ANNEX F - STATEMENT OF WORK Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 1 of 31

ANNEX F - STATEMENT OF WORK Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam TABLE OF CONTENTS A1. SCOPE SUMMARY ...... 3 A1.1 Purpose ...... 3 A1.2 Project Summary ...... 3 A2. BACKGROUND ...... 3 A2.1 Rideau Falls West Dam ...... 3 A2.2 Stoplog Lifter Operations ...... 3 A3. GOVERNING DOCUMENTS ...... 4 A3.1 Statutory Requirements ...... 4 A3.2 Codes and Standards ...... 4 A3.3 Internal Documents for Reference ...... 5 A4. TECHNICAL REQUIREMENTS ...... 5 A4.1 General Technical Requirements ...... 5 A4.1.1 Maintainability ...... 5 A4.1.2 Corrosion Considerations ...... 5 A4.1.3 Guarding and Safeguarding ...... 5 A4.1.4 Personnel Tie-off Points ...... 5 A4.1.5 Flexible Horizontal Lifeline System ...... 6 A4.2 Gantry Structure ...... 6 A4.2.1 Configuration ...... 6 A4.2.2 Design ...... 6 A4.2.3 Shielding from Spray ...... 7 A4.2.4 Finish ...... 7 A4.3 Mechanical Systems ...... 7 A4.3.1 Hoists...... 7 A4.3.2 Gantry Travel System ...... 8 A4.3.3 Lubrication ...... 9 A4.3.4 Noise Level at Dam Deck ...... 9 A4.4 Electrical and Controls Systems ...... 9 A4.4.1 General Requirements ...... 9 A4.4.2 Power Supply ...... 9 A4.4.2.1 For Motors...... 9 A4.4.2.2 For Strip Heaters ...... 9 A4.4.2.3 For Controls ...... 10 A4.4.3 Enclosures and Panels ...... 10 A4.4.4 Operator’s Controls ...... 11 A4.4.5 Lights ...... 11 A4.4.6 Emergency Stop ...... 12 A5. DELIVERY, INSTALLATION, AND SET-TO-WORK ...... 13 A5.1 Delivery to Dam Site ...... 13 A5.1.1 Stoplog Lifter...... 13 A5.1.2 Operation & Maintenance Manuals ...... 13 A5.1.3 Training ...... 13 A5.2 Deliveries to Shops ...... 13 A5.3 Deliveries to Technical Authority ...... 14

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 2 of 31 A6. ADMINISTRATIVE REQUIREMENTS ...... 14 A6.1 Project Manager ...... 14 A6.2 Meetings...... 14 A6.3 Warranty ...... 14 A6.4 Schedule of Written Deliverables ...... 14 A6.4.1 Due Dates ...... 14 A6.4.2 Project Schedule ...... 15 A6.4.3 Inspection and Test Plan (ITP) ...... 15 A6.4.4 Preliminary Design Package ...... 17 A6.4.5 Critical Design Package...... 18 A6.4.6 Monthly Progress Reports ...... 18 A6.4.7 Results of FAT ...... 18 A6.4.8 Installation Plan ...... 18 A6.4.9 Health & Safety Submittals for Work at Dam Site ...... 19 A6.4.10 Operation & Maintenance Manual ...... 20 A6.4.11 Results of SAT ...... 21 A7. IMAGES ...... 21

LIST OF FIGURES Figure 1: Location of Rideau Falls Dams within the City of Ottawa ...... 21 Figure 2: Rideau Falls, looking upstream. The East Dam is on the left, the West Dam is on the right...... 22 Figure 3: Detail location of Rideau Falls West Dam ...... 22 Figure 4: West Dam looking downstream. Note old stoplog lifter at left...... 22 Figure 5: Schematic of West Dam looking downstream. Dimensions are in millimetres...... 23 Figure 6: Schematic cross-section of West Dam. Dimensions in millimetres except where noted...... 23 Figure 7: West Dam looking upstream, with old stoplog lifter in place...... 23 Figure 8: Old stoplog lifter on West Dam...... 24 Figure 9: Old cable reel for West Dam's old stoplog lifter. (Conductix, NEMA 4, 150 ft of 10 AWG SOOW cable) ... 24 Figure 10: West Dam's spreader beam...... 25 Figure 11: Side view of lifting beam. Lifting lugs are shown in red on top. Dimensions are in feet and inches...... 25 Figure 12: Stoplog storage on the operational deck of West Dam, immediately downstream of the sluice opening...... 26 Figure 13: Old stoplog lifter on West Dam showing ice build-up...... 27 Figure 14: Stoplogs in gain on West Dam (typical)...... 28 Figure 15: Left (west) approach. Crane parking for access adjacent to Sluice #1...... 29 Figure 16: Left (west) approach to West Dam at ground level...... 29 Figure 17: Right (east) approach. Crane parking for access adjacent to Sluice #4...... 30 Figure 18: Right (east) approach to West Dam at ground level...... 30 Figure 19: East Dam's stoplog lifter, for reference...... 31

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 3 of 31 A1. SCOPE SUMMARY A1.1 Purpose This Technical Statement of Requirements (TSOR) defines characteristics required of a new stoplog lifter for Rideau Falls West Dam and associated requirements for equipment delivery. The new stoplog lifter will be used to remove stoplogs from sluices and stack them on dam deck; to retrieve stoplogs from stacked position and placing them in sluices; and, to move stoplogs between sluices along dam deck.

A1.2 Project Summary 1) Appoint a Project Manager to be responsible for Work and to be main point of contact with Canada. 2) Visit and inspect dam site and surrounding areas to conduct all necessary site inspections, surveys, measurements, evaluations, etc. In particular, locate dam appurtenances that could interfere with movements of stoplog lifters and verify all dimensions in situ and measure gauge and section of existing rails before finalizing size of stoplog lifters. 3) Design and fabricate new stoplog lifter. Design and fabrication must be supervised by Professional Engineer(s) licensed to practice in geographic area of fabrication. 4) Be available for site visits from Technical Authority to fabrication shop during fabrication period and before shipping. 5) Deliver, install, and set-to-work the new stoplog lifter on the dam deck. Installation must be supervised by a Professional Engineer licensed to practice in who must supervise installation and certify device to requirements of Ontario regulations, including doing a "Pre-Start Health and Safety Review" to O. Reg. 851. 6) Deliver spare parts, maintenance materials, special tools, and Operating & Maintenance Manuals. 7) New stoplog lifter must be delivered to the dam site no more than 40 weeks from contract Award.

A2. BACKGROUND A2.1 Rideau Falls West Dam The Rideau Falls Dam complex is located in the City of Ottawa where the discharges into the over the Rideau Falls (see Figures 1, 2, and 3). The complex consists of the East Dam and the West Dam located respectively on the east and west sides of Green Island. The West Dam has four sluices (numbering shown in Figures 4 and 5). Sluices #2 and #3 use vertical lift gates to regulate water flow whilst sluices #1 and #4 use stoplogs. Stoplogs can also be placed upstream of the two vertical lift gates to allow the gates to be dewatered for maintenance. Stoplogs are wooden logs, rectangular in cross-section, stacked in special slots called "gains" in the piers (typical gain in Figure 14). The stacked stoplogs form a variable height weir, allowing more or less water to flow through the sluice depending on the number of logs in place in the gains.

A2.2 Stoplog Lifter Operations Stoplogs are handled with a stoplog lifter, being a crane customized to place stoplogs in the sluice and remove them from the sluices for storage on deck (old West stoplog lifter in Figure 8, current East stoplog lifter in Figure 19). The previous stoplog lifter, which was 25 years old, was found to be have a cracked structural member at its last inspection and has since been decommissioned. Canada requires a new stoplog lifting machine to replace the old one. Figures 10 and 11 shows the existing spreader beam, which is to be retained. This connects to a stoplog’s end caps through hooks located on lever arms (one at each end of the spreader beam). To hook onto stoplogs and to release them, Damkeepers move the lever arm manually, either doing this by hand for the upper stoplogs or Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 4 of 31 by means of wooden poles when handling the lower stoplogs. The stoplog lifter lifts the spreader beam and stoplog together. The total load of a double stoplog with the spreader beam together is 7000 pounds weighed in air.

A3. GOVERNING DOCUMENTS In performing the work of the contract, the Contractor must comply with the most recent versions of the following: A3.1 Statutory Requirements 1) Workplace Hazardous Materials Information System (WHMIS 2015) 2) Occupational Health and Safety Act (R.S.O. 1990, c. O.1) 3) O. Reg. 851 Industrial Establishments

A3.2 Codes and Standards 1) ASME (American Society of Mechanical Engineers) a) ASME B30.17 Overhead and Gantry Cranes (Top Running Bridge, Single Girder, Underhung Hoist) b) ASME - ANSI B30.10 Hooks 2) CMAA (Crane Manufacturers Association of America, Inc.) a) CMAA Specification #74: Top Running and Under Running Single Girder Electric Traveling Cranes Utilizing Under Running Trolley Hoist b) CMAA Specification #78: Standards and Guidelines for Professional Services Performed On Overhead and Traveling Cranes and Associated Equipment 3) CGSB (Canadian General Standards Board) a) CAN/CGSB-48.9712-/ ISO 971 2:2012, IDT), Non-destructive Testing - Qualification and Certification of NDT Personnel (ISO 9712:2012, IDT) 4) CSA International (formerly Canadian Standards Association) a) CAN/CSA Z259.13-16, Flexible Horizontal Lifeline Systems b) CAN/CSA Z432-16, Safeguarding of Machinery c) CSA B167-16, Overhead cranes, gantry cranes, monorails, hoists, and jib cranes d) CAN/CSA Z460-20, Control of hazardous energy - Lockout and other methods e) CSA Z259.16-15 Design of Active Fall-Protection Systems 5) IEC (International Electrotechnical Commission) a) IEC 60529, Degrees of protection provided by enclosures (IP Code) b) IEC 62262 Ed. 1.0 b:2002, Degrees of protection provided by enclosures for electrical equipment against external mechanical impacts (IK code) 6) NEMA (National Electrical Manufacturer's Association) a) NEMA 250-2003 (11-Mar-2009), Enclosures for Electrical Equipment (1000 Volts Maximum) 7) SSPC (formerly Steel Structures Painting Council) a) SPC-SP 10 Near-White Metal Blast Cleaning (NACE No.2)

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 5 of 31 A3.3 Internal Documents for Reference The following documents are available only in the languages indicated. Technical Authority will provide these documents to the Contractor after Award. 1) Single line diagrams (bilingual) 2) Drawing of previous stoplog lifter’s frame (Transcrane 1994) 3) Drawing of existing spreader beam

A4. TECHNICAL REQUIREMENTS A4.1 General Technical Requirements 1) New stoplog lifter must conform to all federal and provincial statutory requirements for safety of lifting apparatus and material handling devices and for guarding and safeguarding of personnel. 2) New stoplog lifter must conform to Canadian and international standards and best practices for lifting apparatus and material handling devices.

A4.1.1 Maintainability 1) Provide access to all mechanical, electric, and other equipment for future repairs, maintenance, and replacement of components. 2) Access to motors, gearboxes, and electrical panels must be possible for a single man working from a lift truck. Therefore, weight of shields, guards, and other removable components must be within capacity of a single man to remove and remount. 3) All components that Damkeepers will be required to service must be accessible from dam deck. 4) Provide lifting lugs for lifting whole stoplog lifter and for large subassemblies or components separately, if required by design. Mark centre of gravity on major subassemblies.

A4.1.2 Corrosion Considerations 1) All surfaces to be accessible for inspection and maintenance. 2) Design to eliminate water traps, avoid accumulation of water or dirt, and prevent corrosion. Provide drainage holes if necessary to meet this criterion. 3) Isolate dissimilar metals with nylon grommets, gaskets, or sleeves as appropriate. A4.1.3 Guarding and Safeguarding Employ inherently safe design measures, and where inherently safe design is not practicable, provide safeguarding such as (but not limited to) fixed guarding, interlocked guarding, etc. to CSA Z432 Safe Guarding of Machines and Canada Occupational Health and Safety Regulations (SOR/86-304).

A4.1.4 Personnel Tie-off Points 1) Provide four (4) engineered tie-offs for fall arrest equipment, located on underside of gantry over each gain, and another two (2) each located on each gantry for use by inspection and maintenance personnel climbing gantries. 2) Technical Authority will indicate preferred location on frame shop drawings when these are submitted as part of Preliminary Design Package.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 6 of 31 A4.1.5 Flexible Horizontal Lifeline System 1) Provide two horizontal cables, one on each side of the sluice opening, so that two Damkeepers may tie-off and walk back and forth on deck beside stoplog lifter, one on upstream side and one on downstream side, for the full length of the stoplog lifter, (similar to that provided on the East Dam’s stoplog lifter.) 2) A Professional Engineer must design the system, including anchorages, according to good engineering practice. 3) Horizontal cable to: a) Section 85 of O. Reg. 851 Industrial Establishments, as amended; b) Section 12.10 of Canada Occupational Health and Safety Regulations (SOR/86-304); c) CSA Z259.16-15 Design of Active Fall-Protection Systems; and, d) CSA Z259.13 Flexible Horizontal Lifeline Systems. 4) Assume in design that, when using horizontal cable, Damkeepers are wearing a Class A full body harness to CAN/CSA Z259.10 Full Body Harnesses and a fall-limiting device to CAN/CSA Z259.2.2 Self-Retracting Devices for Personal Fall Arrest Systems complete with connecting components to CSA Z259.12-11 Connecting Components for Personal Fall Arrest Systems. 5) Note that this Standard specifies strength requirements for anchorages but not strength-testing requirements for such anchorages. Test strength of anchorages to provincial regulations, or submit calculations proving that they meet requirements.

A4.2 Gantry Structure A4.2.1 Configuration 1) Provide stoplog lifter with same general configuration as the existing stoplog lifter on the East Dam, that is, two gantry cranes rigidly joined together (see Figure 19 for general configuration). 2) Each gantry itself must consist of two portal frames joined at the top by a single transverse crane beam upon which the new underhung 5-ton wire rope hoist is to be mounted. 3) Each hoist will lift one end of the existing spreader beam. A4.2.2 Design 1) Design for a safe working load of 5,000 pounds per gantry (10,000 pounds for machine overall). 2) Dimensions a) Vertical distance from deck to underside of crane beam must be same as for previous version of stoplog lifter gantry (see Transcrane drawing). b) Gantry wheels to be located same as for previous gantry (see Transcrane drawing). c) Spacing between gantries must suit the lifting points on spreader beam (see drawing of spreader beam). d) Maintain minimum 3 inches clearance from all existing dam appurtenances in all positions on dam deck. 3) To make repairs and overhauling easier in future, use bolted connections in preference to welded wherever possible. 4) Clearly identify information about bolt strength and bolt torque limits on as-built drawings; this will assist in future when bolts are changed as part of periodic maintenance activities. 5) Provide rubber bumpers at ends of gantries to absorb kinetic energy of stoplog lifter impacting end stop on crane rail. 6) Rated Load Marking.—Mark stoplog lifter with maximum rated load, as per requirements of ASME B30.17 and Section 51 of O. Reg. 851 Industrial Establishments. Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 7 of 31 A4.2.3 Shielding from Spray 1) Provide roof and walls over entire stoplog lifter to protect hoists from excessive ice build-up from spray in winter (see Figure 13 for typical winter conditions). 2) Roof must have positive slope for drainage to upstream and/or downstream sides of stoplog lifter. 3) Walls must extend down from roof to approximately 8 feet above deck level so as not to interfere with Damkeepers’ line-of-sight to water. 4) Design this shielding in small components weighing a maximum of 30 pounds, such that one man working from a boom truck can easily remove shielding and obtain access to hoists for maintenance purposes.

A4.2.4 Finish 1) Select coating system from one of the following three options: a) The Ontario Ministry of Transportation’s qualified products list #9.20.39 for Low VOC structural coatings (bridge paints) available online at http://applications.roadauthority.com/mpl/mpl.asp?MPIShortName=MTO+DSM; or, b) a proprietary coating, abrasion-resistant, designed so that ice does not adhere to it, with hardness and abrasion-resistant qualities no less than that of the bridge paints described above (submit test data proving this); or, c) powder-coating, abrasion-resistant, with hardness and abrasion-resistance qualities no less than that of the bridge paints described above (submit test data proving this). 2) Topcoat Colour a) High gloss black on gantry frame and outside of roof and walls b) White on underside of roof and walls to help reflect light onto dam deck 3) Colour of Primer and Intermediate Coats.—Any colour. 4) Surface Preparation.—To suit paint manufacturer’s requirements, but no less than SSPC-SP 10 Near-White Metal Blast Cleaning (NACE No. 2). 5) Film Thickness.—Maximum thicknesses that coating manufacturer allow for each product.

A4.3 Mechanical Systems A4.3.1 Hoists 1) In order to rationalize inventory of spare parts and maximize ability of one stoplog lifter to provide backups for the other, provide same make and model of hoists as on East Dam: a) Stahl model SH 4012-20 4/1 L2 KE with under-running trolley b) Capacity 5000 kg. c) Two lift speeds: 6m/min and 1 m/min. d) Two trolley speeds: 6.3m/min and 25m/min. e) Ingress protection: IP 66. f) Hoist modified by factory with 120V panel heaters fed on a separate circuit thus making hoists suitable for -40oC to +40oC operation. 2) Total lift distance same as previous stoplog lifter (see Transcrane drawing). 3) Lubricate wire rope when installing it on the drum. 4) Provide a third hoist that we will keep as a spare (ref. Section 6.4.5 of this TSOR).

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 8 of 31 5) Note: hoists are expected to be long lead-time items, estimated 14-20 weeks delivery. Schedule ordering accordingly. 6) Additional Overload Cut-Off.—Because lifting underwater, sometimes complicated by the presence of ice, does not allow Damkeepers to be certain of the load they are lifting, provide each hoists with an additional overload cut-off device set to 85% of the safe working load.

A4.3.2 Gantry Travel System 1) Use of Gantry Travel System a) The stoplog lifter is normally stored at Sluice #1 to minimize the stretch on the 600V power cable coming from the motorized cable reel. When Damkeepers need to move to other sluices to perform work, the gantry travel system will be used to move the stoplog lifter along the rails. b) The other stoplog-controlled sluice (Sluice #4) is at the other end of the dam, therefore Damkeepers frequently need the stoplog lifter to travel quickly from one end of the deck to the other (longitudinal dimensions given in Figure 5). Damkeepers will desire a higher speed of travel for efficiency in getting between the two sluices. c) Upon approach to the other sluice, Damkeepers will desire a lower speed travel in order to help line up the stoplog lifter with the sluice opening. d) To make precise positioning at the sluice, Damkeepers will perform inching/jogging motions with the gantry travel system in order to line-up the stoplog lifter with the sluice. They do this by eye based on their experience. e) Upon arrival at the new sluice, the gantry travel system will have a chance to cool off during the time the Damkeepers are manipulating stoplogs at the other sluice before the return trip to Sluice #1. The shortest time would be approximately 5 minutes, if the Damkeepers are only manipulating one stoplog. f) During their work, it could be the case that the Damkeepers will need to move the stoplog lifter slightly, about an inch or less, from one side to the other if they have difficulty hooking onto stoplogs. 2) Requirements for Gantry Travel System a) Use existing crane rails on dam deck. b) Provide driven power at both gantries, both drive systems being placed on the same side (either upstream or downstream). c) Locate all components of drive system such that they will be protected from impact from stoplogs when these are being stacked on deck. The configuration of locating the drive mechanism between back-to- back C-channels, similar to that of the East Dam’s stoplog lifter, would be one acceptable way of doing this, though there may well be others. d) Provide sheet metal cover over motor and associated components to protect them from spray, salt, etc. Cover must be removable for access to components for servicing. Cover must be strong enough to support weight of 300 lb. if a man ends up standing on it for any reason. e) Provide two-speed motor to achieve normal and low travel speeds. i) Normal travel speed: 3.81 m/min (12.5 ft/min) ii) Low travel speed: 1.14 m/min (3.75 ft/min) iii) Small variation in specified speeds (±15%) is permitted to account for exact motor rotation and standard gear sizes. f) System must operate at temperatures down to -40oC (ref. Section 4.4.2.2 of this TSOR). g) Gearmotors of gantry drive system and their starters must be capable of extensive inching/jogging action, in either direction of rotation, so that Damkeepers can achieve precise alignment of stoplog lifter with gains. Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 9 of 31 h) Mechanical horsepower rating: service factor of 1.5 based upon maximum connected motor horsepower requirements. 3) Wheels.—Single flange type, mounted on roller bearings. Provide grease tubes for the bearings. 4) Braking.—Provide mechanical braking system at either wheels or axles to ensure positive stops and hold of gantry once Damkeeper has achieved correct position over sluice. Spring applied, solenoid released. Brakes must come on after a certain time delay to allow speed to drop to zero naturally―normal stop must be gradual. 5) Interlocks.—For motion along dam deck, provide mechanism to ensure that stoplog lifter has come to a complete stop before power can be applied through drive system to make it move in opposite direction.

A4.3.3 Lubrication 1) Provide grease tubes or otherwise ensure ease of access to lubrication points without having to dismantle anything more than simply removing a cover and while working from the dam deck. 2) Provide a numbered or lettered tag at each lubrication point corresponding to lubricant schedule and numbers on maintenance check-sheets. 3) Provide self-sealing grease fittings, identical in size, make, and model.

A4.3.4 Noise Level at Dam Deck Machinery noise when operating must be maximum of 87 dB(A) to meet exposure limits specified in Canada Labour Code, Regulation Part VII - Levels of Sound for continuous 8-hour operation.

A4.4 Electrical and Controls Systems A4.4.1 General Requirements 1) All materials and equipment to be CSA certified, and installed according to manufacturer’s instructions. 2) Controls must avoid fancy electronics in favour of simple, old-fashioned, devices. 3) Variable Frequency Drives (VFDs) are NOT PERMITTED.

A4.4.2 Power Supply A4.4.2.1 For Motors 1) Take power for motors from 600V 20A power supply at the dam deck. 2) Ensure full load amperes (FLA) of all motors on stoplog lifter will be suitable for this supply. 3) A new motorized cable reel for this 600V supply will be provided to the Contractor as Government Supplied Material; install it as per manufacturer’s instructions on a new mounting table that Contractor will design and fabricate.

A4.4.2.2 For Strip Heaters 1) Provide 120V power to the strip heaters that are within the control panels. This must be on separate circuit, which is itself fed from the 120V power on dam deck. 2) Because members of the public may be present on dam deck after hours, 120V supply to strip heaters must be configured as follows: a) Provide a manual cable reel located on deck, within in a lockable enclosure that has solid walls. b) Cable coming from manual cable reel must go up a 3-inch diameter pipe no less than 10 feet up from the dam deck to a 90-degree elbow directed towards the receptacle on the stoplog lifter when the stoplog lifter is parked at Sluice #1.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 10 of 31 c) Provide a set of foldable or retractable steps on the frame of the stoplog lifter such that the Damkeepers can swing these into position, and go up a couple of steps to reach the receptacle and the cable from the manual cable reel, and in this way plug the cable into the receptacle. d) Provide sleeves and housings such that no water may enter the joint between cable and receptacle. e) Damkeepers will fold or retract steps into storage position after plugging-in the panel heater circuit and lock these in place so that members of the public cannot use them. f) Damkeepers will unplug this circuit before using stoplog lifter, and will plug it back in again after operations. g) Provide stopper ball on cable such that it cannot be pulled back down the pipe. h) Canada will provide the 120V circuit up to the location on the dam deck; the Contractor will install the cable reel and its vertical tube.

Sketch 1: Very rough sketch of configuration of 120V power supply’s connection to panel heater circuits. 3) During the early design phases, discuss this feature with the Technical Authority so that the preparatory work Canada will do is going to line up properly with the work that the Contractor will do.

A4.4.2.3 For Controls Provide a transformer within stoplog lifter’s main electrical panel to provide power for the controls.

A4.4.3 Enclosures and Panels 1) All Enclosures and Boxes.—Ingress protection: NEMA 4X, IP66 2) All Panels a) Design and test to CSA C22.2 No.14 Industrial Control Equipment. Provide CSA sticker on panel proving that it meets this standard. b) Panel builder must be certified by CSA or alternatively have final product inspected by CSA to ensure modifications made during panel building have not rendered it nonconforming. c) Provide strip heaters inside all control panels on gantry travel system and on hoist. A single thermostat must control the strip heaters’ circuit. This circuit must be a separate 120V circuit fed from the dam deck (see Section 4.4.2.2 of this TSOR). 3) Main Electrical Enclosure a) Locate main electrical enclosure on downstream side of stoplog lifter to provide a bit of a windbreak for Damkeepers. b) Provide one main electrical enclosure serving both gantries. c) Within enclosure, provide document storage compartment sized to suit a logbook, a hardcopy of Operating & Maintenance Manuals, and a complete set of as-built drawings and schematics; the intent is to keep these in stoplog lifter at all times to assist with maintenance, troubleshooting, and repair.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 11 of 31 A4.4.4 Operator’s Controls 1) Provide both push button pendant station and a radio remote. Provide a safe way of selecting between these two methods of control. 2) Enclosure protection: NEMA 4X 3) Sequence of operations is as follows: a) Resting State i) On the dam deck, Damkeepers turn off 600V power supply at disconnect switch on dam deck, then close and lock the enclosure. ii) Damkeepers manually connect120V supply to panel heaters before leavings site (in winter) with heaters’ ON/OFF control done by one single thermometer controlling all heaters (see section 4.4.2.2 of this TSOR). b) Travelling State i) At the dam deck: (1) Damkeepers unplug the feed cable for the strip heater circuit coming from the 120V manual cable reel. (2) Damkeepers turn the main disconnect ON, thus powering the stoplog lifter through the 600V power cable reel. ii) Damkeeper's pushbuttons activate solenoid to release the gantry brakes and start the gantry travel motors; the stoplog lifter travels from one sluice to another on the rails. iii) Provide high speed and low speed travel as described in Section 4.3.2 of this TSOR. c) Hoisting and Stoplog Transfer State i) Gantry travel motors are stopped, and spring-applied brakes keep the gantries from moving. ii) Hoists’ hoisting and trolley motors are activated by Damkeeper's pushbuttons to lift, lower, or move stoplogs between deck and sluice. iii) Hoists usually move together, but Damkeepers must have option to activate them separately if needed for precise stoplog positioning. d) Emergency Stop State.—Any one of the four emergency stop buttons can act as an OFF switch cuts all power to every motor on machine and all brakes come on with mechanical spring pressure allowing no use or movement.

A4.4.5 Lights 1) Use of Lights a) Damkeepers do most operations during the daytime, when lights are not needed. However, sometimes they do operations at dusk or in darkness. b) Provide Stoplog lifter with two sets of lights: c) “operating lights” (illuminating deck and down the sluice opening), and d) “headpond lights” (shining into headpond to allow Damkeepers to check for debris upstream before operating). 2) General Requirements for All Lights a) Ingress protection: IP 66 b) Impact protection: IK 10

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 12 of 31 c) Protect all light bulbs with wire guards d) Locate all lights on uppermost part of gantry frame e) Provide lights with LED bulbs in a warm colour, approximating what would come from old incandescent bulbs f) Provide and projector-style heads 3) Details of Operating Lights a) Locate ON/OFF light switches within main electrical enclosure, one switch controlling all operating lights. b) Operating lights consist of 8 lights: i) 2 lights mounted under roof of stoplog lifter, directly over sluice openings, and shining down the gains illuminating the stoplogs (one on each gantry); (1) Very narrow beam directed down each gain (2) Select lumens to achieve 150 lx at a depth of 2 m below deck ii) 4 lights mounted under roof of stoplog lifter, shining on deck between the gantries providing illumination on deck under the stoplog lifter (two on each gantry) (1) Wide beam configuration directed under stoplog lifter and slightly upstream and downstream of the crane rails. (2) Select lumens to achieve 30 lux of general illumination at deck level below stoplog lifter. iii) 2 lights mounted outside of roof of stoplog lifter, shining on crane rails ahead and behind the stoplog lifter to illuminate the deck around the stoplog lifter (one on each gantry). (1) Very wide beam configuration illuminating deck at the next sluice over from the stoplog lifter, and upstream and downstream of the crane rails for some distance (2) Select lumens to achieve 15 lux on the deck over at the farthest end of the next sluice from the stoplog lifter. 4) Details of Headpond Lights a) Locate ON/OFF switch within main electrical enclosure, with one switch controlling all headpond lights. b) Provide 2 lights (one on each gantry) mounted outside the roof and walls of the stoplog lifter on the upstream side. c) Very wide beam configuration to illuminate the water of the headpond area from channel wall to channel wall and as far as the abutments of the Bridge, about 90m upstream of the dam. d) Select lumens to achieve about 10 lux on water at bridge abutments. 5) Spares.—Provide spare parts for lighting system as indicated in Section 6.4.5 of this TSOR.

A4.4.6 Emergency Stop 1) Provide four (4) emergency stop buttons located one at each corner of stoplog lifting machine. 2) Emergency stops must stop gantry travel, hoisting, and hoist trolley motors all with push of any one of those four buttons. 3) Ingress protection: NEMA 6P / IP 66. 4) Impact protection: IK 10.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 13 of 31 A5. DELIVERY, INSTALLATION, AND SET-TO-WORK A5.1 Delivery to Dam Site A5.1.1 Stoplog Lifter 1) Provide all trucks, cranes, access equipment, and other equipment necessary for packaging, shipping, delivery, and installation. 2) Provide blocking and covers to protect parts during transportation. 3) See Figures 15-18 for potential access locations for delivery crane and truck. 4) Technical Authority will inspect stoplog lifter immediately upon arrival at dam site. If damage is found, Contractor must make all required repairs. 5) For all installation work, follow accepted Site-Specific Hazard Assessment and Health and Safety Plan (HASSHSP) (ref. Section 6.4.9 of this TSOR). 6) Protect surrounding private and public property from damage during installation work. Repair, restore, or replace all damage to surroundings due to Work. 7) Provide services of Professional Engineer licensed to practice in Ontario to supervise delivery and installation of stoplog lifter and SAT, with full authority over quality control. 8) Provide Certificate and Pre-Start Health and Safety Review signed by Professional Engineer licensed to practice in Ontario, saying that stoplog lifter conforms to requirements of O. Reg. 851 Industrial Establishments. Submit this as part of results of Site Acceptance Tests.

A5.1.2 Operation & Maintenance Manuals 1) Description of requirements for manual: see Section 6.4.10 of this TSOR. 2) Provide hardcopy of manual and drawings in storage pocket within interior of electrical enclosure.

A5.1.3 Training 1) Trainees will be Damkeepers and maintenance personnel, all of whom are English-speaking. 2) Technical Authority will provide names of trainees 3 weeks before delivery date. a) Informal Training.—Allow students to observe installation and commissioning work and answer questions as these arise. b) Formal training i) Provide minimum 8-hour formal training session in machine operation during Damkeepers’ working hours after commissioning is complete. ii) Training must cover all procedures that Damkeepers would be expected to do themselves, as listed and described in the Operating & Maintenance Manual. iii) After each procedure has been demonstrated, allow each trainee a chance to practice it. 3) Submit a Training Plan describing curriculum as part of Critical Design Package (ref. Section 6.4.4 of this TSOR). Execute training on site as described in accepted Training Plan. 4) All training must be completed before Technical Authority will accept stoplog lifter.

A5.2 Deliveries to Ottawa Shops 1) Deliver spare parts and maintenance materials to the Ottawa Shops, located at 950 Ages Drive in Ottawa. 2) Delivery must take place during Damkeepers’ working hours, which are 8 AM - 4 PM, Monday through Friday. Coordinate exact date and time with Technical Authority no less than one week before expected delivery date.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 14 of 31 3) Items delivered must be in good condition and match in type and quantity those in approved list.

A5.3 Deliveries to Technical Authority Provide electronic copy of Operation and Maintenance Manual in PDF format using Contractor’s FTP site.

A6. ADMINISTRATIVE REQUIREMENTS A6.1 Project Manager 1) Appoint a Project Manager to plan, direct, control, and make decisions for the Contractor and who must be the main point of contact between the Contractor and the Technical Authority. 2) Submit the Project Manager’s name and contact information no later than 7 calendar days after Award. 3) Provide an FTP site for the exchange of documents that are too large for the email system.

A6.2 Meetings 1) The Technical Authority will take and distribute Minutes of all meetings. 2) Kick-off Meeting.—A kick-off meeting will be scheduled within 5 working days of contract award. The discussion will include, but not necessarily be limited to, a review of the project requirements and the Contractor’s schedule and identification of items on critical path. This meeting will be held at Rideau Falls Dam. 3) Design Review Meetings.—To allow PWGSC to ask questions related to the Consultant’s engineering deliverables (Preliminary Design Package and Critical Design Package). These meetings will be face-to-face to facilitate going over drawings and will be held at the Rideau Falls Dam. They will occur one week after submission of the respective Design Packages. Official written response on the submittal from Technical Authority will follow 5 working days after meeting. 4) Progress Review Meetings.—Will be held as mutually agreed between the Contracting Authority, the Technical Authority, and the Contractor to discuss other issues as these arise. The Technical Authority will visit the Contractor’s shop at about the 33% and 66% fabrication stages, and may elect to be present during the Factory Acceptance Testing (FAT).

A6.3 Warranty Warrant all products delivered for minimum two (2) years. See the contract for details of warranty.

A6.4 Schedule of Written Deliverables A6.4.1 Due Dates

Weeks after Project Phase Description of Written Deliverable contract Award Initial Submittals Project Schedule 3 Inspection and Test Plan Design Preliminary Design Package 6 Critical Design Package 10 Fabrication Monthly Progress Reports 11-34 Results of Factory Acceptance Test Delivery and Set-to-Work Installation Plan 36 Health and Safety Submittals for Work at Dam Site Operation and Maintenance Manuals – Draft Operation and Maintenance Manuals – Final 39 DELIVERY OF STOPLOG LIFTER 40 Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 15 of 31

Weeks after Project Phase Description of Written Deliverable contract Award Results of Site Acceptance Test 42

A6.4.2 Project Schedule 1) Description.—Final project schedule must be a revision to the schedule submitted with the bid, include the following milestones: a) Submission of all written deliverables. b) Preliminary Design Review Meeting and Critical Design Review Meetings c) Fabrication Milestones.—Note that Technical Authority will make shop visits at approximately 33% and 66% fabrication completion to see progress of work, so identify these points in the schedule. d) Factory Acceptance Testing (FAT).—Do these tests when fabrication is approximately 99% complete. Technical Authority may elect to be present. e) Operating & Maintenance Manuals —Delivery of Draft and Final versions f) Work at Dam Site.—Includes delivery, installation and set-to-work; Site Acceptance Testing; and Training. NOTE: For water control reasons, the delivery of the stoplog lifter must take place outside of Ice Flush and Freshet (i.e. must not take place in the months of January through the end of May). 2) Schedule must show crane being delivered to the dam within the time indicated in Section 6.4.1 of this TSOR.

A6.4.3 Inspection and Test Plan (ITP) 1) Roles and Responsibilities a) Contractor is responsible for quality control which must include, but is not limited to: coordinating work of suppliers and subcontractors, fabrication quality control procedures, factory acceptance tests (FAT), and site acceptance tests (SAT) along with acceptance criteria for each test. b) Technical Authority may elect to make some checks and 3rd party tests for quality assurance purposes on a random sampling basis; provide access to Work wherever it is located and cooperate in this process whenever it occurs. Technical Authority may elect to witness any phase of Contractor’s quality control procedures or may send a representative to do so on his behalf. c) Until acceptance by Canada, correct all defects and irregularities found by Technical Authority or by 3rd party inspectors, whether these are result of poor workmanship, use of defective products, or damage. Replace or re execute Work to meet quality standards. d) In cases of dispute, decisions regarding standard or quality of Work rest solely with Technical Authority, whose decision is final. 2) Description a) The Contractor must prepare and implement an Inspection and Test Plan (ITP) for the work. b) ITP must include evidence the Contractor is in contact with the hoist manufacturer, has received all technical information required to install hoists, and has the name and contact information of a manufacturer’s representative who will be able to provide advice and assistance in case of problems. c) Describe procedures to be used for welding inspection, stress relieving, dimensional controls, coating application, electrical testing, and all other tests Contractor will do to ensure stoplog lifter conforms to the requirements of this TSOR.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 16 of 31 d) Minimum Requirements for Factory Acceptance Testing (FAT).—FAT must include: i) Check overall workmanship, surfaces free of blemishes and sharp edges, coating are uniform and free of defects. ii) Check dimensions against drawings and ensure no distortion in gantry. iii) Ensure dissimilar metals have been electrically isolated. iv) Welding inspection by independent 3rd party welding inspectors with certified by Canadian Welding Bureau, 100% visual weld inspection and NDT if welding inspection believes this to be necessary for specific welds. (a) Submit name and qualifications of welding inspector in ITP v) Test operation of hoist controls with all controllers vi) Test operation of gantry drive controls with all controllers vii) Test operation of lights viii) Test all limit switches ix) Test emergency stop buttons x) Load test (1) Perform static and dynamic load testing to requirements of ASME B30.17 or other appropriate standards (specify which standard used and provide copy of original text), along with other proof tests as determined by Professional Engineer designing stoplog lifters. (2) Provide all required weights and load measuring devices. xi) Install supplementary load limiters (the ones to be set at 85% of safe working load) after load test. e) Minimum Requirements for Site Acceptance Testing (SAT) i) SAT consists of activities Contractor performs on-site to prove that as-installed stoplog lifter meets the requirements of this TSOR. ii) SAT must take place during Damkeepers’ working hours which are 8 AM - 4 PM, Monday through Friday. iii) SAT may take place immediately after delivery, if this is convenient to the Contractor, or at a separate visit which may be no more than one week after delivery iv) SAT must include at minimum the following: (1) Check that minimum clearance requirement from all dam appurtenances is met (ref. Section 4.2.2 of this TSOR). (2) Check that shields protecting hoists from spray are in place. (3) Perform load testing if not already done as part of FAT. Install supplementary load limiters (the ones to be set at 85% of safe working load) after load test. (4) Demonstrate operation of hoist controls with all controllers (5) Demonstrate correct operation of gantry drive controls with all controllers (6) Demonstrate operation of lights (7) Demonstration functioning of all limit switches (8) Demonstrate functioning of emergency stop buttons (9) Demonstrate operation for removing and placing a log in a sluice. v) The Technical Authority (or designate) will be the official witness to SAT. Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 17 of 31 vi) Allow Damkeepers to observe all parts of SAT, as this forms the “informal training” portion of their training (see Section 5.1.3 of this TSOR). vii) Contractor must make all repairs and adjustments found to be required to ensure that the stoplog lifter performs as required. viii) Upon successful completion of SAT, the Contractor must leave the stoplog lifter in a fully ready condition (i.e., no further set-up or configuration is necessary; the equipment can be deployed as- is).

A6.4.4 Preliminary Design Package 1) General Information.—Submit the following: a) Contractor’s understanding of technical and performance requirements for stoplog lifters; b) Contractor’s proposed adjustments to these requirements, if any, for Technical Authority consideration; and, c) measurements taken on West Dam deck, showing crane rail profile, gauge, and distance from crane rails to all appurtenances that may interfere with stoplog lifter. 2) Structural.—Submit the following: a) drawings (expected to be at about 50% complete) showing overall configuration of stoplog lifter and upon which Technical Authority can indicate preferred location of fall-arrest anchor points and horizontal lifeline; b) proposed mounting location for lights; and, c) proposed surface preparation & coating system. 3) Mechanical.—Submit the following: a) confirmation of make and model of East Dam’s wire rope hoists―intent is to have Contractor order these early in the fabrication process, as these are long lead-time items; b) measured speed of travel of East Dam stoplog lifter and estimated speed of travel of new West Dam stoplog lifter; c) proposed equipment and configuration of gantry base showing travel mechanism and how it will be protected from impact with swinging stoplogs and showing that wheels and their bearings can be accessed for servicing; d) drawings showing proposed method for safeguarding and machine guarding; e) drawings showing proposed scheme for protecting hoists from spray; and, f) proposed lifeline products. 4) Electrical and Controls.—Submit the following: a) product data for proposed lights; b) control sequence for each possible motion of gantry and hoist: i) describe what happens from when Damkeeper pushes button to when motion starts or is stopped, e.g. which contact opens or closes, which circuit is energized or de-energized, which brakes are engaging or disengaging, etc.; ii) describe how safety interlocks are achieved; and, iii) describe how normal and emergency stopping is going to be achieved.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 18 of 31 A6.4.5 Critical Design Package 1) Spare Parts List.—Submit the proposed list of spare parts, maintenance materials, and special tools & test equipment. Technical Authority will consider list, and inform Contractor of final list of spares to be delivered. Spare parts list must include at minimum the following: a) Hoist System i) 1 complete spare hoist ii) 2 rope guides iii) 1 supplementary overload device iv) 2 sets of wire rope per hoist, pre-lubricated, protected for storage in a high-humidity environment, with end terminations such that they are ready to install on hoists. v) 1 spare radio remote controller b) Gantry Drive System.—1 spare gantry drive mechanism (motor, gearbox, etc.) c) Gantry Lights i) 6 spare light bulbs ii) 1 spare luminaire body 2) Structural.—Drawings of gantry frames with details at least 90% complete 3) Mechanical a) final design of machine guarding b) product data for all components selected 4) Electrical and Controls.—Submit electrical schematics for all systems and product data for all components selected, including IP ratings 5) Training Plan.—Submit a “curriculum” for Damkeeper’s training.

A6.4.6 Monthly Progress Reports 1) Every month during fabrication phase, submit report on work done in that reporting period. 2) Submit product data for all components installed 3) Submit mill test certificates for steel. 4) Submit results of all fabrication tests demonstrating that tested systems met acceptance criteria in Inspection and Test Plan (e.g. CSA certifications, welding inspection, etc.).

A6.4.7 Results of FAT 1) Results must demonstrate that tested components and systems met acceptance criteria. 2) Technical Authority may choose to witness FAT; therefore, provide 14 days advance notice of date of FAT so that government travel arrangements to Contractor’s facility can be made.

A6.4.8 Installation Plan 1) Describe packaging, shipping, unpacking, and on-site assembly. 2) Discuss traffic control procedures if road will have to be closed or partially closed for delivery, and provide copies of all permits obtained from local municipalities for this. 3) Describe equipment that Contractor will use to deliver and set up the stoplog lifter.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 19 of 31 4) Contractor may access the dam through either left (west) or right (east) abutments. See Figures 15 through 18 for details of access areas at those two abutments. Note that permission from National Capital Commission (NCC) is required for access through Green Island. 5) Indicate on a map of site where truck and crane will park for delivery of stoplog lifter at dam. 6) Provide name of Professional Engineer who will supervise this work and provide Pre-Start Health and Safety Review to requirements of Section 7 of O. Reg. 851 Industrial Establishments and written report to requirements of O. Reg. 528/00 which amends O. Reg. 851

A6.4.9 Health & Safety Submittals for Work at Dam Site 1) Purpose.—Canada requires proof of Contractor compliance with regulatory requirements whenever a Contractor is working at a Federal Government facility. 2) Responsibility a) When on the dam site, the Contractor is responsible for health and safety of own personnel and all sub-contractors and must comply with the requirements of the Province of Ontario. b) Provide Supervisor at the dam site, who is an employee of the Contractor, and who will be responsible for the site whenever sub-contractors are working at the dam. Supervisor must have the authority to stop Work when, at Supervisor's discretion, it is necessary or advisable to do so for reasons of health or safety. c) Contracting Authority and Technical Authority may stop Work for health and safety considerations. d) Immediately address health and safety non-compliance issues, whether identified by authority having jurisdiction, or by Contracting Authority, or by Technical Authority. e) Submit to the Technical Authority, within twenty-four hours of occurrence, copies of all reports or directions issued by Federal or Provincial health and safety inspector, and reports of all accidents, incidents, and/or near-misses that occur during the term of the Contract. f) If unforeseen or peculiar safety-related conditions arise during performance of Work, follow procedures in place for Employee's Right to Refuse Work in accordance with Acts and Regulations of Ontario and advise Contracting Authority and Technical Authority both verbally and in writing. 3) Existing Known Site Conditions.—Currently known hazards and conditions at the dam site to which Contractor may be exposed include, but are not necessarily limited to, the following: a) Weather hazards (extreme hot, cold, precipitation) b) Trip-and-fall hazards such as uneven ground and slippery surfaces c) Pinch hazards d) Electrical hazards e) Contact with oil and grease f) Working at heights from elevated work platforms (e.g. to install hoists) g) Working with lifting equipment (cranes) h) Working over water 4) Description.—Submit the following: a) Company information (also submit for those sub-contractors who will be working at the dam site): i) Clearance Certificate from the Workplace Safety Insurance Board of Ontario. ii) Company’s Health & Safety Policy Statement meeting the requirement of the Provincial Occupational Health and Safety Act.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 20 of 31 iii) Company’s Occupational Health and Safety Program meeting the requirements of the Provincial Occupational Health and Safety Act. b) Names & Training Records.—For all members of Contractor’s team (both staff and sub- contractors) who will be on site, submit names of all persons who will be present on site along with proof they have received appropriate health and safety training for Work, which includes at minimum WHMIS, Working at Heights, First Aid, and CPR. c) Site Specific Hazard Assessment and Health and Safety Plan (SSHAHSP) i) Develop written SSHAHSP based on hazard assessment before starting Work at the dam. ii) Implement and enforce requirements of SSHAHSP whenever work takes place at the dam site. iii) Provide name of person(s) responsible for ensuring adherence to SSHAHSP whilst at the dam sites. iv) Technical Authority will review. Revise and re-submit as often as required. Technical Authority’s review of SSHAHSP should not be construed as approval and does not reduce the Contractor's overall responsibility. v) SSHAHSP must include the following: (1) Part 1 - Safety Hazard Assessment and Mitigation Measures.—Consider the operations to be performed at the dam site and identify safety hazards. Currently known hazards include, but are not necessarily limited to, the ones listed in Section A5.7.2 Existing Known Site Conditions, as well as all other hazards Contractor foresees arising during Work. For each safety hazard identified, describe measures and controls that will be used to protect employees and subcontract personnel and for ensuring compliance with Federal, Provincial, and Municipal laws and regulations. Mitigation measures may include a range of engineering controls, work practices, and personal protective equipment. (2) Part 2 - Safety Briefing Agenda.—Contractor must provide employees and sub-contractors with a short safety briefing before starting work on site. All persons must sign off as having received this briefing before starting Work; submit a copy of briefing agenda beforehand and signed attendance list afterwards. (3) Part 3 - Emergency Contacts.—This is an organization chart for Work on site showing specific chain of command and responsibilities in case of emergencies. This must include all sub-contractors. Include name of nearest health facility, a map showing its location, and how it will be contacted during an emergency. (4) Part 4 - Contingency and Emergency Response Plan.—Describe standard operating procedures specific to the project site to be implemented during emergencies.

A6.4.10 Operation & Maintenance Manual 1) Intended audience for this document are present and future Damkeepers, over working life of stoplog lifter. When writing, do not assume these Damkeepers have any formal technical training. 2) For tasks requiring certified trades or 3rd parties, direct reader to contact a specific trade. 3) Contents a) Normal and Emergency Operations, including all blank pre-operation “circle-check” form for Damkeepers to fill out each day before operating stoplog lifter. b) Maintenance Procedures i) Lock-out tag-out procedure(s) to be used to render stoplog lifter safe for maintenance work to all motors.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 21 of 31 ii) Recommend scope for Pre-Operation, Frequent, and Periodic inspection and maintenance service, including blank inspection forms for each type of inspection iii) Lubrication chart showing location of lubrication points and what type of lubricant goes where. iv) Provide list of materials that will be needed for ongoing maintenance. Include minimum 3 alternative product names for these materials, along with contact information for local suppliers. c) Troubleshooting Procedures for conditions likely to be encountered by Damkeepers d) As-Built Drawings and Schematics.—Include all drawings, schematics, documents, parts lists, change notices, and other related documentation necessary to completely define system for use in maintenance and troubleshooting both by Damkeepers and by licensed trades (e.g. electricians or controls specialists.) Clearly indicate information about connection bolt type, strength, and torque on the structural drawings. e) OEM Manuals for Commercial Off-the-Shelf Components.—Annotate OEM information where required to reflect specific equipment, nomenclature, part numbers, modifications, and maintenance procedures suitable to stoplog lifter as designed and fabricated. 4) Review and Acceptance Criteria.—Manuals must be complete in all its parts, organized appropriately to serve its purposes, correct in matters of fact and documentation, and edited for proper grammar and basic uniformities of style and usage. Technical Authority will require revision of unclear wording or poor grammar. Revise and re-submit as often as necessary to achieve acceptable deliverables.

A6.4.11 Results of SAT 1) Results must demonstrate that tested components and systems met acceptance criteria. 2) Technical Authority will witness SAT.

A7. IMAGES

Figure 1: Location of Rideau Falls Dams within the City of Ottawa

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 22 of 31

Figure 2: Rideau Falls, looking upstream. The East Dam is on the left, the West Dam is on the right.

Figure 3: Detail location of Rideau Falls West Dam

Figure 4: West Dam looking downstream. Note old stoplog lifter at left.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 23 of 31

Figure 5: Schematic of West Dam looking downstream. Dimensions are in millimetres.

Figure 6: Schematic cross-section of West Dam. Dimensions in millimetres except where noted.

Figure 7: West Dam looking upstream, with old stoplog lifter in place.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 24 of 31

Figure 8: Old stoplog lifter on West Dam.

Figure 9: Old cable reel for West Dam's old stoplog lifter. (Conductix, NEMA 4, 150 ft of 10 AWG SOOW cable)

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 25 of 31

Figure 10: West Dam's spreader beam.

Figure 11: Side view of lifting beam. Lifting lugs are shown in red on top. Dimensions are in feet and inches.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 26 of 31

Figure 12: Stoplog storage on the operational deck of West Dam, immediately downstream of the sluice opening.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 27 of 31

Figure 13: Old stoplog lifter on West Dam showing ice build-up.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 28 of 31

Figure 14: Stoplogs in gain on West Dam (typical).

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 29 of 31

The building near this abutment is the heating plant for the National Research Council building. The delivery crane can park outside the heating plant building, close to Sluice #1, in the area shown in green. Outriggers can go in the trees, but keep away from the areas marked in red. The forbidden red area extends back 18 feet from the dam walls, and 3 feet out past the painted markings for car parking in front of the building, as there Figure 15: Left (west) approach. Crane parking for access adjacent to Sluice #1. is a basement area under that parking slab.

Figure 16: Left (west) approach to West Dam at ground level.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 30 of 31

The National Capital Commission (NCC) manages the park near this abutment, and Contractor must obtain permission from them for access. The delivery crane can park close to Sluice #4, in the area shown in green. Outriggers must avoid the areas marked in red, Figure 17: Right (east) approach. Crane parking for access adjacent to Sluice #4. which extends back 18 feet from the walls.

Figure 18: Right (east) approach to West Dam at ground level.

Dams and Water Management Engineering 21 August 2020 ANNEX A - TECHNICAL STATEMENT OF REQUIREMENTS Supply & Deliver New Stoplog Lifter for Rideau Falls West Dam Page 31 of 31

Figure 19: East Dam's stoplog lifter, for reference.

Dams and Water Management Engineering 21 August 2020