The Reform of the Electricity Sector in Uganda
Total Page:16
File Type:pdf, Size:1020Kb
Load more
Recommended publications
-
Buikwe District Economic Profile
BUIKWE DISTRICT LOCAL GOVERNMENT P.O.BOX 3, LUGAZI District LED Profile A. Map of Buikwe District Showing LLGs N 1 B. Background 1.1 Location and Size Buikwe District lies in the Central region of Uganda, sharing borders with the District of Jinja in the East, Kayunga along river Sezibwa in the North, Mukono in the West, and Buvuma in Lake Victoria. The District Headquarters is in BUIKWE Town, situated along Kampala - Jinja road (11kms off Lugazi). Buikwe Town serves as an Administrative and commercial centre. Other urban centers include Lugazi, Njeru and Nkokonjeru Town Councils. Buikwe District has a total area of about 1209 Square Kilometres of which land area is 1209 square km. 1.2 Historical Background Buikwe District is one of the 28 districts of Uganda that were created under the local Government Act 1 of 1997. By the act of parliament, the district was inniatially one of the Counties of Mukono district but later declared an independent district in July 2009. The current Buikwe district consists of One County which is divided into three constituencies namely Buikwe North, Buikwe South and Buikwe West. It conatins 8 sub counties and 4 Town councils. 1.3 Geographical Features Topography The northern part of the district is flat but the southern region consists of sloping land with great many undulations; 75% of the land is less than 60o in slope. Most of Buikwe District lies on a high plateau (1000-1300) above sea level with some areas along Sezibwa River below 760m above sea level, Southern Buikwe is a raised plateau (1220-2440m) drained by River Sezibwa and River Musamya. -
The Least Cost Generation Plan 2016
THE LEAST COST GENERATION PLAN 2016 – 2025 EXECUTIVE SUMMARY In 2013, the Authority developed a 5 year Least Cost Generation Plan (LCGP) that covered the period 2013 to 2018. An update of the LCGP has been undertaken covering a 10 year period of 2016 to 2025. The update involved review of the load forecast in light of changed parameters, commissioning dates for committed projects, costs of generation plants, transmission and distribution system investment requirements. In the update of the plan, similar to the Power Sector Investment Plan, prepared by the Ministry of Energy and Mineral Development, the ”Econometric Demand” forecasting method was used at distribution level to forecast Commercial, Medium Industry and Large Industry customer category demand. A bottom up approach was used for Domestic customer category using the end-user method. A Base Case, Low Case and High Case scenario were developed for sensitivity analysis. The resultant demand forecast was 6.5%, 3.6% and 12% growth rate in energy demand for the Base Case, Low Case and High Case scenarios respectively. This growth rate is lower than the projection in the 2013 LCGP of 10%, 5% and 14% for Base Case, Low Case and High Case respectively. A number of energy supply options were considered including Hydro, Peat, Solar PV, Bagasse Cogeneration, Wind and Natural Gas. The planned supply considered already existing, committed and candidate generation plants/projects with their estimated commissioning dates aligned. We note that more than 80% of the generation will come from hydro. 1 In the demand supply balance, Figure E1 shows the demand and supply balance over the planning period. -
IGG Report 2017.Indd
THE REPUBLIC OF UGANDA BI-ANNUALBI-ANNUAL INSPECTORATE INSPECTORATE OF GOVERNMENTGOVERNMENT PERFORMANCEPERFORMANCE REPORT REPORT TOTO PARLIAMENTPARLIAMENT JANUARY - JUNE 2017 MandateMandate To promote just utilization of public resources VisionVision A responsive and accountable public sector MissionMission To promote good governance, accountability and rule of law in public offfice CCoreore ValuesValues Integrity Impartiality Professionalism Gender Equality and Equity INSPECTORATE OF GOVERNMENT BI-ANNUAL INSPECTORATE OF GOVERNMENT PERFORMANCE REPORT TO PARLIAMENT JANUARY – JUNE 2017 THE LEADERSHIP OF THE INSPECTORATE OF GOVERNMENT Justice Irene Mulyagonja Kakooza Inspector General of Government Ms. Mariam Wangadya Mr. George Bamugemereire Deputy Inspector General of Deputy Inspector General of Government Government Ms. Rose N. Kafeero Secretary to the Inspectorate of Government THE INSPECTORATE OF GOVERNMENT Jubilee Insurance Centre, Plot 14, Parliament Avenue P.O. Box 1682 Kampala, Uganda General Lines: 0414-255892/259738 z Hotlines: 0414-347387/0312-101346 Fax: 0414-344810 z Email: [email protected] z Website: www.igg.go.ug Facebook: Inspectorate of Government z Twitter: @IGGUganda YouTube: Inspectorate of Government OFFICE OF THE INSPECTOR GENERAL OF GOVERNMENT Inspector General of Government Justice Irene Mulyagonja Kakooza Tel: 0414-259723 z Email: [email protected] Deputy Inspector General of Government Deputy Inspector General of Government Mr. George Bamugemereire Ms. Mariam Wangadya Tel: 0414-259780 Tel: 0414-259709 Email: [email protected] Email: [email protected] Department of Finance and Administration: Secretary to the Inspectorate of Government Undersecretary Finance and Administration Ms. Rose N. Kafeero Ms. Glory Anaƾun Tel: 0414-259788; Fax: 0414-257590 Tel: 0414-230398 Email: [email protected] Email: [email protected] Information and Internal Inspection Division Public and International Relations Division Head of Division: Mr. -
E464 Volume I1;Wj9,GALIPROJECT 4 TOMANSMISSIONSYSTEM
E464 Volume i1;Wj9,GALIPROJECT 4 TOMANSMISSIONSYSTEM Public Disclosure Authorized Preparedfor: UGANDA A3 NILE its POWER Richmond;UK Public Disclosure Authorized Fw~~~~I \ If~t;o ,.-, I~~~~~~~ jt .4 ,. 't' . .~ Public Disclosure Authorized Prepared by: t~ IN),I "%4fr - - tt ?/^ ^ ,s ENVIRONMENTAL 111teinlauloln.al IMPACT i-S(. Illf STATEME- , '. vi (aietlph,t:an,.daw,,, -\S_,,y '\ /., 'cf - , X £/XL March, 2001 - - ' Public Disclosure Authorized _, ,;' m.. .'ILE COPY I U Technical Resettlement Technical Resettlement Appendices and A e i ActionPlan ,Community ApenicsAcinPla Dlevelopment (A' Action Plan (RCDAP') The compilete Bujagali Project EIA consists of 7 documents Note: Thetransmission system documentation is,for the most part, the same as fhat submittedto ihe Ugandcn National EnvironmentalManagement Authority(NEMAI in December 2000. Detailsof the changes made to the documentation betwoon Dccomber 2000 and the presentsubmission aro avoiloblo from AESN P. Only the graphics that have been changed since December, 2000 hove new dates. FILE: DOChUME[NTC ,ART.CD I 3 fOOt'ypnIp, .asod 1!A/SJV L6'.'''''' '' '.' epurf Ut tUISWXS XillJupllD 2UI1SIXg Itb L6 ... NOJIDSaS1J I2EIof (INY SISAlVNV S2IAIlVNTIuaJ bV _ b6.sanl1A Puu O...tp.s.. ZA .6san1r^A pue SD)flSUIa1DJltJJ WemlrnIn S- (7)6. .. .--D)qqnd llH S bf 68 ..............................................................--- - -- io ---QAu ( laimpod u2Vl b,-£ 6L ...................................... -SWulaue lu;DwIa:43Spuel QSI-PUU'l Z btl' 6L .............................................----- * -* -SaULepunog QAfjP.4SlUTtUPad l SL. sUOItllpuo ltUiOUOZg-OioOS V£ ££.~~~~~~~~~~~~~~~~~A2~~~~~~~~~3V s z')J -4IOfJIrN 'Et (OAIOsOa.. Isoa0 joJxxNsU uAWom osILr) 2AX)SO> IsaIo4 TO•LWN ZU£N 9s ... suotll puoD [eOT20olla E SS '' ''''''''..........''...''................................. slotNluolqur wZ S5 ' '' '' '' ' '' '' '' - - - -- -........................- puiN Z'Z'£ j7i.. .U.13 1uu7EF ................... -
Improving Emergency Care in Uganda a Low-Cost Emergency Care Initiative Has Halved Deaths Due to Emergency Conditions in Two District Hospitals in Uganda
News Improving emergency care in Uganda A low-cost emergency care initiative has halved deaths due to emergency conditions in two district hospitals in Uganda. The intervention is being scaled up nationally. Gary Humphreys reports. Halimah Adam, a nurse at the Mubende countries have no emergency access In Uganda, road traffic crashes are regional referral hospital in Uganda, telephone number to call for an ambu- a matter of particular concern. “Uganda remembers the little boy well. “He was lance, and many countries have no am- has one of the highest incidences of brought into the hospital by his mother,” bulances to call. Hospitals lack dedicated road traffic trauma and deaths on the she says. “He was unconscious and emergency units and have few providers African continent,” says Joseph Ka- barely breathing.” trained in the recognition and manage- lanzi, Senior House Officer, Emergency The mother told Halimah that the ment of emergency conditions. Medicine, Makerere University College boy had drunk paraffin, mistaking it “Over half of deaths in low- and of Health Sciences. “We are faced with for a soft drink. Paraffin (kerosene) is middle-income countries are caused multiple road traffic crashes daily and poorly absorbed by the gastrointestinal by conditions that could be addressed have barely any dedicated emergency tract, but when aspirated, which can by effective emergency care,” says Dr re s p on s e .” happen when a child vomits, it causes Teri Reynolds, an expert in emergency, According to WHO’s Global status lung inflammation, preventing the lungs trauma and acute care at the World report on road safety 2018, road traffic from oxygenating the blood. -
Bujagali Final Report
INDEPENDENT REVIEW PANEL COMPLIANCE REVIEW REPORT ON THE BUJAGALI HYDROPOWER AND INTERCONNECTION PROJECTS June 20, 2008 1 ACKNOWLEDGEMENTS The IRM Compliance Review Panel could not have undertaken and completed this report without the generous assistance of many people in Uganda and at the African Development Bank. It wishes to express its appreciation to all of them for their cooperation and support during the compliance review of the Bujagali Hydropower and Interconnection projects. The Panel thanks the Requesters and the many individuals from civil society and the communities that it met in the Project areas and in Kampala for their assistance. It also appreciates the willingness of the representatives of the Government of Uganda and the projects’ sponsors to meet with the Panel and provide it with information during its visit to Uganda. The Panel acknowledges all the help provided by the Resident Representative of the African Development Bank in Uganda and his staff and the willing cooperation it has received from the Bank’s Management and staff in Tunis. The Panel appreciates the generous cooperation of the World Bank Inspection Panel which conducted its own review of the “UGANDA: Private Power Generation Project”. The Compliance Review Panel and the World Bank Inspection Panel coordinated their field investigations of the Bujagali projects and shared consultants and technical information during this investigation in order to enhance the efficiency and cost effectiveness of each of their investigations. While this collaboration between the Panel and the World Bank Inspection Panel worked to the mutual benefit of both parties, each Panel focused its compliance review on its own Bank’s policies and procedures and each Panel has made its own independent judgments about the compliance of its Management and staff with its Bank’s policies and procedures. -
24-Investigation Report (English)
1 Part One Introduction 2 Chapter 1 The Projects and Their Financing 1. This Report addresses questions concerning three IDA-financed projects in Uganda: namely, (1) the Power III Project, otherwise known as the Owen Falls Extension; the Supplemental Loan to the Power III Project; (2) the Power IV Project, which finances power generation Units 14 and 15, (the latter if economically viable); and (3) the Bujagali Hydropower Project.1 1.1. The Power III Project (Owen Falls Extension) 2. In the mid-1980s, soon after IDA recommenced its involvement in Uganda, a severe deterioration of power infrastructure was identified as a serious obstacle to the revival of the commodity-producing sectors of the economy. In 1988, with IDA’s assistance, the Government began work on the Power III Project. According to the Development Credit Agreement for the Project, its objectives were to: “ (a) assist the Borrower with the continued rehabilitation of the power system in Uganda; and (b) develop its hydroresources and expand the transmission and distribution system, to provide reliable, least-cost energy to Uganda's growing population.”2 The Project provided for: a) “… dam strengthening, construction of a spillway, plant capacity expansion by at least 102MW, and civil works to accommodate a plant capacity of 170MW; b) rehabilitation and expansion of transmission and distribution on the national grid; and c) provision of technical assistance services mainly to the Uganda Electricity Board (UEB) and the Ministry of Energy.” 3 IDA provided a credit of SDR 86,900,000 (about US$125 million) for this work. The projects included the installation of three units (11, 12 and 13) and provided capacity for two additional units in the future. -
Bujagali Energy Limited Project Number
BUJAGALI ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT SUMMARY Project Title: Bujagali Energy Limited Project Number: P-UG-FAB-008 Country: Uganda Department: Energy Financial Solutions, Policy & Regulation Division: Energy Financial Solutions Project Category: 1 1.0 Introduction Bujagali Energy Limited (BEL) is owned by SG Bujagali Holdings Ltd (an affiliate of Sithe Global Power LLC), Jubilee Insurance Company Ltd., as well as the Africa Power Platform PCC, which is owned by CDC (the UK’s Development Finance Institution), the Aga Khan Fund for Economic Development (AKFED) and IPS Kenya (“the Sponsors”). Operations and Maintenance Energy (Uganda) Limited (O&ME) operates the Hydropower project. The Bujagali Project is a 250MW hydropower facility — developed through a build-own-operate-transfer (BOOT) model — on the Victoria Nile River near the town of Jinja. It reached financial close in 2007, eight years after Government of Uganda (GoU) liberalized its electricity sector in 1999. When commissioned in 2012, it did not only displace expensive emergency power generation, but also contributed towards paving the way for a handful of other smaller scale IPPs that will provide more than 200 MW of small hydro, solar, and bagasse power to the network by around 2020. However, to drive the country’s industrialization program, the GoU is actively looking for ways to reduce the country’s electricity tariffs. In this context, and based on the projected tariff profile, the Bujagali tariff is set to increase from 11.3 US cents/kWh in 2016 to 13.3 US cents/kWh in 2018 and to 14.7 US cents by 2023 due to end of a tax ‘holiday’ (accelerated depreciation) and the debt amortization — before decreasing to 7 US cents/kWh from 2024. -
Croc's July 1.Indd
CLASSIFIED ADVERTS NEW VISION, Monday, July 1, 2013 57 BUSINESS INFORMATION MAYUGE SUGAR INDUSTRIES LTD. SERVICE Material Testing EMERGENCY VACANCIES POLICE AND FIRE BRIGADE: Ring: 999 or 342222/3. One of the fastest developing and THE ONLY 6. BOILER ATTENDANT - 3 Posts Africa Air Rescue (AAR) 258527, MANUFACTURER OF SULPHURLESS SUGAR IN Boiler Attendant Certificate Holders with 3-5 258564, 258409. EAST AFRICA based in Uganda. The organization yrs working experience preferred (Thermo ELECTRICAL FAILURE: Ring is engaged in the manufacturing of “Nile Sugar” fluid handling) UMEME on185. and soon starting the manufacturing of Extra 7. SR. ELECTRICAL & INSTRUMENTATION ENGR. MATERIAL TESTING AND SURVEY EQUIPMENT Water: Ring National Water and Neutral Alcohol Invites applications for below - 1Post Sewerage Corporation on 256761/3, 242171, 232658. Telephone inquiry: posts; B.E.(electrical & instrumentation) or equallent Material Testing UTL-900, Celtel 112, MTN-999, 112 1. SHIFT CHEMIST FOR DISTILLATION - 3 Posts with experience of 15 years FUNERAL SERVICES Must have 3-5 years of experience in PLC/ 8. ELECTRICAL ENGR - 1 Post Aggregates impact Value Kampala Funeral Directors, SKADA system independent operation . Diploma in Electrical Engr.or equallent with Apparatus Bukoto-Ntinda Road. P.O. Box 9670, Qualification :-B.SC.Alco,Tech or Diploma in exp of 5 yrs Flakiness Gauge&Flakiness Chem Eng. 9. INSTRUMENTATION ENGR. - 1 Post Kampala. Tel: 0717 533533, 0312 Sleves 533533. 2. LABORATORY CHEMIST SHIFT - 3 Posts Diploma in Instrumentation or equallent with Los Angeles Abrasion Machine Uganda Funeral Services For Mol Analysis /Spirit Analysis /Q.C exp of 5 yrs H/Q 80A Old Kira Road, Bukoto Checking/Spent wash loss checking etc 10. -
To Reach the Youth: Creating Adolescent-Friendly Reproductive Health Services in Uganda
To Reach the Youth: Creating Adolescent-Friendly Reproductive Health Services in Uganda Stembile Matatu, Clinical Services Advisor, DISH II project, Box 3495, Kampala, Uganda Wangoi Njau, Programme Officer, UNFPA, UN Complex, Gigiri, Block Q, Box 30218, Nairobi, Kenya Fatu Yumkella Regional Evaluation and Research Officer, PRIME II/Intrah project, Box 44958, Nairobi, Kenya Paper Submitted for Poster Session 86 (P86.7) At the xx1v IUSSP General Population Conference Salvador- Brazil 18-24 August 2001 Page 1 The Situation in Uganda While the transition from childhood to adolescence presents challenges for parents and communities worldwide, the situation in the Republic of Uganda is striking. One quarter of the population between the ages of 15 and 19 have their first sexual experience by the age of 15, and nearly half of all Ugandan women become mothers by the age of 18. Adolescents account for 30% of the pregnancy-related deaths in Uganda, about 30% of which are caused by postabortion complications.i Adolescents in Uganda also report a high incidence of negative health consequences as a result of unprotected sexual activity. The Adolescent Reproductive Health (ARH) initiative was implemented jointly by the Uganda Ministry of Health (MOH), and two USAID funded projects- the PRIME Project, and the Delivery of Improved Services for Health (DISH) project. The project was conceived after it became apparent that Ugandan adolescents were not making use of public health care facilities even though they suffered from myriad health problems. As an initial stage of intervention, the MOH and the District Health Management Team (DHMT) in the district of Jinja in southeastern Uganda, in collaboration with PRIME and DISH, established an ARH pilot project within four existing health care centers in Jinja. -
Uganda Health Facilities Survey 2002 [FR140]
Uganda Health Facilities Survey 2002 Ministry of Health Kampala, Uganda ORC Macro MEASURE DHS+ Calverton, Maryland, USA John Snow, Inc./DELIVER Arlington, Virginia, USA JSI Research & Training Institute, Inc./ Uganda AIDS/HIV Integrated Model District Programme (AIM) Kampala, Uganda June 2003 Contributors: John Snow, Inc./DELIVER JSI Research and Training Institute, Inc./AIM Dana Aronovich Evas Kansiime Allison Farnum Cochran Maurice Adams Erika Ronnow Ministry of Health ORC Macro F. G. Omaswa Gregory Pappas H. Kyabaggu Eddie Mukooyo Martin O. Oteba This report presents findings from the 2002 Uganda Health Facilities Survey (UHFS 2002) carried out by the Uganda Ministry of Health. ORC Macro (MEASURE DHS+) and John Snow, Inc. (DELIVER) provided technical assistance. Other organizations contributing to the project were the U.S. Centers for Disease Control and Prevention (CDC/Uganda), the U.S. Agency for International Development (USAID/Uganda), and the JSI Research and Training Institute, Inc., AIDS/HIV Integrated Model District Programme (AIM). MEASURE DHS+, a USAID-funded project, assists countries worldwide in the collection and use of data to monitor and evaluate population, health, and nutrition programs. Information about the Uganda Health Facilities Survey or about the MEASURE DHS+ project can be obtained by contacting: MEASURE DHS+, ORC Macro, 11785 Beltsville Drive, Suite 300, Calverton, MD 20705 (Telephone 301-572-0200; Fax 301-572-0999; E-mail [email protected]; Internet: www.measuredhs.com). DELIVER, a worldwide technical assistance support project, is funded by the Commodities Security and Logistics Division (CSL) of the Office of Population and Reproductive Health of the Bureau for Global Health (GH) of the U.S. -
Half Pages 2018 New.Indd
NOTICE ON FILING CUSTOMARY MARRIAGE RETURNS Article 18 of the Constitution mandates the Government of Uganda to register all The Fees payable are as follows:- PAKELE SUB COUNTY – ADJUMANI MASINYA SUBCOUNTY-BUSIA ITOJO SUBCOUNTY-NTUNGAMO 23 12/09/2018 27 12/09/2018 14 27/01/2018 marriages that occur in Uganda. The Uganda Registration Services Bureau (URSB) is DISTRICT DISTRICT DISTRICT the Government agency responsible for this mandate and administers all laws relating • Issuance of a customary marriage certificate (Form B): 20,000/= PANDWONG DIVISION-KITGUM 28 MORUNGATUNY SUBCOUNTY-AMURIA 28/07/2017 24 20/12/2017 KABWOHE DIVISION – SHEEMA DISTRICT MULANDA SUB COUNTY – TORORO 15 02/05/2018 to marriage. • Registration of a customary marriage within six (6) months: 20,000/= 29 20/04/2018 DISTRICT PATONGO TOWN COUNCIL – AGAGO DISTRICT Customary Marriage is one of the recognized forms of marriage in Uganda. It is performed • Registration of a customary marriage after six (6) months:40,000/= 25 30/05/2018 KAHOORA DIVISION – HOIMA DISTRICT MUYEMBE SUBCOUNTY-MBALE 16 17/08/2016 according to the traditions or customs of a particular African community and is potentially • Certification of registered customary marriage: 25,000/= 30 26/09/2017 DISTRICT 26 PECE DIVISION – GULU DISTRICT 29/03/2018 DISTRICT polygamous. Examples of Customary Marriages in Uganda include Kwanjula for Baganda, • Search on the marriage Register: 25,000/= RUPA SUBCOUNTY-MOROTO NABWIGULU SUBCOUNTY-KAMULI KANUNGU TOWN COUNCIL – 27 08/09/2017 31 07/12/2017 17 13/06/2018 Kuhingira for the Banyankole, Nyom metekwaro a’lango for the Langi, Nyom Acholi for DISTRICT DISTRICT KANUNGU DISTRICT the Acholi etc.