SOCG007

Flintshire Local Development Plan 2015-2030

Statement of Common Ground STR3B Warren Hall

February 2021 LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

Contents 1. Introduction 1 2. Site Context 1 3. Current Planning Status 1 4. Background and Technical Studies 2 5. Economic Viability 3 6. Development Parameters 5 7. Development Trajectory 7 8. Infrastructure 8 9. Other Matters 10 10. Conclusion 13

Appendix 1 Placemaking Appraisal Appendix 2 Aeronautical Constraints

Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

1. Introduction 1.1 This Statement of Common Ground (SoCG) has been prepared by Flintshire County Council in conjunction with Welsh Government Department of Economy, Skills and Natural Resources (represented by WYG, now known as Tetra Tech) and Welsh Government Land Division and also the North Economic Ambition Board. It has been prepared to assist and inform the Examination of the Flintshire Local Development Plan (LDP) in respect of the strategic site allocation STR3B Warren Hall. The purpose of the document is to determine the matters agreed between the parties as well as any matters yet to be resolved.

2. Site Context 2.1 The site is located on the south side of junction 36 of the A55(T). It is broadly triangular in shape being bounded by Kinnerton Lane to the south west, Lesters Lane to the east and the A5104 to the north west. It wraps around existing residential at Warren Hall Court, which is accessed directly off the A5104. To the north east is Broughton, to the south east is and to the west is / . The site comprises 76.3ha of land which was submitted as candidate site BROU011 for mixed use development.

3. Current Planning Status 3.1 In the adopted Flintshire Unitary Development Plan (UDP) the site is allocated within policy EM2(1) as a High Quality Site allocation for B1 development. The allocation is for a smaller parcel of land amounting to 36.5ha and excludes the land between Kinnerton Lane and Warren Dingle and also excluded the land bounded by Kinnerton Lane, the A5026 and Warren Hall Court. 3.2 The site has a planning history dating back to the early 1990’s. The more recent and relevant planning history is detailed below:

Ref No. Description Decision Date 038744 Outline - Application (with details of siting and access) for Approved 21/04/08 76,394 square metre business park (Class B1), hotel and associated leisure facilities, roadway, car parking, drainage and landscaping, and off-site roadworks including new slip roads from A55(T)

Page | 1

Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

046961 Removal of conditions 9 & 10 of planning permission code approved 28/01/10 no. 038744 pertaining to the construction of slip roads 046962 Variation of condition no. 14 of planning permission ref. Approved 04/02/10 no. 038744 to read 'No site infrastructure or construction works shall be commenced until a scheme for the improvement and/or extension of the existing sewerage system has been agreed with the sewerage undertaker to the satisfaction of the Local Planning Authority. No buildings (or uses) hereby permitted shall be occupied (or commenced) until such improvements and/or extensions have been commissioned to the reasonable satisfaction of the Local Planning Authority.' 047092 Reserved Matters Application - details of structural Approved 06/04/10 landscaping required under condition no.1 of planning permission ref: 038744

048360 Application to vary condition no.2 of planning permission Approved 19/07/11 ref: 038744 to extend time for submission of reserved matters by 3 years

051965 Application for approval of reserved matters following withdrawn 19/02/20 outline approval. (038744) 051973 Application for approval of details reserved by condition approved 09/05/14 Nos.28 (noise management) and No.29(dust assessment) attached to planning permission ref:038744

4. Background and Technical Studies 4.1 The allocation of the site is informed by a number of background and technical studies undertaken and prepared by the site promoters Welsh Government. 4.2 As part of the suite of documents supporting the Deposit LDP the Council published a Warren Hall Masterplan and Delivery Statement which included an indicative masterplan for the site. This document represented a summary of the following background studies:  Masterplan LDP-EBD-STR3B.1  Agricultural Land Classification – Ray Leverton 2019 LDP-EBD-STR3B.3  Ecological Assessment – (TEP) 2019 LDP-EBD-STR3B.4 o Appendix A Desk Based Assessment – TEP 2019 LDP-EBD-STR3C.4.A o Appendix B Target Notes Report LDP-EBD-STR3B.4.B o Appendix C Hedgerow Assessment and Woodland NVC Survey Technical Report – TEP 2019 LDP-EBD-STR3B.4.C

Page | 2

Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

o Appendix D Arboricultural Survey – TEP LDP-EBD-STR3B.4.D o Appendix E Bat Surveys – TEP 2018 LDP-EBD-STR3B.4.E o Appendix F Great Crested Newt Survey – TEP 2019 LDP-EBD-STR3B.4.F o Appendix G Breeding Bird Survey – TEP 2019 LDP-EBD-STR3B.4.G o Appendix H Water Vole and Otter Survey – TEP 2018 LDP-EBD-STR3B.4.H o Appendix I Badger Survey – TEP 2018 LDP-EBD-STR3B.4.I o Appendix J Reptile Survey – TEP 2018 LDP-EBD-STR3B.4.J o Appendix K Invertebrate Assessment – TEP 2018 LDP-EBD-STR3B.4.K o Appendix K Arboricultural Constraints Drawing LDP-EBD-STR3B.4.L  Phase 1 Geo Environmental Assessment – TEP 2019 LDP-EBD-STR3B.5.1 o Historical Records – Atkins 2019 LDP-EBD-STR3B.5.2 o Envirocheck Report Part 1 – Landmark 2019 LDP-EBD-STR3B.5.3 o Envirocheck Report Part 2 – Landmark 2019 LDP-EBD-STR3B.5.4  Archaeological and Heritage Based Assessment WYG 2019 LDP-EBD-STR3B.6  Noise, Air Quality, Lighting and Odour (NALO) – WYG 2019 LDP-EBD-STR3B.7  Transport Feasibility Study Pt1– WYG 2019 LDP-EBD-STR3B.8.1 o Transport Feasibility Study Pt2– WYG 2019 LDP-EBD-STR3B.8.2  Preliminary Utilities Appraisal Report – WYG 2019 LDP-EBD-STR3B.9.1 o Preliminary Utilities Appraisal Report – WYG 2019 Apps LDP-EBD-STR3B.9.2  Dev Enq Mains Letter Hafren Dyfrdwy LDP-EBD-STR3B.9.3  DCWW LDP-EBD-STR3B.9.4 4.3 As part of representations to the Deposit LDP, Welsh Government through WYG submitted the following documents:  Market Assessment – Thomas Lister Limited – 2019 LDP-EBD-STR3B.2 4.4 Further supporting studies have been submitted by Welsh Government including:  Placemaking Appraisal – WYG – 2020 (see Appendix 1)

5. Economic Viability 5.1 To capitalise on opportunities to generate growth, the region has developed a single, ‘joined-up’ vision for economic and employment growth, with a commitment between all the partners to work together collaboratively for a common purpose.

5.2 The Growth Vision produced by the North Wales Economic Ambition Board (NWEAB) is founded on three key aims (Smart North Wales, Resilient North Wales and Connected North Wales) with nine Programmes forming the “key drivers” to deliver the vision. The Programmes will be long-term, broad based in nature and provide a clear framework to

Page | 3

Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall pool and integrate private and public resources to deliver positive outcomes for the economy. One of these is the Land and Property Development Programme, with the aim of addressing the shortage of suitable land and properties for business growth and to bring forward sites for housing development. The North Wales Growth Deal was completed by all the NWEAB partners and UK and WG on 18th December 2020.This commits the two Governments to investing £240m into programmes which, when combined with the contributions the board hopes to secure from partners and the private sector, result in a deal worth more than £1billion. 5.3 Warren Hall is identified as one of the first six priority projects within the Land and Property Programme of the Growth Deal. While there is clear evidence of demand from the private sector, private investment cannot be secured and interest can’t proceed unless the primary infrastructure is provided. Accordingly, the NWEAB funding plan identifies funding of up to £15M to meet primary services and up front infrastructure costs at the site. 5.4 The Welsh Government will provide the land and work with the NWEAB to deliver the necessary planning consents and enable the site for development subject to all necessary approvals. 5.5 The new Land Division within Welsh Government will be responsible for future delivery of the residential parts of the site. The Land Division has been formed to serve the policy objective of Ministers to deliver more well designed, affordable and sustainable homes and places whilst leveraging additional social benefits. This reflects the way the Welsh Government has transformed its approach towards publicly owned land by taking a far more strategic approach to utilising these key public assets. The WG has introduced a policy which recognises that public land can have a long-term value far beyond that which the commercial market can generate in the short term, and its establishment is a clear demonstration from Government that it is serious about accelerating the development of public sector land to ensure a concerted public sector response to the shortage of social housing. This is in alignment with the clear intentions in the National Development Framework in relation to the delivery of affordable housing, with the final NDF expected to be made public in February 2021. 5.6 The fundamental principle governing WG developments is that the WG will retain control of those developments rather than simply handing them over to a developer. Retaining control enables the WG to determine the tenure mix of a development, with the target being that at least half of the new homes should be affordable housing. 5.7 WG are also able to specify the energy efficiency of any new homes built where the target now is that every new development should be net zero in terms of carbon emissions. WG are also able to stipulate minimum space standards for the market housing as well as the social housing on these sites. The need to respond to the challenges of climate change is at the heart of this new response. The zero carbon homes

Page | 4

Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall on our exemplar sites will demonstrate to communities that it is possible to build homes which are solely dependent on renewables. 5.8 A high level cost estimate for preparing development plots on the employment and commercial parts of the site has been prepared. The figures below provide a current estimate with no allowance for inflation. This has no bearing on the delivery of the housing element.

Development Costs: 1 Enabling works, site clearance £4,000,000 2 Roads, paths, paving and surfacing £1,538,000 3 Soft landscaping and planting 4 Fencing, railings and walls £822,000 5 External fixtures £161,000 6 External drainage £444,000 7 External services £961,000 8 Minor building works and ancillary buildings £27,000 9 Provisional Sums £2,537,000 10 Main Contractor's Preliminaries £1,573,000 11 Risks / Design Contingencies £1,206,000 12 Inflation Excl 13 Fees £905,000 14 VAT Assessment Excl ESTIMATE TOTAL £14,174,000

6. Development Parameters 6.1 The site is allocated by virtue of STR3B for a mixed use development comprising the following elements:  300 new homes, including affordable

Page | 5

Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

 22.7Ha of B1 and high quality B2 employment land  Commercial hub involving hotel, leisure, local centre and retail  Strategic landscaping and green infrastructure network  Sustainable transport links with nearby settlements and a link with the section of the Mold – Active Travel route between Penymynydd and Broughton. 6.2 The housing element of the site falls within the Mold and Buckley Local Housing Market Area as defined in the Flintshire Local Housing Market Assessment which, in conjunction with the Viability Study, requires the provision of 40% affordable Housing. The Affordable Housing Background Paper 7 identifies 120 affordable units being delivered on the site. However, Welsh Government will seek to achieve at least 50% affordable on this site, which will result in an additional 30 affordable dwellings. In terms of size of units the Local Housing market Assessment identifies that 45.6% of need is for smaller 1-2 be units, 28.3% for 3 bed general needs, 12% for 4 bed or more and 14.1% for older persons. 6.3 In accordance with the findings of the LHMA the development should comprise a mix of housing by type and size. Table 5.7 of the Local Housing Market Assessment (Update) identifies the following breakdown for open market dwellings which represents a guide to the likely mix of dwellings by type and size within the development:

6.4 As the Warren Hall site is in Welsh Government ownership, it is the intention to make the residential element of the mixed use site available as part of the Welsh Government’s programme of making land available to accelerate the provision of affordable housing, and work is ongoing with the North Wales Registered Social Landlords to advance this site. As set out above, the target is that at least half of the new homes to be affordable housing.

Page | 6

Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

7. Development Trajectory 7.1 The development of the housing element of the site, as detailed in Background Paper 10 Housing Land Supply will proceed at the following rate of development:

Year Completions

2023-24 30

2024-25 45

2025-26 45

2026-27 45

2027-28 45

2028-29 45

2029-30 45

7.2 One of the most important manifestations of the Welsh Government’s approach to publicly owned land has been the development of a new approach to housing development on so called ‘exemplar sites’. By harnessing the opportunities available to utilise public land in a manner which recognises its wider public value, the WG are placing social housing at the heart of the approach to development. By moving to a model that insists on decarbonisation of new homes, space standards and an insistence on mixed tenure development, WG are taking an integrated approach to the development of new homes which reflects its wider policy goals as well as the crucial need to deliver additional social housing. 7.3 The WG Land Division is focused on delivering this new approach on exemplar sites, focused on the delivery of primary benefits relating to Design Quality, Site Coverage and Dwelling Size and the Placemaking Wales Charter. The intention is for Warren Hall to comprise an exemplar site. 7.4 The planning strategy to deliver this site is envisaged to comprise a single outline planning application covering the commercial, employment and residential parts of the allocation. The outline application would seek permission for the enabling infrastructure in full. In parallel with the production of this application, the Land Division of WG would pursue discussions with residential developers such that reserved matters applications of the residential part of the site could be pursued promptly. The overall aim would be that implementation of the employment/commercial enabling infrastructure would occur in tandem with the development of the residential part of the site. Subsequent reserved matters for employment development would respond to market demand.

Page | 7

Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

8. Infrastructure Utilities 8.1 The Councils Infrastructure Plan LDP-EBD-BP3 sets out some of the infrastructure required to deliver this development and further information is provided in the Preliminary Utilities Appraisal Report LDP-EBD-STR3B.9.1 undertaken by the site promoter. Infrastructure will be funded through the Growth Deal. Highways 8.2 Junction 36 has already been upgraded in the form of a grade separated interchange, which was a requirement of the previous planning permission. This upgrade provides access and egress to both carriageways of the A55(T) from the A5104. This will provide vehicular access to the business park and local centre / commercial hub. The residential development shall be accessed from a single / two points of vehicular access along Kinnerton Lane. 8.3 In accordance with the Transport Feasibility Study, which establishes the feasibility of the proposed development, further work on trip generation and assignment will be required in support of a planning application. The development of the site needs to fully consider the role of Lesters Lane as part of the local highway network. The road is unsuitable to provide a means of vehicular access to the site and options exist for it to become one-way or for it to be become a no-through road whilst maintaining access to land holdings and properties from either end. This should prevent Lesters Lane from becoming a rat run.

Links to Active Travel / Public Transport 8.4 The Council has adopted an Active Travel strategy for the County. The Integrated Network Map (INM) schedules show a route BR2/2 from the footbridge to the east of Dobshill (Over the A55T) along The Old Warren to the junction with the A5104. The schedule also mentions an alternative route from Rd Penyffordd along the A5104 to the Warren Hall interchange. At present the Council is progressing both schemes as part of its Active Travel and Core Cycle Network initiatives. The layout and design of the proposed development at Warren Hall should provide safe and convenient links from the site to Active Travel route(s) thereby linking with Penyffordd / Penymynydd and Broughton. 8.5 The proposed development should also ensure walking and cycling links throughout the site and provide links to Higher Kinnerton to enable services and facilities to be accessed by residents. As indicated on the Masterplan, pedestrian/cycle links are proposed at south of the site onto Kinnerton Lane and Lesters Lane, ultimately creating

Page | 8

Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall pedestrian/cycle connectivity through the Strategic Site, including to the employment/commercial elements and up to the A5104 to the north. 8.6 Kinnerton Lane and Lesters Lane currently provide no dedicated footway / cycleway facilities. As part of Elan Homes residential scheme (planning permission ref. 054770) located to the south of Kinnerton Lane (circa 500m eastwards of the southern periphery of the Warren Hall site), new footpaths were required to be constructed as follows and this work is either complete or being progressed:  Provision of a footway along the northern boundary of the site from the point Footpath No. 5 joins Kinnerton Lane and on to Main Road  Provision of a lit footway along the western boundary of the site from the point Footpath No. 5 joins Kinnerton Lane to the south western corner  Improvements to Footpath No. 5 from the point it joins the site at its south western corner to Park Avenue. 8.7 A new dedicated footway/cycleway could potentially be created to complete the current ‘gap’ in pedestrian/cycle access (extending to circa 500m) from the location of the proposed pedestrian/cycle access point into the Warren Hall site along Kinnerton Lane eastwards, connecting with the newly constructed footpath created as part of the Elan Homes scheme (i.e. connecting at the point where Footpath No. 5 joins Kinnerton Lane and including pedestrian crossing facilities as necessary). This would create a dedicated pedestrian route from the Strategic Site to the settlement of Higher Kinnerton, with pedestrians able to access the local services and facilities along Kinnerton Lane / Main Road or along Kinnerton Lane / Footpath No. 5 / Park Avenue. Further consideration needs to be given to improving cycle links between the site and Higher Kinnerton as part of drawing up more detailed development proposals. 8.8 The formulation of detailed development proposals will need to assess the capacity of existing bus services and the likely demand for new or improved services. At present, service number LT8 / Hope / Penyffordd / Higher Kinnerton / Broughton runs along Kinnerton Lane past the site and provides a link to Arriva service 3 between Broughton and Chester. The proposed development should provide appropriately sited new bus stops and routes within the development or ensure that the layout and design of the proposed development provides safe and convenient links to bus stops along Kinnerton Lane and the A5104.

Education 8.9 The Infrastructure Plan (Background Paper LDP03) provides a commentary in respect of Education. The Local Education Authority has not formally objected to the proposed development and the LDP continues the approach adopted in the UDP and existing SPG23 Developer Contributions to Education in seeking financial contributions whereby new development places pressure on the capacity of existing schools. Utilising

Page | 9

Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall this methodology the Local Education Authority presently seeks a financial contribution of £845,733 to Derwen Foundation School, Higher Kinnerton and £960,388 to High School. However, this will need to be reviewed in the light of up to date information at the time of a planning application. Public Space / Green Infrastructure 8.10 The development will deliver a high quality green infrastructure framework for the site as indicated in the illustrative masterplan. For the residential element comprising:  16,000sqm play and recreation space including o An equipped neighbourhood play area o Signage / seating / picnic tables / litter bins / bike racks o Multi use Games Area (MUGA) 30m x 16m  Structural landscaping  Creation of attractive pedestrian and cycling routes through the site as part of a green infrastructure network (see Active Travel section) 8.10 The extensive areas of undeveloped land in the north western corner of the site may have the potential, subject to the extent of ecological mitigation, to accommodate a sports pitch, which could be utilised by residents of both the development and nearby settlements.

9. Other Matters Placemaking 9.1 The development must embrace the Placemaking principles embodied within PPW10 in order to deliver a sustainable high quality living environment. 9.2 A detailed assessment of the sustainability credentials of the Warren Hall Strategic Site allocation has been undertaken in the context of The Well-Being of Future Generations (Wales) Act 2015 and Planning Policy Wales Edition 10 (December 2018) and this is presented in the form of a placemaking Appraisal .The allocation is capable of achieving the majority of the PPW placemaking outcomes (Paragraph 2.20 of PPW 10 clarifies that “not every development or policy proposal will be able to demonstrate they can meet all of these outcomes”) and is therefore capable of delivering a highly sustainable development. A summary of the key placemaking outcomes as well as the full assessment is set out in Appendix 1. Indicative Layout 9.3 An indicative layout is provided as part of the Masterplan for the site and this identifies the broad location and arrangement of the land uses proposed as well as strategic green infrastructure network and access points. This will form the basis for the formulation of detailed development proposals at planning application stage.

Page | 10

Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

Noise 9.4 In accordance with the NALO Report, an on-site noise assessment will be required in respect of existing sensitive receptors and to identify avoidance and mitigation measures in respect of the following potential noise sources: • Road traffic noise from A55 to the north-east of the site; • Road traffic noise from A5104 to the north of the site; • towards the north-west of the site; and • Operational noise from North Wales Autograss Club to the east of the site. SuDS 9.5 A Sustainable Drainage Scheme based approach to the surface water drainage of the site will be required in accordance with the Flood Water Management Act 2010. The level of development proposed as part of the Strategic Site allocation can be delivered as part of a SuDS compliant scheme. The site is primarily characterised by medium/large pasture fields and areas of woodland, including the woodland and watercourse knows as Warren dingle in the southern third of the site. Of the total site area of 75.49 hectares, development / built-form is proposed on circa 32 hectares. As such, over half of the site will remain undeveloped. A significant amount of undeveloped land is therefore retained on the site, allowing flexibility for appropriate areas to be utilised for SuDS measures as required. A SuDS compliant scheme can be delivered and the requirement to implement SuDS measures will have no significant effect on developable area. The scheme should be designed from the outset as an integral part of the overall design in accordance with the Statutory SuDS Standards and capable of being adopted by the SuDS Approval Body (SAB) which is FCC.

Ecology 9.6 The site is supported by an extensive and detailed range of ecological surveys. These identify the key ecological features, habitats and species in the site which are the linear hedgerows, mature trees, woodlands, patches of semi improved and marshy grasslands which are associated with a variety of species associated with the woodland. The development of the site should implement the Ecological Appraisal’s recommendations and biodiversity enhancements in conjunction with the drafted Masterplan. Further ecological assessment work will be required in drawing up detailed development layouts and designs, in particular relating to breeding birds, and Hobby. 9.7 In addition to the existing Ecological Appraisal, an Ecological Impact Assessment will be required to inform a masterplan approach for the site at planning application stage supported by appropriate avoidance and mitigation measures for both species

Page | 11

Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall and habitats. Overall, the proposed development should enhance biodiversity on the site. 9.8 Habitats to be retained need to be buffered appropriately so not to be squeezed (particularly hedgerows) between development land and footpath/cycleways particularly where lighting is required so that the habitats can continue to provide wildlife connectivity. Trees and Hedgerows 9.9 Mature trees are on the site and will need to be retained and protected. Hedgerows should also be retained but where required to be removed they shall be replanted using indigenous species. Further advice is contained in adopted SPG4 Trees and Development. 9.10 Warren Dingle is a wooded valley running through the site which is designated as an Ancient Woodland under the title of ‘Plantation on Ancient Woodland Site’. Gravelhole Wood is designated as a Restored Ancient Woodland Site. As indicated on the Masterplan these features will be protected from development. A planted buffer will be required between such woodland and built development and can help create dark corridors through the site. These habitats have good opportunities for biodiversity enhancement through appropriate management. Built Heritage 9.11 In line with the findings of the Archaeological and Heritage Desk Based Assessment, the formulation of detailed development proposals will have regard to mitigating identified impacts on designated and non-designated heritage assets. With regards to Built Heritage, levels of less than substantial harm have been identified in relation to historic assets in proximity to the site boundary, and to the potential non- designated heritage asset of Warren Hall Garden, which lies wholly within the Site. With the levels of harm being demonstrably of a less than substantial nature and in the main at the lowest end of the scale of harm, the harm is required to be balanced against the public benefits arising from the development proposals. Parking 9.12 Parking provision shall be made within the development in line with the current parking standards in SPG11 Parking Standards. Space Around Dwellings 9.13 The development will ensure adequate separation distances between existing and proposed dwellings and adequate private amenity spaces in dwellings in line with existing SPG2 Space Around Dwellings to ensure that adequate living standards or amenity is established.

Page | 12

Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

Aeronautical Constraints 9.14 The IFP Assessment (Cyrrus, December 2018) provides evidence to demonstrate that development of two or more storeys in height will be acceptable on approximately 53.6 ha / 71.2% of the overall site area. As such, it is confirmed that aeronautical restrictions will not constrain the deliverability of the Warren Hall Strategic Site. This position has been discussed with Airbus UK, who consider that in light of the results of the IFP Assessment, further detailed design work at Warren Hall can proceed. Further details are contained in Appendix 2.

10. Conclusion 10.1 The Council, Welsh Government and the North Wales Economic Ambition Board consider that the allocation is sustainable, viable and deliverable.

Andrew Roberts Andrew Roberts, Service Manager Strategy, Environment Directorate, FCC 03/02/21 Peter Waldren Peter Waldren, Director, Tetra Tech, Agent on behalf of Landowners 03/02/21 Alwen Williams Alwen Williams, Director NWEAB 03/02/21

Richard Baker Richard Baker, Deputy Director, Land Division, Welsh Government 03/02/21

Tim Howard Tim Howard, Deputy Director – Property, Welsh Government 03/02/21

Page | 13

Appendix 1 Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

Appendix 1 Placemaking Appraisal A summary of the way in which the Warren Hall Strategic Site has embraced the key sustainable placemaking outcomes is set out below (and detailed fully within the attached Placemaking Appraisal).

 Outcome: Creating and Sustaining Communities The mix of uses to be located on the Strategic Site allocation will deliver a significant number of jobs located directly adjacent to new homes. The co-location of employment and residential land will create a balanced , with the commercial hub providing complementary local facilities for use by future residents and employees alike. In addition, a significant number of affordable homes will be delivered on the site (circa 50%). The Warren Hall site will therefore provide much-needed high-quality affordable housing, and the phasing, mix, and integration of affordable and general market houses will ensure social inclusion and create an inclusive and mixed community, promoting the wellbeing of future occupiers.

 Outcome: Making Best Use of Resources The site does not specifically make use of previously developed land – however, as set out within the LDP Preferred Strategy “Given the polycentric settlement and development pattern, and as a general rule the lack of suitable new strategic sites, the Council’s focus in the Plan is on ensuring that the existing strategic site commitments are fully enabled to deliver development, before considering further strategic scale allocations”. The Warren Hall site can deliver a sustainable mixed-use allocation adjacent to the existing settlement of Broughton directly to the north-east, within walking and cycling distance of existing services and facilities. The delivery of the Warren Hall site will assist in ensuring that less sustainable greenfield allocations are not required to provide jobs and homes for the residents of Flintshire.

Furthermore, the site does not contain any agricultural land that is classified as ‘Grade 1’ (excellent quality) or ‘Grade 2’ (very good quality). The site primarily comprises Appendix 1 Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

agricultural land classified as ‘Subgrade 3a’ (good quality) and ‘Subgrade 3b’ (moderate quality), with some areas of ‘Grade 5’ (very poor quality) and ‘non-agricultural’ land. The Grade 3a land is present in patches across the site, principally north of Warren Dingle, south and west of Gravelhole Wood and adjoining the south and east of Warren Hall. Accordingly, allocation and development of the site is not considered to remove viable areas of best and most versatile agricultural land.

 Outcome: Maximising Environmental Protection and Limiting Environmental Impact The illustrative masterplan for the Strategic Site incorporates a substantial degree of open space and high-quality green spaces. A network of green infrastructure threads throughout the site, through the retention of existing natural features as well as the provision of new or enhanced planting/hedgerows/footpaths. A number of ecological enhancement measures are incorporated within the masterplan, including the protection of existing hedgerows and woodland; management works to waterbodies and woodland on site; wildflower corridor planting; a bat and bird box scheme; and reptile habitat creation. Also key to the masterplan is the incorporation of sustainable drainage, with the site allowing for a SuDS-compliant scheme.

 Outcome: Growing Our Economy in a Sustainable Manner The mixed-use allocation includes provision for a substantial degree of high-quality employment land. Warren Hall presents in the short term, prospects to deliver a mix and type of commercial development to Flintshire, to complement and enhance the type of employment development being provided on other sites in North East Wales. The site, therefore, will assist in facilitating economic growth and bringing about an increase in skilled / high-value employment. As stated above, the mixed-use nature of the allocation will ensure that homes are provided next to jobs, enhancing the site’s sustainability.

 Outcome: Facilitating Accessible and Healthy Environments A shared cycleway / footway is present along the Warren Interchange to the north of the site, which provides a connection into the existing pedestrian footway along Mold Road Appendix 1 Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

and Main Road within Broughton. Main Road provides a link to Chester Road where lit footways are provided on both sides of the carriageway. These footways provide a link from the site to and Hawarden Industrial Estate. There are a number of Public Rights of Way (PRoW) which run along the boundary of the site and provide a connection to the surrounding areas. Footpath Higher Kinnerton 5 runs to the south of the site from Kinnerton Lane to Main Road within Higher Kinnerton village centre, this provides an onwards link to PRoW Higher Kinnerton 4 and to the village of Penyfford. In addition, PRoW Buckley 77 runs to the west of the site off the A5104 to Old Warren Road, providing a link under the North Wales Expressway. A GIS network analysis has been carried out to assess pedestrian accessibility from the site. This analysis shows that Broughton, Higher Kinnerton, Kinnerton Green and Penyffordd are all accessible within a 30-minute walk from the site (based upon a walk speed of 4.8 km/hr).

There are a number of proposed cycling routes within the site that will tie in with the surrounding infrastructure including the new shared cycleway / footway along the Warren Interchange north of the site. National Cycle Network (NCN) route 568 runs approximately 6km north east of the site along the River Dee. NCN 568 runs along the River Dee shared cycleway/footway and provides a connection to NCN5 (North Wales Coastal Regional Route 89) within Shotton and NCN 45 within Chester, this allows for onward cycle connectivity within the wider surrounding areas. A GIS network analysis has been carried out to assess cyclist accessibility from the development site. This analysis shows that Broughton, Buckley, Higher Kinnerton and Bretton are all accessible within a 30-minute cycle from the site (based upon a cycling speed of 16km/hr).

The nearest bus stops to the north of the site are located on A5104 (‘Warren Hall Court’, immediately adjacent to the site.) This is served by the number 13 bus service which provides an hourly connection to the ‘Old Cross Keys Farm’ bus stop located approximately 300m from Buckley Rail Station. Additional bus services can be accessed from the ‘Royal Oak’ bus stop within Higher Kinnerton located approximately 600m south of the site. This stop operates is served by numbers 61, 61X and 62 providing additional Appendix 1 Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

bus services to Broughton Heath, Wepre and Chester. It is pertinent to note that due to the scale of the site, certain areas are closer to bus services than others and, on this basis, it is considered that bus services are available within appropriate distances either from the A5104 Main Road, or from Higher Kinnerton. The site is well located to integrate into the local pedestrian and public transport network. Given the location of the development on the southern edge of Broughton it is well located to maximise access by sustainable transport modes. Both village centres are accessible by walking and cycling to the north of the site and provide a number of employment opportunities, retail, leisure, healthcare and grocery facilities.

To the south of the site, the settlement of Higher Kinnerton is located within circa 1km, within which are located a range of local services and facilities, including shops; public house; primary school; village hall. Proposed enhancements to pedestrian and cycle linkages from the south of the Warren Hall site to Higher Kinnerton are outlined below.

The full Placemaking appraisal is presented overleaf: Appendix 2 Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

Appendix 2 Aeronautical Constraints The development of land at Warren Hall will be constrained by the operation of the runway at Hawarden Airport, which is located circa 2km to the north-west of the Warren Hall site. An assessment of aeronautical constraints has been carried out drawing upon the following (as detailed in full below):  Obstacle limitation surfaces assessment  Instrument flight procedure assessment

Obstacle Limitation Surfaces Assessment The use of an aerodrome is influenced by natural features and man-made constructions inside and outside its boundary. The initial method of assessing the significance of any existing or proposed object within the aerodrome boundary or near the aerodrome is to establish defined obstacle limitation surfaces particular to the runway and its intended use.

Assuming that flights take off and land in both directions at Hawarden, there are two obstacle limitation surfaces that affect the Warren Hall site:  Take-off climb surface – illustrated on Drawing A093950-15[B]02 (attached at Appendix A)  Approach surface – illustrated on Drawing A093950-15[B]03 (attached at Appendix B)

The difference between existing ground levels and the obstacle limitation surfaces has been calculated. Much of the existing ground level of the site infringes the take-off climb surface and approach surface. For the balance of the site, the difference in height between the existing ground level and the obstacle limitation surfaces has been calculated and is illustrated on Drawing A093950-15[B]05 (attached at Appendix C). From this, it is concluded in summary:  10.35 ha (13.74% of the overall site) would be available for single-storey development.  7.85 ha (10.42% of the overall site) would be available for two-storey development.  6.18 ha (8.21% of the overall site) would be available for three-storey development.  2.57 ha (3.41% of the overall site) would be available for development above three storeys.  In addition, there is a strip of land in the north-west of the site, adjacent to the A5104, that is unaffected by the obstacle limitation surfaces (2.61 ha).

This initial assessment indicated that surfaces were penetrated with the worst-case being the Instrument Landing System (ILS). Accordingly, an Instrument Flight Procedure (IFP) Assessment was required to provide a more detailed/refined assessment.

Appendix 2 Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall

Instrument Flight Procedure (IFP) Assessment Further to discussions with Airbus UK, an Instrument Flight Procedure Assessment was commissioned and undertaken by Cyrrus (Aviation Consultant) in December 2018 (Cyrrus Report attached at Appendix D). The IFP would establish the Target Level of Safety for aircraft operating to a specified Obstacle Clearance Altitude/Height (OCA/H), with consideration of all obstacles penetrating the Basic ILS surfaces.

The assessment was based broadly on building heights and locations proposed in the Masterplan approved as part of the 2008 outline permission for a business park and hotel/leisure uses (Permission Ref. 038744). Converting the OCA/H into metres and taking away the obstacle clearance of 50m provides a height of 87.16m. The ILS surface altitude at the critical point (Building Plot 04) is 74.2m, which indicates a maximum height of 74.2m for the development. As this assessment only considered the development as a whole, a further assessment would be required for each individual building against each IFP to determine individual building height requirements – however, this would need to follow more detailed designs for the site.

The assessment concludes that notwithstanding the penetration of the instrument landing system’s basic surfaces, the assessed Instrument Flight Procedures were not impacted at a maximum building elevation of 74.2m.

The difference between the existing ground levels and an elevation of 74.2m across the site has been calculated. Some of the existing ground level of the site infringes the 74.2m elevation but, for the balance of the site, the difference in height between the existing ground level and the elevation of 74.2m has been calculated and is illustrated on Drawing A093950-15[B]08 (attached at Appendix E). From this, it is concluded in summary:  6.58 ha (8.73% of the overall site) would be available for single-storey development.  6.20 ha (8.23% of the overall site) would be available for two-storey development.  7.80 ha (10.35% of the overall site) would be available for three-storey development.  39.67 ha (52.65% of the overall site) would be available for development above three storeys.  In addition, there is a strip of land in the north-west of the site, adjacent to the A5104, that is unaffected by the obstacle limitation surfaces (2.61 ha).

Conclusions It can be concluded that the IFP Assessment (Cyrrus, December 2018) provides evidence to demonstrate that development of two or more storeys in height will be acceptable on approximately 53.6 ha / 71.2% of the overall site area. As such, it is confirmed that aeronautical restrictions will not constrain the deliverability of the Warren Hall Strategic Site. This position has been discussed with Airbus UK, who Appendix 2 Flintshire LDP – Statement of Common Ground – Feb 2021 STR3B – Strategic Site Warren Hall consider that in light of the results of the IFP Assessment, further detailed design work at Warren Hall can proceed (as set out within the letter attached at Appendix F dated 15th January 2019 from the Aerodrome Compliance and Safeguarding Engineer, Airbus Operations).

2018 hands 0@A3 0 tober 0 safe Oc 10, 02

minds 1: e e

of es r [2018] le Scale eativ 0AD ol r c metr rights 0 Contr CF24 ase , 50 f

ab

5321 the

s

t n

of dat

n o Cardif sion 0 2045

and intervals el 2018 40

n

ited Road, (0)29 permis

surface: 4

n copyright .com the

Lim fun 1.0m g 0 rt +4 tio at with 30 wy Crown ta

i Newport

site Fax:

l w.

constrai © Brought

map w

Transpo 47 0 e:

ours 3

l, l, lim mb surface mb surface

ng w 02 fic al f

e 0 Hal

ni 920 Of al 01.vwx m Survey 2 03167 20 en e o Court, acl

0 cont ery cli r Plan

s 0 nc

5[B] f st

nt H Hal

os ar 208

tion f 01 ake-of

me

n 0-15drf

autic n W Ob T with o 0 Sta Ordna e en s 95 (0)29 r r Survey 10 950-1 Longcr the e- 4

r

Enviro [email protected]

Group nce rth 5, on

a A093 +4

Majesty' or eron ey o ak

WYG o

ased

File: War W A T A093 Email: K WYG Fl © B Her Ordna Tel: N 0

Park CR ng i

p

ain Dr

a

Shop t n

S ond o

ub P ack

S l ation Tr

E St g ought n r i l B Fil ond a P t S ub S l E od o ak W

O en ond r P War els 12.54m n en BM BM K Def ond ank P T ank

Ex Bdy T R Bdy el EE T & UA rm

le ER e Asly Gab 5m Const, ak 8. Hous O Elm GP Asly ey erton Fa erton

15 n Const, n

e TCB

i Co

Handl K ain r

ous D

E H

29 RIV

nks D

28 10 a

T 24 LARNE Drain

45 Stamford 2 2 arns

B

AD

O R

ONE ak

B ONST SIM O

1 F

43

20 39

Def Old 8

1 3 14.6m 2

n RH n

1 2 m

2 ai o

FB 2 t 23 Dr

E s

Sta 1.2 3 Drain ri 3 NU ide

n 7 E ows ain

Chy ad

2 Sub War Me Dr

AV El ROAD

E 28

19 34 eld 8 hfi

ER Hig

ER

OAD

24 20 R aven 1 LESM Fairh

EL s

STONE ry Tank CHEST u Norb ow

sue

1.0m

SIMON 2 al 9 Is 1 m aul ng

ron H u

ar F

Pond B 4 Drain

15

D) ot e

F

l

2 Westc

ank A

T Bdy Th el 17 7 Bungalow

RO G

1 e RH

1 UA AY 40

1 Def

2 & Th EN W 2m r

e 1.2 ER

12 EDW elt

L Oulton

1 e Asly

C Sh RH 2m 15 e 1.2 ( tag AUGHTON Cot n Pond ous

9 o

i

n ain

t

1 4 rest H

26 lc Const, l 1 19 Hil

ta Dr

7 Drai S

rt rain

2 EN D

Asly Wal

10

T)

R 7 ng

OU ey i

C 1 RH

(um) 5

H

1.6m ANT

T

DN EDW

A 2m

AN 1 C

( N

D

9

Const,

CA B

14 1.2 S

LY CL

L Path

1.3m

Co Pump Farm

W 15 5 D 1 e t

arde

D 12 n

iew r 1 R Lodge e

2 r o V O l o

il

Pond F o rain 25 D n B

3 F H a esc L M

r

9.8m M 2 E C

Newhous

Bdy onds

OAD RD 14

E P

R R

I

ED m e

l

SH

CLOS E

0 t AN

L

ey R ON

OAD it

CH O

O

R 1

BS

13 M 1 EV

L L H

D 37

HAL 13.0

1 y ON

CHUR B BM BM

y

l HAWKER BROUGHT

16

1 e r Lay age Hal

tag

10.58m B Lay EVARD

ck Borde Gar 49 Cot

BOUL (um)

BM BM nwi THE i 7

Lodge

L (um) Sta Path rpo 27

Jays 2

149 18 Path 30

orts Sub ond

ound

El P 1 1 6

11 n

Sp

od 1

Gr o

14 2

8 Touchw

rto

1 Def

17 e 21 42

12

n

23 6

n

5 2

4 CL

CT

S D

1

E 9

15 1

Ki 7 Bethany S

BISHOP

10 2 15 2

Haw Ai

1

irch 1 1 12 CLO 7 B sprey Rise O EY DENFOR 1

3 22 E Drain 1

DEL 27

L OS

oul Lower

n C 5 L

Hey

ey SID 9 C n

CT n

Kin 38

S 4 35 Spi

E

OP

e ER

29

d Th

a e

BISH AL

ROAD est

RH

1.9m in V

on om

Broad a

H 1 16

e 2m

Th 2

Dr 2

3 MARTON

WEBST 37 56 1.2 7

36

13

2 1

75

18

ROAD

47

D

137

EL I

7 F 12

Chelston 6 RK

19 2a A P

49

26 154

a 2b

kd 1 18 CL ond

Ski E

P

4 2 EN 4 9

r 1

u 1 CLOS D

ts

mo C 12

a s EY 7

Pond 1

o

L 20

BRACK 1

P 15 5

1 Sta

Sub

65 146

MADEL El

on 127 t 54 Brought 13

en K RY 2 ROAD

1 2 1 N 7

rch CL

ary's O

125

7 T ley Gas SE

E ROSEMA

M

Gov e

CLO

27 123 14 4

Chu S 4 ge

m St 14 2 8 ag

Timber 1 t 2m 6

1 ONGL t

LB C

WATSON' Brid Far

1 Co

ac 16

12.9 1 d

56

ta n E

S

Jacm o

OS

BM BM 1

12

Sub 15 P

6 la CL

l

i

l 4

40 17

OAD E ROAD N

Son

R O CH Def

12.8m L 28 BS

2 15 RND

Sock CHUR 2 HAL Sta

age CR 2

d FA 1 es l

ON 1 10 70

al

Vicar 134 Sub

WAY T 19

Win LB Tre El

e S ebank tage

57 e

OSE 13 BROUGHT 2

7 Bridg

Cot

lk

ry 13

a

ack

MARY'

CL Def ewtr r ROAD 24

1 age

14 T

CLOSE Y ST h W h

Old Libra A 104 on 32 ORD

5 AD GAL

ars 18 The

A EATON 8

Churc 1 124 10 P

RO

2 2 SOMERF

43 e

E 2 1 OS

3

NSTAY ous CL 6

e 8 d n

WYN

1 60 1 E ain o ub 1 r

Forg

P 9 D Clockh

0 e

ond

2 Cl

e 1 36

7 ers

14 P

Old 6

1 ed) ri

SUCKL Th

e s e Gat

Th

on e Youth Far Whit disu e 1m

CS ( e 48 Sit Camp

12 Th 1

13. HONEY

Hous 8

t

ic 9

2

od

5 al ewo

Ingl

Clin

1 M

1 12 ry e Farm e a

45 47 e

28 t

22 53 an

ol 30 e dg ag

e

en t

akd o 24

O

32 6 Gr

4 2 39

102 3 tag

3 Bri

e

age

t s

Cot

Cot ack

m 36

e o

2 Cour r e

ro Th 79 B 38 ay Sch T e Cot fa'

h ag

t RH 13 (PH) on

ays Dyke

nts ad Of

erds 2m

hous

C Cot

House 2

plewhit ark 1 P rm 1.2 nfa eph enw

Ap a

I

19 h 1 2 e F

16 Old S CL e

Brought Gr

3 7 15 3 3 Th

The or and or ROW RIVE Dairy

14 D ni 14

19 d

ather

YAR ation AD

Ju

e 19 es on

St 26 e RO FOREST We P

ey

8 tag 1

103 Sta 8

ecot

Th

104 El

5

(um)

MAIN 1

Pop Cot A 1

h t

Sub Sub Dov

25 16 a

63 P Bdy

EER

1

CLOSE CL

1 Def 2 6 E OD

O S e

10 C 2

13 e

e D TRE COPESW D 7 17.4m s e tag rd

OA e

ew

2 Bridg

R YEW t Y Tr

2 n ROA o

2 arn Cot 65 Hou o

3 The B e

Drain 3 (um) Orcha F ELD 2

Stables

1 Const, erto

MEADOW Path

NFI 10 n Coach AD ridg

E 1 E Asly

B

3 12

Bdy RO

El 2 DRIV 6

Sub Sta Kin

3 GRE CL 56 TON

34 ET Const, UA BR & MAIN

RON Co

125 2

104

1 1

10

1 2 ER

HE 7 2

1 89

5 5 y

5 8 A 2 sl

B A

73

1

12 1 6 3

35 6 n 7 48

5 8 1 e 3 104 10

ai S

d 8 15 r E 73a

5 AD

5 dsi 14 H

D A 16 16 512 rt 8 RC

Fiel ou BI B RO CLOSE

C E 40 Def 21 2 H t T m r

den 1

MAIN

r 75

ERON ROAD

BM

27

a H 1 1.6

rpo 16

2 2 RH

2

2m

8 EADOW 79 Brought e 1.2 e 8 DRIVE Ai M c 90

us 73

Haw 1

o 5 19 2 TON 9

7 34

Poli H

m

1 5

6 BRET .

2 1

1 E 2 C A

m 86 L

1

7 P 2

80 GR 5

ON 19 1

T 2 1 15

18. SYCAMORE

LYN 2

1

5

7 31

BM

6

50

WAY 12 2 2

Sta

3 1

4 ack r E 6 3

El T 33 LOW 2

OAD 4 OS

16 Sub

7 9 2 R

WIL 1

2 7 1

ON CL 4 17

Def

OAD 2

7

12

R

er 9

9 RN ONATI 6

8 1 BLACKTHO

ONE COR 19 OKERY

21 27

3 3

19 Shelt 53

4

54

RO

2

ROAD 2 m

17 GLADST 1 56 THE

.5

1 (um) RFIELD 20 8 19 ath 3 FAI

P 1 1 2

9

2 40

LANE

53 58 23

60 LB m)

(u

59

7 24 OD WAY

ath P

WO EN'S

E 4 51 1 13 RIVE

QU 2 39

D

49 CB 38

T

34 7 5 5 ark

LB

10 29

8

4 1 47 1

P

5 6 FOREST 4 WAY 4

SONS 3 1

1 1

4 1

1 SIMP

1

4 RH

E 83 32 OS

Sta CL 2m

El LE

2 10 arden DA 1.2 Sub

9 18 OAK 4

r ay e

aw 8

elt athw

46

P 2 D 2 2

H

Sh

Track

29 OA

The 39

R

69 47 8

N 21

5

1

ROAD

7

L

13 AL

1

H

4 ok

4 36

o LANSDOW

3

ON Sta

43

5 1 Br 4

9

4

3

on ROAD 20 1 18

Sub HOPE

1 El

16 2 2

rought

3

27 E CS

BROUGHT CLOS B ECK 1 FIRB 12

8 6 1

ry m 2 4 BS

5

7 2

5

3 2

3 4

OAD 2 8

26. Surge

30

R

6

N

6 6

17.86m

83 3 3

2.3m

4

5 7 2 BM

SM

LINGTO 1 83 5

15 8

18 7

8 WEL a 1

SM 12 5

E 8

89

1 AVENU 26 OD

1 SANDWO

BS

13 rain

3 D OAD

4 8

R 24b

24a 2

27.61m

2b

5 2 24

14 7

Def

BM 16

74

2

ESTON

2

D 4

2

A

103 BE 87

O

8

R

ROAD 2 23

20 IN 2 A

arm

R

M

13

E 1 Sta F

29 1

e T e

S

Sta r

Sub 1

T 9

El 2

3

14

7 ar ROWANS

Sub 1

1 15 1

El e 1 H P

24 IRC LANE B ESTMIN

7 ER THE SILV

W OD 1 ROFT

PH 5 C

WO

19 1 E ENU 8

AV 1.6m 1 D

2 OO

W 2

IN y e L

19a 1 r CO Bdy t

25 Injury

1 n Bd

16

10 UA

ain 19

r ER

Ce

&

15 8 E

O

B 7 18

P

ER

15

2 y

34 e sl t

t 13

LB

o A

9 C 1 Ros

13 1 R 1

ar

ark 36

ark C Const, C

Pond P

P sly

3 e A

13 Car 3a 4m .

3 25 rndal

27 Const, e

F

1 Co 10 a 147

rage

9

a 2 5

Are

Play 13 5 G ack A Tr

ack ield

r er

T 19 F 27 50

ark E 4m Shelt AVENU 24. P ES OK e

BRO Playing ac Bdy 33 ED 8

m 2 osp

r 5 15

27.4

e

a

2

5

1 munity

Ae

5 5 rm Centr

ain a er

F

Com t Dr 17m ouse

on 5.

i H s 2b

t 2 n RK

ng 5 e

e 4

Sta BM e

s PA

rn R rack Gr E

o 23 e

T Bowli

Ch T

82 l 7

l 2

awth 16 a CAS

H Hous 1 E H

e

16 37 t AC LAN

u PL it ange

t Sta e

s ation 2

35 t 2 Gr n n es

I Sub S d OD in

El

Dra Barns Sto

ROAD

70 Pon Stabl MAIN alve V

The

s MARLWO 1

a 28.7m Bdy

G 69

1 ED

34 58 100 GP

46 106

73 ount

2 m 1 0

5

6 8 5 ork

A 28. osem Farm 12

3 R

Gardens 2 t 10 9 E n E CLOS e ER 98

Lane Earthw 7 1

n 1

17 STLEM

CA 9

e

ER

on CA 20.4m LYS otm L t l re h

G

Al 7

Bridge 25 37 1

Drain

ok 1 oug r n 87

ROAD B Bro 10 m ER 20.85m WINDSOR DRIVE M B 28.3

CHEST er

13 8 rto

8 2 2 nd 14

14 49

h

Po CS

E S LO C ELD ERFI e M SUM 86 7

9 n 5 8

1 n Hig r

e 14 t Ki

el

1 6

Sh 8

42

1 2

1 2

LB

7 B 17 19 7 17 5 3 TC 1 Lodge

74 m .0 Pond 8

2 E 2 BROAD OAK AVENU View

ok

CLOSE

20 22 D 18

6

Bro

ODFIEL 4 2

r ain

r

90 WO 7 e 7 D Sta

2 1 ok

19 o arm r Shelt 4

Sub ok 6 F B

CR o El Br

3 n 5

View

o

n 1 1 e 49 r r a

Park 9 W

n

CS ought Pond

e r 5

d

B 6 78 r CR

m ARNOLD'S a

56 9

dy k a

9. 3

m B aw 2 2 e O

l H

ED 05 ROAD

14 21 31 a (PH)

Th 32.6m 30. oy

DALE

R BM

RY

52

46

7

3 CHER m 6

6

1 5

l

ROAD

37 26

h

3

D Hal 4

43 E

OL 3l

38 N 7m M 5

Churc LA d) m Pond se Bed 35. r e su

lt E

BM di ( IV CF Fi 4

ERTON DR N 2 25 4 1 WARREN KIN

52 38

5 m 5

40 26

45 es Oaks ok r

nd CH o o d

N 19 Po Gwyn's Tu

17 24A Pin The

24

9 67 ae 46m y-c - n

y CLOSE

6 5

m 1

Ty- 9

3 BANK 16 5104 5

5

NY

A A

EN

32. P

1 2

E OS 47m 14

5 5 CL

BANK AD 5 m

2

NY 1 1 A

s

EN RO

P 32.0

nk CLOSE l L Si

10

as

DALE NHIL l 2

e RY

Vil R THOR ag

t E 48m t en H r o C awthorn C ar

H

8

W

17 15

4 1

2 49m on ry

10 o CH g lur

m on S Farm ry 19 l r La e um

rack Slu

T Mil

Lago

ag

t 6 1 ab ot aburn C

L 50

Cr 20 7 2 m rm Silos

ark a 31 P F 51 Farm Mount

Depot m s e ak ack su s o Tr I 52 ad Farm ro

Bank m B

n E

AN L

ER

EST

C EI

L ath (um)

Fer P

s

CR ESTER LANE CR on LEIC m 6m sue Mount s ry 85 I 53 r Bungalow Track 36. BM e Lago ages t The 40. Slu Th m GP

Cot LANE LEICESTER

Track Farm rk a

Drain P 54 rack

T m 5

ond E 5 P N LA

m N RTO

NE m 7 KIN

56 42.

n i

a

r

D m 57 S CCS m 17m 58 . 42

m BM s sue Is 59 m ery on e t ok r o e n odg R

60 n i L e K

m Th d ed e B 61 age B age age ond ew

P m S Sew ank T Tank 48.2m Bank en

r 62 ar

W m

Farm

rain D Bank

ren 63 ar

W m 51.84m BM 64 m 1.8m 5 age t dy

B Cot Track CS

ED Bdy 65 ond P Pond Bank ED d l o

ren m War

Wo 6 l

d Bdy

Hil

ED e 6 ros 5[B]02) ond shpon P ects i l m Prim s F S a l t CSC Col t A

rain

D Sluice

reads 67 an Sp Hal g l en Farmhouse r

al eg

r 1 ar 1 Old H e W

aych

Th 5 8m T l

al 58. 4 950-1 H ages t en r

4 Pond tage 5 ot 3 ar 3 C ond

2 W

Cot

P 1 2

6 House on 1 10 at ren o Boat B

Drain 12 ages t Brought 26 r 25 Cot

27 14 BM 5.31m

CR 1 5 d awr

o 24

2 M t

n 18

a A093 Wo ert N

r

23 l ov Fi al C

e H e

17 age ond t tag Th en t P Dingle r o n ar C Cot e en e W Wa r r d Croft i s e l

ar 5104 Th

Hil A War W l al

rt CF H

age t Track en ot Drain r Cou r C a .0m e W t 60 n

u

o 5104 eysuckl A

M n 6m o

en

H CH r 64. ar s drawing e W

su

Is ren

Lodge e

War

age

t t o

C

od

o rw Fi LANE

N 68.3m od od

o nd Bdy Bdy UndUnU

e NERTO ED Wo W ED r

e le l KIN Ac

d (se

alf o l H elho

1m

av

e ravelho

s .8

d Wo d e ag t t o e C 9 el G Gr

69.81m 6

su

y ar em s Ros

I BM n CH d r

shpon n

y r CR

Fi

rm s

e

ghad o L

e

Fa D

Cher

Orcha LANE

s AMLEY BR

sue Is

CH fun Grid fun en House e r tl at C leston c 1.6m 7 Ec War d l Bdy

ED O

m

ANE L

m BRAMLEY

2 OAD CH 72.8m 72.8

RCHARD R CHERRY O CF 72. s

od m e

y su Und

s s CH

65.2 Wo I

m 7 Lay-b ry surface

sue .5 s BM I er e surface ack 67

lb r

us T s Track Bi Ho d

r sue

RD ROAD e a s RCHA O r I RRY CHE h

a m c

r

Dale .4 eg d m m O

mb 7 S 8 Un .

CR 6 ren ry r 3 79.18m arehous a 73.8 7 ED Bdy er h W W BM C

.5m 2

age t

ale 7 t Track

o D 5104

C A Cli 69.8m

5 roach

s

5104 m k A 7m 7 7. p Sin

PH

7

12 Track

1 1 Pond

e 5

Hous

m d s ap r k (um) Path 73.8 A View rcha Sin O on 74.1m

ry est ROAD eston

e TCB e RD Be B Cher op

T of Tre

es

ORCHA u s e e ond s

RY I P R on m la 3 rise . Vil

CHE 2 ok ladst 82.3m 8 ank G ro T B

2

al s r u Edg

1 Sink tages (um) n

Cot Path m 7 Agricult e

r LANE N 7. 7 m low ar rf .3

CR age

NERTO t e

2 N W

ot

8 KI

Ov e

Ris C n e r ar W Old

ack Pond amley

Tr Br

8

m

8 m m

7 79.8 8. 8.7

8 BM

5 Track eys n m age i t 3m ot Ch 5. s C

8 d

o 4 sue o Farm l Is W Hal ey l s e tone su s S Bram

I 1

97m

ack Tr 90. m BM 90.2m m 85.6 3 . 93 ond P od CS o es W r su e s 7m I 7. Silv 7 rack T

ack ack

Tr Tr

ack r T Dingle en es r u

Track s

Is War

Bdy ack

r ED T d m n 3 o 0. od P GP o 10 W l

el ack Tr rw d e lv o Si Wo El Sub Sta 77.7m ok o Br on Track Pond Chester Aerospace Park rought Wind Sock B Tank

Weather Hawarden Park Station

SM BM 35.57m

SM CR Sta 32.6m Sub El Tanks

ED ack r B T CHE dy R RY 74.1m ORCHA

RD ROAD

CR

Hall

Hawarden Park

Track Filter Bed (disu se d)

Lodge FB

Bdy

ED CHEST

ER ROAD 20.4m Pond

BM 20.85m rain D Hawarden Broug hton Overflow Issues Brook Bridge

ook d on Br Issues Brought Sinks Un

69.8m CS Pond Airport

ED Bdy FB CS

Dra

in Pond

C

H Haw arden

E

R T

RY rack Airpo rt

O 24.4m

RC Track Sports HA

T RD Ground rack

ROAD

ED

B

dy WB Tank

CR Chy Issues

Wood Fishpon d Wo od Sinks 22.3m

Issues T Tr ank ack Drain BM 8.5m 67.57m Cherry Orchard Broughton Sluice Farm Elm Gab le ROAD age ER t CHEST 45 Tank Cot

House Pond m 67.4m o 28 e ark ro P en B 16 33 od 19.5m akd e BM 18.80m O 9.8m e 11 Park ewo 6 Broughton Shopping Park Whit Gat

39 Ingl Farm 1 15 5 7 11 Drain 34 WAY 17 Drain ST MARY' S Garage

T) 1 R T

B 512 OU AN

C AD 24 5 A 5104 N 4 B 5 OAD D O 125 R CA R Silos L S ANT 1 12 2 12.8m 7 11 15 3 LY 3 DN L 7 A ONE HAL C (

2m ON 12.9 FFOR L ONST LB BM inwi DD CL EDW EN 24 Tr ck 2 LANE (CLEDW EN RO AD) 2 ack CHUR Slurry 1 SIM Lagoon OD 2 lk Vicar CT Jays a S Lodge CH BROUGHT T Pond WO h W 3 rack age St Mary's El Sub S ta ROAD 12 WarWarren Hall, Broughtonon m) Churc 6 BISHOP 23 ath 2 (u Church 20 P

4 Th e Bungalow 149

Issues Issues The Old Tall 2

Pars on age CT 19 Tre es S Track 14 lla 65.2m i OP 15 Aeronautical constraints Park Farm Cot tages ac Son 1 BISH 2 104 1 5 Timber Fishpond Wood Jacm Kin 14 Issues A ley noul K en O Hall Sinks ton sprey 5 L AUGHTON amo Bethany Sinks ur od Ski o 9 2 15 kd BM 10.58m W a AY OAD Chelston R Touchw P d ath a ey 8 9 e n (um) n 13 est Approach surface EATON Spi STONE AD om e H e Th 1 RO CL 1 10 OSE Th 7 SIMON 17.4m MAIN 2 15 11 Birch 1 1 Rise E 03 104 A 5 CHUR 19 RIV 104 D 5 10 CH EL 7 T A 2 R LESM Filling Station rack 15 OAD 1 ER LARNE 2 E 9 1 AV 20 ENU 29 72.2m E 8 4 WYN 20 NSTAY 13 2 137 2 2 20 RO AD Earthwork in a Dr ED 28 Bdy Shelter Fiel 27 El Sub C dsi Key ou 6m d Sta 1. rt e 2 BM 43 127 LANE 21.61m OD 40 Fir Wo od WO 21 l E Youth Sub ta 125 154 Track Club S 3 4 123 14.6m BM 79.18m CHER Path (um) Poli ce 11 Def Cher ry Orchard Ho us e House Cher ry Orcha rd Hous e RY Broughton Path HE O (um) 31 RON Junior and Infants School 146 R Track CHARD Warren Hall site 7 CL LB 15 SID 2 1 2 DEL Gas 1 Pond Dra EY in Gov R CLO O CR 4 S AD OAD 14 E 1 R 3 4 1 73 L 7 Drain 7 7 5 ry HAL 1 8 1 90 8 ON rack Libra T 27 63 10 2 53 CLOSE 18 BROUGHT 2 ts s 12 QU ERON 6 o H P E 134 1 9 Obstacle limitation surface: EN'S 1 W ood Cottage RD 2 6 3 E 19 r 55 e WAY 86 R elt M 1 7 I Sh 53 EADOW 1 SH 16 15 2 3 ON 14 D ic 5 Issues 4 EV ROAD ROA 40 26.5m Clin 12 D Green Lane Farm ELD 2 19 El Sub ENFI 1 Sta HAWKER Approach surface funnel 72 GRE 124 MADEL 17 2 CLOS 9 51 7 El 19 49 E 69 Sub EY 1 CLOS 45 Sta 12 2 2 ry 47 14 1 BM 27.61m 4 14 E 2

ack 2 Pond Surge 43 Tr 14 2 1 1 with contours at 1.0m intervals 60 24 16 12 1 83 17 17 Track Tree 5 26 Pear F arm 13 CR 7 83 8 1 18 5 8 1 1 Pond 89 8 Track ROAD 13 19 MEADOW ORD Pond ROAD 23 IN 35 2 A 2 M LYN 71 2 C 9 2 ONGL 71.6m 9 T R SOMERF 5 TCB ON 1 OA 2 103 102 36 4 P D ET L O A 103 N C E 56 ROAD 2 Rose 27 E 19 BM 90.97m 17 1 1 OS 6 90.2m Cott 7 7 2 1 5 The 5 1 CL 36 Bilberry Wood PH 1 El 3 N FAI 19 Offa's 21 O 119 P Sub Sta 16 1 RFIELD 1 Dyke DENFOR 25 athw 10 RND 1 5 1 4 2 48 (PH) 1 Old W arren 25 4 FA 1 D CL ay LB 2 Silv er W ood 82.3m Cattle Grid 27.4m ROAD 18 27 58 Pond 1 ED 1 2 OAD 2 4 8 3 R B 4 N 5 2 3 dy 1 14 Bowling 3 8 39 3 13 LINGTO 1 13 Green 3 1 13 WEL 8 Shelter 4 4 72.5m 1 2 Brain Injury 8 30 Centre 35 2b 1 1 Hall D 34 2a 37 2 OA 8 89 3 36 16 TCB 147 R 3 38 4 1 N WEBST 32 3 1 12 19 3 SE EVARD 27 4 ER 30 PH 29 Ch imneys 46 CL LANSDOW CLO 1 64.6m 27.4m 2 OAD BOUL Issues R 3 S Seg ar 8 ROAD 37 D 9 e ONE THE 4 16 13 30 CR 4 EL Ec cleston House 28 I 10 7 F Ris Dale 2 Agricultural CH 58.8m 2 6 n 2 4 ED 15 GLADST e Cottage Bdy 24 WATSON' RK r Institute Gladst on e 15 A ar Cottages a COR P 12 79 W Vil la Tre e Garage 2 49 4 2 BM 51.84m 28 Top y 32 ONATI ED 1 19 ar e 2 1 1 2 W arren M ount 48.2m 10 42 age Bdy 60 15 ag Half Ac re t em t 47 t 20 ON t o s 2 o 3 56

e R C Mawr C N ant Cot tages

Ros e Bro ok View 5 1 OAD 71 od War ren Bank Cot tage Ferndal e D 57 o W arren View ghad Allotm ent Gardens 2 CF 5 47 o rw 8 25 L Fi Prim ros e Hil l 5 5 54 Th e Croft 36.6m 4 69 Honeysuckl e Cottage Pond 15 18 2 Sta 49 W arren Bank Farm 12 1 75 1 1 Sub 7 W arren Dale 3 1 El 6 3 16 13 7 12 1 3a 59 3 1 32.3m 7 1 Car O Fer n Bank P 3 50 Old Warren 16 6 7 3 2 2 Park 7 1 Depot Laburn um 1 Brought2 on ROAD 19 FOREST 1 Cottag e Hawthorn LB 1 29.9m 1 9 Cottag e 4 5 C 19a BRET El 84 169 H R D awth 2 43 1 Stone 28.0m 1 2 CLOSE RIVE Taych reg gan o 40 TON E Sub Sta MARTON Shelter rn s 33 10 15 32 DRIVE 8 VAL 2 TRE 1 2 Church Shelter 23 L ROAD E C HAL 65 LOS 13 ON YEW 1 Silverwell Wood W arren Vil las 2 Ty- yn-y-c ae 05m 173 7 BROUGHT 1 12 E Und 2 BM 30. LB 16 12 14 56 Tu dor Oaks 2 7 1 1 36 1 1 1 17 Car Park 34 39 A TCB 2 2 1 1 1 5 ROAD 19 D 5 OL 10 38 M 19 17 7 ROSEMA 7 9 1 El Sub Sta 31 26 12 2 1 3 2a 2 OKERY E 1 MARLWO 24a 24 45 0 24 RO 8 2 RY 20 22 24b OS CL 22b THE 1 2b 1 1 CL 9 OD 3 1 2 9 El 18 3 3 27 1 4 Sub 2 2 1 PL 4 E 2 12 AC BR CL Sta 29 1 4 ROW 70 E 21 ET YAR 2 13 16 SUCKL 36 2 TON 2 34 55 2 RK 4 12 3 HONEY 5104 14 2 24 3 1 A PA B 29 50 3 1 R RO DRIV T E 1 T 14 18 r 5 38 ack 1 1 CAS OK LAN 22 E 2 ES WAY 67 26 34 8 LOW BROAD 2 14 23 WIL W ESTMIN SIMP ARNOLD'S 9 1 AVENU STER ROAD 1 15 16 47 13 HOPE 3 15 6 2 5 34

25 5 S 6 9 13 WIN 2

5 OAK 2 O E CL 7 SANDWO 10 2 N 86 38 R EN S 6 D CO 1 13 27 OAD WAY El C AVENU SOR BRACK 35 16 Sub 1 L

l R Community 2 53 C 1 IN 40 37 1 Sta 26 H DRIVE 9 E Centre W OD Pond R CLOSE E 2 BANK 1 O 2 RY 14 21 E NY OS 1 39 y O DALEEN CL 46 37 AVENU 26 8 P BANK 32 19 9 Lay B D 7 GAL NY AV 7 RO EN W 8 2 P 9 A 4 AD A ENU 5 8 CLOSE 16 R E 9 3

REN 7 1 T 6 1 6 1 8 2 1 1 E 13 y 1 H 10 9 8 2 E B 17 18 Lay 2 8 6 4 OS E 20 CL 67 8 14 16 BLACKTHO 5 BI 36 15 Issues 31 1 DR 1 18 4 14 IV Play RC 79 Path E 42 2 10 77 1 H COPESW Area 4 1 65 5 5 ROAD E 8 ESTON 5 BE 63 ( 10 2 52 S um)

82 RN 2 7 13 3 1 2 65 1 O OD 18 2 CH 17 3 5 8 CLOSE 1 L 2 El 8 66 49 ER 29 56 54 40 CL 23 61 20 Sub Sta 90 70 19 NHIL 5 78 CA

19 6 4

2 6

LYS THOR 16 0 25 L 74 2 1 8 71 2 2 19 2 66 5 17 D RIVE 12

2 14 FOREST 77 15 LB 73 10 7 1 3l 53 CA 8 El Sub GR Sta 1 OAK 75 7 14 91 73a STLEM W arren Bank 1 3 1 7 1 Pond 24 DA SYCAMORE 8 24A 87 2

8 L 26 1 D 49 85 2 8 FIRB E ER Playing Field 83 5 4 rain CHER E RY DALE S ROAD E CL 6

CLOSE 8 Issues CLOS 38 D ECK LO 1 OS

7

52 C E 7

ODFIEL 2 CLO 1 E 56 1 ELD SILV WO

2

S

2 C E E 4 ERFI 91 87 8 77 ROFT R 11

M B 2 85 106 10 2 I 8 RC A 64 55 SUM 1 H 46 9 9 12 A 55 10 ROWANS Brought on Cot tage THE 74 98 86 10 1 Issues 0 1 15

3 25 3

Drain

th (um) A 5104 Pa

A 55 A 55 A 5104 CH (um) Path 68.3m Th e The Old Broadoak The Dov ecot es Dairy Th e Far riers Stables Farm Th e Old Forg e War ren Th e Clockh ous e CR Lodge Coach Hou se

BM 669.81m9.81m Dra Pop ey Th e Old Farmhouse in Pond 5 Cot tag e 2 4 6 3 1 D rain

25 M al t Hous e 24 Yew Th e Gr an ary 23 Tree P Ap plewhit e Cot tag e ath 4 Cot tag e

3 Sheph erds Cot tag e (um) Orcha rd Warren Hall Th e Farm hous e Barn Pond Court 26 27

y 5 Greenways Court 18 72.8m72.8m 10 Lay-b

1

4

LEIC

1 12

7

1 EST

1

ER

5104 LANE

A W arren Hall 2 W arren Hall Attlas Cottag e Cottages T SewSewage Beedd rack 5104 A nel 1 CH TTankank Warren BS Hall 77.7m7m fun Warren Hall Pond Def

Track

rface Issues RH Ponds 2m 1.2 su 47 Track m 82.3m82.3m CF

Def

RH 48 Oak 2m BoatBoat House Oak roach 1.2 m Def p PPondond 1.2 2m RH Def T GGrravelhoavelho llee WoWood Def r Ap ack 49 m RH 1.22m Bdy Pond UA & ER BS Asly 88.8.77m 50 RH 2m Bdy Const, ED 1.2 m Asly Const, Co

Pond Path (um) Pond 51 BS LEIC m EST

ER Pond El Sub Sta

LANE 85.3m CH 52

93.3m m 53 m

CH BS KI N 54 NERTO GP CH N Brookrise LANE m Drain

100.3m BeBeestonest on View Def 5 5 Bdy UA m & y ER sl y A Bd ER Const, E sly 56 A Const, Co

UndUnU

n m CS d Pond Pond 57 Warren Dingle WarWarrenen Dingle

CR m North 73.8m 58 773.83.8m Pond

m CF 0 100 200 300 400 500 metres

Handl ey Hous e

59 CS

ack r m T Pond T rack CSCS Pond Hey Wal l H ous e ED Bdy Yewtreebank 1 Stamford H ous e 60m 2

rack T Old O ak Barns Gell Farm BM 12.54m m Crab Mill Farm 0 Drain GP CCSS Broad Hey 13.0 BM Bramley Hall Farm 61m Shelter TCB Scale 1:10,000@A3 KIN 11.9m Drain A093950-15[B]03 BM 79.8 NERTO 8m Hill View War ren Wood N Bdy LANE Me Hil ED LB Cot Oulton l c ad

r t Drain 11.6m est ag o Brid ge Little e Hi ws F g Borde r i airh hfi de N Tr Far m Hey F Tel Ex Co o r eld Cot tag e W 85.6m ack o A 13.1m 1 rb av 62 n Const, Bridg e Co ttag e sl estc u y H e ry ER n Cot tage aul o & Asly t File: A093950-15drf01.vwx October 2018 UA

LANE m Bdy Const,

C

60.0m S Pond

AMLEY

77.7m BR 5 Mount Farm Kinnerto n E CS Bridge Farm War riston 63m AN

L

Bridg e R Cad hay O Track O

M Kennels Cot tag e Moor creative minds safe hands Th e Bung alow Pond Br amley Cottage Crescent

Hil lside Cot tage E E AD R BM Bdy RO 55.31m 64m 10 MAIN Foot Bridge

The Mount Pumping Station Slurry AD RO Lagoon Issues MAIN

Slurry 1.2 WYG Group 65m Lagoon 2m 51.8m RH

Track Floor 5, Longcross Court, 47 Newport Road, Cardiff, CF24 0AD

Spreads 11.3m 6 Def 6m Tel: +44 (0)29 2082 9200 Fax: +44 (0)29 2045 5321 Pond Collects Newhouse Farm Email: [email protected] www. wyg .com Dr ai 67m E n

AN

L

D

r 1.2 Sta tion F arm ain ER BM 17.86m 2 House m © RH EST 21.6m Tank WYG Environment Planning Transport Limited 2018 C

EI

L RH Th e Bungalow

2m BM 42.17m 68m D 1.2 rain Sto ne Barns Based on the Ordnance Survey map with the permission of the Controller of rain D 17m 25. BM The Rook ery 42.7m Her Majesty's Stationery Office: © Crown copyright and database rights [2018] 69m Kinnerton Farm KIN The Stabl es NE RTO N Pond LA Ordnance Survey 0100031673 ain NE Dr Manor Lodge GP Pond 70 CS Co BM Const, 40.85m rain m D ROAD Def Asly Rosem ount MAIN

ANE Const,

L Issues E E R Asly Bdy

Kinnerton ER BRAMLEY Drain Lodge GP & 28.0m UA

Bdy 11.0m 32.0m

Gr ange Hous e Gwyn's D C ain ert Nook 28.3m Dr ov Brook C e Farm Camp Site Th (disu sed) Drain

Pond Gas Valve Station KIN NERTON Def Warehouse LA NE P

ath

T

rack 28.7m

( 2

u

m) The Pines 1 Dr The Higher ain ain r Royal Oak D (PH) Kinnerton

à

ÿ

@

è

U

?

ç

T

>

ˆ

þ

P

æ

Q

=

S



<

å

‡ ‡ ‡

‡

:;



R

å

; ‡ ‡ ‡ ‡

‡

Q

å

8 9

ß

! !

Þ

þ

A å A

6 7 † " ã

â â

ã ä



NOP

å

! † ! è

   å 

ã è è

â

û

JM

 å    å 

â â â â â

L

á

à

ü

³

G

ÿ

º Ê

²

ß à á

½

Þ

É

¹

JK ‚

a

¼

I Þ ®

à

µ

¸ ¹

H Þ

û \

ÜÝ

ƒ „

$

Þ Þ Þ Þ Þ Þ

µ Þ ±

G

‚

$ > °

²

$ $ $ $ $ $

$

F ·

 

à

ã

â

q

E

®

³

=

†

" è ã

â â

ã

} »

X

³

â

A å å

ã

â

~

²

p

¬

 å 

 µ

?

€

³

Â

     

A † " å å å

è

â â

¯  =

R

m

µ È

R ^

´

Y

í

ß U

à

_

U



þ

û

 

g

¿

<

® Ç

%

²

ß _

d

ò Þ

Q

1

q

p ¼

³

¿

ü

ß Ê

Û





¿

à

£ 

² >

} ÿ

-

Z f

´

ü Ï

Þ

Q

ÿ ¼

=

­

}

Ð 0

ß à

Þ U m

*

Y



 ­

õ ö

8 ¹

Ú

+

€

ß à

Q

¼ ]

T µ

¾

Þ

ÿ



®

¯

. =

û



.

ô

µ ³

¦  u

9 ®

Ý

+

8

y

;

®

-

²

ü º

Þ

>

ü

±

¼

þ

¼

8 ¾

$

º

( 9

ó e *

¤ x

þ



<

þ ¬

d

®



¼

Þ

 º

- Ë q

8

½

·

 ò

9

c

T

º

£ q



º

ÿ

1

}



9

Ý µ

t ­

w

½ ¥

² -'

Æ

~ 

û

7

ß

ü ë

¹

d;

º

*

Þ ±

$ à o f

¼

º



)

à

»

­

[ ­ |

ñ s ;

Ý c

ÿ ÿ

g



³

) ®

t

¤ $

¬

Ý

4 Q

ÿ ¬

Å

r ü

¬

ü º

µ

9

 X

Z

Ù

¬

t

ß þ Ä

q f



ÿ



ß

¯

b

Þ

;

>

Þ

É

t

-

Þ

/

µ

ï ð



à ¹

>

³

8

®

m

ý

0

t

ã

" å

ü ® ! < a ;

*

ï ÿ ¼

 û

= Ã



}

ß

 ³

+

¢

¸ l

¨ þ

Ó



å

! ! è ]

! â !

³

µ }

¿

Ð

_

ü

 °

²

¬

à d

Ò



 9 D

â p

 > =

¤

· ê Á

î à

Ø Ñ

C

µ

û

'

 @

ß

5

®

./

Ï

®

_

º

à 9



à Þ

à > B

- Á

¶ 

â  â  â  â 

â 

³

à Á

Ð

 ?

û  ²

7

à ¤

ã

³ =

©

®

Ð

f

o

, µ

Þ û â  â  

â

¬ 4

í

¾

P

º

<9

Ð

    

" å

! > ` |

â

]

ú ³

³

P  

Ï

#

  _ ³ t

 à  ¨

+ ²

¯

å    

! ! ! ü =

â â 7

o

)

ì

²

Þ

µ Â Î

]

c

å

y

} T {

´ µ

Í

^ > 

*

l ¼

¦ §

®

¸ 0

ë ~

ã

W

£

x

] U

³

9 ³ ½

n

Ì

) A ²

²

ë ¥

<9 > º Z

ù

q

-

l

±

þ ³

\ ¿

3'

q

è

à

Ö ×

_ m

²

° (

(

~

®

[

û

w

Õ

A

j k

Z

¿

£ ¤ € ­

<

¯

) Y

[ Á

é ê Ô Q

³

¬

®

i

å

[

÷ ø  à

®

d

½

9

­ '

2

Z

&'

;

Z

V h

ç ¶

¬ ¡ ¢ Y ®

9 È

Z X

v

¼

X z

« 

; À

Ë

}

” •

¢

“

¥ ¡

¤

¨

W

£

§

V

¦

›

U

‰

x

w

v

š

‰

™

©

‡ ˆ

R

ª

Q

T

p q

S









u

t



Ž









¤ ¥

 





 Œ





© / 0 1

‹



Š

¨



s 



˜

r

—

–

2 3 4

"

!

$

8 9

5 6 7

#

&

%

Y

: ;

(

X

'

ž

*

)

,

’

< = œ 

+

‘

.

-



`

_

^

y z

o

c d e f

n

m

g h

¦ §

¡

Ÿ

} ~

b

a

a

{ |

L

 €

K

Z[

J

N

\]

ƒ „

M

 ‚

†

P

k l

O

i j

> ?

@ A

¢ £

C

B

E F

D

G

I H

Instrument Flight Procedure

Safeguarding

Warren Hall Development

Assessment

Hawarden Airport

14 December 2018

CL-5348-IFP-004 V1.0 www.cyrrus.co.uk [email protected]

Commercial in Confidence Instrument Flight Procedure Safeguarding

Introduction

The Welsh Government, through WYG, have requested an Instrument Flight Procedure (IFP) Assessment on a proposed development site at Warren Hall, Broughton. As the development site is only in proposal phase and forms part of a feasibility study, the assessment considered each building in the development, and reported on the most critical.

The closest point of the development site is positioned approximately 1.58 nautical miles (nm) south west of the Runway 04 threshold at Hawarden Airport (Figure 1). All the relevant IFPs will be assessed and any that are impacted will be detailed in this report.

Figure 1: Distance from ARP

List of data received from client:

• Co-ordinates of each building planned for the development (18 Plots, 25 Buildings)

• Heights of each building shown in drawings (tallest building at 75.00m)

CL-5348-IFP-004 V1.0 Cyrrus Limited 1 of 4 Commercial in Confidence Instrument Flight Procedure Safeguarding

Assessment

In order to conduct the assessment, the lateral coordinates were extracted for each building, i.e. the corner for each building. Once each building was accurately placed the development was modelled against each IFP using specialist software application for the design and assessment of IFPs.

The initial assessment, on the Basic Surfaces, indicated that surfaces were penetrated with the worst- case being the Instrument Landing System (ILS). As a result of the penetration, the Obstacle Assessment Surfaces (OAS) were assessed, the outcome of which is detailed in Table 1.

Assessed Procedure Runway Impact Comments Penetrating but not affecting ILS/DME/NDB(L) No surfaces. LOC/DME/NDB(L) No 04 SRA RTR 2nm No NDB(L)/DME No Visual Segment Surface No Holding 04 & 22 No ILS/DME/NDB(L) No LOC/DME/NDB(L) No 22 SRA RTR 2nm No NDB(L)/DME No

Table 1: Summary of Assessed Procedures

CL-5348-IFP-004 V1.0 Cyrrus Limited 2 of 4 Commercial in Confidence Instrument Flight Procedure Safeguarding

Conclusion

Due to the penetration of the Basic Surfaces, the numerical risk which can be compared to the Target Level of Safety for aircraft operating to a specified OCA/H height, should be established with consideration of all obstacles penetrating the Basic ILS surfaces. The safety process is conducted by running a Collision Risk Modelling (CRM) assessment. It is intended to assist operational judgement in the choice of an OCA/H value and is recommended following this assessment.

The procedure with the lowest OCA is the LOC/DME/NDB(L) for Runway 22 at 450ft. Converting the OCA/H into metres and taking away the obstacle clearance of 50m provides a height of 87.16m. The ILS surface altitude at the critical point (Building Plot 04) is 74.2m, which indicates a maximum height of 74.2m for the development. As this assessment only considered the development as a whole, a further assessment would be required for each individual building against each IFP to determine individual building height requirements.

The OAS analysis indicates that the assessed IFPs are not impacted by the proposed development, however, the development is restricted to a maximum elevation of 74.2m amsl. Although the ILS basic surfaces are penetrated, and the subsequent assessment resulted in the obstacles not affecting the surfaces it is recommended that CRM is conducted for the ILS Approach.

CL-5348-IFP-004 V1.0 Cyrrus Limited 3 of 4

COPYRIGHT © 2018 Cyrrus Limited

This document and the information contained therein is the property of Cyrrus Limited. It must not be reproduced in whole or part or otherwise disclosed to parties outside of Cyrrus Limited without written consent.

Cyrrus Limited is a company registered in and Wales: Company Number 06455336. Registered Office: Cyrrus House, Concept Business Court, Thirsk, YO7 3NY.

A

`

a

µ

I

É

´

H

®

³

_

Å

G

²

È­

t

±

F

ÿ ÿ ÿ

ÿ

°

z

ÆÇ

F

ÿ ÿ ÿ ÿ ÿ

ÿ ÿ

ÿ

¯­

F

­

®

@

€ 

D þ

?

_

F F ƒ ƒ ƒ

I I ‚ þ

I ‚

D E

C

¬ ­

ÃÄÅ

¶ ¶ F

þ ‚ þ

C

F

F ~ F ~ F ~ F ~

C

\

u

¿Â

~ ~ ~ ~ ~ ~ ~

þ   ¶ ¶ ¶ F

‚

C C C C

~

Á

B

A

]a



¼

`

 +



@AB 

ý

?

É

*



¿À ú

Þ

Ö



¾ 

A



 

Ú

½

\ Ñ

= >

û ü

? ? ? ? ? ? ?

? ? ? ?  

?

a

¼

ú

³ 



Ú â

»



ù

}



A

à

º



²



²   F F

‚ I D

ƒ F ¶

‚



C

õ 

Í



C

¶ F

‚ D ‚ ‚

C

€ 

ö þ D I à á 

ë

q 

ß

ø ´



#

þ ~ ƒ ~ ƒ ~ þ ƒ ~ þ  ~ þ þ ~ F ~

D ‚

~ ~ ~ ~ ~ ²



Æ

ç Þ

¡  )

Æ Ò



Î

N

@

A Ó

É

s

_ Ý­

\ z

°

 (

†



@ Ó

?

S



– ¢

à

ë 



­

]a

@

Ô +

t x <

d p A

 ³

õ `

Ï



a 0

]

?

` 

¡ š ²

n

õ 

Š

1

@

? ç

A É

Î

­

Û

s 

VW



;

ø

u

@

A

®

 µ



` ?

t



­



\ ²

y

 ‘

U 



î g o Ç



> Û

Ø

a u

ò

Ÿ 





] 

?

³

] 



_



Û

a Ü

Ø 

T

Ž e ñ

_

n

°

_ Ú



|

t 

?

a 

w

Û , à





š

S t

Ù ®

Ø

 à

d

y 

`

õ

t x

> ê

 Ø

í 

 ð

f

 

ˆ '

ö w

\

Ç

L a @

]

Ú  

ž

? 

— é â

A





÷



A

Ç 

Ð  ±

ì

R

> Ù

`

` a

Þ

w





í

e

m

}

A

>

Œ

`

‹ &

ß ]

]a





| Í

ÏØ

­

œ 

:

í

%

@_ a â

à

`

|

l

@

Ç 

×

?

³

?

*

í



?



« a

›

P Q

} 

A

š ³



Û



ç

^

Ç

í



ƒ F € ƒ x F €

 ] ‚ ° Ö 

Ž ª

P `



w \

² $

t

õ

@



c

¯ 

i

_ 4

|

F

€ €

‚ ‚ I I µ

‚ C ‚



õ 

1

Õ

]

©





Ú

A ™ š

3

€ t

 ÷ ¹

C ë Ø

|t

e ³ ²

K k

" 

O

A v

9 2

¸



\

ˆ

t

Õ

@ 



¨ 0



Ó



u

A y

? ê

A · ³ Ø

A "



C  C  C  C C  C  C  C 

 

A "

1

t

\ ´



e

A D

 ²

j



â 1

é

a 

?\

C  C  C 

Œ

N

Å



° 1

~ ~ ~ ~ ~ ~ ~ ~

ƒ F €  ƒ F Ø

‚ ‚ ³ Ô ±

C

µ

[  

˜—

êÅ s t u

0

„

u t t Ó  í

{ { i

A



F ~ € ~  ~ € t 

‚ ‚ ‚ I I ] ²

C C

é

M



?

 # /

µ

Ù

F

ò

® ô

õ



 § —

.

Ò ³



¯ 

g h



 Š ‹

L ö

D

Ì

d

ñ

µ

É



 

è

Ø -

– —

¶ 



L f

 Ï

° ³ ¥ ¦

Z Ø

à

 •

¯

 

_

Ñ

‰

ˆ

à

I

7 8

Ó ç A



Ë



ö ¤



Ð

\

ð

6

å æ

Ï

d e ø 

°

 a

Î

Ð "

JK 5



“ ”

ä 

F

£

Ð

XY r

A 

Ú­





Ç Ø

‡ ˆ

Ï

Ï

Ê ‹ ã

H 

Î b c 

)

Í ÏØ

’ ï

Ç 

Í ó

q

!

,

õ



™

˜

œ

—

›

Ë

š

ë

ê

Ÿ

ž



­

¢

é

¡

è

ç

¬

î

«

í

ì

¥

¤

® ¯ °

£

¨

³

§

ï ð ñ

¦

²

±

©

©



ª

´ µ ¶





§ ¨

©



¦

©













¢

¡





¼

»

º



£ ¤ ¥





z { |

· ¸ ¹

 } ~ 



! "

%

$

#

ó ô

v

u

õ ö ÷

u

ò

ÐÑ Ò

(

'

&

+

¿

*

)

ú

¾

.

-

,

† ‡

½

à ÄÅ

ø ù

1

ˆ ‰ Š

0

/

4

3

‹ Œ 

2

4

5

2

8

(



Ž 7

6

 ‘ 

Â

Á

À

;

:

’ “ ”

9

ß à á

>

=

<

Ø

A

Ö ×

@

?

ý þ ÿ

û ü UV W

û

C XY Z

ÜÝ Þ

y

x

B

w

B

Û

[\ ]

Ú

F

E

D

Ù

^ _ `

¢

a b c

¡

Ó Ô Õ

d e f

Æ Ç

g h i

H

G

j k

j

£

• –

â ã ä

Å

€  ‚

J

I

l m n

L

o p

K

ƒ „

Ë

Ê

N

M

Ï

Î

P

r

¨ ©

O

q

R

Q

T

s t

S

ÈÉ

§

¤ ¥ ¦

å æ

Í Ì AIRBUS

Clwyd Roberts Ian Crawford Department for Economy and Transport T +44 1244528292 Welsh Government E ian.ia.crawford @airbus.com Llandudno Junction LL31 9RZ Our Reference: Warren Hall IFP Response Your Reference:

l5 January2019 Warren Hall Development

Dear , Thank you for your e-mail dated 7th January 2019.

As discussed in our meeting on the 14h November 2018, the initial 1FFassessment results are encouraging which can now allow for further design work for development of the site.

At present the Hawarden Aerodrome Management Team require the next steps to investigate the extent of the risk to operations as follows:

• IFP further impact assessment Cyrrus require a detailed site plan for them to consider potential buildings as a whole to determine individual building height requirements and impact on IFFs and ILS basic surfaces.

• Collision Risk Modelling Due to penetration of ILS surfaces, Cyrrus will be required to carry out a CAM (Collision Risk Modelling assessment) to assist in determining the obstacle clearance altitude (OCA).

• Assessment of Dominant Obstacles I Type A Chart Hawarden Aerodrome Management Team will need to assess any dominant obstacles that may appear due to this development on the Type A chart and assess the risk to operations accordingly.

• Assessment of Approach Slope 04 An assessment is needed to identify any possible infringement of the 1:50 surface and proposed mitigation measures in order to maintain EASA compliance.

• Assessment of Take Off 22 Assess impact on the take-off surface for runway 22.

• Beluga ST I XL Flight Performance It is necessary to liaise with ATI (AirTransport International) to ensure that the Beluga ST and the new Beluga XL flight performance is not impacted due to this development.

The next steps above are reliant on a detailed indicative plan and so Hawarden Aerodrome would be grateful of any plans being given to us at the earliest time possible to assess these risks in collaboration with yourselves.

C Aches Ops’u”onsji eu 20th At ng’ts ‘esened Dc’aessw ed ovpenlsry xseweenl Thisdoc.’eeel at’s all “‘CaisSonccntsinedne’eir. site sue p’ope’tya AthusOperaioesLr’ted \o ‘Ieel,.at prcpery e”u we slanted b, ‘he Ce:ver/ eta dx’re” a he uls0000re c Is coxce—his documentshallnut be reprndunedon hedsoed an ha oaThwithout he excess shin” csnseh a’ Ai’OuuCpetahcxauL‘Med Thisa,rser’ and its coin” nsa no: be used tat an,’ cutpcse a:twn hat’Au: Ia’whichills supzed

Airbus Operations Limited Registered in England &Wales Cheater Road Compar.y No. 3468788 Broughton. Fantshire. CH4 ODR Registered Office Pegasus House Phone 44 (0) 124 452 0444 Aerospace Avenue. Filton Fax +44 0)124 452 3000 Bristol, BS34 7PA 2 the any Dy tar this Page used itrsr,Ied be on are net ‘grts sirs talent posaty its and information ‘:ellecOaal No tenure’: This Lrritnd. further United Cperatons Ooera2c’s Arrcos a receiving Citrus ci prO:nrry to sale terser” ne is white’ reran forward a.sprass ‘an ha costa look arthci: Response pa’ty rnisnniatrora we - rd a IFP ann 10019 and Hall dctr’re’: isdcsan S or ‘rn, Engineer Warren Ltd reooaiazed doemetr Tn ret proone:ary stat Reterence correspondence and 2019 doau’rent Safeguarding Operations This Ooefider:a and non:eqt January continued resersed. iT Airbus ct 15 ng”ts of ersphed. Cii is your II Date &sAcssre 2319 iha nob or for Compliance behalf ICr taed. L //--- ‘ha on crs Crawford dctrrra’r you Iran ha Ian Opeat Other it and Crawford Toy Aiross From dn DUrposa ©

Regards For AIRBUS development. Aerodrome Thank lan