Implementation Status & Results China Shandong Ecological Afforestation (P112759)
Operation Name: Shandong Ecological Afforestation (P112759) Project Stage: Implementation Seq.No: 3 Status: ARCHIVED Archive Date: 20-Dec-2012 Country: China Approval FY: 2010
Public Disclosure Authorized Product Line:IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Shandong Provincial Forestry Department Key Dates Board Approval Date 06-May-2010 Original Closing Date 31-Jul-2016 Planned Mid Term Review Date Last Archived ISR Date 26-Mar-2012 Public Disclosure Copy Effectiveness Date 11-Aug-2010 Revised Closing Date 31-Jul-2016 Actual Mid Term Review Date
Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to demonstrate effective afforestation models for environmentally degraded areas in support ofShandong's environmental afforestation programs. Has the Project Development Objective been changed since Board Approval of the Project?
Yes No Public Disclosure Authorized Component(s)
Component Name Component Cost Environmental Plantation Establishment 101.95 Technical Support and Project Management 6.35
Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Moderate Moderate Public Disclosure Authorized Implementation Status Overview Overall project implementation has continued to be good over the past year. Project management offices at provincial and county levels have made great efforts to promote the project ecological afforestation models, restore vegetation in highly degraded mountainous areas and establish protection plantations in saline coastal areas. It is also noted that the community consultation process has been mainstreamed and appreciated by participating communities and households. In addition, the technical support and extension activities, as well as the project monitoring and evaluation programs is also working well. Public Disclosure Copy
Locations
Page 1 of 5 Public Disclosure Authorized The World Bank Report No: ISR8691
Country First Administrative Division Location Planned Actual China Shandong Sheng Zoucheng Shi
China Shandong Sheng Zhucheng Shi
China Shandong Sheng Zhanhua Xian
China Shandong Sheng Yishui Xian
China Shandong Sheng Xintai Shi
China Shandong Sheng Wulian Xian
Public Disclosure Copy China Shandong Sheng Wudi Xian
China Shandong Sheng Weifang Shi
China Shandong Sheng Tai'an Shi
China Shandong Sheng Sishui Xian
China Shandong Sheng Rushan Shi
China Shandong Sheng Rizhao Shi
China Shandong Sheng Qufu Shi
China Shandong Sheng Qingzhou Shi
China Shandong Sheng Mengyin Xian
China Shandong Sheng Lijin Xian
China Shandong Sheng Laiwu Shi
China Shandong Sheng Kenli Xian
China Shandong Sheng Jiaxiang Xian
China Shandong Sheng Huimin Xian
China Shandong Sheng Gaomi Shi
China Shandong Sheng Dongping Xian
China Shandong Sheng Changyi Shi
Public Disclosure Copy China Shandong Sheng Binzhou Shi
China Shandong Sheng Bincheng Qu
Page 2 of 5 The World Bank Report No: ISR8691
Country First Administrative Division Location Planned Actual China Shandong Sheng Anqiu Shi
China Shandong Sheng Zhoucheng
China Shandong Sheng Laicheng Qu
China Shandong Sheng Hekou Qu
China Shandong Sheng Hanting Qu
China Shandong Sheng Donggang Qu
Public Disclosure Copy China Shandong Sheng Lanshan Qu
Results
Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Increased number of plant species growing on Number Value 3.00 12.00 15.00 project sites (No.) (b) saline coastal area Date 31-Dec-2009 30-Jun-2012 31-Jul-2016 Comments Improvement in environmental conditions (a) Percentage Value 100.00 81.00 80.00 decrease in soil erosion in mountainous area Date 31-Dec-2009 30-Jun-2012 31-Jul-2016 (percentage of baseline) Comments Increase of vegetative cover (tree, grass, and Percentage Value 7.00 26.00 55.00 shrub) in project sites (%) (b) saline coastal Date 31-Dec-2009 30-Jun-2012 31-Jul-2016 area Comments 26 Improvement in environmental conditions (b) Percentage Value 100.00 87.00 85.00 decrease in wind velocity at 5-10 time of tree Date 31-Dec-2009 30-Jun-2012 31-Jul-2016 height (percentage of baseline) Comments Increase of vegetative cover (tree, grass, and Percentage Value 16.00 23.00 60.00 shrub) in project sites (%) (a) Degraded Date 31-Dec-2009 30-Jun-2012 31-Jul-2016 mountainous area Comments Increased number of plant species growing on Number Value 10.00 36.00 30.00 project sites (No.) (a) degraded mountainous Date 31-Dec-2009 30-Jun-2012 31-Jul-2016 area Comments Public Disclosure Copy
Intermediate Results Indicators
Page 3 of 5 The World Bank Report No: ISR8691
Indicator Name Core Unit of Measure Baseline Current End Target Number of different local tree and shrub Number Value 15.00 38.00 44.00 species available in the project areas Date 31-Dec-2009 30-Jun-2012 31-Jul-2016 Comments Area restored or re/afforested Hectare(Ha) Value 0.00 58200.00 66000.00 Date 31-Dec-2009 30-Jun-2012 31-Jul-2016 Comments Area restored Hectare(Ha) Value Sub Type Date Breakdown Comments Public Disclosure Copy Areas of degraded mountain revegetation Hectare(Ha) Value 0.00 16810.00 18600.00 established: limestone areas Sub Type Date 31-Dec-2009 30-Jun-2012 31-Jul-2016 Breakdown Comments Areas of degraded mountain revegetation Hectare(Ha) Value 0.00 16180.00 19400.00 establishement: standstone areas Sub Type Date 31-Dec-2009 30-Jun-2012 31-Jul-2016 Breakdown Comments Areas of wind protection plantation in saline Hectare(Ha) Value 0.00 25210.00 27600.00 coastal areas established Sub Type Date 31-Dec-2009 30-Jun-2012 31-Jul-2016 Breakdown Comments Number of draft technical recommendations/ Number Value 0.00 6.00 10.00 guidelines developed and adopted Date 31-Dec-2009 30-Jun-2012 31-Jul-2016 Comments M&E system for physical and financial inputs Text Value N/A Yes Yes and outputs established and operational Date 31-Dec-2009 30-Jun-2012 31-Jul-2016 Comments
Data on Financial Performance (as of 09-Nov-2012)
Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P112759 IBRD-78820 Effective 06-May-2010 17-Jun-2010 11-Aug-2010 31-Jul-2016 31-Jul-2016
Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed Public Disclosure Copy P112759 IBRD-78820 Effective USD 60.00 60.00 0.00 25.82 34.18 43.00
Page 4 of 5 The World Bank Report No: ISR8691
Disbursement Graph Public Disclosure Copy
Key Decisions Regarding Implementation The next full supervision mission is scheduled in October 2013.
Restructuring History There has been no restructuring to date.
Related Projects There are no related projects. Public Disclosure Copy