Massachusetts State Seal, Charles D. Baker, Governor Karyn E. Polito, Lieutenant Governor Stephanie Pollack, Secretary & CEO, Jonathan L. Gulliver, Highway Administrator, MassDOT Highway Division Logo

March 19, 2019 609200-106704

ADDENDUM NO. 3

To Prospective Bidders and Others on:

BERKLEY, LAKEVILLE AND FREETOWN 4 Railroad Bridge Replacements (Steel) along the South Coast Rail Line over the Cotley and Cedar Swamp Rivers and Fall Brook

BIDS TO BE OPENED AND READ: TUESDAY, APRIL 9, 2019 AT 2:00 P.M. Transmitting revisions to the Contract Documents as follows:

RESPONSES TO BIDDER’S QUESTIONS: 2 pages.

COVER PAGE: Revised cover pages volume 1 and volume 2.

DOCUMENT 00010: Revised pages 1 and 3.

DOCUMENT 00102: Inserted new pages 3 and 4.

DOCUMENT A00801: Revised pages 125, 135, and 225.

DOCUMENT A00831: Revised pages 9 through 12. Inserted new pages 12.1 through 12.6.

DOCUMENT A00880: Inserted new document (96 pages).

PLANS: Revised drawing 8 of 207.

Please take note of the above, substitute the revise pages for originals, insert new pages in proper order, insert new document in proper order, and acknowledge Addendum No. 3 in your Expedite Proposal file before submitting your bid.

Very truly yours,

Frank Kucharski, P.E. Construction Contracts Engineer

SP c: John Fallon Ten Park Plaza, Suite 4160, Boston, MA 02116 Tel: 857-368-4636, TTY: 857-368-0655 www.mass.gov/massdot

THIS PAGE INTENTIONALLY LEFT BLANK BERKLEY, LAKEVILLE AND FREETOWN 4 Railroad Bridge Replacements (Steel) along the South Coast Rail Line over the Cotley and Cedar Swamp Rivers and Fall Brook (609200-106704) Responses to Bidder’s Questions Addendum No. 3, March 19, 2019

D.W. White Construction, Inc. , e-mail dated March 7, 2019

Question 4) There are several places in the contract documents that specify the contractor shall inspect the site prior to bidding. Will MASSDOT and the managing authorities hold a pre-bid meeting and offer a time and means to access the individual bridge and culvert locations on the ROW?

Response 4) See new page 00102 – 3. In addition, a hy-rail view of the New Bedford Main Line right-of-way from Cotley Street in Taunton to Chace Road in Freetown (7.3 miles) is available at: https://youtu.be/2E6H_5lg1kE

D.W. White Construction, Inc. , e-mail dated March 13, 2019

Question 5) Please clarify the gap dimension at the global stability steel sheeting. Notes on sheets 50, 140, & 177 state “Global stability walls: provide 5 foot gap in sheeting every 50 feet along the wall length to allow for groundwater flow through wall”. Wall elevation sheets 56 & 57 show a dimension of 5’0” for a gap. Page 125 of the special provisions, item 952.1 states under construction to “Leave a 6” gap in global stability walls every 50 feet along thee stability wall length”. Please clarify which dimension should be used.

Response 5) See revised page A00801 – 125.

Question 6) Please clarify the pay unit of measure for item 995.042 modular block walls. Is the pay item per linear foot or per square feet? Page 225 of the special provisions, states under method of measurement “Item 995.042 will be measured for payment by the Foot, complete in place.” The next sentence states “The measurement of the wall area shall be made based on the vertical area of the front face of the wall installed.” The second sentence is stating payment per area, and the first sentence is stating per linear foot. Please clarify.

Response 6) See revised page A00801 – 225.

D.W. White Construction, Inc. , e-mail dated March 15, 2019

Question 7) The bid form indicates that Items 953.31 and 953.32 are to be paid by the square yard. The Basis of Payment in the special provisions for these items stipulate that payment of 70% of the Lump Sum bid price will be paid upon complete installation and the remaining 30% of the Lump Sum bid price will be paid upon complete removal. Will these two items be paid as a Lump Sum or will they be paid by the square yard per the bid form? If they are to be paid by the square yard will the quantities be measured by the square yard of exposed face of sheeting or by total square yard of steel sheeting installed?

Response 7) See revised page A00801 – 135.

PAGE 1 OF 2 BERKLEY, LAKEVILLE AND FREETOWN 4 Railroad Bridge Replacements (Steel) along the South Coast Rail Line over the Cotley and Cedar Swamp Rivers and Fall Brook (609200-106704) Responses to Bidder’s Questions Addendum No. 3, March 19, 2019

D.W. White Construction, Inc. , e-mail dated March 18, 2019

Question 8) Item 754.2 – Turtle Protection Plan – Lump Sum, calls out for the Installation of 6” buried silt fence from Station 2104+00 to Station 2053+00. Measurement and payment for Item 754.2 is on a lump sum basis. Will item 697.0 be added to the contract to cover the 10,200 LF of silt fence?

Response 8) No. The silt fence barrier depicted in the “Silt Fence Barrier/Compost Filter Tube” detail on sheet 6 (Construction Details 1 of 3) shall be included in the lump sum cost for Item 754.2 – Turtle Protection Plan. The compost filter tube shall be paid for separately under item 767.12.

PAGE 2 OF 2 ③ Addendum No. 3, March 19, 2019 ② Addendum No. 2, March 11, 2019 SP VOLUME 1 OF 2

COMMONWEALTH OF

CONTRACT DOCUMENTS

AND SPECIAL PROVISIONS

PROPOSAL NO. 609200-106704 P.V. = $25,244,000.00 PLANS YES

FOR

4 Railroad Bridge Replacements (Steel) along the South Coast Rail Line over the Cotley and Cedar Swamp Rivers and Fall Brook

in the Towns

BERKLEY, LAKEVILLE AND FREETOWN

In accordance with the 1988 English Edition of the STANDARD SPECIFICATIONS For HIGHWAYS and BRIDGES and the Supplemental Specifications dated July 1, 2015

② This Proposal to be opened and read: TUESDAY, APRIL 9, 2019 @ 2:00 P.M.

③ PRE BID SITE WALK THROUGH A pre-bid site visit will be held on Thursday, March 28, 2019. The meeting point is MassDOT’s District 5 office, 1000 County Street (Route 140), Taunton, MA. Those who wish to view the site shall email John Fallon at [email protected], by 10:00AM Wednesday, March 27, 2019 and supply the names and identification of their representatives to be placed on a list of authorized personnel to accompany Mass DOT staff. The site visit will be conducted under the terms and conditions stipulated by the District. The individuals attending the site visit shall bring and wear personal protective equipment (hard hats, safety glasses, reflectorized vests, and safety footwear). The site visit will not be repeated – however, it is not mandatory. Prior to the site visit, a safety briefing will be held at 7:30 AM (7:00 AM sign-in) in the training building located in the back-parking lot of the MassDOT District 5 Office to discuss on track safety details. Each participant shall participate in this safety briefing before visiting the site.

*** THIS PAGE IS INTENTIONALLY LEFT BLANK *** ③ Addendum No. 3, March 19, 2019 ② Addendum No. 2, March 11, 2019 SP VOLUME 2 OF 2

COMMONWEALTH OF MASSACHUSETTS

CONTRACT DOCUMENTS

AND SPECIAL PROVISIONS

PROPOSAL NO. 609200-106704 P.V. = $25,244,000.00 PLANS YES

FOR

4 Railroad Bridge Replacements (Steel) along the South Coast Rail Line over the Cotley and Cedar Swamp Rivers and Fall Brook

in the Towns

BERKLEY, LAKEVILLE AND FREETOWN

In accordance with the 1988 English Edition of the STANDARD SPECIFICATIONS For HIGHWAYS and BRIDGES and the Supplemental Specifications dated July 1, 2015

② This Proposal to be opened and read: TUESDAY, APRIL 9, 2019 @ 2:00 P.M.

③ PRE BID SITE WALK THROUGH A pre-bid site visit will be held on Thursday, March 28, 2019. The meeting point is MassDOT’s District 5 office, 1000 County Street (Route 140), Taunton, MA. Those who wish to view the site shall email John Fallon at [email protected], by 10:00AM Wednesday, March 27, 2019 and supply the names and identification of their representatives to be placed on a list of authorized personnel to accompany Mass DOT staff. The site visit will be conducted under the terms and conditions stipulated by the District. The individuals attending the site visit shall bring and wear personal protective equipment (hard hats, safety glasses, reflectorized vests, and safety footwear). The site visit will not be repeated – however, it is not mandatory. Prior to the site visit, a safety briefing will be held at 7:30 AM (7:00 AM sign-in) in the training building located in the back-parking lot of the MassDOT District 5 Office to discuss on track safety details. Each participant shall participate in this safety briefing before visiting the site.

*** THIS PAGE IS INTENTIONALLY LEFT BLANK *** Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704 ③ Addendum No. 3, March 19, 2019 TABLE OF CONTENTS

VOLUME 1

DOCUMENT 00010 TABLE OF CONTENTS ...... 00010-1 through 4 DOCUMENT 00102 ③ NOTICE TO CONTRACTORS ...... 00102- 1 through 4 DOCUMENT 00210 REQUIREMENTS OF MASSACHUSETTS GENERAL LAWS CHAPTER 30, SECTION 39R; CHAPTER 30, SECTION 39O ...... 00210-1 through 4 DOCUMENT 00331 LOCUS MAP ...... 00331-1 through 2 DOCUMENT 00439 CONTRACTOR PROJECT EVALUATION FORM ...... 00439-1 through 2 DOCUMENT 00440 SUBCONTRACTOR PROJECT EVALUATION FORM ...... 00440-1 through 2 DOCUMENT 00710 GENERAL CONTRACT PROVISIONS ...... 00710-1 through 2 DOCUMENT 00715 INTERIM SUPPLEMENTAL SPECIFICATIONS ...... 00715-1 through 32 DOCUMENT 00718 SPECIAL PROVISION FOR PARTICIPATION BY MINORITY OR WOMEN'S BUSINESS ENTERPRISES AND SERVICE- DISABLED VETERAN- OWNED BUSINESS ENTERPRISES ...... 00718-1 through 10 DOCUMENT 00761 SPECIAL PROVISIONS FOR CERTIFICATION REGARDING DEBARMENT, SUSPENSION, INELIGIBILITY AND VOLUNTARY EXCLUSION...... 00761-1 through 4 DOCUMENT 00812 MONTHLY PRICE ADJUSTMENT FOR DIESEL FUEL AND GASOLINE ...... 00812-1 through 2 DOCUMENT 00813 PRICE ADJUSTMENT FOR STRUCTURAL STEEL AND REINFORCING STEEL ...... 00813-1 through 4 DOCUMENT 00814 PRICE ADJUSTMENT FOR PORTLAND CEMENT CONCRETE MIXES ...... 00814-1 through 2 DOCUMENT 00820 THE COMMONWEALTH OF MASSACHUSETTS SUPPLEMENTAL EQUAL EMPLOYMENT OPPORTUNITY, NON-DISCRIMINATION AND AFFIRMATIVE ACTION PROGRAM ...... 00820-1 through 6 DOCUMENT 00821 ELECTRONIC REPORTING REQUIREMENTS CIVIL RIGHTS PROGRAM AND CERTIFIED PAYROLL ...... 00821-1 through 2 DOCUMENT 00859 CONTRACTOR/SUBCONTRACTOR CERTIFICATION FORM ...... 00859-1 through 2

00010 - 1 Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704

DOCUMENT 00860 COMMONWEALTH OF MASSACHUSETTS PUBLIC EMPLOYMENT LAWS ...... 00860-1 through 2 DOCUMENT 00861 STATE WAGE RATES ...... 00861-1 through 42 DOCUMENT A00801 SPECIAL PROVISIONS ...... A00801-1 through 246 DOCUMENT A00802 DETAIL SHEETS ...... A00802-1 through 12 DOCUMENT A00809 SECTION 01569 SYSTEM SAFETY CERTIFICATION TIER 2 - MBTA SYSTEM SAFETY CERTIFICATION CHECKLIST ...... A00809-1 through 14 DOCUMENT A00810 MBTA DESIGN EXCEPTION REQUEST (DER) ...... A00810-1 through 8 DOCUMENT A00811 MBTA RAILROAD OPERATIONS DIRECTORATE ...... A00811-1 through 132 DOCUMENT A00812 MBTA RAILROAD SAFETY SPECS WITH OSHA TOC ...... A00812-1 through 14 DOCUMENT A00813 MBTA SPECIAL INSTRUCTIONS ...... A00813-1 through 16 DOCUMENT A00814 MBTA / MBCR RAILROAD OPERATIONS MW-1 ...... A00814-1 through 136

VOLUME 2

DOCUMENT A00815 MBTA / KEOLIS COMMUTER SERVICES RAILROAD OPERATIONS CWR PLAN ...... A00815-1 through 38 DOCUMENT A00816 MASSACHUSETTS COASTAL RAILROAD ON-TRACK SAFETY MANUAL ...... A00816-1 through 34 DOCUMENT A00817 MASSACHUSETTS COASTAL RAILROAD CONTRACT GENERAL CONDITIONS ...... A00817-1 through 36 DOCUMENT A00818 RAILROAD FIELD REPORTS ...... A00818-1 through 10 DOCUMENT A00819 MBTA SUB-CONTRACTOR APPROVAL REQUEST FORM ...... A00819-1 through 6 DOCUMENT A00820 REQUEST FOR RELEASE OF MASSDOT AUTOCAD FILES FORM ...... A00820-1 through 2 DOCUMENT A00830 U.S. ARMY CORPS OF ENGINEERS GENERAL PERMIT APPLICATION ...... A00830-1 through 282

00010 - 2 Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704 ③ Addendum No. 3, March 19, 2019

DOCUMENT A00831 U.S. ARMY CORPS OF ENGINEERS GENERAL PERMIT ...... A00831-1 through 94 DOCUMENT A00840 MASSACHUSETTS DEPARTMENT OF ENVIRONMENTAL PROTECTION WATER QUALITY CERTIFICATION APPLICATION ...... A00840-1 through 282 DOCUMENT A00841 MASSACHUSETTS DEPARTMENT OF ENVIRONMENTAL PROTECTION WATER QUALITY CERTIFICATION ...... A00841-1 through 28 DOCUMENT A00870 MASSACHUSETTS DIVISION OF FISHERIES AND WILDLIFE NATURAL HERITAGE AND ENDANGERED SPECIES PROGRAM ...... A00870-1 through 72 ③ DOCUMENT A00880 TRANSPORTATION AUTHORITY BRIDGE INSPECTION REPORTS ...... A00880-1 through 96 DOCUMENT B00420 PROPOSAL ...... B00420-1 through 12 DOCUMENT B00842 SCHEDULE OF PARTICIPATION BY MINORITY OR WOMEN BUSINESS ENTERPRISE (M/WBE) ...... B00842-1 through 2 DOCUMENT B00843 MINORITY OR WOMENS BUSINESS ENTERPRISE PARTICIPATION LETTER OF INTENT ...... B00843-1 through 2 DOCUMENT B00846 M/WBE OR SDVOBE JOINT CHECK ARRANGEMENT APPROVAL FORM ...... B00846-1 through 2 DOCUMENT B00847 JOINT VENTURE AFFIDAVIT ...... B00847-1 through 4

END TABLE OF CONTENTS

00010 - 3 Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704

THIS PAGE INTENTIONALLY LEFT BLANK

00010 - 4 Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704 Addendum No. 3, March 19, 2019

NOTICE TO CONTRACTORS (Continued)

PRE BID SITE WALK THROUGH

A pre-bid site visit will be held on Thursday, March 28, 2019. The meeting point is MassDOT’s District 5 office, 1000 County Street (Route 140), Taunton, MA.

Those who wish to view the site shall email John Fallon at [email protected], by 10:00AM Wednesday, March 27, 2019 and supply the names and identification of their representatives to be placed on a list of authorized personnel to accompany Mass DOT staff. The site visit will be conducted under the terms and conditions stipulated by the District. The individuals attending the site visit shall bring and wear personal protective equipment (hard hats, safety glasses, reflectorized vests, and safety footwear). The site visit will not be repeated – however, it is not mandatory.

Prior to the site visit, a safety briefing will be held at 7:30 AM (7:00 AM sign-in) in the training building located in the back-parking lot of the MassDOT District 5 Office to discuss on track safety details. Each participant shall participate in this safety briefing before visiting the site.

00102 - 3 Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704 Addendum No. 3, March 19, 2019

THIS PAGE INTENTIONALLY LEFT BLANK

00102 - 4 Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704 ③ Addendum No. 3, March 19, 2019 ITEM 952.1 STEEL SHEETING FOOT

The work under this Item shall conform to the relevant provisions of Section 950 of the Standard Specifications and the following:

The work under this Item consist of furnishing and installing slope stability and track retaining wall steel sheeting as shown on the drawings or as required by the Engineer.

MATERIALS

Alternative size sheeting is allowed, provided that both Section Modulus and Moment of Inertia are equal to or greater than the sections recommended on the Contract Drawings. Alternative sheeting shall be reviewed and approved by the Engineer prior installation.

SUBMITTALS

During wall construction, the Contractor shall maintain and submit weekly to the Engineer, clearly written and illustrated reports documenting the Work as actually constructed. Each weekly report shall be submitted within 24 hours of the last day of the week for which the report applies (i.e., reporting period). Each weekly report shall contain all of the daily reports for the reporting period and a summary report for Work completed during the reporting period.

CONSTRUCTION

Weep holes shall be cut through the steel sheeting as shown on the Contract Drawings.

The Contractor shall install and maintain the sheet pile retaining wall system in accordance with the accepted working drawings, and in such a manner as to prevent movement, settlement, or loss of ground, removal of fines from the adjacent ground, and damage to or movement of adjacent structures and utilities.

To allow for groundwater flow through the sheeting walls, please make the following adjustments in the wall installation as shown and indicated on the Contract Drawings: ③ 1. Leave a gap in global stability walls as shown on the drawings. 2. Approximately every 50 feet along sheet pile retaining walls, drive one pair of steel sheeting to 10 to 15 feet below grade.

METHOD OF MEASUREMENT

Item 952.1 will be measured for payment by the Foot of the steel sheeting wall, complete in place.

Measurements will be taken along the Track 1 baseline and will include any gaps left in global stability sheeting as shown and indicated on the drawings.

PAYMENT AND COMPENSATION

Item 952.1 will be paid for at the Contract unit price per Foot of the steel sheeting wall, which price shall include all labor, materials, equipment, excavation, backfill, installation of the weep holes, and all incidental costs required to complete the work.

A00801 - 125 Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704

ITEM 953.31 EXCAVATION SUPPORT SYSTEM - SQUARE YARD BRIDGE NO. B-08-004 ITEM 953.32 EXCAVATION SUPPORT SYSTEM - SQUARE YARD BRIDGE NO. B-08-005

The work under these Items shall conform to the relevant provisions of Sections 140, 940, 950, 955 of the Standard Specifications and the following:

The Contractor shall design, furnish, install, maintain and remove temporary support of excavation and protection systems as schematically shown on the drawings and/or as required by the Engineer.

The limits of the excavation support systems shall be submitted for review and acceptance by the Engineer.

The Contractor shall NOT assume that all locations where excavation support and protection are needed are shown on the Contract Drawings. PERFORMANCE REQUIREMENTS

Excavation support systems shall be capable of supporting excavation sidewalls and of resisting soil and hydrostatic pressure and superimposed rail and construction loads. The Contractor shall:

1. Provide professional engineering services needed to assume engineering responsibility, including preparation of Shop Drawings and a comprehensive engineering analysis. 2. Prevent surface water from entering excavations by grading, dikes, or other means. 3. Install excavation support and protection systems without damaging existing substructure elements to temporarily remain. 4. Provide vibration monitoring. 5. Prevent impacts to adjacent structures and utilities.

Design calculations and Shop Drawings shall be prepared and sealed by a Professional Engineer registered in the Commonwealth of Massachusetts retained by the Contractor.

Review of the Contractor’s plans, design calculations, and methods of construction by the Engineer does not relieve the Contractor of the responsibility for the safe and satisfactory performance of the earth support systems.

The system of temporary support shall consist of soldier piles and lagging or steel sheet piling secured in place by means of bracing members such as wales, cross-lot or raker bracing, shores, or tieback anchors. Other methods of support may only be used when approved by the Engineer.

Where existing structures, walls, or abutments are used to brace the excavation, a complete structural investigation of the structure shall be performed, along with calculations showing the integrity of the structure can be maintained.

A00801 - 126 Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704

③ Addendum No. 3, March 19, 2019 ITEMS 953.31 and 953.32 (Continued)

Survey instruments used for vertical deformation monitoring shall have a minimum accuracy of 0.05 inch and a minimum setting accuracy of 1.0 arc seconds. Leveling staffs shall be non- telescopic in design (i.e. ‘Chicago’ style leveling staff). A bull’s eye bubble shall be used to plumb the leveling rod.

Survey instruments used for horizontal deformation monitoring shall have a minimum accuracy of 3.0 arc seconds and a minimum display reading less than or equal to the accuracy. Distances less than 30 feet shall be measured with a standardized steel tape used in conjunction with a tension handle. Distances greater than 30 feet shall be measured with an Electro-Optical Distance Measuring Instrument (EDM). Distances between 30 and 100 feet shall be verified with a standardized steel tape in conjunction with a tension handle. Electronic pointing shall be used to minimize error due to possible misalignment of the EDM axis and telescope. Centering shall be accomplished using high precision optical plummets or mechanical centering devices.

EDM equipment used for lateral deformation monitoring shall, after calibration, have a minimum accuracy of 0.02 in plus 5 parts per million.

Make adjustments to survey schedule and monitoring point locations (including the addition of monitoring points) as requested by the Engineer if additional monitoring of wall performance is desired. Extra monitoring points and increases in survey frequency shall be considered incidental to the costs associated with this Section.

The Contractor shall submit the results of the settlement point readings to the Engineer in draft form at the end of each working day. All monitoring data shall be reported to the Department and Engineer within twenty-four (24) hours of measurement in tabular format, allowing comparison of current data to previous data, including baseline, and showing a complete history of movement versus time.

The Contractor shall be responsible for the repair of any damage to the existing structure or tracks caused by the Contractor’s failure to comply with the requirements of this Section. The Department or Engineer may require the Contractor to take steps to control movements to levels which are lower, if in the opinion of the Engineer the measured or observed movements are detrimental or damaging.

BASIS OF PAYMENT

③ Item 953.31 and Item 953.32 will be measured and paid for at the respective Contract unit prices per Square Yard of exposed face of sheeting, which price shall include all labor, materials, equipment, design, submittals, plans, installation, maintenance, subsequent removal, and all incidental costs required to complete the work.

③ Payment of 70% of the Square Yard bid price will be made upon complete installation.

③ The remaining 30% of the Square yard bid price will be paid following complete removal.

A00801 - 135 Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704

ITEM 983.525 STREAMBED RESTORATION MATERIAL CUBIC YARD

The work under this Item shall conform to the relevant provisions of Section 983 of the Standard Specifications and the following:

The work under this Item consist of furnishing and installing a natural streambed restoration material over the proposed rip rap scour protection installed as part of the North and South crossings and within Culvert CV-FRN-4. The intent to is provide a natural streambed appearance, maintain aquatic and terrestrial organism passage and to enhance habitat and ecological connectivity at both crossings. The streambed material is to be installed to the depths and extents as depicted on the plans or as required by the Engineer.

MATERIAL

The natural streambed material shall consist of field stone or natural river rock similar in color and appearance to in-situ native materials. Crush stone shall not be permitted.

The natural streambed material shall approximate the following size distribution; amounts finer than each laboratory sieve (square openings) (percent by weight):

Sieve opening Percent Finer 4-inch 100% 3.5-inch 85% - 95% 2.5-inch 40% - 60% 1.25-inch 25% - 35% 0.25-inch 5% - 15%

The size of an individual stone particle will be determined by measuring its diameter across the intermediate axis. Stone particles shall be sound, tough, dense, resistant to the action of air and water, and suitable in all respects for the purpose intended. Gravel fill may contain small amounts of fine aggregate but shall contain no amounts of soil material.

All gravel fill shall be approved by the Engineer prior to furnishing and stockpiling of materials on site.

CONSTRUCTION

Cotley River Bridges

The Contractor shall install a 8-inch thick layer of streambed material over a 3-ft thick layer of riprap, as depicted on the plans or as required by the Engineer. The material shall be installed during dewatered conditions and in accordance with the environmental permits.

A00801 - 136 Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704

③ Addendum No. 3, March 19, 2019 ITEM 995.042 (Continued)

Compaction within 3 ft of the back face of the wall shall be achieved by at least three passes of lightweight mechanical tamper, roller, or vibratory system.

At the end of each day’s operation, the Contractor shall slope the last lift of the backfill away from the wall facing to rapidly direct runoff away from the wall face. In addition, the Contractor shall not allow surface runoff from other areas to enter the wall construction site. Ponding of water behind the proposed wall during wall construction shall not be allowed.

As-Built Construction Tolerances

Vertical alignment: ± 1/2" over any 10' distance. Wall Batter: within 2 degrees of design batter. Horizontal alignment: ± 1/2" over any 10' distance. Corners, bends, curves: ± 1 feet to theoretical location. Maximum horizontal gap between erected units shall be 1/2 inch.

COMPENSATION

Method Of Measurement

③ Item 995.042 will be measured for payment by the Foot, complete in place. The measurements of the wall will be taken along of the front face of the wall installed.

Basis Of Payment

Item 995.042 will be paid for at the Contract unit price per Foot, which price shall include all labor, materials, equipment, design work, preparation of written submittals and plans, revision of submittals, sample submittals, transportation, reinforcing elements, bearing blocks, shims, railing, joint materials, concrete masonry, reinforcing steel, drainage material including crushed stone, underdrain pipe, geotextile fabric, cleanouts (frame and cover castings), flared end sections, excavation and preparation the wall foundation, placing the leveling pad, wall drainage, erect the PM block wall to the lines and grades shown on the Plans, install the joint materials, install railing, place and compact backfill, and construct any other items necessary to complete the PM block wall, temporary shoring, and all incidental costs required to complete the work.

Payment for excavation, water control and incidentals to complete the excavation are included in the modular block wall item.

A00801 - 225 Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704

ITEM 997.01 TRACK STRUCTURE FOOT ITEM 997.02 NO. 10 LEFTHAND TURNOUT, BRIDGE NO. B-08-004 EACH ITEM 997.03 NO. 10 RIGHTHAND TURNOUT, BRIDGE NO. B-08-005 EACH

The work under these Items shall conform to the relevant provisions of Sections 120, 150, 170, and 400 of the Standard Specifications and the following:

The Contractor shall perform all work in accordance with applicable recommended practices set forth in the current American Railway Engineering and Maintenance of Way Association Manual for Railway Engineering 2014 (AREMA Manual), MBTA Railroad Operations Directorate, MBTA “Railroad Operations Book of Standard Plans Track and Roadway”, and MBTA’s “Railroad Operations Commuter Rail Design Standards Manual”.

Access MBTA information related to construction, design/engineering, manuals, and publications and Forms at: https://www.mbta.com/engineering or http://bc.mbta.com/business_center/bidding_solicitations/design_and_construction/?id=22072&t itle=MBTA Contract Guidlines.com

The work shall include dismantling, removal and salvage of existing track, stockpile or disposal of materials, fine grading and compacting subgrade, furnishing, delivering, and placing of ballast stone, construction of new continuously welded rail track including furnishing and installation of all track materials and connections, tamping, surfacing, and aligning of track, ballast stabilization, and furnishing and installation of bridge guard rail. The Contractor shall install No.10 Lefthand turnout and No. 10 righthand turnout. No. 10 Left-Hand and No. 10 Right-Hand Turnouts will be procured and delivered by the operating railroad, MCRR.

The work consists of three separate track segments on the New Bedford Mainline, respectively located in Berkley, Lakeville, and Freetown, MA. The New Bedford Main Line work includes installation of new 136 lb. Continuously Welded Rail (CWR) between Sta. 2048+00.00 to Sta. 2091+50.00, Sta. 2205+12.82 to Sta. 2240+00.00, and Sta. 2394+14.83 to Sta. 2405+09.70.

The Contractor shall submit to the Engineer for approval a prepared sequence of operations including descriptions of the following: details and sequences of construction activities including track dismantling and stockpile, material handling and delivery, ballast installation and supply, wood crosstie installation and supply, installation of Continuously Welded Rail (CWR) and other track materials, surfacing and alignment, bridge guard rail installation, surfacing and aligning existing track at tie-in points, and production equipment. The Contractor shall also submit identity and location of licensed incinerator and landfill facilities proposed for crosstie disposal, submit copies of certified weight slips for each quantity of crossties shipped, unloaded, and properly disposed of at the licensed facility, submit name and location of rail supplier along with manufacturer’s catalog cut and specifications for rail, submit identity and location of treated wood crosstie supplier with certified inspection mills and test reports, submit name and location of proposed ballast supplier, submit name and manufacturers’ catalog cuts and specifications, and submit certified inspection and test reports for every 1,000 tons of subballast and ballast stone, joint bars and fastenings, standard ties plates, rail anchors, resilient tie plates and fasteners, joint bar fasteners, weld on shoulders for guardrail rail seats, and screw spikes prior to shipment, submit manufacturers’ catalog cuts for rail expansion shims and joint lubricant, submit the type and specifications of rail thermometer and equipment to be used in placing, compacting, and tamping ballast, and aligning track, submit tapes or graphs as specified from tamper/liner.

A00801 - 226 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019

FINAL Avoidance and Protection Plan Braley Cemetery (FRE.823) Freetown South Coast Rail Project, Phase 1

MassDOT has developed an avoidance and protection plan for potential impacts to the historic Braley Cemetery in Freetown (MHC #FRE.823), aka the Braley’s Station Cemetery.1 The cemetery is bisected by the New Bedford Main Line railroad right-of-way (ROW) (active MassCoastal freight line) between East Chipaway Road in Freetown and the Freetown-New Bedford town line. Project work in the section of the New Bedford Main Line ROW between Station (STA) 2527+00 and STA 2535+00 consists of the replacement of an existing culvert (CV-FRN-12) and improvements to the existing single-track structure (Figures 1 and 2).

Previous Investigations

The 2001 archaeological reconnaissance survey for the New Bedford/Fall River Commuter Rail Extension Project identified the presence of the recorded Braley Cemetery along the New Bedford Main Line railroad ROW in Freetown (Cherau et al. 2001). The origins of the cemetery were unknown and it was suggested that burials could pre-date the 1840 opening of the Old Colony Railroad from Weir Junction in Taunton through Freetown to New Bedford (Cherau and Banister 2009). Because of the potential for marked and unmarked burials adjacent to the ROW embankments, the 2001 report recommended avoidance and protection/stabilization measures in the area of the historic cemetery during construction activities for the new commuter railroad service. The 2009 reconnaissance survey for the South Coast Rail Project confirmed the 2001 survey assessment and continued to recommend the development of avoidance and protection/stabilization measures for the historic Braley Cemetery in Freetown to ensure that the cemetery is preserved during and post- construction work for improvements to the track structure in the railroad ROW.

In 2013 following Section 106 consultation among the US Army Corps of Engineers (USACE) Massachusetts Historical Commission/State Historic Preservation Office (MHC/SHPO), and MassDOT for the South Coast Rail Project, additional documentary research including land evidence records was undertaken for the Braley Cemetery to more fully define the historical and modern boundaries of the cemetery on both sides of the contemporary railroad ROW (Cherau et al. 2013). The additional research determined that the historic cemetery on both sides of the ROW was established prior to the construction of the New Bedford and Taunton Railroad in 1839–1840. The northern and southern boundaries of the cemetery abutting the railroad ROW are depicted on a 1915 railroad valuation map; these boundaries roughly correspond to the modern assessor’s map for Lots 29.01 and 31 (Braley East and West Cemetery lots, see below). The 2013 report recommended that the Project avoid impacts outside of the current railroad ROW cut/cemetery embankments using the Town’s assessor map lot lines and 1915 railroad valuation map cemetery boundaries, and that the design provide for protection/stabilization measures along the cemetery-ROW property lines during and following project construction activities.

1 The cemetery lots on both sides of the railroad ROW have continued in active use for burials (2012 on the west side and 2016 on the east side – see below).

A00831 - 9 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019

Existing Conditions/Cemetery History2

The historic Braley Cemetery in the MHC’s inventory (MHC #FRE.823) is comprised of three lots: Braley West (Assessor’s Lot 31); Braley East (Assessor’s Lot 29.01); and Reynolds Cemetery (Assessor’s Lot 29) (see Figure 1). All three cemetery lots are privately-owned, but the Town of Freetown Cemetery Commission takes care of grounds maintenance for the Braley East and Braley West cemetery lots.3 The Reynolds Cemetery is maintained by the private Reynold Cemetery Association and is accessed directly off East Chipaway Road. The Braley East cemetery lot is accessed through a driveway directly off East Chipaway Road. The Braley West cemetery lot is accessed through an undefined right-of-way in the yard of 7 East Chipaway Road.4

The west side of the railroad ROW is bordered by the Braley West Cemetery (so-called Braleyville Cemetery, Assessor’s Lot 31), which is rectangular in shape and encompasses 0.50 acres. Access to the cemetery is by way of East Chipaway Road through Assessor’s Lot 33. The Braley West Cemetery is referred to in “Old Cemeteries in Southeastern Massachusetts” by Charles M. Thatcher as “Cemetery at Braleys Station west of R.R.” In 2001 and 2008 the cemetery on the west side of the railroad ROW was observed to contain visible burial plots, a number of which were maintained but others that were fairly neglected and overgrown. The burials were all situated on top of a broad knoll bisected by the railroad ROW, opposite the Braley East Cemetery.

The east side of the railroad ROW is bordered by the Braley East Cemetery (so-called Braleytown Cemetery, Assessor’s Lot 29.01), which is roughly rectangular in shape and encompasses 0.60 acres with direct access to East Chipaway Road. The Braley East Cemetery is referred to in “Old Cemeteries in Southeastern Massachusetts” by Charles M. Thatcher as “Cemetery at Braleys Station east of R.R.” In 2001 and 2008 the cemetery on the east side of the railroad ROW was observed to contain visible burial plots, several of which at the top of the hill were within 15 feet (ft) of the cut embankment and stone retaining wall abutting the tracks. At that time, it was observed that some of the burial plots were well maintained while others were fairly neglected and overgrown, similar to those on the west side of the railroad ROW.

Braley West (Lot 31) and Braley East (Lot 29.01) form the cemetery on either side of the railroad ROW historically known as Braley’s Station Cemetery, which was established in 1841 and as of 2013 contained 150 burials (Cherau et al. 2013).5 An anonymous, undated transcript on file at the Old Colony Historical Society describes the cemetery as “in a field about 75 feet south of Chippeway Road in East Freetown. Both east and west of railroad about 200 feet south of the former site of the Braley’s Railroad Station in East Freetown, fairly well kept. No wall.” (Anon. n.d.). The transcript includes 116 names of interred persons, the earliest dating from 1817 (William S. Westgate) and the latest to 1950 (Donald Cornell) on the east side of the railroad ROW; and the earliest 1842 (Susan G. Lucas) and latest 1949 (Harry L. Woodis) on the west side of the railroad ROW. Cemetery records on file at the Freetown Historical Society and Freetown Cemetery Commission indicate the known date range of burials on the east side of the ROW to be 1845 (Mary Pittsley) to 2009 (Edna Warwick,

2 The existing conditions/cemetery history are taken from the Cultural Resources Reconnaissance Survey Technical Report, South Coast Rail Project, Volume II-Archaeological Resources Survey Results (Cherau and Banister 2009:22-25) and Intensive (Locational) Archaeological Survey, Stoughton and Whittenton Alternatives, South Coast Rail Project Technical Report (Cherau et al. 2013:193-2002). 3 Information provided by Mike McCue, Chairman and Superintendent of Public Cemeteries, Town of Freetown Cemetery Commission, August 2018. 4 Access confirmed by Mike McCue, Freetown Cemetery Commission, August 2018. 5 Findagrave.com (2018) indicates both Braley West and Braley East cemetery lots have continued to be actively used, with the most recent burial in 2012 (Wallace Woodis Jr.) in Braley West and in 2016 (Dexter R. Cornell) in Braley East.

A00831 - 10 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019

née Pittsley); the 1817 date was corrected to 1847 for William Westgate. The 2001 reconnaissance survey for the South Coast Rail Project identified a burial dating to 1984 on the east side of the ROW (Cherau et al. 2001), although this burial may be situated on the adjacent Reynolds Family Cemetery lot. For the west side of the cemetery (west side of the ROW), the historical society and cemetery commission records provide a date range of burials from 1841 (Betsey Gibbs) to 1999 (Charles Perry). Charles’ mother, Viola E. (Westgate) Perry, was also buried in Braley West in 2006.

The 2013 research produced documentary records suggesting that the cemetery was established prior to the construction of the New Bedford and Taunton Railroad, which was chartered in 1839 and completed in July 1840 (Karr 1995). The NYNHH Railroad Company 1915 valuation map for the section of ROW south of Braley Road (present East Chipaway Road) indicates that two cemetery strips of land (designated parcels 22 and 23 on the map) within the ROW were “titled” to the railroad on April 9, 1840 and October 14, 1879. Land evidence records indicate that the cemetery was used by members of the Braley, Reynolds, Pittsley, Westgate, and Wilbur families, who lived in this section of East Freetown in the nineteenth century. The 1915 railroad valuation map identifies the cemetery to either side of the ROW, and the northern and southern boundaries at that time roughly correspond to the modern assessor’s map for Lots 29.01 and 31. Deed records indicate that Daniel Westgate of East Freetown had ownership of the Braley West (Braleyville) cemetery in the 1870s; there are no other records of burial plot or lot ownership, and there is no known plan of either the Braley West or Braley East cemetery lots (Cherau et al. 2013).

Barbara Cole, local Freetown historian, reported in 2001 that Braley’s Station Cemetery may have been founded by the South Freetown Branch of the Dartmouth Baptist Church for their congregation (founded in 1805). The Baptist Church was located on the east side of Braley Road just north of the crossroad with Chipaway/East Chipaway Road, and was reorganized as the Braley Station Advent Christian Church in 1884. The church/congregation was abandoned before the 1940s, and then reopened following repairs in the early 1950s by the South Christian Church of All Nations. In 2001 the church building and grounds were acquired by the Church of the New Beginning (still extant) (Barcellos 2001). It is possible that permission(s) for the railroad to lay tracks through the cemetery lands to complete the ROW connection were decided by town or church vote, and not necessarily through deeded land transfers, although no information on the cemetery has been found in town records for the period from the 1830s through the 1870s (M. McCue, personal communication 2013 in Cherau et al. 2013).

A third cemetery lot (Assessor’s Lot 29) is on the east side of the railroad ROW, bordering East Chipaway Road (chain link fence) on the north and the Braley East cemetery lot on the south. The cemetery lot contains about 0.39 acres. It is owned by the Reynolds Cemetery Association, and is locally known as the Reynolds Cemetery. According to land evidence records and the Freetown Cemetery Commission, the Reynolds Cemetery was established in 1946 for use as a private family cemetery. There is no mention of a cemetery on the lot in any of the nineteenth-century property deeds reviewed as part of the 2013 documentary research (Cherau et al. 2013). In 2013 the Reynolds Cemetery Association, c/o Richard Pittsley, was identified as the owner and caretaker of Lot 29.

Proposed Construction Work

MassDOT’s 401/404 permit application project plans for the State of Good Repair Culvert & Bridge Replacement, MassDOT Freight Lines, include the replacement of an existing culvert (CV-FRN-12) that runs transverse to the ROW and carries a small natural stream under the track structure on the south side of the cut railroad embankment where the visible cemetery markers are located. The culvert work involves removing the existing 1.5-foot (ft)-x-3-ft stone box culvert, pipe, and headwalls, and replacing it with a 6-ft-x-7-ft concrete box culvert (see Figure 2). The limit of grading and excavations

A00831 - 11 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019

for the removal of the existing culvert and installation of the new structure will extend east and west into the existing tree line in the railroad ROW.

The 30% design track plans for the New Bedford Main Line ROW indicated the improvements to the track structure through the historic cemetery will involve adding underground drainage pipes to both sides within 10 ft of the center line from STA 2527+00 to STA 2530+00. The pipes will extend from 2 to 4 ft below the existing grade. The proposed track work will not extend horizontally to the edge of the cemetery embankment, although the 30% design proposed a new ornamental fence along the existing stone retaining wall bordering the cemetery on the north side of the track (see Figure 1).

Avoidance and Protection Measures During Construction

MassDOT, in consultation with USACE and the SHPO, is proposing the following phased measures to ensure the protection of the cemetery lots including the historic Braley Cemetery in Freetown during the culvert replacement construction work in the fall 2018 and track structure improvements construction work starting in the fall of 2020.

Culvert Replacement

Protective Fencing and Signage

During culvert construction mobilization, the contractor will install high visibility (temporary) orange construction fencing along the limit of grading and limit of work/erosion control for the culvert replacement as depicted on the Culvert Plan and Profile Sheet (TD/324) (see Figure 2). MassDOT’s archaeological consultant will inspect the locations of the protective fencing on both sides of the track structure in the railroad ROW prior to the start of construction excavations for the removal of the existing culvert. Signs will be placed on the orange construction fencing that indicate SENSITIVE RESOURCE AREA ACTIVE/HISTORIC CEMETERY SITES– NO ACCESS ALLOWED.

The temporary protective fencing will be removed by the contractor at the completion of the culvert replacement construction work.

Archaeological Monitoring

MassDOT’s archaeological consultant will monitor construction excavations for the removal of the existing culvert structure and grading needed for the installation of the new culvert and headwalls at both sides of the track structure. Should any grave stones or human remains be uncovered during the excavations, the Project’s Post-Review Discoveries Plan Including Human Remains, to be developed and implemented in accordance with Stipulation V of the Project’s Programmatic Agreement, consistent with the Massachusetts Unmarked Burial Law (Massachusetts General Laws, Chapter 38 § 6; Chapter 9, §§ 26A and 27C; and, Chapter 7, § 38A; all as. amended), will be followed.

Track Structure Improvements

During the track structure construction mobilization, the contractor will install high visibility (temporary) orange construction fencing along the limit of grading and limit of work/erosion control as depicted on the 30% Track Plan and Profile Sheet (TK-3055) (see Figure 1) and depicted on the corresponding 90% and final design plan sheets (Figure 3). MassDOT’s archaeological consultant will inspect the locations of the temporary protective fencing on both sides of the railroad ROW prior to the start of track construction work. Signs will be placed on the orange construction fencing that

A00831 - 12 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019

indicate SENSITIVE RESOURCE AREA ACTIVE/HISTORIC CEMETERY SITES– NO ACCESS ALLOWED.

Construction Plans and Documents

The following guidelines will be followed in developing text for specifications or notes in contract and construction bid documents for both the 2018 culvert replacement construction work and for the subsequent track structure improvements work to prevent inadvertent impacts to the three cemetery lots. Digital Geographic Information System (GIS) information representing the location of the high visibility construction fencing will be recorded on all relevant construction plan sheets used in the contractor bid documents.

• The fenced areas will be placed on construction plans by MassDOT as a “Sensitive Resource Area Active/Historic Cemetery Sites No Access/No Impact.” Construction plans should include notes specifying that no excavation or grading should take place within the limits of the sensitive resource area.

• MassDOT’s archaeological consultant will meet on-site prior to construction and brief construction personnel on the nature of the sensitive resource areas and coordinate construction protocols in proximity to it, if necessary.

No ground disturbance or construction will take place outside the high visibility fencing placed along the railroad ROW in the area of the three cemetery lots.

MassDOT will indicate the location of the sensitive cemetery resource areas on the contractor bid documents for the culvert replacement construction work and on the contractor bid documents for the track structure improvements construction work. The bid documents should include notes specifying that the Sensitive Resource Areas (Active/Historic Cemetery Sites) on both sides of the railroad ROW are to be avoided during all stages of the construction process from initial site preparation to final grading and restoration. Construction documents and contracts will include suitable language to prevent inadvertent disturbance or impacts to the Sensitive Resource Areas (Active/Historic Cemetery Sites). Construction contractors and personnel should be informed in writing and verbally that all fenced areas are a “no impact zone.” No construction, excavation, grading, filling, dumping, or storage of vehicles, equipment, or materials and supplies should occur within the fenced Sensitive Resource Areas (Active/Historic Cemetery Sites).

Post-Construction Protection, Inspection, and Reporting

MassDOT will indicate the location of the three cemetery lots including the historic Braley Cemetery on their “as-built” drawings of the New Bedford Main Line railroad line in Freetown. This is so that MBTA commuter rail operation and maintenance (O&M) personnel conducting future maintenance or construction activities in the areas on both sides of the track will be aware of the active/historic cemeteries in this area and appropriate precautions can be initiated. In addition to “SENSITIVE RESOURCE AREA ACTIVE/HISTORIC CEMETERY SITES,” language recommending “consultation with MBTA compliance personnel for further information” will be included.

Following the completion of the South Coast Rail Project Phase 1 construction work for the track structure improvements in the vicinity of the active/historic cemetery lots, the temporary orange construction fencing will be removed by the contractor and permanent security/safety fencing will be installed along the railroad ROW in accordance with MBTA ROW safety specifications. The permanent fencing locations will be depicted on the 90% and final design plans. The permanent

A00831 - 12 .1 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019

fencing will be made of black rust-proof chain-link material or material of similar aesthetic appearance.

• Braley East cemetery lot (east side of the railroad ROW): the permanent fencing will extend from East Chipaway Road south to the Freetown-New Bedford town line. At the new box culvert (CV-FRN 12) the fence will tie into the wingwalls and railing. The fence will pass on top of the existing masonry wall to replace an existing wood post and rail fence placed in this area by the Freetown Cemetery Commission.

Because graves are known to extend to the interior side of the masonry wall, the new fence posts will be anchored to the top of the wall and not into the adjacent soils.

• Braley West cemetery lot (west side of the railroad ROW): the permanent fencing will extend from East Chipaway Road south to the Freetown-New Bedford town line, with a break along its alignment to avoid impacting existing wetlands. The wetlands will provide a natural barrier to the ROW and cemetery in lieu of a fence.

The permanent fencing will forestall any inadvertent or future use by MBTA personnel of lands associated with the cemetery lots adjacent to the railroad ROW for additional workspace, access routes, or other appurtenances and facilities. The permanent ROW fence will also discourage unauthorized pedestrian or vehicle crossing of the railroad tracks by local residents and town maintenance personnel, as agreed to by the Freetown Cemetery Commission.

MassDOT’s archaeological consultant will conduct a post-construction inspection of the permanent ROW fencing including photographic documentation of the railroad ROW track and culvert work areas along the historic Braley Cemetery and will provide that information in a letter report to the MassDOT and MHC once the Project has been completed.

References

Cherau, Suzanne G., Alan Leveillee, and Holly Herbster 2001 Archaeological Reconnaissance Survey, New Bedford/Fall River Commuter Rail Extension Project, Canton, Stoughton, Easton, Raynham, Taunton, Berkley, Lakeville, Freetown, Fall River, and New Bedford, Massachusetts. The Public Archaeology Laboratory, Inc. Report No. 935-1. Submitted to Massachusetts Bay Transportation Authority, Boston, MA, and Vanasse Hangen and Brustlin, Inc., Watertown, MA.

Cherau, Suzanne and Jennifer Banister 2009 Cultural Resources Reconnaissance Survey, South Coast Rail Project, Volume II: Archaeological Resources Survey Results, Southeast Massachusetts, March 2009. The Public Archaeology Laboratory, Inc. Report No. 2266. Submitted to Vanasse Hangen Brustlin, Inc., Boston, MA.

Cherau, Suzanne, Jenifer Elam, and Jennifer Banister 2013 Intensive (Locational) Archaeological Survey, Stoughton and Whittenton Alternatives, South Coast Rail Project, Easton, Raynham, Taunton, Freetown, Fall River, New Bedford, Massachusetts. The Public Archaeology Laboratory, Inc. Report No. 2266.01. Prepared for Vanasse Hangen Brustlin, Inc., Boston, MA.

A00831 - 12 .2 Proposal No. 609200-106704 .3 A00831 - 12 Addendum No. 3, March 19, 2019

Figure 1. Avoidance and protection plan fencing along the New Bedford Main Line ROW during culvert replacement and track improvements, historic Braley Cemetery (FRE.823), Freetown, South Coast Rail Project-Phase 1 30% Design Plan. Proposal No.609200-106704 .4 A00831 - 12 Addendum No.3,March19,2019

Figure 2. Detail of avoidance and protection fencing during culvert replacement work at the historic Braley Cemetery (FRE.823), Freetown, South Coast Rail Project-Phase 1.

Proposal No. 609200-106704 .5 A00831 - 12 Addendum No. 3, March 19, 2019

Figure 3. 90% Design Plan showing construction notes and avoidance and protection fencing along the New Bedford Main Line ROW during track improvements, historic Braley Cemetery (FRE.823), Freetown, South Coast Rail Project-Phase 1. Proposal No. 609200-106704 Addendum No. 3, March 19, 2019

THIS PAGE INTENTIONALLY LEFT BLANK

A00831 - 12 .6 Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704 Addendum No. 3, March 19, 2019 DOCUMENT A00880

MASSACHUSETTS BAY TRANSPORTATION AUTHORITY

BRIDGE INSPECTION REPORTS

Assonet River Bridge LAKEVILLE, MA BRIDGE NO. L-01-018; BIN NO. BE7; MILE POST 18.60 STRUCTURE NO. L01018BE7DOTRRO

Cotley North Bridge BERKLEY, MA BRIDGE NO. B-08-004; BIN NO. BG3; MILE POST 15.17 STRUCTURE NO. B08004BG3DOTRRO

Cotley South Bridge BERKLEY, MA BRIDGE NO. B-08-005; BIN NO. BG4; MILE POST 15.70 STRUCTURE NO. B08005BG4DOTRRO

Fall Brook Bridge FREETOWN, MA BRIDGE NO. F-09-028; BIN NO. BE8; MILE POST 21.65 STRUCTURE NO. F09028BE8DOTRRO

A00880 - 1 Massachusetts Department Of Transportation Highway Division Proposal No. 609200-106704 Addendum No. 3, March 19, 2019

THIS PAGE IS INTENTIONALLY LEFT BLANK

A00880 - 2 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019

0$66$&+86(776%$<75$163257$7,21$87+25,7<

%5,'*(,163(&7,21



1(:%(')25'0$,1/,1(29(5$6621(75,9(5 &('$56:$03  /$.(9,//(0$ %5,'*(12/ %,112%( 0,/(3267 6758&785(12/%('27552

35(3$5('%< 9$1$66(+$1*(1%5867/,1,1& :DOQXW6WUHHW :DWHUWRZQ0DVVDFKXVHWWV

'(&(0%(5

A00880 - 3 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019  /DNHYLOOH $VVRQHW5LYHU &HGDU6ZDPS  %ULGJH1R/

 7$%/(2)&217(176

6(&7,21 3$*(

/2&$7,210$3 

'(6&5,37,212)%5,'*( 

7<3,&$/%5,'*((/(9$7,21$1'&52666(&7,21

7<3,&$/%5,'*(3/$1 

,163(&7,21),1',1*6$1'5(&200(1'$7,216 

$9$,/$%/(3/$16 

$33(1',;$,163(&7,21)2506),(/'127(6$1'3+2726$

$33(1',;%6758&785(,19(1725<$1'$335$,6$/)250%



2 A00880 - 4 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019  /DNHYLOOH $VVRQHW5LYHU &HGDU6ZDPS  %ULGJH1R/

 /2&$7,210$3

 3 A00880 - 5 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019  /DNHYLOOH $VVRQHW5LYHU &HGDU6ZDPS  %ULGJH1R/

 '(6&5,37,212)%5,'*(

'DWHRI&RQVWUXFWLRQ 3DUWLDOO\UHFRQVWUXFWHGLQ

2ULJLQDO'HVLJQ/RDGLQJ 8QNQRZQ

%ULGJH7\SH 7LPEHU6WULQJHU

6NHZ 'HJUHHV

6SDQV 7ZR  VSDQFRQWLQXRXVDW¶´ VRXWK DQG¶´ QRUWK  FWRFRIEHDULQJV

:LGWKRI%ULGJH'HFN ¶´LQFOXGLQJZDONZD\

7UDFN6XUIDFH 2QH  WUDFNZLWKMRLQWHGUDLORQRSHQWLPEHUGHFN

6LGHZDON:DONZD\0HGLDQ 6WHHOJUDWLQJRQHDVWIDVFLD

%ULGJH5DLOLQJ ¶´ZHOGHGWZRUDLOVWHHO

6XSHUVWUXFWXUH (LJKW  QHVWHGWLPEHUVWULQJHUVLQJURXSVRIIRXU  VWULQJHUV IRXUVWULQJHUVXQGHUHDFKUDLO 

0RGLILFDWLRQVWR (QWLUHO\UHSODFHG 2ULJLQDO6XSHUVWUXFWXUH

8WLOLWLHV 1RQHQRWHG

6XEVWUXFWXUH 7LPEHUEHQWV DEXWPHQWVDQGSLHU IRXQGHGRQWLPEHUSLOHV

0RGLILFDWLRQVWR 3DUWLDOO\UHSODFHGUHSDLUHG 2ULJLQDO6XEVWUXFWXUH





 4 A00880 - 6 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019  /DNHYLOOH $VVRQHW5LYHU &HGDU6ZDPS  %ULGJH1R/

 7<3,&$/%5,'*((/(9$7,21$1'&52666(&7,21                     

 5 A00880 - 7 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019  /DNHYLOOH $VVRQHW5LYHU &HGDU6ZDPS  %ULGJH1R/

 7<3,&$/%5,'*(3/$1

 6 A00880 - 8 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019  /DNHYLOOH $VVRQHW5LYHU &HGDU6ZDPS  %ULGJH1R/

 ,163(&7,21),1',1*6$1'5(&200(1'$7,216

0,/(3267 0HDVXUHGIURPWKH-XQFWLRQZLWKWKHH[LVWLQJSKRUHOLQHLQ$WWOHERUR 

,163(&7,21),1',1*6

7KHEULGJHDW03RYHU$VVRQHW5LYHU &HGDU6ZDPS LVDWZRVSDQWLPEHUVWULQJHUVWUXFWXUH ZLWKDQRSHQGHFN7KHVLQJOHWUDFNVXSHUVWUXFWXUHLVVXSSRUWHGE\WLPEHUDEXWPHQWVDQGDWLPEHU SLHUFRQVLVWLQJRIWLPEHUEHQWVIRXQGHGRQWLPEHUSLOHV7KHUHLVD¶´VWHHOJUDWLQJZDONZD\RQ WKHHDVWVLGHRIWKHEULGJHVXSSRUWHGE\RXWULJJHUEULGJHWLPEHUV

7KHVWUXFWXUHFRQVLVWVRIHLJKW  QHVWHGWLPEHUVWULQJHUVZLWKIRXU  VWULQJHUVEROWHGWRJHWKHUDQG FHQWHUHGXQGHUHDFKUDLO6WULQJHUJURXSVDUHVSDFHGDWDSSUR[LPDWHO\¶´FHQWHUWRFHQWHU7KH VWULQJHUVDUH´ZLGHDQG´GHHSDQGDUHFRQWLQXRXVRYHUWKHSLHU7KHVRXWKVSDQLV¶´EHWZHHQ FHQWHUOLQHVRIEHDULQJDQGWKHQRUWKVSDQLV¶´EHWZHHQFHQWHUOLQHVRIEHDULQJ7KHVWULQJHUVEHDU GLUHFWO\RQWKHVXEVWUXFWXUH

7KH DEXWPHQWV DQG WKH SLHU DUH WLPEHU EHQWV FRQVWUXFWHG RI WLPEHU SLOHV DQG D WLPEHU FDS 7KH VXEVWUXFWXUHLVQRUPDOWRWKHWUDFNFHQWHUOLQH ]HURGHJUHHVNHZ :LQJZDOOVDUHFRQVWUXFWHGRXWRI WLPEHUODJJLQJ7KHEDFNZDOOLVD´WKLFNVKHHWRIWLPEHUWKDWDSSHDUVWRUXQWKHIXOOGHSWKRIWKH DEXWPHQWDQGGRXEOHVDVDEDOODVWUHWDLQHU

)RUWKLVLQVSHFWLRQWKHEULGJHRULHQWDWLRQIRUWKHDSSURDFKHVDQGDEXWPHQWVDUHQRUWKDQGVRXWK7KH WLPEHUVWULQJHUVDUHQXPEHUHG6WKURXJK6IURPZHVWWRHDVW

$W WKH WLPH RI LQVSHFWLRQ WKHUH ZHUH QR SODQs available IRU WKH H[LVWLQJ EULGJH 3ODQV DUH DYDLODEOHIRUWKHEULGJHRULJLQDOO\FRQVWUXFWHGDWWKLVORFDWLRQDQGLQGLFDWHWKDWWKHRULJLQDOEULGJH ZDVFRQVWUXFWHGLQ7KHEULGJHZDVSDUWLDOO\UHFRQVWUXFWHGLQFOXGLQJWKHHQWLUHVXSHUVWUXFWXUH DQGSRUWLRQVRIWKHVXEVWUXFWXUHLQDIWHUUHFRPPHQGDWLRQVPDGHWRFORVHWKHEULGJHIURPWKH SUHYLRXV LQVSHFWLRQ SUHIRUPHG E\ 9+% LQ -XQH RI  7KH GHVLJQ OLYH ORDG IRU WKH FXUUHQW VXSHUVWUXFWXUHLVXQNQRZQ

,7(0±'(&.

7KHEULGJHGHFNLWHPVZHUHIRXQGWREHLQJRRGFRQGLWLRQ7KHWLHVDUHLQJRRGFRQGLWLRQDQGWKHUDLO IDVWHQHUV DUH DOO SUHVHQW DQG LQ SODFH 7KH ZDONZD\ RQ WKH HDVW VLGH RIWKHEULGJHLVDOVRLQJRRG FRQGLWLRQZLWKPLQRUVXUIDFHUXVWRQWKHUDLOLQJ

,7(0±683(56758&785(

7KHVWULQJHUVDUHDOOLQYHU\JRRGFRQGLWLRQ7KHEROWVDWWKHFRQQHFWLRQVDUHDOOQHZ7KHEHDULQJ DUHDVDUHLQYHU\JRRGVKDSH7KHUHZHUHQRGHILFLHQFLHVQRWHGWRWKHVXSHUVWUXFWXUH



 7 A00880 - 9 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019  /DNHYLOOH $VVRQHW5LYHU &HGDU6ZDPS  %ULGJH1R/



,163(&7,21),1',1*6$1'5(&200(1'$7,216

,7(0±68%6758&785(

7KHDEXWPHQWVDUHLQYHU\JRRGFRQGLWLRQ7KHVWHPVEDFNZDOOVEULGJHVHDWVDQGSLOHVDOOKDYHQR QRWHG GHILFLHQFLHV 7KH ZLQJZDOOV DSSHDU WR EH SDUWLDOO\ UHSDLUHG KRZHYHU DUH VWLOO RQO\ LQ VDWLVIDFWRU\ FRQGLWLRQ 7KH\ VWLOO DSSHDU WR EH WLOWHG VOLJKWO\ IRUZDUG 7KHUH LV QR HURVLRQ RU VHWWOHPHQWDSSDUHQWDWHLWKHUDEXWPHQW

7KHSLHULVLQJRRGFRQGLWLRQ7KHFDSEHDPLVLQYHU\JRRGFRQGLWLRQZLWKQRGHILFLHQFLHVQRWHG 7KHPDMRULW\RIWKHSLOHVDUHDOVRLQYHU\JRRGFRQGLWLRQKRZHYHUWKHZHVWHUQPRVWSLOHKDVYHUWLFDO VSOLWUXQQLQJWKHOHQJWKRIWKHSLOHEXWZDVVWLOOUDWHGDVLQJRRGFRQGLWLRQ7KHUHZDVPLQRUVFRXU XQGHUWKHWLPEHUSLOHFDSEXWQRVHWWOHPHQWZDVQRWHG

,7(0±&+$11(/ &+$11(/3527(&7,21

7KHFKDQQHOLVLQIDLUFRQGLWLRQ7KHUHLVKHDY\YHJHWDWLRQDURXQGWKHEULGJHDQGRQWKHDSSURDFKHV 0LQRUHURVLRQZDVQRWHGDORQJWKHHPEDQNPHQWV7KHFKDQQHOLVVNHZHGDORQJWKHHDVWVLGHRIWKH EULGJHDQGWKHUHLVPLQRUGULIWRQWKHDSSURDFKHVWRWKHEULGJHKRZHYHUQRQHGLUHFWO\DWWKHEULGJH 7KHUHLVPLQRUVFRXUXQGHUWKHWLPEHUSLOHFDSVDWERWKDEXWPHQWV

&/($5$1&(

7KHPD[LPXPYHUWLFDOFOHDUDQFHXQGHUWKHEULGJH WRWKHERWWRPRIFKDQQHO ZDVDSSUR[LPDWHO\¶ ´7KHZDWHUGHSWKZDVDSSUR[LPDWHO\¶´DWWKHWLPHRIWKHLQVSHFWLRQ

5(&200(1'$7,216

9+%UHFRPPHQGVWKHIROORZLQJ

,7(0±'(&.

1RUHFRPPHQGDWLRQVDWWKLVWLPH

,7(0±683(56758&785(

1RUHFRPPHQGDWLRQVDWWKLVWLPH

,7(0±68%6758&785(

1RUHFRPPHQGDWLRQVDWWKLVWLPH

,7(0±&+$11(/ &+$11(/3527(&7,21

1RUHFRPPHQGDWLRQVDWWKLVWLPH

 8 A00880 - 10 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019  /DNHYLOOH $VVRQHW5LYHU &HGDU6ZDPS  %ULGJH1R/



$9$,/$%/(3/$16

7KHIROORZLQJUHSRUWZDVPDGHDYDLODEOHWR9DQDVVH+DQJHQ%UXVWOLQ,QFIRUXVHGXULQJWKHEULGJH LQVSHFWLRQ

9 9DQDVVH+DQJHQ%UXVWOLQ,QF 0%7$1HZ%HGIRUG)DOO5LYHU&RPPXWHU5DLO3URMHFW 8QGHUJUDGH%ULGJH,QVSHFWLRQDQG5DWLQJ5HSRUW 1HZ%HGIRUG6HFRQGDU\/LQH%ULGJH1RRYHU$VVRQHW5LYHU 'DWHG-XO\$XJXVW

7KLVUHSRUWFRQWDLQHGDEULGJHSODQHOHYDWLRQDQGFURVVVHFWLRQWKDW9+%XVHGDVDVXSSOHPHQWWR YHULI\DQGEDFNFKHFNWKHLQIRUPDWLRQJDWKHUHGGXULQJWKHEULGJHLQVSHFWLRQVDQGILHOGLQYHVWLJDWLRQV LQ-XQH

 9 A00880 - 11 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019  /DNHYLOOH $VVRQHW5LYHU &HGDU6ZDPS  %ULGJH1R/



$33(1',;$±,163(&7,21)2506),(/'127(6$1' 3+2726



A-1 A00880 - 12 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019

MASSACHUSETTS BAY TRANSPORTATION AUTHORITY PAGE 1 OF 10

2-DIST B.I.N. STRUCTURES INSPECTION FIELD REPORT BRIDGE NO. 5 BE7 RAILROAD/TRANSIT BRIDGE INSPECTION L-01-018

4-CITY/TOWN 8-STRUCTURE No./MDPW BRIDGE No. MILE POST/T ID No. 41-STATUS INSPECTION DATE _Lakeville, MA L01018BE7DOTRRO MP 18.60 Active 12/1/2011 7-FACILITY CARRIED/LINE MEMORIAL NAME/LOCAL NAME 27-YR BUILT 106-YR REBUILT VERT. UNDERCLEARANCE _New Bedford Mainline ** 1906 2011 4'-1" 06-FEATURES INTERSECTED/BRIDGE OVER 26-FUNCTIONAL CLASS. DISTRICT BRIDGE INSPECTION ENGINEER _Assonet Rivert (Cedar Swamp) _Freight ** 43-STRUCTURE TYPE 2-OWNER 21-MAINTAINER TEAM LEADER NO. TRACKS Timber Stringer MassDOT MBTA Kris Kretsch, P.E. 1 107-DECK TYPE WEATHER TEMP. (air) TEAM MEMBERS NO. SPANS Open Deck Sunny 40 Kaleigh Rowe 2 ITEM 58 ITEM 59 ITEM 60 7_ 8 7 DECK DEF SUPERSTRUCTURE DEF SUBSTRUCTURE DEF 1. Girders, Beams or Trusses 2 1. Structural Condition 7 1. Abutments 8 a. Top Flange or Chord 8 N b. Bottom Flange or Chord 8 a. Stems 2. Ballast 6 N c. Web or Diagonals 8 b. Wingwalls d. Truss Joints N c. Backwalls 8 3. Ties 7 e. Bearing Stiffeners N d. Pedestals N f. Cross Frames, Diaphragms N e. Bridge Seat 8 4. Deck Joints N g. Knee Braces N f. Pointing N h. Pins N g. Footing H 5. Walkways 7 i. Rivets or Bolts 8 h. Erosion 6 N j. Welds i. Settlement 8 k. Conn Plt's, Gussets & Angles N 6. Drainage N j. Piles 8 l. Top Lateral Bracing N m. Bottom Lateral Bracing N 2. Piers or Bents 7 7. Fire Protection N n. Sway Frames N a. Piles 7 o. Portals N b. Footings H 8. Handrails 7 p. Hangers N c. Stem or Columns N q. Bearings 8 d. Cap Beams 8 9. Utilities N r. * e. Top of Stem or Cap 8 2. Floor Beams N f. Pedestals N 10. Approach Settlement 7 a. Top Flanges g. Diagonal Bracing N b. Bottom Flanges h. Fender System N 11. Water Proofing N c. Webs i. Erosion or Scour 6 d. Stiffeners j. Settlement 8 e. Rivets or Bolts k. Pointing N f. Welds l. g. Connections h. UNDERMINING (Y/N) If YES please explain N APPROACHES 3. Stringers N DEF COLLISION DAMAGE: a. Top Flanges None Minor Moderate Severe a. Appr. pavement condition N b. Bottom Flanges c. Webs b. Appr. Roadway Settlement N I-60 (Dive Report):N I-60 (This Report): N d. Stiffeners c. Appr. Sidewalk Settlement N e. Rivets or Bolts 93b-U/W (DIVE) INSP DATE: f. Welds d. g. Connections Any Fracture Critical Member : (Y/N) N h. Diaphragms Any Cracks in Tension Plates : (Y/N) N OVERHEAD SIGNS (Y/N) N i. Year Painted : (Attached to bridge) DEF 4. Superstructure (General) COLLISION DAMAGE: a. Paint N None Minor Moderate Severe a. Condition of Welds b. Action Under Trains N LOAD DEFLECTION: b. Condition of Bolts c. Collision Damage N None Minor Moderate Severe d. Member Alignment 8 LOAD VIBRATION: c. Condition of Signs e. * None Minor Moderate Severe X=UNKNOWN N=NOT APPLICABLE H=HIDDEN/INACCESSIBLE R=REMOVED RAIL-P1(V4)-12/00

A-2 A00880 - 13 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019 PAGE 2 OF 10 CITY/TOWN B.I.N. BR. DEPT. NO. 8-STRUCTURE NO. INSPECTION DATE

_Lakeville BE7 L-01-018 L01018BE7DOTRRO 12/1/2011 ITEM 61 ITEM 62 CULVERT & RETAINING WALLS 5 DEF DEF CHANNEL & 1. Barrel 5. Settlement CHANNEL PROTECTION DEF 2. Headwall 6. Footings 1. Channel Scour 4 3. Wingwalls 7. Adequacy of Cover 2. Embankment Erosion 5 4. Cutoff Wall 8. 3. Drift 6 ACCESSIBILITY: (Y/N/P) Needed Used 4. Channel Alignment 5 Lift Bucket N N 5. Vegetation 5 Ladder N N Boat N N 6. Rip-Rap N Wader Y Y 7. Silt 8 Inspector 50 N N Rigging N N 8. Debris in Channel 8 Staging N N 9. Traffic Control N N RR Flagger Y Y Police N N Other N N

STREAM FLOW VELOCITY: CLEARANCE POSTING: N/E S/W ft in ft in meter TOTAL HOURS: Tidal High Medium Low Not Applicable Actual Field Measurement N N N N PLANS: (Y/N) Posted Clearance N N N N N At bridge Other Advance I-61 (Dive Report): I-61 (This Report): N/E S/W N/E S/W (V.C.R.): (Y/N) N Signs in Place (Y=Yes N=No) N N N N TAPE #: 93b-U/W INSP DATE Legibility/ List of Field Tests Performed: Visibility CONDITION RATING GUIDE (for Items 58, 59, 60) GENERAL DEF 1. Clearance Signs N CODE CONDITION DEFECTS N NOT APPLICABLE 2. Rail on Bridge 6 G 9 EXCELLENT Excellent condition. G 8 VERY GOOD No problem noted. 3. Track Guard Rail N G 7 GOOD Some minor problems. F 6 SATISFACTORY Structural elements show some minor deterioration. 4. Rail Fasteners 6 F 5 FAIR All primary structural elements are sound but may have minor section loss, cracking, spalling or scour.

5. P 4 POOR Advanced section loss, deterioration, spalling or scour. Loss of section, deterioration, spalling or scour have seriously affected primary structural components. Local 6. P 3 SERIOUS failures are possible. Fatigue cracks in steel or shear cracks in concrete may be present. Advanced deterioration of primary structural elements. Fatigue cracks in steel or shear cracks in concrete C2CRITICAL may be present or scour may have removed substructure support. Unless closely monitored it may be 7. necessary to close the bridge until corrective action is taken. Major deterioration or section loss present in critical structural components or obvious vertical or horizontal C1"IMMINENT" FAILURE movement affecting structure stability. Bridge is closed to traffic but corrective action may put it back in light 8. service. 0 FAILED Out of service - beyond corrective action. 9. DEFICIENCY REPORTING GUIDE 10. A defect in a structure that requires corrective action. DEFICIENCY: CATEGORIES OF DEFICIENCIES: 11. M= Minor Deficiency - Deficiencies which are minor in nature, generally do not impact the structural integrity of the bridge and could easily be repaired. Examples include but are not limited to: Spalled concrete, Minor pot holes, Minor corrosion to steel, Minor scouring, Clogged drainage, etc. S= Severe/Major Deficiency - 12. Deficiencies which are more extensive in nature and need more planning and effort to repair. Examples include but are not limited to: Moderate to major deterioration in concrete, Exposed and corroding rebars, Considerable settlement, Considerable scouring or undermining, Moderate to extensive corrosion to structural steel with measurable loss of section, etc. C-S= Critical-Structural Deficiency - A deficiency in a structural element of a bridge that poses an extreme unsafe condition due to the failure or imminent C-H= Critical-Hazard Deficiency - failure of the element which will affect the structural integrity of the bridge. A deficiency in a component or element of a bridge that poses an extreme hazard or unsafe condition to the public, but does not impair the structural integrity of the bridge. Examples include but are not limited to: Loose concrete hanging down over traffic or pedestrians, A hole in a sidewalk that may cause injuries to pedestrians, Missing section of bridge railing, etc. URGENCY OF REPAIR: I= Immediate - [Inspector(s) immediately contact District Bridge Inspection Engineer (DBIE) to report the Deficiency and to receive further instruction from him/her]. A= As soon as possible - [Action/Repair should be initiated by District Maintenance Engineer or the Responsible Party (if not a State owned bridge) upon receipt P= Prioritize - of the Inspection Report]. [Shall be prioritized by District Maintenance Engineer or the Responsible Party (if not a State owned bridge) and repairs made when funds and/or manpower is available].

RAIL-P2(V4)-12/00

A-3 A00880 - 14 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019 PAGE 3 OF 10 CITY/TOWN B.I.N. BR. DEPT. NO. 8-STRUCTURE NO.

_Lakeville BE7 L-01-018 L01018BE7DOTRRO 12/1/2011 REMARKS & PHOTOS The Bridge at MP 18.60 is a two-span continuous timber stringer over the (Cedar Swamp) spanning approximately 10'-4" and 8'-5". Each group of stringers is spaced at 4'-11" on center and is made up of 4 timber stringers bolted together per group for a total of 8 stringers, which supports an open timber deck and carries a single track. The substructure consists of two timber abutments (timber cap/seat, backwall, and piles) and a timber bent pier (timber cap and piles). There is a 41" Catwalk along the East side of the bridge. The original date of construction was 1906, and the current bridge was partially reconstructed in 2011.

For this inspection the bridge orientation for the approaches and abutments are north and south. The timber stringers are numbered S1 through S8 from west to east.

ITEM 58 - DECK

58.1 Structural Condition (Good): No deficiencies noted.

58.3 Ties (Good): No deficiencies noted.

58.5 Walkways (Good): No deficiencies noted.

58.8 Hand Rails (Good): Minor surface rust. no other deficiencies noted.

58.10 Approach Settlement (Good): No settlement noted.

ITEM 59 - SUPERSTRUCTURE

Timber stringers S1 through S8, oriented west to east.

59.1 GIRDERS, BEAMS or TRUSSES

59.1a Top Flanges (Very Good): No deficiencies noted.

59.1b Bottom Flanges (Very Good): No deficiencies noted.

59.1c Webs (Very Good): No deficiencies noted.

59.1i Rivets or Bolts (Very Good): No deficiencies noted.

59.1q Bearings (Very Good): The bearing area has no deficiencies noted.

59.4 GENERAL

59.4d Member Alignment (Very Good): No deficiencies noted.

ITEM 60 - SUBSTRUCTURE

Timber bent pier and abutments supported on timber piles.

60.1 ABUTMENTS

60.1b Wingwalls (Satisfactory): The wingwalls were partially repaired, however they still appear to be tilted slightly forward .

60.1c Backwalls (Very Good): No deficiencies noted. The timber lagging was replaced by a 1" thick timber sheet which appears to be the full height of the abutment and combination backwall, stem, and ballast retainer.

60.1e Bridge Seat (Very Good): No deficiencies noted.

60.1g Footing (Hidden): Footing hidden under water level/underground.

60.1h Erosion (Satisfactory): Slight undermining possible under the abutment caps, however they appear to be stable.

60.1i Settlement (Very Good): No settlement noted.

60.1j Piles (Very Good): No deficiencies noted.

A-4 A00880 - 15 Proposal No. 609200-106704 Addendum No. 3, March 19, 2019 PAGE 4 OF 10 CITY/TOWN B.I.N. BR. DEPT. NO. 8-STRUCTURE NO. INSPECTION DATE

_Lakeville BE7 L-01-018 L01018BE7DOTRRO 12/1/2011 REMARKS & PHOTOS 60.2 PIERS OR BENTS

60.2a Piles (Good): The western most pile supporting the pier has a minor split running vertically through it. No other deficiencies noted.

60.2b Footings (Hidden): Footing hidden under water level/underground.

60.2d Cap Beams (Very Good): No deficiencies noted.

60.2e Top of Stem or Cap (Very Good): No deficiencies noted.

60.2i Erosion or Scour (Satisfactory): Minor scour was noted around the bottom cap beam.

60.2j Settlement (Very Good): No settlement noted.

ITEM 61 - CHANNEL & CHANNEL PROTECTION

61.1 Channel Scour (Poor): Moderately pronounced signs of channel scour both north and south of the bridge.

61.2 Embankment Erosion (Fair): Minor erosion along the embankments.

61.3 Drift (Satisfactory): There is minor drift both along the channel approaches, however there is none directly at the bridge.

61.4 Channel Alignment (Fair): The channel is skewed against the east side of the bridge.

61.5 Vegetation (Fair): There is heavy vegetation around the bridge, on the approaches as well as the bridge seat.

61.7 Silt (Very Good): No silt detected in channel.

61.8 Debris in Channel (Very Good): No visible debris in channel.

GENERAL

2. Rail on Bridge (Satisfactory): The rail on the bridge is present and appears serviceable.

4. Rail Fasteners (Satisfactory): Rail fasteners are present and appear serviceable.

A-5 A00880 - 16