Tunnelling and Underground Space Technology 29 (2012) 10–30
Contents lists available at SciVerse ScienceDirect
Tunnelling and Underground Space Technology
journal homepage: www.elsevier.com/locate/tust
Shallow tunnelling method (STM) for subway station construction in soft ground ⇑ Qian Fang a,b, Dingli Zhang b, Louis Ngai Yuen Wong a, a School of Civil and Environmental Engineering, Nanyang Technological University, Singapore 639798, Singapore b School of Civil Engineering, Beijing Jiaotong University, Beijing 100044, China article info abstract
Article history: This paper provides an in-depth illustration of the shallow tunnelling method (STM) used for tunnelling Received 2 May 2011 in shallowly buried soft ground. Limited arching effect and limited ground strength mobilization are the Received in revised form 30 November 2011 two mechanical characteristics of the STM. The stability of the cutting face and the dry tunnelling condi- Accepted 28 December 2011 tion are the two preconditions that should be satisfied for the STM. Some ‘‘necessary’’ auxiliary methods Available online 30 January 2012 mainly served to guarantee these two preconditions are highlighted. Five principles, namely proper aux- iliary methods, sequential excavation with short advance length, rigid support with quick installation, Keywords: short ring closure time and systematic deformation monitoring, which are required to follow when using Shallow tunnelling method the STM are summarized. The state-of-art of the STM is classified into five different construction Soft ground tunnelling Subway station construction approaches according to tunnelling sequences, which are adopted in the construction of the nine subway Sequential excavation stations in Beijing. The tunnelling procedures, support measures and settlement characteristics associ- Ground surface settlement ated with excavation are demonstrated. Statistical analyses of the settlement data of 342 ground surface Numerical simulation monitoring points above these nine stations are performed to illustrate the ground deformation charac- teristics of the STM. Numerical simulations are also employed to study the ground deformation charac- teristics of different construction approaches under the same geological conditions. This paper systematically demonstrates the applicability of STM in theory and practice. It is helpful in updating the database of the world tunnel projects and serving as a practical reference for future similar projects. Ó 2012 Elsevier Ltd. All rights reserved.
1. Introduction possible extent by allowing a controlled ground deformation (Brown, 1981; Sauer, 1988; Will, 1989; Health and Safety Execu- The New Austrian Tunnelling Method (NATM) has become very tive, 1996). Institution of Civil Engineers (ICE) claimed that any soft popular for tunnel construction all over the world due to its tech- ground application of NATM is associated with the following nical feasibility, safety and economic competitiveness. This method principal measures: (1) Excavation stages must be sufficiently is based on the principles established by Rabcewicz (1964, 1965) short, both in terms of dimensions and duration. (2) Completion for the use of shotcrete as a support system in tunnel construction, of primary support—in particular, closure of the sprayed concrete together with observational method to determine whether the ‘‘ring’’ must not be delayed. Since these two measures are not support system is sufficient. The use of NATM in soft ground was compatible with the original NATM philosophy for soft ground, largely pioneered by Professor Müller for the Frankfurt Metro con- ICE proposed a different title of Sprayed Concrete Lining (SCL) struction in 1968 and was later further developed by London instead of NATM for soft ground tunnelling (ICE, 1996). Underground in the early 1990s. The NATM was first introduced to China at the end of 1960s. It Although the NATM has achieved remarkable successes (Tauern was widely used after the construction of the Dayaoshan railway tunnel, Arlberg tunnel, Inntal tunnel, metro Rankfurt, Schweikheim tunnel (double track, 14.3 km in length, constructed from January tunnel, Tarbela caverns) all over the world (Kolymbas, 2005), as 1981 to November 1988). This method was first adopted for soft many of the NATM’s recommendations were already in use, there ground excavation in the construction of the Jundushan railway exists some confusions and conflicts (Karakus and Fowell, 2004). tunnel (double track, 8.5 km in length, constructed from January One debate of the NATM is whether it is suitable for soft ground 1985 to August 1988). This method was first used for shallow sub- construction (Brown, 1981). It is widely accepted that one of the way tunnel construction in the Fuxingmen U-turn project (445 m major principles of the NATM is the deliberate mobilization of single track, 262 m double track, 7.0–14.9 m tunnel span, 9–12 m the strength of the ground around a tunnel to the maximum soil overburden, constructed from May 1986 to May 1987). These three projects are regarded as the milestones for the NATM used in China. During the Fuxingmen U-turn project construction, ⇑ Corresponding author. Tel.: +65 6790 5290; fax: +65 6791 0676. tunnelling in shallowly buried soft ground was found to be greatly E-mail address: [email protected] (L.N.Y. Wong). different from tunnelling in solid or fair rock, although the
0886-7798/$ - see front matter Ó 2012 Elsevier Ltd. All rights reserved. doi:10.1016/j.tust.2011.12.007 Q. Fang et al. / Tunnelling and Underground Space Technology 29 (2012) 10–30 11
Ground surface (P /σ )×100 σ i 0 0 Legend 100 O σ Legend 0: in-situ stress GRC for ur σ Pi: support pressure Bt: tunnel width natural ground 0 r: tunnel radius Pi 2r Ht: tunnel height 80 ur : radial displacement W W: arching zone width D: arching zone height A c d SCC 1 H H: tunnel overburden depth 60 SCC 2 SCC 3 D 40 C D loosening B
(Zone of arching) 20 E GRC in the presence of ground reinforcement
EF (ur/r)×100 Ht 0 ab 012345
Bt Fig. 2. Schematic representation of ground-support interaction curves.
Fig. 1. Configuration of ground arch (after Terzaghi, 1946).
Although great construction achievements have been made by using the STM, limited research papers on this topic have been construction techniques adopted for these two ground conditions published in international journals (Xiang et al., 2005; Fang et al., were more or less the same. Therefore the name ‘‘shallow tunnel- 2011). In order to bridge the gap between practice and research, ling method’’ (STM) was assigned by the Ministry of Construction this paper provides an in-depth illustration of the STM. In this pa- of the People’s Republic of China in 1987 to distinguish it per, the two mechanical characteristics of the STM which distin- from the NATM. This method has been widely used in subway guish it from the NATM are first illustrated. The two necessary construction in densely built urban areas in many cities in China preconditions of the STM are then explained. Next the auxiliary since then, such as Beijing, Shanghai, Guangzhou, Shenzhen and methods which are used to guarantee the two preconditions of Hangzhou. the STM are demonstrated. After that the underlying principles of
Table 1 Classification of typical auxiliary methods. 12 Q. Fang et al. / Tunnelling and Underground Space Technology 29 (2012) 10–30
8mm injection hole 0.1m
0.35m 2.5-3.5m 42mm (a) Forepoling pipe
Forepoling with grouting Forepoling pipe I 10-30° VII III I 0.5m or 0.75m III II VII Arc-shaped top heading II
0 Support . 3 Support core - core 0 . 5 m 6.3m Bench + Invert VI IV IV VI V V
6.0m Determined by monitoring 4-5m (b) Typical layout of forepoling
Fig. 3. Example of forepoling.
sults are presented to compare various sequential excavation approaches.
Arc-shaped top heading t 2. Insights into the STM n e m e ) rc In China, soft ground tunnels are generally shallowly buried, fo m Support core n 3 i = particularly common for urban subway construction in soft re L g n 2 ground. The associated tunnelling techniques dominated by using ti 4 o Φ Bench + Invert o ( manpower-excavation are collectively referred as STM. F e il p The STM is a concept or philosophy for tunnelling in soft ground rather than a set of excavation and support techniques. It is differ- ent from the NATM with regard to the design philosophy, although the former also adopts some of the widely used techniques such as sequential excavation, ground reinforcement, shotcreting, moni- toring as in the NATM. Fig. 4. Typical layout of footing reinforcement pile. The critical overburden depth, which distinguishes the shal- lowly buried conditions from the deeply buried conditions, is the STM based on the engineering practices are elaborated. Fur- obtained by considering whether the arching effect can be ade- thermore nine subway stations using typical sequential excavation quately developed. Under deeply buried conditions, the arching approaches of the STM together with their on-site monitoring zone heights are assumed to be unchangeable. While for shallowly results are shown respectively. Finally numerical simulation re- buried conditions, the failure zones are easy to extend to the
Φ108 steel pipe
0.3-0.4m
1
.
5 °
Φ108 steel pipe Support core
Fig. 5. Typical layout of pipe roof protection. Q. Fang et al. / Tunnelling and Underground Space Technology 29 (2012) 10–30 13
Tunnel crown Grout pipe
Primary lining
Fleece Sealing membrane Grout pipe Secondary lining
Fig. 6. Typical layout of contact grouting.
Table 2 Information about Line 4, Line 5 and Line 10 of Beijing subway.
Line Year opened Length (km) Number of stations Number of stations using different construction method STM Open cut method (OCM) STM and OCM Above ground Line 4 2009 28.2 24 6 12 5 1 Line 5 2007 27.6 23 4 7 5 7 Line 10 2008 24.7 22 8 9 5 0
ground surface. According to the Code for Design on Tunnel of Rail- Method (CCM), which is a widely used tool for preliminary assess- way (TB10003-2005, 2005), the critical overburden depth is con- ment of convergence potential and support requirements for circu- sidered to be 2.5 times of the arching zone height obtained by lar tunnels in a variety of geological conditions and stress states the deeply buried conditions. In practice, this critical overburden (Carranza-Torres and Fairhust, 2000; Oreste, 2003), is conducted depth is commonly considered to be 4–6 times of the tunnel diam- to illustrate this key principle. The CCM basically consists of the eter as the arching zone height varies with different soil conditions. definition of the internal support pressure (Pi)–radial displacement The arching effect is illustrated in detail below. (ur) relationship on the boundary of a circular void that represents the tunnel. This relationship is indicated by the Ground Reaction 2.1. The mechanical characteristics of the STM Curve (GRC). The Support Characteristic Curve (SCC) can be con- structed from the elastic relationship between the applied stress 2.1.1. Limited arching effect Arching effect is one of the most universal phenomena encoun- tered in soils both in the field and in the laboratory (Terzaghi, 53 Elevation (m) 1943). Arching can be best described as a transfer of stresses be- Back fill tween a yielding mass of geomaterial and the adjoining stationary 51 members induced by stress redistribution. The shearing resistance Sand tends to keep the yielding mass in its original position resulting in 49 a change of the pressure on both of the yielding part’s support and 47 the adjoining medium. The concept of arching is illustrated in Fig. 1 Silty sand (Terzaghi, 1946). Due to arching, the height of the relatively loose 45 overburden above the tunnel roof resulting from the excavation of Silt the tunnel is D (the height of the arching zone) instead of H (the 43 overburden depth). The limitation of this practice is that it lowers Silty clay 41 the strength of the rock mass and permits a significant roof conver- Clay gence, which mobilizes a zone of loosened rock mass above the Water 39 tunnel roof. Despite all these limitations, arching effect does play table Gravel an important role in reducing the load on the roof support of a 37 deep tunnel. However, for a shallow tunnel in soft ground, the Clay arching effect may not be adequately developed to enable an arch 35 5.8m to be self-supporting above the excavation. Therefore, under this condition, the support may actually carry a significant portion of Fig. 7. Typical geological profile of a tunnel section. the ground directly above the roof.
Table 3 2.1.2. Limited ground strength mobilization Physical and mechanical properties of soils. The philosophy of the NATM relies on the mobilization of the strength of the ground by allowing a controlled deformation. For Specific Elastic Poisson’s Cohesion Friction weight modulus ratio (kPa) angle (°) the STM, however, the ground settlement should be strictly con- 3 (kN/m ) (MPa) trolled instead of being readily mobilized. This is of paramount Backfill soil 18.0 10.5 0.32 20.0 14.0 importance for shallow tunnelling under densely built urban area, Sand 19.5 30.0 0.29 – 25.0 since excessive ground settlement may cause tunnel cave-in, and Silt sand 20.5 25.0 0.24 18.5 29.0 bring negative effects or even damages to the existing nearby Silt 20.0 16.0 0.28 23.0 27.0 structures and utilities. Therefore the key principle for the STM is Silty clay 20.0 35.0 0.29 32.0 17.0 to control the ground deformation in order to guarantee the tunnel Clay 21.0 30.0 0.32 40.0 20.0 Gravel 21.5 75.0 0.22 – 42.0 stability and the environmental safety. Convergence-Confinement 14 Q. Fang et al. / Tunnelling and Underground Space Technology 29 (2012) 10–30
6.5m 6.5m
Back fill LMR Φ114 roof pipe Key
Silt 5.5m Ground settlement monitoring point Φ42 grout pipe Φ1000 cylindrical steel column Silty clay
Silt 3.6m 25cm temporary support
Water
table 3.5m 60cm secondary lining Sand
16.3m Floor slab
4.5m 30cm primary lining
Silty clay 4.7m Sand
Gravel 22.6m
Fig. 8. Cross-section of the Puhuangyu station.
1 5 5 2 6 6 3 7 7
4 8 8
(a) Stage 1 (b) Stage 2 (c) Stage 3 (d) Stage 4 (e) Stage 5
Fig. 9. MDA used in the Puhuangyu station.
and the resulting convergence for a section of the support in the longitudinal direction of the tunnel. By making a significant and 0 Stage 3 - Stage 5 possibly debatable assumption that the support application does not change the ground response, the tunnel-support system -50 reaches equilibrium at the point where the GRC and the SCC inter- Stage 1 & Stage 2 sect. The curve GRC I in Fig. 2 represents the condition of natural -100 ground. The beginning point O of GRC I represents the condition
that for the internal pressure equal to the far-field stress r0.As -150 L there is no change in the initial stress and strain state around the R void, the radial displacement of the wall is zero. With a decrease -200 M of the internal pressure, the radial displacement of the wall in- -250 creases. The initial deformation is linear. It becomes curvilinear Ground surface settlement (mm) 2003/11/1 2004/2/1 2004/5/1 2004/8/1 2004/11/1 2005/2/1 2005/5/1 2005/8/1 upon reaching point A, which indicates the onset of plastic defor- mation. Beyond point B, with excessive displacement, the disinte- Date gration of the surrounding ground may cause cave-in and hence Fig. 10. Measured ground surface settlements. disasters. Therefore, under this condition, it is necessary to take
Back fill 2.8m Lateral rainwater pipe branch Silt Longitudinal rainwater pipe branch
3m Vertical rainwater well Φ1200 rainwater pipe
Fig. 11. The rainwater pipes above the tunnel. Q. Fang et al. / Tunnelling and Underground Space Technology 29 (2012) 10–30 15
L 0 R M Stage 3 - Stage 5 -50
-100 Stage 1 & Stage 2
-150 Ground surface settlement (mm) 2004/1/1 2004/4/1 2004/7/1 2004/10/1 2005/1/1 2005/4/1 Date
Fig. 15. Measured ground surface settlements.
Fig. 12. Temporary vertical steel bar support. gravel. Two preconditions, namely stability of the cutting face suitable ground reinforcement measures before tunnelling to guar- and dry tunnelling condition, must be satisfied when using the STM. antee its stability. The GRC II is derived in the presence of ground reinforcement, where ‘‘detrimental loosening’’ is prevented. With 2.2.1. Stability of the cutting face the installation of ground reinforcement, the ground deformation Generally, the self-stability of the shallow tunnel in soft ground and the load on the support can be greatly reduced. Even though is very limited. It is impossible to tunnel through a cutting face the ground is reinforced, a stiffer support with installation with a very short stand-up time. Therefore, suitable measures immediately after excavation is still preferred (SCC 1 is preferred should be taken to guarantee a long enough stand-up time for to SCC 2 and SCC 3) for shallow tunnelling in soft ground, espe- the cutting face and the unsupported span before the support takes cially in the densely built areas, where strict ground deformation action. control is required. 2.2.2. Dry tunnelling condition 2.2. Preconditions for the STM For shallow tunnelling below the groundwater level or in the water-bearing ground, dry tunnelling condition should be guaran- Using specific construction techniques, the STM allows shallow teed. Dry tunnelling condition is essential in maintaining the sta- tunnelling in soft ground conditions, such as silt, clay, sand and bility of the cutting face by avoiding the mechanical properties
7m 7m
Back fill LMR Key Silt Ground settlement monitoring point Φ Φ 7.4m 42 grout pipe 108 roof pipe Φ800 cylindrical steel column Sand
25cm temporary support 2.61m Water table 60cm secondary lining 3m Floor slab Silt 30cm primary lining 3m
Silty clay 15.06m Silt 3m
Silty clay 2.91m Sand 23.78m
Fig. 13. Cross-section of the Tiantan Dongmen station.
1 3 11 11 2 4 12 12 5 7 13 13 6 8 14 14 9 10 15 15 (a) Stage 1 (b) Stage 2 (c) Stage 3 (d) Stage 4 (e) Stage 5
Fig. 14. MDA used in the Tiantan Dongmen station. 16 Q. Fang et al. / Tunnelling and Underground Space Technology 29 (2012) 10–30
5.0m 5.0m 5.0m 5.0m 1.7m 1.7m 1.7m 1.9m 1.9m 1.8m 1.8m 1.8m 1.8m 1.9m 1.9m 1.7m 1.7m 1.7m 5.0m 5.0m 5.0m 5.0m
Back fill Key Ground settlement monitoring point
Φ Φ Silt 7.9m 32 grout pipe Φ121 roof pipe 800 cylindrical steel column
Backfill concrete Sand 30cm primary support 5.1m Gravel 60cm secondary lining Floor slab Φ800 Bored and cast-in-place pile Silt 3.55m 17.15m
Silty clay 2.4m 25cm primary support Water table 5m
Gravel
26.4m
Fig. 16. Cross-section of the Xuanwumen station.
5786
1 3 4 2
(a) Stage 1 (b) Stage 2 (c) Stage 3
(d) Stage 4 (e) Stage 5
Fig. 17. PBAA used in the Xuanwumen station. deterioration of the surrounding ground due to water inflow and objectives—crown stabilization, cutting face stabilization, footing increasing the effective stress of the surrounding ground. Further- stabilization, ground water control and ground (existing nearby more, dry tunnelling condition could also improve the under- ground working environment, hence increasing the working efficiency and decreasing the unsupported time of the free span be- 0 hind the cutting face. In practice, these two preconditions cannot be always satisfied. -10 Therefore, one or more auxiliary methods for the STM, which are -20 illustrated below, should be adopted. -30 Stage 1 (drift 1&drift 2) Stage 1 (drift 3&drift 4) 2.3. Auxiliary methods for the STM -40 Stage 1 (drift 5&drift 6) Stage 1 (drift 7&drift 8) -50 Stage 2 An auxiliary method is a construction method of a secondary or Stage 3 Stage 4 & Stage 5 special nature adopted to ensure tunnel construction safety and -60 Ground surface settlement (mm) surrounding environmental safety, where either conventional sup- -30 -20 -10 0 10 20 30 port patterns or sequential excavation measures do not provide Distance from centerline (m) effective solutions or where they are not advantageous (Japan Soci- Stage 1 Stage 2 Stage 3 Stage 4&5 ety of Civil Engineers, 1996). Date Sep,2004 Jan,2005 Mar,2005 Jun,2005 Feb,2006 Table 1 lists some typical auxiliary methods currently used in the STM. These auxiliary methods are classified according to their Fig. 18. Measured ground surface settlements. Q. Fang et al. / Tunnelling and Underground Space Technology 29 (2012) 10–30 17
8.8m 8.8m
Back fill
6m Φ32 grout pipe Φ159 roof pipe
35cm primary support Silty clay
Φ1000 Bored and 6.06m cast-in-place pile
Water Φ table 800 cylindrical steel column 80cm secondary lining 4.2m
Gravel 18.47m Floor slab
3.52m 35cm primary support
Sand 4.69m Gravel 26.46m
Fig. 19. Cross-section of the Huangzhuang station in Line 10.
7 8 6 5 9 10
3 4 2 1
(a) Stage 1 (b) Stage 2 (c) Stage 3
(d) Stage 4 (e) Stage 5 (f) Stage 6
Fig. 20. DPCAA used in the Huangzhuang station in Line 10. structure) movement control. Most auxiliary methods have more than one function in the STM; and all these methods, except the drainage methods, serve the purpose of limiting ground settlement. More than one auxiliary method is often adopted simultaneously. Some auxiliary methods, such as forepoling, footing reinforcement 0 L bolt (pile), pipe roof, and contact grouting, are widely used in the R M STM due to their efficiency and cost-effectiveness. In this way, the -20 auxiliary methods are not only auxiliary but also necessary for the STM. These ‘‘necessary’’ auxiliary methods are further discussed -40 Stage 3 - Stage 6 below.
-60 Stage 1 & Stage 2 2.3.1. Forepoling Grouting type forepoling is commonly used in the STM. Forep-
Ground surface settlement (mm) -80 oling pipes (Fig. 3a), steel, U42 (or U32), 2.5–3.5 m length, are dri- 2005/4/1 2005/7/1 2005/10/1 2006/1/1 2006/4/1 2006/7/1 2006/10/1 ven at an angle of 10–30° with the tunnel longitudinal axis into the Date ground above the top heading arch ahead of the cutting face. The separation of the forepoling pipes in the tunnel cross section is Fig. 21. Measured ground surface settlements. 18 Q. Fang et al. / Tunnelling and Underground Space Technology 29 (2012) 10–30
6.5m 6.5m
Back fill
Sand 8.24m Φ42 grout pipe Φ108 roof pipe 35cm primary support
Gravel 30cm temporary support Φ800 cylindrical 3.81m steel column
Silty clay 2.5m 9.91m 60cm secondary lining
Gravel 3.6m Water 22.08m table
Fig. 22. Cross-section of the Jiaomen west station.
1 3 7 7
2 4 8 8
5 6 9 9
(a) Stage 1 (b) Stage 2 (c) Stage 3
(a) Stage 4 (b) Stage 5
Fig. 23. MDA used in the Jiaomen west station.
about 0.3–0.5 m. The distance between the exposed ends of two 2.3.3. Pipe roof protection adjacent loops of forepoling pipes along the tunnel is 1–1.5 m, The pipe roof protection consists of installing, prior to the tun- which is 2 or 3 round lengths of the top heading. Fig. 3b shows a nel excavation, a series of steel pipes, parallel (or at a certain angle) typical layout of forepoling. Forepoling is very effective to enhance to the tunnel axis around the periphery of the tunnel. The steel the stability of the free span and prevent the failure from extending pipes are installed by horizontally boring or ramming at portals. to the ground surface during construction.
0 2.3.2. Footing reinforcement bolt and pile Footing reinforcement bolting and piling consists of installa- tion of downward-facing small diameter steel pipes with grouting Stage 3 - Stage 5 -10 or bolts at the footing of the primary supports. Compared to foot- L ing reinforcement bolt, footing reinforcement pile is more com- R monly used in China. For the footing reinforcement piling, U42 M steel grout pipes, 2.5–3.5 m in length, are driven diagonally -20 Stage 1 & Stage 2 downward into the side ground at the foot of the top heading pri- mary support. Fig. 4 shows a typical layout of the footing rein- Ground surface settlement (mm) forcement pile. This method is helpful to bring the support 2006/11/25 2006/12/25 2007/1/25 2007/2/25 2007/3/25 2007/4/25 2007/5/25 capability of the steel grid into full action soon after installation. Date It is also useful to prevent any potential collapse during the fol- lowing bench excavation. Fig. 24. Measured ground surface settlements. Q. Fang et al. / Tunnelling and Underground Space Technology 29 (2012) 10–30 19
7.0m 7.0m
Back fill Key Ground settlement monitoring point
Silty clay 12.52m Φ Φ42 grout pipe 159 roof pipe 35cm primary support Water table 30cm temporary support Sand 5.23m Φ800 cylindrical Gravel steel column 11.45m 3.2m 60cm secondary lining
Sand 3.02m
Gravel 24.06m
Fig. 25. Cross-section of the Huangzhuang station in the single-deck part of Line 4.
1 3 1 3 2 5 2 5 4 6 4 6
(a) Stage 1 (b) Stage 2 (c) Stage 3
(d) Stage 4 (e) Stage 5 (f) Stage 6
Fig. 26. SDA used in the Huangzhuang station in the single-deck part of Line 4.
The voids between the surrounding soils and pipes, and the pipes unintentionally created during tunnelling. As the voids induced themselves are then grouted. Commonly, U108, U114, U127 and by the STM generally occur between the primary lining and the U159 pipes are used. However, large diameter pipes (e.g. U300, surrounding ground, and between the primary lining and the sec- U600) may sometimes be adopted. An individual pipe of the ondary lining, there are two types of contact grouting. pipe roof is either a single pipe or assembled by welding or screwing multiple pipes together. The pipe roof should be longer than 10 m in view of the efficiency and cost-effectiveness. The maximum length of a pipe roof can be up to 150 m, which means -10 that the entire subway station is under the protection of the pipe L1 M1 R1 L2 M2 R2 L3 M3 R3 L4 roof. Fig. 5 shows a typical layout of the pipe roof protection. This -20 M4 R4 L5 M5 R5 method plays an important role in controlling the potential cave-in during excavation and is very useful in reducing both the -30 magnitude and the lateral extent of the ground settlement. This -40 method is widely used at tunnel portals, other types of tunnel junctions and for the protection of neighboring structures such -50 as buildings, pipelines, and existing tunnels. -60 Before construction Stage 1 Stage 2 Stage 3 & 4 Stage 5 & 6 2.3.4. Contact grouting -70 Ground surface settlement (mm) Grouting is used for various purposes during shallow tunnelling 2007/1/25 2007/5/3 2007/7/1 2007/7/23 2007/9/25 in soft ground. Among which, contact grouting, which plays an Date important role in controlling ground settlement, is highly recom- mended. Contact grouting is the process of filling voids that are Fig. 27. Measured ground surface settlements. 20 Q. Fang et al. / Tunnelling and Underground Space Technology 29 (2012) 10–30
2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m
Back fill
Φ42 grout pipe Φ108 roof pipe Silt 7.09m 35cm primary support 30cm temporary support Silty clay Φ
3.15m 800 cylindrical Water steel column table 2.99m Silt 9.47m 60cm secondary lining
Silty clay 3.32m 21.64m
Fig. 28. Cross-section of the Liujiayao station.
1 3 7 7
2 4 8 8
5 6 9 9
(a) Stage 1 (b) Stage 2 (c) Stage 3
(d) Stage 4 (e) Stage 5
Fig. 29. MDA used in the Liujiayao station.
One type of contact grouting involves grouting between the pri- 2.4. Principles of the STM mary lining (or temporary lining) and the surrounding soils using pre-embedded pipes (Fig. 6). Since lattice girder and wire mesh Since the STM is mainly used for tunnelling under densely built are used in the primary lining, the shotcrete must be sprayed urban area, the primary aim of this method is to control the ground through the girder and the mesh. Due to uneven spraying and deformation in order to guarantee the tunnel stability as well as rebounding of some shotcrete off the bars, voids are inevitably left the environmental safety. The underlying principles of the STM behind the individual bars, especially on the tunnel crown. These based on the engineering practices are elaborated below. existing voids may extend and collapse in the course of tunnelling, which will lead to a disturbance to the ground above. Moreover, stress concentration induced around these voids may crack the pri- 0 mary lining locally. This kind of contact grouting is helpful in sta- bilizing the ground above the tunnel crown during construction -10 and ensuring the primary lining in full contact with the surround- ing ground to allow an effective load transfer. -20 Another type of contact grouting involves injecting grout be- -30 tween the primary lining (waterproofing membrane, to be more accurate) and the secondary lining (Fig. 6). Due to the gravity- -40 Stage 1 (drift 1 & drift 2) Stage 1 (drift 3 & drift 4) Stage 1:Dec,2004-Apr,2005 driven flow of the casted secondary lining before hardening and Stage 1 (drift 5 & drift 6) Stage 2-5:Apr,2005-Dec,2005 -50 the shrinkage of the concrete, a crescent-shaped void is unavoid- Stage 2- Stage 5 Ground surface settlement (mm) ably created between the primary lining and the secondary lining -20 -10 0 10 20 on the tunnel crown. By a subsequent contact grouting from Distance from centerline (m) pre-embedded pipes through the secondary lining, the structural integrity and waterproofing ability of the lining can be enhanced. Fig. 30. Measured ground surface settlements. Q. Fang et al. / Tunnelling and Underground Space Technology 29 (2012) 10–30 21
5.0m 5.0m 4.0m 3.5m 3.0m 2.0m 2.0m 3.0m 3.5m 4.0m 5.0m 5.0m
Back fill Key Ground settlement monitoring point
Silty clay 11.67m Φ32 grout pipe Φ159 roof pipe
35cm primary support
Sand 30cm temporary support Water
table 4.38m Φ950 cylindrical steel column 10.64m 2.9m Gravel 60cm secondary lining 3.36m
23.86m Silty clay
Fig. 31. Cross-section of the Zhangzizhong station.
1 3 3 1 2 4 4 2 5 6 6 5
(a) Stage 1 (b) Stage 2 (c) Stage 3
(d) Stage4 (e) Stage5
Fig. 32. SDA used in the Zhangzizhong station.