Managing the Planning Fallacy in Large, Complex Infrastructure Programs by Bob Prieto

Total Page:16

File Type:pdf, Size:1020Kb

Managing the Planning Fallacy in Large, Complex Infrastructure Programs by Bob Prieto PM World Journal Managing the Planning Fallacy in Large Vol. II, Issue VIII – August 2013 Complex Infrastructure Programs www.pmworldjournal.net Featured Paper by Bob Prieto Managing the Planning Fallacy in Large, Complex Infrastructure Programs by Bob Prieto Daniel Kahneman’s recent book, “Thinking, Fast and Slow” 1 returned his concept of the “planning fallacy” to the project management center stage when considering large, complex projects and programs. First coined by Kahneman and Amos Tversky in a 1979 paper2, the planning fallacy is the tendency of people and organizations to underestimate how long a task will take even when they have experience of similar tasks over running. Perhaps the poster children for the planning fallacy are large scale public works projects. In a 2006 paper in the Project Management Journal3, Bent Flyvbjerg describes transportation projects “inaccuracy in cost forecasts in constant prices is on average 44.7% for rail, 33.8% for bridges and tunnels, and 20.4% for roads.” Work by Kahneman, Tversky, Flyvbjerg and others shows that errors of judgment are: - systematic and predictable - reflect bias - persist even when we are aware of, and - require corrective measures that reflect recognition of this bias These natural tendencies are further exacerbated when “motivated” individuals frame questions in such a way as to constrain the range of possible answers. Consider these two situations. In the first, a manager is given responsibility to come up with a budget and schedule for a large project. He engages outside help, conducts a thorough risk analysis and looks at comparable other projects. In the second a manager is asked by the politically appointed Chairman of the Authority if he can do the same project for $ XX. Which answer are you more comfortable with? Reference class forecasting is one method for suspending one’s impressions and providing a more critical evaluation of the task at hand. It addresses the natural tendency to underestimate costs, completion times and risks while at the same time overestimating benefits. It squeezes out biases while considering the inevitable “improbable” risks that all projects face. The risks 1 Thinking, Fast and Slow; Daniel Kahneman; ISBN:9780374275631; 2011 2 "Prospect theory: An analysis of decisions under risk". Econometrica; Kahneman and Tversky; 1979 3 From Nobel Prize To Project Management: Getting Risks Right; Bent Flyvbjerg; Aalborg University, Denmark; Project Management Journal; August, 2006. © 2013 Bob Prieto www.pmworldlibrary.net Page 1 of 16 PM World Journal Managing the Planning Fallacy in Large Vol. II, Issue VIII – August 2013 Complex Infrastructure Programs www.pmworldjournal.net Featured Paper by Bob Prieto that inhabit the “white space” between elements of a program and possibly even the odd “Black Swan” that shows up from time to time. The Association for the Advancement of Cost Engineering (AACE) has recognized the value of estimate validation using separate empirical-based evaluations to benchmark the base estimate, the equivalent of reference based forecasting. This estimate benchmarking process is widely used in the process industries but need not be constrained to them. Reference Class Forecasting Let’s look at an example at how reference class forecasting can be used not only to provide a basis for checking planned execution approaches and associated project timelines but also to identify how the execution methodology and, in this case, even the contracting strategy will need to be modified. The particular project of interest was the pacing element of a larger program. The methodology described below was also extended to the complete program and identified several added changes to the program methodology which would be required. The reference class forecast began by identifying a comparable scale similar type project for which there was a good information database and performance was well documented. That project was in the later stages of completion and actual schedule performance through the majority of the project was already known. The schedule for this reference project is reflected in Figure 1. Project activities and dates have been generalized for purposes of this paper. While the design of the new project clearly will be different, it was judged that in terms of supply chain, complexity and scale those differences were not significant and that the reference class forecast undertaken would provide a good initial indicator of project durations and contract delivery strategies. © 2013 Bob Prieto www.pmworldlibrary.net Page 2 of 16 PM World Journal Managing the Planning Fallacy in Large Vol. II, Issue VIII – August 2013 Complex Infrastructure Programs www.pmworldjournal.net Featured Paper by Bob Prieto 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 1 Design Activity 1.1 Design Activity 1.2 Construction Tender 2 Construction Mobilization Activity 2.1 Contract Award Activity 2.2 Mobilization Activity 2.3 Specialized Construction Technology Mobilization 3 Enabling Works Activity 3.1 Enabling Works Activity 3.2 Temporary Construction – Land Based Activity 3.3 Temporary Construction – Marine Based Activity 3.4 Temporary Steel #1 Activity 3.5 Temporary Steel #2 4 Long Lead Procurement Activity 4.1 Group #1 Activity 4.2 Group #2 Activity 4.3 Group #3 © 2013 Bob Prieto www.pmworldlibrary.net Page 3 of 16 PM World Journal Managing the Planning Fallacy in Large Vol. II, Issue VIII – August 2013 Complex Infrastructure Programs www.pmworldjournal.net Featured Paper by Bob Prieto 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 5 Steel Fabrication Activity 5.1 Shop Drawings Activity 5.2 Shop Practices/Fabrication & Erection Drawings Activity 5.3 Fab Package #1 Activity 5.4 Fab Package #2 6 Erection Activity 6.1 Erection Package #1 Activity 6.2 Erection Package #2 Activity 6.3 Erection Package #3 Activity 6.4 Erection Package #4 Activity 6.5 Erection Package #5 Activity 6.6Major Structural Activity Activity 6.7 Activity 6.8 Activity 6.9 Activity 6.10 Activity 6.11 Mechanical/Electrical Activity 6.12 Completion & Commissioning Activity 6.13Complete Figure 1 The next step in developing a reference case based forecast was to overlay the project schedule against the then “current” calendar so that likely end dates could be forecast. This is shown in Figure 2. Initial activities pacing the schedule are related to design activities which in the reference case were completed before construction was started. 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 1 Design Activity 1.1 Design Activity 1.2 Construction Tender 2 Construction Mobilization Activity 2.1 Contract Award Activity 2.2 Mobilization Activity 2.3 Specialized Construction Technology Mobilization 3 Enabling Works Activity 3.1 Enabling Works Activity 3.2 Temporary Construction – Land Based Activity 3.3 Temporary Construction – Marine Based Activity 3.4 Temporary Steel #1 Activity 3.5 Temporary Steel #2 © 2013 Bob Prieto www.pmworldlibrary.net Page 4 of 16 PM World Journal Managing the Planning Fallacy in Large Vol. II, Issue VIII – August 2013 Complex Infrastructure Programs www.pmworldjournal.net Featured Paper by Bob Prieto 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 4 Long Lead Procurement Activity 4.1 Group #1 Activity 4.2 Group #2 Activity 4.3 Group #3 5 Steel Fabrication Activity 5.1 Shop Drawings Activity 5.2 Shop Practices/Fabrication & Erection Drawings Activity 5.3 Fab Package #1 Activity 5.4 Fab Package #2 6 Erection Activity 6.1 Erection Package #1 Activity 6.2 Erection Package #2 Activity 6.3 Erection Package #3 Activity 6.4 Erection Package #4 Activity 6.5 Erection Package #5 Activity 6.6Major Structural Activity Activity 6.7 Activity 6.8 Activity 6.9 Activity 6.10 Activity 6.11 Mechanical/Electrical Activity 6.12 Completion & Commissioning Activity 6.13Complete Figure 2 As can be seen in Figure 3, construction was anticipated to be complete at the end of the first quarter of 2019 if a comparable design development and contracting approach was utilized. The client’s target date of mid-2017, also reflected in Figure 3, was 21 months earlier. The initial project execution strategy envisioned engaging a singular design-build contractor, but this initial reference class forecasting step highlighted that this would not achieve the required 21 month schedule reduction. 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 1 Design Activity 1.1 Design Activity 1.2 Construction Tender 2 Construction Mobilization Activity 2.1 Contract Award Activity 2.2 Mobilization Activity 2.3 Specialized Construction Technology Mobilization 3 Enabling Works Activity 3.1 Enabling Works Activity 3.2 Temporary Construction – Land Based © 2013 Bob Prieto www.pmworldlibrary.net Page 5 of 16 PM World Journal Managing the Planning Fallacy in Large Vol. II, Issue VIII – August 2013 Complex Infrastructure Programs www.pmworldjournal.net Featured Paper by Bob Prieto 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Activity 3.3 Temporary Construction – Marine Based Activity 3.4 Temporary Steel #1 Activity 3.5 Temporary Steel #2 4 Long Lead Procurement Activity 4.1 Group #1 Activity 4.2 Group #2 Activity 4.3 Group #3 5 Steel Fabrication Activity 5.1 Shop Drawings Activity 5.2 Shop Practices/Fabrication & Erection Drawings Activity 5.3 Fab Package #1 Activity 5.4 Fab Package #2 6 Erection Activity 6.1 Erection Package #1 Activity 6.2 Erection Package #2 Activity 6.3 Erection Package #3 Activity 6.4 Erection Package #4 Activity 6.5 Erection Package #5 Activity 6.6Major Structural Activity Activity 6.7 Activity 6.8 Activity 6.9 Activity 6.10 Activity 6.11 Mechanical/Electrical Activity 6.12 Completion & Commissioning Activity 6.13Complete Figure 3 This set the stage for developing an alternative contracting and delivery approach that would provide a better founded basis for project delivery. The development of the alternative approach began with sliding required construction activities forward such that the actual construction durations required could still be available to the program although it was clear that they would have to be contracted for in a very different manner.
Recommended publications
  • Cost Engineering Journal
    THE JOURNAL OF AACE® INTERNATIONAL - THE AUTHORITY FOR TOTAL COST MANAGEMENT® March/April 2016 ENGINEERINGENGINEERING COSCOSTT www.aacei.org REVIEWING RESOURCE LEVELED SCHEDULES USING P6TM THE PLANNING FALLACY AND ITS EFFECT ON REALISTIC PROJECT SCHEDULES FORENSIC SCHEDULE ANALYSIS AND DISCRETIONARY LOGIC TECHNICAL ARTICLE The Planning Fallacy and Its Effect on Realistic Project Schedules Jeffrey Valdahl and Shannon A. Katt performing similar tasks. Kahneman Abstract: “How long do you think that task will take?” It’s a question that is states that the planning fallacy asked frequently during the course of a project, but is often answered with describes plans and forecasts that: little or no factual basis. Project team members typically underestimate the time needed to complete a task they are responsible for. This tendency has been referred to as the “planning fallacy,” and it can have a dramatic effect • Are unrealistically close to best- on developing a realistic overall project schedule. This article examines var- case scenarios ious causes of the planning fallacy, including optimism bias, lack of task un- • Could be improved by consulting packing, and short memory. the statistics of similar cases [7]. As a project manager or planner, it is important to recognize when these psychological effects are impacting your project schedule. This article uses Kahneman also describes the examples from various projects to show where this challenging planning exercise that first led him to describe issue is likely to occur. Identifying where adjustments need to be made, at the concept. He was working with a both the task and overall project level, is essential in developing a project team of colleagues to write an schedule that is both achievable and reasonable.
    [Show full text]
  • Cost Overruns in Large-Scale Transportation Infrastructure Projects: Explanations and Their Theoretical Embeddedness
    Cost overruns in Large-Scale Transportation Infrastructure Projects: Explanations and Their Theoretical Embeddedness By Chantal C. Cantarelli, Bent Flybjerg, Eric J. E. Molin, and Bert van Wee Full reference: Cantarelli, C. C., Flyvbjerg, B., Molin, E.J.E., and van Wee, B. 2010. “Cost Overruns in Large-Scale Transportation Infrastructure Projects: Explanations and Their Theoretical Embeddedness,” European Journal of Transport and Infrastructure Research, 10 (1): 5-18. Link to published article: http://www.ejtir.tbm.tudelft.nl/issues/2010_01 2 Abstract Managing large-scale transportation infrastructure projects is difficult due to frequent misinformation about the costs which results in large cost overruns that often threaten the overall project viability. This paper investigates the explanations for cost overruns that are given in the literature. Overall, four categories of explanations can be distinguished: technical, economic, psychological, and political. Political explanations have been seen to be the most dominant explanations for cost overruns. Agency theory is considered the most interesting for political explanations and an eclectic theory is also considered possible. Non- political explanations are diverse in character, therefore a range of different theories (including rational choice theory and prospect theory), depending on the kind of explanation is considered more appropriate than one all-embracing theory. Keywords: cost overruns, explanations, large-scale projects, theoretical embeddedness, transportation infrastructure 3 Introduction Investments in infrastructure are a considerable burden on a country’s gross domestic product (GDP). For example, in 2005 the Dutch government invested about 8 billion euros (CBS, 2005 in KIM, 2007) in infrastructure, amounting to 1.55% of GDP. This is of even greater concern if the inefficient allocation of financial resources as the result of decisions based on misinformation are recognised (Flyvbjerg, 2005b, De Bruijn and Leijten, 2007).
    [Show full text]
  • How to Cite Complete Issue More Information About This
    Revista Finanzas y Política Económica ISSN: 2248-6046 ISSN: 2011-7663 Universidad Católica de Colombia Peña, Víctor Alberto; Gómez-Mejía, Alina Effect of the anchoring and adjustment heuristic and optimism bias in stock market forecasts Revista Finanzas y Política Económica, vol. 11, no. 2, 2019, July-December, pp. 389-409 Universidad Católica de Colombia DOI: https://doi.org/10.14718/revfinanzpolitecon.2019.11.2.10 Available in: https://www.redalyc.org/articulo.oa?id=323564772010 How to cite Complete issue Scientific Information System Redalyc More information about this article Network of Scientific Journals from Latin America and the Caribbean, Spain and Journal's webpage in redalyc.org Portugal Project academic non-profit, developed under the open access initiative Finanz. polit. econ., ISSN: 2248-6046, Vol. 11, N.° 2, julio-diciembre, 2019, pp. 389-409 http://doi.org/10.14718/revfinanzpolitecon.2019.11.2.10 Effect of the anchoring and Víctor Alberto Peña* Alina Gómez-Mejía** adjustment heuristic and optimism bias in stock market Recibido: 21 de agosto de 2019 forecasts Concepto de evaluación: 30 de octubre de 2019 ABSTRACT Aprobado: 12 de diciembre de 2019 Stock market forecasting is an important and challenging process that influences investment decisions. This paper presents an experimental design Artículo de investigación that aims to measure the influence of the anchoring and adjustment heuristic © 2019 Universidad Católica de Colombia. and optimism bias in these forecasts. Facultad de Ciencias The study was conducted using information from the S&P MILA Pacific Económicas y Administrativas. Alliance Select financial index; this was presented to 670 students from the cities Todos los derechos reservados of Concepción (Chile), Cali (Colombia), and Lima (Peru).
    [Show full text]
  • A Proposal to Study the Effect of Optimism, Overconfidence, and the Planning Fallacy on Lawyers’ Ability to Secure Favorable Results for Clients
    University of Pennsylvania Carey Law School Penn Law: Legal Scholarship Repository Prize Winning Papers Student Papers 2017 A Proposal to Study the Effect of Optimism, Overconfidence, and the Planning Fallacy on Lawyers’ Ability to Secure Favorable Results for Clients Chelsea Berry University of Pennsylvania Follow this and additional works at: https://scholarship.law.upenn.edu/prize_papers Part of the Legal Ethics and Professional Responsibility Commons Repository Citation Berry, Chelsea, "A Proposal to Study the Effect of Optimism, Overconfidence, and the Planning allacyF on Lawyers’ Ability to Secure Favorable Results for Clients" (2017). Prize Winning Papers. 7. https://scholarship.law.upenn.edu/prize_papers/7 This Prize Paper is brought to you for free and open access by the Student Papers at Penn Law: Legal Scholarship Repository. It has been accepted for inclusion in Prize Winning Papers by an authorized administrator of Penn Law: Legal Scholarship Repository. For more information, please contact [email protected]. Chelsea Berry A Proposal to Study the Effect of Optimism, Overconfidence, and the Planning Fallacy on Lawyers’ Ability to Secure Favorable Results for Clients I. Introduction Lawyers are notoriously risk averse. The media and popular culture have an abundance of references to lawyers serving reality checks to overambitious clients, often labeling lawyers as “deal breakers” or “obstructionists.”1 Risk aversion may come with pessimism or cautious decision-making. Lawyers may also be seen, by some, as professional
    [Show full text]
  • Reduce Optimism Bias Introduction to Reference Class Forecasting
    Transactions, SMiRT-25 Charlotte, NC, USA, August 4-9, 2019 Division XII REDUCE OPTIMISM BIAS INTRODUCTION TO REFERENCE CLASS FORECASTING James Michael Devine1 CCP 1 Director, International Business Development, Project Time & Cost LLC, Atlanta, GA, USA, [email protected] ABSTRACT Project planning often contains several elements of optimism bias. Even when project planners are aware of the potential to do so, overly optimistic cost estimates and schedules are produced. Also, all too often, risks tend to be overlooked or downplayed during the planning process. The tendency to “bake in” overly optimistic outcomes into project planning, per several well-known, analytical studies, is simply human nature. Information, supporting this tendency is presented within this paper. Several different approaches and guidance have been developed and deployed by different professional organizations and government agencies to help alleviate overly optimistic project planning. This paper introduces the concept of Reference Class Forecasting (RCF) which, when properly implemented, can improve project planning and more accurately predict final project outcomes. To implement RCF it is important to identify relevant past projects, or applicable elements of past projects, that can be used as reference points or benchmarks. Once these relevant benchmarks have been established and converted into a meaningful reference class distribution, project planners can use these known, external elements, for comparison to help alleviate optimism bias in their project plans. Recognition and treatment of project risk is also improved through this process. This methodology can produce a project plan that is more likely to approximate a project’s outcome. INTRODUCTION One might consider that optimism lies at the very core of human nature and the primary factor contributing to the survival of the species.
    [Show full text]
  • Reference Class Forecasting Guidelines for Use in Connection with National Roads Projects Table of Contents
    Reference Class Forecasting Guidelines for use in connection with National Roads Projects Table of Contents Page Section 1 1 Background to Reference Class Forecasting Section 2 9 Development of National Roads Reference Class Section 3 17 Reference Class Forecasting for National Roads Schemes Bibliography 20 Appendix A 21 Schemes included in Reference Classes Appendix B 23 Reference Class Curves for National Roads Projects Appendix C 25 Worked Examples Foreword The government is seeking to transform the way we both deliver and use our infrastructure so we can extract the maximum possible value from our investment and so bring about real change for people, communities and our economy. In response to updated guidance in the Public Spending Code, Transport Infrastructure Ireland (TII) is transforming its cost forecasting process both through an update to TII’s Cost Management Manual (for publication in 2020) and the preparation of this document providing guidance on the use of reference class forecasting in connection with Irish national roads projects. TII has been involved in the delivery of new national road schemes since the formation of the National Roads Authority in 1994 and thus has a wealth of data available to it from previous Irish national roads projects which is suitable for use in generating specific reference class curves appropriate to Irish national roads projects. As reference class forecasting, as a concept, evolved from issues with cost estimation identified through behavioural science, it is appropriate that the first section of these guidelines addresses the background to reference class forecasting and provides the context for its use. While it is acknowledged that much of this context is based on international experience and would not truly reflect TII’s experience on Irish national roads projects, it was felt that findings from a blend of international experience would provide the reader with an introduction to the concepts underlying reference class forecasting.
    [Show full text]
  • What Are the Causes and Cures of Poor Megaproject Performance? a Systematic Literature Review and Research Agenda
    What Are the Causes and Cures of Poor Megaproject Performance? A Systematic Literature Review and Research Agenda Juliano Denicol1, Andrew Davies2, and Ilias Krystallis1 Abstract This systematic literature review explores the megaproject management literature and contributes by improving our understanding of the causes and cures of poor megaproject performance. The review analyzes 6,007 titles and abstracts and 86 full papers, identifying a total of 18 causes and 54 cures to address poor megaproject performance. We suggest five avenues for future research that should consider examining megaprojects as large-scale, inter-organizational production systems: (1) designing the system architecture; (2) bridging the gap with manufacturing; (3) building and leading collaborations; (4) engaging institutions and communities; and (5) decomposing and integrating the supply chain. Keywords megaproject management, performance, problems, solutions, failure, success 1School of Construction and Project Management, University College London, UK 2Science Policy Research Unit, University of Sussex Business School, UK Corresponding author(s): Juliano Denicol, School of Construction and Project Management, University College London, Gower Street, London WC1E 6BT, UK; [email protected] 1 Introduction Megaprojects are the delivery model used to produce large-scale, complex, and one-off capital investments in a variety of public and private sectors. With a total capital cost of US$1 billion or more, megaprojects are extremely risky ventures, notoriously difficult to manage, and often fail to achieve their original objectives (Altshuler & Luberoff, 2003; Flyvbjerg, Bruzelius, et al., 2003; Merrow, 2011; Priemus & Van Wee, 2013). In 2013, McKinsey suggested that US$57 trillion would be spent on infrastructure investment between 2013 and 2030 (McKinsey Global Institute, 2013).
    [Show full text]
  • A Review of Optimism Bias, Planning Fallacy, Sunk Cost Bias and Groupthink in Project Delivery and Organisational Decision Making
    Behavioural Insights Team A review of optimism bias, planning fallacy, sunk cost bias and groupthink in project delivery and organisational decision making Accompanying An Exploration of Behavioural Biases in Project Delivery at the Department for Transport Client: Department for Transport Date: July 2017 1 © Behavioural Insights Ltd Contents Introduction ....................................................................................................................................... 3 How we make decisions and judgements ........................................................................................ 3 Optimism bias and the planning fallacy .............................................................................................. 5 How prevalent is the planning fallacy? ............................................................................................ 5 Causes of optimism bias and the planning fallacy ........................................................................... 6 Self-serving biases..................................................................................................................... 6 Illusion of control ....................................................................................................................... 7 Confirmation bias ...................................................................................................................... 8 Perception of risk ......................................................................................................................
    [Show full text]
  • Policy and Planning for Large Infrastructure Projects: Problems, Causes, Cures
    WPS3781 Public Disclosure Authorized Policy and Planning for Large Infrastructure Projects: Problems, Causes, Cures By Public Disclosure Authorized Bent Flyvbjerg Public Disclosure Authorized World Bank Policy Research Working Paper 3781, December 2005 The Policy Research Working Paper Series disseminates the findings of work in progress to encourage the exchange of ideas about development issues. An objective of the series is to get the findings out quickly, even if the presentations are less than fully polished. The papers carry the names of the authors and should be cited accordingly. The findings, interpretations, and conclusions expressed in this paper are entirely those of the authors. They do not necessarily represent the view of the World Bank, its Executive Directors, or the countries they represent. Policy Research Working Papers are available online at http://econ.worldbank.org. Public Disclosure Authorized Page 1 of 32 1. Introduction * For a number of years my research group and I have explored different aspects of the planning of large infrastructure projects (Flyvbjerg, Bruzelius, and Rothengatter, 2003; Flyvbjerg, Holm, and Buhl, 2002, 2004, 2005; Flyvbjerg and Cowi, 2004; Flyvbjerg, 2005a, 2005b).1 In this paper I would like to take stock of what we have learned from our research so far. First I will argue that a major problem in the planning of large infrastructure projects is the high level of misinformation about costs and benefits that decision makers face in deciding whether to build, and the high risks such misinformation generates. Second I will explore the causes of misinformation and risk, mainly in the guise of optimism bias and strategic misrepresentation.
    [Show full text]
  • Planning Fallacy Or Hiding Hand: Which Is the Better Explanation?
    Planning Fallacy or Hiding Hand: Which Is the Better Explanation? By Bent Flyvbjerg* Full reference: Bent Flyvbjerg, 2018, "Planning Fallacy or Hiding Hand: Which Is the Better Explanation?" World Development, vol. 103, March, pp. 383-386. DOI: 10.1016/j.worlddev.2017.10.002. URL: http://www.sciencedirect.com/science/article/pii/S0305750X17303169?via%3Dihub Draft 3.1, all rights reserved Abstract: This paper asks and answers the question of whether Kahneman's planning fallacy or Hirschman's Hiding Hand best explain performance in capital investment projects. I agree with my critics that the Hiding Hand exists, i.e., sometimes benefit overruns outweigh cost overruns in project planning and delivery. Specifically, I show this happens in one fifth of projects, based on the best and largest dataset that exists. But that was not the main question I set out to answer. My main question was whether the Hiding Hand is "typical," as claimed by Hirschman. I show this is not the case, with 80 percent of projects not displaying Hiding Hand behavior. Finally, I agree it would be important to better understand the circumstances where the Hiding Hand actually works. However, if you want to understand how projects "typically" work, as Hirschman said he did, then the theories of the planning fallacy, optimism bias, and strategic misrepresentation – according to which cost overruns and benefit shortfalls are the norm – will serve you significantly better than the principle of the Hiding Hand. The latter will lead you astray, because it is a special case instead of a typical one. Keywords: The principle of the Hiding Hand, the planning fallacy, optimism bias, wider development impacts, dynamic linkages, cost-benefit analysis, project management, development economics, behavioral science, Albert O.
    [Show full text]
  • Masterarbeit / Master's Thesis
    MASTERARBEIT / MASTER’S THESIS Titel der Masterarbeit / Title of the Master‘s Thesis "Rational enough to know better, confident enough to ignore anyway" ‘The role of overconfidence in group target estimations’ verfasst von / submitted by Karim Julian Gharbi, BSc angestrebter akademischer Grad / in partial fulfilment of the requirements for the degree of Master of Science (MSc) Wien, 2018 / Vienna 2018 Studienkennzahl lt. Studienblatt / A 066 914 degree programme code as it appears on the student record sheet: Studienrichtung lt. Studienblatt / Masterstudium degree programme as it appears on Internationale Betriebswirtschaft the student record sheet: Betreut von / Supervisor: Ass.-Prof. Steffen Keck, PhD Acknowledgements In deep gratitude for the guidance, support and patience from my former colleagues of the Strategic Management Department, I’d like to say thank you. To my beloved ones - this is (finally) for you! i "What a piece of work is man, How noble in reason, how infinite in faculty, In form and moving how express and admirable, In action how like an Angel, In apprehension how like a god, The beauty of the world, The paragon of animals." William Shakespeare - Hamlet, Act II, scene 2 (1986) ii Abstract Aligned with the principles of behavioural economics, the aim of this thesis is to detect irrationalities in human behaviour that lead to ‘non-optimal’ decisions. The praised picture of mankind, as portrayed by the excerpt of Hamlet on the previous page, thereby gets gradually disassemble by examining cognitive restrictions in our daily thought processes. Making plausible and realistic predictions about the future events is not only one of the more prominent fallacies, but also represents the cornerstone of this study.
    [Show full text]
  • The Case of Cost Overruns in Project Management
    buildings Review When Parallel Schools of Thought Fail to Converge: The Case of Cost Overruns in Project Management Aaron Anil Chadee 1,* , Xsitaaz Twinkle Chadee 2 , Indrajit Ray 1 , Abrahams Mwasha 1 and Hector Hugh Martin 3 1 Department of Civil and Environmental Engineering, The University of the West Indies, St. Augustine, Trinidad and Tobago; [email protected] (I.R.); [email protected] (A.M.) 2 Department of Physics, The University of the West Indies, St. Augustine, Trinidad and Tobago; [email protected] 3 School of Civil Engineering and Built Environment, Liverpool John Moores University, Liverpool 72046, UK; [email protected] * Correspondence: [email protected] Abstract: This paper investigates the conflicting and contrasting views between two prominent schools of thought (SOT), the conventional project management empirical school and the incoming behavioural and psychological sciences, to explain the cost overrun phenomenon in transportation infrastructure projects. Although theories within these SOTs seem to coexist and are used interchange- ably, there exists a widening knowledge gap that leads to conflicting and contrasting ideological views. In this paper, we contend that there is a lack of a cross-fertilisation mechanism to fuse and co-join contemporary theories on cost overruns. This has led to the encapsulation and fragmented adhocracy in theory building. Utilising a critical review approach, this study proposes the concepts of ideological distancing and encapsulation between “empiricism” and “behavioural” SOTs as the focus of analyses for understanding the root causes of cost overruns in project studies. The study Citation: Chadee, A.A.; Chadee, X.T.; showed that the extant debate on cost overruns is limited and divergent, effectively contributing Ray, I.; Mwasha, A.; Martin, H.H.
    [Show full text]