IOM - Humanitarian Assistance Programme Weekly Activity Report

Week Starting Date Week Ending Date Period: 25 October 2017 31 October 2017 Submission Date: 01 November 2017

Cumulative Highlights01 January to 31 October 2017

# of Provinces # of ND # of Joint # of Report- # of Report- # of Houses # of Houses # of Houses # of Individu- # of Individu- # of Verified # of Verified # of Families # of Individ- Affected incidents Assessments ed Affected ed Affected Completely Severely Moderately als Deaths als Injured Affected Affected Assisted by uals Assisted Reported Families Individuals Destroyed Damaged Damaged Families Individuals IOM by IOM

33 256 527 15,814 110,673 1,878 4,769 1,261 121 104 7,214 46,183 5,233 36,631

2016 vs 2017 Analysis Weekly Highlights 25 –31 October 2017 # of Provinces # of ND # of Joint # of Report- # of Report- # of Houses # of Houses # of Houses # of Individu- # of Individu- # of Verified # of Verified # of Families # of Individ- Affected incidents Assessments ed Affected ed Affected Completely Severely Moderately als Deaths als Injured Affected Affected Assisted by uals Assisted Reported Families Individuals Destroyed Damaged Damaged Families Individuals IOM by IOM

Natural Disasters, Coordination and DRR activity UPDATE: 25-31 October 2017

Natural Disaster Updates: Takhar:

As per initial report by ANDMA; reportedly 45 families were displaced from Shortaghai village to various locations in Yangi Qala districts due to high risk of riverbank erosion. A joint assessment team consisting of IOM, ANDMA, DoRR and DAC was mobilized for assessment of the displaced families on 25 October. During the coordination with district governor, the team was not allowed to visit the area due to security concerns, the district governor also stated that caseload seems to be fake. The assessment team together with district governor agreed to refer the caseload to ARCS for verification.

Nangrahar- conflict IDPs: As per initial report obtained from ANDMA, around 2,000 families were reportedly displaced due conflict in Khogyani district on 16 October. 16 Joint assessment teams con- sisting of ARCS, IOM, ACTED, DORR, WFP/PAT, NRC, APA, DACAAR and NCRO initiated assessment in various locations of Khogyani, Surkh Road, Behsood and dis- tricts. So far 3,971 families were assessed of which 2,493 families were verified in need of humanitarian assistance. 1,027 families were assisted by UNHCR, NRC, WFP, SCI, ANDMA, DoRRD, DORR and ARCs with the provision of NFIs, food items, tents, emergency shelter, winter clothing and cash assistance. The assessment and response is on- going in various locations. Jowzjan conflict IDP Update: As per initial report obtained from agencies during PDMC meeting on 28 October, around 1,000 families were reportedly displaced due to conflict in Darzab and Qushtapa districts. Two joint assessment teams consisting of WFP, ZoA, SCI, ANDMA, DoRRD, ACTED and ARCS were assigned to first verify the reported displacement and initiate assess- ment following verification. The team visited the areas with reported displaced families and verified families being displaced by recent conflict in Qushtepa district. The teams have initiated assessment of the families on 31 October, the findings of the assessment will be shared with the PDMC members once the assessment concludes.

Disaster Risk Reduction (DRR):

The second round of the Community Based Disaster Risk Management (CBDRM) (early warning, search and rescue and first aid) training workshop initiated in two communi- ties in . - Two communities in Kapisa province, Ashor Khil and Ghani Khil village, Mohmood Raqi, Kapisa Province, 27 October for five days. 82 members of the community (41 male and 41 female) including a staff from ANDMA, DoRRD are participating in the training.

Natural Disaster Initial Incident Information Summary Sheet: 25-31 October 2017

Date of Inci- Date of Assess- Location Type of Incident # of ND Affected Families # of ND-Induced IDP Partner Agencies Involved in Assessment dent ment Province District Families Individual Families Individual

Total 45 315 45 315

16 CBDRM workshop In Central Region 20 August-31 October 2017 Workshop Selected Communities Date Participants Number of partici- No Phases Village District Province Start End Male Female Training status pants CBDRM1 2-Oct-17 6-Oct-17 71 41 30 Completed 1 Ghani Khail Dara Panshir CBDRM2 8-Oct-17 12-Oct-17 43 22 21 Completed CBDRM1 2-Oct-17 6-Oct-17 69 39 30 Completed 2 Manjahor Bazarak Panshir CBDRM2 8-Oct-17 12-Oct-17 42 21 21 Completed CBDRM1 24-Sep-17 28-Sep-17 73 43 30 Completed 3 Ali khill Mahmood Raqi Kapisa CBDRM2 2-Oct-17 6-Oct-17 40 20 20 Completed CBDRM1 24-Sep-17 28-Sep-17 70 40 30 Completed 4 Badam Ali Mahmood Raqi Kapisa CBDRM2 2-Oct-17 6-Oct-17 41 20 21 Completed CBDRM1 2-Oct-17 6-Oct-17 71 41 30 Completed 5 Mori Kham Zargar Hasa Awal Kapisa CBDRM2 8-Oct-17 12-Oct-17 41 20 21 Completed CBDRM1 2-Oct-17 6-Oct-17 73 41 32 Completed 6 Lakar Gul bahar Jabal Sirag Parwan CBDRM2 8-Oct-17 12-Oct-17 42 21 21 Completed CBDRM1 2-Oct-17 6-Oct-17 71 41 30 Completed 7 Parcha 11 Charikar Parwan CBDRM2 8-Oct-17 12-Oct-17 41 21 20 Completed CBDRM1 8-Oct-17 12-Oct-17 74 43 31 Completed 8 Royab Charikar Parwan CBDRM2 15-Oct-17 19-Oct-17 42 21 21 Completed CBDRM1 8-Oct-17 12-Oct-17 71 41 30 Completed 9 Balto khill Charikar Parwan CBDRM2 15-Oct-17 19-Oct-17 42 21 21 Completed CBDRM1 15-Oct-17 19-Oct-17 70 38 32 Completed 10 Shahrak Medyah PD-13 Kabul CBDRM2 21-Oct-17 25-Oct-17 45 22 23 Completed CBDRM1 15-Oct-17 19-Oct-17 72 42 30 Completed 11 Shahrak Khurasan PD-16 Kabul CBDRM2 21-Oct-17 25-Oct-17 45 24 21 Completed CBDRM1 15-Oct-17 19-Oct-17 73 41 32 Completed 12 Qala Abdul Ali Paghman Kabul CBDRM2 21-Oct-17 25-Oct-17 43 22 21 Completed CBDRM1 15-Oct-17 19-Oct-17 72 42 30 Completed 13 Speen Jomat Dehsabz Kabul CBDRM2 21-Oct-17 25-Oct-17 41 21 20 Completed CBDRM1 15-Oct-17 19-Oct-17 73 43 30 Completed 14 Naqash PD-6 PD-06 Kabul CBDRM2 21-Oct-17 25-Oct-17 41 20 21 Completed CBDRM1 21-Oct-17 25-Oct-17 72 41 31 Completed 15 Ashor Khil Mahmood Raqi Kapisa CBDRM2 27-Oct-17 31-Oct-17 40 20 20 Ongoing CBDRM1 21-Oct-17 25-Oct-17 73 42 31 Completed 16 Ghani Khail Mahmood Raqi Kapisa CBDRM2 27-Oct-17 31-Oct-17 42 21 21 Ongoing Community Based Disaster Risk Management (CBDRM) training workshop, Ashor Khil village, Mohmood Raqi, Kapisa province – 27 Oct, 2017 @ IOM

Community Based Disaster Risk Management (CBDRM) training workshop, Ashor Khil village, Mohmood Raqi, Kapisa province – 27 Oct, 2017 @ IOM Note: The figures on the map is extracted from Multi-sector Rapid Assessment Form (MSRAF) database, the differences in the figures on the first page is due to MSRAFs not yet submitted to IOM and yet to be encoded in HAP DB. Stock Update Countrywide (31 October 2017) Family Revitalisa- Emergency Shelter Blanket Mod- Winter Clothing Region Warehouse Winter Kit Tarpaulin Household Module Solar Module Family Tent tion Kit Kit ule Module Kabul 1 0 2,052 0 2,610 1,399 624 2,089 784 Central Logar 0 0 272 0 4 0 0 Sub Total 1 0 2,324 0 2,610 1,399 628 2,089 784 Bamyan Centre 0 0 544 0 1,011 768 763 394 184 Central Highland Daikundi-Nilli 0 0 272 33 1,042 398 638 495 100 Lal Wa Sare Jungle 0 0 224 0 545 321 204 187 50 Sub Total 0 0 1,040 33 2,598 1,487 1,605 1,076 334 Badakshan-Faizabad 12 1 625 0 2,112 807 1,008 383 316 BDK-Ishkashim-FOCUS 38 0 0 0 0 0 0 0 0 BDK-Wakhan-FOCUS 0 0 0 0 100 0 89 0 0 BDK-Sheghnan-FOCUS 0 0 0 0 89 0 0 0 0 Northeast BDK-Shukai-FOCUS 75 0 0 0 0 0 0 0 0 BDK-Nussai-FOCUS 85 0 0 0 0 0 0 0 0 BDK-Maymai-FOCUS 100 0 0 0 0 0 0 0 0 Badakshan-Ishkashim 500 0 0 0 0 0 0 0 0 Takhar-Taloqan 0 0 56 0 315 443 150 165 100 Sub Total 810 1 681 0 2,616 1,250 1,247 548 416 Ghazni 0 0 111 0 168 185 73 187 56 Southeast Paktia-Gardez 0 0 344 0 1,352 1,025 666 316 303 Sub Total 0 0 455 0 1,520 1,210 739 503 359 Herat 0 0 839 601 1,226 862 456 616 397 Ghor- 0 55 200 0 172 200 122 0 0 West Farah 0 0 168 0 164 214 100 100 0 Badgish 0 5 105 0 165 115 83 82 0 Sub Total 0 60 1,312 601 1,727 1,391 761 798 397 East Jalalabad 245 2 1,530 620 1,809 1,584 414 946 502 Sub Total 245 2 1,530 620 1,809 1,584 414 946 502 Mazar 0 8 1,102 22 1,722 1,010 817 127 830 North Faryab 0 59 278 0 676 198 150 0 49 Sub Total 0 67 1,380 22 2,398 1,208 967 127 879 Helmand 0 0 100 121 121 71 100 27 South Nimruz 0 0 13 0 0 0 5 0 5 Kandahar 0 0 818 67 1,106 1,118 566 325 389 Sub Total 0 0 931 67 1,227 1,239 642 425 421 Grand Total 1,056 130 9,653 1,343 16,505 10,768 7,003 6,512 4,092