Environment Monitoring Report

Project Number: 35354-013 January 2018

PRC: - Chongqing Railway Development Project

Prepared by Beijing OASIS Environmental Protection Technology Co., Ltd.

This Environment Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

New Project Developed with Loan from Asian Development Bank New Lanzhou-Chongqing Railway Development Project Environmental Monitoring Report (2017)

Beijing OASIS Environmental Protection Technology Co., Ltd. January 2018 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

Table of Contents

1. Foreword ············································································ 1

1.1 Project Introduction ···························································· 1

1.2 Characteristics of This Project ·············································· 3

1.3 Environment Monitoring ······················································ 4

2. Brief of Engineering ······························································· 6

2.1 Project Construction Unit, Constructor and Supervision Unit of

Lanzhou - Chongqing Railway ······················································ 6

2.2 Engineering Progress ·························································· 8

3. Environmental Management ···················································· 9

3.1 Environmental Management System ········································ 9

3.2 Environment Management of Lan-Yu Railway Company in 2017 ····· 11

4. Supervision and Inspection of Influential Point ··························· 12

4.1 Ecological Protection and Soil and Water Conservation Engineering · 14

4.2 Implementation of Pollution Control Measures ·························· 22

5. Photos ·············································································· 25

1 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

List of Photos

Photo 1. Static Acceptance Report for Environmental Protection and Water & Soil Conservation Project

of Newly Built Lanzhou ~ Chongqing Railway (K41+759.928~k221+393

County Section>)

Photo 2. Reply of Provincial Agricultural and Pastoral Department to the Evaluation Report on

Impacts of Lanzhou-Chongqing Railway on Provincial Natural Reserve of for

Brachymytax Lenoks (Presently the Zhang County National Nature Reserve for Rare Aquatic

Lives)

Photo 3. Reply of Sichuan Provincial Agricultural Department for Disaster Prevention, Rescue &

Evacuation Project of Zizhuyuan Tunnel of Lanzhou~Chongqing Railway to Run through

Sichuan Maozhai Pilot Nature Reserve

Photo 4. Exit of Humaling Tunnel of Railway No.19 Bureau in Bid Section I

Photo 5. The spoil area for 3# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid

Section I has been constructed with retaining wall and already restored as farmland.

Photo 6. The spoil area for 3# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid

Section I has been constructed with flood drainage trench and already restored as farmland.

Photo 7. The spoil area for 4# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid

Section I has been constructed with flood drainage trench and already restored as farmland.

Photo 8. Small bridge over the flood drainage trench for 4# inclined shaft spoil area of Humaling Tunnel

of China Railway No.19 Bureau in Bid Section I

Photo 9. The spoil area for 5# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid

Section I has been constructed with flood drainage trench and already restored as farmland.

Photo 10. The spoil area at exit of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has

already been restored as farmland.

Photo 11. The spoil area at the inlet of Jutou Tunnel of China Railway No.19 Bureau in Bid Section I has

already been restored as farmland.

Photo 12. The spoil area at the inlet of Yangjiawan Tunnel of China Railway No.16 Bureau in Bid Section

II has been constructed with retaining wall and already restored as farmland.

Photo 13. The spoil area at the inlet of Yangjiawan Tunnel of China Railway No.16 Bureau in Bid Section

II has been constructed with drain and planted with trees and already restored as farmland.

2 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

Photo 14. The spoil area at the outlet of Yangjiawan Tunnel of China Railway No.16 Bureau in Bid

Section II has been constructed with drain and divided into two levels of steps and already

restored as farmland.

Photo 15. After delivery, the spoil area at the outlet of of Kezhai Tunnel of China Railway No.16 Bureau

in Bid Section II is occupied by Lintao~Weiyuan Expressway as permanent construction land.

Photo 16. Daping trackless spoil area for Muzhailing Tunnel of China Railway Tunnel Group in Bid

Section III has been constructed with retaining wall and drain and presently is used as

construction camp of the Expressway project.

Photo 17. Daping track-section spoil area for Muzhailing Tunnel of China Railway Tunnel Group in Bid

Section III has been constructed with retaining wall and now is used as construction camp of the

Expressway project.

Photo 18. The spoil area for south drainage ditch of Muzhailing tunnel of China Railway Tunnel Group in

Bid Section III has been constructed with retaining wall and the side slope has been divided into

four levels of steps and already restored as forest land and planted with trees.

Photo 19. The newly-built Luzha Spoil Area of Muzhailing Tunnel of China Railway Tunnel Group in Bid

Section III has been constructed with retaining wall and the side slope has been divided into

three levels of steps and already afforested. Now houses have been built for the Expressway

project.

Photo 20. The Luzha spoil area of Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III

has been constructed with retaining wall and the side slope has been divided into three levels of

steps and already afforested. Some work sheds have been built there for the Expressway project.

Photo 21. Dagouzhuang Spoil Area for Muzhailing Tunnel of China Railway Tunnel Group in Bid Section

III has been constructed with retaining wall and the side slope has been divided into three levels

of steps and already afforested.

Photo 22. Dazhangou Spoil Area for Muzhailing Tunnel of China Railway Tunnel Group in Bid Section

III has been constructed with retaining wall and the side slope has already been afforested.

Photo 23. The spoil area at the outlet of of Muzhailing Tunnel of China Railway Tunnel Group in Bid

Section III has been constructed with retaining wall, and most of wasted soil is transported away

for reuse. Some resident houses are built there.

Photo 24. The spoil area at the inlet of Guzishan Tunnel of China Railway No.7 Bureau in Bid Section II

3 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

has been constructed with retaining wall, and the side slope has been divided into 5 steps and

the land there is already restored as farmland.

Photo 25. The camp for 3# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid

Section I has been rehabilitated and now is going through the delivery formalities.

Photo 26. The mixing station for 3# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in

Bid Section I has been rehabilitated and delivered.

Photo 27. The camp for 4# inclined Shaft for Humaling Tunnel of China Railway No.19 Bureau in Bid

Section I has already been restored as farmland and already delivered.

Photo 28. The camp for 5# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid

Section I has already been restored as farmland and already delivered.

Photo 29. The construction roads for 3# and 5# inclined shafts of Humaling Tunnel of China Railway

No.19 Bureau in Bid Section I is being restored as farmland.

Photo 30. The camp at the inlet of Jutou Tunnel of China Railway No.19 Bureau in Bid Section I has been

restored as farmland and already delivered.

Photo 31. The mixing station at the inlet of Jutou Tunnel of China Railway No.19 Bureau in Bid Section I

has been restored as farmland and already delivered.

Photo 32. The sites of the camp and mixing station for 6# inclined shaft of Muzhailing Tunnel of China

Railway Tunnel Group in Bid Section III have been restored as farmland.

Photo 33. The noise barrier for K136+211~k136+411 of China Railway No.16 Bureau in Bid Section II

has been completed, beside which is Weiyuan County Vocational School.

4 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

1. Foreword

1.1 Project Introduction

1.1.1 Route trend & major technological standards Lanzhou-Chongqing Railway (Lan-Yu Railway) starts from Lanzhou terminal of Lanzhou city, Gansu, goes through administration areas such as and of Gansu, Hanzhong of Shaanxi, Guangyuan, Nanchong and Guang’an of Sichuan, and Hechuan District of Chongqing, and ends at Chongqing terminal of Chongqing. A single-line railway branches out from Nanchong to Gaoxing via Guang’an. The railway line goes roughly in the south-north direction. A double-line railway, 819.975 Km in total, shall be built between Lanzhou station and Beibei North Station. Of it, 491.437 Km is for the section between Lanzhou and Guangyuan (not included) and 328.538 Km for the section between Guangyuan (included) and Chongqing. The length of single-line railway between Nanchong and Gaoxing via Guang’an is 93.639 Km. The construction period of this project is 6 years and the estimated total investment for this project is 78.9 billion yuan, of which, 300 million US dollars are the loan from Asian Development Bank.

The main technical standards for the main line of Lanzhou-Chongqing railway: Grade of railway State railway, grade I Number of main lines Double-line railway for the section between Lanzhou and Chongqing and single-line railway for the section between Nanchong East and Gaoxing; Limiting Gradient 13‰ for the section between Lanzhou and Guangyuan; 6‰ for the section between Guangyuan and Chongqing and for the section between Nanchong East and Gaoxing; Target speed: 200 Km/h for the section between Lanzhou and Chongqing and 160 Km/h for the section between Nanchong East and Gaoxing; Traction mode Electric power

1 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

Traction mass: 4000t The minimum curvature radius: 3500 m for ordinary railway section and 2800 m for difficult railway section between Lanzhou and Chongqing 200 km /h; 2000 m for ordinary railway section and 1600 m for the difficult railway section between Nanchong East and Gaoxing; Locomotive type The section between Lanzhou and Chongqing: passenger train CRH, SS7E; cargo train SS7. The section between Nanchong East and Gaoxing: passenger train SS7E and cargo train SS7. Effective Line from the Starting to the Destination: Single module: 850 m; dual module: 880 m

1.1.2 Main engineering content  Total cubic meter of earth and stone for the whole line is 22880.5×104m3, 17776.82×104m3 for excavation, 5103.68×104m3 for filling; there are 433 Super-major bridges, major bridges and medium bridges with total length of 181788 linear meters of whole line; there are 267 tunnels, 596.8 km long wholly; there are 11 tunnels more than 10 km long with length of 168 km; the track laying of main track is 819.975 km, and that for hub and link lines is 180 km; 23 traction substations; the whole line covers land of 5218.2 hm2, land of permanent use covers 3289.7 hm2 and the land of temporary use covers 1928.5 hm2.  42 new stations will be built and 15 stations will be modified along the whole line.  Pavements 1445.1 Km in length will be built.  There are 324 sensitive points for noise and vibration treatment along the whole line. Besides functional replacement is needed for 115 places, noise barriers (40310 m) or acoustic windows (83120 m2) will be arranged at 209

2 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

places. The total investment on noise treatment will be 202.433 million Yuan.

1.2 Characteristics of This Project

Lanzhou – Chongqing Railway goes through, from the north to the south, such three geomorphic units as Loess Plateau, high and medium mountains of the Qinling Mountains and low mountains and hills area in Sichuan Basin and spans such four climate zones as the arid climate area in the mid-temperate zone of Loess Plateau, sub-humid climate zone of mid-temperate zone, North Asia tropical humid zone in the high and medium mountains in the Qinling Mountains and Middle Asia tropical humid zone in Sichuan Basin. Along Lanzhou-Chongqing Railway, there are many kinds of vegetation. The horizontal and vertical distribution of vegetation is obvious. Roughly, Qinling Mountains is taken as the dividing line. The biodiversity in Yangtze River Basin on the south of Qinling Mountains is higher than that in the Yellow River basin. The land erosion area in the drainage area of the Yellow River basin, in which the railway goes, is big, and the erosion extent is mainly medium, but it is serious or extra serious for some sections. The erosion variety takes the water conservancy erosion as the main and such gravity erosions as mud-stone flow and landslide etc. often occur in the earth and stone and mountain area. The ecological environment along the line sections in the drainage area of the Yangtze River is comparatively better, and, basically no obvious erosion or only light erosion can be seen for soil erosion. Along the line, there are rich resources of wildings as well as cultural relics, which are mainly distributed in the natural reservation zones, the famous scenery spots and historical relics, forest parks, and the cultural relic protection zones and are greatly affected by human activities. Emphasized protection targets: Ancient Xiaguanying relic, ancient Shannashuzha relic, Yuhe Natural Reserve of Gansu Province, Sichuan Maozhai Nature Reserve, Wetlands Natural

3 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

Reserve of Jialing River Source, Myxiocyprinus Asiaticus of Natural Reserve, etc.; Ecological environmental protection main targets: cultural heritage, the vegetation, rare animal and land resources, etc. along the line. It is the important contents for environment monitoring work to strictly implement the relevant state laws and regulations, abide by the requirements and replies from the relevant state and local departments as well as various levels of departments for cultural relics, water conservation, forestry, environmental protection and fishing administration etc. and strictly execute the various measures in the EIA (environmental impact assessment) report during the construction. The big rivers spanned by the railway line are the Yellow River, the Wei River, the , the Bailong River, the Jialing River, the Fu River and the Qu River etc. Since high subgrads will be replaced by bridges for this project, there is much bridge construction engineering for the whole line. The land occupation and disposed earth from the sub-grade for non-river-crossing bridges has certain impacts on the ecological environment along the line, so has the construction of river-crossing bridges on the water quality and hydro bios of rivers. The total volume of the cubic meter of earth and stone along this line is large and the volume of disposed earth is far bigger than the volume of taken earth, so it is vitally important to further optimize the allotment of cubic meter of earth and stone, reduce the earth-taking and earth-disposing volumes and occupied land areas, take such preventive measures as land reclamation and afforestation etc. in accordance with the land reclamation program and design for temporary land use and prevent the generation of new land erosion.

1.3 Environment Monitoring

The environment monitoring is to supervise and inspect the execution of environmental protection measures during construction of the project on the basis of the design and environment evaluation report of this project and to affirm the achievements, find out existing problems and give suggestions on

4 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017 countermeasures. By strengthening process control, the environmental monitoring ensures to carry out “Three-simultaneousness” system strictly. It reflects the dynamic implementation status of environmental protection work on the construction site during the construction activities so as to confirm whether the relevant rules and regulations for environmental protection have been satisfied and whether the requirements from Ministry of Railways and Asian

Development Bank have been met. Key points that attention should be paid to during environment monitoring include:  Whether the environmental impact during construction is consistent with the environmental problem put forward in the environmental impact assessment report;  The accomplishment of environmental protection measures given in environmental impact assessment report;  Identify and find out any unexpected environmental problems and put forward recommended solutions; The environmental monitoring of Lanzhou-Chongqing Railway is taken by Beijing OASIS Environmental Protection Technology Co., Ltd. The service range is the main line of Lanzhou-Chongqing Railway from Lanzhou to Beibei North, which is 818.71 km long in total. The cycle of environment monitoring work is the construction period of the whole line and within the two years after being put into operation after completion. For every half year of the construction period and for every year of the two years after completion, one environment monitoring report (in both English and Chinese) should be prepared by OASIS Company on the basis of the on-site survey and collected monitored data and submitted to Materials Department of China Railway Corporation, Lanzhou-Chongqing Railway Co., Ltd., Development Planning Department of the Ministry of Railways and Asian Development Bank. The monitoring report should contain the following content:  Impacts on the ecological environment imposed by construction of stations,

5 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017 tunnels, bridges and subgrade inside key ecological environmental protection zones such as natural preservation zones, scenic spots, forest park and ancient cultural relics etc. as well as the recovery and treatment measures;  Impacts of arrangement, protection, reclamation and afforestation measures for the spoil ground (area) on the water and soil conservation facilities, disturbance imposed by construction to vegetation and recovery and treatment measures;  Impacts of tunnel construction on ambient environment and implementation status of protective measures;  Impacts on the surface water body from the bridge construction and the implementation status of preventive measures;  The implementation and effect of the protective measures of subgrade slope.  Impact and prevention of noise, sewage water, dust and solid waste created in the construction camps, on the pavements, girder fabrication yards and laying and erecting foundation on the temporary engineering sites and recovery measures of land for temporary use.  Implementation status of various environment protection measures adopted for the project (including the noise prevention engineering, sewage treatment and electromagnetism, etc.).  Propaganda on sanitation in the construction camp and health of construction personnel.

2. Brief of Engineering

2.1 Project Construction Unit, Constructor and Supervision Unit of Lanzhou - Chongqing Railway

The project implementation unit of Lanzhou-Chongqing Railway is Lanzhou-Chongqing Railway Co., Ltd. There are 16 bid sections, 19 constructors and 13 supervision units along the whole line. Table 2-1 lists the

6 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017 constructors and supervision units for each bid section.

Table 2-1 Constructors and Supervision units of Various Bid Sections of

Lanzhou-Chongqing Railway Length of N Construction Section Constructor Supervision unit bid section o. mileage (km) China Railway No.10 Bureau Engineering Consultancy Group Co., Ltd. DK30+000- 1 LYS-1 & Supervision Co., Ltd. 73.14 China Railway DK103+150 of FSDI. No.19 Bureau Group Co., Ltd. China Railway Gansu Tieke No.16 DK103+150- 2 LYS-2 Construction Supervision 69.96 Engineering DK173+200 Co., Ltd. Group Co., Ltd. China Railway Tunnel Group Beijing Tiecheng DK173+200- 3 LYS-3 China Railway Construction Supervision 83.74 DK259+510 No.7 Engineering Co., Ltd. Group Co., Ltd. China Railway No.11 Engineering Beijing Tieyan Group Co., Ltd. DK259+510- 4 LYS-4 Construction Supervision 93.65 China Railway DK352+759 Co., Ltd. No.13 Engineering Group Co., Ltd. CCCC Second Supervision Company of Highway DK352+759- 5 LYS-5 Lanzhou Jiaotong 33.45 Engineering Co., DK391+800 University Ltd. China Railway Sichuan Tieke DK391+800- No.18 6 XQLS1 Construction Supervision DK423+915(right 32.11 Engineering Company line) Group Co., Ltd. Sichuan Tieke China Railway DK391+800- 7 XQLS2 Construction Supervision 32.11 Tunnel Group DK423+915(left line) Company CCCC First Inner Mongolia QinYuan Harbor DK423+915- 8 LYS-6 Engineering Consultancy 76.94 Engineering Co., DK501+005 Co., Ltd Ltd. China Railway Gansu Xinda No.21 DK000+000- 9 LYS-7 Construction Supervision 29 Engineering DK30+000 Co., Ltd. Group Co., Ltd. China National Zhengzhou Zhongyuan DK569+385- 10 LYS-8 Coal Group Construction Supervision 8.065 DK577+450 Corporation Co., Ltd.

7 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

China Railway Zhengzhou Zhongyuan No.18 DK606+710- 11 LYS-9 Construction Supervision 9.015 Engineering DK615+725 Co., Ltd. Group Co., Ltd. China Railway China Railway Eryuan DK615+725- 12 LYS-10 No.2 Engineering Engineering Consultancy 31.575 DK647+300 Group Co., Ltd. & Supervision Co., Ltd. Road and bridge Beijing Fangda DK647+300- 13 LYS-11 international Co., Construction Supervision 105.617 DK754+000 Ltd. Co., Ltd. CCCC First Beijing Fangda Highway DK754+000- 14 LYS-12 Construction Supervision 108.354 Engineering Co., DK881+400 Co., Ltd. Ltd. Not within China Railway Henan Changcheng ID2K770+955.51- the 15 LYS-13 No.1 Bureau Construction Supervision ID2K860+092 monitoring Group Co., Ltd. Co., Ltd. range China Railway Beijing Tiecheng DK881+400- 16 LYS-14 No.10 Bureau Construction Supervision 70.713 DK952+110.299 Group Co., Ltd. Co., Ltd. 2.2 Engineering Progress The construction kickoff meeting for this railway line was held on Sep. 26, 2008, on which the construction of this project starts officially. In October 2008, construction of 28 Km-long Xiqinling Tunnel started, which is the control project of the whole line; in March 2009, Xiaguanying-Guangyuan section started for construction; in July 2009, the bidding documents for Guangyuan-Chongqing section were opened and the contractors concerned arrived at the site; in September 2009, commencement began in succession in all construction and supervision bid sections. By far, Gaoxing branch line has been completed, Weituo-Chongqing section was opened on Dec. 30, 2014; Guangyuan-Weituo section of Lanzhou-Chongqing Railway was opened on Dec. 30, 2015. The section from Lanzhou East Railway Station to Xiaguanying Station was opened on June 28, 2016; the Guangyuan ~ section was opened on December 26, 2016; the Min County ~ Xiaguanying section was opened in September 2017, which means that the Lanzhou-Chongqing Railway is wholly opened for traffic. In view of the residual engineering workload of Lanzhou-Chongqing Railway is not large and has little impact on the surrounding environment. Therefore, the

8 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017 environment monitoring reports from 2015 to 2017 will be reported to ADB, China Railway Corporation and the Lanzhou-Chongqing Railway Co., Ltd. in the form of annual reports.

3. Environmental Management

3.1 Environmental Management System As the implementation unit of this railway line, Lanzhou-Chongqing Railway Co., Ltd. is responsible for the environmental protection of this line. The Environmental Protection Bureaus of Gansu (Lanzhou, Dingxi and Longnan cities), Shaanxi (Hanzhong city), Sichuan (Guangyuan, Nanchong and Guang’an cities) and Chongqing (Hechuan District) are responsible for supervision and management of environmental protection in their respective jurisdiction regions. Environmental monitoring for main line of Lanzhou-Chongqing Railway shall be undertaken by Beijing OASIS. The constructors and supervision units are responsible for daily monitoring and supervision during construction. The construction unit and OASIS are responsible for collection of monitoring data, and then OASIS shall compile the environmental monitoring report and submit it to China Railway Corporation and Asian Development Bank. The environment monitoring procedures for this railway line are shown in block diagram 3-1. According to the characteristics of this project and frequent environmental problems in the construction, the monitoring unit advises to conduct the environmental protection and management from the following aspects:  Advise the project management department of each bid section to have the full-time (part-time) worker for environmental protection. They need the pre-post training of environmental protection, take charge of supervising and managing the environmental problem during construction process, and assist environmental administrative department to do well the environmental protection work.

9 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

Lanzhou-Chongqing Railway Co., Ltd. Consultation

Entrusting & Assisting

Sub-contracting Environmental Monitoring Unit Contract

CONSTRUCTOR Engineering Supervisor

Implementation Supervision

Engineering Construction of Lanzhou-Chongqing Evaluation of Engineering Railway Implementation

Figure 3-1 Block Diagram of Environment Monitoring Procedures

Block diagram instructions: Lanzhou-Chongqing Railway Co., Ltd.: As the constructor, entrusts the supervision unit to complete the monitoring work, including signing the relevant environmental protection contracts with the constructors and supervision units when awarding the contracts of project. Contractor: Execute the project and complete the environmental protection work according to the requirements of contract. Engineering Supervisor: It supervises the engineering quality and environmental protection processing according to contractual requirements. Monitoring unit: As an external monitoring unit, it evaluates the implementation of environmental engineering and submits the monitoring reports to Lanzhou-Chongqing Railway Co., Ltd., China Railway Corporation and Asia Development Bank.

 Each constructor is advised to perform the corresponding promise of environmental protection in construction contract. Formulate corresponding measures for environmental protection pursuant to the environmental protection requirements specified in the design document, protect the environment of construction site, and avoid and reduce environmental pollution or damage due to improper methods of construction. Upon occurrence of environmental damage, adopt measures actively for treatment, and invite relevant experts and units immediately for solution if independent solution is not available.  The supervision unit is required to be responsible for daily environmental monitor work in accordance with the environmental protection requirements under the construction contract. Once an environmental problem occurs during the construction, it should supervise and urge

10 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017 its timely solution and include the environmental protection into the engineering quality supervision system. 3.2 Environment Management of Lan-Yu Railway Company in 2017

I. The environmental management of sections which have been opened in operation period After the completion of Lanzhou-Chongqing railway sections, the Lanzhou-Chongqing Railway Co., Ltd. will entrust the operations management to Chengdu Railway Bureau and Lanzhou Railway Bureau for unified management in accordance with the principle of territory. Chengdu Railway Bureau and Lanzhou Railway Bureau have a complete environment management system and will manage the environmental protection work of the whole railway bureau. The environmental protection and energy saving and emission reduction work of Chengdu Railway Bureau and Lanzhou Railway Bureau is in the charge of the chief engineer and the leadership of railway bureau and they specifically set up the Energy Conservation and Environmental Protection Office (Section) under the Planning and Statistics Department, with full-time management staffs who are responsible for daily environmental monitoring work in environmental monitoring agency set up in the railway bureau. II. Static acceptance of environment and water conservation project of Xiaguanying ~ Min County Section (K41+759.928~K221+393, totally 179.6km (normal line)) The working group for the professional static acceptance of environment and water conservation work in Guangyuan-Min County section that composed by Lanzhou Railway Bureau and Lanzhou-Chongqing Railway Co., Ltd. has carried on the static preliminary inspection on July 24 to 28, 2017 and the static re-inspection on Aug. 20 to 23, 2017.

11 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

III. The static acceptance conclusion: According to the Notice of the former Ministry of Railways on Reprinting the Administrative Measures for Completion Acceptance and Hand-over of Railway Construction Projects (Tiejianshe [2008] No.23) and the Implementation Rules for Completion Acceptance Work of Environmental Protection and Water & Soil Conservation Facilities of Expressways (Tieji [2012] No.264), the workgroup for static acceptance of environment and water conservation executed the acceptance to relevant environment and water conservation projects of the newly built Lanzhou ~ Chongqing Railway (Xiaguanying – Min County section). The Workgroup believed that the suggestions reflected in the Environmental Impact Assessment Report and its reply and the environmental protection measures proposed in the design documents have already been basically ascertained and implemented; the water and soil conservation plan and the suggestions given in its reply and the water conservation measures specified in design documents have already been basically ascertained and implemented and the protective effects are outstanding. The environment and water conservation projects have passed the static acceptance inspection, and the next step could be carried out according to the procedures. Photo 1. Static Acceptance Report for Environmental Protection and Water & Soil Conservation Project of Newly Built Lanzhou ~ Chongqing Railway (K41+759.928~k221+393 )

4. Supervision and Inspection of Influential Point

On November 1, 2017, OASIS submitted the Executive Plan for Environmental Monitoring and Survey of Lanzhou-Chongqing Railway for 2017 to Lanzhou-Chongqing Railway Co., Ltd. to define the key points and the

12 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017 executive plan of this monitoring activity. The key contents of this environment monitoring work are: 1. Field Investigation Investigate the Min County ~ Xiaguanying section opened this year on the field, and check whether appropriate fence and / or retaining wall has been built for relevant spoil grounds and whether the topsoil there has been rehabilitated; investigate the restoration of beam fabrication yards, concrete mixing stations, construction roads on the construction sites; investigate the implementation of environmental protection measures such as noise barriers on the field. 2. Data and Information Collection Collect the static and dynamic environment protection acceptance reports of various sections successfully opened, and understand the implementation of environment protection measures of the whole line and the details of ecological sensitive areas it runs across. Collect the data obtained during the environment protection and water & soil conservation supervision and monitoring work of this year and the inspections by governmental departments concerned; collect relevant documents issued by relevant administrative departments of ecological sensitive areas for construction of Lanzhou~Chongqing Railway. This report is based on the site restoration data and static acceptance report obtained during the field investigation made after the Min County ~ Xiaguanying section of Lanzhou ~ Chongqing Railway was opened in 2017 and will focus on introducing the implementation of environment protection measures of this section. From November 9 to 15, 2017, Jiao Jusheng from our company, accompanied by Engineer Zhang Yong from the Engineering Department of Lanzhou ~ Chongqing Railway Co., Ltd., investigated part of construction sites of Xiaguanying ~ Min County section of this railway and mainly visited 17 (borrow) spoil grounds (areas), 9 temporary construction sites and 1 noise barrier (totally 27).

13 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

Main sites investigated are: Borrow and spoil (grounds) areas (17 in total) are: Spoil areas for 3#, 4# and 5# inclined shafts of Humaling Tunnel; spoil area at the outlet of of Humaling Tunnel; spoil area at the inlet of Jutou Tunnel; spoil areas at the inlet and the outlet of Yangjiawan Tunnel; spoil area at the outlet of of Kezhai Tunnel; Daping Trackless Section, Daping Track-section, Nanshuigou, Newly-added Luzha, Luzha, Dagouzhuang and Dazhangou spoil areas; spoil area at the outlet of Muzhailing tunnel and spoil area at the inlet of Guzishan tunnel. Land restoration of 9 temporary construction sites: Camps for 3#, 4# and 5# inclined shafts of Humaling Tunnel; camp at the outlet of Humaling Tunnel; camp at the inlet of Jutou tunnel; mixing station for 3# inclined shaft of Humaling Tunnel; mixing station at entrance of Jutou Tunnel and construction roads of 3# and 5# inclined shafts of Humaling Tunnel; 1 noise barrier: the noise barrier for K136+211~k136+411 This report is written by: Jiao Jusheng

4.1 Ecological Protection and Soil and Water Conservation Engineering

Ecological protection and water & soil conservation measures mainly include: Afforestation works and water drainage works for roadbeds and side slopes; Station and yard protection works; protection works for front slopes of tunnels; restoration measures for such temporary works as borrow pits, spoil grounds (areas), mixing stations, construction camps, construction roads and so forth. 4.1.1 Implementations of protection measures for key environment-sensitive protection objects I. In the region where the Xiaguanying ~ Min County section is located, there is 1 important sensitive protection object: Zhang County Province-level Natural Reserve for Brachymystax Lenoks Tsinlingensis

14 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

(presently Zhang County National Nature Reserve for Rare Aquatic Lives), Overview of Zhang County National Nature Reserve for Rare Acquatic Lives On February 2, 2005, the People’s Government of Gansu Province approved in File Ganzhenghan [2005] No.4 to set up Gansu Zhang County Province-level Natural Reserve for Brachmystax Lenoks Tsinlingensis, which focuses on protecting brachmystax lenoks tsinlingensis (a national Level II protected aquatic wildlife). In March 2010, the Bureau of Zhang County Province-level Natural Reserve for Brachmystax Lenoks Tsinlingensis submitted the Application for Establishing National Nature Reserve and associated documents to the National Nature Reserve Assessment Committee step by step for setting up Gansu Zhang County National Nature Reserve for Rare Aquatic Wildlife, which was finally approved and, then, in File Guobanfa [2013] No.48, it was approved by the General Office of the State Council to be upgraded as a national nature reserve. (1) Environment Impact Assessment Stage The Environment Impact Assessment Report does not cover relevant content relating to Lanzhou-Chongqing Railway running across Zhang County Province-level Natural Reserve for Brachymystax Lenoks Tsinlingensis (presently Zhang County National Nature Reserve for Rare Aquatic Wildlife). In October 2012, the Bureau of Gansu Zhang County Natural Reserve for Brachymystax Lenoks Tsinlingensis issued the document Zhangqinguanzi [2012] No.3 – the Letter on Going through Required Formalities for Construction of Lanzhou~Chongqing Railway in Zhang County Natural Reserve for Brachymystax Lenoks Tsinlingensis as Soon as Possible to the project undertaker Lanzhou~Chongqing Railway Co., Ltd., requiring that the project undertaker should contact the Aquatic Wildlife Protection Office of Gansu Agriculture Department or the Bureau of Zhang County Natural Reserve for Brachymystax Lenoks Tsinlingensis as soon as possible to verify the railway route, jointly

15 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017 discuss and work out the protect plan and take practicable protection measures. In January 2013, Lanzhou-Chongqing Railway Co., Ltd. entrusted Gansu Fishery and Water Environment Protection Station to work out the Aquatic Life Assessment Report. The Aquatic Life Assessment Report and its reply required the project undertaker to perform associated promises and agreements comprehensively, ascertain and implement various protection measures, strictly ascertain and implement relevant vibration and noise reduction measures in the operation period so as to minimize the impacts to be imposed by railway operation on brachymystax lenoks tsinlingensis. It also required that the project undertaker should hold responsible for the ecological compensation funds for natural reserve monitoring, fishery management, artificial domestication center construction, fish fry releasing station and rescue station construction, enrichment and release and so on. (2) Opinions of Competent Authority In the construction period of this project, Gansu Provincial Agricultural and Pastoral Department approved in principle the construction of this project by issuing Gannongmuhan [2016] No.65 Reply of Gansu Provincial Agriculture and Animal Hudbandry Department to the Report on Assessment of Impacts of Lanzhou-Chongqing Railway to Zhang County Province-level Natural Reserve for Brachymystax Lenoks Tsinlingensis (Presently Zhang County National Nature Reserve for Rare Aquatic Wildlife). (3) Field Inspection The field inspection shows that Lanzhou-Chongqing Railway actually built 3 bridges (Zhoujiazhuang Tiegouhe Major Bridge (DK151+676), Chichali Medium Bridge (DK152+918) and Hujiawan Tiegouhe Medium Bridge (DK155+949) over Tiegou River and its core branches in Zhang County Province-level Natural Reserve for Brachymystax Lenoks Tsinlingensis (presently Zhang County National Nature Reserve for Rare Aquatic Wildlife).

16 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

These projects have not set up any piers in water and are not materially running across the Nature Reserve. During the construction, the project undertaker has basically satisfied the requirements set forth in the Environment Impact Assessment Report and its reply, reinforced various protection measures, and arranged the ecological compensation funds for natural reserve monitoring, fishery management, artificial domestication center construction, fish fry releasing station and rescue station construction, enrichment and release and so on. For examples, it has strengthened the storage and management of construction materials, arranging them far away from rivers and taking appropriate rainproof and damp-proof measures; it has arranged appropriate centralized storage places for solid wastes, arranging them far away the rivers and in low places, while taking perfect wind-proof, rainproof, fencing and retaining measures. II. The proposal for the disaster prevention, rescue and evacuation works of Zizhuyuan Tunnel to run through Sichuan Maozhai Protection Zone was approved by Sichuan Provincial Agricultural Department via the Reply on the Disaster Prevention, Rescue and Evacuation Works of Zizhuyuan Tunnel of Lanzhou-Chongqing Railway to Run Through Sichuan Maozhai Province-level Pilot Nature Reserve. Strictly in accordance with the the Reply of Sichuan Provincial Agricultural Department on the Disaster Prevention, Rescue and Evacuation Works of Zizhuyuan Tunnel of Lanzhou-Chongqing Railway to Run Through Sichuan Maozhai Province-level Pilot Nature Reserve, the project undertaker had focused on executing the following work: (I) Prior to construction, according to the approved land occupation range and area, planned the red lines of land to be occupied by the disaster prevention, rescue and evacuation works of Zizhuyuan Tunnel of Lanzhou-Chongqing Railway in Sichuan Maozhai Province-level Pilot Nature Reserve, strictly controlled all construction activities within the red

17 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

lines, and strictly forbidden any land occupation or vegetation clearing or removal out of the land occupation range. (II) Optimized the construction plan, reasonably arranged the quantity of construction persons, used the centralized construction method to shorten the construction time in the protection zone and forbidden any nighttime construction so as to reduce the disturbance of construction activities to the protection zone. (III) During the construction of main work of disaster prevention, rescue and evacuation platform, tamped and refilled the ground step by step and taken measures to avoid construction wastes from falling off. Strictly follow relevant technical indicators and the engineering design to carry out such auxiliary works as ballasted walls and drains, avoiding induced geological hazards. (IV) While building up any construction roads, made efforts to reduce construction excavation surfaces and carry out various construction activities strictly in compliance with the water and soil conservation plan, and ascertained and implemented required water and soil conservation measures to reduce water loss, soil erosion and vegetation damage. (V) Strengthened the management of construction camps, stock yards and construction persons, especially strengthened the management of fire sources and field fires, worked out appropriate fire-fighting contingency plans, and arranged specially-assigned persons to inspect and remove potential fire hazards periodically so as to prevent from forest fire. (VI) Upon completion of any works, carry out vegetation rehabilitation in time, used natively-distributed birches, Chinese red pines, alders and other plants for vegetation restoration, while forbidding the use of exotic species. (VII) During construction and operation of the project, according to the ecological monitoring data, post-impact assessment report and the like,

18 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

further reinforced and perfected pertinent impact reduction and ecological protection measures. The disaster prevention, rescue and evacuation works of Zizhuyuan tunnel had been put into official operation in 2016. Photo 3. Reply of Sichuan Provincial Agricultural Department for Disaster Prevention, Rescue & Evacuation Project of Zizhuyuan Tunnel of Lanzhou~Chongqing Railway to Run through Sichuan Maozhai Pilot Nature Reserve 4.1.2 Water and Soil Conservation The field inspection shows, in the scope of this acceptance test, totally 2 borrow pits and 64 spoil grounds (areas) are investigated along the entire line, which have been rehabilitated and gone through the hand-over formalities; totally 37 mixing stations, 136.7km of construction roads, 33hm2 of land occupied by the project and 48.9 hm2 of land temporarily occupied as construction camps are invested, which are rehabilitating the landforms successively and going through relevant hand-over formalities; totally 41.1 hm2 of the slopes and both sides of roadbeds has been afforested. Photo 4. Exit of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I Photo 5. The spoil area for 3# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has been constructed with retaining wall and already restored as farmland. Photo 6. The spoil area for 3# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has been constructed with flood drainage trench and already restored as farmland. Photo 7. The spoil area for 4# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has been constructed with flood drainage trench and already restored as farmland. Photo 8. Small bridge over the flood drainage trench for 4# inclined shaft spoil

19 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

area of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I Photo 9. The spoil area for 5# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has been constructed with flood drainage trench and already restored as farmland. Photo 10. The spoil area at the outlet of of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has already been restored as farmland. Photo 11. The spoil area at the inlet of Jutou Tunnel of China Railway No.19 Bureau in Bid Section I has already been restored as farmland. Photo 12. The spoil area at the inlet of Yangjiawan Tunnel of China Railway No.16 Bureau in Bid Section II has been constructed with retaining wall and already restored as farmland. Photo 13. The spoil area at the inlet of Yangjiawan Tunnel of China Railway No.16 Bureau in Bid Section II has been constructed with drain and planted with trees and already restored as farmland. Photo 14. The spoil area at the outlet of Yangjiawan Tunnel of China Railway No.16 Bureau in Bid Section II has been constructed with drain and divided into two levels of steps and already restored as farmland. Photo 15. After delivery, the spoil area at the outlet of of Kezhai Tunnel of China Railway No.16 Bureau in Bid Section II is occupied by Lintao~Weiyuan Expressway as permanent construction land. Photo 16. Daping trackless spoil area for Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall and drain and presently is used as construction camp of the Expressway project. Photo 17. Daping track-section spoil area for Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III had been constructed with retaining wall and now is used as construction camp of the Expressway project.

20 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

Photo 18. The spoil area for south drainage ditch of Muzhailing tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall and the side slope has been divided into four levels of steps and already restored as forest land and planted with trees. Photo 19. The newly-built Luzha spoil area of Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall and the side slope has been divided into four levels of steps and already afforested. Now houses have been built for the Expressway project. Photo 20. The Luzha spoil area of Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall and the side slope has been divided into three levels of steps and already afforested. Some work sheds have been built there for the Expressway project. Photo 21. Dagouzhuang spoil area for Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall and the side slope has been divided into three levels of steps and already afforested. Photo 22. Dazhangou spoil area for Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall and the side slope has already been afforested. Photo 23. The spoil area at the outlet of of Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall, and most of wasted soil is transported away for reuse. Some resident houses are built there. Photo 24. The spoil area at the inlet of Guzishan Tunnel of China Railway No.7 Bureau in Bid Section II has been constructed with retaining wall, and the side slope has been divided into 5 steps and the land there is already restored as farmland.

21 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

Photo 25. The camp for 3# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has been rehabilitated and now is going through the delivery formalities. Photo 26. The mixing station for 3# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has been rehabilitated and delivered. Photo 27. The camp for 4# inclined Shaft for Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has already been restored as farmland and already delivered. Photo 28. The camp for 5# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has already been restored as farmland and already delivered. Photo 29. The construction roads for 3# and 5# inclined shafts of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I is being restored as farmland. Photo 30. The camp at the inlet of Jutou Tunnel of China Railway No.19 Bureau in Bid Section I has been restored as farmland and already delivered. Photo 31. The mixing station at the inlet of Jutou Tunnel of China Railway No.19 Bureau in Bid Section I has been restored as farmland and already delivered. Photo 32. The sites of the camp and mixing station for 6# inclined shaft of Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III have been restored as farmland.

4.2 Implementation of Pollution Control Measures

4.2.1 Noise and Vibration Control Measures (1) Noise barrier Stage of environment impact assessment: This section has set up 6 noise barriers (totally 4,300 linear meters and 12,262.5m2).

22 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

Stage of construction drawing: Due to routine and position adjustment of railway or resettlement of sensitive protective objects, in the construction drawing stage of this acceptance test, totally 8 noise barriers (totally 3,935 linear meters and 9,682.5m2) are planned. 5 noise barriers for the stage of environment impact assessment are canceled (for the purpose to routine and position detouring) and 7 noise barriers (3,145 linear meters) are newly added (new sensitive points of changed section). The field investigation results show that 8 noise barriers (totally 3,935 linear meters and 9,682.5m2) have completed the construction drawings. Photo 33. The noise barrier for K136+211~k136+411 of China Railway No. 16 Bureau in Bid Section II has been completed, beside which is Weiyuan

County Vocational School. (2) Acoustic window Stage of environment impact assessment: This section sets up 10,650m2 of acoustic window in total. Stage of construction drawing: This section sets up 5830m2 of acoustic window in total. Actual completion: This section has actually completed 5830m2 of acoustic window. (3) Vibration Prevention and Control, Functional Displacement and Resettlement Required in environment impact assessment report: Within the scope of this acceptance test, functional displacement is conducted for 2 sensitive points in Liujiaju Village in the City of Dingxi (totally 9 households). Actual completion: The vibration prevention and control measures are incorporated into the resettlement or functional displacement of the whole line, and totally 266 households (24,967m2 in total) of residents within 30 meters apart from the boundary of the land used by this project are relocated. 4.2.2 Electromagnetic protection measures Requirements in environment impact assessment report: Within the scope of this

23 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017 acceptance, 4 traction substations (Zhangjiazhuang, Yangjiachuan, Weiyuan and Dacaotan) are set. Actual completion: The field inspection shows that 4 new 220kV traction substations (Zhangjiazhuang, Yangjiachuan, Weiyuan and Zhang County Station) are built, and there are no residential houses distributed within 30m apart from the fences of these traction substations. 4.2.3 Water Pollution Abatement Measures Requirements in environment impact assessment report: The domestic wastewater from Zhangjiazhuang Station should be drained into nearby ditches and trenches after having been treated in the septic tank and anaerobic treatment facilities and then into Wanchuan River; The domestic wastewater from Yangjiachuan Station should be drained into Qiaoyu River after having been treated in the septic tank and land-based treatment system and then into Weihe River; The domestic wastewater from Weiyuan Station should be drained into Qiaoyu River after having been treated in the septic tank and land-based treatment system and then into Weihe River; The domestic wastewater from Dacaotan Station (Zhang County Station) should be drained into Zhanghe River after having been treated in the septic tank and MBR treatment system. Actual situation: The domestic wastewater from Zhangjiazhuang Station, Yangjiachuan Station and Weiyuan Station of this project is drained into nearby ditches and trenches after being treated in the land-based treatment system, and that from Zhang County Station (Dacaotan Station) is drained into the municipal wastewater system. All these wastewater treatment systems have been completed. 4.2.4 Air Pollution Abatement Measures Requirements in environment impact assessment report: Within the scope of this acceptance test, five 0.35MW vertical coal-fired boilers and one 0.7MW vertical coal-fired boiler are newly built for environmental protection purpose. Actual situation: This project has no coal-fired boiler, and the heating facilities

24 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017 of Zhangjiazhuang Station, Yangjiachuan Station, Weiyuan Station and Zhang County Station use air-sourced heat pump systems. 4.2.5 Treatment and Disposal Measures of Solid Wastes Garbage from passenger train and household garbage of station staff shall be designated collected and be unified removed. After being equipped with trash collection in station and waiting room, the garbage shall be unified treated by local sanitation department. In brief, the environmental protection and water conservation measures have been basically implemented. As for the existing problems, the problem library and rectification measures and completion time have been provided in the static acceptance report and have been signed to confirm by Lanzhou Railway Bureau, Lanzhou-Chongqing Railway Co., Ltd., design unit FSDI, project constructor, project supervision unit, the environmental protection acceptance unit China Railway Fifth Survey and Design Institute Group Co., Ltd, water conservation monitoring unit Gansu Lvhua Ecological Company and so on.

5. Photos

1. Static Acceptance Report for Environmental Protection and Water & Soil Conservation Project of Newly Built Lanzhou ~ Chongqing Railway (K41+759.928~k221+393 )

25 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

2. Reply of Gansu Provincial Agricultural and Pastoral Department to the Evaluation Report on Impacts of Lanzhou-Chongqing Railway on Provincial Natural Reserve of Zhang County for Brachymytax Lenoks (Presently the Zhang County National Nature Reserve for Rare Aquatic Lives)

3. Reply of Sichuan Provincial Agricultural Department for Disaster Prevention, Rescue & Evacuation Project of Zizhuyuan Tunnel of Lanzhou~Chongqing Railway to Run through Sichuan Maozhai Pilot Nature Reserve

4. Exit of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I

26 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

5. The spoil area for 3# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has been constructed with retaining wall and already restored as farmland.

6. The spoil area for 3# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has been constructed with flood drainage trench and already restored as farmland.

7. The spoil area for 4# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has been constructed with flood drainage trench and already restored as farmland.

27 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

8. Small bridge over the flood drainage trench for 4# inclined shaft spoil area of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I

9. The spoil area for 5# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has been constructed with flood drainage trench and already restored as farmland.

10. The spoil area at the outlet of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has already been restored as farmland.

28 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

11. The spoil area at the inlet of Jutou Tunnel of China Railway No.19 Bureau in Bid Section I has already been restored as farmland.

12. The spoil area at the inlet of Yangjiawan Tunnel of China Railway No.16 Bureau in Bid Section II has been constructed with retaining wall and already restored as farmland.

13. The spoil area at the inlet of Yangjiawan Tunnel of China Railway No.16 Bureau in Bid Section II has been constructed with drain and planted with trees and already restored as farmland.

29 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

14. The spoil area at the outlet of Yangjiawan Tunnel of China Railway No.16 Bureau in Bid Section II has been constructed with drain and divided into two levels of steps and already restored as farmland.

15. After delivery, the spoil area at the outlet of Kezhai Tunnel of China Railway No.16 Bureau in Bid Section II is occupied by Lintao~Weiyuan Expressway as permanent construction land.

16. Daping trackless spoil area for Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall and drain and presently is used as construction camp of the Expressway project.

30 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

17. Daping track-section spoil area for Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall and now is used as construction camp of the Expressway project.

18. The spoil area for south drainage ditch of Muzhailing tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall and the side slope has been divided into four levels of steps and already restored as forest land and planted with trees.

19. The newly-built Luzha spoil area of Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall and the side slope has been divided into three levels of steps and already afforested. Now houses have been built for the Expressway project.

31 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

20. The Luzha spoil area of Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall and the side slope has been divided into three levels of steps and already afforested. Some work sheds have been built there for the Expressway project.

21. Dagouzhuang spoil area for Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall and the side slope has been divided into three levels of steps and already afforested.

22. Dazhangou spoil area for Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall and the side slope has already been afforested.

32 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

23. The spoil area at the outlet of Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III has been constructed with retaining wall, and most of wasted soil is transported away for reuse. Some resident houses are built there.

24. The spoil area at the inlet of Guzishan Tunnel of China Railway No.7 Bureau in Bid Section II has been constructed with retaining wall, and the side slope has been divided into 5 steps and the land there is already restored as farmland.

25. The camp for 3# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has been rehabilitated and now is going through the delivery formalities.

33 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

26. The mixing station for 3# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has been rehabilitated and delivered.

27. The camp for 4# inclined Shaft for Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has already been restored as farmland and already delivered.

28. The camp for 5# inclined shaft of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I has already been restored as farmland and already delivered.

34 Environment Monitoring Report on New Lanzhou-Chongqing Railway Development Project in 2017

29. The construction roads for 3# and 5# inclined shafts of Humaling Tunnel of China Railway No.19 Bureau in Bid Section I is being restored as farmland.

30. The camp at the inlet of Jutou Tunnel of China Railway No.19 Bureau in Bid Section I has been restored as farmland and already delivered.

31. The mixing station at the inlet of Jutou Tunnel of China Railway No.19 Bureau in Bid Section I has been restored as farmland and already delivered.

35 Environment Monitoring Report on Newly-built Lanzhou-Chongqing Railway in 2017

32. The sites of the camp and mixing station for 6# inclined shaft of Muzhailing Tunnel of China Railway Tunnel Group in Bid Section III have been restored as farmland.

33. The noise barrier for K136+211~k136+411 of China Railway No. 16 Bureau in Bid Section II has been completed, beside which is Weiyuan County Vocational School.