The World Bank Report No: ISR15830
Implementation Status & Results Argentina Urban Transport in Metropolitan Areas (P095485)
Operation Name: Urban Transport in Metropolitan Areas (P095485) Project Stage: Implementation Seq.No: 9 Status: ARCHIVED Archive Date: 28-Oct-2014 Country: Argentina Approval FY: 2010
Public Disclosure Authorized Product Line:IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Adaptable Program Loan Implementing Agency(ies): Buenos Aires Urban Transport Project Implementing Unit Key Dates Board Approval Date 20-Oct-2009 Original Closing Date 29-Feb-2016 Planned Mid Term Review Date 04-Nov-2013 Last Archived ISR Date 18-Feb-2014 Public Disclosure Copy Effectiveness Date 26-Nov-2010 Revised Closing Date 29-Feb-2016 Actual Mid Term Review Date 16-Dec-2013
Project Development Objectives Project Development Objective (from Project Appraisal Document) The overall development objective of the program is to improve the quality and sustainability of urban transport systems in Argentine Metropolitan Areas, through the improvement of sectoral decision making frameworks and by giving priority to public transport modes in the urban transport sector. The project (APL1) development objectives contribute to the overall program development objective by: (i) supporting the design and creation of a multijurisdictional Metropolitan Transport Agency for the Buenos Aires Metropolitan Area (AMBA); (ii) strengthening the institutional capacity of the transport authorities in decision making, planning, priority setting, and resource allocation in urban transport; (iii) improving the quality and performance of urban transport infrastructure and/or services in medium size Metropolitan Areas; Public Disclosure Authorized and (iv) improving the physical integration and access to public transport networks in the Buenos Aires Metropolitan Area. Has the Project Development Objective been changed since Board Approval of the Project?
Yes No
Component(s)
Component Name Component Cost Creation of the MTA 17.61 Urban Transport Improvements in Medium Size Metropolitan Areas 24.46 Public Transport Access and Modal Integration in AMBA 99.28 Sectoral Training 2.50 Project Management 5.77 Public Disclosure Authorized Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Unsatisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Satisfactory Public Disclosure Copy Overall Risk Rating High Substantial
Page 1 of 9 Public Disclosure Authorized The World Bank Report No: ISR15830
Implementation Status Overview The loan has been effective since November 2010 and has disbursed USD47.6 or 32% as of September 2014. The project was restructured in August 2014. The level 2 restructuring of the project resulted in: (i) a reallocation of funds within the components to allow the execution of selected high priority investments for urban transport in the metropolitan areas; (ii) a formal transfer of the implementing unit to the Ministry of the Interior and Transport; (iii) modification of the key indicators for the Project; and (iv) modification of certain Project activities. The restructured project is now focused primarily on three public transport investments under preparation: a BRT project in greater Buenos Aires with proposed works in the municipalities of La Matanza and the city of Buenos Aires; segregated lanes projects in the municipalities of Santa Fe and Rosario. The project is also financing technical assistance to strengthen planning and data platforms for urban mobility planning and management in medium-sized Argentine cities. The project is expected to achieve its development objectives and be complete by the Loan closing date in February 2016.
Locations Country First Administrative Division Location Planned Actual
Public Disclosure Copy Argentina Not Entered Partido de Zárate
Argentina Not Entered Partido de Vicente López
Argentina Not Entered Partido de Tres de Febrero
Argentina Not Entered Partido de Tigre
Argentina Not Entered Partido de San Vicente
Argentina Not Entered Partido de San Isidro
Argentina Not Entered Partido de San Fernando
Argentina Not Entered Resistencia
Not Entered Not Entered Resistencia ✔ ✔
Argentina Not Entered Partido de Quilmes
Argentina Not Entered Posadas
Not Entered Not Entered Posadas ✔ ✔
Argentina Not Entered Partido de Pilar
Argentina Not Entered Partido de Morón
Argentina Not Entered Partido de Moreno
Argentina Not Entered Esteban Echeverría
Not Entered Not Entered Esteban Echeverría ✔ ✔
Public Disclosure Copy Argentina Not Entered Partido de Merlo
Page 2 of 9 The World Bank Report No: ISR15830
Country First Administrative Division Location Planned Actual Argentina Not Entered Partido de Mercedes
Argentina Not Entered Partido de Matanza
Argentina Not Entered Partido de Marcos Paz
Argentina Not Entered Partido de Luján
Argentina Not Entered Partido de Lomas de Zamora
Argentina Not Entered Partido de Lobos
Public Disclosure Copy Argentina Not Entered Partido de La Plata
Argentina Not Entered Partido de Lanús
Argentina Not Entered Partido de José C. Paz
Argentina Not Entered Departamento de Ituzaingó
Argentina Not Entered Hurlingham
Not Entered Not Entered Hurlingham ✔
Argentina Not Entered Partido de General San Martín
Argentina Not Entered Partido de General Rodríguez
Argentina Not Entered Partido de General Las Heras
Argentina Not Entered Partido de Florencio Varela
Argentina Not Entered Ezeiza
Argentina Not Entered Partido de Exaltación de la Cruz
Argentina Not Entered Partido de Esteban Echeverría
Argentina Not Entered Partido de Escobar
Argentina Not Entered Partido de Ensenada
Argentina Not Entered Partido de Canuelas
Argentina Not Entered Partido de Campana
Public Disclosure Copy Argentina Not Entered Buenos Aires
Not Entered Not Entered Buenos Aires ✔ ✔
Page 3 of 9 The World Bank Report No: ISR15830
Argentina Not Entered Partido de Brandsen
Argentina Not Entered Partido de Berisso
Argentina Not Entered Partido de Berazategui
Argentina Not Entered Partido de Avellaneda
Argentina Not Entered Partido de Almirante Brown
Not Entered Not Entered Partido de Almirante Brown ✔ ✔
Argentina Not Entered Guernica Public Disclosure Copy Argentina Not Entered Santa Fe de la Vera Cruz
Not Entered Not Entered Santa Fe de la Vera Cruz ✔ ✔
Argentina Not Entered San Miguel de Tucumán
Not Entered Not Entered San Miguel de Tucumán ✔ ✔
Argentina Not Entered Rosario
Not Entered Not Entered Rosario ✔ ✔
Argentina Not Entered Paraná
Argentina Not Entered Mendoza
Not Entered Not Entered Mendoza ✔ ✔
Argentina Not Entered Córdoba
Not Entered Not Entered Córdoba ✔ ✔
Argentina Not Entered Partido de Malvinas Argentinas
Argentina Not Entered Partido de San Miguel
Results
Project Development Objective Indicators Public Disclosure Copy
Page 4 of 9 The World Bank Report No: ISR15830
Indicator Name Core Unit of Measure Baseline Current End Target Existence of a legal agreement for creating the Yes/No Value No Yes Yes AMT, signed inter-jurisdictionally. Date 20-Oct-2009 15-Aug-2014 29-Feb-2016 Comments The agreement was signed on October 3, 2012 and legally ratified by the City by Decree No. 513 on October 23, 2012, the Province byDecree No. 490, on July 26, 2013, and the National Government on August 14
Public Disclosure Copy 2014 under Decree No. 1359. Produce transport planning instruments based Number Value 0.00 2.00 3.00 on systematic data collection such as: Urban Date 20-Oct-2009 15-Aug-2014 29-Feb-2016 Transport Planning Model, Transportation Master Plan, and/or Urban Transport Center or Comments A master plan for Rosario and Observatory. The Planning document "five- year transport plan" was elaborated under the framework of the AMT. A MoUwas signed on August, 2014 by 4 National Universities to create a consortium for developing a Transport Integrated Information System. The Urban Transport Model for the AMBA is on its final stage. Existence of a portfolio of projects with Number Value 0.00 4.00 6.00 feasibility studies or detailed designs for the Date 20-Oct-2009 15-Aug-2014 29-Feb-2016 implementation of projects in Metropolitan Areas of Argentina. Comments Detailed designs for two transfer centers in Florencio Varela and Pilar have been developed; the detail design for the Barrio 11 deMarzo upgrade in Tucuman (pavement and drainage) is finished; the final design for a BRT in Posadas is in its final revision.
Public Disclosure Copy New portfolio includes projects in the cities of Salta,
Page 5 of 9 The World Bank Report No: ISR15830
Tucumán, Corrientes, Rosario and Santa Fe. In the AMBA, in addition to the BRT metro3, a feasibility study is planned for the rehabilitation of an disused railroad. Segregated corridor constructed in Argentina’s Percentage Value 0.00 0.00 -10.00 medium size Metropolitan Areas that provides Date 20-Oct-2009 15-Aug-2014 29-Feb-2016 a 10% reduction in generalized cost of travel. Comments Rosario & Santa Fe are finalizing detail designs and bidding documents for the Public Disclosure Copy construction of segregated bus lanes. Improved mobility in the RN3 corridor –BRT R3 Percentage Value 0.00 0.00 -10.00 Juan Manuel de Rosas– which provides at Date 20-Oct-2009 15-Aug-2014 29-Feb-2016 least a 10% reduction in generalized cost of travel. Comments Based on the ambitious calendar: the documents are expected to be ready by November 2014, in order to the civil works to start in February 2015, and the service start operating in September 2015.
Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Evidence of AMT performance, such as: Yes/No Value No Yes Yes creating a project with inter-jurisdictional Date 20-Oct-2009 15-Aug-2014 29-Feb-2016 participation and/or inter-jurisdictional agreements on specific transport issues. Comments A political inter-jurisdictional agreement was reached which allowed for the extension of the Illia Highway in the CABA and also, the technical specialist of three jurisdictions defined an inter- jurisdictional project (BRT) connecting La Matanza and the center of Buenos Aires. Public Disclosure Copy
Page 6 of 9 The World Bank Report No: ISR15830
Existence of a valid statute for the internal Yes/No Value No Yes Yes organization of the AMT and appointed Date 20-Oct-2009 15-Aug-2014 29-Feb-2016 representatives for each jurisdiction. Comments The ATM is chaired by a representative of the City, one of the province and one of the National Government. Statute for internal organization is under discussion. Number of minutes of the AMT meetings per Number Value 0.00 2.00 3.00 year. Date 20-Oct-2009 15-Aug-2014 29-Feb-2016 Comments Two formal meetings were Public Disclosure Copy organized on the first semester of the year. Number of Metropolitan Areas with updated Number Value 0.00 5.00 6.00 OD Home Mobility Surveys. Date 20-Oct-2009 15-Aug-2014 29-Feb-2016 Comments Home Mobility Surveys have been produced for: Mendoza, Cordoba, Rosario, Posadas, y Tucumán. Kilometers of segregated bus lanes Kilometers Value 0.00 0.00 2.50 constructed in Metropolitan Areas of Argentina. Date 20-Oct-2009 15-Aug-2014 29-Feb-2016 Comments Rosario is working on the detail designs and bidding documents for the construction of the first phase of the segregated bus lanes. Kilometers of segregated bus lanes Kilometers Value 0.00 0.00 10.00 constructed in the AMBA. Date 20-Oct-2009 15-Aug-2014 29-Feb-2016 Comments Based on the ambitious calendar: the documents are expected to be ready by November 2014, in order to the civil works to start in February 2015, and the service start operating in September 2015. Improvement of access conditions in trains Percentage Value 0.00 100.00 100.00 stations in AMBA Date 20-Oct-2009 15-Aug-2014 29-Feb-2016 Public Disclosure Copy Comments 28 interventions in 21 Municipalities were
Page 7 of 9 The World Bank Report No: ISR15830
constructed to improve the surroundings of the suburban rail stations in the AMBA. Post-graduate course in urban transport is Yes/No Value No Yes Yes approved and created by Buenos Aires Date 20-Oct-2009 15-Aug-2014 29-Feb-2016 University Comments Based on the agreement signed with UBA the master's course in urban transport planning started April 2014. The Project financed 20 students. Public Disclosure Copy Data on Financial Performance (as of 08-Sep-2014)
Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P095485 IBRD-77940 Effective 20-Oct-2009 11-Aug-2010 26-Nov-2010 29-Feb-2016 29-Feb-2016
Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P095485 IBRD-77940 Effective USD 150.00 149.68 0.32 51.79 97.89 35.00
Disbursement Graph Public Disclosure Copy
Page 8 of 9 The World Bank Report No: ISR15830
Key Decisions Regarding Implementation No key issues to raise.
Restructuring History Level 2 CD Decision on 19-Aug-2014
Related Projects There are no related projects. Public Disclosure Copy Public Disclosure Copy
Page 9 of 9