Jetpur - Somnath Section of NH-8D

PROJECT STATUS REPORT AS ON 31 May ’14

PHYSICAL PROGRESS OF THE PROJECT

The Progress of the major works carried out at the site in the month of May 2014 is as follows: ROAD WORKS:

Sl. Descriptio Uni Total Cumulative Qty Cumulative % Work No. n t Qty (2 Qty Achieved Achieved Qty Achieved Achieved till 30 April '14 in May '14 till 31 May '14 till 31 May Lane) '14

1 Clearing & Km 246.9 182.39 6.78 189.17 76.62% Grubbing 2 Embankment Km 246.9 176.16 4.18 180.34 73.04% 3 Sub grade Km 246.9 161.78 6.26 168.04 68.06% 4 Granular Sub Km 246.9 157.53 5.13 162.66 65.88% Base 5 Wet Mix Km 246.9 152.79 4.57 157.35 63.73% Macadam 6 Median Kerb Km 246.9 134.93 4.34 139.27 56.41% 7 Dense Km 246.9 145.64 5.30 150.94 61.13% Bituminous Macadam 8 BC Km 246.9 116.91 10.00 126.91 51.40% 9 DLC Cu 5292 1911 535 2446 46.22% m 10 PQC Cu 11996 2670 580 3250 27.09% m

WORK IN PROGRESS

Sl. Uni WIP Qty till 31st May N Description t ‘14 o 1 Embankment Km 8.53 2 Sub grade Km 3.65 3 Granular Sub Base Km 1.25 4 Wet Mix Macadam Km 1.30 5 Median Kerb Km 0.40 6 Dense Bituminous Macadam Km 0.0

4 L a n i n g o f J e t p u r - S o m n a t h S e c t i o n ( K m . 0 . 0 0 0 t o 1 2 7 . 6 0 0 ) o f N H - 8 D i n t h e S t a t e o f G u j a r a t o n D B F O P a t t e r n u n d e r N H D P P h a s e I I I Jetpur - Somnath Section of NH-8D

STRUCTURE WORKS:

Physical Progress status of Structures

Scope as per Balance to S No T ype of Structure C A (No of C ompleted In Progress Start Locations)

1 Hume Pipe C ulverts 32 27 2 3

2 Box / Slab C ulverts 84 55 3 25

3 Minor Bridges 84 75 1 8

4 PUP / C UP 11 7 0 3

5 VUP 5 1 2 2

6 Major Bridges - New 11 11 0 4

7 Major Bridges - W idening 0 0 0

8 RoB 4 0 3 1

9 Fly Over 1 1 0 0

T otal : 232 177 11 46 100% 76% 5% 20%

4 L a n i n g o f J e t p u r - S o m n a t h S e c t i o n ( K m . 0 . 0 0 0 t o 1 2 7 . 6 0 0 ) o f N H - 8 D i n t h e S t a t e o f G u j a r a t o n D B F O P a t t e r n u n d e r N H D P P h a s e I I I Jetpur - Somnath Section of NH-8D

FINANCIAL PROGRESS OF THE PROJECT

The Financial Progress of the major works carried out in the Project till the month of April 2014 is as follows: Cumulativ % Financial Financial Cumulati Cumulativ % % e Financial Financia Progress Progress ve e Financial Financial Financial Progress l for May '14 for May Financial Progress Progress Progress achieved Progres (Planned) '14 Progress till date Planned Achieved till April s (Achieve till date (Achieved) till date till date '14 achieved d) (Planned) till April '14 (crores) % (crores) (crores) (crores) (crores) % % 549.73 56.04% 33.06 25.21 866.38 574.94 88.32% 58.61%

4 L a n i n g o f J e t p u r - S o m n a t h S e c t i o n ( K m . 0 . 0 0 0 t o 1 2 7 . 6 0 0 ) o f N H - 8 D i n t h e S t a t e o f G u j a r a t o n D B F O P a t t e r n u n d e r N H D P P h a s e I I I