Estimating Contingency Sum for Building Works in Ghana

Total Page:16

File Type:pdf, Size:1020Kb

Estimating Contingency Sum for Building Works in Ghana Sci., Tech. and Dev., 32 (3): 266-275, 2013 ESTIMATING CONTINGENCY SUM FOR BUILDING WORKS IN GHANA RICHARD ODURO ASAMOAH1*, JAMES COFIE DANKU2 AND P.D. BAIDEN AMISSAH1 1Research Scientist, Building and Road Research Institute, Council for Scientific and Industrial Research, Kumasi, Ghana. 2Department of Building Technology, Kwame Nkrumah University of Science and Technology, Ghana. Abstract It is a common practice in the construction industry in Ghana to allow for contingencies to cater for any unforeseen events. This study was to identify existing methods of determining contingency sum, factors influencing contingency sum and develop a new system of determining contingency sum. The study employed a case study of some 38 completed building projects in Ashanti and Brong Ahafo regions of Ghana to compare the accuracy of both the existing and the new method. Questionnaires were distributed to the selected professionals. Relative Importance Indices Ranking and the Kendall coefficient of concordance were used to rank factors and the agreement of factors ranking among building professions. It was established that the most commonly used method is the Percentage Approach method. The study revealed that 77% of the building professionals have been using the Percentage Approach and 23% have been using the Probabilistic Estimation Methods. These methods were based on subjective approach. Economic, Environmental and Technical factors were identified as the most influential factors. The study concludes by developing a new software system of determining contingency sum and new method was found to be 45% more accurate than the Percentage Approach. Keywords: Contingency sum, Factors, Existing methods, Proposed new method. Introduction projects altogether. In particular, overestimated Contingency sum has been defined as an contingency sums limit the cash-flow to additional fund, meant to cater for unforeseeable contractors. To address these problems, it is elements of cost, within the defined project scope. important for building professionals to consider The purpose of contingency sum is to generate a other methods of determining contingency sums. reserve fund that may be sufficient to manage the Determination of an appropriate contingency sum inherent risk within the project, so as to complete requires an understanding of how estimators it on time (Ford, 2002). In Ghana, it is make budget contingency decisions and the characteristics of a construction work to proceed impact on the level of accuracy of the included without any risk appraisal. In order to address any contingency sum. The contingency sum is usually future risk, high contingency sums are included in expressed as a percentage mark-up on the base the mark-ups (Badu, 2004). There has been little estimate (Picken and Mak, 2001). In the empirical research into the concept of construction industry, building professionals have contingency sum, its intended scope and methods not been able to state the actual percentage range of estimating contingency sum in infrastructure for Contingency Sum. Available information, development contracts. The difficulty in however, indicates percentage ranges of 2.5% - determining contingency sum depends on 10%, which have been determined for some technical, economic and institutional factors selected projects financed by the Government of (Tawiah, 1999). Inappropriate contingency sums Ghana and other development partners, such as, have resulted in poor management of risk leading the African Development Bank and the World to underestimation or overestimation, delay in the Bank from 1999 to 2007 (GPRP/SIF, 2004). The completion of projects and abandonment of amount for contingency sum varies but 10% is *Author for correspondence E-mail: [email protected] ESTIMATING CO NTINGENCY SUM FOR BUILDING WORKS IN GHANA 267 recommended for lump sum projects and for Ghana. The study showed that the ‘Deterministic other types of contracts (cost plus contracts), it is Approach’ (Percentage Approach) was the most advisable to set contingency above 10% (Davey, widely used and known method for determining 1992). Contingency Sum by professionals in Ghana. As Existing Method(s) of Determining Projects indicated in Table 2, 77% of the sampled Contingency Sum in Building Works professionals have been using the Deterministic Approach and only 23% have been using the Baccarini in 2005 came out with 14 methods Probabilistic Estimation. The sampled of determining contingency sum for construction professionals had knowledge about the works. The methods are as follows; Estimating using Risk Analysis, Range Deterministic Estimation (Percentage Estimating and the Monte Carlo methods of Addition) determining the Contingency Sum, but have not Range Estimating used any of the methods before. Analytical Hierarchy Process Methodology and Data Collection Monte Carlo Simulation In this study, initial review of documents on Probabilistic Estimating the subject was conducted. Data collection was Methods of Moments carried out using the stratified random sampling Factors Rating technique. The target population comprised Individual Risks – expected value construction professionals, working in Kumasi Regression and Accra. The target professionals were Artificial Neural Networks Architects, Civil Engineers and Quantity Fuzzy Sets Surveyors. Furthermore, Kumasi and Greater Controlled Interval Memory Accra are the commercial cities in Ghana where Influence Diagrams many of the working building professionals are Theory of Constraints located and most of the construction activities in Preliminary survey conducted in the study the country could be located. Using the Kish indicated that among the above methods, building (1965) formula, the overall sample size of 224 professionals had knowledge or had used the was obtained and assuming a return rate of 45%, following methods before. These methods were: the sample size was increased to 250. Two hundred and fifty (250) questionnaires were (i) Deterministic Method (Traditional or administered to professionals in the building Percentage addition estimate). industry. A total of 133 questionnaires (ii) Probabilistic Estimation (Based on representing 53.2% of the total questionnaire experience of past projects completed) administered were returned. The return rate was (iii) Estimating using Risk Analysis (ERA) high for the Quantity Surveyors and out of the (iv) Range Estimating 53.2% returned questionnaire as indicated in (v) Monte Carlo Simulation Table 1. 79.70% were responsive and 20.3% were This study therefore used these known not responsive. methods to determine the most widely used method in the building construction industry in Table 1. Questionnaire Response from Professionals. Building Professionals No. of Questionnaires No. of Questionnaires % Rate of Returned Distributed Returned Quantity Surveyors 90 52 57.8 Architects 80 41 51.3 Civil/Structural 80 40 50 Engineers Total 250 133 53.2 Source: Field Survey, February – March, 2007 268 RICHARD ODURO ASAMOAH ET AL. Table 2. Questionnaire Response from Professionals. Quantity Civil Methods Architects Total % Surveyors Engineers Percentage Approach 43 27 21 91 77 (Existing Method) Probabilistic Method 8 12 8 23 23 Range Estimating 0 0 0 0 0 ERA 0 0 0 0 0 Monte Carlo 0 0 0 0 0 Total 51 39 29 119 100 Source: Field Survey, February – March, 2007 Kendall (1970) coefficient of concordance, The New Method of Determining Contingency the best estimate of true ranking (rating) of ‘n’ Sum objects is provided, where ‘W’ (the coefficient of The study adopted and modified risk rating concordance) is significant by the order of factors developed by the American Association of various sums of ranks. If one accepts the criteria Cost Engineers (AACE, 2008), as shown in Table used by the judges, then the best true ranking is 3, to develop a system for determining provided by the mean of the ranks. This implies contingency figure as a percentage to be added to that most factors influencing contingency sum are project cost. The method is a visual basic the highest overall ranking. Based on the above programme designed to cover identified factors premise, the overall rankings were calculated for influencing the determination of contingency the Quantity Surveyors, Architects and Civil sum. The factors have been grouped into Engineers. The Kendall’s concordance co- Economic, Technical and Environmental/Cultural efficient, which measures the degree of Factors. From the study Technical and agreement among professionals of ranking, is Environmental/Cultural Factors contribute 20% expressed as respectively to the determination of contingency k sum, whiles Economic factors contributes 60%. 2 2 W = [ (Ri – Ř) ] ∕ [n (n -1)/12] Each of the main factors has related minor factors. Each of these minor factors has risk rated where, values, which vary depending on conditions and k = the number of set of ranking (e.g. the number the impact of risk as identified by the project of judgments) team, as shown in Table 3 and Fig. 1. Fig. 2 n = the number of aspects of a problem or factors shows the pictorial nature of the Proposed being ranked. Method. Ř= average of the ranks assigned to the nth aspect Table 5 shows the list of projects that were of the problem used for the case studies. The projects were under n(n2-1)/12 = the maximum possible squared the sponsorship of the government of Ghana and deviation, i.e., the numerator, which the development partners, including the World will occur if there were perfect Bank, African Development
Recommended publications
  • The Study on the Comprehensive Urban Development Plan for Greater Kumasi in the Republic of Ghana Final Report
    13-203 13-203 The Study on the Comprehensive Urban Development Plan for Greater Kumasi in the Republic of Ghana Final Report Table of Contents Volume 3 Page PART VIII Capacity Development Programme for Spatial Development Planning and Implementation Chapter 25 Capacity Development Programme for Spatial Planning and Implementation 25.1 Introduction ................................................................................................................ 25-1 25.2 Institutional Analysis for Spatial Planning and Implementation ................................ 25-1 25.2.1 Town and Country Planning Department (becoming the Land Use and Spatial Planning Authority (LUSPA) under the forthcoming new law). ................................ 25-1 25.2.2 Regional Office of TCPD (becoming the Physical Planning Department of the RCC) .......................................................................................................................... 25-3 25.2.3 Physical Planning (Town Planning) Departments at Metropolitan, Municipal and District Assembly (MMDA) Level ............................................................................. 25-4 25.3 Basic Framework for Capacity Development Programme for Spatial Planning and Implementation........................................................................................................... 25-7 25.3.1 Primary Objective ...................................................................................................... 25-7 25.3.2 Identifying Capacity Development Needs .................................................................
    [Show full text]
  • Bosomtwe District
    BOSOMTWE DISTRICT Copyright (c) 2014 Ghana Statistical Service ii PREFACE AND ACKNOWLEDGEMENT No meaningful developmental activity can be undertaken without taking into account the characteristics of the population for whom the activity is targeted. The size of the population and its spatial distribution, growth and change over time, in addition to its socio-economic characteristics are all important in development planning. A population census is the most important source of data on the size, composition, growth and distribution of a country’s population at the national and sub-national levels. Data from the 2010 Population and Housing Census (PHC) will serve as reference for equitable distribution of national resources and government services, including the allocation of government funds among various regions, districts and other sub-national populations to education, health and other social services. The Ghana Statistical Service (GSS) is delighted to provide data users, especially the Metropolitan, Municipal and District Assemblies, with district-level analytical reports based on the 2010 PHC data to facilitate their planning and decision-making. The District Analytical Report for the Bosomtwe District is one of the 216 district census reports aimed at making data available to planners and decision makers at the district level. In addition to presenting the district profile, the report discusses the social and economic dimensions of demographic variables and their implications for policy formulation, planning and interventions. The conclusions and recommendations drawn from the district report are expected to serve as a basis for improving the quality of life of Ghanaians through evidence- based decision-making, monitoring and evaluation of developmental goals and intervention programmes.
    [Show full text]
  • Quantifying the Spatio-Temporal Patterns of Settlement Growth in a Metropolitan Region of Ghana
    GeoJournal DOI 10.1007/s10708-016-9719-x Quantifying the spatio-temporal patterns of settlement growth in a metropolitan region of Ghana Ransford A. Acheampong . Felix S. K. Agyemang . Mohammed Abdul-Fatawu Ó The Author(s) 2016. This article is published with open access at Springerlink.com Abstract Retrospective understanding of the mag- increase occurred in the last 13 years alone, with UEII nitude and pace of urban expansion is necessary for value of 0.605 indicating a moderate intensity of urban effective growth management in metropolitan regions. expansion. Moreover, the metropolitan-core of the The objective of this paper is to quantify the spatial– sub-region, being the focal point of urban develop- temporal patterns of urban expansion in the Greater ment and the historical origins of expansion, Kumasi Sub-Region (GKSR)—a functional region accounted for more than half of the total built-up land comprising eight administrative districts in Ghana, increase over the 28-year period. Over the last decade West Africa. The analysis is based on Landsat remote and half however, urban expansion has spilled into the sensing images from 1986, 2001 and 2014 which were neighbouring peripheral districts, with the highest classified using supervised maximum likelihood algo- intensity and fastest rate of expansion occurring in rithm in ERDAS IMAGINE. We computed three districts located north and north east of the sub- complementary growth indexes namely; Average regional core. We recommend a comprehensive Annual Urban Expansion Rate, Urban Expansion regional growth management strategy grounded in Intensity Index (UEII) and Urban Expansion Differ- effective strategic partnerships among the respective entiation Index to estimate the amount and intensity of administrative districts to curb unsustainable urban expansion over the 28-year period.
    [Show full text]
  • Atwima Kwanwoma District Assembly
    i ATWIMA KWANWOMA DISTRICT ASSEMBLY IMPLEMENTATION OF THE GHANA SHARED GROWTH AND DEVELOPMENT AGENDA II (GSGDA II), 2014-2017 2017 ANNUAL PROGRESS REPORT PREPARED BY: DISTRICT PLANNING CO-ORDINATING UNIT (DPCU) JANUARY, 2018 ii TABLE OF CONTENT CHAPTER PAGE Title Page………………………………………………………………………………………………...i Table of Content………………………………………………………………………………………...v List of Acronyms……………………………………………………………………………………….xiv CHAPTER ONE ANNUAL PERFORMANCE REVIEW 1.1 Introduction…………………………………………………………………………………………...1 1.2 Achievements and Challenges in the Implementation of Programmes and Projects in the 2017 District Composite Annual Action Plan (Status of Implementation of DMTDP {2014-2017}….2 1.3 Reasons for Non-Implementation of some planned Programmes and Projects…………..….......4 1.4 Purpose of the 2017 Annual Progress Report………………………………………………………5 1.5 Processes and Difficulties Encountered in the Preparation of the 2017 Annual Progress Report…………………………………………………………………………………………………6 CHAPTER TWO MONITORING AND EVALUATION ACTIVITIES REPORT 2.1 Introduction………………………………………………………………………………………......7 2.2 Departmental Programme and Project Status under each Thematic Area……………………...7 2.2.1 Ensuring and Sustaining Macroeconomic Stability……………………………………………12 2.2.2 Enhancing Competitiveness of Ghana’s Private Sector………………………………………..13 2.2.3 Accelerated Agricultural Modernization and Sustainable Natural Resource Management…...15 2.2.4 Infrastructure and Human Settlement………………………………………………………….21 2.2.5 Human Development, Employment and Productivity…………………………………………27
    [Show full text]
  • Atwima Kwanwoma District
    ATWIMA KWANWOMA DISTRICT Copyright ©2014 Ghana Statistical Service ii PREFACE AND ACKNOWLEDGEMENT No meaningful developmental activity can be undertaken without taking into account the characteristics of the population for whom the activity is targeted. The size of the population and its spatial distribution, growth and change over time, in addition to its socio-economic characteristics are all important in development planning. A Population census is the most important source of data on the size, composition, growth and distribution of a country’s population at the national and sub-national levels. Data from the 2010 Population and Housing Census (PHC) will serve as reference for equitable distribution of national resources and government services, including the allocation of government funds among various regions, districts and other sub-national populations to education, health and other social services. The Ghana Statistical Service (GSS) is delighted to provide data users, especially the Metropolitan, Municipal and District Assemblies, with district-level analytical reports based on the 2010 PHC data to facilitate their planning and decision-making. The District Analytical Report for the Atwima Kwanwoma District is one of the 216 district census reports aimed at making data available to planners and decision makers at the district level. In addition to presenting the district profile, the report discusses the social and economic dimensions of demographic variables and their implications for policy formulation, planning and interventions. The conclusions and recommendations drawn from the district report are expected to serve as a basis for improving the quality of life of Ghanaians through evidence-based decision-making, monitoring and evaluation of developmental goals and intervention programmes.
    [Show full text]
  • Chapter 3 Present Situation of Ghana, Ashanti Region and Greater Kumasi Sub-Region 3.1 Past Development Trend and Current Development Policies of Ghana
    13-203 13-203 The Study on the Comprehensive Urban Development Plan for Greater Kumasi in the Republic of Ghana Final Report Table of Contents Volume 1 Page Study Area: Greater Kumasi Sub-Region ................................................................................. 1 Photos of Greater Kumasi Sub-Region ..................................................................................... 2 Brief on the Study Project ......................................................................................................... 3 Executive Summary .................................................................................................................. 4 Conclusion ............................................................................................................................... 14 Part I Introduction Chapter 1 Introduction 1.1 Background .................................................................................................................. 1-1 1.2 Goals of the Study Project ............................................................................................ 1-2 1.3 Objectives of the Study Project .................................................................................... 1-2 1.4 Study Area .................................................................................................................... 1-3 1.5 Executive Agency, Implementing Agency and Other Counterpart Agencies ............... 1-3 1.6 Phases of the Project ...................................................................................................
    [Show full text]
  • Factors Predicting Home Delivery Among Women in Bosomtwe-Atwima-Kwanwoma District of Ghana: a Case Control Study
    Original Article Factors predicting home delivery among women in Bosomtwe-Atwima-Kwanwoma district of Ghana: A case control study Background: Maternal mortality is unacceptably high in Ghana. This situation is attributed partly to non-availability of healthcare services and poor utilization of these services when they are available. More deliveries are still performed at home, and in many cases, without the supervision of trained attendants, despite the Ghana Abstract Government’s fee exemption policy on maternal deliveries. The purpose of this study was to identify factors that predict home delivery among mothers. Materials and Methods: An unmatched case control study was conducted among mothers in the Bosomtwe-Atwima-Kwanwoma district of Ghana. A total of 114 mothers consisting of 54 cases and 60 controls participated in the study. A multi-stage sampling technique was used to select participants of the study. Data were collected using pre-tested questionnaires and analyzed using EPIINFO (3.3) and STATA (8.2) statistical software. Results: Mothers aged 31 years and above (AOR 3.00, 95% CI: 1.16-7.74) and those with primary or no formal education (AOR 3.88, 95% CI: 1.60-9.46) were more likely to deliver at home. Also, the risk of home delivery for mothers with more antenatal care (ANC) clinic visits was less by 0.3 (30%) (AOR 0.70, 95% CI: 0.53-0.88). Conclusion: The factors infl uencing home delivery among mothers were maternal ages of 31 years and above, primary or no formal education, and less than four ANC visits. Interventions aimed at improving female education, increasing the number of ANC visits, and providing counselling, follow-up, and support to older pregnant mothers are recommended to increase the number of women who deliver in healthcare facilities.
    [Show full text]
  • Manufacturing Capabilities in Ghana's Districts
    Manufacturing capabilities in Ghana’s districts A guidebook for “One District One Factory” James Dzansi David Lagakos Isaac Otoo Henry Telli Cynthia Zindam May 2018 When citing this publication please use the title and the following reference number: F-33420-GHA-1 About the Authors James Dzansi is a Country Economist at the International Growth Centre (IGC), Ghana. He works with researchers and policymakers to promote evidence-based policy. Before joining the IGC, James worked for the UK’s Department of Energy and Climate Change, where he led several analyses to inform UK energy policy. Previously, he served as a lecturer at the Jonkoping International Business School. His research interests are in development economics, corporate governance, energy economics, and energy policy. James holds a PhD, MSc, and BA in economics and LLM in petroleum taxation and finance. David Lagakos is an associate professor of economics at the University of California San Diego (UCSD). He received his PhD in economics from UCLA. He is also the lead academic for IGC-Ghana. He has previously held positions at the Federal Reserve Bank of Minneapolis as well as Arizona State University, and is currently a research associate with the Economic Fluctuations and Growth Group at the National Bureau of Economic Research. His research focuses on macroeconomic and growth theory. Much of his recent work examines productivity, particularly as it relates to agriculture and developing economies, as well as human capital. Isaac Otoo is a research assistant who works with the team in Ghana. He has an MPhil (Economics) from the University of Ghana and his thesis/dissertation tittle was “Fiscal Decentralization and Efficiency of the Local Government in Ghana.” He has an interest in issues concerning local government and efficiency.
    [Show full text]
  • Elixir Journal
    44135 Joseph Nkyi-Asamoah / Elixir Edu. Tech. 101 (2016) 44135-44141 Available online at www.elixirpublishers.com (Elixir International Journal) Educational Technology Elixir Edu. Tech. 101 (2016) 44135-44141 Impact of Teacher Trainee Sponsorship Scheme on Improving Teacher Supply in Bosomtwe-Atwima-Kwanwoma District of Ashanti Region Joseph Nkyi-Asamoah Wesley College of Education, Kumasi. ARTICLE INFO ABSTRACT Article history: This study investigated the impact of Teacher Trainee Sponsorship Scheme on improving Received: 4 October 2016; teacher supply in the Bosomtwe -Atwima-Kwanwoma District of the Ashanti Region of Received in revised form: Ghana. Questionnaire and interview guide were used to collect data from the District 20 December 2016; Education Office and the District Assembly. The sample included 228 teachers selected Accepted: 31 December 2016; from 45 primary and Junior High Schools.The study revealed that majority of sponsored teachers are native of Bosomtwe-Atwima-Kwanwoma District or share common border Keywords with the district. Most sponsored teachers in the deprived areas have some rural Teacher supply, background. The scheme is faced with the problem of non-payment of regular and Retention, realistic allowances to the teacher trainees. The study revealed that sponsored teachers in Trainee Sponsorship. the Bosomtwe-Atwima-Kwanwoma District have high expectations for conditions and facilities in the schools and communities. When the conditions and facilities are favourable, the teachers feel satisfied. © 2016 Elixir
    [Show full text]
  • Ejura Sekyedumase District Assembly Annual Progress
    EJURA SEKYEDUMASE DISTRICT ASSEMBLY IMPLEMENTATION OF DISTRICT MEDIUM-TERM DEVELOPMENT PLAN (2014-2017) ANNUAL PROGRESS REPORT FOR 2014 PREPARED BY: DISTRICT PLANNING COORDINATING UNIT JULY, 2015 CHAPTER ONE ANNUAL PROGRESS REPORT FOR 2014 1.1 Introduction The focus of the Government as enshrined in the Medium Term Development Policy Framework is to “address the economic imbalance, re-stabilizing the economy and placing it on a path of sustained accelerated growth and poverty reduction towards achieving the Millennium Development Goals in 2015 and middle income status”. In line with its introduction and subsequent adoption, MMDA’s were required to prepare four (4) year Medium Term Development Plan (2014 – 2017) by adopting strategies within the Medium Term Development Policy Framework thematic areas that are appropriate and applicable. The thematic areas of the MTDPF 2014 – 2017 are as follows; 1. Ensuring and Sustaining Macroeconomic Stability 2. Enhancing Competiveness in Ghana’s Private Sector 3. Accelerated Agricultural Modernization and Sustainable Natural Resource Management 4. Infrastructure and Human Settlements Development 5. Human Development, Productivity and Employment 6. Oil and Gas 7. Transparent and Accountable Governance The Medium Term Development Plan began in the first month of 2014 and as such, it becomes necessary to prepare progress report to show programmes and projects implemented within the 2014.This Annual Progress Report is based on the Monitoring and Evaluation exercise conducted to track progress in the implementation of the 2014 Annual Action Plan. The report presents the achievements, problems, constraints and challenges identified during the Monitoring and Evaluation (M&E) of programmes and projects in the Municipality.
    [Show full text]
  • Government of Ghana Ministry of Local Government and Rural Development Afigya-Kwabre District Assembly Kodie – Ashanti Draft F
    GOVERNMENT OF GHANA MINISTRY OF LOCAL GOVERNMENT AND RURAL DEVELOPMENT AFIGYA-KWABRE DISTRICT ASSEMBLY KODIE – ASHANTI PEACE, UNITY & DEV’T DRAFT FOR DISTRICT MEDIUM TERM DEVELOPMENT PLAN (2014 - 2017) UNDER THE GHANA SHARED GROWTH DEVELOPMENT AGENDA PREPARED BY: AFIGYA-KWABRE DISTRICT ASSEMBLY SEPT. 2014 1 TABLE OF CONTENTS Title Page i Table of Content ii List of Tables ix List of Figures xiii List of Acronyms xv Executive Summary xix CHAPTER ONE PERFORMANCE REVIEW AND DISTRICT PROFILE 1.1 INTRODUCTION 1.1.1 The 2009-2013 Medium Term Development Plan 1 1.1.2 Goal of the 2009-2013 Development Plan 1 1.1.3 Objectives of the 2009-2013 Development Plan 2 1.1.4 Status of Implementation of the 2009-2013 Medium Term Plan 3 1.1.5 Statement of Income and Expenditure of the District from 11 2009-2013 1.1.6 Key Problems/Challenges Encountered During the 14 Implementation of the 2010-2013 Plan 1.1.7 Lessons Learnt 15 1.2 DISTRICT PROFILE 16 1.2.1 Location and Size 16 1.2.2 Climate 20 1.2.3 Vegetation 20 2 1.2.4 Relief and Drainage 21 1.2.5 Soils and Geological Formation 23 1.2.6 Conditions of the Natural Environment 26 1.2.7 Conditions of the Built Environment 27 1.2.8 Climate Change Issues 28 1.2.9 Development Implications 28 1.3 DEMOGRAPHIC CHARACTERISTICS 27 1.3.1 Population Size 27 1.3.2 Spatial Distribution of Population 29 1.3.3 Age-Sex Structure 30 1.3.4 Population Density 31 1.3.5 Rural Urban Split 32 1.3.6 Household Characteristics 33 1.3.7 Dependency Ratio 33 1.3.8 Religious Affiliation 33 1.3.9 Migration Trends 33 1.3.10 Culture 34 1.3.11 Labour Force 34 1.4 SPATIAL ANALYSIS 38 1.4.1 Scalogram Analysis 38 1.4.2 Functional Hierarchy of Settlements 41 1.5 Physical Accessibility to Services 41 1.5.1 Accessibility to Health 44 1.5.2 Accessibility to Second Cycle Institutions 46 3 1.5.3 Accessibility to Agriculture Extension Services 48 1.5.4 Accessibility to Banking Services 50 1.5.5.
    [Show full text]
  • Atwima Kwanwoma District Assembly
    TABLE OF CONTENTS PART A: STRATEGIC OVERVIEW OF THE ATWIMA KWANWOMA DISTRICT ASSEMBLY . 3 1.0 BRIEF INTRODUCTION OF THE ESTABLISHMENT OF THE DISTRICT ....................... 3 2.0 POLICY OBJECTIVES ................................................................................................................ 4 3.0 VISION ........................................................................................................................................... 4 REPUBLIC OF GHANA 4.0 MISSION ....................................................................................................................................... 4 5.0 GOALS .......................................................................................................................................... 4 6.0 CORE FUNCTIONS .................................................................................................................... 5 COMPOSITE BUDGET 7.0 DISTRICT ECONOMY ................................................................................................................ 6 FOR 2021-2024 8.0 KEY ACHIEVEMENTS IN 2020 .............................................................................................. 13 9. 0 REVENUE AND EXPENDITURE PERFORMANCE ............................................................ 17 PROGRAMME BASED BUDGET ESTIMATES 10.0 POLICY OUTCOME INDICATORS AND TARGETS ........................................................... 20 FOR 2021 10.0 REVENUE MOBILIZATION STRATEGIES FOR KEY REVENUE SOURCES ............... 21 PART B: BUDGET
    [Show full text]