PROJECT COMPLETION REPORT (PCR)

A. PROJECT DATA AND KEY DATES

I. BASIC INFORMATION

Project Number Project Name Country (ies) P-NE-IA0-005 Basic Education Enhancement Project Lending Instrument(s) Sector Environmental Classification Loan No. 2100 150007155 Education Category II Grant No. 2100155002002 Original Commitment Amount Amount Percent Disbursed Cancelled1 Disbursed

Loan: UA 10 000 000 UA 547 UA 9 994 422.18 99.94% Grant: UA 2 000 000 469.43 UA 1 458 108.39 72.90% Counterpart contribution: UA 1 330 000

Borrower Government of the Republic of Niger Executing Agency(ies) Education Projects Implementation Office of the Ministry of National Education

Co-financers and other External Partners NA

II. KEY DATES

Project Concept Note Appraisal Report Cleared Board Approval Cleared by Ops. Com. NA NA NA

Restructuring(s) NA

1 The balance amounts to be cancelled are UA 541 891.61 for the grant and UA 5 577.82 for the loan. 1

Original Date Actual Date Difference in months MM/DD/YY MM/DD/YY

EFFECTIVENESS 06/2004 04/05/2004 -1

MID-TERM REVIEW July 2006 Not conducted CLOSING 31/12/2009 31/03/2011 15

III. RATINGS SUMMARY

CRITERIA SUB -CRITERIA RATING 3 Achievement of Outputs 3 Achievement of Outcomes PROJECT OUTCOME 3 Timeliness

OVERALL PROJECT OUTCOME 3

3 Design and Readiness 3 BANK PERFORMANCE Supervision

OVERALL BANK PERFORMANCE 3

3 Design and Readiness

BORROWER 3 Implementation PERFORMANCE OVERALL BORROWER PERFORMANCE 3

IV. RESPONSIBLE BANK STAFF

POSITIONS AT APPROVAL AT COMPLETION NA J. K. LITSE Regional Director Z. EL BAKRI A. SOUCAT Sector Director T. P. SEYA B. SAVADOGO Sector Manager J. E. PORGO S. ILBOUDO Task Manager S. ILBOUDO PCR Team Leader S. DIAWARA ; I. ADAMOU PCR Team Members

2

B. PROJECT CONTEXT Summarize the rationale for Bank assistance. State:

- what development challenge the project addresses, - the Borrower's overall strategy for addressing it, - Bank activities in this country (ies) and sector over the past year and how they performed, and - ongoing Bank and other externally financed activities that complement, overlap with or relate to this project.

Please cite relevant sources. Comment on the strength and coherence of the rationale.

[300 words maximum. Any additional narrative about the project's origins and history, if needed, must be placed in Annex 6: Project Narrative]

The development challenge of this project is the implementation of the Ten-year Basic Education Development Programme (PDDE) for 2003-2013. With the support of technical and financial partners (TFP), the PDDE aims to: (i) accelerate school enrolment and adapt supply to demand so as to reducing disparities (region, area and gender); (ii) promote non-formal education; (iii) strengthen and develop the institutional capacities of Ministries; and (iv) strengthen and develop vocational and technical training. To that end, the Government adopted a strategy with the priority to improve access and quality in formal and non-formal basic education. The Basic Education Enhancement Project is in line with the first three objectives of the PDDE.

The Bank is financing four operations in the agricultural sector: Invasive Aquatic Weeds – Niger, Kandadji Programme, Water Development Project, Diffa Agro-Pastoral Development Project; one in the multi-sector (Decentralization Support Project); two in the transport sector (Tibiri-Dakoro and Madaoua-B Road Project, Dori-Téra Road Project); and one in the water sector (Rural Drinking Water Supply and Sanitation Project in three regions).

In December 2010, the Bank approved a budget support and an education and vocational and technical training development project. According to the September 2010 portfolio review report, the overall performance is improving steadily and stands at 2.3.

Operations by other multilateral (IDA, EDF, IDB, UNESCO) and bilateral partners in the education sector complement those of the Bank.

3

C. PROJECT OBJECTIVES AND LOGICAL FRAMEWORK

1. State the Project Development Objective(s) (as set out in the appraisal report) 1. Overall Goal: Contribute to PDDE implementation 2. Specific Objectives:

- Broaden access and strengthen equity and the quality of cycles 1 and 2 of basic education; - Improve school health and intensify STI/HIV/AIDS control; - Strengthen the institutional capacities of basic education. 2. Describe the major project components and indicate how each will contribute to achieving the Project Development Objective(s). COMPONENT 1: Improvement of access and quality in Cycles 1 and 2 of Basic education This component seeks to increase the intake capacity of formal education in four project intervention regions (Tillabéry, , Zinder and Maradi) and develop human potential by organizing training sessions for teachers, school management committee members, laboratory technicians and inspectors. COMPONENT 2: Support for girls’ education and literacy for women This component seeks to contribute to the development of non-formal education by increasing women’s adult literacy rate and promoting girls’ enrolment in schools. COMPONENT 3 : Improvement of health and STI/HIV/AIDS control in schools This component seeks to help the Government develop a school health strategy so as to adopt a school health policy; as well as to provide resources to cover the drug costs of all HIV-positive teachers in the project area.

COMPONENT 4 : Project management This component provides support to the Education Projects Implementation Office (BEPE) 3. Provide a brief assessment (up to two sentences) of the project objectives along the following dimensions. Insert a working score, using the scoring scale provided in Appendix 1. PROJECT OBJECTIVES WORKING ASSESSMENT DIMENSIONS SCORE The objectives are relevant because they are a) Relevant to the country's consistent with the government’s education RELEVANT development 4 policy through the PDDE strategy and priorities priorities. b) Objectives could in These objectives are deemed achievable principle be achieved considering that 98.80% of the planned ACHIEVABLE with the project inputs and activities have been carried out. However, the 3 in the expected time frames seem inadequate. timeframe c) Consistent with the The objectives are consistent with the Bank’s Bank's country or regional national education strategy, namely develop 4 strategy human resources (2002-2004 CSP). CONSISTENT d) Consistent with the The objectives are consistent with the Bank Bank's corporate Group’s education and training policy. 4 priorities

4

4. Lay out the log. frame. If a log. frame does not exist, complete the table below, indicating the overall project development objective, the major components of the project, the major activities of each component and their expected outputs, outcomes, and indicators for measuring the achievement of outcomes. Add additional rows for components, activities, outputs or outcomes, if needed. EXPECTED INDICATORS TO BE COMPONENTS ACTIVITIES OUTPUTS OUTCOMES MEASURED Component 1: Basic Cycle 1 Improvement of access and quality in cycles 1 Activity 1: Construction, and 2 of basic Output 1: 300 rehabilitation education classrooms and equipment constructed 3 560 additional of school and equipped pupils are enrolled Number of additional infrastructure each year in basic pupils enrolled in the four in cycle 1 of the regions cycles 1 and 2 project area Output 2: 15 of basic school education canteens

constructed

Improvement of Regularity of pedagogic Output 3: 35 pedagogic supervision pedagogic supervision in the sectors project area constructed and equipped

Basic Cycle 2

Output 1: 8 1 200 additional Number of additional

new general pupils are enrolled pupils enrolled in the four

education each year in Basic regions

colleges Cycle 2 of the

(GEC) project area

constructed

and equipped

Output 2: 15 10-point increase in laboratories the success rate of Success rate of PC and are PC and ELS pupils ELS pupils rehabilitated of the project regions Activity 2: Basic Cycle 1 Strengthening Output 1: 2 Better planning Existence in the DEP of a the senior staff and management team with skills in these institutional trained in of the system domains capacities of education basic planning, 2 in education engineering, 2 in learning evaluation

5

Output 2: 3 500 Building school Familiarization of SMC School management members with proper Management capacity school management Committee principles (SMC) members trained in the management of their committees Basic Cycle 2 Output 1: 25 10-point increase Success rate of Physics, laboratory in the success rate Chemistry and ELS technicians, 24 of PC and ELS pupils inspectors, pupils of the 500 PC and project regions ELS teachers retrained. Component 2: Activity 1: 60 PECs 60 PECs Women’s literacy rate Support for girls’ Construction constructed constructed and education and literacy and equipment and equipped equipped for women of permanent education centres (PEC)

Activity 2: 5 400 women Women’s taught to read literacy and write in the project area Activity 3: Promotion of girls’ The girls’ enrolment rate Procurement 10 000 school enrolment in Basic in Basic Cycle 2 in the of school kits kits procured Cycle 2 project area for the most for underprivilege underprivilege d GEC- d GEC girls enrolled girls Activity 1: Output 1: A Existence of a School health system put Conduct a school health school health in place and school school health strategy study strategy medical policy strategy study is conducted. implemented Activity 2: Output 2: The trained Effective school health Training of 6248 head- personnel teach teaching head-teachers teachers and school health in Component 3: and teachers 5975 teachers their schools. Improvement of health in school of basic cycle and STI/HIV/AIDS health 1 received control in schools school health training. Output 3: Adult population Percentage of the Activity 3: School health sensitized on sensitized adult STI/HIV/AID and school health and population S control in STI/HIV/AID STI/HIV/AIDS schools. S information and 6

sensitization campaigns are conducted Output 4: The 100 HIV- Number of HIV-positive Medical positive teachers teachers under ARV coverage of are under ARV treatment HIV-positive treatment. teachers. 5. For each dimension of the log. frame, provide a brief assessment (up to two sentences) of the extent to which the log. frame achieved the following. Insert a working score, using the scoring scale provided in Appendix 1. If no log. frame exists, score this section as a 1 (one). WORKING LOG. FRAME DIMENSIONS ASSESSMENT SCORE a) Presents a The manner in which the project was logical causal designed, structured and arranged is chain for achieving deemed satisfactory, because it follows a LOGICAL 3 the project logical causal chain for achieving project development development objectives objectives b) Expresses The logical framework expresses objectives and objectives and indicators (outcomes) in a MEASURABLE outcomes in a way way that is measurable and quantifiable 3 that is measurable with means of verification. and quantifiable c) States the risks Risks and key assumptions were identified THOROUGH and key and mitigation measures proposed at 3 assumptions project design.

7

D. OUTPUTS AND OUTCOMES

I. ACHIEVEMENT OF OUTPUTS

In the table below, assess the achievement of actual vs. expected outputs for each major activity. Import the expected outputs from the log. frame in Section C. Score the extent to which the expected outputs were achieved. Weight the scores by the activities' approximate share of project costs. Weighted scores are auto-calculated by the computer. The overall output score must be calculated as the sum of the weighted scores. Override the calculated score, if desired, and provide justification. Share of Project Costs Weighted MAJOR ACTIVITIES Working in percentage Score Score (as stated in

Expected Outputs Actual Outputs Appraisal Report) 300 classrooms, 35 300 classrooms, 35 pedagogic sectors, 15 pedagogic sectors, 15 school canteens school canteens 1.17 4 29.38 constructed and constructed and equipped equipped 8 new GECs 7 new GECs constructed and 15 constructed and 15 laboratories laboratories 3 34.00 1.02 rehabilitated and rehabilitated and equipped equipped 60 PECs 49 PECs constructed/equipped constructed/equipped 3 4.00 0.12 and 5400 women taught and 5 299 women to read and write taught to read and write 2 senior staff trained in 2 senior staff trained in education planning, 2 in education planning, 2 4 0.41 0.05 engineering, 2 in in engineering, 2 in learning evaluation learning evaluation 3 500 SMC members 3 986 SMC members trained in the trained in the 4 3.76 0.15 management of their management of their committees committees 25 laboratory 25 laboratory technicians, 24 technicians, 24 4 2.29 0.09 inspectors, 500 PC and inspectors, 525 PC and ELS teachers retrained ELS teachers retrained A school health A school health improvement and improvement and HIV/AIDS control HIV/AIDS control 3 0.08 0.00 strategy adopted strategy study developed STI/HIV/AIDS-related A study on issues integrated into STI/HIV/AIDS-related 3 0.08 0.00 basic cycles 1 and 2 issues conducted

8

About 6 248 head- 7 007 head-teachers teachers and 5 975 and principals, 6 980 teachers of Basic Cycle PTA members and 100 3 1.13 0.00 1 received school health focal points received training training School health and 72 radio programmes STI/HIV/AIDS and 72 TV programmes information and produced 4 0.7 0.06 sensitization campaigns through radio and TV programmes About one hundred ARV drugs were HIV-positive teachers procured and made 4 2.35 0.75 identified and their available to medical costs covered beneficiaries OVERALL OUTPUT SCORE 3.4 [Score is calculated as the sum of weighted scores]

Check here to override the calculated score

Provide justification for over-riding the calculated score

Insert the new score or re-enter the calculated score 3.4

II. ACHIEVEMENT OF OUTCOMES

1. Using available monitoring data, assess the achievement of expected outcomes. Import the expected outcomes from the log. frame in Section C. Score the extent to which the expected outcomes were achieved. The overall outcome score must be calculated as an average of the working scores. Override the calculated score, if desired, and provide justification. OUTCOMES Working Expected Actual Score 3 560 additional pupils enrolled each year The number of additional pupils enrolled in basic cycle 1 of the project area per year in basic cycle 1 of the project 4 area rose from 174 974 in 2004-2005 to 348 106 in 2009-2010. Regular pedagogic supervision in the The setting up of 35 pedagogic sectors has project area contributed to regular pedagogic 3 supervision in the project area 1 200 additional pupils are enrolled each In 2010, 2 528 additional pupils were year in basic cycle 2 of the project area enrolled in basic cycle 2 of the project area. The new infrastructure created such 4 interest that grass hut classrooms were built within GECs; permanent classrooms are occupied in a rotational manner. 10-point increase in the success rate of PC Not yet available in terms of completion and ELS pupils of the project area of construction works of laboratories and Not their operation. This outcome will only be available measured in the coming years. Existence in the DEP of a team with skills The capacities of MEB’s DEP were in planning, training engineering and strengthened with the availability of senior 3 pedagogic evaluation staff trained in planning, training engineering and pedagogic evaluation 9

All SMC members and most PTA SMC members and PTA members were members familiarized with proper school familiarized with proper management management principles principles. However, with the replacements, measures must be taken in 3 the country for these training sessions to be provided at least every two years (the modules used are available). Increase in women’s adult literacy rate in Adult literacy rates have increased from the project area 20% in 2000 to 29% in 2008, with that of 3 women rising from 11 % to 17.1 %. 50 % of the adult population sensitized on The 72 radio programmes and 72 TV school health and STI/HIV/AIDS programmes produced covered the entire Not country; however, no specific study can available determine the adult population percentage sensitized. School health education in the project area 7 007 principals and head-teachers, and the 100 school health focal points 3 contribute to school health education in the project area. OVERALL OUTCOME SCORE 3.4 [Score is calculated as an average of the working scores] Check here to override the calculated score

Provide justification for over-riding the calculated score

Insert the new score or re-enter the calculated score 3.4

2. Additional outcomes . Comment on the project's additional outcomes not captured in the log. frame, including cross-cutting issues (e.g. gender). The project improved the school environment and put in place better learning conditions. Indeed, the grass-hut classrooms in which pupils sat on the bare floor, and without latrines on the school campus, were replaced by spacious and equipped classrooms, with latrines for pupils (having separate sections for girls and boys) and teachers. An office/store for head-teachers helps them to perform their duties under better conditions. With their infrastructure and equipment, the schools and GECs constructed by the project generated enthusiasm for parents who all want to enroll their children there, as well as teachers who want to work there. This enthusiasm has led to increased demand such that grass-hut classrooms have been constructed to receive the additional influx. Management of schools with greater involvement of parents through SMCs has improved: visibility, increased confidence, availability, quick problem-solving, etc.). Improvement of gender equity, particularly for basic cycle 1. At the environmental level, the stakeholders were sensitized on tree planting on the school campus to improve the living environment and contribute to the fight against desertification. 3. Risks to sustained achievement of outcomes. State the factors that affect, or could affect, the long-run or sustained achievement of project outcomes. Indicate if any new activity or institutional change is recommended to help sustain outcomes. The analysis could draw upon the sensitivity analysis in Annex 3. Inadequate budget resources for infrastructure maintenance and replacement of laboratory products taking into account the other needs of the sector, and the intense demand pressure, could lead to their rapid deterioration. Sensitization of beneficiaries (pupils, teachers, administration) and effective involvement of parents in proper infrastructure and equipment use and routine maintenance are necessary. The Ministry should also provide the laboratory products needed for continuous operation and continuing training of teachers. A public infrastructure maintenance strategy, including that of education, should be developed.

10

E. PROJECT DESIGN AND READINESS FOR IMPLEMENTATION

1. State the extent to which the Bank and the Borrower ensured the project was commensurate with the Borrower’s capacity to implement by designing the project appropriately and by putting in place the necessary implementation arrangements. Consider all major design aspects, such as extent to which project design took into account lessons learned from previous PCRs in the sector or the country (please cite key PCRs); whether the project was informed by robust analytical work (please cite key documents); how well Bank and Borrower assessed the capacity of the implementing agencies and/or Project Implementation Unit; scope of consultations and partnerships; economic rationale of project; and provisions made for technical assistance.

[250 words maximum. Any additional narrative about implementation should be included at Annex 6: Project Narrative]

The project was formulated following discussions that involved the various stakeholders of Niger’s education sector (public authorities, direct beneficiaries, parents, civil society and NGOs), as well as the TFPs organized within the Partnership Framework. Exchanges within this partnership framework helped to coordinate the proposed support so as to avoid duplication and maximize the chances of achieving the objectives pursued. The project is the continuation of Education Project I, with which it shares components and a similar objective, and which was implemented satisfactorily.

Lessons have been learnt from this project, especially as concerns effectiveness conditions and those preceding the first disbursement that were reduced to the essential, so as to guarantee project performance. The project is implemented by the Education Projects Implementation Office (BEPE), which took part in its design and which has acquired experience from previous project management. Indeed, after the sanction period which retarded project implementation, BEPE was able to take appropriate measures for project implementation, and prepared and transmitted activity reports regularly, and has a good knowledge of the Bank’s rules of procedure.

At the economic level, no specific profitability study has been conducted. However, the substantial financial resources injected into the economic fabric through investments in the project activities, as a whole, and payments resulting from them, gave impetus to the commercial activities of small and medium-sized enterprises, hence job creation and the consumption of goods and services. The long- term effect of the various training sessions that were provided and the equipment will improve teaching in terms of quantity and quality, which is an indispensable factor for quality human resource development that the economy needs. In addition, STI/HIV/AIDS sensitization activities seek to reduce their negative impacts on the working population. Sources: Education Project I Completion Report; Ten-Year Education Development Programme (PDDE).

2. For each dimension of project design and readiness for implementation, provide a brief assessment (up to two sentences). Insert a working score, using the scoring scale provided in Appendix 1. PROJECT DESIGN AND READINESS FOR IMPLEMENTATION ASSESSMENT WORKING SCORE DIMENSIONS a) Project complexity is The project is not complex and matched with benefitted from a favourable REALISM 4 country capacity and context in its implementation. political commitment. Despite the political changes 11

that took place, the country’s commitment to the sector through the PDDE remains. It takes into account the RISK b) Project design includes ASSESSMENT analysis of identified risks. The adequate risk 3 AND country’s commitment limited MITIGATION analysis. their impacts c) Project procurement, Bank procurement procedures financial were used, along with the management, monitoring national bid evaluation system. USE OF and/or other Financial management, audit COUNTRY 3 systems are based on and monitoring systems are the SYSTEMS those already in use same as those of other partners. by government and/or other partners.

WORKING SCORE For the following dimensions, provide separate working scores for Bank performance and Borrower performance: Bank Borrower

d) Responsibilities for The roles and responsibilities of project stakeholders were clearly CLARITY 3 3 implementation are defined in project clearly defined. implementation, Project implementation arrangements, procurement arrangements, disbursement e) Necessary methods, budget and implementation implementation schedule were documents (e.g. described in the appraisal report PROCUREMENT specifications, design, and the financing agreements. 3 3 READINESS procurement All procurement of goods, documents) are ready works and services financed by at appraisal. the ADF were done according to the Bank’s relevant rules of procedure and standard bidding documents. f) Monitoring The indicators and the indicators and monitoring plan were adopted MONITORING monitoring plan were and implemented 3 3 READINESS agreed upon before project launch. Project evaluation and the data h) Baseline data are used came from the PDDE BASELINE available or are being report, statistical yearbooks of 3 3 DATA collected during the Ministries in charge of project design. Education, and the PRSP.

12

F. IMPLEMENTATION

1. State the major characteristics of project implementation with reference to: adherence to schedules, quality of construction or other work, performance of consultants, effectiveness of Bank supervision, and effectiveness of Borrower oversight. Assess how well the Bank and the Borrower ensured compliance with safeguards.

[300 words maximum. [Any additional narrative about implementation should be included at Annex 6: Project Narrative.]

The project was implemented behind schedule by 15 months. The delay was due to: i) difficulties faced in recruiting the consulting and control firm; ii) procurement methods not appropriate for certain training and technical assistance activities; and iii) non-compliance with contractual deadlines by certain works contractors. Most of the construction works were executed by the rules of the trade. Globally, the quality of facilities is good and they are in a satisfactory state. The consultants accomplished all the tasks assigned to them in their mission’s Terms of Reference. Their performance is satisfactory. The supervision missions helped to resolve certain problems relating to the procurement of goods, works and services. These missions helped in strengthening project implementation capacity. The government complied with the loan’s effectiveness conditions and other conditions. The counterpart contribution was available during implementation, despite some difficulties; the activity reports were also transmitted to the Bank; the audit of the various financial years was conducted in accordance with the agreements. The project’s planned mid-term review was not conducted; however, that did not affect project implementation activities, insofar as supervision missions and permanent exchanges between the borrower and the Bank helped to sort out the problems faced. 2. Comment on the role of other partners (e.g. donors, NGOs, contractors, etc.). Assess the effectiveness of co-financing arrangements and of donor coordination, if applicable. Niger’s education system is supported by the technical and financial partners involved in the sector, as a supplement to Government efforts. In the PDDE implementation, the various proposed operations are better coordinated than in the past, thus avoiding duplication and promoting synergies. The objective sought by all donors, be they bilateral or multilateral, is education development. However, each partner, while being in line with the programme in general, gives preference to the aspects that fit with its strategic priorities. MEF coordinates all donor operations. As concerns the education sector, there is a partnership framework aimed at bringing together and defining the terms and conditions of work between the TFPs and MEB/A, with a view to achieving the objectives set by the basic education promotion strategy within the PDDE framework. 3. Harmonization. State whether the Bank made explicit efforts to harmonize instruments, systems and/or approaches with other partners. As indicated above, the project was formulated following discussions that involved the various stakeholders in Niger’s education sector (public authorities, direct beneficiaries, civil society and NGOs) as well as TFPs organized within the Partnership Framework. During supervision missions, the Bank maintained dialogue and consultation with the other partners. This consultation, which had to ensure the setting up of a common mechanism for the teaching development programme and vocational and technical training, did not succeed, because of other partners’ deadline constraints.

. For each dimension of project implementation, assess the extent to which the project achieved the following. Provide a brief assessment (up to two sentences) and insert a working score, using the scoring scale provided in Appendix 1.

13

PROJECT IMPLEMENTATION WORKING ASSESSMENT DIMENSIONS SCORE a) Extent of project Difference in 15 months adherence to the months between original closing date. original closing If the number on the date and actual right is: closing date or below 12, "4" is date of 98% TIMELINESS 3 scored disb. rate. between 12.1 to 24, "3" is scored between 24.1 to 36, "2" is scored beyond 36.1, "1" is scored b) Bank complied with: Environmental category II. There were safeguards in the works bidding documents to avoid environmental Environmental problems (erosion, water stagnation, 3 Safeguards vegetation destruction, etc.). The project also provided for the construction of latrines. Fiduciary The Bank ensured compliance with 3 BANK Requirements fiduciary requirements. PERFORMANCE The agreements signed were complied Project Covenants with 4 c) Bank provided Bank supervision was satisfactory in quality supervision in terms of skills mix and practicality of the form of skills mix solutions. However, the mid-term review 3 and practicality of was not conducted. solutions d) Bank provided Bank project management oversight was quality management satisfactory 3 oversight e) Borrower complied with: The construction works executed took Environmental environmental protection into account. 3 Safeguards Generally, the measures taken are satisfactory. Generally, the fiduciary requirements were complied with: charging and Fiduciary justification of expenditure, transmission 3 BORROWER Requirements PERFORMANCE of annual audit reports. The counterpart contribution was disbursed. The conditions and provisions of Project Covenants financing agreements were complied with. 4 f) Borrower was The recommendations made by Bank responsive to Bank supervision missions were taken into 3 supervision findings account. and recommendations

14

The borrower collected and used g) Borrower collected information from the monitoring and and used monitoring supervision process, thus making it 3 information for possible to resolve certain implementation decision making problems

G. COMPLETION

1. IS THE PCR DELIVERED ON A TIMELY BASIS, IN COMPLIANCE WITH BANK POLICY? Date project reached 98% Date PCR was sent to Differenc WORKING SCORE disb. Rate (or closing date if [email protected] e in if the difference is 6 applicable) months months or less, a 4 is scored. If the difference is MM/DD/YY 6.1 or more, a 1 is scored

31/03/2011 4

2. Briefly describe the PCR Process. Describe the Borrower’s and co- financers' involvement in producing the document. Highlight any major differences of opinion concerning the assessments made in this PCR. Describe the team composition and confirm whether a site visit was undertaken. Mention any major collaboration from other development partners. State the extent of field office involvement in producing the report. Indicate whether comments from Peer Reviewers were received on time (provide names and positions of Peer Reviewers).

[150 words maximum] The new PCR format was submitted to the Project Implementation Office during the October 2010 supervision mission; this format was therefore used to initiate a draft report. This report was improved with the 23 April to 8 May 2011 PCR drafting mission, comprising an architect, a procurement specialist and an education specialist. Field visits were made and meetings held with beneficiaries, officials of the Ministry of National Education and the Ministry of Economy and Finance, as well as with the Project Implementation Office team. The various stakeholders, particularly in schools, colleges and Permanent Education Centres appreciated the project’s achievements and were sensitized on measures to be taken to ensure sustainability of these achievements.

The Bank does not have an office in Niger. The comments of peer reviewers were made on time. The peer reviewers were:

. DJOGOYE TALANSADI, Socio-economist; . MASSISSOU NADAB, Education Economist; . MARIA MDACHI, Education Analyst; . ALI EYEGHE, Social Protection Specialist; and . LUCETTE OYOUBI, Socio-economist.

15

H. LESSONS LEARNED

Summarize key lessons for the Bank and the Borrower suggested by the project’s outcomes

[250 words maximum. Any additional narrative about lessons learned, if needed, must be placed in Annex 6: Project Narrative] The main lessons learned from project implementation are as follows:

The involvement of the project execution structure in the various phases of its design ensured better control and implementation of activities;

 As concerns procurement, the inappropriate procurement methods for certain training and technical assistance activities, particularly as regards school health resulted in delays in providing the training;  The continuous drop in the rate of the Unit of Account (UA) created problems of availability of resources for the implementation of all projected activities; certain activities were reduced (7 GECs instead of 8) and others cancelled (organization of medical examinations, development of a national school health policy and equipment for the glassmaking workshop of the National Maintenance Centre (CNM));  The slow disbursement of counterpart contribution resources led to delays especially in the execution of construction works;  The government’s political commitment to the basic education sector and the implementation of Bank monitoring action and recommendations contributed to proper project implementation.

Recommendations : - For the Bank:  Restructure the project, in accordance with the rules, if the borrower cannot cover the financing deficit noted during implementation;  Ensure adoption of procurement methods that are more adapted to the nature of activities, with a view to guaranteeing effective project implementation. - For the government:  Ensure the presence and effective involvement of future project officials in the various phases of its design;  Ensure, as from project preparation, that procurement methods are adapted to the activities so as to ensure rapid and adequate implementation;  Take appropriate measures to disburse needed counterpart contribution resources on time for project activity financing, to avoid implementation delays. Minimize the counterpart contribution, in future, and even finance project activities fully from ADF resources;  Take measures to finance the deficit linked to fluctuations in the UA’s exchange rate or propose the project’s restructuring.

16

I. PROJECT RATINGS SUMMARY All working scores are auto-generated by the computer from the relevant section in the PCR. WORKI CRITERIA SUB-CRITERIA NG SCORE Achievement of outputs 3 PROJECT Achievement of outcomes 3 OUTCOME Timeliness 3 OVERALL PROJECT OUTCOME SCORE 3 Design and Readiness Project Objectives are relevant to country development priorities. 4 Project Objectives could in principle be achieved with the project 3 inputs and in the expected time frame. Project Objectives are consistent with the Bank’s country or 4 regional strategy Project Objectives are consistent with the Bank’s corporate 4 priorities The log frame presents a logical causal chain for achieving the 3 project development objectives. The log frame expresses objectives and outcomes in a way that is 3 measurable and quantifiable. The log frame states the risks and key assumptions. 3 Project complexity is matched with country capacity and political 3 commitment. Project design includes adequate risk analysis. 3 Project procurement, financial management, monitoring and/or other systems are based on those already in use by government 3 BANK and/or other partners. PERFORMANCE Responsibilities for project implementation are clearly defined. 3 Necessary implementation documents (e.g. specifications, design, 3 procurement documents) are ready at appraisal. Monitoring indicators and monitoring plan are agreed upon during 3 design. Baseline data are available or are being collected during design. 3 PROJECT DESIGN AND READINESS SUB-SCORE 3 Supervision: Bank complied with: Environmental Safeguards 3 Fiduciary Requirements 4 Project Covenants 4 Bank provided quality supervision in the form of skills mix 3 provided and practicality of solutions. Bank provided quality management oversight. 3 PCR was delivered on a timely basis 4 SUPERVISION SUB-SCORE 3 OVERALL BANK PERFORMANCE SCORE 3

17

Design and Readiness Responsibilities for project implementation are clearly defined. 3 Necessary implementation documents (e.g. specifications, design, 3 procurement documents) are ready at appraisal. Monitoring indicators and monitoring plan are agreed upon and 3 baseline data are available or are being collected. PROJECT DESIGN AND READINESS SCORE 3 Implementation BORROWER Borrower complied with: PERFORMANCE Environmental Safeguards 3 Fiduciary Requirements 3 Project Covenants 4 Borrower was responsive to Bank supervision findings and 3 recommendations. Borrower collected and used of monitoring information for 3 decision-making. IMPLEMENTATION SUB-SCORE 3 OVERALL BORROWER PERFORMANCE SCORE 3

J. PROCESSING

STEP SIGNATURE AND COMMENTS DATE

Sector Manager Clearance Mr. B. SAVADOGO 18/07/2011

Regional Director Mr. J. K. LITSE 2/08/2011 Clearance

Sector Director Approval Mrs. A. SOUCAT 15/09/2011

18

APPENDIX 1

Scale for Working Scores and Ratings

NOTE EXPLANATION 4 Very Good- Fully achieved with no shortcomings 3 Good- Mostly achieved despite a few shortcomings 2 Fair- Partially achieved. Shortcomings and achievements are roughly balanced 1 Poor- Very limited achievement with extensive shortcomings NA Non Applicable

N.B.: The formulas round up or down for decimal points. Only whole numbers are computed.

i

ANNEX 1

PROJECT NARRATIVE

The project’s sector goal is to contribute to PDDE implementation. The specific objectives are as follows: i) increase access and strengthen equity and quality in basic cycles 1 and 2 education; ii) improve school health and intensify STI/HIV/AIDS control; and iii) strengthen the institutional capacities of basic education. Project activities concern mainly Maradi, Tahoua, Tillabéry and Zinder regions. However, certain activities such as sensitization campaigns through radio and TV programmes concerned the entire country. The project has four (4) components.

Component 1: Access and quality improvement of basic cycles 1 and 2 education

This component covers: i) increase in formal education reception capacities in the above four project intervention regions, and ii) development of human potential by organizing training sessions. Activities planned under this component concern the construction of classrooms, pedagogical sectors, school canteens, laboratories and colleges; the extension of the National Maintenance Centre (CNM) premises; and the procurement of goods for infrastructure to be constructed for the Regional Departments of Secondary and Higher Education (DRESS). Support to school canteens is also planned by the WFP under this institution’s programme in Niger. Activities also concern various training sessions for teachers, COGES members, laboratory technicians and inspectors, with a view to developing human potential.

Component 2: Support for girls’ education and female literacy

This component seeks to contribute to the development of non-formal education, especially increasing the women’s adult literacy rate and promoting girls’ education. Activities planned under this component concern the construction of 60 PECs and 60 latrines; the procurement of various goods; the organization of literacy campaigns and public sensitization campaigns and training of gender teachers.

Component 3: School health improvement and STI/HIV/AIDS control

This component seeks to help the government in developing a school health strategy so as to improve its policy in the area. It also aims to intensify STI/HIV/AIDS control. To achieve these objectives, the project will carry out the following activities: procurement of goods (essential generic drugs for HIV-positive teachers), conduct of studies, organization of training sessions, and STI/HIV/AIDS sensitization. Component 4: Project management

Activities under this component concern the procurement of various goods and services and the operation of the Education Projects Implementation Office (BEPE).

ii

ANNEX 2

PHYSICAL IMPLEMENTATION

PROJECT DESIGN AND IMPLEMENTATION CONTEXT

Project context

The project was designed and developed in 2003 within the context of PDDE implementation. This programme is the single reference framework for the education policy, which gives priority to basic education in its implementation. The project is limited mainly to this sub-sector of the system. It intends, by taking into account the educational system’s constraints, to provide solutions to the problems of access, quality, relevance and equity of basic education, as well as health and STI/HIV/AIDS in schools. According to the Government and the Bank, these issues emerged as the main challenges to be faced by basic education in Niger over the next decade. The PDDE objectives constitute the essential elements of Niger’s poverty reduction strategy, whose major orientations are consistent with the Bank’s CSP for Niger.

Through this strategy, the Bank intends to contribute to 50% reduction in the number of poor people in the country by 2015, mainly by broadening access by poor people to quality social services, in which basic education occupies a prominent place. The discussions which led to project definition also concerned other stakeholders in the education sector, organized within a Partnership Framework. Indeed, support was discussed and validated with the other members of this structure, namely the WFP, the UNDP, the World Bank, the IDB, the EU and bilateral cooperation agencies active in Niger (especially Canada, France, Germany and Switzerland). Exchanges within the Partnership Framework also helped to coordinate the envisaged support so as to avoid duplication and maximize the chances of achieving the objectives pursued. Just like the other TFPs, the Bank’s intervention is based on a programme approach, but with its own procedures. Consultations between the Bank and the WFP within the Partnership Framework made it possible for the WFP to orientate its basic education support programme, as much as possible, within a parallel action framework in favour of schools retained by the project.

ACTIVITIES TO BE FINALIZED

These mainly are: (i) the completion of construction works of eleven (11) PECs executed up to 90% and whose contract was terminated; and (ii) the construction of Sakoira GEC, the rehabilitation of Téra SEC, Tillabery GEC 1, Filingué GEC and Ouallam GEC laboratories, the contractor not having completed works by 31 March 2011.

iii

ANNEX 3

PROJECT DEVELOPMENT IMPACT

 Achievement of Development Objectives

- Economic impact: Substantial resources were injected into Niger’s economic fabric through the investments made. The private sector benefitted very much from it, particularly through conduct of architectural and technical studies, execution of construction works, and procurement of goods. Jobs were created, and goods and services consumed, without mentioning the long-term effect of the human investment made through education and training of beneficiaries. Small and medium- sized enterprises created jobs subsequent to the contracts that they obtained from the project.

- Social impact: Through the various activities, the project has contributed significantly to poverty reduction. It has therefore contributed to the achievement of the PRSP objectives, especially increasing access to social services and improving their quality. With the construction of 300 new classrooms, 7 GECs and 49 PECs, the project has extended intake capacities with about 12 000 additional places in basic cycle 1 education, 1 680 in basic cycle 2 and about 4 410 women for literacy campaigns. The project has improved the gross enrolment rate in basic cycle 1 as follows between 2002 and 2010: in Maradi from 40.8% to 75.3%; in Tahoua from 36% to 70.7%; in Zinder from 28.9% to 64.9%; and in Tillabéry from 39% to 68.9 %.

By extending the intake capacity of basic education through the construction of hundreds of new classrooms and school canteens mainly for girls, the project has made a positive contribution to girls’ school attendance and helped to increase their gross enrolment rates (basic cycle 1) in the regions retained.

 Prospects

The good performances obtained in the implementation of the Basic Education Enhancement Project (Education II/ADF Project) open new prospects for continued cooperation between the Government and the African Development Bank Group, especially in the area of National Education where considerable needs remain to be met in terms of improving the access and quality of education and strengthening human and institutional capacities.

iv

ANNEX 4

FINANCIAL EXECUTION

The Bank disbursed an amount of UA 9 994 422.18 for the loan and UA 1 458 108.39 for the grant, representing an amount of UA 11 452 530.57 out of UA 12 000 000; the overall disbursement rate stands therefore at 95.44 %. The balances to be cancelled are UA 541 891.61 for the grant, and UA 5 577.82 for the loan. Accounting audit and management: Since the start of the project in 2004, audits have been conducted and reports transmitted regularly to the Bank.

Table 1 BREAKDOWN OF FINANCING BY CATEGORIES AT APPRAISAL (IN UA)

Expenditure Categories ADF Loan ADF Grant Government Total Category % A Works 4.40 00 1.03 5.43 40.75% B Goods 2.84 0.37 0.07 3 .28 24.60% C Services 2.24 1.63 00 3.88 29.10% D Operating costs 0.51 00 0.23 0.74 5.56% TOTAL 10.00 2.00 1.33 13.33 100.00%

Table 2 ADF DISBURSEMENTS BY EXPENDITURE CATEGORY OF THE LOAN (IN UA)

Expenditure ADF Loan ADF Grant Categories Amount % disbursed Amount % disbursed A Works 4 930 139.81 112. 04% 00 B Goods 2 525 607.99 88.82% 348 673.97 94.24% C Services 1 835 358.31 81.93 % 1 109 434.42 60.45 % D Operating costs 703 316.07 137. 90% 00 TOTAL 9 994 422.18 99.94% 1 458 108.39 72.90%

v

ANNEX 5 MISSIONS UNDERTAKEN BY ADB EXPERTS

N° Mission Period No. of No. of Composition Days Persons 1 Identification 6-27/12/2002 15 - Preparation 25/6 - 12 3 Pierre Thizier SEYA : Division Manager 11/7/2003 OCSD.2 2 Hend MRABET : Architect Souleymane ZERBO : Architect/Consultant Appraisal 25/8 - 5/9/2003 17 3 Pierre Thizier SEYA : Division Manager OCSD.2 3 Hend MRABET : Architect Souleymane ZERBO : Architect/Consultant 4 Supervision 2004 - - 5 Supervision 06- 21/6 / 2005 15 1 ANN Dao SOW : Education Expert Supervision 13- 27/12/ 15 3 Hend MRABET: Architect 6 2005 Nadine ABIOLA : Health Expert (Consultant) IIDE LAMBRECHTS : Architect Supervision 16-30/6/ 2006 15 2 Clotilde BAI : Architect 7 Zoumana KONE : Education Expert (Consultant) 03-17/11/ 2006 15 2 Médjomo Coulibaly : Chief Education Expert 8 Supervision Ismail HADDA : Architect (Consultant) Supervision 20/04-05/ 2007 15 2 Boukary SAVADOGO : Chief Education 9 Expert Makhete CISSE : Senior Architect Supervision 16-30/10/2007 15 2 Boukary SAVADOGO : Chief Education 10 Expert Makhete CISSE : Senior Architect Supervision 12/6-03/2008 21 2 Boukary SAVADOGO : Chief Education 11 Expert Makhete CISSE : Senior Architect Supervision 13/11- 19 1 12 Emmanuel NYIRINKWAYA : Chief Architect 2/12/2008 Supervision 17-28/04/2009 12 2 Emmanuel NYIRINKWAYA : Chief Architect 13 Salamata ILBOUDO : Social Development Specialist Supervision 01-15/2010 15 2 Emmanuel NYIRINKWAYA : Chief Architect 14 KHADIDJA Khoudari : Education Expert Supervision 9-24/10/2010 15 2 Salamata ILBOUDO : Chief Education Analyst 15 Andrée DIOP-DEDRET : Architect (Consultant) Completion 23/04- 15 3 Salamata ILBOUDO : Chief Education Analyst 08/05/2011 Souweye DIAWARA MAIGA : Procurement 16 Specialist Issaka ADAMOU : Architect (Consultant)

vi

ANNEX 6

RATINGS FOR THE LAST SUPERVISION

RATINGS: 3 = Highly Satisfactory, 2 = Satisfactory, 1 = Unsatisfactory, 0 = Highly Unsatisfactory, ‘‘= Not Applicable

RATINGS Preceding report This INDICATORS report 13.11.200 20.10.201 16.04.2009 01.02.2010 23.04.201 8 0 1 A. PROJECT IMPLEMENTATION Compliance with loan conditions precedent to entry 2 2 2 2 2 into force Compliance with General Conditions 2 2 2 2 2 Compliance with Other Conditions 1 1 1 1 1 B. PROCUREMENT PERFORMANCE Procurement of Consultancy Services 3 3 3 3 3 Procurement of Goods and Works 2 3 3 3 3 C. FINANCIAL PERFORMANCE Availability of Foreign Exchange 2 3 3 3 3 Availability of Local Currency 2 2 2 3 2 Disbursement Flows 2 3 3 3 3 Cost Management 2 2 2 2 2 Performance of Co-Financiers 0 0 D. ACTIVITIES AND WORKS Adherence to implementation schedule 1 2 2 2 2 Performance of Consultants or Technical Assistance 3 3 3 3 3 Performance of Contractors 1 3 3 2 2 Performance of Project Management 3 3 3 3 2 E. IMPACT ON DEVELOPMENT Likelihood of achieving development Objectives 2 2 2 2 2 Likelihood that benefits will be realized and 2 2 2 2 2 sustained Likely contribution of the project towards an increase 2 2 2 2 2 in Current Rate of Return 0 0 F. OVERALL PROJECT ASSESSMENT Current Supervision Average 2.00 2.11 2.38 2.11 2.25 Current Trend over time 2.17 RATINGS: 3 = Highly Satisfactory, 2 = Satisfactory, 1 = Unsatisfactory, 0 = Highly Unsatisfactory, ‘‘= Not Applicable

STATUS Implementation Progress (IP) = 2.31 Development Objectives (DO) = 2.00

OVERALL STATUS : NON PROBLEMATIC PROJECT / NON POTENTIALY PROBLEMATIC PROJECT /

JUSTIFICATION OF RATINGS

vii

ANNEX 7

SOURCES OF INFORMATION

Title of documents Source Project Appraisal Report ADF Loan Agreement ADF Grant Protocol Agreement ADF Table of Disbursements (Ledger) BEPE/ADF Quarterly Activity Reports BEPE/ADF Aide-Mémoire of Bank Missions BEPE/ADF Statistical Yearbooks of the Ministries in charge of Education, 2009/2010 Edition MEN

viii

ANNEX 8

SITUATION OF SIGNED CONTRACTS FOR GOODS AND SERVICES AS AT 31 MARCH 2011

No. No. and Dates of Purpose of Contract or Convention Amount Payments Procurement Method Beneficiaries Balance Signature (CFAF) Made 1. SERVICES 01 09/05/2005 Training of laboratory technicians Mutual agreement ENS 19 000 000 19 000 000 0 008/06/MEF/DCF Studies and inspection of construction works of school and literacy Agence AIC 02 35 036 of 20/02/2006 and its infrastructure International short list 319 085 000 284 048 332 668 amendment 03 008/06/MEF/DCF Audit of project accounts, 2005-2006 financial years CGIC Afrique International short list 20 000 000 20 000 000 0 of 20/02/2006 150/07/MEF/DGCF Continuing training design, continuing training restructuring Association PRO-Ed International short list 186 050 000 86 050 000 0 04 of 09/08/2007 support, learning evaluation, teaching material design Development of a school health/hygiene improvement strategy, Association AIRSE 05 125/07/MEF/DGCF study on the STI/HIV/AIDS situation in schools and development International short list 35 850 000 35 850 000 0 of 09/07/2007 of the STI/HIV/AIDS issue in the curriculum 06 Retraining of 24 secondary education inspectors in education IPN 17 September 2007 Mutual agreement 1 250 000 1 250 000 0 administration and management 07 05 October 2007 Training of 500 teachers in gender approach Mutual agreement IPN 4 627 600 4 627 600 0 Retraining of 500 physical sciences and ELS teachers in the

handling of scientific equipment and the development of teaching IPN 14 280 640 14 280 640 0 08 05 October 2007 Mutual agreement aids Retraining of 500 teachers in the development and implementation IPN 09 05 October 2007 5 176 000 5 176 000 0 of education action projects Mutual agreement 10 17 September 2007 Continuing training of college teachers in 50 EUs Mutual agreement IPN 40 432 240 40 432 240 0 Sensitization and social mobilization action on STI/HIV/AIDS in 11 17 September 2007 498 600 498 600 0 schools Mutual agreement DHP/ES Radio and TV sensitization and information programmes on school 12 05 October 2007 13 626 200 13 626 200 0 health and hygiene Mutual agreement DHP/ES Radio and TV sensitization and information programmes on 13 333 800 13 333 800 0 13 05 October 2007 STI/HIV/AIDS in schools Mutual agreement DHP/ES Information/training of 3 500 PTA representatives on the health

05 October 2007 improvement strategy and school hygiene and health action 34 053 170 34 053 170 0 14 Mutual agreement planning DHP/ES Information/training of 3 500 head-teachers on the health Mutual agreement 34 053 170 34 053 170 0 15 05 October 2007 improvement strategy and school hygiene and health action DHP/ES

ix

planning 16 05 October 2007 Functional literacy campaigns for 5 400 women Mutual agreement DGENF 62 339 000 62 339 000 0 Production/binding of teaching aids of training and retraining National shopping Imprimerie EXPRESS 77 701 600 75 246 320 0 17 04 December 2007 workshops Procurement of supplies for training and retraining workshops (Lot National shopping 48 635 464 48 635 464 0 18 04 December 2007 2/ NCB 25 May 2007) Librairie NIGEMAT Procurement of small teaching aids for female literacy (Lot 1/ Ets DIMAS National shopping 26 935 800 26 935 800 0 19 04 December 2007 NCB 25 May 2007) 20 04/08/2005 National language manuals for female literacy Mutual agreement DGENF 13 950 000 13 950 000 0 21 0 January 2008 Girls’ enrolment sensitization campaigns Mutual agreement DPSF 9 222 599 9 222 599 0 22 24 January 2008 Drafting of the EDUII/ADF Project management manual International short list CGIC Afrique 9 000 000 9 000 000 0 Training of SMC board members for their committee EMOCRATIE 2000 23 11 April 2008 International short list 58 519 800 58 519 800 0 administration Audit of project accounts for 2007 to 2009 financial years Cabinet ACSA 08 May 2008 International short list 20 100 000 20 100 000 0 24 Training of 12 MEN senior staff in learning evaluation BIEF SA 0 11 April 2008 International short list 73 195 618 73 195 618 25 126/09/MEF/DGCF of Design and production of an STI/HIV/AIDS image box in schools ANIMAS SUTURA International short list 34 833 750 34 833 750 0 26 26/05/2009 Broadcast of radio and TV sensitization and information

067/09/MEF/DGCF of programmes on health and hygiene, and STI/HIV/AIDS in schools ORTN 35 682 800 35 682 800 0 27 Mutual agreement 09/04/2009 Evaluation of the impact of school canteens on girls’ enrolment in 259/09/MEF/DGCF of 28 nomadic regions International short list SOFRECO Sarl 46 238 409 46 238 409 0 20/07/2009

Reproduction/binding of workshop teaching aids, continuation of 526/09/MEF/DGCF of information/training on the school health and hygiene Mutual agreement Imprimerie EXPRESS 21 909 768 21 909 768 0 29 04/12/2009 improvement strategy 527/09/MEF/DGCF of Procurement of workshop kits, continuation of information/training 30 Mutual agreement 18 514 400 18 514 400 0 04/12/2009 on the school health and hygiene improvement strategy NIGEMAT 526/09/MEF/DGCF of Organization of workshops, continuation of information/training 31 Mutual agreement 58 272 840 58 272 840 0 04/12/2009 on the school health and hygiene improvement strategy DHP/ES 0013/10/MEF/DGCF of Audit of project accounts for the 2010 financial year FICADEX International 32 19/01/2010 + International short list 7 037 500 0 7 037 500 amendment

1 318 876 32 42 074 16 TOTAL SERVICES 1 363 405 768 0 8

x

2. GOODS 0158/05/MEF/DCF Rolling stock CFAO Niger National competitive bidding 164 825 000 164 825 000 0 01 of 09/12/2005 0162/05/MEF/DCF Automated office equipment NIGEMAT National competitive bidding 135 940 625 135 940 625 0 02 of 09/12/2005 0159/05/MEF/DCF Computer hardware BEPE KANF ELECTRONICS National competitive bidding 184 406 000 184 406 000 0 03 of 09/12/2005 0160/05/MEF/DCF Classroom, office, store and educational sector furniture (Lot N°1) 276 337 221 National competitive bidding Hamdallaye Meubles 299 288 750 04 of 09/12/2005 (*) 0 0161/05/MEF/DCF College, PEC and school health office furniture (Lots N°2 & 3) 205 952 758 National competitive bidding 218 775 500 05 of 09/12/2005 Boubacar SIDI (*) 0 0088/MEF/DCF College-type laboratory equipment International competitive 448 397 886 444 810 910 06 of 07/07/2006 bidding ACIA (683 578,17 €) (*) 0 0082/07/MEF/DGCF Generic essential drugs for schools International competitive 139 029 037 139 029 037 IMC 0 07 of 22/05/2007 bidding (211 948,40 €) Procurement of school kits for college girls 0 07 December 2007 National competitive bidding Ets DIMAS 99 719 520 99 719 520 08 Computer hardware for BEPE 0 21 February 2008 Local shopping 29 982 860 29 982 860 09 KANF ELECTRONICS 45/09/MEF/DGCF of Procurement of secondary school manuals International competitive Hachette Livre International 0 313 272 469 282 580 588 (*) 10 30/03/2009 bidding 0014/10/MEF/DGCF of Drugs and medical consumables International competitive 0 91 135 229 65 711 919 (*) 11 19/01/2010 (Lot 1 : Drugs and medical consumables) bidding REALAB PHARMA 0 0013/10/MEF/DGCF of Drugs and medical consumables International competitive 31 682 723 12 CIPLA LTD 30 960 514 (*) 19/01/2010 (Lot 2 : ARVs) bidding (48 300 Euros)

TOTAL GOODS 2 156 455 599 2 060 256 952 42 074 168 3. WORKS 233/08/MEF/DGCF of Construction of 10 PECs in the Bâti-Niger 01 National competitive bidding 77 045 185 74 669 223 0 29/08/2008

231/08/MEF/DGCF of 02 Construction of 12 PECs in National competitive bidding Entreprise ABC 84 829 181 61 115 761 2 307 686 29/08/2008

232/08/MEF/DGCF of Construction of 8 PECs in Tahoua region 03 National competitive bidding 56 114 271 20 496 747 0 29/08/2008 Entreprise Moumouni Iyo 234/08/MEF/DGCF of Construction of 8 PECs in (Lot 4.1) Bâti-Niger 04 National competitive bidding 59 008 878 59 008 878 0 29/08/2008 229/08/MEF/DGCF of Construction of 10 PECs in Tillabéri region 05 National competitive bidding 69 140 484 44 123 203 3 864 959 29/08/2008 Entreprise KARFÉ 235/08/MEF/DGCF of Construction of 10 PECs in Zinder region 06 National competitive bidding 78 393 389 76 492 621 0 29/08/2008 Entreprise EZT 245/08/MEF/DGCF of School infrastructure construction in Konni, Madaoua, Keita and Bouza International competitive 07 274 506 349 274 506 349 0 29/08/2008 Departments bidding Entreprise TIMBO 246/08/MEF/DGCF of School infrastructure construction in Abalack, Tahoua Department, Tahoua Cne, International competitive 08 329 106 340 329 106 340 29/08/2008 Illéla and Tchinta Departments bidding Mohamédine Abdoulkarim 0 253/08/MEF/DGCF of Construction of the Tsernaoua GEC, rehabilitation of Madaoua GEC 1, Bouza International competitive Entreprise DAR ES SALAM 09 314 358 865 273 970 352 29/08/2008 GEC and Keita GEC laboratories bidding 0 254/08/MEF/DGCF of Construction of Badaguichiri GEC and rehabilitation of Tahoua Commune GEC International competitive Entreprise DKO 10 265 922 201 265 922 201 29/08/2008 bidding 0

xi

247/08/MEF/DGCF of School infrastructure construction in Kollo, Say, Fillingué and Ouallam International competitive 11 237 470 728 237 470 728 29/08/2008 Departments bidding Entreprise SOBAFOR 0 248/08/MEF/DGCF of School infrastructure construction in Tillabéri, Tillabéri Cne and Téra Divisions International competitive 12 217 359 396 217 359 396 29/08/2008 bidding Entreprise ENTE 0 255/08/MEF/DGCF of Laboratory rehabilitation in Téra SEC, Tillabéri GEC 1, Fillingué GEC and International competitive 13 313 021 944 193 099 523 3 958 386 29/08/2008 Ouallam GEC bidding Entreprise EGTC 256/08/MEF/DGCF of School infrastructure construction in Guidan Roumji, Madarounfa and Dakoro (Lot International competitive 14 274 100 161 274 100 161 0 29/08/2008 A2) Departments bidding Entreprise MIKA 257/08/MEF/DGCF of School infrastructure construction in Kantché and Magaria Departments International competitive 15 334 067 451 334 067 451 0 29/08/2008 bidding Entreprise ENICO 252/08/MEF/DGCF of School infrastructure construction in Gouré, Tanout and Zinder Council International competitive 16 420 951 538 420 951 538 29/08/2008 Departments bidding Entreprise EZT 0 244/08/MEF/DGCF of Construction of Zinder GEC 8 and rehabilitation of Matameye SEC laboratories International competitive 17 278 770 851 278 770 851 29/08/2008 bidding Entreprise EKO 0 250/08/MEF/DGCF of School infrastructure construction in Aguié, Tessaoua, Mayahi and Maradi Council International competitive 18 235 789 933 235 789 933 29/08/2008 (Lot A1) Departments bidding Entreprise MIKA 0 251/08/MEF/DGCF of Construction of Zinder Council GEC 7 and rehabilitation of Magariadu SEC International competitive 19 286 564 947 286 564 947 29/08/2008 laboratory bidding BATI-NIGER 0 62/09/MEF/DGCF of Construction of Dan Issa GEC, rehabilitation of Madarounfa laboratory and International competitive Entreprise Sani Souley Dan 20 280 764 233 280 764 233 09/04/2009 rehabilitation/extension of Soura Bildi (Lot A4) laboratory bidding GARA 0 63/09/MEF/DGCF of Construction of Zinder Council GEC 9 and rehabilitation of Zinder (Lot D5) SEC International competitive 21 345 427 126 345 427 126 0 09/04/2009 F/A laboratory bidding Entreprise Laoualy Ibrahim 345/10/MEF/DGCF of Completion of construction of Sakoira GEC and rehabilitation of Tillabéry GEC 1, Short list (with 22 11/08/2010 Fillingué GEC and Ouallam GEC (Lot C3) laboratories prequalification) Entreprise ENTE 188 151 544 76 205 843 75 279 677 Completion of construction of 12 PECs in Tahoua region (Lot 2.2) 346/10/MEF/DGCF of Short list (with 23 Entreprise EBIM SARL 54 451 641 18 356 149 3 482 323 11/08/2010 prequalification)

TOTAL WORKS 5 075 316 636 4 678 519 554 88 893 031

GRAND TOTAL 8 595 178 003 8 057 652 826 30 967 199

(*): Takes into account penalties applied on the contract

xii

ANNEX 9

PROCUREMENT PLAN

1. PROCUREMENT PLAN (GOODS)

Various Lots with Procurement Methods Baseline Data Bidding Documents (BD) Pre-Qualification (PQ) Pre-Qualification (PQ) Bidding Period Evaluation of Bids Draft Contract Contract Award Contract Execution and Schedule Publication Reception Date Date of Date of Non- Prior or Plan/ Evaluation Competitive Contract Date Estimated Amount Procurement Pre- or Post- Nation./Reg. Projected Bids BDs Receipt Date of Non- PQ Publication Bids Submission Date of Non- Bids Submission- of Bids Date of Non- Draft Contract Date of Non- Contract Contract Description* Lot Number ASAO*/APQ* Objection to Subsequent Revised/ Report Bidding Amount in Starting Date Completion Date (UNDB) in CFAF Method Qualification Preference (Y/N) Submission Date Date objection Date Date objection Opening Date Evaluation objection Receipt Date Objection Award Date Signature Date Receipt ASAO/APQ Examination Current Reception Date Launching Date CFAF ASAO/APQ Report 1 171 630 000.00 LCB Post-Qualification N Prior Plan 01/01/2005 31/08/2005 01/04/2006 30/04/2006 Procurement of rolling stock Revised LCB 1 16/09/2005 31/05/2005 171 630 000.00 Post-Qualification N Prior 15/07/2005 Current 16/03/2005 02/05/2005 31/05/2005 15/07/2005 02/08/2005 16/09/2005 02/08/2005 16/09/2005 164 825 000.00 29/09/2005 09/11/2005 11/11/2005 24/02/2006

LCB 1 254 800 000.00 Post-Qualification N Prior Plan 01/01/2005 31/08/2005 01/04/2006 30/04/2006 Procurement of computer LCB Revised hardware LCB Prior 1 16/09/2005 31/05/2005 254 800 000.00 Post-Qualification N 15/07/2005 Current 16/03/2005 02/05/2005 31/05/2005 15/07/2005 02/08/2005 16/09/2005 02/08/2005 16/09/2005 184 406 000.00 29/09/2005 09/11/2005 11/11/2005 20/02/2006 date LCB Prior 1 66 500 000.00 Post-Qualification N Plan 01/01/2005 31/08/2005 01/04/2006 30/04/2006 Procurement of LCB Prior automated office Revised equipment LCB Prior 1 16/09/2005 31/05/2005 66 500 000.00 Post-Qualification N 15/07/2005 Current 16/03/2005 02/05/2005 31/05/2005 15/07/2005 02/08/2005 16/09/2005 02/08/2005 16/09/2005 135 940 625.00 29/09/2005 09/11/2005 11/11/2005 15/02/2006

LCB Prior Procurement of primary 1 340 280 000.00 Post-Qualification N Plan 01/01/2005 31/08/2005 01/04/2006 30/04/2006 classroom , store office LCB Prior Revised and educational sector LCB Prior furniture (Lot N°1) 1 16/09/2005 31/05/2005 340 280 000.00 Post-Qualification N 15/07/2005 Current 16/03/2005 02/05/2005 31/05/2005 15/07/2005 02/08/2005 16/09/2005 02/08/2005 16/09/2005 299 288 750.00 29/09/2005 09/11/2005 10/11/2005 16/10/2006

LCB Prior Procurement of college, 1 178 450 000.00 Post-Qualification N Plan 01/01/2005 31/08/2005 01/04/2006 30/04/2006 PEC and School Health LCB Prior Revised Office furniture (Lots LCB Prior N°2 & 3) 1 16/09/2005 31/05/2005 178 450 000.00 Post-Qualification N 15/07/2005 Current 16/03/2005 02/05/2005 31/05/2005 15/07/2005 02/08/2005 16/09/2005 02/08/2005 16/09/2005 218 775 500.00 29/09/2005 09/11/2005 10/11/2005 26/07/2006

Prior 1 21 020 000.00 Mutual agreement Post-Qualification Y Plan 01/10/2006 30/09/2007 Procurement of national Prior Revised language manuals Prior 1 21 020 000.00 Mutual agreement Post-Qualification Y Current 14/06/2005 15/07/2005 13 950 000.00 05/08/2005 04/08/2005 05/08/2005 21/04/2006

Prior 1 828 000 000.00 ICB Post-Qualification N Plan 01/01/2005 31/08/2005 01/04/2006 30/04/2006 Procurement of college- Prior type laboratory Revised equipment ICB Prior 1 16/09/2005 16/06/2005 828 000 000.00 Post-Qualification N 17/08/2005 Current 16/03/2005 09/05/2005 16/06/2005 17/08/2005 06/01/2006 30/01/2006 06/01/2006 30/01/2006 448 397 886.00 02/03/2006 07/06/2006 12/06/2006 14/02/2008

ICB Prior 1 100 000 000.00 Post-Qualification N Plan 01/08/2004 28/02/2005 01/03/2005 30/04/2005 Procurement of generic ICB Prior essential drugs for Revised schools ICB Prior 1 15/02/2006 31/05/2006 100 000 000.00 Post-Qualification N 10/08/2006 Current 06/01/2006 25/04/2006 31/05/2006 10/08/2006 12/10/2006 08/01/2007 12/10/2006 08/01/2007 139 029 037.00 13/03/2007 22/05/2007 28/05/2007 04/01/2008

Prior 1 100 000 000.00 LCB Post-Qualification N Plan 01/03/2005 30/04/2006 01/10/2006 30/09/2007 Procurement of school Prior kits for college girls of Revised project areas Prior 1 12/01/2007 31/01/2007 100 000 000.00 LCB Post-Qualification N 29/03/2007 Actuel 20/09/2006 12/01/2007 31/01/2007 29/03/2007 09/10/2007 12/11/2007 09/10/2007 12/11/2007 99 719 520.00 03/12/2007 07/12/2007 14/12/2007 14/02/2008

ICB Prior 2 289 000 000.00 Post-Qualification N Plan 16/08/2007 31/10/2007 01/04/2006 30/04/2006 Procurement of ICB Prior secondary school Revised manuals ICB Prior 2 06/03/2006 16/08/2007 289 000 000.00 Post-Qualification N 16/10/2007 Current 29/06/2007 12/07/2007 16/08/2007 31/10/2007 06/11/2008 15/12/2008 06/11/2008 15/12/2008 313 272 469.00 20/01/2009 30/03/2009 02/04/2009 24/06/2010 ICB

ICB Prior 1 141 120 000.00 Post-Qualification N Plan 01/08/2004 28/02/2005 01/03/2005 30/04/2005 Procurement of drugs for ICB Prior Revised HIV-positive teachers ICB Prior 2 23/03/2009 03/04/2009 141 120 000.00 Post-Qualification N 18/05/2009 Current 10/03/2009 23/03/2009 03/04/2009 17/07/2009 21/10/2009 11/11/2009 21/10/2009 11/11/2009 91 135 229.00 03/12/2009 19/01/2010 27/01/2010 10/09/2010 ICB

ICB Prior 1 Post-Qualification N Plan 01/08/2004 28/02/2005 01/03/2005 30/04/2005 Procurement of Anti ICB Prior Retro- Virals (ARV) for Revised the HIV-positive ICB Prior 1 23/03/2009 03/04/2009 Post-Qualification N 18/05/2009 Current 10/03/2009 23/03/2009 03/04/2009 17/07/2009 21/10/2009 11/11/2009 21/10/2009 11/11/2009 31 682 723.00 03/12/2009 19/01/2010 27/01/2010 10/09/2010

Prior 1 - 0.00 DCL Post-Qualification N Plan 01/09/2004 31/10/2004 Replacement of BEPE’s Prior Revised computer hardware Prior 1 - 29 982 860.00 DCL Post-Qualification N Current 07/06/2007 17/07/2007 31/10/2007 17/12/2007 26/12/2007 31/01/2008 26/12/2007 31/01/2008 29 982 860.00 28/02/2008 21/02/2008 28/02/2008 10/03/2008

Total Cost Goods 2 349 680 000.00 Plan 0.00 171 630 000.00 Revised 2 035 337 2 349 680 000.00 Current 510.00

ix

2. WORKS

Various Lots with Procurement Baseline Data Bidding Documents (BD) Pre-Qualification (PQ) Pre-Qualification (PQ) Bidding Period Evaluation of Bids Draft Contract Contract Award Contract Execution Methods and Schedule

Reception Date Date of Date of Non- Publication Date Fixed Rate Prior or BDs Date of PQ Evaluation Competitive Bids Date of Lot Estimated Amount Procurement Pre- or Post- Nation./Reg.Preference Projected Bids Plan/ Revised/ Date of Non- of Bids Date of Non- Draft Contract Contract Amount Contract Award Contract Description* ASAO*/APQ* Objection to (UNDB) or Unit Subsequent Receipt Non- Publication BidsDate Report Receipt Bidding Submission- Non- Starting Date Completion Date Number in CFAF Method Qualification (Y/N) Submission Date Current objection Evaluation objection Receipt Date in CFAF Date Signature Date Receipt ASAO/APQ ASAO/APQ Price Examination Date objection Date Date Launching Date Opening Date Objection Report

1 31/082007 50 440 000.00 Unit Price NCB Post Qualification N Prior 16/10/2007 Plan 01/07/2005 30/03/2006 Date 01/04/2006 30/04/2007 Construction of 10 PECs in Maradi region (Lot 1) Revised 31/07/2009 Unit Price NCB 1 31/082007 50 440 000.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/10/2007 11/12/2007 29/01/2008 16/05/2007 10/08/2007 77 045 185,00 16/07/2008 29/08/2008 01/10/2008 17/11/2009

Unit Price NCB 1 31/082007 61 692 000.00 Post Qualification N Prior 16/10/2007 Plan 01/07/2005 30/03/2006 01/04/2006 30/04/2007 Construction of 12 PECs in Unit Price NCB Tahoua region (Lot 2.1) Revised 10/05/2010 Unit Price NCB 1 31/082007 61 692 000.00 Post Qualification N Prior 16/10/2007 Actual 16/05/2007 10/08/2007 17/09/2007 16/10/2007 11/12/2007 29/01/2008 16/05/2007 10/08/2007 84 829 181,00 16/07/2008 29/08/2008 01/10/2008 TERMINATED

Unit Price NCB 1 31/082007 41 128 000.00 Post Qualification N Prior 16/10/2007 Plan 01/07/2005 30/03/2006 01/04/2006 30/04/2007 Construction of 8 PECs in Unit Price NCB Tahoua region (Lot 2.2) Revised 30/06/2009 Unit Price NCB 1 31/082007 41 128 000.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/10/2007 11/12/2007 29/01/2008 16/05/2007 10/08/2007 56 114 271,00 16/07/2008 29/08/2008 01/10/2008 TERMINATED

Unit Price NCB 1 31/082007 49 670 000.00 Post Qualification N Prior 16/10/2007 Plan 01/07/2005 30/03/2006 01/04/2006 30/04/2007 Construction of 10 PECs in Unit Price NCB Tillabéry region (Lot 3) Revised 10/06/2010 Unit Price NCB 1 31/082007 49 670 000.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/10/2007 11/12/2007 29/01/2008 16/05/2007 10/08/2007 69 140 484,00 16/07/2008 29/08/2008 01/10/2008 TERMINATED

Unit Price NCB 1 31/082007 41 904 000.00 Post Qualification N Prior 16/10/2007 Plan 01/07/2005 30/03/2006 01/04/2006 30/04/2007 Construction of 8 PECs in Unit Price NCB Zinder region (Lot 4.1) Revised 31/07/2009 Unit Price NCB 1 31/082007 41 904 000.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/10/2007 28/02/2008 29/01/2008 16/05/2007 10/08/2007 59 008 878,00 16/07/2008 29/08/2008 01/10/2008 10/09/2009

Unit Price NCB 1 31/082007 62 856 000.00 Post Qualification N Prior 16/10/2007 Plan 01/07/2005 30/03/2006 01/04/2006 30/04/2007 Construction of 12 PECs in Unit Price NCB Zinder region (Lot 4.2) Revised 31/05/2009 Unit Price NCB 1 31/082007 62 856 000.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/10/2007 11/12/2007 08/04/2008 16/05/2007 10/08/2007 78 393 389,00 16/07/2008 29/08/2008 01/10/2008 14/09/2009

Construction of 28 classrooms, Unit Price 5 store offices, 4 pedagogic 1 16/09/2007 207 391 660.00 ICB Post Qualification N Prior 16/10/2007 Plan 01/01/2005 31/08/2005 15/06/2005 31/05/2007 sectors, 1 school canteen and 4 Unit Price latrines in Aguié, Tessaoua, Revised 31/08/2009 Mayahi and Maradi Council Unit Price ICB Districts (Lot A1) 1 16/09/2007 207 391 660.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 16/09/2007 16/11/2007 18/02/2008 29/01/2008 16/05/2007 10/08/2007 235 789 933,00 16/07/2008 29/08/2008 01/10/2008 21/11/2009

Unit Price ICB Construction of 33 classrooms, 3 store offices, 4 pedagogic 1 16/09/2007 267 686 340.00 Post Qualification N Prior 16/10/2007 Plan 01/01/2005 31/08/2005 15/06/2005 31/05/2007 sectors, 2 school canteens and 6 Unit Price ICB latrines in Guidan-Roumdji, Revised 31/08/2009 Madarounfa and Dakoro Unit Price ICB Departments (Lot A2) 1 16/09/2007 267 686 340.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/11/2007 18/02/2008 08/04/2008 16/05/2007 10/08/2007 274 100 161,00 16/07/2008 29/08/2008 01/10/2008 21/11/2009

Unit Price ICB Construction of 38 classrooms, 1 16/09/2007 267 995 158.00 Post Qualification N Prior 16/10/2007 Plan 01/01/2005 31/08/2005 15/06/2005 31/05/2007 4 store offices, 4 pedagogic Unit Price ICB sectors, 1 school canteen and 6 Revised 30/09/2009 latrines in Konni, Madaoua, Keita and Bouza Districtsot B1) Unit Price ICB 1 16/09/2007 267 995 158.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/11/2007 18/02/2008 08/04/2008 16/05/2007 10/08/2007 274 506 349,00 16/07/2008 29/08/2008 01/10/2008 23/11/2009

Unit Price ICB Construction of 40 classrooms, 5 store offices, 5 pedagogic 1 16/09/2007 311 844 842.00 Post Qualification N Prior 16/10/2007 Plan 01/01/2005 31/08/2005 15/06/2005 31/05/2007 sectors, 3 school canteens and Unit Price 10 latrines in Abalack, Tahoua Revised 31/08/2009 Department, Tahoua Council, Illéla and Tchinta Districts (Lot Unit Price ICB B2) 1 16/09/2007 311 844 842.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/11/2007 18/02/2008 08/04/2008 16/05/2007 10/08/2007 329 106 340,00 16/07/2008 29/08/2008 01/10/2008 19/07/2009

Unit Price ICB Construction of Tsernaoua 1 16/09/2007 172 307 000.00 Post Qualification N Prior 16/10/2007 Plan 01/08/2005 31/03/2006 01/04/2006 31/03/2007 GEC, rehabilitation of Unit Price ICB Madaoua GEC 1, Bouza GEC Revised 30/11/2209 and Keita GEC laboratories Unit Price ICB (Lot B3) 1 16/09/2007 172 307 000.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/11/2007 18/02/2008 08/04/2008 16/05/2007 10/08/2007 314 358 865,00 16/07/2008 29/08/2008 01/10/2008 17/06/2010

Unit Price ICB 1 16/09/2007 142 907 000.00 Post Qualification N Prior 16/10/2007 Plan 01/08/2005 31/03/2006 01/04/2006 31/03/2007 Construction of Badaguichiri GEC and rehabilitation of Unit Price ICB Revised 31/07/2009 Tahoua Council GEC (Lot B4) Unit Price ICB 1 16/09/2007 142 907 000.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/11/2007 18/02/2008 08/04/2008 16/05/2007 10/08/2007 265 922 202,00 16/07/2008 29/08/2008 01/10/2008 28/08/2009

Unit Price ICB Construction of 29 classrooms, 1 16/09/2007 222 379 857.00 Post Qualification N Prior 16/10/2007 Plan 15/06/2005 31/05/2007 01/10/2008 31/03/2009 4 store offices, 4 pedagogic Unit Price ICB sectors, 2 school canteens and 8 latrines in Kollo, Say, Fillingué Revised 31/072009 and Ouallam Districts (Lot C1) Unit Price ICB 1 16/09/2007 222 379 857.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/11/2007 18/02/2008 08/04/2008 16/05/2007 10/08/2007 237 470 728,00 16/07/2008 29/08/2008 01/10/2008 30/05/2010

Unit Price ICB Construction of 28 classrooms, 1 16/09/2007 211 020 143.00 Post Qualification N Prior 16/10/2007 Plan 15/06/2005 31/05/2007 01/10/2008 30/04/2009 4 store offices, 4 pedagogic Unit Price ICB sectors and 10 latrines in Tillabéri, Tillabéri Council and Revised 31/08/2009 Téra Districts (Lot C2) Unit Price ICB 1 16/09/2007 211 020 143.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/11/2007 18/02/2008 08/04/2008 16/05/2007 10/08/2007 217 359 396,00 16/07/2008 29/08/2008 01/10/2008 03/10/2009 x

Construction of Sakoira GEC Unit Price ICB 1 16/09/2007 211 752 800.00 Post Qualification N Prior 16/10/2007 Plan 01/08/2005 31/03/2006 01/04/2006 31/03/2007 and rehabilitation of Téra SEC, Tillabér GEC 1, Fillingué GEC Unit Price ICB Revised 30/09/2009 and Ouallam GEC laboratories Unit Price ICB (Lot C3) 1 16/09/2007 211 752 800.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/11/2007 18/02/2008 08/04/2008 16/05/2007 10/08/2007 313 021 944,00 16/07/2008 29/08/2008 01/10/2008

Construction of 46 classrooms, Unit Price ICB 1 16/09/2007 317 896 570.00 Post Qualification N Prior 16/10/2007 Plan 15/06/2005 31/05/2007 01/10/2008 30/04/2009 2 store offices, 5 pedagogic sectors and 7 latrines in Unit Price ICB Revised 31/08/2009 Kantché and Magaria Districts Unit Price ICB (Lot D1) 1 16/09/2007 317 896 570.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/11/2007 18/02/2008 08/04/2008 16/05/2007 10/08/2007 334 067 451,00 16/07/2008 29/08/2008 01/10/2008 23/03/2010

Unit Price ICB Construction of 56 classrooms, 1 16/09/2007 442 713 430.00 Post Qualification N Prior 16/10/2007 Plan 15/06/2005 31/05/2007 01/10/2008 31/03/2009 8 store offices, 5 pedagogic Unit Price ICB sectors, 6 school canteens and15 Revised 31/07/2009 latrines in Gouré, Tanout and Unit Price ICB Zinder Council (Lot D2) 1 16/09/2007 442 713 430.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/11/2007 18/02/2008 08/04/2008 16/05/2007 10/08/2007 420 951 538,00 16/07/2008 29/08/2008 01/10/2008 20/03/2010

Unit Price ICB Construction of Zinder Council 1 16/09/2007 171 991 200.00 Post Qualification N Prior 16/10/2007 Plan 01/08/2005 31/03/2006 01/04/2006 31/03/2007 GEC 7 and rehabilitation of Unit Price ICB Magaria SEC laboratory (Lot Revised 31/12/2009 D3) Unit Price ICB 1 16/09/2007 171 991 200.00 Post Qualification N Prior 16/10/2007 Current 16/05/2007 10/08/2007 17/09/2007 16/11/2007 18/02/2008 08/04/2008 16/05/2007 10/08/2007 286 564 947,00 16/07/2008 29/08/2008 01/10/2008 28/07/2010

Unit Price ICB Construction of Zinder GEC 8 1 16/09/2007 171 991 200.00 Post Qualification N Prior 16/10/2007 Plan 01/08/2005 31/03/2006 01/04/2006 31/03/2007 and rehabilitation of Unit Price ICB Matameye SEC laboratories Revised 31/07/2009 (Lot D4) Unit Price ICB 1 16/09/2007 171 991 200.00 Post Qualification N Prior 16/10/2007 Actual 16/05/2007 10/08/2007 17/09/2007 16/11/2007 18/02/2008 08/04/2008 16/05/2007 10/08/2007 278 770 851,00 16/07/2008 29/08/2008 01/10/2008 10/11/2009

Construction of Maradi Dan Unit Price 1 16/09/2007 180 865 600.00 NCB Post Qualification N Prior 17/07/2008 Plan 01/08/2005 31/03/2006 01/04/2006 31/03/2007 Issa GEC, rehabilitation of Madarounfa laboratory and Unit Price Revised rehabilitation/extension of Unit Price NCB Soura Bildi laboratory (Lot A4) 1 16/09/2007 180 865 600.00 Post Qualification N Prior 17/07/2008 Current 16/05/2007 10/08/2007 29/05/2008 17/07/2008 13/10/2008 11/12/2008 280 764 233,00 16/02/2009 09/04/2009 01/06/2009 16/10/2010

Unit Price NCB Construction of Zinder Council 1 16/09/2007 171 991 200.00 Post Qualification N Prior 17/07/2008 Plan 01/04/2006 31/03/2007 GEC 9 and rehabilitation of Unit Price NCB Zinder CES F/A laboratory Revised (Lot D5) Unit Price NCB 1 16/09/2007 171 991 200.00 Post Qualification N Prior 17/07/2008 Current 16/05/2007 10/08/2007 29/05/2008 17/07/2008 13/10/2008 11/12/2008 345 427 126,00 16/02/2009 09/04/2009 01/06/2009 29/07/2010

Unit Price Mutual Completion of Sakoira GEC construction works and 1 agreement Prequalification N Prior Plan rehabilitation of Téra SEC, Unit Price Tillabéri GEC 1, Fillingué Revised GEC and Ouallam GEC Unit Price laboratories (Lot C3) Mutual 1 agreement Prequalification N Prior Current 04/05/2010 18/05/2010 23/06/2010 193 135 968,00 01/07/2010 11/08/2010 11/10/2010 IN PROGRESS

Unit Price Mutual 1 agreement Prequalification N Prior Plan Completion of construction works of 8 PECs in the Tahoua Unit Price Revised region (Lot 2.2) Unit Price Mutual 1 agreement Prequalification N Prior Current 09/03/2010 14/04/2010 17/06/2010 54 451 641,00 05/08/2010 11/08/2010 11/10/2010 TERMINATED

Total Cost Works 1 222 754 358.00 Plan 0

0.00 Revised 1 222 754 358.00 Current 1 801 942 566

xi

. CONSULTANTS

Various Services with Methods of Call for Expression of Interest Technical (T) & Financial (F) Evaluation Baseline Data Terms of Reference (TOR) Short List Request for Proposals (DDP) Proposals Submission Period Draft Contract Contract Award Contract Execution Selection and Schedule (CEI) Evaluation Evaluation Non-objection of CEI Date of Fixed Rate Estimated Prior or Projected Plan/ Proposals Non-objection Financial Contract Method of Publication Submission Date Non- Date of Non- Date of Non- Report Report Evaluation Draft Contract Date of Non- Contract Amount Contract Description* Receipt Non- or Time Amount in Subsequent Submission Revised/ Receipt Date Receipt Date Receipt Date Invitation Date Submission- of Evaluation Proposals Award Starting Date Completion Date Selection Date Date Objection Objection Objection Submission Submission Date Report Receipt Date Objection in CFAF Signature Date Date Objection Spent CFAF Examination Date Current Opening Date Report (T) Opening Date Date Date (T) (T)&(F)&Neg (T)&(F)&Neg Mutual agreement Fixed Rate 17 500 000.00 Prior Plan 01/10/2005 31/08/2007 Training of laboratory technicians Revised Mutual agreement Fixed Rate 17 500 000.00 Prior Current 31/10/2004 21/02/2005 19 000 000.00 13/05/2005 09/05/2005 01/09/2005 31/07/2007

Quality/price Fixed Rate 334 860 000.00 Prior Plan 01/06/2004 31/08/2004 01/08/2004 31/05/2007 Studies and inspection of school and Revised literacy infrastructure construction works Quality/price Fixed Rate 334 860 000.00 Prior Current 24/09/2004 24/09/2004 06/10/2004 09/12/2004 18/01/2005 09/12/2005 14/09/2005 09/12/2005 289 125 000.00 25/01/2006 20/02/2006 16/03/2006 In progress

Quality/price Time spent 24 803 640.00 Prior Plan Audit of project accounts for the 2005- Revised 2006 financial years 15/10/2005/ Quality/price Time spent 24 803 640.00 Prior Current 01/12/2004 20/06/2005 01/12/2004 20/06/2005 01/12/2004 20/06/2005 31/08/2005 17/10/2005 02/02/2006 04/05/2006 04/04/2006 04/05/2006 02/02/2006 04/05/2006 20 000 000.00 25/01/2006 19/05/2006 28/06/2006 21/06/2007

Continuing training design, Support to Quality/price Fixed Rate 192 000 000.00 Prior Plan 01/07/2004 31/10/2004 01/03/2005 31/01/2006 continuing training restructuring, Revised Learning evaluation and teaching aids design Quality/price Fixed Rate 192 000 000.00 Prior Current 02/02/2006 24/02/2006 02/02/2006 24/02/2006 02/02/2006 24/02/2006 12/02/2006 12/04/2006 12/10/2006 12/12/2006 12/10/2006 12/12/2006 10/04/2007 186 050 000.00 30/04/2007 09/08/2007 16/08/2007 20/11/2008

Development of a school health/hygiene Quality/price Fixed Rate 36 000 000.00 Prior Plan 01/07/2004 30/09/2004 01/01/2005 30/06/2006 improvement strategy, Study of the STI/HIV/AIDS situation in schools and Revised development of STI/HIV/AIDS issues in 16/07/2006/ the curriculum Quality/price Fixed Rate 36 000 000.00 Prior Current 02/02/2006 27/04/2006 02/02/2006 27/04/2006 02/02/2006 27/04/2006 17/05/2006 10/08/2006 12/10/2006 15/03/2007 12/10/2006 15/03/2007 35 850 000.00 09/07/2007 16/07/2007 19/03/2009

Mutual Retraining of 24 secondary school agreement Fixed Rate 800 000.00 Prior Plan 01/10/2005 31/08/2007 inspectors in education administration and Revised management Mutual agreement Fixed Rate 800 000.00 Prior Current 29/03/2007 28/06/2007 1 250 000.00 01/11/2007 17/10/2007 03/12/2007 13/12/2007

Mutual agreement Fixed Rate 19 000 000.00 Prior Plan 15/08/2005 15/08/2007 Training of 500 teachers in gender Revised approach Mutual agreement Fixed Rate 19 000 000.00 Prior Current 29/03/2007 28/06/2007 4 627 600.00 01/11/2007 05/10/2007 02/01/2008 07/02/2008

Mutual Retraining of 500 physical science and agreement Fixed Rate 8 000 000.00 Prior Plan 01/10/2005 31/08/2007 ELS teachers in scientific equipment handling and teaching material Revised development Mutual agreement Fixed Rate 8 000 000.00 Prior Current 29/03/2007 28/06/2007 14 280 640.00 01/11/2007 05/10/2007 21/01/2008 27/01/2009

Mutual agreement Fixed Rate 2 160 000.00 Prior Plan 22/07/2008 07/02/2009 Retraining of 360 teachers in educational Revised action project design and implementation Mutual agreement Fixed Rate 2 160 000.00 Prior Current 29/03/2007 28/06/2007 5 176 000.00 01/11/2007 05/10/2007 22/07/2008 07/02/2009

Mutual agreement Fixed Rate 50 000 000.00 Prior Plan 01/10/2005 31/08/2007 Continuing training of college teachers in Revised 50 Education Units Mutual agreement Fixed Rate 50 000 000.00 Prior Current 29/03/2007 28/06/2007 40 432 240.00 17/09/2007 03/2008 14/03/2010

Mutual agreement Fixed Rate 500 000.00 Prior Plan 01/07/2004 30/09/2004 01/01/2005 30/06/2006 Sensitization and social mobilization Revised action on STI/HIV/AIDS in schools Mutual agreement Fixed Rate 500 000.00 Prior Current 16/05/2007 28/06/2007 4 989 600.00 05/10/2007 13/12/2007 09/12/2008

Mutual Radio and TV sensitization and agreement Fixed Rate 72 000 000.00 Prior Plan 01/07/2004 30/09/2004 01/01/2005 30/06/2006 information programmes on school health Revised and hygiene Mutual agreement Fixed Rate 72 000 000.00 Prior Current 16/05/2007 28/06/2007 13 626 200.00 05/10/2007 08/11/2007 09/06/2008

Mutual Radio and TV sensitization and agreement Fixed Rate 72 000 000.00 Prior Plan 01/07/2004 30/09/2004 01/01/2005 30/06/2006 information programmes on Revised STI/HIV/AIDS in schools Mutual agreement Fixed Rate 72 000 000.00 Prior Current 16/05/2007 28/06/2007 13 333 800.00 05/10/2007 08/11/2007 09/06/2008

Mutual Information/training of 3 500 PTA agreement Fixed Rate 7 000 000.00 Prior Plan 01/07/2004 30/09/2004 01/07/2005 30/06/2008 representatives on the school health improvement strategy and hygiene and Revised health action planning Mutual agreement Fixed Rate 7 000 000.00 Prior Current 16/05/2007 28/06/2007 34 053 170.00 05/10/2007 24/04/2008 27/01/2009

Mutual Information/training of 3 500 head- agreement Fixed Rate 7 000 000.00 Prior Plan 01/07/2004 30/09/2004 01/07/2005 30/06/2008 teachers on the school health improvement strategy and hygiene and Revised health action planning Mutual agreement Fixed Rate 7 000 000.00 Prior Current 16/05/2007 28/06/2007 34 053 170.00 05/10/2007 24/04/2008 27/01/2009

Mutual agreement Fixed Rate 57 000 000.00 Prior Plan 01/08/2004 30/06/2008 Community sensitization campaigns and Revised functional literacy for 5 400 women Mutual agreement Fixed Rate 57 000 000.00 Prior Current 16/05/2007 28/06/2007 62 339 000.00 05/10/2007 14/12/2007 30/06/2009

Quality/price Fixed Rate 86 542 650.00 Prior Plan 01/07/2004 30/09/2004 01/07/2005 30/06/2008 Reproduction and binding of teaching Revised aids for training and retraining workshops Quality/price Fixed Rate 86 542 650.00 Prior Current 29/03/2007 25/06/2007 01/08/2007 06/09/2007 01/08/2007 06/09/2007 77 701 600.00 03/10/2007 04/12/2007 12/12/2007 09/12/2009

Procurement of supplies for training and Quality/price Fixed Rate 94 669 000.00 Prior Plan 01/07/2004 30/09/2004 01/07/2005 30/06/2008 retraining workshops (Lot 2 of the NCB Revised of 25 May 2007) Quality/price Fixed Rate 94 669 000.00 Prior Current 29/03/2007 25/06/2007 01/08/2007 06/09/2007 01/08/2007 06/09/2007 48 635 464.00 03/10/2007 04/12/2007 12/12/2007 28/01/2008

Procurement of small teaching material Quality/price Fixed Rate 30 000 000.00 Prior Plan 01/07/2004 30/09/2004 01/07/2005 30/06/2008 for female literacy (Lot 1 of the LCB of Revised 25 May 2007) Quality/price Fixed Rate 30 000 000.00 Prior Current 29/03/2007 25/06/2007 01/08/2007 06/09/2007 01/08/2007 06/09/2007 26 935 800.00 03/10/2007 04/12/2007 12/12/2007 17/12/2007

Organization of community sensitization Mutual campaigns for girl child enrolment agreement Fixed Rate 15 000 000.00 Prior Plan xii promotion Revised Mutual agreement Fixed Rate 15 000 000.00 Prior Current 10/10/2005 01/10/2007 9 222 599.00 25/01/2008 10/01/2008 02/11/2008 20/03/2009

Quality/price Fixed Rate 0.00 Prior Plan Drafting of the Education II/ADF Project Revised management manual Quality/price Fixed Rate 0.00 Prior Current 13/02/2007 02/04/2007 13/02/2007 02/04/2007 13/02/2007 02/04/2007 15/04/2007 15/06/2007 29/08/2007 01/10/2007 29/08/2007 01/10/2007 29/08/2007 01/10/2007 9 000 000.00 29/01/2008 24/01/2008 29/01/2008 09/09/2008

Quality/price Fixed Rate 24 000 000.00 Prior Plan 15/02/2005 15/07/2006 Training of SMC board members in the Revised administration of their committees Quality/price Fixed Rate 24 000 000.00 Prior Current 29/06/2007 19/07/2007 29/06/2007 19/07/2007 29/06/2007 19/07/2007 10/08/2007 10/10/2007 08/02/2008 26/02/2008 08/02/2008 26/02/2008 08/02/2008 58 519 800.00 07/03/2008 11/04/2008 27/01/2009 27/08/2009

Quality/price Fixed Rate 90 000 000.00 Prior Plan 01/07/2004 31/10/2004 01/03/2005 30/06/2008 Training of 12 MEN executives in Revised learning evaluation Quality/price Fixed Rate 90 000 000.00 Prior Current 30/01/2007 19/03/2007 30/01/2007 19/03/2007 30/01/2007 19/03/2007 18/05/2007 18/07/2007 21/09/2007 12/11/2007 21/09/2007 12/11/2007 03/01/2008 01/02/2008 73 195 618.00 06/12/2007 11/04/2008 15/09/2008 04/12/2009

Quality/price Fixed Rate 37 205 460.00 Prior Plan 20/08/2007 13/09/2007 20/08/2007 13/09/2007 20/08/2007 Audit of project accounts for the 2007 to Revised 2009 financial years 27/11/2007 Quality/price Fixed Rate 37 205 460.00 Prior Current 20/08/2007 13/09/2007 20/08/2007 13/09/2007 20/08/2007 13/09/2007 27/09/2007 26/12/2007 04/03/2008 07/04/2008 04/03/2008 07/04/2008 04/03/2008 07/04/2008 20 100 000.00 10/04/2008 08/05/2008 15/06/2008 10/07/2010

Mutual Broadcast of radio and TV sensitization agreement Fixed Rate 0.00 Prior Plan 01/07/2004 30/09/2004 01/01/2005 30/06/2006 and information programmes on school health and hygiene and STI/HIV/AIDS in Revised schools Mutual agreement Fixed Rate 0.00 Prior Current 22/01/2009 18/03/2009 35 682 800.00 09/04/2009 27/07/2009 05/08/2010

Quality/price Fixed Rate 36 000 000.00 Prior Plan 01/07/2004 30/09/2004 01/01/2005 30/06/2006 Design and production of a school Revised STI/HIV/AIDS idiot box 30/09/2008 Quality/price Fixed Rate 36 000 000.00 Prior Current 19/03/2007 17/03/2008 19/03/2007 31/07/2008 22/12/2008 13/01/2009 18/03/2009 13/01/2009 18/03/2009 13/01/2009 18/03/2009 34 833 750.00 08/04/2009 26/05/2009 05/06/2009 15/04/2010

Evaluation of the impact of school Quality/price Fixed Rate 39 360 000.00 Prior Plan 01/07/2004 30/06/2008 01/07/2004 30/06/2008 canteens on girls’ enrolment in nomadic Revised areas Quality/price Fixed Rate 39 360 000.00 Prior Current 03/07/2008 23/09/2008 06/11/2008 23/09/2008 06/11/2008 27/11/2008 15/01/2009 02/03/2009 18/03/2009 02/03/2009 18/03/2009 46 238 409,00 08/04/2009 20/07/2009 16/11/2009 27/07/2010

Quality/price Fixed Rate 12 401 820.00 Prior Plan Audit of project accounts for the 2010 Revised financial year 05/07/2010 Quality/price Fixed Rate 12 401 820.00 Prior Current 10/03/2010 19/04/2010 10/03/2010 19/04/2010 10/03/2010 19/04/2010 20/05/2010 17/08/2010 04/10/2010 08/11/2010 04/10/2010 08/11/2010 04/10/2010 08/11/2010 5 630 000,00 23/11/2010 05/01/2011 15/03/2011 30/04/2011

Mutual agreement Fixed Rate 4 000 000.00 Prior Plan 01/07/2004 30/09/2004 01/07/2005 30/06/2008 Training of 12 School Health Office Revised senior staff in school health management Mutual agreement Fixed Rate 4 000 000.00 Prior Current 11/03/2010 20/04/2010 11/03/2010 20/04/2010 11/03/2010 20/04/2010 4 115 000,00 14/06/2010 26/08/2010 24/09/2010

Mutual Information/training of 7 100 head- agreement Fixed Rate 0.00 Prior Plan 15/01/2010 28/02/2011 teachers, PTA representatives and school health focal points on the health Revised improvement strategy and school health Mutual and hygiene action planning agreement Fixed Rate 0.00 Prior Current 30/10/2009 16/11/2009 58 272 840,00 04/12/2009 15/01/2010 28/02/2011

Mutual Supplies for the training of 7 100 head- agreement Fixed Rate 0.00 Prior Plan 09/12/2009 31/12/2009 teachers, PTA representatives and school health focal points on the health Revised improvement strategy and school health Mutual and hygiene action planning agreement Fixed Rate 0.00 Prior Current 30/10/2009 16/11/2009 18 514 400,00 04/12/2009 09/12/2009 31/12/2009

1 369 802 Total Cost Services 570.0 Plan 0,0 0.0 Revised 0,0 1 369 802 570.0 Current 1 304 784 500,0

xiii