Upcoming Projects

Strathcona

CEA Partnering with Industry Symposium January 2021 Introduction Relevant departments: • Transportation Planning and Engineering (TPE) o planning studies o roadway upgrades, or new growth projects • Transportation and Agriculture Services o maintenance/rehab of transportation infrastructure • Planning and Development Services • Utilities o sanitary, water • Facility Services • Recreation, Parks and Culture • For more information: Strathcona.ca 21/11/21 Approved Capital Plan Transportation Planning and Engineering

• Annual programs: – Annual Missing Links Program – Annual Replacement Program – Traffic and Pedestrian Safety Program – Traffic Signal and Intersection Improvement Program

• 2021: – Sherwood Drive/Granada intersection improvements, design – Broadway Boulevard and Broadview Drive , construction

1/13/213 Sherwood Drive/Granada Boulevard Intersection Improvement Design Transportation Planning and Engineering

• Align with Centre In The Park area redevelopment plan • Improve pedestrian access and safety • Significant bus route • Address operational issues

41/11/21 Broadway Boulevard and Broadview Drive Roundabout Construction Transportation Planning and Engineering

51/11/21 Approved 5-Year Capital Plan Transportation Planning and Engineering

• 2023: (Tentative) – Range 231 Design, Wye Road to Hillshire Boulevard – South of LEA Functional Planning Study ( 21 to Range Road 222 and Road 530 to LEA Boundary)

• 2024: (Tentative) – Sherwood Drive / Broadmoor Boulevard Roundabout Design – Township Road 530 and Range Road 222 Intersection Improvements

• 2025: (Tentative) – Broadmoor Boulevard and Baseline Road Functional Planning Study – Fir , Sherwood Drive to Ash Street, Design

61/11/21 Other Projects Transportation Planning and Engineering

• 2021 roadway improvements (Municipal Stimulus Program): – Bethel Way, Bison Way to Lakeland Drive, construction – Range Road 232, Township Road 534 to 400m south, widening construction – Township Road 560, Range Road 214 to 1 km east, widening construction

For more information: strathcona.ca/transportation-/

71/13/21 Bethel Way, Bison Way to Lakeland Drive Construction Transportation Planning and Engineering

81/11/21 Range Rd 232, Township Rd 534 to 400m south Construction Transportation Planning and Engineering

City of Edmonton Strathcona County

91/11/21 Township Rd 560, Range Rd 214 to 1km East Construction Transportation Planning and Engineering

Strathcona County Alberta Industrial Heartland

101/11/21 Capital Projects Facility Services Department

• Projects approved: – Multi-Purpose Agriculture Facility – Tender prequalification complete – Strathcona Public Services Yard, Facility Expansion – Tender prequalification complete – Annual Facility Lifecycle Program – Work released throughout 2021 – Strathcona Olympiette Centre, curling rink modernization – Tendered – Moyer Recreation Centre, emergency generator and power upgrade – Tendered

• 2021-2024 tentative capital projects: – Festival Place, exterior recladding – In design – Multi-Sport Indoor Fieldhouse – Planning Phase – Emerald Hills Aquatic Center, 2nd floor tenant improvements – Planning phase – Millennium Place, flooring modernization – Planning phase

111/11/21 Projects Recreation, Parks and Culture Department

Projects vary: • Design and construction of new trails, landscaping, and gathering spaces (parks, amenities) • McPherson Park spray deck design-build project planned in 2021 • Examples of past projects: – paved trail connections in urban fringe areas – new trails with River Valley Alliance and TransCanada Trails – design and construction of Ardrossan Regional Park including spray park – Emerald Hills Sports Pavilion • Project management by Transportation Planning and Engineering department

121/11/21 Transportation and Agriculture Services and Utilities Departments

• no anticipated new capital projects in the 5-year capital budget • annual rehabilitation programs: – Rural Road program – Urban Road program – Asphalt Trail program – program – Parking Lot Program

• on-going projects for Utilities department: – North of Yellowhead Water & Wastewater Transmission Infrastructure – Collingwood Cove Wastewater Lift Station Renewal – South Cooking Lake Residential Water Fill Station

131/12/21 New Development Areas Planning and Development Services

141/11/21 Future Outlook Heartland • Future capital projects may be created due to: Area Map – emerging industrial development projects in Alberta’s Industrial Heartland – residential development – other emergent needs

151/11/21 Questions?

Kevin Cole, P.Eng Transportation Planning and Engineering, Strathcona County [email protected]

161/11/21