Triton Knoll Offshore Limited Triton Knoll Electrical System

Comparison Outline Access Management Plan (Revision A to Revision B)

April February 20162015

Appendix 13 of the Applicant’s response to Deadline 6 Document Reference: 8.13

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

Triton Knoll Offshore Wind Farm Limited www.rweinnogy.com/tritonknoll

Triton Knoll Electrical System

Comparison Outline Access Management Plan (Revision A to Revision B) LIABILITY Appendix 13 of the Applicant’s In preparation of this document Triton response to Deadline 6Document Knoll Offshore Wind Farm Limited Reference: 8.13 (TKOWFL) and their subconsultants have made reasonable efforts to April February 20162015 ensure that the content is accurate, up to date and complete for the purpose for which it was prepared. Neither Drafted By: RWE TKOWFL nor their subcontractors make any warranty as to the accuracy Approved By: Paul Carter or completeness of material supplied. Date of Approval 08.04.15February Other than any liability on TKOWFL or 2016 their subcontractors detailed in the contracts between the parties for this Revision 00B work neither TKOWFL or their subcontractors shall have any liability

for any loss, damage, injury, claim, Triton Knoll Offshore Wind Farm Ltd expense, cost or other consequence Trigonos arising as a result of use or reliance Windmill Hill Business Park upon any information contained in or Whitehill Way omitted from this document. Swindon SN5 6PB Copyright © 2015 Triton Knoll Offshore Wind Farm Limited T 0845 026 0562 All pre-existing rights reserved. Email: tritonknoll@.com I www.rweinnogy.com

i

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

Table of Contents

1 INTRODUCTION ...... 1 Overview ...... 1 The Applicant ...... 1 Project Overview ...... 1 Purpose of this Outline Plan...... 2 Scope of this Outline Plan ...... 2 2 TEMPORARY CONSTRUCTION ACCESS ...... 3 Temporary Construction Compounds ...... 3 Road Crossings ...... 6 3 PERMANENT ACCESS ...... 8

ii

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

Figures Figure 3.1: TCC locations ...... 9 Figure 3.2: Indicative Construction access layout – TCC 1 landfall ...... 10 Figure 3.3: Indicative Construction access layout – TCC 5 A158 (to IEC) ...... 11 Figure 3.4: Indicative Construction access layout – TCC 24a/24b A17 (substation) .. 12 Figure 3.5: Indicative Construction access layout – Typical layout for A roads ...... 13 Figure 3.6: Indicative Construction access layout – Typical layout for other roads .... 14 Figure 3.7: Road crossing locations ...... 15 Figure 3.8: Indicative Construction access layout – Typical haul road crossing ...... 16 Figure 4.1: Indicative Permanent access layout – Intermediate Electrical Compound 17 Figure 4.2: Indicative Permanent access layout – Substation ...... 18

Tables Table 1: Temporary Construction Compound Indicative Access Drawings ...... 5

iii

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

Glossary

Term Definition

Authorised The development and associated development described in Part 1 development of Schedule 1 (authorised development) and any other development authorised, which is a development within the meaning of section 32 of the Planning Act

Authorised project The authorised development and the ancillary works authorised by a Development Consent Order..

Cable ducts Conduits for the installation of cables.

Environmental The document that sets out the results of the environmental impact Statement assessment (EIA) for the proposed scheme.

Highway / They both have the same meaning as in the 1980 Act. Highway Highway Authority authority for the relevant area.

IEC enabling In relation to Work No. 9 (in the draft Development Consent works Order),site clearance; the establishment of temporary working areas; temporary fencing; the installation of construction haul roads; ground works including the installation of cabling ducting and the relocation and installation of below ground utilities and drainage; ground raising and establishment of stoned site platform.

Intermediate The area containing a building housing switchgear, busbars, Electrical capacitors, reactors, reactive power compensation equipment, Compound (IEC) filters, cooling equipment, control and welfare buildings, lightning rods (if required), internal roads, security fencing and other associated equipment, structures and buildings including noise attenuation works.

Onshore Works Works No. 2 to 54 (in the draft Development Consent Order) and any related further associated development in connection with those works, including, in relation to cable laying, jointing bays, manholes, marker posts and other works associated with cable laying.

Order Limits The limits shown on the Order Limits plans within which the authorised project may be carried out.

Outline traffic The document certified as the outline traffic management plan by management plan the Secretary of State for the purposes of this Order.

iv

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

Unlicensed Works Unlicensed works are electrical works needed to connect Triton Knoll to the National Grid substation at Bicker Fen that National Grid is not required pursuant to its transmission licence to carry out itself

Relevant planning The district planning authority for the area in which the land to authority which the relevant provision of the development applies is situated

Statutory Any person falling within section 127(8), 128(5) or 129(2) of the Undertaker Planning Act 2008

Street A street within the meaning of section 48 of the New Roads and Street Works Act 1991, together with land on the verge of a street or between two carriageways, and includes part of a street.

Substation A compound containing switchgear and electrical equipment including power transformers, switchgear, reactive compensation equipment, filters, cooling equipment, control and welfare buildings, lightning rods (if required), internal roads, security fencing and other associated equipment, structures and buildings including noise attenuation works.

Substation In relation to Work No 49 (In the draft Development Consent Order, enabling works site clearance; the establishment of temporary working areas; temporary fencing; the installation of construction haul roads; ground works including the installation of cabling ducting and the relocation and installation of below ground utilities and drainage; ground raising and establishment of stoned site platform

Temporary A temporary construction site compound associated with the Construction electrical works including hard standings, lay down and storage Compound areas for construction materials and equipment, areas for spoil, areas for vehicular parking, bunded storage areas, areas for welfare facilities including offices and canteen and washroom facilities, workshop facilities and temporary fencing or other means of enclosure and areas for other facilities required for construction purposes.

The requirements The necessary requirements that must be carried out by the Undertaker as part of the draft Development Consent Order.

Transition jointing Houses the connection between the offshore cables and the bay onshore cables.

Trenchless An alternative methodology of cable installation to cross significant Technique environmental and physical features such as main rivers, major

v

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

drains, main roads and railways.

Undertaker Triton Knoll Offshore Wind Farm Limited

Works Plan The plan certified as the works plan by the Secretary of State for the purposes of the Order.

vi

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

1 INTRODUCTION

Overview

1.1 Triton Knoll Offshore Wind Farm Limited (TKOWFL) is submitting an application to the Planning Inspectorate (PINS), on behalf of the Secretary of State for Energy and Climate Change, for a Development Consent Order (DCO) for the Triton Knoll Electrical System (the proposed development) under the Planning Act 2008. The Triton Knoll Electrical System (TKES) would connect the consented Triton Knoll Offshore Wind Farm (TKOWF) offshore array to the existing National Grid substation at Bicker Fen, Boston. 1.2 The TKOWF is located approximately 33km (20.5 miles) east of the coast. The Secretary of State granted a DCO for the TKOWF offshore array on 12th July 2013. 1.3 All terms, acronyms and abbreviations used within this outline plan are explained on first use, and / or set out in full within the Glossary appearing in the Environmental Statement - document reference 6.2.1.

The Applicant

1.4 TKOWFL is a joint venture between two leading international energy companies; RWE Innogy and Statkraft. RWE Innogy UK Ltd is the UK subsidiary of the German renewable energy company RWE Innogy (part of RWE AG), a company with a strong and diversified position in renewable energy development. Statkraft is Europe’s largest generator of renewable energy and is the leading power company in Norway.

Project Overview

1.5 The components of the TKES, which are needed to connect TKOWF to the National Grid, comprise:  Up to six offshore export cable circuits – to transmit the high voltage alternating current (HVAC) electricity from the offshore substations to the transition joint bays at the landfall;  Landfall infrastructure just north of , Lincolnshire – including transition joint bays which house the connection between the offshore cables and the onshore cables;

1

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

 Up to six onshore export cable circuits (up to 220 kV) – to transmit the HVAC electricity from the transition joint bays at the landfall to the Substation via the Intermediate Electrical Compound;  An Intermediate Electrical Compound near to Orby Marsh – to provide compensation for reactive power to allow more efficient transmission to minimise losses;  A substation near the existing Bicker Fen National Grid Substation – to step-up the voltage to the voltage used by the National Grid and provide additional compensation for reactive power built up over the export transmission;  Up to four onshore export cable circuits (400 kV) – to transmit the electricity from the proposed Triton Knoll Substation to the existing National Grid substation at Bicker Fen, Boston; and  Unlicensed Works within the existing National Grid Bicker Fen substation compound comprising up to two new ‘connection bays’ of electrical equipment required to connect the Electrical System to the National Grid. 1.6 The onshore Proposed Development Boundary for the Triton Knoll Electrical System is shown on the Works Plans( Application Document 2.1 and Figure 1.1 of Vol 3 Chapter 1: Onshore Project Description Application Document 6.2.3.1). Purpose of this Outline Plan

1.7 This outline Access Management Plan (AMP) forms part of the application for a DCO for the TKES and has been allocated application document reference 8.13 by TKOWFL. 1.8 This outline AMP is being provided in an indicative form to provide the Examining Authority and parties to the examination with an outline of the AMP to be submitted for any stage of the TKES in accordance with requirement 8 of the proposed DCO. 1.9 Its purpose is to provide outline proposals for access to the TKES for construction and operational purposes.

Scope of this Outline Plan

1.10 This outline plan relates to the onshore elements of the TKES for the proposed TKOWF, which include all construction access points to the cable

2

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

route and permanent access to the Intermediate Electrical Compound and Triton Knoll Substation. 2 TEMPORARY CONSTRUCTION ACCESS

Temporary Construction Compounds

2.1 Access to the cable route landfall, IEC and substation will be via the 26 Temporary Construction Compounds (TCCs) located along the Onshore Cable Route. These are illustrated on Figure 3.1 and will be accessed from the existing highways network. Access to a TCC will be designed to accommodate all types of vehicle required for that section of the works, including heavy goods vehicles (HGV’s) and any abnormal indivisible loads (AILs) required. 2.2 This outline plan identifies the location and indicative layout of the temporary access arrangements for each TCC. The drawings enclosed within this report relate to key locations along the route, together with generic layouts for the remaining accesses depending on the category of road that these TCCs will be accessed from, as summarised below:  Landfall;  Intermediate Electrical Compound;  Triton Knoll Substation;  Typical access from A road; and  Typical access from other roads. 2.3 Prior to construction, detailed layouts for each TCC would be confirmed by the Principal Contractor and agreed with the Highway Authority. Details of the access design will include the following areas:  Access point construction (i.e. crushed type 1 stone laid over terram membrane);  Fluming arrangements for any ditches at the side of the road;  Assessment of visibility splays at the access point and any mitigation required;  Extent of road-sweeping activity in vicinity of access point;  Construction routing for approaching and departing the site access;  Any temporary control measures to be applied to construction traffic using the access point (i.e. temporary speed limits); and

3

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

 Schedule of temporary signage to be used, and its location at the access and on the approach routes, in accordance with Chapter 8 of the Traffic Signs Manual (Traffic Safety Measures and Signs for Road Works and Temporary Situations, Part 1 Design, 20091),. 2.4 Draft outline drawings illustrating the potential layout of the temporary access arrangements for the above locations are provided at Figures 3.2-3.6. The ES assesses a worst case scenario for removal of vegetation to facilitate visibility at TCC accesses. In practice, removal of trees and hedgerows would be unlikely to be the first option for vegetation clearance, and alternatives such as hedgerow coppicing would be considered. If these measures were insufficient, traffic management measures would also be considered to ensure safety of access e.g. use of banksmen, temporary reductions in speed limit or temporary traffic lights. 2.5 The layout for each individual TCC access onto the public highway should be designed for the current level of traffic flows along the TCC frontage, as agreed with the relevant highway authority taking into account traffic flows from the committed developments, and the predicted level of turning movements and sizes of vehicles required to use the TCC during the construction period. The access design and layout should be produced in accordance with the ‘Design Manual for Roads and Bridges’ and the Highway Authority’s requirements. 2.6 The typical access arrangements provided for the TCC sites illustrate how they would accommodate all sizes of vehicles required to deliver specialist equipment and materials to the TCCs. 2.7 All TCC access arrangements would be designed to accommodate two-way traffic and, where appropriate, provide for standing vehicles clear of the through carriageway, sufficient to mitigate queuing on the highway. 2.8 The following table identifies the relevant outline access drawing appropriate to each TCC:

1 https://www.gov.uk/government/publications/traffic-signs-manual

4

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

Table 1: Temporary Construction Compound Indicative Access Drawings Temporary Construction Temporary Construction Indicative Access Compound Compound Locations Layout Drawing (TCC) Figure 3.2 – TCC 1: TCC 1 Landfall Landfall Figure 3.5 – Access TCC 2 North side of A52 from A Road Figure 3.5 – Access TCC 3 South side of A52 from A Road

TCC 4 Intermediate Electrical Compound (Accessed via TCC 5)

Figure 3.3 – TCC 5: TCC 5 North side of A158 A158 / Intermediate Electrical Compound Figure 3.5 – Access TCC 6 South side of A158 from A Road East side of Railway (south of Figure 3.6 – Access TCC 7 Lymn Bank Crossing) from other roads Figure 3.6 – Access TCC 8 West side of Steeping River from other roads Figure 3.6 – Access TCC 9 South side of Thorpe Bank from other roads Figure 3.6 – Access TCC 10 East side of Hobhole Bank from other roads Figure 3.6 – Access TCC 11 North side of Fodder Dike from other roads Figure 3.5 – Access TCC 12 East side of A16 from A Road Figure 3.5 – Access TCC 13 West side of A16 from A Road Figure 3.6 – Access TCC 14 West side of Staunt Road from other roads Figure 3.6 – Access TCC 15 East side of Carrington Road from other roads TCC 16 North side of Leagate Road Figure 3.6 – Access

5

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

Temporary Construction Temporary Construction Indicative Access Compound Compound Locations Layout Drawing (TCC) from other roads

Figure 3.6 – Access TCC 17 North side of Mere Booth Road from other roads Figure 3.6 – Access TCC 18 South side of Mere Booth Road from other roads North side of North Forty Foot Figure 3.6 – Access TCC 19 Bank from other roads Figure 3.6 – Access TCC 20 North side of Sutterton Drove from other roads Figure 3.6 – Access TCC 21 West side of Claydike Bank from other roads Figure 3.5 – Access TCC 22 North Side of A17 from A Road Figure 3.5 – Access TCC 23 South side of A17 from A Road Figure 3.4 – TCC TCC 24a/TCC At entrance from A17 to new 24a/24b: Triton Knoll 24b access track to substation Substation (Accessed via TCC TCC 25 Triton Knoll Substation 24a/24b) Adjacent to Unlicensed Works area (Accessed via TCC TCC 26 at National Grid Bicker Fen 24a/24b) Substation

2.9 Finalised drawings, showing the full detail of access improvements, including measures to ensure safe access from the highway onto the Onshore Cable Route via the TCC locations, would be agreed as part of the detailed AMP through consultation with the Highway Authority as part of a section 184 Agreement..

Road Crossings

2.10 The Onshore Cable Route will cross public roads at a number of locations where a TCC is not proposed to be constructed, as illustrated at Figure 3.7. In these locations, HGVs will only cross the road while non-HGV traffic may

6

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

enter and exit the construction site. Methods of management of construction vehicles at each road crossing will be agreed within the Traffic Management Plan. 2.11 Draft outline drawings illustrating the typical layout of the temporary access arrangements for the above locations are provided at Figure 3.8. 2.12 Finalised drawings, showing the full detail of access improvements, including traffic management measures to ensure safe access across the highway between sections of the Onshore Cable Route, would be agreed as part of the detailed AMP through consultation with the Highway Authority.

7

Triton Knoll Offshore Wind Farm Ltd Triton Knoll Electrical System

3 PERMANENT ACCESS

3.1 The Intermediate Electrical Compound and Substation will require permanent access for regular maintenance purposes. The location of these is illustrated on Figure 3.1 and would be accessed from the existing highways network. 3.2 This AMP identifies the location and layout of each of the permanent access arrangements. Prior to construction, detailed layouts for each access would be confirmed by the Principal Contractor and agreed with the Highway Authority as part of a section 278 Agreement. TKOWFL will subsequently carry out the works under the DCO. 3.3 Draft outline drawings illustrating the layout of the proposed permanent access arrangements for the Intermediate Electrical Compound and Triton Knoll Substation are provided at Figures 4.1 and 4.2. 3.4 The layout for each individual TCC access onto the public highway should be designed in accordance with the ‘Design Manual for Roads and Bridges’ and the Highway Authority’s requirements. The drawings also illustrate how each access would accommodate all sizes of vehicles required to deliver specialist equipment and materials. 3.5 Finalised drawings showing the full detail of permanent access arrangements would be agreed as part of the detailed AMP through consultation with the Highway Authority.

8

510000 520000 530000 540000 550000 560000 570000

Legend:

Proposed Development Boundary Administrative Boundary (District / Borough) 0

0 Temporary Construction Compound 0 ! 0

8 (TCC) 3 TCC 1 Total Area of Land Required for the West Substation Compound, Underground Lindsey ! " Cabling, Permanent and Temporary Access Tracks and Drainage and District Landscape Mitigation Total Area of Land Required for the Intermediate Electrical Compound, TCC 2 " Permanent and Temporary Access ! Tracks, Underground Cabling and ! Drainage and Landscape Mitigation TCC 3 0 0 0 0 7 3

"! East Lindsey TCC 4 District !! TCC 5 TCC 6 TCC 7 TCC 8 ! ! 0 ! 0

0 TCC 9 0 6 3 TCC 10

! !

TCC 11 TCC 12 Coordinate System: British National Grid d

Projection: Transverse Mercator x

North !! m Datum: OSGB 1936 . 0

Units: Meter 1 4

Kesteven TCC 13 0 TCC 15 5 ! 1 0 2

District TCC 14 _ s n o i TCC 16 ! t a c 0 o 0 L 0 _

0 TCC 18 C 5 3 C T

Source: Global Land Cover Facility, www.landcover.org. _ TCC 19 S

! E \

! S ! I G

4 TCC 20 . 5 0

! \ S

TCC 17 C ! I H

! P A

01 10/04/2015 TCC & IEC Update AJ IW KB R G

5 0

00 17/03/2015 First Draft DR AJ IW \

TCC 21 e !! t

TCC 22 u o r

Rev Date Description Drn Chk App e !! l

TCC 23 b a c

Boston l Triton Knoll Electrical System l TCC 24a & 24b o n 0 K 0

0 ! District n 0 o t 4 " i 3 r

TCC 25 T

-

! 7 2 4

TCC 26 0 8 P \ l a n o TITLE: i t a n

Figure 3.1 r e t n

TCC Locations I - 8 0 \ South King's Lynn and West : P

South : h 0 4 8 t Holland South Holland Norfolk District a P

Kesteven t Kilometres n District District / e m

SCALE: 1:200,000 @ A3 u

District c

REV 01 o D

© Crown copyright, All rights reserved. 2015 License number 0100031673 Contains Ordnance Survey data © Crown copyright and database right 2015

510000 520000 530000 540000 550000 560000 570000

Legend:

Proposed Development Boundary

Administrative Boundary (District / Borough)

! Temporary Construction Compound (TCC) 380000 West TCC 1 (! Road Crossing Locations Lindsey ! Total Area of Land Required for the Sea Road (! Substation Compound, Underground District (! " Cabling, Permanent and Temporary Access Tracks and Drainage and Langham Roman Bank Landscape Mitigation Road (! TCC 2 Total Area of Land Required for the Listoft ! Intermediate Electrical Compound, ! Permanent and Temporary Access Lane " (! TCC 3 Tracks, Underground Cabling and (! Drainage and Landscape Mitigation Sloothby High Lane 370000 Chalk Lane "! Ingoldmells Road TCC 4 East Lindsey (! (! District Younger's Lane High Lane !! (!(! (! TCC 5 Lymn Bank TCC 6 TCC 7 LowBligate Lane TCC 8 (! Fendike Bank !(! B1195 Lane (! (!! TCC 9 ! Tip Lane Harrison's Lane 360000 TCC 10 (! (! Bell Water East Fen ! Drain Bank Lane ! Spilsby xd TCC 12 (! TCC 11 Road Coordinate System: British National Grid North !! Projection: Transverse Mercator Westhouses Datum: OSGB 1936 (! Units: Meter Kesteven TCC 13 TCC 15 ! District TCC 14 TCC 16 ! (! Westville (! TCC 18 Road

350000 (! TCC 19 ! Canister Lane Source: Global Land Cover Facility, www.landcover.org. ! Peacock's TCC 20 (! Road ! (! ! TCC 17 ! Kirton Langrick Drove Road 01 10/04/2015 TCC & IEC Update AJ IW KB !! TCC 22TCC 21 00 17/03/2015 First Draft DR AJ IW ! Rev Date Description Drn Chk App TCC 23 Boston Triton Knoll Electrical System TCC 24a & 24b District Bicker "! 340000 Drove (! TCC 25 ! TCC 26

TITLE: Figure 3.7 Road Crossing Locations South King's Lynn and West South Holland South Holland Norfolk District 048 Kesteven / District District Kilometres District SCALE:1:200,000 @ A3 REV 01 Document Path: P:\08-International\P80427 - Triton Knoll cable route\05 GRAPHICS\05.4 GIS\ES_Road_Crossing_Locations_20150410.m GRAPHICS\05.4 route\05 cable Knoll Triton - P:\08-International\P80427 Path: Document

© Crown copyright, All rights reserved. 2015 License number 0100031673 Contains Ordnance Survey data © Crown copyright and database right 2015

Indicative Indicative