The World Bank Implementation Status & Results Report Transmission Grid Strengthening Project (P147348)
Transmission Grid Strengthening Project (P147348)
EUROPE AND CENTRAL ASIA | Georgia | Energy & Extractives Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 11 | ARCHIVED on 16-Feb-2021 | ISR44802 | Public Disclosure Authorized
Implementing Agencies: Ministry of Finance, Ministry of Economy and Sustainable Development, Georgian State Electrosystem
Key Dates
Key Project Dates
Bank Approval Date: 13-May-2014 Effectiveness Date: 29-Dec-2014 Planned Mid Term Review Date: 03-Apr-2017 Actual Mid-Term Review Date: 21-Jun-2017 Original Closing Date: 31-Mar-2019 Revised Closing Date: 01-Mar-2021 pdoTable
Project Development Objectives Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) The project development objectives are to provide reliable power transmission to the southwestern part of the grid, upgrade electricity exchange systems, and provide economically efficient, environmentally and socially sustainable electricity sector planning.
Has the Project Development Objective been changed since Board Approval of the Project Objective? No
Components Table
Name Component 1. Transmission System Strengthening:(Cost $52.35 M) Component 2. Wholesale Power Exchange Platform:(Cost $6.00 M) Component 3. Electricity Sector Strategic Environmental and Social Assessment:(Cost $1.00 M) Public Disclosure Authorized Component 4. Project Management and Transmission Systems Studies:(Cost $0.50 M)
Overall Ratings
Name Previous Rating Current Rating
Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate
Implementation Status and Key Decisions
Component 1 of the Project finances major transmission infrastructure, Akhaltsikhe-Batumi double circuit overhead 220kV transmission line (ABT). Segment 2 of the ABT line is completed. Completion of the Segment 1 is delayed. Segment 2 is 52 km long. It connects Batumi high voltage substation with Shuakhevi hydropower station. As Segment 2 is Public Disclosure Authorized completed, the hydropower plant was connected to the national grid and started supply electricity. Segment I is about 93 km long. It connects the Shuakhevi hydropower station with Akhaltsikhe high voltage substation. Out of the three parts of this segment, Parts 1 and 2 are substantially completed. The works have not started on Part 3 because of the contractual issues. Those issues are being resolved and the construction is expected to commence by June 2021.
2/16/2021 Page 1 of 6 The World Bank Implementation Status & Results Report Transmission Grid Strengthening Project (P147348)
Component 2 of the Project finances upgrade of the Supervisory Control and Data Acquisition (SCADA) system and the preparation of the metering system for the new, day-ahead electricity trading. The SCADA has been upgraded and the readiness of the GSE's metering system for day-ahead electricity trading has been assessed. Component 3 of the Project, Electricity Sector Strategic Environmental and Social Assessment, finances preparation of the Strategic Environmental and Social Assessment (SESA) of Georgia's electricity sector development scenarios. The preparation of the SESA is being finalized.
Risks
Systematic Operations Risk-rating Tool
Risk Category Rating at Approval Previous Rating Current Rating
Political and Governance -- Low Low Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Low Low Technical Design of Project or Program -- Low Low Institutional Capacity for Implementation and -- Low Low Sustainability Fiduciary -- Low Low Environment and Social -- High High Stakeholders -- Moderate Moderate Other -- -- Substantial Overall -- Moderate Moderate
Results
PDO Indicators by Objectives / Outcomes
Provide reliable power transmission to the southwestern part of the grid
IN00932342 ►Total duration of outages in Batumi substation (Hours, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 136.00 0.00 0.00 0.50
Date 01-Jun-2014 31-Dec-2019 31-Dec-2020 01-Mar-2021
The reported outages are for the year 2020 Comments:
IN00932343 ►Total electricity evacuated from the newly developed power generation stations in southwestern Georgia through the grid (Gigawatt-hour (GWh), Custom)
2/16/2021 Page 2 of 6 The World Bank Implementation Status & Results Report Transmission Grid Strengthening Project (P147348)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 0.00 258.40 400.00
Date 31-Dec-2013 31-Dec-2019 31-Dec-2020 01-Mar-2021 Segment II of the ABT line has been completed which connected Shuakhevi hydropower station with the grid. The power station has started commercial generation in February 2020 therefore, the annual Comments: generation target was not achieved.
IN00932344 ►Transmission lines constructed or rehabilitated under the project (Kilometers, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 154.40 154.40 244.00
Date 01-Mar-2016 31-Dec-2019 31-Dec-2020 01-Mar-2021 This includes 52.4 km Segment II of the ABT line and three rehabilitated lines with length of 15 km, 21 km, Comments: and 66 km connecting substations Kutaisi Tsklatubo, Kutaisi Zestaphoni, Kutaisi Menji respectively.
IN00932345 Transmission lines rehabilitated under the project (Kilometers, Custom Breakdown)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 102.00 102.00 102.00
Date 01-Mar-2016 31-Dec-2019 31-Dec-2020 01-Mar-2021
IN00932346 Transmission lines constructed under the project (Kilometers, Custom Breakdown)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 52.40 52.40 142.00
Date 01-Mar-2016 31-Dec-2019 31-Dec-2020 01-Mar-2021
Upgrade electricity exchange systems
IN00932335 ►Power is exchanged (traded) using new exchange platform (Yes/No, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value No No No Yes
Date 31-Dec-2013 31-Dec-2019 31-Dec-2020 01-Mar-2021
Provide economically efficient, environmentally and socially sustainable electricity sector planning
IN00932341 ►The results of the least cost planning and strategic environmental assessment have been incorporated into the Government?s hydropower development plan (Yes/No, Custom)
Baseline Actual (Previous) Actual (Current) End Target
2/16/2021 Page 3 of 6 The World Bank Implementation Status & Results Report Transmission Grid Strengthening Project (P147348)
Value No No No Yes
Date 31-Dec-2013 31-Dec-2019 31-Dec-2020 01-Mar-2021 No Citizen Engagement has been carried out because the results of the strategic environmental Comments: assessment are not available
Intermediate Results Indicators by Components
Component 1. Transmission System Strengthening
IN00932347 ►Section from Shuakhevi to Batumi transmission line constructed (Kilometers, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 52.40 52.40 52.00
Date 31-Dec-2013 31-Dec-2019 31-Dec-2020 01-Mar-2021 The final, as constructed length of the Segment II from Shuakhevi hydropower station to Batumi Comments: substation has been identified as 52.4 km.
IN00932350 ►Kutaisi Zestaphoni 220 kV line upgraded (Kilometers, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 21.00 21.00 21.00
Date 30-Apr-2016 31-Dec-2019 31-Dec-2020 01-Mar-2021
IN00932352 ►Tskaltubo Kutaisi 220 kV line upgraded to double circuit (Kilometers, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 15.00 15.00 15.00
Date 30-Apr-2016 31-Dec-2019 31-Dec-2020 01-Mar-2021
IN00932353 ►Menji Kutaisi line rehabilitated (Kilometers, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 66.00 66.00 66.00
Date 30-Apr-2016 31-Dec-2019 31-Dec-2020 01-Mar-2021
Component 2. Wholesale Power Exchange Platform
IN00932348
2/16/2021 Page 4 of 6 The World Bank Implementation Status & Results Report Transmission Grid Strengthening Project (P147348)
►Wholesale power exchange systems updated (Yes/No, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value No No No Yes
Date 31-Dec-2013 31-Dec-2019 31-Dec-2020 01-Mar-2021
IN00932351 ►SCADA/EMS updated (Yes/No, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value No No Yes Yes
Date 30-Apr-2016 31-Dec-2019 31-Dec-2020 01-Mar-2021
Component 3. Electricity Sector Strategic Environmental and Social Assessment
IN00932349 ►Strategic Environmental Impact Assessment prepared based on the feedback from all stakeholders (Yes/No, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value No No No Yes
Date 31-Dec-2013 31-Dec-2019 31-Dec-2020 01-Mar-2021
Performance-Based Conditions
Data on Financial Performance
Disbursements (by loan)
Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed
P147348 IBRD-83770 Effective USD 60.00 60.00 0.00 50.54 9.46 84%
Key Dates (by loan)
Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date
P147348 IBRD-83770 Effective 13-May-2014 03-Sep-2014 29-Dec-2014 31-Mar-2019 01-Mar-2021
Cumulative Disbursements
2/16/2021 Page 5 of 6 The World Bank Implementation Status & Results Report Transmission Grid Strengthening Project (P147348)
PBC Disbursement
Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC
Restructuring History
Level 2 Approved on 28-Jul-2016 ,Level 2 Approved on 13-Mar-2019
Related Project(s)
There are no related projects.
2/16/2021 Page 6 of 6