PROPOSED CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

PUBLIC HEARING REPORT FOR THE PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT TO BE LOCATED IN THE WATERS OF BAY IN THE TERRITORIAL JURISDICTION OF PASAY CITY

06 July 2018 , Pasay City

1.0 Announcements / Notice of Postings / Invitations

Announcements were properly made at least 21 days before the date of the Public Hearing.

 1st Newspaper Publication -15 June 2018  2nd Newspaper Publication - 22 June 2018

Copies of the newspaper announcements and affidavit of posting from Manila Times are shown on pages 2 to 4.

Invitations to the stakeholders were delivered personally, except for a few whose locations were not easy to find. In addition, all letter invitations were also sent via LBC.

Typical copy of the received invitations is shown on page 16.

1 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

JUNE 2018

 1st Newspaper Publication - 15 June 2018 (Manila Times)

2 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

JUNE 2018

 2nd Newspaper Publication – 22 June 2018 (Manila Times)

3 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

2.0 Invited Stakeholders

The list of invitees shown below also included stakeholders outside the Direct and Indirect Impact Areas.

1. HON MAYOR ANTONINO G. CALIXTO Pasay City Mayor Pasay City Hall Building F.B. Harrison, Pasay City

2. HON. BOYET DEL ROSARIO PASAY CITY VICE MAYOR Pasay City Hall Building F.B. Harrison, Pasay City

3. CITY PLANNING AND DEVELOPMENT COORDINATOR Pasay City Hall Building F.B. Harrison, Pasay City

4. CITY ENGINEER Pasay City Hall Building F.B. Harrison, Pasay City

5. CITY HEALTH OFFICER Pasay City Hall Building F.B. Harrison, Pasay City

6. CITY COUNCILS OFFICE Pasay City Hall Building F.B. Harrison, Pasay City

7. HON. ROSEMARIE B. SAN MIGUEL Chairwoman Brgy. 76 Zone 10 Pasay City

8. MS. DONNA MAYOR- GORDOVE CESO IV Coordinating Office DENR Building, Visayas Avenue, Diliman, , 1100, Tel. No. 928-1225 Trunkline 929-6626 local 2102 www.themanilabay.com

9. MS. JACQUELINE A. CAANCAN, CESO V OIC, Regional Executive Director DENR-National Capital Region Nursery Compound, North Avenue, Diliman, Quezon City Tel No. 373-34-33

10. ATTY. DOMINGO M. CLEMENTE Regional Director DENR-EMB NCR National Ecology Center Compound East Avenue, Diliman, Quezon City 11. NATIONAL MAPPING AND RESOURCE INFORMATION AUTHORITY (NAMRIA) DENR-FMB Compound, Visayas Avenue, Quezon City

4 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

(02) 925-1157

12. NATIONAL MAPPING AND RESOURCE INFORMATION AUTHORITY (NAMRIA) Lawton Avenue, Fort Andres Bonifacio, Taguig City (02) 810-4831 to 42 loc 431 (02) 810-5467

13. ATTY. JANILO E. RUBIATO General Manager and Chief Executive Philippine Reclamation Authority (PRA) 7th Floor, Legaspi Towers 200 Bldg, 107 Paseo de Roxas Street, Legaspi Village 02-817-4711

14. PASAY CITY TRAFFIC AND MANAGEMENT BUREAU F.B. Harrison, Pasay City

15. ATTY. MICHAEL DRAKE MATIAS Chief, EIAMD DENR -EMB Central Office

16. SCHOOL DIVISION SUPERINTENDENT Divisions of City Schools, Pasay Zamora St., Pasay City

17. COMMODORE ILDEFONSO TRONQUED JR. Manila Yacht Club 2351 , Malate, City of Manila, Metro Manila 1000 +63(2) 521 4458

18. THE PRESIDENT OFFICE OF THE PHILIPPINE PLAZA HODINGS, INC. Sofitel Manila Philippine Plaza Holdings, Inc. Room 155 Sofitel Phil. Plaza CCP Complex Roxas, Bouleverd, Pasay City 551-5625 551-5619

19. MR. WILSON TIENG Manila GoldCoast Development Corporation 12th Floor, Solar Century Tower, Tordesillas cor. Dela Costa Sts., Makati City 813-7000

20. JESUS CLINTO O. ARANAS PRESIDENT AND GENERAL MANAGER Government Services Insurance System Financial Center Pasay City

21. MR. JAY DANIEL R. SANTIAGO General Manager PHILIPPINE PORTS AUTHORITY PPA Corporate Bldg. Bonifacio Drive, South Harbor, Port Area, Manila 1018, 527-4855 or 527-83-56 to 83 [email protected]

5 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

22. ADMIRAL RPBERT EMPEDRAD, AFP Flag Officer in Command (FOIC) Philippine Navy Naval Station Jose V Andrada #2335 Roxas Boulevard, Manila PLDT Line: +632-524-20-61 to 69

23. MR. ARSENIO J. LIZASO President Cultural Center of the Philippines CCP Complex, Roxas Boulevard, Pasay City, Metro Manila, Philippines Phone: Trunkline (632) 832-1125; Directline (632) 834-0468

24. MS. AIMEE GONZALES Executive Director Partnership in Environmental Management for the Seas of East Asia (PEMSEA) DENR Compound, Diliman Quezon City

25. SEC. BERNADETTE ROMULO-PUYAT Secretary Department of Tourism The New DOT Bldg., 351 Sen. Gil Puyat Avenue 12.., Makati City Tel No. 02-459-5200

26. LIGA NG MGA BARANGAY 4th Floor Pasay City Hall Building F.B. Harrison, Pasay City

Non-Government Organization (NGO’s) Accredited with the City of Pasay

LIST OF NGO’s/PO’s No. NAME OF ADDRESS PRESIDENT CONTACT ORGANIZATION NO. 1 Emma Homeowners No.61 Emma St. MRS. ADELAIDA 889-9231 Association Inc. Pasay City PACIENTE President 2 Prime Movers Multi Rm. 426 4th F Pasay ENGR. ROLANDO 0920- Purpose Cooperative City Hall Pasay City LONDONIO 9065756 President 3 Pasay City Network for 2442 Torres Bldg. MR. SAMUEL the Protection of Park Ave. Pasay City ENESANDO Children President 4 Our Lady of Sorrows 2130 F.B. Harrison REV. FR. SOCRATES Outreach Foundation St. Pasay City MONTEALTO President 5 Peace and Order Force 181 P. Santos St. MR. ALFREDO 853-8013 Multiplier Malibay Pasay City FRANCISCO President 6 Eduardo “DUAY” 167 San Juan St. MR. EDGARDO M. Calixto Foundation Inc. Malibay Pasay City RUBIANO President 7 Maricaban Market Block 23 Snt. Peter MS. CRISTINA AVILA 0918- Vendors Association St. Maricaban Pasay President 5243940 Inc. City

6 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

No. NAME OF ADDRESS PRESIDENT CONTACT ORGANIZATION NO. 8 Sun Valley NAIA Stall No.16 Sun Valley MS. FE AMADOR Owner & Vendors Drive NAIA, Pasay President Association Inc. City 9 E.Cornejo Vitalez No.741 Vitales St. MS. TERESITA LIGTAS Residents Association Malibay Pasay City President Inc. 10 Geronimo Homeowners 282 M. Geronimo St. MS. ARMIDA CERDEÑA Geronimo Association Inc. Malibay Pasay City President Homeowners Association Inc. 11 Family Touch Malibay 842 A I. Santos St. MS. VILMA B. PENOS 912-3629 Association Inc. Malibay Pasay City President 12 SPECS Foundation Inc. 53 Cementina St. MS. SANDRA M. 5860336/ Pasay City CAMESA 5527030 President 13 SERRAS Center for 162 Sinsiego SR. NIDA VIOVICENTE 524-4705 Girls St.F.B.Harrison St. Executive Director Fax 524-4083 Pasay City 14 Pangarap Foundation 2503 Taft Ave. cor. MS.LEAH LAMSUELA 834-1061- Escobal St. Pasay Program Director telefax City MA.VICTORIA C. YULO President

Others:

1. MS. GEMMA G. CRUZ-ARANETA Chairperson Heritage Conservation Society (HCS) G/F Building, Roxas Boulevard, Ermita Manila, Philippines Tel. No. +632 353 4494 Fax No. +632 522 2497

2. SAVE MANILA BAY PHILIPPINES https://www.facebook.com/savemanilabay

3. Mr. JEFFREY C. LIM Director and President SM Prime Holdings, Inc. 10th Floor, Annex Building, Coral Way, Pasay City

4. REV. FR. BENITO TUAZON Ministry on Ecology and Commission on Social Services and Development The Roman Catholic Archdiocese of Manila Caritas Manila Compound 2002 Jesus St., Pandacan, Manila

5. ARCHBISHOP LUIS ANTONIO G. TAGLE The Archdiocese of Manila 121 Arzobispo St, , Manila, Metro Manila 527-3962

7 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

6. DR. RENATO SOLIDUM Philippine Institute of Volcanology and Seismology (PHIVOLCS) PHIVOLCS Building, C.P. Garcia Avenue, U.P. Campus, Diliman Quezon City, Philippines [email protected] +632 426 1468 to 79 +632 929 8366, 927 4524

7. MR. JAIME “JOEY” MEDINA General Manager Lake Development Authority (LLDA) 4/F Annex Bldg., Sugar Regulatory Administration (SRA) Compound North Ave., Diliman, Quezon City Phone 332-2346

8. ENGR. EMITERIO HERNANDEZ Hydrologist Laguna Lake Development Authority (LLDA) 4/F Annex Bldg., Sugar Regulatory Administration (SRA) Compound North Ave., Diliman, Quezon City Phone 376-4044

9. MR. JOSE ANGELITO PALMA President, World Wildlife Fund WWF-Philippines Headquarters 4th Floor JBD Plaza #65 Mindanao Avenue Barangay Bagong Pag-asa, Quezon City 1105 Philippines Tel: +632 920 79 23/26/31 Fax: +632 426 39 27 Email: [email protected]

10. THE UNITED ARCHITECTS OF THE PHILIPPINES UAP Building, 53 Scout Rallos Street, Barangay Laging Handa Diliman 1103 Quezon City, Philippines Phone (+632) 4126403; 4126364; 4123311; 4120051; 4126394 Fax (632) 3721796 E-mail: [email protected]; [email protected]

11. CRISANTA MARLENE P. RODRIGUEZ OIC Director Protected Area and Wildlife Bureau Department of Environment and Natural Resources Ninoy Aquino Parks and Wildlife Center Diliman, 1100 Quezon City Philippines +(63 2) 9246031-35 +(63 2) 9240109 www.pawb.gov.ph [email protected]

12. BRIG. GEN. DANILO DELAPUZ LIM (Ret) Chairman Metro Manila Development Authority (MMDA) MMDA Bldg., EDSA cor. Orense St., Guadalupe, Makati City Directline (632) 882-0854; 882-0893

8 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

13. ARCHITECT JUN PALAFOX Palafox & Associates 5/F PCCI Corporate Center 118 L.P. Leviste St. (02) 812 1254

14. MR. ERNESTO M. PERNIA Director General National Economic and Development Authority No. 12 St. Jose Maria Escriva Drive, , Pasig City Trunkline: +63 631 0945 – 56 Email: [email protected]

15. MR. MELVIN B. NAVARRO Regional Director Department of Public Works and Highways 2nd Street, Port Area, Manila Contact No(s).: (02) 304-3910 Fax No.: (02)304-3910 Email: [email protected]

16. COMMODORE EDUARDO B/ GONGONA Director BUREAU OF FISHERIES AND ACQUATIC RESOURCES (BFAR) PCA Compound, Q. C. Elliptical Road, Diliman, Quezon City, 1101 Metro Manila (929-8074, 929-9597)

17. DR. FRANCISCO DUQUE III Secretay DEPARTMENT OF HEALTH (DOH) San Lazaro Compound, Tayuman, Sta. Cruz, Manila

18. DR. FERNANDO SIRINGAN National Academy of Science and Technology 3rd Level Science Heritage Building, DOST Complex Bicutan, Taguig City (632) 837-3170 / 838-7739

19. Asean Avenue corner Roxas Boulevard, , Parañaque 1701, Manila, Philippines (632) 800-8080

20. ANCHOR LAND HOLDINGS INC. 15TH Floor C.C. Locsin Bldg. 6752 Ayala Ave. (02) 488-7988 loc. 203 103 20. JEREMY BARNS, CESO III DIRECTOR IV NATIONAL MUSEUM OF THE PHILIPPINES P.Burgos Drive, , Manila 02-527-1209

21. HOTEL JEN 3001 Roxas Boulevard, Pasay City, Metro Manila

9 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

795-8888

22. Office of the President De La Salle University 14th Floor, , Senior Hall De La Salle University, 2401 Taft Avenue, 1004 Manila Tel. 524-1611 loc. 802

23. Office of the President De La Salle College of St. Benilde 2544 Taft Avenue, Malate Manila Tel. 230-5100 loc 1801 to 1803

24. DR. RENE R. ESCALANTE Chairman NATIONAL HISTORICAL COMMISSION OF THE PHILIPPINES (NHCP) NHCP Building, T.M. Kalaw St., Manila, 1000 Tel No. +632.536.3181

27. COMMODORE ELSON E. HERMOGINO Commandant PHILIPPINE COAST GUARD (PCG) 139 25TH St. South Harbor, Port Area 527-8482 loc. 6291

28. BIODIVESITY MANAGEMENT BUREAU Ninoy Aquino Parks and Wildlife Ceter, Diliman, 2200 Quezon City 02-924-6031

29. CENTER FOR ENVIRONMENTAL CONCERNS 175-B Kamias Road, Quezon City, Metro Manila 02-920-9099

28. ATTY. LUTGARDO B. BARBO Senate Secretary SENATE OF THE PHILIPPINES

29. SEC. ALAN PETER S. CAYETANO Secretary DEPARTMENT OF FOREIGN AFFAIRS (DFA) 2330 Roxas Blvd. Pasay City

30. PASAY BOAT OPERATORS Libertad Channel Pasay City

------CITY OF MANILA------

01. HONOURABLE MAYOR JOSEPH EJERCITO ESTRADA City Mayor , Arroceros, Manila

02. HONOURABLE VICE MAYOR HONEY LACUNA City Vice Mayor, Manila Manila City Hall, Arroceros, Manila

10 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

03. MANILA CITY COUNCIL 4th Floor Manila City Hall, Arroceros, Manila

04. CITY ENGINEER Dept. of Engineering & Public Works 3rd Floor Manila City Hall, Arroceros, Manila

05. CITY PLANNING & DEVELOPMENT OFFICE 3rd Floor Manila City Hall, Arroceros, Manila

06. CITY TRAFFIC & PARKING BUREAU 3rd Floor Manila City Hall, Arroceros, Manila

------LAS PIÑAS CITY ------

01. HONORABLE MAYOR IMELDA AGUILAR Alabang Zapote Road, Pamplona Tres Las Piñas City

02. HONORABLE VICE MAYOR LOUIE BUSTAMANTE Alabang Zapote Road, Pamplona Tres Las Piñas City

03. LAS PIÑAS CITY COUNCIL Alabang Zapote Road, Pamplona Tres Las Piñas City

------PARAÑAQUE CITY------

01. HONORABLE MAYOR EDWIN OLIVAREZ San Antonio Valley 1 Parañaque City

02. HONORABLE VICE MAYOR RICO GOLEZ San Antonio Valley 1 Parañaque City

03. PARAÑAQUE CITY COUNCIL San Antonio Valley 1 Parañaque City

04. CITY PLANNING & DEVELOPMENT OFFICE San Antonio Valley 1 Parañaque City

05. CITY ENGINEER San Antonio Valley 1 Parañaque City

06. CITY TRAFFIC MANAGEMENT OFFICE San Antonio Valley 1 Parañaque City

------Additional Entries------

1. TERESITA M. BISCOCHO Chairwoman Barangay 1, 1739 Cuyegking St. Pasay City

11 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Tel No. 0929-5268467

2. DANILO B. FELICIANO Chairman Barangay 2, 488 Cuyegking St. Pasay City Tel No. 0919-2134263

3. ARNEL V. CELIS Chairman Barangay 3, 1807 Cuyegking St. Pasay City Tel No. 524-5544

4. ALBERTO G. ARGUELLES Chairman Barangay 4, 1855 R. Tankian St. Pasay City Tel No. 0920-4542073

5. VISITACION C. DOMIQUIL Chairman Barangay 5, 43 Loudes St. Pasay City Tel No. 0918-2463920

6. RENATO M. LOGRO Chairman Barangay 6, 23 Lourdes St. Pasay City Tel No. 536-3456

7. CARLOS N. LIPNICA Chairman Barangay 7, 14B San Juan St. Pasay City Tel No. 546-7864

8. MILMA M. AGUSTIN Chairwoman Barangay 8, 2009 FB Harrison St. Pasay City Tel No. 0921-3394345

9. ROGELIO D. ATANGAN, JR. Chairman Barangay 9, 90 Gil Puyat Ave., Pasay City Tel No. 524-7945

10. ROSAURO P. MORALES Chairman Barangay 10, 54 Sta. Monica St. Pasay City Tel No. 831-5451

11. MARLON C. CONTRERAS Chairman Barangay 11, 64 Antipolo St. Pasay City Tel No. 0905-4180849

12. WILFREDO ORTALIZ Chairman Barangay 12, 54 San Luis St. Pasay City Tel No. 831-2383

13. FOR

12 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Cultural Center of the Philippine Complex Roxas Boulevard, Manila

MANAGER DANILO S. MARTINEZ Officer IV, Property Administration Department Government Services Insurance System (GSIS) Financial Center, Pasay City

14 Society for the Unit 208 Grand President T/F: +63 2 637 2409 Conservation of Emerald Tower, Philippines Wetlands, F. Ortigas Ave. Inc. corner Garnet St., Ortigas Center, Pasig City, Philippines 1605 15 Villar Sipag Masibay St. President Tel. No. (632) 551-1871 BFResort Village, [email protected] Talon Dos Las Piñas City

 IMPACT AREAS

1. PRESIDENT Tanghalang Francisco Balagtas F. Ma. Guerrero St. Pasay Metro Manila

2. PRESIDENT Gloria Maris Shark’s Fin Restaurant CCP Complex, Roxas Blvd. Pasay, 1300 Metro Manila 02-831-3816

3. PRESIDENT Sky Garden By the Bay Restaurant Brgy. 719 Zone 78 Trellis 2 Asean Promenade Pedro Bukaneg St. CCP Complex Metro Manila 0917-639-3821

4. PRESIDENT Star City Vicente Sotto St. CCP Complex, Pasay Metro Manila 02-832-3249

5. PRESIDENT Upside Down Museum Boom na Boom Grounds CCP Complex, Roxas Blvd. 1300 Metro Manila 02-834-8997

6. PRESIDENT Seascape Village Atang Dela Rama, Pasay, Metro Manila 0917 807-6171

13 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

7. PRESIENT Cultural Center of the Philippines, Roxas Blvd. Pasay City 1300 02-834-8870

8. PRESIDENT HK Sun Plaza Diosdado Macapagal Blvd. Pasay Metro Manila 0917 000-0000

9. SUPT. CARLOS T. DUEÑAS Senate Fire Sub-Station Jose Diokno Boulevard, Pasay, Metro Manila 02-552-6601 loc. 1999

10. PRESIDENT Hobbies of Asia Diosdado Macapagal Avenue Pasay, Metro Manila 02-556-2007

11. PRESIDENT Hyundai Manila Bay Diosdado Macapagal Avenue, Pasay City, 1307 Metro Manila 02-556-1493

12. PRESIDENT World Trade Center Metro Manila 2/F WTCMM Building, Gil Puyat Avenue Extension corner Diosdado Macapagal Blvd., Pasay City, Metro Manila 1300 02-902-0000

13. PRESIDENT Philippine National Bank – Financial Center Pasay, Kalakhang Maynila 02-573-88888

14. PRESIDENT CITEM – Center for International Trade Expositions and Missions Golden Shell Pavilion, Roxas Blvd. cor. Sen. Gil J. Puyat Avenue 1300 Pasay Metro Manila 02-831-2201

15. PRESIDENT Philippine Trade Training Center Cor. Sen J. Gil J. Puyat Ave, Pasay Metro Manila 02-263-2878

16. PRESIDENT Seaside Restaurant 105, Roxas Boulevard, Diosdado , Pasay, 4115 Metro Manila (02) 843 4545

14 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

17. PRESIDENT Harbor Square CCP Complex, Roxas Blvd. PICC Reclamation Area, Pasay City

15 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

3.0 Typical Received Copies of Invitations

16 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

17 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

4.0 Actual Participation

There are total of 136 attendees from different sectors during the Public Hearing. Provided in Annex B is the copy of attendance sheets.

5.0 Report on the Proceedings

The public hearing conforms to the DAO 2017-15 guidelines on Public Participation. The Public Hearing allowed all questions, issues and concerns to be raised completely and freely.

The process and purpose of the Public Hearing were explained by the EIA Case handler, Engr. Carlo Vic Arida and the Public Hearing Officers are Atty. John Edward Ang and Atty. Aime Rodaje. The program started at around 9:30 o’clock in the morning. It was formally opened through an opening remarks conducted by Hon. Mayor Antonino G. Calixto. The project details and Environmental Impact were presented and discussed by the EIA preparer, Dr. Edgardo G. Alabastro.

The Public Hearing Officer, Atty. John Edward Ang explained guidelines and moderated the open forum.

Provided in the annexes are the following documentations:

ANNEXES

 ANNEX A. Project Presentation  ANNEX B. Attendance Sheets  ANNEX C. Table of Issues and Concerns During the Public Hearing and Responses Thereto  ANNEX D. Photographs of the Public Hearing

 Registration of Participants  Portion of the Participants  Welcome Remarks of Mayor Calixto  Briefing and Orientation on the Process Of Public Hearing (Engr. Carlo Arida)  Project Presentation and Environmental Impact Discussion (Dr. Alabastro)  Open Forum Discussion

 ANNEX E. Notice of Posting With Tarpaulins  ANNEX F. Transcriptions of the Recording  ANNEX G. Video clippings in CD

18 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

ANNEX A. PROJECT PRESENTATION

19 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

20 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

21 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

22 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

23 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

24 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

25 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

26 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

27 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

28 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

29 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

30 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

31 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

32 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

33 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

34 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

35 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

36 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

37 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

38 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

39 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

40 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

41 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

42 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

43 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

44 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

45 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

46 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

47 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

48 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

49 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

50 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

51 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

52 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

53 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

54 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

55 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

56 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

57 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

ANNEX B. ATTENDANCE SHEETS

58 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

59 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

60 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

61 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

62 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

63 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

64 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

65 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

66 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

67 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

68 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

69 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

70 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

71 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

72 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

73 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

74 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

ANNEX C. TABLE OF ISSUES AND CONCERNS DURING THE PUBLIC HEARING AND RESPONSES THERETO

75 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Project Name Proposed Pasay Harbor City Reclamation Project Location Municipality/City Province Project Pasay Metro Manila

Proponent Name Pasay City Government Proponent Pasay City Hall, F.B. Harison, Pasay City Address Proponent Atty. Severino Madrona, City Legal of Pasay Proponent Contact Person Means of Landline No : 02-833-3729 Fax No. : Contact Mobile No : Email :

EIA Preparer Technotrix Consultancy Services, Inc. Preparer Suite 305 FMSG Building #9 Balete Drive, New Manila Quezon City Address EIA Preparer Edgardo G. Alabastro Ph.D. Preparer Landline No :02-4164625 Fax No. : 02-4164625 Contact Person Mean`s of Mobile No :0917.8255203 Email : [email protected]

Contact EMB/DENR Mr. Carl Louie Santiago Place of Public Cuneta Astrodome, Pasay City Scoping Engr. Carlo Arida Scoping Representatives Engr. Joel Polintan Date of Public 06 July 2018 Casehandlers Scoping DENR-EMB-Central Office

76 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

ATTY. JEN RAMOS – LEGAL Sea level rise galing sa climate change. ADB conducted a DR. ED ALABASTRO POLICY DIRECTOR OCEANA study stating most cities are vulnerable to sea level rise and storm surges, na-consider po ba ito? Base sa aming pag aaral hindi ito magdudulot ng climate change. No greenhouse effects, walang icocontribute itong project na ito. Ang climate change ay dahil sa activities ng mga tao. Ang main contributors are China and USA. The

project will not emit significant greenhouse gases.

With or without project, magkakaroon ng sea level rise. Ang projection ng IPCC ay dahil sa ibang bansa ang sanhi ng climate change. 0.3 or 0.4m sea level rise ang projection po, with or without the project.

LAND Sa storm surge, pinakita namin sa oceanography section ng EIS na ang project ay nagpoprovide ng sheltering effect, o pag sangga ng reclamation islands sa puwersa ng ocean waves galling sa storm surge. Through reclamation this will serve as defense mechanism. Example Tacloban coastal defense.

77 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

Filling materials sa San Nicholas Shoal, Napag aralan na POST PUBLIC HEARING NOTE of DR. ED ALABASTRO ba ito? Unang-una po, gagamitin ang teknolohiya na maaring ibalik High density na ang Pasay, saan ilalagay/itatapon ang sa seabed ang bahagi ng dredged materials para di itapon sa dredging materials? ibang lugar. Kung sakali naman dapat po talaga mag-dispose ay mag-aapply po ang dredging contractor ng kaukulang permit sa disposal. Sa pagkakaalam ko, dapat yatang idispose ang unwanted dredged materials sa malalim na bahagi ng Manila Bay.

Magiging basehan din po sa disposal ang ibang pag-aaral tungkol sa disposal ng Pasig River dredged materials sa Manila Bay.

Para sa substantial alteration of boundaries ng isang ENGR. LAGMAY munisipyo, kailangan ng LGU na magdaos ng plebisito. On the alteration of boundaries hindi po kami nag-alter. Within the political jurisdiction of the City of Pasay. Humingi po kami ng tulong sa NAMRIA tungkol sa municipal waters.

78 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

ATTY. JEN RAMOS – LEGAL Gaano kataas ang Isla? ang storm surge? Dr. ED ALABASTRO POLICY DIRECTOR OCEANA Ang finished platform ay 4meters above MLLW. And in case of worst situation na sinabi ng IPCC, this platform provides cushion kung magkaroon ng sea level rise.

Sa isyu naman ng Mandamus, “Mandamus” orders the clean- up of Manila Bay. Pinatawag ang LGUs at agencies para tumupad sa Mandamus pero hindi sinasabi what and what not to do with respect to development plans.

A percentage of the revenue from taxes of the reclamation will be for environmental initiatives including the clean-up of the Manila Bay.

79 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

ATTY. CORPUS – Office of Sen. Yong sinasabi na source ng filing materials ay San DR. ED ALABASTRO Villar Nicholas Shoal, we received an order from DENR that extraction of filing materials from SNS is already We were asked saan ang options. Regarding Mandamus, the prohibited. Siguro kailangan ng ibang bundok na investors will have to invest Php 72billion. Kapag hindi tatapyasin. Ibig sabihin, kung sa SNS kayo kukuha ng maganda ang project, nasira ang dagat, bumaho at masira filling materials, wala po kayong project sa ngayon at hindi ang kalikasan, contrary siguro ito sa investments ng investor, na dapat muna kayo nag-aaply ng ECC. Dapat din which is pagandahin. sigurong ibahin na rin ninyo and powerpoint presentation ATTY. MADRONA na ginagamit ninyo at palitan na ang SNS kasi hindi na puwede doon. Hindi requirement ang Area Clearance para ma-acquire ang ECC. Area Clearance will be given after the ECC, just to Sinabi po ninyo na the reclamation is not an ECA because clarify. it is 8.5km away from LPPCHEA. I’d like to disagree. As of June 22, LPPCHEA is no longer just a critical habitat but ENGR. ARIDA already a protected area. The LPPCHEA has a mangrove area. The flow of the water will affect the mangroves. Yan May bagong guidelines tungkol sa area clearance at ECC to ang kanilang nursery that is why we from Las Pinas clarify. Paranaque ay pinoprotektahan namin ang area na yan. If we will do the reclamation we have to undergo a process. PRA: Wala pong memo regarding pinagbabawal yung Reclamation is an Environmental Critical Activity. Ang pagkumuha ng ano from SNS, wala lang palang siyang ECC area ng proyekto ay nasa loob ng buffer zone ng kaya hindi pa pwede gawin. PRA is currently applying for the protected area. ECC, it is not the project proponent’s responsibility to get the ECC for the area where they will get their filling materials. The Area Clearance should first be applied for before the Additionally po, nakapag bigay na din po kami ng advise na ECC? Iyan po ang nasasaad sa order na nanggaling sa mag consider ng other sources of filling materials dahil nga po DENR-EMB na kung saan ay nabigyan kami ng kopya. hindi pa siya nabibigyan ng ECC.

The application for SNS is subject to separate EIS. Pag na-grant ang ECC, pero mukhang impossible na dahil ipinagbabawal na nga ang pagkuha ng fill materials sa SNS.

80 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

ATTY. CORPUS – Office of Sen. We stand by our interpretation of area clearance first ENGR. ARIDA Villar before ECC. If ECC, which is a planning tool, area clearance will not serve its purpose. That issue nakarating na sa higher management ng DENR

DR. ED ALABASTRO

Nag-aaply kami ng area clearance sa ibang proyekto kahit naniniwala kami na ECC muna. Lumalabas sa aming application na kailangan ang informasyon galling sa EIS at ECC bago ma-evaluate ang Area Clelarance

DENR NCR

Under the Old DAO, mauuna ang ECC pagkatapos Area Clerance kaso nag issue si USEC ADOBO na area clearance muna bago ECC. Pero isa sa mga requirements ng Area Clearance ang ECC. Ngayon, meron nang discussion regarding Area Clearance ba muna or ECC dahil hindi ka iissuehan ng Area Clearance kapag wala kang ECC. Sa ngayon, di pa kami maka-issue dahil wala pang final Memo

.ATTY. MADRONA:

This shows that we are on the right part of the process. Wala pa po yong DAO. Thus we stand our part na ECC muna.

81 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

Representative from NAMRIA Regarding doon sa assistance para sa pagdetermine ng ATTY. MADRONA Municipal Waters, tama po ang sagot ni Engr. Lagmay na ang Pasay ay lumapit sa amin. We clarify that DAO 2004- Our legal basis is the ordinance of our municipal waters to 01 we are requesting to plot Pasay City municipal waters assess your concern we are coordinating with our neighboring based on the RA. We responded to the letter saying, the cities. existing and technical description of Pasay was already revoked. Pursuant to the plot, we attached the requested map. The attached plotting is not binding to other laws and the delination procedure of plotting of NAMRIA is not in accordance to other guidelines. There is no certified technical description that were delineated and plotted. NAMRIA only follows what is in the guidelines. Ang pag- plot ng municipal waters ay mayroon pong sinusunod kaya po ang pagdrawing ng NAMRIA ay based sa guidelines at maiwasan ang overlap. Tumutulong po ang NAMRIA sap ag-plot sa mapa pero hindi ang NAMRIA ang may kapangyarihan para magdelineate nito. Kapag mayroong overlap, ang mga concerned LGUs ay maghaharap-harap upang iresolba ang isyu.

WATER Representative from Save our Sentiments of the Community: Marine ecology POST PUBLIC HEARING NOTE: A complete and in depth Shore marine survey has been reported in the EIS and has been

82 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

Ms. ISSA of Wetlands Instead of asking questions, I would like to give reviewed by the Review Committee, which is composed of International suggestions if that is possible, independent professionals including a Marine Biologist

May mga issues yong sa lack ng marine species, sabi ng UP Marine Institute, wala ng species. Mataas ang coliform at algal bloom at ganun kadumi ang Manila Bay.

Yong sa Tacloban, we are advocating soft and hard engineering. Our suggestion, since our advocacy includes actions, ano po ang pro-active measures na naiisip ninyo for Manila Bay?

Mas maganda po kung magkakroon ng Ecosystem Valuation vis-à-vis reclamation.

83 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

Mr. Pablo Rosales – President ng Pangunahing kabuhayan ng mga mangingisda ang MAYOR CALIXTO: Mangingisda sa Pilipinas pangingisda. Ayon sa aming pagkakaalam, merong 36,000 hectares reclamation na plano sa Manila Bay. Na- Walang marine life na nabubuhay as of today sa City of consider po ba ang pagtaas ng tubig? Kabuhayan ng Pasay. Kinukuha ang mga isda sa at Bataan at mangingisda sa Manila Bay? Food security sa Manila dinadala lang dito sa Paranaque at Pasay. Hindi pwedeng Bay? Almost 1,500 hectares na ang nareclaim example alisin ang mga fisherfolks. Maglalagay tayo ng fisherman’s CCP, PICC, asan at paano na po ang mga mangingisda? wharf sa reclamation area dahil kasama ito sa plano at Sana ma-consider ang mga sector na ito para maisama magiging tourist attraction pa ito. Naka design po iyon. sa pag unlad. DR. ED ALABASTRO:

Ang 36, 000 hectare project yon po ang study area ng PRA Project na “Programmatic EIS Study” Pag-aaralan ang Manila Bay. Hindi sinasabi na maglalagay ng reclamation project. Nasa 4th bidding na po itong proyekto para makapag-award ng Study Consultant. Study lamang po ito; Hindi pagcoconstruct ng reclamation.

PRA:

36,000 Hectare reclamation is true. It is not something that is planned, it is a study to comply para lahat ng reclamation ay integrated. And that we can plan it well. Dahil consolidated ito. Macoconsider ang traffic, storm surges, etc. rest assured, all of this will be included in the EIA of the DENR and PRA evaluation and how it can lessen the impact on climate change. PRA is looking into including coastal protection. Other agencies are also being consulted in the EIA process to look into the modeling of the preparer.

In terms of San Nicholas, the EIS has been conducted pero 84 | P a g e wala pang ECC. If ever this will be granted, the DENR can insure that no marine life will be affected.

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

ATTY. JEN RAMOS – LEGAL How do you address na wala ng marine life sa Manila ENGR. LAGMAY: POLICY DIRECTOR OCEANA Bay? Instead of rehabilitating Manila Bay, magtatayo na lang ba ng structures? Hindi ba nakakabahala ito na Tungkol sa Manila Bay Clean up, all LGUs are part of the instead I rehabilitate, irereclaim? Mayroon pong Mandamus. Sa kasalukuyan po ay sumusunod sa Mandamus mandamus na ipinatutupad upang linisin ang Manila Bay. ng Supreme Court.

SAVE OUR SHORES Naawa ako sa mga fishermen. There are no products for DR. ED ALABASTRO: fishing because of reclamation. More people from Manila will be flocking to Manila. Fish will flock in Bataan. With Gaya po ng nasabi ko kanina sa Multi Sectoral Forum ng scientific things, prominent scientist Dr. Rodolfo predicted NAST nuong Feb 15, 2016 na sinalihan din po ni Dr. Rodolfo, disaster in Pinatubo. He also predicted that Manila will ang lawak ng aming EIS study area ay base sa impact areas have flood, expects storm surge, degradation of water and of the project. Kaya ung nangyayari sa ibang lugar tulad disaster in the area. halimbawa sa Mt Pinatubo o Bicol ay labas po sa impact zones.

ATTY. CORPUS – Office of Sen. Yong tungkol sa mandamus, we should remove all DR. ED ALABASTRO: Villar structures that will impede the flow of natural waters. Pag tinakpan ang dagat, ang unang matatamaan ay mga isda. Gumawa po kami ng circulation modeling para malaman Kawawa naman ang mga isda hindi maka- attend ng hanggang saan ang impacts ng project at resulta walang public hearing. Maapektuhan lahat ng 16 cities and highly significant impacts. Noong Feb 2016 Forum ang municipalities mula Cavite hanggang Bataan na sinasabi ang impact ng project has to be viewed with respect nakapaligid dahil sa alteration. Manila Bay is the natural to other projects. EIA is a planning tool. Hindi kasama ang drainage of Manila. nangyari sa Bicol. Pati storm surge. These discussions of professionals say that the project shall look into the impacts

85 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

Mr. PETER VILLEGAS of Save Kami po ay inanyayahan ng Office ni Sen. Villar upang sa ibang area. the Bay dumalo sa Public Hearing na ito. Tungkol po sa Mandamus, ngayong December 2018, mapapaso na ito. Sabi ni Doctor Alabastro, ay kumplikado ito. Bilang ordinaryong mamayan, ang efforts sa clean up ay mabisa, malinis na ang manila bay at maaari nang tirhan ng isda. Gaya ng sabi ng mga mangingisda, pwedeng magmura ang isda at ma-save ang historical na Manila Bay. Tingin po naming, kapag natuloy ito, ang view sa Manila Bay ay mapaprivatize. Kailangan pang pumunta sa dulo ng reclamation. Kaya kami po ay tumutulong sa layunin na irehabilitate ang Manila Bay, particularly LLPCHEA para mapakita na kaya ito ibalik. Kaya pa linisin ang Manila Bay at ibalik ang ganda ng Manila Bay. Lumalabas sa usapin na negosyo kesa protekta. Kung sa Pasay walang mangroves, puwede tayo magtanim ng iba’t-ibang klase ng mangroves.

86 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

Mangingisda ng Las Pinas Parang yung impact hindi ko nakita, yong halimbawa High DR. ED ALABASTRO Tide. Mula magkaroon ng reclamation, lagyan ng lupa aapaw ang tubig. Doon sa high tide, ano kaya ang nagyari Yong proyekto will require a filling of 50M cu.m. and ang pagsalubunga ng tubig galling sa bundok. Manila Bay ay may 30 Billion cu.m. na dagat; hindi po naming nakikitata ang pag-apaw ng Manila Bay. Kung sakali, sa SNS Dati hindi kami inaabot ng tubig. After reclamation tayo kukuha ng filling materials mag icrecreate po na tubig na umangat ang tubig, paano pa kapag matapos ang ibang parehas sa natakpan sa reclamation project. reclamation? Ang project ay hindi magcocontribute sa climate change. Ang climate change ay dulot ng GHG emission from US, China, Russia. May project man o wala, may sea level rise. Yon po ang nakikita namin.

Paranaque Resident Yong mga proyekto kayo din ang preparer ng Paranaque, DR. ED ALABASTRO kung iisahin ang mga project lahat po ay may epekto sa Manila Bay, Pati po tayo ay apektado. We cannot deny Saan nanggaling ang greenhouse gases sa buong mundo. that this project has negative effects kaya bakit pa natin i- Hindi kasama ang greenhouse gases sa idudulot ng San Dionisio Credit Cooperative undertake? At what cost, what stake. Hindi kami nainiwala reclamation na wala ng marine resource sa Manila Bay. Kailangan ito linisin para yumabong.

Meron fisherman sa Paranaque pero sa Pasay wala. Kaya meron pang mga isda

87 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

Representative from Save our Will the reclamation help the problem and alleviate Traffic DR. ED ALABASTRO Shore Congestion? PEOPLE Creation of the land ang application po namin. This involves As per JICA, the Philippines is wasting 3.5B/day because activities up to horizontal development. Nasa dagat ang of traffic in EDSA. operation wala po sa land. Magkakaroon ng Traffic Management sa Operations Phase. Sa Metro Manila Traffic No problem if the islands are completely isolated (no Bureau nakipagcoordinate na po si City of Pasay. bridge to travel to the islands), but if it’s connected, it will affect the traffic. The additional reclamation will contribute Wala ng land sa kalupaan ng Pasay na sinlaki ng 265 to additional population. I hope the LGU will involve city hectares na available at contiguous para ilagay and planners rather than scientists who are trying to solve proyektong ito. Sa reclamation project better management of problems. Is this project going to make Manila more of a traffic and more effective control of vehicular egress and problem? ingress.

MAYOR CALIXTO:

Inaanticipate namin ang traffic para sa mga susunod na dekada. Ang government ay mayroong solusyon at tinutugunan naman po namin at ng MMDA.

POST PUBLIC HEARING NOTE

The Mayor stated one of the rationale for the Project is to address the current and future population density problem of the City. Pasay City is the 6th most dense City.

88 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

ATTY. PE BENITO Hindi malinaw ang DENR Regulation but we can look into ATTY. MADRONA considerations of environmental impacts pag OTHERS pinagsamasama ito. Bakit di muna Area Clearance kesa 60% National ECC to consider all impacts. Pagsamasamahin ito, 40% Local mababago ang complexion. Sa presentation ni Dr. Alabasro, the contractor will not make charitable Sa issues ng Via Mare case we have the right to reclaim that contribution but to always make a profit. May kaso po na is why we have our MOU between LGU and PRA. If we sinasabi na ang Manila Bay ay owned ng state, but they reclaim, iba ang area clearance definition. It provides permits found a loophole in the LGU code that the LGU can to applicant subject to EIS. The DAO itself defines what is an reclaim, hence this is valid. Area Clearance. We followed, without that, this is logical process. Ano ang sharing ng LGU at Contractor? Magkano ang share ng LGU, Private contractor

89 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Sector or Representative Who Raised the Issue/ Suggestion EIA Module Issues/Suggestions Raised by Stakeholder Proponent’s Response

REPRESENTATIVE FROM Hindi po ba mas mabuti kung maghanda na programmatic ATTY. JED (HEARING OFFICER): PEISS is required for LYCEUM College of LAW EIS para isa lang at ma address lahat ng concern ng lahat industrial project. It is initiation of the proponent ng mamamyan kapag may Public Hearing? Although optional, hindi naman masama to make an interest to ENGR. CARLO ARIDA: PEISS is just an option. Mas ma- address the general public dahil baka magamit ang aappreciate to kapag Industrial Park. ganitong systema sa EIS. ATTY. CORPUZ: Back in 2014, there was a letter to PRA for the 36,000-hectare reclamation from Cavite to Bataan mas dangerous po ito dahil isang permit lang sa lahat ng reclamation sa Manila Bay. I do not advise the programatic EIS. It is very alarming.

DR. ED ALABASTRO: Yong project ng PRA sa 20,000+ Ha Study is a programmatic EIS Hindi po namin nakikita na itong 265-Ha Project ay Programmatic EIS.

The operations phase will be at least 20 years from now. For the Reclamation Phase we choose to apply for an EIS type of documentation.

ENGR. LAGMAY: Pag na-formulate ang CLUP, mayroon po kaming kolatilya na dati bawal ang reclamation, however, nag update na kami at kasama na ito until 2022. Doon po kasama ang proposal for reclamation dahil ang existing reclamation such as MOA ay developed na at kaya na I-sustain ang ibang reclamation project. Kasama sa considerations namin ang effect sa traffic at wastes na in-approve ng HLURB. At dumaan sa matinding review process.

90 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

ANNEX D. PHOTOGRAPHS OF THE PUBLIC HEARING

91 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

92 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

REGISTRATION OF PARTICIPANTS

93 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

PORTION OF THE PARTICIPANTS

WELCOME REMARKS OF MAYOR CALIXTO

94 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

BRIEFING AND ORIENTATION ON THE PROCESS OF PUBLIC HEARING (ENGR. CARLO ARIDA)

PROJECT PRESENTATION AND ENVIRONMENTAL IMPACT DISCUSSION (DR. ALABASTRO)

95 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

96 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

OPEN FORUM DISCUSSION

 ATTY. JEN RAMOS – LEGAL POLICY DIRECTOR OCEANA

 Ms. ISSA of Wetlands International

97 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

 Representative from PRA

 ATTY. CORPUS – Office of Sen. Villar

98 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

 Response of Atty. Madrona, City Legal of Pasay

 Mangingisda ng Las Pinas

99 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

 Closing Remarks of Mayor Calixto

100 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

ANNEX E. NOTICE OF POSTING WITH TARPAULINS

101 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

 Notice of Posting at Barangay 76 Zone 10 Barangay Hall

102 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

ANNEX F. TRANSCRIPTIONS OF THE RECORDING

103 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Dr. Alabastro: Kung to xxx ordinance wala pang progress na pinatapatahak nila (inaudible) established, yes is it undertaken kung magtatagumpay for bidding progress plebiscite.

Atty. Jennifer Ramos: HI, Good morning, I’m Jennifer Ramos, I’m a lawyer, I’m a legal policy director of OCEANA, (inaudible) kaya yung sa EIS study yung sa storm search (inaudible) ng sea level rise, pero hindi ata natin namention yung sea level wise na manggagaling sa climate change, kase nasabe ba yun sa study ng EIS sa climate change (inaudible) ng PRA kase infact yung iibang company nag conduct ng study and they resulted to that, yung sa coastal cleaning nga ng Pilipinas ay at risk of sea level rise. Masasabe ba yung protection ng sea level rise dito sa project na to kase nakakaano talaga eh (inaudible) island pa (inaudible) protection kase yun na lang yung kulang yung Pablo, Pablo Pablo ba yun? Eh hindi, hindi salik ang mga concerns natin kase tataas at tataas talaga ito dahil tataas at tataas talaga ang sa global warming pati yung sa climate change, with that namention ni mayor na wala ng marine life ngayon ang municipal waters ng Pasay, kaya diba nakakabahala ito tas lalagyan pa natin ng isla, how do we addressed this na wala ng marine life ang Pasay ang sagot ba natin dito ay magbibilang tayo ng mga isla (inaudible) instead of rehabilitating it (inaudible) diba ang, yung Manila Bay case kasama ang Pasay kase Manila Bay pa din ito, anong impact nito sa Manila Bay case kase nagkaron ng drainage, ng infastracture dun sa dalawang isla, eh (inaudible) pa yung Manila Bay case hanggang ngayon nagcocomply pa ang mga agencies, DPWH, (inaudible), MMDA I don’t know kung kasama pa yung LGUs, concerned with that ma aadress ba to kase hanggang ngayon (inaudible) ng Supreme Court sa Manila Bay case. Yung sinabing kukuha ng cleaning materials sa San Nicolas shoal (inaudible) ba yung San Nicolas shoal kase sabe yung area na yan wala ng corals, wala ng mga isda, yung San Nicolas Shoal anong meron dun, kukuhain natin dun yung mga cleaning materials, ang laki laki nito, tapos sabe din ni mayor na high density ang Pasay City. So wala na talagang makitang lugar (inaudible) ng isla , sabe din naman ni doctor na yung sa gagawan ng isla (inaudible) yun, saan naman ilalagay yung mga (inaudible) material, eh wala naman tayong matatambaka kase high density na ang Pasay City, uhh, tapos yung (inaudible) , diba sa local government (inaudible), required di ba yung pag may substantial alkylation ng boundaries ng isang syudad , kailangan muna ng plebesito, para aprubahan? kase mukhang gagawa ng dalawang isla so, substantial alkylation to ng boundaries ng syudad, kase kailangan muna unadible for applying for (inaudible) ang ano yan plebesito, so, so far yun lang po muna.

Public Hearing Officer: Unahin muna natin yung sa issue ng study about sa climate change

Dr. Alabastro: I’m sorry kung malapit sa puso namin yung (inaudible), yun pong bahagi hindi lamang ang pag aaral dito, kundi sa aming pag aaral, sinabe po natin na ang proyektong ito ay hindi magdudulot ng impact sa climate change, ayun nga po sa aming pag aaral ang climate change ay dulot ng mga aktibidades ng ano bang tawag dun, ng mga gawa ng tao galing sa China, United States at iba pa, mas malayo po ang Pilipinas, nagbigay po kami ng isang sample ng climate change impact, ito po ay hindi dito sa proyekto, mas malaking proyekto, hindi po magbibigay ang proyektong ito ng any significant greenhouse gas, yung panggagalingan ng greenhouse gas dito yun po ang climate change,

Public Hearing Officer: Sir clarification lang po dun sa tanong nya, isasama po ba yung climate change impact yung sa sea uhh pagtaas ng tubig?

Dr. Alabastro: Ah opo, pinakita po naming sa inyo yung study, ewan ko kung, ang mismong projection ng ITCZ binanggit ko na po anong reference, anong page number, ang sea level rise ay hindi nanggagaling sa atin kundi galing sa ibang bansa ay most likely it measures about .3-.4 level rise, so with or without the reclamation project magkakaroon po ng sea level rise wala po tayong magagawa, hindi po tayo ang nagbigay nyan, ang sagot nasa likod po naming ang protection ng ITCZ with reference at page number nung kanilang projection

Public Hearing Officer: yung sa storm search daw po?

104 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Dr. Alabastro: yun pong storm search ay part po ng pinakita naming oceanography, storm search nandon po ang modelling ng storm search at sinabe ko din po na ito pong mismong proyektong ito, reclamation project, provides safe beneath effect, depensa po ito sa storm search, kase with or without the project magkakaron pa din po ng storm search, wag naman pero pwedeng magkaron. And in fact, po yung Tacloban (inaudible) ano po yung (inaudible)storm search, ano pong ginawa sa Tacloban, reclamation by providing defense mechanism through reclamation project, ang solusyon po reclamation, hindi ko po nilagay sa likod pero pwede pong ilagay yung case sa Tacloban (inaudible) storm search, protection against that is the ongoing reclamation project coastal defense project. meron pa pong tanong?

Public Hearing Officer: Question na lang about sa LGUs, tsaka yung isa pang concern na ano yung (inaudible) ng government regarding dun sa Manila Bay case.

Engr. Lagmay: ahm yung tungkol po sa alkylation ng boundary hindi po kami nag alter ng boundary, yun pong aming proposal reclamation is within the political and legislative jurisdiction ng Pasay, una humingi po kami ng tulong sa NAMRIA, actually sa NAMRIA po, para dun sa delineation ng aming municipal water and binigyan po kami ng NAMRIA dahil binigyan kami ng mapa nila kung saan yung extention ng municipal water ng Pasay City, and yun po ang aming proposal sa reclamation ay within the municipal waters of Pasay City, base po dun sa I don’t know sa RA, di ko saluado yung number ng RA, first 3 km from sea shoreline yun pong municipal water ng Pasay City, with provision of Local Government Code, ah ngayon naman po yung sa Manila Bay Clean up, actually po lahat ng mga LGUs na naka above sa Manila Bay bound po nung mandamus ano ng Supreme Court at sa kasalukuyan pong dire diretso po yung aming mga initiative para po makasunod, hindi lang po yung LGUs kundi lahat ng mga (inaudible) na nandoon sa paligid sa Manila Bay, so dirediretso po ang aming mga initiative para po makasunod kami sa mandamus ng Supreme Court.

Atty. Jennifer Ramos: follow up question lang po sa climate change sir, ang ibig mo bang sabihin sir, yung sa sea level rise, hindi po yung contribution ng proyekto sa climate change, kundi ang impact ng climate change, one of it ay yung sa sea level rise, paano po yung tinitingnang proyekto, kase ang sabe nyo na ang latest report ng sa ITCZ ay ilang cm na ang taas, pero hindi pa din titigil dun no na tataas at tataas yun, in fact ang sabe ng (inaudible) mga 1 meter ang protection nila, so gano po ba kataas ang isla ninyo at san yung mga storm search nyo.

Dr. Alabastro: Ang finish product po is 4 meter above (inaudible) 4 meter yung taas sa lebel, samantalang ang worst situation sabi ng ITCZ, baka nga magkaroon ng sea level rise and point something lang yung meter, yun pong flat form na yan, we can provide some kind of ah caution kung magkaroon ng sea level rise (inaudible) kase hindi ako apektado ng sea level rise. Ngayon, mandamus, yan po ay kasama sa report namin, baka matulungan ako ng aming tumutulong sa legal. On layman’s term, sinabe po sa summary report, mandamus is to order hindi to restrain, mandamus orders the cleanup of Manila Bay, maganda po yan, tinutupad ng LGUs at iba pang ahensya, wala naman sinabe si mandamus of what not to do, they tell us what to do, but what not to do, hindi po sinasabeng bawal ang reclamation infact makakatulong po ang reclamation dahil binanggit po ng kagagalang galang na alkade na 35% po yan (inaudible) so dito magkakaroon ng fund na mapalinis pa natin ang Manila Bay, so yung sa mandamus pwede ba yung (inaudible) na sinasabe naming na hindi po relevant ang mandamus sa ECC application in layman’s term tama po ba ako? Yan po ang nakasulat sa aming EIS report, ok, maraming salamat po, hindi po ako abogado pero nagkonsulta po ko sa mga iba pang legal

Ms. ISSA of Wetlands International: Gusto ko lang i share na yung sa last week, we had a forum under sa rehabilitation ng Manila Bay and we invited experts from (inaudible) at iba pang mga institutions kagaya ng DENR, at may mga issue po ngayon na gusto kong sagutin based dun sa shinare nila, actually lahat ng share nila ay gusto akong ishare sa inyo para maging (inaudible) yung discussion na to, ahm first po gusto ko pang ma addressed yung sa sinabe ni Atty. Regarding sa lack of marine species ng Pasay City (inaudible) ng Manila Bay, ah tapos wala ng mga species kase dumami yung mga fish feed species at tsaka mataas nga po yung point overview so sagad sagad na yan sa

105 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

Manila Bay, so ano pa ba, and then yung sa ..unaudible.. regarding yung sa storm search (inaudible) isla regarding to the fishermen followers (inaudible) pwede bang sumabay sa (inaudible) artificial framework tapos gusto ko lang po i share (inaudible) sa Tacloban at hindi po reclamation yung solution sa proposal ng (inaudible) soft and hard engineering build with nature approach, so competition ba sya ng, so eto bang environment at the same time protecting the nature, so siguro ang mashe-share ko lang po is hindi actually question pero suggestion po kung ok lang. since ina advocate natin yung sa build with nature approach, so ano yung proactive ways ng project para ma ensure yung sustainability ng Manila Bay at the same time, bakit po ganun yung sa plan (inaudible) yung ecosystem by (inaudible) services meron po kasing (inaudible) sa last week forum, na may ibat ibang percent ang ibat ibang bahagi ng ecosystem which is will help us determine long term and short term kung ano yung (inaudible) ng isang project sa mga tao at sa environment, maganda po sya yung (inaudible) violation, yun lang po

Mr. Hao: ok I would like to call on the project consultant (inaudible) lalo na yung tungkol sa traffic, kanina consultant (inaudible) ng traffic management with law (inaudible) then I said no, because the I only came her for the reclamation (inaudible) of course if you would propose reclamation (inaudible) local and international, ok because of the possible problems, naawa ako sa mga fishermen, of course I understand their (inaudible) mga fishport nasa bataan, sa cavite, just two, we have to study the Hong Kong reclamation, you know, when you’re a tourist in Hong Kong, you’ll glad to visit the (inaudible) the typhoon on fishing fort (inaudible) kase gusto ko (inaudible) to fetch but because of the reclamation there’s no more fishing products coming to Hong Kong (inaudible) they are imported from Vietnam, Indonesia, Philippines, from other countries, why? Because of reclamation (inaudible) malayo dyan, reclamation was in critical area, malayo, but I (inaudible) the fish, (inaudible) ng Manila Bay (inaudible) from the provinces and then in Manila (inaudible) baka sa Zambales na, they are not in Bataan, they are not in Cavite anymore, awa ako sa mga kabuhayan ng mga fishermen, so addressed that problem in the Philippines of reclamation (inaudible) yung sa sea level that matters, of course yung sa storm search kasama sa, ok I don’t know what to (inaudible) Filipino fried fish (inaudible) in business, it’s disaster sabe nga ni (inaudible) now this time, (inaudible) of Manila Bay (inaudible) no to (inaudible) project and Roxas Blvd., sabe ni Doctor Alabastro, we have no reclamation in Manila Bay, we can expect storm search, we can expect the creation of underground water, we can expect disaster in the Metro Manila area, I hope (inaudible) do not happen without a pre-caution, thank you.

Public Hearing Officer: Thank you sir.

Representative from PRA: (inaudible) regarding PRA and reclamation, so regarding po dun sa (inaudible) na sinasabe nila, regarding po dun sa sinabe ni Doctor Ed, na it is not something that is planned or approached (inaudible) the reclamation, (inaudible) that PRA wants to understand exactly is the concerned of everyone in here. So we conduct a study that we would like to (inaudible) para po sa reclamation, maging mas integrated yung consideration natin, so siguro .. (inaudible).. that were able to study the both side of the reclamation and then (inaudible) planet (inaudible) para maging maganda yung mga consideration natin sa lahat ng mga .. (inaudible).. for the planet, for the system, for ecology, for everything (inaudible) reclamation project, mas magiging integrated po, kaya po gusto po ng PRA magtayo ng ganyang study and na-mention ko po before na all of these we consider including na din po sa climate change na (inaudible) natin (inaudible)we facilitated by the DENR (inaudible) included in the PRA projects. if the project is gonna be contributing or how can it be.

Representative from PRA: So, gusto ko lang din po kayong informed na ang PRA is actually looking to include coastal protection or coastal defense strategies into the plans of reclamation projects para po sa consideration ng climate change natin and also other agencies are also consulted within the EIA process so including na din po dito yung PHILVOCS na sila din ay nakakapag raised ng mga ibang concerns like sa hazards and the modeling of the preparer kung pano nila dapat I consider lahat ito like the level of the xxx air in the project area. Yung mga ganung bagay po dapat I consider lahat. And then regarding Tacloban po, sorry una muna po siguro yung sa San Nicholas Shoal po, regarding sa study

106 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT that had been conducted wala pa po syang ECC pero EMB is required xxx mas assured din po if ever the SNS will be granted an ECC and will be used for Reclamation Projects DENR will also insured na wala nga pong maaapektuhan na marine ecology or marine life. And then for the Tacloban Project po, the current Project being undertaken by the PRA Tacloban is actually mangrove xxx reforestation. It is a soft measure but it is true but we are proposing xxx the plan is actually for soft and hard like xxx earlier and it is also true that what Dr. Alabastro said earlier that part of the proposal is reclamation. So yung hard part of it is definitely for soft and hard part of it is actually possible for reclamation and then the shoreline is like putting up a protection xxx saw earlier sa presentation nila is xxx area para gumawa ng hard structure for the prevention. But currently, hindi pa po sya under xxx. Yun lang po, very xxxx on the xxx. Thank you.

Atty. Corpus: I’m Atty. Corpus from the Office of Senator Cynthia Villar. Xxx of this Public Hearing from the DENR and the Senate Secretary xxx to attend this Public Hearing. Ang number one xxx na nakita ko sa presentation ni Mr. Alabastro na yung sinasabi nya na yung source ng filling materials for the reclamation ay yung SNS. Just a month ago or more than month ago we received a formal communication from the DENR-EMB Director Torbella that any extraction from the SNS is prohibited ibis sabihin po pinagbawal na po ang extraction ng filling materials sa SNS. Xxx Mr. Alabastro does not change the presentation it is the same time presentation that makes in other Public Hearings that he conducts. Siguro kailangan naman na maghanap sila ng other baka this time naman bundok na tatapyasin para pang reclaim. So sa ngayon ho, wala hong source ng reclamation filling materials. Yun ho yung una. Pangalawa ho, which xxx also brought up by the lawyer from oceana, yung tungkol ho sa effect ng yung tungkol ho sa xxx ng Mandamus tama po Pañera? Ang alam ko ho sabi sa continuing Mandamus ng Manila Bay which is issued on December xxx. We should remove all obstruction that could xxx the flow of water so I believe that reclamation since technically talagang tatambakan ang tubig xxx it’s an obstruction anyway itself. Kung tama ang xxx na nga xxx sila sa xxx yung mga samahan natin ng mga mangingisda. Kase talaga naman po na kapag tinakpan nyo po ang dagat, e ang una hong tatamaan dyan ay yung mga isda ho. Kawawa naman yung mga isda hindi kyang umattend ng Public Hearing. Xxx yung mg isda, even the smallest particles, lahat ho yan ang Manila Bay ho is one big ecosystem xxx operation that you would do in Manila Bay xxx effect on xxx Manila Bay and even sa atin ho na mga nakatira dito sa kalupaan. Kahit na taga Pasay ka, Las Piñas, Manila lahat po ng cities. Xxx cities and one municipality, and even the provinces of Bataan, Cavite, Bulacan, lahat ho tayo na dikit sa Manila Bay. Any alteration of the ecosystem in Manila Bay may affect po iyan lahat sa atin. Alalahanin nyo po na ang Manila Bay ay natural drain ng lahat ng tubig na galling sa Metro Manila at sa mga probinsya na nabanggit ko. Diba kapag tayo binabagyo, tayo ang binbaha, lahat ho yon ay par sa Manila Bay. Lahat ho yon ang bagsak non sa Manila Bay, so even if you live in Quezon City any alteration in Manila Bay your affected. Pangalawa ho, yung sinbi ho ni Dr. Alabastro that the reclamation is not an Environmental Area because sabi nya is 8.5 km from the LPPCHEA. Ang LPPCHEA ho ay yung Las Piñas Parañaque Critical Habitat and Ecotourism Area which is located in Parañaque and Las Piñas and I xxx to disagree kasi pasay is just beside from Parañaque and ang LPPCHEA ho ay hindi na sya Critical Area as of June 22 Protected Area na po sya. So the area that is being considered here is part of the buffer zone of the LPPCHEA. Pangalawa ho, kasi ho ang LPPCHEA ay meron hong mga mangroves plantation dyan so na coconcern ho kaming mga environmentalist na yung flow ho ng tubig ay makakaapekto sa buhay ng mga mangroves. Bakit ho napaka importante ng mangroves? E iyan lng naman ho yung tinutuluyan ng mga maliliit na isda, yan po yung kanilang nursery bgo sila pumalaot sa malaking dagat. So tlaga ho kami sa Las Piñas Parañaque poprotekhan ho naming yung area na yan. Even the prompted Senator Villar xxx Writ of Kalikasan, gainst PRA and DENR, against the Proponent of the Reclamation in Las Piñas. Which as of this day xx kinasel na ho ng DENR yung ECC doon xx. So if they want to do reclamation they have to go through all the process so yun ho yung mg actual na nagawa namin. Balikan ko lang xxx hindi ho environmentally critical area yung Pasay, itong subject property na gusto nilang I reclaim. Hindi ho totoo yan, sa reclamation itself it’s an environmentally critically itself so kasi nga ho inaalter nya yung ecosystem so ano pa ba? Teka lang, may notes ako. Ah ok. Meron xxx nabanggit kanina na ang area clearance is xxx for the post ECC. I gather from the legal of DENR xxx that is not the case are

107 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT clearance should always proceed the issuance of ECC so absence of area clearance I don’t think xxx nag apply na kayo ng ECC. Ok iyon. Tapos that’s about it pero kung meron ho kaming kung meron man po kaming mga additional questions frm the committee on environmental and natural resources on senate that we would like to bring up we would always have an investigation to the inquiry regarding the status of the reclamation in the Philippines. Maraming salamat po.

Atty. Madrona: I’m Atty. Madrona, City Legal Officer of City of Pasay, xxx clarify lang don sa about the continuing Mandamus to the Supreme Court, we read the case carefully the mandamus for the purpose of improving the water quality. We presented a while ago, it is not xxx as mention there will be no xxx reclamation in the xxx itself. We believe that xxx successful xxx will be approved in the Manila Bay area. What xxx will be the Pasig River xxxx the Pasig River for the Manila Bay t for the records Pasay City is a xxx among Metro Manila, LGU with respect to compliance to the continuing Mandamus. Nagawa po naming sa Estero de Gallina xxx were doing for the xxx in compliance with this. So we believe na the xxx pollution that were further improve our project we further improve our compliance that xxx continuing Mandamus. For clarifications, thank you.

Dr. Alabastro: I xxx to respond, medyo madami. Ito ang unang nakita ko, SNS meron bang marine species dyan xxx environmental impact area. SNS is within the political xx of PRA. Sila ay nag apply ng EIS, sila ay hindi pa rin nabibigyan ng ECC or xxx. So kung meron mang gustong kumuha ng fill materials dyan and kakausapin nila PRA. Iba po, kung Pasay o kung sino man ang may responsibility ng Pasay o xxx SNS ay magagamit naman ng PRA xxx kung angkinin naming na kami ang may responsibility dyan. Ngayon yung hindi na pwedeng kumuha, talagang hindi pwede kasi walang ECC, so with or without the memo hindi talaga pwedeng kumuha as of now ng anything materials sa SNS dahil walang ECC. So hindi ko po alam kung meron pang ibang memorandum xxx wala naman po kaming alam. Baka meron na hindi ko po alam.

Atty. Corpus: Sir kase, yung application ho ng ECC pagkuha ng filling materials to be extracted from the SNS is a subject to a separate EIS diba? Ngayon sinaabi ko na nga ho sa inyo na kung sinasama nyo sa presentation nyo nay un ho yung source, sinasabi ko na sa inyo pg na grantan kayo ng ECC dito, e xxx wala hong ECC xxx sa Pasay City, ke sa Manila, ke sa PRA xxx sa DENR ho nag apply. Xxx so siguro I revised nyo yung ano ninyo kailangan nyong kumuha ng ibang source ng filling materials kase and I think that EIA yung taga DENR should EMB to diba should take it to consideration na yung report sinaabi na SNS e hindi na nga pwedeng kumuha ng filling materials doon sa SNS kase pinag babawal na. so what are we talking is para naman ho na wala ng reclamation. Ano hong source ng reclamation nyo? Diba ho ba ang ibig sabihin ng reclamation ay pagtambak, eh ano po yung pagtambak na eh wala kayong source.

Dr. Alabastro: Xxxx, ah sinasabe po namin na that is a separate project ng Xxxx, we were asked kung saaan ang mga options namin, sinabe namin sa Xxxx, yung disposal ng Xxxx, isa pa po, mabalik po ako sa Mandamus, kase mag iinvest ba, sino ba ang investor? Mag iinvest ba dito sa Xxxx, 75 billion pesos para magawa ang dagat, edi sana budgeted ko na, hindi maganda ang project, DAHIL PO SA Xxxx, ay mamamaho ang dagat o masisira ang kalikasan. Kung di nyo po nakikita, na contrary itong project na to sa Mandamus, baka nga magkabaliktad noh, young sinasabeng magandang yung project, Xxxx San Nicholas Shoal, ah medyo siguro may ibang xxx, eto po yung aming sinasabe na conceptual project manual, iniikot pa namin yung iba’t ibang area, sinabe po ng iba, nagpakita samin ng mahabang study. Tapos yung Manila Bay ang sinasabe po natin, ang pinag uusapan po namin why considering the order as Manila Bay is this impact. Kaya po ang ginawa namin, tama naman po yung sa xxx, except ano po bang boundary na yan, hanggang saan ba yung boundary impact na yan. Gumawa po ng circulation xxx, kung hanggang saan pwedeng xxx tong project na to, itong impact na to. Nasa report po naming, even the xxxx, sinabe yung sa circulation xxxx, hindi po nagdudulot ito ng highly significant impact. Isa pa po, napanuod ko po ang iba’t ibang Filipino Scientists, nung February 15, 2016, nagconduct po ang mga xxxx ng Open Xxxx sa mga scientists ng Research xxxx, nandun si Dr. xxxx, Dr. Lagmay, ako po’y nandito din, nandun di si Jun Palafox, ang sinasabe opo naming, ang impact ng

108 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT isang project has to be viewed by impact areas cities , hindi pwedeng sabihin na ipasa ito, it has to be xxx, yung sa xxx ganito eh. Yung sa Bicol, Pinatubo at ibang areas, ang sgot natin ay xxxx, bahagi ng sinasabe na xxxx na climate change. Xxx is this, is the study area, hindi po kasama dyan ang mga xxxx ng Bicol, xxx ng Catanduanes, kase po yung pong issue ng impact na to. Yun pong isa sa bahagi ng aming pagpupulong, hindi po sinabing xxxxx, nagpahayag po kami ng mga xxx. Pati po yung sa mga storm search, xxxx, yun pong na kay Lagmay at sa PRA, yun pong xxx, so that is the xxx in 2016. That is the explain of protection of ng sinabe ko pong maaring tama o maaring mali. Pero tignan nyo po yung Supreme Court, ano ba iniexpect is ano bang impact xxx, pag pinagsama ang halimbawa yung sa, reclamation project, except dun sa issue ng climate change, iba yun. Pero nirerespeto po namin yung xxx, pero tama po yun, yun sa sinasabe ko lang, xxx reclamation project, hindi po yung xxx. Salamat po Sir

Mr. xxxx: Diba po yung sa xxx PRA clearance sa ECC na sinabe pong under the xxx January 30, XXXX of the ECC. However, yung PRA xxx the results of XXXX last 2015, xxxx before issuance of 2014 approved by PRA. So, after xx it, there still note that it should not be presented xxx DAO, Nung xxx 30, inissuance po ang reclamation xxxx ng clearance, for the actual approval of ECC. So, pag na approved na po yung ECC dun pa lang makukuha yung clearance? Kase po ok yung clearance, formerly known as the xx under a DAO or xxxxx. So, base po sa xxx standard xxx, tumutulong sa xx ng clearance for this project. For the xxx, yung provision ng xxx yung issuance ng clearance xxxx. Salamat po.

Dr. Alabastro: (inaudible). Yung sa issuance po ng clearance naming sa ECC. So, siguro this month mag i-issue kami ng xxxx ng DAO. Actually, so mag i-ssue yung sa DAO, yung sa bagong guidelines sa ECC and sa xxx, maybe next month or hopefully this month. Kase medyo yung xxx before, medyo malapit, tsaka yung xxx.

Engr. Lagmay: Withstand by the rule, na dapat area clearance muna, kase yung Area Clearance ang magsasabi na yung area ay possible na magkaron ng reclamation. Yun na muna kase kung hindi, edi hindi n asana magpoprogress yung sa xxx ng EIS. So, that’s the national demanding, it’s with the Presidential Decree, xxxx. So which is enacted 1970’s xxxx, so, I’m not sure of what the exact 1970 act, so yun ho. So, we study by that ng xxxx, yun po muna, because, kung uunahin yung sa ECC, which is applying the code of xxxxxx, area clearance will become a stub line. Yung parang ano lang compliance, but with not any purpose. So yun po yung xx line ng Environmentalist.

Public Hearing Officer: salamat po, so dito na muna tao sa likod.

Public Hearing Officer: yung sa issueance, xxx ano yun, yung sinabe nyo na sa higher management na xxx, magkakaroon kami ng xxx, na hopefully this month na I publish na po sya, except po yung sa xxx

XXXXX: yung issuance ng sa DAO, sabe ko nga kanina, within commercial lang, so, I suggest na xxx, na una talaga yung ECC over everything else. Because people can xxx, kase may mga people can (inaudible)

Dr. Alabastro: (unaudible). Kung ako kase ang tatanungin dito, ang dapat ay ECC muna bago (unaudible) nag apply po kami ng Area Clearance, na ayon sa paniniwala namin ay ECC muna bago Area Clearance. Xxx checklist, eh yung mga xxx sa ECC yun eh, kaya nakakalito na.

Representative of DENR-NCR: (unaudible) una yung sa ECC bago Area Clearance, una po (unaudible) na dapat Area Clearance mun bago sa ECC, in fact nag submit na po xxx sa xx (inaudible). ito yung isa sa mga discussion, kelangan may xxx yung ano (inaudible) kase nga may DAO, so, yun may mga (inaudible ) PRA, AMB (unaudible) pilit mag apply. Area Clearance then ECC (inaudible) so parang pwedeng mag apply ng ECC, (inaudible) ngayon sabe ng isang mayor namin, hindi nap o mag apply ng Area Clearance, para pong ano, (inaudible) parang may contribution yan, (inaudible). at

109 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT sinasabe ni Doc na ano ba dapat mauna (inaudible) sa pangkalahatan na issueance ng clearance. Yung mga (inaudible), pero sa ngayon hindi po kami makakapag issue ng Area Clearance dahil po kami natatanggap (inaudible) ngayon po, xx ng DAO, (inaudible). hindi sya DAO, (inaudible) hindi requirement ang ECC kase isa po yan sa mga implementing rules ng (inaudible). So on showing na, we are on the right track so far, (unaudible). We are xxx the office of Hon. Cynthia Villar, we study also the xxx, iba po yung (inaudible) ito po ang, wala daw pong masasabi ang DAO (inaudible).

Paul Villegas: ako po si Paul Villegas from Save the Bay, kasama ko po yung sa xxx, kami po ay naanyayahan dito ng office of Secretary ni Sen. Cynthia Villar, upang makadalo po at maibahagi an gaming tingin tungkol po dun sa kasalukuyang proyekto po na ito. Dun po sa binabanggit ni Doctor, tungkol dun sa Mandamus, ngayon December po ay mapapso na yung Mandamus na yun. So by 2008 po sya inissue at ngayon pong 2018 ang kanyang pgka repaso. At tama po na yung binbanggit ni Doctor Alabastro na medyo komplikado yung Mandamus na yun at wala pong xxx tungkol po sa usapan ng reclamation. Ngunit sa tingin po naming, bilang isang ordinaryong mamamayan,.…ma cleanup o ang pag utos ng Supreme Court na ma cleanup ay upang irehabilitate ang Manila Bay Ngayon nabanggit din ho kanina na marami na din effort ang mga LGU sa pagki cleanup ibig sabihin ho may basehan na po yung Manila Bay na pwede ho siyang tirahan ng mga isda, kung nasunod po ang original na plano ng Supreme Court. Ngayon edi bakit ho mahalagao bakit kailangan irehabilitate, di, hindi lang ho simple irehabilate ang Manila Bay marami po sying pwede sagutin na usapin. Katulad po ng binabanggit po ng mga mangingisda po na kapag na rehabilitate po natin yung Manila Bay, mumura ang bilihan ng mga isda dahil imbis na mangisda sila sa may bandang Bataan, Cavite, mapapalitan po ang pangingisda nila ditto sa badang Metro Manila. At the same time historical din po ang Manila Bay dahil wala pa pong Pasay, Manila ay nandyan na ho iyan at maganda ho siyang idevelop at buhayin po muli yung ningning ng Manila Bay. Kase po tingin po namin kapag ho natuloy ang mga reclamation project ultimo yung view sunset ng Manila Bay ay ma pa privitize dahil kailangan ko pa pumunta dun sa mga lugar na maganda ang pwesto. Kung baga yung mga ordinaryong tao na yan galing Manila, Pasay, Paranaque, Las Pinas ay hindi na makakakita mula ng ganda ng Manila Bay dahil kailangan pa nila pumunta dun sa dulo ng reclamation. Kung kaya po bilang po kami bilang pagtugon dun sa Mandamus nung naglabas si Supreme Court at kami po bilang mga environmentalist at mga educate sa mga nangangalaga sa kalikasan ay tumutulong na rin sa gobyerno dahil ang gusto po namin ay makasatuparan na irehabilitate ang Manila Bay. Kung kaya po sa loob ng mahabang panahon sa mga nakaraang taon ay patuloy po ang aming paglulunsad dun sa mga cleanup, cleanup operation dun sa Manila Bay pangunahi po duon sa may LPPCHEA sa may Las Pinas-Paranaque ah para sa ganun ay mapakita na at kung sama-sama ang mga mamamayan na ito ay linisin kasama ang LGU ay kaya ito ibalik. At ganun din po yung binabanggit ni Dr. Alabastro na kaya pa ho linisin ang Manila Bay at ibalik yung kanyang ganda nang sa ganun edi mapakinabanggan ng mamayan ang Manila Bay hindi lang sa simpleng ano kase lumalabas na nanaig ang usapin ng negosyo kasya dun sa aaah pangangalaga at pag protekta sa Manila Bay. Kaya yun po huli nalang. Actually, kung dito ho ipapatayo yan talaga ho na walang mangrove pero hindi po ibig sabihin nito ay hindi na tayo pwede magtanim. Pwede ho tayo magtayo ng mga mangroves at kailangan lang po may mag initiate. Yun po ang sinsikap namin, katuwang din po ang DENR NCR na makipagtulungan para makapagtanim ng mga ibat ibang klase ng mangrove bilang pangangalago ho sa… sa Manila Bay. Yun lang po.

People clapping…

Atty: Pe Benito: Aaaah magandang umaga po, Atyy. Pe Benito po. Actually ho I would like to congratulate si Atty. Ang for conducting this Public Hearing and open forum for a very fair manner. So pasalamatan ho natin siya. Aaaah makikisawsaw na di po ako sa (inaudible) na yan. I, I, I definitely feel the opinion of Atty. Corpus of (inaudible) office. You know, bakit naman Area Clearance yung kuwan, you don’t have siguro hindi malinaw yung mga DENR regulation but we can look at PD 6081 and (inaudible) and see kung ano yung yung yung requirements ng batas. And which is really the considerations of environmental impact. Sa dami ho ng kuwan ng mga reclamation project ngayon, hindi ko na ho mabilang ang mga reclamation project ditto sa Manila. Kapag pinagsama sama po yan

110 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT magbabago po ang complexion ng environmental impact. Bakit, bakit hindi Area Clearance muna yung itutok, ok? Yung In line with PD 11 (inaudible) and 1586, I think we should comply with the spirit of the law. Below this is strict governmental responsibility to consider environmental impact. Istriktong responsibilidad po ng government natin to consider all impacts hindi lang ho ang mga maliliit but yung mga malalaki pa po. Pagsamsamahin natin lahat ng reclamation project natin, magbabago po yung complexion, ok? . Now, sa presentation po ni Dr. Alabastro he pointed out that the project contractor is carrying out something like Php 75 billion pesos, Php 72 billion pesos ah before that the people is misled let us just clarify, they are not making a charitable contribution mga kumpanya po yan nakalagay po yung prior objective which is always to make a profit. Let me explain, meron ho tayong isang kaso, Via Mare vs Chavez, ang sabi ho sa kasong nyan is Manila Bay is ownd by the state. Now, na realeased po yang decision na yan but they found a loop hole in the Local Government Code that LGU can reclaim which becomes their property which they can take away. So I will, I will resume that the prohibition of the Local Government Code is valid. Now, ang gusto ko lang malaman ngayon is ano po yung sharing with the private contractor ditto sa project na ito? Ok? I understand that this area in this reclaimed area in Manila Bay is something like Php 150, 000 to Php 200, 000. May makukuha po sila duon. Hindi ho libre yan, hindi po charitable donation yan. Hindi ho ba kayo, ahh. Tingin niyo ho yung mga net worth ninyo in a yearly basis? Tumataas ho ba ng milyon yan? But if (inaudible) palagi ho tumataas yun net worth nila. Ang gusto ko lang po malaman bakit ho ganun yung share, share ng city at share ng LGU, ng private contractor, the moment this project is completed.

(inaudible)

(inaudible)

(inaudible)

Atty. Madrona: Actually dun po sa isyu ng Via Mare case is (inaudible) kaya po we have an MOU with the Philippine Reclamation Authority as to the sharing between the National Government and Local Government . Dineclare po yan at hindi po iyan pagaari ng ng pribado sector, ito po ay pag aari ng gobyerno between the Republic of the Philippines and the Local Government Unit of Pasay City just to clarify with that. Then just to move (inaudible) sa Area Clearance at ECC, iba po kase yung interpretation nung sa Area Clearance, Area Clearance as can define dun sa DAO mismo, government issuance over reclamation projects na inissue po ng DENR nuong 2007. Very clear po dun na ang Area Clearance is a (inaudible) document issued by the DENR Secretary providing the authorization or permit to undertake reclamation projects over the applied area subject to certain provision including environmental mitigation and enhancement measure. So, typically, how can the DENR Area Clearance kung wala ang Environmental Impact Statement o environmental impact analysis sa proposed project. (inaudible). Before yung interpretation ng Area Clearance, the DAO itself defines what an Area Clearance (inaudible) is. Iba’t iba ng interpretation, we followed the DAO interpretation na Area Clearance under the DAO nung 2007-20 as amended by 2009-07. So (inaudible) dun po tayo sa issue kung sino ang mas nauna but again this (inaudible) idea na ma issuehan sila as long as may environmental mitigation na and enhancement issue. (inaudible) we believe that it would be a logical issue tong Area Clearance kung wala kaming Environmental Impact Statement, just to clarify that. Thank you.

NAMRIA: (Inaudible) gusto ko lang po magreact duon sa sinabi ni Mam na City Planning Officer ng Pasay tungkol po dun sa nabanggi po niya na humingi po sila ng assistance sa NAMRIA tungkol dun sa Municipal Water. Ang NAMRIA po kase ang naataasan ng gobyerno na mag delinated ng ating municipal waters nationwide. Tama po ang sinabi ni mam na lumapit po sila sa NAMRIA 2016 November meron p tayong natanggap na sulat mula po sa ating municipal mayor regarding po sa NAMRIA na i-drawing po ang kanilang municipal waters based sa RA 7160 or yung Local Government Code or Republic Act 8550. Sinabi po duon sa sulat, ditto po sa huling paragraph na sulat po ni mayor. Aaaahhh babasahin ko po, we clarify ah eto po, in this regard may we request your good office to determine the technical description of the municipal waters of Pasay City based only in Section 1311 of

111 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

RA7160 and Section 58 of Republic Act 8560. At sinabi pa po dun na we clarify that since DAO number 2004-01 (inaudible), we are not filing application for delineation of municipal waters under the questionable provisions instead we are requesting your office for an assistance to plot our municipal water delineation based only on RA 8560. Yun po yung request. SUmagot po ang aming administrator, SI Administrator Tianco nung December 9, 2016 at sinasabi po ditto, babasahin ko po. Dear Mayor Calixto, we are writing this response to your letter request dated 11 November 2016 regarding the captioned matter. We acknowledged that the DENR Administrative Order 2001-17 was already revoked by DENR Administrative Order 2003-07 dated 17 March 2008 and that the existing map, land technical description of the municipal waters of the Cities of Manila and Pasay that are expand in the reports of NAMRIA were based on the DAO 2001-17 that was already revoked. We must qualify that our office has no jurisdiction to rule upon the validity or invalidity of DAO 2004-01 issued pursuant to Republic Act 8550. Nevertheless, pursuant to your request to plot and meet the technical description of municipal waters of Pasay City based on the Section 131R of Republic Act 7160 and Section 58 of RA 5550, please find the attached map and technical description of Pasay City municipal waters. We must stress that the attached plotting is not binding on (inaudible) Local Government Unit concern which have the right to assert the interpretation of the law and delineation in plotting the boundaries of municipal waters in the property (inaudible). Please note that this office adheres the delineation procedure under DAO 2004-01 which considers the effect of all plotted points along the coastline and declared overlapping boundaries. We trust that we fully addressed your concern. Thank you very much. So iyun po yung sagot ni Administrator Tiangco, aaah dun po sa (inaudible) na letter na galing po dun sa EMB, na pinagcocomment po yung NAMRIA sumagot din po ang NAMRIA, si Admimistrator Tiangco at babasahin ko din po ng buo yung sulat na pinadala sa EMB nuon pong July 3. Dear Atty. Matias, as requested by your office, NAMRIA submit this official paper on the Proposed Pasay City Harbor Reclamation Project of the City Government of Pasay. NAMRIA is the lone agency in the government authorized to delineate the limit municipal water for coastal occupancies and cities for the whole country in accordance for the authorize, with the authority granted by the Department of Agriculture under Section 123 of Republic Act 8550 and as amended by Republic Act 10854, the plotted municipal waters of NAMRIA were not with accordance with the guidelines issued by the Department of Environment and Natural Resources Administrative Order # 2001-17 Guidelines for Delineating Municipal Water and Department of Agriculture Administrative Order # 1 Series of 2004. Guidelines for delineating municipal water for municipal or city offshore island, based on NAMRIA’s record there was no certified technical description for the delineation of municipal waters and copy of the document chart were not certified with technical description of the municipal waters of the City of Pasay that were delineated or plotted based on the old guidelines and or existing guidelines. On 11 of November 2016, NAMRIA received a letter from the Honorable Mayor of Pasay City with subject and to quote “we request for plotting of Pasay City Municipal Waters based on RA 7160 and RA 8550 before granting the request (inaudible) NAMRIA that have certificate from Pasay City (inaudible). The process of delineation of municipal waters and how it was being plotted based on the existing guidelines was explained. We were told that the Pasay City representative and the contained in the letter that all (inaudible) NAMRIA was to plot and determine the technical description of the municipal water. The municipal water of Pasay City based on RA 7160 and 8560, so sa proposal ng NAMRIA, we assess that the project has requested binding nabanggit naman po namin kanina and we adhere to the delineation procedure of the DAO which considers the effect of the (inauble) point along coastline. As to the correctness of the existing guideline issue by the Department of Agriculture, it is the showing of (inaudible) that the amended (inaudible) NAMRIA only follows what is on the guidelines. Pagka po kase itaas po natin yung municipal waters, sinukat po natin siya ng 15 kilometers na manggagaling sa coastline, ang mangyayari po kase magkakaroon ng overlap duon po sa mapa. Ang pag plot po kase ng municipal waters meron pong guidelines na sinusunod po para po sa dino-drawing nung sa guideline na inissue ng Department of Agriculture. Kung halimbawa po let us say na yung coastline natin ay palabas, paganito po siya. Ang magiging drawing po ng 15 kilometers ay papunta ditto kung halimbawa po yan po ay Pasay o Paranaque nandito ang Paranaque, nandito ang Pasay magkakaroon po yan ng 15 kilometers ditto, nandito naman ang Manila magkakaroon din ng 15 kilometrs ditto. Kung ang Manila naman po ang

112 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT mag do-drawing, mag do-drawing po sila ditto. Kung magkakarron po ng (inaudible) sa gitna kanino po mapupunta iyun? Dito din po sa Pasay at Paranaque mag do drawing sa Pasay mag drawing din po sa Paranaque, magkakaroon po ng triangle dun sa gitna, so meron pong maiiwanan. Kanino po mapupunta iyun? Kung ang coastline naman po natin ay papasok, halimbawa po pakurba, gaya po ng sa Manila, pa ganyan, pag nagdrawing po tayo ng perpendicular na 15 kilometrs pa punta ditto at nag drawing po tayo ng Pasay 15 kilometres, magkakroon naman po ng overlap. Kaya po yung pag do drawing na ginagawa ng NAMRIA, ay sinusunod po talaga namin yung guidelines para po maiwasan namin yung overlap. Ang ginagawa po ditto ay nagkakaroon po ng Public Consultation, kinakausap po yung mga Local Government ahmmm Representatives, yung mga mayors po ay pinapagawa po ag pag do drawing para po maiwasan ang overlap at sa pag resolve naman po ng boundary overlap, may mga dalawang magkakatabi na bayan at munisipyo ay ahhmmm tumutulong po ang NAMRIA kung paano po mareresulba yung pati kase po hindi po kami ang magsasabi na nandito ang boundaries, wala po yun sa mandato ng NAMRIA yun, ang makakaresolba lang po ng boundary ng magkakatabing bayan ay ang dalawang magkatabing musipyo at yun nga po, hinuhimok po namin na yun pong magkakatabi na mga bayan ay mag usap usap para po maiwasan niyo ang conflict (inaudible). Yun lang po Salamat.

People clapping…

Atty. Madrona: Salamat po Sir from NAMRIA, NAMRIA as mentioned has no final say on the (inaudible) but definitely we are working with our neighboring LGU (inaudible) as with the legal basis of our municipal waters as you mentioned the NAMRIA letter, we have an ordinance on the municipal waters in our CLUP as approved by the (inaudible) and the HLURB last year. So, it will be included in our municipal waters, but (inaudible), we are actually working now with our neighboring cities. So, rest assured we will (inaudible).

Public Hearing Officer: Ah okay, salamat po, atty may follow up question lamang po sa Via Amare case na tinanong kanina ni Atty. Pe Benito, ah among the chair ano?

Atty. Pe Benito: Ah the share between the city and the private contractor sa reclaimed area?

Atty. Madrona: Subject for approval po ng PRA, ah actually we have ahmm, its been, we will be entering up to the (inaudible) nag MOU palang po kami sa PRA. Ang MOU po mismo total naka delineate na po dun yung sharing mismo. What has been clear now as per PRA po na what we call this… ang kanilang rules sa (inaudible) 60-40 under the Republic of the Philippines and the Municipality of Pasay.

XXXX: Sino po yung 60%?

Atty. Madrona: Republic of the Philippines, (inaudible), so yun po yung (inaudible), so as to the project, subject po eto ng approval ng Philippine Reclamation Authority (inaudible), we will be entering with them our Memorandum of Agreement. As of the moment, nasa MOU palang po kami, nag aapply po kami for reclamation project as a requirement po dun is of course we should have ECC. So ayun po marami pong requirements, we have a lot of stages to follow pa before pa kami makadating sa ganun na step. So as of the moment we could not state clearly kase nga subjected to the national government. As (inaudible) to 146, dadaan pa po sa NEDA eto, it is a long process. May NEDA pa po kami sa EO 146 so hindi p ito madalian, we believe all the agencies of the government are looking at our project. And we are certain that they will be examining likewise and we are glad and happy to handle. Thank you.

Public Hearing Officer: Ok, concerns pa po? Yung iba, please.

….

Public Hearing Officer: Ah sige po, wala na? I just want to clarify, wala na po ba? May mga concerns pa po ba kayo na gusto niyo iraise? Ay sige, yes sir, go ahead.

113 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

….

Mangiginisda sa Las Pinas: Ah magandang umaga po sa ating lahat, ako nga po pala si Vic Martinez mula po sa mangingisda ng Las Pinas, ah ngayon po sa [resentasyon ni doctor kanina, para hindi p kakulangan, parang yung impact na ano parang yung sa alon, hindi naman po iyong halimbawa po yung high tide (inaudible) hindi po aabot ang tubig diyan. Mula ng magkaroon ng reclamation, kase (inaudible) may lupa na mababa talaga. Ngaun umaano ngayon sa bahay namin ang tubig, so siguro nga talagan napapagusapan natin ngayo yung Manila. Syempre lagyan natin ng lupa, aapaw yung tubig so wala pong (inaudible) mababang lugar eh. Eh duon po sa high tide syempe taas yung tubig ano pa kaya po kung salubungin yan ng baha galing dun sa bundok, ano po ba ang mangyayari?

Public Hearing Officer: Ok, ahhhh Dr. aaahhhh naiintindihan niyo po yung question, sir? Ok.

Dr. Alabastro: Ah tama po ba ang aking pagkakaintindi? Yung parang may isang banyerang tubig na kung kagyan niyo ng lupa, aapaw iyun.

Mangiginisda sa Las Pinas: Opo, tama po.

Dr. Alabastro: Ah… ok, ang nakikita ko lang ganito. Yung proyekto na ito, will require a filling ng lupa, 50 million cubic meter, ang Manila Bay po 30 Billion cubic meter. So kung sakali po maglagay kayo ng lupa, aapaw ba? Hindi po namin nakikita kung paano mapapa-apaw ng 30 million so 60 million cubic meter ng lupa ang 30 billion cubic meter ng lupa. Ngayon, dalawa pa po, so nagpatong tayo ng lupa ditto pero naghukay naman po tayo ng lupa sa San Nicholas Shoal. Pangalawa po kung yan po ay aapaw, ang Manila Bay po ay connected sa South China Sea. So dapat ang atin pong titingnan na banyera ay Manila Bay at South China Sea, hindi pwedeng Manila Bay lang.

Mangiginisda sa Las Pinas: Pero po (inaudible). Pero kami po nararamdaman po namin dahil kami po yung nasa lower area. Nung araw po ay ( inaudible), almost wala pa pong ano, hindi pa po inaabot yung bahay namin ng tubig. Nagyon po matapos yang mga reclamation na yan, Las Pinas taga Barangay( inaudible) pa po ako at nung nito p nung mangyari yung reclamation na yan, yung tubig po nandun na po sa may bahay namin, sa madaling sabi po dahil sa ano sa resulta ng climate change talgang umaangat yung tubig. Paano po kung (inaudible) alam ko madami pang magyayari na reclamation, ano po kaya mangyayari sa buhay namin dyan. Pag high tide mataas ang tubig tapos sasalubungin ng baha. Yun lang po, salamat po.

Public Hearing Officer: Aaahhh, doc…. May ahhh, may response po ba tayo dun? Yung relevance daw po ng climate change sa reclamation project at sa pagtaas ng tubig?

Dr. Alabastro: (inaudible) Ang ating ah project ay hindi magbibigay ng pressure sa climate change. . Wala pong kinalaman ang project na ito sa climate change. Ang climate change ay dulot ng mga (inaudible) emission galing sa Russia, China, United State. Claro po iyun. Pangalawa po, yung climate change naman ang maaring maidulot sa project ay baka po sa sea level rise. May project man o wala pwedeng magkaroon ng sea level rise. At sino ang magbibigay at ano ang sanhi ng sea level rise? Hindi lang po dahil sa reclamation project dahil din po sa climate change na binubuga ng mga greenhouse gas gaya ng ibang bansa. Yun po ang nakikita naming, wala po kaming nakikita na epekto or (inaudible) by the project on climate change.

Public Hearing Officer: Yes mam.

Resident of Paranaque: Kase po ahhh. Engr. Alabastro, meron pong mga proyekto kagay po ngayon, na preparer ng Pasay pero kayo din po ang preparer ng Paranaque, alam ko dahil ako po ay taga Paranaque at yun din po an gaming question sa inyo, kung iisa-isahin niyo lang po yung project, talagang pwede naming matanggap yung sagot niyo. Pero alam po natin na konektado po lahat yan, konektado lahat yan sa Manila Bay. Kaya yan po ay may epekto and don’t ano the climate change, kase ngayon palang po tayo ay apektado na ng climate change. Baka di po natin alam itong mga

114 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT pagbagyo, yung ating mga pagbaha, apektado na po tayo. So ah ang sinasabi ko lang po ay we cannot deny that itogng mga mga iaano sa atin, itong mga project na ito ay mayron mga sa ating hindi magandang ahhh epekto kaya nga sinasabi naming bakit pa natin i-undertake, para saan, para kanino at what cost, what price and for what? Ayan nap o yung mga fishermen natin, sinasabi po nila na ano,. Sa Paranaque nakakahuli pa po ng mga isda na mga maliliit at yun po ang kinakabuhay ng mga fisherman sa Paranaque. Kaya hindi po kami naniniwala na ang Manila Bay ay walang marine life (inaudible) at marine resource. Kailangan nga po natin linisin upang magkaroon po at mas lalong yumabong pa ang ano nito ang yamang dagat na binibigay nito. Salamat po.

People clapping…

Dr. Alabastro: Ganito lang po, yung… sinabing marine life, ahhhh what ahhh Manila Bay ay ang tintingnan po naming (inaudible) ay hindi po Manila. In connection sa mga reclamation projects (inaudible) mga 20, 000 hectares, tinangnan po natin kung saan nangagaling yung greenhouse gas. (inaudible) Yan po ay (inaudible) ng IPCC, isa-isa po sinasabi kung saan nangagaling CO2 at tyaka NOx. Sa buong mundo ginagamit yan , wala po duon nakalagay kase ang reclamation project ay madami sa China marami sa ibang bansa. Hindi po kasama ang reclamation project sa major sources ng greenhouse gas. (inaudible) at wala naman po kaming alam na project na paisa-isa. Maaring meron sa Paranaque, maaring mayroon ditto, magkakaiba po iyun. Ayun po.

Public Hearing Officer: Ok po. Ahhhm concerns with, questions, comments, yes mam.

Lyceum College of Law Representative: Hello po, magandang tangahli po. Ahhh… from Lyceum College of Law, aahhh siguro po gusto ko lang po mag speak sa general public, kase po di ba kanina may na address na traffic issue, meron din po mga nag address ng concern nila whereas po ang sagot ng ating local government ay let us focus on the reclamation phase of the project. Hindi po ba siguro parang mas maganda kung isang full blown siya po na Programmatic EIS nalang po kaya para po lahat ng concerns, lahat po ng issue ay masama na total naman po nasabi ng local government na ang Pasay po ay marami ng na reclaim project, siguro po hindi na magiging problema na magkaroon ng isang programmatic EIS para ma shoulder o ma address na po lahat ng concern ng mamamayan kase po kung general public po kayo magtatanong kayo, nasa phase palang po tayo ng reclamation at hindi nasagot ang concern niyo, baka po ang tendency natin ay tambakan na ho ang umattend sa susunod na hearing which is the aaahh ahhhmmm program o which is yung second phase na po ng reclamation na nandito sa paper, not the second phase the first one is reclamation, the second is the ahhh operations phase po. Di ba parang ok po siguro pag ganun, kung although optional lang naman po yung Programmatic EIS, di ba? Pero naiintindihan ko naman po na siguro talagang maganda ang plano ng ating Local Government Unit, hindi naman po siguro masama kung baka magkaroon din sila ng interest to make a Programmatic EIS para po sa isang Public Hearing ma address lahat ng tanong ng general public (inaudible) kase baka mamaya rin po may fear din po siguro tayo na kung pa patuloy ang reclamation na ganitong project, baka po mamaya magamit at magamit ang ganitong systema natin. (inaudible)

Atty Corpus: Can you clarify what is Programmatic EIS? Kase mas dangerous yun.

Lyceum College of Law Representative: Ahhh (inaudible) pag sinabi po natin na Programmatic EIS, nandun na po lahat nan aka… nandun nap o lahat sa plan na yun, yung… kumbaga not only the reclamation but pagka tinayo na po yung mismong project and its environmental impact.

Public Hearing Officer: Ahhh… Carlo, I will explain ano? Kase ang isang Programmatic EIS its ahhh required for coal (inaudible) projects, so ang nagsasabi kunwari reclamation project tapos kunwari meron naman isang reclamation project which is also move by the ano, the proponent. Carlo??

Engr. Arida: In addition lang dun sa sinabi ni Atty., (inaudible) kase ano yung programmatic is a (inaudible) is special option of the (inaudible) is an optional ang nakalagay. Pwede mag apply ang

115 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT proponent kase usually yung usually study based yung programmatic mas ma appreciate mo siya kapag ano eh Industrial Park, ayun dun whereas yung isa din sa Bataan, so programmatic siya. So yun po pinag aaralan natin (inaudible). We have also observed the application (inaudible). So (inaudible).

Public Hearing Officer: So, I think the question ni madam is about sustainability noh? And yung way forward, tama ba?

(inaudible)

Atty Corpus: Back in 2014 or 2015, there was a letter from the CEO of PRA applying for the programmatic clearance for the whole, for the 36, 000 flood reclamation from Cavite to Bataan, and It was (inaudible), so concern about with that move from PRA, that ahhmmm the Senate, that the Senate Committee on Government Corporation conducted an inquiry kase mas dangereous ho yung sinasabi niyo na programmatic dahil ibig sabihin ho yung application pag na yung isang permit lang sa lahat ng 36, 000 hectares of Manila Bay, reclamation project, so that is aaahh unthinkable. Ibig sabihin isa lang ang applyan ng PRA for 36, 000 hectares of reclamation ehhh tapos na tayo lahat regardless of the city. So I do not ano, I do not advise it, it’s very dangerous. Dangerous and tawag dun nakakabahala, very alaraming pag ganun ang ini expose lalo pag coming from DENR.

Public Hearing Officer: Ok po, ahhh.

Dr. Alabastro: Eto po ang nakikita namin sa programmatic, yung project ng PRA for the 36,000 is a Programmatic EIS. Tama po yun, it is a study, hindi po yun application. We can always study so that we can (inaudible) guidelines of the Revised Procedural Manual. However for the purpose of applying for an ECC hindi po naming nakikita na itong 265 hectares ay magiging programmatic unang una simple lang po ang involve. Unang una, creation of land ,ayan po. However during operations, the creation of land the (inaudible). However during operations phase baka pwede, baka, depende po sa proponent ang programmatic. Why? Because during the creation, during operations phase there are certain components merong mall, merong arena, iba iba ang may ari nyan at ang operations phase natitiyak po ako will be completed in maybe at least 20 years, so pwede ganun programmatic. Samantalang itong reclamation maybe completed in 5 years. So depende po iyun, kaya ko po sinagot iyun dahil kami po at our choice sabi nga po ng casehandler, we chose to apply for an EIS documentation.

Public Hearing Officer: Ahhh ok, questions, query, anymore?

(inaudible)

Engr. Lagmay: SIguro po ahhh baka po ang ibig niyong sabihin, kapag kapag… meron po kaseng proseso kapag nag formulate ng CLUP, yung Comprehensive Land Use Plan, so pinormulate po namin ang aming CLUP nuong 2003 meron pong kolatilya sa CLUP namin na bawal ang reclamation naming na bawal ang reclamation for the next ahhhmmmm for the in coming period this is until 2013. However nuon pong 2013 and 2014, nag update po kami ng aming CLUP ng Pasay, nanduon na po ang aming proposal for reclamation projects at isinama po naming ito duon sa sa aming proposal para duon sa aming CLUP na 2014 up to 2022 actually ah supposed to be that would be until 2028 however sinabi ng mga national government agencies na dapat 9 years lang daw so ahhh up to 2022 lang tong aming ano aming CLUP. Duon po sa aming CLUP mam 2014-2022 kasama po duon yung proposal naming for reclamation, bakit po naming isinama? Dahil pagdating po nung time na yun, yun pong aming existing na reclamation project which yun na po yung tinatayuan ng MOA at ng CCP ahhh anon a ho siya halos developed na siya so meron na po kaming way para mag extend dun sa ano naming na reclamation project so kaya lang poi sustain yung another reclamation project, yun pong ahhh proposed na reclamation project naming na yun, yun pong mga impacts niya regarding traffic yung yung effect ng sa population kasama po yun sa kinonsider namin nuong prinoposed po namin yung aming reclamation project. So siguro po duon po sa proseso ng formulation ng CLUP, duon po pumapasok siguro yung mga tanong tungkol sa mga study nay un and yun pong aming CLUP before was approved by HLURB,

116 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT dumaan po siya sa MMDA technical review and as well as na process din po ng technical review yun pong mga national government agencies actually kasama po duon yung DENR, ang DPWH, halos lahat po ng national government agencies na nandun sa Housing and Land Use Regulatory Board. Sila po yung nagbigay sa amin ng approval para duon sa CLUP ng Pasay from 2014 to 2022 po. Dumaan po siya sa matinding review po.

Public Hearing Officer: Ok, maraming salamat po. Questions, concerns, please. K, anyone? Kung wala na pong concerns, ahhh formal na po nating sinasara yung open forum natin. For the recap dun sa mga issues na natalakay natin during this open forum, I’d like to call on Atty. A. Rondaje para dun sa recap namin. Thank you.

Atty. Rondaje: Magandang umaga po sa inyong lahat, aaahhh para po sa recap ng mga diniscuss po natin awhile ago ah yung issue po about dun sa traffic, diniscuss po kanina. Then na discuss po natin yung (inaudible) ng proponen nun sa LGU with regards dun sa alteration of boundary. Ah pinakita din po sa atin ng NAMRIA na wala silang jurisdiction so kung ano po yung mga boundaries but pwede po sila (inaudible) yun lang po ang kanilang jurisdiction and nasa LGU po ang reclamation. Then the other one is regards to the effect of climate change, na discuss din po kanina. And also yung pagtaas ng sea level. And the other one, yung inipen po, yung ni raise ni atty. sa office ni Senator VIllar ah yung about po dun sa lack of source of the filling materials, meron daw memo na nagbabawal na mag extract. Sinagot din po n gating proponent na mag aapply po ng bagong ECC ulit on that matter. And also meron pong suggestions ahhh with regards to the Programmatic EIS study, kung pwede or possible ba. So, sinagot naman po ng ating proponent. Then ahhhmm, meron po nag raise with regards dun sa sharing dun sa or profit na makukuha ng government, 60% mapupunta sa national government and 40% will go to the Local Government Unit. And also na discuss din po kanina yung regarding sa Mandamus Order of Supreme Court, na clarify na din po ng proponent yung abot po duon. Yun lang po.

Engr Arida: Ahhh hello, hello, for the ano yung way forward natin, so this is documented, lahat ng concerns niyo ay i-publish naming sa website naming pero as of the moment may problema ho yung DOST sa mga government sites down po ngayon. Pero eto lang yung kung may concerns pa ho kayo or kung gusto niyo mag submit sa amin ng position paper, naka flash po dyan yung address po namin noh, Environmental Management Bureau, Environmental Impact Management Division tapos yung address po namin tapos you can call us po sa telephone number naming (02) 920-2240 and yung website po namin emb.gov.ph. Ayan po. May email address ho kami noh, yung (pa-type naman).

Eto na yung email address naming ho [email protected]. So, once po na ma submit sa amin yung Public Hearing Documentation, i-popost po namin yung Public Hearing Documentation, ipopost po naming yan sa website naming for 7 working days. So, during that period pwede pa ho kayo mag send ng comments niyo and after that mag schedulepo kami ng review namin. Ayun po.

Woman speaking: Sir sa ano, dun po sa recap, paki ahhh firstly question ko kanina, paki include nalang po yung question ko kanina, ano yung mga proactive active measure ng the project to be able to help the Manila Bay Rehabilation na according to the Supreme Court Madamus. Number two, dun sa suggestion kop o na magkaroon tayo ng Ecosystem Evaluation to be able to determine the values of ecosystem for the shorter and long terms para maipakita natin na kung ano yung global benefit for the people and for nation. Yun lang po.

Atty Corpus: Sir, you mentioned that ano, that the documentation will be submitted to you? Isn’t it the DENR-EMB whose present should be the one doing the documentation? And not just, they could have their own documentation but for purposes po, it should be the DENR who should have to the documentation, personally. So? So who among you will documents?

Engr Arida: Meron din kami mam. Mam, I have here, 2 lawyers and tatlo po kaming handlers. (inaudible), opo.

117 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

PRA: Ahhhmmm, just a short ano po, for the summary of the (inaudible), wala pong memo regarding pinagbabawal yung pagkumuha ng ano from SNS, wala lang palang siyang ECC kaya hindi pa pwede gawin. And PRA is currently applying for the ECC. And it is not the project proponent’s responsibility to get the ECC for the area where they will get their filling materials kase ahhmm the responsibility of the one providing the (inaudible). And additionally po, nakapag bigay na din po kami ng advise na mag consider ng other ahh,, sources of filling materials dahil nga po hindi pa siya nabibigyan ng ECC. Thank you po.

Engr Arida: Ok po. So, for the Closing Remarks, may I call on our Hounourable Mayor.

Hounourable Mayor Calixto: Muli, magandang hapon ho, aaahh (inaudible) invited dito sa Public Hearing, don’t worry ho, i-ko-comply po ng city government lahat ng dapat naming i-comply para po maging (inaudible) pero pupwede ho sana na ang programang ito ay hindi lang ho para sa ating mamamayan ng ating lungsod kundi para Pilipinas para po sa mamayan ng ating Republika. Alam po ninyo yung po mga nakaraan ang Pasay City Government ay 30 million lang ho ang income ng Pasay during Mayor Pablo Cuneta. Naging OIC Mayor ang aking amo, nagging 100 million plus, pero nung mga nakaraang taon, when I was elected as City Mayor nuong 1995, ang income po naming ay 1.2 Biliion pesos after 8 years ang income po ng Lungsod ng Pasay ay umabot nap o sa 6.4 billion pesos+. Ilang libong mga kabataan at mamamayan ang pinakikinabangang ang income ng Lungsod ng Pasay. Lahat ng estudyante ng ating lungsod magmula elementarya, college, elementary ay may benepisyo na Php500 buwan buwan. Saan naming kinikuha ang pera para sa aming mga estudyante? Dyan po sa reclamation. Alam niyo po kung bakit? Kung an gating mga tao ay pagdagdag ng padagdag wala pong magagawng programa ang pamunuan ng Lungsod ng Pasay. Bakit po nasabi ni Mayor Tony Calixto? Kung iisipin po natin that beyond on our call, yun pong mga kalamidad at kung ano ano nangyatari. Pero kaya lamang malakas ang aking loob sa reclamation na ito dahil 40 years na po ang ating reclamation ng Pasay. Wala pong perwisyo, wala din po damage na nagawa para sa ating lungsod at para sa ating mga katabi. Kaya naman ang aapela ako sa inyo, sa aking mga minamahal na kababayan na kung maari ay ating pag aralan ng mabuti bago po tayo gumawa ng kung ano-ano dahil napakalaking programa po hindi lamang po sa ating lungsod ang gagawin natin na reclamation. Ito ay magiging tourist spot at ito ay gagawin natin sa loob ng 10 hangang 15 taon. Hindi ko na po yan maabutan, yun pong mga nakalagay na programa sa reclamation. Ang sinasabi ko po sa inyo, yun pong 6.5 billion ay aabutin po kami ng 20 billion pesos pag natapos po ang reclamation na yan. Kaya inaasahan ko po ang kooperasyon ng bawat isa, hindi lamang po ito sa aming Lungsod ng Pasay kundi para sa ating Pilipino, mga mamayan ng ating bansa. At nakita niyo naman ho ninyo pati po local pati foreign na turista ay nagpupunta po dito sa MOA. Nuon po traffic, concern din po yan, noon pa, yung peace and order concern din po yan pero meron po kaming mga pag aaral. Maraming salamat po sa inyong mga suggestion na binigay sa araw na ito, kung kulang po ay aming dadagdagan at kukumpletuhin an gaming mga requirements upang maituloy na itong reclamation project na ito. Hindi ko na po yan aabutan, last term na po ako ngayon, (inaudible) na ppo ngayong Mayo year 2018 pero gusto ko lang po iwan ito na legacy para sa ating mga kababayan dito sa ating Lungsod ng Pasay. Kaya ako ay nakikiusap sa bawat isa naririto na masusi natin pag aralan kung hindi po talaga pwede ay hindi po natin ito itutuloy, kung pwede naman po naman ay huwag na nating patagalin at tulungan nap o ninyo ang Lungsod ng Pasay dahil ilang lining mga kababayan o mga kabataan ang makikinabang. Ang mga guro, estudyante, mamamayan at hindi lamang ang mga mamamayan ng Pasay kundi ang bawat isang Pilipino. Marami pong salamat at mabuhay po kayong lahat.

People clapping…

Engr Arida: Maraming salamat ho mayor, so pasalamat lang ho ako muli kase dumalo kayo sa Public Hearing namin. So ditto ho nagtatapos ang activity natin. Maraming salamat po.

People clapping…

118 | P a g e

PROPOSED PASAY CITY HARBOR CENTER RECLAMATION PROJECT PUBLIC HEARING REPORT

ANNEX G. VIDEO CLIPPINGS IN CD (Attached in a Separate File)

119 | P a g e