Work 41 (2012) 5935-5942 DOI: 10.3233/WOR-2012-0990-5935 5935 IOS Press

Development of an ergonomics device for maintenance of hydraulic generators of Tucuruí hydropower plant

Batista, I.C. a,*, Gomes, G.J.C a, Teles, C.S a , Oliveira, P.F. a , Santos, R. M. b, Sassi, A. C. c Sá, B. c, B. V d and. Pardauil ,A. A e a Mechanics Maintenance Area, Eletronorte,Vila Permanente, Tucuruí, Pará, e Health Pillar, Eletrobras Eletronorte,Vila Permanente, Tucuruí, Pará, Brazil fStrategic Management Committee , Eletrobras Eletronorte, Tucuruí, Pará, Brazil fhHydraulic Generation Superintendent, Eletrobras Eletronorte,Vila Permanente, Tucuruí, Pará, Brazil

Abstract. This paper aims to present an ergonomic device to assist in the maintenance of the units of Tucuruí Hydropower Plant. The development of this ergonomic device made possible to reduce maintenance time, reduce losses caused by billing, improve performance and reduce the physical strain for labors during the execution of services.

Keywords: Device, maintenance, ergonomics

1051-9815/12/$27.50 © 2012 – IOS Press and the authors. All rights reserved

5936 I.C. Batista et al. / Development of an Ergonomics Device for Maintenance of Hydraulic Generators

1. Introduction always seek the best solutions, seeking to make the set more agile and dynamic, because its role is to Tucuruí Hydropower Plant is the largest hydroe- support the production. lectric plant in Brazilian territory (8370 MW), as the More broadly, the term maintenance encompasses Itaipu plant is binational. It is located on the To- the concepts of prevention (keeping) and fix (re- cantins River in the town of Tucuruí, about 400 km store) [2]. Monchy [1] also comments on the blank from Belém, in Pará State. It was built to generate left by most definitions when they make no refer- electricity and to make a navigable a stretch of the ence to the economic aspect involved in making an river full of rapids, overcoming them by means of a efficient maintenance, which should ensure that its lock chamber. activities would lead to an overall optimized cost. With the globalization of market competition be- According to Nakajima [3], the evolution of the came fiercer, requiring companies a world-class maintenance system in Japan was done in four phas- performance. Given this need, companies have been es: Corrective Maintenance, Preventive Maintenance, adapting to the standards of quality, so it becomes Production System Maintenance and TPM. necessary to do the maintenance at specific periods, TPM also includes Predictive Maintenance tech- thus avoiding undue costs with corrective mainte- niques, ie, the use of tools that enable preliminary nance. Such things confirm the importance of im- diagnosis of machinery and equipment. plementation of a methodology with focus on pre- TPM focuses on reducing costs with equipment’s ventive maintenance, exactly what is approached in life cycle, combining preventive maintenance with TPM and ergonomics science. sustainable improvements and preventive mainte- The purpose of this paper is to present the devel- nance project. TPM yields autonomous maintenance opment of an ergonomic device constructed inside of a production that attempts to optimize the opera- Tucuruí plant in order to held generating units main- tor's skill and knowledge of own working equipment tenances during a shorter time and reduce the physi- to maximize its operating efficiency. cal exertion made by employees during the execu- In consonance with the definition of TPM, each tion of services. letter has its own meaning as follows: The text is made up of a section that presents the - The letter "T" means "TOTAL". Total in the theoretical framework about the maintenance history, sense of overall efficiency, also in the sense of total with application of the Total Productive Mainte- life cycle of the production system and in the sense nance methodology. Next are the methodology and of the totality of departments and participation; development stages of the ergonomic device and - The letter "P" means "PRODUCTIVE." The finally, it presents final considerations for the work. quest of the system of production to reach the max- imum efficiency, achieving "zero accidents, zero defects and zero breakdowns/failure", that is to say, 2. Maintenance history the elimination of all types of loss until reaching the zero; According to Monchy, the term "maintenance" - The letter "M" means "MAINTENANCE". has its origin in military vocabulary whose meaning Maintenance in the broad sense, which has as its was “keeping the military personnel and the material object the total life cycle of the production system, at a constant level in combat units”. Clearly, the additionally means the maintenance that that has as units that interest us here are the production units, object the production system of single process, the and the combat is primarily economic. The appear- factory and the sales system. The following item ance of the term "maintenance" in the industry oc- will address the implementation of ergonomics prin- curred around 1950 in the United States of America. ciples in the company. In France, this term overlays progressively the word It is important to remind the fact the TPM meth- "conservation" [1]. odology is used in Tucuruí plant since 1999 and it The industries need urgent technical and adminis- has been contributing significantly to the develop- trative changes in all sectors to ensure their produc- ment of the ergonomic process in the company. tivity. Maintenance has to be modern and efficient, keeping up with the rhythm of the whole techno- logical development process, and before becoming one more obstacle to the means of production it must always seek the best solutions, seeking to

I.C. Batista et al. / Development of an Ergonomics Device for Maintenance of Hydraulic Generators 5937

2.1. Ergonomics program in Tucuruí plant occurs because such research involves obtaining descriptive data about certain places, people or in- After the implementation of the TPM methodol- teractive processes; through direct contact of the ogy in Tucuruí plant, the organization of the Ergo- researcher with the studied situation, trying to un- nomics Program had its start in 2001, introducing derstand the phenomena from the perspective of the the development of various actions, such as: analysis subject [4]. In this scenario, the case study was con- of work from an ergonomic point, awareness of the ducted at the Tucuruí Hydropower Plant to the de- workforce, changes in the workspaces, and studies velopment of ergonomic device to be used in the for the development of ergonomic devices. maintenance of generating units. In 2006, the Ergonomics Committee was struc- tured, comprising representatives from all areas of Tucuruí plant, whose goal is the early identification 4. Development of the improvement (Kaizen) of ergonomic non-conformities, that is, potential causes of musculoskeletal and psychological injuries The Tucuruí plant has 25 generating units, those in the workplace or while using tools or finding is- are scheduled for review in its various systems every sues of working methods. five years, an average of five units per year. The The Ergonomics Committee considered that the braking system, for which this tool was developed, maintenance process demands great physical exer- is one of the most important systems of the genera- tion and requires a person to put him/herself in tor, because it stops the machine not only in normal awkward postures due to the difficulty of entering operation, but in emergency situations. the place on its own, without forgetting the weight The maintenance of this system consists in re- of tools; thereupon, in accordance with the direction moving the brake actuator (Figure 1) from its base of the committee it was defined the adoption of the for inspection and replacement of the pads (brake tool developed by Suzanne Rodgers (Suzanne Rod- plates) and repair of the