AWARDED SOLAR PROJECTS as of January 31, 2015 POTENTIAL INSTALLED ISLAND / CITY / REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY GRID MUNICIPALITY (MW) (MW) Under Development Stage. On-going negotiations LUZON I Ilocos Norte Currimao Curimao Solar Power Project Mirae Asia Energy Corporation 20.00 for project financing. Request for reconsideration and its submission of Pasuquin East Solar Power Pasuquin, Burgos Energy Logics , Inc. additional requirements for its Declaration of 50.00 Project Commerciality is under evaluation.

Burgos Burgos Solar Power Project Energy Development Corporation Under Development Stage. On-going construction. 4.10 Compliance with Milestone Approach is under Pangasinan Manaoag Pugaro Solar Power Project AVGarcia Power Systems Corp. 2.00 evaluation. GreEnergy Power Systems Request for one-year extension is under II Cagayan Aparri Aparri Solar Power Project 105.00 Philippines, Inc. evaluation. Under Development Stage. On-going Solar Power III Pampanga Mexico RASLAG Corp. construction. Nominated to the FIT System on 30 10.00 Project January 2015. Clark Freeport Zone Solar Enfinity Philippines Renewable Declaration of Commerciality is under evaluation. Power Project Resources Inc. Hermosa Ecozone Industrial Hermosa Sunterra Energy Inc. Request for reconsideration is under evaluation. 10.00 Park Solar Power Project SPARC Solar Powered Agri-Rural On-going completion of pre-development activitie Morong Morong Solar Power Project 5.00 Communities Corporation with one-year extension. Next Generation Power Compliance with Milestone Approach is under Bataan Solar Power Project 20.00 Technology Corp. evaluation. Compliance with Milestone Approach is under Orani Bataan Solar Power Project BWST, Inc. 150.00 evaluation. San Rafael Solar Power SPARC Solar Powered Agri-Rural On-going completion of pre-development activitie San Rafael 5.00 Project Communities Corporation with one-year extension. SPARC Solar Powered Agri-Rural On-going completion of pre-development activitie Palauig Palauig Solar Power Project 5.00 Communities Corporation with one-year extension. Solar Power Cabanatuan City First Cabanatuan Ventures, Inc. Request for reconsideration is under evaluation. Project Compliant with Milestone Approach. On-going pre- Bataan Morong -Hermosa SBFZ Solar Power Project Jobin-Sqm Inc. 100.00 development activities. AWARDED SOLAR PROJECTS as of January 31, 2015 POTENTIAL INSTALLED ISLAND / CITY / REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY GRID MUNICIPALITY (MW) (MW) Concepcion Solar Power Enfinity Philippines Renewable Compliance with Milestone Approach is under LUZON III Concepcion 10.00 Project Resources Inc. evaluation. Rosario and General Cavite Economic Zone Solar Under Development Stage. On-going testing and IV-A Cavite Majestics Energy Corporation 41.30 Trias Power Project commissioning. G.A. PHILKOR MULTI ENERGY Compliance with Milestone Approach is under Naic Sabang Solar Power Project 50.00 CORP. evaluation. Noveleta, Rosario, Enfinity Philippines Renewable Cavite Solar Power Project Declaration of Commerciality is under evaluation. 20.00 Gen. Trias, Tanza Resources Inc. SM City Dasmariñas Solar Solar Philippines Commercial On-going pre-development activities. Requested Dasmariñas 0.80 Power Project Rooftop Projects, Inc. for NCIP endorsement.

Under Development Stage. Entered into ATN Philippines Solar Energy Rizal Rodriguez Macabud Solar Power Project Interconnection Agreement with MERALCO. On- 30.00 Group, Inc. going negotiations for project financing and ROW.

Canlubang Solar Power Transnational Renewable Energy Laguna Calamba Request for reconsideration is under evaluation. 0.206 Project Corporation Solar Philippines Commercial Binan Laguna Solar Power Project Declaration of Commerciality is under evaluation. 0.70 Rooftop Projects, Inc. Asia Brewery Solar Power Solar Philippines Commercial On-going pre-development activities. Requested Cabuyao 16.00 Project Rooftop Projects, Inc. for NCIP endorsement. Solar Philippines Commercial On-going pre-development activities. Requested Batangas Calatagan Batangas Solar Power Project 30.00 Rooftop Projects, Inc. for NCIP endorsement. Compliance with Milestone Approach is under IV-B Palawan Puerto Princesa Palawan Solar Power Project Sabang Renewable Energy Corp. evaluation. Compliance with Milestone Approach is under Phil. Solar Farm-Palawan, Inc. 10.00 evaluation. Compliance with Milestone Approach is under El Nido Island El Nido Solar Power Project SolarPacific Energy Corporation 3.00 evaluation.

Certificate of Confirmation of Commerciality is Solar Philippines Commercial NCR Metro Manila Quezon City SM North Solar Power Project subject to the submission of Quezon City 1.50 Rooftop Projects, Inc. Resolution of Support to the Project.

LUZON Sum 699.61 AWARDED SOLAR PROJECTS as of January 31, 2015 POTENTIAL INSTALLED ISLAND / CITY / REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY GRID MUNICIPALITY (MW) (MW) Under Development Stage. On-going acquisition of Negros VISAYAS VI Cadiz City Cadiz Solar Power Project Phil-Power Solar Energy Corp. relevant permits under Pre-Construction Stage as 100.00 Occidental per Work Plan. San Carlos Solar Power Under Development Stage. On-going mobilization San Carlos City San Carlos Solar Energy Inc. 23.00 Project of major equipment.

Under Development Stage. Phase "A" with 13 MWp and Phase "B" with 9 MWp commissioned 22.00 and started commercial operation on 15 May 2014 and 16 August 2014, respectively.

Pulupandan Solar Power Green Innovation, Exploration and Compliance with Milestone Approach is under Pulupandan Project Resources Inc. evaluation. Valladolid Solar Power Green Innovation, Exploration and Compliance with Milestone Approach is under Valladolid Project Resources Inc. evaluation. La Carlota City Solar Power La Carlota City San Carlos Solar Energy Inc. Declaration of Commerciality is under evaluation. 18.00 Project (SaCaSol II) Compliance with Milestone Approach is under Bago Bago Solar Power Project Energy Development Corporation evaluation. Manapla Solar Power Project Compliance with Milestone Approach is under Manapla and Cadiz San Carlos Solar Energy Inc. 22.00 (SaCaSol III) evaluation.

Bais City Solar Power Project Request for assignment of contract to MONTE Bais City San Carlos Solar Energy Inc. 25.00 (SaCaSol IV) SOLAR ENERGY INC. is under evaluation. Under Development Stage. On-going mobilization Iloilo Miag-ao Miag-ao Solar Power Project Cosmo Solar Energy, Inc. 5.67 of major equipment. Compliance with Milestone Approach is under Iloilo Tigbauan Tigbauan Solar Power Project Solexar Energy International, Inc. 30.00 evaluation. Under Development Stage. On-going VIII Leyte Ormoc Leyte Solar Power Project Phil. Solar Farm-Leyte, Inc. 30.00 construction. Compliance with Milestone Approach is under Leyte Solar Power Project II Phil. Solar Farm-Leyte Inc. 30.00 evaluation. Tacloban, Santa Fe Sulu Electric Power and Light Request for amendment of contract area is under Palo Solar Power Project 50.00 and Palo (Phils.), Inc. evaluation. VISAYAS Sum 333.67 22.00 AWARDED SOLAR PROJECTS as of January 31, 2015 POTENTIAL INSTALLED ISLAND / CITY / REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY GRID MUNICIPALITY (MW) (MW)

Zamboanga La Libertad and Zamboanga del Norte Solar Astronergy Development Dipolog On-going pre-development activities. Requested MINDANAO IX del Norte Dapitan Power Project Inc. for NCIP endorsement.

Misamis X Villanueva Kirahon Solar Power Project Kirahon Solar Energy Corporation Declaration of Commerciality is under evaluation. 20.00 Oriental

Bukidnon Kibawe Kibawe Solar Power Project Asian Greenenergy Corp. Declaration of Commerciality is under evaluation. 12.00

Compliance with Milestone Approach is under Sumilao Bukidnon Solar Power Project SunAsia Energy Inc. 2.00 evaluation.

Misamis Laguindingan Solar Power Cagayan Electric Power & Light Compliance with Milestone Approach is under Laguindingan 20.00 Oriental Project Company, Inc. evaluation. On-going pre-development activities. Requested Misamis Oriental Solar Power The Ark Green Dynamic Resources Claveria for NCIP endorsement and posted Performance 60.00 Project Corp. Bond. Misamis Oriental Solar Power Astronergy Development On-going pre-development activities. Requested Balingasag Project Mindanao, Inc. for NCIP endorsement. Completed 2-Year Pre-development Stage. XI Davao del Sur Sta. Cruz Darong Solar Power Project PhilNewEnergy, Inc. Awaiting for the submission of compliant 35.00 Declaration of Commerciality. Under Development Stage. Certificate of Enfinity Philippines Renewable Digos Digos Solar Power Project Confirmation of Commerciality is subject to the 10.00 Resources Inc. Amendment of Contract Area.

Davao Davao Oriental Solar Power Enfinity Philippines Renewable Compliance with Milestone Approach is under Mati 10.00 Oriental Project Resources Inc. evaluation. Under Development Stage. On-going acquisition South nv vogt Philippines Solar Energy XII Surallah Centrala Solar Power Project of relevant permits under Pre-Construction Stage 6.25 Cotabato One, Inc. as per Work Plan. General Santos City 1 Solar Enfinity Philippines Renewable Compliance with Milestone Approach is under General Santos City 10.00 Power Project Resources Inc. evaluation. AWARDED SOLAR PROJECTS as of January 31, 2015 POTENTIAL INSTALLED ISLAND / CITY / REGION PROVINCE PROJECT NAME COMPANY NAME STATUS CAPACITY CAPACITY GRID MUNICIPALITY (MW) (MW) South South Cotabato Solar Power Astronergy Development GenSan On-going pre-development activities. Requested MINDANAO XII General Santos City Cotabato Project Inc. for NCIP endorsement.

General Santos City 3 Solar Enfinity Philippines Renewable Compliance with Milestone Approach is under Polomolok 10.00 Power Project Resources Inc. evaluation.

Compliance with Milestone Approach is under Sarangani Alabel Alabel Solar Power Project SolarPacific Energy Corporation 15.00 evaluation.

Agusan del Butuan City 1 Solar Power Enfinity Philippines Renewable Compliance with Milestone Approach is under XIII Butuan City 10.00 Norte Project Resources Inc. evaluation.

Butuan City 3 Solar Power Enfinity Philippines Renewable Compliance with Milestone Approach is under 10.00 Project Resources Inc. evaluation.

Tagoloan II, Local Government Unit of the Compliance with Milestone Approach is under ARMM Lanao del Sur Saguiaran & Marawi ICOM Solar Power Project 35.00 Islamic City of Marawi evaluation. City

MINDANAO Sum 265.25

Grand Total 1,298.53 22.00