MINISTRY OF HEALTH INFRASTRUCTURE DIRECTORATE UPDATE ON COMPLETED AND ONGOING PROJECTS (2017-2020) APRIL 2020 NO. TITLE OF LOCATION EXECUTING FUNDING START DATE ANTICIPATED COST (CONTRACT REMARKS PROGRAMME/PROJEC FIRM SOURCE(S) COMPLETION SUM) (PROGRESS/CHALLENGES) T/INITIATIVE DATE COMPLETED PPROJECTS WHICH COMMENCED BEFORE 2017

1 Construction &Equipping Bisease, Gomoa Vamed Health Raffeisen Bank Jan. 2016 Jan. 2018 € 23,500,000.00 Works Completed and Commissioned of 10 Polyclinics in the Dawurampong, Biriwa, Projects CZ S.r.o for use in Aug. 2018 Etsii Sunkwa, Binpong Egya, Gyamera, Mankrong, Akonfude, Ekumfi Naakwa & Gomoa Potsin

2 TB Case Detection Nationwide Oldelft Benelux ORIO Grant/ ABN April, 2016 24 Months for 18,842,335.00 Installation of equipment completed Programme Ambro Loan Installation and 7 as at August 2018 years of Warranty & Maintenance

3 Major Rehabilitation and Tamale Vamed ABN AMRO Bank, July, 2015 December, 2018 € 38,500,000.00 Works Completed and handed over. Upgrade of Tamale Engineering KG Netherlands Commissioned for use on 27th Teaching Hospitals Phase II & Co GmbH February 2019

4 Construction & Equipping Legon EDC Limited Bank Hapoalim B.M. April, 2013 Nov,2016 $ 184,740,001.00 Project completed and commissioned. of 597-Bed University of of Israel Teaching Hospital. Phase I

5 Construction of Offices for Ridge Amandi GOG/ABFA Apr-16 October, 2019 $ 24,300,000.00 The project is completed as at January MOH 2019 Headquarters/Regulatory Bodies

COMPLETED PPROJECTS WHICH COMMENCED AFTER 2016

6 Construction & Completion Vamed Unicredit Bank Jan-17 Feb-19 € 13,500,000.00 Works Completed and of 5 Polyclinics in the Obojo (Adentan), Engineering KG Austria AG Commissioned for use as at May Greater Region , Bortianor, & Co GmbH 2019 Oduman & ONGOING PROJECTS COMMENCING BEFORE 2017

7 Expansion of Radiotherapy KBTH/KATH (M/S Cymain & BADEA/OFID/Count March, 2012 April, 2020 $ 13,500,000.00 Works are ongoing and about 80.25% & Nuclear Medicine M/S Maripoma - erpart Funding complete Services at KBTH & Civil/Retrofit KATH Works) (M/S Techfab, M/S Seimens & M/S Comicel - Suppliers)

8 Construction of 2 Regional /Madina (relocated Euroget De Invest Barclays Bank November, 2014 December 2020 $ 339,000,000.00 Works are ongoing and about 56% & 6 District Hosp. by to Kwabenya), Twifo- Anticipated complete. Euroget Praso, Konongo- Government Obligations with respect Odumasi, , Tepa to connection of External Road & networks to the sites especially at Konongo and Sewua remains a huge challenge.

Wa Regional Hospital and Ga East Municipal Hospital (Kwabenya) have been commissioned for use as at August and November 2019 respectively

9 Construction of 7 District , Fomena, NMS Barclays Bank PLC, November, 2012 October, 2016 $ 175,000,000.00 Dodowa is Completed.Civil Works Hospitals & Integrated IT , , Garu Infrastructure London progress stands at 72% at Fomena, System in Ghana Tempane, Sekondi & Ltd. 60% at Kumawu, 35% at Abetifi, Takoradi Takoradi European is at 50%, however, the staff residential apartment which is part of the development is 89%, Sekondi at 6% and Garu at 3% complete. Work has currently stalled awaiting approval for the extension of the loan agreement. Ministry of Finance, however is has concluded VFM Audit on the project. The contractor is yet to be mobilised to site ONGOING PROJECTS COMMENCING AFTER 2017

10 Cons. & Equi. Of Legon EDC Bank Hapoalim B.M. May 2019 December 2020 € 40,500,000.00 Phase I of the Project Completed, University of Ghana Construction of Israel Anticipated commissioned and in use. Phase has Medical Centre (Phase II) Limited commenced works and would be completed by December 2020

11 Construction of 5 District Sawla, Tolon, , Vamed Raffeisen Bank August 2018 February 2021 € 80,000,000.00 The project is progressing steadily Hospitals in Sawla, Tolon, , Wheta & Bamboi Engineering and currently between 45% - 65% Somanya, Buipe And GmbH Co KG complete. These would be completed Wheta and a Polyclinic In by June 2020 Bamboi 12 Construction of 5 and Akontombra, Elubo, Vamed ING Bank/ORIO December, 2019 December, 2024 € 26,290,429.00 Contract signed. Contractor has upgrading of 1 public , Mpohor, Engineering Grant Anticipated mobilised to site and has commenced health facilities in the Nsuaem, Wassa Dunkwa GmbH Co KG works since July 2019 13 Completion and Equipping Ellipse Projects UKEF/ Deutsche March, 2019 March, 2021 € 22,330,550.00 Contract signed. Works progressing of Bekwai District Hospital S.A.S Bank Anticipated steadily and expected to be completed by November 2020 14 Modernisation and Tetteh Quarshie Memorial Contracta DEUTSCHE BANK October, 2019 October, 2021 € 40,000,000.00 Contractor has mobilised to site to Equipping of 4 Selected Hospital, Kibi District COSTRUZIONI Anticipated commence works.. Works expected to facilities Hospital, and ITALIA S.R.L. be completed by mid 2021 Atibie Hospitals

15 Construction of 15 CHPS Oshiyie, Tetegu, Various ABFA November, 2018 December, 2019 GHS 19,500,000.00 The project is progressing steadily. Compounds Antwirifo, Mantewareso, Contractors are at various levels of Mewerenfiwuo, Kofiasua, completion between 40% and 95%. 3 Amakyekrom, Akaaso, have been completed Akaasu, Samproso, (Near Offiso), Akyem , Tiawia, Ahankrasu

16 Construction of 26 CHPS Otumi, Akim Various ABFA November, 2019 December, 2020 GHS 39,257,792.59 The project is progressing steadily. Compounds (Otumi, Akim Nkwantanang, Gyakiti, Anticipated Contractors are at various levels of Nkwantanang, Gyakiti, Kwanyako, Mpeasem- completion between 10% and 25%. Kwanyako, Mpeasem- Kwaebibirem, Jamasi, Kwaebibirem, Jamasi, Wiaboman, Nsutam , Wiaboman, Nsutam , Asunafo, , , Asunafo, Gbawe, Weija, Ananekrom, Ananekrom, Nkroful Denkyira, Kwamoano, Denkyira, Kwamoano, Ajumako , Ajumako Kumasi, Nwenoso Nwenoso No. 3, No. 3, Ntunkumso, Ntunkumso, Akuakrom, Akuakrom, Tanyigbe, Klefe Tanyigbe, Klefe Demetey, Kato, Koduakrom Demetey, Kato, (near Nsoatre), Aboabo, Koduakrom (near Debiso, Kwagyekrom, Nsoatre), Aboabo, Timeabu Debiso, Kwagyekrom, Timeabu

SCHEDULING FOR IMPLEMENTATION IN 2020

17 Rehabilitation of Bolga Berock Ghana Saudi fund March 2020 March 2021 $ 20,000,000.00 Cabinet and Parliamentary approval Regional Hospital (Phase Limited Anticipated Anticipated received on the loan. PPA Approval II) - 295 has been received for restrictive tendering on the Equipment procurement. Tendering Process ongoing 18 Completion and Equipping Komfo Anokye Teaching Contracta DEUTSCHE BANK/ February 2020 December 2022 $ 138,500,000.00 Cabinet and Parliamentary approvals of KATH Maternity and Hospital COSTRUZIONI UKEF Anticipated received on the loan. VFM Audit Children's Block ITALIA S.R.L. concluded by MOF. Design preparation completed awaiting sod cutting 19 Construction of Eastern Koforidua Messrs Tyllium/EllipseUKEF March 2020 December 2022 € 70,000,000.00 Cabinet and Parliamentary approvals Regional Hospital in Anticipated Anticipated received on the loan. Awaiting Koforidua conclusion if VFM by MOF

20 Construction of District , Anyinam, Universal Deutsche Bank November 2019 November 2022 € 55,000,000.00 Awaiting Cabinet and Parliamentary Hospital at Obuasi, Enyiresi Hospital Group Anticipated Anticipated approvals Anyinam Trauma Hospital and Rehabilitation of Enyiresi Government Hospital 21 Rehabilitation and Shama Poly Changda Standard Chartered April 2020 April 2022 € 32,000,000.00 Cabinet and Parliamentary approvals Expansion of Shama Engineering Bank Anticipated Anticipated received for both Financing and Hospital project - 100 Bed Co.,Ltd supply contract. Awaiting VFM Audit by MOF and PPA approva for single sourcing

22 Rehabilitation and La Poly Changda Standard Chartered April 2020 April 2022 € 63,000,000.00 Cabinet and Parliamentary approvals Expansion of La General Engineering Bank Anticipated Anticipated received for both Financing and Hospital - 180 Bed Co.,Ltd supply contract. Awaiting VFM Audit by MOF and PPA approva for single sourcing

23 Construction of Urology Korle-Bu Teaching VAMED Raffeisen Bank June 2020 December 2022 € 38,000,000.00 Cabinet and Parliamentary approvals and Nephrology Centre of Hospital Engineering International Anticipated Anticipated received for both Financing and Excellence GmbH supply contract. Awaiting VFM Audit by MOF and PPA approva for single sourcing 24 Completion of the New 330 Korle-Bu Teaching Hospital Standard Chartered August 2020 August 2022 € 142,220,000.00 Cabinet and Parliamentary approvals Beds Maternity Block Hospital Engineering Bank Anticipated Anticipated received for both Financing and GmbH supply contract. Awaiting VFM Audit by MOF and PPA approva for single sourcing

25 Construction of Tema, , Dormaa E.D.C Israel Discount Bank April 2020 Dec. 2020 for CMS € 140,000,000.00 Cabinet and Parliamentary approvals General Hospital & Central Engineering, ltd. Anticipated and April 2022 for received for both Financing and Medical Stores and Development and Tema, Nkoranza supply contract. Awaiting VFM Audit Rehabilitation of Nkoranza Construction and Dormaa by MOF and PPA approva for single and Dormaa Hospitals in Compay ltd. sourcing Ghana 26 Construction of 12 Jumapo, , VAMED Bank Austria April 2020 April 2023 € 71,500,000.00 Cabinet and Parliamentary approvals Hospitals in Eastern, Nkwatia, , Engineering Anticipated Anticipated received for both Financing and Ashanti, Ahafo and Gt , Suame, GmbH supply contract. Awaiting VFM Audit Accra Drobonso, Sabronum, by MOF and PPA approva for single Manso , Twedie, sourcing Mim, Kpone Katamanso 27 Construction of Ridge Ridge Gold Coast Swiss Bank August 2020 September 2022 $ 100,000,000.00 Awaiting Ministry of Finance's Hospital, Phase II Pioneer Anticipated Anticipated approval Construction Limited

28 Supply of 20 ICU Carl Friederichs Deutsch Bank Ag. € 20,000,000.00 Awaiting Ministry of Finance's Ambulance Trucks and 90 GmnH approval Ambulances

29 Construction of 22 District , Sinohydro Sinohydro November 2020 November 2023 $ 100,000,000.00 Awaiting Cabinet and Parliamentary Hospitals under Sinohydro Adabokrom,Mpohor,Nyin Anticipated Anticipated approvals on the Loan financing ahin, Suame, Kraboa Coatar, , , Kukuom, Busunya, Amasu, Herman, , Kyekyewere, Kunkurugu, , , Nangodi, Pusiga, &

TREATMENT AND HOLDING CENTRES

30 Comprehensive Treatment Adaklu ADB Ghana Ltd World Bank April 2020 November 2020 GH₵ 15,600,000.00 Site set up and mobilisation ongoing and Quarantine facility 31 Comprehensive Treatment Sewua Universal GOG April 2020 November 2020 GH₵ 22,800,000.00 Site set up and mobilisation ongoing and Quarantine facility Hospitals Group Ltd 32 Comprehensive Treatment China Railway GOG April 2020 November 2020 GH₵ 28,925,100.00 Site set up and mobilisation ongoing and Quarantine facility (CRCEG Ghana Ltd) 33 Comprehensive Treatment Pantang, Dodowa and Gold Coast World Bank/GOG April 2020 November 2020 GH₵ 78,230,100.00 Site set up and mobilisation ongoing and Quarantine facility Asawinso Pioneer Construction 34 Remodelling and Hospital Cresflex GOG April 2020 November 2020 GH₵ 9,750,600.00 Site set up and mobilisation ongoing refurbishment of existing Company Limited facilities at Goaso 35 Treatment and Holding Syndicated GOG April 2020 November 2020 GH₵ 15,000,000.00 Site set up and mobilisation ongoing Centre Capital Engineering 36 Mechanical and Electrical KorleBu Teaching Kissart Group GOG April 2020 November 2020 GH₵ 15,600,000.00 Site set up and mobilisation ongoing Installation and Equipping Hospital Limited of Treatment and Holding Centre 37 Rehabilitation of Fevers KorleBu Teaching Golden Mainland GOG April 2020 November 2020 GH₵ 20,632,053.85 Site set up and mobilisation ongoing Unit as Holding Centre Hospital 38 Treatment and Holding Takoradi Metalex GOG May 2020 December 2020 GH₵ 15,000,000.00 Procurement Ongoing Centre Engineering and Anticipated anticipated Construction Services Ghana Limited 39 Treatment and Holding City Plus Limited GOG May 2020 December 2020 GH₵ 15,000,000.00 Procurement Ongoing Centre Anticipated anticipated 40 Treatment and Holding Budox GOG May 2020 December 2020 GH₵ 28,925,100.00 Procurement Ongoing Centre Construction Anticipated anticipated Company Limited