ENVIRONMENTAL IMPACT ASSESSMENT
For the Construction and Setup of an Island Sewerage System in Dhiggaru Island, Meemu Atoll, Maldives
Photo: Water Solutions Pvt.Ltd; October 2016
Proposed by Male' Water and Sewerage Company Pvt. Ltd (MWSC)
Prepared by Ahmed Jameel, Ibrahim Faiz For Water Solutions Pvt. Ltd., Maldives
November 2016
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Page 2
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
1 Table of Contents 1 Table of Contents 3 2 Declaration of the consultants 8 4 Proponents Commitment and Declaration 10 5 Non-Technical Summary 13 6 Introduction 15 6.1STRUCTURE OF THE EIA 15 6.2AIMS AND OBJECTIVES OF THE EIA 15 6.3EIA IMPLEMENTATION 16 6.4TERMS OF REFERENCE 16 7 Project Setting 17 7.1LAWS AND REGULATIONS 17 7.1.1 Environmental Protection and Preservation Act ...... 17 7.1.2 Environmental Impact Assessment Regulation 2012 ...... 17 7.1.3 National Waste Water Quality Guidelines...... 18 7.1.4 National biodiversity strategy and action plan...... 19 7.1.5 Waste management Regulations 19 7.1.6 Protected Areas and Sensitive Areas 20 7.1.7 Third National Environment Action Plan ...... 20 7.1.8 Regulation cutting down, uprooting, digging out and export of trees...... 20 7.1.9 Post EIA Monitoring, Auditing and Evaluation...... 21 7.2INTERNATIONAL CONVENTIONS 21 7.2.1 Climate Change Convention and Kyoto Protocol...... 21 7.2.2 Convention on Biological Diversity22 8 Project Description23 8.1PROJECT PROPONENT 23 8.2PROJECT LOCATION AND STUDY AREA 23 8.3NEED AND JUSTIFICATION FOR THE PROJECT 24 8.4EXISTING SANITATION SYSTEM 25 8.5WHAT DOES THE PROJECT CONSTITUTE? 26 8.5.1 The schematic diagramme of the wastewater system...... 26 8.5.2 House hold connections 26 8.5.3 Sea outfall 27 8.5.4 Two Pump stations 28 8.5.5 Treatment of wastewater 31 8.5.6 Technology 31 8.5.7 Design period 32 8.5.8 Population and household projection 32 8.5.9 Flow rates 32 8.5.10 Sewerage network design 33 8.6BRIEF DESCRIPTION OF THE SEWAGE DISPOSAL PROCESS 36 8.6.1 Technical details 36 8.7PROJECT MANAGEMENT 36 8.7.1 Project duration 37 8.7.2 Planning and Programme 37 8.7.3 Waste Management 37 8.7.4 Safety 37 8.7.5 Housing of temporary labour 37 8.8RISKS ASSOCIATED WITH THE PROJECT 37 8.9PROJECT INPUTS AND OUTPUTS 38 8.9.1 Project Inputs 38 8.9.2 Project Outputs 39 9 Methodology 40 10 Existing Environment 41 10.1 EXISTING MARINE ENVIRONMENT 41
Page 3 EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
10.1.1 Methodology of marine surveys 41 10.1.2 Coral reef 42 10.1.3 Status of fish abundance 48 10.1.4 Marine water quality and bathymetry 51 10.1.5 Prevailing currents around the sea outfall location ...... 53 10.1.6 Waves 55 10.1.7 Tides 55 10.1.8 Risk of storm surges and flood 56 10.1.9 Marine Protected Areas and Environmentally Sensitive Areas ...... 57 10.2 EXISTING TERRESTRIAL ENVIRONMENT 58 10.2.1 Section Brief 58 10.2.2 Vegetation at pump stations 58 10.2.3 Ground water 61 10.3 CLIMATE 64 10.3.1 Rainfall and Infiltration 64 10.3.2 Wind 65 10.4 EXISTING SOCIO-ECONOMIC ENVIRONMENT 69 10.4.1 Introduction to the atoll 69 10.4.2 Dhiggaru island 71 10.4.3 Economic Activities 72 10.4.4 Electricity 72 10.4.5 Health 72 10.4.6 Water and Sanitation 73 10.4.7 Land Use Plan 73 11 Environmental Impacts 75 11.1 ASSESSING AND IDENTIFICATION OF IMPACT 75 11.2 IMPACT IDENTIFICATION MATRIX 75 11.3 MAGNITUDE OF IMPACTS 77 11.4 UNCERTAINTIES IN IMPACT PREDICTION 77 11.5 IMPACTS AND MITIGATION MEASURES 80 11.6 IMPACTS ON THE ENVIRONMENT AND THEIR MITIGATION MEASURES ...... 91 12 Stakeholder Consultations 93 12.1 DISCUSSIONS WITH THE MWSC 93 12.2 CONSULTATION WITH THE MINISTRY OF ENVIRONMENT AND ENERGY ...... 93 12.3 CONSULTATION WITH THE ISLAND COUNCIL 93 12.4 CONSULTATION WITH MEEMU ATOLL COUNCIL 95 12.5 CONSULTATION WITH HPA 95 12.6 LIST OF PEOPLE CONSULTED 96 13 Alternatives 97 13.1 NO PROJECT OPTION 97 13.2 ALTERNATIVE ANALYSIS MATRIX 98 13.3 ALTERNATIVE SITES/LOCATION FOR OUTFALL 99 13.4 ALTERNATIVE SEWERAGE SYSTEMS 100 13.4.1 Deep bore disposal 100 13.4.2 Septic tanks 101 13.4.3 Gravity flow systems without septic tanks...... 102 13.4.4 Vacuum sewers 102 13.4.5 Grey water separation system 102 13.5 PREFERRED ALTERNATIVE 103 13.5.1 Secondary Treatment and Effluent Reuse ...... 103 13.5.2 Mitigation Measures for the Preferred Alternative...... 103 14 Environmental Management and Monitoring Plan 104 14.1 INTRODUCTION 104 14.2 COST OF MONITORING 104 14.3 DURATION OF MONITORING 104 14.4 METHODS OF MONITORING 104 14.5 MONITORING RESPONSIBILITY 104 14.6 MONITORING REPORT 104 15 Conclusion 108
Page 4 EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
16 Recommendations 110 17 People who have assisted in the preparation of this report ...... 111 18 Acknowledgements 112 19 Reference Books and Sources 113 20 Annex: Terms of reference 114 21 Annex: Project Drawings 115 22 Annex: Bathymetry of outfall location 116 23 Annex: Project Schedule 117 24 Annex: Project concept approval letter from Ministry of Environment...... 118 25 Annex: Pump station approval 119 26 Annex: Concept Design Report 120 27 Annex: Methodology of data collection 121 28 Annex: CVs of people who assisted 122 29 Annex: Letter from Atoll Council 123
Page 5 EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Table of Figures and Tables FIGURE 1: LOCATION OF DHIGGARU ISLAND IN MEEMU ATOLL 24 FIGURE 2: SCHEMATICS OF THE SEWERAGE SYSTEM 26 FIGURE 3: OUTFALL LOCATION OF DHIGGARU AS INITIALLY PROPOSED 27 FIGURE 4: FINAL OUTFALL LOCATION 28 FIGURE 5: PROPOSED PUMP STATIONS LOCATIONS 29 FIGURE 6: CHARACTERISTICS OF THE WASTEWATER 36 FIGURE 7: EPA GUIDELINES FOR MAXIMUM ALLOWABLE CONCENTRATIONS FOR DISCHARGE INTO DEEP SEA 36 FIGURE 8: MARINE SURVEY LOCATIONS 41 FIGURE 9: PERCENTAGE BENTHIC COMPOSITION AT SITE 1 43 FIGURE 10: MARINE PHOTOS FROM SITE 1 44 FIGURE 11: PERCENTAGE BENTHIC COMPOSITION AT SITE 2 45 FIGURE 12: MARINE PHOTOS FROM SITE 2 46 FIGURE 13: PERCENTAGE BENTHIC COMPOSITION AT SITE 3 47 FIGURE 14: MARINE PHOTOS FROM SITE 3 48 FIGURE 15: WATER CURRENT MEASURED DURING THE FIELD VISIT TO DHIGGARU 54 FIGURE 16: MONSOONAL WIND WAVES AROUND THE ISLAND 54 FIGURE 17: EAST SIDE OF DHIGGARU ISLAND 57 FIGURE 18: AERIAL PHOTO OF DHIGGARU TAKEN DURING FIELD VISIT (OCTOBER 2016) 59 FIGURE 19: LOCATION OF PUMP STATION 1 60 FIGURE 20: LOCATION OF PUMP STATION 2 AND STP 60 FIGURE 21: GROUNDWATER SAMPLING LOCATIONS IN DHIGGARU ISLAND (OCTOBER 2016) 62 FIGURE 22: MONTHLY AVERAGE RAINFALL SINCE 2000 (SOURCE: MALDIVES METEOROLOGICAL SERVICE) 64 FIGURE 23: MONTHLY RAINFALL DATA OF HULHULE STATION FOR 2015 (SOURCE: MALDIVES METEOROLOGICAL SERVICE) 65 FIGURE 24: MONTHLY WIND DATA FOR 2015 (SOURCE: MALDIVES METEOROLOGICAL SERVICE) 66 FIGURE 25: MONTHLY WINDROSES (SOURCE: MALDIVES METEOROLOGICAL SERVICE) 68 FIGURE 26: NUMBER OF INHABITED ISLANDS BY ATOLL 69 FIGURE 27: DHIGGARU ISLAND (SOURCE: GOOGLE EARTH) 71 FIGURE 28: PROPOSED AND ALTERNATIVE LOCATION FOR THE SEA OUTFALL 99
TABLE 1: MAXIMUM ALLOWABLE CONCENTRATIONS IN DOMESTIC WASTE WATER FOR DISCHARGE INTO DEEP SEA 18 TABLE 2: FLOW RATES OF THE PUMP STATIONS 33 TABLE 3: MATRIX OF MAJOR INPUTS DURING CONSTRUCTION PERIOD 38 TABLE 4: MATRIX OF MAJOR OUTPUTS OF ENVIRONMENTAL SIGNIFICANCE DURING CONSTRUCTION STAGE 39 TABLE 5: PERCENTAGE BENTHIC COMPOSITION AT SITE 1 43 TABLE 6: PERCENTAGE BENTHIC COMPOSITION AT SITE 2 45 TABLE 7: PERCENTAGE BENTHIC COMPOSITION AT SITE 3 47 TABLE 8: FISH CENSUS SURVEY RESULTS FOR SITE 1 49 TABLE 9: FISH CENSUS SURVEY RESULTS FOR SITE 2 50
Page 6
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
TABLE 10: FISH CENSUS SURVEY RESULTS FOR SITE 3 50 TABLE 11: RESULTS OF THE MARINE WATER QUALITY TESTS UNDERTAKEN IN DHIGGARU ISLAND 51 TABLE 12: SUMMARY OF THE TIDE LEVELS HULHULE ISLAND, MALE ATOLL 56 TABLE 13: RESULTS OF THE GROUNDWATER QUALITY IN DHIGGARU, MEEMU ATOLL 61 TABLE 14: LIST OF INHABITED ISLANDS IN MEEMU ATOLL 69 TABLE 15: POPULATION OF DHIGGARU (SOURCE: DHIGGARU ISLAND COUNCIL) 71 TABLE 16: EMPLOYMENT BY SECTOR OF DHIGGARU (SOURCE: HARBOUR REDEVELOPMENT EIA BY MEECO, 2015) 72 TABLE 17: IMPACT ASSESSMENT MATRIX FOR THE PROJECT 76 TABLE 18: IMPACT MAGNITUDES AND THEIR CORRESPONDING SCORES 77 TABLE 19: MATRIX OF SPECIFIC IMPACTS AND THEIR CHARACTERIZATION 92 TABLE 20: LIST OF PEOPLE CONSULTED 96 TABLE 21: ADVANTAGES AND DISADVANTAGES OF THE NO PROJECT OPTION 98 TABLE 22: SCHEDULE FOR ENVIRONMENTAL MONITORING DURING THE CONSTRUCTION PERIOD AS WELL AS PER ANNUM DURING OPERATION PERIOD. 106
Page 7
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
2 Declaration of the consultants
This EIA has been prepared according to the EIA Regulations 2012, issued by the Ministry of Housing and Environment. The EIA was carried out by a multidisciplinary consulting team representing Water Solutions Private Ltd. In preparing this report, no data has been manipulated. All data has been collected by field visits.
I as the lead consultant certify that the statements in this Environmental Impact Assessment study are true, complete and correct.
Name: Ahmed Jameel (EIA 07/07)
Signature:
Name: Ibrahim Faiz (EIA T06/15) Signature:
Page 8
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
4 Proponents Commitment and Declaration
Page 10
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll c
ާސާލުޙ ާދާސ
ެގ ީދެޕްމޮކ ްޖޭރަވުސ ްޑްދެއ ރަޓޯވ ޭލާމ ީކަޓޯޕިރިމ
ެގާމަދުރަދ ިއަގުރަގްއިދ .މ ީކަޓރޯޕިރިމ .ެވެކެޓރޯޕިރ ާވިއަފިވެރުކުރާޔްއަތ ްފަކަމުތަގިއަޑަވިދެއ
ާހިކ ްފަޓްއެވާމިތ ްދުބަބަސެގ ުއޫރްޝަމ ާވިއަފިވޭރ ްދަގްދިހ ްފަމުރުކުމިއާގ ްއެމާޒިދ
ާވިއަފިވެރުކުރާޔްއަަތ ްދިއ ްދަޝުއިލޮސ ރަޓޯވ ްދުތޮގ ެގުމުލެބ ޯތްއެމަކެދާރުކްއެރަސައ
ްދިއީޖރަދެއ ްޑްދެއ ްޓްދަމްދަރަޔަވްދެއ ްފޮއ ީރްޓްސިދިމ ީކަޓްކެޖޮރްޕ ިމ .ެވެކެޓރޯޕިރ
.ެވެކެޓްކެޖޮރްޕ ާވިއަފިއަލާވަލުކެއ
ްފަދަތާހިމ ިއަގުފަރިމ .ެވެކެފަރ ަދްދޮއ ްއެއ ީދާބާއ ެގ ްދުހީމ 1731 ީކަރަގްއިދ .މ
ީދަވ ްދެފ ެގުމިބ ެގުފަރ ްދުބަބަސ ެގުމަކިމ .ެވެއަފިވެރުކުދ ުމިއާގ ީދަވ ްއެއްމާޒިދ ެގާމަދުރަދ
ުޑޮބ ްފަރަވ ީދަވ ްދުވުދ ްސަވ ިއަބުދ ްދުދެފ ްދުބަބަސެގީމ .ެވެއަފެވުރަޔްއަޢަތްފަޑޮބ ްފަރަވ
ިދައ ްދަދްދޮދ ިހެޗްއެއ ިދަކެއަމަހ ުރާހިމ ީކަދެފުޅަވ ެގުފަރ .ެވެއަފެވ ްފަކައަލަސްއަމ ީޙްއިސ
ްދަކާރުކްދުދޭބ ްދެފުޅަވ ުކަޔަބަދިގ ްފަރަވްދެފ ްސެވަމަދ .ެވެދެފ ާރުކްދުދޭބ ްދަރަވްދެފ
ީދަވ ްފަކަތޮގަލަހަކްފޮކްއެއ ްފަރ ކްދުމަކްއެފަރަޑުކ ްދުތޮގ ެގުމިބ ީކަރަގްއިދ .ެވެެއެވެލްފޮކަގަހާފ
ާވިއަފިދެހ ިއަގުދްއަހަރަސ ެގޭގ ީދަދްދުމަދްދިހ ުރާހިމ ްދެފްސިޖަދ ިއަގޭގޭގ ެގުފަރިމ .ެވެއަފިރުފ
ްދަކާރުކުރޭބ ްސިޖަދ ިއަޅައިޅޮހ ްފަދޫމ ިއަގުރަވްދެފުފަރ ްދުކަތީސިބޭގ ްއެއަބ .ެވެފަކަތުޅަވްސިޖަދ
ިއާފަމުރުކުޅަގަރ ުތަލާހ ެގުދެފ ެގުފަރ ީކައޫރްޝަމ ިމ ާމީވ .ެވެއެރުކަގަހާފ ްދުލިސްދުއަކ ުފަރ
.ެވެކެޓްކެޖޮރްޕ ުމްދިހުމ ްފަމުރުކުޅަގަރ ުތަހްއިސ ުމްދާއ ެގުފަރ
ްއަތުޑދަގުޅަވ ާދްދިހ ްދެފްސިޖަދ ިރުހ ުރާހިމ ީދަވިއަފިދެމިހ ްދުތޮގިމ ިއަގުއޫރްޝަމިމ
ިވެރުކްއެއ ްދުކަމާޒިދ ެގާމަދުރަދ ްދެފ ާވުރޭބ ްދުކަތްތާރާމިއ ާދްދިއެގ ޭގ ާހިރުހ ިދައ ިވެލާވުއ
ާދީސ ިއަގުލަދަބ ެގުޅަވްސިޖަދ ާރުކްދުދޭބ ުރާހިމ ިއަގޭގޭގ .ެވެމުރުކުރޭބ ްދުރަފ ެގުފަރ ިދައ
Page 11
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
ްޕްދަޕ ޭދެހ ިއަގުކަތ ުދްއަހަރަސ ިކެއ ެގުފަރ ުހަފްފައެއ .ެވެއެދޭވެރުކުރޭބ ްސިޖަދ ްފައާމަދުރަދ
.ެވެފަރޭބ ްދުރަފ ެގުފަރ ީދޭވެރުކުރޭބ ްދެފްސިޖަދ ްދުދަތެއ ިވެރުކާމަޖ ްފަކަތްދަޝޭޓްސ
ެގޫރްޝަމ ިމ ްދުކަތާސާރިދ ުދުދެހ ިދައ ްދުކަތްއަތްދަކ ިލެބ ްފޮކްތަޔާއިރ ްފަމަކްދަކިމ
ެބ ްފަކަތ ާސާރިދ ުދުވެރުކ .ެވެއަފިވެދަގެދެދ ީދަވ ުރަސައ ެދާރުކ ްފަޓްއެވާމިތ ްދުބަބަސ
ްފަކަމަކެދޭބިލ ްއެކަތ ްދުލްއެގ ެގުރަވާވުޑޮބްދަކ ްފަޓްއެވާމިތ ްދުބަބަސ ެގ ްޓެޖޮރްޕ ިމ ުހަފްފަމުލ
ަދިގާމ ާވްދުލްއެގ ްފަޓްއެވާމިތ ުރިއާދްދެގ ްފައިރުކ ްޓްކެޖޮރްޕ ިމ ީކަބަބަސ .ެވެއެދެފުދ
ިއަގްޓްކެޖޮރްޕ ިމ ްސެވ ީކަކަތްއަތްދަކ ަލަހަކ ްދުޑދެކްސަގ ްދުފަރ .ެވެއީތޭދެމިހުދ ްއެކަތްއަތްދަކ
ްދުރުކ ރަޓޯވީޑ ްފަކަރަވ ްސެވެމްދޮކ ުރިއަދްދޮކ ްދަޅައ ްދިއަލިޅޮހ ްސެވަމަދ .ެވެކެމަކ ޭދެމިހުދ
ކެވެކަތްދަކ ެދާގދިހ ިއަގްއެތަދްއުމ ުރުކ ްފަރަވ ްދުތަބްސިދ ީއިމ ްސެވަމަދ .ެވެއެދޭދެމިހ
ިއަގްޓރޯޕިރ ްސެވްދަކެދާރުކ ްއެކަތާދިއަފ ްއަތެއ ްދުބަބަސ ެގ ުޢޫރްޝަމ ިމ
ްފަދްދުތަޔްއަރ ުރަސައ ެގޭއ ިއަފެވަދިގުދަހުދ ްއަތާދިއަފޭބިލ ްދުތޮގިމ .ެވެއެދާވިއަފިވެރުކަގަހާފ
ްދުމުލެބިލެބ ްފޮކާސާރިދ ިމ .ެވެދޫދ ްއެމަކްތޮއ ްސެވްއެކްއަޝ ީމަކެދާރުކ ްފަޓްއެވާމިތ ިދައ
ެގްޓްކެޖޮރްޕ ިމ .ެވެއާދިއަފ ީދާރުކ ެރުވްފަމުލްއެގ ޭބިލ ްފަޓްއެވާމިތ ްދުބަބަސ ެގުއޫރްޝަމިމ
ިދައ ުމްދިހުމ ްފަރަވ ީކަމުއިދްދެގ ްފައިރުކ ުއޫރްޝަމިމ ްދުމަކެދާރުކ ްއެކަތާދިއަފ ްދުބަބަސ
.ެވެއެދެފ ްފަމަކްއެމަކުޅަގދަރ ެމްދެއ
Page 12
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
5 Non-Technical Summary
This report discusses the findings of an environmental impact study undertaken by Water Solutions Pvt. Ltd in order to fulfill obligatory requirements of the National Environment Protection and Preservation Act, Law No. 4/93 for the proposed setup of the sewerage system (hereafter referred to as the project) in Dhiggaru island, Meemu Atoll, Maldives.
The purpose of this EIA is to identify and minimize potential adverse environmental impacts related to this project and enhance the overall quality of the project. By examining the project location, the legal framework and the existing environmental components such as marine ecology and the socio-economic aspects, this EIA provides useful information regarding the extent, nature and the magnitude of impacts that are likely to occur. The EIA will also help to identify the long term socio-economic benefits to the community after implementing this project. It also provides a framework for future monitoring of the environment, so that changes can be monitored and corrective measures can be undertaken.
The proposed project aims to establish an island wide sewerage collection and disposal system. At present household wastewater is disposed on site by the use of septic tanks and this has contributed to the contamination of the groundwater to a state that it cannot be utilized. There is also a private sewer main pipes laid in some roads which outfalls into the shallow lagoon by gravity. This is a basic system of pipes that was constructed at the community level, but without any proper assessment or design.
The project therefore involves the following components: a) Installation of an island wide sewage collection network.
b) Installation of new catch pits for each house / institution.
c) Construction of pump stations in strategic locations to collect and convey raw sewage from the households and to the final disposal station.
d) Construction of a sea outfall.
The proposed project will ensure that the groundwater of the island does not get contaminated through improper sanitation systems. It will also ensure that the surrounding marine environment will improve in terms of environmental quality and will ensure pollution from sewage does not occur on the near shore environments.
The project is expected to bring several positive impacts on the environmental
Page 13
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll quality of the island and the surrounding reef. Particularly, the most significant benefit would be achieved through improvement in the groundwater quality. The health benefits of the project are also worthy of noting as the improvement in water quality are going to bring significant health benefits to the community.
Various alternatives to the proposed system were also studied. One of the options identified include deep bore well disposal and gravity systems among others. Based on the assessment, these alternatives were assessed to identify their potential application in the island against the proposed system.
Several environmental impacts of this proposed project have been examined through a number of processes. These include consultations with the project development team, field surveys, observations and assessment, and field experience gained from similar development projects implemented throughout the country. Potential positive and negative impacts on the environment have been considered. The assessment indicates environmental impacts both during the construction and operation stage. During the construction period, impacts are likely to occur on the marine and terrestrial environment (groundwater) as the proposed project does necessitate construction of an outfall but avoids large scale construction activities such as clearing trees. Most of the impacts during the construction period are impacts related to construction waste, dust emission, damage to the reef during outfall construction and noise. During the operational stage of this project, there will be both positive and negative impacts. Positive impacts include the improvement of the ground water quality of the island and also the quality improvement of the near shore environment. Negative impacts include the increased in extraction of groundwater for toilet flushing. This project does not foresee many negative impacts even during the construction stage and is geared towards improving the environmental quality of the island, most notably the environmental health.
The project does not pose serious threats to the marine or terrestrial environment and will directly benefit the environment and the community, both in the short and long term. Nevertheless, negative impacts with varying significance will occur as the project is implemented. Based on this assessment, it is advised to undertake this project.
Page 14
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
6 Introduction
This Environmental Impact Assessment (EIA) report has been prepared to fulfil the requirements of the Environmental Protection and Preservation Act, law no. 4/93 in order to assess the impacts of the proposed construction of a sewerage system in Dhiggaru island. The aim of this project is to ensure that the project is sustainably undertaken to address and manage the environmental issues.
6 . 1 Structure of the EIA
The report has been structured to meet the requirements of the EIA regulations 2012 issued by the Ministry of Housing and Environment. Hence, the report will provide an executive summary at the beginning. The report will then have a project description in detail, existing environmental conditions, justifications given by the proponent for undertaking the proposed project components and alternatives. Alternatives to proposed components or activities in terms of location, construction methods and technologies, design and environmental considerations would be suggested. A mitigation plan and monitoring programme before, during and after the works will be outlined at the end.
The major findings of this report are based on qualitative and quantitative assessments undertaken during site visit in October 2014 and through the use of available secondary data. However, due to unavailability of long term site-specific data, the impact assessment methodology has been restricted to field data collected, consultations, experience and professional judgment and field data taken on site. In addition, satellite and aerial photos have also been used to study the geography and environment where necessary.
6 . 2 Aims and Objectives of the EIA
The objective of the report is to: Promote informed and environmentally sound decision making. Report the existing situation of wastewater treatment and its shortcomings. To fulfill the obligations of the proponent to undertake an EIA under Clause 5 of the Environmental Protection and Preservation Act of the Maldives. Undertake the proposed project work with minimum damage to the environment. Ensure that all the environmental and social aspects of the project are addressed. Propose recommendations to the proponent
Page 15
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
6 . 3 EIA Implementation
This EIA has been prepared by a local environmental consulting firm, Water Solutions. Water Solutions have been chosen by the proponent as the environmental consultants for this project. The team members were: Abdul Aleem, (EIA-09/07) Ahmed Jameel, (EIA-07/07) Ibrahim Faiz, (EIA-T06/15) Hamdhulla Shakeeb, - Assistant Surveyor.
6 . 4 Terms of Reference
Terms of Reference for this assessment has been included in the Appendix of this report.
Page 16
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
7 Project Setting
This section outlines the relevant environmental legislation pertaining to this project. The following table outlines a matrix of major environmental laws, guidelines, codes and standards, both local and international indicating the relevance to this project. Details of these regulations, what they cover and under what circumstances they apply are attached as an annex. 7.1 Laws and Regulations 7 . 1 . 1 Environmental Protection and Preservation Act
Article 5 (a) of the Environmental Protection and Preservation Act (Law No. 4/93) addresses the submission of an EIA (Majilis, 1993). It states that an EIA shall be submitted to Ministry of Environment before implementing any developing project that may have a potential impact on the environment. This project complies with this Act.
7 . 1 . 2 Environmental Impact Assessment Regulation 2012
The Ministry of Environment has issued EIA regulation on May 2012, which guides the process of undertaking the Environmental Impact Assessment in the Maldives – This guideline also provides a comprehensive outline of the EIA process, including the roles and responsibilities of the consultants and the proponents. This regulation outlines every step of the EIA process beginning from application to undertake an EIA, details on the contents, minimum requirements for consultants undertaking the EIA, format of the EIA/IEE report and many more. The Ministry of Environment has issued 3 amendments to this regulation over the past years.
Amendment 1 (issued on 9th April 2013) covers the fines for proponents who fail to obey the regulations.
Amendment 2 (issued on 30th August 2015) covers the EIA report review criteria and review fees. This amendment also includes the latest update to the list of the projects that require EIA and the latest update to the list of the projects that do not require EIA.
Amendment 3 (issued on 11th August 2016) covers the point systems for consultants, categories of the consultants and amendment of the penalties to consultants and proponents who fail to follow the regulation.
The guidance provided in this Regulation and its Amendments was followed in
Page 17
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll the preparation of this EIA report. The EIA has also been prepared by registered consultants.
7 . 1 . 3 N a t i o n a l Waste Water Quality Guidelines
These guidelines are developed by the Maldives Water and Sanitation Authority and are implemented by the Environment Protection Agency. The guidelines are to improve public health through improved sanitation and cleaner and safer environment by regulating the disposal of domestic wastewater.
Wastewater is referred in this guideline as water produced and discharged by any water user as a result of the non-consumptive use of water, for example to flush the toilet or to wash clothes. The quality of the waste water has usually been changed as a result of the specific use of the water.
According to this guideline deep sea discharge in context of the Maldives means discharge of waste water beyond the shallow reef and at a depth which will ensure proper dispersion and rapid dilution.
Table 1: Maximum allowable concentrations in Domestic Waste Water for discharge into deep sea
Domestic Waste Water Maximum Remarks Component allowable concentration Faecal coliforms 100 org / 100 ml For less than 95% of samples taken E. coli 1 org / 100 ml pH 5 – 9.5
To prevent sludge formation Suspended solids 150 mg/l on corals
Residual chlorine 0.1 mg/l Nitrates as N 15 mg/l Free and saline Ammonia 10 mg/l as N Ortho-phosphate as P 10 mg/l Surfactants 10 mg/l Conductivity < surrounding sea Should be less or equal to water surrounding sea water Soap, oils and grease (food 5 mg/l related) Oils, grease and waxes 5 mg/l Chemical Oxygen demand 50 mg/l After applying chloride correction
Page 18
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Biological Oxygen demand 40 mg/l Five-day test Phenolic compounds as 1 mg/l Phenol Sum of metals 5 mg/l Cadmium+Chromium+Copp er+Mercury+Lead Acute toxicity Zero No constituents allowed in concentrations which are poisonous or injurious to aquatic life
7 . 1 . 4 National biodiversity strategy and action plan
The goals of the National Biodiversity Strategy and Action Plan are conserve biological diversity and sustainably utilize biological resources, build capacity for biodiversity conservation through a strong governance framework, and improved knowledge and understanding, foster community participation, ownership and support for biodiversity conservation (Ministry of Housing and Environment, 2003).
In implementing the proposed project activities due care would be given to ensure that the national biodiversity strategies are adhered to. The proponent has committed on conservation and protection of the environment while undertaking this proposed project. More specifically, the coral reef and generally the marine environment have been assessed in order to assess baseline values. Quantitative and qualitative surveys were undertaken to assess the biological diversity of the marine environment, especially in close proximity to the proposed project area. Practical mitigation measures and solutions have been identified to conserve and protect the biodiversity.
7 . 1 . 5 Waste management Regulations
The Ministry of Environment has developed national waste management regulations. The key elements of the regulations include: ensure safe disposal of solid waste and encourage recycling and reduction in waste generated, develop guidelines on waste management and disposal and advocate enforcing these guidelines through inter-sectoral collaboration and ensure safe disposal of chemical, industrial and hazardous waste.
Waste management for the proposed project during the construction and operation phase will be in line with this regulation. The waste generated from the project site
Page 19
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll would be taken to the island waste management facility or Thilafushi for processing and disposal.
7 . 1 . 6 Protected Areas and Sensitive Areas
Under Article 4 of the Environment Protection and Preservation Act, the Ministry of Environment is vested with the responsibility of identifying and registering protected areas and natural reserves and drawing up of rules and regulations for their protection and preservation.
As part of the Environmental Regulation, EPA has established list of „sensitive sites‟ in the Maldives. Although not formalized as a regulation, the sensitive list is mentioned in the recent Regulation on Dredging and Reclamation (Regulation number 2014/R-13, see Section 5.7, page34). The sensitive sites, according to EPA are sites in the Maldives (islands, reefs, mangroves, inter-tidal areas) where developments ought to be restricted, regulated or controlled. Some view those sites mentioned in the sensitive list have no meaning because there is no evidence to show any „sensitive features‟ of the areas.
Dhiggaru is not a protected island and the island is not included in an environmentally sensitive area list maintained by EPA. Hence this regulation is not relevant to the proposed project.
7 . 1 . 7 Third National Environment Action Plan
The Third National Environment Action Plan is divided into principles, results and goals to achieve the results. Some of the fundamental principles prescribed in NEAP 3, which have been incorporated into this environmental impact assessment exercise include local democracy, informed decision making, continuous learning and improvement, right to information and participation and most importantly the complementing role of environmental protection in socio-economic development. The proposed project is expected to provide a learning experience in terms of effectiveness of the use of EIA as a planning instrument and appropriate monitoring for which specific focus is laid in Objective 24.1 of NEAP 3 (Ministry of Housing, Transport and Environment, 2009).
By undertaking EIA prior to developmental projects, it ensures that environmental impacts from the project activities are minimized / avoided. 7 . 1 . 8 Regulation cutting down, uprooting, digging out and export of trees
The Regulation on cutting down, uprooting, digging out and export of trees and
Page 20
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll palms from one island to another was issued by the Ministry of Environment, Energy and Water. Clause 5 (a) of the regulations states that Prior to the commencement of any project(s) that would require the indiscriminate removal and export of trees/palms from one island to another for the purpose of agriculture, development/development, construction or any other purpose, it is mandatory under the Regulation to prepare an Environmental Impact Assessment Report stating clearly the details of the Project(s) with all necessary information and submit the same through the relevant Ministry to Ministry of Environment Energy and Water, and the project(s) can only commence upon the grant of written approval from the Ministry of Environment, Energy and Water.
Article 8 (a) requires permission be obtained from Ministry of Environment, Energy and Water, if more than 10 coconut palms that are of a height of 15 ft (from base of the palm to the tip of the palm frond) are cut, uprooted or relocated to another island. The regulation also ensures the replacement of the vegetation that is lost by imposing the planting of two palms for every palm tree that is cut or uprooted (Article 2 (d)). Logging on inhabited islands must be done under supervision of the islands chief or an official appointed by the island chief (Article 8 (c)).
The proposed project in Dhiggaru does not require removal of trees. All the proposed pump stations are already cleared of vegetation.
7 . 1 . 9 Post EIA Monitoring, Auditing and Evaluation
The environmental monitoring programme given in EIA report is an important aspect of the EIA process. The monitoring programme outlines the objectives of the monitoring; the specific information to be collected; the data collection program, and managing the monitoring programme. Managing the monitoring programme requires assigning institutional responsibility, reporting requirements, enforcement capability, and ensuring that adequate resources are provided in terms of funds, skilled staff, etc.
The monitoring programme outlined in this report will comply with the EIA Regulations 2012. 7.2 International Conventions 7 . 2 . 1 Climate Change Convention and Kyoto Protocol
The Maldives is a party to the United Nations Framework Convention on Climate Change (UNFCCC) and the Kyoto Protocol to the UNFCCC. The objective of the Convention is to stabilize greenhouse gas concentrations in the atmosphere at a
Page 21
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll level that would prevent dangerous anthropogenic interference with the climate system. The greenhouse gas inventory of the Maldives forms an integral part of the First National Communication of the Maldives to the UNFCCC.
In March 2009, the government of the Maldives announced the target to make Maldives carbon neutral by 2020. Hence, in the implementation of the project, careful attention needs to be given to ensure energy efficiency and reduce transport related fuel consumption.
7 . 2 . 2 Convention on Biological Diversity
The Maldives is a party to the United Nations Convention on Biological Diversity. The objective of the convention is “the conservation of biological diversity, the sustainable use of its components and the fair and equitable sharing of the benefits arising out of the utilization of genetic resources, including by appropriate access to genetic resources and by appropriate transfer of relevant technologies, taking into account all rights over those resources and to technologies, and by appropriate funding. The proposed development activities outlined in this project does not fall on any area recognised for its ecological value. Therefore it is unlikely there will be a major loss of biodiversity. The loss is not going to be significant at atoll or national level. Yet, it is recommended that the developer ensures that mitigation measures are taken to reduce the impact of terrestrial biodiversity.
Page 22
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
8 Project Description 8 . 1 Project proponent
This project is proposed by the government of Maldives with Ministry of Environment and Energy as the implementing agency. Ministry of Environment and Energy is the government ministry responsible for the welfare of the environment including water, waste management, sanitation and environmental management. The Ministry of Environment and Energy has awarded the contract to MWSC.
This sewerage system will be designed and constructed by Male‟ Water and Sewerage Company Pvt. Ltd (MWSC) The Company has been established in the year 1995 with the purpose of solving the growing water needs in Malé. The principle objective of the company was to design, develop, operate, manage and maintain the public water, wastewater collection and disposal system in Malé. MWSC has attained achievements including International awards for its success in operations and sharing its knowledge and business practice with regional utility companies. MWSC became an ISO 9001 certified Company in July 2006 on the basis of its good management of business.
MWSC has gained significant amount of knowledge and experience in designing, constructing, managing and operating water and wastewater related facilities during the past 21 years of its existence.
8 . 2 Project Location and Study Area
The project takes place in the island of Dhiggaru in Meemu Atoll. Dhiggaru is located in Mulaku Atoll at 3° 6'42.93"N and 73°33'55.90"E and the land area is 12.8 Ha. The registered population of the island is 982 (Census, 2014) and the actual population, according to island council, is believed to be 1371. Major occupation of the community is fishing and majority of the younger population is involved in the tourism sector. There are 249 registered house plots in the island, out of which 178 are currently occupied. The census 2006 population was 909.
There is an existing water supply facilities established in the island which was installed by MWSC. Electricity is operated by the Fenaka Cooperation. There are few private sewer main pipes laid in the some roads which outfalls into the shallow lagoon by gravity.
Page 23
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Figure 1: Location of Dhiggaru island in Meemu Atoll
8 . 3 Need and Justification for the project
The proposed project, appropriate sewage disposal or wastewater management has always been a high priority for the islands of the Maldives. Maldives being a premium tourist destination promoting sun, sand and sea as the main tourism products has much to offer in terms of pristine environmental quality. The white sandy beaches and crystal clear lagoons are among the main attractions of the Maldives. Most of the resort islands boast of the best beaches in the world. Furthermore, Maldives provides nearly “perfect” dives to its guests through designated Marine Protected Areas and even the house reefs of the resort islands.
Despite the importance of the beaches and coastal waters to the economy of the Maldives, the beach and lagoon in inhabited islands of the Maldives has been regarded as a dumpsite and often referred to as “gondudhoh” which directly translates to “dumping ground” or “dumpsite”.
However, the impacts of both burial and disposal into the nearshore and groundwater environment have now become evident. In some of the inhabited islands, the lagoonal waters have been deteriorated to the extent that they are not even suitable for swimming. If people do swim, skin rashes and other health effects become
Page 24
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll prevalent especially in young children who are fond of the lagoon/nearshore environment. Additionally, the increased nutrient levels in lagoons aid the growth of sea grass making marine waters aesthetically unpleasant.
Similarly, the disposal of improperly treated wastewater to the ground has resulted in the contamination of the groundwater in many inhabited islands of the Maldives and Dhiggaru being among them.
In addition to the improvements in environmental quality which itself has economic benefits, there are several other socio-economic benefits of proper sewage and wastewater disposal. These include:
Protection of the groundwater aquifer, which is the main source of water for the communities. This in turn helps in reducing morbidity and mortality due to water-borne diseases. Health benefits due to improvements in environmental health Protection of groundwater means that the community can rely on a safe source of water for basic needs other than potable use.
Site investigation of Dhiggaru Island revealed that the island is almost flat, and ground water is contaminated and smelly. Housing is clustered in to blocks which have taken up the entire island‟s available landmass. Most households have a septic tank or a pit to which all human waste is disposed. In addition, some private sewers have been constructed with houses connecting their wastewater pipes to this and eventually disposing the sewer in to the nearshore environment.
Proper sewage collection and disposal has now become a key basic requirement for all inhabited islands as human development is significantly impacted without this basic facility.
8 . 4 E x i s t i n g s a n i t a t i o n s y s t e m
At present, the island has two types of wastewater disposal system. 1- Septic tanks that treat and dispose the wastewater in to ground.
2- Private sewer networks laid in some main pipes that connect groups of houses. The final disposal is to the near shore lagoon.
According to Ministry of Environment and Energy, this project does not involve decommissioning of the existing sanitation systems in the island.
Page 25
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
8 . 5 What does the project constitute?
A gravity sewer system is proposed for Dhiggaru island. The gravity sewerage network is divided into two zones. The reason being that two pumping stations have been proposed in this Island. Two Pumping Stations will be constructed in the Island for collection of Sewerage which is integrated by pumping mains. From the main Pump Station sewerage is pumped out by means of the sea outfall beyond the reef. This will ensure that the wastewater disposal takes place in the deep sea where proper dilution will take place.
The project involves the following components: a) Installation of an island wide sewage collection network.
b) Installation of new catch pits for each house / institution.
c) Construction of pump stations in strategic locations to collect and convey raw sewage to the final disposal station.
d) Construction of a sea outfall.
8 . 5 . 1 The schematic diagramme of the wastewater system
The following figure outlines the schematics of the sewerage system.
Figure 2: Schematics of the sewerage system
8 . 5 . 2 House hold connections
The first element and perhaps a very basic component of this project are at the household level. Individual households will have private toilets that are pour flush or
Page 26
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll fitted with automatic flush tanks to carry the wastewater in to the system. This is the point where the wastewater disposal process begins and therefore forms an important aspect of the disposal cycle. Wastewater will flow by gravity to catch pits located inside each house plots. These catch pits will be constructed as part of the project.
8 . 5 . 3 Sea outfall
Wastewater will be pumped to the deep sea using the sea outfall. The seaoutfall will be constructed on the lagoon by laying the pipeline and securing the pipe with anchor blocks. At the planning stage of the project MWSC proposed an outfall location on the north side of the island. After the EIA study consultation with island council and MWSC the outfall location is changed to the east side of the island. End Figure below shows the location of the proposed outfall for this project and a diagram of how outfall will be anchored on the lagoon. Bathymetry and cross section profile of the outfall location is attached as an annex.
Figure 3: Outfall location of Dhiggaru as initially proposed
Page 27
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Figure 4: Final outfall location
8 . 5 . 4 T w o Pump stations
There are two pump stations (PS) allocated. The sewer network has been designed to carry the sewage under gravity from households to each of the two pump stations. Pump stations (PS1) will pump sewage to PS2 which will eventually dispose the raw sewage in to the ocean. The land allocated for the Pump Stations were discussed with the Island Council and the approved locations were sent to Ministry of Environment and Energy. Finalized location of the Pump station was decided after Ministry of Environment discussed with Ministry of Housing (Land Authority) and the Island Council. Diagram of the finalized location is attached on the next page.
The two pumping Stations are to be constructed in the Island for collection of Sewerage from the gravity Sewerage main line and are to be pumped to the sea outfall. Civil constructions of the Pump Stations are of RCC. Pumping stations 1 will discharge wastewater through the sewage pumping main (HDPE) to the pumping station 2. The number of pumps in each pumping station will be two (one working + one Stand-by). An automated control panel is provided for the pumps to alternate between the working pump and the standby pump for consecutive pumping events. Each pump capacity will have peak flow capacity. The following table shows the details of the Pumps used in most pump station.
Page 28
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
1.0 PUMPING STATION SUBMERSIBLE PUMP DETAILS
1.1 Pump Maker‟s Name FLYGT 1.2 Level control type(s) Ultrasonic or float switches 1.3 Country of Origin Sweden
Pumping Station Float Levels are as follow;
- Low Level : Pump cut off level
- High Level : Pump I duty level
- Extra High level: Pump 2 duty level
Figure 5: Proposed pump stations locations
Attached on the following page are the pump stations sump and chamber sectional details.
Page 29
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
8 . 5 . 5 Treatment of wastewater
Treatment of wastewater is the most ideal method of disposal, especially when the receiving water body does not have the potential to dilute the sewage. The dilution potential is determined by the prevailing conditions in the receiving environment such as current flow, volume of water and frequency of disposal. Studies and hydraulic modelling undertaken in Male‟ indicate that although treatment is ideal before discharge, it is not required for such a size island as the wastewater is domestic in nature and there is high potential for dilution. In the future, it may be worthwhile to do at least a reduction of the BOD value by holding the wastewater in a large tank before disposal. In the project island, there is potential land area approved for such a facility if it is required in the future, as this project does not included construction and commissioning of a Sewerage Treatment Plant (STP).
8 . 5 . 6 Technology
Flygt submersible N series pumps will be used in pump stations. The number of pumps in each pump station will be two (1working + 1 Standby), each having the peak wet weather flow capacity of the zone). The highest efficiency values for typical single vane pumps are around 70% but flygt N pump series deliver 80% or better at 10-15% lower power consumption. And flygt pump maintains this efficiency even in fluids with high solid fibrous content. Required spare parts for operation and maintenance of the pumps will be available from xylem, Hong Kong branch.
The control system will be designed to control two pumps of desired capacity. The pump start stops will work on the high and low water level float switches installed in the collection sump.
The pumps will run on alternate basis i.e if pump P1 is running, P2 will be as standby. On the second start cycle P2 will run while P1 will stay as standby.
Operations of the pumps are controlled by level controllers/switches. A float switch is used as emergency float which will be switched on and alarm buzzer and beacon will be activated if both pumps are faulty or if the water level in the sump reaches the Alarm Level.
The control panel is designed with microprocessor based controller for automatic control and monitoring of the system. The system will alert on situation, as detailed below. Pump failure / trip alarm for each pump
Page 31
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
High water level alarm Supply power failure alarm Standby generator startup and trip alert. Low Low level alarm ( activated after specified period of time – dry run protection )
Panel board shall be fabricated in IP65 enclosures. Yet, the panel boards will be installed under a shed to protect from direct sunlight and rain. Cables from the pumps and float switches to the control panel will be laid through a cable duct or trench put in place from the sump up to the control panel mounting shed.
8 . 5 . 7 Design period
The Sewerage networks have been designed for a period of 35 years.
8 . 5 . 8 Population and household proje c t i o n
The projected populations have been estimated for a 35 year period which is the design horizon for the sewerage collection network. The following table shows the current population and projected population for 35 years. (The data has been collected from the Island record)
Present Population
At the time of the concept design, registered population of the island is 950 and the actual population is recorded as 1334. For the design the current population is taken as 1334. Based upon the above data, projected population in PS1 and PS2 area is distribution in the table below. This will be used as a basis of design.
Projected Population Network area Present population Predicted Growth Projected population PS1 area 640 1.5% 1078 PS2 area 694 1.5% 1169 Total 1334 1.5% 2247
8 . 5 . 9 F l o w r a t e s
The following table shows the flow rates that have been considered for the design of the network. (The flow rate is inclusive of 10% filtration as per EPA guideline).
Peak wet weather flow
Page 32
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Average Dry Average Wet Peak wet weather weather flow Peak factor weather flow flow Network area (AWWF) (PWWF) (ADWF) (m³/day) PS1 area 129.36 142.30 3.0 426.90 PS2 area 140.28 154.31 3.0 462.93
Table 2: Flow rates of the pump stations
8 . 5 . 1 0 Sewerage network design
Conventional gravity Sewerage system, mainly consisting of uPVC of OD 160 mm OD uPVC pipe has been used for the main Sewerage network and OD110mm have been used for house connection. Network site plan including manhole location is attached on the following page.
8.5.10.1 Design parameters
The following design parameters and considerations according to the EPA guideline (Design criteria and technical specifications for conventional gravity sewerage systems) were taken during the design of the Sewerage network; Minimum slope of 1 in 250 has been taken. The pipe network have been desgined for a full flow velocity of 0.64m/sec Maximum Depth of 2.5m has been considered for pipe laying. Infiltration of 10% had been considered in the flow rates. Peak factor of 3 is considered. Manhole / Access Chamber spacing of not more than 60m and will be provided at street crossings, change of slope, change of size/direction of street sewer. The manhole will be of plastic material like uPVC or HDPE
8.5.10.2 Sewerage Flow formula;
The sewerage network has been designed using the following formula;
Manning Formula
Q=AxV 2/3 1/2 V=1/nxR xI Q: Design wastewater flow incl.reserve capacity(m3/s) A:Sectionareaofsewageinpipe(m2) V: Velocity(m/s) N: Roughness coefficient
Page 33
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
R: HydraulicRadius=A/P(m) P:Wettedperimeter(m) I: Slope
8.5.10.3 Network design
The main sewer is OD 160mm laid at slope of 1 in 250 in all areas. This will provide a peak discharge of 462.93 m³/day according to Island maximum discharge in a PS area. At 120 Lcd with a peak factor of 3, this translates into a population capacity of maximum 1169 in one PS area network. Each road will have a collector of 150 mm main line which will join an inlet into the pump station or last manhole in zones where pump stations located.
Page 34
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
8 . 6 B r i e f d escription of the sewage disposal p r o c e s s
The system will collect raw sewage from households and convey to the pump stations through gravity. The sewage will be disposed to the deep water beyond the reef without any treatment.
8 . 6 . 1 T echnical details
The following table outlines the Raw Effluent Quality (Domestic Sewage & Wastewater) Parameter Characteristics of Influent Biochemical Oxygen Demand (BOD5) 350 mg/l Chemical Oxygen Demand (COD) 650 mg/l Suspended Solids 500 mg/l Oil & Grease 3-30 mg/l pH 6.5-80 Water Temperature 28 0C Figure 6: Characteristics of the wastewater
The following table outlines the EPA guidelines for maximum allowable concentrations for discharge into deep waters EPA guidelines for maximum Parameter allowable concentrations for discharge into deep sea. Biochemical Oxygen Demand (BOD5) 40 mg/l
Chemical Oxygen Demand (COD) 50 mg/l
Suspended Solids 150 mg/L
pH 5 -9.5
Oil & Grease (After effective fat/Grease trap) 5 mg/L
Figure 7: EPA guidelines for maximum allowable concentrations for discharge into deep sea
8 . 7 Project management
The project will be managed by MWSC by way of subcontracting some of the civil works to contractors. Other technical and engineering services will be managed by MWSC team. The contractor will provide a daily work schedule for the project and will be responsible from hiring labourers to supply, installation and commissioning of the works assigned to that contractor.
Page 36
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
8 . 7 . 1 Project duration
The total project duration is expected to be 12 months after the approval of the EIA. Mobilization is expected to start during first quarter of 2017. A project schedule is attached in annex.
8 . 7 . 2 Planning and Programme
The project will be implemented through a carefully managed plan. Mobilization will be initiated during first quarter of 2017.
8 . 7 . 3 Waste Management
Managing the waste generated during the construction stage is a responsibility of contractor. There is an existing waste management center in the island. Domestic waste can be managed using the existing system. However, it is not recommended to use existing waste management cycle in Dhiggaru to manage hazardous waste produced during the construction. Such waste needs to be transported to Thilafushi for disposal.
8 . 7 . 4 S a f e t y
Full recognition and regard should be taken in the management and execution of project safety plan. Any subcontractors are obliged to provide safety policies, plans and method statements and will be interviewed prior to order placement on all aspects of safety, health and welfare. All sites are subject to independent site safety checks, inspection and reports by independent site safety inspectors and advisors.
8 . 7 . 5 Housing of temporary labour
Housing of labour will also be the responsibility of the contractor. Priority should be given to rent houses from island, so existing utility services can be used rather than constructing temporary facilities. According to Island Council, there are plenty of houses that can be rented for labour housing.
8 . 8 Risks Associ ated with the Project
There are many risk factors associated with this project that could possibly have both financial and environmental implications. The scheduling of the project would affect the lives of many people at the island, especially during the road excavation. Hence proper information needs to be provided to the public to make them aware of
Page 37
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll the scheduling of the project. There is also the risk of project delays caused by bad weather. This risk can be minimized if the works are scheduled as such that weather is taken as important aspect in the project planning.
8 . 9 Project Inputs and Outputs 8 . 9 . 1 Project Inputs
Input resource(s) Source/ Type How to obtain resources 10 to 15 Construction Maldivians +foreign Contractor‟s responsibility workers labours Operational Staff. 3 to 4 Locals Advertise in local papers or obtain local staff trained by through island office contractor and working in shifts. Already MWSC has the technical and human resource capability. Construction materials UPVC pipes, reinforcement Import and purchase where locally steel bars, sand, cement, available at competitive prices – aggregates, etc. Contractor‟s responsibility. Maintenance material. 5- Pump spares, catchpit Import and also local purchase year spares made covers, replacement pipes, available cleaning gear etc. Water supply (during RO and groundwater from From the island. construction) the island Electricity/Energy Electricity from the Diesel-based electricity from island (during construction) island‟s main power grid. mains Electricity/Energy Electricity for operation Diesel-based electricity from island (during operation) mains Table 3: Matrix of major inputs during construction period
Page 38
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
8 . 9 . 2 Project Outputs
The type of outputs (products and waste streams) and what is expected to happen to them are given in the following table. Products and waste Anticipated quantities Method of disposal materials Effluent ready for Refer to Table 2 Disposed to open sea via pumping discharge to deep sea station. Sludge Approximately 0.38% of Dried and used as fertilizer or disposed the total. in to the deep sea. This will be required to do once in 3 years. Constructional waste Small quantities Reused and sent to landfill (Thilafushi) Noise Localised to the project Unavoidable during the construction site including the stage but will be minimized. Noise will surrounding areas. not be a nuisance as manual labour will be used without the need for any heavy machinery. Air pollution Limited quantities of dust, Mainly arising as a result of emission oxides of Nitrogen and from the construction work such as sulphur from use of from excavation of trenches to replace machinery in the the catch pits and pipes. construction zone. Foul odour Moderate levels at Venting will be done and pump station pumping station during will discharge to the deep sea. Pump the pumping hours stations are located in appropriate areas especially. away from the general community as much as possible. Table 4: Matrix of major outputs of environmental significance during construction stage
Page 39
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
9 Methodology
This section outlines the methodologies used in this environmental assessment. The following table outlines a matrix of methodologies used in this project. Details of these methodologies and their descriptions are attached as an annex.
Methodology type Area / environmental aspect Used in this project (yes/no)
General methodologies of data Generally covering the Yes collection broader Environment Mapping and location identification Coastal, terrestrial and Yes marine environment. Marine Environmental survey Marine environment Yes
20 m Line Intercept transect (LIT) Marine environment Yes
50 m photo quadrate analysis Marine environment No
Qualitative assessment of the reef Marine environment Yes Permanent photo quadrate Marine environment No Ref fish visual census Marine environment Yes
Marine Water Quality Marine environment Yes Coastal Environment Coastal Environment Yes Shoreline and vegetation line Coastal Environment No mapping Coastal structures mapping Coastal Environment No
Erosion and accretion areas Coastal Environment No mapping Beach profiles Coastal Environment No
Drogues and current Coastal Environment Yes Terrestrial Environment Terrestrial environment Terrestrial floral survey Terrestrial environment Yes Terrestrial faunal survey Terrestrial environment No Groundwater assessment Terrestrial environment Yes Bathymetry Marine / Coastal Yes Environment Aerial Photos Generally covering the Yes broader Environment Long term weather data Generally covering the Yes broader Environment
Page 40
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
10 Existing Environment 1 0 . 1 Existing Marine Environment
The marine environmental survey at Dhiggaru was focused on three sites as indicated in the diagramme below. Site selection for the marine survey was based on the location where the sea outfall will be constructed.
Figure 8: Marine Survey Locations
1 0 . 1 . 1 Methodology of marine surveys
To assess the benthic composition of the survey site, an LIT transect of 20 meters were undertaken. The benthic categorization was focused on categorizing life forms followed under the Reef Check protocol, which emphasises on benthic composition categorizing such as hard corals, sand, rock and others. The emphasis is not on recording corals to their species levels, but rather the general coral and other life forms such as hard and soft corals. This method is more accurate as the percentage of healthy coral cover and other life forms can be more accurately recorded even by a non-experienced surveyor. Recording corals to their species levels will pose difficulty if the surveyor is not familiar with the different coral types. This method is universally used throughout the world by Reef Check surveyors and hence
Page 41
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll it has been used.
This LIT method was also complimented by qualitative methods, such as visual observations and through the use of photos. Fish counts were also undertaken to get a snapshot of the fish population. Details of these methodologies are discussed in the methodology section.
The following are definition of benthic categories used in this survey. HC: All living coral including bleached coral; includes fire, blue and organ pipe corals SC: Include zoanthids but not anemones (OT) RKC: Coral that has died within the past year; appears fresh and white or with corallite structures still recognizable NIA: All macro-algae except coralline, calcareous and turf (record the substrate beneath for these); Halimeda is recorded as OT; turf is shorter than 3cm. SP: All erect and encrusting sponges (but no tunicates). RC: Any hard substrate; includes dead coral more than 1 yr old and may be covered by turf or encrusting coralline algae, barnacles, etc. RB: Reef rocks between 0.5 and 15cm in diameter SD: Sediment less than 0.5cm in diameter; in water, falls quickly to the bottom when dropped. SI: Sediment that remains in suspension if disturbed; recorded if color of the underlying surface is obscured by silt.
OT: Any other sessile organism including sea anemones, tunicates, gorgonians or non-living substrate.
General impression and quantitative results of the sites surveyed are described in the following pages.
1 0 . 1 . 2 C o r a l r e e f
Three sites were surveyed to assess the marine environment as baseline for reef benthic community. Three sites from east side of the island lagoon and reef was selected.
For more information about marine environment of Dhiggaru island, refer to the report, EIA for Redevelopment of Harbour at M. Dhiggaru (MEECO, 2015) and First Addendum to EIA for Harbour Redevelopment Project at M. Dhiggaru (Water Solutions, 2016).
Page 42
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
10.1.2.1 Status of coral reef at site 1
Site 1 was chosen from the eastern side of the island lagoon. Proposed outfall pipeline will pass on this lagoon bottom. There is an existing brine discharge pipe from RO Plant in this area. Site 1 mainly has coral rubbles and is less than 1.5m deep in most area. Few scattered massive corals were found in this area. However, most of the lagoon bottom of this area is dead with sand and rubble. The following graph outlines the percentage benthic composition at site 1 and the following table outlines the results of the LIT transect at site 1 in Dhiggaru island.
Figure 9: Percentage benthic composition at site 1
Live reef cover Mean % per segment SE HC 3% 1% SC 0% 0% NIA 0% 0% SP 0% 0% OT 2% 1% Non-living reef cover Mean % per segment SE RKC 0% 0% RC 20% 0% RB 50% 0% SD 25% 0% SI 0% 0% Table 5: Percentage benthic composition at site 1
Page 43
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Live coral cover at site 1 was 3%. Of the non-living components, rubble dominated this area with 50%. Percentage of sand is 25%. Below are the photos from the site.
Figure 10: Marine photos from Site 1
10.1.2.2 Status of coral reef at site 2
Site 2 was selected from the east side of the island reef and it is the proposed location of the sea outfall. The reason for selecting this location was to assess the reef health as baseline in order to ensure that the proposed seaoutfall has the least impact on this area, and hence help to monitor the reef. This area has live coral colonies most notably massive coral species. In addition, few Pocillopora sp and Porites rus species were also found. Benthos of this area was dominated by rocks and live corals. Reef slope of this area is very steep and resemble a wall. This site faces the channel between Dhiggaru and Maduvvari house reef. This channel has very strong ingoing and outgoing current especially during tide transition period. Fish population was another indicator that was used to assess the health of the site. Most of the fishes at this site were limited to herbivore species. They were moderate but the diversity of
Page 44
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll fish population can be considered low. To assess the fish population, fish counts were done for fish families as used by the Reef Check fish survey method. Fish population was considered abundant. The following graph outlines the percentage benthic composition at site 2 and the following table outlines the results of the LIT transect at site 2 in Dhiggaru island.
Figure 11: Percentage benthic composition at site 2
Live reef cover Mean % per segment SE HC 18% 3% SC 0% 0% NIA 0% 0% SP 5% 0% OT 5% 0% Non-living reef cover Mean % per segment SE RKC 3% 0% RC 39% 3% RB 25% 0% SD 5% 3% SI 0% 0% Table 6: Percentage benthic composition at site 2
Live coral cover at site 2 was 18%. Of the non-living components, rocks
Page 45
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll dominated this area with 39%. Percentage of coral rubbles is 25% and sand is 5%. Following are the photos from the site.
Figure 12: Marine photos from Site 2
10.1.2.3 Status of coral reef at site 3
Marine survey site 3 is on the east of the island reef as a control site and as an alternative site to outfall. Benthic composition of the site 3 is dominantly covered with rocks and rubbles. Few Massive coral species were observed in this location. This side of the island reef faces the channel between Dhiggaru and Maduvvari. Reef slope of this area is very steep similar to site 2. Underwater photos from this location are attached below.
Page 46
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Figure 13: Percentage benthic composition at site 3
Live reef cover Mean % per segment SE
HC 8% 0% SC 0% 0% NIA 0% 0% SP 0% 0% OT 5% 0%
Non-living reef cover Mean % per segment SE RKC 1% 1% RC 56% 4% RB 23% 4% SD 8% 0% SI 0% 0% Table 7: Percentage benthic composition at site 3
Live coral cover at site 3 was 8%. Of the non-living components, rocks dominated this area with 56%. Percentage of coral rubbles is 23%. Below are the marine photos from site 3.
Page 47
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Figure 14: Marine photos from Site 3
1 0 . 1 . 3 Status of fish abundance
The amount and type of fish present at a given site can be a good indicator of the marine environment. For example, increased grazers are generally a sign of increased nutrients in the area, thus decreased coral cover and increased algal cover. Similarly, more live corals will attract more fish and some of the fishes are associated with different types and growth forms of corals. For example, Damselfish like Dascyllus sp. or Chromis sp. are common fish found in branching corals and large schools are often seen around healthy branching corals. For the fish census, only indicator families were recorded as per Reef Check protocol.
Fish counts for site 1 are outlined below
0-5m 6-10m 11-15m 16-20m Butterflyfish Family Chaetodontidae Grunts/Sweetlips/Margates Family Haemulidae Snapper Family Lutjanidae 2
Page 48
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Barramundi cod Cromileptes altivelis Humphead (Napoleon) wrasse Cheilinus undulatus
Bumphead parrotfish Bolbometopon muricatum Other parrotfish ONLY >20cm Family Scaridae Moray eel Family Muraenidae 1
Grouper ONLY >30cm Family Serranidae 0-5m 6-10m 11-15m 16-20m 30-40 cm 40-50 cm 50-60 cm >60 cm
Rare animals sighted (#/type/size) 0-5m 6-10m 11-15m 16-20m Sharks Turtles Mantas Other Table 8: Fish census survey results for site 1
Fish counts for site 2 are outlined below
0-5m 6-10m 11-15m 16-20m Butterflyfish Family Chaetodontidae 2 1 3 4 Grunts/Sweetlips/Margates Family Haemulidae Snapper Family Lutjanidae 3 1 11 Barramundi cod Cromileptes altivelis 2 Humphead (Napoleon) wrasse Cheilinus undulatus
Bumphead parrotfish Bolbometopon muricatum Other parrotfish ONLY >20cm Family Scaridae 6 3 1 7 Moray eel Family Muraenidae
Grouper ONLY >30cm Family Serranidae 0-5m 6-10m 11-15m 16-20m 30-40 cm 1
Page 49
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
40-50 cm 50-60 cm >60 cm
Rare animals sighted (#/type/size) 0-5m 6-10m 11-15m 16-20m Sharks Turtles Mantas Other Table 9: Fish census survey results for site 2
Fish counts for site 3 are outlined below
0-5m 6-10m 11-15m 16-20m Butterflyfish Family Chaetodontidae 1 1 Grunts/Sweetlips/Margates Family Haemulidae Snapper Family Lutjanidae 1 3 2 Barramundi cod Cromileptes altivelis Humphead (Napoleon) wrasse Cheilinus undulatus
Bumphead parrotfish Bolbometopon muricatum Other parrotfish ONLY >20cm Family Scaridae 2 3 1 5 Moray eel Family Muraenidae 1
Grouper ONLY >30cm Family Serranidae 0-5m 6-10m 11-15m 16-20m 30-40 cm 1 1 40-50 cm 50-60 cm >60 cm
Rare animals sighted (#/type/size) 0-5m 6-10m 11-15m 16-20m Sharks Turtles Mantas Other Table 10: Fish census survey results for site 3
Page 50
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
1 0 . 1 . 4 Marine water quality and bathymetry
The primary objective of the marine water quality sampling was to determine the baseline conditions of the marine water in the proposed sea outfall location. Qualitative and quantitative assessments were made on seawater from one location. Chemical properties were tested on site using YSI Multiparameter probe. Samples were taken and sent to laboratory for biological parameter testing. The bathymetry of the lagoon where the sea outfall is proposed is attached as an annex. The following table illustrates the result of the marine water quality test.
Water Quality Site SW1 Optimal range Ref
Physical appearance Clear Electrical Conductivity (us/cm) 55100.00 Temperature C 18 - 32 Degree GBRMPA 2009 29.00 Celcius Salinity (mg/l) or PPT 34300.00 3.2% - 4.2% GBRMPA 2010 pH 8 to 8.3. Levels 8.50 below 7.4 will cause stress Turbidity (NTU) 3 to 5 NTU. > 5 Cooper et al 2008 3.00 NTU causes stress BOD 760 mg/L
COD 8 mg/L DO >800 µg/L
Nitrate 6 ppm Suspended solids (mg/l) 8.00
Total coliform 0
Faecal coliform 0
Table 11: Results of the marine water quality tests undertaken in Dhiggaru island
Page 51
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
1 0 . 1 . 5 Prevailing currents around the sea outfall l o c a t i o n
To understand the water current around the island, current measurements should be taken over a long period of time. Currents data around specific islands are not available in the Maldives. However, during the EIA process, currents were measured around the proposed outfall area to obtain a snapshot of the existing conditions prevailing and to link them with the historical and present conditions. Nevertheless, this data set may not represent the actual current patterns around the island. During the course of the day, currents change twice with the changing tide and monthly with the moon cycles. The result therefore is a very complex change in current direction. Proposed outfall location is discussed with island council and fisherman of Dhiggaru. They informed that construction of outfall to the channel between Dhiggaru and Maduvvaru is the best option in case of Dhiggaru as there is strong current inside channel throughout the day. They also highlighted that putting outfall to north side reef facing out of atoll is also an option. However, this area is not preferred as this area has strong wave throughout the year which may destroy the outfall and increase the maintenance frequency of the outfall. Council also highlighted that brine from RO plant is also discharged to the channel.
To measure the currents around the proposed sea outfall location, a drogue test was undertaken. The test was undertaken using a floating GPS and the results are illustrated below.
Page 53
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Figure 15: Water current measured during the field visit to Dhiggaru
Figure 16: Monsoonal wind waves around the island
Page 54
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
1 0 . 1 . 6 W a v e s
It was not possible to obtain site specific data on wave conditions due to lack of time. Studies conducted elsewhere in the Maldives have been considered as a general guide to wave conditions at Dhiggaru.
Two major types of waves have been reported on the coasts of the Maldives: wave generated by local monsoon wind and swells generated by distance storms. The local monsoon predominantly generates wind waves which are typically strongest during April-July in the south-west monsoon period. During this season, swells generated north of the equator with heights of 2-3 m with periods of 18-20 seconds have been reported in the region. Local wave periods are generally in the range 2-4 seconds and are easily distinguished from the swell waves.
Distant cyclones and low pressure systems originating from the intense South Indian Ocean storms are reported to generate long distance swells that occasionally cause flooding in Maldives (Goda, 1988). The swell waves that reached Malé and Hulhule in 1987, thought to have originated from a low pressure system of west coast of Australia, had significant wave heights in the order of 3 metres.
In addition, Maldives have been subject to earthquake generated tsunami reaching heights of 4.0m on land (UNEP, 2005). Historical wave data from Indian Ocean countries show that tsunamis have occurred in more than 1 occasion, most notable been the 1883 tsunami resulting from the volcanic explosion of Krakatoa(Choi and others, 2003).
1 0 . 1 . 7 T i d es
Tide affects wave conditions, wave generated and other reef-top currents. Tide levels are believed to be significant in controlling amount of wave energy reaching the island, as no wave energy crosses the edge of the reef at low tide under normal conditions. In the Maldives where the tidal range is small (1m), tides may have significantly important influence on the formation, development and sediment movement process around the island tides also may play an important role in lagoon flushing, water circulation within the reef and water residence time within an enclosed reef highly depends on tidal fluctuations.
Tide data is important information in any coastal development project as it determines the elevation of the structures relative to a datum. A permanent tidal record station has been established at Ibrahim International Airport by Maldives
Page 55
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Meteorological Service. The maximum tidal range recorded at this tide station is 1.2m. The highest astronomical tide level is +0.64m (MSL) and lowest astronomical tide level is -0.56m MSL). The following table gives a summary of the tide levels for the tide datum has been widely used in Maldives.
Table 12: Summary of the Tide Levels Hulhule Island, Male Atoll
Water level referred to Mean Sea Tide Level Level (MSL) (m) Highest Astronomical Tide (HAT) +0.64 Mean Higher High Water (MHHW) +0.34 Mean Lower High Water (MLHW) +0.14 Mean Sea Level (MSL) 0 Mean Higher Low Water (MHLW) -0.16 Mean Lower Low Water (MLLW) -0.36 Lowest Astronomical Tide (LAT) -0.56
1 0 . 1 . 8 Risk of storm surges and flood
The primary sources of natural hazard risks in Maldives are strong winds during monsoons or freak storms, earthquakes, island interior flooding caused by heavy rain, coastal flooding caused by high surf, storm surge, prolonged strong monsoonal wind, high astronomical tides or tsunamis, and sea level rise. Coastal flooding related flooding and wind damage can be considered as the most frequent natural hazards that occur in Maldives (see Maniku (1990), Luthfy(1994)). Most of these risk factors (apart from earthquake, wind damage and rainfall flooding), stems from the extremely low elevation of all Maldivian islands: the average elevation is 1.5 meters above sea level. In spite of the occasional natural hazards, Maldives in general is relatively from high risk natural disasters.
Spatial variations in hazards are evident across Maldives (Maniku, 1990). Northern atolls are more exposed to intense storm systems, increasing the risk of wind damage in these atolls. In comparison, southern atolls experience less storms systems, but are more exposed to flooding events, probably as a result of exposure to intense South Indian Ocean storm surges and wind-waves during south west monsoons. Southern atolls are also more likely to experience earthquakes.
Observations from the field visit to Dhiggaru indicate that coastline of the island is heavily modified with seawalls on whole east side of the island. Reef edge is in very close proximity to island shoreline of east side making this side very vulnerable to wave surges. According to island council, east side of the island is very
Page 56
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll prone to storm surges during north east monsoon. They experience impact of wave surges on east side of the island during north east monsoon in almost every year. Flooding of the areas from wave surges near the east coastline occurred during the last north east monsoon.
Figure 17: East side of Dhiggaru Island
1 0 . 1 . 9 Marine Protected Areas and Environmentally Sensitive Areas
There is no Marine Protected Areas (MPA) in Meemu Atoll. However, there are 10 Environmentally Sensitive Areas (ESA) inside MeemuA Atoll. The closest ESA to project site, Dhiggaru, is Veyvah Faru which is 18km southeast to Dhiggaru. Second nearest ESA is Raabandhi Huraa located 19km west to project site. It is not estimated that proposed project will have any impacts on any of the ESAs.
Page 57
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
1 0 . 2 Existing Terrestrial Environment 1 0 . 2 . 1 Section Brief
The terrestrial environment of Dhiggaru was assessed using the following methods: 1- High definition low aerial photography to assess the vegetation and the island as a whole from above. Particular focus was given to areas where pump stations will be constructed.
2- Ground truthing of the island and by undertaking a visual inspection of the areas where the proposed pump stations will be constructed. The objective of the terrestrial assessment was to identify whether any vegetation clearance would be required to construct the pump stations or while laying the pipe line.
3- Testing the ground water quality both quantitatively and qualitatively.
The sewerage pipes will be laid on existing roads areas and does not require cutting or clearing any vegetation. Hence, no detail tree surveys were undertaken as it is irrelevant for this project.
The diagrammes attached in the following pages depicts the terrestrial environment of Dhiggaru.
1 0 . 2 . 2 Vegetation at pump stations
Dhiggaru island has very few vegetation compared to most of the inhabited islands of Maldives. Whole land area of Dhiggaru island has been used for housing and other infrastructures other than a part of reclaimed land on north side of the island. According to island council, the reclaimed land area is also reserved for housing plots. Most of the roads of Dhiggaru is narrow and has no vegetation. Therefore sewer network construction does not require any vegetation clearing. Proposed pump stations are also cleared land. However, 1 Dhiggaa (Hibiscus tiliasceus) and 1 Hirundhu (Thespesia populnea) tree may be removed near the pump station 1 to make the boundary wall for the pump station (this will be confirmed after a detailed land survey). Below are the aerial and ground photos taken during the field visit.
Page 58
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Figure 18: Aerial photo of Dhiggaru taken during field visit (October 2016)
Page 59
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Figure 19: Location of Pump station 1
Figure 20: Location of pump station 2 and STP
Page 60
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
1 0 . 2 . 3 Ground water
Groundwater quality was assessed by taking a sample from a groundwater well. The household wells were visually inspected, and samples were tested for chemical properties such as electrical conductivity and salinity. The water quality results for the sampled wells of Dhiggaru are tabulated in the following table. The survey period coincided with the south west monsoon rains; it is possible that the salinity readings are biased to some extent.
It is assumed that freshwater can be defined by a maximum limit of 2500 µS/cm. WHO guidelines suggest a maximum Chloride content of 250 mg/l for potable uses which equates to a salinity of approximately 1,500 µS/cm. However experience in other small island states (Falkland, 2000) confirms whilst this is desirable, a more realistic limit is 2,500 µS/cm. Using this definition, it is clear that some of the sampled wells in Dhiggaru does not have freshwater.
The results are illustrated below.
Parameters GW1 GW2 GW3 GW4 GW5 GW6 tested Physical Clear Clear Clear Clear Clear Clear appearance pH 8 7.7 7.6 8 8 7.5 Temp (C) 29.3 29.9 29.4 30.2 30.8 29.6 Salinity (PPT)) 0.7 0.7 0.2 1 1.2 0.5 Electrical 1860 1025 374 1930 2290 985 conductivity (uS/cm) BOD mg/l 8 - 10 - - 13 COD mg/l 760 - 810 - - 920 Total Coliform 26 49 33 2 179 105 MPN/100ml Faecal 2 0 0 0 12 12 Coliform MPN/100ml Table 13: Results of the groundwater quality in Dhiggaru, Meemu Atoll
Page 61
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Figure 21: Groundwater sampling locations in Dhiggaru island (October 2016)
Page 62
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
1 0 . 3 C l i m a t e
There is no site specific climate data available for Dhiggaru. Therefore climate figures given below are either average climate data for Maldives or data for Male‟ region recorded in Hulhule Meteorological Station which is the nearest Meteorological Station to Dhiggaru.
1 0 . 3 . 1 R a i n f a l l and Infiltration
Annual average rainfall in Maldives is about 1900mm. There is a marked variation in rainfall across Maldives with an increasing trend towards south. The annual rainfall in north is 1977mm and for south is 2470mm. the southwest monsoon is known as wet monsoon with monthly average rainfall ranging from 125-250mm. The northeast monsoon is known as the dry season with average monthly rainfall of 50-75mm.
Figure 22: Monthly average rainfall since 2000 (Source: Maldives Meteorological Service)
Page 64
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Figure 23: Monthly rainfall data of Hulhule station for 2015 (Source: Maldives Meteorological Service)
Groundwater recharge from infiltration of rainwater is one of the primary resources of freshwater available to Dhiggaru. However, currently the groundwater condition of the island is not favorable in some parts of the island. Freshness of groundwater will depend on amount of rainfall to the island as the groundwater recharge from rainfall replenishes the thin freshwater lens that sits on top of brackish salt water beneath the island. Infiltration capacity of the rainwater will depend on the porosity of the soil. Previous studies done in Maldives indicate that most of the islands of Maldives have the recharge capacity of 30% of the total rainfall (Falkland, 2000). This will depend on the porosity of the soil and open spaces available in the island for rainwater to infiltrate to ground. Most islands of Maldives might be assumed to be having a good infiltration capacity as the island consists of coral sand and limestone soils. However, during the field visit to Dhiggaru it is observed that ponds created during the rain remain for hours even after the rainfall event, indicating that soil compaction and mud in the roads has reduced infiltration. For the recharge of the groundwater, it is very important to direct rainwater to open spaces or wells rather than the sewer network to allow the rainwater to seep into ground.
1 0 . 3 . 2 W i n d
Maldives Meteorological Service provides data for wind speed recorded in meteorological stations of Maldives. The windroses below shows the wind speed and direction recorded at Hulhule Meteorological Station in 2015 and for 20 year perios (1990-2010).
Page 65
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Wind (kts) Month/ Year Mean Maximum Dir Speed Dir Speed Jan-15 ENE 10 ENE 26 Feb-15 ENE 10 ENE 33 Mar-15 ENE 6 NE 27 Apr-15 W 5 W 25 May-15 WSW 11 W 35 Jun-15 WSW 9 W 40 Jul-15 W 9 W 46 Aug-15 W 9 W 39 Sep-15 W 10 W 39 Oct-15 SSW 6 W 30 Nov-15 W 7 NNW 32 Dec-15 NE 8 ENE 30 Figure 24: Monthly wind data for 2015 (Source: Maldives Meteorological Service)
Page 66
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Page 67
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
Figure 25: Monthly windroses (Source: Maldives Meteorological Service)
Page 68
EIA for the construction and setup of an island sewerage system in Dhiggaru Meemu Atoll
1 0 . 4 Existing Socio - Economic Environment 1 0 . 4 . 1 Introduction to the atoll
Meemu Atoll is located in the central region of Maldives. There are 8 inhabited islands and 2 resorts in Meemu atoll. The following table outlines the list of inhabited islands in the atoll.
Island Name Population (Census, 2014) Raimandhoo 113 Veyvah 254 Mulah 1264 Muli 862 Naalaafushi 426 Kolhufushi 748 Dhiggaru 982 Maduvvari 369 Total 5018 Table 14: List of inhabited islands in Meemu Atoll
Inhabited Islands by Atolls 16 15 14 14 14 13 13 13 13
12 11 10 10 9 9 9 8 8 8
6 6 6 5 5 4 4 3
2 1
0
Figure 26: Number of inhabited islands by Atoll
Page 69
Preliminary Results of Census 2014
ތ ވ ލ 15 : ރ ށ ރ ށ ގ އ ބ ދ ، ޖ ނ ސ ގ ނ ސ ބ ތ އ ދ އ ހ ރ ކ ށ އ ބ ދ އ ތ ރ ވ މ ނ ވ ރ - މ . އ ތ ޅ ، 2006 އ ދ 2014 Table P15 : POPULATION, SEX RATIO AND ANNUAL POPULATION GROWTH BY ISLANDS- M. ATOLL, 2006 & 2014
Mulakatholhu (M) (މ) ޅ ތ ކ ލ މ Population 2014 ދ ބ އ Maldivian Population 2006 ދ ބ އ ހ ވ ދ Maldivian Population 2014 ދ ބ އ ހ ވ ދ Total ލ މ ޖ Maldivians ނ ހ ވ ދ Foreigners ނ ސ ދ ބ