APPENDIX VIII (See paragraph 6) FORM 1 M APPLICATION FOR MINING OF MINERALS UNDER CATEGORY ‘B2’ FOR LESS THAN AND EQUAL TO FIVE HECTARE.

1. Basic Information

Name of the I Mining Permit “Granite Building Stone Quarry of Mr. Ummer Kutty K” Site Survey No:- 153/2,154/pt Village: Morayur Taluk: District: State:- Location/Site II (GPS Co- Boundary Latitude Longitude Ordinate) Pillar BP 1 N 11° 6'39.26" E 76° 0'47.00" BP 2 N 11° 6'36.11" E 76° 0'45.01" BP 3 N 11° 6'37.40" E 76° 0'44.38" BP 4 N 11° 6'38.95" E 76° 0'42.99" BP 5 N 11° 6'41.65" E 76° 0'44.89"

Size of the III 0.9994 Ha Mining Permit Capacity of IV 204891 MT Mining Permit Period of V 5 Years Mining Permit Expected Cost VI 60 Lakhs of Project VII Contact

1

Information Name Mr. Ummer Kutty K Address Director Morayoor granites Pvt Ltd Mucheth House,Elambra Nellikuzhy Ernakulam-686691 Mob 9895755133

2. Environment Sensitivity

Sl.No. Areas Distance (KM) Distance of project site from Rail, Road 1 Bridge over the concerned River, Rivulet, Cheralappalam Bridge-5.95km-NW Nallah etc. Distance from infrastructural facilities Railway Line Vallikunnu Railway Station -17.8 km -W National Highway NH 966(-)-2.3km NE State Highway SH 71(-)-10.2km SE, Major District Road Arimbra-Morayur Road-0.92km E, Other Road Arimbra-Arimbra mala Road-0.32km E 2 Electrical Transmission Line or Pole Arimbra-1.9km-SE Chamakayam Check Dam-7.9km-SE Canal/Check Dam/Reservoirs/Lake/Pond Kallakkayam Check Dam-9.1km-SW Vachal Check Dam-10.95km-NE In-take for drinking water/pump house Harijan Colony-1.2km-SW In-take for Irrigation canal pumps Charapara-1.4km-SE Areas protected under international conventions, national or local legislation for 3 None within 1KM from project site their ecological, landscape, cultural or others related value. Areas which are important or sensitive for Mavoor Wetlands- 18.3 km- NW 4 ecological reasons – Wetlands, watercourses Kadalundi River-17.4km-SW

2

or other water bodies, coastal zone, -19.9km-NW biospheres,mountains, Mudumalai Periyar-40.7km-SE New Amarambalam Wildlife Sanctuary- 50.3km-NE Cheruppadi Mala-2.06km-SW Areas used by protected, important or sensitive 5 species of flora or fauna for breeding, nesting, None within 1KM from project site foraging, resting, over Wintering, migration 6 Inland, coastal, marine or underground Waters Kadalundi River-17.4km-SW 7 State, National boundaries Kerala-Tamilnadu Border-47.8km-E NH 966(Palakkad-Kozhikode)-2.3km NE, Routes or facilities used by the public for SH 71(Tirur-Manjeri)-10.2km SE, 8 access to recreation or other tourist, pilgrim Arimbra-Morayur Road-0.92km E, areas Arimbra-Arimbra mala Road-0.32km E 9 Defense installations None within 1KM from project site Densely populated or built-up area, distance 10 Morayur-2.63 km NE from nearest human habitation Hospital: Co-operative Hospital, Musliyarangadi – 2.3km N School: GVHSS Arimbra – 0.8km N-E Areas occupied by sensitive man-made land Church: Christ King Church, 2.5 km S-E 11 uses (Hospitals, schools, places of worship, Temple: Morayur Maha Siva Temple,2.64km community facilities) N-E Mosque: Morayur Town Juma Masjid,2.55km N-E Areas containing important, high quality or Kadalundi River-17.4km-SW scarce resources (ground water resources, Chaliyapuram Reserve Forest-15.32km-NW 12 surface resources, forestry, agriculture, Mangrove Forest-29.8km-NW fisheries, tourism, minerals) Medappara Rock-30.43km-NE Areas already subjected to pollution or 13 environmental damage, (those where existing No legal environmental standards are exceeded) 14 Areas susceptible to natural hazard which No

3

Could cause the project to present environmental problems (earthquake, subsidence, landslides, erosion, flooding, or extreme or adverse climate conditions) is proposed mining site located over or near fissure/fracture for ground water recharge Whether the proposed involves approval or clearance under the following Regulations or Acts namely:- (i) The Forest (Conservation) Act, No 1980; 15 (ii) The wildlife No (Protection) Act,1972; (iii) The Coastal Regulation Zone No Notification, 2011 If yes, details of the same and their status To

be given. 16 Forest land involved (hectares) No forest land involved Whether there is any litigation pending against the project and/or land in which The project is proposed to be set up? (i) Name of the Court 17 No (ii) Cash No. (iii) Orders or directions of the court, if any and its relevance with the proposed project

4

hereby give "I undertukins that the data and information given in the application and enclosure are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading ar any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost."

Place: Malappuram Date: 2f lt f lon

Applicant: V

Ummer Kutty.K

.., Morayur granites Pvt Ltd

Reg. Office Mucheth House Elambra Nellikkuzhy Eranakulam (Kerala)