Project Management Unit

West Inland Water Transport, Logistics and

Spatial Development Project

Environmental & Social Impact Assessment (ESIA) and Environmental & Social

Management Plan (ESMP)

for First Year Investments

February 8, 2020

West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

TABLE OF CONTENTS Executive Summary ...... 1 Proposed Development Objective(s) ...... 1 First Year Investments ...... 1 Jetty Locations ...... 2 Development Schedule ...... 4 Purpose of the Report ...... 5 Methodology Applied ...... 5 National Policy and Legal Framework ...... 5 Other Requirements - World Bank Safeguard Policies ...... 6 Baseline Environment ...... 6 Project Opportunities/Enhancement Measures ...... 7 Stakeholder Consultations ...... 7 Potential Impacts and Mitigation Measures ...... 8 Environmental and Social Management Plan ...... 11 Environmental Monitoring Program ...... 12 Project Management Unit (PMU) ...... 12 Conclusions...... 13 1 Introduction ...... 14 1.1 Proposed Development Objective(s) ...... 14 1.2 Overall Project Description/Components ...... 14 1.2.1 Component A: Strengthening IWT Institutional Capacity (USD 20 Million) ...... 15 1.2.2 Component B: Technical Assistance for Planning and Investment Prioritization (USD 8 Million) ...... 15 1.2.3 Component C: Infrastructure Investments to Improve Water Transport (USD 115 Million) ...... 16 1.2.4 Component D: Support to Implementation (estimated cost USD 7 Million) ...... 17 1.3 Project Beneficiaries ...... 17 1.4 Project Investments under First Year Investments ...... 17 1.5 Purpose of the Report ...... 18 1.6 Details of Project Proponent ...... 18 1.7 Methodology Applied ...... 19 1.7.1 Project Study Area ...... 19 1.7.2 Project Influence Area ...... 20 1.8 Structure of the Report ...... 20 1.8.1 Executive Summary ...... 20 1.8.2 Introduction ...... 20 1.8.3 Policy and Legal Framework ...... 20 1.8.4 Description of First Year Investments ...... 20 1.8.5 Baseline Scenario ...... 21 1.8.6 Analysis of Alternatives...... 21 1.8.7 Potential Impacts and Mitigation Measures ...... 21 1.8.8 Stakeholder Consultations & Information Disclosure ...... 21 1.8.9 Environmental and Social Management Plan...... 21 1.8.10 Conclusions & Recommendations ...... 21 2 Policy and Legal Framework ...... 22 2.1 EIA Notification ...... 22 2.2 CRZ Notification ...... 22 2.3 Forest and Wild Life Acts ...... 22 2.4 The Water (Prevention & Control of Pollution) Act, 1974 ...... 22 2.5 The Air (Prevention & Control of Pollution) Act, 1981 ...... 23 2.6 Noise Pollution Act/Rules ...... 23 2.7 Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016 23 2.8 The Motor Vehicle Act, 1988 ...... 23 2.9 Chemical Accidents (Emergency Planning, Preparedness and Response) Rules, 1996 ..... 23 2.10 Public Liability and Insurance Act 1991 ...... 24 2.11 Port Trust Guidelines ...... 24

Table of Contents Page i Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

2.12 Environmental Legislations ...... 24 2.13 Inland Waterways Regulations/Guidelines...... 27 2.13.1 The National Waterway Act, 2016 ...... 27 2.13.2 Prevention of Collision on National Waterways Regulations, 2002 ...... 27 2.13.3 National Waterways, Safety of Navigation and Shipping Regulations, 2002 ...... 27 2.13.4 National Disaster Management Guidelines on Boat Safety, September 2017 ...... 27 2.14 Land Acquisition/R&R ...... 28 2.15 Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 ...... 28 2.16 Memorandum - Direct Land Purchase from Land Owners ...... 28 2.17 The Right to Information Act, 2005 ...... 28 2.18 Kolkata Gazette – Multiplication Factor...... 29 2.19 The West Bengal Inland Fisheries Act, 1984 ...... 29 2.20 West Bengal Minimum Wages Rules, 1951 ...... 29 2.21 World Bank Safeguard Policies and Guidelines ...... 29 2.21.1 Environmental Assessment (OP/BP 4.01) ...... 30 2.21.2 Natural Habitats (OP 4.04) ...... 30 2.21.3 Physical Cultural Resources (OP/BP 4.11) ...... 30 2.21.4 Involuntary Resettlement (OP/BP 4.12) ...... 30 2.21.5 Projects on International Waterways (OP/BP 7.50) ...... 31 2.21.6 World Bank’s EHS Guidelines ...... 31 3 Description of First Year Investments ...... 33 3.1 First-Year Investments ...... 33 3.1.1 Gangways and Pontoons ...... 33 3.1.2 Waterside Construction Works ...... 34 3.1.3 New Vessels ...... 34 3.1.4 Turnstile Gates ...... 35 3.2 Jetty Locations ...... 35 3.3 Schedule and Cost ...... 41 3.3.1 Estimated Cost ...... 41 4 Baseline Scenario ...... 42 4.1 Introduction ...... 42 4.2 ...... 42 4.3 District Profiles ...... 43 4.3.1 Hooghly ...... 43 4.3.2 ...... 43 4.3.3 East Medinipur ...... 44 4.3.4 North 24 Parganas ...... 44 4.3.5 Kolkata ...... 44 4.3.6 South 24 Parganas ...... 44 4.3.7 Population Summary ...... 45 4.4 Climatic Conditions ...... 45 4.4.1 Hooghly ...... 45 4.4.2 Howrah ...... 45 4.4.3 East Medinipur ...... 45 4.4.4 North 24 Parganas ...... 46 4.4.5 South 24 Parganas ...... 46 4.4.6 Kolkata ...... 46 4.5 Social Profile ...... 46 4.5.1 Hooghly ...... 46 4.5.2 Howrah ...... 47 4.5.3 East Medinipur ...... 47 4.5.4 North 24 Parganas ...... 47 4.5.5 South 24 Parganas ...... 48 4.5.6 Kolkata ...... 48 4.6 Baseline Environment ...... 48 4.6.1 Ambient Air Quality ...... 49 4.6.2 Noise Environment ...... 50

Table of Contents Page ii West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

4.6.3 Water Environment ...... 51 4.6.4 Land Environment-Soil Quality ...... 55 4.6.5 Biological Environment ...... 56 5 Analysis of Alternatives ...... 64 5.1 No Project v/s With Project Alternative ...... 64 5.1.1 Telinipara Jetty Accident...... 64 5.2 Technical Design Alternatives...... 65 6 Potential Impacts and Mitigation Measures ...... 67 6.1 Project Activities ...... 67 6.1.1 Gangways and Pontoons...... 67 6.1.2 Waterside Construction Works ...... 68 6.1.3 New Vessels ...... 68 6.1.4 Turnstile Gates ...... 70 6.2 General Impact Matrix ...... 70 6.3 Vessel/Pontoon/Gangways Manufacturing ...... 71 6.3.1 Vessel Building Process ...... 72 6.4 Waterside Construction Works ...... 76 6.4.1 Construction Works ...... 76 6.5 Operation Stage (Vessel Movement) ...... 81 6.5.1 Vessel Movement ...... 81 6.6 Impacts Screening Matrix ...... 84 6.7 Indirect impacts ...... 86 6.8 Cumulative impacts ...... 86 6.9 Environmental Monitoring ...... 86 7 Stakeholder Consultations & Information Disclosure ...... 87 7.1 Introduction ...... 87 7.1.1 Modes of Stakeholder Consultations ...... 87 7.2 Stakeholder Consultation Findings ...... 87 7.3 Planned Information Disclosure ...... 91 7.3.1 At State Level ...... 91 7.3.2 On World Bank’s External website ...... 91 8 Environmental and Social Management Plan ...... 92 8.1 Components of ESMP ...... 92 8.2 Environmental and Social Management Plan Matrix ...... 92 8.2.1 ESMP Integration to Bid Document ...... 107 8.3 Environmental Monitoring Program ...... 107 8.4 Implementation Arrangements and Responsibilities ...... 111 8.4.1 Institutional Set-up for the Project ...... 111 8.4.2 Institutional Strengthening and Business Planning (ISBP)...... 111 8.4.3 Project Management Unit (PMU) ...... 112 8.4.4 Project Management Consultants ...... 112 8.4.5 Audits and Inspections...... 113 8.4.6 Contractors ...... 113 8.4.7 Grievance Redress Mechanism ...... 113 8.5 Capacity Building Requirements ...... 116 8.6 ESMP Budget...... 117 9 Conclusions ...... 119 LIST OF APPENDIXES ...... 120 Appendix 1: Environmental and Social Screening Forms ...... 121 Appendix 2: List of Projects or Activities Requiring Prior Environmental Clearance ...... 146 Appendix 3: Chance Find Procedure ...... 156 Appendix 4: CPCB’s National Ambient Air Quality Standards, GoI ...... 157 Appendix 5: Noise Quality Standards, GoI ...... 159

Table of Contents Page iii West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 6: Water Quality Standards, GoI ...... 160 Appendix 7: Soil Quality Standards, GoI...... 166 Appendix 8: Stakeholder Consultations ...... 167 Stakeholder Consultations - their views / perspectives ...... 167 The Vessel Operator ...... 167 The Jetty Operators ...... 167 The Passengers ...... 167 The local Governing bodies ...... 173 The shop owners ...... 173 Other beneficiaries ...... 173 Appendix 9: Draft Format for Monitoring of Grievances ...... 185

LIST OF FIGURES Figure 1 Jetty Locations...... 2 Figure 2: PMU's Institutional Set Up ...... 12 Figure 3-1 Jetty Locations ...... 37 Figure 4-1 Dolphin Population ...... 57 Figure 6-1 Schematic Flow of Activities, Impacts & Mitigation Measures ...... 71 Figure 8-1: Overall Institutional Framework for WBTIDCL ...... 111 Figure 8-2: PMU's Institutional Set Up...... 112

LIST OF TABLES Table 1 Estimated Cost (First Year Investments) ...... 4 Table 2 Potential Impacts of First Year Activities ...... 9 Table 3 Potential Impacts Screening Matrix ...... 10 Table 2-1: Relevant Environmental Laws & Regulations ...... 24 Table 2-2: Regulations Applicable for Inland Waterways ...... 27 Table 3-1 List of Selected Jetties (First Year Investments) ...... 36 Table 3-2 Estimated Cost (First Year Investments) ...... 41 Table 4-1 Population Summary ...... 45 Table 4-2 Social Profile – ...... 46 Table 4-3 Social Profile – ...... 47 Table 4-4 Social Profile – East Medinipur District ...... 47 Table 4-5 Social Profile – North 24 Parganas District ...... 47 Table 4-6 Social Profile – South 24 Parganas District ...... 48 Table 4-7 Social Profile – Kolkata District ...... 48 Table 4-8 Ambient Air Monitoring Stations ...... 49 Table 4-9: Summary of Air Quality Parameters ...... 49 Table 4-10: Ambient Noise Quality Monitoring Stations ...... 50 Table 4-11: Noise Levels during Study Period ...... 50 Table 4-12: Noise Levels at Jetty Location ...... 50 Table 4-13: Water Sampling Locations ...... 52 Table 4-14: Ground Water Quality ...... 52 Table 4-15: Surface Water Quality ...... 53 Table 4-16: Soil Sampling Locations ...... 55 Table 4-17: Soil Quality Results ...... 55 Table 4-18 Sightings of River Dolphin ...... 59 Table 6-1 Potential Impacts of First Year Activities ...... 70 Table 6-2 Potential Impacts Screening Matrix ...... 85 Table 7-1 Stakeholder Suggestions and Design Considerations ...... 90 Table 8-1 Environmental and Social Management Plan Matrix ...... 93 Table 8-2 Environmental Parameter Monitoring Program during Construction Stage ...... 109 Table 8-3 Details of Grievance Redressed Committee Members ...... Error! Bookmark not defined. Table 8-4: Training Type, Target Groups, Purpose and Frequency ...... 116 Table 8-5: Estimated EMP Budget ...... 117

Table of Contents Page iv West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Table 8-6: Estimated Budget ...... 117

Table of Contents Page v West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

LIST OF ABBREVIATIONS AND ACRONYMS AAQ Ambient Air Quality BOT Build, Operate and Transfer CO Carbon Monoxide CPCB Central Pollution Control Board CRZ Coastal Regulation Zone CTE Consent to Establish CTO Consent to Operate CZMA Coastal Zone Management Authority CZMP Coastal Zone Management Plan DG Diesel Generator EHS Environment, Health & Safety EIA Environmental Impact Assessment EMP Environmental Monitoring Program ESIA Environmental & Social Impact Assessment ESMF Environmental & Social Management Framework ESMP Environmental and Social Management Plan GoI Government of GoWB Government of West Bengal GRC Grievance Redressal Committee GRM Grievance Redressal Mechanism HAPs Hazardous Air Pollutants HTL High Tide Line ISBP Institutional Strengthening and Business Planning IUCN International Union for Conservation of Nature IWT Inland Water Transport KMA Kolkata Metropolitan Authority KMC Kolkata Municipal Corporation KoPT Kolkata Port Trust L&TIEL L&T Infrastructure Engineering Limited LA Land Acquisition LARR Land Acquisition, Rehabilitation and Resettlement Act LTL Low Tide Line MPT Major Port Trusts MoEF&CC Ministry of Environment, Forest and Climate Change NGT National Green Tribunal NOx Oxides of Nitrogen OP Operational Policies PAPs Project Affected Persons PDOs Project Development Objectives PIC Public Information Center PM10 Particulate Matter <10 micron size PM2.5 Particulate Matter <2.5 micron size PMC Project Management Consulting PMU Project Management Unit PPE Personal Protective Equipment PUC Pollution Under Control PWD Public Works Department

Table of Contents Page vi West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

RFCTLARR Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act SO2 Sulphur Dioxide SOP Standard Operating Procedures SPCB State Pollution Control Board TOIP Traffic Operation and Improvement Program VOCs Volatile Organic Compounds WBTC West Bengal Transport Corporation WBPCB West Bengal State Pollution Control Board WBTIDCL West Bengal Transport Infrastructure Development Corporation Limited WBIWTLSDP West Bengal Inland Water Transport, Logistics and Spatial Development Project

Table of Contents Page vii

West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Executive Summary

Government of West Bengal (GoWB) is promoting Inland Waterways Transportation through its network of rivers and canals. In this backdrop, GoWB, through Government of India has applied for financing from the World Bank for financial assistance for improvement/ development of the inland water transport system in the state. Under the investments requested for the First Year, the proposed developments will include upgradation of selected existing jetties that would have improved facilities and amenities for passenger movement. As per the World Bank Guidelines, prior to investing into such development projects, the Environmental and Social Impact Assessment is to be carried out. In this regard, West Bengal Transport Infrastructure Development Corporation Limited (WBTIDCL), the implementing agency under GoWB has appointed L&T Infrastructure Engineering Limited (L&TIEL), for providing necessary “Consulting Services for Environmental & Social Management Framework (ESMF) and Environmental & Social Impact Assessment (ESIA) for West Bengal Inland Water Transport, Logistics and Spatial Development Project”. As part of the overall consultancy services this report, the “Draft Environmental and Social Impact Assessment (ESIA) including the Environmental and Social Management Plan (ESMP)”, has been prepared. Prior to conduct/preparation of this ESIA, specific Environmental and Social Management Framework (ESMF) was prepared for the entire project. The ESMF provides a basis for conducting ESIA studies and preparing the ESMPs for all investments under the Project. Therefore, this ESIA/ESMP, which is solely for the First Year Investments, are consistent with the ESMF. Further, during the first year, an integrated spatial development plan will be prepared. This will determine the rest of the investments to be facilitated during the rest of the project period. The CIA and the required ESIA/ESMPs will be as part of this plan. Proposed Development Objective(s) The Project Development Objectives (PDO) as defined for the proposed development are: (i) to improve the efficiency and safety of passenger and freight movement across the Hooghly River; and (ii) establish a spatial planning framework to enhance accessibility within Kolkata Metropolitan Area (KMA). First Year Investments 30% of the overall project budget is proposed to be taken up under First Year of Investments (~USD 45 Million). Under the investments requested for the First Year, the proposed developments will include upgradation of existing jetties that would have improved facilities and amenities for both passenger movement. Subprojects that will be supported as a part of the First-Year investments are: • Improving the capacity of selected jetties by adding pontoons and gangways • Implementing minor waterside construction works to install gangways and pontoons • Adding new vessels with enhanced designs to existing fleet • Installing turnstile gates in selected jetties

Executive Summary Page 1 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Jetty Locations A total of 30 Ghats (jetty locations) are included to be taken up in the proposed developments under the First Year investments. The jetty locations are on either side of the Hooghly River, some on the Kolkata side and some on the Howrah side. A map showing the locations is presented as Figure 1.

Figure 1 Jetty Locations

Executive Summary Page 2 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Gangways and Pontoons Pontoons and Gangways are proposed to be added at selected jetties to improve the capacity of the jetties. Gangways and Pontoons are proposed to be added at 30 selected jetty locations. Pontoons and gangways are added to existing ones in these locations to improve the capacity and safety of passengers. When there is a need to remove existing pontoons and/or gangways, they will be taken out and re-used at another existing or new jetty location under WBTC within the project influence areas. Those that cannot be reused, will be sold to local companies in the market who are specialized in recycling the material.

Typical (existing) gangways and pontoons are as shown as Exhibit 1 and Exhibit 2.

Exhibit 1 Typical Gangway (Existing) Exhibit 2 Pontoon Structure (Existing)

Waterside Construction Works Proposed developments activities will include minor waterside construction works mainly needed to put in place the new pontoons and gangways. In general, and because of the tidal nature of the Hooghly river, pontoons are designed to be floating and cannot be pinned to the ground. Gangways are supported by the pontoons on one side and linked to the existing jetty on the landside in a manner that allows vertical and horizontal movement caused by the high river waves. As such, dredging is very minimal and impact from sediments is not significant.

New Vessels Project first Year investments will include modernizing the fleet through the introduction of new vessels with enhanced designs. New vessels will be an addition to the existing fleet. Investments will include addition of Twenty (20) cross movement vessels of 100 passenger capacity and Two (02) longitudinal movement vessels also of 100 passenger capacity. Cross movement and longitudinal movement vessels have the same features; however, the engine power and dimensions differ. An existing vessel and an image of a new vessel are shown as Exhibit 3 and Exhibit 4, respectively. The new passenger ferries will be built based on enhanced design that is inclusive with improved safety standards, fuel efficiency, and solid and liquid waste management facility.

Executive Summary Page 3 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

.

Exhibit 3 Existing Vessels Exhibit 4 Image of New Vessel Turnstile Gates Installation of Turnstile Gates at 40 selected jetty locations are proposed to be taken up under the First Year investments. Existing Turnstile Gates at Howrah jetty location is as shown in Exhibit 5.

Exhibit 5 Turnstile Gate (Howrah Jetty) Development Schedule Proposed developments discussed above are to be taken up in the First Year of investments. As such, the schedule for this development shall be for a period of one year. Estimated Cost The estimated costs for proposed developments under First Year of investments are as provided in Table 1. Table 1 Estimated Cost (First Year Investments) S. Unit Cost (INR No. of Total Cost (INR Total Cost Activity No. in Crores) Units in Crores) (US$ Million) Works at the Jetties (includes Pontoon, 1. ~ 4.33 30 130.00 18.60 Gangway and the necessary Civil Works) 2. 100 Passenger Size Vessels ~ 2.80 20 56.00 8.00 3. Longitudinal Vessels (100 Passenger Size) ~ 4.5 2 9.00 1.28 Turnstile Gates (4 nos. at each of the 40 4. ~ 1.00 40 40.00 5.80 selected jetty locations) First Year Investments Estimated Total 235.30 33.68

Executive Summary Page 4 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Jetty Locations The Project area is one of the most populous areas in India, stretching for more than 120 km along the Hooghly river from Tribeni, to the north of Kolkata, to Roychak, to the south. A total of 30 Ghats within the Project area are included to be taken up in the proposed developments under the First Year investments. The jetty locations are on either side of the Hooghly River, some on the Kolkata side and some on the Howrah side. Purpose of the report This ESIA is carried out as part of the process of compliance with the World Bank Safeguard Policies in relation to the proposed development activities. The ESIA studies the existing environmental and social conditions and provides an understanding of the likely impacts (adverse as well as positive) to the environmental and social conditions at the project area. The ESIA suggests measures needed to be put in place to prevent/minimise the likely environmental and social impacts due to the proposed project development activities. Also, the ESIA helps formulate and provide a project specific Environmental and Social Management Plan (ESMP). This ESMP will form a part of project developments tender/bid document and will form the basis for the selected contractor(s) to prepare the Operational ESMP to be implemented during project execution stage. Methodology Applied The methodology is based on the requirements of the applicable National Policies, World Bank Safeguard Policies as well as the ToR for the ESIA study provided by the client (WBTIDCL). Also, the methodology adopted for the study, builds on the consultants overall experience in carrying out such studies. Accordingly, the methodology involved in this study included: • Site Reconnaissance • Preliminary Environmental and Social Screening • Review of Applicable Legislation, • World Bank’s Safeguard requirements • Other available/relevant secondary data, information resources, including other ESIA studies available as reference (Data collection is carried out within the defined Project Study Area) • Analysis of alternatives wherever feasible • Stakeholder Consultations • Data Collection • Identification of Potential Impacts and suggestion of Mitigation Measures (Considering the small scale of activities to be taken up under the First Year of Investments, the Potential Impacts are assessed within the defined Project Influence Area) The ESIA study has been carried out considering the Design, Construction and Operational stages of the project. In each stage, anticipated impacts due to proposed development on the environment and social components have been assessed and appropriate mitigation measures have been suggested and formulated in the ESMP. The site assessments, data collection, stakeholder consultations, etc. as part of the ESIA study have been carried out between October 2019 and January 2020.

National Policy and Legal Framework India has a well-defined institutional and legislative framework covering various parameters including the Environmental and Social components. The applicability of the regulations has been reviewed as part of the study. The regulations include:

Executive Summary Page 5 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

• EIA Notification: the proposed development activity does not fall under the purview of the EIA Notification needing an Environmental Clearance • CRZ Notification: project development area is beyond the CRZ limits and hence CRZ Notification will not be applicable for proposed development needing the CRZ Clearance • Forest and Wild Life Acts: proposed development will not involve diversion of Forest Land/Wild Life areas and hence will not need the Forest Clearance/Wild Life Clearance. • The Water (Prevention & Control of Pollution) Act, 1974: proposed development will need to obtain the necessary CTE and CTO from WBPCB • The Air (Prevention & Control of Pollution) Act, 1981: proposed development will need to obtain the necessary CTE and CTO from WBPCB • Kolkata Port Trust Guidelines: necessary permissions/approvals will need to be obtained from KoPT • Land Acquisition/R&R: proposed development will not involve Land Acquisition

Other Requirements - World Bank Safeguard Policies World Bank’s Operational Policies (OPs) and Requirements on environmental and social safeguards have been reviewed and found the following OPs are be triggered under the project: o OP/BP 4.01: Environmental Assessment o OP/BP 4.04: Natural Habitats o OP/BP 4.11: Physical Cultural Resources o OP/BP 4.12: Involuntary Resettlement o OP/BP 7.50: Projects on International Waterways Baseline Environment The proposed project will be implemented in Hooghly River, a part of the Ganga River. The project influence areas stretch from Tribeni to Roychak (Figure 1). The baseline environmental quality represents the background environmental scenario of various components such as air, noise, water, soil quality status in the study area. The baseline assessment is presented based on secondary data as referred from the EIA study recently carried out (March 2019 – May 2019) for the Proposed Construction of Gangway-Pontoon Jetty with Link platform on river Hooghly at Geonkhali, District, East/ Purba Medinipur. The location of this study is within the overall study area of the present jetty improvement project. As such, data from the Geonkhali study is considered as relevant to the current study area as well. The monitoring data has been referenced from EIA Report prepared for the above project and titled “Rapid Environmental Impact Assessment & EMP Report for Proposed Construction of Gangway-Pontoon Jetty with Link platform on River jetty Hooghly at Geonkhali, Dist.-Purba Medinipur, W.B for Passenger Ferry service of WBTIDCL (Geonkhali Jetty EIA Report). The baseline data suggests that environmental parameters of ambient air quality, noise levels, water quality and soil are in general within permissible limits/standards. Dolphins in the Hoogly River The Ganga-Brahmaputra-Meghna and - systems of Nepal, India and are home to Gangetic Dolphin (Platanista gangetica). Report on the distribution of Gangetic Dolphin (GD) in the project stretch/influence area is mixed and reported sightings ranged from 11-50. Sangita Mitra & Mahua Roy Chowdhury (2018) studied the stretch in Hooghly River during the period of 2012–2016 and reported a total of 13 sightings of GD1. A

1 Chowdhury, M.R., S. Mitra & S. Sen (2016). On the Behaviour, abundance, habitat use and potential threats of the Gangetic Dolphin Platanista gangetica in southern West Bengal, India. Journal of Threatened Taxa 8(9): 9131–9137; https://doi.org/10.11609/ jott.1752.8.9.9131-9137

Executive Summary Page 6 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments reconnaissance survey conducted by the Wildlife Institute of India reported sightings 21 and 50 during Pre and post -monsoons of 2018 and 20192. Due to these sightings, the stretch was classified as a medium priority area for conservation. WWF-INDIA has conducted a visual survey in 2016 with sightings of an estimated 11 individuals. No information is available on the pattern of GD distribution in the project stretch. According to experts view from WWF, GD are found dispersed in the stretch with more concentration at the confluences of the rivers where the water current is strong. The experts also explained the biggest threat for dolphins comes from fishing activities because dolphins are wrongly trapped and drowned to death. The threat from vessel movement is because of noise. GD is sensitive to sound and it is unlikely that it will be hit by running vessels.

Project Opportunities/Enhancement Measures The proposed development will provide opportunities for various technical related alternatives to be implemented. Such alternatives include: • Introduction of newer/better efficient vessels with reduced emissions • Vessels/Gangways/Pontoons can have additional safety features • Better performance engines and lighter vessels, can help in reduced fuel consumptions • Vessels/Gangways can be provided with solar components for lighting purpose which will help reduce energy costs • Vessels with latest applicable best management practices/technology can be built and introduced • Project vessels being operated in an aquatic environment with relatively rich aquatic life, mechanisms like sound emitting devices in the waters can be adopted which will alert fishes of the approaching vessels • Vessels shall have necessary oil spill control/collection systems • Jetty locations can be provided with appropriate oil spill control/collection equipment’s • Vessels can be fitted with sewage/waste collection systems; similarly sewage/waste collection facilities can be provided at the terminals which can collect sewage/waste from the vessels and dispose it appropriately • Various enhancements at the jetty locations can be provided (provision of signages, information systems, easy access for elderly/disabled commuters, etc.) • Jetty location aesthetic improvements can be taken up (landscaping, planting of trees, etc.) • Improved facilities at the vessel/gangway/pontoon manufacturing units in terms of environmental and social aspects Stakeholder Consultations Stakeholder Consultations form an important part of the ESIA process and is essential in achieving the overarching objectives of any project implementation to help ensure sustainable development. This consultation process is a major tool for information dissemination to the direct and indirect impacted due to the project. The stakeholder consultation process helps in reducing the public resistance to change and enable the participation of the local people in the decision-making process. For proposed development project, informal stakeholder consultations have been conducted at several jetty locations. Consultations included discussions with PMU team, ferry

2 Wildlife Institute of India, Conserving Gangetic Dolphin, Smart Strategy Implementation and Adaptive Management for the Ganga River (WII – GACMC, 2019)

Executive Summary Page 7 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments commuters/operators, locals in immediate vicinity of jetty locations (e.g. small shop operators just outside jetty area, daily-wage workers, rickshaw (auto, cycle, toto) operators, etc.) In addition, a formal Stakeholder Conference was also held at the WBTIDCL office location on October 31, 2019. Stakeholder Consultation Findings In general, the participants were enthusiastic and appreciated the proposed project and gave valuable inputs over the development aspect, localized needs and suggestions for the design/construction of the project. They appreciated the fact that this project will help provide improved facilities at the jetty locations and provide added convenience to the commuters. Following is a brief summary of the consultation inputs from the Stakeholder Consultations: • Need for widening of the gangway with a separate entry and exit points • Barricading on Pontoons and Gangway • Provision of roof on gangway/concrete ramps to Pontoon • Provision of better facilities at jetty area (waiting area, toilets, seating arrangements, fans, drinking water, etc.) • Request by workers on the pontoon for provision of rain/sun shade and seating facility on the Pontoons • Need for automatic ticket punching system • Proper displays and announcements at the jetty locations is essential • Increase frequency of ferries during peak hours would be beneficial • Provide facilities for handicap/elderly commuters (like wheel chair) • Regular maintenance of the jetty infrastructure shall be ensured; stakeholder consultations reveal that several commuters fear maintenance works are far lacking at the jetty locations (includes vessels, gangways, etc.) • Is understood that vessels get overcrowded during the peak hours • Some commuters try and get on and off board while the vessel is in motion which is a major safety concern • Adequate safety measures to be provided at all jetty locations • Vessel operators find it difficult to control the commuters during peak hours and it gets difficult to check if all commuters have paid for the commute or not • Bigger capacity vessel with better facilities shall be provided at locations with larger passenger movements • Passengers expressed willingness in temporary inconveniences to be faced during the construction period of the works Suggestions given by stakeholders have been looked into and whatever is found to be feasible will be incorporated into the design/planning and implementation of the project. Such suggestions included: widening of the gangway, barricading on pontoons and gangways, provision of better facilities at jetty locations (toilets, drinking water, etc.), proper displays and announcements at the jetty locations, etc. The stakeholder suggestions and its considerations are elaborated further in Section 7.2. Potential Impacts and Mitigation Measures Proposed activities are limited to minor construction works at the jetty locations which will involve installation of the pontoon and gangways and minimal civil works on the link platform (concrete structure). In addition, the major activity under the First Year Investments is the manufacturing of the vessels, pontoons and gangways which will be done at the manufacturing yards of the selected contractors. Proposed development activities will have more positive impacts than negative impacts on the environmental/social conditions.

Executive Summary Page 8 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Proposed development will involve three stages, namely: Design/Build, Construction and Operation stage. These stages are likely to have varying levels of environmental and social impacts. Table 2 presents a brief summary of activities and likely impacts it could have. Table 2 Potential Impacts of First Year Activities Description of No. Likely Impacts Project Investments Mostly limited to the manufacturing facility: Gangways and 1 Generation of Solid Waste, Wastewater, Air Pollution, Noise Pollution, Worker Pontoons Safety and Labour / Worker Camps At the Jetty Locations: Waterside Construction Waste/Debris, Wastewater, Air Pollution, Noise Pollution, Water 2 Construction Works Pollution, Worker Safety, Community Safety and Temporary Community Disturbances Mostly limited to the Vessel Building Yard: 3 New Vessels Generation of Solid Waste, Wastewater, Air Pollution, Noise Pollution, Worker Safety and Labour / Worker Camps None to Minor environmental and social issues envisaged and limited to production 4 Turnstile Gates facility. Being a bought-out item, it is beyond purview of this ESIA study Based on the above matrix, the likely impacts from the activities of vessel manufacturing, pontoon and gangways manufacturing are similar. As such the impacts and mitigation measures for these activities are discussed in common. Impacts and mitigation measures from the waterside construction works activities are discussed separately. Further, Turnstile Gates being a bought out item, any impacts associated with this activity (although none to minimal envisaged). The assessment covered various likely impacts on environmental/social parameters as follows: • Impacts on Air Quality • Impacts on Noise Levels/Quality • Impacts on Water Quality • Impacts Due to Solid Waste • Impacts on Soil Quality • Impacts on Land Acquisition/Land use • Impacts on Flora and Fauna • Impacts on Socio-Economic Environment • Impacts during Operation Stage (Vessel Movement) • Impacts on Health & Safety Based on the nature of activities to be carried out under the First Year investments, it is envisaged that there will be minimal environmental/social impacts. The minimal impacts that could be there are in general temporary in nature, localised and reversible. Mitigation measures to avoid/minimize the likely impacts have been suggested. Impacts can be minimized/ avoided by implementation of the suggested mitigation measures. Impacts Screening Matrix Based on the ESIA, an impacts screening matrix is prepared and presented as Table 3. The matrix presents a summary of potential impacts due to various project activities and indicates its level of significance viz. Insignificant, -significant, Small, Moderate and Major. The different levels of significances can be rated as follows:

Executive Summary Page 9 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

• Insignificant – none to extremely minimal impacts; impact can be easily absorbed without requiring much efforts • Small – minimal impacts mostly short term; impact can be absorbed with minimal mitigation measures/efforts • Moderate – beyond minimal but mostly reversible; impact to be absorbed with higher level of mitigation measures/efforts and resources • Major – irreversible impacts, likely long term; impacts require extremely high level of mitigation measures/effort and resources to be in place to be handled Table 3 Potential Impacts Screening Matrix Significance

Project Activities Concerns Small Major Moderate Insignificant Manufacturing Works Vessel, Pontoon, Air Pollution, Water Pollution, Noise Levels, ● Gangways Soil Contamination, Solid Waste Manufacturing Workers health & safety ● Waterside Construction Works Site surveys & Destruction of vegetation/landscape ● investigations Displacement of population Not Applicable Loss of livelihood (squatters, vendors – non ● Land Acquisition & title holders) Resettlement Displacement of structures and disruption to ● services (during construction) Loss cultural heritage Not Applicable Loss of Top soil and change in characteristics Not Applicable Loss of trees & vegetable cover Not Applicable Construction Site Noise, vibration and dust nuisance from site Clearance ● clearance activity Demolition, removal of existing infrastructure ● Construction camp Friction between construction personnel and ● establishment & local population operation Water pollution from sanitary and other wastes ● Overloading of road structures & damage to pavement (will have movement on waterways ● Mobilization of heavy as much as possible) machinery Inducement of traffic congestion & road safety ● hazards Disturbance of sediments / deterioration in water quality, when construction activities ● Construction of carried along/in water bodies structures Air Pollution, Water Pollution, Noise Levels, Soil Contamination, Solid Waste issues due to ● construction activities Construction works Workers health & safety ●

Executive Summary Page 10 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Significance

Project Activities Concerns Small Major Moderate Insignificant Disturbance to aquatic fauna (including ● Dolphins) Operation Phase Pollution from oil spills from vessels ● Disturbance to aquatic fauna (including Operation ● Dolphins) Workers health & safety ●

Impact on Gangetic Dolphin First year investments is expected to have no impacts on dolphins as most of the activities are conducted at the water fronts and vessel manufacturing yards. However, the Project ESMF and ESIA provided specific mitigation measures to protect Gangetic Dolphins during construction and operation phases.

Beyond protecting dolphins from impacts associated with the proposed project activities, it is envisaged to work closely with WWF INDIA to create awareness to fishermen operating at the project stretch to help minimize impacts on GD from fishing, as they are causing the highest threat to dolphins. Further, the Project will collaborate with Inland Water Transport Project (P157929) to exchange best practices in protecting GD during vessel operations, and seek for financial resources for conducting an in-depth study on distribution patterns and behavior of GD. The outcome of such a study will provide not only practical mitigation measures (by indicating areas where more care is needed) but also will be used to generate additional funds for a larger project for conservation of dolphins and other endangered aquatic fauna.

Indirect Environmental Impacts The likely sources of indirect impacts include (i) increased vessel and human traffic; and (ii) replacement of old gangways and pontoons. Increase in vessel numbers will improve the currently congested water way transportation system. The daily volume of passengers using the existing vessels, pontoons and gangways is 200,000. The 22 new vessels which will be added as part of first year investment will absorb 10 percent of the daily volume of passengers. As such, increase vessel numbers will improve passengers’ safety with no indirect impacts. Given the shortage of vessels there is no plan to replace vessels in the first-year investments. Regarding replacement of gangways and pontoons, most of the gangways and pontoons may not be replaced as the plan is expand some of them for providing safety to passengers. Those that will be replaced will be transferred to recycling facilities Environmental and Social Management Plan Based on the identified likely impacts and suggested mitigation measures, the ESMP has been prepared. Following specific environmental/social management aspects are discussed under the ESMP: • Summary of project activities, associated impacts and mitigation measures • Administrative and Technical Setup for Environmental/Social Management • Institutional Mechanism for Implementation of Mitigation Measures • Audits and Inspections • Grievance Redress Mechanism

Executive Summary Page 11 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

• Capacity Building Requirements Environmental Monitoring Program Environmental monitoring is one of the important components of the ESMP. The main aim of the monitoring is to establish the existing scenario to make informed decisions to ascertain the proper implementation. The main objectives of the environmental monitoring are: • To ensure the effective implementation of ESMP • To comply with all relevant environmental/social regulations • To modify the mitigation measures and implementation arrangements, if found necessary Nature of activities to be taken up under First Year investments is not envisaged to have significant sources of environmental pollution. As such, a minimal monitoring program is suggested and implementation of suggested mitigation measures is to be ensured. Monitoring shall include air quality, water quality, noise levels, etc. Monitoring will aim to keep track of construction/operation related air emissions, spills/leaks in the water body, etc. and check its compliance with the relevant standards. The ESMP in Section 8.3 discusses the monitoring program and implementation/supervising responsibilities. Project Management Unit (PMU) The WBTIDCL is the overall PMU unit operating under the West Bengal Transport Corporation (WBTC). It serves as a dedicated Engineering Wing for taking up development works for WBTC. WBTIDCL will be the PMU for the proposed development works as well. The Project Director (PD) will have the overall responsibility whereas dedicated Environmental Specialist and Social Development Specialists will have day-to-day implementation responsibilities. In the current institutional arrangement, the Environmental Specialist will also coordinate the safety management functions. Thus, the position under the PMU will be Environmental and Safety Specialist. The PMU under the WBTIDCL will be responsible for ensuring that this ESIA/ESMP is adhered during the project implementation. In addition, a PMC unit will be in place under the ISBP component. The PMC consultant under the ISBP will work/coordinate with the PMU/WBTIDCL for the day-to-day implementation aspects and associated safeguards compliance. The PMU shall be as shown in Figure 2.

Project Director

Environmental & Social Safety Specialist Development Specialist

Procurement PMC/ISBP Specialist Consultant

Figure 2: PMU's Institutional Set Up

Executive Summary Page 12 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Conclusions The proposed development activities seek to address urgent enhancement needs of the existing jetty infrastructure requirements. The activities under First Year investments will be limited to building/manufacturing of 22 new Vessels, addition of new Gangways and Pontoons at 30 selected jetty locations, installation of Turnstile Gates at 40 jetty locations and minor Waterside Construction Works at the 30 selected jetty locations. The activities under First Year investments will not involve Land Acquisition. Also, the activities are not envisaged to pose environmental and social impacts. However, as any development project, there will likely be some minimal impacts which have been identified in this report. These impacts are short term/localized and reversible impacts. Mitigation measures to avoid/ minimize the likely impacts have been suggested. The implementation arrangements needed to ensure implementation and effectiveness of the mitigation measures will be carried out through the PMU. Details of the arrangements have been discussed in this report. Proposed development activities will help enhance the existing jetty infrastructure and will have overall positive impacts to the community as well as environment and without adversely affecting the environmental and social conditions/quality in the project area.

Executive Summary Page 13 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

1 Introduction Government of West Bengal (GoWB) is keen to promote Inland Waterways Transportation through its network of rivers and canals. In this backdrop, GoWB, through Government of India has applied for financing from the World Bank for financial assistance for improvement/ development of the inland water transport system in the state. Under the investments requested for the First Year, the proposed developments will include upgradation of existing jetties that would have improved facilities and amenities for passenger movement. Such developmental projects are likely to trigger set of environmental and social impacts which forms a critical part of decision making. Significant benefits occur due to such development projects while adverse impacts may arise in terms of environment and social aspects. Impacts can be minimized/avoided with help of appropriate mitigation measures. Proposed development activities must adhere to the best standards meeting sustainable environment, social acceptability and economic viability. As per the World Bank Guidelines, prior to investing into such development projects the Environmental and Social Impact Assessment is to be carried out. In this regard, West Bengal Transport Infrastructure Development Corporation Limited (WBTIDCL), the implementing agency under GoWB has appointed L&T Infrastructure Engineering Limited (L&TIEL), for providing necessary “Consulting Services for Environmental & Social Management Framework (ESMF) and Environment & Social Assessment (ESIA) for West Bengal Inland Water Transport, Logistics and Spatial Development Project”. As part of the overall consultancy services this report, the “Draft Environmental and Social Impact Assessment (ESIA) including the Environmental and Social Management Plan (ESMP)”, has been prepared. Prior to conduct/preparation of this ESIA, specific Environmental and Social Management Framework (ESMF) was prepared for the entire project. The ESMF provides a basis for conducting ESIA studies and preparing the ESMPs for all investments under the Project. Therefore, this ESIA/ESMP, which is solely for the First Year Investments, are consistent with the ESMF.

1.1 Proposed Development Objective(s)

The Project Development Objectives (PDO) as defined for the proposed development objectives are to: (i) improve the efficiency and safety of passenger and freight movement across the Hooghly River; and (ii) establish a spatial planning framework to enhance accessibility within Kolkata Metropolitan Area.

1.2 Overall Project Description/Components

In the above context, the WBTIDCL (undertaking of the GoWB) with loan assistance from World Bank is planning to improve the waterways system for optimized usage for the overall development of the Kolkata Metropolitan Area in particular and the state in general. The project comprises four components.

Introduction Page 14 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

1.2.1 Component A: Strengthening IWT Institutional Capacity (USD 20 Million) This component will support institutional capacity enhancements for the GoWB’s Departments of Transport. This component is intended to provide West Bengal Transport Department with the required assistance to: i. Assess, identify and develop the scope for sector planning, regulatory and institutional reforms review of governance structures, business and financial planning, safety management and capacity enhancement for key agencies operating within the West Bengal IWT sector, including private sector operators. It includes the following two subcomponents: Subcomponent A.1 Support for institutional capacity enhancement to regulate, manage, and (USD 8 Million) maintain river transport systems This subcomponent will finance the preparation of the Institutional Strengthening and Business Plan (ISBP), which will comprehensively map the institutional structure, business processes, and human resource management and identify opportunities for improvement and consolidation. As part of preparing the ISBP, a Training Needs Assessment (TNA) of Transport Department and its key subsidiaries will be conducted to support a full training program implemented under the project. Interventions under this subcomponent will aim to increase the percentage of women in technical and non-technical job roles in the IWT Department as well as with the ferry operators. Subcomponent A.2 Safety management: river navigation aids, night navigation (USD 12 Million) technology on some routes, and emergency response system The subcomponent will draw on national and international experience in assessing appropriate aids to navigation, their procurement and deployment to allow 24-hour services/night navigation on the most hazardous and/or trafficked routes and crossing points of the Hooghly River. Beginning with pilots at two-three crucial locations, deployment of navigation aids will be scaled up based on the investment strategy for the sector. The subcomponent will finance hardware and software for the navigation system and emergency response system. The proposed Project will finance an assessment of the existing River Information System (RIS) and the implementation of a system update.

1.2.2 Component B: Technical Assistance for Planning and Investment Prioritization (USD 8 Million)

With a large coverage area and multiple institutions, the proposed Project will finance a spatial development strategy (SDS), logistics master plan (LMP) and a comprehensive mobility plan (CMP) to ensure improved accessibility to the IWT network and identify ways to create wider economic development opportunities around the Project’s investments. This will complement the institutional capacity strengthening efforts and tackle the structural elements that form the basis for the Project’s main challenge: constrained accessibility. Accordingly, this component will focus on the medium and long-term spatial, mobility and logistics planning to improve the livelihood and mobility within the city and the linkages to the port. As a result of the intervention, the GoWB will prepare a broad roadmap for future transport investments that promotes a more balanced modal mix, improved modal integration, mainstreaming of IWT, better climate adaptability/resilience, and emissions reduction. The roadmap will include provisions to attract and gradually promote the participation of the private sector in the financing and operation of

Introduction Page 15 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments transport infrastructure. The component will be implemented through the following two subcomponents. Subcomponent B.1 Spatial Development Strategy and Logistics Master Planning (USD 5 Million) The subcomponent will finance preparation of (a) a Spatial Development Strategy and (b) Logistics Master Plan. Focus will be on strengthening the capacity to support investments, as well as an effective linkage between planning, implementation capacity and coordination, and the budget process for the KMA. The LMP will include technical support to be provided to a high-level council on logistics recently created by GoWB. Subcomponent B.2: Prioritizing investments in IWT and linkages to transport (USD 3 Million) network This subcomponent will prioritize investments in IWT in the short and medium-term and provide a long-term vision for mobility within the KMA. The analytical work under this sub-component includes the Integrated Strategic Development Plan and the Comprehensive Mobility Plan.

1.2.3 Component C: Infrastructure Investments to Improve Water Transport (USD 115 Million)

This Component will provide infrastructure investments to improve passenger urban mobility and freight movement. It will be implemented in two phases addressing short and long-term solutions to the critical needs of the current IWT system. The first phase (subcomponent C.1) provides investments that are urgently needed to support the IWT system. The second phase (subcomponents C.2 and C.3) deals with long-term improvements to the efficiency and safety of IWT through infrastructure investments. Subcomponent C.1 Improve infrastructure capacity of the existing network USD 40 Million Activities under this subcomponent are intended to support the capacity of the existing system including, inter alia: a. Pontoons, gangways and turnstile gates to enhance the capacity existing jetties. 26 sites have been selected, and the expected value of this investment is USD 18.64 million; b. 22 new passenger ferries will be built based on the design with improved safety standards and fuel efficiency at an expected cost of USD 9.28 million; And c. Electronic smart ticketing gates at 40 jetties at an expected cost of USD 8.85 million. Subcomponent C.2 Enhancing Passenger Movement USD 40 Million This subcomponent includes long-term investments to be identified in the ISDP including inter alia: a. terminals jetties, road access and ancillary infrastructure in addition to other investments required to ensure navigable fairways; b. improved design of inland water transport vessels and solutions to modernize the fleet; and c. System management (e.g. river information systems integrated with the national river information system and the port information system).The exact number of jetties and their locations will be determined after analysis of economic benefits, access, intermodal connectivity, and social and environmental impacts.

Introduction Page 16 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

The ISDP will offer a phased approach to private sector solutions to vessel financing, and this subcomponent will create a pilot project demonstrating the solutions. Subcomponent C.3 Improving Infrastructure Capacity for Freight Movement USD 35 Million These investments will provide an alternative for truck movement, focusing on decongesting vehicular movement by facilitating access across the Hooghly River. Investments will include, inter alia: a. roll on-roll off (ro-ro) jetties, terminals, and road access; b. design and financing solutions for private participation in ro-ro vessels, and c. system management. Locations where connectivity across the river can be effectively utilized to enhance cargo movement have been identified based on preliminary assessment and demand. The exact number of jetties and their locations will be determined after analysis of economic benefits, access, intermodal connectivity, and social and environmental impacts through the ISDP. While there are no ro-ro vessels currently operating, market demand studies indicate the potential for a private sector solution. This component will aim to create a pilot project to increase the number of ro-ro vessels in operation as part of the private sector solution.

1.2.4 Component D: Support to Implementation (estimated cost USD 7 Million) This component will finance technical assistance and advisory services to the PMU and the Steering Committee (SC), including project management and coordination costs associated with project implementation, consultancy services for feasibility, conceptual, and detailed designs, safeguards instruments for subprojects, and the preparation of follow-on operations. It will provide for mobilization of expertise, exchange of international experience, and advisory services to support the SC (and the Logistics Council once established) in preparing and adopting a shared vision focused on improving logistics and developing a coordinated roadmap of future investments and key policy reforms needed to realize that vision. This component will include capacity development and policy support on climate mitigation and adaptation through specific consultancies, knowledge events, and staff training.

1.3 Project Beneficiaries

The four main beneficiary groups of the proposed Project are: i. the users of passenger ferry services; ii. private vessel owners and operators through fleet modernization and upgrading of facilities; iii. government employees in the institutions of the sector who will be trained to fulfil more effective and focused roles in the new institutions in industry; iv. shippers of goods to/from West Bengal to its adjacent states (Jharkhand, Bihar, and Uttar Pradesh) and countries (Bangladesh, Nepal, Bhutan).

1.4 Project Investments under First Year Investments

Of the overall project scope, activities covering 30% of the project budget is to be taken up under the First Year Investments (~USD 45 Million). Following are subprojects to be supported as a part of the First Year Investments: 1. Improving the capacity of selected jetties by adding pontoons and gangways;

Introduction Page 17 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

2. Implementing minor waterside construction works to install gangways & pontoons; 3. Adding new vessels with enhanced designs to existing fleet; 4. Installing turnstile gates in selected jetties. The projects to be taken up under First Year Investments are further discussed in Chapter 3.

1.5 Purpose of the Report

This ESIA is carried out as part of the process of compliance with the World Bank Safeguard Policies in relation to the proposed development activities. The ESIA studies the existing environmental and social conditions and provides an understanding of the likely impacts (adverse as well as positive) to the environmental and social conditions at the project area. The ESIA suggests measures needed to be put in place to prevent/minimise the likely environmental and social impacts due to the proposed project development activities. Also, the ESIA helps formulate and provide a suggested Environmental and Social Management Plan (ESMP). This ESMP will form a part of the project developments tender/bid documents and will form the basis for the selected contractor(s) to prepare the Operational ESMP to be implemented during project execution stage. The scope/objective of this study is to carry out the Environmental and Social Impact Assessment (ESIA) and prepare the ESMP for the proposed development involving “Construction of new jetties and upgradation of existing jetties with improved facilities and amenities”. The study is carried out in line with applicable World Bank, National and West Bengal State Government Policies/Regulations on Environmental, Social, Health and Safety Management.

1.6 Details of Project Proponent

West Bengal Transport Infrastructure Development Corporation Limited (WBTIDCL) is the implementing agency of the proposed development project. WBTIDCL is a fully owned GoWB company/agency and administered by the Transport Department, GoWB. WBTIDCL has been set up with the aim of making it a dedicated Engineering Wing for taking up development works in the Transport Department. Main activities of WBTIDCL are classified into following broad categories: • Execution of Schemes under Transport Department o Traffic Operation and Improvement Program (TOIP) o Road Safety Schemes o Inland Water Transport Development Schemes • Execution of Centrally Sponsored Schemes in Transport Sector • Execution of Projects of other departments of State Government as Deposit Works • Implementation of Transport Infrastructure Project through following modes:- o With Loan Assistance from Bank/Financial institutions o Through Joint Venture with Private Developers o Build, Operate and Transfer (BOT) basis • Participation in Joint Venture Companies for developing transport infrastructure and other real estate projects in the State of West Bengal • To provide consultancy services to other Government organizations and also to other public or private bodies for development of transport infrastructure projects, real estate etc. in the matter of preparing project reports, techno-economic feasibility studies, procurement and project management, etc.

Introduction Page 18 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

1.7 Methodology Applied

The methodology is based on the requirements of the applicable National Policies, World Bank Safeguard Policies as well as the ToR for the ESIA study provided by the client (WBTIDCL) has been considered in the methodology for the study. Also, the methodology adopted for the study uses the consultants overall experience in carrying out such studies. Accordingly, the methodology involved in this study included: • Site Reconnaissance • Preliminary Environmental and Social Screening o The Environmental and Social Screening forms are provided as Appendix 1. • Review of Applicable Legislation • Other available/relevant secondary data, information resources, including other ESIA studies available as reference (Data collection is carried out within the defined Project Study Area (Section 1.7.1)) • Analysis of alternatives wherever feasible • Stakeholder Consultations • Data Collection • Identification of Potential Impacts and suggestion of Mitigation Measures (Considering the small scale of activities to be taken up under the First Year of Investments, the Potential Impacts are assessed within the defined Project Influence Area (Section 1.7.2)) The ESIA study has been carried out considering the Design, Construction and Operational stages of the project. In each stage, anticipated impacts due to proposed development on the environment and social components have been assessed and appropriate mitigation measures have been suggested and formulated in the ESMP. The site assessments, data collection, stakeholder consultations, etc. as part of the ESIA study have been carried out between October 2019 and January 2020.

1.7.1 Project Study Area Proposed development is to be carried out at selected jetty locations along the Hooghly River banks. The study area considered while carrying out the ESIA along the North-South direction is between Roychak and Tribeni. Noorpur (5km to the west of Roychak) is the last jetty location on the South and is near the confluence of the which flows into the Hooghly River near Gadiara (jetty location on opposite bank across Noorpur). The last jetty location in the North under the current ESIA study for First Year investments is at and Tribeni is more than 100 kms beyond this location. However, the overall study area is considered up to Tribeni. Proposed development can technically be seen as a linear project, although developments are not to be taken up throughout the linear length. As per the MoEF&CC guidelines for Highway projects, secondary data should be collected within 15 km aerial distance of the project area3. Considering the significantly small scale of activities to be taken up under the First Year Investments, the study area on the east-west direction has looked into major ecologically sensitive areas present within about 10 kms on either side of the bank.

3 Environmental Impact Assessment Guidance Manual for HIGHWAYS, prepared by Administrative Staff College of India, February 2010

Introduction Page 19 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

The study area, although not anticipated to be influence by impacts of prosed development, if any, has been looked into to get an overall understanding of the project area and its surroundings.

1.7.2 Project Influence Area Proposed development involved infrastructural enhancement works at identified jetty locations along the Hooghly River (see figure 1). Works at the jetty locations under the First Year of investments will be limited to minor waterside construction works to install the gangways and pontoons. As such the Project Influence Area will be limited to the actual area of the works and its immediate surroundings where, impacts if any, would likely occur. Similarly, in the case of the vessels, pontoons and gangways, which would be manufactured at yards, the Project Influence Area also would be limited to the actual yard area and its immediate surroundings where, impacts if any would likely occur.

1.8 Structure of the Report

The ESIA Report is structured as follows: • Executive Summary • Chapter 1: Introduction • Chapter 2: Policy and Legal Framework • Chapter 3: Description of First Year Investments • Chapter 4: Baseline Scenario • Chapter 5: Analysis of Alternatives • Chapter 6: Potential Impacts and Mitigation Measures • Chapter 7: Stakeholder Consultations & Information Disclosure • Chapter 8: Environmental and Social Management Plan • Chapter 9: Conclusions

1.8.1 Executive Summary This chapter will provide the overall Executive Summary of the ESIA Report. This chapter will subsequently be translated to the local language (Bengali) which will be used for project disclosure purpose as per the World Bank requirements.

1.8.2 Introduction The project introduction, purpose of this study, project proponent details are provided in this chapter / Chapter 1.

1.8.3 Policy and Legal Framework The applicable World Bank, National and West Bengal State Government policies/regulations on Environmental, Social, Health and Safety Management are discussed in Chapter 2.

1.8.4 Description of First Year Investments The description of the project activities to be taken up under the First Year of Investments is discussed in Chapter 3.

Introduction Page 20 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

1.8.5 Baseline Scenario The baseline environmental status of the project area based on site reconnaissance and available secondary data has been reviewed and presented. The baseline environmental and social conditions are discussed in Chapter 4.

1.8.6 Analysis of Alternatives To ensure sustainable development under the given conditions, the analysis of alternatives considered for the proposed development is discussed and presented in Chapter 5.

1.8.7 Potential Impacts and Mitigation Measures The environmental and social impacts which are likely to arise due to the proposed development during the design, construction and operation stages have been assessed. Appropriate mitigation measures to prevent/minimize the likely environmental and social impacts due to the proposed project development activities have been suggested. The likely impacts and mitigation measures are discussed and presented in Chapter 6.

1.8.8 Stakeholder Consultations & Information Disclosure The methodology adopted in the study included carrying out stakeholder consultations. Details of stakeholder consultations are presented in Chapter 7.

1.8.9 Environmental and Social Management Plan Environmental and Social Management Plan (ESMP) for design, construction and operation phases of the project has been formulated based on the identified likely impacts and suggested mitigation measures. The ESMP is discussed and presented in Chapter 8. The ESMP also includes the Environmental Monitoring Program.

1.8.10 Conclusions & Recommendations Based on the ESIA study, the conclusions as per the consultants understanding is presented in Chapter 9.

Introduction Page 21 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

2 Policy and Legal Framework India has a well-defined institutional and legislative framework covering various parameters including the Environmental and Social components. Similarly, World Bank also has defined its Environmental and Social Safeguard Operational Policies. This section discusses applicability of some policies/frameworks that will be relevant to this proposed development.

2.1 EIA Notification

Ministry of Environment, Forest and Climate Change’s (MoEF&CC) through its EIA Notification, 2006 (as amended), provides a list of projects or activities which require prior Environmental Clearance. These projects/activities also include River Valley Projects, Ports, Harbours, Highways, Building and Construction Projects (built-up area >20,000 sq. mtrs), in addition to few other projects/activities. The list of projects/activities that require prior Environmental Clearance is provided as Appendix 2. Proposed development is construction/establishment of a jetty structure only along with the gangway, floating pontoon, link, and associated facilities like toilets, ticket counters and passenger waiting area. Total area of development in terms of square meters will be very minimal. As such, the proposed development activity does not fall under the purview of the EIA Notification needing an Environmental Clearance.

2.2 CRZ Notification

Through the CRZ Notification, the Ministry of Environment and Forests & Climate Change (MoEF&CC), Government of India imposed certain restrictions on setting up and expansion of industries, operations or processes, etc. in the Coastal Regulation Zone (CRZ). The CRZ is area influenced by tidal action (in the landward side) up to 500 metres from the High Tide Line (HTL) and the land between the Low Tide Line (LTL) and the High Tide Line (HTL). Based on available Coastal Zone Management Plan (CZMP) of West Bengal, dated 27th September 1996, the proposed development is falling beyond demarcated CRZ limits. Also, based on secondary data information, the project development area is beyond the CRZ limits. As such the CRZ Notification will not be applicable for the proposed development needing the CRZ Clearance.

2.3 Forest and Wild Life Acts As per assessment of the project locations and information seen on Google Imageries, there are no identified Reserve Forests/Wild Life Protected Areas at the jetty location as well as along proposed development corridor. As such, diversion of Forest Land/Wild Life areas will not be applicable for proposed development requiring Forest Clearance/Wild Life Clearance.

2.4 The Water (Prevention & Control of Pollution) Act, 1974

This act provides for prevention and control of water pollution and maintaining and restoring of wholesomeness of water. The Act seeks to have in place certain measures/ responsibilities which include managing water quality and effluent standards, as well as monitoring water quality, prosecuting offenders and issuing licenses for construction and operation of various facilities. Proposed development will involve activities at for manufacturing of vessels,

Policy and Legal Framework Page 22 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments gangways and pontoons. In addition there would be minor civil works at jetty locations as well. As such, proposed development project will need to obtain the necessary Consent to Establish (CTE) and Consent to Operate (CTO) from West Bengal State Pollution Control Board prior to commencement of project activities on site.

2.5 The Air (Prevention & Control of Pollution) Act, 1981

This act provides for prevention, control and abatement of air pollution. The SPCB is empowered to set air quality standards and monitor and prosecute offenders under The Air (Prevention and Control of Pollution) Act, 1981. As proposed development will involve activities for manufacturing of vessels, gangways and pontoons as well as minor civil works at jetty locations, it will be needed to obtain the necessary Consent to Establish (CTE) and Consent to Operate (CTO) from West Bengal State Pollution Control Board prior to commencement of project activities on site.

2.6 Noise Pollution Act/Rules

The Noise Pollution (Regulation And Control) Act, 1990, Noise Pollution (Regulation and Control) Rules 2000 Noise Pollution (Regulation and Control) (Amendment) Rules 2010 aim at control/regulation of noise pollution. Proposed development will involve several activities which will generate noise. As such, consent required for not causing noise pollution during project design/construction and its operation will need to be obtained for the proposed development.

2.7 Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016

The Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016 aims to protect the general public against improper handling and disposal of hazardous wastes. The proposed development will likely involve management of hazardous wastes. As such, the provisions of the Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016 will be applicable to the proposed development.

2.8 The Motor Vehicle Act, 1988

The Motor Vehicle Act, 1998, empowers State Transport Authority to enforce standards for vehicular pollution. From August 1997 the "Pollution Under Control” Certificate is issued to reduce vehicular emissions. Proposed development activities will engage several vehicles (transport of materials, worker movements, etc.). As such, provision of The Motor Vehicle Act, 1988 will be applicable for the proposed project development.

2.9 Chemical Accidents (Emergency Planning, Preparedness and Response) Rules, 1996

The Chemical Accidents (Emergency Planning, Preparedness and Response) Rules, 1996 provides protection against chemical accidents while handling hazardous chemicals.

Policy and Legal Framework Page 23 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Proposed development will involve handling of hazardous (flammable, toxic and explosive) chemicals during the project manufacturing/construction activities. As such, provisions of this Act will be applicable for the proposed development.

2.10 Public Liability and Insurance Act 1991

The Public Liability and Insurance Act has been enacted for the purpose of providing immediate relief to persons affected by accidents while handling hazardous substances and other incidents. The project is being carried out in mainly urban areas where there are already existing vessel movements as well as several other human activities at the jetty locations (vendors, locals moving around, etc.). Protection to general public from the accidents due to hazardous material (especially if any used at the vessel yards, gangway/pontoon manufacturing units) is essential. As such, provisions of this Act shall be applicable for the proposed development.

2.11 Kolkata Port Trust Guidelines

A National Green Tribunal (NGT) order dated 13.09.2017, has directed Kolkata Port Trust (KoPT) to ensure Environmental and Social Impact Assessments are done for all investments in the KoPT jurisdiction of Hooghly River. Accordingly, an order has been formulated under the Major Port Trusts (MPT) Act. “Under Section 46(1) of the MPT Act, prior permission of KoPT Board is required for making erecting or fixing within the port limits or port approaches any wharf, dock, quay, stage, jetty, pier, erection or mooring or undertaking any reclamation of foreshore within the said limit”. The stretch of proposed development corridor falls in the waters of Hooghly River which is within the jurisdiction of the Kolkata Port Trust (KoPT). As per KoPT guidelines, the “Port Limit is that part of River Hooghly and shores thereof as are within 45.7 mtrs of High Water Mark at Spring Tide”. This portion of the Port Limits is leased to other agencies for the development of public purpose projects. As such, development in these areas will need necessary approvals/clearances from KoPT. As part of the current study, based on the requirement of KoPT, necessary documents will be submitted to KoPT (EIA/EMP report) for the approval process.

2.12 Environmental Legislations

Government of India has formulated various policy guidelines, acts and regulations aimed at protection and enhancement of environmental resources as discussed in above section. Table 2-1 provides a summary of the relevant/applicable legislations (as discussed above) pertaining to the project that will have varying degrees of applicability. Table 2-1: Relevant Environmental Laws & Regulations Implementing / S. Law / Regulation / Reason for Relevance Responsible No. Guidelines Application Agency 1 The Environmental Umbrella Act. Protection All environmental MoEF&CC, State (Protection) Act. 1986, and Improvement of the notifications, rules and Department of and the Environmental environment. schedules are issued Environment & (Protection) Rules, under the act Forest, CPCB and (proposed SPCB

Policy and Legal Framework Page 24 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Implementing / S. Law / Regulation / Reason for Relevance Responsible No. Guidelines Application Agency 1987-2002 (various development under amendments) Fist Year investments does not need Environmental Clearance) 2 Coastal Regulation To restrict development Obtaining CRZ State Coastal Zone Zone (CRZ) activities and act as primary Clearance for projects Management Notification, 2011 regulation for conservation within CRZ limits Authority/CZMA, and protection of India's (proposed MoEF&CC coastline and protection of development under coastal livelihoods Fist Year investments are beyond CRZ limits and do not need CRZ Clearance) 3 The Water (Prevention Central and State Pollution Consent required for State Pollution & Control of Pollution) Control Board to establish/ not polluting ground Control Board Act,1974 enforce water quality and and surface water effluent standards, monitor during project water quality, prosecute design/construction offenders, issue licenses for and its operation (will construction/operation of need to confirm to certain facilities. applicable standards) 4 Air (Prevention and To control air pollution by Consent required for State Pollution Control of Pollution) controlling emission and air not causing air Control Board Act, 1981 & 1987 pollutants according to pollution during project (amendment) prescribed standards design/construction and its operation (will need to confirm to applicable standards) 5 Noise Pollution Noise pollution regulation Consent required for State Pollution (Regulation And and controls not causing noise Control Board Control) Act, 1990 pollution during project Noise Pollution design/construction (Regulation and and its operation (will Control) Rules 2000 need to confirm to Noise Pollution applicable standards) (Regulation and Control) (Amendment) Rules 2010 6 Forest (Conservation) Conservation and definition Diversion of forest State Forest Act, 1980 of forest areas. Diversion of land is not envisaged Department/ forest land follows the in proposed MoEF&CC process as laid by the act development 7 Hazardous and Other Protection to the general Proposed State Pollution Wastes (Management public against improper development will likely Control Board and Transboundary

Policy and Legal Framework Page 25 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Implementing / S. Law / Regulation / Reason for Relevance Responsible No. Guidelines Application Agency Movement) Rules, handling and disposal of involve management 2016 hazardous wastes of hazardous wastes 8 The Motor Vehicle Act. Empowers State Transport All vehicles used for State Motor 1988 Authority to enforce proposed Vehicles standards for vehicular development activities Department pollution. From August will need to comply 1997 the "Pollution Under with the provisions of Control Certificate is issued this act. to reduce vehicular emissions. 9 Chemical Accidents Protection against chemical Handling of hazardous District & Local (Emergency Planning, accident while handling (flammable, toxic and Crisis Group Preparedness and hazardous chemicals explosive) chemicals headed by the DM Response) Rules, during project and SDM 1996 design/construction and operation 10 Public Liability and This Act has been enacted Protection to general District Collector Insurance Act 1991 for the purpose of providing public from the immediate relief to persons accidents due to affected by accidents while hazardous material handling hazardous (especially if any used substances and other at the vessel yards, incidents. gangway/pontoon manufacturing units) 11 National Green NGT has been established Proposed KoPT Tribunal (NGT) Orders under the NGT Act 2010 for development activities effective and expeditious at the jetty locations disposal of cases relating to are in the KoPT environmental protection jurisdiction of Hooghly and conservation of forests River; hence NGT and other natural requirements will have resources. to be met as per KoPT guidelines. • NGT has ordered KoPT to ensure Environmental and Social Impact Assessments are done for all investments in the KoPT jurisdiction of Hooghly River

Policy and Legal Framework Page 26 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

2.13 Inland Waterways Regulations/Guidelines

2.13.1 The National Waterway Act, 2016 The National Waterway Act, 2016 is an Act to make provisions for existing national waterways and to provide for declaration of certain inland waterways to be national waterways and also provide for regulation and development of said waterways for purposes of shipping and navigation and for matters connected therewith or incidental thereto. Proposed development is along the waters of the stretch of NW-1. As such, The National Waterway Act, 2016 will be applicable to the development.

2.13.2 Prevention of Collision on National Waterways Regulations, 2002 The Prevention of Collision on National Waterways Regulations, 2002 shall apply to all vessels plying on the National Waterways. All vessels plying in the National Waterways shall adhere to these rules having regard to precautions required by the ordinary practice of Seamen and limitations of the vessel. Proposed development is along the waters of the stretch of NW-1. As such, the Prevention of Collision on National Waterways Regulations, 2002 will be applicable to the development.

2.13.3 National Waterways, Safety of Navigation and Shipping Regulations, 2002 The National Waterways, Safety of Navigation and Shipping Regulations, 2002 is aimed to ensuring safety during navigation on the national waterways. Proposed development is along the waters of the stretch of NW-1. As such, the National Waterways, Safety of Navigation and Shipping Regulations, 2002 will be applicable to the development.

2.13.4 National Disaster Management Guidelines on Boat Safety, September 2017 The National Disaster Management Guidelines on Boat Safety is a guideline provided by the National Disaster Management Authority Government of India. The guidelines addresses all facets of boat safety such as weather forecasting & early warning system, safety standards & specifications, regulatory & legal issues, search & rescue, capacity development and do’s & don’ts for boat safety has been elaborated in details in the guidelines. The regulations/guidelines applicable for Vessels plying in Inland Waterways are listed in Table 2-2. Table 2-2: Regulations Applicable for Inland Waterways Name Key Requirements Applicability The National Waterway Act, 2016 Regulation and development of rivers for navigation Prevention of Collision on National Precautions required for vessels and Waterways Regulations, 2002 crew members Applicable for all vessels National Waterways, Safety of Navigation Ensuring safety during navigation on the plying in IWT and Shipping Regulations, 2002 national waterways National Disaster Management Guidelines Guidelines help in improving Boat on Boat Safety, September 2017 Navigation Safety whether mechanized or non-mechanized

Policy and Legal Framework Page 27 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

2.14 Land Acquisition/R&R

Proposed development activities under the First Year investments are to be taken up within lands belonging to the government. No private land will be involved. Proposed project will not involve Land Acquisition. However, at some jetty locations, the presence of vendors/squatters at the jetties was noticed. The need for any R&R related to temporary displacement of such vendors, squatters, encroachers, etc. is being assessed. These will be assessed and addressed accordingly as per applicable Land Acquisition, Rehabilitation and Resettlement (LARR) Act, 2013 and applicable World Bank Safeguard Policies.

2.15 Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013

The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act (RFCTLARR) extends to the whole of India except the State of Jammu and Kashmir. The act provides for a transparent process and fair compensation in land acquisition for public purpose and provides for rehabilitation and resettlement of land owners and those affected by land acquisition. It comprises four schedules that provide the minimum applicable norms for compensation based on market value, multiplier and solatium; Resettlement and Rehabilitation (R&R) entitlements to land owners and livelihood losers; and facilities at resettlement sites for displaced persons, besides providing flexibility to states and implementing agencies to provide higher norms for compensation and R&R.

2.16 Memorandum - Direct Land Purchase from Land Owners State Government and also the Central Government department(s) or its organisation (s) based on merit of its project to go in for the direct purchase of land for public purpose mainly involving the early commissioning of infrastructure projects like roads, railways, bridges, food godowns, drinking water, flood protection works and other similar projects, as the Government may consider, in rural and / or urban areas through Zilla Parishad/ Municipality/Municipal Corporation/other Government bodies and parastatals, as the case may be, by adopting, the following given procedures. Land required for the project (development of access road to ro-ro service locations, and others, if any in subsequent years of investment) may be directly purchased from land owners as per the provisions of this memorandum, “Memorandum: No. 756-LP/1A-03/14(Pt-II) Date: 25.02.2016 - direct land purchase from land owners, Land and Land Reforms Department, Govt. of West Bengal”. Although direct purchase is part of the LARR Act 2014, this State Government memorandum has expanded the provisions, state specific and made it more workable.

2.17 The Right to Information Act, 2005

The Act provides for setting out the practical regime of right to information for citizens to secure access to information under the control of public authorities, in order to promote transparency and accountability in the working of every public authority, the constitution of a Central Information Commission and State Information Commissions and for matters connected therewith or incidental thereto.

Policy and Legal Framework Page 28 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

2.18 Kolkata Gazette – Multiplication Factor

The Kolkata Gazette No. 2083LA/3M-49/14, dated 30.07.2014, provides for Multiplication Factor notified by the State Governments in compliance to Sr. No. 2 of the First Schedule to the RFCTLARR Act, 2013 in the State of West Bengal.

2.19 The West Bengal Inland Fisheries Act, 1984

The West Bengal Inland Fisheries Act, 1984, is an Act which provides conservation, development propagation, protection, exploitation and disposal of inland fish and fisheries in West Bengal and for matters connected therewith and thereto.

2.20 West Bengal Minimum Wages Rules, 1951

The West Bengal Minimum Wages Rules, 1951 provides the scope of employment and defines the minimum wage of the employee.

2.21 World Bank Safeguard Policies and Guidelines The physical components of the proposed development project will be limited to establishment of the jetty structure, gangway/link platform and floating pontoon. For the structure there would be need of concrete piles/pillars. There will most likely be some dismantling of existing structures as well. Proposed development is envisaged to be carried out within lands belonging to the government. No land acquisition is envisaged. Temporary impacts to vendors/squatters at some of the locations could be likely during construction /redevelopment of the facilities. This will be assessed and addressed accordingly. In addition, proposed activities will involve vessel manufacturing at the vessel yards as well as manufacturing/fabrication of the gangways and pontoons. The below mentioned World Bank’s Operational Policies (OP’s) and Requirements on environmental and social safeguards have been reviewed during the screening stage. The applicability of the OP’s is discussed in this report. Subsequent stages of the study will be carried out meeting requirements of the identified OP’s and appropriate measures will be framed and included in the ESMF for proposed development. • OP/BP 4.01: Environmental Assessment • OP/BP 4.04: Natural Habitats • OP/BP 4.36: Forests • OP/ 4.09: Pest Management • OP/BP 4.11: Physical Cultural Resources • OP/BP 4.10: Indigenous Peoples • OP/BP 4.12: Involuntary Resettlement • OP/BP 4.37: Safety of Dams • OP/BP 7.50: Projects on International Waterways • OP/BP 7.60: Projects in Disputed Areas Of the above mentioned Operational Policies, the triggered safeguard policies for this project are discussed below:

Policy and Legal Framework Page 29 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

2.21.1 Environmental Assessment (OP/BP 4.01) Environmental Assessment is used in the World Bank to identify, avoid, and mitigate the potential negative environmental and social impacts associated with Bank’s lending operations early on in the project cycle. This policy is triggered if a project is likely to have potential adverse environmental and social risks and impacts in its area of influence. The environmental and social issues are likely to arise both during construction and operation stages of this project. The likely impacts would include air pollution, water pollution, increase in noise levels, etc. during construction activities as well as manufacturing/ fabrication of the vessels, gangways and pontoons. The ESMP will meet the requirements of this OP.

2.21.2 Natural Habitats (OP 4.04) Any project with the potential to cause significant conversion (loss) or degradation of natural habitats, whether directly or indirectly would trigger this OP. The Gangetic River Dolphin (GRD), or the Platanista gangetica, is an endangered species according to the International Union for Conservation of Nature (IUCN) which is found in the Ganga-Brahmaputra-Meghna and Karnaphuli-Sangu river systems of Nepal, India and Bangladesh. The Hooghly River is a distributary system of the overall Ganga River system and also has presence of the GRD. As jetty locations of the proposed development are within the Hooghly River, the OP on Natural Habitats is triggered. The ESMP as a whole will contribute to the natural habitat conservation which will include mitigation measures to address likely impacts to Dolphins.

2.21.3 Physical Cultural Resources (OP/BP 4.11) For purposes of this policy, “Physical Cultural Resources” are defined as movable or immovable objects, sites, structures, groups of structures, natural features and landscapes that have archaeological, paleontological, historical, architectural, religious, aesthetic, or other cultural significance. This policy assists to avoid or mitigate adverse impacts of development projects on Physical Cultural Resources. Several jetty locations have religious structures (mostly temples) at the project location. Designs for the proposed development will take this into consideration. Accordingly, this OP on “Physical Cultural Resources” is triggered. A Chance Find Procedure to meet the requirements of this OP is included as Appendix 3.

2.21.4 Involuntary Resettlement (OP/BP 4.12) This policy is triggered if the project will involve involuntary taking of land and involuntary restrictions of access to property, protected areas, etc. The policy aims to avoid involuntary resettlement to the extent feasible, or to minimize and mitigate its adverse social and economic impacts. Proposed development will not involve land acquisition under the First Year investments. However there will be minimal temporary resettlements involved with squatters/ vendors operating at some of the jetty locations. As such this OP has been triggered. A project specific RPF has been prepared to address issues under the OP.

Policy and Legal Framework Page 30 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

2.21.5 Projects on International Waterways (OP/BP 7.50) The project and its influence area is located within the Ganga basin - a basin shared by riparian countries of China, Nepal and Bangladesh. As per the requirements of OP/BP 7.50, the riparians have been notified of the due proposed development.

2.21.6 World Bank’s EHS Guidelines Though not an Operational Policy, the World Bank’s Environment, Health & Safety (EHS) guidelines are relevant to the manufacture of the vessels, pontoons and gangways as well as the civil works to be done under the proposed development. During subproject assessments, these guidelines will be used to ensure effective EHS management under the project. The World Bank Groups EHS Guidelines are technical reference documents with general and industry specific examples of Good International Industry Practice. World Bank has a General EHS Guidelines document as well as Industry specific EHS guidelines. The General EHS guidelines provide guidance to users on common EHS issues potentially applicable to all industry sectors. The industry specific EHS guidelines are designed to be used together with the General EHS Guidelines. The EHS Guidelines contain the performance levels and measures that are generally considered to be achievable in new facilities by existing technology at reasonable costs. The applicability of the EHS Guidelines should be tailored to the hazards and risks established for each project on the basis of the results of an environmental assessment. When host country regulations differ from the levels and measures presented in the EHS Guidelines, projects are expected to achieve whichever is more stringent.

2.21.6.1 General EHS Guidelines

The General EHS Guidelines4 contain the following information: 1. Environmental 2. Occupational Health and Safety 1.1 Air Emissions and Ambient Air Quality 2.1 General Facility Design and Operation 1.2 Energy Conservation 2.2 Communication and Training 1.3 Wastewater and Ambient Water Quality 2.3 Physical Hazards 1.4 Water Conservation 2.4 Chemical Hazards 1.5 Hazardous Materials Management 2.5 Biological Hazards 1.6 Waste Management 2.6 Radiological Hazards 1.7 Noise 2.7 Personal Protective Equipment (PPE) 1.8 Contaminated Land 2.8 Special Hazard Environments 2.9 Monitoring 3. Community Health and Safety 4. Construction and Decommissioning 3.1 Water Quality and Availability 4.1 Environment 3.2 Structural Safety of Project Infrastructure 4.2 Occupational Health and Safety 3.3 Life and Fire Safety (L&FS) 4.3 Community Health and Safety 3.4 Traffic Safety 3.5 Transport of Hazardous Materials 3.6 Disease Prevention 3.7 Emergency Preparedness and Response

4 General: https://www.ifc.org/wps/wcm/connect/29f5137d-6e17-4660-b1f9-02bf561935e5/Final%2B- %2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES&CVID=jOWim3p

Policy and Legal Framework Page 31 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

2.21.6.2 Industry Specific EHS Guidelines The proposed development project is construction/redevelopment of jetties. As such, the EHS Guidelines for Ports, Harbors, and Terminals5 are applicable to this project.

5 Ports, Harbors and Terminals: https://www.ifc.org/wps/wcm/connect/ddfac751-6220-48e1-9f1b- 465654445c18/20170201- FINAL_EHS+Guidelines+for+Ports+Harbors+and+Terminals.pdf?MOD=AJPERES&CVID=lD.CzO9

Policy and Legal Framework Page 32 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

3 Description of First Year Investments Government of West Bengal (GoWB) is promoting Inland Waterways Transportation through its network of rivers and canals. GoWB, through Government of India has applied for financing from the World Bank for financial assistance for improvement/ development of the inland water transport system in the state. Of the entire project budget, 30% of the budget (~USD 45 Million) is proposed to be taken up under First Year of Investments. Details of First Year Investment are discussed below.

3.1 First-Year Investments 30% of the overall project budget is proposed to be taken up under First Year of Investments. Under the investments requested for the First Year, the proposed developments will include “Construction of new jetties and upgradation of existing jetties that would have improved facilities and amenities for both passenger and goods movements”. The subprojects that will be supported as a part of the First-Year investments are: • Improving the capacity of selected jetties by adding pontoons and gangways • Implementing minor waterside construction works to install gangways and pontoons • Adding new vessels with enhanced designs to existing fleet • Installing turnstile gates in selected jetties

3.1.1 Gangways and Pontoons Pontoons and Gangways are proposed to be added at selected jetties to improve the capacity of the jetties. Gangways and Pontoons are proposed to be added at 30 selected jetty locations. The Pontoons and Gangways will be manufactured/fabricated at the selected contractors manufacturing/fabricating unit(s). Subsequently, these will be brought to the respective jetty locations and installed at the site. Pontoons and gangways are added to existing ones in these locations to improve the capacity and safety of passengers. When there is a need to remove existing pontoons and/or gangways, they will be taken out and re-used at another existing or new jetty location under WBTC (not part of the proposed development activities). Those that cannot be reused, will be sold to local companies in the market who are specialized in reusing the material. The Pontoons will be of uniform dimensions across all selected jetties. The size of the Pontoons shall be 30 m length x 9 m width. Similarly, all gangways shall be of uniform size of (30 m length, 3.5 m width and 2.9 m height).

Description of First Year Investments Page 33 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Exhibit 3-1 Typical Gangway (Existing) Exhibit 3-2 Pontoon Structure (Existing)

3.1.2 Waterside Construction Works Proposed developments activities will include minor waterside construction works mainly needed to put in place the new pontoons and gangways. In general, and because of the tidal nature of the Hooghly river, pontoons are designed to be floating and cannot be pinned to the ground. Gangways are supported by the pontoons on one side and linked to the existing jetty on the landside in a manner that allows vertical and horizontal movement caused by the high river waves. Depending on the length of the gangway, very small number of piles might be added to provide support.

3.1.3 New Vessels First Year project investments will include modernizing the fleet through the introduction of new vessels with enhanced designs. New vessels will be an addition to the existing fleet. Investments will include addition of Twenty (20) cross movement vessels of 100 passenger capacity and Two (02) longitudinal movement vessels also of 100 passenger capacity. Cross movement and longitudinal movement vessels have the same features; however the engine power and dimensions differ. The vessels shall be of twin screw self-propelled steel hull configuration with twin engines. The will be built based on enhanced design that is inclusive with improved safety standards and fuel efficiency. The vessels will be built at selected contractor’s vessel building yard(s). Subsequently, vessels will be deployed at respective jetty locations for operation.

Description of First Year Investments Page 34 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Exhibit 3-3 New Vessel

3.1.4 Turnstile Gates

Installation of Turnstile Gates at 40 selected jetty locations are proposed to be taken up under the First Year of investments. These are standard turnstile gates that are in use in a range of transport terminals, particularly seen in city metro stations. The turnstile gates will be built at the selected supplier’s production unit(s). These will essentially be the same across all jetties and produced at the production facility in as many numbers as per the requirement. Subsequently, these would be brought onto the jetty locations for its installation.

Exhibit 3-4 Turnstile Gates (at Howrah) Exhibit 3-5 Smart Chip For Gate Access

3.2 Jetty Locations

A total of 30 Ghats within the Project area are identified to be taken up in the proposed developments under the First Year investments. The Project area is one of the most populous areas in India, stretching for more than 120 km along the Hooghly river from Tribeni, to the north of Kolkata, to Roychak, to the south. The jetty locations are on either side of the Hooghly River, some on the Kolkata side and some on the Howrah side. The list of jetties included (list arranged from North to South) and a map showing the locations is presented as Table 3-1 and Figure 3-1, respectively. Exhibit 3-6 shows some existing features at some jetty locations. Google images of some of the jetty locations are shown as Exhibit 3-7 to Exhibit 3-11.

Description of First Year Investments Page 35 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Table 3-1 List of Selected Jetties (First Year Investments)

Kolkata Side Howrah Side 10. Kashipur (K10) 1. Rashmoni Ghat (K1) 11. Ratan Babu (K11) 1. Bansberia (H1) 2. Halisahar (K2) 12. Barahnagar (K12) 2. Chinsura (H2) 3. Naihati (K3) 13. Shovabazar (K13) 3. (H3) 4. Debitala (K4) 14. Ahiritala (K14) 4. Sheoraphuli (H4) 5. (K5) 15. Armenian Ghat (K15) 5. Shrirampur (H5) 6. /Dhobighat (K6) 16. Chandpal –I (K16) 6. (H6) 7. Titagarh (K7) 17. Chandpal – II (K17) 7. Howrah – I (H7) 8. Khardah (K8) 18. Outram Jetty (K18) 8. Howrah – II (H8) 9. Panihati (K9) 19. Noorpur (K19) 9. Howrah – III (H9) 10. Fulleswar (H10) 11. Gadiara (H11)

Description of First Year Investments Page 36 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Figure 3-1 Jetty Locations

Description of First Year Investments Page 37 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Outram Ghat (Used by Kolkata River Police) Chandpal Ferry Ghat

Concrete Piers for Link Platform at Kardah Jetty Access Road – Barrackpore/Dhobighat Jetty

Link Platform Submerged (Barrackpore Jetty) Small Temple, Banyan Tree at Barrackpore Jetty

Description of First Year Investments Page 38 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

People Waiting on Pontoon – Ghat Panihati Jetty (Gates Closed once Vessel Leaves)

Manirampur Jetty (Pontoon Width is Inadequate) Vessel Completely Full

Different types of Passenger Vessels/Boats Plying across the River Exhibit 3-6 Existing Jetty Locations

Description of First Year Investments Page 39 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Exhibit 3-7 Konnagar Ferry Ghat

Exhibit 3-8 Chandpal Ghat – II

Exhibit 3-9 Bansberia Jetty

Description of First Year Investments Page 40 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Exhibit 3-10 Ahiritola Ghat

Exhibit 3-11 Manirampur Jetty

3.3 Schedule and Cost

Proposed developments discussed above are to be taken up in the First Year of investments. As such, the schedule for this development shall be for a period of one year.

3.3.1 Estimated Cost The estimated costs for proposed developments under First Year of investments are as provided in Table 3-2. Table 3-2 Estimated Cost (First Year Investments) S. Unit Cost (INR No. of Total Cost (INR Total Cost Activity No. in Crores) Units in Crores) (US$ Million) Works at the Jetties (includes Pontoon, 1. ~ 4.00 30 120.00 17.15 Gangway and the necessary Civil Works) 2. 100 Passenger Size Vessels ~ 2.00 20 40.00 5.71 3. Longitudinal Vessels (100 Passenger Size) ~ 2.65 2 5.30 0.75 Turnstile Gates (4 nos. at each of the 40 4. ~ 3.50 40 140.00 20.00 selected jetty locations) First Year Investments Estimated Total 305.30 43.61

Description of First Year Investments Page 41 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

4 Baseline Scenario

4.1 Introduction The baseline/existing environmental and social conditions at the project area are established based on reconnaissance survey, investigations and review of relevant secondary data. This chapter details the profile of the overall project area(s), existing features, climatic conditions, environmental/social aspects, etc. The baseline environmental studies also included analysis of secondary data collected for terrestrial environmental parameters. Terrestrial data presented included the following parameters: • Ambient Air Quality o Particulate Matter <10 micron size (PM10) o Particulate Matter <2.5 micron size (PM2.5) o Sulphur Dioxide (SO2) o Oxides of Nitrogen (NOx) o Carbon Monoxide (CO) • Ambient Noise o Day equivalent noise o Night equivalent noise levels • Inland Water Quality o Groundwater Quality o Surface Water Quality • Soil Quality

4.2 Hooghly River

The Hooghly River traditionally called ‘Kati-Ganga’, is approximately 260 km long (160 mi) distributary of the Ganges River in West Bengal. The Ganges splits into the Padma and the Hooghly near Giria, Murshidabad. Course: The vast majority of the water that flows into the Hooghly River is provided by the man-made Farakka Feeder Canal. The Farakka Barrage is a dam that diverts water from the Ganges into the Hooghly River. In 1974, the Farakka Barrage began diverting water into the Hooghly during the dry season so as to reduce the silting difficulties at Kolkata's Port. Farakka Feeder Canal is located near the town of Tildanga in Murshidabad district. History: The Bhagirathi-Hooghly river system is an essential lifeline for the people of West Bengal. It was through this river that the East India Company sailed into Bengal and established their trade settlement, Calcutta, the capital of British India. People from other countries such as the French, Dutch, Portuguese, etc. all had their trade settlements by the banks of this river. Economics: The river provides a perennial supply of water to the plain of West Bengal for irrigation and human & industry consumption. The river is navigable and a major transport system in the region with a large traffic flow. For a long time, the Calcutta Port was the biggest port of India. The modern container port of , on the intersection of lower Hooghly and Haldi River, now carries much of the region's maritime trade. Present Scenario: The Hooghly- Bhagirathi River is affected due to abstraction of large amount of water for industrial uses. Sewer outlets and drainages, which open into the river

Baseline Scenario Page 42 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments directly, cause resource deterioration6. Water Hardness varied from 90-490 mg/l, the high value of hardness indicates the high pollution load of sewage7. Kolkata Metropolitan Area (KMA) is the major urban agglomeration in the West Bengal. The River Hooghly, the lower most stretch of the river Ganga, forms the principal drainage line for the KMA8. While flowing through this state, the river is receiving both the industrial effluents and domestic effluents from municipal towns located on both banks of the river. The river water is used for various purposes like bathing, washing, fishing, industrial cooling, etc. The river stretch of 100 km between Kalyani and Birlapur in eastern bank and Tribeni and in western bank receives maximum wastewater from approximately 250 outfalls3. Water Quality Index (WQI) values confirmed the prevailing 'bad' condition, detrimental for sustenance of aquatic biota, Wide variations in turbidity, total dissolved solids and fecal coliform exceeded the permissible BIS drinking water level limit9. Fauna: The Gangetic River Dolphin (GRD), an endangered species according to the International Union for Conservation of Nature (IUCN), can be found in the Ganga- Brahmaputra-Meghna and Karnaphuli-Sangu river systems of Nepal, India and Bangladesh. Hooghly River, being a distributary of the main Ganges river system, also has GRD’s in it. Sightings of GRD have been reported in the project corridor along the Hooghly River.

4.3 District Profiles10

Proposed development project falls in Six (06) districts of West Bengal, namely: Hooghly, Howrah, East Medinipur, North and South 24 Parganas and Kolkata. A brief profile of each of the districts is presented below.

4.3.1 Hooghly Hooghly district has its headquarters at Chinsura (Chuchura). The district has four subdivisions: Chinsura Sadar, , , and . The district is flat, with no place having an elevation of more than 200 meters. Hooghly is one of the most economically developed districts in West Bengal. It is the main jute cultivation, jute industry, and jute trade hub in the state. The railway communication of the district, especially at the suburban area, is very developed. According to the 2011 census Hooghly district has a population of 5,520,389. This gives it a ranking of 16th in India (out of a total of 640). The district has a population density of 1,753 inhabitants per square kilometre (4,540/sq mi).

4.3.2 Howrah Howrah district has its headquarters in the City of Howrah. Howrah District is split into the Howrah Sadar subdivision and the Uluberia subdivision. The Howrah Sadar subdivision has 1 municipal corporation and 5 community development (CD) blocks. The Uluberia subdivision

6 Bhuban Mohan Majhi, Ashim Kumar Nath, Chiranjeeb Dey, Ayan Mondal and Nimai Chandra Saha. 2018. Ecological Assessment of Hooghly - Bhagirathi River System through the Study of Diversity of Bivalves and Gastropods in Relation to Physico-chemical Parameters Int.J.Curr.Microbiol.App.Sci. 7(07): 2700-2715. doi: https://doi.org/10.20546/ijcmas.2018.707.317 7 Sharma, K.D., Lal, N. and Pathak, P.D. 1981. Water quality of sewage drains entering Yamuna at Agra. Indian J. Environ. Hlfh., 23: 118 – 122. 8 Dipak Chakraborty (2003),Rapid Estimation of Major Wastewater Discharges to River Hooghly between the stretch of Palta to DhanKheti Khal, West Bengal Pollution Control Board. 9 Mitra S et. al. 2018, Water quality assessment of the ecologically stressed Hooghly River Estuary, India: A multivariate approach. Mar Pollut Bull. 2018 Jan;126:592-599. DOI: 10.1016/j.marpolbul.2017.09.053 10 Source: Wikipedia (viewed on date October 28, 2019)

Baseline Scenario Page 43 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments has 1 municipality and 9 CD blocks. Howrah district is one of the highly urbanized areas of West Bengal. The urbanized sectors gradually increase the slum populations. Howrah is the second largest city and second smallest district after Kolkata. According to the 2011 census Howrah district has a population of 4,841,638. This gives it a ranking of 23rd in India (out of a total of 640). The district has a population density of 3,300 inhabitants per square kilometre (8,500/sq mi).

4.3.3 East Medinipur East Medinipur has its headquarters at . East Medinipur district is divided into the administrative subdivisions of Tamluk, Haldia, and . In 2006 the Ministry of Panchayati Raj named Purba/East Medinipur one of the country's 250 most backward districts (out of a total of 640). It is one of the 11 districts in West Bengal receiving funds from the Backward Regions Grant Fund Program (BRGF). According to the 2011 census Purba/East Medinipur district has a population of 5,094,238. This gives it a ranking of 20th in India (out of a total of 640). The district has a population density of 1,076 inhabitants per square kilometre (2,790/sq mi).

4.3.4 North 24 Parganas North 24 Parganas has its headquarters located at Barasat. District comprises 5 subdivisions: Barrackpore, Barasat Sadar, , Bangaon and Bidhannagar. The electrified suburban rail network of ER is extensive and penetrates far and deep into the neighbouring districts of Kolkata, South 24 Parganas, Nadia, Howrah, Hooghly etc. Metro rail is also transport medium of this district's people. Two stations of are located here, metro station at Dum Dum and Noapara station at Noapara. Netaji Subhash Chandra Bose International Airport, at Dum Dum is also in North 24 Parganas. This is the only airport serving the city Kolkata. According to the 2011 census North 24 Parganas district has a population of 10,082,852. This gave it a ranking of 2nd in India (out of a total of 640) and 1st in its state. However, in 2014 the Thane district (in Maharashtra), which had been ranked 1st in India in 2011, was divided into two, thus promoting North 24 Parganas District to 1st in India. It is the tenth-largest district in the State by area. The district has a population density of 2,463 inhabitants per square kilometre (6,380/sq mi).

4.3.5 Kolkata Kolkata city is the headquarters of the district. In terms of area, it is the smallest amongst all the districts of West Bengal but has the highest density of population. It is only district in the state with cent percent urban population. According to the 2011 census Kolkata district has a population of 4,486,679. This gives it a ranking of 35th in India (out of a total of 640). The district has a population density of 24,252 inhabitants per square kilometre (62,810/sq mi).

4.3.6 South 24 Parganas South 24 Parganas has its headquarters located at Alipore. The district comprises five subdivisions: Alipore Sadar, Baruipur, , Canning and Kakdwip. Agriculture, Industry and Pisciculture are all at their peak in the district. On the west side of the district is the Falta Special Economic Zone (SEZ), which houses various types of industry. In 2006, the Ministry of Panchayati Raj named South 24 Parganas one of the country's 250 most backward districts. It is the largest district of West Bengal state by area and second largest by population. On one side is the urban fringe of Kolkata and on the other, the remote riverine villages in the

Baseline Scenario Page 44 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Sundarbans. In 1984, South 24 Parganas district became home to Sundarbans National Park, which has an area of 1,330 km2 (513.5 sq mi). It shares the park with North 24 Parganas district and is also home to four wildlife sanctuaries: Haliday Island, Lothian Island, Narendrapur, and Sajnekhali. According to the 2011 census of India, South 24 Parganas district had a total population of 8,153,176. This made in the 6th most populous district in India out of a total of 640. The district had a population density of 819 inhabitants per square kilometre (2,120/sq mi).

4.3.7 Population Summary The population summary (based on 2011 census) in regards with the density at each of the six districts is presented in Table 4-1. Table 4-1 Population Summary S. No. District Total Population Density (inhabitants/km2) 1 Hooghly 5,520,389 1,753 2 Howrah 4,841,638 3,300 3 East Medinipur 5,094,238 1,076 4 North 24 Parganas 10,082,852 2,463 5 Kolkata 4,486,679 24,252 6 South 24 Parganas 8,153,176 819

4.4 Climatic Conditions

4.4.1 Hooghly An oppressive summer season, profuse rains and high humidity all through the year are the main characteristic of the climate of the district. The hot season begins with strong Westerly winds from the middle of March and continues up to the middle of May. The weather is oppressively hot. Thunder storm commonly occurs in the afternoon in association with heavy rains with hails. The Kal Baisakhi or the North-Western storms are often violent and cause sharp drop in temperature. The post Monsoon season usually starts from middle of October and continues till the end of February with January being the coldest month.

4.4.2 Howrah A moderate climatic condition prevails due to influences of the sea on the district’s climate under the impact of the branch of the monsoon brought by Bay of Bengal. Three conventional seasons viz. the cold dry season, hot dry season and the rainy season earmark the climatic condition of the district. The period falling between November to February is the cold season, January being the coldest month. The summer season falls during the period from March to the middle of June when the weather remains hot dry, May being the hottest month. The spell of monsoon starts from the middle of June ranging upto October. July and August are the months with the heaviest rain. Mean daily temperature varies between 10ºC in winter to 39ºC in the summer.

4.4.3 East Medinipur The climate of East Medinipur district is tropical in nature. There are four marked seasons (a) Cold, dry weather from December to February (b) Hot, dry weather from March to May (c)

Baseline Scenario Page 45 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Monsoon period lasts from June to September, and (d) Post monsoon period prevail in October and November. The district receives almost over 70% of its annual rainfall between June to September. Average temperature in the district varies from 25.50C to 38.60C.

4.4.4 North 24 Parganas Hot humid summer, a characteristic of the tropical climatic region, prevails all over the district. The monsoon mainly occurs during the months of July, August and September. During this period almost two-third of the normal annual rainfall occurs which leads to sultry weather, flood and water logging in low areas. The maximum and minimum temperatures recorded in the district have been about 420C and 80C respectively.

4.4.5 South 24 Parganas The normal climate of the district is hot and humid throughout the year with well distributed rainfall during the monsoon season. The maximum temperature as recorded at Diamond Harbour is 370C and the minimum is 90C during the year 2011. Winds are generally stronger in Sundarbans and its surroundings. North-Western rains from March to May and the Bay cyclones during the monsoon ravage the land every year.

4.4.6 Kolkata Summer is hot and humid and during dry spells the maximum temperature often touches 400C during May and June. Winter tends to last for only about two and a half months, with seasonal lows dipping almost to 100C between December and January. Often during early summer, dusty squalls followed by spells of thunderstorm and heavy rains lash the city, bringing relief from the humid heat. This thunderstorm is convective in nature, and is locally known as Kal Baisakhi.

4.5 Social Profile

Proposed development activities fall in Six (06) districts of West Bengal, namely: Hooghly, Howrah, East Medinipur, North and South 24 Parganas and Kolkata. These six districts also form six of the eight districts that constitute the Kolkata Metropolitan Area (KMA). Brief social profiles of the six districts are provided in Table 4-2 to Table 4-7.

4.5.1 Hooghly Table 4-2 Social Profile – Hooghly District Description 2011 2001 Population (Nos) 5,519,145 5,041,976 Male (Nos) 2,814,653 2,589,625 Female (Nos) 2,704,492 2,452,351 Population Growth (%) 9.46 15.77 Area (Sq. Km) 3,149 3,149 Density/km2 (Nos) 1,753 1,601 Sex Ratio (Per 1000) 961 947 Average Literacy (%) 81.80 75.11 Male Literacy (%) 87.03 82.59 Female Literacy (%) 76.36 67.21

Baseline Scenario Page 46 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Source: Population Census, 2011

4.5.2 Howrah Table 4-3 Social Profile – Howrah District Description 2011 2001 Population (Nos) 4,850,029 4,273,099 Male (Nos) 2,500,819 2,241,898 Female (Nos) 2,349,210 2,031,201 Population Growth (%) 13.50 14.57 Area (Sq. Km) 1,467 1,467 Density/km2 (Nos) 3,306 2,913 Sex Ratio (Per 1000) 939 906 Average Literacy (%) 83.31 77.01 Male Literacy (%) 86.95 83.22 Female Literacy (%) 79.43 70.11 Source: Population Census, 2011

4.5.3 East Medinipur Table 4-4 Social Profile – East Medinipur District Description 2011 2001 Population (Nos) 5,095,875 4,417,377 Male (Nos) 2,629,834 2,268,322 Female (Nos) 2,466,041 2,149,055 Population Growth (%) 15.36 14.87 Area (Sq. Km) 4,713 4,713 Density/km2 (Nos) 1,081 933 Sex Ratio (Per 1000) 938 947 Average Literacy (%) 87.02 80.16 Male Literacy (%) 92.32 89.13 Female Literacy (%) 81.37 70.70 Source: Population Census, 2011

4.5.4 North 24 Parganas Table 4-5 Social Profile – North 24 Parganas District Description 2011 2001 Population (Nos) 10,009,781 8,934,286 Male (Nos) 5,119,389 4,638,756 Female (Nos) 4,890,392 4,295,530 Population Growth (%) 12.04 22.69 Area (Sq. Km) 4,094 4,094 Density/km2 (Nos) 2,445 2,182 Sex Ratio (Per 1000) 955 926 Average Literacy (%) 84.06 78.07 Male Literacy (%) 87.61 83.92 Female Literacy (%) 80.34 71.72

Baseline Scenario Page 47 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Source: Population Census, 2011

4.5.5 South 24 Parganas Table 4-6 Social Profile – South 24 Parganas District Description 2011 2001 Population (Nos) 8,161,961 6,906,689 Male (Nos) 4,173,778 3,564,993 Female (Nos) 3,988,183 3,341,696 Population Growth (%) 18.17 20.85 Area (Sq. Km) 9,960 9,960 Density/km2 (Nos) 819 693 Sex Ratio (Per 1000) 956 937 Average Literacy (%) 77.51 69.45 Male Literacy (%) 83.35 79.19 Female Literacy (%) 71.40 59.01 Source: Population Census, 2011

4.5.6 Kolkata Table 4-7 Social Profile – Kolkata District Description Total Male Female Population (Nos) 4,496,694 2,356,766 2,139,928 Literates (Nos) 3,588,137 1,926,915 1,661,222 Children (0-6) (Nos) 339,323 175,564 163,759 Average Literacy (%) 86.31 88.34 84.06 Sex Ratio (Nos) 908 - Child Sex Ratio (Nos) 933 - Source: Population Census, 2011

4.6 Baseline Environment

The baseline environmental quality represents the background environmental scenario of various environmental components such as air, noise, water, soil quality status in the study area. The baseline assessment is presented based on secondary data as referred from the EIA study recently carried out (March 2019 – May 2019) for the Proposed Construction of Gangway-Pontoon Jetty with Link platform on river Hooghly at Geonkhali, District, East/ Purba Medinipur. The location of this study is within the overall study area of the present jetty improvement project. As such, data from the Geonkhali study is considered as relevant to the current study area as well. The monitoring data has been referenced from EIA Report prepared for the above project and titled “Rapid Environmental Impact Assessment & EMP Report for Proposed Construction of Gangway-Pontoon Jetty with Link platform on River Hooghly at Geonkhali, Dist.-Purba Medinipur, W.B for Passenger Ferry service of WBTIDCL (Geonkhali Jetty EIA Report)”. Proposed activities are limited to minor construction works at the jetty locations which will involve installation of the pontoon and gangways and minimal civil works on the link platform (concrete structure). In addition, the major activity under the First Year investments is the manufacturing of the vessels, pontoons and gangways which will be done at the manufacturing yards of the selected contractors. Proposed development activities are not envisaged to have

Baseline Scenario Page 48 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments significant sources of adverse environmental/social impacts. Also, the development activities are not envisaged to alter the baseline environmental conditions.

4.6.1 Ambient Air Quality As per Central Pollution Control Board (CPCB) monitoring guidelines monitoring of Particulate Matter size less than 10 microns (PM10) and Particulate Matter size less than 2.5 microns (PM2.5), Sulphur Dioxide (SO2), Oxides of Nitrogen (NOx) were monitored on 24 hourly basis and Carbon Monoxide (CO) monitored on eight hourly basis. Details of the AAQ locations are given in Table 4-8. Table 4-8 Ambient Air Monitoring Stations S. No. Code Location 1. AAQ-1 Project Site 2. AAQ-2 Gadiara 3. AAQ-3 Noorpur 4. AAQ-4 Jambari 5. AAQ-5

4.6.1.1 Observations

Statistical parameters like Arithmetic Mean and 98th Percentiles have been computed from the observed raw data for all sampling stations. Minimum and Maximum levels recorded are also calculated from the data. The summary of baseline data values minimum, maximum along with th 98 percentile value for PM10, PM2.5, SO2 and NOx are presented in Table 4-9. Table 4-9: Summary of Air Quality Parameters Location Name AAQ-1 AAQ-2 AAQ-3 AAQ-4 AAQ-5

PM10 Maximum (µg/m3) 125.09 152.17 129 97.6 121.84 Minimum (µg/m3) 25.88 33.6 50.59 19.57 33.03 Average (µg/m3) 66.3 83.2 90.7 53.8 58.5 98th Percentile (µg/m3) 117.7 142.7 128.7 91.2 109.7 CPCB Standard (µg/m3) 100

PM2.5 Maximum (µg/m3) 46.13 57.08 64.2 43.77 44.85 Minimum (µg/m3) 10.08 15.23 24 9.5 11.57 Average (µg/m3) 25.1 34.1 42.4 25.8 28.5 98th Percentile (µg/m3) 45.7 52.8 63.3 42.3 44.4 CPCB Standard (µg/m3) 60

SO2 Maximum (µg/m3) 17.19 20.72 10.2 18.83 21.29 Minimum (µg/m3) 9.99 4.85 2 10.02 8.32 Average (µg/m3) 13.1 11.0 6.7 13.1 13.7 98th Percentile (µg/m3) 17.0 19.8 10.1 18.0 19.3 CPCB Standard (µg/m3) 80

NOx Maximum (µg/m3) 36.33 37.87 49.05 32.97 35.4 Minimum (µg/m3) 6.8 15.68 29 8.04 8.8 Average (µg/m3) 26.9 26.7 36.9 24.6 23.5

Baseline Scenario Page 49 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Location Name AAQ-1 AAQ-2 AAQ-3 AAQ-4 AAQ-5 98th Percentile (µg/m3) 35.5 37.8 46.0 31.4 34.1 CPCB Standard (µg/m3) 80 CO Maximum (µg/m3) <0.5 <0.5 <0.5 <0.5 <0.5 Minimum (µg/m3) <0.5 <0.5 <0.5 <0.5 <0.5 Average (µg/m3) <0.5 <0.5 <0.5 <0.5 <0.5 98th Percentile (µg/m3) <0.5 <0.5 <0.5 <0.5 <0.5 CPCB Standard (µg/m3) 2

Analysis of ambient air quality data for three months consequently indicates average PM10 as well as PM2.5 is within prescribed limits. SO2 and NOx levels are well below the prescribed limits. Hence overall scenario as far as ambient air is concerned is positive. Ambient Air Quality standards are provided as Appendix 4.

4.6.2 Noise Environment Observed baseline ambient noise levels are as referenced from the above mentioned Geonkhali Jetty EIA Report. The noise recording stations are mentioned in Table 4-10 and the summary of the minimum, maximum day-equivalent, night equivalent and day-night equivalent values computed for various locations in the study area is presented in Table 4-11. Ambient noise monitoring results at the project location is presented as Table 4-12. Table 4-10: Ambient Noise Quality Monitoring Stations Code Location ANQ-1 Project Site ANQ-2 Gadiara ANQ-3 Noorpur ANQ-4 Jambari ANQ-5 Mahishadal Table 4-11: Noise Levels during Study Period Equivalent Noise Levels ANQ-1 ANQ-2 ANQ-3 ANQ-4 ANQ-5

Ld 54.1 52.1 51.5 50.0 53.0

Ln 51.3 43.2 41.5 41.5 42.3 Ld 55 dB(A) CPCB Ln 45 dB(A)

Ld: Day Equivalent; Ln: Night Equivalent Table 4-12: Noise Levels at Geonkhali Jetty Location Ambient Noise Monitoring Results Noise Level Location: Geonkhali Time Leq. dB(A) Jetty Location Maximum 62.8 6.00-9.00 Minimum 52.4 Leq. 58.5 Maximum 63.1 9.00-12.00 Minimum 57.2 Leq. 60.5 12.00-15.00 Maximum 63.8

Baseline Scenario Page 50 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Ambient Noise Monitoring Results Noise Level Location: Geonkhali Time Leq. dB(A) Jetty Location Minimum 56.1 Leq. 61.7 Maximum 62.9 15.00-18.00 Minimum 54.8 Leq. 59.5 Maximum 57.3 18.00-21.00 Minimum 47.5 Leq. 54.5 Maximum 51.9 21.00-00.00 Minimum 44.2 Leq. 47.8 Maximum 45.2 00.00-3.00 Minimum 42.1 Leq. 43.6 Maximum 47.5 3.00-6.00 Minimum 42.4 Leq. 45

4.6.2.1 Observations

It is observed that the noise values obtained were within the prescribed Ambient Air Quality Standards with respect to Noise. The maximum and minimum day time value monitored at the Geonkhali Jetty Location was 63.8 dB(A) and 52.4 dB(A), respectively. Noise level standards are provided as Appendix 5.

4.6.3 Water Environment Baseline surface water quality is referenced from the Geonkhali Jetty EIA Report. Data on baseline condition of water environment in study area was collected with following objectives: • Qualitative assessment of water sources of the area. • To judge the temporal changes in water quality of different sources. • To predict the Impact of Power Plant over water environment of the area. To judge the water environment of the area, both the sources of water (surface & ground) were given due consideration. Water samples were collected and analyzed for various parameters. Based on the analysis of different parameters, results were checked up against the limits set up to statuary authorities. Reconnaissance survey of the area was made for the selection of sampling location for surface and ground water analysis. Stations were selected keeping the objectives in mind. The monitoring locations of surface and ground water are presented in Table 4-13. Assessment of baseline data on water environment included: 1. Identification of surface water sources 2. Identification of ground water sources 3. Collection of water samples 4. Analyzing water samples collected for physico-chemical and biological parameters

Baseline Scenario Page 51 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Samples were collected and analysed as per standard methods and frequency of sampling was as per norms. Assessment of water quality in the study area was carried out as per the Indian Standard IS 10500:2012 (Drinking Water Standard). The analysis results of the Ground Water collected from sampling stations are presented in Table 4-14 and the analysis results of the Surface Water collected are presented in Table 4-15. Standards/criteria for water quality are provided as Appendix 6. Table 4-13: Water Sampling Locations Code Location GWQ-1 Project Site GWQ-2 Gadiara GWQ-3 Noorpur GWQ-4 Jambari GWQ-5 Mahishadal SWQ-1 Up Stream SWQ-2 Downstream Table 4-14: Ground Water Quality Concentration Acceptable Permissible S. Parameter Unit GWQ GWQ GWQ GWQ GWQ Limit as per Limit as per No 1 2 3 4 5 IS10500:2012 IS10500:2012 1. Turbidity NTU 0.1 1.2 1.7 1.4 1.3 1 5 2. pH - 6.8 7.22 7.14 7.11 7.15 6.5-8.5 No Relaxation T. Hardness 3. mg/l 239 140 473 136 380 200 600 (as CaCO3) 4. Iron (as Fe) mg/l 0.16 0.15 0.16 0.01 0.14 0.3 No Relaxation Chloride (as 5. mg/l 114 65 55 48 52 250 1000 Cl) Free Residual

Baseline Scenario Page 52 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Concentration Acceptable Permissible S. Parameter Unit GWQ GWQ GWQ GWQ GWQ Limit as per Limit as per No 1 2 3 4 5 IS10500:2012 IS10500:2012 Cadmium (as 23 <1.3 <1.5 <1.1 <1.2 Coliform* 100 ml Shall not be detectable in any Faecal MPN/ 100 ml sample 22. 5.1 8.5 6.2 5.3 7.6 Coliform* 100 ml NTU: Nephelometric Turbidity Unit; MRL: Maximum Residue Levels; MPN: Most Probable Number Table 4-15: Surface Water Quality Result/Concentration Tolerance Limits SWQ-1 SWQ-2 for Inland S. No. Parameter Unit (Upstream (Downstream Surface Waters, Hooghly River) Hooghly River) Class – C 1. pH - 7.2 7.1 6.5 to 8.5 Dissolved 2. mg/l 6.8 6.7 4.0 Oxygen 3. BOD mg/l 2.5 3.6 3.0 4. Total Coliform MPN/100ml 39039 54687 5000 Faecal 5. MPN/100ml 12956 14706 - Coliform Total Hardness 6. mg/l 180 219 - (as CaCO3) Calcium (as 7. mg/l 47 55 - Ca) Magnesium 8. mg/l 15 20 - (as Mg) 9. Fluoride (as F) mg/l 0.21 0.24 1.5 Cadmium (as 10. mg/l

Baseline Scenario Page 53 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Result/Concentration Tolerance Limits SWQ-1 SWQ-2 for Inland S. No. Parameter Unit (Upstream (Downstream Surface Waters, Hooghly River) Hooghly River) Class – C Total 13. Dissolved mg/l 750 810 1500 Solids Sulphate (as 14. mg/l 19 20 400 SO4) 15. Lead (as Pb) mg/l

4.6.3.1 Observations

Groundwater: pH in ground water sample was observed to be in the range 6.8 to 7.22. The value of alkalinity and hardness were observed in the range of 102-355 mg/l and 140 to 473 mg/I respectively. It can be inferred that all above reported parameters for groundwater are within the Permissible Limits specified as per Drinking Water Quality Standards (IS 10500:2012) except Coliforms (likely result of large scale sewage being discharge into the river system). Surface Water: pH in surface water sample was observed to be in the range 7.1 to 7.2. The value of hardness was observed in the range of 180 to 219 mg/l. All reported parameters are well within the limits specified for Class C, Drinking Water source with conventional treatment followed by disinfection (ISI-IS: 2296-1982) except Coliforms (likely result of large scale sewage discharge into the water bodies).

4.6.3.2 Namami Gange

The Ganga (Ganges) emanates from Gangotri Glacier at Gaumukh at an elevation of 3,892 m (12,770 feet). Many small streams comprise the headwaters of Ganga. It traverses a course of ~2,525 km before flowing into the Bay of Bengal. It has a large number of tributaries joining it during this journey. In addition there are also distributaries which are formed from the Ganges system. One such distributary is the Hooghly River in West Bengal forming part of the Ganges system. The Hooghly River is an approximately 260 km long distributary of the Ganges River.

Baseline Scenario Page 54 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

'Namami Gange Program', is an Integrated Conservation Mission, approved as 'Flagship Program' by the Union Government of India in June 2014 to accomplish the objectives of effective abatement of pollution, conservation and rejuvenation of the National River Ganga. As part of this program, clean-up measures have been observed within the current project corridor as well. The clean-up is carried out by means of a specifically designed vessel which plies along the river and collects debris flowing in the river. The clean-up vessel(s) operate on daily basis at different locations in the river. The waste material is collected onto the vessel which is then transferred to receiving stations at various jetty terminals. The waste/ debris from the terminals are then carried away and disposed by the Municipality authorities. Exhibit 4-1 shows pictures taken of the river clean-up works under Namami Gange at Shibpur Jetty.

River Clean-Up Works at Shibpur Jetty Location Exhibit 4-1 River Clean-up Works 'Namami Gange’

4.6.4 Land Environment-Soil Quality Baseline soil quality data was also referenced from the Geonkhali Jetty EIA Report. The soil samples were collected from five sampling locations within an area of 10 km radius around the proposed project for analysis of the physico-chemical characteristics of the soil quality. The locations of soil sampling stations are given Table 4-16. The soil quality analysis/results are presented as Table 4-17. Soil quality standards are provided as Appendix 7. Table 4-16: Soil Sampling Locations Code Location SQ-1 Project Site SQ-2 Gadiara SQ-3 Noorpur SQ-4 Jambari SQ-5 Mahishadal Table 4-17: Soil Quality Results Concentration S. No Parameter Unit SQ1 SQ2 SQ3 SQ4 SQ5 1. Color --- Brown Blackish Brown Brown Blackish Clay Sandy Sandy Sandy Sandy 2. Texture --- Loam Loam Loam Loam Loam 3. Bulk Density gm/cm3 1.12 1.44 1.32 1.58 1.35 4. Moisture % 19.8 31.6 42.4 56.5 28.5

Baseline Scenario Page 55 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Concentration S. No Parameter Unit SQ1 SQ2 SQ3 SQ4 SQ5 5. Ph --- 8.0 7.5 6.7 7.1 6.9 6. Conductivity (1:2.5) at 250C µS/cm 305 253 4.6 355 345 7. Organic Carbon % .0 1.2 1.3 1.15 1.33 8. Organic Matter % 2.29 1.5 1.7 1.9 1.6 9. Available Nitrogen mg/gm 0.23 0.31 0.26 0.32 0.25 10. Available Phosphorous mg/gm 0.71 0.52 0.49 0.44 0.49 11. Available Potassium mg/gm 5.13 3.23 2.62 4.33 5.53 12. Calcium mg/gm 1.13 2.32 1.5 2.9 3.3 13. Magnesium mg/gm 0.42 0.38 1.6 0.27 1.51 14. Sodium mg/gm 2.0 2.4 3.6 2.8 2.2 15. Iron mg/kg 0.38 0.62 1.6 2.7 0.3 16. Copper mg/kg 0.03 0.88 0.72 0.82 0.75 17. Zinc mg/kg 0.06 0.11 1.1 0.9 1.2

4.6.5 Biological Environment

4.6.5.1 Endemic and Endangered Species

The project activities under the First Year investments will be limited mainly to the waterside at existing jetty locations. There are no known endemic and endangered species at the jetty locations. However, the Gangetic River Dolphin or Gangetic Dolphin or the Platanista gangetica, an endangered species according to the International Union for Conservation of Nature (IUCN), can be found in the Ganga-Brahmaputra-Meghna and Karnaphuli-Sangu river systems of Nepal, India and Bangladesh (Exhibit 4-5). The Hooghly River being a distributary of the overall Ganga River system, the presence of the Gangetic dolphin in the project stretch was examined. The overall project corridor from Tribeni to Noorpur has presence of the Gangetic dolphins, as seen from several sighting reports as well as seen during the field observations (especially at the confluence areas near Noorpur). Although there are reportedly dolphins in the Hooghly River, they are dispersed in the river and are found concentrated more at the confluences of the rivers where the water current is strong. However, sightings (rare) are reported throughout the corridor.

Exhibit 4-2 Gangetic River Dolphin

Baseline Scenario Page 56 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

11Anderson (1879) estimated that about 10,000 Gangetic dolphins were present in the Ganga River and its tributaries during the late 19th Century. In recent past, Sinha and Kannan (2014) estimated 3526 individuals during the early 2000s. A recent review of literature estimate about 3,200 individuals in the Ganga basin. Recognizing the ecological role of the species in river ecosystems and its need for protection, the Gangetic Dolphin was listed in the Schedule I of Wild Life ACT 1972 and was designated as the National Aquatic Animal in 2009. Gangetic Dolphin is also considered as an endangered species by the International Union for Conservation of Nature (IUCN). The distribution range has reduced in the Ganga River as well as its tributaries (Sinha et al., 2000). The population trend of the dolphin in the Ganga River basin over the years is shown in Figure 4-1.

Figure 4-1 Dolphin Population According to Ravindra Kumar Sinha, Patna University and recipient of a Padma Shri for his work on the conservation of Gangetic dolphins, dolphins prefer deep water with adjoining shallow water. They live in a zone where there is little or no current that helps them save energy. If they sense danger, they can go into the deep waters," he said. The dolphins swim from the no-current zone to the edges to hunt for fish and return. The Ganges dolphins have been reported to be avoiding the river stretch with heavy traffic in the Hooghly River, preferring relatively undisturbed areas where a lower number of mechanized vessels ply12. Freshwater dolphins and their natural habitats are under threat. One of the causes is the large scale discharge of municipal waste, siltation and the countless brick kilns that have sprung up along the riverbanks. Brick kilns discharge hot water while civic waste pollutes the water and alters its character. The unfavourable conditions are mainly due to increase in salinity levels and sedimentation due to reduced discharges from upstream barrages. Siltation reduces the depth of the river. Too much vessel movement, mechanized boats/trawlers, also drive away aquatic animals. Over the past several years, there have been reported incidents of deaths as well as some stranding of Dolphins in Hooghly River system. These incidents typically happen as result of Dolphins getting trapped in fishing nets, getting stranded in canals with vegetation’s as well as very rare or occasional deaths due to vessel collisions (Times of India, Nov.16, 2019; Mitra, S.

11 Wildlife Institute of India, Conserving Gangetic Dolphin, Smart Strategy Implementation and Adaptive Management for the Ganga River (WII – GACMC, 2019) 12 The Conservation Action Plan for the Ganges River Dolphin, 2010-2020, National Ganga River Basin Authority, Ministry of Environment & Forests, Government of India, https://iucn-csg.org/wp- content/uploads/2010/03/DolphinCAP_27092010_editSS1.pdf

Baseline Scenario Page 57 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

& M.R. Chowdhury (2018)). Also, vessel collisions are a likely cause of impacts on dolphins that stray outside their habitats into the navigation areas of the river. The reports of deaths/injuries to dolphins due to vessel movements are understood to be significantly less as compared to the other threats faced by the dolphins. Vessel movements (motorized boats) are known to be source of impacts to the Dolphins – not necessarily due to collisions but due to the disturbances the vessel movements cause in the ecosystem (pollution, vessel vibrations, noise, etc.) leading to the dolphins behavioral changes, stress, alteration in prey-base, etc. The threats to dolphins can be from water development projects (e.g., barrages, high dams, levies or embankments and withdrawal of surface water), which often isolate subpopulations, alter the ecological features which characterize dolphin habitat, reduce water discharge to a level where the river can no longer sustain aquatic megafauna, and block the spawning migrations of dolphin prey; Overexploitation of dolphin prey; Incidental catches, most often occurring in monofilament gill nets; Direct exploitation, generally for dolphin oil which is used mainly as a fish attractant and also for medicinal purposes; Increasing levels of organic and inorganic pollution. The risk categories13 of the threats faced by dolphins are as shown in Exhibit 4-6.

• Reduced Depths Very High • Fishing Risks

• Motorised Boats • Riverbed Agriculture High Risks • Drain

• Sand Mining • Solid Waste Medium • Open Cremation Risk

• Cultural Offering • Mass Bathing Low Risk

Exhibit 4-3 Dolphins Risk Categories Finally, it is to be noted that the jetty operations (waterways) in the area have been an ongoing activity for several decades and are not known to have been a cause for adverse impacts to the dolphins (Ref: stakeholder consultations). Proposed development will also not involve activities that are likely to threaten the dolphins. Threats to dolphins, if any, would be mainly due to the vessel operations, not necessarily due to collisions but due to the disturbances the vessel movements cause in the ecosystem (pollution, vessel vibrations, noise, etc.) leading to

13 Wildlife Institute of India, Conserving Gangetic Dolphin, Smart Strategy Implementation and Adaptive Management for the Ganga River (WII – GACMC, 2019)

Baseline Scenario Page 58 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments behavioral changes, stress, alteration in prey-base, etc. However, it is also to be noted that this is the navigational route for large cargo ships as well which are several times bigger than the passenger vessels to be operated under the proposed development. As such, proposed development activities are not envisaged to cause adverse impacts to the dolphins; nevertheless, as the Hooghly River system has presence of dolphins and some of the dolphins could be present in the core areas of operation (navigation areas, though rare), which mitigation measures as suggested in Sections 6.4.1.13 and 6.5.1.3 shall be put in place which will help avoid impacts to dolphins, if any. Sighting records of Gangetic River Dolphin As mentioned above, the Hooghly River has reported sightings of the GRD. Several studies have been carried out along the Hooghly River to understand more about the GRD (its numbers, areas where seen more, etc.). Also, several awareness campaigns have also been carried out by organizations like the WWF. Three such studies are discussed below: Study by Chowdhury, M.R., S. Mitra & S. Sen (2016) The Platanista gangetica (Ganges River Dolphin GRD) subpopulation occurring downstream of Farakka Barrage in the river Ganges and its tributaries in West Bengal was studied by Chowdhury et al. (2016)14. The study was carried out in the Hooghly River from the point where the Ganges meets with the river Jalangi at Nabadwip until it reaches the Bay of Bengal. The present corridor of development falls within this study area and as such is relevant to the project area. Sangita Mitra & Mahua Roy Chowdhury (2018)15 studied the stretch in Hooghly River during the period of 2012–2016. The waterways were scanned in all the seasons to confirm the presence or absence of dolphins and to avoid any information gap due to seasonal differences. During the survey period from 2012 to 2016 a total of 13 sightings of Ganges River Dolphins were recorded. An average sighting of Ganges River Dolphin in the Hooghly Rivers along the stretch is 0.30 per year. The major congregations of GRD or sighting points were in the lower stretch of the Hooghly as shown in Table 4-18. Table 4-18 Sightings of Ganges River Dolphin Boat-based Land (B)/ Land- Geographic District River Year Reference based (L) Coordinates Survey Budge budge South 24 22.4830N & Hooghly B, L 2015 river side Paraganas 88.1830E South 24 22.5000N & Bata nagar Hooghly L 2015–16 Paraganas 88.2000E South 24 22.4660N & Pujali Hooghly L 2015 Paraganas 88.1500E Millenium 22.5500N & Kolkata Hooghly B 2014–15 park 88.0310E

14 Chowdhury, M.R., S. Mitra & S. Sen (2016). On the Behaviour, abundance, habitat use and potential threats of the Gangetic Dolphin Platanista gangetica in southern West Bengal, India. Journal of Threatened Taxa 8(9): 9131–9137; https://doi.org/10.11609/ jott.1752.8.9.9131-9137 15 Mitra, S. & M.R. Chowdhury (2018). Possible range decline of Ganges River Dolphin Platanista gangetica (Mammalia: Cetartiodactyla: Platanistidae) in Indian Sundarban. Journal of Threatened Taxa 10(13): 12738–12748; https://doi.org/10.11609/jott.2493.10.13.12738-12748

Baseline Scenario Page 59 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Boat-based Land (B)/ Land- Geographic District River Year Reference based (L) Coordinates Survey Diamond South 24 22.1600N & Hooghly B, L 2015 Harbour Paraganas 88.0170E South 24 21.8500N & Kachuberia Muriganga B, L 2015–16 Paraganas 88.1330E Confluence of River South 24 21.7500N & Namkhana Muriganga and B 2015–16 Paraganas 88.2100E Hatania- Doania Confluence of 22.2160N & Gadiara Howrah Rupnarayan and B, L 2012–15 88.0330E Hooghly South 24 Confluence of Haldi 22.0000N & Haldia L 2012 Paraganas and Hooghly 88.0500E Confluence of 22.3330N & Garchumuk Howrah L 2012–2015 Damodar and Hooghly 88.0800E Confluence of 22.5100N & Bakshi Howrah Rupnarayan, Damodar L 2014–15 88.0160E and Mundeshwari East 22.4160N & Kolaghat Rupnarayan B, L 2011–15 Midnapur 87.8830E 22.6160N & Belur Howrah Hooghly L 2015 88.3500E Study by WWF INDIA To overview the threats to the river dolphins in West Bengal and minimizing those threats, WWF INDIA, WBSO in collaboration with HSBC has been working for the conservation of river dolphin through several activities like campaign, workshop, awareness, interaction with suitable stakeholders, placing display boards at different locations, river watch and survey along the river stretch. Details of one such study published in the WWF’s Annual Report 2015- 2016 titled “Conserving the aquatic resource diversity including the National Aquatic Animal through capacity building, community education and developing a better understanding for sustainable use of resources”, is discussed in this section. Some important literature from the report is quoted below: • “Its global population is declining. The current global population of the species is hardly 1200 individuals (Smith & Braulik 2012)”. • “The rapid declination of the global population of this endangered creature is due to accidental killing through fishing net entanglement, unsustainable fishing practices in and around dolphin habitats through the use of destructive fishing gear as well as illegal fishing during closed fishing season, water development projects, habitat degradation with increasing pollution and siltation”. • “So, illegal harvesting of fishes caused loss of many species which were identified as like dolphin’s major foods like Rhinomugil corsula (Mitra et al. 2015). The above factors confined this species in isolated pockets and restricted their range in southern West Bengal”. WWF INDIA has conducted a visual survey for assessment of the Gangetic River Dolphin population in the lower stretch of River Ganga on 17th February, 2016. During the survey, it

Baseline Scenario Page 60 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments had been observed that very small populations of dolphins were present in this riverine stretch. In the study the best estimates of river dolphin were recorded at 11 individuals.

Study by Wildlife Institute of India The National Mission for Clean Ganga (NMCG) has taken up the task of conservation of the Ganga River. Under this program, the Wildlife Institute of India (WII), Dehra Dun, has been entrusted with the Biodiversity Conservation and Ganga Rejuvenation project which focuses on science based species restoration. As part of the project, surveys of aquatic species of conservation significance has been carried out between Devprayag in Uttarakhand and Noorpur in West Bengal resulting in additional information of the GRD in the Ganga River. This information will provide vital information of identification of dolphin hot spots and risk prone stretches. The results will aim to be used to formulate a Gangetic Dolphin Conservation Action Plan and concurrently prioritize the river stretches for conservation of Gangetic dolphins and their habitat. Details of this study are presented in the WII’s report, Conserving Gangetic Dolphin, Smart Strategy Implementation and Adaptive Management for the Ganga River (WII – GACMC, 2019). WII has conducted surveys during the pre and post monsoons of 2018 and pre-monsoon period of 2019. The entire stretch of the river from Devprayag to Noorpur was divided into 24 basis survey units (BSUs). The BSUs included the stretch from to Noorpur/Nurpur. The proposed development corridor from Tribeni to Noorpur falls in this BSU. In pre-monsoon 2018, in the stretch from Bandel to Noorpur 42 sightings have been recorded. In post -monsoon 2018, the same stretch had 50 sightings that were recorded. Similarly, during the survey carried out in pre-monsoon 2019, 21 sightings have been recorded in the same stretch. Based on a modelling exercise that was carried out, the BSU/stretch of concern (Bandel to Noorpur) has been classified as a “Medium Priority Area”. A medium priority area is where: • 40% to 60% probability of occurrence of Gangetic dolphins across seasons • Stretch act as seasonal dispersal route • Can act as buffer to the high priority areas and existing Protected Areas • Conservation intervention is needed for protection of the species and its habitat The sightings per km in this stretch is estimated between 0.19 – 0.45. The major pressures on habitats and species in this stretch are reportedly fishing, deliberate killing and vessel traffic.

Assessment

Baseline Scenario Page 61 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

“The Ganges River dolphin ranges into most of the large tributaries in the Ganges Basin: the Ramganga, Yamuna, Gomti, Ghaghara, Rapti, Son, Gandak and Kosi besides the main channel of the Ganga” “While there were occasional reports of dolphin sightings in some of the smaller tributaries of the Ganga during the 1980s, it is now likely that dolphins have been completely extirpated from these rivers due to insufficient and inconsistent water supplies”. “Dolphins in the main channel of the Ganga were split into two subpopulations in 1975 when the Farakka Barrage was commissioned. The Lower Ganga Barrage at Narora (1966) and the Middle Ganga Barrage at Bijnor (1984) further fragmented the Ganga main stem population into four subpopulations. Dolphins have now been extirpated above the Middle Ganga Barrage at Bijnor. Today they occur in three subpopulations bounded by the Bijnor, Narora and Farakka Barrages”. • Bijnor and Narora are located in state of Uttar Pradesh; Farakka Barrage, is in West Bengal, but ~ 150 kms north of Tribeni

Anderson (1879) estimated that about 10,000 Gangetic dolphins were present in the Ganga River and its tributaries during the late 19th Century. In recent past, Sinha and Kannan (2014) estimated 3526 individuals during the early 2000s. A recent review of literature estimate 3294 individuals in the Ganga basin. The distribution range has reduced in the Ganga River as well as its tributaries (Sinha et al., 2000) Based on several secondary data we understand that in the earlier days (likely prior to 1975 when the Farakka Dam began operating), the Hooghly River stretch also likely had much more numbers of dolphins as it has currently. The numbers have decreased significantly over the years as the dolphin’s habitat has been disturbed mainly due to manmade reasons such as development works, increased pollution, shallow waters, etc. conditions which are not suitable for dolphins to flourish. As such, there remain only very few dolphins which are sighted in this stretch (published information on exact dolphin distribution and its numbers are limited). To avoid/minimse impacts to the dolphins, if any, in the project area due to prosed development activities, mitigation measures shall be put in place.

Baseline Scenario Page 62 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

In addition, as proposed development works are to be carried out in areas where Gangetic dolphins are present (reportedly dispersed in the Hooghly River), it is of utmost importance that WBTIDCL plays a role in conservation activities of the dolphins. WBTIDCL shall support agencies involved in conservation works (such as WWF) to create awareness and obtain additional/updated information on the dolphins especially in the project corridor from Tribeni to Noorpur. A budgetary provision for this activity has been made and presented in the ESMP budget in Section 8.6.

Baseline Scenario Page 63 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

5 Analysis of Alternatives

5.1 No Project v/s With Project Alternative The “No Project” option will entail retaining the existing conditions of the jetty facilities and vessels or status quo of the proposed project. Hence, if this option is preferred it will mean that no enhancements/upgradation of existing jetties would be taken up and commuters would not have any improved facilities and amenities. The “With Project Alternative” will provide commuters with the much needed upgradation of existing facilities with improved facilities and amenities. As such, the alternative with proposed development is to be taken up for overall benefits of the commuters. This will have significant overall positive impacts to the entire ferry operating services. Further, the key argument for the project is to encourage the shift from road transport to water transport, which provides a cleaner form of transportation from an environmental perspective.

5.1.1 Telinipara Jetty Accident

Exhibit 5-1 News Clipping of Telinipara Jetty Accident In the morning hours of April 26, 2017, the bamboo structured jetty structure/link platform to the boat at Telinipara Ferry Ghat collapsed under the impact of high tide on the river. Several

Analysis of Alternatives Page 64 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments people were on the jetty structure awaiting the boat when the structure collapsed leading to the tragic loss of lives. Following this incident, the West Bengal Transport Corporation (WBTC) has put in place Standard Operating Procedures (SOP) for the jetty operations. However, even with the SOP’s in place the jetty infrastructure and operations still are found lacking in various aspects of safety, infrastructure facilities, etc. As such, this proposed development activities alternative is even more essential for enhancing the facilities at the jetty locations. In addition, the First Year investments are not envisaged to have environmental and social impacts as well.

5.2 Technical Design Alternatives

Proposed development under the First Year of investments are planned to be carried out at the existing jetty locations itself where necessary improvements to the facilities are to be made. As such, the project will not have an alternative in terms of location. In terms of the technical designs, various alternatives were considered for the vehicle design and the jetty layout / infrastructure provisions. Based on the analysis of alternatives, the following environmentally positive features (in italics) were included in the technical designs. These include: • Introduction of newer/better efficient vessels with reduced emissions • Vessels/Gangways/Pontoons can have additional safety features • Better performance engines and lighter vessels, can help in reduced fuel consumptions • Vessels/Gangways can be provided with solar components for lighting purpose which will help reduce energy costs • Vessels with latest applicable best management practices/technology will be built and introduced for more enhanced operational efficiency. • Project vessels being operated in an aquatic environment with relatively rich aquatic life, mechanisms like sound-emitting devices in the waters will be adopted as that will alert fishes of the approaching vessels • Vessels shall have necessary oil spill control/collection systems • Jetty locations will be provided with appropriate oil spill control/collection equipment • Vessels will be fitted with sewage/waste collection systems; similarly sewage/waste collection facilities will be provided at the terminals which can collect sewage/waste from the vessels and dispose it appropriately • Various enhancements at the jetty locations will be provided (provision of signage’s, information systems, easy access for elderly/disabled commuters, etc.) • Jetty location aesthetic improvements will be taken up (landscaping, planting of trees, etc.) wherever feasible • Improved facilities at the vessel/gangway/pontoon manufacturing units to make effective management of environmental and social issues. Hence proposed technical design alternative provides opportunities for environmental enhancement measures that have been integrated. Also, it is to be noted that the major activities under the First Year Investments will include manufacturing of the vessels, pontoons and gangways. Although the tender for bidding for the project works will be nationwide, it is envisaged that most of the bidders would be from the Hooghly River area. Manufacturing of the vessels, pontoons and gangways items outside of the Hooghly River area and then bringing it in to the Hooghly River area will be too expensive and will likely require several clearances from various regulatory authorities. These manufacturing activities anticipated to be taken up in the project area itself will help in providing

Analysis of Alternatives Page 65 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments several employment opportunities to the locals which will in turn contribute towards the local economy.

Analysis of Alternatives Page 66 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

6 Potential Impacts and Mitigation Measures The waterways mode of transportation is an operationally cheaper, fuel efficient and environmentally friendly mode of transport, especially for handling bulk cargo/commodities. This mode has the potential to be developed in a big way and serve as an alternate/ supplementary mode of transportation. The waterways mode of transport has several benefits which include16: • Less fuel consumption (1 litre fuel moves 24 t-km on road, 85 t-km on rail, 105 t-km on waterways) • Lower energy/fuel requirement but can produce higher output (i.e. 1 HP can move 150 kg on road, 500 kg on rail and 4000 kg on water) • Significantly helps to reduce burden on road and rail networks, helps reduce congestion and accidents on road • Cost of developing waterways is much lower than rail & road • CO2 emissions are almost 50% of emissions from trucks • Very minimal land requirements (direct savings in land acquisition and R&R costs) • Safer mode for transport of hazardous and over dimensional cargo Identifying importance and need of this transport mode, GoWB is taking up several initiatives for improvement/sustainable development of its waterways. Such initiation has led to the present proposed project of “Construction of new jetties and upgradation of existing jetties that would have improved facilities and amenities”. Proposed development activities to be undertaken under the First Year of investments will involve “Construction of new jetties and upgradation of existing jetties that would have improved facilities and amenities”. From the above-mentioned advantages of the water mode of transport, the proposed development will likely have significantly more positive impacts than negative impacts on the environmental/social conditions. This section of the ESIA report details the projects potential impacts and proposes mitigation measures to limit/minimise negative impacts identified.

6.1 Project Activities

The subprojects that will be supported under the First Year investments are: • Improving the capacity of selected jetties by adding pontoons and gangways • Implementing minor waterside construction works to install gangways and pontoons • Adding new vessels with enhanced designs to existing fleet • Installing turnstile gates in selected jetties

6.1.1 Gangways and Pontoons Pontoons and Gangways are proposed to be added at selected jetties to improve the capacity of the jetties. The Pontoons and Gangways will be manufactured/fabricated at the selected contractors manufacturing/fabricating unit(s). Subsequently, these will be brought to the respective jetty locations and installed at the site. As such, any environmental impacts are likely limited to the area of the manufacturing unit(s). These are minor, reversible impacts that can be addressed through appropriate management measures. During the operation phase,

16 Press Information Bureau, Government of India, Ministry of Shipping, dated 26.03.2015

Potential Impacts and Mitigation Measures Page 67 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments these Gangways and Pontoons are not likely to cause any environmental/social impacts in the river or on the landside/riverbanks.

6.1.2 Waterside Construction Works Proposed developments activities will include minor waterside construction works mainly needed to put in place the new pontoons and gangways as well as some civil works at the link platform (concrete structure). The existing pontoons and gangways will be taken out and re- used at another existing or new jetty location under the WBTC (not part of the proposed development activities). The construction works at the jetty locations could cause some environmental/social impacts. These are minor, temporary and reversible impacts that can be addressed through appropriate management measures.

6.1.3 New Vessels First Year project investments will include modernizing the fleet through introduction of new vessels with enhanced designs. The vessels will be built at selected contractor’s vessel building yard(s). Subsequently, vessels will be deployed at respective jetty locations for its operation. In the manufacturing of these vessels, there would be minor, reversible environmental and social impacts. Further, during the operation of these vessels, there are environmental issues such as air pollution from the engines using diesel as fuel, noise pollution due to vessel operations, sewage/sullage generation and disposal, oil spills, etc. The impacts can be addressed through appropriate management measures.

6.1.3.1 Vessel Building Yard

During the ESIA study, consultants have visited vessel building yards in the project area. In general, most of the facilities available and activities being carried out at vessel yards are similar to each other. Also, as the pontoons and gangways would also be manufactured at similar yards, the facilities and activities remain the same. Exhibit 6-1 shows existing features at one of the vessel building yards in the project area. Some of the environmental/ social/health & safety related concerns at the vessel yard are mentioned below. These concerns need to be addressed by implementation of appropriate mitigation measures by the contractors to be selected for manufacturing operations in this project.

View of the Vessel Yard Gas Cylinders in the Open

Potential Impacts and Mitigation Measures Page 68 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Large Quantities of Oils/Paints in the Open Welding works without proper PPE

Paint Storage in Enclosed Area (Good Practice) Gas Cylinders in the Open

Waste Materials Accumulated at the Site Oil/Fluids Stored in the Open on Soil

Potential Impacts and Mitigation Measures Page 69 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

First Aid Kit at the Yard (inadequate) Fire Extinguisher at the Site Exhibit 6-1 Features at a Vessel Building Yard

6.1.3.2 Vessel Yard Observations Environmental/Social/Health & Safety related observations made at the vessel yard include: • Oils/fluids/lubricants seen stored in containers in the open areas • Several items stored at the facility – no labeling of the areas/items seen • No training program/new employee induction program in place • No programs in place for skill development • No process of worker safety/working conditions audits/inspections in place • Gas cylinders left in the open and can be exposed to extreme temperatures especially during summer seasons or rains during the monsoon • Several workers are not using the appropriate PPE; no program in place to ensure that workers are using the appropriate PPE while carrying out the works at the yards • Large quantities of waste materials seen at the site • First aid available at site is highly inadequate and not easily accessible • Fire safety equipment’s (like hydrants) are inadequate at the overall yard area • Lighting in the open yard working areas appears to be inadequate • The overall yard area needs to be organized in better way

6.1.4 Turnstile Gates Installation of Turnstile Gates at 40 selected jetty locations are proposed to be taken up under the First Year of investments. The turnstile gates will be built at the selected supplier’s production unit(s). Subsequently, these would be brought onto the jetty locations for its installation. As these are standard items that are manufactured under controlled operational facilities, minor environmental impacts could be envisaged which will be limited to the production unit(s) itself. Minor impacts could be due to activities such as metal cutting and painting in the supplier’s production unit.

6.2 General Impact Matrix

Proposed development will involve three stages, namely: Design/Build, Construction and Operation stage. These stages are likely to have varying levels of environmental and social impacts. Table 6-1 presents a brief summary of the activities and likely impacts it could have. Table 6-1 Potential Impacts of First Year Activities

Potential Impacts and Mitigation Measures Page 70 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Description of No. Likely Impacts Project Investments Mostly limited to the manufacturing facility: Gangways and 1 Generation of Solid Waste, Wastewater, Air Pollution, Noise Pollution, Worker Pontoons Safety and Labour / Worker Camps At the Jetty Locations: Waterside Construction Waste/Debris, Wastewater, Air Pollution, Noise Pollution, Water 2 Construction Works Pollution, Worker Safety, Community Safety and Temporary Community Disturbances Mostly limited to the Vessel Building Yard: 3 New Vessels Generation of Solid Waste, Wastewater, Air Pollution, Noise Pollution, Worker Safety and Labour / Worker Camps None to Minor environmental and social issues envisaged and limited to production 4 Turnstile Gates facility. Being a bought-out item, it is beyond purview of this ESIA study Based on the above matrix, the likely impacts from the activities of vessel manufacturing, pontoon and gangways manufacturing are similar. As such the impacts and mitigation measures for these activities will be discussed in common. Impacts and mitigation measures from the waterside construction works activities will be discussed separately. Further, Turnstile Gates being a bought out item, any impacts associated with this activity (although none to minimal envisaged). Accordingly, a schematic flow of the proposed development’s activities, its likely impacts and suggested mitigation measures are shown as Figure 6-1.

Activities

Manufacturing/ Operation Construction Stage Stage

Vessel Vessel Pontoon Gangway Waterside Movement Manufacturing Manufacturing Manufacturing Construction Works

Likely Likely Likely Impacts Impacts Impacts

Mitigation Mitigation Mitigation Measures Measures Measures

Figure 6-1 Schematic Flow of Activities, Impacts & Mitigation Measures

6.3 Vessel/Pontoon/Gangways Manufacturing

A typical vessel/pontoon/gangway manufacturing facility engages in various activities such as blasting, painting, metal plating, surface finishing, machining, metal working/welding, solvent cleaning, degreasing, etc. All these activities have potential to cause adverse impacts to air quality, water quality, soil, noise levels and also generation of solid wastes. Appropriate mitigation measures shall need to be in place to avoid/minimize likely impacts from these

Potential Impacts and Mitigation Measures Page 71 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments activities. The impacts anticipated during design, construction/manufacturing stage of the project and suggested mitigation measures are discussed below.

6.3.1 Vessel Building Process The manufacturing/building of a vessel is a highly technical activity which involves various activities and need for many skilled trades. The initial step is design of the vessel as per the specifications provided by the client. The basic component of a vessel building is steel plate. The plates are cut, shaped, bent or otherwise manufactured to the desired configuration specified by the design. Typically the plates are cut by an automatic flame cutting process to various shapes. The plates are then sent to fabrication units, where they are joined into various units and subassemblies to form the necessary structural members. At this juncture, piping, electrical and other utility systems are assembled and integrated into the units. The units are assembled using automatic or manual welding or a combination of the two. Several types of welding processes are employed (e.g. stick welding, inert gas shielded arcs, etc.). The units or subassemblies are usually then transferred to an open-air platen or lay down area where erection, or joining of assemblies, occurs to form even larger units or blocks. At this stage the units are abrasive blasted to ensure proper profiling, and painted. Paint may be applied by brush, roller or spray gun. The completed larger units are then moved to the final assembly area. Here, the larger units are joined together to form the vessel. Again, welding and fitting is involved. Once the hull is structurally complete and watertight, the vessel is launched. This may involve sliding it into the water from the shipway on which it was constructed, flooding of the dock in which it was constructed or lowering the vessel into the water. After the ship is launched, it enters the outfitting phase. A large amount of time and equipment are required. The work includes the fitting of cabling and piping, furnishing, insulation works, installation of electronic equipment, installation of propulsion and ancillary machinery, etc. After completion of the outfitting phase, the vessel undergoes trials, during which the entire vessel’s systems are checked for proposer functioning and operations. Finally, after all testing and associated repair work is performed, the vessel is delivered to the customer for its operations.

Pontoons and Gangways also in general go through similar stages for its manufacturing

6.3.1.1 Typical Pollutant Outputs at Vessel Yards

Primary raw material inputs to vessel building activity are steel and other metals, paints and solvents, blasting abrasives, machine and cutting oils. Pollutants and wastes typically generated include VOCs, particulates, waste solvents, oils and resins, metal bearing sludge and wastewater, waste paint, waste paint chips, spent abrasives, etc. Major vessel building activities that generate wastes/pollutants include welding, surface preparation and painting. Welding: is a source of air pollution. The main emission potentials from welding are Particulate Matter (PM). The impact of PM emitted from welding operations is localized and no impacts on the surrounding areas are envisaged. Surface Preparation: this activity includes high pressure blasting works and is also a source of pollution. Material inputs used for preparing surfaces include: abrasive materials such as

Potential Impacts and Mitigation Measures Page 72 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments steel shot or grit, and cleaning water, detergents, etc. Air emissions from surface preparation operations include particulate emissions of blasting abrasives and paint chips. Particulates emissions can be blown off-site during high wind conditions. The primary residual waste generated will be a mixture of paint chips and used abrasives. In general impact generated due to the surface preparation activities will be localized at the vessel yard and impacts are not envisaged on surrounding areas. Painting: material inputs for painting are primarily paints and solvents. VOCs and HAPs from painting solvents are one of the most important sources of pollutant outputs from painting works. Water is also used for equipment cleaning when water-based paints are used. In addition, painting activities also are a source of residual solid wastes which include leftover paint, waste paint containers, spent equipment, rags and other materials contaminated with paint, spent solvents, etc.

6.3.1.2 Impacts on Air Quality

As discussed above, the sources of air emissions at the vessel/pontoon/gangway building facilities include activities such as blasting, painting, metal plating, surface finishing, machining, metal working/welding, solvent cleaning, degreasing, etc. Based on the mitigation measures proposed/implemented, the buildup of air pollutants is not expected to result in adverse impacts on neighbouring habitations.

6.3.1.3 Mitigation Measures • Store and handle the welding gas, paints and other chemicals according to applicable guidelines • Check gas cylinders regularly to avoid leakage • Use vacuum floor cleaners for abrasive material recovery • Dispose waste paint in the designated waste disposal facility • Use airless or high volume low pressure spray guns to reduce overspray • Use only Volatile Organic Compounds (VOC) free paints • Use airless high pressure equipment for drying metal plates to control fugitive emissions from surfaces • Use of water soluble fluids instead of oil-based fluids shall be practiced within the manufacturing facility • Ensure that surface preparation works are controlled; indoors if possible or by surrounding the work area with steel/plastic/fabric to help minimize dispersion of dust and grit during surface preparation works • Provide basic training/awareness on air pollution management to the workforce • Provide workers exposed to emissions with proper Personal Protective Equipment (PPE) • Ensure that Diesel Generator (DG) set, if to be used, has adequate stack height and acoustic enclosures • Emissions from the vessel/pontoon/gangway manufacturing activities (welding, blasting, painting, etc.) will mostly be restricted to the particular area of activities; hence impacts would be confined to the area of the manufacturing activities. As such, major concerns of air pollution from the vessel/pontoon/gangway manufacturing activities are not envisaged.

6.3.1.4 Impacts on Noise Levels/Quality

Typical noise generating sources at the vessel/pontoon/gangway manufacturing facilities are abrasive blasting, chemical/mechanical paint removals, metal working/welding, equipment

Potential Impacts and Mitigation Measures Page 73 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments handling, vehicular movement, etc. The impact of the noise generated on the human settlements in the vicinity of the yards will be insignificant. Noise anticipated from the proposed project shall be confined only within the yard boundary and more precisely within the source area.

6.3.1.5 Mitigation Measures • Design the major noise generating equipment such that 85 dB(A) is the cumulative noise at a distance of 1 m • Maintain occupational noise exposure to the workers in the form of 8 hourly time weighted average within the prescribed OSHA standard limits • Provide for abatement of noise arising from equipment/ machineries, acoustic enclosures/silencers, etc. • Provide workers exposed to excessive noise with appropriate PPE including ear plugs, muffs, etc. • Ensure Diesel Generator (DG) set, if used, have adequate stack height and acoustic enclosures to minimise noise levels

6.3.1.6 Impacts on Water Quality

The water requirement for the manufacturing operations being carried out in open yard is almost nil except washing and cleaning. The manufacturing process does not require water. As such there shall be no effluent discharged from the vessel/pontoon/gangway manufacturing yards and hence no impact on surface water quality is envisaged. The manufacturing yards will have water requirement for workers consumption (drinking, bathing, toilets, etc.). This water requirement will be procured by the yard operators from municipality source and will not be a cause for conflict with local reserves. Typical activities to be carried out include abrasive blasting, chemical/mechanical paint removals, metal working/welding, equipment handling, vehicular movement, etc. The activities are in general carried out in open yard areas. The runoff from the yards containing manufacturing materials, waste/debris, oil/grease/lubricants, paints, etc. may have adverse impacts on the water environment if these are drained into it. This is especially so as the yards are in general located in the immediate vicinity of the Hooghly River banks. However, in general, manufacturing operations are temporarily suspended during the monsoon period; as such runoff from the yards should not be a significant source of water quality impacts. Hence, it can be said that the proposed development activities under First Year of investments does not have the potential of impacting the ground water quality in a significant manner in the long term and no significant impact on water quality is expected.

6.3.1.7 Mitigation Measures • Do not permit vehicle entry into water bodies • Avoid/Minimize spillage of pollutants like oils, fuels and grease etc. into the water body • Ensure that oil spill control/collection equipment is available at vessel yards • Clean up any spills in the yard area immediately to avoid runoff into the water body • Store contaminated soils, if any, properly in a covered area at the site before disposing it off-site through authorised vendors • Avoid indiscriminate dumping of wastes • Do not dump manufacturing wastes/debris into the water body, or in areas which can affect the flow of water or even cause reduction in width of the river • Do not store oils / fuels near the water body

Potential Impacts and Mitigation Measures Page 74 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

• Ensure that sites for disposal of manufacturing wastes/debris are identified and approved by authorized representatives prior to commencement of the manufacturing activities

6.3.1.8 Impacts Due to Solid Waste

Significant amount of solid wastes are generated from the vessel/pontoon/gangway manufacturing facilities. These includes steel plates/scrap, glass wool, empty containers, paint chips, used abrasives, rags, leftover paints, Oil and grease, inorganic salts, metals, etc. These need proper handling, transportation and disposal. Solid waste not handled properly at the yards will be a concern and lead to pollution issues.

6.3.1.9 Mitigation Measures • Ensure proper disposal of solid wastes so that it does not pose hazards to water, soil as well as health & safety issues • Store all hazardous materials (including paints & solvents), chemicals, etc. appropriately in designated areas • Handle with care all vessel insulation materials like glass wool as these are potentially hazardous substances • Ensure that solid waste generated shall be collected and stored in an organised manner at the site • Make necessary arrangements to dispose accumulated solid waste from the site in an appropriate manner through authorized vendors • Ensure that collection, storage and disposal of solid/hazardous waste shall be carried out as per applicable rules • Separate areas for storage of hazardous and non-hazardous solid wastes shall be provided at the facility

6.3.1.10 Impacts on Soil Quality

The activities can have impacts on soil quality in case of improper handling of items used in the manufacturing process such as steel plates, glass wool, empty containers, paint chips, used abrasives, rags, leftover paints, Oil and grease, inorganic salts, metals, etc. These need proper handling, transportation and disposal. Under ordinary and safe operating conditions, adverse impacts to the land/soil are not envisaged.

6.3.1.11 Mitigation Measures • Make available oil spill control/collection equipment at vessel yards; any spills at yard area shall be cleaned up immediately to avoid likely contamination of the soil • Store contaminated soils, if any, properly at the site before disposing it off-site through authorised vendors • Ensure there is no indiscriminate dumping of wastes • Do not dump or leave manufacturing wastes/debris unattended in the open yard areas • Store and place oils/fuels in designated areas to avoid spills onto the soil • Store hazardous wastes like used oil in HDPE containers and on paved surfaces in isolated location to prevent its spillage and contamination of soil • Ensure no deviations from the hazardous waste management rules • Provide waste collection facilities at the work areas

Potential Impacts and Mitigation Measures Page 75 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

6.4 Waterside Construction Works

The impacts & mitigation measures related to the waterside construction works is only limited to the construction stage. This will not be an operational activity.

6.4.1 Construction Works Proposed development activities under the First Year Investments will involve minimal waterside construction works. The works will be for installation of the pontoons and gangways, repairs at the jetty locations, civil works at the concrete link platforms, dismantling of existing structures, if any, and construction of new jetties (not to be taken up in First Year of investments) & renovation of existing jetties.

6.4.1.1 Impacts on Land Acquisition/Land use

Typical construction activities involve alterations in the local physiographic and drainage patterns, especially when activities are near water bodies. The impacts on physiographic may include destabilization of slopes due to cut and fill operations. However, the proposed development being limited to minor construction works for installation of the factory made gangways and pontoons, such impacts are not bound to occur. Also, the proposed development is not envisaged to result in loss of productive land. Proposed development under the First Year of investments will be carried out within existing jetty locations and will not involve additional land requirements. As such, proposed development will not result in Land Acquisition (LA). Hence there are no impacts of the project on Land Acquisition.

6.4.1.2 Mitigation Measures

Proposed development will not involve LA; however, there are likely temporary impacts to some squatters/vendors operating at the jetty locations. Appropriate compensation/ assistance as per provisions mentioned in the RPF shall be provided, i.e. The kiosks and vendors affected by way of moving out their business temporarily for project works will be provided with one financial assistance . A minimum wage of Rs.8,177/- per month to each affected commercial structure for the number of days it loses its livelihood, provided that there should be loss of livelihood more than 10 days. However, for losses less than 10 days, the wage would be calculated on a pro-rata basis.

6.4.1.3 Impacts Causing Soil Contamination

Soil contamination can take place due to solid waste contamination from construction activities, possible labor camps set up at project location, oil leaks from vehicles, construction equipment’s, concrete mixers, etc. Contamination of soil can be a major long-term residual negative impact if appropriate mitigation measures are not in place. Development activities are to be carried out along the waterside. The soils at the river banks will be exposed to contamination from the construction works at the jetty locations. Construction debris is also a likely cause for soil contamination if not handled appropriately. The debris arising out of construction activities can have impacts to alterations in the local physiographic and drainage patterns, especially when activities are near water bodies. The impacts on physiographic may include destabilization of slopes due to cut and fill operations. However, the proposed development being limited to minor construction works for installation

Potential Impacts and Mitigation Measures Page 76 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments of the factory made gangways and pontoons, such impacts will be minimal and mitigation measures are not warranted.

6.4.1.4 Mitigation Measures • The scale of construction activities at the jetty locations being very minimal, the project will not involve setting up labour camps at the project area; as such any impacts from labour camps will not be applicable • Should not dispose construction waste debris, if any, at the river banks and should not be left unmanaged at the project site • Enforce hazardous waste management rules • Clean up oil spills, if any, on river banks during construction immediately; Dispose contaminated soils appropriately • Make sure that good practices for solid waste management shall be in place • Give general awareness to workforce not to dispose any waste materials onto river banks • Provide waste collection facilities at jetty locations

6.4.1.5 Impacts on Air Quality

Development activities are limited to minor construction works at the site for installation of the factory made gangways and pontoons. As such, the activities are not envisaged to cause significant air quality impacts. The impacts, if any, will be short term in nature. Site activities would likely involve minimal site clearance works. There will be activities such as vehicular movements to bring in the construction materials/workers, use of concrete mixers on site, etc. Some amount of dust could be generated from these activities. Also, use of construction equipment’s, construction works vehicles, could have generation of some exhaust gases. In typical construction works, emissions from construction machinery are one of the major sources of ambient air pollution during construction stage. Continuous use of concrete mixers, generators, trucks, etc. give rise to the ambient air quality parameters (like NOx, SOx, etc.) to levels which may exceed the permissible concentration limits. High levels of SOx, HC, are likely from concrete mixer operations. However, considering scale of this development being relatively very small, such emissions related impacts are not envisaged.

6.4.1.6 Mitigation Measures • Conduct a baseline study to assess the condition of anticipated components to be affected (water quality, noise levels, soil quality, river bed sediments, aquatic ecology, river morphology) for ascertaining impacts on air quality, water quality, noise and debris as a result of dredging (not envisaged for works under First Year investments) and project activities • Regulate or control movement of construction materials and workers to the project site by using water transport mode (ferries/boats) • Movement of material shall be mostly during non-peak hours and shall be regulated during peak hours • Provide dust covers (tarpaulins, etc.) for trucks/vehicles, as well as boats/vessels, used for transporting materials to minimize dust emissions • Periodically wash to remove all accumulated dirt/waste from construction equipment and transport vehicles • Regularly clear all construction debris from the site • Ensure that (contractor) concrete mixer plants, if operating at the sites, are away from residential areas

Potential Impacts and Mitigation Measures Page 77 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

• Provide Pollution Under Control (PUC) certificate for Contractors equipment’s and machinery as per prevalent norms during construction period • Do not permit idling of construction vehicles/equipment when they are being loaded/unloaded or not in active use • Use low emission construction vehicles/equipment’s for all activities • Grow native species of plantation at river banks as a long term approach

6.4.1.7 Impacts on Noise Levels/Quality

Typically the activities that have an impact on air quality will also tend to have an impact on noise levels. During the construction stage, major sources of noise pollution would be from movement of vehicles transporting the construction material/workers, pile driving activities (at locations where concrete piling is needed) and the various constructions related activities. These impacts will be spread throughout the construction period. However, the impacts during construction are short-term in nature and will cease on completion of the construction.

6.4.1.8 Mitigation Measures • Use well-maintained construction equipment, which meets regulatory standards for source noise levels • Orient equipment emitting high noise, wherever possible, so that the noise is directed away from sensitive receptors and provide noise shields (like a physical barrier, etc.) • Shall not use machineries for extensive period of time during night hours • Restrict all construction activities that will generate disturbing sounds to normal working hours • Provide noise shields around stationary noise producing sources such as generator sets • Provide noise protection personal protection equipment (earplugs, earmuffs etc.) to those working very close to the noise generating machinery

6.4.1.9 Impacts on Water Quality/Resources

During construction phase of the proposed development use of water for construction purposes and disposal of construction waste into the water bodies may affect the quality of water in the project area. The main activities at site would mostly be installation of the factory made pontoons and gangways. As such need for water for construction works would be very minimal. Also, the works under the First Year investments are not envisaged to involve dredging. Dredging will be avoided to the maximum possible by adopting measures such as increasing the length of the link platform to get to deeper water areas rather than dredging in the shallower areas nearer to the bank, if such a case exists. Also, use of rail piles will be preferred over concrete piles which will help reduce piling works and minimize disturbance to the river beds. Hence the construction works at the jetty locations are not envisaged to have impacts on the water resources of the area. Impacts on water quality during the construction works could be due to disposal of construction debris into the water body, debris from dismantling of existing structures, if any, contamination by fuel and oil from construction vehicles/equipment’s, accidental spillage of construction material such as bentonite clay, concrete mix, etc. Impacts can also be envisaged during construction activities while erecting the piers at the jetty locations which will include this in its development. Impacts could mainly be due to disturbance to the sediments, spills into the water, increased turbidity, etc. However, in general, the proposed project is not expected to alter the existing water quality on a permanent basis.

Potential Impacts and Mitigation Measures Page 78 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

6.4.1.9.1 Design Considerations With regard to the likely impacts on flow of water in the Hooghly River due to construction of piers for the link platform at selected jetty locations, necessary design considerations have to be taken to address this likelihood. Use of Rail Piles shall be preferred in cases of longer link platforms. In other cases, circular shapes of piers shall be used, which will help minimize obstruction of water flow in the river as compared to rectangular/square shaped piers.

6.4.1.10 Mitigation Measures • No vehicle entry to water body will be permitted • Use PUC certified vehicles only • Restrict total number of vehicles to minimum • Ensure good practices and take precautions to minimize the risks of spillage of pollutants like oils, fuels, grease, etc. into the water body • Ensure Oil spill control/collection equipment’s are available at the project sites • Operate all activities on an impermeable Cement Concrete (CC) platform and collection and disposal of POL waste thus precipitated to the local PCB approved vendors • Indiscriminate dumping of wastes will not be permitted under any circumstance’s • Do not dump Construction debris into the water body, or dumped in areas which can affect the flow of water or even cause reduction in width of the river • No unauthorized clearing of vegetation will be permitted • Do not establish/locate construction mixers or other heavy machinery near water bodies • Identify and approve sites for disposal of construction and demolition wastes by authorized representatives prior to commencement of construction activities • Construction works of piers, where applicable, shall be taken up during lean flow periods to minimize impacts • Recirculate/Reuse bentonite clay and adopt better construction techniques to minimise spillage into water bodies Conduct necessary training(s) to provide instruction for workers working in water areas to prevent/minimise issues of contamination

6.4.1.11 Impacts on Flora and Fauna

Proposed development activities are to be taken up in the waterside areas of the jetty locations falling in the Hooghly River. The river is known to be in an ecologically stressed condition. Also, the development is to be taken up at the existing operational facilities itself. The project areas being operational jetty locations, there is considerable traffic and human activity at the locations. As such, no new impacts are likely to be introduced. As discussed in the baseline Sections 4.6.5.2 and 4.6.5.3, we see the project locations do not have any known endangered floral or faunal species. In general it can be concluded that proposed development is not envisaged to cause impacts to Flora and Fauna at the project locations.

6.4.1.12 Impacts to Aquatic Environment

Proposed development being on the waterside of the jetty locations in the Hooghly River will have some construction activities to be carried out in the aquatic environment. Construction of piers17 will be needed at selected jetty locations where construction would be directly in the water body.

17 Pier is an upright support for a structure or superstructure such as bridge, arch (link platform in the present scenario).

Potential Impacts and Mitigation Measures Page 79 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Construction of link platforms involves excavation of riverbed and banks for the construction of the foundations and piers. If the residual spoil is not properly disposed off, increased sedimentation downstream of the jetty location is likely. Movement of the sand of bottom of the river during erection of the piers will cause disturbance to the sediments and most likely produce muddy water, although temporarily. Increased turbidity, oil spills, construction material/debris getting into the water body, spillage of other residues, obstruction of drainage patterns/flow of water due to inappropriate dumping of debris, etc. are some other likely impacts during construction works in riverine/aquatic environment. Also, construction activities like manoeuvring at the jetty locations, construction of piers/jetty structures, dismantling of existing structures, if any, have potential to impact aquatic ecology of the area, which includes the dolphins.

6.4.1.13 Mitigation Measures

The construction/widening of the link platform if to be taken up will likely involve piling activity. Piling is proposed to be carried out by use of bored cast-in-situ concrete piles by use of a permanent liner by rotary drilling. The liner will ensure stability of the borehole as the liner is lowered into the riverbed. As the liner is lowered, soil material from within will be flushed out and deposited back in the surrounding area of the pile. Thereby the soil will mix and settle back into its same origins. Concrete will be poured into the liner through mechanized systems ensuring complete control on the concreting activities. This will help avoid any discharge of concrete slurry into the water body. This method of piling will help to avoid the use of bentonite slurry as a medium used in some other piling methods to stabilize sides of the boreholes. As such, proposed method will avoid impacts caused due to use of bentonite slurry. Turbidity due to the piling works is possible. Since rotary drilling is proposed to be adopted the period of turbidity will be drastically reduced when compared to conventional piling. Also, a cast-in-situ pile eliminates/reduces need for pile driving machinery, thereby reducing noise/vibration impacts and also turbidity. As a behavioral response, instinctively animals at the first encounter avoid approaching the site of unknown object. As such, it would be most likely those aquatic animals, if any at the site of construction works would move away from the area as soon as they sense unknown objects/activities in the area. Additionally, these construction works are to be taken up at areas where jetty movements are already in place as a result of which presence of aquatic animals at the location would be minimal to begin with. Nevertheless, certain mitigation measures shall be in place to ensure no impacts to the aquatic animals, particularly the Gangetic Dolphins, during the construction works. Such measures include: • For carrying out the piling works, carefully determine drop sites before anchor placement to ensure aquatic animals (dolphins and fish communities) that could be present in the area move away and are not impacted • Before starting piling allow some time for the aquatic fauna, if any, to move away from the works area. Measures such as bubble curtains shall be put in place to displace the aquatic fauna prior to piling works/construction activities • Piling works must be carried out in shortest possible timeframe • Debris generated from the construction works should be disposed away from the water body/banks • Noise reducing devices like mufflers, enclosures shall be fitted with the equipment wherever feasible • Piling/construction works in the water area should be stopped immediately if any dolphin is sighted in the activity area or its immediate vicinity

Potential Impacts and Mitigation Measures Page 80 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

• All construction equipment’s shall be maintained in good condition to prevent/minimise noise, leaks or spills of materials like hydraulic fluid, diesel, gasoline, etc.

6.4.1.14 Impacts on Socio-Economic Environment

Proposed development activities under the First Year of investments will not involve any Land Acquisition. In addition, impacts due to resettlement & rehabilitation are also not envisaged. There are likely minor temporary resettlements of some vendors/squatters at few jetty locations that could be needed. Appropriate measures will be in place to ensure their livelihood is not affected. As such, proposed development activities under First Year investments will not have adverse social impacts. The development will however have several positive impacts to the social environment in the project area. The development will provide employment opportunities to several people at the vessel/pontoon/gangway manufacturing yards as well as the jetty locations for civil works. Although the workforce requirement will be temporary in nature, it will be met from the local populace as far as possible hence there will be positive impact in terms of local resource utilization. There will be opportunities for several material suppliers and its associated activities (like transportation, etc.). Demands generated from the project works for basic facilities will increase the local business activity of the area. Any development, either temporary or permanent will be beneficial to the socio-economic environment The adverse impacts of the project activities will be almost none whereas several positive impacts can be envisaged. Hence, in addition to enhancing the existing jetty facilities, the project development activities will also provide several temporary/short-term benefits. As such proposed development activities will have an overall positive impact to the socio-economic environment.

6.5 Operation Stage (Vessel Movement)

The operational activity per se amongst the vessel/gangway/pontoon manufacturing and minor waterside construction works is the vessel movements. As such impacts would be associated with the vessel operations as discussed below.

6.5.1 Vessel Movement In the current scope of development, the operational activity would be the vessel movements itself. Proposed development is taken up with the intent to enhance the existing operations. New vessels will be introduced having significantly better facilities (e.g. better noise control measures, newer engines with lesser emissions, better facilities for oil storage, toilet facilities, etc.) than many of the existing vessels. As such, the enhanced facilities/vessels will be envisaged to have more positive impacts than adverse impacts.

6.5.1.1 Impacts due to Vessel Movement

Anticipated impacts due to the vessel operations include: • Excessive noise from vessel engine operations • Emissions from vessel engine operations • On-board storage of fuel, oils, etc. could cause impacts (spill into the waters, safety hazards, etc.) if not stored/handled appropriately • Bilge water from the vessels can be a source of pollution if not handled appropriately

Potential Impacts and Mitigation Measures Page 81 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

• Oil/fuel spills from vessel operations also during fuelling • Human safety and property loss could happen due to fire accidents caused by hazardous material handling, vessel grounding • Sewage disposal into the river from the vessels • Sewage disposal from toilet facilities at the jetty locations • Although, vessel movement is an existing activity in the project area and aquatic life is not as such impacted, there could be rare occurrences of impacts on the aquatic life (which includes Dolphins); dolphins typically are understood to keep themselves away from the navigational areas; however, it can happen that a dolphin strays into the navigational areas and can be subjected to impacts due to vessel movements (vessel collision, propeller related injuries, etc.) • Dolphins could be subject to impacts of disturbances caused due to vibrations in the vessels, pollution from the vessel movements, etc. • Waste dumping into the water body by commuters/ferry operators • There could be likely instances when commuters dispose of waste materials onto the river banks. This, over a period of time, depending on the type of waste material (paper, food wastes, etc.) and if kept on accumulating could cause concerns on soil contamination • Uncontrolled movement of commuters/locals at the jetty area, Pontoons, Gangways are likely • Over loading of the vessels is likely to happen if not controlled properly

6.5.1.2 Mitigation Measures • Ensure vessels have facilities for Bilge Water Holding and are supported with necessary pump system to pump it to the receiving facility at the terminals; bilge water from vessels shall not be discharged into the water body • Ensure the terminals have adequate provisions for receipt of the bilge water from the vessels which shall then be disposed off-site appropriately • Vessels shall be fitted with Bio Toilet facilities. • Provide Sewage/waste collection facilities at terminals which can collect sewage/waste from vessels and dispose it appropriately • Conduct periodic maintenance works for the engines and overall vessels as per the requirements to ensure efficient operations and control/minimise of pollution from engine emissions • Provide appropriate sound proofing for vessel engine room so that the engine noise is curbed • Appropriate facilities shall be provided on board the vessels for safe storage/handling of fuels, oils, any other hazardous materials • Provide all safety provisions in the Vessels as per navigational requirements (life buoys, safety vests, etc.) • Vessel operators shall be well trained and have necessary certifications/licenses to operate the vessels • Fueling for vessels shall be done with proper care to avoid spills • Vessels shall have necessary oil spill control/collection systems; spill kits shall also be made available at fuelling locations. • Provide appropriate oil spill control/collection equipment’s at Jetty locations • Ensure controlled /disciplined entry/exit from/to the vessels • Waiting on pontoons/gangways shall not be permitted • Once vessel leaves, commuters for next vessel shall stand behind a gate at jetty; gate shall be opened only after a vessel arrives and commuters from it have alighted and left the jetty

Potential Impacts and Mitigation Measures Page 82 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

• Over loading of the vessels shall not be allowed

6.5.1.3 Mitigation Measures (specific to aquatic life/dolphins) • Food items shall not be thrown into the river (especially by the ferry commuters) as it will attract the fishes including Dolphins towards it • Awareness on the importance/sensitivity of the dolphins should be created; all staff/operators should be given instructions that no dolphin or any other endangered species should be harmed due to any reason; signboards displaying the importance of the dolphin species in particular should be placed to create more awareness amongst the commuters/general public • Project vessels being operated in an aquatic environment, mechanisms like sound emitting devices/dolphin deterrent devices18 in the waters can be adopted which will alert the aquatic species of approaching vessels • Vessels should be fitted with propeller guards, aquatic deflectors to minimize impacts to aquatic fauna (especially if a dolphin which might drift into project corridor stretch) • The vessels will have in place design considerations to minimize vibrational effects • Vessel operators shall be vigilant while operating the vessels and shall look out for signs of aquatic life (especially dolphins) along their route of operation • If any aquatic mammal/dolphin is spotted, then measures to push it away should be taken up (through use of sirens/signals, creating noise signals); the operator should communicate to other operators in the area about the presence of a dolphin in the area; vessel movement operations should be immediately suspended until it is confirmed that the dolphin has moved away from the area of vessel operations • Vessel operators shall be instructed to immediately report to the terminal authority in case of any accidents involving aquatic fauna especially Dolphins • The enhanced vessels and other facilities at the jetties proposed under this development will avoid/minimize several pollution, vibration related issues and as such the development in itself will be an overall positive mitigation measure especially to the aquatic life in the area, including the Dolphins.

6.5.1.4 Impacts on Health & Safety

There is several health and safety related issues concerning manufacturing of vessels/ pontoons/gangways at the yards as well as waterside construction activities. The health and safety concerns as understood from visit of a vessel yard are discussed under Section 6.1.3.1.

6.5.1.5 Mitigation Measures

The mitigation measures are essentially best management practices that need to be in place and ensured these are followed at the workplace/yards. • Create awareness on OHS during site meetings • Provide safety gadgets for all workers engaged in places of work hazards with appropriate PPE (protective footwear, helmets, gloves, earplugs, safety belt when working at higher platforms, face masks, etc.) • Ensure facility management to the PPE used at all times as per the work situation • Make available facilities like first aid; it shall be well stocked and easily accessible to all • Comply with all site rules and regulations

18 Dolphin deterrent devises are a mechanical audio signal generating instrument which can generate ultrasonic signals to keep dolphins away from the activity area

Potential Impacts and Mitigation Measures Page 83 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

• Ensure suitable transport facility to take any injured/sick worker to nearest hospital immediately • Ensure facilities for safe potable water supply to the workers on site; adequate sanitation facilities shall be made available at the workplace/yards • Ensure transportation, handling and storage of hazardous materials are handled safely by experienced/trained personnel • Post safety signs at facility as per the need • Provide adequate facility and adequate provisions of fire safety equipment’s/measures spread throughout the facility • Make sure that entry and exit points are always kept clear of materials/ equipment’s/ debris, etc. • Maintain all work areas clean; areas shall be provided with optimum lighting • Conduct regular training sessions at the workplace to ensure all workers are aware of general safety measures, awareness on safe working practices, explaining clear procedures, etc. • Provide Workforce facilities such as health check-ups • Strictly follow the provisions of statutory Child Labor Act by the yard/site management • Conform to the relevant Indian Standard Code for All machines/equipment’s to be used at the manufacturing facilities; machines/equipment’s shall be kept in good working condition, be regularly inspected and properly maintained as per IS provision; Ensure safety features of equipment and machines are functional • Demarcate construction work zones and maintain strict adherence so that no community members are exposed to construction hazards and risks • Report and investigate any near misses, accidents and injuries and record remediation actions to avoid future occurrences • Apply sanctions where safety procedures are not adhered to • Monitor all parameters that include the conduct safety awareness sessions, the upkeep/condition of the on board safety provisions, the occurrence of near miss and safety incidents, and preventive and corrective actions taken

6.6 Impacts Screening Matrix Based on the ESIA, an impacts screening matrix is prepared and presented as Table 6-2. The matrix presents a summary of potential impacts due to various project activities and indicates its level of significance viz. Insignificant, Small, Moderate and Major. The different levels of significances can be rated as follows: • Insignificant – none to extremely minimal impacts; impact can be easily absorbed without requiring much efforts • Small – minimal impacts mostly short term; impact can be absorbed with minimal mitigation measures/efforts • Moderate – beyond minimal but mostly reversible; impact to be absorbed with higher level of mitigation measures/efforts and resources • Major – irreversible impacts, likely long term; impacts require extremely high level of mitigation measures/effort and resources to be in place to be handled

Potential Impacts and Mitigation Measures Page 84 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Table 6-2 Potential Impacts Screening Matrix Significance

Project Activities Concerns Small Major Moderate Insignificant Manufacturing Works Vessel, Pontoon, Air Pollution, Water Pollution, Noise Levels, ● Gangways Soil Contamination, Solid Waste Manufacturing Workers health & safety ● Waterside Construction Works Site surveys & Destruction of vegetation/landscape ● investigations Displacement of population Not Applicable Loss of livelihood (squatters, vendors – non ● Land Acquisition & title holders) Resettlement Displacement of structures and disruption to ● services (during construction) Loss cultural heritage Not Applicable Loss of Top soil and change in characteristics Not Applicable Loss of trees & vegetable cover Not Applicable Construction Site Noise, vibration and dust nuisance from site Clearance ● clearance activity Demolition, removal of existing infrastructure ● Construction camp Friction between construction personnel and ● establishment & local population operation Water pollution from sanitary and other wastes ● Overloading of road structures & damage to pavement (will have movement on waterways ● Mobilization of heavy as much as possible) machinery Inducement of traffic congestion & road safety ● hazards Disturbance of sediments / deterioration in water quality, when construction activities ● Construction of carried along/in water bodies structures Air Pollution, Water Pollution, Noise Levels, Soil Contamination, Solid Waste issues due to ● construction activities Workers health & safety ● Construction works Disturbance to aquatic fauna (including ● Dolphins) Operation Phase Pollution from oil spills from vessels ● Disturbance to aquatic fauna (including Operation ● Dolphins) Workers health & safety ●

Potential Impacts and Mitigation Measures Page 85 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

6.7 Indirect impacts

The likely sources of indirect impacts include (i) increased vessel and human traffic; and (ii) replacement of old gangways and pontoons. Increase in vessel numbers will improve the currently congested water way transportation system. The daily volume of passengers using the existing vessels, pontoons and gangways is 200,000. The 22 new vessels which will be added as part of first year investment will absorb 10 percent of the daily volume of passengers. As such, increase vessel numbers will improve passengers’ safety with no indirect impacts. Given the shortage of vessels there is no plan to replace vessels in the first-year investments. Regarding replacement of gangways and pontoons, most of the gangways and pontoons may not be replaced as the plan is expand some of them for providing safety to passengers. Those that will be replaced will be transferred to recycling facilities

6.8 Cumulative Impact Assessment

As described above, the first year investments are minor waterfront investments As such, they do not cause significant impacts on the Valued Ecosystem Components (VECs) in the project influence areas. Thus, no stand alone cumulative impact assessment is prepared for the first year investments. However, the project’s subsequent investments, particularly the land-based activities, have the potential to cause significant impacts on project influence areas and beyond. Therefore, a Cumulative Impact Assessment (CIA) will be prepared along with the Integrated Spatial Development Plan which will be finalized after the first year of the project. This Plan will determine not only subsequent investments that will be made under the project but also provide a road-map for future infrastructure investments.

Environmental Monitoring Environmental monitoring is one of the important components of the Environmental and Social Management Plan (ESMP). The monitoring will help identify the effectiveness of implemented mitigation measures. Any changes/additions that need to be made can be subsequently taken up based on the monitoring results/assessments. The suggested environmental monitoring is discussed elaborately in Section 8.3.

Potential Impacts and Mitigation Measures Page 86 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

7 Stakeholder Consultations & Information Disclosure

7.1 Introduction Stakeholder Consultations forms an important part of the ESIA process and is essential in achieving the overarching objectives of any project implementation to help ensure sustainable development. This consultation process is a major tool for information dissemination to the direct and indirect impacted due to the project. The stakeholder consultation process helps in reducing the public resistance to change and enable the participation of the local people in the decision making process. These consultations help to acknowledge the Project Affected Persons (PAPs), if any, about the project. Relevant information is exchanged, remarks, suggestions given by the people are noted. Such discussions benefit the overall design prospective as well. Stakeholder Consultations are continuous process which should be conducted throughout the project lifecycle. Stakeholder consultations can involve any direct or indirect impacted persons associated or affected. Stakeholder Consultation objectives are summarised as follows: • To create general public awareness and understanding of the project, and ensure its acceptance • To develop and maintain avenues of communication between the project proponent, stakeholders and PAPs in order to ensure that their views and concerns are incorporated into project design and implementation with the objectives of reducing, mitigating or offsetting negative impacts and enhancing benefits from the project • To inform and discuss about nature and scale of adverse impacts and to identify and prioritize mitigation measures for the impacts in a more transparent and direct manner • To document concerns raised by stakeholders and PAPs so that their views and proposals are mainstreamed to formulate mitigation and benefit enhancement measures • To sensitize other agencies/local authorities about the project and solicit their views and discuss their share of responsibility for smooth functioning of overall project operations

7.1.1 Modes of Stakeholder Consultations The various stakeholder consultations of the following order were conducted: • Informal consultations- Informal consultations are part of all site visits. This gathered maximum information from public. • Formal consultations-This part is taken up with formal communications and and identified stakeholders • Stakeholder workshop – This is a major stakeholder workshop inviting all important stakeholder’s.

7.2 Stakeholder Consultation Findings

Informal stakeholder consultations have been conducted at several jetty locations. Consultations included discussions with PMU team, ferry commuters/operators, locals in immediate vicinity of jetty locations (e.g. small shop operators just outside jetty area, daily- wage workers, rickshaw (auto, cycle, toto) operators, etc. The consultations were carried out by ESIA consultants in month of October 2019. In addition, a formal Stakeholder Conference was also held at the WBTIDCL office location on October 31, 2019. Few pictures taken during

Stakeholder Consultations & Information Disclosure Page 87 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments consultations process is shown as Exhibit 7-1. Additional details of the stakeholder conference are attached as Appendix 8. • State pollution control board • Inland water passengers ((men, • State environmental department women, students, elderly persons, • Passengers (commuters) people with disabilities, people of • Tourists different faiths, etc.) • Shop keepers • Vessel operators • Encroachers • Jetty operators • Squatters • Vessel suppliers • Vessel building yard workers • Workers in the jetties • Workers in the Vessels • Small scale unorganized illegal fishermen • Kolkata Municipal corporation (KMC) • Kolkata Port trust (KoPT) • WB Transport Infrastructure Development corporation

Consultations with PMU Team Consultations with Vendor

Consultations with Ticket Checker

Stakeholder Consultations & Information Disclosure Page 88 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Consultations with Small Shop Operators

Consultations with Ferry Operators

Consultations with Ferry Commuter Consultations with Locals

Stakeholder Conference at WBTIDCL Exhibit 7-1 Stakeholder Consultations In general, the participants were enthusiastic and appreciated the proposed project and gave valuable inputs over the development aspect, localized needs and suggestions for the design/construction of the project. They appreciated the fact that this project will help provide improved facilities at the jetty locations and provide added convenience to the commuters. Also, the non-commuters around the jetty locations (shop operators, rickshaw operators, etc.) also feel that improved jetty facilities would indirectly be beneficial to them as well (as more

Stakeholder Consultations & Information Disclosure Page 89 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments commuters could use the services, better arrangements at the jetty locations could minimise congestions outside the jetty areas, especially during peak hours, etc.). Following is a brief summary of the consultation inputs from the Stakeholder Consultations: • Need for widening of the gangway with a separate entry and exit points • Barricading on Pontoons and Gangway • Provision of roof on gangway/concrete ramps to Pontoon • Provision of better facilities at jetty area (waiting area, toilets, seating arrangements, fans, drinking water, etc.) • Request by workers on the pontoon for provision of rain/sun shade and seating facility on the Pontoons • Need for automatic ticket punching system • Proper displays and announcements at the jetty locations is essential • Increase frequency of ferries during peak hours would be beneficial • Provide facilities for handicap/elderly commuters (like wheel chair) • Regular maintenance of the jetty infrastructure shall be ensured; stakeholder consultations reveal that several commuters fear maintenance works are far lacking at the jetty locations (includes vessels, gangways, etc.) • Is understood that vessels get overcrowded during the peak hours • Some commuters try and get on and off board while the vessel is in motion which is a major safety concern • Adequate safety measures to be provided at all jetty locations • Vessel operators find it difficult to control the commuters during peak hours and it gets difficult to check if all commuters have paid for the commute or not • Bigger capacity vessel with better facilities shall be provided at locations with larger passenger movements • Passengers expressed willingness in temporary inconveniences to be faced during the construction period of the works Suggestions given by stakeholders have been looked into and whatever is found to be feasible will be incorporated into the design/planning and implementation of the project. Details of the stakeholder suggestions and its considerations are presented in Table 7-1. Table 7-1 Stakeholder Suggestions and Design Considerations S. No. Key Findings/Project Considerations Design/Implementation Inclusions 1. Widening of the gangway Gangways will be wider than existing gangways 2. Barricading on Pontoons and Gangway • Barricading on the Pontoons is understood to be not feasible from the operational point of view; hence cannot be taken up • Gangway design will include railings/protection 3. Provision of roof on gangway/concrete ramps to Provision of roof on gangway/concrete ramp (link Pontoon platform) is understood to be not feasible from the design/loading point of view; hence cannot be taken up 4. Provision of better facilities at jetty area (toilets, Design for the enhanced jetty locations will include drinking water, etc.) enhancement of the toilet facilities as well 5. Need for automatic ticket punching system This will be taken up under current scope of development 6. Proper displays and announcements at the jetty Design considerations will include display of locations is essential signboards at the jetty locations

Stakeholder Consultations & Information Disclosure Page 90 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

S. No. Key Findings/Project Considerations Design/Implementation Inclusions 7. Provide facilities for handicap/elderly These facilities are considered in the current scope commuters (like wheel chair) of development 8. Bigger capacity vessel with better facilities shall Proposed development will introduce 22 new 100 be provided at locations with larger passenger PAX size vessels replacing several of the smaller/ movements outdated vessels/boats

7.3 Planned Information Disclosure

The PMU will ensure that relevant information about environmental and social safeguard issues are made available in a timely manner, in an accessible place, and in a form and language(s) understandable to the public and other stakeholders. The purpose of such disclosure is that the public can provide meaningful inputs into project/subproject design and implementation.

7.3.1 At State Level This ESIA/ESMP will be disclosed at the state level in the project website. Print copies will be made available upon request at the PMU/WBTIDCL. Further, the executive summary of this ESIA will be available in English and translated to the local language, Bengali. This will also be available as an easy-to-download document in the project website. The website disclosure will be kept up-to-date throughout project implementation. In addition, the ESIA/ESMP (in hard copy) will be made available for public access at the local body authority offices of each of the jetty locations, and also at the jetty location itself. Also, the documents will be circulated to all stakeholder departments (like Irrigation and Waterways, KoPT, PCB, UDMA, Fisheries and IWAI).

7.3.2 On World Bank’s External website This ESIA/ESMP will be disclosed at the World Bank’s external website. This disclosure will be constantly updated as the project implementation progresses.

Stakeholder Consultations & Information Disclosure Page 91 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

8 Environmental and Social Management Plan

The main objectives of an Environmental and Social Management (ESMP) are to: • Identify key environmental/social issues envisaged to be encountered during design, construction and operation phases of the project • Provide guidelines for appropriate mitigation measures • Establish systems and procedures for implementing mitigation measures • Ensure that the mitigation measures are being implemented • Monitor the effectiveness of mitigation measures • Take necessary prompt action when unforeseen impacts occur • Develop an institutional framework which shall include/address the responsibilities for environment/social management and implementation of the measures The ESMP will be included as part of the bid/contract documents inviting bids for proposed development activities. The responsibility for the implementation and compliance of the ESMP thus would be binding upon the prospective contractor. The supervision will be responsibility of the PMU / WBTIDCL.

8.1 Components of ESMP

Anticipated environmental/social impacts and mitigation/avoidance measures for likely impacts have been discussed in respective sections in Chapter 6. The Environmental Monitoring Program (EMP) will be component of ESMP and is discussed in this chapter. Following specific environmental/social management aspects are discussed in this Chapter: • Summary of project activities, associated impacts and mitigation measures • Administrative and Technical Setup for Environmental/Social Management • Institutional Mechanism for Implementation of Mitigation Measures • Audits and Inspections • Grievance Redress Mechanism • Capacity Building Requirements

8.2 Environmental and Social Management Plan Matrix

This ESMP chapter presents summary of various project activities associated environmental/ social impacts and proposed mitigation measures as given in Table 8-1.

Environmental and Social Management Plan Page 92 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Table 8-1 Environmental and Social Management Plan Matrix Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring Vessel / Ferries Air pollution − Store and handle the welding gas, paints and other chemicals Parameters to monitor Manufacturing Pontoon / • Welding, Surface according to applicable guidelines include regular Contractor Gangway Preparation, Painting, − Check gas cylinders regularly to avoid leakage monitoring of air quality PMU – monitoring of manufacturing etc. causing air − Use vacuum floor cleaners for abrasive material recovery for all 12 air quality the activities emissions − Dispose waste paint in the designated waste disposal facility parameters as specified • Yard works causing − Use airless or high volume low pressure spray guns to reduce in the ESIA Appendix 4 dust emissions overspray to gauge air pollution • Diesel Generator (DG) − Use only Volatile Organic Compounds (VOC) free paints from regular sources sets causing − Use airless high pressure equipment for drying metal plates to (DG), fugitive sources emissions control fugitive emissions from surfaces and occupational health − Use of water soluble fluids instead of oil-based fluids shall be arising from air practiced within the manufacturing facility pollutants (VOCs). − Ensure that surface preparation works are controlled; indoors if possible or by surrounding the work area with steel/plastic/fabric to help minimize dispersion of dust and grit during surface preparation works − Provide basic training/awareness on air pollution management to the workforce − Provide workers exposed to emissions with proper Personal Protective Equipment (PPE) − Ensure that Diesel Generator (DG) set, if to be used, has adequate stack height and acoustic enclosures Noise levels − Design the major noise generating equipment such that 85 Parameters to monitor Manufacturing − Noise emissions from dB(A) is the cumulative noise at a distance of 1 m include noise levels Contractor manufacturing related − Maintain occupational noise exposure to the workers in the form within the premises and PMU – monitoring of activities of 8 hourly time weighted average within the prescribed OSHA occupational health the activities standard limits arising from exposure to Environmental and Social Management Plan Page 93 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring − Noise due to activities − Provide for abatement of noise arising from equipment/ noise (regular and like loading/unloading machineries, acoustic enclosures/silencers, etc. impact noise) for all four of steel plates and − Provide workers exposed to excessive noise with appropriate categories of noise other materials at the PPE including ear plugs, muffs, etc. zones as specified in building yards − Ensure Diesel Generator (DG) set, if used, have adequate stack Appendix 5 for Noise − Noise emissions from height and acoustic enclosures to minimise noise levels pollution. DG sets, if to be used Water Quality − Do not permit vehicle entry to water bodies All water quality Manufacturing − Water pollution − Avoid/Minimize spillage of pollutants like oils, fuels and grease parameters provided in Contractor resulting from etc. into the water body Appendix 6 to be PMU – monitoring of manufacturing related − Ensure that oil spill control/collection equipment is available at monitored. This the activities activities (mainly in vessel yards includes river water case of any runoff from − Clean up any spills in the yard area immediately to avoid runoff quality in the immediate the yards, oil spills into into the water body precincts and effluent the water body, etc.) − Store contaminated soils, if any, properly in a covered area at discharge quality into − Increase in turbidity the site before disposing it off-site through authorised vendors the drains or river for all − Change in water quality − Avoid indiscriminate dumping of wastes class of water. due to aqueous − Do not dump manufacturing wastes/debris into the water body, discharges or in areas which can affect the flow of water or even cause reduction in width of the river − Do not store oils / fuels near the water body − Ensure that sites for disposal of manufacturing wastes/debris are identified and approved by authorized representatives prior to commencement of the manufacturing activities Impacts Due to Solid Waste − Ensure proper disposal of solid wastes so that it does not pose Parameters to monitor Manufacturing − Waste generation due hazards to water, soil as well as health & safety issues include handling, Contractor to manufacturing − Store all hazardous materials (including paints & solvents), storage and disposal of PMU – monitoring of activities chemicals, etc. appropriately in designated areas hazardous waste and the activities ensuring no waste is Environmental and Social Management Plan Page 94 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring − Solid waste not − Handle with care all vessel insulation materials like glass wool disposed in to the drains handled properly at the as these are potentially hazardous substances or river. yards will be a concern − Ensure that solid waste generated shall be collected and stored and lead to pollution in an organised manner at the site issues (water pollution, − Make necessary arrangements to dispose accumulated solid soil contamination, waste from the site in an appropriate manner through authorized health & safety issues, vendors etc.) − Ensure that collection, storage and disposal of solid/hazardous waste shall be carried out as per applicable rules19 − Separate areas for storage of hazardous and non-hazardous solid wastes shall be provided at the facility Soil Quality − Make available oil spill control/collection equipment at vessel All parameters to Manufacturing − Likely soil yards; any spills at yard area shall be cleaned up immediately to monitor evidence of soil/ Contractor contamination resulting avoid likely contamination of the soil land contamination (e.g. PMU – monitoring of from manufacturing − Store contaminated soils, if any, properly at the site before oil/waste spillages) in the activities related activities disposing it off-site through authorised vendors the premises as per (mainly in case of oil − Ensure there is no indiscriminate dumping of wastes standard soil quality spills onto the soil, river − Do not dump or leave manufacturing wastes/debris unattended standards provided in banks, etc.) in the open yard areas Appendix 7. − Impacts due to disposal − Store and place oils/fuels in designated areas to avoid spills onto of solid waste the soil − Store hazardous wastes like used oil in HDPE containers and on paved surfaces in isolated location to prevent its spillage and contamination of soil − Ensure no deviations from the hazardous waste management rules

− 19 Hazardous Waste Management & Handling Rules, 2016

Environmental and Social Management Plan Page 95 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring − Provide waste collection facilities at the work areas Minor works for Debris waste − Minimise (or dispose off), debris arising out of construction Parameters to monitor Construction Contractor installation of the activities involving alterations in the local physiographic and include evidence of PMU – monitoring of pontoons and drainage patterns, especially when activities are near water debris waste in the river. the activities gangways bodies. The impacts on physiographic may include Repairs at the jetty destabilization of slopes due to cut and fill operations. However, locations the proposed development being limited to minor construction Civil works at the works for installation of the factory-made gangways and concrete link pontoons, such impacts will be minimal. In such cases no platforms specific mitigation measures are warranted. Dismantling of Soil Quality − Should not dispose construction waste debris, if any, at the river Parameters to monitor Construction Contractor existing structures, − Soil contamination due banks and should not be left unmanaged at the project site include evidence of PMU – monitoring of if any to construction works − Enforce hazardous waste management rules soil/land contamination the activities Construction of − Oil leaks from vehicles, − Clean up oil spills, if any, on river banks during construction (e.g. oil/waste spillages) new jetties & construction immediately; Dispose contaminated soils appropriately in the premises. renovation of equipment’s, concrete − Make sure that good practices for solid waste management shall existing jetties mixers, etc. be in place − Give general awareness to workforce not to dispose any waste materials onto river banks − Provide waste collection facilities at jetty locations Air Quality − Conduct a baseline study to assess the condition of anticipated All 12 Parameters to be Construction Contractor − Emissions / dust due to components to be affected (water quality, noise levels, soil monitored (see PMU – monitoring of site clearance works, quality, river bed sediments, aquatic ecology, river morphology) Appendix 4) include air the activities vehicular movements, for ascertaining impacts on air quality, water quality, noise and pollution from regular transport of materials, debris as a result of dredging and project activities sources - Diesel use of concrete mixers, − Regulate or control movement of construction materials and Generator (DG), fugitive etc. workers to the project site by using water transport mode sources and (ferries/boats) occupational health arising from air Environmental and Social Management Plan Page 96 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring − Movement of material shall be mostly during non-peak hours pollutants such as and shall be regulated during peak hours Volatile Organic − Provide dust covers (tarpaulins, etc.) for trucks/vehicles, as well Compounds (VOCs). as boats/vessels, used for transporting materials to minimize dust emissions − Periodically wash to remove all accumulated dirt/waste from construction equipment and transport vehicles − Regularly clear all construction debris from the site − Ensure that (contractor) concrete mixer plants, if operating at the sites, are away from residential areas − Provide Pollution Under Control (PUC) certificate for Contractors equipment’s and machinery as per prevalent norms during construction period − Do not permit idling of construction vehicles/equipment when they are being loaded/unloaded or not in active use − Use low emission construction vehicles/equipment’s for all activities − Grow native species of plantation at river banks as a long-term approach Noise Levels/Quality − Use well-maintained construction equipment, which meets Parameters to monitor Construction Contractor − Increased noise levels regulatory standards for source noise levels include noise levels for PMU – monitoring of due to movement of − Orient equipment emitting high noise, wherever possible, so that all four category/or the activities vehicles, pile driving the noise is directed away from sensitive receptors and provide zones provided in activities (at locations noise shields (like a physical barrier, etc.) Appendix 5 within the where concrete piling is − Shall not use machineries for extensive period of time during premises and needed), other night hours occupational health construction and − Restrict all construction activities that will generate disturbing arising from exposure to installation works sounds to normal working hours noise (regular and impact noise). Environmental and Social Management Plan Page 97 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring − Provide noise shields around stationary noise producing sources such as generator sets − Provide noise protection personal protection equipment (earplugs, ear muffs etc.) to those working very close to the noise generating machinery Water Quality/Resources − No vehicle entry to water body will be permitted Parameters to monitor Construction Contractor − Change in water quality − Use PUC certified vehicles only include river water PMU – monitoring of due to aqueous − Restrict total number of vehicles to minimum quality (as per the activities discharges − Ensure good practices and take precautions to minimize the Appendix 6) in the − Increase in turbidity risks of spillage of pollutants like oils, fuels, grease, etc. into the immediate precincts − Spill of Bentonite Clay water body and ensure no during pile driving − Ensure Oil spill control/collection equipment’s are available at additional effluent the project sites discharges into the river − Operate all activities on an impermeable Cement Concrete (CC) due to construction platform and collection and disposal of POL waste thus activities. precipitated to the local PCB approved vendors − Indiscriminate dumping of wastes will not be permitted under any circumstance’s − Do not dump Construction debris into the water body, or dumped in areas which can affect the flow of water or even cause reduction in width of the river − No unauthorized clearing of vegetation will be permitted − Do not establish/locate construction mixers or other heavy machinery near water bodies − Identify and approve sites for disposal of construction and demolition wastes by authorized representatives prior to commencement of construction activities − Construction works of piers, where applicable, shall be taken up during lean flow periods to minimize impacts Environmental and Social Management Plan Page 98 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring − Recirculate/Reuse bentonite clay and adopt better construction techniques to minimize spillage into water bodies Conduct necessary training(s) to provide instruction for workers working in water areas to prevent/minimize issues of contamination Impacts to aquatic − For carrying out the piling works, carefully determine drop sites environment (fishes, before anchor placement to ensure aquatic animals (dolphins dolphins, etc.) and fish communities) that could be present in the area move − Disturbance/dangers to away and are not impacted any fishes/dolphins at − Before starting piling allow some time for the aquatic fauna, if the construction areas any, to move away from the works area. Measures such as or its immediate vicinity bubble curtains shall be put in place to displace the aquatic fauna prior to piling works/construction activities − Piling works must be carried out in shortest possible timeframe − Debris generated from the construction works should be disposed away from the water body/banks − Noise reducing devices like mufflers, enclosures shall be fitted with the equipment wherever feasible − Piling/construction works in the water area should be stopped immediately if any dolphin is sighted in the activity area or its immediate vicinity − All construction equipment’s shall be maintained in good condition to prevent/minimize noise, leaks or spills of materials like hydraulic fluid, diesel, gasoline, etc. Land Acquisition, − No Land Acquisition is involved under development works in the As discussed in the RPF PMU (Social displacement and other First Year Investments; hence no compensations for land is Development social impacts involved Specialist) − Development needing − Proposed development will have temporary impacts to about 13 Land Acquisition petty vendors (combined total of all jetties); appropriate

Environmental and Social Management Plan Page 99 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring − Temporary impacts to compensations as per provisions mentioned in the RPF shall be vendors/squatters provided during construction − No impacts to cultural properties or other social impacts are activities at the jetty involved under development works in First Year Investments; locations hence no mitigation measures for this is warranted − Cultural property impacts and other social impacts Felling of trees − No felling of trees will be involved under development works in Parameters to include Construction Contractor First Year Investments; hence no mitigation measures for this is evidence of tree-felling PMU – monitoring of warranted at this stage that is not permitted/ the activities required Turnstile Gates, No onsite impacts; Waste − Ensure proper E&HS management at their manufacturing facility Nil Supplier Electronic Smart and debris generation by necessary provisions built into the goods procurement PMU Ticketing Gates at impacts in the supplier’s contract 40 jetty locations manufacturing facility All activities Health & Safety – − Create awareness on OHS during site meetings Parameters include H & Construction Contractor Construction worker and − Provide safety gadgets for all workers engaged in places of work S records of site PMU – monitoring of community hazards with appropriate PPE (protective foot wear, helmets, meetings, near miss the activities gloves, earplugs, safety belt when working at higher platforms, and accident reports face masks, etc.) − Ensure facility management to the PPE used at all times as per the work situation − Make available facilities like first aid; it shall be well stocked and easily accessible to all − Comply with all site rules and regulations − Ensure suitable transport facility to take any injured/sick worker to nearest hospital immediately

Environmental and Social Management Plan Page 100 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring − Ensure facilities for safe potable water supply to the workers on site; adequate sanitation facilities shall be made available at the work place/yards − Ensure transportation, handling and storage of hazardous materials are handled safely by experienced/trained personnel − Post safety signs at facility as per the need − Provide adequate facility and adequate provisions of fire safety equipment’s/measures spread throughout the facility − Make sure that entry and exit points are always kept clear of materials/equipment’s/debris, etc. − Maintain all work areas clean; areas shall be provided with optimum lighting − Conduct regular training sessions at the workplace to ensure all workers are aware of general safety measures, awareness on safe working practices, explaining clear procedures, etc. − Provide Workforce facilities such as health check-ups − Strictly follow the provisions of statutory Child Labor Act by the yard/site management − Conform to the relevant Indian Standard Code for All machines/equipment’s to be used at the manufacturing facilities; machines/equipment’s shall be kept in good working condition, be regularly inspected and properly maintained as per IS provision; Ensure safety features of equipment and machines are functional − Demarcate construction work zones and maintain strict adherence so that no community members are exposed to construction hazards and risks − Report and investigate any near misses, accidents and injuries and record remediation actions to avoid future occurrences Environmental and Social Management Plan Page 101 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring − Apply sanctions where safety procedures are not adhered to − Monitor all parameters that include the conduct safety awareness sessions, the upkeep/condition of the on board safety provisions, the occurrence of near miss and safety incidents, and preventive and corrective actions taken Public Safety and Security − Complete works on exposed trenches and earth materials Parameters include Contractors before new earth is dug and trenches are created community H & S PMU − Avoid inquisitive trespassers especially children by adequately records of site hoarding off work areas meetings, near miss − Post warning signs around work areas to discourage and accident reports trespassers and inform the public of the hazard − Maintain adequate security at construction sites to avoid pilfering or vandalising of property − Ensure visibility in the night time by providing adequate lighting − Equip vehicles with reflectors and adequate signaling during works − Ensure safety features of equipment and vehicles are functional − Discuss works procedures to be designed with workers before works commence each day to minimize accidents with communities Limited dredging impacts − Test any river sediment material generated at all the dredging Parameters include Construction Contractor when works are carried out sites to ensure there is no contamination instances of dredging, PMU – monitoring of alongside the river − If the dredged material is not contaminated, it will be used for quantity of dredged the activities rising of the terminal sites. Fill sediments in bunded areas to material and quality of avoid sediment laden runoff dredged material. The − If suitable and there is a demand, the excess dredged material, quality of dredged if any, will be used for other beneficial purposes such as rising material will be of public lands and selling to the willing buyers after an end user ascertained by chemical agreement/declaration Environmental and Social Management Plan Page 102 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring − If dredged material is contaminated, then it will be collected, tests for heavy metals stored and disposed in accordance with hazardous waste and pesticide content. management requirements with advice/knowledge of local PCB Managing Labour Influx − Main contractor will maintain separate registers for migrant Parameters to monitor Construction Contractor labour as per the Migrant Labour Act on all aspects include Labour influx PMU − Compile information like place of origin, contact details, next of − Local labourer kin details, etc. − Migrant labour − Ensure a labour code of conduct is signed by main contractor − Code of conduct and all the sub-contractors − Grievance − Treat all migrant labour in line / consistent with the other labour redressal including access to the GRM established for labour − Address threats either to the migrant labour or from migrant labour due to cultural differences in an amicable manner − Ensure no gender based violence in relation to all dealings with the migrant labour Cultural Heritage impacts − Apply chance find procedures in consultation with relevant NA Contractors authorities (as described in Appendix 3). PMU − Consult with local community and provide for any cultural use as per the community practices in the river Impacts in the contractor − Provide adequate sanitation facilities in line with government NA Contractors camps regulations PMU − Ensure proper housekeeping − Provide first aid boxes with required items Operational Stage Vessel Operation Potential impacts on air, − Ensure vessels have facilities for Bilge Water Holding and are Air/noise/water quality Ferry Operators noise, water, soil supported with necessary pump system to pump it to the monitoring shall be PMU environment, aquatic life receiving facility at the terminals carried out periodically (rarely envisaged), safety aspects, etc. Environmental and Social Management Plan Page 103 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring − Excessive noise from − Ensure the terminals have adequate provisions for receipt of the Parameters to monitor vessel engine bilge water from the vessels which shall then be disposed off- include fuel use & operations site appropriately efficiency levels, air − Emissions from vessel − Vessels shall be fitted with Bio Toilet facilities. emissions from the engine operations − Provide Sewage/waste collection facilities at terminals which can vessels, noise level of − Oil/fuel spills including collect sewage/waste from vessels and dispose it appropriately the engines, solid waste during fueling, fire − Conduct periodic maintenance works for the engines and overall storage & disposal, accidents, vessel vessels as per the requirements to ensure efficient operations toilet gray and black grounding and control/minimise of pollution from engine emissions water storage & − Bilge water from the − Provide appropriate sound proofing for vessel engine room so disposal, bilge disposal vessels if not handled that the engine noise is curbed appropriately − Appropriate facilities shall be provided on board the vessels for − Sewage disposal into safe storage/handling of fuels, oils, any other hazardous water body from materials vessels − Provide all safety provisions in the Vessels as per navigational − Sewage disposal from requirements (life buoys, safety vests, etc.) toilet facilities at jetty − Vessel operators shall be well trained and have necessary locations certifications/licenses to operate the vessels − Impacts to aquatic life − Vessels are suggested to have mechanisms like sound emitting (rarely envisaged) devices in waters which will alert fishes/aquatic life of − Waste dumping into the approaching vessels water body by − Fueling for vessels shall be done with proper care to avoid spills commuters/ferry − Vessels shall have necessary oil spill control/collection systems; operators spill kits shall also be made available at fuelling locations. − Safety issues if there is − Provide appropriate oil spill control/collection equipment’s at uncontrolled movement Jetty locations of commuters/locals at − Ensure controlled /disciplined entry/exit from/to the vessels Jetties, Pontoons, − Waiting on pontoons/gangways shall not be permitted Gangways Environmental and Social Management Plan Page 104 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring − Over loading of vessels − Once vessel leaves, commuters for next vessel shall stand behind a gate at jetty; gate shall be opened only after a vessel arrives and commuters from it have alighted and left the jetty − Over loading of the vessels shall not be allowed Impacts/disturbance to − Food items shall not be thrown into the river (especially by the NA Ferry Operators aquatic life including ferry commuters) as it will attract the fishes including Dolphins PMU dolphins due to vessel towards it movements − Awareness on the importance/sensitivity of the dolphins should be created; all staff/operators should be given instructions that no dolphin or any other endangered species should be harmed due to any reason; signboards displaying the importance of the dolphin species in particular should be placed to create more awareness amongst the commuters/general public − Project vessels being operated in an aquatic environment, mechanisms like sound emitting devices/dolphin deterrent devices in the waters can be adopted which will alert the aquatic species of approaching vessels − Vessels should be fitted with propeller guards, aquatic deflectors to minimize impacts to aquatic fauna (especially if a dolphin which might drift into project corridor stretch) − Vessel operators shall be vigilant while operating the vessels and shall look out for signs of aquatic life (especially dolphins) along their route of operation − If any aquatic mammal/dolphin is spotted, then measures to push it away should be taken up (through use of sirens/signals, creating noise signals); the operator should communicate to other operators in the area about the presence of a dolphin in the area; vessel movement operations should be immediately

Environmental and Social Management Plan Page 105 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Responsible Agency Monitoring Type of Activity Impacts Mitigation Measures for Implementation Measures and Monitoring suspended until it is confirmed that the dolphin has moved away from the area of vessel operations − Vessel operators shall be instructed to immediately report to the terminal authority in case of any accidents involving aquatic fauna especially Dolphins

Environmental and Social Management Plan Page 106 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

8.2.1 ESMP Integration to Bid Document The proposed development is to be taken up as a design/build contract. This ESMP will be included into the overall bid document. The ESMP will be added as an Appendix in the Construction Schedule section of the bid document. The Appendix section will have the technical Proposal Forms to be submitted which will include the Code of Conduct - Environmental, Social, Health and Safety (ESHS) and ESHS Management Strategies and Implementation Plans (MSIP). The ESMP will serve as a guidance document. The selected contractor shall prepare an Operational ESMP based on this ESMP which will form the MSIP; the MSIP which shall be approved by the PMU/PMC as well as the World Bank prior to its implementation at the project site by the contractor. As part of the bid document, the contractor will need to submit the following information: • Code of Conduct - Environmental, Social, Health and Safety (ESHS): The selected bidder shall submit its Code of Conduct that will apply to its employees and subcontractors, to ensure compliance with its Environmental, Social, Health and Safety (ESHS) obligations under the contract. In addition, the Bidder shall detail how this Code of Conduct will be implemented. This will include: how it will be introduced into conditions of employment/engagement, what training will be provided, how it will be monitored and how the Contractor proposes to deal with any breaches. The Contractor shall be required to implement the agreed Code of Conduct. • ESHS Management Strategies and Implementation Plans (MSIP): The operational ESMP mentioned above shall be the MSIP. The selected bidder shall submit the MSIP to manage the following key Environmental, Social, Health and Safety (ESHS) risks. o Traffic Management Plan to ensure safety of local communities from construction traffic as well as Vessel movements bringing in the newly built Gangways / Pontoons to jetty locations for installation; o Water Resource Protection Plan to prevent contamination in waters of Hooghly River; o Strategy for obtaining Consents/Permits prior to the start of relevant works; o Waste Management Plan (include measures for handling/disposal of waste/debris generated at workplace due to construction/manufacturing activities); o Plan for Storage/Handling of Oils/Fuels to address any spills; o Workforce Engagement Plan (including staff benefits, insurance, emergency responses in case of accidents, training, communication etc.); o Standard Operating Procedures (all the above may be covered under a Standard Operating Procedure including specific Health & Safety measures to be implemented at the work site). • The successful Bidder shall also be required to submit an Environmental, Social, Health and Safety (ESHS) Performance Security • ISO 14001 certificate, if available

8.3 Environmental Monitoring Program

Environmental monitoring is one of the important components of the Environmental and Social Management Plan (ESMP). The main aim of the monitoring is to establish the existing scenario to make informed decisions to ascertain the proper implementation. The main objectives of the environmental monitoring are: • To ensure the effective implementation of ESMP

Environmental and Social Management Plan Page 107 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

• To comply with all relevant environmental/social regulations • To modify the mitigation measures and implementation arrangements, if found necessary Nature of activities to be taken up under First Year investments is not envisaged to have significant sources of environmental pollution. As such, a minimal monitoring program is suggested and implementation of suggested mitigation measures is to be ensured. The Environmental Monitoring Program mentions the monitoring plan, specifies the parameters to be monitored, location, frequency and duration of monitoring as well as implementation and supervising responsibilities. The monitoring covering the First Year of investments (i.e. period of One Year) for environmental condition indicators during construction/manufacturing stage and operation stage (considered for Four Years period) of the project are presented in Table 8-2.

Environmental and Social Management Plan Page 108 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Table 8-2 Environmental Parameter Monitoring Program during Construction Stage Attribute Monitoring Measures Frequency Location Implementation Supervision Manufacturing/ Construction Works Parameters to monitor include regular monitoring of air quality for all 12 air quality parameters • Vessel/Pontoon/Gangway manufacturing as specified in the ESIA yards Manufacturing Once in a quarter during Air Appendix 4 to gauge air • Immediate vicinity of the yards Contractor/ PMU construction stage pollution from regular sources • At jetty locations of waterside areas of Construction Contractor (DG), fugitive sources and construction works occupational health arising from air pollutants (VOCs). Parameters to monitor include noise levels within the premises • Vessel/Pontoon/Gangway manufacturing and occupational health arising yards Manufacturing from exposure to noise (regular Once in a quarter during Noise • Immediate vicinity of the yards Contractor/ PMU and impact noise) for all four construction stage • At jetty locations of waterside areas of Construction Contractor categories of noise zones as construction works specified in Appendix 5 for Noise pollution. All water quality parameters provided in Appendix 6 to be • Water body in the vicinity of the vessel/ monitored. This includes river Manufacturing Water Once in a quarter during pontoon/ gangway manufacturing yards water quality in the immediate Contractor/ PMU Quality construction stage • Water body at jetty locations at waterside precincts and effluent discharge Construction Contractor areas of construction works quality into the drains or river for all class of water. All parameters to monitor • Vessel/Pontoon/Gangway manufacturing Manufacturing evidence of soil/ land Once in a quarter during yards Soil Contractor/ PMU contamination (e.g. oil/waste construction stage • At jetty locations of waterside areas of Construction Contractor spillages) in the premises as per construction works Environmental and Social Management Plan Page 109 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Attribute Monitoring Measures Frequency Location Implementation Supervision standard soil quality standards provided in Appendix 7. Operation Stage (Vessel Movements) Parameters as mentioned under Air At least twice a year • Vessels/Jetty Locations Vessel Operator PMU Construction stage above Parameters as mentioned under Noise At least twice a year • Vessels/Jetty Locations Vessel Operator PMU Construction stage above • Jetty locations Water Parameters as mentioned under • Water body along the route of the vessel At least twice a year Vessel Operator PMU Quality Construction stage above • In the upstream/downstream of river from route of vessel operation

Environmental and Social Management Plan Page 110 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

8.4 Implementation Arrangements and Responsibilities

A high-level Project Steering Committee headed by Chief Secretary will be the apex body. The West Bengal Transport Infrastructure Development Corporation Limited (WBTIDCL) will be the Project Management Unit (PMU). The Department of Industries, Commerce & Enterprises will lead the development of Logistics Master Plan and other related developments. The Urban Development Department shall lead for planning initiatives, including the spatial development strategy and the comprehensive mobility plan.

8.4.1 Institutional Set-up for the Project The overall institutional Framework for the WBTIDCL is provided in Figure 8-1. A project development specific Project Management Unit (PMU) will be in place under the overall framework. The PMU will consist of the Project Director, the Environmental & Safety Specialist, Social Specialist, Procurement Specialist and the PMC/ISBP consultant. PMU is discussed in Section 8.4.3.

Figure 8-1: Overall Institutional Framework for WBTIDCL

8.4.2 Institutional Strengthening and Business Planning (ISBP) This will include strengthening the planning process, improving inter-agency decision-making and supporting the modernization of the IWT system. The nodal agency for this activity will be the Transport Department. Shortly an agency will be entrusted to look after this work for a period of three years. The ISBP agency will have a Project Management Consulting (PMC) unit with a dedicated Environmental/Social Expert to look after the Institutional Strengthening part of the Waterways Sector.

Environmental and Social Management Plan Page 111 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

8.4.3 Project Management Unit (PMU) The WBTIDCL is the overall PMU unit operating under the West Bengal Transport Corporation (WBTC). It serves as a dedicated Engineering Wing for taking up development works for WBTC. WBTIDCL will be the PMU for the proposed development works as well. The Project Director (PD) will have the overall responsibility whereas a dedicated Environmental Specialist and Social Development Specialist will have day-to-day implementation responsibilities. In the current institutional arrangement, the Environmental Specialist will also coordinate the safety management functions. Thus the position under the PMU will be Environmental and Safety Specialist. The PMU under the WBTIDCL will be responsible for ensuring that this ESIA/ESMP is adhered during the project implementation. In addition, a PMC unit will be in place under the ISBP component. The PMC under the ISBP will work/coordinate with the PMU/WBTIDCL for the day-to-day implementation aspects and associated safeguards compliance. The PMU shall be as shown in Figure 8-2.

Project Director

Environmental & Social Safety Specialist Development Specialist

Procurement PMC/ISBP Specialist Consultant

Figure 8-2: PMU's Institutional Set Up This should be detailed to meet all institutional aspects of the WBIWTLSDP. The team will work/coordinate with the technical and procurement officers of the PMU as well as the contractors and consultants for the day-to-day implementation aspects and associated safeguards compliance. They will monitor the portfolio of subprojects financed under the projects on safeguards. They will ensure compliance to both the national and state policy requirements, as well as the World Bank requirements. They will prepare a quarterly progress report wherein they will report project progress as well as safeguards implementation/compliance. The specialists will also arrange to conduct training and capacity-building initiatives to build awareness, knowledge and skills of PMU, consultants and contractors on an on-going basis. Here again, the specialists will engage external environmental and social consultants on a need basis to support the capacity building efforts.

8.4.4 Project Management Consultants In addition to the PMU, a PMC consultant will be in place under the ISBP component. The PMC/ISBP consultant will work/coordinate with the PMU/WBTIDCL for the day-to-day implementation aspects and associated safeguards compliance. The PMU/PMC will oversee the contractor’s activities. The PMC consultant will have in place an environmental and social specialist to oversee the day-to-day implementation of the ESMP measures in different

Environmental and Social Management Plan Page 112 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments subprojects. Lapses in implementation will be brought to the notice of the PMU, which is to take necessary corrective and preventive action in consultation with the respective contractor.

8.4.5 Audits and Inspections In addition, the department shall be responsible for implementing Compliance Assurance activities, namely environmental and social audits. Third party audits and reviews of environmental and social procedures shall be conducted annually. During these audits any change to the environment or social conditions wholly or partially is identified, evaluated and equally corrective actions are taken to better the environmental/social performance. A vital part of EHS practice is to learn from experience, using it as basis to improve the system. To this effect, periodic inspections and record keeping provides a measure of how effective programs are and facilitates identification of areas where improvement will be necessary. Environmental inspections consist of examining all activities and documenting those actions that are carried out as various compliance requirements, specifications relating to environmental protection, and mitigation plans approved.

8.4.6 Contractors The contractors will be responsible for ensuring the effective implementation of the ESMP requirements at the subproject level. These will be a part of the contract documents to which they will have to adhere. As required, the contractor will assign adequate/qualified staff in each subproject to ensure that ESHS requirements are met on a day-to-day basis. The contractor shall have the qualified staff either in-house (on the contractor’s pay-roles) or engage an external agency/consultant for this role. The assigned staff will work/coordinate with the PMU/WBTIDCL specialists on day-to-day/ monthly basis as required and confirm compliance to the safeguard requirements.

8.4.7 Grievance Redress Mechanism Grievance Redressal Mechanism is an integral part of the institutional arrangement in relation to social safeguard issues. At present, there is no established grievance redressal mechanism in PMU. Grievances related to employees and others are dealt on a case to case basis depending upon the nature of grievances. Social safeguards related grievances are expected from affected persons and other interested groups during the project implementation and therefore, it is important to set up a GRM at PMU level for resolution of such grievances. Anticipated grievances could be:

• Environmental (e.g. air, noise and water pollution) and social (e.g. labour and community safety) issues arising from the project activities • Non-payment of Resettlement and Rehabilitation assistance • Name of affected persons missing • Affected persons missed out/ not enumerated during the survey • Social category and vulnerability incorrect • Difference in land area acquired/purchased and measured at site • Type and use of land acquired/purchased not considered correctly • Wrong measurement of structure/building affected • Wrong valuation of structure/building • Damage to adjoining property • Construction activities at the site, quality of works, safety, etc.

Environmental and Social Management Plan Page 113 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

In view of the above, a Grievance Redressal Committee (GRC) will be constituted by the Project Authority with the aim to resolve as many grievances as possible related to resettlement and rehabilitation and land acquisition/purchase through consultations and negotiation. The GRC will comprise seven (8) members. The committee will comprise the following officials: i. Project Director, PMU, WBTIDCL – Chairperson

ii. Representative of MD, WBTC-Member

iii. Representative of Chairman, KoPT- Member

iv. Representative of UD & MA Department-Member

v. Social Development Expert (SDE), PMU, WBTIDCL – Convener-Member

vi. DG/Executive Engineer or his/her representative (from the concerned department - PWD/Irrigation, Municipal Engineering Directorate/KMC, District Engineer- Zilla Parishad) – Member

vii. Municipal Corporator/Councilor or Representative of Gram Panchayat of the concerned area – Member viii. Representative of Project Affected Population

Complaint boxes will be placed at every ferry locations which would be collected once a week by PMU. Grievances received through other modes (postal, email, or over the phone) will be compiled. A dedicated email and toll free phone number will be provided for receiving grievances/complaints through these methods. Toll free phone number, email, and address of PMU shall also be suitably displayed at entry and exit gates of ferry locations. Additionally, PMU will provide support to illiterate, physically challenged and other vulnerable PAPs to record their grievances. The various modes of registering grievances by the vulnerable are depicted in tabular format in Table -5.

Table - xx Tabular Format for Modes of Registering Grievances

Modes of Registering Grievances S. Category Toll Authorized No. of Person free Mobile Letter Email Physically Others Person Phone Poor and 1. Yes Yes Yes Yes Yes BPL* SC,ST or 2. Yes Yes Yes Yes Yes Yes WHH 3. Illiterate Yes Yes Yes Yes Senior 4. Yes Yes Yes Yes Yes Yes Citizen 5. Differently Able Yes Yes Yes Yes (Blind) 6. Differently Able (Deaf Yes Yes Yes Yes and/or Dumb)

Environmental and Social Management Plan Page 114 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Modes of Registering Grievances S. Category Toll Authorized No. of Person free Mobile Letter Email Physically Others Person Phone 7. Differently Able Yes Yes Yes Yes Yes Yes (Others) Note: BPL is the person enumerated by Government of India as living Below the Poverty Line and possessing a BPL Card given by the Government. At the PMU level the Social Development Expert will act as the Convener of the GRC as well as will be responsible for the day to day management of the GRM. He would also take the major responsibility to register complaints of the illiterate, physically challenged and other vulnerable PAPs. Grievances received by the PMU would be acknowledged by the PMU within seven days from the date of receipt of grievances. The GRC meeting will be convened once in a month or as per the requirements. Aggrieved persons will be duly intimated about the scheduled GRC meeting in sufficient advance time. On the day of GRC meeting, aggrieved persons will be given an opportunity to present his/her case before the committee in a free and fair manner. The decision of GRC will be intimated to the aggrieved person within 21 days from the date of the GRC meeting. In case the decision of the GRC is not acceptable to the aggrieved person in such case he/she may approach the court of law, if he/she so desires. Broad functions of GRC are as under:

• document all grievances received through different modes, • undertake site visit (if required), ask for further information from aggrieved persons, • co-ordinate and collect relevant information/data from concerned department/agencies (e.g. District Magistrate, DL& LRO, KPT, KMC, PWD, Zilla Parishad, etc.) area, • fix a time frame for next hearing in case additional information is required from aggrieved persons and other agencies, • inform EPs about the status of their case and the decision of GRC

The GRC will be constituted within a month before the implementation of activities during the first year of investment starts.

Besides, a field level grievance redressal mechanism will be established to resolve grievances/complaints received mainly during the implementation of project activities. It is expected that majority of grievances will be related to the following:

• indirect impact of project activities on adjoining structure/building, • project execution area not suitably barricaded, inadequate safety arrangements and signage in the project area, • closure to access/street roads, • loss of business, • non-availability of project information board, • un-certainty regarding timeline for resuming the ferry operation, etc.

Majority of the site-specific grievances/complaints can be resolved by the site engineer through the contractor as per the provisions of the contract. In case the damage to the structure/building is caused due to the negligence of the contractor, then the contractor will be responsible for reinstating/ repairing the damaged structure/building otherwise, it will be resolved as per the provisions of the RPF.

Environmental and Social Management Plan Page 115 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

A field-level GRC comprising SDE/JE (designated as Site Engineer), Social Development Expert, PMU and representative of Contractor shall be constituted for redressal of grievances/complaints at the site itself. One employee of the Jetty will be assigned to register the grievances and he/she will be responsible for the daily work of the GRC at the field level. This person at field level will provide support to illiterate, physically challenged and other vulnerable PAPs to record their grievances. The Committee will meet twice a week at the project site office at a fixed time so that aggrieved persons from surrounding areas can approach and lodge their complaints. A compliant box shall be placed at the project site for the collection of complaints/grievances. Wide publicity of GRM (at field level and PMU level) shall be made in the surrounding areas by adopting suitable publicity methods. Grievances/complaints not resolved at the site shall be escalated to the PMU level for redressal. A draft format for monitoring of grievances (received, type of grievances, grievances redressed, time required for resolving the grievances, etc.) has been provided as Appendix 9.

World Bank GRS: Communities and individuals who believe that they are adversely affected by a World Bank (WB) supported project may submit complaints to existing project-level grievance redress mechanisms or the WB’s Grievance Redress Service (GRS). The GRS ensures that complaints received are promptly reviewed in order to address project-related concerns. Project affected communities and individuals may submit their complaint to the WB’s independent Inspection Panel which determines whether harm occurred, or could occur, as a result of WB non-compliance with its policies and procedures. Complaints may be submitted at any time after concerns have been brought directly to the World Bank's attention, and Bank Management has been given an opportunity to respond. For information on how to submit complaints to the World Bank’s corporate Grievance Redress Service (GRS), please visit

• http://www.worldbank.org/en/projects-operations/products-and-services/grievance- redress-service. • For information on how to submit complaints to the World Bank Inspection Panel, please visit www.inspectionpanel.org.

8.5 Capacity Building Requirements

To ensure successful ESMP implementation, series of orientation, capacity building and training activities will be undertaken by PMU with contractors, consultants and other stakeholders who are directly implementing or indirectly involved with the project. Table 8-4 provides different types of training and capacity-building that will be carried out. Table 8-3: Training Type, Target Groups, Purpose and Frequency Training Required and Target S. No. Purpose Frequency Group Environmental and social general To inform senior management about ½ day workshop 1. awareness and appreciation importance and know how to recognize every 6 months workshop for senior management impacts that various activities may have To ensure that all stakeholders are informed ESMP implementation workshop for about requirements of ESMP and know how ½ day workshop 2. subproject contractors and to minimize environmental & social impacts every 6 months subproject consultants that various activities may have during implementation To ensure that all stakeholders are informed Subproject specific environmental Immediately after about the particular environmental and 3. and social management training for the award of the social impacts of their sub-projects and how subproject beneficiaries, contract and prior these should be mitigated.

Environmental and Social Management Plan Page 116 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Training Required and Target S. No. Purpose Frequency Group contractors and consultants based to initiating on the ESIA & ESMP construction Training programs will be practical and will include work with realistic case studies based on type of subprojects supported under the project. Training will cover following issues: a. (GOI) National and World Bank requirements for environmental/social assessment b. Screening and scoping procedures c. Main provisions of ESMPs for proposed subprojects, including mitigation and monitoring requirements Such training will enable these target groups to recognize and assess the potential negative environmental and social impacts and set of measures to mitigate them.

8.6 ESMP Budget The ESMP budget will have provisions for the EMP as presented in Table 8-5. The overall estimated budget for proposed capacity building activities, training, logistic support expenses for implementation of the project activities under the First Year of investments is presented in Table 8-6. This will include the budget towards the Gangetic Dolphin conservation efforts. In addition, the EMP provides an estimate for monitoring during the operational period considered for a four years. This is co-related to the remaining period of the five year investments period. The cost of hiring consultants for any aspects of the work is not reflected in this budget and is to be determined as per the need. Table 8-4: Estimated EMP Budget S. Unit Cost Total Cost INR in Component Description Unit Quantity No. (INR) Crores Construction/Manufacturing Stage (One Year) 1 Air Quality Nos. 80* 6000 0.048 2 Noise Nos. 80 1500 0.012 Environmental Monitoring 3 Water Quality Nos. 80 6000 0.048 4 Soil Nos. 80 6000 0.048 Operation Stage (Four Years) 5 Air Quality Nos. 160* 6000 0.096 6 Noise Nos. 160 1500 0.024 Environmental Monitoring 7 Water Quality Nos. 160 6000 0.096 8 Soil Nos. 160 6000 0.096 Sub Total 0.468 Contingency (Cost Escalations/Inflation, etc.) @ 10% 0.047 Grand Total of Anticipated Budget for EMP 0.515 Amount in US$ (rounded) 75,000 * Assumed monitoring to be conducted at 20 different locations Table 8-5: Estimated Budget Amount Amount Amount Amount S. (INR (INR Description (US$) (US$) No. Million) Million) First Year 2nd to 5th Years 1 Monitoring and Reporting 40,000 2.80 50,000 3.5 2 Training & Capacity Building 60,000 4.20 - -

Environmental and Social Management Plan Page 117 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Logistics Support (includes PMU, - - 3 125,000 8.75 PMC, Audit/Inspection costs) 4 Dolphin Conservation Efforts ~7,500 0.5 ~30,000 2.0 Total 232,500 16.25 80,000 5.5 US$ 312,500 Total Estimate for Five Years Investment Period INR Million 21.75 Further, this does not include the cost of environment (including health and safety) and social costs to be met by the contractor as these are necessary to meet the general requirements of the contract.

Environmental and Social Management Plan Page 118 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

9 Conclusions The proposed development activities seek to address urgent enhancement needs of the existing jetty infrastructure requirements. The activities under First Year investments will be limited to building/manufacturing of 22 new Vessels, addition of new Gangways and Pontoons at 30 selected jetty locations, installation of Turnstile Gates at 40 jetty locations and minor Waterside Construction Works at the 30 selected jetty locations. The activities under First Year investments will not involve Land Acquisition. Also, the activities are not envisaged to pose environmental and social impacts. However, as any development project, there will likely be some minimal impacts which have been identified in this report. These impacts are short term/localized and reversible impacts. Mitigation measures to avoid/ minimize the likely impacts will be implemented. The implementation arrangements needed to ensure implementation and effectiveness of the mitigation measures will be carried out through the PMU. Details of the arrangements have been presented in this report. Proposed development activities will help enhance the existing jetty infrastructure and will have overall positive impacts to the community as well as environment and without adversely affecting the environmental and social conditions/quality in the project area.

Conclusions Page 119 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

LIST OF APPENDIXES

Appendix 1: Environmental and Social Screening Forms ...... 121 Appendix 2: List of Projects or Activities Requiring Prior Environmental Clearance ...... 146 Appendix 3: Chance Find Procedure ...... 156 Appendix 4: CPCB’s National Ambient Air Quality Standards, GoI ...... 157 Appendix 5: Noise Quality Standards, GoI ...... 159 Appendix 6: Water Quality Standards, GoI...... 160 Appendix 7: Soil Quality Standards, GoI ...... 166 Appendix 8: Stakeholder Consultations ...... 167 Appendix 9: Draft Format for Monitoring of Grievances ...... 185

List of Appendixes Page 120 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 1: Environmental and Social Screening Forms

1. Jetty Location: Rashmoni Ghat, North 24 Parganas District (Kolkata/Howrah side) Responsible Organization: Operated by Titagarh Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located away from core urban areas (more of a semi-rural environment). Currently this ghat is not operational (closed since April 2018). Technical Features Jetty Timings - No. of Pontoons - Length of Gangway - Length of Link - Estimated Passengers/day - Presence of Concrete - Structures Environmental Features Air quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing air pollution issues Water quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing water pollution issues Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing noise pollution issues Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages None observed at Jetty, if any Presence of Natural Vegetation/ trees None specifically at jetty location; however the overall area has natural vegetation Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if No any Fishing Activities, if any No Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Currently jetty is not operational Drinking Water Facility Specific community issues, if any Locals are eagerly awaiting resumption of jetty services

Appendix 1: Environmental and Social Screening Forms Page 121 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

2. Jetty Location: Halisahar Ghat, North 24 Parganas District (Kolkata/Howrah side) Responsible Organization: Operated by Halisahar Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located away from core urban areas (more of a semi-rural environment) Technical Features Jetty Timings 6:00 AM to 9:30 PM No. of Pontoons No pontoons at the location; vessels berth along the gangway for passengers to enter/exit Length of Gangway Length of Link Estimated Passengers/day ~700 Presence of Concrete Link platform, jetty entrance area on landside Structures Environmental Features Air quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing air pollution issues Water quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing water pollution issues Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing noise pollution issues Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Some landscaping at jetty entrance area Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if No any Fishing Activities, if any No Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Toilet facilities need to be significantly improved Drinking Water Facility Drinking water facility needed at the jetty location Specific community issues, if any Lack of pontoon is a safety concern; need better vessels and a pontoon

Appendix 1: Environmental and Social Screening Forms Page 122 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

3. Jetty Location: Naihati Ghat, North 24 Parganas District (Kolkata/Howrah side) Responsible Organization: Operated by Naihati Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in a semi-urban area Technical Features Jetty Timings 5:00 AM to 11:30 PM No. of Pontoons 1 Length of Gangway 30 m Length of Link ~40 m Estimated Passengers/day ~14,000 Presence of Concrete Link platform is a concrete structure; needs immediate repairs Structures Environmental Features Air quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing air pollution issues; also no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing water pollution issues; also no specific water pollution issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) Although the jetty is located in a semi-urban area, no much indications of prevailing noise pollution issues; also no specific noise pollution issues at the jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Some vegetation seen at the river bank Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if No any Fishing Activities, if any Small fishing boats seen at the jetty area; vendors seen on the gangway/link platform Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Toilet facilities need to be significantly improved Drinking Water Facility Drinking water facility needed at the jetty location Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 123 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

4. Jetty Location: Debitala Ghat, North 24 Parganas District (Kolkata/Howrah side) Responsible Organization: Operated by Debitala Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located away from core urban areas (more of a semi-rural environment). Currently the jetty services is not operational; the operations were shut down following the Telinipara Ghat (about 6 kms away) mishap where the wooden gangway had collapsed leading to fatalities. Technical Features Jetty Timings - No. of Pontoons - Length of Gangway - Length of Link - Estimated Passengers/day - Presence of Concrete - Structures Environmental Features Air quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing air pollution issues Water quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing water pollution issues Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing noise pollution issues Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil None observed Spillages/Leakages at Jetty, if any Presence of Natural Vegetation/ trees Natural vegetation seen at the river bank; also the overall surrounding areas have natural vegetation Increased soil erosion and/or None observed sedimentation? Social Features: Temples/Mosques/Places of Worship, if No any Fishing Activities, if any No Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Currently jetty is not operational Drinking Water Facility Specific community issues, if any Locals face hardship due to closure of the jetty; they prefer commuting via the water mode to avoid heavy congestions on the roads. Currently they have to travel 2-3 kms to get to another jetty location and are eagerly awaiting resumption of jetty services

Appendix 1: Environmental and Social Screening Forms Page 124 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

5. Jetty Location: Monirampur Ghat, North 24 Parganas District (Kolkata/Howrah side) Responsible Organization: Operated by North Barrackpore Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in a semi-urban area; has parking facility outside the jetty area (mainly for bi- cycles and 2-wheelers) Technical Features Jetty Timings 6:00 AM to 11:00 PM No. of Pontoons 1 Length of Gangway 30 m Length of Link ~25 m Estimated Passengers/day ~15,000 Presence of Concrete Link platform is a concrete structure Structures Environmental Features Air quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing air pollution issues; also no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing water pollution issues; also no specific water pollution issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) Although the jetty is located in a semi-urban area, no much indications of prevailing noise pollution issues; also no specific noise pollution issues at the jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Some vegetation seen at the river bank Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if A small temple along the approach road to the jetty; none at the any jetty area Fishing Activities, if any Small fishing boats seen operating in the jetty area Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Need improved facilities Drinking Water Facility Need facilities for drinking water Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 125 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

6. Jetty Location: Barackpore/Dhobhighat Jetty, North 24 Parganas District (Kolkata/Howrah side) Responsible Organization: Operated by Barrackpore Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in a semi-urban area; the location is in an army cantonment area. Small boats (BhutBhuti) operating at the location. Technical Features Jetty Timings 6:00 AM to 10:30 PM No. of Pontoons None Length of Gangway None Length of Link ~ 50 m Estimated Passengers/day ~5,000 Presence of Concrete Structures None other than the jetty entrance areas Environmental Features Air quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing air pollution issues; also no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing water pollution issues; also no specific water pollution issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) Although the jetty is located in a semi-urban area, no much indications of prevailing noise pollution issues; also no specific noise pollution issues at the jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil None observed Spillages/Leakages at Jetty, if any Presence of Natural Vegetation/ trees Plantation/vegetation seen at river bank. Big banyan tree at entrance to ghat; this is of religious significance (small temple also located there) Increased soil erosion and/or None observed sedimentation? Social Features: Temples/Mosques/Places of Worship, if any Small temple located at entrance area of the jetty location Fishing Activities, if any Small fishing boats seen at the jetty area Record of Past Community Accidents, if any No Toilet Facilities (Operational?) Need improved facilities Drinking Water Facility Need facilities for drinking water Specific community issues, if any Safety concerns due to lack of pontoons, proper gangway and bigger vessels; during high tide portion of the wooden link platform submerges. Need overall enhancement of the facilities.

Appendix 1: Environmental and Social Screening Forms Page 126 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

7. Jetty Location: Titagarh Jetty, North 24 Parganas District (Kolkata/Howrah side) Responsible Organization: Operated by Titagarh Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in a semi-urban area; location has several industrial activities (jute, paper mills, glassmaking, textile, etc.). Small boats (BhutBhuti) operating at the location. Technical Features Jetty Timings 5:00 AM to 10:00 PM No. of Pontoons None Length of Gangway No gangway Length of Link ~30 m Estimated Passengers/day ~3,000 Presence of Concrete The link platform is a concrete structure Structures Environmental Features Air quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing air pollution issues; also no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Due to open sewage discharge into the water body, prevailing water quality at the area appears to be polluted Sewage discharge, if any Open sewage discharge into the river is seen at the location Noise level (any anticipated issues) Although the jetty is located in a semi-urban area, no much indications of prevailing noise pollution issues; also no specific noise pollution issues at the jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages None observed at Jetty, if any Presence of Natural Vegetation/ trees Plantation/vegetation seen at the river banks Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if No any Fishing Activities, if any Not seen at the jetty location Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Need improved facilities Drinking Water Facility No drinking water facility at the location Specific community issues, if any Safety concerns due to lack of pontoons, proper gangway and bigger vessels; during high tide portion of the link platform submerges. Need overall enhancement of the facilities.

Appendix 1: Environmental and Social Screening Forms Page 127 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

8. Jetty Location: Khardah Jetty, North 24 Parganas District (Kolkata/Howrah side) Responsible Organization: Operated by Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located away from core urban areas (more of a semi-rural environment). Several small shops, auto-rickshaw stand outside the jetty entrance area. This screening was conducted on October 21, 2019. Subsequently due to damage to the gangway as a result of heavy rains/cyclone the jetty services have been suspended since end of October 2019. Technical Features Jetty Timings 5:30 AM – 10:45 PM (during operational period) No. of Pontoons 1 Length of Gangway 30 m Length of Link ~ 50 m Estimated Passengers/day ~ 2,000 Presence of Concrete The link platform is a concrete structure Structures Environmental Features Air quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing air pollution issues Water quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing water pollution issues Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing noise pollution issues Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Natural vegetation seen at the river bank; also the overall surrounding areas have natural vegetation Increased soil erosion and/or sedimentation? As per locals, this jetty location is prone to heavy sedimentation. Social Features: Temples/Mosques/Places of Worship, if any No Fishing Activities, if any Not seen at jetty location Record of Past Community Accidents, if any No Toilet Facilities (Operational?) Need improved facilities Drinking Water Facility Need facilities for drinking water Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 128 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

9. Jetty Location: Panihati Ghat, North 24 Parganas District (Kolkata/Howrah side) Responsible Organization: Operated by Konnagar Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in semi-urban area Technical Features Jetty Timings 5:00 AM to 10:45 PM No. of Pontoons 1 Length of Gangway 30 m Length of Link ~20 m Estimated Passengers/day ~4,000 Presence of Concrete The link platform is a concrete structure Structures Environmental Features Air quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing air pollution issues; also no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing water pollution issues; also no specific water pollution issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) Although the jetty is located in a semi-urban area, no much indications of prevailing noise pollution issues; also no specific noise pollution issues at the jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Landscaping done at jetty entrance area Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if No any Fishing Activities, if any Small fishing boats seen at the jetty location Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Need improved facilities Drinking Water Facility Need facilities for drinking water Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 129 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

10. Jetty Location: Sovabazar Ghat, Kolkata District (Kolkata/Howrah side) Responsible Organization: Operated by Hooghly Nadi Jalpath Paribahan Samabay Samity Ltd. (HNJPSS) Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in semi-urban area; densely populated area Technical Features Jetty Timings 8:00 AM to 8:00 PM No. of Pontoons 1 Length of Gangway 30 m Length of Link ~ 10 m Estimated Passengers/day ~6,000 Presence of Concrete The link platform is a concrete structure Structures Environmental Features Air quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing air pollution issues; also no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing water pollution issues; also no specific water pollution issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) Although the jetty is located in a semi-urban area, no much indications of prevailing noise pollution issues; also no specific noise pollution issues at the jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Vegetation seen at the river banks Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if No any Fishing Activities, if any Not seen at the jetty area Record of Past Community Accidents, if No any Toilet Facilities (Operational?) No toilet facilities available; need toilet facilities at the jetty location Drinking Water Facility Need facilities for drinking water Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 130 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

11. Jetty Location: Ahiritola Ghat, Kolkata District (Kolkata/Howrah side) Responsible Organization: Operated by Indo Swiss Trading Company Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in urban area; densely populated Technical Features Jetty Timings 8:00 AM to 8:00 PM: Howrah to Bagbazar via Ahiritola 5:30 AM to 9:30 PM: Ahiritola to Bandha Ghat No. of Pontoons 2 (for different routes) Length of Gangway 30 m Length of Link ~ 15 m Estimated Passengers/day ~15,000 Presence of Concrete The link platform is a concrete structure Structures Environmental Features Air quality (any pollution issues) Jetty located in congested urban area having prevailing air pollution issues mainly due to large number of vehicular movements; no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Jetty being located in a core urban area has its associated impacts on the water quality (mainly due to wastewater/ sewage discharges into the water body); no specific water quality issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located in congested urban area having prevailing high noise levels mainly due to large number of vehicular movements; no specific noise pollution issues at jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Vegetation is seen at the river banks Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if None at the jetty location; adjacent to the ghat area there is another any ghat built for undertaking religious activities Fishing Activities, if any Not seen at the jetty location Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Need improved toilet facilities Drinking Water Facility Need facilities for drinking water Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 131 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

12. Jetty Location: Armenian Ghat, Kolkata District (Kolkata/Howrah side) Responsible Organization: Operated by Hooghly Nadi Jalpath Paribahan Samabay Samity Ltd. (HNJPSS) Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in urban area; densely populated. Is a busy commercial area with lot of traders (wholesale markets of stationeries, cosmetic, electronics, medicine, plastic toys, etc.). Technical Features Jetty Timings 8:00 AM to 8:00 PM No. of Pontoons 1 Length of Gangway 30 m Length of Link ~10 m Estimated Passengers/day ~4,000 Presence of Concrete The link platform/jetty entrance area is a concrete structure Structures Environmental Features Air quality (any pollution issues) Jetty located in congested urban area having prevailing air pollution issues mainly due to large number of vehicular movements; no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Jetty being located in a core urban area has its associated impacts on the water quality (mainly due to wastewater/sewage discharges into the water body). The jetty is a fueling station for vessels as such oil/fuel spills is likely water pollution issue at the jetty location Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located in congested urban area having prevailing high noise levels mainly due to large number of vehicular movements and commercial activities; no specific noise pollution issues at jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Some plantation seen at the river bank Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if any No Fishing Activities, if any Not seen at the jetty area Record of Past Community Accidents, if any No Toilet Facilities (Operational?) Need improved toilet facilities Drinking Water Facility Need facilities for drinking water Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 132 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

13. Jetty Location: Chandpal Ghat 1, Kolkata District (Kolkata/Howrah side) Responsible Organization: Operated by Hooghly Nadi Jalpath Paribahan Samabay Samity Ltd. (HNJPSS) Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in urban area alongside busy streets; densely populated area Technical Features Jetty Timings 6:50 AM to 8:45 PM No. of Pontoons 1 Length of Gangway 30 m Length of Link Directly connected to jetty entrance area; no separate link platform Estimated Passengers/day ~5,000 Presence of Concrete Jetty entrance area Structures Environmental Features Air quality (any pollution issues) Jetty located in congested urban area having prevailing air pollution issues mainly due to large number of vehicular movements; no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Jetty being located in a core urban area has its associated impacts on the water quality (mainly due to wastewater/ sewage discharges into the water body); no specific water quality issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located in congested urban area having prevailing high noise levels mainly due to large number of vehicular movements also railway line just outside the ghat area; no specific noise pollution issues at jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Vegetation seen at the river bank Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if No any Fishing Activities, if any Not seen at jetty location Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Need improved toilet facilities Drinking Water Facility Need facilities for drinking water Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 133 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

14. Jetty Location: Chandpal Ghat 2, Kolkata District (Kolkata/Howrah side) Responsible Organization: Operated by Hooghly Nadi Jalpath Paribahan Samabay Samity Ltd. (HNJPSS) Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in urban area alongside busy streets; densely populated area Technical Features Jetty Timings 8:00 AM to 8:00 PM – to Howrah 7:30 AM to 8:15 PM – to Shibpur No. of Pontoons 1 Length of Gangway 30 m Length of Link Directly connected to jetty entrance area; no separate link platform Estimated Passengers/day ~15,000 Presence of Concrete Jetty entrance area Structures Environmental Features Air quality (any pollution issues) Jetty located in congested urban area having prevailing air pollution issues mainly due to large number of vehicular movements; no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Jetty being located in a core urban area has its associated impacts on the water quality (mainly due to wastewater/ sewage discharges into the water body); no specific water quality issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located in congested urban area having prevailing high noise levels mainly due to large number of vehicular movements also railway line just outside the ghat area; no specific noise pollution issues at jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Vegetation seen at the river bank Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if any No Fishing Activities, if any Not seen at jetty location Record of Past Community Accidents, if any No Toilet Facilities (Operational?) Need improved toilet facilities Drinking Water Facility Need facilities for drinking water Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 134 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

15. Jetty Location: Outram Jetty, Kolkata District (Kolkata/Howrah side) Responsible Organization: Jetty used/operated by Kolkata River Police and Customs Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in urban area alongside busy streets Technical Features Jetty Timings 24 hours No. of Pontoons 3 Length of Gangway 30 m Length of Link Directly connected to jetty entrance area; no separate link platform Estimated Passengers/day Used only by Police and Customs personnel; not available for general public Presence of Concrete Jetty entrance area Structures Environmental Features Air quality (any pollution issues) Jetty located in congested urban area having prevailing air pollution issues mainly due to large number of vehicular movements; no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Jetty being located in a core urban area has its associated impacts on the water quality (mainly due to wastewater/ sewage discharges into the water body); no specific water quality issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located in congested urban area having prevailing high noise levels mainly due to large number of vehicular movements; no specific noise pollution issues at jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Plantation/vegetation seen along the gangway, at river bank Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if No any Fishing Activities, if any No Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Jetty used by Police and Customs; they have their offices/stations Drinking Water Facility at the jetty with adequate toilet and drinking water facilities Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 135 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

16. Jetty Location: Noorpur Ghat, South 24 Parganas District (Kolkata/Howrah side) Responsible Organization: Operated by United Transport Company Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located away from core urban areas (more of a semi-rural environment). Jetty is located at the confluence of Roopnarayani and Hooghly Rivers and is in close proximity to the Bay of Bengal. Gangetic River Dolphins reported to be rarely sighted at this area. Technical Features Jetty Timings 6:00 AM to 7:40 PM No. of Pontoons None Length of Gangway No gangway Length of Link Wooden link platform structure ~ 30 m Estimated Passengers/day ~1,000 Presence of Concrete None other than main jetty entrance area Structures Environmental Features Air quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing air pollution issues Water quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing water pollution issues Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing noise pollution issues Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Vegetation seen at the river bank Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if any No Fishing Activities, if any Not seen at jetty location; however this jetty being close to the confluence of Rivers and in close proximity to the Bay of Bengal fishing activities are prevalent in the overall area. Record of Past Community Accidents, if any No Toilet Facilities (Operational?) Need improved toilet facilities Drinking Water Facility Need facilities for drinking water Specific community issues, if any Safety concerns due to lack of pontoons, proper gangway and bigger vessels; during high tide portion of the link platform submerges. Need overall enhancement of the facilities.

Appendix 1: Environmental and Social Screening Forms Page 136 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

17. Jetty Location: Bansberia Ghat, Hooghly District (Kolkata/Howrah side) Responsible Organization: Operated by Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located away from core urban areas (more of a semi-rural environment) Technical Features Jetty Timings 6:00 AM to 10:00 PM No. of Pontoons None Length of Gangway No gangway; only wooden link platform Length of Link ~ 30 m Estimated Passengers/day ~700 Presence of Concrete No concrete structures other than the main entrance area to the jetty Structures Environmental Features Air quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing air pollution issues Water quality (any pollution issues) Due to open wastewater discharge into the water body, prevailing water quality at the area appears to be polluted Sewage discharge, if any Wastewater discharge into the river is seen at the location Noise level (any anticipated issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing noise pollution issues Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Vegetation seen at the river bank Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if No any Fishing Activities, if any Not seen at jetty location Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Need improved toilet facilities Drinking Water Facility Need improved facilities for drinking water Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 137 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

18. Jetty Location: Chinsurah Ghat, Hooghly District (Kolkata/Howrah side) Responsible Organization: Operated by Hooghly-Chinsura Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in a semi-urban area Technical Features Jetty Timings 5:00 AM to 11:30 PM No. of Pontoons 1 Length of Gangway 30 m Length of Link ~ 15 m Estimated Passengers/day ~15,000 Presence of Concrete Link platform is a concrete structure Structures Environmental Features Air quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing air pollution issues; also no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing water pollution issues; also no specific water pollution issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) Although the jetty is located in a semi-urban area, no much indications of prevailing noise pollution issues; also no specific noise pollution issues at the jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Slight vegetation seen at the river bank Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if No any Fishing Activities, if any Not seen at jetty location Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Need improved toilet facilities Drinking Water Facility Need improved facilities for drinking water Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 138 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

19. Jetty Location: Gourhati Ghat, Hooghly District (Kolkata/Howrah side) Responsible Organization: Operated by Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located away from core urban areas (more of a semi-rural environment). Currently the jetty services is not operational; the operations were shut down following the Telinipara Ghat (about 4 kms away) mishap where the wooden gangway had collapsed leading to fatalities. Technical Features Jetty Timings - No. of Pontoons - Length of Gangway - Length of Link - Estimated Passengers/day - Presence of Concrete Structures - Environmental Features Air quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing air pollution issues Water quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing water pollution issues Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing noise pollution issues Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil None observed Spillages/Leakages at Jetty, if any Presence of Natural Vegetation/ trees Natural vegetation seen at the river bank; also at the ghat location there are at least couple of trees of relegiouis significance (a Peepal and Champa tree20); the overall surrounding areas have natural vegetation Increased soil erosion and/or None observed sedimentation? Social Features: Temples/Mosques/Places of Worship, if any Small temple at ghat entrance Fishing Activities, if any Not seen at jetty location Record of Past Community Accidents, if any No Toilet Facilities (Operational?) Currently jetty is not operational Drinking Water Facility Specific community issues, if any Locals face hardship due to closure of the jetty. Currently they have to travel 2-3 kms to get to another jetty location and are eagerly awaiting resumption of jetty services

20 Scientific Names: Ficus religiosa and Plumeria alba, respectively

Appendix 1: Environmental and Social Screening Forms Page 139 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

20. Jetty Location: Sheoraphuli Ghat, Hooghly District (Kolkata/Howrah side) Responsible Organization: Operated by Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in a semi-urban area; very busy commercial/market area Technical Features Jetty Timings 6:00 AM to 11:00 PM No. of Pontoons 1 Length of Gangway 30 m Length of Link No link platform; gangway directly connected to entrance area Estimated Passengers/day ~10,000 Presence of Concrete Entrance area of the ghat Structures Environmental Features Air quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing air pollution issues; also no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Although the jetty is located in a semi-urban area, no much indications of prevailing water pollution issues; also no specific water pollution issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) The ghat is located in a crowded commercial/market area having prevailing high noise levels mainly due to large number of vehicular movements and commercial activities; no specific noise pollution issues at jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Vegetation present at the river bank Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if No any Fishing Activities, if any Not seen at the jetty area Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Need improved toilet facilities Drinking Water Facility Need improved facilities for drinking water Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 140 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

21. Jetty Location: Konnagar Ghat, Hooghly District (Kolkata/Howrah side) Responsible Organization: Operated by Konnagar Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in away from core urban areas (more of a semi-rural environment) Technical Features Jetty Timings 5:00 AM to 11:00 PM No. of Pontoons 1 Length of Gangway 30 Length of Link ~40 m Estimated Passengers/day ~4,000 Presence of Concrete Link platform is a concrete structure Structures Environmental Features Air quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing air pollution issues Water quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing water pollution issues Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing noise pollution issues Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages at Jetty, None observed if any Presence of Natural Vegetation/ trees Vegetation/plantation seen at river bank, jetty entrance area Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if No any Fishing Activities, if any Small fishing boats seen at jetty location Record of Past Community Accidents, if No any Toilet Facilities (Operational?) Need improved toilet facilities Drinking Water Facility Need improved facilities for drinking water Specific community issues, if any No

Appendix 1: Environmental and Social Screening Forms Page 141 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

22. Jetty Location: Howrah Jetty – 1, Howrah District (Kolkata/Howrah side) Responsible Organization: Operated by Hooghly Nadi Jalpath Paribahan Samabay Samity Ltd. (HNJPSS) Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in urban area; within walking distance of the very busy Technical Features Jetty Timings 5:15 AM to 10:30 PM No. of Pontoons 1 Length of Gangway 30 Length of Link ~ 20 m Estimated Passengers/day ~10,000 Presence of Concrete Structures Main jetty area Environmental Features Air quality (any pollution issues) Jetty located in congested urban area having prevailing air pollution issues mainly due to large number of vehicular movements; no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Jetty being located in a core urban area has its associated impacts on the water quality (mainly due to wastewater/sewage discharges into the water body); no specific air water quality issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located in congested urban area having prevailing high noise levels mainly due to large number of vehicular movements; no specific noise pollution issues at jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil None observed Spillages/Leakages at Jetty, if any Presence of Natural Vegetation/ trees Vegetation seen at the river bank Increased soil erosion and/or None observed sedimentation? Social Features: Temples/Mosques/Places of Worship, if any No Fishing Activities, if any Small fishing boats seen at the jetty location Record of Past Community Accidents, if any No Toilet Facilities (Operational?) Need improved toilet facilities Drinking Water Facility Need improved facilities for drinking water Specific community issues, if any No

23. Jetty Location: Howrah Jetty – 2, Howrah District (Kolkata/Howrah side) Responsible Organization: Operated by Hooghly Nadi Jalpath Paribahan Samabay Samity Ltd. (HNJPSS)

Appendix 1: Environmental and Social Screening Forms Page 142 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances: MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in urban area; within walking distance of the very busy Howrah Railway Station Technical Features Jetty Timings 6:00 AM to 10:00 PM No. of Pontoons 1 Length of Gangway 30 Length of Link ~ 20 m Estimated Passengers/day ~3,500 Presence of Concrete Structures Main jetty entrance area Environmental Features Air quality (any pollution issues) Jetty located in congested urban area having prevailing air pollution issues mainly due to large number of vehicular movements; no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Jetty being located in a core urban area has its associated impacts on the water quality (mainly due to wastewater/sewage discharges into the water body); no specific air water quality issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located in congested urban area having prevailing high noise levels mainly due to large number of vehicular movements; no specific noise pollution issues at jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil None observed Spillages/Leakages at Jetty, if any Presence of Natural Vegetation/ trees Vegetation seen at the river bank Increased soil erosion and/or None observed sedimentation? Social Features: Temples/Mosques/Places of Worship, if any No Fishing Activities, if any Small fishing boats seen at the jetty location Record of Past Community Accidents, if any No Toilet Facilities (Operational?) Need improved toilet facilities Drinking Water Facility Need improved facilities for drinking water Specific community issues, if any No

24. Jetty Location: Howrah Jetty – 3, Howrah District (Kolkata/Howrah side) Responsible Organization: Operated by WBTC Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances:

Appendix 1: Environmental and Social Screening Forms Page 143 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located in urban area; within walking distance of the very busy Howrah Railway Station Technical Features Jetty Timings 6:00 AM to 10:00 PM No. of Pontoons 2 Length of Gangway 30 Length of Link ~ 20 m Estimated Passengers/day ~6,000 Presence of Concrete Structures Main jetty entrance area on landside Environmental Features Air quality (any pollution issues) Jetty located in congested urban area having prevailing air pollution issues mainly due to large number of vehicular movements; no specific air pollution issues at the jetty location as such Water quality (any pollution issues) Jetty being located in a core urban area has its associated impacts on the water quality (mainly due to wastewater/sewage discharges into the water body); no specific air water quality issues at the jetty location as such Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located in congested urban area having prevailing high noise levels mainly due to large number of vehicular movements; no specific noise pollution issues at jetty location as such Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil Spillages/Leakages None observed at Jetty, if any Presence of Natural Vegetation/ trees Vegetation seen at the river bank Increased soil erosion and/or sedimentation? None observed Social Features: Temples/Mosques/Places of Worship, if any No Fishing Activities, if any Small fishing boats seen at the jetty location; squatters seen selling fish on pontoon Record of Past Community Accidents, if any No Toilet Facilities (Operational?) Need improved toilet facilities Drinking Water Facility Need improved facilities for drinking water Specific community issues, if any No

25. Jetty Location: Fuleswar Ghat, Howrah District (Kolkata/Howrah side) Responsible Organization: Operated by Fuleswar Municipality Type of Activity Proposed: Enhancing jetty facilities, provision of new gangway, pontoons Regulatory Clearances:

Appendix 1: Environmental and Social Screening Forms Page 144 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

MoEF&CC/SEIAA Environmental Clearance NA Forest and Wild Life Clearance NA Existing Site Features: Located away from core urban areas (more of a semi-rural environment); this is a proposed development location. Currently there are no jetty services at the location. Technical Features Jetty Timings - No. of Pontoons - Length of Gangway - Length of Link - Estimated Passengers/day - Presence of Concrete Structures - Environmental Features Air quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing air pollution issues Water quality (any pollution issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing water pollution issues Sewage discharge, if any Not noticed Noise level (any anticipated issues) Jetty located away from core urban areas (more of a semi-rural environment); no indications of prevailing noise pollution issues Solid Waste No disposal of solid waste seen at jetty location Land Contamination, Oil None observed Spillages/Leakages at Jetty, if any Presence of Natural Vegetation/ trees Vegetation seen at the river bank Increased soil erosion and/or None observed sedimentation? Social Features: Temples/Mosques/Places of Worship, if any No Fishing Activities, if any Small fishing boats seen at jetty location Record of Past Community Accidents, if any No Toilet Facilities (Operational?) To be developed Drinking Water Facility To be provided Specific community issues, if any Locals currently have to travel 2-3 kms to get to another jetty location and are eagerly awaiting jetty service at this location

Appendix 1: Environmental and Social Screening Forms Page 145 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 2: List of Projects or Activities Requiring Prior Environmental Clearance

SCHEDULE List of Projects or Activities Requiring Prior Environmental Clearance as per MoEF&CC Notification, S.O. 1533; Dated: August, 2015 Category with threshold limit Project or Activity Conditions if any A B (1) (2) (3) (4) (5) 1 Mining, extraction of natural resources and power generation (for a specified production capacity) General Condition shall apply except for project or activity of less than 5 ha of mining lease area: Provided that the above exception shall not apply for project or activity if ≥ 50 ha. of mining lease the sum total of the mining lease area of the said project or activity and that area in respect of non- of existing operating mines and mining projects which were accorded coal mine lease. (i)Mining of minerals ≤50 ha of mining lease environment clearance and are located within 500 meters from the ≥150 ha of mining lease area in respect of non- (ii)Slurry pipelines (coal, lignite periphery of such project or activity equals or exceeds 5 ha. area in respect of coal coal mine lease. and other ores) passing Note 1(a) mine lease through national parks / ≤150 ha of mining lease (i)Prior environmental clearance is required at the stage of renewal of mine sanctuaries / coral reefs, Asbestos mining area in respect of coal lease for which an application shall be made up to two years prior to the ecologically sensitive areas. irrespective of mining mine lease. date due for renewal. area Provided that no fresh environmental clearance shall be required for a All projects. mining project or activity at the time of renewal of mining lease, which has already obtained environmental clearance, under this Notification. (ii) Mineral prospecting is exempted.

Appendix 2: List of Projects or Activities Requiring Prior Environmental Clearance Page 146 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Category with threshold limit Project or Activity Conditions if any A B (1) (2) (3) (4) (5) Note: Offshore and onshore oil and 1(b) gas exploration, development & All projects Seismic surveys which are part of Exploration surveys are exempted production provided the concession areas have got previous clearance for physical survey

(i) < 50 MW ≥ 25 MW General Condition shall apply (i) ≥ 50 MW hydroelectric hydroelectric power (i)River Valley projects power generation; generation; Note: Irrigation projects not involving submergence or inter-state domain 1(c) shall be appraised by the SEIAA as Category ‘B’ Projects. (ii)Irrigation projects (ii) ≥ 10,000 ha. of (ii) < 10,000 ha. > 2000 culturable command area ha. of culturable Category ‘B’ river valley projects falling in more than one state shall be command area appraised at the central Government Level.

>50 MW < 500 MW (coal/lignite/ naptha & gas based); ≥ 500 MW General Condition shall apply. (coal/lignite/naptha & gas <50 MW ≥ 5MW (all other based); fuels except biomass and Note: municipal solid non- ≥ 50 MW (all other fuels (i)Thermal Power Plants up to 15 MW based on biomass or non-hazardous 1(d) Thermal Power Plants hazardous waste); except biomass). municipal solid waste using auxiliary fuel such as coal, lignite / petroleum <20 MW ≥15 MW (using products up to 15% are exempt. ≥ 20 MW (using municipal municipal solid non- (ii)Thermal Power plants using waste heat boilers without any auxiliary fuel solid non-hazardous hazardous waste, as are exempt. waste, as fuel). fuel). ≥15 MW plants based on biomass fuel.

Appendix 2: List of Projects or Activities Requiring Prior Environmental Clearance Page 147 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Category with threshold limit Project or Activity Conditions if any A B (1) (2) (3) (4) (5) Nuclear power projects and 1(e) All projects - - processing of nuclear fuel 2 Primary Processing General Condition shall apply ≥ 1 million ton/annum <1million ton/annum 2(a) Coal washeries throughput of coal throughput of coal (If located within mining area the proposal shall be appraised together with the mining proposal)

General Condition shall apply ≥ 0.5 million TPA < 0.5 million TPA 2(b) Mineral beneficiation throughput throughput (Mining proposal with Mineral beneficiation shall be appraised together for grant of clearance). 3 Materials Production a)Primary metallurgical Sponge iron industry manufacturing <200TPD General Condition shall apply. All projects Secondary metallurgical Note: processing industry b) Sponge iron (i)The recycling industrial units registered under the HSM Rules are manufacturing ≥ 200TPD i.)All toxic and heavy Metallurgical industries (ferrous exempt. (ii)In case of secondary metallurgical processing industrial units, 3(a) metal producing units & non-ferrous) c)Secondary those projects involving operation of furnaces only such as induction and <20,000 tonnes /annum metallurgical processing electric arc furnace, and cupola with capacity more than 30000 tonnes per industry ii.)All other non –toxic annum (TPA) would require environmental clearance. (iii)Plant / units other secondary metallurgical than power plants (given against entry no. 1(d) of the schedule), based on All toxic and heavy metal processing industries municipal solid waste (non-hazardous) are exempted. producing units ≥ 20,000 tonnes /annum >5000 tonnes/annum

Appendix 2: List of Projects or Activities Requiring Prior Environmental Clearance Page 148 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Category with threshold limit Project or Activity Conditions if any A B (1) (2) (3) (4) (5) <1.0 million ≥ 1.0 million tonnes/annum production 3(b) Cement plants tonnes/annum production General Condition shall apply capacity. All Stand-alone capacity grinding units 4 Materials Processing 4(a) Petroleum refining industry All projects - -

<2,50,000 & (i)Coke oven plants 4(b) ≥2,50,000 tonnes/annum ≥25,000 tonnes/annum General conditions shall apply (ii) Coaltar processing units All projects

(i)All projects irrespective of the size, if it is located ≥300 TPD production in a Notified Industrial General as well as specific conditions shall apply capacity if a unit located Area / Estate. 4(c) Chlor-alkali industry No new Mercury Cell based plants will be permitted and existing units outside the notified <300 tonnes per day converting to membrane cell technology are exempted from the industrial area/ estate (TPD) and located outside Notification. a Notified Industrial Area / Estate.

4(e) Soda ash Industry All projects - -

All new or expansion of Skin/hide processing including New projects outside the projects located within a 4(f) General as well as specific conditions shall apply tanning industry industrial area or notified industrial area/ expansion of existing estate

Appendix 2: List of Projects or Activities Requiring Prior Environmental Clearance Page 149 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Category with threshold limit Project or Activity Conditions if any A B (1) (2) (3) (4) (5) units outside the industrial area 5 Manufacturing/Fabrication All projects including all All Single Super Single Super Phosphate Phosphate without H2SO4 General condition shall apply. Granulation of single super phosphate 5(a) Chemical fertilizers with H2SO4 production production and powder is exempt. except granulation of granulation of chemical chemical fertilizers. fertilizers

Pesticides industry and All units producing 5(b) pesticide specific intermediates - - technical grade pesticides (excluding formulations)

Petro-chemical complexes (industries based on 5(c) processing of petroleum All projects - - fractions & natural gas and/or reforming to aromatics)

5(d) Manmade fibres manufacturing Rayon Others General Condition shall apply

Petrochemical products and General as well as specific conditions shall apply. petrochemical based Located outside the Located in a notified 5(e) processing such as production notified industrial area/ Note: industrial area/ estate of carbon black and electrode estate grade graphite (processes Manufacturing of products from polymer granules is exempt. other than cracking &

Appendix 2: List of Projects or Activities Requiring Prior Environmental Clearance Page 150 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Category with threshold limit Project or Activity Conditions if any A B (1) (2) (3) (4) (5) reformation and not covered under the complexes).

Synthetic organic chemicals industry (dyes & dye intermediates; bulk drugs and Located outside the (i)Located in a notified General as well as specific conditions shall apply. intermediates excluding drug notified industrial area/ industrial area/ estate. 5(f) Small units: with water consumption <25 cu mt per day, fuel consumption formulations; synthetic rubbers; estate except small units (ii)Small units as defined <25 TPD and not covered in the category of MAH units as per the basic organic chemicals, other as defined in column (5) in column (5) Management, Storage and Import of Hazardous Chemical Rules, 1989. synthetic organic chemicals and chemical intermediates)

(i)All Molasses based Non-molasses based distilleries 5(g) Distilleries distilleries – General Condition shall apply (ii) Non-molasses based <60 KLD distilleries 60 KLD

5(h) Integrated paint industry - All projects General Condition shall apply

Pulp manufacturing from General Condition shall apply. Pulp manufacturing and waste paper and paper Pulp & Paper Note: 5(i) Pulp & paper industry manufacturing from waste manufacturing industry paper pulp and other Paper manufacturing from waste paper pulp and ready pulp without except from waste paper ready pulp deinking, bleaching and colouring is exempt.

≥ 5000 tcd cane crushing 5(j) Sugar Industry - General Condition shall apply capacity 6 Service Sectors

Appendix 2: List of Projects or Activities Requiring Prior Environmental Clearance Page 151 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Category with threshold limit Project or Activity Conditions if any A B (1) (2) (3) (4) (5) Oil & gas transportation pipe line (crude and refinery/ petrochemical products), 6(a) passing through national parks All projects - - /sanctuaries/coral reefs /ecologically sensitive areas including LNG Terminal

Isolated storage & handling of hazardous chemicals (As per threshold planning quantity 6(b) - All projects General Condition shall apply indicated in column 3 of schedule 2 & 3 of MSIHC Rules 1989 amended 2000) 7 Physical Infrastructure including Environmental Services All projects including Air strips which do not involve bunkering / refueling facility and or Air Traffic 7(a) Air ports airstrips, which are for - Control, are exempted. commercial use

All ship breaking yards 7(b) All projects - - including ship breaking units

If at least one industry in General as well as specific conditions shall apply Industrial estates/ parks/ Industrial estates housing the proposed industrial complexes/ areas, export at least one Category B Note: 7(c) estate falls under the processing Zones (EPZs), industry and area <500 Category A, entire 1. Industrial Estate of area below 500 ha. and not housing any industry of Special Economic Zones ha. industrial area shall be category A or B does not require clearance.

Appendix 2: List of Projects or Activities Requiring Prior Environmental Clearance Page 152 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Category with threshold limit Project or Activity Conditions if any A B (1) (2) (3) (4) (5) (SEZs), Biotech Parks, Leather treated as Category A, Industrial estates of area> 2. If the area is less than 500 ha. But contains building and construction Complexes. irrespective of the area. 500 ha. and not housing projects > 20000 sq. mtr. and or development area more than 50 ha it will any industry belonging to be treated as activity listed at serial no. 8(a) or 8(b) in the Schedule, as the Industrial estates with Category A or B. case may be. area greater than 500 ha. and housing at least one Category B industry.

All integrated facilities Common hazardous waste having incineration & All facilities having land fill 7(d) treatment, storage and disposal General Condition shall apply landfill or incineration only facilities (TSDFs) alone

Bio-Medical Waste Treatment 7(da) - All projects - Facilities

< 5 million TPA of cargo General Condition shall apply Note: 1.Capital dredging inside and outside ≥ 5 million TPA of cargo handling capacity and/or the ports or harbors and channels are included; 2.Maintenance dredging Ports, harbors, break waters, handling capacity 7(e) ports/ harbours 10,000 is exempt provided it formed part of the original proposal for which dredging (excluding fishing TPA of fish handling Environment Management Plan (EMP) was prepared and environmental harbours) capacity clearance obtained.

i) New National High i) All New State Highway ways; and Projects; General Condition shall apply ii) Expansion of National ii) State Highway 7(f) Highways Note: High ways greater than expansion projects in hilly 100 km involving terrain (above 1000 m Highways include expressways. additional right of way or AMSL) and or ecologically land acquisition greater sensitive areas.

Appendix 2: List of Projects or Activities Requiring Prior Environmental Clearance Page 153 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Category with threshold limit Project or Activity Conditions if any A B (1) (2) (3) (4) (5) than 40m on existing alignment and 60 m on re- alignment or by-passes

(i)All projects located at altitude of 1000 mtr. and above; All projects except those 7(g) Aerial ropeways General Condition shall apply (ii)All projects located in covered in column (3). notified ecologically sensitive areas. Common Effluent Treatment 7(h) - All projects General Condition shall apply Plants (CETPs) Common Municipal Solid 7(i) Waste Management Facility - All projects General Condition shall apply (CMSWMF) 8 Building or Construction projects or Area Development projects and Townships The term “built up area” for the purpose of this Notification the built up or covered area on all the floors put together including its basement and other service areas, which are proposed in the building or construction projects. ≥20000 sq.mtrs and Note 1 - The projects or activities shall not include industrial shed, school, Building and Construction 8(a) <1,50,000 sq.mtrs. of built college, hostel for educational institution, but such buildings shall ensure projects up area sustainable environmental management, solid and liquid waste management, rain water harvesting and may use recycled materials such as fly ash bricks. Note 2 - “General Conditions” shall not apply.

Appendix 2: List of Projects or Activities Requiring Prior Environmental Clearance Page 154 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Category with threshold limit Project or Activity Conditions if any A B (1) (2) (3) (4) (5) A project of Township and Area Development Projects covered under this item shall require an Environment Assessment report and be apprised as Covering an area of > 50 Townships and Area Category ‘B1’ Project. 8(b) ha and or built up area > Development projects. 1,50,000 sq .mtrs Note : “General Conditions” shall not apply.

Appendix 2: List of Projects or Activities Requiring Prior Environmental Clearance Page 155 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 3: Chance Find Procedure

Contracts for civil works shall incorporate procedures for dealing with situations in which buried Cultural Property Resources (CPRs) are unexpectedly exposed. Recognition of unknown CPRs – This is the most difficult aspect to cover, especially if the contractor is not full-time accompanied by a specialist. Upon discovery of such material during project implementation work, the following should be carried out: • Immediately stop construction activities • With the approval of the Resident Engineer delineate the discovered site area • Secure the site to prevent any damage or loss of removable objects. In case of removable antiquities or sensitive remains, a night guard should be present until the responsible authority takes over • Through the Resident Engineer, notify the responsible authorities, the Department of Archaeology and local authorities within 24 hours • Submit a brief Chance Find Report, within a specified time period, with date and time of discovery, location of discovery, description of finding, estimated weight and dimension of CPR and temporary protection implemented • Responsible authorities would be in charge of protecting and preserving the site before deciding on the proper procedures to be carried out • An evaluation of finding will be performed by Department of Archaeology who may decide to remove the CPR deemed to be of significance, further excavate within a specified distance of the discovery point and conserve on-site, and/or extend/reduce the areas demarcated by the contractor etc. This should ideally take place within about 7 days • Construction work could resume only when permission is given from the Department of Archaeology after the decision concerning the safeguard of the heritage is fully executed

Appendix 3: Chance Find Procedure Page 156 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 4: CPCB’s National Ambient Air Quality Standards, GoI

Appendix 4: CPCB’s National Ambient Air Quality Standards, GoI Page 157 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 4: CPCB’s National Ambient Air Quality Standards, GoI Page 158 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 5: Noise Quality Standards, GoI

Appendix 5: Noise Quality Standards, GoI Page 159 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 6: Water Quality Standards, GoI

Tolerance and Classification As per ISI-IS: 2296-1982, the tolerance limits of parameters are specified as per classified use of water (Table 1,2,3,4,5 below) depending on various uses of water. The following classifications have been adopted in India. Class of Water Classification Type of use Class A Drinking water source without conventional treatment but after disinfection Class B Outdoor bathing Class C Drinking water source with conventional treatment followed by disinfection. Class D Fish culture and wild life propagation Class E Irrigation, industrial cooling or controlled waste disposal TOLERANCE LIMITS TABLE-1: TOLERANCE LIMITS FOR INLAND SURFACE WATERS, CLASS – A S. No. Characteristic Tolerance (1) (2) (3) (i) pH 6.5 to 8.5 (ii) Dissolved Oxygen, mg/l, 6.0 (iii) Bio-chemical Oxygen Demand 2.0 (iv) Total Coliform Organisms, MPN/100 ml, Max 50 (v) Colour, Hazen units, Max 10 (vi) Odour unobjectionable (vii) Taste Agreeable taste (viii) Total Dissolved Solids, mg/l, Max 500 (ix) Total Hardness (as CaCO3), mg/l ,Max 300 (x) Calcium Hardness (as CaCO3), mg/l, Max 200 (xi) Magnesium (as CaCO3), mg/1,Max 100 (xii) Copper (as Cu), mg/l, Max 1.5 (xiii) Iron (as Fe), mg/l,Max 0.3 (xiv) Manganese (as Mn), mg/1,Max 0.5 (xv) Chlorides (as Cl), mg/l,Max 250 (xvi) Sulphate (as SO4), mg/l ,Max 400 (xvii) Nitrates (as NO2), mg/1,Max 20 (xviii) Fluorides (as F,) mg/l,Max 1.5 (xix) Phenolic compounds(as C6H5OH), mg/l,Max 0.002 (xx) Mercury (as Hg), mg/l ,Max 0.001 (xxi) Cadmium (as Cd), mg/1,Max 0.01 (xxii) Selenium (as Se), mg/l ,Max 0.01 (xxiii) Arsenic (as As), mg/1,Max 0.05 (xxiv) Cyanides (as CN), mg/l, Max 0.05 (xxv) Lead (as Pb), mg/l, Max 0.1 (xxvi) Zinc (as Zn), mg/l, Max 15 (xxvii) Chromium (asCr6+ ), mg/l,Max 0.05 (xxviii) Anionic detergents, (as MBAS), mg/l ,Max . 0.2

Appendix 6: Water Quality Standards, GoI Page 160 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

S. No. Characteristic Tolerance (1) (2) (3) (xxix) Poly-nuclear aromatic hydrocarbons (PAH), 0.2 (xxx) Mineral oil, mg/l ,Max 0.01 (xxxi) Barium (as Ba), mg/l ,Max 1.0 (xxxii) Silver (as Ag), mg/l Max 0.05 (xxxiii) Pesticides Absent (xxxiv) Alpha emitters, μc/ml, Max 10-9 (xxxv) Beta emitters, μc/ml, Max 10-8 TABLE- 2: TOLERANCE LIMITS FOR INLAND SURFACE WATERS, CLASS – B S. No Characteristic Tolerance Limit (1) (2) (3) (i) pH Value 6.5 to 8.5 (ii) Dissolved Oxygen, mg/1,Max 5.0 (iii) Biochemical Oxygen Demand (5 days at 20 °C), Max 3.0 (iv) Total Coliform Organisms, MPN/100 ml, Max 500 (v) Fluorides (as F)

Appendix 6: Water Quality Standards, GoI Page 161 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

S.No. Characteristic Tolerance Limit (1) (2) (3) (xx) Insecticides, mg/l, Max Absent (xxi) Anionic detergents (as MBAS), mg/l, Max 1.0 (xxii) Oils and grease, mg/l, Max 0.1 (xxiii) Nitrates (as NO3), mg/1,Max 50 (xxiv) Alpha emititers, μc/mg, Max 10-9 (xxv) Beta emitters, μc/ml, Max 10-8 TABLE- 4: TEOLERANCE LIMITS FOR INLAND SURFACE WATERS, CALSS – D S.No. Characteristic Tolerance Limit (1) (2) (3) (i) pH value 6.5 to 8.5 (ii) Dissolved Oxygen, mg/l, Min. 4.0 (iii) Free Ammonia (as N), mg/l, Max. 1.2 (iv) Electrical Conductance at 25 °C, μS, Max 1000 (v) Free Carbon Dioxide (as C02),mg/1, Max 6.0 (vi) Oils and Grease, mg/l, Max 0.1 (vii) Alpha emitters, μc/ml, Max 10-9 (viii) Beta emitters, μc/ml, Max 10-8 TABLE- 5: TOLERANCE LIMITS FOR INLAND SURFACE WATERS, CLASS – E S.No. Characteristic Tolerance Limit (1) (2) (3) (i) pH value 6.0 to 8.5 (ii) Electrical Conductance at 25°C, μS, Max 2250 (iii) Sodium Adsorption Ratio, Max 26 (iv) Boron (as B), mg/l, Max 2.0 (v) Total Dissolved Solids, (inorganic), mg/l, Max 2100 (vi) Sulphates (as SO4), mg/l, Max 1000 (vii) Chlorides (as Cl), Mg/l, Max 600 (viii) Sodium Percentage, Max 60 (ix) Alpha emitters, μc/ml, Max 10-9 (x) Beta emitters, μc/ml, Max 10-8

Appendix 6: Water Quality Standards, GoI Page 162 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 6 (Contd): Drinking Water Specification (IS 10500:2012) Permissible Method of Requirement Limit in S. Test, Ref Parameter Unit (Acceptable Absence of Remarks No. to Part of Limit) Alternate IS 3025 Source Extended to 15 only, if toxic substances are not 1 Colour (Max) Hazen 5 15 Part 4 suspected in absence of alternate sources a) Test cold and when heated 2 Odour -- Agreeable Agreeable Part 5 b) Test at several dilutions Test to be conducted Parts 7 3 Taste -- Agreeable Agreeable only after safety has and 8 been established 4 Turbidity (Max) NTU 1 5 Part 10 -- 5 pH -- 6.5 to 8.5 No Relaxation Part 2 -- 6 Temperature OC ------Electrical µ 7 ------conductivity mhos/cm 8 Salinity ppt ------9 Total solids ------Total 10 Hardness as 200 600 Part 21 -- CaCO3 (Max) Total Alkalinity as Calcium 11 200 600 Part 23 -- Carbonate (Max) Total concentration of Iron as Fe manganese (as Mn) and 12 0.3 No Relaxation Part 53 (Max) iron (as Fe) shall not exceed 0.3 mg/l mg/l Chlorides as 13 250 1000 Part 32 Cl (Max) To be applicable only when water is chlorinated. Tested at Free Residual consumer end. When 14 0.2 1 Part 26 Chlorine (Min) protection against viral infection is required, it should be minimum 0.5 mg/l Total dissolved 15 500 2000 Part 16 -- solids (Max)

Appendix 6: Water Quality Standards, GoI Page 163 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Permissible Method of Requirement Limit in S. Test, Ref Parameter Unit (Acceptable Absence of Remarks No. to Part of Limit) Alternate IS 3025 Source Calcium as Ca 16 75 200 Part 40 -- (Max) Magnesium as 17 30 100 Part 46 -- Mg (Max) Copper as Cu 18 0.05 1.5 Part 42 -- (Max) Total concentration of Manganese as manganese (as Mn) and 19 0.1 0.3 Part 59 Mn (Max) iron (as Fe) shall not exceed 0.3 mg/l May be extended to 400 Sulphate as provided that 20 200 400 Part 24 SO4 (Max) Magnesium does not exceed 30 Nitrate as NO3 21 45 No Relaxation Part 34 -- (Max) Fluorides as F 22 1 1.5 Part 60 -- (Max) 23 Sodium as Na ------Potassium as 24 ------K 25 Total Nitrogen ------Total 26 ------phosphorous Free Ammonia 27 ------as NH4 Phenolic compounds as 28 0.001 0.002 Part 43 -- C6H5OH mg/l (Max) Biochemical 29 oxygen ------demand Chemical 30 oxygen ------demand Dissolved 31 ------oxygen Part 48(1) Mercury as Hg 32 0.001 No Relaxation Mercury -- (Max) analyser Cadmium as 33 0.003 No Relaxation Part 4 (I) -- Cd (Max)

Appendix 6: Water Quality Standards, GoI Page 164 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Permissible Method of Requirement Limit in S. Test, Ref Parameter Unit (Acceptable Absence of Remarks No. to Part of Limit) Alternate IS 3025 Source IS 3025 In case of dispute, the Selenium as (Part 56) method indicated by ,*, 34 0.01 No Relaxation Se (Max) or shall be the referee IS 15303* method Arsenic as As 35 0.01 0.05 Part 37 -- (Max) Cyanides as 36 0.05 No Relaxation Part 27 -- CN (Max) Lead as Pb 37 0.01 No Relaxation Part 47 -- (Max) Zinc as Zn 38 5 15 Part 49 -- (Max) Anionic Annex K 39 detergent as 0.2 1 of IS -- MBAS (Max) 13428 Chromium as 40 0.05 No Relaxation Part 52 -- Cr6+ (Max) Total coli 41 -- forms MPN/100 Shall not be Detectable in any IS 1622 Faucal coli ml 100 ml sample 42 -- forms It is recommended that the acceptable limit is to be implemented. Values in excess of those mentioned under 'acceptable' render the water not suitable, but still may be tolerated in the absence of an alternative source but up to the limits indicated under 'permissible limit in the absence of alternate source' in col 5, above which the sources will have to be rejected

Appendix 6: Water Quality Standards, GoI Page 165 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 7: Soil Quality Standards, GoI

STANDARD SOIL CLASSIFCATION Sl. No Soil Tests Classification <4.50 extremely acidic 4.51 -5.00 very strongly acidic 5.01 – 5.50 Strongly acidic 5.51 – 6.00 moderately acidic 6.01 – 6.50 Slightly acidic 1 pH 6.51 – 7.30 neutral 7.31 – 7.80 Slightly alkaline 7.81 – 8.50 moderately alkaline 8.51 – 9.00 Strongly alkaline 9.01 Very strongly alkaline Salinity Electrical Conductivity Upto 100 average 2 (mmhos/cm) 101 – 200 harmful to germination (1 mmho/cm = 640 ppm) 201 – 300 harmful to crops (Sensitive to salts) Upto 0.2 : Very less 0.21 – 0.4 : less 0.41 – 0.5 : medium 3 Organic Carbon 0.51 – 0.8 : On an average sufficient 0.81 – 1.0 : Sufficient > 1.0 : More than sufficient Upto 59 very less 51 – 100 less 4 Nitrogen (kg/ha) 101 – 150 good 151 – 300 better Above 300 sufficient Upto 15 very less 16 – 30 less 31 – 50 medium 5 Phosphorus (kg/ha) 51 – 65 on an average sufficient 66 – 80 Sufficient Above 80 more than sufficient 0 – 120 very less 120 – 180 less 181 – 240 medium 6 Potassium (kg/ha) 241 – 300 average 301 – 360 better Above 360 more than sufficient Source: Indian Council of Agricultural Research, New Delhi

Appendix 7: Soil Quality Standards, GoI Page 166 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 8: Stakeholder Consultations

Stakeholder Consultations - their views / perspectives As a part of the project several consultative meetings were held at site. Details of this are provided from Table 1 to 3. This section also provides the different stakeholders and beneficiaries. The specific details of the outcome of the meeting are tabulated and provided.

The Vessel Operator The vessel operator is responsible for the vessel operation, vessel maintenance, managing the ticketing system and managing the daily commuters. They pointed out some difficulties that they faced while operating. The vessels get overcrowded during the peak hours, some commuters try and get on and off board while the vessel is in motion, which causes some accidents and becomes unsafe for the commuters. Also they pointed out during peak hours it becomes almost impossible to check whether all commuters have paid for tickets or not.

The Jetty Operators Jetty operators are responsible for operation of the jetty as a whole. This includes cleanliness of the area around the jetty, managing the crowd, handling the crisis situations, and also looking after the safety and security of the travelers. In most of the cases the vessel operator and the jetty operator are the same organization. Sometimes, more than one operator is operating in a jetty, in which case, the jetty operator may be any one of the vessel operator.

Consultation with Jalsathy (Safety man) at Howrah Jetty

There are specially appointed Jalsathy (Safety Man) personal in most of the crowded Jetties both in Kolkata and Hooghly sides.

The Passengers The passengers or the daily commuters are the major stakeholders. They pointed out some problems that they faced and these problems were of similar types irrespective of the location of the jetties. Some of the issues that they pointed out are listed as below: a. The jetties and vessels needs up gradation b. The vessels are too high to climb for especially for the old and women commuters c. Travelling, getting on and off and walking on the gangway is a challenge for the physically challenged people, insisted for some handrails, and space for wheelchairs d. Washrooms on the vessels are in poor condition e. Washrooms in and around the jetty are not in usable condition f. There are no proper rest area in and around the jetty

Appendix 8: Stakeholder Consultations Page 167 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

g. Putting up of shade on the pontoon h. Widening of the gangway i. Electronic display of vessel timing and route j. Announcements of the arrival and departure of the vessel. The details of Consultation meetings at the jetties (commuters & Jetty workers) are provided in Table 3.

Appendix 8: Stakeholder Consultations Page 168 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Table 1: Consultation meetings with stakeholders (Vessel Suppliers) Name of the Types of Location Environmental Concerns Mitigation measures required Organization Business Located on the banks of the Site needs some monitoring and rearrangements. river Hooghly There should be proper markings on the areas No proper sign boards at the where the people are working. Markings like Building & Repair site ‘hazardous materials’, ‘store’, ‘waste disposal’ etc. of Ship, Vessel, A.C. Roy &Co Shibpur & workers are not very much should be clearly indicated. Vessel, Pontoons, (Total 2 Units) Ghusuri(Howrah) aware of the safety & Scraps are regularly auctioned and sold away Gangway etc. precautions required to be after a particular order is complete

taken while working Paints, spirit, oil and other liquids are bought as No proper storage area for much required and so there are no leftovers and storing of paints, spirit, oil wastes Located on the banks of the Building & Repair river Hooghly Site needs some monitoring and rearrangements. of Ship, Boat, No proper sign boards at the There should be proper markings on the areas Vessel, site Patra & Sons Shibpur (Howrah) where the people are working. Markings like Pontoons, Workers are not very much ‘hazardous materials’, ‘store’, Waste disposal’ etc. Gangway etc. aware of the safety & should be clearly indicated. precautions required to be taken while working Table 2: Consultation meetings for stakeholders (Vessel Operators) Sl. Name and Department Concerns Raised Mitigation measures required No. Designation • Safety norms • Oil Spill • Vessel Operation Rajat Bose • Vessel emission 1 Joint Managing WBTC Relevant Documents delivered by the respective officer • Waste management Director • Vessel Design & capacity • Passenger safety • No of vessel operation

Appendix 8: Stakeholder Consultations Page 169 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Sl. Name and Department Concerns Raised Mitigation measures required No. Designation • Regular survey • No of vessel Operation • Fuel efficiency • Disposal of abandoned Arup Dutta, Chief vessel 2 Engineer WBTC Relevant Documents delivered by the respective officer • Passenger safety (Marine) • Disposal of emission in water • Design of vessel • Construction on river side it has to be approved by Board of Trustee of KoPT • KoPT looks after CRZ clearance is not required for the stretch of river Hooghly conservation of river Capt. Srivastava under the scope of the project. The area is not CRZ zone that Hooghly and keep it 3 Deputy Director-1 KoPT can be classified as CRZ 1 ,II , III or IV as it does not satisfy navigable the requirement of CRZ. • Regular Hydrological survey

is carried out on the entire river • Whether CRZ clearance is required for this project • Separate three bins for waste disposal • Dry waste - Blue, Wet - Dr. Subhashis Green, Hazardous - Black Chatterjee • Taking up public awareness programme • Green bin waste is 4 Director General KMC • Design of various placard for awareness composted, Blue bin is (Solid Waste • Putting coloured bins at various sites. waste recycle Management) • Waste collected from vessels at some ghats is manually collected

Appendix 8: Stakeholder Consultations Page 170 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Sl. Name and Department Concerns Raised Mitigation measures required No. Designation • Formation of committee for taking the decision Md. Salim Ansari, • Mechanism of land • According to court it is done by direct purchase by the Chief MunicipalLaw acquisition 5 KMC client Officer • Legal Framework of Land • Value of purchase land is decided according to rate of acquisition market. • Grievances received from CM's office is addressed within Seven (7) days • No separate wings of grievance cell Biswajit Dutta • Whether any specific time- • Only 2 people are there to look after the issues Commissioner 6 WBTC frame to address the issues • No such mechanism developed by the authority • Grievance redressal • Whatever grievances are received, it only from ferry mechanism passengers • Nature of grievance for water transport • Project area is beyond of requirement of CRZ Clearance. Sidaharta Roy • Requirement CRZ This is not under CRZ category Senior Environment WBPCB clearance • Checking whether clearance of Pollution Control Board is 7 Officer • PCB clearance required or not from PCB office • Oil spill mitigation Plan • Oil spill mitigation plan need to be submitted at the time of starting of the project Ujjal Kumar PCB clearance for construction WBPCB Kolkata Port Trust is the final authority for any clearance of 8 Mukhopadhay on river front & operating construction on river front &operating vessels. Chief Scientist vessels.

Table 3: Consultation meetings at the Jetties (Commuters & Jetty workers) Sl. Stakeholder Response and Mitigation measures Concerns Raised No. Type suggested • Gangway needs to be widened • New structures/ are proposed to have wider Regular • To provide shade on the gangway gangway 1 Commuters • The height difference of the ferry and the pontoon to be • Construction of new and proper washrooms reduced and drinking water facility are also proposed Appendix 8: Stakeholder Consultations Page 171 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

• Separate corridor for elderly and physically challenged • Special design of the gangway to cater to the travelers elderly and the physically challenged people • Proper signboards regarding the route of the ferry • Electronic display system is also being • Proper announcement system proposed at the sites • Electronic display system at the terminals • Proper washroom facility on the jetty • New structures/ are proposed to have wider gangway • Proper signboards regarding the route of the ferry • Construction of new and proper washrooms • Proper announcement system Occasional and drinking water facility are also proposed 2 • Electronic display system at the terminals Commuters • Special design of the gangway to cater to the • Proper washroom facility on the jetty elderly and the physically challenged people • Washroom facility on the vessels • Electronic display system is also being proposed at the sites • Proper space for the shops and washroom to be properly • Construction of new and proper washrooms maintained and drinking water facility are also proposed 3 Shopkeepers • If the jetty services are upgraded, it will be a better place for • Temporary relocation plans to be discussed them to run business as the jetties will attract more and disclosed commuters • Proper sitting arrangements for the on-site workers • Construction of new and proper washrooms • Proper washrooms and drinking water facility are also proposed • Automatic ticketing system • Proper sitting arrangements will be taken 4 Site Workers • Proper signboards regarding the route of the ferry care of • Proper announcement system • Electronic display system is also being • Electronic display system at the terminals proposed at the sites

Appendix 8: Stakeholder Consultations Page 172 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

The local Governing bodies The major governing bodies in this case are Kolkata Municipal Corporation (KMC), Kolkata Metropolitan Development Authority (KMDA), West Bengal Transport Corporation (WBTC) and Kolkata Port Trust (KoPT). After consultation with the concerned authorities, the various issues like waste disposal (solid and liquid wastes) and the contingency plan was discussed. • KMC collects the solid waste from the vessels daily from designated places along the 35 ghats located along the Hooghly River. • The liquid waste was disposed directly into the river without any treatment. • Festive seasons; they also mentioned that they have taken initiative to clean up the river after the idol immersion during the festive season. This is a routine religious happening every year not related to project (Prevailing issue to resolve). Since larger community issues (beyond the size and scope of the project) are involved this is not in the purview of the project.

The shop owners There were a few shops around the jetty area. • The shop owners earn their livelihood by selling goods there. • They also complained of the rush hour pressure at the entrance of the jetties. • They wanted the sites to be more developed so that more commuters could be accommodated which will mean higher income for them as well.

Other beneficiaries Other beneficiaries include the local people, who will be benefitted due to the development. The local transport system include in to auto rickshaw, , etc., who will carry passengers from the jetty terminals to the main road in many of the cases. Overall by this development everyone in the locality will be benefitted. Jetty Beggars: As the government and various agencies are working for the welfare of people, it is necessary to rehabilitate the permanently occupied Land side beggars by giving suitable livelihood opportunities in the waterways sector for a descent earning.

Appendix 8: Stakeholder Consultations Page 173 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

A Report on Stakeholder Consultative Work Shop for West Bengal Inland Water Transport, Logistics and Spatial Development Project Project: West Bengal Inland Water Transport, Logistics and Spatial Development Project with World Bank Loan assistance. Date of workshop – October 31, 2019 Time: 10.30 to 1.30pm Venue of Workshop- Conference Hall, PMU’s office at Paribahan Bhaban – II (CSTC Complex – Ground Floor), Kolkata, West Bengal As per the guidelines of the World Bank a Stakeholder’s consultation and disclosure meeting was held at the Conference Hall, PMU’s office at Paribahan Bhaban – II (CSTC Complex – Ground Floor), Kolkata,, West Bengal on October 31, 2019. Before the meeting the PMU has invited the primary and secondary stakeholders’ at least seven days before the meeting. The invitation letter is also enclosed. Introduction and Welcome Speech by Project Director (PD) The workshop was chaired by the Project Director (PD) Mr Amitabh Sengupta. Meeting started with an opening welcome note by the Project Director, Mr. Amitabha Sengupta. The PD welcomed all the attendees including representative of different Government and quasi government departments, members of the civil society, vessels and ferry operators, vessels, pontoons and gangway manufacture and representatives from various Jetties. In addition from World Bank side the Environmental safe guard specialist Mr. Vaideeswaran and Social safe guard specialist Mr. Neeraj Singh also attended the meeting as observers. Presentation on the proposed Project by Project Director Following which the PD has given a power point presentation on overall background/ introduction to the proposed development project. Subsequently the ESMF/ESIA consultant has preceded with a presentation on the study findings up to this point and overall assessment of the project development was discussed. The Project Director narrated the necessity of the proposed project in context of the present transport crisis and environment. The PD also presented the brief outline of the Multi-modular Transport System for the near future. The presentation depicts a brief roadmap of the future transport in the state of West Bengal. The PD in his presentation conclude that the proposed First year project will improve cross-river passenger ferry infrastructure and services and freight movement along the Hooghly River between Triveni to Nurpur. The project has been proposed for financing by the World Bank as “West Bengal Inland Water Transport, Logistics and Spatial Development Project”. Environmental and Social management Framework The Team Leader of the ESMF/ESIA consultant L&TIEL, Mr. CV Sundara Rajan, introduced the team and initiated the Power point presentations. The presentations were divided into following components: • Overall Main Environmental/Social Assessment – presented by Mr. Reji Varghese, Environmental Engineer , L&TIEL • Details of the Resettlement Policy Framework – presented by Mr. Suman Sarkar, Social Expert L&TIEL

Appendix 8: Stakeholder Consultations Page 174 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

• Generic Environmental & Social Impact Management Mitigation Plan – presented by Mr. CV Sundara Rajan, Team Leader , L&T IEL project team • Presentations on Good and Bad/Poor Practices seen at the jetties – Mr. C V Sundara Rajan, Team leader, Social and environmental Assessment Introduction of Environmental and Social Management Framework (ESMF) The Team Leader of the ESMF team had a brief description of the basis and requirements of the Environmental and Social Management Framework and make path for the subsequent presentation of the Environment and Social presentation. He has giver an abstract of who is going to present what in the subsequent session of the workshop Environment presentation The Environmental Expert of the ESMF Team presented the Environmental Requirements of the State, National and the safeguard policy of the World Bank. Social and Resettlement Policy Framework (RFP) The Social Expert made the presentation of the Social Assessment and RPF. Social Assessment comprised: (i) Consultations with ferry users, (ii) Stakeholder Analysis, (iii) Institutional Analysis; and (iv) Impact Assessment. A Resettlement Policy Framework (RPF) has been prepared which will guide (i) for conducting Social Screening, (ii) Social Impact Assessment (SIA) based on the outcome of social screening, and (iii) preparation of Abbreviated Resettlement Action Plan (ARAP) or Resettlement Action Plan (RAP) depending upon the magnitude of impacts. The participants were interested about the Entitlements of the affected persons due to the project impact. As the First year project does not propose any impacts on the land side thus there might be negligible resettlement and rehabilitation impact explained by the Social Expert and supported by the PD. Environmental impacts and mitigation The most interactive session was the Environmental impacts and mitigation plan presented by the ESMF Team Leader. The participants were more interested regarding the Oil spill management, requirements of toilets, provide dolphin deterrent devices for river dolphin, etc. Good practices The Team Leader also presented the Good Practice followed by the jetties which include the presence of Jaal Sathi, latest Gate system at some jetties, availability of Safety Jacket, etc. Bad practices The working hours of the Jaal Sathi and other contract staff, Safety issue of the Pontoon, oil spillage, pressure on the pontoons during rush hours, spillage of the used tickets etc were discussed. Important Points discussed 1. Bally Ghat: will not be taken up under this proposed development. During the site consultations locals mentioned that the Bally Bridge provides convenient access across the river, as such having a jetty here would not provide added value. In addition, PD has mentioned that from the environmental point of view, there is a banyan tree at the access to the jetty location which is understood to be more than 100 years old. Also there is a Temple at the location. Further, there is a Water Treatment Plant located just adjacent to the ghat location. It would not be technically possible to construct the jetty at the present ghat location. To construct the jetty here would need Land Acquisition as jetty would need

Appendix 8: Stakeholder Consultations Page 175 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

to be constructed at a new location. Considering the above factors, development of a jetty at Bally Ghat is decided not to be taken up under this present scope. 2. CRZ Clearance: An official from the Dept. of Environment, asked for clarity on the project location as the presentation mentioned that proposed development falls beyond CRZ limits and CRZ Clearance will not be applicable. It was mentioned that CRZ limits are upto the Diamond Harbour area and as the proposed development is to be taken up beyond that point (Nurrpur onwards), the CRZ Notification would not apply. 3. Vessel Operation: Concerns of grounding of vessels, oil spills were raised. Need for having an Oil Spill Contingency Plan was suggested With regard to the disturbance to aquatic life in the waterways, it was suggested to have the vessels fitted with dolphin deterrent devices. This will help provide a warning to the fishes as the boat/vessel approaches 4. Sewage issues: direct disposal into the water body STP is too costly and not practical Official from IWAI suggested use of a sewage storage tank on the vessel and a collection tank at each terminal location; this is being practiced in Andaman & Nicobar Islands 5. Fuel Filling Station: Has a diesel filling station near Chandpal Ghat Suggestion for having floating filling stations Filling stations should ensure to have provisions for oil spill recovery 6. Fresh Water Source at Jetties: • Lack of fresh water source at most of the jetties was highlighted Provisions need to be made for supply of fresh water to all jetty locations Suggested that fresh water could be supplied through barges carrying the water 7. Pontoon Operations: a. Need for barricading on the pontoon and gangway was discussed in detail b. Few were not in favour of this as amongst one of the major adverse impacts could be that small boats could use this as place to tie their boats c. Also, need for having roof top over the gangway and link structure was discussed d. The technical feasibility of this was discussed e. It was mentioned that in most foreign countries roof top covering is provided on the gangway and link structures f. Also, an IWAI official mentioned that all such structures in Andaman & Nicobar Islands have been provided with the roof top covering 8. Need for Bigger Vessels: • An official from WBTC, enquired about feasibility of having bigger vessels with capacity of 300-400 PAX. PD mentioned that this enquiry will be looked into.

Appendix 8: Stakeholder Consultations Page 176 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

9. Vessel Building: • An official from a Ship Building Manufacturer mentioned that GoI is providing incentives for building vessels over 24 m length. • PD has requested that circular/guidelines in this regard be shared with the PMU and this will be looked into. 10. Jetty limits and Terminal building • In order to manage most of the issues a terminal building and Jetty limits were discussed. Closing remarks by Project director PD After the presentation there was an open session of for discussion and information from the participants pop up. It was learnt that the there is an incentive from the Central Government for ships beyond 24 m in length, there is specification requirement of sun shade or rain shade in the link way, there is a requirement of waiting hall, there should be more fueling centres, the Jaal Sathi working hours may be considered etc. The meeting ended with a vote of thanks to all from the PD. The Photographic Record of the Meeting

Appendix 8: Stakeholder Consultations Page 177 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

LIST OF ATTENDEES

Appendix 8: Stakeholder Consultations Page 178 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 8: Stakeholder Consultations Page 179 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 8: Stakeholder Consultations Page 180 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

List of other consultations Consultations with Stakeholders Response on Sl. Name of the Name of the Date of Designation Contract No Issues discussed proposed No Office Official Visit project West Bengal Safety norms, Oil Spill, Vessel Operation, Vessel emission, Jt. Managing 19-09- 1 Transport Mr. Rajat Bose 8697733273 Waste management, Vessel Design & capacity, Passenger High Support Director 19 Corporation safety, No of vessel in operation, etc. West Bengal No of vessel Operation, Fuel efficiency, Disposal of Chief Engineer 24-09- 2 Transport Mr. Arup Dutta 9051617695 abandoned vessel, Passenger safety, Disposal of emission -do- (Marine) 19 Corporation in water, Design of vessel Existing grievances redressal mechanism. No established Transport grievance mechanism exists at present. It is dealt on a case Department, Mr. Biswajit 19-09- 9647657740/ to case basis. Grievances received from CM's office are 3 West Bengal Commissioner -do- Dutta 19 9831035329 attended on priority basis. Broadly, complaints/grievances Transport received from CM's office are resolved in seven days. Corporation Occasionally complaints are received from ferry users. Construction on river side requires approval from Board of Trustee of KoPT, KoPT looks after conservation of river Deputy Director - 25-09- Hooghly and keeps it navigable, Regular Hydrological 4 Kolkata Port Trust Capt. Srivastava -do- 1 (Marine) 19 survey is carried out on the entire river, and CRZ clearance is not required for the stretch of Hooghly River under the scope of the project. Waste from vessel are collected at some ghats, Three bins Director General, Kolkata Municipal Dr. Subhashis 20-09- for waste disposal has been started, Green bin waste is 5 Solid Waste 9836536419 -do- Corporation Chatterjee 19 composted, Blue bin is waste recycle, public awareness Management program is being organized Land acquisition and resettlement and rehabilitation, Rules Md. Salim Kolkata Municipal Chief Municipal 20-09- not framed for land acquisition under RFCTLARR Act 2013, 6 Ansari, Law -do- Corporation Law Officer 19 Land required for projects purchased as per Direct land Department purchase from land owners through mutual consent, no

Appendix 8: Stakeholder Consultations Page 181 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Consultations with Stakeholders Response on Sl. Name of the Name of the Date of Designation Contract No Issues discussed proposed No Office Official Visit project provision of resettlement and rehabilitation in direct land purchase system. Requirement CRZ clearance - Project area is beyond of requirement of CRZ Clearance. This is not under CRZ West Bengal Senior Mr. Sidaharta 24-09- category. Requirement of clearance from Pollution Control 7 State Pollution Environment 9432136744 -do- Roy 19 Board for the proposed project needs further verification, Oil Control Board Officer spill mitigation plan needs to be submitted at the time of starting of the project activities. West Bengal 9830063508/ 033- Kolkata Port Trust is the final authority for any clearance of Mr. Ujjal Kumar 25-09- 8 State Pollution Chief Scientist 2335-2813, email: construction on river front & operating vessels, Permission -do- Mukhopadhay 19 Control Board [email protected] is not required from PCB in this regard.

Appendix 8: Stakeholder Consultations Page 182 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

LETTER OF INVITATION

Appendix 8: Stakeholder Consultations Page 183 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 8: Stakeholder Consultations Page 184 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 9: Draft Format for Monitoring of Grievances CONSOLIDATED STATEMENT ON GREIVANCE MANAGEMENT Name of Activities 1 2 3 4 5 5 6 7 8 9 10 11

ng) email Status Sl. No. Sl. (Query, (Query, Further Mode of of Mode Name of Address example: (Yes/No) resolving resolving resolving Remarks, Remarks, ( complaint complaint complaint Complaint) Suggestion, Suggestion, Summary ofSummary information/ information/ complainant of complaint complaint of convened on convened GRC Meeting (dd/mm/yyyy) (dd/mm/yyyy) (dd/mm/yyyy) Classification Constraints in in Constraints Phone/ Mob. & & Mob. Phone/ of Date receipt stipulated time nt of complaint complaint of nt Complaint Box/ Box/ Complaint Resolved within (Resolved/Pendi Acknowledgeme data required for for required data

Appendix 9: Draft Format for Monitoring of Grievances Page 185 West Bengal Inland Water Transport, Logistics and Spatial Development Project ESIA and ESMP Report for First Year Investments

Appendix 9: Draft Format for Monitoring of Grievances Page 186