Environmental Monitoring Report

# Annual Safeguard Monitoring Report March 2021

Uzbekistan: Horticulture Value Chain Development Project – Additional Financing

Prepared by Diana Rakhimova (UZIAFSA) for the Agency for implementation of projects in the field of agroindustry and food security (UZAIFSA) and the Asian Development Bank.

1 ANNUAL SAFEGUARD MONITORING REPORT

Project Number: 3673-UZB Reporting period: January – December 2020

Republic of : Horticulture Value Chain Development Project – Additional Financing ADB Loan 3673-UZB (COL) (Financed by the ADB’s ordinary capital resources)

Prepared by: Rakhimova Diana, Environmental specialist (UZAIFSA) , Uzbekistan

For: ADB

Agency for implementation of projects in the field of agroindustry and food security (UZAIFSA)

Endorsed by: Gayrat Ganiev (Deputy Director General of UZAIFSA)

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

2 ABBREVIATIONS

ADB Asian Development Bank CAR Capital adequacy ratio

COL Concessional OCR loans

CBU Central Bank of Uzbekistan

ESMS Environmental and social management system

MAWR Ministry of Agriculture and Water Resources

MOF Ministry of Finance

PFI Participating financial institution

PIU Project implementation unit

PMO Project management office

RRA Rural Restructuring Agency

SEE State Environmental Expertise

EIS Environmental Impact Statement

NBU National Bank for foreign economic activity of the Republic of Uzbekistan

Subsidiary Loan Agreement SLA Agency for implementation of projects in the field of UZAIFSA Agroindustry and food security

AF Additional financing

3 Table of Contents

Part I Introduction ...... 5 1.1. Short description of the program ...... 5 1.2 Summary of activities and project progress during the previous 12 months...... 6 1.3 Project organization and environmental management team, including organizational relationships with PFIs, sub-borrowers etc...... 8 Part II Environmental issues ...... 10 2.1. Environmental issues in the previous 12 months...... 10 2.2. The findings and conclusions of the monitoring ...... 12 2.3. Recommendations are required to show how any exceedances will be prevented in the future. 13 Part III: Compliance with ADB’s Social Protection Requirements and ADB’s Prohibited Investment Activities List ...... 14 3.1 Provide assessment on these two sets of requirements...... 14 3.2. A brief description of the taken measures...... 15 Part IV: ESMS operations (for PFIs which are financing B-category subprojects) ...... 16 4.1. A brief description of the effectiveness of the ESMS within 12 months...... 16 4.2 Capacity building activities ...... 17 4.3. Specific data on the following activities is recommended ...... 17 Part V: Conclusion and action plan ...... 18 5.1. Conclusions...... 18 5.2. Action plan for the next reporting period...... 19 Annexes ...... 21 Annex 1: Site photographs Annex 2 : ESMS reports Annex 3: Monitoring checklists/NCR

4 Part I Introduction

1.1. Short description of the program

1. Uzbekistan’s horticultural products are fast becoming the second largest agricultural export commodity group, after cotton. Horticultural export revenues have more than tripled since 2006. Uzbekistan is geographically well positioned to take advantage of the large and growing markets for horticultural products domestically and abroad. Of the 20 million tons of horticultural output in 2016, only 15% was processed. Of the 3 million tons of fruit produced, 69% are consumed fresh, 20% are processed, and 11% are exported, while for the 10 million tons of vegetables, 81.0% are consumed fresh, 11.3% are processed, 4.3% are used for seeds, and 3.4% are exported. There is significant opportunity for improved value addition from increased processing and exports of both fresh and processed products. Meeting quality and food safety requirements of the more stringent export markets remain a challenge.

2. The Government is supporting the subsector in many important ways. It has adopted a special set of policies for the horticulture subsector. An additional 220,000 ha of agricultural lands will be gradually released from cotton and wheat in favor of horticulture and fodder crops by 2021.

3. ADB approved a loan for $154 million Concessional OCR loans (COL) on 25 November 2016 to finance the Project. Loan (3471-UZB) and project agreements were signed on 3 March 2017 and made effective on 28 April 2017. Following rapid disbursement of existing loan, ADB approved on 14 June 2018 an additional financing of $198 million (COL) from ADB’s ordinary capital resources to increase the scope of the project. Subsidiary Loan Agreements were signed between Ministry of Finance, UZAIFSA and seven selected PFIs, to participate in the Project, namely: Asaka Bank, Davr Bank, Ipak Yuli Bank, Ipoteka Bank, National Bank of Uzbekistan, Turon Bank, and Uzpromstroybank. On June 27, 2019 were signed amendments to Subsidiary Loan Agreements for Uzpromstroybank and Turon Bank by increasing the loan amount from unallocated funds.

4. The additional financing project aims to help the Government of Uzbekistan to scale up the existing project’s support to horticulture value chain development in all 12 regions nationwide and in the Republic of Karakalpakstan. It will increase the outreach of PFIs and improve access to market-based bank finance for horticulture enterprises (farmers, agro-processing enterprises, owners and operators of cold storage facilities, and trading and logistics service suppliers). These will include both additional enterprises not financed under the original project (financed by Loan 3471-UZB) and enterprises already financed under the original project to enable them to expand operations.

5. ADB funds may not be applied to the activities described on the ADB Prohibited Investment Activities List (PIAL) set forth in Appendix 5 of the SPS, and the Project Prohibited Investment Activities List.This project is categorized as FI for environment and FI (treated as C) for involuntary resettlement, and indigenous peoples safeguards since there are no indigenous people’s communities in Uzbekistan.

6. The government shall cause each PFI to ensure that the preparation, design construction, implementation, operation, and decommissioning of each qualified subproject comply with (i) all applicable laws and regulations of the government relating to environment, health, and safety; (ii) the Environment Safeguards; and (iii) the ESMS, and any corrective or preventative actions set forth in a Safeguards Monitoring Report

7. PFIs issue sub-loans in US dollars and/or local currency to eligible sub-borrowers (farmers and agricultural enterprisers). Sub-loans will have a tenor of up to 10 years and interest rate 5-6%. The maximum sub-loan size is $5 million.

8. The project has Effective Gender Mainstreaming (EGM) classification. Subprojects financed by 5 PFIs’ shall employ at least 20% female workers. 1.2 Summary of activities and project progress during the previous 12 months

9. As of January 1, 2021, out of USD 198.0 million (Loan-3673), USD 186.9 million has been disbursed to sub-borrowers to finance 182 subprojects including modern cold storage facilities, horticulture product processing, intensive gardens, modern greenhouses, agricultural technologies, packaging and others. Credit line disbursed for the purpose of modern greenhouses creation (USD 142.7 million), processing of horticulture products (USD 22.2 million) and modern refrigeration storages (USD 17.6 million). A few projects were financed to establish enterprises operating in packaging sphere of horticultural products (USD 2.7 million), to purchase agriculture technology (USD 0.6 million) and creation of intensive gardens (USD 1.5 million). Allocations and withdrawals of credit line were done by PFIs as shown in the table 1 below:

Table 1: Summary of activities and project progress during 12 months

WITHDRAWN DISBURSEMENT BALANCE AMOUNT (IN Subproject’s Ammount (in № PFIS (IN MILLION MILLION number million USD) USD) USD ) 1 NBU 6.4 2 6.4 0 2 Asaka bank 40.0 33 40.0 0 3 Uzpromstroyb 32.6 21 32.6 0 ank 4 Ipoteka bank 25.0 20 25 0 5 Ipak Yuli 12.8 4 12.8 0 bank 6 Turonbank 70.0 100 70.0 0 7 Davr bank 1.0 2 0.6 0.4 TOTAL 187.8 182 187.4 0.4

In the framework of the additional financing 3506 new jobs were created, among them 1296 workplaces for females (37%) and 2210 workplaces for males (63%).

10. If we see this amount in terms of regional disbursement, more projects were financed in , Sirdarya and Kashkadarya regions, and credit line was allocated to fewer projects in Karakalpakistan Republic, , , Surkhandarya, Tashkent, , Djizak, Khorezm, and regions as shown in the table below:

6 Table 2: Performance in terms of regions and PFIs are given in the table below: Table 2 № Regions Number of Disbursement % from total subprojects ammount ammount (in million USD) 1 Karakalpakistan 4 2,4 1,3 Republic 2 Andijan 1 3,5 1,9 3 Bukhara 40 50,5 27,0 4 Djizak 9 7,0 3,8 5 Kashkadarya 16 17,5 9,4 6 Navoiy 5 5,6 3,0 7 Namangan 4 6,5 3, 5 8 Samarkand 17 13,0 7,0 9 Sirdarya 19 30,9 16,6 10 Surkhandarya 18 7,5 4,0 11 Tashkent 19 18,2 10 ,0 12 Fergana 9 10,9 5,8 13 Khorezm 21 13,9 7,5 Total 18 2 187.4 100%

11. Since the beginning of the project implementation 182 subprojects were financed, In an environmental respect, as the Project screening demonstrated,157 out of 182 financed projects (86.26%) were assessed as the projects of Category "B", while 25 projects (13.74%) were evaluated as Category “C” projects according to the legislation of Uzbekistan in the field of environmental protection and ADB's requirement. As the results of the project screening evidence, none of the projects belonged to Category “A”. as shown in the table below:

Table 3: Financed sub-loans in this reporting period

Number of sub-loans by environmental categories No PFIs ESMS approval date B C Total 1 JSICB «Ipak Yuli» 24.05.2017 4 - 4 2 PJSCB «DAVR BANK» 15.05.2017 2 1 3 3 JSCB «Turonbank» 25.05.2017 81 19 100 4 JSCB «Asaka bank» 30.05.2017 33 - 33 5 JSCMB «Ipoteka bank» 25.05.2017 19 - 19 National Bank of 6 26.05.2017 2 - 2 Uzbekistan

7 JSCB «Uzpromstroybank» 30.05.2017 16 5 21

Total 157 25 182

12. All subprojects underwent preliminary environmental screening by the PFIs strictly following the Environmental and Social Management System (ESMS) procedures. All 182 projects did not need the development of a Resettlement Action Plan within the scope of the Project.

13. All PFIs have individual contracts with ADB. According to this contract all PFIs– „shall ensure that the preparation, design construction, implementation operation and decommissioning of each Subproject comply with (a) all applicable laws and regulations of the Borrower related to environment, health, and safety; (b) the environmental safeguards and (c) the ESMS and any corrective or preventative actions set forth in a safeguards Monitoring Report”.

14. The State Environmental Expertise (SEE) was carried out for each subproject on the basis of a draft EIS (Environmental Impact Statement) and obtained the approval of the Environmental Conclusions of the State Committee for Ecology and Environmental Protection. Control over observance of the requirements of environmental legislation at the enterprises of each sub-project is assigned to the regional department for ecology and environmental protection (depending on which region and district the particular subproject belongs to). During the monitoring, the PFIs check that each sub 7 borrower meets the requirements of the ESMS in accordance with the national regulations and requirements of ADB.

15. As of December 2020, a preliminary estimate indicates that the project has helped to establish 195,8 hectares (ha) of intensive orchards and 404,3 ha of water- and energy-saving greenhouses; increased refrigerated storage capacity by 35 100 tons (on the basis of one-off single load capacity), post-harvest processing capacity by 97,437 tons, and packaging material manufacture of 7,5 million square meters; and procured 9 units of agricultural machinery. Summary table of activities of Created capacity from disbursed subproject during the reporting period is given in the Table 4.

Table 4. Created capacity from disbursed subproject № Type of investment Unit of measure Capaci ty 1 Modern refrigeration storage Ton 35 100 2 Intense garden Hectare 195,8 3 Processing of horticulture complexes Ton 97 437 4 Modern greenhouse complexes Hectare 404 ,3 5 Manufacture of packing Sq.meter 7,5 million 6 Agriculture machinery and other Pcs. 9

16. According to paragraph (l) of Section 6.01 of the Subsidiary loan agreement, (SLA) PFIs are provided annual reports on the effectiveness of implementation of environmental and social measures. Tables 4 and 5 indicats summaries of extended subloans using ADB funds within the Horticulture Value Chain Development Project (HVCDP).

1.3 Project organization and environmental management team, including organizational relationships with PFIs, sub-borrowers etc.

17. A project management office (PMO) has been set up under the existing organization of Rural Restructuring Agency. According to the Resolution of the Cabinet of Ministers of the Republic of Uzbekistan dated 21.11.2018 №940, the Agency for implementation of projects in the field of agroindustry and food security was established (UZAIFSA) on the base of RRA.

18. The PMO is provided with highly qualified staff and operational costs and it is responsible for monitoring the project implementation, including training, capacity development, and providing technical support to PFIs. In order to save the cost of engaging a large team of consultants for project management and to ensure efficient utilization of the loan fund allocated to project management (estimated at USD 3.0 million). PMO staff included in-house UZAIFSA specialists. The PMO is responsible for overall environmental compliance with the ADB’s Safeguard Policy Statement (2009). Implementation of ESMS to comply with ADB safeguards requirements and environmental national regulations.

19. Environmental specialist is responsible for coordinating and reporting to ADB, advising PFI's on possible environmental issues, coordinating overall environmental monitoring at the project level, and integrating environmental safeguards issues into the curriculum for the agricultural extension program. Environmnetal spesialist is also responsible for identifying training needs for PFI, ensuring that PIAL integrate environmental requirements into bidding documents. In addition, she conducts periodic field trips to subprojects, ensuring that PFI's are committed to their environmental oversight and monitoring responsibilities and overall environmental compliance.

20. These staff members, with the exception of Hamkorbank, will continue implementing additional financing. Each PFI has established a project implementation unit (PIU) under its existing structure to oversee the implementation of the credit line activities at the respective PFI. The project organization chart is in Figure 1.

8 Figure 1: Project Organization Chart

Loan Agreement between ADB and MOF MOF and RRA

CWRD RRA

obligations to monitor implementation of PFI relending

During implementation PFIs submit to ADB through RRA: quarterly progress report; Project Agreements Statement of Utilization of Funds; annual reports on safeguards compliance

Asaka Bank, Davr Bank, Ipak Yuli Bank, Ipoteka Bank,

(Hamkor Bank excluded)

ADB = Asian Development Bank; CWER = Environment, Natural Resources, and Agriculture Division of Central and West Asia Department of ADB; CWRD = Central and West Asia Department of ADB; MOF = Ministry of Finance; PFI = participating financial institution; PIU = project implementation unit; PMO = project management office; and UZAIFSA = Rural Restructuring Agency.

21. All PFIs have an assigned manager of environmental and social measures at full employment responsible for the preparation of annual reports on the environmental and social efficiency of ESMS. All PFIs have an assigned coordinator of environmental and social measures at full employment responsible for the preparation of annual reports on the environmental and social efficiency of ESMS.

22. During this reporting period, there were significant changes in the composition of the Environmental Management team, two banks organized their departments for addressing to ESMS requirements of the projects. Specifically, “Ipoteka Bank” JSCMB developed the Department of Environmental and Social Risk Management, while “Uzpromstroybank” JSCB arranged their department called «Green Banking». Environmental Management Team for the Project is shown in table 5.

9 Table 5: Environmental Management Team for the Project

Na me Org Position Contact (email and/or tel.) [email protected] Diana Rakhimova UZAIFSA Environmental Expert +998 99 8989099

[email protected] Sardor JSICB «Ipak Yuli» ESMS Coordinator (+998-71) 140-6943 Nigmatullaev (+998-71) 140-6900

[email protected] Gayrat Mahmudov PJSCB «DAVR BANK» ESMS Coordinator +998(90) 909 0223

Deputy of the Head of Zuhhridin [email protected] JSCB «Turonbank» Division Coordinator of the Hamraev +99897 1401385 ESMS

[email protected] M.Nurrulaev JSCB «Asaka bank» Head of Department (78) 120 82 96

Head of Department of Bakhtiyor JSCMB «Ipoteka [email protected] Environmental and Social Abdusalomov bank» +9989(71) 150 8930 Risk Management National Bank of [email protected] Obid Rashidov Uzbekistan for Foreign Coordinator of the ESMS +9989(71) 234 1117 Economic Activities

Rakhimjan JSCB Head of department «Green Bakhramov +998 91 4980424 «Uzpromstroybank» Banking».

23. A PFI is responsible for conducting proper pre-investment inspection on prospective subborrowers in accordance with the PFI’s prevailing credit and risk management policies and procedures and following appropriate commercial banking criteria together with past and ongoing environmental performance. In case if such inspection was not undertaken or is not undertaken in with appropriate level of rigor, the subborrower may be required to immediately repay to the PFI any disbursed funds and the PFI to repay such funds to MOF, in accordance with the terms of the SLA.

Part II Environmental issues

2.1. Environmental issues in the previous 12 months.

24. During the reporting period, the monitoring of subprojects was carried out by the UZAIFSA and PFI. UZAIFSA ‘s monitoring department conducts monitoring at the project sites once every six months and PFI specialists who were especially trained and instructed in the framework of monitoring compliance of the Environmental Plan, labor and safety measures. In line with the ESMS monitoring requirements, the credit officer/ESMS coordinator conducts monitoring of environmental issues and risks as part of a general monitoring process every six-month.

25. The PFIs’ quarterly progress reports include the status of compliance with safeguards covenants. Monitoring of environmental legislation compliance at the enterprises of each subproject is assigned to the regional department for ecology and environmental protection. The sub- borrowers are also responsible for their own regular monitoring and compliance. If non- compliances are observed, non-compliance letters are issued to the sub-borrowers with deadlines to close, subject to financial penalties if not complied with. According to monitoring results, the main non-compliances observed were mainly related to health and safety, handling and storage of pesticides and mineral fertilizers, waste management, not using of PPE by workers, non-satisfactory sanitarian conditions for dining facilities, solid and liquid waste, spills, garbage etc. 10

26. During the review mission of the Asian Development Bank, which took place remotely from September 7 to 11, 2020, meetings were held with PFIs and UZAIFSA. The mission discussed with PFIs and UZAIFSA the Environmental and Social Management System (ESMS) implementation via remote meeting on September 8, 2020. The mission made sure that all PFIs established ESMS maintained as part of bank’s overall management system and assigned credit officers as ESMS coordinator. The mission also noted the importance of timely monitoring and capacity building of PFI, which was carried out within the framework of the project Horticulture Value Chain Development Project No. 3471 to verify compliance with the implementation of ESMS. 102 PFI employees participated in the training.

27. In the framework of loan # 3471 a consultant was hired and the PFIs’ capacity building in the implementation of the Environmental and Social Management System (ESMS) was provided. In this regard, the Agency and the consulting company "Eco-Spectri" LLC, hereinafter referred to as the Consultant, signed a contract on December 6, 2019 for consulting services on Compliance review of Environmental and Social Management System (ESMS) implementation; and the training on environmental and social screening and monitoring of sub-projects. Under the terms of the contract, the Consultant conducted training, review and monitoring of sub-projects throughout the Republic, where a selectively 40 sub-projects funded in the framework of the loans 3471 and 3671 were reviewed/verified for compliance with the ESMS. On November 30, 2020, the Consultant presented the final report and the corrective action plan approved by the Asian Development Bank.

28. The subprojects, which were assigned Environmental Category “B”, as per the charged obligation, are monitored at least once in every six months. According to the monitoring reports of PFIs only visual and desktop monitoring are conducted under the subprojects. None of the PFIs monitoring groups owns the equipment to measure the environmental quality indicators. Consequently, the PFI representatives undertake the monitoring only by visualization and exploration of the environmental documents developed within the scope of the subprojects. All inspections are documented in written form (Annex 8, template 3 with images supported - if necessary). Photographs of the site monitoring are given in Annex 1.

29. In case of complaints of the population or other concerned parties, needing the identification of the environmental quality indicators by means of measurements, the relevant unit of “Goskomekologia “provides the required measurements based on the Resolution No. 541 of the Cabinet of Ministers of the Republic of Uzbekistan dated September 07, 2020.

30. All discrepancies observed in the past reporting period during the visit in 2020, have been significantly improved. As the annual reports submitted by PFIs show, there were no complaints filed and no incidents occurred in the implementation phase of the subprojects in 2020 consequently, within the scope of the subprojects, no corrective measures were developed.

31. According to the annual report submitted in 2020, environmental and social monitoring conducted in the framework of sub-projects funded by the PFIs - Ipoteka Bank, Turon Bank, Promstroybank, Asaka bank revealed non-compliance with the requirements that were submitted in writing form to the Beneficiary. The annual reports submitted in 2020 provided in the Annex#2.

32. Consequently, corrective actions were developed. According to monitoring results, the main non- compliances observed were mainly related to health and safety, handling and storage of pesticides and mineral fertilizers waste management, not using of PPE by workers, non- satisfactory sanitarian conditions for dining facilities, solid and liquid waste, spills, garbage etc. Monitoring checklists and a non-compliance report are provided in the Annex #3.

33. During the monitoring by UZAIFSA, supervisory measures were taken to prevent activities sub- projects that cause a negative impact on the environment of such factors as nature protection, labour protection and safety, soil pollution, impact on the soil due to the use of agricultural chemicals, soil salinization, environmental sanitation and dangerous factors of food contamination, waste management and timely removal of industrial and household waste outside 11 the facilities in accordance with the established procedure.

34. The nature and scale of impact on the environment is insignificant and cannot lead the quality of the environment to negative changes. 2.2. The findings and conclusions of the monitoring

35. In the course of monitoring, it was revealed that the heads of all farms have higher or secondary specialized education. Each studied greenhouse farm has an agronomist who conducts all agrotechnical activities for the cultivation of agricultural products. During the conversation, it was identified that the latter have sufficient experience in growing products in greenhouse conditions. Also, some have international experience working in greenhouses. Specialists freely analyze the production process of vegetable crops, operate automated installations, determine the needs of plants during the growing season, carry out preparatory and post-harvest activities. The structure and conditions of growing vegetables are agreed with the companies that supply the seed material and in accordance with the instructions provided by the greenhouse builders.

36. During the visits to the projects with refrigeration storage and processing of horticulture complexes units in February – March of 2020, minor non-compliances were identified, as: garbage in cesspools, safety breach associated with the equipment of working personnel: - LLC «Agrosoy Plast», LLC “Fashion Trend Furniture” - insignificant irregularities were revealed for warehousing and storage of building materials, a household garbage was observed in the project area - “Muzaffar” LLC- on construction stage – Occupational health and safety of workers: were absent workers ' personal protective equipment (helmets, if necessary, masks and goggles, uniforms and protective shoes), Unavailability of environmental documentation (IEE / ESMS) at construction sites; - «Dolina stroy» LLC- breakage in the drainage channel draining water from the freezer.

37. During the visits to greenhouses in September – October of 2020, by UZAIFSA environmental specialisit was observed: - LLC "Almaz Green Valley" LLC, LLC “Azamat Elshod",”Mirfayz Parfyum Invest” LLC - chemicals storages and preparation аге not constructed yet and thеiг handling is not done in full compliance with the safety rulеs; - “Uchkuprik Vegetable Business" LLC, ", Grand Boglari - irregularities were revealed for warehousing and storage of building materials, - LLC «, NRJ Agro centures" - were absent workers ' personal protective equipment (masks and goggles, uniforms and protective shoes) non-satisfactory sanitarian conditions for dining facilities, incorrect storage of building material in the greenhouse.

- LLC “Exim Agro Logistic” LLC «Samarkand Agro Green House» LLC "Barakali Chandler, LLC “Kras Net Servis ”, LLC "Farhona Limonari 1”, LLC “Buri devonbegi” ,LLC ”Sardor Sarbon” LLC “Salomat Suxrob Ziyo Farm”, LLC Zarafshan Grand Boglari, - on construction stage – lack of environmental documentation (IEE / ESMS) at construction sites; in addition, it was requested to add a detailed pest management plan, storage conditions and use of pesticides, chemicals management, experience and skills in the use of pesticides and mineral fertilizers, as well as safety measures plan to the ESIA project.

38. The nature and scale of the environmental impact of all the above non-compliances are insignificant and could be effectively eliminated.

39. Recommendations for solving the above environmental problems are indicated in the paragraph 2.3.

40. Prior to the implementation of any type of activity in the field of horticulture production, ESMS manager of each certain PFI’s informed one by one all beneficiaries of the sub-projects on environmental and technical safety requirements. During the reporting period, any other issues related to noise and vibration, water and air quality have not been identified. There were no any

12 accidents or emergency except a minor disruption. Complaints from nearby residential populations were not received. Environmental inspections are carried out by specialists of the district department for ecology and environmental safeguard in accordance with committee's internal environmental monitoring program.

2.3. Recommendations are required to show how any exceedances will be prevented in the future. 41. UZAIFSA Environmental specialist suggested recommendations for identified deficiencies in the above indicated sub-projects, particularly: - Persons who carry out spraying use minimal or unsafe equipment, although safe equipment may be available. Many knapsack sprayers with plastic pumps start to leak after two to three years, thus creating a risk for people using the sprayers by contaminating their clothing. Therefore, it is very important to use the appropriate protective equipment as well as timely maintenance and repairs. - Disposal of domestic water, water run-offs from hydroponic irrigation of the greenhouse, as well as the remains of storm and rainwater must be carried out properly. That is, the generated excess run-off water should be collected in a waterproof pit in the volume of 5 m3, after which, according to the measures of their accumulation, they are transferred to treatment facilities for their further treatment and waste disposal by specialized organizations. Moreover, it is necessary to provide copies of contracts with appropriete companies. - Contracts with a solid waste disposal company were requested. And also it was requested to indicate the process of collecting them on the territory of the greenhouse area in special containers, before their disposal in special waste disposal sites. - as specified above, a very important issue which requires the subproject beneficiaries and the PFI attention is to improve the efficiency and safety while handling mineral fertilizers and pesticides, in particular fоr greenhouse and orchards subproject. - improve the work on monitoring environmental protection and safety at construction sites and training workers and own personnel on environmental aspects, as well as conducting basic monitoring in accordance with the ZVOS.

- correct all the shortcomings and irregularities made during the work, tidy up collective protective equipment, clean the proper areas of rubbish, provide all workers with personal protective equipment, organize medical kits, equip electrical equipment and fire boards, organize safety and health nooks.

- Keep all floors clean in the premises and prevent fertilizer from being carried by people or machines outside the project site Store each fertilizer in a separate container in a folding room or in a fixed place. The personnel must complete relevant training session or instruction.

- Integrated methods of pest control with the rational use of both chemical and non-chemical methods of control. 42. It was also recommended to carry out activities aimed at ensuring the readiness of the object to actions to prevent, localize and eliminate the consequences of accidents or emergencies. There were instructions, recommendations given to ensure healthy, and safety use of pesticides: - Wearing recommended protective clothing (long-sleeved shirt and trousers, socks, boots and gloves) in order to reduce exposure or skin contact; - Chemically resistant shoes and gloves; Use of safety glasses; Use of approved respirators; - Stand on the windward side when using pesticides; Avoid contact of food with pesticides; - When pouring pesticides, keep the container below eye level to prevent eye contact; - After handling pesticides, wash hands thoroughly with soap before eating or drinking; For all recommendations above have been taken appropriate measures by UZAIFSA and PFIs which are given in Chapter 3.2 13 Part III: Compliance with ADB’s Social Protection Requirements and ADB’s Prohibited Investment Activities List

3.1 Provide assessment on these two sets of requirements.

43. ADB's requirements for social protection were met. According to the list of prohibited types of investment activities, preliminary environmental screenings of social and safeguard measures were carried out. 44. During of the project implementation, PFI specialists conducted a preliminary analysis (screening) of each sub-project with respect to social safeguard measures. 45. Prior to approval, subprojects were screened according to the following questions:

Table 6. Involuntary Resettlement Impact Checklist

Screening Questions Yes No Remarks

1. Will there be land acquisition using eminent domain law? If yes, exclude from financing

2. Will there be permanent or temporary loss of shelter and If yes, exclude from financing. residential land due to land acquisition?

3. Will there be permanent or temporary loss of agricultural If yes, exclude from financing. and other productive assets due to land acquisition?

4. Will there be losses of crops, trees, and fixed assets due to If yes, exclude from financing. land acquisition?

5. Will there be permanent or temporary loss of businesses or If yes, exclude from financing. enterprises due to land acquisition?

6. Will there be permanent or temporary loss of income If yes, exclude from financing. sources and means of livelihoods due to land acquisition?

7. If land or private property is purchased through negotiated settlement or willing buyer-willing seller, will it result in the If yes, exclude from financing. permanent or temporary removal or displacement of renters, or leaseholders?

8. If land or private property is purchased through negotiated settlement or willing buyer-willing seller, will it result in the permanent or temporary removal or displacement of informal If yes, exclude from financing. land-users (people without legal rights on the land) or squatters?

9. Will the project involve any permanent or temporary restrictions in land use or access to legally designated parks or protected areas and cause people or any community to lose If yes, exclude from financing. access to natural resources, traditional habitats, communal land, or communal facilities?

10. Will the project use government land or any public land or property, which will require the permanent or temporary If yes, exclude from financing. removal of informal occupants or users (residential or economic)?

14 46. During the preliminary monitoring at the sub-project areas, all the above questions were answered (NO) confirming the absence of impact caused to Involuntary Resettlement, which in turn does not hamper the financing of sub-projects. 47. PFIs specialists discussed, explained and clarified to the subprojects owners of all the requirements for the environmental and social safeguard that they should comply with during the implementation of the subproject.

3.2. A brief description of the taken measures.

48. During the monitoring conducted by the UZAIFSA and PFI’s in February, September 2020, it was noted that the corrective measures recommended in 2019-2020 were implemented. On the current visit and by the photos submitted from the Beneficiary, the environmental impacts state has significantly improved.

49. All sub-borrowers agreed to keep log book of complaints within the scope of the sub-project. The log book of complaints should include not only written, but also verbal complaints and proposals of the employees and stakeholders.

50. The water consumption in the greenhouse is significantly lower due to the automation of the control and the drip irrigation system. The supply of mineral fertilizers and preparations is also carried out point-by-point, which prevents the abundant flushing of harmful substances into the environment.

51. Management and storage of pesticides. Contamination of soil, groundwater or water sources due to accidental leaks during the transportation, mixing and storage of pesticides can be prevented by following the recommendations for the handling and storage of hazardous materials.

52. During the monitoring of sub-projects, it was recommended for each sub-borrower to have environmental documents such as an EIA, an environmental expert opinion, as well as a developed EMP and a book of complaints for the project area.

53. Below are the measures taken by beneficiaries in order to eliminate the inconsistencies identified during the visit in September -November 2020:

- workers are provided with workwear, shoes and gloves.

- increased the number of garbage bins for waste collection and garbage, as well as the frequency of area cleaning.

- started construction of a separate storage facility for chemicals and minerals.

It was clarified that timely disposal of waste, prevention of littering in the territory of projected objects will prevent negative impact on natural resources: soil, underground horizon.

54. During the reporting period, incidents and accidents were not observed in the project’s areas.

55. In order to minimize environmental and social risks, UZAIFA has been taken appropriate measures to eliminate all non-compliances: - UZAIFSA sent a request to all PFI's to send credit contracts for reviewing all ADB-funded sub- projects for compliance by the client with the conditions for environmental and social safeguard measures that must be provided in the credit contract; - All credit contracts were received and reviewed; - Institutional strengthening of the Banks’ head offices and regional branches by hiring a full- time Manager with education in environmental and protective measures. PFIs need to periodically conduct training sessions for current and new employees involved in meeting the ESMS requirements. - UZAIFSA requested an update the lists of regional employees involved in the implementation 15 of the ESMS. - ESMS coordinators must complete all documents for “B” category sub-projects, documentation and store the considered environmental and social risks, managing them and monitoring process in each sub-borrower’s credit files; - UZAIFSA advised to PFIs Strengthen the complaints mechanism and consultation, closely monitor and address project-specific complains and grievances received from local communities and record acqtions taken to resolve.

Part IV: ESMS operations (for PFIs which are financing B-category subprojects)

4.1. A brief description of the effectiveness of the ESMS within 12 months.

56. According to paragraph 9 of Schedule 4 in Loan agreement between Republic of Uzbekistan and ADB dated 05.11.2018, no withdrawal shall be made from the Loan account for a PFI for the purposes of any qualified subprojects until such PFI has established the ESMS in a manner satisfactory to ADB and has appointed designated staff who is capable and adequately trained in fully implementing the ESMS.

57. For each sub-project, a State Environmental Expertise (SEE) was carried out on the basis of a draft Environmental Impact Statement (EIS) and obtained approval Environmental Conclusions of the State Committee for Ecology and Environmental Protection. Control over observance of the requirements of environmental legislation at the enterprises of each sub-project is assigned to the regional department for ecology and environmental protection (depending on which region and district the particular subproject belongs to).

58. During the monitoring, the PFIs check that each sub borrower meets the requirements of the ESMS in accordance with the national regulations and requirements of ADB.

59. During the project implementation period, none of the PFIs did face significant environmental problems for each sub-project. There were no exceedances in the frame of established norms for the current subprojects.

60. ADB's requirements for social protection were met. According to the list of prohibited types of investment activities, a preliminary screening of social safeguard measures were carried out. All requirements are implemented based on the documents of the ESMS. Implementation of corrective actions was not required.

61. Guided by the agreement on the refinancing of part of the ADB loan, Article VI, Section 6.01, paragraph (l) of the PFIs provided annual reports on the effectiveness of the implementation of environmental and social measures. In this report, the information should be provided by PFIs and responsible persons for the implementation of the ESMS.

62. At the end of January 2020 and the beginning of February 2021, all PFIs provided to UZAIFSA annual reports on the effectiveness of environmental and social measures implementation. Based on the analysis of the submitted reports, it can be seen that the process of subprojects reviews and approval was carried out in accordance with the national legal and normative acts of the Republic of Uzbekistan. The risk categorization was implemented on the base of the screening for the presence of environmental and social risks under the legislation of the Republic of Uzbekistan and ADB requirements.

63. All subprojects with category "B" passed pre-investment monitoring. Monitoring of environmental safeguard and social issues in the framework of sub loans was implemented particularly on a bi- annual basis by the Bank staff. Please see the Annex 2. PFIs provided annual reports on the effectiveness of the implementation of environmental and social measures.

16 64. All discrepancies observed in the past reporting period during the visit in 2020, have been significantly improved. As the annual reports submitted by PFIs show, there were no complaints filed and no incidents occurred in the implementation phase of the subprojects in 2020 consequently, within the scope of the subprojects, no corrective measures were developed

65. No issues related to social safeguard measures (land acquisition, individual’s/commercials displacement, loss of income/livelihood) were observed.

4.2 Capacity building activities

66. In order to increase the capacity, training sessions were organized in the framework of the project: - presentation for PFI’s on the implementation of environmental management and social issues was conducted by ADB Technical consultant Armine Yedigaryan, (December 10, 2018);

67. Within the framework of the “Horticulture Value Chain Development #3471” project, In December 2019 AIFSA recruited the consulting firm for compliance review of ESMS implementation and capacity building trainings. The contract period was originally for 4 months and included random review of 40 sub-projects and trainings in 5 provinces (Andijan, Samarkand, Bukhara, Khorezm and Tashkent). The main goal of the project was to train environmental and social professionals of PFIs in: (i) environmental and social screening, (ii) preparation and implementation of environmental and social monitoring; (iii) registration of non-compliances and preparation of corrective actions; and (iv) preparation of semi-annual and annual reports.

68. The Consultant conducted 40 sub-project monitoring reviews and 3 two-day training sessions in the Bukhara, Andijan, and Samarkand regions, for PFI staff. The Consultant provided video training programs which were sent to all PFIs for further use.

69. Before commencement of training in each country, the project implementation team held initial briefing meetings with the representatives of PFIs so as to have a common understanding of the objectives of the assignment as well as agreeing on the participants to be involved in the training, the grouping of participants, the detailed scheduling of training, and the expected outcomes.

70. Based on the results of the training seminars' analysis, it was found that the PFIs demonstrated a high level of interest towards the existing problems of environmental safeguard and they also indicated the importance of the knowledge gained during the training seminars to improve the quality and quantity of agricultural production, as well as safety in the storage and use of pesticides.

71. PFIs periodically conduct training sessions for current and new employees involved in meeting the ESMS requirements.

72. UZAIFSA, in the collaboration with the ADB, is continuously building the capacity of the PFIs on environmental issues. So, in March 2020 training seminars were held in the framework of the new project "Livestock Value Chain Development Project" on the topic "Implementation of the environmental and social management system in the bank's credit cycle". Seminars were attended by such banks as JSCB Turonbank, JSCB Uzpromstroybank, JSCMB Ipoteka bank and etc.

4.3. Specific data on the following activities is recommended

Site inspections and audits – to summarize the number and type of site visits.

73. Monitoring was carried out on a half-yearly basis during a year. Audits by the banks were 17 conducted in January Fabruary March, September, October, December, of the reporting period, and the UZAIFSA implemented it in, February, March, September, October and December. Totally 98 financed sub projects have been inspected out of 182.Monitoring of remained and newly financed projects will be conducted in the next reporting period.

74. Prior to the implementation of any type of activity in the field of horticulture production, all beneficiaries of subprojects were aware of environmental and technical safety requirements. To the present day, problems related to noise and vibration, water and air quality have not been identified. There were no any accidents or emergency situation. During the monitoring, the PFIs also checked the current environmental state of the sub- projects. Noncompliance case.

75. Some non-compliance was observed during site visits. Among them: untimely disposal of wastes from construction sites, non-satisfactory sanitarian conditions for dining facilities, not using PPE by workers, solid and liquid waste, spills, garbage, after being notified, all non-compliances were eliminated. Each subproject was provided with the recommendations on methods of storing waste and observing safety regulations. Corrective action plans.

76. Issues were identified in respect of environmental protection and safety during the monitoring of the subprojects using pesticides or fertilizers in the production cycle. The procedures to store, use and neutralize the pesticides and fertilizers were violated. During the monitoring of subprojects, could not record environmental documents (IEE/ZVOS, ESMS or inspection reports) at the construction or production site; it was recommended for each sub-borrower to have environmental documents for the project area.

77. Most of the subprojects have no a grievance log book on the construction and production sites. Consultation and complaints.

78. Prior to the financing of each subproject, the PFI specialist consulted the beneficiaries about the environmental and social requirements of ADB. In this, regard no complaint was received. Part V: Conclusion and action plan 5.1. Conclusions.

79. The annual report on the monitoring of safeguard measures of the project provided information on the implementation of the project in the field of development of the value chain in the horticulture sector (additional financing). Based on the PFI data, it can be concluded that the project helped to increase the productivity of farming activities, increase the processing and storage capacity and reduce post-harvest losses due to the implementation and improvement of intensive gardening practices, modern and efficient greenhouses and processing, storage and refrigeration capacities. PFIs have expanded the coverage of farmers and enterprises, 182 subprojects were financed during the entire project period, while in the reporting period - there were 28 subprojects financed. Each sub-project was carried out by SEE based on the developed draft EIS and agreed Environmental Conclusions of the State Committee for Ecology and Environmental Protection.

80. PFIs provided annual reports to UZAIFSA on the effectiveness of environmental and social measures. The received annual reports on the implementation of the ESMS from the PFIs for 2020 were analyzed and examined for compliance with the list of prohibited investment activities of the ADB (PIAL), the selection, classification and verification procedure; the organizational structure and staffing, including skills and knowledge in the environmental and social sphere; the existence of an Environmental Management Plan; the Grievance Mechanism and Monitoring 18 checklists.

81. The issues of applying mineral fertilizers and pest management have a direct impact on the environment, on farmer’s health as well as on the quality of agricultural products. It is important that PFI requires the beneficiary documents all necessary documentation in line with the project documents and ESMS.

82. At the observance of the rules of safety and sanitary-hygienic conditions, there will be no significant impact on the environment.

83. Additional funding has strengthened the impact of the existing project and further increased farm productivity, improved processing and storage capacity, and reduced post-harvest losses by upgrading and creating intensive gardens; modern and efficient greenhouses; and processing, storage, and cooling equipment. This, in turn, contributes to long-term economic and environmental sustainability and increased further farm productivity.

84. Greenhouses allow you to grow all kinds of fruits and vegetables several times a year, regardless of the time of year and season. In greenhouses, the level of humidity and lighting is controlled, which allows you to harvest almost all year round.

85. Thus, compliance with the policies and procedures of the ESMS will lead to long-term of economic and environmental sustainability and increased profitability for farmers and agribusinesses.

86. The nature and scale of impact on the environment is insignificant and cannot lead the quality of the environment to negative changes.

5.2. Action plan for the next reporting period.

87. Compliance of the PFIs to project agreement covenants is monitored through periodic ADB review missions, quarterly progress reports by the PFIs, random spot checks of subloan documents, and review of the PFIs' audited financial statements. An environmental specialist hired by the PMO (based in UZAIFSA) will help monitor PFIs’ training and carry out monitoring site visits, also assist to PFIs in the implementation of ESMS, including the preparation of Annual Environmental and Social (ES) performance reports of the PFIs and ensure on-time completion of the annual report on ESMS. If necessary, will assist to PFIs and beneficiaries of environmental and social issues. See table 7 below.

19 Table 7: The monitoring action plan of the UZAIFSA Environmental Specialist

№ Region May May April April March March August August October October January January December December November November 1 Karakalpakistan Republic 2 Khorezm 3 Bukhara 4 Navoiy 5 Kashkadarya 6 Surkhandarya 7 Namangan 8 Andijan 9 Fergana 10 Samarkand 11 12 Syrdarya 13 Tashkent region

UZAIFSA specialist will carry out monitoring according to the ESMS during the next reporting period March 2021 – December 2021

20 Annexes Please see the Annex (Annual ESMS performance reports by PFIs.

21 ANNEX 2 Table 8: Information on all loans

JSCB “IPOTEKA BANK”

funds category Safeguard Safeguard using ADBusing Subpro-ject Subpro-ject Industry Industry Sector* IP IR IR Name of Name Subproject Env Tenor ofloan Tenor (months) Value ofValueexposure (US$) (yes/no) and IR and IPand issues IR and during taken theto address issues reporting reporting periodand actions Any outstandingAny environmental Type ofType loan SME/ trade finance) AGRO TRADE LLC credit 83 5,000.0 greenhouse B C N/A no Yes ISLOMBEK - AGRO - SERVIS LLC credit 120 5,000.0 greenhouse B C N/A no Yes Kesh Nur Makoni LLC credit 85 700.0 greenhouse B C N/A no Yes "ABLAQUL QODIR SHARIF AGRO" LLC credit 60 75.0 cold storages B C N/A no Yes "SAMARQAND AGRO GREEN HOUSE" LLC credit 84 500.0 greenhouse B C N/A no Yes "DIAMOND ORIGINAL" LLC credit 85 249.6 cold storages B C N/A no Yes "Samir Nuri Zamin" LLC credit 60 100.0 cold storages B C N/A no Yes "Surxon Fruits Frezer" LLC credit 61 500.0 cold storages B C N/A no Yes Istiqlol LLC credit 85 330.0 cold storages B C N/A no Yes NOZIMA FAYZ LLC credit 85 381.0 greenhouse B C N/A no Yes XITOY TULPORI LLC credit 85 420.0 greenhouse B C N/A no Yes RUSLANBEK MO'MINJON LLC credit 85 620.0 greenhouse B C N/A no Yes BOBOXON ALIJON LLC credit 85 420.0 greenhouse B C N/A no Yes DILOBAR MUXLISA LLC credit 83 380.0 greenhouse B C N/A no Yes ALMAZ GREEN VALLEY LLC credit 97 2,164.2 greenhouse B C N/A no Yes PROVENT AIRCOOL ENGINEERING LLC credit 60 130.0 cold storages B C N/A no Yes to produce nonalcohol beverages "RICOMEL BEVERAGES" LLC credit 85 2,070.0 B C N/A no Yes from fruits 22 Shohjahon Ibroxim LLC credit 84 440.0 greenhouse B C N/A no Yes Exim agro logistic LLC credit 84 440.0 greenhouse B C N/A no Yes Piskent mega omega LLC credit 84 440.0 greenhouse B C N/A no Yes

23

JSCB “UZPROMSTROYBANK LLC "Farm Agroimpeks" MSB 84 2 773,05 Fruits and vegetables growing B C N/A No Yes LLC "Agrosoy Plast" MSB 84 2 162,0 Fruits and vegetables growing (Cold storages) B C N/A No Yes LLC "Amirtepa texnik servis" MSB 84 1 320,0 Fruits and vegetables growing B C N/A No Yes LLC "Bukha ra gold favorit" MSB 84 1 320,0 Fruits and vegetables growing B C N/A No Yes Farm “Inom” MSB 84 345,0 Creating an intensive garden B C N/A No Yes LLC" Oil" MSB 84 100,0 Butter production B C N/A No Yes LLC “Mirfayz Parfyum” MSB 84 1 500,0 Fru its and vegetables growing B C N/A No Yes LLC "Agro Generous Profusion" MSB 84 1 200,0 Fruits and vegetables growing B C N/A No Yes LLC "Servis Excellence in action" MSB 84 1 320,0 Fruits and vegetables growing B C N/A No Yes JV LLC “Uz -Segang” MSB 84 599,1 Fruits and vegetables growing B C N/A No Yes LLC"Murodbek Shakhrizoda Agro MSB 84 520,0 Fruits and vegetables growing B C N/A No Yes Invest" LLC "Bekhara Mega Gold" MSB 84 4 200,0 Fruits and vegetables growing B C N/A No Yes LLC "Ali Murod Sher Savdo" MSB 84 1 200,0 Fruits and vegetables growing B C N/A No Yes LLC "Nozim Kozim" MSB 84 600,0 Fruits and vegetables growing B C N/A No Yes LLC "Elnazar Shernazar" MSB 84 613,8 Fruits and vegetables growing B C N/A No Yes LLC "Toshkent Ta’mir Temir Beton" MSB 84 3 080,0 Fruits and vegetables growing B C N/A No Yes Organization of a logistics center (processing JV LLC “Uz-Segang” MSB 84 2 279,8 B C N/A No Yes and storage of agricultural products) LLC "Mega Ziroat" MSB 84 3 500,0 Fruits and vegetables growing B C N/A No Yes LLC «Uchko'prik Vegetables business" MSB 84 1 200,00 Greenhouse B C N/A No Yes LLC "Sherobod Anor Impex MSB 84 985,16 Greenhouse B C N/A No Yes Melon cultivation and processing cluster LLC "Muzaffar" MSB 72 1 750,00 B C N/A No Yes organizations JSCB “ASAKA BANK” LLC "Accent Way Tading" credit 84 489,7 Procecing B c N/A No Yes ЧФ "Qudrat Baraka" credit 84 2700,0 Packing B c N/A No Yes LLC "Universal Euro Food Trading" credit 84 2580,0 Greenhouse B c N/A No Yes LLC "Zero Fax" credit 72 450,0 Greenhouse B c N/A No Yes LLC "Kasmetik Ta'mir" credit 84 450,0 Greenhouse B c N/A No Yes LLC "Ibrohimjon Muhammadamin credit 84 410,0 Greenhouse B c N/A No Yes Baraka" LLC «Oltin Voha Gidroponika" credit 84 500,0 Greenhouse B c N/A No Yes LLC "Bukhara Gold" credit 84 2000,0 Greenhouse B c N/A No Yes LLC "Lider Invest Millenium" credit 84 1400,0 Greenhouse B c N/A No Yes LLC "Qashqadaryo Parnik Taraqqiyot credit 84 5000,0 Greenhouse B c N/A No Yes Invest" LLC "Dolina Stroy" credit 84 2,200,0 Greenhouse B c N/A No Yes LLC "Inshoot Turxoll Agro" credit 84 1200,0 Greenhouse B c N/A No Yes 24 LLC «Bukhara Best Greenhouse" credit 84 550,0 Greenhouse B c N/A No Yes LLC"Sardor Sarbon" credit 84 400,0 Greenhouse B c N/A No Yes LLC «Murod Bobo Jasur" credit 84 760,0 Greenhouse B c N/A No Yes LLC "Salomat Suxrob Ziyo Farm" credit 84 400,0 Greenhouse B c N/A No Yes LLC «Al Samo Nur" credit 84 750,0 Greenhouse B c N/A No Yes LLC «Asadbek G'isht sanoati" credit 84 1 200,0 Greenhouse B c N/A No Yes LLC «BUXARA PROF STROY credit 84 640,0 Greenhouse B c N/A No Yes STANDART" LLC «Greenhouse Company" credit 84 4892,0 Greenhouse B c N/A No Yes LLC «Universal Agrotex Servis" credit 84 1397,2 Greenhouse B c N/A No Yes LLC «-Agrozamini" credit 84 1,400,0 Greenhouse B c N/A No Yes LLC "Agro Mega City" credit 84 900,0 Greenhouse B c N/A No Yes ФХ "Nigina Bektosh Bog'i" credit 84 1008,0 Greenhouse B c N/A No Yes ФХ "Xayit Chori Zamini" credit 84 4000,0 Greenhouse B c N/A No Yes ЧП "Qoraqosh Greenhouse" credit 84 358,0 Greenhouse B c N/A No Yes LLC Yug Sever Story credit 84 800,0 Greenhouse B c N/A No Yes ФX "Dostonbek Dilshodbek Zamini" credit 84 520,0 Greenhouse B c N/A No Yes LLC "Aslonobod Plyus" credit 84 1285,0 Greenhouse B c N/A No Yes LLC «Akbarshox Mironshox Bobirshox" credit 84 650,0 Greenhouse B c N/A No Yes LLC” Azamat Elshod” credit 84 500,0 Greenhouse B c N/A No Yes LLC “Everest Green House” credit 84 900,0 Greenhouse B c N/A No Yes LLC «NRJ Agro centure" credit 84 900,0 Greenhouse B c N/A No Yes PJSCB “DAVR BANK” Small 36 "Shah Polan" LLC Busin 156 000.0 Packing B C N/A No Yes months ess

Small Greenhouse 48 “Sendrillion” LLC Busin 89 650.0 B C N/A No Yes months ess Small 60 “Eco Fresh Fruit” LLC Busin 499 000.0 Orchard B C N/A No Yes months ess JSCB “Turonbank ” longt Processing of LLC "O'ZMATBAA TA'MINOT" erm. 84 1,705 agricultural C C N/A No Yes credit products JV LLC "JIANSHENG longt INTERNATIONAL AGRICULTURAL erm. 84 1,000 Greenhouse В C N/A No Yes TECHNOLOGY" credit longt LLC "ZARAFSHON GRAND BOҒLARI" 84 2,065 Greenhouse В C N/A No Yes erm. 25 credit longt FK "MARD ZHALOLIDDIN" erm. 84 460 Greenhouse В C N/A No Yes credit longt LLC "METIN TEXTILES" erm. 84 1 198 cold storages C C N/A No Yes credit longt LLC "SHIRIN NIYAT BARAKA" erm. 84 4,500 cold storages В C N/A No Yes credit longt LLC "BEST VEG" erm. 84 3,494 Processing of agricultural products В C N/A No Yes credit longt Processing of LLC "SAMARҚAND MEVALARI" erm. 84 950 agricultural C C N/A No Yes credit products longt Processing of JV LLC "SAMAR K AND GARDEN erm. 84 345 agricultural C C N/A No Yes PLAST" credit products longt LLC "CHANDLER INTENSIV BOG'I" erm. 84 109 Garden C C N/A No Yes credit longt LLC "ZIYO FRUITS WORLD" erm. 84 92 Garden C C N/A No Yes credit longt FH "BOBON SARKOR" erm. 84 880 Greenhouse В C N/A No Yes credit longt LLC "KESH GLOBAL STROY SERVIS" erm. 84 300 Greenhouse B C N/A No Yes credit longt LLC "KESH-AZIZ-SHIFO" erm. 84 200 Greenhouse B C N/A No Yes credit longt LLC "ҚЎ SH ҲOVUZ" erm. 84 2,500 Greenhouse В C N/A No Yes credit longt LLC "ASIA AGRO PRODUCTS" erm. 84 500 cold storages C C N/A No Yes credit LLC "SAPAR BOBO NABIRASI longt 84 1,300 Greenhouse В C N/A No Yes 26 ZHAVOHIR" erm. credit longt LLC "EXPRESS TEMIR-BETON erm. 84 1,000 Greenhouse В C N/A No Yes SERVICE" credit longt LLC "KUDEKOV ZHADIGER erm. 84 270 Greenhouse В C N/A No Yes SAPARABAEVICH" credit longt LLC "ETI HAZINA MOZHIZASI" erm. 84 400 Greenhouse В C N/A No Yes credit longt LLC "BANOAZ TEXTILES" erm. 84 350 Greenhouse В C N/A No Yes credit longt LLC "FARҒONA LIMONLARI-1" erm. 84 950 Greenhouse В C N/A No Yes credit longt OOO "VALI AGRO" erm. 84 840 Cold storages C C N/A No Yes credit longt FH "VODIY AGRO COMPLEX " erm. 84 520 Greenhouse В C N/A No Yes credit longt JV LLC "BULUNGUR-SANDVIK" erm. 84 807 Processing of agricultural products C C N/A No Yes credit longt LLC "DRIED INGREDIENTS" erm. 84 924 Processing of agricultural products C C N/A No Yes credit longt LLC " BЎRI DEVONBEGI" erm. 84 400 Greenhouse В C N/A No Yes credit longt LLC "BULUNҒUR MEVA-SABZAVOT" erm. 84 932 Cold storages C C N/A No Yes credit longt LLC "SHERKHON OIL" erm. 84 490 Greenhouse В C N/A No Yes credit longt LLC "ARKO STYIL" erm. 84 126 Garden C C N/A No Yes credit 27 longt ФХ "ADIZBOBO" erm. 84 628 Greenhouse В C N/A No Yes credit longt LLC "BUXORO INTERKONTINENTAL" erm. 84 840 Greenhouse В C N/A No Yes credit longt LLC "BUYUK SHER" erm. 84 fifty Greenhouse B C N/A No Yes credit longt LLC " TOZA URUG ' NASLLI CHORVA erm. 84 600 Greenhouse B C N/A No Yes " credit longt LLC " YANGI HAYOT CHORVA erm. 84 300 Greenhouse В C N/A No Yes INVEST" credit longt PE “ULUG'OBOD IXLOS BARAKA” erm. 84 1,500 Greenhouse В C N/A No Yes credit longt PE “HUSEYN UNIVERSAL HAMKOR” erm. 84 1,500 Greenhouse В C N/A No Yes credit longt PE “VOHIDJON UNIVERSAL erm. 84 1,500 Greenhouse В C N/A No Yes HAMKOR” credit longt PE “BUNYODKORBEK UNIVERSAL erm. 84 1,500 Greenhouse В C N/A No Yes HAMKOR” credit longt PE " JAGUAR" erm. 84 130 Greenhouse В C N/A No Yes credit longt PE "OYDIN OKHUNOVNA" erm. 84 130 Greenhouse В C N/A No Yes credit longt PE "SUNNATILLO HAMKOR FAYZ" erm. 84 600 Greenhouse В C N/A No Yes credit longt LLC "MARGILON GAZAVTOMATIKA" erm. 84 2,500 Greenhouse В C N/A No Yes credit longt LLC "GO'ZAL BOG'LAR NA'MUNASI" 84 48 Garden C C N/A No Yes erm. 28 credit longt LLC "JEYNOV MEBEL GOLD" erm. 84 100 Greenhouse В C N/A No Yes credit longt LLC “VIT-XIM-MED” erm. 84 130 Greenhouse В C N/A No Yes credit longt LLC "NARPAY XOSILBEK AGRO" erm. 84 330 Greenhouse В C N/A No Yes credit longt LLC "FAR YOZ INNOVATSIYA" erm. 84 297 Greenhouse В C N/A No Yes credit longt PE "ILHOMJON UNIVERSAL erm. 84 1,500 Greenhouse В C N/A No Yes HAMKOR" credit longt PE "OTABEK UNIVERSAL HAMKOR" erm. 84 1,500 Greenhouse В C N/A No Yes credit longt PE "SAYHUN HAMKOR BIZNES" erm. 84 1,500 Greenhouse В C N/A No Yes credit longt PE "MUHIDDIN SIFAT BARAKA" erm. 84 1,500 Greenhouse В C N/A No Yes credit longt PE "MURODJON IXLOS BARAKA" erm. 84 1,500 Greenhouse B C N/A No Yes credit longt LLC "AGRO SAVDO URGANCH" erm. 84 600 Greenhouse B C N/A No Yes credit longt PE "QORAQOSH SAVDO INVEST" erm. 84 298 Greenhouse В C N/A No Yes credit longt LLC "ZILOLA ZUFAR AGRO" erm. 84 259 Greenhouse В C N/A No Yes credit longt LLC "LIMO LAYM" erm. 84 90,0 Greenhouse В C N/A No Yes credit LLC "JOMBOY GOLDEN FRUITS" longt 84 1,040 Greenhouse C C N/A No Yes 29 erm. credit longt LLC "MIRAXIMOV MIRBOSIT erm. 84 500,0 Greenhouse B C N/A No Yes MIRISHKOR INVEST" credit long LLC "ZAMIN AGRO EXPERT" 60 753,0 Greenhouse B C N/A No Yes сredit long LLC "MARGILON GAZAVTOMATIKA" 84 2 500,0 Greenhouse B C N/A No Yes сredit LLC "TO'RAQO'RG'ON SHIRINLIK long 84 834,5 Greenhouse B C N/A No Yes AGRO" сredit long LLC "EAST-WEST SURXON" 84 312,4 Greenhouse B C N/A No Yes сredit long LLC "ZIYO FRUITS WORLD" 84 72,0 Greenhouse C C N/A No Yes сredit JSC “NATIONAL BANK FOR FOREIGN ECONOMIC ACTIVIT Y OF THE REPUBLIC OF UZBEKISTAN” "SUB-DRY" LLC SME 84 1 709,7 For processing fruits and vegetables B C N/A No Yes "YUSUF DIYOR" FE SME 84 4 950,0 Cultivation of cereals (except rice) B C N/A No Yes

JSICB “IPAK YULI”

ЧФ «Hoji-Gadoyboy Ota» credit 116 1500,0 Greenhouse B C N/A No Yes

LLC "ECO GRAND FRUITS" credit 84 4250,0 Greenhouse B C N/A No Yes

LLC "ECO PRODUCE TRADING" credit 84 4250,0 Greenhouse B C N/A No Yes Credi ООО "Fashion trend furnutere" 84 t

30 Annex 1: Photos LLC Mirfayz parfyum

31 Toshkent ta’mir beton

LLC "Muzaffar"

32 Murodbek shakhrizod Agro invest LLC

LLC "NOZIM KOZIM"

LLC Agrosoy Plast

33 Agro trade

Exim Agro

34 Shohjahon Ibroxim МЧЖ

Mirzahmedov Ravshan PF

35 Navoi Agro LLC

36 Annex 2

HORTICULTURE: PFI’s ANNUAL ENVIRONMENTAL AND SOCIAL PERFORMANCE REPORT

(To be submitted by PFIs to UZAIFSA)

1.

Name of the Financial Institution JSICB “Ipak Yuli” Completed by (name): S.Nigmatullaev Position in organization: ESMS Manager of JSICB “Ipak Yuli” Date: 15.01.2021 a. Portfolio Information

Report Covering Period: 1 year From: 01.01.2020 To: 31.12.2020 2. Information about loan portfolio of the Bank for the reporting period: b. Business Lines

Product Description Total exposure Average loan line outstanding for (or most recent transaction) FY end size (US$) (US$) Microfinance Loans or other financial products 28 609 079 12 773 for individuals with individual transactions less than $50,000 Small Loans or other financial products 3 066 972 87 341 business for individuals with individual transactions less than $300,000 Long term: Transactions with tenor greater than 12 months Microfinance Any lending, leasing or other 32 590 318 19 355 financial assistance to any corporate or legal entity other than an individual, with individual transactions less than $50,000 Any lending, leasing or other 62 231 378 126 334 financial assistance to any corporate or legal entity other than an individual, with Small individual transactions less than business $300,000 Other Other (if Shor-term transactions with 97 801 589 131 655 applicable) corporate clients (tenor less than 12 monts) and long-term transaction (tenor 171 998 203 1 179 395 greater than 12 months) with corporate clients of more than $300,000.

37 c. Exposure by Horticulture Sectors

3.1 Indicative percentage of industrial sectors for the project financed under ADB Loan 3471-UZB: Horticulture Value Chain Development Project:

Industrial Sector % Horticulture Value Chain Develoment Project Portfolio Intensive garden 27,4% Modern greenhouse complex 53,0% Regrigirated store 13,5% Equipment for processing of agriculture products 6,1% {Note: Please attach environmental and social audit or due diligence reports and environmental and social monitoring reports for each Project Company, if available} 3.2 Indicative percentage of industrial sectors for the project financed under ADB Loan 3673(COL)- UZB: Horticulture Value Chain Development Project:

Industrial Sector % Horticulture Value Chain Develoment Project Portfolio Moder n greenhouse complex 78% Organization of a refrigerated warehouse 22% 4 Information on all loans with: (i) tenor longer than 12 months; and (ii) maximum $5,000,000 loan size: Any outstanding environmental and IR and IP issues during reporting period and actions taken to address the issues – For all projects there are not outstanding environmental and IR and IP issues. Please see attachment 1. *Please use the sectors listed in the earlier table or any standard classification. Note: Env = Environment, IR = Involuntary Resettlement, IP = Indigenous Peoples.

d. Environmental and Social Management System (ESMS)

5 REQUIREMENT : (1) FOR EXISTING SUBPROJECTS: ATTACHMENTS OF MONITORING REPORTS OR REPORT ON DISCHARGE PERMITS; AND

(2) FOR NEWLY APPROVED SUBPROJECTS: ATTACHMENTS OF ENVIRONMENTAL OPINION APPROVAL.

38

Policies & Processes Yes/No Has your organization developed and implemented On April 15 th , 2013, the Bank's Supervisory Council approved the Regulation “On an ESMS? the environmental and social risk management system” of the JSICB "Ipak Yuli". On September 13 th , 2016, the Supervisory Council of the Bank approved the Policy “On the environmental and social risks management of JSICB "Ipak Yuli". According to the above-mentioned documents, all projects considered by the bank for financing must comply with the requirements of ESMS. In connection with the implementation of the ADB project 3471-UZB: Horticulture Value Chain Development, the Management Board of JSICB "Ipak Yuli" approved the ESMS Procedures for implementation of the above Project on 24 th May 24, 2017.

If there is an ESMS already in place, have there been There were no updates. However, the bank obtained technical asssitance from any updates to the ESMS or policy and procedures DEG in order improve and update its current ESMS by taking into account E&S adopted by your organization during the reporting requirement of bank’s international lenders. period? Has senior management signed off on the updated No, ESMS staff is currently working on updating the document. policy/pr ocedure? Has your organization appointed staff tasked to In order to implement the ESMS the ESMS Manager and ESMS Coordinator were implement the ESMS? appointed in the Bank's head office. In the branch offices, the heads of lending departments are appointed as regional ESMS managers. Also all employees of the Bank's lending divisons are involved in the implementation of ESMS. Loan officers apply procedures for managing environmental and social risks when considering every project financed by the Bank. They ensure compliance with protective measures for environmental and social issues, and if required, ensure the availability of environmental documents for each decision on granting a loan. Moreover, the staff of the Loan Portfolio Monitoring department carry out monitoring on the fulfillment of the ESMS obligations by the borrower after granting loan. All the above-mentioned staff is trained and have knowledge about ESMS procedures of the Bank. Please give details of any transactions rejected due Some examples from the Bank’s practice when the Bank rejected transactions to environmental and/or social concerns. due to environmental and / or social concerns: - Сlient's activities - production of cast iron, steel and ferroalloys. This activity of the client belongs to category A; - B category was assigned to the project, however the client did not bring the required documents (state expertise conclusion, etc.); - Client approached bank to obtain loan for purchase of special technical

39 equipemnt/machines. However, his main business activety was related to road construction. Please state any difficulties and/or constraints related Sometimes there are difficulties in determining which category of environmental to the implementation of the ESMS . risk the project belongs to. Please describe how you ensure that your subproject Financing of projects by the bank (project evaluation, financing and monitoring) is companies and their subprojects are operated in carried out in accordance with the procedure stipulated in the "ESMS procedures compliance with the national laws and regulations for ADB Loan 3471-UZB: Horticulture Value Chain Development Project", the and applicable ADB’s requirements. implementation of which ensures that the subproject complies with national laws and regulations, and the requirements of ADB. During monitoring it is checked that the borrower meets the ESMS requirements in accordance with the national standards and the requirements of ADB. In addition, according to the local legislation the divisions of the State Committee on Ecology and Environmental Protection monitor compliance with the requirements stated in the State Expert Examination Conclus ion by enterprises. Please give details of any material social and n/a environmental issues associated with clients during the reporting period. In case the existing ESMS is not fully functional, what The existing ESMS is fully functional. is the action plan being implemented by your organiz ation? Capacity Yes/No Please provide the name and contact information of ESMS Manager – Sardor Nigmatullaev the Environmental/Social Officer or Coordinator who Tel. No. +998 78 140-69-43 has the overall responsibility for the implementation of Email : [email protected] the ESMS. Nigmatullaev Sardor works as a Deputy head of IFI department and ESMS Manager since August 2019. He is a graduate of Westminster International University in Tashkent with bachelor’s degree in economics with finance.

ESMS Coordinator – Nargiza Atabaeva Tel.:+998-78 140-69-43 Email : [email protected]

Nargiza Atabaeva has been working in banking sector since 2011. Currently, she occupies position of lead specialist of IFI department and ESMS Coordinator. She has bachelor’s degree in international economic relations obtained from Tashkent State University of Econom ics.

40

Please provide current staffing of other core ESMS S. Nigmatullaev – ESMS Manager persons in the organization involved with ESMS implementation. N. Atabaeva – ESMS Coordinator

Sh. Mamatov – Deputy head of Investment Monitoring and Coordination Division

G. Abdukadyrov - Head of Loan Portfolio Monitoring Department

What was the budget allocated to the ESMS and its Salaries of employees involved in the implementation of ESMS. Other expencse implementation during the year? are covered based on re quest of ESMS manager. Monitoring Yes/No Do you receive environmental and social monitoring After financing of the project, environmental and social issues are monitored in reports from subproject companies that you finance? accordance with the Annex 6 of the ESMS Procedures for the ADB Loan 3471- UZB "Horticulture Value Chain Development Project". Monitoring is carried out according to the provided list of questions. Also, the Bank's monitoring officer checks the implementation of the Environmental Man agement Plan of the project. Do you check for ongoing compliance of your When completing Annex 5 (Analysis of the environmental impact of the project subproject companies with national regulation and and the preparation of the Environmental Management Plan), the requirements for any other requirements? mitigation measures prescribed in the Conclusion of the State Committee on Ecological and Environmental Protection are considered. When monitoring is carried out, implementation of the activities envisaged in the environmental management plan is verified, thus implementation of the national rules and ADB’s standards is checked. Also, according to the local legislation, the divisions of the State Committee on Ecology and Environmental Protection carriy out monitoring on implementation of the requirements, envisioned in the Conclusion of the State Committee on Ecology and Environmental Protection by enter prese. Please describe how you monitor the subproject Under the ADB loan 3471-UZB: Horticulture Value Chain Development Project the company and their subproject’s social and Bank financed 9 projects. The equipment of all projects has already arrived and environmental performance. projects were launched. The Bank conducted environmental and social monitoring for all financed projects (Acts of monitoring are attached). Пожалуйста, опишите, как вы осуществляете Under the ADB loan 3673(COL)-UZB: Horticulture Value Chain Development мониторинг компании подпроекта и социальных и Project the Bank apporved and financed 3 projects in 2019. The purpose of these экологических показателей их подпроекта project are purchasing materials, equipment for construction of green houses. The Bank carried out environmental and social monitoring on all financed projects, except for the subproject PF “HOJI GADOYBOY OTA” financed in 2018 and 2019. In connection with the facts of violation of financial discipline by t he HOJI

41 GADOYBOY OTA PF, the Bank has begun procedures for the early collection of loans from the HOJI GADOYBOY OTA PF, including those issued for projects approved by ADB. At the same time, the financial condition of the borrower will not affect the fulfillment of the Bank's obligations towards ADB. Under the ADB loan 3673 (COL)-UZB: Horticulture Value Chain Development Project, the Bank financed 1 project in 2020. The objective of the project is the purchase of refrigeration equipment for storing agricultural products. As soon as financing was made for the sub-projects, the loan files were transferred from the Credit operations department to the Loan Monitoring Department. After familirization with environmental and social protection documents the monitoring specialist during sight visit filled annex 6 (Act of Monitoring of environmental and social impact of the subproject). The monitoring specialist also check implementation of environmental management plan. The frequency of monitoring is in the course of usual monitoring which is usually not less than once every 6 months for B category projects. However, due to the introduction of measures to prevent the spread of coronavirus infection (COVID-19) in the Republic of Uzbekistan, a quarantine regime was imposed in the country and this affected the frequency of monitoring on sub -projects. Do you require the subproject owner to submit to you The Environmental Management Plan is completed in accordance with Annex 5 of evidence of compliance with required environmental the ESMS Procedures for ADB Loan 3471-UZB: Horticulture Value Chain and social approvals and permits for the subprojects. Development Project. It takes into account the impacts identified in Environmental Opinion report and mitigation measures prescribed in the Conclusion of the State Committee on Ecology and Environmental Protection. The monitoring officer at the site visit is required to verify the implementation of the mitigation measures specified in the environmental management p lan. Please provide details of any accidents/ During the site visit by monitoring staff, it was found that employee did not receive litigation/complaints/regulatory notices and fines: relevant training on pesticide handling. Monitoring specialists with participation of - Any incidents of non-compliance with the the Bank's ESMS Staff requested Sub-borrower and OHS staff to provide training applicable Environmental and Social Requirements for employess by taking into account following rules "Sanitary Rules and Hygienic - Covenants/conditionalities imposed Norms of Use, Storage and Transportation of Pesticides in Agriculture of by the Financial Institution to the subproject company Uzbekistan" and "Hygienic Requirements to Safety of Agricultural Chemicals". as a result of any non -compliance Reporting Yes/No Is there an internal process to report on social and According to the adopted procedure, based on the results of the monitoring, if the environmental issues to senior management? borrower fails to meet the requirements for compliance with environmental protection measures, the monitoring specialist must notify the ESMS Manager for taking appropriate measures.

42 The ESMS Manager should provide timely reports on the implementation of ESMS policies and procedures to the Management Board and interested parties of the Bank. Do you prepare any social and environmental reports: Yes, prepared for Netherlands Development Finance Company (FMO), Deutsche - For other multilateral agencies Investitions - und Entwicklungsgesellschaft mbH (DEG), European Bank for - Other stakeholders Reconstruction and Development's (EBRD), International Finance Corporation - E&S reporting in the Report (IFC) and others. Sustainability reports Activities on ADB’s Prohibited Investment Activities List If any, please indicate the dollar percentage of loans or investments out of your total outstanding exposure provided to clients who 0% are substantially involved in ADB’s Prohibited Investment Activities List (Refer to page 122 of SPS). If the percentage is not zero, please explain these exposures and any steps that have been taken to reduce such exposure. e. Category “B” Subprojects Using ADB Funds Information about all new subprojects using ADB loan funding approved during this reporting period (Under the ADB loan 3673(COL)-UZB: Horticulture Value Chain Development Project

E.1 Information about subproject "FASHION TREND FURNITURE" LLC Name of Subproject Company: LLC "FASHION TREND FURNITURE" (subproject is financed in March 2020) Subproject location: Tashkent city, Yashnabad district, st. Uysozlar, 49 Horticulture sector: The оrganization of a refrigerated warehouse (Construction of a refrigerated warehouse for storing agricultural products. The project provides for the purchase of refrigeration equipment with RGS system in order to provide services for the storage of fruits and vegetables in a cold room with a capacity of 3000 tons of agricultural products) Value of exposure (US$ ): 2.800.000 US Dollars Was any environmental and social due Yes, in particular, there were carried out analysis of environmental impact (ecological screening), as well as diligence undertaken by your social safeguards screening, safeguard due diligence briefing note during review. Review of safeguard organization? documents and field visits had been conducted by credit expert and ESMS coordinator. Any environmental assessment report Yes. Draft of Environmental Opinion and positive Conclusion of State ecological expertise dated 23.06.2020 or audit reports reviewed by your No.04/628 were inspected by the loan specialist and ESMS coordinator. According to the mentioned organization? Conclusion, the project is given 3rd category of environmental impact. ADB environmental category B/social category (environmental resettlement) C. What were the main environmental According to the Conclusion of State Ecological Expertise, this project falls under the category 3rd (low risk) issues associated with this subproject based on the resolution of the Cabinet of Ministers of the Republic of Uzbekistan 949 dated November 22, that were identified through due 2018. diligence conducted by your This object is bordered by: a void from the north; production site from the east; highway from the south; road

43 organization, and how were the issues from the west, then the production site. dealt with (i.e., outcome of due Impact on water : According to the project, the water required for domestic and drinking technological needs diligence)? of the facility will come from the district drinking water supply networks, of which 1176 cubic meters per year for domestic and drinking water supply. Impact on air: During the operation of the facility, pollutant emissions are 0.0324 tn/year: tetrafluoroethane 0.018 tn and carbohydrates 0.0144 tn. Waste : From territory cleaning and solid waste - 1,906 ton/year, used light bulbs - 0,00194472 ton/year, during operation 3 tons of unusable products are formed and transferred as animal feed, used rags 0,016 ton/year and paper waste 0,088 ton/year and transferred to companies for processing on a contractual basis. The generated waste is stored in metal containers and taken to landfills. The following ecological requirements must be fulfilled: - Maintenance of protective zones of engineering networks (gas, roads, water, electricity, communications, etc.) passing around the facility during its construction; - Contracting with territorial sanctioned landfills to dispose of wastewater, domestic and industrial waste generated during the operation of the facility; It is forbidden to discharge sewage water into natural open water bodies, burn waste on the territory of the site. Did you discuss with the subproject Yes. Bank inspectors carefully discussed with the subproject owner all the requirements regarding the owner the applicable environmental and environmental and social safeguard that he/she should meet during the implementation of project. social safeguard requirements and their implementation? Does the subproject comply with Yes, it does, as witnessed by the positive Conclusion of State Ecological Expertise. applicable government requirements? Does the subproject comply with Yes, as the results of preliminary analyzes shows, screening and safeguard due diligence this project applicable ADB safeguard complies with ADB safeguard requirements. requirements? Have there been any recorded incidents No, there were no incidents of non-compliance observed. of non-compliance or requests for corrective actions? Have there been any grievances or No, by this time there were no complaints received. complaints lodged on the subproject by any affected person or concerned stakeholder?

44 ANNUAL ENVIRONMENTAL AND SOCIAL PERFORMANCE REPORT

3. Please provide responses to the questions below. Please include additional sheets or attachments as required to provide details on questions that have been answered Yes. The Bank is required to submit the annual performance report to RRA.

Name of the Financial JSCB “Uzpromstroybank” Institution Completed by (name): Bahramov Rahimjon Date: Position in organization: Specialist at JSCB “Uzpromstroybank” 28.01.2021

A. Portfolio Information

Report Covering Period:

From: 01.01.2020 To: 31.12.2020

4. For the reporting period, please provide the following information about your portfolio where applicable:

B. Business Lines

Total exposure outstanding for Average loan Product Description most recent (or transaction) line FY end size (US$) (US$) Loan or other types of financial products Microfinance for individuals Loans or other financial products for Microfinance - - individuals Small Loans or other financial products for - - business individuals Long term: Transactions wit h tenor greater than 12 months Any lending, leasing or other financial assistance to any corporate or legal Microfinance - - entity other than an individual, with individual transactions less than $50,000 Any lending, leasing or other financial assistance to any corporate or legal Small entity other than an individual, with 1 062,06 1 524,5 business individual transactions less than $300,000 Other Other (if Please describe - - applicable)

C. Exposure by Horticulture Sectors

5. Please provide an indicative percentage of total Innovation to horticulture modernization loan portfolio per subcomponents:

45 Number of % Horticulture Value Chain Industrial Sector subprojects Develoment Project Portfolio

Cold storages 12 29,26%

Modern greenhouse complex 23 56,1% Equ ipment for processing and packaging 4 9,78% (logistics) Organization of logistics center 1 2,43% Organization of intensive orchards 1 2,43% Total: 41 100,0%

{Note: Please attach environmental and social audit or due diligence reports and environmental and social monitoring reports for each Project Company, if available}

4. In case of participation in long-term financing schemes for small businesses, please provide information on all loans: (i) which term exceeds 12 months; (ii) the amount of which is a maximum of US $ 5,000,000.

Loan Категория Unresolved Name type защитных мер issues related to of (Small Amount the environment, Sub-project Sub- ,medi Loan owed PQ and IP during using ADB Industry projec um period (thousand the reporting funds sector* t bis/sa (month) US ОС ВП КН period and comp les/fin dollars) measures to (yes/no) any ancin address these g) issues ООО "Uchk o'prik Horticulture Veget SMB 84 1 200,00 В No No No Yes (greenhouse) ables busine ss" ООО "Sher obod Horticulture SMB 84 985,16 В No No No No Anor (greenhouse) Impex " Organization of melon ООО producing "Muza SMB 72 1 750,00 В No No No No and ffar" processing cluster

* Use the sectors listed in the previous table or any standard classification D. Environmental and Social Management System (ESMS)

6. REQUIREMENT : (1) FOR EXISTING SUBPROJECTS: ATTACHMENTS OF MONITORING REPORTS OR REPORT ON DISCHARGE PERMITS; AND

(2) FOR NEWLY APPROVED SUBPROJECTS: ATTACHMENTS OF ZVOS APPROVAL. Policies & Processes Yes/No Yes, there is, "Policy for managing Has your organization developed and environmental and social risks of JSCB" Yes implemented an ESMS? Uzpromstroybank "and" Procedure for managing environmental and socia l risks

46 and impacts of JSCB "Uzpromstroybank"

"Policy for managing environmental If there is an ESMS already in place, and social risks of JSCB" have there been any updates to the Uzpromstroybank "and" Procedure for ESMS or policy and procedures adopted No managing environmental and social by your organization during the reporting risks and impacts of JSCB period? "Uzpromstroybank" were approved in 2020. Has senior management signed off on Yes the updated policy/procedure? The Director of the “Green Banking” Department of JSCB “Uzpromstroybank” A.R. Islamov is responsible for the implementation of the Bank's Environmental and Social Risk Management Policy. Head of the Project Analysis Department of the Green Banking Department N. Has your organization appointed staff Yes Rakhmanov and Chief Ecologist tasked to implement the ESMS? R.Bakhramov are responsible for the implementation of the Environmental and Social Risk and Impact Management Procedure for the implementation of the project "Development of the value chain in the Horticulture sector" using funds from the Asian Development Bank Please give details of any transactions rejected due to environmental and/or No - social concerns. Currently, the process of introducing a system for managing environmental and social risks is underway. There are practically no difficulties associated with the implementation of an Please state any difficulties and/or environmental and social risk constraints related to the implementation No management system. In case of any of the ESMS. questions or problems regarding the implementation of the environmental and social risk management system, the specialists of the "Green Banking" department are involved in solving the issue (problem). The work of companies conducting our Please describe how you ensure that your subproject and their subprojects is subproject companies and their ensured in accordance with SPSU that subprojects are operated in compliance meets the requirements of national with the national laws and regulations and legislation, as well as established applicable ADB’s requirements. requirements of ADB. Please give details of any material social and environmental issues associated with No Did not occur clients during the reporting period. In case the existing ESMS is not fully The current SPSU is fully functional functional, what is the action plan being

47 imp lemented by your organization? Capacity Yes/No Please provide the name and contact N. Rakhmanov, Head of the Project information of the Environmental/Social Analysis Division of the “Green Banking” Officer or Coordinator who has the overall Yes Department Tel. +998 (94) 711-37-47, responsibility for the implementation of Chief environmental specialist the ESMS. R. Bakhramov tel: +998 (91) 4980424 Please provide current staffing of other Credit specialists of the branches of core ESMS persons in the organization No involved with ESMS implementation. the Bank The costs of the implementation of SPSU What was the budget allocated to the were allocated to the salaries of ESMS and its implementation during the No employees involved in the implementation year? of SPSU. Other expenses are payable as required. Monitoring Yes/No Monitoring is carried out by the Do you receive environmental and social employees of the Bank's branches monitoring reports from subproject No companies that you finance? who financed the project together with the project initiators. During the monitoring process, the implementation of the measures provided for in the environmental management plan is checked, that is, the implementation of Do you check for ongoing compliance of the ADB national norms and requirements your subproject companies with national Yes is checked in this way. In addition, regulation and any other requirements? according to the current legislation, the units of the Committee on Ecology and Environmental Protection monitor the implementation of the requirements of the conclusion of the state eco -examination. In practice, monitoring of environmental Please describe how you monitor the and social impact issues will be carried out subproject company and their subproject’s by bank employees. The Bank will monitor social and environmental performance. environmental and social impact issues on which the equipment is ful ly delivered. The monitoring officer, when visiting the Do you require the subproject owner to site, is obliged to check the submit to you evidence of compliance with Yes implementation of the mitigation required environmental and social approvals and permits for the subprojects. measures specified in the environmental management plan. Please provide details of any accidents/ litigation/complaints/regulatory notices and fines: - Any incidents of non-compliance with the applicable Environmental and Social Requirements No - Covenants/conditionalities imposed - by the Financial Institution to the subproject company as a result of any non -compliance Reporting Yes/NO According to the adopted SPSU, based on the results of the monitoring, if the Is there an internal process to report on borrower has failed to comply with the social and environmental issues to senior Yes requirements for compliance with management? protective measures for environmental protection, the employee is obliged to

48 inform the SPSU Manager about this to take appropriate measures.

Do you prepare any social and environmental reports: - For other multilateral agencies No For ADB - Other stakeholders - E&S reporting in the Report Sustainability reports

Activities on ADB’s Prohibited Investment Activ ities List If any, please indicate the dollar percentage of loans or investments out of your total outstanding exposure provided to clients who are There aren’t any substantially involved in ADB’s Prohibited Investment Activities List (Refer to page 122 of SPS). If the percentage is not zero, please explain these exposures and any - steps that have been taken to reduce such exposure.

E. Category «В», Subprojects using ADB Funds

6. Please provide information about all new subprojects using ADB loan approved during this reporting period

Name of Subproject Company: "Uchko'prik Vegetables business" Llc Subproject location: Fergana region, Uchko’prik district Horticulture sector: Greenhouse Value of exposure (US$ ): 1 200 000,0 US dollars Was any environmental and social Yes, according to the “Procedure for managing due diligence undertaken by your environmental and social risks and impacts of JSCB“ organization? Uzpromstroybank ”, preliminary environmental impact analyzes are carried out with a visit to the Borrower (screening, categorization of projects, environmental and social assessment with the development of corrective measures (if necessary) and environmental and social monitoring) with the study of the necessary documents and permits, including the conclusions of the state ecological expertise. For category B projects, a loan officer of the Bank's branch conducts the audit, and category A projects are carried out by specialists of the "Green Banking" department Any environmental assessment Yes, the documents for this reason for the sub-project, report or audit reports reviewed by such as the Draft ZVOS (Environmental Impact your organization? Statement) and the State Environmental Expertise Conclusion under the State Committee for Ecology and Environmental Protection, have been reviewed by the Bank's loan officer. What were the main environmental As a result of the inspection of this subproject, it was issues associated with this revealed that production and consumption wastes will subproject that were identified be generated during the year, which are generated through due diligence conducted by during the year, such as vegetable waste, waste of used your organization, and how were plastic film, waste of rejected boxes, waste of worn out the issues dealt with (i.e., outcome bags, fluorescent lamps. Since the technology of energy of due diligence)? efficient and resource efficient greenhouses does not involve planting seedlings in the ground and involves the

49 use of hydroponics, there will be no soil pollution and land cultivation. The greenhouse will run on natural gas, which will help to avoid the emission of air pollutants in large quantities. Since this green technology is designed to conserve resources, chemical fertilizers will be used in limited quantities through a drip irrigation system that also conserves water provided from the planned artesian well. A short-term exposure to inorganic dust is also expected during the construction work of the facility, the subproject provided dust suppression of the work site.

For each type of waste, the place and conditions of temporary storage on the territory of the site, as well as further movement of waste, are determined. In particular, the remainder of consumption is transferred to specialized enterprises for disposal. Did you discuss with the subproject Yes, the Bank's specialists discussed, explained and owner the applicable environmental explained to the owner of the subproject all the and social safeguard requirements requirements related to environmental and social and their implementation? protection that the Borrower must comply with when implementing the subproject. In addition, the loan agreement provides for an obligation to implement the project with due diligence and efficiency in accordance with safety, health and environmental standards and practices. Does the subproject comply with Yes, this is consistent, as evidenced by the positive applicable government conclusion of the State Environmental Expertise. requirements? Does the subproject comply with Yes, according to preliminary analysis, this subproject applicable ADB safeguard meets ADB security requirements. requirements? Have there been any recorded No inconsistencies were found. In case of non- incidents of non-compliance or compliance, corrective measures will be developed to requests for corrective actions eliminate or minimize risks (problems) together with the Borrower. No, by this time no corrective action had been requested. Have there been any grievances or No, by this time no complaints had been received. complaints lodged on the subproject by any affected person or concerned stakeholder?

Name of Subproject Company: "Sherobod Anor Impex" Llc Subproject location: Surkhandarya region, Sherabad district Horticulture sector: greenhouse, processing of horticulture products Value of exposure (US$ ): 985 160 ,0 US dollars Was any environmental and social Yes, according to the “Procedure for managing due diligence undertaken by your environmental and social risks and impacts of JSCB organization? “Uzpromstroybank”, preliminary environmental impact analyzes are carried out with a visit to the Borrower (screening, categorization of projects, environmental and social assessment with the development of corrective measures (if necessary) and environmental

50 and social monitoring) with the study of the necessary documents and permits, including the conclusions of the state ecological expertise. For category B projects, a loan officer of the Bank's branch conducts the audit, and category A projects are carried out by specialists of the "Green Banking" department. Any environmental assessment Yes, the documents for this reason for the sub-project, report or audit reports reviewed by such as the Draft ZVOS (Environmental Impact your organization? Statement) and the State Environmental Expertise Conclusion under the State Committee for Ecology and Environmental Protection, have been reviewed by the Bank's loan officer. What were the main environmental As a result of checking this subproject, it was revealed issues associated with this that production and consumption wastes will be subproject that were identified generated during the year, which are generated during through due diligence conducted by the year, such as vegetable waste, waste of used plastic your organization, and how were film, waste of rejected boxes, waste of used bags, the issues dealt with (i.e., outcome fluorescent lamps. Since the technology of energy of due diligence)? efficient and resource efficient greenhouses does not involve planting seedlings in the ground and involves the use of hydroponics, soil pollution and land cultivation will not occur. The greenhouse will run on natural gas, which will help to avoid the emission of air pollutants in large quantities. Since this green technology is designed to conserve resources, chemical fertilizers will be used in limited quantities through a drip irrigation system that also conserves water provided from the planned artesian well. A short-term exposure to inorganic dust is also expected during the construction work of the facility, the subproject provided dust suppression of the work site. For each type of waste, the place and conditions of temporary storage on the territory of the site, as well as further movement of waste, are determined. In particular, the remainder of consumption is transferred to specialized enterprises for disposal. Did you discuss with the subproject Yes, the Bank's specialists discussed, explained and owner the applicable environmental explained to the owner of the subproject all the and social safeguard requirements requirements related to environmental and social and their implementation? protection that the Borrower must comply with when implementing the subproject. In addition, the loan agreement provides for an obligation to implement the project with due diligence and efficiency in accordance with safety, health and environmental standards and practices. Does the subproject comply with Yes, this is consistent, as evidenced by the positive applicable government conclusion of the State Environmental Expertise. requirements? Does the subproject comply with Yes, according to the results of preliminary analysis, applicable ADB safeguard verification, and due diligence regarding protection, this re quirements? project complies with ADB security requirements. Have there been any recorded No, there have been no cases of non-compliance. incidents of non -compliance or

51 requests for corrective actions? Have there been any grievances or No, no complaints have been received by this time. complaints lodged on the subproject by any affected person or concerned stakeholder?

Name of Subproject Company: "Muzaffar" LLC Subproject location: Surkhandarya region, Sherabad district. Horticulture sector: Greenhouse, processing horticulture products Value of exposure (US$ ): 1 750 000,0 US dollars Was any environmental and Yes, according to the “Procedure for managing social due diligence undertaken environmental and social risks and impacts of JSCB by your organization? “Uzpromstroybank”, preliminary environmental impact analyzes are carried out with a visit to the Borrower (screening, categorization of projects, environmental and social assessment with the development of corrective measures (if necessary) and environmental and social monitoring) with the study of the necessary documents and permits, including the conclusions of the state ecological expertise. For category B projects, a loan officer of the Bank's branch conducts the audit, and category A projects are carried out by specialists of the "Green Banking" department. Any environmental assessment Yes. The draft Environmental Impact Statement (EIA) report or audit reports reviewed by and the State Environmental Review Report were your organization? reviewed by the loan officer and ESMS coordinator to thoroughly evaluate the project. What were the main As a result of the verification of this subproject, it was environmental issues associated revealed that production and consumption wastes will be with this subproject that were generated during the year, which are generated during identified through due diligence the year, such as vegetable waste, waste of used plastic conducted by your organization, film, waste of rejected boxes, waste of used bags, waste and how were the issues dealt of used LED lamps, solid waste and waste from cleaning with (i.e., outcome of due the territory. diligence)? For each type of waste, the place and conditions of temporary storage in the territory of the site, as well as further movement of waste, have been determined. In particular, the remainder of consumption is transferred to specialized enterprises for disposal. Since the technology of energy-efficient and resource- efficient greenhouses does not involve planting seedlings in the ground and involves the use of hydroponics, there will be no soil pollution and land cultivation and, accordingly, there is no risk of soil erosion. The greenhouse will run on natural gas, which will help to avoid the emission of air pollutants in large quantities. However, short-term exposure to air pollutants is expected during the renovation of the facility, these minor emissions do not have a significant impact on the environment. Since this green technology is designed to conserve resources, chemical fertilizers will be used in limited quantities through a drip irrigation system that also conserves water provided from the planned artesian well. A short -term exposure to air pollutants is also expected

52 during the renovation of the facility, these minor emissions do not have a significant impact on the environment. Did you discuss with the Yes, the Bank's specialists discussed, explained and subproject owner the applicable explained to the owner of the subproject all the environmental and social requirements related to environmental and social safeguard requirements and their protection that the Borrower must comply with when implementation? implementing the subproject. In addition, the loan agreement provides for an obligation to implement the project with due diligence and efficiency in accordance with safety, health and environmental standards and practices. Does the subproject comply with Yes, this is consistent, as evidenced by the positive applicable government conclusion of the State Environmental Expertise. requirements? Does the subproject comply with Yes, according to the results of preliminary analysis, applicable ADB safeguard verification, and due diligence regarding protection, this requirements? project complies with ADB security requirements. Have there been any recorded No inconsistencies were found. In case of non- incidents of non-compliance or compliance, corrective measures will be developed to requests for corrective actions? eliminate or minimize risks (problems) together with the Borrower. No, there have been no cases of non-compliance.

Have there been any grievances or complaints lodged on the No, no complaints have been received by this time. subproject by any affected person or concerned stakeholder?

53 Annual report of PJSCB “DAVR BANK” on the environmental and social performance (as of January. 01, 2021)

1. Please provide the answers to the questions below. Please include additional sheets or attachments as needed to provide detailed information on matters for which the answers are in the affirmative. Bank must submit an annual report on the implementation to ADB

Name of Financial Institution PJSCB “DAVR BANK” Completed specialist (full name): Gayrat Mahmudov Head of Project Position in the organization: ImplementationDate: January. 01, 2021 Group

A. Information on the portfolio

The period of coverage of the report: From: Till: Jan. 01, 2020 Dec. 31, 2020

2. Please provide the following information about your portfolio, where applicable in the reporting period:

B. Type of activity

The overall effect Average loan size issued at the end of Product line Description (or transaction) the last fiscal year (in US$) (in US$)

Loans and other financial Micro financing 47 236 288,41 1 349,38 products for physical entities

Loans and other financial Small business products for physical entities 1 967 073,90 1 934,19 and individual entrepreneurs

Long term: Transactions for a period longer than 12 months Any lending, leasing and other financial support to corporate entities or entities, Micro financing 15 678 037,07 9 020,73 that are not individuals, deal with less than 45 000 US dollars Any lending, leasing and other financial support to corporate entities or entities, Small business 22 424 876,95 104 789,14 that are not individual, deal with less than 300 000 US dollars Other

54 Any lending, leasing and other financial support to Other (if corporate entities or entities, 29 554 559,95 107 863,36 applicable) that are not individual, deal with more than 300 000 US dollars

C. Impacton on the horticulture 3. Please provide the estimated percentage of the total loan portfolio of horticulture: % of the loan portfolio of horticulture value Industry Sector chain development project Fruit seedlings 14

Vegetable seeds 0

Refrigeration warehouses 2 Technological line for drying fruits and 38 vegetables processing line for mung beans 0

Packaging equipment 4

Greenhouse 42 Note: Please attach environmental and social audits or expert reports, test reports on environmental and social risks for each project of the company, subject to availability. 4. If there is a long-term financing of horticulture, please provide information on all loans to: (I) for a period longer than 12 months; and (II) the sum of the loan is not more than 5 000 000 US dollars.

Any outstandin Protection g Category environme The ntal and IR project is and IP due to issues the line of during the the Asian period of Value Value (US$) (US$) Sector* Sector*

impacts impacts Develop Industry Industry Finance) Finance) drafting the ment reports IP IR IR Bank ENV ENV Name of the project project the of Name and Loan term (in months) months) (in term Loan (yes / no) actions taken to

Loan type (Small Business / Trade Trade / Business (Small type Loan address issues Small 36 "Shah Polan" 156 000. Horti N/ Busines month B C No Yes LLC 0 culture A s s “Sendrillion” Small 48 Horti N/ 89 650.0 B C No Yes LLC Busines month culture A

55 s s Small 60 “Eco Fresh 499 000. Horti N/ Busines month B C No Yes Fruit” LLC 0 culture A s s * Please use a sector listed in the preceding table or any standard classification Note: Env = Environment, IR = displacement, IP = Indigenous Peoples.

D. Environmental and Social Management System (ESMS) 5. Requirements: (1) for existing projects: investment monitoring reports or documents for issuing permits for discharges; and (2) for newly approved projects: the attachment of the approved ZVOS.

Policies and Processes Yes/No Does your organization have Submitted Yes developed and feasible ESMS? If ESMS already there, whether any New procedure was approved on additions and changes made to or 15.05.2017 for ESMS, a copy was received from your organization's No submitted. policies and procedures during the reporting period? Does management signed an Management has not signed an updated No updated policy / procedure? policy Does your organization assigned Mahmudov Gayrat personnel, which tasked with the Yes Head of Project Implementation Group implementation of ESMS? Provide details of any transactions Several subprojects were rejected rejected due to environmental and / Yes according to ZVOS category and or soci al problems. equipment's Country of origin Please indicate any difficulties and / There was not any difficulty regarding to or restrictions related to the No implementation of ESMS. implementation of ESMS. It should describe what was All subprojects which refinanced by ADB confirmed that the companies and were screened by following steps: their projects operate in accordance • in accordance with the list of prohibited with laws and regulations and meet investment activities; the requirements of ADB. Yes • according to the list of control questions for environmental screening; • According to the screening list for compliance with ADB's social risk measures Please describe in detail any of the During refinancing subprojects, ESMS materials on the social and managers deeply learned all stages of environmental risks regarding No environmental and social risks and did not customers for the period. find any seriously risks which can influence to environment and social. If the existing ESMS is not fully Existing ESMS approved fully functional functional, which action plans are No approved in your organization? Capabilities Yes/No Please provide the name and Mahmudov Gayrat Mazbudovich contact information of the manager Head of Project Implementation Group or the Environmental Protection Yes Tel num: +998712070909 (internal numb Environment Coordinator / social 123) protection, which is the main

56 responsible for the implementation / Present staff schedule of the Every quarter PJSCB “DAVR BANK” organization and staff involved in the ESMS managers organizes seminars for implementation of ESMS. credit officers in order to give correct Yes perception to initiators of subprojects and implement monitoring while refinancing projects What is a budget for the Budget is not allocated implementation of ESMS during the No year? Monitoring Yes/No Are you getting the environmental Monitoring managers of the bank fills the and social monitoring reports from act-“Typical area monitoring form” during the companies whose projects were refinancing for sub-projects of ADB. Yes financed? Moreover, every year monitoring managers make cite visiting monitoring of refinanced sub-projects Are the company projects constantly Once a year, sub-projects are monitored checked for compliance with laws Yes by monitoring officer. and other requirements? Please describe how you are With access to the site, monitoring checking the project of the company, manager fills the act-“typical area social and environmental Yes monitoring form” after refinanced performance of the project. subproject. This year, a visit was made to the place of all sub-projects Is the project initiator requested to The subproject initiator requested to get provide verification for compliance Conclusion of State committee for Nature with the required environmental and protection (ZVOS) social agreements and project approvals? Please provide information on any During researching environmental and incidents / litigation / complaints / social risks of sub-projects there was not legal requirements and fines: any incident, ligation and complaints. - Cases of non-compliance with applicable environmental and social No protection; Covenants / conditionality imposed by the financial institution on the project of the company as a result of any non-compliance Reporting Yes /No Is there an internal process to inform During the processing of documents, management on the environmental specialist of the credit department gives a and social protection? conclusion on approval of the project for refinancing, as well as on environmental and social checklist screening. After Yes financing, every year with the access to the site, the project will be monitored and environmental and social checklist will be completed by the monitoring department manager and the Bank's management will be informed about monitoring results. Do you prepare any reports on social PJSCB “DAVR BANK” does not prepare No and environmental protection? any reports on social and environmental

57 - Other multilateral agencies protection to other agencies. - Other interested parties - Statements of E & S on the report on sustainable development Activity on the list of prohibited investment activities ADB If any, please specify dollar equivalent of loans in percentage or investments of the total portfolio to customers who, in fact, fall into the No 0% list of prohibited investment activities ADB (Page 122 environmental policy). If the percentage is not zero, please explain these effects and any steps No 0% that would be taken to reduce such exposure.

E. Projects category "B" using ADB funds

6. Provide information on all new projects, debt financing by ADB funds approved during the reporting period. The name of the project company: "Parkent" LLC Location of the project: Republic of Uzbekistan, Tashkent region, Parkent district, Bogbon street Branch: PJSCB “DAVR BANK” Mirza Ulugbek branch The volume of investments (in US $): 60 000.00 Protection classification: Environment:0 “B” Involuntary Resettlement: “C” Indigenous peoples: “N/A” Did your organization conducted legal due Yes diligence of environmental and social protection Environmental Screening Checklist and Social Safeguards Screening Checklists were attached Other reports of environmental assessment or Yes audit reports reviewed by your organization Conclusion of State committee for Nature protection (ZVOS) What are the major environmental problems associated with this project, which were identified during the examination carried out in your No organization, how these issues were addressed (ie, the result of expertise)? Did you discuss with initiator of the project applicable requirements for environmental and Yes social protection and their implementation? Does the project suit to the applicable Yes requirements of the legislation of Uzbekistan? Does the project suit to the current protection Yes requirements of the ADB? Were there any documented cases of non- compliance or requests for corrective action? No

58 Were there any complaints or claim on the draft submitted by any injured person or an interested party? No

ANNUAL ENVIRONMENTAL AND SOCIAL PERFORMANCE REPORT

7. Please provide responses to the questions below. Please include additional sheets or attachments as required to provide details on questions that have been answered Yes. The Bank is required to submit the annual performance report to UZAIFSA Name of the Financial Institution JS “Asakabank” Completed by (name): M.Nurullaev Position in organization: Specialist of major projects Date: 15.01.2021

E. Portfolio Information

Report Covering Period: From: 01.01.2020 To: 31.12.2020

8. For the reporting period, please provide the following information about your portfolio where applicable:

F. Business Lines

Total exposure Average loan (or outstanding for most Product line Description transaction) size recent FY (thousand US$) end(thousand US$) Loans or other financial products for Microfinance 347 336 816,0 3 179.0 individuals Loans or other financial products for Small business 4 809.0 7 387.0 individuals Long term: Transactions with tenor greater than 12 months Any lending, leasing or other financial assistance to any corporate or legal Microfinance 39 263 053.83 11 992.8 entity other than an individual, with individual transactions less than $50,000 Any lending, leasing or other financial assistance to any corporate or legal Small business entity other than an individual, with 2 279 072 364 1 832 051.0 individual transactions less than $300,000 Other Factoring Any crediting, leasing or other financial Other (if assistance to any corporate or legal applicable) entity, with the exception of an individual, with a separate transaction amount of more than $ 300,000

G. Exposure by Horticulture Sectors

9. Please provide an indicative percentage of total Innovation to horticulture modernization loan portfolio per subcomponents: % Horticulture Value Chain Develoment Industrial Sector Project Portfolio Intensive garden 3% Modern green house complex 17% Cold storages 64%

59 % Horticulture Value Chain Develoment Industrial Sector Project Portfolio Equipment for processing of agriculture products 17%

60 10. If engaged in long-term small business finance, please provide information on all loans with: (i) tenor longer than 12 months; and (ii) maximum $5000000 loan size. ( Sub-project using ADB funds ) Any outstanding Sub-project Value of environmental and IR and IP Tenor of Safeguard using ADB Type of loanSME /trade exposure issues during reporting Name of Sub-project loan Industry Sector category funds finance) (thousand period and actions taken to (months) (yes/no) US$) address the issues Env IR IP

LLC "Accent Way Tading" credit 84 489,7 Procecing B c N/A No Yes

ЧФ "Qudrat Baraka" credit 84 2700,0 Packing B c N/A No Yes

LLC "Universal Euro Food Trading" credit 84 2580,0 Greenhouse B c N/A No Yes

LLC "Zero Fax" credit 72 450,0 Greenhouse B c N/A No Yes

LLC "Kasmetik Ta'mir" credit 84 450,0 Greenhouse B c N/A No Yes

LLC "Ibrohimjon Muhammadamin Baraka" credit 84 410,0 Greenhouse B c N/A No Yes

LLC «Oltin Voha Gidroponika" credit 84 500,0 Greenhouse B c N/A No Yes

LLC "Bukhara Gold" credit 84 2000,0 Greenhouse B c N/A No Yes

LLC "Lider Invest Millenium" credit 84 1400,0 Greenhouse B c N/A No Yes

LLC "Qashqadaryo Parnik Taraqqiyot Invest" credit 84 5000,0 Greenhouse B c N/A No Yes

LLC "Dolina Stroy" credit 84 2,200,0 Greenhouse B c N/A No Yes

LLC "Inshoot Turxoll Agro" credit 84 1200,0 Greenhouse B c N/A No Yes

LLC «Bukhara Best Greenhouse" credit 84 550,0 Greenhouse B c N/A No Yes

LLC"Sardor Sarbon" credit 84 400,0 Greenhouse B c N/A No Yes

LLC «Murod Bobo Jasur" credit 84 760,0 Greenhouse B c N/A No Yes

LLC "Salomat Suxrob Ziyo Farm" credit 84 400,0 Greenhouse B c N/A No Yes

61 LLC «Al Samo Nur" credit 84 750,0 Greenhouse B c N/A No Yes

LLC «Asadbek G'isht sanoati" credit 84 1 200,0 Greenhouse B c N/A No Yes

LLC «BUXARA PROF STROY STANDART" credit 84 640,0 Greenhouse B c N/A No Yes

LLC «Greenhouse Company" credit 84 4892,0 Greenhouse B c N/A No Yes

LLC «Universal Agrotex Servis" credit 84 1397,2 Greenhouse B c N/A No Yes

LLC «Romitan-Agrozamini" credit 84 1,400,0 Greenhouse B c N/A No Yes

LLC "Agro Mega City" credit 84 900,0 Greenhouse B c N/A No Yes

ФХ "Nigina Bektosh Bog'i" credit 84 1008,0 Greenhouse B c N/A No Yes

ФХ "Xayit Chori Zamini" credit 84 4000,0 Greenhouse B c N/A No Yes

ЧП "Qoraqosh Greenhouse" credit 84 358,0 Greenhouse B c N/A No Yes

LLC Yug Sever Story credit 84 800,0 Greenhouse B c N/A No Yes

ФX "Dostonbek Dilshodbek Zamini" credit 84 520,0 Greenhouse B c N/A No Yes

LLC "Aslonobod Plyus" credit 84 1285,0 Greenhouse B c N/A No Yes

LLC «Akbarshox Mironshox Bobirshox" credit 84 650,0 Greenhouse B c N/A No Yes

LLC” Azamat Elshod” credit 84 500,0 Greenhouse B c N/A No Yes

LLC “Everest Green House” credit 84 900,0 Greenhouse B c N/A No Yes

LLC «NRJ Agro centure" credit 84 900,0 Greenhouse B c N/A No Yes

62 H. Environmental and Social Management System (ESMS)Requirement:

Policies & Processes Yes/No Has your organization developed and implemented Being attached a copy of the ESMS to this Yes an ESMS? report. If there is an ESMS already in place, have there been any updates to the ESMS or policy and No procedures adopted by your organization during the reporting period? Has senior management signed off on the updated No policy/procedure? Has your organization appointed staff tasked to 22 ESMScoordinators from branches of the Yes implement the ESMS? bank Please give details of any transactions rejected due No to environmental and/or social concerns. Please state any difficulties and/or constraints Delivering reports on the ADB project in Yes related to the implementation of the ESMS. english language Please describe how you ensure that your On the basis of the loan agreement and in subproject companies and their subprojects are accordance with the legislation of the operated in compliance with the national laws and Republic of Uzbekistan, the borrower is Yes regulations and applicable ADB’s requirements. obliged to fulfill all obligations to implement the current requirements for environmental protection measures Please give details of any material social and environmental issues associated with clients during No the reporting period. In case the existing ESMS is not fully functional, what is the action plan being implemented by your No organization? Capacity Yes/No Please provide the name and contact information of Head of Unit: Bozorov M; the Environmental/Social Officer or Coordinator Yes who has the overall responsibility for the implementation of the ESMS. Please provide current staffing of other core ESMS Head of Unit: Bozorov M; persons in the organization involved with ESMS Yes implementation. What was the budget allocated to the ESMS and its ESMScoordinatorsare the current specialists

implementation during the year? of the branch of the bank Monitoring Yes/No Do you receive environmental and social After having been financed the project, monitoring reports from subproject companies that environmental and social issues are you finance? presented in a monitored way due to the Annex 6 of the ESMS Procedures for the ADB Loan 3471-Uzb "Horticulture Value Yes Chain Development Project". Monitoring is completed according to the provided list of questions. Besides that, the Bank's monitoring officer checks the implementation of the Environmental Management Plan of the project. Do you check for ongoing compliance of your According to the legislation of the Republic subproject companies with national regulation and of Uzbekistan, the implementation of any other requirements? national standards and any other Yes environmental requirements is controlled by state bodies. The Bank monitors the project to implement their mitigation measures. Please describe how you monitor the subproject Thecoordinator of the sub-project monitors company and their subproject’s social and fills appendix 6,and on the basis of environmental performance. supporting documents, monitoring is carried Yes out, the sub-project initiator fulfills all obligations to implement the current requirements for environmental protection measures prescribed in the EIS and in the

63 conclusion of the state environmental review. Do you require the subproject owner to submit to The initiator of the subproject submits to the you evidence of compliance with required Coordinator of the ESMS a confirmation of environmental and social approvals and permits for compliance with the necessary the subprojects. environmental and social approvals and Yes permits, on the basis of which the coordinator of the ESMS monitors and provides the Manager of the ESMS for further reporting on ESMS. Please provide details of any accidents/ litigation/complaints/regulatory notices and fines: - Any incidents of non-compliance with the applicable Environmental and Social Requirements No - Covenants/conditionalities imposed by the Financial Institution to the subproject company as a result of any non-compliance Reporting Yes/No Is there an internal process to report on social and Due to the adopted procedure, based on the environmental issues to senior management? results of the monitoring if the the requirements for compliance with environmental protection measures were Yes failed by the borrowers, manager of the ESMS collects all project reports from the coordinators of the ESMS and provides the management of the bank quarterly Do you prepare any social and environmental Social and environmental reports are reports: provided only to ADB - For other multilateral agencies No - Other stakeholders - E&S reporting in the Report Sustainability reports

Activities on ADB’s Prohibited Investment Activities List If any, please indicate the dollar percentage of loans or investments out of your total outstanding exposure provided to clients who are substantially involved in ADB’s 0% Prohibited Investment Activities List (Refer to page 122 of SPS). If the percentage is not zero, please explain these There is no credit that essentially falls under the exposures and any steps that have been taken to reduce "List of prohibited types of investment activities" such exposure. of ADB I. Category “B” Subprojects Using ADB Funds

11. Please provide information about all new subprojects using ADB loan funding approved during this reporting period. N/A The Bank was not funding the projects category "b" at the expense of the ADB.

Sub-projects of the category “C”in which are usedfromADB funds.

the amountof The Initiator The locationof Sub-loan The goal of The basis for classifying a sub- № of the sub- Sub-project (thousand sub-project project into category "C" project US $)

N/A For the current report period, there are no sub-projects in JSC ASAKA, financed with ADB loan resources.

64 ANNUAL REPORT ON EFFECTIVENESS OF IMPLEMENTATION OF ECOLOGICAL AND SOCIAL MEASURES

Name of financial institution JSCB Turonbank Filled in (name): Muminov Tahir Position in organization: Specialist Date: 03.01.2021

Information about portfolio

Period covered by the report: From: 01.01.2019 y. Until: 31.12.2020 y.

1. Provide the following information for the reporting period about your loan portfolio, when applicable B. Activity Average loan Total outstanding size (or debt at the end of the Products Description operations) last available f.g. (thoUSDnd dall. (thoUSDnd dall. USD) USD) Microfinance Loans or other financial 30 269, 4 2,0 products for individuals Small Loans or other financial 12 290, 4 1,4 business products for individuals Long-term operations: on surgery with a validity period of more than 12 months Any lending, leasing and other financial assistance to any corporate or legal entity, Microfinance except for the individual, with 31 600, 2 10,2 the volume of individual transactions of less than 50 000 dollars. US Any lending, leasing and other financial assistance to any corporate or legal entity, Small with the exception of the 59 149, 5 124,14 business individual, with the volume of individual transactions 300 000 dollars. US Other Other (if Factoring 204, 9 34,2 available) Any lending, leasing and other financial assistance to any corporate or legal entity, except for the individual, with 314 507, 3 1 443,28 the volume of separate operations over 300 000 dollars. US Total 448 021 ,7 16,3

C. Debt by fruit and vegetable sectors 2. Indicate the approximate percentage of total innovation for the loan portfolio for the

65 modernization of the fruit and vegetable by subcomponents:

Industrial sector % of innovations within the loan portfolio for the modernization of horticulture (ADB) Purchase of equipment I have for the greenhouse 77 % farming Purchase of processing equipment 10% Purchased tion equipment for the 8 % refrigeration chamber Creating an intense garden 4% Agrology 0.5% Grape 0.5%

3. If you participate in long-term financing schemes for small businesses in the horticulture sector, please provide information on all loans: (i) whose term exceeds 12 months; (ii) whose size is a maximum of 5,000 thoUSDnd. Category of Unresolved protective issues on the Sub- Amount measures environment, project Type Loan owed Sector indus airspace with ADB Subproject Name of term (thoUSD t- and indigenou Execui- m line loan (months) nd dall. riallaziness* V s peoples and ations USD) OS KN P measures to ADB funds address long LLC "BENOIS TEKSTIL" 84 350,0 fruit In No No No Yes 3673 сredit LLC "BUXORO long 120 840,0 fruit In No No No Yes 3673 INTERKONTINENTAL" сredit LLC "UMARBEK long 84 106,0 fruit In No No No Yes 3673 BUSINESS CLASS" сredit LLC "O'RTACHO'L MEVA- long 120 540,0 fruit In No No No Yes 3673 SABZAVOT" сredit LLC "ZOHID OZOD long 108 350,0 fruit In No No No Yes 3673 KELAJAGI" сredit LLC "SHIRIN NIYAT long 84 4 500,0 fruit In No No No Yes 3673 BARAKA" сredit LLC "SAPAR BOBO long 84 1 300,0 fruit In No No No Yes 3673 NABIRASI JAVOXIRI" сredit LLC "EXPRESS TEMIR- long 84 1 040,0 fruit In No No No Yes 3673 CONCRETE SERVICE" сredit long LLC "BO’RI DEVONBEGI" 84 400,0 fruit In No No No Yes 3673 сredit long SE "MUBORAK JAGUAR" 84 130,0 fruit In No No No Yes 3673 сredit long PE "OYDIN OHUNOVA" 84 130,0 fruit In No No No Yes 3673 сredit LLC "JEYNOV MEBEL long 84 100,0 fruit In No No No Yes 3673 GOLD" сredit long LLC "LIMO LAYM" 84 90,0 fruit In No No No Yes 3673 сredit LLC "ZARAFSHON long 84 2 065,0 fruit In No No No Yes 3673 GRAND BOG'LARI" сredit long LLC "SHERKHON OIL" 84 490,0 fruit In No No No Yes 3673 сredit long FH " ADIZBOBO" 84 628,0 fruit In No No No Yes 3673 сredit LLC "NAVBAHOR AGRO long 84 1 050,0 fruit In No No No Yes 3673 LIMON" сredit LLC "ZARAFSHON long 84 1 325,0 fruit In No No No Yes 3673 GRAND BOG'LARI " сredit FE "VODIY long 84 520,0 fruit In No No No Yes 3673 AGRO COMPLEX" сredit long LLC “METIN TEKSTIL" 84 1 198,0 fruit In No No No Yes 3673 сredit long LLC "QO’SHXOVUZ" 84 2 500,0 fruit In No No No Yes 3673 сredit LLC "NARPAY XOSILBEK long 84 330,0 fruit In No No No Yes 3673 AGRO" сredit LLC "JOMBOY GOLDEN long 84 1 040,0 fruit In No No No Yes 3673 FRUITS" сredit

66 LLC "EXPRESS TRADE long 84 238,0 fruit In No No No Yes 3673 ORGANIZATION" сredit LLC "PURE FREEZING long 84 750,0 fruit In No No No Yes 3673 SERVIСЕ" сredit LLC "ASIA AGRO long 84 500,0 fruit In No No No Yes 3673 PRODUCTS" сredit FARM "SOBIR long 84 70,0 fruit In No No No Yes 3673 ABDIMURODOV" сredit LLC "AHMAD DONISH long 84 90,0 fruit In No No No Yes 3673 RISOL" сredit FARM "RUZIEV HUSAN long 84 39,0 fruit In No No No Yes 3673 RUZIEVICH" сredit LLC " MARHAMAT long 72 255,0 fruit In No No No Yes 3673 TOHIR” сredit long LLC "FRYON FABARET" 72 600,0 fruit In No No No Yes 3673 сredit FARM "ERMUMINOVLAR long 84 100,0 fruit In No No No Yes 3673 UZUMZORI" сredit FARM " KARIMOV long 84 115,0 fruit In No No No Yes 3673 BEKMUROD" сredit long LLC "JUMA TURSUNOV" 84 68,0 fruit In No No No Yes 3673 сredit long "HOLBI MOMO" LLC 84 40,0 fruit In No No No Yes 3673 сredit " SANAOT long 84 90,0 fruit In No No No Yes 3673 EXPORT " LLC сredit long "OZOD ELBEGI " LLC 84 50,0 fruit In No No No Yes 3673 сredit "UMIDULLA long 84 50,0 fruit In No No No Yes 3673 CHORIYEVLAR" PE сredit "OQTEPA BARAKALI long BALIQCHILIK VA 84 90,0 fruit In No No No Yes 3673 сredit CHORVACHILIK" LLC LLC "JIANSHENG INTERNATIONAL long 84 1 000,0 fruit In No No No Yes 3673 AGRICULTURAL сredit TECHNOLOGY" PE " VOHIDJON long 84 1 500,0 fruit In No No No Yes 3673 UNIVERSAL HAMKOR” сredit PE " HUSEYN long 84 1 500,0 fruit In No No No Yes 3673 UNIVERSAL HAMKOR” сredit PE " BUNYODKORBEK long 84 1 500,0 fruit In No No No Yes 3673 UNIVERSAL HAMKOR” сredit PE " ULUG'OBOD IXLOS long 84 1 500,0 fruit In No No No Yes 3673 BARAKA” сredit PE " SUNNATILLO long 84 600,0 fruit In No No No Yes 3673 HAMKOR FAYZ" сredit PE " OTABEK long 84 1 500,0 fruit In No No No Yes 3673 UNIVERSAL HAMKOR" сredit PE " ILHOMJON long 84 1 500,0 fruit In No No No Yes 3673 UNIVERSAL HAMKOR" сredit PE " SAYHUN HAMKOR long 84 1 500,0 fruit In No No No Yes 3673 BIZNES" сredit PE " MUHIDDIN SIFAT long 84 1 500,0 fruit In No No No Yes 3673 BARAKA" сredit PE " MURODJON IXLOS long 84 1 500,0 fruit In No No No Yes 3673 BARAKA" сredit LLC "PROMEAT long 84 945,0 fruit In No No No Yes 3673 GULISTAN" сre dit LIMON long 84 324,0 fruit In No No No Yes 3673 EXPORT LLC” сredit LLC "SAMARQAND long 84 950,0 fruit With No No No Yes 3673 MEVALARI" сredit SP LLC "SAMARKAND long 84 345,0 fruit With No No No Yes 3673 GARDEN PLAST" сredit long LLC "KRAS NET SERVIS" 72 1 250,0 fruit In No No No Yes 3673 сredit LLC "O'ZMATBAA- long 84 1 705,0 fruit With No No No Yes 3673 TA'MINOT" сredit FARM "BOG’BON long 84 880,0 fruit In No No No Yes 3673 SARKOR" сredit LLC "FARG’ONA long 84 1 250,0 fruit In No No No Yes 3673 LIMONLARI -1" сredit LLC "FAR YOZ long 84 297,0 fruit In No No No Yes 3673 INNOVATSIYA" сredit FARM "MARD long 84 460,0 fruit In No No No Yes 3673 JALOLIDDIN" сredit LLC "ZILOLA long 84 258,7 fruit In No No No Yes 3673 ZUFAR AGRO" сredit

67 LLC “AGRO long 84 600,0 fruit In No No No Yes 3673 SAVDO URGENCH" сredit "MUZAFFAR long HURSANDBEK 84 444,0 fruit In No No No Yes 3673 сredit DAVLATBEK " LLC SE "QORAQOSH SAVDO long 84 298,0 fruit In No No No Yes 3673 INVEST" сredit LLC "SIROJIDDIN FRUIT long 84 370,0 fruit In No No No Yes 3673 GARDEN" сredit long LLC "BEK OSIYO TRANS" 60 550,6 fruit With No No No Yes 3673 сredit LLC " WARM- long 84 265,0 fruit In No No No Yes 3673 HOUSE" сredit LLC "FAYZ BARAKA long 72 330,0 fruit In No No No Yes 3673 XORA ZM" сredit "BOG'OLON GREEN long 84 60,0 fruit In No No No Yes 3673 HOUSE" LLC сredit "SHUXRAT GREEN long 84 264,0 fruit In No No No Yes 3673 GROUP" LLC сredit long "ELEGANT GIGANT " LLC 84 396,0 fruit In No No No Yes 3673 сredit "YANGIBOZOR AGRO long 84 396,0 fruit In No No No Yes 3673 HOLDING" LLC сredit LLC "KUDEKOV long 84 270,0 fruit In No No No Yes 3673 JADIGER" сredit LLC "ETTI XAZINA long 84 400,0 fruit In No No No Yes 3673 MO’JIZASI" сredit LLC "ILXAM AGRO long 96 870,0 fruit In No No No Yes 3673 TEPLITSA" сredit long LLC "UMIDBEK ODILBEK" 84 870,0 fruit In No No No Yes 3673 сredit LLC "CHANDLER long 84 110,0 fruit With No No No Yes 3673 INTENSIV BOG'I" сredit long LLC "BUYUK SHER" 84 50,0 fruit In No No No Yes 3673 сredit LLC "TOZA URUG' long 84 600,0 fruit In No No No Yes 3673 NASLLI CHORVA" сredit LLC "GO'ZAL BOG'LAR long 84 47,9 fruit With No No No Yes 3673 NA'MUNASI" сredit long LLC "YURT MANZARASI" 84 115,0 fruit In No No No Yes 3673 сredit LLC "BARAKALI long 84 300,0 fruit With No No No Yes 3673 CHANDLER" сredit LLC "YANGIOBOD long 84 72,0 fruit In No No No Yes 3673 XOVOS" сredit LLC "EAST-WEST long 84 191,6 fruit With No No No Yes 3673 SURXON" сredit LLC "EAST-WEST long 84 3 302,0 fruit With No No No Yes 3673 SURXON" сredit long “VIT-XIM-MED” LLC 60 130,0 fruit In No No No Yes 3673 сredit long LLC "KESH-AZIZ-SHIFO" 84 200,0 fruit In No No No Yes 3673 сredit LLC "KESH GLOBAL long 84 300,0 fruit In No No No Yes 3673 STROY SERVIS" сredit LLC "YANGI HAYOT long 84 300,0 fruit In No No No Yes 3673 CHORVA INVEST" сredit long LLC "VALI AGRO" 84 840,0 fruit In No No No Yes 3673 сredit LLC "BULUNG’UR MEVA- long 84 932,0 fruit In No No No Yes 3673 SABZAVOT" сredit LLC "PACKING long 84 834,5 fruit With No No No Yes 3673 INDUSTRIES" сredit LLC "MIRAXIMOV long MIRBOSIT MIRISHKOR 84 500,0 fruit In No No No Yes 3673 сredit INVEST" LLC "ZAMIN AGRO long 60 753,0 fruit In No No No Yes 3673 EXPERT" сredit LLC "MARGILON long 84 2 500,0 fruit In No No No Yes 3673 GAZAVTOMATIKA" сredit JV LLC " BULUNGUR- long 84 806,9 fruit With No No No Yes 3673 SANDVIK" сredit LLC "DRIED long 84 924,1 fruit With No No No Yes 3673 INGREDIENTS" сredit long LLC "BEST-VEG FARM" 84 826,7 fruit With No No No Yes 3673 сredit LLC "TO'RAQO'RG'ON long 84 834,5 fruit With No No No Yes 3673 SHIRINLIK AGRO" сredit

68 LLC "ZIYO FRUITS long 84 72,0 fruit With No No No Yes 3673 WORLD" сredit D. Environmental and Social Management System (SPSU) REQUIREMENT: (1) FOR FURTHER SUBPROJECTS: ATTACHED MONITORING REPORTS OR PERMIT ISSUANCE REPORT; (2) FOR NEWLY APPROVED SUBPROJECTS: ATTACHED DOCUMENT ON APPROVAL OF THE ZVOS.

Policies and processes Well no Does your organization To describe I instrument on SPSU have developed and Yes to this report attached implemented SPSU? Is there an existing SPSU, has this system been updated or the policies and Not procedures adopted by your organization for the reporting period? Has senior management signed updated policy / Not procedure documents? Naz start your organization persons from respectively for 2 UECD coordinators and 20 UECD Yes the implementation of coordinators from bank branches SPSU? Provide details of any operations rejected due to concerns about Not environmental and / or social is sues. Indicate any difficulties and / Submission of reports on the ADB or limitations associated with Yes project in a foreign language the implementation of SPSU. Describe how you will ensure the work of On the basis of the credit in the companies conducting your contract in and under the laws of the sub - project and their Republic of Uzbekistan the borrower sub - projects in accordance is obliged to fulfill all obligations on with national laws and the implementation of existing regulations, as well as requirements for environmental established requirements of protection measures ADB. Report any significant social and environmental issues related to customers that Not arose during the reporting period. If the current SPSU is not fully functional, what will be Not the action plan of your organization? Potential Well no Provide the name and Khamraev Zukhriddin At all trainings conducted by ARSP

69 contact details of the (tel:202-01-01 and ADB specialist or environmental / ext.160) social coordinator who has overall responsibility for the implementation of the MPS. Provide the names of other actors in the organization Dustov Alisher The Bank holds training responsible for SPSU and (tel:202-01-01 seminars for branch specialists in participating in the ext.265) each quarter of the year. implementation of this system. What was the budget The sum of n eznachiteln th , as allocated to SPSU and its the coordinator of UESR are active implementation during the professionals bank branch year? Monitoring Well no Do you receive reports on monitoring environmental and social issues from the Yes supporting documents attached companies that sponsor subprojects funded by you? Do you check the level of According to the legislation of the current implementation by Republic of Uzbekistan, the the company conducting implementation of national your subproject, national standards and any standards and any other Yes other environmental requirements is requirements? controlled by state bodies. The Bank monitors the project to implement their mitigation measures. Describe how you monitor Coordinator of the subproject is the companies carried out on-site monitoring of the responsible for your object space and to subproject and the social base e acknowledging x document s and environmental indicators being monitored, studied performing of their subproject. Yes initiated subproject implementation of all obligations under the existing requirements for environmental protection measures, spelled out in the EIS and in the conclusion of the state ecological expertise. Do you require the initiator of The initiator of the subproject is the the subproject to provide you Coordinator UESR evidence of with confirmation of compliance with the required compliance with the environmental and social approving necessary environmental Yes documents and permits, to and social approving base e which UESR Coordinator documents and permits for monitors and provides managers subprojects? UESR for dalneyschem formation of SPSU reporting. Provide details of any accidents / litigation / Not complaints / regulatory notices and fines:

70 - any cases of non- compliance with applicable environmental and social requirements - mandatory conditions / counter conditions put forward by the financial organization in relation to the company conducting the subproject as a result of any non-compliance with the requirements Reporting Well no Is there a procedure adopted There is a position of the by the organization department in charge according to which it is of international credit lines. On the necessary to report on social basis of th position Yes and environmental issues to manager UESR collects all project senior management? reporting coordinator UESR quarterly and provides the bank's management. Are you preparing any social and environmental reports: - for other multilateral AKB Turonbank social and institutions Not environmental reports provided only - other interested parties by ADB - as part of environmental and social reporting Sustainability Reports

Activities listed in ADB's List of Prohibited Investment Activities If any, indicate the dollar denominated percentage of loans or investments from the outstanding receivables of your customers that essentially fall under the ADB's List of 0% Prohibited Investment Activities (see page 122 of the ADB Safeguards Policy Statement). If the percentage is not zero, explain these There is no loan that essentially falls debts, as well as any steps that have been under the “List of prohibited investment taken to reduce them. activities” by ADB

E. Category B subprojects that use ADB funds. Provide information on all new subprojects using ADB loan financing that were approved during this reporting period.

Name of the company conducting the LLC "SARBON ASL SAVDO" sub - project: Location of the sub - project: Bukhoro Shahar Mustakillik kuchasi 72/2- UY 51-khona Fruit and vegetable sector: Creation of a greenhouse complex on 2 ha. Amount owed (USD): 440 000 USD Has your organization conducted an It was carried out. Coordinator of the sub-

71 environmental and social pre-investment project was carried out on-site inspection audit? of the object space and the base e of supporting documents on the Safeguards and developm n Environmental Management Plan. Have any audit or environmental assessment Yes. The Bank reviewed the EIA and the reports been reviewed by your organization? conclusions of the state environmental review. What were the main environmental issues The formation of construction, household, associated with this subproject that were household, food waste. The project initiator identified during the pre-investment audit was tasked with taking the waste to conducted in your organization, and what especially remote locations. measures were taken on the issues (i.e. the results of the pre-investment audit)? Did you discuss with the initiator of the Yes. subproject the current requirements for protective measures on environmental and social issues and their implementation? Does the subproject comply with current Yes. government requirements? Does the subproject comply with ADB’s Yes. current safeguards requirements? Have there been any recorded cases of non- Not. compliance or requests for corrective action? Are there any complaints or complaints filed Not. with respect to the subproject by any affected person or interested party?

Name of the company conducting the LLC "BANOAZ TEKSTIL" sub - project: Location of the sub - project: , Bukhara city, S. Zhura street, 11-house Fruit and vegetable sector: Creation of a greenhouse complex on 1 ha. Amount owed (USD): 35 0 000 US D Has your organization conducted an It was carried out. Coordinator of the sub- environmental and social pre-investment project was carried out on-site inspection audit? of the object space and the base e of supporting documents on the Safeguards and developm n Environmental Management Plan. Have any audit or environmental assessment Yes. The Bank reviewed the EIA and the reports been reviewed by your organization? conclusions of the state environmental review. What were the main environmental issues The formation of construction, household, associated with this subproject that were household, food waste. The project initiator identified during the pre-investment audit was tasked with taking the waste to conducted in your organization, and what especially remote locations. measures were taken on the issues (i.e. the results of the pre-investment audit)? Did you discuss with the initiator of the Yes. subproject the current requirements for protective measures on environmental and

72 social issues and their implementation? Does the subproject comply with current Yes. government requirements? Does the subproject comply with ADB’s Yes. current safeguards requirements? Have there been any recorded cases of non- Not. compliance or requests for corrective action? Are there any complaints or complaints filed Not. with respect to the subproject by any affected person or interested party?

LLC "BUXORO INTERKONTINENTAL" Sub-project location: Bukhara region, Bukhara district, Cuticular SSG, Bukhara street Agro-Free economic zone Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 3 ha. The amount arrears (United States 840 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an envir onmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "UMARBEK BUSINESS CLASS" Sub-project location: Bukhara region, Fruit and vegetable sec tor: Creation of a greenhouse complex on 2.0 ha.

73 The amount arrears (United States 106 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered does Your Yes. reviewed by an ATM ZVS and organization have any audit reports or a conclusions of the state environmental report on environmental assessment? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "O'RTACHO'L MEVA-SABZAVOT" Sub -project location: Bukhara region, Zhandar district Fruit and vegetable sector: Creation of a greenhouse complex on 1.5 ha. The amount arrears (United States 540 000 000,0 dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)?

74 Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

Name of the company leading the sub- LLC "ZOHID OZOD KELAJAGI" project: Sub-project location: Bukhara region, BooArsky district, mahalla Logicalorsky the village Panzha Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 1,5 ha. The amount arrears (United States 350 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions?

75 Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

Name of the company leading the sub- LLC "TEXCHORVA SERVIS" project: Sub-project location: Kashadrinska region, Karshi st. Ipak Yuli 1 Fruit and vegetable sector: Creation of a greenhouse complex on 3.0 ha. The amount arrears (United States 564 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "SAPAR BOBO NABIRASI JAVOXIRI" Sub-project location: Kashkadarya region, Karshi district, mahalla Batosh Fruit and vegetable sector: Creation of a greenhouse complex on 5.0 ha. The amount arrears (United States 1 300 000 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan.

76 Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection mea sures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "EXPRESS TEMIR- CONCRETE SERVICE" Sub-project location: Kashkadarya region, Karshi district, mahalla Bato sh Fruit and vegetable sector: Creation of a greenhouse complex on 4.0 ha. The amount arrears (United States 1 040 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes.

77 state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "BO’RI DEVONBEGI" Sub-project location: Toescadaria region, Miaskowski district, array Mirishkor Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 1,8 ha. The amount arrears (United States 400 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

PE " MUBORAK JAGUAR" Sub-project location: Kashkadarya region, Mubarak district, SSG Sarik Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha.

78 The amount arrears (United States 130 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental man agement plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measu res? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

PE "OYDIN OHUNOVA" Sub-project location: Kashkadarya region, Dehkanabad district, M. Akhmedov street, M. Tursunzoda SSG Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 130 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)?

79 Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "JEYNOV MEBEL GOLD" Sub-project location: Kashkadarya region Ministarski district, town Mirishkor Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 100,000,000 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's sa feguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "LIMO LAYM"

80 Sub-project location: Kashkadarya region, Karshi district, massif Otchopar Fruit and vegetable sector: Creation of a greenhouse complex for 1,3 ha. The amount arrears (United States 90 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

Name of the company leading the sub- LLC "ZARAFSHON GRAND BOG'LARI" project: Sub-project location: Navoi region, Karmana district district, village Malik Works Fruit and vegetable sector: Creation of a greenhouse complex on 3.0 ha. The amount arrears (United States 2 065 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your or ganization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of

81 identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "SHERKHON OIL" Sub-project location: Navaginskaya region Cizimlerini district, Mulakrobat SSG Fruit and vegetable sector: Creation of a greenhouse complex on 2.0 ha. The amount arrears (United States 490 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection me asures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions?

82 Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

FH " ADIZBOBO" Sub-project location: Navaginskaya the area of KiziltepeandItalian district, Akmescid SSG. Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 10,0 ha. The amount arrears (United States 628 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "NAVBAHOR AGRO LIMON" Sub-project location: Navaginskaya region Nabakowski district, Uzbekistanskiy SSG Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 3,0 ha. The amount arrears (United States 1 050 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an

83 environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

Name of the company leading the sub- LLC "ZARAFSHON GRAND BOG'LARI" project: Sub-project location: Navoi region, Karmana district district, village Malik Works Fruit and vegetable sector: Creation of a greenhouse complex on 3.0 ha. The amount arrears (United States 1 325 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes.

84 state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

Farm "VODIY AGRO COMPLEX" Sub-project location: Namangan region Yanikurganskiy district, SSG Huracan Fruit and vegetable sector: Creation of a greenhouse complex on 2.0 ha. The amount arrears (United States 520 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

Name of the company leading the sub- LLC "QO’SHXOVUZ" project: Sub-project location: Samarkand region, Kattakurgon district, A. Navoi street

85 Fruit and vegetable sector: Creation of a greenhouse complex on 10.0 ha. The amount arrears (United States 2 500 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "NARPAY XOSILBEK AGRO" Sub-project location: Samarkand region Karpinski district, SSG Tepa Fruit and vege table sector: Creation of a greenhouse complex on 2.0 ha. The amount arrears (United States 330 000 000,0 dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, eespecially remote places.

86 and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "SHURCI FURNITURE" Sub-project location: Surkhandarya region, The Shurchi district Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 1,0 ha. The amount arrears (United States 98 600,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective act ions? Have there been any complaints or No. complaints made about the subproject by

87 any affected person or interested party?

FARM " NUROBOD" Sub -project location: Surkhandarya region, The Shurchi district Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 1,0 ha. The amount arrears (United States 185 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

FARM "SOBIR ABDIMURODOV" Sub-project location: Surkhandarya region Altinsay district Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 70 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre - conducted an on-site inspection of the investment review? facility and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your expertise.

88 organization? What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The identified during the pre -investment initiator of the project was instructed to review conducted in Your take waste to especially remote places. organization, and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "MARHAMAT TOHIR” Sub -project location: Surkhandarya region, region district Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 255 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements?

89 Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

ООО "FRYON FABARET" Sub -project location: Surkhandarya region, Termez region district Fruit and vegetable sector: Creation of a greenhouse complex on 2,0 ha. The amount arrears (United States 600 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

FARM "ERMUMINOVLAR UZUMZORI" Sub-project location: Surkhandarya region, Kumkurgan district Fruit and vegetable sector: Creation of a greenhouse co mplex on 1,0 ha. The amount arrears (United States 100 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and b ased on supporting documents on

90 protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

FARM "KARIMOV BEKMUROD" Sub-project location: Surkhandarya region, Denau district Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 115 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements?

91 Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "JUMA TURSUNOV" Sub -project location: Surkhandarya region, Denau district Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 68 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

"HOLBI MOMO" LLC Sub-project location: Surkhandarya region, Termez region district Fr uit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 40 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on

92 protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "DENOV SANAOT EXPORT" Sub-project location: Surkhandarya region, Denau district Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 90 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implem entation? Does the subproject meet the current Yes. state requirements?

93 Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "OZOD ELBEGI" Sub -project location: Surkhandarya region, The Shurchi district Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 50 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

"UMIDULLA CHORIYEVLAR" SP Sub-project location: Surkhandarya region, Denau district Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 50 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting docu ments on

94 protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "OQTEPA BARAKALI BALIQCHILIK VA CHO RVACHILIK" Sub-project location: Surkhandarya region, Gargulinski district Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 90 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes.

95 state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

Name of the company leading the sub- LLC "JIANSHENG INTERNATIONAL project: AGRICULTURAL TECHNOLOGY" Sub-project location: Syrdarya region, district , SSG Hakikat Fruit and vegetable sector: Creation of a greenhouse complex on 3.0 ha. The amount arrears (United States 1 000 000,0 United States dollars dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

PE "VOHIDJON UNIVERSAL HAMKOR” Sub-project location: Syrdarya region, Mirzaabad district, SIU Okoltin Fruit and vegetable sector: Creation of a greenhouse complex on 5.0 ha.

96 The amount arrears (United States 1 500 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected p erson or interested party?

PE "BUNYODKORBEK UNIVERSAL HAMKOR” Sub-project location: Syrdarya region, Mirzaabad district, SIU Okoltin Fruit and vegetable sector: Creation of a greenhouse complex on 5.0 ha. The amount arrears (United States 1 500 000,0 USD dollars ): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e.,

97 the results of the pr e -investment review )? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

PE "ULUG'OBOD IXLOS BARAKA” Sub-project location: Syrdarya region, Mirzaabad district, SIU Okoltin Fruit and vegetable sector: Creation of a greenhouse complex on 5.0 ha. The amount arrears (United States 1 500 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

98

PE "OTABEK UNIVERSAL HAMKOR" Sub-project location: Syrdarya region, saikhunabad district, SIU Surasak Fruit and vegetable sector: Creation of a greenhouse complex on 5.0 ha. The amount arrears (United States 1 500 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

PE "ILHOMJON UNIVERSAL HAMKOR" Sub-project location: Syrdarya region, saikhunabad district, SIU Surasak Fruit and vegetable sector: Creation of a greenhouse complex on 5.0 ha. The amount arrears (United States 1 500 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of

99 identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

PE "SAYHUN HAMKOR BIZNES" Sub-project location: Syrdarya region, saikhunabad district, SIU Surasak Fruit and vegetable sector: Creation of a greenhouse complex on 5.0 ha. The amount arrears (United States 1 500 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions?

100 Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

PE "MUHIDDIN SIFAT BARAKA" Sub-project location: Syrdarya region, saikhunabad district, SIU Surasak Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 5,0 ha. The amount arrears (United States 1 500 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affecte d person or interested party?

PE "MURODJON IXLOS BARAKA" Sub-project location: Syrdarya region, saikhunabad district, SIU Surasak Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 5,0 ha. The amount arrears (United States 1 500 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an

101 environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "PROMEAT GULISTAN" Sub-project location: Syrdarya region, Khavas district, SIU Kh.Narchaev Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 3,5 ha. The amount arrears (United States 945 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes.

102 state re quire ments? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

“GULISTON LIMON EXPORT ” LLC Sub-project location: Syrdarya region, Belovodski district Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 1,5 ha. The amount arrears (United States 324 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "KRAS NET SERVIS" Sub-project location: Tashkent region area, Kuyichirchik district district Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 3,5 ha. The amount arrears (United States 1 250 000,0 USD

103 dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

Name of the company leading the sub- FARM "BOG’BON SARKOR" project: Sub-project location: Ferghana region, Tashlak district, Zarkent SSG, massif Turbat Fruit and vegetable sector: Creation of a greenhouse complex on 3.0 ha. The amount arrears (United States 880 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)?

104 Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "FARG’ONA LIMONL ARI -1" Sub-project location: Ferghana region, Ferghana district, Ilgor SSG, Yangi ASR street Fruit and vegetable sector: Creation of a greenhouse complex on 5.0 ha. The amount arrears (United States 1 250 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

105

LLC "FAR YOZ INNOVATSIYA" Sub-project location: Fergana region Tavanski district, Virgance SSG Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 297 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

Name of the company leading the sub- FARM "MARD JALOLIDDIN" project: Sub-project location: Khorezm the area of Yangibazar district, Syringomyelia SSG Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 460 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues - Education construction, household,

106 related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions - Storage of pesticides/ herbicides. Organize were made on the following issues: (i.e., specifically a sheltered, protected and clearly the results of the pre -investment review)? marked place. Marking boxes/ bags/ containers. Train personnel in handling, using, and disposing of pesticides Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "ZILOLA ZUFAR AGRO" Sub-project location: Khorazm region, Urganchi district, settlement street Kungirot Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 258 700,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safegu ard

107 measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC “AGRO SAVDO URGENCH" Sub-project location: Khorazm region, Urgench district, Bekabad, Kungirat mahalla Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 2,0 ha. The amount arrears (United States 600 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their im plementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party? LLC "MUZAFFAR HURSANDBEK DAVLATBEK" Sub-project location: Horezmskaya region Chencinski district, SSG Nawas street Fruit and vegetable sector: Creation of a greenhouse complex on 1.5 ha. The amount arrears (United States 444 000,0 USD dollars):

108 Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organizati on? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

SE "QORAQOSH SAVDO INVEST" Sub-project location: Khorazm region, khonka district, town Coracos street Street Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 298 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes.

109 the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "SIROJIDDIN FRUIT GARDEN" Sub-project location: Horezmskaya region Jasarevski district, village Pitnak, array Мирзо Улуғбек Fruit and vegetable sector: Creation of a greenhouse complex on 1.25 ha. The amount arrears (United States 370 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

110

LLC "HAZORASP WARM -HOUSE" Sub-project location: Khorazm province, Khazarasp district, Gorodok Piciocchi street Piciocchi. Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 265 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "FAYZ BARAKA XORAZM" Sub-project location: Khorazm region, Urgench district. Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 330 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of

111 identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "BOG'OLON GREEN HOUSE" Sub -project location: Khorazm region, Yangibazar district. Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 60 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions?

112 Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "SHUXRAT GREEN GROUP" Sub -project location: Khorazm region, Yangibazar district. Fruit and vegetable sector: Creation of a greenhouse complex on 3.0 ha. The amount arrears (United States 264 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "ELEGANT GIGANT" Sub-project location: Khorazm region, Yangibazar district. Fruit and vegetable sector: Creation of a greenhouse complex on 3.0 ha. The amount arrears (United States 396 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental

113 assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the re sults of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "YANGIBOZOR AGRO HOLDING" Sub-project location: Khorazm region, Yangibazar district. Fruit and vegetable sector: Creation of a greenhouse complex on 3.0 ha. The amount arrears (United States 396 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures?

114 Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "ETTI XAZINA MO’JIZASI" Sub-project location: Karakalpak Republic Republic Shumanai district, SSG Begab Fruit and vegetable sector: Creation of a greenhouse complex on 1.5 ha. The amount arrears (United States 400 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "UMIDBEK ODILBEK" Sub-project location: Republic Karakalpakistan, district Fruit and vegetable sector: Creation of a greenhouse complex on 3.0 ha. The amount arrears (United States 870 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility

115 review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "YANGIOBOD XOVOS" Sub-project location: Jizzakh region Anyobody district Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States 72 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation?

116 Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested pa rty?

“VIT-XIM-MED” LLC Sub-project location: Tashkent region, Yangiyul district, massif Dustlik Fruit and vegetable sector: Creation of a greenhouse complex on 0.76 ha. The amount arrears (United States 130 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state r equirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

Name of the company leading the sub- LLC "FAYZ BARAKA XORAZM" project:

117 Sub -project location: Kashkadarya region, Shakhrisabz dist rict Fruit and vegetable sector: Creation of a greenhouse complex on 3.0 ha. The amount arrears (United States 300 000,0 USD dollars): Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility review? and based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any Yes. reviewed by an ATM ZVS and audit reports or environmental conclusions of the state environmental assessment reports in Your organization? expertise. What were the main environmental issues Education construction, household, related to this subproject that were household, and food waste. The initiator of identified during the pre -investment the project was instructed to take waste to review conducted in Your organization, especially remote places. and what measures were taken decisions were made on the following issues: (i.e., the results of the pre -investment review)? Have you discussed with the initiator of Yes. the subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current Yes. state requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of No. non -compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person o r interested party?

LLC "YANGI HAYOT CHORVA INVEST" Sub-project location: Kashkadarya region, Shakhrisabz district Fruit and vegetable sector: Creation of a greenhouse complex on 1,0 ha. The amount arrears (United States dollars): 300 000,0 USD Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility and review? based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any audit Yes. reviewed by an ATM ZVS and conclusions reports or environmental assessment reports of the state environmental expertise. in Your organization? What were the main environmental issues Education construction, household, household, related to this subproject that were identified and food waste. The initiator of the project was during the pre -investment review conducted instructed to take waste to especially remote in Your organization, and what measures places. were taken decisions were made on the following issues: (i.e., the results of the pre - investment review)?

118 Have you discussed with the initiator of the Yes. subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current state Yes. requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of non - No. compliance or requests for co rrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "MIRAXIMOV MIRBOSIT MIRISHKOR INVEST" Sub-project location: Tashkentlast name regionb, Kibray RAyon, 21 Mi rabad street Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 2,0 ha. The amount arrears (United States dollars): 500 000,0 USD Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility and review? based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any audit Yes. reviewed by an ATM ZVS and conclusions reports or environmental assessment reports of the state environmental expertise. in You r organization? What were the main environmental issues Education construction, household, household, related to this subproject that were identified and food waste. The initiator of the project was during the pre -investment review conducted instructed to take waste to especially remote in Your organization, and what measures places. were taken decisions were made on the following issues: (i.e., the results of the pre - investment review)? Have you discussed with the initiator of the Yes. subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current state Yes. requirement s? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of non - No. compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "ZAMIN AGRO EXPERT" Sub -project location: Tashkent last name region b, Zangiota rAyo n. Fruit and vegetable sector: Creation of a greenhouse complex on the territory of 2,0 ha. The amount arrears (Uni ted States dollars): 753 000,0 USD Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility and

119 review? based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any audit Yes. reviewed by an ATM ZVS and conclusions reports or environmental assessment reports of the state environmental expertise. in Your organization? What were the main environmental issues Education construction, household, household, related to this subproject that were identified and food waste. The initiator of the project was during the pre -investment review conducted instructed to take waste to especially remote in Your organization, and what measures places. were taken decisions were made on the following issues: (i.e., the results of the pre - investment review)? Have you discussed with the initiator of the Yes. subproject the current requirements of environmental and social protection measures and their impleme ntation? Does the subproject meet the current state Yes. requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of non - No. compliance or requests for corrective actions? Have there been any complaints or No. complaints made about the subproject by any affected person or interested party?

LLC "MARG ’ILON GAZAVTOMATIKA" Sub -project location: Tashkent region, Kuyic hirchik district Fruit and vegetable sector: Creation of a greenhouse complex on 10.0 ha. The amount arrears (United States dollars): 2 500 000,0 USD Did your organization conduct an Was conducted. The sub-project coordinator environmental and social pre -investment conducted an on-site inspection of the facility and review? based on supporting documents on protective measures and developed an environmental management plan. Were they considered do you have any audit Yes. reviewed by an ATM ZVS and conclusions reports or environmental assessment reports of the state environmental expertise. in Your organization? What were the main environmental issues Education construction, household, household, related to this subproject that were identified and food waste. The initiator of the project was during the pre -investment review conducted instructed to take waste to especially remote in Your organization, and what measures places. were taken decisions were made on the following issues: (i.e., the results of the pre - investment review)? Have you discussed with the initiator of the Yes. subproject the current requirements of environmental and social protection measures and their implementation? Does the subproject meet the current state Yes. requirements? Does the subproject meet the current Yes. requirements ADB's safeguard measures? Have there been any recorded cases of non - No. compliance or requests for corrective actions? Have there been any complaints or No.

120 complaints made about the subproject by any affected person or interested party?

Sub projects categories "C", which uses ADB funds. The amount sub- Initiator of the sub- Sub-project Goal Footing classification of the sub- № credit (thoU project location sub-project project into the "C" category" SDnds of USD)

Purchase of According to the ADB system based on equipment for the requirements of protective measures processing fruits and 1 (environment Wednesday) purchase of LLC "SHIRIN NIYAT Kashkadarya 1 4 500,0 vegetables and equipment for processing fruits and BARAKA" region, Karshi purchasing cold storage vegetables and purchasing cold storage rooms with a capacity rooms with a capacity of 4000 tons of 4000 tons classified like the "C" category" According to the ADB system based on the requirements of protective measures Kashkadarya Purchase of cold storage 1 (environment Wednesday) Purchase of 2 LLC METIN TEKSTIL" 1 198,0 region, Karshi units with a capacity of cold storage facilities with a capacity of 2000 tons classified like the "C" catego ry" According to the ADB system based on Samarkand the requirements of protective measures Purchase of cold storage LLC "JOMBOY GOLDEN region 1 (environment Wednesday) Purchase of 3 1 040,0 units with a capacity FRUITS" Bulungur cold storage rooms with a capacity of of 3,000 tons district 3 000 tons of classified like the "C" category" According to the ADB system based on Samarkand the requirements of protective measures Purchase of cold storage LLC "EXPRESS TRADE region 1 (environment Wednesday) Purchase of 4 238,0 units with a capacity ORGANIZATION" Zhambay cold storage facilities with a capacity of 500 tons district of 500 tons classified like the "C" category"

Samarkand According to the ADB system, based on LLC "PURE FREEZING region Purchase of cold storage 5 750,0 the requirements of protective measures, SERVIСЕ" Bulungur units with a capacity of it is classified like the "C" category" district

Purchase of According to the ADB system based on equipment for the requirements of protective measures Samarkand processing fruits and LLC "ASIA AGRO 1 (environment Wednesday) Purchase of 6 region 500,0 vegetables and PRODUCTS" cold storage facilities with a capacity district purchasing cold storage of 300 tons classified like the "C" rooms with a capacity category" of 300 tons According to the ADB system based on Surkhandarya the requirements of protective measures region, Purchase of cold storage 1 (environment Wednesday) Purchase of 7 LLC "FRYON FABARET" 600,0 Shurchi units with a capacity of cold storage facilities with a capacity district of 300 tons classified like the "C" category" According to the ADB system based on Surkhandarya Purchase of the requirements of protective measures LLC "SAMARQAND region, equipment for 1 (environment Wednesday) Purchased 8 939,9 MEVALARI" Termez processing fruits and equipment for processing fruits and district vegetables vegetables classified like the "C" category" According to the ADB system based on Samarkand Purchase of the requirements of protective measures SP LLC "SAMARKAND region equipment for 1 (environment environment) Purchase 9 345,0 GARDEN PLAST" Bulungur processing fruits and of equipment for processing fruits and district vegetables vegetables classified like the "C" category" According to the ADB system based on Ferghana Creating a modern the requirements of protective measures 10 LLC "BEK OSIYO TRANS" region, 550,6 website Agricultural 1 (environment Wednesday) Creating a Ferghana city logistics complex modern agrologistic complex is classified as like the "C" category" According to the ADB system based on Khorezm the requirements of protective measures LLC "CHANDLER region 1 11 110,0 Intensive garden INTENSIV BOG'I" Khazarasp (environment Wednesday) Creation Inte district nsive care classified like the "C" category"

121 According to the ADB system based on the requirements of protective measures LLC "GO'ZAL BOG'LAR Sh.Rashidov Creation Intensive 1 12 47,9 NA'MUNASI" district garden on 8.0 ha (environment Wednesday) Creation Inte nsive care classified like the "C" category" According to the ADB system based on the requirements of protective measures Jizzakh region LLC "BARAKALI 1 13 Bakhmala 300,0 Intensive garden CHANDLER" (environment Wednesday) Creation Inte district nsive care classified like the "C" category" According to the ADB system based on Purchase of the requirements of protective measures LLC "EAST-WEST Gallaaral equipment for 1 (environment environment) Purchase 14 3 493,6 SURXON" district processing fruits and of equipment for processing fruits and vegetables vegetables classified like the "C" category" According to the ADB system based on Surkhandarya Purchase of the requirements of protective measures LLC "EAST-WEST region equipment for 15 191,6 1 (environment Wednesday) Creating a SURXON" Altynsarinskiy processing fruits and modern agrologistic complex is classified district vegetables as like the "C" category" According to the ADB system based on the requirements of protective measures Purchase of cold storage 1 (environment Wednesday) Purchase of 16 LLC "VALI AGRO" Ferghana city 840,0 units with a capacity cold storage facilities with a capacity of 2,000 tons of 2,000 tons classified like the "C" cat egory" According to the ADB system based on Tashkent the requirements of protective measures Purchase of cold storage LLC "BULUNG’UR MEVA- region 1 (environment Wednesday) Purchase of 17 932,0 units with a capacity SABZAVOT" Yangiyul cold storage facilities with a capacity of 2,000 tons district of 2,000 tons classified like the "C" category" According to the ADB system based on Tashkent Purchase of the requirements of protective measures LLC "PACKING region equipment for 19 834,5 1 (environment environment) the INDUSTRIES" Angiotensin processing fruits and purchase of fruit processing equipment is district vegetables classified as like the "C" category"

According to the ADB system based on Samarkand Purchase of the requirements of protective measures JV LLC " BULUNGUR- region equipment for 22 806,9 1 (environment environment) the SANDVIK" Bulungur processing fruits and purchase of fruit processing equipment is district vegetables classified as like the "C" category"

According to the ADB system based on Samarkand Purchase of the requirements of protective measures LLC "DRIED region equipment for 23 924,1 1 (environment environment) the INGREDIENTS" Bulungur processing fruits and purchase of fruit processing equipment is district vegetables classified as like the "C" category"

According to the ADB system based on Tashkent Purchase of the requirements of protective measures region equipment for 24 LLC "BEST-VEG FARM" 826,7 1 (environment environment) the Yangiyul processing fruits and purchase of fruit processing equipment is district vegetables classified as like the "C" category"

According to the ADB system based on Tashkent Purchase of the requirements of protective measures LLC "TO'RAQO'RG'ON region equipment for 25 834,5 1 (environment environment) the SHIRINLIK AGRO" Yangiyul processing fruits and purchase of fruit processing equipment is district vegetables classified as like the "C" category"

According to the ADB system based on Samarkand Purchase of the requirements of protective measures LLC "EAST-WEST region equipment for 26 191,6 1 (environment Wednesday) Creating a SURXON" Bulungur processing fruits and modern agrologistic complex is classified district vegetables as like the "C" category"

Director Coordination center Investment activity and project management Z.A. Khamrayev

122 ANNUAL ENVIRONMENTAL AND SOCIAL PERFORMANCE REPORT (Contract №3673)

(To be submitted by the Bank to UZAIFSA)

12. Please provide responses to the questions below. Please include additional sheets or attachments as required to provide details on questions that have been answered Yes. The Bank is required to submit the annual performance report to UZAIFSA.

Name of the Financial Institution JSCMB “Ipoteka bank” Completed by (name): Bakhtiyor Abdusalomov Posit ion in organization: Head of Divison Date: 14.01.2020

J. Portfolio Information Report Covering Period: From: 01.01.2020 To: 31.12.2020

13. For the reporting period, please provide the following information about your portfolio where applicable:

K. Business Lines Product Description Total exposure Average loan (or line outstanding for transaction) most recent FY size (US$) end (US$)

Microfinance Loans or other financial products for 0 0% individuals Small Loans or other financial products for 0 0% business individuals Long term: Transactions with tenor greater than 12 months Microfinance Any lending, leasing or other financial 0 0 assistance to any corporate or legal entity other than an individual, with individual transactions less than $50,000 Any lending, leasing or other financial 25 000 000 100% assistance to any corporate or legal entity Small other than an individual, with individual busi ness transactions less than $300,000 Other Other (if Please describe applicable)

L. Exposure by Horticulture Sectors 14. Please provide an indicative percentage of total Innovation to horticulture modernization loan portfolio per subcomponents:

Industrial Sector % Horticulture Value Chain Develoment Project Portfolio Intensive garden Modern greenhouse complex 65% Refrigerated store 30% Equipment for processing of agriculture products 5%

{Note: Please attach environmental and social audit or due diligence reports and environmental and social monitoring reports for each Project Company, if available} 15. If engaged in long-term small business finance, please provide information on all loans with: (i) tenor longer than 12 months; and (ii) maximum $5 000,000 loan size.

123

category Safeguard ADB ADB funds Subpro-jectusing finance) the issues the Industry Sector* Any outstanding Name ofSubpro-ject Tenor of (months) loan IP IP IR IR Typeofloan SME/ trade Value ofexposure (US$) Env Env environmentaland IRand IP and and actions to taken address (yes/no) issues during reporting period

AGRO TRADE LLC credit 83 5,000.0 greenhouse B C N/A no Yes ISLOMBEK - AGRO - SERVIS credit 120 5,000.0 greenhouse B C N/A no Yes LLC Kesh Nur Makoni LLC credit 85 700.0 greenhouse B C N/A no Yes "ABLAQUL QODIR SHARIF cold credit 60 75.0 B C N/A no Yes AGRO" LLC storages "SAMARQAND AGRO GREEN credit 84 500.0 greenhouse B C N/A no Yes HOUSE" LLC cold "DIAMOND ORIGINAL" LLC credit 85 249.6 B C N/A no Yes storages cold "Samir Nuri Zamin" LLC credit 60 100.0 B C N/A no Yes storages cold "Surxon Fruits Frezer" LLC credit 61 500.0 B C N/A no Yes storages cold Istiqlol LLC credit 85 330.0 B C N/A no Yes storages NOZIMA FAYZ LLC credit 85 381.0 greenhouse B C N/A no Yes XITOY TULPORI LLC credit 85 420.0 greenhouse B C N/A no Yes RUSLANBEK MO'MINJON LLC credit 85 620.0 greenhouse B C N/A no Yes BOBOXON ALIJON LLC credit 85 420.0 greenhouse B C N/A no Yes DILOBAR MUXLISA LLC credit 83 380.0 greenhouse B C N/A no Yes ALMAZ GREEN VALLEY LLC credit 97 2,164.2 greenhouse B C N/A no Yes PROVENT AIRCOOL cold credit 60 130.0 B C N/A no Yes ENGINEERING LLC storages to produce nonalcohol "RICOMEL BEVERAGES" LLC credit 85 2,070.0 B C N/A no Yes beverages from fruits Shohjahon Ibroxim LLC credit 84 440.0 greenhouse B C N/A no Yes Exim agro logistic LLC credit 120 5 000.0 greenhouse B C N/A no Yes Piskent mega omega LLC credit 84 520.0 greenhouse B C N/A no Yes

*Please use the sectors listed in the earlier table or any standard classification. Note: Env = Environment, IR = Involuntary Resettlement, IP = Indigenous Peoples.

M. Environmental and Social Management System (ESMS)

16. REQUIREMENT : (1) FOR EXISTING SUBPROJECTS: ATTACHMENTS OF MONITORING REPORTS OR REPORT ON DISCHARGE PERMITS; AND (2) FOR NEWLY APPROVED SUBPROJECTS: ATTACHMENTS OF ZVOS APPROVAL. Policies & Processes Yes/No In connection with the implementation of the ADB project Has your organization №3673-UZB: Horticulture Value Chain Development, the developed and Yes Management Board of JSCMB "Ipotekabank" approved the implemented an ESMS? ESMS Procedures for implementation of the above Project on 24 th May 24, 2017. If there is an ESMS As part of the ongoing transformation of the bank, with the Yes already in place, have cooperation of the IFC, the Env ironmental and Social Risk

124 there been any updates to Management System has been created and is being the ESMS or policy and implemented. Developed, in accordance with the IFC procedures adopted by performance standards, the Environmental and Social Risk your organization during Management Policy and the Environmental and Social Risk the reporting period? Management Regulation (procedure). In accordance with the transformation plan, the Environmental and Social Risk Management System is being introduced into the bank's activities. Each branch has appointed persons responsible for the functioning of the Environmental and Social Risk Management System, a review mechanism, both internal and external. Work has begun on using the information disclosure mechanism. A training course was conducted with the bank's personnel on the implementation of the Environmental and Social Risk Management System. In the framework of work with ADB or other partners, the Environmental and Social Risk Management Policy provides for the possibility of using the environmental and social management system and the requirements of partners, if the Environmental and Social Risk Management System suits the partners requirements, then the Environmental and Social Management System procedure can also be used. That is, the bank will adjust the work of the Environmental and Social Risk Management System so that it suits all partners and is used in financing at the expense of all partner’s credit lines. Has senior management As indicated in the paragraphs above, the internal documents signed off on the updated Yes of the bank on ESMS were approved by the Supervisory policy/procedure? Board and the Management Board of the Bank. The Bank appointed Mr.Bakhtiyor Abdusalomov (Head of Has your organization Ecological and social risk management division) tasked to appointed staff tasked to Yes implement the ESMS. As well there are responsible for implement the ESMS? implementation ESMS from in every branch is head of credit divisions. (High education) . Please give details of any transactions rejected due During the reporting period, no rejected transactions were to environmental and/or identified. social concerns. Please state any difficulties and/or Sometimes there are some misunderstandings and constraints related to the difficulties to categorize some sub projects in requirement implementation of the ADB. ESMS. Please describe how you ensure that your subproject companies and their subprojects are Every sub projects should accord natioanal laws and norms, operated in compliance as well requirements ADB. with the national laws and regulations and applicable ADB’s requirements. Please give details of any material social and environmental issues No There are no questions during period of report. associated with clients during the reporting period. In case the existing ESMS is not fully functional, what is the action plan being Current ESMS is functional implemented by your organization?

125 Capacity Yes/No Please provide the name and contact information of the Environmental/Social Officer or Coordinator who Bakhtiyor Abdusalomov, Head of ecological and social risk has the overall management division, [email protected] responsibility for the implementation of the ESMS. Please provide current Anatoliy Kresov, main specialist of of ecological and social staffing of other core risk management division, [email protected] ESMS persons in the Yes State committee on Ecology and environmental protection. organization involved with State sanitary epidemiology service of the Republic of ESMS implementation. Uzbekistan. What was the budget allocated to the ESMS and If there is any business trips on regarding ESMS, bank pay its implementation during for this expenses and etc. the year? Monitoring Yes/No After financing subprojects, there will be done monitoring Do you receive ecology and social questions according to appendix 6, environmental and social Procedures on Environmental and Social Management for monitoring reports from Yes “Horticulture Value Chain Development” project financed by subproject companies that Asian Development Bank. Beside of this, staff will check you finance? requirements of ADB. Do you check for ongoing compliance of your In process monitoring, checking whether doing national law subproject companies with Yes norms and requirements ADB. national regulation and any other requirements? The sub-project coordinator monitors the site visits and on Please describe how you the basis of the supporting documents, monitoring is carried monitor the subproject out, the sub-project initiator fulfills all the obligations to company and their implement the current requirements for environmental subproject’s social and protection measures prescribed in the EIS and in the environmental conclusion of the state environmental review. performance.

Do you require the The initiator of the subproject submits to the ESMS subproject owner to submit Coordinator the supporting documents for compliance with to you evidence of the necessary environmental and social approving compliance with required Yes documents and permits, on the basis of which the ESMS environmental and social coordinator monitors and provides the ESMS Manager for approvals and permits for further reporting on ESMS. the subprojects. Please provide details of any accidents/ litigation/complaints/regula tory notices and fines: - Any incidents of non- compliance with the applicable Environmental No There is no any notices and fines. and Social Requirements - Covenants/conditionali ties imposed by the Financial Institution to the subproject company as a result of any non- compliance Reporting Yes/No

126 Is there an internal process On a quarterly basis, the Risk Department submits a report to report on social and Yes to the Bank's Supervisory Board on managing all types of environmental issues to bank risks, including environmental and social risks. senior management? Do you prepare any social and environmental reports: - For other multilateral agencies Yes, we provide reports to other partners of the bank too, Yes - Other stakeholders such as EBRD, IFC, etc. - E&S reporting in the Report Sustainability reports

Activities on ADB’s Prohibited Investment Activities List If any, please indicate the dollar percentage of loans or investments out of your total outstanding exposure provided to clients who are substantially involved in ADB’s Prohibited 0% Investment Activities List (Refer to page 122 of SPS). If the percentage is not zero, please explain these exposures and any steps that have been taken to reduce such exposure.

N. Category “B” Subprojects Using ADB Funds 17. Please provide information about all new subprojects using ADB loan funding approved during this reporting period.

Name of Subproject Company: "Exim agro logistic" LLC Subproject location: Bukhara region Horticulture s ector: Greenhouse Value of exposure (US$ ): 5 000,0 Was any environmental and Yes, there were carried out analysis of environmental impact social due diligence undertaken (ecological screening), as well as social safeguards screening, by your organization? safeguard due diligence briefing note during review. Review of safeguard documents and field visits had been conducted by credit expert of branch. Any environmental assessment Yes. Copy of ZVOS (statement of environmental impact) and report or audit reports reviewed positive Conclusion of State ecological expertise were inspected by by your organization? the loan specialist and ESMS coordinator. According to the mentioned Conclusion, the project is given 3th category of environmental impact. ADB environmental category B/social category (environmental resettlement) C. What were the main According to the Conclusion of State Ecological Expertise, this environmental issues project falls under the category 3 based on the resolution of the associated with this subproject Cabinet of Ministers of the Republic of Uzbekistan №541 dated that were identified through due 07/09/2020. diligence conducted by your Impact on water : Water supply of the object will be carried out by organization, and how were the water from brought by Suvsoz, distributor of drinking water. Water issues dealt with (i.e., outcome consumption for household and drinking needs of workers will be of due diligence)? 200, m3 / year. Water consumption for washing floors 100,0 m3 / year, irrigation of the territory with a ground surface-200, m3/year. Irretrievable water consumption, effluents are not formed. Waste : In the course of business activity of the site, the following waste can be generated: municipal waste-2.5 tons/year, and waste from cleaning the territory - 15.0 tons/year. The following ecological requirements must be fulfilled: - Take measures for safeguarding trees, growing at the site during construction work; - Community waste must be temporary stored in containers and after it taken to local waste site;

127 - Control keeping wasting water under sanitary norm. It is forbidden to discharge sewage water into natural open water bodies, burn waste on the territory of the site, water green plants with drinking water. Did you discuss with the Yes. Bank inspectors carefully discussed with the subproject owner subproject owner the all the requirements regarding the environmental, ecological and applicable environmental and social safeguard that he/she should meet during the social safeguard requirements implementation of project. and their implementation? Does the subproject comply Yes, it does, as witnessed by the positive Conclusion of State with applicable government Ecological Expertise. Additionally, staff of ecological committee ll requirements? be check requirements of ecology at least once a year. Does the subproject comply Yes, as the results of analyzes shows, screening and safeguard with applicable ADB safeguard due diligence this project complies with ADB safeguard requirements? require ments. Have there been any recorded No, there have not been any recorded incidents of non-compliance incidents of non-compliance or or requests for corrective actions. requests for corrective actions? Have there been any No, there have not been any grievances or complaints lodged on grievances or complaints the subproject by any affected person or concerned stakeholder. lodged on the subproject by any affected person or concerned stakeholder?

Name of Subproject Company: "Piskent mega omega" LLC Subproject location: Tashkent region Horticulture sector: Greenhouse Value of exposure (US$ ): 520,0 Was any environmental and Yes, there were carried out analysis of environmental impact social due diligence undertaken (ecological screening), as well as social safeguards screening, by your organization? safeguard due diligence briefing note during review. Review of safeguard documents and field visits had been conducted by credit expert of branch. Any environmental assessment Yes. Copy of ZVOS (statement of environmental impact) and report or audit reports reviewed positive Conclusion of State ecological expertise were inspected by by your organization? the loan specialist and ESMS coordinator. According to the mentioned Conclusion, the project is given 3th category of environmental impact. ADB environmental category B/social category (environmental resettlement) C. What were the main According to the Conclusion of State Ecological Expertise, this environmental issues project falls under the category 3 based on the resolution of the associated with this subproject Cabinet of Ministers of the Republic of Uzbekistan №541 dated that were identified through due 07/09/2020. diligence conducted by your Impact on water : Water supply of the object will be carried out by organization, and how were the water from brought by Suvsoz, distributor of drinking water. Water issues dealt with (i.e., outcome consumption for household and drinking needs of workers will be of due diligence)? 200, m3 / year. Water consumption for washing floors 100,0 m3 / year, irrigation of the territory with a ground surface-200, m3/year. Irretrievable water consumption, effluents are not formed. Waste : In the course of business activity of the site, the following waste can be generated: municipal waste-2.5 tons/year, and waste from cleaning the territory - 15.0 tons/year. The following ecological requirements must be fulfilled: - Take measures for safeguarding trees, growing at the site during construction work; - Community waste must be temporary stored in containers and after it taken to local waste site;

128 - Control keeping wasting water under sanitary norm. It is forbidden to discharge sewage water into natural open water bodies, burn waste on the territory of the site, water green plants with d rinking water. Did you discuss with the Yes. Bank inspectors carefully discussed with the subproject owner subproject owner the all the requirements regarding the environmental, ecological and applicable environmental and social safeguard that he/she should meet during the social safeguard requirements implementation of project. and their implementation? Does the subproject comply Yes, it does, as witnessed by the positive Conclusion of State with applicable government Ecological Expertise. Additionally, staff of ecological committee ll requirements? be check requirements of ecology at least once a year. Does the subproject comply Yes, as the results of analyzes shows, screening and safeguard with applicable ADB safeguard due diligence this project complies with ADB safeguard requirements? requirements. Have there been any recorded No, there have not been any recorded incidents of non-compliance incidents of non-compliance or or requests for corrective actions. requests for corrective actions? Have there been any No, there have not been any grievances or complaints lodged on grievances or complaints the subproject by any affected person or concerned stakeholder. lodged on the subproject by any affected person or concerned stakeholder?

129 ANNUAL REPORT OF JSC “NATIONAL BANK FOR FOREIGN ECONOMIC ACTIVITY OF THE REPUBLIC OF UZBEKISTAN” ON EFFICIENCY OF IMPLEMENTATION OF ECOLOGICAL AND SOCIAL MEASURES

18. Please provide responses to the questions below. Please include additional sheets or attachments as required to provide details on questions that have been answered Yes. The Bank is required to submit the annual performance report to RRA.

Name of the Financial JSC “NATIONAL BANK FOR FOREIGN ECONOMIC ACTIVITY OF Institution THE REPUBLIC OF UZBEKISTAN”

Completed by (name): Khalilov Nurali Position in organization: Chief specialist Date: 12.02.2021

130 O. Portfolio Information Report Covering Period:

From: 01.01.2020 To: 31.12.2020

19. For the reporting period, please provide the following information about your portfolio where applicable:

P. Business Lines

Total exposure outstanding for most Average loan (or Product line Description recent transaction) size Microfinance Loan or other types of financial products for individuals FY end (thousand US$) (thousand US$)

Microfinance Loans or other financial products for individuals 549 294,51 2,45

Small business Loans or other financial products for individuals 13 496,41 5,87

Long term: Transactions with tenor greater than 12 months Any lending, leasing or other financial assistance to any corporate or legal Microfinance 89 309,01 13,48 entity other than an individual, with individual transactions less than $50,000 Any lending, leasing or other financial assistance to any corporate or legal Small business 215 959,52 63,41 entity other than an individual, with individual transactions less than $300,000 Other Any crediting, leasing or other financial assistance to any corporate or legal Other (if applicable) entity, with the exception of an individual, with a separate transaction amount 5 138 811,57 2 591 of more than $ 300,000

131 Q. Exposure by Horticulture Sectors

20. Please provide an indicative percentage of total Innovation to horticulture modernization loan portfolio per subcomponents:

% of Innovation to horticulture Industrial Sector modernization loan portfolio

For processing fruits and vegetables 28,5% For creating intensive garden 32,8% Purchase of energy efficient greenhouses 23,9% Purchase of refrigerators 14,8% Total 100% {Note: Please attach environmental and social audit or due diligence reports and environmental and social monitoring reports for each Project Company, if available}

132

21. If engaged in long-term small business finance, please provide information on all loans with: (i) tenor longer than 12 months; and (ii) maximum $5 000 000 loan size.

Safeguard category Any outstanding Value of Type of loan Tenor of environmental and IR and IP Subproject exposure Name of Sub-project SME/Trade loan Industry Sector* issues during reporting using ADB funds (thousand finance (months) period and actions taken to (yes/no) US$) Env. IR IP address the issues

For processing fruits "SUB-DRY" LLC SME 84 1 709,7 B C N/A NO YES and vegetables

Cultivation of cereals "YUSUF DIYOR" FE SME 84 4 950,0 B C N/A NO YES (except rice)

*Please use the sectors listed in the earlier table or any standard classification. Note: Env = Environment, IR = Involuntary Resettlement, IP = Indigenous Peoples.

R. Environmental and Social Management System (ESMS)

22. REQUIREMENT : (1) FOR EXISTING SUBPROJECTS: ATTACHMENTS OF MONITORING REPORTS OR REPORT ON DISCHARGE PERMITS; AND

(2) FOR NEWLY APPROVED SUBPROJECTS: ATTACHMENTS OF ZVOS APPROVAL.

Policies & Processes Yes/No Has your organization developed and implem ented an ESMS? Yes - If there is an ESMS already in place, have there been any updates to the ESMS or policy and procedures adopted by your organization during the No - reporting period? Has senior management signed off on the updated policy/procedure? No - The coordinators, that is, the heads of the credit Has your organization appointed staff tasked to implement the ESMS? Yes department in the branches are responsible for monitoring the implementation of the requirement of ESMS. 133

Please give details of any transactions rejected due to environmental and/or No - social concerns. Please state any difficulties and/or constraints related to the implementation No of the ESMS. We require customers to obtain a state environmental Please describe how you ensure that your subproject companies and their review. If during the analysis or monitoring of the client’s subprojects are operated in compliance with the national laws and regulations activities we notice shortcomings, then, as necessary, we and applicable ADB’s requirements. include work to eliminate these shortcomings in the loan agreement. Please give details of any material social and environmental issues

associated with clients during the reporting period. Not occured In case the existing ESMS is not fully functional, what is the action plan being Active ESMS is considered as totally functional implemented by your organization? Capacity Yes/No Please provide the name and contact information of the Environmental/Social Head of Loan Department Sh.Kamarov Officer or Coordinator who has the overall responsibility for the Yes Call: +998 (78) 147-15-32 implementation of the ESMS. All employees of the credit departments of branches are trained throughout the year according to the ESMS policy. Please provide current staffing of other core ESMS persons in the Yes The heads of credit departments in the branches are the organization involved with ESMS implementation. coordinators for monitoring the work of ESMS in the branches Our bank does not allocate a budget for seminars. What was the budget allocated to the ESMS and its implementation during the No Workshops are organized according to the schedule of year? workshops. Monitoring Yes/No Do you receive environmental and social monitoring reports from subproject No companies that you finance? We check our customers in compliance with the laws of the Do you check for ongoing compliance of your subproject companies with Yes Republic of Uzbekistan, and check their activity in national regulation and any other requirements? compliance with the requirements of our policy ESMS. Please describe how you monitor the subproject company and their All projects are monitored once every 6 months and once

subproject’s social and env ironmental performance. every 12 m onths, in accordance with the ESMS policy. Do you require the subproject owner to submit to you evidence of compliance No with required environmental and social approv als and permits for the

134

subprojects. Please provide details of any accidents/ litigation/complaints/regulatory notices and fines: - Any incidents of non-compliance with the applicable Environmental and Social Requirements No - Covenants/conditionalities imposed by the Financial Institution to the subproject company as a result of any non- complianc e Reporting Yes/No The following reports are submitted to management on a Is there an internal process to report on social and environmental issues to quarterly basis:

senior management? 1. Branch monitoring report 2. Report on the conclusion of th e financial project manager Do you prepare any social and environmental reports: - For other multilateral agencies - Other stakeholders No - E&S reporting in the Report Sustainability reports

Activities on ADB’s Prohibited Investment Activities List If any, please indicate the dollar percentage of loans or investments out of your total outstanding exposure provided to clients who are substantially involved in ADB’s Prohibited Investment Not available Activities List (Refer to page 122 of SPS). If the percentage is not zero, please explain these exposures and any steps that have been taken Not available to reduce such exposure. S. Category “B” Subprojects Using ADB Funds The Bank was not funding the projects category "b" at the expense of the ADB.

6. Please provide information about all new subprojects using ADB loan approved during this reporting period:

For the current report period, there are no sub-projects in JSC NBU, financed with ADB loan resources.

135