The World Bank Report No: ISR4662
Implementation Status & Results Bangladesh Empowerment and Livelihood Improvement "Nuton Jibon" Project (P073886)
Operation Name: Empowerment and Livelihood Improvement "Nuton Jibon" Project Stage: Implementation Seq.No: 3 Status: ARCHIVED Archive Date: Project (P073886)
Public Disclosure Authorized Country: Bangladesh Approval FY: 2010 Product Line:IBRD/IDA Region: SOUTH ASIA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Public Disclosure Copy Board Approval Date 23-Jun-2010 Original Closing Date 30-Jun-2016 Planned Mid Term Review Date 30-Sep-2013 Last Archived ISR Date 25-Jun-2011 Effectiveness Date 05-Dec-2010 Revised Closing Date 30-Jun-2016 Actual Mid Term Review Date
Project Development Objectives Project Development Objective (from Project Appraisal Document)
Has the Project Development Objective been changed since Board Approval of the Project?
Yes No Public Disclosure Authorized
Component(s)
Component Name Component Cost Community and Livelihood Developement at the Village Level 82.50 Institutional Development and Livelihoods Promotion at Inter-village Level 19.50 Capacity Development and Partnership Building from Cluster to National Levels 6.10 Project Management, Monitoring and Coordination 11.90
Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory
Public Disclosure Authorized Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Substantial
Implementation Status Overview Public Public Disclosure Copy
Locations
Page 1 of 4 Public Disclosure Authorized The World Bank Report No: ISR4662
Country First Administrative Division Location Planned Actual Bangladesh Borishal Barisal District
Bangladesh Not Entered People's Republic of Bangladesh
Bangladesh Rajshahi Division Dinajpur District
Bangladesh Rajshahi Division Nilphamari District
Bangladesh Rajshahi Division Kurigram District
Bangladesh Rangpur Division Rangpur District
Public Disclosure Copy Bangladesh Rangpur Division Gaibandha District
Bangladesh Rajshahi Division Naogaon
Bangladesh Rajshahi Division Sirajganj District
Bangladesh Dhaka Division Sherpur District
Bangladesh Dhaka Division Jamalpur District
Bangladesh Dhaka Division Mymensingh District
Bangladesh Khulna Division Bagerhat District
Bangladesh Borishal Patuakhali District
Bangladesh Borishal Barguna District
Bangladesh Borishal Pirojpur District
Results
Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Village institutions supported by the Project Number Value 1454.00 1454.00 2250.00 functioning in a transparent, inclusiive and accountable manner Date 30-Apr-2011 30-Nov-2011 30-Jun-2016 Comments
Intermediate Results Indicators Public Disclosure Copy
Page 2 of 4 The World Bank Report No: ISR4662
Indicator Name Core Unit of Measure Baseline Current End Target Gram Samity accessing and managing VDRRF Number Value 1364.00 1364.00 2290.00 as per agreed rules and service standards as set out in the COM Date 30-Nov-2011 Comments
Village organizations having applied part. Number Value 1266.00 1324.00 1050.00 methods for risk and vulnerability analysis and implemented risk reduction and preparedness Sub Type Date plans. Supplemental Comments
HCP and vulnerable in participating villages Number Value 120000.00 120000.00 500000.00 having access resources under the project and Public Disclosure Copy started IGA Sub Type Date Supplemental Comments
Data on Financial Performance (as of 28-Nov-2011)
Financial Agreement(s) Key Dates Project Loan No. Status Approval Date Signing Date Effectiveness Date Closing Date P073886 IDA-47570 Effective 23-Jun-2010 23-Aug-2010 05-Dec-2010 30-Jun-2016
Disbursements (in Millions) Project Loan No. Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P073886 IDA-47570 Effective XDR 76.20 76.20 0.00 5.18 71.02 7.00
Disbursement Graph Public Disclosure Copy
Page 3 of 4 The World Bank Report No: ISR4662 Public Disclosure Copy
Key Decisions Regarding Implementation Official use only
Restructuring History Level two Approved on 15-Nov-2011
Related Projects There are no related projects. Public Disclosure Copy
Page 4 of 4