without-project'. Other crops & Wheat areas. Failure (unchanged) Table A.33 Without-project'. Net crop returns. Kuyu Mazar. Failure (updated) Table A.34 Without-project'. Net crop returns Kizil Tepa Failure (updated) Table A.35 Without-project'. Net crop returns Karaul Bazar Failure (updated) Table A.36 Without-project'. Net incremental agricultural benefits. Failure (updated) Table A.37 Without and with project non-energy PS Recurrent Costs – Failure (updated) Table A.38 Without-Project Power consumption. Failure (updated) Table A.39 With -project power consumption. Failure (updated) Table A.40 Capital cost financial phased (updated) Table A.41 Capital cost economic phased (updated) Table A.42 Cash flow. Gradual decline (updated) Table A.43 Cash flow – Failure (updated) Table A.44 Expenditure by Outputs (updated) Table A.45 Expenditure by Category (updated) Table A.46 Expenditure by Year (updated) Table A.47 Expenditure by Financier (new) Table A.48 Detailed Cost Estimates by Year (new) Table A.49 Detailed Cost Estimates by Financier (new)

445. The Financial Management Assessment prepared as part of the PPTA Final Report has also been updated (refer to Appendix 12).

Lahmeyer International in association with InfoCapital Group page 68

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

V. ECONOMIC AND FINANCIAL ANALYSIS (LINKED DOCUMENT FOR RRP 44458)

A. Approach and Methodology

446. The economic and financial analyses prepared assumed that all subprojects which had been recommended for implementation would be included in the project cost; due to budgetary constraints, however, it was necessary to scale down the level of the originally proposed investment. The main subprojects comprised five pump stations (PS) (Khamza New, Khamza 2, Kuyu Mazar, Kizil Tepa (partial) and Kizil Tepa Auxiliary (partial)). It was also necessary to reclassify the costs of replacing the discharge pipes in all but the Khamza New PS from a loan to a maintenance cost, to be borne by the Uzbekistan Government. Other subprojects included the Amu Bukhara Main Canal (ABMC) rehabilitation subproject, the decision support system (DSS) and supervisory control and data acquisition (SCADA) subproject and the Climate Change Adaptation and Demonstration Farms subproject. Management and implementation supporting activities were also included. The main economic benefit of the Project would be to maintain existing levels of agricultural production in most parts of the Project Area and to limit the extent of decline which would ensue if the existing pumps are not replaced. With improved pump-set efficiencies there would also be substantial energy savings. Project investment is focused on three irrigation schemes, covering around 250,000 hectares (ha), which lie within the overall ABIS area of 315,000 ha.

B. Key Assumptions

447. All investments and benefits have been valued at late 2012 prices. For traded commodities, such as cotton, fertilizers, and wheat, border parity prices, based on World Bank Commodity price projections, were prepared. For non-traded commodities, all prices were based on current market prices. A shadow value of 0.8 was applied to normal agricultural wage rates, but not to that used for cotton harvesting where it is becoming increasingly difficult to find sufficient labor. A markup of 20% was applied in the economic analysis to standard farm machinery rental charges, which are considered to be rather low and generally under-reflective of the costs of replacement. A standard conversion factor of 0.8 was applied to the local currency portion of capital costs. The current price for power at SUM 112.2/kW-hr, was applied in the base case economic analysis.

C. Project Benefits

448. This Project is focused primarily on sustainable and reliable water supplies and is unlikely to make any significant contribution towards improved cropping productivity. Project benefits will be derived from (i) the avoidance of the crop losses which would be incurred if the existing pump stations are not replaced or rehabilitated, (ii) some improvement in water conveyance efficiencies resulting from the rehabilitation of the ABMC structures and improved system management which will be facilitated through the DSS and SCADA interventions, and (iii) the reduced power consumption of the higher– efficiency pump sets.

Lahmeyer International in association with InfoCapital Group page 69

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

449. Future Without Project. All the large pumps within the pump stations of concern to this study are between 38 and 48 years old. Assessment reports generally indicate that all are in either worn or in critical condition, but with skilled and innovative maintenance they continue to operate. Despite the occasional pump and discharge pipe breakdown and periods when insufficient water flows from the Amu Darya, the Amu Bukhara Irrigation System (ABIS) scheme continues to be irrigated. Nevertheless, two scenarios have been identified to represent the alternative options of future system decline. The more conservative scenario assumes as a base case that within a few years, depending on the current age of the pumps, there will be a slow annual decline in pumping hours. In the base case it is assumed that the 1965 constructed Khamza 1 and Kuyu Mazar PS pumps would start declining in Year 4, the increasingly heavily used Khamza 2 PS pumps in Year 6 and the two less worn Kizil Tepa PS pumps in Year 7. Sensitivity analyses, where the decline onset period is extended, were undertaken. The more pessimistic scenario assumes that the pumps within a given pump station will totally fail over a four year period. Differing dates when the breakdowns within a given pump station will commence have been assumed according to pump age and use. The consequences of reductions in pumping capacity in terms of areas irrigated were calculated and schedules of declining net farm income prepared up to Year 25.

450. Future With Project. Following replacement or rehabilitation of the pump stations it is assumed that present cropping and cropping intensities can be maintained at current levels for the main part of the Project Area. Inevitably, where only some of the pumps will be replaced, part of the command area currently served by the two Kizil Tepa PS will not be served. Two on-going land drainage programs are currently being implemented, the benefits of which should manifest in the near future and should impact beneficially on the ‘with’ (WP) and ‘without-project’ (WOP) situations. Hence, no project- induced improvements in cropping productivity have been considered in this analysis. Once the new pumps begin operating, it is assumed that there will be substantial energy savings. Maintenance costs will, however, be considerably higher as the new machinery will be much more complex and less tolerant of the less sophisticated maintenance practices currently applied. It is also anticipated that with improved pump reliability, improved main canal structures and the provision of management facilities, there should be some saving in the total amount of water required to irrigate the scheme.

D. Financial Analysis

451. Study Area. The total area of the ABIS is approximately 315,000 ha. Development activities funded under the proposed Project are likely to have an impact on approximately 225,000 ha within three irrigation schemes as follows:

(i) Karaul Bazar – approximately 16,000 ha within Bukhara Region, (ii) Kuyu Mazar – approximately 91,000 ha within Bukhara Region, and (iii) Kizil Tepa – approximately 119,000 ha within Bukhara and Navoi Regions.

452. Crops and cropping intensities. A wide range of crops are grown with state- controlled cotton and wheat representing approximately 39% and 26% of the total cropped area respectively. Approximately half the wheat area, after harvest, is used to grow short-term ‘secondary’ crops, and virtually all the non-wheat land which is not occupied by cotton or perennial crops is also used to grow crops of the farmers’ choice.

Lahmeyer International in association with InfoCapital Group page 70

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

For the overall ABIS approximately 10% of the irrigated area is covered by perennial crops (grapes, mulberry, and other fruit). Overall cropping intensity is approximately 108%.

453. Cropping patterns and intensities vary between the schemes within ABIS. If account is taken of the detailed crop breakdowns of ‘secondary’ crops and of the large area described as ‘homestead’, vegetables occupy approximately 18% of the overall cropped area.4 Fodder crops,5 lucerne, and maize silage, occupy approximately 16% of the cropped area.

454. Crop yields. The yields of seed cotton (approximately 3.2 tons/ha) and wheat (approximately 6.0 tons/ha) in the Bukhara Region are among the highest yielding cotton in the country. This indicates that the natural soil fertility levels are better than the official classification might suggest and it is possible that the average wheat yield understates the actual yield. For vegetables, fruit and fodder, yield levels appeared to be similar to those achieved in other areas of the country.

455. Salinity and waterlogging. Care must be taken to distinguish between those areas where no significant salinity, water-logging or water shortage constraints exist and those which have such problems. In general terms about 12% of the total area is classified as having unsatisfactory cropping potential due to salinity, high groundwater, or water shortage. Interventions under Loan 2245/2246-UZB Land Improvement Project6 and the Government funded Amelioration Programme are being implemented and these should soon be having an impact, in both the ‘with’ and ‘without-project’ situations. The impact has been incorporated in the analysis in terms of the reduction in the percentage of cropped area which is affected by poor growing conditions. In the near future this is anticipated to decrease to around 5%.

456. Crop budgets in financial and economic terms were prepared for wheat, cotton, cucumbers, maize silage and mature peaches. The latter three crops were selected as representatives of their crop category after having calculated the returns for a range of the main crops within each crop category, and weighting them according to cropped area. Table 14 summarizes the estimated financial returns per hectare for normal and marginal lands.

Table 14: Financial Returns. UZS’000/ha. 2012 Land condition Crop Good Marginal Cotton 448 205 Wheat 807 378 Vegetables 2,418 1,073 Fruit 2,283 1,010 Fodder 2,173 1,056 Source: Consultant’s estimates.

4 Predominantly cabbage, carrots, cucumbers, melons, onions, potatoes, and tomatoes. 5 Comprising mainly of short- and long-term pasture. 6 ADB. 2007. Report and Recommendation of the President to the Board of Directors on Proposed Loan to the Republic of Uzbekistan for Land Improvement Project. Manila.

Lahmeyer International in association with InfoCapital Group page 71

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

457. The crop budgets which are presented in detail in the Financial and Economic Annex of the PPTA Final Report, provide details of inputs used and unit costs and values. Cotton and wheat production are heavily mechanized, except in regard to the cotton harvest, which is usually performed manually. No costs for the government provided irrigation water have been included, as this is free of charge to the farmer. The economic costs of water are included elsewhere in the analysis. Land is allocated free of charge to farmers, and in the most part is not owned by the farmer.

458. Whilst financial returns to cotton and wheat are rather low it should be borne in mind that the water and land are provided at no cost to the farmer, that mechanization facilities are provided at subsidized rates and the farmer is given the opportunity to utilize approximately one third of the land to grow crops of his own choice. Returns from the main crops of vegetables and fruit appear to be very attractive. Whilst in the analysis a financial value has been placed on fodder, in reality most of these crops are consumed by the farmers’ own livestock; large numbers of sheep, goats and cattle are found in the area.

459. The net economic returns per hectare of cotton are considerably higher than the financial returns, reflecting the fact that Government purchases all the cotton at prices 7 which it determines. For wheat and the other crops, the differences between the financial and economic returns are relatively small.

460. Farm size. It is estimated that there are approximately 2,570 micro-farms (smaller than 50 ha); 1,100 small farms (50 ha to 100 ha); and up to 25 large farms (exceeding 100 ha) in the Study Area. Average farm size is thus around 67 ha. For analysis purposes, it has been assumed that three typical farm sizes would be 50 ha, 100 ha and 200 ha. The number of farms has reduced dramatically over recent years. In 2007 there were over 15,000 holdings in Bukhara Region, and currently there are fewer than 4,000.

461. ‘Without-project’ irrigation scheme specific scenarios. For most farms in the Karakul Bazar irrigation scheme, the 16,000 ha scheme which gets first call on the water being pumped from the Khamza 1and Khamza 2 pump stations, it is likely that it will be many years before their supplies will be reduced. The Stage 2 pumps supplying this area are in good condition, and their replacement is not envisaged under this project. For individual farms within the Kuyu Mazar and Kizil Tepa irrigation schemes, the impact will depend on how the declining water volume is allocated between the two schemes, the rate at which the Stage 2 pumps deteriorate and the location of the farm. It is likely that farms located near the heads of the main canals feeding the irrigation areas, in Kizil Tepa, Vobkent, Gidjuvan, Kagan and Bukhara districts will be least impacted whilst those in the more remote districts will be the most severely impacted. Whilst it is envisaged that there would be attempts to spread the water, the realistic scenario is one where the tail- end farms would cease to function and the problem would gradually spread up-stream towards the main irrigation canal outlets as the water supplies diminish. With so little rainfall, the opportunities for farmers to adjust their cropping patterns in the face of declining irrigation supplies are virtually nil. With the assumptions applied, in the total failure scenario, all cropping would cease by around year 11. With the gradual decline scenario approximately 20% of the area would remain productive up to and beyond Year 25. Whatever scenario were to apply in reality for those farmers who, in the ‘without-

7 Half of the wheat crop is purchased by the government.

Lahmeyer International in association with InfoCapital Group page 72

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report project’ condition lose their water supply, the impact of the Project would be to save them from total loss. The annual benefit gained would not only be the value of the crop saved, but also the safeguarding of any investments such as those made in perennial crop establishment, in land improvement, and in farm-level irrigation and on-farm access infrastructure improvement.

462. Returns per average farmed hectare. The likely average return per hectare for lands cropped in the three Study Area irrigation schemes is given in Table 15. It is assumed that by the time the Project commences, approximately 95% of the irrigated area will be capable of producing good crops and around 5% of the area will be of marginal productivity. Although there are some differences in cropping patterns between irrigation schemes, the calculations indicate that average returns/ha are very similar and average out at around SUM1,370,000 per hectare (around $500/ha at market exchange rates).

Table 15: Financial returns/ha. ‘SUM'000/ha ‘Without’ and ‘With-Project’ situations Cotton Wheat Vegetables Fodder Perennial Total Good Land: Return/ha 448 807 2,418 2,173 2,283 Kizil Tepa 157 206 429 330 220 1,341 Kuyu Mazar 172 176 401 353 242 1,344 Karaul Bazar 153 305 160 610 25 1,253 Average 163 201 399 359 215 1,336 Marginal Land: Return/ha 205 378 1,073 1,056 1,010 Kizil Tepa 4 5 10 8 5 32 Kuyu Mazar 4 4 9 9 6 32 Karaul Bazar 4 8 4 15 1 30 Average 4 5 9 9 5 32 All Land: Kizil Tepa 161 211 439 338 225 1,373 Kuyu Mazar 177 180 410 362 248 1,376 Karakul Bazar 156 313 163 625 26 1,284 Average 167 205 408 368 220 1,368 Source: Consultant’s estimates.

463. Net Farm Returns. No differences in cropping patterns between holding sizes have been incorporated in the analysis and the net annual returns for the three selected indicator holding sizes are presented in Table 16 below. The data presented apply to both the ‘with’ and ‘without-project’ situations as no changes in the current cropping patterns or productivity are assumed in the ‘with-project’ condition. Farms will operate similarly until the water fails to reach the farm, at which point all production will cease. Experiences on individual farms will naturally vary, depending on the rate in decline of water supply. Once the supply starts to decline it is anticipated complete farm failure would ensue over a short period.

Lahmeyer International in association with InfoCapital Group page 73

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Table 16: Average financial returns per farm UZS '000/farm ‘Without’ and ‘With-Project’ situations Farm size (ha) 50 100 200 Kizil Tepa 68,663 137,325 274,651 Kuyu Mazar 68,803 137,605 275,211 Karaul Bazar 64,194 128,388 Average 68,403 136,805 274,893 Source: Consultant’s estimates.

464. Labour use. Despite the heavy mechanization, because of the nature of the crops grown there is a substantial requirement for manual labor, with a weighted average utilization per hectare for the overall cropping pattern of around 55 workdays per hectare/year, including 13 workdays used for cotton picking. A daily wage of SUM12,000 has been used for general labor and SUM15,000 (net of tax) for cotton picking. Thus average annual labor cost per cropped ha is around SUM700,000/ha. In the ‘without- project’ situation, for every hectare falling into disuse this would be the revenue lost to the local economy. On a weighted average basis the daily cost of labor is approximately SUM12,700/day.

465. Overall Financial Impact. Table 17 summarizes the anticipated overall financial impact the Reduced Cost Option investment would have over a 25 year period, based on an assumed water supply decline scenario that pumps would gradually, rather than catastrophically, fail. It indicates that over a 25 year period, the net financial farm income saved would be in the order of $1.25 billion.

466. With regard to manual labor, the total value of wages saved as a consequence of project implementation would be of the order of $636 million, or 105 million workdays.

Lahmeyer International in association with InfoCapital Group page 74

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Table 17: Total With-Project Saved Financial Farm Returns & Manual Wages (Reduced Cost Option) Year 1 5 10 15 20 25 Total Farm returns 25 years Irrigated area WOP ha '000 241 213 154 111 77 50 WOP Return/ha/yr UZS million 1,37 1,37 1,37 1,37 1,37 1,37 Total WOP Return/yr UZS billion 330 291 211 152 105 69 4,703 Irrigated area WP ha '000 241 213 217 217 217 217 WP Return/ha/yr UZS million 1,37 1,37 1,37 1,37 1,37 1,37 Total WP Return/yr UZS billion 330 291 296 296 296 296 7,492 Net WP saved income/yr UZS billion - - 85 144 191 228 2,789 Net WP saved income/yr US$ million - - 41 69 91 109 1,331 Labour (manual) workdays WOP Labour use million 13 12 8 6 4 3 189 WOP Labour wages UZS/yr 13 13 13 13 13 13 13 Total WOP wages UZS billion 168 149 108 78 54 35 2,401 workdays WP Labour use million 13 12 12 12 12 12 301 WP Labour wages UZS/yr 13 13 13 13 13 13 13 Total WP wages UZS billion 168 149 151 151 151 151 3,825 Net WP saved wages UZS billion - - 43 73 98 116 1,424 Net WP saved wages/yr US$ million - - 21 35 47 55 679 Source : Consultants Estimates

E. Economic Analysis

467. Capital Costs. The financial base capital costs for the proposed Project were mostly computed in $ terms based on price quotations from foreign equipment suppliers. For those components which were originally derived in SUM terms, these were converted to economic values by making appropriate adjustments. A standard conversion factor was applied to the local currency portion of all components. Physical contingencies were then added and the prices converted into economic prices, as discussed previously. Cost inflation contingencies, financing charges and import duties and taxes on foreign sourced inputs were not included at this stage.

468. Most of the total capital cost is related to the construction/rehabilitation of five pump stations and associated management consultancy, whilst a remaining small portion (approximately 2.5%) of the total base cost is concerned with the rehabilitation of the main canal system and a further (less than 1%) provision of facilities to develop water saving initiatives.

469. Implementation period. In the analysis, it has been assumed that all major works would be completed during a six year implementation period. It is anticipated that the pumps would become fully operational in the seventh year after the construction program commences.

Lahmeyer International in association with InfoCapital Group page 75

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

470. Recurrent Costs. Schedules were prepared for the ‘without’ and ‘with-project’ situations. Five separate elements were identified as follows

(i) Energy costs, (ii) Maintenance of Pumps and Pump Stations, (iii) Other operation and maintenance (O&M) for ABIS, excluding the above, and (iv) Periodic Pump Maintenance (in with-project situation only). (v) Rehabilitation/replacement of discharge pipes, not funded under the loan.

471. In the ‘without-project’ situation, for the one where the pumps would gradually fail to operate completely it is assumed that maintenance costs would reduce as the number of working pumps is also reduced. Where it was assumed that the pumps would gradually decline in operating capability it has been assumed that current maintenance costs would increase over time. A 5% annual increase in maintenance costs has been assumed.

472. Once the new pumps commence operating in the ‘with-project situation’, maintenance costs would rise substantially over existing levels, as a consequence of the requirement to service much more sophisticated equipment than has been the case in the past. Overall current annual non-energy O&M costs for the pump stations, are, at market exchange rates, approximately $1.2 million. For the ‘with-project’ they are anticipated to rise to around $4.5 million; exclusive of any contributions towards the capital cost of repairs and/or replacement of discharge pipes to be funded by Government.

473. In the ‘without-project’ situation there would be a reduction in Mwh used per year as the pumps become less capable of pumping, with the rate of decline depending on the assumed decline scenario. In the ‘with-project’ situation there would be an immediate reduction in power consumption once the new more efficient pumps become operational. These savings would substantially exceed the relatively small increases in additional maintenance costs. Two adjustments were made to the long term schedule of ‘with- project’ power consumption. After ten years of operation it has been assumed that there would be slight reductions in overall pump set efficiency and power consumption would consequently increase. It was also assumed that for three years, commencing in year 7, there would be an annual improvement in overall system efficiency of 1.5% resulting from several of the improvements which the Project would have introduced, including the rehabilitation of the ABMC structures and the establishment of DSS and SCADA systems. Present annual energy costs for the whole Study Area are estimated, at official exchange rates, at around $ 81 million, based on current tariffs. Once the new pumps are installed the equivalent cost should be approximately $64 million.

474. Agricultural Benefits. Apart from the energy saving benefits mentioned above, the main project benefit is that most of the area’s present status quo is maintained and most farmers would avoid the potential disaster of being deprived of all production capability. With such low rainfall, there is little prospect of farmers making a living once the irrigation supply ceases. No project derived impacts have been assumed to improve productivity beyond the levels currently being achieved, neither have any domestic, municipal, and industrial water benefits been included. The current net annual economic

Lahmeyer International in association with InfoCapital Group page 76

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report value of agricultural production from the Study Area is estimated at $246 million at market exchange rates.

475. In the ’without-project’ situations, depending on the pump decline assumption, the associated declines in cropped area were estimated and by applying crop budgets (in economic prices) schedules of overall net income for the Project Area were calculated. In the ‘with-project’ situation it is assumed that the net income would remain the same as at present, once the pumps become fully operational, except in those areas currently served by pumps which would not be rehabilitated under the Project.

476. Based on the derived capital costs economic analyses were carried out and the base case results were as follows, for the two options:

(i) Where it is assumed that the Khamza pumps would totally fail by Year 11 (after project commencement), the economic internal rate of return (EIRR) was 18%, (ii) Where it is assumed that pumps would gradually decline (base case), with only 20% of the currently cropped area functioning (within the Study Area) in Year 25 after project commencement the EIRR was 12%.

477. A number of sensitivity analyses were also carried out and the results of these are presented in Table 18.

Table 18: EIRR Summary (%) Case Gradual Pump Total Pump Decline Scenario Failure Scenario (base case) Base Case 12.2 18.4 Sensitivity 1 – 10% increased capital costs 10.7 17.5 Sensitivity 2 – 20% increased capital cost 9.4 16.6 Sensitivity 3 – 3% annual decline in pumping capacity 7.0 na Sensitivity 4 – 4% annual decline in pumping capacity 9.9 na Sensitivity 5 – 1 year delay in onset of pump decline 11.1 na Sensitivity 6 – 2 year delay in onset of pump decline 9.9 na Sensitivity 7 – 3 year delay in onset of pump decline 8.6 na Sensitivity 8 – 10% increase in seed cotton price 13.3 19.7 Sensitivity 9 – 10% reduction in seed cotton price 11.0 16.9 Sensitivity 10 – energy cost US$ 0.075/kwh 11.0 16.5 Sensitivity 11 – energy cost US$ 0.10/kwh 9.4 13.9 na = not applicable.

Lahmeyer International in association with InfoCapital Group page 77

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Appendix 1

Protocol of Joint Meeting on Agreement of Design Criteria for Design of the Khamza New Pump Station under Amu-Bukhara Irrigation System Rehabilitation Project

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Appendix 2

Monthly Pump Records – Khamza 1 Pump Station and Khamza Auxiliary Pump Station

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Discharge from the Khamza 1 Pump Station and Khamza Auxiliary Pump Station (2006 to 2012)

Pumped Volume, Mm3 Month 2006 2007 2008 2009 2010 2011 2012 Jan 25.3 56.5 33.3 56.5 65.7 50.7 53.5 Feb 40 36 48.5 61.2 49.4 53.9 38.5 March 60.2 49.8 35.6 52.5 42.5 55.2 41.1 Apr 36.7 54.3 39.4 42.2 63.6 23.7 100.8 May 75.2 62.5 70.7 76.9 71.2 81.9 100.0 June 129.5 116.8 144 117.4 110.2 113.9 128.1 Khamza 1 PS July 142.9 147.4 141 150.9 164.3 103.2 120.5 Aug 147.3 137.1 131.5 120.1 131.5 136.9 76.2 Sep 98.1 86.2 87.7 52.35 54.3 89.7 42.1 Oct 74.7 71.1 57.6 79.6 29.56 46 32.0 Nov 70.2 68.4 67.8 56.9 71.6 38.2 35.9 Dec 37 29.6 35.1 39 63 49.4 48.6 Total 934.4 915.7 892.2 905.55 916.86 842.7 817.3 Jan 2.3 Feb 0.1 March Apr 0.84 0.94 30.1 28.9 May 27.7 1.2 5.9 45.8 1.8 13.3 June 17 21.9 49.9 41.5 8.4 28.4 Khamza Aux. July 40.6 50.7 37.5 18.9 53.6 3.6 20.8 PS Aug 40.5 23.21 22.6 16.8 40.84 15.8 4.4 Sep 15 7.76 13.7 2.6 2.2 Oct 0.53 23.7 5.98 Nov 4.5 11.9 Dec Total 145.8 140.26 130.4 45.22 211.84 35.8 100.4 Source: MAWR (Tashkent), 2013

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Appendix 3

Crop Irrigation Norms per Hydro-module (m3/ha)

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Uzgipromeliovodkhoz m3/ha

Vegetation period Non-Vegetation period Total Irrigation Irrigation Non- Crop Dates III IV V VI VII VIII IX X Dates II III IV IX X XI XII Veg. Year III Hydromodule 13.III- 25.IX- Winter wheat 20.V 289 831 580 5.XI 340 1380 280 2000 3700 W. wheat with 13.III- 25.IX- secondary 20.V 289 831 580 1680 1659 1596 5.XI 340 1380 280 2000 8635 16.V- 21.II- Cotton 15.IX 560 1470 2310 2030 630 10.IV 360 1170 270 1800 8800 Vegetables, melons, potatoes + homestead land 1.IV-5.X 1772 1395 1767 2325 1860 1395 186 1.II-31.III 360 1170 270 1800 12500 1.IV- 11.XI- Fodder and alfalfa 25.IX 570 1235 1995 2375 2090 1235 20.XII 1050 1050 2100 11600 Orchard s and other 26.IV- 11.XI- trees 15.IX 130 975 1560 1820 1560 455 20.XII 1050 1050 2100 8600 11.V- 11.XI- Fallow lands 31.VIII 504 972 1152 972 20.XII 360 1170 270 1800 5400 IV Hydromodule 11.III- 28.IX- Winter wheat 20.V 288 942 570 5.XI 160 1300 240 1700 3500 W. wheat with 11.III- secondary 10.X 288 942 570 1712 1691 1626 160 1300 240 1700 8529 21.V- Cotton 10.IX 390 1365 2275 2015 455 1.II-31.III 920 1380 2300 8800 Vegetables, melons, potatoes + homestead land 16.IV-5.X 1658 1204 1634 2236 1978 1118 172 1.II-31.III 920 1380 2300 12300 6.IV- 6.XI- Fodder and alfalfa 25.IX 522 1131 1827 2262 2001 957 20.XII 1210 990 2200 10900 Orchard s and other 6.XI- trees 1.V-10.IX 900 1440 1740 1500 420 20.XII 1210 990 2200 8200 11.V- Fallow lands 31.VIII 462 891 1056 891 1.II-31.III 920 1380 2300 5600

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Vegetation period Non-vegetation period Total Irrigation Irrigation Non- Crop Dates III IV V VI VII VIII IX X Dates II III IV IX X XI XII Veg. Year V Hydromodule 15.III- 26.IX- Winter wheat 20.V 256 754 590 6.XI 250 1360 190 1800 3400 W. wheat with 15.III- secondary 20.V 256 754 590 1568 1548 1500 250 1360 190 1800 8016 26.V- 11.II- Cotton 10.IX 310 1364 2232 1922 372 31.III 1040 1560 2600 8800 Vegetables, melons, potatoes + 21.IV- 11.II- homestead land 30.IX 1464 1148 1640 2214 1968 1066 31.III 1040 1560 2600 12100 11.IV- 6.XI- Fodder and alfalfa 20.IX 336 1092 1848 2268 2016 840 20.XII 1375 1125 2500 10900 Orchard s and other 6.XI- trees 6.V-10.IX 741 1425 1710 1482 342 20.XII 1375 1125 2500 8200 16.V- 11.II- Fallow lands 25.VIII 384 928 1088 800 31.III 1040 1560 2600 5800 VI - VII Hydromodule 11.III- 26.IX- Winter wheat 20.V 53 1208 840 30.X 790 1210 2000 4101 W. wheat with 11.III- 26.IX- secondary 20.V 53 1208 840 1280 1264 1216 30.X 790 1210 2000 7861 Cotton 1.VI-5.IX 1200 1950 1700 150 6.II-25.III 2000 2000 4000 9000 Vegetables, melons, potatoes + 16.IV- homestead land 30.IX 1200 938 1407 1876 1675 804 6.II-25.III 2000 2000 4000 11900 21.IV- 1.XI- Fodder and alfalfa 15.IX 138 897 1587 2001 1725 552 20.XII 1260 840 2100 9000 Orchard s and other 1.XI- trees 11.V-5.IX 517 1222 1457 1316 188 20.XII 1260 840 2100 6800 21.V- 1.XI- Fallow lands 25.VIII 208 806 910 676 20.XII 2000 2000 4000 6600

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Appendix 4

Weighted Average Irrigation Norms by District (m3/ha)

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Vegetation period Non-vegetation period Total Total Non- Crop III IV V VI VII VIII IX X Veg. II III IV IX X XI XII veg. Year Alat Winter wheat 143 1058 733 0 0 0 0 0 1934 0 0 0 550 1260 88 0 1898 3832 W. wheat with secondary 143 143 143 143 1058 733 0 1427 1409 1358 0 6128 0 0 0 550 1260 88 Cotton 0 0 144 1268 2075 1810 258 0 5554 1581 1783 0 0 0 0 0 3364 8918 Vegetables, melons, potatoes + homestead land 0 0 0 0 1347 1036 1502 2020 1798 922 34 8658 1581 1783 0 0 0 0 Fodder and alfalfa 0 256,4 985 1690 2110 1842 694 0 7578 0 0 0 0 0 1275 931 2206 9783 Orchard s and other trees 0 0 0 0 0 641 1309 1567 1388 267 0 5171 0 0 0 0 0 1275 Fallow lands 0 0 296 849 977 745 0 0 2867 1581 1783 0 0 0 0 0 3364 6231 Weighted average 36 570 574 1030 1728 1541 574 7 6060 970 1094 0 140 320 193 124 2841 8901 Bukhara Winter wheat 230 823 624 0 1230 0 0 0 2907 0 0 0 332 1341 170 0 1843 4750 W. wheat with secondary 230 230 230 230 823 624 0 2057 1390 1468 0 6593 0 0 0 332 1341 170 Cotton 0 0 286 1349 2184 1871 361 0 6051 1122 1592 21 0 0 0 0 2734 8785 Vegetables, melons, potatoes + homestead land 0 0 0 0 1451 1138 1617 2218 1932 1055 14 9424 1122 1592 21 0 0 0 Fodder and alfalfa 0 326 1076 1823 1801 1963 830 0 7820 0 0 0 0 0 1334 1080 2414 10233 Orchard s and other trees 0 0 0 0 10 728 1407 1195 1505 329 0 5174 0 0 0 0 0 1334 Fallow lands 0 0 369 914 215 841 0 0 2339 1122 1592 21 0 0 0 0 2734 5073 Weighted average 46 464 634 1170 1918 1640 644 3 6517 674 956 12 66 265 303 218 2495 9012

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Vegetation period Non-vegetation period Total Total Non- Crop III IV V VI VII VIII IX X Veg. II III IV IX X XI XII veg. Year Vabkent Winter wheat 268 782 586 0 0 0 0 0 1636 0 0 0 282 1367 222 0 1872 3508 W. wheat with secondary 268 268 268 268 782 586 0 1608 1588 1535 0 6367 0 0 0 282 1367 222 Cotton 0 0 400 1402 2260 1961 465 0 6488 795 1419 97 0 0 0 0 2312 8800 Vegetables, melons, potatoes + homestead land 0 0 0 0 1575 1237 1686 2254 1929 1185 67 9932 795 1419 97 0 0 0 Fodder and alfalfa 0 420 1144 1901 2307 2043 982 0 8796 0 0 0 0 0 1258 1098 2356 11152 Orchard s and other trees 0 0 0 0 47 825 1474 1750 1510 383 0 5988 0 0 0 0 0 1258 Fallow lands 0 0 427 944 1111 862 0 0 3344 795 1419 97 0 0 0 0 2312 5656 Weighted average 78 550 676 1075 1769 1555 677 13 6391 475 848 58 82 396 205 123 2188 8580 Gijduvan Winter wheat 224 835 622 0 0 0 0 0 1681 0 0 0 339 1318 167 0 1823 3504 W. wheat with secondary 224 224 224 224 835 622 0 1519 1499 1450 0 6148 0 0 0 339 1318 167 Cotton 0 0 281 1330 2168 1876 358 0 6013 1119 1570 23 0 0 0 0 2713 8726 Vegetables, melons, potatoes + homestead land 0 0 0 0 1439 1124 1593 2143 1887 1041 24 9252 1119 1570 23 0 0 0 Fodder and alfalfa 0 329 1061 1795 2206 1950 823 0 8163 0 0 0 0 0 1303 1052 2355 10518 Orchard s and other trees 0 0 0 0 11 723 1387 1659 1445 326 0 5551 0 0 0 0 0 1303 Fallow lands 0 0 365 899 1050 789 0 0 3103 1119 1570 23 0 0 0 0 2713 5816 Weighted average 39 531 642 1176 1844 1621 624 6 6483 761 1068 16 59 231 219 153 2506 8989

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Vegetation period Non-vegetation period Total Total Non- Crop III IV V VI VII VIII IX X Veg. II III IV IX X XI XII veg. Year Kagan Winter wheat 139 1016 734 0 0 0 0 0 1889 0 0 0 562 1273 80 0 1916 3805 W. wheat with secondary 139 139 139 139 1016 734 0 1402 1384 1336 0 6011 0 0 0 562 1273 80 Cotton 0 0 131 1269 2069 1794 244 0 5507 1594 1814 0 0 0 0 0 3408 8916 Vegetables, melons, potatoes + homestead land 0 0 0 0 1312 1027 1505 2019 1799 915 0 8576 1594 1814 0 0 0 0 Fodder and alfalfa 0 222 979 1697 2114 1848 674 0 7534 0 0 0 0 0 1308 960 2269 9803 Orchard s and other trees 0 0 0 0 0 612 1308 1564 1386 253 0 5123 0 0 0 0 0 1308 Fallow lands 0 0 282 858 985 728 0 0 2854 1594 1814 0 0 0 0 0 3408 6262 Weighted average 39 462 557 1001 1634 1447 492 0 5632 814 927 0 156 354 299 203 2754 8385 Karakul Winter wheat 155 985 715 0 0 0 0 0 1855 0 0 0 523 1285 98 0 1906 3762 W. wheat with secondary 155 155 155 155 985 715 0 1428 1410 1361 0 6054 0 0 0 523 1285 98 Cotton 0 0 163 1285 2093 1814 269 0 5625 1499 1767 9 0 0 0 0 3275 8900 Vegetables, melons, potatoes + homestead land 0 0 0 0 1342 1051 1527 2048 1818 945 7 8738 1499 1767 9 0 0 0 Fodder and alfalfa 0 245 999 1722 2138 1872 709 0 7684 0 0 0 0 0 1306 979 2285 9970 Orchard s and other trees 0 0 0 0 4 637 1328 1587 1401 269 0 5225 0 0 0 0 0 1306 Fallow lands 0 0 300 868 1001 744 0 0 2912 1499 1767 9 0 0 0 0 3275 6188 Weighted average 38 552 568 1045 1665 1470 500 1 5840 963 1136 6 128 314 172 111 2829 8669

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Vegetation period Non-vegetation period Total Total Non- Crop III IV V VI VII VIII IX X Veg. II III IV IX X XI XII veg. Year Peshkun Winter wheat 255 773 595 0 0 0 0 0 1623 0 0 0 273 1359 196 0 1827 3450 W. wheat with secondary 255 255 255 773 595 0 1574 1554 1504 0 6255 0 0 0 273 1359 196 0 Cotton 0 0 331 1372 2234 1929 396 0 6263 985 1526 31 0 0 0 0 2541 8805 Vegetables, melons, potatoes + homestead land 0 0 0 1493 1171 1649 2219 1949 1097 21 9600 985 1526 31 0 0 0 0 Fodder and alfalfa 0 358 1104 1859 2274 2018 878 0 8491 0 0 0 0 0 1335 1110 2445 10936 Orchard s and other trees 0 0 0 15 762 1436 1717 1487 351 0 5768 0 0 0 0 0 1335 1110 Fallow lands 0 0 394 930 1091 817 0 0 3232 985 1526 31 0 0 0 0 2541 5773 Weighted average 61 482 621 1113 1856 1637 654 4 6429 624 967 19 66 327 215 139 2357 8786 Romitan Winter wheat 243 799 608 0 0 0 0 0 1650 0 0 0 295 1348 182 0 1826 3476 W. wheat with secondary 243 243 243 799 608 0 1557 1537 1487 0 6231 0 0 0 295 1348 182 0 Cotton 0 0 304 1358 2216 1914 374 0 6167 1067 1564 18 0 0 0 0 2649 8815 Vegetables, melons, potatoes + homestead land 0 0 0 1468 1149 1630 2196 1939 1068 16 9467 1067 1564 18 0 0 0 0 Fodder and alfalfa 0 340 1087 1837 2254 1998 846 0 8363 0 0 0 0 0 1341 1095 2436 10799 Orchard s and other trees 0 0 0 8 743 1418 1698 1475 339 0 5682 0 0 0 0 0 1341 1095 Fallow lands 0 0 380 921 1078 804 0 0 3182 1067 1564 18 0 0 0 0 2649 5831 Weighted average 58 453 590 1095 1820 1604 605 3 6230 683 1002 11 70 321 206 133 2427 8657

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Vegetation period Non-vegetation period Total Total Non- Crop III IV V VI VII VIII IX X Veg. II III IV IX X XI XII veg. Year Jondor Winter wheat 213 872 645 0 0 0 0 0 1730 0 0 0 365 1321 151 0 1837 3567 W. wheat with secondary 213 213 213 213 872 645 0 1514 1495 1446 0 6186 0 0 0 365 1321 151 Cotton 0 0 246 1327 2172 1879 328 0 5952 1248 1645 0 0 0 0 0 2893 8845 Vegetables, melons, potatoes + homestead land 0 0 0 0 1420 1105 1587 2139 1902 1011 14 9178 1248 1645 0 0 0 0 Fodder and alfalfa 0 306 1051 1787 2207 1949 784 0 8084 0 0 0 0 0 1335 1049 2385 10469 Orchard s and other trees 0 0 0 0 0 703 1380 1655 1446 313 0 5498 0 0 0 0 0 1335 Fallow lands 0 0 350 897 1045 779 0 0 3072 1248 1645 0 0 0 0 0 2893 5965 Weighted average 40 411 576 1150 1835 1615 557 2 6186 783 1033 0 68 246 276 195 2601 8787 Shafirkan Winter wheat 224 850 634 0 0 0 0 0 1708 0 0 0 364 1336 170 0 1869 3577 W. wheat with secondary 224 224 224 224 850 634 0 1533 1514 1463 0 6219 0 0 0 364 1336 170 Cotton 0 0 294 1351 2193 1899 373 0 6109 1106 1578 44 0 0 0 0 2727 8837 Vegetables, melons, potatoes + homestead land 0 0 0 0 1465 1149 1618 2170 1897 1071 30 9401 1106 1578 44 0 0 0 Fodder and alfalfa 0 338 1079 1824 2236 1975 851 0 8303 0 0 0 0 0 1301 1061 2362 10665 Orchard s and other trees 0 0 0 0 21 738 1410 1681 1464 332 0 5646 0 0 0 0 0 1301 Fallow lands 0 0 371 913 1066 805 0 0 3155 1106 1578 44 0 0 0 0 2727 5882 Weighted average 52 504 650 1120 1872 1658 708 6 6569 636 907 25 85 313 288 203 2457 9026

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Vegetation period Non-vegetation period Total Total Non- Crop III IV V VI VII VIII IX X Veg. II III IV IX X XI XII veg. Year Karaulbazar Winter wheat 289 831 580 0 0 0 0 0 1700 0 0 0 340 1380 280 0 2000 3700 W. wheat with secondary 289 289 289 289 831 580 0 1680 1659 1596 0 6635 0 0 0 340 1380 280 Cotton 0 0 560 1470 2310 2030 630 0 7000 360 1170 270 0 0 0 0 1800 8800 Vegetables, melons, potatoes + homestead land 0 0 0 0 1772 1395 1767 2325 1860 1395 186 10700 360 1170 270 0 0 0 Fodder and alfalfa 0 570 1235 1995 2375 2090 1235 0 9500 0 0 0 0 0 1050 1050 2100 11600 Orchard s and other trees 0 0 0 0 130 975 1560 1820 1560 455 0 6500 0 0 0 0 0 1050 Fallow lands 0 0 504 972 1152 972 0 0 3600 360 1170 270 0 0 0 0 1800 5400 Weighted average 114 498 697 938 1662 1483 769 11 6172 171 555 128 134 544 248 138 1918 8090 Kiziltepa Winter wheat 197 971 669 0 0 0 0 0 1837 0 0 0 408 1290 142 0 1840 3678 W. wheat with secondary 197 197 197 197 971 669 0 1517 1498 1445 0 6297 0 0 0 408 1290 142 Cotton 0 0 234 1310 2151 1878 327 0 5899 1318 1646 5 0 0 0 0 2969 8869 Vegetables, melons, potatoes + homestead land 0 0 0 0 1441 1099 1561 2107 1869 999 58 9133 1318 1646 5 0 0 0 Fodder and alfalfa 0 332 1040 1755 2177 1913 786 0 8002 0 0 0 0 0 1277 983 2260 10262 Orchard s and other trees 0 0 0 0 2 719 1363 1635 1432 316 0 5468 0 0 0 0 0 1277 Fallow lands 0 0 351 875 1018 790 0 0 3034 1318 1646 5 0 0 0 0 2969 6003 Weighted average 62 505 584 896 1606 1432 613 7 5706 708 885 3 129 408 232 144 2509 8215

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Vegetation period Non-vegetation period Total Total Non- Crop III IV V VI VII VIII IX X Veg. II III IV IX X XI XII veg. Year Karmana Winter wheat 190 1053 682 0 0 0 0 0 1925 0 0 0 422 1263 140 0 1825 3750 W. wheat with secondary 190 190 190 190 1053 682 0 1532 1513 1455 0 6426 0 0 0 422 1263 140 Cotton 0 0 228 1296 2140 1884 328 0 5876 1369 1638 0 0 0 0 0 3007 8883 Vegetables, melons, potatoes + homestead land 0 0 0 0 1468 1093 1540 2086 1852 987 100 9127 1369 1638 0 0 0 0 Fodder and alfalfa 0 362 1034 1727 2153 1886 789 0 7951 0 0 0 0 0 1231 928 2158 10110 Orchard s and other trees 0 0 0 0 0 741 1349 1622 1423 324 0 5459 0 0 0 0 0 1231 Fallow lands 0 0 356 856 995 802 0 0 3009 1369 1638 0 0 0 0 0 3007 6016 Weighted average 66 604 618 898 1645 1484 657 15 5988 676 808 0 146 436 247 149 2461 8449

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Appendix 5

Pumping Requirements for Khamza New Pump Station (m3/ha)

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

KHAMZA NEW PUMP STATION

CURRENT CROPPING PATTERN

ESTIMATED PUMPING REQUIREMENT FOR IRRIGATION WATER (Mm3)

District II III IV V VI VII VIII IX X XI XII Total

Vabkent 5.73 11.17 7.33 8.15 12.96 21.34 18.76 9.15 4.94 2.48 1.48 103.49

Peshkun 6.65 10.95 5.35 6.62 11.85 19.77 17.44 7.66 3.53 2.29 1.48 93.60

Gijduvan 10.30 14.99 7.41 8.69 15.92 24.96 21.94 9.25 3.21 2.96 2.07 121.69

Shafirkan 9.32 14.07 7.75 9.53 16.41 27.44 24.31 11.62 4.66 4.23 2.97 132.33

Romitan 8.86 13.74 6.02 7.65 14.20 23.59 20.79 8.76 4.19 2.68 1.73 112.20

Kiziltepa 10.86 14.52 7.79 8.96 13.74 24.62 21.96 11.37 6.36 3.56 2.21 125.95

Karmana 2.55 3.29 2.27 2.33 3.38 6.20 5.59 3.02 1.70 0.93 0.56 31.83

Karaulbazar 1.23 4.82 4.51 5.02 6.76 11.97 10.68 6.51 4.00 1.79 0.99 58.27

Kagan 6.66 7.89 3.77 4.55 8.18 13.36 11.83 5.30 2.89 2.44 1.66 68.56

Bukhara 9.78 14.54 6.92 9.20 16.98 27.84 23.80 10.30 3.89 4.41 3.17 130.83

Jondor 4.73 6.47 2.48 3.47 6.94 11.07 9.74 3.77 1.50 1.67 1.18 53.01

Total 76.67 116.45 61.60 74.16 127.34 212.17 186.86 86.71 40.87 29.42 19.50 1031.74

Design Service Area = 72,000 ha

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Appendix 6

Geotechnical Investigation Report - Uzsuvloyiha Design Institute

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

GEOTECHNICAL CONDITIONS AT KHAMZA NEW PUMP STATION

INTRODUCTION

In December 2012, the Geological Department of Uzsuvloyiha Design Institute has implemented geotechnical investigations of Khamza New construction site under the Feasibility Study for construction of Khamza New PS in Bukhara Region. No new investigation were performed for the Khamza New PS. Instead, the information as available from following previously prepared investigation reports are used as the basis for the geotechnical investigation of the proposed Khamza new PS, which is located 300-500 m toward southwest side from Khamza I and Khamza auxiliary PS. a. In 1980 Uzsuvloyiha Design Institute has implemented geotechnical investigations for Detailed Design of Khamza auxiliary PS in Bukhara region. b. In 1984 the Institute has implemented geotechnical investigations for Detailed Design of drainage construction to divert ground waters away from existing Khamza 1 PS area.

GEOTECHNICAL CONDITIONS The proposed site is located at the western slope of Karakul plateau. The plateau consists of deposits formed in Neocene age, covered by Aeolian sands with a thickness from 0.5 to 4-5 m. Deposits of Neocene age are presented by weak sandstones with frequent interlayers and lenses of moderately stronger sandstones and siltstones with a thickness ranging between 0.1 m and 0.5 m. Gypsum content in the soils is to 1.1% of the air-dry soil. According to the operation manual of existing Khamza 1 PS, the elevation of ground water level is 190.5 m (as per 2012). Water is saline, with dissolved salts of sodium chloride & sulfate chloride (8.8-9.4 g/l).

The content of anions of SO4 is 3168 mg/l, HCO3 = 2.8 mg/eqv. Water is aggressive to Portland cement as per standard, GOST 10178-76. Therefore, suggested to use the Sulphate resisting cement as per recommendations of the local standard. Weak sandstone will be the base/sub-soil beneath the foundation of the pump station. Therefore required to confirm it during the detailed geotechnical investigation and design the foundation accordingly to consider the properties and bearing capacity of the existing subsoil. The density/unit weight (dry) of sandstone is 2.67-2.70 tons/m3. The submerged (with natural moisture) density/unit weight of sandstone is 1.59-2.0 tons/m3, while only the skeleton’s unit weight is 1.57-1.83 tons/m3. Unit weight of loose sandstone (with structural damage) is 1.25-1.30 tons/m3, and under compacted condition is 1.39-1.45 tons/m3.

Page 1 of 2

Sandstone filtration coefficient is 3 - 5 m/day. Nominal design pressure is 3 kgf/cm2. The present report does not include any test results for the physical and mechanical properties of the subsoil including the bearing capacity of subsoil beneath the foundation. Therefore, during the detailed design stage further detailed geotechnical investigations of the project site will be required. The final design of structure and its foundation will be based on the properties of subsoil and the recommendations included in the final geotechnical report.

SEISMICITY The proposed project site is located in a seismic zone. The seismicity of the proposed project site of Khamza New PS is assessed at 8 points (in accordance with K K 2.01.03- 96), which can be confirmed during the detailed design of the project. The category of sub- soil beneath footing is Class III with respect to seismic properties of the subsoil and shall be verified during the detailed geotechnical investigation of the site. The FS design of building and foundations of the pumping station is according to the local seismic code “KMK 2.01.03-96” of the country. The design should be verified during the detailed design phase. It is recommended to perform 3-D nonlinear structural analysis and design of the pumping station building as required by the seismic code during the detailed design phase.

Page 2 of 2 Uzsuvloyiha JSC

No. 01-25-69 18 January 2013

To: Mr. R. Mohammed

PPTA Team Leader

Your ref: KS/RAM/380087/GEN/

According to your letter, Uzsuvloyiha JSC has commenced a toposurvey at Khamza new construction site.

Regarding the projections of geotechnical conditions at the new pump station’s construction site we would like to inform that Uzsuvloyiha JSC confirms the submitted geotechnical report, as they are based on surveys conducted in this area in 1980 and 1984 with drilling of deep boreholes.

M. Najimov, Director

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Appendix 7

Topographical Survey Report - Uzsuvloyiha Design Institute

Lahmeyer International in association with InfoCapital Group

InfoCapital Group Topographical Survey

Introduction

The Republic of Uzbekistan (Uzbekistan) is located in Central Asia and its geographical co- ordinates are within 41 00 N and 64 00 E. Its territory extends for 950 km from north to south and for over 1,450 km from east to west, occupying a total area of some 447,400 km2. The Republic of Uzbekistan is divided into 12 administrative units/provinces, ‘wiloyatlar’ in Uzbek or ‘oblast’ in Russian, plus one autonomous republic of Karakalpakstan. The capital city of Uzbekistan is Tashkent, which lies within the coordinates of 41o 20’ N and 69o 10’ E. Uzbekistan is one of the only two doubly-land locked countries of the world, sharing borders with Turkmenistan to the south west, Afghanistan to the south, Tajikistan to the south-east, Kyrgyzstan to the north-east and Kazakhstan to the north and west. It generally lies between the two largest rivers of Central Asia, the Amu Darya and Syr Darya. These two roughly parallel rivers both have their headwaters in the mountains east of Uzbekistan and follow northwestern courses toward the Aral Sea Most of the central and western part of Uzbekistan is rolling dune sandy desert or steppe with the Kyzl Kum desert in the center and the autonomous region of Karakalpakstan, bounded by the Aral Sea and the sparsely populated Ustyurt Plateau, in the north-west. The south and east are dominated by the Tien Shan and Pamir-Alai mountain ranges.

Project Area The proposed project area of Khamza New Pump Station is located in Alat District of Bukhara Province. The significant part of the territory is occupied with desert pasture. The Bukhara Province is located within coordinates of 39o 48’ N and 69o 10’ E. The District of Alat is located on the west of Bukhara province, bordered with Turkmenistan and is about 430 Km southwest of Tashkent. The area is sharply characterized by continental climatic conditions, prolonged hot, dry summers with short periods of precipitation. The proposed Khamza New PS is to replace the existing Khamza 1 PS and Auxiliary Khamza. The existing Khamza 1 PS is located at PK 501+00, on a part of Amu-Bukhara canal (ABMK) and is designed to lift the water up to a height of about 45 meters. The building of existing Khamza 1 was built and constructed in 1965. The water intake into Amu-Bukhara pumping canal is from the right side of Amudarya River in the territory of Turkmenistan. The canal traverses from west to east direction and Khamza 1 along with Khamza Auxiliary is the first pump station on Amu-Bukhara Canal in the cascade of other pumping stations. The canal (ABMK) passes through the Barkhan sands of Kara Kum Desert from Uzbekistan national border to Khamza New PS. After the pump station, the canal passes through Karakul Desert.

The proposed Khamza new PS is located about 300-500 m from Khamza I and Khamza auxiliary PS on the southwest side.

Page 1 of 2 Topographic Survey The Design Institute has accomplished the survey for the Feasibility Study (FS) of Khamza New PS in February 2013. The following coordinate system was used: Projection: Gauss Kruger Datum: Pulkovo 1942, Zone 11 The survey consists of an area survey for the site of proposed building of pump station and a line survey along the center line of the traverse from the intake to the outlet. The area survey is on a total area of about 400 m x 300m and it shows the existing features and the spot elevations of the ground. The spot elevations are shown with reference to a permanent bench mark (Rp – 6 – 13g, elevation 205.762). A total of seven available permanent bench marks are marked and shown on other sheet with their elevations. A line survey along the center line of the traverse of proposed intake channel and discharge channel along with the building is accomplished comprising the cross sections at a longitudinal interval of 100 m and up to 40 m at each transverse side of center line. It is recommended to do a detailed area survey of the site before detailed design is undertaken including the area from the start of intake channel to the end of outlet channel. The detailed survey should show the complete topography of the area including the contours, elevations, existing features, the coordinates and any additional cross sections as required for the detailed design.

Page 2 of 2 ●9076 бр ●87.93

NjnjǕ

●88.73

●89.13 ●98.10

●88.53 ●00.06 ●88.73 ●203.00 ось агрегата ●02.25 ●87.53 ǭǹǯǹǺǻdzȋǷǸdzǵ ●88.13 бет.забор ●204.00 ●03.54 ●87.73 н/ст бет.площадка ●01.73 ●205.00 ●87.53 ●88.13 ●88.13 бассейн ●01.83

●05.48 ●87.96 ● d=0.1 89.31 ●88.93 ●88.63 ●88.33 ●05.32 ●88.13 ● 96.54 98.03 ●05.51 ●88.12 89.16 ● ● ●88.33 ●87.93 бет ●01.13 ●03.23 напор труба провод ●05.39 d=3.2 ǵǸ ǵǸ м ●04.15 ●05.74 ●88.73 ǼǽǰǺȇ ЛР-100 ●89.47 лоток d=0.35 ●04.75 ●05.34 Ǽǫǯ Ǽǫǯ ●98.13 ●04.54 ●89.73 ●06.80

●05.86 03.40 под тр ●90.33 ●88.86 ● ● ●05.80 ●05.25 ●02.63 89.86 88.06 ●05.50 дно ●88.86 ●05.54 ●07.30 ● ●03.20 90.16 205.00 ●99.73 207.00 лоток ●98.33 ●04.12 ● ● 205.00 ●05.41 05.30 00.13 ●03.75 ●04.07 ●07.83 лоток ●05.53 43.100 ● ●02.63 03.72 ●04.00 ●06.53 ●04.13 ●00.73 Ǽǫǯ ●10.75 ●03.80 ●04.33 ● 04.04 ● дно 04.57 ●10.41 ǹǮǹǻǹǯ●03.77 Ǽǫǯ ●04.73 01.90 ●07.00 ●03.80 ●03.76 ●10.42 ●04.32 ●06.30 ●04.00 ●03.77 ●0430 ●04.20 ●03.80 ● ●04.23 03.81 ●99.53 ●08.53 ●04.05 ●97.93 ●03.87 дно ●04.70 ●10.37 ●10.39 ●97.30 ●04.01 ●97.53 02.80 ●97.33 ●00.73 ● Ǽǫǯ ●97.13 04.20 ● ●10.73 ǹǮǹǻǹǯ Ǽǫǯ 04.30 ●08.47 03.70 ось агрегата дно04.00 ●00.45 ●04.04 подводящего 04.54 Ǽǫǯ ●07.40 ●10.33 ●10.43 дно ●04.35 ●08.44 канала 04.80 ●07.45 ●08.64 ● ●04.96 04.11 04.18 ● ●02.25 ●08.08 ●07.83 ●10.43 04.35 ●07.30 трасса ●01.41 Ǽǫǯ ●07.77 ●08.55 ● 04.02 ●08.29 ǹǮǹǻǹǯ ●08.34 ●07.25 ●07.43 ●10.40 ●02.45 ●10.73 ●05.01 Ǽǫǯ ●03.15 ●01.50 ● ●04.10 г.н ●04.00 ●07.70 10.93 огор п.ст пол.дорога ●0483 ●04.75 ●10.30 ●03.55 ǹǮǹǻǹǯ ●04.26 ●07.80 ●04.45 ●04.24 ●07.10 пустырь ● ●07.35 г.ж 04.00 ●04.94 ●04.91 пол.дорога ●04.55 ●04.50 Ǽǫǯ ●04.30 ●07.60 ● дно 04.33 04.45 ●05.26 ●03.80 ●10.25 ● ● дно ●07.77 ●07.60 04.53 05.30 ●04.70 ●07.74 ●05.16 04.76 ●07.25 ●08.25 Г.Н ●03.87 ●05.21 06.44 ●06.73 ●07.15 а=0,35 ● ●05.02 ●07.60 ●08.55 04.26 ●05.08 дно ●05.02 ●08.24 ●●08.46 04.74 ●06.80 07.44 ●08.65 ●05.18 ●05.52 ферма ●04.34 ●04.40 ● ●04.35 ●06.85 10.05 ●05.67 ●06.35 ●06.29 ●09.05 дно 04.76 ●10.37 Ǽǫǯ ●05.65 ●05.90 ●06.20 ●04.40 ●08.00 пустырь ●10.25 ● 04.30 ● ●06.00 ●06.85 05. ●06.22 ●08.60 ●05.53 54 ● К.Н ●04.37 ●06.27 06.80 ●06.22 ●0650 склад ●04.21 ●05.35 дно 05.15 ●06.25 ●05.79 ●06.14 ●08.34 ●05.20 ●05.20 ●05.50 Ǽǫǯ пустырь ●07.05 ●06.13 ●06.60 ось агрегата ●06.25 ●04.30 ●05.89 ●05.51 дно ●04.18 ●05.37 ●06.20 ●07.65 напорного трубопровода 05.77 ● ●07.85 04.37 ●05.94 ●05.90 ● ●06.68 Ǽǫǯ ●05.40 06.47 ●06.35 ●06.74 ●08.08 ●05.47 ● ●05.47 06.90 ●06.30 ●08.84 d=0.35 ●04.44 ●06.00 бет 06.93 ●08.68 ● ●07.00 42.900 Ǽǫǯ ●05.40 06.65 ●06.52 трасса ●06.37 ●08.88 ●05.60 ●07.10 ●05.67 ●05.46 ●06.45 пустырь ●10.70 ●07 ǹǮǹǻǹǯ . ●06.00 20 дно ●06.61 ●06.70 06 ●06.41 ●05.69 .42 ●06.66 бет 0.3м ●06.90 ●07.61 ●05.71 ● ●06.88 07.45 ●07.34 ●06.53 ● дно 06.62 07.00 ●06.70 ● ●06.57 ● 10.63 07.07 ●08.70 ǹǮǹǻǹǯ дно 06.74 ●06.60 07.34 ●09.64 ●07.34 ●09.12 ●06.69 ●09.12 Ǽǫǯ ●07.52 ●07.32 ● ●06.79 08.80 ●10.52 ●07.54 ●08.27 Ǽǫǯ ǓDzǷ ǖdzǼǽ /PǯǹǵǾǷǰǸǽǫ ǚǹǯǺdzǼȇ Ǐǫǽǫ Cheng Sheet Drawing No. Sign Date Ǐdzǻǰǵǽǹǻ ǖdzǼǽ ǖdzǼǽǹǭ ǗǫǼȃǽǫǬ Director ǪDzdzǶǹǭǠǪ Sheet Sheets Scale

34.000 34.100 34.200 34.300 1 1 1:1000 ǓǼǺǹǶǸdzǽ Designed by ǠǫǶȉDzdzǸǍǍ ǚǻǹǭǰǻdzǶ Checked ǞǮǶǫǸǹǭǛǝ

ǕǹǶǶǰǵǽǹǻ ǠǫǷDzǫ1 ǹǼȇǵǫǸǫǶǫNjnjǗǕ 15+94 Ǻǵ Ƿ h=2 10+76 Ǻǵ ǵǫǬǯǰǻǹǺǹǻ 2 Ƿ Ƿ Ǽ . Ƕ h=4 Ƿ h=5 h=7 Ƿ Ƿ ǬǹǺǹǻ 10+48 h=6 10+46 / h=8 ǬǹǺǹǻ Ǻǵ 10+36 / Ǻǵ ǺǻDZ

ǵǫǬǯǰǻǹǺǹǻ Ǻǵ 3 2 ǺǻDZ 10+20 Ǽ . ǬǹǺǹǻ 3 10+12 Ƕ / ǶȈǺ Ǻǵ Ǻǵ ǵǫǬǯǰǻǹǺǹǻ ǶȈǺ ǺǻDZ 2 2 Ǽ . Ƕ ǶȈǺ 9+14 Ǻǵ ǫǵǭǰǯǾǵǷǰǽǽǻ Ƿ =3 Ƿ h=7 Ƿ Ƿ 4+82 h=9 h=2 Ǻǵ

ǬǹǺǹǻ 6+99 ǮǻǾǸǽǯǹǻȃ ǹǻǫǼdzǽǰǶȇ / Ǻǵ ǬǹǺǹǻ ǺǻDZ 6+24 6+22 ǬǹǺǹǻ 5+40 / / 3+82 2 Ǻǵ Ǻǵ Ǻǵ 5+17

ǹǻǫǼdzǽǰǶȇ

Ǻǵ ǹǻǫǼdzǽǰǶȇ ǺǻDZ ǶȈǺ ǺǻDZ Ǻǵ 6 2

ǶȈǺ 5+20 ǍǭǶȈǺ Ǻǵ ǹǻǫǼdzǽǰǶȇ -1 NjnjǕ + 0+00 Ǻǵ

ǹǸDZǰǚǕ 0+00 ǚǕ

ǚǕ0+00 ǹǸDZǰ ǚǕ+ NjnjǕ-1

ǜǾȄǰǼǽǭǾȉȄdzǰ ǜǹǹǻǾDZǰǸdzȊ ǞǼǶǹǭǸȆǰǹǬǹDzǸǫȂǰǸdzȊ ǎǰǹǶǹǮdzȊ Road crossing (pipe) Ǚutfall to collector ǚǹǭǰǻȀǸǹǼǽȇDzǰǷǶdz ǜǬǻǹǼǭǵǹǶǶǰǵǽǹǻ Ground level ǝǻǾǬȂǫǽȆǴǺǰǻǰǰDzǯ ǕǹǸǮǶǹǷǰǻǫǽ CǾǮǶdzǸǹǵ ǚǻǫǭǫȊǬǻǹǭǵǫ ǚ Foot-bridge Right Embankment ǚǰȃǰȀǹǯǸȆǴǷǹǼǽ CǾǺǰǼȇ ǎǫǶǰȂǸdzǵdz Cross regulator ǖǰǭǫȊǬǻǹǭǵǫ Road bridge Nj ǚǰǻǰǮǹǻǫDZdzǭǫȉȄǰǰǼǹǹǻǾDZǰǸdzǰ Left Embankment NjǭǽǹǯǹǻǹDZǸȆǴǷǹǼǽ ǚǰǼǹǵ ǜǵǭǫDZdzǸǫ ǝǨǙǺǻǹǰǵǽǫ"ǛǰǫǬǰdzǶdzǽǫȁdzȊNjnjǕI ǹȂǰǻǰǽdzǻǻdzǮǫȁdzǹǸǸǹǴǼdzǼǽǰǷȆǭ Pipe under canal on collector ǎǹǻdzDzǹǸǽǭǹǯȆ Inlet to collector njǾȀǫǻǼǵǹǴǹǬǶǫǼǽdzNjǶǫǽǼǵǹǮǹǻǫǴǹǸǫ Water level ǝǻǾǬǫǺǹǯǵǫǸǫǶǹǷǸǫǵǹǶǶǰǵǽǹǻǰ ǚǻdzǷǰȂǫǸdzȊ: ǓDzǷ ǖdzǼǽ /PǯǹǵǾǷǰǸǽǫ ǚǹǯǺdzǼȇ Ǐǫǽǫ ǍǺǾǼǵǭǵǹǶǶǰǵǽǹǻ 1. ǚǻǹǯǹǶȇǸȆǴǺǻǹǿdzǶȇǵǹǶǶǰǵǽǹǻǫǼǹǼǽǫǭǶǰǸǺǹǷǫǽǰǻdzǫǶǫǷǽǹǺǹǮǰǹǯǰDzdzȂǰǼǵǹǴ Cheng Sheet Drawing No. Sign Date ǏǸǹǼǾȄǰǼǽǭǾȉȄǰǰ Outfall structure Ǐdzǻǰǵǽǹǻ ǖdzǼǽ ǖdzǼǽǹǭ ǗǫǼȃǽǫǬ ǼȅǰǷǵdzǭȆǺǹǶǸǰǸǸǹǴǭ2012 ǮǹǯǾ. ǪDzdzǶǹǭǠǪ Existing Bed Dive culvert ǞǼǽȇǰǭǹǰǼǹǹǻǾDZǰǸdzǰ Director Sheet Sheets Scale Ǐȉǵǰǻ 2. ǛǫDzǻǫǬǹǽǵǾǹǽǵǹǼǹǭǵǹǶǶǰǵǽǹǻǫc Ǻǵ0+00 ǺǹǺǵ..+.. ǺǻǹdzDzǭǹǯdzǽȇǼǺǻǫǭǹǴ ǘǫȂǹǽǯ ǕǫǻdzǷǹǭǒnj ǚǻǹǰǵǽǸȆǰ High voltage supply line / ǍǍǖ ǼǽǹǻǹǸȆ. Project leader ǎǓǚ 1 1 ǎǹǻdzDzǹǸǽǭǹǯȆ Electric power supply line / ǖǨǚ 3. ǍǷǰǼǽǫȀǺǰǻǰǼǰȂǰǸdzȊǵǹǶǶǰǵǽǹǻǫǼǵǹǷǷǾǸdzǵǫȁdzȊǷdz (ǖǨǚ, ǮǫDzǹǺǻǹǭǹǯ) ǻǫǬǹǽȆ ǜǫǽǽǹǻǹǭǛǜ Rp. ǛǰǺǰǻ Chief engineer Water level Cable / ǕǫǬǰǶȇ ǺǻǹdzDzǭǹǯdzǽȇǭǺǻdzǼǾǽǼǽǭdzdzǺǻǰǯǼǽǫǭdzǽǰǶǰǴǼǹǹǽǭǰǽǼǭǾȉȄdzȀǹǻǮǫǸdzDzǫȁdzǴ . ǓǼǺǹǶǸdzǽ Designed by ǕǫǻdzǷǹǭǒnj ǙǙǙ ǏǸǹǺǻǹǰǵǽǸǹǰ Communication line / ǖdzǸdzȊǼǭȊDzdz 4. ǍǻǫǴǹǸǰǼǾȄǰǼǽǭǾȉȄdzȀǼǹǹǻǾDZǰǸdzǴ(ǷǹǼǽǹǭ, ǫǵǭǰǯǾǵǹǭ) ǻǫǬǹǽȆǺǻǹdzDzǭǹǯdzǽȇ ǚǻǹǯǹǶȇǸȆǴǺǻǹǿdzǶȇǽǻǫǼǼǫǺǹǯǭǹǯȊȃdzǴdz ǜǾȄǰǼǽǭǾȉȄdzǰǼǹǹǻǾDZǰǸdzȊ ǭǻǾȂǸǾȉ. ǚǻǹǭǰǻdzǶ Design Bed Water supply line / ǍǹǯǹǺǻǹǭǹǯ Checked ǛǫȀdzǷǹǭǘǠ "njǾȀǹǻǹǎdzǯǻǹǷǰǶdzǹǶǹǴdzȀǫ" ǛǰǵǹǸǼǽǻǾdzǻǾǰǷȆǰǼǹǹǻǾDZǰǸdzȊ 5. ǛǫDzǷǰǻȆǸǫȂǰǻǽǰDZǰǯǫǸȆǭǷ. ǹǽǭǹǯȊȃdzǴǵǫǸǫǶǫǺǵ0+00 Ǻǵ15+94 ǖdzǵǭdzǯdzǻǾǰǷȆǰǼǹǹǻǾDZǰǸdzȊ Gas supply line / ǎǫDzǹǺǻǹǭǹǯ njǾȀǫǻǫ-2012 Ǯ. . ǕǹǶǶǰǵǽǹǻ ǠǫǷDzǫ1

ǹǼȇǵǫǸǫǶǫNjnjǗǕ 15+94 Ǻǵ Ƿ h=2 10+76 Ǻǵ

ǵǫǬǯǰǻǹǺǹǻ 2 Ƿ Ƿ Ǽ Ƕ . h=4 Ƿ h=5 h=7 Ƿ Ƿ 10+48 h=6 10+46 / ǬǹǺǹǻ h=8 Ǻǵ

10+36 / ǬǹǺǹǻ Ǻǵ

ǺǻDZ

ǵǫǬǯǰǻǹǺǹǻ Ǻǵ 3 2 ǺǻDZ 10+20 Ǽ .

ǬǹǺǹǻ 3 10+12 Ƕ / ǶȈǺ Ǻǵ Ǻǵ

ǵǫǬǯǰǻǹǺǹǻ ǶȈǺ ǺǻDZ 2 2 Ǽ Ƕ . ǶȈǺ 9+14 Ǻǵ

ǫǵǭǰǯǾǵǷǰǽǽǻ Ƿ =3 Ƿ h=7 Ƿ h=9

ǬǹǺǹǻ 6+99 ǮǻǾǸǽǯǹǻȃ / Ǻǵ ǺǻDZ 6+24 6+22 5+40 / ǬǹǺǹǻ 3+82 2 Ǻǵ Ǻǵ Ǻǵ 5+17 ǹǻǫǼdzǽǰǶȇ ǹǻǫǼdzǽǰǶȇ Ǻǵ

ǺǻDZ ǶȈǺ

Ǻǵ 2 ǶȈǺ 5+20 Ǻǵ ǹǻǫǼdzǽǰǶȇ -1 NjnjǕ + 0+00 Ǻǵ ǹǸDZǰǚǕ

0+00 ǚǕ

ǚǕ0+00 ǹǸDZǰ ǚǕ+ NjnjǕ-1 ǵǹǶǶǰǵǽǹǻǽȈǹǺǻǹǰǵǽǫNjnjǕ-1 ǖdzǼǽ1 ǖdzǼǽǹǭ5 ǵǹǶǶǰǵǽǹǻǽȈǹǺǻǹǰǵǽǫNjnjǕ-1 ǖdzǼǽ2 ǖdzǼǽǹǭ5 ǵǹǶǶǰǵǽǹǻǽȈǹǺǻǹǰǵǽǫNjnjǕ-1 ǖdzǼǽ3 ǖdzǼǽǹǭ5 ǵǹǶǶǰǵǽǹǻǽȈǹǺǻǹǰǵǽǫNjnjǕ-1 ǖdzǼǽ4 ǖdzǼǽǹǭ5 ǵǹǶǶǰǵǽǹǻǽȈǹǺǻǹǰǵǽǫNjnjǕ-1 ǖdzǼǽ5 ǖdzǼǽǹǭ

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Appendix 8

Cost Estimate Breakdown for the Khamza New Pump Station

Lahmeyer International in association with InfoCapital Group

InfoCapital Group ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/9/2013 Technical Feasibility Report

KHAMZA NEW PUMPING STATION PLANT - OPTION 2 (8 UNITS)

ITEM / SYSTEM / EQUIPMENT COST [US$] (A) MECHANICAL EQUIPMENT 24,335,000 (B) BUILDING SERVICES 1,010,000 (C) HYDRAULIC STEEL STRUCTURE 19,267,000 (D) ELECTRICAL EQUIPMENT 18,381,000 (E) INSTRUMENTATION AND CONTROL 422,000 Total Khamza NEW Pump Station 63,415,000 Applied Contingencies (10%) 6,341,500 Sum Khamza NEW Pump Station 69,756,500 (F) CIVIL STRUCTURE 28,620,500 Total Khamza NEW Pump Station 28,620,500 Applied Contingencies (7%) 2,003,435 Sum Khamza NEW Pump Station 30,623,935 GRAND TOTAL KHAMZA NEW PUMP STATION 100,380,435 ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/9/2013 Technical Feasibility Report

KHAMZA NEW PUMPING STATION PLANT - OPTION 2 (8 UNITS)

Cost Estimates by Expenditure Category Exchange Rate: 1 US$ =2096 SOUM

Item No. Item Description Unit Quantity Total Unit Rate Unit Rate Unit Rate Total Price Total Price Total Price Foreign Foreign Local Foreign Local Foreign % Currency Currency Currency Currency Currency Currency Local/Foreign US$ US$ US$ US$ US$ US$ Portion

(A) MECHANICAL EQUIPMENT

1 Pump House Mechanical Equipment 1.1 Main Pump Units, centrifugal type (H=53m, Q=11,4m³/s, n=300min^-1) incl. Model Tests, - 8 2,250,000 337,500 1,912,500 2,700,000 15,300,000 18,000,000 15 Spare Parts 1.2 Main Discharge Shut-Off Valves (DN2100, PN10) incl. Hydraulic Units - 9 245,000 36,750 208,250 330,750 1,874,250 2,205,000 15 1.3 Maintenance Discharge Valve (DN2300, PN10) incl. Elect. Actuator - 9 270,000 40,500 229,500 364,500 2,065,500 2,430,000 15 1.4 Technical Water Supply System incl. Shaft Seal Water Supply - 1 440,000 88,000 352,000 88,000 352,000 440,000 20 1.5 Oil Supply and Disposal System incl. Compact Mobile Purification Unit - 1 140,000 28,000 112,000 28,000 112,000 140,000 20 1.6 Low Pressure Compressed Air System - 1 50,000 10,000 40,000 10,000 40,000 50,000 20 1.7 Emergency Dewatering System - 1 80,000 16,000 64,000 16,000 64,000 80,000 20 1.8 Drainage and Dewatering System - 1 230,000 46,000 184,000 46,000 184,000 230,000 20

2 Cranes and Lifting Equipment 2.1 Pump House Overhead Crane 50/15 tons - 1 290,000 58,000 232,000 58,000 232,000 290,000 20 2.2 Overhead Crane 15 tons, Butterfly Valves - 1 115,000 23,000 92,000 23,000 92,000 115,000 20 2.4 Lifting Equipment 1 x 2 tons, Aux. Equipment - 8 15,000 3,000 12,000 24,000 96,000 120,000 20 2.5 Lifting Equipment 1 x 4 tons, Drainage and Dewatering Room - 1 25,000 5,000 20,000 5,000 20,000 25,000 20 2.6 Gantry Crane 15 tons, Maintenance Butterfly Valve - 1 210,000 42,000 168,000 42,000 168,000 210,000 20

TOTAL Mechanical Equipment 3,735,250 20,599,750 24,335,000

(B) BUILDING SERVICES

3 Building Service Equipment 3.1 Water Supply System - 1 110,000 22,000 88,000 22,000 88,000 110,000 20 3.2 Air Conditioning and Ventilation System - 1 400,000 80,000 320,000 80,000 320,000 400,000 20 3.3 Fire Fighting Equipment - 1 360,000 72,000 288,000 72,000 288,000 360,000 20 3.4 Workshop Facilities - 1 140,000 28,000 112,000 28,000 112,000 140,000 20

TOTAL Building Service Equipment 202,000 808,000 1,010,000

(C) HYDRAULIC STEEL STRUCTURE

4 Forebay, Discharge and Intake Hydraulic Steel Structure Equipment 4.1 Intake Trash Rack Cleaning Machine - 1 250,000 50,000 200,000 50,000 200,000 250,000 20 4.2 Intake Trash Racks incl. Embedded Parts, 8 bays - 8 27,000 5,400 21,600 43,200 172,800 216,000 20 4.3 Intake Stoplogs Sets incl. Embedded Parts - 3 57,000 11,400 45,600 34,200 136,800 171,000 20 4.4 Intake Gantry Crane (7 tons), Grappling Beam - 1 170,000 34,000 136,000 34,000 136,000 170,000 20

5 Discharge Pipe System 5.1 Pump Discharge Pipe, 8 x dia. 2300 mm m 700 5,300 1,060 4,240 742,000 2,968,000 3,710,000 20 5.2 Main Discharge Pipe, 2 x dia. 4100 mm m 1,240 11,750 2,350 9,400 2,914,000 11,656,000 14,570,000 20 5.3 Air Breaker Valves - 4 15,000 3,000 12,000 12,000 48,000 60,000 20 5.4 Vaccum Pump System (Ejector) - 1 120,000 24,000 96,000 24,000 96,000 120,000 20

TOTAL Hydraulic Steel Structure 3,853,400 15,413,600 19,267,000

(D) ELECTRICAL EQUIPMENT 6 Pump House Electrical Equipment 6.1 Main Electrical Motors, synchronous type (P=7330kW, 6.3kV, n=300min^-1) incl. Spare - 8 1,520,000 228,000 1,292,000 1,824,000 10,336,000 12,160,000 15 Parts 6.2 6.3kV Switchgear Installations - 1 2,821,000 564,200 2,256,800 564,200 2,256,800 2,821,000 20 6.3 LV Transformers and 380/220 V Switchgears - 1 550,000 110,000 440,000 110,000 440,000 550,000 20 6.4 Emergency Diesel Generator Set - 1 120,000 18,000 102,000 18,000 102,000 120,000 15 6.5 Cabling, Earthing & Lighting Systems - 1 330,000 66,000 264,000 66,000 264,000 330,000 20 6.6 6.3kV LCI (Start-Up Equipment) - 2 1,200,000 240,000 960,000 480,000 1,920,000 2,400,000 20

TOTAL Electrical Equipment 3,062,200 15,318,800 18,381,000

(E) INSTRUMENTATION AND CONTROL

7 Pump House Instrumentation and Control Equipment 7.1 Field Instrumentation, Control System and SCADA - 1 160,000 32,000 128,000 32,000 128,000 160,000 20 7.2 Ultrasonic Discharge Flow Measurement, dia. 2300 mm - 8 24,000 4,800 19,200 38,400 153,600 192,000 20 7.3 Fire Detection and Alarm System - 1 20,000 4,000 16,000 4,000 16,000 20,000 20 7.4 Telecommunication System and Equipment - 1 50,000 10,000 40,000 10,000 40,000 50,000 20

TOTAL Instrumentation and Control 84,400 337,600 422,000

(F) CIVIL STRUCTURE

8 Intake Canal and Forebay 8.1 Excavation m³ 900,000 2 1.4 0.6 1,260,000 540,000 1,800,000 70 8.2 Concrete m³ 2,250 125 88 38 196,875 84,375 281,250 70 8.3 Reinforcement ton 225 1,800 1,260 540 283,500 121,500 405,000 70 8.4 Rip-Rap m³ 5,000 20 14 6 70,000 30,000 100,000 70

9 Pump Station 9.1 Excavation m³ 300,000 2 1.4 0.6 420,000 180,000 600,000 70 9.2 Construction Pit & Dewatering - 1 10,000,000 7,000,000 3,000,000 7,000,000 3,000,000 10,000,000 70 9.3 Formwork m² 30,000 30 21 9 630,000 270,000 900,000 70 9.4 Concrete m³ 21,250 140 98 42 2,082,500 892,500 2,975,000 70 9.5 Reinforcement ton 2,550 1,800 1,260 540 3,213,000 1,377,000 4,590,000 70 9.6 Precast reinforced concrete m³ 2,500 300 210 90 525,000 225,000 750,000 70 9.7 Metal Works ton 250 2,000 1,400 600 350,000 150,000 500,000 70 9.8 Backfill and Embankment m³ 100,000 2 1.4 0.6 140,000 60,000 200,000 70 9.9 Fencing - 1 525,000 367,500.0 157,500.0 367,500 157,500 525,000 70

10 Protection Dam 10.1 Excavation m³ 4,500 2 1.4 0.6 6,300 2,700 9,000 70 10.2 Concrete m³ 450 125 88 38 39,375 16,875 56,250 70 10.3 Reinforcement ton 10 1,800 1,260 540 12,600 5,400 18,000 70 10.4 Rip-Rap m³ 300 20 14 6 4,200 1,800 6,000 70

11 Discharge Pipelines & Canal 11.1 Excavation m³ 300,000 2 1.4 0.6 420,000 180,000 600,000 70 11.2 Formwork m² 14,000 30 21 9 294,000 126,000 420,000 70 11.3 Concrete m³ 10,000 140 98 42 980,000 420,000 1,400,000 70 11.4 Reinforcement ton 1,200 1,800 1,260 540 1,512,000 648,000 2,160,000 70 11.5 Backfil and Embankment m³ 50,000 2 1.4 0.6 70,000 30,000 100,000 70 11.6 Road Bridge - 1 225,000.0 157,500.0 67,500.0 157,500 67,500 225,000 70

TOTAL Civil Structure 20,034,350 8,586,150 28,620,500

Total Mechanical and Electrical Equipment 10,937,250 52,477,750 63,415,000 Applied Contingencies (10%) 1,093,725 5,247,775 6,341,500 Sum Mechanical and Electrical Equipment 12,030,975 57,725,525 69,756,500

Total Civil Structure 20,034,350 8,586,150 28,620,500 Applied Contingencies (7%) 1,402,405 601,031 2,003,435 Sum Civil Structure 21,436,755 9,187,181 30,623,935 GRAND TOTAL KHAMZA NEW PUMP STATION - OPTION 2 (8 UNITS) 33,467,730 66,912,706 100,380,435

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Appendix 9

Updated Cost Estimate Breakdowns for the Khamza 2, Kuyu Mazar, Kizil Tepa and Kizil Tepa Auxiliary Pump Stations

Lahmeyer International in association with InfoCapital Group

InfoCapital Group ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/9/2013 Technical Feasibility Report

KHAMZA-2 PUMPING STATION PLANT REHABILITATION

ITEM / SYSTEM / EQUIPMENT COST [US$] (A) MECHANICAL EQUIPMENT REHABILITATION 42,235,000 (B) BUILDING SERVICES REHABILITATION 520,000 (C) HYDRAULIC STEEL STRUCTURE REHABILITATION 21,900,840 (D) ELECTRICAL EQUIPMENT REHABILITATION 21,860,000 (E) INSTRUMENTATION AND CONTROL REHABILITATION 480,000 Total Khamza-2 Pump Station Rehabilitation 86,995,840 Applied Contingencies (10%) 8,699,584 Sum Khamza-2 Pump Station Rehabilitation 95,695,424 (F) CIVIL STRUCTURE REHABILITATION 1,344,000 Total Khamza-2 Pump Station Rehabilitation 1,344,000 Applied Contingencies (7%) 94,080 Sum Khamza-2 Pump Station Rehabilitation 1,438,080 GRAND TOTAL KHAMZA-2 PUMP STATION REHABILITATION 97,133,504 ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/9/2013 Technical Feasibility Report

KHAMZA-2 PUMPING STATION PLANT REHABILITATION

Cost Estimates by Expenditure Category (1) rehabilitation/modernization/renewal of the exiting equipment/system/structure Exchange Rate: 1 US$ =2096 SOUM (2) replacement of the exiting equipment/system/structure

Item No. Item Description Unit Quantity Total Unit Rate Unit Rate Unit Rate Total Price Total Price Total Price Foreign Foreign Local Foreign Local Foreign % Currency Currency Currency Currency Currency Currency Local/Foreign (1) (2) US$ US$ US$ US$ US$ US$ Portion

(A) MECHANICAL EQUIPMENT REHABILITATION

1 Pump House Mechanical Equipment 1.1 Main Pump Units, centrifugal type (H=54m, Q=15m³/s, n=250min^-1) incl. Model x - 10 3,830,000 574,500 3,255,500 5,745,000 32,555,000 38,300,000 15 Tests, Spare Parts 1.2 Main Discharge Shut-Off Valves (DN2200, PN10) incl. Hydraulic Units x - 11 260,000 39,000 221,000 429,000 2,431,000 2,860,000 15 1.3 Technical Water Supply System incl. Shaft Seal Water Supply x - 1 310,000 62,000 248,000 62,000 248,000 310,000 20 1.4 Oil Handling System incl. Compact Mobile Purification Unit x - 1 130,000 26,000 104,000 26,000 104,000 130,000 20 1.5 Low Pressure Compressed Air System x - 1 45,000 9,000 36,000 9,000 36,000 45,000 20 1.6 Emergency Dewatering System x - 1 95,000 19,000 76,000 19,000 76,000 95,000 20 1.7 Drainage and Dewatering System x - 1 210,000 42,000 168,000 42,000 168,000 210,000 20

2 Cranes and Lifting Equipment 2.1 Pump House Overhead Crane 100/20 tons x - 1 180,000 36,000 144,000 36,000 144,000 180,000 20 2.2 Overhead Crane 15 tons, Butterfly Valves x - 1 35,000 7,000 28,000 7,000 28,000 35,000 20 2.3 Monorail Lifting Equipment 2 x 3 tons for Main Pumps x - 1 40,000 8,000 32,000 8,000 32,000 40,000 20 2.4 Elevator 500 kg x - 1 30,000 6,000 24,000 6,000 24,000 30,000 20

TOTAL Mechanical Equipment Rehabilitation 6,389,000 35,846,000 42,235,000

(B) BUILDING SERVICES REHABILITATION

3 Building Service Equipment 3.1 Water Supply System x - 1 110,000 22,000 88,000 22,000 88,000 110,000 20 3.2 Air Conditioning and Ventilation System (HVAC) x - 1 340,000 68,000 272,000 68,000 272,000 340,000 20 3.3 Fire Fighting Equipment x - 1 25,000 5,000 20,000 5,000 20,000 25,000 20 3.4 Workshop Facilities x - 1 45,000 9,000 36,000 9,000 36,000 45,000 20

TOTAL Building Service Equipment Rehabilitation 104,000 416,000 520,000

(C) HYDRAULIC STEEL STRUCTURE REHABILITATION

4 Forebay and Intake Hydraulic Steel Structure Equipment 4.1 Intake Trash Rack Cleaning Machine x - 1 250,000 50,000 200,000 50,000 200,000 250,000 20 4.2 Intake Trash Rack Screens (3,5 x 8 m) x - 14 21,000 4,200 16,800 58,800 235,200 294,000 20 4.3 Gantry Crane Forebay (5 ton) x - 1 50,000 10,000 40,000 10,000 40,000 50,000 20 4.4 Gantry Crane Intake (16/5 ton) x - 1 60,000 12,000 48,000 12,000 48,000 60,000 20 4.6 Intake Slide Gates incl. Electrical Drive x - 10 55,000 11,000 44,000 110,000 440,000 550,000 20 5 Discharge Pipe System 5.1 Discharge Pipe No. 1, 10 x dia. 2440 mm incl. Disassembly old Pipe (total pipe x m 300 7,760 1,552 6,208 465,600 1,862,400 2,328,000 20 weight 290 ton) 5.2 Discharge Pipe No. 1, 4 x dia. 3240 mm incl. Disassembly old Pipe (total pipe x m 160 12,200 2,440 9,760 390,400 1,561,600 1,952,000 20 weight 250 ton) 5.3 Discharge Pipe No. 1, 2 x dia. 4240 mm incl. Disassembly old Pipe (total pipe x m 1,218 13,380 2,676 10,704 3,259,368 13,037,472 16,296,840 20 weight 2050 ton) 5.4 Air Breaker Valves x - 8 15,000 3,000 12,000 24,000 96,000 120,000 20

TOTAL Hydraulic Steel Structure Rehabilitation 4,380,168 17,520,672 21,900,840

(D) ELECTRICAL EQUIPMENT REHABILITATION

6 Pump House Electrical Equipment 6.1 Main Electrical Motors, synchronous type (P=12500kW, 10kV, n=250min^-1) incl. x - 10 1,638,000 245,700 1,392,300 2,457,000 13,923,000 16,380,000 15 Spare Parts 6.2 10 kV Switchgear Installations x - 1 2,200,000 440,000 1,760,000 440,000 1,760,000 2,200,000 20 6.3 LV Transformers and 380/220 V Switchgears x - 1 550,000 110,000 440,000 110,000 440,000 550,000 20 6.4 Emergency Diesel Generator Set x - 1 120,000 18,000 102,000 18,000 102,000 120,000 15 6.5 Cabling, Earthing & Lighting Systems x - 1 330,000 66,000 264,000 66,000 264,000 330,000 20 6.6 10 kV LCI (Start-Up Equipment) x - 2 1,140,000 228,000 912,000 456,000 1,824,000 2,280,000 20

TOTAL Electrical Equipment Rehabilitation 3,547,000 18,313,000 21,860,000

(E) INSTRUMENTATION AND CONTROL REHABILITATION

7 Pump House Instrumentation and Control Equipment 7.1 Field Instrumentation, Control System and SCADA x - 1 160,000 32,000 128,000 32,000 128,000 160,000 20 7.2 Ultrasonic Discharge Flow Measurement, dia. 2440 mm x - 10 25,000 5,000 20,000 50,000 200,000 250,000 20 7.3 Fire Detection and Alarm System x - 1 20,000 4,000 16,000 4,000 16,000 20,000 20 7.4 Telecommunication System and Equipment x - 1 50,000 10,000 40,000 10,000 40,000 50,000 20

TOTAL Instrumentation and Control Rehabilitation 96,000 384,000 480,000

(F) CIVIL STRUCTURE REHABILITATION

8 Construction and Renovation Works 8.1 Earth Works x - 1 49,000 34,300 14,700 34,300 14,700 49,000 70 8.2 Civil and Erection Works x - 1 1,295,000 906,500 388,500 906,500 388,500 1,295,000 70

TOTAL Civil Structure Rehabilitation 940,800 403,200 1,344,000

Total Rehabilitation Mechanical and Electrical Equipment 14,516,168 72,479,672 86,995,840 Applied Contingencies (10%) 1,451,617 7,247,967 8,699,584 Sum Rehabilitation Mechanical and Electrical Equipment 15,967,785 79,727,639 95,695,424

Total Rehabilitation Civil Structure 940,800 403,200 1,344,000 Applied Contingencies (7%) 65,856 28,224 94,080 Sum Rehabilitation Civil Structure 1,006,656 431,424 1,438,080

GRAND TOTAL KHAMZA-2 PUMP STATION REHABILITATION 16,974,441 80,159,063 97,133,504 ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/9/2013 Technical Feasibility Report

KUYU-MAZAR PUMPING STATION PLANT REHABILITATION

ITEM / SYSTEM / EQUIPMENT COST [US$] (A) MECHANICAL EQUIPMENT REHABILITATION 13,384,000 (B) BUILDING SERVICES REHABILITATION 355,000 (C) HYDRAULIC STEEL STRUCTURE REHABILITATION 1,278,200 (D) ELECTRICAL EQUIPMENT REHABILITATION 8,120,000 (E) INSTRUMENTATION AND CONTROL REHABILITATION 405,000 Total Kuyu-Mazar Pump Station Rehabilitation 23,542,200 Applied Contingencies (10%) 2,354,220 Sum Kuyu-Mazar Pump Station Rehabilitation 25,896,420 (F) CIVIL STRUCTURE REHABILITATION 2,660,000 Total Kuyu-Mazar Pump Station Rehabilitation 2,660,000 Applied Contingencies (7%) 186,200 Sum Kuyu-Mazar Pump Station Rehabilitation 2,846,200 GRAND TOTAL KUYU-MAZAR PUMP STATION REHABILITATION 28,742,620 ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/9/2013 Technical Feasibility Report

KUYU-MAZAR PUMPING STATION PLANT REHABILITATION

Cost Estimates by Expenditure Category (1) rehabilitation/modernization/renewal of the exiting equipment/system/structure Exchange Rate: 1 US$ =2096 SOUM (2) replacement of the exiting equipment/system/structure

Item No. Item Description Unit Quantity Total Unit Rate Unit Rate Unit Rate Total Price Total Price Total Price Foreign Foreign Local Foreign Local Foreign % Currency Currency Currency Currency Currency Currency Local/Foreign (1) (2) US$ US$ US$ US$ US$ US$ Portion

(A) MECHANICAL EQUIPMENT REHABILITATION

1 Pump House Mechanical Equipment 1.1 Main Pump Units (No. 1-3), axial type (H=23m, Q=18,4m³/s, n=333min^-1) incl. Model x - 3 1,960,000 294,000 1,666,000 882,000 4,998,000 5,880,000 15 Tests, Spare Parts 1.2 Main Pump Units (No. 4-6), centrifugal type (H=18m, Q=20m³/s, n=333min^-1) incl. Model x - 3 2,293,000 343,950 1,949,050 1,031,850 5,847,150 6,879,000 15 Tests, Spare Parts 1.3 Technical Water Supply System incl. Shaft Seal Water Supply (in house) x - 1 180,000 36,000 144,000 36,000 144,000 180,000 20 1.4 Oil Handling System incl. Compact Mobile Purification Unit x - 1 80,000 16,000 64,000 16,000 64,000 80,000 20 1.5 Low Pressure Compressed Air System x - 1 40,000 8,000 32,000 8,000 32,000 40,000 20 1.6 Emergency Dewatering System x - 1 85,000 17,000 68,000 17,000 68,000 85,000 20 1.7 Drainage and Dewatering System x - 1 180,000 36,000 144,000 36,000 144,000 180,000 20

2 Cranes and Lifting Equipment 2.1 Pump House Overhead Crane 20/5 tons x - 1 40,000 8,000 32,000 8,000 32,000 40,000 20 2.2 Monorail Lifting Equipment 5 tons for Main Pumps x - 1 20,000 4,000 16,000 4,000 16,000 20,000 20

TOTAL Mechanical Equipment Rehabilitation 2,038,850 11,345,150 13,384,000

(B) BUILDING SERVICES REHABILITATION

3 Building Service Equipment 3.1 Water Supply System x - 1 110,000 22,000 88,000 22,000 88,000 110,000 20 3.2 Air Conditioning and Ventilation System (HVAC) x - 1 180,000 36,000 144,000 36,000 144,000 180,000 20 3.3 Fire Fighting Equipment x - 1 25,000 5,000 20,000 5,000 20,000 25,000 20 3.4 Workshop Facilities x - 1 40,000 8,000 32,000 8,000 32,000 40,000 20

TOTAL Building Service Equipment Rehabilitation 71,000 284,000 355,000

(C) HYDRAULIC STEEL STRUCTURE REHABILITATION

4 Forebay and Intake Hydraulic Steel Structure Equipment 4.1 Intake Trash Rack Cleaning Machine (Kuyu-Mazar, ABK-1) x - 2 250,000 50,000 200,000 100,000 400,000 500,000 20 4.2 Intake Trash Rack (Kuy-Mazar Canal) x - 1 80,000 16,000 64,000 16,000 64,000 80,000 20 4.3 Intake Trash Rack (ABK-1) x - 1 190,000 38,000 152,000 38,000 152,000 190,000 20 4.4 Intake Stoplogs x - 2 12,000 4,800 7,200 9,600 14,400 24,000 40 4.5 Hoist for Stoplogs (2 x 5 tons), Grappling Beam x - 1 45,000 9,000 36,000 9,000 36,000 45,000 20 4.6 Diversion Gates incl. Hyd. Electrical Drive x - 3 50,000 10,000 40,000 30,000 120,000 150,000 20

5 Discharge Pipe System 5.1 Discharge Pipe Corrossion Repair Works, No. 6, Dia. 2840 mm x m 420 260 104 156 43,680 65,520 109,200 40 5.3 Air Breaker Valves x - 12 15,000 3,000 12,000 36,000 144,000 180,000 20

TOTAL Hydraulic Steel Structure Rehabilitation 282,280 995,920 1,278,200 (D) ELECTRICAL EQUIPMENT REHABILITATION

6 Pump House Electrical Equipment 6.1 Main Electrical Motors, synchronous type (P=5000kW, 6kV, n=333min^-1) incl. Spare Parts x - 6 1,040,000 156,000 884,000 936,000 5,304,000 6,240,000 15

6.2 6 kV Switchgear Installations x - 1 900,000 180,000 720,000 180,000 720,000 900,000 20 6.3 LV Transformers and 380/220 V Switchgears x - 1 580,000 116,000 464,000 116,000 464,000 580,000 20 6.4 Emergency Diesel Generator Set x - 1 100,000 15,000 85,000 15,000 85,000 100,000 15 6.5 Cabling, Earthing & Lighting Systems x - 1 300,000 60,000 240,000 60,000 240,000 300,000 20

TOTAL Electrical Equipment Rehabilitation 1,307,000 6,813,000 8,120,000

(E) INSTRUMENTATION AND CONTROL REHABILITATION

7 Pump House Instrumentation and Control Equipment 7.1 Field Instrumentation, Control System and SCADA x - 1 160,000 32,000 128,000 32,000 128,000 160,000 20 7.2 Ultrasonic Discharge Flow Measurement, dia. 2840 mm x - 6 30,000 6,000 24,000 36,000 144,000 180,000 20 7.3 Fire Detection and Alarm System x - 1 15,000 3,000 12,000 3,000 12,000 15,000 20 7.4 Telecommunication System and Equipment x - 1 50,000 10,000 40,000 10,000 40,000 50,000 20

TOTAL Instrumentation and Control Rehabilitation 81,000 324,000 405,000

(F) CIVIL STRUCTURE REHABILITATION

8 Construction and Renovation Works 8.1 Earth Works x - 1 342,000 239,400 102,600 239,400 102,600 342,000 70 8.2 Civil and Erection Works x - 1 2,318,000 1,622,600 695,400 1,622,600 695,400 2,318,000 70

TOTAL Civil Structure Rehabilitation 1,862,000 798,000 2,660,000

Total Rehabilitation Mechanical and Electrical Equipment 3,780,130 19,762,070 23,542,200 Applied Contingencies (10%) 378,013 1,976,207 2,354,220 Sum Rehabilitation Mechanical and Electrical Equipment 4,158,143 21,738,277 25,896,420

Total Rehabilitation Civil Structure 1,862,000 798,000 2,660,000 Applied Contingencies (7%) 130,340 55,860 186,200 Sum Rehabilitation Civil Structure 1,992,340 853,860 2,846,200

GRAND TOTAL KUYU-MAZAR PUMP STATION REHABILITATION 6,150,483 22,592,137 28,742,620 ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/9/2013 Technical Feasibility Report

KIZIL-TEPA PUMPING STATION PLANT REHABILITATION

ITEM / SYSTEM / EQUIPMENT COST [US$] (A) MECHANICAL EQUIPMENT REHABILITATION 36,006,000 (B) BUILDING SERVICES REHABILITATION 490,000 (C) HYDRAULIC STEEL STRUCTURE REHABILITATION 4,847,600 (D) ELECTRICAL EQUIPMENT REHABILITATION 20,628,000 (E) INSTRUMENTATION AND CONTROL REHABILITATION 480,000 Total Kizil-Tepa Pump Station Rehabilitation 62,451,600 Applied Contingencies (10%) 6,245,160 Sum Kizil-Tepa Pump Station Rehabilitation 68,696,760 (F) CIVIL STRUCTURE REHABILITATION 2,554,000 Total Kizil-Tepa Pump Station Rehabilitation 2,554,000 Applied Contingencies (7%) 178,780 Sum Kizil-Tepa Pump Station Rehabilitation 2,732,780 GRAND TOTAL KIZIL-TEPA PUMP STATION REHABILITATION 71,429,540 ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/9/2013 Technical Feasibility Report

KIZIL-TEPA PUMPING STATION PLANT REHABILITATION

Cost Estimates by Expenditure Category (1) rehabilitation/modernization/renewal of the exiting equipment/system/structure Exchange Rate: 1 US$ =2096 SOUM (2) replacement of the exiting equipment/system/structure

Item No. Item Description Unit Quantity Total Unit Rate Unit Rate Unit Rate Total Price Total Price Total Price Foreign Foreign Local Foreign Local Foreign % Currency Currency Currency Currency Currency Currency Local/Foreign (1) (2) US$ US$ US$ US$ US$ US$ Portion

(A) MECHANICAL EQUIPMENT REHABILITATION

1 Pump House Mechanical Equipment 1.2 Main Pump Units (No. 1-4), centrifugal type (H=45m, Q=13.3m³/s, n=250min^-1) incl. Model x - 4 2,685,000 402,750 2,282,250 1,611,000 9,129,000 10,740,000 15 Tests, Spare Parts 1.1 Main Pump Units (No. 5-10), centrifugal type (H=70m, Q=12m³/s, n=250min^-1) incl. Model x - 6 3,556,000 533,400 3,022,600 3,200,400 18,135,600 21,336,000 15 Tests, Spare Parts 1.3 Main Discharge Shut-Off Valves (DN2200, PN10) incl. Hydraulic Units x - 11 260,000 52,000 208,000 572,000 2,288,000 2,860,000 20 1.4 Technical Water Supply System incl. Shaft Seal Water Supply x - 1 310,000 62,000 248,000 62,000 248,000 310,000 20 1.5 Oil Handling System incl. Compact Mobile Purification Unit x - 1 130,000 26,000 104,000 26,000 104,000 130,000 20 1.6 Low Pressure Compressed Air System x - 1 45,000 9,000 36,000 9,000 36,000 45,000 20 1.7 Emergency Dewatering System x - 1 90,000 18,000 72,000 18,000 72,000 90,000 20 1.8 Drainage and Dewatering System x - 1 210,000 42,000 168,000 42,000 168,000 210,000 20

2 Cranes and Lifting Equipment 2.1 Pump House Overhead Crane 100/20 tons x - 1 180,000 36,000 144,000 36,000 144,000 180,000 20 2.2 Overhead Crane 15 tons, Butterfly Valves x - 1 35,000 7,000 28,000 7,000 28,000 35,000 20 2.3 Monorail Lifting Equipment 2 x 3 tons for Main Pumps x - 1 40,000 8,000 32,000 8,000 32,000 40,000 20 2.4 Elevator 500 kg x - 1 30,000 6,000 24,000 6,000 24,000 30,000 20

TOTAL Mechanical Equipment Rehabilitation 5,597,400 30,408,600 36,006,000

(B) BUILDING SERVICES REHABILITATION

3 Building Service Equipment 3.1 Water Supply System x - 1 110,000 22,000 88,000 22,000 88,000 110,000 20 3.2 Air Conditioning and Ventilation System (HVAC) x - 1 310,000 62,000 248,000 62,000 248,000 310,000 20 3.3 Fire Fighting Equipment x - 1 25,000 5,000 20,000 5,000 20,000 25,000 20 3.4 Workshop Facilities x - 1 45,000 9,000 36,000 9,000 36,000 45,000 20

TOTAL Building Service Equipment Rehabilitation 98,000 392,000 490,000

(C) HYDRAULIC STEEL STRUCTURE REHABILITATION

4 Forebay and Intake Hydraulic Steel Structure Equipment 4.1 Intake Trash Rack Cleaning Machine x - 1 250,000 50,000 200,000 50,000 200,000 250,000 20 4.2 Intake Trash Rack Screens (3,5 x 8 m) x - 14 21,000 4,200 16,800 58,800 235,200 294,000 20 4.3 Gantry Crane Forebay (5 ton) x - 1 50,000 10,000 40,000 10,000 40,000 50,000 20 4.4 Gantry Crane Intake (16/5 ton) x - 1 60,000 12,000 48,000 12,000 48,000 60,000 20 4.5 Intake Slide Gates incl. Electrical Drive x - 10 55,000 11,000 44,000 110,000 440,000 550,000 20 5 Discharge Pipe System 5.1 Discharge Pipe No. 1 - 4 , 4 x dia. 2440 mm incl. Disassembly of Pipe (total pipe weight 170 x m 160 8,200 1,640 6,560 262,400 1,049,600 1,312,000 20 ton) 5.2 Discharge Pipe No. 4 - 10 , 6 x dia. 2440 mm incl. Disassembly of Pipe (total pipe weight x m 240 6,750 1,350 5,400 324,000 1,296,000 1,620,000 20 210 ton) 5.3 Discharge Pipe Corrossion Repair Works Kharakur Branch, 2 x dia. 3240 mm x m 1,740 340 136 204 236,640 354,960 591,600 40 5.4 Air Breaker Valves x - 8 15,000 3,000 12,000 24,000 96,000 120,000 20

TOTAL Hydraulic Steel Structure Rehabilitation 1,087,840 3,759,760 4,847,600

(D) ELECTRICAL EQUIPMENT REHABILITATION

6 Pump House Electrical Equipment 6.1 Main Electrical Motors, synchronous type (P=8500kW, 10kV, n=250min^-1) incl. Spare x - 4 1,230,000 184,500 1,045,500 738,000 4,182,000 4,920,000 15 Parts (No. 1 - 4) 6.2 Main Electrical Motors, synchronous type (P=12500kW, 10kV, n=250min^-1) incl. Spare x - 6 1,638,000 245,700 1,392,300 1,474,200 8,353,800 9,828,000 15 Parts (No. 5 - 10) 6.3 6 kV Switchgear Installations x - 1 2,200,000 440,000 1,760,000 440,000 1,760,000 2,200,000 20 6.4 LV Transformers and 380/220 V Switchgears x - 1 550,000 110,000 440,000 110,000 440,000 550,000 20 6.5 Emergency Diesel Generator Set x - 1 120,000 18,000 102,000 18,000 102,000 120,000 15 6.6 Cabling, Earthing & Lighting Systems x - 1 330,000 66,000 264,000 66,000 264,000 330,000 20 6.6 10 kV LCI (Start-Up Equipment) x - 2 1,340,000 268,000 1,072,000 536,000 2,144,000 2,680,000 20

TOTAL Electrical Equipment Rehabilitation 3,382,200 17,245,800 20,628,000

(E) INSTRUMENTATION AND CONTROL REHABILITATION

7 Pump House Instrumentation and Control Equipment 7.1 Field Instrumentation, Control System and SCADA x - 1 160,000 32,000 128,000 32,000 128,000 160,000 20 7.2 Ultrasonic Discharge Flow Measurement, dia. 2440 mm x - 10 25,000 5,000 20,000 50,000 200,000 250,000 20 7.3 Fire Detection and Alarm System x - 1 20,000 4,000 16,000 4,000 16,000 20,000 20 7.4 Telecommunication System and Equipment x - 1 50,000 10,000 40,000 10,000 40,000 50,000 20

TOTAL Instrumentation and Control Rehabilitation 96,000 384,000 480,000

(F) CIVIL STRUCTURE REHABILITATION

8 Construction and Renovation Works 8.1 Earth Works x - 1 29,000 20,300 8,700 20,300 8,700 29,000 70 8.2 Civil and Erection Works x - 1 2,525,000 1,767,500 757,500 1,767,500 757,500 2,525,000 70

TOTAL Civil Structure Rehabilitation 1,787,800 766,200 2,554,000

Total Rehabilitation Mechanical and Electrical Equipment 10,261,440 52,190,160 62,451,600 Applied Contingencies (10%) 1,026,144 5,219,016 6,245,160 Sum Rehabilitation Mechanical and Electrical Equipment 11,287,584 57,409,176 68,696,760

Total Rehabilitation Civil Structure 1,787,800 766,200 2,554,000 Applied Contingencies (7%) 125,146 53,634 178,780 Sum Rehabilitation Civil Structure 1,912,946 819,834 2,732,780 GRAND TOTAL KIZIL-TEPA PUMP STATION REHABILITATION 13,200,530 58,229,010 71,429,540 ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/16/2013 Technical Feasibility Report

KIZIL-TEPA PUMPING STATION PLANT REHABILITATION (PARTIAL REHABILITATION)

ITEM / SYSTEM / EQUIPMENT COST [US$] (A) MECHANICAL EQUIPMENT REHABILITATION 28,114,000 (B) BUILDING SERVICES REHABILITATION 490,000 (C) HYDRAULIC STEEL STRUCTURE REHABILITATION 1,324,000 (D) ELECTRICAL EQUIPMENT REHABILITATION 17,352,000 (E) INSTRUMENTATION AND CONTROL REHABILITATION 430,000 Total Kizil-Tepa Pump Station Rehabilitation 47,710,000 Applied Contingencies (10%) 4,771,000 Sum Kizil-Tepa Pump Station Rehabilitation 52,481,000 (F) CIVIL STRUCTURE REHABILITATION 2,554,000 Total Kizil-Tepa Pump Station Rehabilitation 2,554,000 Applied Contingencies (7%) 178,780 Sum Kizil-Tepa Pump Station Rehabilitation 2,732,780 GRAND TOTAL KIZIL-TEPA PUMP STATION REHABILITATION 55,213,780 ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/16/2013 Technical Feasibility Report

KIZIL-TEPA PUMPING STATION PLANT REHABILITATION

Cost Estimates by Expenditure Category (1) rehabilitation/modernization/renewal of the exiting equipment/system/structure Exchange Rate: 1 US$ =2096 SOUM (2) replacement of the exiting equipment/system/structure

Item No. Item Description Unit Quantity Total Unit Rate Unit Rate Unit Rate Total Price Total Price Total Price Foreign Foreign Local Foreign Local Foreign % Currency Currency Currency Currency Currency Currency Local/Foreign (1) (2) US$ US$ US$ US$ US$ US$ Portion

(A) MECHANICAL EQUIPMENT REHABILITATION

1 Pump House Mechanical Equipment 1.2 Main Pump Units (No. 1-4), centrifugal type (H=45m, Q=13.3m³/s, n=250min^-1) incl. Model x - 4 2,685,000 402,750 2,282,250 1,611,000 9,129,000 10,740,000 15 Tests, Spare Parts 1.1 Main Pump Units (No. 5-10), centrifugal type (H=70m, Q=12m³/s, n=250min^-1) incl. Model x - 4 3,556,000 533,400 3,022,600 2,133,600 12,090,400 14,224,000 15 Tests, Spare Parts 1.3 Main Discharge Shut-Off Valves (DN2200, PN10) incl. Hydraulic Units x - 8 260,000 52,000 208,000 416,000 1,664,000 2,080,000 20 1.4 Technical Water Supply System incl. Shaft Seal Water Supply x - 1 310,000 62,000 248,000 62,000 248,000 310,000 20 1.5 Oil Handling System incl. Compact Mobile Purification Unit x - 1 130,000 26,000 104,000 26,000 104,000 130,000 20 1.6 Low Pressure Compressed Air System x - 1 45,000 9,000 36,000 9,000 36,000 45,000 20 1.7 Emergency Dewatering System x - 1 90,000 18,000 72,000 18,000 72,000 90,000 20 1.8 Drainage and Dewatering System x - 1 210,000 42,000 168,000 42,000 168,000 210,000 20

2 Cranes and Lifting Equipment 2.1 Pump House Overhead Crane 100/20 tons x - 1 180,000 36,000 144,000 36,000 144,000 180,000 20 2.2 Overhead Crane 15 tons, Butterfly Valves x - 1 35,000 7,000 28,000 7,000 28,000 35,000 20 2.3 Monorail Lifting Equipment 2 x 3 tons for Main Pumps x - 1 40,000 8,000 32,000 8,000 32,000 40,000 20 2.4 Elevator 500 kg x - 1 30,000 6,000 24,000 6,000 24,000 30,000 20

TOTAL Mechanical Equipment Rehabilitation 4,374,600 23,739,400 28,114,000

(B) BUILDING SERVICES REHABILITATION

3 Building Service Equipment 3.1 Water Supply System x - 1 110,000 22,000 88,000 22,000 88,000 110,000 20 3.2 Air Conditioning and Ventilation System (HVAC) x - 1 310,000 62,000 248,000 62,000 248,000 310,000 20 3.3 Fire Fighting Equipment x - 1 25,000 5,000 20,000 5,000 20,000 25,000 20 3.4 Workshop Facilities x - 1 45,000 9,000 36,000 9,000 36,000 45,000 20

TOTAL Building Service Equipment Rehabilitation 98,000 392,000 490,000

(C) HYDRAULIC STEEL STRUCTURE REHABILITATION

4 Forebay and Intake Hydraulic Steel Structure Equipment 4.1 Intake Trash Rack Cleaning Machine x - 1 250,000 50,000 200,000 50,000 200,000 250,000 20 4.2 Intake Trash Rack Screens (3,5 x 8 m) x - 14 21,000 4,200 16,800 58,800 235,200 294,000 20 4.3 Gantry Crane Forebay (5 ton) x - 1 50,000 10,000 40,000 10,000 40,000 50,000 20 4.4 Gantry Crane Intake (16/5 ton) x - 1 60,000 12,000 48,000 12,000 48,000 60,000 20 4.5 Intake Slide Gates incl. Electrical Drive x - 10 55,000 11,000 44,000 110,000 440,000 550,000 20 5 Discharge Pipe System 5.1 Discharge Pipe No. 1 - 4 , 4 x dia. 2440 mm incl. Disassembly of Pipe (total pipe weight 170 x m 0 8,200 1,640 6,560 0 0 0 20 ton) 5.2 Discharge Pipe No. 4 - 10 , 6 x dia. 2440 mm incl. Disassembly of Pipe (total pipe weight x m 0 6,750 1,350 5,400 0 0 0 20 210 ton) 5.3 Discharge Pipe Corrossion Repair Works Kharakur Branch, 2 x dia. 3240 mm x m 0 340 136 204 0 0 0 40 5.4 Air Breaker Valves x - 8 15,000 3,000 12,000 24,000 96,000 120,000 20

TOTAL Hydraulic Steel Structure Rehabilitation 264,800 1,059,200 1,324,000

(D) ELECTRICAL EQUIPMENT REHABILITATION

6 Pump House Electrical Equipment 6.1 Main Electrical Motors, synchronous type (P=8500kW, 10kV, n=250min^-1) incl. Spare x - 4 1,230,000 184,500 1,045,500 738,000 4,182,000 4,920,000 15 Parts (No. 1 - 4) 6.2 Main Electrical Motors, synchronous type (P=12500kW, 10kV, n=250min^-1) incl. Spare x - 4 1,638,000 245,700 1,392,300 982,800 5,569,200 6,552,000 15 Parts (No. 5 - 10) 6.3 6 kV Switchgear Installations x - 1 2,200,000 440,000 1,760,000 440,000 1,760,000 2,200,000 20 6.4 LV Transformers and 380/220 V Switchgears x - 1 550,000 110,000 440,000 110,000 440,000 550,000 20 6.5 Emergency Diesel Generator Set x - 1 120,000 18,000 102,000 18,000 102,000 120,000 15 6.6 Cabling, Earthing & Lighting Systems x - 1 330,000 66,000 264,000 66,000 264,000 330,000 20 6.6 10 kV LCI (Start-Up Equipment) x - 2 1,340,000 268,000 1,072,000 536,000 2,144,000 2,680,000 20

TOTAL Electrical Equipment Rehabilitation 2,890,800 14,461,200 17,352,000

(E) INSTRUMENTATION AND CONTROL REHABILITATION

7 Pump House Instrumentation and Control Equipment 7.1 Field Instrumentation, Control System and SCADA x - 1 160,000 32,000 128,000 32,000 128,000 160,000 20 7.2 Ultrasonic Discharge Flow Measurement, dia. 2440 mm x - 8 25,000 5,000 20,000 40,000 160,000 200,000 20 7.3 Fire Detection and Alarm System x - 1 20,000 4,000 16,000 4,000 16,000 20,000 20 7.4 Telecommunication System and Equipment x - 1 50,000 10,000 40,000 10,000 40,000 50,000 20

TOTAL Instrumentation and Control Rehabilitation 86,000 344,000 430,000

(F) CIVIL STRUCTURE REHABILITATION

8 Construction and Renovation Works 8.1 Earth Works x - 1 29,000 20,300 8,700 20,300 8,700 29,000 70 8.2 Civil and Erection Works x - 1 2,525,000 1,767,500 757,500 1,767,500 757,500 2,525,000 70

TOTAL Civil Structure Rehabilitation 1,787,800 766,200 2,554,000

Total Rehabilitation Mechanical and Electrical Equipment 7,714,200 39,995,800 47,710,000 Applied Contingencies (10%) 771,420 3,999,580 4,771,000 Sum Rehabilitation Mechanical and Electrical Equipment 8,485,620 43,995,380 52,481,000

Total Rehabilitation Civil Structure 1,787,800 766,200 2,554,000 Applied Contingencies (7%) 125,146 53,634 178,780 Sum Rehabilitation Civil Structure 1,912,946 819,834 2,732,780 GRAND TOTAL KIZIL-TEPA PUMP STATION REHABILITATION 10,398,566 44,815,214 55,213,780 ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/9/2013 Technical Feasibility Report

KIZIL-TEPA AUX. PUMPING STATION PLANT REHABILITATION

ITEM / SYSTEM / EQUIPMENT COST [US$] (A) MECHANICAL EQUIPMENT REHABILITATION 9,491,000 (B) BUILDING SERVICES REHABILITATION 340,000 (C) HYDRAULIC STEEL STRUCTURE REHABILITATION 53,801,000 (D) ELECTRICAL EQUIPMENT REHABILITATION 10,990,000 (E) INSTRUMENTATION AND CONTROL REHABILITATION 528,000 Total Kizil-Tepa Aux. Pump Station Rehabilitation 75,150,000 Applied Contingencies (10%) 7,515,000 Sum Kizil-Tepa Aux. Pump Station Rehabilitation 82,665,000 (F) CIVIL STRUCTURE REHABILITATION 2,070,000 Total Kizil-Tepa Aux. Pump Station Rehabilitation 2,070,000 Applied Contingencies (7%) 144,900 Sum Kizil-Tepa Aux. Pump Station Rehabilitation 2,214,900 GRAND TOTAL KIZIL-TEPA AUX. PUMP STATION REHABILITATION 84,879,900 ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/9/2013 Technical Feasibility Report

KIZIL-TEPA AUX. PUMPING STATION PLANT REHABILITATION

Cost Estimates by Expenditure Category (1) rehabilitation/modernization/renewal of the exiting equipment/system/structure Exchange Rate: 1 US$ =2096 SOUM (2) replacement of the exiting equipment/system/structure

Item No. Item Description Unit Quantity Total Unit Rate Unit Rate Unit Rate Total Price Total Price Total Price Foreign Foreign Local Foreign Local Foreign % Currency Currency Currency Currency Currency Currency Local/Foreign (1) (2) US$ US$ US$ US$ US$ US$ Portion

(A) MECHANICAL EQUIPMENT REHABILITATION

1 Pump House Mechanical Equipment 1.1 Main Pump Units, centrifugal type (H=80m, Q=1.75m³/s, n=750min^-1) incl. Spare Parts x - 26 290,000 43,500 246,500 1,131,000 6,409,000 7,540,000 15

1.2 Main Discharge Shut-Off Valves (DN800, PN16) incl. Electrical Actuator x - 30 20,000 3,000 17,000 90,000 510,000 600,000 15 1.3 Main Discharge Check Valves (DN800, PN16) incl. Damping Device x - 30 25,000 3,750 21,250 112,500 637,500 750,000 15 1.4 Technical Water Supply System incl. Shaft Seal Water Supply x - 1 230,000 46,000 184,000 46,000 184,000 230,000 20 1.5 Oil Handling System incl. Compact Mobile Purification Unit x - 1 65,000 13,000 52,000 13,000 52,000 65,000 20 1.6 Low Pressure Compressed Air System x - 1 50,000 10,000 40,000 10,000 40,000 50,000 20 1.7 Drainage and Dewatering System x - 1 160,000 32,000 128,000 32,000 128,000 160,000 20

2 Cranes and Lifting Equipment 2.1 Pump House Overhead Crane 20/5 tons x - 2 38,000 7,600 30,400 15,200 60,800 76,000 20 2.2 Monorail Lifting Equipment 1 tons for Drainage Room x - 2 10,000 2,000 8,000 4,000 16,000 20,000 20

TOTAL Mechanical Equipment Rehabilitation 1,453,700 8,037,300 9,491,000

(B) BUILDING SERVICES REHABILITATION

3 Building Service Equipment 3.1 Water Supply System x - 1 110,000 22,000 88,000 22,000 88,000 110,000 20 3.2 Air Conditioning and Ventilation System (HVAC) x - 1 160,000 32,000 128,000 32,000 128,000 160,000 20 3.3 Fire Fighting Equipment x - 1 25,000 5,000 20,000 5,000 20,000 25,000 20 3.4 Workshop Facilities x - 1 45,000 9,000 36,000 9,000 36,000 45,000 20

TOTAL Building Service Equipment Rehabilitation 68,000 272,000 340,000

(C) HYDRAULIC STEEL STRUCTURE REHABILITATION

4 Forebay and Intake Hydraulic Steel Structure Equipment 4.1 Intake Trash Rack Cleaning Machine x - 1 250,000 50,000 200,000 50,000 200,000 250,000 20 4.2 Intake Trash Rack Screens incl. Embedded Parts (two sets) x - 1 35,000 7,000 28,000 7,000 28,000 35,000 20 4.3 Intake Stoplogs incl. Embedded Parts x - 2 120,000 24,000 96,000 48,000 192,000 240,000 20

5 Discharge Pipe System 5.1 Pump Discharge Pipe No. 1 to 26, dia. 820 mm incl. Disassembly of Pipe (total pipe weight x m 100 1,460 292 1,168 29,200 116,800 146,000 20 19 ton) 5.2 Discharge Pipe 2 x dia. 2850 mm incl. Disassembly of Pipe dia. 3640 mm (total pipe weight x m 5,800 9,150 1,830 7,320 10,614,000 42,456,000 53,070,000 20 6970 ton) 5.3 Air Breaker Valves x - 4 15,000 3,000 12,000 12,000 48,000 60,000 20

TOTAL Hydraulic Steel Structure Rehabilitation 10,760,200 43,040,800 53,801,000 (D) ELECTRICAL EQUIPMENT REHABILITATION

6 Pump House Electrical Equipment 6.1 Main Electrical Motors, synchronous type (P=2000kW, 6kV, n=750min^-1) incl. Spare Parts x - 26 280,000 56,000 224,000 1,456,000 5,824,000 7,280,000 20

6.2 6 kV Switchgear Installations x - 1 1,510,000 302,000 1,208,000 302,000 1,208,000 1,510,000 20 6.3 LV Transformers and 380/220 V Switchgears x - 1 1,120,000 224,000 896,000 224,000 896,000 1,120,000 20 6.4 Emergency Diesel Generator Set x - 1 100,000 15,000 85,000 15,000 85,000 100,000 15 6.5 Cabling, Earthing & Lighting Systems x - 1 980,000 196,000 784,000 196,000 784,000 980,000 20

TOTAL Electrical Equipment Rehabilitation 2,193,000 8,797,000 10,990,000

(E) INSTRUMENTATION AND CONTROL REHABILITATION

7 Pump House Instrumentation and Control Equipment 7.1 Field Instrumentation, Control System and SCADA x - 1 130,000 26,000 104,000 26,000 104,000 130,000 20 7.2 Electromagnetic Flow Measurement, dia. 1200 mm (suction side) x - 26 13,000 2,600 10,400 67,600 270,400 338,000 20 7.3 Fire Detection and Alarm System x - 1 10,000 2,000 8,000 2,000 8,000 10,000 20 7.4 Telecommunication System and Equipment x - 1 50,000 10,000 40,000 10,000 40,000 50,000 20

TOTAL Instrumentation and Control Rehabilitation 105,600 422,400 528,000

(F) CIVIL STRUCTURE REHABILITATION

8 Construction and Renovation Works 8.1 Earth Works x - 1 370,000 259,000 111,000 259,000 111,000 370,000 70 8.2 Civil and Erection Works x - 1 1,700,000 1,190,000 510,000 1,190,000 510,000 1,700,000 70

TOTAL Civil Structure Rehabilitation 1,449,000 621,000 2,070,000

Total Rehabilitation Mechanical and Electrical Equipment 14,580,500 60,569,500 75,150,000 Applied Contingencies (10%) 1,458,050 6,056,950 7,515,000 Sum Rehabilitation Mechanical and Electrical Equipment 16,038,550 66,626,450 82,665,000

Total Rehabilitation Civil Structure 1,449,000 621,000 2,070,000 Applied Contingencies (7%) 101,430 43,470 144,900 Sum Rehabilitation Civil Structure 1,550,430 664,470 2,214,900 GRAND TOTAL KIZIL-TEPA AUX. PUMP STATION REHABILITATION 17,588,980 67,290,920 84,879,900 ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/9/2013 Technical Feasibility Report

KIZIL-TEPA AUX. PUMPING STATION PLANT REHABILITATION (PARTIAL REHABILITATION)

ITEM / SYSTEM / EQUIPMENT COST [US$] (A) MECHANICAL EQUIPMENT REHABILITATION 4,963,000 (B) BUILDING SERVICES REHABILITATION 340,000 (C) HYDRAULIC STEEL STRUCTURE REHABILITATION 585,000 (D) ELECTRICAL EQUIPMENT REHABILITATION 6,310,000 (E) INSTRUMENTATION AND CONTROL REHABILITATION 359,000 Total Kizil-Tepa Aux. Pump Station Rehabilitation 12,557,000 Applied Contingencies (10%) 1,255,700 Sum Kizil-Tepa Aux. Pump Station Rehabilitation 13,812,700 (F) CIVIL STRUCTURE REHABILITATION 2,070,000 Total Kizil-Tepa Aux. Pump Station Rehabilitation 2,070,000 Applied Contingencies (7%) 144,900 Sum Kizil-Tepa Aux. Pump Station Rehabilitation 2,214,900 GRAND TOTAL KIZIL-TEPA AUX. PUMP STATION REHABILITATION 16,027,600 ADB TA 7971 Uzbekistan – Amu Bukhara Irrigation System Rehabilitation Status: 7/9/2013 Technical Feasibility Report

KIZIL-TEPA AUX. PUMPING STATION PLANT REHABILITATION

Cost Estimates by Expenditure Category (1) rehabilitation/modernization/renewal of the exiting equipment/system/structure Exchange Rate: 1 US$ =2096 SOUM (2) replacement of the exiting equipment/system/structure

Item No. Item Description Unit Quantity Total Unit Rate Unit Rate Unit Rate Total Price Total Price Total Price Foreign Foreign Local Foreign Local Foreign % Currency Currency Currency Currency Currency Currency Local/Foreign (1) (2) US$ US$ US$ US$ US$ US$ Portion

(A) MECHANICAL EQUIPMENT REHABILITATION

1 Pump House Mechanical Equipment 1.1 Main Pump Units, centrifugal type (H=80m, Q=1.75m³/s, n=750min^-1) incl. Spare Parts x - 13 290,000 43,500 246,500 565,500 3,204,500 3,770,000 15

1.2 Main Discharge Shut-Off Valves (DN800, PN16) incl. Electrical Actuator x - 14 20,000 3,000 17,000 42,000 238,000 280,000 15 1.3 Main Discharge Check Valves (DN800, PN16) incl. Damping Device x - 14 25,000 3,750 21,250 52,500 297,500 350,000 15 1.4 Technical Water Supply System incl. Shaft Seal Water Supply x - 1 230,000 46,000 184,000 46,000 184,000 230,000 20 1.5 Oil Handling System incl. Compact Mobile Purification Unit x - 1 65,000 13,000 52,000 13,000 52,000 65,000 20 1.6 Low Pressure Compressed Air System x - 1 50,000 10,000 40,000 10,000 40,000 50,000 20 1.7 Drainage and Dewatering System x - 1 160,000 32,000 128,000 32,000 128,000 160,000 20

2 Cranes and Lifting Equipment 2.1 Pump House Overhead Crane 20/5 tons x - 1 38,000 7,600 30,400 7,600 30,400 38,000 20 2.2 Monorail Lifting Equipment 1 tons for Drainage Room x - 2 10,000 2,000 8,000 4,000 16,000 20,000 20

TOTAL Mechanical Equipment Rehabilitation 772,600 4,190,400 4,963,000

(B) BUILDING SERVICES REHABILITATION

3 Building Service Equipment 3.1 Water Supply System x - 1 110,000 22,000 88,000 22,000 88,000 110,000 20 3.2 Air Conditioning and Ventilation System (HVAC) x - 1 160,000 32,000 128,000 32,000 128,000 160,000 20 3.3 Fire Fighting Equipment x - 1 25,000 5,000 20,000 5,000 20,000 25,000 20 3.4 Workshop Facilities x - 1 45,000 9,000 36,000 9,000 36,000 45,000 20

TOTAL Building Service Equipment Rehabilitation 68,000 272,000 340,000

(C) HYDRAULIC STEEL STRUCTURE REHABILITATION

4 Forebay and Intake Hydraulic Steel Structure Equipment 4.1 Intake Trash Rack Cleaning Machine x - 1 250,000 50,000 200,000 50,000 200,000 250,000 20 4.2 Intake Trash Rack Screens incl. Embedded Parts (two sets) x - 1 35,000 7,000 28,000 7,000 28,000 35,000 20 4.3 Intake Stoplogs incl. Embedded Parts x - 2 120,000 24,000 96,000 48,000 192,000 240,000 20

5 Discharge Pipe System 5.1 Pump Discharge Pipe No. 1 to 26, dia. 820 mm incl. Disassembly of Pipe (total pipe weight x m 0 1,460 292 1,168 0 0 0 20 19 ton) 5.2 Discharge Pipe 2 x dia. 2850 mm incl. Disassembly of Pipe dia. 3640 mm (total pipe weight x m 0 9,150 1,830 7,320 0 0 0 20 6970 ton) 5.3 Air Breaker Valves x - 4 15,000 3,000 12,000 12,000 48,000 60,000 20

TOTAL Hydraulic Steel Structure Rehabilitation 117,000 468,000 585,000 (D) ELECTRICAL EQUIPMENT REHABILITATION

6 Pump House Electrical Equipment 6.1 Main Electrical Motors, synchronous type (P=2000kW, 6kV, n=750min^-1) incl. Spare Parts x - 13 280,000 56,000 224,000 728,000 2,912,000 3,640,000 20

6.2 6 kV Switchgear Installations x - 1 850,000 170,000 680,000 170,000 680,000 850,000 20 6.3 LV Transformers and 380/220 V Switchgears x - 1 1,120,000 224,000 896,000 224,000 896,000 1,120,000 20 6.4 Emergency Diesel Generator Set x - 1 100,000 15,000 85,000 15,000 85,000 100,000 15 6.5 Cabling, Earthing & Lighting Systems x - 1 600,000 120,000 480,000 120,000 480,000 600,000 20

TOTAL Electrical Equipment Rehabilitation 1,257,000 5,053,000 6,310,000

(E) INSTRUMENTATION AND CONTROL REHABILITATION

7 Pump House Instrumentation and Control Equipment 7.1 Field Instrumentation, Control System and SCADA x - 1 130,000 26,000 104,000 26,000 104,000 130,000 20 7.2 Electromagnetic Flow Measurement, dia. 1200 mm (suction side) x - 13 13,000 2,600 10,400 33,800 135,200 169,000 20 7.3 Fire Detection and Alarm System x - 1 10,000 2,000 8,000 2,000 8,000 10,000 20 7.4 Telecommunication System and Equipment x - 1 50,000 10,000 40,000 10,000 40,000 50,000 20

TOTAL Instrumentation and Control Rehabilitation 71,800 287,200 359,000

(F) CIVIL STRUCTURE REHABILITATION

8 Construction and Renovation Works 8.1 Earth Works x - 1 370,000 259,000 111,000 259,000 111,000 370,000 70 8.2 Civil and Erection Works x - 1 1,700,000 1,190,000 510,000 1,190,000 510,000 1,700,000 70

TOTAL Civil Structure Rehabilitation 1,449,000 621,000 2,070,000

Total Rehabilitation Mechanical and Electrical Equipment 2,286,400 10,270,600 12,557,000 Applied Contingencies (10%) 228,640 1,027,060 1,255,700 Sum Rehabilitation Mechanical and Electrical Equipment 2,515,040 11,297,660 13,812,700

Total Rehabilitation Civil Structure 1,449,000 621,000 2,070,000 Applied Contingencies (7%) 101,430 43,470 144,900 Sum Rehabilitation Civil Structure 1,550,430 664,470 2,214,900 GRAND TOTAL KIZIL-TEPA AUX. PUMP STATION REHABILITATION 4,065,470 11,962,130 16,027,600

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Appendix 10

Updated Economic and Financial Analysis Tables

Lahmeyer International in association with InfoCapital Group

InfoCapital Group Table 1: ABIS Irrigated Area (ha), by Irrigation System Administrations ISA District District District Municipality Total ha Bukhara Region 275,111 Amu – Karakul Alat Karakul Jondor 21,475 25,065 33,066 79,606 Shakrud – Dustlik Bukhara Kagan Karaul Bazar Bukhara city 27,967 18,845 16,078 2,350 65,240 Kharkur – Duoba Vobkent Peshku Romitan 24,792 22,756 27,241 74,789 Toshrabod - Jilvon Gidjuvon Shafirkan 27,074 28,402 55,476 Navoi Region Toshrabod – Urtachul Kizil Tepa Karmana 32,360 7,529 39,889 Total 315,000 Source: Amu Bukhara BISA Table 2 Part A Irrigated and Cropped Areas by ABIS Irrigation scheme - 2011. Hectares.

System District Irrigated area Cotton Wheat Veg Fodder Fruit Crop area Fallow Irrigable area Yamanjar Alat 620 250 158 135 115 42 700 4 624 Karakul 3,739 1,541 917 896 337 295 3,985 33 3,772 Total 4,360 1,791 1,075 1,031 452 337 4,685 36 4,396 Alat/ Karakul Alat 16,873 6,803 4,302 3,666 3,125 1,142 19,038 99 16,972 Karakul 19,641 8,093 4,815 4,706 1,770 1,548 20,931 172 19,813 Total 36,514 14,896 9,117 8,371 4,895 2,690 39,969 272 36,786 Jondor Bukhara 3,976 1,562 792 763 651 563 4,332 97 4,073 Jondor 20,163 8,785 3,800 3,434 3,172 1,893 21,085 864 21,027 Alat 3,786 1,527 965 823 701 256 4,272 22 3,809 Karakul 1,568 646 384 376 141 124 1,671 14 1,581 Total 29,493 12,520 5,942 5,396 4,666 2,836 31,360 997 30,490 Outside Study Area Total 70,367 29,208 16,134 14,797 10,012 5,863 76,014 1,305 71,672 Kizil Tepa 1/ Vobkent 20,168 8,166 5,874 4,018 2,416 1,794 22,268 54 20,222 Peshku 22,629 9,855 5,486 4,698 2,777 2,262 25,078 287 22,916 Gidjuvan 26,931 10,300 4,731 6,635 3,133 3,398 28,197 1,229 28,160 Shafirkan 28,047 10,220 6,644 5,345 6,644 3,229 32,082 814 28,861 Kizil Tepa 29,882 8,880 10,224 4,134 4,208 2,588 30,035 4,448 34,330 Karmana 8,258 2,775 3,467 540 1,506 495 8,783 0 8,258 Total 135,915 50,196 36,426 25,370 20,685 13,766 146,443 7,561 143,476 Kuyu Mazar Vobkent 4,554 1,844 1,326 907 546 405 5,028 12 4,566 Romitan 27,184 12,100 6,480 4,546 3,489 2,807 29,422 771 27,955 Bukhara 23,691 9,308 4,720 4,549 3,881 3,357 25,814 577 24,268 Kagan & city 18,819 7,120 5,176 2,533 4,252 1,569 20,650 319 19,138 Bukhara city 2,327 300 330 877 366 632 2,505 3 2,330 Jondor 12,542 5,465 2,364 2,136 1,973 1,178 13,115 537 13,079 Total 89,117 36,136 20,396 15,548 14,506 9,947 96,534 2,220 91,336 Karaul Bazar Karaul Bazar 15,907 5,715 6,335 1,105 4,476 186 17,817 970 16,877 Within Study Area Total 240,939 92,047 63,157 42,023 39,667 23,899 260,794 10,750 251,689 Total ABIS area Total 311,306 121,255 79,291 56,820 49,679 29,762 336,808 12,055 323,361 Source : District Agric Office/ABIS 1/ Only partially served in reduced cost option. Table 3 ABIS Cropping Patterns - 2011. % of irrigated area Cropped Cotton Wheat Veg Fodder Other Area Yamanjar 41% 25% 24% 10% 8% 107% Alat/ Karakul 41% 25% 23% 13% 7% 109% Jondor 42% 20% 18% 16% 10% 106% Kizil Tepa 1/ 37% 27% 19% 15% 10% 108% Kuyu Mazar 41% 23% 17% 16% 11% 108% Karaul Bazar 36% 40% 7% 28% 1% 112% Within Study Area 38% 26% 17% 16% 10% 108% Total ABIS area 39% 25% 18% 16% 10% 108% Source: ABIS Table 4: The ABMK System - Reach Lengths and Capacities in km and m3/s

Other Capacity Reach Cumulative Reach 3 name (m /s) length (km) length (km) Amu Darya River to Dvoynik ABMK 328 17 17 structure (PK 137) Dvoynik structure to first division ABMK (PK 828) - Northern branch 150 67 84 - Southern branch 135 66 150

First junction to Karaul Bazar offtake ABMK 236 41 191 Karaul Bazar offtake to Tudakul ABMK 212 29 220 diversion (Troynik – PK 1520)) Tudakul diversion to Kuyu Mazar PS ABMK 1 60 18 238 Kuyu Mazar PS to Zarafshan River, Shakhru Khachkab Diversion (PK 1796) d 100 10 248 branch Tudakul diversion to Kizil Tepa PS ABMK 2 152 38 286 Kizil Tepa PS to Zarafshan River - West branch to Kharkhur Kharkur Barrage 40 15 310 branch

- East branch to Tashrabad Shafrika Barrage, Rostguy & Jilvan n 69 27 328 branch Other short reaches (approx) 7 335

Source: Present Study 2013

Table 5: Main Pump Stations within the Study Area - Summary of Main Features

Pump Station Pumps Pump Installed Maximum Instal- Life-time Annual Power Vol. (nr) capacity total dynamic lation use up use (Ave Used (Total (m3/sec/p capacity lift (m) date to 2011 annual (Mwh/ Mm3/yr ump) (m3/s) (year) (Ave hr/ yr 2011) total hrs/ pump) 2011) pump) 1 Khamza 1 8+1 8.4 64 51 1963 201,000 4,300 159 700 2 Khamza 26+4 1.5 40 55 1982 28,000 930 6 25 Auxiliary Total 1+2 - - 104 - - - - 165 725 3 Khamza 2 9+1 15.5 135 54 1974 176,000 4,750 612 2,800 Total 1, 2, 3 - - 239 - - - - 777 3,525 4 Kuyu Mazar To Shakrud 3 20 60 24 1965 211,000 4,489 To Kuyu Mazar 117 1,400 3 20 40/60 20 1965 294,000 6,255 Res 5 Kuyu Mazar 12 3.3 35 24 2012 - - 39 460 Auxiliary Total 4+5 - - 135/155 - - - - 156 1,860 6 Kizil Tepa To Karkhur 4 15 46 48 1975 77,000 2,080 386 1,650 To Shafrikan 6 15 63 74 1975 120,000 3,250 7 Kizil Tepa 22+4 1.5 33 75 1982 21,000 700 23 90 Auxiliary Total 6+7 36 - 142 - - - - 409 1,740 8 Navoi 10+2 1.5 18 65 2013 47 160 Total 6, 7, 8 160 456 1,900 9 Drujba 12 1.5 10 58 1982 - - 13 60 10 Karaul 1997/2 5 4 22 56 - - 55 250 Bazar 012 Total 9+10 - - 32 - na - - 68 310

Total Stage 1 - - 239 - na - - 777 3,525 Total Stage 2/3 na Na 327/357 - na - - 680 4,070 Source: ABIS Table 6 Power consumption. Mwh/month. 2006-2011. Main Pump stations (including Kuyu Mazar Auxiliary, Navoi and Karaul Bazar)

Khamza 1 Total Khamza Total Kuyu Kizil Tepa Total Kizil Total Stage 1 and Karaul Total Karaul Pump Station Khamza 1 Khamza 2 Total Stage Kuyu Mazar Kuyu Mazar Kizil Tepa Navoi 1/ Total Stage 2 Drujba Total Auxiliary 1 Mazar Auxiliary Tepa 2 Bazar Bazar 1 Auxiliary

January 8,919 - 8,919 42,612 51,531 9,782 3,287 13,069 26,282 42 26,324 39,393 90,923 99 448 548 91,471 February 8,595 - 8,595 39,105 47,700 8,432 2,794 11,226 17,483 34 17,516 28,742 76,442 512 1,920 2,432 78,874 March 9,331 - 9,331 35,855 45,186 7,561 2,004 9,565 25,129 240 25,369 34,934 80,120 585 5,992 6,577 86,698 April 8,020 896 8,917 45,546 54,463 6,924 2,863 9,786 28,642 1,976 30,617 40,404 94,867 1,566 7,092 8,658 103,524 May 13,451 2,538 15,988 63,458 79,446 8,814 3,098 11,912 35,198 4,668 3,319 43,185 55,097 134,544 1,606 6,013 7,620 142,164 June 22,538 4,219 26,756 71,034 97,790 11,280 4,649 15,929 47,207 4,959 7,509 59,676 75,604 173,395 1,809 5,084 6,893 180,288 July 26,327 5,511 31,838 81,387 113,225 16,479 5,975 22,454 69,539 13,490 11,815 94,845 117,298 230,523 2,584 7,764 10,348 240,871 August 24,962 3,762 28,724 79,324 108,048 16,702 4,265 20,967 66,898 7,238 10,346 84,482 105,448 213,496 2,037 7,228 9,264 222,761 September 13,872 918 14,790 61,610 76,400 8,897 4,125 13,022 33,164 457 10,015 43,635 56,657 133,058 557 3,276 3,833 136,890 October 10,714 849 11,563 47,655 59,217 6,446 2,090 8,536 22,554 30 3,696 26,280 34,816 94,033 334 5,241 5,575 99,608 November 11,362 408 11,770 37,314 49,084 3,796 1,515 5,311 15,944 32 15,976 21,287 70,371 376 3,841 4,217 74,588 December 7,700 216 7,916 34,597 42,513 4,735 2,121 6,856 9,986 41 10,027 16,883 59,397 85 494 579 59,975 Total 165,791 19,317 185,107 639,497 824,605 109,847 38,786 148,633 398,025 33,207 46,700 477,931 626,564 1,451,169 12,150 54,393 66,543 1,517,712 Ave July/Aug 2006-2011 25,645 4,637 30,281 80,356 110,637 16,590 5,120 21,710 68,218 10,364 11,081 89,663 111,373 222,010 2,311 7,496 9,806 231,816

Ave m3/s in July/Aug 2006-2011 48 9 56 146 202 85 26 111 109 14 15 137 248 4 14 19 (24 hrs/day pumping) Average 2006-2011 165,791 19,267 185,057 639,336 824,393 109,863 38,786 148,649 398,025 33,106 46,700 477,830 626,480 1,450,873 12,051 54,293 66,344 1,517,217 Source: ABMK Note 1/ Monthly consumption estimated from 2009 actuals. Table 7 Energy Consumption and Cost, by Irrigation System. Average 2006-2011 use at 2013 financial prices.

Area Energy consumption. Energy Cost Irrigation System Irrigated area Stage 1 Stage 2/3 Total Per/ha Stage 1 Stage 2/3 Total Per ha Per ha US$ (official % in scheme ha % in total Mwh Mwh Mwh Mwh UZS m UZS m UZS m UZS m ex) Karaul Bazar 100% 15,907 7% 54,427 66,344 120,771 7.59 6,107 7,444 13,550 851.9 406 Kuyu Mazar 100% 89,117 37% 304,921 148,649 453,571 5.09 34,212 16,678 50,891 571.1 272 Kizil Tepa - Khakhur 33% 45,305 19% 155,015 113,552 268,567 5.93 17,393 12,741 30,133 665.1 317 - Shafrikan 61% 82,352 34% 281,775 288,635 570,409 6.93 31,615 32,385 64,000 777.2 371 - Navoi 6% 8,258 3% 28,255 75,643 103,899 12.58 3,170 8,487 11,657 1411.7 673 Kizil Tepa Total 135,915 56% 465,045 477,830 942,875 6.94 52,178 53,613 105,791 778.4 371 Total 240,939 100% 824,393 692,823 1,517,217 6.30 92,497 77,735 170,232 706.5 337 Source: Table 2 Table 6 Ex Rate 2096 Table 8 Current (2006-2011) and Future Energy Consumption and Pumped Volumes. Total Study Area. Reduced capacity Khamza 1 and partial rehabilitation of two Kizil Tepa PS. Present situation With-project Water use per Energy Pumping Reported Calculated Likely Likely New New Irrigated area With-project' ha 2/ Used Total cost Unit cost 1/ head volume efficiency check efficiency volume efficiency Mwh used efficiency factor Mwh UZS m UZS/kwh metres m3 m % m3 million % m3 m % Mwh ha m3'000/ha Stage 1 - Khamza 1 3/ 165,791 18,602 112.200 55 901 81% 896 72% 796 87% 157,865 95.2% - Khamza I Auxiliary 4/ 19,267 2,162 112.200 55 118 91% 117 72% 93 87% - 0.0% - Khamza 2 639,336 71,734 112.200 56 3,061 73% 3,058 72% 3,017 87% 526,684 82.4% Total Stage 1 824,393 92,497 4,080 4,071 3,906 684,549 Stage 2 - Karaul Bazar 54,293 6,092 112.200 60 292 86% 287 80% 266 80% 54,293 100.0% - Drujba 12,051 1,352 112.200 60 48 67% 49 80% 59 80% 12,051 100.0% Total Karaul Bazar 66,344 7,444 340 336 325 66,344 15,907 20.4 - Kuyu Mazar 109,863 12,327 112.200 20 1,449 72% 1,451 72% 1,451 87% 90,505 82.4% - Kuyu Mazar Auxiliary 38,786 4,352 112.200 20 405 57% 406 72% 512 87% 31,952 82.4% Total Kuyu Mazar 148,649 16,678 1,854 1,857 1,964 122,457 89,117 22.0 - Kizil Tepa 5/ 398,025 44,658 112.200 61 1,727 74% 1,772 72% 1,724 87% 283,627 103,257 16.3 - Kizil Tepa Auxiliary 6/ 33,106 3,714 112.200 75 95 60% 97 72% 117 87% 13,636 - Navoi 46,700 5,240 112.200 65 160 61% 160 61% 160 87% 32,487 8,258 19.4 69.6% Total Kizil Tepa 477,830 53,613 1,982 2,029 2,001 329,750 111,515 17.9 Total Stage 2 692,823 77,735 4,177 4,222 4,289 518,551

Total Stage 1 and 2 1,517,217 170,232 8,257 8,294 8,195 1,203,100 216,539

Source: ABMK Note 1/ July 2013 price.UZS/kwh 112.200 2/ includes volumes double pumped 3/ 'with-project' consumption separately calculated 4/ Assumes Khamza 1 Auxiliary ceases to function 5/ Assumes 'with-project' energy consumption reduced by 13.5% and irrigated area by 14,200 ha. 6/ Assumes energy consumption reduced by 50% and irrigated area by 10,000 ha Table 9 Main pump stations. Current non-energy O&M expenditure. UZS million

Capital Other 2009 2010 2011 Average 2009 2010 2011 Average Khamza 1 372 348 297 339 42 101 29 57 Khamza 1 Aux 88 113 143 115 3 28 7 13 Khamza 2 355 394 433 394 21 142 42 68 Kuyu Mazar 160 172 183 172 155 393 32 193 Kizil Tepa 368 383 368 373 778 75 - 284 Kizil Tepa Aux 144 133 147 141 572 625 - 399 Total 1,487 1,543 1,571 1,534 1,571 1,364 110 1,015

Total Capital and Other Salaries 2009 2010 2011 Average 2009 2010 2011 Khamza 1 414 449 326 396 165 Khamza 1 Aux 91 141 150 127 174 Khamza 2 376 536 475 462 205 Kuyu Mazar 315 565 215 365 124 Kizil Tepa 1,146 458 368 657 242 Kizil Tepa Aux 716 758 147 540 170 Total 3,058 2,907 1,681 2,549 1,080

Total pump repairs ABISOA 3,153 3,315 2,983 3,150 Source: ABMK Table 10 Farm holdings in Bukhara District. Areas (ha) and numbers of holdings

Within Bukhara District Total Agricultural Micro Small Large Total Ave size/ District Area holdings farms farms holdings holding ha nr nr nr nr ha Bukhara 27,390 369 159 11 539 50.8 Romitan 27,955 424 6 0 430 65.0 Jondor 34,106 327 183 0 510 66.9 Kagan 19,138 148 112 0 260 73.6 Vobkent 24,788 270 95 0 365 67.9 Peshku 22,916 203 203 2 408 56.2 Shafrikan 28,861 444 35 1 480 60.1 Gidjuvan 28,160 155 161 7 323 87.2 Karaul Bazar 16,877 56 84 0 140 120.6 Total 230,191 2,396 1,038 21 3,455 66.6 Source : District 'Passports' - statistical summaries Table 11 Poor Drainage & Salinity Areas and Amelioration Activities

Past & planned improvements Total Unsatisfactory Irrigated growing Amelioration LIP overall Area conditions programme 2013 programme

District ha ha ha ha Bukhara 27,390 3,100 5,226 4,000 Romitan 27,955 3,200 2,556 6,000 Jondor 34,106 4,000 3,600 32,000 Kagan 19,138 2,400 4,884 Vobkent 24,788 1,000 2,660 Peshku 22,916 1,800 4,540 Shafrikan 28,861 8,900 4,598 Gidjuvan 28,160 2,300 960 Kizil Tepa 30,688 na 2,395 Karmana 20,270 na 2,770 Karaul Bazar 16,877 800 2,184 Total 281,149 27,500 36,373 42,000 Sources: Agricultural Dept. and LIP Project Table 12 Crop Yields. Present & 'With-Project' tonnes/ha

Growing condition Good Marginal

Cotton 3.3 2.6 Wheat 6.0 4.5 Vegetables 13.6 10.0 Fruit 7.0 4.0 Maize silage 27.0 18.0 Source: District Agric Office. Bukhara. Navoi

Source: Consultants estimates Table 13 Summary of Agricultural Produce and Input Prices. @ constant 2012 economic and financial prices. UZS/unit Unit Financial Economic Unit Financial Economic Agricultural outputs 2012 2015-2020 Agricultural inputs 2012 2015-2020 Crop Seed cotton kg 885 1,730 Spraying ha 10,000 12,000 Wheat kg 380 558 Furrow creation ha 45,000 54,000 Vegetables kg 500 500 Cultivating/fertilizing ha 35,000 42,000 Fruit kg 800 800 Fertilising - single pass ha 24,000 28,800 Maize silage kg 175 175 Rolling ha 15,000 18,000 Agricultural inputs Harvesting - wheat ha 160,000 192,000 Planting material Cotton kg 1,650 1,650 Harvesting - silage ha 60,000 72,000 Wheat kg 705 705 Harvesting - general ha 50,000 60,000 Vegetables kg 40,000 40,000 Chopping cotton stalks ha 6,500 7,800 Fruit kg 1 1 Transport to field ha 10,000 12,000 Fodder kg 4,000 4,000 Transport from field ton 17,000 20,400 Fertilizers Urea kg 1,160 867 Transport to market ton 60,000 72,000 TSP kg 1,950 1,040 Fuel litre 1,700 2,040 KCl kg 1,170 940 Equipment Bags & packaging lumpsum 1,000 1,000 Carbamide kg 400 400 Tools & equipment ha 10,000 10,000 Compost ton 12,000 12,000 Labour Male/female workday 12,000 9,600 Farm yard manure ton 35,000 35,000 Cotton harvest ton 180,000 150,000 Agrochemicals herbicide lumpsum 10,000 10,000 Other costs WUA ha 20,000 20,000 insecticide lumpsum 10,000 10,000 Pumping ha 30,000 30,000 general lumpsum 25,000 25,000 Interest ha 3% 0% biological control lumpsum 10,000 10,000 Contingencies ha 10% 10% Mechanisation Land levelling ha 250,000 300,000 Land tax lumpsum/ha 50,000 0 Manure application ha 56,000 67,200 Administration tax lumpsum/ha 23,000 0 Ploughing ha 109,000 130,800 Labour tax tonne 30,000 0 Chisel ploughing ha 36,000 43,200 Exchange rate UZS per 1 US$ (July 2013) 2096 2760 Irrig canal formation ha 28,000 33,600 Machinery factor 120% Basin formation ha 17,000 20,400 Shadow labour factor 80% Cultivating ha 51,000 61,200 Electricity (UZS & US $)/kwh 112.2 0.05353053 Planting - cotton ha 17,000 20,400 Marginal area % 5% Planting - wheat ha 15,000 18,000 Scf 80% Planting - other ha 50,000 60,000 Source: Field data. World Bank price projections. Table A.1 Table A.2 Table 14 Summary of Net Crop Returns. Present and Future 'With-Project'. @ constant 2012 financial and economic prices. UZS'000 /ha/crop season

Financial Economic Land condition good marginal good marginal

Cotton 448 205 3,570 2,668 Wheat 807 378 1,892 1,164 Vegetables 2,418 1,073 2,608 1,236 Fruit 2,283 1,010 2,532 1,120 Fodder 2,173 1,056 1,977 930

Source. Table A.3 Table 15 Project Area. Summary of Current Cropping & Net Income UZS million (economic)

Kuyu Mazar Kizil Tepa Karau Bazar Total

Irrigated Area ('000 ha) 89.1 135.9 15.9 240.9

Cropping Pattern (%) - Cotton 41% 37% 36% 38% - Fodder 16% 15% 28% 16% - Vegetables 17% 19% 7% 17% - Fruit 11% 10% 1% 10% - Winter wheat 23% 27% 40% 26% Total 108% 108% 112% 108%

Cropped Areas ('000ha) - Cotton 36.1 50.2 5.7 92.0 - Fodder 14.5 20.7 4.5 39.7 - Vegetables 15.5 25.4 1.1 42.0 - Fruit 9.9 13.8 0.2 23.9 - Winter wheat 20.4 36.4 6.3 63.2 Total 96.5 146.4 17.8 260.8

Net value of production (UZS million) - Cotton 127,393 176,957 20,147 324,497 - Fodder 27,917 39,809 8,614 76,340 - Vegetables 39,481 64,421 2,806 106,708 - Fruit 24,483 33,881 458 58,821 - Winter wheat 37,842 67,584 11,754 117,180 Total 257,116 382,652 43,779 683,547 Crop production ('000 tons) - cotton 116.6 162.0 17.7 296.29 - wheat 120.8 215.8 37.5 374.20

Sources: Table A.30 Table A.33 Table A.34 Table A.35 Table 16 Capital Cost Summary @ constant 2012 financial prices. US$ million Excluding discharge pipes in all PS except Khamza 1, and covering partial rehabilitation of two Kizil Tepa PS. Component Pump Stations Management Khamza 1 Kuyu Mazar Khamza 2 Tepa Kizil Tepa Kizil Aux

new rehab rehab rehab rehab & PIU PMO Consultancy & SCADA DSS FarmsPilot ABMKrehabilitation Total1 Option Civil Works - earth works 13.31 0.34 0.05 0.03 0.37 0.00 0.00 0.00 0.13 3.15 17.37 - construction 15.31 2.32 1.30 2.53 1.70 0.00 0.00 0.00 0.20 1.66 25.01 Sub-total civils 28.62 2.66 1.34 2.55 2.07 0.00 0.00 0.00 0.32 4.81 42.39 Equipment - Mechanical 24.34 13.38 42.24 28.11 4.96 0.00 0.00 0.00 0.00 0.00 113.03 - Anciliary systems 1.01 0.36 0.52 0.49 0.34 0.00 0.00 0.00 0.00 0.00 2.72 - Hydraulic steel structures 19.27 0.99 1.20 1.32 0.59 0.00 0.00 0.00 0.00 2.14 25.51 - Electrical equipment 18.38 8.12 21.86 17.35 6.31 0.00 0.00 0.00 0.00 0.37 72.39 - Instrumentation 0.42 0.41 0.48 0.43 0.36 0.00 0.00 0.00 0.00 0.02 2.11 - Other equipment 0.00 0.00 0.00 0.00 0.00 0.02 0.04 0.83 0.33 0.00 1.22 - Vehicles 0.00 0.00 0.00 0.00 0.00 0.04 0.22 0.00 0.00 0.00 0.26 Sub-total equipment 63.42 23.25 66.30 47.71 12.56 0.06 0.25 0.83 0.33 2.52 217.23 Training, Capacity Building & Studies Workshops etc 0.00 0.00 0.00 0.00 0.00 0.00 0.50 0.06 0.905 0.00 1.47 Demonstration farming operations 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.193 0.00 0.19 Sub-total training etc 0.00 0.00 0.00 0.00 0.00 0.00 0.50 0.06 1.10 0.00 1.66 Consulting Services - international 0.00 0.00 0.00 0.00 0.00 0.00 4.28 0.36 0.00 0.00 4.64 - local 0.00 0.00 0.00 0.00 0.00 0.00 2.04 0.08 0.00 0.00 2.12 - other 0.00 0.00 0.00 0.00 0.00 0.00 1.35 0.01 0.00 0.00 1.36 Sub-total consultancy 0.00 0.00 0.00 0.00 0.00 0.00 7.68 0.45 0.00 0.00 8.12 Project Management and Monitoring 0.00 0.00 0.00 0.00 0.00 1.14 0.47 0.11 0.00 0.00 1.72

Subtotal management 0.00 0.00 0.00 0.00 0.00 1.14 0.47 0.11 0.00 0.00 1.72

Total Capital Costs 92.04 25.91 67.64 50.26 14.63 1.19 8.90 1.45 1.75 7.33 271.11 Physical contingencies civils- rate 7% 7% 7% 7% 7% 0% 0% 0% 10% 10% Physical contingencies - value 2.00 0.19 0.09 0.18 0.14 0.00 0.00 0.00 0.03 0.48 3.12 Physical contingencies non civils - rate 10% 10% 10% 10% 10% 8% 8% 10% 10% 10% Physicals contingencies - value 6.34 2.33 6.63 4.77 1.26 0.10 0.71 0.15 0.14 0.25 22.67 Total Physical contingencies 8.34 2.51 6.72 4.95 1.40 0.10 0.71 0.15 0.18 0.73 25.79 Total Base cost incl physical contingencies 100.38 28.42 74.37 55.21 16.03 1.29 9.61 1.60 1.93 8.06 296.91 Price contingencies rate forex 8.0% 8.0% 8.0% 8.0% 8.0% 8.0% 8.0% 8.0% 8.0% 8.0% Price contingencies rate local 7.0% 7.0% 7.0% 7.0% 7.0% 7.0% 7.0% 7.0% 7.0% 7.0% Price contingencies rate combined 7.7% 7.8% 7.8% 7.8% 7.7% 7.0% 7.6% 7.8% 7.2% 7.5% Total price contingencies 7.05 2.02 5.30 3.93 1.13 0.08 0.68 0.11 0.13 0.55 20.98 Total base cost inc all contingencies 107.43 30.44 79.67 59.14 17.16 1.37 10.29 1.71 2.06 8.61 317.88 Table 17 'With-Project' Pump Station Non-Energy O&M Costs @ constant 2012 financial prices. Reduced capacity Khamza 1 PS, Discharge pipes only at Khamza 1 and partial rehabilitation of both Kizil Tepa PS. US$ million Kuyu Khamza Kizil Kizil % rate Khamza 1 Total Mazar II Tepa Tepa Aux Civil Works - structures 1% 0.15 0.02 0.01 0.03 0.02 0.23 Equipment - Mechanical 2% 0.49 0.27 0.84 0.56 0.10 2.26 - Anciliary systems 2% 0.02 0.01 0.01 0.01 0.01 0.05 - Hydraulic steel structures 2% 0.39 0.02 0.02 0.03 0.01 0.47 - Electrical equipment 2% 0.37 0.16 0.44 0.35 0.13 1.44 - Instrumentation 2% 0.01 0.01 0.01 0.01 0.01 0.04 Sub-total 1.27 0.47 1.33 0.95 0.25 4.26 Total 1.42 0.49 1.34 0.98 0.27 4.50 Periodic additional (8 years) 3% 1.90 0.70 1.99 1.43 0.38 6.40 Source : Consultants estimates Table 18 Capital Cost Summary @ constant 2012 economic prices. US$ million Excluding discharge pipes in all PS except Khamza 1, and covering partial rehabilitation of two Kizil Tepa PS. Year 1 2 3 4 5 6 7 Total Khamza 1 new 0.0 0.0 25.4 28.4 19.2 6.9 0.0 79.9 Kuyu Mazar rehab 0.0 0.0 5.1 12.4 6.2 0.6 0.0 24.3 Khamza 2 rehab 0.0 0.0 14.5 31.4 17.6 1.6 0.0 65.1 Kizil Tepa rehab 0.0 0.0 10.4 23.6 12.7 1.1 0.0 47.8 Kizil Tepa Auxiliary rehab 0.0 0.0 2.1 5.7 2.5 0.2 0.0 10.5 ABMK rehabilitation 0.0 0.0 0.0 0.9 2.8 1.8 0.0 5.6 DSS and SCADA 0.0 0.0 0.0 1.4 0.0 0.0 0.0 1.4 Pilot Farms 0.0 0.5 0.6 0.3 0.1 0.0 0.0 1.5 Consultancy 1.4 1.5 1.4 1.5 0.9 0.9 0.0 7.8 PMO/PIU 0.2 0.1 0.1 0.1 0.1 0.1 0.0 1.0 Total Base Cost 1.6 2.2 59.6 105.8 62.3 13.3 0.1 244.8 Physical Contingencies 0.2 0.2 5.7 10.1 6.2 1.3 0.0 23.8 Total Cost 1.8 2.4 65.3 115.9 68.5 14.6 0.1 268.6 Source : Table A.41

Table 19: Base Case and Sensitivity Analysis – EIRR % Case Gradual Pump Total Pump Decline Scenario Failure (base case) Scenario Base Case 12.2 18.4 Electricity price : - US$ 0.075/kwh 11 16.5 - US$ 0.100/kwh 9.4 13.9 Capital costs : - Increased to 110% 10.7 17.5 - Increased to 120% 9.4 16.6 Cotton price : - Increased to 110% 13.3 19.7 - Decreased to 90% 11 16.9 Pump capacity decline rate: - Reduced from 5% to 3% 7 na Onset of first year of decline - Advanced by 1 year 11.1 na - Advanced by 2 years 9.9 na - Advanced by 3 years 8.6 na na = not applicable. Table 20 Crop returns per ha. @ constant 2012 financial UZS'000 Land condition good marginal Cotton 448 205 Wheat 807 378 Vegetables 2,418 1,073 Fruit 2,283 1,010 Fodder 2,173 1,056 Source. Table A.3 Table 21 Crop returns per average cropped ha @ constant 2012 financial UZS'000 Good Land Cotton Wheat Vegetables Fodder Perennial Total Return/ha 448 807 2,418 2,283 2,283 Kizil Tepa 157 206 429 330 220 1,341 Kuyu Mazar 172 176 401 353 242 1,344 Karaul Bazar 153 305 160 610 25 1,253 Average 163 201 399 359 215 1,336 Marginal Land Cotton Wheat Vegetables Fodder Perennial Total Return/ha 205 378 1,073 1,056 1,010 Kizil Tepa 4 5 10 8 5 32 Kuyu Mazar 4 4 9 9 6 32 Karaul Bazar 4 8 4 15 1 30 Average 4 5 9 9 5 32 All Land Cotton Wheat Vegetables Fodder Perennial Total Kizil Tepa 161 211 439 338 225 1,373 Kuyu Mazar 177 180 410 362 248 1,376 Karaul Bazar 156 313 163 625 26 1,284 Average 167 205 408 368 220 1,368 Source: Consultant's estimates. Table 3 Table A.3 Table 22 Average annual financial returns per farm @ constant 2012 financial UZS'000 Farm size (ha) 50 100 200 Kizil Tepa 68,663 137,325 274,651 Kuyu Mazar 68,803 137,605 275,211 Karaul Bazar 64,194 128,388 Average 68,403 136,805 274,893 - - - Source : Table 21 Table 23 Total With-Project saved Financial Farm Returns & Manual Wages. Reduced Cost Option

Year 1 5 10 15 20 25 Total Farm returns 25 years Irrigated area WOP ha '000 241 213 154 111 77 50 Return/ha/yr UZS '000 1,368 1,368 1,368 1,368 1,368 1,368 Total WOP return/yr UZS billion 330 291 211 152 105 69 4,703 Irrigated area WP ha '000 241 213 210 210 210 210 Return/ha/yr UZS'000 1,368 1,368 1,368 1,368 1,368 1,368 Total WP return/yr UZS billion 330 291 287 287 287 287 7,315 Net WP saved income/yr UZS billion - - 76 135 182 218 2,612 Net WP saved income/yr US$ million - - 36 64 87 104 1,246 Labour (manual) WOP Labour use workdays million 13 12 8 6 4 3 189 WOP Labour wages UZS/yr 13 13 13 13 13 13 13 Total WOP wages UZS billion 168 149 108 78 54 35 2,401 WP Labour use workdays million 13 12 12 12 12 12 294 WP Labour wages UZS/yr 13 13 13 13 13 13 13 Total WP wages UZS billion 168 149 146 146 146 146 3,735 Net WP saved wages UZS billion - - 39 69 93 111 1,334 Net WP saved wages/yr US$ million - - 18 33 44 53 636 Source : Consultants Estimates Table A.3 Table A.19

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Appendix 11

Updated Supporting Tables for Economic and Financial Analysis

Lahmeyer International in association with InfoCapital Group

InfoCapital Group Table A.1 (a) Border Parity Price Calculations for Cotton - @ 2012 economic prices

Export/Import Substitute Note: Export Indicator product location 1/ Quality of Indicator product 2/ 2012 2015 2020 World price Jan-Aug 2012 3/ = 2,040 Indicator price - 2005 base 4/ = 1,660 1,710 1,610 Indicator price - 2012 base 6/ = 2,002 2,062 1,942 Quality differential (between Uzbek and Indicator product) 5/ x 1.0 1.0 1.0

lint Equivalent value of Uzbek product at transit port 7/ = 2,002 2,062 1,942

US$/ton Assumed transit port China Freight & insurance (between China port and Uzbek border) - 75 75 75 Value at Uzbek border = 1,927 1,987 1,867 Value at Uzbek border 8/ = 5,318 5,485 5,152 Uzbekistan border charges - 20 20 20 Handling/transport/trader margin - between wholesaler/processor and border - 200 200 200 Value at wholesale market/processor = 5,098 5,265 4,932

lint Net processing cost - 400 400 400 Net value at ginnery = 4,698 4,865 4,532 Processing percentage (lint/kg seed cotton) x 33% 33% 33% Net value of lint delivered to ginnery/kg of seed cotton = 1,550 1,605 1,496 Net percentage of cotton seed/kg of seed cotton x 55% 55% 55% Unit value of cotton seed 9/ = 470 486 453 UZS/kg seed

cotton Net value of cotton seed/kg of seed cotton = 258 268 249 Net percentage of linters/kg of seed cotton x 3% 3% 3% Unit value of linters 10/ = 705 730 680

linters Net value of linters/kg of seed cotton = 21 22 20 Total value of seed cotton at ginnery = 1830 1895 1765 Handling/transport/trader margin - from farmgate to wholesaler/processor - 100 100 100 seed

cotton Value at farmgate = 1,730 1,795 1,665 Crop form at farmgate seed cotton Table A.1 (b) Border Parity Price Calculations for Wheat - @ 2012 economic prices

Export/Import Substitute Import Indicator product location 1/ Kazakstan Quality of Indicator product 2/ US Hard 1 2012 2015 2020 World price Jan-Aug 2012 3/ = 292 Indicator price - 2005 base 4/ = 257 211 195 Indicator price - 2012 base 6/ = 310 254 235 Quality differential (between Uzbek and Indicator product) 5/ x 0.8 0.8 0.8 Equivalent value of Uzbek product 7/ = 248 204 188 US$/ton Assumed source Kazakhstan Freight & insurance (from Kazakhstan to Uzbek border) + 10 10 10 Value at Uzbek border = 258 214 198 Value at Uzbek border 8/ = 712 589 547 Uzbekistan border charges + 20 20 20 Handling/transport/trader margin - between wholesaler/processor and border + 40 40 40 Value at wholesale market/processor = 772 649 607 Handling/transport/trader margin - between local and wholesale market/processor - 40 40 40 UZS/kg Value at local market = 732 609 567 Handling/transport/trader margin - from farmgate to wholesaler/processor - 30 30 30 Value at farmgate = 702 579 537 Crop form at farmgate dry grain Notes : See Table A.2 Table A.2 Border Parity Price Calculations for Fertilizers - @ 2012 economic prices.

Note Urea TSP KCl Normally exported or imported Exported Exported Exported Indicator product location 1/ Europe Nutrient content of marker product 2/ N% 46 P% 46 K% 60 2012 2015 2020 2012 2015 2020 2012 2015 2020 World price Jan-May 2012 3/ = 416 = 463 = 469 Indicator price - 2005 base 4/ = 332 274 232 = 390 328 282 = 386 297 253 Indicator price - 2012 base 5/ = 400 330 280 = 470 396 340 = 466 358 305 Quality differential (between Uzbek and Indicator product) 6/ x 1.0 1.0 1.0 x 1.0 1.0 1.0 x 1.0 1.0 1.0 Equivalent value of Uzbek product = 400 330 280 = 470 396 340 = 466 358 305

US$/ton Assumed transit port na na na Freight & insurance (between Baltic port and point of origin/final destination) na 0 0 0 na 0 0 0 na 0 0 0 Freight & insurance (between Baltic port and Uzbek border) - 0 0 0 + 0 0 0 + 0 0 0 Value at Uzbek border = 400 330 280 = 470 396 340 = 466 358 305 Value at Uzbek border 8/ = 1,105 912 772 = 1,298 1,092 939 = 1,285 989 842 Border charges - 0 0 0 - 0 0 0 + 0 0 0 Handling/transport/trader margin - between border and wholesaler/factory - 0 0 0 - 0 0 0 + 0 0 0 Value at wholesaler/central distributor,factory = 1,105 912 772 = 1,298 1,092 939 = 1,285 989 842 Handling/transport/trader margin - between wholesaler/factory and local distrib + 50 50 50 + 50 50 50 + 50 50 50

UZS/kg Value at local distribution port = 1,155 962 822 = 1,348 1,142 989 = 1,335 1,039 892 Handling/transport/trader margin - from local distributor to farmgate + 25 25 25 + 25 25 25 + 25 25 25 Value at farmgate (fertiliser) = 1,130 937 797 = 1,323 1,117 964 = 1,310 1,014 867 Value at farmgate (nutrient) = 2,457 2,037 1,733 2,876 2,428 2,095 = 2,183 1,689 1,445 Form at farmgate bagged bagged bagged

Notes 1/ Source of Indicator product or of product imported into Uzbekistan 7/ Indicator price x quality differential factor 2/ Quality standard of Indicator product 8/ US$/ton value in UZS/kg at 1 US$ = UZS'000 2.76 3/ World Bank. Pink sheets. May 2012 9/ Assumed value of cotton seed as % of lint price 10% 4/ World Bank Commodity Price Projections. Jan 2012. at constant 2005 prices 10/ Assumed value of linters as % of lint price 15% 6/ Value of Uzbekistan product/value of Indicator product. 11/ Uzbekistan imports most of its 1 m ton from Kazakhstan 5/ 2005 constant price adjusted to 2012 constant price using MUV factor 1.206 Table A.3 Part A Net crop returns, UZS'000/ha @ 2012 financial & economic prices. Yields and physical inputs per ha Crop cotton wheat vegetables fruit fodder wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop Details WP/WOP Irrigation condition good marginal good marginal good marginal good marginal good marginal Unit Unit nr Unit nr Unit nr Unit nr Unit nr Unit nr Unit nr Unit nr Unit nr Unit nr Yields/Returns cotton tonne 3.3 ------cotton tonne - 2.6 ------wheat tonne - - 6.0 ------wheat tonne - - - 4.5 ------Main Crop vegetables tonne - - - - 13.6 - - - - - vegetables tonne - - - - - 10.0 - - - - fruit tonne ------7.0 - - - fruit tonne ------4.0 - - fodder tonne ------27.0 - fodder tonne ------18.0 By-product % of main crop value lumpsum 5% 5% 10% 10% ------Gross returns Inputs/Costs cotton kg 55 ------cotton kg - 55 ------wheat kg - - 220 ------wheat kg - - - 200 - - - - - Seeds & planting vegetables kg - - - - 6 - - - - - material vegetables kg - - - - - 6 - - - - fruit kg ------fruit kg ------fodder kg ------40 - fodder kg ------40 Urea kg 265 150 160 110 150 150 50 50 50 50 TSP kg 56 45 40 30 50 50 - - 50 50 KCl kg 6 5 4 3 ------Fertilsers & manure Carbamide kg 5 5 ------Compost tonne - - - - 4 4 - - - - Farm yard manure tonne 1 1 1 1 12 12 5 5 - - herbicide lumpsum 5.0 3.0 6.0 4.0 ------insecticide lumpsum 5.0 3.0 ------Agro chemicals general lumpsum - - - - 3.0 3.0 1.0 1.0 1.0 1.0 biological control lumpsum 2.0 2.0 ------Land levelling ha 0.2 0.2 - - 0.2 0.2 - - 0.2 0.2 Manure application ha - - - - 1.0 1.0 1.0 1.0 - - Ploughing ha 1.0 1.0 1.0 1.0 1.0 1.0 - - 1.0 1.0 Chisel ploughing ha 1.0 1.0 ------Irrig canal formation ha - - - - 1.0 1.0 6.0 6.0 1.0 1.0 Basin formation ha 1.0 1.0 - - 1.0 1.0 - - 1.0 1.0 Cultivating ha 1.0 1.0 1.0 1.0 1.0 1.0 - - 2.0 2.0 Planting - cotton ha 1.0 1.0 ------Planting - wheat ha - - 1.0 1.0 ------Planting - other ha - - - - 1.0 1.0 - - 1.0 1.0 Spraying ha 2.0 2.0 2.0 2.0 ------Mechanisation Furrow creation ha 2.0 2.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 Cultivating/fertilizing ha 3.0 3.0 3.0 3.0 ------Fertilising - single pass ha - - - - 3.0 3.0 2.0 2.0 2.0 2.0 Rolling ha - - - - 1.0 1.0 - - 1.0 1.0 Harvesting - wheat ha - - 1.0 1.0 ------Harvesting - silage ha ------5.0 3.0 Harvesting - general ha - - - - 1.0 1.0 - - - - Chopping cotton stalks ha 1.0 1.0 ------Transport to field ha 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 Transport from field tonne 3.3 2.6 6.0 4.5 - - - - 27.0 18.0 Transport to market tonne - - - - 6.8 5.0 3.5 2.0 - - Fuel litre 120 117 119 113 98 98 44 44 244 188 Bags & packaging tonne - - 120 76 292 215 581 387 - - Materials Tools & equipment lumpsum 1 1 1 1 1 1 1 1 1 1 Hired/family workday 15 15 6 6 119 100 120 60 19 15 Labour Cotton harvest tonne 3.3 2.6 ------WUA charges ha 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 Private pumping ha 0.3 0.3 0.2 0.2 1.0 1.0 1.0 1.0 1.0 1.0 Other Interest charges ha 1.0 1.0 1.0 1.0 ------Contingencies season 1.0 1.0 1.0 1.0 1.0 - - - 1.0 1.0 Land tax lumpsum 1.0 1.0 0.5 0.5 0.5 0.5 1.0 1.0 1.0 1.0 Taxes Administration tax lumpsum 1.0 1.0 0.5 0.5 ------Labour tax tonne 3.3 2.6 ------

Sources: Consultant's estimates and Table 13 Table 12 Table A.3 Part B Net crop returns, UZS'000/ha @ 2012 financial prices cotton wheat vegetables fruit fodder Crop Unit value Details wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop good marginal good marginal good marginal good marginal good marginal Financial UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 Yields/Returns 2,885 ------885 - 2,301 ------885 - - 2,280 ------380 - - - 1,710 ------380 Main Crop - - - - 6,800 - - - - - 500 - - - - - 5,000 - - - - 500 ------5,576 - - - 800 ------3,200 - - 800 ------4,725 - 175 ------3,150 175 By-product 144 115 228 171 Gross returns 3,029 2,416 2,508 1,881 6,800 5,000 5,576 3,200 4,725 3,150 Inputs/Costs 91 ------1.7 - 91 ------1.7 - - 155 ------0.7 Seeds & planting - - - 141 ------0.7 material - - - - 240 - - - - - 40.0 - - - - - 240 - - - - 40.0 ------0.0 ------0.0 ------160 - 4.0 ------160 4.0 307 174 186 128 174 174 58 58 58 58 1.2 109 88 78 59 98 98 - - 98 98 2.0 Fertilsers & manure 7 6 5 4 ------1.2 2 2 ------0.4 - - - - 48 48 - - - - 12.0 35 35 35 35 420 420 175 175 - - 35.0 50 30 60 40 ------10.0 Agro chemicals 50 30 ------10.0 - - - - 75 75 25 25 25 25 25.0 20 20 ------10.0 50 50 - - 50 50 - - 50 50 250.0 - - - - 56 56 56 56 - - 56.0 109 109 109 109 109 109 - - 109 109 109.0 36 36 ------36.0 - - - - 28 28 168 168 28 28 28.0 17 17 - - 17 17 - - 17 17 17.0 51 51 51 51 51 51 - - 102 102 51.0 17 17 ------17.0 - - 15 15 ------15.0 - - - - 50 50 - - 50 50 50.0 Mechanisation 20 20 20 20 ------10.0 90 90 45 45 45 45 45 45 45 45 45.0 105 105 105 105 ------35.0 - - - - 72 72 48 48 48 48 24.0 - - - - 15 15 - - 15 15 15.0 - - 160 160 ------160.0 ------300 180 60.0 - - - - 50 50 - - - - 50.0 7 7 ------6.5 10 10 10 10 10 10 10 10 10 10 10.0 - - 51 38 - - - - 459 306 17.0 - - - - 408 300 209 120 - - 60.0 204 200 202 192 167 167 75 75 415 320 1.7 Materials - - 120 76 292 215 581 387 - - 1.0 10 10 10 10 10 10 10 10 10 10 10.0 Labour 180 180 72 72 1,428 1,200 1,440 720 228 180 12.0 587 468 ------180.0 20 20 20 20 20 20 20 20 20 20 20.0 Other 10 10 6 6 30 30 30 30 30 30 30.00 0 0 0 0 ------3% 217 185 149 131 394 353 293 193 226 184 10% Taxes 50 50 25 25 25 25 50 50 50 50 50 23 23 12 12 ------23 Total costs 2,582 98 2,211 78 1,701 - 1,503 - 4,382 - 3,927 - 3,293 - 2,190 - 2,552 - 2,094 - 30 Net returns 448 205 807 378 2,418 1,073 2,283 1,010 2,173 1,056 Table A.3 Part C Net crop returns, UZS'000/ha @ 2012 economic prices cotton wheat vegetables fruit fodder Crop Unit value Details wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop wp/wop good marginal good marginal good marginal good marginal good marginal Economic UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 UZS'000 Yields/Returns 5,640 ------1,730 - 4,498 ------1,730 - - 3,349 ------558 - - - 2,512 ------558 Main Crop - - - - 6,800 - - - - - 500 - - - - - 5,000 - - - - 500 ------5,576 - - - 800 ------3,200 - - 800 ------4,725 - 175 ------3,150 175 By-product 282 225 335 251 Gross returns 5,922 4,723 3,684 2,763 6,800 5,000 5,576 3,200 4,725 3,150 Inputs/Costs 91 ------1.7 - 91 ------1.7 - - 155 ------0.7 Seeds & planting - - - 141 ------0.7 material - - - - 240 - - - - - 40.0 - - - - - 240 - - - - 40.0 ------0.0 ------0.0 ------160 - 4.0 ------160 4.0 230 130 139 95 130 130 43 43 43 43 0.9 58 47 42 31 52 52 - - 52 52 1.0 Fertilsers & manure 6 5 4 3 ------0.9 2 2 ------0.4 - - - - 48 48 - - - - 12.0 35 35 35 35 420 420 175 175 - - 35.0 50 30 60 40 ------10.0 Agro chemicals 50 30 ------10.0 - - - - 75 75 25 25 25 25 25.0 20 20 ------10.0 60 60 - - 60 60 - - 60 60 300.0 - - - - 67 67 67 67 - - 67.2 131 131 131 131 131 131 - - 131 131 130.8 43 43 ------43.2 - - - - 34 34 202 202 34 34 33.6 20 20 - - 20 20 - - 20 20 20.4 61 61 61 61 61 61 - - 122 122 61.2 20 20 ------20.4 - - 18 18 ------18.0 - - - - 60 60 - - 60 60 60.0 Mechanisation 24 24 24 24 ------12.0 108 108 54 54 54 54 54 54 54 54 54.0 126 126 126 126 ------42.0 - - - - 86 86 58 58 58 58 28.8 - - - - 18 18 - - 18 18 18.0 - - 192 192 ------192.0 ------360 216 72.0 - - - - 60 60 - - - - 60.0 8 8 ------7.8 12 12 12 12 12 12 12 12 12 12 12.0 67 53 122 92 - - - - 551 367 20.4 - - - - 490 360 251 144 - - 72.0 245 239 243 231 200 200 90 90 498 384 2.0 Materials - - 120 76 292 215 581 387 - - 1.0 10 10 10 10 10 10 10 10 10 10 10.0 Labour 144 144 58 58 1,142 960 1,152 576 182 144 9.6 489 390 ------150.0 20 20 20 20 20 20 20 20 20 20 20.0 Other 10 10 6 6 30 30 30 30 30 30 30.0 ------0% 212 185 161 144 379 340 275 187 248 200 10.0% Taxes ------0 ------0 Total costs 2,351 - 2,055 - 1,792 - 1,599 - 4,192 - 3,764 - 3,044 - 2,080 - 2,748 - 2,220 - 0 Net returns 3,570 2,668 1,892 1,164 2,608 1,236 2,532 1,120 1,977 930 Table A.4 Part A Selected Vegetables. Crop Budgets @ constant 2012 financial prices. UZS/ha

Vegetables (weighted average) Cucumber Early Carrot Main Crop Carrot Early Cabbage Unit units unit value total value units unit value total value units unit value total value units unit value total value units unit value total value Gross Return nr UZS/unit UZS nr UZS/unit UZS nr UZS/unit UZS nr UZS/unit UZS nr UZS/unit UZS Gross Production tonne 20.8 16.0 17.0 22.0 22.0 Wastage % 13% 15% 10% 5% 20% Net Production tonne 17.9 492,500 8,160,925 13.6 500,000 6,800,000 15.3 400,000 6,120,000 20.9 250,000 5,225,000 17.6 350,000 6,160,000 Input Costs Planting material (seeds & seedling) kg 654.4 39,340 1,250,000 6 40,000 240,000 6 20,000 120,000 6 30,000 180,000 1.5 100,000 150,000 (Potatoes) kg 650.0 340 1,105,000 Mineral fertilizers tonne -nitrogen (urea 46%) tonne 0.2 1,160,000 174,000 0.15 1,160,000 174,000 0.15 1,160,000 174,000 0.15 1,160,000 174,000 0.15 1,160,000 174,000 -phosphorous (TSP 46%) tonne 0.1 1,950,000 117,000 0.05 1,950,000 97,500 0.05 1,950,000 97,500 0.05 1,950,000 97,500 0.05 1,950,000 97,500 Manure tonne 13.6 35,000 476,000 12 35,000 420,000 12 35,000 420,000 12 35,000 420,000 12 35,000 420,000 Compost tonne 3.4 2,700 19,800 4 12,000 48,000 0 0 0 Bio & chemical kg 1.0 25,000 25,000 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 Mechanisation Pre - Planting period Land levelling pass 0.1 250,000 35,000 0.2 250,000 50,000 0.2 250,000 50,000 0 250,000 0 0.2 250,000 50,000 Manure application pass 1.2 56,000 67,200 1 56,000 56,000 1 56,000 56,000 1 56,000 56,000 1 56,000 56,000 Fertilizer application pass 1.0 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 Ploughing pass 0.8 109,000 87,200 1 109,000 109,000 1 109,000 109,000 1 109,000 109,000 1 109,000 109,000 Furrow formation pass 1.0 45,000 45,000 1 45,000 45,000 1 45,000 45,000 1 45,000 45,000 1 45,000 45,000 Cultivation pass 1.0 51,000 51,000 1 51,000 51,000 1 51,000 51,000 1 51,000 51,000 1 51,000 51,000 Rolling pass 1.0 15,000 15,000 1 15,000 15,000 1 15,000 15,000 1 15,000 15,000 1 15,000 15,000 Planting period Planting pass 1.0 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 Growing period Opening irrigation canals pass 1.0 28,000 28,000 1 28,000 28,000 1 28,000 28,000 1 28,000 28,000 1 28,000 28,000 Harrowing pass 2.8 15,000 42,000 2 15,000 30,000 3 15,000 45,000 1 15,000 15,000 3 15,000 45,000 Fertilizer application pass 1.7 24,000 40,800 2 24,000 48,000 2 24,000 48,000 1 24,000 24,000 2 24,000 48,000 Harvesting period Mechanical Harvesting tonne 0.4 20,000 20,000 1 50,000 50,000 1 50,000 50,000 Transportation (half of total yelds) tonne 8.9 60,000 535,530 6.8 60,000 408,000 7.7 60,000 459,000 10.5 60,000 627,000 8.8 60,000 528,000 Fuel and lubricants litre 374.1 1,700 635,970 416 1,700 707,200 230 1,700 391,000 220 1,700 374,000 375 1,700 637,500 Packaging tonne 266.8 700 292,261 302 400 120,889 340 400 136,000 464 400 185,778 Tools and equipment lump sum 1.0 10,000 10,000 1 10,000 10,000 1 10,000 10,000 1 10,000 10,000 1 10,000 10,000 Labor (including hand harvesting) workdays 120.5 12,000 1,446,000 119 12,000 1,428,000 119 12,000 1,428,000 70 12,000 840,000 167 12,000 2,004,000 WUA charge months 1.0 20,000 20,000 1 20,000 20,000 1 20,000 20,000 1 20,000 20,000 1 20,000 20,000 Private pumping lump sum 1.0 30,000 30,000 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 Contingencies 10% 0.0 0 553,676 423,459 388,150 345,028 461,700 Land taxes year 1.0 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 Total costs mln.UZS 6,140,437 4,708,048 4,319,650 3,845,306 5,128,700 Net income mln.UZS 2,020,488 2,091,952 1,800,350 1,379,694 1,031,300 Proportion of veg area planted % 100% 10% 10% 10% 10% Wholesale bazaar prices sacks, etc type kg/unit unit cost type kg/unit unit cost type kg/unit unit cost type kg/unit unit cost UZS per unit plastic plastic plastic 45 400 45 400 45 400 na sack sack sack Table A.4 Part B Selected Vegetables. Crop Budgets @ constant 2012 financial prices. UZS/ha

Main Crop Cabbage Onion Tomato Melons Early Potato Main Crop Potato Unit units unit value total value units unit value total value units unit value total value units unit value total value units unit value total value units unit value total value Gross Return nr UZS/unit UZS nr UZS/unit UZS nr UZS/unit UZS nr UZS/unit UZS nr UZS/unit UZS nr UZS/unit UZS Gross Production tonne 35.0 22.0 18.0 22.0 14.0 20.0 Wastage % 25% 7% 20% 15% 5% 10% Net Production tonne 26.25 225,000 5,906,250 20.46 300,000 6,138,000 14.4 700,000 10,080,000 18.7 400,000 7,480,000 13.3 1,000,000 13,300,000 18 800,000 14,400,000 Input Costs Planting material (seeds & seedling) kg 2 60,000 120,000 14 20,000 280,000 2.5 100,000 250,000 5.5 20,000 110,000 (Potatoes) kg 3000 1,700 5,100,000 3500 1,700 5,950,000 Mineral fertilizers tonne -nitrogen (urea 46%) tonne 0.15 1,160,000 174,000 0.15 1,160,000 174,000 0.15 1,160,000 174,000 0.05 1,160,000 58,000 0.2 1,160,000 232,000 0.2 1,160,000 232,000 -phosphorous (TSP 46%) tonne 0.05 1,950,000 97,500 0.05 1,950,000 97,500 0.05 1,950,000 97,500 0.05 1,950,000 97,500 0.1 1,950,000 195,000 0.1 1,950,000 195,000 Manure tonne 12 35,000 420,000 12 35,000 420,000 12 35,000 420,000 12 35,000 420,000 20 35,000 700,000 20 35,000 700,000 Compost tonne 0 0 10 5,000 50,000 0 10 5,000 50,000 10 5,000 50,000 Bio & chemical kg 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 Mechanisation Pre - Planting period Land levelling pass 250,000 0 0.2 250,000 50,000 0.2 250,000 50,000 0.2 250,000 50,000 0.2 250,000 50,000 250,000 0 Manure application pass 1 56,000 56,000 1 56,000 56,000 1 56,000 56,000 1 56,000 56,000 2 56,000 112,000 2 56,000 112,000 Fertilizer application pass 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 Ploughing pass 1 109,000 109,000 1 109,000 109,000 109,000 0 109,000 0 1 109,000 109,000 1 109,000 109,000 Furrow formation pass 1 45,000 45,000 1 45,000 45,000 1 45,000 45,000 1 45,000 45,000 1 45,000 45,000 1 45,000 45,000 Cultivation pass 1 51,000 51,000 1 51,000 51,000 1 51,000 51,000 1 51,000 51,000 1 51,000 51,000 1 51,000 51,000 Rolling pass 1 15,000 15,000 1 15,000 15,000 1 15,000 15,000 1 15,000 15,000 1 15,000 15,000 1 15,000 15,000 Planting period Planting pass 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 Growing period Opening irrigation canals pass 1 28,000 28,000 1 28,000 28,000 1 28,000 28,000 1 28,000 28,000 1 28,000 28,000 1 28,000 28,000 Harrowing pass 3 15,000 45,000 3 15,000 45,000 4 15,000 60,000 3 15,000 45,000 3 15,000 45,000 3 15,000 45,000 Fertilizer application pass 2 24,000 48,000 1 24,000 24,000 2 24,000 48,000 1 24,000 24,000 2 24,000 48,000 2 24,000 48,000 Harvesting period Mechanical Harvesting tonne 1 50,000 50,000 1 50,000 50,000 Transportation (half of total yelds) tonne 13.1 60,000 787,500 10.2 60,000 613,800 7.2 60,000 432,000 9.4 60,000 561,000 6.7 60,000 399,000 9.0 60,000 540,000 Fuel and lubricants litre 310 1,700 527,000 255 1,700 433,500 535 1,700 909,500 440 1,700 748,000 480 1,700 816,000 480 1,700 816,000 Packaging tonne 538 400 215,368 576 3,000 1,728,000 190 1,200 228,000 257 1,200 308,571 Tools and equipment lump sum 1 10,000 10,000 1 10,000 10,000 1 10,000 10,000 1 10,000 10,000 1 10,000 10,000 1 10,000 10,000 Labor (including hand harvesting) workdays 133 12,000 1,596,000 100 12,000 1,200,000 158 12,000 1,896,000 60 12,000 720,000 134 12,000 1,608,000 145 12,000 1,740,000 WUA charge months 1 20,000 20,000 1 20,000 20,000 1 20,000 20,000 1 20,000 20,000 1 20,000 20,000 1 20,000 20,000 Private pumping lump sum 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 Contingencies 10% 427,800 401,617 646,900 318,750 1,004,000 1,119,357 Land taxes year 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 Total costs mln.UZS 4,755,800 4,467,785 7,165,900 3,556,250 11,094,000 12,362,929 Net income mln.UZS 1,150,450 1,670,215 2,914,100 3,923,750 2,206,000 2,037,071 Proportion of veg area planted % 10% 10% 10% 10% 10% 10% Wholesale bazaar prices sacks, etc type kg/unit unit cost type kg/unit unit cost type kg/unit unit cost type kg/unit unit cost type kg/unit unit cost type kg/unit unit cost banana UZS per unit na string sack 38 400 25 3,000 paper sack 70 1,200 paper sack 70 1,200 box Table A.5 Selected Fruit Crops. Crop Budgets @ constant 2012 financial prices. UZS/ha

Fruit (weighted average) New orchards Immature orchards Productive apples Productive apricots/peaches New grapes Mature grapes Unit units unit value total value units unit value total value units unit value total value units unit value total value units unit value total value units unit value total value units unit value total value Gross Return ha Gross Production c/ha 94.7 110 85 120 Wastage % 12.4 15 18 10 Net Production tonne 8.3 677,000 6,171,120 9.35 800,000 7,480,000 6.97 800,000 5,576,000 10.8 700,000 7,560,000 Input Costs Planting material kg 66.5 440 385,920 330 5,000 1,650,000 1333 6,000 7,998,000 Mineral fertilizer tonne -nitrogen (urea 46%) tonne 0.1 1,160,000 58,000 0.05 1,160,000 58,000 0.05 1,160,000 58,000 0.05 1,160,000 58,000 0.05 1,160,000 58,000 0.05 1,160,000 58,000 0.05 1,160,000 58,000 -phosphorous (TSP 46%) tonne 0.0 1,950,000 0 1,950,000 0 1,950,000 0 1,950,000 0 1,950,000 0 1,950,000 0 1,950,000 0 Manure tonne 5.0 35,000 175,000 5 35,000 175,000 5 35,000 175,000 5 35,000 175,000 5 35,000 175,000 5 35,000 175,000 5 35,000 175,000 Bio & chemical kg 1.0 25,000 25,000 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 Mechanisation Pre - Planting period Land levelling pass 0.1 250,000 20,000 1 250,000 250,000 250,000 0 250,000 0 250,000 0 1 250,000 250,000 250,000 0 Manure application pass 1.0 56,000 56,000 1 56,000 56,000 1 56,000 56,000 1 56,000 56,000 1 56,000 56,000 1 56,000 56,000 1 56,000 56,000 Fertilizer application pass 1.0 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 Ploughing pass 1.0 109,000 109,000 1 109,000 109,000 1 109,000 109,000 1 109,000 109,000 1 109,000 109,000 1 109,000 109,000 1 109,000 109,000 Furrow formation pass 1.3 45,000 59,850 1 45,000 45,000 3 45,000 135,000 2 45,000 90,000 1 45,000 45,000 1 45,000 45,000 1 45,000 45,000 Cultivation pass 0.1 51,000 4,998 1 51,000 51,000 0.6 51,000 30,600 51,000 0 51,000 0 1 51,000 51,000 51,000 0 Rolling pass 0.1 15,000 1,200 1 15,000 15,000 15,000 0 0 15,000 0 15,000 0 1 15,000 15,000 15,000 0 Planting period Planting pass 0.2 79,000 12,640 2 79,000 158,000 79,000 0 79,000 0 79,000 0 2 79,000 158,000 79,000 0 Growing period Making irrigation canals pass 5.7 28,000 159,040 2 28,000 56,000 6 28,000 168,000 6 28,000 168,000 6 28,000 168,000 2 28,000 56,000 6 28,000 168,000 Harrowing pass 4.5 15,000 68,100 10 15,000 150,000 6 15,000 90,000 4 15,000 60,000 4 15,000 60,000 10 15,000 150,000 4 15,000 60,000 Fertilizer application pass 1.0 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 Harvesting period Transportation (half of total yelds) tonne 4.1 60,000 245,592 0.0 60,000 0 0.0 60,000 0 4.7 60,000 280,500 3.5 60,000 209,100 0.0 60,000 0 5.4 60,000 324,000 Fuel and lubricants litre 327.7 1,700 557,073 293 1,700 498,100 174 1,700 295,800 307 1,700 521,900 270 1,700 459,000 374 1,700 635,800 400 1,700 680,000 Packaging boxes 661.1 1,025 724,163 468 1,500 701,250 581 1,000 580,833 1080 1,000 1,080,000 Tools and equipment lumpsum 1.0 10,000 10,000 1 10,000 10,000 1 10,000 10,000 1 10,000 10,000 1 10,000 10,000 1 10,000 10,000 1 10,000 10,000 Labor (including hand harvesting) workday 108.7 12,000 1,304,880 66 12,000 792,000 32 12,000 384,000 102 12,000 1,224,000 120 12,000 1,440,000 80 12,000 960,000 120 12,000 1,440,000 WUA charge lump sum 1.0 20,000 20,000 1 20,000 20,000 1 20,000 20,000 1 20,000 20,000 1 20,000 20,000 1 20,000 20,000 1 20,000 20,000 Private pumping lump sum 1.0 30,000 30,000 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 Contingencies 10% 0.0 0 407,446 419,610 163,440 357,665 349,293 1,084,980 432,800 Land taxes year 1.0 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 Total costs mln.UZS 4,531,901 4,665,710 1,847,840 3,984,315 3,892,227 11,984,780 4,810,800 Net income mln.UZS 1,639,219 -4,665,710 -1,847,840 3,495,685 1,683,773 -11,984,780 2,749,200 Proportion of veg area planted % 100% 4% 3% 27% 27% 4% 35% Wholesale bazaar prices sacks, etc type kg/unit unit cost type kg/unit unit cost type kg/unit unit cost type kg/unit unit cost type kg/unit unit cost type kg/unit unit cost big wood small small UZS per unit na na 20 1,500 12 1,000 na 10 1,000 box wood box wood box Table A.6 Selected Fodder Crops. Crop Budgets @ constant 2012 financial prices. UZS/ha

Fodder (weighted average) Year 1 Lucerne - fresh Year 2 Lucerne - fresh Lucerne for silage Maize for grain Maize for silage Maize after wheat (for grain) Unit units unit value total value units unit value total value units unit value total value units unit value total value units unit value total value units unit value total value units unit value total value

Gross Return Gross production c/ha 99.0 100 350 120 45 270 45 Wastage % 6.0 10 10 Net Production tonne 9.3 569,500 3,676,500 10 175,000 1,750,000 35 175,000 6,125,000 12 450,000 5,400,000 4.05 750,000 3,037,500 27 175,000 4,725,000 4.05 750,000 3,037,500 Input Costs Planting material kg 24.4 6,680 159,200 20 15,000 300,000 20 15,000 300,000 30 4,000 120,000 40 4,000 160,000 30 4,000 120,000 Mineral fertilizer tonne -nitrogen (urea 46%) tonne 0.1 1,160,000 58,000 0.05 1,160,000 58,000 0.05 1,160,000 58,000 0.05 1,160,000 58,000 0.05 1,160,000 58,000 0.05 1,160,000 58,000 0.05 1,160,000 58,000 -phosphorous (TSP 46%) tonne 0.1 1,950,000 97,500 0.05 1,950,000 97,500 0.05 1,950,000 97,500 0.05 1,950,000 97,500 0.05 1,950,000 97,500 0.05 1,950,000 97,500 0.05 1,950,000 97,500 -potash (KCl 57%) tonne 0.0 1,170,000 0 1,170,000 0 1,170,000 0 1,170,000 0 1,170,000 0 1,170,000 0 1,170,000 0 Bio & chemical lumpsum 1.0 25,000 25,000 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 1 25,000 25,000 Pre - Planting period Land levelling pass 0.0 250,000 10,000 250,000 0 250,000 0 250,000 0 0.2 250,000 50,000 0.2 250,000 50,000 250,000 0 Fertilizer application pass 1.0 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 Ploughing pass 0.9 109,000 98,100 1 109,000 109,000 109,000 0 1 109,000 109,000 1 109,000 109,000 1 109,000 109,000 1 109,000 109,000 Furrow formation pass 0.7 45,000 32,400 1 45,000 45,000 45,000 0 45,000 0 1 45,000 45,000 1 45,000 45,000 1 45,000 45,000 Cultivation pass 1.3 51,000 68,340 1 51,000 51,000 51,000 0 51,000 0 2 51,000 102,000 2 51,000 102,000 2 51,000 102,000 Rolling pass 1.2 15,000 17,700 1 15,000 15,000 1 15,000 15,000 1 15,000 15,000 2 15,000 30,000 1 15,000 15,000 1 15,000 15,000 Planting period Planting pass 0.9 79,000 71,100 1 79,000 79,000 79,000 0 1 79,000 79,000 1 79,000 79,000 1 79,000 79,000 1 79,000 79,000 Growing period Opening irrigation canals pass 1.0 28,000 28,000 1 28,000 28,000 1 28,000 28,000 1 28,000 28,000 1 28,000 28,000 1 28,000 28,000 1 28,000 28,000 Harrowing pass 0.6 15,000 9,300 15,000 0 15,000 0 15,000 0 1 15,000 15,000 1 15,000 15,000 1 15,000 15,000 Fertilizer application pass 1.0 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 1 24,000 24,000 Harvesting period Mechanised harvesting tonne 1.6 60,000 98,400 1 60,000 60,000 3 60,000 180,000 3 60,000 180,000 1 60,000 60,000 5 60,000 300,000 1 60,000 60,000 Transportation (assuming 2.5 tonne 4.1 35,060 107,105 4.0 17,000 68,000 14.0 17,000 238,000 4.8 17,000 81,600 2.0 17,000 34,425 13.5 17,000 229,500 2.0 60,000 121,500 tonne/truck) Fuel and lubricants litre 264.5 1,700 449,650 166 1,700 282,200 218 1,700 370,600 310 1,700 527,000 315 1,700 535,500 430 1,700 731,000 250 1,700 425,000

Packaging sacks 32.4 720 38,880 54 1,200 64,800 54 1,200 64,800 Tools and equipment lump sum 1.0 10,000 10,000 1 10,000 10000 1 10,000 10000 1 10,000 10000 1 10,000 10000 1 10,000 10000 1 10,000 10000 Labor work day 11.7 12,000 140,880 12 12,000 144,000 8 12,000 96,000 9 12,000 108,000 15 12,000 180,000 19 12,000 228,000 12 12,000 144,000 WUA charge months 0.6 11,600 11,600 1 20,000 20,000 1 20,000 20,000 1 20,000 20,000 1 20,000 20,000 1 20,000 20,000 Private pumping lump sum 1.0 30,000 30,000 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 1 30,000 30,000 Contingencies 10% 160,915 146,970 121,610 171,610 174,123 238,000 159,680 Land taxes year 0.6 29,000 29,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 1 50,000 50,000 Total costs mln.UZS 1,799,070 1,666,670 1,387,710 1,937,710 1,965,348 2,668,000 1,756,480 Net income mln.UZS 1,877,430 83,330 4,737,290 3,462,290 1,072,153 2,057,000 1,281,020 Proportion of fodder area planted % 100% 10% 10% 18% 18% 2% 42% Table A.7 Capital cost - Khamza 1 Pump Station. New. Reduced capacity @ constant 2012 financial and economic prices. US$'000

Financial cost Economic cost 1/ Unit Unit nr Unit cost Total Cost Foreign % scf % Total A.Civil Works Local Foreign Local Foreign Total (a) earth works lumpsum 1 0 0 2,316 993 3,309 30% 80% 2,846 (b) construction lumpsum 1 10,718 4,593 10,718 4,593 15,312 30% 80% 13,168 (c) Other earthworks lumpsum 1 7,000 3,000 7,000 3,000 10,000 30% 80% 8,600 Sub-total 20,034 8,586 28,621 30% 24,614 B. Equipment (a) Mechanical - pumps (1) nr 8 338 1,913 2,700 15,300 18,000 85% 80% 17,460 - pumps (2) nr - valves (1) nr 9 37 208 331 1,874 2,205 85% 80% 2,139 - valves (2) nr 9 41 230 365 2,066 2,430 85% 80% 2,357 - miscellaneous lumpsum 1 188 752 188 752 940 80% 80% 902 - cranes and lifting equipment lumpsum 1 152 608 152 608 760 80% 80% 730 (b) Anciliary systems lumpsum 1 202 808 202 808 1,010 80% 80% 970 c) Hydraulic steel structures - intake lumpsum 1 161 646 161 646 807 80% 80% 775 - discharge lumpsum 1 3,692 14,768 3,692 14,768 18,460 80% 80% 17,722 (d) Electrical equipment - motors (1) nr 8 228 1,292 1,824 10,336 12,160 85% 80% 11,795 - motors (2) nr - miscellaneous lumpsum 1 1,238 4,983 1,238 4,983 6,221 80% 80% 5,973 (e) Instrumentation lumpsum 1 84 338 84 338 422 80% 80% 405 Sub-total equipment 10,937 52,478 63,415 83% 61,228 C. Training, Capacity Building & Studies D. Consulting Services E. Project Management and Monitoring Total Base Line Capital Cost 30,972 61,064 92,036 66% 85,841 Physical Contingencies - civil 1,402 601 2,003 30% 80% 1,723 Physical Contingencies - other 1,094 5,248 6,342 83% 80% 6,123 Total Capital Cost, including physical contingencies 33,468 66,913 100,380 67% 93,687 Source : PPTA estimates Note 1/ No currency adjustment applied Table A.8 Capital Cost - Kuyu Mazar Pump Station. Rehabilitation. @ constant 2012 financial and economic prices. US$'000 Excluding discharge pipe costs. Economic cost 1/ Unit Unit nr Unit cost Total Cost Foreign % scf % Total A.Civil Works Local Foreign Local Foreign Total (a) earth works lumpsum 1 239 103 239 103 342 30% 80% 294 (b) construction lumpsum 1 1,623 695 1,623 695 2,318 30% 80% 1,993 (c) Other structures lumpsum Sub-total 1,862 798 2,660 30% 2,288 B. Equipment (a) Mechanical - pumps (1) nr 3 294 1,666 882 4,998 5,880 85% 80% 5,704 - pumps (2) nr 3 344 1,949 1,032 5,847 6,879 85% 80% 6,673 - valves (1) nr - valves (2) nr - miscellaneous lumpsum 1 113 452 113 452 565 80% 13,384 80% 542 - cranes and lifting equipment lumpsum 1 12 48 12 48 60 80% 80% 58 (b) Anciliary systems lumpsum 1 71 284 71 284 355 80% 80% 341 c) Hydraulic steel structures - intake lumpsum 1 203 786 203 786 989 80% 989 80% 948 - discharge lumpsum 1 0 0 0 0 0 80% 80% 0 (d) Electrical equipment - motors (1) nr 6 156 884 936 5,304 6,240 85% 8,120 80% 6,053 - motors (2) nr - miscellaneous lumpsum 1 371 1,509 371 1,509 1,880 80% 80% 1,806 (e) Instrumentation lumpsum 1 81 324 81 324 405 80% 80% 389 Sub-total equipment 3,700 19,553 23,253 84% 22,513 C. Training, Capacity Building & Studies D. Consulting Services E. Project Management and Monitoring Total Base Line Capital Cost 5,562 20,351 25,913 79% 24,801 Physical Contingencies - civil 130 56 186 30% 80% 160 Physical Contingencies - other 370 1,955 2,325 84% 80% 2,251 Total Capital Cost, including physical contingencies 6,063 22,362 28,425 79% 27,212 Source : PPTA estimates Note 1/ No currency adjustment applied Table A.9 Capital Cost - Khamza 2 Pump Station Rehabilitation.@ constant 2012 financial and economic prices. US$'000 Excluding discharge pipe costs. Economic cost1/ Unit Unit nr Unit cost Total Cost Foreign % scf % Total A.Civil Works Local Foreign Local Foreign Total (a) earth works lumpsum 1 34 15 34 15 49 30% 80% 42 (b) construction lumpsum 1 907 389 907 389 1,295 30% 80% 1,114 (c) Other structures lumpsum Sub-total 941 403 1,344 30% 1,156 B. Equipment (a) Mechanical - pumps (1) nr 10 575 3,256 5,745 32,555 38,300 85% 80% 37,151 - pumps (2) nr - valves (1) nr 11 39 221 429 2,431 2,860 85% 80% 2,774 - valves (2) nr - miscellaneous lumpsum 1 158 632 158 632 790 80% 80% 758 - cranes and lifting equipment lumpsum 1 57 228 57 228 285 80% 80% 274 (b) Anciliary systems lumpsum 1 104 416 104 416 520 80% 80% 499 c) Hydraulic steel structures - intake lumpsum 1 241 963 241 963 1,204 80% 80% 1,156 - discharge lumpsum 1 0 0 0 0 0 80% 80% 0 (d) Electical equipment - motors (1) nr 10 246 1,392 2,457 13,923 16,380 85% 80% 15,889 - motors (2) nr - miscellaneous lumpsum 1 1,090 4,390 1,090 4,390 5,480 80% 80% 5,262 (e) Instrumentation lumpsum 1 96 384 96 384 480 80% 80% 461 Sub-total equipment 10,377 55,922 66,299 84% 64,224 C. Training, Capacity Building & Studies D. Consulting Services E. Project Management and Monitoring Total Base Line Capital Cost 11,318 56,325 67,643 83% 65,379 Physical Contingencies - civil 66 28 94 30% 80% 81 Physical Contingencies - other 1,038 5,592 6,630 84% 80% 6,422 Total Capital Cost, including physical contingencies 12,421 61,946 74,367 83% 71,883 Source : PPTA estimates Note 1/ No currency adjustment applied Table A.10 Capital Cost - Kizil Tepa Pump Station - Partial rehabilitation. @ constant 2012 financial and economic prices. US$'000 Excluding discharge pipe costs. Economic cost 1/ Unit Unit nr Unit cost Total Cost Foreign % scf % Total A.Civil Works Local Foreign Local Foreign Total (a) earth works lumpsum 1 20 9 20 9 29 30% 80% 25 (b) construction lumpsum 1 1,768 758 1,768 758 2,525 30% 80% 2,172 (c) Other structures lumpsum Sub-total 1,788 766 2,554 30% 2,196 B. Equipment (a) Mechanical - pumps (1) nr 4 533 3,023 2,134 12,090 14,224 85% 80% 13,797 - pumps (2) nr 4 403 2,282 1,611 9,129 10,740 85% 80% 10,418 - valves (1) nr 8 52 208 416 1,664 2,080 80% 80% 1,997 - valves (2) nr - miscellaneous lumpsum 1 157 628 157 628 785 80% 80% 754 - cranes and lifting equipment lumpsum 1 57 228 57 228 285 80% 80% 274 (b) Anciliary systems lumpsum 1 98 392 98 392 490 80% 80% 470 c) Hydraulic steel structures - intake lumpsum 1 241 963 241 963 1,204 80% 80% 1,156 - discharge lumpsum 1 24 96 24 96 120 80% 80% 115 (d) Electrical equipment - motors (1) nr 4 185 1,046 738 4,182 4,920 85% 80% 4,772 - motors (2) nr 4 246 1,392 983 5,569 6,552 85% 80% 6,355 - miscellaneous lumpsum 1 1,170 4,710 1,170 4,710 5,880 80% 80% 5,646 (e) Instrumentation lumpsum 1 86 344 86 344 430 80% 80% 413 Sub-total equipment 7,714 39,996 47,710 84% 46,167 C. Training, Capacity Building & Studies D. Consulting Services E. Project Management and Monitoring Total Base Line Capital Cost 9,502 40,762 50,264 81% 48,364 Physical Contingencies - civil 125 54 179 30% 80% 154 Physical Contingencies - other 771 4,000 4,771 84% 80% 4,617 Total Capital Cost, including physical contingencies 10,399 44,815 55,214 81% 53,134 Source : PPTA estimates Note 1/ No currency adjustment applied Table A.11 Capital Cost - Kizil Tepa Auxiliary Pump Station - Partial rehabilitation. @ constant 2012 financial and economic prices. US$.'000 Excluding discharge pipe costs. Economic cost 1/ Unit Unit nr Unit cost Total Cost Foreign % scf % Total A.Civil Works Local Foreign Local Foreign Total (a) earth works lumpsum 1 259 111 259 111 370 30% 80% 318 (b) construction lumpsum 1 1,190 510 1,190 510 1,700 30% 80% 1,462 (c) Other structures lumpsum Sub-total 1,449 621 2,070 30% 1,780 B. Equipment (a) Mechanical - pumps (1) nr 13 44 247 566 3,205 3,770 85% 80% 3,657 - pumps (2) nr - valves (1) nr 14 3 17 42 238 280 85% 80% 272 - valves (2) nr 14 4 21 53 298 350 85% 80% 340 - miscellaneous lumpsum 1 101 404 101 404 505 80% 80% 485 - cranes and lifting equipment lumpsum 1 12 46 12 46 58 80% 80% 56 (b) Anciliary systems lumpsum 1 68 272 68 272 340 80% 80% 326 c) Hydraulic steel structures - intake lumpsum 1 105 420 105 420 525 80% 80% 504 - discharge lumpsum 1 0 60 0 60 60 100% 80% 60 (d) Electrical equipment - motors (1) nr 13 56 224 728 2,912 3,640 80% 80% 3,494 - motors (2) nr - miscellaneous lumpsum 1 529 2,141 529 2,141 2,670 80% 80% 2,564 (e) Instrumentation lumpsum 1 72 287 72 287 359 80% 80% 345 Sub-total equipment 2,274 10,283 12,557 82% 12,102 C. Training, Capacity Building & Studies D. Consulting Services E. Project Management and Monitoring Total Base Line Capital Cost 3,723 10,904 14,627 75% 13,882 Physical Contingencies - civil 101 43 145 30% 80% 125 Physical Contingencies - other 227 1,028 1,256 82% 80% 1,210 Total Capital Cost, including physical contingencies 4,052 11,975 16,028 75% 15,217 Source : PPTA estimates Note 1/ No currency adjustment applied Table A.12 Capital Cost - ABMK rehabilitation.@ 2012 Financial and Economic Prices. US$'000 Dvoynik Escape-1 Escape-2 Troynik Peresechenie Prokop Kharkhur Tashrabad Rostgoy Jilvon Total ForeignExchange % Total Forex % SCF EconomicCost 1/

Civil Works - earthworks 487.5 292.0 329.1 716.9 356.8 626.9 136.0 55.0 142.4 6.7 3,149.4 30% 944.8 80% 2,708.5 - structures 140.1 85.5 219.7 27.5 27.0 34.5 142.8 327.6 500.9 157.9 1,663.5 30% 499.0 80% 1,430.6 Sub-total civil works 627.62 377.46 548.77 744.40 383.74 661.47 278.74 382.66 643.34 164.62 4,812.84 30% 1,443.9 80% 4,139.0 Equipment - mechanical 605.4 189.0 223.2 250.1 175.3 324.8 192.4 114.3 26.0 36.4 2,137.0 80% 1,709.6 80% 2,051.5 - electrical 49.6 13.4 13.4 46.3 33.4 40.1 36.7 73.0 36.7 22.9 365.5 80% 292.4 80% 350.8 - instrumentation 2.4 - - - 2.4 - 2.4 3.8 2.4 2.4 15.7 80% 12.6 80% 15.1 Sub-total equipment 657.4 202.4 236.6 296.4 211.1 364.8 231.5 191.2 65.2 61.7 2,518.2 80% 2,014.6 80% 2,417.5 Total Base Cost 1,285.1 579.8 785.4 1,040.8 594.9 1,026.3 510.2 573.8 708.5 226.3 7,331.1 47% 3,458.4 80% 6,556.5 Physical Contingencies - Civils rate % 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% - Cost 62.8 37.7 54.9 74.4 38.4 66.1 27.9 38.3 64.3 16.5 481.3 47% 292.4 80% 413.9 - Equipment rate % 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% - Cost 65.7 20.2 23.7 29.6 21.1 36.5 23.1 19.1 6.5 6.2 251.8 241.8 Total Cost incl contingencies 1,413.6 637.8 863.9 1,144.9 654.4 1,128.9 561.2 631.2 779.3 249.0 8,064.2 3,750.8 1.60 7,212.2 Source : PPTA estimates Note 1/ No currency adjustment applied Table A.13 Capital Cost. DSS & SCADA @constant 2012 financial and economic prices. US$'000

Foreign Foreign Local Economic Total cost scf % Item % cost cost cost Equipment - Computer 50.0 85% 42.5 7.5 80% 48.5 - SCADA 320.0 100% 320.0 0.0 80% 320.0 - Software 50.0 100% 50.0 0.0 80% 50.0 - Survey equipment 12.0 100% 12.0 0.0 80% 12.0 - Meteorological equipment 100.0 100% 100.0 0.0 80% 100.0 - Remote sensing materials 300.0 100% 300.0 0.0 80% 300.0 Sub-total equipment 832.0 99% 824.5 7.5 830.5 Training 60.0 10% 6.0 54.0 80% 49.2 Consultancy International consultants 360.0 100% 360.0 0.0 80% 360.0 National consultants 75.0 0% 0.0 75.0 80% 60.0 International transport 12.0 100% 12.0 0.0 0% 12.0 Sub-total consultants 447.0 83% 372.0 75.0 432.0 Project Management & Administration Reporting 10.0 10% 1.0 9.0 80% 8.2 Local transport 6.0 0% 0.0 6.0 80% 4.8 Administration 95.5 5% 4.8 90.7 80% 77.4 Sub-total Project Management 111.5 5% 5.8 105.7 90.4 Total Base Cost 1,450.5 1,208.3 242.2 1,402.1 Physical contingencies 10% 145.1 120.8 24.2 80% 140.2 Total cost including contingencies 1,595.6 83% 1,329.1 266.4 1,542.3 Source : PPTA estimates Table A.14 Capital Costs - Water Conservation Demonstration Initiative. (3 sites) @ constant 2012 financial and economic prices. US$'000 Unit cost 1 Farm 2 Farm 3 Farm Extension Area Capacity Building Total Forex % Total forex Scf % Economic Cost Civil works Inter-farm canals - Structures/repairs 25.0 75.0 75.0 20% 15.0 80% 63.0 - Sediment removal 28.0 84.0 84.0 20% 16.8 80% 70.6 On-farm canals - Structures/repairs 24.2 24.2 24.2 24.2 72.6 20% 14.5 80% 61.0 - Sediment removal 10.0 10.0 10.0 10.0 30.0 20% 6.0 80% 25.2 Demonstration plot - Structures/repairs 7.0 7.0 7.0 7.0 21.0 20% 4.2 80% 17.6 - Canal repairs 10.0 10.0 10.0 10.0 30.0 20% 6.0 80% 25.2 - Sediment removal 4.0 4.0 4.0 4.0 12.0 20% 2.4 80% 10.1 Sub-total earth moving 42.0 14.0 14.0 14.0 84.0 126.0 20% 25.2 80% 105.8 Sub-total structures 66.2 41.2 41.2 41.2 75.0 198.6 20% 39.7 80% 166.8 Sub-total civils 55.2 55.2 55.2 159.0 324.6 20% 64.9 272.7 Equipment - Computer/printer/UPS 2.0 2.0 2.0 2.0 4.0 10.0 80% 8.0 80% 9.6 - EC/pH meter 0.1 0.1 0.1 0.1 0.3 100% 0.3 80% 0.3 - Soil testing kit/reagents 0.3 0.3 0.3 0.3 0.9 100% 0.9 80% 0.9 - Sonic depth-velocity meter 25.0 75.0 75.0 100% 75.0 80% 75.0 - Field tensiometers 0.2 2.4 2.4 2.4 6.0 13.2 100% 13.2 80% 13.2 - Wetting front detectors 0.1 1.2 1.2 1.2 3.0 6.6 100% 6.6 80% 6.6 - Drip Irrigation System 45.0 45.0 45.0 45.0 135.0 80% 108.0 80% 129.6 - Pressure irrigation system 15.0 15.0 15.0 15.0 45.0 80% 36.0 80% 43.2 - Micro-meteorology station 10.0 20.0 20.0 100% 20.0 80% 20.0 - Class A pan evaporimeter 3.0 9.0 9.0 80% 7.2 80% 8.6 - Water table loggers 2.5 7.5 7.5 100% 7.5 80% 7.5 - Mulching machine 3.0 3.0 3.0 3.0 9.0 80% 7.2 80% 8.6 Sub-total equipment 69.0 69.0 69.0 120.5 4.0 331.5 87% 289.9 323.2 Training - WUA training IWRM principles 20.0 60.0 60.0 0% - 80% 48.0 - WUA training - conservation 20.0 60.0 60.0 0% - 80% 48.0 - WUA training - monitoring 20.0 60.0 60.0 0% - 80% 48.0 - ToT WUAs 10.0 30.0 30.0 0% - 80% 24.0 - Workshops - WUA staff 30.0 120.0 120.0 0% - 80% 96.0 - Workshops farmers 30.0 30.0 30.0 30.0 90.0 0% - 80% 72.0 - Workshop National 40.0 40.0 40.0 0% - 80% 32.0 - Farm visits 30.0 30.0 30.0 30.0 90.0 0% - 80% 72.0 - Community awareness 10.0 30.0 30.0 0% - 80% 24.0 - Curriculum development 15.0 45.0 45.0 0% - 80% 36.0 - Retail staff training 40.0 40.0 40.0 0% - 80% 32.0 Sub-total training 60.0 60.0 60.0 445.0 40.0 665.0 - - 532.0 Field operations - Drilling piezometers 1.5 1.5 1.5 1.5 3.0 7.5 20% 1.5 80% 6.3 - Deep ripping 5.0 5.0 5.0 5.0 15.0 20% 3.0 80% 12.6 - Laser levelling 8.0 8.0 8.0 8.0 24.0 80% 19.2 80% 23.0 - Minimum tillage 1.4 1.4 1.4 1.4 4.2 20% 0.8 80% 3.5 - Instrument maintenance 4.0 4.0 4.0 50% 2.0 80% 3.6 - Servicing micro-met services 3.0 6.0 6.0 50% 3.0 80% 5.4 - Shelter belt establishment 2.0 2.0 2.0 2.0 6.0 0% - 80% 4.8 - Pest control 2.0 2.0 2.0 2.0 6.0 20% 1.2 80% 5.0 - Crop budget 40.0 40.0 40.0 40.0 120.0 20% 24.0 80% 100.8 Sub-total field operations 59.9 59.9 59.9 9.0 4.0 192.7 28% 53.2 158.8 Retail Outlet establishment 240.0 240.0 240.0 50% 120.0 80% 216.0 Total 244.1 244.1 244.1 973.5 48.0 1,753.8 30% 528.1 1,502.7 Physical Contingencies 10% 24.4 24.4 24.4 97.4 4.8 175.4 52.8 150.3 Grand total including contingencies 268.5 268.5 268.5 1,070.9 52.8 1,929.2 580.9 1,652.9 Source : PPTA estimates

Table A.15 A. Consultant Services. International Staff @ constant 2012 financial prices. US$'000 Work months

A. International Consultants Persons Visits Unit Yr 1 2 3 4 5 6 7 Total Unit cost

Project Management, Monitoring and Evaluation US$'000 Water Resources Engineer/Team Leader 1 6 pm 4 5 6 6 6 6 33 21.0 Social and Economic M&E Specialist 1 2 pm 1 1 2 21.0 Environmentalist (M&E) 1 6 pm 2 2 2 2 2 2 12 21.0 Social Safeguards & Gender Specialist 1 2 pm 1 1 2 21.0 Climate Change Adaptation Specialist 1 2 pm 2 2 4 21.0 Climate Change Mitigation Specialist/Carbon Credit Specialist 1 1 pm 1 1 21.0 Engineering Procurement & Construction Supervision Chief Resident Engineer 1 5 pm 4 11 11 11 11 48 21.0 Mechanical Engineers - design 1 4 pm 4 4 2 2 12 21.0 Electrical Engineers (HV+Switch Gear) 1 3 pm 2 3 3 8 21.0 Electrical Engineers (Motors and Auxiliary Facilities) 1 3 pm 2 2 4 8 21.0 Civil Engineers (Structual Design) 1 4 pm 3 3 3 3 12 21.0 Hydrologist 1 1 pm 4 4 21.0 Geotechnical Specialist 1 1 pm 3 3 21.0 DSS & SCADA Preparation Specialist 1 1 pm 2 2 21.0 Survey Engineer 1 1 pm 2 2 21.0 Procurement/Contract Specialist 1 4 pm 5 3 2 2 12 21.0 Instrumentation Engineer 1 2 pm 2 2 4 21.0 Institutional Support, Capacity Building and Training Extension Specialist 1 1 pm 4 4 21.0 Irrigation and Drainage Specialist 1 2 pm 2 2 4 21.0 Monitoring & Change Management Specialist 1 2 pm 2 2 4 21.0 WUA Specialist 1 2 pm 4 4 8 21.0 Hydrometeorologist 1 1 pm 3 3 21.0 Unallocated 6 6 pm 4 4 4 12 21.0 Total International months 62 pm 38 43 41 39 22 21 0 204 Total International Trips local trips 15 19 18 14 6 7 79 Source : PPTA estimates int trips 12 17 12 11 5 5 62

Base Cost US$'000 Economic Economic/Financial Yr 1 2 3 4 5 6 7 Total forex % Total forex Scf % cost ratio

84.0 105.0 126.0 126.0 126.0 126.0 - 693.0 100% 693.0 80% 693.0 100% - 21.0 - - - 21.0 - 42.0 100% 42.0 80% 42.0 100% 42.0 42.0 42.0 42.0 42.0 42.0 - 252.0 100% 252.0 80% 252.0 100% - 21.0 - - - 21.0 - 42.0 100% 42.0 80% 42.0 100% - - - 42.0 42.0 - - 84.0 100% 84.0 80% 84.0 100% - - - - 21.0 - - 21.0 100% 21.0 80% 21.0 100%

- 84.0 231.0 231.0 231.0 231.0 - 1,008.0 100% 1,008.0 80% 1,008.0 100% 84.0 84.0 42.0 42.0 - - - 252.0 100% 252.0 80% 252.0 100% - 42.0 63.0 63.0 - - - 168.0 100% 168.0 80% 168.0 100% - 42.0 42.0 84.0 - - - 168.0 100% 168.0 80% 168.0 100% 63.0 63.0 63.0 63.0 - - - 252.0 100% 252.0 80% 252.0 100% - 84.0 - - - - - 84.0 100% 84.0 80% 84.0 100% 63.0 ------63.0 100% 63.0 80% 63.0 100% - 42.0 - - - - - 42.0 100% 42.0 80% 42.0 100% 42.0 ------42.0 100% 42.0 80% 42.0 100% 105.0 63.0 42.0 42.0 - - - 252.0 100% 252.0 80% 252.0 100% - 42.0 42.0 - - - - 84.0 100% 84.0 80% 84.0 100%

84.0 ------84.0 100% 84.0 80% 84.0 100% 42.0 42.0 - - - - - 84.0 100% 84.0 80% 84.0 100% 42.0 42.0 - - - - - 84.0 100% 84.0 80% 84.0 100% 84.0 - 84.0 - - - - 168.0 100% 168.0 80% 168.0 100% 63.0 ------63.0 100% 63.0 80% 63.0 100% - 84.0 84.0 84.0 - - - 252.0 100% 252.0 80% 252.0 100% 798.0 903.0 861.0 819.0 462.0 441.0 - 4,284.0 4,284.0 4,284.0 100% Table A.15 B.Consultant Services. National Staff @ constant 2012 financial prices. US$'000 Work months B. National Consultants Persons Visits Yr 1 2 3 4 5 6 7 Total Unit cost Yr 1 Project Management US$'000

Hydroelectric Engineer/Deputy Team Leader 1 19 pm 11 11 11 11 11 11 6 72 3.0 33.0 Social and Economic M&E Specialist 1 6 pm 3 3 3 3 3 3 18 3.0 9.0 Environmentalist (M&E) 1 6 pm 3 3 3 3 3 3 18 3.0 9.0 Social Safeguards & Gender Specialist 1 6 pm 2 2 2 2 2 2 12 3.0 6.0 Climate Change Adaptation Specialist 1 2 pm 2 2 4 3.0 - Climate Change Mitigation Specialist/Carbon Credit Specialist 1 3 pm 3 3 3 9 3.0 - Engineering Procurement & Construction Supervision Resident Engineer 1 18 pm 7 11 11 11 11 11 3 65 3.0 21.0 Mechanical Engineer - Design 1 5 pm 5 5 2 12 3.0 15.0 Electrical Engineer - HV 1 2 pm 2 2 4 3.0 - HVAC Engineer 1 2 pm 2 2 4 3.0 - Electrical Engineers (Motors and Auxiliary Facilities) 1 3 pm 4 4 4 12 3.0 12.0 Civil Engineers (Structual Design) 1 3 pm 4 4 4 12 3.0 12.0 Bridge Engineer - design 1 2 pm 2 2 4 3.0 - Hydrologist 1 2 pm 6 2 8 3.0 - Geotechnical Specialist 1 3 pm 5 3 8 3.0 15.0 Survey Engineer 1 6 pm 2 1 1 1 1 1 7 3.0 6.0 Procurement/Contract Specialist 1 8 pm 6 6 6 6 24 3.0 18.0 Instrumentation 1 2 pm 3 2 5 3.0 - Electrical Engineer (Installation of Pump and other facilities) 2 12 pm 4 12 12 8 36 3.0 - Pump Station Civil Works Inspectors (Measurement and Quality control) 2 16 pm 16 16 16 12 60 3.0 - Mechanical & Electrical Works Inspectors 2 6 pm 18 18 18 54 3.0 - Electrical Engineer (Transmission and installation facilities) 1 5 pm 6 6 4 16 3.0 - ABMK Civil Works Inspectors 2 6 pm 6 6 6 18 3.0 - Bridge Engineer (Structures and building) 1 2 pm 4 4 8 3.0 - Institutional Support, Capacity Building and Training Extension Specialist 1 7 pm 6 6 3 3 2 20 3.0 18.0 Irrigation & Drainage Specialist & OFWM Specialist 1 12 pm 6 6 6 6 6 6 36 3.0 18.0 Institutional Specialist (extension) 1 5 pm 4 4 4 4 4 20 3.0 - Monitoring & Change Management Specialist 1 4 pm 3 3 3 3 12 3.0 - Agronomist 1 12 pm 6 6 6 6 6 6 36 3.0 18.0 WUA Specialist 1 7 pm 6 4 6 6 22 3.0 18.0 Hydrometeorologist 1 3 pm 6 3 9 3.0 18.0 Unallocated 12 18 pm 12 12 12 36 3.0 - Total National Consultants 213 pm 82 118 130 129 114 99 9 681 246.0 Trips 15 41 44 44 34 32 3 213 Source : PPTA estimates Base Cost US$'000 Economic Economic/Financial 2.0 2.0 3.0 4.0 5.0 6.0 7.0 Total forex % Total forex Scf % cost ratio

33.0 33.0 33.0 33.0 33.0 33.0 18.0 216.0 0% - 80% 172.8 80% 9.0 9.0 9.0 9.0 9.0 9.0 - 54.0 0% - 80% 43.2 80% 9.0 9.0 9.0 9.0 9.0 9.0 - 54.0 0% - 80% 43.2 80% 6.0 6.0 6.0 6.0 6.0 6.0 - 36.0 0% - 80% 28.8 80% - - - 6.0 - 6.0 - 12.0 0% - 80% 9.6 80% 9.0 9.0 9.0 - - 9.0 - 27.0 0% - 80% 21.6 80%

33.0 33.0 33.0 33.0 33.0 33.0 9.0 195.0 0% - 80% 156.0 80% 15.0 15.0 6.0 - - - - 36.0 0% - 80% 28.8 80% 6.0 6.0 6.0 - - - - 12.0 0% - 80% 9.6 80% 6.0 6.0 6.0 - - - - 12.0 0% 80% 9.6 80% 12.0 12.0 12.0 - - - - 36.0 0% 80% 28.8 80% 12.0 12.0 12.0 - - - - 36.0 0% - 80% 28.8 80% 6.0 6.0 6.0 - - - - 12.0 0% - 80% 9.6 80% 18.0 18.0 6.0 - - - - 24.0 0% - 80% 19.2 80% 9.0 9.0 - - - - - 24.0 0% - 80% 19.2 80% 3.0 3.0 3.0 3.0 3.0 3.0 - 21.0 0% - 80% 16.8 80% 18.0 18.0 18.0 18.0 - - - 72.0 0% - 80% 57.6 80% 9.0 9.0 6.0 - - - - 15.0 0% 80% 12.0 80% - - 12.0 36.0 36.0 24.0 - 108.0 0% - 80% 86.4 80% - - 48.0 48.0 48.0 36.0 - 180.0 0% - 80% 144.0 80% - - - 54.0 54.0 54.0 - 162.0 0% - 80% 129.6 80% 18.0 18.0 18.0 - 12.0 - - 48.0 0% - 80% 38.4 80% - - - 18.0 18.0 18.0 - 54.0 0% - 80% 43.2 80% - - 12.0 12.0 - - - 24.0 0% - 80% 19.2 80%

18.0 18.0 9.0 9.0 6.0 - - 60.0 0% - 80% 48.0 80% 18.0 18.0 18.0 18.0 18.0 18.0 - 108.0 0% - 80% 86.4 80% 12.0 12.0 12.0 12.0 12.0 12.0 - 60.0 0% - 80% 48.0 80% - - 9.0 9.0 9.0 9.0 - 36.0 0% 80% 28.8 80% 18.0 18.0 18.0 18.0 18.0 18.0 - 108.0 0% - 80% 86.4 80% 12.0 12.0 18.0 - 18.0 - - 66.0 0% - 80% 52.8 80% 9.0 9.0 - - - - - 27.0 0% 80% 21.6 80% 36.0 36.0 36.0 36.0 - - - 108.0 0% - 80% 86.4 80% 354.0 354.0 390.0 387.0 342.0 297.0 27.0 2,043.0 - 1,634.4 80% Table A.15 C. Consultant Services. Supporting Services @ constant 2012 financial prices. US$'000 Units

Yr 1 2 3 4 5 6 7 Total Unit cost Yr 1 C. Consultant Support. Per diems and travel International Perdiems mths 38 43 41 39 22 21 0 204 3.0 114.0 International Transport trips 12 17 12 11 5 5 0 62 2.5 30.0 Local Transport for International Staff trips 15 19 18 14 6 7 79 0.2 3.0 Local Transport for National Staff trips 15 41 44 44 34 32 3 213 0.2 3.0 Total Consultant Support 150.0

D. Office Equipment and Vehicles Vehicles - Tashkent based no 2 2 20.0 40.0 Vehicles - Field based no 5 5 35.0 175.0 Computers/Printers/Copiers no 20 20 1.5 30.0 Photocopier no 1 1 1.5 1.5 Furniture ls 1 1 3.0 3.0 Communications equipment ls 1 1 1.0 1.0 Air Conditioners no 6 6 0.5 3.0 Total Office Equipment and Vehicles 253.5

E. Workshops/training - general ls 0.4 0.4 0.3 1 150.0 - - gender ls 0.2 0.1 0.2 0.1 0.2 350.8 - Sub-total workshops/training -

F. Office operation & management - Administrative staff pm 60 60 60 60 60 60 20 380 1.0 60.0 - Report preparation ls 1 1 1 1 1 1 6 2.0 2.0 - Other costs ls 12 12 12 12 12 12 6 78 1.0 12.0 Total Office Operation 74.0

G. Surveys - Geotechnical ls 0.5 0.5 500 - - Remote sensing ls 0.5 0.5 25 - Total surveys -

Total Consultants Base Cost 1,521.5 Physical contingencies 8% 121.7 Total Cost including contingencies 1,643.2 Source : PPTA estimates Base Cost US$'000 Economic Economic/Financial 2.0 3.0 4.0 5.0 6.0 7.0 Total forex % Total forex Scf % cost ratio

129.0 123.0 117.0 66.0 63.0 - 612.0 100% 612.0 80% 612.0 100% 42.5 30.0 27.5 12.5 12.5 - 155.0 100% 155.0 80% 155.0 100% 3.8 3.6 2.8 1.2 1.4 - 15.8 0% - 80% 12.6 80% 8.2 8.8 8.8 6.8 6.4 0.6 42.6 0% - 80% 34.1 80% 183.5 165.4 156.1 86.5 83.3 0.6 825.4 767.0 813.7 99%

------40.0 40% 16.0 80% 35.2 88% ------175.0 40% 70.0 80% 154.0 88% ------30.0 85% 25.5 80% 29.1 97% ------1.5 85% 1.3 80% 1.5 97% ------3.0 20% 0.6 80% 2.5 84% ------1.0 85% 0.9 80% 1.0 97% ------3.0 85% 2.6 80% 2.9 97% ------253.5 116.8 226.2 89%

52.5 - 52.5 - 45.0 - 150.0 10% 15.0 80% 123.0 82% 86.5 48.7 86.5 48.7 80.4 - 350.8 10% 35.1 80% 287.6 82% 139.0 48.7 139.0 48.7 125.4 - 500.8 50.1 410.6 82%

60.0 60.0 60.0 60.0 60.0 20.0 380.0 0% - 80% 304.0 80% 2.0 2.0 2.0 2.0 2.0 - 12.0 20% 2.4 80% 10.1 84% 12.0 12.0 12.0 12.0 12.0 6.0 78.0 20% 15.6 80% 65.5 84% 74.0 74.0 74.0 74.0 74.0 26.0 470.0 4% 18.0 80% 379.6 81%

250.0 250.0 - - - - 500.0 50% 250.0 80% 450.0 90% 12.5 12.5 - - - - 25.0 100% 25.0 80% 25.0 100% 262.50 262.50 - - - - 525.00 150% 275.00 1.60 475.00 90%

1,916.0 1,801.6 1,575.1 1,013.2 1,020.7 53.6 8,901.7 1,226.9 7,368.9 83% 153.3 144.1 126.0 81.1 81.7 4.3 712.1 98.1 589.5 83% 2,069.3 1,945.7 1,701.1 1,094.2 1,102.4 57.9 9,613.8 1,325.0 7,958.4 83% Table A.16 Capital Costs. PMO. @ constant 2012 financial prices. US$'000 Units

Unit Yr 1 2 3 4 5 6 7 Total Unit cost Yr 1 1. Staff Professional Staff - Project Manager pm 12 12 12 12 12 12 0.5 72.5 1.0 12.0 - Acountant pm 12 12 12 12 12 12 0.5 72.5 0.8 9.6 - Procurement Specialist pm 12 12 12 12 12 12 0.5 72.5 0.8 9.6 Sub-total Professional staff 31.2 Support Staff - Secretary/Computer Operator pm 12 12 12 12 12 12 0.5 72.5 0.5 6.0 - Translator pm 12 12 12 12 12 12 0.5 72.5 0.5 6.0 - Office Assistant pm 12 12 12 12 12 12 0.5 72.5 0.4 4.8 - Driver pm 12 12 12 12 12 12 0.5 72.5 0.4 4.8 Sub-total Support Staff 21.6 Total all staff 52.8 2. Vehicles and Equipment - Vehicle - sedan no 1 1 20.0 20.0 - Computers/Printers/UPS no 3 3 1.5 4.5 - Air conditioners no 3 3 0.5 1.5 - Photocopier no 1 1 1.0 1.0 - Furniture ls 1 1 1.0 1.0 - Communications equipment ls 1 1 1.0 1.0 Sub-total Vehicles and Equipment 29.0 Other 3. Office Renovation ls 1 10.0 10.0 4. Annual Audits ls 1 1 1 1 1 1 1.0 7 15.0 15.0 5. Vehicle operation mth 12 12 12 12 12 12 6.0 78 0.3 3.6 6. Office Operation - Staff travel and allowances ls 1 1 1 1 1 1 0.5 6.5 8.0 8.0 - Office expenses ls 12 12 12 12 12 12 0.5 72.5 0.5 6.0 - Communications ls 12 12 12 12 12 12 0.5 72.5 0.3 3.6 Sub-total Office Operation 46.2

Total PMO Base Costs 128.0 Physical Contingencies 8% 10.2 Total PMO Cost including contingencies 138.2 Source : PPTA estimates Base Cost US$'000 Economic Economic/Financial 2 3 4 5 6 7 Total forex % Total forex Scf % cost ratio

12.0 12.0 12.0 12.0 12.0 0.5 72.5 0% - 80% 58.0 80% 9.6 9.6 9.6 9.6 9.6 0.4 58.0 0% - 80% 46.4 80% 9.6 9.6 9.6 9.6 9.6 0.4 58.0 0% - 80% 46.4 80% 31.2 31.2 31.2 31.2 31.2 1.3 188.5 - 104.4 55%

6.0 6.0 6.0 6.0 6.0 0.3 36.3 0% - 80% 29.0 80% 6.0 6.0 6.0 6.0 6.0 0.3 36.3 0% - 80% 29.0 80% 4.8 4.8 4.8 4.8 4.8 0.2 29.0 0% - 80% 23.2 80% 4.8 4.8 4.8 4.8 4.8 0.2 29.0 0% - 80% 23.2 80% 21.6 21.6 21.6 21.6 21.6 0.9 130.5 - 104.4 80% 52.8 52.8 52.8 52.8 52.8 2.2 319.0 - 208.8 65%

------20.0 40% 8.0 80% 17.6 88% ------4.5 85% 3.8 80% 4.4 97% ------1.5 85% 1.3 80% 1.5 97% ------1.0 85% 0.9 80% 1.0 97% ------1.0 20% 0.2 80% 0.8 84% ------1.0 85% 0.9 80% 1.0 97% ------29.0 15.0 26.2 90%

------10.0 10% 1.0 80% 8.2 82% 15.0 15.0 15.0 15.0 15.0 15.0 105.0 0% - 80% 84.0 80% 3.6 3.6 3.6 3.6 3.6 1.8 23.4 10% 2.3 80% 19.2 82%

8.0 8.0 8.0 8.0 8.0 4.0 52.0 0% - 80% 41.6 80% 6.0 6.0 6.0 6.0 6.0 0.3 36.3 20% 7.3 80% 30.5 84% 3.6 3.6 3.6 3.6 3.6 0.2 21.8 0% - 80% 17.4 80% 36.2 36.2 36.2 36.2 36.2 21.2 248.4 10.6 200.8 81%

89.0 89.0 89.0 89.0 89.0 23.4 596.4 25.6 435.8 73% 7.1 7.1 7.1 7.1 7.1 1.9 47.7 2.0 34.9 73% 96.1 96.1 96.1 96.1 96.1 25.3 644.1 27.6 470.7 73% Table A.17 Capital Costs. PIU. @ constant 2012 financial prices. US$'000 Units

1. Staff Unit Yr 1 2 3 4 5 6 7 Total Unit cost Yr 1 Professional Staff - Deputy Project Manager pm 12 12 12 12 12 12 6 78 0.8 9.6 - Assistant Accountant pm 12 12 12 12 12 12 6 78 0.8 9.6 - Procurement Specialist pm 12 12 12 12 12 12 6 78 0.8 9.6 - DSS/Environment M&E pm 12 12 12 12 12 12 6 78 0.8 9.6 Sub-total Professional staff 38.4 Support Staff - Secretary/Computer Operator pm 12 12 12 12 12 12 6 78 0.5 6.0 - Translator pm 24 24 24 24 24 24 12 156 0.5 12.0 - Office Assistant pm 12 12 12 12 12 12 6 78 0.4 4.8 - Drivers pm 12 12 12 12 12 12 6 78 0.4 4.8 Sub-total Support Staff 27.6 Total all staff 66.0 2. Vehicles and Equipment - Vehicle - sedan no 1 1 20.0 20.0 - Computers/Printers/UPS no 3 3 1.5 4.5 - Air conditioners no 3 3 1.0 3.0 - Photocopier no 1 1 1.0 1.0 - Furniture ls 1 1 1.0 1.0 - Communications equipment ls 1 1 1.0 1.0 Sub-total Vehicles and Equipment 30.5 Other 3. Office Renovation ls 1 1 10.0 10.0 4. Vehicle operation mth 12 12 12 12 12 12 6 78 0.3 3.6 5. Office Operation - Staff travel and allowances ls 1 1 1 1 1 1 6 8.0 8.0 - Office expenses ls 12 12 12 12 12 12 72 0.4 4.8 - Communications ls 12 12 12 12 12 12 72 0.4 4.8 Sub-total Office Operation 31.2

Total PIU Base Costs 127.7 Physical Contingencies 8% 10.2 Total PUI Cost including contingencies 137.9 Source : PPTA estimates Base Cost US$'000 Economic Economic/Financial 2 3 4 5 6 7 Total forex % Total forex Scf % cost ratio

9.6 9.6 9.6 9.6 9.6 4.8 62.4 0% - 80% 49.9 80% 9.6 9.6 9.6 9.6 9.6 4.8 62.4 0% - 80% 49.9 80% 9.6 9.6 9.6 9.6 9.6 4.8 62.4 9.6 9.6 9.6 9.6 9.6 4.8 62.4 0% - 80% 49.9 80% 38.4 38.4 38.4 38.4 38.4 19.2 249.6 - 149.8 60%

6.0 6.0 6.0 6.0 6.0 3.0 39.0 0% - 80% 31.2 80% 12.0 12.0 12.0 12.0 12.0 6.0 78.0 0% - 80% 62.4 80% 4.8 4.8 4.8 4.8 4.8 2.4 31.2 0% - 80% 25.0 80% 4.8 4.8 4.8 4.8 4.8 2.4 31.2 0% - 80% 25.0 80% 27.6 27.6 27.6 27.6 27.6 13.8 179.4 - 143.5 80% 66.0 66.0 66.0 66.0 66.0 33.0 429.0 - 293.3 68%

------20.0 40% 8.0 80% 17.6 88% ------4.5 85% 3.8 #REF! #REF! #REF! ------3.0 85% 2.6 #REF! #REF! #REF! ------1.0 85% 0.9 #REF! #REF! #REF! ------1.0 20% 0.2 #REF! #REF! #REF! ------1.0 85% 0.9 #REF! #REF! #REF! ------30.5 16.3 #REF! #REF!

------10.0 10% 1.0 80% 8.2 82% 3.6 3.6 3.6 3.6 3.6 1.8 23.4 10% 2.3 80% 19.2 82%

8.0 8.0 8.0 8.0 8.0 - 48.0 0% - 80% 38.4 80% 4.8 4.8 4.8 4.8 4.8 - 28.8 20% 5.8 80% 24.2 84% 4.8 4.8 4.8 4.8 4.8 - 28.8 0% - 80% 23.0 80% 21.2 21.2 21.2 21.2 21.2 1.8 139.0 9.1 113.0 81%

87.2 87.2 87.2 87.2 87.2 34.8 598.5 25.4 #REF! 7.0 7.0 7.0 7.0 7.0 2.8 47.9 2.03 #REF! 94.2 94.2 94.2 94.2 94.2 37.6 646.4 27.41 #REF! #REF! 1,194.9 Table A.18 Part A Pump Capacity , Pumped Volumes available to Stage 2 pump stations. Assumed 'Without-Project'. Reduced Cost Option. Pumps decline Stage 1 - Khamza PS unit unit value base Year 1 2 3 4 5 6 7 8 9 Khamza pumps capacity Khamza 1 m3/s/PS 65 65 65 65 65 62 59 56 53 50 48 Khamza Aux m3/s/PS 20 20 20 20 20 19 18 17 16 15 15 Khamza 2 m3/s/PS 135 135 135 135 135 135 135 128 122 116 110 Total Khamza. Stage 1 capacity m3/s 220 220 220 220 220 209 199 189 179 170 162 Proportion of 2012 capacity 100% 100% 100% 95% 90% 86% 81% 77% 74% Pump time % of maximum 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% Volume pumped peak month from Stage 1 m3/s peak month 202 202 202 202 192 183 174 165 157 149 - Less other direct offtakes m3/s peak month 5 -5 -5 -5 -5 -5 -5 -5 -5 -5 -5 Stage 2 - Karaul Bazar PS irrigated area - ha 15,907 Karaul Bazar pump capacity m3/s peak month 32 32 32 32 32 32 32 32 32 32 32 - Less Karaul Bazar offtake m3/s peak month 19 -19 -19 -19 -19 -19 -19 -19 -19 -19 -19 - Less main ABMK losses m3/s peak month 7% -14 -14 -14 -14 -14 -14 -14 -14 -14 -14 Available at Tudakul Diversion m3/s peak month 165 165 165 165 155 145 136 127 119 111 Proportion of 2012 availabilty % 100% 100% 100% 100% 94% 88% 82% 77% 72% 67% Flow division at Tudakul Diversion (TD) (a) Allocation to Kuyu Mazar PS (KM) % 39% 39% 39% 39% 39% 39% 39% 39% 39% 39% To Kuyu Mazar PS m3/s peak month max 60 64 64 64 64 60 57 53 50 46 43 - Losses between TD and KM (17 km) m3/s peak month 2% -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 + From Kuyu Mazar & Tudakul Lakes m3/s peak month max 44 44 44 44 44 41 39 36 34 32 30 Available at Kuyu Mazar PS m3/s peak month 111 107 107 107 107 100 94 88 82 77 72 Proportion of 2012 availabilty % 100% 100% 100% 100% 94% 88% 82% 77% 72% 67% (b) Allocation to Kizil Tepa PS (KT) % 61% 61% 61% 61% 61% 61% 61% 61% 61% 61% To Kizil Tepa PS m3/s peak month 100 100 100 100 94 88 83 78 73 68 - Losses between TD and KT (38 km) m3/s peak month 3% -3 -3 -3 -3 -3 -3 -3 -3 -3 -3 + From Tudakul Lake m3/s peak month max 28 24 24 24 24 23 21 20 19 17 16 Available at Kizil Tepa PS m3/s peak month 123 121 121 121 121 114 107 100 93 87 81 Proportion of 2012 availabilty % 100% 100% 100% 100% 94% 88% 82% 77% 72% 67% 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

45 43 41 39 37 35 33 32 30 29 27 26 25 23 22 21 14 13 13 12 11 11 10 10 9 9 8 8 8 7 7 6 104 99 94 90 85 81 77 73 69 66 63 59 56 54 51 48 154 146 139 132 125 119 113 107 102 97 92 87 83 79 75 71 70% 66% 63% 60% 57% 54% 51% 49% 46% 44% 42% 40% 38% 36% 34% 32% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 141 134 128 121 115 109 104 99 94 89 85 80 76 73 69 65 -5 -5 -5 -5 -5 -5 -5 -5 -5 -5 -5 -5 -5 -5 -5 -5

32 32 32 32 32 32 32 32 32 32 32 32 32 32 32 32 -19 -19 -19 -19 -19 -19 -19 -19 -19 -19 -19 -19 -19 -19 -19 -19 -14 -14 -14 -14 -14 -14 -14 -14 -14 -14 -14 -14 -14 -14 -14 -14 104 97 90 84 77 72 66 61 56 51 47 43 39 35 31 28 63% 59% 55% 51% 47% 44% 40% 37% 34% 31% 29% 26% 23% 21% 19% 17%

39% 39% 39% 39% 39% 39% 39% 39% 39% 39% 39% 39% 39% 39% 39% 39% 40 38 35 33 30 28 26 24 22 20 18 17 15 14 12 11 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 28 26 24 22 21 19 18 16 15 14 13 11 10 9 8 7 67 62 58 54 50 46 42 39 36 32 30 27 24 22 19 17 62% 58% 54% 50% 46% 43% 39% 36% 33% 30% 28% 25% 23% 20% 18% 16% 61% 61% 61% 61% 61% 61% 61% 61% 61% 61% 61% 61% 61% 61% 61% 61% 63 59 55 51 47 44 40 37 34 31 29 26 24 21 19 17 -3 -3 -3 -3 -3 -3 -3 -3 -3 -3 -3 -3 -3 -3 -3 -3 15 14 13 12 11 10 10 9 8 7 7 6 6 5 5 4 75 70 65 60 56 51 47 43 39 36 32 29 26 23 21 18 62% 58% 53% 49% 46% 42% 39% 35% 32% 29% 27% 24% 22% 19% 17% 15% Table A.18 Part B Pump Capacity , Pumped Volumes available for irrigation. Assumed 'Without-Project' . Reduced Cost Option. Pumps decline unit unit value base Year 1 2 3 4 5 6 7 8 9 Stage 2 - Kuyu Mazar PS irrigated area - ha 89117 Kuyu Mazar (KM) pump capacity - New PS m3/s/PS 40 40 40 40 40 40 40 40 40 40 40 - Main PS - to Shakrud Canal m3/s/PS 60 60 60 60 60 57 54 51 49 46 44 - Main PS - to Kuyu Mazar Lake m3/s/PS 40 40 40 40 40 38 36 34 33 31 29 Total Kuyu Mazar capacity (to Shakhrud) m3/s/PS 100 100 100 100 100 97 94 91 89 86 84 Proportion of 2012 capacity m3/s/PS % 100% 100% 100% 100% 97% 94% 91% 89% 86% 84% Volume pumped at Kuyu Mazar m3/s peak month 107 107 107 107 100 94 88 82 77 72 Volume pumped as % of 2012 pumping m3/s peak month 100% 100% 100% 100% 94% 88% 82% 77% 72% 67% - DMI and fisheries m3/s peak month 2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 Net available for agriculture m3/s peak month 105 105 105 105 98 92 86 80 75 70 Proportion of 2102 agricultural water % 100% 100% 100% 100% 94% 88% 82% 76% 71% 66% Stage2 - Kizil Tepa PS irrigated area - ha 135915 Kizil Tepa (KT) pump capacity - Kizil Tepa m3/s/PS 109 109 109 109 109 109 109 109 104 98 93 - Kizil Tepa Aux m3/s/PS 20 20 20 20 20 20 20 20 19 18 17 Total Kizil Tepa capacity m3/s/PS 129 129 129 129 129 129 129 129 122 116 110 Proportion of 2012 capacity 100% 100% 100% 100% 100% 100% 100% 95% 90% 86% Volume pumped at Kizil Tepa m3/s peak month 121 121 121 121 114 107 100 93 87 81 Volume pumped as % of 2012 pumping m3/s peak month 100% 100% 100% 100% 94% 88% 82% 77% 72% 67% - DMI and fisheries m3/s peak month 2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 - Net available for agriculture m3/s peak month 119 119 119 119 112 105 98 91 85 79 Proportion of 2102 agricultural water % 100% 100% 100% 100% 94% 88% 82% 76% 71% 66% Total Stage 1 pumping capacity ms/s peak month 220 220 220 220 220 209 199 189 179 170 162 Total Stage 2 pumping capacity ms/s peak month 228.8 229 229 229 229 226 223 220 211 203 195 Decline assumptions Khamza 1 decline % 5% 100% 100% 100% 95% 90% 86% 81% 77% 74% Khamza Aux decline % 5% 100% 100% 100% 95% 90% 86% 81% 77% 74% Khamza 2 decline % 5% 100% 100% 100% 100% 100% 95% 90% 86% 81% Kuyu Mazar decline % 5% 100% 100% 100% 95% 90% 86% 81% 77% 74% Kizil Tepa decline % 5% 100% 100% 100% 100% 100% 100% 95% 90% 86% Kizil Tepa Aux decline % 5% 100% 100% 100% 100% 100% 100% 95% 90% 86% Sources : Table 2 Table 5 Table 6 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 42 40 38 36 34 32 31 29 28 26 25 24 23 22 20 19 28 27 25 24 23 22 21 20 19 18 17 16 15 14 14 13 82 80 78 76 74 72 71 69 68 66 65 64 63 62 60 59 82% 80% 78% 76% 74% 72% 71% 69% 68% 66% 65% 64% 63% 62% 60% 59% 67 62 58 54 50 46 42 39 36 32 30 27 24 22 19 17 62% 58% 54% 50% 46% 43% 39% 36% 33% 30% 28% 25% 23% 20% 18% 16% -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 65 60 56 52 48 44 40 37 34 30 28 25 22 20 17 15 62% 57% 53% 49% 45% 42% 38% 35% 32% 29% 26% 24% 21% 19% 16% 14%

89 84 80 76 72 69 65 62 59 56 53 50 48 46 43 41 16 15 15 14 13 12 12 11 11 10 10 9 9 8 8 7 105 100 95 90 85 81 77 73 70 66 63 60 57 54 51 49 81% 77% 74% 70% 66% 63% 60% 57% 54% 51% 49% 46% 44% 42% 40% 38% 75 70 65 60 56 51 47 43 39 36 32 29 26 23 21 18 62% 58% 53% 49% 46% 42% 39% 35% 32% 29% 27% 24% 22% 19% 17% 15% -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 73 68 63 58 54 49 45 41 37 34 30 27 24 21 19 16 61% 57% 53% 49% 45% 41% 38% 34% 31% 28% 26% 23% 20% 18% 16% 13% 154 146 139 132 125 119 113 107 102 97 92 87 83 79 75 71 187 179 172 166 160 154 148 143 137 133 128 124 119 115 112 108

70% 66% 63% 60% 57% 54% 51% 49% 46% 44% 42% 40% 38% 36% 34% 32% 70% 66% 63% 60% 57% 54% 51% 49% 46% 44% 42% 40% 38% 36% 34% 32% 77% 74% 70% 66% 63% 60% 57% 54% 51% 49% 46% 44% 42% 40% 38% 36% 70% 66% 63% 60% 57% 54% 51% 49% 46% 44% 42% 40% 38% 36% 34% 32% 81% 77% 74% 70% 66% 63% 60% 57% 54% 51% 49% 46% 44% 42% 40% 38% 81% 77% 74% 70% 66% 63% 60% 57% 54% 51% 49% 46% 44% 42% 40% 38% Table A.19 Irrigated Areas and Cropping Patterns. 'Without-Project' Scenario. '000 ha. Reduced Cost Option. Pumps decline

Year 1 2 3 4 5 6 7 8 9 Total Land Area irrigated - Kuyu Mazar '000 ha 89.1 89.1 89.1 89.1 83.5 78.1 73.0 68.2 63.6 59.2 - Kizil Tepa '000 ha 135.9 135.9 135.9 135.9 127.2 118.9 111.1 103.6 96.5 89.8 - Karaul Bazar '000 ha 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 Total irrigated area '000 ha 240.9 240.9 240.9 240.9 226.6 213.0 200.0 187.7 176.0 164.9 % of current level 100% 100% 100% 94% 88% 83% 78% 73% 68% Total Cropped Area - Cotton '000 ha 38% 92.0 92.0 92.0 86.5 81.3 76.4 71.6 67.1 62.9 - Fodder '000 ha 16% 39.7 39.7 39.7 37.4 35.3 33.3 31.3 29.5 27.8 - Vegetables '000 ha 17% 42.0 42.0 42.0 39.4 36.9 34.6 32.3 30.2 28.2 - Fruit '000 ha 10% 23.9 23.9 23.9 22.4 21.0 19.6 18.3 17.1 15.9 - Winter wheat '000 ha 26% 63.2 63.2 63.2 63.2 63.2 63.2 63.2 54.8 51.5 Total crops '000 ha 108% 260.8 260.8 260.8 248.9 237.7 226.9 216.8 198.8 186.2 Cropping pattern Kuyu Mazar - Cotton '000 ha 41% 36.1 36.1 36.1 33.8 31.7 29.6 27.6 25.8 24.0 - Fodder '000 ha 16% 14.5 14.5 14.5 13.6 12.7 11.9 11.1 10.3 9.6 - Vegetables '000 ha 17% 15.5 15.5 15.5 14.6 13.6 12.7 11.9 11.1 10.3 - Fruit '000 ha 11% 9.9 9.9 9.9 9.3 8.7 8.1 7.6 7.1 6.6 - Winter wheat '000 ha 23% 20.4 20.4 20.4 20.4 20.4 20.4 20.4 17.5 16.3 Total crops Kuyu Mazar '000 ha 108% 96.5 96.5 96.5 91.7 87.1 82.8 78.6 71.8 66.8 Cropping pattern Kizil Tepa - Cotton '000 ha 37% 50.2 50.2 50.2 47.0 43.9 41.0 38.3 35.7 33.2 - Fodder '000 ha 15% 20.7 20.7 20.7 19.4 18.1 16.9 15.8 14.7 13.7 - Vegetables '000 ha 19% 25.4 25.4 25.4 23.7 22.2 20.7 19.3 18.0 16.8 - Fruit '000 ha 10% 13.8 13.8 13.8 12.9 12.0 11.3 10.5 9.8 9.1 - Winter wheat '000 ha 27% 36.4 36.4 36.4 36.4 36.4 36.4 36.4 31.1 28.9 Total crops Kizil Tepa '000 ha 108% 146.4 146.4 146.4 139.4 132.7 126.4 120.3 109.2 101.6 Cropping pattern Karaul Bazar - Cotton '000 ha 36% 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 - Fodder '000 ha 28% 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 - Vegetables '000 ha 7% 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 - Fruit '000 ha 1% 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 - Winter wheat '000 ha 40% 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 Total Crops Karaul Bazar '000 ha 112% 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 Sources : Table 3 Table A.18 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

55.1 51.8 48.1 44.6 41.3 38.2 35.2 32.3 29.6 27.1 24.6 22.3 20.1 18.0 16.0 14.2 83.4 78.3 72.6 67.2 62.1 57.2 52.6 48.2 44.1 40.1 36.3 32.7 29.3 26.1 23.1 20.1 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 154.4 146.0 136.7 127.8 119.4 111.3 103.7 96.5 89.6 83.1 76.9 71.0 65.4 60.1 55.0 50.2 64% 61% 57% 53% 50% 46% 43% 40% 37% 34% 32% 29% 27% 25% 23% 21%

58.8 55.6 52.1 48.7 45.4 42.3 39.4 36.6 34.0 31.5 29.1 26.9 24.7 22.7 20.7 18.9 26.1 24.8 23.4 22.0 20.7 19.4 18.2 17.1 16.0 15.0 14.0 13.1 12.2 11.4 10.6 9.8 26.3 24.8 23.1 21.4 19.9 18.5 17.1 15.8 14.5 13.3 12.2 11.1 10.1 9.1 8.2 7.3 14.8 13.9 12.9 12.0 11.1 10.2 9.4 8.7 8.0 7.3 6.6 6.0 5.4 4.8 4.3 3.8 48.3 45.2 42.4 39.6 37.0 34.5 32.2 30.0 27.8 25.8 23.9 22.1 20.4 18.7 17.2 15.7 174.3 164.4 153.8 143.7 134.1 125.0 116.3 108.1 100.3 92.9 85.8 79.1 72.8 66.7 61.0 55.6

22.3 21.0 19.5 18.1 16.8 15.5 14.3 13.1 12.0 11.0 10.0 9.0 8.2 7.3 6.5 5.7 9.0 8.4 7.8 7.3 6.7 6.2 5.7 5.3 4.8 4.4 4.0 3.6 3.3 2.9 2.6 2.3 9.6 9.0 8.4 7.8 7.2 6.7 6.1 5.6 5.2 4.7 4.3 3.9 3.5 3.1 2.8 2.5 6.1 5.8 5.4 5.0 4.6 4.3 3.9 3.6 3.3 3.0 2.7 2.5 2.2 2.0 1.8 1.6 15.1 14.0 13.0 12.0 11.1 10.2 9.4 8.6 7.8 7.1 6.4 5.8 5.2 4.6 4.0 3.5 62.2 58.3 54.1 50.2 46.4 42.8 39.4 36.2 33.2 30.2 27.5 24.8 22.4 20.0 17.7 15.6

30.8 28.9 26.8 24.8 22.9 21.1 19.4 17.8 16.3 14.8 13.4 12.1 10.8 9.6 8.5 7.4 12.7 11.9 11.1 10.2 9.5 8.7 8.0 7.3 6.7 6.1 5.5 5.0 4.5 4.0 3.5 3.1 15.6 14.6 13.6 12.6 11.6 10.7 9.8 9.0 8.2 7.5 6.8 6.1 5.5 4.9 4.3 3.8 8.4 7.9 7.4 6.8 6.3 5.8 5.3 4.9 4.5 4.1 3.7 3.3 3.0 2.6 2.3 2.0 26.8 24.9 23.0 21.3 19.6 18.0 16.5 15.0 13.7 12.4 11.1 10.0 8.9 7.8 6.8 5.9 94.4 88.3 81.8 75.7 69.9 64.3 59.1 54.1 49.3 44.8 40.6 36.5 32.6 29.0 25.5 22.2

5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 0.0 0.0 17.8 17.8 Table A.20 Cropped Area. Cotton, Forage Crops, Vegetables. 'Without-Project' Scenario. '000 ha. Reduced Cost Option. Pumps decline

Cotton Year 1 2 3 4 5 6 7 8 9 Cotton Kuyu Mazar 41% - Out of production '000 ha 0.0 0.0 0.0 2.3 4.5 6.5 8.5 10.4 12.1 - Reduced yield '000 ha 1.8 1.8 1.8 1.7 1.6 1.5 1.4 1.3 1.2 - Unaffected '000 ha 34.3 34.3 34.3 32.2 30.1 28.1 26.3 24.5 22.8 - Total area '000 ha 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 Cotton Kizil Tepa 37% - Out of production '000 ha 0.0 0.0 0.0 3.2 6.3 9.2 11.9 14.5 17.0 - Reduced yield '000 ha 2.5 2.5 2.5 2.3 2.2 2.1 1.9 1.8 1.7 - Unaffected '000 ha 47.7 47.7 47.7 44.6 41.7 39.0 36.4 33.9 31.5 - Total area '000 ha 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 Cotton Karaul Bazar 36% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - Reduced yield '000 ha 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 - Unaffected '000 ha 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.4 - Total area '000 ha 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 Forage Forage Kuyu Mazar 16% - Out of production '000 ha 0.0 0.0 0.0 0.9 1.8 2.6 3.4 4.2 4.9 - Reduced yield '000 ha 0.7 0.7 0.7 0.7 0.6 0.6 0.6 0.5 0.5 - Unaffected '000 ha 13.8 13.8 13.8 12.9 12.1 11.3 10.5 9.8 9.2 - Total area '000 ha 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 Forage Kizil Tepa 15% - Out of production '000 ha 0.0 0.0 0.0 1.3 2.6 3.8 4.9 6.0 7.0 - Reduced yield '000 ha 1.0 1.0 1.0 1.0 0.9 0.8 0.8 0.7 0.7 - Unaffected '000 ha 19.7 19.7 19.7 18.4 17.2 16.1 15.0 14.0 13.0 - Total area '000 ha 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 Forage Karaul Bazar 28% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - Reduced yield '000 ha 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 - Unaffected '000 ha 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 - Total area '000 ha 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 Vegetables Vegetables Kuyu Mazar 17% - Out of production '000 ha 0.0 0.0 0.0 1.0 1.9 2.8 3.7 4.5 5.2 - Reduced yield '000 ha 0.8 0.8 0.8 0.7 0.7 0.6 0.6 0.6 0.5 - Unaffected '000 ha 14.8 14.8 14.8 13.8 12.9 12.1 11.3 10.5 9.8 - Total area '000 ha 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 Vegetables Kizil Tepa 19% - Out of production '000 ha 0.0 0.0 0.0 1.6 3.2 4.6 6.0 7.3 8.6 - Reduced yield '000 ha 1.3 1.3 1.3 1.2 1.1 1.0 1.0 0.9 0.8 - Unaffected '000 ha 24.1 24.1 24.1 22.6 21.1 19.7 18.4 17.1 15.9 - Total area '000 ha 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 Vegetables Karaul Bazar 7% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - Reduced yield '000 ha 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 - Unaffected '000 ha 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 - Total area '000 ha 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 Sources: Table A.19 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

13.8 15.1 16.6 18.0 19.4 20.7 21.9 23.0 24.1 25.2 26.1 27.1 28.0 28.8 29.6 30.4 1.1 1.1 1.0 0.9 0.8 0.8 0.7 0.7 0.6 0.5 0.5 0.5 0.4 0.4 0.3 0.3 21.2 20.0 18.5 17.2 15.9 14.7 13.6 12.5 11.4 10.4 9.5 8.6 7.7 6.9 6.2 5.5 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1

19.4 21.3 23.4 25.4 27.3 29.1 30.8 32.4 33.9 35.4 36.8 38.1 39.4 40.5 41.7 42.8 1.5 1.4 1.3 1.2 1.1 1.1 1.0 0.9 0.8 0.7 0.7 0.6 0.5 0.5 0.4 0.4 29.3 27.5 25.5 23.6 21.8 20.1 18.5 16.9 15.5 14.1 12.7 11.5 10.3 9.2 8.1 7.1 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7

5.5 6.1 6.7 7.2 7.8 8.3 8.8 9.2 9.7 10.1 10.5 10.9 11.2 11.6 11.9 12.2 0.4 0.4 0.4 0.4 0.3 0.3 0.3 0.3 0.2 0.2 0.2 0.2 0.2 0.1 0.1 0.1 8.5 8.0 7.4 6.9 6.4 5.9 5.4 5.0 4.6 4.2 3.8 3.5 3.1 2.8 2.5 2.2 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5

8.0 8.8 9.6 10.5 11.2 12.0 12.7 13.3 14.0 14.6 15.2 15.7 16.2 16.7 17.2 17.6 0.6 0.6 0.6 0.5 0.5 0.4 0.4 0.4 0.3 0.3 0.3 0.2 0.2 0.2 0.2 0.2 12.1 11.3 10.5 9.7 9.0 8.3 7.6 7.0 6.4 5.8 5.3 4.7 4.2 3.8 3.3 2.9 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5

5.9 6.5 7.1 7.8 8.3 8.9 9.4 9.9 10.4 10.8 11.3 11.7 12.0 12.4 12.7 13.1 0.5 0.5 0.4 0.4 0.4 0.3 0.3 0.3 0.3 0.2 0.2 0.2 0.2 0.2 0.1 0.1 9.1 8.6 8.0 7.4 6.9 6.3 5.8 5.4 4.9 4.5 4.1 3.7 3.3 3.0 2.7 2.3 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5

9.8 10.8 11.8 12.8 13.8 14.7 15.5 16.4 17.1 17.9 18.6 19.3 19.9 20.5 21.1 21.6 0.8 0.7 0.7 0.6 0.6 0.5 0.5 0.5 0.4 0.4 0.3 0.3 0.3 0.2 0.2 0.2 14.8 13.9 12.9 11.9 11.0 10.2 9.3 8.6 7.8 7.1 6.4 5.8 5.2 4.6 4.1 3.6 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 Table A.21 Cropped Areas. Fruit, Winter Wheat. 'Without-Project' Scenario.'000 ha. Reduced Cost Option. Pumps decline

Fruit Year 1 2 3 4 5 6 7 8 9 Fruit Kuyu Mazar 11% - Out of production '000 ha 0.0 0.0 0.0 0.6 1.2 1.8 2.3 2.9 3.3 - Reduced yield '000 ha 0.5 0.5 0.5 0.5 0.4 0.4 0.4 0.4 0.3 - Unaffected '000 ha 9.5 9.5 9.5 8.9 8.3 7.7 7.2 6.7 6.3 - Total area '000 ha 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 Fruit Kizil Tepa 10% - Out of production '000 ha 0.0 0.0 0.0 0.9 1.7 2.5 3.3 4.0 4.7 - Reduced yield '000 ha 0.7 0.7 0.7 0.6 0.6 0.6 0.5 0.5 0.5 - Unaffected '000 ha 13.1 13.1 13.1 12.2 11.4 10.7 10.0 9.3 8.6 - Total area '000 ha 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 Fruit Karaul Bazar 1% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - Reduced yield '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - Unaffected '000 ha 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 - Total area '000 ha 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 Winter wheat Wheat Kuyu Mazar 23% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.9 4.1 - Reduced yield '000 ha 1.0 1.0 1.0 1.0 1.0 1.0 1.0 0.9 0.8 - Unaffected '000 ha 19.4 19.4 19.4 19.4 19.4 19.4 19.4 16.6 15.4 - Total area '000 ha 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 Wheat Kizil Tepa - Out of production '000 ha 27% 0.0 0.0 0.0 0.0 0.0 0.0 0.0 5.4 7.5 - Reduced yield '000 ha 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.6 1.4 - Unaffected '000 ha 34.6 34.6 34.6 34.6 34.6 34.6 34.6 29.5 27.4 - Total area '000 ha 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 Wheat Karaul Bazar 40% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - Reduced yield '000 ha 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 - Unaffected '000 ha 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 - Total area '000 ha 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 Total croppable areas Kuyu Mazar '000 ha 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 Kizil Tepa '000 ha 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 Karaul Bazar '000 ha 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 Total '000 ha 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 Source: Table A.19 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

3.8 4.2 4.6 5.0 5.3 5.7 6.0 6.3 6.6 6.9 7.2 7.5 7.7 7.9 8.2 8.4 0.3 0.3 0.3 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.1 0.1 0.1 0.1 0.1 0.1 5.8 5.5 5.1 4.7 4.4 4.0 3.7 3.4 3.1 2.9 2.6 2.4 2.1 1.9 1.7 1.5 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9

5.3 5.8 6.4 7.0 7.5 8.0 8.4 8.9 9.3 9.7 10.1 10.4 10.8 11.1 11.4 11.7 0.4 0.4 0.4 0.3 0.3 0.3 0.3 0.2 0.2 0.2 0.2 0.2 0.1 0.1 0.1 0.1 8.0 7.5 7.0 6.5 6.0 5.5 5.1 4.6 4.2 3.9 3.5 3.2 2.8 2.5 2.2 1.9 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2

5.3 6.4 7.4 8.4 9.3 10.2 11.0 11.8 12.6 13.3 14.0 14.6 15.2 15.8 16.4 16.9 0.8 0.7 0.7 0.6 0.6 0.5 0.5 0.4 0.4 0.4 0.3 0.3 0.3 0.2 0.2 0.2 14.4 13.3 12.4 11.4 10.5 9.7 8.9 8.2 7.4 6.8 6.1 5.5 4.9 4.3 3.8 3.3 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4

9.6 11.6 13.4 15.2 16.8 18.4 20.0 21.4 22.8 24.0 25.3 26.4 27.6 28.6 29.6 30.6 1.3 1.2 1.2 1.1 1.0 0.9 0.8 0.8 0.7 0.6 0.6 0.5 0.4 0.4 0.3 0.3 25.5 23.6 21.9 20.2 18.6 17.1 15.7 14.3 13.0 11.8 10.6 9.5 8.4 7.4 6.5 5.6 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3

96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 Table A.22 Net Crop returns. Kuyu Mazar. 'Without-Project Scenario. UZS million. Economic prices. Reduced Cost Option. Pumps decline

per ha return Year 1 2 3 4 5 6 7 8 9 10 Net returns without-project UZS'000/ha Kuyu Mazar Total Total Total Total Total Total Total Total Total Total - Cotton (marginal) 2668 4,821 4,821 4,821 4,516 4,226 3,950 3,688 3,439 3,203 2,978 - Cotton (unaffected) 3570 122,571 122,571 122,571 114,805 107,427 100,418 93,760 87,434 81,425 75,716 - Cotton (total) 127,393 127,393 127,393 119,321 111,653 104,368 97,448 90,873 84,628 78,694

- Forage (marginal) 930 675 675 675 632 591 553 516 481 448 417 - Forage (unaffected) 1977 27,242 27,242 27,242 25,516 23,877 22,319 20,839 19,433 18,097 16,828 - Forage (total) 27,917 27,917 27,917 26,148 24,468 22,871 21,355 19,914 18,545 17,245

- Vegetables (marginal) 1236 961 961 961 900 842 787 735 686 638 594 - Vegetables (unaffected) 2608 38,520 38,520 38,520 36,080 33,761 31,558 29,466 27,478 25,589 23,795 - Vegetables (total) 39,481 39,481 39,481 36,980 34,603 32,346 30,201 28,163 26,228 24,389

- Fruit (marginal) 1120 557 557 557 522 488 456 426 397 370 344 - Fruit (unaffected) 2532 23,926 23,926 23,926 22,410 20,970 19,601 18,302 17,067 15,894 14,780 - Fruit (total) 24,483 24,483 24,483 22,931 21,458 20,058 18,728 17,464 16,264 15,124

- Wheat (marginal) 1164 1,187 1,187 1,187 1,187 1,187 1,187 1,187 1,016 946 880 - Wheat (unaffected) 1892 36,655 36,655 36,655 36,655 36,655 36,655 36,655 31,377 29,220 27,172 - Wheat (total) 37,842 37,842 37,842 37,842 37,842 37,842 37,842 32,393 30,167 28,052

Kuyu Mazar Total Return 257,116 257,116 257,116 243,223 230,024 217,486 205,574 188,808 175,832 163,504 Sources: Table A.21 Table 14 Table A.20 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Total Total Total Total Total Total Total Total Total Total Total Total Total Total Total 2,803 2,605 2,416 2,236 2,066 1,904 1,750 1,604 1,465 1,333 1,207 1,088 975 868 766 71,270 66,214 61,411 56,848 52,513 48,395 44,483 40,767 37,236 33,882 30,695 27,668 24,792 22,060 19,465 74,074 68,819 63,827 59,084 54,579 50,299 46,233 42,370 38,701 35,215 31,903 28,757 25,768 22,928 20,231

392 364 338 313 289 266 245 224 205 186 169 152 136 121 107 15,840 14,717 13,649 12,635 11,672 10,756 9,887 9,061 8,276 7,531 6,822 6,149 5,510 4,903 4,326 16,233 15,081 13,987 12,948 11,961 11,023 10,132 9,285 8,481 7,717 6,991 6,302 5,647 5,025 4,433

559 519 481 446 412 379 349 320 292 266 241 217 194 173 153 22,398 20,809 19,300 17,866 16,503 15,209 13,980 12,812 11,702 10,648 9,647 8,695 7,792 6,933 6,117 22,957 21,328 19,781 18,311 16,915 15,589 14,328 13,131 11,994 10,914 9,887 8,912 7,986 7,106 6,270

324 301 279 258 239 220 202 185 169 154 140 126 113 100 88 13,912 12,925 11,987 11,097 10,251 9,447 8,683 7,958 7,268 6,614 5,992 5,401 4,839 4,306 3,800 14,236 13,226 12,266 11,355 10,489 9,667 8,885 8,143 7,438 6,768 6,131 5,527 4,952 4,406 3,888

817 757 700 646 595 546 500 456 414 374 336 301 266 234 203 25,226 23,377 21,620 19,951 18,366 16,860 15,429 14,070 12,779 11,552 10,387 9,280 8,228 7,229 6,280 26,042 24,134 22,320 20,597 18,961 17,406 15,929 14,526 13,193 11,927 10,724 9,581 8,495 7,463 6,484

153,541 142,588 132,182 122,296 112,905 103,983 95,508 87,456 79,806 72,540 65,636 59,078 52,847 46,929 41,306 Table A.23 Net Crop returns. Kizil Tepa. 'Without-Project Scenario. UZS million. Economic prices. Reduced Cost Option. Pumps decline

per ha return Year 1 2 3 4 5 6 7 8 9 10 UZS'000/ha Kizil Tepa Total Total Total Total Total Total Total Total Total Total - Cotton (marginal) 2,668 6,697 6,697 6,697 6,269 5,861 5,474 5,107 4,758 4,426 4,111 - Cotton (unaffected) 3,570 170,260 170,260 170,260 159,361 149,006 139,169 129,825 120,947 112,513 104,501 - Cotton (total) - 176,957 176,957 176,957 165,629 154,867 144,644 134,931 125,704 116,939 108,612

- Forage (marginal) 930 962 962 962 900 842 786 734 683 636 590 - Forage (unaffected) 1,977 38,847 38,847 38,847 36,360 33,998 31,754 29,621 27,596 25,671 23,843 - Forage (total) - 39,809 39,809 39,809 37,261 34,840 32,540 30,355 28,279 26,307 24,434

- Vegetables (marginal) 1,236 1,568 1,568 1,568 1,468 1,372 1,282 1,196 1,114 1,036 962 - Vegetables (unaffected) 2,608 62,853 62,853 62,853 58,829 55,007 51,375 47,926 44,648 41,535 38,577 - Vegetables (total) - 64,421 64,421 64,421 60,297 56,379 52,657 49,121 45,762 42,571 39,540

- Fruit (marginal) 1,120 771 771 771 722 675 630 588 548 509 473 - Fruit (unaffected) 2,532 33,110 33,110 33,110 30,990 28,977 27,064 25,247 23,520 21,880 20,322 - Fruit (total) - 33,881 33,881 33,881 31,712 29,651 27,694 25,834 24,068 22,390 20,795

- Wheat (marginal) 1,164 2,120 2,120 2,120 2,120 2,120 2,120 2,120 1,807 1,681 1,561 - Wheat (unaffected) 1,892 65,464 65,464 65,464 65,464 65,464 65,464 65,464 55,804 51,913 48,216 - Wheat (total) 67,584 67,584 67,584 67,584 67,584 67,584 67,584 57,611 53,594 49,777

Kizil Tepa Total Return 382,652 382,652 382,652 362,483 343,322 325,119 307,826 281,425 261,801 243,158 Sources: Table A.21 Table 14 Table A.20 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Total Total Total Total Total Total Total Total Total Total Total Total Total Total Total 3,859 3,579 3,313 3,061 2,821 2,593 2,377 2,171 1,976 1,790 1,614 1,446 1,287 1,136 992 98,098 90,986 84,230 77,811 71,714 65,921 60,418 55,190 50,224 45,506 41,023 36,765 32,720 28,877 25,226 101,956 94,565 87,543 80,872 74,535 68,514 62,795 57,361 52,199 47,296 42,637 38,211 34,007 30,013 26,219

554 514 476 440 405 372 341 312 284 257 232 208 185 163 143 22,382 20,760 19,218 17,754 16,363 15,041 13,785 12,592 11,459 10,383 9,360 8,389 7,466 6,589 5,756 22,937 21,274 19,694 18,193 16,768 15,413 14,127 12,904 11,743 10,640 9,592 8,596 7,650 6,752 5,898

903 838 776 717 660 607 556 508 463 419 378 339 301 266 232 36,213 33,588 31,094 28,725 26,474 24,335 22,304 20,374 18,540 16,799 15,144 13,572 636 561 490 37,117 34,426 31,870 29,441 27,134 24,942 22,860 20,882 19,003 17,218 15,522 13,911 937 827 722

444 412 381 352 325 298 274 250 227 206 186 166 148 131 114 19,077 17,694 16,380 15,132 13,946 12,819 11,749 10,733 9,767 8,849 7,978 7,150 6,363 5,616 4,906 19,521 18,106 16,761 15,484 14,271 13,118 12,023 10,983 9,994 9,055 8,163 7,316 6,511 5,746 5,020

1,448 1,340 1,237 1,140 1,047 959 875 796 720 649 581 516 454 396 341 44,704 41,368 38,198 35,187 32,327 29,609 27,028 24,575 22,246 20,032 17,930 15,932 14,034 12,232 10,519 46,152 42,707 39,435 36,327 33,374 30,568 27,903 25,371 22,966 20,681 18,510 16,448 14,489 12,628 10,860

227,683 211,078 195,303 180,317 166,081 152,556 139,707 127,501 115,906 104,890 94,424 84,482 63,594 55,966 48,719 Table A.24 Net Crop returns. Karaul Bazar. 'Without-Project Scenario. UZS million. Economic prices. Reduced Cost Option. Pumps decline

per ha return Year 1 2 3 4 5 6 7 8 9 10 UZS'000/ha Karaul Bazar Total Total Total Total Total Total Total Total Total Total - Cotton (marginal) 2,668 763 763 763 763 763 763 763 763 763 763 - Cotton (unaffected) 3,570 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 - Cotton (total) - 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147

- Forage (marginal) 930 208 208 208 208 208 208 208 208 208 208 - Forage (unaffected) 1,977 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 - Forage (total) - 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614

- Vegetables (marginal) 1,236 68 68 68 68 68 68 68 68 68 68 - Vegetables (unaffected) 2,608 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 - Vegetables (total) - 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806

- Fruit (marginal) 1,120 10 10 10 10 10 10 10 10 10 10 - Fruit (unaffected) 2,532 447 447 447 447 447 447 447 447 447 447 - Fruit (total) - 458 458 458 458 458 458 458 458 458 458

- Wheat (marginal) 1,164 369 369 369 369 369 369 369 369 369 369 - Wheat (unaffected) 1,892 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 - Wheat (total) 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754

Karaul Bazar Total Return 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 Sources: Table A.21 Table 14 Table A.20 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Total Total Total Total Total Total Total Total Total Total Total Total Total Total Total 763 763 763 763 763 763 763 763 763 763 763 763 763 763 763 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147

208 208 208 208 208 208 208 208 208 208 208 208 208 208 208 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614

68 68 68 68 68 68 68 68 68 68 68 68 68 68 68 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806

10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 447 447 447 447 447 447 447 447 447 447 447 447 447 447 447 458 458 458 458 458 458 458 458 458 458 458 458 458 458 458

369 369 369 369 369 369 369 369 369 369 369 369 369 369 369 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754

43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 Table A.25 Net Crop Returns. 'With-Project' Incremental Benefits. UZS million. Reduced Cost Option. Pumps decline

Year 1 2 3 4 5 6 7 8 9 10 Without-Project' Return Without-Project' Return - Kuyu Mazar 257,116 257,116 257,116 243,223 230,024 217,486 205,574 188,808 175,832 163,504 - Kizil Tepa 382,652 382,652 382,652 362,483 343,322 325,119 307,826 281,425 261,801 243,158 - Karaul Bazar 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 Total 'Without-Project' Return 683,547 683,547 683,547 649,484 617,125 586,383 557,178 514,012 481,411 450,440 'With-Project' Return - Kuyu Mazar 257,116 257,116 257,116 243,223 230,024 217,486 257,116 257,116 257,116 257,116 - Kizil Tepa 382,652 382,652 382,652 362,483 343,322 325,119 313,957 313,957 313,957 313,957 - Karaul Bazar 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 Total 'With-Project' Return 683,547 683,547 683,547 649,484 617,125 586,383 614,852 614,852 614,852 614,852 Net 'With -Project' Incremental Return ------57,673 100,840 133,441 164,411 Sources : Table A.22 Table A.23 Table A.24 11 12 13 14 15 0 17 18 19 20 21 22 23 24 25

153,541 142,588 132,182 122,296 112,905 103,983 95,508 87,456 79,806 72,540 65,636 59,078 52,847 46,929 41,306 227,683 211,078 195,303 180,317 166,081 152,556 139,707 127,501 115,906 104,890 94,424 84,482 63,594 55,966 48,719 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 425,003 397,444 371,264 346,392 322,764 300,318 278,994 258,736 239,491 221,208 203,839 187,339 160,221 146,673 133,803

257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 189,849 217,408 243,588 268,460 292,087 314,534 335,858 356,116 375,361 393,644 411,013 427,513 454,631 468,179 481,049 Table A.26 Without and With-Project Non-energy Recurrent Costs - @ constant 2012 Financial prices. US$ M. Full Cost Option. Pumps decline

Current Year 1 2 3 4 5 6 7 8 9 10 Without -project Pump Station O&M - Khamza 1 0.19 0.19 0.19 0.19 0.20 0.21 0.22 0.23 0.24 0.25 0.27 - Khamza 1 Auxiliary 0.06 0.06 0.06 0.06 0.06 0.07 0.07 0.07 0.08 0.08 0.09 - Khamza 2 0.22 0.22 0.22 0.22 0.22 0.22 0.23 0.24 0.26 0.27 0.28 - Kuyu Mazar 0.17 0.17 0.17 0.17 0.18 0.19 0.20 0.21 0.22 0.23 0.25 - Kizil Tepa 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.33 0.35 0.36 0.38 - Kizil Tepa Aux 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.27 0.28 0.30 0.31 Sub-total PS 1.22 1.22 1.22 1.22 1.24 1.26 1.29 1.36 1.43 1.50 1.57 Remaining ABIS O&M costs 5.13 5.13 5.13 5.13 4.82 4.53 4.26 4.00 3.75 3.51 3.29 Total 'without-project' O&M 6.35 6.35 6.35 6.35 6.06 5.79 5.55 5.35 5.17 5.01 4.86 Future 'With-project' Option 1 wp - Khamza 1 1.42 0.19 0.19 0.19 0.20 0.21 0.22 1.42 1.42 1.42 1.42 - Khamza 1 Auxiliary 0.00 0.06 0.06 0.06 0.06 0.07 0.07 0.00 0.00 0.00 0.00 - Khamza 2 1.34 0.22 0.22 0.22 0.22 0.22 0.23 1.34 1.34 1.34 1.34 - Kuyu Mazar 0.49 0.17 0.17 0.17 0.18 0.19 0.20 0.49 0.49 0.49 0.49 - Kizil Tepa 0.98 0.31 0.31 0.31 0.31 0.31 0.31 0.98 0.98 0.98 0.98 - Kizil Tepa Aux 0.27 0.26 0.26 0.26 0.26 0.26 0.26 0.27 0.27 0.27 0.27 Sub-total PS 4.50 1.22 1.22 1.22 1.24 1.26 1.29 4.50 4.50 4.50 4.50 Periodic Maintenance - Khamza 1 1.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - Khamza 1 Auxiliary 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - Khamza 2 1.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - Kuyu Mazar 0.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - Kizil Tepa 1.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - Kizil Tepa Aux 0.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Sub-total Periodic maintenance 6.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Remaining ABIS O&M costs 5.13 5.13 5.13 5.13 5.13 5.13 5.13 4.97 4.61 4.61 4.61 Discharge pipe special maintenance 0.00 12.24 12.24 12.24 12.24 12.24 12.24 12.24 0.00 0.00 0.00 Total 'with-project' O&M 18.59 18.59 18.59 18.61 18.63 18.67 21.71 9.11 9.11 9.11 Incremental 'with-project' O&M costs 12.24 12.24 12.24 12.55 12.84 13.11 16.36 3.93 4.10 4.25 Without and With-Project Non-energy Recurrent Costs - @ constant 2012 Financial prices. US$ M. Full Cost Option. Pumps decline

11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

0.28 0.29 0.31 0.32 0.34 0.36 0.37 0.39 0.41 0.43 0.46 0.48 0.50 0.53 0.55 0.09 0.09 0.10 0.10 0.11 0.11 0.12 0.13 0.13 0.14 0.15 0.15 0.16 0.17 0.18 0.30 0.31 0.33 0.34 0.36 0.38 0.40 0.42 0.44 0.46 0.48 0.51 0.53 0.56 0.59 0.26 0.27 0.28 0.30 0.31 0.33 0.34 0.36 0.38 0.40 0.42 0.44 0.46 0.49 0.51 0.40 0.42 0.44 0.46 0.49 0.51 0.54 0.56 0.59 0.62 0.65 0.68 0.72 0.75 0.79 0.33 0.35 0.36 0.38 0.40 0.42 0.44 0.46 0.49 0.51 0.54 0.56 0.59 0.62 0.65 1.65 1.73 1.82 1.91 2.01 2.11 2.21 2.32 2.44 2.56 2.69 2.82 2.97 3.11 3.27 3.11 2.91 2.72 2.54 2.37 2.21 2.05 1.91 1.77 1.64 1.51 1.39 1.28 1.17 1.07 4.76 4.64 4.54 4.45 4.38 4.32 4.27 4.23 4.21 4.20 4.20 4.22 4.24 4.28 4.34

1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50

0.00 0.00 0.00 1.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.99 0.00 0.00 0.00 0.00 0.00 0.00 0.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.70 0.00 0.00 0.00 0.00 0.00 0.00 1.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.43 0.00 0.00 0.00 0.00 0.00 0.00 0.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.38 0.00 0.00 0.00 0.00 0.00 0.00 6.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.40 0.00 0.00 0.00 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.11 9.11 9.11 15.50 9.11 9.11 9.11 9.11 9.11 9.11 9.11 15.50 9.11 9.11 9.11 4.35 4.46 4.56 11.05 4.73 4.79 4.84 4.88 4.90 4.91 4.91 11.29 4.86 4.82 4.77 Table A.27 Power Consumption. 'Without-Project' Scenario. MWh/year. Reduced Cost Option. Pumps decline

Present usage % future Year 1 2 3 4 5 6 7 8 9 Stage 1. Mwh/yr consumption Khamza 1 165,791 100% 165,791 165,791 165,791 157,501 149,626 142,145 135,037 128,286 121,871 Khamza Aux 19,317 100% 19,317 19,317 19,317 18,351 17,433 16,562 15,734 14,947 14,200 Khamza 2 639,497 100% 639,497 639,497 639,497 639,497 639,497 607,523 577,146 548,289 520,875 Total Stage 1 824,605 824,605 824,605 824,605 815,349 806,557 766,229 727,917 691,522 656,945 Stage 2 Kuyu Mazar Main Station 109,847 100% 109,847 109,847 109,847 103,017 96,529 90,365 84,509 78,946 73,661 Kuyu Mazar Auxiliary (new) 38,786 82% 31,952 31,952 31,952 29,965 28,078 26,285 24,582 22,964 21,426 Sub-total Kuyu Mazar 148,633 141,799 141,799 141,799 132,982 124,607 116,650 109,091 101,910 95,088 Kizil Tepa Main Station 398,025 100% 398,025 398,025 398,025 372,964 349,157 326,540 305,053 284,641 265,250 Kizil Tepa Auxiliary 33,207 100% 33,207 33,207 33,207 31,116 29,130 27,243 25,450 23,747 22,129 Navoi (new) 46,700 70% 32,487 32,487 32,487 30,442 28,498 26,652 24,899 23,233 21,650 Sub-total Kizil Tepa 477,931 463,718 463,718 463,718 434,521 406,785 380,434 355,402 331,621 309,029 Drujba 12,150 100% 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 Karaul Bazaar 54,393 100% 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 Sub-total Karaul Bazaar 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 Total Stage 2 693,108 672,060 672,060 672,060 634,047 597,935 563,628 531,036 500,074 470,660

Total Stage 1 and Stage 2 1,517,712 1,496,665 1,496,665 1,496,665 1,449,396 1,404,491 1,329,857 1,258,954 1,191,596 1,127,606 Sources: Table A.18 Table 6 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

115,778 109,989 104,489 99,265 94,302 89,587 85,107 80,852 76,809 72,969 69,320 65,854 62,562 59,434 56,462 53,639 13,490 12,815 12,174 11,566 10,987 10,438 9,916 9,420 8,949 8,502 8,077 7,673 7,289 6,925 6,579 6,250 494,831 470,089 446,585 424,256 403,043 382,891 363,746 345,559 328,281 311,867 296,274 281,460 267,387 254,018 241,317 229,251 624,098 592,893 563,249 535,086 508,332 482,915 458,769 435,831 414,039 393,337 373,671 354,987 337,238 320,376 304,357 289,139

68,641 63,871 59,340 55,036 50,947 47,062 43,371 39,865 36,535 33,370 30,364 27,509 24,796 22,219 19,770 17,444 19,966 18,579 17,261 16,009 14,819 13,689 12,616 11,596 10,627 9,707 8,832 8,002 7,213 6,463 5,751 5,074 88,607 82,450 76,601 71,045 65,766 60,751 55,987 51,461 47,162 43,077 39,197 35,510 32,008 28,682 25,521 22,518 246,828 229,327 212,702 196,907 181,903 167,648 154,107 141,242 129,021 117,410 106,380 95,902 85,948 76,491 67,507 58,973 20,592 19,132 17,745 16,428 15,176 13,987 12,857 11,784 10,764 9,795 8,875 8,001 7,170 6,382 5,632 4,920 20,146 18,718 17,361 16,072 14,847 13,684 12,578 11,528 10,531 9,583 8,683 7,828 7,015 6,243 5,510 4,813 287,567 267,178 247,808 229,407 211,926 195,318 179,542 164,554 150,315 136,789 123,938 111,731 100,133 89,116 78,649 68,706 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 442,717 416,171 390,953 366,995 344,235 322,613 302,072 282,558 264,020 246,409 229,679 213,785 198,685 184,341 170,714 157,768

1,066,815 1,009,064 954,201 902,081 852,567 805,528 760,842 718,389 678,060 639,747 603,349 568,772 535,923 504,717 475,071 446,907 Table A.28 Power Consumption. 'With-Project' Scenario. MWh/year. Reduced Cost Option. Pumps decline

Present usage % future Future usage Year 1 2 3 4 5 6 7 8 9 Stage 1. Mwh/yr consumption Mwh/yr Khamza 1 165,791 95.22% 157,865 165,791 165,791 165,791 157,501 149,626 142,145 157,865 157,865 157,865 Khamza Aux 19,317 95.22% 18,393 19,317 19,317 19,317 18,351 17,433 16,562 - - - Khamza 2 639,497 95.22% 608,927 639,497 639,497 639,497 639,497 639,497 607,523 608,927 608,927 608,927 Total Stage 1 824,605 785,185 824,605 824,605 824,605 815,349 806,557 766,229 766,792 766,792 766,792 Stage 2 - Kuyu Mazar Main Station 109,847 95.22% 104,596 109,847 109,847 109,847 103,017 96,529 90,365 104,596 104,596 104,596 Kuyu Mazar Auxiliary (new) 38,786 82.38% 31,952 31,952 31,952 31,952 29,965 28,078 26,285 31,952 31,952 31,952 Sub-total Kuyu Mazar 148,633 136,548 141,799 141,799 141,799 132,982 124,607 116,650 136,548 136,548 136,548 Kizil Tepa Main Station 398,025 82.38% 283,627 398,025 398,025 398,025 372,964 349,157 326,540 283,627 283,627 283,627 Kizil Tepa Auxiliary 33,207 82.38% 13,636 33,207 33,207 33,207 31,116 29,130 27,243 13,636 13,636 13,636 Navoi (new) 46,700 69.57% 32,487 32,487 32,487 32,487 30,442 28,498 26,652 32,487 32,487 32,487 Sub-total Kizil Tepa 477,931 329,750 463,718 463,718 463,718 434,521 406,785 380,434 329,750 329,750 329,750 Drujba 12,150 100.00% 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 Karaul Bazaar 54,393 100.00% 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 Sub-total Karaul Bazaar 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 Total Stage 2 693,108 532,841 672,060 672,060 672,060 634,047 597,935 563,628 532,841 532,841 532,841

Total Stage 1 and Stage 2 1,517,712 1,318,026 1,496,665 1,496,665 1,496,665 1,449,396 1,404,491 1,329,857 1,299,632 1,299,632 1,299,632 Increasing inefficiency of new pump factor % 100% 100% 100% 100% 100% 100% 100% 100% 100% Net Mwh with declining pump efficiency 1,496,665 1,496,665 1,496,665 1,449,396 1,404,491 1,329,857 1,299,632 1,299,632 1,299,632 Improved system efficiency factor % 1.5% 100% 100% 100% 100% 100% 100% 99% 97% 96% Net Mwh with improved system efficiency 1,496,665 1,496,665 1,496,665 1,449,396 1,404,491 1,329,857 1,280,138 1,260,643 1,241,149 Sources : Table 6 Table A.18 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 ------608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792

104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841

1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 100% 100% 100% 100% 100% 100% 100% 101% 101% 102% 102% 103% 103% 104% 105% 105% 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,306,813 1,314,073 1,321,414 1,328,838 1,336,345 1,343,938 1,351,618 1,359,386 1,367,243 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 1,241,149 1,241,149 1,241,149 1,241,149 1,241,149 1,241,149 1,241,149 1,248,006 1,254,939 1,261,950 1,269,040 1,276,210 1,283,461 1,290,795 1,298,213 1,305,717 Table A.29 Part A Pump Capacity , Pumped Volumes available to Stage 2 pump stations. Assumed 'Without-Project' Reduced Cost Option. Pumps fail Stage 1 - Khamza PS unit unit value base Year 1 2 3 4 5 6 7 8 9 10 11 12 Khamza pumps capacity Khamza 1 m3/s/PS 65 65 65 65 65 65 65 65 58 44 22 0 0 0 Khamza Aux m3/s/PS 20 20 20 20 20 20 20 20 18 14 8 0 0 0 Khamza 2 m3/s/PS 135 135 135 135 135 135 135 135 135 135 122 95 54 0 Total Khamza. Stage 1 capacity m3/s 220 220 220 220 220 220 220 220 211 193 152 95 54 0 Proportion of 2012 capacity 100% 100% 100% 100% 100% 100% 96% 88% 69% 43% 25% 0% Pump tours % of maximum 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% Volume pumped peak month from Stage 1 m3/s peak month 202 202 202 202 202 202 202 202 194 177 139 87 50 0 - Less other direct offtakes m3/s peak month 5 -5 -5 -5 -5 -5 -5 -5 -5 -5 -5 -5 -5 0 Stage 2 - Karaul Bazar PS irrigated area - ha 15,907 Karaul Bazar pump capacity m3/s peak month 32 32 32 32 32 32 32 32 32 32 32 32 32 32 - Less Karaul Bazar offtake m3/s peak month 19 -19 -19 -19 -19 -19 -19 -19 -19 -19 -19 -19 -19 0 - Less main ABMK losses m3/s peak month 7% -14 -14 -14 -14 -14 -14 -14 -14 -14 -14 -14 -14 0 Available at Tudakul Diversion m3/s peak month 165 165 165 165 165 165 165 156 139 102 49 12 0 Proportion of 2012 availabilty % 100% 100% 100% 100% 100% 100% 100% 95% 85% 62% 30% 7% 0% Flow division at Tudakul Diversion (TD) (a) Allocation to Kuyu Mazar PS (KM) % 39% 39% 39% 39% 39% 39% 39% 36% 34% 34% 34% 34% 0% To Kuyu Mazar PS m3/s peak month max 60 64 64 64 64 64 64 64 56 47 35 17 4 0 - Losses between TD and KM (17 km) m3/s peak month 2% -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 0 + From Kuyu Mazar & Tudakul Lakes m3/s peak month max 44 44 44 44 44 44 44 44 44 37 27 13 3 0 Available at Kuyu Mazar PS m3/s peak month 111 107 107 107 107 107 107 107 99 83 61 29 6 0 Proportion of 2012 availabilty % 100% 100% 100% 100% 100% 100% 100% 93% 78% 57% 27% 6% 0% (b) Allocation to Kizil Tepa PS (KT) % 61% 61% 61% 61% 61% 61% 61% 64% 66% 66% 66% 66% 0% To Kizil Tepa PS m3/s peak month 100 100 100 100 100 100 100 100 92 67 33 8 0 - Losses between TD and KT (38 km) m3/s peak month 3% -3 -3 -3 -3 -3 -3 -3 -3 -3 -3 -3 -3 0 + From Tudakul Lake m3/s peak month max 28 24 24 24 24 24 24 24 24 20 15 7 2 0 Available at Kizil Tepa PS m3/s peak month 123 121 121 121 121 121 121 121 121 109 79 37 7 0 Proportion of 2012 availabilty % 100% 100% 100% 100% 100% 100% 100% 100% 90% 65% 30% 5% 0%

Table A.29 Part B Pump Capacity , Pumped Volumes available for irrigation. Assumed 'Without-Project'. Reduced Cost Option. Pumps fail unit unit value base Year 1 2 3 4 5 6 7 8 9 10 11 12 Stage 2 - Kuyu Mazar PS irrigated area - ha 89,117 Kuyu Mazar (KM) pump capacity - New PS m3/s/PS 40 40 40 40 40 40 40 40 40 40 40 40 40 40 - Main PS - to Shakrud Canal m3/s/PS 60 60 60 60 60 60 60 60 50 40 20 0 0 0 - Main PS - to Kuyu Mazar Lake m3/s/PS 40 40 40 40 40 40 40 40 33 26 13 0 0 0 Total Kuyu Mazar capacity (to Shakhrud) m3/s/PS 100 100 100 100 100 100 100 100 90 80 60 40 40 40 Proportion of 2012 capacity m3/s/PS % 100% 100% 100% 100% 100% 100% 100% 90% 80% 60% 40% 40% 40% Volume pumped at Kuyu Mazar m3/s peak month 107 107 107 107 107 107 107 99 83 61 29 6 0 Volume pumped as % of 2012 pumping m3/s peak month 100% 100% 100% 100% 100% 100% 100% 93% 78% 57% 27% 6% 0% - DMI and fisheries m3/s peak month 2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 0 Net available for agriculture m3/s peak month 105 105 105 105 105 105 105 97 81 59 27 4 0 Proportion of 2102 agricultural water % 100% 100% 100% 100% 100% 100% 100% 92% 78% 56% 25% 4% 0% Stage2 - Kizil Tepa PS irrigated area - ha 135,915 Kizil Tepa (KT) pump capacity - Kizil Tepa m3/s/PS 109 109 109 109 109 109 109 109 109 109 109 109 109 98 - Kizil Tepa Aux m3/s/PS 20 20 20 20 20 20 20 20 20 20 20 20 20 17 Total Kizil Tepa capacity m3/s/PS 129 129 129 129 129 129 129 129 129 129 129 129 129 116 As % of 2012 capacity 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 90% Volume pumped at Kizil Tepa m3/s peak month 121 121 121 121 121 121 121 121 109 79 37 7 0 Volume pumped as % of 2012 pumping m3/s peak month 100% 100% 100% 100% 100% 100% 100% 100% 90% 65% 30% 5% 0% - DMI and fisheries m3/s peak month 2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 -2 0 Net available for agriculture m3/s peak month 119 119 119 119 119 119 119 119 107 77 35 5 0 Proportion of 2102 agricultural water % 100% 100% 100% 100% 100% 100% 100% 100% 90% 64% 29% 4% 0% Total Stage 1 pumping capacity ms/s peak month 220 220 220 220 220 220 220 220 211 193 152 95 54 0 Total Stage 2 pumping capacity ms/s peak month 229 229 229 229 229 229 229 229 219 208 189 169 169 156 Decline assumptions Khamza 1 decline % 0% 0% 0% 0% 0% 0% 11% 22% 33% 34% 0% 0% Khamza Aux decline % 0% 0% 0% 0% 0% 0% 10% 20% 30% 40% 0% 0% Khamza 2 decline % 0% 0% 0% 0% 0% 0% 0% 0% 10% 20% 30% 40% Kuyu Mazar decline % 0% 0% 0% 0% 0% 0% 17% 17% 33% 33% 0% 0% Kizil Tepa decline % 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 10% Kizil Tepa Aux decline % 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 12% Sources : Table 2 Table 5 Table 6 13 14 15 16 17 18 19 20 21 22 23 24 25

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

32 32 32 32 32 32 32 32 32 32 32 32 32 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

13 14 15 16 17 18 19 20 21 22 23 24 25

40 40 40 40 40 40 40 40 40 40 40 40 40 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 40 40 40 40 40 40 40 40 40 40 40 40 40 40% 40% 40% 40% 40% 40% 40% 40% 40% 40% 40% 40% 40% 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

76 44 0 0 0 0 0 0 0 0 0 0 0 13 7 0 0 0 0 0 0 0 0 0 0 0 89 50 0 0 0 0 0 0 0 0 0 0 0 69% 39% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0 0 0 0 0 0 0 0 0 0 0 0 0 129 90 40 40 40 40 40 40 40 40 40 40 40

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 20% 30% 40% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 24% 31% 33% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% Table A.30 Irrigated Areas and Cropping Patterns. 'Without-Project' Scenario. '000 ha. Reduced Cost Option. Pumps fail

Year 1 2 3 4 5 6 7 8 9 10 11 12 Total Land Area irrigated - Kuyu Mazar '000 ha 89.1 89.1 89.1 89.1 89.1 89.1 89.1 82.3 69.1 49.7 22.6 5.0 0.0 - Kizil Tepa '000 ha 135.9 135.9 135.9 135.9 135.9 135.9 135.9 135.4 122.1 87.6 39.4 7.4 0.0 - Karaul Bazar '000 ha 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 15.9 0.0 Total irrigated area '000 ha 240.9 240.9 240.9 240.9 240.9 240.9 240.9 233.7 207.1 153.2 78.0 28.4 0.0 Total Cropped Area - Cotton '000 ha 38% 92.0 92.0 92.0 92.0 92.0 92.0 89.1 78.8 58.2 29.5 10.5 0.0 - Fodder '000 ha 16% 39.7 39.7 39.7 39.7 39.7 39.7 38.5 34.3 25.9 14.2 6.4 0.0 - Vegetables '000 ha 17% 42.0 42.0 42.0 42.0 42.0 42.0 40.7 36.0 26.1 12.4 3.4 0.0 - Fruit '000 ha 10% 23.9 23.9 23.9 23.9 23.9 23.9 23.1 20.3 14.6 6.7 1.5 0.0 - Winter wheat '000 ha 26% 63.2 63.2 63.2 63.2 63.2 63.2 63.2 63.2 48.2 25.2 9.0 0.0 Total crops '000 ha 108% 260.8 260.8 260.8 260.8 260.8 260.8 254.6 232.5 173.0 88.0 30.8 0.0 Cropping pattern Kuyu Mazar - Cotton '000 ha 41% 36.1 36.1 36.1 36.1 36.1 36.1 33.4 28.0 20.1 9.2 2.0 0.0 - Fodder '000 ha 16% 14.5 14.5 14.5 14.5 14.5 14.5 13.4 11.2 8.1 3.7 0.8 0.0 - Vegetables '000 ha 17% 15.5 15.5 15.5 15.5 15.5 15.5 14.4 12.1 8.7 3.9 0.9 0.0 - Fruit '000 ha 11% 9.9 9.9 9.9 9.9 9.9 9.9 9.2 7.7 5.5 2.5 0.6 0.0 - Winter wheat '000 ha 23% 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 13.6 6.2 0.9 0.0 Total crops Kuyu Mazar '000 ha 108% 96.5 96.5 96.5 96.5 96.5 96.5 90.8 79.4 56.1 25.5 5.2 0.0 Cropping pattern Kizil Tepa - Cotton '000 ha 37% 50.2 50.2 50.2 50.2 50.2 50.2 50.0 45.1 32.4 14.6 2.7 0.0 - Fodder '000 ha 15% 20.7 20.7 20.7 20.7 20.7 20.7 20.6 18.6 13.3 6.0 1.1 0.0 - Vegetables '000 ha 19% 25.4 25.4 25.4 25.4 25.4 25.4 25.3 22.8 16.4 7.4 1.4 0.0 - Fruit '000 ha 10% 13.8 13.8 13.8 13.8 13.8 13.8 13.7 12.4 8.9 4.0 0.8 0.0 - Winter wheat '000 ha 27% 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 28.2 12.7 1.7 0.0 Total crops Kizil Tepa '000 ha 108% 146.4 146.4 146.4 146.4 146.4 146.4 146.0 135.3 99.1 44.6 7.7 0.0 Cropping pattern Karaul Bazar - Cotton '000 ha 36% 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 0.0 - Fodder '000 ha 28% 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 0.0 - Vegetables '000 ha 7% 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 0.0 - Fruit '000 ha 1% 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.0 - Winter wheat '000 ha 40% 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 0.0 Total Crops Karaul Bazar '000 ha 112% 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 0.0 Sources : Table 2 Table A.29 13 14 15 16 17 18 19 20 21 22 23 24 25

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Table A.31 Cropped Area. Cotton, Forage Crops, Vegetables. 'Without-Project' Scenario. '000 ha. Reduced Cost Option. Pumps fail

Cotton Year 1 2 3 4 5 6 7 8 9 Cotton Kuyu Mazar 41% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 2.7 8.1 16.0 - Reduced yield '000 ha 1.8 1.8 1.8 1.8 1.8 1.8 1.7 1.4 1.0 - Unaffected '000 ha 34.3 34.3 34.3 34.3 34.3 34.3 31.7 26.6 19.1 - Total area '000 ha 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 Cotton Kizil Tepa 37% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.2 5.1 17.8 - Reduced yield '000 ha 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.3 1.6 - Unaffected '000 ha 47.7 47.7 47.7 47.7 47.7 47.7 47.5 42.9 30.7 - Total area '000 ha 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 Cotton Karaul Bazar 36% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - Reduced yield '000 ha 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 - Unaffected '000 ha 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.4 5.4 - Total area '000 ha 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 Forage Forage Kuyu Mazar 16% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 1.1 3.3 6.4 - Reduced yield '000 ha 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.6 0.4 - Unaffected '000 ha 13.8 13.8 13.8 13.8 13.8 13.8 12.7 10.7 7.7 - Total area '000 ha 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 Forage Kizil Tepa 15% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.1 2.1 7.4 - Reduced yield '000 ha 1.0 1.0 1.0 1.0 1.0 1.0 1.0 0.9 0.7 - Unaffected '000 ha 19.7 19.7 19.7 19.7 19.7 19.7 19.6 17.7 12.7 - Total area '000 ha 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 Forage Karaul Bazar 28% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - Reduced yield '000 ha 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 - Unaffected '000 ha 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 - Total area '000 ha 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 Vegetables Vegetables Kuyu Mazar 17% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 1.2 3.5 6.9 - Reduced yield '000 ha 0.8 0.8 0.8 0.8 0.8 0.8 0.7 0.6 0.4 - Unaffected '000 ha 14.8 14.8 14.8 14.8 14.8 14.8 13.6 11.5 8.2 - Total area '000 ha 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 Vegetables Kizil Tepa 19% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.1 2.6 9.0 - Reduced yield '000 ha 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.1 0.8 - Unaffected '000 ha 24.1 24.1 24.1 24.1 24.1 24.1 24.0 21.7 15.5 - Total area '000 ha 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 Vegetables Karaul Bazar 7% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - Reduced yield '000 ha 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 - Unaffected '000 ha 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 - Total area '000 ha 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 Sources: Table A.30 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

27.0 34.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 0.5 0.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 8.7 1.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1 36.1

35.6 47.4 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 0.7 0.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 13.8 2.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2 50.2

0.0 0.0 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 0.3 0.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 5.4 5.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7 5.7

10.8 13.7 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 0.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 3.5 0.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5 14.5

14.7 19.6 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 0.3 0.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 5.7 1.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7 20.7

0.0 0.0 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 0.2 0.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 4.3 4.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5

11.6 14.7 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 0.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 3.7 0.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5 15.5

18.0 24.0 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 0.4 0.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 7.0 1.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4 25.4

0.0 0.0 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 0.1 0.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 1.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 Table A.32 Cropped Areas. Fruit, Winter Wheat. 'Without-Project' Scenario.'000 ha. Reduced Cost Option. Pumps fail

Fruit Year 1 2 3 4 5 6 7 8 9 Fruit Kuyu Mazar 11% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.8 2.2 4.4 - Reduced yield '000 ha 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.4 0.3 - Unaffected '000 ha 9.5 9.5 9.5 9.5 9.5 9.5 8.7 7.3 5.3 - Total area '000 ha 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 Fruit Kizil Tepa 10% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.1 1.4 4.9 - Reduced yield '000 ha 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.6 0.4 - Unaffected '000 ha 13.1 13.1 13.1 13.1 13.1 13.1 13.0 11.8 8.4 - Total area '000 ha 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 Fruit Karaul Bazar 1% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - Reduced yield '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - Unaffected '000 ha 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 - Total area '000 ha 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 Winter wheat Wheat Kuyu Mazar 23% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 6.8 - Reduced yield '000 ha 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 0.7 - Unaffected '000 ha 19.4 19.4 19.4 19.4 19.4 19.4 19.4 19.4 13.0 - Total area '000 ha 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 Wheat Kizil Tepa - Out of production '000 ha 27% 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 8.3 - Reduced yield '000 ha 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.4 - Unaffected '000 ha 34.6 34.6 34.6 34.6 34.6 34.6 34.6 34.6 26.8 - Total area '000 ha 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 Wheat Karaul Bazar 40% - Out of production '000 ha 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - Reduced yield '000 ha 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 - Unaffected '000 ha 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 - Total area '000 ha 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 Total croppable areas Kuyu Mazar '000 ha 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 Kizil Tepa '000 ha 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 Karaul Bazar '000 ha 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 Total '000 ha 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 Source: Table A.30 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

7.4 9.4 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 0.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.4 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9 9.9

9.8 13.0 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 0.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 3.8 0.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8 13.8

0.0 0.0 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.2 0.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2

14.2 19.5 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 0.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 5.9 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4 20.4

23.7 34.7 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 0.6 0.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 12.1 1.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4 36.4

0.0 0.0 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 0.3 0.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 6.0 6.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3

96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 96.5 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 146.4 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 17.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 260.8 Table A.33 Net Crop returns. Kuyu Mazar. 'Without-Project Scenario. UZS million. Economic prices.Reduced Cost Option. Pumps fail

per ha return Year 1 2 3 4 5 6 7 8 9 10 Net returns without-project UZS'000/ha Kuyu Mazar Total Total Total Total Total Total Total Total Total Total - Cotton (marginal) 2668 4,821 4,821 4,821 4,821 4,821 4,821 4,455 3,739 2,688 1,223 - Cotton (unaffected) 3570 122,571 122,571 122,571 122,571 122,571 122,571 113,261 95,048 68,336 31,090 - Cotton (total) 127,393 127,393 127,393 127,393 127,393 127,393 117,717 98,786 71,024 32,313

- Forage (marginal) 930 675 675 675 675 675 675 623 523 376 171 - Forage (unaffected) 1977 27,242 27,242 27,242 27,242 27,242 27,242 25,173 21,125 15,188 6,910 - Forage (total) 27,917 27,917 27,917 27,917 27,917 27,917 25,797 21,648 15,564 7,081

- Vegetables (marginal) 1236 961 961 961 961 961 961 888 745 536 244 - Vegetables (unaffected) 2608 38,520 38,520 38,520 38,520 38,520 38,520 35,595 29,871 21,476 9,771 - Vegetables (total) 39,481 39,481 39,481 39,481 39,481 39,481 36,483 30,616 22,012 10,014

- Fruit (marginal) 1120 557 557 557 557 557 557 515 432 311 141 - Fruit (unaffected) 2532 23,926 23,926 23,926 23,926 23,926 23,926 22,108 18,553 13,339 6,069 - Fruit (total) 24,483 24,483 24,483 24,483 24,483 24,483 22,623 18,985 13,650 6,210

- Wheat (marginal) 1164 1,187 1,187 1,187 1,187 1,187 1,187 1,187 1,187 794 361 - Wheat (unaffected) 1892 36,655 36,655 36,655 36,655 36,655 36,655 36,655 36,655 24,523 11,157 - Wheat (total) 37,842 37,842 37,842 37,842 37,842 37,842 37,842 37,842 25,318 11,518

Kuyu Mazar Total Return 257,116 257,116 257,116 257,116 257,116 257,116 240,461 207,878 147,567 67,137 Sources: Table A.31 Table A.32 Table 14 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Total Total Total Total Total Total Total Total Total Total Total Total Total Total Total 271 ------6,877 ------7,147 ------

38 ------1,528 ------1,566 ------

54 ------2,161 ------2,215 ------

31 ------1,342 ------1,374 ------

54 ------1,677 ------1,731 ------

14,033 ------Table A.34 Net Crop returns. Kizil Tepa. 'Without-Project Scenario. UZS million. Economic prices. Reduced Cost Option. Pumps fail

per ha return Year 1 2 3 4 5 6 7 8 9 10 UZS'000/ha Kizil Tepa Total Total Total Total Total Total Total Total Total Total - Cotton (marginal) 2,668 6,697 6,697 6,697 6,697 6,697 6,697 6,672 6,018 4,317 1,944 - Cotton (unaffected) 3,570 170,260 170,260 170,260 170,260 170,260 170,260 169,625 152,999 109,739 49,418 - Cotton (total) - 176,957 176,957 176,957 176,957 176,957 176,957 176,297 159,018 114,056 51,362

- Forage (marginal) 930 962 962 962 962 962 962 958 864 620 279 - Forage (unaffected) 1,977 38,847 38,847 38,847 38,847 38,847 38,847 38,702 34,909 25,039 11,275 - Forage (total) - 39,809 39,809 39,809 39,809 39,809 39,809 39,661 35,773 25,659 11,555

- Vegetables (marginal) 1,236 1,568 1,568 1,568 1,568 1,568 1,568 1,562 1,409 1,011 455 - Vegetables (unaffected) 2,608 62,853 62,853 62,853 62,853 62,853 62,853 62,618 56,481 40,511 18,243 - Vegetables (total) - 64,421 64,421 64,421 64,421 64,421 64,421 64,180 57,890 41,522 18,698

- Fruit (marginal) 1,120 771 771 771 771 771 771 768 693 497 224 - Fruit (unaffected) 2,532 33,110 33,110 33,110 33,110 33,110 33,110 32,986 29,753 21,341 9,610 - Fruit (total) - 33,881 33,881 33,881 33,881 33,881 33,881 33,754 30,446 21,837 9,834

- Wheat (marginal) 1,164 2,120 2,120 2,120 2,120 2,120 2,120 2,120 2,120 1,640 738 - Wheat (unaffected) 1,892 65,464 65,464 65,464 65,464 65,464 65,464 65,464 65,464 50,633 22,801 - Wheat (total) 67,584 67,584 67,584 67,584 67,584 67,584 67,584 67,584 52,272 23,539

Kizil Tepa Total Return 382,652 382,652 382,652 382,652 382,652 382,652 381,476 350,711 255,346 114,987 Sources: Table A.31 Table A.32 Table 14 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Total Total Total Total Total Total Total Total Total Total Total Total Total Total Total 367 ------9,327 ------9,694 ------

53 ------2,128 ------2,181 ------

86 ------3,443 ------3,529 ------

42 ------1,814 ------1,856 ------

99 ------3,060 ------3,159 ------

20,420 ------Table A.35 Net Crop returns. Karaul Bazar. 'Without-Project Scenario. UZS million. Economic prices (pumps fail). Reduced Cost Option. Pumps fail

per ha return Year 1 2 3 4 5 6 7 8 9 10 UZS'000/ha Karaul Bazar Total Total Total Total Total Total Total Total Total Total - Cotton (marginal) 2,668 763 763 763 763 763 763 763 763 763 763 - Cotton (unaffected) 3,570 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 19,385 - Cotton (total) - 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147 20,147

- Forage (marginal) 930 208 208 208 208 208 208 208 208 208 208 - Forage (unaffected) 1,977 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 8,406 - Forage (total) - 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614 8,614

- Vegetables (marginal) 1,236 68 68 68 68 68 68 68 68 68 68 - Vegetables (unaffected) 2,608 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 2,737 - Vegetables (total) - 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806 2,806

- Fruit (marginal) 1,120 10 10 10 10 10 10 10 10 10 10 - Fruit (unaffected) 2,532 447 447 447 447 447 447 447 447 447 447 - Fruit (total) - 458 458 458 458 458 458 458 458 458 458

- Wheat (marginal) 1,164 369 369 369 369 369 369 369 369 369 369 - Wheat (unaffected) 1,892 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 11,385 - Wheat (total) 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754 11,754

Karaul Bazar Total Return 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 Sources: Table A.31 Table A.32 Table 14 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Total Total Total Total Total Total Total Total Total Total Total Total Total Total Total 763 ------19,385 ------20,147 ------

208 ------8,406 ------8,614 ------

68 ------2,737 ------2,806 ------

10 ------447 ------458 ------

369 ------11,385 ------11,754 ------

43,779 ------Table A.36 Net Crop Returns. 'With-Project' Incremental Benefits. UZS million. Reduced Cost Option. Pumps fail

Year 1 2 3 4 5 6 7 8 9 10 11 Without-Project' Return - Kuyu Mazar 257,116 257,116 257,116 257,116 257,116 257,116 240,461 207,878 147,567 67,137 14,033 - Kizil Tepa 382,652 382,652 382,652 382,652 382,652 382,652 381,476 350,711 255,346 114,987 20,420 - Karaul Bazar 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 Total 'Without-Project' Return 683,547 683,547 683,547 683,547 683,547 683,547 665,716 602,367 446,692 225,903 78,231 'With-Project' Return - Kuyu Mazar 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 - Kizil Tepa 382,652 382,652 382,652 382,652 382,652 382,652 381,476 350,711 313,957 313,957 313,957 - Karaul Bazar 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 Total 'With-Project' Return 683,547 683,547 683,547 683,547 683,547 683,547 682,371 651,606 614,852 614,852 614,852 Net 'With -Project' Incremental Return ------16,655 49,238 168,160 388,949 536,620 Source: Table A.33 Table A.34 Table A.35 12 13 14 15 16 17 18 19 20 21 22 23 24 25

------

257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 257,116 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 313,957 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 43,779 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 614,852 Table A.37 Without and With-Project Non-energy Recurrent Costs - @ constant 2012 Financial prices. US$ M. Full Cost Option. Pumps fail

Current Year 1 2 3 4 5 6 7 8 9 10 Without -project Pump Station O&M - Khamza 1 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 - Khamza 1 Auxiliary 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 - Khamza 2 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 - Kuyu Mazar 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 - Kizil Tepa 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 - Kizil Tepa Aux 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 Sub-total PS 1.22 1.22 1.22 1.22 1.22 1.22 1.22 1.22 1.22 1.22 1.22 Remaining ABIS O&M costs 5.13 5.13 5.13 5.13 5.13 5.13 5.13 4.97 4.41 3.26 1.66 Total 'without-project' O&M 6.35 6.35 6.35 6.35 6.35 6.35 6.35 6.19 5.63 4.48 2.88 Future 'With-project' Option 1 - Khamza 1 1.42 0.19 0.19 0.19 0.19 0.19 0.19 1.42 1.42 1.42 1.42 - Khamza 1 Auxiliary 0.00 0.06 0.06 0.06 0.06 0.06 0.06 0.00 0.00 0.00 0.00 - Khamza 2 1.34 0.22 0.22 0.22 0.22 0.22 0.22 1.34 1.34 1.34 1.34 - Kuyu Mazar 0.49 0.17 0.17 0.17 0.17 0.17 0.17 0.49 0.49 0.49 0.49 - Kizil Tepa 0.98 0.31 0.31 0.31 0.31 0.31 0.31 0.98 0.98 0.98 0.98 - Kizil Tepa Aux 0.27 0.26 0.26 0.26 0.26 0.26 0.26 0.27 0.27 0.27 0.27 Sub-total PS 4.50 1.22 1.22 1.22 1.22 1.22 1.22 4.50 4.50 4.50 4.50 Periodic Maintenance - Khamza 1 1.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - Khamza 1 Auxiliary 0.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - Khamza 2 1.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - Kuyu Mazar 0.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - Kizil Tepa 1.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - Kizil Tepa Aux 0.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Sub-total Periodic maintenance 6.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Remaining ABIS O&M costs 5.13 5.13 5.13 5.13 5.13 5.13 5.13 4.97 4.61 4.61 4.61 Discharge pipe special maintenance 0.00 12.24 12.24 12.24 12.24 12.24 12.24 12.24 0.00 0.00 0.00 Total 'with-project' O&M 18.59 18.59 18.59 18.59 18.59 18.59 21.71 9.11 9.11 9.11 Incremental 'with-project' O&M costs 12.24 12.24 12.24 12.24 12.24 12.24 15.52 3.48 4.63 6.23 Without and With-Project Non-energy Recurrent Costs - @ constant 2012 Financial prices. US$ M. Full Cost Option. Pumps fail

11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 1.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 1.34 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50 4.50

0.00 0.00 0.00 1.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.99 0.00 0.00 0.00 0.00 0.00 0.00 0.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.70 0.00 0.00 0.00 0.00 0.00 0.00 1.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.43 0.00 0.00 0.00 0.00 0.00 0.00 0.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.38 0.00 0.00 0.00 0.00 0.00 0.00 6.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.40 0.00 0.00 0.00 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 4.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.11 9.11 9.11 15.50 9.11 9.11 9.11 9.11 9.11 9.11 9.11 15.50 9.11 9.11 9.11 7.71 9.11 9.11 15.50 9.11 9.11 9.11 9.11 9.11 9.11 9.11 15.50 9.11 9.11 9.11 Table A.39 Power Consumption 'With-project' Scenario. Mwh/year. Reduced Cost Option, Pumps fail

Present usage Cost ratio Future usage Year 1 2 3 4 5 6 7 8 9 Stage 1. Khamza 1 165,791 95.2% 157,865 165,791 165,791 165,791 165,791 165,791 165,791 157,865 157,865 157,865 Khamza Aux 19,317 95.2% 18,393 19,317 19,317 19,317 19,317 19,317 19,317 - - - Khamza 2 639,497 95.2% 608,927 639,497 639,497 639,497 639,497 639,497 639,497 608,927 608,927 608,927 Total Stage 1 824,605 785,185 824,605 824,605 824,605 824,605 824,605 824,605 766,792 766,792 766,792 Stage 2/3 Kuyu Mazar Main Station 109,847 95.2% 104,596 109,847 109,847 109,847 109,847 107,221 104,596 104,596 104,596 104,596 Kuyu Mazar Auxiliary (new) 38,786 82.4% 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 Sub-total Kuyu Mazar 148,633 136,548 141,799 141,799 141,799 141,799 139,173 136,548 136,548 136,548 136,548 Kizil Tepa Main Station 398,025 95.2% 378,997 398,025 398,025 398,025 398,025 398,025 398,025 283,627 283,627 283,627 Kizil Tepa Auxiliary 33,207 95.2% 31,619 33,207 33,207 33,207 33,207 33,207 33,207 13,636 13,636 13,636 Navoi (new) 46,700 69.6% 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 Sub-total Kizil Tepa 477,931 443,103 463,718 463,718 463,718 463,718 463,718 463,718 329,750 329,750 329,750 Drujba 12,150 100.0% 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 Karaul Bazar 54,393 100.0% 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 Sub-total Karaul Bazar 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 Total Stage 2/3 693,108 646,194 672,060 672,060 672,060 672,060 669,435 666,809 532,841 532,841 532,841

Total Stage 1 and 2/3 1,517,712 1,431,379 1,496,665 1,496,665 1,496,665 1,496,665 1,494,039 1,491,414 1,299,632 1,299,632 1,299,632 Increasing inefficiency of new pump factor % 100% 100% 100% 100% 100% 100% 100% 100% 100% Net Mwh with declining pump efficiency 1,496,665 1,496,665 1,496,665 1,496,665 1,494,039 1,491,414 1,299,632 1,299,632 1,299,632 Improved system efficiency factor % 1.5% 100% 100% 100% 100% 100% 100% 99% 97% 96% Net Mwh with improved system efficiency 1,496,665 1,496,665 1,496,665 1,496,665 1,494,039 1,491,414 1,280,138 1,260,643 1,241,149 Sources : Table 6 Table A.38 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 157,865 ------608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 608,927 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792 766,792

104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 104,596 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 31,952 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 136,548 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 283,627 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 13,636 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 32,487 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 329,750 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 12,150 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 54,393 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 66,543 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841 532,841

1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 100% 100% 100% 100% 100% 100% 100% 101% 101% 102% 102% 103% 103% 104% 105% 105% 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,299,632 1,306,813 1,314,073 1,321,414 1,328,838 1,336,345 1,343,938 1,351,618 1,359,386 1,367,243 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 1,241,149 1,241,149 1,241,149 1,241,149 1,241,149 1,241,149 1,241,149 1,248,006 1,254,939 1,261,950 1,269,040 1,276,210 1,283,461 1,290,795 1,298,213 1,305,717 Table A.40 Capital Costs phased @ constant 2012 financial prices. US$ million Excluding discharge pipes in all PS except Khamza 1, and covering partial rehabilitation of two Kizil Tepa PS. Year 1 2 3 4 5 6 7 Total Khamza 1 new Civil works: - construction of pump house 0.00 0.00 13.59 13.59 0.00 0.00 0.00 27.19 - construction of intake 0.00 0.00 0.00 1.43 0.00 0.00 0.00 1.43 Equipment and mechanical - acquisition of hardware 0.00 0.00 17.12 17.12 17.12 5.71 0.00 57.07 - installation of discharge pipes 0.00 0.00 0.00 1.16 0.39 0.39 0.00 1.93 - installation of equipment 0.00 0.00 0.00 0.94 2.40 1.07 0.00 4.41 Sub-total Khamza 1 0.00 0.00 30.72 34.24 19.91 7.17 0.00 92.04 Kuyu Mazar rehab Civil works: - rehabilitation of pump house 0.00 0.00 0.00 2.66 0.00 0.00 0.00 2.66 Equipment and mechanical - acquisition of hardware 0.00 0.00 5.23 10.46 5.23 0.00 0.00 20.93 - installation of equipment 0.00 0.00 0.00 0.58 1.16 0.58 0.00 2.33 Sub-total Kuyu Mazar 0.00 0.00 5.23 13.71 6.39 0.58 0.00 25.91 Khamza 2 rehab Civil works: - rehabilitation of pump house 1.34 1.34 Equipment and mechanical - acquisition of hardware 14.92 29.83 14.92 59.67 - installation of discharge pipes 0.03 0.06 0.03 0.12 - installation of equipment 1.63 3.25 1.63 6.51 Sub-total Khamza 2 0.00 0.00 14.95 32.87 18.20 1.63 0.00 67.64 Kizil Tepa rehab Civil works: - rehabilitation of pump house 2.55 2.55 Equipment and mechanical - acquisition of hardware 10.73 21.47 10.73 42.94 - installation of discharge pipes 0.03 0.07 0.03 0.13 - installation of equipment 1.16 2.32 1.16 4.64 Sub-total Kizil Tepa 0.00 0.00 10.77 25.25 13.09 1.16 0.00 50.26 Kizil Tepa Auxiliary rehab Civil works: - rehabilitation of pump house 2.07 2.07 Equipment and mechanical - acquisition of hardware 2.83 5.65 2.83 11.30 - installation of discharge pipes 0.01 0.03 0.01 0.06 - installation of equipment 0.30 0.60 0.30 1.20 Sub-total Kizil Tepa Aux 0.00 0.00 2.84 8.05 3.44 0.30 0.00 14.63 ABMK rehabilitation Civil works 0.00 0.00 0.00 0.82 2.45 1.54 0.00 4.81 Acquisition/installation of equipmenrt 0.00 0.00 0.00 0.43 1.28 0.81 0.00 2.52 Sub-total ABMK rehabilitation 0.00 0.00 0.00 1.25 3.74 2.35 0.00 7.33 DSS and SCADA Equipment 0.00 0.00 0.00 0.83 0.00 0.00 0.00 0.83 Consultancy 0.00 0.00 0.00 0.45 0.00 0.00 0.00 0.45 Training 0.00 0.00 0.00 0.06 0.00 0.00 0.00 0.06 Project Management 0.00 0.00 0.00 0.11 0.00 0.00 0.00 0.11 Sub-total DSS/SCADA 0.00 0.00 0.00 1.45 0.00 0.00 0.00 1.45 Pilot Farms Civil works - off and on farm canals 0.000 0.054 0.162 0.109 0.000 0.000 0.000 0.325 Equipment acquisition 0.000 0.166 0.166 0.000 0.000 0.000 0.000 0.332 Training 0.000 0.300 0.300 0.200 0.105 0.000 0.000 0.905 Field operations - Shelter belts 0.000 0.002 0.002 0.002 0.000 0.000 0.000 0.006 - Levelling 0.000 0.008 0.008 0.000 0.000 0.000 0.000 0.016 - Ripping 0.000 0.003 0.005 0.003 0.000 0.000 0.000 0.010 - Minimum tillage 0.000 0.001 0.001 0.001 0.000 0.000 0.000 0.003 - Other 0.000 0.002 0.022 0.040 0.040 0.050 0.000 0.154 Sub-total Pilot Farms 0.000 0.535 0.666 0.354 0.145 0.050 0.000 1.750 Consultancy International 0.80 0.90 0.86 0.82 0.46 0.44 0.00 4.28 National 0.25 0.35 0.39 0.39 0.34 0.30 0.03 2.04 Supporting Services 0.15 0.18 0.17 0.16 0.09 0.08 0.00 0.83 Equipment and vehicles 0.25 0.00 0.00 0.00 0.00 0.00 0.00 0.25 Workshops 0.00 0.14 0.05 0.14 0.05 0.13 0.00 0.50 Management 0.07 0.07 0.07 0.07 0.07 0.07 0.03 0.47 Surveys 0.00 0.26 0.26 0.00 0.00 0.00 0.00 0.53 Sub-total Consultancy 1.52 1.92 1.80 1.58 1.01 1.02 0.05 8.90 PMO Staff 0.05 0.05 0.05 0.05 0.05 0.05 0.00 0.32 Equipment and vehicles 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.03 Management 0.05 0.04 0.04 0.04 0.04 0.04 0.02 0.25 Sub-total PMO 0.13 0.09 0.09 0.09 0.09 0.09 0.02 0.60 PIU Staff 0.07 0.07 0.07 0.07 0.07 0.07 0.03 0.43 Equipment and vehicles 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.03 Management 0.03 0.02 0.02 0.02 0.02 0.02 0.00 0.14 Sub-total PIU 0.13 0.09 0.09 0.09 0.09 0.09 0.03 0.60 Total Base Cost 1.78 2.63 67.15 118.91 66.11 14.43 0.11 271.11 Physical Contingencies - civil works 0.00 0.01 0.97 1.75 0.25 0.15 0.00 3.12 - other 0.14 0.21 5.30 9.40 6.34 1.26 0.01 22.67 Total Capital Costs, incl contingencies 1.92 2.85 73.41 130.06 72.69 15.85 0.12 296.90 Table A.41 Capital Costs phased @ constant 2012 economic prices. US$ million Excluding discharge pipes in all PS except Khamza 1, and covering partial rehabilitation of two Kizil Tepa PS. Year 1 2 3 4 5 6 7 Total Khamza 1 new Civil works: - construction of pump house 0.00 0.00 8.88 8.88 0.00 0.00 0.00 17.76 - construction of intake 0.00 0.00 0.00 0.93 0.00 0.00 0.00 0.93 Equipment and mechanical - acquisition of hardware 0.00 0.00 16.53 16.53 16.53 5.51 0.00 55.10 - installation of discharge pipes 0.00 0.00 0.00 1.11 0.37 0.37 0.00 1.85 - installation of equipment 0.00 0.00 0.00 0.90 2.32 1.04 0.00 4.26 Sub-total Khamza 1 0.00 0.00 25.41 28.36 19.22 6.92 0.00 79.91 Kuyu Mazar rehab Civil works: - rehabilitation of pump house 0.00 0.00 0.00 1.74 0.00 0.00 0.00 1.74 Equipment and mechanical - acquisition of hardware 0.00 0.00 5.07 10.13 5.07 0.00 0.00 20.26 - installation of equipment 0.00 0.00 0.00 0.56 1.13 0.56 0.00 2.25 Sub-total Kuyu Mazar 0.00 0.00 5.07 12.43 6.19 0.56 0.00 24.25 Khamza 2 rehab Civil works: - rehabilitation of pump house 0.00 0.00 0.00 0.88 0.00 0.00 0.00 0.88 Equipment and mechanical - acquisition of hardware 0.00 0.00 14.45 28.90 14.45 0.00 0.00 57.80 - installation of discharge pipes 0.00 0.00 0.03 0.06 0.03 0.00 0.00 0.12 - installation of equipment 0.00 0.00 0.00 1.58 3.15 1.58 0.00 6.31 Sub-total Khamza 2 0.00 0.00 14.48 31.41 17.63 1.58 0.00 65.10 Kizil Tepa rehab Civil works: - rehabilitation of pump house 0.00 0.00 0.00 1.67 0.00 0.00 0.00 1.67 Equipment and mechanical - acquisition of hardware 0.00 0.00 10.39 20.78 10.39 0.00 0.00 41.55 - installation of discharge pipes 0.00 0.00 0.03 0.06 0.03 0.00 0.00 0.13 - installation of equipment 0.00 0.00 0.00 1.12 2.24 1.12 0.00 4.49 Sub-total Kizil Tepa 0.00 0.00 10.42 23.63 12.66 1.12 0.00 47.83 Kizil Tepa Auxiliary rehab Civil works: - rehabilitation of pump house 0.00 0.00 0.00 1.35 0.00 0.00 0.00 1.35 Equipment and mechanical - acquisition of hardware 0.00 0.00 2.07 4.14 2.07 0.00 0.00 8.27 - installation of discharge pipes 0.00 0.00 0.01 0.02 0.01 0.00 0.00 0.04 - installation of equipment 0.00 0.00 0.00 0.22 0.44 0.22 0.00 0.88 Sub-total Kizil Tepa Aux 0.00 0.00 2.08 5.73 2.52 0.22 0.00 10.54 ABMK rehabilitation Civil works 0.00 0.00 0.00 0.53 1.60 1.01 0.00 3.14 Acquisition/installation of equipment 0.00 0.00 0.00 0.41 1.23 0.77 0.00 2.42 Sub-total ABMK rehabilitation 0.00 0.00 0.00 0.95 2.84 1.78 0.00 5.56 DSS and SCADA Equipment 0.00 0.00 0.00 0.83 0.00 0.00 0.00 0.83 Consultancy 0.00 0.00 0.00 0.43 0.00 0.00 0.00 0.43 Training 0.00 0.00 0.00 0.05 0.00 0.00 0.00 0.05 Project Management 0.00 0.00 0.00 0.09 0.00 0.00 0.00 0.09 Sub-total DSS/SCADA 0.00 0.00 0.00 1.40 0.00 0.00 0.00 1.40 Pilot Farms Civil works - off and on farm canals 0.000 0.045 0.136 0.091 0.000 0.000 0.000 0.273 Equipment acquisition 0.000 0.162 0.162 0.000 0.000 0.000 0.000 0.323 Training 0.000 0.240 0.240 0.160 0.084 0.000 0.000 0.724 Field operations - Shelter belts 0.000 0.002 0.002 0.002 0.000 0.000 0.000 0.005 - Levelling 0.000 0.008 0.008 0.000 0.000 0.000 0.000 0.015 - Ripping 0.000 0.002 0.004 0.002 0.000 0.000 0.000 0.008 - Minimum tillage 0.000 0.001 0.001 0.001 0.000 0.000 0.000 0.002 - Other 0.000 0.002 0.018 0.034 0.034 0.042 0.000 0.129 Sub-total Pilot Farms 0.000 0.460 0.571 0.289 0.118 0.042 0.000 1.480 Consultancy International 0.80 0.90 0.86 0.82 0.46 0.44 0.00 4.28 National 0.20 0.28 0.31 0.31 0.27 0.24 0.02 1.63 Supporting Services 0.15 0.18 0.16 0.15 0.09 0.08 0.00 0.82 Equipment and vehicles 0.23 0.00 0.00 0.00 0.00 0.00 0.00 0.23 Workshops 0.00 0.11 0.04 0.11 0.04 0.10 0.00 0.41 Management 0.07 0.07 0.07 0.07 0.07 0.07 0.02 0.42

Sub-total Consultancy 1.44 1.55 1.44 1.46 0.93 0.93 0.05 7.79 PMO Staff 0.04 0.04 0.04 0.04 0.04 0.04 0.00 0.26 Equipment and vehicles 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.03 Management 0.04 0.03 0.03 0.03 0.03 0.03 0.02 0.20 Sub-total PMO 0.11 0.07 0.07 0.07 0.07 0.07 0.02 0.48 PIU Staff 0.05 0.05 0.05 0.05 0.05 0.05 0.03 0.34 Equipment and vehicles 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.03 Management 0.03 0.02 0.02 0.02 0.02 0.02 0.00 0.11 Sub-total PIU 0.11 0.07 0.07 0.07 0.07 0.07 0.03 0.48 Total Base Cost 1.65 2.15 59.61 105.80 62.25 13.29 0.09 244.84 Physical Contingencies - civil works 0.00 0.00 0.64 1.14 0.16 0.10 0.00 2.04 - other 0.16 0.21 5.06 8.97 6.06 1.23 0.01 21.71 Total Capital Costs, incl contingencies 1.81 2.36 65.30 115.92 68.48 14.62 0.10 268.59

Currency factor 0.75942 Table A.42 Base Case EIRR calculations. Cash Flows. US$ million. Full Cost Option. Pumps decline

Year 1 2 3 4 5 6 7 8 9 10 Capital Cost Khamza 1 79.9 0.0 0.0 25.4 28.4 19.2 6.9 Kuyu Mazar 24.3 0.0 0.0 5.1 12.4 6.2 0.6 Khamza 2 65.1 0.0 0.0 14.5 31.4 17.6 1.6 Kizil Tepa 47.8 0.0 0.0 10.4 23.6 12.7 1.1 Kizil Tepa Aux 10.5 0.0 0.0 2.1 5.7 2.5 0.2 ABMK rehab 5.6 0.0 0.0 0.0 0.9 2.8 1.8 DSS/SCADA 1.4 0.0 0.0 0.0 1.4 0.0 0.0 Pilot Farms 1.5 0.0 0.5 0.6 0.3 0.1 0.0 Consultancy 7.8 1.4 1.5 1.4 1.5 0.9 0.9 PMO 0.5 0.1 0.1 0.1 0.1 0.1 0.1 PIU 0.5 0.1 0.1 0.1 0.1 0.1 0.1 Contingencies 23.8 0.2 0.2 5.7 10.1 6.2 1.3 Total capital costs 268.6 1.8 2.4 65.3 115.9 68.5 14.6 Recurrent and periodic costs 3. Pump Station Rehabilitation 3.1. Energy costs - with project 0.000054 80.1 80.1 80.1 77.6 75.2 71.2 68.5 67.5 66.4 66.4 - without project 0.000054 80.1 80.1 80.1 77.6 75.2 71.2 67.4 63.8 60.4 57.1 Net incremental energy cost 0.0 0.0 0.0 0.0 0.0 0.0 1.1 3.7 6.1 9.3 3.2. Non-energy O&M and periodic cost - with project 14.1 14.1 14.1 14.1 14.1 14.2 21.7 9.1 9.1 9.1 - without project 4.8 4.8 4.8 4.6 4.4 4.2 4.1 3.9 3.8 3.7 Net incremental non-energy O&M cost 9.3 9.3 9.3 9.5 9.7 10.0 17.6 5.2 5.3 5.4 Total capital and recurrent costs 11.1 11.7 74.6 125.4 78.2 24.6 18.8 8.9 11.4 14.7 Net crop returns - with project 247.7 247.7 247.7 235.3 223.6 212.5 222.8 222.8 222.8 222.8 - without project 247.7 247.7 247.7 235.3 223.6 212.5 201.9 186.2 174.4 163.2 Incremental crop returns 0.0 0.0 0.0 0.0 0.0 0.0 20.9 36.5 48.3 59.6

Net cash flow -11.1 -11.7 -74.6 -125.4 -78.2 -24.6 2.1 27.7 37.0 44.8

EIRR 12.2%

0 Base Case EIRR calculations. Cash Flows. US$ million. Full Cost Option. Pumps decline 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

66.4 66.4 66.4 66.4 66.4 66.4 66.8 67.2 67.6 67.9 68.3 68.7 69.1 69.5 69.9 54.0 51.1 48.3 45.6 43.1 40.7 38.5 36.3 34.2 32.3 30.4 28.7 27.0 25.4 23.9 12.4 15.4 18.2 20.8 23.3 25.7 28.4 30.9 33.3 35.6 37.9 40.0 42.1 44.1 46.0

9.1 9.1 9.1 15.5 9.1 9.1 9.1 9.1 9.1 9.1 9.1 15.5 9.1 9.1 9.1 3.6 3.5 3.4 3.4 3.3 3.3 3.2 3.2 3.2 3.2 3.2 3.2 3.2 3.3 3.3 5.5 5.6 5.7 12.1 5.8 5.8 5.9 5.9 5.9 5.9 5.9 12.3 5.9 5.9 5.8 17.9 20.9 23.8 32.9 29.1 31.5 34.2 36.8 39.2 41.6 43.8 52.3 48.0 49.9 51.8

222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 154.0 144.0 134.5 125.5 116.9 108.8 101.1 93.7 86.8 80.1 73.9 67.9 58.1 53.1 48.5 68.8 78.8 88.3 97.3 105.8 114.0 121.7 129.0 136.0 142.6 148.9 154.9 164.7 169.6 174.3

50.9 57.8 64.4 64.3 76.7 82.4 87.5 92.3 96.8 101.1 105.1 102.6 116.8 119.7 122.5 Table A.43 Base Case EIRR calculations. Cash Flows. US$ million. Reduced Cost Option. Pumps fail

Base Year 1 2 3 4 5 6 7 8 9 10 11 Capital Cost Khamza 1 79.9 0.0 0.0 25.4 28.4 19.2 6.9 Kuyu Mazar 24.3 0.0 0.0 5.1 12.4 6.2 0.6 Khamza 2 65.1 0.0 0.0 14.5 31.4 17.6 1.6 Kizil Tepa 47.8 0.0 0.0 10.4 23.6 12.7 1.1 Kizil Tepa Aux 10.5 0.0 0.0 2.1 5.7 2.5 0.2 ABMK rehab 5.6 0.0 0.0 0.0 0.9 2.8 1.8 DSS/SCADA 1.4 0.0 0.0 0.0 1.4 0.0 0.0 Pilot Farms 1.5 0.0 0.5 0.6 0.3 0.1 0.0 Consultancy 7.8 1.4 1.5 1.4 1.5 0.9 0.9 PMO 0.5 0.1 0.1 0.1 0.1 0.1 0.1 PIU 0.5 0.1 0.1 0.1 0.1 0.1 0.1 Contingencies 23.75 0.16 0.21 5.69 10.12 6.23 1.33 Total capital costs 268.6 1.8 2.4 65.3 115.9 68.5 14.6 0.0 0.0 0.0 0.0 0.0 Recurrent and periodic costs 3. Pump Station Rehabilitation 3.1. Energy costs - with project 0.000054 80.1 80.1 80.1 80.1 80.0 79.8 68.5 67.5 66.4 66.4 66.4 - without project 0.000054 80.1 80.1 80.1 80.1 80.1 80.1 78.4 72.7 58.2 37.1 19.0 Net incremental energy cost 0.0 0.0 0.0 0.0 -0.1 -0.3 -9.9 -5.2 8.2 29.4 47.4 3.2. Non-energy O&M and periodic cost - with project 14.1 14.1 14.1 14.1 14.1 14.1 21.7 9.1 9.1 9.1 9.1 - without project 4.8 4.8 4.8 4.8 4.8 4.8 4.7 4.3 3.4 2.2 1.1 Net incremental non-energy O&M cost 9.3 9.3 9.3 9.3 9.3 9.3 17.0 4.8 5.7 6.9 8.0 Total capital and recurrent costs 11.1 11.7 74.6 125.2 77.6 23.6 7.2 -0.4 13.9 36.3 55.4 Net crop returns - with project 247.7 247.7 247.7 247.7 247.7 247.7 247.2 236.1 222.8 222.8 222.8 - without project 247.7 247.7 247.7 247.7 247.7 247.7 241.2 218.2 161.8 81.8 28.3 Incremental crop returns 0.0 0.0 0.0 0.0 0.0 0.0 6.0 17.8 60.9 140.9 194.4

Net cash flow -11.1 -11.7 -74.6 -125.2 -77.6 -23.6 -1.1 18.3 47.0 104.6 139.0

EIRR 18.4%

Sources : Table 18 Table A.37 Table A.39 Table A.38 Table A.36 12 13 14 15 16 17 18 19 20 21 22 23 24 25

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

66.4 66.4 66.4 66.4 66.4 66.8 67.2 67.6 67.9 68.3 68.7 69.1 69.5 69.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 66.4 66.4 66.4 66.4 66.4 66.8 67.2 67.6 67.9 68.3 68.7 69.1 69.5 69.9

9.1 9.1 15.5 9.1 9.1 9.1 9.1 9.1 9.1 9.1 15.5 9.1 9.1 9.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 9.1 9.1 15.5 9.1 9.1 9.1 9.1 9.1 9.1 9.1 15.5 9.1 9.1 9.1 75.5 75.5 81.9 75.5 75.5 75.9 76.3 76.7 77.0 77.4 84.2 78.2 78.6 79.0

222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8 222.8

147.2 147.2 140.8 147.2 147.2 146.9 146.5 146.1 145.7 145.4 138.6 144.6 144.2 143.8 Table A.44 Project Investment Plan ($ million) Item A. Base Cost 1. Output 1 Pump Stations 250.5 2.ABMK Rehabilitation 7.3 3. Demonstration Areas 1.7 4. Project management 11.5 Sub-total A 271.1 B. Contingencies - Physical 25.8 - Cost 21.0 Sub-total B 46.8 317.9 C. Financing Charges During Implementation 15.3 Total (A+B+C) 333.2 Table A.45 Financing Plan ($ million)

Amount ($ Source: million) Share of total %

Asian Development Bank 220.0 57.9% 1. Ordinary Capital Resources (OCR) 174.0 45.8% 2. Asian Development Fund (ADF) 46.0 12.1% Other Co-Financier/s JICA 100.0 26.3%

Government 60.0 15.8% Total 380.0 100.0%

Includes taxes and duties of $ 90.1 million to be financed from government sources Table A.46 E. Detailed Cost Estimates by Outputs/Components. $ million

Demonstration Total Cost Khamza 1 PS Kuyu Mazar Khamza 2 Kizil Tepa PS Kizil Tepa Aux PS ABMK SCADA Area Consultants PMO/PIU Item A Amount % Amount % Amount % Amount % Amount % Amount % Amount % Amount % Amount % Amount % Investment Costs 1. Civil Works 42.4 28.6 68% 2.7 6% 1.3 3% 2.6 6% 2.1 5% 4.8 11% 0% 0.3 1% 0% 0% 2.Mechanical & Equipment 217.2 63.4 29% 23.3 11% 66.3 31% 47.7 22% 12.6 6% 2.5 1% 0.8 0% 0.3 0% 0.3 0% 0.1 0% 3. Environmental and Social Mitigation 0.0 0.0 4. Consultants & Capacity Building (a) Project Implementation 8.1 0.0 0% 0.0 0% 0.0 0% 0.0 0% 0.0 0% 0% 0.4 6% 0% 7.7 94% 0% (b) Capacity Building 1.7 0.0 0% 0.0 0% 0.0 0% 0.0 0% 0.0 0% 0% 0.1 4% 1.1 66% 0.5 30% 0% 5. Project Management 1.7 0.0 0% 0.0 0% 0.0 0% 0.0 0% 0.0 0% 0% 0.1 6% 0% 0.5 27% 1.1 66% Subtotal A (Base Cost) 271.1 92.0 34% 25.9 10% 67.6 25% 50.3 19% 14.6 5% 7.3 3% 1.5 1% 1.8 1% 8.9 3% 1.2 0% B. Contingencies 1. Physical 25.8 8.3 32% 2.5 10% 6.7 26% 4.9 19% 1.4 5% 0.7 3% 0.1 1% 0.2 1% 0.7 3% 0.1 0% 2. Price 21.0 7.1 34% 2.0 10% 5.3 25% 3.9 19% 1.1 5% 0.5 3% 0.1 1% 0.1 1% 0.7 3% 0.1 0% Subtotal B 46.8 15.4 33% 4.5 10% 12.0 26% 8.9 19% 2.5 5% 1.3 3% 0.3 1% 0.3 1% 1.4 3% 0.2 0% Sub-total A+B 317.9 107.4 30.4 79.7 59.1 17.2 8.6 1.7 2.1 10.3 1.4 C. Financing Charges During Implementation 1. Interest During Implementation 14.3 4.9 34% 1.4 10% 3.6 25% 2.7 19% 0.8 5% 0.4 3% 0.1 1% 0.1 1% 0.5 3% 0.1 0% 2. Commitment Charges 1.0 0.3 34% 0.1 10% 0.2 25% 0.2 19% 0.1 5% 0.0 3% 0.0 1% 0.0 1% 0.0 3% 0.0 0% Subtotal C 15.3 5.2 34% 1.5 10% 3.8 25% 2.8 19% 0.8 5% 0.4 3% 0.1 1% 0.1 1% 0.5 3% 0.1 0% Total Project Cost (A+B+C) 333.2 112.6 31.9 83.5 62.0 18.0 9.0 1.8 2.2 10.8 1.4 Table A.47 A. Detailed Cost Estimates by Expenditure Category ($ million) Local Foreign Total Item Currency currency A Investment Costs 1. Civil Works 29.7 12.7 42.4 2.Mechanical & Equipment 35.7 181.5 217.2 3. Environmental and Social Mitigation 4. Consultants & Capacity Building (a) Project Implementation 2.7 5.4 8.1 (b) Capacity Building 1.6 0.1 1.7 5. Project Management 1.7 0.0 1.7 Subtotal A 71.4 199.8 271.1 B. Contingencies 1. Physical 6.8 19.0 25.8 2. Price 5.5 15.5 21.0 Subtotal B 12.3 34.5 46.8 Base Cost incl contingencies 83.7 234.2 317.9 C. Financing Charges During Implementation 1. Interest During Implementation 0 14.3 14.3 2. Commitment Charges 0 1.0 1.0 Subtotal C 0.0 15.3 15.3 Total Project Cost (A+B+C) 83.7 249.5 333.2

Taxes and Duties 44.7 44.7 Total Cost including duties and taxes 83.7 294.2 377.9 Table A.48 F. Detailed Cost Estimates by Year. ($ million)

Total Cost Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7

Item A Investment Costs 1. Civil Works 42.4 0.0 0.1 13.8 24.6 2.5 1.5 0.0 2.Mechanical & Equipment 217.2 0.3 0.2 51.1 91.7 62.3 11.6 0.0 3. Environmental and Social Mitigation 4. Consultants & Capacity Building (a) Project Implementation 8.6 1.3 1.8 1.8 1.9 1.0 0.9 0.1 (b) Capacity Building 1.7 0.0 0.5 0.4 0.4 0.2 0.2 0.0 5. Project Management 1.2 0.2 0.2 0.2 0.3 0.2 0.2 0.1 Subtotal A 271.1 1.8 2.6 67.1 118.9 66.1 14.4 0.1 B. Recurrent Costs 1. Pump Station Power 2. Pump Sation Maintenance Subtotal B 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Base Cost 271.1 1.8 2.6 67.1 118.9 66.1 14.4 0.1 C. Contingencies 1. Physical 25.8 0.1 0.2 6.3 11.1 6.6 1.4 0.0 2. Price 21.0 0.1 0.2 5.2 9.2 5.1 1.1 0.0 Subtotal C 46.8 0.3 0.4 11.5 20.3 11.7 2.5 0.0 Subtotal A+B+C 317.9 2.1 3.1 78.6 139.3 77.8 17.0 0.1 D. Financing Charges During Implementation 1. Interest During Implementation 14.3 0.0 0.1 0.8 2.9 4.8 5.7 2. Commitment Charges 1.0 0.5 0.2 0.2 0.1 0.0 0.0 Subtotal D 15.3 0.5 0.3 1.0 2.9 4.9 5.7 0.0 Total Project Cost (A+B+C+D) 333.2 2.5 3.4 79.6 142.2 82.7 22.7 0.1 Table A.49 A. Detailed Cost Estimates by Financier ($ million)

ADB (OCR) ADB (ADF) JICA Sub-total GOU Total cost Amount % Amount % Amount % Amount % A. Investment costs 1. Turnkey Contracts (a) New Khamza PS 92.0 92.0 92.0 (b) Khamza 2 PS 32.7 35.0 67.6 67.6 '/c) Kuyu Mazar PS 25.9 25.9 25.9 (d) Kizil Tepa PS 50.3 50.3 50.3 (e) Kizil Tepa Auxiliary PS 14.6 14.6 14.6 2. Civil Works 5.1 5.1 5.1 ADB financing 0.0 0.0 JICA financing 5.1 5.1 5.1 3. Equipment 4.0 4.0 4.0 ADB financing 0.0 0.0 JICA financing 4.0 4.0 4.0 4. Environment and Social Mitigation 0.0 2.05 2.1 5. Consulting Services 9.8 9.8 (a) Project Implementation 2.3 4.1 1.8 8.1 8.1 ADB financing 2.3 4.1 6.4 6.4 JICA financing 1.8 1.8 1.8 (b) Capacity Building 1.7 1.7 1.7 6. Project Management & Monitoring 1.7 1.7 1.7 7. Taxes and Duties 0.0 42.7 42.7 Total Base Cost 141.6 39.0 90.4 271.1 44.7 315.8 B. Contingencies - physical 13.2 3.9 8.7 25.8 25.8 - financial 10.9 3.1 6.9 21.0 21.0 - total 24.2 7.0 15.7 46.8 46.8 C. Financing Charges during Implementation 15.3 15.3 D. Total Project Cost (A+B+C) 165.8 0.0% 46.0 0.0% 106.0 0.0% 0.00 317.8 60.00 0.00 0.00 377.8

Amu Bukhara Irrigation System Rehabilitation Feasibility Study – Supplemental Report

Appendix 12

Updated Financial Management Assessment

Lahmeyer International in association with InfoCapital Group

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

APPENDIX 12 – FINANCIAL MANAGEMENT ASSESSMENT

CONTENTS

I. INTRODUCTION ...... 1 A. Summary of Findings ...... 1 B. Country Issues ...... 3 C. Executing Agency ...... 4 D. Funds Flow Arrangements ...... 5 E. Staffing ...... 6 F. Accounting Policies and Procedures ...... 7 G. Internal Audit ...... 8 H. External Audit ...... 9 I. Reporting and Monitoring ...... 9 J. Information System ...... 11 K. Conclusions ...... 11

List of Attachments

Attachment 1: Financial Management Assessment Questionnaire Attachment 2: Organizational Chart of the Ministry of Agriculture and Water Resources of the Republic of Uzbekistan Attachment 3: Structure of the Central Administration of the Ministry of Agriculture and Water Resources Attachment 4: Flow of Funds and Lending Arrangements Attachment 5: Chart of Accounts (National Accounting Standards No. 21)

List of Tables

Table 1: Summary of the FMA ...... 2 Table 2: List of statuary reporting requirements of the MAWR ...... 10 Table 3: Summary of Required Financial Reports ...... 11

Lahmeyer International in association with InfoCapital Group page i

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

I. INTRODUCTION

1. The purpose of this Financial Management Assessment (FMA) is to assess the financial management capacity of the Ministry of Agriculture and Water Resources (MAWR), the Executing Agency (EA) and the financial accounting units to be established under MAWR for the upcoming ADB-financed Amu Bukhara Irrigation System Rehabilitation Project (ABIS Rehabilitation Project). The Project with a cost of approximately $400 million will be implemented over 6 years, starting early in 2013. The estimated project completion date is 30 June 2019 and the loan closing date is 31 December 2019.

2. Within the framework of the FMA the following was undertaken: (i) review and analyse the results of Financial Management Assessment of MAWR, the executing agency; (ii) review of the FMA prepared for the proposed ADB-financed Farm and Agribusiness Development Project in Fruit and Vegetable Sectors (FADP) 2007; (iii) review the EA’s structure and management framework with regard to financial management; (iv) assessment of MAWR’s resources, including its personnel, the scale of Government budgetary support and other sources of income, its information technology equipment and software; and (v) MAWR’s experience in implementing externally financed projects. Consequently, analyses of the EA and PMO’s accounting, reporting, auditing, internal control systems, information systems, and capacity of the personnel were carried out. Additional follow-up interviews with MAWR and PMO staff, discussions with authorities, international financial institutions representatives, and reviews of relevant national legislation were also conducted.

3. The FMA is based on ADB’s Guidelines for the Financial Governance and Management of Projects Financed by the Bank (2002). The instrument used for assessment was ADB’s standard financial management assessment questionnaire (FMAQ).

A. Summary of Findings

4. It is concluded that MAWR currently satisfies ADB’s minimum financial management requirements for EAs. The MAWR has a satisfactory financial management capability to: (i) record required financial transactions and balances; (ii) provide regular and reliable financial statements and monitoring reports; (iii) safeguard financial assets; and (iv) submit the required financial documents to auditors with arrangements acceptable to ADB. A summary of the FMA is given in Table 1.

Lahmeyer International in association with InfoCapital Group page 1

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

Table 1: Summary of the FMA

Particulars Rating Conclusions

A. Implementing Moderate MAWR is a government ministry that is accountable to the Agency Cabinet of Ministers (COM) of the Republic of Uzbekistan. MAWR has experience in managing and implementing large scale projects financed by ADB, World Bank, and other international funding institutes.

B. Funds Flow Satisfactory MAWR has knowledge of and working experience in ADB Arrangements funds flow arrangements. Preliminary funds flow and lending arrangements have been identified in consultation with MAWR and Ministry of Finance representatives. Prior to loan negotiations it is essential to ensure the availability of counterpart funds for year 2009, which were not included in state investment program for year 2009.

C. Staffing Moderate MAWR is moderately staffed with experienced financial specialists. Since the project staff will be newly recruited, it is recommended to organize training and workshops on ADB financial management procedures. It is expected that on-the- job training provided by the staff of other PMO/PIU of ongoing projects, being implemented under MAWR, will also be beneficial.

D. Accounting Satisfactory The MAWR accounting policy is based on the Uzbekistan Policies and National Accounting Standards, which are progressively being Procedures modernized in accordance with International Accounting Standards. For ABIS Rehabilitation Project PMO/PIU separate accounting policy, subject to annual updates, and a financial management manual will be established in accordance with requirements of ADB and MOF of Uzbekistan.

E. Internal Audit N.A. There is no internal audit unit within the structure of the MAWR.

F. External Audit N.A. MAWR has not been audited by external auditor but annual procedural audits are conducted by MOF. Operating PMOs under the Ministry are audited by independent external auditors on an annual basis. Audit of the project accounts will be done in accordance with the International Standards on Auditing (ISA), which complies with the requirements of ADB, and this shall be stipulated in the loan agreement.

G. Reporting and Satisfactory MAWR and PMO reports comply with the reporting requirements Monitoring of the MOF, the Ministry of Economy (MOE), and the State Taxation Committee. Acceptable reporting requirements for the proposed PMO and PIUs shall be stipulated in the Loan Agreement between ADB and Government of Uzbekistan.

H. Information Moderate MAWR’s financial system utilizes the 1S Buhgalteriya accounting Systems software supplemented with the use of excel spreadsheets and manual methods. Management and operational units of projects, being implemented under MAWR, use similar accounting software for internal and project operations, as well as financial reporting.

Lahmeyer International in association with InfoCapital Group page 2

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

5. Overall, the FMA rated the performance and capacity of the financial, accounting, and procurement management, reporting and monitoring systems of MAWR as satisfactory in serving as an EA for the Project. However it is noted that MAWR should ensure that the PMO is adequately staffed with efficient and experienced personnel, and that MAWR pays special attention to train project staff in procedural and reporting requirements of ADB as a means to enhance staff professional capacity for the following reasons: (i) the accounting policy and procedures of the PMO is required to be established following both national and ADB regulations, which can be easily accommodated as they are not contradictory; (ii) although competent staff are available, it is difficult to retain staff as their period of employment comes to an end as the will leave to take up alternative employment.

6. The following findings and observations have been prepared in accordance with the FMAQ categories and based on interviews, follow-up consultations and supporting documents. The completed FMAQ questionnaire is included in Attachment 1.

B. Country Issues

7. The successful implementation of large scale projects financed by international financial institutions and the Government is conditional on a favourable political and economic environment in the county. At the project preparation stage, it is essential to conduct a general assessment study in order to identify the possible risks arising from environmental factors and inadequate control mechanisms in the country or organizations responsible for implementation and long-term management of development projects funded by the international financial institutions. The following is the summary of these issues that will influence the implementation of the ABIS Rehabilitation Project:

1 (i) The Law on Budgetary System regulates the budgeting process in Uzbekistan. This law provides the legal basis for preparation, review, approval and execution of the state budget. In case of projects financed jointly with International Financial Institutions (IFI), the PMO is responsible for providing the forecasted project budget for the subsequent year to the MOE for approval in May of the current year. (ii) Government is taking strong measures to transform accounting standards in order to make them consistent with IASs. There is sufficient accounting personnel capacity, provided that they are trained and informed about IASs, contemporary financial management techniques and accounting software. (iii) Internal audit in both the private and public sector is very poor in Uzbekistan. Government ministries and agencies do not have a unit responsible for internal control and audit. CRD of MOF is responsible for internal audit of public sector organizations, but both the scope of its work and its human resources are limited.

1 Law of the Republic of Uzbekistan No. 158-II on Budgetary System dated 14 December 2000 and amended on 23 May 2005

Lahmeyer International in association with InfoCapital Group page 3

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

(iv) In Uzbekistan, the external audit system is being developed based on International Standards on Auditing. External audit is not compulsory for state ministries or agencies. However, Article 1 of the Auditing Law (2000) states that if a certain international agreement signed by the Republic of Uzbekistan lays down rules and regulations other than those contained in the legislation of the Republic of Uzbekistan on audit activity, the former is applicable. Projects financed by IFIs are subject to annual audit by an independent auditor, as long as the loan agreement between the Government and IFIs stipulates this condition. (v) Existing legal and organizational arrangements discussed in CDSR pose considerable risks, and make the public procurement process vulnerable. Institutional and human resources capacity at the level of executing and implementing agencies should be evaluated and possible institutional and procurement arrangements need to be defined at the stage of project appraisal. Procurement of smaller packages should be subject, at least, to International Shopping and National Shopping methods.

C. Executing Agency

8. MAWR will be the Project Executing Agency for the ABIS Rehabilitation Project and have overall responsibility for the Project. A deputy minister under MAWR will be appointed as Project Director and oversee project implementation. MAWR is a ministry of the 2 Government, operated under Regulations approved by the Cabinet of Ministers (COM). In carrying out its activities MAWR is accountable to COM. The Ministry’s organizational arrangements and functions were approved by the same resolution of the COM. MAWR is responsible for overall coordination of the country’s agricultural sector, irrigation and forestry. The Ministry was reorganized in 2003 to fulfil its new roles which now include: (i) formulating agriculture and water policies, (ii) improving and introducing new agricultural and water technologies, and (iii) co-coordinating agencies and service enterprises (either state owned or operating on market based principles). MAWR’s organizational chart and structure of the central administration are included in Attachment 2 and 3, respectively.

9. MAWR is largely a self-financing entity, receiving some funding from the state and contributions from its provincial departments and organizations under its coordination. The current annual budget is around UZS 1.7 billion ($850,000) and it is increased in line with inflation. MAWR has two main functions; support for water resources taking around 35% of its budget and receiving around 35% of its funds from the State, and support for the agricultural sector using 65% of the budget and mostly self-financed from provincial and district contributions. MAWR considers that their current annual allocation is sufficient for their activities.

10. Provincial departments and organizations under MAWR are entitled to receive state budget support. The budget for the O&M of the water sector receives a budget of over $400 million a year. All the procedures regarding their application for budget funds and execution of the budget are coordinated by MAWR.

2 Appendix 5 to the Resolution of the COM of the Government No 290 of 28 June 2003 on Improvement of the Organization of the Activities of the Ministry of Agriculture and Water Resources (amended in 2004)

Lahmeyer International in association with InfoCapital Group page 4

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

11. MAWR is authorized to attract foreign investments to finance projects in the fields of agriculture, irrigation and forestry and MAWR has experience in the rehabilitation, upgrade and management of irrigation infrastructure facilities and projects. For example the Land Improvement Project and the Amu Zang Irrigation Rehabilitation Project funded by ADB, and the Drainage, Irrigation and Wetlands Improvement Project of the World Bank are implemented with MAWR as the EA.

12. Project Management Office. For the implementation of ABIS Rehabilitation Project, a project management office (PMO) will be set up in Tashkent and a PIU in Bukhara to facilitate project implementation prior to disbursement of loan proceeds. The PMO will be responsible for: (i) financial management, (ii) procurement and recruitment of consultants, (iii) preparing the periodic reports; (iv) screening, preparation, and implementation of subprojects; (v) ensuring compliance with ADB and Government environment and social safeguards’ requirements; (vi) monitoring and evaluation; and (iv) coordinating interaction with relevant agencies. The PMO and PIUs will have permanent Uzbek staff supported by national and international specialists. Comprehensive results based monitoring and management will be a critical feature of the PMO.

13. Overall guidance and coordination will be provided by a Project Steering Committee (PSC), to be established by government within six months of loan effectiveness to be chaired by a deputy prime minister. The PSC will comprise representatives from the Cabinet of Ministers (COM), MAWR, Ministry of Finance (MOF), Ministry of Economy (MOE), and the State Committee for Nature Protection (SCNP). The PSC will: (i) provide policy guidance, (ii) review and evaluate Project performance, (iii) review audited accounts, (iv) resolve issues affecting Project implementation as needed, and (v) approve jointly with ADB the subprojects recommended by the PMO. The PSC will meet at least semi-annually.

D. Funds Flow Arrangements

14. The proceeds of the ADB loan will be disbursed according to ADB’s Loan Disbursement Handbook (2012, as amended from time to time). For large scale contracts for consulting services and equipment following ICB procedures, loan funds will be disbursed through direct payment. For civil works following NCB procedures and small expenditures related to the PMO, reimbursement and imprest fund procedures will be applied. For minor goods or services procured at provincial levels payments to suppliers can be done through corresponding PIU.

15. In accordance with ADB’s project implementation guidelines, after loan effectiveness, MAWR will open two imprest accounts, one for each loan (ADF and OCR) at a commercial bank in Uzbekistan acceptable to ADB. These imprest accounts will be established and managed according to ADB’s Loan Disbursement Handbook. Total outstanding advances are not to exceed estimated share of eligible project expenditures to be financed through the imprest account for the next 6 months or 10% of the loan amount, whichever is lower. ADB’s statement of expenditures procedure will be applied when reimbursing eligible project outlays and liquidating and replenishing the imprest accounts for individual payments not exceeding $100,000. As per banking regulations in Uzbekistan, the PMO will be required to establish two bank accounts, one for foreign exchange and second account for local currency. The foreign currency account will be used by PMO as its imprest account.

Lahmeyer International in association with InfoCapital Group page 5

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

16. During the implementation of previous projects, PMOs operating under MAWR faced delays in receiving counterpart funding for settlement of payment requests to contractors and suppliers tendered at the local level. This is related to inappropriate practices of PMOs in sending requests for funds to MOF. It is important to ensure PMO staff are aware of the correct procedures.

17. As is discussed in the CDSR, in line with the state budgeting process the PMO should identify the project expenditure budgeted for in the upcoming year and send it to the MOE (through MAWR) in May of the current year. Later the request for funds will be sent to MOF. With respect to Amu Bukhara Rehabilitation Project, expenditure needs for the upcoming 2013 year were not considered in the state budget for year 2012, since the feasibility study is not yet approved by the COM. Therefore before the loan agreement is finalized, it will be essential to ensure that the budget for project start-up is available for the initial fiscal year.

18. The overall budget for project implementation is included in the Presidential Decree for the Project as an annex, to ensure that sufficient funds are budgeted for each component for each year of implementation.

19. Lending and re-lending arrangements. Since the ABIS Rehabilitation Project is a non-revenue earning project (for MAWR), Government will take the responsibility for repaying the ADB loans. The project beneficiaries are not expected to provide reim- bursement of loans and or to pay for services provided by the project.

20. Management of foreign exchange. MAWR is not greatly experienced in managing foreign exchange risks. MOF needs to be consulted regarding this issue prior to the finalization of loan agreement.

E. Staffing

21. It is proposed that the PMO will be headed by a Project Manager appointed by MAWR and acceptable to ADB. The Project Manager will report to the Project Director. The Project Manager will be supported with national specialists for procurement, financial management, accounting, engineering, social and environmental safeguards, water management, and M&E along with administrative staff. PMO staff will be recruited by the EA using procedures acceptable to ADB. The PMO will be supported by international and national consultants recruited through the Project.

22. To ensure adequate financial and accounting capacity it is proposed to recruit a financial manager and an accountant for the PMO and accountants for the two PIUs who will serve for the duration of the project in the respective locations. In selecting the project financial personnel, special attention will be paid to the experience of the staff with IFIs. Project accounting and finance staff will be trained in ADB procedures. PMO personnel are usually employed on one-year contracts, which are renewed for the subsequent year subject to satisfactory performance of the staff member.

Lahmeyer International in association with InfoCapital Group page 6

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

23. Competent staff are available but it is difficult to retain staff as their period of employment comes to an end as the will leave to take up alternative employment. The cap on the salary rates that can be offered that is imposed by government does restrict the PMO in flexible recruitment and remuneration.

F. Accounting Policies and Procedures

24. MAWR through the PMO will be required to establish financial management and accounting systems for the Project in accordance with Financial Reporting and Auditing of Projects Financed by the ADB. The PMO will also be responsible to maintain project accounts and financial statements.

25. MAWR and its PMO use the accrual method of accounting in their regular and project operations. The accounting system of MAWR, as well as of all state and private legal entities in Uzbekistan, is based on the NAS and the national accounting guidelines of the MOF. As it is practiced in other ADB financed projects, the PMO will develop a project accounting manual in accordance with ADB and MOF requirements. The manual will be updated annually to include project accounting policy changes issued by the MOF. The PMO and PIU follow the procedures stipulated in ADB’s Handbook for Borrowers on the Financial Governance and Management of Investment Projects Financed by the ADB (2003). The Chart of Accounts based on NAS 21, in Attachment 5, will be applied by the PMO.

26. All reports and supporting documents on all transactions will be stored and retained by the project financial manager until documents are inspected by state controlling agencies (District Tax Inspection, MOF), after which documents will be stored in archives.

27. Clear segregation of duties will be implemented at PMO level. The Project Manager is authorized to execute the project transactions while the financial manager and the accountant handles recording of the transactions. Payments are approved and made by the project manager and the financial manager. In order to increase transparency and reduce potential misappropriation the double checking system (i.e. requiring the documents to be signed by two persons) for bank reconciliations has been found to be the best alternative in MAWR, since the number of PMO accounting personnel is limited in the case of non-revenue earning projects.

28. Budgeting System. The Ministry’s and the PMO’s budgeting systems will be separate and follow a clear process. The project’s budgets are to be prepared annually by the PMO manager together with the financial manager and other management staff as appropriate. The budget developed by the PMO sets annual physical and financial targets. The budget is presented to the MOE, which after approval, is submitted to MOF for final approval.

29. During project implementation the actual expenditures are compared with planned budgeted expenditures on a monthly and quarterly basis, and reports on an analysis of variations is prepared. Significant variations in budgeted expenditure need to be approved by the PSC prior to actual expenditure.

Lahmeyer International in association with InfoCapital Group page 7

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

30. Procurement. All ADB-financed procurement of goods, works, and consulting services will follow ADB’s Procurement Guidelines (2007, as amended from time to time). Civil works contracts costing more than $1 million and contracts for supply (and installation) of equipment and materials valued at more than $1 million, will be awarded under international competitive bidding (ICB) while those valued at $1 million or less will be awarded following national competitive bidding (NCB) procedures acceptable to ADB. Equipment and materials packages valued at less than $100,000 will be procured through the shopping mode. The relevant sections of ADB’s Policy on Anticorruption (1998, as amended to date) will be included in all bid documents issued during implementation of the Project.

31. Currently, there are ADB, World Bank and other donor-financed projects under the management and supervision of MAWR. The MAWR has improved its capacity in procurement by participating in these projects and by involving its staff. The Government has established a Tender Commission with an Evaluation Committee. The Evaluation Committee’s membership has several MAWR staff (of the five to seven members, two to three are from MAWR) who take part in decision making for the procurement evaluations. In the Tender Commission, MAWR also has staff participating. By participating in these tenders, MAWR staff have improved their skills in following guidelines for procurement and knowledge of bidding process for international donors. MAWR has established a library of reference materials related to procurement from the various donors.

32. Payments. All project payments are made with payrolls and bank transfers. In accordance with national accounting procedures, instead of invoices, the payroll is stamped (PAID) and assigned an accounting code. Payrolls prepared by the PMO’s accountant are to be checked by the financial manager and the project manager.

33. Cash and Bank. The PMO manager and the financial manager will be the duly authorized signatories to all project-bank transactions. Use of the accounting software “1S Buhgalteriya” (to be installed in the PMO) will allow maintaining the cashbook in a computerized electronic system. Bank reconciliations are to be undertaken at the end of each month, or at any time as necessary.

34. Safeguard over Assets. MAWR and its PMOs have procedures that assure sufficient controls are undertaken over project assets, and safeguards are in place to protect assets from fraud, waste and abuse. An annual physical inventory of all stocks and materials is carried out as required by NAS and the fixed assets inventory is required to be updated every two years. An inventory stock-take is also practiced when the chief accountant or office manager is changed.

G. Internal Audit

35. As it has been described in previous FMAs for MAWR, currently there are no internal audit units in any government ministry or entity in Uzbekistan. MAWR does not have a department for conducting internal audit of either the ministry’s or project operations. Although the PMOs of ongoing projects executed under MAWR prepare monthly, quarterly and annual financial statements to the financial and economic department of the ministry, these are not intended for internal audit purposes.

Lahmeyer International in association with InfoCapital Group page 8

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

36. In Uzbekistan, the Control Revision Department (CRD) of the MOF is the equivalent of a Supreme Audit Institution. This department carries out an internal audit of MAWR, usually every year. However, CRD is mainly concerned with inspecting the compliance of the ministry with budget rules and regulations. CRD does not conduct a “value-for-money” analysis and the department is not involved in identifying gaps in internal control systems and making recommendation on strengthening them, features that are accepted as part and parcel of modern internal audit processes.

H. External Audit

37. Since the state agencies are not required to undergo external auditing, MAWR has not been audited. However, as part of ADB’s conditions PMOs under MAWR are subject to annual external audit. In other ADB financed projects external auditors are selected based on competitive bidding process in accordance with ADB requirements. For the ABIS Rehabilitation Project independent auditors acceptable to ADB will audit the accounts and records yearly to international standards on auditing and in accordance with the provisions of the Loan Agreement and as specified in ADB guidelines. Annual expenditure for an external auditor during project implementation are included in project costs with provision for loan proceeds to finance the services of private auditors and the translation of their reports into English. Terms of reference for external auditor, in accordance with ADB regulations, shall be prepared for the Project after establishment of the PMO.

38. The PMO will have to maintain separate accounts for the Project. Within 6 months of the close of the financial year, certified copies of the audit report, together with the auditor’s opinion, will be submitted by the PMO to the Government and ADB in English. The audit reports will include a management letter and a separate opinion on the use of the imprest accounts and statement of expenditures procedure. The Project is subject to central Government audit by MOF only at project completion, unless any major accountability issue is raised that would warrant carrying it out sooner.

39. The external audit undertaken of MAWR PMOs is carried out in a timely manner and issues and recommendations made by the auditions are implemented promptly where appropriate.

I. Reporting and Monitoring

40. MAWR financial reporting follows the NAS procedures and requirements. The Financial and Economic Department of the Ministry prepares reports on budget execution and internal financial activities. These reports are prepared using the computerized accounting software and spreadsheets following existing templates where necessary. The types of reports prepared and their frequency is presented in Table 2 below.

Lahmeyer International in association with InfoCapital Group page 9

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

Table 2: List of statuary reporting requirements of the MAWR

No Type Frequency

Group 1. Budget Execution

1 Comparative report on budget planning and execution Monthly, Quarterly

2 Report on the inflow and utilization of development funds Quarterly

3 Balance sheet on the implementation of the planned budget Quarterly

Group 2. Internal Financial Activities Balance sheet, Income statement, and Statement of creditors and 1 Quarterly liabilities 2 Cash flow statement Semi-annually Statement of financial and economic condition, Movements in fixed 3 Annually assets, and Statement of movements in equity

41. Project financial statements are prepared using a computerized accounting system and submitted to MAWR, MOE, MOF and ADB on a monthly, quarterly and annual basis. The quarterly project progress reports highlights the physical accom- plishments and financial progress and follow ADB formats. Spreadsheet analysis and reports are prepared to adapt to special and supplementary reporting requirements. Based on previous project implementation experience, MAWR has well established financial management reporting responsibilities that specify the type and requirements for reports to be prepared. MAWR through the PMO will establish financial management and accounting systems for the Project in accordance with Financial Reporting and Auditing of Projects Financed by the ADB. PMO will also be responsible to maintain project accounts and financial statements.

42. MAWR, through the PMO, will submit quarterly and annual reports to ADB. The reports will indicate progress made, problems encountered, steps taken to remedy the problems, and a program of activities along with expected progress during the remainder of the implementation period. The reports will also incorporate project performance monitoring data and all relevant financial data. The reporting system will focus on outcomes, efficiency, and quality and will be consistent with international and local reporting standards, as well as with the design and monitoring framework. MAWR will also provide other reports and information relating to the Project as ADB may reasonably request. Within 6 months of project completion, MAWR will submit a project completion report to ADB that includes information on project implementation, use of both the ADF and OCR loan proceeds, and accomplishments in relation to the Project’s outcome and impact.

43. In general ADB requires the reports listed in the following Table 3 to be prepared by the PMO:

Lahmeyer International in association with InfoCapital Group page 10

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

Table 3: Summary of Required Financial Reports Report Frequency Basis Duration Due date Project expenditures Semi-annual Annual Term of project Every 6 months after forecast commencement of loan project Operation plan Annual Annual 12 months January 10 QP-01 Annual Quarterly 12 months January 10 Project expenditures Monthly, Monthly, Monthly, Monthly report Quarterly, Quarterly, or Quarterly, or Annually Annually Annually Audited annual Annual Annual Annual September 1 of the financial statements subsequent year

J. Information System

44. MAWR uses 1S Buhgalteriya accounting software package that is integrated with the Internet for exchange of information. For complimentary reasons, the PMO should use a similar computerized financial accounting and management system. The system should enable the PMO to: (i) respond to operational and project-related queries pertaining to specific accounts, and (ii) prepare financial reports on the transactions that occurred in the reporting period. The accounting system should be capable of generating financial reports for both external and internal use. For some types of reports PMOs use spreadsheets.

45. The PMO will establish a Project Performance and Monitoring System to monitor the Project’s progress in achieving the planned outputs, outcome, and impact within 6 months of loan effectiveness. An M&E unit will be established in the PMO to measure results and report findings to the Government and ADB. During project inception, a matrix of indicators will be confirmed and baseline data for the agreed indicators will be gathered. The indicator data will be updated every 6 months and reported to stakeholders and the public. During loan review missions, the indicators will be validated and may be modified to reflect Project performance and results more accurately.

K. Conclusions

46. Overall, the FMA rated the performance and capacity of the financial management, reporting and monitoring systems of MAWR as satisfactory in serving as an EA for the Project. However it is noted that MAWR should ensure that the PMO is adequately staffed with efficient and experienced personnel, and that MAWR pays special attention to train project staff in procedural and reporting requirements of ADB as a means to enhance staff professional capacity.

Lahmeyer International in association with InfoCapital Group page 11

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

47. Accounting and financial reporting practices of the PMO under MAWR are found to be reliable. The accounting policy and procedures of the PMO is required to be established following both national and ADB regulations, which can be easily accommodated as they are not contradictory. As the ABIS Rehabilitation Project executed by MAWR is a non-revenue earning project, the number of accounting and financial personnel assigned to PMOs is limited as they are only accounting for expenditure, not receipts. However, the reliability of the accounting documentation will be ensured by the current system of authentication that requires double signatures (i.e. signing by two persons) for the most of the accounting documents. As it is practiced by other PMOs, ABIS Rehabilitation Project financial reporting will be computerized, and it will not necessitate any changes in MAWR’s financial reporting system.

48. It is noted that there is no department within the structure of MAWR responsible for internal audit and that the Ministry has not been audited by external independent auditor, apart from the procedural audits that are required to conduct by MOF. This means that is very important that for projects being implemented under MAWR an external annual audit is carried out in a through and timely way in line with the external donor requirements, as will be the case for the ABIS Rehabilitation Project.

Lahmeyer International in association with InfoCapital Group page 12

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

ATTACHMENT 1: Financial Management Assessment Questionnaire

Topic Response Remarks 1. Implementing Agency 1.1 What is the entity’s legal status / Government Ministry, accountable to the Structure is registration? Cabinet of Ministers of the Republic of attached Uzbekistan 1.2 Has the entity implemented an 1. Land Improvement Project. Financed by 2006 – 2011 externally-financed project in the ADB past (if so, please provide 2004 – 2009 details)? 2. Amu Zang Irrigation Rehabilitation Project. Financed by ABD (US$ 73.2 mln. of total US$100.0 mln.).

3. The Drainage, Irrigation and Wetlands Improvement Project. Financed by World 2003 – 2010 Bank (US$60 mln. of total US$74mln.)

4. The Grain Productivity Improvement Project. Financed by ADB

5. Ak Altin Agricultural Development Project. Financed by ADB

1.3 What are the statutory reporting Group 1: Budget Execution requirements for the entity? Comparative report on budget Monthly / planning and execution Quarterly

Report on the inflow and utilization of Quarterly development funds Balance sheet on the implementation Quarterly of the planned budget

Group 2: Internal Financial Activities Balance sheet, Income statement, and Statement of creditors and liabilities Quarterly Cash flow statement Semi-annually Statement of financial and economic Annually condition, Movements in fixed assets, and Statement of movements in equity

1.4 Is the governing body for the project independent? 1.5 Is the organizational structure Yes appropriate for the needs of the project? 2. Funds Flow Arrangements 2.1 Describe (proposed) project A flow of funds arrangement is proposed. Structural funds flow arrangements, chart is including a chart and explanation attached of the flow of funds from ADB, government and other financiers.

Lahmeyer International in association with InfoCapital Group page 13

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

Topic Response Remarks 2.2 Are the (proposed) Yes arrangements to transfer the proceeds of the loan (from the government / Finance Ministry) to the entity satisfactory? 2.3 What have been the major Delays in receiving counterpart funds from problems in the past in receipt of MOF and delays in project startup. funds by the entity? 2.4 In which bank will the Imprest PMO Imprest Account will be opened in a local Account be opened? bank acceptable to ADB 2.5 Does the (proposed) project Specialists with adequate experience of implementing unit (PIU) have management of disbursements will be experience in the management recruited to PMO and PIUs of disbursements from ADB? 2.7 Does the entity have/need a MAWR does not but the borrower (MOF) has capacity to manage foreign capacity to manage foreign exchange risks exchange risks? 2.8 How are the counterpart funds N/A accessed? 2.9 How are payments made from Government contribution is disbursed the counterpart funds? according to the State Program that is annually approved by the Government resolution 2.10 If part of the project is Yes implemented by communities or NGOs, does the PIU have the necessary reporting and monitoring features built into its systems to track the use of project proceeds by such agencies? 2.11 Are the beneficiaries required to No contribute to project costs? If beneficiaries have an option to contribute in kind (in the form of labour), are proper guidelines formulated to record and value the labour contribution? 3. Staffing 3.1 What is the (proposed) For each operational unit (PMO/PIU) at least organizational structure of the one competent financial specialist will be accounting department? Attach assigned for the duration of the project an organization chart. 3.2 Identify the (proposed) accounts To be prepared in the design stage staff, including job title, responsibilities, educational background and professional experience. Attach job descriptions and CVs of key accounting staff. 3.3 Is the project finance and Refer to 3.1 accounting function staffed adequately?

Lahmeyer International in association with InfoCapital Group page 14

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

Topic Response Remarks 3.4 Is the finance and accounts staff Competent personnel are available. adequately qualified and Financial/accounting personnel with sufficient experienced? qualifications and skill will be recruited 3.5 Is the project accounts and Financial/accounting personnel recruited will finance staff trained in ADB be given special training in ADB procedures as procedures? appropriate. 3.6 What is the duration of the Duration of the contract with PMO/PIU staff is contract with the finance and usually 1 year, renewable subject to accounts staff? satisfactory performance 3.7 Indicate key positions not N/A (no staff have been recruited yet) contracted yet, and the estimated date of appointment. 3.10 Does the project have written TORs have not available but will be prepared position descriptions that clearly at the start of project implementation. define duties, responsibilities, lines of supervision, and limits of authority for all of the officers, managers, and staff? 3.11 At what frequency are personnel N/A transferred? 3.12 What is training policy for the Organization of annual training programs and finance and accounting staff? participating in ADB seminars and workshops. Training in the use of accounting software is also provided by the supplier 4. Accounting Policies and Procedures 4.1 Does the entity have an Yes, 1S Buhgalteriya account software accounting system that allows for the proper recording of For the PMO/PIU a compatible accounting project financial transactions, system using the same software will be including the allocation of established based on regulations and expenditures in accordance with instructions of ADB and MOF the respective components, disbursement categories, and sources of funds? Will the project use the entity accounting system? 4.2 Are controls in place concerning Yes the preparation and approval of transactions, ensuring that all transactions are correctly made and adequately explained? 4.3 Is the chart of accounts NAS 21 is applied. Supplementary paragraphs adequate to properly account for will be added to ensure the compliance with and report on project activities accounting and financial reporting and disbursement categories? requirements of ADB and MOF 4.4 Are cost allocations to the Yes various funding sources made accurately and in accordance with established agreements? 4.5 Are the General Ledger and General ledger and subsidiary ledgers are subsidiary ledgers reconciled verified periodically and in balance?

Lahmeyer International in association with InfoCapital Group page 15

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

Topic Response Remarks 4.6 Are all accounting and Until inspections by state controlling agencies supporting documents retained are carried out accounting documents are kept on a permanent basis in a in the accounting department. Afterwards they defined system that allows are kept in archives. authorized users easy access? Segregation of Duties 4.7 Are the following functional (i) PMO Project Manager responsibilities performed by (ii) PMO Financial Manager different units or persons: (i) (iii) PMO accountant authorization to execute a (iv) Procurement Specialist transaction; (ii) recording of the transaction; and (iii) custody of assets involved in the transaction? 4.8 Are the functions of ordering, Depending on the type of operation these receiving, accounting for, and functions are divided among the Project paying for goods and services Manager, Procurement Specialist, Financial appropriately segregated? Manager and Accountant 4.9 Are bank reconciliations Financial Manager and Project Manager or prepared by someone other than Deputy Project Manager and Accountant make those who make or approve or approve payments. For the bank payments? reconciliations a double checking system is practiced, i.e. signing documents both by accountant and project manager, accountant and office manager, etc. Budgeting System 4.10 Do budgets include physical and Yes financial targets? 4.11 Are budgets prepared for all Yes significant activities in sufficient detail to provide a meaningful tool with which to monitor subsequent performance? 4.12 Are actual expenditures Yes, monthly and quarterly. Based on these, compared to the budget with preparation of interpretation reports is as reasonable frequency, and required explanations required for significant variations from the budget? 4.13 Are approvals for variations from In advance the budget required in advance or after the fact? 4.14 Who is responsible for PMO Project Manager, Financial Manager, preparation and approval of Deputy Director Project Manager and budgets? Accountant with input from the Project Consultants 4.15 Are procedures in place to plan Yes project activities, collect information from the units in charge of the different components, and prepare the budgets?

Lahmeyer International in association with InfoCapital Group page 16

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

Topic Response Remarks 4.16 Are the project plans and Yes budgets of project activities realistic, based on valid assumptions, and developed by knowledgeable individuals? Payments 4.17 Do invoice-processing Yes procedures provide for: (i) Copies of purchase orders and receiving reports to be obtained directly from issuing departments? (ii) Comparison of invoice quantities, prices and terms, with those indicated on the purchase order and with records of goods actually received? (iii) Comparison of invoice quantities with those indicated on the receiving reports? (iv) Checking the accuracy of calculations? 4.18 Are all invoices stamped PAID, According to the national regulations, similar dated, reviewed and approved, procedures are practiced with payrolls, i.e. and clearly marked for account payroll is stamped, reviewed and approved, code assignment? and an accounting code is assigned. 4.19 Do controls exist for the Checked by the Project Director/Project preparation of the payroll and Manager are changes to the payroll properly authorized? Policies And Procedures 4.20 What is the basis of accounting Accrual method is practiced (e.g., cash, accrual)? 4.21 What accounting standards are National Accounting Standards and followed? International Accounting Standards approved by MOF 4.22 Does the project have an It will be utilized from previous ADB projects adequate policies and but adapted to conform with project activities procedures manual to guide activities and ensure staff accountability? 4.23 Is the accounting policy and The EAs accounting policy and procedure procedure manual updated for manual does not need to be updated for the the project activities? project activities 4.24 Do procedures exist to ensure Yes that only authorized persons can alter or establish a new accounting principle, policy or procedure to be used by the entity? 4.25 Are there written policies and Yes procedures covering all routine financial management and related administrative activities?

Lahmeyer International in association with InfoCapital Group page 17

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

Topic Response Remarks 4.26 Do policies and procedures Yes clearly define conflict of interest and related party transactions (real and apparent) and provide safeguards to protect the organization from them? 4.27 Are manuals distributed to Yes appropriate personnel? Cash and Bank 4.28 Indicate names and positions of Project Manager and Financial Manager and in authorized signatories in the the Project Manager’s absence by the Deputy bank accounts. Project Manager and the Accountant 4.29 Does the organization maintain Yes an adequate, up-to-date cashbook, recording receipts and payments? 4.30 Do controls exist for the Yes collection, timely deposit and recording of receipts at each collection location? 4.31 Are bank and cash reconciled on Yes a monthly basis? 4.32 Are all unusual items on the Yes bank reconciliation reviewed and approved by a responsible official? 4.33 Are all receipts deposited on a Yes timely basis? Safeguard over Assets 4.34 Is there a system of adequate Yes safeguards to protect assets from fraud, waste and abuse? 4.35 Are subsidiary records of fixed Yes assets and stocks kept up to date and reconciled with control accounts? 4.36 Are there periodic physical Yes, annually. inventories of fixed assets and For fixed assets – once in 2 years or when the stocks? responsible person (accountant or office manager) is changed 4.37 Are assets sufficiently covered No by insurance policies? Other Offices and Implementing Entities 4.38 Are there any other regional Yes offices or executing entities participating in implementation? 4.39 Has the project established Yes, and will be further developed at the start controls and procedures for flow of implementation of funds, financial information, accountability, and audits in relation to the other offices or entities?

Lahmeyer International in association with InfoCapital Group page 18

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

Topic Response Remarks 4.40 Does information among the Yes different offices/implementing agencies flow in an accurate and timely fashion? 4.41 Are periodic reconciliations Yes, quarterly or as required performed among the different offices/implementing agencies? Other 4.42 Has the project advised Yes employees, beneficiaries and other recipients to whom to report if they suspect fraud, waste or misuse of project resources or property? 5. Internal Audit 5.1 Is there an internal audit No department in the entity? 5.2 What are the qualifications and N/A experience of audit department staff? 5.3 To whom does the internal N/A auditor report? 5.4 Will the internal audit department N/A include the project in its work program? 5.5 Are actions taken on the internal N/A audit findings? 6. External Audit 6.1 Is the entity financial statement MAWR is audited by the MOF on procedural audited regularly by an matters. PMOs under the Ministry are audited independent auditor? Who is the annually by an independent external auditor auditor? 6.2 Are there any delays in audit of No. Issuance dates of auditors reports are set the entity? When are the audit in accordance with external donor institutions’ reports issued? requirements 6.3 Is the audit of the entity Yes conducted according to the International Standards on Auditing? 6.4 Were there any major N/A accountability issues brought out in the audit report of the past three years? 6.5 Will the entity auditor audit the Auditor is selected on tender basis project accounts or will another auditor be appointed to audit the project financial statements? 6.6 Are there any recommendations N/A made by the auditors in prior audit reports or management letters that have not yet been implemented?

Lahmeyer International in association with InfoCapital Group page 19

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

Topic Response Remarks 6.7 Is the project subject to any kind Yes, Control Revision Department of MOF of audit from an independent governmental entity (e.g., the supreme audit institution) in addition to the external audit? 6.8 Has the project prepared No, preparation of terms of reference for the acceptable terms of reference Project’s financial statements audit is expected for an annual project audit? to be prepared after establishment of the PMO. 7. Reporting and Monitoring 7.1 Are financial statements Based on NAS prepared for the entity? In accordance with which accounting standards? 7.2 Are financial statements PMO prepares its own financial statements prepared for the implementing unit? 7.3 What is the frequency of Yes. Depending on the form of report monthly, preparation of financial quarterly, annual statements are prepared. statements? Are the reports prepared in a timely fashion so as to useful to management for decision making? 7.4 Does the reporting system need No to be adapted to report on the project components? 7.5 Does the reporting system have Yes, control is exercised by management and the capacity to link the financial specialists at the PMO and PIUs information with the project's physical progress? If separate systems are used to gather and compile physical data, what controls are in place to reduce the risk that the physical data may not synchronize with the financial data? 7.6 Does the project have Yes established financial management reporting responsibilities that specify what reports are to be prepared, what they are to contain, and how they are to be used? 7.7 Are financial management Yes, for planning, budgeting and decision reports used by management? making purposes 7.8 Do the financial reports compare Yes actual expenditures with budgeted and programmed allocations? 7.9 Are financial reports prepared Yes MAWR uses the 1S Buhgalteriya directly by the automated accounting software system. Financial reports accounting system or are they are also prepared using spreadsheets or prepared by spreadsheets or manually as necessary. For the proposed some other means? PMO, it is recommended to install a similar automated accounting system

Lahmeyer International in association with InfoCapital Group page 20

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

Topic Response Remarks 8. Information Systems 8.1 Is the financial management Yes system computerized? 8.2 Can the system produce the Yes, if necessary the software can be necessary project financial reprogrammed to produce desired reports. reports? 8.3 Is the staff adequately trained to Yes, training is provided in house and by the maintain the system? software supplier. New staff will also receive adequate training to operate the system 8.4 Does the management Yes organization and processing system safeguard the confidentiality, integrity and availability of the data?

Lahmeyer International in association with InfoCapital Group page 21

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

ATTACHMENT 2: Organizational Chart of the Ministry of Agriculture and Water Resources of the Republic of Uzbekistan

Lahmeyer International in association with InfoCapital Group page 22

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

ATTACHMENT 3: Structure of the Central Administration of the Ministry of Agriculture and Water Resources

Lahmeyer International in association with InfoCapital Group page 23

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

ATTACHMENT 4: Flow of Funds and Lending Arrangements

Asian Development Bank

Ministry of Counterpart Finance funding Contractors Suppliers Consultants Executing Agency Consulting and PMO Companies NGOs

Participating BISA, WUA and Water Resource Management Institutions ABMK

ABIS

Subprojects

Flow of funds

PIU: Project Implementation Unit PMO: Project Management Office

Lahmeyer International in association with InfoCapital Group page 24

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

ATTACHMENT 5: Chart of Accounts (National Accounting Standards No. 21)

No of Name of account Type acc PART I LONG-TERM ASSETS Section 1 FIXED ASSETS, INTANGIBLE & OTHER LONG-TERM ASSETS

0100 FIXED ASSETS A 1100 Land 0111 Land Improvements 0112 Long-term Leasehold Improvements 0120 Buildings and Facilities 0130 Machinery and Equipment 0140 Furniture and Office fixtures 0150 Computer equipment and techniques 0160 Vehicles 0170 Draft animals and Livestock 0180 Perennial Plants 0190 Other Fixed Assets 0199 Preserved Fixed Assets 0200 DEPRECIATION OF FIXED ASSETS CA 0211 Depreciation of Land Improvements 0210 Depreciation of Long-term Leasehold Improvements

0220 Depreciation of Buildings and Facilities 0230 Depreciation of Machinery and Equipment 0240 Depreciation of Furniture and Office fixtures 0250 Depreciation of Computer equipment and techniques 0260 Depreciation of Vehicles 0270 Depreciation of Draft Animals 0280 Depreciation of Perennial Plants 0290 Depreciation of Other Fixed Assets 0299 Depreciation of Fixed Assets Received on Long-term Rent

0300 FIXED ASSETS RECEIVED ON LONG-TERM RENT A

0310 Fixed Assets, Received on Long-term Rent 0400 INTANGIBLE ASSETS A 0410 Patents, Licenses and Know-how 0420 Trademarks, Trade signs & Industrial samples 0430 Software 0440 Rights to use land and natural resources 0450 Organization Costs 0460 Franchise fees 0470 Copyrights 0480 Goodwill 0490 Other Intangible Assets 0500 AMORTIZATION OF INTANGIBLE ASSETS CA 0510 Accumulated Amortization - Patents, Licenses and Know-how 0520 Accumulated Amortization - Trademarks, Trade signs & Industrial samples 0530 Accumulated Amortization - Software 0540 Accumulated Amortization - Rights to use land and natural resources

0550 Accumulated Amortization - Organization Costs 0560 Accumulated Amortization - Franchise fees

Lahmeyer International in association with InfoCapital Group page 25

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

No of acc Name of account Type 0570 Accumulated Amortization - Copyrights 0590 Accumulated Amortization - Other Intangible Assets 0600 LONG-TERM INVESTMENTS A 0610 Securities 0620 Investments in Subsidiaries 0630 Investments in Subordinates 0640 Investments in enterprises with foreign capital 0690 Other Long-term Investments 0700 EQUIPMENT TO BE INSTALLED A 0710 Equipment to be installed - Local 0720 Equipment to be installed - Imported 0800 CAPITAL INVESTMENTS A 0810 Work in progress 0820 Acquisition of fixed assets 0830 Acquisition of intangible assets 0840 Formation of main herd 0850 Capital Investments in Land Improvements 0860 Capital Investments in Fixed Assets received on long-term rent 0890 Other Capital investments 0900 LONG-TERM RECEIVABLES AND DEFERRED CHARGES A 0910 Notes Receivable 0920 Long-term Rent Payments Receivable 0930 Personnel Long-term Receivables 0940 Other Long-term Receivables 0950 Deferred income tax on temporary differences 0960 Long-term Deferred Expenses on Discounts 0990 Other Long-term Deferred Expenses PART II CURRENT ASSETS Section 2 INVENTORY 1000 RAW MATERIALS INVENTORY A 1010 Materials 1020 Purchased Semi-finished Goods and Components 1030 Fuel 1040 Spare Parts 1050 Construction Materials 1060 Packaging Materials 1070 Materials for Outside Processing 1080 Inventory and household fixings 1090 Other Materials 1100 ANIMALS FOR BREEDING A 1100 Animals for Growing 1120 Animals for Fattening 1200 1300 1400 1500 PROVISION AND PURCHASE OF MATERIALS 1510 Provision and Purchase of Materials

Lahmeyer International in association with InfoCapital Group page 26

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

No of Typ Name of account acc e

1600 DEVIATION IN COST OF MATERIALS A 1610 Deviation in Cost of Materials 1700 1800 1900 2000 MAIN PRODUCTION WORK IN PROCESS 2010 Main Production Work in Process 2100 TRANSFER OF IN PROCESS INVENTORY A 2110 Transfer of in process inventory 2200 2300 AUXILIARY PRODUCTION IN PROCESS A 2310 Auxiliary Production in Process 2400 2500 GENERAL PRODUCTION EXPENSES 2510 General Production Expenses 2600 DAMAGE IN PRODUCTION 2610 Damage in Production 2700 ATTENDANT ENTERPRISES A 2710 Attendant Enterprises 2800 FINISHED GOODS INVENTORY A 2810 Finished Goods in Warehouse 2820 Finished Goods in Exhibition 2830 Finished Goods submitted to commission 2900 GOODS A 2910 Goods in Warehouse 2920 Goods in Retail Trade 2930 Goods in Exhibition 2940 Items for Rent 2950 Full and Empty packaging 2960 Goods submitted to commission 2970 Goods in Transit 2980 Trading Estimate 2990 Other Goods Section 3 PREPAID EXPENSES AND DEFERRED EXPENSES - CURRENT PORTION

3000 3100 PREPAID EXPENSES A 3110 Prepaid Rent 3120 Prepaid Services 3190 Other Prepayments 3200 DEFERRED EXPENSES A 3210 Deferred income tax on temporary differences 3220 Deferred Expenses on Discounts 3290 Other Deferred Expenses 3300 3400 3500 3600 3700

Lahmeyer International in association with InfoCapital Group page 27

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

3800 No of Typ acc Name of account e 3900 Section 4 RECEIVABLES - CURRENT PORTION 4000 ACCOUNTS RECEIVABLE A 4010 Accounts Receivable form Customers 4020 Notes Receivable

4100 ACCOUNTS RECEIVABLE FROM SUBDIVISIONS, SUBSIDIARIES AND SUBORDINATES A

4110 Accounts Receivable from Subdivisions 4120 Accounts Receivable from Subsidiaries and Subordinates 4200 ADVANCES GIVEN TO PERSONNEL A 4210 Advances given for payroll 4220 Advances given for business-trips 4230 Advances for General Expenses 4290 Other Advances given to personnel 4300 ADVANCES GIVEN TO SUPPLIERS AND CONTRACTORS A 4310 Advances given to suppliers and contractors for inventory 4320 Advances given to suppliers and contractors for long-term assets 4330 Other Advances Given 4400 ADVANCE PAYMENTS TO BUDGET A 4410 Advance payments on taxes and fees to budget

4500 ADVANCE PAYMENTS TO STATE FUNDS FOR SPECIAL PURPOSE AND ON INSURANCE A

4510 Advance payments on insurance 4520 Advance payments to state funds for special purpose 4600 RECEIVABLES FROM FOUNDERS A

4610 Receivables from Founders 4700 RECEIVABLES FROM PERSONNEL ON OTHER TRANSACTIONS A 4710 Receivables for goods on credit 4720 Receivables on loans 4730 Receivables to cover material loss 4790 Receivables on other transactions 4800 OTHER RECEIVABLES A 4810 Long-term Rent Payments Receivable 4820 Short-term Rent Payments Receivables 4830 Interest Receivable 4840 Dividends Receivable 4850 Royalty Receivable 4860 Claims Receivable 4890 Other Receivables 4900 ALLOWANCE FOR DOUBTFUL DEBTS CA 4910 Allowance for Doubtful Debts

Section 5 CASH, SHORT-TERM INVESTMENTS AND OTHER NON-CASH CURRENT ASSETS

5000 CASH A 5010 Cash in national currency 5020 Cash in foreign currency 5100 CASH ON SETTLEMENT ACCOUNT A 5110 Settlement account 5200 CASH IN FOREIGN CURRENCY ACCOUNTS A

Lahmeyer International in association with InfoCapital Group page 28

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

5210 Foreign Currency Accounts Domestic 5220 Foreign Currency Accounts Abroad No of acc Name of account Type 5300 5400 5500 SPECIAL BANK ACCOUNTS A 5510 Letters of Credit 5520 Cash in Checking Account 5530 Other Special Accounts

5600 CASH EQUIVALENTS A 5610 Cash Equivalents 5700 CASH (TRANSFERS) IN TRANSIT A 5710 Cash (Transfers) in Transit 5800 SHORT-TERM INVESTMENTS A 5810 Securities 5830 Short-term loans receivable 5890 Other Current Investments SHORTAGE AND LOSS FROM DETERIORATION OF VALUABLES AND OTHER 5900 CURRENT ASSETS A 5910 Shortage and Loss from deterioration of valuables 5920 Other Current Assets PART III LIABILITIES Section 6 SHORT-TERM LIABILITIES 6000 ACCOUNTS PAYABLE TO SUPPLIERS AND CONTRACTORS L

6010 Accounts Payable to Suppliers and Contractors 6020 Notes Payable ACCOUNTS PAYABLE 6100 L TO SUBDIVISIONS AND SUBORDINATES 6110 Accounts Payable to Subdivisions 6120 Accounts Payable to Subsidiaries and Subordinates 6200 DEFERRED LIABILITIES L 6210 Unearned Discounts CL 6220 Unearned Premiums 6230 Other Unearned Income 6240 Deferred Liabilities on Taxes and Obligatory payments 6250 Liabilities on Income Tax on Temporary Differences 6290 Other Deferred Liabilities 6300 ADVANCES RECEIVED L 6310 Advances Received from Customers 6320 Advances Received from Subscribers to Stock 6390 Other Received Advances 6400 DEBT ON BUDGET PAYMENTS L 6410 Debt on Budget Payments (on types of taxes) INSURANCE DEBT AND DEBT ON PAYMENTS TO STATE FUNDS FOR SPECIAL 6500 L PURPOSE

6510 Insurance Debt 6520 Debt on payments to state funds for special purpose 6600 DEBT TO FOUNDERS L 6610 Dividends Payable 6620 Debt due to leaving founders 6700 SETTLEMENTS WITH PERSONNEL L

Lahmeyer International in association with InfoCapital Group page 29

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

6710 Settlements with Personnel 6720 Escrow Salary

No of Name of account Type acc

6800 SHORT-TERM CREDITS AND LOANS L 6810 Short-term Bank Credits 6820 Short-term Loans 6830 Bonds Payable - non-bank 6840 Notes Payable - non-bank 6900 OTHER PAYABLES L 6910 Short-term Rent Payable 6920 Accrued Interest 6930 Debt on Royalty 6940 Debt on Guaranties 6950 Long-term Liabilities - current portion 6960 Payable on Claims 6970 Debt due to employees 6990 Other Liabilities Section 7 LONG-TERM LIABILITIES 7000 ACCOUNTS PAYABLE TO SUPPLIERS AND CONTRACTORS L 7010 Accounts Payable to Suppliers and Contractors 7020 Notes Payable

7100 LONG-TERM LIABILITIES TO SUBDIVISIONS, SUBSIDIARIES AND SUBORDINATES L

7110 Long-term Liabilities to Subdivisions 7120 Long-term Liabilities to Subsidiaries and Subordinates

7200 DEFERRED LONG-TERM LIABILITIES L 7210 Deferred Discounts 7220 Deferred Premiums 7230 Other Deferred Incomes 7240 Deferred Liabilities on Taxes and Obligatory payments 7250 Deferred Income Tax Liability on temporary differences

7290 Other Deferred Long-term Liabilities 7300 ADVANCES RECEIVED FROM CUSTOMERS - LONG-TERM PORTION L 7310 Advances Received from Customers - long-term portion 7400 7500 7600 7700 7800 LONG-TERM CREDITS AND LOANS L 7810 Long-term bank credits 7820 Long-term Loans 7830 Bonds Payable 7840 Notes Payable 7900 OTHER LONG-TERM LIABILITIES L 7910 Long-term Rent Payable 7920 Other Long-Term Liabilities

Lahmeyer International in association with InfoCapital Group page 30

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

PART IV OWNER'S EQUITY Section 8. CAPITAL, RETAINED EARNINGS AND RESERVES 8000 No of acc Name of account Type 8100 8200 8300 CHARTERED CAPITAL L 8310 Common Stock 8320 Preferred Stock 8430 Donated Capital 8400 ADDITIONAL CAPITAL 8410 Revenues from Issuance 8420 Foreign Exchange difference in forming chartered capital 8500 RESERVE CAPITAL L 8510 Assets Revaluation Adjustment 8520 Reserve Capital fixed by Legislation 8530 Property Received on Gratis 8600 TREASURY STOCK CL 8610 Treasury Stock - Common 8620 Treasury Stock - Preferred 8700 RETAINED EARNINGS (NON-COVERED LOSS) L 8710 Retained Earnings (Non-covered Loss) for Reporting Period 8720 Retained Earnings for Prior Periods (Non-covered Loss) 8800 FUNDS RECEIVED FOR SPECIAL PURPOSES L 8810 Grants 8820 Subsidies 8830 Membership fees 8840 Tax Remissions for special purpose 8890 Other funds received for special purposes 8900 RESERVE OF FUTURE EXPENSES AND PAYMENTS L 8910 Reserve of Future Expenses and Payments

PART V FORMATION AND UTILIZATION OF FINANCIAL RESULTS Section 9. REVENUES AND EXPENSES 9000 REVENUES FROM MAIN BUSINESS T 9010 Revenues from Sale of Finished Goods 9020 Revenues from Sale of Goods 9030 Revenues from Sales of Works and Services 9040 Sales Return CL 9050 Discounts for Customers CL

9100 COST OF GOODS (WORKS, SERVICES) SOLD T

9110 Cost of Finished Goods Sold 9120 Cost of Goods Sold 9130 Cost of Works and Services Sold 9140 Acquisition/Purchase of Inventory in periodical accounting 9150 Inventory Adjustments in periodical accounting 9200 DISPOSAL OF FIXED AND OTHER ASSETS

Lahmeyer International in association with InfoCapital Group page 31

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

9210 Disposal of fixed assets 9220 Disposal of other assets

No of Name of account Type acc 9300 OTHER INCOME FROM MAIN BUSINESS T 9310 Gain from disposal of fixed assets 9320 Gain from disposal of other assets 9330 Paid fines, penalties and forfeits 9340 Income of previous years 9350 Income from short-term rent 9360 Income from writing off payables and depositor debt 9370 Income of attendant enterprises 9380 Financial Donations 9390 Other operating income 9400 PERIOD EXPENSES T 9410 Selling Expenses 9420 Administrative Expenses 9430 Other Operational Expenses 9440 Reporting Period Expenses excluded from taxable base in future

9500 INCOME FROM FINANCIAL ACTIVITY T 9510 Income from Royalty 9520 Income from Dividends 9530 Interest Income 9540 Income from differences in currency exchange (positive) 9550 Income from long-term rent 9560 Income from revaluation of securities 9570 Other Income from Financial Activity 9600 EXPENSES ON FINANCIAL ACTIVITY T 9610 Interest expenses 9620 Foreign Currency Exchange difference losses (negative) 9630 Expenses on Issue and Distribution of Securities 9690 Other Expenses on Financial Activity 9700 EXTRAORDINARY GAIN (LOSS) T 9710 Extraordinary Gain 9720 Extraordinary Loss 9800 UTILIZATION OF PROFIT FOR TAXATION AND FEES T 9810 Income Tax 9820 Fees and other mandatory deductions 9900 INCOME SUMMARY T 9910 Income Summary PART VI OFF-BALANCE ACCOUNTS 001 Fixed Assets on short-term rent (leased) OB 002 Inventory deposited in custody OB 003 Materials received for processing OB 004 Goods taken on commission OB 005 Equipment received for mounting OB 006 Forms under seal OB 007 Written-off bad debts OB 008 Security for debt and payment - received OB

Lahmeyer International in association with InfoCapital Group page 32

InfoCapital Group

Amu Bukhara Irrigation System Rehabilitation Appendix – Financial Management Assessment

009 Security for debt and payment - issued OB 010 Fixed Assets under long-term rent agreement OB 011 Property received under subsidy agreement OB No of Name of account Type acc 012 Expenses excluded from taxable base of the following periods OB 013 Temporary tax remissions (by types) OB 014 Inventory and household fixings in operation OB

Notes:

A - Assets Account CA - Contra Assets Account L - Liability & Owners Equity Account CL - Contra Liability & Owners Equity Account T - Temporary Account OB - Off-Balance Sheet Account

Lahmeyer International in association with InfoCapital Group page 33

InfoCapital Group