Tel: (403) 920-5214 Fax: (403) 920-2347 Email: [email protected] January 18, 2021 Filed Electronically

Canada Energy Regulator Suite 210, 517 Tenth Avenue SW Calgary, Alberta T2R 0A8

Attention: Mr. Jean-Denis Charlebois, Secretary of the Commission

Dear Mr. Charlebois:

Re: NOVA Gas Transmission Ltd. (NGTL) 2021 NGTL System Expansion Project (Project) Certificate GC-129 (Certificate) and Order XG-001-2020 (as amended) (Order) Certificate Condition 19 and Order Condition 17 Construction Progress Report No. 3 File No.: OF-Fac-Gas-N081-2018-03 02

Pursuant to Certificate condition 19 and Order condition 17, NGTL encloses Construction Progress Report No. 3 (Report).

Please view the following attachments:

• Attachment 1 – Pipeline Construction Progress Report • Attachment 2 – Compressor Station Construction Progress Report

This bi-monthly Report covers the period from January 1 to 15, 2021, (Reporting Period). As per NGTL’s letter of January 15, 2020,1 NGTL stood down work on pipeline related section 58 activities on January 15 and 16, 2020, and restarted critical work under the Order on January 18, 2021.

1 CER Filing ID: C10972. January 18, 2021 Mr. Charlebois Page 2 of 2

Should the CER require additional information, please contact me by phone at (403) 920-5214 or by email at [email protected]. Yours truly, NOVA Gas Transmission Ltd.

Original signed by

Jaron Dyble Regulatory Project Manager Regulatory Facilities, Canadian Natural Gas Pipelines

Enclosures

cc: Heather Dodds, Energy Regulator NOVA Gas Transmission Ltd. Attachment 1 2021 NGTL System Expansion Project Pipe Construction Progress Report No. 3 Section

CONSTRUCTION PROGRESS REPORT NO. 3 Elmworth Section Reporting Period – January 1 to 15, 2021

1.0 REPORT OVERVIEW The Elmworth Section consists of approximately 47 km of 1,219 mm (NPS 48) outside diameter (OD) pipeline, a mainline block valve and associated crossover assemblies. The Elmworth Section begins at NW 24-68-07 W6M and ends at SE 12-71-10 W6M. Section 58 construction activities commenced on December 9, 2020. No Section 52 construction activities have commenced.

This construction progress report (Report) complies with Condition 19 of Certificate GC-129 and Condition 17 of Order XG-001-2020 (as amended), which requires NGTL to report on the following: · information on the activities carried out during the reporting period, any environmental, socio-economic, safety and security issues and issues of non- compliance; and the measures undertaken for the resolution of each issue and non-compliance.

This Report discusses the construction activities for the Elmworth Section that occurred between January 1 to 15, 2021, (Reporting Period).

2.0 CONSTRUCTION PROGRESS · laydown yard activities are complete, with all office trailers and supporting services in place · Section 58 construction activities, including clearing and grading on existing and temporary access commenced on January 4, 2021. · equipment mobilization is on-going to the prime contractor’s yard in , AB.

Table 1 summarizes the status of major construction activities on during the Reporting Period.

January 2021 Page 1 of 3 Attachment 1 NOVA Gas Transmission Ltd. Pipe Construction Progress Report No. 2 Elmworth Section 2021 NGTL System Expansion Project

Table 1: Construction Activity Summary

Activity % Complete Preparation of laydown yard 100 Preparation of existing and temporary access 20 Clearing 0 Grading 0 Stringing 0 Bend and Setup 0 Poor Boy Welding 0 Mainline Welding 0 Coating 0 Ditching 0 Lower-in 0 Backfill 0 Tie-ins 0 Road/Pipeline Bores 0 Hydrostatic Testing 0 Caliper Pigging 0 Final Tie-ins 0 Machine Cleanup 0 Final Cleanup 0

3.0 ENVIRONMENT

3.1 Environmental Issues

During clearing activities on January 7, 2021, within SW 11-70-8 W6M a feller-buncher brought down a large deciduous tree. After the tree was on the ground, the clearing crew inspected the area of the felled tree and found a deceased black bear lying next to the tree. Clearing activities were immediately shut down by the contractor undertaking the work and notified NGTL. Immediately after being notified, NGTL’s lead Environmental Inspector was dispatched to the site to confirm details of the incident. Alberta Environment and Parks (AEP) Land Use Officer, Senior Wildlife Biologist and Fish and Wildlife officer were informed about the incident on January 7, 2021. Post-incident evaluation by the Alberta Fish and Wildlife officer identified an entrance approximately 40 feet above ground to the hollow interior of the tree. The Wildlife officer concluded this hollow was being used as a den. NGTL conducted a bear den sweep through the area by a NGTL-contracted environmental consultant and Indigenous participants in advance of construction and in adherence to the appropriate methodology and did not identify a bear den in the relevant area. While the denning location is considered uncommon, future den survey crews will be requested to be vigilant for large over-mature trees, and signs of bear climbing and potential denning activity. NGTL notified the CER of the incident by

Page 2 of 3 January 2021

NOVA Gas Transmission Ltd. Attachment 1 2021 NGTL System Expansion Project Pipe Construction Progress Report No. 3 Elmworth Section

phone on January 12, 2021. NGTL also notified Aboriginal groups via email on January 12, 2021.

4.0 SAFETY AND SECURITY

No major or critical incidents were recorded during this Reporting Period. For a summary of all safety and security reporting events, see Table 2.

Table 2: Safety Reporting on the ROW

Description Reporting Period/Total Safe Acts 1/1 Unsafe Acts 0/0 Safety 24/7 0/0 Near Hits 0/0 Minor 0/0 Serious 0/0 Major 0/0 Critical 0/0 Note: For incident descriptions, see TC Energy Incident Classification Guide, Safety/Security sections.

5.0 CONSTRUCTION SCHEDULES

The in-service date for the Elmworth Section is forecasted as December 1, 2021, pending completion of the Wapiti HDD.

January 2021 Page 3 of 3

NOVA Gas Transmission Ltd. Attachment 1 2021 NGTL System Expansion Project Pipe Construction Progress Report No. 3 Deep Valley North

CONSTRUCTION PROGRESS REPORT NO. 3 Deep Valley North Section Reporting Period – January 1 to 15, 2021

1.0 REPORT OVERVIEW The Deep Valley North Section consists of approximately 42 km of 1,219 mm (NPS 48) outside diameter (OD) pipeline, mainline block valves, associated crossover assemblies and launcher/receiver assemblies. The Deep Valley North Section begins at SE 25-58-24 W5M and ends at W1/2 28-63-1 W6. Section 58 construction activities commenced on December 10, 2020. No Section 52 construction activities have commenced.

This construction progress report (Report) complies with Condition 19 of Certificate GC-129 and Condition 17 of Order XG-001-2020 (as amended), which requires NGTL to report on the following: · information on the activities carried out during the reporting period, any environmental, socio-economic, safety and security issues and issues of non- compliance; and the measures undertaken for the resolution of each issue and non-compliance.

This Report discusses the construction activities for the Deep Valley North Section that occurred between January 1 to 15, 2021, (Reporting Period).

2.0 CONSTRUCTION PROGRESS

· Clearing contractor continues to progress clearing and grading of the camp and pipe yard, as well as Contractor yard.

· Clearing and grading work will begin this week at the Latornell laydown area.

Table 1 summarizes the status of major construction activities on during the Reporting Period.

Table 1: Construction Activity Summary

Activity % Complete Preparation of laydown yards 100% Preparation of existing and temporary access 20% Clearing 75% Grading 45%

January 2021 Page 1 of 3

Attachment 1 NOVA Gas Transmission Ltd. Pipe Construction Progress Report No. 3 Deep Valley North 2021 NGTL System Expansion Project

Table 1: Construction Activity Summary (cont’d)

Activity % Complete Stringing 0 Bend and Setup 0 Poor Boy Welding 0 Mainline Welding 0 Coating 0 Ditching 0 Lower-in 0 Backfill 0 Tie-ins 0 Road/Pipeline Bores 0 Hydrostatic Testing 0 Caliper Pigging 0 Final Tie-ins 0 Machine Cleanup 0 Final Cleanup 0

3.0 ENVIRONMENT

3.1 Environmental Issues

No major or critical environmental incidents occurred in the Reporting Period.

4.0 SAFETY AND SECURITY

No major or critical incidents were recorded during this Reporting Period. For a summary of all safety and security reporting events, see Table 2.

Table 2: Safety Reporting on the ROW

Description Reporting Period/Total Safe Acts 2/2 Unsafe Acts 0/0 Safety 24/7 0/0 Near Hits 0/0 Minor 1/1 Serious 0/0 Major 0/0 Critical 0/0 Note: For incident descriptions, see TC Energy Incident Classification Guide, Safety/Security sections.

Page 2 of 3 January 2021

NOVA Gas Transmission Ltd. Attachment 1 2021 NGTL System Expansion Project Pipe Construction Progress Report No. 3 Deep Valley North

5.0 CONSTRUCTION SCHEDULES

The in-service date for the Deep Valley North Section is now forecasted as April 1, 2022.

January 2021 Page 3 of 3

NOVA Gas Transmission Ltd. Attachment 1 2021 NGTL System Expansion Project Pipe Construction Progress Report No. 3 Deep Valley Section

CONSTRUCTION PROGRESS REPORT NO. 3 Deep Valley South Section Reporting Period – January 1 to 15, 2021.

1.0 REPORT OVERVIEW The Deep Valley South Section consists of approximately 27 km of 1,219 mm (NPS 48) outside diameter (OD) pipeline, mainline block valves, associated crossover assemblies and launcher/receiver assemblies. The Deep Valley South Section begins at SE 25-58-24 W5M and ends at NE 18-60-25 W5M. Section 58 activities commenced on January 13, 2021. No Section 52 construction activities have commenced.

This construction progress report (Report) complies with Condition 19 of Certificate GC-129 and Condition 17 of Order XG-001-2020 (as amended), which requires NGTL to report on the following: · information on the activities carried out during the reporting period, any environmental, socio-economic, safety and security issues and issues of non- compliance; and the measures undertaken for the resolution of each issue and non-compliance.

This Report discusses the construction activities for the Deep Valley South Section that occurred between January 1 to 15, 2021, (Reporting Period).

2.0 CONSTRUCTION PROGRESS · Contractor has commenced mobilizing to site · Line locating activities have commenced

Table 1 summarizes the status of major construction activities on during the Reporting Period.

Table 1: Construction Activity Summary

Activity % Complete Preparation of laydown yards 0 Preparation of existing and temporary access 0 Clearing 0 Grading 0 Stringing 0 Bend and Setup 0 Poor Boy Welding 0 Mainline Welding 0 Coating 0

January 2021 Page 1 of 2

Attachment 1 NOVA Gas Transmission Ltd. Pipe Construction Progress Report No. 2 Deep Valley Section 2021 NGTL System Expansion Project

Table 1: Construction Activity Summary (cont’d) Activity % Complete Ditching 0 Lower-in 0 Backfill 0 Tie-ins 0 Road/Pipeline Bores 0 Hydrostatic Testing 0 Caliper Pigging 0 Final Tie-ins 0 Machine Cleanup 0 Final Cleanup 0

3.0 ENVIRONMENT

3.1 Environmental Issues

No major or critical environmental incidents occurred in the Reporting Period.

4.0 SAFETY AND SECURITY

No major or critical incidents were recorded during this Reporting Period. For a summary of all safety and security reporting events, see Table 2.

Table 2: Safety Reporting on the ROW

Description Reporting Period/Total Safe Acts 0/0 Unsafe Acts 0/0 Safety 24/7 0/0 Near Hits 0/0 Minor 0/0 Serious 0/0 Major 0/0 Critical 0/0 Note: For incident descriptions, see TC Energy Incident Classification Guide, Safety/Security sections.

5.0 CONSTRUCTION SCHEDULES

The in-service date for the Deep Valley South Section is forecasted for April 1, 2022.

Page 2 of 2 January 2021

NOVA Gas Transmission Ltd. Attachment 1 2021 NGTL System Expansion Project Pipe Construction Progress Report No. 3 Karr Section

CONSTRUCTION PROGRESS REPORT NO. 3 Karr Section Reporting Period – January 1 to 15, 2021.

1.0 REPORT OVERVIEW The Karr Section consists of approximately 57 km of 1,219 mm (NPS 48) outside diameter (OD) pipeline, mainline block valves, associated crossover assemblies and launcher/receiver assemblies. The Karr Section begins at NW 28-63-01 W6M and ends at NE 26-67-05 W6M. Section 58 activities commenced on January 15, 2021. Section 52 construction activities have not commenced.

This construction progress report (Report) complies with Condition 19 of Certificate GC-129 and Condition 17 of Order XG-001-2020 (as amended), which requires NGTL to report on the following: · information on the activities carried out during the reporting period, any environmental, socio-economic, safety and security issues and issues of non- compliance; and the measures undertaken for the resolution of each issue and non-compliance.

This Report discusses the construction activities for the Karr Section that occurred between January 1 to 15, 2021, (Reporting Period).

2.0 CONSTRUCTION PROGRESS

· Clearing at Karr Camp site has been completed

· Contractor started installing signs on the Canfor 2000 & 4000 roads

· Contractor has started clearing Latornell staging area

· Equipment mobilization in progress

Table 1 summarizes the status of major construction activities on during the Reporting Period.

January 2021 Page 1 of 3

Attachment 1 NOVA Gas Transmission Ltd. Pipe Construction Progress Report No. 2 Karr Section 2021 NGTL System Expansion Project

Table 1: Construction Activity Summary

Activity % Complete Preparation of laydown yards 10 Preparation of existing and temporary access 0 Clearing 0 Grading 0 Stringing 0 Bend and Setup 0 Poor Boy Welding 0 Mainline Welding 0 Coating 0 Ditching 0 Lower-in 0 Backfill 0 Tie-ins 0 Road/Pipeline Bores 0 Hydrostatic Testing 0 Caliper Pigging 0 Final Tie-ins 0 Machine Cleanup 0 Final Cleanup 0

3.0 ENVIRONMENT

3.1 Environmental Issues

No major or critical environmental incidents occurred in the Reporting Period.

4.0 SAFETY AND SECURITY

No major or critical incidents were recorded during this Reporting Period. For a summary of all safety and security reporting events, see Table 2.

Page 2 of 3 January 2021

NOVA Gas Transmission Ltd. Attachment 1 2021 NGTL System Expansion Project Pipe Construction Progress Report No. 3 Karr Section

Table 2: Safety Reporting on the ROW

Description Reporting Period/Total Safe Acts 0/0 Unsafe Acts 0/0 Safety 24/7 0/0 Near Hits 0/0 Minor 0/0 Serious 0/0 Major 0/0 Critical 0/0 Note: For incident descriptions, see TC Energy Incident Classification Guide, Safety/Security sections.

5.0 CONSTRUCTION SCHEDULES

The in-service date for the Karr Section is now forecasted as March 2022.

January 2021 Page 3 of 3

NOVA Gas Transmission Ltd. Attachment 1 2021 NGTL System Expansion Project Pipe Construction Progress Report No. 3 Dismal Creek Section

CONSTRUCTION PROGRESS REPORT NO. 3 Dismal Creek Section Reporting Period – January 1 to 15, 2021

1.0 REPORT OVERVIEW The Dismal Creek Section consists of approximately 32 km of 1,219 mm (NPS 48) outside diameter (OD) pipeline, mainline block valves, associated crossover assemblies and launcher/receiver assemblies. The Dismal Creek Section begins at SW 3-47-14 W5M and ends at NW 23-49-16 W5M. Section 58 construction activities commenced on January 5, 2021. No Section 52 construction activities have commenced.

This construction progress report (Report) complies with Condition 19 of Certificate GC-129 and Condition 17 of Order XG-001-2020 (as amended), which requires NGTL to report on the following: · information on the activities carried out during the reporting period, any environmental, socio-economic, safety and security issues and issues of non- compliance; and the measures undertaken for the resolution of each issue and non-compliance.

This Report discusses the construction activities for the Dismal Creek Section that occurred between January 1 to 15, 2021, (Reporting Period).

2.0 CONSTRUCTION PROGRESS · Clearing contractor has commenced mobilizing to a contractor yard in Drayton Valley, AB. · Preparation of access

Table 1 summarizes the status of major construction activities on during the Reporting Period.

Table 1: Construction Activity Summary

Activity % Complete Preparation of laydown yards 10% Preparation of existing and temporary access 30% Clearing 0 Grading 0 Stringing 0 Bend and Setup 0 Poor Boy Welding 0

January 2021 Page 1 of 2

Attachment 1 NOVA Gas Transmission Ltd. Pipe Construction Progress Report No. 2 Dismal Creek Section 2021 NGTL System Expansion Project

Table 1: Construction Activity Summary (cont’d)

Activity % Complete Mainline Welding 0 Coating 0 Ditching 0 Lower-in 0 Backfill 0 Tie-ins 0 Road/Pipeline Bores 0 Hydrostatic Testing 0 Caliper Pigging 0 Final Tie-ins 0 Machine Cleanup 0 Final Cleanup 0

3.0 ENVIRONMENT

3.1 Environmental Issues

No major or critical environmental incidents occurred in the Reporting Period.

4.0 SAFETY AND SECURITY

No major or critical incidents were recorded during this Reporting Period. For a summary of all safety and security reporting events, see Table 2.

Table 2: Safety Reporting on the ROW

Description Reporting Period/Total Safe Acts 0/0 Unsafe Acts 0/0 Safety 24/7 0/0 Near Hits 0/0 Minor 0/0 Serious 0/0 Major 0/0 Critical 0/0 Note: For incident descriptions, see TC Energy Incident Classification Guide, Safety/Security sections.

5.0 CONSTRUCTION SCHEDULES

The in-service date for the Dismal Creek Section is now forecasted as April 1, 2022

Page 2 of 2 January 2021

NOVA Gas Transmission Ltd. Attachment 1 2021 NGTL System Expansion Project Pipe Construction Progress Report No. 3 Brewster Section

CONSTRUCTION PROGRESS REPORT NO. 3 Brewster Section Reporting Period – January 1 to 15, 2021

1.0 REPORT OVERVIEW SCOPE The Brewster Section consists of approximately 49 km of 1,219 mm (NPS 48) outside diameter (OD) pipeline, mainline block valves, associated crossover assemblies and launcher/receiver assemblies. The Brewster Section begins at SE 14-39-10 W5M and ends at NW 20-43-12 W5M. Section 58 construction activities commenced on December 2, 2020. No Section 52 construction activities have commenced.

This construction progress report (Report) complies with Condition 19 of Certificate GC-129 and Condition 17 of Order XG-001-2020 (as amended), which requires NGTL to report on the following: · information on the activities carried out during the reporting period, any environmental, socio-economic, safety and security issues and issues of non- compliance; and the measures undertaken for the resolution of each issue and non-compliance.

This Report discusses the construction activities for the Brewster Section that occurred between January 1 to 15, 2021, (Reporting Period).

2.0 CONSTRUCTION PROGRESS · Contractor remobilized to site following holiday break. · Preparation for Section 58 activities is underway.

Table 1 summarizes the status of major construction activities on during the Reporting Period.

Table 1: Construction Activity Summary

Activity % Complete Preparation of laydown yards 20 Preparation of existing and temporary access 0 Clearing 0 Grading 0 Stringing 0 Bend and Setup 0 Poor Boy Welding 0

January 2021 Page 1 of 2

Attachment 1 NOVA Gas Transmission Ltd. Pipe Construction Progress Report No. 2 Brewster Section 2021 NGTL System Expansion Project

Table 1: Construction Activity Summary (cont’d)

Activity % Complete Mainline Welding 0 Coating 0 Ditching 0 Lower-in 0 Backfill 0 Tie-ins 0 Road/Pipeline Bores 0 Hydrostatic Testing 0 Caliper Pigging 0 Final Tie-ins 0 Machine Cleanup 0 Final Cleanup 0

3.0 ENVIRONMENT

3.1 Environmental Issues

No major or critical environmental incidents occurred in the Reporting Period.

4.0 SAFETY AND SECURITY

No major or critical incidents were recorded during this Reporting Period. For a summary of all safety and security reporting events, see Table 2.

Table 2: Safety Reporting on the ROW

Description Reporting Period/Total Safe Acts 0/0 Unsafe Acts 0/0 Safety 24/7 0/0 Near Hits 0/0 Minor 0/0 Serious 0/0 Major 0/0 Critical 0/0 Note: For incident descriptions, see TC Energy Incident Classification Guide, Safety/Security sections.

5.0 CONSTRUCTION SCHEDULES

The in-service date for the Brewster Section is now forecasted as April 1, 2022.

Page 2 of 2 January 2021

NOVA Gas Transmission Ltd. Attachment 2 2021 NGTL System Expansion Project Compressor Station Construction Progress Report No. 3

CONSTRUCTION PROGRESS REPORT NO. 3 Compressor Stations Reporting Period – January 1 to 15, 2021

1.0 REPORT OVERVIEW SCOPE

The Compressor Station scope includes the installation of three unit-additions as detailed in Table 1.

Table 1: Compressor Station Scope Compressor Station Location Scope Nordegg Clearwater County; located Full expansion, inclusive of, but not limited to, the addition of Compression approximately 80 km NW of a Siemens SGT-A35-GT61 DLE with RFA-36 Compressor, Station Rocky Mountain House, AB new buildings, electrical system upgrades, new auxiliary systems and, interconnecting yard piping. Beiseker Rocky View County; located Full expansion, inclusive, but not limited to, the addition of a Compressor approximately 17 km SE of Siemens SGT-A35-GT61 DLE with RFA-36 Compressor, gas Station Beiseker, AB aerial cooling, new buildings, electrical system upgrades, new auxiliary systems and interconnecting yard piping. Didsbury Mountainview County; Full expansion, inclusive, but not limited to, the addition of a Compressor located approximately 20 km Siemens SGT-A35-GT61 DLE with RFA-36 Compressor, gas Station SW of Didsbury, AB aerial cooling, new buildings, electrical system upgrades, new auxiliary systems and interconnecting yard piping.

This construction progress report (Report) complies with Condition 17 of Order XG-001-2020 (as amended), which requires NGTL to report on the following:

• information on the activities carried out during the reporting period, any environmental, socio-economic, safety and security issues and issues of non- compliance; and the measures undertaken for the resolution of each issue and non-compliance.

This Report discusses the construction activities for the Nordegg, Didsbury and Beiseker compressor stations that occurred between January 1 to 15, 2021, (Reporting Period).

2.0 CONSTRUCTION PROGRESS Planned activities at the Nordegg Compressor Station include:

• Gravel and aggregate deliveries to site

• Site pad construction including aggregate placement, backfilling and testing

• Temporary workspace slurry pit construction

• Formwork construction and removal

• Concrete pour for compressor block and grade beam

• Steel piling and pile driver analysis (PDA) testing

January 2021 Page 1 of 5

Attachment 2 NOVA Gas Transmission Ltd. Compressor Station Construction Progress Report No. 2 2021 NGTL System Expansion Project

A summary of construction activities for the Nordegg Compressor Station from January 1 to 15, 2021, is as follows:

• Gravel and aggregate deliveries to site

• Site pad construction including aggregate placement, backfilling and testing

• Matting temporary workspace and laydowns

• Topsoil stripping

• Temporary workspace slurry pit construction

• Formwork construction in preparation for concrete pouring

• Surveying steel pile locations

• Hydrovac pilot holes for steel piles

Planned activities at the Didsbury Compressor Station include:

• Steel piling and PDA testing

• Cast-In-Place (CIP) piling

• Remediation of contaminated soil area

• Continue with clean up and demolition scope

• Shipment of modules to site

A summary of construction activities for the Didsbury Compressor Station from January 1 to 15, 2021, is as follows:

• Hydrovac activities

• Continue remediation of contaminated soil area

• Piling and PDA testing on site

• Building access mat road into the tie-in area for the piling rig

• Continue with clean up site holes and pilot holes for sleeves and demolition scope

• Lay out temporary work area for setting down mods

Planned activities at the Beiseker Compressor Station include:

• Rough grade cut and fill

• Pre-cast foundation and bollards for transformer

• Piling installation and cutting/cap

• Construct site access road (to underside of final grade)

• Start backfilling of compressor block and rebar

• Emergency shutdown device (ESD) cable loop and electrical device install

Page 2 of 5 January 2021

NOVA Gas Transmission Ltd. Attachment 2 2021 NGTL System Expansion Project Compressor Station Construction Progress Report No. 3

A summary of construction activities for the Beiseker Compressor Station from January 1 to 15, 2021, is as follows:

• Rough grade cut and fill

• Stripping, compaction

• Piling and PDA testing

Table 2 summarizes the status of major construction activities conducted during the Reporting Period.

Table 2: Construction Activity Summary

Station Activity % Complete Nordegg Compressor Station Prime Contractor Mobilization 100 Pipe Fabrication 99 Structural Steel Fabrication 99 Site Survey Sweep 100 Site Clearing/Grading 100 Site Backfilling Rough Grade 30 Site Piling 2 Pile Cutting and Capping 0 Pipe Installation 0 Compressor Building Foundation 0 Compressor and Turbine Installation 0 Compressor Package Final Installation 0 Site Electrical Installation 0 Didsbury Compressor Station Prime Contractor Mobilization 100 Pipe Fabrication 97 Structural Steel Fabrication 97 Site Survey Sweep 100 Site Clearing/Grading 90 Site Backfilling Rough Grade 0 Site Piling 15 Pile Cutting and Capping 0 Pipe Installation 0 Compressor Building Foundation 0 Compressor and Turbine Installation 0 Compressor Package Final Installation 0 Site Electrical Installation 0

January 2021 Page 3 of 5

Attachment 2 NOVA Gas Transmission Ltd. Compressor Station Construction Progress Report No. 2 2021 NGTL System Expansion Project

Table 2: Construction Activity Summary (cont’d)

Station Activity % Complete Beiseker Compressor Station Prime Contractor Mobilization 95 Pipe Fabrication 99 Structural Steel Fabrication 95 Site Survey Sweep 100 Site Clearing/Grading 90 Site Backfilling Rough Grade 70 Site Piling 21 Pile Cutting and Capping 3 Pipe Installation 0 Compressor Building Foundation 15 Compressor and Turbine Installation 0 Compressor Package Final Installation 0 Site Electrical Installation 1

3.0 ENVIRONMENT AND SOCIO-ECONOMIC No major or critical environmental incidents occurred in the Reporting Period.

4.0 SAFETY AND SECURITY No major or critical incidents were recorded during this Reporting Period. For a summary of all safety and security reporting, see Tables 3 through 5.

Table 3: Safety Reporting at Nordegg Description Reporting Period/Total Safe Acts 29/697 Unsafe Acts 4/59 Safety 24/7 0/6 Near Hits 0/0 Minor 0/2 Serious 0/0 Major 0/0 Critical 0/0 Note: For incident descriptions, see TC Energy Incident Classification Guide, Safety/Security sections.

Page 4 of 5 January 2021

NOVA Gas Transmission Ltd. Attachment 2 2021 NGTL System Expansion Project Compressor Station Construction Progress Report No. 3

Table 4: Safety Reporting at Didsbury Description Reporting Period/Total Safe Acts 0/203 Unsafe Acts 1/9 Safety 24/7 0/1 Near Hits 0/1 Minor 1/10 Serious 0/0 Major 0/0 Critical 0/0 Note: For incident descriptions, see TC Energy Incident Classification Guide, Safety/Security sections.

Table 5: Safety Reporting at Beiseker Description Reporting Period/Total Safe Acts 3/40 Unsafe Acts 0/19 Safety 24/7 0/4 Near Hits 0/0 Minor 1/7 Serious 0/0 Major 0/0 Critical 0/0 Note: For incident descriptions, see TC Energy Incident Classification Guide, Safety/Security sections.