<<

Environmental Assessment Report

Initial Environmental Examination Project Number: 37192 August 2009

PAK: Multitranche Financing Facility Power Transmission Enhancement Investment Program, Tranche 1

Sub Project No. 20 220 kV - Double Circuit Transmission Line Subproject

Prepared by National Transmission and Despatch Company for the Asian Development Bank (ADB).

The initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

CURRENCY EQUIVALENTS (as of 30 May 2009)

Currency Unit – rupee/s (Pre/PRs) PRe1.00 = $.0080 $1.00 = PRs79.80

ABBREVIATIONS

ADB – Asian Development Bank dB(decibel) – sound level measure EIA – environmental impact assessment EMP – environmental management plan IEC – International environmental consultants IEE – initial environmental examination LARP – land acquisition and resettlement plan MFF – Multitranche Financing Facility PCB – Polychlorinated biphenyls PEPA – Environmental Protection Agency PEPAct – Pakistan Environmental Protection Act 1997 (as regulated and amended) PMU – project management unit ROW – right of way WMP – waste management plan

DEFINITIONS

Barren Land – Land which has not been cultivated and was lying barren at the time of field survey for this IEE

Cropped land – Land which was under agricultural crops at the time of field survey for this IEE.

Landowner – Person(s) holding legal title to property on the electric transmission line route from whom the Company is seeking, or has obtained, a temporary or permanent easement, or any person(s) legally authorized by a landowner to make decisions regarding the mitigation or restoration of agricultural impacts to such landowner(s) property.

Right-of-Way – Includes the permanent and temporary easements that the Company acquires for the purpose of constructing power transmission facilities. For IEE of this Subproject Right of Way was 100m on either side from the center line.

Tenant or Hari – Persons cultivating the land on tenancy or share cropping basis.

Topsoil – The soil that has the highest content of organic matter, more specifically defined as the "A" horizon.

Transmission Line – Includes electric transmission and distribution lines, substations, and their associated components.

Uncultivated Land – The land which was not cropped at the time of field survey for this IEE.

CONTENTS

Page

I. INTRODUCTION 1 A. Overview 1 B. Background 1 C. Scope of the IEE Study and Personnel 2 D. Policy and Statutory Requirements in Pakistan 4 E. Structure of Report 7

II. DESCRIPTION OF THE PROJECT 8 A. Type of Project 8 B. Categorization of the Project 8 C. Need for the Project 9 D. Location and Scale of Project 10 E. Alternatives 10 F. Proposed Schedule for Implementation 11

III. DESCRIPTION OF THE ENVIRONMENT 11 A. Project Area 11 B. Physical Resources 13 C. Ecological Resources 17 D. Economic Development 19 E. Social and Cultural Resources 21

IV. SCREENING POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 25 A. Project Location 25 B. Potential Environmental Impacts 29 C. Environmental Impacts During Detailed Design and Pre-construction Phase 33 D. Environmental Impacts and Mitigation Measures During Construction 39 E. Environmental Impacts and Mitigation Measures During Operation 48

V. INSTITUTIONAL REQUIREMENTS & ENVIRONMENTAL MANAGEMENT PLAN 50

VI. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE 54

A. Approach to Public Consultation 54 B. Public Consultation Process 55 C. Results of Public Consultation 55

VII. CONCLUSIONS 56 A. Findings and Recommendations 56 B. Summary and Conclusions 57

APPENDIXES 1. Pakistan EIA Process 41 2. Environmental Management Plan 42 3. Monitoring plan 50 4. Summary of public consultation 63 5. Preliminary program for design, construction and commissioning 88 6. Trees affected by transmission line route 89 7. Cropping, trees and other infrastructure within 200m ROW 93 8. List of affected sensitive receivers 118

Annexure 1. Emissions Standards 142 2. Photographs 144

I. INTRODUCTION

A. Overview

1. This document is the Initial Environmental Examination (IEE) for the construction of the new Dera Ghazi Khan to Loralai, 220 kilovolt (kV) double circuit transmission line and forms Subproject No. 20 under Tranche–1 of the Asian Development Bank (ADB) Multitranche Financing Facility (MFF) Power Transmission Enhancement Investment Program (the Program). This IEE presents the results and conclusions of environmental assessment for the proposed construction of Dera Ghazi Khan to Loralai Transmission Line (TXL) Subproject and is submitted by the (the Government), Ministry of Water and Power and National Transmission and Dispatch Company (NTDC). The Dera Ghazi Khan to Loralai TXL Subproject is to be considered for early construction under the Program and requires environmental assessment under ADB operating procedures. An IEE has been carried out to fulfill the requirements of ADB Guidelines (May 20031 2). This IEE study report is used to complete the Summary SIEE, the sub project along with the Rohri to Gumbat Transmission Line sub project are being shifted from Tranche 3 of the MFF to Tranche 1 and as part of the request to ADB for this reallocation of sub projects a SIEE (Dated May 2009) has been prepared and submitted to ADB .3 Figure 1 presents the location of the substation.

1 Initial project classification was carried out in 2008 and the Category is B. Most of the construction impacts will take place with only local impacts and there are no potential significant environmental impacts associated with the Tranche 3 Subproject construction. Initial environmental reconnaissance and Rapid Environmental Assessment carried out by consultants under ADB guidelines in March 2008 indicated that all the Tranche 3 Subprojects will be Category “B”. 2 ADB. 2003. Environmental Assessment Guidelines. Manila. 3 Category A projects that are deemed by ADB's chief compliance officer to be environmentally sensitive for the purposes of (i) the 120 day rule, and (ii) the environmental management plan requirement could involve projects that are near or in environmentally sensitive areas. At this stage, no component of the Tranche 1 Subprojects under consideration is actually within a critical area and therefore the MFF as a whole is Category “B”.

Figure 1: Location of the Sub Station

2. The total cost of the Loralai Subproject is estimated at US$ 70.00 million. ADB will fund the design, civil works and procurement of equipment.

3. The Project involves the construction of TXL over land at of Punjab and Barkhan, Musakhel and Loralai districts of Baluchistan. Detailed designs are currently being progressed. Land will be not acquired for the TXL as only compensation for crop and trees damages will be paid.

4. The environmental assessment requirements of the Government for power transmission projects are different to those of ADB. The environmental regulations of the Government categorize development projects into two schedules according to their anticipated potential environmental impact. The proponents of projects that have more adverse environmental impacts (Schedule II) are required to submit an environmental impact assessment (EIA). The policy is ambiguous and needs clarification. The consultants have initiated a dialogue with Environmental Protection Agency (EPA) for review of the policy. EPA Islamabad has agreed to open discussions with provincial EPAs and other stakeholders to revise the schedules, so that study requirements are not related to voltage or length of facilities being proposed to be added, but are related to impacts. A review of the need for EIA/IEE submission is therefore required by the relevant environmental protection authority, in this case both the Punjab Environmental Protection Department and Baluchistan EPA.

B. Background

5. The condition of the power transmission system in Pakistan is inadequate to meet rapidly growing demand for electrical power. This situation limits national development and economic growth. To cope with the constraints, the existing power transmission infrastructure has to be improved and upgraded. The overall contribution of power infrastructure also requires

2 institutional arrangements and capacity that support strategic management of the sector, and planning and management of investments. Overall, the Program has been designed to address both investment and institutional aspects in the electrical power sector.

6. The Tranche–1 Subprojects involve the addition of new facilities, which requires damages to be paid for crop damages. Dera Ghazi Khan to Loralai TXL Subproject is in the group of projects that involve construction of new TXLs. Impacts from the Subproject are potentially significant, although not insurmountable, although no land will be needed to be acquired for the TXL. The design for Dera Ghazi Khan to Loralai TXL Subproject is sufficiently complete (March 2008) to permit initial environmental examination (Cat “B”). The designs for the Tranche–1 Subprojects have been developed under the ADB Loan No. 2178-PAK: Infrastructure Development. The Subproject, originally a part of tranche 3, is being shifted to Tranche-1 so as to utilize the unspent amount allocated to Tranche 1.

7. The Government has requested the ADB to provide financing for the Dera Ghazi Khan to Loralai TXL Subproject to cover the construction of 220 kV of double circuit 220 kV TXL to help fulfill the overall objective of the MFF to encourage economic growth and improve transmission efficiency by creating a series of national improvements. The improved transmission efficiency will contribute to expansion of economic opportunities by improving capacity and efficiency and security of supply in the Baluchistan Province of Pakistan.

8. At the time of writing this report, (March 2008) the route for the TXL has been surveyed and tower spotting carried out, the preliminary detailed designs for the TXL are completed and the overall requirements for the expansion have been clearly identified (Figures 1 and 2). This IEE has been conducted based on those assumptions as of March 2008. The line route has been selected, by NTDC, with the purpose of minimizing impacts upon population and assets. The route chosen is the shortest that can avoid existing villages and farmhouses.

C. Scope of the IEE Study and Personnel

9. The Dera Ghazi Khan to Loralai TXL Subproject includes construction of 245 km double circuit 220 kV TXL. This IEE study has included field reconnaissance of the TXL right of way (ROW) area with surveys taking place in March and April 2008. Figure 2 presents the TXL ROW area. 3

Figure 2: Transmission Line ROW area

10. The Study Area included the line corridor including all irrigation facilities, water supply, habitable structures, schools, health facilities, hospitals, religious places and sites of heritage or archaeological importance and critical areas and other infrastructures like railway lines, roads, etc.

11. Critical Areas4 if any within about 100 meters (m) of the TXL route also need to be studied. The works will involve construction of the TXL only as substations are not a part of this subproject.

12. The field studies were undertaken by a core study team with experience of environmental assessment for power projects in Pakistan. Mrs. Syeda Bushra Waheed conducted preliminary scoping, survey and assessment activities and coordinated the field sampling and analysis. Mrs. Waheed was also responsible to supervise collection of information and coordinate the various public consultation activities. International environmental consultants (IEC) provided leadership and guidance with regard to the essential detailed assessments of design, construction, operational and decommissioning impacts, noise, air quality and waste disposal. The environmental team also benefited from technical support and other important information on the impacts of the proposed power works provided in feasibility summaries prepared for NTDC, and by expert consultants BPI dealing with engineering, power transmission, socio-economic, resettlement and institutional aspects.

13. The study process began with scoping and field reconnaissance during which a Rapid Environmental Assessment was carried out to establish the potential impacts and categorization of enhancement activities. The environmental impacts and concerns requiring further study in the environmental assessment were then identified. The methodology of the IEE study was then

4 Critical areas as published by the PEPA on the website put in specific reference

4 elaborated in order to address all interests. Subsequently, both primary and secondary baseline environmental data was collected from the enhancement works and the intensity and likely location of impacts were identified with relation the sensitive receivers; based on the work expected to be carried out. The significance of impacts from the power transmission expansion work was then assessed and, for those impacts requiring mitigation, measures were proposed to reduce impacts to within acceptable limits.

14. Public Consultation was carried out on 18-21 March 2008 and 15-22 April 2008 in line with ADB guidelines (footnote 2). Under ADB requirements, the environmental assessment process must also include meaningful public consultation during the completion of the draft IEE. In this IEE, the public consultation process included verbal disclosure of the subproject works as a vehicle for discussion. Interviews were conducted with local families and communities along the TXL ROW area and transmission line alignment. Written records of the responses have been submitted to the Project Proponent, NTDC. The responses from correspondents have been included in Appendix 5 and summarized in Section VI of this IEE.

D. Policy and Statutory Requirements in Pakistan

15. Direct legislation on environmental protection is contained in several statutes, namely the Pakistan Environmental Protection Act (1997) the Forest Act (1927) the Baluchistan Wildlife Act (1976), Baluchistan Irrigation and Drainage Act, Balochistan Canal & Drainage Ordinance passed in 1980. In addition, the Land Acquisition Act (1894) also provides powers in respect of land acquisition for public purposes. The Baluchistan Wildlife Act (1976) is applicable throughout the province. On the other hand, the Forest Act and the Forest Regulation extend only to certain districts. The Forest Act is applicable in Kalat, , Awaran, Lasbela, Mastung, , Panjgur, Kech, Kharan, Bolan, Jaffarabad, Nasirabad and Jhal Magsi Districts. The Forest Regulations (1890) apply to , Changai, Pishin, Qila Abdullah, Qila Saifullah, Zhob, Sibi, , Loralai, Musakhel, Kohlu, Dera and Barkhan districts. There are also several other items of legislation and regulations which have an indirect bearing on the project or general environmental measures. Where GOP has not set a standard or guideline criterion the standards given in World Banks publication Pollution Prevention and Abatement Handbook are used as criteria. World Band criterion is also used in parallel to GoP criteria

1. Statutory Framework

16. The Constitution of Pakistan distributes legislative powers between the federal and the provincial governments through two ‘lists’ attached to the Constitution as Schedules. The Federal List covers the subjects over which the federal government has exclusive legislative power, while the Concurrent List contains subjects regarding which both the federal and provincial governments can enact laws. “Environmental pollution and ecology” is included in the concurrent list. Hence, both the federal and the provincial governments can enact laws on this subject. However, to date, only the federal government has enacted laws on environment, and the provincial environmental institutions derive their power from the federal law. The Punjab Environmental Protection Act 1997 is now redundant. The key environmental laws are discussed below. 5

2. Pakistan Environmental Protection Act, 1997

17. The Pakistan Environmental Protection Act, 1997 (PEPAct) is the basic legislative tool empowering the government to frame regulations for the protection of the environment. The act is applicable to a wide range of issues and extends to air, water, soil, marine, and noise pollution, as well as to the handling of hazardous wastes. The key features of the law that have a direct bearing on the proposed project relate to the requirement for an IEE and EIA for development projects. Section 12(1) requires that: “No proponent of a project shall commence construction or operation unless he has filed with the Federal Agency an IEE or, where the project is likely to cause an adverse environmental effect, an EIA, and has obtained from the Federal Agency approval in respect thereof.” The Pakistan EPA has delegated the power of review and approval of environmental assessments to the provincial environmental protection agencies.

3. Pakistan Environmental Protection Agency Review of IEE and EIA Regulations, 2000

18. The PEPAct provides for two types of environmental assessments: IEE and EIA. EIAs are carried out for projects that have a potentially ‘significant’ environmental impact, whereas IEEs are conducted for relatively smaller projects with a relatively less significant impact. The Pakistan EPA Review of IEE and EIA Regulations, 20005 (the ‘Regulations’), prepared by the Pak-EPA under the powers conferred upon it by the PEPAct, categorizes projects for IEE and EIA. Schedules I and II, attached to the Regulations, list the projects that require IEE and EIA, respectively.

19. The Regulations also provide the necessary details on the preparation, submission, and review of IEEs and EIAs. The following is a brief step-wise description of the approval process: (i) A project is categorized as requiring an IEE or EIA using the two schedules attached to the Regulations. (ii) An EIA or IEE is conducted as per the requirement and following the Pak-EPA guidelines. (iii) The EIA or IEE is submitted to the concerned EPA—provincial EPAs if the project is located in the provinces or the Pak-EPA if it is located in Islamabad. (iv) A fee, depending on the cost of the project and the type of the report, is submitted along with the document. (v) The submittal is also accompanied by an application in the format prescribed in Schedule IV of the Regulations. (vi) The EPA conducts a preliminary scrutiny and replies within 10 days of the submittal of a report, a) confirming completeness, or b) asking for additional information, if needed, or c) returning the report requiring additional studies, if necessary. (vii) The EPA is required to make every effort to complete the IEE and EIA review process within 45 and 90 days, respectively, of the issue of confirmation of completeness. (viii) When the EPAs accord their approval subject to certain conditions: a. Before commencing construction of the project, the proponent is required to submit an undertaking accepting the conditions.

5 Government of Pakistan. 2000. The Pakistan Environmental Protection Agency Review of Initial Environmental Examination and Environmental Impact Assessment Regulations, Islamabad.

6

b. Before commencing operation of the project, the proponent is required to obtain from the EPA a written confirmation of compliance with the approval conditions and requirements of the IEE. (ix) An environmental management plan (EMP) is to be submitted with a request for obtaining confirmation of compliance. (x) The EPAs are required to issue confirmation of compliance within 15 days of the receipt of request and complete documentation. (xi) The EIA approval is valid for 3 years from the date of accord. (xii) A monitoring report is to be submitted to the EPA after completion of construction, followed by annual monitoring reports during operation. 20. TXLs and grid substations above 11 kV are included under energy projects in Schedule II, under which rules EIA is required by the Government for all projects involving transmission lines of 11 kV and above and for grid substations. IEE is required for TXLs less than 11 kV and large distribution projects (Schedule I). A review of the need for EIA/IEE submission is therefore required by the relevant environmental protection authority in this case the Punjab EPA. As the proposed project will be located in Punjab, it falls under the jurisdiction of the Punjab EPA.

21. There are no formal provisions for the environmental assessment of expanding existing TXLs and grid substations but Punjab and Baluchistan EPA (PEPA-QEPA) have requested disclosure of the scope and extent of each Subproject in order that the Director General of PEPA/QEPA can determine if additional land is required and the need for statutory environmental assessment (footnote 1). The details of this Subproject have been forwarded to the Punjab EPA (October 2006) in order to commence the local statutory environmental assessment process.

4. National Environmental Quality Standards

22. The National Environmental Quality Standards were first promulgated in 1993 and have been amended in 1995 and 2000. The following standards are specified therein: (i) Maximum allowable concentration of pollutants (32 parameters) in municipal and liquid industrial effluents discharged to inland waters, sewage treatment facilities, and the sea (three separate sets of numbers); (ii) Maximum allowable concentration of pollutants (16 parameters) in gaseous emissions from industrial sources; (iii) For power plant operating on oil or coal: (a) Maximum allowable emission of sulfur dioxide from the power plant (b) Maximum allowable increment (concentration) sulfur dioxide in ambient air due to operation of the plant (iv) Maximum allowable concentration of nitrogen oxides in ambient air when the plant is operating (v) Maximum allowable emission of nitrogen oxide for steam generators as a function of heat input (vi) Maximum allowable concentration of pollutants (2 parameters) in gaseous emissions from vehicle exhaust and noise emission from vehicles.

5. Other Relevant Laws

23. There are a number of other federal and provincial laws that are important in the context of environmental management. The important laws are listed below. 7

(i) The Baluchistan Wildlife Protection Ordinance, 1972 empowers the government to declare certain areas reserved for the protection of wildlife and control activities within in these areas. It also provides protection to endangered species of wildlife. As no activities are planned in these areas, no provision of this law is applicable to the proposed project. (ii) The Forestry Act, 1927 empowers the government to declare certain areas reserved forest. As no reserved forest exists in the vicinity of the proposed project, the provisions of this law are not applicable to the proposed project. (iii) The Antiquities Act of 1975 ensures the protection of Pakistan’s cultural resources. The Act defines ‘antiquities’ as ancient products of human activity, historical sites, or sites of anthropological or cultural interest, national monuments, etc. The Act is designed to protect these antiquities from destruction, theft, negligence, unlawful excavation, trade, and export. The law prohibits new construction in the proximity of a protected antiquity and empowers the Government of Pakistan to prohibit excavation in any area that may contain articles of archaeological significance. Under the Act, the project proponents are obligated to: (a) Ensure that no activity is undertaken in the proximity of a protected antiquity (b) Report to the Department of Archaeology, Government of Pakistan, any archaeological discovery made during the course of the project. No protected or unprotected antiquity was identified in the vicinity of the proposed project that may be affected by the project.

E. Structure of Report

24. This report reviews information on existing environmental attributes of the Study Area. Geological, hydrological and ecological features, air quality, noise, water quality, soils, social and economic aspects and cultural resources are included. The report predicts the probable impacts on the environment due to the proposed project enhancement and expansion. This IEE also proposes various environmental management measures. Details of all background environmental quality, environmental impact / pollutant generating activities, pollution sources, pollution control equipment, predicted environmental quality and related aspects have been provided in this report. References are presented as footnotes throughout the text. Following this introduction the report follows ADB guidelines and includes: (i) Description of the Project (ii) Description of Environmental and Social Conditions (iii) Assessment of Environmental Impacts and Mitigation Measures (iv) Environmental Monitoring Plan (v) Public Consultation (vi) Recommendations and Conclusions

8

II. DESCRIPTION OF THE PROJECT

A. Type of Project

25. The new Loralai 220 kV transmission line Subproject is an extension of the New Dera Ghazi Khan 500 kV grid station to the New Loralai 220 kV grid station (Subproject Nos. 5 and 6, respectively, of Tranche 2), to provide the north-eastern part of Baluchistan province with another means of extra high-tension (220 kV) power supply. It includes the construction of a new 245.01 km long 220kV double circuit transmission line, traversing four districts, i.e. Dera Ghazi Khan district in the Punjab province (62.5 km); and the remaining 182.5 km in three districts of Baluchistan province (42.8 km in Barkhan, 24.0 km in Musa Khel and 115.4 km in Loralai district). The alignment of this new 220 kV double circuit transmission line has deliberately been designed to traverse mostly the unproductive hilly to rough lands, to avoid the villages and Almond orchards. As a result, only about 10.43 km (4.26%) of its length will traverse private farmlands, including fruit and wood trees / orchards and wheat-cum-maize farmlands with scattered wood trees belonging to a total of 126 farming households from 21 villages. The alignment of this new 220 kV double circuit transmission line is along the Dera Ghazi Khan – Loralai road, almost parallel to the existing 132 kV transmission line from Dera Ghazi Khan to Loralai. Figure 3 presents the route of the proposed transmission line.

Figure 3: Route of the proposed transmission Line

B. Categorization of the Project

26. The construction works are generally expected to take place within approximately 10 m around the TXL, depending on local requirements. At this stage, the methods to construct the TXL are presumed to take the usual pattern. 9

27. The construction of the TXL is within a barren, uncultivated and some private cultivated land. The land in Dera Ghazi Khan is rangeland which is plain with good enough soil cover and land with heavy content of limestone being used at present by crushing industries while the land in other districts of the Subproject area is mostly barren and hilly and some cultivated land. The potential environmentally significant features will be limited but they will not affect significantly any crops on agriculture cultivated land, green field sites because the route selected for TXL is mostly barren with some growth of grasses in small patches whereupon animals are grazed. Besides grasses, no bushes, some trees or a few built-up structures are found in Dera Ghazi Khan-Loralai Route. Some villages are situated on outer fringes of the TXL corridor. No built–up structures except few houses of these villages will be affected which will be compensated. Angle towers are used to avoid the impact on built–up structures or gardens. The village access road leading to TXL will also remain intact, and not affected by the Subproject.

28. Categorization is based on the most environmentally sensitive component and the Subproject and TXL is categorized as a Category ‘B’ subproject under ADB requirements and this IEE report is based on that assumption.

29. The aspects of the project with potential for significant environmental impacts need to be assessed in detail and environmental assessment has therefore focused on significant impacts from the construction aspects as well as consultation with the public all along the proposed alignment of the transmission line. This report has also surveyed the transmission line corridor and immediate hinterland that may be affected by knock on effects from impacts such as waste disposal.

C. Need for the Project

30. The condition of the power transmission system in Pakistan is inadequate to meet rapidly growing demand for electrical power. This situation limits national development and economic growth. To cope with the constraints, the existing power transmission infrastructure has to be improved and upgraded. The overall contribution of power infrastructure also requires institutional arrangements and capacity that support strategic management of the sector, and planning and management of investments. Overall the proposed PTE-MFF facility has been designed to address both investment and institutional aspects in the electrical power sector. Pakistan has a wide network of power transmission.

31. The new 220 kV sub-station has been proposed at Loralai. Load flow studies have been carried out for the peak load conditions of August and September 2010 with a new 220 kV grid station and two 250 MVA 220/132 kV transformers commissioned at Loralai, and a new 220 kV transmission line connected between Dera Ghazi Khan-Loralai. In general, the studies show that with the commissioning of Loralai 220 kV grid station, the transmission lines and transformers will operate within both load and voltage limits. The sub projects (transmission line and substation) will stabilize the northern Baluchistan system which at present is unstable and prone to frequent interruptions.

32. The feasibility study for the Subproject was prepared by consultants under Loan TA- 2168 has demonstrated the need for the proposed improvements based on electricity demand and network studies and that significant benefits can accrue in the form of reduced load on transformers and reduction in transmission line losses. Thus there is a clear and immediate future need for this Subproject.

10

D. Location and Scale of Project

33. The new 220 kV Dera Ghazi Khan to Loralai TXL has been proposed at Dera Ghazi Khan, Barkhan, Musa Khel and Loralai Districts in Punjab and Balochistan. The Subproject will involve the construction of new 220 kV TXL from proposed Dera Ghazi Khan 500 kV Grid Substation to the proposed 220 kV Loralai Grid Substation.

34. In aligning the design aims to site it on barren land. As such, the accessibility will not be a problem. There are roads (20 m), tracks and katcha (unpaved/dirt tracks) ways and the contractor should have to develop a few tracks for transporting the materials. The contractor is likely to be needed to transport the materials manually at tower locations on mountainous areas. This should result in very little if any damage to the vegetation or disruption to the population in the vicinity of the TXL. The TXL site is approachable through a number of major or minor metalled roads and village tracks. Almost all the village tracks are linked to the metalled roads and are thus accessible to vehicles. In any event care will be taken that the disruption to the vegetation is kept to a minimum.

35. The environmental impacts are likely to be localized along the TXL ROW construction site at most places and impacts are reviewed in the environmental impact section of the report. The impacts will need to be reviewed and amended if necessary if the locations change and when the detailed designs are available.

E. Alternatives

36. The Tranche-1 (T1) of projects will contribute to the improvement of the overall performance of the power transmission sector, improving transmission efficiency, broadly widening access to power to drive economic opportunities. The beneficiaries of the Project will be people, companies, and government and non-government agencies in Pakistan that use power transmission services. Power users will benefit in terms of secure power and improved power safety and potentially increased productivity.

37. Do nothing scenario: Predictions have indicated that, without T1 power transmission Subproject, supply will not be as reliable as with the project in purely power transmission terms based on the available information. The project is part of an overall strategic improvement to the system.

38. In absence of the Subproject, the potential for interruptions to power supply will increase and socio-economic development of the provinces could be affected in the short to medium term. In an un-enhanced state the potential for interruptions to supply and increased wear and tear on equipment will increase. In the short term the power program would improve and provide more reliable access to secure power.

39. Alternative construction methods: The feasibility and constructability of the transmission line towers is well established locally and the construction of TXL and installation of equipment is well practiced in the international context (even if some types of equipment are new Pakistan). The process basically includes the transportation of equipment to site and the assembly of pre-fabricated units in-situ. Thus the impacts from construction per se are very manageable from the environmental viewpoint.

40. Alternative geometry: The ROW for 220 kV Dera Ghazi Khan to Loralai TXL is selected on mainly barren state land in Dera Ghazi Khan, Barkhan, Musakhel and Loralai and some 11 private cultivated land in these Districts. It does not include any urban and rural settlements. Although the line design has been finalized and approved, some further detailed surveys may be carried out at construction stage and some changes may occur. The extent of land acquisition is presently anticipated to be minimal and additional land will not be required for TXL on barren or private land. The consultants are informed that all Dera Ghazi Khan–Loralai 220 kV TXL S.P. works are to be completed within ROW of TXL corridor and no land acquisition for the TXL is required. The present assumption is that the construction of TXL will be completed as planned on the defined alignment.

F. Proposed Schedule for Implementation

41. The Project Proponent (NTDC) plans to have the T1 completed by mid to late 2013. The details for the implementation of the Subprojects are in development. There will be no land acquisition however crop, trees and orchards will be paid for the damages of crops and trees through compensation process but detailed plans extension must be made. Design’s TXL arrangements, access, review of environmental management and construction processes will need to be completed in say about three months. When the detailed designs are completed, tendering and award of contract will take place over about three to six months. The construction period will follow and best estimates indicate about 18 months to 2 years. The preliminary schedule is presented in Appendix 5.

III. DESCRIPTION OF THE ENVIRONMENT

A. Project Area

1. General Characteristics of Project Area 42. The Dera Ghazi Khan to Loralai 220 kV transmission line will cross over barren uncultivated land and some cultivated land in Dera Ghazi Khan, Barkhan, Musakhel and Loralai Districts up to Grid Substation site at Purana Bawar Killy on Loralai Ziarat road, 2 km south of town. 43. There are houses including residential, other social infrastructure and other transmission lines that are located within 100m of the proposed TXL corridor. No infrastructure like canal, railway line, river or minor is within the line route. However, the line crosses over some wide streams (nullahs), water flows, paved roads and 11kV transmission lines. The TXL is not immediately adjacent to any residential or school property based on the land details provided by NTDC.

44. There is plenty of room available in the selected land to support the Dera Ghazi Khan to Loralai 220kV TXL on the unproductive state and private land and some productive private land. Provisions have been made in the land acquisition and resettlement plan (LARP) to compensate the cost of damaged crops and trees. Access to the TXL will be from metalled and katcha (unpaved/dirt tracks) roads adjacent to the TXL site. The access to the TXL Subproject will be from the Dera Ghazi Khan to Loralai road. There should be no need to disturb any existing roads and watercourses, based on the current land required, this however is subject to reconfirmation after detailed designs are completed.

12

2. Affected Administrative Units

45. The Dera Ghazi Khan to Loralai 220 kV Subproject will indirectly affect only a few villages of Dera Ghazi Khan, (Punjab), Barkhan, Musakhel and Loralai, Districts of province of Baluchistan. There is a Police Camping area at more than 300 m away from the TXL..The villages directly affected by the line , by Province and Districts is as follows:

Province District/Village Punjab D.G.Khan District Basti Shikar Khan Rajhani Village Village Gamuli Baluchistan Bar Khan District Pailia Thal Mir Hamadani Killi Basti Khaprani Basti Kaurri Deh Bhebani Rarkan Village Musa Khel District Village Rarrasham Gidar Daag Loralai District Mekhtar Village Ashberg Village Indah Village Sehan Gharra Village Shabozai Village Masood Killi Sagor Village Bala Killi Tattai Naway Bawar Killi

46. For the purpose of this study the Dera Ghazi Khan to Loralai TXL Subproject has been assumed to affect all the adjacent villages and interviews have been conducted with the public along the TXL route. 13

B. Physical Resources

1. Topography, Geography, Geology, and Soils

47. Dera Ghazi Khan District is divided into two parts. The mountainous area is in the west and the plain in the east. The western half of the district is covered by the hills of the . Most of these hills are seen in the tribal area known commonly as the De-Excluded area. The hills are higher in the north where they rise to peak as high as 3,000 m above the sea level. In addition to main range, there are two smaller chains parallel to each other between the main range and the plain in the east. The height of these ranges gradually decreases southwards. The high peaks towards the centre of the district are Ekbhai (2,274 m), (1,916 m) and Dragul (1,640 m). The mountains are formed of sandstone with occasional outcrops of limestone. These are barren except some of the higher summits in the north of district.

48. The plain area of the district can be subdivided into three natural tracks, namely, the piedmont area, canal and river areas; The well irrigated canal-plain area forms the intermediate zone between the piedmont and the river area. The latter area lies close to the where the cultivation depends on the flooding rather than irrigation from canal

49. The topography of the Dera Ghazi Khan district is dominated by the mountains and hills of the Sulaiman range which runs mostly in a north–south direction in the eastern portion of the district. The off–shoots of the Sulaiman range run, across the district, in a northeast southwest direction. From east to west the mountains ranges are the Phulali, the Sukha Daula, the Jandaran and the Karwadda. The elevation of the mountains varies from 1,000 to 2,000 m. Phulali and Sukha Daula ranges cover the eastern portion while Jandran range, is in the western portion of the district, along the boundary with Kohlu district. Mar, Anadari and Pikal ranges cover the southern portion of the district. In between the mountain ranges are the valleys. Seasonal rivers, streams and nullahs flow in these valleys.

50. The topography of Barkhan is dominated by the mountains and hills of the Sulaiman range. The terrain is rugged and divided into basins by ranges from 900 to 3000 m above sea level. The highest peak in the district is 3,109 m above sea level. There are a series of plains in between the parallel ranges. There are several other important ranges the Spara or Sohar range runs from north to south on the eastern border of the district. The Surghar range extends from north–east to southwest of the western border of the district.

51. The Torghar, Shinghar and Morga ranges are in the upper north. The Nathaghar and Lakhighar ranges are in the southern portion of the district. The Bujgar, Sputoghar, Dhaulighar and Galaisar are on the south–east. Land along Razanni River, from Palosi Punga in the north upto Musakhel town in the south, is a fertile plain. There are also several river valleys. The Ispangla valley is situated in the eastern portion of the district. Limestone, shale and sand stone are the main types of rocks involved in the formation of the area.

52. The topography of Musakhel is dominated by the mountain and hills, varying in elevation from about 900 to 3,000 m. The highest mountains are in the northwest along the border with Ziarat, Pishin and Qila Saifullah districts. The direction of the mountain ranges, in the western half of the district, is mostly from west to east while that in the eastern half, from northwest to southwest. In the western part, the main ranges are the Shoreghar, Nagarghar, Murdarghar, Ghulamghar, Saraighar, Dabbarghar, Landaghar, Pitaoghar and Damanghar. In the part of the

14 district, the important mountain ranges are Sebatghar, Mandghar, Gadabarghar, Spinkaighar, Dadarghar and Torghar.

53. In between the mountain ranges of Loralai, there are fertile valleys. In the northern part of the district lies the Bori valley, which runs east to west and is bounded on the north by the Damanghar range and other ridges and on the south by Kurghar range. It continues westward up to the Murdarghar. The Murdarghar forms the southwest corner of the Thal or plain. The Chamalang valley is situated in the southeastern part of Duki subdivision. It gets water from the Chamalang Rud and other smaller streams flown from Dodarghar in the north and Kharlakghar in the south.

2. Climate and Hydrology

54. There is large variation of altitude above sea level in the land along the alignment. The big change in altitude in the districts and long length of the line means variation between the climates of the project area. The climate of the districts varies with the elevation, but on the whole it is dry and healthy. The summer is cool and pleasant but the winter is intensely cold with hard frost and snowfall.

55. The climate of Dera Ghazi Khan is typical of Southern Punjab. The maximum temperature of the district in summer reaches 42oC. In winter, the minimum is 4.5oC. The mean maximum and minimum temperatures in summer for this period are 40.6oC and 27.2oC, respectively, and in winter 22.3oC and 5.9oC, respectively. At Fort Munro, which is a hill station, the day temperature indoor rarely rises over 27oC. In the remaining Subproject area, Barkhan, Musakhel, Loralai districts, the maximum temperature in summer reaches 38oC. In winter, the minimum is 4oC. The mean maximum temperature is 29oC mean minimum annual temperatures is 15oC, 4oC. The summer season starts from April and continues until October. May, June and July are the hottest months. The winter season on the other hand starts from November and continues until March. December, January and February are the coldest months. The summer season starts from April and continues until October. May, June and July are the hottest months. The winter season on the other hand starts from November and continues till March, December, January and February are the coldest months.

56. The rainy season starts in July and ends in September. Annual rainfall varies from 167 millimeters (mm) in Dera Ghazi Khan, to 398 mm in other districts of the Subproject area. More rains occur in July and August than any other months. Most of the winter rains are received in the months of March and April.

3. Groundwater and Water Supply 57. Irrigation is largely dependent on the canals, but tube wells have also been sunk in the areas where water is fit for irrigation. The chemical quality of groundwater in the Dera Ghazi Khan varies area wise and depth wise. According to the Feasibility study conducted in 2003 for the Water and Power Development Authority, Water quality data of hand pump at mouza Chohata pajahda indicates ph 7.75, Specific Absorption Rate (SAR) .46, Cations meg/l 7.50, Anions mg/l 7.40, Ca mg/l 1.90, Mg mg/l 3.00, Na mg/l 2.28, HCO3 mg/l 4.70, chlorides mg/l mg/l 2.20, electric conductivity mmohs/cm at 25oC 717 D.S. by evaporation ־Sulphates ,0.50 part per million (ppm) 444. According to Pakistan Council of Research in Water Resources (PCRWR), 2005 data, ground water quality in Dera Ghazi Khan was: ph 7.7-8, Total dissolved salt (TDS) 230-240 mg/L, Hardness 140-152 mg/L, chlorides 17-20 mg/L, Iron 0.2-0.9 mg/L, 15

Water Quality-Average Values-2007 Values

Maximium Average Minimium Unit Loralai Musakhel Burkhan Loralai Musakhel Burkhan Loralai Musakhel Burkhan ph mg/L 8.41 8.05 8.03 776 7.83 7.83 708 7.5 7.26 Turbidity mg/L 12.05 24.61 10.79 0.41 9.28 6.78 0 0.57 0 TDS mg/L 1456 1148 1208 645 542 678 317 256 381 Na mg/L 177 138 152 83 65 88 30 37 62 Ca mg/L 136 188 276 72 112 96 48 48 20 Hardness mg/L 730 850 860 560 320 580 250 180 140 E Coli +ive +ive +ive +ive +ive +ive +ive +ive +ive

Source:: National Water Qualty Monitoring Program, Quetta Loralai= 22 samples from different locations Musakhel = 15 samples from different locations Burkhan = 16 samples from different locations

58. The precipitation in the Subproject area (Barkhan, Musakhel and Loralai) is inadequate only partly compensated for by the winter rains and snow. The overall rainfall pattern has proved sufficient for the recharging of underground aquifers and water table and thus keep the tube wells going. Almost 83% of the cultivated area is irrigated from the water from tube wells, 7% is canal fed and 5% each from water from Karezes (man made water extraction system that does not involve use of pumping) and spring and dug wells. Only 149,246 hectares (ha) out of the total area 993,300 has is under cultivation.

59. Irrigation is largely dependent on tube wells which have been in the areas where water is fit for irrigation. The tube wells have been installed to make up the deficiencies. The water table is at 80 m and water is drinkable. Groundwater sources exist in the area and there are tube wells within 500 m of the proposed TXL. Only 19% and 16 % housing units use piped water inside their houses and 81% and 84% of housing units have this facility outside their houses in Barkhan & Musakhel. The facility of drinking water inside the houses available to 54% of the housing units while 46% of the housing units use outside sources as drinking water in Loralai. The local population in most of the TXL area is generally reliant on supply from wells. Purana

16

Bawar Killi village has its own independent water supply through a tube well. Besides this supply, there is Pathankot spring with sufficient water (about equal to eight tube wells). Water from this spring is used for cropping and Army Cantt located at 1 km from the proposed Grid Substation site. There should be no impact on these sources of water during the construction.

4. Surface water

60. In Dera Ghazi Khan, the River Indus which lies on the east begins to rise in May when melting snow from the Himalayas commences and gradually fills its bed to a breadth of 14 kilometers (km). It continues to gain height till the end of August and then begins to subside, reaching its cold weather level at the end of September. Two large nullahs (streams) rising far to the west to east through narrow and tremendous gorges. The most northerly, the Vihowa, emerges from those into District, but its flood water reaches the villages in the north of Sangarh. The Sangarh emerges near the village of at the centre of the western boundary of . Water quality of Indus at D.G Khan , 2004 data from PCRWR is as follows : ph 7.1- 7.5 ; TDS 154-305 mg/L ; Faecal coli form 140-390 / 100 mL ; Chlorides 6-90 mg/L dissolved oxygen 1.5-6.9 mg/L ; nitrates 4.2 – 10 mg/L . 61. Rakhni stream runs northeast along the eastern boundary of Barkhan District and receives the water of a number of effluents from the west of which the principal the Chung, Churi and Padhi. It irrigates Raknil and Chach areas of Barkhan District. The Han stream runs in a southwest direction and carries the drainage of Hanpass and southeastern slopes of Tandran range. At Dhamani, the stream becomes perennial up to its Junction with Kah River in Dera Ghazi Khan. Daula stream, its tributary brings water from the hills situated to the south Bagh Valley and irrigates a number of villages in Barkhan Valley and joins Han in Vitahari Rakni and Han join Kah stream which then passes in Dera Ghazi Khan, Bala Dhaha stream lies in Berg– Sham Mauza of Barkhan Tehsil, the stream is a tributary of Nachari River, it irrigates a very small area of Mauza Berg Sham then water passes to Duki tehsil. Water in this stream comes down from southwestern slopes of hills located north of Hanpass.

62. The main rivers and streams which drain the Musakhel are Razanni Loe, Lahar, Lori, Tang, Kingri and Sarin. The general flow of the rivers and streams is from west to east. During the monsoon, these streams are flooded resulting in widespread losses of livestock and property.

63. The drainage of western and central portion of the Loralai District is provided by the Ambar River and its tributaries while the eastern drainage bursts through the Sulaiman range into the Indus Valley. The principal tributaries of the Anambar are the Kohan and Loralai streams. The Narochi River which rise north–east of the Chamalang valley with its tributary Baldehaka is next in importance. The Thal and Beji Rivers irrigate parts of Duki and Thal plains.

64. Irrigation. The major source of irrigation in Dera Ghazi Khan is canals while in other districts of the Subproject area, sources of irrigation are tube wells, karezes, springs, canals and wells. Musakhel is irrigated by 12 streams and seven springs with permanent flow, which irrigate 35% of the area. The remaining is khushkaba or sailaba (land depending upon rainfall). Other significant sources of irrigation are tube wells and open surface wells. The kareze and spring are mostly community owned, whereas tube wells and open surface wells are privately owned. A comprehensive system based on the extent of landholdings exists for the distribution of water from community owned sources. The system also caters for the repair and maintenance of water channels.

17

65. The cost of which is again apportioned on the above principle. On the other hand however, the growing number of tube wells is tending to disrupt the delicate balance between recharge and exploitation of groundwater resources. It is extremely vital that the cycle (recharge / use) be made sustainable for long-term irrigation prospects. The construction, recently of the Kohar delay action dam would go some way in this direction, but there is a crying need for building many more such dams if the long term irrigation prospects are not to be jeopardized. The nearest Nadi (flood water streams) or floodwater hill torrent, which is non-perennial, is located at about 1 km from the Grid Substation site.

5. Air Quality

66. Air quality in the Subproject area appears good based on observation during the study period. Domestic sources of air pollution, such as emissions from wood and kerosene burning stoves as well as small diesel standby generators in some households, are well dissipated. There are no other industrial pollution sources at present in the vicinity.

67. The other major source of air pollution is dust arising from construction and other ground or soil disturbance. Near the access roads, when vehicles pass, dust levels will increase. The nearby road is paved but dust levels are elevated when vehicles pass intermittently over the roads based on field observations and may be high enough to obscure vision significantly based on observations in April 2008.

6. Noise and Vibration

68. Noise from vehicles and other powered mechanical equipment is intermittent. There are also the occasional calls to prayer from the Public Address systems at the local mosques but there are no significant disturbances to the quiet rural setting. However, the construction from the proposed power expansion will use powered mechanical equipment. Subjective observations were made of background noise and also of individual vehicles which pass by. Based on professional experience background daytime noise levels are probably well below 55dB(A)L90.

C. Ecological Resources

1. Wildlife, Fisheries and Aquatic Biology

69. There are no areas of wildlife significance near the Subproject area. In Dera Ghazi Khan, pigs and hog deer are fairly common in the woodlands near the River. Black and gray partridges are also found. Migratory birds use the Indus valley in cold weather. Many varieties of duck and teal visit the district. The Indus contains a variety of fish. In the winter months when the river recedes, fish are caught in greater quantity.

70. Wildlife found in the Barkhan, Musakhel and Loralai [Baluchistan] is much the same as that found in other highland areas of the province such as wolves, jackal, hyena, fox, wild cat, mongoose, deer and hare. Porcupines and badgers are also common. Wild pigs are occasionally found in the Gadebar and Anambar forests. Mountain sheep and Chiltan markhor and Sulaiman markhor are fairly plentiful especially in the higher altitudes of the Suleman range

18 and in the hills near Chautair and Wana. Among the game birds, chukor and si-si are numerous in the hills. Black and grey partridge, pigeon, sand grouse, quail and bustard are found in the plains. Waterfowl is plentiful in the season. Common birds such as vulture, kite dove, sparrow, lark, hoopoe (hudhud) and starling (sarau) are also found. Among reptiles, snakes are numerous in all the tehsils except Sinjawi. No commercial fishing is taking place in the Subproject area.

71. The houbara bustard is predominantly a winter visitor to the deserts of Baluchistan; 12% of the area of the province forms the winter habitat of this species. Live birds and eggs are smuggled out of the country. It is estimated that about 400 falcons are trapped in Baluchistan each year and illegally exported to the Middle East. Demoiselle and Eurasian cranes migrate between and . A major migration route for demoiselle cranes crosses the Zhob River and Loralai before entering Punjab. It is estimated that more than 40,000 demoiselle cranes pass through Zhob, of which a minimum of 5,000 are trapped each year. The most important staging areas for cranes in Baluchistan include the Zhob River, the plains of Loralai, Zangi Nawar, Chagai, the desert of Lasbela and Hab reservoir.

2. Terrestrial Habitats, Forests and Protected Species

a. Vegetation Cover and Trees

72. The Subproject area, which is dry, is dominated by plain barren, hilly and some rural suburbs with various productive fields of monocultures that now dominate the agro-ecosystems present in parts of the Subproject area.

73. The vegetation cover in the Subproject area is sparse trees such as Acacia modesta, Olive, Tamarix orientalis, halanea, Carogana,Vitis vinifera, Zizyphus nimularia, Ziziphusj ujuba, Grewia oppositifolia, Pistacio cabulica, Salix and, Dalbergia sisso, gunal, raga, iguzma in Barkhan and Musakhel while in Loralai juniper, macrocode and Pistachio, are found on the hills and mountain olive grow on low-lying hills. Phulai (Acacia modesta) is found along the Anambar River to the east end of the Bori valley. Other commonly occurring trees in the district include ash and myrtle. Less common species include beer gargat, bushk and pamagi. All these are used as vegetables. A variety of grasses grow in the Subproject area, the most important being barwaz barara, barav, buski ghalmea ganderae khar or zmai tukha, saba (Step caliphat) and sargrah. In the plain area, a considerable undergrowth of shrub, suitable for camel grazing is to be found.

74. The cultivated area of Baluchistan is about 6% of the total area of the province and is regarded as private property. The remaining lands, with the exception of the state lands, are considered common property. The major use of these lands is predominantly pastoral. In addition to providing forage for livestock, these lands provide wildlife habitat and play a valuable role in recharging groundwater.

75. The Household Income and Expenditure Survey estimated about 9,000 ha under farmland trees, with a standing volume of about 3.43 million cubic m, giving an annual production of about 100,000 cubic m a year (in the province) (IUCN 1992). The most common trees growing on farmers' fields are Prosopis cineraria (kandi), which occur naturally. Introduced trees include A. nilotica, Eucalyptus spp., Cupressus arizonica, Alianthus altissima, Populus spp., Melia azedaraca, Salix spp., Albizzia lebbek, Robinia pseudoacacia, Platanus orientalis, Gleditsia tricanthos, Sesbania sesban, Prosopis juliflora, Morus alba, Azadirahta indica, Ficus religiosa, Pinus eldarica and Elaeagnus hortensis. 19

b. Protected and Religious Trees

76. There is no protected forest near the DeraGhazi Khan to Loralai TXL Subproject. The nature of terrain with plain barren rangeland, lime stone containing land and steep mountain slopes ranging from 1,500 to 3,000 m in elevation and limited rainfall has not been conducive in making Subproject area suitable for purposes of forestry .Musakhel is devoid of forest. The Forest Department has declared a small piece of land Sarkandi area as Reserved Forest. Out of a total of 44,397 has, only 18,305 has are reserved for coniferous forest and the remaining 18,305 is scrubland or rangeland which is counted as forest in Loralai. The major trees found on higher hills are juniper and pistachio. Olive grows on the lower hills. 77. The rural poor are trapped in a vicious cycle of the over–exploitation of whatever remains, to compensate for the loss of productivity and the ever–increasing cost of living. It is estimated that barely 8% of provincial energy demands are currently being met from forest resources, compared with 33% on the country level (Government of Pakistan and IUCN, 1992). These estimates, however, do not appear to include dependence of the rural population on rangeland shrubs. In a recent survey in Sinjawi (Loralai District), it was found that on average, 250 kilograms per ha of woody shrubs are annually collected for fuel wood from the rangelands (Maarten, 1996). The situation is the same or even worse in other areas of Baluchistan, as fuel wood availability is limited. 78. The TXL ROW land is plain rangeland to steep mountain slopes. However, some grass growth, a very few bushes, no trees or built–up structures are found there.

3. Protected Areas / National Sanctuaries 79. The history of state involvement in conservation dates back to the Baluchistan Forest Regulation (1890). The Forest Department took control of forests and game–reserves on state lands. In 1960, 831,000 has of the former Kalat State were declared Protected Forests under the Forest Act 1927 when the state was merged with Pakistan. The Forest Department currently holds about 3% (1.086 million has) of the land. This includes forests, rangelands, wildlife areas and many deforested lands. In addition to affording legal protection to the forest areas, 22 threatened tree species were given legal protection under the Reserve Trees Rules (1901). The Baluchistan Wildlife Act (1974) provides for the establishment of national parks, wildlife sanctuaries and game reserves.

80. There are two national parks with an area of 646,464 has; 14 wildlife sanctuaries totaling 967,592 has; eight game reserves covering 409,719 has; five private game reserves; and one community conservation area with a core area of 300 square kms (Table 14 and Map 4 in Maps section).

81. Industrial effluents discharged into rivers and streams not only kill aquatic life or contaminate freshwater life, but also find their way to the open sea, where marine habitats are affected.

D. Economic Development

1. Agriculture, Industries & Tourism

82. Cropping Pattern. The main crops in the Subproject area during winter are wheat (tricticum sativum), gram, barley (hordeum vulgara), oil seeds, Taramira, Sarson and Toria,

20 fodder. In summer sugarcane, cotton, Jawar, Bajra (pennisetum) and rice, Maize, pulses, potato, tobacco and cotton (gossypium genus) are grown.

83. Horticulture. The main fruits grown in the Subproject area are date, orange and mango [Dera Ghazi Khan]. In De-Excluded area at Khar near Fort Munro, there is a garden of fruits where mulberry, vine, fresh olive, almond, peach, plum and apricot are grown. Climate of Barkhan and Musakhel and Loralai is favorable for horticulture. The main fruits grown in the Subproject area are almond, apple, apricot, grape, peach, plum, pomegranate, cherry, pistachio, fig and other fruits and vegetables.

84. Minerals. Main minerals are petroleum, natural gas, uranium, gypsum, limestone, etc. No minerals are reported from Barkhan and Musakhel Districts. The Duki tehsils is the coal producing region of the Loralait where coal-mining activity offers a highly lucrative investment outlet by virtue of the fact that a ready market exists in the neighboring Punjab province. However, entry into the field is relatively restricted and only a handful of entrepreneurs are reaping the benefit. The local consumption of coal is almost negligible and is primarily used for domestic heating / cooking purposes. A limited number of low-grade marble deposits are also being worked and the production again ends up in Punjab.

85. Industry. There are nine major Industrial units of cotton ginning and pressing, cotton textiles, a cement factory and vegetable oil factory. Dera Ghazi Khan is well known for lacquered articles such as wooden / electric lamps, mirror frames, pottery, furniture and several other articles of decoration. There are cotton seed oil factories at 2 km from the TXL. There are no industrial units in Barkhan and Musakhel. The commercial activities are limited due to absence of infrastructure, roads, electricity, credit facilities, skilled manpower and technical support which are considered the prerequisite for enterprise development. No major industry, as such, exists in the district. However, cottage industry based on handicrafts and embroidery produced by the local womenfolk is a fairly thriving commercial enterprise, supplementing the income of the individual households. Apart from this, small scale auto and electrical goods repair outfits are operating in Loralai town where other commercial activities such as whole selling, retailing, hotels, and restaurants are also found.

86. Tourism. There are many places of interest that attract tourists and promote tourisms e.g. Fort Munro (is situated at a height of 1,890 m above sea level), There are gardens, orchids, beautiful bungalows, government offices. During summer season, climate of this place remain cool and mercury goes up to 4 to 7oC. It is used as summer resort during hot weather, Dam, lake and Trimmu waterfalls situated near Fort Munro are good picnic spots. Shrines of , Zinda Pir, Derah Din Panah, , Muhammad Suleman at Taunsa are religious places to visit. There are no places worth mentioning in Barkhan and Musakhel. There are no archaeological sites or other worth mentioning historical landmarks.

2. Transportation

87. The Subproject area i.e., Dera Ghazi Khan, Barkhan, Musakhel and Loralai Districts are linked by road to Punjab province to the northeast and to the provincial capital Quetta to the southwest. Approximately 38 km of the portion of main Highway running from Dera Ghazi Khan to Quetta via Loralai falls in the Barkhan District. Only 72 kms of National Haighway (N–70) passing through the Kingri area of the District is metalled besides there is only one metalled road i.e, from Barkhan to Rakhni 51 km. All other roads are single or Kacha and are in a very poor position Kingri to Musakhel road has been constructed. It is linked with Killa Saifullah 21 district which lies to the northwest and to Sibi district lying to the southeast. The Subproject area is accessible through Dera Ghazi Khan Loralai road. All tehsils headquarters are connected with districts headquarters by roads. The Subproject area does not have any railway linkage. However, it is connected by Dera Ghazi Khan and Quetta airports to other parts of the country.

3. Energy Sources

88. The transmission lines for electrical power run to a main grid substation Dera Ghazi Khan. The existing 220 kV Dera Ghazi Khan Grid Station, owned by Electric Power Company, transmits power to the load centres. A 132 kV substation feeds the customers in the area of Barkhan District, 132 kV Musakhel substation feeds the customers in the Musakhel area. The 11 kV distribution lines for electrical power originate from the existing, Quetta Electric Supply Company owned, 132 kV Loralai sub station. 132 kV Loralai substation feeds the customers in the area. The 11 kV distribution lines for electrical power originate from the existing, Quetta Electric Supply Company owned, 132 kV Loralai substation.

89. Reserves of fossil fuels is the main source of energy in Pakistan, others are derived from hydropower. In the study area, there is no source of hydropower and other energy sources are progressively more common further away from the major towns. The biomass sourcing is concentrated on home garden production of fuel wood, the extraction of wood from forests, woodland, crop plantations and agricultural residues. The other significant energy sources in the Subproject areas are kerosene and liquefied petroleum gas (LPG). There are numerous petrol stations and LPG dealers in these districts.

E. Social and Cultural Resources

1. Population Communities and Employment

90. The total population of Dera Ghazi Khan District was1,643,118 as enumerated in March 1998. The population of Barkhan was 103,545, Musakhel 134,056 and Loralai 297,555 as mentioned in Statistical Book, 2007. The 1998 Census and Statistical Book shows the population of the Subproject area is predominantly 99% – 100% Muslim in rural areas. The next higher percentage in Dera Ghazi Khan is of Ahmadis with 0.2% followed by scheduled castes 0.10%. Other minorities like Christians, Hindus (Jati), etc are small in number. The proportion of population of Muslims in rural and urban areas is over 99%. Ahmadis in urban areas are 0.4 % and rural areas 2%. Christians are more in urban areas as compared to their proportion in rural areas. The Hindus (Jati) are very small in number in rural area. Siraiki is the predominant language being spoken in the Dera Ghazi Khan district, representing 80% of the population, followed by Balochi which spoken by 14%, 3% and Punjabi 1%. Others speak Sindhi, Pushto, Barahvi, Dari, etc. In Barkhan, predominant language is Balochi spoken by 75 % of the population. In Musakhel, 79% population speak Pushto, next language is Balochi spoken by 14%, of the population. Pushto is the predominant language being spoken in the Loralai district, representing 93% of the total population followed by Balochi spoken by 3%. Only 5% speaks Urdu, Punjabi, Sindhi, Siraiki, etc.

91. Of the total economically active population, 75% were registered as employed in 1998 in Dera Ghazi Khan. Nearly three-fourths, i.e. 73 %, were self-employed, 10 % private employees and 6 % government employees. Unpaid family helpers were recorded as 10 %. The difference in proportions of employed population was significant between the genders and urban and rural

22 residences. The economically active population of the Loralai area is 25%. Out of the employed population 51% are self-employed, 32% working as employee (Govt. autonomous and private) and 15% are unpaid family helpers. The economically active population of Barkhan is 21%. Out of this, 76% are self-employed, 13% working as employees (Govt. Autonomous and Private) and 11% are unpaid family helper. The economically active population in Musakhel is 19%. Out of this, 67% are self employed 22% working as employees (Govt. Autonomous and private) and 10% are unpaid family helper.

92. The main occupation of women in rural areas including the Subproject area of Dera Ghazi Khan, Barkhan, Musakhel and Loralai is housekeeping which includes attending to the cattle, extracting butter and Ghee from milk, collection of firewood, weaving, embroidery and sewing of family clothes. Women strictly remain within the boundary walls except for going out to bring drinking water from springs/wells. In city, women are housewives or work as professional doctors, nurses, teachers and health visitors. 93. The degradation of natural resources has a major impact on women’s lives. It is generally the women who collect fuel wood and cut the grass for forage. Fuel wood and fodder, once within their reach, are now harder to find. As a result, they have to invest a lot of their time in this activity. The cutting of Pistachio trees for fuel and of edible pine trees for timber has reduced family income and a source of nutrition.

2. Education and Literacy

94. The literacy ratio in Dera Ghazi Khan District is 31% in 1998. The literacy ratio for males is 42% and 18% for females. Literacy is much higher in urban areas compared with rural areas for male and female. The literacy of Barkhan District is 16%. The male literacy ratio is 34% compared to 6% for female. Literacy is much higher, i.e. 37%, in urban areas compared with rural areas, i.e. 14% for male and female. The literacy ratio of Musakhel is 10%. The male literacy ratio is 14% compared to 5% for female. Literacy is much higher i.e. 16% in urban areas compared with rural areas i.e. 10% for male and female. The literacy ratio of the Loralai District is 20%, 53% in urban areas and 16% in rural areas. The male literacy ratio is 30% as compared to 9% for female.

95. There is no separate girls' school in the villages along TXL ROW. The inhabitants do not send their daughters in the co-education schools and women requested for separate girls' school in their village or even their joint family houses. There are primary, middle, and high schools, colleges with M.A. M.Sc. classes in the Subproject area including Dera Ghazi Khan, Barkhan, Musakhel and Loralai town. The educational institutions in the district are as follows:

23

Table 1: Educational Institutions by Level of Education, 1997-98 Institution Number Enrolment SCHOOL Primary 1405 85000 Middle 142 26000 High 99 42000 Higher Secondary 8 5347 (I-XII Classes) COLLEGES Degrees 4 5790 Intermediate 1 268 TECHNICAL/ PROFESSIONAL INSTITUTE Technology/ Polytechnic 2 915 Institute Commercial Training 12 1493 Institute Vocational Institute 12 569 Source: Punjab Development Statistics, Bureau of Statistics Punjab, 1995-96.

Table 2: Educational Institutions by Level of Education, 1997-98 Institution Number Enrolment SCHOOL Primary 1405 85000 Middle 142 26000 High 99 42000 Higher Secondary 8 5347 (I-XII Classes) COLLEGES Degrees 4 5790 Intermediate 1 268 TECHNICAL/ PROFESSIONAL INSTITUTE Technology/ Polytechnic 2 915 Institute Commercial Training 12 1493 Institute Vocational Institute 12 569 Source: Punjab Development Statistics, Bureau of Statistics Punjab, 1995-96.

Table 3: Educational Institutions by Level of Education, 2006 (Barkhan District) Institution Number of Institutions Enrolment Male Female SCHOOL Primary 394 171 6948 + 5459 = 12407 Middle 14 3 1032+190 = 1222 High 11 2 13 Higher Secondary 0 0 0 PRIVATE SCHOOLS 9 1121+207 = 1328 COLLEGES Degrees 0 0 0 Intermediate 1 0 412 TECHNICAL/ PROFESSIONAL INSTITUTE Technology/ Polytechnic 2 915 Institute Commercial Training

24

Institute Vocational Institute Source: Government of Baluchistan, Quetta Development Statistics, Bureau of Statistics, 2007.

Table 4: Educational Institutions by Level of Education, 2006 (Musakhel District) Institution Number of Institutions Enrolment Male Female SCHOOL Primary 178 55 5118+2283 = 7401 Middle 8 3 1040+498 = 1538 High 7 2 1460+495 = 1955 Higher Secondary PRIVATE SCHOOLS 3 COLLEGES Degrees 1 0 21 Intermediate 1 1 228+30 = 258 TECHNICAL/ PROFESSIONAL INSTITUTE Technology/ Polytechnic Institute Commercial Training Institute Vocational Institute Source: Government of Baluchistan, Quetta Development Statistics, Bureau of Statistics, 2007.

Table 5: Educational Institutions by Level of Education, 2006 (Loralai District) Institution Number of Institutions Enrolment Male Female SCHOOL Primary 435 152 14557+13705 = 28262 Middle 16 5 3672+1420 = 4092 High 13 3 3995+1821 = 5816 Higher Secondary – – – PRIVATE SCHOOLS 16 3297+476 = 3773 COLLEGES Degrees 1 1 304+118 = 411 Intermediate 2 0 747+247 = 994 TECHNICAL/ PROFESSIONAL INSTITUTE Technology/ Polytechnic Institute Commercial Training Institute Vocational Institute Source: Government of Baluchistan, Quetta Development Statistics, Bureau of Statistics, 2007.

3. Health Facilities

96. In Dera Ghazi Khan District, there are 6 hospitals with 305 beds, 35 dispensaries with 14 beds, nine Rural Health Centers with 180 beds, 52 Basic Health Units with eight beds along with one T.B. Clinic, 34 Sub-Health Centers and six Mother Care Health Centers are functioning day and night for providing the medical facility to the people of the district. According to the Statistics Book, 2007 there is one hospital with ten beds and 10 dispensaries. Six BHU, two MCH and no T. B. Clinic, 11 doctors, no nurse, 21 LHV, 22 Dais / midwives in Barkhan district in Musakhel there is one hospital with 25 beds, 15 dispensaries, one rural health center with 10 beds, six BHU, two MCH, 13 doctors, no nurse, 3 LHV, 28 Dais / midwives, while in Loralai District, there are two government hospitals, 138 beds, 47 dispensaries, two rural health centers 25 with 20 beds on private side. Two private hospitals with 12 beds, two rural Health centers, 27 basic health units, 56 dispensaries, one health auxiliary, five Mother and Child Health Care Centers, one Leprosy clinic and one School Health Services Unit, 57 doctors, seven nurses, 26 LHV, 1,060 Dais / Midwives in Loralai. No medical facilities are available in villages along TXL corridor. However, all health facilities including civil hospital are located in Towns and Cities. The roads' condition is not good and transport facilities are not sufficient to go to medical centers. But due to non-availability of specialists’ doctors and paramedical staff, a large number of patients have to go Dera Ghazi Khan and / or Quetta to get treatment.

4. Cultural Heritage and Community Structure

97 There are no official heritage sites or historic, religious or archeologically important sites located in the Subproject works areas. There are no major historic or archaeological features of note but line passes over graveyard at few places. There are a few places of worship / mosques within about 500 m of the works.

98 The inhabitants of the Dera Ghazi Khan District are predominantly Baloch belonging to various tribal groups. Nutkani, and tribes are in overwhelming majority in Taunsa Tehsil, whereas Sori , Khosa, and Leghari tribes dominate in . Aside from this, people belonging to smaller sub-tribes such as and Jaskan are settled in the entire district. Khitran, Pathans dominate in the villages situated in the north-west of Taunsa Tehsil, which formerly formed a part of Dera Ismail Khan District. Apart from this, the people of other tribes, i.e. Syed, Pathan, Mughal, Jat, Arain, Awan, Rajput,and Jats, are scattered all over the district but they are found mostly in area along the Indus. The Barkhan District is mainly inhabited by three main tribes namely , and Buzdar. The Principal tribe is Khetran which is very mixed race. They have a chief or Tumandar, a headman or Wadera for each clan or section. The major tribes of Musakhel are Musakhels, the principal divisions of which are Belkhels and Laherzais, Jafar (Afghan), Isot Afghan, Zimiri (Afghan), Syed, Qaisarani (Baloch) and Buzdar (Baloch). The languages spoken are , Jafarki and Balochi.

99. While main tribes that inhabit Loralai are Kakars, Dummars, Tareens, Lunis, Zakhpels, Nasirs, Pachis Syeds together with Ghilzais, Sulemankhels Baloch and Marris constitute the principle tribes of the District. With the exception of Baloch and Marris, the remaining tribes are all Pashtoons. All the affected households are Muslim and ethnically Baloch, Khetran and Pushtoons. IV. SCREENING POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

A. Project Location

1. Impact Assessment and Mitigation

100. This Subproject will involve the construction of a TXL, most sensitive receivers are set well back from the TXL ROW, just outside the 20 m radius of the subproject in some areas.

101. The location and scale of the works are very important in predicting the environmental impacts. This process of impact prediction is the core of the IEE process and it is critical that the recommendations and mitigation measures are carried out with reference to the conditions on the ground in the affected areas in the spirit of the environmental assessments process. In this

26 section, the potential environmental impacts are reviewed. Where impacts are significant enough to exceed accepted environmental standards, mitigation is proposed in order to reduce residual impact to acceptable levels and achieve the expected outcomes (minimization of crop and asset damages; noise and dust mitigation; redress of damages to infrastructure; management of transport and construction machinery to minimize inconvenience to adjoining settlements; minimize invasion of privacy impacts) of the Subproject being implemented. Therefore, it is essential that a proper analysis is carried out during the project planning period. In this regard, the impact prediction plays a vital role as these predictions are used for developing mitigation measures and any alternative options, if appropriate. When the detailed designs are completed, the impacts and mitigation measures will need to be further reviewed to take into account how the contracts are set up and in the light of any fine tuning of the Subproject proposals.

102. The potential environmental impacts in the design, construction and operational phases are assessed below. Where impacts are significant enough to exceed accepted environmental standards, mitigation is proposed in order to reduce residual impact to acceptable levels and achieve the expected outcomes of the project. The criteria for assessment are the national standards and criteria set by the GOP. Where GOP has not set a standard or guideline criterion the standards given in World Banks publication Pollution Prevention and Abatement Handbook6 are used as criteria. The EMP is presented in Appendix 2 as a matrix of mitigation measures to prevent or minimize the impacts .

103. The environmental management plan (Section 5 and EMP matrix Attachment 2) shall be revised at project inception and through construction in order to feed back any significant unpredicted impacts. It is based on the analysis of impacts, primarily to document key environmental issues likely to arise from subproject project implementation, to prescribe mitigation measures to be integrated in the project design, to design monitoring and evaluation schedules to be implemented during subproject project construction and operation, and to estimate costs required for implementing subproject mitigation measures. The EMP plan must be reviewed at the subproject inception by the project management and approved before any construction activity is initiated, to take account of any subsequent changes and fine tuning of the proposals

2. General Approach to Mitigation

104 During the preparation for the Subproject construction phase, the future contractors must be notified and prepared to cooperate with the executing agency, project management, supervising consultants and local population in the mitigation of impacts. Furthermore, the contractor must be primed through bidding stages and the contract documentation to implement the EMP in full and be ready to engage trained environmental management staff to audit the effectiveness and review mitigation measures as the project proceeds. The effective implementation of the EMP will be audited as part of the loan conditions and the executing agency (NTDC) must be prepared for this. In this regard, the NTDC must fulfill the requirements of the law and guidance prepared by PEPA on the environmental aspects of power projects and the recommendations already made for Subproject in this IEE and under PEPAct.

6 Pollution Prevention and Abatement Handbook 1998, World Bank Group, Washington D.C.

27

105. The location of the residences, mosques, schools, hospitals and civic cultural and other heritage sites has been reviewed in Section III. Some of the residences and schools are close enough to Subproject that there will be potential impacts in the construction stage from disturbance and significant noise and dust. Water is available in the study area although surplus water may not always be available to suppress dust at many locations in the dry season. Therefore as a general approach it is recommended that where works are within 10m of any sensitive receivers, the contractor should install segregation between the works and the edge and the sensitive receivers. The segregation should be easily erectable 2.5 m high tarpaulin sheet and designed to retain dust and provide a temporary visual barrier to the works. Where dust is the major consideration the barrier can take the form of tarpaulins strung between two poles mounted on a concrete base. These can be moved along from tower base to tower base the power as the work proceeds. Where noise is a major consideration (say outside schools or hospitals) construction should be avoided at sensitive times. As a fall back option to control noise, the mass of the barriers can be increased using block-board or corrugated metal sheet to supplement the tarpaulins. In addition to the physical effect of mitigating dust and noise the installation of such measures should be discussed with the local population and serve as a vehicle for further public consultation at the implementation stage to assist in public relations.

3. Cultural Heritage, Mosques, Temples, Religious Sites & Social Infrastructure 106. The location of mosques, cultural, heritage sensitive receiver sites and infrastructures has been reviewed in Section III. There are no mosques or religious sites near the works, except that the line will cross over graveyards at a few locations [Appendix 7]. It will traverse mostly barren hilly and rough lands (95.74%), and minimally the tube-well irrigated farmlands (4.26%), no land will be acquired permanently. The TXL will affect 734.96 ha of land of which 31.28 ha are productive land and 703.68 ha unproductive land and will affect a total of 126 households with a total population of 1,232 affected persons, who are all landowner farmers. The new 245.01 km TXL will traverse lands of some 21 villages. It may partially affect or damage some seven stone-mud built houses and one boundary (which will not require demolition/relocation), and affect crops and trees of a total of 88 households (1,232 Affected Persons). Of the total 755 towers, only 723 towers will be constructed on barren hilly and rough lands, while only 32 towers (4.24%) will be constructed in privately owned farmlands. The majority of the towers are straight towers and in some cases, to avoid and/or minimize impacts, some 118 angular towers (Angle Markers) will be constructed. Moreover, 4-6 m leg extensions will be provided to the corresponding towers, to maintain 7-8 m vertical clearance to the tops of the likely affected eight structures (7 houses and 1 boundary wall), falling partially within the 30 m wide corridor. Aside from affecting agricultural crops on 31.28 ha of farmlands, some 356 trees (152 fruit trees and 204 wood trees) will need to be removed from the 30 m wide corridor of impact. Aside from these, no other built-up structures, whether private or community owned, will be affected. None of the 755 towers will be constructed in an urban or compact village housing areas, nor will any of these towers have a low-bar to restrict the future use of farmlands under the towers. The overall impacts on social infrastructure, therefore, will be temporary and minor and no land under any tower will be affected and acquired permanently. 107. The clinic / hospitals are all at more than 2 km from the edge of the TXL Subproject in Dera Ghazi Khan, Barkhan, Musakhel and Loralai town and there will be sufficient buffer distance between the works and the sensitive receiver as such that no major significant impact would be expected from the works [Appendix7].

28

108. The location of schools is more than 200 m – 2 km from the edge of the Subproject. There will be sufficient buffer distance between the works and all the sensitive receiver is well away from the TXL [Appendix 7] and as such, there is no significant impacts that can be expected. Public consultation should be undertaken at the implementation stage to ensure nuisances are not allowed to escalate.

4. Cut and fill

109. The Subproject work should not involve any significant cutting and filling but minor excavations (down to 4 m) and piling will not be required at the TXL ROW site to create the footings for the towers with the exception of a few locations where tower will be installed in nullahs (flood streams) and it is envisaged (depending on the mode of contract) that the surfaces under the towers will need to be scrabbled to remove unstable materials, or to stockpile topsoil.

110. Mitigation measures must focus on the minimization of impacts. In order to allow the proper functioning of the settlement sites (access to villages) during construction, it is recommended that consideration be given to erect temporary hoardings immediately adjacent to the nearest houses and shops if they are within 15 m of the TXL construction site.

111. If surplus materials arise from the removal of the existing surfaces, these can be used elsewhere on the project before additional soil rock, gravel or sand extraction is considered. The use of this immediately available material will minimize the need for additional rock based materials extraction in this stretch. The Subproject detailed designers have so far estimated that no substantial additional materials will be required subject to confirmation at the detailed design stage.

112. At this stage, no areas require removal of woodland. However, if specimen trees of religious plantations are affected the owners should be given the resources and opportunity to reinstate the woodland long term and a plantation compensation plan should be drawn up to replant the woodland/trees. In the event that the land is not suitable for plantation, then other areas should be identified to replace the cut trees and sufficient areas should be identified to allow plantation of trees at a rate of say 5:1. The replacement ratio should allow for a high mortality rate among the newly planted trees in the dry environment or otherwise as based on advice from the District Forest Officer.

113. Contractual clauses should be included to require each contractor to produce a materials management plan (1 month before construction commences) to identify all sources of cement and aggregates and to balance cut and fill. The plan should clearly state the methods to be employed prior to and during the extraction of materials and all the mitigation measures to be employed to mitigate nuisances to local residents. Financial compensation shall not be allowed as mitigation for environmental impacts or environmental nuisance. Mitigation measures shall seek to control the impacts at source in the first place. The engineer shall be responsible to update the Subproject cut and fill estimates and create Materials Master Plan to facilitate materials exchange between the different contract areas along the power line and sub- contractors on the power line and to provide an overall balance for materials and minimize impacts on local resources.

114. Land holders will be paid compensation for their standing trees in accordance with prevailing market rates (as per LARP). The land holders will be allowed to salvage the wood of the affected trees. They will also be encouraged to plant suitable new trees outside the 30 m 29 corridor of the transmission line in lieu of tree removed. The contractor’s staff and labor will be strictly directed not to damage any vegetation such as trees or bushes. Clearing of green surface cover for construction, for borrow or for development, cutting of trees and other important vegetation during construction should be minimized. Landscaping and road verges to be re-installed on completion. Compensatory planting of trees/shrubs/ornamental plants (at a rate of 5:1) to contribute to the aesthetic value of the area and compensate for the lost capability of the area to absorb carbon dioxide in line with best international practice. At completion, all debris and waste shall be removed.

B. Potential Environmental Impacts

1. Encroachment, Landscape and Physical Disfiguration

115. Prior to the operation of the Subproject, TXL will be constructed. The extent of the proposed power expansion is moderate and should not at all extend beyond the TXL corridor or boundary in Subproject area. No significant additional landscape impacts (other than the impact of the construction of the transmission line ) can be expected from construction of the Subproject [Appendix7].

116. Disposal of surplus materials must also be negotiated through local authority approvals prior to the commencement of construction.

2. Trees, Ecology and Protected Areas 117. Surveys have been made all along the TXL ROW and line alignment of Subproject. Trees are present at a few locations in cultivated areas and fruit gardens in the ROW site. The land is covered with scanty grasses, and some bushes are found and there may not be a need for any disturbance of trees in most of the Subproject works area [Appendix 6]. A total 356 trees will require removal from the 30 m wide corridors of the new transmission line. Of the 356 affected trees, 152 are fruit trees (42.7%) and 204 (57.3%) are wood trees. Six Almond orchards will be affected only partially. Among the 152 affected fruit trees, 88 Almond trees (57.9%) are found in six compact Almond orchards, while 64 affected fruit trees (42.1%) are found scattered within the 30 m wide corridor of the transmission line. Of the 64 scattered fruit trees, there are 40 Almond trees and 24 Berri (zizyphus) trees. Among the 204 affected wood trees, kikar (acacia) shisham (Dalbergia sisso), poplar/eucalyptus, willow, etc. are found scattered in the Subproject area. 118. If for some unforeseen reason Reserved Trees or other trees do need to be removed, permission should be obtained from the forest user group and Department of Forests after written justification.

119.. A requirement shall be inserted in the contracts that no trees are to be cut in the ROW without the written permission from the Supervising consultant who may permit the removal of trees if unavoidable on safety and technical engineering grounds after written justification to the satisfaction of the local user groups or Department of Forests.

30

3. Hydrology, Sedimentation, Soil Erosion

120. Some drainage streams en–route the Subproject ROW [Appendix 7] so the project should be impeded to some extent by the works and the scale of the works does warrant hydrological monitoring. Refer to Appendix 7 for likely impacts upon waterways and ponds.

121. Compile temporary drainage management plan 1 month before commencement of works. Proper installation of temporary drainage and erosion control before works within 50 m of water bodies should be done. Proper construction of temporary drainage and erosion control measures, maintenance and management including training of operators and other workers to avoid pollution of water bodies by the considerate operation of construction machinery and equipment. Storage of lubricants, fuels and other hydrocarbons in self-contained dedicated enclosures should be >50m away from water bodies. Proper disposal of solid waste from construction activities and labor camps should be ensured. Cover the construction material and spoil stockpiles with a suitable material to reduce material loss and sedimentation and avoid stockpiling near to water bodies. Topsoil stripped material shall not be stored where natural drainage will be disrupted. Borrow sites (if required) should not be close to sources of drinking water.

122. Temporary erosion control plan should be prepared 1 month before commencement of works. Proper installation of Temporary Drainage and Erosion Control should be provided before works within 50 m of water bodies. Back-fill should be compacted properly in accordance with design standards and graded to original contours where possible. Excavated areas should be treated against flow acceleration while filled areas should be carefully designed to avoid improper drainage. Stockpiles should not be formed within such distances behind excavated or natural slopes that would reduce the stability of the slopes. In the short-term, either temporary or permanent drainage works shall protect all areas susceptible to erosion. Measures shall be taken to prevent ponding of surface water and scouring of slopes. Newly eroded channels shall be backfilled and restored to natural contours. Contractor should arrange to adopt suitable measures to minimize soil erosion during the construction period. Contractor should consult concerned authorities in the area before deciding mitigation measures. Clearing of green surface cover to be minimized during site preparation. Replanting trees to be done before the site is vacated and handed back to NTDC with appropriate trees (other vegetation cover as appropriate) to ensure interception of rainwater and the deceleration of surface run-off.

4. Air Pollution from Earthworks and Transport

123. All heavy equipment and machinery shall be fitted in full compliance with the national and local regulations. (Relevant regulations are in the Motor vehicles fitness rules and Highway Act). Stockpiled soil and sand shall be slightly wetted before loading, particularly in windy conditions. Fuel-efficient and well-maintained haulage trucks shall be employed to minimize exhaust emissions. Vehicles transporting soil, sand and other construction materials shall be covered. Limitations to speeds of such vehicles are necessary. Transport through densely populated area should be avoided. To minimize the dust within the vicinity of orchards and fruit farms, spraying of bare areas with water is planned.

124. Field observations indicate that ambient air quality is generally acceptable and that emissions from powered mechanical equipment are rapidly dispersed. 31

125. Earthworks will contribute to increasing dust, and the foundation earthworks will generate dust and the following mitigation measures are needed: (i) Dust suppression shall be undertaken where towers are within 50 m of houses. (ii) Construction materials (sand, gravel, and rocks) and spoil materials will be transported trucks covered with tarpaulins. (iii) All vehicles (e.g., trucks, equipment, and other vehicles that support construction works) will comply with the national vehicle regulations. 126. The need for large stockpiles should be minimized by careful planning of the supply of materials from controlled sources. Stockpiles should not be located within 50 m of schools, hospitals or other public amenities such as wells and pumps and should be covered with tarpaulins when not in use and at the end of the working day to enclose dust.

5. Noise, Vibration and Blasting

127. Noise impacts from the construction of the TXL should be reviewed at the detailed design stage. Such equipment should be located within TXL corridor or boundary far from sensitive receivers as possible to prevent nuisances to dwellings and other structures from operation. Appendix 7 identifies six locations where noise could be a problem. See Annexure 1 for standards.

128. It is anticipated that powered mechanical equipment and a lot of local labor with hand tool methods will be used to construct the Subproject towers works. Blasting is anticipated. Powered mechanical equipment can generate significant noise and vibration. The cumulative effects from several machines can be significant. To minimize such impacts, the contractor for Subproject should be requested by the Engineer to provide evidence and certification that all equipment to be used for construction is fitted with the necessary air pollution and noise dampening devices to meet NTDC requirements.

129.. At nearby schools, the contractor shall discuss with the school principals the agreed time for operating these machines and completely avoid machine use near schools during examination times.

130. Conduct detailed acoustic assessment for all residential, school, (other sensitive structures) within 50 m of ROW. If noise at sensitive receiver exceeds the permissible limit, the construction activities should be monitored and controlled. Locations that may require such assessment have been identified and presented in Appendix 7.

6. Air pollution and noise from the enhanced operations

131. The Subproject works will extend the power transmission lines but no settlements, villages and schools will be close to the facilities in the operational phase. Noise from local power transmission in the villages is not currently a major consideration and cumulative effects of the expanded system should not be a problem. Nevertheless, certain residences, places of worship and schools will be quite close to the expanded TXL. Therefore, it is recommended that an acoustical check be made on the detailed design to determine of any noise barriers are required.

32

7. Sanitation, Solid Waste Disposal, Communicable Diseases

132. The main issues of concern are uncontrolled defecation by construction workers, unmanaged disposal of solid and liquid wastes into watercourses, natural drains and improper disposal of storm water and black water in the village areas.

133. In order to maintain proper sanitation around construction sites, provision of temporary toilets will be made. Construction worker camps will not be located in settlement areas or near sensitive water resources.

134. Identify location of work camps in consultation with local authorities. The location shall be subject to approval by the NTDC. If possible, camps shall not be located near settlements or near drinking water supply intakes. Cutting of trees shall be avoided and removal of vegetation shall be minimized. Water and sanitary facilities (at least pit latrines) shall be provided for employees. Worker camp and latrine sites to be backfilled and marked upon vacation of the sites. Solid waste and sewage shall be managed according to the national and local regulations. As a rule, solid waste must not be dumped, buried or burned at or near the project site, but shall be disposed of to the nearest sanitary landfill or site having complied with the necessary permits of local authority permission. The Contractor shall organize and maintain a waste separation, collection and transport system. The Contractor shall document that all liquid and solid hazardous and non-hazardous waste are separated, collected and disposed of according to the given requirements and gelatins. At the conclusion of the Project, all debris and waste shall be removed. All temporary structures, including office buildings, shelters and toilets shall be removed. Exposed areas shall be planted with suitable vegetation. NTDC and Supervising Engineer shall inspect and report that the camp has been vacated and restored to pre-project conditions

8. Disease Vectors

135. Vectors such as mosquitoes will be encountered at any standing water which is allowed to accumulate in the temporary drainage facilities, improper storm water management in the settlement areas, improper disposal of wastewater generated from the local wells or water accumulating in borrow pits. Temporary and permanent drainage facilities shall be designed to facilitate the rapid removal of surface water from all areas and prevent the accumulation of surface water ponds.

9. Pollution from oily run-off, fuel spills and dangerous goods

136. Control measures for oily residues, lubricants and refueling are prescribed in the EMP. Control measures in Subproject maintenance yards have been created but they have no dedicated drainage which can capture run-off. Oily residues and fuel should be captured at source and refueling and maintenance should take place in dedicated areas away from surface water resources. No significant impacts should be allowed to arise in Subproject. Used oil and lubricants shall be recovered and reused or removed from the site in full compliance with the national and local regulations. Oily wastes must not be burned. Disposal location will be agreed with local authorities/EPA. Machinery should be properly maintained to minimize oil spill during the construction. Solid waste should be disposed at an approved solid waste facility open burning is illegal and contrary to good environmental practice 33

137. Avoid disposal of wash water, solid waste and discarded packing, etc. on wetlands. Piling up of loose material should be done in segregated areas to arrest washing out of soil. In addition, these materials should not be tipped or stockpiled near wetlands . Leftovers from concrete works should not be dumped close to wetlands. Avoid temporary structures or *stockpiling within banks of river and on wetlands. Special measures will be adopted to minimize impacts on the wild birds, such as avoiding construction activities during the critical periods of breeding and feeding. Staff working on the Project should be given clear orders, not to shoot, snare or trap any bird. During the period of migration of birds from Central Asia to the plains of , which are normally the coldest months of December and January and their return journey during February/March, the construction activities, around the wetlands should be kept as efficient as possible to minimize impacts and to encourage these migratory birds to settle at normal feeding grounds in wetlands. The contractor will prevent the workers from hunting and fishing for water birds and fish resources, etc. Food and fuel will be provided by the contractor from local villages. Erection of towers in the wetlands will be avoided as far as possible. However, at places where realignment of the transmission is unavoidable, towers with maximum span will be used to minimize the impacts.

10. Social 138. Potential for spread of vector borne and communicable diseases from labor camps shall be avoided (worker awareness orientation and appropriate sanitation should be maintained). Claims/complaints of the people on construction nuisance/damages close to ROW to be considered and responded to promptly by the contractor, contractor should organize temporary means of access and make alternative arrangements to avoid local community impacts and to avoid such short-term negative impacts.

C. Environmental Impacts During Detailed Design and Pre-construction Phase

139. The line alignment of the Project and construction are critical in determining the environmental impacts and route selection and the related impacts have been discussed in Chapter 3. There are also a number of other matters that will require detailed designs that consultant engineers will prepare and it is assumed that the detailed designs will avoid construction impacts by good design and to minimize operational environmental pollution impacts as far as practicable. In line with ADB policy on environmentally responsible procurement, opportunities to provide environmental enhancements have been identified and will also be included in the detailed designs. Routine matters such as avoiding unnecessary removing of trees will also require attention in the detailed design and preconstruction stages. Opportunities for enhancements during detailed design, construction and operation, which are envisaged at this stage, have also been included in the EMP to be reviewed at the detailed design stage (DDS).

1. Review of impact assessment, mitigation, and EMP

140. The EMP will be reviewed during the implementation phase at the detailed design stage in line with best practice as required by ADB. A check will be made at the detailed design stage that the alignment has been designed as planned to ensure the route is as described in the EIA and the RRP for ADB with the same land acquisition. If there are changes in project scope or alignment these will be disclosed to EPA and the EIA, LARP and EMP will be revised. The

34 revised EIA, LARP and EMP will be resubmitted to ADB, incorporating any recommendations and requirements from EPA.

141. The EMP (section 5 and EMP matrix Appendix 2) has been compiled based on the EMP principles promulgated by EPA, in a format familiar to ADB. The EMP is a working document and will need to be reviewed in due course at inception and throughout construction in order to feed back any significant unpredicted impacts. It is based on the analysis of impacts, primarily to document key environmental issues likely to arise from project implementation, to prescribe mitigation measures to be integrated in the contract documentation, project design, to design monitoring and evaluation schedules to be implemented during project construction and operation, and to estimate costs required for implementing mitigation measures. The EMP must be reviewed at the inception phase by the project management when the detailed designs are complete and the EMP will be approved by NTDC Environmental and Social Implementation Cell (ESIC) before any construction activity is initiated, to take account of any changes and fine tuning of the design proposals.

2. Social Impacts and Resettlement

142. The need for social preparation of the APs has been included in the social assessment. The LARP has been completed to clarify the entitlements for resettlement and for compulsory purchase of land and other matters for compensation. The social preparation will be completed prior to commencement of construction. All acquisition of lands and monetary compensation will be completed to minimize the uncertainty of people. All the payments/entitlements will be paid according to the principles established in the entitlement matrix prepared as an integral part of the LARP the details of which may be amended if there are changes in alignment.

3. Project disclosure

143. The preliminary design has been disclosed to the EPA and public consultations have been conducted based on the preliminary alignment designs presented in Appendix 10. The environmental clearances which will be required from EPA have also been identified (in principle) subject to confirmation at the Detailed Design Phase (DDS).

144. It is common for the alignment of power transmission line projects to undergo some or fine tuning during the detailed design phase.. The final alignment shall be disclosed to EPA at the detailed design stage and the EMP must be reviewed.

4. Environmentally Responsible Procurement (ERP)

145. During the detailed design phase and in preparation for the construction phase, the Detailed Design Cell (DDC) will prepare tender documents to make sure that future contractors will be prepared and primed to cooperate with the implementing agency, project management, supervising consultants and local population in the mitigation of environmental impacts.

146. The ADB guidelines on ERP8 recommend identification of opportunities to enhance design and avoid environmental pollution by choosing non-polluting or enhancing methods. In order to introduce this process as early as possible in the project the contractor will be required to submit with their tender a Method Statement and schedule of environmental mitigation 35 measures in response to EMP. Contractual clauses will be included in the tender documents to tie the implementation of environmental mitigation measures to a performance milestones. The ESIC cell will check that contractors Method Statements submitted with tenders have made sufficient provisions and include plans and sufficient resources to implement the mitigation measures in the EMP that will be reviewed and updated as necessary at the detailed design stage.

147. In order to comply with best international practice and ADB guidelines all the new equipment will not contain Polychlorinated biphenyl (PCB) or other hazardous or persistent polluting chemicals. Therefore in procurement documents it always shall be specified that transformers, transformer oil and other equipment are to be free from PCB and other petroleum fractions that may be injurious to environment or equipment. Although to date it has not been possible to identify any PCB containing equipment in the sites so far investigated, it is required that a plan will be made by NTDC to gradually phase out any isolated remaining items of existing equipment with transformer oil, breaker oil or other equipment that may contain PCB and this shall be done as soon as practicable.

148. The Detailed design Cell/Consultant (DDC) in cooperation with the ESIC cell will include in the tender documents and draft contracts requirements that will also include but not necessarily limited to the following:

(i) Minimize acquisition of agricultural land for temporary facilities (if needed) by selecting preferred locations in detailed designs for construction yards and asphalt plant on barren or marginal land and agree terms with local community. (ii) Potential solution spaces will be identified in advance by the DDC and approved by NTDC in consultation with the local community to ensure sufficient storage and disposal space for cut surface materials and to avoid fly-tipping. (iii) Include plans in detailed designs and programming that avoid community severance and minimize disturbance of pedestrians and vehicular traffic during construction. Detailed designs will also retain passageways along all footpaths, tracks and access ways near the project during construction. (iv) Designs will require hydrological and drainage impacts during construction to be minimize by early phasing of replacement of culverts and other infrastructure. These plans and designs will be included for in contracts. (v) Extensions and improvements to drainage culverts that fall under embankments of the project will be designed to account for increased runoff from rain due to climate change and included in detailed designs. (vi) Avoid disruption to and retain or re-provision current facilities for irrigation and potable water supply before construction works commence; that provisions are made to preserve the operation of current facilities for irrigation and potable water supply in sufficient quantity in agreement with the local community. (vii) Aim to provide some enhancements in line with ADB policy on environmentally responsible procurement and avoid negative impacts due to unnecessary removing of trees.

5. Planning Waste Disposal

149. Waste management plans (WMP) will be drawn up at the project planning stage of the subproject to ensure that waste disposal measures will be undertaken to reuse and recycle all materials wherever possible minimize the generation of waste. WMPs will be prepared for all

36 subproject packages as part of the environmental management plan to ensure that the waste generated during the construction is disposed in an environment-friendly manner. With the proper implementation of an appropriate waste disposal plan, there will be no residual risk due to improper waste disposal. ADB Guidelines on Environmentally Responsible Procurement 2007 (ERP7) recommend reduction, reuse and recycling of waste.

6. Planning Hazardous Waste Disposal

150. The waste management plan (WMP) drawn up will also cover measures to be undertaken to reuse and recycle all equipment and oil wherever possible and minimize the generation of waste. WMPs shall ensure that any residual oily waste and other contaminated waste generated in the construction and operational phase is disposed in line with provincial EPA and local authority requirements. With the proper implementation of an appropriate waste disposal plan, there will be no residual risk due to improper waste disposal.

151. The selected contractor will prepare a Waste Management Plan that will be dovetailed including the management of oil and other waste materials; with disposal sites identified based on the agreement with the local authorities for agreement by ESIC 1 month prior to the commencement of construction work.

7. Avoiding adverse operational air quality and noise mitigation by design

152. The residential dwellings and other Sensitive Receivers near the Project are generally set back sufficiently so that operational impacts will not be sufficient to affect the sensitive receivers in the settlements. In order to preserve this acceptable situation NTDC must prevent encroachment of settlements into the ROW. Construction impacts including dust and fumes from erosion and earthworks will be controlled through the EMP. Operational air quality monitoring will only be carried out for reassurance purposes at the substations.

153. The accepted World Bank criterion8 of Leq55dB(A) or an increase in 3dB(A) at the sensitive receiver for noise sensitive developments such as residences, schools, colleges and hospitals is unlikely to be exceeded at any sensitive receivers in the villages during the operational phase based on the alignment. Based on the public consultation there also seems to be some local acceptance of the noise impacts that will come with the project. Therefore it is recommended that before mitigation is designed at the detailed design stage the acceptability of noise impacts on the residences and other sensitive receivers should be established with the local stakeholders to ensure no unacceptable nuisances arise.

8. Managing hydrological impacts

154. The proposed Project will cross numerous rivers and rivulets. The tower footings and support pads near the rivers will be designed to be safe during an occurrence of floods within the expected design life of the structures. At the same time, the design of the river crossing structures should be economical and within an acceptable risk limit.

7 ADB. 2007. Environmentally Responsible Procurement - A Reference Guide for Better Practice. Manila. 8 World Bank. 1998. Pollution Prevention and Abatement Handbook. Washington D.C. 37

155. Therefore to minimize and manage hydrologic flow at sites where flooding may occur, appropriate structures will be included in the detailed designs in order to cater for worst case flow and take account of increased rain from climate change during the life of the project. The contractor will also base calculations on available industry standard estimates of such increased flows that are available in the literature at the time (e.g. OECD9). The designs will also provide for redistributing sheet flows from surfaces to reduce erosion and other impacts. Designs will also include adequate major and minor lead off drainage facilities to the nearest water courses, as necessary. In order to minimize and manage hydrologic flow at bridges and culverts during construction a Drainage Plan will also be prepared by the contractor to control construction runoff and prepare to prevent flooding.

9. Planning for Erosion Control

156. The natural environment around the project is prone to erosion in some areas and the construction works will aggravate this situation. Therefore the necessary engineering controls for erosion protection measures need to be planned in advance. An Erosion Control and Temporary Drainage Plan will be compiled in order to avoid any significant or catastrophic erosion or landslide events. The Erosion Control and Temporary Drainage Plan will be agreed with ESIC cell at least 1 month prior to the commencement of construction. This will allow time for the contractor to make necessary provisions to install the soil erosion control and temporary drainage measure in good time. The plan will include all the constructed works and peripheral areas, particularly along access and haul tracks.

10. Planning Construction camps

157. Public consultation has also identified significant concerns about uncontrolled worker camp operations and stockpiling of construction materials.

158. The sites selected for worker camps and back up areas for stockpiling materials and equipment will be planned in advance in consultation with the local community and located to avoid the most productive agriculture and will use waste/barren land and non-agricultural plots as far as possible. Consultation will be undertaken with local authorities and land owners by the detailed design engineers to agree use of such lands before detailed designs are finalized and before construction contracts are signed and the arrangements will be reconfirmed by the construction contractors and notified to NTDC before construction commences.

9 Agrawala S. et al. Development and Climate Change in Nepal – Focus on Climate Change – OECD, Working party on Global Structural Policies - Environment Directorate / Development Co-operation Directorate 2003.

38

11. Temporary Traffic Management

159. There are also concerns about blocking existing roads and many other footpaths and tracks near the route during construction. Therefore a provisional Temporary Pedestrian and Traffic Management plan will be prepared by the contractor that can be updated by the contractors and agreed with ESIC 1 month prior to start of works. Alternative footpaths and access should discussed in advance with the local authorities in the districts and signposted and be re provisioned before the start of construction.

12. Institutional strengthening and capacity building

160. The ESIC cell currently has few staff and there will be a need for more human resources as discussed in the Chapter 5. A substantial amount of training will be undertaken in order to ensure that the Cell officials are trained to understand how to apply the EMP. The training will ensure they have the resources to apply the EMP and have the capacity to evaluate the environmental requirements and contractors’ mitigation measures and also to facilitate capacity building activities. This will work towards the development of a strengthening plan for the environmental management undertaken by ESIC as the Project moves from the detailed design to the construction and maintenance phases. There will be a net increase in staffing in the ESIC cell for monitoring all stages of the Project from pre-construction to commissioning and for the first year of the operation and maintenance. An international environmental specialist should also be engaged to support the ESIC at least for the first 6 months from pre-construction until the monitoring and auditing methodologies are established by the ESIC cell.

13. Preparing the Contractor(s) to Address Mitigation Measures

161. The contractor will be primed by including the EMP and environmental assessments in the bidding and contract documentation. The contractor(s) will be informed that they will be required to produce method statements and plans in advance as required in the EMP for, Temporary Pedestrian and Traffic Management Plan, Drainage Plan, Erosion Control Plan, Waste Management Plan and Noise and Dust Control Plan, and a schedule of costs for implementation of mitigation measures.

162. It has been reported that it has been typical for contractors to put emphasis on the financial compensation for nuisances. This may be acceptable for some social impacts where evacuation is necessary or houses have been accidentally damaged, however it is not best international practice to accept payment for environmental impacts. It has been noted by NTDC that the approach of some contractors has been to pay money for nuisances rather than control impacts at source. If say erosion impacts are not controlled properly there could be serious environmental consequences such as landslides or runoff could cause fish kills in the rivers. Therefore, the practice of paying financial compensation for impacts should not be allowed and financial compensation will not be allowed as mitigation for environmental impacts or environmental nuisance.

163. During the preparation for the construction phase the future contractors must be prepared and primed to co-operate with the executing agency, project management, supervising consultants and local population in the mitigation of impacts. Furthermore the contractor must 39 be primed by including IEE and the EMP in the contract documentation. The contracts must require full implementation of the EMP and the contractor must be ready to engage capable and trained environmental management staff to audit the effectiveness and review mitigation measures as the project proceeds. The effective implementation of the EMP should be audited as part of the loan conditions and the executing agency must be prepared for this. In this regard the NTDC (the EA) will also prepare resources to fulfill the requirements of the law and guidance prepared by EPA on the environmental aspects of projects and any updated recommendations in the EMP as the mitigation measures are rolled out and updated as necessary.

164. The requirements in the contract will include full implementation of all of the environmental mitigation measures in the EMP. (Some of the social requirements in the EMP will be carried out by the proponent NTDC vis a vis land acquisition and resettlement). The agreement with the contractor will include preparing all the above documentation in advance in the pre-construction phase with agreement from NTDC and the method statements and plans will subsequently become part of the contract documentation. The contractor will also be required to engage capable and trained staff or site agents to take responsibility for the environmental management at the working level and to monitor and report on the effectiveness and review mitigation measures as the project proceeds. The effective implementation of the EMP will be audited as part of the loan conditions and the executing agency will be prepared for this. In this regard, the NTDC (the Implementing Agency) will also prepare resources to fulfill the requirements of the law and guide the contractors on the environmental aspects of construction. Recommendations, guidelines and initiatives promulgated by NTDC and EPA will also be incorporated in the revised EMP and updated as necessary.

D. Environmental Impacts and Mitigation Measures During Construction

165. The source of the construction impacts will mainly be from removal of structures and vegetation, construction of access, minor earthworks to construct the towers and bases courses, re provisioning and repairing nearby pedestrian tracks.

1. Orientation for Contractor

166. Prior to the commencement of construction the contractor, all subcontractors and all his workers will need to be trained on the requirements for environmental management. In order to ensure that the contractor, subcontractors and workers understand and have the capacity to implement the environmental requirements and mitigation measures there will be regular and frequent training sessions and tool-box talks. Contractors tenders will be required to identify separately the resources and funds to be applied to the training and mitigation measures and contractors tenders shall identify named staff to supervise and responsible for mitigation measures for all works including but not limited to earthworks, drainage re-provisioning, erosion control, traffic management, materials management, noise and dust control, waste management. Engineering controls will be designed by contractor as mitigation measures and approved by the ESIC (supervising authority) prior to the commencement of the construction works. No construction works will commence until all mitigation measures are in place and approved by the supervising authority.

40

2. Advance planning of environmental mitigation measures

167. Removal of isolated trees: A significant proportion of the Project will run through agricultural land. There are numerous isolated trees on farms and homesteads that will need to be cut and will be compensated for under the provisions of the entitlement matrix in the LARP (Appendix 6). Surveys made all along the alignment indicate trees are present very near the project in many places but there should not be any need for further disturbance of trees in the works once the ROW has been cleared.

168. By the time construction commences the contractor will have been primed by including the revised EMP and environmental assessments in the bidding and contract documentation. The contractor will be required to produce method statements and plans in advance of commencement of construction as required in the EMP for:

(i) Drainage Management Plan (ii) Temporary Pedestrian and Traffic Management Plan. (iii) Erosion Control and Temporary Drainage Plan (iv) Waste Management Plan, (v) Noise and Dust Control Plan (vi) Safety Plan (vii) Material Management Plan

169. All the above plans will be submitted one month in advance of any construction activities to ESIC cell to check and agree and verify requirements from EPA have been complied with. A schedule of costs for environmental mitigation measures (including maintenance where applicable) should be agreed with the contractor before the construction commences. The implementation of mitigation measures shall be tied to payment milestones or a performance bond for an amount agreed with the contractor and NTDC shall be deposited by the contractor. The bond shall be forfeit in the event that environmental mitigation measures required in the EMP are not fully implemented.

3. Hydrological, drainage and irrigation impacts

170. The Project will be designed not to interfere with the drainage on adjacent lands and paths and to prevent soil erosion and retain the existing irrigation system in the operational phase. However in the construction stages there is the potential for the works to have impact on local water resources. There are numerous rivers, streams, irrigation and drainage channels that cross or are affected by the project. The plans to avoid and retain such drainage and irrigation works shall be included in the Drainage Management Plan and the contractors will include plans for any necessary temporary drains to cater for worst case flow. The designs will also provide for protection of the works that are in progress and for redistributing flash flows from prepared surfaces during heavy rain to reduce erosion and other impacts. The contractor(s) will be required to have a drainage engineer / erosion control officer to check implementation of the temporary drainage mitigation on site and make modifications on a daily basis as necessary.

41

171. To protect the drainage and irrigation system on surrounding land that may be affected by construction activities and contractors will incorporate the following design features to minimize alterations in the surface drainage near the project:

(i) Contractors will review the irrigation systems and irrigation structures potentially affected by construction of the Project. If the irrigation cannot be maintained they will provide and maintain alternative temporary irrigation structures for the construction phase. At the completion of construction the contractor(s) will re provision the irrigation structures disturbed by construction and agree with ESIC cell if redesign is required or if new structures will be constructed or if the original irrigation structures will be repaired. (ii) Re provisioned irrigation channels will capable to supply all the fields previously supplied with at least the volume of water supplied before the construction of the

4. Soil erosion and surface runoff

172. In the construction stages there is the potential for the works to have impact on local water resources. The works are quite close to some major streams and rivers in some places and there are several crossings of significant tributaries. There are potentially major impacts from all the works near the rivers and streams. The drainage designs for the Project should be cleared with the local drainage and irrigation authorities before works commence.

173. It is recommended that sedimentation facilities be set up at rivers where all working stations are within 100m of streams and rivers, to trap and settle out runoff from the works. Where wet works have to be pumped dry the waste water should first be passed through a proprietary sedimentation tank (or similar) to remove suspended particles before discharge at a location agreed with the ESIC cell. The contractor shall be required to have a dedicated drainage engineer and erosion control officer. Where works cross streams and rivers the preliminary designs for sedimentation facilities such as sediment traps, filter fabric fences, or straw bale barriers should be included as a line item before those new areas are cleared and opened up for construction works.

174. Professional experience suggests that it will be typical for contractors to claim that there is insufficient space to set up erosion control and sedimentation facilities along the working areas. Based upon observation it is not credible that there is no space and it is not acceptable that there are no opportunities to use at least some form of sediment basins sediment traps. It is recommended that preliminary designs for sedimentation facilities are included in the contracts and subsequently in the Erosion Control and Temporary Drainage plans. Combinations of alternative methods should be considered including but not necessarily limited to:

(i) schedule work so clearing and grading are done during the time of minimum rainfall. (ii) clear only areas essential for construction. (iii) locate potential area pollutant sources away from steep slopes, water bodies, and other critical areas. (iv) route construction traffic to avoid existing works or newly planted vegetation. (v) protect natural vegetation with fencing, tree armoring, and retaining walls or tree wells. (vi) stockpile topsoil and reapply to re-vegetate the site. (vii) cover and stabilize topsoil stockpiles. (viii) use wind erosion controls.

42

(ix) intercept runoff above disturbed slopes. Convey to permanent channel or storm drain. (x) on long or steep, disturbed, or man-made slopes, construct benches, terraces, or ditches at regular intervals to intercept runoff. (xi) use retaining walls. (xii) use check dams. (xiii) Install bioengineering in line with NTDC manuals and seed and fertilize. (xiv) use seeding and mulch/mats. (xv) use turfing. (xvi) use wildflower cover.

175. Stockpiles should be covered before heavy rain to prevent wash out due to runoff. Stockpiles should not be located within 20m of water courses and there should be an intervening vegetated buffer to control any un-expected run-off. As a long-term benefit of the project, the drainage infrastructure may be able to be modified as water harvesting structures to collect water for irrigation and other uses and such options should be discussed and investigated at the detailed design stage.

5. Water Quality Impacts

176. Water is a critical resource for the local community and resources will be protected during construction. Where works are in progress, erosion control and sedimentation facilities including sediment traps and straw bale barriers or combinations thereof will remain in place and be maintained throughout the works to protect local water resources. Lubricants, fuels and other hydrocarbons will be stored >100m away from water bodies. Solid wastes will be disposed of properly (not dumped in streams). Construction material and spoil stockpiles will be covered to reduce material loss and run-off and stockpiles will not be nearer than 100m to water bodies. Borrow sites will not be close to sources of drinking water in case of runoff.

177. If complaints are received, the incidents and possible sources of water supply disruption will be investigated by the contractor and the ESIC cell and where the complaint can be substantiated; water samples will be taken and analyzed based on the baseline monitoring results obtained in the preconstruction stage. Samples will be taken as soon after the complaint as possible and analyses immediately and again two weeks after the complaint to determine if water quality has been restored. The criteria will be based on the national standard.

6. Water Resources Impacts

178. It is assumed that ample water will be available and local water resources could be used as sufficient yield is generally available. However the drainage system and water resources on surrounding land will be affected by construction activities as follows: a) local water supplies will need to be tapped to meet campsite and construction requirements, so bringing project based water use into competition with local use; b) surface and subsurface water resources in the selected sections could be contaminated by fuel and chemical spills, or by solid waste and effluents generated by the kitchens and toilets at construction campsites; c) natural streams and irrigation channels may become silted by borrow material (earth) in the runoff from the construction area, workshops and equipment washing-yards.

179. Measures to mitigate the adverse impact on water resources and surface drainage patterns have been incorporated into the other drainage mitigation measures. The contractors 43 will also carry out the following measures to mitigate the impact of tapping local community water resources, where required:

180. Availability of water will be assessed to evaluate the impact on community resources. Project water will be obtained without depleting local village supplies.

181. Camps will be located at least 100m away from the nearest local settlement to prevent the contamination of community-owned water resources.

182. The contractors will be required to maintain close liaison with local communities to ensure that any potential conflicts related to common resource utilization for project purposes are resolved quickly.

183. Guidelines will be established to minimize the wastage of water during construction operations and at campsites.

184. Availability of water will be assessed to evaluate the impact on community resources. Project water will be obtained without depleting local village supplies.

185. Camps will be located at least 100m away from the nearest local settlement to prevent the contamination of community-owned water resources.

186. The contractors will be required to maintain close liaison with local communities to ensure that any potential conflicts related to common resource utilization for project purposes are resolved quickly.

187. Guidelines will be established to minimize the wastage of water during construction operations and at campsites.

188. The water ways and drainage streams en-route of the subproject project should not be impeded by the works and the scale of the works does not warrant hydrological monitoring. Refer to attachment 7 for likely impacts upon waterways and ponds (51 line spans cross water courses or canals). The line crosses the waterways (canals and watercourses) at different places. This crossing, however, is between two power pylons and in itself has no impact upon the water way, even during construction the tower foundations are located away form the waterway. Line stringing is by means of tension stringing equipment which has no impact on the waterways.

189. During construction, machinery and transport will be used by the contractor, both have potential of causing contamination to under ground and above ground water assets .There is need to compile temporary drainage management plan one month before commencement of works. Proper installation of temporary drainage and erosion control before works within 50m of water bodies should be done. Proper construction of temporary drainage and erosion control measures, maintenance and management including training of operators and other workers to avoid pollution of water bodies by the considerate operation of construction machinery and equipment. Storage of lubricants, fuels and other hydrocarbons in self-contained dedicated enclosures should be >50m away from water bodies. Proper disposal of solid waste from construction activities and labor camps. Cover the construction material and spoil stockpiles with a suitable material to reduce material loss and sedimentation and avoid stockpiling near to water bodies. Topsoil stripped material shall not be stored where natural drainage will be disrupted. Borrow sites (if required) should not be close to sources of drinking water.

44

190. Wetland: There is no wet land in the vicinity of the sub project except for a small check dam ( Dam for collection of water during rains) which is in the vicinity of the line route, the line , however, does not traverse over the small check dam . There is need to protect this one water resource from possible fuel and oily spills form construction machinery and transport used during the construction phase of the subproject. The measures that need to be employed include: .Avoid disposal of wash water, solid waste and discarded packing etc. on wetlands; Piling up of loose material should be done in segregated areas to arrest washing out of soil. In addition, these materials should not be tipped or stockpiled near wetlands. Leftovers from concrete works should not be dumped close to wetlands. Avoid temporary structures or stockpiling within banks of river and on wetlands. Special measures will be adopted to minimize impacts on the wild birds, such as avoiding construction activities during the critical periods of breeding and feeding. Staff working on the project should be given clear orders, not to shoot, snare or trap any bird. Contractor will prevent the workers from hunting and fishing for water birds and fish resources, etc. Food and fuel to be provided by contractor local villages. Erection of towers in the wetlands will be avoided as far as possible. However, at places where realignment of the transmission is unavoidable, towers with maximum span will be used to minimize the impacts.

7. Waste Management and Spoil Disposal

191. There may be some surplus rock and soil based materials. The waste management plan (WMP) will be required to ensure waste from construction is managed properly and to reduce, reuse and recycle waste wherever possible. Contractors will initially review the detailed design consultant’s options for stockpiling and disposal locations for cut surface materials and reconfirm or propose alternative disposal locations for agreement with NTDC and local authorities. The contractor will prepare the WMP one month before the commencement of construction with disposal sites identified for agreement by project supervision consultants (CSC/ESIC/NTDC). The WMP will cover all aspects of construction waste disposal. It is preferred that government land is used for dumping of material. If private land is to be used for the purpose of dumping it shall commence only after written permission from the land owner is checked by the ESIC in NTDC.

192. The mitigation measures in the waste management plan (WMP) will include but not necessarily be limited to:

(i) Spoil will not be disposed of in rivers and streams or other natural drainage path. (ii) Spoil will not be disposed of on fragile slopes, flood ways, wetland, farmland, forest, religious or other culturally sensitive areas or areas where a livelihood is derived. (iii) Use surplus spoil for local repair works to fill eroded gullies and depression areas and degraded land in consultation with local community. (iv) Dispose of spoil will be to disused quarries and abandoned borrow pits. (v) Disposed spoil will be spread in 15cm and compacted to optimum moisture content , covered with topsoil, landscaped and provided with drainage and vegetation to prevent erosion following NTDC/GESU guidelines10. 8. Noise

10 Guide to Slope Protection Works–. NTDC GOP 2007. 45

193. Powered mechanical equipment such as generators, excavators, piling rigs, stabilizers and concrete-mixing plant can generate significant noise and vibration. Whereas various modern machines are acoustically designed to generate low noise levels there is not much evidence that acoustically insulated plant is available in Pakistan. The cumulative effects from several machines can be significant and may cause significant nuisances.

194. To minimize impacts the contractors should be required by the Cell to (i) maintain and service all equipment to minimize noise levels, and (ii) locate equipment to minimize nuisances and (iv) install acoustic insulation or use portable noise barriers where practicable to limit noise at sensitive receivers. Insulation should be provided to minimize noise impacts such that the measured noise at the edge of the works nearest residential areas will be less than 50dB(A)Leq during nighttime (9 p.m. to 6 a.m.) and 75 dB(A) Leq at other times during the day.

195. There are a few schools near the project. The occasional commercial premises and some residences are also set back from the likely working areas. Where schools are nearby, the contractor shall discuss with the ESIC cell and the school principals the agreed time for operating these machines and completely avoid machine use near schools during examination times. Where noise is a major consideration (say outside places of religious worship) construction should be avoided at sensitive times. As a fall back option to control noise, portable barriers can be introduced creased using heavy thick ply-board or corrugated metal sheet. In addition to the physical effect of mitigating dust and noise the installation of such measures should be discussed with the local population and serve as a means for further public consultation during implementation and assist in public relations.

9. Air Quality and Dust Control

a. Dust control

196. The location of the residences, places of worship, schools, hospitals and civic cultural and other heritage sites has been reviewed above. Some of the residences in the settlements are close enough to be disturbed by dust. Water is available in the study area although surplus water may not always be available to suppress dust at many locations in the dry season. Therefore as a general approach it is recommended that if works are within 15m of any sensitive receivers, the contractor should install segregation between the works at the edge and the sensitive receivers. The segregation should be easily erectable 2.5m high tarpaulin sheet and designed to retain dust and provide a temporary visual barrier to the works. Where dust is the major consideration the barrier can take the form of tarpaulins strung between two poles mounted on a concrete base. These can be moved along the as the work proceeds.

197. Noise and dust were recognized by the local population as concerns but were considered to be acceptable nuisances and that there were benefits from future improved travel conditions. However in the dry season, when most of the construction will be carried out noise and dust will be significant concerns for the general public in consultation. Therefore in line with good practice mitigation measures are proposed to control all dusty materials at source. Also works will not take place at night.

(i) If the working surfaces become dry and dusty, water will be sprinkled on the and exposed surfaces when work is carried out within 50m of the side Sensitive Receivers.

46

(ii) No work will be carried out during the night (2100hrs to 0700hrs). (iii) If works give rise to complaints over dust, the contractor shall investigate the cause and review and propose alternative mitigation measures before works recommence. (iv) All heavy equipment and machinery will be fitted in full compliance with the national and local regulations. (v) Fuel-efficient and well-maintained haulage trucks will be employed to minimize exhaust emissions. Smoke belching vehicles and equipment will not be allowed and will be removed from the project. (vi) Vehicles transporting soil, sand and other construction materials will be covered with tarpaulin sheets to avoid impact from dust. Speeds limits will be established for vehicles within the works sites and on unpaved edge areas of the project .

b. Soil Contamination

198. Possible contamination of soil may occur from oils and chemicals at workshop areas, and equipment washing-yards. The contamination may limit the future use of land for agricultural purposes.

199. The following practices will be adopted to minimize the risk of soil contamination:

(i) The contractors will be required to instruct and train their workforce in the storage and handling of materials and chemicals that can potentially cause soil contamination. (ii) If waste oils or other contaminants are accidentally spilled on open ground the waste including the top 2cm of any contaminated soil shall be disposed of as chemical waste to a disposal site acceptable to the NTDC and agreed with the local authority / community. Debris generated by the dismantling of existing structures will be recycled subject to the suitability of the material in line with the MMP.

200. Solid waste generated during construction and at worker campsites will be properly treated and safely disposed of only in demarcated waste disposal sites identified and agreed with DOW and the local community.

201. Control measures for oily residues, lubricants and refueling are prescribed in the EMP. The maintenance yards that will be created will have dedicated drainage which can capture run- off. Oily residues and fuel should be captured at source and refueling and maintenance should take place in dedicated areas away from surface water resources. With these measures in place no significant impacts should be arise in construction.

10. Worker camps, maintenance yards and canteens operation

202. Uncontrolled worker camp operations can cause significant impacts. The sites for worker camps will be planned in advance in consultation with the local community.

203. In consultation the public have expressed concerns about nuisances from construction camps. The main issues of concern are uncontrolled defecation by construction workers, unmanaged disposal of solid and liquid wastes into watercourses, natural drains and improper disposal of storm water and black water in the village areas. The contractors will therefore adopt 47 good management practices to ensure that fuels and chemicals, raw sewage, wastewater effluent, and construction debris/scarified material is disposed of under controlled conditions to reduce the risk of contamination.

204. Prior to the close out of the Project construction in any area the worker camps will be removed and restored to the original condition as far as is reasonably practicable to the satisfaction of the and the local authority.

205. Before construction commences arrangements will be reconfirmed by the construction contractors and notified to ESIC Cell / NTDC for approval as follows:

(i) Confirm location of work camps in consultation with ESIC and local authorities with location subject to approval by the ESIC. If possible, camps shall not be located near settlements or near drinking water supply intakes. (ii) Cutting of trees shall be avoided and removal of vegetation shall be minimized. (iii) Water and sanitary facilities shall be provided for workers and employees. (iv) Construction camps will be established in areas with adequate natural drainage channels in order to facilitate flow of the treated effluents. (v) Portable lavatories or at least pit latrines will be installed and open defecation shall be discouraged and prevented by keeping lavatory facilities clean at all times. (vi) Wastewater effluent from contractors’ workshops and equipment washing-yards will be passed through gravel/sand beds to remove oil/grease contaminants before discharging it into natural streams. Oil and grease residues shall be stored in drums awaiting disposal in line with the agreed Waste Management Plan. (vii) Predictable wastewater effluent discharges from construction works shall have the necessary permits from EPA before the works commence. (viii) Solid waste and sewage shall be managed according to the national and local regulations. As a rule, solid waste must not be dumped, buried or burned at or near the project site, but shall be disposed of to the nearest site approved by the local authority. (ix) The Contractor shall organize and maintain a waste separation, collection and transport system. (x) The Contractor shall document that all liquid and solid hazardous and non- hazardous waste are separated, collected and disposed of according to the given requirements and regulations. (xi) At the conclusion of the project, all debris and waste shall be removed. All temporary structures, including office buildings, shelters and toilets shall be removed by the contractor and exposed areas shall be planted with suitable vegetation, to the satisfaction of the and the local authority (xii) The ESIC Cell shall inspect and report that the camp has been vacated and restored to pre-project conditions as far as is reasonably practicable.

11. Safety of the Workforce

206. In order to maintain proper sanitation around construction sites, temporary toilets will need to be provided. Construction worker camps will not be located in settlement areas or near sensitive water resources.

207. The comfort and health of the workforce and surrounding local residents may be affected to some extent from emissions of dust, noise and construction litter. The chances of serious

48 injury or accident during the construction activities are moderate and can be mitigated by safety training and monitoring. Insufficient toilet provisions may give encouragement to defecation in the open and may increase transfer of water or air borne diseases. Local labor will be used wherever possible and where worker camps are needed they will include proper sanitation facilities (at lease pit latrines and showering facilities).

208. Existing health services in the localities near the project such as health posts and clinics have limited resources and may lack sufficient medicines and health personnel to accommodate any additional patients from the construction workforce. Therefore in the construction stages the contractor shall provide first aid facilities for the workers on the and at the worker camps with at least one qualified first-aider.

12. Social Facilities and Health

209. Existing health services in the localities near the project such as health posts and clinics have limited resources and may lack sufficient medicines and health personnel to accommodate any additional patients from the construction workforce. Therefore in the construction stages the contractor shall provide first aid facilities for the workers on the and at the worker camps with at least one qualified first-aider or nurse present at all times. It is recommended that the workforce be given access to a trained doctor at least once per week for routine checks and medical examinations if necessary.

13. Enhancements or Changes in Scope

210. Opportunities for enhancements (or changes in scope) can be assessed prior to construction and proposed enhancements will be discussed with the local population to identify stewardship of any planting and also to serve as a vehicle for further public consultation at the implementation stage and to assist in public relations.

211. Where rock based materials, gravels and sands are extracted it is a requirement to rehabilitate the re-vegetation of these areas with indigenous species and this has been a concern of local people in the public consultation. Following the completion of the landscaping will take place and overall the appearance will be improved.

E. Environmental Impacts and Mitigation Measures During Operation

212. The alignment seeks to provide a buffer distance from the corridor, keeping vehicles away from sensitive receivers in the operational phase as far as possible. It is difficult with a project of this magnitude to achieve an alignment that make sure all residences or commercial premises or schools will far enough away from the project not to be affected in any way by traffic emissions Therefore air quality will be monitored in the operational phase to provide reassurance of the sustainability of the subproject. NTDC/the Government will also prevent encroachment and enforce the exclusion zone and preserve the buffer distances to residences within the substation.

213. No alignment could avoid crossing some rivers and streams and protection of water resources must also be monitored in the operational phase to reassure the public that the project does not make any long term impact on the water quality. Therefore chemical water quality and the status of the river invertebrate communities will also be monitored in the 49 operational phase as an indicator of the sustainability of the rivers’ ecology and to provide reassurance that the impacts were mitigated acceptably.

214. The alignment must also inevitably cross plantations or forests and the success of compensatory planting must also be monitored in the operational phase to reassure relevant authorities that the project impacts have been successfully mitigated and that the long term impacts on plantations or forests are acceptable.

1. Air Quality

215. It is not likely that the Projects will give rise to any significant accumulations of air emissions in the operational stage.

216. Air quality monitoring for of nitrogen dioxide and PM10 as a key indicator pollutants should be carried out after the opening and at yearly intervals for 3 years prove the acceptability of the project in air quality terms.

2. Success of compensatory planting

217. To ensure the success of enhancement planting and survival of the planted trees it is recommended that an audit of the enhancements and other trees and shrubs under the Project transmission line be undertaken by the NSIC after the initial cutting and planting has been commenced to review conditions and maintain the planted trees

3. Encroachment and community awareness

218. The transmission line alignment will not displace any household. Resettlement and compensation will be dealt with before construction starts. However experience suggests that there will be additional encroachment. In addition some families may seek to resettle within the ROW. During the design phase and subsequently in the course of construction and operation awareness campaigning with the local public will be included in the project and the ESIC will try to foster public stewardship of the Project to prevent the encroachment. Any areas where local encroachment into the ROW or immediately adjacent to the ROW has taken place will be identified and reported to the ESIC. Based on the proposed alignments these should not be difficult tasks and this can be conducted as to minimize adverse impacts and maximize benefits.

219. The Social Impact Assessment (SIA) study and LARP have been completed in tandem with this EIA for the whole of the project.

4. Effects of frequency

220. Transmission frequency used is 50 Hz , which is considered extremely low frequency, impacts of this reduce rapidly with distance and there are no residential or other buildings that are located at a distance that could be impacted by electric and magnetic fields, See IFC guideline ‘Environmental, Health, and Safety Guidelines- Electric Power Transmission and Distribution’, April, 30, 2007.

50

V. INSTITUTIONAL REQUIREMENTS & ENVIRONMENTAL MANAGEMENT PLAN

221.. The EMP is based on the type, extent and duration of the identified environmental impacts, this includes disaster management. The EMP has been prepared by reference to and following the best practices (these include EPA stipulations/guidelines and where EPA is silent International guidelines and the ADB Environmental Assessment Guidelines (footnote 2) (see paragraph 21 and Annexure 2 for various standards).

222.. It is important that the recommendations and mitigation measures are carried out according to the spirit of the environmental assessment process and in line with the guidelines. NTDC tender/contract documents do include a clause (Annexure ‘C’ of the tender document) which requires the contractor to adhere to the EMP. In this section, the mitigation measures that are required, for the power transmission enhancements, to reduce residual impact to acceptable levels and achieve the expected outcomes of the project are discussed. The EMP matrix is presented as Appendix 2. The impact prediction (Section IV) has played a vital role in reconfirming typical mitigation measures and in identifying some different approaches based on the feasibility and detailed design assumptions and any alternatives available at this stage.

223.. Prior to the implementation and construction of the TXL, the EMP shall be amended and reviewed by the NTDC after detailed designs are complete. Such a review shall be based on reconfirmation and additional information on the assumptions made at the feasibility stage on alignment, location scale and expected operating conditions of the Project. For example, if there are any additional TXLs or extension of the substation boundaries to be included, the designs may be amended and then the performance and evaluation schedules to be implemented during project construction and operation can be updated, and costs estimates can be revised. Major changes in scope of work will necessitate a fresh environmental assessment and approval of the new IEE by ADB.

224.. The EMP must be reviewed by the project management and approved by the PEPA before any construction activity is initiated. This is also an ADB requirement in order to take account of any subsequent changes and fine tuning of the proposals. It is recommended that before the works contract is worked out in detail and before pre-qualification, a full extent of the environmental requirements of the Project (IEE/EIA) are included in the bidding documents including the EMP. Past environmental performance of contractors and awareness of environmentally responsible procurement should also be used as indicators for prequalification of contractors.

225. In order to facilitate the implementation of the EMP, during the preparation for the construction phase, the future contractors must be prepared to cooperate with the local population in the mitigation of impacts. Furthermore, the contractor must be primed through the contract documentation and ready to implement all the mitigation measures and engage trained environmental management staff to audit the effectiveness and review mitigation measures as the project proceeds. The effective implementation of the EMP will be audited as part of the mid term review of loan conditions and the executing agency must be prepared for this. Six monthly monitoring reports have to be submitted to ADB on the effectiveness of the EMP implementation

226. The details of the EMP is given in Appendix 2 in the form of the matrix. The impacts have been classified into those relevant to the design/preparation stage, construction stage and operation and maintenance stage. The matrix provides details of the mitigation measures recommended for each of the identified impacts, approximate location of the mitigation sites, time span of the implementation of mitigation measures, an analysis of the associated costs and 51 the responsibility of the institution. The institutional responsibility has been specified for the purpose of the implementation and the supervision. The matrix is supplemented with a monitoring plan (Appendix 3) for the performance indicators. An estimation of the associated costs for the monitoring is given with the plan including physical mitigation costs. The EMP has been prepared following the best practices and the ADB environmental assessment guidelines.

227. Prior to implementation of the Project, NTDC needs to comply with several environmental requirements, such as obtaining PEPA clearance (“No Objection Certificate”, compiling acceptable EMP and Clearance Certificate) under PEPAct (guidelines and regulations, 2000), securing tree removal and replanting permits from the Department of Forests and any permissions required from the Irrigation Department and Department of Wildlife Services. NTDC will also need to confirm that contractors and their suppliers have complied with all statutory requirements and have appropriate and valid licenses and permits for all powered mechanical equipment, permissions for use of local water supplies in line with the all environmental requirements (e.g. and local authority conditions).

228. The EMP (Appendix 2) was prepared taking into account the lack of capacity of the NTDC to conduct environmental assessments of the Subproject and it is envisaged and strongly recommended that for the Subproject, NTDC engage an environmental specialist with at least 10 years experience in environmental management, 5 years site experience in environmental monitoring and auditing to guide the subsequent formal assessment and submission process under the PEPAct and monitor compliance with the EMP. As of January 2007, NTDC has created environmental and social impact cell (ESIC) under General Manager, GSC (this is now being changed as the ESIC is now being placed under the General |Manager (Projects) . Attachment 3 presents the changed structure of NTDC’s implementation formations . . Currently, there are two environmental staff members (one Deputy Manager and one Assistant manager). At this stage, staff members and the consultants are responsible for addressing environmental concerns for the MFF potentially involving hundreds kilometers of power transmission lines and Grid Substation in later tranches. Most of the environmental work is delegated to consultants. Whereas there is a limited level of awareness, NTDC staff needs more training and resources if they are to effectively provide quality control and oversight for the EMP implementation. Specific areas for immediate attention are in EMP auditing, environmentally responsible procurement, air, water and noise pollution management and ecological impact mitigation. It is recommended that an environmental specialist consultant with 10 years experience covers this aspect full time for at least the first 6 months of the MFF project and that on a call off basis with local support, those services are retained for the life of the MFF loan. Attachment 3 2 presents the institutional structure of NTDC where social and environmental assessment and implementation of plans is concerned

229. For this Subproject and the whole MFF, the environmental staff for the project implementation team has been appointed prior to the outset of the implementation design stage to ensure compliance with the statutory obligations under the PEPAct. It is also mentioned that the NTDC will process some in house capability such as Environmental and Social Cell and as soon as possible, potentially suitable staff are nominated to be trained and man the unit at least on an inaugural basis. Due to the lack of in-house capability, at this point, environmental specialist consultants for the project implementation cell must address all environmental aspects in the detailed design. It is recommended that the project management unit (PMU) will have one technical manager (senior environmental specialist) to address all environmental aspects in the detailed design and contracting stages. In addition, there will be an environmental specialist(s) to cover the implementation of environmental mitigation measures in the project packages. Both shall be members of the supervising consultant’s team.

52

The environmental specialists will: a. work in the PMU with NTDC to ensure all statutory environmental submissions under PEPAct and other environmentally related legislation are thoroughly implemented;

b. work in the PMU with NTDC to ensure all environmental requirements and mitigation measures from the environmental assessment of Subprojects are included in the contract prequalification and bidding documents;

c. work with NTDC to execute any additional IEE and IEE requirements needed to the fine tuning of the Subprojects and that environmental performance targets are included in the contracts prior to project commencement;

d. work in the PMU with NTDC to ensure all environmental requirements and mitigation measures from the IEEs and IEEs and environmental performance criteria are incorporated in the Subproject contracts or variations and that the EMP is effectively implemented;

e. work with management consultant, supervising consultant and contractors to manage and monitor the implementation of the project EMP.

f. Overall implementation of the EMP will become NTDC’s responsibility. Other parties to be involved in implementing the EMP are as follows: 230. Contractors: responsible for implementing all measures required to mitigate environmental impacts during construction;

231. Government agencies: such as provincial environmental agencies, and bureaus, at the local level, will be responsible for monitoring the compliance with implementation of environmental conditions related to statutory approvals of Subprojects in their areas.

232. NTDC Board of Directors: responsible to ensure that sufficient timely resources are allocated to process the environmental assessments and to monitor implementation of all construction and operational mitigation measures required to mitigate environmental impacts.

233. Considering that other government agencies that need to be involved in implementing the EMP, training workshops should be conducted at every 6 months or twice each year, for the first 2 years (and annually thereafter) to share the monitoring report on the implementation of the EMP, to share lessons learned in the implementation and to decide on remedial actions, if unexpected environmental impacts occur.

234. The monitoring plan (Appendix 3) was designed based on the project cycle. During the preconstruction period, the monitoring activities will focus on (i) conducting baseline monitoring; (ii) checking the contractor’s bidding documents, particularly to ensure that all necessary environmental requirements have been included; and (iii) checking that the contract documents’ references to environmental mitigation measures requirements have been incorporated as part of contractor’s assignment and making sure that any advance works (protection of specimens and transplantation, design of TXL or Grid Substation, etc.) are carried out in good time. Where detailed design is required (e.g. for power transmission lines and avoidance of other resources), the inclusion and checking of designs must be carried out. During the construction period, the monitoring activities will focus on ensuring that environmental mitigation measures are 53 implemented, and some performance indicators will be monitored to record the Project’s environmental performance and to guide any remedial action to address unexpected impacts. Monitoring activities during project operation will focus on recording environmental performance and proposing remedial actions to address unexpected impacts. The potential to use local community groups' contacts for monitoring should be explored as part of the activities in setting up the Environmental and Social Cell which should have regular meetings with the nongovernmental organizations as a matter of good practice and to discuss matters of mutual concern.

235. At this stage, due to the modest scale of the TXL and by generally keeping to non- sensitive and non-critical areas, the construction and operational impacts will be manageable and no insurmountable impacts are predicted providing that the EMP is implemented to its full extent and required in the contract documents. However, experience suggests that some contractors may not be familiar with this approach or may be reluctant to carry out some measures. In order that the contractors are fully aware of the implications of the EMP and to ensure compliance, it is recommended that the cost of environmental measures be treated separately in the tender documentation and that payment milestones are linked to environmental performance, vis-a-vis the carrying out of the EMP.

236. The effective implementation of the EMP will be audited as part of the loan conditions and the executing agency must be prepared for this. In this regard, the NTDC must be prepared to guide the design engineers and contractors on the environmental aspects.

237. The NTDC procedures for handling Polychlorinated biphenyls (PCB) need to be strengthened and the maintenance of transformers need to be based on the manufacturer's instructions. There needs to be a performance evaluation procedure prescribed and followed for each power transformer. In working areas where PCBs are handled, it is necessary to monitor the levels of chlorinated solvents. In case of emergencies, the first step is to attempt to control the spread of the liquid, this is especially relevant during transportation. In case of spills, emergency measures need to be taken by specially trained personnel and wearing protective clothes. An oil absorptive material is a useful tool and needs to be spread over the spill. All equipment and surfaces exposed to the spill need to be washed with solvent. The best international procedures and guidelines need be followed, one such guideline is the UNEP ‘PCB Transformers and Capacitors – From Management to Reclassification and Disposal, May 2002’. NTDC, however, prohibits supply of any PCB based equipment. This Subproject is related to TXL construction where PCBs are not relevant anyway. Even new substations do not have any PCB based equipment. 238. NTDC already prohibits use of PCBs in new power transformers, there is, however, need to prepare an inventory of any PCB carrying equipment in the system and all such equipment be replaced. The maintenance instructions prepared by the Technical Services Group needs to be reviewed and revised to add PCB based equipment maintenance and a procedure for handling any PCB spills. The Kot Lakhpat workshop already follows. Such procedures, however, these need to be reviewed and upgraded in light of best International practice. This would include provision of special clothing, availability of oil absorptive solvents, and availability of steel containers. Training to staff on oil spills and special care during transportation of equipment using PCBs.

54

VI. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

A. Approach to Public Consultation 239. The public consultation process with various stakeholders has been approached so as to involve public and other stakeholders from the earliest stages. Public consultation has taken place during the planning and design and viewpoints of the stakeholders have been taken into account and their concerns and suggestions for possible improvements have been included where appropriate. Much of the public consultation process to date has revolved around concerns for the mitigation of construction impacts and the possible side effects from the proximity of high voltage power lines. Figure 4 presents public consultation.

Figure 4: Public consultation

240. There is also ongoing consultation for land acquisition and resettlement (LARP) and the completion of the Resettlement Plan is documented separately. It is expected that this process will continue through all stages of the Subproject in order to accommodate stakeholders' aspirations and to orient the stakeholders positively towards the project implementation and where possible to harness cooperation over access issues in order to facilitate timely completion.

241. The public consultation process has commenced in the initial feasibility stages (prior to construction) in order to disclose the project information to the stakeholders and record feedback regarding the proposed project and preferences. The stakeholders involved in the process were the population likely to be impacted along the route of the proposed power lines; the village leaders, schoolteachers, district administration. 55

B. Public Consultation Process

242. Prior to the implementation of the consultation, feedback, etc. has been carried out to support this IEE and recorded. The focus of attention has been the population near the proposed TXL that may be affected by the Subproject expansion. The level of engagement varied from the stakeholder to stakeholder with some registering no major comment but it is noted that none registered any outright opposition to Subproject.

243. The disclosure of the Program in advance and subsequent consultation with stakeholders has advantages in the environmental assessment and mitigation of impacts. Public consultation can also provide a conduit for the improvement of the project implementation to better serve the stakeholders.

244. The environmental assessment process under the PEPAct only requires the disclosure to the public after the relevant EPA to be in strict adherence to the rules has accepted the statutory IEE/EIA. In this IEE, the consultation process was performed to satisfy the ADB requirements. The locations of consultation and people consulted are listed in the full table of public consultation presented in Appendix 4.

C. Results of Public Consultation

245. The consultations identified some potential environmental and social impacts and perceptions of the affected communities. The public consultation resulted to 240 responses in May 2008 –Preliminary field survey was carried out during the period 18 th. To 21 st. March 2008 and detailed survey was carried out during the period 15 th. To 22 nd. March 2008(Appendix 4). Separate consultation meetings were held with men and women groups, land owners, tenants and general community at villages. The groups unanimously showed their willingness to let NTDC establish the proposed 220 kV TXL on the selected route and to provide their land on compensation of damages to crops and trees for it, preferably against a negotiated market price. But they said they are not willing to let compensation to be estimated through the district revenue department, which always under values the compensation and there are reportedly several outstanding grievances and prolonged court litigation cases in the district. The community supports the expansion and upgrading of the power line. The landowners insisted for negotiation on compensation of crops and trees and asked for fair and handsome compensation on market rate. The inhabitants near the TXL expect more stable power supply in the region, with lesser complaints of load shedding, with the provision of a higher voltage connection. Community requested for electrification of affected villages. Poor people requested for unskilled and semi skilled jobs on priority basis with the contractors during implementation of the Project. No land acquisition and resettlement is involved in this Project.

246. On the basis of the consultations so far, it appears that the Project will have no insurmountable environmental and social impacts but NTDC will have to make sure that compensation and assistance amounts are assessed justly and that skilled and unskilled employment should be preferentially given to the Affected Persons as far as is reasonably practicable.

56

VII. CONCLUSIONS

A. Findings and Recommendations

247. This study was carried out at the planning stage of the Project. Primary and secondary data were used to assess the environmental impacts. The potential environmental impacts were assessed in a comprehensive manner. The report has provided a picture of all potential environmental impacts associated with the Project, and recommended suitable mitigation measures. This study recommends that some further follow up studies be undertaken during project processing in order to meet the ADB requirements.

248. There are some further considerations for the planning stages such as obtaining clearance for the Project under the PEPAct but environmental impacts from the power enhancements will mostly take place during the construction stage. There are also some noise impacts and waste management issues for the operational stage that must be addressed in the detailed design and through environmentally responsible procurement. At the detailed design stage, the number of and exact locations for transmission tower enhancements may change subject to detailed surveys but the impacts are likely to be broadly similar at most locations and impacts have been reviewed in the environmental impact section of this IEE report.

249. There are a number of key actions required in the detailed design phase. Prior to construction, the NTDC must receive clearance certification from the PEPA and NTDC must complete an EMP that will be accepted by the PEPA and agreed by the contractor prior to signing the contract. The information provided in this report can form the basis of any further submission to PEPA as required in the future.

250. The line alignment is restricted to the tower placements. There is to be no compensation for land, however, crops and some trees will be compensated to the concerned parties, this compensation has been presented in the LARP. The present alignment is based on design, and its approval by NTDC in the future may be need to make revisions to the line route, which will entail a revision to the IEE/LARP. A social impact assessment and resettlement action plan (LARP) has been completed in tandem with this IEE for the whole Subproject. The study (LARP) has: (i) Examined and assess the overall social and poverty profile of the Subproject area on the basis of the primary and secondary data sources and preparation of a socio-economic profile of the project districts. (ii) Prepared a social and poverty analysis, taking into account socio-economic and poverty status of the Subproject area of influence, including the nature, extent and determinants of poverty in the Subproject area including assessment. In addition, estimation of the likely socioeconomic and poverty reduction impacts of the project should be included. (iii) Held consultations with relevant officials from the government and other relevant officials, including consultation with affected communities to assess responses to the project and ascertain the nature and scope of local participation in project planning and implementation. (iv) Identified, analyzed and, where appropriate, quantified the potential resettlement impacts (minimal) of the proposed Project on the area and the population. 251. Baseline monitoring activities should be carried out during project detailed design stage to establish the baseline of parameters for checking during the construction stage. The 57 monitoring schedule (Appendix 3) recommends monitoring on two occasions at six locations along the Dera Ghazi Khan–Loralai TXL Subproject. The results should be integrated with the contract documentation to establish performance action thresholds, pollution limits and contingency plans for the contractor’s performance.

252. During the commissioning phase, noise monitoring should ensure that statutory requirements have been achieved. Monitoring activities during project operation will focus on periodic recording environmental performance and proposing remedial actions to address any unexpected impacts.

B. Summary and Conclusions

253. Construction of Dera Ghazi Khan to Loralai double circuit transmission is a feasible and sustainable option from the power transmission, engineering, environmental, and socioeconomic points of view. Implementation of the EMP is required and the environmental impacts associated with the Subproject need to be properly mitigated, and the existing institutional arrangements are available. Additional human and financial resources will be required by NTDC to complete the designs and incorporate the recommendations effectively and efficiently in the contract documents, linked to payment milestones. The proposed mitigation and management plans are practicable but require additional resources.

254. This IEE, including the EMP, should be used as a basis for an environmental compliance program and be included as an Appendix to the contract. The EMP shall be reviewed at the detailed design stage. In addition, any subsequent conditions issued by PEPA as part of the environmental clearance should also be included in the environmental compliance program. Therefore, continued monitoring of the implementation of mitigation measures, the implementation of the environmental conditions for work and environmental clearance, and monitoring of the environmental impact related to the operation of the Project should be properly carried out and reported at least twice per year as part of the project performance report. Six monthly monitoring reports have to be submitted to ADB on effectiveness of the EMP implementation.

58 Appendix 1

PAKISTAN EIA PROCESS

ENVIRONMENTAL MANAGEMENT PLAN

Environmental Objectives Mitigation Measures (MM) recommended Timing to Locations to Implement Resp. Imp Resp concern Implement MM MM mon MM MM Design and Preconstruction Stage 1. Review of EMP Ensure EMP Ensure proposed live diversions are agreed and included in Completion of All project alignment Contractor ESIC/ADB sufficient to control contract. detailed design. impacts and Ensure final route to be built by contractor is as described in compliance with RRP with same land acquisition. statutory OR requirement of EPA Review EIA and EMP & submit revised REA & environmental assessment in line with PCC/ADB Guidelines. Resubmit. 2. Social Impacts To ensure that the To be completed prior to commencement of Before the Targeted APs and families NTDC ADB and Resettlement adverse impacts construction removal of according to the LAC. due to the property 1. Social preparation of the APs to be completed prior to houses and acquisition and commencement of construction. other structures The LAC and The Project Staff resettlement are 2. Acquisition of lands completed to minimize the the APs to be will prepare an Inventory of mitigated according uncertainty of people. given sufficient Losses (IOL). to the LARP. 3. Completed implementation of LARP to provide time with compensation and assistance to the APs. compensation 4. All the payments/entitlements are paid according to the money and entitlement matrix, which was prepared according to the assistance to LARP. resettle 5. All the impacts identified by the EIA were incorporated in satisfactorily. to the LARP and relevant entitlements included into the entitlement matrix. 3. Project Ensure compliance 1. Design all changes to alignment disclosed to EPA. Completion of All project alignment. NTDC ESIC disclosure with statutory 2. Ensure all changes to alignment are included in the detailed design. Cell/ADB requirement of EPA revised EMP. 4 Environmentally Ensure 1. Require in procurement specifications that transformers, Method ESIC Cell to check contractors ESIC Cell. NTDC / DB. responsible environmentally transformer oil and other equipment are to be free from statement Method Statements include procurement responsible PCB and other petroleum fractions that may be injurious during resources for mitigation procurement. to environment or equipment. contractor measures during negotiations. 2. Require new switchgear to be free from CFCs in selection, prior Look for Appendix 2 procurement specifications. SF6 gas insulated to contract opportunities to equipment to be effectively leak free with nominal SF6 signing. enhance design top up less than 1% per year. No later than Avoid environmental 3. Choose non-polluting or enhancing methods. Contractor pre-qualification

pollution. to submit Method Statement and schedule of 59 environmental mitigation measures in response to EMP or tender

60 Appendix2

Environmental Objectives Mitigation Measures (MM) recommended Timing to Locations to Implement Resp. Imp Resp concern Implement MM MM mon MM MM

with tender. Include enhancements, techniques to negotiations. reduce impacts. 4. Contractual clauses included to tie the implementation of environmental mitigation measures to a performance bond. 5. Waste disposal Ensure adequate 1. Create waste management policy and plan to identify 1.Prior to Locations approved by local ESIC Cell NTDC disposal options for sufficient locations for, storage and reuse of transformers detailed design waste disposal authorities. with the all waste including and recycling of breaker oils and disposal of transformer oil, stage no later design transformer oil, residually contaminated soils and scrap metal “cradle to than pre- consultant. residually grave”. qualification or contaminated soils, 2. Include in contracts for unit rates for re-measurement for tender and scrap metal. disposal. negotiations 3. After agreement with local authority, designate disposal 2. Include in sites in the contract and cost unit disposal rates accordingly. contract. 6. Noise and air Plan and design to 1. If noise at sensitive receiver exceeds WB criterion [e.g. 1. During All locations where SRs are ESIC Cell NTDC / quality mitigation ensure noise Leq55db(A)] include design and installation of acoustic designing stage within 50m of alignment ADB in design. impacts are insulation measures to control noise at SRs. no later than acceptable in 2. Consider solid barrier to attenuate noise at schools and pre-qualification operational phase. hospitals to below accepted criterion. or tender 3. Prepare Air Quality and Noise Control plan for negotiations construction stage 8 Hydrological To minimize 1. Assess expected hydrologic flow in all areas where it is Before the Considered locations to be as Contractor NTDC / and Impacts hydrological and sensitive, such as for irrigated lands taking into account commencement identified in the Detailed ESIC Cell. drainage impacts changes due to climate change as predicted by accredited of construction Drainage Report. during sources such as OECD. activities/during constructions. 2. Ensure surface flows are controlled and facilitated detailed through early re-provision of irrigation with appropriate designing stage. drainage structures in the road base including bridges and culverts. 3. Prepare Drainage Management Plan, to be completed and approved by NTDC in the DDS at least one month prior to construction. 9 Temporary 1. Prevent runoff 1. Identify locations for Erosion Control and Temporary 1. During first All stream and river crossings Contractor. NTDC / and drainage and and control erosion. Drainage along all of the line and around GSS. month after and all alignments where ESIC Cell. erosion control 2. Include 2. Include designs for EC and TD in contract (s) contract is slopes indicate erosion will be preliminary designs 3. Agree detailed EC and TD plan with NTDC / ESIC Cell at signed but a problem based on for Erosion Control least one month prior to construction. before observation. in NTDC contract. construction. 2. Include in the NTDC contract.

Environmental Objectives Mitigation Measures (MM) recommended Timing to Locations to Implement Resp. Imp Resp concern Implement MM MM mon MM MM 10 Planning To plan to minimize 1. Plan sites for worker camps and back up areas for During first Locations decided by NTDC / Contractor. NTDC / and construction the effect of the stockpiling materials and equipment in advance. month after ESIC Cell in consultation with ESIC Cell camps and work camps on the 2. Consult local community and locate to use waste/barren contract is community and the Contractor. materials surrounding land and non-agricultural plots. signed but management environment and 3. Agree use of land before construction commences before residents in the reconfirmed by the Contractor and agreed NTDC / ESIC construction area. Cell at least one month prior to construction. 2. Include in the NTDC contract. 11.Traffic Plan to minimize Avoiding blocking existing roads and other access near the No later than Important locations to be ESIC Cell. NTDC. Condition disturbance of traffic works route during construction. one month after identified n revised EMP. contract award. Plans made available to Contractor with tenders. 12. Institutional Prepare ESIC Cell 1. Develop strengthening plan for the environmental As soon as Throughout the project NTDC ADB. strengthening and for implementation management by ESIC Cell as the Project rolls out. practicable no capacity building of EMP. later than one 2. Increase staffing of NTDC Cell. month before 3. Train ESIC Cell officials to apply the EMP and to evaluate BOT contract the environmental requirements and contractors’ mitigation award. measures. 13 Prepare Full and effective 1. Prepare contractors to co-operate with the executing During pre- Throughout the project ESIC cell. NTDC / and contractors for implementation of agency, project management, supervising consultants and construction no ADB. implementation of environmental local population in the mitigation of impacts. Include the later than 1 EMP mitigation approved EIA and the EMP in the contract documentation. month after measures. BOT contract 2. Contracts must require full implementation of the EMP award. 3. Contractor to engage capable and trained environmental management staff to audit the effectiveness and review mitigation measures as project proceeds. 4. The effective implementation of the EMP audited as part of the loan. NTDC to prepare resources to fulfill the requirements of the EMP and EPA guidance on the environmental aspects of road projects Appendix 2

CONSTRUCTION STAGE 61 1.Orientation for To ensure that the 1. Conducting special briefing and / or on-site training for the Induction for all All staff members in all ESIC Cell and ESIC Cell

62 Appendix2

Environmental Objectives Mitigation Measures (MM) recommended Timing to Locations to Implement Resp. Imp Resp concern Implement MM MM mon MM MM

Contractor, and Contractor, contractors and workers on the environmental requirement site agents and categories. monthly induction Contractor to observe Workers subcontractors and of the project. Record attendance and achievement. above before and six month refresher and record and record workers understand 2. Conducting special briefing and training for Contractor on commencement course as necessary until details success and have the the environmental requirement of the project. Record of work. contractors comply / improve capacity to ensure attendance and achievement. that the 3. Agreement on critical areas to be considered and At early stages environmental necessary mitigation measures, among all parties who are of construction requirements for involved in project activities. for all mitigation measures 4. Periodic progress review sessions to be conducted every construction are implemented. 6 months employees as far as reasonably practicable. 2. Plans to control Avoid impacts from 1. Drainage management plan, Deliverable in All of NTDC alignment. Contractor ESIC. environmental and unplanned activities 2. Temporary pedestrian and traffic management plan, final form to associated by penalizing 3. Erosion control and temporary drainage plan NTDC one impacts contractors for not 4. Materials management plan, month before committing to 5. Waste management plan; construction properly planning 6. Noise and dust control plan, commences for works. 7. Safety Plan any given 8. Agreed schedule of costs for environmental mitigation stretch. measures (including maintenance where applicable). {N.B. Forest Clearance and compensatory planting plan is by NTDC} 3. Water quality To prevent adverse 1. Proper construction of TD and EC measures , Prior to Relevant locations are Contractor ESIC water quality maintenance and management including training of construction, construction within 50m of impacts due to operators and other workers to avoid pollution of water 50m from water rivers. negligence and bodies by the considerate operation of construction bodies ensure unavoidable machinery and equipment and reporting and feedback by Timing will impacts are ESIC. depend on the managed 2. Storage of lubricants, fuels and other hydrocarbons in construction effectively. self-contained dedicated enclosures >50m away from water timetable. bodies. 3. No stockpiles next ling to water bodies. 4. Proper disposal of solid waste from construction activities & worker camps. 5. Borrow sites should not be close to sources of drinking water. 4. Water To minimize impacts 1. In all areas, availability of water will be assessed to Prior to Relevant locations are all local Contractor NTDC Resources on local water evaluate the impact on community resources. construction, at water supply resources and and ESIC

Environmental Objectives Mitigation Measures (MM) recommended Timing to Locations to Implement Resp. Imp Resp concern Implement MM MM mon MM MM supply caused by 2. Project water will be obtained brought in by tanker as all local water rivers. construction necessary without depleting local village supplies. supply activities are 3. Camps will be located at least 100m away from the resources. minimized. nearest local settlement. 4. The contractors will be required to maintain close liaison Timing will with local communities to ensure that any potential conflicts depend on the related to common resource utilization for project purposes construction are resolved quickly. timetable. 5. Guidelines will be established to minimize the wastage of water during construction operations and at campsites. 5. Spoil disposal To minimize the 1. Implement Waste Management Plan. 1. Before Locations approved by ESIC/ Contractor. NTDC and construction environmental 2. Confirm conditions and safety of proposed disposal sites. construction local authority. and ESIC waste disposal impacts arising from 3. Confirm amounts of surplus rock based materials that can commences A list of temporary dumping generation of spoil be reused in the project or by other interested parties for 2. Include in the sites to be prepared at the waste, reuse where public projects. contract. bidding stage for agreement possible and 4. Confirm sufficient locations in the contract for disposal of 3. UPDATE provide adequate at least 4,000,000m3lspoil (or best updated estimate). Once a month disposal options for 5. In contracts specify locations for disposal of all unsuitable soils. construction waste and spoil at unit rates for re- measurement. 6. Used oil and lubricants shall be recovered and reused or removed from the site in full compliance with the national and local regulations. 7. Waste oil must not be burned. – Oil and solid waste disposal location to be agreed with NTDC and local authority. 8 Open burning is contrary to good environmental practice and will not be allowed. 6. Noise To minimize noise 1. Install, maintain and monitor all requisite mitigation as per Maximum 1. Strong follow up from ESIC Contractor. NTDC level increases and contract all transformers and machinery shall be fitted with allowable noise Cell required to update and ESIC ground vibrations acoustic insulation levels are locations monthly during construction 2. Hammer-type pile driving operations shall be avoided 70dB(A)LEQ. 2. Potential noise impact operations. during nighttime. locations will be within 100m Well-maintained haulage trucks will be used with speed near all settlements and controls. towns. Appendix 2 7. Air quality To minimize 1. Control all dusty materials at source. 1. Dust control 1. A list of locations to be Contractor. NTDC effectively and avoid 2. Stockpiled soil and sand shall be slightly wetted before planning will be prepared by the Contractor and ESIC complaints due to loading, particularly in windy conditions. a line item in the 1month prior to

the airborne 3. Fuel-efficient and well-maintained haulage trucks shall be approval of commencement of 63 particulate matter employed to minimize exhaust emissions. setting up dust construction.

64 Appendix2

Environmental Objectives Mitigation Measures (MM) recommended Timing to Locations to Implement Resp. Imp Resp concern Implement MM MM mon MM MM

released to the 4. Vehicles transporting soil, sand and other construction producing atmosphere. materials shall be covered. Limitations to speeds of such activities. 2. Most villages and hamlets vehicles necessary. Transport through densely populated are sensitive locations area should be avoided. 2.A schedule of (Appendix E) 5. Spray bare ground areas with water. spraying water to be revised 3. All concrete plant and any monthly rock crushing plant. 8. Soil Avoid soil Contractors to instruct and train workforce in the storage Instruct before Throughout all NTDC. Contractor NTDC Contamination contamination and handling of materials and chemicals that can potentially works and ESIC cause soil contamination. commence and Accidentally spills on open ground including the top 2cm of throughout all any contaminated soil shall be disposed of as chemical construction waste to a disposal site acceptable to the local authority / works. community. 9. Work Camp To ensure that the 1. Confirm location of work camps in consultation with UPDATE Once Location Map is prepared by Contractor NTDC Location and operation of work NTDC and local authorities. Location subject to approval by a month the Contractor in tender/ bid and ESIC Operation camps does not the NTDC. If possible, camps shall not be located near documentation. adversely affect the settlements or near drinking water supply intakes. surrounding 2. Water and sanitary facilities shall be provided for workers environment and and employees. residents in the 3. Solid waste and sewage shall be managed according to area. the national and local regulations. As a rule, solid waste must not be dumped, buried or burned at or near the project site, but shall be disposed of to the nearest site approved by the local authority. 4. Portable lavatories or at least pit latrines will be installed and open defecation shall be discouraged and prevented by keeping lavatory facilities clean at all times. 5. The Contractor shall document that all liquid and solid hazardous and non-hazardous waste are separated, collected and disposed of according to the given requirements and regulations. 6. At the conclusion of the project, all debris and waste shall be removed. All temporary structures, including shelters and toilets shall be removed. 7. Exposed areas shall be planted with suitable vegetation. 8. The ESIC Cell shall inspect and report that the camp has been vacated and restored to pre-project conditions as far as is reasonably practicable. 10. Safety To ensure physical 1. Submit Safety Plan one month before commencement of During All areas of NTDC alignment. Contractor NTDC

Environmental Objectives Mitigation Measures (MM) recommended Timing to Locations to Implement Resp. Imp Resp concern Implement MM MM mon MM MM Precautions for safety of workers construction. construction and ESIC Workers 2. Providing adequate warning signs. 3. Providing every worker with skull guard or hard hat and safety shoes. 4. Establish all relevant safety measures as required by law and good engineering practices. 5. The Contractor shall instruct his workers in health and safety matters, and require the workers to use the provided safety equipment. 11. Social To engage local 1. Use local labor as far as possible for manual work. Claims of APs AA list of current construction Contractor NTDC Impacts workforce and 2. Use local educated people for clerical and office work to be solved as areas and planned works to be and ESIC community in the where possible. soon as updated by the Contractor Cell NTDC Project. 3. Encourage monitoring of the project by local village possible monthly and displayed at local To encourage local groups. village offices. support for the 4. Claims/complaints of the people on construction Necessary project. nuisance/damages close to ROW to be considered and evacuations to Special attention to locations To ensure minimum responded to promptly by the Contractor and monitored by be done as of irrigation systems, irrigated impacts to people NTDC. when necessary terraces and lands damaged living close to the 5. Quarterly meetings with local VDC for liaison purposes to due to flood or landslide. ROW. monitor complaints. 6. Set up or maintain local communication lines via landline or satellite phone. 12. To make 1. Include planting of trees in addition to those removed Before close out All areas of the alignment. Contractor NTDC Enhancements environmental such as under lines in detailed design for visual interest and of construction and ESIC enhancements and amenity. in all areas Cell improve appearance close to the ROW.

Appendix 2

Environmental Objectives Mitigation measures recommended Proposed timing Proposed Responsibility Concern locations OPERATIONAL STAGE 65

66 Appendix2

1. Encroachment To control 1. Maintain and monitor NTDC RoW boundary to prevent encroachment. During operation ESIC NTDC and community encroachment. 2. Involve local community in line monitoring awareness 3. Conduct awareness campaigning with the local public to foster public stewardship of the area around the towers to prevent the encroachment. 4. Patrol and monitor the NTDC RoW & involve local groups or an NGO in the protection of the new line. 5. Report any areas of encroachment into the ROW to the ESIC. 2 Crops and Monitor impacts Track growth of large trees under the conductors. Operational phase all NTDC and vegetation from maintaining subprojects ESIC tree clearance in future under transmission tranches lines ADB = Asian Development Bank, AP = affected people, BOT = build-operate-transfer, DDS = detailed design stage, EIA = Environmental Impact Assessment, EMP= environmental management action plan, EPA= Environmental Protection Agency, ESIC = Environmental and Social Implementation Cell, GSS = Grid Substation, IOL = Inventory of Losses, LAC = Land Acquisition Collector, LARP = land acquisition and resettlement plan, MM = mitigating measure, NGO = nongovernment organization, NTDC = National Transmission and Despatch Company, OECD = Organization for Economic Co-operation and Development, PCB = Polychlorinated Biphenyls, PEPAct = Pakistan Environmental Protection Act 1997 (as regulated and amended), REA = Rapid Environmental Assessment, ROW = right of way, RRP = Report and Recommendation of the President, SF6 = sulfur hexafluoride, SR = sensitive receiver, TD = temporary drainage, VDC = Voluntary District Committee, WB = World Bank.

Notes: Based on EIA/IEE reports to be revised at DDS, RAP, SIA and other engineering considerations may change. ADB checks that processes have been completed and signed off by NTDC before moving to construction stage.

Source: Project Preparatory Technical Assistance Consultants.

MONITORING PLAN FOR PERFORMANCE INDICATORS Environmental Performance indicator (PI) Frequency to Timing to check Locations to Responsible Cost of Resp PI Cost of concern monitor PI implement PI to implement Implementation supervision Supervision PI Design and Preconstruction Stage 1. Review of Environmental Management Action During detailed By completion of All project Contractor Initially NTDC NTDC, ESIC ESIC cell EMAP Plan (EMAP) is reviewed design (later monthly detailed design. alignment Cell / later / ADB* staff cost by Contractor to Contractor cost cover any unidentified impacts) 2. Social Inventory of losses, Property Completed prior to Before removal APs according NTDC Cell NTDC Cell staff NTDC ESIC staff Impacts and acquisition, compensation and commencement of of houses and to RP & LAFC. cost /ADB* cost Resettlement resettlement completed to RP construction structures. requirements. 3. Project Design changes notified During detailed Completion of All project Contractor Contractor cost NTDC & ESIC staff disclosure design by Contractor detailed design. alignment. ESIC cell / cost to cover any access ADB* roads and alignment changes, additional Villages. 4. Environmen- Contract follows ADB Guidelines on Once, before Before Contract Method NTDC Project Contractor cost NTDC ESIC NTDC Cell tally ERP. Performance bond. Deposited Contract is signed. is signed. Statements Cell. cell / ADB*. staff cost Responsible include Contractual clauses include Procurement. resources for implementation of environmental (ERP) mitigation mitigation measures tied to a measures. performance bond. 5. Waste Disposal options for all waste Monthly or as 1.Prior to Locations NTDC cell ESIC ESIC NTDC disposal transformer oil, residually required in waste detailed design approved by with the contaminated soils, scrap metal management plan to stage no later local waste design agreed with NTDC and local identify sufficient than pre- disposal consultant. authority. locations for, storage qualification or authorities. and reuse of tender transformers and negotiations recycling of breaker 2. Include in oils and disposal of contract.

transformer oil, Appendix 3 residually contaminated soils and scrap metal 67

68 Appendix3

Environmental Performance indicator (PI) Frequency to Timing to check Locations to Responsible Cost of Resp PI Cost of concern monitor PI implement PI to implement Implementation supervision Supervision

PI “cradle to grave”. 2. Include in contracts for unit rates for re- measurement for disposal. 3. After agreement with local authority, designate disposal sites in the contract and cost unit disposal rates accordingly. 6. Noise and air Design changes included in EIA During detailed Completion of As defined in NTDC Cell / Contractor cost NTDC / NTDC Cell quality (supplementary) & EMAP approved design by Contractor. detailed design. EIA Contractor /ADB* staff cost mitigation in by MOEST. (supplementary design. ) & EMAP. 7. Hydrological Temporary Drainage Management During detailed One month Considered Contractor Contractor cost NTDC / and NTDC Cell Impacts plan. design by Contractor before locations to be NTDC staff cost and monthly to cover commencement as identified in Project Cell. any unidentified of construction the Detailed impacts Drainage Report. 9. Temporary Erosion Control and Temporary During detailed One month All stream and Contractor. Contractor cost NTDC / and NTDC Cell drainage and Drainage completed. design updated by before river crossings NTDC staff cost erosion Contractor monthly to construction and where Project Cell. control cover any unidentified commences. slopes indicate impacts. erosion will be a problem. 10. Planning Use of land agreed with surrounding During detailed One month Locations Contractor Contractor cost NTDC / and NTDC Cell construction residents & Villages. design updated by before agreed NTDC NTDC Cell NTDC staff cost camps Contractor monthly to construction cell in facilitates. Project Cell. cover any unidentified commences. consultation impacts. with community and the Contractor. 13.Traffic Temporary Pedestrian and Traffic During detailed One month Locations Contractor Contractor cost NTDC / and NTDC Cell Condition Management Plan agreed. design updated by before agreed with NTDC staff cost Contractor monthly to construction NTDC cell in Project Cell.

Environmental Performance indicator (PI) Frequency to Timing to check Locations to Responsible Cost of Resp PI Cost of concern monitor PI implement PI to implement Implementation supervision Supervision PI cover any unidentified commences. consultation impacts. with community and the Contractor. 15. Institutional 1. Strengthening plan agreed for 1. Once, 1. As soon as Throughout the NTDC Project NTDC Cell staff NTDC / and ADB cost of strengthening NTDC cell. 2. Once practicable project Cell. cost /ADB*. IES & and capacity 2. International environment specialist 3. Ongoing 2, 3, 4. No later support for 1 building (IES) 4. Ongoing than one month month 3. Increase staffing of NTDC Cell. before Contract US$25,000 4. Train NTDC Cell officials. award. Construction Stage 1.Orientation for 1. Contractor agreed to provide 1. Once 1. Before All BOT staff Contractor Contractor cost NTDC and NTDC Cell Contractor, and training to professional staff and 2. Ongoing contract is members in all with IES NTDC to staff cost Workers workers. 3. Ongoing signed categories. assistance observe and 2. Special briefing and training for 2. Before monthly and record record Contractor completed. construction induction and details. success 3. Periodic progress review areas are six month sessions. opened up refresher 3. Every 6 course months 2. Plans to 1. Drainage Management plan Deliverable in final One month All of NTDC Contractor Contractor cost NTDC NTDC Cell control 2. Temp. Pedestrian & Traffic form to NTDC cell before alignment. Project Cell. staff cost environmental Management plan, one month before construction impacts 3. Erosion Control & Temp. Drainage construction commences. plan commences for any 4. Materials Management plan, given stretch. 5. Waste Management plan; 6. Noise and Dust Control plan, 7. Safety Plan 8. Agreed schedule of costs for environmental mitigation.{N.B. Forest Clearance and Compensatory Planting plan is prepared by NTDC cell} Appendix 3 5. Water quality Meaningful water quality monitoring Once (line item when During detailed Locations to be Independent Contractor cost NTDC / NTDC Cell up and downstream during opening up design by provided with experienced NTDC Cell. staff cost construction within 100m of rivers. construction near Contractor and the detailed laboratory. 69

70 Appendix3

Environmental Performance indicator (PI) Frequency to Timing to check Locations to Responsible Cost of Resp PI Cost of concern monitor PI implement PI to implement Implementation supervision Supervision

PI Rapid reporting and feedback by water bodies). update to cover designs NTDC. any unidentified including all impacts. bridges during construction within 100m of rivers 6. Water 1. Availability of water acceptable to 1. Monthly Prior to All local water Contractor Contractor cost NTDC and NTDC Cell Resources community. No complaints. 2. Monthly submission of supply NTDC staff cost 2. Guidelines established to progress reports. resources and Cell minimize the water wastage during rivers. construction operations and at worker camps. 8. Spoil disposal 1. Use of land agreed with Monthly (line item Prior to All NTDC Contractor Contractor cost NTDC and NTDC Cell and construction surrounding residents & Villages. when opening up construction. alignment. NTDC Cell staff cost waste disposal 2. Waste Management Plan construction). Update monthly. implemented. 3 No open burning 10. Noise Noise mitigation measures Monthly (line item Maximum All NTDC Contractor Contractor cost NTDC / NTDC Cell implemented in line with guidelines when opening up allowable noise alignment. should NTDC staff cost for noise reduction from construction). levels are maintain the Project Cell ISO/TR11688-1:1995(E) 70dB(A)LEQ. accepted will monitor standards sample activities. 11. Air quality Noise and dust control plan Monthly (line item Prior to All NTDC Contractor Contractor cost NTDC and NTDC Cell implemented. when opening up construction. alignment. NTDC Cell staff cost construction). Update monthly. 13..Soil Contractors workforce to instructed Monthly (line item Prior to All NTDC Contractor Contractor cost NTDC and NTDC Cell Contamination and train handling of chemicals when opening up construction. alignment. NTDC Cell staff cost construction). Update monthly. 14. Work Camp 1. Use of land agreed with Monthly (line item Prior to All NTDC Contractor Contractor cost NTDC and NTDC Cell Location and surrounding residents & Villages. when opening up construction. alignment. NTDC Cell staff cost Operation 2. Waste Management Plan construction). Update monthly. implemented. 3 No open burning 19. Safety Safety Plan submitted Once (update One month All NTDC Contractor. Contractor cost NTDC / NTDC Cell Precautions for monthly as before alignment. (ESIC cell to staff cost Workers necessary) construction and actively

Environmental Performance indicator (PI) Frequency to Timing to check Locations to Responsible Cost of Resp PI Cost of concern monitor PI implement PI to implement Implementation supervision Supervision PI update quarterly. supervise and enforce. 20. Social 1. Local labor is used and workforce Monthly (line item During All NTDC Contractor Contractor cost NTDC and NTDC Cell Impacts 2. Local educated people for office when opening up construction. alignment. NTDC Cell staff cost work. construction). Update monthly. 3. Complaints on construction nuisance damages close to ROW are responded to promptly by the Contractor. 4. Quarterly meetings with local VILLAGE for liaison purposes to monitor complaints. 21. Contractor has included for some Once (update One month All NTDC Contractor. Contractor cost NTDC / NTDC Cell Enhancements enhancements in detailed designs monthly as before alignment. (NTDC Cell staff cost Including planting of trees in necessary) construction and to actively addition to bioengineering such as update quarterly. supervise in median and enforce. Operational Stage 1. Air Quality 1. Roadworthiness of vehicles on 1. Roadworthiness of During 5 locations on Contractor Contractor cost NTDC / and NTDC Cell NTDC. vehicles on NTDC operation. NTDC ESIC Cell staff cost 2. Monitor NO2 and PM10 as Daily during alignment indicators. operations nearest 2. Yearly intervals for settlements. 3 years after opening for reassurance. 2. Crops and 1. Follow up on Tree Clearance and 1) Quarterly 1) Throughout All NTDC Contractor ESIC NTDC MOFSC and vegetation Compensatory Planting Plan. 2) Quarterly project alignment. NTDC staff 2. Records on survival of planted 3) Quarterly 2) Each of three cost. trees. 4) Quarterly years after initial 3. The compensatory planting planting. maintained 3) Continuous 4. Audited report by ESIC for on site for three years and off-site compensatory planting. after project completion 4) For 4 years Appendix 3 after initial clearance of the 71

72 Appendix3

Environmental Performance indicator (PI) Frequency to Timing to check Locations to Responsible Cost of Resp PI Cost of concern monitor PI implement PI to implement Implementation supervision Supervision

PI forest. ADB = Asian Development Bank, AP = affected people, BOT = build-operate-transfer, EIA = Environmental Impact Assessment, EMAP= environmental management action plan, ERP = Environmentally Responsible Procurement, ESIC = Environmental and Social Implementation Cell, IEC = International environment specialist, LAFC = Land Acquisition Compensation Fixation Committee, MOEST = Ministry of Environment, Science and Technology, NTDC = National Transmission and Despatch Company, ROW = right of way, RP = Resettlement Plan.

Notes: Based on EIA/IEE reports to be revised at DDS, RAP, SIA and other engineering considerations may change. ADB checks that processes have been completed and signed off by NTDC before moving to construction stage.

Source: Project Preparatory Technical Assistance Consultants. Appendix 3 73

I. MONITORING PLAN

1. NTDC have established the Environmental and Social Impacts Cell (ESIC) manned by two professionals and support staff .The cell is attached with both the implementing Agency , the Chief Engineer EHV (General Manager Grid System Construction , NTDC ) and the planning agency Project Director Technical Assistance (General Manager Planning , NTDC) . The NTDC instructional arrangement with respect to social and environmental monitoring and implementation is presented as follows:

II. INSTITUTIONAL ARRANGEMENTS

2. The implementation and monitoring of the social and environmental program involves a number of agencies including, NTDC as the implementing agencies, the Environmental Protection Agencies of Sindh, Provincial Government Sindh.

A. National Transmission and Dispatch Company 3. NTDC as the prime executing agency (EA), bears the overall responsibility for the preparation, implementation and financing of all tasks set out in this IEE/ LARP, as well as, inter-agency coordination, and monitoring and evaluation activities required the LARP preparation, implementation, and monitoring and evaluation. Institutionally, NTDC has three functional divisions, namely the Planning, Projects and Grid Station Construction divisions. 4. The Planning Division is responsible for planning and preparation of subprojects and keeping liaison with the Government of Pakistan and Asian Development Bank (ADB), as the donor of this Project. This division is currently being assisted by the PPTA Consultants11, including a Environmental Expert for the preparation of the IEE and Resettlement Expert responsible for LARP preparation), in preparing the identified subprojects in line with the ADB Policies and obtaining approval from the donor ADB. 5. The Projects Division is responsible for the overall management and coordination of the subprojects. Its major functions include, keeping regular liaison with ADB and relevant departments of the federal and provincial governments, updating of IEE/LARP and its monitoring and evaluation activities. In addition, the Project Management Unit takes care of the overall coordination and liaison with the Government of Pakistan and ADB. It will be assisted by the Project Management Consultants team, including a Resettlement Specialist, to be hired shortly12. Secondly, the Environmental and Social Impact Cell is responsible for the updating of and internal monitoring of IEEs/LARPs of approved Subprojects. It will be assisted by the Resettlement Specialist in the external Monitoring and Evaluation Consultants team to be hired shortly.13 6. The Grid Station Construction Division is responsible for implementing the Subprojects, including IEE/LARP preparation/updating and implementation. This large division is divided into two geographical regions, each headed by a Chief Engineer. They are EHV – I (Northern Region, ) and EHV – II (Southern Region, Hyderabad). The Rohri to Gumbat 132kV Transmission Line Subproject falls under the jurisdiction of EHV – II (Hyderabad), where a Project Director as head of the Project Implementation Unit (PIU), along with an Executive

11 British Power International (BPI), a UK Based firm. 12 The hiring pf Project Management Consultants team is under process of selection (proposals are being evaluated). 13 The hiring of Monitoring and Evaluation Consultants team is under process of selection (proposals are being evaluated).

74 Appendix 3

Engineer and Sub-Divisional Officers (Junior Engineers) will be managing the construction works. 7. Besides, each regional EHV has an in-house Land Acquisition Collector (LAC), who along with his field staff, an Assistant Land Acquisition Officer (Tehsildar) and Patwaris will take care of the updating (if required) and implantation of the LARP. The NTDC LAC normally works as an independent entity, but in case of local needs like price updating, grievance redress, etc., involves the respective District Government, especially the District Coordination Officer (DCO / District LAC), Union Council Nazims, and other local leaders, and/or the Provincial Revenue Boards, for addressing broader matters and resolving permanent Land Acquisition issues (not applicable to this Subproject). In addition, the NTDC LAC will be provided technical assistance by the Resettlement Specialist included in both the Project Management Consultants and the external Monitoring and Evaluation Consultants teams. This intuitional arrangement is presented as follow: Appendix 3 75

Figure A3.1: NTDC Organization for LARP Planning, Implementation and Monitoring

Chief Executive, NTDC

General Manager, General Manager, Projects General Manager, Grid Station Planning (GM Planning) (GM Projects) Construction (GM, GSC)

Project Chief Engineer, Project Chief Engineer, Director, EHV-II, Preparation EHV-I, Lahore Project Hyderabad Consultants Preparation (PPTA/BPI) (PD PPTA)

Project Project Director Manager, Project Project Director Management Unit Management Project Project (PMU) Consultants Implementation Implementation Unit (PIU) Unit (PIU)

Environmental and Environmental and Social Impacts Cell Social Monitoring XEN & SDOs XEN & SDOs (ESIC) Consultants

Land Land Acquisition Provincial Boards of Revenue Acquisition Collector (For Land Acquisition) Collector (LAC) (LAC)

District LACs, Tehsildars/Patwaris Assistant Land Assistant Land (For Land Acquisition) Acquisition Acquisition Officer Officer (ALAO) Affected (ALAO) Households / Tehsildar/Patwari Communities Tehsildar/Patwari

8. The amount and scope of work to be handled by the above referred cell far exceeds the physical and professional ability and capabilities of the incumbents. To support this cell, to carry out this task: monitoring consultants (MC) are being hired (these are also required as per ADB loan covenants). The brief terms of Reference of the MC is as follows:

B. Environmental monitoring

76 Appendix 3

9. An environment evaluation expert(s) for a period of four person-month (on as and when required basis) who will undertake monitoring of IEEs and also other environmental issues related to design, construction and commissioning of the subprojects according to the relevant reports already prepared and approved by NTDC/ADB. The expected completion time of these projects is 1 year.

1. Design Phase

(I) Monitor final site selection process and final alignment selection process and its environmental compliance with EMP. (II) Review the implementation of the land acquisition plan and expropriation, including considerations concerning vulnerable groups among land-owners, farmers, and farm workers. (III) Monitor contractor’s detailed project design to ensure relevant environmental mitigation measures in EMP have been included. (IV) Monitor the detailed environmental guidelines for construction works, including procurement, management, works, closing operations etc in the light of IEE and EMP. (V) Review the management plan for mineral construction materials and waste management. (VI) Audit detailed designs of facilities and installations to ensure standard environmental safeguards/ mitigation measures (as identified in EMP) have been included. (VII) Review landscape design plan, including compensatory planting. (VIII) Monitor the performance of environmental training and briefings for the creation of environmental awareness of project staff and NTDC.

2. Construction phase

(I) Regular monitoring and reporting of contractor’s compliance with contractual environmental mitigation measures in light of IEE and EMP. (II) Monitoring of the implementation of the landscape design plan.

3. Operation and Maintenance phase

(I) Monitoring of routine maintenance of facilities and transmission line in light of mitigation measures specified in EMP. (II) Monitoring of the implementation of the landscape design plan.

10. The MC will mainly assist the cell in the monitoring functions .NTDC is also in the process of hiring Management consultants, who will assist the Project Management Unit (PMU) of NTDC in amongst other things the implementation of the IEE/LARP, including updating of LARP s (price updating ) and updating of IEEs when ever major changes are made to approved sub projects .the Terms of Reference (related to social and environmental aspects) of the Implementation consultants are as follows :

Appendix 3 77

(i) Specifically, the PMC shall ensure that: (a) All environmental assessment, framework, and plans for all the subprojects should be conducted and implemented in accordance with ADB’s Environment Policy and Environmental Assessment Guidelines, and Pakistan environmental assessment regulations and guidelines. (b) All land acquisition, and resettlement framework and plan are implemented promptly and efficiently according to its terms in accordance with the applicable Pakistan laws, and ADB’s Policy on Involuntary Resettlement. (c) PMU will guarantee that all subprojects affecting ethnic minorities are constructed and operated in accordance with the requirements of ADB’s Policy on Indigenous Peoples and applicable Pakistan rules and regulations. (d) PMU will follow the principles of the ADB’s Policy on Gender and Development and use appropriate Pakistan laws during each subproject implementation.

The Activities at various stages of the project cycle are presented as follows:

Sr. Monitoring Parameter Monitoring Timing Responsibility No. Locations Design Phase 1. Audit project bidding documents - Prior to issue of NTDC through to ensure IEE and EMP is biding documents project included implementation unit. 2. Monitor that the selection - Prior to NTDC NTDC with the process and final alignment approval of assistance of and selection process and its contractor’s detail external environmental compliance with alignment survey environmental EMP consultants 3. Monitor contractor’s detail project - Prior to NTDC NTDC with the design to ensure relevant approval of assistance of environmental mitigation contractor’s detail project measures in EMP have been alignment survey implementation included unit 4. Monitor through implementation - Prior to NTDC NTDC with the of detail environmental guidelines approval of assistance of and for construction works including contractor’s detail external procurement management, design environmental works and closing operation consultants 5. Review the mineral, construction - Prior to NTDC NTDC with the materials and waste approval of assistance of and management contractor’s detail external design environmental consultants 6. Audit detail design of facilities - Prior to NTDC NTDC with the and installation to ensure approval of assistance of standard contractor’s detail project design implementation unit

78 Appendix 3

Construction Phase Sr. Monitoring Parameter Monitoring Locations Timing Responsibility No. 1 Observation of soil Construction sites, During routine PMU erosion campsites monitoring 2 Water quality At wells and surface Before mobilization Contractor/PMU water bodies near grid station and construction campsites Selected local wells Monthly Contractor/PMU Selected locations at Monthly Contractor/PMU nearby surface water bodies 3 Water consumption Construction sites, Daily Contractor/PMU campsite 4 Checks for any damage Construction sites During routine PMU to water course, monitoring groundwater wells 5 Ambient air quality Construction sites, Before mobilization Contractor/PMU campsites Construction sites, Once every two Contractor/PMU campsites months 6 Checks for exhaust Construction sites, During routine Contractor/PMU emissions campsites monitoring Checks for dust emissions Construction sites, During routine Contractor/PMU campsites, project monitoring roads 7 Noise At nearby communities Fortnightly or during Contractor/PMU the construction activities causing noise. 8 Public concerns At nearby communities Throughout the field PMU activities.

Operational Phase Sr. Monitoring Parameter Monitoring Locations Timing Responsibility No. 1 Compensatory tree Selected sites for After construction NTDC planting plantation of trees phase 2 Crops and vegetation Land under the During routine NTDC transmission line maintenance 3 Social safety Impacts Population along During routine NTDC transmission line maintenance PMU = Project Monitoring Unit, NTDC = National Transmission and Despatch Company Complete record of sampling and analysis should be maintained and documented.

Appendix 3 79

Summary of Estimated Costs for EMP

Implementation for Tranche 1

Staffing, audit 1 person for 2 years 1,200,0001 19,900 and monitoring Monitoring As detailed under EMP 5,000,0002 83,000 activities Mitigation As prescribed under EMP and 8,000,0003 132,800 measures IEE Transport 1 dedicated vehicle 2 years 1,000,0004 16,600 Contingency 3% contingency 456,000 7,600 Total 15,656,000 259,900 Cost for SP about 1/7th of total monitoring costs for Tranche 1.

1 @ Rs. 50,000/month. 2 Laboratory charges for: testing of construction materials; water quality tests; ambient air tests; emissions measurements; and noise measurements. 3 Includes: Compensatory tree plantation under supervision of forest department; and training on counterpart staff. 4 @ Rs. 25,000 per month rental charges and Rs. 550.0 per day fuel and operating cost

80 Appendix4

SUMMARY OF PUBLIC CONSULTATION

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests Man Group: Basti Shikar Khan 1. Shikar Khan Khosa Landowner Basti Shikar 18-3- Tree compensation Compensation NTDC should pay Khan 08 should be fair and timely should be paid compensation of crops and adequately and trees fairly and timely at timely least 15 days before civil works 2. Khuda Bukhsh Khosa Landowner Basti Shikar 18-3- Tree compensation Compensation NTDC should pay Khan 08 should be fair and timely should be paid compensation of crops and adequately and trees fairly and timely at timely least 15 days before civil works 3. Sabzal Khan Khosa Landowner Basti Shikar 18-3- Tree compensation Compensation NTDC should pay Khan 08 should be fair and timely should be paid compensation of crops and adequately and trees fairly and timely at timely least 15 days before civil works 4. Mehr Bakhsh Khosa Shepherd Basti Shikar 18-3- Electricity should be Electricity should NTDC should consider Khan 08 provided to the affected be provided to the electrification of villages which are still villages / houses villages/houses, which are without electricity which are not not electrified yet. electrified Woman Group: Basti Shikar Khan 5. Salima Mai House-Wife Basti Shikar 18-3- Line should not pass Line should be NTDC should avoid Khan 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 6. Shabnam Bibi House Girl Basti Shikar 18-3- Extensive load shedding - - Khan 08 in the summer is a nuisance; she hoped the TXL would improve the situation. 7. Norina Kulsoom House Girl Basti Shikar 18-3- Local norms should be Contractor/labor NTDC should the contractor Khan 08 honored should honor the to respect the local norms. local norms 8. Maryam Bibi House-Wife Basti Shikar 18-3- Line should not pass Line should be NTDC should avoid Khan 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. Man Group: Rajhani Village 9. Musallim Master Landowner Rajhani Village 19-3- Tree compensation Compensation NTDC should pay 08 should be fair and timely should be paid compensation of crops and

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests adequately and trees fairly and timely at timely least 15 days before civil works 10. Razi Khan Landowner Rajhani Village 19-3- Tree compensation Compensation NTDC should pay 08 should be fair and timely should be paid compensation of crops and adequately and trees fairly and timely at timely least 15 days before civil works 11. Mithu Khan Mujawar Sharecropper Rajhani Village 19-3- Tree compensation Compensation NTDC should pay 08 should be fair and timely should be paid compensation of crops and adequately and trees fairly and timely at timely least 15 days before civil works 12. Wahid Bakhsh Mujawir Landowner Rajhani Village 19-3- Tree compensation Compensation NTDC should pay 08 should be fair and timely should be paid compensation of crops and adequately and trees fairly and timely at timely least 15 days before civil works 13. Ghulam Sarwar Teacher Rajhani Village 19-3- Load shedding is more in - - 08 villages and affects all spheres of life including schools. Woman Group: Rajhani Village 14. Shamman Mai House-Wife Rajhani Village 19-3- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 15. Bakhtawar Mai House-Wife Rajhani Village 19-3- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 16. Haleema Mai House-Wife Rajhani Village 19-3- Local norms should be Contractor/labor NTDC should the contractor 08 honored should respect the to honor the local norms. local norms 17. Lali Mai House-Wife Rajhani Village 19-3- Local norms should be Contractor/labor NTDC should the contractor 08 honored should respect the to honor the local norms. local norms Man Group: Village Gamoli, Choti Bala Road 18. Nabli Ramba Mujawir Landowner Village Gamoli, 20-3- Crop and tree Compensation NTDC should pay Choti Bala 08 compensation should be should be paid compensation of crops and Appendix 4 Road fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 19. Fazlur Rahman Mujawir Landowner Village Gamoli, 20-3- Crop and tree Compensation NTDC should pay Choti Bala 08 compensation should be should be paid compensation of crops and 81

82 Appendix4

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions &

Requests Road fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 20. Bhagoo Khan Mujawir Landowner Village Gamoli, 20-3- Crop and tree Compensation NTDC should pay Choti Bala 08 compensation should be should be paid compensation of crops and Road fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 21. Chimru Khan Mujawir Landowner Village Gamoli, 20-3- Crop and tree Compensation NTDC should pay Choti Bala 08 compensation should be should be paid compensation of crops and Road fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 22. Mohammad Rasheed Sharecropper Village Gamoli, 20-3- Crop and tree Compensation NTDC should pay Choti Bala 08 compensation should be should be paid compensation of crops and Road fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 23. Afzal Alyani Landowner Village Gamoli, 20-3- Crop and tree Compensation NTDC should pay Choti Bala 08 compensation should be should be paid compensation of crops and Road fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 24. Kaurra Mekrri Landowner Village Gamoli, 20-3- Crop and tree Compensation NTDC should pay Choti Bala 08 compensation should be should be paid compensation of crops and Road fair and timely adequately and trees fairly and timely at timely least 15 days before civil works Woman Group: Village Gamoli, Choti Bala Road 25. Nasima Mai House-Wife Village Gamoli, 20-3- Line should not pass Line should be NTDC should avoid Choti Bala 08 over the houses avoided to pass distribution lines to pass Road over the houses over the houses. 26. Madho Mai House-Wife Village Gamoli, 20-3- Local norms should be Contractor/labor NTDC should the contractor Choti Bala 08 honored should respect the to honor the local norms. Road local norms 27. Amir Bibi House Girl Village Gamoli, 20-3- Local norms should be Contractor/labor NTDC should the contractor Choti Bala 08 honored should respect the to honor the local norms. Road local norms 28. Shamim House-Wife Village Gamoli, 20-3- Line should not pass Line should be NTDC should avoid Choti Bala 08 over the houses avoided to pass distribution lines to pass Road over the houses over the houses. 29. Hayati Mai House-Wife Village Gamoli, 20-3- Local norms should be Contractor/labor NTDC should the contractor

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests Choti Bala 08 honored should respect the to honor the local norms. Road local norms Man Group: Pailia Thal Bawata 30. Jan Mohammad Leghari Landowner Pailia Thal 21-3- Crop and tree Compensation NTDC should pay Bawata 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 31. Haji Sain Dad Leghari Landowner Pailia Thal 21-3- Crop and tree Compensation NTDC should pay Bawata 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 32. Spar Khan Leghari Landowner Pailia Thal 21-3- Crop and tree Compensation NTDC should pay Bawata 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 33. Shahab Din Khetran Landowner Pailia Thal 21-3- Crop and tree Compensation NTDC should pay Bawata 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 34. Manzoor Hussain Landowner Pailia Thal 21-3- Crop and tree Compensation NTDC should pay Khetran Bawata 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works Woman Group: Pailia Thal Bawata 35. Rehmat Mai House-Wife Pailia Thal 21-3- Local norms should be Contractor/labor NTDC should bind the Bawata 08 honored should honor the contractor to respect the local norms local norms. 36. Mira Mai House Girl Pailia Thal 21-3- Prolonged load shedding Line should not NTDC should avoid Bawata 08 in the summer is a pass over the distribution lines to pass nuisance; she hoped the houses of the over the houses. TXL would improve the colony. situation. 37. Lali Mai House-Wife Pailia Thal 21-3- Local norms should be Contractor/labor NTDC should bind the Appendix 4 Bawata 08 honored should honor the contractor to respect the local norms local norms. 38. Gulshan House Girl Pailia Thal 21-3- Prolonged load shedding Line should not NTDC should avoid Bawata 08 in the summer is a pass over the distribution lines to pass nuisance; she hoped the houses of the over the houses. 83

84 Appendix4

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions &

Requests TXL would improve the colony. situation. 39. Mukhtar Mai House-Wife Pailia Thal 21-3- Local norms should be Contractor/labor NTDC should bind the Bawata 08 honored should honor the contractor to respect the local norms local norms. Man Group: Sarpa Village Bawata 40. Pahada Khan Khetran Landowner Sarpa Village 15-4- Crop and tree Compensation NTDC should pay Bawata 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 41. Kalu Khan Khetran Landowner Sarpa Village 15-4- Crop and tree Compensation NTDC should pay Bawata 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 42. Karim Khan Khetran Sharecropper Sarpa Village 15-4- Crop and tree Compensation NTDC should pay Bawata 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 43. Mohammad Afzal Labour Sarpa Village 15-4- Local skilled and Skilled and NTDC should employ Skilled Khetran Bawata 08 unskilled labor should be unskilled labor and unskilled labor from the used wherever possible should be area preferred from the area Woman Group: Sarpa Village Bawata 44. Bakhi Mai House-Wife Sarpa Village 15-4- Line should not pass Line should be NTDC should avoid Bawata 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 45. Humaira Mai House-Wife Sarpa Village 15-4- Line should not pass Line should be NTDC should avoid Bawata 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 46. Saira Bibi House Girl Sarpa Village 15-4- Prolonged load shedding Line should not NTDC should avoid Bawata 08 in the summer is a pass over the distribution lines to pass nuisance; she hoped the houses of the over the houses. TXL would improve the colony. situation. 47. Munira Mai House-Wife Sarpa Village 15-4- Line should not pass Line should be NTDC should avoid Bawata 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 48. Hijran Mai House Girl Sarpa Village 15-4- Prolonged load shedding Line should not NTDC should avoid Bawata 08 in the summer is a pass over the distribution lines to pass

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests nuisance; she hoped the houses of the over the houses. TXL would improve the colony. situation. Man Group: Mir Hamadani Killi 49. Mir Hamadani Landowner Mir Hamadani 15-4- Crop and tree Compensation NTDC should pay Killi 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 50. Balakh Khetran Landowner Mir Hamadani 15-4- Crop and tree Compensation NTDC should pay Killi 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 51. Haibat Saryam Landowner Mir Hamadani 15-4- Crop and tree Compensation NTDC should pay Killi 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 52. Badha Khetran Landowner Mir Hamadani 15-4- Crop and tree Compensation NTDC should pay Killi 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works Woman Group: Mir Hamadani Killi 15-4-08 53. Sanab Mai House-Wife Mir Hamadani 15-4- Line should not pass Line should be NTDC should avoid Killi 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 54. Shamim House Girl Mir Hamadani 15-4- Prolonged load shedding Line should not NTDC should avoid Killi 08 in the summer is a pass over the distribution lines to pass nuisance; she hoped the houses of the over the houses. TXL would improve the colony. situation. 55. Hava Mai Mid Wife Mir Hamadani 15-4- Line should not pass Line should be NTDC should avoid Killi 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 56. Kanara Bibi House-Wife Mir Hamadani 15-4- Line should not pass Line should be NTDC should avoid Killi 08 over the houses avoided to pass distribution lines to pass Appendix 4 over the houses over the houses. Man Group: Basti Khaprani 57. Haji Gul Moahmmad Landowner Basti Khaprani 16-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at 85

86 Appendix4

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions &

Requests timely least 15 days before civil works 58. a Khan Khetran Landowner Basti Khaprani 16-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 59. Khan Mohammad Teacher Basti Khaprani 16-4- Load shedding is more in - - 08 villages and affects all spheres of life including schools. 60. Mohammad Aslam Shopkeeper Basti Khaprani 16-4- Electricity should be Electricity should NTDC should consider Khetran 08 provided to the affected be provided to the electrification of villages which are still villages / houses villages/houses, which are without electricity which are not not electrified yet. electrified Woman Group: Basti Khaprani 61. Wazifa Mai House Girl Basti Khaprani 16-4- Prolonged load shedding - - 08 in the summer is a nuisance; she hoped the TXL would improve the situation. 62. Wazira Bibi House-Wife Basti Khaprani 16-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 63. Tajan Mai House-Wife Basti Khaprani 16-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local local norms norms. Man Group: Basti Kauri Rakni 64. Ahmad Khan Khetran Landowner Basti Kauri 16-4- Crop and tree Compensation NTDC should pay Rakni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 65. Kamal Khan Khetran Landowner Basti Kauri 16-4- Crop and tree Compensation NTDC should pay Rakni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 66. Lal Khan Khetran Landowner Basti Kauri 16-4- Crop and tree Compensation NTDC should pay Rakni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests works 67. Sahib Khan Khetran Landowner Basti Kauri 16-4- Crop and tree Compensation NTDC should pay Rakni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 68. Wadera Mohammad Landowner Basti Kauri 16-4- Crop and tree Compensation NTDC should pay Jan Rakni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 69. Gul Khan Khetran Landowner Basti Kauri 16-4- Crop and tree Compensation NTDC should pay Rakni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 70. Bilal Khan Khetran Transporter Basti Kauri 16-4- Electricity should be Electricity should NTDC should consider Rakni 08 provided to the affected be provided to the electrification of villages which are still villages / houses villages/houses, which are without electricity which are not not electrified yet. electrified 71. Sadaram Khan Khetran Landowner Basti Kauri 16-4- Crop and tree Compensation NTDC should pay Rakni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 72. Allah Dad Khetran Landowner Basti Kauri 16-4- Crop and tree Compensation NTDC should pay Rakni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 73. Khamees Khan Khetran Landowner Basti Kauri 16-4- Crop and tree Compensation NTDC should pay Rakni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 74. Ismail Shah Sheikh Landowner Basti Kauri 16-4- Crop and tree Compensation NTDC should pay

Rakni 08 compensation should be should be paid compensation of crops and Appendix 4 fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 75. Khadim Husain Shekh Teacher Basti Kauri 16-4- Electricity should be Electricity should NTDC should consider

Rakni 08 provided to the affected be provided to the electrification of 87 villages which are still villages / houses villages/houses, which are

88 Appendix4

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions &

Requests without electricity which are not not electrified yet. electrified Woman Group: Basti Kauri Rakni 76. Gul Bibi House Girl Basti Kauri 16-4- Prolonged load shedding - - Rakni 08 in the summer is a nuisance; she hoped the TXL would improve the situation. 77. Amna Mai House-Wife Basti Kauri 16-4- Line should not pass Line should be NTDC should avoid Rakni 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 78. Asmat Mai House-Wife Basti Kauri 16-4- Local norms should be Contractor/labor NTDC should bind the Rakni 08 honored should respect the contractor to honor the local local norms norms. 79. Murada Mai House Girl Basti Kauri 16-4- Prolonged load shedding - - Rakni 08 in the summer is a nuisance; she hoped the TXL would improve the situation. 80. Maryam Bibi House-Wife Basti Kauri 16-4- Line should not pass Line should be NTDC should avoid Rakni 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 81. Halima Mai House-Wife Basti Kauri 16-4- Local norms should be Contractor/labor NTDC should bind the Rakni 08 honored should respect the contractor to honor the local local norms norms. 82. Shehla Bibi House-Wife Basti Kauri 16-4- Line should not pass Line should be NTDC should avoid Rakni 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 83. Ahmad Mai House-Wife Basti Kauri 16-4- Local norms should be Contractor/labor NTDC should bind the Rakni 08 honored should respect the contractor to honor the local local norms norms. 84. Chand Bibi House Girl Basti Kauri 16-4- Prolonged load shedding Line should not NTDC should avoid Rakni 08 in the summer is a pass over the distribution lines to pass nuisance; she hoped the houses of the over the houses. TXL would improve the colony. situation. 85. Saleema Mai House-Wife Basti Kauri 16-4- Line should not pass Line should be NTDC should avoid Rakni 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 86. Sitara Mai House-Wife Basti Kauri 16-4- Local norms should be Contractor/labor NTDC should bind the Rakni 08 honored should respect the contractor to honor the local local norms norms. Man Group: Deh Bhebani Rakni

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests 87. Khuda Bukhsh Landowner Deh Bhebani 16-4- Crop and tree Compensation NTDC should pay Rakni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 88. Gamman Khan Landowner Deh Bhebani 16-4- Crop and tree Compensation NTDC should pay Rakni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 89. Sher Khan Landowner Deh Bhebani 16-4- Crop and tree Compensation NTDC should pay Rakni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 90. Amin Khan Landowner Deh Bhebani 16-4- Crop and tree Compensation NTDC should pay Rakni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works Woman Group: Deh Bhebani Rakni 91. Batool Mai House-Wife Deh Bhebani 16-4- Line should not pass Line should be NTDC should avoid Rakni 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 92. Amina Mai House-Wife Deh Bhebani 16-4- Local norms should be Contractor/labor NTDC should bind the Rakni 08 honored should respect the contractor to honor the local local norms norms. 93. Irsa Bibi House-Wife Deh Bhebani 16-4- Line should not pass Line should be NTDC should avoid Rakni 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. Man Group: Rarkan Village 17-4-08 94. Khairullah Hasni Landowner Rarkan Village 17-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 95. Rahimullah Hasni Landowner Rarkan Village 17-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and Appendix 4 fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 96. Sohrab Khan Hasni Landowner Rarkan Village 17-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and 89

90 Appendix4

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions &

Requests fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 97. Nabi Bukhsh Hasni Landowner Rarkan Village 17-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 98. Mohammad Deen Hasni Landowner Rarkan Village 17-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 99. Ahmad Deen Hasni Landowner Rarkan Village 17-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 100. Habeeb ur Rehman Landowner Rarkan Village 17-4- Crop and tree Compensation NTDC should pay Hasni 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 101. Ubaidullah Hasni Landowner Rarkan Village 17-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 102. Amanullah Hasni Landowner Rarkan Village 17-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works Woman Group: Rarkan Village 103. Phool Bibi House-Wife Rarkan Village 17-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 104. Tasleem Bibi House-Wife Rarkan Village 17-4- Local norms should be Contractor/labor NTDC should the contractor 08 honored should respect the to honor the local norms. local norms 105. Karima Mai House-Wife Rarkan Village 17-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses.

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests 106. Meena Mai House-Wife Rarkan Village 17-4- Local norms should be Contractor/labor NTDC should the contractor 08 honored should respect the to honor the local norms. local norms 107. Ameer Begum House-Wife Rarkan Village 17-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 108. Shakira Bibi House Girl Rarkan Village 17-4- Prolonged load shedding - - 08 in the summer is a nuisance; she hoped the TXL would improve the situation. 109. Shakila Bibi House Girl Rarkan Village 17-4- Prolonged load shedding - - 08 in the summer is a nuisance; she hoped the TXL would improve the situation. 110. Nahida Mai House-Wife Rarkan Village 17-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. Man Group: Village Rarrasham 111. Amir Khan Baloch Landowner Village 17-4- Crop and tree Compensation NTDC should pay Rarasham 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 112. Bakhshal Khan Baloch Landowner Village 17-4- Crop and tree Compensation NTDC should pay Rarasham 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 113. Deen Mohammad Landowner Village 17-4- Crop and tree Compensation NTDC should pay Baloch Rarasham 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 114. Ayaz Khan Baloch Shopkeeper Village 17-4- Electricity should be Electricity should NTDC should consider Rarasham 08 provided to the affected be provided to the electrification of villages which are still villages / houses villages/houses, which are Appendix 4 without electricity which are not not electrified yet. electrified Woman Group: Village Rarrasham 115. Zinat Mai House-Wife Village 17-4- Line should not pass Line should be NTDC should avoid Rarasham 08 over the houses avoided to pass distribution lines to pass 91

92 Appendix4

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions &

Requests over the houses over the houses. 116. Ashra Mai House-Wife Village 17-4- Local norms should be Contractor/labor NTDC should bind the Rarasham 08 honored should respect the contractor to honor the local local norms norms. 117. Puran Mai House Girl Village 17-4- Prolonged load shedding - - Rarasham 08 in the summer is a nuisance; she hoped the TXL would improve the situation. 118. Jannat Bibi House Girl Village 17-4- Prolonged load shedding - - Rarasham 08 in the summer is a nuisance; she hoped the TXL would improve the situation. 119. Miran Mai House-Wife Village 17-4- Line should not pass Line should be NTDC should avoid Rarasham 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. Man Group: Gidder Daag 120. Fazal Karim Khan Landowner Gidder Daag 17-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 121. Fazal ur Rehman Landowner Gidder Daag 17-4- Crop and tree Compensation NTDC should pay Baloch 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 122. Bukhsh Ali Baloch Landowner Gidder Daag 17-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 123. Hameed Khan Baloch Sharecropper Gidder Daag 17-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 124. Mujtaba Khan Baloch Landowner Gidder Daag 17-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests 125. Murtaza Khan Baloch Landowner Gidder Daag 17-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works Woman Group: Gidder Daag 126. Nasiba Mai House Girl Gidder Daag 17-4- Prolonged load shedding Line should not NTDC should avoid 08 in the summer is a pass over the distribution lines to pass nuisance; she hoped the houses of the over the houses. TXL would improve the colony. situation. 127. Hasina Bibi House-Wife Gidder Daag 17-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 128. Bilqees Akhtar House-Wife Gidder Daag 17-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local local norms norms. 129. Farzana Jamal House-Wife Gidder Daag 17-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 130. Bina Mai House Girl Gidder Daag 17-4- Prolonged load shedding - - 08 in the summer is a nuisance; she hoped the TXL would improve the situation. Man Group: Mekhtar Village 131. Gul Mohammad Khan Landowner Mekhtar Village 19-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 132. Sherak Talakzai Landowner Mekhtar Village 19-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 133. Majak Haji Landowner Mekhtar Village 19-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and Appendix 4 fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 134. Mohammad Zaman Landowner Mekhtar Village 19-4- Crop and tree Compensation NTDC should pay Nasir 08 compensation should be should be paid compensation of crops and 93

94 Appendix4

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions &

Requests fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 135. Tore Khan Palezai Landowner Mekhtar Village 19-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 136. Sardar Abdul Mannan Landowner Mekhtar Village 19-4- Crop and tree Compensation NTDC should pay Nasir 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 137. Dinnak Jallozai Landowner Mekhtar Village 19-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 138. Khula Khan Adezai Landowner Mekhtar Village 19-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 139. Aurak Haji Jallozai Landowner Mekhtar Village 19-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 140. Haji Rehmat Khan Landowner Mekhtar Village 19-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 141. Abdul Malik Nasir Landowner Mekhtar Village 19-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 142. Haji Bazik Palezai Landowner Mekhtar Village 19-4- Electricity should be Electricity should NTDC should consider 08 provided to the affected be provided to the electrification of villages which are still villages / houses villages/houses, which are without electricity which are not not electrified yet. electrified Woman Group: Mekhtar Village

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests 143. Zarina Bibi House-Wife Mekhtar Village 19-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 144. Mehnaz Bibi House-Wife Mekhtar Village 19-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local local norms norms. 145. Hameedah House-Wife Mekhtar Village 19-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 146. Haleema Bibi House-Wife Mekhtar Village 19-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local local norms norms. 147. Zalacha Old Women Mekhtar Village 19-4- Prolonged load shedding - - 08 in the summer is a nuisance; she hoped the TXL would improve the situation. 148. Zartaja House-Wife Mekhtar Village 19-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 149. Malika Gul House Girl Mekhtar Village 19-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 150. Mahnaz Gul House Girl Mekhtar Village 19-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 151. Malaika House-Wife Mekhtar Village 19-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 152. Farsheen House Girl Mekhtar Village 19-4- Prolonged load shedding - - 08 in the summer is a nuisance; she hoped the TXL would improve the situation. Man Group: Ashberg Village 153. Hidayatullah Khan Landowner Ashberg Village 20-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at Appendix 4 timely least 15 days before civil works 154. Mohammad Saleem Landowner Ashberg Village 20-4- Crop and tree Compensation NTDC should pay Khan 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at 95

96 Appendix4

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions &

Requests timely least 15 days before civil works 155. Jamal Khan Landowner Ashberg Village 20-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 156. Faiz ur Rehman Landowner Ashberg Village 20-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works Woman Group: Ashberg Village 157. Noor Nisa House-Wife Ashberg Village 20-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 158. Najiba Bibi House-Wife Ashberg Village 20-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local local norms norms. 159. Arsha Khatoon House Girl Ashberg Village 20-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local local norms norms. 160. Zarsanga House-Wife Ashberg Village 20-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. Man Group: Indah Village 161. Abdul Hameed Kakar Landowner Indah Village 20-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 162. Raz Mohammad Kakar Landowner Indah Village 20-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 163. Dost Mohammad Kakar Landowner Indah Village 20-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 164. Fazal ur Rehman Kakar Landowner Indah Village 20-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 165. Atta Mohammad Kakar Landowner Indah Village 20-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 166. Mohammad Aslam Landowner Indah Village 20-4- Crop and tree Compensation NTDC should pay Kakar 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 167. Mohammad Hayat Landowner Indah Village 20-4- Crop and tree Compensation NTDC should pay Kakar 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 168. Mohammad Iqbal Kakar Teacher Indah Village 20-4- Load shedding is more in - - 08 villages and affects all spheres of life including schools. 169. Jumma Khan Kakar Shopkeeper Indah Village 20-4- Electricity should be Electricity should NTDC should consider 08 provided to the affected be provided to the electrification of villages which are still villages / houses villages/houses, which are without electricity which are not not electrified yet. electrified Woman Group: Indah Village 170. Aasia Bibi House-Wife Indah Village 20-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 171. Akalmanda House-Wife Indah Village 20-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local local norms norms. 172. Gull Bibi House-Wife Indah Village 20-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 173. Gulnaz House Girl Indah Village 20-4- Prolonged load shedding - - Appendix 4 08 in the summer is a nuisance; she hoped the TXL would improve the situation.

174. Rehana House Girl Indah Village 20-4- Prolonged load shedding - - 97 in the summer is a

98 Appendix4

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions &

Requests 08 nuisance; she hoped the TXL would improve the situation. 175. Zarfaka House Girl Indah Village 20-4- Prolonged load shedding - - 08 in the summer is a nuisance; she hoped the TXL would improve the situation. 176. Samina House Girl Indah Village 20-4- Prolonged load shedding - - 08 in the summer is a nuisance; she hoped the TXL would improve the situation. 177. Qayamat Bibi House-Wife Indah Village 20-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. Man Group: Sehna Gharra Village 178. Haji Mirajan Landowner Sehna Gharra 21-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 179. Mullah Jamal Landowner Sehna Gharra 21-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 180. Shadi Khan Sharecropper Sehna Gharra 21-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 181. Malak Ghulam Landowner Sehna Gharra 21-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 182. Zantoo Khan Landowner Sehna Gharra 21-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 183. Mir Khan Hamzazai Landowner Sehna Gharra 21-4- Crop and tree Compensation NTDC should pay compensation should be should be paid compensation of crops and

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests 08 fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 184. Baath Khan Hamzazai Landowner Sehna Gharra 21-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 185. Khan Mohamad Landowner Sehna Gharra 21-4- Crop and tree Compensation NTDC should pay Hamzazai 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 186. Khair Mohamad Landowner Sehna Gharra 21-4- Crop and tree Compensation NTDC should pay Hamzazai 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works Woman Group: Sehna Gharra Village 187. Gul Pari House-Wife Sehna Gharra 21-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 188. Bakhtiara House-Wife Sehna Gharra 21-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local local norms norms. 189. Shekhato Bibi House Girl Sehna Gharra 21-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 190. Sanam Khatoon Student Sehna Gharra 21-4- Electricity should be Electricity should NTDC should consider 08 provided to the affected be provided to the electrification of villages which are still villages / houses villages/houses, which are without electricity which are not not electrified yet. electrified 191. Afzal Nisa House-Wife Sehna Gharra 21-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 192. Naimat Jan House Girl Sehna Gharra 21-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local Appendix 4 local norms norms. Man Group: Shabozai Village 193. Mohamad Salman Landowner Shabozai 22-4- Crop and tree Compensation NTDC should pay Kudozai 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at 99

100 Appendix4

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests timely least 15 days before civil works 194. Mohammad Sultan Landowner Shabozai 22-4- Crop and tree Compensation NTDC should pay Kudozai 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 195. Hayat Khan Kudozai Landowner Shabozai 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 196. Afta Khan Kudozai Landowner Shabozai 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 197. Laal Mohammad Landowner Shabozai 22-4- Crop and tree Compensation NTDC should pay Kudozai 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 198. Arsalan Khan Student Shabozai 22-4- Electricity should be Electricity should NTDC should consider 08 provided to the affected be provided to the electrification of villages which are still villages / houses villages/houses, which are without electricity which are not not electrified yet. electrified Women Group: Shabozai Village 199. Aslama Student Shabozai 22-4- Prolonged load shedding - - 08 in the summer is a nuisance and affects the studies; she hoped the TXL would improve the situation. 200. Akhtar Jana House-Wife Shabozai 22-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 201. Hajira House Girl Shabozai 22-4- Local norms should be Contractor/labor NTDC should the contractor 08 honored should respect the to honor the local norms. local norms 202. Saira House-Wife Shabozai 22-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses.

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests 203. Mirana House-Wife Shabozai 22-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local local norms norms. Man Group: Masood Killi 22-4-08 204. Alauddin Khan Landowner Masood Killi 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 205. Haji Feroz Khan Landowner Masood Killi 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 206. Bakhtiar Temarkhel Landowner Masood Killi 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 207. Ajamir Temarkhel Landowner Masood Killi 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 208. Sultan Khan Temarkhel Landowner Masood Killi 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 209. Ajamir Khan Temarkhel Landowner Masood Killi 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works Women Group: Masood Killi 210. Khairat Bibi House-Wife Masood Killi 22-4- Line should not pass Line should be NTDC should avoid

08 over the houses avoided to pass distribution lines to pass Appendix 4 over the houses over the houses. 211. Amir-us-Nisa House-Wife Masood Killi 22-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local local norms norms.

212. Mehnaz House Girl Masood Killi 22-4- Line should not pass Line should be NTDC should avoid 101 08 over the houses avoided to pass distribution lines to pass

102 Appendix4

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests over the houses over the houses. Man Group: Sagor Village 213. Banaras Khan Landowner Sagor Village 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 214. Bawar Khan Landowner Sagor Village 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 215. Arshad Khan Landowner Sagor Village 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 216. Amir Sultan Govt. Service Sagor Village 22-4- Electricity should be Electricity should NTDC should consider 08 provided to the affected be provided to the electrification of villages which are still villages / houses villages/houses, which are without electricity which are not not electrified yet. electrified 217. Huzoor Bakhsh Policeman Sagor Village 22-4- Electricity should be Electricity should NTDC should consider 08 provided to the affected be provided to the electrification of villages which are still villages / houses villages/houses, which are without electricity which are not not electrified yet. electrified Women Group: Sagor Village 218. Rafiqah Khanam Teacher Sagor Village 22-4- Load shedding is more in - - 08 villages and affects all spheres of life including schools. 219. Ameena Gul House-Wife Sagor Village 22-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 220. Hanifa House-Wife Sagor Village 22-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local local norms norms. 221. Mirana House-Wife Sagor Village 22-4- Line should not pass Line should be NTDC should avoid 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. Man Group: Bala Killi Tattai 222. Haji Kareem Utamkhel Landowner Bala Killi Tattai 22-4- Crop and tree Compensation NTDC should pay

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 223. Haji Khan Mohammad Landowner Bala Killi Tattai 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 224. Barat Khan Landowner Bala Killi Tattai 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 225. Haji Saleem Utamkhel Landowner Bala Killi Tattai 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 226. Hasan Nawaz Transporter Bala Killi Tattai 22-4- Electricity should be Electricity should NTDC should consider 08 provided to the affected be provided to the electrification of villages which are still villages / houses villages/houses, which are without electricity which are not not electrified yet. electrified 227. Israr Khan Utmankhel Landowner Bala Killi Tattai 22-4- Crop and tree Compensation NTDC should pay 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works Women Group: Bala Killi Tattai 228. Sehrish Student Bala Killi Tattai 22-4- Prolonged load shedding - - 08 in the summer is a nuisance and affects the studies; she hoped the TXL would improve the situation.

229. Ajeeba Khatoon House-Wife Bala Killi Tattai 22-4- Line should not pass Line should be NTDC should avoid Appendix 4 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 230. Murada Bibi House-Wife Bala Killi Tattai 22-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local local norms norms. 103 231. Marina Gul House-Wife Bala Killi Tattai 22-4- Line should not pass Line should be NTDC should avoid over the houses avoided to pass distribution lines to pass

104 Appendix4

Sr. Participant Name Participant Address Date Issues Proposed Action Taken / Proposed No. Profession Raised/Concerns Measure expressed/ Suggestions & Requests 08 over the houses over the houses. 232. Hasina Gul House Girl Bala Killi Tattai 22-4- Local norms should be Contractor/labor NTDC should bind the 08 honored should respect the contractor to honor the local local norms norms. Man Group: Naway Bawar Killi 233. Haji Faiz Mohamad Landowner Naway Bawar 22-4- Crop and tree Compensation NTDC should pay Nasir Killi 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 234. Abdul Rafique Landowner Naway Bawar 22-4- Crop and tree Compensation NTDC should pay Killi 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works 235. Master Amanullah Landowner Naway Bawar 22-4- Crop and tree Compensation NTDC should pay Killi 08 compensation should be should be paid compensation of crops and fair and timely adequately and trees fairly and timely at timely least 15 days before civil works Women Group: Naway Bawar Killi 236. Banafsha Gul House-Wife Naway Bawar 22-4- Line should not pass Line should be NTDC should avoid Killi 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 237. Hakima Khatoon House-Wife Naway Bawar 22-4- Local norms should be Contractor/labor NTDC should the contractor Killi 08 honored should respect the to honor the local norms. local norms 238. Noor Nisa House-Wife Naway Bawar 22-4- Line should not pass Line should be NTDC should avoid Killi 08 over the houses avoided to pass distribution lines to pass over the houses over the houses. 239. Gulshana House Girl Naway Bawar 22-4- Local norms should be Contractor/labor NTDC should bind the Killi 08 honored should respect the contractor to honor the local local norms norms. 240. Arbaza House-Wife Naway Bawar 22-4- Line should not pass Line should be NTDC should avoid Killi 08 over the houses avoided to pass distribution lines to pass over the houses over the houses.

IMPLEMENTATION SCHEDULE

2007 2008 2009 2010 2011 2012 Task Name J FMAMJ JASONDJ FMAMJ JASONDJ FMAMJ J ASONDJ FMAMJ JASONDJ FMAMJ JASONDJFMAMJ J ASONDJ FMA Tranche 1 13 Extension Sub Projects Contract Award

Delivery of Equipment x x x i d n e p p A Construction and Erection Testing and Commissioning Other 6 Sub Projects Contract Award Construction and Erection Delivery of Equipment Testing and Commissioning Tranche 2 Preparation of subprojects Submission of Sub Projects for Approval (PFR) ADB's PFR Processing Contract Award Construction and Erection DeliveryTesting andof Equipment Commissioning Tranche 3 (indicative) Preparation of subprojects Submission of Sub Projects for Approval (PFR) ADB's PFR Processing Contract Award Construction and Erection DeliveryTesting andof Equipment Commissioning Tranche 4 (indicative) Preparation of subprojects Submission of Sub Projects for Approval (PFR) ADB's PFR Processing Contract Award Construction and Erection DeliveryTesting andof Equipment Commissioning

Appendix 5 105

106 Appendix6

FRUIT AND WOOD TREES LIKELY TO BE AFFECTED BY 30M ROW

Angle TL Reach Name of Village / Affected Fruit Trees (No.) Affected Wood Trees (No.) Total Marker (Tower Nos.) Hamlet Almond Berri Total Kikar / Shisham Poplar / Willow Total Affected Trees No. From To (Trees) (Zizphus (Fruit) Toot (Sisso) Eucallypts / Other (Wood) ) (No.) Section - A: Punjab Province - Sub-section A.1: Dera Ghazi Khan District (DGK): 28 29 Basti Shikar Khan - 2 2 1 - - - 1 3 AM 007 29 30 Basti Shikar Khan - 2 2 2 - - - 2 4 54 55 Rajhani Village - 3 3 3 - - - 3 6 AM 010 55 56 Rajhani Village - 3 3 1 - - - 1 4 (AM 011) 62 63 Gamuli (Choti Bala Road) - 7 7 - 2 - - 2 9 63 64 Gamuli (Choti Bala Road) - 3 3 2 - - - 2 5 (AM 012) 64 65 Gamuli (Choti Bala Road) - 4 4 1 1 - - 2 6 Sub-total (a): Punjab - DGK: 0 24 24 10 3 0 0 13 37 Section - B: Baluchistan Province:

Sub-section - B.1: Bar Khan District (Baluchistan): 197 198 Basti Kamdan (Bawata) - 1 1 1 1 - 1 3 4 198 199 Basti Kamdan (Bawata) - - 0 1 - - - 1 1 199 200 Pailia Thal (Bawata) - 1 1 - - - - 0 1 200 201 Pailia Thal (Bawata) - 1 1 2 1 - 1 4 5 AM 050 201 202 Pailia Thal (Bawata) - - 0 1 1 - - 2 2 202 203 Sarpa Village - - 0 1 1 - - 2 2 204 205 Mir Hamadani Village - - 0 2 - 1 - 3 3 205 206 Mir Hamadani Village - 1 1 - 1 3 - 4 5 206 207 Mir Hamadani Village - 2 2 - - - - 0 2 AM 051 207 208 Basti Kaurri (Rakni) - - 0 - - 2 - 2 2 208 209 Basti Kaurri (Rakni) - - 0 2 1 4 - 7 7 209 210 Basti Kaurri (Rakni) - - 0 1 2 3 - 6 6 210 211 Basti Kaurri (Rakni) - - 0 3 1 - - 4 4 AM 052 211 212 Basti Kaurri (Rakni) - - 0 4 - - - 4 4 AM 053 212 213 Basti Kaurri (Rakni) - - 0 2 1 4 - 7 7 213 214 Basti Kaurri (Rakni) - - 0 3 - - 8 8 5 214 215 Basti Kaurri (Rakni) - - 0 2 - 5 - 7 7

Angle TL Reach Name of Village / Affected Fruit Trees (No.) Affected Wood Trees (No.) Total Marker (Tower Nos.) Hamlet Almond Berri Total Kikar / Shisham Poplar / Willow Total Affected Trees No. From To (Trees) (Zizphus (Fruit) Toot (Sisso) Eucallypts / Other (Wood) ) (No.) 215 216 Basti Kaurri (Rakni) - - 0 2 - - - 2 2 216 217 Basti Kaurri (Rakni) - - 0 3 - - - 3 3 AM 054 217 218 Basti Kaurri (Rakni) - - 0 1 - 4 - 5 5 218 219 Basti Kaurri (Rakni) - - 0 1 2 - - 3 3 (AM 55) 238 239 Deh Bhebani 1 - 1 2 - 3 - 5 6 239 240 Deh Bhebani 2 - 2 1 - 2 - 3 5 286 287 Rarkan Village 3 - 3 0 1 1 - 2 5 AM 065 287 288 Rarkan Village 4 - 4 0 2 - - 2 6 288 289 Rarkan Village 5 - 5 1 - - - 1 6 AM 066 290 291 Rarkan Village - - 0 0 - - - 0 0 293 294 Rarkan Village - - 0 1 - - - 1 1 294 295 Rarkan Village - - 0 0 - - - 0 0 295 296 Rarkan Village - - 0 1 - - - 1 1 300 301 Rarkan Village - - 0 0 - - - 0 0 301 302 Rarkan Village - - 0 0 - - - 0 0 Sub-total (b.1): Bar Khan (Bal.): 15 6 21 38 15 32 7 92 113 Sub-section B.2: Musakhal District (Baluchistan): 323 324 Rarrasham - - 0 - - - - 0 0 (AM 068) 324 325 Rarrasham - - 0 1 - - - 1 1 (AM 070) 346 347 Gidar Daag - 4 4 - 1 - 4 5 9 347 348 Gidar Daag - 7 7 - - - 1 8 1 (AM 071) 348 349 Gidar Daag - 5 5 1 - - 1 2 7 Sub-total (b.2): Musa Khel (Bal.): 0 16 16 2 1 0 6 9 25 Sub-section B.3: Loralai District (Baluchistan): (AM 085) 486 487 Mekhtar Village - - 0 1 - 2 6 9 9 487 488 Mekhtar Village 4 - 4 - - - 2 2 6 Appendix 6 488 489 Mekhtar Village 5 - 5 - - - - 0 5 489 490 Mekhtar Village 2 - 2 - 2 - - 2 4 (AM 086) 490 491 Mekhtar Village - - 0 - - - - 0 0

(AM 087) 501 502 Indah Village 2 3 5 - - - - 0 5 107

108 Appendix6

Angle TL Reach Name of Village / Affected Fruit Trees (No.) Affected Wood Trees (No.) Total Marker (Tower Nos.) Hamlet Almond Berri Total Kikar / Shisham Poplar / Willow Total Affected Trees No. From To (Trees) (Zizphus (Fruit) Toot (Sisso) Eucallypts / Other (Wood) ) (No.)

502 503 Indah Village 4 - 4 - - - - 0 4 (AM 088) 503 504 Indah Village 3 - 3 - - - - 0 3 508 509 Torat Thana Village 4 1 5 - - - - 0 5 509 510 Torat Thana Village 4 2 6 - - 3 3 6 12 (AM 089) 510 511 Torat Thana Village 5 1 6 - - 4 2 6 12 (AM 093) 543 544 Gharra Village (Sehan) - 2 2 2 1 3 - 6 8 544 545 Gharra Village (Sehan) 2 - 2 3 - 2 - 5 7 (AM 094) 545 546 Gharra Village (Sehan) 4 - 4 - 2 6 - 8 12 AM 105 694 695 Shabozai Village 2 - 2 1 3 - - 4 6 AM 106 695 696 Shabozai Village 6 - 6 - - 2 - 2 8 696 697 Shabozai Village 8 - 8 2 2 - - 4 12 AM 107 697 698 Shabozai Village 6 - 6 - 1 - 2 3 9 708 709 Masood Killi 5 - 5 3 - - 1 4 9 AM 109 710 711 Masood Killi 6 - 6 1 - - - 1 7 711 712 Masood Killi 6 - 6 - - 1 - 1 7 AM 110 712 713 Masood Killi 4 - 4 - - - 1 1 5 713 714 Masood Killi - - 0 1 - - - 1 1 (AM 113) 721 722 Tattai Bala Killi - - 0 2 - 1 - 3 3 722 723 Tattai Bala Killi - - 0 1 2 - - 3 3 724 725 Tattai Bala Killi - - 0 2 - - - 2 2 725 726 Tattai Bala Killi - - 0 - - 2 2 4 4 (AM 116) 740 741 Naway Bawar Killi - - 0 - 1 1 - 2 2 741 742 Naway Bawar Killi - - 0 - - - 2 2 2 742 743 Naway Bawar Killi - - 0 - - 2 3 3 1 743 LP Naway Bawar Killi - - 0 - 1 3 - 4 4 LP - GS LP (end) GS/Loralai Naway Bawar Killi - - 0 - - 1 2 2 1 Sub-total (b.3): Loralai (Bal.): 82 9 91 19 15 33 23 90 181 Sub-total (b): Baluchistan: 97 31 128 59 31 65 36 191 319 Total (Subproject): 97 55 152 69 34 65 36 204 356

Angle TL Reach Name of Village / Affected Fruit Trees (No.) Affected Wood Trees (No.) Total Marker (Tower Nos.) Hamlet Almond Berri Total Kikar / Shisham Poplar / Willow Total Affected Trees No. From To (Trees) (Zizphus (Fruit) Toot (Sisso) Eucallypts / Other (Wood) ) (No.) Percentages - Fruit & Wood Trees: 63.82 36.18 100.00 33.82 16.67 31.86 17.65 100.00 - Percentages - Fruit Trees Versus Wood Trees: 42.70 57.30 100.00 Appendix 6 109

110 Appendix7

TREES AND INFRASTRUCTURE LIKELY TO BE AFFECTED BY 30M ROW

yy

Angle Reach of the New Marker Transmission Line Number Twr-Twr HOUSE/ WATER K/ GRAVE NALA / (Angular (Tower Nos.) of Distance TREES TL SIDE GARDEN WC / TW WT/WP FLOW/ ROAD/P YARD SUMP Tower) From To Towers (m) SLOPE POND ROAD Section - A: Punjab Province - Sub-section A.1: Dera Ghazi Khan District (DGK): GS - LP GS/DGK LP (start) 4 820.00 LP T# 1 1 420.00 2-11KV 1-P 121200.00 132KV AM 001 2 3 1 329.98 341265.45 AM 002 4 5 1 320.55 561352.00 671366.00 7 8 1350.37 AM 003 8 9 1 305.63 9 10 1 318.00 10 11 1 328.00 11 12 1 314.00 12 13 1 300.00 13 14 1 319.48 1 AM 004 14 15 1 100.52 132KV 15 16 1 240.00 16 17 1 294.21 1-P AM 005 17 18 1 337.79 18 19 1 361.66

AM 006 19 20 1 346.34 20 21 1 373.00 21 22 1 345.00 22 23 1 358.00 23 24 1 358.00 24 25 1 360.00 25 26 1 336.00 26 27 1 360.00 27 28 1 350.00 28 29 1 350.16 3 1 1 AM 007 29 30 1 343.84 4 30 31 1 362.00 31 32 1 360.00 32 33 1 372.00 33 34 1 352.00 34 35 1 358.00 35 36 1 370.00 36 37 1 352.00 37 38 1 366.00 38 39 1 354.00 39 40 1 361.21 AM 008 40 41 1 340.79 41 42 1 330.00 42 43 1 338.00 11KV 43 44 1 360.61 1-T AM 008A 44 45 1 333.39 1-T 45 46 1 312.00 46 47 1 336.00 1 47 48 1 261.98 11KV 1 1-P AM 009 48 49 1 305.79 1 49 50 1 302.00 50 51 1 324.00 1 Appendix 7 111

112 Appendix7

51 52 1 316.00 1-T 52 53 1 328.00 1-T 53 54 1 328.00 54 55 1 303.65 6 1-T AM 010 55 56 1 376.35 4 1

56 57 1 356.00 1 57 58 1 348.00 1 58 59 1 376.00 59 60 1 354.00 60 61 1 376.17 11KV 1-T AM 011 61 62 1 393.83 62 63 1 280.00 9 63 64 1 290.00 5 1 64 65 1 287.51 6 1 AM 012 65 66 1 312.49 1 1-T 66 67 1 310.00 11KV 1-T 67 68 1 320.00 21-T 68 69 1 263.14 AM 013 69 70 1 288.86 1-T 70 71 1 328.00 71 72 1 326.00 11-T 72 73 1 360.00 1 73 74 1 332.00 74 75 1 320.84 AM 014 75 76 1 331.16 1 76 77 1 300.00 77 78 1 270.00 78 79 1 320.00 WP 1 79 80 1 316.00 80 81 1 301.93

AM 015 81 82 1 306.07 82 83 1 342.00 83 84 1 354.00 84 85 1 370.95 11KV AM 016 85 86 1 189.05 1-P 86 87 1 140.00 132KV 87 88 1 197.78 11KV AM 017 88 89 1 292.22 1 89 90 1 504.73 1 AM 018 90 91 1 339.27 1 91 92 1 256.00 92 93 1 388.00 1 93 94 1 372.00 94 95 1 358.00 1 95 96 1 368.91 1 AM 019 96 97 1 443.09 1 97 98 1 360.00 1 98 99 1 320.00 1-P 99 100 1 333.23 AM 020 100 101 1 370.77 2 101 102 1 260.00 102 103 1 256.00 1 103 104 1 260.00 104 105 1 354.00 2 105 106 1 336.00 106 107 1 380.00 2 107 108 1 171.84 AM 021 108 109 1 156.67 AM 022 109 110 1 377.49 1 110 111 1 361.02 1 Appendix 7 113

114 Appendix7

AM 023 111 112 1 312.98 1 112 113 1 281.06 AM 024 113 114 1 348.94 114 115 1 315.00 115 116 1 355.00

116 117 1 364.00 117 118 1 416.00 1-P 118 119 1 168.00 119 120 1 253.45 1-P AM 025 120 121 1 286.55 1 121 122 1 227.52 11-P AM 026 122 123 1 291.48 123 124 1 355.00 124 125 1 308.00 11KV 125 126 1 338.00 126 127 1 352.00 127 128 1 333.39 1-T AM 027 128 129 1 279.77 129 130 1 350.00 2-T 130 131 1 368.00 131 132 1 362.00 132 133 1 522.00 2 133 134 1 232.51 AM 028 134 135 1 65.49 135 136 1 240.40 AM 029 136 137 1 375.65 AM 030 137 138 1 337.23 AM 031 138 139 1 384.64 1 AM 032 139 140 1 283.08 AM 033 140 141 1 215.66

AM 034 141 142 1 394.34 AM 035 142 143 1 320.00 1 AM 036 143 144 1 254.00 144 145 1 206.00 145 146 1 300.00 AM 037 146 147 1 200.00 147 148 1 340.00 148 149 1 136.00 149 150 1 164.00 150 151 1 374.00 151 152 1 405.91 AM 038 152 153 1 184.09 153 154 1 449.42 AM 039 154 155 1 270.58 155 156 1 257.69 AM 040 156 157 1 448.31 157 158 1 278.30 AM 041 158 159 1 107.70 159 160 1 464.00 160 161 1 461.15 AM 042 161 162 1 134.85 162 163 1 276.00 11KV 163 164 1 458.00 AM 043 164 165 1 150.00 165 166 1 310.00 1 166 167 1 265.87 AM 044 167 168 1 492.13 168 169 1 438.00 WP 1-P 169 170 1 384.34 WP G.Y AM 045 170 171 1 389.66 Appendix 7 115

116 Appendix7

171 172 1 260.00 172 173 1 343.94 AM 046 173 174 1 252.06 174 175 1 404.00 175 176 1 250.00 1-P

176 177 1 302.00 177 178 1 456.12 AM 047 178 179 1 191.88 TWWP 1-P 179 180 1 288.00 WP 180 181 1 312.00 181 182 1 314.00 182 183 1 395.02 AM 048 183 184 1 78.98 184 185 1 426.00 185 186 1 290.00 186 187 1 276.00 187 188 1 378.00 1+ 188 189 1 352.00 189 190 1 374.00 1+ 190 191 1 210.00 191 192 1 294.00 192 193 1 362.00 1+ 193 194 1 150.00 Sub-total (a): Punjab - DGK: 198 ####### Section - B: Baluchistan Province: Sub-section - B.1: Bar Khan District (Baluchistan): 194 195 1 297.01 AM 049 195 196 1 262.99 11KV 196 197 1 320.00 1+ 197 198 1 326.00 4 11KV

198 199 1 328.00 1 1-T 199 200 1 346.00 1 200 201 1 362.14 5 AM 050 201 202 1 351.86 2 1 1-T 202 203 1 366.00 2 203 204 1 362.00 204 205 1 364.00 3 11KV 205 206 1 358.00 5 206 207 1 378.00 2 207 208 1 356.00 2 208 209 1 370.33 7 1 AM 051 209 210 1 365.67 6 11KV 1 210 211 1 366.00 4 1 211 212 1 356.00 4 1 212 213 1 352.25 7 11KV 1 TW AM 052 213 214 1 367.10 8 11KV AM 053 214 215 1 338.65 7 2-11KV 1-T 215 216 1 288.00 2 216 217 1 330.00 3 SUMP 217 218 1 270.00 5 2-11KV 1-T 218 219 1 294.01 3 1-T AM 054 219 220 1 299.99 220 221 1 354.00 221 222 1 362.00 222 223 1 330.00 223 224 1 338.00 224 225 1 346.00 225 226 1 374.00 1 226 227 1 296.00 11KV 227 228 1 364.00 228 229 1 366.00 Appendix 7 117

118 Appendix7

229 230 1 346.00 1 230 231 1 348.00 231 232 1 360.00 232 233 1 286.00 11KV 233 234 1 342.00 11KV

234 235 1 348.00 235 236 1 338.00 1 TW 236 237 1 356.80 AM 055 237 238 1 349.03 11KV 238 239 1 356.00 6 239 240 1 366.00 5 1 240 241 1 344.00 241 242 1 344.00 1 242 243 1 319.83 1-T AM 056 243 244 1 302.12 11KV 244 245 1 323.42 AM 057 245 246 1 282.58 1-P 246 247 1 340.00 247 248 1 314.00 11KV 248 249 1 320.00 11KV 249 250 1 310.00 250 251 1 378.00 11-P 251 252 1 332.00 252 253 1 390.00 253 254 1 247.27 AM 058 254 255 1 351.74 AM 059 255 256 1 374.99 256 257 1 340.00 257 258 1 190.00 258 259 1 462.00 259 260 1 236.00

260 261 1 338.80 AM 060 261 262 1 416.20 262 263 1 240.00 263 264 1 258.00 264 265 1 247.94 AM 061 265 266 1 346.06 266 267 1 334.00 267 268 1 354.00 268 269 1 272.00 269 270 1 228.21 AM 062 270 271 1 371.79 1 271 272 1 260.00 11KV 272 273 1 226.34 AM 063 273 274 1 397.66 274 275 1 322.00 275 276 1 316.00 276 277 1 268.00 11KV 277 278 1 356.00 278 279 1 362.00 279 280 1 348.00 11KV 280 281 1 352.00 281 282 1 264.00 2-11KV 282 283 1 330.64 11KV AM 064 283 284 1 253.36 2-11KV 1-P 284 285 1 292.00 11KV 285 286 1 328.00 1-P 286 287 1 374.89 5 GARDEN AM 065 287 288 1 371.11 6 1-P 288 289 1 248.00 6 11-KV 289 290 1 350.79 GARDEN Appendix 7 119

120 Appendix7

AM 066 290 291 1 300.00 2-T 291 292 1 324.00 WELL 2 292 293 1 346.00 WELL 293 294 1 346.00 1 1-T 294 295 1 360.00 WELL 1 1-T 295 296 1 366.00 1 11KV 1 296 297 1 300.00 11KV 1-P 297 298 1 344.00 298 299 1 348.00 12-T 299 300 1 316.00 11KV 3 1-WF 1-T 300 301 1 364.00 2-WF 301 302 1 368.00 WF 302 303 1 332.00 WF 303 304 1 308.00 304 305 1 402.00 WF 305 306 1 329.24 2-WF AM 067 306 307 1 386.76 WF 1-T 307 308 1 344.00 308 309 1 320.00 309 310 1 362.00 310 311 1 368.00 1 311 312 1 330.00 1-T 312 313 1 358.00 313 314 1 332.00 314 315 1 354.00 315 316 1 266.00 11KV 316 317 1 400.00 317 318 1 332.00 318 319 1 276.00 1 319 320 1 330.00 1-T

320 321 1 280.00 11KV 1 321 322 1 324.00 1-T 322 323 1 336.00 Sub-total (b.1): Bar Khan (Baln.): 129 42,784 Sub-section B.2: Musakhal District (Baluchistan): 323 324 1 346.00 1-T 324 325 1 310.11 1 AM 068 325 326 1 417.89 326 327 1 224.00 327 328 1 254.00 328 329 1 396.00 329 330 1 332.00 330 331 1 338.00 331 332 1 378.00 332 333 1 342.00 333 334 1 364.00 334 335 1 340.00 335 336 1 390.00 336 337 1 148.00 337 338 1 412.00 1 338 339 1 273.03 AM 069 339 340 1 170.97 340 341 1 258.00 1-T 341 342 1 309.75 1-T AM 070 342 343 1 414.25 343 344 1 304.00 344 345 1 278.00 345 346 1 308.00 1 346 347 1 302.00 9 347 348 1 386.00 8 Appendix 7 121

122 Appendix7

347 348 1 386.00 8 348 349 1 260.00 7 1 349 350 1 202.00 11KV 350 351 1 390.21 AM 071 351 352 1 331.79

352 353 1 388.00 353 354 1 266.00 354 355 1 284.75 AM 072 355 356 1 311.25 11KV 356 357 1 392.00 3-WF 357 358 1 220.00 358 359 1 422.00 11KV 1 1-P 359 360 1 418.00 1-P 360 361 1 242.00 361 362 1 444.00 11KV 1 1-P 362 363 1 286.00 363 364 1 350.00 364 365 1 432.00 365 366 1 422.00 1 366 367 1 240.00 1 367 368 1 173.35 AM 073 368 369 1 362.65 2 369 370 1 288.00 2 370 371 1 319.41 Am 074 371 372 1 336.59 372 373 1 330.00 373 374 1 346.00 374 375 1 356.00 375 376 1 486.00 12-WF 376 377 1 352.00 2-WF

377 378 1 266.77 2-WF AM 075 378 379 1 333.48 11KV 1 1-P AM 076 379 380 1 439.75 380 381 1 232.00 381 382 1 256.00 WF 382 383 1 342.00 383 384 1 356.00 1 384 385 1 340.00 385 386 1 434.00 1 386 387 1 250.00 1 387 388 1 328.00 388 389 1 218.00 WF 389 390 1 404.00 11KV 1 390 391 1 326.00 391 392 1 404.00 12-WF 392 393 1 326.00 1 393 394 1 350.00 394 395 1 380.00 1 395 396 1 348.00 Sub-total (b.2): Musa Khel (Baln.) 73 23,982 Sub-section B.3: Loralai District (Baluchistan): 396 397 1 408.11 AM 077 397 398 1 259.89 398 399 1 300.00 399 400 1 414.18 1 AM 078 400 401 1 145.82 401 402 1 358.00 402 403 1 372.00 11KV 1-P 403 404 1 308.00 1WF 404 405 1 294.00 3-WF 405 406 1 364.00 WF Appendix 7 123

124 Appendix7

406 407 1 370.00 1WF 407 408 1 360.00 408 409 1 358.00 409 410 1 372.00 410 411 1 358.00 UCR

411 412 1 372.00 412 413 1 358.00 11KV 2-WF 413 414 1 314.00 414 415 1 344.00 WF 415 416 1 346.00 4-WF 416 417 1 258.00 1 417 418 1 376.00 WF 418 419 1 356.00 WF 419 420 1 346.00 WF 420 421 1 370.00 421 422 1 314.00 422 423 1 410.00 1 423 424 1 314.00 424 425 1 336.00 425 426 1 260.00 11KV 426 427 1 314.00 427 428 1 324.00 1-P 428 429 1 244.00 429 430 1 348.00 WF 430 431 1 354.69 1 AM 079 431 432 1 367.31 432 433 1 334.00 433 434 1 398.42 WF AM 080 434 435 1 377.58 1 435 436 1 260.00

436 437 1 254.00 437 438 1 314.00 1 438 439 1 420.00 WF 439 440 1 280.00 440 441 1 330.00 441 442 1 356.00 442 443 1 356.00 443 444 1 356.00 444 445 1 304.88 AM 081 445 446 1 279.12 446 447 1 312.00 1 447 448 1 304.00 1 448 449 1 390.00 449 450 1 274.00 450 451 1 304.00 WF 451 452 1 370.00 452 453 1 320.00 453 454 1 314.00 454 455 1 374.00 WF 455 456 1 326.00 456 457 1 330.00 457 458 1 392.00 458 459 1 272.00 459 460 1 291.71 AM 082 460 461 1 342.29 1 461 462 1 336.00 1WF 462 463 1 366.00 463 464 1 270.00 464 465 1 348.00 1 Appendix 7 125

126 Appendix7

465 466 1 356.00 466 467 1 368.00 11KV WF UCR 467 468 1 362.00 468 469 1 360.00 469 470 1 366.00

470 471 1 356.00 1 471 472 1 228.00 472 473 1 464.00 473 474 1 334.00 1-T 474 475 1 308.00 WF 475 476 1 382.37 1 AM 083 476 477 1 233.23 1 477 478 1 324.00 478 479 1 404.00 4 479 480 1 107.98 132KV AM 084 480 481 1 368.02 2 481 482 1 314.00 1 482 483 1 253.40 1 AM 085 483 484 1 278.60 1 484 485 1 324.00 WF 485 486 1 340.00 2-WF 486 487 1 270.00 9 WF 487 488 1 330.00 6 1 488 489 1 364.00 5 2WF 489 490 1 354.00 4 WF 490 491 1 340.00 491 492 1 266.00 GARDEN WF 1-P 492 493 1 278.54 11KV AM 086 493 494 1 299.46 1 494 495 1 310.00

495 496 1 268.00 11KV 496 497 1 350.00 11KV 497 498 1 348.00 11KV 498 499 1 291.16 AM 087 499 500 1 320.84 GARDEN 500 501 1 366.00 501 502 1 336.00 5 502 503 1 338.00 4 503 504 1 366.76 3 SIDE SLOP AM 088 504 505 1 359.24 505 506 1 320.00 GARDEN 506 507 1 300.00 SIDE SLOP 507 508 1 300.00 508 509 1 340.00 5 GARDEN 509 510 1 350.00 12 1 510 511 1 348.00 12 GARDEN 511 512 1 382.00 11KV 512 513 1 314.04 AM 089 513 514 1 295.96 514 515 1 327.73 12-WF AM 090 515 516 1 316.27 1WF 516 517 1 380.00 WF 517 518 1 306.00 WF UCR 518 519 1 244.00 WF 519 520 1 277.67 WF AM 091 520 521 1 372.36 WF UCR 521 522 1 340.00 522 523 1 300.00 523 524 1 310.00 Appendix 7 127

128 Appendix7

524 525 1 290.00 1 525 526 1 330.00 3 526 527 1 316.00 WF 527 528 1 334.00 WF 528 529 1 300.00 1

529 530 1 320.00 1 530 531 1 346.00 4 531 532 1 346.00 532 533 1 372.00 4 533 534 1 315.15 AM 092 534 535 1 336.85 1 535 536 1 358.00 1 536 537 1 328.00 537 538 1 318.00 538 539 1 320.00 1 539 540 1 202.11 AM 093 540 541 1 217.89 541 542 1 360.00 1WF 542 543 1 364.00 1 543 544 1 320.00 8 544 545 1 328.00 7 545 546 1 306.00 12 1-T 546 547 1 277.58 1-T AM 094 547 548 1 262.42 1 WF 548 549 1 314.00 549 550 1 314.00 1 550 551 1 314.00 551 552 1 315.99 WF AM 095 552 553 1 284.01 553 554 1 300.00 554 555 1 292.00

555 556 1 318.00 1-T 556 557 1 277.45 AM 096 557 558 1 224.55 558 559 1 342.00 WC 559 560 1 266.00 G.Y 1-T 560 561 1 234.00 1-T,UCR 561 562 1 246.00 562 563 1 352.00 1 563 564 1 281.72 AM 097 564 565 1 298.28 1 565 566 1 326.00 1 566 567 1 342.00 3 567 568 1 344.00 2 568 569 1 276.00 1 569 570 1 316.00 1 570 571 1 336.00 571 572 1 326.00 1 572 573 1 302.00 573 574 1 328.00 WF 574 575 1 312.00 575 576 1 310.00 576 577 1 350.00 1 577 578 1 348.00 578 579 1 348.00 579 580 1 348.00 580 581 1 318.00 581 582 1 338.00 582 583 1 306.00 1-P 583 584 1 360.00 1 584 585 1 360.00 585 586 1 340.00 Appendix 7 129

130 Appendix7

586 587 1 364.00 1 587 588 1 352.00 588 589 1 292.00 589 590 1 350.00 GARDEN 590 591 1 347.39

AM 098 591 592 1 268.61 11KV 592 593 1 344.00 1-P 593 594 1 358.00 594 595 1 344.00 595 596 1 354.00 1 596 597 1 364.00 597 598 1 336.00 1-P 598 599 1 368.00 599 600 1 362.00 WF 600 601 1 336.00 601 602 1 346.00 602 603 1 306.00 11KV 603 604 1 322.00 604 605 1 321.81 AM 099 605 606 1 340.19 606 607 1 364.00 607 608 1 364.00 608 609 1 354.00 609 610 1 352.00 610 611 1 364.00 611 612 1 353.48 AM 100 612 613 1 266.52 2 613 614 1 338.00 1 614 615 1 338.00 1-P 615 616 1 262.00 11KV 616 617 1 328.00

617 618 1 268.00 618 619 1 370.00 619 620 1 356.00 WF 620 621 1 342.00 621 622 1 318.00 622 623 1 300.00 623 624 1 366.00 WF 624 625 1 340.00 625 626 1 384.00 1 626 627 1 344.00 627 628 1 346.00 628 629 1 370.00 11KV 1 629 630 1 334.00 630 631 1 358.00 631 632 1 346.00 632 633 1 292.00 LT 1-P 633 634 1 310.00 LT 634 635 1 320.00 635 636 1 324.00 1-P 636 637 1 286.00 2-11KV 637 638 1 254.00 11KV GARDEN 638 639 1 332.00 639 640 1 298.00 1-P 640 641 1 352.00 641 642 1 358.00 642 643 1 360.00 643 644 1 372.00 644 645 1 358.00 645 646 1 368.00 1-P 646 647 1 362.00 Appendix 7 131

132 Appendix7

647 648 1 340.00 648 649 1 348.00 1-P 649 650 1 318.00 650 651 1 318.68 WF AM 101 651 652 1 309.32 2-WF

652 653 1 257.71 WF AM 101A 653 654 1 244.29 G.Y 654 655 1 250.00 655 656 1 334.71 2-P AM 102 656 657 1 291.96 657 658 1 326.00 658 659 1 266.00 659 660 1 352.00 11KV 660 661 1 346.00 661 662 1 366.00 662 663 1 334.00 11KV 663 664 1 328.00 664 665 1 338.00 665 666 1 352.47 WC AM 103 666 667 1 347.54 667 668 1 362.00 LT 668 669 1 316.00 LT 669 670 1 366.00 1 670 671 1 360.00 671 672 1 368.00 11KV 672 673 1 352.00 673 674 1 354.00 674 675 1 344.00 675 676 1 337.96 AM 104 676 677 1 344.04 1 677 678 1 362.00 WF

678 679 1 356.00 679 680 1 338.00 1 680 681 1 346.00 1 681 682 1 332.00 682 683 1 344.00 WF 683 684 1 354.00 684 685 1 374.00 1 685 686 1 348.00 686 687 1 356.00 687 688 1 374.00 688 689 1 342.00 689 690 1 322.00 690 691 1 324.00 691 692 1 340.00 692 693 1 328.00 WF 693 694 1 334.15 1 AM 105 694 695 1 323.00 6 AM 106 695 696 1 290.85 8 1 696 697 1 319.93 12 11KV GARDEN AM 107 697 698 1 346.07 9 11KV 698 699 1 352.00 WF 699 700 1 346.00 700 701 1 328.00 LT 701 702 1 332.00 11KV 702 703 1 337.14 2 AM 108 703 704 1 350.86 704 705 1 346.00 705 706 1 356.00 11KV WF 1-P 706 707 1 342.00 3 707 708 1 332.00 1 Appendix 7 133

134 Appendix7

708 709 1 332.00 9 1 709 710 1 357.98 11KV AM 109 710 711 1 262.07 7 711 712 1 213.84 7 GARDEN AM 110 712 713 1 382.16 5 1

713 714 1 334.32 1 AM 111 714 715 1 324.51 AM 112 715 716 1 345.12 716 717 1 370.00 717 718 1 340.00 718 719 1 338.05 GARDEN AM 113 719 720 1 369.96 1-P 720 721 1 360.00 721 722 1 370.00 3 11KV 722 723 1 336.00 3 11KV 723 724 1 360.00 724 725 1 306.00 2 11KV 725 726 1 360.00 4 726 727 1 344.00 727 728 1 320.00 728 729 1 328.00 729 730 1 350.00 1 730 731 1 350.00 1 731 732 1 310.25 AM 114 732 733 1 303.75 733 734 1 332.00 734 735 1 328.00 735 736 1 300.20 AM 115 736 737 1 317.80 4-WF 737 738 1 288.00 7-WF 738 739 1 285.53 2-11KV WF AM 116 739 740 1 314.47 740 741 1 326.00 2 1 741 742 1 324.00 2 742 743 1 270.00 3 11KV 743 LP 1359.28 4 WC 1-P LP - GS LP (end) GS/Loralai 7 1,420.00 2 Sub-total (b.3): Loralai: 355 115,742 Sub-total (b): Balochistan: 557 182,507 Total (Subproject): 755 245,013 Overall Percentage 100.00 100.00 Appendix 8 135

PHOTOGRAPHS OF PROPOSED TRANSMISSION LINE SUBPROJECT

General Topography: Line Route

Tower location

136 Appendix 8

Tower Location

Water logged portion of the line route Appendix 8 137

Orchard

Sparse vegetation along portion of line route Orchards along Line route

138 Appendix 8

Small check dam along line route

Orchards along line route Appendix 8 139

Tower location

Tower location, Hilly portion

140 Appendix 8

.

Road crossing

Annexure 141

EMISSIONS STANDARDS

142 Annexure Annexure 143

NTDC Standards for Transformer Noise

NTDC specifications for auto (Power) transformers (220 kV and 500 kV) require that noise level be as per IEC 551 which simplistically interpreted results in a permissible noise level of 80 db (this is subject to measurement conditions laid down in IEC 551).