CHAPTER 6 Highways Department Tung Chung Road Improvement Project Audit Commission Hong Kong 28 March 2013 This audit review was carried out under a set of guidelines tabled in the Provisional Legislative Council by the Chairman of the Public Accounts Committee on 11 February 1998. The guidelines were agreed between the Public Accounts Committee and the Director of Audit and accepted by the Government of the Hong Kong Special Administrative Region. Report No. 60 of the Director of Audit contains 8 Chapters which are available on our website at http://www.aud.gov.hk Audit Commission 26th floor, Immigration Tower 7 Gloucester Road Wan Chai Hong Kong Tel : (852)28294210 Fax : (852) 2824 2087 E-mail :
[email protected] TUNG CHUNG ROAD IMPROVEMENT PROJECT Contents Paragraph EXECUTIVE SUMMARY PART 1: INTRODUCTION 1.1 – 1.17 Audit review 1.18 – 1.19 Acknowledgement 1.20 PART 2: PROJECT PLANNING AND 2.1 ENVIRONMENTAL IMPACT ASSESSMENT Decision in 1997 of not adopting 2.2 – 2.4 on-line widening arrangement Consultation on Tai Ho Wan Option from 1997 to 2000 2.5 – 2.20 Areas for improvement 2.21 – 2.28 Audit recommendations 2.29 Response from the Administration 2.30 PART 3: PROJECT IMPLEMENTATION 3.1 Project cost and completion time 3.2 – 3.8 Areas for improvement 3.9 – 3.28 — i — Paragraph Audit recommendations 3.29 Response from the Administration 3.30 – 3.32 PART 4: ADOPTION OF ALTERNATIVE DESIGNS 4.1 Contractor’s alternative design 4.2 2001 Technical Circular 4.3 2004 Technical Circular 4.4 Negotiation over alternative designs from 2004 to