Updated FORM – 1

By

PHOENIX INNSdesh. PVT. LTD. (Retail cum Multiplex Complex) RS No. # 176 / 1,

Enikepadu village, Rural mandal, Krishna district,

Andhra Pradesh

Prepared by

6-3-652 | Flat # 7-3 | Dhruvatara Apartments | Amrutha Estates | Erramanjil | Somajiguda | |Hyderabad- 500082|Phone: + 91-40-23314270 / 71| E mail: [email protected] |www.pioneerenvirolabs.com | PEOPLE | SAVE ENVIRONMENT | PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum) APPENDIX I (See paragraph – 6) FORM - 1 S. No (I) Basic Information 1 Name of the project PHOENIX INNS PVT. LTD. (Retail cum Multiplex Complex) 2 S. No. in the schedule 8(a) 3 Proposed capacity / area / length / Total Built up area – 26,304.53 Sq.m tonnage to be handled / command area / (which includes building with 3 lease area/number of wells to be drilled basements + ground floor + 6 upper floors + mumty) The increase in built-up area is only due to addition of basement floor for parking purpose. Earlier we have proposed stack parking for parking purpose, now we proposed to add another basement floor for parking purpose. 4 New / Expansion / Modernization For corrigendum in Amended Environmental clearance issued vide no. SEIAA / AP / KRI / CON / 05 / 2018 / 576 dated 03-05-2019 The company name is mentioned as “Phoenix Multiplex Pvt. Ltd” instead of “Phoenix Inns Pvt. Ltd”. RS. No. is mentioned as “176/Ru” instead of “176/1” Mandal is mentioned as “Penamluru” instead of “Vijayawada Rural” 5 Existing capacity/Area etc. There is no change in built-up area issued in amended Environmental clearance issued vide no. SEIAA / AP / KRI / CON / 05 / 2018 / 576 dated 03-05-2019 6 Category of project i.e. ‘A’ or ‘B’. B 7 Does it attract the general condition? If No yes, please specify. 8 Does it attract the specific condition? If No yes, please specify. 9 Location Plot/Survey / Khasra No. RS No. # 176/1 Village Tehsil / Mandal Vijayawada Rural District Krishna

1 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum) State 10 Nearest railway station/airport along with Nearest Railway station: Ramavarappadu distance in kms. – 2.1 Kms. Nearest Airport – Gannavaram airport – 9.5 Kms 11 Nearest Town, city, District Headquarters Nearest town: Vijayawada along with distance in kms District Head quarter: Vijayawada 12 Village Panchayats,Zilla Parishad, Vijayawada Municipal Corporation Municipal corporation, Local body(complete postal addresses with telephone no.s to be given) 13 Name of the applicant PHOENIX INNS PVT. LTD. 14 Registered Address 1335, Phoenix House, Road No 45, Jubilee Hills, Hyderabad 500033 15. Address for correspondence: Name SRIKANTH BADIGA Designation(owner/partner/CEO) Group Director Address 1335, Phoenix House, Road No 45, Jubilee Hills, Hyderabad 500033 Pin code 500033 E-Mail [email protected] Telephone No. 91-40-23553351 / 61 Ext : 143 Fax No. Details of Alternative sites examined, if No alternate sites are considered 16. any. Location of these sites should be shown on a topo sheet

17. Interlinked Projects No 18. Whether separate application of No interlinked project has been submitted?

19. If yes, date of submission Not applicable 20. If no, reason Not applicable 21. Whether the proposal involves No approval/clearance under; if yes, details of the same and their status to be given. (a) The Forest (conservation)Act,1980 (b) The Wildlife(protection)Act,1972 (c) The C.R.Z Notification,1991?

2 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum) Whether there is any a government No 22. order/policy relevant/relating to the site? 23. Forest land involved(hectares) No 24. Whether there is any litigation pending No against the project and/or land in which the project is propose to be set up? (a)Name of the court (b)Case No. (c) Orders/directions of the court, if any and its relevance with the proposed project.

3 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum)

(II) ACTIVITY 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Details thereof (with approximate S.No. Information/Checklist Yes/No quantities /rates, wherever possible) confirmation with source of information data 1.1 Permanent or temporary change in Yes There is no change in built-up area land use, land cover or topography issued in amended Environmental including increase in intensity of clearance issued vide no. SEIAA / land use (with respect to local AP / KRI / CON / 05 / 2018 / 576 land use plan) dated 03-05-2019 Hence there will not be any adverse impact due to the change in land use pattern due to the proposed amendment of Environmental clearance issued 1.2 Clearance of existing land, Yes Sparse vegetation consisting of vegetation and buildings? Thorny and shrubs exists in the site earmarked for the proposed Retail cum Multiplex complex. However good Greenbelt / greenery will be developed with in the premises as per the norms. Hence there will not be any adverse impact due clearance of vegetation due to the proposed Retail cum Multiplex complex 1.3 Creation of new land uses? No Presently there are sheds and buildings in the site area proposed for Retail cum Multiplex. These sheds and buildings will be demolished before the construction of the Retail cum Multiplex. 1.4 Pre-construction investigations e.g. No Investigations will be carried out for bore houses, soil testing? soil and water at the site. 1.5 Construction works? No No construction work will be taken- up without obtaining the Prior Environmental clearance from SEIAA and Consent For Establishment from APPCB. 1.6 Demolition works? Yes Presently there are sheds and buildings in the site area proposed

4 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum) Details thereof (with approximate S.No. Information/Checklist Yes/No quantities /rates, wherever possible) confirmation with source of information data for Retail cum Multiplex complex. These will be demolished before the construction of the Retail cum Multiplex complex. 1.7 Temporary sites used for Yes Construction workers will be from construction works or housing of local area only. Temporary housing construction workers? is proposed for construction workers. 1.8 Above ground buildings, structures Yes Most of the structures will be above or earthworks including linear the ground. However excavations structures, cut and fill or will be involved for foundations. The excavations excavation will be stacked properly at site. Part of the excavated soil will be used for backfilling, greenery and landscaping and balance quantity will be sent to the sites where land filling is required 1.9 Underground works including mining No No mining and tunneling will be or tunneling? involved in the proposed activity. 1.10 Reclamation works? No No reclamation works are envisaged in proposed project. 1.11 Dredging? No No dredging activity will be involved. 1.12 Offshore structures? No No offshore structures are envisaged in the proposed project. 1.13 Production and manufacturing No Not applicable as proposed project processes? involves construction of Retail cum Multiplex complex. 1.14 Facilities for storage of goods or Yes Raw materials will be stored as per materials? norms. The raw materials like Cement, Sand, Bricks, Steel, Wood, Paint & aggregates will be stored at site only. Cement & Paint will be stored at indoors & remaining will be at outdoors. 1.15 Facilities for treatment or disposal of Yes Wastewater generated during the solid waste or liquid effluents? operation of the Retail cum Multiplex complex will be treated in sewage treatment plant. Treated wastewater will be utilized for non- potable purposes like Toilet flushing, HVAC & Greenbelt

5 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum) Details thereof (with approximate S.No. Information/Checklist Yes/No quantities /rates, wherever possible) confirmation with source of information data development. Treatment and disposal of wastewater & solid waste will be in accordance with the CPCB/APPCB norms. 1.16 Facilities for long term housing of No No permanent housing will be operational workers? provided for the construction workers. 1.17 New road, rail or sea traffic during Yes There will be a slight increase in construction or operation? traffic volume during construction and operation of the proposed Retail cum Multiplex complex. The proposed Retail cum Multiplex complex is well connected by NH # 16. Hence there will not be any adverse impact on road traffic / rail traffic / sea traffic due to the proposed Retail cum Multiplex complex. 1.18 New road, rail, air waterborne or No No new road / rail / air transport other transport infrastructure infrastructure is proposed. including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of existing No No closure or diversion of existing transport routes or infrastructure transport routes is envisaged. leading to changes in traffic movements? 1.20 New or diverted transmission lines No Water required for the proposed or pipelines? Retail cum Multiplex complex will be sourced from Municipal supply. 1.21 Impoundment, damming, culverting, No No culverting, realignment are realignment or other changes to the envisaged. There will not be any hydrology of watercourses or changes to the hydrology of aquifers? watercourses or aquifers. 1.22 Stream crossings? No No stream crossing is involved 1.23 Abstraction or transfers of water Yes Water required for the proposed form ground or surface waters? project will be sourced from Municipal supply. 1.24 Changes in water bodies or the land No No changes in water bodies, surface affecting drainage or run- drainage and land surface are off? anticipated as the site is more or less flat without many undulations.

6 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum) Details thereof (with approximate S.No. Information/Checklist Yes/No quantities /rates, wherever possible) confirmation with source of information data Separate storm water drains will be provided. 1.25 Transport of personnel or materials Yes There will be a slight increase in for construction, operation or traffic volume during construction decommissioning? and operation of the proposed Retail cum Multiplex complex. The proposed Retail cum Multiplex complex is well connected by NH # 16. The existing road can handle this additional increase in vehicular traffic. Hence there will not be any adverse impact on road traffic / rail traffic / sea traffic due to the proposed Retail cum Multiplex complex. 1.26 Long-term dismantling or No No such works are envisaged decommissioning or restoration works? 1.27 Ongoing activity during No No such works are envisaged decommissioning which could have an impact on the environment? 1.28 Influx of people to the area either No Temporary labour required for the temporarily or permanently? construction activity will be met from the local places. 1.29 Introduction of alien species? No No such activity is envisaged 1.30 Loss of native species or genetic No As a part of greenbelt/greenery diversity? development plan native species that are suitable to that soil condition will be developed. 1.31 Any other actions? No Nil

7 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum)

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply)

Details thereof (with approximate S.No. Information/checklist Yes/No quantities /rates, wherever confirmation possible) with source of information data 2.1 Land especially undeveloped or Yes Presently there are sheds and agricultural land (ha) buildings in the site area proposed for Retail cum Multiplex. These will be demolished before the construction of the Retail cum Multiplex complex. Total land acquired for proposed Retail cum Multiplex complex is 1.43 acres (5,786.41 Sq.m). Net area available after road widening – 1.39 acres (5,627.09 Sq.m) Water (expected source & Yes Water required for the proposed competing users) unit: KLD project will be sourced through 2.2 Municipal supply / Ground water during operation of the Project and through Ground water during construction of the Project. Total water demand is about 10 KLD during Construction of complex & 183 KLD during operation of the Retail cum Multiplex complex.

The increase in built-up area is only due to addition of basement floor for parking purpose. Earlier we have proposed stack parking for parking purpose, now we proposed to add another basement floor for parking purpose.

Hence there will not be any change in water requirement. 2.3 Minerals (MT) Yes Manufactured sand – 16,000 MT 2.4 Construction material – stone, Yes All construction materials such as aggregates, sand / soil (expected Ready mix Concrete, Cement, source – MT) Sand, Aggregate, Aerated Auto clave, Concrete Brick (nos.),

8 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum) Details thereof (with approximate S.No. Information/checklist Yes/No quantities /rates, wherever confirmation possible) with source of information data Reinforcement Steel, Wood material, Painting material, Flooring Material, Sanitary Material, Electrical Material, Plumbing material are available locally. 2.5 Forests and timber (source – MT) No Wood material required for Windows & Doors of Imported Quality will be procured locally. 2.6 Energy including electricity and fuels Yes The total energy requirement for (source, competing users) Unit: fuel the proposed project is 4000 kVA (MT), energy (MW) (Maximum peak demand). It will be taken from Transco. However 3 x 2000 kVA DG sets will be provided for emergency Backup Power Supply. 2.7 Any other natural resources (use No Not applicable appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health

Details thereof (with approximate S.No. Information/Checklist Yes/No quantities/rates, wherever possible) confirmation with source of information data 3.1 Use of substances or materials, Yes The hazardous wastes like empty which are hazardous (as per containers of paints, petroleum MSIHC rules) to human health or products, thinners, adhesives will be the environment (flora, fauna, and given to authorized recyclers. All the water supplies) hazardous materials will be stored as per HWM rules. 3.2 Changes in occurrence of disease No Not Applicable or affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people e.g. by No Not Applicable as the proposed changing living conditions? Retail cum Multiplex complex will create direct / indirect employment opportunities in the area and thereby contributing in the improvement of socio-economic status of people in the area. Land prices will increase

9 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum) substantially.

3.4 Vulnerable groups of people who No  Approach roads to the complex could be affected by the project e.g. will be paved hospital patients, children, the  Speed of the vehicles will be elderly etc., reduced  Greenbelt will be developed By following the above the dust generation will be minimized. The Solid waste in the form of garbage will be segregated at each section distinguishing wet and dry waste. Dry waste will be taken away by Municipal Corporation. Wastewater generated from the Retail cum Multiplex complex will be treated in sewage treatment plant and treated waste water will be utilized for non-potable purposes like flushing, HVAC and Green belt development plan Hence there will not be any adverse impact on vulnerable groups. 3.5 Any other causes No Not Applicable

10 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum)

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

Details thereof (with approximate S.No. Information/Checklist Yes/No quantities/rates, wherever possible) confirmation with source of information data 4.1 Spoil, overburden or mine wastes Yes The excavation will be stacked properly at site. Part of the excavated soil will be used for backfilling, greenery and landscaping and balance quantity will be sent to the site where land filling is required. 4.2 Municipal waste (domestic and or Yes Municipal solid waste generated Residential wastes) during construction phase of the project will be given to the Municipal Corporation. The Solid waste generated during operation phase will be mainly in the form of garbage, paper waste, plastic waste and e-waste from the Retail cum Multiplex complex. The garbage will be segregated at each section distinguishing wet and dry waste. Kitchen and food waste will be composted within the complex premises only. 4.3 Hazardous wastes (as per Yes Used batteries & Waste oil will be Hazardous Waste given to APPCB approved vendors Management Rules) 4.4 Other industrial process wastes No Not Applicable as there will not be any industrial operations in the Complex 4.5 Surplus product Yes Surplus raw materials after construction will be given to the suppliers. 4.6 Sewage sludge or other sludge Yes Sewage sludge generated will be from effluent treatment stored in HDPE bags and will be used as manure. 4.7 Construction or demolition wastes Yes At the time of construction of the proposed project, there will be some recyclable material like Steel, metal,

11 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum) Details thereof (with approximate S.No. Information/Checklist Yes/No quantities/rates, wherever possible) confirmation with source of information data Plastic material, Wood etc., will be sent to reuse / recycle and other wastes like Bricks, cement waste will be used for leveling. The disturbed slopes shall be well stabilized before the onset of the monsoon. Presently there are sheds and buildings in the site area proposed for Retail cum Multiplex. These will be demolished before the construction of the Retail cum Multiplex. Demolition waste will be recycled / disposed as per norms. 4.8 Redundant machinery or equipment No No redundant machinery will be kept in the premises after construction of the Retail cum Multiplex complex 4.9 Contaminated soils or other No During the construction phase of materials the Project, all precautionary measures will be taken to prevent the spillage of oil, paints on to the ground to prevent the contamination of soil. 4.10 Agricultural wastes No Not applicable 4.11 Other solid wastes Yes E-waste generated will be given Authorized recyclers approved by APPCB.

12 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum)

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Details thereof (with approximate S.No. Information/Checklist Yes/No quantities/rates, wherever possible) confirmation with source of information data 5.1 Emissions from combustion of Yes During the operation phase of the fossil fuels from stationary or Retail cum Multiplex complex, mobile sources emissions will be mainly PM, HC, CO and NOx due to vehicular traffic and from D.G. sets provided for Backup power supply.  All the roads leading to the complex and internal roads will be paved. Hence the dust emissions due to the vehicles will be very low  Good greenbelt will be developed in the complex premises which will further help in mitigating the emission levels.  Stack of adequate height will be provided for effective dispersion of gases into the atmosphere. Hence there will not be any much impact on surrounding environment due to the proposed Retail cum Multiplex complex. 5.2 Emissions from production No Not applicable. processes 5.3 Emissions from materials handling No Not applicable as there will not be including storage or transport any storage or transportation of raw materials 5.4 Emissions from construction Yes During construction phase, there activities including plant and will be dust emissions during raw equipment material handling and transportation of raw materials. To mitigate the dust emissions  Raw materials will be brought to the site through covered trucks / Trolleys.

13 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum) Details thereof (with approximate S.No. Information/Checklist Yes/No quantities/rates, wherever possible) confirmation with source of information data  Minimum water spraying will be done to mitigate the dust emanation  All the materials will be properly covered to prevent the dust emissions during high winds  Due to the operation of cranes during raw material handling Hence there will not be any significant dust emissions due to raw material storage & transportation during construction phase of the project. 5.5 Dust or odours from handling of Yes Adequate precautionary measures materials including construction will be taken up to control the Odour materials, sewage and waste from the Construction materials like Paint material & Sewage. 5.6 Emissions from incineration of No Not applicable waste 5.7 Emissions from burning of waste in No All such wastes will be disposed open air (e.g. slash materials, along with Municipal Solid Waste. construction debris) 5.8 Emissions from any other sources No Nil

14 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum)

6.0 Generation of Noise and Vibration, and Emissions of Light and Heat:

Details thereof (with approximate S.No. Information/Checklist Yes/No quantities/rates, wherever possible) confirmation with source of information data with source of information data 6.1 From operation of equipment e.g. Yes Main source of Noise generation engines, ventilation plant, crushers will be DG sets and Motor pumps for supply of water. All the D.G. Sets & Motor pumps will be manufactured in accordance with the noise level standards stipulated by MOEF vide notification dated 14-02-2000. Hence there will not be much increase in Noise levels in the surrounding areas. 6.2 From industrial or similar processes Yes The sources of noise generation in the proposed project will be DG sets. All machinery will be manufactured as per OSHA / MOEF guidelines. Ambient noise levels will be in accordance with MOEF notification dated 14-02-2000 i.e. noise levels will be <55 dBA during daytime and < 45 dBA during night time. 6.3 From construction or demolition Yes Construction equipment will cause some noise. Ear plugs will be provided to construction workers who work near the noise generating equipment. 6.4 From blasting or piling No No such operations are involved. 6.5 From construction or operational Yes There will be slight increase in traffic traffic noise during construction and operation of the proposed Retail cum Multiplex complex.  Speed of the vehicles will be reduced  Greenbelt will be developed By following above control measures noise levels will be minimized.

15 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum) Details thereof (with approximate S.No. Information/Checklist Yes/No quantities/rates, wherever possible) confirmation with source of information data with source of information data 6.6 From lighting or cooling systems No Not applicable 6.7 From any other sources No Not applicable

16 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum)

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

Information/Checklist Details thereof (with approximate S.No. confirmation Yes/No quantities/rates, wherever possible) with source of information data 7.1 From handling, storage, use or Yes Good housekeeping practices will spillage of hazardous materials be followed to prevent any spillage of hazardous materials. 7.2 From discharge of sewage or other No Wastewater generated during the effluents to water or the land operation of the Retail cum (expected mode and place of Multiplex complex will be treated in discharge) sewage treatment plant and treated wastewater will be utilized for non- potable purposes like Toilet flushing, HVAC & Gardening 7.3 By deposition of pollutants emitted No During construction phase, there to air into the land or into water will be dust emissions during raw material handling and transportation of raw materials. To mitigate the dust emissions  Raw materials will be brought to the site through covered trucks / Trolleys.  Minimum water spraying will be done to mitigate the dust emanation  All the materials will be properly covered to prevent the dust emissions during high winds  Due to the operation of cranes during raw material handling Hence there will not be any significant dust emissions due to raw material storage & transportation during construction phase of the project. During the operation phase of the Retail cum Multiplex complex, emissions will be mainly PM, NMHC, CO and NOx due to vehicular traffic and from D.G. sets provided for Backup power supply.

17 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum) Information/Checklist Details thereof (with approximate S.No. confirmation Yes/No quantities/rates, wherever possible) with source of information data  All the roads leading to the complex and internal roads will be paved. Hence the dust emissions due to the vehicles will be very low  Good greenbelt will be developed in the complex premises which will further help in mitigating the emission levels.  Stack of adequate height will be provided for effective dispersion of gases into the atmosphere. Hence there will not be any much impact on surrounding environment due to the proposed Retail cum Multiplex complex. 7.4 From any other sources No Not applicable 7.5 Is there a risk of long term build up No Not applicable of pollutants in the environment from these sources?

18 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum)

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment

Details thereof (with approximate S.No. Information/Checklist Yes/No quantities/rates, wherever possible) confirmation with source of information data 8.1 From explosions, spillages, fires etc Yes Good housekeeping practices will from storage, handling, use or be maintained during Construction production of hazardous and Operation phase of the Retail substances cum Multiplex complex. All precautionary measures will be taken to prevent the spillage of oil, paint etc. D.G sets will be operated during short supply of electricity. Hence storage of Diesel will be very low. Hence the occurrence of explosion due to the storage of Diesel will be low. All the rules and regulations as per the Fire & Safety Department, Andhra Pradesh will be followed strictly to prevent the Fire accidents in the complex 8.2 From any other causes Yes Earthquakes & Natural disasters 8.3 Could the project be affected by No Not applicable natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)?

19 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum)

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

Details thereof (with approximate S. No. Information/Checklist Yes/No quantities/rates, wherever possible) confirmation with source of information data 9.1 Lead to development of supporting utilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.: • Supporting infrastructure No No such activities are envisaged (roads, power supply, waste or waste water treatment, etc.) • housing development • extractive industries • supply industries • other 9.2 Lead to after-use of the site, which No Not applicable could have an impact on the environment 9.3 Set a precedent for later Yes With the improvement in the socio- developments economic status of the people in the area, later developments are expected. 9.4 Have cumulative effects due to No Not applicable proximity to other existing or planned projects with similar effects

20 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum)

(III) Environmental Sensitivity

Name/ Aerial distance S.No. Areas Identity (within 15 km.) Proposed project location boundary 1 Areas protected under international No Nil within 15 Km conventions, national or local legislation radius for their ecological, landscape, cultural or other related value 2 Areas which are important or sensitive for Yes RYVES canal – 0.45 ecological reasons - Wetlands, Kms watercourses or other water bodies, Eluru canal – 0.93 coastal zone, biospheres, mountains, Kms forests 3 Areas used by protected, important or No Nil within 15 Km sensitive species of flora or fauna for radius breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, marine or underground Under ground Available at the site waters water

5 State, National boundaries ---- No inter-state boundary, No international boundary. 6 Routes or facilities used by the public for NH # 16 Adjacent to the site access to recreation or other tourist, pilgrim areas 7 Defence installations No Nil within 15 Km radius 8 Densely populated or built-up area Yes Project proposed comes under Vijayawada Municipal jurisdiction 9 Areas occupied by sensitive man-made Many schools & Within 15 Km radius land uses (hospitals, schools, places of Hospitals exits worship, community facilities 10 Areas containing important, high quality or Yes RYVES canal – 0.45 scarce resources Kms (ground water resources, surface Eluru canal – 0.93 resources, forestry, agriculture, fisheries, Kms tourism, minerals) 11 Areas already subjected to pollution or --- Not applicable environmental damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural hazard which --- Based on the could cause the project to present historical data, the environmental problems site is not likely to (earthquakes, subsidence, landslides, prone to erosion, flooding or extreme or adverse earthquakes, floods, climatic conditions) etc.

21 PHOENIX INNS PVT. LTD. Updated FORM –1 RETAIL CUM MULTIPLEX (for corrigendum) (IV). PROPOSED TERMS OF REFERENCE FOR EIA STUDIES

Not applicable as the present proposal is for corrigendum in amended Environmental clearance issued vide no. SEIAA / AP / KRI / CON / 05 / 2018 / 576 - 198 dated 03-05-2019.

“I hereby given undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost.

Date: 24-05-2019 Place: Hyderabad

22