Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

Assets | Engineering | Environment | Noise | Spatial | Waste

Traffic and Transport Assessment

Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean

Prepared for Aurigen Group Ltd

December 2016

Project Number: TW15042

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 1 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

DOCUMENT CONTROL

Version Description Date Author Reviewer 0a Internal Review 7/11/16 RO SC/TM 1a Draft Released to Client 11/11/16 RO/LM AM 1b Final Report 22/12/16 RO/LM AM

Approval for Release

Name Position File Reference Associate Director and Environment TW15042 - Traffic and Transport Andrew Mack Section Leader Assessment.1b Signature

Copyright of this document or any part of this document remains with Talis Consultants Pty Ltd and cannot be used, transferred or reproduced in any manner or form without prior written consent from Talis Consultants Pty Ltd.

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page i Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

Table of Contents

1 Introduction ...... 1

1.1 Background ...... 1

1.2 Scope of the Report ...... 1

2 Site Information ...... 2

2.1 Surrounding Land Uses ...... 2

2.2 Surrounding Road Network ...... 2

2.2.1 Crash Blackspots...... 2

2.2.2 Speed on the Surrounding Road Network ...... 2

2.3 Site Access ...... 3

2.3.1 Staff Access ...... 3

2.3.2 Pedestrian and Cyclist Access and Networks ...... 3

2.3.3 Public Transport Access ...... 4

2.4 On-site Parking ...... 4

2.5 Loading and Unloading Areas ...... 5

2.6 Environmental Noise ...... 5

3 Existing Traffic Volumes ...... 6

4 Development Proposal ...... 8

4.1 Assumptions ...... 9

4.2 SIDRA Analysis ...... 9

4.3 Impact on Scenario 1 and 2 ...... 11

4.4 Impact on Scenario 3 and 4 ...... 12

4.5 Committed Developments ...... 12

4.5.1 Lot 10 – Railway Parade, Bayswater ...... 12

4.6 On-site Vehicle Movements ...... 13

4.6.1 Turning Path Movements ...... 13

4.6.2 Traffic Safety on-site ...... 13

5 Conclusions ...... 14

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page ii No table of conten ts entries found.

Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

References...... 15

Tables

Table 2-1: Heavy vehicles accessing the Site during operation

Table 2-2: Proposed on-site parking facilities

Table 4-1: Future Operational Inbound/Outbound Traffic per day

Table 4-2: Level of Service Ratings

Table 4-3: SIDRA Analysis Summary – Existing Traffic Conditions

Table 4-4: SIDRA Analysis Summary – Scenario 1 and 2

Table 4-5: SIDRA Analysis Summary – Scenario 3 and 4

Diagrams

Diagram 3-1: Existing Weekday Traffic Flow with Heavy Vehicle Percentage over 1 hour (10:00 – 11:00)

Diagram 3-2: Existing Weekday Approach Volumes over 1 hour (10:00 – 11:00)

Plate

Plate 2-1: Bicycle Network surrounding the Site

Appendices

Appendix A : Manual Count Sheets

Appendix B : Drawings

Appendix C : SIDRA Modelling Output

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page iii

Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

1 Introduction

1.1 Background

Aurigen Group Limited (Aurigen) is a private waste service provider that specialises in a variety of services to domestic, industrial and local government clients including resource recovery, waste logistics, waste disposal and commodity aggregation and trading. Commodity aggregation refers to the sorting and consolidation of recycled materials in order to prepare them for sale to markets. Aurigen acquired a lease on 25 Jackson Street, Bassendean (the Site) in late 2015 where they propose to develop a Waste Transfer and Resource Recovery Facility (the Proposed Development). This will be an integrated Facility providing a range of recycling and waste management services reflective of modern, advanced facilities.

Talis Consultants Pty Ltd (Talis) has been engaged by Aurigen to prepare a Traffic and Transport Assessment (the Assessment) to determine the potential traffic impacts of operating the Facility on the adjacent road network and also considers the traffic arrangements within the Site. This Assessment has been requested by the (the Town) to support Aurigen’s planning approval sought for the proposed Facility, in addition to the Environmental Assessment and Management Plan (EAMP). Operation of the Facility will generate new inbound and outbound vehicle movements accessing the Site and the Assessment provides evidence that this increase in traffic will not cause an unacceptable impact to surrounding businesses and other road users.

1.2 Scope of the Report

This Traffic and Transport Assessment has been broadly prepared in general context with the Western Australian Planning Commission’s (WAPC) Traffic Impact Assessment Guidelines, Volume 4: Individual Developments (2016) to demonstrate to the Town that the Proposed Development will:

 Provide safe and efficient access for all modes of traffic type which will be associated with the proposed development;  Be well integrated with surrounding land uses;  Not adversely impact surrounding land uses; and  Not adversely impact surrounding transport networks and the users of those networks.

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 1 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

2 Site Information

The Site is located at 25 Jackson Street, Bassendean in the Bassendean Industrial Area within the administrative boundary of the Town of Bassendean, approximately 10km from the centre of Perth. The site is bordered by Jackson Street on its southwestern side with a separate access road to the Site from Alice Street to the southeast of the Site. The location of the site is shown in Figure 1.

2.1 Surrounding Land Uses

The Site is located in the middle of an industrial zone that is comprised of the Bassendean (or Tonkin) Industrial Area and the adjoining Bayswater Industrial Area to the west. Consistent with the zoning, the area is characterised by numerous industrial businesses including manufacturing companies and warehouses.

The closest residential area to the Site is located approximately 570m away to the north in the neighbouring suburb of Bayswater (within the ). These residences are situated directly adjacent to the northern extent of the industrial area, which extends onto the northern side of Collier Road.

There are also a number of waste management facilities at which similar operations are undertaken in the vicinity of the Site. Talis is of the opinion that this demonstrates that the Site is located within an appropriate area for the proposed Facility.

2.2 Surrounding Road Network

The surrounding road network in the immediate vicinity of the Site includes Jackson Street and Alice Street. Both Jackson Street and Alice Street are on the oversize Restricted Access Vehicle (RAV) network, as defined by Main Roads Western Australia (MRWA). These streets are considered as RAV Network 2-7 (Main Roads WA) roads, which means that vehicles equal or up to 36.5m in length and up to a mass of 107.5 tonne can utilise them. According to the MRWA Road Hierarchy, Jackson Street is classified as a Local Distributor road and Alice Street and Wood Street are classified as Access Roads, all of which have a speed limit of 50km/h.

2.2.1 Crash Blackspots

In preparation of this report, the Town’s Local Area Traffic Management (LATM) Plan (Opus, 2012) was reviewed. The LATM Plan sets out local traffic issues and proposed measures to address these issues. The intersection of Collier Road/Grey Street/Jackson Street was identified as a problematic crash site, ranking No. 1 based on crash data from 2006 to 2010, which reported 47 collisions. The LATM Plan indicated that this intersection was proposed for treatment with the construction of a dual lane roundabout. The Town submitted a nomination for the construction of the roundabout at the Collier Road/Grey Road/Jackson street intersection to MRWA in July 2012 and MRWA approved funding of the project under their 2014/15 State Black Spot Program.

2.2.2 Speed on the Surrounding Road Network

The LATM Plan also analysed the incidence of speeding on local roads. Jackson Street, at its northern end, Alice Street at its northern end and all of Wood Street were flagged as roads with over one quarter (25%) of road users exceeding the speed limit and in the 85th percentile speeds of 5km or more over the speed limit.

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 2 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

2.3 Site Access

The Bassendean Industrial Area is conveniently located in close proximity to a number of major arterial roads including Collier Road (approximately 100m to the north) and bordered by Railway Parade/ (approximately 750m to the south) and (approximately 415m to the west), which is accessible via Collier or Guildford Roads.

There are three gated vehicle access points to the Site. Two of these are from the front of the Site on Jackson Street, which are separated from each other by a security fence on a small embankment. There is a third Site access point from a private access road on the adjacent Alice Street. Most of the traffic will be dropping off or collecting commodities, recyclables or waste and will access the site via the northern Jackson Street or Alice Street entrances. Both of these entry points will be equipped with weighbridges. The Alice Street entry will also have a gatehouse.

Heavy vehicles will enter and exit the Site via two primary Site entrances, namely the northern Jackson Street entrance and Alice Street entrance. The types of heavy vehicles that will drop-off and collect waste and commodities are detailed in Table 2-1.

Table 2-1: Heavy vehicles accessing the Site during operation Vehicle Type Capacity Kerbside/Front Lift Collection vehicles 6-9 tonnes Semi-trailers such as side loading 20 tonnes B-doubles 60 tonnes

Given Waste Transfer and Resource Recovery are logistics operations, it is important that the Site is easily accessible by road. The Site is in an excellent strategic location, in close proximity to major roads including Collier Road (to the north) and Tonkin Highway (accessed via Collier Road) which provides easy access to other associated facilities (e.g. port).

2.3.1 Staff Access

Staff, maintenance and visitor vehicles will enter the Site through the northern of the two Jackson Street entrances to access the designated small vehicle car parking areas. The parking facilities on-site will be upgraded to include provision for at least 40 parking bays, as shown in the Conceptual Site Plan (Drawing G-001 in the EAMP). The number of inbound and outbound staff vehicles from the Site assumes one vehicle per staff member. Aurigen forecast the fully developed site would operate with thirty (30) staff members, with 10 parking bays allowed for visitors and maintenance vehicles. Aurigen will encourage the employment of local people at the Facility, the use of public transport, car sharing, or other sustainable forms of transport (cycling etc.). Therefore, it is anticipated that the staff vehicle traffic volumes will be significantly less than those estimated in the Assessment.

2.3.2 Pedestrian and Cyclist Access and Networks

There are no pedestrian footpaths currently located along Jackson Street. However, the Site has provision for pedestrians and cyclists to have direct access to the Site via the office, which is equipped with a dedicated path accessible from Jackson Street, north of the two vehicle entrances (see Conceptual Site Plan Drawing G-001).

According to the Department of Transport, Jackson Street is on the Perth Bicycle Network (

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 3 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

Plate 2-1) which connects with cycling routes to the east (towards Bassendean), north (towards Morley), west (towards Embleton) and south (towards Ashfield).

25 Jackson Street

Department of Transport of Department

Source:

Plate 2-1: Perth Bicycle Network surrounding the Site

2.3.3 Public Transport Access

The closest train station to the Site is Ashfield station on the Perth to Midland line, which is approximately 12 minutes’ walk from the Site. The closest bus stop is on Collier Road where bus no. 955 runs between Ellenbrook and Morley Bus Station.

2.4 On-site Parking

As mentioned above, there will be on-site parking provided for staff, maintenance and visitors. Details of the parking including the type, number and dimensions are shown in Table 2-2. The dimensions for car parking bays were allocated utilising of the following documents as guidance:

 Town of Bassendean’s Local Planning Policy No. 8 – Parking Specifications; and  Australian Standard Parking facilities – Part 6: Off-street parking for people with disabilities.

The location of the car parking facilities are shown on the Conceptual Site Plan (Drawing G-001 in the EAMP).

Table 2-2: Proposed on-site parking facilities Type of Parking No. of bays Parking angle Dimensions per bay Upgraded car park 17 0º or 90º 2.5m x 5.4m Undercover parking 4 0º 2.5m x 2.5m Parking outside office 3 90º 2.5m x 5.4m Parallel parking bays 14 45º 2.5m x 5.3m Disabled parking (with shared area) 2 90º 2.4m x 5.4m TOTAL 40 - -

The designated small vehicle parking area is located between the Jackson Street entrance and the main office, which accommodates 17 vehicles. There are an additional 3 parking spaces on the rear side of the office, along with two accessible (disabled) parking spaces. An additional 14 parallel

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 4 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

parking bays along the north-west perimeter of the Site. The parking area will include an upgraded car park, existing undercover parking and disabled parking facilities totalling 40 bays.

2.5 Loading and Unloading Areas

As shown in Drawings G301- G303, the designated loading and unloading areas are located in close proximity to each of the Facility’s proposed operations. An undercover unloading area on the south- eastern side of the Site next to the baler/shredder shed will enable vehicles to unload scrap metals prior to baling/shredding and consolidation in the Metal Recovery Facility. Once consolidated, scrap metal will be loaded into sea containers to the south-west of the Metal Recovery Facility ready for collection and shipment to overseas markets. The Materials Recovery Facility (MRF) and Waste Transfer Station (WTS) will have designated unloading areas (2 for the MRF and 3 for the WTS) inside the proposed building to allow vehicles to reverse and unload their waste. The Baling Shed that will bale paper and cardboard from the MRF will have a loading bay at its north-eastern end.

2.6 Environmental Noise

An Environmental Noise Assessment was undertaken for the Site by Lloyd George Acoustics (Lloyd George) (full report in Appendix E of the EAMP). The Noise Assessment concluded the Site complies with noise regulations during the daytime, Monday to Saturday 7:00 to 19:00. To operate the site on Sundays and public holidays between 9:00 and 19:00, a 5dB reduction in noise would be required.

Noise from trucks currently utilising the site from the Alice Street entrance were predicted to generate 67dB, which after a 5dB penalty for tonal noise emissions, results in an assembled level of 71dB. The assigned noise level for this industrial area during the day is 65dB. The assessment identified that a 6dB exceedance must be mitigated to ensure compliance with noise requirements. Lloyd George recommended that a noise wall be constructed along the east side of the ramp and a section of the north east boundary to mitigate noise form trucks. Implementing this targeted noise controls is anticipated to sufficiently reduce the environmental disturbance of any current or future traffic movements to and from the Site.

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 5 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

3 Existing Traffic Volumes

As part of this analysis, two intersections were analysed including Jackson Street and Alice Street, as well as Alice Street and Wood Street, as shown in Diagram 3-1. As mentioned previously, Jackson Street is classified as a Local Distributor road and Alice Street and Wood Street are Access Roads, both of which have a speed limit of 50km/h. These three roads surround the Site and will likely experience the most direct impact of any increase in traffic volume due to the operation of the Facility.

No recent traffic data was available on these roads from MRWA or the Town of Bassendean. As a result, in order to analyse current traffic movement, Talis performed a manual traffic count on these intersections. The traffic count was performed between 10:00-11:00 on a weekday to gain an average representation of peak traffic volumes. Based on advice from the client in relation to anticipated Site traffic, peak periods of two hours duration are anticipated to occur on weekday mornings (9:00-11:00) and afternoons (14:00-16:00).

Copies of the original manual count sheets have been attached in Appendix A. The results of the manual traffic count are shown below in Diagram 3-1, where the number of vehicles passing and percentage of heavy vehicles are displayed.

Diagram 3-1: Existing Weekday Traffic Flow with Heavy Vehicle Percentage over 1 hour (10:00 – 11:00)

The manual traffic count provided a breakdown of heavy vehicle traffic and overall volumes to be determined for the hour in question. From these volumes, the traffic flows towards the two primary Facility entrances can be calculated and used to determine traffic impact. The approach and exit flow for each direction is shown below in Diagram 3-2.

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 6 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

Diagram 3-2: Existing Weekday Approach Volumes over 1 hour (10:00 – 11:00)

As expected, the highest volume of traffic was observed on Jackson Street, as this road creates a direct connection between Collier Road and Railway Parade. At the time of the traffic count, none of the traffic movements involved vehicles entering and exiting the Site as the Facility is operating with limited traffic movements currently.

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 7 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

4 Development Proposal

Talis modelled the vehicle movements based on the quantity of waste and materials anticipated to be accepted per annum at the Site along with the types of vehicles expected to carry loads. For completeness, the incoming vehicles to the Waste Transfer Station (WTS) and Materials Recovery Facility (MRF) are predicted to be primarily kerbside waste collection vehicles with a capacity of approximately 9 tonnes. The incoming commodity drop-off vehicles may vary in capacity from 15 to 26 tonnes.

Table 4-1 sets out the anticipated daily vehicle movements to and from the Site based on the following design capacities:  Material Recovery Facility of 100,000 tonnes per annum (tpa);  Commodity aggregation activities of up to 120,000 tpa; and  Waste Transfer Station with capacity for 100,000 tpa.

It is important to note that the calculations have assumed a seven day working week for waste acceptance. In reality, fewer vehicles are expected on weekends than weekdays.

Table 4-1: Future Operational Inbound/Outbound Traffic per day Average No. of Vehicles Vehicle Total No. of Site Operations Vehicle Type during peak Capacity Vehicles period (2 hours) (tonnes) Inbound Traffic Materials Recovery Kerbside/front lift 6 46 16 Facility collection vehicle Commodity Drop-offs Various 20 50 8 Putrescible Waste Transfer Kerbside/front lift 9 30 11 Station collection vehicle Outbound Traffic Commodity Removals Various 20 28 5 (includes MRF Materials) Putrescible Waste Transfer Compaction 50 7 1 Station haulage vehicles Total Operational - 161 41 Vehicles Staff Staff Vehicles Cars - 30 0 Total Staff Vehicles - 30 0 Total Inbound/Outbound Traffic - 191 -

As shown in Table 4-1, the traffic data modelling indicates that there would be an estimated 161 vehicle movements or trucks dropping off and collecting waste and materials to and from the Site during normal operating hours (06:00-18:30) along with 30 staff vehicles.

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 8 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

During each of the two hour peak periods occurring in the morning (09:00-11:00) and the afternoon (14:00-16:00), the following predicted traffic volumes were utilised:

 35% of total daily inbound MRF vehicles (16 vehicles);  35% of total daily inbound Putrescible WTS vehicles (11 vehicles);  Inbound Commodity drop-offs (8 vehicles); and  Even distribution of outbound traffic associated with commodity collections and compacted putrescible waste removal (6 vehicles).

This equates to 41 vehicles over the two hour period or 20-21 vehicles over the one hour peak period. This is a conservative ‘worst-case’ approach towards expected vehicle movements and volumes are not anticipated to exceed these volumes. Commodity drop-offs and compaction haulage vehicle movements are not anticipated to experience ‘peak periods’ and were modelled to arrive and depart consistently over the duration of 12.5 hour working day.

Operational staff will be required to be present at the Site prior to waste vehicle arrivals and following the end of the day, so it was assumed that staff vehicle traffic did not impact site operation vehicles and was analysed separately. Designated staff car parking will also be provided for small vehicles (see Section 2.4 for more information).

To determine the impact constructing the proposed Facility would have on the surrounding traffic network, four scenarios were analysed and compared to current volumes, including:

 Scenario 1: Jackson Street Entrance (Trucks Only);  Scenario 2: Alice Street Entrance (Trucks Only);  Scenario 3: Staff Arriving Jackson Street Entrance; and  Scenario 4: Staff Departing Jackson Street Entrance.

4.1 Assumptions

When modelling the scenarios, the following assumptions were made:

 Manual traffic counts undertaken for one hour between 10:00-11:00 on a weekday on the intersections of Jackson Street and Alice Street, as well as Alice Street and Wood Street is during the morning peak period (09:00-11:00) expected at the Facility;  Half of the staff arrive and depart from the Site via Collier Road, whilst the other half arrive and depart from Railway Parade;  The model assumes that all staff will drive to work and each drive their own vehicle. In reality, there is potential for staff to carpool, cycle or use public transport with a dedicated pedestrian and cyclist access gate off Jackson Street; and  Half of the vehicle movements or trucks dropping off and collecting waste will utilise the Jackson Street entrance, arriving from and departing towards Collier Road, whilst the other half of vehicles movements or trucks are anticipated to access the Site via Alice Street utilising the Alice Street and Collier Road access point.

4.2 SIDRA Analysis

In order to assess the operation of the intersections and the impact of additional traffic, analysis was undertaken using SIDRA INTERSECTION 5.0 (SIDRA), a software package utilised for intersection design and modelling network capacity.

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 9 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

SIDRA creates a model based on the lane geometry and traffic volumes and provides a number of outputs including, but not limited to:

 Degree of Saturation: the ratio of demand to capacity on the approach to the intersection;  Average Delay: average of all time delays of vehicles travelling through the intersection; and  Average Speed.

One of the key outputs of the SIDRA analysis is the Level of Service for each approach to the intersection. Level of Service (LOS) is a qualitative measure used to describe the operating conditions of a roadway. By performing an analysis of current conditions and predicted traffic, the Level of Service provides a means of comparison to easily identify overall impact to the intersection. An explanation of the different Level of Service ratings is shown below in Table 4-2.

Table 4-2: Level of Service Ratings Level of Service Rating Traffic Condition LOS A Excellent Free flowing LOS B Very good Stable flow with minimal delays LOS C Good Stable with restricted movement LOS D Fair Movement more restricted LOS E Poor Traffic is congested with long queues and delays LOS F Very Poor Traffic demand exceeds intersection capacity

The current traffic volumes, as discussed in Section 3, were modelled in SIDRA to allow a comparison to be made against the predicted conditions. The results of the analysis are shown below in Table 4-3 including left (L), right (R) and through (T) traffic movements. Output calculations from the SIDRA modelling are presented in Appendix C.

Table 4-3: SIDRA Analysis Summary – Existing Traffic Conditions Intersection Degree of Average Delay Level of Average Turn Approach Saturation (sec) Service Speed (km/h) Jackson Street and Alice Street

Jackson Street: T 0.088 1.9 LOS A 45.1 South East R 0.088 9.3 LOS A 42.3 Alice Street: L 0.058 8.8 LOS A 41.2 North East R 0.058 10.0 LOS A 41.2

Jackson Street: L 0.059 7.3 LOS A 43.3 North East T 0.059 0.0 LOS A 50.0 Alice Street and Wood Street

Wood Street: T 0.027 7.3 LOS A 42.6 South East R 0.027 7.7 LOS A 42.4 Alice Street: L 0.023 7.0 LOS A 43.3 North East R 0.023 0.0 LOS A 50.0

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 10 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

Intersection Degree of Average Delay Level of Average Turn Approach Saturation (sec) Service Speed (km/h)

Alice Street: L 0.029 0.6 LOS A 47.1 South West T 0.028 8.1 LOS A 42.9

As shown in Table 4-3, the current traffic movements of both intersections are categorised as LOS A (Excellent) in all directions. Traffic is freely flowing and there are no significant delays experienced by any of the flow directions.

4.3 Impact on Scenario 1 and 2

When introducing the Facility’s operations into the analysis, the impact of the additional traffic on the existing volumes entering and exiting the Site could be determined through the SIDRA modelling process, as shown in Table 4-4.

Table 4-4: SIDRA Analysis Summary – Scenario 1 and 2 Intersection Degree of Average Delay Level of Average Turn Approach Saturation (sec) Service Speed (km/h) Scenario 1 - Jackson Street Entrance (Trucks Only)

Jackson Street: T 0.066 1.3 LOS A 45.5 South East R 0.050 1.3 LOS A - Site Entrance: L 0.050 12.6 LOS B - North East R 0.054 21.9 LOS C 33.8

Jackson Street: L 0.068 8.5 LOS A 42.2 North West T 0.068 0.0 LOS A 50.0 Scenario 2 - Alice Street Entrance (Trucks Only)

Alice Street: T 0.048 2.0 LOS A 45.7 North East R 0.048 11.3 LOS B 41.4

Site Entrance: L 0.020 9.2 LOS A 41.3 North West R 0.020 0.8 LOS A -

Alice Street: L 0.025 0.0 LOS A - South West T 0.022 0.0 LOS A 50.0

In Scenario 1, the north-west and south-east approaches of Jackson Street experienced no change to their Level of Service. The only changes appear to affect vehicles exiting the Facility from the Jackson Street access point turning left (LOS B) and turning right (LOS C), of which only the right turning vehicles are relevant as vehicles are expected to exit towards Collier Road for Tonkin Highway. The SIDRA modelling has determined that only vehicles entering and exiting the Facility are going to experience any sort of delay, with maximum average delays expected to be up to 21.9 seconds. The entrance has sufficient space for one B-double, the longest vehicle accessing the Site, to queue on the access road.

With respect to the SIDRA modelling for Scenario 2, all directions of traffic are classified as LOS A, except for the vehicles entering the Facility turning right from Alice Street. The only vehicles subject to any delays for Scenario 2 are the vehicles entering the Facility with maximum average delays

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 11 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

expected to be up to 11.3 seconds. The Alice Street entrance also has sufficient space for one B- double, the longest vehicle accessing the Site, to queue on the access road.

4.4 Impact on Scenario 3 and 4

The traffic conditions under Scenario 3, when staff arrive at the start of the day (pre-peak) and Scenario 4, when the staff leave at the end of the day (post-peak), in conjunction with the current traffic volumes is summarised in Table 4-5 below. These movements were modelled on a conservative basis assuming that morning and afternoon traffic volumes are the same as the Facility’s peak period. In reality, the traffic volumes at these times will be much lower.

Table 4-5: SIDRA Analysis Summary – Scenario 3 and 4 Intersection Degree of Average Delay Level of Average Turn Approach Saturation (sec) Service Speed (km/h) Scenario 3 - Jackson Street Entrance Staff Arrival AM

Jackson Street: T 0.086 1.3 LOS A 45.6 South East R 0.086 8.1 LOS A 42.8

Site Entrance: L 0.000 1.5 LOS A - North East R 0.000 1.5 LOS A -

Jackson Street: L 0.066 6.4 LOS A 43.3 North West T 0.066 0.0 LOS A 50.0 Scenario 4 - Jackson Street Entrance Staff Departing PM

Jackson Street: T 0.066 1.2 LOS A 45.8 South East R 0.050 1.2 LOS A -

Site Entrance: L 0.039 8.0 LOS A 41.9 North East R 0.039 8.3 LOS A 41.7

Jackson Street: L 0.050 0.0 LOS A - North West T 0.058 0.0 LOS A 50.0

All volumes under these scenarios still maintain the same level of service (LOS A) as the current traffic conditions. The office and parking areas are located on the Jackson Street side of the Site. All staff vehicles will enter the Site through the Jackson Street (small vehicle) entrance.

4.5 Committed Developments

4.5.1 Lot 10 – Railway Parade, Bayswater

As part of the Assessment, the Town requested that the Outline Development & Subdivision Concept Plan – Eastern Access Assessment (Concept Plan) be considered. The Concept Plan was prepared in relation to a development of vacant industrial land located at Lot 10 Railway Parade, Bayswater, south of the Site. This plan includes a new access point onto Tonkin Highway, a full movement access point on Railway Parade and construction of Vincent Street and Wicks Street, with a roundabout at its intersection with Jackson Street.

The Concept Plan reports on the preferred eastern road connection to the development. The preferred connection was found to be the proposed new road, Wick Street, onto Jackson Street with provision

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 12 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

of a new roundabout, at this intersection. The Concept Plan states that traffic would be anticipated to utilise Jackson Street to access Tonkin Highway however, no vehicle movements are quantified within the Concept Plan. Traffic produced as a result of this development is expected to interact with traffic volumes surrounding the Site. However, all vehicles accessing the Site during operations will access and depart the Site utilising Jackson Street and Collier Road or Alice Street and Collier Road for Tonkin Highway and are not anticipated to utilise Railway Parade or the new Wick Street/Jackson Street intersection.

4.6 On-site Vehicle Movements

4.6.1 Turning Path Movements

Vehicle movement mapping was performed for a kerbside collection vehicle, B-double and semi- trailer as shown in Drawings G-301- G-303 in Appendix B. These turning path movements demonstrate that the Site has sufficient capacity for all vehicles types modelled to manoeuvre between the loading and unloading areas, and still enter and exit the Site without major obstruction.

4.6.2 Traffic Safety on-site

A number of management measures will be adopted on-site to safely manage traffic including:

 Vehicles will be restricted to a maximum speed of 10km/hour whilst on the Site which will be signposted at appropriate locations including the entrance to the Site;  Signage providing Site directions, traffic control measures and safety instructions will be established and maintained at appropriate locations around the Site;  There will be adequate staff supervision to ensure staff safety around moving vehicles; and  Employees and contractors shall wear high visibility and reflective clothing when working in areas where vehicle movement occurs.

Further information in relation to traffic management on-site can be found in the EAMP.

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 13 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

5 Conclusions

The conclusions of the Traffic and Transport Assessment are as follows:

 The current traffic volumes on the road network surrounding the Site will experience minimal impact due to the predicted traffic movements during the Facility’s peak periods.

 The development of the proposed Facility will generate an estimated 161 heavy vehicle and 30 staff vehicle two-way movements (into and out of the Site) each day under the ‘worst-case’ scenario.

 Up to 70% of the total heavy vehicle traffic is expected during the morning and afternoon peak periods between 09:00-11:00 and 14:00-16:00 for Materials Recovery Facility and Waste Transfer Station drop-offs. This would result in up to 41 vehicle movements per hour with these vehicles utilising Jackson Street and Alice Street to access the Site and Collier Road.

 Turning path movements undertaken demonstrate that the Site has sufficient capacity for all vehicle types modelled to manoeuvre between the various loading and unloading points, and still enter and exit the Site without major obstruction.

 SIDRA analysis of the two Site entrances determined that these intersections have sufficient operational capacity for the Facility’s vehicle movements.

 The modelling indicates that the only delays created due to the additional traffic associated with the Site would be experienced by those vehicles entering and exiting the Site with maximum average delays expected to be up to 21.9 seconds. Both entrances have sufficient space for one B-double, the longest vehicle accessing the Site, to queue on the access road. The modelling indicates that surrounding businesses and other road users will not experience any significant impact.

 The development of Lot 10 Railway Parade, Bayswater has been considered as part of this Assessment. Traffic produced as a result of the development of Lot 10 Railway Parade is expected to interact with traffic volumes surrounding the Site. However, all vehicles accessing the Site during operations will access and depart the Site utilising Jackson Street and Collier Road or Alice Street and Collier Road for Tonkin Highway and are not anticipated to utilise Railway Parade or the new Wick Street/Jackson Street intersection.

 Based on the modelling, available information and the assumptions made, the Facility will have limited impact on the surrounding area and should not create a significant disturbance to surrounding business or other road users in the area.

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 14 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

References

Australian/New Zealand Standard Parking facilities. Part 6: Off-street parking for people with disabilities

Department of Transport. Perth, Fremantle and Stirling: Perth bike map. Available: http://www.transport.wa.gov.au/mediaFiles/active-transport/at_CYC_map_PerthFremantle-Stirling.pdf

Main Roads WA. Approved 2014/15 State Black Spot Program. Available at: https://www.mainroads.wa.gov.au/Documents/2014- 2015%20Approved%20State%20Black%20Spot%20Program%20- %20Local%20Roads%20(External%20Web%20Version).RCN-D14%5E23486393.PDF

Opus (2012), Town of Bassendean - Local Area Traffic Management Plan.

Town of Bassendean, Confirmation of Minutes for Ordinary Council Meeting held on 24 July 2012. Available at: http://www.bassendean.wa.gov.au/3_your_council/agendas_minutes/council-2012-08- 28-agn.htm

Western Australian Planning Commission’s (2016) Traffic Impact Assessment Guidelines, Volume 4: Individual Developments. Available at: http://www.planning.wa.gov.au/dop_pub_pdf/TIAGuidelinesVolume4IndividualDevelopments.pdf

1

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 15 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

Appendix A : Manual Count Sheets

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 16

Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

Appendix B : Drawings

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 17 P PO Box 454, Leederville WA 6903 | A Level 1 660 Newcastle St, Leederville WA 6007 | T 1300 251 070 | W www.talisconsultants.com.au

GREY ST 398,600 398,800 399,000 LEGEND

COLLIER RD COLLIER RD Site Boundary (! Manual Count Intersection ^_ Primary Site Access Points COLLIER RD 6,469,400 6,469,400

© Talis Consultants Pty Ltd ("Talis") Copyright in the drawings, information and data recorded in this document ("the information") is the property of Talis. This document and the information are soley for the use of the authorised recipient and J T this document may not be used, transferred or reproduced in whole or part A S for any purpose other than that which it is supplied by Talis without C E written consent. Talis makes no representation, undertakes no duty and K IC accepts no responsibility to any third party who may use or rely upon this S L document or the information. O A N S LOCALITY T Yanchep

(!2

Perth Armadale

Mandurah

6,469,200 ^_ 6,469,200

JACKSON ST WOOD ST km ^_ 0 20 40 80 120 160

DUFFY ST ALICE ST LOCALITY AND SURVEY MAP Aurigen - Traffic Impact Assessment

(!1 metres 0 5 10 20 30 40 Coordinate System: GDA 1994 MGA Zone 50 Projection: Transverse Mercator, Datum: GDA 1994 ¤ Scale @ A3:1:2,000 Prepared: TM Date: 4/11/2016 JACKSON ST Checked: RO Project No: TW15042 CLUNE ST Reviewed: NK Revision: A

JACKSON Figure 1 Figure 6,469,000 6,469,000 ST 398,600 398,800 LAVANST Data source: Roads, Suburbs, LGA's - Landgate,399,000 2015 and MRWA. Imagery: Nearmaps, 2015. Document Path: \\server\talis\SECTIONS\Waste\PROJECTS\TW2015\TW15042 - Auricom Jackson St Facility\GIS\Maps\TW15042_01T_TrafficLocality.mxd 3.00 8.05 12.50

1.40 8.05 0.00 9.15

0.00

1.40 4.50 0.45

B-DOUBLE 26M meters Tractor Width : 2.50 Lock to Lock Time : 6.0 Trailer Width : 2.50 Steering Angle : 23.4 Tractor Track : 2.50 Articulating Angle : 70.0 Trailer Track : 2.50

ASSET MANAGEMENT

CIVIL ENGINEERING

ENVIRONMENTAL SERVICES

SPATIAL INTELLIGENCE

WASTE MANAGEMENT

Level 1 660 Newcastle Street, Leederville WA 6007 w w w . t a l i s c o n s u l t a n t s . c o m . au T: 1 3 0 0 2 5 1 0 7 0 PO Box 454, Leederville WA 6903 4.20 13.70

1.40 9.50

0.20

1.60 5.30 PM S 19M meters Tractor Width 2.50: Lock to Lock Time 6.0: Trailer Width : 2.50 Steering Angle 27.8: Tractor Track : 2.50 Articulating Angle 70.0: Trailer Track 2.50:

ASSET MANAGEMENT

CIVIL ENGINEERING

ENVIRONMENTAL SERVICES

SPATIAL INTELLIGENCE

WASTE MANAGEMENT

Level 1 660 Newcastle Street, Leederville WA 6007 w w w . t a l i s c o n s u l t a n t s . c o m . au T: 1 3 0 0 2 5 1 0 7 0 PO Box 454, Leederville WA 6903 9.40 10.57

1.40 4.37 1.40 5.35

CAMION2 meters LOS meters Width : 2.50 Width : 2.55 Track : 2.39 Track : 2.55 Lock to Lock Time : 6.0 Lock to Lock Time : 7.4 Steering Angle 41.8: Steering Angle 41.2:

ASSET MANAGEMENT

CIVIL ENGINEERING

ENVIRONMENTAL SERVICES

SPATIAL INTELLIGENCE

WASTE MANAGEMENT

Level 1 660 Newcastle Street, Leederville WA 6007 w w w . t a l i s c o n s u l t a n t s . c o m . au T: 1 3 0 0 2 5 1 0 7 0 PO Box 454, Leederville WA 6903 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

Appendix C : SIDRA Modelling Output

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 18 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

SIDRA Analysis - Existing Traffic Flow for Jackson Street & Alice Street Intersection

SIDRA Analysis - Existing Traffic for Alice Street & Wood Street Intersection

SIDRA Analysis - Scenario 1 - Jackson Street Entrance (Trucks Only)

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 19 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

SIDRA Analysis – Scenario 2 – Alice Street Entrance (Trucks Only)

SIDRA Analysis – Scenario 3 -Jackson Street Entrance Staff Arrival AM

SIDRA Analysis – Scenario 4 – Jackson Street Entrance Staff Departing PM

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 20 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

Scenario 1 - Jackson Street Entrance Level of Service

Scenario 2 - Alice Street Entrance Level of Service

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 21 Traffic and Transport Assessment Waste Transfer and Resource Recovery Facility, 25 Jackson St, Bassendean Aurigen Group Ltd

Scenario 1 – Jackson Street Entrance Average Delay Times (secs)

Scenario 2 – Alice Street Entrance Average Delay Times (secs)

TW15042 - Traffic and Transport Assessment.1b December 2016 | Page 22