Transport for NSW Beaches Link and Connection Environmental Impact Statement

Artarmon temporary construction support sites This fact sheet outlines the proposed construction # and operational impacts in your local area, as The Beaches Link and Gore Hill outlined in the EIS. We encourage you to visit «! Freeway Connection Environmental our interactive portal for more information, T1 and Northern rail line Impact Statement (EIS) is now on our interactive map, videos and to view the full Artarmon Flat Rock Creek Hampden Road public exhibition until midnightRe serve EIS chapters. sey Road MondayJer 1 March 2021.

Thomson Barton Road Park Cleland construction support site Park # «! T1 North Shore and Northern rail line

Artarmon Flat Rock Creek Hampden Road Reserve Goresey Ro Hillad Freeway Jer

Gore Hill Freeway median Thomson Barton Road construction support site Lane CovePark Cleland construction supportTunnel site entrance Park

Lambs Road Punch Street Gore Hill Freeway Punch Street Dickson Avenue Hesky construction support site Lane Gore Hill Freeway median construction support site construction support site Cleg Street Tunnel entrance

Lambs Road Punch Street Punch Street Dickson Avenue Hesky construction support site Lane construction support site P Cleg Street a c Naremburn ifi c Reserve Road Park H Dickson Avenue i P g Dickson Avenue a h construction support site c w Naremburn ifi a c Reserve Road Park H y Dickson Avenue ig Dickson Avenue h construction support site w a y

0 200 m 0 200 m

Construction footprint Surface Work TemporaryConstruction construction footprint Cut and cover Surface Work support site TunnelTemporary (underground) construction Cut and cover Constructionsupport site site buildings Tunnel (underground) Construction site buildings

Beaches Link and Gore Hill Freeway Connection EIS December 2020 Punch Street

We will be setting up a temporary construction • excavating the tunnel access support site at Punch Street within the Artarmon • tunnelling, including the ramp tunnels industrial area. We will use this site to support the towards Northbridge excavation and fitout of the tunnels east towards • treatment of wastewater from Northbridge, the construction of the Beaches tunnelling activities Link cut and cover and trough structures and the • storing, handling and transporting materials, permanent motorway facilities for Beaches Link. including tunnel spoil Our key activities include: • tunnel fitout and finishing work • removing existing structures • building the permanent motorway facilities • utility work • testing and commissioning of the tunnel • building and operating temporary site facilities, • rehabilitating the site. including an acoustic shed, temporary noise barrier, wastewater treatment facility, air intake, and staff offices and amenities

Punch Street temporary construction support site

Temporary relocation of pedestrian and cyclist path

Temporary heavy vehicle access to Gore Hill Freeway

NAREMBURN Gore Hill Freeway

LaydownWorkshop

T1 North Shore and Western Line and T9 Northern Line

Acoustic Francis Street shed Punch Street

Site o‚ce

Motorway facilities and Lambs Road ventilation outlet will be built after tunnel excavation is completed and acoustic reet shed is removed St g Cle Access from Gore Hill Freeway via Reserve Road ARTARMON 0 50 m

Legend Construction footprint Surface Work Temporary site access Wastewater treatment plant Temporary construction Cut and cover and Site access - in Indicative temporary noise barrier support site trough structures Site access - out Temporary pedestrian and cyclist Tunnel (underground) Access decline (underground) path diversion Ventilation outlet Construction site buildings Ventilation tunnel

Beaches Link and Gore Hill Freeway Connection EIS December 2020 Punch Street temporary construction support site indicative construction program

Construction activity 2023 2024 2025 2026

Early works and site establishment

Excavation of tunnel access decline

Tunnel construction

Tunnel fitout

Construction of operational facilities

Testing, commissioning and site rehabilitation

Duration You may see us in this area for up to four years as we setup, carry out our construction work, then demobilise the site and rehabilitate it for future use. We will be building permanent infrastructure to support the operation of Beaches Link at Gore Hill Freeway, including motorway facilities and a ventilation outlet. The construction peak at this site will be when we are tunnelling and will be up to two years.

Hours of work We will be tunnelling up to 24 hours a day, seven days a week. Once we are tunnelling, the majority of the work will take place underground and activity on the surface will reduce. Based on our planned tunnelling rate and depth we expect the impact from tunnelling to be minimal for residents as we will only be excavating directly under each property for about one week, and will generally be quite deep. When tunnelling, our work will be as deep as about 42 metres (13 storeys) at Artarmon. The majority of the tunnelling work on the surface at this site takes place inside the acoustic shed, which manages the potential impacts of noise, dust and light spill. These sheds are closed at night to further reduce noise. There may be occasional deliveries and some light vehicle movements outside of standard construction hours. General site activities and spoil transport will only take place during standard construction hours. For any work outside the standard construction hours, the community will be notified in advance.

Traffic/vehicle Access into the site will be via Cleg Street and out of the site via movements Punch Street. An alternative heavy vehicle exit will be constructed to connect directly to the Gore Hill Freeway heading west to reduce heavy vehicles on local streets. At our construction peak, there will be around 370 heavy vehicle movements and 580 light vehicle movements per day (a vehicle travelling in and out of the site is counted as two movements). The combined activity for all Artarmon temporary sites will increase traffic in the area by 7.5 per cent during peak construction. Overall, this is a small increase to current traffic volumes.

Beaches Link and Gore Hill Freeway Connection EIS December 2020 Dickson Avenue We will be setting up a temporary construction For the Gore Hill Freeway Connection support site at Dickson Avenue within the construction work: Artarmon industrial area to support construction • the site will be used for equipment laydown, of Beaches Link and Gore Hill Freeway Connection. car parking for construction workers and Our key activities include: temporary site office buildings to support surface work • setting up the site by removing existing structures • once most of the surface and tunnelling work has been completed, the site will be • building and operating temporary site rearranged to build the off ramp structures, facilities, including laydown areas, staff surface work onto Reserve Road, the offices and amenities and car parking. motorway control centre and the tunnel For the Beaches Link construction work: support facility. • the site will be used to support tunnelling activities at the Punch Street construction site and construction of operational facilities.

Dickson Avenue temporary construction support site

Reserve Road Bridge modification

Gore Hill Freeway

Storage Laydown Site Laydown oce

Storage and amenities Construction of Site oce Beaches Link motorway control centre

Construction of Beaches Link tunnel support facilities

Curry Lane

Surface work to Waltham Street widen Reserve Road

Intersection work to accomodate new exit ramp from the Beaches Link Tunnel Taylor Lane

Reserve Road

Linemarking along ARTARMON Dickson Avenue Dickson Avenue

0 50 m

Legend Construction footprint Surface Work Beaches Link construction Surface connection Temporary construction Cut and cover support site area Site access - in support site Car park Gore Hill Freeway Connection Site access - out Tunnel (underground) Temporary site access construction support site area Construction site buildings

Beaches Link and Gore Hill Freeway Connection EIS December 2020 Dickson Avenue temporary construction support site indicative construction program

Construction activity 2023 2024 2025 2026

Beaches Link construction works

Early works and site establishment

Additional tunnel support at Punch Street

Construction of operational facilities

Testing and commissioning

Gore Hill Freeway Connection construction work

Early works and site establishment

Construction of Gore Hill Freeway surface works and bridge modifications

Construction of the off ramp trough and surface works to Reserve Road

Site rehabilitation

Duration You may see us in this area for about four years as we setup, carry out our construction work, then demobilise the site and rehabilitate it for future use. We will be building permanent infrastructure to support the operation of Beaches Link at the Gore Hill Freeway, including motorway facilities and a ventilation outlet. The construction peak at this site will be when we are tunnelling and carrying out Gore Hill Freeway surface works and will be up to three years in duration.

Hours of work Our general site activities including most surface work and building the motorway control centre and tunnel support facilities will be carried out during standard construction hours. There will be some activities, such as complex surface work and utility adjustments which occur outside of standard construction hours due to site access restrictions, traffic staging and safety requirements. For any work outside the standard construction hours, the community will be notified in advance.

Traffic/vehicle Access to site will be via Dickson Avenue. movements At our construction peak, there will be around 90 heavy vehicle movements and 500 light vehicle movements per day (a vehicle travelling in and out of the site is counted as two movements). The combined activity for all Artarmon temporary sites will increase traffic in the area by 7.5 per cent during peak construction. Overall, this is a small increase to current traffic volumes.

Beaches Link and Gore Hill Freeway Connection EIS December 2020 Artarmon Barton Road We will be setting up a temporary construction Our key site features include: support site on Barton Road to support Thomson Milner Road Park • equipment laydown facilities construction of the Gore Hill Freeway Connection. • car parking for construction workers • temporary site office buildings.

Barton Road temporary construction support site

Thomson

Milner Road Park

Thomson

Milner Road ParBartonk Road Carpark and ARTARMON laydown area Butchers Lane

Reserve Road SIte oce

Reserve Road Bridge modification Barton Road

Carpark and ARTARMON laydown area Butchers Lane

Reserve Road

SIte oce Barton Road Gore Hill Freeway Carpark and ARTARMON laydown area Butchers Lane Reserve Road Reserve Road Bridge modification SIte oce

Reserve Road Gore Hill Freeway Bridge modification

ARTARMON

Gore Hill Freeway Legend Construction footprint Surface Work Site access - in Temporary site access Temporary construction Construction site buildings Site access - out Carpark support site ARTARMON

Legend Construction footprint Surface Work Site access - in Temporary site access Temporary construction Construction site buildings Site access - out Carpark support site ARTARMON

Legend Construction footprint Surface Work Site access - in Temporary site access Beaches LinkTemporary and Gore construction Hill Freeway ConnectionConstruction EIS site buildings Site access - out DecemberCarpark 2020 support site Barton Road temporary construction support site indicative construction program

Construction activity 2023 2024 2025 2026 2027

Early work and site establishment

Construction support for surface works

Site restoration and demobilisation

Duration You may see us in this area for up to four years as we setup, carry out our construction work, then demobilise the site and rehabilitate it for future use. The construction peak at this site will be when we are carrying out surface work and will be up to three years.

Hours of work Our general site activities including most surface work will be carried out during standard construction hours. There will be some activities, such as complex and constrained surface work and utility adjustments, which occur outside of standard construction hours due to site access restrictions and traffic staging requirements. For any work outside the standard construction hours, the community will be notified in advance.

Traffic/vehicle Access to site will be via Reserve Road. movements At our construction peak, there will be around 35 heavy vehicle movements and around 120 light vehicle movements per day (a vehicle travelling in and out of the site is counted as two movements). The combined activity for all Artarmon temporary sites will increase traffic in the area by 7.5 per cent during peak construction. Overall, this is a small increase to current traffic volumes.

Artist’s impression of Gore Hill Freeway Connection. Indicative only.

Beaches Link and Gore Hill Freeway Connection EIS December 2020 Artarmon Gore Hill Freeway median We will be setting up a temporary construction support site on the median above the , within the Gore Hill Freeway to support construction of the Gore Hill Freeway Connection.

Our key site features include: • equipment laydown facilities.

Gore Hill Freeway median temporary construction support site

Rimm

ingt

on Geo Stre

rg et Broughton Road e Plac

e

Site access fromfrom Exit to Gore Hill Epping Road Freeway eastbound

Exit to Gore Hill Freeway eastbound

Oces, amenities and laydown area

Gore Hill Freeway

Site access fromfrom Gore Hill Freeway ARTARMON

t ee n Str de Mar

0 50 m

Legend Construction footprint Surface Work Site access - in Temporary construction Temporary site access Site access - out support site

Beaches Link and Gore Hill Freeway Connection EIS December 2020 Gore Hill Freeway median temporary construction support site indicative construction program

Construction activity 2023 2024 2025 2026 2027

Early works and site establishment

Construction support for surface work

Site restoration and demobilisation

Duration You may see us in this area for up to four years as we setup, carry out our construction work, then demobilise the site and rehabilitate it for future use. The construction peak at this site will be when we are carrying out surface work and will be up to three years.

Hours of work Our general site activities will be carried out during standard construction hours. There may be occasional activities, such as complex surface work, utility adjustments, and oversized deliveries which occur outside of standard construction hours due to site access restrictions, traffic staging and safety requirements. For any work outside the standard construction hours, the community will be notified in advance.

Traffic/vehicle Access into the site will mainly be via the Gore Hill Freeway. A secondary movements access will be provided via Epping Road. Access out of the site will be via the Gore Hill Freeway (eastbound). At our construction peak, there will be around 10 heavy vehicle movements and 100 light vehicle movements per day (a vehicle travelling in and out of the site is counted as two movements). The combined activity for all Artarmon temporary sites will increase traffic in the area by 7.5 per cent during peak construction. Overall, this is a small increase to current traffic volumes.

Beaches Link and Gore Hill Freeway Connection EIS December 2020 How to make a submission

How to make an online submission You can post your submission to: Attention: Director, Transport Assessments 1. Visit DPIE’s Major Projects website at Planning & Assessment, Department of Planning planningportal.nsw.gov.au/major-projects Industry and Environment 2. Create a user account by clicking the ‘Sign Locked Bag 5022 In’ icon in the top right of the homepage or Parramatta NSW 2124 under the ‘Services’ tab and then click the ‘Have Your Say’ link Donations and Gift Disclosure 3. When you are logged in, fnd the Anyone lodging submissions must declare Beaches Link and Gore Hill Freeway reportable political donations made in the previous Connection project and click the two years. To fnd out what is reportable, and ‘Make a Submission’ icon. for a disclosure form, go to planning.nsw.gov.au/ How to make a hard copy donationsandgiftdisclosure or phone 1300 305 submission 695 for a copy. You can also submit a hard copy of your Privacy submission. If you want DPIE to delete your Before making your submission, please read DPIE’s personal information before publication, please Privacy Statement at planning.nsw.gov.au/privacy make this clear at the top of your letter. or phone 1300 305 695 for a copy. You need to include: DPIE will publish your submission on its website 1. your name and address, at the top of the in accordance with their Privacy Statement. letter only 2. the name of the application and application number: SSI_8862 Submissions must be received by 3. a statement on whether you support or DPIE before midnight Monday 1 object to the proposal March 2021. 4. the reasons why you support or object to the proposal 5. a declaration of any reportable political donations made in the previous two years.

nswroads.work/blportal Visit our interactive web portal Read the EIS, fnd out more or ask our 1800 931 189 team a question. [email protected] nswroads.work/blportal Customer feedback Transport for NSW, Locked Bag 928 Our phone line is monitored 24 hours North NSW 2059 when work is taking place.

Translating and Interpreting Service

If you need an interpreter, please call the Translating and Interpreting Service (TIS National) on 131 450 and ask them to telephone Transport for NSW on 1800 931 189.

Chinese (simplified) Italian Portuguese 若您需要口译员,请拨打 131 450 致电翻 Se avete bisogno di un interprete, Se necessitar de um(a) Intérprete, por 译与口译服务处(TIS National),并要求他 chiamate il servizio traduttori e interpreti favor, ligue para o Serviço de Tradução e 们转拨 1800 931 189致电 Transport for (TIS National) al numero 131 450 e Interpretação (TIS National), através de NSW。 chiedete di telefonare a Transport for 131 450 e peça o telefone do Transport NSW al numero 1800 931 189. for NSW, através de 1800 931 189.

Privacy Transport for NSW is collecting your personal information in connection with Beaches Link and Gore Hill Freeway Connection (”the Project”). In addition to collecting your name and contact details we may collect other information such as your submissions and other communications with us. We will retain and use this information for consultation purposes, including communications and analysis in connection with the Project. We will not disclose your personal information to third parties unless authorised by law and if we include your submissions in any public report we will not identify you. Providing your personal information is voluntary but if you do not provide it we may not include you on our stakeholder database and you might miss further consultation opportunities. Your personal information will be held by us and you can contact us to access or correct it. Please write to us at either [email protected] or Transport for NSW, Locked Bag 928, North Sydney NSW 2059.

Beaches Link and Gore Hill Freeway Connection EIS December 2020