Vidhan Sabha Question Name of Department : Public Works Starred Question No. : 3422

Date of Reply : 03-03-2021 Subject : MLA Priority Asked by : Smt. Asha Kumari (Dalhousie) Concerned Minister : Chief Minister

Question Reply (a) during the last three years upto

31.01.2021, how many roads and

bridges under Public Works

Divisions have been listed under

MLA priority; what is the latest (a) & (b) The information has been laid on the position of these roads and Table of the House. bridges; and (b) how many roads have been started, completed and how many DPRs are under preparation during this period ?

Information relating to Starred Assembly Question No. 3422 asked by Smt. Asha Kumari (Dalhousie):-

(a) During the last three year upto 31/01/2021, 673 roads and bridges under PWD Divisions have been listed under MLA priority. The status of these schemes is as under:-

STATUS OF SCHEMES

Sr.No. Schemes listed DPRs prepared (In Nos) Draft DPR DPR yet to DPR not MLA priority Sanctioned Under prepared be prepared required w.e.f. 2017-18 (In Nos) Scrutiny and under for want of due to to 31/01/2021. with checking Pvt./ forest sanction Planning/ (In Nos) land / of work in Nabard (In alignment CRIF/ Nos) issues (In priority Nos) repeated / urban area 1 673 98 109 196 261 9

STATUS OF SANCTIONED PROJECTS

Sr. Status of sanctioned projects. No. Total work Work Work Tender work under process (In Nos) sanctioned Completed started (In RIDF RIDF State Total (In Nos) (In Nos) Nos) (XXV) (XXVI) Head 1 98 1 39 4 52 2 58

(b) Status of under preparation DPRs for Schemes listed under MLA Priority during last three years Total No. Schemes for which DPRs yet to be prepared = 466 Nos.

(i) DPRs under preparation = 196 Nos (ii) DPRs which could not be prepared for Various reasons.  Involvement of Private /Forest land = 261 Nos  Priority repeated = 4 Nos  Urban area = 2 Nos  Sponsored under CRIF = 3 Nos

The details (workwise) is appended as annexure-A Annexure-A

CONSTITUENCY / WORK WISE DETAIL OF HON'BLE M.L.As PRIORITY SCHEMES W.E.F. YEAR 2003-04 TO 2020-21 UPTO 24-02-2021 Sr.N Constitue Year of Name of Scheme Pr Present Status Division o ncy Priority No. 1 2 3 5 6 7 8 1 Chopal 2017-18 C/O road from Daiya to Mashot I The existing road executed by the Chopal via Serti Malat. forest department & forest land involved. FCA case for motorable road yet to be prepared at Sub-Divn. level. 2 Chopal 2017-18 C/O road from Nevti to Rana II Forest case prepared & submitted to Chopal Kyar via Civil Hospital Nerva DFO Chopal & joint inspection bye pass. conducted. 3 Chopal 2018-19 C/o Road from Main road to II The alignment has been finalized . Chopal Thekra, Bangana, Gunsa, Total length of this road is 6.000 Km. Nakoud Pul G.P. Nerwa. which involves Forest / Private land. Partial Gift deeds have been received and Forest case will be prepared after receipt of all Gift deeds. 4 Chopal 2018-19 C/o road from Batveri Kainchi IV The alignment is finalized and forest Theog to Devathi, Shirgali, Kadharan , land is 9.500 Kms. and 4.500 Kms. Alidhar, Ghog Adshala Jatheri. Private land.. The Joint inspection is (Scheme given by the MLA in fixed for 27.01.2021 for FCA case. place of MI schemes). Gift deeds of private land are also awaited.

5 Chopal 2019-20 Up-gradation Metaling,Tyring I Road constructed by other agency Theog of road from Deha to Khatori upto 4.000 Kms and also passed for Pundar Butali Balah Ghalana Vehicular Traffic. Beyond 4.00 Km. Kishore. forest landis involved and .Joint inspection has been fixed on 27.01.2021.

6 Chopal 2019-20 Up-gradation Metaling,Tyring III DPR under preparation Chopal of road from Matal to , Shingroli Mamvi. 7 Chopal 2019-20 Up-gradation Metaling, Tarring VI This requires clearance under FCA Chopal of road from Nawan to which under process. Malkohat Kaloon Dasheya Dhagun Tuil Jhina Gheylot. 8 Chopal 2020-21 C/O road from Thithroli, II Alignment to be finalized gift deeds yet Chopal Ramdara, Telor, Karag, Banan to be received and forest case will be to Kashak and Kashak Gaad. prepared after receipt of gift deeds. 9 Chopal 2020-21 C/O road from G.P.Dewat III Alingment is finalized, total length of Chopal Shilikayan, Mashdoh. this road is 4.600 km . Gift deeds received and forest case under preparation . 10 Chopal 2020-21 C/O road from Navi Khudah, V The alignment has been finalized . Chopal Auli G.P. Tharoach. Total length of this road is 6.000 Km. which involved Forest / Private land. Partial Gift deeds have been received and Forest case will be prepared after receipt of all Gift deeds. 11 Chopal 2020-21 C/O road Deiya Kidakuffta VI The existing road was constructed by Chopal Rehosti to Churayn. the forest department The DFO Chopal has been asked to hand over the road to this department by EE letter No. 1269 dt. 5.11.2020 . 12 Theog 2017-18 C/O road from Jai-Kashoo- I The alignment has been finalized. The Theog Dhanoo-Kalahar Mandir total length is 8.00 Km.out of which Length 8Kms. forest land is 3.000 Kms. and private land is 5.000 Kms..AE Matiana vide his office letter NO.450-53 dt.17.07.2017 has requested GP Pradhan for Gift deeds. It has come to the knowledge that land owner are not ready to donate land. 13 Theog 2017-18 C/o road from village Reog- I Alignment finalized. Total length of Kumarsain Dwala -Galanaghati in GP road is 8.050 km.out of which Jadroon Tehsil Kumarsain 5.00km.Pvt.land & 3.050km. forest (Substituted from MI scheme land. FCA case has been re-uploaded on dated 23/08/2017). online on dated 4/7/19 After attending the observations. Forest case resubmitted on dt. 08/09/2020 but received back with observations. Submitted to DC for revise non availaility of Non forest land certificate by EE Kumarsain on dt. 04/12/2020. 14 Theog 2018-19 C/O road from Reog, Dawala, II Total length of this road is 8.050 Km Kumarsain Glanghatti in GP Jadhoon out of which 5.00 Km is private land Tehsil Kumarsain. and 3.050 Km is forest land. Gift deed of private land have been received and forest case has been sent to D.C. Shimla for approval vide Executive Engineer, Kumarsain letter No.9154-55 dated 4.12.2020 for non availability of forest land certificate which is still awaited. 15 Kasumpti 2017-18 C/O road from Chtog to Satoh I Pvt./foest land involved. Shimla (via Shilli Mohalla). No.I 16 Kasumpti 2018-19 C/O road from Thalot to Jhagog I The total length is 5.00 Km. which is Shimla (GP Darbhog). 4.00 Km. is forest land and 1.00 Km. is No.I private land. The alingnment of road has been fixed some gift deeds have been recived. Letter has been written to the SDM(R ) to conduct the Joint inspection vide this office letter No. 7570-72 dated 1.08.2019, but the dated has not been fixed till date. 17 Kasumpti 2018-19 C/O roads from Kamyana to III The Survey work has been completed Shimla Bisk/ Tud/ Lachot (GP Bhont). and length of road is 1.700 Km. ( total No.I forest land ).Requested to SDM, Shimla for joint inspection vide letter No. 12301-04 dated 28.09.2020. The Pradhan GP Bhont requested to provide relevant record vide letter No. 427-28 dated 03.08.2020. After collecting all relevant record from concerned department. The FCA case will be up loaded on line. 18 Kasumpti 2019-20 C/O road from Koti to village I The total length is 7.00 Km. which 6.00 Shimla Bhararia via Paradi. Km. is forest land and 1.000 Km. is No.I private land. The alingnment has been fixed all the gift deeds have been received. The forest case being submitted.

19 Kasumpti 2019-20 C/O road from Paobo Talab to II The total length is 5.330 Km.which is Shimla Kaltu via Obna. 4.00 Km. forest land and 1.330 Km. is No.I private land. The Gram Panchyat pradhan Bhont, Dumi and Cheri has been requested to provide the gift deed from private land owner which is still awaited.

20 Kasumpti 2020-21 C/O road from Kelti to Chari I The total length is 3.500 Km. which Shimla (G.P.Chari). 1.500 Km. is forest land and 2.000 Km. No.I is private land.The Pradhan GP Cheri requested for providing gift deed on dated 12.01.2021. which is still awaited. 21 Kasumpti 2020-21 C/O road from Godpa to II The total length is 1.000 Km. which Shimla Village Shildi (G.P.Pujarli). 0.300 Km. is forest land and 0.700 Km. No.I is private land.The Pradhan GP requested for providing gift deed on dated 12.01.2021. which is still awaited. 22 Shimla 2017-18 C/O link roads from Holiday I Survey work yet to be done & joint Shimla Home to bye pass road Nabha- inspection has been conducted. The No.I Phagli to Lal Pani and Lal Pani starting portion of the road about to Bye Pass road. 700mtrs.CPWD land is involved but the NOC this deptt.still awaited. In this alignment MC land also involved & has raise objections as Housing scheme for Rajeev Awas Yojna is involved in this portion, NOC from MC still awaited. 23 Shimla 2019-20 C/O link road Ghanahatti- II The 3.500 Km. road has been Shimla Rural Kalihatti-Shakoh-Pawri-Ka- constructed by the B.D.O. Mashobra Rural Pipal. which involve forest / pvt. Land. Forest case is being prepared and the Pradhan Gram Panchayat Mahli has been requested to provide the gift deeds of pvt. land onwers vide EE office letter No.17224-29 dated 30.12.2019 but the same are still awaited. The SDM Rural Shimla has also been requested vide EE office letter no. 1554-55 Dated 06.01.2020 for the demarcation / status of land. further reminder has been issued vide EE No. 15995-98 dt. 11.01.2021. 24 Shimla 2020-21 C/O link road Drol to Village I Total length of this road is 6.540 Shimla Rural Jaishi. Km.,out of which 3.540 Km is Govt. Rural Land / Forest land and 3.00 Km. Pvt land. The forest case has been prepared and request for Non-availibility of Non-forest land cerificate has been made to D.C. Shimla vide AE Jalog Sub Div vide letter No.81-82 dt. 08.06.2020 and reminder has also been made vide letter No. 467-68 dt. 22.09.2020 and even file No.957-58 dt. 06.01.2021. 25 Jubbal & 2018-19 C/o Tharola-Pajai-Chanj road- I Total length of the proposed road is Kotkhai Kotkhai G.P. Tharola, Kotkhai. 8.500 Km (Forest Land 7.800 Km Pvt land 0.700 Km ) . Work being carried out under SCCP for portion Tharola to Pajai i.e. km 0/0 to 6/0 for which FCA approval has been accorded. For portion i.e. link to Chanj case for FCA approval is under preparation. DPR can not be prepared till the approval of FCA and Gift deed are not received from owner of land. 26 Jubbal & 2018-19 C/O -M/T Khorwi-Dalsar to III Total length of the proposed road is Kotkhai Kotkhai Pragati Nagar (Baghi) (Scheme 5.000 Km (Forest Land 3.00 km Pvt given by the MLA in place of Land is 2.00 Km) . Pvt. Land owners MI Scheme). have not agreed to donate their land (app. 200 mtr.) possibilities of alternate alignment being explored. FCA case can be processed after gift deeds are received. DPR can not be prepared till the approval of FCA and Gift deed are not received from owner of land. 27 Jubbal & 2019-20 C/O link road from Kathandi III Total length of the proposal is 2.250 Kotkhai Kotkhai Nallah to Jhandoli via Shoshan km Forest land is 0.810 Km Private (Substituted from MI Scheme Land is 1.410 Km . Gift deed awaited. on dated 03/01/2020). FCA case can be processed after gift deeds are received. DPR can not prepared till the approval of FCA and Gift deed are not received from owner of land. 28 Rampur 2018-19 C/O Nagadhar to Delath road II Alignment finalized. Total length of Rampur G.P. Delath. poposed road is 4.500km.out of which 0.500km. Pvt.land & 4.00km.forest land. Gift deeds are awaited from Pvt.land owners. As & when the gift deeds are received the FCA case shall be processed. 29 Rampur 2019-20 C/O road to Khanotu from I Alignment finalized. Total length of Rampur Taklech RD. in GP Taklech. poposed road is 3.00km.out of which 1.00km.Pvt.land & 2.00km.forest land. Gift deeds pvt.land stands received & FRA of forest land also received. DPR under preparation in Sub-Divnl.office. 30 Rampur 2020-21 C/O road from Bahli to I Survey conducted. Total length of road Rampur Shangri-Devnagar-G.P.Bahli is 7.500 kms . PVt. Land is 0.800 km & (Rampur). forest land is 6.700 kms involved. 31 Rampur 2020-21 C/O road from Souddhar to II Alignment finalized. Total length of Rampur Tangri-Dogri- proposed road is 3.00 kms. Forest & G.P.Khamadi(Nankhari). Pvt. Land involved. Gift deeds are awaited from land owners, 32 Rohru 2018-19 L/R Joban thach to Arthi-Bajain I Total length of road is 4.250 km. forest Rohru (Bhaloon) Division Rohru. land 2.00 km Private land is 2.250 km. Gift deed awaited. F.C.A. is under preparation. Alignment finalised . DPR can not prepared till the approval of FCA and Gift deed are not received from owner of land. 33 Rohru 2018-19 L/R Main road to Main II Alignment finalised Total length of this Rohru road Nandla and bridge. road is 3.00 Kms out of which 1.00 Division Rohru. Kms Governemnt land and 2.00 is Private land Gift deed of private land Not received DPR not Prepared due to non approval of F.R..A. DPR can not prepared till the approval of FCA and Gift deed are not received from owner of land.

34 Rohru 2020-21 C/O link road Dodra to I Total Length of the road is private land Dodra Chamdhar. 5.00 km. Gift deeds received recently Kawar from land owner DPR is under preparation being a snow bound area and DPR submitted by June 2021. 35 Rohru 2020-21 Up-gradation of Poudhar II Total length of road is 12.300 km. Rohru Mandeori road up to Karasa. Private land is 12.300 km. Gift deed completed DPR under preparation. 36 Arki 2018-19 C/O Link road from Padyar to I Forest land involved. Arki Boi. 37 Arki 2020-21 C/O road to village Bohi. I Forest land involved Arki 38 Arki 2020-21 C/O from to village Shelly. II Forest land involved. Arki 39 Nalagarh 2017-18 C/O Pucca link road Sirsa- I Survey work completed & alignment Nalagarh Tarwal-Bhruwali-Khuibada, marked on ground. Gift deeds awaited Teh.Nalagarh (Substituted on from land owners. dt.29/08/2019). 40 Nalagarh 2019-20 C/O road from Gujjarhatti, II The survey work of this road is Nalagarh Amb-da-Haar Panehli. completed, and alignment of road marked on the ground. The concerned Gram Panchayat Pradhaan has been requested to motivate the private land owners for gift deed of the private land coming in the alignment of this road. The DPR can only be prepared after gift deed of land. This department has requested Pardhan GP Bagheri vide AE office letter No. 3026-29 dated 26.11.2019 & this office letter No, 14433-35 dated 28.12.2019, Pardhan GP Kundlu vide AE office letter No. 3018-21 dated 26.11.2019& this office letter No, 14439-41 dated 28.12.2019 41 Nalagarh 2020-21 C/O Pucca road Galot-Banali- II Survey done . Total road length = Sersa Riya-Kapoli-Syarli village 3.600Km , Private land = 2.6 2.800Km Teh.Nalagarh. , Forest Land =0.800 Km. Gift deeds from lacal land owners awaited. 42 Doon 2017-18 CD & MT from Kanol Kainchi II Forest land involved and forest case is Nalagarh more to Aleta, Beh Mandi & being prepared. Beh Kaneta (Substituted on dated 05/01/2019). 43 2017-18 C/O road from Dooh to Bhola II Survey done. Total length Arki in GP Mamleeg. 4.00km.Pvt.land 3.00km. Gift deeds not available.

44 Solan 2018-19 C/O Kiari Bainoo to Khinna I Total length Solan road km. 0/0 to 7/820. 7.820km.Pvt.3.320km.forest 4.500 km. Physical copies of forest case submitted to CF and are in process & DPR for 818.38 lacs checked by Zonal office & sent to EE Solan for fair out.

45 Solan 2018-19 C/O Uperala Badyawal to II Total length 4.450km.Survey work Solan Nichla Badyawala road GP Kot done. Gift deeds manuscript DPR for Kadaur. Rs.520.53 lacs under scrutiny in Zonal office. 46 Solan 2019-20 C/O road from Kaithlighat to II Alignment marked in the field gift Solan Katoh, Lachog, Ganrodi via deeds available for intial 2.00 Km and Garoo road in GP Kot. for remaining 4.5 Km awaited & letter has been writte to Panchyat Pradhan to collect a gift deeds of Pvt. Land 47 Kasauli 2017-18 C/O road Paidi to Banaghat II Total length 1.30km. Pvt.land Kasauli G.P. Devathi. 1.30km.survey conducted. Alignment not acceptable to local people. Realighment is being finalized. 48 Kasauli 2018-19 L/R Groni to Sari- M/T from I Total length 18.00km.land available Kasauli 0/6.500 and C/F,CD etc. from 6.500 forest land 11.500kms. DPR 6.500/18. under scrutiny in CE(SZ) Shimla. 49 Kasauli 2018-19 C/O L/R from Dhar to Jaliana II Total length 6.500km. Survey done Kasauli via Dhaiyan, Androl and Arni alignment finalized Pvt.land 5.00km. in G.P. Bhojnagar. and forest land 1.50km. Gift deeds of Pvt.land being collected. 50 Pachhad 2020-21 C/O Foot bridge in Giri river at I Transfer of private land for approach Rajgarh Thor Niwar village GP. Thor in favour of PWD Department is under Niwar, Community Block proces. Letter sent to Gram Panchyat Rajgarh. Pardhan by Exectuvie Engineer, Rajgarh Division., gift deed still awaited from land owners. 51 Pachhad 2020-21 C/O L/R from Phagoo to II Total length is 13.00 Km:- Private & Rajgarh Bathaudhar, Banalidhar via forest land involves in the alignment. Ulakh Katoga to Serva, GP. Transfer of Private lnad in favour of Dahan & Nerti Baghot, PWD Department letter sent to Gram Community Block Rajgarh. Panchyat Pardhan by E.E. Rajgarh & gift deeds is still awaited from the land owners & forest case will be prepared after getting the gift deeds from land owners. 52 Pachhad 2020-21 C/O L/R from Nohri to Kotla III Total length Km.0/0 to 5/100 & Rajgarh Bangi via Shaya Sanora i/c C/O Transfer of private land in favour of bridge on Bajhethu Khad, GP. PWD Department under process. Letter Shaya Sanora, Community sent to Gram Panchyat Pardhan by Block Rajgarh. E.E. Rajgarh . Gift deeds still awaited from land owners.

53 Pachhad 2020-21 Preparation of Dubloo IV The starting reach of 700 mtrs. the Rajgarh Mandiaghat road via Laharab local peoples are objecting for to Shamloh village & ITI (CDMP) donate the land in favour of HP.PWD., Scheme, GP Tikker, in this regard letter`s sent to Gram Community Block Rajgarh. Panchyat Pardhan by Executive Engineer, Rajgarh. Gift deeds still awaited from land owners. 54 2017-18 C/O MT/CD on NH-7 Jatanwal Forest case stand submitted to Forest Paonta to Ambwala Tappad to Deptt. but sanction awaited. Sukhchainpur to Kheari to NH- 7 (Paonta Division). 55 Nahan 2019-20 C/O CD/MT road from Village IV Survey work has been completed .DPR Nahan Haripur to Nalka, Sambhalka, under prepration & gift deed are Agdiwala & C/O bridge over required from the land owners. Haripur Khad(Substituted on dated 23/05/2020). 56 Nahan 2019-20 C/O CD, MT road Mattar to V DPR under prepration at Sub-Division Nahan Manatra Mata Temple. level for Rs. 1527.24 lakhs. Forest case under prepration & gift deed required from land owners. 57 Renuka 2017-18 C/O road Gheliyon to Palgech- I The alignment of road has been done Sangrah Kuryan via but gift deeds is still awaited from the Dhar,Thanga,Kyarkoti,Bara land owners. Khanara,Chumanu. 58 Renuka 2017-18 C/O road Fandi Bodi wala to II FCA case is re-submitted to DFO Sangrah Janglot. Nahan after attending the all observation by EE Paonta on dt. 3/12/2019. 59 Renuka 2017-18 C/O road from Koti Dhiman to I Approximate length 6.500km. Gift Sangrah Kota-Pab (Substituted from MI deeds not available efforts are being scheme on dated 07/01/2019). made. FCA also involved. 60 Renuka 2017-18 C/O link road from Khala- II Gift deeds not available efforts are Sangrah Kyar, Koti Dhiman road-Tippra being made. to Kyarik via Halayion- Rajaina- Pirtabi- Maila (Substituted from MI scheme on dated 07/01/2019). 61 Renuka 2019-20 C/O road from Devamanal to I Approximate length is 16.555 Sangrah Shiya via Bakhan-Kothi-Begra- kms.50% gift deed have been done & Charag-Jiyar. efforts are being made to get the remaining gift deeds. 62 Renuka 2019-20 C/O road from Gattadhar to II Approximate length is 9.00 km. Private Sangrah Tandio via Chiyaro. & shamlat land is involved & Demarcation from revenue department is awaited. 63 Renuka 2020-21 C/O link rod from village Khali I Alignment is under process at Sub- Paonta Achhon to Kyari Dadua division level. Km.12/0 to 16/0. 64 Renuka 2020-21 C/O link road from village II Alignment is under process at Sub- Paonta Kyari Dadua to Nadi Km.16/0 division level. to 20/0. 65 Paonta 2020-21 C/O link road Nageta to Aagro I Alignment could not be finalised due to Shillai G.P.Nageta. private land dispute. 66 Shillai 2017-18 Link road Bhadlat to kanti I Survey of 4.00km.out of total length Shillai Mashwa via Dab, Pipli, Tilwadi 7.50 km.has been done but rest of land Baag, Chowki Mirgwal. is not available as land owners are not allowing to do the balance survey work. 67 Shillai 2017-18 link road Feduwala to Drabil II Survey of 1.50km.out of total length Shillai via Mangtadi, Timba, Shanail 7.00 km.has been done but rest of land Gatu, Bapil, Kuitheti. is not available as land owners are not allowing to do the balance survey work. 68 Shillai 2018-19 Dubor Lani Tityana road. I This road 6.00km.in length & its Shillai alignment has been finalized. But land owners are not ready to give gift deeds for their land in favour of HP.PWD. 69 Shillai 2019-20 Jamli to Kharkha road. I Alignment finalized. Gift deeds Shillai obtained up to 4.00km only Accordingly DPRs is being prepared upto 4.00kms. 70 Shillai 2019-20 Chilon Bag Tilwagi Choki II Forest land involved. FCA case Shillai Margwal road. uploaded online on dated 12/01/2021. 71 Shillai 2020-21 C/O link road from Baralani to I Private land involved. Shillai Nauna Bhatwar. 72 Shillai 2020-21 C/O link road from Loja to II FCA case is under preparation . Joint Shillai Manal. inspection has been done. 73 Kinnaur 2017-18 C/O link road from Kalpa I Alignment finalized through Kalpa Kanda. 1.50mtr.wide local path. The FRA of jeepable road received from DFO Kinnaur at R/Peo on dated 1/5/17. Funds amounting t Rs.30.00 lacs received under BADP and 1.200km.formation cutting of jeepable standard has been completed. 6.00km. motorable standard road id required to be construction as per the demand of local people up to Kalpa Kanda. Out of which 5.00km.road is passing through Pvt.land & 1.00km.road is passing through forest land . The gift deeds is stikll awaited from Pvt.land owners. As & when the gift deeds will be received the DPR under NABARD shall be prepared. 74 Kinnaur 2017-18 C/O link road from Dot to II In this respect it is submitted that there Karchham Nichar. is no such place called as Dot. In place of Dot this could be Det Sungra to Nichar and above said road is alraedy taken up in the MLA Priority as Link road to Village Grange. For this Alignment finalized. Total length of road is 3.500 Kms out of which 0.900 Km is private land and 2.600 Km forest land. Gift deeds are awaited from the land owners. Pradhan Gram Panchayat Nichar has also requested to expedite the matter for gift deed vide E.E. Karchham letter No. 7676-77 dated 09/01/2019 and A.E. Ponda letter No. 379-80 dated 02/08/2019.

75 Kinnaur 2018-19 C/O link road from Batitas I Alignment finalized.Total length of this Karchham Somgas to Urabrang Kamo. road is 1.735 Kms. Forest land involved in entire length. FRA submitted to DFO Kinnaur for approval on dated- 13-07-2020. DPR is under preparation in Sub-Division.

76 Kinnaur 2018-19 C/O Link road to Sungra II Total length this road is 4.550. Forest Karchham Kande. & private land involved. FRA has been approved vide DFO Kinnaur letter No- 19412 dated- 01-02-2019 & gift deed partly received for new alignment. Whereas old alignment whose gift deed of land has been received earlier is heavely steep gradient.The manuscript DPR amounting to Rs. 361.94 lacs approved and fair DPR under preparation in Division office Karchham & being submitted to higher authority for its approval shortely. 77 Kinnaur 2019-20 NH-05 to Village Runang I Alignment finalized on 08-08-2020. Karchham Total length of this road is 3.650 Kms. Forest land involved in entire length & Joint inspection of road has been conducted on 22-01-2021 but cnacelled. Army camp is situted under the proposed road alingnment. So, NOC is to be taken from army before the submission of F.R.A. A joint meeting was conducted with Pardhan Gram Panchayat Yulla and army officals and representative of runang village. The army officials asked to submit the working program showing the usage of blasting material and machinery. only after receiving the NOC from army department could go ahead for the preocess of DPR prepration and FCA clearance. 78 Kinnaur 2019-20 Link road to Village Grang. II Alignment finalized by the department. Karchham Total length of road is 3.500 Kms. out of which 0.900 Km Forest and 2.600 Kms private land involved. Approval of forest land under FRA, 2006 has been received form DFO Kinnaur vide DFO Kinnaur letter no-3099 dated- 11- 05-2017. However Gift deeds of the private land coming in the alignment of the road are still awaited from the land owners. Pradhan Gram Panchayat Nichar has also requested to expedite the matter for gift deed vide E.E. Karchham letter No. 7676-77 dated 09/01/2019 and A.E. Ponda letter No. 379-80 dated 02/08/2019.

79 Kinnaur 2020-21 C/O link road to Sangla Kanda. I Survey conducted upto 5.000 kms total Karchham length is 15.000 Kms. approximately. Beyond 5.000 Kms. private land involved and survey to be finalized. 80 Kinnaur 2020-21 C/O link road Bodh Mandir to II Alignment finalized. Total length is Karchham Ti Nalha Thowaring 1.313 kms out of which 1.193 kms (Moorang). private land and 0.120 kms forest land. Gift deeds awaited from land owners. 81 Anni 2017-18 C/O road from Garshai to I Alignment finalized. Total length is Nirmand Ropru via sheugi, Lower Dhar 4.860 kms out of which 0.150 kms (substituted on dt.28-08/2019). private land and 4.710 kms forest land. Gift deeds awaited from land owners. 82 Anni 2017-18 C/O road from Kansari Kainchi II Alignment finalized. Total length is Nirmand to Shailinala via Fanauti Juhal, 11.330 kms out of which 4.752 kms Balel (Substituted on dated private land and 6.578 kms forest land. 258/08/2019). Gift deeds awaited from land owners. 83 Anni 2017-18 C/O Motorable road from Jajar II Alignment finalized. Total length is Nirmand Kainchi to Ronala via Chowki 4.110 kms out of which 1.400 kms under HPPWD Divn. Nirman private land and 2.710 kms forest land. (Substituted on dated Gift deeds partly received. Joint 28/09/2019 from RWSS inspection conducted on dated Scheme). 20/03/2020.. 84 Anni 2018-19 C/O road from Shamshar to I Alignment finalized. Total length of Nirmand Panai. proposed road is 9.390 kms.out of which 6.965 kms.forest land & 2.425 kms is pvt.land. Gift deed received. Joint inspection has been conducted. FCA case re-submitted on dt. 08/09/2020. Some observations raised which are being attended. 85 Anni 2018-19 C/O road Sarahan to Bashleu II The alignment has been re-finalized as Nirmand Jot (Substituted on dated per direction of Hon'ble MLA. Total 28/02/2019). length of this road has now comes to 14.825 kms which totally falls under forest land. Joint inspection has been conducted on dated 03.12.2020. Enumeration of trees yet to be done by forest department. Forest case is under preparation. 86 Anni 2019-20 C/O road from Thachvi to II Alignment finalized. Total length of Nirmand Ladair via Kui. proposed road is 5.390 kms.out of which 3.790 kms. Gift deed received. FCA case under preparation. 87 Lahaul & 2018-19 C/O Kurched road Lahaul. II Alignment now finalized due to Udaipur Spiti involvement of Forest & Pvt.land.

88 Manali 2018-19 C/o Archhandi-Dhamasharni - II Alignment finalized. Total length Manali Barnot road. 7.250km. Forest 4.00km.,Pvt.land 3.250km. Gift deeds awaited from pvt.land owners.

89 Manali 2019-20 C/O road from Bulang to I Alignment finalized.FRA awaited. Manali Damchin via Bhatmeha to Bhujnu. 90 Manali 2019-20 C/O road from Kasheni- II FRA awaited from Deputy Manali Galoon-Marjan-Halan-II. Commissioner Kullu 91 Manali 2020-21 C/O Bye Pass road from Manali II Alignment finalized. FRA awaited Manali pul to Club House. from Municipal Committee Manali. 92 Kullu 2017-18 C/O road from Fati Peej Fati I Survey conducted, but alignment could Kullu Barhhar, Fati not be finalized due to involvement of Khaihar(Substituted on dated Private land of number of adjoining 23/02/2018 from MI Scheme). villages and non receipt of FRA & Ban Adhikar certificate from Panchayat & concerned villages. 93 Kullu 2017-18 C/O Circular road in Kullu NOC from concerned Panchyat & MC Kullu Town (Substituted on dated awaited. Gift deeds from Pvt.land 23/02/2018 for RWSS owners also awaited. Scheme). 94 Kullu 2018-19 C/o road from Gobha Villages I Survey conducted, but alignment could Kullu to Vijali Mahadev, Deugra, not be finalized due to involment of Braihan , Kraduful, Ganakhla, Pvt.land of number of adjoining Chhamahn, Danogi, Mandoli villages & non receipt of FRA & Ban Sharsh, Tippari, Sharni, Bekta, Adhikar Certificate from Panchyat & Flati, Fagta, Blaghi, Pauhal, concerned villages. Chohki, Ktagala, Chhachhal, Chogh, Gadagi, Broun upto Manikarn. 95 Kullu 2018-19 C/o road from village Mouhal Total length of road 6.220km. FRA Kullu to upto Tari-Ra-Gran certificate is awaited. (Substituted on dated 16/07/2019). 96 Kullu 2019-20 C/O road Darka-Gadiyada, I Survey work completed. Gift deeds Kullu Nagoojhoud to Garamang-II. from Pvt.land owners awaited. 97 Kullu 2019-20 C/O Shishamati Bye pass road. II Forest case prepared and stands Kullu submitted in the office of ARO Dehradum. Observations raised by ARO Dehradun also attended.Approval still awaited.DPR under preparation. 98 Kullu 2020-21 C/O link road Bagan to Darpoin I Survey work completed and complete Kullu via Bhedhar Bagan. gift deeds not received.Ban Adhikar certificate from Panchyat and concerned village not received as yet. 99 Kullu 2020-21 C/O road from Village Madgan III Survey work completed. Gift deeds Kullu to Shalani, Khopri up to awaited from land owners. Mathala (Substituted on dated 12/10/2020). 100 Banjar 2017-18 C/O road from Talada to II Alignment finalized and Total road Banjar Kulagad. length = 6.150 km.Gift deeds awaited from Private Land owners.Forest case will be submitted on receipt of gift deeds. 101 Banjar 2018-19 C/O road from Fagla to Saila III Alignment finalized and gift deeds Banjar via Mobha (Substituted from received and FCA is under preparation. MI Scheme on dated 24/01/2019). 102 Banjar 2019-20 C/O road from village Shanad I Alignment finalized & gift deeds Banjar to Shaplin & Dhar to Kulthi. awaited from Pvt.land owners. 103 Banjar 2019-20 C/O road from Jaipur-Jibhi II Alignment finalized & gift deeds Banjar Kandi-Dalicha, Sum-Bhumar. awaited from Pvt.land owners. 104 Karsog 2017-18 C/O Ruhni to Thangar road I DPR under praparation. Pvt.land Karsog Km.0/0 to 11/200 (Substituted 3.00km.& forest land is 8.200km. on dated 03/01/2020). 105 Karsog 2018-19 C/O road from Kao to I Alignment has been finalized & gift Karsog Charkufri via Lalag i/c bridge. deeds awaited from land owners. 106 Karsog 2019-20 C/O road from village Sarahan I DPR Sent to Chief Engineer Mandi Karsog to Haripur College i/c bridge. Zone vide S.E. 1st Circle dated 07/01/2021 for Rs. 1298.49 lacs and DPR return to EE Karsog for fair out vide CEMZ) on dated 22.1.2021 for Rs. 1356.38 lakh. Revenue papers for FCA has been prepared and NPC has also been obtained from D.C. Mandi. Now digital map under prepration. .Length of Priviate Land of this road is 7.500 Km and forest land is 3.000 Km. 107 Karsog 2020-21 C/O road from Sartyola to I Alignment finalized and FCA & DPR Karsog Manjoo. under prepration gift deed awaited from the land owners. All the initial formalities of FCA has been done and case has been apploded online on dated 22/12/2020..Length of Priviate Land of this road is 1.000 Km and forest land is 9.000Km. 108 Sunder 2017-18 C/O road Nihri to Borat via I The alignment has been finalized. Sunder Nagar Bahi and Nehra. There is approximate 8.0 Km forest Nagar land and 2.00 Km private land out of 10.00 Km length. The gift deed of private land received. The revenue papers have been collected and the forest case is under preparation. 109 Sunder 2017-18 C/O road Neri to Badoo in G.P. II The road alignment has been finalized. Sunder Nagar Dhanyara. There is approximate 7.000 Km forest Nagar land and 0.700 Km private land out of 7.700 Km length. The private owners have requested for gift deed. The revenue papers have been collected, NAC received and Joint inspection conducted on 17.10.2020. The Forest case is under process.

110 Sunder 2018-19 C/O link road from Bag to Seri I The alignment has been finalized . Sunder Nagar via Lalag (Substituted on dated There is approximate 7.00 km. length Nagar 02/12/2019). of road out of which 3.00 Km. is Private Land and 4.00 km. is Forest Land approx. The revenue papers have been collected . The gift deed of private land has been obtained, FCA case under process. 111 Sunder 2018-19 C/O link road from Chalog to II The road alignment has been finalized Sunder Nagar Cheuri via Dhanyara there is approximate 0.670 km. Private Nagar (Substituted on dated land and 13.330 Km. Forest land. The 02/12/2019). private land owner has been requested to provide gift deed. The forest case is under process. The revenue paaper has been prepared. The NAC and FRA received, joint inspection has been done on 17.10.2020.Forest case under Prepeation.

112 Sunder 2019-20 MT on Bhawana to Gamouhu I Manuscript DPR return to EE Sunder Nagar road & C/O 19.75mtr.bridge Sundernagar for fairout (with Nagar over Plasi Khad alongwith obeservation) vide CE(MZ) letter No. approach road. 17531 dated 4.2.2021 for Rs. 971.99 lakh.The private land owners have been requested for gift deed . 113 Sunder 2020-21 C/O road from Dharli to Balag I DPR under preparation, there is Sunder Nagar via Majhas. approximate 1.600 km. Private land Nagar and 17.300 Km. Forest land Its inspection done on 21.1.2021. 114 Nachan 2017-18 C/O Gohar Mouli ki Aal to V Alignment has been finalized. But the Gohar Kharsi via Kutahad, Gulad, peoples are not ready to give there land Baihri, Gulad mod upper for the construction of road. Badrsav, Lambidhar, Vuratan road i/c motorable bridge over Mouli ki Aal. 115 Nachan 2018-19 C/O road from Burahta, Kasan , I land dispute which is being resolved so Gohar Dev Buniyari temple to Village far. Thedi, Dulad, kutla Gallu i/c motorable bridge over Jagrot and Kasan khad. 116 Nachan 2018-19 C/O road from Khun Surahi II Alignment has been finalized and Gift Gohar khad to Dalidar via Jurah i/c deeds of private land are awaited. (km. motorbale bridge over Suri 0/0 to 1/0 & 2/0 to 4/0 forest land Khad. and1/0 to 2/0 private land) priority needs to be changed. 117 Nachan 2018-19 C/O road from Dindla , III Alignment has been finalized and Gift Gohar Darbehad, Kagar, Naitala, deeds of private land are being taken. Hateshwari temple , Bhanard- (km. 0/0 to 3/190, 3/290to3/770 & Bihari to Sethal Patka (G.P. 3/870 to 4/445 private land and 3/190 Rajwardi) & C/O Motorbale to 3/290, 3/770 to 3/870 & 4/445 to bridge over Panhaind khad. 4/775 forest land. DPR will be (This scheme given by the prepared after receiving the gift deeds MLA in place of MI scheme). of the land. 118 Nachan 2018-19 C/O road from Devidad to Jach IV This alignment totally falls under forest Gohar via Dabroo Dawara land & Revnue papers are being (Substituted on dated prepared. Katcha road stands 29/08/2020). constructed up to 10.000 km. length by local people/panchyat. 119 Nachan 2020-21 C/O road from Brakhmani to I Alignment has been finalized and Gift Gohar Dugrai via Samot. deeds of private land are awaited. (km. 0/0 to 1/0 private land and1/0 to 1/860 forest land) 120 2020-21 C/O road from Greding House I Alignment has been finalized and Gohar Chail Chowk to Samoh via Revnue papers are being prepared (km. Chokhadri Lambidhar. 0/0 to 6/500 forest land & 6/500to 7/0 private land) 121 Nachan 2020-21 C/O road from DAV School IV Alignment has been finalized and Gohar Basa to Baihri via Gulad & C/O Revnue papers are being prepared. motorable bridge over Jyuni (km. 0/0 to 0/500 forest 0/500 to 1/300 Khad. private 1/300 to 2/0 forest 2/0 to 2/500 private & 2/500 to 3/500 forest land) 122 Seraj 2017-18 C/O Motorable road Bagi- II Alignment has been finalized Seraj Dhar-Thach-Bharedi- Alignment done approximate Road Bhatkidhar. length is 12.00 km. out of which 5.00 km. forest land involved and Gift deeds awaited . 123 Seraj 2019-20 C/O road from Samgad- I FCA Case under preparation , Gift Seraj Shalwad-Sandwas-Nalot- deeds awaited . Alignment done the Boong-Dandheli, Tehsil approximate Road length is 3.400 km. Balichowki, Distt.Mandi. out of which 3.140 km. forest land Km. 0.300 Km is Private involved 124 Drang 2017-18 Tiun Bridge to Bulang- II Survey work completed and data Mandi Ghagtian -Kampan-Dhangyan- collected.Gift deed awaited and forest No.I Kashehar- Kalangher- Hurang case will be made on-line after road Km.0/0 to 15/0. receiving gift deed. Road length 15/0 Km. Forest land 6/0 Km. & Private land 9/0 Km. 125 Drang 2017-18 C/O Dhamrehar to Tarswan- III Survey work completed and concent of Mandi Drangar-Garhagoan, Samalang- people donating land free of cost No.I Dagwandhar road Km.0/0 to awaited. Road length 8/0 Km.Forest 8/0. land 3/0 Km. & Private land 5/0 Km. 126 Drang 2017-18 C/O Jorla Darlog Bodandhar IV Survey work completed & DPR under Mandi Kuthyar Badon Kufari road preparaton in Sub division office. Road No.I (Subtituted on dated length 10/0 Km. Forest land 6/0 Km. & 27/11/2019). Private land 4/0 Km. 127 Drang 2018-19 C/O Jamtehar Kalhog Kau I DPR prepared and Feasibility drawing Mandi Maman Dugh Tarwan Kohag of bridge under process. Total Road No.I road i/c C/O bridge over Uhl length 8/0 Km. , forest land 3/200 km. river (Subtituted on dated & Private land 4/800 Km. 27/11/2019). 128 Drang 2018-19 C/O Radahan Suraj Bagala II Alignment finalized and DPR under Mandi Badhala Pundal Kaloun preparstion Gift deed for private land No.I Surahan road (Subtituted on being collected and forest case will be dated 27/11/2019). made on-line after receiving gift deeds.Road length 14.090Km. , forest land 11/640 km. & Private land 2/450 Km. 129 Drang 2019-20 C/O Boching-Sachyan-Kadyan- I Alignment finalized and consent of Mandi Lachyan-Khaman-Jhukan- people donating land free of cost No.I Ganhag, Mad road. awaited. Road length 16/0 Km. , forest land 9/600 km. & Private land 6/400 Km. . 130 Drang 2019-20 C/O road from Basni Nalla to II Revenue paper prepared for obtaining Mandi Sangad Swadi, Teper, Dagsi, gift deed & forest case prepared but No.I Khandli, Kavdyana, gift deed not received yet. Road length Chambadhar. 11.920Km. , forest land 9/570 km. & Private land 2/350 Km. 131 Drang 2020-21 C/O road from Tikker-Sharni- I Survey work completed and consent of Mandi Jorla-Ukhal-Galoo-Tapra- people donating land free of cost No.I Sanvad. awaited .Road length 5/0 Km. Forest land 3/500 Km. & Private land 1/500 Km. 132 Drang 2020-21 C/O road from Kunnu-Badidhar DPR under preparation. Road length Mandi via Gajaon (including two 6/500 Km. Forest land 0/800 Km. & No.I No.bridges). Private land 5/700 Km. . 133 Drang 2020-21 C/o road from Ropa-Ghunag- Survey work completed and consent of Mandi Kathog-Batehad-Jamtehad- people donating land free of cost No.I Hurang-Swad. awaited. Road length 10/0 Km. Forest land 7/0 Km. & Private land 3/0 Km. 134 Drang 2020-21 C/o road from Batheri to Survey work completed and consent of Mandi Bkalboot (including one people donating land free of cost No.I No.bridge). awaited Road length 9/0 Km. Forest land 7/0 Km. & Private land 2/0 Km.

135 Joginder 2019-20 Up-gradation of link road I Alignment finalized Km.0/0 to 13/500. Joginder Nagar Aihju-Golvan to Chalahnu. Gift deed being arranged. Pradhan Nagar Gram Panchyat Ahju, Ropri, Golwan & Pihar Badhlu have been requested to motivate General Public of the area to gift their land coming in the alignment Thereafter FCA case will be processed. 136 Mandi 2017-18 C/O road from Kenchi Mor to 7 I Alignment finalized and revenue Mandi Mile via Janjohi, Lajhukhar papers collected, FRA awaited. Work No.II Bahanidhar Kasani (Substituted is in progress under OTMNP Head. on dated 09/05/2018). Forest land = 12.00 Km. and Private land = 2.400 Km. (80% Gift deed available). 137 Mandi 2017-18 C/O link road Rihan Dhar to V Alignment finalized. FCA case under Mandi Ayala Banot, GP Majhwar preparation and FRA awaited. (90% No.II (Substituted on dated Gift deed available) Forest land = 23/05/2017). 2.500 Km. and Private land = 1.500 Km. 138 Mandi 2018-19 C/O road from Kalothar, I Partially gift deed received. Forest Mandi Lohard, Chanalsa Bhargram, land= 3.900Km. and Private land= No.II Vadyar Harizan Basti Bhoura 2.600 Km. (Proposal submitted for re- Naal Amla -Tala to Harizan naming the road i.e C/O road from Basti Rachhoda. Kalothar to Lohard as desired by the Hon'ble M.L.A. Sadar) 139 Mandi 2019-20 C/O link road Nichla Thanout I Forest land = 0.750 Km. and Private Mandi to Chalonh. land = 0.250 Km. Gift deed partly No.II received. 140 Mandi 2019-20 C/O link road Baggi to II Forest land = 1.850 Km. and Private Mandi Lahanga. land = 1.850 Km.Gift deed partly No.II received. 141 Mandi 2019-20 C/O road Sain Chopra Druman I Forest land = 1.900 Km. and Private Mandi Saploh in GP, Nichli Surrari land = 0.800 Km. F.R.A. completed No.II (Substituted from RWSS upto Druman, revenue paper is to be Scheme on dated 24/01/2020). prepared. 142 Mandi 2019-20 C/O road Kalothar to Karnal in II Alignment has been finalized.Gift Mandi GP Dawah (Substituted from deeds being arranged. FCA case under No.II RWSS Scheme on dated preparation. Forest land = 2.800 Km. 24/01/2020). and Private land = 1.200 Km. All revenue paper completed 143 Sarkaghat 2018-19 C/O road from Gaihra School II FCA under preparation. The Sarkaghat to Khandahar-Sadwal- upto approximate road length is 6/800 out Guhad Majhwad. of which 3.400 Km forest and 3.400 km. is private land. 144 Sarkaghat 2019-20 C/O road Narla to Dameli via I Alignment finalized on 03-12-2019 & Sarkaghat Chowk, Karakwahan GP total road length in 3.500 Km and Chowk. letter written to Gram Panchyat Pardhan for colletion and motivating to local public for giftdeed their land in favour of HPPWD. 0.700 km. forest land 2.800 km Private land invloved. 145 Sarkaghat 2019-20 C/o road Tarda-Ka-Khool to II Alignment finalized on 03-12-2019 and Sarkaghat Baggi via Chuhak. letter written to Gram Panchyat Pardhan for colletion and motivating to local public for giftdeed their land in favour of HPPWD. 0.500 km. forest land 1.500 Private land invloved. 146 Sarkaghat 2019-20 C/O road from Thouna, Gaihra, V Alignment finalized and FCA under Sarkaghat Murahdevi. preparation. The apporximate road length is 6.500 km out of which forest land 0.900 Hect. 2.20 Private land invloed. Gift deed awaited. 147 Sarkaghat 2020-21 MT road Chmyanu-Bhatoh via II Manuscripit DPR submitted to Chief Sarkaghat Paira Kusti Km.0/0 to 6/0. Engineer (MZ) by SE 1st Circle dated 6.2.2021 for Rs.605.98 Lakh.The apporximate road length is 6.000 km out of which forest land 0.600 km. 5.400 Private land invloed. Gift deed under process. 148 Sarkaghat 2020-21 C/O link road Kash-Dabrog- III Alignment finalized. The apporximate Sarkaghat Gehra via Kufru Km.0/0 to road length is 4.000 km out of which 4/00(Substituted on dated forest land 0.600 km. 3.400 km Private 30/12/2020). land invloed. Gift deed under process. 149 Sarkaghat 2020-21 C/O link road Badon to Murari IV Alignment yet to be finalized The Sarkaghat Devi in Km.4/0. apporximate road length is 4.000 km out of which forest land 2.000 km. 2.000 Km Private land invloed. Gift deed under process. 150 Jaisingpur 2017-18 C/O road Suan Bhodi to Baba I Private and forest land involved. Joint Jaisinghpu Sidh Bhodi upto Ashapuri Lad inspection has been done by D.F.O r Galu. Palampur with EE Jaisinghpur on dated 23-1-2020. FRA case sent to SDM Jaisinghpur by E.E. Jaisinghpur dt. 2.12.2020 and again requested to SDM Jaisinghpur byE.E.Jaisinghpur dated 22-1-2021 to manage the meeting as Sub Division levev forest committe is issue the FRA. 151 Jaisingpur 2019-20 C/O road from Paprola I Tentative alignemnt has been finalized Jaisinghpu (Patwarghar, Alampur & link and the gift deed for Alampur side r road Dareda Basti Alampur) i/c approach are still awaited . Hydraulic bridge over Neugal Khad data for 95.00 mtr span bridge over (Substituted on dated Neugal Khad is under preparation. 23/10/2020). 152 Baijnath 2018-19 C/O road from Uttrala to Surahi II Survey and alignment work for Km Baijnath Pass (Portion Baklood to Surahi 10/0 to 33/500 (Portion Baklood to Pass) (Substituted on dated Surahi Pass) completed, which 18/09/2019). involves maximum length of forest land (i.e. area 10-71-59 Hec). Regarding forest land all the formalities i/c preliminary survey detailed survey 2 Nos joint inspectionis FRA/FCA etc. has been completed and forest case has been upload online on dated 1.12.2019. Joint inspection at site by C.F. along with Superintending Engineer PWD 5th Circle Palampur held on dated 02.06.2020 and case (hard copies) further stand submitted to PCCF Shimla by the C.F. Dharamshala. On clearance of FCA case from GOI, the process for DPR preparation shall be taken in hand and only after approval therefore construction work will be started.

153 Baijnath 2019-20 C/O link road Sansal to Thathi II Survey and alignment work completed. Baijnath & Tasijoug to Village Forest and pvt land involved. Forest Chandpur. clearance obtained but pvt land portion gift deeds awaited despite repeated requests by AE Bir with Panchyat Pardhan concerned . 154 Nurpur 2018-19 C/O Sulilai to Relay to Middle I There is forest/ private/ society land Nurpur school Bardi via Band Hatli in the alignment of the road. The land road -3.00km. owners are being persuaded to donate their land free of cost for construction of road. The forest case will be prepared after the receipt of gift deed from private land owners. 155 Nurpur 2019-20 C/O link road from Khajjan to I The total length of the road is around Nurpur Baluhi i/c bridge over Jabbar 1.300 km. i/c 1 No. bridge over Khad. JabbarKhad. The work of construction of the bridge is in progress under State Head. However manuscript DPR for road portion is under preparation at Divisional level. 156 Nurpur 2019-20 C/O link road from Bhaloon to II The FCA case for transfer of forest Nurpur Garore via Bassa Samletian i/c land have been prepared and 1No.Bridge. submitted on line to Nodal Officer (FCA).its approval, the hard copy have been submitted with DFO Nurpur. More-over there is 1 No. bridge in the alignment, for which working drawing have been evolved vide SE letter No. SEIX/WA-1/2020-478 -79 dated 6.6.2020 . The D P R is under preparation. In Divisional Office . 157 Nurpur 2020-21 C/O link Lakhanur Chandahan I The private and forest land involved Nurpur Baranda, road Tehsil Nurpur, in the alignment. The land owners are Distt.Kangra. being persuaded to donate their land free of cost. Thereafter the FCA will be initiated 158 Nurpur 2020-21 C/O road from Mankot to II . The private and forest land Nurpur Samela via Sujanta Draman, involved in the alignment. The private Tehsil Nurpur, Distt. Kangra. land owners are being persuaded to donate their land free of cost. The FCA will be prepared after receipt of gift deed from the private land owners. 159 Nurpur 2020-21 C/O road from Sukhar to III The road passes through private Nurpur Village Salahan including one land. No.bridge over Chhouch Khad, Tehsil Nurpur, Distt. Kangra. 160 Fatehpur 2017-18 C/O road Dayal-Mandlai- I Forest land is falling in the road & Fatehpur Kohladi Dhaiyath. alignment is not finalized as yet. 161 Jawali 2017-18 C/O balance work of link road I Alignment finalized. Investigation Jawali from Nagrotu Khad Bridge to work done. Pvt./forest land involved in Sarola Ludhiar road. some reaches. Forest case under preparation &Pvt.land owners are being motivated to donate their land. 162 Jawali 2018-19 C/O road from PWD Rest I Survey and investigation work Jawali House Kotla to Rajol Anuhi up completed. Alignment finalized. There to Gambhirthal bridge i/c is involvement of private/forest land. bridge over Dehar Khad Forest case under process. Hydraulic (Substituted on dated data over Deharkhad finalized. 30/01/2019). Feasibility report of Proposal drawing sent to CE (KZ) HP:PWD. Dharmshalavide by SE HP:PWD Nurpur dated 11.01.2021 for evolving of working drawing.

163 Dehra 2018-19 C/O road from Thathar to Vasa II Forest land involved FCA case under Dehra Tripal . preparation in Division office. 164 Jaswan 2017-18 Road from Kanol (GP Tikker) II DPR in manuscript under process in Kotla Pragpur with one No. bridge to Divisional office . Gift deeds awaited Behar Chamubha via Handal, from the private owners. Brahman Basti & Gujjar Basti. 165 Jaswan 2020-21 C/O road Durgain-Rakhalda- I Forest and private land involved in the Kotla Pragpur Kanpur Beri via Chakoli alignment of road. (Forest case under Behar including Bridge. preparation and gift deeds awaited from land owner). Joint Inspection to be done on 04/02/2021. 166 Jaswan 2020-21 C/O road Pirsaluhi (Kangra) to II Forest and private land involved in the Kotla Pragpur Kitpal (Hamirpur) via Nauri alignment of road. (Forest case under Behar including bridge. preparation and gift deeds awaited from land owner). 167 Jawalamu 2018-19 C/O Link road from Ghatta to I Forest & Pvt.land involved. Forest case Dehra khi Bhauran Nichali via Uprali is under preparation & department is Bhauran km. 0/0 to 3/0. motivating to public to donate their land. 168 Jawalamu 2018-19 C/O link road from Chowki to II Forest & Pvt.land involved. Forest case Dehra khi Sarvnati G.P.Panchayat Majhin is under preparation & department is km. 0/0 to 2/0. motivating to public to donate their land. 169 Jawalamu 2019-20 C/O road Chouki to Dabkehad I Forest & Pvt.land involved. Forest case Dehra khi (GP Majhin) Km.0/0 to 3/0. is under preparation & department is motivating to public to donate their land. 170 Jawalamu 2020-21 C/O road from Ambada to I Private land involved, Land owners are Dehra khi Bhaloch via Kidi. being motivated to donate their land . 171 Jawalamu 2020-21 C/O road from Dehriyan to II Private land involved, Land owners are Dehra khi Balha. being motivated to donate their land . 172 Nagrota 2020-21 C/o road from Kalijan to Sheedi I Working Drawing preparaed for 30.00 Tanda Bagwan Marg Balol via Tarbhna Degar mtr. Span Bridge over Nareli Khad & Lahad & i/c bridge over Nareli DPR Under Preparation. Private land Khad. involved & Gift land awaited. 173 Kangra 2017-18 C/o link road Rahad Basti Tika I Scheme falls under 100% Forest in Kangra Pantehar G.P.Gahliya length which forest case (FCA)papers under Km.1.5. preparation for granted its approval from the competent authority. DPR Under process in Circle Office . 174 Kangra 2019-20 C/O GP Nanrool Kangdi to II DPR not prepared due to non Kangra Panchayat Ghar Nandrool via availability of land because of scheme up to Munshi Ram house road. falls 60% in pvt. Land and 40% in revenue land in which the gradent of road has not found feasible for moving vehiclers traffice. Affords for getting suitable site are made with local bodies in the area. 175 Kangra 2020-21 C/O road from II Scheme falls under Forest / pvt. Land Kangra Gahliyan(Palera) to Kalothar involved in which forest case (FCA) Matta. papers & gift deed awaited under preparation for granted its approval from the competent authority.

176 Dharamsh 2018-19 C/O link road Bangotoo to II DPR manuscript shape checked by CE Dharamsh ala Lindi, Vehi & Lindi Vehi to (KZ) on dated. 19/12/19 for Rs.426.75 ala Tilla Mata Mandir. lacs. Fair DPR return back to EE D/sala by SE on dated 11/2/19 with observations the FRA certificate due to Hon'ble Supreme Court of has passed interm order on dated 11/3/19 O.A. No.3840. There shall be no diversion of forest lands allotted to protection working Circle under FRA & FCA till next date. Now the DFO Dharamshala has requested vide EE Dharamshala office letter dated 03/11/20 to fix the suitable date and time for inspection. 177 Palampur 2017-18 C/O link road Chouki-Punnoo II Due to involvement of Pvt.land. Palampur Ram Mayul Shed to Nalahar Alignment could not be finalized. via House of Ramesh Chander. 178 Palampur 2018-19 C/O link road to village Gehar, II Survey work completed. Partly forest Palampur Spedu, Kandwari Kalohi- & Pvt.land involved in addition to Rajehar including 25 mtr span 3.00km. Existing road. Paper bridge over Pung khad. formalities for NOC under process. Also hydraulic data of proposed bridge over Pung Khad under preparation. 179 Palampur 2020-21 Construction & Upgradation of I Gift deed being collected from land Palampur road from Rampur-Rajehar- owners and D.P.R under preparation in Sarsawa via Kapen-Neelkanth Division office mandir-Bhadrena-National Highway at Sungal. 180 Churah 2018-19 C/O link road from Tarwai to I Alignment finalized. Total length Tissa Banjal i/c C/O Bridges from 8.00km. Pvt.forest land involved for Km.0/0 to 8/0 (Substituted on which gift deeds still awaited.Pvt.land dated 23/07/2018). owner are not ready to donate their land. Forest case will be prepared after execution of gift deed. 181 Churah 2018-19 C/O link road from Guila to II Total length 3.500km. Forest case 0/0 Tissa Mansa (Substituted on dated to 1/500km. was approved under FRA 23/07/2018). & road has been completed from Km.0/0 to 1/500 under BASP. Km.1/500 to 3/500 pvt./forest land is coming in the alignment of the road. Pvt.land owner are not ready to donate their land hence forest case could not be prepared. 182 Churah 2019-20 C/O road Jarourgad to Gadyog. II Pvt./Forest land coming in the Tissa alignment Pvt.land owner are being motivate for gift deed. Forest case could not be prepared due to execution of gift deed. 183 Churah 2019-20 C/O bridge over Aayal Nallah III Alignment has been finalized. Tissa & C/O road from Aayal to Approximately the length of this road Guwadi. is 2.500km. Pvt./forest land is coming in the alighment. Revnue paper prepared gift deed is yet to be executied. Hydraulic date is under preparation.

184 Churah 2020-21 C/O main road Kenthal- I Alignment has been finalized. Tissa Papadoo to Masrund via Approximately the length of this road Aiharvad-Gurenta-Minda road. is 8.00km.which involved pvt./forest land. Further forest diversion case could not be prepared due to non execution of gift deed by the pvt.land owners.

185 Churah 2020-21 C/O road from Bhanraooo- II Pvt./forest land coming in the Tissa Salancha-Sakloga-Phultva- alognment .Pvt.land owner are not Dudra road. ready to donate their land (land dispute). 186 Bharmour 2020-21 C/O Channi bridge Elakalca I Forest case prepared & pending with Bharmour Mata Jalsu Jot road. Nodal office Shimla & DPR under preparation. 187 Chamba 2019-20 C/O Bhatalwan to Gadadi Ora I Alignment being finalized. Work Chamba road. pending due to non execution of gift deeds of the Pvt.land owners. 188 Chamba 2019-20 Link road to left out villages of II Alignment being finalized. Work Chamba Sirh Panchayat (Baloo to pending due to non execution of gift Housing Board colony). deeds of the Pvt.land owners. 189 Chamba 2020-21 Kotla to Karangar Nag road I Pvt./Forest land coming in the Chamba (Substituted on dated alignment Pvt.land owner are being 22/05/2020). motivate for gift deed. Forest case could not be prepared due to execution of gift deed. 190 Dalhousie 2017-18 C/O Jeepable bridge over Siul II Hydraulic data for C/O bridge has been Salooni river to connect village Matoon collected/ prepared & forest case for with jeepable road. diversion of forest land is being prepared. 191 Dalhousie 2017-18 C/O link road to village Jagot. IV Total length of road is 4.500 km.Forest Salooni land involved. Forest land diversion case under FCA 1980 has been prepared and submitted to forest Department. The DFO Salooni has raised some observation on dated 21.01.2020 through online for submitting hard copy of the case. The EE Salooni has requested the DFO Salooni vide his office letter No 8638- 39 dated 21.12.2020 for fixing joint inspection which is yet to be conducted. 192 Dalhousie 2018-19 Link road from Hathni to Biana III The total length of road is 3.460 km. Salooni in G.P. Biana under PWD The forest case prepared and Division Salooni. uploaded,Some observations have been raised by Regional Office Dehradun on dated 5-5-2020 which have been attended vide Executive Engineer Salooni Division HPPWD Salooni letter No 7406 dated 27-11-2020 & 10034 dated 01.02.2021 and case sent to DFO Salooni through online At present case is pending with DFO Salooni. 193 Dalhousie 2018-19 Link road from Rulyani to IV The total Length of road is 3.000 km. Dalhousie Bathri via Dhrota under PWD 2.193 Km is forest land and 0.807 Km Division Dalhousie. is private land.From Ruliyani to Dharota thick forest is coming in the alignement and Drota to Bathri is Jeepable road grade of existing road is very steep.The private land owners have been requested to gift their land for improvement of grade of the road but, they have refuesed to do so. Foerst case could not be prepared due to non execution of gift deed private land owners. 194 Dalhousie 2019-20 C/O link road village Sagoti in III Forest case for diversion of forest land Salooni GP Bhajotra Km.0/0 to 7/500. is under preparation.The Deputy Commissioner has been requested by the EE Salooni Division vide his office letter No. 10025-26 dated 01.01.2021 for issuing FRA which is awaited. 195 Dalhousie 2019-20 C/O link road from Panoga to IV The allingment for the construction fo Salooni Daneta Km.0/0 to 7/500. road has been finalised. Forest case is under preparation and also gift deeds from private land owner are being collected to donate their land. 196 Dalhousie 2020-21 C/O link road to village I Pvt./forest land coming in the Salooni Tribhol. alignment Pvt.land owner are being motivate for gift deed is yet to be executed. 197 Dalhousie 2020-21 C/O road from village Kilod to III Total length of road is 2.000 Km Salooni village Talai. (Forest Land) revnue paper for preparation of forest case are being prepared. 198 Bhatiyat 2019-20 C/O road from Jandrog to I Alignment has been finalized. Survey Dalhousie Chakki Km.0/0 to 13/0. work completed from Km 0/0 to 7/500 Km. the approximate length in forest is 6.500 Km. and 1.000 Km. is private land.The forest case has been uploadedon line on dated 15.07.2020bearing ID no. FP/HP/RAOD/47175/2020.Therafter the forest case Forest case folder Submitted to DFO Dalhousie and the same was received backwith observation vide DFO Dalhousie letter No. 5158 dated 07.12.2020, which has been attended by EE Dalhousie Division letter No. 17381 dated 10.02.2021. 199 Jhanduta 2017-18 C/O link road Bothu to main I Pvt./ forest land involved. Gift deeds Jhandutta road Chonta via Pump House not available. and Gadiyana. 200 Jhanduta 2017-18 C/O link road from main road II Pvt./ forest land involved. Gift deeds Jhandutta Dharad to Samleta via not available. Kakkdughat & Bareta. 201 Jhanduta 2019-20 C/o road from Jhamrarian to I Pvt.land gift deeds awaited. Forest land Jhandutta Bharoli Kalan via Dadhog- involved. Hydraulic data for the bridge tappe i/c bridge on Saryali is under preparation. Khad. 202 Jhanduta 2019-20 C/o road from Beri-Miyan to II Survey work is in progress. Pvt.land Jhandutta sherad via Baghra i/c CD & gift deed awaited from land owners. MT. 203 Jhanduta 2020-21 C/O road from Damehda to I Pvt.land involved & gift deeds are Jhandutta Lower Bukhar via Upper awaited from land owners. Bukhar Km.0/0 to 6/200. 204 Jhanduta 2020-21 C/O road from Bhadol to Baddi II Pvt.land involved & gift deeds are Jhandutta Billour Km.0/0 to 3/00. awaited from land owners. 205 Ghumarw 2017-18 C/O road in Bhager, Fatoh, I Pvt./forest land involved. Gift deeds Ghumarwi in Khurari, Kalari, Dharai, Sarti, not available. n Panoh i/c bridge (substituted on dated 06/10/2017). 206 Ghumarw 2017-18 C/O road Saloua-Fagat- III Pvt./forest land involved. Gift deeds Ghumarwi in Dardehda-Thyula- Pantehda- not available. n Khubban. 207 Ghumarw 2017-18 C/O link road from New NH- IV Forest/Private land ,gift deeds not Ghumarwi in 21(4-lane road) to NH-103 via available. DPR under scrutiny in n Village Palanth in GP Oahar. Divisional office. 208 Ghumarw 2017-18 C/O link road Daloh-Jol- V Forest/Private land ,gift deeds not Ghumarwi in Galiyan. available. DPR under scrutiny in n Divisional office. 209 Ghumarw 2018-19 C/o link road from Daghol III Gift deeds are awaited from land Ghumarwi in ladraur at Vilage Koti to owners. n Kamali, Samlah ,Bhatwad, Paplan, Malot i/c bridge over Drug khad. (Scheme given by MLA in place of MI scheme). 210 Ghumarw 2019-20 C/O link road from Bum I Gift deeds are awaited from land Ghumarwi in road to Glah Galahi Hatwar owners. n near school via Brahmli Nallah Km.0/0 to 2/0. 211 Ghumarw 2019-20 C/O Link road from Barota- II Gift deeds are awaited from land Ghumarwi in Domehar-Unda owners. n (Mihara)Km.0/0 to 3/800 i/c culvderts. 212 Ghumarw 2020-21 C/O road Nihari to Chanjyar II Gift deeds are awaited from land Ghumarwi in via Klot . owners. n 213 Bilaspur 2017-18 C/O link road Bardi to Bardi II Forest and Pvt.land involved. Gift Bilaspur School and C/O link road to deeds not available. No.I village Jukhap to Maswad i/c bridge. 214 Bilaspur 2019-20 C/o link road Nalti Mour to II Private land involved. Land owners are Bilaspur Talwada i/c bridge & C/O link not donate their gift deeds. No.I road Baroti to Mandridhar via Nanava. 215 Shri 2017-18 C/O link road from S.N.B. road I Private land involved. Gift deeds not Bilaspur Naina to village Khal Tibba in Distt. available. FCA is in progress. No.II Devi Ji Bilaspur (Substituted on dated 13/01/2020). 216 Shri 2017-18 C/O road Tunnidhar to Shikroa II Private land involved. Gift deeds not Bilaspur Naina via Bag Chamyara. available. FCA is in progress. No.II Devi Ji 217 Shri 2019-20 C/O link road villages Gasoud I Private land involved. Gift deeds not Bilaspur Naina to Lower aur Upper Bholi i/c available. FCA is in progress. No.II Devi Ji bridge over Alli Khad. 218 Shri 2019-20 C/O link road Neri to Badnoo II Land owner are being persuading to Bilaspur Naina ghanser Tunnighat. donate their land and FCA under No.II Devi Ji process. 219 Bhoranj 2018-19 C/O Road from Lathwan to I Land not available .Gift deeds are Bhoranj Ladrour . awaited. 220 Bhoranj 2018-19 C/O road from Awahdevi By II Land not available. Gift deeds Bhoranj pass to Harizan Basti via received. Bohan. 221 Bhoranj 2019-20 C/o road Jahu to Chandruhi via I Land not available. The alignment of Bhoranj Badehar, Jol Kohta i/c road/survey work has been completed, 2No.bridges. the total length about 4.00 km.& matter to donate the land was taken by land owners. 222 Bhoranj 2019-20 C/O road Samlog to Gouta i/c II Land not available. The alignment of Bhoranj 1No. Bridge. road/survey work has been completed, the total length about 4.00 km.& matter to donate the land was taken by land owners. 223 Bhoranj 2020-21 C/o link roads in left out II Total length of roads 9.500km.Pvt.land Bhoranj habitation in village Saharwin, involved. Gift deeds awaited from land Bhiar to Kot, Seu toKasiyana, owners. Pehanjwin to Badiyana bridge, upper Karha to Buthwin Tangre. 224 Sujanpur 2017-18 C/O link road from Chabutra to I DPR prepared amounting to Rs. 108.38 Touni Ree via Lahul. lac. but gift deed not handed over by Devi the owners of land to PWD.85% gift deed completed. 225 Sujanpur 2017-18 C/O link road from Bhaleth to IV Survey work done. Gift deeds process Touni Village Ropa. is in progress. Devi 226 Sujanpur 2018-19 Link road from Banalagto I Survey work completed & gift deeds Touni Rangad (G.P. Pouhanj & awaited from land owners. Devi Rangad). 227 Sujanpur 2018-19 C/O link road from Banal to III Gift deeds are awaited. Pradhan GP Touni Dharkad, Dhiman Basti Saluhi, was requeted for persuad the owner to Devi Beri Vet.Hospital to Nagari donate the land. Village, Bagehada to SC Basti Bid Khas, Dhail Village to upto Jamiri khad, Thanadhar main road to upto Mehli Khad via Ropa Km.2.5 (Substituted on dated 21/10/2019). 228 Sujanpur 2019-20 C/O link road from Pohanj- I Survey work completed. Gift deeds Touni Andral to village Bandroh. awaited from land owners. Devi 229 Sujanpur 2019-20 C/O link road from Jamer khad II Survey work completed. Gift deeds Touni to village Racho on Patlandar- awaited from land owners. Devi Rangad road. 230 Sujanpur 2020-21 C/o link road Puad to Tikkri via II Gift deed awaited from land owner of Touni Dharli, main road village Pradhan of G.P. Karot has been Devi Saghun Hira, main road village requested to motivate land owner to Janddu (Ridi)upto house of donate land to HP:PWD., for the C/O Bhag Singh, main road village this road. Chloh upto house Daulat Ram & C/O road Bhadmeli-Majhog- Chabot i/c const./height of bridge. 231 Hamirpur 2018-19 C/O Bridge over Kunah khad to I Land not available and Gift deeds are Hamirpur link Bomana & Lundri (PWD- awaited from land owners. Division Barsar). 232 Hamirpur 2018-19 C/O Link road alongwith bridge II Alignment finalized and Gift deeds are Hamirpur over Nallah Dug from village awaited from land owners. Bhatwara to Nalti via Avdhyal (PWD Division Hamirpur). 233 Hamirpur 2020-21 C/O link road Pandwin to I Alignment has been finalized. Gift Hamirpur Saned via Tikker, Bhuran to deeds are awaited from land owners. Balh Km.0/0 to 4/0. 234 Hamirpur 2020-21 C/o link road Jungle to Galota II Alignment has been finalized. Gift Hamirpur via Gugga i/c bridge Km.0/0 to deeds are awaited from land owners. 4/0. 235 Barsar 2017-18 C/O road from Ropri to Kharal I Survey work has been done. Gift deeds Barsar via Hansara Jandroh, Choa are awaited from land owners. Kathiana Saryana (Substituted on dated 30/10/2018). 236 Barsar 2017-18 Up-gradation of road Badaran II The road has been constructed and Barsar to Garli via Jol Dhabriana maintained under State head and also Garli, Usnar Kalan Nara, qualify for PMGSY-II or III but Darkoti to Harsour (Substituted land is not available to increased on dated 30/10/2018). the road crust from 3.05 mtr to 3.75 mtrs (The total length of this road is 30.500 km &private land is 17.600 Km . 237 Barsar 2018-19 C/O road from Balh, Bihal, I Survey work has been done. Gift deeds Barsar Lakhoh, Gardi to Tikker, Sagi are awaited from land owners. Da Tiyala upto Main road. 238 Barsar 2018-19 C/O road from Kuriyah to II Survey work has been done. Gift deeds Barsar Ghangot Badu via Thedu, are awaited from land owners. Usnad-Kotlu etc (i/c bridges). 239 Barsar 2019-20 C/O bridge over Shukker Khad I Pvt.land involved. Gift deeds are Barsar on Balh Rantu, Choa, Dhamani awaited from Pvt.land owners. road Tehsil Bijhari. 240 Barsar 2019-20 C/o link road from Ganoh II Pvt.land involved. Survey work has Barsar Brhamana via MIT Bani been done. Gift deeds are awaited from Harizan Basti Ganoh Brhamana Pvt.land owners. Tehsil Barsar. 241 Barsar 2020-21 C/O link rod Dandwin to I Pvt.land involved. Survey work is in Barsar Dhangota via Kharal alongwith progress. Gift deeds awaited from the slab culverts. Pvt.land owners. 242 Barsar 2020-21 C/o link road Kakkar to II Private land involved .Survey work is Barsar Kalwara, Peepal wala Pind via in progress.. Gift deeds awaited from Loharka, Dabrani. Private land owners (Total length of this road is 4.500 km & private land is 4.00 Km) 243 Nadaun 2017-18 C/O Pansai-Jasai-Behrad, I Gift deed received total length of this Barsar Dhanoa-Tuhni-Kashmir with road is 17.00 km & private land is upgradation of Paniyali road. 14.500 Km & 2.500 km is Govt. land) (DPR under preparation in Sub Division Office)

244 Nadaun 2017-18 C/O road NH-70 to Kuthar III Survey work is in progress & gift deeds Hamirpur college- Rakkad-Kallar-Bhatta. are awaited. 245 Nadaun 2018-19 C/O road from lower Hareta to I Gift deed received total length of this Barsar Lashmai, Nagarda to Shani Dev road is 1.630 km & Govt. land is 0.500 Mandir Bandos, Reepul Balh Km) (DPR under preparation) Kotlu Tihari road including construction of bridge over Hareta khad at Lower Hareta Sub Division Dhaneta, XEN Barsar. 246 Nadaun 2018-19 C/O link road from Thai More II Alignment finalized. Total Length = Hamirpur to Bann Jandli Gujrian, 3.000 kms. Forest land from Km 0/0 to Bhaloon Panyala Amlehra road 2/210 and private land from KM 2/210 in Teh. Nadaun Sub to 3/0 involved Divn.Nadaun XEN Hamirpur. 247 Nadaun 2019-20 C/O road from Seradi sidh- II Gift deeds awaited from Pvt.land Barsar Jandoo Bahal SC basti i/c owners. The Pradhan of concerned GP bridge. was requested by AE Dhaneta on dated 16/11/2019. 248 Nadaun 2020-21 C/O intermediate road from II Gift deed received and DPR under Barsar Sera road-Sera-Pakhro-Manpul. prepartion in Sub Division Office.Total length of this road is 5.500 km) 249 Chintpurn 2019-20 c/O & MT of link road Kotla to I Alignment has been finalized. Pvt.and Bharwain i Mairi via Nehri Khalsa forest land involved & gift deeds are 1No.bridge and connect DSP awaited from land owners. Mohalla Kuthera Khairla. 250 Chintpurn 2019-20 C/O & MT of link road Jawar II Alignment has been finalized. Pvt.land Bharwain i to Ghagoh High School via involved & gift deeds are awaited from Nari Villanda Thapal Maslana land owners. i/c Bridge.

251 Chintpurn 2020-21 C/O & MT L/r Palian Jaswanla II Pvt.land involved. Gift deeds are Bharwain i to Basantpur under GP.Chowar. awaited from Pvt.land owners. 252 Gagret 2019-20 C/O & MT on link road Joh II Total length is 4.00 kms. Pvt. & forest Bharwain chowk to Tappa Sidh upto land involved. Gindpur Maloun i/c Bridge. 253 Gagret 2020-21 C/O bridge over Swan river on I Private land is involved & gift deed are Bharwain link road Marwadi to Joh via awaited from land owners. Sandhani Km.0/0 to 3/870. 254 Haroli 2018-19 C/O road from Singa to Bathri II Survey work completed. Total length is Una i/c bridge in between. approximately is 3.00 kms and gift deds awaited from land owners. 255 Una 2017-18 C/O link road from Shiv II Field survey has been made at site . Una Temple Malahat to Chatada via Private land involved gift deeds Dhesi Mohalla Vill.Basoli & awaited from land owners. Length = upto Majra Khai Basoli, Una 5.500 kms. Hamirpur road to Ward No.1 & Mohalla Brahaman to Harda wala Bag, Gurdwara Lower Arniyala, Una Satoshgarh road to Swan Vela, Windeing & strengthening of Circular road village Bhadoliyan Kalan & C/O road to 10+2 school & Panchayat Ghar. 256 Una 2018-19 C/O New link road from Sasan I Survey work completed. Length = Una village to Pekhubela. 4.800 kms . Private land involved gift deeds awaited from land owners. 257 Una 2019-20 C/O link road to Kamoon & I Survey work completed. Length = Una Labana Basti from village 2.500 kms . Private land involved , gift Fatehwal in GP Bangarh of Una deeds awaited from land oweners. Constituency & re-construction of link road Mehatpur Handola to Ward No.5 in GP Mehatpur. 258 Una 2019-20 C/O link road from village II Survey work completed. Length = Una Basoli Ward No.1 (Labana 3.200 kms . Private land involved , gift Mohalla) to Lamlehri via deeds awaited from land oweners. Sandhal. 259 Kutlehar 2020-21 C/O Boul to Jhamber, Lam II Alignment finalized. Land dispute. Bangana Nari, takka Mohalla Sainian and abadi Jhingra i/c 2No.bridges over Takka Khad & Dhamandari Khad in Km.0/00 to 12/800. 260 Kutlehar 2020-21 C/O link road from Jagatkhana III Alignment finalized. Gift deeds are Bangana to upper Raipur via Baroti, awaited from land owners. Forest land Ghat, Gharwarsa. involved. 261 Kutlehar 2020-21 C/O road from TMBD to , IV Alignment finalized. Gift deeds Bangana Bagdhar & Bharari Mata receited from land owners. Forest land Mandir Paroian Km.0/0 to 6/00. involved. 262 Gagret 2018-19 C/O Bridge over swan river on II DPR sent to Ministry GOI on dated Bharwain Loharli to Charudoo road. 05/11/2020 for Rs.45.85 crores under CRF 263 Nahan 2018-19 Bridge over Batta River on II DPR sent to MORT&H on dt. Paonta Badripur-Jamniwala-Majra 05/11/2020 for approval under CRIF road Fatehpur Gulabgarh for Rs.1542.00 lacs. alongwith Improvement MT cross drain of the road . 264 Dharamp 2019-20 C/O bridge over Beas river I DPR has been sent to Govt. of India for Dharampu ur from Sidhpur GP, Sidhpur to inclusion under CRIF. r Kothi Pattan. 265 Jubbal & 2017-18 C/O & M/T of Riyoghatti to II Repeated Jubbal Kotkhai Galeha via Kufer Bag Shaktinagar road (substituted on dated 01/07/2017). 266 Nalagarh 2017-18 C/O Pucca link road Barian- II Repeated-2020-21(P-I). Nalagarh Alyon-Dhano Ghat, Teh.Nalagarh (Substituted on dt.29/08/2019). 267 Shillai 2018-19 Improvement of Chimy Barwa II Priority repeated 2015-16 Shillai Chankoli road. 268 Kutlehar 2020-21 Metalling & Tarring of road I Repeated 2019-20(P-I). Bangana from Olinda to Bohru in Km.0/0 to 11/090. 269 Chopal 2018-19 Imp. & M/T Marog , Matal to I DPR under prepration and will be Chopal Lohuna Kelvi Tir Road G.P. submitted by 15.2.2021 . Marog. 270 Chopal 2018-19 Imp. & M/T Pulbahal,Thundal III DPR amounting to Rs. Rs 1166.37 lacs Chopal Kainchi road to connect Lihat is under scrutiny in Zonal office. Bhadah & Saranh. (Scheme given by the MLA in place of MI schemes). 271 Chopal 2018-19 C/O Dasana Kenchi to Deothi I DPR was submitted to CE(SZ) by SE. Theog Jabbal Sabbal road from 4th dt. 01.01.2021 & returned back Km.0/00 to 8/900 for on 14,1,2021 with observation and is construction & Up-gradation of being updated on new schedule of road i/c Danga, Retaining wall, rates. tarring and culverts & etc.(Substituted from MI scheme on dated 03/09/2020). 272 Chopal 2019-20 Up-gradation Metaling & II The DPR in manuscrip shape is Chopal Tyring of road from Dhurla submitted to C.E.(SZ) vide SE-4th Kainchi to Ghichana Jubbar Circle letter No. 20558-60 dt. upto main road Rewalpul 01.02.2021 for Rs. 536.84 Lacs. for Maraog. approval.

273 Chopal 2019-20 C/O road from Sainj Khad to IV Alignment has been finalized .Total Chopal Harijan Basti Gawahi. length is 10.00 Km. which involves Private and Forest land . Gift deeds received and forest case under process 274 Chopal 2019-20 Up-gradation Metaling,Tyring V DPR under preparation a Chopal of road from Kutangan Nala to Kudhi Sarach. 275 Chopal 2020-21 C/o road from Dakoli Sheila I Manuscript DPR got approved and is Chopal Reweti to Khokha. being faired out. 276 Chopal 2020-21 Up-gradation of road Metaling IV DPR is being prepared and will be Theog & tarring from Huli Dasana, submitted by 15.02.2021. Khar, Ghoond, Gaderi, Banari. 277 Theog 2017-18 C/O road from Sandhu-Talash II U/P in field office. Theog via Bagoo length 5kms. 278 Theog 2018-19 Improvement & Up-gradation I Manuscript DPR checked for Rs. Kumarsain of road Sarion to Jadeog via 492.51 lacs by C.E. (SZ) on dated Naag in GP, Gawai (Devi 29/01/2021. DPR is being faired out by More) (Substituted on dated the Divisional office. 22/12/2020).

279 Theog 2019-20 Improvement, Metalling & II Priority received recently. Total length Kumarsain tarring of link road Shamathala of road is 7.600Km. Village wise status from Kanda PMGSY road, of road is given as below:- Kofferdhar to Behara via Kofferdhar to Behara via Nollha Lohrigad to Kofferdhar Nolha=4.530Km. (3.00Km is on the Horticulture road. motorable i.e. from Kofferdhar to Nolha and 1.530Km. is jeepable i.e. from Nolha to Behara Lohri gad to Kofferdhar 1.700Km. is motorable road. DPR is under preparation at will be prepared by the end of this month.

280 Theog 2019-20 C/O Thathal Nalla to Rachhani I U/P in field office. Theog under HPPWD.Theog Sub- Divn.Matiana (Substitued from MI scheme on dated 06/02/2021). 281 Theog 2020-21 C/O road from Kofni to Horu I Survey work is in progress. Kumarsain via Dora (IPH Pump House). 282 Theog 2020-21 C/O road from Tharmati II Alignment yet to be finalized. Theog Batiura Barog Dhamanderi. 283 Kasumpti 2017-18 C/O bridge over Majjar-Juggar II The work for providing consultancy Shimla Khad under GP Satlai. services has been awarded to the No.I consultant M/S Civil Mantra Infracon Pvt.Ltd.vide EE on dated 06/08/2020 to attend the observations. 284 Shimla 2017-18 C/O link road/Ambulance road II U/P in field office. Shimla in all the Wards of Shimla No.I Town. 285 Shimla 2017-18 M/T and Maintenance of roads III U/P in field office. Shimla in Shimla Town. No.I 286 Shimla 2019-20 C/O over bridge on Talaind. II The consultant has submited the Shimla General arrangement drawings for Two No.I No. over head bridge at Winterfield Old Bus stand & Leela Dhar Shop Near (Hotel Himland) and the same has been sent to Circle office on dated 16.10.2020 by EE for approval. 287 Shimla 2020-21 C/O bridge over Sanjouli I Feasibility to be explored. Shimla Chowk. No.I 288 Shimla 2020-21 C/O bridge over Talaind near II The consultant has submit GAD for Shimla Govt.Girls Sr.Sec.School. approval. No.I 289 Shimla 2017-18 C/O link road from Nalah- II Fair DPR is under scrutiny in Zonal Shimla Rural Shada-Natout (Km.5.00) G.P. office. Rural Karyali. 290 Shimla 2018-19 C/O Motorable bridge in I Tender of consultancy for preparation Shimla Rural Thachi Raihna Chanaldi road at & awarded to the contractor .The Rural Thachi Khad (Substituted on Hydrolic data submitted by S.E. 4th dated 28/01/2020). Circle to CE(SZ) on 13.01.202 for evolving drawing & design. 291 Shimla 2018-19 Upgradation and M/T of link II The DPR in Manuscript Shape is Shimla Rural road Fageda. submitted to CE (SZ) after attending Rural observation vide SE 4th circle office dt. 01.02.2021 for Rs.295.20 lacs only. 292 Jubbal & 2017-18 C/O & M/T of Kadivan to I U/P in field office. Jubbal Kotkhai Galoon-Umla Dwar (Tikkar) road. 293 Jubbal & 2019-20 C/O M/T from Baghi road II Total Length of this proposal is 16.00 Kotkhai Kotkhai Bhalidhar in GP Tharola Purag Km (PWD Land) . Work being & Rawlakyar. executed through A.M.P (Annual Maintenance Plan) 294 Jubbal & 2019-20 Up-gradation of Reoghatti to IV Total Length of the Road is 7.915 Km Kotkhai Kotkhai Galeha via Kuffer Bag- (PWD Road .DPR is under Preparation Bagainjubbad road (Substituted in Sub-Division office. DPR being from MI Scheme on dated submited by the 22.02.2021. 03/01/2020). 295 Rampur 2019-20 Bridge over Satluj at Rampur II The place for construction of bridge Rampur from Bye-Pass RD in MC finalized. Hydraulic data submitted to Rampur. higher authority for involving design and drawings. 296 Rohru 2017-18 Construction/Up-gradation of II U/P in field office. Rohru Lalpani, Dhumrera, Ambyasu road-8Kms. 297 Rohru 2019-20 Up-gradation of Badiyara, I DPR sent back to Executive Engineer Rohru Masli & Dakgaon road. Rohru Division for attending the observation on dt. 20.10.2020. 298 Arki 2017-18 Widening & M/T of Chanda II DPR under scrutiny in CE(SZ) on Arki Sehal Kishanpura Kurmula dated 28/07/2020. Ukhoo road. 299 Nalagarh 2018-19 MT from NH-21 to Bagheri - I DPR under scrutiny in CE (SZ) of Nalagarh Khatiwala Garmoda road. Rs.399.99 lacs. 300 Nalagarh 2018-19 C/O Bridge over Kanahan river II Manuscript DPR prepared and under Nalagarh on Dherowal-Chandpur- process. Toranwala- Chhida-Maganpur road. 301 Nalagarh 2020-21 C/O Pucca road Barian-Alyon- I U/P in field office. Nalagarh Dhanoghat Tehsil Nalagarh. 302 Doon 2019-20 C/O Balance work & Metalling I DPR under scrutiny in CE (SZ) Nalagarh on Dheela Kasla Abrani road. amounting Rs.519.71 lacs. 303 Doon 2020-21 Improvement and strengthening I DPR prepared & under process in Kasauli of Shaktighat bandh road. Divisional Office. (RNS) 304 Doon 2020-21 C/o bridge over Gamber Khad II Under process in field office. Kasauli on link road to Rampur. (RNS)

305 Solan 2017-18 Metalling Tarring of Lehan I Menuscript DPR under preparation in Solan Kotla to Sunnu Tikkari Ser field office. Chirag road from Km.4/0 to 8/315 (Substituted on dated 26/10/2020). 306 Solan 2019-20 C/O road Malga to Koon via I Manuscript DPR under preparation in Solan Baneni Khad in GP Poudhna. field office. 307 Solan 2020-21 C/O MT village Shamlech to I Manuscript DPR under preparation. Solan Chilla Km.0/0 to 4/0. 308 Solan 2020-21 C/O road from Jounaji to II Manuscript DPR under preparation. Solan Diyarag Bukharag Km.0/0 to 4/0. 309 Kasauli 2019-20 Improvement or Strengthening II Manuscript DPR under scrutiny in Kasauli of Sukhijori kanda Katal-Ka- Zonal office. Bag road Km.0/0 to 15/500. 310 Kasauli 2020-21 Improvement & widening of I U/P in field office. Kasauli Gharkhal-Subathu road. 311 Kasauli 2020-21 Improvement & Widening of II DPR in manuscript shape sent to Chief Kasauli Lohanji to Mari-Ka-Ghat road Officevide this office letter No-10372- Km.0/0 to 13/200. 74 dated-16.02.2021 for Rs.900.00 Lakh. 312 Pachhad 2017-18 CD/MT on Banalag-Dhamesha- I DPR in manuscript shape of Rs. Kasauli Panjpir road. 1046.86 lacs checked by CE (SZ) & being faired out by the Divisional office. 313 Pachhad 2018-19 CD/MT on Naina-Tikker-Janot II U/P in field office. Rajgarh road. 314 Pachhad 2019-20 Up-gradation & strengthening II DPR checked under CUCPL DRRP-II Rajgarh of Neripul-Pulwahal road and fair DPR was submitted for Km.0/0 to 17/00. approval from STA Hamirpur . But couldn`t be approved. 315 Nahan 2017-18 C/O bridge over Markanda II Manuscript estimate amounting to Nahan Nadi on NH-7 to via Bankla to Rs.1279.31 lacs sent to SE Nahan on Rakhni road including MT and dated 13/09/2018 for fairing out. CD. 316 Nahan 2018-19 MT & CD on Kanyoun Ghat to I DPR in manuscriupte shape checked Nahan Ser Reshla to Gopatiya to Siyun for Rs.2129.69 lakhs vide C.E(SZ) Pudla to Ser Badoun to Sanoga office letter No.PW-P-Cell-NABARD- Bhagdat to Rain Kun Arawali DPR(SZ)-12th Circle/2019-20-4029 to Balak Bratal to Bendali road dated 21-01-2020. Fair out DPR still upto Main road. awaited from division office after necessary corrections.

317 Nahan 2018-19 C/O road from village III Tender floated under MMGSY. Paonta Doiyanwala to Village Ghunglon & Village Tokyon alongwith C/O Bridge at Bata Nadi (Substituted on dated 23/05/2020). 318 Nahan 2019-20 C/O CD/MT road Vailli Aayran I Preliminary estimate for Rs.367.85 Paonta Pul to Shamshanghat , GP. lakhs submitted to C.E(S Dholakuwan i/c Bridge (Substituted on dated 23/05/2020). 319 Nahan 2019-20 C/O CD,MT road Kolanwala II U/P in field office. Nahan Bhood to Neemwali, Kolanwal Bhood to Kotdi, Nairo, Kolanwala Bhuood to Khanda, Bohrlighat i/c bridge. 320 Nahan 2019-20 C/O CD, MT road Kollar i/c III DPR under preparation in Divisional Paonta bridge. office. 321 Nahan 2020-21 C/O bridge over Roon Khad on III Preliminary estimate for Rs.847.04 Nahan link road Bhogpur Simbalwala lakhs submitted to C.E(SZ) vide this G.P. Paliyon. office letter No.2738-41 dated 04-12- 2020 for its approval. 322 Nahan 2020-21 C/O Road alongwith CD from IV Survey work complete & Work is in Nahan Village Tib to Via Main road progress under SCSP. Devka.

323 Paonta 2017-18 C/O Single lane bridge over II GAD with hydraulic data under Paonta Bata Nadi between Kiratpur scrutiny in Zonal office. and Toka (substituted on dated 15/06/2020). 324 Paonta 2018-19 C/O link road to Banaur ,Nigali II Total length of the road is about 13.00 Shillai ,Tilaurdhar (Length 8.00 kms). km. SDM Paonta has been requested on 19-09-2019, 03-01-2020 & 12660- 62 dated to get the alignment demarcated. But demarcation is still awaited.Further process can be intiated only after getting the demarcation. 325 Paonta 2018-19 C/O link road Dholidhang I Survey work is in progress Paonta Mandir to village Shamiyala, Gutkhit & upto Ghat total length 5.0Km.(Substituted from MI scheme on dated 08/09/2020). 326 Paonta 2019-20 C/O road village Bhella to II Manuscript estimate of Rs. 491.56 lacs Shillai Kallatha Badana. is under scrutiny in Zonal office. 327 Paonta 2019-20 C/O link road from I Survey work under process at Sub- Shillai Vill.Bhanour-Chcheti Aandhra Division level. & C/O bridge over Toans Khad (Substituted from RWSS scheme on dated 07/11/2019). 328 Paonta 2019-20 C/o link road NH-07 Amargad, I Manuscript estimate of Rs. 469.82 lacs Paonta Johdon Kyarda, Jagapur upto is under scrutiny in Zonal office. IPH Colony Majra (Substituted from MI scheme on dated 16/06/2020). 329 Paonta 2019-20 C/O link road Phoolpur III Survey work under process at Sub- Paonta Panchayat to Bangran, Division level. Suratghar Shivmandir upto Navada near Giri river length 3.00km. (Substituted from MI scheme on dated 08/09/2020). 330 Paonta 2020-21 C/O road from main road II Survey work is in progress at Sub- Paonta Kundiyon to Bhaba Basti, up to division level. villagge Tobha to Khara. 331 Paonta 2020-21 C/O link road Santosh basti III Survey work is in progress at Sub- Paonta near Shiv Mandir Patliyon upto division level. Surajpur, Katta Pathar Khale. 332 Anni 2020-21 M/T Stage-II road from I Total length of this road is 12.405 Nirmand Ranabag to Kandibag upto Kms. FCA approval already received. Baloo. Manuscript DPR stands submitted to the CE(SZ) vide this office letter No- 7545-47 dated 06.11.2020 for Rs. 1001.95 lacs. 333 Lahaul & 2019-20 C/O Karpat bridge. II Hydraulic data is under under Udaipur Spiti scrutinized in Zonal office. 334 Lahaul & 2020-21 Up-gradation on link road to I U/P in field office. Udaipur Spiti Mooring Chowkhang Naingarh road Km.0/0 to 15/200 Teh.Spiti. 335 Lahaul & 2020-21 C/O Tailing Bridge, II Soil testing has been done. Field data Udaipur Spiti GP.Sagnam, Tehsil Spiti. collected and hydraulic data under preparation. 336 Manali 2018-19 C/O Bridge over Manalsu I Hydraulic data prepared. Finalization Manali Nallah Old Manali. of general arangement drawings under process in Zonal office. 337 Manali 2020-21 C/O motorable bridge from I Hydraulic data sent back to Division Manali Police line Bashing to Vamtat Office for obtaining certain Charoodoo. observations. 338 Kullu 2020-21 Improvement & Metalling II Total length of road 4.735km. This Kullu Tarring Chani-Ra-Roohad, road is also appearing in Budget under Braind Deugra Bijli Mahadev. SCSP. 339 Kullu 2020-21 M/T Chilaage Fagu road. IV Manuscript DPR checked from the Kullu Chief Engineer (MZ) HPPWD Mandi on dated 04.02.2021 amounting to Rs.407.61 Lacs only.Fair DPR is under preparation in Divisional Office. 340 Kullu 2020-21 MT & Upgradation of Doogilag V Manuscript DPR checked from the Kullu Dupkan road. Chief Engineer (MZ) HPPWD Mandi on dated 04.02.2021 amounting to Rs.529.48 Lacs.only.Fair DPR is under preparation in Divisional Office. 341 Banjar 2020-21 C/O road from Tattapan to I U/P in field office. Banjar Khoohan , Salounu & Jagala to Dhameuli. 342 Banjar 2020-21 C/O road from Chani Aage to II U/P in field office. Banjar Pigrang, Ukhldhin, Korpudhar- Maithig, Aaisa Bhatrang up to Nanja & C/O road from Udsoo Naal to upto vilage Udsoo. 343 Karsog 2017-18 C/O Kheel Pangna road Km.0/0 II U/P in fielf office. Karsog to 12/0 (Substituted on dated 03/01/2020. 344 Karsog 2018-19 Bhanthal-Punni road Km.0/0 to II Manuscript DPR under scrutiny in Karsog 4/00 (Substituted on dated Zonal office. 30/12/2019). 345 Karsog 2020-21 C/O road from Shilah to Thrmi Alignment yet to be finalized. Karsog via Pokhi. 346 Sunder 2020-21 C/O M/T road from Jabal to II DPR under preparation. Sunder Nagar Luhnu via Badaon Km.0/0 to Nagar 3/345. 347 Nachan 2017-18 C/O road from Palouta to III DPR under scrutiny in E-in-C office. Gohar Sayanji i/c motorable bridge over Kansa Khad. 348 Nachan 2017-18 C/O road Sarda to Nagadhar via IV The dispute has been arised at starting Gohar Bunala, Sarad, Ghnaidi Shil point of road, people are not ready to Nallah, Kandhi, Munakhad, donate land. Kathla, Khanyarloo Dehra Seri & Nagadhar (Substituted on dated 23/05/2017). 349 Nachan 2017-18 C/O road from Devigad to VI U/P in field office. Gohar Sanhi Shikari. 350 Nachan 2019-20 C/O road from Sianj to Nandi. Stage-I completed, Stage-II DPR is Gohar under preparation. 351 Seraj 2017-18 C/O Motorable road Saroa- III Proposed for substitution. Seraj Jhoat-Khuan-Gudah-Patkari. 352 Seraj 2020-21 Improvement and Upgradation II Manuscript DPR is being fair out by Seraj of road from Khouli, Reshan, the Divisional level. Bhalwar, Boong, Teh.& Distt. Mandi. 353 Joginder 2019-20 C/O road Chontda Chakli, II DPR amounting to Rs. 330.92 lacs is Joginder Nagar Marehad Dohag i/c C/O bridge under process in Zonal office. Nagar over Bajgar Khad. 354 Joginder 2020-21 C/O & MT of Panjalog-Kanarg- II Alignment finalized road constructed Joginder Nagar Fagla-Slahan Dhar road. under state head Km. 5.00.DPR under Nagar prepration. 355 Mandi 2017-18 C/O road NH Dhar to Uparli IV DPR amounting to Rs 446.75 lacs in Mandi Sooradi Chatred(GP Uparli manuscript shape checked by CE (MZ) No.II Sarvadi). on dt 22-12-2020 and being faired out. 356 Mandi 2020-21 M/T Nagrehad to Taryasal I DPR under preparation for Stage-II. Mandi Km.0/0 to 3/500. No.II 357 Mandi 2020-21 M/T Kushwahda, Samrahan III DPR under preparation for Stage-II. Mandi Dandal via Middle School No.II Dadni-Ri-Gahri road. 358 Sarkaghat 2017-18 C/O road Jamsai-Jhijdu-Bagi- II U/P in field office. Dharampu Ropdi-Banehardi-Rachot- r Sandoa-Dharjol upto to Chowk. 359 Sarkaghat 2017-18 C/O road Prasdda-Radoo- III Alignment yet to be finalised. Dharampu Paplog-Samsai upto Damseda. r 360 Sarkaghat 2017-18 M/T on Trifalghat Badoun, IV DPR under preparation. Sarkaghat Bhatera, Thana Chowki road Km.0/00 to 10/00 (Substituted on dated 27/10/2020). 361 Sarkaghat 2018-19 C/O Sarkaghat Khalard via I Manuscripit DPR submitted to Chief Sarkaghat Lukanu & Surjpur Bari Engineer (MZ) by SE Mandi on dated Barswad road. (Scheme given 6.2.2021 for Rs.524.06 Lakh. by MLA in place of WSS Scheme). 362 Sarkaghat 2018-19 C/O 30.00mtr.span Box Girder II Working drawing prepared. DPR under Sarkaghat Bridge over Bharnal Khad at prepeartion in Divisional office. Bharnal on Bharnal Nalah-Ra- Gehra Kolni road at Rd.0/015 (Substituted on dated 07/12/2019). 363 Sarkaghat 2019-20 C/O bridge over Kalthari Khad III DPR submitted to CE (MZ) by SE 1st Sarkaghat between Tikkri-Gaihra Bhadrol. circle HPPWD Mandi dated 5-10-2020 amounting to Rs.276.95 lacs only. DPR has been submit to EE for fair out. 364 Sarkaghat 2020-21 MT road Amla Galoo- I U/P in field office. Sarkaghat Andhrada-Harvan Km.6/0 to 8/500 including bridge over Kalthri Khad. 365 Jaisingpur 2017-18 C/O Balance work Naddli II DPR for balance work is under Jaisinghpu Gharchindi, Malli road preparation in Divisional office. r (Substituted on dated 23/10/2020). 366 Jaisingpur 2019-20 C/O link road Village Umbar I DPR is under preparation in Division Jaisinghpu i/c bridge over Salyani Khad. office. r 367 Baijnath 2017-18 C/O link road from Kumardha II Manuscripte DPR returned to Circle Baijnath toMadho Nagar (Substituted on office because the area of this DPR dt.14/07/2020). has been shiftted to Mandi zone 368 Indora 2017-18 C/O road from Chabbi to II Hydraulic data under preparation in Indora Kharad via Majra & Chakki Divisional office. Khad i/c C/O bridge over Naluan Nehar. 369 Indora 2019-20 C/o Motorable Bridge at Tara I U/P in field office. Indora Khad on link road to Indpur village (Substituted on dated 20/11/2020). 370 Indora 2019-20 C/O link road to Village II Manuscript DPR prepared in Division Indora Traiyah Chamaran (Substituted office & will be submitted shortly. on dated 25/07/2019). 371 Indora 2020-21 C/O road from matoli to Ram I Site finalized Hydraulic data prepared Indora Nagar i/c bridge over Malah- by Division office & DPR under Ri-Khad Km.0/0 to 5/00. preparation in Division office. 372 Jawali 2019-20 C/O Bridge over Dehar Khad II Manuscript DPR under scrutiny in Jawali i/c Rajol Anuhi Jangal Bagga Zonal office. road (Substituted on dated 20/11/2020). 373 Jawali 2020-21 C/O link road from Banoli to I Manuscript DPR sent to CE (KZ) Jawali Bhati-Dugloo-basa-Kotha- HP:PWD. Dharmshalavide by SE Harnera. HP:PWD. 9th Circle dated 09.09.2020 for Rs. 791.85 Lacs only . 374 Jawali 2020-21 C/O bridge over Nyal-Jhalu- II DPR amounting to Rs. 697.87 lacs is Jawali Buhalkhand i/c road. being faired out by the Divisional office. 375 Dehra 2018-19 C/O road from Tutru Dehra I DPR prepared, but returned by SE with Dehra Bharwain road via Bhangnouria some observations which is being Choudhary & Harizan Basti up attended in Divisional office. to GPS Bharwara (Pragpur Sub- Division) (Substituted on dated 30-11-2019). 376 Dehra 2019-20 C/O road Dhar to Dhagad & I Fair DPR amounting to Rs. 613.30 Dehra Lunsoo. under process in Chief Engineer( K.Z) 377 Dehra 2020-21 C/O road from Gambhirpur to I Alignment not yet finalized. Dehra Ludret to Sakri. 378 Dehra 2020-21 C/O road from Badhal Bridge II Alignment not yet finalized. Dehra to Jambal Bassi RD via Kanol & Pinniamal.

379 Jaswan 2017-18 C/O Bani to Pragpur via III Manuscript sent to DPR under process Kotla Pragpur Dangra Sidh including in Chief Engineer( K.Z) Behar 2No.bridges. 380 Jaswan 2017-18 C/O Bharwaini to village IV U/P in field office. Alignment being Kotla Pragpur Bhadyali road. finalized. Behar 381 Jaswan 2018-19 C/O road from Pucca Bharoh to I DPR in manuscript shape amounting to Kotla Pragpur (At Chanour Tayamal Shitla Rs. 120.26 lacs received on 5-2-2021 Behar road) Lower Sawana km. 0/0 & under process in Circle office. to 2/600. 382 Jawalamu 2017-18 C/O link road Balara to Kud via I Returned to S.E. 9th Circle Nurpur with Dehra khi barala Tihri with link road to observations n 11-2-2021 village Parountha (Substituted on dt.06/10/2020). 383 Jawalamu 2017-18 C/O road from Dhatehar II Manuscript DPR under preparation in Dehra khi Mahrana Duhak road in Km.0/0 Division office. to 6/310 (Substituted on dated 15/07/2020). 384 Sulah 2017-18 C/O road from Mahlag to I DPR is being faired out by the Dehra Malahu in GP Malahu & C/O Divisional office. motorable bridge over Moul Khad. 385 Sulah 2017-18 C/O Duhak Tikkri Rakha Basti V U/P in field office. Bhawarna to Dhabi road (Length 5.00Km.) (Substituted on dated 07/12/2020). 386 Sulah 2018-19 C/O Link road Kharouth to I U/P in field office. Bhawarna Kabrian to Nath Basti i/c Bridge over Tahal Khad km. 0/0 to 3/0. 387 Sulah 2019-20 C/O road Thatru-Thare to I DPR under preparation in Divisional Bhawarna Bhaitilu i/c bridge over Bhatlu office. Nallah. 388 Sulah 2020-21 C/O balance work on Henjha to II Manuscript DPR under process in C.E Bhawarna Bhawarna via Garla Dai up to ( K.Z). swargiain road i/c 2No.bridges over Soon Khad. 389 Nagrota 2017-18 C/O Sarotari Uprehar to Jamula II DPR returned back with observation on Tanda Bagwan Kalaban Pattari Sunhi Shaheedi dated 11/01/2021 to S.E. 5th by C.E. Marg road Km.0/0 to 11/0 i/c (KZ). 1No.bridge (Substituted on dated 08/11/2018). 390 Nagrota 2018-19 C/O Sarotri Mangrela Luhana I Hydraulic data under process in C.E Tanda Bagwan Badoh Gadrana i/c bridge over (K.Zone) Drawing Cell . Bathu khad. 391 Nagrota 2018-19 C/O Bridge over Daroo Khad II DPR amounting to Rs. 286.24 lacs is Tanda Bagwan alongwith both side approaches under scrutiny in Zonal office. to connect the village Kaled to Karali- Ka-Bag. 392 Nagrota 2019-20 C/O Rangehar Sadoon Malmu I Manuscript DPRs under process Zonal Tanda Bagwan to Nera roads i/c bridge over office Nera Khad (Substituted on dated 16/12/2019). 393 Nagrota 2020-21 C/O balance work & Imp.of II The DPR Submitted for Rs. 282.74 lacs Tanda Bagwan Tang Uthragran Sihund Baldhar under scrutiny in E-in-C office. road Km.0/0 to 4/360 (Substituted on dt.06/10/2020). 394 Kangra 2018-19 Tiara to Kangra via Shamirpur I Survey work completed . Manuscript Kangra Khas, Tiara Dehrian Kapparia, DPR is being sent to Circle office. Upper Tiara Dehrian & Kalka Mandir km. 0/0 to 12/290 (Substituted on dated 03/02/2020). 395 Kangra 2019-20 Imp. & widening of Ichhi to I Manuscript DPR under process in Kangra Pehag via Doadan Tyali Zonal office for Rs. 654.67 lacs only. Abdullapur, Manjhi khad bridge upto Bhown Kangra km. 0/0 to 9/0 (Substituted on dated. 03/02/2020). 396 Kangra 2020-21 Improvement & Widening of I Manuscript DPR under process in Kangra Dehra Arla, Gabla Andrad Chief Engineer (KZ) Dharamshala Tarsuh, Lalehad, Virta Jogipur Ujjain Sevkara Natehad road Km.0/0 to 12/900. 397 Shahpur 2018-19 C/O link road from Gadapa to I Survey work completed. Kangra Lower Lanjot Damosti Basti km. 0/0 to 2/0 including bridge 13.75 mtr. span. 398 Shahpur 2018-19 C/O Link road from Thulla II Manuscript DPR under scrutiny in Kangra basti to Boie i/c 60.00mtr.span Zonal office. bridge. 399 Shahpur 2019-20 C/O road from village Lanjhani II U/P in field office. Kangra to village Nargeta Km.0/0 to 1/885 (Substituted on dt.22/06/2019). 400 Shahpur 2020-21 C/O link road Laleta to Vannu I Manuscript DPR amounting to Rs. Kangra Mahadev, Dhanotoo & C/O 940.26 lacs under process in Zonal bridge over Chambi Khad. office. 401 Shahpur 2020-21 C/o road from Ghera road to II Manuscript DPRunder process in this Kangra Diyara, Bhitri & Varnet. office . 402 Dharamsh 2017-18 C/O Hiroo Dashalan road II DPR in manuscript shape of Rs. 503.90 Dharamsh ala (Km.0/0 to 4/0) upto village lacs is under scrutiny in Zonal office. ala Gamroo & Cholla & C/O bridge over Churan Khad. 403 Dharamsh 2018-19 C/O bridge over Bahal Khad & I Hydraulic data under scrutiny in Zonal Dharamsh ala M/T link road to village Bahal. office. ala 404 Dharamsh 2019-20 C/O link road from Ward No.4 I Manuscript DPR returned to Circle Dharamsh ala & 5, G.P. Kand Kardiyana. office with observation by Chief ala Engineer (KZ) HP.PWD Dharmshala dt. 23.01.2021 . 405 Palampur 2019-20 C/O link road from GPS I Manuscript DPR under process in C.E Palampur Ghamrota-Balalan-Bhont-Arti (K.Z) . i/c bridge over Lingti Khad (Substituted on dated 27/11/2019). 406 Palampur 2019-20 C/O road from Patti to Gorat II Manuscript DPR under process in C.E Palampur (GP.Rajpur) via Harijan and (K.Z) . Gujjar Basti Badehar and Panchayat Ghar Badehar. 407 Palampur 2020-21 Upgradation of Kulani- II Manuscript DPR amounting to Palampur Chandpdur-Bharmat Colony- Rs.666.50 lacs only is being fair out Kamakhya Mandir-National by the concerned division. Highway Holta-Simblu-Patti road. 408 Churah 2017-18 C/O Tissa Satmas road bridge I Hydraulic data prepared . Tissa constuction at Tarvai. 409 Churah 2017-18 C/O link road from Aniuda to II Alignment finalized & forest case is Tissa Bhanodi via Malli Kundi i/c being prepared & uploaded online. bridge over Trell Nallah Presently forest case pending with (Substituted on dt.19/08/2019). Nodal Officer Shimla. 410 Bharmour 2017-18 C/O Lahal Bagaru road II DPR under preparation. Bharmour (Substituted on dt.20/07/2019). 411 Bharmour 2019-20 C/o road from Hadsar to II DPR under preparation. Bharmour Serkaw i/c bridge over Bhel Nallah. 412 Chamba 2017-18 Metalling/Tarring of Kandu II Manuscript f DPR under process in Chamba Panjoh road (Upper Panjoh) Chief Engineer( Kangra Zone ) Km.0/0 to 3/560 (Substituted on dated 08/07/2020). 413 Chamba 2018-19 Metalling/Tarring of Kandu II Manuscript f DPR under process in Chamba Panjoh (lower Panjoh) road Chief Engineer( Kangra Zone ) Km.0/0 to 3/460 (Substituted on dated 08/07/2020). 414 Dalhousie 2018-19 Link road from Lohani to Kilod I Manuscript f DPR under process in Salooni under PWD Division Salooni. Chief Engineer( Kangra Zone ) 415 Dalhousie 2019-20 C/O 120.00mgtr.motorable I Hydraulic date for C/O bridge has been Salooni bridge over river Siul between collected & is being prepared. DPR Sundla & Koti. shall be prepared on finalization of design of bridge. 416 Dalhousie 2019-20 C/o balance work of II DPR of the road is being prepared in Dalhousie Dalhousie/Talai road in Divisiona office . HPPWD Division Dalhousie. 417 Dalhousie 2020-21 Improvement & Metalling II Manuscript DPR under Process in Dalhousie Tarring of link road to village Chief Engineer(K.Z) Sakrera. 418 Bhatiyat 2017-18 C/O balance work including I DPR under preparation in Divisional Dalhousie M/T of Raipur to Fagot road Office Km.0/0 to 6.750 (Substituted on dated 24/12/2020). 419 Bhatiyat 2018-19 C/O road from Basoldha to I This road has been proposed for Dalhousie Sukiyada via Khadander, substitution for C/O Link road from Draman, Bagga i/c bridges. Dugred to Naloh via Pukhred km 0/0 to 6/300 vide Hon'ble MLA of Bhattiyat Constituency Sh. Bikram Singh Jaryal vide letter No. Nil dated 9-12-2020. 420 Bhatiyat 2018-19 C/O balance work including II DPR under preparation in Divisional Dalhousie M/t of link road Patka to Office hathidhar Km.0/0 to 10/400 (Substituted on dt.24/12/2020). 421 Bhatiyat 2020-21 C/O Balance work inluding I DPR under preparation in Divisional Dalhousie M/T of Kakira to katloo road Office Km.0/0 to 6/500 (Substituted on dated 24/12/2020). 422 Dharamp 2017-18 C/O road Hayolag-Pangoh- I FRA got approved recently & DPR Dharampu ur Kanda Pattan. preparation under Sub-Divn.office. r 423 Dharamp 2019-20 C/O Bridge from Brang to Riur III Hydraulic data received & structural Dharampu ur over Kindri Khad. Drawings are under preparation in r Circle office. 424 Dharamp 2019-20 C/O Bridge on Barchhwad I U/P in field office. Sarkaghat ur Bakrta road (Substituted from MI Scheme on dated 18/01/2020). 425 Dharamp 2020-21 C/O road from Saklana- I Under process in Sub-Divnl.level. Dharampu ur Khanoud-Bhaletoo-Kaltri. r 426 Dharamp 2020-21 C/O bridge over Seer Khad. II U/P in field office. Sarkaghat ur 427 Dharamp 2020-21 C/O bridge over Paplog on III Hydraulic data received and structural Dharampu ur Redu road. drawings are under preparation in r Circle office.

428 Ghumarw 2017-18 Up-gradation of Lethwin to II DPR in manuscript is under process in Ghumarwi in Lanta-Bela road Km.0/00 to Circle office. n 3/400 (substituted on dated 07/03/2020). 429 Ghumarw 2018-19 C/O Link road from Dangar- I Manuscript DPR under scrutiny in Ghumarwi in Chokhna to Village Dhaloh-Jol- Circle office. n Dakhyoda School upto Hamirpur Boundary i/c bridge over Sukkar khad. 430 Ghumarw 2018-19 C/O Link road from NH -103 to II Manuscript DPR under scrutiny in Ghumarwi in village Bhagdwan, lalwan, Circle office. n Lethavi i/c bridge over Rohal khad. 431 Ghumarw 2018-19 C/O bridge over Seer Khad i/c IV Hydraulic data under process in Circle Ghumarwi in approaches on Kot-Tagiar-Jahu office. n road at RD.2/00(Substituted on dated 07/03/2020). 432 Ghumarw 2020-21 C/O road Ghumarwin to Tikker I Manuscript DPR is under process in Ghumarwi in Silh via Marohal, Soi, Ropri. Division level. n 433 Bilaspur 2017-18 C/O Dharwara Daloli Chharal I DPR under preparation in Sub- Bilaspur Talwara road (Substituted on Divnl.level. No.I dated 07/10/2020). 434 Bilaspur 2020-21 Improvement & widening of I DPR under process in Circle office. Bilaspur Sakroha, Manjhwar, Jablyana, No.I Sohar road. 435 Bilaspur 2020-21 C/O road from Dharbada, II DPR under preparation in Sub- Bilaspur Dharbyan to Halwari & C/O Divnl.level. No.I road from Bairi Rajadiyan to Changroo via Judani. 436 Shri 2020-21 C/O link road Janali, Kyariyan, I Survey process is in progress. Bilaspur Naina Bharsda to Maloun GP. No.II Devi Ji Tarwad.

437 Shri 2020-21 C/O link road Noa to Sai II Survey process is in progress. Bilaspur Naina Kanaita, Sai Bharaman i/c C/O No.II Devi Ji bridge over Gambhrola Khad. 438 Bhoranj 2017-18 C/O road from village Joh to II DPR under preparation in Circle level. Bhoranj village Chamboh via ward No.4 in village Chamboh alingwith 2No. Bridges. 439 Bhoranj 2020-21 C/O link road Badhani, I DPR under preparation in Circle level. Bhoranj Nagrotta, Lajhyani, Kalyal, Bahanwin RSSB Bhawan i/c bridge. 440 Sujanpur 2017-18 C/O link road from Sainuan II DPR under preparation in Sub-Division Touni Thathi via Nichla-Manjhla office. Devi Bherda to Bherda Km.0/0 to 4/0 (Substituted on dated 23/07/2018). 441 Sujanpur 2017-18 C/O Ansla to Soud up to Pung III Sanctioned for Rs.419.69 lacs under Touni Khad in Km.0/0 to 4/015 RIDF-XXV. Work is in progress. Devi (Substituted on dated 5/6/2018). 442 Sujanpur 2018-19 C/O & M/T on Bajrol-Lamber- II DPR prepared manuscript shape being Touni Chamarda road ( G.P. Bajrol). scruitized in Division office. Devi 443 Sujanpur 2020-21 C/O link road Tapaldhar to I DPR under preparation in Sub-Division Touni Bjaher via Patiyal basti. office. Devi 444 Hamirpur 2017-18 C/O road from Village Fafan to I DPR is under process in Division office Hamirpur G.P. Ukhali. for fairing out. 445 Hamirpur 2017-18 C/O Khatvin-Lingvi road i/c II DPR is being fairout by the Division Hamirpur bridge over Shukkar Khad near office by Dalyahoo. 446 Hamirpur 2019-20 Widening & Improvement of I DPR under scrutiny in E-in-C office. Hamirpur Hamirpur Galore road Km.0/0 to 18/0. 447 Hamirpur 2019-20 Widening & Improvement of II DPR is being fairout by the Division Hamirpur Kudhiar Masiana road Km.0/0 office to 12/0. 448 Nadaun 2017-18 C/O road Pathriyan(Lachruhi)- II DPR for Rs.175.21 lacs is under Hamirpur Tikroo Barota-Chodoo scrutiny in circle office. Kandrola-Rangas. 449 Nadaun 2020-21 C/O road including bridge from I U/P in field office. Barsar Kuthera Chowk-Ropa, GP.Sareri. 450 Chintpurn 2017-18 C/O & MT of link road village I There are different branches of this Bharwain i Panglu to Mairi via Meosh, road & land is not available on all the Gawalsar, Snow including One branches. However the work under Bridge. State Head has been taken up in portion Gawsalasar Sanoh on which the land is available. Hence the DPR is not required for the road. 451 Chintpurn 2018-19 C/O & MT Shaheed Amol I Survey work of road has been Bharwain i Kalia Basti Chintpurni to Kinnu completed. Design work of one via Raida paida Duhal No.Bridge coming in the road Bangwalan road including alignment is under process in bridges (Substituted on dated Divisional office. 04/01/2019). 452 Chintpurn 2020-21 C/O 2No.bridges over Khai I U/P in field office. Bharwain i Khad and Kotli Khad on link road Kinnu to Guret (Substituted on dated 11/02/2021). 453 Gagret 2017-18 Up-gradation/ Improvement of I 4Nos.Hydraulic data under process in Bharwain link road Guglehad to Kaloh Zonal office. via Upper Kutheda Jaswala Mawa sidhiya tatehda, Oayal, Badoh road km.0/0 to 16/500 i/c 4No. bridges. 454 Gagret 2017-18 C/O Bridges on Gagret II U/P in field office. Bharwain Daulatpur road on Deoli Khad- I, Deoli Khad-II, Ghanari Khad, Chalet Khad-I and Chalet Khad-II (Substituted on dated 11/02/2021). 455 Gagret 2018-19 Improvement/widening/strength I DPR in manuscript shape amounting to Bharwain ening on Gagret Oel Ispur road Rs. 652.26 lacs is under scrutiny in at Kaloh to Shivwari, Ambota, Chief Engineer (HZ). Dhawali upto NH-3 km. 0/0 to 12/500 i/c bridge over Shivwari khad. 456 Gagret 2020-21 Const.& Metaling on link road II DPR under scrutiny in Circle office. Bharwain Raipur to Bkhana via Mallan Da-Pind Km.0/0 to 4/0. 457 Haroli 2018-19 C/O road from Gondpur Behli I Survey under process Una to Bathu Gurplah i/c bridge over Gondpur Jaichand Khad. 458 Haroli 2019-20 C/O & MT of link road Labana I DPR in manuscript shape under Una Basti, Ispur to Dera Baba process in Zonal office. Bharthari (Damanian, GP Ispur). 459 Haroli 2020-21 C/O road from Baba charange I Survey work is in progress. Una Nath Ashram to Pubjab Border Jaijon via Tibian & widening of Janani Polia road and C/O bridges over polian & Pubowal roads. 460 Haroli 2020-21 C/O road fromLowe panjawar II Survey work is in progress. Una covering Saini Muhalla, Dhakki Muhalla up to Daulatpur link road & Nagdoli Petrol Pump via ward No.5 up to Shiv Mandir Panjawar & Maadu Ki Nihali se Madan-Ka-Ghar tak village Panjawar. 461 Una 2018-19 C/O New link road from II DPR in manuscript shape under Una Lalsinghi (Via Baba Beli Ram) process in Circle office. to Jhalera near Brick Kiln. 462 Una 2020-21 Improvement & Strengthening I Survey work is in progress. Una of link road to village Malahat & Mohalla Dehrian Km.0/0 to 3/600 & C/o ring road throughout outer area of Una City from Rakkar to Jhalera. 463 Una 2020-21 Improvement & strengthening II Survey work is in progress. Una of Mehatpur to santoshgarh via Basdehra Km.0/0 to 7/200. 464 Kutlehar 2018-19 C/O & M/Link road from I Bridge designed & DPR under Bangana Dhamandari Bus Stand to preparation. Dhamandari Devi Mandir via Rajputtan & Harizan Basti i/c 2 Nos Bridges i.e. Bridge over Sanjhot Khad-II & Bridge over Barnah Khad. 465 Shimla 2018-19 C/O link road from Golpahari I Being a urban area can not be funded Shimla Annadale to Village Behar under NABARD Project. No.I Annadale. 466 Shimla 2018-19 C/O Link road from Mist II Being a urban area can not be funded Shimla Chamber Khalini to BCS. under NABARD Project. No.I