HDraftARYANA Resettlement and Rehabilitation POWER Action Plan S – YSTEMPackage G 6 Transmission IMPROVEMENT lines Power SystemPROJECT Improvement Project RP769 v9 DRAFT RESETTLEMENT AND REHABILITATION ACTION PLAN

PACKAGE G-6 TRANSMISSION LINES, CIRCLE Public Disclosure Authorized 132 kV line Dhanonda to Nangal Mohanpur () 132 kV Dhanonda to Pali (Mahendragarh)

for

HARYANA VIDYUT PRASARAN NIGAM LIMITED

Public Disclosure Authorized

Public Disclosure Authorized

Prepared by

5th Floor, Tower C, DLF Building No.8, Cyber city Phase II Public Disclosure Authorized Gurgaon 122 022 (Haryana), Tel.(91) 124 4380042, 4501100 Fax.no. (91) 124-4380043 Email: [email protected] Web: www.smec.com.au/india

April 2009 Page 1

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

TTAABBLLEE OOFF CCOONNTTEENNTTSS LIST OF ABBREVIATIONS...... 4 EXECUTIVE SUMMARY...... 5 CHAPTER 1 – INTRODUCTION AND METHODOLOGY...... 7 1.1 Background...... 7 1.2 The Project- HPSIP ...... 7 1.3 Haryana Vidyut Prasaran Nigam Limited ...... 7 1.4 Package G-6 (Transmission Lines) ...... 8 1.5 Measures Taken to Minimize Impacts ...... 9 1.6 Objectives of the Study...... 9 1.7 Approach and Methodology ...... 9 1.8 Structure of the Report ...... 10 CHAPTER 2 – PROFILE OF THE PROJECT AREA ...... 11 2.1 Introduction...... 11 2.2 Profile of the Project Districts...... 11 CHAPTER 3 – SELECTION OF TRANSMISSION LINE ROUTE: ANALYSIS OF ALTERNATIVES ...... 13 3.1 Introduction...... 13 CHAPTER 4 – IMPACT ON LAND AND PERSONS...... 16 4.1 Introduction...... 16 4.2 Social Impact Assessment of the Proposed Sub-packages ...... 16 CHAPTER 5 – STAKEHOLDER CONSULTATIONS ...... 18 5.1 Introduction...... 18 5.2 Consultations for Sub-package VII ...... 18 5.3 Consultations for Sub-package VIII...... 21 CHAPTER 6 – RESETTLEMENT POLICY AND LEGAL FRAMEWORK...... 25 6.1 Policy, Legal and Regulatory Framework ...... 25 6.2 Procedure for Land Acquisition...... 25 6.3 World Bank Operational Policy on Involuntary Resettlement (OP 4.12) ...... 26 6.4 HVPNL Environment and Social Policy and Procedures ...... 27 6.5 Social Entitlement Framework...... 27 CHAPTER 7 – INSTITUTIONAL ARRANGEMENTS AND GRIEVANCE REDRESSAL MECHANISMS...... 32 7.1 Introduction ...... 32 7.2 Institutional Framework...... 32 7.3 Social Procedures...... 32 7.4 Capacity Building...... 33 7.5 Grievance Redress Mechanism ...... 34 CHAPTER 8 – BUDGET ESTIMATES ...... 36 8.1 Introduction...... 36 8.2 Compensation...... 36 8.3 Budget and Costs...... 36 CHAPTER 9 – IMPLEMENTATION SCHEDULE...... 39 9.1 Introduction ...... 39 9.2 Tasks and Schedule...... 39

Page 2

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

LLIIISSTT OOFF AANNNNEEXXUURREESS

Annexure A – Mahendragarh (11.260 km line) Annexure A1 – Photographs of area en-route in Mahendragarh (11.260 km) ...... 41 Annexure A2 – Community Consultations ...... 43 Annexure A3 – Walkover Survey and route marked on Toposheets...... 61

Annexure B - Mahendragarh (13.515 km) Annexure B1 – Photographs of area en-route in Mahendragarh (13.515 km)...... 63 Annexure B3 – Walkover Survey and route marked on Toposheets ...... 76

Annexure C - Rates of Trees and Crops Annexure C1 – Rates of Trees and Crops ...... 78

Annexure D - List of Officials Annexure D1 – List of Officials Met ...... 87

Annexure E - Formats Annexure E1: Consultation Checklist...... 89 Annexure E2: Census/Socio Economic Survey Questionnaire ...... 91 Annexure E3: Proforma for compensation of Standing Crops...... 98

Page 3

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

LIST OF ABBREVIATIONS AEE Assistant Electrical Engineer BPL Below Poverty Line ESMC Environment and Social Management Committee ER&RC Environmental Rehabilitation and Resettlement Committee ESIU Environmental and Social Implementation Unit ESPP Environmental and Social Policy and Procedures GOI Government of India GRC Grievance Redressal Committee HH Household HPGCL Haryana Power Generation Corporation Limited. HVPNL Haryana Vidyut Prasaran Nigam Limited IT Information Technology JE Junior Engineer kV Kilo volts LAA Land Acquisition Act, 1894 (1984) OP Operational Policy PAF Project Affected Families NGO Non Government Organization NRRP National Resettlement and Rehabilitation Policy 2007 PAF Project Affected Family RRAP Resettlement and Rehabilitation Action Plan ROW Right of Way SAMP Social Assessment and Management Plan SC Scheduled Castes SDO Sub-Divisional Officer TS Transmission System UHBVNL Utter Haryana Bijli Vitaran Nigam Limited XEN/EE Executive Engineer WB World Bank

Page 4

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

EXECUTIVE SUMMARY The proposed project – Haryana Power System Improvement Project, funded by the World Bank and implemented by Haryana Vidyut Prasaran Nigam Limited (HVPNL), aims to improve the accountability, efficiency and quality of electricity services in Haryana through investments in power supply infrastructure, training/capacity building and technology-transfer, and overall institutional strengthening.

Scope of the Resettlement and Rehabilitation Plan This plan looks into the resettlement issues for the transmission lines based on the walkover surveys provided by the HVPNL. The Resettlement and Rehabilitation Plan has been prepared for G-6 package consisting of 10 transmission lines1, in compliance with the Environment and Social Policy and Procedures (ESPP) of the HVPNL. The RRAP for G-6 has been prepared Circle-wise. This RRAP deals with the proposed transmission lines located in Gurgaon Circle.

Scope of Land Acquisition and Resettlement Social issues associated with power transmission line projects are mainly related to land required for footing towers, without any acquisition of land. Transmission line alignments have been finalized by avoiding/ crossing villages and settlement areas and trees. Official estimates indicate that for these transmission lines in , a total of 79 towers shall be footed for which the landowners would witness insignificant impact on their land. A total of 0.474 acres of land would be required for footing these 79 towers. Each landowner will lose only a small area for a tower and will be able to cultivate under the transmission lines and towers. The Project will not have adverse impact on livelihood or income.

The outcome of social impact assessment carried out for these transmission lines indicate that the, adverse impacts shall comprise: loss of crops during construction, temporary disturbance during construction and erection of transmission towers and stringing and potential change in land prices. These lines pass through 12 villages in the rural areas of these districts. A total of 42.84 acres of agricultural land will be covered by these transmission lines, thereby impacting standing crops during the construction period. Standing crops observed by the survey team were mainly mustard and wheat. However, HVPNL may like to avoid these standing crops by scheduling the timing of the construction works between two crops.

Community Consultations Consultations constituted an important tool to gauge people’s perceptions and to record their views with regard to the important infrastructure development that shall take place in their area. In addition, they were used as a medium to convey the ESPP and its relevant provisions. Community consultations were carried out in 11 villages with the respective Panchayats, village communities and women groups. These consultations brought forth the necessity of project intervention of this kind. Two distinct perceptions emerged from these discussions. At present

1 These transmission lines include Under Faridabad circle: 220 KV D/C Sector -72 Gurgaon to Rangala Rajpur (Firozepur-Zirka) line with 0.5 Sq. inch ACSR (Moose) via Nuh – 80 Km; Const. of 220 KV D/C Line with “ACSR (Moose) from proposed 400 KV substation Nawada (Faridabad) to 220 KV sub-station A-5 Faridabad – 6 km. Under Hisar circle; LILO of both circuits of existing 220 KV D/C 400 KV Mayar (PGCIL Hisar) S/Stn to Isherwal S/stn at 220 KV S/Stn Sangwan (Tosham) with 0.4 sqm “ACSR (Zebra) 2 x 20 = 40 Km; LILO of 132 KV Isherwal – Jui S/C line at 132 KV sub-station Kairu () with ACSR (Painther) – 4.2 Km; LILO of 132 KV S/C Hansi-Narnaud line at Masudpur (Hansi) with 0.2 Sq.inch “ACSR (Painther) – 13.620 km. Under Panchkula circle: 220 KV D/C line from 400 KV S/Stn PKL to 220 KV S/Stn Rawail (Panchkula) with 0.5 Sq.inch ACSR (Moose) – 13.2 Km; LILO of one circuit of 220 KV D/C Panchkula – Tapla line at 220 KV S/Stn Raiwali (Panchkula) with 0.4 sq. ACSR (Zebra) – 4.5 Km. Under Karnal circle: LILO of one circuit of 132 KV D/C PTPS – Chandauli line at 132 KV S/stn Kabri (Panipat) with 0.2 Sq.inch “ACSR (Painther) – 2.305 Km. Under Gurgaon circle: Const. of 132 KV S/C line on D/C tower with 0.4 sq. “ACSR (Zebra) from 220 KV Dhanonda to proposed 132 KV substation Nangal Mohanpur (Mahendragarh) – 11.260 km; const. of 132 KV S/C line on D/C tower with 0.4 sq “ACSR(Zebra) from 220 kv Dhanonda to proposed 132 KV Sub-station Pali (Gurgaon) – 13.515 km

Page 5

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project power supply is inadequate and demand for more power was unanimous to meet the domestic and agricultural needs of villagers across Mahendragarh regardless of their socio-economic status. Largely, communities were similar in their expectations of the project. They expressed concern about the compensation for land besides standing crops. They appreciated the efforts made by HVPNL in routing these lines. Safety emerged as major concern for most people and in particular for women folks, while they acknowledged the overall benefits that will accrue from these lines.

Resettlement Principles and Policy Framework This project is based on the resettlement principles of avoidance, minimization and alleviation. Among other principles, special attention has been paid for the improvement of living standards of marginalized and vulnerable groups and ensuring delivery of R&R entitlements and compensation for lost assets based on HVPNL’s entitlement framework. This project has taken into account the HVPNL’s Environment and Social Policy and Procedures, which covers the mandatory social requirements for HVPNL transmission works including Land Acquisition Act 1894, Haryana Government Rehabilitation & Resettlement Policy for land acquisition, WB OP 4.12 on Involuntary Resettlement and OP 4.10 on Indigenous Peoples. Besides, these policies, National Rehabilitation and Resettlement Policy 2007 too had been consulted while framing the ESPP. Public is informed about the project at every stage of execution by press notes and media release etc.

Entitlement Framework HVPNL’s framework is to ensure realistic rehabilitation and compensation of the acquired assets of the affected assets covering categories such as loss of land (homestead land, agriculture land, tenants, lease holders, encroachers/ squatters etc), loss of structure ( with valid title, tenants, lease holders, squatters, cattle sheds, workshop sheds etc.), loss of livelihood, Loss of standing crops/ trees, loss of access to common property resources (CPR) and facilities, losses to host communities, panchayat land and additional benefits for vulnerable persons. The entitlement for this subproject adopts and complies with the HVPNL’s framework. For this sub-project, only compensation for standing crops falls under the framework.

Institutional Framework and Grievance Redressal A three-tier set up is proposed in the ESPP of HVPNL viz., Divisional, Zonal and at Headquarters, comprising of Officials at respective levels. At the Head Quarter Level it is Environment, Resettlement and Rehabilitation Committee (ERRC), at Zonal level it is Environment and Social Monitoring Committee (ESMC), and at the Division level it is Environment and Social Implementation unit (ESIU). The grievance if any will be first addressed by the ESMC.

Compensation and Budget Estimates Compensation for this package pertains to standing crops only. These were calculated keeping in view the yield of crops and their rates. Compensation for land for tower base has not been calculated as it is not mandatory as per ESPP. Any claimant for compensation of tower land has to put up his/her case to the District Collector and only after assessing the impact on that particular family, the DC will decide on the compensation. Total compensation for crops has been estimated at Rs. 9,07,956/- (Rupees Nine Seven Thousand Nine Hundred and Fifty Six) only. Options for budget have been provided by taking cognizance of the alternative that HVPNL can schedule such as timing of the construction works between two crops, in which case compensation amount payable would be nil.

Page 6

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

CHAPTER 1 – INTRODUCTION AND METHODOLOGY

1.1 Background The power demand in Haryana on an average has been of the order of 7 to 8% in the past. Now it is in the range of 14% for the state as a whole and between 20-25% in certain pockets like in Gurgaon district. In response to this increasing demand, HVPNL has prepared a comprehensive transmission program that proposes power load growth and evacuation of the proposed capacity addition of power at an estimated cost of Rs. 7643 crore during the 11th Five year plan. Under this program HVPNL will undertake construction of new sub-stations, installations of additional transformers and laying of new transmission lines interlinking of lines of existing substations.

The state of Haryana in the northern part of India is located strategically close to the National Capital of India New Delhi, and one third of its area falls within the National Capital Region (NCR). It is bordered by Himachal Pradesh and Punjab to the north and by to south and west. Its borders to Uttar Pradesh and Uttaranchal in the East are defined by the River Yamuna. The capital of the state is Chandigarh which is administered as a Union Territory and is also the capital of Punjab.

1.2 The Project- HPSIP The proposed project – Haryana Power System Improvement Project (HPSIP), funded by the World Bank, aims to improve the accountability, efficiency and quality of electricity services in Haryana through investments in power supply infrastructure, training/capacity building and technology-transfer, and overall institutional strengthening. Major objectives include improving service delivery; enhancing operational efficiency and institutional capacities. The improvement of service delivery of the transmission company i.e. HVPNL is aimed at by ensuring efficient transmission of additional power to be available within the state over the next 4 years; providing greater grid stability and system security; and by facilitating the transmission to an open access regime within the state. Another important objective, which the project has envisaged includes enhanced operational efficiency and customer service levels in selected geographical areas of Haryana through investments. This project’s third important target is to enhance institutional capacities of three utilities in the transmission lines and distribution sub-sectors through introduction of modern management practices.

In this context, the World Bank is supporting the strengthening of transmission system for enhancing reliability and system security as well as to reduce transmission losses, by constructing new sub-stations and transmission lines. The project is being executed by the Haryana Vidyut Prasaran Nigam Limited (HVPNL). HVPNL has divided the current phase of work into 13 packages consisting of substations and transmission lines.

1.3 Haryana Vidyut Prasaran Nigam Limited In 1998, the Haryana State Electricity Board (HSEB) was re-organized into State owned corporation namely Haryana Vidyut Prasaran Nigam Limited (HVPNL) for Transmission and Haryana Power Generation Corporation Limited (HPGCL). HPGCL was made responsible for operation and maintenance of State’s own power generating stations. HVPNL was entrusted the power transmission and distribution functions. Simultaneously, an independent regulatory body i.e. Haryana Electricity Regulatory Commission (HERC), was constituted to aid and advise the State Government on the development of the power sector, to regulate the power utilities and take appropriate measures to balance the interest of various stake-holders in the power sector, namely electricity consumers, power entities and generation companies etc.

Page 7

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

HVPNL was further reorganized on July 1, 1999 by carving out two more Corporations, namely Utter Haryana Bijli Vitran Nigam Ltd. (UHBVNL) and Dakshin Haryana Vitran Nigam Ltd. (DHBVNL) with the responsibility of distribution and retail supply of power within their jurisdiction. While UHBVNL is responsible for Ambala, Yamunanagar, Kurukshetra, Kaithal, Karnal, Panipat, Sonepat, , Jhajjar and Jind districts, DHBVN caters to Hisar, Fatehabad, Bhiwani, Sirsa, Faridabad, Gurgaon, Mewat, and districts.

1.4 Package G-6 (Transmission Lines) Under this package, ten transmission lines are proposed. These lines are spread in five HVPNL circles in the state of Haryana. Circle-wise lines are given below sub-packages under Package G-6 as listed below: Under Faridabad circle (i) 220 kV D/C Sector -72 Gurgaon to Rangala Rajpur (Firozepur-Zirka) line with 0.5 Sq. inch ACSR (Moose) via Nuh – 80 Km (ii) Const. of 220 kV D/C Line with “ACSR (Moose) from proposed 400 kV substation Nawada (Faridabad) to 220 KV sub-station A-5 Faridabad – 5.6 km

Under Hisar circle (iii) LILO of both circuits of existing 220 KV D/C 400 kV Mayar (PGCIL Hisar) S/Stn to Isherwal S/stn at 220 kV S/Stn Sangwan (Tosham) with 0.4 sqm “ACSR (Zebra) 2 x 20 = 40 Km (iv) LILO of 132 kV Isherwal – Jui S/C line at 132 KV sub-station Kairu (Bhiwani) with ACSR (Painther) – 4.2 Km (v) LILO of 132 kV S/C Hansi-Narnaud line at Masudpur (Hansi) with 0.2 Sq.inch “ACSR (Painther) – 13.620 km

Under Panchkula circle (vi) 220 KV D/C line from 400 kV S/Stn PKL to 220 KV S/Stn Rawail (Panchkula) with 0.5 Sq.inch ACSR (Moose) – 13.2 Km (vii) LILO of one circuit of 220 kV D/C Panchkula – Tapla line at 220 kV S/Stn Raiwali (Panchkula) with 0.4 sq. ACSR (Zebra) – 4.5 Km

Under Karnal circle (viii) LILO of one circuit of 132 kV D/C PTPS – Chandauli line at 132 kV S/stn Kabri (Panipat) with 0.2 Sq.inch “ACSR (Painther) – 2.305 Km

Under Gurgaon circle (ix) Const. of 132 kV S/C line on D/C tower with 0.4 sq. “ACSR (Zebra) from 220 kV Dhanonda to proposed 132 kV substation Nangal Mohanpur (Mahendragarh) – 11.260 Km (x) Const. of 132 kV S/C line on D/C tower with 0.4 sq “ACSR(Zebra) from 220 kv Dhanonda to proposed 132 kV Sub-station Pali (Gurgaon) – 13.515 km

These lines cross ten districts in the state, viz., Palwal, Faridabad, Bhiwani, Panchkula, Karnal, Rewari, Mewat, Mahendgarh, Hisar and Panipat. The present report deals with the transmission lines of Gurgaon circle, located in Mahendgarh district and contain the findings of the impacted area. The report is prepared in conformity with the provisions of the Environment and Social Policy and Procedures of HVPNL.

Page 8

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

1.5 Measures Taken to Minimize Impacts Alignments of transmission lines in rural areas have been finalized in accordance with HVPNL’s R&R policy of avoidance, minimization and alleviation, wherein efforts were made to minimize the adverse impacts of the project, while selecting the route. Criteria considered for selection of optimum route, are the following: (i) The route of the proposed transmission lines does not involve any human habitation; (ii) Any monument of cultural or historical importance is not affected by the route of the transmission line; (iii) The proposed route of transmission line does not create any threat to the survival of any community; (iv) The proposed route of transmission line does not affect any public utility services such as playgrounds, schools and other establishments; (v) The line route does not pass through any sanctuaries, National Park, Biosphere reserves or eco-sensitive zones; and (vi) The line route does not infringe with area of natural resources.

1.6 Objectives of the Study The main objective of the study was to:  identify the impacts of land acquisition and other adverse impacts for various civil works on the people, who own properties to be acquired or used for the project; and  present an action plan for delivery of the compensation and assistance as outlined in the policy to the persons identified as entitled to such assistance.

Scope of the study The scope of the present study is to conduct a survey for these transmission lines for. a) identifying potentially affected populations with special attention to vulnerable group such as scheduled caste, landless households and women headed/physically handicapped households. b) gathering information on various categories of losses and other adverse impact likely under the project. These are:  loss of land and other productive assets such as trees;  loss of structures, temporary or fixed;  loss of access to public services (roads, drinking water, schools, medical, etc);  loss of access to common property resources; and  disruption of social, cultural, religious or economic ties and networks

1.7 Approach and Methodology Approach and methodology mainly consist of qualitative and quantitative tools and techniques. The study was conducted in three phases.

Phase I - Collection and review of documents: This involved collection of documents from client such as walkover survey and relevant topographic maps. This phase was important to scope the activities. It also included preparation of social assessment tools, questionnaires and Focus Group Discussion (FGD) guidelines. The Questionnaires and Checklist for FGDs are presented in the Annexure-E1 & E2.

Phase II - Survey Activities: The phase combined field visitg using the walkover survey and holding consultations, in order to assess the impact if any on any private/ community/government assets. The survey team walked along the route to observe and record socially sensitive receptors, current land use and cropping pattern. The survey, assessed the

Page 9

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project likely impacts of the project, the socio-economic conditions, and living standards of the impacted population. Consultations were held with key informants and the qualitative survey included focus group discussions and in depth interviews with various sections of people such as women, knowledgeable persons, community leaders. It sought to elicit their expectations and suggestions, willingness to contribute, their perceptions of the project and also to convey the likely benefits from the project.

Phase III - Post Survey Activities Analysis and Reports: The information collected through structured interviews and questionnaires was systematically validated, analyzed and processed. Wherever required, the observations were supported from the information collected through desk research.

1.8 Structure of the Report The Chapterisation plan for this RRAP is given in the Table below: Chapters Title of Chapter Brief Description of Contents 1 Introduction and Methodology Project description, approach and methodology adopted 2 Profile of Project Area District profile of Mahendragarh (inclusive of population, social composition – SC population, poverty, education, work force etc.) Impacted villages and their socio-economic profile covering Population, gender, economic activities, workers non-workers, poverty literacy, composition, unemployment, Land use 3 Analysis of Alternatives Analysis of Alternative for routes of transmission lines

4 Impact on Land and persons Adverse/positive Impacts on persons/land/private properties/common property resource; Alternatives, Impact on crops, Landholding size / cropping pattern/standing crops / Estimated impact on crops 5 Community Consultations Details on the community consultations with villagers and vulnerable group (women)

6 Resettlement Policy and Legal HVPNL policy and entitlements and its applicability Framework 7 Institutional Arrangements & Mechanisms for implementation, and grievance Grievance Redress Mechanisms redressal

8 Costs and Budget Compensation for crops and trees and cost estimates for implementation of RRAP 9 Implementation Schedule Time duration for implementation of RRAP

Annexures

Annexure A – Mahendgarh (11.260 km line) Annexure B – Mahendgarh (13.515 km line) Annexure C – Crops and Tree Rates Annexure D – List of Officials Annexure E – Formats and Questionnaires

Page 10

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

CHAPTER 2 – PROFILE OF THE PROJECT AREA

2.1 Introduction This chapter provides a very brief overview of project district through which these two transmission lines pass through under Package G-6 and socio-economic profile of villages through which these proposed lines are likely to pass. These include working population and social composition such as proportion of Scheduled Castes (SCs) to the overall population. The sub-packages pass through Mahendragarh district of Haryana.

2.2 Profile of the Project District

Mahendragarh district formed in the year 1948 has a total area of 1899 sq.km. It is bounded on the north by Bhiwani and Rohtak districts, on the east by and of Rajasthan, on the south by Alwar, Jaipur and Sikar districts of Rajasthan, and on the west by Sikar and Jhunjhunu districts of Rajasthan. It has 2 tehsils of Narnaul and Mahendergarh.

Figure 2.1 – Map of Mahendragarh District

Table 2.1 – Profile of Mahendragarh district S.No. Name of Total Female Male SC Total Main district Population Workers Workers 1 Mahendragarh 812521 388443 423578 132512 351864 204704 Source: Census of India, 2001

The district of Mahendragarh has population less than 10 lakhs with nearly a fourth (25%) constituting its workforce (See Table 2.1).

2.3 Socio-economic Profile of Impacted Villages Transmission lines under Gurgaon circle (i) Const. of 132 KV S/C line on D/C tower with 0.4 sq. “ACSR (Zebra) from 220 kV Dhanonda to proposed 132 KV substation Nangal Mohanpur (Mahendragarh) – 11.260 km

Page 11

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

(ii) Const. of 132 KV S/C line on D/C tower with 0.4 sq “ACSR(Zebra) from 220 kv Dhanonda to proposed 132 KV Sub-station Pali (Gurgaon) – 13.515 km

The proposed transmission line from Dhanonda to Nangal Mohanpur will passes through five villages along its route. The socio-economic profile of these villages is provided in Table 2.2. The Table indicates the villages are having a population of less than 5000. The presence of Scheduled Castes is between 10-15% of the total population. In terms of workforce, Malra village has more than 48% of its population as its workforce. In case of Jhagroli, the share is only about 30%. Table 2.2 – Socio-economic details of villages en-route 11.260 km line S.No. Name of Name of Total Female Male SC Total Main district village Population Workers Workers 1 Mahendragarh Malra 4392 2130 2262 600 2023 1197 2 -do- Jhagroli 3144 1512 1632 520 981 569 3 -do- Pathera 4752 2237 2515 487 2133 920 4 -do- Dhanunda 7332 3421 3911 1452 3253 1930 5 Gurha -do 3472 1633 1839 944 1506 966 Khema Source: Census of India, 2001

The proposed transmission line from Dhanonda to Pali will pass through villages viz. Lawan, Dhanonda, Aghiar, Bhagdana and . The socio-economic profile of these villages is provided in Table 2.3. It is evident from the table that except Dhanonda and Pali, all other villages have a population of less than 2500.

Table 2.3 – Socio-economic details of villages en-route 13.515 km line S.No. Name of Name of Total Female Male SC Total Main district village Population Workers Workers 1 Mahendragarh Lawan 2199 1125 1074 313 916 426 2 -do- Dhanunda 7332 3421 3911 1452 3253 1930 3 -do- Agihar 1702 832 870 541 705 301 4 -do- Bhagdana 2142 1035 1107 179 1267 779 5 -do- Jhook 1866 890 976 199 1174 471 6 -do- Pathera 4752 2237 2515 487 2133 920 7 -do- Pali 6082 2866 3216 1414 2412 1361 Source: Census of India, 2001

Page 12

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

CHAPTER 3 – SELECTION OF TRANSMISSION LINE ROUTE: ANALYSIS OF ALTERNATIVES

3.1 Introduction This chapter deals with the selection of optimum route for transmission lines and an overview of the generic anticipated impacts in context of these lines. Following which, it analyses the already finalized alignment for each of the transmission line by comparing it with alternative explored, if any. Wherever, the alternative was not explored, the smallest distance from the two points was taken as another route for the purpose of analysis. It does so by stating the features observed en- route and the resultant potential impacts on features such as: impacts on land, structures properties, common property resources, crops and trees. The impact assessment includes landholding size/cropping pattern/standing crops, estimated impact on crops, anticipated impact on aesthetic appeal of the project affected area.

As per the provision contained in Haryana Electricity Reforms Act 1997 & Electricity Act, 2003, HVPNL has authority to install transmission towers in any kind of land. In transmission projects land is not acquired for footing towers. For selection of optimum route and siting of towers, HVPNL exercises certain flexibility, by taking the following criteria into consideration:  The route of the proposed transmission lines does not involve any human habitation;  Any monument of cultural or historical importance is not affected by the route of the transmission line;  The proposed route of transmission line does not create any threat to the survival of any community;  The proposed route of transmission line does not affect any public utility services such as playgrounds, schools and other establishments;  The line route does not pass through any sanctuaries, National Park, Biosphere reserves or eco-sensitive zones; and  The line route does not infringe with area of natural resources.

In case of transmission lines in Gurgaon circle, the potential impacts are: i) Land for footing the transmission towers: The amount of land required for footing2 a tower for 220 kV line and 132 kV line is 49 sqm. (approx. 0.012 acre) and 25 sqm. (approx. 0.006 acre) respectively. As per official estimates a total of 79 towers are to be placed for the transmission line in this circle. A tower is placed every 300-350 meters; ii) 7 meter Right of Way: The RoW for line through different areas whether it be the agricultural fields or semi-urban areas; iii) Height: 4.6 metre for a 220 kV tower and 4.0 meter for a 132 kV tower is the minimum clearance between conductors and tops of trees and need to be maintained during the operation stage; iv) Restrictions imposed on the area under the transmission lines and height of trees and crops, though usage of such land continues as before; v) Land holding could become unviable, particularly for the vulnerable groups; vi) Damages that occur to standing crops and other trees during construction and operation;

2 Depending upon the tower type – A or B or C or D used, the area of land required for footing a tower could vary, but is likely to be between 25 sq.m or 49 sq.mtr

Page 13

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

vii) Cutting and trimming of trees to maintain the proper clearances in ROW.

3.2 Analysis of Alternatives The survey team walked along the proposed route of the two transmission lines (see Annexure A3 for walkover survey). Details regarding length of the line, with number of villages and towers that required to be footed are provided in Table 3.1 below.

Table 3.1: Details of sub-packages (Gurgaon circle) S. Name of Transmission line Length of No. of towers No. of villages/ urban No. line (in footed area that the finalized Km.) transmission line route shall pass through 1 Const. of 132 KV S/C line on D/C tower with 11.26 36 5 0.4 sq. “ACSR (Zebra) from 220 KV Dhanonda to proposed 132 KV substation Nangal Mohanpur (Mahendragarh) 2 Const. of 132 KV S/C line on D/C tower with 13.515 43 7 0.4 sq “ACSR(Zebra) from 220 kv Dhanonda to proposed 132 KV Sub-station Pali (Gurgaon) Total 24.775 79 12

Details of the land use, other observation in terms of cropping patterns, and socio-economic profile of the villages adjacent to /crossing the villages are dealt with in the subsequent paragraphs.

3.2.1 132 KV S/C line on D/C tower with 0.4 sq. “ACSR (Zebra) from 220 KV Dhanonda to proposed 132 KV sub-station Nangal Mohanpur (Mahendragarh) – 11.260 Km

Table 3.2: Comparison of the finalized alignment and straight line option (11.260 km) Stretches Option 1 – Finalized Sensitivity Option 2 - If the alignment had Sensitivity alignment Y / N taken the shortest route Y / N Impacts based on features observed as per maps and survey Dhanunda Crosses the Charkhi Dadri road N Crosses the Charkhi Dadri road but Y village to and circumvents Pathera village would have impacted Pathera Pathera habitations village habitations village Pathera Avoids Village Gurha Khemla N Would have impacted Gurha Y village to by crossing another road Khemla village Jhagroli village Jhagroli Crosses the road to N Would have crossed the road to N village to Mahendragarh and another Mahendragarh and another railway Nangal railway crossing also crossing also Mohanpur village Y-Yes, N-No

The analysis of alternative reveals that the finalized alignment as indicated in the walkover survey has taken cognizance of the socially sensitive receptors such as habitations that fall en- route (see Annexure B2 for walkover survey). Hence this route is the optimum route for this transmission line. Table 3.3 contains the details of area required for tower base and number of tower bases required en-route.

Page 14

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Table 3.3: Area impacted by 11.260 km line Length of Right of way Total Area No. of Area required total area required Potentially line for a 132 KV (in acres) towers per tower (in for towers (in Impacted (in Km). line (in meters) acre) acres) plots/ Households 10 7 19.47 36 0.006 0.216 36 Source: Walkover survey

3.2.2 132 KV S/C line on D/C tower with 0.4 sq “ACSR(Zebra) from 220 kV Dhanonda to proposed 132 KV Sub-station Pali (Gurgaon) – 13.515 km Table 3.4: Comparison of the finalized alignment and straight line option (13.515 km) Stretches Option 1 – Finalized Sensitivity Option 2 - If the alignment had Sensitivity alignment Y / N taken the shortest route Y / N Impacts based on features observed as per maps and survey Dhanunda to Travels along an existing road N Would have been same as option I N Pali for its entire length and avoids habitations on either side by 2-5 km Source: Walkover survey Y-Yes, N-No

The analysis of alternative reveals that the finalized alignment as indicated in the walkover survey has taken cognizance of the socially sensitive receptors such as habitations on either side of the road and hence is the most optimum route length. Table 3.5 contains the details of area required for tower base and number of tower bases required en-route.

Table 3.5: Area impacted by 13.515 km line Length of Right of way Total Area No. of Area required total area required Potentially line for a 132 KV (in acres) towers per tower (in for towers (in Impacted (in Km). line (in meters) acre) acres) plots/ Households 13.515 7 23.37 43 0.006 0.216 43 Source: Walkover survey

Page 15

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

CHAPTER 4 – IMPACT ON LAND AND PERSONS

4.1 Introduction Like any investment in linear projects transmission lines impact inhabitants. This chapter provides details on the potential impacts that have been assessed during the survey and in consultations with the villagers. Socio–economic assessment of the proposed transmission line brought forth three types of impact on affected persons: 1. Agriculture land owner will experience insignificant impact due to tower erection; 2. Agriculture land owner will experience loss of crops during implementation; and 3. Reduced/potential drop in agricultural land rates through which the line is passing.

4.2 Social Impact Assessment of the Proposed Sub-packages

4.2.1 Const. of 132 KV S/C line on D/C tower with 0.4 sq. “ACSR (Zebra) from 220 KV Dhanonda to proposed 132 KV substation Nangal Mohanpur (Mahendragarh) – 11.260 km Impact of footing of towers shall be felt 4 villages namely – Nangal Mohanpur, Jhagroli, Gurha- Kemla, Malra and Dhanonda. The land use is predominantly agricultural with nearly 90% of the area en-routte under cultivation wherein crops such as Mustard and Wheat were observed. Other features road, canal, railway track and barren comprise the balance area. While HVPNL shall and can make efforts to minimize the crop damage by starting the work following the harvest season, it shall not be possible in all cases. Habitations have been avoided as per the policy. It is expected that 36 towers would be laid across the 11.26 km stretch and would have the following impacts in terms of area as given in table 4.1.

Table 4.1 – Impacted agriculture area by 11.260 km transmission line Area (acres) Agriculture land (in acres) Estimated Crop area by type Barren / Others of crop (in acres) (in acres) 19.47 18 Mustard 10 1.47 Wheat 8 Source: Preliminary Survey

Page 16

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

4.2.2 Const. of 132 KV S/C line on D/C tower with 0.4 sq “ACSR(Zebra) from 220 kv Dhanonda to proposed 132 KV Sub-station Pali (Gurgaon) – 13.515 km The line starts adjacent to the road between Mahendragarh and Charkhi Dadri and the entire length of the line is falls over the agricultural area. It crosses the road that leads to village Malra as well and near the end of its length it crosses an existing canal. There are a total of 7 villages – Jhook, Dhanonda, Agihar, Malda, Lawan, Pali, Bhagdana and Pathera en-route. Habitations are nearly 3-6 km away on either side of the line and are clearly avoided. Impact on crops is the only impact that shall take place. During the implementation after tower points are fixed, an assessment by the implementing agency will give the exact number of plots impacted and extent of impact in terms of number of PAPs owning the land, particularly on BPL families. 43 towers are expected to be laid across the 13.515 km stretch and would have the following impacts in terms of area as given in table 4.2. As indicated in the table, the entire route passes through agricultural land for nearly 90% of its entire length. Crops observed by the survey team during the visit were Mustard and Wheat.

Table 4.2 – Impacted agriculture area by 13.515 km transmission line Area (acres) Agriculture land (in acres) Estimated Crop area by type Barren / Others of crop (in acres) (in acres) 23.37 21 Mustard 12 2.37 Wheat 9 Source: Preliminary Survey

Page 17

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

CHAPTER 5 – STAKEHOLDER CONSULTATIONS

5.1 Introduction Consultation refers to the two-way transfer of information or joint discussion between project staff and the community in concern. It helps identify impacts in general and on vulnerable groups, in particular. It provides some of the details that planners cannot foresee. Besides information provided during such consultations help allay fears and misinformation.

Under this package, three sets of consultations were held – with the officials, with Panchayats and community members and with women’s groups. Consultations with officials were carried out to understand the coverage of the lines, the proposed route, the difficulties felt in selecting the most appropriate alignment, criterion adopted therein and the alternative routes explored, if any. Consultations with Panchayat/Village community members were carried out based on the list of issues that were part of the consultation checklist developed (see Annexure E1), and covered a host of issues, such as current land holding, BPL status, education, health, types of crops cultivated, likely employment opportunities, etc in order to assess the impact, identify vulnerabilities and understand their perceptions. Consultations with women’s groups were held to understand their perceptions and understand the variations in their perceptions towards a similar infrastructure development. An attempt was made to understand the current power supply status, development schemes of government and other on-going development work in the village. This chapter presents the summary of consultations held.

5.2 Consultations for Sub-package VII 132 KV S/C line on D/C tower with 0.4 sq. “ACSR (Zebra) from 220 KV Dhanonda to proposed 132 KV substation Nangal Mohanpur (Mahendragarh) – 11.260 Km

Consultations with Officials: Consultants met with Superintending Engineer T/S Circle, Gurgaon, SSE, 220 kV substation, Mahendragarh, Executive Engineer (EE), Civil, Mahendragarh and XEN, T/S Division, Rewari (See Annexure D for List of Officials met). Consultations with officials indicated that the line was one of the two lines that shall begin from Dhanonda sub-station to the proposed 132 kV sub-station at Nangal Mohanpur. Further they indicated that the route of the line shall take it over agricultural fields of village such as Pathera, Jhagroli, Gurha Kemla, Agihar and Dhani. It shall also cross certain other features en-route such as Mahendragarh canal, the Nangal distributory and also a railway line near Gurha Kemla. They indicated that, in particular, sharp deviations have been taken to avoid habitations. In fact the reason for the length of the line to be longer than required is to circumvent the villages of Pathera and Gurha Kemla before terminating at Nangal Mohanpur village.

Consultations with Community: Of the villages that fall en-route this line, consultations were held at Gurha Khemla and Pathera villages.

Consultations were held with Panchayat members and village community to inform them about the project, understand their view and the benefits that they are likely to receive. Attempt was made to see if the project would impact them positively or negatively. These covered a host of issues such as current land holding, crops sown, land area and holdings, and potential employment opportunities.

Agriculture is the primary occupation of the all these villages. Crops such as mustard, wheat and bajra are grown. Electricity supply is only available for about 4-5 hours of power is available in

Page 18

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project a whole day. Difficulties are faced by many in the village on different aspects such as crop failure due to poor irrigation, studies of children get disrupted due to poor supply. Electrical appliances such as televisions and coolers are non-functional either due to no supply or they are not in working order due to sudden fluctuations. They observed that water is saline and not good for consumption and therefore better water supply is as critical a need just like better power supply. Summers are often difficult as the heat is unbearable.

Consultations included information dissemination on the 220 kV line, details on likely period of commencement of construction works; height of the towers; time duration of construction, the ROW that would be required. Other information that were highlighted included the requisite safety norms such as ground clearance of transmission wires from trees/structures, potential restrictions on land use, height of trees were also covered. They were informed of the selection criteria adopted for routing these lines where the overriding principle was to avoid habitations as these were high tension lines.

Other impacts: On impacts, they were informed about the land below the towers, potential depreciation of prices of land, restrictions and other trees that are grown. These included aspects such as trimming of trees for maintenance purposes. They accepted the restrictions on the heights of crops and trees.

They were informed of the process of erecting transmission towers – stubbing, erecting and stringing of wires. It was informed that the process required excavators that remove the earth for footing the four legs of each tower. Movement of equipment shall result in damage to crops particularly if there is no other access available. Whereas attempts shall be made to ensure that such works are taken up during the post harvest season and thereby ensure minimum damage, it would not be possible to do so in all cases. Compensation will be calculated as per the prevalent rates and will be disbursed to the eligible owner of the plot. The villagers in response accepted the information and requested that compensation for crops should be given, though they preferred that such works be taken during the off-season.

Safety: They understood this development as necessary to providing the crucial infrastructure of power supply. However, they requested that safety norms be adhered to. They also observed there have been a few instances of a cattle dying because of accidents due to wires, but people have been safe thus far.

Perceived benefits: Benefits of the project too were highlighted and majority of the consulted stakeholders stated better power supply would positively impact their lives in many ways and this was a much needed development. They summed it up by saying that in these modern times, electricity is as essential as water and no work is possible without it. They emphasized that the electricity was the key to diversifying beyond agriculture.

Among other issues, water supply was a major issue. While some villages stated schools were at a distance, others were satisfied on this account. They indicated that installation of handpumps and deep tubewells have been the outcome of this scarcity which has further depleted the ground water.

Consultations with women: No specific consultations with women were held in villages enroute this line.

Page 19

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

CONSULTATIONS WITH COMMUNITY AND WOMEN GROUP

Page 20

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

5.3 Consultations for Sub-package VIII 132 KV S/C line on D/C tower with 0.4 sq “ACSR(Zebra) from 220 kV Dhanonda to proposed 132 KV Sub-station Pali (Gurgaon) – 13.515 km

Consultations with Officials: Consultants met with Superintending Engineer T/S Circle, Gurgaon, SSE, 220 kV substation, Mahendragarh, Executive Engineer (EE), Civil, Mahendragarh and XEN, T/S Division, Rewari. Officials indicated that the line was other transmission line that shall commence from the Dhanunda station. This line, shall terminate at the proposed 132 kV sub-station at village Pali. The line travels along the existing road and hence no deviations were required as the entire route is adjacent to a road. Habitations or villages of Pathera, Agihar, Buwana, Jhook, Malda are at a 2-3 kms from the line.

Consultations with Community: Consultations were held in 4 villages i.e. Pali (site for proposed 132 kV sub-station), Malra, Pathera and Dhanunda (starting point of this line). Consultations were held with Panchayat member and village community to inform them about the project, understand their view and the benefits that they are likely to receive. Attempt was made to see if the project would impact them positively or negatively. These covered a host of issues such as current land holding, crops sown, land area and holdings, and potential employment opportunities.

Agriculture is the mainstay of the majority along the proposed route though in the village of Pali, there are many who are employed in the defense services. Mostly crops such as Mustard, Wheat, Bajra and Chana are grown.

Problems faced and impact of the project: They reportedly receive only 3-4 hours of power supply in a day. Summer months are very difficult for them particularly as demand for electricity and water – two precious commodities that are essential but are in short supply. It becomes a nightmare to live through the scorching summer months. While they feel the heat within their houses, their cattle feel it even more as they are tied outside and the shade is insufficient. Winter months are better as they can make do with the available power. They reported that when approach officials often sited overload on existing transformers as the reason many a times, but it is something that the government and officials should attend to.

A related outcome of this many of the village youths prefer the neighboring towns and cities to work in and even live in. Those in defense services are certainly better off as they are given priority and this is the reason why many from the village have opted for defense services almost like a family tradition.

Information dissemination: Consultations included information dissemination on the 220 kV line, details on likely period of commencement of construction works; height of the towers; time duration of construction, the ROW that would be required. Other information that were highlighted include requisite safety norms such as ground clearance of transmission wires from trees/structures, potential restrictions on land use, height of trees were also covered. Villagers were unaware of such projects though they were familiar with the 11 kV lines in the vicinity which brought them power supply in their homes.

Information on impacts was also elaborated upon. These included impacts such as on the land below the towers, potential depreciation of prices of land, restrictions on crops and other trees

Page 21

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project that have been grown in these villages, particularly Pali village. Persons in these villages understood this as part of the development process that the government is carrying on with. However, they requested that two aspects to be ensured i) better power supply to their villages than what they have been receiving before ii) land under towers should be compensated for.

They were informed of the process of erecting transmission towers – stubbing, erecting stringing of wires. It was informed that the process required an excavator that removes earth for footing the legs of each tower. Movement of such equipment shall result in damage to crops particularly if there is no other access available. Attempt shall be made to carry out such works during the post harvest season and thereby ensure minimum damage. It might not be possible to do so in all cases. Compensation would be calculated as per the prevalent rates and disbursed to the eligible owner of the plot. The villagers in response accepted the information and requested that compensation for crops be given, though they preferred that such works be taken during the off- season. In addition, any trees that might be cut during construction, these would also be compensated as per applicable rates.

Safety: With regard to safety, they observed that there have been a few instances of a cattle dying because of accidents due to wires, but people have been safe thus far.

Perceived benefits: Benefits of the project too were highlighted and majority of the consulted stakeholders stated that there were many benefits of power supply and this would significantly positively impact their daily lives. They reckoned that there were very few activities in today’s modern life that could be carried out without power and better power supply would make a major difference in all spheres of life such as education, irrigation, television, etc. They perceived benefits of power to be employment opportunities for other youths who do not wish to join the defense services besides other domestic chores that could be carried out more efficiently with the help of appliances.

Consultation with women: Women were consulted in only one village of Pali as in other villages they were at work. These women were wives of many persons working in the defense services. They stated that there was in total of 5-6 hours of electricity. Many houses have electrical appliances for carrying out a range of activities. Drinking water from a govt. source was also available but a distance. They stated poor water supply and inadequate facility for education for children as the two main fall outs of the poor water supply. Water level is low since underground water is the only source of water. Depth of ground water is too a matter of concern because of shortage of other water bodies in the vicinity of the village.

Page 22

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Consultation with community and with women group at Lawan

Page 23

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Table 5.1 – Key issues raised in consultations in Village Panchayat, Community members and Womens groups in Package G-6 (Gurgaon circle)

Sl. No. of Issues discussed Benefits perceived by the community Apprehensions raised Suggestions from No. Participants community by the community

1 153 General  Better power supply is welcome in  Safety issues particularly relating to  Compensation for the context of the power cuts that take 11 kV lines. land under the towers Transmission lines (start point and place because of transformer overload destination) & KV (66/132/220/400)  Lines should be placed higher as  Increase ground Duration of construction for Tower  Key infrastructural requirement for there have fatal incidents both clearance of wires so that erection/construction of Sub-station development relating to humans and cattle people, particularly in farms do not feel Details of the ROW (right of way) of  Helps development of industries  Depreciation in land prices induction while passing the transmission lines  Helps education of children as longer  Landlessness owing to the below these lines. hours and reliable power supply cumulative impact of this project immensely benefits development interventions planned Safety Issues  Helps in carrying out domestic chores  Though lines are taken over their Ground clearance of transmission more efficiently and less strenuously fields, they may not be recipient of wire from trees/structures the power supply Restrictions on land use  Land under towers becomes totally Restrictions on height of trees under un-usable as no tractor can ply on the transmission lines land under the tower

Social impacts Loss of land structures and other community property resources Loss of standing crops, trees Temporary Loss of access to road, etc. Temporary loss of income Potential depreciation of land price due to presence of a tower structure

Page 24

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

CHAPTER 6 – RESETTLEMENT POLICY AND LEGAL FRAMEWORK

6.1 Policy, Legal and Regulatory Framework This section presents the legal requirements of Land Acquisition Policy and the Resettlement and Rehabilitation Policy and entitlements for affected families. The legal framework for any project includes process of land acquisition and measures to mitigate adverse impacts. Haryana government had published its R&R policy in 2007. As a result HVPNL has joined a list of other entities in power transmission business to have an Environment and Social Policy and Procedures document. The features of the R&R Policy are indicative of the kind of impacts that have been felt by such companies over many years.

HVPNL undertakes its transmission activities within purview of Indian laws keeping in mind appropriate obligations and guidelines of statutory and funding agencies. As per provision contained in Haryana Electricity Reforms Act 1997 & Electricity Act, 2003 Acts, HVPNL has authority to install transmission towers in any kind of land. Electricity Act, 2003 seeks to create a framework for the power sector development by measures conducive to the industry. However, HVPNL integrates environmental protection as a part of its project activities. Power transmission schemes are planned in such a way that the power of eminent domain is exercised responsibly.

Mandatory environment requirements for HVPNL transmission works include: Mandatory social requirements for HVPNL transmission works includes Land Acquisition Act 1894, Haryana Government Rehabilitation & Resettlement Policy for land acquisition Oustees and funding agencies requirement like WB OP 4.12 involuntary resettlement, WB OP 4.10 Indigenous People. National Rehabilitation and Resettlement Policy 2007 has also been consulted while framing the ESPP.

6.2 Procedure for Land Acquisition All land acquisition for any public purpose in the state is governed by the Land Acquisition Act 1894 as amended from time to time by the State Govt. This empowers the government to acquire compulsorily any land not owned by it which is required for a public purpose. The definition of land includes benefits to arise out of land & things attached to earth or permanently fastened to any thing attached to the earth. This act applies to those with legal entitlements to land and structures thereon.

(i) For any LA the Act under Section (u/s)-4(1) stipulates publication of a notification to that effect in the official Gazette and in 2 daily newspapers circulated in the locality, at least, one shall be in the regional language. Such a publication authorizes an authorized officer to enter upon such a land make a preliminary survey ascertain its suitability and determine the exact position of land to be acquired. However, person can enter into any building or any enclosure attached to a dwelling house either by giving notice of seven days to the occupant or with the consent of occupant. The substance of this notification is given as public notice at a convenient place in the locality in which the land to be acquired is located, such a notification provides an opportunity to the parties interested in the land to file objections if any, u/s-5A to the proposed acquisition. (ii) In order to proceed with the acquisition of the land (as notified u/s-4) it is followed by declaration u/s 6 of the ibid Act specifying that land is required for public purpose. Every declaration is published in the official Gazette and in two daily newspapers with circulation in the local area, thereafter revenue Department issues direction to the Collector u/s-7 of the Act to take order for the acquisition of notified land to be marked

Page 25

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

out, measured land/or other immovable properties, which is done under the provision of Sec.8 of the act in question. Thereafter under the provisions contained in Sec.-9 notices are served to the concerned persons stating the intention of the Government to take possession of the land and that any claims for compensation should be made to the Collector, Finally, the award of compensation is made by the collector u/s-11 of the Act after inquiring into objections(if any) in pursuance of the notice given u/s-9 to the measurements made u/s-8 and into the value of the land on the date of publication of the notification/s4(1). The award u/s-11 is made within two years from the date of publication of the declaration and if no award is made within this period, the entire proceedings of the LA is lapsed and fresh notification u/s-(4) needs to be initiated. Once the award is passed, the collector takes possession of the land which there upon vests absolutely in the Government free from all encumbrances. However, in case of urgency Section-17 of the Act empowers the Collector to take possession of the land even though no award has been made. Such land thereupon vests with the Government free from all encumbrances.

However, this Act further provides remedy for seeking enhancement of compensation by the person to seek enhancement of compensation in lieu of acquired as per provisions contained in Sec.18 of ibid Act.

This act was further amended in 1984 with respect to sections 4,23,28 and 34 which deal with publication of primary notification determination of compensation; power of the court in determining the amount of compensation; interest on compensation and payment of interest respectively. To sum up the amended provisions have resulted in the following:-  The publication of the primary notification, apart from the Official Gazette, has to be made in two daily newspapers circulated in that locality of which at least one shall be in the regional language.  In addition to the market value of the land the court is to award a sum of thirty percent as solatium on such market value in consideration of the compulsory nature of the acquisition.  The amount of compensation awarded by the court is not to be lower than the amount awarded by the collector.  The interest of excess compensation has been enhanced from 9 per cent to 15 per cent after the date of expiry of a period of one year from the date on which possession has been taken.

HVPNL strictly follows procedures laid down under the Land Acquisition Act (LA Act), 1894, when land is acquired for sub-stations. Once the award is passed, the collector takes possession of the land which there upon vests absolutely in the Government free from all encumbrances. These are further reinforced taking into consideration HVPNL’s entitlement framework and public consultation process apart from inbuilt consultation process of LA act, public consultation/information by HVPNL is an integral part of the project implementation. Public is informed about the project at every stage of execution by Press Notes and media etc. During socio-economic survey taken up in parallel with land acquisition process, HVPNL’s site officials meet people and inform them about the Land acquisition details, proposed R&R measures and compensation packages

6.3 World Bank Operational Policy on Involuntary Resettlement (OP 4.12) The objectives of the Bank’s policy on involuntary resettlement are as follows:  Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs.

Page 26

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

 Where it is not feasible to avoid resettlement, resettlement activities should be conceived and executed as sustainable development programs. Providing sufficient investment resources to enable the persons displaced by the project to share in project benefits.  Displaced persons should be meaningfully consulted and should have opportunities to participate in planning and implementing resettlement programs.  Displaced persons should be assisted in their efforts to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation whichever is higher.

6.4 HVPNL Environment and Social Policy and Procedures The ESPP of the company has been developed following consideration of all the mandatory requirements of the national and state policies and acts and also the guidelines of funding agencies in addressing the social and environmental issues arising out of its activities. The company is committed to identify, assess, and manage environmental and social concerns at both organization and project levels by strictly following the basic principals of avoidance, minimization and mitigation of environmental & social impacts with the improvement of Management Systems and introduction of State of the Art and proven technologies.

The key principles of HVPNL’s social policy are: 1. Avoid any disruption of socially sensitive areas with regard to human habitation and areas of cultural significance; 2. Wherever losses are suffered, assistance will be provided to the affected persons to improve or at least regain their living standards; 3. Consultations will be held among local population regarding finalization of proposed route of the transmission lines and sub-stations; 4. Ensure in delivering R&R entitlements and compensation for lost assets based on HVPNL’s entitlement framework. 5. Involuntary resettlement will be avoided or minimized by exploring all viable alternative project designs. 6. All adversely affected persons including those without title to land will be provided assistance to improve or regain their living standards to the pre project levels. 7. Special attention will be paid for the improvement of living standards of marginalized and vulnerable groups. 8. If any person’s remaining land holding becomes operationally non viable, the entire holding will be acquired and compensated accordingly, if the Affected Family (AF) desires. A similar approach will be adopted for structures affected partially. 9. Physical works will not commence on any portion of land before compensation and assistance to the affected population have been provided in accordance with the policy framework.

6.5 Social Entitlement Framework The prescriptive social entitlement framework derives from the aforementioned constitutional directives national R&R Policy, State R&R Policy and relevant policies. Physical displacement of people is not, and will not be, a major consequence of the company’s projects as has been the experience in the case with the other transmission companies. Regardless of displacement occurs, the entitlement framework will be a base for all its management procedures. The objective of the HVPNL’s framework is to ensure realistic rehabilitation and compensation of the acquired assets of the AFs covers categories such as loss of land (Homestead land, agriculture land, tenants, lease holders, encroachers/ squatters etc), loss of structure ( with valid title, tenants, lease holders, squatters, cattle sheds, workshop sheds etc.), loss of livelihood, loss of standing crops/ trees, loss of access to Common Property Resources (CPR) and facilities,

Page 27

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project losses to host communities, Panchayat land and additional benefits for vulnerable person.

Based on review of literature – walkover survey and Topo maps and surveys carried out by the team, it is to be stated that for the transmission lines in Gurgaon circle under Package G-6, the applicable provision shall be relating to the compensation for loss of standing crops. See Table 6.1 that provides HVPNL’s social entitlement framework applicable for all kinds of impacts.

Table 6.1 - HVPNL's Social Entitlement Framework Sr. Type of Loss/ Impact Entitled Person/s Entitlement No. 1. Loss of Land a) Homestead land with valid Titleholders i) Cash compensation as per LA Act 1894 title, or customary or usufruct rights ii) Actual registration charges for purchase of alternate land for maximum of compensation amount within one year as per proof of purchased land. iii) The land owners will be paid annuity for 33 years over and above the usual land compensation. The amount of annuity will be Rs. 15,000/-per acre per annum on prorata basis. Annuity of Rs. 15,000/- will be increased by a fixed sum of Rs.500/- every year as per State Government Policy.

Vulnerable person Titleholders One time additional compensation of Rs.5000 per acre on prorate basis will be paid in addition to above entitlements. b) Agricultural Land (i) With valid title Titleholders i) Cash compensation as per LA Act 1894 ii) Actual registration charges for purchase of alternate land for maximum of compensation amount within one year as per proof of purchased land. The land owners will be paid annuity for 33 years over and above the usual land compensation. The amount of annuity will be Rs. 15,000/-per acre per annum on prorata basis. Annuity of Rs. 15,000/- will be increased by a fixed sum of Rs.500/- every year as per State Government Policy. Vulnerable person Titleholders One time additional compensation of Rs.5000 per acre on prorate basis will be paid in addition to above entitlements. (ii) tenants, sharecroppers, Individual with Reimbursement for unexpired tenancy/share leaseholder including the proof of cropping/lease period. commercial and other tenancy/share establishments cropping/leasing Note: This amount will be deducted from the compensation payable to land owners.

Vulnerable person Individual with One time additional compensation of Rs.5000 will proof of be paid in addition to above entitlements. tenancy/share cropping/leasing

Page 28

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Table 6.1 - HVPNL's Social Entitlement Framework Sr. Type of Loss/ Impact Entitled Person/s Entitlement No. (iii) Encroacher/Squatters Occupant Assistance to be provided for inclusion in various Government Schemes.

2. Loss of structure (i) with valid title, Structure owner i) Compensation as per Haryana PWD scheduled rates

ii) One time financial assistance of Rs.10,000/- for shifting of family, building material, belongings and cattle etc. Affected Families will be allowed to dismantle structure and carry salvage whatever they can. Vulnerable person Structure owner One time additional compensation of Rs.5000 will be paid in addition to above entitlements.

(ii) Tenant, leaseholder Individuals/ Party i.) Compensation as per Haryana PWD with proof of scheduled rates. (who have created the tenancy/leasing structure) ii) One time financial assistance of Rs.10,000/- for shifting of family, building material, belongings and cattles etc. iii) Affected Families will be allowed to dismantle structure and carry salvage whatever they can. iv) Reimbursement for unexpired tenancy/ lease period. Note: The amount at iv) will be deducted from the compensation payable to land owners. Vulnerable person Individuals/ Party One time additional compensation of Rs.5000 will with proof of be paid in addition to above entitlements. (who have created the tenancy/leasing structure) (iii) Tenant, leaseholder Individuals/ Party Reimbursement for unexpired tenancy/ lease period. with proof of (Who have not created the tenancy/leasing Note: This amount will be deducted from the structure) compensation payable to land owners. Vulnerable person Individuals/ Party Additional compensation of Rs.2000 will be paid in with proof of addition to above entitlements. (Who have not created the tenancy/leasing structure) (iv) Squatters Structure I. Compensation as per Haryana PWD scheduled rates.

II. Assistance in shifting by providing transport charges to actual or Rs.10,000/- maximum. III. Affected Families will be allowed to dismantle structure and carry salvage whatever they can.

(v) Cattle shed Owner/Family Cash compensation of Rs. 15000/- for re- construction of cattle shed.

Page 29

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Table 6.1 - HVPNL's Social Entitlement Framework Sr. Type of Loss/ Impact Entitled Person/s Entitlement No. Vulnerable person Owner/Family Additional compensation of Rs.1000 will be paid to head of family in addition to above entitlements.

(vi) Workshop sheds Owner/Family Cash compensation of Rs. 25000/- for re- construction of workshop shed.\

Vulnerable person Owner/Family Additional compensation of Rs.2000 will be paid to head of family in addition to above entitlements.

3 Loss of livelihood i) Wage /Self employment (both Each adult earning Assistance to be provided for inclusion in various agriculture and Non member (both men State Government Schemes for self-employment. Agriculture) & women)

4 Loss of standing crops/ trees i) a) Crops Cultivator title In either category compensation for the total loss of holders crop/tree as per LA Act during construction as well b) Trees as during O&M**.

5 Loss of access to Common Property Resources (CPR) and facilities i) Common property resources / Community Replacement of CPRs/Civic amenities to ensure Civic amenities. equivalent community resources and amenities or provisions of functional equivalence. 6 Losses to host communities i) CPR and Civic amenities Community Augmentation of resources of host community to sustain pressure of AFs. 7 Panchayat land Village Compensation as per State Government Policy. Panchayat 8. Other Impacts related to loss of AFs Unforeseen impacts should be documented and assets/ livelihood not mitigative measures have to be proposed with in the identified. overall principles & provisions of ESPP. 9. Title holders affected by Title holders Compensation as per “Works of licensees Rules Transmission towers In urban/ 2006” notified by GoI on dated 18.4.2006. rural areas Note: *Vulnerable person means the people below poverty level, widow, physically handicap and SC/ ST. ** compensation of damage to crops/trees during O&M would be paid within one month

Cut Off dates For the non-titleholders the cut-off date will be the date of census survey conducted as part of the socio-economic survey and for titleholders it will be the date of issuance of Section 4 (1) notice under the LA Act. In the case of this package, the date will be survey date after the finalization of detailed route survey.

Public Disclosure, Consultation, And Participation Public consultation has been incorporated as an integral part of the process throughout the planning and execution of project. The Environment and Social Management Team (ESMT) will

Page 30

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project interact closely with PAPs, host communities, project personnel, government departments, NGOs right from the early stages of the project preparation on regular basis for developing and implementing the RAP and EMP.

During implementation the public contact drives have been envisaged by bringing in active NGOs in the affected area. The first step of public awareness program is the publication of the public notification in the local newspapers as per the Section 29 of the Electricity (Supply) Act, 1948 in which details of the proposed project are given. The objections are to be filed within a period of 60 days from the date of publication of notification. The next step of the program is holding of the meetings and discussions with the public during the reconnaissance survey and again during the detailed survey/tower spotting.

Page 31

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

CHAPTER 7 – INSTITUTIONAL ARRANGEMENTS AND GRIEVANCE REDRESSAL MECHANISMS

7.1 Introduction This section deals with the institutional arrangement and grievance redressal mechanisms as enunciated in the ESPP of HVPNL. These would be applicable to all the sub-stations and transmission lines that get funded under this proposed World Bank project.

7.2 Institutional Framework The company will have three levels of Institutional bodies to oversee and implement ESPP. The bodies are constituted at Head Quarter level; Zonal level; and Divisional Level

At Head Quarter Level: Environment, Resettlement and Rehabilitation Committee (ER&R) under the chairmanship of the Director Technical includes the concerned Chief Engineer/TS and CE/P&D HVPN, Panchkula and Deputy Secretary/Projects as the Committee members. Deputy Secretary/Projects will be the Member Secretary of the R&R committee

At Zonal Level: The Environment and Social Monitoring Committee (ESMC) constitute of concerned Chief Engineer/TS , concerned Superintendent Engineer/TS, concerned Executive Engineer/TS, Land Acquisition officer and two representatives of the AFs and ESMC would report to Director Technical, HVPNL, Panchkula

At Divisional Level: In addition to above, Environment and Social Implementation unit (ESIU) will be there consisting of Executive Engineer/TS and SSE/SDO/Construction of concerned place.

The role and functions of the ER&R, ESMC and ESIU include but are not limited to:  Coordinate among the various agencies involved in implementation of the ESPP programs  Monitor and review implementation of the ESPP plans  Function as a grievance redressal body; and  Provide overall guidance and leadership for smooth implementation of the resettlement and rehabilitation plans

To ensure effective implementation of ESPP, HVPNL focuses on  strengthening the implementation of the ESPP by redeployment of appropriately trained persons at key levels  reinforcing in house capabilities by working with specialized external agencies  reviewing progress of the ESPP internally or through external agencies

7.3 Social Procedures HVPNL has developed comprehensive Environmental and Social (E&S) Management Procedures and incorporated them to its project cycle, to ensure that its operation eliminates or minimizes adverse environmental and social impacts. The E&S management procedures identifies the relevant issues at early stages of project cycle and follow the basic philosophy of sustainable development through Avoidance, Minimization and Mitigation.

Page 32

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

HVPNL’s project cycle forms the operational framework and background through which the environment & social issues are addressed. Key milestones in HVPNL’s transmission projects include project conceptualization; planning; approval; design; tendering; implementation and operation; and maintenance.

7.3.1 Project Conceptualization During project conceptualization, HVPNL identifies the project. Identification of a power transmission project is on the basis of demand and supply in regions and links between new power generating projects and availability of state’s quota of power from the Powergrid. HVPNL carries out feasibility studies encompassing demand for energy, prioritizing for different sectors and regions, environmental and social impact assessment; economic and financial analysis; and an implementation schedule. During feasibility studies, HVPNL identifies and weight various line options on a survey map such that there is shortest distance between origin of the proposed transmission line and the substations sites. At all times, while considering line options, HVPNL keeps in view its policy of avoidance of socially (including environmentally) sensitive areas.

7.3.2 Project Planning During project planning, HVPNL carries out a Reconnaissance survey. A number of alternatives are studied to minimize possible environmental impacts of transmission line. Adequate care is taken in the route alignment to avoid forests and areas of natural resources completely, if not possible, allow to traverses minimally. The planning exercise also ensures that the route does not involve human habitation and areas of cultural importance. Field officers verify critical issues e.g. river, hill, railway crossings; power and telephone lines etc. and finalize the optimal route on the map. Once the route is finalized, HVPNL, will carry out a Environment & Social Assessment with its own field staff and prepare a Environment & Social Impact Assessment. Based on the assessment and the provisions under ESPP, HVPNL will formulate an EMP (Environment Management Plan & Resettlement Action Plan (RAP) in consultation with AFs.

HVPNL considers various sites for substations. On the basis of data for various parameters considered during selection process, a comprehensive analysis for each alternative site will be carried out. Weightage will be given to various parameters for finalizing alternative sites which are often site specific. Due consideration is given to availability of infrastructure facilities such as access roads, railheads etc. type of land viz. government, revenue, private, agriculture, environment and social impacts such as number of families affected as well as cost of compensation and rehabilitation.

7.3.3 Operation and Maintenance HVPNL continuously monitors the transmission lines and substations. The lines are patrolled regularly to identify any defects in the components. Monitoring of the line is carried out by the respective HVPNL field offices.

7.3.4 Project Review The social components of the project will be reviewed by the ESMU of HVPNL on regular basis.

7.4 Capacity Building Training and development of employees is integral to implementation of ESPP. In the beginning, training would be imparted to the executive/non-executive from NPTI/PGCIL so as to enable them to understand the ESPP document, to take necessary steps in right time to implement.

Page 33

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

It is recommended that the HVPNL carries out periodic orientation and refresher courses that comprise of social and environmental issues applicable to such projects. Content of these courses should also comprise of the mitigation measures that are required to be adopted in the case of sub-stations and transmission line projects.

7.5 Grievance Redress Mechanism It is expected that through a participatory process and good compensation and support mechanisms, acceptance of the project will be enhanced and complaints reduced. In case of issues related to land acquisition, the LA Act provides adequate provisions at different stages of the LA process for the AFs to object to the proposed acquisition of land and other properties, compensation rates, etc. The LA Act also allows the affected persons to receive the compensation under protest and then refer the case to the court for settlements. However ESMC at the Zonal Level will hear complaints and facilitate solutions. If the grievance is not redressed at zonal level, the affected person can appeal to the Environment R&R committee at Corporate level. He/she can further appeal to the court if his/her grievance is not redressed at either zonal or corporate level.

In addition to the proposed grievance redressal under the ESPP, it is recommended that another level of grievance redressal be added at the Division level to help record complaints. The advantage of such a mechanism would be receive, and forward it to the ESMC at Zonal level for redressal. Past experiences in other such and other infrastructure projects too indicate handling of issues at lowest possible level have proved more effective than if they are let to scale up.

Page 34

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Organizational Structure for ESPP

ER&R High Powered Committee at HQ level

Director/ Technical Chairman

CE/ TS Concerned Deputy Secy/ Projects

Member Member Secy. (Nodal Officer)

CE/ P&D Member

Environment Social management Committee (ESMC) at Zonal level

CE/ TS Concerned Chairman

SE/ TS XEN/ TS LAO Two Concerned Concerned representatives AFs

Environment & Social Implementation Committee (ESIU) at Division level

Complaint recorded at XEn/ TS SSE/ SDO this level Concerned construction concerned

Page 35

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

CHAPTER 8 – BUDGET ESTIMATES

8.1 Introduction This chapter presents the cost and budget for implementation of RRAP. The costs used for the budget are based on information collected during the site visit and also from the revenue department. It is suggested that during implementation, an independent assessment should determine the cost and accordingly the budget be modified. 8.2 Compensation Compensation for Land: The land required for footing of 79 towers shall require marginal amount of land as stated earlier. This land would not be compensated for as per the Electricity Act, 1948. Titleholder(s) affected by transmission towers in urban/ rural areas may approach to the District Collector for compensation for the loss of land. The DC will assess his/ her economic condition and decide the case as per the provisioning of works of Licenses Rules 2006.

Compensation for damage to crops: Though attempts shall be made to minimize the damage to crops by planning the construction work in such a way that harvest is completed, ensuring this would not be possible in all cases. Besides, movement of machinery would cause damage to crops. Compensation shall be as per the Land Acquisition Act. The quantum of crops damaged will be assessed by collecting per acre yield figure of that crop in that area from Tehsildar (Revenue) and the equivalent amount of damaged crops will be calculated by ascertaining rate/quintal from the office of the Secretary Market Committee of the concerned area. There is a standard proforma (See Annexure E3 for Format) that the villager needs to fill in and obtain signatures from Sarpanch of the village and also from Patwari. Compensation would be calculated as per the prevalent rates and disbursed to the eligible owner of the plot. A list of crops yield per acre and applicable rates is attached as Annexure C23 and this would form the basis for compensation. Estimate for the loss of crops has been made on the basis of field visits, observations and site assessment.

Compensation for loss of trees: After the finalization of tower bases and transmission line route, the Contractor/executing agency shall enumerate the trees lost and compensate based on the rates released by Haryana Van Vikas Nigam Limited (Govt. of Haryana) and that are effective since July 2008. See Annexure C2 for list. This list provides zone wise prices for different types of trees such as Safeda, Paplar, Khair, Shisham, Kikar, Mango, etc. department. It is to be noted that PAPs shall be notified of any revision to these rates shall and be compensated accordingly.

8.3 Budget and Costs HVPNL’s ESPP provides the legal framework to establish eligibility criteria for entitlements and other forms of assistance. Based on this framework two budget options for implementation of RRAP have been presented below.

Option 1: It includes the cost of compensation for ‘current’ standing crops based on the ROW calculated, net crop area, yield per acre for different types of crops and market (harvest) rates. (See Annexure C2 for rates of crops and trees). Yield per acre for other crops too have been

3 Source: website: www.agriharyana.nic.in for crop-wise average yield of various crops and www.dacnet.nic.in/eands/fhprice/haryana for farm harvest prices

Page 36

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project provided as it can be used to calculate cost of standing crops as identified at the time of construction.

Option 2: An alternative budget too has been provided by taking cognizance of the option that HVPNL can exercise such as timing the construction works between two crops, in which case the compensation payable would be nil.

Table 8.1 & 8.2 presents separate budget estimates for the two sub-packages.

Table 8.1 – Const. of 132 KV S/C line on D/C tower with 0.4 sq. “ACSR (Zebra) from 220 KV Dhanonda to proposed 132 KV substation Nangal Mohanpur (Mahendragarh) – 11.260 Km

A S. No. Crop type Estimated cropped Yield per Unit Rate Amount area (in acres) acre (in (Rs.) (Rs.) quintals) 1 Paddy 83.01 650 2 Wheat 8 24 1000 192000 3 Mustard 10 12 1730 207600 4 Cotton 5 Rice 22 6 Arhar 8 850 7 Bajra 15 850 8 Jowar 15000 9 Sugarcane 350 135 10 grams 15 2300 Sub-total 399600 Rupees Three Lakhs Ninety Nine Thousand Six Hundred Only

Table 8.2 – Const. of 132 KV S/C line on D/C tower with 0.4 sq “ACSR(Zebra) from 220 kV Dhanonda to proposed 132 KV Sub-station Pali (Gurgaon) – 13.515 km

B S. No. Crop type Estimated cropped Yield per Unit Rate Amount area (in acres) acre (in (Rs.) (Rs.) quintals) 1 Paddy 83.01 650 2 Wheat 9 24 1000 216000 3 Mustard 12 12 1730 249120 4 Cotton 5 Rice 22 6 Arhar 8 850 7 Bajra 15 850 8 Jowar 15000 9 Sugarcane 350 135 10 grams 15 2300 Sub-total 465120 Rupees Four Lakhs Sixty Five Thousand One Hundred and Twenty Only

Page 37

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Table 8.4 – Consolidated budget for Gurgaon Circle

A Const. of 132 KV S/C line on D/C tower with 0.4 sq. “ACSR (Zebra) from 220 KV 399600 Dhanonda to proposed 132 KV substation Nangal Mohanpur (Mahendragarh) – 11.260 Km B Const. of 132 KV S/C line on D/C tower with 0.4 sq “ACSR(Zebra) from 220 kV 465120 Dhanonda to proposed 132 KV Sub-station Pali (Gurgaon) – 13.515 km

Sub-Total 864720 Contingency at 5% 43236 Grand Total (both sub-packages) 907956 Rupees Nine Lakhs Seven Thousand Nine Hundred and Fifty Six Only

The cost of implementation of the RRAP for the two sub-packages in Gurgaon circle is Rs. 9,07,956/- (Rupees Nine Seven Thousand Nine Hundred and Fifty Six) only.

Page 38

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

CHAPTER 9 – IMPLEMENTATION SCHEDULE

9.1 Introduction This section deals with the implementation schedule for the RRAP for the two transmission lines that cross areas in Mahendgarh district of Haryana. The breakdown of each activity according to a specific time frame has been provided in the Implementation Schedule. Implementation Schedule will require detailed coordination between the project authority – HVPNL and other relevant line departments. Key issues in implementation are likely to be the following: (i) Census Survey by contractor – enumeration of tower land owner and standing crops (ii) Clearance of any claim for compensation for land acquired for footing of towers as per The Works of Licensees Rules, 2006.

9.2 Tasks and Schedule Implementation schedule has been spread over a period of 1 to 1-1/2 years in respect of these ten transmission lines that are expected to complete in terms of construction and running. Construction works on different sub-packages are likely to commence at different points of time over the project period. Therefore a list of implementation activities in sequence have been indicated which shall continue over the project period.

Activities in sequence  Census Survey by contractor – enumeration of tower land owner  Estimation of standing crop  Finalization of Affected persons & Final notification  Clearance of any claim as per Workers License Act 2006  Compensation

After compensation, the construction activities may begin. Activities such as disclosure of project information, redressal of grievances and dissemination of safety measures shall continue throughout the project period.

Page 39

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure A – Mahendrgarh (11.260 km line)

Page 40

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure A1 – Photographs of area en-route in Mahendragarh (11.260 km)

Photo 1 – Mahendgarh Canal

Photo 2 – Nangal Distributary

Page 41

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Photo 3 – Railway Cross at Guda Khemla

Photo 4 – Open Scrub Area at Guda Khemla

Page 42

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure A2 – Community Consultations

Focus Group Discussion with key members at Nangal Mohanpur

Name of the Village Nangal Date 20th February 2009 Venue Nangal No. of Persons attended: 23 persons FGD Conducted by Neha and Sangeet Start and End Time 10-12 Objectives:  inform villagers about the proposed transmission line  to understand their overall socio-economic condition  to elicit their views and perceptions on project Issues discussed:

Village and household composition: The village has approximately 350 households with a total population of approximately 1300. In terms of household composition, it is 5-6 members per household.

Land donation: The panchayat has donated 9.36 acres of their land for the sub-station.

Land use: Agricultural land on which crops such as mustard, wheat, and bajra are grown. The produces are sold in the market

Occupation: Farming is the major occupation of the villagers.

Electricity status: Approximately 5 hours of electricity supply to the village.

Medical facilities: No medical facilities are available within the village area. The villagers have to go to Kanina for medicine or treatment.

Education: One school upto 8th standard is functioning in the village and beyond 8th children have to commute to Kanina which is the nearest urban area to the village Nangal.

Outcomes: Better power supply is welcome as it directly benefits households and for irrigation purpose.

Page 43

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Focus Group Discussion with key members at Gurha

Name of the Village Gurha Date 20th February 2009 Venue Sarpanch’s House No. of Persons attended: 9-10 FGD Conducted by Neha and Sangeet Start and End Time 2.30 to 3.15 Objectives:  inform villagers about the proposed transmission line  to understand their overall socio-economic condition  to elicit their views and perceptions on project Issues discussed:

Village and household composition: The village has approximately 700 households with a total population of approximately 4500. Source of income is mostly from agriculture and others from various government departments viz. defense, etc. A Gramin Bank and a post office are also functional in the village.

Land use: Agricultural land on which crops such as mustard, wheat, and bajra are grown. The produces are sold in the market.

Occupation: Farming is the primary occupation, although most of the villagers are employed in defense services. Women are also employed in nearby town area viz. Kanina, etc.

Electricity status: Power is available for approximately 6-8 hours a day

Medical facilities: One Primary Health Centre with doctors is functional.

Education: One Govt. High School and two numbers of private schools. Also a Government Scheme Sarv Saksharta Abhiyaan has been implemented in the village and is ongoing. Overall literacy is 80-90% in the village. One B. Ed college is also functional in the village.

Water Supply: Irrigation is an issue, particular when electricity is not available effectively. Handpumps and tubewells have been installed in the village. In absence of power tubewells are run by generators.

Outcomes: Better power supply is welcome as it directly benefits households and for irrigation purpose.

Page 44

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Focus Group Discussion with key members at Pathera

Name of the Village Pathera Date 20th February 2009 Venue Sarpanch’s House No. of Persons attended: 8-10 FGD Conducted by Sangeet and Neha Start and End Time 1.30 to 2.15 Objectives:  inform villagers about the proposed Transmission line  to understand their overall socio-economic condition  to elicit their views and perceptions on project Issues discussed:

Village and household composition: The village has approximately 1200 households with families of Below Poverty Line (BPL) of 305 households. Source of income is mostly from agriculture.

Land use: Agricultural land on which crops such as mustard, wheat, and bajra are grown. The produces are sold in the market.

Occupation: Farming is the primary occupation.

Electricity status: Power is available for approximately 4-5 hours a day

Education: Two Govt. High Schools are functional. Two qualified engineers from IIT from the village, now based in Noida, Uttar Pradesh.

Water Supply: Irrigation is an issue, particular when electricity is not available effectively. Handpumps and tubewells have been installed in the village. In absence of power tubewells are run by generators.

Outcomes: Better power supply is welcome as it directly benefits households and for irrigation purpose.

Page 45

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Focus Group Discussion with key members at Dhanonda

Name of the Village Dhanonda Date 20th February 2009 Venue Dhanonda No. of Persons attended: 21 persons FGD Conducted by Neha and Sangeet Start and End Time 10.30 to 11.30 am Objectives:  inform villagers about the proposed transmission line  to understand their overall socio-economic condition  to elicit their views and perceptions on project Issues discussed:

Village and household composition: The village has approximately 1500 households with a total population of approximately 8000-9000. In terms of household composition, it is 5-6 members per household. 475 BPL households are there. Approximately there are 800 acres of panchayat land

Land use: Agricultural land on which crops such as mustard, wheat, bajra and chana are grown. At present mustard and wheat are being grown in the 60:40 ratio. The produces are sold in the market.

Occupation: Farming is the primary and major occupation among the villagers, though villagers are engaged in business like small shops and small industries also. Also the villagers are engaged in government services.

Electricity status: Power is available for approximately 5-6 hours a day

Education: Literacy is from 70-80% among the villagers. There are four numbers of private high schools, one B. Ed college and one engineering college is under construction.

Water Supply: Irrigation is an issue, particular when electricity is not available effectively. Handpumps and deep tubewells have been installed in the village

Outcomes: Better power supply is welcome as it directly benefits households and for irrigation purpose.

Page 46

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Focus Group Discussion with key members at Malra

Name of the Village Malra Date 20th February 2009 Venue Sarpanch’s residence No. of Persons attended: 17 persons FGD Conducted by Neha and Sangeet Start and End Time 3.30 to 4.15 pm Objectives:  inform villagers about the proposed transmission line  to understand their overall socio-economic condition  to elicit their views and perceptions on project Issues discussed:

Village and household composition: The village has approximately 705 households with a total population of approximately 3000-4000. In terms of household composition, it is 5-6 members per household. Out of total households 125 are below poverty line. One primary health center is scheduled to be constructed by April-2009. Also one post office and a stadium is proposed to be constructed.

Land use: Agricultural land on which crops such as mustard, wheat, and bajra are grown. At present mustard and wheat are being grown in the 60:40 ratio. The produces are being sold in the market.

Occupation: Farming is the primary and major occupation among the villagers. Also the villagers are engaged in government services like army personnel.

Electricity status: Power is available for approximately 4-6 hours a day. Around 25% households use electrical appliances like television, coolers etc.

Education: Literacy is upto the average level among the villagers which can be divided into various age groups like 20-30 age is 50%, 30-40 age groups is 25% , 40-50 age group is 20% and above 50% its 10%. There is one private high school and one government school upto 8th standard. For higher education villagers have to travel to Kanina upto a distance of around 13 km or to Mahendergarh.

Water Supply: Irrigation is an issue, particular when electricity is not available effectively. Handpumps and deep tubewells have been installed in the village

Outcomes: Better power supply is welcome as it directly benefits households and for irrigation purpose. The villagers have a requirement of veterinary clinic.

Page 47

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Focus Group Discussion with key members at Mohanpur

Name of the Village Mohanpur Date 25th February 2009 Venue Mohanpur No. of Persons attended: 19 persons FGD Conducted by Neha and Sangeet Start and End Time 12.15 to 1.30 pm Objectives:  inform villagers about the proposed sub-station and transmission line  to understand their overall socio-economic condition  to elicit their views and perceptions on project Issues discussed:

Village and household composition: The village has approximately 705 households with a total population of approximately 3000-4000. In terms of household composition, it is 5-6 members per household. Out of total households 125 are below poverty line. One primary health center is scheduled to be constructed by April-2009. Also one post office and a stadium is proposed to be constructed.

Land use: Agricultural land on which crops such as mustard, wheat, and bajra are grown. At present mustard and wheat are being grown in the 60:40 ratio. The produces are being sold in the market.

Occupation: Farming is the primary and major occupation among the villagers. Also the villagers are engaged in various government departments including women also.

Electricity status: Power is available for approximately 3-4 hours a day. Almost no power supply during summer season.

Education: One private school and one government school is in the vicinity of the village.

Water Supply: Irrigation is an issue, particular when electricity is not available effectively. Handpumps and deep tubewells have been installed in the village

Outcomes: Better power supply is welcome as it directly benefits households and for irrigation purpose. The villagers have a requirement of veterinary clinic.

Page 48

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Focus Group Discussion with ladies at Kemla

Name of the Village Kemla Date 25th February 2009 Venue Residence of Sarpanch No. of Persons attended: 8-10 FGD Conducted by Neha and Sangeet Start and End Time 10.30 to 11.15 am Objectives:  inform ladies about the proposed transmission line  to understand their overall socio-economic condition  to elicit their views and perceptions on project Issues discussed:

Village and household composition: The village has approximately 200 households with a total population of approximately 1000-1200. In terms of household composition, it is 5-6 members per household. 30 numbers of households are below poverty line (BPL). The village has panchayat land of total of 10 acres of land.

Land use: Agricultural land on which crops such as mustard, wheat, and bajra are grown. At present mustard and wheat are being grown in the 60:40 ratio. The produces are being sold in the market.

Occupation: Farming is the primary and major occupation among the villagers. Very few villagers are engaged in other services such as defence and labour.

Electricity status: Power is available for approximately 3-4 hours a day with low voltage and few households use electrical appliances like television, coolers etc.

Education: The village has got one M. E school i.e. upto 8th standard and for higher education they have to travel to nearby villages like Kanina or Dhanounda.

Water Supply: Irrigation is an issue, particular when electricity is not available effectively. Handpumps and deep tubewells have been installed in the village.

Outcomes: Better power supply is welcome as it directly benefits households and for irrigation purpose.

Page 49

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 50

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 51

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 52

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 53

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 54

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 55

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 56

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 57

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 58

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 59

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 60

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure A3 – Walkover Survey and route marked on Toposheets

Page 61

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure B – Mahendragarh (13.515 km line)

Page 62

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure B1 – Photographs of area en-route the 13.515 km

Photo 1 – PWD road crossing near Pali

Photo 2- Dense Babul trees

Page 63

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Photo 3 – Lawan Distributory

Photo 4 – Land use en-route

Page 64

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure B2 – Community consultations

Focus Group Discussion with key members at Palli

Name of the Village Palli Date 20th February 2009 Venue Palli No. of Persons attended: 12 persons FGD Conducted by Neha and Sangeet Start and End Time Objectives:  inform villagers about the proposed sub-station  to understand their overall socio-economic condition  to elicit their views and perceptions on project Issues discussed:

Village and household composition: The village has approximately 1700 households with a total population of approximately 10000. In terms of household composition, it is 6-7 members per household. 300 BPL households are there. One stadium (Nehru stadium) is located in the village.

Land donation: The village has a total of 2000 acres of panchayat land. The panchayat has donated 5.52 acres of their land for the sub-station.

Land use: Agricultural land on which crops such as mustard, wheat, bajra and chana are grown. The produces are sold in the market.

Occupation: Farming is the primary occupation, although most of the villagers are employed in defense services.

Electricity status: Power is available for approximately 3-4 hours a day

Medical facilities: A dispensary and primary health centre (PHC) is available with doctors and basic medical facilities are availed. 4 numbers of Anganwadi Kendras are functioning in the vicinity of the village.

Education: One B. Ed College and four numbers of schools upto 10+2 are around in the vicinity of the village. Girls of the present generation are all educated. Also one Kendriya Vidyalaya is located in the village. Education upto the age group of 40 years is 100% and from 40-70 years is 70%. Engineering and medical graduates can also be found in the villages, though they are doing services in distant places.

Water Supply: Irrigation is an issue, particular when electricity is not available effectively Water level is around 400 ft. deep, though tubewells are there. Handpumps have been installed in the village

Outcomes: better power supply is welcome as it directly benefits households and for irrigation purpose.

Page 65

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Focus Group Discussion with key members at Malra

Name of the Village Malra Date 20th February 2009 Venue Sarpanch’s residence No. of Persons attended: 17 persons FGD Conducted by Neha and Sangeet Start and End Time Objectives:  inform villagers about the proposed sub-station  to understand their overall socio-economic condition  to elicit their views and perceptions on project Issues discussed:

Village and household composition: The village has approximately 705 households with a total population of approximately 3000-4000. In terms of household composition, it is 5-6 members per household. Out of total households 125 are below poverty line. One primary health center is scheduled to be constructed by April-2009. Also one post office and a stadium is proposed to be constructed.

Land use: Agricultural land on which crops such as mustard, wheat, and bajra are grown. At present mustard and wheat are being grown in the 60:40 ratio. The produces are being sold in the market.

Occupation: Farming is the primary and major occupation among the villagers. Also the villagers are engaged in government services like army personnel.

Electricity status: Power is available for approximately 4-6 hours a day. Around 25% households use electrical appliances like television, coolers etc.

Education: Literacy is upto the average level among the villagers which can be divided into various age groups like 20-30 age is 50%, 30-40 age groups is 25% , 40-50 age group is 20% and above 50% its 10%. There is one private high school and one government school upto 8th standard. For higher education villagers have to travel to Kanina upto a distance of around 13 km or to Mahendergarh.

Water Supply: Irrigation is an issue, particular when electricity is not available effectively. Handpumps and deep tubewells have been installed in the village

Outcomes: Better power supply is welcome as it directly benefits households and for irrigation purpose. The villagers have a requirement of veterinary clinic.

Page 66

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Focus Group Discussion with key members at Aghiyar

Name of the Village Aghiyar Date 25th February 2009 Venue Aghiyar No. of Persons attended: 8 persons FGD Conducted by Neha and Sangeet Start and End Time Objectives:  inform villagers about the proposed sub-station  to understand their overall socio-economic condition  to elicit their views and perceptions on project Issues discussed:

Village and household composition: The village has approximately 500 households with a total population of approximately 3000-3500. In terms of household composition, it is 5-6 members per household. 145 numbers of households are below poverty line (BPL).

Land use: Agricultural land on which crops such as mustard, wheat, and bajra are grown. At present mustard and wheat are being grown in the 60:40 ratio. The produces are being sold in the market.

Occupation: Farming is the primary and major occupation among the villagers. Also the villagers are engaged in government services like army personnel.

Electricity status: Power is available for approximately 5-6 hours a day. Around 25% households use electrical appliances like television, coolers etc. At present electricity if supplied from Kanina.

Education: Literacy is upto the average level among the villagers which can be divided into various age groups like 20-30 age is 50%, 30-40 age groups is 25% , 40-50 age group is 20% and above 50% its 10%. There is one private high school and one government school upto 8th standard. For higher education villagers have to travel to Kanina upto a distance of around 13 km or to Mahendragarh.

Water Supply: Irrigation is an issue, particular when electricity is not available effectively. Handpumps and deep tubewells have been installed in the village. Better quality of water is available at a level of 450ft.

Outcomes: Better power supply is welcome as it directly benefits households and for irrigation purpose.

Page 67

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Focus Group Discussion with key members at Lawan

Name of the Village Lawan Date 25th February 2009 Venue Lawan No. of Persons attended: 12-14 FGD Conducted by Neha and Sangeet Start and End Time Objectives:  inform villagers about the proposed sub-station  to understand their overall socio-economic condition  to elicit their views and perceptions on project Issues discussed:

Village and household composition: The village has approximately 750 households with a total population of approximately 3500. In terms of household composition, it is 5-6 members per household. 300 numbers of households are below poverty line (BPL). The village has panchayat land of total of 30 acres of agricultural land and 20 acres barren land.

Land use: Agricultural land on which crops such as mustard, wheat, and bajra are grown. At present mustard and wheat are being grown in the 60:40 ratio. The produces are being sold in the market.

Occupation: Farming is the primary and major occupation among the villagers. Also some of the villagers are qualified as engineers and doctors and providing services is urban areas and also some of them are serving as defence personnels.

Electricity status: Power is available for approximately 5-6 hours a day. Around 25% households use electrical appliances like television, coolers etc. At present electricity is supplied from Kanina.

Education: The village has got one M. E school i.e. upto 8th standard and for higher education they have to travel to nearby villages like Malra or Mahendragarh.

Water Supply: Irrigation is an issue, particular when electricity is not available effectively. Handpumps and deep tubewells have been installed in the village.

Outcomes: Better power supply is welcome as it directly benefits households and for irrigation purpose.

Page 68

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 69

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 70

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 71

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 72

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 73

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 74

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 75

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure B3 – Walkover Survey and route marked on Toposheets

Page 76

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure C – Crops and Tree Rates

Page 77

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure C1 – Rates of Trees and Crops

Page 78

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 79

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 80

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 81

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 82

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 83

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 84

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 85

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure D – List of Officials

Page 86

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure D1 – List of Officials

1. Mr. Raghubir Saran SE T/S Circle, Gurgaon 2. Mr R.N. Misha, SSE, 220kV substation, Mahendragarh 3. Mr. Tarachand, EE, Civil, Mahendragarh 4. Mr. R.P. Bhatia, Xen, T/S Division, Rewari

Page 87

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure D – Formats and Questionnaires

Page 88

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure E1: Consultation Checklist

CONSULTATION CHECKLIST

Name of the Village/Panchayat Date Venue No. of Persons attended: Start and End Time Issue Covered Yes No Information about the project Transmission lines (start point and destination) & KV (66/132/220/400)

Duration of construction for Tower erection/construction of Sub-station

Details of the ROW (right of way) of the transmission lines

Safety Issues Ground clearance of transmission wire from trees/structures

Restrictions on land use

Restrictions on height of trees under transmission lines

Page 89

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Social impacts Loss of land structures and other community property resources

Loss of standing crops, trees

Temporary Loss of access to road, etc.

Temporary loss of income

Potential depreciation of land price due to presence of a tower structure

Mitigation Measures  Compensation for land and structures

 Provisions for payment of lost trees

Work Opportunities  Provision of temporary employment opportunities, if any

Page 90

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure E2: Census/Socio Economic Survey Questionnaire

HARYANA POWER PROJECT

Census/Socio Economic Survey Questionnaire

Date Identification Number / / 2 0 0 Road No Side Number

Investigator Name Supervisor Name Respondent Name AC/BC

Type of Household

General SC ST OBC Women headed BPL* If BPL, card NoBPL* household 1 2 3 4 5 6

Type of the Use Residential 1 Commercial 2 Residential cum Commercial 3 No of Storeys Open Land/Plot 4 Plantation/ Orchard 5 Graveyard 6 G 1 School 7 PHC/Hosp./Dispensary. 8 Industrial 9 G+1 2 Mazar 10 Temple 11 Masjid 12 G+2 3 Church 13 Shrine 14 Vill Com/ Panchyat/Govt. Land 15 Agriculture 16 Waste/ Grazing/ Barren 17 Others (specify) 99

(Note: Provide a sketch of the property on Page 4 of this questionnaire.) A. IDENTIFICATION A.1 General Identification.

State District Block Town//Village

A.2 Type of Property Private Government Trust Community Others 1 2 3 4 5 A.3 Ownership A.3.1 Do you own the structure/ plot/ agriculture land?

Owner 1. Tenant 2. Encroacher 3. Squatter 4. Share Cropper 5

A.3.2 Occupiers Name ______S/o______

Page 91

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

A.3.3 Name, Address, Phone Number and LANDMARK ______

______

A.3.4 If Tenant, Name and Address and Contact Number of the Owner ______

______

A.3.5 Please provide with an ID Proof (Ration card, Voter Id, PAN Card, Driving Licence, any ONE) Record the details. ______

A.4 Utilities on the Property Sl.No Utilities Unit(s) owned Sl.No Live Stock Asset Numbers 1. Trees 1. Cow 2. Dug wells 2. Buffalo 3. Tube wells 3. Sheep 4. Lift Irrigation Points 4. Goat 5. Water Tap 5. Pig 6. Water Tank 6. Poultry 7. Hand Pump 7. Pond Others (Mention) 8. Cattle Shed 9 Water supply pipeline 10 Boundary wall 11 Barbed wire fence 12 Pond 13 Others (SP)

A.5 Trees that are likely to be affected

Tree type Height of tree Distance from tower base

1. Mango 2. Mulberry, 3. eucalyptus, 4. pine, 5. kikar, 6. shisham and 7. babul

Page 92

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

A.6 Typology of the Main Structure Roof Wall Floor Boundary No of Rooms RCC/RBC 1 Brick 1 Concrete 1 Brick 1 Thatched Wood Mud Barbed 2 2 2 2 Plastic Wire Mud 3 Mud 3 Stone 3 Wood 3 GI / Asbestos Others Others 4 4 9 9 Asbestos Bamboo 5 Others 9 Others 9

B. Structural Details

B.1.1 How old is the structure? (Mention the Year since you are operating from this structure)

B.1.2. How long are you residing or operating from the structure?

B.1.3 Measurement of the Land (in mts)

Length: Breadth: Total Impacted area Remarks if any Area:

B.1.4 Measurement of the Structure/Asset Length: Breadth: Height Total area of Total Remarks if any the structure Impacted area of the structure

B.1.5 What type of business are you doing, in case of commercial use? 1. Tea Stall 8. Kabari Shop 15. Motel 2. Grocery/General/KiranaStore 9. Educational institution 16. Butcher/meat 3. Vegetables/ Fruits 10. Hotel/ Restaurant 17. Barber Shop 4. Cloth/Garments 11. Electrical 18. Medicine Shop 5. Tailor shop 12 Furniture 19 Wine Shop 6. Pan/ Cigarette Shop 13 Petrol Pump 20 Phone/Photocopy shop 7. Garage/ Mechanic Shop 14. Lubricant Shop 99. Any other, please specify

Page 93

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

B.1.6 Is your business self owned? 1 -Yes / 2 - No

B.1.7 How many people have you employed? (number)

B.1.9 Where would you prefer to move from here ? (Residential and Commercial Both ) S No Place Where (specify) Distance in Kms from current location 1 Within the Village/ Town 2 Outside the Village / Town

B.1.10 Do you have any alternative land /structure? 1 - Yes / 2 - No

B.1.11 If Yes, where? Place (specify) Distance in Kms from existing

B.2. Agricultural Details

B.2.1 Do you have agricultural land? 1 - Yes / 2 - No

B.2.2 Type of Land 1. Irrigated 2. Un-irrigated 3. Waste Land 9. Other (Specify)

B.2.3 What Crops you Grow ? 1. Rice 2. Maize 3. Tea 4. Wheat 5. Vegetables 6. Fruits 7. Bamboo 9. Others (Specify)______

B.2.4 For how many years the Land being cultivated by you / your ancestors ____

C.1. Household Details ST (hills) ST SC MOBC OBC General C.1.1. Caste details (Plain ) 1 2 3 4 5 6 Others Specify the Caste Group 9

C.1.2. Type of Family Nuclear Joint Extended Sibling 1 2 3 4

Page 94

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

C.1.2. No. of Persons in Household. Above 15 yrs Below 15 yrs

Codes for Relationship 1 Head of the House Hold 2 Wife 3 Husband 4 Son 5 Daughter 6 Son-in-law 7 Daughter-in-law 8 Grandfather 9 Grandmother 10 Grandson 11 Grand daughter 12 Grandson-in-law 13 Grand daughter-in-law 14 Brother 15 Sister 16 Brother-in-law 17 Sister-in-law 18 Father 19 Mother 20 Father-in-law 21 Mother-in-law 22 Uncle 23 Aunt 24 Cousin 25 Nephew 26 Niece 27 Any other (specify)

C.2. Family Profile. (Start from Head of the Household)

Member 1 2 3 4 5 6 7 8 9 10 11 12 Number Write down the names of all person who live and eat together in C.2.1 Name this household starting with head exclude persons under the age of 14 years. C.2.2 HH Codes as given above Relationship Is the NAME male or female? C.2.3 Sex 1 1 1 1 1 1 1 1 1 1 1 1 Male 2 2 2 2 2 2 2 2 2 2 2 2 Female How old was NAME on the last birthday? C.2.4 Age Record the age on last

birthday 1 1 1 1 1 1 1 1 1 1 1 1 Married 2 2 2 2 2 2 2 2 2 2 2 2 Unmarried C.2.5 Marital 3 3 3 3 3 3 3 3 3 3 3 3 Divorced Status 4 4 4 4 4 4 4 4 4 4 4 4 Separated 5 5 5 5 5 5 5 5 5 5 5 5 Widow/Widower The class till which the person has been educated. 1 1 1 1 1 1 1 1 1 1 1 1 Illiterate 2 2 2 2 2 2 2 2 2 2 2 2 Primary (class 4) Secondary (Class 5 - C.2.6 Education 3 3 3 3 3 3 3 3 3 3 3 3 10) 4 4 4 4 4 4 4 4 4 4 4 4 Higher (graduate) 5 5 5 5 5 5 5 5 5 5 5 5 Technical 6 6 6 6 6 6 6 6 6 6 6 6 Vocational 1 1 1 1 1 1 1 1 1 1 1 1 Handicap by birth Handicap due to other C.2.7 2 2 2 2 2 2 2 2 2 2 2 2 reasons Health Any other chronic 3 3 3 3 3 3 3 3 3 3 3 3 health problems

Page 95

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

D.1. Employment Status of the Family Members

D.1 Is the NAME working? Employment 1 1 1 1 1 1 1 1 1 1 1 1 Yes Status 2 2 2 2 2 2 2 2 2 2 2 2 No This may have The occupational activity at the place of job? multiple entries 1 1 1 1 1 1 1 1 1 1 1 1 Agriculture 2 2 2 2 2 2 2 2 2 2 2 2 Agri Labour 3 3 3 3 3 3 3 3 3 3 3 3 Non Agri Labour D.2 Occupation 4 4 4 4 4 4 4 4 4 4 4 4 Business/Trade 5 5 5 5 5 5 5 5 5 5 5 5 Govt. Service 6 6 6 6 6 6 6 6 6 6 6 6 Private Service 7 7 7 7 7 7 7 7 7 7 7 7 Maid Servant 9 9 9 9 9 9 9 9 9 9 9 9 Others To be filled for What was the main reason for the NAME not working? persons who are not working. 1 1 1 1 1 1 1 1 1 1 1 1 No work available 2 2 2 2 2 2 2 2 2 2 2 2 Seasonal inactivity D.3 Non- Household family Working Status 3 3 3 3 3 3 3 3 3 3 3 3 duties 4 4 4 4 4 4 4 4 4 4 4 4 Old/young 5 5 5 5 5 5 5 5 5 5 5 5 Handicapped 6 6 6 6 6 6 6 6 6 6 6 6 Student 9 9 9 9 9 9 9 9 9 9 9 9 Others How much does the NAME earn in a month?

1 1 1 1 1 1 1 1 1 1 1 1 Less than Rs.2000 D.4 Income 2 2 2 2 2 2 2 2 2 2 2 2 Rs.2000 – 3000 3 3 3 3 3 3 3 3 3 3 3 3 Rs. 3000 - 4000 4 4 4 4 4 4 4 4 4 4 4 4 Above Rs 4000 What type of skill possessed by the person? D.5 Skills 1 1 1 1 1 1 1 1 1 1 1 1 Computer

2 2 2 2 2 2 2 2 2 2 2 2 Weaving

3 3 3 3 3 3 3 3 3 3 3 3 Typing

4 4 4 4 4 4 4 4 4 4 4 4 Mechanic

5 5 5 5 5 5 5 5 5 5 5 5 Driving

6 6 6 6 6 6 6 6 6 6 6 6 Others (specify)

7 7 7 7 7 7 7 7 7 7 7 7 None

D.6 Household Expenditure Item Amount 1 Food 2 Cooking Fuel 3 Clothing 4 Transport

Page 96

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

5 Health Care/Medicines 6 Education 7 Electricity/Utilities 8 Social events 9 Agriculture (Labor/ Tools) 10 Seeds/Fertilizers/Pesticides 11 Water 12 Deisel Generator 13 Others

D.7 Have you availed of benefit under any Govt. Scheme ? 1. Yes 2. No Yes Purpose Amount Availed Training 1. JRY/ IJRY 2. DWACRA 3. IPDP 4. PMRY 5. NREGP 6. Others (Specify)

D.8 Site Observations (distance from start point):

Km Observations

Page 97

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Annexure E3: Proforma for compensation of Standing Crops

Page 98

Draft Resettlement and Rehabilitation Action Plan – Package G 6 Transmission lines Haryana Power System Improvement Project

Page 99