ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

SERVING BUTLER, CLERMONT, CLINTON, GREENE, HAMILTON, PREBLE AND WARREN COUNTIES

MIKE DEWINE, GOVERNOR | JACK MARCHBANKS, PH.D., ODOT DIRECTOR | TAMMY CAMPBELL, P.E., DISTRICT DEPUTY DIRECTOR ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

2021 CONSTRUCTION PROGRAM

hio’s highways are essential to keeping and creating new jobs. With a mission to provide easy movement of people and goods from place to place, the Ohio Department of Transportation (ODOT) is responsible for maintaining one of the largest transportation networks in the nation. Guided by ethical principles and accountability, ODOT works to improve safety, enhance travel and advance economic development. O The following summary outlines those projects which are currently under construction or programmed for the 2021 construction season in ODOT District 8. With an estimated funding commitment of more than $760 million in construction costs, District 8’s construction program will consist of approximately 95 new and ongoing preservation, maintenance and safety improvement projects to be sold and/or constructed through FY2021 and the first quarter of FY2022.

Due to production and planning variables, however, not all projects may be sold as proposed, and projects are subject to funding availability. Any cost estimates, sale dates or schedules cited in this document are subject to change, and estimated costs are the construction cost estimates established by District 8’s Planning & Design staff prior to bid letting; these do not include any preliminary engineering or right of way acquisition costs as applicable to the project. Projects listed as Local-Let are those which are being administered by the Department of Transportation; additional information about these and other local projects can be obtained from the respective sponsoring agency.

Additional information about these projects will be released as they are scheduled or awarded. For more information, please contact District 8’s Public Information Office by phone at 513-933-6517 or 513-933-6534 or via email to [email protected]. You may also visit ODOT online at www.transportation.ohio.gov, and follow District 8 on Facebook, Twitter, Instagram and NextDoor.

PID = Project Identification Number CRS = County, Route, Section

On the cover: An aerial view of the I-74/I-75 Expressway Project in Hamilton County.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

2021 CONSTRUCTION HIGHLIGHTS MAJOR INTERSTATE CONSTRUCTION PROJECTS

I-70 - PREBLE COUNTY PROJECT DESCRIPTION: Pavement repair, bridge rehabilitations and resurfacing of I-70 from the Indiana State line to the Montgomery County line. Construction will also include paving work in both the rest area and the weigh station.

OVERALL SCHEDULE: Summer 2020 – Summer 2022 CONSTRUCTION COST: $28.2 million

I-71 - HAMILTON COUNTY PROJECT DESCRIPTION: Repaving of approximately 5.5 miles on I-71 and bridge deck replacement of Stewart Road bridge and rehab of other bridges from north of S.R. 562/Norwood Lateral to S.R. 126/Ronald Reagan Cross County Highway. Also includes widening to three continuous through lanes between the Norwood Lateral interchange and Red Bank Expressway, removing the northbound Ridge Road exit and adding a NB I-71 exit to Kennedy Avenue.

OVERALL SCHEDULE: Spring 2018 – Summer 2021 CONSTRUCTION COST: $36 million

I-75/ – HAMILTON COUNTY PROJECT DESCRIPTION: Widening I-75 to four lanes between Monmouth Street and Clifton Avenue, connecting the improvements from Hopple and Mitchell projects. Additional improvements to the connection of eastbound I-74 to I-75.

OVERALL SCHEDULE: Fall 2018 – Fall 2022 CONSTRUCTION COST: $87 million

I-675 – GREENE COUNTY PROJECT DESCRIPTION: Pavement repair and resurfacing on I-675, from the Montgomery County line to near North Fairfield Road. Project also includes bridge overlays, approach slabs and joint repairs on the mainline and overhead bridges.

OVERALL SCHEDULE: Spring 2020 – Summer 2022 CONSTRUCTION COST: $26.1 million

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

2021 CONSTRUCTION HIGHLIGHTS MAJOR INTERSTATE CONSTRUCTION PROJECTS

I-75/THRU THE VALLEY – HAMILTON COUNTY PROJECT DESCRIPTION: Phase 8 of this multi-phase project on I-75 North and South between the Glendale Milford Road interchange and Kemper Road overpass. Project includes widening for a fourth lane on in both directions and auxiliary lanes from Sharon Road to Glendale Milford Road and from Sharon Road to I-275. Work includes improving the capacity at the Sharon Road interchange and the intersection of E. Sharon Road/Chester Road.

OVERALL SCHEDULE: Summer 2021 – Spring 2025 CONSTRUCTION COST: $45.7 million

I-74/MILL CREEK EXPRESSWAY – HAMILTON COUNTY PROJECT DESCRIPTION: Phase 5B of the I-75/Mill Creek Expressway project, addressing work on I-74 as part of the I-74/75 interchange reconstruction. Construction will also improve the ramps from I-75 to I-74 West. Although this project will sell in the Spring of 2021, construction is not anticipated to begin until construction for Phase 5A of the MCE has been completed.

OVERALL SCHEDULE: Spring 2022 – Summer 2025 CONSTRUCTION COST: $93 million

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

2021 CONSTRUCTION HIGHLIGHTS

OTHER NOTABLE PROJECTS

INTERSECTION SAFETY IMPROVEMENTS

BUTLER-73: A safety improvement project to construct a roundabout at the intersection of S.R. 73 and C.R. 24 (Jacksonburg Road), just west of Trenton. Construction is under way, and the project will be completed in the summer of 2021. Estimated cost: $3 million.

BUTLER-127: A safety improvement project to construct a roundabout at the intersection of U.S. 127 and S.R. 73, just west of the community of Seven Mile. Construction will kick off in the spring of 2021, and the project will be completed in 2022. Estimated cost: $2.7 million.

CLERMONT-32: Construction of a signalized Restricted Crossing U-Turn (RCUT) on S.R. 32 at the Bauer Road intersection near Batavia. The project will include building signalized median crossovers to the east and west of Bauer Road and provide for left turn and through traffic movements by way of legal U-turn movements, thereby eliminating the at-grade crossing. Construction is anticipated to begin in the summer of 2021, and the project is scheduled for completion in late fall of 2021. Estimated cost: $6 million.

GREENE-35: Construction of a signalized superstreet on U.S. 35 between Orchard Lane and Factory Road in Beavercreek. In addition to roadway and bridge improvements, the project will include building signalized intersections at both locations to provide for legal U-turn movements and eliminate the at-grade crossing intersections, similar to that of an RCUT. Construction is under way, and the project is scheduled for completion in 2022. Estimated cost: $14.9 million.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

BUTLER COUNTY Carry-Over Projects

BUT-75-5.35

PID: 100801 CONSTRUCTION COST: $2.37 million SCHEDULE: Summer 2020 – Summer 2021

PROJECT DESCRIPTION: A bridge rehabilitation and deck replacement project on the C.R. 20 (Tylersville Road) structure over I-75.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic in each direction will be maintained on C.R. 20 during Phase 1 construction; however, the route will be closed during Phase 2. I-75 traffic will be maintained throughout the project, with intermittent lane restrictions as needed.

BUT-73-13.05

PID: 102059 CONSTRUCTION COST: $2.93 million SCHEDULE: Summer 2020 – Summer 2021

PROJECT DESCRIPTION: Construction of a roundabout at the intersection of S.R. 73 and C.R. 24 (Jacksonburg Road).

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on S.R. 73; C.R. 24 will be subject to temporary closure during some phases of construction.

BUT-747-1.01/2.01

PID: 110213 CONSTRUCTION COST: $375,000 SCHEDULE: Summer 2020 – Summer 2021

PROJECT DESCRIPTION: A signal rebuild and upgrade project at the intersection of S.R. 747 and C.R. 115 (Muhlhauser Road) and at the S.R. 747 and C.R. 116 (Port Union Road) intersection.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on all affected routes.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

BUTLER COUNTY Carry-Over Projects

Districtwide-Various

PID: 94224 CONSTRUCTION COST: $2.34 million SCHEDULE: Summer 2020 – Summer 2021

PROJECT DESCRIPTION: Districtwide bridge maintenance project on structures located on S.R. 126 in Butler County; S.R. 131, S.R. 132 and S.R. 32 in Clermont County; U.S. 35 in Greene County; I-75, I-275, U.S. 50, S.R. 126 and S.R. 562 in Hamilton County; and I-75 in Warren County.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on all affected routes.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

BUTLER COUNTY New Projects

BUT-75-5.52

PID: 100632 CONSTRUCTION COST: $1.09 million SCHEDULE: Spring – Fall 2021

PROJECT DESCRIPTION: A microsurfacing project between the Tylersville Road and S.R. 129 interchanges.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in either direction.

BUT-75-0.00

PID: 102568 CONSTRUCTION COST: $8.04 million SCHEDULE: Spring – Fall 2021

PROJECT DESCRIPTION: A pavement repair and resurfacing project between the Hamilton County line and the Tylersville Road interchange.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in either direction.

BUT-127-16.56

PID: 110466 CONSTRUCTION COST: $2.69 million SCHEDULE: Summer 2021 – Spring 2022

PROJECT DESCRIPTION: Construction of a roundabout at the intersection of U.S. 127 and S.R. 73.

MAINTENANCE OF TRAFFIC: Traffic will be maintained on U.S. 127 throughout construction; S.R. 73 will be subject to intermittent periods of closure.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

BUTLER COUNTY New Projects

BUT-129-0.00

PID: 105105 CONSTRUCTION COST: $2.31 million SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Resurfacing project between S.R. 126 and U.S. 27.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in a minimum of one lane in either direction.

BUT-122D-0.59

PID: 100832 CONSTRUCTION COST: $622,006 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Bridge rehabilitation project on eastbound S.R. 122 over University Boulevard in Middletown.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in a minimum of one lane in either direction.

BUT-122-10.33

PID: 110459 CONSTRUCTION COST: $875,896 SCHEDULE: Spring – Fall 2021

PROJECT DESCRIPTION: Intersection improvement project at the intersection of S.R. 122 and Breiel Boulevard, realigning the southbound left turn and providing an eastbound right-turn lane. A new traffic signal will be constructed, and signal timing will be revised.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in a minimum of one lane in either direction.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

BUTLER COUNTY New Projects

BUT-73-22.55

PID: 107126 CONSTRUCTION COST: $2.08 million SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Paving project in the city of Middletown, between Germantown Road and the northern corporation limit.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in a minimum of one lane in either direction.

BUT-73-18.08

PID: 110467 CONSTRUCTION COST: $258,500 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Implement access management by closing driveways and restricting driveway movements along S.R. 73 and Main Street in South Middletown.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in a minimum of one lane in either direction.

BUT-4-15.80

PID: 102736 CONSTRUCTION COST: $2.82 million SCHEDULE: Spring – Fall 2021

PROJECT DESCRIPTION: Bridge rehabilitation on the structures that carry S.R. 4 over S.R. 63.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in a minimum of one lane in either direction.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

BUTLER COUNTY New Projects

BUT-4-10.83

PID: 110423 CONSTRUCTION COST: $1.97 million SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Intersection widening at the northern intersection of S.R. 4 and S.R. 4 Bypass, located northeast of the city of Hamilton.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in a minimum of one lane in either direction.

BUT-4-13.90

PID: 110458 CONSTRUCTION COST: $789,250 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Intersection improvement project at S.R. 4 and S.R. 747 by constructing a northbound right-turn lane on S.R. 747 and removing the existing slip lane from northbound S.R. 747 to S.R. 4 and rebuilding the existing signal.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in a minimum of one lane in either direction.

Districtwide - Various Locations

PID: 111482 CONSTRUCTION COST: $455,675 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: A guardrail repair/replacement project at multiple locations in District 8, including on S.R. 4 and S.R. 122 in Butler County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

BUTLER COUNTY New Projects

Districtwide - Various Locations

PID: 100835 CONSTRUCTION COST: $2.84 million SCHEDULE: Summer 2021 – Summer 2022

PROJECT DESCRIPTION: Bridge maintenance project at multiple locations in District 8, including on S.R. 747, between Union Centre Boulevard and Smith Road.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

Districtwide - Various Locations

PID: 101025 CONSTRUCTION COST: $2.11 million SCHEDULE: Summer 2021 – Summer 2023

PROJECT DESCRIPTION: Signalization project at multiple locations in District 8, including S.R. 4, S.R. 63, S.R. 73, S.R. 126, S.R. 128, S.R. 129, S.R. 732, S.R. 747 and U.S. 27, U.S. 42 and U.S. 127 in Butler County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

CLERMONT COUNTY Carry-Over Projects

Districtwide-Various

PID: 94224 CONSTRUCTION COST: $2.34 million SCHEDULE: Summer 2020 – Summer 2021

PROJECT DESCRIPTION: Districtwide bridge maintenance project on structures located on S.R. 126 in Butler County; S.R. 131, S.R. 132 and S.R. 32 in Clermont County; U.S. 35 in Greene County; I-75, I-275, U.S. 50, S.R. 126 and S.R. 562 in Hamilton County; and I-75 in Warren County.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on all affected routes.

CLE-28-1.84

PID: 100809 CONSTRUCTION COST: $1.87 million SCHEDULE: Summer 2020 – Summer 2021

PROJECT DESCRIPTION: Bridge replacement project on S.R. 28 over T.R. 241 (Happy Hollow Road).

MAINTENANCE OF TRAFFIC: S.R. 28 traffic will be maintained except for various nightly closures during bridge beam removal and beam erection. T.R. 241 will be reduced to one lane, and traffic will be maintained with temporary signals.

HAM/CLE-275-10.57/32.21/10.36

PID: 112284 CONSTRUCTION COST: $4.36 million SCHEDULE: Summer 2020 – Summer 2021

PROJECT DESCRIPTION: The installation of single mode fiber optic cable at three locations along I-275 in Hamilton and Clermont Counties. The project limits extend from the I-74 interchange to the U.S. 27 interchange; from the U.S. 22 (Montgomery Road) to the S.R. 28 interchange; and from S.R. 32 to the U.S. 52 interchange.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained throughout construction.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

CLERMONT COUNTY New Projects

CLE-275-0.00

PID: 105674 CONSTRUCTION COST: $9.55 million SCHEDULE: Spring – Fall 2021

PROJECT DESCRIPTION: Resurfacing project between the Hamilton County line, west of the Wards Corner Road interchange, and the S.R. 450 interchange.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in a minimum of one or two lanes in either direction.

CLE-275-7.71

PID: 110554 CONSTRUCTION COST: $839,221 SCHEDULE: Spring – Summer 2021

PROJECT DESCRIPTION: Bridge (culvert) repair and erosion control project over Hall Run, east of the Round Bottom Road underpass.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in a minimum of one or two lanes in either direction.

CLE-275/32-10.57/1.35

PID: 113912 CONSTRUCTION COST: $333,133 SCHEDULE: Spring 2021

PROJECT DESCRIPTION: Bridge approach repair project on the ramp (Exit 63B) from I-275 South to S.R. 32 East.

MAINTENANCE OF TRAFFIC: The ramp will be closed for up to 60 days in the Spring, and traffic will be detoured via Exit 63A. At all other times, traffic will be maintained.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

CLERMONT COUNTY New Projects

CLE-32-8.95

PID: 110422 CONSTRUCTION COST: $5.08 million SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Construction of a Restricted Crossing U-Turn (RCUT) at the Bauer Road intersection.

MAINTENANCE OF TRAFFIC: S.R. 32 traffic will be maintained except for various nightly lane closures; Bauer Road may also be subject to intermittent periods of closure at the intersection.

CLE-50-7.80

PID: 113066 CONSTRUCTION COST: $847,000 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Pavement overlay project between S.R. 222 and McKay Road.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in one lane with the use of flaggers.

CLE-131-2.09

PID: 110469 CONSTRUCTION COST: $275,000 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Intersection improvement project at the intersection Wolfpen Pleasant Hill Road, upgrading the eastbound signalization to a protected-only left-turn movement and providing ADA pedestrian crossings.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in one lane with the use of flaggers.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

CLERMONT COUNTY New Projects

CLE-131-11.98

PID: 109671 CONSTRUCTION COST: $517,290 SCHEDULE: Spring – Summer 2021

PROJECT DESCRIPTION: Resurfacing project between S.R. 133 and the Brown County line.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in one lane with the use of flaggers.

CLE-756-0.00

PID: 100563 CONSTRUCTION COST: $3.93 million SCHEDULE: Summer 2021 – Summer 2022

PROJECT DESCRIPTION: Resurfacing project between S.R. 232 and the Brown County line. Construction also includes replacing three culverts within the project limits.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in one lane with the use of flaggers. The route may also be subject to intermittent periods of closure, and traffic will be detoured by way of S.R. 743 and S.R. 222.

CLE-Bike Trail

PID: 110576 CONSTRUCTION COST: $1.87 million SCHEDULE: Summer 2020 – Summer 2021

PROJECT DESCRIPTION: Culvert replacement project along the bike path under I-275, near the Hamilton County line.

MAINTENANCE OF TRAFFIC: There will be no impact to roadway traffic.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

CLERMONT COUNTY New Projects

CLE/WAR-Various Locations

PID: 105106 CONSTRUCTION COST: $1.27 million SCHEDULE: Spring – Summer 2021

PROJECT DESCRIPTION: Pavement overlay on various routes, including S.R. 133, between S.R. 131 and the Warren County line, and S.R. 727, between Shiloh Road and S.R. 133, in Clermont County.

MAINTENANCE OF TRAFFIC: Traffic on affected routes will be maintained in one lane with the use of flaggers.

CLE/WAR-Various Locations

PID: 105393 CONSTRUCTION COST: $388,193 SCHEDULE: Spring – Fall 2021

PROJECT DESCRIPTION: Culvert replacement and rehabilitation project at various locations, including S.R. 125 and S.R. 232 in Clermont County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained with flaggers and/or temporary signals as needed, and affected routes may be subject to periods of closure.

Districtwide-Various

PID: 111482 CONSTRUCTION COST: $455,675 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: A guardrail repair/replacement project at multiple locations in District 8, including U.S. 52 and S.R. 125 in Clermont County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

CLERMONT COUNTY New Projects

Districtwide-Various

PID: 101025 CONSTRUCTION COST: $2.11 million SCHEDULE: Summer 2021 – Summer 2023

PROJECT DESCRIPTION: Signalization project at multiple locations in District 8, including I-275, U.S. 52, S.R. 28, S.R. 32, S.R. 125, and S.R. 131 in Clermont County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

CLINTON COUNTY New Projects CLI-71-12.13/13.99

PID: 105225 CONSTRUCTION COST: $7.27 million SCHEDULE: Fall 2021 – Summer 2022

PROJECT DESCRIPTION: Bridge rehabilitation project at two locations between the U.S. 68 interchange and the Greene County line.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in either direction at all times.

CLI-22-11.75

PID: 110996 CONSTRUCTION COST: $7.56 million SCHEDULE: Summer 2021 – Spring 2022

PROJECT DESCRIPTION: An urban paving project in the city of Wilmington, from the junction with Rombach Avenue to the east corporation limit near S.R. 73. Construction includes installation of a concrete median, shared-use path and sidewalk, and signalization.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in each direction.

CLI-68-14.97

PID: 111841 CONSTRUCTION COST: $795,151 SCHEDULE: Fall 2021 – Fall 2022

PROJECT DESCRIPTION: A signalization project at the intersections of South Street and Main and Locust streets that will include signal timing and coordination, converting the intersection of South and Sugartree streets to two-way stop controlled, and adding curb bump-outs, pavement markings and pedestrian upgrades.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

CLINTON COUNTY New Projects

Districtwide-Various

PID: 101025 CONSTRUCTION COST: $2.11 million SCHEDULE: Summer 2021 – Summer 2023

PROJECT DESCRIPTION: Signalization project at multiple locations in District 8, including I-71, U.S. 22, U.S. 68, S.R. 72 and S.R. 73 in Clinton County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

GREENE COUNTY Carry-Over Projects

GRE-675-0.00

PID: 94254 CONSTRUCTION COST: $26.1 million SCHEDULE: Spring 2020 – Summer 2022

PROJECT DESCRIPTION: Pavement repair and resurfacing on I-675, from the Montgomery County line to near North Fairfield Road. Project also includes bridge overlays, approach slabs and joint repairs on the mainline and overhead bridges.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in each direction.

GRE-42-3.15

PID: 108640 CONSTRUCTION COST: $1.80 million SCHEDULE: Spring 2020 – Fall 2020

PROJECT DESCRIPTION: The installation of a Restricted Crossing U-Turn (RCUT) at the intersection of U.S. 42 and C.R. 75 (Spring Valley-Paintersville Road).

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in either direction on U.S. 42.

GRE-35-4.30

PID: 102421 CONSTRUCTION COST: $14.9 million SCHEDULE: Summer 2019 – Summer 2022

PROJECT DESCRIPTION: Construction of a superstreet on U.S. 35 between Orchard Lane and Factory Road. In addition to roadway and bridge improvements, the project will include building signalized intersections at both locations to provide for legal U-turn movements and eliminate the at-grade crossing intersections.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in each direction on U.S. 35; arterial roadways will be subject to lane restrictions and temporary closures.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

GREENE COUNTY Carry-Over Projects

Districtwide-Various

PID: 94224 CONSTRUCTION COST: $2.34 million SCHEDULE: Summer 2020 – Summer 2021

PROJECT DESCRIPTION: Districtwide bridge maintenance project on structures located on S.R. 126 in Butler County; S.R. 131, S.R. 132 and S.R. 32 in Clermont County; U.S. 35 in Greene County; I-75, I-275, U.S. 50, S.R. 126 and S.R. 562 in Hamilton County; and I-75 in Warren County.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on all affected routes.

Districtwide-Various

PID: 109571 CONSTRUCTION COST: $2.39 million SCHEDULE: Summer 2020 – Spring 2021

PROJECT DESCRIPTION: An interchange lighting installation project at locations on I-71/S.R. 741 and I-71/Wilmington Road interchanges in Warren County; I- 275/S.R. 126 interchange in Hamilton County; and U.S. 35/S.R. 835 interchange in Greene County.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on all affected routes.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

GREENE COUNTY New Projects

GRE-235-10.75/11.10

PID: 100826 CONSTRUCTION COST: $3.83 million SCHEDULE: Spring 2021 – Summer 2022

PROJECT DESCRIPTION: A bridge rehabilitation/replacement project over Mud Run and Mad River, just east of the Montgomery County line.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained with the use of temporary signals.

GRE-444-0.00

PID: 113067 CONSTRUCTION COST: $330,000 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: A pavement repair project between the Montgomery County line and Kauffman Avenue at the city of Fairborn.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in either direction.

GRE-68-9.57/13.35

PID: 98510 CONSTRUCTION COST: $987,800 SCHEDULE: Spring – Fall 2021

PROJECT DESCRIPTION: A bridge rehabilitation project at two locations: near the Leaman Street intersection in Xenia and over Massie’s Creek, just south of S.R. 235.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained at both locations.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

GREENE COUNTY New Projects

GRE-Various Locations

PID: 100909 CONSTRUCTION COST: $244,434 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: A culvert rehabilitation project at various locations in Greene County, including I-675, U.S. 35 and S.R. 380.

MAINTENANCE OF TRAFFIC: Traffic will be maintained on all affected routes, and traffic impacts should be minimal.

GRE-Various Locations

PID: 100696 CONSTRUCTION COST: $432,879 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Pavement maintenance (crack sealing) at various locations on U.S. 42, U.S. 68, S.R. 235, S.R. 725 and S.R. 734.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on all affected routes with the use of flaggers as needed.

Districtwide-Various

PID: 101025 CONSTRUCTION COST: $2.11 million SCHEDULE: Summer 2021 – Summer 2023

PROJECT DESCRIPTION: Signalization project at multiple locations in District 8, including I-675, U.S. 35, U.S. 42, U.S. 68, S.R. 235 and S.R. 725 in Greene County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

GREENE COUNTY New Projects

Districtwide - Various Locations

PID: 111482 CONSTRUCTION COST: $455,675 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: A guardrail repair/replacement project at multiple locations in District 8, including on U.S. 42, S.R. 72, C.R. 9, C.R. 95 and T.R. 10 in Greene County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

Districtwide - Various Locations

PID: 100835 CONSTRUCTION COST: $2.84 million SCHEDULE: Summer 2021 – Summer 2022

PROJECT DESCRIPTION: Bridge maintenance project at multiple locations in District 8, including on U.S. 42, between Centerville Road and S.R. 725.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY Carry-Over Projects

HAM-71-8.42

PID: 91826 CONSTRUCTION COST: $36 million SCHEDULE: Summer 2018 – Summer 2021

PROJECT DESCRIPTION: Resurfacing and bridge deck replacement of Stewart Road bridge and rehab of other bridges from the railroad bridge north of S.R. 562/Norwood Lateral to S.R. 126/Ronald Reagan Cross County Highway. Also includes widening to three continuous through lanes between the S.R. 562/Norwood Lateral interchange and Red Bank Expressway, removing the northbound Ridge Road exit and adding a northbound I-71 exit to Kennedy Avenue.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in each direction throughout the duration of the project.

HAM-71-9.92/10.75

PID: 99777 CONSTRUCTION COST: $1.19 million SCHEDULE: Summer 2020 – Spring 2021

PROJECT DESCRIPTION: A drainage system maintenance project to stabilize the stream along northbound I-71 beginning at the Red Bank Road interchange and improve drainage at the northbound exit ramp to Stewart Road.

MAINTENANCE OF TRAFFIC: Traffic will be maintained throughout the project.

HAM-75-12.60

PID: 82288 CONSTRUCTION COST: $96 million SCHEDULE: Summer 2017 – Spring 2021

PROJECT DESCRIPTION: Phases 1 and 2 of the I-75/Thru the Valley project to reconstruct the interstate between Shepherd Lane and Glendale-Milford Road.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in each direction throughout the duration of the project.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY Carry-Over Projects

HAM-75-3.84

PID: 104667 CONSTRUCTION COST: $87 million SCHEDULE: Fall 2018 – Summer 2022

PROJECT DESCRIPTION: Phase 5A of the I-75/Mill Creek Expressway project to widen I-75 to four lanes between Monmouth Street and Clifton Avenue, connecting the improvements from Hopple and Mitchell projects and completing additional improvements to the connection of eastbound I-74 to I-75.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in each direction through the remainder of construction.

HAM/CLE-275-10.57/32.21/10.36

PID: 112284 CONSTRUCTION COST: $4.36 million SCHEDULE: Summer 2020 – Summer 2021

PROJECT DESCRIPTION: The installation of single mode fiber optic cable at three locations along I-275 in Hamilton and Clermont Counties. The project limits extend from the I-74 interchange to the U.S. 27 interchange; from U.S. 22 (Montgomery Road) to the S.R. 28 interchange; and from S.R. 32 to the U.S. 52 interchange.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in either direction. HAM-125-3.78

PID: 24948 CONSTRUCTION COST: $171,246 SCHEDULE: Fall 2020 – Summer 2021

PROJECT DESCRIPTION: A bridge rehabilitation project over Clough Creek, immediately west of Berkshire Lane.

MAINTENANCE OF TRAFFIC: Traffic on S.R. 125 will be maintained in a minimum of one lane in either direction. Berkshire Lane will be maintained by flaggers as needed during hours of operation.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY Carry-Over Projects HAM-CR251-0.64

PID: 98769 CONSTRUCTION COST: $4 million SCHEDULE: Fall 2019 – Summer 2021

PROJECT DESCRIPTION: A pavement rehabilitation project that includes storm sewer improvements, on-street parking reconfiguration, lighting, sidewalks, bus shelters and signal improvements on C.R. 251 (Blue Ash Road), from Duneden Avenue to Galbraith Road in the village of Deer Park.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in each direction.

HAM-CR266-9.19

PID: 111503 CONSTRUCTION COST: $140,938 SCHEDULE: Fall 2020 – Spring 2021

PROJECT DESCRIPTION: A traffic control maintenance project to transfer fiber optic interconnection and power services from the current location to new poles along Kemper Road, between Tri-County Parkway and Century Boulevard.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in each direction.

HAM-Mt. Healthy

PID: 107296 CONSTRUCTION COST: $621,500 SCHEDULE: Summer 2020 – Summer 2021

PROJECT DESCRIPTION: A signalization project in the city of Mt. Healthy, upgrading the existing system at 14 signalized intersections on Hamilton Avenue (U.S. 127), between S.R. 126 and Adams Road, and on Compton Road (C.R. 217).

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on all affected routes.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY Carry-Over Projects

HAM-Dana Avenue

PID: 111536 CONSTRUCTION COST: $110,000 SCHEDULE: Fall 2020 – Spring 2021

PROJECT DESCRIPTION: A drainage improvement project to replace storm sewer lines at the Dana Avenue interchange ramp at I-71.

MAINTENANCE OF TRAFFIC: Traffic will be maintained on all affected routes.

Districtwide-Various

PID: 109571 CONSTRUCTION COST: $2.39 million SCHEDULE: Summer 2020 – Spring 2021

PROJECT DESCRIPTION: An interchange lighting installation project at locations on I-71/S.R. 741 and I-71/Wilmington Road interchanges in Warren County; I- 275/S.R. 126 interchange in Hamilton County; and U.S. 35/S.R. 835 interchange in Greene County.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on all affected routes.

Districtwide-Various

PID: 94224 CONSTRUCTION COST: $2.34 million SCHEDULE: Summer 2020 – Summer 2021

PROJECT DESCRIPTION: Districtwide bridge maintenance project on structures located on S.R. 126 in Butler County; S.R. 131, S.R. 132 and S.R. 32 in Clermont County; U.S. 35 in Greene County; and I-75, I-275, U.S. 50, S.R. 126 and S.R. 562 in Hamilton County.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on all affected routes.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY New Projects

HAM-71-1.34

PID: 110259 CONSTRUCTION COST: $424,935 SCHEDULE: Spring – Fall 2021

PROJECT DESCRIPTION: Repair stone masonry veneer façade in the spandrels over and the pilasters on either side of the portals for Lytle Tunnel. In addition, construction will include replacing the concrete wall cap on the south portal mainline tunnel with new reinforced concrete.

MAINTENANCE OF TRAFFIC: Traffic will be maintained on I-71, with intermittent periods of restriction at the project site.

HAM/WAR-71-19.83/0.00

PID: 104844 CONSTRUCTION COST: $5.10 million SCHEDULE: Fall 2021 – Summer 2023

PROJECT DESCRIPTION: Construction of an on-ramp from southbound Mason-Montgomery Road to southbound I-71.

MAINTENANCE OF TRAFFIC: Traffic will be maintained on I-71, with intermittent periods of restriction at the project site.

HAM-74-17.80

PID: 113476 CONSTRUCTION COST: $4.14 million SCHEDULE: Winter – Summer 2021

PROJECT DESCRIPTION: Emergency slide repair to stabilize the hillside along the ramp from Colerain-Beekman Avenue to westbound I-74. Project will also include pavement repairs.

MAINTENANCE OF TRAFFIC: Traffic will be maintained, but intermittent periods of short-term overnight closures may be in effect on the ramp.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY New Projects

HAM-74-18.01

PID: 104668 CONSTRUCTION COST: $92.3 million SCHEDULE: Fall 2021 – Summer 2025 (Start of construction will likely be contingent upon completion of Phase 5A of the MCE project that is currently under way.)

PROJECT DESCRIPTION: Phase 5B of the Mill Creek Expressway project. Construction includes reconstructing the I-75 South connection to I-74 West, adding a thru lane on westbound I-74 and rehabilitating bridges within the project limits.

MAINTENANCE OF TRAFFIC: Traffic will be maintained throughout the duration of the project.

HAM-75-10.10

PID: 76256 CONSTRUCTION COST: $45.7 million SCHEDULE: Fall 2021 – Spring 2025

PROJECT DESCRIPTION: Phase 8 of the Thru the Valley project. Construction includes widening to add a fourth lane on I-75 North and South between the Glendale Milford Road interchange and Kemper overpass.

MAINTENANCE OF TRAFFIC: Traffic will be maintained throughout the duration of the project.

HAM-75-14.60

PID: 114299 CONSTRUCTION COST: $89,000 SCHEDULE: Spring 2021

PROJECT DESCRIPTION: Tree clearing project in advance of the start of construction for I-75/Thru the Valley Phase 8.

MAINTENANCE OF TRAFFIC: Traffic on the mainline I-75 will be maintained throughout the duration of the project.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY New Projects

HAM-275-4.06

PID: 110175 CONSTRUCTION COST: $662,110 SCHEDULE: Spring – Fall 2021

PROJECT DESCRIPTION: Landslide remediation project on I-275 West near the Kilby Road interchange.

MAINTENANCE OF TRAFFIC: Traffic will be maintained on the mainline throughout the duration of the project; intermittent periods of overnight closures and restrictions on the ramps may be imparted.

HAM-275-21.65

PID: 110004 CONSTRUCTION COST: $2.3 million SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Pavement repair and paving project between the Winton Road interchange/Forest Park and I-75 interchange near Springdale.

MAINTENANCE OF TRAFFIC: Traffic will be maintained throughout the duration of the project.

HAM-275-28.29

PID: 106411 CONSTRUCTION COST: $7.7 million SCHEDULE: Summer 2021 – Summer 2022

PROJECT DESCRIPTION: Safety improvement project at the I-275 and U.S. 42 interchange. Construction includes re-assigning lane usage on U.S. 42 through the interchange and at Hauck Road.

MAINTENANCE OF TRAFFIC: Traffic on the mainline of I-275 will be maintained throughout the duration of the project; intermittent lane restrictions will be in effect on U.S. 42 and on the ramps.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY New Projects

HAM-275-31.88/32.70

PID: 100808 CONSTRUCTION COST: $4.45 million SCHEDULE: Summer 2021 – Summer 2022

PROJECT DESCRIPTION: A pedestrian and bike facility project to replace barriers and construct a sidewalk on Cornell Road over I-275 and a bridge deck replacement and sidewalk construction project on Weller Road over I-275.

MAINTENANCE OF TRAFFIC: Traffic will be maintained on the mainline throughout the duration of the project; intermittent periods of overnight closures and restrictions may be imparted on Cornell and Weller roads.

HAM-275-34.70

PID: 110176 CONSTRUCTION COST: $644,950 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: A landslide remediation project along the right shoulder of the I-275 westbound entrance ramp from Loveland-Madeira Road.

MAINTENANCE OF TRAFFIC: Traffic will be maintained throughout construction; however, intermittent lane restrictions and shoulder closures will be in effect.

HAM-22-10.21

PID: 102887 CONSTRUCTION COST: $1.82 million SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: A resurfacing project between Silverton and Galbraith Road.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in a minimum of one lane in either direction throughout construction.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY New Projects

HAM-27-10.39

PID: 106404 CONSTRUCTION COST: $598,065 SCHEDULE: Summer 2021

PROJECT DESCRIPTION: A sidewalk construction project on the west side of U.S. 27 (Colerain Avenue), between Banning Road and Bryneside Drive.

MAINTENANCE OF TRAFFIC: Traffic will be maintained with minimal impacts to motorists.

HAM-42-9.62

PID: 109354 CONSTRUCTION COST: $330,202 SCHEDULE: Fall 2021

PROJECT DESCRIPTION: A sidewalk construction project on the west side of U.S. 42, between Sunnybrook Drive and S.R. 126; construction also includes installing a section of sidewalk along the east side of U.S. 42 in Reading.

MAINTENANCE OF TRAFFIC: Traffic will be maintained with minimal impacts to motorists.

HAM-42-11.97

PID: 98547 CONSTRUCTION COST: $954,323 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: A bridge rehabilitation over Cooper Creek, near Cooper Road and the Reading corporation limit.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in a minimum of one lane in either direction.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY New Projects

HAM-50-22.30/22.38

PID: 96696 CONSTRUCTION COST: $1.82 million SCHEDULE: Spring – Fall 2021

PROJECT DESCRIPTION: A bridge rehabilitation/preservation project on the ramps from U.S. 50 East to Martin Drive and over mainline U.S. 50 (Columbia Parkway).

MAINTENANCE OF TRAFFIC: Traffic will be maintained on the mainline of U.S. 50; however, lane and ramp closures will be in effect at various intervals during construction.

HAM-127-9.67

PID: 111202 CONSTRUCTION COST: $202,168 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: A pedestrian improvement project on U.S. 127 (Hamilton Avenue) in North College Hill.

MAINTENANCE OF TRAFFIC: Traffic will be maintained with minimal impacts to motorists.

HAM-32/125-1.20/0.00 (LMST)

PID: 107295 CONSTRUCTION COST: $7.91 million SCHEDULE: Spring 2021 – Summer 2022

PROJECT DESCRIPTION: Construction of a new segment of the Little Miami Scenic Trail from the existing trail under the S.R. 32/Beechmont Avenue interchange and to Lunken Trail by way of the Little Miami River (LMR) using the existing Beechmont Avenue bridge.

MAINTENANCE OF TRAFFIC: Traffic will be maintained on Beechmont Avenue and S.R. 32, with intermittent restrictions in place at the ramps and on S.R. 125.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY New Projects

HAM-125-3.78

PID: 24948 CONSTRUCTION COST: $171,246 SCHEDULE: Fall 2020 – Summer 2021

PROJECT DESCRIPTION: A bridge rehabilitation project over Clough Creek, immediately west of Berkshire Lane.

MAINTENANCE OF TRAFFIC: Traffic on S.R. 125 will be maintained in a minimum of one lane in either direction. Berkshire Lane will be maintained by flaggers as needed during hours of operation.

HAM-264-0.00

PID: 113065 CONSTRUCTION COST: $509,373 SCHEDULE: Fall 2021

PROJECT DESCRIPTION: A resurfacing project in the village of Cleves, from U.S. 50 to the east corporation limit.

MAINTENANCE OF TRAFFIC: Traffic will be maintained in a minimum of one lane.

HAM-CR376-0.96

PID: 109437 CONSTRUCTION COST: $294,774 SCHEDULE: Fall 2021 – Summer 2022

PROJECT DESCRIPTION: A sidewalk construction project along Paddison Road between Beechmont Avenue and Woodridge Drive.

MAINTENANCE OF TRAFFIC: Traffic will be maintained with minimal impacts to motorists.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY New Projects

HAM-Lincoln Heights

PID: 106427 CONSTRUCTION COST: $256,135 SCHEDULE: Summer 2021

PROJECT DESCRIPTION: A Safe Routes to School project to construct sidewalks and upgrade traffic controls near Lincoln Heights Elementary School.

MAINTENANCE OF TRAFFIC: Traffic will be maintained with minimal impacts to motorists.

HAM-Mt. Healthy

PID: 106426 CONSTRUCTION COST: $158,799 SCHEDULE: Summer 2021

PROJECT DESCRIPTION: A Safe Routes to School project to construct sidewalks along the north side of Compton Road, between Forest and Werner Avenues. Project will also include curb ramps, pavement markings and signage at various locations on U.S. 127.

MAINTENANCE OF TRAFFIC: Traffic will be maintained with minimal impacts to motorists.

HAM-

PID: 113528 CONSTRUCTION COST: $1.12 million SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Construction of pedestrian improvements at various locations in the city of Cincinnati and two locations in the city of Norwood for the Pedestrian Safety Improvement Program.

MAINTENANCE OF TRAFFIC: Traffic will be maintained along affected routes with minimal impacts to motorists.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY New Projects

Districtwide - Various Locations

PID: 98507 CONSTRUCTION COST: $671,000 SCHEDULE: Fall 2021 – Fall 2022

PROJECT DESCRIPTION: A districtwide bridge sealing project to apply sealant to various structures throughout District 8.

MAINTENANCE OF TRAFFIC: Traffic will be maintained on all affected routes at all times.

Districtwide - Various Locations

PID: 111482 CONSTRUCTION COST: $455,675 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: A guardrail repair/replacement project at multiple locations in District 8, including U.S. 22, U.S. 42, U.S. 50, U.S. 52, S.R. 4, S.R. 32 and S.R. 264 in Hamilton County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

Districtwide - Various Locations

PID: 100835 CONSTRUCTION COST: $2.84 million SCHEDULE: Summer 2021 – Summer 2022

PROJECT DESCRIPTION: Bridge maintenance project at multiple locations in District 8, including structures on S.R. 126, U.S. 50, I-74 and I-275 in Hamilton County. MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

HAMILTON COUNTY New Projects

Districtwide - Various Locations

PID: 101025 CONSTRUCTION COST: $2.11 million SCHEDULE: Summer 2021 – Summer 2023

PROJECT DESCRIPTION: Signalization project at multiple locations in District 8, including locations on S.R. 125, S.R. 126, S.R. 264, U.S. 22, U.S. 27, U.S. 127, I- 71, I-74 and I-275 in Hamilton County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

PREBLE COUNTY Carry-Over Projects

PRE-70-0.00

PID: 96654 CONSTRUCTION COST: $28.2 million SCHEDULE: Summer 2020 – Summer 2022

PROJECT DESCRIPTION: Pavement repair, bridge rehabilitations and resurfacing on I-70 from the Indiana State line to the Montgomery County line. Construction will also include paving work in the rest area and weigh station.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in each direction.

PRE-35-12.58/15.41/19.68

PID: 96686 CONSTRUCTION COST: $2.91 million SCHEDULE: Winter 2020 – Summer 2021

PROJECT DESCRIPTION: A bridge replacement project at three locations between Eaton and the Montgomery County line: over Rocky Run, just east of Eaton; at T.R. 336 (Stover Road); and at T.R. 57 (County Line Road).

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on U.S. 35; arterial county routes will be subject to additional lane restrictions and temporary closures.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

PREBLE COUNTY New Projects PRE-70-Various Locations

PID: 105967 CONSTRUCTION COST: $324,814 SCHEDULE: Summer 2021

PROJECT DESCRIPTION: Culvert maintenance project at various locations between the Indiana state line and the Montgomery County line.

MAINTENANCE OF TRAFFIC: Construction will be conducted off the roadway, and there should be little to no impact to traffic.

PRE-40-6.73

PID: 108849 CONSTRUCTION COST: $680.789 SCHEDULE: Spring – Fall 2021

PROJECT DESCRIPTION: A bridge replacement project on U.S. 40 over Bantas Fork, between Pence Sheman Road and S.R. 726.

MAINTENANCE OF TRAFFIC: U.S. 40 will be closed for up to 30 days, and traffic will be detoured via I-70 and U.S. 127. At all other times, traffic will be maintained with the use of flaggers as needed.

PRE-127-14.69

PID: 98567 CONSTRUCTION COST: $2.36 million SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: A resurfacing and pavement repair project between the northern corporation limit of Eaton and West Manchester.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained with the use of flaggers as needed.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

PREBLE COUNTY New Projects PRE-177-0.70

PID: 110460 CONSTRUCTION COST: $598,731 SCHEDULE: Spring – Fall 2021

PROJECT DESCRIPTION: An intersection improvement project at the intersection of Oxford Germantown Road.

MAINTENANCE OF TRAFFIC: S.R. 177 will be closed for approximately 60 days, and traffic will be detoured via S.R. 73 and S.R. 732. At all other times, traffic will be maintained with the use of flaggers as needed.

PRE-732-9.46

PID: 100622 CONSTRUCTION COST: $1.13 million SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: A resurfacing project between Wyatt Road and Camden Road, south of Eaton.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained with the use of flaggers as needed.

PRE-Eaton

PID: 109091 CONSTRUCTION COST: $156,020 SCHEDULE: Summer 2021

PROJECT DESCRIPTION: Construction along E. St. Clair Street of multiple pedestrian-related improvements associated with the Eaton School District. Improvements include installation of curb bump-outs, installation of signage, and application of high visibility crosswalk markings.

MAINTENANCE OF TRAFFIC: Traffic will be maintained on affected routes at all times and with the use of flaggers as needed.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

PREBLE COUNTY New Projects

PRE-New Paris

PID: 107136 CONSTRUCTION COST: $302,500 SCHEDULE: Summer 2021 – Summer 2022

PROJECT DESCRIPTION: Bridge replacement on Spring Street over Rocky Fork in the village of New Paris.

MAINTENANCE OF TRAFFIC: Spring Street will be closed for up to 60 days, and traffic will be detoured via Cedar Springs Road/Difederico Drive, Washington Street and Wrenn Avenue. At all other times and with the use of flaggers as needed.

Districtwide-Various

PID: 101025 CONSTRUCTION COST: $2.11 million SCHEDULE: Summer 2021 – Summer 2023

PROJECT DESCRIPTION: Signalization project at multiple locations in District 8, including I-275, U.S. 40 and S.R. 177 in Preble County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

WARREN COUNTY Carry-Over Projects

WAR-22/48-3.03/8.63

PID: 103849 CONSTRUCTION COST: $7.29 million SCHEDULE: Spring 2020 – Summer 2021

PROJECT DESCRIPTION: A dual bridge rehabilitation project on U.S. 22 near the C.R. 10/23 (Old 3-C Highway/Fosters-Maineville Road) intersection, and on S.R. 48 near the corporation limit of South Lebanon.

MAINTENANCE OF TRAFFIC: S.R. 48 will be closed during the Summer of 2020, and traffic will be detoured via U.S. 22, S.R. 123 and I-71. U.S. 22 will be subject to a 50-day closure during 2021, and traffic will be detoured via C.R. 15 (Columbia Road), Western Row Road, I-71 and S.R. 48.

Districtwide-Various

PID: 94224 CONSTRUCTION COST: $2.34 million SCHEDULE: Summer 2020 – Summer 2021

PROJECT DESCRIPTION: Districtwide bridge maintenance project on structures located on S.R. 126 in Butler County; S.R. 131, S.R. 132 and S.R. 32 in Clermont County; U.S. 35 in Greene County; I-75, I-275, U.S. 50, S.R. 126 and S.R. 562 in Hamilton County; and I-75 in Warren County.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on all affected routes. Districtwide-Various

PID: 109571 CONSTRUCTION COST: $2.39 million SCHEDULE: Summer 2020 – Spring 2021

PROJECT DESCRIPTION: An interchange lighting installation project at locations on I-71/S.R. 741 and I-71/Wilmington Road interchanges in Warren County; I- 275/S.R. 126 interchange in Hamilton County; and U.S. 35/S.R. 835 interchange in Greene County.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on all affected routes.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

WARREN COUNTY New Projects

WAR/HAM-71-0.00/19.83

PID: 104844 CONSTRUCTION COST: $5.10 million SCHEDULE: Fall 2021 – Summer 2023

PROJECT DESCRIPTION: Construction of an on-ramp from southbound Mason-Montgomery Road to southbound I-71.

MAINTENANCE OF TRAFFIC: Traffic will be maintained on I-71, with intermittent periods of restriction at the project site.

WAR-22-7.12

PID: 106981 CONSTRUCTION COST: $1.26 million SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Construction of left-turn lanes in both directions on U.S. 22 at Zoar Road.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained in either direction.

WAR-48-9.49

PID: 113709 CONSTRUCTION COST: $480,955 SCHEDULE: Fall 2021 – Summer 2022

PROJECT DESCRIPTION: Signalization project to upgrade the existing signal at S.R. 48 and Corwin Nixon Boulevard and provide pedestrian accommodations.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

WARREN COUNTY New Projects

WAR-63-0.84

PID: 109049 CONSTRUCTION COST: $157,500 SCHEDULE: Spring 2021

PROJECT DESCRIPTION: Installation of a railroad interconnected traffic signal for the purpose of controlling traffic at the at-grade crossing, located at the Monroe corporation limit, just east of the I-75 interchange.

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained.

WAR-CR19-2.67

PID: 113596 CONSTRUCTION COST: $1.12 million SCHEDULE: Summer 2021

PROJECT DESCRIPTION: Resurfacing of C.R. 19 (South Dixie Highway) from the southern corporation limit of Franklin to the railroad crossing just south of S.R. 73

MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be maintained on all affected routes.

WAR-Franklin

PID: 100187 CONSTRUCTION COST: $678,000 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: Reconstruction of three traffic signals located on Riley Boulevard and Sixth Street in Franklin.

MAINTENANCE OF TRAFFIC: Traffic will be maintained and with the use of flaggers as needed.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

WARREN COUNTY New Projects WAR-Springboro

PID: 113610 CONSTRUCTION COST: $476,194 SCHEDULE: Summer 2021

PROJECT DESCRIPTION: Traffic control improvement project at nine signalized intersections, including S.R. 73 at Shart Road/Greenwood Lane, Pioneer Boulevard Clearcreek Franklin Road, and Springwood Road; and on S.R. 741 at S.R. 73, Lytle-Five Points Road, Remick Boulevard, and Pennyroyal Road.

MAINTENANCE OF TRAFFIC: Traffic will be maintained on all affected routes.

WAR/CLE-Various Locations

PID: 105106 CONSTRUCTION COST: $1.27 million SCHEDULE: Spring – Summer 2021

PROJECT DESCRIPTION: Pavement overlay and repair on various routes, including S.R. 123, between S.R. 28 and U.S. 22, and S.R. 132, between the Clermont County line and S.R. 123 in Warren County.

MAINTENANCE OF TRAFFIC: Traffic on affected routes will be maintained in one lane with the use of flaggers.

WAR/CLE-Various Locations

PID: 105393 CONSTRUCTION COST: $491,090 SCHEDULE: Spring – Fall 2021

PROJECT DESCRIPTION: Culvert replacement and rehabilitation project at various locations, including S.R. 48 and S.R. 741 in Warren County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained with flaggers and/or temporary signals as needed, and affected routes may be subject to periods of closure.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

WARREN COUNTY New Projects

Districtwide-Various

PID: 101025 CONSTRUCTION COST: $2.11 million SCHEDULE: Summer 2021 – Summer 2023

PROJECT DESCRIPTION: Signalization project at multiple locations in District 8, including I-71, I-75, U.S. 22, U.S. 42, S.R. 48, S.R. 73 and S.R. 741 in Warren County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

Districtwide-Various

PID: 111482 CONSTRUCTION COST: $455,675 SCHEDULE: Summer – Fall 2021

PROJECT DESCRIPTION: A guardrail repair/replacement project at multiple locations in District 8, including S.R. 73, S.R. 123 and C.R. 230 in Warren County.

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times.

ODOT DISTRICT 8 2021 CONSTRUCTION PROGRAM

OUR MISSION

To provide safe and easy movement of people and goods from.. place to place, we will:.. • Improve safety; .. • Take care of what we have; .. • Make our system better; .. • Enhance capacity. ..

OUR VISION

A long-term, reliable, professional and highly productive organization. ..

OUR GUIDING PRINCIPLES

We will serve, innovate, and communicate with purpose. .. We will be productive, lean, efficient and effective. .. We will utilize the public resources entrusted to us by.. satisfying the State's transportation needs. .. We will be the standard of excellence for winter maintenance. .. We will create a working environment based on trust and mutual respect. .. We will value the diversity of all ODOT people. .. We will work together — one team: .. the Ohio Department of Transportation. ..

For more information, contact ODOT District 8’s Public Information Office at (513) 933-6517/6534. Like us on Facebook: Follow us on Twitter: Statewide Traffic Information: /ODOTDistrict8 @ODOT_Cincinnati www.Ohgo.com For general information, call (513) 933-6568 or visit District 8’s web site at: www.transportation.ohio.gov/dist8