Initial Environmental Examination

November 2011

India: North Eastern Roads Project MLN-1: Garodhaba to Dalu

Prepared by the Ministry of Development of North Eastern Region, Government of for the Asian Development Bank.

ABBREVIATIONS

ADB - Asian Development Bank CPCB - Central Pollution Control Board CRRI - Central Road Research Institute DoE - Department of Environment EA - Executing Agency EFRC - Environment Friendly Road Construction EIA - Environmental Impact Assessment EMMP - Environmental Mitigation and Monitoring Plan GDP - Gross Domestic Product GoI - Government of India IEE - Initial Environmental Examination IRC - Indian Road Congress MDONER - Ministry of Development of North Eastern Region MDRs - Major Roads MoEF - Ministry of Environment and Forests MoRT&H - Ministry of Road Transport and Highways MSL - Mean Sea Level MW - Mega Watt NEC - North Eastern Council NER - North Eastern Region NGO - Non Government Organization NH - National Highway NOx - Oxides of Nitrogen NSDP - Net State Domestic Product PIU - Project Implementation Unit PWD - Public Works Department ROW - Right of Way SPM - Suspended Particulate Matter SO2 - Sulphur Dioxide SSI - Small Scale Industries SPCB - State Pollution Control Board TA - Technical Assistance TOR - Terms of Reference WHO - World Health Organisation

This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Contents I. INTRODUCTION 1 II. POLICY, LEGAL, AND ADMINISTRATIVE FRAMEWORK 3 III. DESCRIPTION OF PROJECT 5 A. The North Eastern State Roads Project 5 B. The MNL-1 Subproject: Garodaba to Dalu (NH51) 6 IV. DESCRIPTION OF THE ENVIRONMENT 8 A. Physical Environment 8 B. Ecological Environment 10 C. Socio Economic Environment 12 V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 19 A. Identification and Assessment of Impacts 19 B. Environmental Impacts to be Taken into Account During Construction 27 C. Environmental Effects Related to Operation 41 D. Potential Environmental Enhancement /Protection Measures 42 VI. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION 43 VII. GRIEVANCE AND REDRESS MECHANISM 44 VIII. ENVIRONMENTAL MANAGEMENT PLAN 45 A. Summary of Impacts 45 B. Impacts, Mitigation and Institutional Responsibilities 45 C. Specific Environmental Management Plan 45 D. Environmental Monitoring Plan 47 E. Institutional Requirements 47 F. Proposed Environmental Budget 50 IX. CONCLUSION AND RECOMMENDATION 51

Appendixes:

A. Location of Quarries 52 B. Consultations 55 C. Photographs of Consultations 57 D. Environmental Management Plan 58 E. Environmental Monitoring Plan 65 F. Details of Training Program 67 G. Environmental Management Plan Budget 68 H. Rapid Environmental Assessment Checklist 71 I. Wildlife Clearance 73

EXECUTIVE SUMMARY

1. The environmental screening of MLN-1: Garobadha to Dalu revealed the proposed improvement of the road section will not result to significant adverse environmental impacts, and all significant impacts are site-specific and can be addressed through proven mitigation measures. This road section was classified as Category B and an initial environmental examination was prepared and documented in this report.

2. MLN-1: Garobadha to Dalu (NH51) is located on West District, Meghlaya, and a section of a state highway covering a total length of 98.5 km, The road passes through plain / rolling / low hill terrain, having steep gradients in hilly terrain. The existing carriageway is single lane and the proposed carriageway is intermediate lane. The topography of the region is mixed type. The terrain is plain to undulating in Garobadha, and undulating to hilly towards Dalu. The land use is mostly agricultural with some pockets of community forests on hillocks. These forests are owned and maintained by communities and does not have protected status. Some portion of Project road is covered by vegetation. The right of way (ROW) is not demarcated on the road and as identified from private properties limits, varies in open areas from 10 m to 20 m. and narrows to 8m-12m in built up areas.

3. The significant environmental impacts attributable to the upgrading of the road sections pertains to tree cutting for the proposed widening; intersection with elephant corridors, temporary deterioration of ambients during construction phase from land clearing, ground shaping, and quarry and camp operations; and community and occupational health and safety. These impacts will be mitigated through compensatory afforestation; timing of construction activities to minimize fauna distrubance; control of noise, dust, wastewater, fuel combustion emissions, and construction debris generation through good construction practices; and implementation of road safety measures to separate road users from active construction fronts.

4. The assessment of the potential conflict between the road upgrading, its users, and elephant corridor revealed that there will be no significant impacts as a road already exists and no new road construction is taking place inside pristine or government reserved forests. The project area is largely made up of agricultural fields and settlements, hence additional impacts from road strengthening will be insignificant. Currently there are no information or warning signboards on the existence of elephants along the road. Under the project, signboards will be placed at all locations where elephants cross over. Hence, the awareness of the vehicle drivers and local people on elephant crossings will be enhanced. The Divisional Forest Office did not require wildlife or environmental clearance for the project.

5. During operation stage, the main impacts are increase in mobile emissions, road safety to motorist, pedestrian and animals. Road safety measures will be implemented as per IRC guidelines. Road safety apputenances like information, regulatory and warning signs copuled with crash barriers will reduce serious injuries to road users. Adequate cross drains and side drains and their proper maintenance will be implemented to avoid localised flooding.

6. Several consultations were organized during the project preparation to engage major stakeholder representatives to incorporate their concerns in the overall design. These involved officials of executing agencies, PWD, District Rural Development Officials, Forest department officials, likely affected persons and village heads in the project area. Most of the people interviewed strongly support the project.

7. The PWD, Government of , through its Project Implementing Unit (PIU), is the Executive Agency of the Project. will ensure the effective implementation of the environmental management plan. There is a need for the PIU to organize its environmental unit to provide close support to the Project Director to ensure the contractors maintain environmental compliance. To provide regular monitoring information and technical advice to the PIU are the supervision consultant and the contractors environment and social officer.

8. This initial environmental examination (IEE) ascertains that upgrading the MLN-1: Garobadha to Dalu (NH51 is unlikely to cause any significant environmental impacts. Few impacts were identified attributable to the proposed subproject, all of which are localized and temporary in nature and can be easily mitigated with minor to negligible residual impacts. No additional studies or need of undertaking detailed EIA is envisaged at this stage.

I. INTRODUCTION

1. The North Eastern Region (NER) is bordered , Bhutan, the People’s Republic of China, Myanmar, and Nepal. It represents 8% of India’s geographic area. It has a population of about 54 million. The region consist of 8 states, namely: , , Meghalaya, , , and Tripura. The NER is connected to the rest of the country through the narrow Siliguri Corridor in .

2. Meghalaya is a land-locked state in the eastern corner of the country having a geographical area of about 22,429 sq km. The state is bounded on the north, east and west by Assam and south by Bangladesh. The population of the state stood at 2.31 million in 2001 of which 80% is rural. The topography is hilly with its bountiful vegetation and deep terrain that presents a beautiful landscape of variety of trees.

3. Roads are the major means of getting to and within the state. They are a critical input to the growth of all sectors. The length of roads is reported to be about 7,860 km, 80% of which are rural roads and other district roads. The existing road network suffers from weak pavement and weak and narrow bridges and culverts. There are several semi-permanent timber (SPT) bridges even on main roads. However, there is comparatively better attention to routine maintenance. The riding quality of main roads is reported to be fair to good except in short stretches. The National Highway network covers 799 km of which 187 km is under the jurisdiction of Border Roads Organisation (BRO) for its development and maintenance. The Public Works Department (roads and buildings) is the principal agency in the state responsible for development and maintenance of roads.

4. This road improvement will be pursued in an environmentally congenial manner that avoids, minimizes or mitigates adverse environmental impacts. This IEE contains the approach, evaluation, findings, and recommendation of the environmental assessment for MLN-1: Garobadha to Dalu, in the State of Assam, India, in compliance to the ADB Safeguard Policy Statement 2009. This road section is a component of the Loan 2770 (IND) North Eastern State Roads Project (NESRP) which aims to upgrade and improve priority state roads in the northeast region. The NESRP is classified as environment category “B.” MLN-1: Garobadha to Dalu (NH51) is located on , Meghlaya, and a section of a state highway covering a total length of 93.3 km, The road passes through plain / rolling / low hill terrain, having steep gradients in hilly terrain. The Garo Hills are well known for its rich biodiversity due to large tracks of primary forest.

5. This report has 9 sections following the prescribed IEE outline of the Bank and starts with this introduction and followed by:

• Policy, Legal, and Administrative Frameworks section summarizing the national and local legal and institutional frameworks that guided the conduct of the assessment • Description of the Project and the Road Section presenting the key features and components of the proposed project • Description of the Environment section discussing the relevant physical, biological, and socioeconomic features that may be affected by the proposed project. • Anticipated Environmental Impacts and Mitigation Measures section presenting the environmental assessment of likely positive and adverse impacts attributed to the proposed project and concomitant mitigation measures. 2

• Information Disclosure, Consultation, and Participation section describing the the consultation process undertaken during the environmental examination and its results, their consideration in the project design, and manner of compliance to the ADB’s Publication Policy and related national laws. • Grievance and Redress Mechanism section describing the formal and informal redress procedures for registering, resolving, and reporting complaints. • Environmental Management Plan section discussing the lessons from the impact assessment and translated into action plans to avoid, reduce, mitigate or compensate adverse impacts and reinforces beneficial impacts. This plan is divided into 3 sub- sections; mitigation, monitoring, and implementation arrangements. • Conclusion and recommendation section stating whether there is a need for further environmental assessment and highlights key findings and recommendations to be implemented by the borrower.

6. A companion of this IEE Report is a stand-alone Volume II – Generic Environmental Management Plan which contains mitigation and enhancement measures mainly in the form of good management practices in plant, campsite, debris, borrow area, and quarry area management. This generic management plan applies to all road sections to be upgraded under this loan.

3

II. POLICY, LEGAL, AND ADMINISTRATIVE FRAMEWORK

7. The legal framework of the country consists of several acts, notifications, rules and regulations to protect environment and wildlife. In 1976, the 42nd Constitutional Amendment created Article 48A and 51A, placing an obligation on every citizen of the country to attempt to conserve the environment. Specifically for the Project Roads, the following environmental laws and regulations are applicable:

Table II-1: Applicable Environmental National and State Requirements Sl. Activity Statute Requirement Competent Responsible Time No. Authority Agency for Required Obtaining Clearance Construction Stage (Responsibility: Contractor) 1 Establishing Water Act of Consent-for- State Pollution The 2-3 stone crusher, 1974, Air Act establishment Control Board Contractor months hot mix plant, of 1981, Noise wet mix plant Rules of 2000 and Diesel and Generator Sets Environmental Protection Action of 1986 and as amended 2 Operating Water Act of Consent-for- State Pollution The 2-3 stone crusher, 1974, Air Act operation Control Board Contractor months hot mix plant, of 1981, Noise wet mix plant Rules of 2000 and Diesel and Generator Sets Environmental Protection Action of 1986 and as amended 3 Use and India Explosive Explosive Chief The 2-3 storage of Act 1984 license for Controller of Contractor months explosive for use and Explosives quarry blasting storage work 4. Storage of fuel Manufacture Permission State Pollution The 2-3 oil, lubricants, storage and for storage of Control Board Contractor months diesel etc. at Import of hazardous or Local construction Hazardous chemical Authority camp Chemical (DM/DC) Rules 1989 5 Quarry State Minor Quarry Lease State The 2-3 operation Mineral Deed and Department of Contractor months Concession Quarry Mines and Rules, The License Geology Mines Act of 1952, Indian Explosive Act of 1984, Air Act of 1981 4

Sl. Activity Statute Requirement Competent Responsible Time No. Authority Agency for Required Obtaining Clearance and Water Act of 1974

6 Extraction of Ground Water Permission State Ground The 2-3 ground water Rules of 2002 for extraction Water Board Contractor months of ground water for use in road construction activities 7 Use of surface - Permission Irrigation The 2-3 water for for use of Department Contractor months construction water for construction purpose 7 Engagement of Labour Act Labour Labour The 2-3 labour license Commissioner Contractor months

8. Before the start of civil works for the any project roads the state PWD must obtain necessary clearances /permits from the regional office of Ministry of Environment and Forests and State pollution control board. The ADB categorizes projects based on their potential environmental impacts. This project has been classified as Category B according to the ADB Fact-Finding Mission undertaken in the months of May and July 2004 and affirmed during the November 2011 mission. The Rapid Environment Assessment (REA) checklist for this road section is appended as Appendix H.

5

III. DESCRIPTION OF PROJECT

A. The North Eastern State Roads Project

9. The proposed “North Eastern State Roads Project” is a multitranche financing facility (MFF) that will: improve about 430 kilometers (km.) of priority roads in six states, namely: Assam, Manipur, Meghalaya, Mizoram, Sikkim, and Tripura in the northeastern region (NER) of India; and provide capacity building support to the executing agencies, the Ministry of Development of North Eastern Region (MDONER) and the state public works departments (PWDs) or its equivalent in the six project states. The investment program will target the secondary road network and aim to enhance the performance of state roads sector in NER through investment project implementation and dedicated capacity building measures. The improved secondary road network will provide important linkage between the primary and tertiary road networks in the region, for which there are ongoing national programs for improvement1.

Table III-1: Proposed Roads Under Multitrance Financing Facility North Eastern State Roads Investment Project Road Section Tranche/Road Name State Length Package Code Tranche 1 SK-01 Melli-Nayabazaar Sikkim 9.5 SK-02 Nayabazaar-Namchi Sikkim 20 AS-CW1 Bilaspara-Fakiragam Assam 16.2 AS-37C Kalitakuchi-Barpeta Assam 58.5 ML-CW1 Garobadha-Dalu Megalaya 93.3 Sub-Total 202.4 Tranche 2 TR-02 Udaiphur-Melaghar Tripura 20.3 MZ-CW2 Serchhip-Buarpi Mizoram 55 MN-CW6 Bishnupur-Thoubal- Manipur 128.57 Kasom-Khullen AS-CW3 Barma-Tamulpur Assam 28.9 Sub-Total 232.7 Total 430.7

10. The Public Works Department is the principal agency in the state responsible for development and maintenance of roads. Settlements are scattered and many rural communities are still far from the nearest road. In these areas, goods are brought in, or taken out, either by animal or back loading. Guwahati is the major commercial hub for the state as well as for the north eastern region.

11. The proposed “North Eastern State Roads Project” is a joint initiative of the Government of India and ADB. Funding for the technical assistance (TA) is provided jointly by GOI, through the Executing Agency (EA), namely the Ministry of Development of North Eastern Region (MDONER), and ADB. A Technical Assistance Agreement was signed on 20 December 2004 between GOI and ADB. The project is intended to assist the states of the north eastern region of India to study the feasibility of developing the respective road networks and improving national

1 “Proposed Multitrance Financing Facility and Administration of Technical Assistance Grant India: North Eastern State Roads Investment Program” Report and Recommendation of the President to the Board of Directors. June 2011. 6

and sub-regional connectivity with the objective of enhancing mobility and trade. The project will also assist the states to develop the capacity of road sector institutions to increase productivity of the road assets.

12. The primary focus of the assistance will be on, but not be limited to: (i) prioritization of national highways, state highways, and major district roads to be improved; (ii) determination of the feasibility of an investment project for improvement of priority state roads and bridges; and (iii) preparation of an institutional strengthening action plan comprising immediate action to support implementation of the proposed project.

B. The MNL-1 Subproject: Garodaba to Dalu (NH51).

13. MLN-1: Garobadha to Dalu (NH51) is located on West Garo Hills District, Meghlaya, and a section of a state highway covering a total length of 93.3 km, The road passes through plain / rolling / low hill terrain, having steep gradients in hilly terrain. The existing carriageway is single lane and the proposed carriageway is intermediate lane. The topography of the region is mixed type. The terrain is plain to undulating in Garobadha, and undulating to hilly towards Dalu. The land use is mostly agricultural with some pockets of community forests on hillocks. These forests are owned and maintained by communities and does not have protected status. Some portion of Project road is covered by vegetation. The right of way (ROW) is not demarcated on the road and as identified from private properties limits, varies in open areas from 10 m to 20 m. and narrows to 8m-12m in built up areas. The location map of the Project road is shown in succeeding Figure.

7

Garobadhaba

Dalu (Barengapara )

Figure III-1: Location map of Project road from Garobadha to Dalu Barengpara)

8

IV. DESCRIPTION OF THE ENVIRONMENT

14. A brief description of the existing environment, including its physical and ecological resources, economic development of the region, and issues relating to quality of life are presented in this section. Broad aspects on various environmental parameters like geology, soil, topography, climate, land use, water resources, water quality, air quality, noise quality, tourism, and cultural resources which are likely to be affected by the proposed road improvement project are covered.

A. Physical Environment

1. Topography, Geology, and Soil

15. Located along the hills of eastern sub-Himalayas is the Meghalaya plateau, northeast of India. The highest peak in the state is the Shilling k with an altitude of 1,956m. It extends about 300 kilometres in length and about 100 kilometres in breadth. It is bounded on the north by Goalpara, Kamrup, and Nowgong , on the east by Karbi Anglong and North Cachar Hills districts, all of Assam, and on the south and west by Bangladesh. The state received an annual average rainfall of 1,200 cm and it varies with altitude. The Figure below shows the typical terrain of project road. Geographically the state lies in the Eastern Himalayas between 20010’ to 26005’ North latitude and 85049’ to 92052’ East longitude, and sprawling over 22,429 sq.km.

Figure IV-1: Typical Hilly Terrain through Project Road

16. The plateau is standing as a watershed between the Surma Valley of Bangladesh on the South and the Brahmaputra Valley on the North. Several rivers and a network of their tributaries and lateral streams dissect the plateau. The state is broadly divided into three physiographic zones: (i) the Central Plateau Region between 900m-2,000m elevation: (ii) Sub-montane region in continuation with the Central Plateau below 900m which gradually merges with the plains in the West and North, and (iii) Border region which stretches south-wards abruptly from the Central Plateau to the plains in Bangladesh.

17. Geologically the State is formed by: (a) Archean Gneissic Complex with Acid intrusive; (b) Group of Rocks (mostly Quartzite) usually friable, Schists, Conglomerates; (c)

9

Granite rocks; (d) Lower Gondwana rocks; (e) Sylhet Traps; (f) Cretacious - tertiary sediments viz Khasi Group, (Jadugata and Mahadek formation), Garo Group (Simsang, Baghmara, Chengapara formation). These sediments consist of dominantly sandstone, limestone, silt stone, shale and pebbles, clays, and conglomerates. The sedimentary rocks are in a complex form. The climate, vegetation, relief and parent material constituting the ecosystem influence significantly the pedogenesis resulting in the development of different kinds of soils.

18. The drainage pattern of the State represents a most spectacular feature revealing extraordinary straight courses of the rivers and streams evidently along the joints and faults. The magnificent gorges scooped out by the rivers in the southern Khasi and Jaintia Hills are the result of massive headward erosion by antecedent streams along joints of the sedimentary rocks over the block, experiences relatively great uplift. Westward in the Garo Hills, the consequent streams are mostly controlled by the structures, faults and monoclines in the sedimentary rock. The northern part of the plateau is devoid of any sedimentary cover is marked by long incisive valley formed due to head ward erosion along joints in the gneissic rocks and granites. The limestone-covered country over southern Garo, Khasi and Jaintia Hills represent typical karst topography. The present physiographic configuration of the plateau was attained through different geological events since Melozonic to present day as indicated by polycyclic surface at various levels.

2. Climate

19. The region experiences tropical monsoonic climate, which varies from western to eastern parts of the plateau. The Garo Hills District has tropical climate characterized by high rainfall and humidity, generally warm summer and moderately cold winter. In contrast, the Khasi and Jaintia Hills have high rainfall, moderately warm summer and severe cold winter with periodic depression to below freezing point at higher elevated area. For the entire state, the mean summer temperature is 26° C and the mean winter temperature is 9° C. The mean annual rainfall varies from 2,000-4,000 mm with most rainfall occur during May to September. Maximum rainfall of 12,000 mm has been recorded in the southern slope of Khasi Hills along the Cherrapunjee-Mawsynram belt. The salient climatic features of the state are as follow:

• Average Annual Rainfall - 2000 mm to 4000 mm • Concentration of precipitation - May to September • Humidity - 79 to 96% • Cloudiness - Heavily clouded • Wind - Generally light except rainy season • Mean Temperature - Summer 260C - Winter 90C

3. Water Resources and Water Quality

20. The drainage pattern of the State reveals extraordinary straight courses of the rivers and streams evidently along the joints and faults. The gorges scooped out by the rivers in the southern Khasi and Jaintia Hills are the result of massive headward erosion by antecedent streams along joints of the sedimentary rocks over the block, experiences relatively great uplift. Westward in the Garo Hills, the consequent streams are mostly controlled by the structures, faults and monoclines in the sedimentary rock. The northern part of the plateau devoid of any sedimentary cover is marked by long incisive valley formed due to head ward erosion along joints in the gneissic rocks and granites. The limestone-covered country over southern Garo, 10

Khasi and Jaintia Hills represent typical karst topography. The present physiographic configuration of the plateau was attained through different geological events since Melozonic to present day as indicated by polycyclic surface at various levels. Eight main rivers in the north and five main rivers in the south drain the State. Rivers of north and south are tributaries of Brahmaputra and Meghna, respectively.

21. The ground water aquifers in the region occur in sediments and fractured rocks. Springs are either seasonal or perennial and often used for irrigation and drinking purposes. There are a number of hot springs in the region used by the local communities for domestic and agricultural purposes and visiting tourists.

22. The surface water quality in the region is reported to be within the permissible limits and confirmed visually during the site visits. There are no reports of any water born decease in the region. People are using this water for drinking purpose without any treatment. In case of ground water quality, it is generally good in entire north east region. People use ground water for domestic purposes within any treatment. Overall ground water quality is acceptable.

4. Air Quality

23. The ambient air quality in the state is good as reported by the SPCB except for few urban centres like Shillong and Tura. There are no major industrial activities in the State. Dust arising from unpaved surfaces, forest fire, smoke created by burning of fire woods for producing charcoal and domestic heating, and vehicular pollution are sources of pollution in the region. Firewood burning is the major contributor to air pollution as industrial and vehicular emissions are concentrated in the major commercial areas in state capitol.

24. Vehicular emission is not a major source of pollution in the state as the traffic density in the entire state is low. Pollution from vehicles is mainly due to use of low-grade fuel, low maintenance of vehicles, and the poor conditions of the roads.

5. Noise Quality

25. Noise pollution is minimal in the state and will remain at that level as the proposed road upgrading will result to smooth traffic flow and the projected traffic increase in not substantial. There are however, noise hotspots located at few commercial locations in Garobadha, Ampathi, Zikzak and Dalu.

B. Ecological Environment

1. Vegetation

26. The forests of Meghalaya can be broadly grouped under the tropical type and the temperate type, based on the altitude, rainfall, and dominant species composition. Tropical forests are found up to an elevation of 1,200m and with an average rainfall of about 100-250cm. There are numerous subtypes within this category such as evergreen, semi-evergreen, moist and dry deciduous forest. The temperate forests occupy the higher elevations about 1,000m, mostly along the southern slope of Khasi and Jaintia Hills. Rainfall here is very high 200-500cm with a severe winter during November to March.

11

27. The vegetation of the state is fairly well known. About 8,514 sq.km area is recorded as either reserved or protected forests, representing 38 % of total state area. Except for the reserved and protected forests in and around Shillong that are being managed by the department in coordination with the District Councils, all forest areas are subjected to shifting cultivation or slash and burn method especially in the Garo Hills. However, there are few pockets of undisturbed natural forests still in existence, comprising about 1,000 sq. kms.

28. The forests of Meghalaya are treasure house of valuable products such a timber, fuelwood, fodder, resin, tannin, gums, shellac, fibre, latex, essential oils, fats, edible fruits, honey, and a large number of medicinal plants. Meghalaya is well known for bay leaves and cinnamon. Morus alba, Quercus semiserrata, and a number of other tree species play a vital role in the economy of the State being the host plants for rearing of silk worms for sericulture.

29. Meghalayans in general are fond of decorating their courtyards with seasonal flowers and one comes across Dahlia, Canna, Gladiolus, Begonia, Tropaeolum, Aster, Polargonium, Antirrhinum, Crinum, Celosia, Kniphofia, Impatiens, Chrysanthemum, Petunias, Pansy, Calendula, Sweet peas, and Salvia. Many climbers like Bougainvillea, Rosa, Jasminum, are common. Multiplicity of orchids like Phaius, Dendrobium and Cymbidium spp. are also cultivated.

30. Among the important and recognised medicinal plants found and cultivated in Meghalaya are Ipecac, Rauvolfia serpentina, Cinchona, Abromine, Chaulmoogra Oil, Croton Oil, Eucalyptus, Castor Oil, Chiretta, Solanum khasianum, Casearia vareca, Zanthoxylum armatum, Hedyotis scandens, Paederia foetida, Salix alba, Anacardium occidentale, and Cinnamomum, Taxus baccata.

2. Wildlife and Protected Area Network

31. The State has rich wildlife and has wide network of protected area. In order to protect the rich flora and fauna of Meghalaya from the poachesr, the Government has established parks and sanctuaries. The largest of these is the Khangchendzonga National Park which encompasses an area of 1,784 sq km. It is bounded in the north by the Tent Peak and the ridge of the Zemu glacier while the eastern boundary is the ridge of the mountain.

32. The state’s protected area network comprises of one wildlife sanctuaries and two national parks. Recognizing the importance of this region as one of the biodiversity hot spots in the country, majority of the biodiversity rich areas has been placed inside the protected area network system as national park and sanctuary. The total area under the protected area network is 1.3% and that of under national parks is 1.2% Details on the forest area, forest cover and area under protected areas is presented succeeding Table.

Table IV-1: Protected Areas in Meghalaya National Parks Area in Hectare Balphakram National Park 220 47.48 Wildlife Sancturies Nongkhyllen Wildlife Sanctuary 29 Reserved Forest 9494 Protected Forest 15567 12

33. Meghalaya is considered by many biologists to have been the gateway through which many species of Indo-Chinese origin, particularly mammals, migrated to Peninsular India. It is also said that about 50% of the total number of mammal genera found in the entire Indian sub- continent can be seen in Meghalaya and its adjoining states in the North-East. Out of the above, nine genera of mammals, such as Tupaia, Rhizomys, Cannomys, Chiropodomys, and Micromys are found only in Meghalaya and its adjacent areas.

34. Some of the most interesting animals found in Meghalaya are Hoolock - the only tailless ape in India, Golden Cat, Leopard Cat, Jungle Cat, Large Indian Civet, Binturong or Bear Cat, Himalayan Black Bear, Barking Deer, and Pangolin. Among the endangered birds are Black Nacked Crane (migratory), Blood Pheasant, Peafowl, Tibetan Snow Partridge, and Siberian Crane (migratory).

35. The project road passes through the stretches of unclassified private forests that are management by local forest management committees. Private forests were found on hillocks between chainage km 29 and km 38 and again between km 68 to km 72. The details land use is presented in the Table below.

C. Socio Economic Environment

1. Demography

36. Meghalaya is a land-locked state in the north eastern India with a population of 2.3 million, 80% of which lives in the rural areas. The human population density is 103 persons/km2 which is lower than the 149 persons/km2 density for the north eastern region. Sex ratio is higher at 975 against the 936 in the NER. The demographic feature of north eastern states is unique in that there are many recognized tribes inhabiting mostly the hill areas and each with distinct culture, ethos, and traditional knowledge systems. The three major tribes are Khasi, Garo and Jaintias. Majority of the people survive on subsistence economy based mainly on the agriculture, supplemented with limited horticulture, animal husbandry, and crafts/handloom. The Table below presents the demographic features of the North eastern region.

Table IV-2: Demographic Features of Meghalaya and North Eastern Region (2001 census) Area (sq. Population State km) Rural Urban Total Density Sex Ratio Meghalaya 22429 1853457 452612 2306069 103 975 NE Region 262179 33008703 5809395 39041167 149 936 All India 3287263 741660293 285354954 1027015247 312 933 Source: 1) Census of India, 2001 (Provisional), 2) Statistical Abstract of State Governments, Directorate of Economics and Statistics, 3) Where do we stand in 2003, Meghalaya & North East and India & The World, Directorate of Economics & Statistics,

37. The Gross State Domestic Product of the state was Rs.32913.6 million in 1999-2000. The East Khasi Hills is the major contributor in the state domestic income. A stagnant agriculture sector combined with poor industrial activity has severely limited employment opportunities outside the government. This has also put the government under fiscal stress as expenditure on wages and salaries including pensions and interest payments consume almost half of the total government expenditure.

13

2. Land Resources

38. The area available for land utilization in the state is about 22,409 sq.km out of the total geographical area of 22,429 sq.km. accounting for 95% percent of the total area. Major portion of the land use is under agriculture followed by forest cover with 38%. The succeeding Table presents the land use distribution of the NER.

Table IV-3: Land use pattern in North East Region

(in thousand hectare) Other Area Reporting Not uncultivated sown area for available land Gross Net more land Forest for excluding Fallow cropped area than State utilization area cultivation fallow land land area sown once Total Meghalaya 2240.9 950 220.2 620.6 231.6 247 206 41 2242.9 NE Region 21754.5 13379 3296.8 1624 913.6 5448.6 3891.1 1557.5 30110.6 Source: www.neportal.org (Directorate of Economics and Statistics, NE states and NEC, Shillong). Statistical Abstract (2001-02), Sikkim, Directorate of Economics and Statistics, NE States.

Table IV-4: Chainage wise Land use pattern along project road Chainage Existing Land use Remark From To 0.0 4.0 Residential /settlement Village area 4.0 7.0 Barren land with thin vegetation 7.0 13.0 Mixed residential with patches of agriculture and open land 13.0 16.0 Barren land with thin vegetation 16.0 17.5 Built up /residential area Village area 17.5 19.5 Barren land with thin vegetation 19.5 19.8 residential area 19.8 24.0 Barren /open land with thin vegetation 24.0 28.3 Mixed residential with patches of agriculture and open land 28.3 38.5 Private Forest on hillocks 38.5 38.8 Residential area Village area 38.8 47.0 Barren /open land with thin vegetation 47.0 51.0 Mixed residential with patches of agriculture and open land 51.0 62.7 Barren /open land with thin vegetation 62.7 65.4 Mixed residential with patches of agriculture and open land 66.0 72.0 Private Forest on hillocks 72.0 77.0 Barren /open land with thin vegetation

14

3. Agriculture and Forestry

39. Meghalaya has an agricultural economy with 80% of its total population depending entirely on agriculture for their livelihood. The principal crops grown are rice, maize, and cereals. Other important crops include jute, mesta, cotton, ginger, turmeric, and banana. Potato has become the cash crop in the state. Production of rice was over 179,000 tonnes in 2000-01. Fish farming has also developed in the state and a record production of about 6,200 tonnes was attained in 2000-01.

40. As mentioned earlier, about 38 percent area is under forest and presents a source of wealth and all out efforts is being implemented to reduce the cutting and felling of trees to restore the ecological balance. The Forest Department has taken up social forestry while the Soil Conservation Department is implementing afforestation programs in private forest area and barren lands of private owners in order to rejuvenate with vegetation. Construction of roads to inaccessible remote and interior villages has paved the way for exploitation of forest resources for commercial purposes due to the demand for industrial wood and other forest product mainly from outside the state.

4. Fisheries

41. The state has vast potential for fisheries from its rivers, streams, floodplain, wetlands, reservoirs, lakes, ponds, and paddy-cumfish culture. About 7 hectares of water are available for nursery and 38 hectare under rearing. Inland fish production for the year 2003-2004 was 160 tonnes while total fry and fingerling productions were 2.8 million and 0.6 million, respectively. The fish species commonly found in the region’s plain and river basins are Catla catla, Labeo rohita, Labeio calbase, Cirrihinus mirigale, Clarius, batrachus, Rita rita, Heteropneuptus fonilis, Notopterus nontopterus, N. Chitala, Macrobrachum rosenbergii, M. malconsoni, M. Chapral, Channa punetatus C. gaehua, C. striatus.

5. Transportation

42. Transportation is a key factor in the socio-economic development of any state. The state has no railway lines and water transport is also not feasible because the rivers are not navigable. Shillong, the state capital, is now linked by air with the rest of the country through Guwahati and Kolkata. In these circumstances, roads and road transport constitute the principal mode of transport in the state for carrying goods and passengers. The length of roads is reported to be about 7,860 km and about 80 % are rural and district roads.

6. Mineral Resources

43. The state has good deposits of coal, limestone, and clay. The inferred reserve of coal in the state is estimated to be about 640 million tonnes, limestone at 5,000 million tonnes, and clay at 6 million tonnes. Annual production of coal is around 5,000 tonnes, and limestone 0.6 million tonnes which are mainly used in cement factories and in local kilns for production of lime. Limestone is also exported outside the state and to Bangladesh for which roads need to be in good shape.

7. Industrial Situation

44. The state is industrially backward even though the state has good hydel power potential and supply of coal. Non-availability of cheap means of transport is also one of the factors

15

contributing to weak industrial base. There are only 36 registered manufacturing units engaged in food production, wood furniture, paper printing press, and non-metallic industries. The number of small scale units is 3270 (year 2000-01 data). The state is seized of the need to develop the small scale sector to take care of the unemployment problem.

8. Aesthetic and Tourism

45. The state is well known for its scenic beauty of mountains, hills and valleys and is attracting a large number of tourists for trekking, pilgrimage, and adventure. Capital place Shillong and , considered as the wettest place in the world attracts thousands of tourists annually.

9. Cultural Resources

46. The state has great cultural value. Festivals and cultural activities are being celebrated throughout the year in the state. Specific events are being organised by tribal communities i.e. Khasi, Garo and Jaintis, throughout the year. The department of cultural has taken various activities like promotion of art and culture, preservation of old and historical monuments. The state has great cultural value for Christians. Project road does not affect any historical places. However, there are few small Churches located within corridor of project. These will not be disturbed due to improvement work.

10. Energy and Electric Power Potential

47. The cascading rivers in the state provide favorable conditions for generation of hydel power. The most important hydel project in the state is Umiam Hydel installed in 1965 to harness the Great Umiam Khwan river at the beautiful reservoir known as Umiam lake. Its total capacity is 174 MW and it provides electricity to the whole NER. In the coal belt area of Garo hills in the East, the Nangal Bibra thermal project (8MW) provides electricity to eastern part of the state.

11. International Trade & Commerce

48. There are number of agreements between India and neighboring country to enhance the border trade. The Indo-Myanmar border trade agreement in 1994, border trade agreement between India and Bangladesh in 1972 is some of the agreements signed to develop the trade relations.

49. The north eastern region has the potential to emerge as a strategic base for domestic and foreign investors to tap the potential of the contiguous markets of People’s Republic of China, Myanmar, Lao PDR, Nepal, Bhutan and Tibet. This calls for converting the unauthorized trade into authorized trade, at the policy level as well as at the ground level. The BIMST-EC (Bangladesh-India-Myanmar-Sri Lanka-Thailand Economic Cooperation) initiative is creating an enabling environment for rapid economic development through identification and implementation of specific cooperation projects in the sectors of trade, investment and industry, technology, human resource development, tourism, agriculture, energy, infrastructure and transportation.

50. Various physical features along the project road are described in Table below.

16

Figure IV-1:Physical Features of Meghalaya

17

Figure IV-2: Mineral Map of Meghalaya

18

Figure IV-3: Forest Map of Meghalaya

19

V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

51. This chapter presents key environmental issues associated with various aspects of the proposed project. Identification and assessment of the potential environmental impacts are based on secondary information supplemented by field visits. Impacts on various environmental components have been assessed at four different stages namely:

- the project location; - design; - construction; and - operation stages.

A. Identification and Assessment of Impacts

1. Positive Environmental Impacts due to improvement of state highway section between Garobadha and Dalu in West Garo Hills District

52. The following are expected positive impacts from the improvement of the Garodhaba- Dalu road section includes: • reduction in travel time and lower vehicle operating cost will reduce fuel consumption and emissions of pollutants, therefore exhausts, tyre and spare parts consumption can be expected for the existing traffic. • better access to other parts of the state by connecting to Tura which is a major connecting route to Assam. From economic point of view, proposed road will enhance the trade and commerce between Khasi Hills districts and West Garo Hills and also Jaintia hills areas

2. Negative Environmental Impacts due to improvement of state highway section between Garobadha and Dalu in West Garo Hills District

53. The following are expected from the improvement of the road section:

• cutting of road site trees that falls within formation width i.e. 8.8 m may reduce the ecological balance of the area and also increase soil erosion problem. • a number of quarries and other sources will be established and scar the landscape. • improvements on road and construction of bridges may enhance soil erosion, landslips and reduce the micro -level ecological balance of the area. Construction will also disturb the habitation of a large number of fauna living in this area. These should, however, be only temporary/reversible effects. • Minor impacts of noise and air quality for those now living and workings close to the project road (mainly Thanlong) will deteriorate during the construction period and afterwards during operation.

20

3. Negative Impacts Related to Project Location, Preliminary Planning and Design

a. Forest Clearing and Tree Felling

54. Part of the project road passes though pockets of community forest areas. Since, improvement work will be limited to the available ROW, no adverse impacts due to diversion of forest land. Also, these forests are not categorized as protected forests. Problem of soil erosion is expected to be aggravated in some locations. To minimize loss of vegetative coverage and/or trees and soil erosion the following mitigation measures will be adopted during the detailed design and construction stage of the project: • During detailed engineering design, study will carry out for widening proposal in order to minimize the need for tree felling or removal of vegetation particularly on areas prone to erosion, • The detail engineering studies and construction activities will strictly enforce the environmental conditions put as part of the environmental clearance by the MoEF and SPCB. • The improvement of road will be done by adopting Environmental Friendly Road Construction (EFRC) methods.

55. Most of the project road passes though forest areas. Since, improvement work will be limited to the available ROW, no adverse impacts due to diversion of forest land. Also, these forests are not categorised as protected forests. None the less the land clearing will involve cutting of a large number of trees. Problem of soil erosion is expected in some locations. There will not be any hydro-ecological impacts. To minimize loss of vegetative coverage and/or trees and soil erosion the following mitigation measures will be adopted during the detailed design and construction stage of the project:

• The detail engineering design study will carry out for widening proposal in order to minimize the need for tree felling or removal of vegetation. • The detailed engineering design will identify areas prone to erosion and include land stabilization as part of the design.

56. As per IEE, September, 2006, the total number of tree to be cut was 1200 numbers; however, it has been revised as 2983 numbers of trees to be cut. The details of trees to be cut along the Project road are given in Appendix G.

Table V-1: Social forest near the Project road

Sl. Type of forest Distance (km) District No. 01 Social Forestry 30 meter West Garo Hills 02 Social Forestry 10 meter West Garo Hills 03 Social Forestry 50 meter West Garo Hills 04 Private Forestry 30 meter West Garo Hills 05 Private Forestry 10 meter West Garo Hills 06 Social Forestry 50 meter West Garo Hills 07 Private Forestry 10 meter West Garo Hills

21

b. Interference with the Elephant corridor

57. The Garudhaba-Dalu road section passes through the West Garo Hills. The Garo Hills are is part of the Garo-Khasi tropical evergreen to moist deciduous forest range and well know for its abundance of wildlife which includes the Siju Cave serving as bat habitat; Nokrek National Park with its primary forest supports a large population of Asian Elephants, birds, and orchids; Siju Bird Sanctuary which supports migrating Siberiand ducks, Grey Hornbill, and Peacock Pheasant; and the Balpakaram National Park where elephants, wild buffaloes, gaur, sambar, barking deer, wild boar, slow loris, capped langur, tigers, leopards, clouded leopards and the rare golden cat are found.

58. The Garo Hills have one of the highest elephant density and elephant-human conflict in India. In 1993-94 the Forest Department estimated 1,400 elephants roam a forest area of 3,150 km2 . The succeeding Figures depicts the entire Garo Hills showing the reserve forest, and roads and the West Garo Hills where the Garudhaba-Dalu road section passes.

Figure V-1: Map of Garo Hills showing Reserve Forests, Districts, Roads, Rivers and Important Towns (Source: Williams, A.C. and A.J.T Johnsingh, 1996)

22

Figure V-2: Map of West Garo Hills Elephant Range Showing Reserve Forests, National Park, Roads and Important Human Settlement Areas. (Source: Williams, A.C. and A.J.T Johnsingh, 1996)

59. The West Garo Hills Elephant Range runs north of Dalu, east of Garudhaba and stretching as far as Dibru National Forest and Nokrek National Park on the eastern boundary. In the 1993 Forest Department census estimated that 166 elephants occupies an area of 1,065 km2 of which only 15.02 km2 is under the control of the Forest Department while the rest are area privately owned under Jhum cultivation.

60. There are approximately five elephant crossing areas between Garobadha and Dalu. Discussions with the Office of Divisional Forest Officer (DFO), East and West Garo Hills Wildlife Division in Tura revealed an Asian Elephant (Elephas maximus) corridor between Mahendraganj and Purakhasia of approx chainage 75.0 km to chainage 95.

61. Based on the survey conducted in 2010 by the Tura Wildlife Division the numbers of elephants in each crossing are as given in the following table

23

Table V-2: Elephant Crossing Along the Project Road No. Road section No. of crossings Elephant numbers 1. Zikzak – Betasing 2 23 and 2 2. Mahendraganj - Purakhasia 1 30 3. Purakhasia – Mukchupara 1 45 4. Mukchupara – Dalu 1 25 TOTAL 5 125

62. Discussions with the Forester 1 and a local resident elephants regularly cross the road sections through out the year. The road is very close to the border with Bangladesh where the landform gradually changes from hilly terrain into tropical plains. According to the Assistant Chief Conservator of Forests, the population of elephants appear to be increasing in West Garo hills district. This could be due to increased disturbance to the elephants in other nearby districts such as East Garo hills and also Bangladesh.

63. It was also reported that a few cases of human death occur every year due to attacks by elephants particularly when people go into the forests. When crossing back and forth between the Bangladesh border the elephants also destroy crops or plantations that fall in their path. It is also a common occurrence for the elephants to give a warning sound when they approach the border gate so that the gate can be opened for them. If the gates are note opened they break through the gate and cross over.

64. Discussions with the ACCF revealed that though there are many elephant corridors in Meghalaya state, they are currently not yet recognized officially. Hence, they do not have any rules or policy framework on what is allowed or disallowed within elephant crossing zones. He also advised that the letter (see Appendix I Memo No. B/MWL/GH/146) issued by the Divisional Forest Officer of the East and West Garo Hills Wildlife Division Tura on 2nd June, 2008 (stating that there is no need for further wildlife clearance and installation of sign boards is recommended) is sufficient. Hence, no further clearances or permissions will be required for improving the project road.

65. It must also be noted that the elephant corridors in India currently do not fall under protected areas, hence they do not fall under the purview of chapter 4 on Sanctuaries, National Parks and Closed areas of the Indian Wildlife (Protection) Act, 1972 (amended in 2003).

c. Borrow Pits and Quarries Operation

66. There is a need to establish construction camps and related facilities, such as borrow pits and quarries. These must be located in environmentally sound and socially safe areas. It is expected that construction materials for the road works will be mined only from approved quarries. The following criteria must be applied when locating borrow areas:

• borrow areas are not established in ecologically sensitive areas; • villagers are consulted in regard to the design and location of all borrow areas – these should ensure the safety of local communities and, if possible, should incorporate beneficial post construction features for the villages; • located away from the road and hill slopes as well as settlements facing the road, so as to minimise visual impacts; 24

• In case of reserve forest areas, construction facilities such as temporary workers camp, hot mix plants, and concrete batching plant and stone crushers should not be established in stretches that passes through reserve / protected forests. Consult forest department / village forest management committees before locating temporary project facilities such as construction camps and workers camp; • construction camps for labourers should be located at least 500 m away from settlements; • living accommodation and ancillary facilities should be erected and maintained to standards and scales approved by the Engineer-in-Charge; and • toilets and urinals should be provided in accessible places away from the asphalt plant and mixing yard.

d. Cultural Heritage

67. There are no adverse impacts expected on historical places/monuments. However, there are small shrines which are coming within ROW and adjacent to existing carriageway. Care must be taken to avoid any damage to these structures. Also earthworks, as associated with the actual road construction/improvement works, or deriving from secondary sites such as quarries or borrow pits, may reveal sites or artefacts of cultural/archaeological significance. In the event of such discovery, the proper authorities should be informed and the requirement to take such action should be incorporated in contract documents.

e. Water Body Crossings

68. Several water bodies are crossed by the road section to be upgraded which will be temporarily affected during construction phase when necessary cross drainages and road embankments are being improved. No adverse hydrologic impacts are forseen on these bodies as no course diversion, water impoundment, or extraction will be undertaken. An inventory of these waterbodies is provided in the Table below.

Table V-3: Surface water crossing the Project road Sl. Type of water Village name Crossing from Ch. Availability of No. bodies (Km) to Ch. (Km) water during a year 1 River Kanong Garobadha 0.8 Km-0.955 km Perennial 2 River Kanong Ambari 2.2 – 2.207 Km Perennial 3 River Lutubari Mohishbathan 7.5 – 7.52 Km Perennial Para 4 Dilni River Betasingh 15.7 – 15.726 Km Perennial 5 Daru River 21.425 Km – 21.470 Perennial 6 River Jangnapara 28.975 – 28.983 Km Perennial Jangnapara 7 River Rokai Kalaipara 38.5 – 38.565 Km Perennial 8 Dimasu river Bondonga 54.5 – 54.525 Km Perennial 9 Tipha River Gopinathkilla 62.475 – 62.516 Km Perennial 10 Dimasu River Saldingpara 64.025 – 64.040 Km Perennial 11 Dimasu River Saldingpara 64.465 – 64.507 Km Perennial

25

Sl. Type of water Village name Crossing from Ch. Availability of No. bodies (Km) to Ch. (Km) water during a year 12 Bamela River Nokmapara 68.575 – 68.597 Km Perennial 13 Babela River Deinapara 70.075 – 70.100 Km Perennial 14 Darong River Deinapara 70.550 –70.667 Km Perennial 15 Sanda River Batua 73.475 – 73.575 Km Perennial 16 Golgola River Balijora 73.950 Km–73.964 Perennial Km 17 Dolakhani Belabore 75.6 – 75.616 Km Perennial River 18 Shorai River Halchati 79.8 – 79.826 Km Perennial 19 Nokchi River Nokchi 82.575 – 82.619 Km Perennial 20 Bandra River Pokpara 86.6 – 86.7 Km Perennial 21 Thalang River Adnangre 95.1 – 95.175 Km Perennial

4. Other Impacts deriving from the Project Preliminary Planning and Design Process

69. During preliminary planning and design of this project, the Consultant should take into account the need for: • optimum siting and control of quarries; • reduced incidence of slope failures due to inadequate drainage; • providing adequate culverts/drains; • providing side-drainage structures; • mechanised construction methods and thereby, for example, reduced use of firewood for heating bitumen; • maximising safety and thereby reducing traffic accidents; • reducing travel times and, thereby, fuel consumption and emissions; • increased accessibility for residents to education and health facilities, markets etc., and for others who might come for tourist or other purposes; and • improving the socio-economic conditions of residents in the project areas of influence.

70. As part of the engineering works for this work, the following have been the guiding principles in determining preliminary alignments and other matters concerning route. These principles should be continued during any detailed design phase and, if this is not possible, the appropriate adjustments should be made on site during the construction phase:

Environmental Issue Measures to be taken Alignment Final alignment should be determined so as to minimise land take, air pollution and the impact on people and animals and to avoid unfavourable geological condition and cultural relics. Balancing cut and fill The design should attempt to equalise cut and fill. The centreline should be aligned so that on all slopes below 60 degrees, half cut and half fill can be achieved. 26

Environmental Issue Measures to be taken Soil erosion Temporary and permanent drainage systems should be designed to minimise the soil erosion. Dust and air pollution Borrow sites, waste disposal sites and asphalt mixing sites should be identified – keeping in mind environmental issues such as dust. Cultural heritage Any archaeological sites identified along the alignment should be excavated prior to construction. Wildlife Habitat Care should be taken in preservation of wildlife and construction workers should be educated on wildlife protection.

5. Construction: Permits and Environmental Impacts to be taken into Particular Account During Construction

a. Permits

71. As a mandatory requirement of Environmental Impact Assessment Notification, April 1994, by Government of India, any development activities should not be taken in any part of country unless it has granted clearance from the Ministry of Environment and Forests, Government of India. Highways are classified as one of the project, listed in said notification, which require prior clearance. However, an amendment to this notification clarifies, that the highway improvement project are excluded from this list unless they pass though environmentally sensitive areas.

72. Indian Road Congress and Ministry of Road Transport and Highways published guidelines for environmental considerations into highway projects. Accordingly, for the proposed road improvement project, implementing authority has to apply for the environmental clearance from the regional office of MoEF, located in Shillong.

73. At present, No clearances for any of the project road has been obtained so far. The process is to ensure minimal negative environmental effects. Prior to applying for environmental clearance, a number of resource-specific clearances and permits have to be obtained. The following table outlines the type of clearances and permits and the authorised bodies that issue them along with the procedures involved.

Table V-4: Required Environmental Clearances and Permits Sl. Clearance/ Authorised Procedures involved Time involved No. permit body 1 Clearance Regional Detailed proposal in appendix specified Approximately from Forest Office of in Forest (Conservation) Act, 1980 along 6 months or Departmen MoEF, with project report and necessary details more t Principal of tree felling. Local division office will Chief forward after joint verification of site and Conservator preliminary scrutiny of proposal to PCCF of Forests, office for approval. Shillong, Joint verification and enumeration of Meghalaya trees to be cut shall be done by division office and after approval shall be allowed

27

Sl. Clearance/ Authorised Procedures involved Time involved No. permit body to cut. 2 NOC from Member Application in prescribed form along with Between 6 Meghalaya Secretary, project report and required fee shall be month to 1 State Meghalaya submitted to pollution control board. After year Pollution State scrutiny of application if required, Control Pollution concerned pollution control board shall Board, Control conduct public hearing in particular Shillong Board district involving state authorities and forest department and affected persons. After fulfilling the requirement SPCB may issue the NOC with specific conditions. 3 Clearance Department Submission of application for quarry site Takes between for quarry of Geology to mining department. Department of 3 months and sites and Mines, mines and geology after scrutiny of six months. Govt. of application and consultation with forest Meghalaya, department and revenue department Shillong together with site verifications will give approval with specific conditions. 4 Clearance State Mining Detailed application with blasting 2 to 6 months for blasting department, locations and amount of blasting shall be Shillong submitted to DoGM. Mining department may issue the conditional approval.

74. Any felling of trees requires forestry clearance and appropriate permits requiring liaison with local territorial forestry offices and their head office in Shillong. No clearance is required for the use of surface sand and stone from the river banks as for commercial purposes they can only be purchased in an open auction carried out by the forestry office. It is imperative that all necessary clearances and permits be obtained before commencement of work.

B. Environmental Impacts to be Taken into Account During Construction

1. Physical Environment

a. Topography, Geology and Soil

75. The cutting of hill slope, filling, the cutting of trees, stone quarrying, and construction of structures, will degrade the topography from its original state. With proper planning, these topographical impacts can be minimize through soil erosion control, and proper drainage. The terrain and geological conditions of area are such that, even with reasonable care exercised during final design, during construction the interaction between proposed road features and existing land features may reveal/result in significant land instabilities.During construction phase the following restrictions will be be imposed: • existing vegetation including shrubs and grasses along the road (except within the strip directly under embankments or cuttings) will be properly maintained; • sites for quarrying, borrowing and disposal of spoils are to be confirmed according to the applicable laws and regulations in the state and the practices followed in recent/ongoing internationally funded road projects will be continued; 28

• controlled and environmentally friendly quarrying techniques will be applied to minimise erosions and landslides; • blasting should not be carried out during busy periods; • cut material should be disposed of in suitable depressions;

76. It is also important to: • maintain adequate vegetative cover above and below the road; • maintain the natural course of water bodies (that is as far as possible) and avoid throwing debris into stream courses; • construct proper drainage structures – this in order to prevent soil from being saturated with water and hence susceptible to erosion; • minimise the construction of hair-pin bends that are close to each other: as this often adds to instability.

77. Given the existence of high slope and high rainfall in almost entire project area and weak geology in some areas, it is inevitable that some sites will face problems of erosion, mostly debris slides. Figure below shows the typical soil erosion prone location.

Figure V-3 Soil erosion prone location along the road

b. Erosion, Silt Run-Off and Landslides

78. Construction involving rock/soil cutting of hillsides may render hill slopes unstable and increase vulnerability to landslides. The blasting of rocks may also result in landslides. All hill/soil cutting areas will be revegetated as soon as construction activities are completed. At more vulnerable locations, selected bioengineering techniques should be adopted - a combination of bioengineering techniques and hard engineering solutions such as rock bolting and the provision of bank drains may be required.

29

79. Excavation and earthworks will be undertaken during the dry season when the risks from erosion and silt run-off are least. The materials used for surface dressing will consist of aggregates and gravel, which do not contain silt. Internationally accepted best practice engineering approaches to minimise landslide and erosion risks and silt run-off will be incorporated into contract documents and monitored during construction to include: • ensure that all embankment grades are not too steep and prone to erosion; • waste material is not thrown into nearby river streams and cross cutting water bodies; • temporary retention ponds, interception drains, and silt traps are installed to prevent silt laden water from entering adjacent water bodies; • the topsoil of borrow areas is preserved and used for re-vegetation; • borrow areas are provided with gentle side slope that are re-vegetated and connected to the nearest drainage channel to avoid the formation of cess pools during the rainy season; • control the disposal and ensure the vegetative stabilisation of spoil.

c. Climate

80. The proposed improvement/construction works will be localised activities and the Project will not have significant impact on climatic conditions, such as rainfall, temperature and humidity in the project area.

d. Surface and Ground Water and Drainage and Hydrology

81. Given the presence of many rivers and streams crossing the project road, improvement of road may result in disruptions to the natural hydrology and water mismanagement and lead to further problems of soil erosion. The natural courses of streams should, to the extent possible be maintained. Appropriate temporary diversions of cross water-courses will be installed. These streams brought back to their natural course as soon as is possible. Disposal of construction debris in streams and rivers should be avoided. This would disturb the water flow, cause siltation and also make the area look unattractive.

82. Minor impacts on water resources are expected during the construction phase. The rehabilitation of existing bridges may also cause soil erosion and turbidity in downstream water bodies. To mitigate this, river-bank slope stabilities should be monitored and, if necessary, appropriate remedial measures applied throughout the construction period. If possible, construction work at bridges should also be avoided during the rainy season. This should minimise erosion and sedimentation.

83. The likely impacts of surface water movements are changes in the natural drainage systems and downstream scour and erosion due to constriction in flows. If suspended solid concentrations in the water are affected, this could also affect aquatic river ecology. Construction activities could also lead to: • the temporary pollution of water bodies: from spillage of chemicals and oil at construction sites and waste from construction camps; • discharge of sediment-laden water from construction areas; • uncontrolled surface water discharge over the road edge: creating large–scale erosion on down-slopes.

84. To mitigate these impacts the following should be implemented: 30

• chemicals and oils should be stored in secure, impermeable containers, and disposed of well away from surface waters; • no vehicle cleaning activity should be allowed within 300 m of water bodies/ drains; • construction camps should be equipped with sanitary latrines that do not pollute surface waters; • the work on bridges and culverts should be limited to dry seasons, when many of the smaller streams will have low water - water diversion works can thus be minimised and the original course restored immediately after the work has been completed; • drivers should be made aware of diversions and other works at bridge construction sites; - this is particularly important at night, if accidents are to be avoided; • drainage structures should be properly designed to accommodate forecast discharges; • side drain waters must be discharged at every available stream crossing so that the amount of discharge water is minimised and minimal erosion occurs at the water outlets; • lined drainage structures should be provided; • where an increased discharge of surface water endangers the stability of the water outlet, erosion protection measures such as bioengineering measures, ripraps, check dams etc. should be incorporated; • in areas with high water tables, seepage may occur and side drains and up-slope catch drains must always been lined - this so that no surface water can penetrate into the subsoil; and • all debris and vegetation, clogging culverts should be regularly cleared.

85. Ground water pollution is not envisaged in this project.

86. During construction air quality may be degraded for short periods due to (i) the exhaust emissions from the operation of construction machinery; (ii) fugitive emissions from brick, concrete, and asphalt plants; (iii) the dust generated from the haulage of materials, exposed soils and material stockpiles; (iv) cutting and filling of hill slope; (v) cleaning of the road; (vi) material loading; (vii) unloading; and (viii) blasting activities. The impact is expected to be localised, temporary and confined to construction areas.

87. Negative air quality impacts during construction are likely to result from three main sources; (i) emissions from construction equipment, including delivery trucks; (ii) fugitive dust from earth-moving operations and demolition; and (iii) localised increased traffic congestion in construction areas.

88. The negative impacts on air quality during construction stage were classified in the following Table. There are two types of pollution, dust pollution and pollution from harmful gases.

Table V-5: Impact on Air Quality during Construction Stage Impact Source 1 Generation of Cutting of slopes towards hillsides

31

Impact Source Dust (SPM) Transportation and tipping of cut material - while the former will occur over the entire stretch between the cutting location and disposal site, the latter is more location specific and more intense; Blasting operations; Activation of landslides and rock falls etc.; Transportation of raw materials from quarries and borrow sites; Stone crushing, handling and storage of aggregates in asphalt plants; Site levelling, clearing of trees, laying of asphalt, construction of bridges; Concrete batching plants; Asphalt mix plants – due to the mixing of aggregates with bitumen; and Construction of structures and allied activities 2 Generation of Hot mix plants; polluting gases Large construction equipment, trucks and asphalt producing including SO2, and paving equipment; NOx and HC The movement of heavy machinery, oil tankers etc. on steep slopes will cause much higher emissions of gases; Toxic gases released through the heating process during bitumen production; and Inadequate vehicle maintenance and the use of adulterated fuel in vehicles.

89. On the Garobadha – Dalu section, it is expected that air quality will be affected to some minor extent by dust and particulate matters generated by construction, vehicular movements, site clearance, earth filling and material loading and unloading. The impacts are, however, expected to be localised, temporary and confined to construction areas. Care should, however, be taken at sensitive urban locations so that harmful impacts can be minimised.

90. As it is expected that Suspended Particulate Matter (SPM) levels will increase during construction, certain mitigation measures are suggested in order to bring down these levels to prescribed standards – or, as far as is possible. The following actions should be implemented: • there should be regular check-up and maintenance of construction equipment - the idling of engines should be discouraged and machinery causing excessive pollution (i.e. visible clouds of smoke) should be banned from sites; • mixing plants i.e. asphalt, concrete, and bricks, should be operated within the permissible limits of CPCB, and be located away from settlements; • the contractor should submit a dust suppression and control programme to the PWD prior to construction – this plan should detail actions to be taken to minimise dust generation and identify equipment to be used; • vehicles delivering loose and fine materials should be covered to reduce spills; • controlled blasting should be carried out and such only with the prior approval of the site Engineer and, if required, PWD; • bitumen emulsion should be used wherever feasible, and • bitumen heaters should be used and the use of wood for fuel discouraged or prohibited.

32

e. Noise Levels

91. With the exception of the Garobadha and Dalu centers, the ambient noise level along the road sections is within standards. During the construction period, noise will be generated from the operation of heavy machinery, blasting works, the haulage of construction materials to the construction yard and the general activities at the yard itself. Concrete mixing and material movements will be the primary noise generating activities and will be uniformly distributed over the entire construction period. These construction activities are expected to produce noise levels in the range of 80 – 95 dB(A). Piling, if necessary, will also cause vibration. Noise and vibration from this source will be unavoidable but the impact will only be temporary and affect people living or working near piling locations. In construction sites within 500 metres of a settlement, noisy operations should cease between 22:00 and 06:00 hrs. Regular maintenance of construction vehicles and machinery must also be undertaken to reduce noise. The impact and sources of noise and vibration are summarised in succeeding Table.

Table V-6: Likely Impact on Noise Quality in the Vicinity of Project Area Impact Source Increased Noise Mobilisation of heavy construction machinery; Levels causing Accelerations/decelerations/gear changes – though the extent of discomfort to local impact will depend on the level of congestion and smoothness of residents, workers the road surface; and local fauna Use of blasting to cut into hill sides; Excavation work for foundations and grading; Construction of structures and other facilities; Crushing plants, asphalt production plants; and Loading, transportation and unloading of construction materials.

92. Typical noise levels associated with various construction activities and equipments are presented in Table below:

Table V-7: Typical noise levels of principal construction equipments (Noise Level in db (A) at 50 Feet) Clearing Structure Construction Bulldozer 80 Crane 75-77 Front end 72-84 Welding generator 71-82 loader Jack hammer 81-98 Concrete mixer 74-88 Crane with ball 75-87 Concrete pump 81-84 Concrete vibrator 76 Excavation and Earth Moving Air compressor 74-87 Bulldozer 80 Pneumatic tools 81-98 Backhoe 72-93 Bulldozer 80 Front end 72-84 Cement and dump 83-94 loader trucks

33

Clearing Structure Construction Dump truck 83-94 Front end loader 72-84 Jack hammer 81-98 Dump truck 83-94 Scraper 80-93 Paver 86-88 Grading and Compaction Landscaping and clean-up Grader 80-93 Bulldozer 80 Roller 73-75 Backhoe 72-93 Truck 83-94 Paving Front and end loader 72-84 Paver 86-88 Dump truck 83-94 Truck 83-94 Paver 86-88 Tamper 74-77 Dump truck 83-94 Source: U.S. Environmental Protection Agency, noise from Construction Equipment and Operations. Building Equipment and Home Appliance. NJID. 300.1.Decemember 31, 1971

93. The noise levels indicated for various construction activities/equipment, while far exceeding permissible standards, will occur only intermittently and be only temporary. Despite this, these extremely high sound levels present a real risk to the health of workers on- site.

94. Since the anticipated post-construction volumes of traffic on the project road is expected to be low, impacts from higher noise levels will have little significance even though present noise levels in these areas are low. In these areas, the noise produced during construction will also not have a significant impact, if proper mitigation measures are taken. Mitigation Measures should include: • construction machinery should be located away from settlements; • careful planning of machinery operation and the scheduling of such operations can reduce noise levels. The use of equipment emitting noise not greater than 90 dB(A) for an eight-hour operations shift and, when possible, the siting of construction yards at least 500 metres from residential areas should be adhered to; • controlled blasting should only be carried out with prior approval from the Engineer in charge; • contractors should be required to fit noise shields on construction machinery and to provide earplugs to the operators of heavy machines; • blasting should be conducted only during day-light hours; and • only controlled blasting should be conducted.

f. Topography and Appearance

95. Construction activities of the project roads will bring permanent changes in the local- level topography and appearance of the project site. There will be loss in aesthetic beauty of the project area mainly due to the earthwork. The following table elaborates potential effects on the topography and appearance and appropriate mitigation measures.

34

Table V-8: Potential Effects on Topography by the Proposed Road Section Updrading Construction Potential effect on Mitigation activity topography and appearance Clearing 1 of Scarring of landscape from Cut material should be used to widen vegetation and cutting and potential the road or disposed off at proper cutting of hillside landslides (short term and disposal sites. for widening of the long term) may be caused. Cut slopes should be re-vegetated road There may be minor immediately after widening activities. permanent changes in the landscape. 2 Stone quarrying Scarring of landscape and Stone quarrying should only be potential landslides (rock undertaken in legally approved areas. slides/falls). There may be Controlled and environmental friendly permanent changes in the quarrying should be carried out to landscape. minimise land slides and erosion 4 Earthwork from Scarring of landscape due Borrow areas should be in legally borrow areas to unearthing activities. approved locations. As soon as Minor but permanent construction activities are complete, changes in landscape they should be re-vegetated and brought back as far as possible to their previous appearance. 5 Waste disposal Disposal of cut soils and Cut off material should be used to debris at improper locations widen the road or disposed of at proper such as hillside below the disposal sites road will make the area look untidy and unattractive 6 Establishment of Disposal of waste and litter Provision and allocation of proper labour camps at improper locations and waste disposal bins and sites are deforestation for fire-wood required. A supply of cooking gas will make the area look dirty should be provided by the contractor to and unattractive. eliminate the use of fire wood.

2. Ecological Resources

a. Wildlife

96. The existence of rich biodiversity and micro climatic conditions, the state is home to a number of important wildlife species. However, in project area presence of wild animals is very rare. Also, project road does not pass through dense forests; it will not have any impacts on movement of wild animals. Though no studies of the impacts of development activities on wildlife have been conducted in state so far, the work on this road may have low-level impacts on wildlife.

97. The improvement works to the existing alignment, usefully should involve minimal tree felling and hence cause little impact. However, some section of the project road passes through thin forests, construction work in this area may, may have impacts on presence of wildlife.

98. Some indirect ecological degradation may also occur from wildlife poaching, by construction workers and outsiders due to greater accessibility and as a result of increased local demands for food resulting from road construction activities. In order to avoid such impacts the contract document should include the following:

35

• project staff and work crews should not be allowed to have fire-arms and animal traps etc.; • construction facilities such as workers camp, construction camp, hot mix plant, batching plant should be located at least 1 km away from the forest stretches. • employment agreements should specify heavy penalties for illegal hunting, trapping and wildlife trading – all other ancillary works should also agree not to participate in such activities;

b. Vegetation

99. The part of project road passes through the pockets of forest area of West Garo Hills Forest Division. The density of vegetation in forest is 0.3 to 0.4. As per IEE, September, 2006, the total number of tree to be cut was 1200 numbers; however, it has been revised as 2983 numbers of trees to be cut. This will also affect the wildlife habitat and enhance soil erosion. A total of approximately 492500 sq m (5 m strip for about 98.5 km length) of scrubs and vegetation will probably be removed for improvement of road between Garobadha and Dalu. The loss of vegetative cover will mostly be permanent and only some might be revived through mitigation efforts. Another impact from road construction activities and deriving from the cutting of hillsides, quarrying, preparation and transfer of stone chips and other earthwork, is the accumulation of dust on the surrounding vegetation. This will leads to deterioration of the vegetative health, which in turn will affect the ecology as well as the aesthetic beauty of the area. Induced impacts may result from the following: • increased forest harvesting for fire-wood, construction timber, forage, medicinal plants and other products; • increased earth and rock extraction; • construction crew demands for wood as a fuel and for building materials; • construction crew demands for food and recreational hunting and fishing;

100. To minimise negative impacts on the vegetative cover the contract documents should specify that: • all wood building material for workers’ housing should be brought from outside the project area; • workers should be supplied with non-wood fuels such as kerosene or liquefied petroleum gas for the duration of the contract; • all contract equipment and plants should be cleaned to the satisfaction of the project engineer in charge prior to their relocation to project sites; • during site clearance, care should be taken to ensure that the minimum area of vegetation area is affected; • the water sprinkling of trucks used as construction vehicles should be properly and regularly undertaken, so that dust deposition problem on vegetation are minimised.

3. Human Use Values

a. Land use and Settlements

101. Field reconnaissance surveys of the project roads were conducted in first week of August 2006. These, amongst other things, assessed environmental and social conditions. Particular note was made of likely sensitive issues. In the project area, the relocation of structures will only be required at a very few locations. In these areas, most structures which 36

may require to be removed are, moreover, made of light materials i.e. compacted earth, timber and corrugated iron sheets. The widening options, however, been devised so as to cause minimise destruction of structures. The sensitive location such as school along the project corridor within 100 meter from the edge of the existing road is given in Table below.

Table V-9: School, College and health centre located 100 meter from the edge of the existing Project road Sl. Name of School/ Name of the Distance & Direction Chainage No. College/ Hospital Village (LHS / RHS) from existing (km) road edge

1 a) Garobadha Govt Garobadha RHS - 14.5 m 0.2 Km Assisted LP School b) Garobadha Higher RHS-31m 0.4 Km Sec School 2 Garobadha Sub Health Baishpara LHS- 8 m 4.3 Km Centre 3 Khongpara LP School Khongpara LHS- 23m 5.4 Km

4 Sapthika LP School Lingopa LHS- 36.6 m 6.5 Km 5 Monishbathan Para LP Monishbathan LHS- 40m 7.3 Km School Para 6 Lutubari UP School Lutubari RHS-11.7 m 8.2 Km 7 Betasingh Higher Betasingh RHS-24.7 m 14.3 Km Secondary School 8 Nirghini Govt. L.P. Nirghini LHS – 88m 15.2 – 15.3 School Km 9 Betasingh LP School Betasingh LHS – 40.8 m 16.5 Km 10 Betasingh LP School Betasingh RHS – 80 m 17.1 Km 11 Bolsalgiri Govt LP Bolsalgiri RHS – 7.6 m 18.9 Km School 12 Govt L.P School Dumduma LHS – 31 m 19.7 Km 13 Ghasura L.P School Ghasura RHS – 11.9 m 20.7 Km 14 Ghasura M.E School Ghasura RHS – 32 m 20.7 Km

15 Ampati Community Ampati RHS – 86.20 m 21.4Km Health Centre 16 Birin Nuchong Private Ampati LHS – 24.3 m 22.0 Km School 17 Gara Bokmangre U.P Bokmangre LHS-43m 26.1 Km School 18 Zikzak Government Zikzak LHS-11.9 34.2 Km Aided school 19 Magurmari Govt. L.P Magurmari RHS-14.6 35.4 Km School 20 Patijora Govt Assisted Patijora RHS-25.7 36.9 Km Sec School

37

Sl. Name of School/ Name of the Distance & Direction Chainage No. College/ Hospital Village (LHS / RHS) from existing (km) road edge

21 Dharmachas L.P.Govt. Harmachas LHS-48.3 41.9 Km School

22 Nogarpara U.P.School Nogarpara RHS-49 44.3 Km Govt. School 23 Chapahati Govt L.P. Chapahati II RHS-30.5m 46.8 Km School 24 Chapahati L.P. Govt. Chapahati I RHS – 26.6 m 48.1 Km School 25 Bidukura L.P. School Bidukura RHS – 41 m 49.2 Km

26 Jawahar Novodaya Kendrakona LHS – 50 m 50.4 Km Vidyalaya 27 Arakgittim SSA U.P. Kendrakona LHS – 42.30 m 51.3 Km School 28 New Tarapara L.P. Tarapara RHS – 13.1 m 52.7 Km School 29 Debajani L.P. Govt. Debjani RHS – 47.79 m 57.0 Km School 30 Private English School Saldingpara LHS – 14.3 m 64.4 Km

31 Renthangpara Govt. Rengthanpara LHS – 23.3m 65.6 Km L.P. School 32 Hathimara Govt. L.P. Hathimara RHS – 3.80 m 68.3 Km School 33 L.P. School Halchati LHS – 38.5 m 80.0 Km 34 Halchati Govt Aided Halchati RHS – 17.90 m 80.1 Km Secondary School 35 Halchati Govt L.P. Halchati RHS – 17.90 m 80.1 Km School 36 Sesengpara U.P. Sesengpara RHS – 22m 86.9 Km School 37 Sesengpara Bengali Sesengpara LHS – 20.8 m 87.9 Km L.P. School 38 Mobile Leprosy Sesengpara LHS – 11.0 m 88.3 Km Treatment Unit 39 Mongolagere Sec. Mongolagere LHS- 36.2 m 89.2 Km School 40 Matchokpara Adhoc Matchokpara LHS – 35.5m 91.7 Km L.P.School 41 Koinaboi I.C.D.S Koinaboi LHS – 31.8 m 97.9 Km Centre

102. At certain locations on the road, particularly at bridge sites, traffic will be temporarily diverted from the existing carriageway while construction is in progress and temporary traffic diversions will be managed within the ROW. In other instances, traffic may have to be diverted 38

across adjacent private land, in which case compensation will be paid for any loss of crops or the replacement of damaged structures. In other situations, most frequently not at bridge sites, for example when bitumen surfacing is in progress, it may be required to close the road temporarily. In these circumstances, adequate radio and press releases should be made beforehand and a date/time given for the re-opening.

103. Most construction will be undertaken during the dry season when few crops are planted.

b. Health, Safety and Hygiene for Construction Workers

104. Construction of the road will result in the generation of waste. In isolated places, the amount of waste generated may be greater than normal because of substandard subsoil materials, which will need to the replaced.

105. The Contractor will be required to control the construction site, keep it clean and provide facilities such as dust bins and collectors for the temporary storage of all waste. This waste should be adequately stored to avoid pollution of water supplies and water sources and to avoid dust formation. The Contractor will be responsible for the safe removal and/or storage of all waste in order to prevent environmental pollution of any type that may be harmful to people or animals.

106. All necessary safeguards should be taken to ensure the safety, welfare and good health of all persons entitled to be on the sites and to ensure that works are carried out in a safe and efficient manner. All personnel working at vulnerable site locations will wear safety helmets and strong footwear. It should be ensured that all workmen and staff employed on site use proper safety equipment – for example, eye protectors, ear plugs, safety helmets, the designated safety equipment when working over water - and that proper rescue equipment is available. Fire extinguishers and first-aid equipment will be kept at all sites.

107. The construction camps are anticipated to house up to 300 people for two to three years. With this concentration of people, the potential for the transmission of diseases and illnesses will increase. The main health and safety risks during construction will arise from:

• inadequate sanitation facilities in worker camps; • introduction of sexually transmitted, and other diseases, by immigrant workers; and • outbreaks of malaria, typhoid, cholera etc. amongst the labour force.

108. The following actions will be undertaken at construction camps and stipulated in construction contracts:

• submit and obtain approval for a health and safety plan prior to the commencement of work; • provision of adequate health care facilities; and • workers will be required to undergo pre-employment medical screening and treatment (if required) and periodic health checks thereafter.

109. The project will support a public health education programme for workers and villagers covering road safety, malaria, hygiene, and sexually transmitted diseases. The district health departments will be enjoined to participate in monitoring and education of communities and workers affected by the project.

39

c. Nuisance to nearby properties

110. Nuisance to nearby properties is likely to result from:

• noise and vibration from mechanical devices and construction plant; • dust during quarrying, construction and the trafficking of new surfaces prior to sealing; • gaseous emissions from heavy equipment; and • fumes from asphalt boiling sites.

111. Much of the project road pass through forest areas and presently air/dust pollution is not a major issue. Nonetheless, there will be regular watering of the road surfaces or the application of emulsion coats near villages, where dust is a nuisance. Noise generating equipment such as power generators and concrete mixers will be kept away from populated/commercial areas. Provisions will be incorporated into the contractor’s contract to require the use of dust suppression measures.

d. Interference with Utilities and Traffic

112. On the project road, utilities interfere with the ROW at few locations that will have to be moved prior to construction. This should not be a major problem.

113. Traffic may experience minor delays when diverted around active construction areas, but will be more severely hampered at the locations where temporary road closures are necessary. Such hazard points will have proper signs indicating the nature of the problem envisaged.

e. Community Impacts

114. There will be minor widening work on entire road length - in which case the resettlement problem will be minor.

115. Construction camps may put stress on local resources and the infrastructure in nearby communities resulting to people raising grievances. This sometimes leads to aggression between residents and migrant workers. To prevent such problems, the contractor should provide the construction camps with facilities such as health care clinics, places of worship, and occasional entertainment. The use of local labourers during the construction will be promoted to minimise these problems.

f. Quality of Life

116. The impact of the improvements of project road on the socio-economic environment will be significantly beneficial. Improved access and reduced travel times and costs will be major stimuli to economic growth, particularly in rural areas. Better access of agricultural goods to market will be important and a major contributor to poverty reduction.

117. Increased labour mobility will occur. This has both positive and negative impacts. Increased access is a two-way phenomenon, and the corollary to increased access to the project areas is increased access for the residents of these areas to more urban life-styles. Out-migration may result. There is also the likelihood of the relocation of homes and businesses to new road-side locations.

40

118. During construction, benefits to local people can be maximised if the contractor recruits construction workers locally regardless of gender. Where possible, he/she should also not discriminate in the employment of women.

g. Construction Materials

119. The use of proper sources for stone and aggregates has become a major issue in most states. Historically, stone has been collected from the roadside or from shallow surface workings. Small quarries on steep slopes are often enlarged by blasting or excavation at the base. This is dangerous and can cause slope failures. Roadside stone collection continues in some districts despite its proven negative impacts on road safety and stability. Sand and gravel are often obtained from river deposits. Jurisdiction over stone and aggregates is shared between the Geological Survey of India and the State Forest Department. The Geological Survey of India issues licences for major mineral developments while the Forest Department issues permits for stone quarrying and for sand and gravel extraction. This is largely because these are mostly found on forest lands. Roadside quarrying is officially discouraged, but unofficially continues, invariably by petty contractors.

120. Road maintenance, repair and new construction will continue to cause large demands for construction materials. There is a clear need for a better materials supply policy in each district to minimise environmental impacts of small-scale, poorly managed operations and improve the quality and reliability of supply. In some districts, it may be appropriate to develop centralised quarries, if an operator can be attracted. In any case, pre-designation of sources would give contractors a level playing field for bidding and minimise incentives for environmentally damaging cost cutting.

121. As a prior requirement of projects, every quarry and borrow area should be subjected to a site specific environmental investigation, work according to an approved plan; and should be left in a safe condition or restored to a productive land use. Subject to these conditions, obtaining construction materials for projects will not cause unacceptable impacts.

122. Quarry and borrow pits may be filled with rejected construction waste and afterwards should be given a vegetative cover. If this is not possible, then the excavated slopes will be filled in such a way that they resemble an original ground surface.

123. Mitigation for Quarries

• aggregates will be sourced only from licensed quarry sites that comply with environmental and other applicable regulations; • occupational safety procedures/practices for the work force will be adhered to in all quarries; • quarry and crushing units will be provided with adequate dust suppression measures; and • regular monitoring of the quarries by concerned authorities to ensure compliance with environmental management and monitoring measures.

124. Mitigation of Borrow Areas

• prior approval will be obtained from concerned authorities and all local environmental regulations be complied with;

41

• within all identified borrow areas, the actual extent of area to be excavated will be demarcated with signs and access to the operational area controlled; • borrow pit plant and machinery will conform to EPA noise emission regulations; • protective gear will be provided to the workforce exposed to noise levels beyond threshold limits and there should be proper rotation of such personnel; and • all operation areas will be water sprinkled to control dust levels to national ambient air quality standards.

125. The project will require large amounts of bitumen or bitumen emulsion usually stored in drums. These empty bitumen drums are generally recycled as steel sheeting, or used in road construction as parapets or for bank stabilisation. When supplied and used in this manner, bitumen is not regarded as a significant environmental hazard.

126. The project will require the import, transport and use of fuel and oils. Minor diesel spills are common in region, especially around fuel stations. The project provides an opportunity to assist the PWD and contractors in improving fuel handling practices so as to minimise future fuel spillage.

C. Environmental Effects Related to Operation

1. Noise Vibration, Air Pollution, Runoff, Spoils of Hazardous Materials

127. The current low traffic flows along the project road is expected to increase because of improved economic activities associated with better access. The larger numbers of vehicles will be an additional source of noise and gaseous emissions. Repairs to culverts and new drainage work will eliminate/reduce the soil erosion problems presently caused by poor cross drainage. Also, the situation will remain good because this road pass through area that are largely forested and trees and plants have the capacity to absorb gaseous as well as noise pollutants. Bioengineering techniques may also help to absorb pollution.

128. Stone and sand quarries, and water sources along the Project road are provided in the Appendix A.

2. Land Use and Settlements

129. The likely impacts on land use and settlement patterns are limited. Improved access will lead to increased migration, but this will occur gradually and over a prolonged period. There will be time for new residential areas to be established. There will be a need to control ribbon development.

3. Social Impacts

130. Specific benefits to local people will include:

• easier communication; • easier access to markets (both internally and regionally) with savings in travel times and costs; • enhanced market efficiency through better distribution and accelerated deliveries etc.; • improved access to health, education and other social services; • employment generation; 42

• improved technical skills; and • enhanced economic activity.

131. Likely adverse social impacts will include: • increased chances of exposure to communicable diseases, particularly during construction; • influxes of new settlers leading to increased pressure on natural resources causing hardship to local communities relying on local/forest resources; and • rural-to-urban migration causing labour shortages in the depleted rural areas and other negative impacts in the urban areas.

D. Potential Environmental Enhancement /Protection Measures

132. Volume II of this IEE Report presents good environmental management practices and guide documents in the following aspects of road construction:

• Plant Management • Campsite Management • Debris Disposal Management • Borrow Area Management • Air Standards • Environmental Clearances

43

VI. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION

133. A public consultation process has been undertaken as part of the IEE study and for the social assessment study. A series of meetings were conducted involving officials of executing agencies, PWD, District Rural Development Officials, Forest department officials, likely affected persons and village heads in the project area. The list of the officials/persons consulted is provided in Appendix B. Most of the people interviewed strongly support the project. The people living in all the project areas expect the different project elements to facilitate transport, boost economic development and thereby provide directly, or indirectly, benefits to themselves.

134. Although most of the people interviewed strongly support the project, several project activities and components were identified to pose environmental risk and appropriate mitigation measures must be implemented, and these are:

• Construction camps may put stress on local resources and the infrastructure in nearby communities, and • Potential conflicts between community and migrant workers which sould be prevented by the contractor by providing the construction camps with facilities such as proper housing, health care clinics, proper drinking water and timely payment. The use of local labourers during the construction will, of course, increase benefits to local peoples and minimise these problems. Wherever possible, such people should be employed.

44

VII. GRIEVANCE AND REDRESS MECHANISM

135. All the three parties involved in this project implementation i.e. Contractor, Engineer and Employer will maintain complaint registers at their respective offices:

• Contactor’s main site offices i.e. office of the Project Manager; • SC’s main site office i.e. office of the Engineer’s Representative; and • Executive Engineer’s office i.e. Employer’s field office

136. All public complaints regarding environmental issues received by any of the above mentioned offices will be entered into the register with specific details such as name and address of the person or representative of the community registering a complaint, the details of complaint, and time. The Executive Engineer and Engineer’s Representative will immediately communicate the details of the complaint to the Contractor. The ESO of the contractor will promptly investigate and review the environmental complaint and implement appropriate corrective actions to arrest or mitigate the cause of the complaints. The Engineer’s Representative will decide on the exact time frame within which the action will be taken on case- to-case basis depending on the nature and sensitivity of the same. However, in all the cases, it will be responsibility of the contractor to take action immediately upon receiving any complaint. The contractor will report to Engineer’s Representative about the action taken on the complaint, preferably within 48 hours of receiving the complaint, for his further intimating to PMU and the Executive Engineer. The person making a complaint would be intimated by the complaint receiving person or his representative, about the action taken, within 48 hours, along with his/her feedback.

45

VIII. ENVIRONMENTAL MANAGEMENT PLAN

137. The Environmental Management Plan (EMP) consists of a set of mitigation, monitoring and institutional measures to avoid, minimize and mitigate adverse environmental impacts and enhance positive impacts.

138. The major components of the EMP are the mitigation of potentially adverse impacts, monitoring of EMP implementation during project implementation and operation; and Institutional arrangements to implement the EMP.

A. Summary of Impacts

139. Following are anticipated potential adverse environmental impacts: • tree cutting for the proposed widening; • shifting of cultural properties and common property resources for the proposed widening; • environmental pollution of land and air environments due to locating construction camp; • deterioration of ambient air quality from the construction plants (Hot Mix Plant and Diesel Generator [DG] sets); • biophysical environment deterioration due to quarry operation; • removal of flora and disturbance on fauna; • occupational health and safety risk from construction works.

B. Impacts, Mitigation and Institutional Responsibilities

140. The identified environmental issues and suggested mitigation measures with institutional arrangements for implementation, supervision and monitoring have been provided in matrix format in Appendix D These mitigation measures will be implemented as applicable for this subproject.

C. Specific Environmental Management Plan

141. A Generic Environmental Management Plan (GEMP) applicable for all sub projects of Tranche-1, Tranche-2 and Tranche-3 of North Eastern State is appended as Volume II. This GEMP details the good practices and mitigtaion measures on plant, campsite, debris, borroe areas, and quarry management. The GEMP also provides guide to contractors on air standards and environmental clearances required. However, a Specific Environmental Management Plan provides project-specific measures to be implemented particularly during the construction phase. The suceeding section presents the specific Environmental Management Plan for MLN- Garodabha-Dalu.

1. Compensatory tree plantation

142. As per compensatory afforestation, the tree plantation will be done three times of tree cutting (1:3 of tree cutting).

46

Table VIII-1: Proposed Compensatory Afforestation for Garodabja-Dalu Road Section No. From To Length Tree to be Compensatory Afforestation in (km) cut in the consultation with Forest Dept. Project road (1:3 of tree cutting) MLN-1 Garobadha Dalu 93.3 2983 8949

2. Elephant Crossings

143. The assessment of the potential conflict between the road upgrading, its users, and elephant corridor revealed that there will be no significant impacts as a road already exists and no new road construction is taking place inside pristine or government reserved forests. The project area is largely made up of agricultural fields and settlements, hence additional impacts from road strengthening will be insignificant.

144. Currently there are no information or warning signboards on the existence of elephants along the road. Under the project, signboards will be placed at all locations where elephants cross over. Hence, the awareness of the vehicle drivers and local people on elephant crossings will be enhanced.

145. Based on the feedback from the ACCF it is concluded that no further wildlife or environmental clearance is required for the project.

3. Bio-Engineering Measures

146. The following bio-engineering measures for slope protection in hill roads were incorporated in the EMP budget.

• Turning of slopes through rough grassing; and • Tree plantation along the hill section (slopes) of the Project road to control the soil erosion.

4. Proposed Noise Barrier at sensitive location

147. The folloring proposed noise barrier at sensitive receptor such as schools, colleges and hospitals have been incorporated in EMP of the Project road.

Table VIII-2: Proposed noise barrier at School/ College Sl. Name of School/ college Approx Proposed Name of the No. Chainage Noise Barrier village (km) (meter) 1 Lutubari UP School 8.2 15 Lutubari 2 Bolsalgiri Govt LP School 18.9 15 Bolsalgiri 3 Zikzak Government Aided school 34.2 20 Zikzak 4 Magurmari Govt. L.P School 35.4 25 Magurmari 5 New Tarapara L.P. School 52.7 20 Tarapara 6 Hathimara Govt. L.P. School 68.3 25 Hathimara Total Noise Barrier (meter) along the Project road 120

47

5. Excavated road side debris and its disposal

148. The provision has been made in cost estimate to use the roadway excavated materials as necessary for the construction of road, which are as follows. (i) For all types of soil, such as ordinary rock, hard rock and (ii) Excavation from drain and foundation of other structures.

149. As per above description, the Contractor will use the excavated road side material for construction of road. The rest unsuitable material will be disposed suitably. The lead and lift has been considered in cost estimates. The Contractor will not dispose the excavated unsuitable material generated from hill section to other side (valley side) of the Project road. Proper disposal plan will be prepared by the Contractor to dispose the unsuitable material generated from hill cutting/ road excavation.

6. Water bodies to be protected

150. The surface water bodies in the Project road require protection during construction phase of the Project road. The Contractor shall not disturb/ pollute the surface water due to construction activities of the Project road. The Contractor will be responsible to protect the surface water and extra payment for the same will not be given.

7. Re-development of Borrow area

151. The items for redevelopment of borrow area such as preservation of top soil and re- application of stored top soil has been considered in proposed EMP cost. The Contractor will re- develop the borrow areas before closing of same. The estimated quantities for preservation and re-application of the top soil has been considered for redevelopment of borrow area.

D. Environmental Monitoring Plan

152. Environmental monitoring is an essential tool for environmental management as it provides the basic information for rational management decisions. To ensure the effective implementation of mitigation measures and environmental management plan during construction and operation phase of the up gradation of Project road, it is essential that an effective Environmental Monitoring Plan be designed and followed. The effects monitoring will be undertaken by monitoring selected parameters of air, water, noise, soil and performance monitoring on tree plantation as mentioned in Appendix E. The stipulated standards for various environmental attributes are given in Volume II-F.

E. Institutional Requirements

153. The PWD, Government of Meghalaya, through its Project Implementing Unit (PIU), is the Executive Agency of the Project. The Project Director is overall responsible for EMP implementation. The following key players are involved in EMP implementation during construction stage:

• PIU and its environmental unit; • Construction Supervision Consultant (SC) i.e. Engineer and his representatives; and • Contractor 48

154. There is a need for fully establishing an Environmental and Social Management Unit (EMSU) within the PIU. It is recommended that one of the senior officers of PIU could be designated as Environmental and Social Officer for monitoring implementation of proposed safeguard measures, as IEE does not envisage any significant impact and thus, additional senior staff requirements is not considered. EMSU will be headed by the Project Director but coordinating and supervising implementation of safeguard measures will be undertaken by the designated Environmental and Social Officer. There is a need for capacity building of environmental unit through various trainings.

155. The Project Director of PIU with the assistance of designated Environmental and Social Officer will be overall responsible for ensuring compliance of safeguard measures and will be reporting to the regulatory bodies and ADB certifying that relevant environmental safeguard measures have been complied with during project implementation. At the field level, the Executive Engineer with his Assistant Engineer/s will supervise implementation of safeguard measures for this subproject and submit monthly reports to PIU.

156. PIU may engage independent agencies for carrying out pollution monitoring activities. The Supervision Consultant shall be interacting with these agencies and facilitate them in carrying out such activities.

157. The Supervision Consultant (SC) will liaise with PIU environment unit to ensure that Contractor complies with the requirements of various environmental safeguard measures through supervision, monitoring and reporting on the same. Efforts must be made by SC to ensure that environmental mitigation and good-construction-practices are not only considered but actually implemented as integral component of each civil activity. It should be considered as day-to-day activity. Implementation of environmental safeguard measures needs team effort and as such the Team Leader of SC will delegate the responsibilities to each member of the supervision team with respect to their core responsibilities. The project should have a provision of part time input of Environmental Specialist within SC to supervise implementation of safeguard measures. His role would be more on advisory. He will assist the Team Leader of SC on the following: • Advise PIU on preparing reports to ADB and other statutory bodies; • Preparing procedures for implementing EMP; • review Contractor’s EMP, traffic management plan and safety plan and recommend for its approval / improvements, to the Team Leader; • provide training to PIU, SC and Contractors’ staff on implementing environmental safeguard measures; • advise on obtaining various statutory environmental clearances on time; • conduct periodic field visits to examine environmental compliances and suggest corrective actions ; and • any other issues as will be required to ensure environmental compliance.

158. Besides, the Team Leader of SC will nominate a senior engineer from the site office for being directly responsible for day-to-day supervision of implementation of stipulated safeguard measures, to ensure accountability. He will provide guidance to the field staff of SC and Contractor for implementing each of the activities as per the EMP. He will be responsible for record keeping, providing instructions through the Engineer for corrective actions, ensuring compliance of various statutory and legislative requirements and assist Engineer for submitting

49

reports to PIU. He will maintain a close co-ordination with the Contractor and PIU for successful implementation of the environmental safeguard measures.

159. For ensuring that EMP is properly implemented, Contractor shall appoint a full time qualified and experienced Environmental and Safety Officer (ESO) from the commencement to completion of the Project. The qualification and responsibilities of ESO as stipulated below should be considered.

160. The qualification of ESO will be as given below: • Diploma or Graduate in Civil Engineering with post graduate specialization in Environmental Engineering or Environmental Science or equivalent; • 5 to 10 years of total professional experience; and • About 3 to 5 years of experience in similar projects i.e. management of environmental issues in design and construction of road / highway / flyover / bridge projects.

161. The responsibilities of ESO of Contractor will include the following: • Directly reporting to the Project Manager of the Contractor; • Discussing various environmental issues and environmental mitigation, enhancement and monitoring actions with all concerned directly or indirectly; • Prepare Contractor’s EMP, traffic management plan and safety plan as part of their Work Program; • Ensure contractor’s compliance with the EMP stipulations and conditions of statutory bodies; • Assisting his Project Manager to ensure environmentally sound and safe construction practices; • Assisting his Project Manager to ensure the timely procurement of materials that are included in the Bill of Quantities relating to environmental mitigation and enhancement measures; • Conducting periodic environmental and safety training for contractor’s engineers, supervisors and workers; • Preparing a registers for material sources, labour, pollution monitoring results, public complaint and as may be directed by the Engineer; • Assisting the PIU on various environmental monitoring and control activities including pollution monitoring; and • Preparing and submitting monthly reports to SC on status of implementation safeguard measures.

162. As mentioned above, there is a need for capacity building of PIU on various environmental and social aspects of the project through various environmental training. Recently, there has been change of statutory requirements for this similar projects based on new EIA Notification. This has changed the landscape of legal and administrative framework for implementing the projects. Thus, there is a need for the PIU staff to updating the information and keeping abreast with the changing legal and administrative requirement. The requirements of various statutory permits and clearances are mentioned in Volume II-F. For successful implementation of EMP, it is essential to orient engineers of PIU, SC and Contractor who would be mobilized for this project. One day environmental orientation workshop will be conducted at Shillong by PIU, once most of the staff has been mobilized. The training program is included in Appendix F.

50

F. Proposed Environmental Budget

163. The proposed EMP budget is Rupees/ 4,468,585. The environmental budget including cost of environmental training is detailed in Appendix G.

51

IX. CONCLUSION AND RECOMMENDATION

164. The proposed ML01: Garodhaba- Dalu road section improvement has been categorized as Category ‘B’ based on environmental screening and assessment of likely impacts while the initial environmental examination ascertains that it is unlikely to cause any significant environmental impacts. Few impacts were identified attributable to the proposed subproject, all of which are localized and temporary in nature and easy to mitigate.

165. The road section improvement does not pass through or located nearby any national park, wildlife sanctuary, reserved forests, or any other ecologically sensitive or areas. No archaeological/protected monument is located in the project vicinity. The land use pattern around the alignment is predominantly forestland.

166. The significant adverse impacts of the road section upgrading are:

• Impacts on surrounding area due to tree cutting for the proposed widening; • Impacts on cultural properties and common property resources for the proposed widening; • Temporary impact on land and air environment due to locating construction camp; • Temporary impact on land, air and water environment due to establishing and operating construction plants (Hot Mix Plant and Diesel Generator [DG] sets); • Impact on biophysical environment due to quarry operation; • Impacts on roadside flora and fauna; • Impact on air quality, water quality, drainage, road users due to construction activities of project road ; • Impact on land and water environment due to disposal of waste materials; and • Impact on occupational health and safety due to all onsite and offsite construction works

167. In general, the subproject received immense support from local people. The local people appreciated that besides providing an all-weather efficient connectivity to large rural populations and improving the traffic scenario in the region, it will bear out several other socio-economic positive benefits.

168. The initial environmental examination of the subproject ascertains that the project is unlikely to cause any significant environmental impacts. No additional studies or need of undertaking detailed EIA is envisaged at this stage. The Executing Agency shall ensure that EMP and EMoP are included in Bill of Quantity (BOQ) and forms part of bid document and civil works contract. The same shall be revised if necessary during project implementation or if there is any change in the project design and with approval of ADB.

52 Appendix A: Location of Quarries and Water Sources

Appendix A: Location of Quarries and Water Sources 53

54 Appendix A: Location of Quarries and Water Sources

Appendix B: List of Officials and Issues Discussed in Field Visits 55

Sl. Name of Official Department Issue discussed Date No. Consulted Status of present road Adviser, North Eastern network in the North Eastern 13th May 1 Mr. P.K. Deb Council, Shillong Region, Scope of NESR 2005 Project

Conditions of road network, Executive Engineer, North scope of road improvement, 13th May 2 Mr. Haridas Eastern Council, Shillong environmental issues in north 2005 eastern India

Managing Director, Forest Forest development Development Corporation, schemes, timber trading in 17th May 3 Mr. G. Das Choudhary Govt. of Meghalaya, state, environmental impacts, 2005 Shillong deforestation,

Chief Conservator of Status of Wildlife in State, Forests (Wildlife), Office of Impacts on forests & wildlife, 25th May 4 Mr. Sunil Kumar PCCF, Govt. of Mitigation options, 2005 Meghalaya, Sylven Environmental friendly forest Bhavan, Shillong activities

Conservator of Forests Wildlife in state, Impacts on (Planning & GIS), PCCF 25th May 5 Mr. Subhash Ashutosh forests & wildlife, Mitigation Office, Sylvan Bhavan, 2005 options Shillong

Environmental Issues in the north-eastern region, legal framework of MoEF, applicable permits & Conservator of Forests clearances, forest resources Ministry of Environment & & wildlife in the north-east, Dr. B.S. Forests, North-East Impacts of proposed project 25th May 6 Kharmawphlang, IFS Regional Office, Upland on environment, IEE of 2005 Road, Laitumkhrah, proposed core road section, Shillong - (0361) 2227929 criteria for selection of core road section, major issues to be considered, wildlife conservation & mitigation measures

Research Officer, Directorate of Socio-economic conditions 17th May 7 Ms. A.M. Laloo Economics & Statistics, of the state 2005 Govt. of Meghalaya, Shillong

Legal framework of state 15th may 8 Mr. P. Somasundaram Legal Advisor, Shillong government wrt 2005 environment & wildlife

Statistical Officer, Socio-economic conditions Directorate of Statistical 17th May 9 Mr. S. Nongkoynrih in the state, major social & & Economics, Govt. of 2005 economic issues Meghalaya, Shillong 56 Appendix B: List of Officials and Issues Discussed in Field Visits

Sl. Date Consultation Name and Designation Topic Discussed No. with Department 01 12.04.08 PWD Mr.P.S.G.Lyndoh, Nodal The Project road drawing on the Officer, PWD Roads, Shillong district planning map 02 15.04.08 PWD Mr.Clithos W. Momin, SE, The Project road drawing and PWD Roads,Tura Circle impact on ecology and environment. 03 15.04.08 PWD Mr.Gromyko K. Marak Executive Engineer, PWD Roads, Barengapara Divn. 04 15.04.08 PWD Mr.Lemark Sangma, SDO The information of Technical,Ampaty Divn. Retaining/Breast Wall, proper chainage and formation width 05 15.04.08 PWD Mr.Freddy O.N.Sangma, The information of SDO-Technical, Barengapara Retaining/Breast Wall, proper Divn. Chainage and formation width 06 17.04.08 Forest Mr.J.Dutta,DFO-Social The forest Map, Flora List, Social Department Forestry,Tura,W.Garo Hills. Forestry data chainage wise, Mr.B.A.Sangma, RO, Tura Community forest Area, plantation Circle strategy, Plantation ratio 07 17.04.08 Forest Mr.P.R.Marak, DFO (WL) The Project road and if it passes Department Tura,East & W.Garo Hills through National park/Wild Life Sanctuary/Tiger Reserve/ Biosphere Reserve/Bird Sanctuary. 08 19.04.08 Forest Mr.Roaming, IFS Circulars/ Orders on restrictions/ Department DFO (T)-Garo Hills Divn. permission for carrying out road project.

Appendix C Photographs Taken During Consultations 57

Photographs during stake holders’ consultation

Mr. F.O.Sangma,L.Sangma,G.Marak and CW Momin Mr. P. S. G. Lyndoh, B. M. Syiem

Mr. J.Dutta,DFO-SF,Mr.Gromyko Marak,EE,PWD

Mr. Muktajul Haque, RO-Mahendragunj Mr. B.N.Sangma, RO-Tura 58 Appendix D: Environmental Management Action Plan (EMAP)

Supervising Environmental Location/ Implementing S.No. Mitigation Measures & Monitoring Issue sources Agency Agency Pre-Construction Phase Cutting of about • Restricting tree cutting within construction limit 9785 nos. trees • Avoiding tree cutting at ancillary sites Forest Dept. / 1 Tree cutting PIU during site • Providing and maintaining compensatory tree plantation of 29,355 PIU clearance numbers i.e. three times of cutting • Necessary planning and coordination with concerned authority and local body Concerned Removal of Work site 2 • Prior notice to and consultation with concerned authority, local utility agencies SC/ PIU utilities clearance body and public to be affected so as to ensure that work does not / PIU get affected and impact on public is minimum Religious • Suitable mitigation measures have been incorporated in Social 3 Work site PIU SC / PIU places report. Construction Phase Construction plants, equipment Refer Volume II-A and Volume II-B Contractor SC/PIU and vehicles • Maintaining diversion and detour for road traffic in good shape Temporary and traffic regulated. Contractor SC/PIU diversion • Regular sprinkling of water, as necessary. • Maintaining adequate moisture at surface of any earthwork layer Dust during completed or non-completed unless and until base course is 1 Air Pollution earth works or applied, to avoid dust emission. Contractor SC/PIU from spoil • Stockpiling spoil at designated areas and at least 5 m away from dumps traffic lane. • Refer Volume II-C Borrow pits and Refer Volume II-D Contractor SC/PIU haul road Storage of construction • Sprinkling of water as necessary. Contractor SC/PIU materials

Appendix D: Environmental Management Action Plan (EMAP) 59

Supervising Environmental Location/ Implementing S.No. Mitigation Measures & Monitoring Issue sources Agency Agency Construction of Bridges or Culverts - • Constructing and maintaining diversion channel, sedimentation Earthwork and basin, dykes, etc. as may be required to temporarily channelise marginal spillage water flow of streams / river Contractor SC/PIU of construction • Storage of construction material and excavated soil above high materials causing flood level temporary turbidity and suspended solids Construction • Strictly avoiding cleaning / washing of construction vehicle in any Water Contractor SC/PIU 2 vehicles water body Pollution • Proper planning of site clearing and grubbing so as not to keep the cleared site before working for long duration. Soil erosion from • Providing temporary side drains, catch water bank or drains, Contractor SC/PIU construction site sedimentation basin, as necessary to avoid or minimize erosion and prevent sedimentation to receiving water bodies Seepage from Construction • Refer Volume II-C Debris Construction camp and • Refer Volume II-B Contractor SC/PIU workers’ camp • All wastewater will be diverted to a ditch that will be managed for Wastewater the period of construction and after construction such ditches will Contractor SC/PIU logging be filled and restored to original condition. Borrow pit • Excavation of borrow pit should not touch the aquifer Contractor SC/PIU excavation Ground water • Providing septic tanks for treating sewage from toilets before 3 Pollution discharging through soak pits Human wastes • Locating soak pits at least 50m from any ground water sources and wastewater • Decanting and or controlled disposal of oil and grease as Contractor SC/PIU at construction collected at collection tanks of maintenance yard and chemical camp storage areas • Refer Volume II-B

60 Appendix D: Environmental Management Action Plan (EMAP)

Supervising Environmental Location/ Implementing S.No. Mitigation Measures & Monitoring Issue sources Agency Agency • Site Controls: Stationary equipment will be placed along un- inhabited stretches as per distance requirements computed above as far as practicable to minimize objectionable noise impacts. • Scheduling of Project Activities: Operations will be scheduled to coincide with period when people would least likely to be affected. Construction activities will be avoided between 9 P.M. and 6 A.M. near residential areas. • Protection devices (ear plugs or ear muffs) will be provided to the workers operating in the vicinity of high noise generating machines. • Construction equipment and machinery should be fitted with silencers and maintained properly. Noise Vehicles and • Source-control through proper maintenance of all equipment. 4 Pollution and Construction • Use of properly designed engine enclosures and intake silencers. Contractor SC/PIU Vibration machinery • Noise measurements should be carried out along the road to ensure the effectiveness of mitigation measures. • Vehicles and equipment used should confirm to the prescribed noise pollution norms. • Constructing noise barriers as proposed for schools and hospitals prior to taking up road construction activities at those sections. • Movements of heavy construction vehicles and equipment near public properties will be restricted. • Comply with siting criteria for stone crushers, Hot Mix Plant/s (HMP) and concrete batching plant/s (CBP), and installations and maintenance of pollution control devices as mentioned in Volume II-B. • Refer Volume II-E for identification, and operation of quarry areas and adopting controlled blasting

Appendix D: Environmental Management Action Plan (EMAP) 61

Supervising Environmental Location/ Implementing S.No. Mitigation Measures & Monitoring Issue sources Agency Agency • Providing impervious platform and oil and grease trap for collection of spillage from construction equipment vehicle maintenance platform • Collection oil and lubes drips in container during repairing construction equipment vehicles • Providing impervious platform and collection tank for spillage of Spillage from liquid fuel and lubes at storage area plant and • Providing bulk bituminous storage tank instead of drums for equipment at storage of bitumen and bitumen emulsion Contractor SC/PIU construction • Providing impervious base at bitumen and emulsion storage area camp and regular clearing of any bitumen spillage for controlled disposal 5 Land Pollution • Reusing bitumen spillage • Disposing non-usable bitumen spills in a deep trench providing clay lining at the bottom and filled with soil at the top (for at least 0.5 m) • Refer Volume II-A and B • Collecting kitchen waste at separate bins and disposing of in a pit Domestic solid at designated area/s waste and liquid • Collecting plastics in separate bins and disposing in deep trench Contractor SC/PIU waste generated at designated area/s covering with soil at camp • Collecting cottons, clothes etc. at separate bins and burning in a pit (with sand bed) • Controlled operation and redevelopment of borrow pits to avoid Borrow pits Contractor SC/PIU water logging and land contamination

62 Appendix D: Environmental Management Action Plan (EMAP)

Supervising Environmental Location/ Implementing S.No. Mitigation Measures & Monitoring Issue sources Agency Agency • The topsoil from all areas of cutting and all areas to be permanently covered shall be stripped to a specified depth of 150 mm and stored in stockpiles. At least 10% of the temporarily acquired area shall be earmarked for storing topsoil. • The stockpile shall be designed such that the slope does not exceed 1:2 (vertical to horizontal), and the height of the pile be restricted to 2m. To retain soil and to allow percolation of water, the edges of the pile shall be protected by silt fencing. • Stockpiles will not be surcharged or otherwise loaded and multiple handling will be kept to a minimum to ensure that no Loss of All construction 6 compaction will occur. The stockpiles shall be covered with gunny Contractor SC/PIU topsoil sites bags or tarpaulin. • It shall be ensured by the contractor that the topsoil will not be unnecessarily trafficked either before stripping or when in stockpiles. • Such stockpiled topsoil will be returned to cover the disturbed area and cut slopes. Residual topsoil will be distributed on adjoining/proximate barren/rocky areas as identified by the SC in a layer of thickness of 75mm – 150mm. Top soil shall also be utilized for redevelopment of borrow areas, landscaping along slopes, medians and incidental spaces. • Construction vehicle, machinery and equipment shall move or be stationed in the designated area (RoW or CoI, as applicable) Compaction All construction only. While operating on temporarily acquired land for traffic 7 Contractor SC/PIU of soil sites detours, storage, material handling or any other construction related or incidental activities, topsoil from agricultural land will be preserved as mentioned above. 8 Ecology Site clearance • Restricting tree cutting within corridor of impact Contractor SC/PIU

Appendix D: Environmental Management Action Plan (EMAP) 63

Supervising Environmental Location/ Implementing S.No. Mitigation Measures & Monitoring Issue sources Agency Agency • Minimizing tree cutting and vegetation clearance during site selection • Preservation of trees within ancillary sites and avoiding impact on forest resources by providing buffer area from boundary of PF, RF, national park and wildlife sanctuary of 1km for locating Ancillary sites Contractor SC/PIU construction plants, construction camp, and quarry and 500 m for borrow areas • Preservation of trees of ecological, socio-cultural importance • Providing cooking at camp for discouraging and prohibiting use of fire-wood i.e. cutting of trees by the workers. • Water supply, sanitation, drainage and medical health facilities at campsite • Providing and using PPEs Occupational • Using working reverse horn for all construction equipment and health and Construction vehicles 9 Contractor SC/PIU safety of camp • Providing earth link circuit breaker (ELCB) for all electrical workers connections • Maintaining first aid at construction sites • Maintaining emergency response system • Refer Volume II-B • Providing and maintaining traffic management comprising diversion; warning, guiding and regulatory signage; channelisers and delineators; lighting, flagmen; dust control system etc. as Construction specified in the contract. Contractor SC/PIU sites • Providing adequate light at construction zone if working during Accidents 1 night time is permitted by the Engineer and safety 0 • Conducting induction and periodic training for all workers and supervisors • Conducting periodic mock drilling on critical accident prone Construction activities Contractor SC/PIU camp • Conducting periodic training for all personnel working at plant site Operation Phase Vehicular • Periodicals monitoring of air pollutants and if values exceed SPCB and 1 Air Pollution gaseous PIU the standard limits, suitable mitigation measures to be Traffic Police emission taken.

64 Appendix D: Environmental Management Action Plan (EMAP)

Supervising Environmental Location/ Implementing S.No. Mitigation Measures & Monitoring Issue sources Agency Agency • Periodical monitoring of noise level will be carried out. If values exceed the standard limits, suitable measures will be taken. 2 Noise Pollution Vehicular PIU SPCB • Providing and maintaining signage on noise regulation at silence zones Traffic and Vehicles Maintenance of standard Highway Safety Signage and Traffic PIU and PIU Slow moving Management. Traffic Police 3 Road Safety traffic Lighting PIU/Traffic Maintenance of road / flyover lighting. PIU police Tree plantation Forest Dept. 4 - Roadside tree plantation three times of cutting PIU / PIU Contamination of Soil and • Contingency plans to be in place for cleaning up of spills of oil, Water fuel and toxic chemicals. 5 Resources Vehicular Traffic PIU PIU • Spill of oil, fuel and automobile servicing units without adequate from Spills preventive systems in place to be discouraged. due to traffic & Accidents Soil Erosion • Maintaining the slope protection measures provided at stretches and of high embankment and protection measures for bed scouring 6 PIU PIU Sedimentation at cross drainage locations as per maintenance manual to be prepared before operation Maintenance • The drains will be periodically cleared to maintain storm water of drainage flow. 7 - PIU PIU system • Road drains will be cleared of debris before onset of every monsoon.

Appendix E: Environmental Monitoring Plan 65

MONITORING RESPONSIBILITY Environmental Project Measurement Implementati Component Stage Parameters Standards Location Frequency Duration Supervision Method on SPM Gravimetric National Hot mix plant Once in a Continuous Contractor SC, PIU (High-Volume) Ambient /Batching Quarter and 24 hours/ or through Gravimetric Quality plant (1 as may be for 1 full approved RPM (High-Volume Standards location) instructed working day monitoring with Cyclone) (Refer by SC (for 3 agency EPA Modified Appendix C) years) SO2 West & Gaeke method NOx Arsenite Construction modified Jacob Stage & Hochheiser Air CO NDIR technique SPM, Same as Above National Stretch of the Once in a Continuous Contractor SC, PIU RSPM, SO2, Ambient road where Quarter for 24 hours/ or through NOX, CO Quality construction 3 years for 1 full approved Standards is in progress working day monitoring (Refer (1 locations)2 agency Appendix C) 1 location SPM, National Continuous PIU through throughout Half-yearly Operation RSPM, SO2, Ambient 24 hours/ or approved Same as above the stretch for first two PIU Stage NOX, CO, Quality for 1 full monitoring during years HC Standards working day agency operation Grab sample collected from pH, 2 locations source and temperature, Water quality trough out the Contractor analyzed as per Construction turbidity, standards by corridor will Once in a through IS : 2488 (Part 1- Water Quality stage (surface DO, BOD, CPCB be monitored Quarter for - approved SC, PIU 5) methods for water) COD, TDS, (Refer till end of 3 years monitoring sampling and TSS, Oil & Appendix C) construction agency testing of Grease period Industrial effluents

2 The need for carrying out monitoring at any additional locations would be decided by SC

66 Appendix E: Environmental Monitoring Plan

MONITORING RESPONSIBILITY Environmental Project Measurement Implementati Component Stage Parameters Standards Location Frequency Duration Supervision Method on Contractor All IS: 10500, Construction through parameters 1991 1 location at half yearly stage (ground approved SC, PIU of drinking (Refer Camp site for 3 years water) monitoring water Appendix C) agency Grab sample pH, collected from 1 location temperatur source and trough out the Operation e, turbidity, analyzed as per PIU through Water quality corridor will half yearly Stage DO, BOD, IS : 2488 (Part approved standards by be monitored for two - PIU (surface COD, TDS, 1-5) methods for monitoring CPCB till end of years water) TSS, Oil & sampling and agency construction Grease and testing of period Pb Industrial effluents Readings to Equivalent noise be taken at levels using an Noise As directed 15 seconds Contractor Noise integrated noise standards by by the Once in a interval for 15 through Construction levels on level meter kept Noise levels CPCB Engineer (At Quarter for minutes approved SC, PIU stage dB (A) at a distance of (Refer maximum 2 3 years every hour monitoring scale 10-15 m from Appendix C) locations) and then Leq agency edge of should be pavement estimated. Area of plantation Ensuring at Operation Rate of Physical along the For three Tree plantation least 75% - Forest Dept. PIU stage Survival verification road will be years survival specified by PIU

Appendix F: Details of Training Plan 67

Details of Training Plan

Module Title Objectives Duration Participants (Day) 1 Environmental • Brush up latest on environmental 1 PIU and SC Legislations and legislations staff Bank’s Safeguard • Brush up safeguard policies Policies

2 Environmental • EMP requirements 1 PIU and SC Supervision and • Implementation, Supervision and staff Monitoring Monitoring Mechanism • Provision made in Contract Documents for Works • Provision made in contract Agreement for Supervision Services 3 Orientation Workshop • EMP requirements 1 PIU, on EMP • Implementation, Supervision and Contractors Implementation Monitoring Mechanism and SCs • Roles and Responsibilities of Contractors and SCs

4 Focused Training on • Analyzing problems, referring 0.5 PIU, Specific Issue/s (three stipulations in Contract and EMP Contractors during course of and agreed to feasible solution and SCs implementation) within specified timeframe

68 Appendix G: Proposed Environmental Management Plan Budget

Proposed Environmental Management Plan Budget

SL. RATE AMOUNT ITEM DESCRIPTION QUANTITY UNIT RESPONSIBILITY NO. (Rs.) (Rs.) A Tree Plantation Plantation of trees (Compensatory plantation i.e Three times of total tree cut along road side) by road side in 0.6 m dia hole 1 m deep dug A.1 in the ground, mixing the soil with decayed farm yard sludge manual, 8,949 No. 285 2,550,465 PIU through planting the saplings, backfilling the trenches, watering and Forest maintaining plants for one year. Department Providing bamboo tree guard of height 1.2 meters above ground and A.2 8,949 No. 100 894,900 0.20 meter below ground for all tree other than bamboo tree.

B Informatory Boards along the project road in Elephant corridor section (from Mahendraganj to Purakhasia) Providing and erecting informatory board of size 800 mm x 600 mm at an interval of 2 km starting from Mahendraganj to Purakhasia along the project road by putting up hoardings "THE AREA IS ELEPHANT CROSSING ZONE". It should be made up as per IRC: 67 made of Contractor B.1 encapsulated lens type reflective sheeting vide clause 801.3, fixed 10 No. 5,872 58,720 through BOQ over aluminium sheeting, 2 mm thick supported on a mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved drawing.

B Environmental Monitoring

Ambient air quality monitoring as per Appendix B of EMP (2 location B.1 24 No. 4,000 96,000 in the interval of 3 months for 3 Years)

Ambient noise level monitoring as per Appendix B of EMP (2 location B.2 24 No. 500 12,000 PIU through in the interval of 3 months for 3 Years) Approved Water quality monitoring of surface water as per Appendix B of EMP Monitoring B.3 24 No. 3,500 84,000 (2 location in the interval of 3 months for 3 Years) Agency Water quality monitoring of drinking water from construction camp as B.4 per Appendix B of EMP (1 location in the interval of 6 months for 3 6 No. 3,750 22,500 Years)

F Noise Barrier at sensitive location

Appendix G: Proposed Environmental Management Plan Budget 69

SL. RATE AMOUNT ITEM DESCRIPTION QUANTITY UNIT RESPONSIBILITY NO. (Rs.) (Rs.) Provide the Noise barrier at sensitive areas like schools and hospitals. The noise barrier of hollow brick wall/reinforced concrete panels with Contractor F.1 height of 3.5m. The design of the noise barrier shall be approved by 120 Rm 4,000 480,000 through BOQ the engineer in charge, where as a typical drawing of noise barrier is given in Appendix G of EMP.

G Enhancement of cultural properties as per directed by the engineer including the following items Provision and erection of cement concrete, standard sitting benches G.1 30 No. 1,000 30,000 including clearing of the area around the benches. Contractor Boundary fencing with barbed wire fencing of approved make and through BOQ G.2 300 Rm. 550 165,000 specification including provision and errection of struts H Environmental Training PIU through Lump H.1 Training at site as per Appendix E of EMP 1 75,000 75,000 Supervision Sum Consultant Grand Total 4,468,585 (Rupe es)

70 Appendix H: Rapid Environmental Assessment (REA) Checklist

Rapid Environmental Assessment (REA) Checklist - MLN 1 Section

Country/Project Title: INDIA: North Eastern State Roads Project Sector Division: Roads and Highways Road Section: MLN-1: Garobadha – Dalu section in the State of Meghalaya – 93.35 km

Screening questions Yes No Remarks A. Project siting Is the project area adjacent to or within any of the following environmentally sensitive areas? ▪ Cultural heritage site X X The Project road passes though the pockets of community forest on hillocks at ▪ Protected area few places. Also there is road side plantation at some places. Specific mitigation measures with respect to flora and fauna will be followed strictly. ▪ Wetland X ▪ Mangrove X ▪ Estuarine X X Elephant corridor is passing from Mahendraganj to Purakhasia of approx ▪ Buffer zone of protected area chainage 75.0 km to chainage 95.1 km along the Project road. ▪ Special area for protecting X biodiversity B. Potential environmental impacts Will the project cause… Encroachment on historical/cultural Encroachment on historical/ cultural area areas; disfiguration of landscape by X has been updated in Social report. road embankments, cuts, fills, and Proper management plan will be required quarries? during construction to sustain the quarries. Encroachment on precious ecology X (e.g. Sensitive or protected areas)? Alteration of surface water X Project road is running parallel along some hydrology of waterways crossed by of the major/minor rivers/streams like roads, resulting in increased Goram, Bokman, Nagathi, Rongkhai, Pagla, sediment in streams affected by Cowhagra, Dimashi, Benkha, Kochadak, increased soil erosion at Goram etc. through most of the stretches of construction site? the Project road length. Controlled construction activities will ensure sediment discharge into streams to the extent.

Appendix H: Rapid Environmental Assessment (REA) Checklist 71

Screening questions Yes No Remarks Deterioration of surface water X Adequate Sanitary facilities and drainage in quality due to silt runoff and the workers camps will help to avoid this sanitary wastes from worker-based possibility. As the construction activity in camps and chemicals used in this project will not contain any harmful construction? ingredients, no impact on surface water quality is anticipated. Increased local air pollution due to X With appropriate mitigation measures and rock crushing, cutting and filling use of most modern environment friendly works, and chemicals from asphalt equipments/machineries air pollution shall processing? be reduced to permissible levels. Noise and vibration due to blasting X Short term minor impact may occur during and other civil works? construction period, suitable mitigation measures will be required to minimize the adverse effects. Dislocation or involuntary X This has been updated in Social report. resettlement of people Other social concerns relating to X Imposing of appropriate mitigation inconveniences in living conditions measures in contract agreement to keep in the project areas that may trigger the air pollution within permissible levels will cases of upper respiratory keep a check on this problem. problems and stress? Hazardous driving conditions where X To minimize the impact suitable traffic construction interferes with pre- management plan will be required. existing roads? Poor sanitation and solid waste Proper provisions for sanitation, health care disposal in construction camps and X and solid waste disposal facilities will be work sites, and possible available in the contract documents to avoid transmission of communicable such possibility. diseases from workers to local Workers will be made aware about populations? communicable diseases.

Creation of temporary breeding X habitats for mosquito vectors of disease? Dislocation and compulsory X It has been updated in social report. resettlement of people living in right-of-way? Accident risks associated with X Adoption of suitable traffic signage system increased vehicular traffic, leading at sensitive places will reduce such to accidental spills of toxic possibility. materials and loss of life? Increased noise and air pollution X Due to improvement in Riding Quality & resulting from traffic volume? Comfort in driving due to unidirectional traffic such pollution will be reduced. Mitigation measures along with monitoring plan will be required.

72 Appendix H: Rapid Environmental Assessment (REA) Checklist

Screening questions Yes No Remarks Increased risk of water pollution X Controlled construction activities and proper from oil, grease and fuel spills, and drainage system will reduce this possibility. other materials from vehicles using the road?

After reviewing the answers above the Mission Leader and Environment Specialist agree that the project.

should be categorized as an A project. X should be categorized as a B3 project. should be categorized as a C project. should be categorized as an A/B project because (give reason) . requires additional information for classification. Therefore,

3 As per IEE, September, 2006, the Project road has been categorised as category B, as no significant adverse impacts was envisaged. This was further emphasized in the revision of the IEE in 2011 which resulted in the further description of the notified Elephant Corridor from Mahendraganj to Purakhasia of approx chainage 75.0 km to 95.1 km along the Project road. Discussions with the Divisional Forest Officer, East and West Garo Hills Wildlife Division in Tura (see Appendix I) identified needed mitigation measures along this corridor to be implemented by the PWD.

Appendix I: Wildlife Clearance 73