CONTENTS
CHAPTER 1 -EXECUTIVE SUMMARY ...... 01
CHAPTER 2 -DETAILED PROJECT DESCRIPTION ...... 03
CHAPTER 3 -TEAM COMPOSITION APPROACH, METHODOLOGY
AND SCHEDULE OF THE SOCIAL IMPACT ASSESSMENT ...... 06
CHAPTER 4 - LAND ASSESSMENT ...... 09
CHAPTER 5 -ESTIMATION AND ENUMERATION (WHERE REQUIRED)
OF AFFECTED FAMILIES AND ASSETS ...... 12
CHAPTER 6 –SOCIAL ECONOMIC AND CULTURAL PROFILE
(AFFECTED AREA AND RESETTLEMENT SITE) ...... 14
CHAPTER 7 - SOCIAL IMPACT MANAGEMENT ...... 17
CHAPTER 8 – SOCIAL IMPACT MANAGEMENT PLAN
INSTITUTIONAL FRAMEWORK ...... 19
CHAPTER 9 - SOCIAL IMPACT MANAGEMENT PLAN BUDGET AND FINANCING OF MITIGATION PLAN…………………………………...... 21
CHAPTER 10 - SOCIAL IMPACT MANAGEMENT PLAN MONITORING
AND EVALUATION ...... 22
CHAPTER 11 - ANALYSIS OF COSTS AND BENEFITS AND
RECOMMENDATION ON ACQUISITION ...... 23
ANNEXURES...... 25
SIA of Land Acquisition for Kurumkotta Boat Jetty
CHAPTER 1
EXECUTIVE SUMMARY
1.1 Project and public purpose
The proposed project is intended to construct Kurumkotta Boat Jetty. The term ‘Jetty’ will be renamed as internationally accepted term for boat station, ‘Pier’. Kurumkotta Boat jetty is a minor jetty and will be implemented as Phase I development. The jetty is proposed to be developed as floating pontoon. Automated docking mechanism with smart jetty architecture is proposed for the jetty. The pontoon will have covered roof to create a passenger comfort ambiance.
As per the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 Section 2-(1)-(b)-(vi), the project can be considered as a public purpose.
1.2 Location
The land to be acquired for the proposed project is located in Block No.4 of Cheranalloor Village of Ernakulam District.
1.3. Size and attributes of land acquisition
An extent of 15.8 Ares of land under survey numbers 624/5 (4.40 ares) and 624/7pt (11.40 ares) from Block No.4 of Cheranalloor Village of Ernakulam District is required for implementation of the proposed project.
1.4 Alternatives considered
No alternatives are identified for the implementation of the project.
1.5 Social impacts
The proposed land is owned by two individuals. The proposed project includes Home Stay Resorts named ‘Island D Cochin’. Due to the COVID-19 pandemic the business activities have faced a serious downfall. The resort employs three permanent staff. The proposed project site also includes compound walls and trees. Acquisition of land will result in the loss of income to the owners as well as the
Centre for Management Development, Thiruvananthapuram 1
SIA of Land Acquisition for Kurumkotta Boat Jetty
staff employed here. The owners also claimed that a portion of land was submerged in the lake and they demand a compensation needs to be given for that land too.
1.6 Mitigation measures
Though, by considering the following measures the authorities can mitigate and compensate the possible negative impacts of the land acquisition.
Compensation for the land owners as per the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013. Resettlement and Rehabilitation procedure as per the Policy issued by Revenue(B) Department, Government of Kerala vide G.O.(Ms)No.448/2017/RD dated 29/12/2017 for the rehabilitation and resettlement package for land acquisition in the state in lieu of RFCTLAR&R Act 2013.
Centre for Management Development, Thiruvananthapuram 2
SIA of Land Acquisition for Kurumkotta Boat Jetty
CHAPTER 2
DETAILED PROJECT DESCRIPTION
2.1 Background of the Project including Developer’s Background and Governance/Management structure
Often quoted as the Queen of Arabian Sea, Kochi is a major port city located on the south-western cost of India. It is a part of Ernakulam District in the State of Kerala. The city have a total urban population of more than 2.1 million within an area of 440 sq. km. as of 2011. Population growth rate of the surrounding municipalities and villages is more as compared to the urban area which in turn constitutes to increased traffic in commute between the mainland, nearby municipalities, adjoining islands and panchayaths. Recent traffic surveys and studies indicates the rapid growth of vehicles in the city premises. This in turn increase traffic jam during peak hours.
Kochi Metro Rail System was introduced to reduce private transport and encourage public transit. Kochi Metro Rail Limited (KMRL), as part of setting up of Metropolitan Transportation Authority (MTA-KOCHI), have initiated steps to implement a model transportation system for Kochi city region. Integrated Water Transport System for Kochi is been initiated to integrate the water transport system with other modes of transport
2.2 Rationale for Project, including how the project fits the public purpose criteria listed in the Act.
At present several State Water Transport Development mainly operates water transport system in Kochi. In addition to this various private operators and localised jangar services operates service. Over the last decades the system have been deteriorated due to depleting number of boats, low quality of boats, lack of safety measures, poor assess of infrastructure to the jetties, etc. More than 20,000 passengers uses the services of present system on a daily basis of which more than 50% access water transport. It was also found through various surveys that more than 70% of passengers are willing to shift to water transport system for transit as it saves about 15 minutes in comparison with other mode of transport.
Centre for Management Development, Thiruvananthapuram 3
SIA of Land Acquisition for Kurumkotta Boat Jetty
As per the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 Section 2-(1)-(b)-(vi), the project can be considered as a public purpose.
2.3 Details of Project size, location, capacity outputs, production targets, costs and risks
The implementation of the proposed project requires an area of 15.8ares of land. The land to be acquired for the proposed project is located in Block no. 4 of Cheranalloor Village of Ernakulam District.An estimated cost of INR 819.28 crores is expected to be the total cost of the project including land acquisition for all proposed boat jetties. Fig. 2.1: Photographs of Proposed Project Area
Centre for Management Development, Thiruvananthapuram 4
SIA of Land Acquisition for Kurumkotta Boat Jetty
2.4 Examination of alternatives
No alternatives is considered.
2.5 Phases of the Project Construction
The construction of the project will be completed based on the approved plans.
2.6 Core design Features, size and Type of Facilities
The existing jetty is built of cement and is in a decrepit condition. The term ‘Jetty’ will be renamed as internationally accepted term for boat station, ‘Pier’. Kurumkotta Boat jetty is a minor jetty and will be implemented as Phase I development. The jetty is proposed to be developed as floating pontoon. Automated docking mechanism with smart jetty architecture is proposed for the jetty. The pontoon will have covered roof to create a passenger comfort ambiance.
2.7 Need for Ancillary Infrastructural Facilities
Road access of the existing jetty is in a dilapidated condition. This will be rectified by providing adequate access roads with a minimum of 5 m width. Improved infrastructure facilities such as good lighting, security and safety assurance, etc., will be provided.
2.8 Workforce Requirements (temporary and permanent)
Both temporary and permanent workforce will be employed with modern machineries and equipment at appropriate stages of the project implementation.
2.9 Details of Social Impact Assessment/Environment Impact Assessment if Already Conducted and any Technical Facility Reports
No Social Impact Assessment/Environment Impact Assessment has been conducted previously.
2.10 Applicable legislations and policies
The land acquisition for the proposed project is governed by the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act (2013) & Rules (2015)
Centre for Management Development, Thiruvananthapuram 5
SIA of Land Acquisition for Kurumkotta Boat Jetty
CHAPTER 3
TEAM COMPOSITION, APPROACH, METHODOLOGY AND SCHEDULE OF THE SOCIAL IMPACT ASSESSMENT
3.1 List of all Team Members with Qualifications
The details of the team members involved in the SIA are given in Annexure III.
3.2 Description and Rationale for the Methodology and Tools Used to collect Information for the Social Impact Assessment
An inclusive and participatory approach through involvement of multiple stakeholders such as elected representatives and project affected people including vulnerable sections such as Scheduled Castes, Scheduled Tribes, women, and those among below poverty line, at appropriate stages of the project.
3.3 Sampling Methodology Used
Qualitative information was gathered along with the field survey through public consultation/Focus Group Discussions (FGDs) with all relevant stakeholders. The public consultation encompassed the project components as well as its socio- economic impacts. The SIA team had preliminary discussions with the key officials of the district administration and gathered information regarding the status of the government procedures, the project area and intensity of the acquisition. The team also made a preliminary site visit with the officials for physical inspection and information dissemination purposes. The existing conditions of land, status of infrastructure/structures, land use pattern and the facilities available to people residing in the project area were analysed.
The quantitative information regarding the families affected by the project was collected through household surveys, in the form of structured questionnaires. The survey was conducted in all the households of the persons affected by the project. The results of the survey provided information pertaining to the demography, socio-economic status and livelihood status of the target community, and formed the basis for development of Social Impact Management Plan.
Centre for Management Development, Thiruvananthapuram 6
SIA of Land Acquisition for Kurumkotta Boat Jetty
3.4 Overview of Information/Data Sources Used
The primary data was collected directly from the representatives of all affected families through face to face interview. Structured questionnaires were used for collecting the details of the affected people. The results of the survey provided information pertaining to the demography, socio-economic status and livelihood status of the target community.
The secondary data was collected from the Requiring Body and the Revenue department. The SIA team had preliminary discussions with the key officials of the district administration and gathered information regarding the status of the government procedures, the project area and intensity of the acquisition.
3.5 Schedule of Consultations with Key Stakeholders
Date Details of Consultation Collection of documents form November 2020 Land Acquisition office Meeting with the officials of November 2020 Requiring Body December 2020 Visit to project area December 2020 Collection of Primary Data 20/01/2021 Public Hearing
3.6 Public Hearing
In accordance with the Section 5 of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, a Public Hearing was conducted at Cheranalloor Panchayath Hall on 20/01/2021 at 10.30 am to collect the views and opinions of the people affected by the project. Prior intimation will be given to all the stakeholders regarding the date and venue of the public hearing through advertisements in leading newspapers, individual letters and/or over telephone.
Centre for Management Development, Thiruvananthapuram 7
SIA of Land Acquisition for Kurumkotta Boat Jetty
Figure 3.1. Photos from Public Hearing
Centre for Management Development, Thiruvananthapuram 8
SIA of Land Acquisition for Kurumkotta Boat Jetty
CHAPTER 4 LAND ASSESSMENT 4.1 Description of Land with the help of Maps, Information from Land Inventories and Primary Sources
The implementation of the proposed project requires an area of 15.8Ares of land. The land to be acquired for the proposed project is located in Block no. 4 of Cheranalloor Village of Ernakulam District.
Figure 4.1.Kurumkotta Boat Jetty Alignment
Centre for Management Development, Thiruvananthapuram 9
SIA of Land Acquisition for Kurumkotta Boat Jetty
4.2 Entire area of impact under the influence of the project
A total area of 15.8Ares of land from Block no. 4 of Cheranalloor Village of Ernakulam District needs to be acquired for the proposed project.
4.3 Total Land Requirement for the Project
For the implementation of the proposed project, an extent of 15.8 Ares of land from Block no. 4 of Cheranalloor Village of Ernakulam District is required to be acquired.
4.4 Present Use of any Public, Utilized land in the Vicinity of the Project Area
No such land is identified.
4.5 Land (if any) Already Purchased, Alienated, Leased or Acquired, and the intended Use for Each Plot of Land required for the project
No land has bees already acquired for the proposed project.
4.6 Quantity and Location of Land Proposed to be acquired for the Project
A total area of 15.8Ares of land from Block no. 4 of Cheranalloor Village of Ernakulam District needs to be acquired for the proposed project.
4.7 Nature, Present use and classification of Land and if Agricultural Land, Irrigation Coverage and Cropping Patterns
The land proposed to be acquired for the project is classified as dry land.
4.8 Size of Holding, Ownership Pattern, Land Distributions and Number of Residential Houses
Land under survey numbers 624/5 (4.40 ares) and 624/7pt (11.40ares) of land needs to be acquired for the proposed project. No residential houses are identified on the proposed project site. Commercial buildings are present on the proposed project location.
Centre for Management Development, Thiruvananthapuram 10
SIA of Land Acquisition for Kurumkotta Boat Jetty
4.9 Land prices and recent changes in ownership, transfer and use of lands over the last 3 years
As per the information received from the respondents, no land transactions were done in the proposed area for the last 3 years.
Centre for Management Development, Thiruvananthapuram 11
SIA of Land Acquisition for Kurumkotta Boat Jetty
CHAPTER 5
ESTIMATION AND ENUMERATION OF AFFECTED FAMILIES AND ASSETS
5.1 Estimation of families
a) Families which are directly affected (own land that is proposed to be acquired)
The land proposed for acquisition is possessed by 2 individuals.
5.2 Family of Scheduled Tribes and other Traditional Forest Dwellers who have lost any of their Forest Rights
Not Applicable
5.3 Families which depend on Common Property Resources which will be affected due to Land Acquisition for their Livelihood
No common property resources are affected by this land acquisition.
5.4 Families which have been assigned Land by the State Government for the Central Government Under any of its Schemes and such Land is Under Acquisition
Not Applicable
5.5 Families which have been Residing on any land in the Urban Areas for proceeding three years of more prior to the acquisition of land
Not applicable
5.6 Families which have depended on the Land Being Acquired as a Primary Source of Livelihood for three years prior to the acquisition
Not applicable
Centre for Management Development, Thiruvananthapuram 12
SIA of Land Acquisition for Kurumkotta Boat Jetty
5.6.1 Families which are indirectly impacted by the project (not affected directly by the acquisition of own lands)
Not applicable.
5.6.2 Inventory of productive assets and significant lands
The proposed land is owned by twoindividuals. The proposed project includes Home Stay Resorts named ‘Island D Cochin’. Due to the COVID-19 pandemic the business activities have faced a serious downfall. The resort employs three permanent staff. The proposed project site also includes compound walls and trees. Acquisition of land will result in the loss of income to the owners as well as the staff employed here. The owners also claimed that a portion of land was submerged in the lake and they demand a compensation needs to be given for that land too.
Centre for Management Development, Thiruvananthapuram 13
SIA of Land Acquisition for Kurumkotta Boat Jetty
CHAPTER 6
SOCIO-ECONOMIC AND CULTURAL PROFILE
6.1 Demographic Details of the Population in the Project Area
a) Age Group of Affected Individuals
Table 6.1.1. Age Group of Affected Individuals
Age in Years No. of Individual 0-18 2 19-30 3 31-45 1 46-59 3 60 and Above 1 N/A 0 Total 10
b) Gender of Affected Individuals
Table 6.1.2. Gender of Affected Individuals
Gender Number of Individuals Male 6 Female 4 Others 0 Total 10
c) Literacy of the Affected Individuals Table 6.1.3 Literacy of the Affected Individuals
Sl. Education Frequency No. 1 Lower Primary 2 Upper Primary & High School 1 3 Plus Two 1 4 Diploma 1 5 Graduation 6 6 Post-Graduation 1 Total 10
Centre for Management Development, Thiruvananthapuram 14
SIA of Land Acquisition for Kurumkotta Boat Jetty
d) Family Pattern
Affected families possess nuclear structure.
6.2 Vulnerable Groups
Vulnerable groups are not identified in the proposed location.
6.3 Land Use and Livelihood
The proposed land is owned by two individuals. The proposed project includes Home Stay Resorts named ‘Island D Cochin’. Due to the COVID-19 pandemic the business activities have faced a serious downfall. The resort employs three permanent staff. The proposed project site also includes compound walls and trees. Acquisition of land will result in the loss of income to the owners as well as the staff employed here. The owners also claimed that a portion of land was submerged in the lake and they demand a compensation needs to be given for that land too.
Table No. 6.1 Details of Owners
Sl. Survey Village Name Address Contact No. No. Number D. Island Home Denny/P.T. stays- Resorts, 1 624/5 Cheranallur 9847034981 John Alex Vaduthala - 682 023 Anugrah, PP Leo Road, Purushothaman 2 624/7 pt Cheranallur Chilavannoor, 9447039993 /Arun Kumar Kadavanthra-682 020
6.4 Local Economic Activities
The proposed project site is used as homestay resort.
6.5 Factors that Contribute to Local Livelihood
Not applicable.
Centre for Management Development, Thiruvananthapuram 15
SIA of Land Acquisition for Kurumkotta Boat Jetty
6.6 Kinship Patterns and Social and Cultural Organization
The area have a pleasant social environment. Land owned by the affected people is obtained by hereditary.
6.7 Administrative Organization
No administrative organisations are functioning in the area.
6.8 Political Organization
No political organisations are identified at the proposed project site.
6.9 Community Based Civil and Society Organization
No such organizations are affected by the proposed the project.
6.10 Regional Dynamics and Historical Change Process
No major negative impact could be found regarding the regional dynamics and historical change processes.
6.11 Quality of the Living Environment
The Quality of the Living Environment is fair in the project area with decent livelihood options and transportation facilities with access to amenities such as Schools, Hospitals, Civil Organisations, etc.
Centre for Management Development, Thiruvananthapuram 16
SIA of Land Acquisition for Kurumkotta Boat Jetty
CHAPTER 7
SOCIAL IMPACT MANAGEMENT
7.1 Approach to Mitigation
The CMD team made use of a combination of two research approaches i.e., quantitative and qualitative, for the identification of various social impact and the mitigation measures. Adoption of a combination of both qualitative and quantitative methodology was indented to obtain a more comprehensive data and more holistic result without excluding any important area of assessment.
7.2 Measures to avoid, mitigate and compensate impact
An extent of 15.8 Ares of land under survey numbers624/5 (4.40 ares) and 624/7pt (11.40 ares) from Block No.4 of CheranalloorVillage of Ernakulam District is required for implementation of the proposed project. Providing fair compensation to the owners will reduce the negative impacts.Also, by considering the following measures the authorities can mitigate and compensate the possible negative impacts of the land acquisition.
Compensation for the land owners as per the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013. Resettlement and Rehabilitation procedure as per the Policy issued by Revenue(B) Department, Government of Kerala vide G.O.(Ms)No.448/2017/RD dated 29/12/2017 for the rehabilitation and resettlement package for land acquisition in the state in lieu of RFCTLAR&R Act 2013. 7.3 Measures that are included in terms of Rehabilitation and Resettlement and Compensation as outlined in the Act
The Rehabilitation and Resettlement package as per the Policy issued by Revenue(B) Department, Government of Kerala vide G.O.(Ms)No.448/2017/RD dated 29/12/2017 for the rehabilitation and resettlement package for land acquisition in the state in lieu of RFCTLAR&R Act 2013 shall be provided to the affected people.
Centre for Management Development, Thiruvananthapuram 17
SIA of Land Acquisition for Kurumkotta Boat Jetty
7.4 Measures that the Requiring Body has stated it will introduce in the project proposal
The requiring body has stated that sufficient fund has been reserved as compensation.
7.5 Alterations to project design and additional measures that may be required to address the extend and intensity of impacts across various groups as identified during SIA
Not applicable.
7.6 Detailed Mitigation Plan including detailed activities to be carried out for each mitigation strategy, timelines for each mitigation strategy
To mitigate the social impact of the proposed land acquisition, R&R package should be provided to the families as per the Policies issued by Revenue(B) Department, Government of Kerala vide G.O.(MS)No.485/2015/RD dated 23/09/2015 and G.O.(Ms)No.448/2017/RD dated 29/12/2017 for the rehabilitation and resettlement package for land acquisition in the state in lieu of RFCT in LAR&R Act 2013.
Compensation for the land owners as per the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013. Resettlement and Rehabilitation procedure as per the Policy issued by Revenue(B) Department, Government of Kerala vide G.O.(Ms)No.448/2017/RD dated 29/12/2017 for the rehabilitation and resettlement package for land acquisition in the state in lieu of RFCTLAR&R Act 2013.
7.7 The Social Impact Management Plan indicating which measures the Requiring Body has committed to undertake and those that have been proposed, but not committed to be undertaken by the Requiring Body
The requiring body has stated that sufficient fund has been reserved as compensation.
Centre for Management Development, Thiruvananthapuram 18
SIA of Land Acquisition for Kurumkotta Boat Jetty
CHAPTER 8
SOCIAL IMPACT MANAGEMENT PLAN INSTITUTIONAL FRAMEWORK
8.1 Description of institutional structures and key person responsible for each mitigation measures
The Government of Kerala vide G. O. (P) No. 649/2015/RD dated 04/12/2015 had appointed Special Tahsildar, (L.A.)No.2,Kochi Metro Rail Project to perform one or more functions of the collector under in the Right to Fair Compensation and Transparency in Land Acquisition, Resettlement and Rehabilitation Act (RFCTLARR), 2013 within their area of jurisdiction.
Also vide G. O. (P) M. No. 590/2015/RD dated 11 November 2015, Government of Kerala, in line with the sub-section (1) of section 43 of the Right to Fair Compensation and Transparency in Land Acquisition, Resettlement and Rehabilitation Act (RFCTLARR) 2013 and sub-rule (1) of rule 21 of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Kerala) Rules, 2015, the Deputy Collector (Land Acquisition) in each district has been appointed as the Administrator for Rehabilitation and Resettlement, for performing the functions under the said act and Rules in respect of involuntary displacement of persons due to requisition of land. The Administrator shall be responsible for the formulation, execution and monitoring of the Rehabilitation and Resettlement scheme in respect of land acquisition.
Vide G. O. (P) M. No. 589/2015/RD dated 11 November 2015, in exercise of the powers conferred by sub-section (1) of section 44 of the Right to Fair Compensation and Transparency in Land Acquisition, Resettlement and Rehabilitation Act (RFCTLARR), 2013, the commissioner for Rehabilitation and Resettlement supervising the formulation of Rehabilitation and Resettlement scheme or plans, proper implementation of the same and post implementation of social audit.
Centre for Management Development, Thiruvananthapuram 19
SIA of Land Acquisition for Kurumkotta Boat Jetty
8.2 Specify the Role of Non-GovernmentalOrganisation, if any
Providing support services of a dependable NGO can help in alleviating the psycho-social impact of the acquisition.
8.3 Indicate Capacities Required and Capacity Building Plan, Including Technical Assistance, if any
Not applicable
8.4 Timelines for Each Activity
Proper timeline for each activity should be framed in accordance with the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act (2013) and Rules (2015).
Centre for Management Development, Thiruvananthapuram 20
SIA of Land Acquisition for Kurumkotta Boat Jetty
CHAPTER 9
SOCIAL IMPACT MANAGEMENT PLAN BUDGET AND FINANCING OF MITIGATION PLAN
9.1 Costs of all resettlement and rehabilitation costs
The requiring body stated that necessary budget provision exists for meeting the cost of acquisition.
9.2 Annual budget and plan of action
Not Applicable
9.3 Funding sources with break up
Not Applicable
Centre for Management Development, Thiruvananthapuram 21
SIA of Land Acquisition for Kurumkotta Boat Jetty
CHAPTER 10
SOCIAL IMPACT MANAGEMENT PLAN MONITORING AND EVALUATION
10.1 Key monitoring and evaluative indicators
Monitoring is a long-term process, which should begin from the starting of the project and should continue throughout the life of the project. Its purpose is to establish benchmarks so that the nature and magnitude of anticipated social impacts can be continually assessed. Monitoring involves the continuous or periodic review to determine the effectiveness of recommended mitigation measures. The types of parameters that can be monitored may include mitigation measures or design features, or actual impacts. All the mitigation measures stated in Chapter 7 should be considered as the indicators for evaluation.
10.2 Reporting mechanisms and monitoring roles
Rehabilitation and Resettlement procedures as stated in the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement act (2013) and Rules (2015) will be applicable.
10.3 Plan for independent evaluation
Not applicable.
Centre for Management Development, Thiruvananthapuram 22
SIA of Land Acquisition for Kurumkotta Boat Jetty
CHAPTER 11
ANALYSIS OF COSTS AND BENEFITS AND RECOMMENDATION ON ACQUISITION
11.1 Final conclusions on:Assessment of public purpose, less displacing alternatives, minimum requirements of land, the nature and intensity of social impacts, and viable mitigation measures and the extent to which mitigation measures will address costs
The proposed project is intended to implement KurumkottaBoat Jetty.
An extent of 15.8 Ares of land under survey numbers 624/5 (4.40 ares) and 624/7pt (11.40 ares) from Block No.4 of Cheeranalloor Village of Ernakulam District is required for implementation of the proposed project.
The proposed land is owned by two individuals. The proposed project includes Home Stay Resorts named ‘Island D Cochin’. Due to the COVID-19 pandemic the business activities have faced a serious downfall. The resort employs three permanent staff. The proposed project site also includes compound walls and trees. Acquisition of land will result in the loss of income to the owners as well as the staff employed here. The owners also claimed that a portion of land was submerged in the lake and they demand a compensation needs to be given for that land too.
Through the proper measures as per Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement act (2013) and Rules (2015) the negative impacts of land acquisition can be mitigated.
11.2 The above analysis will use the equity principle as a framework of analysis for presenting a final recommendation on whether the acquisition should go through or not.
Comparing/weighing the positive against the negative impacts, it can be observed that the implementation of the project will result in improving the overall development oftourism in Ernakulamdistrict.Through the execution of proper measures listed in chapter 7, the negative impact of the land acquisition can be mitigated.
Centre for Management Development, Thiruvananthapuram 23
SIA of Land Acquisition for Kurumkotta Boat Jetty
Thus, it can be concluded that the former outweighs the latter reaffirming the identified site as the most suitable and apt one for the project. The families that are affected would require adequate and fair compensation. It is observed that many of the negative impacts highlighted can be minimized or reduced with effective and relevant mitigation measures and strategies mentioned.
Thus the study suggests to acquire the land providing adequate compensation to the affected people.
Centre for Management Development, Thiruvananthapuram 24
SIA of Land Acquisition for Kurumkotta Boat Jetty
ANNEXURES
i. Details of the land covered in the SIA study
ii. List of key informants contacted and interacted
iii. SIA Team members
iv. Various Government Orders concerning Social Impact Assessment
v. Questionnaires used for survey
vi. Concerns raised and corresponding answers given during public hearing
vii. Notice and newspaper notification regarding public hearing
viii. Attendance of public hearing
Centre for Management Development, Thiruvananthapuram 25
SIA of Land Acquisition for Kurumkotta Boat Jetty
ANNEXURE-I
Details of the Land Covered in the SIA Study
Centre for Management Development, Thiruvananthapuram 26
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 27
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 28
SIA of Land Acquisition for Kurumkotta Boat Jetty
ANNEXURE-II
List of Key Informants Contacted and Interacted
1. Deputy Collector, L.A, Kochi Metro Rail Project
2. Special Tahsildar, (L.A.) No.2, Kochi Metro Rail Project
3. Concerned Officials of Water Metro Project
4. Elected Representatives
Centre for Management Development, Thiruvananthapuram 29
SIA of Land Acquisition for Kurumkotta Boat Jetty
ANNEXURE-III
SIA Team Members
Sl. No. Name Designation Qualification
1. Dr. G. Suresh Project Director Ph. D.
2. Shri. Riyas K. Basheer Project Coordinator MBA, B.Tech.
3. Dr. S. Remadevi Domain Expert Ph. D.
4.. Shri. Suradh K. Surendran Field Coordinator M. Tech.
5. Shri. Albin M. Project Officer MBA
6. Shri. Josukutty Kurian Project Officer MSW
Centre for Management Development, Thiruvananthapuram 30
SIA of Land Acquisition for Kurumkotta Boat Jetty
ANNEXURE-IV Various Government Orders Concerning Social Impact Assessment on Land Acquisition
Centre for Management Development, Thiruvananthapuram 31
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 32
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 33
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 34
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 35
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 36
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 37
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 38
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 39
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 40
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 41
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 42
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 43
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 44
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 45
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 46
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 47
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 48
SIA of Land Acquisition for Kurumkotta Boat Jetty
ANNEXURE- V Questionnaires used for survey
Centre for Management Development, Thiruvananthapuram 49
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 50
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 51
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 52
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 53
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 54
SIA of Land Acquisition for Kurumkotta Boat Jetty
ANNEXURE-VI Concerns raised and answers given during public hearing
t]cv Bi-¦-IÄ/Bh-iy-§Ä/]cm-Xn-IÄ _Ô-s¸« A[n-Im-cn-I- fpsS adp-]Sn tPmWn kÀ¡mÀ Gsä-Sp-¡m-\p-t±-in-¡p¶ 2013 se ]pXnb LARR AeIvkv `qan-bn dntkmÀ«v \S¯n hcp-I-bm- Act {]Im-c-amWv `qan Wv. Gsä-Sp-¡p¶ `qan-bn Ipd¨v Gsä-Sp-¡p-¶-Xv. Gsd-`mKw shÅ-¯n-\-Sn-bn Bbn- Gsä-Sp¡p¶ `qan-tbmSv t¸m-bn-«p-v. AXpw-IqSn IW-¡m¡n kmay-s¸« , aq¶v hÀj- \jvS-s¸-Sp¶/Gsä-Sp-¡p¶ `qanbv¡v ¯n-\p-Å- \S¶ Gähpw \à \jvS-]-cn-lmcw e`y-am-¡- Gähpw IqSnb hne-bm- Ww. hyh-kmb Øm]-\hpw, hcp-am- [mcw t\m¡n AXn-sâ \-hpw, Gsä-Sp-¡p¶ `qan-bn-epÅ icm-icn IW-¡m-¡n- \nÀ½m-W-§fpw ac-§fpw FÃmw bmWv hne \nÝ-bn-¡p-¶- \jvS-s¸-Sp-¶p-v. hÃmÀ]mSw sSÀan-\- Xv. en-\p-thn `qan Gsä-Sp-¯-Xnsâ \jvS-]-cn-lmcw C\nbpw In«n-bn-«n-Ã. s^-bÀhmeyp icm- A§s\ Hc-hØ Dm-h-cp-Xv. icntb¡mÄ IqSp-X-em- sW-¦n s^bÀ hmeyp \ne-hn sImtdmW h¶-Xn-t\m-S-\p-_- BIpw, ]cn-K-Wn-¡p-¶-Xv. Ôn¨v _nkn-\kv CÃ. AXn-\m \nÝ-bn-¡p¶ {]Imcw Ipsd ISw Dv. AXp-sImv `qan hne-bpsS 100 iX- hn«p-\ÂIm³ k½-X-am-Wv. Gähpw am\hpw IqSmsX Gsä-Sp- \Ã-hne \ÂI-W-sa¶v A`yÀ°n-¡p- ¡p¶ `qan-bn DÅ ¶p. sI«n-S-§-fp-sS-bpw, ac-§- _nkn-\kv \jvS-s¸-Sp-¶-Xn\v fp-sSbpw FÃmw {]tXyI {]tXyIw \jvS-]-cn-lmcw In«ptam hnebpw \ÂIp-¶-Xm-Wv. hgn \ne-\nÀ¯n XcWw `qan Gsä-Sp-¡p-¶-Xn\v ap³-]p- Xs¶ apgp-h³ \jvS -]-cn-lm-chpw A¡u-n \ÂIn-b-ti- jta Gsä-Sp-¡p-I-bp-Åq. \jvS-]-cn-lmcw t]msc- ¦n tImS-Xnsb kao-]n- ¡m-hp-¶-Xp-am-Wv. aq¶v hÀjw XpSÀ¨- bmbn _nkn-\kv \S-¶p- h-cp-¶-Xm-sW-¦n AXn\v {]tXyIw ]mt¡Pv Dm-Ipw. hgn kuIcyw \ne- \nÀ¯n Xcp-¶-Xm-Wv.
Centre for Management Development, Thiruvananthapuram 55
SIA of Land Acquisition for Kurumkotta Boat Jetty
2 tImta-gvky hmeyp IW-¡m¡n Acp¬ C³shÌv sNbvXv hm§nb `qanbpw IpamÀ XpS-§nb {]Øm-\-hp-am-Wv. `qan Gsä-Sp-¡p-t¼mÄ hcp-am\w CÃm-Xm- Ipw. Gsä-Sp-¡p¶ `qanbv¡v \ymb- amb hne \ÂI-Ww. AXnsâ \S-]-Sn- IÄ F{]-Im-c-amWv _me³kv hcp¶ `qan-bn-te-¡pÅ hgn \ne-\nÀ¯n Xc- Ww. an¨w-h-cp¶ `qan IqSn Gsä-Sp-¡p- Itbm AsÃ-¦n B `qan D]-tbm-K-{]- Z-am-Ip¶ Xc-¯n AXn-tebv¡v hgn kuIcyw e`y-am¡n Xcp-Itbm sN¿- Ww. ]©m-b¯v hnI-k\ {]hÀ¯-\-§Ä¡mbn `qan {]kn-Uâv hn«p \ÂIp-¶-h-cpsS a\-kns\ Ip- sIm-mWv \jvS-s¸-Sp¶ `qanbv¡pw Gähpw \ymb-amb \jvS-]-cn-lm-chpw _me³kv hcp¶ `qan-bn-te¡v t]mIp- hm³ \à hgnbpw e`y-am-¡n-sImv ]²Xn F{Xbpw thKw \S-¸m-¡-W- sa¶pw Bb-Xn-\mbn ]©m-¯nsâ FÃm-hn[ klmb kl-I-c-W-§fpw Dm-I-W-sa¶pw Adn-bn-¡p-¶p.
Centre for Management Development, Thiruvananthapuram 56
SIA of Land Acquisition for Kurumkotta Boat Jetty
ANNEXURE-VII Notice and newspaper notification regarding public hearing
Centre for Management Development, Thiruvananthapuram 57
SIA of Land Acquisition for Kurumkotta Boat Jetty
Janmabhoomi Dated 01/01/2021
Centre for Management Development, Thiruvananthapuram 58
SIA of Land Acquisition for Kurumkotta Boat Jetty
Deepika Dated 01/01/2021
Centre for Management Development, Thiruvananthapuram 59
SIA of Land Acquisition for Kurumkotta Boat Jetty
ANNEXURE-VIII Attendance of public hearing
Centre for Management Development, Thiruvananthapuram 60
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 61
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 62
SIA of Land Acquisition for Kurumkotta Boat Jetty
Centre for Management Development, Thiruvananthapuram 63
CENTRE FOR MANAGEMENT DEVELOPMENT (An Autonomous Institution Sponsored by the Government of Kerala) THYCAUD, THIRUVANANTHAPURAM KERALA – 695014