WELCOME TO THE SUNCOR COMMUNITY MEETING

Please fill out a comment card and visit www.suncor.com/fortymilewind for more information. If you have any further questions or concerns, please call 1-866-344-0178 ext. 2 or email [email protected] ABOUT SUNCOR

Suncor Energy is Canada’s leading integrated energy company. Our operations include oil sands development and upgrading, conventional and offshore oil and gas production, renewable energy development, petroleum refining, and product marketing under the Petro-Canada brand. Our vision is to be trusted stewards of valuable natural resources. Guided by our values, we will lead the way to deliver economic prosperity, improved social well-being and a healthy environment for today and tomorrow. SUNCOR’S RENEWABLE ENERGY BUSINESS

is one of the fastest growing sources of electricity generation in the world. Investment in wind power is a key component of Suncor’s climate change action plan. • Suncor and our partners are currently involved in five operational wind power facilities that have a generating capacity of 187 megawatts (MW), enough to power about 65,000 Canadian homes. • Suncor has developed and constructed a total of eight wind power facilities with a total generating capacity of 395 MW

Wind Projects Developed by Suncor

Date Project Name Location Capacity Turbines Current Owners

2002 SunBridge Saskatchewan 11 MW 17, 660 kW Suncor & Enbridge

2004 Magrath Alberta 30 MW 20, 1.5 MW GE Suncor, Acciona & Enbridge

2006 Chin Chute Alberta 30 MW 20, 1.5 MW GE Suncor, Acciona & Enbridge

2007 Ripley Ontario 76 MW 38, 2.0 MW Suncor & Acciona

2010 Kent Breeze 1 Ontario 20 MW 20, 2.5 MW GE TransAlta

2011 Wintering Hills 1 Alberta 88 MW 55, 1.6 MW GE IKEA Canada

2015 Adelaide Ontario 40 MW 18, 2.3 MW Siemens Suncor & Aamjiwnaang First Nation

2015 Cedar Point II 1 Ontario 100 MW 46, 2.3 MW Siemens Cedar Point II LP

1. Suncor sold our interest in these projects over the last few years as part of ongoing activities focused on core businesses and exploring opportunities for strategic divestitures.

WORKING WITH OUR STAKEHOLDERS

Our Beliefs • Involving communities in activities that affect them • Transparency • Early engagement • Mutual benefit • Sharing up-to-date project information

Goal • To be a trusted member of the communities where we operate by demonstrating our commitment to building and maintaining positive, meaningful relationships

Objectives • Engage early • Understand concerns, interests and values of communities we work with • Develop long-term positive relationships • Be responsive to community concerns

Approach • Build our knowledge of communities • Proactively engage with key stakeholders to share project information • Engage with community leaders on a regular basis • Understand development plans, visions and/or needs of community • Collaboratively work together to identify opportunities for shared benefit WHAT MAKES A SUCCESSFUL WIND PROJECT

A successful wind power project requires: 1) A strong wind resource 2) Access to transmission lines 3) An engaged and supportive community

Suncor believes that this area has the necessary elements for the development of a successful wind project.

We are here to learn more about your community and values - and to work together to develop our proposed wind project.

Source: AESO 2015 Long-term Transmission Plan BENEFITS OF WIND

What are the typical benefits of wind development?

• Employment – Temporary jobs during construction and permanent jobs associated with the operations and maintenance of the Project. There is the potential that local contractors would be involved in the construction of the Project.

• New Investment – In the form of local services and supplies such as infrastructure improvements, fuel, accommodation, meals and supplies for employees, construction personnel, and contractors who will spend time in the local communities.

• Landowners and Community – Wind turbines provide additional revenue to landowners and have a minimal impact on current farming practices. Wind turbines are compatible with other land uses, and can serve as a boost for rural economic development.

• Municipal Tax Revenues – Municipal taxes paid by wind companies to rural communities can be important, and the Project does not increase demand on municipal services or public works such as sewer and water upgrades. Payments from a wind project can be directly allocated to increasing local services or stabilizing local tax rates.

• Clean Energy – Wind energy provides societal benefits by offsetting harmful emissions such as carbon dioxide, oxides of nitrogen, and sulphur dioxides that are created through conventional, thermal power generation.

• Stability and Predictability– Wind energy costs are stable and predictable over the long term because there are no fuel costs. Wind energy helps to diversify and decentralize our power supply. The Proposed Forty Mile Wind Power Project

Proposed project details: • Size: 400 megawatts (MW) • Number of turbines: up to 175 • Tower height: up to 110 m • Rotor diameter: up to 145 m • Access and temporary construction roads • 2 project collector substations (Granlea & Maleb) • Underground and overhead electrical collector system from turbines to project collector substation • Connection infrastructure from project collector substations to the Alberta Interconnected Electrical System will be completed by Altalink Management Limited

The proposed Forty Mile Wind Power Project will deliver generated electricity to the grid via two proposed substations which will both have separate connections to the existing 240 kilovolts (kV) Alberta Interconnected Electrical System.

TOWNSHIP ROAD 102

95

AD

12 7 8 9 10 11 12 7 RO 8 9 10 11 12 7 8 9 10

E

G

TWP10 RGE10 RAN RGE9 RGE8

W4M 93

AD

RO 1 6 5 4 3 2 1 6 5 4 E 3 2 1 6 5 4 3

G

RAN TOWNSHIP ROAD 100 65 92 48 64 91 36 31 32 33 34 35 36 47 31 32 33 34 35 36 31 32 33 34 110 120 63 Murray 46 90 Lake 108 119 109 61 89 107 25 30 29 28 27 26 25 30 29 28 27 26 25 30 29 27 45 62 60 88 106 118 TOWNSHIP ROAD 94 5 44 59 87

105 127 4 117

AD 105

24 19 20 21 22 23 101 RO 24 58 19 20 21 22 23 24 19 20 21 22 12 126 E 43 86 AD G 3 116

RO 104 57 85

E

RAN

TWP9 G 42 11 115 125 RAN 56 103

94 10

13 18 17 16 15 14 13 18 17 AD 16 15 14 13 18 17 16 15 2 18 138

RO

100 84 114 137 9 41 E

G 124 Seven Persons Creek

AD TOWNSHIP ROAD 92

RO

RAN

0

E

1 8 83 102 136 40 G 1 1 55

D 54 113 135

A 17

RAN 12 7 8 7 9 10 11 12 39 7 8 9 10 11 12 7 8 9 10 101 123

E RO

92 134 16 82 100 NG 6 38

A 53 AD

R

22 99 RO 133

E 122

13 15 21 81 G 132

RAN 1 6 5 4 3 20 2 1 6 5 4 98 3 2 1 121 6 5 4 3 14 52 112 131 104 37 51

103 19 36 TOWNSHIP ROAD 90 AD AD TOWNSHIP ROAD 90

RO

RO E 97 111

G E 130

G 35

36 RAN 31 32 33 RAN 34 35 36 31 32 33 96 35 36 31 32 33 34 GRANLEA 129

102 SUBSTATION95 128 AD AREA RO 50 E 34 G 80 79 94 33 49 Granlea RAN Reservoir 25 30 29 28 27 26 25 30 29 28 27 26 25 30 29 28 27 32 93 31 168

TOWNSHIP ROAD 84 30 174 78 167

24 19 21 22 23 24 19 20 21 22 23 24 19 20 21 22 175 164 76 885 TWP8 77 166 173

k

e

29 e 163 r C 165 172 75 n a

g i 13 18 17 16 15 e 14 13 18 17 16 15 14 13 18 P 162 17 16 15 171 74 TOWNSHIP ROAD 82 72 73 28 71 161

105 170 27 AD 12 7 8 9 10 11 12 7 8 9 10 11 12 7 8 RO 9 10 70 158 E 26 G 159 160 169

RAN 25 69 95 101 68 157

AD

24 AD 1 6 5 4 3 RO 2 RO 1 6 5 4 3 2 1 6 5 4 3 E 156

E

G

23 G 67 MALEB

RAN

RANGE ROAD 94

TOWNSHIP ROAD 80 RAN SUBSTATION EXISTING ALTALINK AREA 66 148

WHITLA SUBSTATION 154 155 k k

e

e 36 31 32 33 34 35 36 31 32 34 r 33 35 36 31 32 33 C

n

147 a

g i

153 e

P

146 140 145

25 30 29 28 27 26 25 30 29 28 27 26 25 30 29 28 27 139 152

TOWNSHIP ROAD 74

143 144 151 24 19 20 21 22 23 24 19 20 142 21 22 23 24 19 20 21 22 150 40 Mile Coulee Lake TWP7 141 149

13 18 17 16 15 14 13 18 17 16 15 14 13 18 17 16 15

TOWNSHIP ROAD 72

12 7 8 9 10 11 12 7 8 9 10 11 12 7 8 9 10

104

AD

RO

E To Etzikom

G

RAN 1 6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3

TOWNSHIP ROAD 70 TOWNSHIP ROAD 70

Legend Notes 1. All mapped features are approximate and should be used Forty Mile Wind Power Project Proposed Turbine Location Secondary Highway for discussion purposes only. BROOKS 1 Proposed Blade Rotor Area Road ALBERTA Sources Map Extent SASKATCHEWAN Date Created: May 11, 2017 Reference Scale: 1:30,000 Residence Watercourse - Basedata: Government of Alberta - Layout: WSP Canada Inc., 2017 MEDICINE Page Size: 36" x 48" Coordinate System: NAD 1983 UTM Zone 12N Project Boundary Waterbody - Basemap: ESRI World Imagery 3 HAT - Inset Map: ESRI World Topographic Map LETHBRIDGE Existing 240 kV Transmission Line Township Boundary 61 2 Proposed Area for Project Collector Quarter Section Boundary 4 CANADA Substation and Temporary 0 1 2 3 U.S.A. Construction Parking/Offices 0 50 100 150 Kilometres Existing AltaLink Whitla Substation Kilometres Path : O:\!1000-\1025\005\03\mxd \fig1__1 025_005_03_OpenHouse_E-size _170511.m xd xd _170511.m 025_005_03_OpenHouse_E-size \fig1__1 O:\!1000-\1025\005\03\mxd: Path GOVERNMENT OF ALBERTA’S RENEWABLE ELECTRICITY PROGRAM (REP)

• The Renewable Electricity Program (REP) is intended to encourage the development of 5,000 MW of renewable electricity generation capacity connected to the Alberta grid between now and 2030. • The first competition will procure up to 400 megawatts of renewable electricity capacity with a target operational date of Dec. 1, 2019. The Alberta Electric System Operator (AESO) has shared the following timelines for the 2017 REP procurement:

Activity Timing Request for Qualifications (RFQ) due June 2017 Request for Proposals (RFP) due October 2017 Successful proponent(s) selected December 2017 PROPOSED TIMELINE

The timeline for design and construction of wind power projects can vary depending on a number of factors. If the Forty Mile Wind Power Project is successful in winning a contract through the Alberta Electric System Operator’s first competition, a potential timeline could look like the following:

• 2017: preliminary project design and permitting (including submitting a permit application to the Alberta Utilities Commission (AUC) for review and approval) • 2018: finalizing detailed project engineering and contracting • 2019: construction and commercial operations

The expected project process and timeline will include the following:

2016 – 2017 Late 2017 2018 – 2019 2019 – 2044

If Suncor is not successful in the first round of procurement, we will continue to develop the project for future competitions. POTENTIAL IMPACTS OF WIND

What are the potential impacts of wind development?

I’ve heard that the noise We follow specific requirements that are administered by the provincial caused by turbines can be government with regards to the sound guidelines for the operation of wind farms, annoying for area including conservative modeling and setbacks residents. (Alberta Utilities Commission Rule 012) Do wind farms kill birds As with all structures there are encounters with birds and bats. To mitigate the and bats? frequency/number of encounters, environmental studies are conducted and appropriate setbacks will be applied. We will also complete post construction monitoring to identify the impact of the wind farms on birds and bats. We will work with Alberta Environment and Parks to identify mitigation strategies as required. How would you address The result of numerous health studies is that the balance of independent, peer health and safety concerns reviewed, scientific research shows no direct link between wind turbines and related to this proposed harmful effects to human health as long as we follow provincial regulations and wind project? industry best practices for turbine siting. What is Suncor doing to Shadow flicker occurs when the blades of a turbine pass in front of the sun to minimize the shadow create a recurring shadow on an object. Currently the Province of Alberta does not flicker caused by the set standards for shadow flicker. Shadow flicker is contained to properties close to turbines? turbines. Mitigation measures can be employed by Suncor to reduce impacts caused by shadow flicker on a case by case basis. What kind of setbacks are Suncor applies industry best practice when determining appropriate setbacks from involved in this wind farm? environmental features and infrastructure in project design. POTENTIAL IMPACTS OF WIND

What are the potential impacts of wind development?

Do wind farms cause a Current studies show no direct link between wind turbines and decreased decrease in the value of property values. Suncor will continue to review third party studies related to properties nearby? property values. During construction there will be a large amount of construction material, equipment and personnel brought to and travelling through the project area. Like any large infrastructure project there may be traffic delays due to partial road closures, noise, increased dust and increased amounts of traffic.

What can I expect during Most of the construction will be on private lands however there may be impact to project construction? the public due to the number and size of loads for material like concrete as well as the turbine components. Suncor will work with the County to complete a detailed traffic management plan that reviews delivery routes for heavy and oversize loads and will also assess the condition of the roads and any upgrades required to support the project. What happens to the wind At the end of the 25 year operating life of the project, the owner could consider farm at the end of the life of decommissioning or repowering the facility with new components. the project? If decommissioning is chosen, the owner of the wind power project is responsible for the decommissioning of the Project. Suncor is committed to returning the site to a safe and clean condition after decommissioning of the Project as stated in our lease commitments. REGULATORY PROCESS

What government bodies and agencies need to approve or review wind development in Forty Mile County? Municipal • County of Forty Mile No. 8

Provincial • Alberta Utilities Commission • Alberta Environment and Parks • Alberta Transportation

Federal • Transport Canada • Nav Canada • Environment Canada • Royal Canadian Mounted Police • Department of National Defence WIND 101 – HOW DOES IT WORK?

Turbines consist of four main components: Foundation: concrete and rebar to provide strength

Tower: steel tubular sections up to 110m tall

Nacelle: houses the generator

Hub Rotor: diameter up to 145m

Turbines convert the kinetic energy in the wind into mechanical rotation, then to electrical energy. Wind lifts and turns the blades, the blades turn the rotor, the rotor is connected to the generator and the generator converts rotational energy to electricity.

Turbines are programmed to automatically rotate to face the wind direction, optimizing generation.

Power output from multiple turbines are collected via low voltage cables to a common substation. The transformer at the substation boosts the voltage to match the transmission network. CONSTRUCTION AT THE WINTERING HILLS WIND POWER PROJECT CONSTRUCTION AT THE WINTERING HILLS WIND POWER PROJECT CONSTRUCTION AT THE WINTERING HILLS WIND POWER PROJECT CONSTRUCTION AT THE WINTERING HILLS WIND POWER PROJECT SUNCOR’S MAGRATH WIND POWER PROJECT We want to hear from you!

Please help us build our community engagement plan for the proposed project by helping us get to know you better.

• What does Suncor need to know about this community as we advance this project?

• How do people in this community get their information? Are there specific newspapers, community bulletins, websites, email notices, Facebook pages, or other ways we should be communicating with you about the proposed project?

• What brings people in this community together? Think about events, values, organizations, or programs that build community here. As we work to become your neighbour, how can we enhance your community?

• What questions or concerns do you have about the proposed project?

THANK YOU FOR ATTENDING

We value your feedback and would like to learn more about your community. Please fill out a comment card and visit www.suncor.com/fortymilewind for more information. If you have any further questions or concerns, please call 1-866-344-0178 ext. 2 or email [email protected]